Brian Smith, network administrator of Advanced Energy Technologies (AET), has been
tasked with implementing a large data center to a new office location. AET operates in the
petroleum industry, where there is fierce competition, therefore careful planning is necessary.
AET is one of five national software companies that supply an accounting and business
management suite to oil jobbers and gasoline distributors. Thanks to AET's large data center,
clients can access the entire suite of application software remotely. One of AET's primary
Currently located in the center of downtown, the AET data center occupies the second
floor of a remodeled bank building. The data center move project was approved by the AET
directors to save operational costs and enhance the current IT infrastructure. The project team
thinks that relocating to the newly constructed one-story building in the industrial complex will
be advantageous in the long run since it will put AET in accordance with current construction
regulations and provide opportunities for growth and development in the future.
Project Description.
Following some initial deliberations with AET directors from every functional department, Brian
was officially designated as the data center migration project manager. The project's high-level
The project will involve many teams. Our facilities staff will be primarily responsible for
shipping and inventory management. Our Operations/Systems team will oversee the hardware
migration and logistics. Our Systems and Applications team will handle regulatory functions
related to software and compliance testing, while the Operations/Telecom division will handle
crew resource management, including the installation of workstation phones. Our Customer
Also, the project team will deploy the test servers over seven days once the power check and
switchover meetings are finished. Before the network is taken offline, the test servers will verify
that all the main network features are operational and serve as a safety measure. Following the
test server installation and power check, Brian will oversee a primary system check with senior
management and call a follow-up meeting to determine the formal date of the network
relocation. All network components can be moved by Brian to the new data center on the
designated day. Expecting the move to finish in two days, he is willing to work on the weekends
if needed.
Based on the feedback and input from various stakeholders and teams involved with the
project team will create WBS table below for the data center migration (Su, Y. (2022)).
WBS-Table
Task Time
Nr. Task Name Start Date Finish Date (days) Predecessors
1 Launch meeting 3/4/2024 3/4/2024 1 None
2 Hire Contractors 3/5/2024 3/11/2024 7 1
3 Order ventilation system 3/5/2024 3/5/2024 1 1
4 Order racks 3/5/2024 3/5/2024 1 1
5 Order power supplies & cables 3/5/2024 3/5/2024 1 1
6 Network design 3/12/2024 3/25/2024 14 1
7 Data center construction 3/26/2024 4/14/2024 20 2,3
8 Install racks 4/15/2024 5/5/2024 21 4
9 Install ventilation system 4/15/2024 4/21/2024 7 3
10 City inspection 5/6/2024 5/7/2024 2 8,9
11 Install power supplies 5/8/2024 5/12/2024 5 10
12 Install Cables 5/13/2024 5/19/2024 7 10
13 Initiate power check 5/20/2024 5/20/2024 1 7,11,12
14 All unit's approval 5/21/2024 5/25/2024 5 13
15 Switchover meetings 5/26/2024 6/1/2024 7 14
16 Install test servers 6/2/2024 6/8/2024 7 15
17 Safety check 6/9/2024 6/10/2024 2 9,13,16
18 Primary systems check 6/11/2024 6/11/2024 1 17
19 Set date to move 6/12/2024 6/12/2024 1 18
20 Network components move 6/13/2024 6/14/2024 2 19
Output
The change management plan will be included in the project's changelogs to reduce delays and
guarantee that all parties affected are informed of any changes made within the project deadline.
In addition, the project manager and the stakeholders will oversee a quality management plan.
This will make it more likely that the project's quality goals, and important deliverables will be
met on time.
The main goal that AET Corp set out to accomplish with this project was to relocate its
data center in a way that would be convenient for its clients while meeting the project's quality,
budget, and regulatory criteria. Project team and Brian are certain that they will satisfy the
demands of the stakeholders while staying within the time, budget, and quality restrictions if they
examine and put into practice an out-of-project management strategy. They expect a smooth data
References:
Project Management Institute, Inc. (2017). A guide to the project management body of knowledge