GENERAL NOTES :
1. Refer to 400V Load Center and Motor Control Center Load Schedule for details
(number and rating) of outgoing feeders.
H H
2. Breakers shall be operated electrically or manually.Breaker status (close / test /
available) shall be monitored and controlled by DCS.
3. Refer to 400V Schematic Diagrams for details.
4. An Auto / Manual Switch shall be fixed on the switch board.The position of the
switch is monitored by DCS as well as transfer device.
5. In manual operating mode , the incomings and tie feeder breakers shall have DCS
initiated commands executed via transfer device (PLC). DCS shall monitor status of
breaker (close / test / available).
6. For bus transfer in auto operating mode, transfer device (PLC) shall control the
operation of incomings and tie feeder breakers. In manual operating mode Local
and DCS shall control the operation of breakers via transfer device (PLC). Live bus
transfer shall be make-before-break in both operating modes, for detail operation
G philosophy refer Technical Specification for 400V Load Centers and MCC. G

REFERENCES :
DQR/00/K/001b---004/SD/001 MAIN SINGE LINE DIAGRAM
DQR/00/K/BF----EP24/ES/101 ... 108 400V SCHEMATIC DIAGRAMS
F DQR/00/K/BF----EP24/ES/002 TECHNICAL SPECIFICATION FOR 400V LOAD F
CENTERS AND MCC
DQR/00/K/BF----EP24/EL/001 400V LOAD CENTER AND MOTOR CONTROL
CENTER LOAD SCHEDULE

E E

D D

Revision History

00 18.09.2017 C.B. O.O. T.O. H.S. Issued for Use

B 30.06.2017 C.B. O.O. T.O. H.S. Issued for Review

Rev. Revision Date BY CHK EGS PEM Brief Description

Description Current Version

PROJECT
C C
DHI QAR COMBINED CYCLE
POWER PLANT PROJECT
NASIRIYAH, IRAQ
OWNER

M
E

CONTRACTOR NOMINATED SUB CONTRACTOR


GE POWER

B B

MOE Contract Number :

CONTRACT NO: 1
Cross Checked
Department Name Date Signature

Replaces Responsible Dept. Document Type Project Document Code

ELECTRICAL DRAWING DQR/00/K/BF----EP24/SD/001


BY CHK EGS PEM Format

C.B. O.O. T.O. H.S. A3


Nominated Sub Contractor Document Title Document Status Scale :
A A
ONE LINE PROTECTION AND Issued for Use NTS
METERING DIAGRAM FOR 400V Identification Number

SIZE A3 (420x297 mm)


SWITCHGEARS WITH DOUBLE IQ360-000-E5-BFA-00001
BUS BAR AND TWO XFMR Rev. Date Lang. Sheet

00 18.09.2017 EN 1/1
INCOMINGS