Introduction
This method statement outlines the procedure for conducting megger testing on power
cables and branch circuit wiring.
Megger testing is an important step in ensuring the electrical integrity and safety of wiring
systems. This document guides equipment, preparation, testing procedures, and reporting.

A. Megger Test Equipment

1. Megger Instrument Calibration


• The megger instrument used for testing must have valid calibration to
ensure accurate results.
2. Megger Testers
o Two types of megger testers will be used:
• Megger with a range of 500V for wire testing.
• Megger with a range of 1000V for cable testing.

B. Pre-Test Preparation
1. Check Lead Integrity
• Ensure that the leads used for connecting the megger to the circuit are free from
faults. Verify electrical continuity by touching the free ends of the leads together
while the megger button is pressed ON to confirm zero resistance.

Business Centre, Sharjah


+971 563 444 875
Publishing City Free Zone, Sharjah,
info@PlanningEngineer.Net https://planningengineer.net/
Page 1 of 4
Planning Engineer FZE Project Management & Planning Services and Training
‫بالنينغ إنجينير م م ح‬ ‫خدمات وتدريب إدارة المشروعات والتخطيط‬

2. Inspect PVC Adapters


• Verify the presence of PVC adapters for cables and male adapters for all PVC
conduits terminating in the panel board.
3. Verify Wiring Dressing
• Confirm that the dressing for all wires in the panel boards is complete and tidy.
4. Confirm All Connections
• Ensure that all electrical connections are completed before proceeding with
testing.

C. Electrical Continuity Test


1. Test Setup
• Connect the free megger test probes to any two conductors that need to be
tested.
2. Conduct Test
• With all appliances connected or the two ends of the conductors shorted, and all
switches turned ON, the megger reading should be zero. If the reading shows
infinity, it indicates an open circuit, which needs to be traced and rectified.
3. Cable Testing
• For cables, shorten the extreme ends of any two phases and conduct the test.
The reading should be zero. If the megger reads infinity or a value in mega ohms,
there is a fault in the cable that requires rectification. Repeat this procedure for
the other three conductors of the cable.

D. Short Circuit Test / Insulation Resistance Test


For Wires
1. Test Setup
• Use a megger with a 500V range.
• Conduct tests between:
• Phase and neutral.
• Phase and earth.
• Neutral and earth.
2. Conduct the test with the other ends of the circuit conductor open. The value
should be infinity for all tests. If the value is zero, it indicates a short circuit or
damaged wire insulation, necessitating replacement.

Business Centre, Sharjah


+971 563 444 875
Publishing City Free Zone, Sharjah,
info@PlanningEngineer.Net https://planningengineer.net/
Page 2 of 4
Planning Engineer FZE Project Management & Planning Services and Training
‫بالنينغ إنجينير م م ح‬ ‫خدمات وتدريب إدارة المشروعات والتخطيط‬

For Cables
1. Test Setup
• Use a megger with a 1000V range.
• Keep both ends of the cable open.
• Conduct tests between phases and neutrals as follows:
• R to Y
• R to B
• Y to B
• R to N
• Y to N
• B to N
2. All these readings should be infinite. Any other value suggests a fault in the
cable cores/phases that requires rectification.

E. Reporting
The test results must be recorded in a specified format for reference and record-keeping by
the engineers.
This format should be submitted to the consultant for approval before conducting the
megger testing operation. Proper documentation ensures transparency and accountability
in the testing process.

Here is the sequence of Testing and Commissioning in the construction projects.


Business Centre, Sharjah
+971 563 444 875
Publishing City Free Zone, Sharjah,
info@PlanningEngineer.Net https://planningengineer.net/
Page 3 of 4
Planning Engineer FZE Project Management & Planning Services and Training
‫بالنينغ إنجينير م م ح‬ ‫خدمات وتدريب إدارة المشروعات والتخطيط‬

Article Link: https://planningengineer.net/method-statement-megger-testing/


---------------
Useful links:
Join our email Newsletter, we send useful free content regularly:
https://planningengineer.net/newsletter/
Our Services https://planningengineer.net/our-services/
Our Courses: https://planningengineer.net/lp-courses/
Free Arabic Basic Course Playlist:
https://youtube.com/playlist?list=PL7qHhNmknL6F5IOHAsNnPVMt1X-fvYe3J
---------------
Keep in Touch:
WhatsApp: +201277767728
Email: Info@PlanningEngineer.Net
English YouTube Channel: https://www.youtube.com/c/PlanningengineerNet/videos
Arabic YouTube Channel: https://www.youtube.com/@planningengineer3906
Linked in: https://www.linkedin.com/company/planning-engineer-est/
Facebook Page: https://www.facebook.com/PlanningEngineerDotNet
Facebook Group: https://www.facebook.com/groups/1138400132963230
Twitter: https://twitter.com/PlanningEEst
Instagram: https://www.instagram.com/planningengineerest/
TikTok: https://www.tiktok.com/@planningengineerest
---------------

Business Centre, Sharjah


+971 563 444 875
Publishing City Free Zone, Sharjah,
info@PlanningEngineer.Net https://planningengineer.net/
Page 4 of 4

You might also like