Professional Documents
Culture Documents
Valves Data Final
Valves Data Final
Valves Data Final
NAME OF WORK: PROVIDING DRINKING WATER TO HABITATIONS IN SRSP ADILABAD SEGMENT IN ADILABAD DISTRICT
NAME OF WORK: PROVIDING DRINKING WATER TO HABITATIONS IN SRSP ADILABAD SEGMENT IN ADILABAD DISTRICT
NAME OF WORK: PROVIDING DRINKING WATER TO HABITATIONS IN SRSP ADILABAD SEGMENT IN ADILABAD DISTRICT
Total Amount in GST Labour cess Vat Labour cess GST Labour cess GST QC GST 18% QC GST 12% NAC GST 18% NAC GST 12%
S.NO DESCRIPTION OF ITEM Total Labour Cess QC Vat Period Total QC NAC Vat Period Total NAC Vat GST 18% GST 12% Total
12% Period Period 18% Period 12% Period Period Period Period Period
TOTAL
Certified that
1. The above item and measurements are the TRUE EXTRACT of the Measurement Book
No.326,357/TDWSP/NIRMAL/2015 & 1083, 1146/TDWSP/Nirmal/2016 and the total work is completed in all
aspects.
Bela
1.50
1.43
Amount
110,464.00
-586.00
33,490.00
143,368.00
ok
work is completed in all
GST AND EMBEDDED TAX CALCULATIONS FOR WORK DONE SUB-ESTIMATE
Name of the work : PROVIDING DRINKING WATER TO HABITATIONS IN SRSP ADILABAD SEGMENT IN ADILABAD DISTRICT
Name of the Sub - work : Providing Water supply connection to KGBV Bela
Construction of pipeline including supply ,delivery , laying and jointing of HDPE pipes for water
supply as per IS:4985 :1988 with its amendments and revisions thereon including supply of
pipes ,treach excavation for pipe lines in all soils except rock requiring blasting, lowering ,laying
and jointing of pipes true to alignment and gradient, and refilling trenches with excavated earth
1 (other than rocky soils and boulders) with watering and tamping and removing surplus earth from
site of work and testing pipeline with water and required pressure etc., as per Trench size of
0.7X0.8 Mts complete. The rates are inclusive of cost & conveyance of all materials, and labour
charges, but excluding CED and taxes for finished pipeline work.
1.Part-A-Supply
28/Jun/2020 326/TDWSP/NIRMAL/2015 Invoice No:01734 41 HDPE 75 mm 8 kg/cm2 325.00 50% 339.89 Rmt 55,232.00 339.89 55,232.00 0.00 0 0 6627.84
2.Part-B-Laying
28/Jun/2020 1146/TDWSP/NIRMAL/2016 7 HDPE 75 mm 8 kg/cm2 325.00 30% 339.89 Rmt 33,139.00 339.89 33,139.00 0.00 0 0 3976.68
15/Dec/2020 1146/TDWSP/NIRMAL/2016 25 HDPE 75 mm 8 kg/cm2 325.00 15% 339.89 Rmt 16,569.00 339.89 16,569.00 0.00 0 0 1988.28
3.Part-D- Commissioning
20/Dec/2020 1146/TDWSP/NIRMAL/2016 30 HDPE 75 mm 8 kg/cm2 325.00 5% 339.89 Rmt 5,523.00 339.89 5,523.00 0.00 0 0 662.76
Manufacture, Supply delivery and fixing of DI D/F Gate Valves arrangement on HDPE Pipes
(Soft Seated) Resilient seated soft sealing gate valves (Sluice valves) with body bonnet of ductile
cast iron of grade GGG40/ SG 400/12 or equivalent grade as per I.S.3896-part2-1985 and
subsequent revisions, wedge fully rubber lined with EPDM food grade quality and seals of NBR and
the valves should be of vacuum tight and 100% leak proof with face to face dimensions as per
BS5163-89/IS14846-2000/DIN 3202 F 4. All the valves should be with Electrostatic powder coating
2
both inside and outside pocket less body passage. Drilled as per IS:1538.PN16-All the valves fixed
with , 0.6m D/F DI pipes 2nos,2 ns HDPE Tail Pieces, 2Nos MS Flanges,2, Jointing material
such as Rubber Washers, Nuts and Bolts, Labour charges for lowering and fixing valves, With RCC
Valve Chamber of Size 0.90X0.90X0.75 Mts , including Earth work Excavation, PCC(1:4:8),
M20 Grade concrete for Raft, Side walls and Precast slab, supply and fabrication steel as per
Approved Drawing etc complete for fininshed itme of work
1.Part-A-Supply
27/Jun/2017 357/TDWSP/NIRMAL/2015 Invoice No. 58 1 DI 80 mm PN16 1 50% 33490.00 Nos 16,745.00 28,453.00 14,227.00 2,518.00 711.35 0 0
2.Part-B-Errection
22/Dec/2020 1146/TDWS/Nirmal/2016 40 DI 80 mm PN16 1.00 50% 33490.00 Nos 16,745.00 28,453.00 14,227.00 2,518.00 0 0 1707.24
TOTAL 143,367.00 138,331.00 5,036.00 711.35 0.00 14,892.48
PRICE VARIATION OF CEMENT FOR VALVE CHAMBERS & CAGES
NAME OF THE WORK:- PROVIDING DRINKING WATER TO HABITATIONS IN SRSP ADILABAD SEGMENT IN ADILABD DIST.
Name of the Sub - work : Providing Water supply connection to KGBV Bela
1 1083/TDWSP/NIRMAL/2016 52 Valve Chamber PCC 0.90 x 0.75 x 1.05 0.224 1/6/2021 0.162 0.036 12/9/2020 6200 4813.29 5500.00 686.71 14.27 9.27 16.19 2.20 18.00 0.00 0.00 2.00
2 1083/TDWSP/NIRMAL/2016 54 Valve Chamber RCC 0.90 x 0.75 x 1.05 0.115 1/7/2021 0.400 0.046 12/10/2020 6200 4813.29 5500.00 686.71 14.27 9.27 20.52 2.79 23.00 0.00 0.00 3.00
3 1083/TDWSP/NIRMAL/2016 55 Valve Chamber RCC 0.90 x 0.75 x 1.05 0.408 1/8/2021 0.400 0.163 12/11/2020 6200 4813.29 5500.00 686.71 14.27 9.27 72.82 9.91 83.00 0.00 0.00 10.00
4 1083/TDWSP/NIRMAL/2016 57 Valve Chamber RCC 0.90 x 0.75 x 1.05 0.110 1/9/2021 0.400 0.044 12/12/2020 6200 4813.29 5500.00 686.71 14.27 9.27 19.72 2.68 22.00 0.00 0.00 3.00
146.00 0.00 0.00 18.00
Page 7 of 108
PRICE VARIATION OF STEEL FOR WORK DONE SUB-ESTIMATE
NAME OF THE WORK:- PROVIDING DRINKING WATER TO HABITATIONS IN SRSP ADILABAD SEGMENT IN ADILABD DIST.
Name of the Sub - work : Providing Water supply connection to KGBV Bela
Revised
Rate of Rate of Differenc
Rate of Steel Steel Diff in
Work Cement as % increase e
Date of after rate as Total
Page done per as per PH or Variation Add CP Total PV Amount 5% VAT 18%
S. No MB No. Work Done item Chamber size Measuremen Dt-28 Embedded per price Amount 12% GST
Tax (18.12%) (28 days variation decrease Rate @13.615% (Rs)
No. quantity sanctione GST
t
in MT d estimate prior to After (+/-
in MT ₹
in MT ₹ DOM) in 5%)
MT ₹
0.90 x 0.75 x
1083/TDWSP/NIRMAL/2016 53
1.05
0.03769 1/7/2021 12/10/2020 40000 33863.87 48000 14136.13 41.74 36.74 468.95 63.85 533.00 0.00 0.00 64.00
1 Valve Chamber
0.90 x 0.75 x
1083/TDWSP/NIRMAL/2016 56
1.05
0.0073 1/2/2021 12/5/2020 40000 33863.87 48000 14136.13 41.74 36.74 90.83 12.37 103.00 0.00 0.00 12.00
2 Valve Chamber
Total amount 636.00 0.00 0.00 76.00
Page 8 of 108
SEINORAGE CHARGES FOR WORK DONE SUB ESTIMATE
NAME OF THE WORK:- PROVIDING DRINKING WATER TO HABITATIONS IN SRSP ADILABAD SEGMENT IN ADILABD DIST.
Name of the Sub - work : Providing Water supply connection to KGBV Bela
Price Variation on
Aggregates (Metal) Sand Seignorage Charges
Work Work
Total As Per Total
As
S.N Done Done As per As per G.O-67, Dtd Differe As per G.O-67, Dtd
Per
o Description quantit quantit Consta Agreement 26.09.2015 nce Const
As per Agreement 26.09.2015 Differen Total Diff GO Agreement
Value of work in
y(RCC) y(PCC) nts Qty Qty ce
Rate Amount Rate Amount Amoun ants Amount Amount Amount VAT GST
(Rs) (Rs) (Rs) (RS) t Rate (Rs) (Rs) Rate (Rs) (Rs) 5% 18% GST 12%
1 Valve Chamber 0.63 0.22 0.90 0.77 50.00 39.00 75.00 58.00 19.00 0.45 0.39 40.00 16.00 40.00 16.00 0.00 19.00 74.00 55.00 - - 19.00
0.63 0.22 39.00 58.00 16.00 16.00 0.00 19.00 74.00 55.00 0.00 0.00 19.00
Page 9 of 108
Sub-estimate
Construction of 0.90mx0.9mx1.6m Size valve chamber
for Pipes of DI 100-200mm dia and HDPE 63-150mm dia
Embeded
Date of Amount
Embeded Embeded Tax
Sno Description measuremen MB No Pg No No L B D Qty Unit Rate Per Amount Excluding
Rate Tax Rate /Unit
t Taxes
rate
Earth work excavation and depositing on bank with an initial lead of 50m and lift of
1 3.0m in all types of soils except hard rock requiring blasting for founadtion
3/Oct/2020 1132 43 1 1 1.50 1.35 0.75 1.519 Cum 128.20 cum 195.00 128.20 0.00 0.00 195.00
CC M15 Using 40mm HBG metal including cost and conveyance of all materials,labour
2 charges etc., complete for foundation.
5/Oct/2020 1132 44 1 1 1.30 1.15 0.15 0.224 Cum 4,927.10 Cum 1,104.00 4,656.59 270.51 61.00 1,043.00 61.00
RCC (1:1.5:3) using 20mm HBG metal including cost and conveyance of all
3 materilas,labour charges and centering etc., complete but excluding cost of steel 0.00
and its fabrication.
a) For Bottom Footing 7/Oct/2020 1132 46 1 1 1.30 1.15 0.10 0.15 Cum 0.00
Total 7/Oct/2020 0.150 Cum 8,953.80 Cum 1,343.00 8,308.32 645.48 97.00 1,246.00 97.00
b) For Side walls allround 9/Oct/2020 1132 47 1 1 3.70 0.10 1.05 0.389 0.00 seinorage
Deduct two openings 9/Oct/2020 1132 47 2 0.785 0.10 0.10 0.10 -0.002 0.00
9/Oct/2020 0.387 Cum 18,350.27 Cum 7,102.00 17,704.77 645.50 250.00 6,852.00 250.00
c) For Pre cast top slab(100mm thick) 11/Oct/2020 1132 49 1 1 1.10 0.95 0.10 0.105 0.00 78.94
Deduct two openings 11/Oct/2020 1132 49 2 0.785 0.05 0.05 0.10 0 0.00
11/Oct/2020 0.1050 Cum 11,812.24 Cum 1,240.00 11,166.74 645.50 68.00 1,173.00 67.00
Cost and supply of Steel including 0.00
4
fabrication charges
Along short span 10mm dia 200c/c 7/Oct/2020 1132 45 1 7 1.05 0.617 0.005 0.00
Along long span 10mm dia 200c/c 7/Oct/2020 1132 45 1 6 1.20 0.617 0.004 0.00
Side wall vertical bars 10mm dia 0.00
7/Oct/2020 1132 45 1 19 1.11 0.617 0.013
200c/c
Hoop ring 10mm dia 200 c/c 7/Oct/2020 1132 45 1 6 4.28 0.617 0.016 0.00
0.038 MT 51,392.60 MT 1,944.00 43,999.30 7,393.30 280.00 1,665.00 279.00
Along short span 10mm dia 200c/c 11/Oct/2020 1132 48 1 6 0.89 0.617 0.003 0.00
Along long span 10mm dia 200c/c 11/Oct/2020 1132 48 1 5 1.04 0.617 0.003 0.00
lift hooks 10mm dia 2nos 11/Oct/2020 1132 48 1 2 0.65 0.617 0.001 0.00
0.0073 MT 51,392.60 MT 375.00 43,999.30 7,393.30 54.00 321.00 54.00
Total Amount for Chamber 13,303.00 810.00 12,495.00 808.00
Valve cha 2015-16
Embeded Steel for
Approved SG
Tax raft,side Steel for
Rate Charges
3240 Rectangula Amount EW PCC Raft Side walls Slab wall slab
0.90x0.75x1.0
5m 13,303 810.00 195.00 1,104.00 1,343.00 7,102.00 1,240.00 1,944.00 375.00
0.90x0.90x1.4
0m 0
1.05x1.20x1.
70m 0
1.20x1.20x
2.10m 0
1.70x1.20x
2.1m 0
3.0x2.0x2.5
0m 0
Asst. Executive Engineer Deputy Executive Engineer
MB Grid Division Asifabad MB Grid Division, Kerameri
# Sensitivity: Unclassified
Sub-estimate
Construction of 0.90mx0.75mx1.05m Size valve chamber
for Pipes of dia upto 80mm dia
1 1 1.30 1.15 1.35 2.018 Cum 219.44 cum 443.00 219.44 0.00 0.00 443.00
CC(1:4:8) Using 40mm HBG metal including cost and
conveyance of all materials,labour charges etc.,
2
complete for foundation.
1 1 1.30 1.15 0.15 0.22425 Cum 5,547.72 Cum 1,245.00 5,382.01 165.71 37.00 1,207.00
RCC (1:1.5:3) using 20mm HBG metal including cost
and conveyance of all materilas,labour charges and
centering etc., complete but excluding cost of steel
3 and its fabrication.
c) For Pre cast top slab(100mm thick) 1 1 1.10 0.95 0.10 0.1045
Sensitivity: Unclassified
#
Data Sheet for Fixing Sluice valves on HDPE Mains
Manufacture, Supply and delivery of DI D/F Gate Valves (Soft Seated) Resilient seated
soft sealing gate valves (Sluice valves) with body bonnet of ductile cast iron of grade
GGG-40/ SG- 400/15 or GGG-50/SG-500/7 or equivalent grade as per I.S.3896-part2-
1985 and subsequent revisions, wedge fully rubber lined with EPDM food grade
1 quality and seals of NBR and the valves should be of vacuum tight and 100% leak 9426 9426 9426 12434
proof with face to face dimensions as per BS5163-89/IS14846-2000/DIN 3202 F 4. All
the valves should be with Electrostatic powder coating both inside and outside
pocket less body passage. Drilled as per requirement of the dept.
Jointing materials such as bolts nuts and rubber vouchers including material cost for
6 559.94 559.94 559.94 1024.97
main line - 2nos
7 Jointing materials such as bolts nuts and rubber vouchers for Sluice valve fixing 0.00 0.00 0.00
8 Labour charges for lowering DI pipes (2 jobs) 49.11 49.11 49.11 62.12
9 Lowering of valve and keeping in postion 133.35 133.35 133.35 177.07
10 Cost of RCC valve chamber 17121.00 17121.00 17121.00 17121.00
11 Add: contractors profit 13.615% 1884.85 1897.65 1908.27 2509.74
Grand total 32850 32957 33045 38064
12 Contractors profit 13.615% (W/o cost of Gate valve) 537.34 550.13 560.75 732.21
13 Total W/o cost of Gate valve) 21604.98 21711.78 21800.40 23231.14
14 Labour charges of Loosening of Sluice valve 182.46 182.46 182.46 239.19
15 Contractors profit 13.615% 24.84 24.84 24.84 32.57
16 Total Labour charges of Loosening of Sluice valve 207.30 207.30 207.30 271.76
17 Total cost for loosening and re-fixing of Sluice valve with chamber 21812.28 21919.08 22007.70 23502.90
1 Single Chamber DI Air Valve with Body and cover in Ductile Iron of grade SG
400/12 or equivalent grade as per I.S.3896-part2-1985 and subsequent 30745.00 30745.00 30745.00 30745.00
revisions
2 Cost and supply of DI D/F bewel geared Isolaated sluice valve confirming to IS
3986 part - 2 1985 etc. 9426.00 9426.00 9426.00 12434.00
2 Transportation charges(5%) 2009.00 2009.00 2009.00 2159.00
3 Cost of Air Tee DI A/F 2448.64 2448.64 2448.64 2950.40
4 Cost of 0.6m D/F DI pipes 2nos 2810.25 2810.25 2810.25 3445.77
5 Cost of D/F DI pipe Vetical Stem 5344.00 5344.00 5344.00 5344.00
6 Cost of HDPE Tail pieces 2 nos 148.00 178.00 230.00 318.00
7 Cost of MS flanges 2nos 246.00 310.00 336.00 350.00
8 Jointing materials such as bolts nuts and rubber vouchers including material
cost for main line - 4nos 447.95 447.95 447.95 819.98
9 Jointing materials such as bolts nuts and rubber washers for Air valve and
Isolated Gate Valve and extra stem pipe fixing 215.70 215.70 215.70 215.70
10 Labour charges for lowering DI pipes and tees - (2 jobs+1job)+3 194.26 194.26 194.26 220.24
11 Labour charges for fixing of Air valve with isolated sluice Valve 335.85 335.85 335.85 335.85
12 Add MA 0.00 0.00 0.00 0.00
13 Air Valve Encasement for the stem pipe of the air valve for the earthwork ,
PCC , and 20 mm HBG grade RCC including labour charges and etc., as per the 7885.00 7885.00 7885.00 7885.00
specified dimesnsions.
