WORK SCHEDULE (KAROORA HOJII)

Project: Special School Class Room


Client: Hurumu Woreda Education Office
Contractor: Abebaw, Mintamir, Bizunesh and Friends BC SME
ID Task Name Duration Start Finish Dec '23 Jan '24 Feb '24 Mar '24 Apr '
26 3 10 17 24 31 7 14 21 28 4 11 18 25 3 10 17 24
1 Project: Tomorrow's Foundation School Class Room 90 days Mon 12/4/23 Sat 3/16/24
2 Site Mobilization 3 days Mon 12/4/23 Wed 12/6/23
3 A. SUB STRUCTURE 35 days Thu 12/7/23 Tue 1/16/24
4 1. EXCAVATION AND EARTH WORK 31 days Thu 12/7/23 Thu 1/11/24
5 1.1 clear the site (top 200mm thick) 2 days Thu 12/7/23 Fri 12/8/23
6 1.2 excavate bulck (avg. depth of 150cm) 3 days Fri 12/8/23 Mon 12/11/23
7 1.3 excavate trench (depth up to 150cm) 4 days Tue 12/12/23 Fri 12/15/23
8 1.4 back fill around masonary foundation and under hardcore 2 days Tue 1/2/24 Wed 1/3/24
9 1.5 cart away excavated material 2 days Thu 1/4/24 Fri 1/5/24
10 1.6 250mm thick basaltic stone hard core 3 days Tue 1/9/24 Thu 1/11/24
11 2. MASONRY WORK 13 days Mon 12/18/23 Mon 1/1/24
12 2.1 50cm thick trachytic masonary BNGL 6 days Mon 12/18/23 Sat 12/23/23
13 2.2 50cm thick trachytic masonary ANGL 7 days Mon 12/25/23 Mon 1/1/24
14 3.CONCRETE WORK 27 days Sat 12/16/23 Tue 1/16/24
15 3.1 50mm thick C-5 lean concrete under Foundation Wall 2 days Sat 12/16/23 Mon 12/18/23
16 3.2 C-25 reinforced concrete filled into formwork 10 days Fri 1/5/24 Tue 1/16/24
17 a) In grade beam 3 days Fri 1/5/24 Mon 1/8/24
18 b) In 100mm thick ground floor slab 3 days Sat 1/13/24 Tue 1/16/24
19 3.3 Provide, cut & fix in position form work 4 days Thu 1/4/24 Mon 1/8/24
20 a) to grade beam 4 days Thu 1/4/24 Mon 1/8/24
21 3.4 Mild steel reinforcement 8 days Fri 1/5/24 Sat 1/13/24
22 a) dia 8mm deformed barfor ground slab 2 days Fri 1/12/24 Sat 1/13/24
23 b) dia 12mm deformed bar 4 days Fri 1/5/24 Tue 1/9/24
24 B. SUPER STRUCTURE 62 days Fri 1/5/24 Sat 3/16/24
25 1.CONCRETE WORKS 22 days Fri 1/5/24 Tue 1/30/24
26 1.1 C-25 reinforced concrete filled into formwork 11 days Thu 1/18/24 Tue 1/30/24
27 a. to elevation column 4 days Thu 1/18/24 Mon 1/22/24
28 b. to top tie beam 5 days Thu 1/25/24 Tue 1/30/24

Task Inactive Milestone Finish-only


Split Inactive Summary External Tasks
Milestone Manual Task External Milestone
Project: special school.mpp
Date: Sun 11/26/23 Summary Duration-only Critical
Project Summary Manual Summary Rollup Critical Split
External Tasks Manual Summary Progress
External Milestone Start-only Deadline

NB: 90days for Project Completion are Only Working Days


Hubachiisa: Goyyootiin 90 Hojii itti Xumuruuf Ibsaman, Guyyoolee Hojii qofa
Page 1
WORK SCHEDULE (KAROORA HOJII)
Project: Special School Class Room
Client: Hurumu Woreda Education Office
Contractor: Abebaw, Mintamir, Bizunesh and Friends BC SME
ID Task Name Duration Start Finish Dec '23 Jan '24 Feb '24 Mar '24 Apr '
26 3 10 17 24 31 7 14 21 28 4 11 18 25 3 10 17 24
29 1.2 Provide, cut & fix in position form work 10 days Wed 1/17/24 Sat 1/27/24
30 a. to elevation column 4 days Wed 1/17/24 Sat 1/20/24
31 b. to top tie beam 5 days Tue 1/23/24 Sat 1/27/24
32 1.3 Mild steel reinforcement 21 days Fri 1/5/24 Mon 1/29/24
33 1.31 in elivation column 4 days Fri 1/5/24 Tue 1/9/24
34 a) dia 6mm plain bar for stirrup 4 days Fri 1/5/24 Tue 1/9/24
35 b) dia 12mm deformed bar 4 days Fri 1/5/24 Tue 1/9/24
36 1.32 in top tie beam 4 days Thu 1/25/24 Mon 1/29/24
37 a) dia 6mm plain bar for stirrup 4 days Thu 1/25/24 Mon 1/29/24
38 b) dia 12mm deformed bar 4 days Thu 1/25/24 Mon 1/29/24
39 2. BLOCK WORK 7 days Tue 2/13/24 Tue 2/20/24
40 2.1 200mm thick Class B HCB wall 7 days Tue 2/13/24 Tue 2/20/24
41 2.2 Ditto but 150mm thick 4 days Tue 2/13/24 Fri 2/16/24
42 3.ROOFING 34 days Wed 2/7/24 Sat 3/16/24
43 3.1 G-30 Roofing cover 5 days Wed 2/7/24 Mon 2/12/24
44 3.2 dia 110mm PVC down pipe 1 day Sat 3/16/24 Sat 3/16/24
45 3.3 G-28 ribbed sheet ceiling under eave 2 days Sat 3/2/24 Mon 3/4/24
46 3.4 G-28 flat iron Metal gutter 1 day Tue 3/5/24 Tue 3/5/24
47 3.5 Flush type internal Wood Door; D2 size:- 90cmX280cm 1 day Thu 3/14/24 Thu 3/14/24
48 4.CARPENTORY AND JOINARY 28 days Thu 2/1/24 Mon 3/4/24
49 4.1 10-12dia wooden lower and upper 2 days Thu 2/1/24 Fri 2/2/24
50 4.2 8-10cm dia wooden vertical and diagonal chord member 2 days Fri 2/2/24 Sat 2/3/24
51 4.3 5x7cm zigba wood purlins 2 days Mon 2/5/24 Tue 2/6/24
52 4.4 10mm thick chipwood ceiling 4 days Thu 2/29/24 Mon 3/4/24
53 4.5 Fascia board 250x25mm 2 days Thu 2/29/24 Fri 3/1/24
54 5.METAL WORK 20 days Thu 2/1/24 Fri 2/23/24
55 5.1 door and windows fabrication (welding) 12 days Thu 2/1/24 Wed 2/14/24
56 5.2 installing and finishing work for doors and windows 3 days Wed 2/21/24 Fri 2/23/24

