2.5 Prepare PPE required for the Contact with sharp edges Hand laceration or cut Toolbox talks should be conducted prior to the work commences.
installation works such as leather Working in an awkward position Body sprain or back injury Appropriate personal protective equipment should be available like
gloves, full-body harness Musculoskeletal illness coverall, safety shoes, hand gloves, eye protection, and etc.
Damage to end truck Observe proper posture and natural working position.
Crashed feet Discuss proper ergonomics during toolbox meeting.