AUTHORITY ENGINEER
M/s Theme Engineering Services Pvt. Ltd.
CONTRACTOR
Contents
1. Executive Summary .................................................................................3
1.1. Construction Progress in Current Month .........................................................3
1.2 Current Issues & Recommended Action by AE..............................................................................3
1.3 Scope Summary ..................................................................................... 4-5
1.4 Strip Plan Details – To be attached as annexure ...................................................6
Project Over view............................................................................................9
2.1 Salient Features of Project. ........................................................................9
2.2 Project Milestone .................................................................................. 10
2.3 Location Map of Project (Index Map) . ............................................................. 11
2.2 Key Plan of Project ................................................................................ 12
3. Critical Issues & Action Log ...................................................................... 13
3.1 Pending Issues and action Log .................................................................. 13
3.2 Obligation as per contract: ........................................................................ 13
4. Physical Progress ................................................................................. 14
5. Land Acquisition and Clearance................................................................. 23
5.1 LA Summary - Nil ...................................................... 23
5.2 Clearance Summary:-Nil ......................................................................... 24
5.3 Status of utilities shifting: Submitted by EPC Contractor in Month ofJan-2024............ 25
6. Change of Scope and EOT ...................................................................... 29
6.1 106.85 Cr. has been recommended by AE ................................................ 29
6.2 EOT: N/A ............................................................................................... 29
7. Mobilization Resources ........................................................................... 29
8 Financial Progress Details ....................................................................... 30
8.1 Stage Payment Statement: - Nil .................................................................... 30
8.2 For Project (S-Curve): ............................................................................ 31
9.0 Summary of Quality Control Test and Weather Report ...................................... 33
9.1 Test witnessed by AE QAP Not Submitted ............................................ 41
9.2 Test Conducted By AE QAP Not Submitted ........................................... 41
10.0 Site Photographs .................................................................................. 41
10.1 Critical Issues and Action log: ................................................................... 42
10.2 NCR Status: - ........................................................................................ 42
11.0 Safety Features.................................................................................... 42
11.1 Pen Picture on Safety Features ................................................................. 42
11.2 Accident Report ................................................................................... 43
12. Organization Chart for Key Personal and supporting staff .................................. 44
13.Design and Drawing Approval list: ............................................................... 45
1. Executive Summary
SUMMARY OF PROGRESS-JANUARY-2024
The project consists of "Construction of new 4 lane Prayagraj Southern Greenfield Bypass from design km.
43.200 (Near Mahuwari ) to design km.50.860 (Nibi Kala Uparhar) including Major Bridge at Ganga River
of span 3.100Km (Package 2 under Phase 1) in the state of UP on EPC mode under Bharatmala Pariyojna
with total cost 739,00,00,000/-. The NHAI has awarded the contract to M/s GPT Infraprojects Limited. and
the contract signed on 20-11-2023 between National Highway Authority of India, New Delhi and M/s GPT
Infraprojects Limited
There are three different stages (viz. Development Stage, Construction Stage and Operation &
Maintenance Stage) of the Project. The Appointed Date of the Project has been fixed as 19th December
2023 by the NHAI. The Defect Liability Period of 10 years excluding the Construction Period of 910days
commenced on the Appointed Date. The construction period of 910 days completed on 15thJune 2026.
1.Work Program:
Work Program is pending at the EPC end, AE’s vide Letter No. TES/TL/AE Prg. Southern Bypass
PKG-2/17 Dated:-07/02/2024 has instructed to Submit the work program at earliest.
