Download as pdf or txt
Download as pdf or txt
You are on page 1of 47

Construction of new 4 lane Prayagraj Southern bypass from design Km 43.

200 (near Mahuwari


Nibi Kala Uparhar) to design Km 50.860 (near Nibi Kala Uparhar) (design length 7.660 km)
Pkg-2 under Ph-I on NH-19 in the state of UP under Bharatmala on EPC mode

National Highways Authority of India


Authority Engineer for Construction of new 4 lane Prayagraj Southern bypass
from design Km 43.200 (near Mahuwari Nibi Kala Uparhar) to design Km 50.860
(near Nibi Kala Uparhar) (design length 7.660 km) Pkg-2 under Ph-I on NH-19 in
the state of UP under Bharatmala on EPC mode

AUTHORITY ENGINEER
M/s Theme Engineering Services Pvt. Ltd.

CONTRACTOR

M\S GPT INFRAPROJECT LTD.

MONTHLY PROGRESS REPORT NO.1


FOR THE MONTH OF: JANUARY-2024

Page 1 of 46 Monthly Progress Report-January-2024


“Construction of new 4 lane Prayagraj Southern bypass from design Km 43.200 (near
Mahuwari Nibi Kala Uparhar) to design Km 50.860 (near Nibi Kala Uparhar) (design length
7.660 km) Pkg-2under Ph-I on NH-19 in the state of UP under Bharatmala on EPC mode”

Contents
1. Executive Summary .................................................................................3
1.1. Construction Progress in Current Month .........................................................3
1.2 Current Issues & Recommended Action by AE..............................................................................3
1.3 Scope Summary ..................................................................................... 4-5
1.4 Strip Plan Details – To be attached as annexure ...................................................6
Project Over view............................................................................................9
2.1 Salient Features of Project. ........................................................................9
2.2 Project Milestone .................................................................................. 10
2.3 Location Map of Project (Index Map) . ............................................................. 11
2.2 Key Plan of Project ................................................................................ 12
3. Critical Issues & Action Log ...................................................................... 13
3.1 Pending Issues and action Log .................................................................. 13
3.2 Obligation as per contract: ........................................................................ 13
4. Physical Progress ................................................................................. 14
5. Land Acquisition and Clearance................................................................. 23
5.1 LA Summary - Nil ...................................................... 23
5.2 Clearance Summary:-Nil ......................................................................... 24
5.3 Status of utilities shifting: Submitted by EPC Contractor in Month ofJan-2024............ 25
6. Change of Scope and EOT ...................................................................... 29
6.1 106.85 Cr. has been recommended by AE ................................................ 29
6.2 EOT: N/A ............................................................................................... 29
7. Mobilization Resources ........................................................................... 29
8 Financial Progress Details ....................................................................... 30
8.1 Stage Payment Statement: - Nil .................................................................... 30
8.2 For Project (S-Curve): ............................................................................ 31
9.0 Summary of Quality Control Test and Weather Report ...................................... 33
9.1 Test witnessed by AE QAP Not Submitted ............................................ 41
9.2 Test Conducted By AE QAP Not Submitted ........................................... 41
10.0 Site Photographs .................................................................................. 41
10.1 Critical Issues and Action log: ................................................................... 42
10.2 NCR Status: - ........................................................................................ 42
11.0 Safety Features.................................................................................... 42
11.1 Pen Picture on Safety Features ................................................................. 42
11.2 Accident Report ................................................................................... 43
12. Organization Chart for Key Personal and supporting staff .................................. 44
13.Design and Drawing Approval list: ............................................................... 45

Page 2 of 46 MPR For the Month Of January 2024


“Construction of new 4 lane Prayagraj Southern bypass from design Km 43.200 (near
Mahuwari Nibi Kala Uparhar) to design Km 50.860 (near Nibi Kala Uparhar) (design length
7.660 km) Pkg-2under Ph-I on NH-19 in the state of UP under Bharatmala on EPC mode”

1. Executive Summary

1.1. Construction Progress in Current Month

SUMMARY OF PROGRESS-JANUARY-2024

The project consists of "Construction of new 4 lane Prayagraj Southern Greenfield Bypass from design km.
43.200 (Near Mahuwari ) to design km.50.860 (Nibi Kala Uparhar) including Major Bridge at Ganga River
of span 3.100Km (Package 2 under Phase 1) in the state of UP on EPC mode under Bharatmala Pariyojna
with total cost 739,00,00,000/-. The NHAI has awarded the contract to M/s GPT Infraprojects Limited. and
the contract signed on 20-11-2023 between National Highway Authority of India, New Delhi and M/s GPT
Infraprojects Limited
There are three different stages (viz. Development Stage, Construction Stage and Operation &
Maintenance Stage) of the Project. The Appointed Date of the Project has been fixed as 19th December
2023 by the NHAI. The Defect Liability Period of 10 years excluding the Construction Period of 910days
commenced on the Appointed Date. The construction period of 910 days completed on 15thJune 2026.

Key Reporting Metrics Value % Amount

Schedule Financial Progress (Target) (%) 3.00%

Cumulative Financial Progress up to Current Month (Target) (%) 2.10%

Financial During Current Month (Achievement) (%) 0.00%

Cumulative Financial Progress (Achievement) (%) 0.00%

1.2 Current Issues & Recommended Action by AE

1.Work Program:
Work Program is pending at the EPC end, AE’s vide Letter No. TES/TL/AE Prg. Southern Bypass
PKG-2/17 Dated:-07/02/2024 has instructed to Submit the work program at earliest.

2.Status of Change of Scope Proposals: AE’s has recommended COS of 106.85 Cr. by vide
Letter No. TES/TL/AE Prg. Southern Bypass PKG-2/11 , Dated :-31/01/2024

Page 3 of 46 MPR For the Month Of January 2024


“Construction of new 4 lane Prayagraj Southern bypass from design Km 43.200 (near
Mahuwari Nibi Kala Uparhar) to design Km 50.860 (near Nibi Kala Uparhar) (design length
7.660 km) Pkg-2under Ph-I on NH-19 in the state of UP under Bharatmala on EPC mode”

1.3 Scope Summary

A Civil Works
1 Survey Work km 7.66
1.1 TBM km 7.66
1.2 Centre Line Marking km 7.66
1.3 OGL km 7.66
B ROB
2.1 Pile Nos 36
2.2 Pile Cap Nos 8
2.3 Pier/Abutment Shaft Nos 8
2.4 Pier Cap Nos 8
2.6 Composite Girder Span 1
Fabrication
2.7 Composite Girder Erection Span 1
2.8 Deck Slab Casting Span 3
2.9 Pedestal Casting Nos 48
2.10 Bearing Fixing Nos 48
2.11 RCC Girder Casting Nos 10
C Flyover
3.1 Pile Nos 32
3.2 Pile Cap Nos 8
3.3 Pier/Abutment Shaft Nos 8
3.4 Pier Cap Nos 8
3.6 PSC Girder Casting Span 10
3.7 PSC Girder Erection Span 10
3.8 RCC Girder Casting Span 20
3.9 Deck Slab casting Span 20
3.10 Pedestal Casting Nos 60
3.11 Bearing Fixing Nos 60
3.12 Approach Slab Casting Nos 3
D Box Culvert
4.1 Excavation Nos 5
4.2 PCC Nos 5
4.3 Raft Nos 5
4.4 Wall Nos 5
4.5 Slab Nos 5
E River Ganga
5.1 Length of Ganga Bridge RMT 3100
5.2 Span Arrangement Nos (5 x 38 + 1 x 79.8 + 14
x 174.6 + 1 x 79.8 +
18 x 38)
F Drain Work

Page 4 of 46 MPR For the Month Of January 2024


“Construction of new 4 lane Prayagraj Southern bypass from design Km 43.200 (near
Mahuwari Nibi Kala Uparhar) to design Km 50.860 (near Nibi Kala Uparhar) (design length
7.660 km) Pkg-2under Ph-I on NH-19 in the state of UP under Bharatmala on EPC mode”

6.1 Excavation RMT 3800


6.2 Raft casting RMT 3800
6.3 Wall casting RMT 3800
6.4 Final finishing RMT 3800
G Highway Work
7.1 Main Carriageway RMT 4340
7.2 Embankment RMT 4340
7.3 Subgrade RMT 4340
7.4 Cement Treated Sub base RMT 4340
7.5 Cement Treated Base RMT 4340
7.6 Aggregate Inter Layer RMT 4340
7.7 Dense Bituminous Macadam RMT 4340
7.8 Bituminous Concrete RMT 4340
H RE Panel
8.1 RE Panel
8.2 RE Panel Casting Sqm 26023
8.3 RE Panel Fixing Sqm 26023

With pursuant to clause 10.1.(iv) contractor has not submitted the scope of the project.

