1. This agreement is between Sinoj of Valiyath constructions and Shamnad Subair of BLUE ARC builders for the construction of a steel foot bridge over the Ithikkara river in Kollam District.
2. Shamnad Subair will serve as the sub-contractor and will be responsible for the fabrication, erection, and civil works of the bridge project. Sinoj will provide all necessary materials and drawings.
3. The total project cost is Rs. 20,00,000 and payment will be made in stages upon completion of certain milestones. Both parties agree to be liable for losses due to any breaches of the contract terms.
1. This agreement is between Sinoj of Valiyath constructions and Shamnad Subair of BLUE ARC builders for the construction of a steel foot bridge over the Ithikkara river in Kollam District.
2. Shamnad Subair will serve as the sub-contractor and will be responsible for the fabrication, erection, and civil works of the bridge project. Sinoj will provide all necessary materials and drawings.
3. The total project cost is Rs. 20,00,000 and payment will be made in stages upon completion of certain milestones. Both parties agree to be liable for losses due to any breaches of the contract terms.
1. This agreement is between Sinoj of Valiyath constructions and Shamnad Subair of BLUE ARC builders for the construction of a steel foot bridge over the Ithikkara river in Kollam District.
2. Shamnad Subair will serve as the sub-contractor and will be responsible for the fabrication, erection, and civil works of the bridge project. Sinoj will provide all necessary materials and drawings.
3. The total project cost is Rs. 20,00,000 and payment will be made in stages upon completion of certain milestones. Both parties agree to be liable for losses due to any breaches of the contract terms.
1. This agreement is between Sinoj of Valiyath constructions and Shamnad Subair of BLUE ARC builders for the construction of a steel foot bridge over the Ithikkara river in Kollam District.
2. Shamnad Subair will serve as the sub-contractor and will be responsible for the fabrication, erection, and civil works of the bridge project. Sinoj will provide all necessary materials and drawings.
3. The total project cost is Rs. 20,00,000 and payment will be made in stages upon completion of certain milestones. Both parties agree to be liable for losses due to any breaches of the contract terms.
Puthenchantha,. of one part, the contractor, here in after called the Ist party and BLUE ARC builders and engineers represented by its Managing partner Shamnad Subair S/o.Subair kutty, Edavanthazhathu veedu, Vavvakkavu.P.O., Changankulangara, Oachira Village, Karunagappally Taluk of the other part, the Sub contractor, here in after called the 2nd party. In consideration of the payment to be made by the Ist party to the 2nd party the 2nd party hereby convenents with the Ist party to execute, complete and maintain the subcontract work in conformity in all respect with the terms and conditions of this Agreement. IN WITNESS thereof the Ist and 2nd parties here into set their respective hand the day month and year first above written.
Ist Party 2nd party.
Sinoj Shamnad Subair
1. Specification and scope of work of the Sub-Contract.
1. Description of work:- Construction of steel foot brich at Marakkulam Kadavu across Ithikkara river in Kollam District. Site Location Markkulam Kadavu, Sheematti.P.O., Chathanoor. 1(2) Mechanical work 1.(2) (i)The specification and scope of works to be performed by the 2nd party, the sub-contractor under this agreement with regard to mechanical work in connection with the discription of work is as follows; (a) Fabrication and erection of the brdige, all materials, tools, and tackles, consumables, Lifting equipments, Labour, electricity, scafoldings, and other work expenses are to be met by the 2nd party. 1(2)(ii) The specification and scope of work to be performed by the Ist party the contractor under this agreement with regard to mechanical work in connection with the description of work is as follows; (a)All drawings, working procedure, inspection documents is to be provided by the Ist party 1(2) (iii) Total weightage of mechanical work is 9.74 Tones. 1(2) (iv) Rate of Fabrication and errection work Rs. 1,20,000/- per tone. 1(2)(v) Total amount 11, 68,800 1(2) (vi) Hand rails. Total length of Hand rail is 417 meters. 1(2) (vii) Rate of Hand rail Rs. 80/- per meter Total amount for hand rail Rs. 33,360/- 1(2)(viii) Grand total of Mechanical work Rs. 12,02,16/- Round off Rs. 12,00,000/-
1(3) Civil work.
Pilling work of the bridge is already completed by the Ist party, contractor. 1(3) (i) Specification and scope of work to be performed by the 2nd party, sub contractor, with regard to the civil work in connection with the description of work is as follows; (a) Pile chipping, PCC, RCC, steal bending, rubble work, ceramic floor laying, interlock laying escavations, painting, granular sub abse, Labour work, Labour, shutter materials, mixer and tools and necessary for the work completion. 1(3) (ii) Specification and scope of work to be performed by the Ist party, with regard to civil work, is as follows. (a) All materials such as M.Sand, Metal, Steel, Cement, Rubble, floor tile, all other meterials required for the work is to be provided by the Ist party. (b) All drawings, working procedure, inspection reports etc. i(3) (iii) Total amount labour work with tools and tackles for civil work is Rs. 8, 00,000/-. 2. Payment condition for Mechanical and Civil Work (a) Advance 2,00,000 (Two Lakhs) on date 23/7/2018. (b) 5,00,000/- (Five Lakhs) on date 9/8/2018. (c) 3,00,000/- (Three Lakhs) on date 24/8/2018. (d) Rs.3,00,000/- (Three Lakhs) after completion of fabrication and before starting the erection work. (e) Rs.4,00,000/- (Four Lakhs) on date 25/9/2018 (f) Balance 3,00,000/- (Three Lakhs) within 30 days after completion of work. Total cost for the completion of work Rs. 20,00,000/-(Twenty Lakhs) 3 Accomodation, Food. The second party, the sub-contractor shall be responsible for accommoda tion and food for his staff and labours. 4. Transportation The second party, the sub contractor shall be responsible for transportation of his staff and Labours to and from the site. 5. Quality of Assurance By putting signature in this agreement the 2nd party the subcontractor agrees to comply with required quality for the work done by him. 6 Consequenses of breach The second party hereby affirms that he will perform all the duties incurred upon him, by using of this agreement and that if any loss occured to the Ist party due to derliction of duty or breach of conditions, by the 2nd party all assets including immovable and movable properties of the 2nd party will be liable to compensate the said loss. The first party also hereby affirmed that he will perform all the duties incurred upon by him by way of this agreement including the payments to 2nd party, and that if any loss occured due to derliction of duty or breach of conditions by the ist party, all the assets including immovable and movable properties of the Ist party will be made liable to compensate the said loss of the Ist Party. In case any breach on this conditions mentioned above the affected party can approach court of law for reddressal of his grievance.