16 Contractors profit 13.615% (W/o cost of Air valve & Gate valve) 1659.76 1672.56 1683.17 1906.09
17 Total (W/o cost of Air valve & Gate valve) 21735.41 21842.20 21930.82 23791.03
18 Labour charges of Loosening of air valve 530.11 530.11 530.11 556.09
19 Contractors profit 13.615% 72.17 72.17 72.17 75.71
20 Total Labour charges of Loosening of air valve 602.28 602.28 602.28 631.80
21 Total cost for loosening and re-fixing of air valve 22337.69 22444.49 22533.11 24422.83
Note: For 50mm and 80mm dia Air valve DI stem and Air tee meterial cost is taken bz it is embede in concrete.Above 80mm dia Air valve only
labour charges is considered.
3 Transportation chargers (5% of basic cost) 471.30 621.70 978.85 978.85 1626.60 3404.90
2 Cost of Dismantling Joint (up to 300 mm dia CI and above 300 mm dia MS 5559.00 7294.00 10289.00 10289.00 14591.00 27791.00
4 Cost of DI Duck foot bend 1920.00 2176.00 3456.00 3456.00 4864.00 300.00
5 Cost of 0.6m DI D/F pipes 3nos 4215.38 5168.65 8380.47 8380.47 11950.86 20390.37
6 Cost of DI Semicircular bend 1792.00 2304.00 4096.00 4096.00 6272.00 14848.00
7 Jointing materials such as bolts nuts and rubber vouchers - 7 Jobs 783.91 1434.96 2400.51 2400.51 2648.35 4208.32
8 Labour charges for lowering DI pipes & Bends (5 jobs) 204.62 258.85 422.80 422.80 608.32 1063.23
9 Sluice valve lowering and fixing charges 133.35 177.07 300.12 300.12 495.12 1001.75
10 Cost of RCC valve chamber
11 Add: contractors profit 13.6150% 3336.43 4339.00 6793.99 6793.99 10291.34 19211.52
12 Grand total 27842.00 36208.00 56695.00 56695.00 85880.00 160317.00
14 Contractors profit 13.615% (W/o cost of Gate valve,) 1988.91 2561.46 3995.31 3995.31 5640.65 9476.40
15 Total (W/o cost of Gate valve,) 16597.18 21374.99 33340.21 33340.21 47070.30 79079.07
16 Labour charges of Loosening of Scour valve 337.97 435.92 722.92 722.92 1103.44 2064.98
17 Contractors profit 13.615% 46.01 59.35 98.43 98.43 150.23 281.15
18 Total Labour charges of Loosening of Scour valve 383.98 495.27 821.34 821.34 1253.67 2346.13
19 Total cost for loosening and re-fixing of Scour valve with chamber 16981.16 21870.26 34161.55 34161.55 48323.97 81425.20
Note : VRCC valve chamber can not be relocated.
Asst. Executive Engineer Dy. Executive Engineer(FAC) Executive Engineer Superintending Engineer
MB Grid Sub Division, Adilabad MB Grid Sub Division, Adilabad MB Grid , Division-Adilabad MB Circle, Adilabad
Data for DI Fixures-Per Each Joint
2022-23
Cost of Synthetic 6mm thick rubber sheet 12kg/sqm - PHSSR 31 Cost of nut bolts including vauchers - P
1 2 3 4 5 6 7 8 9
Jointing DI D/F pipes
DI PIPE LINE Per Joint Size considered from AP standard PH data upto 750mm dias (above 750mm - from SSR directly)
1 1000mm dia D/F Joint 8259.00 1.215x1.215 10.500 111.00 1165.50 51.80 51.80
2 900mm dia D/F Joint 7173.00 1.115x1.115 9.450 111.00 1048.95 40.60 40.60
3 800mm dia D/F Joint 6098.00 1.015x1.015 8.400 111.00 932.40 27.36 27.36
4 750mm dia D/F Joint 4249.38 0.965x0.965 7.843 111.00 870.57 26.04
5 700mm dia D/F Joint 3952.74 0.915x0.915 6.891 111.00 764.90 24.48
6 600mm dia D/F Joint 3098.33 0.815x0.815 5.171 111.00 573.98 19.20
7 500mm dia D/F Joint 2218.43 0.670x0.670m 3.819 111.00 423.91 13.40
8 450mm dia D/F Joint 1909.26 0.615x0.615m 2.266 111.00 251.53 12.30
9 400mm dia D/F Joint 1636.87 0.565x0.565m 2.764 111.00 306.80 9.84
10 350mm dia D/F Joint 1019.52 0.505mx0.505 2.126 111.00 235.99 16nosx0.39 Kg 5.44
11 300mm dia D/F Joint 703.88 0.45mx0.45m 1.028 111.00 114.11 12nosX0.39Kg 3.96
AC PIPE LINE
11 250mm dia D/F Joint 671.67 0.40mX.040m 0.85 111.00 94.35 12nosX0.39Kg 3.96
12 200mm dia D/F Joint 459.65 0.35mX0.365m 0.62 111.00 68.38 8nosX0.39Kg 2.52
13 150mm dia D/F Joint 419.03 0.30mX0.30m 0.43 111.00 47.73 8nosX0.39Kg 2.40
14 125mm dia D/F Joint 268.66 0.26mX0.26m 0.31 111.00 34.85 8nosX0.297Kg 1.36
15 100mm dia D/F Joint 0.23mX0.23m 0.25 111.00 28.19 8nosX0.297Kg 1.36
16 80mm dia D/F Joint 0.21mX0.21m 0.21 111.00 23.59 4nosX0.297Kg 0.68
17 50mm dia D/F Joint 0.20mX0.20m 0.15 111.00 16.65 4nosX0.297Kg 0.43
18 40mm dia D/F Joint 0.13mX0.13m 0.13 111.00 14.43 4nosX0.21Kg 0.34
13.55
34450.325
11077.1045
45527.4295 600mm dia
PN16 kgs
DI Spiogot Flange 80 1080 8 56604.534 700mm dia
At 135 per kg upto 500mm dia 100 1350 10
Rs 147 above 500mm dia 125 1755 13
135 150 2160 16
147 200 3105 23
250 4320 32
300 5670 42
350 7560 56
400 9450 70
450 11880 88
500 14850 110
600 23373 159
COMMON SSR: 2015-16 Lowering
10 11 12 14
Lowering CI D/F pipes For PVC Air valves
R directly) per RMT
123.00 6371.40 7536.90 15795.90
895.00 SSR 18308
123.00 4993.80 6042.75 13215.75
689.00 SSR 15724
123.00 3365.28 4297.68 10395.68
530.00 SSR 13256
123.00 3202.92 4073.49 8322.87
529.1 PH data 9556.96
123.00 3011.04 3775.94 7728.68
468.51 PH data 8842.5
123.00 2361.60 2935.58 6033.91
362.19 PH data 6921.04
123.00 1648.20 2072.11 4290.54
270.33 PH data 4977.52
123.00 1512.90 1764.43 3673.69
231.4 PH data 4281.32
123.00 1210.32 1517.12 3153.99
192.19 PH data 3658.12
123.00 669.12 905.11 1924.63
157.63 PH data 2354.3
123.00 487.08 601.19 1305.07
125.04 PH data 1657.84
0.00
0
0.00
0
123.00 487.08 581.43 1253.10
96.86 PH data 1537.06
123.00 309.96 378.34 837.99
71.54 PH data 1062.38
123.00 295.20 342.93 761.96
49.72 PH data 937.5
123.00 167.28 202.13 470.79
39.53 PH data 616.38
0.00
0
0.00
0
130.00 176.80 204.99 204.99
30.44 PH data 60.88
130.00 88.40 111.99 111.99
24.06 PH data 48.12
130.00 88.40 111.99 111.99
559.9375 559.9375
Amount Dia Weight Rate Amount lowering DI tee DI A/F TEES TAKEN FRO
1755 80 x 40 13 106 1378 43.0164428571429 80x80x80 21.00
2025 100 x 50 15 106 1590 49.6343571428571 100x100x80 25.00
2160 100 x 65 15 106 1590 49.6343571428571 100x100x100 26.00
2835 125 x 80 18 106 1908 59.5612285714286 125x125x80 32.00
2970 125 x 100 20 106 2120 66.1791428571429 125x125x100 34.00
3645 125 x 125 22 106 2332 72.7970571428571 125x125x125 36.00
3915 150x40 17 106 1802 56.2522714285714 150x150x80 41.00
4185 200x125 35 106 3710 115.8135 150x150x100 42.00
4860 250x50 36 106 3816 119.122457142857 150x150x125 45.00
5670 400x50 67 106 7102 221.700128571429 150x150x150 47.00
4995 450x50 84 106 8904 277.9524 200x200x80 62.00
5265 700x100 219 119 26061 724.661614285714 200x200x100 63.00
700x150
6075 221 119 26299 731.279528571429 200x200x125 66.00
6885 700x250 238 119 28322 787.5318 200x200x150 68.00
7965 700x300 289 119 34391 956.288614285714 200x200x200 74.00
6480 900x150 361 119 42959 1194.53352857143 250x250x80 89.00
6750 250x250x100 90.00
7695 250x250x125 93.00
8640 250x250x150 96.00
9855 250x250x200 102.00
11205 250x250x250 109.00
7695 300x300x80 122.00
8100 300x300x100 124.00
9180 300x300x125 126.00
10125 300x300x150 129.00
11475 300x300x200 136.00
13095 321452000 300x300x250 143.00
14580 32.15 300x300x300 151.00
9180 11.26 350x350x200 169.00
9720 20.89 350x350x250 173.00
10935 350x350x300 188.00
12015 350x350x350 195.00
13500 400x400x200 211.00
14985 400x400x250 215.00
17820 400x400x300 232.00
18765 400x400x350 239.00
11340 400x400x400 246.00
12015 450x450x250 260.00
13230 450x450x300 277.00
14580 450x450x350 284.00
16200 450x450x400 290.00
17820 450x450x450 296.00
19710 500x500x250 315.00
21735 500x500x300 334.00
24030 500x500x350 342.00
14445 500x500x400 349.00
14445 500x500x450 356.00
17010 500x500x500 363.00
17415 600x600x300 466.00
22680 600x600x350 475.00
21735 600x600x400 485.00
24165 600x600x450 492.00
25110 600x600x500 499.00
28755 600x600x600 516.00
30645 80x80x40 18.13
22197 80x80x50 19.13
24843 100x100x40 22.05
25137 106 15 1590 100x100x50 23.05
26166 125x125x50 29.56
26607 150x150x50 38.00
33957 200x200x50 57.80
34839 350x350x100 161.08
35721 400x400x100 202.75
41895 450x450x100 249.76
42630 500x500x150 308.94
49833 6996.66 600x600x150 440.59
33222 16748.15 700x700x150 608.40
43953 9751.49 11872.405 400mm
64386 4875.745
38367
48804
74970
42630 28 10494.99
55713 31376.296
81879 20881.306 400mm
88053 10440.653 20935.643
53361
68355 31376 3 94128
104958
115101 -10440.357 -41816.357 -125449.071
65268
82467 -135889.428
1000 2319.17
900 2109.02
800 1771.4
750 1364.82
700 1247.66
600 974.6
500 825.54
450 661.15
400 581.62
350 532.72
300 429.43
250 310.54
200 275.51
150 233.35
125 194.9
100 156.58
80 117.12
50 117.12
40 117.12
Lowering tee
Assumtion 10 m
200 mm dia CI pipes 5m long (class ‘A’)
Weight = 2 x 257 kgs = 514 kgs = 5.14 quintal
(a) LABOUR:
Plumber 1st class day 0.102 710.00 72.42
Plumber 2nd class day 0.238 580.00 138.04
Man mazdoor day 1.330 545.00 724.85
(b) Cost for 10 metres 935.31
Rate per metre = b/10 93.53 51.4
Rate for 1 kg = b/514 1.820 0.549550416
1 Lowering C.I. / D.I. Pipes (all classes) and specials (fittings) with
s/s ends carefully into trenches and laying them true to alignment
PHE-LCIS-1 and gradient including all sundries but excluding cost and
conveyance of pipes from source of supply (Ref to specifications.
BIS No.3114/1994)
Note : The Labour charges for cost of Lowering & Laying per 1
kg weight shall be as per sub-analysis made for 200 mm dia CI
Pipes S/s ends.
Details of cost for 5m
i 80 mm dia pipe
Weight of 5m length = (79 +85.5 + 92)/3 = 85.5 kgs
(a) Labour charges for laying kgs 85.500 1.820 155.58
(b) Overheads & Contractors Profit
(c) Cost for 5 metres = a+b 155.58
Rate per metre = c/5 31.12
ii 100 mm dia pipe
Weight of 5m length = (100+109+117)/3 = 108.67 kgs
(a) Labour charges for laying kgs 108.670 1.820 197.74
(b) Overheads & Contractors Profit
(c) Cost for 5 metres = a+b 197.74
Rate per metre = c/5 39.55
iii 125 mm dia pipe
Weight of 5m length = (130+141+153)/3 = 141.33 kgs
(a) Labour charges for laying kgs 141.330 1.820 257.17
(b) Overheads & Contractors Profit
(c) Cost for 5 metres = a+b 257.17
Rate per metre = c/5 51.43
iv 150mm dia pipe
Weight of 5m length = (162+178+191)/3 = 177 kgs
(a) Labour charges for laying kgs 177.000 1.820 322.08
(b) Overheads & Contractors Profit
(c) Cost for 5 metres = a+b 322.08
Rate per metre = c/5 64.42
v 200 mm dia pipe
Weight of 5m length = (237+257+278)/3 = 257.33 kgs
(a) Labour charges for laying kgs 257.330 1.820 468.26
(b) Overheads & Contractors Profit
(c) Cost for 5 metres = a+b 468.26
Rate per metre = c/5 93.65
864
S No
PHE
Index-code Description Unit Quantity Rate Rs. Amt Rs. Remarks
1 2 3 4 5 6 7
vi 250 mm dia pipe
Weight of 5m length = (319+348+376)/3 = 347.67 kgs
(a) Labour charges for laying kgs 347.670 1.820 632.64
(b) Overheads & Contractors Profit
(c) Cost for 5 metres = a+b 632.64
Rate per metre = c/5 126.53
vii 300 mm dia pipe
Weight of 5m length = (412+450+487)/3 = 449.67 kgs
(a) Labour charges for laying kgs 449.670 1.820 818.25
(b) Overheads & Contractors Profit
(c) Cost for 5 metres = a+b 818.25
Rate per metre = c/5 163.65
viii 350 mm dia pipe
Weight of 5m length =(519+563+610)/3=564
(a) Labour charges for laying kgs 564.000 1.820 1026.29
(b) Overheads & Contractors Profit
(c) Cost for 5 metres = a+b 1026.29
Rate per metre = c/5 205.26
ix 400 mm dia pipe
Weight of 5m length =(631+690+744)/3=688.33
(a) Labour charges for laying kgs 688.330 1.820 1252.53
(b) Overheads & Contractors Profit
(c) Cost for 5 metres = a+b 1252.53
Rate per metre = c/5 250.51
x 450mm dia pipe s/s for 5m
Weight of 5m length =(761+836+901)/3=832.67
(a) Labour charges for laying kgs 832.670 1.820 1515.18
(b) Overheads & Contractors Profit
(c) Cost for 5 metres = a+b 1515.18
Rate per metre = c/5 303.04
xi 500 mm dia pipe
Weight of 5m length =(892+971+1049)/3=970.67
(a) Labour charges for laying kgs 970.670 1.820 1766.30
(b) Overheads & Contractors Profit
(c) Cost for 5 metres = a+b 1766.30
Rate per metre = c/5 353.26
xii 600 mm dia pipe
Weight of 5m length =(1188+1296+1404)/3=1296
(a) Labour charges for laying kgs 1296.000
(b) Overheads & Contractors Profit
(c) Cost for 5 metres = a+b
Rate per metre = c/5
xiii 700mm dia pipe s/s for 5m
Weight of 5m length =(1533+1675+1808)/3=1672
(a) Labour charges for laying kgs 1672.000
(b) Overheads & Contractors Profit
(c) Cost for 5 metres = a+b
Rate per metre = c/5
xiv 750 mm dia pipe
Weight of 5m length =(1718+1876+2029)/3=1874.33
(a) Labour charges for laying kgs 1874.330
(b) Overheads & Contractors Profit
(c) Cost for 5 metres = a+b
Rate per metre = c/5
xv 800 mm dia pipe
Weight of 5m length =(1922+2093+2263)/3=2092.67
(a) Labour charges for laying kgs 2092.670
(b) Overheads & Contractors Profit
(c) Cost for 5 metres = a+b
Rate per metre = c/5
865
S No
PHE
Index-code Description Unit Quantity Rate Rs. Amt Rs. Remarks
1 2 3 4 5 6 7
xvi 900 mm dia pipe
Weight of 5m length =(2342+2544+2766)/3=2554
(a) Labour charges for laying kgs 2544.000
(b) Overheads & Contractors Profit
(c) Cost for 5 metres = a+b
Rate per metre = c/5
xvii 1000 mm dia pipe
Weight of 5m length =(2814+3072+3318)/3=3068
(a) Labour charges for laying kgs 3068.000
(b) Overheads & Contractors Profit
(c) Cost for 5 metres = a+b
Rate per metre = c/5
2 Lowering C.I. / D.I. Pipes (all classes) and specials (fittings) with flanged
ends carefully into trench and laying them true to alignment and gradient
including all sundries but excluding cost and conveyance of pipes from
PHE-LCIF-2 source of supply. (Reference to specifications. BIS No.3114/1994)
Note : The cost of lowering and laying is taken as per sub analysis made
for S/S ends.