Page 5 of 46 MPR For the Month Of January 2024


“Construction of new 4 lane Prayagraj Southern bypass from design Km 43.200 (near Mahuwari Nibi Kala Uparhar) to design Km 50.860 (near
Nibi Kala Uparhar) (design length 7.660 km) Pkg-2under Ph-I on NH-19 in the state of UP under Bharatmala on EPC mode”

1.4 Strip Plan Details – To be attached as annexure

Page 6 of 46 MPR For the Month Of January 2024


“Construction of new 4 lane Prayagraj Southern bypass from design Km 43.200 (near Mahuwari Nibi Kala Uparhar) to design Km 50.860 (near
Nibi Kala Uparhar) (design length 7.660 km) Pkg-2under Ph-I on NH-19 in the state of UP under Bharatmala on EPC mode”

Page 7 of 46 MPR For the Month Of January 2024


“Construction of new 4 lane Prayagraj Southern bypass from design Km 43.200 (near Mahuwari Nibi Kala Uparhar) to design Km 50.860 (near
Nibi Kala Uparhar) (design length 7.660 km) Pkg-2under Ph-I on NH-19 in the state of UP under Bharatmala on EPC mode”

Page 8 of 46 MPR For the Month Of January 2024


“Construction of new 4 lane Prayagraj Southern bypass from design Km 43.200 (near
Mahuwari Nibi Kala Uparhar) to design Km 50.860 (near Nibi Kala Uparhar) (design length
7.660 km) Pkg-2under Ph-I on NH-19 in the state of UP under Bharatmala on EPC mode”

Project Over view


2.1 Salient Features of Project.

Project Name “ Construction of new 4 lane Prayagraj


Southern bypass from design Km 43.200
(near Mahuwari Nibi Kala Uparhar) to
design Km 50.860 (near Nibi Kala
Uparhar) (design length 7.660 km) Pkg-
2under Ph-I on NH-19 in the state of UP
under Bharatmala on EPC mode”
Scheme/Phase Bharatmala
Mode of the Execution (BOT Toll/BOT EPC
Annuity/EPC/HAM/Item Rate/Other)
No. of Lanes/Configuration Four Lanes
Length of the Project (in KM) 7.66 KM
Total Project Cost (in Cr.) Rs.739 Cr.
No. of ROB 01
No. of Fly Over’s 01
No. of MNB 00
No. of VUP 01

No. Of Major Bridge 01


No. of Box Culverts 09
No. of Toll Plazas 00
DPR Consultant Name M/s. Artefact Projects Ltd. In association with
Renaissance IOP LLP.
EPC Contractor Name (SPV & Parent Company ) M/s GPT Infra projects Ltd
Date of Award (LOA Date) 17thOctober 2023
Appointed Date 19thDecember 2023
Construction Period (in Days) 910 days
O&M period (in Years) 10 Years
Scheduled Date of completion 15th June 2026
Authority Engineer Theme Engineering Services Pvt. Ltd.
AE Agreement Date 03rd January 2024
AE Mobilization Date 04th January 2024

Page 9 of 46 MPR For the Month Of January 2024


“Construction of new 4 lane Prayagraj Southern bypass from design Km 43.200 (near
Mahuwari Nibi Kala Uparhar) to design Km 50.860 (near Nibi Kala Uparhar) (design length
7.660 km) Pkg-2under Ph-I on NH-19 in the state of UP under Bharatmala on EPC mode”

2.2 Project Milestone

Project Milestones Status:


Appointment Date 12/19/2023 TPC 7390000000
Planned Actual
Description
Project (Days from Proportion Current
Milestone Appointed of TPC to be Scheduled Actual Status
Amount Rs Amount
Date) expended Date Date
(%)

Milestone I 319 days 10% 739000000 11/1/2024

Milestone II 546 days 35% 2586500000 16/06/2025 - - -

Milestone
774 days 70% 5173000000 30/01/2026 - - -
III

Scheduled
910 days 100% 7390000000 15/06/206 - - -
Completion

Page 10 of 46 MPR For the Month Of January 2024


“Construction of new 4 lane Prayagraj Southern bypass from design Km 43.200 (near
Mahuwari Nibi Kala Uparhar) to design Km 50.860 (near Nibi Kala Uparhar) (design length
7.660 km) Pkg-2under Ph-I on NH-19 in the state of UP under Bharatmala on EPC mode”

2.3 Location Map of Project (Index Map) “ Construction of new 4 lane Prayagraj Southern bypass
from design Km 43.200 (near Mahuwari Nibi Kala Uparhar) to design Km 50.860 (near Nibi
Kala Uparhar) (design length 7.660 km) Pkg-2 in the state of UP under Bharatmala on EPC
mode”.

Page 11 of 46 MPR For the Month Of January 2024


“Construction of new 4 lane Prayagraj Southern bypass from design Km 43.200 (near
Mahuwari Nibi Kala Uparhar) to design Km 50.860 (near Nibi Kala Uparhar) (design length
7.660 km) Pkg-2under Ph-I on NH-19 in the state of UP under Bharatmala on EPC mode”

2.2 Key Plan of Project

Start End

Km. Km. Km.


Km. 44.193 Km. 44.290 Km.46.950 Km 47.006 Km.48.860
43.200 43+817 50.860

ROB Flyover Bus Shelter Bus Shelter VUP Extra Dosed


Ganga Bridge

Page 12 of 46 MPR For the Month Of January 2024


“Construction of new 4 lane Prayagraj Southern bypass from design Km 43.200 (near
Mahuwari Nibi Kala Uparhar) to design Km 50.860 (near Nibi Kala Uparhar) (design length
7.660 km) Pkg-2under Ph-I on NH-19 in the state of UP under Bharatmala on EPC mode”

3. Critical Issues & Action Log


3.1 Pending Issues and action Log
1. Submission of Documents

3.2 Obligation as per contract:

A. Comply with applicable laws as Applicable Permits (Including renewal as required as Clause
3.1.7 as of the Contract Agreement:

Status Applicable Permits as per Schedule –F

Sl. Description Status Remarks


No.
i) The contractor shall obtain , as required under the Application Laws, the following
Application permit

1 Permission of the state government for extraction of NA


boulders from Quarry
2 Permission of village Panchayats and pollution control NA
boards for installation of crushers
3 License for use of Explosives NA
4 Permission of the state Govt. for drawing water from Not provided By
river/reservoir. Contractor
5 License from Inspector of Factories or other NA
competent Authority for Setting up batching plant
6 Clearance of Pollution control boards for setting up NA
batching plant
7 Clearance of Village Panchayats and pollution control -
boards for setting up asphalt plant
8 Permission of Village Panchayats and state Not provided by
Government for Borrow area earth the contractor
9 Any other permits or clearance required under Not provided by
Applicable laws. (Labour License ) the contractor
10 Permission and Licenses for HSD Pump Not provided by
the contractor
ii) Application permit, as required, relating to Not provided by
environmental protection and conservation shall the contractor
have been procured by the Authority in accordance
with the provisions of this Agreement

Page 13 of 46 MPR For the Month Of January 2024


“Construction of new 4 lane Prayagraj Southern bypass from design Km 43.200 (near
Mahuwari Nibi Kala Uparhar) to design Km 50.860 (near Nibi Kala Uparhar) (design length
7.660 km) Pkg-2under Ph-I on NH-19 in the state of UP under Bharatmala on EPC mode”

4. Physical Progress

Item Description Unit Scope Progress Progress Balance % Remarks


No. of Achieved up to work completion
Work for the previous
month of month
Jan
2024
1. C&G Work Km 7.66 3.66 3 0 100%
2. Centre Line Km 7.66 3.66 3 0 100%
Marking
3. OGL Km 7.66 3.66 3 0 100%
recording
4. ROB

A. Pilling Nos 36 10 0 26 28%


5. RS Wall
B. Panel Sqm 26,099 322 0 0 1%
Casting

With pursuant to clause 10.1.(iv) contractor has not submitted the scope of work.

