059-B01-MC020 - Mechanical Schedules - Sheet (20 of 23)

You might also like

Download as pdf or txt
Download as pdf or txt
You are on page 1of 1

PROCURER

FUEL TANKS SCHEDULE COMPUTER ROOM AIR CONDITIONER SCHEDULE (CRAC-01) - CHILLED WATER-

SUPPLY FAN FAN ELECTRICAL DATA COIL LOAD CHILLED QUANTITY HUMIDIFIER ELECTRIC ELECTRICAL ELECTRICAL
TITLE DESIGNATION TYPE COMPARTMENT MATERIAL CAPACITY DIAMETER LENGTH QTY. EQUIPMENT TAG LOCATION SYSTEM SERVED
(m3) (m) (m) REMARKS HEATER POWER DATA EMERGENCY REMARKS
TOTAL SENSIBLE (kg/hr)
ESP Pa FLOW L/s V Hz Phase POWER (kW) L/s ENT. C LVG. C DUTY STAND BY TOTAL (KW) (KW) (V/hz/phase)
kW kW PROJECT
FT-01 DIESEL STORAGE TANK BELOW GROUND ,DOUBLE SINGLE CARBON STEEL 60 2.9 10.2 2 TANK SHALL BE DESIGNED AS PER EN 12285-1 SUITABLE FOR UNDERGROUND INSTALLATION, WITH PROTECTIVE
SKINNED STEEL CONFIGURATION. COATING, CATHODIC PROTECTION, NORMAL VENT, SUPPORTS AND ALL NECESSARY ACCESSORIES. DUAL CIRCUIT WITH DX COOLING COIL, COMPLETE
TANK SHALL BE DESIGNED AS PER EN 12285-1 SUITABLE FOR UNDERGROUND INSTALLATION, WITH PROTECTIVE CRAC-01 L03 SERVER ROOM 5000 400 60 3 4.0 1.66 1 1 2 10.0 10.0 35.0 400/60/3 YES WITH MICROPROCESSOR CONTROLLER AND ALL
BELOW GROUND ,DOUBLE 100 62.0 62.0 5.6 14.5
FT-02 DIESEL STORAGE TANK SINGLE CARBON STEEL 80 2.9 13.2 1 REQUIRED ACCESSORIES UNIT SHALL FLOOR
SKINNED STEEL CONFIGURATION. COATING, CATHODIC PROTECTION, NORMAL VENT, SUPPORTS AND ALL NECESSARY ACCESSORIES.
STANDING TOP DISCHARGE & BOTTOM RETURN
BELOW GROUND ,DOUBLE TANK SHALL BE DESIGNED AS PER EN 12285-1 SUITABLE FOR UNDERGROUND INSTALLATION, WITH PROTECTIVE
FT-03 DIESEL STORAGE TANK SINGLE CARBON STEEL 120 3.0 17.9 2
SKINNED STEEL CONFIGURATION. COATING, CATHODIC PROTECTION, NORMAL VENT, SUPPORTS AND ALL NECESSARY ACCESSORIES.
NOTE:
NOTES:- NORMAL VENT PIPES SHALL BE TERMINATED AT LEAST 3.6 m ABOVE GROUND LEVEL. * EACH CRAC UNIT SHALL BE EQUIPPED WITH CONDENSATE PUMP.
* CONTRACTOR SHALL FINALIZE THE POWER REQUIREMENTS BASED ON THE FINAL SELECTION OF THE UNITS NOT BASED ON THE DESIGN VALUES. CONSORTIUM
FUEL GEAR PUMPS SCHEDULE SCHEDULE OF HOT WATER EXPANSION TANK * CRAC UNITS SERVING DATA SERVER ROOM SHALL BE CAPABLE OF PROVIDING COOLING IN WINTER AND SUMMER.
* THE SHOWN UNITS CAPACITIES ARE CALCULATED & SHALL BE CAPABLE OF SATISFYING THE ACTUAL COOLING LOAD, TAKING INTO CONSIDERATION
ELECTRICAL DATA* each set pumps QUANTITY UNIT REFERENCE NO. EXP-01 EXP-02
FLOW ESTIMATED AMBIENT CONDITIONS DRY BULB 47.7°C & ROOM TEMP 22°C FOR INDOOR UNIT SELECTION.
PUMPS SETS REMARKS
PUMP
(M3/HR) HEAD (M) ESTM. * V / Hz / Ph QUANTITY TOTAL DUTY STAND BY * THE SHOWN UNITS SHALL BE EQUIPPED WITH ULTRA SONIC HUMIDIFIER.
EXPANSION TANK (L) 300 150
(KW)
GEAR FUEL PUMPS COMPLETE * AT EMERGENCY MODE, MEAN WHEN THE MAIN ELECTRICAL POWER IS SHUT DOWN AND THE GENERATOR WILL START AND SUPPLY POWER TO SPECIFIC SERVICES.
LOCATION TECHNICAL FLOOR TECHNICAL FLOOR
FGP-01 2.0 25 1.0 220/60/1 5 2 1 1 WITH CONTROL PANEL AND ALL
REQUIRED ACCESSORIES QTY 5 2
AUTOMATIC PRESSURIZATION SET SCHEDULE
REMARKS COMPLETE WITH ALL NECESSARY ACCESSORIES COMPLETE WITH ALL NECESSARY ACCESSORIES TAMASUK – ALGHANIM CONSORTIUM
TANK ELECTRICAL DATA
VOLUME NOTES
EQUIPMENT TAG LOCATION SERVICE (L) kW VOLT PHASE HZ HEALTHCARE PLANNER
* TWIN PUMPS, HORIZONTAL PERIPHERAL TYPE
SUBMERSIBLE PUMPS SCHEDULE * PLASTIC ENCLOSURE
APS-01 ETS ROOM CHILLED WATER 21 0.9 400 3 60
* 800 LITER FABRICATED STEEL EXPANSION TANK
* 21 POLYETHYLENE BREAK TANK
NOTE:
PUMP QUANTITY PER EACH SET 1- THE FINAL UNITS SELECTION AND CAPACITY SHALL BE ACCORDING TO MANUFACTURE SELECTION
FLOW HEAD M.C.C. NO. PUMP SET
PUMP ELECTRICAL DATA*
LOCATION REMARKS CHEMICAL POT FEEDER SCHEDULE DESIGN TEAM
L/S BAR
ESTIM. QUANTITY
(Kw) V / Hz / Ph NORMAL EMERGENCY TOTAL DUTY STAND BY CAPACITY
EQUIPMENT TAG LOCATION SERVICE NOTES
(L)
SUBMERSIBLE PUMP COMPLETE WITH CONTROL PANEL AND
SUMP-01 BASEMENT 4 FLOOR 3 3.0 2.5 400/60/3Ø Y Y 1 2 1 1 -
ALL REQUIRED ACCESSORIES CPF-01 ETS ROOM CHILLED WATER 25