Details of cost for 10m
i 80 mm dia pipe
Weight of 1m length = 19.8+(2x3.7)/2.75 = 22.49 kgs
(a) Labour charges for laying kgs 22.490 1.820 40.92
(b) Overheads & Contractors Profit
Rate per metre
ii 100 mm dia pipe
Weight of 1m length = 25.4+(2x4.2)/2.75 = 28.45 kgs
(a) Labour charges for laying kgs 28.450 1.820 51.77
(b) Overheads & Contractors Profit
Rate per metre
iii 125 mm dia pipe
Weight of 1m length = 33.1+(2x5.3)/2.75 = 36.95 kgs
(a) Labour charges for laying kgs 36.950 1.820 67.24
(b) Overheads & Contractors Profit
Rate per metre
iv 150mm dia pipe
Weight of 1m length = 41.6+(2x6.7)/2.75 = 46.47 kgs
(a) Labour charges for laying kgs 46.470 1.820 84.56
(b) Overheads & Contractors Profit
Rate per metre
v 200 mm dia pipe
Weight of 1m length = 60.1+(2x9.3)/2.75 = 66.86 kgs
(a) Labour charges for laying kgs 66.860 1.820 121.66
(b) Overheads & Contractors Profit
Rate per metre
vi 250 mm dia pipe
Weight of 1m length = 81.8+(2x12)/2.75 = 90.53 kgs
(a) Labour charges for laying kgs 90.530 1.820 164.73
(b) Overheads & Contractors Profit
Rate per metre
vii 300 mm dia pipe
Weight of 1m length = 106.1+(2x14.8)/2.75 = 116.86 kgs
(a) Labour charges for laying kgs 116.860 1.820 212.65
(b) Overheads & Contractors Profit
Rate per metre
viii 350 mm dia pipe
Weight of 1m length = 133.5+(2x19)/2.75 = 147.32 kgs
(a) Labour charges for laying kgs 147.320 1.820 268.07
(b) Overheads & Contractors Profit
Rate per metre
866
S No
PHE
Index-code Description Unit Quantity Rate Rs. Amt Rs. Remarks
1 2 3 4 5 6 7
ix 400 mm dia pipe
Weight of 1m length = 162.6+(2x23.4)/2.75 = 179.62 kgs
(a) Labour charges for laying kgs 179.620 1.820 326.85
(b) Overheads & Contractors Profit
Rate per metre
x 450mm dia pipe
Weight of 1m length = 197+(2x26.5)/2.75 = 216.27 kgs
(a) Labour charges for laying kgs 216.270 1.820 393.54
(b) Overheads & Contractors Profit
Rate per metre
xi 500 mm dia pipe
Weight of 1m length = 229.3+(2x32.1)/2.75 = 252.65 kgs
(a) Labour charges for laying kgs 252.650 1.820 459.74
(b) Overheads & Contractors Profit
Rate per metre
xii 600 mm dia pipe
Weight of 1m length = 306.5+(2x44)/2.75 = 338.5 kgs
(a) Labour charges for laying kgs 338.500 1.820 615.96
(b) Overheads & Contractors Profit
Rate per metre
xiii 700mm dia pipe s/s for 5m
Weight of 1m length = 394.3+(2x59.9)/2.75 = 437.86 kgs
(a) Labour charges for laying kgs 437.860
(b) Overheads & Contractors Profit
Rate per metre
xiv 750 mm dia pipe
Weight of 1m length = 443.8+(2x59.7)/2.75 = 494.49 kgs
(a) Labour charges for laying kgs 494.490
(b) Overheads & Contractors Profit
Rate per metre
PHE-LCIF-2A 2A Sub Analysis : (Basic Data)
OBSERVED DATA FOR TESTING OF 450 MM DIA PSC MAIN :
Pumping main to Hydralic field test pressure including
transportation of Water with minimum lead of 500 M
(Length = 500 Mts) taking out put / 500 Mts. Unit = 1 Rmt.
Labour
Fitters (2 x 3 days)
Fitters I Class day 3.000 660.00 1980.00
Fitters II Class day 3.000 550.00 1650.00
Machinery
Hire chargers for Hydralic field test pressure testing including days 3.000 1746.30 5238.90
transportation of water @ Rs. 1200/- (1000+200) / day
Materials
Pressure guage Nos 0.050 693.00 34.65
3/4" G.I. Pipe (20 mm) RM 3.000 162.00 486.00
Specials Ls 94.00 94.00
Dummies No. 0.100 0.00
Diesel (2 Lts. / Hr) 30 Hrs. Lts. 60.000 97.82 5869.20
(T) Total Rate per 500 Mts. 15352.75
(r) Rate per 1 Rmt for 450 mm dia 30.71
(R) Rate per 1 Rmt for 10 mm dia = (10/450) x r
Note : Proportionate Testing Charges may be arrived,
keeping the diametre of pipe based on this analysis, for an
varities of pipes for various Dia Pipes.
867
S No
PHE
Index-code Description Unit Quantity Rate Rs. Amt Rs. Remarks
1 2 3 4 5 6 7
4 Jointing C.I., D.I. pipes and fittings with rubber gasket (push-on-
joint), excluding the cost of the gasket but including all sundries
filling with water, with a water lead up to 500m and testing to
PHE-JCIR-4 required pressure, etc. complete Reference to specifications IS
3114/1994/12888/1987
868
S No
PHE
Index-code Description Unit Quantity Rate Rs. Amt Rs. Remarks
1 2 3 4 5 6 7
ii 100 mm dia pipe
a) Labour
Plumber 2nd class day 0.500 580.00 290.00
Man mazdoor day 1.000 545.00 545.00
b) Material
Rubber gasket each 1.000 111.00 111.00
c) Testing
Testing of Pipelines with required pressure as per relevant IS rm 50.000 30.71 1535.28
Specification including filling with water with a water lead upto
500 M, including hire charges of testing equipment, labour and
Materials needed for testing (as per Sub Analysis 2 A)
869
S No
PHE
Index-code Description Unit Quantity Rate Rs. Amt Rs. Remarks
1 2 3 4 5 6 7
v 200 mm dia pipe
a) Labour
Plumber 2nd class day 0.600 580.00 348.00
Man mazdoor day 1.100 545.00 599.50
b) Material
Rubber gasket each 1.000 198.00 198.00
c) Testing
Testing of Pipelines with required pressure as per relevant IS rm 50.000 30.71 1535.28
Specification including filling with water with a water lead upto
500 M, including hire charges of testing equipment, labour and
Materials needed for testing (as per Sub Analysis 2 A)
870
S No
PHE
Index-code Description Unit Quantity Rate Rs. Amt Rs. Remarks
1 2 3 4 5 6 7
viii 350 mm dia pipe
a) Labour
Plumber 2nd class day 0.900 580.00 522.00
Man mazdoor day 1.500 545.00 817.50
b) Material
Rubber gasket each 1.000 425.00 425.00
c) Testing
Testing of Pipelines with required pressure as per relevant IS rm 50.000 30.71 1535.28
Specification including filling with water with a water lead upto
500 M, including hire charges of testing equipment, labour and
Materials needed for testing (as per Sub Analysis 2 A)
871
S No
PHE
Index-code Description Unit Quantity Rate Rs. Amt Rs. Remarks
1 2 3 4 5 6 7
x 500 mm dia pipe
a) Labour
Plumber 2nd class day 1.300 580.00 754.00
Man mazdoor day 1.800 545.00 981.00
b) Material
Rubber gasket each 1.000 690.00 690.00
c) Testing
Testing of Pipelines with required pressure as per relevant IS rm 50.000 30.71 1535.28
Specification including filling with water with a water lead upto
500 M, including hire charges of testing equipment, labour and
Materials needed for testing (as per Sub Analysis 2 A)
872
S No
PHE
Index-code Description Unit Quantity Rate Rs. Amt Rs. Remarks
1 2 3 4 5 6 7
xiii 700 mm dia pipe
a) Labour
Plumber 2nd class day 1.700
Man mazdoor day 2.200
b) Material
Rubber gasket each
c) Testing
Testing of Pipelines with required pressure as per relevant IS rm 50.000
Specification including filling with water with a water lead upto
500 M, including hire charges of testing equipment, labour and
Materials needed for testing (as per Sub Analysis 2 A)
873
S No
PHE
Index-code Description Unit Quantity Rate Rs. Amt Rs. Remarks
1 2 3 4 5 6 7
xxi 900 mm dia pipe
a) Labour
Plumber 1st class day 2.750
Plumber 2nd class day 5.500
Foreman (work inspector) Non technical day 0.700
b) Material
Rubber gasket each
c) Testing
Testing of Pipelines with required pressure as per relevant IS rm 50.000
Specification including filling with water with a water lead upto
500 M, including hire charges of testing equipment, labour and
Materials needed for testing (as per Sub Analysis 2 A)
874
S No
PHE
Index-code Description Unit Quantity Rate Rs. Amt Rs. Remarks
1 2 3 4 5 6 7
(e) Add for water charges @ 1% on Labour & Testing
Charges
(f) Total = d+e+f
(g) Overheads & Contractors Profit
(h) Cost for 10 joints (f+g)
Rate per joint = h/10
ii 100 mm dia pipe
a) Labour
Plumber 1st class day 0.150
Plumber 2nd class day 0.350
Man mazdoor day 1.000
b) Material
Bolts and nuts 16mm dia 60mm long kg 13.600
Rubber insertion 5mm thick kg 2.540
White lead
c) Testing
Testing of Pipelines with required pressure as per relevant IS rm 27.500
Specification including filling with water with a water lead upto
500 M, including hire charges of testing equipment, labour and
Materials needed for testing (as per Sub Analysis 2 A)
875
S No
PHE
Index-code Description Unit Quantity Rate Rs. Amt Rs. Remarks
1 2 3 4 5 6 7
c) Testing
Testing of Pipelines with required pressure as per relevant IS rm 27.500
Specification including filling with water with a water lead upto
500 M, including hire charges of testing equipment, labour and
Materials needed for testing (as per Sub Analysis 2 A)
876
S No
PHE
Index-code Description Unit Quantity Rate Rs. Amt Rs. Remarks
1 2 3 4 5 6 7
vii 300 mm dia pipe
a) Labour
Plumber 1st class day 0.240
Plumber 2nd class day 0.560
Man mazdoor day 1.200
b) Material
Bolts and nuts 20mm dia 75mm long kg 39.600
Rubber insertion 5mm thick kg 10.280
White lead
c) Testing
Testing of Pipelines with required pressure as per relevant IS rm 27.500
Specification including filling with water with a water lead upto 500 M,
including hire charges of testing equipment, labour and Materials needed
for testing (as per Sub Analysis 2 A)
877
S No
PHE
Index-code Description Unit Quantity Rate Rs. Amt Rs. Remarks
1 2 3 4 5 6 7
Plumber 1st class day 0.360
Plumber 2nd class day 0.840
Man mazdoor day 1.700
b) Material
Bolts and nuts 24mm dia 85mm long kg 123.000
Rubber insertion 8mm thick kg 22.660
White lead
c) Testing
Testing of Pipelines with required pressure as per relevant IS rm 27.500
Specification including filling with water with a water lead upto 500 M,
including hire charges of testing equipment, labour and Materials needed
for testing (as per Sub Analysis 2 A)
878
S No
PHE
Index-code Description Unit Quantity Rate Rs. Amt Rs. Remarks
1 2 3 4 5 6 7
xiii 700 mm dia pipe
a) Labour
Plumber 1st class day 0.510
Plumber 2nd class day 1.190
Man mazdoor day 2.200
b) Material
Bolts and nuts 24mm dia 90mm long kg 244.800
Rubber insertion 8mm thick kg 68.910
White lead
c) Testing
Testing of Pipelines with required pressure as per relevant IS rm 27.500
Specification including filling with water with a water lead upto
500 M, including hire charges of testing equipment, labour and
Materials needed for testing (as per Sub Analysis 2 A)
Unit= 1 rmt
Taking out put 100 rmt
i 80 mm dia
a) Labour
Mason 1st class day 0.780
Mason 2nd class day 1.800
Man mazdoor day 5.000
Woman mazdoor(water carrier) day 1.300
b) Material
Rubber rings conforming BIS 5382/1985 each 50.000
879
S No
PHE
Index-code Description Unit Quantity Rate Rs. Amt Rs. Remarks
1 2 3 4 5 6 7
c) Testing
Testing of Pipelines with required pressure as per relevant IS rm 100.000
Specification including filling with water with a water lead upto
500 M, including hire charges of testing equipment, labour and
Materials needed for testing (as per Sub Analysis 2 A)
880
S No
PHE
Index-code Description Unit Quantity Rate Rs. Amt Rs. Remarks
1 2 3 4 5 6 7
iv 200 mm dia
a) Labour
Mason 1st class day 1.170
Mason 2nd class day 2.730
Man mazdoor day 7.800
Woman mazdoor(water carrier) day 1.600
b) Material
Rubber rings conforming BIS 5382/1985 each 50.000
c) Testing
Testing of Pipelines with required pressure as per relevant IS rm 100.000
Specification including filling with water with a water lead upto
500 M, including hire charges of testing equipment, labour and
Materials needed for testing (as per Sub Analysis 2 A)
881
S No
PHE
Index-code Description Unit Quantity Rate Rs. Amt Rs. Remarks
1 2 3 4 5 6 7
vii 300 mm dia
a) Labour
Mason 1st class day 1.750
Mason 2nd class day 4.140
Man mazdoor day 11.600
Woman mazdoor(water carrier) day 2.300
b) Material
Rubber rings conforming BIS 5382/1985 each 40.000
c) Testing
Testing of Pipelines with required pressure as per relevant IS rm 100.000
Specification including filling with water with a water lead upto 500 M,
including hire charges of testing equipment, labour and Materials needed
for testing (as per Sub Analysis 2 A)
882
S No
PHE
Index-code Description Unit Quantity Rate Rs. Amt Rs. Remarks
1 2 3 4 5 6 7
x 450 mm dia
a) Labour
Mason 1st class day 2.250
Mason 2nd class day 5.250
Man mazdoor day 15.000
Woman mazdoor(water carrier) day 3.300
b) Material
Rubber rings conforming BIS 5382/1985 each 40.000
c) Testing
Testing of Pipelines with required pressure as per relevant IS rm 100.000
Specification including filling with water with a water lead upto 500 M,
including hire charges of testing equipment, labour and Materials needed
for testing (as per Sub Analysis 2 A)
883
S No
PHE
Index-code Description Unit Quantity Rate Rs. Amt Rs. Remarks
1 2 3 4 5 6 7
7 Lowering and Jointing G.I. pipes and specials / fittings including
excavation of trench of 0.5m width and 0.50 m depth in all soils except
rock requiring blasting and refilling trenches after laying and jointing pipes
PHE-LJGI-7 and also including cost of jointing materials but excluding the cost of
pipes. Reference to specifications. BIS No.783/85
884
S No
PHE
Index-code Description Unit Quantity Rate Rs. Amt Rs. Remarks
1 2 3 4 5 6 7
iv 32mm dia nominal bore
a) Labour
Plumber 2nd class day 0.120
Man mazdoor day 0.250
E.W.Excavation & refilling 10x0.50x0.50=2.50cum cum 2.500
b) Material
G.I. pipes m 10.000
white lead, hemp yarn, oil etc. L.S.