Page 14 of 46 MPR For the Month Of January 2024


“Construction of new 4 lane Prayagraj Southern bypass from design Km 43.200 (near Mahuwari Nibi Kala Uparhar) to design Km 50.860
(near Nibi Kala Uparhar) (design length 7.660 km) Pkg-2under Ph-I on NH-19 in the state of UP under Bharatmala on EPC mode”

4 Annexures

Annex 1 Detailed list of physical components as per Schedule H

Project Cost: -
7,390,000,000
Month: - Oct-23

Weight
age in % Weight
Amount wrt
percentage Total Amount age to Total Amount per
Item Item Description contract price in Unit Side
to the (Rs,) Particular Scope Unit in Rs.
Rs.
Contract Item
Price

B1 Reconstruction /New 4-Lane realignment /bypass(flexible payment)


Earthwork up to top of the
3.75% 16,793,775 Km. BHS
Road works 1 subgrade
including Sub-Base Course 5.01% 22,436,483 Km. BHS
culverts, 2
6.06%
widening and 447,834,000
Non Bituminous Base Course 6.27% 28,079,192 Km. BHS
repair of 3
culverts.
Bituminous Base Course 4.01% 17,958,143 Km. BHS
4
Wearing Coat 2.79% 12,494,569 Km. BHS
5

Page 15 of 46 MPR For the Month Of January 2024


“Construction of new 4 lane Prayagraj Southern bypass from design Km 43.200 (near Mahuwari Nibi Kala Uparhar) to design Km 50.860
(near Nibi Kala Uparhar) (design length 7.660 km) Pkg-2under Ph-I on NH-19 in the state of UP under Bharatmala on EPC mode”

New 6-Lane Grade Separated


C
Approaches

Earthwork up to top of the sub


1.68% 7,523,611 Km. BHS
1 grade
Sub-Base Course 8.50% 38,065,890 Km. BHS
2
Non Bituminous Course 13.75% 61,577,175 Km. BHS
3
Dense Bituminous Macadam 8.63% 38,648,074 Km. BHS
4
Bituminous Concrete 6.00% 26,870,040 Km. BHS
5
New Construction (Service/Slip
D
Flexible Pavement)
Earthwork up to top of the sub
6.60% 29,557,044 Km. BHS
1 grade
Sub-Base Course(GSB ,Shoulders) 7.45% 33,363,633 Km. BHS
2
Non-Bituminous Course 8.19% 36,677,605 Km. BHS
3
Dense Bituminous Macadam 5.44% 24,362,170 Km. BHS
4
Bituminous Concrete 3.32% 14,868,089 Km. BHS
5
E New Culverts

Page 16 of 46 MPR For the Month Of January 2024


“Construction of new 4 lane Prayagraj Southern bypass from design Km 43.200 (near Mahuwari Nibi Kala Uparhar) to design Km 50.860
(near Nibi Kala Uparhar) (design length 7.660 km) Pkg-2under Ph-I on NH-19 in the state of UP under Bharatmala on EPC mode”

Culverts (Length<6m) 8.61% 38,558,507 Nos. BHS

100.00% 447,834,000

Under Passes/Overpasses
B2 New Under Passes/Overpasses
Foundation + Sub Structure: on
completion of the foundation work
including foundations for wing and 11.21% 9,443,977 RM BHS
1
return walls, abutments, piers up
to the abutment/pier cap
Super-structure: On completion of
the super-structure in all respects
including wearing coat, bearings,
Minor bridges/ expansion joints, hand rails, crash
underpasses/ 1.14% barriers, road signs and markings,
84,246,000 9.93% 8,365,628 Nos. BHS
overpasses work 2 tests on completion etc. complete
in all respect. Wearing Coat
Including expansion joints
complete in all respect as
specified
Approaches: On completion of
approaches including Retaining
walls/reinforced Earth walls
RE/Embankment Earth Filling, 33.57% 28,281,382 Nos. BHS
3
stone pitching, protection works
complete in all respect and fit for
use.

Page 17 of 46 MPR For the Month Of January 2024


“Construction of new 4 lane Prayagraj Southern bypass from design Km 43.200 (near Mahuwari Nibi Kala Uparhar) to design Km 50.860
(near Nibi Kala Uparhar) (design length 7.660 km) Pkg-2under Ph-I on NH-19 in the state of UP under Bharatmala on EPC mode”

(4) Approaches to structures only


embankment and RCC Crash
Barrier friction slab Other
components are included in road
works
a)Backfilling with Borrow Area soil,
Meter
fly ASH Reinforced Earth Soil and 35.98% 30,311,711 BHS
Cube
Filter Media
b)RCC Crash Barrier with Friction
9.31% 7,843,303 Rm. BHS
Slab
Minor
100.00% 84246000.00
Bridges/Underpasses/Overpasses

New Major Bridges


A.1
Foundation : on completion of the
foundation work including
21.46% 1,402,088,885 Rm. BHS
Major Bridges 1 foundations for return walls,
(length> 60m.) abutments, piers
works and
Sub Structure:-on completion of
ROB/RUB/
88.41% abutments, piers up to the 10.39% 678,830,546 Nos. BHS
elevated 6,533,499,000 2
abutment/pier cap
sections/flyovers
including Super-structure: Including
53.52% 3,496,728,665 Nos.
viaducts, if any 3 Bearings
Wearing Coat including Expansion
1.89% 123,483,131 Km.
4 joint
Miscellaneous Items like hand rail
3.50% 228,672,465 Rm.
5 crash barrier , road marking etc.

Page 18 of 46 MPR For the Month Of January 2024


“Construction of new 4 lane Prayagraj Southern bypass from design Km 43.200 (near Mahuwari Nibi Kala Uparhar) to design Km 50.860
(near Nibi Kala Uparhar) (design length 7.660 km) Pkg-2under Ph-I on NH-19 in the state of UP under Bharatmala on EPC mode”

Approaches: Approaches
including Retaining walls, stone 2.16% 141,123,578 Nos.
6
pitching, protection works.

Backfill with Borrow Area Soil Fly


Cubic
Ash Reinforced earth soil and Filter 0.57% 37,240,944
7 meter
media

B2 New Rob/RUB -

A ROB -

Foundation 0.54% 35,280,895 Rm.


1
Sub-Structure 0.24% 15,680,398 Nos.
2
Super Structure Including Bearing 2.04% 133,283,380 Nos.
3
Wearing Coat including Expansion
0.14% 9,146,899 Rm.
4 joint incase of ROB
Miscellaneous Items like hand rail
0.05% 3,266,750 Rm.
5 crash barrier , road marking etc.
Approaches: Approaches
including Retaining
0.68% 44,427,793 Nos.
6 walls/Reinforced Earth Wall, stone
pitching, protection works.
Approaches to structures
embankment and RCC Crash
8 Barrier friction slab Other -
components are included in road
works

Page 19 of 46 MPR For the Month Of January 2024


“Construction of new 4 lane Prayagraj Southern bypass from design Km 43.200 (near Mahuwari Nibi Kala Uparhar) to design Km 50.860
(near Nibi Kala Uparhar) (design length 7.660 km) Pkg-2under Ph-I on NH-19 in the state of UP under Bharatmala on EPC mode”

Backfill with Borrow Area Soil Fly


0.56% 36,587,594 Nos.
8 Ash Reinforced earth soil and Filter
media
RCC Crash Barrier with Friction
0.25% 16,333,748 Rm.
9 Slab
New Elevated
C2 -
Section/Flyovers/Grade Separator

Foundation 0.51% 33,320,845 Rm.


1
Sub-Structure 0.21% 13,720,348 Nos.
2

Super Structure Including Bearing 0.31% 20,253,847 Rm.


