CLEVER CONSULTS & CONSTRUCTION CO.

LTD
C/O P.O Box 31744 Kampala (U), Located at Ayubu PlazaNtinda
Tel: +256-785763597/753894098

MATERIALS SCHEDULE AND LABOR FOR PHASE 2 BOUNDARY WALL CONSTRUCTION GARUGA

Amount
No Description Qty Unit Rate (UGX)
(UGX)

1 Masonry Work

A Hardcore
2 Trips 280,000 560,000
B Clay Bricks 2000 Bricks 500 1,000,000

C Lake sand 8 Trips 280,000 2,240,000

Blocks
D 1600 Blocks 2000 3,200,000

E 70 Bags 35000 2,450,000


Cement

Total 9,450,000

Others

G Dpc 4 Rolls 35,000 140,000

210,000
H Pian 3 Rolls 70,000
Total 410,000

Grand Total Without Labor : 9,860,000


Labor
I Masons(Four)@30,000 per Day 14 Days 120,000 1,680,000
J Helpers(Four)@15,000 per Day 14 Days 60,000 840,000
K Excavation 1 Sum Total 300,000 300,000
L Engineers Transport and Supervision 1 Sum Total 200,000 200,000

Total Labor 3,020,000

Note
The prices stated can vary depending on the hardware
Prepared by Henry Darlin Kiige 31st October 2023

Experts in: General Construction, Architectural and Structural Designs, Civil engineering, Interior
Design, Project Management, Water Works and General Supplies

God Bless You