SUBMERSIBLE PUMP COMPLETE WITH CONTROL PANEL AND


SUMP-02 BASEMENT 4 FLOOR 3 3.0 2.5 400/60/3Ø Y Y 1 2 1 1 ALL REQUIRED ACCESSORIES

SUBMERSIBLE PUMP COMPLETE WITH CONTROL PANEL AND AIR AND DIRT SEPARATOR SCHEDULE
SUMP-03 BASEMENT 4 FLOOR 1 3.0 1.5 400/60/3Ø Y Y 1 1 1 0 ALL REQUIRED ACCESSORIES
CONNECTION SIZE
SUBMERSIBLE PUMP COMPLETE WITH CONTROL PANEL AND EQUIPMENT TAG LOCATION SERVICE NOTES
SUMP-04 BASEMENT 4 FLOOR 4 3.0 2.5 400/60/3Ø Y Y 1 2 1 1 (mm)
ALL REQUIRED ACCESSORIES
* MAXIMUM VELOCITY: 1.8 m/s
SUBMERSIBLE PUMP COMPLETE WITH CONTROL PANEL AND AS-01 ETS ROOM CHILLED WATER 500 * WATER FLOWRATE REQUIRED: 300 L/s
SUMP-05 BASEMENT 4 FLOOR 3 3.0 2.5 400/60/3Ø Y Y 1 2 1 1 ALL REQUIRED ACCESSORIES