c) Machinery
Nil
(d) Total = a+b+c
(e) Add for water charges @ 1% on Labour & Testing
Charges
(f) Total = d+e
(g) Overheads & Contractors Profit
(h) Cost for 100 rmt (f+g)
Rate per rmt = h/100
v 40mm dia nominal bore
a) Labour
Plumber 2nd class day 0.160
Man mazdoor day 0.330
E.W.Excavation & refilling 10x0.50x0.50=2.50cum cum 2.500
b) Material
G.I. pipes m 10.000
white lead, hemp yarn, oil etc. L.S.
c) Machinery
Nil
(d) Total = a+b+c
(e) Add for water charges @ 1% on Labour & Testing
Charges
(f) Total = d+e
(g) Overheads & Contractors Profit
(h) Cost for 100 rmt (f+g)
Rate per rmt = h/100
vi 50mm dia nominal bore
a) Labour
Plumber 2nd class day 0.160
Man mazdoor day 0.330
E.W.Excavation & refilling 10x0.50x0.50=2.50cum cum 2.500
b) Material
G.I. pipes m 10.000
white lead, hemp yarn, oil etc. L.S.
c) Machinery
Nil
(d) Total = a+b+c
(e) Add for water charges @ 1% on Labour & Testing
Charges
(f) Total = d+e
(g) Overheads & Contractors Profit
(h) Cost for 100 rmt (f+g)
Rate per rmt = h/100
885
S No
PHE
Index-code Description Unit Quantity Rate Rs. Amt Rs. Remarks
1 2 3 4 5 6 7
vii 65mm dia nominal bore
a) Labour
Plumber 2nd class day 0.250
Man mazdoor day 0.660
E.W.Excavation & refilling 10x0.50x0.50=2.50cum cum 2.500
b) Material
G.I. pipes m 10.000
white lead, hemp yarn, oil etc. L.S.
c) Machinery
Nil
(d) Total = a+b+c
(e) Add for water charges @ 1% on Labour & Testing
Charges
(f) Total = d+e
(g) Overheads & Contractors Profit
(h) Cost for 100 rmt (f+g)
Rate per rmt = h/100
viii 80mm dia nominal bore
a) Labour
Plumber 2nd class day 0.250
Man mazdoor day 0.660
E.W.Excavation & refilling 10x0.50x0.50=2.50cum cum 2.500
b) Material
G.I. pipes m 10.000
white lead, hemp yarn, oil etc. L.S.
c) Machinery
Nil
(d) Total = a+b+c
(e) Add for water charges @ 1% on Labour & Testing
Charges
(f) Total = d+e
(g) Overheads & Contractors Profit
(h) Cost for 100 rmt (f+g)
Rate per rmt = h/100
ix 100mm dia nominal bore
a) Labour
Plumber 2nd class day 0.370
Man mazdoor day 0.970
E.W.Excavation & refilling 10x0.50x0.50=2.50cum cum 2.500
b) Material
G.I. pipes m 10.000
white lead, hemp yarn, oil etc. L.S.
c) Machinery
Nil
(d) Total = a+b+c
(e) Add for water charges @ 1% on Labour & Testing Charges
886
S No
PHE
Index-code Description Unit Quantity Rate Rs. Amt Rs. Remarks
1 2 3 4 5 6 7
(e) Add for water charges @ 1% on Labour & Testing
Charges
(f) Total = d+e
(g) Overheads & Contractors Profit
(h) Cost for 100 rmt (f+g)
Rate per rmt = h/100
8 Making connection of G.I. distribution branch with G.I. main by
providing and fixing tee, including cutting and threading the pipes
PHE-GIDM-8 and fixing tee etc., complete. Reference to specifications. BIS
No.783/85
887
S No
PHE
Index-code Description Unit Quantity Rate Rs. Amt Rs. Remarks
1 2 3 4 5 6 7
9 Lowering and laying AC pressure pipes (class 5 & 10) in ready
made trenches true to alignment and gradient including all
PHE-LACP-9 sundries but excluding conveyance from source of supply.
Reference to specifications BIS 6530/72
Details of cost for 1rmt
Note : The Coat of lowring, laying is taken for 1 kg weight as per
sub-analysis made for CI SS ends.
A Class 10 & 15 pipes :
i 80 mm dia pipe
Weight of 1m length = (6.225+6.225)/2 = 6.225 kgs
(a) Labour charges for laying kgs 6.225
(b) Overheads & Contractors Profit
Rate per metre
ii 100 mm dia pipe
Weight of 1m length = (7.8+8.18)/2 = 7.99 kgs
(a) Labour charges for laying kgs 7.990
(b) Overheads & Contractors Profit
Rate per metre
iii 125 mm dia pipe
Weight of 1m length = (9.8+10.725)/2 = 10.262 kgs
(a) Labour charges for laying kgs 10.262
(b) Overheads & Contractors Profit
Rate per metre
iv 150 mm dia pipe
Weight of 1m length = (12.15+15.18)/2 = 13.665 kgs
(a) Labour charges for laying kgs 13.665
(b) Overheads & Contractors Profit
Rate per metre
v 200 mm dia pipe
Weight of 1m length = (19.1+25.3)/2 = 22.2 kgs
(a) Labour charges for laying kgs 22.200
(b) Overheads & Contractors Profit
Rate per metre
vi 250 mm dia pipe
Weight of 1m length = (24.9+32)/2 = 28.450 kgs
(a) Labour charges for laying kgs 28.450
(b) Overheads & Contractors Profit
Rate per metre
vii 300 mm dia pipe
Weight of 1m length = (32.2+44.925)/2 =38.562 kgs
(a) Labour charges for laying kgs 38.562
(b) Overheads & Contractors Profit
Rate per metre
viii 350 mm dia pipe
Weight of 1m length = (13.6+54.875)/2 = 47.237 kgs
(a) Labour charges for laying kgs 47.237
(b) Overheads & Contractors Profit
Rate per metre
ix 400 mm dia pipe
Weight of 1m length = (49.125+71.425)/2 =60.275 kgs
(a) Labour charges for laying kgs 60.275
(b) Overheads & Contractors Profit
Rate per metre
x 450 mm dia pipe
Weight of 1m length = (59.225+84.025)/2 = 71.625 kgs
(a) Labour charges for laying kgs 71.625
(b) Overheads & Contractors Profit
Rate per metre
888
S No
PHE
Index-code Description Unit Quantity Rate Rs. Amt Rs. Remarks
1 2 3 4 5 6 7
xi 500 mm dia pipe
Weight of 1m length = (73.2+104.25)/2 = 88.725 kgs
(a) Labour charges for laying kgs 88.725
(b) Overheads & Contractors Profit
Rate per metre
xii 600 mm dia pipe
Weight of 1m length = (102.5+148.025)/2 = 125.262 kgs
(a) Labour charges for laying kgs 125.262
(b) Overheads & Contractors Profit
Rate per metre
B Class 20 & 25 pipes :
i 80 mm dia pipe
Weight of 1m length = (6.23+8.525)/2 = 7.378 kgs
(a) Labour charges for laying kgs 7.378
(b) Overheads & Contractors Profit
Rate per metre
ii 100 mm dia pipe
Weight of 1m length = (10.35+12.825)/2 =11.587 kgs
(a) Labour charges for laying kgs 11.587
(b) Overheads & Contractors Profit
Rate per metre
iii 125 mm dia pipe
Weight of 1m length = (13.35+16.825)/2 = 15.087 kgs
(a) Labour charges for laying kgs 15.087
(b) Overheads & Contractors Profit
Rate per metre
iv 150 mm dia pipe
Weight of 1m length = (18.9+23.65)/2 = 21.275 kgs
(a) Labour charges for laying kgs 21.275
(b) Overheads & Contractors Profit
Rate per metre
v 200 mm dia pipe
Weight of 1m length = (32.1+40.75)/2 = 36.425 kgs
(a) Labour charges for laying kgs 36.425
(b) Overheads & Contractors Profit
Rate per metre
vi 250 mm dia pipe
Weight of 1m length = (41.175+51.65)/2 = 46.412 kgs
(a) Labour charges for laying kgs 46.412
(b) Overheads & Contractors Profit
Rate per metre
vii 300 mm dia pipe
Weight of 1m length = (58.1+74.05)/2 = 66.075 kgs
(a) Labour charges for laying kgs 66.075
(b) Overheads & Contractors Profit
Rate per metre
viii 350 mm dia pipe
Weight of 1m length = (71.275+81.55)/2 = 76.412 kgs
(a) Labour charges for laying kgs 76.412
(b) Overheads & Contractors Profit
Rate per metre
ix 400 mm dia pipe
Weight of 1m length = (93.05+115.4)/2 = 104.225 kgs
(a) Labour charges for laying kgs 104.225
(b) Overheads & Contractors Profit
Rate per metre
x 450 mm dia pipe
Weight of 1m length = (111.275+139.45)/2 = 125.36 kgs
(a) Labour charges for laying kgs 125.360
(b) Overheads & Contractors Profit
Rate per metre
889
S No
PHE
Index-code Description Unit Quantity Rate Rs. Amt Rs. Remarks
1 2 3 4 5 6 7
xi 500 mm dia pipe
Weight of 1m length = (136.325+171.275)/2 = 153.8 kgs
(a) Labour charges for laying kgs 153.800
(b) Overheads & Contractors Profit
Rate per metre
xii 600 mm dia pipe
Weight of 1m length = (192.925+245.9)/2 = 219.412 kgs
(a) Labour charges for laying kgs 219.412
(b) Overheads & Contractors Profit
Rate per metre
10 Jointing A.C. pressure pipes with A.C. coupling or C.I.
detachable joints complete with rubber rings including filling with
water, with a water lead up to 500m and testing to required
pressure etc., complete but excluding cost of jointing materials
PHE-JACP-10 and conveyance of pipe from source of supply. Reference to
specifications BIS No.6530/72 (Labour Charges Only)
(Length = 500 Mts) taking out put / 500 Mts. Unit = 1 Rmt.
Machinery
Hire chargers for Hydralic field test pressure testing including days 3
transportation of water @ Rs. 1200/- (1000+200) / day
Materials
Pressure guage Nos 0.05
3/4" G.I. Pipe Mts 3
Specials Ls
Dummies No. 0.1
Diesel (2 Lts. / Hr) 30 Hrs. Lts. 60
(T) Total Rate per 500 Mts.
(r) Rate per 1 Rmt for 450 mm dia
(R) Rate per 1 Rmt for 10 mm dia = (10/450) x r
i 80 mm dia meter pipe
(a) Labour
Plumber 1st class day 0.180
Plumber 2nd class day 0.420
Man mazdoor day 1.600
Total
(b) Machinery for Testing of Pipelines with required pressure rm 40.000
as per relevant IS Specification including hire charges of
testing equipment, labour and transportation of water upto
500 M lead Materials needed for testing (as per Sub Analysis
11 A)
890
S No
PHE
Index-code Description Unit Quantity Rate Rs. Amt Rs. Remarks
1 2 3 4 5 6 7
ii 100 mm dia meter pipe
(a) Labour
Plumber 1st class day 0.300
Plumber 2nd class day 0.700
Man mazdoor day 2.000
Total
(b) Machinery for Testing of Pipelines with required pressure rm 40.000
as per relevant IS Specification including hire charges of
testing equipment, labour and transportation of water upto
500 M lead Materials needed for testing (as per Sub Analysis
11 A)
891
S No
PHE
Index-code Description Unit Quantity Rate Rs. Amt Rs. Remarks
1 2 3 4 5 6 7
(c) Add for water charges @ 1% on Labour & Testing
Charges
(d) Total = a+b+c
(e) Overheads & Contractors Profit
(f) Cost for 10 joints = d+e
Rate per each joint = f/10
vi 250 mm dia meter pipe
(a) Labour
Plumber 1st class day 0.480
Plumber 2 class
nd day 1.120
Man mazdoor day 2.600
Total
(b) Machinery for Testing of Pipelines with required pressure rm 40.000
as per relevant IS Specification including hire charges of
testing equipment, labour and transportation of water upto
500 M lead Materials needed for testing (as per Sub Analysis
11 A)
892
S No
PHE
Index-code Description Unit Quantity Rate Rs. Amt Rs. Remarks
1 2 3 4 5 6 7
ix 400 mm dia meter pipe
(a) Labour
Plumber 1st class day 0.600
Plumber 2nd class day 1.400
Man mazdoor day 3.000
Total
(b) Machinery for Testing of Pipelines with required pressure rm 40.000
as per relevant IS Specification including hire charges of
testing equipment and transportation of water upto 500 M
lead Materials needed for testing (as per Sub Analysis 11 A)
893
S No
PHE
Index-code Description Unit Quantity Rate Rs. Amt Rs. Remarks
1 2 3 4 5 6 7
(c) Add for water charges @ 1% on Labour & Testing
Charges
(d) Total = a+b+c
(e) Overheads & Contractors Profit
(f) Cost for 10 joints = d+e
Rate per each joint = f/10
11 Lowering, laying, jointing and testing to hydralic test pressure
including cost of water with minimum water lead of 500m for
UPVC pressure pipes in ready made trenches true to alignment
PHE-LJUP-11 and gradient including all sundries but excluding cost &
conveyance of pipes from source of supply and jointing materials
as per BIS No. 7634 - Part III - 1975
Total
(b) Material
Add for Water charges at 1% on Labour & Testing Lt
(c) Overheads & Contractors Profit
(d) Total (a+b+c)
Rate per RM =d/500
Rate per 10 mm / 1rm
A All Classes pipes :
i 63 mm dia pipe
Weight of 1m length = (0.468+0.666+1.01)/3 =0.715 kgs
(a) Labour charges for laying, jointing & testing rm 6.300
(b) Overheads & Contractors Profit
Rate per metre a+b
ii 75 mm dia pipe
Weight of 1m length = (0.655+0.923+1.439)/3 =1.005 kgs
(a) Labour charges for laying, jointing & testing rm 7.500
(b) Overheads & Contractors Profit
Rate per metre a+b
iii 90 mm dia pipe
Weight of 1m length = (0.924+1.321+2.032)/3 =1.426 kgs
(a) Labour charges for laying, jointing & testing rm 9.000
(b) Overheads & Contractors Profit
Rate per metre a+b
iv 110 mm dia pipe
Weight of 1m length = (1.323+1.902+3.062)/3 =2.096 kgs
(a) Labour charges for laying, jointing & testing rm 11.000
(b) Overheads & Contractors Profit
Rate per metre a+b
v 125 mm dia pipe
Weight of 1m length = (1.722+2.511+3.929)/3 =2.72 kgs
(a) Labour charges for laying, jointing & testing rm 12.500
(b) Overheads & Contractors Profit
Rate per metre a+b
894
S No
PHE
Index-code Description Unit Quantity Rate Rs. Amt Rs. Remarks
1 2 3 4 5 6 7
vi 140 mm dia pipe
Weight of 1m length = (2.144+3.116+4.905)/3 =3.388 kgs
(a) Labour charges for laying, jointing & testing rm 14.000
(b) Overheads & Contractors Profit
Rate per metre a+b
vii 160 mm dia pipe
Weight of 1m length = (2.799+4.012+6.414)/3 =4.408 kgs
(a) Labour charges for laying, jointing & testing rm 16.000
(b) Overheads & Contractors Profit
Rate per metre a+b
viii 180 mm dia pipe
Weight of 1m length = (3.581+5.134+8.092)/3 =5.602 kgs
(a) Labour charges for laying, jointing & testing rm 18.000
(b) Overheads & Contractors Profit
Rate per metre a+b
ix 200 mm dia pipe
Weight of 1m length = (4.331+6.351+10.001)/3 =6.894 kgs
(a) Labour charges for laying, jointing & testing rm 20.000
(b) Overheads & Contractors Profit
Rate per metre a+b
x 225 mm dia pipe
Weight of 1m length = (5.511+7.975+12.675)/3 =8.72 kgs
(a) Labour charges for laying, jointing & testing rm 22.500
(b) Overheads & Contractors Profit
Rate per metre a+b
xi 250 mm dia pipe
Weight of 1m length = (6.674+9.886+15.666)/3 =10.742 kgs
(a) Labour charges for laying, jointing & testing rm 25.000
(b) Overheads & Contractors Profit
Rate per metre a+b
xii 280 mm dia pipe
Weight of 1m length = (8.453+12.404+19.616)/3 =13.491 kgs
895
S No
PHE
Index-code Description Unit Quantity Rate Rs. Amt Rs. Remarks
1 2 3 4 5 6 7
(b) Machinery
Hirecharges of Generator Set & Hydraulic Testing Equipment day 1.000
(c) Material
Kerosene Lt 4.000
Diesel Lt 8.000
Water for Testing Lt
Transport day 1.000
Overheads & Contractors Profit
(d) Total (a+b+c)
Rate per RM =d/480
ii 75 mm Dia
Taking output : Length - 456 m ; Joints - 38 Nos
(a) Labour
For lowering / sub surface transport
Mazdoor day 4.000
Jointing
Fitter day 1.000
Mazdoor day 2.000
Testing
Fitter day 1.000
Mazdoor day 2.000
Supervisor day 1.000
Total
(b) Machinery
Hire charges of Generator Set & Hydraulic testing equipment day 1.000
(c) Material
Kerosene Lt 4.000
Diesel Lt 8.000
Water for Testing Lt
Transport day 1.000
Overheads & Contractors Profit
(d) Total (a+b+c)
Rate per RM =d/456
iii 90 mm Dia
Taking output : Length - 432 m ; Joints - 36 Nos