2.Status of Change of Scope Proposals: AE’s has recommended COS of 106.85 Cr. by vide
Letter No. TES/TL/AE Prg. Southern Bypass PKG-2/11 , Dated :-31/01/2024
A Civil Works
1 Survey Work km 7.66
1.1 TBM km 7.66
1.2 Centre Line Marking km 7.66
1.3 OGL km 7.66
B ROB
2.1 Pile Nos 36
2.2 Pile Cap Nos 8
2.3 Pier/Abutment Shaft Nos 8
2.4 Pier Cap Nos 8
2.6 Composite Girder Span 1
Fabrication
2.7 Composite Girder Erection Span 1
2.8 Deck Slab Casting Span 3
2.9 Pedestal Casting Nos 48
2.10 Bearing Fixing Nos 48
2.11 RCC Girder Casting Nos 10
C Flyover
3.1 Pile Nos 32
3.2 Pile Cap Nos 8
3.3 Pier/Abutment Shaft Nos 8
3.4 Pier Cap Nos 8
3.6 PSC Girder Casting Span 10
3.7 PSC Girder Erection Span 10
3.8 RCC Girder Casting Span 20
3.9 Deck Slab casting Span 20
3.10 Pedestal Casting Nos 60
3.11 Bearing Fixing Nos 60
3.12 Approach Slab Casting Nos 3
D Box Culvert
4.1 Excavation Nos 5
4.2 PCC Nos 5
4.3 Raft Nos 5
4.4 Wall Nos 5
4.5 Slab Nos 5
E River Ganga
5.1 Length of Ganga Bridge RMT 3100
5.2 Span Arrangement Nos (5 x 38 + 1 x 79.8 + 14
x 174.6 + 1 x 79.8 +
18 x 38)
F Drain Work
With pursuant to clause 10.1.(iv) contractor has not submitted the scope of the project.
Milestone
774 days 70% 5173000000 30/01/2026 - - -
III
Scheduled
910 days 100% 7390000000 15/06/206 - - -
Completion
2.3 Location Map of Project (Index Map) “ Construction of new 4 lane Prayagraj Southern bypass
from design Km 43.200 (near Mahuwari Nibi Kala Uparhar) to design Km 50.860 (near Nibi
Kala Uparhar) (design length 7.660 km) Pkg-2 in the state of UP under Bharatmala on EPC
mode”.
Start End
A. Comply with applicable laws as Applicable Permits (Including renewal as required as Clause
3.1.7 as of the Contract Agreement:
4. Physical Progress
With pursuant to clause 10.1.(iv) contractor has not submitted the scope of work.
4 Annexures
Project Cost: -
7,390,000,000
Month: - Oct-23
Weight
age in % Weight
Amount wrt
percentage Total Amount age to Total Amount per
Item Item Description contract price in Unit Side
to the (Rs,) Particular Scope Unit in Rs.
Rs.
Contract Item
Price
100.00% 447,834,000
Under Passes/Overpasses
B2 New Under Passes/Overpasses
Foundation + Sub Structure: on
completion of the foundation work
including foundations for wing and 11.21% 9,443,977 RM BHS
1
return walls, abutments, piers up
to the abutment/pier cap
Super-structure: On completion of
the super-structure in all respects
including wearing coat, bearings,
Minor bridges/ expansion joints, hand rails, crash
underpasses/ 1.14% barriers, road signs and markings,
84,246,000 9.93% 8,365,628 Nos. BHS
overpasses work 2 tests on completion etc. complete
in all respect. Wearing Coat
Including expansion joints
complete in all respect as
specified
Approaches: On completion of
approaches including Retaining
walls/reinforced Earth walls
RE/Embankment Earth Filling, 33.57% 28,281,382 Nos. BHS
3
stone pitching, protection works
complete in all respect and fit for
use.
Approaches: Approaches
including Retaining walls, stone 2.16% 141,123,578 Nos.
6
pitching, protection works.