3
Wearing Coat including Expansion
0.11% 7,186,849 Rm.
4 joint incase of ROB
Miscellaneous Items like hand rail
0.01% 653,350 Rm.
5 crash barrier , road marking etc.
Approaches: Approaches
including Retaining
0.37% 24,173,946 Nos.
6 walls/Reinforced Earth Wall, stone
pitching, protection works.
Approaches to structures
embankment and RCC Crash
Barrier friction slab Other -
components are included in road
works
Backfill with Borrow Area Soil Fly
Ash Reinforced earth soil and Filter 0.33% 21,560,547 Rm
8
media

Page 20 of 46 MPR For the Month Of January 2024


“Construction of new 4 lane Prayagraj Southern bypass from design Km 43.200 (near Mahuwari Nibi Kala Uparhar) to design Km 50.860
(near Nibi Kala Uparhar) (design length 7.660 km) Pkg-2under Ph-I on NH-19 in the state of UP under Bharatmala on EPC mode”

RCC Crash Barrier with Friction 0.16% 10,453,598 Rm


9
Slab

100.00% 6533499000.00

Road side drains


i RCC and Earthen Drain 8.40% 20,981,688 Km. BHS
Road signs, marking, km stones,
ii 3.02% 7,543,416 Km. BHS
safety devices, crash barrier…
iii Project facilities
a Bus Bays & Bus Shelters 0.12% 299,738 Nos. BHS
ATMS( Advance Traffic
b 2.24% 5,595,117 Km. BHS
Management system
Other Items
Other works 3.38% h-1 electrification 12.52% 31,272,706 Nos.
249,782,000
h-2 junction improvement 3.40% 8,492,588 Nos.
h-3 utility ducts 6.26% 15,636,353 Km.
h-4 protection works 0.00% - Nos.
h-5 Boundary Pillars 0.05% 124,891 Km.
Median plantation 0.79% 1,973,278 Nos.
site clearance 1.09% 2,722,624 Km.
construction of median and island 0.28% 699,390 Nos.
MBCB, Railing ,RCC crash barrier 16.16% 40,364,771 Rm

Page 21 of 46 MPR For the Month Of January 2024


“Construction of new 4 lane Prayagraj Southern bypass from design Km 43.200 (near Mahuwari Nibi Kala Uparhar) to design Km 50.860
(near Nibi Kala Uparhar) (design length 7.660 km) Pkg-2under Ph-I on NH-19 in the state of UP under Bharatmala on EPC mode”

low height subway(RUB) at ROB


10.15% 25,352,873 Nos.
including approach road
staircase of ROB 1.78% 4,446,120 Nos.
ROB instrumental scheme 1.48% 3,696,774 Nos.
Drainage chamber at median 1.19% 2,972,406 Nos.
Bridge health and monitoring
31.07% 77,607,267 Nos.
system

100.00%

shifting of electrical & water


Shifting of Utility supply utility
1.01%
services
Utility shifting 100.00% 249,782,000 Km.

100.00%

Project Cost
7,390,000,000

Contractor has not submitted scope of the work as per clause 10.1.(iv)

Page 22 of 46 MPR For the Month Of January 2024


“Construction of new 4 lane Prayagraj Southern bypass from design Km 43.200 (near Mahuwari Nibi Kala Uparhar) to design Km 50.860
(near Nibi Kala Uparhar) (design length 7.660 km) Pkg-2under Ph-I on NH-19 in the state of UP under Bharatmala on EPC mode”

5. Land Acquisition and Clearance


5.1 LA Summary - Nil

Details of Existing Land:


Sr. Description Total Required (Ha) Total in possession at start Total to be Acquired (Ha)
No (Ha)
1 Existing ROW
2 Private Land to be acquired
3 Public Land to be transferred

4 Grand Total

Page 23 of 46 MPR For the Month Of January 2024


“Construction of new 4 lane Prayagraj Southern bypass from design Km 43.200 (near Mahuwari Nibi Kala Uparhar) to design Km 50.860
(near Nibi Kala Uparhar) (design length 7.660 km) Pkg-2under Ph-I on NH-19 in the state of UP under Bharatmala on EPC mode”

Sr. Description %
No

1 Award I
2 Award II
3 Total Award I+II
4 Amount deposited with
CALA by NHAI
5 Amount Disbursed by CALA
6 Balance amount Available
with CALA

5.2 Clearance Summary:-Nil

Environment
Proposal Description Status Length Impacted Current Stage Issues/ Comments

Environmental Clearance Achieved


Forest Land
Proposal Description Status Length Impacted Current Stage Issues/ Comments

Page 24 of 46 MPR For the Month Of January 2024


“Construction of new 4 lane Prayagraj Southern bypass from design Km 43.200
(near Mahuwari Nibi Kala Uparhar) to design Km 50.860 (near Nibi Kala
Uparhar) (design length 7.660 km) Pkg-2under Ph-I on NH-19 in the state of UP
under Bharatmala on EPC mode”

5.3 Status of utilities shifting: Submitted by EPC Contractor in Month ofJan-2024

Sr. Particulars Scope (No’s) Executed Balance Remarks


No (No’s) (No’s)
1 Electrical Poles 43 10 33
2 EHT Transmission Line 1 Nil 1
Crossing
3 EHT Pylon Transmission 1 Nil 1
Line
4 LT Crossing 5 Nil 3
5 Crossing (HT/LT),33Kv 6 Nil 5
6 Crossing (HT/LT),11Kv 14 Nil 10

5.4 List of Land Hindrance

Submitted by Contractor

Page 25 of 46 MPR For the Month Of January 2024


“Construction of new 4 lane Prayagraj Southern bypass from design Km 43.200 (near Mahuwari Nibi Kala Uparhar) to design Km
50.860 (near Nibi Kala Uparhar) (design length 7.660 km) Pkg-2under Ph-I on NH-19 in the state of UP under Bharatmala on EPC
mode”

Village Name of Work


Design Chainage Length
Name
Gata No SIDE
Affected
Reason for not working Remarks
SL. NO
Fro
To 4-lane
m
43+
1 43+212 12.00 Rehi Kala 121 CL Highway Compensation Issues Building
200
43+ Aata Chakki
2 43+256 15.50 Rehi Kala 90 RHS Highway Compensation Issues
240 (building)
43+
3 43+318 2.80 Rehi Kala 90 LHS Highway Compensation Issues tube well
315
43+ Agriculture
4 43+470 120.00 Rehi Kala 112 LHS Highway Compensation Issues
350 Land
Pipe line across the
43+
5 43+735 35.00 Rehi Kala CL ROB Abutment alignment, shifting IOCL Pipe Line
700
to be required
44+ Agriculture
6 44+190 140.00 Mahuwari 126 LHS Highway Compensation Issues
050 Land
44+ 653, School
7 44+146 56.00 Mahuwari RHS Flyover Compensation Issues
090 655,657 Building
44+
8 44+186 22.00 Mahuwari 649 RHS Highway Compensation Issues Building
164
Sarawati UPSIDA
44+ UPSIDA Flyover/Highwa
46+660 2440.00 Hi Tech BHS UPSIDA Land Issue infrastructure
220 Land y
City s
Sarawati
45+ UPSIDA
9 45+434 12.00 Hi Tech LHS Highway Compensation Issues Building
422 Land
City
45+ Villagers
10 46+020 90.00 Kuria - LHS Box Culvert Compensation Issues
930 Houses
46+ Villagers
11 46+037 7.00 Kuria - RHS Highway Compensation Issues
030 Houses

Page 26 of 46 MPR For the Month Of January 2024


“Construction of new 4 lane Prayagraj Southern bypass from design Km 43.200 (near Mahuwari Nibi Kala Uparhar) to design Km
50.860 (near Nibi Kala Uparhar) (design length 7.660 km) Pkg-2under Ph-I on NH-19 in the state of UP under Bharatmala on EPC
mode”

46+ Villagers
12 46+388 5.00 Kuria - RHS Highway Compensation Issues
383 Houses
46+ Villagers
13 46+393 5.00 Kuria - RHS Highway Compensation Issues
388 Houses
46+ Mayashri College
14 46+549 100.00 - RHS Highway Compensation Issues
449 College Boundary
46+ Pandeypu Agriculture
15 46+780 80.00 - BHS Highway Compensation Issues
700 ra Land
46+ Agriculture
16 47+000 100.00 Velvet 191-192 RHS Highway Compensation Issues
900 Land
46+
17 46+973 10.00 Velvet 191-192 LHS Highway Compensation Issues Toilet
963
47+ Lawayan Villagers
18 47+086 86.00 - BHS VUP Compensation Issues
000 Kala house
Villagers
house
47+ Lawayan
19 47+146 18.00 - RHS VUP Approach Compensation Issues
128 Kala

