PROJECTPIM
What Is The Difference Between Lead &
Lag | Simple Example
July 21, 2021 / Project Management / Leave a Comment
Lead and lag are the terms used to define a relationship between the
tasks on a project. Both are scheduling terms used with relationships like
Finish to Start, Start to Start. We will see below simple examples.You may be interested in Download & Install Primavera P6.
Quick Navigation [show]
Lead
A Lead is the amount of time that successor activity is ahead of its
predecessor activity. For example, in a construction project, it is maybe
desired to start working on landscaping four weeks before the furniture
purchase. This will be shown on a scheduling diagram like below.
——
Lead FS — Relation Lead
This type of interlinked activity sequence is known as the finish to start
and is the most often used type of sequence in project scheduling. In
simple words, we can say that the lead time is four weeks.This type of interlinked activity sequence is known as the finish to start
and is the most often used type of sequence in project scheduling. In
simple words, we can say that the lead time is 4 weeks.
In this scenario, these 5 days’ t be before the design finishes when the
development starts are called lead time.
Example for Lead
Let’s take the example of a project involving software development. We
might want to start with the programming of the hardware screen where
the software will run as the programming itself is dependent on technical
design, including the dimensions of the screen. So both activities can
definitely not start simultaneously. When we go deep into the activity
plan, we know that technical design will take 20 days, but after 15 days,
most activities are in the final stages. Most importantly, the information
required for programming is concluded so we can start programming
from thereon. Hence the overall duration of a project will be reduced.
Lag
Opposite to Lead, Lag is the amount of time successor activity is delayed
from its predecessor activity.
For example, the time duration for the first activity is 2 days, and then
there is a gap of 3 days before you start the next activity, so you can say
that there is a lag of 3 days. It will be shown on the scheduling diagram
as Finish to Start.
Let us look at the below snip, here we have to wait to start Paintwork after
Plastering is finished. This wait is mandatory as Platser will take time to
set or cure.Ta
/
Lo Lt
Lag FS+7 Days Lag
Similarly, we can also have a case like you may start editing a book after
10 days you begin writing it. It will be shown as a start-to-start sequence
as below.
Similarly, we can also have a case like you may start editing a book after
10 days you begin writing it. It will be shown as a start-to-start sequence
as below.
Example for Lag
Let’s consider another example from a construction project. It is only
logical to first prepare concrete and gets the foundation work completed.
Only then can we start working on the rest of the construction activities.
But there is one problem, as the foundation requires curing concrete for
at least 3 days, the remaining work can't be initiated. These 3 days’ time
can be termed as lag, which can’t be avoided. So it is important to
understand the logical dependencies of activities for precise project
planning.
Wrap Up
Lead and lag both are important concepts and must be considered in
project schedule development. Lead is the amount of time that successor
activity is ahead of its predecessor activity. Whereas Lag is the amount of
time successor activity is delayed from its predecessor activity.