B2 New Rob/RUB -
A ROB -
100.00% 6533499000.00
100.00%
100.00%
Project Cost
7,390,000,000
Contractor has not submitted scope of the work as per clause 10.1.(iv)
4 Grand Total
Sr. Description %
No
1 Award I
2 Award II
3 Total Award I+II
4 Amount deposited with
CALA by NHAI
5 Amount Disbursed by CALA
6 Balance amount Available
with CALA
Environment
Proposal Description Status Length Impacted Current Stage Issues/ Comments
Submitted by Contractor
46+ Villagers
12 46+388 5.00 Kuria - RHS Highway Compensation Issues
383 Houses
46+ Villagers
13 46+393 5.00 Kuria - RHS Highway Compensation Issues
388 Houses
46+ Mayashri College
14 46+549 100.00 - RHS Highway Compensation Issues
449 College Boundary
46+ Pandeypu Agriculture
15 46+780 80.00 - BHS Highway Compensation Issues
700 ra Land
46+ Agriculture
16 47+000 100.00 Velvet 191-192 RHS Highway Compensation Issues
900 Land
46+
17 46+973 10.00 Velvet 191-192 LHS Highway Compensation Issues Toilet
963
47+ Lawayan Villagers
18 47+086 86.00 - BHS VUP Compensation Issues
000 Kala house
Villagers
house
47+ Lawayan
19 47+146 18.00 - RHS VUP Approach Compensation Issues
128 Kala
Agriculture
Land
owner-
Banarasi Lal,
Nibikala, Ganga Bridge- Nandlal,
23 49+600 49+700 100.00 45,55G BHS Compensation Issues
Kachar Approach -A2 Motilal,
Amritlal,
Dasrath,
Hiralal,
Rangbahadur
Agriculture
Land
owner-
Nibikala, Ganga Bridge-
24 49+700 49+800 100.00 49, 54K BHS Compensation Issues Bholanath,
Kachar Approach -A2
Ramsurat,
Ramsingh,
Santosh
7. Mobilization Resources
15 DG- 63 KVA 1
16 DG- 30 KVA 2
17 DG- 20 KVA 1
18 BP-350 Concrete Pump 4
19 Bar Bending Machine 1
20 Bar Cutting Machine 1
21 Soil Compactor 2
22 Container (20x8) 4
23 backhoe Loader 2
24 Hydra 14-15T 2
25 Auto Level 1
26 Total Station 1
27 Motor Grader 1
28 Excavator 3
29 Tipper 1
30 Water Tanker 10-12KL 1
31 Water Tanker 3KL 2
32 TMR 2
33 Tractor Trolley 2
S-Curve
140.00
120.00
100.00
80.00
60.00
40.00
20.00
0.00
Qtr-01 Qtr-02 Qtr-03 Qtr-04 Qtr-01 Qtr-02 Qtr-03 Qtr-04 Qtr-01 Qtr-02
FY 2024-25 FY 2025-26 FY 2026-27
Security
0 0 0 0 0 0 0 0 0
FREE SWELLING INDEX 1 Test/500 M 1 Test/500 M 1 Test/500 M
0 0 0 0 0 0 0 0 0
Sieve Analysis ( GSA ) 1 Test/500 M 1 Test/500 M 1 Test/500 M
0 0 0 0 0 0 0 0 0
ATTERBERG LIMITS 1 Test/500 M 1 Test/500 M 1 Test/500 M
0 0 0 0 0 0 0 0 0
MAX. DRY DENSITY TEST 1 Test/500 M 1 Test/500 M 1 Test/500 M
CALIFORNIABEARING 0 0 0 0 0 0 0 0 0
RATIO (CBR) 1 Test/500 M 1 Test/500 M 1 Test/500 M
1 Set Per
1 Set Per 3000 1 Set Per 3000 3000 m² 0 0 0 0 0 0 0 0 0
DENSITY OF COMP.LAYER m² m² (1 Set =10
