METHOD STATEMENT
FOR
BI-DIRECTIONAL STATIC LOAD TEST (BDSLT)
(Preliminary Test Piles – 900mm Diameter)
Prepared for:
CONTENTS
1. Introduction
1.1 Project Information
1.2 Test Objectives
1.3 Applicable Standard/References
2. Sub-surface Conditions
3. Bi-directional Static Load Test
3.1 Test Theory and Advantages
3.2 Test Instrumentations
3.3 Installation of Super Cell
3.4 Load Test Procedures
3.5 Loading & Unloading Sequence
3.6 Pile Shaft Axial Force Test
3.7 Test Results Analysis And Conclusion
4. Worksheet
4.1 Field Responsibilities
4.2 Equipment/materials and staff provided by contractor
5. Risk Assessment
Appendices
A. Test Pile Layout
B. Super Cell position
C. Schematic Section of Test Pile & Reference pile/Reference Beam Layout
D. Super Cell Calibration Certificate Reference
E. Project References With Same Test Instrumentations
1
Hangzhou Ougan Technology Co., Ltd
17th Floor, Wanda Plaza, Hangxing Rd, Gongshu District, Hangzhou, 310015, P.R. China
Tel: 86-571-28223950 Fax: 86-571-28993137
1. Introduction
1.1 Project Information
One Bi-directional Static Load Tests will be applied to one bored pile at__. The details of this
Preliminary Test Piles are as below:
2. Sub-surface Conditions
Borehole log
3
Hangzhou Ougan Technology Co., Ltd
17th Floor, Wanda Plaza, Hangxing Rd, Gongshu District, Hangzhou, 310015, P.R. China
Tel: 86-571-28223950 Fax: 86-571-28993137
a. Precast Concrete:
i. Super Cell is put on even ground with cone-shape mechanism upwards. Special material
should be put under the super cell to prevent super cell from bonding to ground;
ii. After pouring of concrete into cone-shape mechanism, vibrating spear is used to tamp; the
concrete strength should be no less than pile shaft concrete strength;
iii. Super Cell couldn’t be removed within 10 hours after cast;
4
Hangzhou Ougan Technology Co., Ltd
17th Floor, Wanda Plaza, Hangxing Rd, Gongshu District, Hangzhou, 310015, P.R. China
Tel: 86-571-28223950 Fax: 86-571-28993137
3.4.2. Level the ground surrounding the test pile and put up an 8m length reference beam about
1m above ground over the test pile. Provide metal frame and canvas sheet over the reference
beam to form a space of 6m×4m to protect the test equipment from weather and dust. Dial
gauges with electronic displacement transducers are fixed onto the reference beam to record
displacements of the load-cell.
3.4.3. Bring in an 8’ ×10’ metal container or suitable equivalent with suitable space heater for test
equipments, including hydraulic pump with pressure gauges, computer and data collector.
3.4.4. Carry out loading and unloading to the test pile according to the attached sequence, the
upward & downward displacements against applied loads would be shown on the computer
screen. Test can be ended once either one of below situations happen:
a. The max. stroke of load cell is reached (150mm);
b. The test load has been applied;
c. The max. rated load of cell is reached;
d. Capacity of the pile above or below the Super-cell location has been reached.
6
Hangzhou Ougan Technology Co., Ltd
17th Floor, Wanda Plaza, Hangxing Rd, Gongshu District, Hangzhou, 310015, P.R. China
Tel: 86-571-28223950 Fax: 86-571-28993137
Ground ±0m
Cross-section 1 12 2 pcs -2.0m
Cross-section 2 15 2 pcs -5.0m
Cross-section 3 18 2 Pcs -8.0m
Cross-section 4 21 2 Pcs -11.0m
Cross-section 5 24 2 Pcs -14.0m
Cross-section 6 27 2 Pcs -17.0m
Cross-section 7 30 2 Pcs -19.0m
Cross-section 8 33 4 Pcs -21.0m
Load cell -23.0m
8
Hangzhou Ougan Technology Co., Ltd
17th Floor, Wanda Plaza, Hangxing Rd, Gongshu District, Hangzhou, 310015, P.R. China
Tel: 86-571-28223950 Fax: 86-571-28993137
Cross-section 9 35 4Pcs -25.5m
Pile bottom -26.0m
We can get two load deformation curves from self-balancing test while there is only one
load deformation curve in traditional load test. In order to equivalently switch the result of
self-balancing into normal, we should firstly compare both the bearing mechanism so that
we can find the law of conversion, secondly, the bearing capacity and subsidence value
which get from the self-balance test should accord with the reality of project for control the
error. The key to these problems is doing enough comparison tests. See figure 4-2.
3.7.2 Equivalent Conversion Method
E.0.1: To convert two Q-S curves of upward and downward from Bi-directional static load
test into a Q-S curve of traditional load-deformation, to get pile top settlement, as shown by
E.0.1.