(a) Labour
For lowering / sub surface transport
Mazdoor day 5.000
Jointing
Fitter day 1.000
Mazdoor day 2.000
Testing
Fitter day 1.000
Mazdoor day 2.000
Supervisor day 1.000
Total
(b) Machinery
Hire charges of Generator Set & Hydraulic testing equipment day 1.000
(c) Material
Kerosene Lt 5.000
Diesel Lt 8.000
Water for Testing Lt
Transport day 1.000
Overheads & Contractors Profit
(d) Total (a+b+c)
Rate per RM =d/432
iv 110 mm Dia
Taking output : Length - 384 m ; Joints - 32 Nos
(a) Labour
For lowering / sub surface transport
Mazdoor day 6.000
Jointing
Fitter day 1.000
Mazdoor day 2.000
896
S No
PHE
Index-code Description Unit Quantity Rate Rs. Amt Rs. Remarks
1 2 3 4 5 6 7
Testing
Fitter day 1.000
Mazdoor day 2.000
Supervisor day 1.000
Total
(b) Machinery
Hirecharges of Generator Set & Hydraulic Testing Equipment day 1.000
(c) Material
Kerosene Lt 6.000
Diesel Lt 8.000
Water for Testing Lt
Transport day 1.000
Overheads & Contractors Profit
(d) Total (a+b+c)
Rate per RM =d/384
v 125 mm Dia
Taking output : Length - 348 m ; Joints - 29 Nos
(a) Labour
For lowering / sub surface transport
Mazdoor day 7.000
Jointing
Fitter day 2.000
Mazdoor day 3.000
Testing
Fitter day 1.000
Mazdoor day 2.000
Supervisor day 1.000
Total
(b) Machinery
Hire charges of Generator Set & Hydraulic testing equipment day 1.000
(c) Material
Kerosene Lt 7.000
Diesel Lt 8.000
Water for Testing Lt
Transport day 1.000
Overheads & Contractors Profit
(d) Total (a+b+c)
Rate per RM =d/348
vi 140 mm Dia
Taking output : Length - 300 m ; Joints - 25 Nos
(a) Labour
For lowering / sub surface transport
Mazdoor day 7.000
Jointing
Fitter day 2.000
Mazdoor day 3.000
Testing
Fitter day 1.000
Mazdoor day 2.000
Supervisor day 1.000
Total
(b) Machinery
Hire charges of Generator Set & Hydraulic testing equipment day 1.000
(c) Material
Kerosene Lt 8.000
Diesel Lt 8.000
Water for Testing Lt
Transport day 1.000
Overheads & Contractors Profit
(d) Total (a+b+c)
Rate per RM =d/300
897
S No
PHE
Index-code Description Unit Quantity Rate Rs. Amt Rs. Remarks
1 2 3 4 5 6 7
vii 160 mm Dia
Taking output : Length - 303 m ; Joints - 25 Nos
(a) Labour
For lowering / sub surface transport
Mazdoor day 7.000
Jointing
Fitter day 2.000
Mazdoor day 4.000
Testing
Fitter day 1.000
Mazdoor day 2.000
Supervisor day 1.000
Total
(b) Machinery
Hire charges of Generator Set & Hydraulic testing equipment day 1.000
(c) Material
Kerosene Lt 9.000
Diesel Lt 8.000
Water for Testing Lt
Transport day 1.000
Overheads & Contractors Profit
(d) Total (a+b+c)
Rate per RM =d/303
viii 180 mm Dia
Taking output : Length - 240 m ; Joints - 20 Nos
(a) Labour
For lowering / sub surface transport
Mazdoor day 8.000
Jointing
Fitter day 2.000
Mazdoor day 4.000
Testing
Fitter day 1.000
Mazdoor day 2.000
Supervisor day 1.000
Total Labour
(b) Machinery
Hire charges of Generator Set & Hydraulic testing equipment day 1.000
(c) Material
Kerosene Lt 10.000
Diesel Lt 8.000
Water for Testing Lt
Transport day 1.000
Overheads & Contractors Profit
(d) Total (a+b+c)
Rate per RM =d/240
ix 200 mm Dia
Taking output : Length - 240 m ; Joints - 20 Nos
(a) Labour
For lowering / sub surface transport
Mazdoor day 10.000
Jointing
Fitter day 2.000
Mazdoor day 6.000
Testing
Fitter day 1.000
Mazdoor day 2.000
Supervisor day 1.000
Total
(b) Machinery
Hire charges of Generator Set & Hydraulic testing equipment day 1.000
(c) Material
Kerosene Lt 11.000
Diesel Lt 8.000
Water for Testing Lt
Transport day 1.000
Overheads & Contractors Profit
(d) Total (a+b+c)
Rate per RM =d/240
x 225 mm Dia
Taking output : Length - 216 m ; Joints -18 Nos
(a) Labour
898
S No
PHE
Index-code Description Unit Quantity Rate Rs. Amt Rs. Remarks
1 2 3 4 5 6 7
For lowering / sub surface transport
Mazdoor day 10.000
Jointing
Fitter day 2.000
Mazdoor day 6.000
Testing
Fitter day 1.000
Mazdoor day 2.000
Supervisor day 1.000
Total
(b) Machinery
Hire charges of Generator Set & Hydraulic testing equipment day 1.000
(c) Material
Kerosene Lt 12.000
Diesel Lt 8.000
Water for Testing Lt
Transport day 1.000
Overheads & Contractors Profit
(d) Total (a+b+c)
Rate per RM =d/216
xi 250 mm Dia
Taking output : Length - 216 m ; Joints - 18 Nos
(a) Labour
For lowering / sub surface transport
Mazdoor day 11.000
Jointing
Fitter day 2.000
Mazdoor day 6.000
Testing
Fitter day 1.000
Mazdoor day 2.000
Supervisor day 1.000
Total
(b) Machinery
Hire charges of Generator Set & Hydraulic testing equipment day 1.000
(c) Material
Kerosene Lt 13.000
Diesel Lt 8.000
Water for Testing Lt
Transport day 1.000
Overheads & Contractors Profit
(d) Total (a+b+c)
Rate per RM =d/216
xii 280 mm Dia
Taking output : Length - 192 m ; Joints - 16 Nos
(a) Labour
For lowering / sub surface transport
Mazdoor day 12.000
Jointing
Fitter day 2.000
Mazdoor day 6.000
Testing
Fitter day 1.000
Mazdoor day 2.000
Supervisor day 1.000
Total
(b) Machinery
Hire charges of Generator Set & Hydraulic testing equipment day 1.000
(c) Material
Kerosene Lt 14.000
Diesel Lt 8.000
Water for Testing Lt
Transport day 1.000
Overheads & Contractors Profit
(d) Total (a+b+c)
Rate per RM =d/192
xiii 315 mm Dia
Taking output : Length - 180 m ; Joints - 15 Nos
(a) Labour
For lowering / sub surface transport
Mazdoor day 12.000
Jointing
899
S No
PHE
Index-code Description Unit Quantity Rate Rs. Amt Rs. Remarks
1 2 3 4 5 6 7
Fitter day 2.000
Mazdoor day 6.000
Testing
Fitter day 1.000
Mazdoor day 2.000
Supervisor day 1.000
Total
(b) Machinery
Hire charges of Generator Set & Hydraulic testing equipment day 1.000
(c) Material
Kerosene Lt 15.000
Diesel Lt 8.000
Water for Testing Lt
Transport day 1.000
Overheads & Contractors Profit
(d) Total (a+b+c)
Rate per RM =d/180
xiv 355 mm Dia
Taking output : Length - 144 m ; Joints - 12 Nos
(a) Labour
For lowering / sub surface transport
Mazdoor day 14.000
Jointing
Fitter day 2.000
Mazdoor day 8.000
Testing
Fitter day 1.000
Mazdoor day 2.000
Supervisor day 1.000
Total
(b) Machinery
Hire charges of Generator Set & Hydraulic testing equipment day 1.000
(c) Material
Kerosene Lt 16.000
Diesel Lt 8.000
Water for Testing Lt
Transport day 1.000
Overheads & Contractors Profit
(d) Total (a+b+c)
Rate per RM =d/144
13 Lowering and laying in ready made trench true to alignment and gradient,
jointing, and testing of stone ware pipes including cost of jointing material
such as cement mortar (1:1) proportion and hemp yarn but excluding
PHE-LJSW-13 cost and conveyance of pipe. (Reference to specifications BIS No.
6530/72)
900
S No
PHE
Index-code Description Unit Quantity Rate Rs. Amt Rs. Remarks
1 2 3 4 5 6 7
(d) Add for water charges @ 1% on Labour & Testing
Charges
(e) Total = c+d
(f) Overheads & Contractors Profit
(g) Cost for 30 m (e+f)
Rate per metre = g/30
ii 150 mm dia
(a) Labour
Mason 1st class day 0.900
Mason 2nd class day 2.100
Man mazdoor day 4.000
Woman mazdoor (Water carrier) day 1.000
b) Material
150 mm dia SW pipe 60cm long each 50.000
Cement for 50 joints =0.045 cum t 0.097
Sand = 0.045 cum cum 0.068
Spun yarn = 0.09x50=4.50 kgs 9.000
(c) Total = a+b
(d) Add for water charges @ 1% on Labour & Testing
Charges
(e) Total = c+d
(f) Overheads & Contractors Profit
(g) Cost for 30 m (e+f)
Rate per metre = g/30
iii 200 mm dia
(a) Labour
Mason 1st class day 1.050
Mason 2nd class day 2.450
Man mazdoor day 4.500
Woman mazdoor (Water carrier) day 1.250
b) Material
200 mm dia SW pipe 60cm long each 50.000
Cement for 50 joints =0.045 cum t 0.130
Sand = 0.045 cum cum 0.091
Spun yarn = 0.09x50=4.50 kgs 12.000
(c) Total = a+b
(d) Add for water charges @ 1% on Labour & Testing
Charges
(e) Total = c+d
(f) Overheads & Contractors Profit
(g) Cost for 30 m (e+f)
Rate per metre = g/30
iv 230 mm dia
(a) Labour
Mason 1st class day 1.200
Mason 2nd class day 2.800
Man mazdoor day 5.000
Woman mazdoor (Water carrier) day 1.500
b) Material
230 mm dia SW pipe 60cm long each 50.000
Cement for 50 joints =0.045 cum t 0.146
Sand = 0.045 cum cum 0.102
Spun yarn = 0.09x50=4.50 kgs 13.500
(c) Total = a+b
(d) Add for water charges @ 1% on Labour & Testing
Charges
(e) Total = c+d
(f) Overheads & Contractors Profit
(g) Cost for 30 m (e+f)
Rate per metre = g/30
901
S No
PHE
Index-code Description Unit Quantity Rate Rs. Amt Rs. Remarks
1 2 3 4 5 6 7
v 250 mm dia
(a) Labour
Mason 1st class day 1.350
Mason 2nd class day 3.150
Man mazdoor day 5.500
Woman mazdoor (Water carrier) day 1.500
b) Material
250 mm dia SW pipe 60cm long each 50.000
Cement for 50 joints =0.045 cum t 0.162
Sand = 0.045 cum cum 0.113
Spun yarn = 0.09x50=4.50 kgs 15.000
(c) Total = a+b
(d) Add for water charges @ 1% on Labour & Testing
Charges
(e) Total = c+d
(f) Overheads & Contractors Profit
(g) Cost for 30 m (e+f)
Rate per metre = g/30
vi 300 mm dia
(a) Labour
Mason 1st class day 1.500
Mason 2nd class day 3.500
Man mazdoor day 6.000
Woman mazdoor (Water carrier) day 1.500
b) Material
300 mm dia SW pipe 60cm long each 50.000
Cement for 50 joints =0.045 cum t 0.194
Sand = 0.045 cum cum 0.136
Spun yarn = 0.09x50=4.50 kgs 18.000
(c) Total = a+b
(d) Add for water charges @ 1% on Labour & Testing
Charges
(e) Total = c+d
(f) Overheads & Contractors Profit
(g) Cost for 30 m (e+f)
Rate per metre = g/30
vii 350 mm dia
(a) Labour
Mason 1st class day 1.650
Mason 2nd class day 3.850
Man mazdoor day 7.000
Woman mazdoor (Water carrier) day 1.750
b) Material
350 mm dia SW pipe 60cm long each 50.000
Cement for 50 joints =0.045 cum t 0.225
Sand = 0.045 cum cum 0.159
Spun yarn = 0.09x50=4.50 kgs 21.000
(c) Total = a+b
(d) Add for water charges @ 1% on Labour & Testing
Charges
(e) Total = c+d
(f) Overheads & Contractors Profit
(g) Cost for 30 m (e+f)
Rate per metre = g/30
902
S No
PHE
Index-code Description Unit Quantity Rate Rs. Amt Rs. Remarks
1 2 3 4 5 6 7
viii 400 mm dia
(a) Labour
Mason 1st class day 1.800
Mason 2nd class day 4.200
Man mazdoor day 8.000
Woman mazdoor (Water carrier) day 1.750
b) Material
400 mm dia SW pipe 60cm long each 50.000
Cement for 50 joints =0.045 cum t 0.256
Sand = 0.045 cum cum 0.181
Spun yarn = 0.09x50=4.50 kgs 24.000
(c) Total = a+b
(d) Add for water charges @ 1% on Labour & Testing
Charges
(e) Total = c+d
(f) Overheads & Contractors Profit
(g) Cost for 30 m (e+f)
Rate per metre = g/30
ix 450 mm dia
(a) Labour
Mason 1st class day 2.100
Mason 2nd class day 4.900
Man mazdoor day 10.000
Woman mazdoor (Water carrier) day 2.000
b) Material
450 mm dia SW pipe 60cm long each 50.000
Cement for 50 joints =0.045 cum t 0.293
Sand = 0.045 cum cum 0.204
Spun yarn = 0.09x50=4.50 kgs 27.000
(c) Total = a+b
(d) Add for water charges @ 1% on Labour & Testing
Charges
(e) Total = c+d
(f) Overheads & Contractors Profit
(g) Cost for 30 m (e+f)
Rate per metre = g/30
PHE-CISP- 14 Sub Analysis :
14(sub_analys Labour charges for laying in position S&S or flanged C.I. specials
is) such as tees, bends, collars tapers and caps etc
10 No. Tees of 200x150mm dia
Weight = 10x70kgs = 700 kgs
(a) Labour
Plumber 1st class day 0.465 710.00 330.15
Plumber 2nd class day 1.094 580.00 634.52
Man mazdoor day 2.480 545.00 1351.60
Cost for 700 kgs 2316.27
Cost for 1kg 3.31
15 Lowering, keeping in position and fixing C.I. sluice valves (with cap / with
PHE-CISV-15 hand wheel & reflex valves) excluding cost of bolts, nuts, rubber insertion,
sluice valve and tail pieces
Details of cost for 1No
i 80 mm dia meter
(a) Labour
Labour for laying Sluice Valve with cap, with hand wheel & reflex valves - kgs 35.470 3.31 117.37
Weight (32.3+34.1+40)/3=35.47
Overheads & Contractors Profit 15.98
Rate per 1 Sluice valve 133.35
ii 100 mm dia meter
(a) Labour
Labour for laying Sluice Valve with cap, with hand wheel & reflex kgs 47.100 3.31 155.85
valves - Weight (44.3+47+50)/3=47.1
(g) Overheads & Contractors Profit 21.22
Rate per 1 Sluice valve 177.07
903
S No
PHE
Index-code Description Unit Quantity Rate Rs. Amt Rs. Remarks
1 2 3 4 5 6 7
iii 125 mm dia meter
(a) Labour
Labour for laying Sluice Valve with cap, with hand wheel & reflex kgs 61.770 3.31 204.39
valves - Weight (56.3+59+70)/3=61.77
(g) Overheads & Contractors Profit 27.83
Rate per 1 Sluice valve 232.22
iv 150 mm dia meter
(a) Labour
Labour for laying Sluice Valve with cap, with hand wheel & reflex kgs 79.830 3.31 264.15
valves - (72.5+77+90)/3=79.83
(g) Overheads & Contractors Profit 35.96
Rate per 1 Sluice valve 300.12
v 200 mm dia meter
(a) Labour
Labour for laying Sluice Valve with cap, with hand wheel & reflex kgs 131.700 3.31 435.79
valves - (121.5+128.6+145)/3=131.7
(g) Overheads & Contractors Profit 59.33
Rate per 1 Sluice valve 495.12
vi 250 mm dia meter
Labour for laying Sluice Valve with cap, with hand wheel & reflex kgs 187.160 3.31 619.30
valves - (179.9+186.6+195)/3=187.16
(g) Overheads & Contractors Profit 84.32
Rate per 1 Sluice valve 703.62
vii 300 mm dia meter
(a) Labour
Labour for laying Sluice Valve with cap, with hand wheel & reflex kgs 266.460 3.31 881.70
valves - (242.4+257+300)/3=266.46
(g) Overheads & Contractors Profit 120.04
Rate per 1 Sluice valve 1001.75
viii 350 mm dia meter
(a) Labour
Labour for laying Sluice Valve with cap, with hand wheel & reflex kgs 450.000 3.31 1489.03
valves - (430+470)/2=450
Overheads & Contractors Profit 202.73
Rate per each 1691.76
ix 400 mm dia meter
(a) Labour
Labour for laying Sluice Valve with cap, with hand wheel & reflex kgs 552.500 3.31 1828.20
valves - (525+580)/2=552.5
Overheads & Contractors Profit 248.91
Rate per each 2077.11
x 450 mm dia meter
(a) Labour
Labour for laying Sluice Valve with cap, with hand wheel & reflex kgs 722.500 3.31 2390.72
valves - (635+810)/2=722.5
Overheads & Contractors Profit 325.50
Rate per each 2716.22
xi 500 mm dia meter
(a) Labour
Labour for laying Sluice Valve with cap, with hand wheel & reflex kgs 837.500 3.31 2771.25
valves - (775+900)/2=837.5
Overheads & Contractors Profit 377.31
Rate per each 3148.56
xii 600 mm dia meter
(a) Labour
Labour for laying Sluice Valve with cap, with hand wheel & reflex kgs 1422.500 3.31 4706.99