( NO of Pits ) (1 Set =10 pit) (1 Set =10 pit) pit)
Sampling (Borrow Area/
Cutting Soil)
1 Set Per
1 Set Per 3000 1 Set Per 3000
DENSITY OF COMP.LAYER 3000 m²
m² (1 Set =10 m² 0 0 0 0 0 0 0 0 0
( NO of Pits ) (1 Set =10
pit) (1 Set =10 pit)
pit)
CTSB SAMPLING
0 0 0 0 0 0 0 0 0
CBR AS REQUIRED AS REQUIRED AS REQUIRED
AGGREGATE IMPACT 0 0 0 0 0 0 0 0 0
VALUE AS REQUIRED AS REQUIRED AS REQUIRED
0 0 0 0 0 0 0 0 0
Moisture Content AS REQUIRED AS REQUIRED AS REQUIRED
DENSITY OF COMP.LAYER 1 Test Per 1000 1 Test Per 1000 1 Test Per 0 0 0 0 0 0 0 0 0
( NO of Pits ) M² M² 1000 M²
AGGREGATE IMPACT 1 Test Per 1000 1 Test Per 1000 1 Test Per 0 0 0 0 0 0 0 0 0
VALUE M3 M3 1000 M3
0 0 0 0 0 0 0 0 0
Moisture Content AS REQUIRED AS REQUIRED AS REQUIRED
DENSITY OF COMP.LAYER 1 Test Per 1000 1 Test Per 1000 1 Test Per 0 0 0 0 0 0 0 0 0
( NO of Pits ) M² M² 1000 M²
PRIME COAT
TACK COAT
1 SET PER
1 SET PER 400 400 MT
GRADATION OF 1 SET PER 400
MT OR MINM 2 0 0 0 0 0 0 0 0 0
AGGREGATE (INDIVIDUAL) MT OR MINM 2
OR MINM 2 TEST PER
DAY
1 SET PER
1 SET PER 400 400 MT
GRADATION OF 1 SET PER 400
MT OR MINM 2 0 0 0 0 0 0 0 0 0
AGGREGATE (COMBINED) MT OR MINM 2
OR MINM 2 TEST PER
DAY
AGGREGATE IMPACT 1 SET PER 350 1 SET PER 350 1 SET PER 0 0 0 0 0 0 0 0 0
VALUE M3 M3 350 M3
COMBINED FLAKINESS AND 1 SET PER 350 1 SET PER 350 1 SET PER 0 0 0 0 0 0 0 0 0
ELONGATION TEST M3 M3 350 M3
3 MARSHAL 0 0 0 0 0 0 0 0 0
3 MARSHAL 3 MARSHAL
MOULD FOR
MARSHAL STABILITY MOULD FOR MOULD FOR
EACH 400
EACH 400 EACH 400
TONNES OF
TONNES OF MIX TONNES OF MIX
MIX SUBJECT 0 0 0 0 0 0 0 0 0
SUBJECT TO SUBJECT TO
MARSHAL FLOW TO MINM OF
MINM OF 2 TEST MINM OF 2 TEST
2 TEST PER
PER DAY PER PER DAY PER
DAY PER
PLANT PLANT 0 0 0 0 0 0 0 0 0
PLANT
MARSHAL DENSITY
0 0 0 0 0 0 0 0 0
% AIR VOIDS
%VOIDS IN MINERAL 0 0 0 0 0 0 0 0 0
AGGREGATE (VMA)
1 TEST PER 0 0 0 0 0 0 0 0 0
MAXIMUM SP. GRAVITY 1 TEST PER DAY 1 TEST PER DAY DAY
1 SET PER 0 0 0 0 0 0 0 0 0
400 MT OR
1 SET PER 400 1 SET PER 400 MINM 2 TEST
BINDER CONTENT MT OR MINM 2 MT OR MINM 2 PER DAY
BITUMENIOUS CONCRETE
(BC)
1 SET PER
400 MT OR
MINM 2 0 0 0 0 0 0 0 0 0
GRADATION OF 1 SET PER 400 1 SET PER 400 TEST PER
AGGREGATE (INDIVIDUAL) MT OR MINM 2 MT OR MINM 2 DAY
1 SET PER
400 MT OR 0 0 0 0 0 0 0 0 0
GRADATION OF 1 SET PER 400 1 SET PER 400 MINM 2 TEST
AGGREGATE (COMBINED) MT OR MINM 2 MT OR MINM 2 PER DAY
AGGREGATE IMPACT 1 SET PER 350 1 SET PER 350 1 SET PER 0 0 0 0 0 0 0 0 0
VALUE M3 M3 350 M3
COMBINED FLAKINESS AND 1 SET PER 350 1 SET PER 350 1 SET PER 0 0 0 0 0 0 0 0 0
ELONGATION TEST M3 M3 350 M3