SUBMERSIBLE PUMP COMPLETE WITH CONTROL PANEL AND


SUMP-06 BASEMENT 4 FLOOR 3 3.0 2.5 400/60/3Ø Y Y 1 2 1 1 ALL REQUIRED ACCESSORIES
CHILLED WATER BIOCIDE DOSING PUMP AND TANK
SUBMERSIBLE PUMP COMPLETE WITH CONTROL PANEL AND ELECTRICAL DATA
SUMP-07 BASEMENT 4 FLOOR 3 3.0 2.5 400/60/3Ø Y Y 1 2 1 1 EQUIPMENT TAG LOCATION QTY FLOW RATE TANK SIZE
ALL REQUIRED ACCESSORIES POWER (kW) V/PH/Hz NOTE
(L/Hr) (L)
SUBMERSIBLE PUMP COMPLETE WITH CONTROL PANEL AND
SUMP-08 BASEMENT 4 FLOOR 3 3.0 2.5 400/60/3Ø Y Y 1 2 1 1 DP-01 ETS ROOM 1 60 1.0 220/ 1 /60 500 -
ALL REQUIRED ACCESSORIES

SUBMERSIBLE PUMP COMPLETE WITH CONTROL PANEL AND


SUMP-09 BASEMENT 4 FLOOR 1 3.0 1.5 400/60/3 Y Y 1 1 1 0 ALL REQUIRED ACCESSORIES

SUBMERSIBLE PUMP COMPLETE WITH CONTROL PANEL AND REVERSE OSMOSIS SCHEDULE - CSSD UNITS
SUMP-10 BASEMENT 4 FLOOR 3 3.0 2.5 400/60/3Ø Y Y 1 2 1 1 ALL REQUIRED ACCESSORIES
WORKING
POWER SUPPLY
EQUIPMENT TAG LOCATION DESCRIPTION QTY PRESSURE EMERGENCY
SUBMERSIBLE PUMP COMPLETE WITH CONTROL PANEL AND
SUMP-11 BASEMENT 4 FLOOR 15 3.5 12 400/60/3Ø Y Y 1 3 2 1 (BAR) Kw V
ALL REQUIRED ACCESSORIES
R.O UNIT SET FOR CSSD
SUBMERSIBLE PUMP COMPLETE WITH CONTROL PANEL AND CAPACITY:10.0 m3/DAY
SUMP-12 BASEMENT 4 FLOOR 10 3.5 9.0 400/60/3Ø Y Y 1 3 2 1 ALL REQUIRED ACCESSORIES MAX. FEED WATER TEMP: 25°C
L03 MIN. FEED WATER PRESSURE: 1.5 bar
* CONTRACTOR SHALL TAKE INTO CONSIDERATION THE ACTUAL RESISTANCE THROUGH THE EQUIP., VALVES, ...ETC. RO-01 1 7.0 25.0 400 3 YES
* CONTRACTOR SHALL SUBMIT CALCULATIONS OF PUMPS TOTAL HEAD. COMPONENTS:
(5.0 FOR RO UNIT)
* CHLORINE METERING PUMP (3.9 L/hr) WITH CHEMICAL TANK (20.0 FOR HEATER UNIT)
* PH METERING (3.9 L/hr) WITH CHEMICAL TANK
* 1X2000 L POLYETHYLENE BREAK TANK AND 1X700 LITER STAINLESS STEEL 316 L PRODUCT TANK
PUMPS SCHEDULE
* STAINLESS STEEL TANKS TO BE EQUIPPED WITH 316 L STAINLESS STEEL
ELECTRIC HEAT TRACED VENT 0.2 MICRON HYDROPHOBIC VENT FILTER
REF NO. FLOW For HEAD ELEC DATA ESTIMATED LOCATION QTY AREA SERVED NOTES EMERGENCY
POWER REMARKS * 5 MICRON CARTRIDGE FILTER
Each (m) V/PH/HZ Y/N
(KW) * UV LAMP
(L/S) * 0.5 MICRON FILTER
TECHNICAL FLOOR 2 DUTY &1 STAND BY COMPLETE WITH CONTROL PANEL AND ALL NECESSARY ACCESSORIES * HEAT UNIT FOR DISINFECTION COMPLETE WITH PUMPS, HEATERS, ...ETC.
SWP-T-01 5.5 30.0 400/3/60 5.0 THIRD FLOOR LEVEL 3 COLD WATER FOR WC (B4-L3) Y
(VARIABLE SPEED PUMP'S) INCLUDING PRESSURE VESSEL * UNIT SHALL BE EQUIPPED WITH STAND-BY RO MEMBRANE.
TECHNICAL FLOOR * ALL REQUIRED RO PUMPS.
2 DUTY &1 STAND BY COMPLETE WITH CONTROL PANEL AND ALL NECESSARY ACCESSORIES
SWP-T-02 5.0 60.0 400/3/60 10.0 THIRD FLOOR LEVEL 3 COLD WATER FOR WC (L4-L9) Y * CONTROL AND CONTROL PANEL
(VARIABLE SPEED PUMP'S) INCLUDING PRESSURE VESSEL
TECHNICAL FLOOR 2 DUTY &1 STAND BY COMPLETE WITH CONTROL PANEL AND ALL NECESSARY ACCESSORIES
