Professional Documents
Culture Documents
220802DJPCME710 Flushing and Blowing Procedure Rev - 00
220802DJPCME710 Flushing and Blowing Procedure Rev - 00
220802DJPCME710 Flushing and Blowing Procedure Rev - 00
EPCI-2
Contract N.
Rev Validity
Number Status
JANGKRIK COMPLEX PROJECT
Blowing and Flushing Procedure Page 2 of 14
EniMuara Bakau B.V. 00 EX-CO
The purpose of this document is to provide blowing and flushing procedure in Jangkrik new field
Abstract
development. This procedure define the requirements for preparation and execution of blowing and
flushing activities during construction work of Jangkrik new field developments.
Document Verification
Signature
Prepared by Date
Arief Bashori 10-Nov-2018
Vendor Prepared
Signature
Checked by Date
Basir Sinaga 10-Nov-2018
Signature
Approval by Date
Jakarias Haloho 10-Nov-2018
Proj. Dev.
Rev Validity
Number Status
JANGKRIK COMPLEX PROJECT
Blowing and Flushing Procedure Page 3 of 14
EniMuara Bakau B.V. 00 EX-CO
REVISION LIST
RECORD OF AMENDMENT
No Section Para No Description of Changes
HOLD LIST
Section Description of Hold
Rev Validity
Number Status
JANGKRIK COMPLEX PROJECT
Blowing and Flushing Procedure Page 4 of 14
EniMuara Bakau B.V. 00 EX-CO
TABLE OF CONTENTS
ATTACHMENT A ............................................................................................................................................ 13
ATTACHMENT B ............................................................................................................................................ 14
Rev Validity
Number Status
JANGKRIK COMPLEX PROJECT
Blowing and Flushing Procedure Page 5 of 14
EniMuara Bakau B.V. 00 EX-CO
1.0 INTRODUCTION
1.1 Project Overview
Jangkrik field is located about 70 km from the coast, in the Muara Bakau permit area,
Makassar Strait, offshore Kalimantan, at water depth ranging from 250 to 500 m. ENI through
its Indonesian subsidiary, operates the Muara Bakau PSC.
The treated gas and condensate from FPU are exported via 24 inch treated gas export
pipeline and 4 inch condensate export pipeline to shore at Sapi landfall. An onshore receiving
facility (ORF) fiscal metering system for gas and condensate is located approximately 4 km
downstream of Sapi Landfall. Gas and condensate pipelines are the tie-in to existing East
Kalimantan pipeline network. Another tie-in at KM 21.65 is required for the gas line to allow
the full capacity of jangkrik gas. For this purpose, a 15 km of new pipelines is to be installed
parallel to existing line with TEPI’s ROW from ORF to KM 21.65, and will be tie-in to existing
20 inch Handil-Nilam pipeline and modification to be done at Nilam, BEM, and KM 53 inside
POMA area. Final destination of Jangkrik treated gas is to the Bontang LNG Plant and
domestic Bontang market; and the final destination of Jangkrik condensate is to Senipah
Plant.
2.0 ABBREVIATIONS
AA : Area Authority
QC : Quality Control
CONTRACTOR : PT Meindo Elang Indah
COMPANY : Eni Muara Bakau B.V
HSSE : Health Safety, Security and Environment
Rev Validity
Number Status
JANGKRIK COMPLEX PROJECT
Blowing and Flushing Procedure Page 6 of 14
EniMuara Bakau B.V. 00 EX-CO
3.0 REFERENCES
The following documents are referred to in this document.
3.1 Company Reference
Rev Validity
Number Status
JANGKRIK COMPLEX PROJECT
Blowing and Flushing Procedure Page 7 of 14
EniMuara Bakau B.V. 00 EX-CO
Rev Validity
Number Status
JANGKRIK COMPLEX PROJECT
Blowing and Flushing Procedure Page 8 of 14
EniMuara Bakau B.V. 00 EX-CO
Process impulse or injection to the lines should be disconnected. Control valve, Globe Valve &
Safety Valve will be dismantled and replaced by a dummy spool piece if required. Gate valve and
ball valve shall be removed and replace by dummy spool /spool piece if required. All vessel or
equipment should be blinded.