47+ Lawayan Ganga Bridge- Villagers


20 47+162 10.00 - LHS Compensation Issues
152 Kala Approach house
47+ Lawayan Ganga Bridge- Villagers
21 47+175 9.00 - LHS Compensation Issues
166 Kala Approach house
47+ Lawayan Ganga Bridge- Villagers
22 47+208 8.00 - LHS Compensation Issues
200 Kala Approach house

Page 27 of 46 MPR For the Month Of January 2024


“Construction of new 4 lane Prayagraj Southern bypass from design Km 43.200 (near Mahuwari Nibi Kala Uparhar) to design Km
50.860 (near Nibi Kala Uparhar) (design length 7.660 km) Pkg-2under Ph-I on NH-19 in the state of UP under Bharatmala on EPC
mode”

Agriculture
Land
owner-
Banarasi Lal,
Nibikala, Ganga Bridge- Nandlal,
23 49+600 49+700 100.00 45,55G BHS Compensation Issues
Kachar Approach -A2 Motilal,
Amritlal,
Dasrath,
Hiralal,
Rangbahadur
Agriculture
Land
owner-
Nibikala, Ganga Bridge-
24 49+700 49+800 100.00 49, 54K BHS Compensation Issues Bholanath,
Kachar Approach -A2
Ramsurat,
Ramsingh,
Santosh

Page 28 of 46 MPR For the Month Of January 2024


“Construction of new 4 lane Prayagraj Southern bypass from design Km 43.200 (near Mahuwari Nibi Kala Uparhar) to design Km
50.860 (near Nibi Kala Uparhar) (design length 7.660 km) Pkg-2under Ph-I on NH-19 in the state of UP under Bharatmala on EPC
mode”

Activities permitted in the ROW:


Vendors have been finalized for electric line shifting works.

6. Change of Scope and EOT


6.1 106.85 Cr. has been recommended by AE

6.2 EOT: N/A

7. Mobilization Resources

SL DESCRIPTION OF ITEMS NOS.


No
1 RE Panel/Facia panel Moulds 31
2 Transit Mixer 5
3 WMM plant 100 TPH 1
4 WMM plant Cabin with control panel, Motor & other Accessories 1
5 Motor Grader-Komatsu 1
6 Motor Cycle-Splendor (UP61BD9803) 3
7 Hydraulics Excavator-Kobelco 1
8 Digger drum Compactor-Kobelco 1
9 BP CP-18 2
10 BP CP-30 1
11 DG-30KVA 1
12 DG-160KVA 2
13 DG-82.5KVA 1
14 DG- 50 KVA 2

Page 29 of 46 MPR For the Month Of January 2024


“Construction of new 4 lane Prayagraj Southern bypass from design Km 43.200 (near Mahuwari Nibi Kala Uparhar) to design Km
50.860 (near Nibi Kala Uparhar) (design length 7.660 km) Pkg-2under Ph-I on NH-19 in the state of UP under Bharatmala on EPC
mode”

15 DG- 63 KVA 1
16 DG- 30 KVA 2
17 DG- 20 KVA 1
18 BP-350 Concrete Pump 4
19 Bar Bending Machine 1
20 Bar Cutting Machine 1
21 Soil Compactor 2
22 Container (20x8) 4
23 backhoe Loader 2
24 Hydra 14-15T 2
25 Auto Level 1
26 Total Station 1
27 Motor Grader 1
28 Excavator 3
29 Tipper 1
30 Water Tanker 10-12KL 1
31 Water Tanker 3KL 2
32 TMR 2
33 Tractor Trolley 2

8 Financial Progress Details

8.1 Stage Payment Statement: - Nil

Page 30 of 46 MPR For the Month Of January 2024


“Construction of new 4 lane Prayagraj Southern bypass from design Km 43.200 (near Mahuwari Nibi Kala Uparhar) to
design Km 50.860 (near Nibi Kala Uparhar) (design length 7.660 km) Pkg-2under Ph-I on NH-19 in the state of UP under
Bharatmala on EPC mode”

8.2 For Project (S-Curve):

S-Curve
140.00

120.00

100.00

80.00

60.00

40.00

20.00

0.00
Qtr-01 Qtr-02 Qtr-03 Qtr-04 Qtr-01 Qtr-02 Qtr-03 Qtr-04 Qtr-01 Qtr-02
FY 2024-25 FY 2025-26 FY 2026-27

FY 2024-25 FY 2025-26 FY 2026-27


Qtr-01 Qtr-02 Qtr-03 Qtr-04 Qtr-01 Qtr-02 Qtr-03 Qtr-04 Qtr-01 Qtr-02
32.88 14.28 45.46 92.61 126.95 128.96 119.75 111.71 66.37 00.00

Page 31 of 46 MPR For the Month Of January 2024


“Construction of new 4 lane Prayagraj Southern bypass from design Km 43.200 (near
Mahuwari Nibi Kala Uparhar) to design Km 50.860 (near Nibi Kala Uparhar) (design length
7.660 km) Pkg-2under Ph-I on NH-19 in the state of UP under Bharatmala on EPC mode”

Bank Guarantee Details: - EPC Contractor


Bank Guarantees submitted against of Performance Guarantee and Additional Performance
Policy No Dated Bond Amount Expiry Insurer Remarks
Date
120400502351000000001 07-11-2023 11,08,50,000.00 07-05-2026 The New India Performance
Assurance Security
Company Ltd

120400502351000000002 07-11-2023 5,99,92,000.00 07-05-2026 The New India Additional


Assurance Performance
Company Ltd Security

Security

Page 32 of 46 MPR For the Month Of January 2024


“Construction of new 4 lane Prayagraj Southern bypass from design Km 43.200 (near Mahuwari Nibi Kala Uparhar) to design Km
50.860 (near Nibi Kala Uparhar) (design length 7.660 km) Pkg-2under Ph-I on NH-19 in the state of UP under Bharatmala on EPC
mode”

9.0 Summary of Quality Control Test and Weather Report

Frequency Previous Month This Month Cumulative up to till

Total Test up Total Tests Total Tests


Description Total Test up Total Test up Total Tests in Cumulative Cumulative Cumulative Remarks
Frequency of Frequency of to previous in this in this
Unit to previous to previous this month Nos. of Test Nos. of Nos. of
Test(No.) Test (Qty.) month month month
month (Pass) month (Fail) (Conducted) (Conducted) Test (Pass) Test (Fail)
(Conducted) (Pass) (Fail)

Original Ground level


(OGL)

0 0 0 0 0 0 0 0 0
FREE SWELLING INDEX 1 Test/500 M 1 Test/500 M 1 Test/500 M

0 0 0 0 0 0 0 0 0
Sieve Analysis ( GSA ) 1 Test/500 M 1 Test/500 M 1 Test/500 M

0 0 0 0 0 0 0 0 0
ATTERBERG LIMITS 1 Test/500 M 1 Test/500 M 1 Test/500 M

0 0 0 0 0 0 0 0 0
MAX. DRY DENSITY TEST 1 Test/500 M 1 Test/500 M 1 Test/500 M

CALIFORNIABEARING 0 0 0 0 0 0 0 0 0
RATIO (CBR) 1 Test/500 M 1 Test/500 M 1 Test/500 M

1 Set Per
1 Set Per 3000 1 Set Per 3000 3000 m² 0 0 0 0 0 0 0 0 0
DENSITY OF COMP.LAYER m² m² (1 Set =10
( NO of Pits ) (1 Set =10 pit) (1 Set =10 pit) pit)
Sampling (Borrow Area/
Cutting Soil)

2Test Per 3000 2Test Per 3000 2Test Per 0 0 0 0 0 0 0 0 0


FREE SWELLING INDEX M3 M3 3000 M3

2 Test Per 3000 2 Test Per 3000 2 Test Per 0 0 0 0 0 0 0 0 0


Sieve Analysis ( GSA ) M3 M3 3000 M3

2 Test Per 3000 2 Test Per 3000 2 Test Per 0 0 0 0 0 0 0 0 0


ATTERBERG LIMITS M3 M3 3000 M3

2 Test Per 3000 2 Test Per 3000 2 Test Per 0 0 0 0 0 0 0 0 0


MAX. DRY DENSITY TEST M3 M3 3000 M3

1 Set Per
1 Set Per 3000 1 Set Per 3000
DENSITY OF COMP.LAYER 3000 m²
m² (1 Set =10 m² 0 0 0 0 0 0 0 0 0
( NO of Pits ) (1 Set =10
pit) (1 Set =10 pit)
pit)