valves - (1220+1625)/2=1422.5
Overheads & Contractors Profit 640.86
Rate per each 5347.85
904
S No
PHE
Index-code Description Unit Quantity Rate Rs. Amt Rs. Remarks
1 2 3 4 5 6 7
16 Providing and fixing double acting air valves including boring the
A main threading the bore and fixing nipple etc.,excluding the cost
PHE-DAAV-16 of rubber insertions, bolts & nuts, air valve & flanged tail pieces
complete
Unit each
i 40 mm dia
(a) Labour
Lowering charges for air valve kgs 27.000
Boring main & threding etc
Plumber 2nd class day 0.140
Man mazdoor day 0.140
Overheads & Contractors Profit
Rate per each valve
ii 25 mm dia
(a) Labour
Lowering charges for air valve kgs 20.000
Boring main & threding etc
Plumber 2nd class day 0.110
Man mazdoor day 0.110
Overheads & Contractors Profit
Rate per each valve
17 Providing and fixing spindle fire hydrant with 65 mm outlet.
PHE-SFHD-17 Complete with bolts, nuts, and rubber insertion etc. complete but
excluding cost of Materials.
Details of cost for 1fire hydrants
i 65 mm dia
(a) Labour
Plumber 1st class day 0.750
Plumber 2 class
nd day 1.750
Man mazdoor day 4.000
Overheads & Contractors Profit
Rate per each fire hydrant
Note : For other sizes proportionately allow the Data.
18 Dismantling of spindle fire hydrant including stacking of useful
PHE-DSFH-18 materials within 50m lead
Details of cost for 10 Nos
65 mm dia
(a) Labour
Fitter 1st class day 0.750
Fitter 2nd class day 1.750
Man mazdoor day 4.000
Overheads & Contractors Profit
Rate per each
905
S No
PHE
Index-code Description Unit Quantity Rate Rs. Amt Rs. Remarks
1 2 3 4 5 6 7
19 Uprooting of C.I. pipes by melting lead, loosening the joints, separating
the pipes, hoisting and keeping within a lead of 10 metres but excluding
PHE-URCI-19 earth work excavation and refilling
906
S No
PHE
Index-code Description Unit Quantity Rate Rs. Amt Rs. Remarks
1 2 3 4 5 6 7
vi 250mm dia metre
(a) Labour
Assistant fitter(plumber 2nd class) day 1.300
Man mazdoor day 7.500
b) Material
For breacking lead coulked joints, melting lead etc.,
Fuel wood q 1.026
Kerosene oil litre 1.137
(c) Total = a+b
(d) Overheads & Contractors Profit
(e) Cost for 40.26 m (c+d)
Rate per each m = e/40.26
vii 300mm dia metre
(a) Labour
Assistant fitter(plumber 2nd class) day 1.500
Man mazdoor day 8.500
b) Material
For breacking lead coulked joints, melting lead etc.,
Fuel wood q 1.120
Kerosene oil litre 1.515
(c) Total = a+b
(d) Overheads & Contractors Profit
(e) Cost for 40.26 m (c+d)
Rate per each m = e/40.26
viii 350mm dia metre
(a) Labour
Assistant fitter(plumber 2nd class) day 1.750
Man mazdoor day 9.500
b) Material
For breacking lead coulked joints, melting lead etc.,
Fuel wood q 1.231
Kerosene oil litre 1.515
(c) Total = a+b
(d) Overheads & Contractors Profit
(e) Cost for 40.26 m (c+d)
Rate per each m = e/40.26
ix 400mm dia metre
(a) Labour
Assistant fitter(plumber 2nd class) day 2.000
Man mazdoor day 10.500
b) Material
For breacking lead coulked joints, melting lead etc.,
Fuel wood q 1.306
Kerosene oil litre 1.894
(c) Total = a+b
(d) Overheads & Contractors Profit
(e) Cost for 40.26 m (c+d)
Rate per each m = e/40.26
x 450mm dia metre
(a) Labour
Assistant fitter(plumber 2nd class) day 2.250
Man mazdoor day 11.500
b) Material
For breacking lead coulked joints, melting lead etc.,
Fuel wood q 1.400
Kerosene oil litre 2.273
(c) Total = a+b
(d) Overheads & Contractors Profit
(e) Cost for 40.26 m (c+d)
Rate per each m = e/40.26
907
S No
PHE
Index-code Description Unit Quantity Rate Rs. Amt Rs. Remarks
1 2 3 4 5 6 7
xi 500mm dia metre
(a) Labour
Assistant fitter(plumber 2nd class) day 2.500
Man mazdoor day 12.500
b) Material
For breacking lead coulked joints, melting lead etc.,
Fuel wood q 1.492
Kerosene oil litre 2.652
(c) Total = a+b
(d) Overheads & Contractors Profit
(e) Cost for 40.26 m (c+d)
Rate per each m = e/40.26
xii 600mm dia metre
(a) Labour
Assistant fitter(plumber 2nd class) day 3.000
Man mazdoor day 14.500
b) Material
For breacking lead coulked joints, melting lead etc.,
Fuel wood q 1.580
Kerosene oil litre 3.410
(c) Total = a+b
(d) Overheads & Contractors Profit
(e) Cost for 40.26 m (c+d)
Rate per each m = e/40.26
20 Uprooting of R.C.C. Pipes including breaking the collars, loosing
the joint, scraping the pipe, hoisting and keeping within a lead of
PHE-URRC-20 10 M but excluding earthwork excavation and refilling
908
S No
PHE
Index-code Description Unit Quantity Rate Rs. Amt Rs. Remarks
1 2 3 4 5 6 7
21 Uprooting of old S.W. pipes including breaking of joints and bed
concrete stacking of useful materials near the site with in 50m
PHE-URSW-21 lead and disposal of un serviceable materials in to municipal
dumps excluding the cost of earth work excavation. (Reference
to specifications BIS No.)
909
S No
PHE
Index-code Description Unit Quantity Rate Rs. Amt Rs. Remarks
1 2 3 4 5 6 7
viii 400mm dia metre
(a) Labour
Man mazdoor day 0.660
Women mazdoor day 0.750
(b) Overheads & Contractors Profit
(c) Cost for 10 m (a+b)
Rate per each m =c/10
ix 450mm dia metre
(a) Labour
Man mazdoor day 0.660
Women mazdoor day 0.810
(b) Overheads & Contractors Profit
(c) Cost for 10 m (a+b)
Rate per each m =c/10
22 Removing old G.I.pipes and specials / fittings and cleaning,
scraping the pipes, hoisting and keeping with in 50m lead but
PHE-URGI-22 excluding earth work excavation of trenches and refilling
910
S No
PHE
Index-code Description Unit Quantity Rate Rs. Amt Rs. Remarks
1 2 3 4 5 6 7
v 200 mm dia
(a) Labour
Asst. Fitter / Plumber 2nd class day 0.200
Man mazdoor day 0.200
(b) Overheads & Contractors Profit
Rate per each m
vi 250 mm dia
(a) Labour
Asst. Fitter / Plumber 2nd class day 0.250
Man mazdoor day 0.250
(b) Overheads & Contractors Profit
Rate per each m
vii 300 mm dia
(a) Labour
Asst. Fitter / Plumber 2nd class day 0.300
Man mazdoor day 0.300
(b) Overheads & Contractors Profit
Rate per each m
viii 350 mm dia
(a) Labour
Asst. Fitter / Plumber 2nd class day 0.350
Man mazdoor day 0.350
(b) Overheads & Contractors Profit
Rate per each m
ix 400 mm dia
(a) Labour
Asst. Fitter / Plumber 2nd class day 0.400
Man mazdoor day 0.400
(b) Overheads & Contractors Profit
Rate per each m
x 450 mm dia
(a) Labour
Asst. Fitter / Plumber 2nd class day 0.450
Man mazdoor day 0.450
(b) Overheads & Contractors Profit
Rate per each m
xi 500 mm dia
(a) Labour
Asst. Fitter / Plumber 2nd class day 0.500
Man mazdoor day 0.500
(b) Overheads & Contractors Profit
Rate per each m
xii 600 mm dia
(a) Labour
Asst. Fitter / Plumber 2nd class day 0.600
Man mazdoor day 0.600
(b) Overheads & Contractors Profit
Rate per each m
24 Drilling and tapping C.I./D.I. main and fixing brass screw down
PHE-DTCI-24 ferrule and C.I.mouth cover.(Labour charges only)
Details of cost for one no
i 15 mm dia
(a) Labour
Plumber day 0.130
(b) Overheads & Contractors Profit
Rate per each m
ii 20 mm dia
(a) Labour
Plumber day 0.150
(b) Overheads & Contractors Profit
Rate per each m
iii 25 mm dia
(a) Labour
911
S No
PHE
Index-code Description Unit Quantity Rate Rs. Amt Rs. Remarks
1 2 3 4 5 6 7
Plumber day 0.170
(b) Overheads & Contractors Profit
Rate per each m
PHE-SHST-25 25 Shoring and strutting of trenches for water and sewer lines
(A) Single staging from 0’ to 8’-0” ( 0 to 2.5 Metre)
Depth not exceeding 1.5 M
Details of cost for an area 30 M long and 1.5 M deep.
Area = 30 x 1.5 = 45 sqm
(a) Labour
Carpenter 2nd class day 0.570
Man mazdoor day 1.100
b) Material
Polling boards and ballies sqm
Requirement for 45 sqm :
Polling Boards of 250 mm x 35 mm (40 x 1.5 x 0.25 x 0.038) cum
Ballies 125 mm dia 1.5 mts long (60 x p x (0.125)2 / 4 x 1.5 cum
Deduct–Credit for materials after use @ 80% of the cost of materials =0.8
xX
c) Machinery
Nil
Overheads & Contractors Profit
(d) Cost for 45 sqm (a+b+c)
Rate per each sqm = d/45
(B) Double staging from 8’ to 14 ( 2.5 to 4.5 Metre)
Depth not exceeding 1.5 M
Details of cost for an area 30 M long and 1.5 M deep.
Area = 30 x 1.5 = 45 Sqm
(a) Labour
Carpenter 2nd class day 0.500
Man mazdoor day 1.320
b) Material
Polling boards and ballies sqm
Requirement for 45 sqm :
Polling Boards of 250 mm x 35 mm (40 x 1.5 x 0.25 x 0.038 = cum 0.110
0.57 cum)
Ballies 125 mm dia 1.5 mts long (60 x p x (0.125)2 / 4 x 1.5 = 1.1 cum 0.220
cum
Deduct – Credit for materials after use @ 80% of the cost of
materials = 0.8 x X
c) Machinery
Nil
Overheads & Contractors Profit
(d) Cost for 45 sqm (a+b+c)
Rate per each sqm = d/45
(C) Triple staging beyond 14’ for every 2 meter (beyond 4.5 M)
Depth not exceeding 1.5 M.
Note : Add for every 2 Mts (difference of single and double
staging) for staging beyond 4.5 mts.
26 Barricading, hoarding, lighting and watching etc., for water supply
PHE-BHLW-26 and sewerage works for trenches of depths upto 6’-0” (2 Meter)
below G.L
Taking output 3 Rmt
Material
Bamboos of 1 ½ ”dia 2.5 M long (5 ft c/c = 3 x 2.5) rmt 7.50
Baboom of 1 ½ ”dia 3.66 M long (5 ft c/c = 3x 3.66) rmt 10.98
Cost of Bamboos
(a) Usage of Material 5 times. Thus Cost of Material taken as
20%
912
S No
PHE
Index-code Description Unit Quantity Rate Rs. Amt Rs. Remarks
1 2 3 4 5 6 7
(b) Labour
Man mazdoor day 0.500
(c) Sundries for Coir rope, nails, @ 1%
(d) Sundries for lighting and watching etc at 1%
Overheads & Contractors Profit
Cost for 3rmt (a+b+c+d)
Rate per each rmt = (a+b+c+d)/3
27 Providing RCC spun vent shaft with cowl 140 mm and 200 mm internal
and external dia respectively at top, 300 and 450 mm internal and
external dia respectively at bottom and 9.10m overall length. Bottom 1.25
m below ground level fixed in a pit 90cmx90cm x150 cm with cement
concrete 1:4:8, 25cm in bed and minimum 20cm all-round with top 15cm
in cement concrete 1:2:4. Junction of vent shaft and concrete grouted with
PHE-RCVS-27 cement mortar 1:1 including making connection with sewer manhole with
150 mm dia metre cement concrete pipe of required length complete as
per standard design
914
S No
PHE
Index-code Description Unit Quantity Rate Rs. Amt Rs. Remarks
1 2 3 4 5 6 7
iii4.0 to 6.0 m below G.L. :
(a) Labour
Man mazdoor day 157.000
Sinkers day 48.000
Crane Operator day 12.000
b) Machinery
Hire charges for crane hour 96.000
Hire charges for Air compressor hour 102.000
Hire charges for Generator hour 96.000
Diesel L 1056.000
Overheads & Contractors Profit
c) Total
Rate per Rm = c/2
iv 6.0 to 8.0 m below G.L. :
(a) Labour
Man mazdoor day 195.000
Sinkers day 120.000
Crane Operator day 15.000
b) Machinery
Hire charges for crane hour 120.000
Hire charges for Air compressor hour 124.000
Hire charges for Generator hour 120.000
Diesel L 1334.000
Overheads & Contractors Profit
c) Total
Rate per Rm = c/2
v 8.0 to 10.0 m below G.L. :
(a) Labour
Man mazdoor day 272.000
Sinkers day 204.000
Crane Operator day 17.000
b) Machinery
Hire charges for crane hour 124.000
Hire charges for Air compressor hour 124.000
Hire charges for Generator hour 136.000
Diesel L 1344.000
Overheads & Contractors Profit
c) Total
Rate per Rm = c/2
vi 10.0 to 12.85 m below G.L. :
(a) Labour
Man mazdoor day 360.000
Sinkers day 288.000
Crane Operator day 24.000
b) Machinery
Hire charges for crane hour 192.000
Hire charges for Air compressor hour 198.000
Hire charges for Generator hour 160.000
Diesel L 2148.000
Overheads & Contractors Profit
c) Total
Rate per Rm = c/2.85
30 Well sinking in sandy and other loose soils under water either by
manual labour, divers or dredgers weighting the top of steining to
assist sinking etc., including dewatering and other incidental
PHE-WSPR-30 charges such as hire charges for mechanical equipment etc.,
complete upto 7 m dia (In Perennial Rivers only)
915
S No
PHE
Index-code Description Unit Quantity Rate Rs. Amt Rs. Remarks
1 2 3 4 5 6 7
Hire charges for crane hour 32.00
Hire charges for compressors hour 32.00
Diesel L 120.00
Overheads & Contractors Profit
c) Total
Rate per Rm = c/2
ii 2.0 to 4.0 m below G.L. :
(a) Labour
Man mazdoor day 40.000
Well sinkers day 80.000
b) Machinery
Hire charges of set of Helmets & Air circulating pipes / valves day 5.00
Hire charges for crane hour 40.00
Hire charges for compressors hour 40.00
Diesel L 150.00
Overheads & Contractors Profit
c) Total
Rate per Rm = c/2
iii 4.0 to 6.0 m below G.L. :
(a) Labour
Man mazdoor day 48.000
Well sinkers day 96.000
b) Machinery
Hire charges of set of Helmets & Air circulating pipes / valves day 6.00
Hire charges for crane hour 48.00
Hire charges for compressors hour 48.00
Diesel L 180.00
Overheads & Contractors Profit
c) Total
Rate per Rm = c/2
iv 6.0 to 8.0 m below G.L. :
(a) Labour
Man mazdoor day 56.000
Well sinkers day 112.000
b) Machinery
Hire charges of set of Helmets & Air circulating pipes / valves day 7.00
Hire charges for crane hour 56.00
Hire charges for compressors hour 56.00
Diesel L 210.00
Overheads & Contractors Profit
c) Total
Rate per Rm = c/2
v 8.0 to 10.0 m below G.L. :
(a) Labour
Man mazdoor day 64.000
Well sinkers day 128.000
b) Machinery
Hire charges of set of Helmets & Air circulating pipes / valves day 8.00
Hire charges for crane hour 64.00
Hire charges for compressors hour 64.00
Diesel L 240.00
Overheads & Contractors Profit
c) Total
Rate per Rm = c/2
Note : This data shall be adopted for well sinking in perennial rivers. For
other rivers, data available for 4.0 m dia infiltration well may be adopted
for guidance
916
S No
PHE
Index-code Description Unit Quantity Rate Rs. Amt Rs. Remarks
1 2 3 4 5 6 7
31 Curing of CC pavement for 21 days including cost and
PHE-CCCP-31 conveyance of water, labour charges, etc., complete
Areas Considered 3 . 5 x 100 mts = 350 sqm
Units = 1 sqm
Mud quantity is required = 14% of CC area x 5 cm
(a) Labour
Man mazdoor (21 x 2). day 42.000
b) Machinery
Carting earth for 3 kms cum 2.450
Hire charges for Water Drum (5 x 21 days) each 105.000
c) Material
Earth Work (100 x 3.5 x 14/100 x .05) cum 2.450
Supply of Water (240 Lts / cum / day) L 18900.000
Overheads & Contractors Profit
(d) Total = a+b+c
Rate per sqm =d/350
Note : 1. When Curing compound is used @ 1.97 kgs/cum, water
requirement is 206 Lts / cum per 14 days.