SWP-T-03 5.8 30.0 400/3/60 5.0 THIRD FLOOR LEVEL 3 HOT WATER CYLINDER (B1-L3) Y * SKID MOUNTED FACTORY ASSEMBLED UNIT.
(VARIABLE SPEED PUMP'S) INCLUDING PRESSURE VESSEL
* REDUNDANT UNIT AND PIPING SHALL MAINTAIN COMPLETE FLOW DURING
TECHNICAL FLOOR 2 DUTY &1 STAND BY COMPLETE WITH CONTROL PANEL AND ALL NECESSARY ACCESSORIES MAINTENANCE.
SWP-T-04 5.0 60.0 400/3/60 10.0 THIRD FLOOR LEVEL 3 HOT WATER CYLINDER (L4-L9) Y
(VARIABLE SPEED PUMP'S) INCLUDING PRESSURE VESSEL * MEMBRANE SHALL BE WASHABLE TYPE .
TECHNICAL FLOOR COMPLETE WITH CONTROL PANEL AND ALL NECESSARY ACCESSORIES * ALL RO STORAGE TANKS SHALL BE STAINLESS STEEL 316.
SWP-T-05 7.2 30.0 400/3/60 6.0 3 COOLING WATER (B1-L3) 2 DUTY &1 STAND BY Y
THIRD FLOOR LEVEL INCLUDING PRESSURE VESSEL * FULL CONTROL OF PLANT AND PUMP BY SAME MANUFACTURER.
(VARIABLE SPEED PUMP'S)
* FILTERS AND CHEMICALS FOR 2 YEARS SHALL BE INCLUDED.
TECHNICAL FLOOR 2 DUTY &1 STAND BY COMPLETE WITH CONTROL PANEL AND ALL NECESSARY ACCESSORIES
SWP-T-06 5.8 60.0 400/3/60 10.0 3 COOLING WATER (L4-L9) Y
THIRD FLOOR LEVEL (VARIABLE SPEED PUMP'S) INCLUDING PRESSURE VESSEL
* PUMPS SHALL BE PACKAGED BOOSTER PUMPS FACTORY ASSEMBLED.
* PUMPS CONTROLLER SHALL BE RATED TEMPERATURE TILL 50 C.
HOT WATER CIRCULATING PUMPS SCHEDULE
* PUMPS CONTROLLER SHALL BE WATER PROOF TYPE.
* EACH PUMP IN THE SET TO HAVE OWN VFD. M.C.C. NO. PUMP QUANTITY PER EACH SET
FLOW HEAD ELECTRICAL DATA* PUMPS SETS
* PUMPS SKID SHALL BE FACTORY ASSEMBLED FROM SAME MANUFACTURER. PUMP LOCATION REMARKS
NO. (L/SEC) (m) ESTIM.
* PUMPS AND ACCESSORIES SHALL BE SUITABLE FOR DRINKING WATER APPLICATION AND RO WATER. V / Hz / Ph NORMAL EMERGENCY QUANTITY TOTAL DUTY STAND BY
* EACH PACKAGED PUMP SHALL INCLUDE PRESSURE TANKS. (Kw)
* VERTICAL INLINE MULTISTAGE PUMPS WITH VIBRATION ISOLATOR, CHECK VALVE, GATE VALVES, FLEXILE INLINE HOT WATER CIRCULATING PUMP COMPLETE WITH
HWCP-01 TECHNICAL LEVEL 2.60 20 1.0 400/60/3 Y Y 1 2 1 1
CONNECTIONS ALL ACCESSORIES AND PIPES STAINLESS STEEL 316 TYPE. CONTROL PANEL AND ALL REQUIRED ACCESSORIES.
* PUMPS SHALL HAVE STAINLESS STEEL 316 HEADER AND ACCESSORIES.
* CONTROLLER SHALL BE INTEGRATED WITH BMS TO ALLOW FOR COMPLETE MONITOR AND CONTROL PUMPS. ALSO TO INLINE HOT WATER CIRCULATING PUMP COMPLETE WITH
HWCP-02 TECHNICAL LEVEL 0.50 10 0.25 230/60/1 Y Y 1 2 1 1
ALLOW KNOW THE STATUS OF THE PUMPS AND PRESSURE DIFFERENCE. CONTROL PANEL AND ALL REQUIRED ACCESSORIES.
* CONTRACTOR SHALL TAKE INTO CONSIDERATION THE ACTUAL RESISTANCE THROUGH THE EQUIP., VALVES, ...ETC.
* CONTRACTOR SHALL SUBMIT CALCULATIONS OF PUMPS TOTAL HEAD. INLINE HOT WATER CIRCULATING PUMP COMPLETE WITH
HWCP-03 TECHNICAL LEVEL 1.80 20 0.75 230/60/1 Y Y 1 2 1 1
CONTROL PANEL AND ALL REQUIRED ACCESSORIES.