1 Test Per 3000 1 Test Per 3000 1 Test Per 0 0 0 0 0 0 0 0 0


California Bearing Ratio M3 M3 3000 M3

Page 33 of 46 MPR For the Month Of January 2024


“Construction of new 4 lane Prayagraj Southern bypass from design Km 43.200 (near Mahuwari Nibi Kala Uparhar) to design Km
50.860 (near Nibi Kala Uparhar) (design length 7.660 km) Pkg-2under Ph-I on NH-19 in the state of UP under Bharatmala on EPC
mode”
0 0 0

CTSB SAMPLING

1 TEST Per 1 TEST Per 1 TEST Per 0 0 0 0 0 0 0 0 0


MAX.DRY DENSITY TEST SOURCE SOURCE SOURCE

1 Test Per 400 1 Test Per 400 1 Test Per 0 0 0 0 0 0 0 0 0


GRADATION (Combined) M3 M3 400 M3

1 Test Per 400 1 Test Per 400 1 Test Per 0 0 0 0 0 0 0 0 0


ATTERBERG LIMITS M3 M3 400 M3

0 0 0 0 0 0 0 0 0
CBR AS REQUIRED AS REQUIRED AS REQUIRED

1 TEST PER 1 TEST PER 1 TEST PER 0 0 0 0 0 0 0 0 0


WATER ABSORPTION SOURCE SOURCE SOURCE

AGGREGATE IMPACT 0 0 0 0 0 0 0 0 0
VALUE AS REQUIRED AS REQUIRED AS REQUIRED

0 0 0 0 0 0 0 0 0
Moisture Content AS REQUIRED AS REQUIRED AS REQUIRED

DENSITY OF COMP.LAYER 1 Test Per 1000 1 Test Per 1000 1 Test Per 0 0 0 0 0 0 0 0 0
( NO of Pits ) M² M² 1000 M²

WET MIX MACADAM

1 TEST Per 1 TEST Per 1 TEST Per 0 0 0 0 0 0 0 0 0


MAX.DRY DENSITY TEST SOURCE SOURCE SOURCE

1 Test Per 200 1 Test Per 200 1 Test Per 0 0 0 0 0 0 0 0 0


GRADATION:- WMM MIX M3 M3 200 M3

1 Test Per 200 1 Test Per 200 1 Test Per 0 0 0 0 0 0 0 0 0


ATTERBERG LIMITS M3 M3 200 M3

1 Test Per 500 1 Test Per 500 1 Test Per 0 0 0 0 0 0 0 0 0


FLAKINESS TEST M3 M3 500 M3

1 TEST PER 1 TEST PER 1 TEST PER 0 0 0 0 0 0 0 0 0


WATER ABSORPTION SOURCE SOURCE SOURCE

AGGREGATE IMPACT 1 Test Per 1000 1 Test Per 1000 1 Test Per 0 0 0 0 0 0 0 0 0
VALUE M3 M3 1000 M3

0 0 0 0 0 0 0 0 0
Moisture Content AS REQUIRED AS REQUIRED AS REQUIRED

DENSITY OF COMP.LAYER 1 Test Per 1000 1 Test Per 1000 1 Test Per 0 0 0 0 0 0 0 0 0
( NO of Pits ) M² M² 1000 M²

Page 34 of 46 MPR For the Month Of January 2024


“Construction of new 4 lane Prayagraj Southern bypass from design Km 43.200 (near Mahuwari Nibi Kala Uparhar) to design Km
50.860 (near Nibi Kala Uparhar) (design length 7.660 km) Pkg-2under Ph-I on NH-19 in the state of UP under Bharatmala on EPC
mode”

PRIME COAT

1-TEST PER 1-TEST PER 1-TEST PER


Viscosity Test 0 0 0 0 0 0 0 0 0
Each Lots Each Lots Each Lots

RATE OF SPREAD OF 3-TEST PER 0 0 0 0 0 0 0 0 0


BINDER (Tray Test) 3-TEST PER DAY 3-TEST PER DAY DAY

TACK COAT

1-TEST PER 1-TEST PER 1-TEST PER 0 0 0 0 0 0 0 0 0


Viscosity Test Each Lots Each Lots Each Lots

RATE OF SPREAD OF 3-TEST PER 0 0 0 0 0 0 0 0 0


BINDER (Tray Test) 3-TEST PER DAY 3-TEST PER DAY DAY
DENSE BITUMEN
MACADAM ( DBM )

1 SET PER
1 SET PER 400 400 MT
GRADATION OF 1 SET PER 400
MT OR MINM 2 0 0 0 0 0 0 0 0 0
AGGREGATE (INDIVIDUAL) MT OR MINM 2
OR MINM 2 TEST PER
DAY

1 SET PER
1 SET PER 400 400 MT
GRADATION OF 1 SET PER 400
MT OR MINM 2 0 0 0 0 0 0 0 0 0
AGGREGATE (COMBINED) MT OR MINM 2
OR MINM 2 TEST PER
DAY

AGGREGATE IMPACT 1 SET PER 350 1 SET PER 350 1 SET PER 0 0 0 0 0 0 0 0 0
VALUE M3 M3 350 M3

COMBINED FLAKINESS AND 1 SET PER 350 1 SET PER 350 1 SET PER 0 0 0 0 0 0 0 0 0
ELONGATION TEST M3 M3 350 M3

STRIPPING VALUE OF 1 TEST Per 1 TEST Per 1 TEST Per 0 0 0 0 0 0 0 0 0


AGGREGATE SOURCE SOURCE SOURCE

1 TEST Per 1 TEST Per 1 TEST Per 0 0 0 0 0 0 0 0 0


WATER ABSORPTION SOURCE SOURCE SOURCE

3 MARSHAL 0 0 0 0 0 0 0 0 0
3 MARSHAL 3 MARSHAL
MOULD FOR
MARSHAL STABILITY MOULD FOR MOULD FOR
EACH 400
EACH 400 EACH 400
TONNES OF
TONNES OF MIX TONNES OF MIX
MIX SUBJECT 0 0 0 0 0 0 0 0 0
SUBJECT TO SUBJECT TO
MARSHAL FLOW TO MINM OF
MINM OF 2 TEST MINM OF 2 TEST
2 TEST PER
PER DAY PER PER DAY PER
DAY PER
PLANT PLANT 0 0 0 0 0 0 0 0 0
PLANT
MARSHAL DENSITY

Page 35 of 46 MPR For the Month Of January 2024


“Construction of new 4 lane Prayagraj Southern bypass from design Km 43.200 (near Mahuwari Nibi Kala Uparhar) to design Km
50.860 (near Nibi Kala Uparhar) (design length 7.660 km) Pkg-2under Ph-I on NH-19 in the state of UP under Bharatmala on EPC
mode”

0 0 0 0 0 0 0 0 0
% AIR VOIDS

%VOIDS WITH FILL 0 0 0 0 0 0 0 0 0


BITUMEN (VFB)

%VOIDS IN MINERAL 0 0 0 0 0 0 0 0 0
AGGREGATE (VMA)

1 TEST PER 0 0 0 0 0 0 0 0 0
MAXIMUM SP. GRAVITY 1 TEST PER DAY 1 TEST PER DAY DAY

1 SET PER 0 0 0 0 0 0 0 0 0
400 MT OR
1 SET PER 400 1 SET PER 400 MINM 2 TEST
BINDER CONTENT MT OR MINM 2 MT OR MINM 2 PER DAY