2. This data is for urban areas only
32 Cutting sheet rock including stocking of excavated material.
PHE-CSHR-32
Quality of sheet rock as per stock measurement = 36.53 cumm
(taking out put = 36.53 cum)
(a) Labour
Man mazdoor day 60.000
b) Machinery
Drilling of holes each 342.000
Hire charges for JCB hr 3.000
MS Nokkulu each 10.000
Overheads & Contractors Profit
(c) Total = a+b
Rate per cum =c/36.53
33 Excavation in Hard Rock (blasting prohibited)
PHE-EXRW-33
Excavation for roadway in hard rock (blasting prohibited) with
rock breakers including breaking rock, loading in tippers and
disposal with all lifts and lead upto 1000 metres, trimming
bottom and side slopes in accordance with requirements of lines,
grades and cross- sections as per Technical Specification Clause
302.3.5
917
S No
PHE
Index-code Description Unit Quantity Rate Rs. Amt Rs. Remarks
1 2 3 4 5 6 7
(B) Mechanical Means
Unit = cum
Taking output = 1 cum
a) Labour
Mate day -
Mazdoor (Unskilled) day 0.289
b) Machinery
Hydraulic excavator 0.9 cum with rock breaker attachment @ 6 hour 0.167
cum per hour
Tipper 5.5 cum capacity tipper, 1 trip per hour hour 0.180
Credit for excavated rock found suitable for use @ 50 per cent of cum 0.500
excavated quantity
Sundries on Labour
c&d) Overheads & Contractors Profit
Rate per cum = (a+b+c+d)
Note : 1. The quality and availability of rock shall be checked before affording
credit.
2. In case some rock is issued to the contractor at site, the item of carriage shall
be restricted/reduced to that extent.
3. Being small quantity, manual loading will be economical in this case and has
been provided accordingly.
34 Loading or Unloading materials such as C.I / D.I Pipes, R.C.C.
Pipes, P.V.C. pipes, A.C. Pressure pipes and Specials less than
PHE-LUSS-34 300 mm upto 4 mts in length including stacking.
918
S No
PHE
Index-code Description Unit Quantity Rate Rs. Amt Rs. Remarks
1 2 3 4 5 6 7
35 Loading or unloading materials such as C.I / D.I. Pipes, stone
ware pipes, R.C.C. pipes, A.C. Pressure pipes and specials from
PHE-LUMS-35 300 mm to 600 mm dia upto 4 mts in length including stacking.
919
S No
PHE
Index-code Description Unit Quantity Rate Rs. Amt Rs. Remarks
1 2 3 4 5 6 7
ii C.I. Pipes (load per truck = 3.85 T)
Taking Output = 1MT
a) Labour
Man Mazdoor day 0.780
Add sundries at 1% towards Nylon rope, Tyres etc 1%
Overheads & Contractors Profit
Cost for MT
38 Centering and scaffolding charges for R.C.C. members including
PHE-CSRC-38 all materials and labour charges for forming and dismantling
Surface area:
Outside – π x 4.40 x 1.00 = 13.83 Sqm
Inside area = π x 4 x 1 = 12.57 Sqm
= 26.40 Sqm
a) Materials
i) Planks 33 mm
26.40 x 0.038 = 1.003 cum
Extra & Wastage @ 20% = 0.201 cum
= 1.204 Cum cum 1.204
ii) Hattens – 75 x 38 mm
Inside – 2 x 25 x 0.50 x 0.075 x 0.075 = 0.1406
Outside – 2 x 28 x 0.50 x 0.075 x 0.175 = 0.1575
= 0.2981
Add 5% wastage = 0.0149
= 0.3130 cum cum 0.313
920
S No
PHE
Index-code Description Unit Quantity Rate Rs. Amt Rs. Remarks
1 2 3 4 5 6 7
iii) Ballion 125 mm dia
Inside – 25 x 1 = 25 m
Outside – 28 x 1 = 28 m
= 53.00 m
Add 5% wastage = 2.65 m
55.65 π x 0.1252 = 0.68 cum cum 0.680
Assuming that timber shall become unserviceable after being
used for 5 times
Cost for 5 times
Rate per 1 time
b) Labour
Add labour charges for assembling, erection and dismantling
etc., @ 1/6 cost of materia
c) Total
Overheads & Contractors Profit
c) Cost for 26.04 Sqm
Rate per sqm =c/26.04
B For Ground level works
i R.C.C. vertical wells of plane surface upto 3 meters height such
as G.L. tanks clarifiers and sludge digestor etc,
Rate per Sqm (as arrived in item A (i) above)
ii R.C.C. Vertical walls of circular faces upto 3 meters height
Rate per Sqm (as arrived in item A (ii) above)
PHE-HSSG-39 39 Hoisting of S.S. Girders in pump house etc.
Detail cost of S.S. Joist = 300 x 140 mm - 6 M long
Wt. 44.2 Kgs/M = 6 x 44.20 = 265.20 kgs
Tolerances @ 5% = 13.26 kgs
= 278.46 kgs
a) Labour
Labour for hoisting inn position:
Mason 2nd class day 1.000
Man Mazdoor day 2.750
Total
(b) Overheads & Contractors Profit
c) Cost for 278.46 Sqm
Rate per sqm =c/278.46
Cost for 50 Kg
40 Labour charges for fixing ventilating shafts in sewerage
PHE-LCVS-40 scheme complete with all accessories
Unit – Each
a) Labour
Mason 1st class day 0.150
Mason 2nd class day 0.350
Plumber 2nd Class day 0.600
Man Mazdoor day 2.000
Overheads & Contractors Profit
Rate
921
TELANGANA DRINKING WATER SUPPLY PROJECT - SRSP Adilabad Segment
Datas-SSR -2015-16
MA 0%
Contractor' Profi 10.615%
S.No Qty units Description Rate unit Amount
For 3m to 6m (4.68*310/10)
1 Cum Initial cost 255.06 1 Cum 255.060
--- 0% 0.000
Contractor's Profit 10.615% 27.07
Total 282.13
For above 6m depth (6.24*310/10)
1 cum Intial cost 340.08 340.08
--- 0% 0.00
Contractor's Profit 10.615% 36.10
Total 376.18
8 Cement concrete(1:1.5:3) prop using 20mm gauge HG metal including cost and conveyance
of all materials and labour charges ,seign. charges etc.complete.
FOUNDATIONS, PLINTH, PEDESTALS (Below Plinth)
0.9 cum 20mm HBG graded metal Rs. 1997.83 cum 1798.05
0.45 cum Sand for concrete Rs. 2481.89 cum 1116.85
400 Kgs Cement Rs. 5200.00 Kgs 2080.00
0.133 day 1st Class Mason Rs. 610.00 day 81.13
0.267 day 2nd Class Mason Rs. 580.00 day 154.86
3.6 day Mazdoor (Both Men and Wome Rs. 545.00 day 1962.00
1 hour Concrete Mixer 10 / 7 cft (0.2 Rs. 513.20 hour 513.20
0.133 Liters Cost of Diesel for Miller Rs. 97.82 Liters 13.01
0.667 Liters Cost of Petrol for Vibrator 109.66 Liters 73.14
1.2 kl Water (including for curing) 81.00 kl 97.20
--- 0% 0.00
Contractor's Profit 10.615% 837.46
Total rate per cum 8726.90
Cont
Basic Rate & labour Including Centering
13 Prop Mix Profit10.615 Total Rate Per
Cont Profit Charges
%
Footings (1:1.5:3) 8726.90 1332.00 141.39 10200.29 /1Cum
28 Cost of steel and its fabrication charges incl., bending, cost of binding wire etc., complete
as per standard specification steel Steel beams
1.05 MT Cost of steel 58000.00 60900.00 64050.00
6.00 Binding wire 85.00 kg 510.00
(b) Labour for cutting, bending,
shifting to site, tying and placing
in position
bldg.26
2.00 Blacksmith / Bar bender 720.00 day 1440.00 1440.00
6.40 Mazdoor (Unskilled) 545.00 day 3488.00 3488.00
--- 0% 0.00 0.00
Contractor's Profit 10.615% 7041.78 7322.01
Sundries on Material
Total Rs. 73379.80 76300.00
VRCC (1:1.5:3) using 20mm HBG metal including cost and conveyance of all material, labour charges,
62
centering etc., complete but excluding cost of steel and its fabrication charges for side wall of (straight)
Chambers 100 mm thick for Rectangular chambers
1.00 Cum Cost of CC (1:1.5:3) 9253.50 1 Cum 9253.50
10.00 Sqm Centering charges 1218.00 1 Sqm 12180.00
--- 0% 0.00
Contractor's Profit 10.615% 1292.91
Total 22726.41
VRCC (1:1.5:3) using 20mm HBG metal including cost and conveyance of all material, labour charges,
centering etc., complete but excluding cost of steel and its fabrication charges for slab of Chambers
64
100 mm thick
1.00 Cum Cost of VRCC (1:1.5:3) 7416.60 1 Cum 7416.60
10.00 Sqm Centering charges 710.00 1 Sqm 7100.00
--- 0% 0.00
Contractor's Profit 10.615% 753.67
Sundies
Total 15270.27
VRCC (M30) using 20mm HBG metal including cost and conveyance of all material, labour charges,
centering etc., complete but excluding cost of steel and its fabrication charges for Column(Circular)
Column 0.30 Circular
1 cum Intial Rate 9253.50
1.00 cum coulmn cetering charges 3527.00 3527.00
extra allowance on centring
charges 0% 0.00
--- 0% 0.00
Contractor's Profit 10.615% 374.39
0 - 3 Mts Total 13154.89
Leads statement
MSSION BHAGIRATHA ADILBAAD
Municipal allowence 0%
1 40mm size HBG (SS5) Nirmal 65 909.00 931.83 1798.83 0.00 1.000 909.00 931.83 1840.83
2 20mm size HBG metal Nirmal 65 1108.00 931.83 1997.83 0.00 1.000 1108.00 931.83 2039.83
6 Sand for concrete items Peddavagu 138 662.00 1863.49 2481.89 5.00 1.050 630.48 1863.49 2493.97
7 Sand for mortar Peddavagu 138 872.00 1863.49 2735.49 5.00 1.050 830.48 1863.49 2693.97
10 Cement 5200 5200.00 28.81 1.288 4036.95 0.00 4036.95
11 Steel Fe 500 of SAIL, TATA, Jindal 60000 60000.00 18.12 1.181 50795.80 0.00 50795.80
12 Steel I Beams 61000 61000.00 18.12 1.181 51642.40 0.00 51642.40
13 6 mm size HBG metal Nirmal 55 806.00 804.21 1610.21 0.00 1.000 806.00 804.21 1610.21
14 12mm size HBG metal Nirmal 55 1057.00 804.21 1861.21 0.00 1.000 1057.00 804.21 1861.21
15 10mm size HBG metal Nirmal 55 957.00 804.21 1761.21 0.00 1.000 957.00 804.21 1761.21
16 uncoursed rubble stone Nirmal 55 229.00 804.21 1033.21 5.00 1.050 218.10 804.21 1022.31
17 Gravel Local 10 109.00 178.85 287.85 0.00 1.000 109.00 178.85 287.85
18 Shabad stone thandur 150 2139.59 2139.59 5.00 1.050 0.00 2139.59 2139.59
19 Present Pig Iron Cost as per BOC
20 Present Coke Cost as per SSR
Binding wire 85 85.00 18.12 1.181 71.96 0.00 71.96
Water 81 81.00 5.00 1.050 77.14 0.00 77.14
Paint 0.00 28.81 1.288 0.00 0.00 0.00
White Cement 0.00 28.81 1.288 0.00 0.00 0.00
Snowcem 0.00 0.00 1.000 0.00 0.00 0.00
Accoproof Powder 0.00 28.82 1.288 0.00 0.00 0.00
Emulsion Piant 0.00 28.81 1.288 0.00 0.00 0.00
Wood Primer 0.00 28.81 1.288 0.00 0.00 0.00
Epoxy protective coating 0.00 28.81 1.288 0.00 0.00 0.00
Gelatin 80% 0.00 28.79 1.288 0.00 0.00 0.00
Detonetor Electric 0.00 28.84 1.288 0.00 0.00 0.00
GI pipe 32mm 0.00 28.84 1.288 0.00 0.00 0.00
MS Angles 0.00 18.12 1.181 0.00 0.00 0.00
SS Railing 40mm dia Pipe 0.00 28.84 1.288 0.00 0.00 0.00
1 Binding wire M072, 70 PHSSR-p19
2 Delifting charges 41 Lift charges 134 with SSR 2015-16
3 Slab up to 150mm 1 sqmt 710 bldg.92
3 Slab above 150mm upto 300mm 1 sqmt 730 bldg.92
4 Slab above 300mm 1 sqmt 418 bldg.89
5 Centering Charges Footing/BedBlocks 750 bldg.89 305 Bed blocks
6 Lifting charges (Concrete) 134
7 Mason Ist Class 610 PHSSR-p6
8 Mason II nd class/Work Inspector 580 PHSSR-p6
9 Men mazdoor 545 p11
10 Woman Mazdoor 310 p11
11 Centering Charges Ring Beam/Cir Col 1206 PHSSR-p46
12 Centering Charges Doome 2670.00 PHSSR-p46 1643 Roof slab
13 Earth work Initial rate (up to 3M) Manual Excavation 198.38 R&B.Ch.11/1
14 Earth work Initial rate(3-6m) Manual Excavation 255.06 R&B.Ch.11/2/A
15 Earth work Initial rate(above-6m) Manual Excavation 340.08 R&B.Ch.11/3/A
16 Sand filling Charges Manual Refilling 168.95 R&B.Ch.11/2/A
17 Water 77.00 M 189
18 dome slabs centering 6302.00 buildings
19 Beams 3428.00 bldg.89
20 Column/Braces centering charges 1099.00 PH P-301
20a Brace centering charges(Circular) 1206.00 PH p-47
21 Columns 2041.00 bldg.89
22 Column above 3.6mt 2381.15 bldg.89
23 Beams above 3.66m height 3999.31 bldg.89
24 Lintels 2344.00 bldg.89 1068 Pedestrals
25 Sun shades 0.6m Width 410.00 bldg.89
26 Roof slab up to 150mm thick 389.00 bldg.89 650 above 3.66m 201
27 Roof slab 150-300mm thick 399.00 bldg.89 669 above 3.66m 209
28 Roof slab above 300.0mm thick 418.00 bldg.89 408 upto 3.66mts height 219
29 Helical Stair case 1 sqmt 480.00 bldg.89
30 Concrete Mixer 10 / 7 cft (0.2 / 0.8 cum) capacity 513.20 P-49 CSSR item 16
31 Cost of Diesel for Miller per Lts 97.82 C-SSR p-30
32 Cost of Petrol for Vibrator per Lts 109.66 C-SSR p-21 above 3.66m
33 RCC Vertical wall of circular surface GLSR/Sump 1115.00 1449.50 1469
34 Side walls curved surfaces. ELSR 2463.00 PH p-8 1909.7
35 Side walls St Surface ELSR 2192.00 PH p-48
36 Lifting charges (Mortar) 71.80 60.9
37 Pig Iron as per SSR 26000 PH p-72
38 Coke as per SSR 36570 PH p-72
39 CI specials per Kg as per SSR 73.70 PH p-72
40 Seignorage charges Gravel 22.00
RCC Vertical wall of plane surfaces GLSR/Sump 1218.00 876 both faces
41 wood primer 158.00 Bld SSR-31-S.No371
42 cost of Syenthetic Enamil paint Grade-I 276.00 Bld SSR-28-S.No382
43 cost of white cement 29.00 Bld SSR-88-S.No943
44 Snowcem @ 55.00 Bld SSR-27-S.No376 water proof cement
45 Rooling Shutters80x1.25mm 3576.00 Bld SSR-28-S.No137
46 Painter 1st class 480.00
47 Acco Proof powder 75.00 (water proofing compound) as per buildings ssr
48 weigh Batcher hire charges 0.5 Cum ( 6 Cum/hr) 548.30
RSF Rate
As per SSR 2015-16
total 5,143.00
Earth work excavation and depositing on bank with an initial lead of 50m
and lift of 3.0m in all types of soils except hard rock requiring blasting for
1
founadtion
###
S.N
Description of work Nos L B D Qty Units Rate Amount
o
1 Single Chamber DI Air Valve with Body and 32363.00 32363.00 32363.00 32363.00 32363.00 32363.00 32363.00 32363.00 32363.00 32363.00 43175.00 43175.00 43175.00
cover in Ductile Iron of grade SG 400/12 or
equivalent grade as per I.S.3896-part2-1985
and subsequent revisions
2 Cost and supply of DI D/F bewel geared 7747.00 7747.00 7747.00 7747.00 7747.00 7747.00 7747.00 7747.00 7747.00 7747.00 9922.00 9922.00 9922.00
Isolaated sluice valve confirming to IS 3986
part - 2 1985 etc.