LIFTING PUMPS SCHEDULE * PUMP SHALL BE SUITABLE FOR WATER APPLICATION. * CONTRACTOR SHALL TAKE INTO CONSIDERATION THE ACTUAL
* CONTROLLER SHALL BE INCLUDED FROM SAME MANUFACTURER. RESISTANCE THROUGH THE EQUIP., VALVES, ...ETC.
* CONTROLLER SHALL BE INTEGRATED WITH BMS TO ALLOW FOR * CONTRACTOR SHALL SUBMIT CALCULATIONS OF PUMPS TOTAL
FLOW ELECTRICAL DATA* M.C.C. NO. PUMPS SETS EACH SET PUMPS QUANTITY COMPLETE MONITOR AND CONTROL PUMPS. HEAD.
PUMP LOCATION HEAD
(L/SEC) REMARKS
NO. (m) ESTIM. NORMAL EMERGENCY QUANTITY TOTAL DUTY STAND BY
(Kw)* V / Hz / Ph
DOMESTIC WATER EQUIPMENT SCHEDULE
CWFP-01 12.0 40 11.0 400/60/3Ø Y Y 1 2 1 1 COMPLETE WITH CONTROL PANEL AND ALL NECESSARY ACCESSORIES
BASEMENT 4 LEVEL