ONE TEST PER ONE TEST PER ONE TEST 0 0 0 0 0 0 0 0 0


CORE CUTTING 700 Sq m 700 Sq m PER 700 Sq m

BITUMENIOUS CONCRETE
(BC)
1 SET PER
400 MT OR
MINM 2 0 0 0 0 0 0 0 0 0
GRADATION OF 1 SET PER 400 1 SET PER 400 TEST PER
AGGREGATE (INDIVIDUAL) MT OR MINM 2 MT OR MINM 2 DAY
1 SET PER
400 MT OR 0 0 0 0 0 0 0 0 0
GRADATION OF 1 SET PER 400 1 SET PER 400 MINM 2 TEST
AGGREGATE (COMBINED) MT OR MINM 2 MT OR MINM 2 PER DAY

AGGREGATE IMPACT 1 SET PER 350 1 SET PER 350 1 SET PER 0 0 0 0 0 0 0 0 0
VALUE M3 M3 350 M3

COMBINED FLAKINESS AND 1 SET PER 350 1 SET PER 350 1 SET PER 0 0 0 0 0 0 0 0 0
ELONGATION TEST M3 M3 350 M3

STRIPPING VALUE OF 1 TEST Per 1 TEST Per 1 TEST Per 0 0 0 0 0 0 0 0 0


AGGREGATE SOURCE SOURCE SOURCE

1 TEST Per 1 TEST Per 1 TEST Per 0 0 0 0 0 0 0 0 0


WATER ABSORPTION SOURCE SOURCE SOURCE

0 0 0 0 0 0 0 0 0
MARSHAL STABILITY

0 0 0 0 0 0 0 0 0
3 MARSHAL
MARSHAL FLOW 3 MARSHAL 3 MARSHAL MOULD FOR
MOULD FOR MOULD FOR EACH 400
EACH 400 EACH 400 TONNES OF 0 0 0 0 0 0 0 0 0
MARSHAL DENSITY TONNES OF MIX TONNES OF MIX MIX SUBJECT
SUBJECT TO SUBJECT TO TO MINM OF
MINM OF 2 TEST MINM OF 2 TEST 2 TEST PER
PER DAY PER PER DAY PER DAY PER 0 0 0 0 0 0 0 0 0
% AIR VOIDS PLANT PLANT PLANT

Page 36 of 46 MPR For the Month Of January 2024


“Construction of new 4 lane Prayagraj Southern bypass from design Km 43.200 (near Mahuwari Nibi Kala Uparhar) to design Km
50.860 (near Nibi Kala Uparhar) (design length 7.660 km) Pkg-2under Ph-I on NH-19 in the state of UP under Bharatmala on EPC
mode”

%VOIDS WITH FILL 0 0 0 0 0 0 0 0 0


BITUMEN (VFB)

%VOIDS IN MINERAL 0 0 0 0 0 0 0 0 0
AGGREGATE (VMA)

1 TEST PER 0 0 0 0 0 0 0 0 0
MAXIMUM SP. GRAVITY 1 TEST PER DAY 1 TEST PER DAY DAY
1 SET PER
1 SET PER 400 1 SET PER 400 400 MT OR 0 0 0 0 0 0 0 0 0
BINDER CONTENT MT OR MINM 2 MT OR MINM 2 MINM 2

ONE TEST PER ONE TEST PER ONE TEST 0 0 0 0 0 0 0 0 0


CORE CUTTING 700 Sq m 700 m3 PER 700 m3

BITUMEN TESTS

1 TEST Per 1 TEST Per 1 TEST Per 0 0 0 0 0 0


Penetration Test Consignment Consignment Consignment 0 0 0

1 TEST Per 1 TEST Per 1 TEST Per 0 0 0 0 0 0


Softening Test Consignment Consignment Consignment 0 0 0

1 TEST Per 1 TEST Per 1 TEST Per 0 0 0 0 0 0


Ductility Test Consignment Consignment Consignment 0 0 0

1 TEST Per 1 TEST Per 1 TEST Per 0 0 0 0 0 0


Solubility Test SOURCE SOURCE SOURCE 0 0 0

1 TEST Per 1 TEST Per 1 TEST Per 0 0 0 0 0 0


Flash/Fire Point Test SOURCE SOURCE SOURCE 0 0 0

1 TEST Per 1 TEST Per 1 TEST Per 0 0 0 0 0 0


Specific Gravity Test SOURCE SOURCE SOURCE 0 0 0

1 TEST Per 1 TEST Per 1 TEST Per 0 0 0 0 0 0


Visocity Test Consignment Consignment Consignment 0 0 0

CEMENT TESTS

1 TEST Per 1 TEST Per 1 TEST Per 0 0 0 0 0 0


FINENESS TEST Consignment Consignment Consignment 0 0 0

1 TEST Per 1 TEST Per 1 TEST Per 0 0 0 0 0 0


CONSISTENCY TEST Consignment Consignment Consignment 0 0 0

1 TEST Per 1 TEST Per 1 TEST Per 0 0 0 0 0 0


SETTING TIME Consignment Consignment Consignment 0 0 0

1 TEST Per 1 TEST Per 1 TEST Per 0 0 0 0 0 0


SOUNDNESS Consignment Consignment Consignment 0 0 0

Page 37 of 46 MPR For the Month Of January 2024


“Construction of new 4 lane Prayagraj Southern bypass from design Km 43.200 (near Mahuwari Nibi Kala Uparhar) to design Km
50.860 (near Nibi Kala Uparhar) (design length 7.660 km) Pkg-2under Ph-I on NH-19 in the state of UP under Bharatmala on EPC
mode”

0 0 0 0 0 0
3-Days 3-Days 3-Days 0 0 0
COMPRESSIVE STRENGTH
OF CEMENT MORTAR 0 0 0 0 0 0
CUBE 7-days 7-days 7-days 0 0 0

0 0 0 0 0 0
28-days 28-days 28-days 0 0 0

CONCRETE WORKS

COARSE AGGREGATES
GRADATION 20MM & 1 test/Day 1 test/Day 1 test/Day 0 0 0 0 0 0 0 0 0
10MM

FINE AGGREGATES 0 0 0 0 0 0
GRADATION 1 test/Day 1 test/Day 1 test/Day 0 0 0

Water Absorption of 0 0 0 0 0 0
Aggregate CA/FA/ Boulder AS REQUIRED AS REQUIRED AS REQUIRED 0 0 0

0 0 0 0 0 0
Specific Gravity CA/FA AS REQUIRED AS REQUIRED AS REQUIRED 0 0 0

AGGREGATE IMPACT 0 0 0 0 0 0
VALUE AS REQUIRED AS REQUIRED AS REQUIRED 0 0 0

0 0 0 0 0 0
FLAKINESS TEST AS REQUIRED AS REQUIRED AS REQUIRED 0 0 0

SILT & CLAY CONTENT 0 0 0 0 0 0


(75 mic Passing) AS REQUIRED AS REQUIRED AS REQUIRED 0 0 0

7 Days-Mix 7 Days-Mix 0 0 0 0 0 0
COMPRESSIVE STRENGTH 7 Days Design Design 0 0 0
OF CONCRETE CUBE
28 Days-Mix 28 Days-Mix 0 0 0 0 0 0
28 Days Design Design 0 0 0

7 Days-Mix 7 Days-Mix 7 Days-Mix 0 0 0 0 0 0


COMPRESSIVE STRENGTH
Design Design Design 0 0 0
OF CONCRETE CUBE Mix
Design. 28 Days-Mix 28 Days-Mix 28 Days-Mix 0 0 0 0 0 0
Design Design Design 0 0 0
Concrete Mix Design

Grade
Pcc - M15, M20
RCC - M25,M30,M35,M35-RE Pannel, M35-Pile.