All mechanical equipment such as process pumps shall be blinded from the flushing and drying
network. Check and ensure spring support hangers (if any) are still blocked according to
manufacture standard prior to flushing. The lock shall be released only prior to commissioning.
Rev Validity
Number Status
JANGKRIK COMPLEX PROJECT
Blowing and Flushing Procedure Page 9 of 14
EniMuara Bakau B.V. 00 EX-CO
8 Helper 2 Persons
9 Company Rep 1 Person
8.5 Mechanic
Prepare testing requirement tools & standby during testing activities and responsibilities
for any emergency / damage on the tools/ testing equipment.
Rev Validity
Number Status
JANGKRIK COMPLEX PROJECT
Blowing and Flushing Procedure Page 10 of 14
EniMuara Bakau B.V. 00 EX-CO
a) Prior blowing and flushing, the CONTRACTOR to prepare and submit a flushing notice
to all parties concerned by the witnessing of the test, with the following document
attached:
Test pack data sheet
Marked-up P&ID showing test limits or boundaries
Isometric drawings
Detail pipe support drawings
Flushing/blowing and test layout showing:
test limits or boundaries
pressure utilized
location of fluid inlet from pump or compressor
location of gauges
medium
vents, drain or other fluid outlet
Check lists form for line check
Test sheets
Punch List Form
Blowing and Flushing Form
Make sure the Blowing & Flushing Procedure must be in place prior blowing and
flushing activities.
Make sure all line will be blowing and flushing have been NDT clearance.
Make sure line to be flushing has been hydrotest
b) All check and test forms shall be prepared and ready for fill up and sign off by
CONTRACTOR Inspector and COMPANY inspector who witnesses the test.
c) Whenever possible, the cleaning shall flow from top to bottom.
d) The diameter of the outlet pipe shall be at least two third of the diameter of the line to be
flushed, and at least as large as the inlet pipe.
e) Main header shall be cleaned first.
f) Large diameter pipes shall be cleaned before small diameter ones.
g) Fragile devices included in the network shall be removed.
h) Each flushing shall have a test number which same as test package number.
i) During flushing, large quantities of dirty is spread out in the outlet point and around test
pack network. This air generally contains sand, particles of rust, etc and might damage
other equipment (ex: breaking the glass of a pressure gauge). Additionally, compressed
air itself may damage the insulation materials, the electric motors, etc. Accordingly, the
following actions shall be taken where necessary:
To put a tarpaulin on motors, insulation, instruments near the flow outlet.
To direct outlet flow toward a place where there is no (fragile) equipment.
To change the direction of the flow by rotating an elbow.
To add a dummy spool to extend the outlet further.
j) Determination of the network maximum allowable pressure:
If the quick decompression method is used, the air pressure in the network shall
never exceed 6 Bar and use the calibrated pressure gauge.
If should also be checked that all pipes and vessels of the network are designed to
with stand a pressure of 6 Bar.
If a rupture disk is to be installed on a large diameter pipe, the set pressure of the
disk shall be carefully calculated in order to limit the energy released when bursting
occurs to an acceptable level.
Rev Validity
Number Status
JANGKRIK COMPLEX PROJECT
Blowing and Flushing Procedure Page 11 of 14
EniMuara Bakau B.V. 00 EX-CO
For pipes above 10” especially the first blowing will take place with the network
pressurized at only 2-3 Bar.
Detail method of flushing will be indicated on each test pack which TP use air
flushing Blowing, which the TP use quick opening valve, and which TP use
mechanical cleaning prior.