2 Transportation charges(5%) 2006.00 2006.00 2006.00 2006.00 2006.00 2006.00 2006.00 2006.00 2006.00 2006.00 2655.00 2655.00 2655.00
3 Cost of Air Tee DI A/F 2027.78 2027.78 2027.78 2756.00 3604.00 4452.00 4452.00 4452.00 6678.00 6678.00 9540.00 9540.00 13144.00
4 Cost of 0.6m D/F DI pipes 2nos 2841.88 2841.88 2841.88 3484.54 4489.80 5654.26 5654.26 5654.26 8056.88 8056.88 10772.00 10772.00 13746.52
7 Cost of D/F DI pipe 4895.00 4895.00 4895.00 4895.00 4895.00 4895.00 4895.00 4895.00 4895.00 4895.00 4895.00 4895.00 4895.00
5 Cost of HDPE Tail pieces 2 nos 214.00 258.00 332.00 462.00 832.00 840.00 1172.00 1660.00 2134.00 2448.00 2868.00 3204.00 3696.00
6 Cost of MS flanges 2nos 262.00 262.00 262.00 376.00 516.00 560.00 560.00 560.00 1342.00 1342.00 1978.00 2244.00 2640.00
8 Jointing materials such as bolts nuts and rubber 560.76 560.76 560.76 1036.32 1074.64 1676.12 1676.12 1676.12 1838.60 1838.60 2686.68 2686.68 2815.52
vouchers including material cost for main line -
4nos
9 Jointing materials such as bolts nuts and rubber 203.18 203.18 203.18 203.18 203.18 203.18 203.18 203.18 203.18 203.18 316.58 316.58 316.58
washers for Air valve and Isolated Gate Valve and
extra stem pipe fixing
10 Labour charges for lowering DI pipes and tees - 113.25 113.25 113.25 143.51 167.44 243.10 243.10 243.10 354.93 354.93 489.95 489.95 648.13
(2 jobs+1job)+3
11 Labour charges for fixing of Air valve with 188.00 188.00 188.00 188.00 188.00 188.00 188.00 188.00 188.00 188.00 220.00 220.00 220.00
isolated sluice Valve
12 Add MA 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
13 Air Valve Cage of size 1.5x1.8x2.5 firmly 29152.00 29152.00 29152.00 29152.00 29152.00 29152.00 29152.00 29152.00 29152.00 29152.00 29152.00 29152.00 29152.00
embedded four legs in concrete block M20 of size
0.3x.03x0.6m to a depth of 0.90m, with
IS40x40x5mm top and bottom frame with legs
projection of size 1.0m with 10mm square bars at
100mm c/c in both ways on sides and top and
with 40x60mm flat stiffner at the middle of the
vertical face alround and with hinges and locking
arrangement with a vertical stem of 100mm dia
2.0m lond DI D/F pipe, including fabrication
charges, welding including cost of material
transportation labour charges including 2 coats of
best quality blue colour enamil paint including
fixing charges all incidental and operational
charges etc complete for fininshed itme of work
14 Add: contractors profit 13.615% 7273.38 7279.38 7289.45 7578.18 7908.42 8281.69 8326.89 8393.33 9231.87 9274.62 12187.90 12269.87 13325.51
15 Part B - Total 89847.00 89897.00 89981.00 92391.00 95146.00 98261.00 98639.00 99193.00 106190.00 106547.00 130858.00 131542.00 140351.00
Sno Discription of Item 50mm air 50mm air 50mm air 80mm air 80mm air 100mm air 100mm air 100mm air 150mm air
valve valve valve valve valve valve valve valve valve
Dia of pipeline 100mm line 150mm line 200mm line 250mm line 300mm line 350mm line 400mm line 450mm line 500mm line
Size of tee 100x100 150x100 200x100 250x100 300x100 350x100 400x100 450x100 500x150
1 Single Chamber DI Air Valve with Body and cover in Ductile Iron of 30745.00 30745.00 30745.00 41016.00 41016.00 47888.00 47888.00 47888.00 58298.00
grade SG 400/12 or equivalent grade as per I.S.3896-part2-1985 and
subsequent revisions
2 Cost and supply of DI D/F bewel geared Isolaated sluice valve 7360.00 7360.00 7360.00 9426.00 9426.00 12434.00 12434.00 12434.00 19577.00
confirming to IS 3986 part - 2 1985 etc. PN 16
3 Transportation charges (5% of basic) 1905.00 1905.00 1905.00 2522.00 2522.00 3016.00 3016.00 3016.00 3894.00
4 Cost of DI Air Tee D/S branch flanged 2160.00 2970.00 4185.00 5265.00 6750.00 8100.00 9720.00 12015.00 17010.00
5 Cost of D/F DI pipe Vetical Stem 5593.00 5593.00 5593.00 5593.00 5593.00 5593.00 5593.00 5593.00 8115.00
6 Jointing materials such as bolts nuts and rubber vouchers for Air 614.98 614.98 614.98 614.98 614.98 614.98 614.98 614.98 1028.79
valve fixing (1 set)
Part -A (Material cost) 48377.98 49187.98 50402.98 64436.98 65921.98 77645.98 79265.98 81560.98 107922.79
7 Labour charges for S/S jointing including cost of rubber gaskets (2 501.22 534.45 541.52 559.31 603.83 666.55 685.74 738.26 799.98
jobs)
8 Labour charges for fixing of Air valve with isolated sluice Valve 335.85 335.85 335.85 439.35 439.35 534.07 534.07 534.07 880.12
9 Labour charges for lowering of tee 1 job 52.94 72.80 102.58 129.05 165.45 198.54 238.24 294.50 416.93
Part -B (Labour cost) 890.01 943.09 979.94 1127.71 1208.63 1399.16 1458.06 1566.83 2097.02
10 Air Valve Cage of size 1.5x1.8x2.5 firmly embedded four legs in 62001.00 62001.00 62001.00 62001.00
concrete block M20 of size 0.3x.03x0.6m to a depth of 0.60m, with
IS40x40x5mm top and bottom frame with legs projection of size 1.0m
with 10mm square bars at 100mm c/c in both ways on sides and top
and with 40x60mm flat stiffner at the middle of the vertical face
alround and with hinges and locking arrangement with a vertical stem
of 100mm dia 2.0m lond DI D/F pipe, including fabrication charges,
welding including cost of material transportation labour charges
including 2 coats of best quality blue colour enamil paint including
fixing charges all incidental and operational charges etc complete for
fininshed itme of work (For above 80mm dia Air valve)
11 AIR valve Stem Pipe Encasement of Block size 600 x 600 for upto 7885.00 7885.00 7885.00 7885.00 7885.00
80mm dia airvalve
12 Add: contractors profit 13.615% 6707.84 6825.35 6995.79 8926.63 9139.83 10762.00 10990.58 11317.85 14979.20
Grand total 63860.83 64841.42 66263.71 82376.33 84155.44 151808.14 153715.62 156446.67 187000.01
Note: For 50mm and 80mm dia Air valve DI stem and Air tee meterial cost is taken bz it is embede in concrete.Above 80mm dia Air valve only labour charges is considered.
Asst. Executive Engineer Dy. Executive Engineer(FAC) Executive Engineer Superintending Engineer
MB Grid Sub Division, Adilabad MB Grid Sub Division, Adilabad MB Grid , Division-Adilabad MB Circle, Adilabad
Data Sheet for Fixing Sluice valves on DI Mains
As per SSR 2022-23
SL
Discription of Item/ Dia of Sluice valve 100 mm 150 mm 200 mm 250 mm 300 mm 350 mm 400 mm 450 mm 500 mm
No.
on 100mm
Size of pipeline 150mm line 200mm line 250mm line 300mm line 350mm line 400mm line 450mm line 500mm line
dia line
0.90x0.90x 0.90x0.90x 0.90x0.90x 1.05x1.20x 1.05x1.20x 1.05x1.20x 1.05x1.20x 1.20x1.20x2.10 1.20x1.20x2.10
Size of Valve chamber 1.40m 1.40m 1.40m 1.70m 1.70m 1.70m 1.70m m m
Class of valve PN-1.6 PN-1.6 PN-1.6 PN-1.6 PN-1.6 PN-1.6 PN-1.6 PN-1.6 PN-1.6
1 DI D/F Gate valves ( soft Seated ) valves conforming to IS 3896- 12434.00 19577.00 32532.00 45058.00 68098.00 206179.00 216249.00 372041.00 395083.00
oart 2-1985 wedge fully rubber lined with EPDM food grade quality
and the valve should be of vacuum tight and 100% leak proof with
face to face dimensions. All the valves should be with Electrostatic
powder caoting both insisde and outside pockets body passages.Drilled
as per IS: 1538
2 Cost of Dismantling Joint (up to 300 mm dia CI and above 300 mm dia
MS
3 Transportation chargers (5% of basic cost) 621.70 978.85 1626.60 2252.90 3404.90 10308.95 10812.45 18602.05 19754.15
4 Cost of DI flanged sockets - 2 Nos 2430.00 3780.00 5670.00 7560.00 9,990.00 12,960.00 16,470.00 20,520.00 25,920.00
5 D/F Reducers 2Nos 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
6 Jointing materials such as bolts nuts and rubber washers for dismantling 614.98 1028.79 1135.01 1744.29 1803.56 2715.32 4551.37 5293.28 6216.33
joint including cost of materials (3 joints)
7 Jointing materials such as bolts nuts and rubber washers for reduced dia 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
including cost of materials (1 joints)
8 Jointing of DI S/S 2 Jobs Labour 501.22 534.45 541.52 559.31 603.83 666.55 685.74 738.26 799.98
9 Lowering of valve and keeping in postion 177.07 300.12 495.12 703.62 1001.75 1691.76 2077.11 2716.22 3148.56
10 Cost of RCC valve chamber 24310.00 24310.00 24310.00 36328.00 36328.00 36328.00 36328.00 45066.00 45066.00
11
Add: contractors profit 13.615% 2284.46 3567.02 5718.33 7880.11 11559.41 31930.11 34152.64 57170.86 61393.03
12 Grand total
43373.00 54076.00 72029.00 102086.00 132789.00 302780.00 321326.00 522148.00 557381.00
13 Contractors profit 13.615% (W/o cost of Gate valve) 506.92 768.34 1067.64 1438.73 1824.29 2455.28 3238.22 3984.81 4912.95
14 Total (W/o cost of Gate valve) 28540.19 30721.70 33219.29 48333.95 51551.44 56816.91 63350.45 78318.57 86063.81
15 Labour charges of Loosening of Sluice valve 678.29 834.57 1036.64 1262.94 1605.58 2358.32 2762.85 3454.48 3948.53
16 Contractors profit 13.615% 92.35 113.63 141.14 171.95 218.60 321.08 376.16 470.33 537.59
17 Total Labour charges of Loosening of Sluice valve 770.64 948.19 1177.78 1434.88 1824.18 2679.40 3139.02 3924.81 4486.13
18 Total cost for loosening and re-fixing of Sluice valve with chamber 29310.83 31669.89 34397.06 49768.84 53375.62 59496.32 66489.46 82243.38 90549.94
Note : VRCC valve chamber can not be relocated.
Asst. Executive Engineer Dy. Executive Engineer(FAC) Executive Engineer Superintending Engineer
MB Grid Sub Division, Adilabad MB Grid Sub Division, Adilabad MB Grid , Division-Adilabad MB Circle, Adilabad
Data Sheet for Jointing material required for Di to MS joint
4 Jointing materials such as bolts nuts and rubber washers 409.99 685.86 756.67 1162.86 1202.38 1810.21 3034.25 3528.85 4144.22
for dismantling joint including cost of materials (2 joints)
5 Jointing of DI S/S 2 Jobs Labour 501.22 534.45 541.52 559.31 603.83 666.55 685.74 738.26 799.98
6 Add: contractors profit 13.615% 531.6 831.1 1193.0 1643.9 2106.4 2940.9 3772.6 4716.4 5742.8
Total 4435.8 6935.4 9955.2 13718.1 17577.6 24541.7 31481.6 39357.5 47923.0
Asst. Executive Engineer Dy. Executive Engineer(FAC) Executive Engineer Superintending Engineer
MB Grid Sub Division, Adilabad MB Grid Sub Division, Adilabad MB Grid , Division-Adilabad MB Circle, Adilabad
B
D 0 0.1 0.2 0.3 0.4 0.5 0.6 0.7 0.8 0.9
0
0.1
0.2
0.3
0.4
0.5
0.6
0.7
0.8
0.9
1.0
1.1
1.2
1.3
1.5
1.6
1.7
1.8
1.9
2.0
2.1
2.2
2.3
Data Sheet for Fixing Air valves on MS Pipeline
Air valves PN-16 on MS Mains
SL No. Discription of Item
PN 16 As per SSR 2023-24
1 Single Chamber DI Air Valve with Body and cover in Ductile Iron of grade SG
400/12 or equivalent grade as per I.S.3896-part2-1985 and subsequent 30745.00 30745.00 30745.00 30745.00
revisions
2 Cost and supply of DI D/F bewel geared Isolaated sluice valve confirming to IS
3986 part - 2 1985 etc. 7360.00 7360.00 7360.00 7360.00
2 Transportation charges(5%) 1905.00 1905.00 1905.00 1905.00
3 Cost of Air Tee G.I A Class 1.5M Length 492.00 492.00 492.00 492.00
7 Cost of MS flanges 2nos 96.00 96.00 96.00 96.00
9 Jointing materials such as bolts nuts and rubber washers for Air valve and
Isolated Gate Valve and extra stem pipe fixing 143.80 143.80 143.80 143.80
11 Labour charges for fixing of Air valve with isolated sluice Valve 335.85 335.85 335.85 335.85
12 Fabrication charges 321.90 321.90 321.90 321.90
13 Air Valve Encasement for the stem pipe of the air valve for the earthwork ,
PCC , and 20 mm HBG grade RCC including labour charges and etc., as per the 7885.00 7885.00 7885.00 7885.00
specified dimesnsions.
14 Add: contractors profit 13.615% 5636.55 5636.55 5636.55 5636.55
15 Part B - Total 54921.10 54921.10 54921.10 54921.10
Manufacture, Supply and delivery of DI D/F Gate Valves (Soft Seated) Resilient seated
soft sealing gate valves (Sluice valves) with body bonnet of ductile cast iron of grade
GGG-40/ SG- 400/15 or GGG-50/SG-500/7 or equivalent grade as per I.S.3896-part2-
1985 and subsequent revisions, wedge fully rubber lined with EPDM food grade
1 quality and seals of NBR and the valves should be of vacuum tight and 100% leak 9426 12434 19577 32532
proof with face to face dimensions as per BS5163-89/IS14846-2000/DIN 3202 F 4. All
the valves should be with Electrostatic powder coating both inside and outside
pocket less body passage. Drilled as per requirement of the dept.