Dear Sir,
As discussed we are submitting our best possible rate for the following Equipments,
6 3500/- 3500/-
Night charges for three persons
7 Transportation charges to carry the ductline and 1500/- 1500.00
hood to site
TOTAL 102200.00
ADVANCE ENGINEERING
Proprietor:- Ria Sengupta
Chandigarh, Mathpara, Ganganagar, Kolkata – 700132
E-mail: suvankar.aew@gmail.com,
Mobile no: 8017045561, 8017834116
1. Payment: 75% advance along with PO and balance 25% Before delivery .
2. DELIVERY : Completion within 2-3 days for Ductline work, and 15 days for Chiller after receiving your
confirmed purchase order along with advance payment, however in case of unavoidable circumstances like
natural calamities, war, strikes etc. We will not be held responsible for any delay in delivery.
3. Transportation : At an actual
4. 18% GST will be charged extra against bill.
4. Bank Details: Name – RIA SENGUPTA
AC NO: 50220024479682, IFSC: BDBL0001129
BANDHAN BANK