9.2 Blowing and Flushing Detail Procedure
Once all preparation work is completed, Testing Supervisor / Engineer shall inspect the
preparation work and check specially that all protections (safety devices) are installed i.e.:
pipe restraints, clamps, supports, protection of equipment and obtain the clearance of HSE
coordinator/Testing Supervisor. Air inlets and outlets shall be made during site review to
determine the possible of location, and any necessary temporary pipes. Isometric drawings
shall be marked up, and the required equipment to be supplied and installed i.e.: pipes,
valves, gaskets and shall be determined.
Once the site check is satisfied and ensure no person / material in the area, the testing
Supervisor / Engineer shall give authorization to start the air blowing operation. Testing
area will be barricaded and only authorized person on the work location.
Main methods use for air blowing is Quick Decompression Method.
Where the quick decompression method has been selected, the network can be isolated.
The pressure release can be obtained by:
A quick opening valve (required a quarter turn valve).
A rupture disk.
In the first case, the flow rate may be roughly adjusted, if necessary, and the quick opening
valve may be closed in case of emergency. Due to the high velocity involved, the quick
opening valve might be eroded if it is used in an intermediate state (i.e. not completely
opened). Therefore, whenever possible, the valve shall be completely open.
a. If a quick opening valve is used, allow the air to enter the network and carefully check
that pressure in the system never exceeds the maximum allowable pressure (2-3 Bar).
When the required pressure is reached, check that all safety measures have been
adhered to, and open the valve. This operation shall be repeated several times.
b. If a rupture disk is used, after having checked that safety measures have been taken,
allow the air to enter the network, check continuously the pressure rise, and when the
rupture disk blows out, stop the air inlet in the network. The operation shall be repeated
several times.
Note: Nominal pipe size more than 4” decompression with rapture disk. Nominal pipe size
smaller than 3” decompression with method quick decompression with valve (quick
decompression method).
Cleanliness check:
Mark Up P&ID and showing test limits or boundaries.
Color of the air at the exit point. This will roughly indicate whether or not rust and dirt
remain in the piping. This is usually sufficient for the majority of process and utilities
piping.
Use of a target plate. A polished aluminum or soft metal target is attached to the target
plate carrier on the tailpipe end.
After air blow of the system, examine the plate at the end of the air blowing. If the plate
has become eroded and pitted, easily seen by a matt grey appearance and surface
pitting, continue air blowing. Ensure blowing and flushing area is closed to avoid any
flying object hit the people.
This document is property of Eni Muara Bakau B.V.
It shall neither be shown to Third Parties not used for purposes other than those for which it has been sent.
220802DJPCME710 Revision Index
Rev Validity
Number Status
JANGKRIK COMPLEX PROJECT
Blowing and Flushing Procedure Page 12 of 14
EniMuara Bakau B.V. 00 EX-CO
AND
All un-authorized personnel are evacuated from that area, before the test is commenced.
The discharge areas shall be free from people working and passing. They shall be at
minimum distance of 30 meters from horizontal discharge.
The large quantities of dirty air released during the blowing and flushing carries particles of
sand, rust, welding rods, etc which could damage the equipment nearby and dangerous for
the personal. Therefore, adequate barricade must installed, such as hard barricade,
additional PPE, etc
Protection for personnel carrying out the operation must be ensured by suitable protective
equipment (PPE shall be appropriate with a rule be valid). Such us ear protection, gloves,
coverall, goggles as a minimum.
Note: equipment checked by competent person including specification of hoses and
connectors. Check/inspection result should be tag on equipment
11.0 ATTACHMENT
Attachment A - List of Equipment
Attachment B – Blowing schematic
Rev Validity
Number Status
JANGKRIK COMPLEX PROJECT
Blowing and Flushing Procedure Page 13 of 14
EniMuara Bakau B.V. 00 EX-CO
ATTACHMENT A
List of Equipment
Rev Validity
Number Status
JANGKRIK COMPLEX PROJECT
Blowing and Flushing Procedure Page 14 of 14
EniMuara Bakau B.V. 00 EX-CO
ATTACHMENT B
Blowing schematic
Air Compressor
PG
AIR
KO COMPRESSOR
Drayer
POT /Water Saparator
Basket