Task Inactive Milestone Finish-only


Split Inactive Summary External Tasks
Milestone Manual Task External Milestone
Project: special school.mpp
Date: Sun 11/26/23 Summary Duration-only Critical
Project Summary Manual Summary Rollup Critical Split
External Tasks Manual Summary Progress
External Milestone Start-only Deadline

NB: 90days for Project Completion are Only Working Days


Hubachiisa: Goyyootiin 90 Hojii itti Xumuruuf Ibsaman, Guyyoolee Hojii qofa
Page 2
WORK SCHEDULE (KAROORA HOJII)
Project: Special School Class Room
Client: Hurumu Woreda Education Office
Contractor: Abebaw, Mintamir, Bizunesh and Friends BC SME
ID Task Name Duration Start Finish Dec '23 Jan '24 Feb '24 Mar '24 Apr '
26 3 10 17 24 31 7 14 21 28 4 11 18 25 3 10 17 24
57 6. FINISHING 19 days Wed 2/21/24 Wed 3/13/24
58 6.1 30mm thick cement sand screed 3 days Tue 3/5/24 Thu 3/7/24
59 6.2 Three coats of plastering to internal walls, beam and column 7 days Wed 2/21/24 Wed 2/28/24
60 6.3 Two coats of plastering to external wall surface 5 days Wed 2/21/24 Mon 2/26/24
61 6.4 3x25cm terrazo window sill 1 day Fri 2/23/24 Fri 2/23/24
62 6.5 100cm wide and 15cm thick C-20 concrete around building 2 days Fri 3/8/24 Sat 3/9/24
63 6.6 C-25 concrete pipe of rectangular ditch 3 days Mon 3/11/24 Wed 3/13/24
64 7. GLAZING 1 day Sat 3/16/24 Sat 3/16/24
65 7.1 4mm thick clear glass 1 day Sat 3/16/24 Sat 3/16/24
66 7.2 6mm thick figured glass 1 day Sat 3/16/24 Sat 3/16/24
67 8. PAINTING 6 days Sat 3/9/24 Fri 3/15/24
68 8.1 Three coats of plastic emultion paint to internal plastered 4 days Tue 3/12/24 Fri 3/15/24
surface, external beam & columns
69 8.2 Ditto but to Chipwood ceiling 2 days Sat 3/9/24 Mon 3/11/24
70 8.3 Three coats of synthetic enamel paint to ceiling under eave 1 day Sat 3/9/24 Sat 3/9/24
71 9. EECTRICAL INSTALLATION 1 day Sat 3/16/24 Sat 3/16/24
72 9.1 Flush mounted SDB 1 day Sat 3/16/24 Sat 3/16/24
73 9.2 Surface mounted light point fed through PVC 1 day Sat 3/16/24 Sat 3/16/24
74 9.3 Fluish mounted Two way 10Amp switch 1 day Sat 3/16/24 Sat 3/16/24
75 9.4 Surface mounted Socket outlet 1 day Sat 3/16/24 Sat 3/16/24
76 9.5 Telephone point fed through PVC 1 day Sat 3/16/24 Sat 3/16/24
77 9.6 Phillips Florecent 1 day Sat 3/16/24 Sat 3/16/24
78 9.7 Earthing System 1 day Sat 3/16/24 Sat 3/16/24

Task Inactive Milestone Finish-only


Split Inactive Summary External Tasks
Milestone Manual Task External Milestone
Project: special school.mpp
Date: Sun 11/26/23 Summary Duration-only Critical
Project Summary Manual Summary Rollup Critical Split
External Tasks Manual Summary Progress
External Milestone Start-only Deadline

NB: 90days for Project Completion are Only Working Days


Hubachiisa: Goyyootiin 90 Hojii itti Xumuruuf Ibsaman, Guyyoolee Hojii qofa