E.0.3 Calculation with embedded strain gauge should conform below provisions:
According to item7 in E.0.2, the pile above load cell is broken down into numerous
points(drawing E.0.3-1), in which any point i axial force Q(i) and displacement S(i) could be
shown as below:
2. Unit i (drawing E.0.3-2) midpoint displacement sm (i) could be shown as below formula:
(E.0.3-3)
3. Based on the above formula, the curve between skin friction resistance qsi from
bi-directional load test and displacement sm(i), qsi as regarded as the function of sm(i), by any
sm(i) we could get qsi., and also could get Qd with the curve between load cell load Qd and
downward displacement Sd. So for 2n unknown numbers from S(i) and Sm(i), 2n
simultaneous equations could be built. In case the load hasn’t been transferred to load cell, the
12
Hangzhou Ougan Technology Co., Ltd
17th Floor, Wanda Plaza, Hangxing Rd, Gongshu District, Hangzhou, 310015, P.R. China
Tel: 86-571-28223950 Fax: 86-571-28993137
upper pile Q-su curve may be utilized for conversion directly.
4. Worksheet
4.1. Field Responsibilities
No. Content Field Responsibilities
1 Precast cone-shape flow-guiding Contractor provide concrete and pour
mechanism under Ougan supervision
2 Weld super cell to reinforcing Contractor weld under Ougan
cage supervision.
3 Funnel reinforcement fabrication Contractor fabricate under Ougan
supervision. Φ20 or bigger steel rod
with minimum length 1.2m each is
used.
4 Telltale casing, rod extensometer Contractor do under Ougan supervision
and hydraulic hoses arrangement
5 Tie telltale casing and hydraulic Contractor do under Ougan supervision
hoses when lowering the
reinforcing cage
6 Put simple reinforcing cage Contractor fabricate and put on site
between pile cut-off level and under Ougan supervision.
borehole top, to guide and protect
pipelines.
7 Mark pipelines Ougan mark.
8 Provide and setup suitable stable Contractor do it under Ougan
reference beam(s) as required to supervision.
ensure good reference point.
9 Set up a shelter above test pile Contractor set up
after installation
10 Site security, dry and level Contractor do it
platform area around test pile
area.
11 Test equipment set up in the field Contractor do under Ougan supervision
12 Field testing Ougan do testing, but contractor should
ensure working conditions such as
lighting, generator/electricity supply,
air-conditioned shelter etc.
13 Any required support during Contractor do it
conduction of the test
14 Disassembly of testing equipment Ougan do it
13
Hangzhou Ougan Technology Co., Ltd
17th Floor, Wanda Plaza, Hangxing Rd, Gongshu District, Hangzhou, 310015, P.R. China
Tel: 86-571-28223950 Fax: 86-571-28993137
Staff requirement
Stage Name Unit Qty Remark
If 1 welding machine
was only for 1
Welder person 2
welder, than we need
2 welding machines.
Strain gauges welding and person
3
Installation tying
Telltale casing and hydraulic person
hoses tying when lowering 3
reinforcing cage
Pipelines protection on pile person
2
head after installation
Level and clean testing person
2
platform
Set up reference beam and person
4 Crane is required
shelter
Testing
Welder person 2
Electrician person 1
person Assistant of Ougan
Backman for testing 1
engineer
Materials
Name Unit Qty Application
20 steel rod m 1.2m length, 96pcs Horn reinforcement
Welding super cell to
20 rebar m 0.3m length, 40pcs
reinforcing cage
9m length, 2pcs;1m length,
32a I-beam pcs Reference beam, reference piles
8pcs
Precast cone-shape flow-guiding
Concrete m3 1.0
mechanism
5. Risk Assessment
RISK MATRIX AND RISK ACTIONS
Likelihood
A – Very B– C– D– E–
Unlikely Unlikely Possible Likely Very
Hazard (a freak (a rare (could (not certain
Reputation Assets Environment People Likely
Severity combination combination happen to
(almost
of of when happen but
factors factors would additional an inevitable
14
Hangzhou Ougan Technology Co., Ltd
17th Floor, Wanda Plaza, Hangxing Rd, Gongshu District, Hangzhou, 310015, P.R. China
Tel: 86-571-28223950 Fax: 86-571-28993137
required be factors are additional that an
for incident to required for present but factor incident
result) an otherwise may result would
incident to unlikely to in an result)
result) occur) accident)
Little or no actual Slight
Slight
1. Slight Slight Impact or potential for health A1 B1 C1 D1 E1
damage
damage. effect/injury
Within site
boundary, Minor
Minor
2. Minor Limited Impact short term impact health A2 B2 C2 D2 E2
damage
recoverable by the effect/injury
work site.
Beyond the site
boundary unlikely
Major
Considerable Major to last beyond 1
3. Major health A3 B3 C3 D3 E3
Impact damage month.
effect/injury
Recovery requires
external aid.
Beyond the site
Permanent
boundary unlikely
Total
National Severe to last beyond 12
4. Severe Disability A4 B4 C4 D4 E4
Impact damage months.
or single
Recovery requires
fatality
external aid.