Page 38 of 46 MPR For the Month Of January 2024


“Construction of new 4 lane Prayagraj Southern bypass from design Km 43.200 (near
Mahuwari Nibi Kala Uparhar) to design Km 50.860 (near Nibi Kala Uparhar) (design length
7.660 km) Pkg-2under Ph-I on NH-19 in the state of UP under Bharatmala on EPC mode”

Weather Report:

Date Temperature (°C) Humidity (%) Weather Rain Cumulativ Remark


Conditio Fall e Rain Fall
Minimu Maximu Minimu Maximu n (mm) (mm)
m m m m
1-Jan-24 10 21.5 56 69 Sunny 0.0 0

2-Jan-24 12.3 20.9 55 72 Sunny 0.0 0.0

3-Jan-24 11 19.6 56 70 Sunny 0.0 0.0

4-Jan-24 12.1 16.8 55 67 Sunny 0.0 0.0

5-Jan-24 13.4 17.7 56 64 Sunny 0.0 0.0

6-Jan-24 12.9 20.6 56 65 Sunny 1.0 1.0

7-Jan-24 12.4 24.2 57 66 Sunny 0.0 1.0

8-Jan-24 14.0 26.0 56 67 Foggy 0.0 1.0

9-Jan-24 15.2 23.3 57 68 Sunny 0.0 1.0

10-Jan- 16.6 25.9 59 69 Sunny 0.0 1.0


24
11-Jan- 9 19.0 56 67 Foggy 0.0 1.0
24
12-Jan- 7 19.0 57 68 Foggy 0.0 1.0
24
13-Jan- 7 20.0 48 59 Sunny 0.0 1.0
24
14-Jan- 7 19.0 47 60 Foggy 0.0 1.0
24
15-Jan- 6 18 50 59 Sunny 3.0 4.0
24
16-Jan- 6 18 51 59 Foggy 0.0 4.0
24
17-Jan- 7 18 52 61 Sunny 0.0 4.0
24
18-Jan- 7 18 50 63 Foggy 0.0 4.0
24
19-Jan- 7 21 53 64 Sunny 0.0 4.0
24
20-Jan- 5 20 52 67 Foggy 0.0 4.0
24

Page 39 of 46 MPR For the Month Of January 2024


“Construction of new 4 lane Prayagraj Southern bypass from design Km 43.200 (near
Mahuwari Nibi Kala Uparhar) to design Km 50.860 (near Nibi Kala Uparhar) (design length
7.660 km) Pkg-2under Ph-I on NH-19 in the state of UP under Bharatmala on EPC mode”
21-Jan- 6 23.8 55 68 Sunny 0.0 4.0
24
22-Jan- 7 24.7 53 65 Foggy 0.0 4.0
24
23-Jan- 7 20.6 52 64 Sunny 0.0 4.0
24
24-Jan- 5 22.8 50 63 Foggy 0.0 4.0
24
25-Jan- 6 20.4 52 64 Sunny 0.0 4.0
24
26-Jan- 7 21.5 51 65 Sunny 0.0 4.0
24
27-Jan- 7 19.8 50 64 Foggy 0.0 4.0
24
28-Jan- 10 21.0 51 63 Sunny 0.0 4.0
24
29-Jan- 10 21.9 53 64 Sunny 2.0 6.0
24
30-Jan- 9 22.2 52 63 Sunny 0.0 6.0
24
31-Jan- 8 25.5 53 64 Sunny 0.0 6.0
24

Weather
45
40
35
30
25
20
15
10
5
0
2-Jan-24

7-Jan-24

12-Jan-24
1-Jan-24

3-Jan-24
4-Jan-24
5-Jan-24
6-Jan-24

8-Jan-24
9-Jan-24
10-Jan-24
11-Jan-24

13-Jan-24
14-Jan-24
15-Jan-24
16-Jan-24
17-Jan-24
18-Jan-24
19-Jan-24
20-Jan-24
21-Jan-24
22-Jan-24
23-Jan-24
24-Jan-24
25-Jan-24
26-Jan-24
27-Jan-24
28-Jan-24
29-Jan-24
30-Jan-24
31-Jan-24

Minimum Maximum

Page 40 of 46 MPR For the Month Of January 2024


“Construction of new 4 lane Prayagraj Southern bypass from design Km 43.200 (near
Mahuwari Nibi Kala Uparhar) to design Km 50.860 (near Nibi Kala Uparhar) (design length
7.660 km) Pkg-2under Ph-I on NH-19 in the state of UP under Bharatmala on EPC mode”
9.1 Test witnessed by AE QAP Not Submitted
9.2 Test Conducted By AE QAP Not Submitted

10.0 Site Photographs

Page 41 of 46 MPR For the Month Of January 2024


“Construction of new 4 lane Prayagraj Southern bypass from design Km 43.200 (near
Mahuwari Nibi Kala Uparhar) to design Km 50.860 (near Nibi Kala Uparhar) (design length
7.660 km) Pkg-2under Ph-I on NH-19 in the state of UP under Bharatmala on EPC mode”
10.1 Critical Issues and Action log:
Hard Copy of RFI must be on site.

10.2 NCR Status: -


Sr. NCR No. NCR Description Active Status Close reference Action
No.
1 1 Without SBC leveling pad work - -
started

11.0 Safety Features

11.1 Pen Picture on Safety Features


Details to be provided after assessment of the site requirement vis-a-vis provisions in the concession
agreement

Location Of Block Suggested Remedial Additional Financial Implications Of


Spots Measures Within Provision Remedial Additional Remedial Measures
Of Concession Agreement Measures (If For Authority(Cr.)
Any)
- - - -

Page 42 of 46 MPR For the Month Of January 2024


“Construction of new 4 lane Prayagraj Southern bypass from design Km 43.200 (near Mahuwari Nibi Kala Uparhar) to design
Km 50.860 (near Nibi Kala Uparhar) (design length 7.660 km) Pkg-2under Ph-I on NH-19 in the state of UP under Bharatmala
on EPC mode”

11.2 Accident Report


No. of
A B C D E F G H I J K affected
persons

Help provided by
Time of accident
Chainage no

Intersection type of
Nature of accident

Weather condition
Load conditions of
Accident location
Sex (M/F)

Classification of

Type of vehicle
Road condition

Type of victim
Age of victim
Date
S No

accident

vehicle

control
Causes

Minor
Major
Fatal
- - - - - - - - - - - - - - - - - - - -

- - - - - - - - - - - - - - - - - - - -

- - - - - - - - - - - - - - - - - - - -

Note: -Nil Accident.

Page 43 of 46 MPR For the Month Of January 2024


“Construction of new 4 lane Prayagraj Southern bypass from design Km 43.200 (near Mahuwari Nibi Kala Uparhar) to design
Km 50.860 (near Nibi Kala Uparhar) (design length 7.660 km) Pkg-2under Ph-I on NH-19 in the state of UP under Bharatmala
on EPC mode”

12. Organization Chart for Key Personal and supporting staff

Mr. Sachin Mishra Asst.


Highway Engineer

Mr. Srikant tripathi (Quantity


Surveyor)
Mr. Kamweshar Prasad
(Resident Cum Highway
Engineer)
Permanand
CAD Expert

Mr. Kapil Dev


(Survey Engineer )

Mr.D.K Gupta ( Authorized


Signatory ) ( Team Leader) Mr. Mr. Shivam Singh and Avinash
(Bridge /Structure Engineer) Singh (Asst. Bridge Engineer )

Mr. Girijesh Kumar


Road Safety Expert

Mr. Sujeet Tiwari


Mr.Akash shrivastva and Mr. Satyam
Senior Quality Cum Material singh (AQME)
Expert

Page 44 of 46 MPR For the Month Of January 2024


“Construction of new 4 lane Prayagraj Southern bypass from design Km 43.200 (near Mahuwari Nibi Kala Uparhar) to design
Km 50.860 (near Nibi Kala Uparhar) (design length 7.660 km) Pkg-2under Ph-I on NH-19 in the state of UP under Bharatmala
on EPC mode”
13.Design and Drawing Approval list:

Sr Description Chainage Status Remarks


No.
Highway
1 P&PMCW Under review
2 P&PSR Under review
3 Drain Under review
4 Signage Not Submitted
5 Utility Crossing Not Submitted
6 Median drain Not Submitted
7 Lighting Under preparation
8 ATMS Under preparation
9 RE wall Submitted
10 Pavement design Traffic survey completed

Structure
5 ROB 43+817 Submitted to Railway
6 Flyover 44+193 Under review
7 VUP 47+006 Not Submitted
8 Major Bridge 48+860 Not Submitted
14 Box Culverts Not Submitted
15 Box Culverts Not Submitted

Page 45 of 46 MPR For the Month Of January 2024


“Construction of new 4 lane Prayagraj Southern bypass from design Km 43.200 (near
Mahuwari Nibi Kala Uparhar) to design Km 50.860 (near Nibi Kala Uparhar) (design length
7.660 km) Pkg-2under Ph-I on NH-19 in the state of UP under Bharatmala on EPC mode”

Thank you

Page 46 of 46 MPR For the Month Of January 2024

You might also like