FLOW ELECTRICAL DATA*


CWLP-01 6.0 60 11.0 400/60/3Ø Y Y 1 2 1 1 COMPLETE WITH CONTROL PANEL AND ALL NECESSARY ACCESSORIES TITLE DESIGNATION QTY. DUTY STAND BY LOCATION REMARKS
BASEMENT 4 LEVEL
(L/SEC) ESTIM.
(Kw)* V / Hz / Ph
* PUMPS SHALL BE PACKAGED LIFTING PUMPS FACTORY ASSEMBLED.
* PUMPS CONTROLLER SHALL BE RATED TEMPERATURE TILL 50 C. AUTOMATIC SAND COMPLETE WITH AUTOMATIC BACK WASHING VALVE
SF-01 FILTER 12.0 2 1 1 BASEMENT 4 LEVEL 0.1 220/60/1
* PUMPS CONTROLLER SHALL BE WATER PROOF TYPE. AND ALL NECESSARY ACCESSORIES
* EACH PUMP IN THE SET TO HAVE OWN VFD. ACTIVATED CARBON COMPLETE WITH AUTOMATIC BACK WASHING VALVE
* PUMPS SKID SHALL BE FACTORY ASSEMBLED FROM SAME MANUFACTURER. CF-01 FILTER 12.0 2 1 1 BASEMENT 4 LEVEL 0.1 220/60/1
AND ALL NECESSARY ACCESSORIES
* PUMPS AND ACCESSORIES SHALL BE SUITABLE FOR DRINKING WATER APPLICATION AND RO WATER.
* EACH PACKAGED PUMP SHALL INCLUDE PRESSURE TANKS. SEDIMENT CARTRIDGE
* VERTICAL INLINE MULTISTAGE PUMPS WITH VIBRATION ISOLATOR, CHECK VALVE, GATE VALVES, FLEXILE CAF-01 6.00 4 2 2 BASEMENT 4 LEVEL - - COMPLETE WITH ALL NECESSARY ACCESSORIES
5 MICRON FILTER
CONNECTIONS ALL ACCESSORIES AND PIPES STAINLESS STEEL 316 TYPE.
* PUMPS SHALL HAVE STAINLESS STEEL 316 HEADER AND ACCESSORIES. WS-01 DUPLEX WATER SOFTENER 12.00 1 1 - BASEMENT 4 LEVEL COMPLETE WITH AUTOMATIC BACK WASHING VALVE
0.1 220/60/1
* CONTROLLER SHALL BE INTEGRATED WITH BMS TO ALLOW FOR COMPLETE MONITOR AND CONTROL PUMPS. ALSO TO AND ALL NECESSARY ACCESSORIES
ALLOW KNOW THE STATUS OF THE PUMPS AND PRESSURE DIFFERENCE.
* CONTRACTOR SHALL TAKE INTO CONSIDERATION THE ACTUAL RESISTANCE THROUGH THE EQUIP., VALVES, ...ETC. UV-01 UV LIGHT 12.00 2 1 1 BASEMENT 4 LEVEL 1.0 220/60/1 COMPLETE WITH ALL NECESSARY ACCESSORIES
* CONTRACTOR SHALL SUBMIT CALCULATIONS OF PUMPS TOTAL HEAD.
UV-02 UV LIGHT (KITCHEN) 1.00 1 1 - L03 LEVEL 0.3 220/60/1 COMPLETE WITH ALL NECESSARY ACCESSORIES

CIRCULATION PUMPS SCHEDULE


* SEDIMENT CARTRIDGE 5 MICRON FILTER CAPACITY NEED TO BE * FILTERS SHALL HAVE FACTORY ASSEMBLED PANELS FROM SAME
EACH SET PUMPS QUANTITY INCREASED TO MATCH OTHER FILTERS. MANUFACTURER WITH CONNECTION TO BMS.
FLOW HEAD ELECTRICAL DATA* M.C.C. NO. PUMPS SETS * USED PIPES AND ACCESSORIES SHALL BE PN24.
PUMP LOCATION
(L/SEC) REMARKS
NO. (m) ESTIM. QUANTITY TOTAL DUTY
NORMAL EMERGENCY STAND BY
(Kw)* V / Hz / Ph

WCP-01 B04 4.50 15 1.5 220/60/1Ø Y Y 1 2 1 1 COMPLETE WITH CONTROL PANEL AND ALL NECESSARY ACCESSORIES DOMESTIC HOT WATER CALORIFIERS SCHEDULE