Massive
uncontrolled
Multiple
release with
5. International Extensive serious
significant A5 B5 C5 D5 E5
Catastrophic Impact damage injuries or
impact extending
fatalities
well beyond the
site boundary.
Green Acceptable (When risk reduction / control measures have been implemented). Ensure
(Low) controls are maintained and manage for continuous improvement.
Tolerable (When risk reduction / control measures have been implemented). Where
Yellow
possible, the work activity / task should be redefined to take account of the hazards
(Medium)
involved or the risk should be reduced further prior to task commencement.
Intolerable (Work activity / task must not proceed). It should be redefined or further
Red
control measures put in place to reduce risk. The controls should be re-assessed for
(High)
adequacy prior to task commencement.
16
Hangzhou Ougan Technology Co., Ltd
17th Floor, Wanda Plaza, Hangxing Rd, Gongshu District, Hangzhou, 310015, P.R. China
Tel: 86-571-28223950 Fax: 86-571-28993137
concern.
Keep lifebuoy on site, keep distance
Fall into water C4 B2 Low
from water.
Note: We assume that the Site Main Contractor will complete site induction.
17
Hangzhou Ougan Technology Co., Ltd
17th Floor, Wanda Plaza, Hangxing Rd, Gongshu District, Hangzhou, 310015, P.R. China
Tel: 86-571-28223950 Fax: 86-571-28993137
Appendix A
Test Pile Layout
Appendix B
18
Hangzhou Ougan Technology Co., Ltd
17th Floor, Wanda Plaza, Hangxing Rd, Gongshu District, Hangzhou, 310015, P.R. China
Tel: 86-571-28223950 Fax: 86-571-28993137
Appendix C
Schematic Section of Test Pile & Reference Pile/Reference Beam Layout
19
Hangzhou Ougan Technology Co., Ltd
17th Floor, Wanda Plaza, Hangxing Rd, Gongshu District, Hangzhou, 310015, P.R. China
Tel: 86-571-28223950 Fax: 86-571-28993137
20
Hangzhou Ougan Technology Co., Ltd
17th Floor, Wanda Plaza, Hangxing Rd, Gongshu District, Hangzhou, 310015, P.R. China
Tel: 86-571-28223950 Fax: 86-571-28993137
Appendix D
Super Cell Calibration Certificate for Reference
21
Hangzhou Ougan Technology Co., Ltd
17th Floor, Wanda Plaza, Hangxing Rd, Gongshu District, Hangzhou, 310015, P.R. China
Tel: 86-571-28223950 Fax: 86-571-28993137
22
Hangzhou Ougan Technology Co., Ltd
17th Floor, Wanda Plaza, Hangxing Rd, Gongshu District, Hangzhou, 310015, P.R. China
Tel: 86-571-28223950 Fax: 86-571-28993137
Appendix E
Part Project References With Same Test Instrumentations
Single Pile Test Load Pile Dia.
Project Description Qty
(ton) (m)
Hong Kong-Zhuhai-Macao
11000/14000 2.0/2.2 2 Pcs each
Bridge
Macao Fai Chi Kei public
1920/820(tension pile) 1.0 1 pc each
housing project
Macao Hengqin Island
630/1300/510
University of Macau new 1.2/1.5/1.2 6pcs
(tension pile)
campus subsea tunnel
Social housing of Ilha Verde
1170 1.0 2pcs
Lote 3
Catholic High School At Bishan St22,
Singapore
650 0.8 2pcs
A 3-Storey Factory Extension at No.5
Tuas Lane, Singapore
1370 1.0 1pc
A 5-Storey Building at No.231A
Pandan Loop, Singapore
1450 0.9 1pc
Jiaxing - Shaoxing
20500 3.8 1pc
River-Crossing Bridge
Hangzhou Bay Bridge 7000 2.2 1pc
Beijing Ministry of Railways
4000 2.0 3pcs
Command and Control center
Highway-Railway Bridge over
4200 1.5 4pcs
Yellow River in Zhengzhou
Humen Bridge 20700/20000/11600 2.8/2.8/2.5 1pc each
Yangtze River Bridge in Anqing,
1800 1.0 3pcs
Anhui Province
Grand Bridge Over Yangtze
12000 1.8 1pc
River in Wuhu, Anhui Province
Hubei Province Danjiangkou
5700 1.8 1pc
Han River Grand Bridge
The Yellow River Bridge in
1200 1.0 2pcs
Shandong Juancheng
Shandong Yantai Fortune Center 2300 1.15 3pcs
Shandong Yantai Hengyue
1400/700 1.8 1pc each
Square
Liuzhou Diwang International
9800/9040 2.5/2.4 2/1 pcs
Fortune Center
Guangxi Nanning East Railway
4000 1.4 4pcs
Station
Guangxi Nanning Traffic police
900 1.1 57pcs
complex
Guizhou China Tobacco
1000 1.0 3pcs
Building
Jinlin Gymnasium in Sanmen, 500
1.0 2pcs
Guangdong province (tension pile)
23