Download as pdf or txt
Download as pdf or txt
You are on page 1of 9

See discussions, stats, and author profiles for this publication at: https://www.researchgate.

net/publication/336279625

Structural Robustness of a Single Span Extra Dosed Bridge over Cable Stayed
Bridge

Preprint · October 2019


DOI: 10.6180/jase.201909_22(3).0003

CITATIONS READS

0 2,323

3 authors, including:

Mohan Ganesh Santhi A.S.


VIT University VIT University
80 PUBLICATIONS 557 CITATIONS 68 PUBLICATIONS 490 CITATIONS

SEE PROFILE SEE PROFILE

All content following this page was uploaded by Mohan Ganesh on 01 May 2020.

The user has requested enhancement of the downloaded file.


Journal of Applied Science and Engineering, Vol. 22, No. 3, pp. 413-420 (2019) DOI: 10.6180/jase.201909_22(3).0003

Structural Robustness of a Single Span Extra Dosed


Bridge over Cable Stayed Bridge
M. Vinayagamoorthy, G. Mohan Ganesh* and A. S. Santhi
School of Civil and Chemical Engineering, VIT, Vellore, India

Abstract
This paper presents the structural behavior and robustness of extra dosed bridge and compares
with cable stayed bridge using finite element analysis software-Midas civil. The various influencing
parameters of the deck such as displacement, axial force, shear force, bending moment, bending stress
and stay cable forces of cable stayed bridge and extra dosed bridge were compared.

Key Words: Extra Dosed Bridge, Cable Stayed Bridge, Finite Element Analysis, Bending Stiffness,
Pier Stiffness

1. Introduction minimise the wind dynamic effects such as the less wind
vibration in the cable and reduced exposed area in pylon.
Term ‘extra dosed’ was coined by Jacques Mathivat
(1988) to appropriately describe an innovative cabling 2. Investigation Implication
concept, developed for the Arret-Darre Viaduct in which
external tendons were placed above the deck instead of The objective of this study is to provide insight into
within the cross-section as would be the case in a girder how different geometric parameters like tower height and
bridge.
Early post-tensioned concrete bridges placed the pre-
(A)
stressing tendons within the concrete cross section, that
is, within the webs of the box girder or the top or bottom
flanges. The past fifty years has seen continued develop-
ment in pre-stressed concrete bridges [1]. One of the ma-
jor themes in recent years has been towards lightening of
the structure by the use of external pre-stress, where the
pre-stressing tendons are placed externally with the gir-
der. An extra dosed bridge (Figure 1A and 1B) is a bridge
type that combines a pre-stressed girder bridge with ca- (B)
ble-stayed bridge [2]. The major advantages of using ex-
tradosed bridge are the speed of construction, reduced
pylon height, flexible deck, lesser material usage and
sleek dimensions to look better; the cable anchorage sys-
tem is simpler and erecting the stay cable is easy because
of its less length compared with cable stayed bridge (Fig-
ure 2A and 2B). The reduced pylon height and cables

Figure 1. (A) Components of extra dosed bridge. (B) Deh


*Corresponding author. E-mail: gmohanganesh@vit.ac.in Cho extra dosed bridge.
414 M. Vinayagamoorthy et al.

(Force distribution is high due to high stiffness on the


(A) girder.
(c) Location of cable: High capacity of deck slab in gir-
der can be utilised in negative bending moment re-
gions over the piers, leading to an efficient structure
than conventional box girder bridge.
The height of pylon for extradosed bridge is L/5
(Figure 2A) and the cable stayed bridge is L/9 (Figure
2B) in which the extradosed bridge provides the geomet-
rical benefits like maximum force distribution in the ca-
ble due to less pilon height that leads to the maximum
(B) load carrying capacity of the deck. The investigation of
optimum height of pylon was considered from L/7 to L/
15; the locations of the node, reactions forces, out of all
the parameter compared with these ratios, the optimum
ratio is based on the force distribution with respect to the
cable type found as L/9. Fan type cable arrangement was
selected which gives the combination of radial and harp
type arrangements (Figure 2A) and compared their re-
sults. Furthermore, it can provide the reference for the ef-
fective height of the tower, economic and reasonable st-
Figure 2. (A) Extra dosed Bridge. (B) Cable stayed bridge. ructure form design in the bridge of structural behavior
assessment. It also can evaluate the safety of girder and
pier dimensions influence the structural behavior, and tower through reliability theory [3]. Bridge with cable
possibility of an extra dosed bridge. An extra dosed bri- stayed bridge (Figure 2B). It can help us to understand
dge with stiff girder and cable stayed bridge with stiff structural properties of the structure to estimate behavior
tower were designed for a single span bridge with the evaluation when the structure parameters are changed.
central span of 150.5 m which is the cable-stayed bridge
over Tapi River which connects Pal and Athwalines in 3. Geometry and Material Properties
Surat, Gujarat, India. The structural behavior of an extra
dosed bridge was compared with cable stayed bridge The material property for the Deck, Pylon and cable
providing stiffness either in the girder or in the piers of properties considered are taken as follows: modulus of
an extra dosed bridge or both, found to be influencing in elasticity, Poisson’s ratio, thermal coefficient; weight
the competitive designs for the following parameters: density are tabulated below (Table 1). The geometry us-
(a) Lever arm increases: Tendon placed above deck. (Le- ing one dimensional element (Line Elements) defining
ver arm was calculated between the deck and cable). the types of elements, element material properties, sec-
(b) Distribution of LL: Extra dosed bridge cables make tion properties and element stiffness data were given as
stiffer girder to distribute the LL to multiple cables. the input parameter connecting node numbers were then