WCP-02 1.20 15 1.0 220/60/1Ø Y Y 1 2 1 1 COMPLETE WITH CONTROL PANEL AND ALL NECESSARY ACCESSORIES
L03 CAPACITY OPERATING
DESIGNATION TYPE LOCATION ELECTRICAL DATA QTY. REMARKS
TEMPERATURE INSTALLATION
( LITERS )
WCP-03 1 1 1 COMPLETE WITH CONTROL PANEL AND ALL NECESSARY ACCESSORIES ( °C ) ESTIM. N
L03 1.80 15 1.0 220/60/1Ø Y Y 2
(Kw)* V / Hz / Ph KEY PLAN
COMPLETE WITH THERMOSTATIC MIXING VALVES, PRESSURE AND TEMPERATURE GAUGES, SAFETY
HWC-01 ELECTRIC TECHNICAL LEVEL (3RD FLOOR) 2500 65 70 400/60/3 VERTICAL 5
* VERTICAL INLINE WATER CIRCULATING PUMP VALVES GAUGES, SAFETY VALVES AND ALL NECESSARY ACCESSORIES
* PUMP SHALL BE SUITABLE FOR WATER APPLICATION. COMPLETE WITH THERMOSTATIC MIXING VALVES, PRESSURE AND TEMPERATURE GAUGES, SAFETY
* CONTROLLER SHALL BE INCLUDED FROM SAME MANUFACTURER. HWC-02 ELECTRIC TECHNICAL LEVEL (3RD FLOOR) 500 80 20 400/60/3 VERTICAL 2
VALVES GAUGES, SAFETY VALVES AND ALL NECESSARY ACCESSORIES
* CONTROLLER SHALL BE INTEGRATED WITH BMS TO ALLOW FOR COMPLETE MONITOR AND CONTROL PUMPS.
* CONTRACTOR SHALL TAKE INTO CONSIDERATION THE ACTUAL RESISTANCE THROUGH THE EQUIP., VALVES, ...ETC.
* CONTRACTOR SHALL SUBMIT CALCULATIONS OF PUMPS TOTAL HEAD. * CALORIFIRES SHALL BE RATED TO 16 BAR.
* PROVIDE CONTROLLER FROM SAME SUPPLIER OF CALORIFIRES AND TO BE
CONNECTED WITH BMS TO CONTROL CIRCULATION PUMPS. ELECTRICAL WATER HEATER
* PROVIDE PRVS AND CHECK VALVES. DOMESTIC WATER ELECTRICAL DATA
* ALL VALVES SHALL BE STAINLESS STEEL CORE SUITABLE FOR DRINKING CAPACITY
WATER REF. LOCATION TYPE REMARKS QUANTITY
(L) TARGET H.W. TEMP. ENTERING POWER VOLT PHASE
* THERMAL INSULATION SHALL BE 10 CM MINIMUM. IP RATING
(°C) C.W. TEMP. (°C) (kW) (V) ()
* CONTROLLER SHALL BE INTEGRATED WITH BMS TO ALLOW FOR MONITOR
FIRE PUMPS SCHEDULE AIR CURTAIN SCHEDULE THE HEATERS.
EWH-01 GUARD HOUSE 50 60 10 1.20 220 1 IPX3 VERTICAL TYPE - WITH ELECTRIC HEATING ELEMENT 1
ITEM NO. REF NO. DESCRIPTION TYPE OF MATERIAL CAPACITY ELEC. DATA ELECTRICAL
SAND INTERCEPTOR
EQUIPMENT LENGTH QTY REMARKS
TAG KW VOLT PH Hz TANK
ELECTRIC, MOTOR DRIVEN, CENTRIFUGAL, PUMP CAP. : DIMENSIONS
MAIN DUTY FIRE PUMP TITLE FLOW (L/s) QTY.
HORIZONTAL, SINGLE-STAGE, SPLIT-CASE 1000 GPM 155 KW TO PROVIDE AIR LOCK FROM
01. FP-01 (AS PART OF A COMPLETE FIRE PUMP
STAR/DELTA (CLOSED TYPE) 400V/3PH/60HZ
(W x L x H mm) GREASE INTERCEPTORS SCHEDULE
SET) AT 14.6 BAR HEAD AC-01 1600 mm 9 0.50 230 1 60 EXTERNAL
PUMP TO NFPA 20, UL LISTED AND FM APPROVED
INTERCEPTOR APPROXIMATE
TO PROVIDE AIR LOCK FROM FLOW TYPE DIMENSIONS
MAIN STANDBY FIRE PUMP ELECTRIC, MOTOR DRIVEN, CENTRIFUGAL, PUMP CAP. : S.INT-01 3.15 1200x1200x1000 08 REF.
155 KW AC-02 1000 mm 5 0.50 230 1 60 EXTERNAL (GPM) (L x W x H mm)
