Professional Documents
Culture Documents
Method Statement For Reservoir Water Tightness Tests
Method Statement For Reservoir Water Tightness Tests
(CRCEG)
1
Method statement for the Reservoirs water tightness test
中 铁 建 工 集 团 有 限 公 司
CHINA RAILWAY CONSTRUCTION ENGINEERING GROUP
Contents
1. Project Overview.......................................................................................................................................3
2. Before the water tightness test.................................................................................................................4
2.1 Prerequisites for the test....................................................................................................................4
2.2 Water tightness test preparation........................................................................................................5
3. Water tightness test..................................................................................................................................5
3.1 Water tightness test............................................................................................................................5
4. Leakage treatment of pool........................................................................................................................6
4.1 Leakage of construction joints...........................................................................................................6
4.2 Leakage due to the low level of concrete impermeability..................................................................7
4.3 Leakage of sealed holes, sealed embedded pipes and other buried parts..........................................7
4.4 Leakage of concrete cracks................................................................................................................8
5. Appendix: Record Form of Water Tightness Test......................................................................................8
2
Method statement for the Reservoirs water tightness test
中 铁 建 工 集 团 有 限 公 司
CHINA RAILWAY CONSTRUCTION ENGINEERING GROUP
1. Project Overview
The reservoirs in the “Design, Rehabilitation, Upgrading and Extension of Water Supply
Network in Kigali City and Peri-Urban Areas” Project, constructed by CRCEG, will be subjected
to water tightness tests according to the BS 8007 ‘Design of concrete structures for retaining
aqueous liquids’. The reservoirs’ information is given below:
3
Method statement for the Reservoirs water tightness test
中 铁 建 工 集 团 有 限 公 司
CHINA RAILWAY CONSTRUCTION ENGINEERING GROUP
Given that water evaporation is negligible for closed-type reservoirs, its calculation is not
required during water tightness tests. It is only required for opened-type reservoirs/tanks.
4
Method statement for the Reservoirs water tightness test
中 铁 建 工 集 团 有 限 公 司
CHINA RAILWAY CONSTRUCTION ENGINEERING GROUP
All holes in the concrete, such as manholes, ventilation duct holes, etc. must be blocked
by a galvanized iron sheet and an adhesive tape will be used to seal around the galvanized
iron sheet;
The installation of water inlet, outlet, overflow pipes and washouts must be completed.
These pipes will be sealed with the approved gate valves or blind plates.
WASAC water will be used in this test.
Reservoirs over 2000 cubic meters are composed of two independent chambers, which will be
tested independently during the water tightness tests. Since the two chambers have independent
inlet, outlet, washout, and overflow pipes; the water tightness test will be first performed in the
first chamber. After the water tightness test is finished, the water in the first chamber will be
directly pumped to the other chamber so as not to waste water. After the test is completed, water
will be drained through the washout.
2.2 Water tightness test preparation
Repair and treat honeycombs, segregation, and formwork screw holes on the concrete
surface. The concrete surface around embedded pipes should also be treated so as to
avoid leakage;
Thorough inspection of concrete surface, if cracks or uneven settlement are identified,
they should be dealt with;
Temporarily block/seal the holes opening as prescribed above;
Check the gate valve for leakage;
Clean and remove all the debris in the reservoir;
Prepare necessary safety protection measures and lighting appliances;
Set the water level observation ruler to indicate the water level during water injection,
and install a water level probe to measure the water level drop (or use a Vernier caliper
instead);
Arrange observation points and measure the initial elevation value of each observation
point of the reservoir;
5
Method statement for the Reservoirs water tightness test
中 铁 建 工 集 团 有 限 公 司
CHINA RAILWAY CONSTRUCTION ENGINEERING GROUP
6
Method statement for the Reservoirs water tightness test
中 铁 建 工 集 团 有 限 公 司
CHINA RAILWAY CONSTRUCTION ENGINEERING GROUP
Note: If the structure does not meet the specified requirements, after the completion of the
remedial work, it will be refilled and a further test of 7 days’ test duration will then be
undertaken in accordance with the BS 8007.
During the water tightness test of the reservoir, the following types of leakage may occur in the
reservoir:
Leakage of construction joints,
Leakage due to the low level of concrete impermeability,
Leakage of sealed holes as well as sealed embedded pipes,
Leakage of concrete cracks, etc.
4.1 Leakage of construction joints
The following reasons can cause the construction joint leakage:
When the construction joints were not properly roughened before casting concrete, thus
causing a weak concrete joint;
When the construction joints were not properly cleaned or water has accumulated;
When the mortar on the concrete joint was insufficient, thus causing the joint to be dry;
When there was poor vibration while casting concrete;
When the poured concrete had poor workability; etc.
Treatment method: Both the inside and outside surface of concrete must be treated and repaired.
1. The leaking construction joints should be cut into 3-5 cm deep and 2-3 cm wide grooves.
2. Then, a wire brush and pressurized water will be used to thoroughly clean the groove.
3. Afterwards, the groove is repaired with SIKA waterproof cement mortar (Technical
specification is attached herewith). It is usually filled in 2-3 layers. The time interval
between layers reparation should not be less than 8h. Before filling, the groove should be
first brushed with cement paste. When the construction joint is located at the corner of the
wall and the floor, the corner is covered with layers of a triangular shape. When
repairing, the groove should be moist, and not overflowing with water.
4. After repairing the seepage area of the joints, another layer of the SIKA waterproof
cement mortar can be added to strengthen the waterproofing and anti-seepage ability.
7
Method statement for the Reservoirs water tightness test
中 铁 建 工 集 团 有 限 公 司
CHINA RAILWAY CONSTRUCTION ENGINEERING GROUP
Project name
8
Method statement for the Reservoirs water tightness test
中 铁 建 工 集 团 有 限 公 司
CHINA RAILWAY CONSTRUCTION ENGINEERING GROUP
(L/㎡·d)
Reservoir surface area Water surface area
(m×m) A1(㎡)
Total wet area
Water depth(m)
A2(㎡)
Difference between
Reading record Initial reading Last reading
readings
Reading time(Year,
month, date)
Hour, seconds
Reservoir water level
E(㎜)
Atmospheric
temperature(℃)
Water temperature
(℃)
Percentage of allowable
m3/d L/㎡·d amount
Actual water %
seepage
Participants
9
Method statement for the Reservoirs water tightness test
中 铁 建 工 集 团 有 限 公 司
CHINA RAILWAY CONSTRUCTION ENGINEERING GROUP
10
Method statement for the Reservoirs water tightness test
中 铁 建 工 集 团 有 限 公 司
CHINA RAILWAY CONSTRUCTION ENGINEERING GROUP
11
Method statement for the Reservoirs water tightness test
中 铁 建 工 集 团 有 限 公 司
CHINA RAILWAY CONSTRUCTION ENGINEERING GROUP
12
Method statement for the Reservoirs water tightness test
中 铁 建 工 集 团 有 限 公 司
CHINA RAILWAY CONSTRUCTION ENGINEERING GROUP
13
Method statement for the Reservoirs water tightness test
中 铁 建 工 集 团 有 限 公 司
CHINA RAILWAY CONSTRUCTION ENGINEERING GROUP
14
Method statement for the Reservoirs water tightness test