0 0 0 0 0 0 0 0 0
MARSHAL STABILITY
0 0 0 0 0 0 0 0 0
3 MARSHAL
MARSHAL FLOW 3 MARSHAL 3 MARSHAL MOULD FOR
MOULD FOR MOULD FOR EACH 400
EACH 400 EACH 400 TONNES OF 0 0 0 0 0 0 0 0 0
MARSHAL DENSITY TONNES OF MIX TONNES OF MIX MIX SUBJECT
SUBJECT TO SUBJECT TO TO MINM OF
MINM OF 2 TEST MINM OF 2 TEST 2 TEST PER
PER DAY PER PER DAY PER DAY PER 0 0 0 0 0 0 0 0 0
% AIR VOIDS PLANT PLANT PLANT
%VOIDS IN MINERAL 0 0 0 0 0 0 0 0 0
AGGREGATE (VMA)
1 TEST PER 0 0 0 0 0 0 0 0 0
MAXIMUM SP. GRAVITY 1 TEST PER DAY 1 TEST PER DAY DAY
1 SET PER
1 SET PER 400 1 SET PER 400 400 MT OR 0 0 0 0 0 0 0 0 0
BINDER CONTENT MT OR MINM 2 MT OR MINM 2 MINM 2
BITUMEN TESTS
CEMENT TESTS
0 0 0 0 0 0
3-Days 3-Days 3-Days 0 0 0
COMPRESSIVE STRENGTH
OF CEMENT MORTAR 0 0 0 0 0 0
CUBE 7-days 7-days 7-days 0 0 0
0 0 0 0 0 0
28-days 28-days 28-days 0 0 0
CONCRETE WORKS
COARSE AGGREGATES
GRADATION 20MM & 1 test/Day 1 test/Day 1 test/Day 0 0 0 0 0 0 0 0 0
10MM
FINE AGGREGATES 0 0 0 0 0 0
GRADATION 1 test/Day 1 test/Day 1 test/Day 0 0 0
Water Absorption of 0 0 0 0 0 0
Aggregate CA/FA/ Boulder AS REQUIRED AS REQUIRED AS REQUIRED 0 0 0
0 0 0 0 0 0
Specific Gravity CA/FA AS REQUIRED AS REQUIRED AS REQUIRED 0 0 0
AGGREGATE IMPACT 0 0 0 0 0 0
VALUE AS REQUIRED AS REQUIRED AS REQUIRED 0 0 0
0 0 0 0 0 0
FLAKINESS TEST AS REQUIRED AS REQUIRED AS REQUIRED 0 0 0
7 Days-Mix 7 Days-Mix 0 0 0 0 0 0
COMPRESSIVE STRENGTH 7 Days Design Design 0 0 0
OF CONCRETE CUBE
28 Days-Mix 28 Days-Mix 0 0 0 0 0 0
28 Days Design Design 0 0 0
Grade
Pcc - M15, M20
RCC - M25,M30,M35,M35-RE Pannel, M35-Pile.
Weather Report:
Weather
45
40
35
30
25
20
15
10
5
0
2-Jan-24
7-Jan-24
12-Jan-24
1-Jan-24
3-Jan-24
4-Jan-24
5-Jan-24
6-Jan-24
8-Jan-24
9-Jan-24
10-Jan-24
11-Jan-24
13-Jan-24
14-Jan-24
15-Jan-24
16-Jan-24
17-Jan-24
18-Jan-24
19-Jan-24
20-Jan-24
21-Jan-24
22-Jan-24
23-Jan-24
24-Jan-24
25-Jan-24
26-Jan-24
27-Jan-24
28-Jan-24
29-Jan-24
30-Jan-24
31-Jan-24
Minimum Maximum
Help provided by
Time of accident
Chainage no
Intersection type of
Nature of accident
Weather condition
Load conditions of
Accident location
Sex (M/F)
Classification of
Type of vehicle
Road condition
Type of victim
Age of victim
Date
S No
accident
vehicle
control
Causes
Minor
Major
Fatal
- - - - - - - - - - - - - - - - - - - -
- - - - - - - - - - - - - - - - - - - -
- - - - - - - - - - - - - - - - - - - -
Structure
5 ROB 43+817 Submitted to Railway
6 Flyover 44+193 Under review
7 VUP 47+006 Not Submitted
8 Major Bridge 48+860 Not Submitted
14 Box Culverts Not Submitted
15 Box Culverts Not Submitted
Thank you