(AS PART OF A COMPLETE FIRE PUMP HORIZONTAL, SINGLE-STAGE, SPLIT-CASE 1000 GPM
02. FP-02 AT 14.6 BAR HEAD 400V/3PH/60HZ
SET) STAR/DELTA (CLOSED TYPE)
PUMP TO NFPA 20, UL LISTED AND FM APPROVED TO PROVIDE AIR LOCK FROM GREASE INTERCEPTOR 271 HYDRO MECHANICAL 1930 x 1219 x 1219
CONNECTED TO EMERGENCY POWER SOURCE AC-03 1200 mm 5 0.25 230 1 60 * DIMENSION SHALL BE VERIFIED ACCORDING TO THE SELECTION.
EXTERNAL
* CONTROL PANEL FOR ALARM CONNECTED TO BMS.
JOCKEY FIRE PUMP TO PROVIDE AIR LOCK FROM
ELECTRIC, MOTOR DRIVEN, CENTRIFUGAL, PUMP CAP. :
03. JFP
(AS PART OF A COMPLETE FIRE PUMP
VERTICAL, MULTI-STAGE. 35 GPM 12.0 KW AC-04 2100 mm 12 1.00 230 1 60 EXTERNAL OIL INTERCEPTORS SCHEDULE NEUTRALIZATION TANK
SET) AT 15 BAR HEAD 400V/3PH/60HZ
TO PROVIDE AIR LOCK FROM INTERCEPTOR APPROXIMATE TANK
AC-05 1400 mm 2 0.25 230 1 60 EXTERNAL FLOW TITLE DESIGNATION DIMENSIONS QTY.
DIMENSIONS Limestone
REF. (GPM) XH
(L x W x H mm) lb
TYPE (mm)
DUCTED DX SPLIT AC UNITS NEUTRALIZATION TANK
OIL INTERCEPTOR 20.0 HYDRO MECHANICAL 640 x 360 x 350 NT-01 1000 711X1067 1
FAN COOLING COIL 284 LITTER
AMBIENT
OPERATING THEATRE CANOPIES
TOTAL SENSIBLE
REF. EXT. STATIC
COOLING COOLING AIR ELECTRICAL DATA REFRIGERANT TYPETEMP. QTY. EMERGENCY SCHEDULE * CONTROL PANEL FOR ALARM CONNECTED TO BMS. * CONTROL PANEL FOR ALARM CONNECTED TO BMS.
PRESSURE
CAPACITY CAPACITY
MAXIMUM DESIGN
Pa kW kW ENT. DB °C ENT. WB °C kW V PH Hz °C TAG SPACE NAME QUANTITY AIR (L/s) @0.15 m/s
OUTFLOW SPEED
CANOPY SIZE
FUEL INTERCEPTOR FOR HELICOPTER WATER TANKS ( GRP TANK ) DISCIPLINE MECHANICAL
SU/OU-01 50 5.20 4.70 25.00 18.00 2.50 230 1 60 R-410A 47.70 51 YES
F2.01-01
OPERATING
ROOM
1 1050 2.7X2.6
TITLE DESIGNATION LOCATION
EFFECTIVE
VOLUME QTY. REMARKS
REF NO.
VOLUME
(m )
3
DIMENSION
( LxWxH ) m
TYPE QTY SHEET TYPE MECHANICAL SCHEDULES
SU/OU-02 150 21.90 19.40 25.00 18.00 9.50 400 3 60 R-410A 47.70 20 YES OPERATING
F2.01-02 1 1050 2.7X2.6
ROOM
OPERATING
(L) COOLED 40 4X4X2.5 INSULATED TANK 2 MECHANICAL SCHEDULES -
NOTES: F2.01-03 1 1050 2.7X2.6 SHEET NAME
* THE CAPACITY SHOWN IN THE SCHEDULE OF EQUIPMENT IS THE SELECTED CAPACITY, IT IS THE CONTRACTOR F2.01-04
ROOM
OPERATING
1 1050 2.7X2.6
FUEL
FUEL SEPARATOR ROOF 1800 1 SOFT 40 4X4X2.5 NON INSULATED TANK 2 SHEET (20 OF 23)
ROOM SEPARATOR
RESPONSIBILITY TO TAKE INTO CONSIDERATION (WHILE DOING THE SELECTION) THE LONG PIPES RUN & THE AMBIENT CONDITIONS
* GRP TANKS ACCESSORIES SHALL BE STAINLESS STEEL 316,
* CONTROL PANEL FOR ALARM CONNECTED TO BMS. TANK SHALL BE NFS CERTIFIED FOR DRINKING WATER DATE 07/12/2023
APPLICATION .
SCALE NTS
DESIGNED BY M.T

CHECKED BY M.M SHEET NO.

APPROVED BY H.H 059-B01-MC020

You might also like