Table 1. Material properties


Property Deck Pylon Cable
2
Modulus of elasticity (Ton/m ) 3.5350e+6 3.5350e+6 1.95e+7
Poisson’s ration 0.15 0.15 0.15
Thermal co-efficient (1/C) 1.13e-005 1.13e-005 1.17e-005
Weight density (Ton/m3) 2.5 2.5 7.85
Structural Robustness of a Single Span Extra Dosed Bridge over Cable Stayed Bridge 415

specified to define the locations, shapes, and sizes of the cable stayed bridge due to pylon height and the vertical
elements. reaction (FZ) is reduced accordingly and is compared
To compare the chosen girder cross-section (Figure with cable stayed bridge. The results are furnished in Ta-
3), it is desirable to calculate the bending moment capac- ble 2A, Table 2B. The prestressing (the stay cable acting
ity of that section. For this purpose, the bending moment as an external pre-stressing due to its low angle position
of the extra dosed cross-section was compared with that with the deck.) generate the additional compression to
of a girder bridge with a box girder cross-section of simi- the deck.
lar depth. Although most of the superimposed dead load
moment in the extra dosed girder will be balanced by in- 5. Deck
ternal pre-stressing, these bending moments could be ac-
commodated in the initial cross section [4]. Then it was 5.1 Displacement
compared with stay cable with the assumption that the Since the short towers act as a cantilever which is ef-
stay cables are acting as an external pre-stressing [5]. fectively pre-stressed by the dead load of the girder act-
The considered cross sections for the tower are given in ing through the cables, it requires relatively little rein-
Figure 4.

4. Reactions at Pylon (Force)

The results are compared for the Load combination


named as LCB (Load combination) was the combination
of self-weight of the bridge and superimposed load of
117.7 kN/m which was applied as uniformly distributed
load. With the expectations that the total reactions are
equal to the total weight of the structure, the reactions for
the extra dosed bridge are compared with cable stayed
bride for the same span 150.5 m mid span, from the free
body diagram of the entire beam, using balance equa-
tions SF = 0, MA = 0.
As per the results which are extracted from the anal-
ysis, it is observed that due to the weight of the structure
of the geometry of the extra dosed bridge is less than the Figure 4. Geometry and cross section of pylon.

Figure 3. Geometry and cross section of box girder.


416 M. Vinayagamoorthy et al.

Table 2A. Horizontal reaction at the supports Table 2B. Horizontal reaction at the support
Extra dosed bridge Fx Cable stayed bridge Fx Extra dosed bridge Fz Cable stayed bridge Fz
Node Node
(tonf) (tonf) (tonf) (tonf)
7 2294.161 2240.872 7 732.8768 11243.91
13 2294.161 2240.872 13 732.8768 11243.91
117 7.95637 4.03722 117 12984.42 125019.3
146 2290.18 2238.85 146 748.6628 11511.8
147 2290.18 2238.85 147 748.6628 11511.8

forcement to resist bending due to vehicle load. So the ble arrangement is used in both the bridges, the reduced
displacements are controlled and reduced better than the cable inclination in an extra dosed bridge leads to an in-
cable stayed bridge. The advantages of stiffer and lower crease in the axial load on the deck and a decrease in the
towers for the extra dosed bridges (i.e.) the full range of vertical component of force at the cable anchorages (Ta-
effective depth of the cross-section is used for the analy- ble 3).
sis. Neither a flexural stiff girder nor backstays are re- The boundary between extra dosed bridges and ca-
quired to provide adequate system stiffness to control the ble stayed bridges is suggested to occur at b = 0.30. (b is
deformations due to externally applied load. With short a constant which explain the force distribution ratio).
towers, larger stay cables are required, but the towers are
cable force
more economical than the tall towers which are normally b=
vertical component of cable force
found in cable-stayed bridges [6].
It is observed from the behaviour analysis of both ca- From the results of axial forces in the deck (Figure
ble stayed bridge, and extra dosed bridge, the resultant 6), it can be seen clearly that performance of low angle
force from the cables are converted to horizontal force cables produced more compressive force to the deck as
which is converted as an axial force to the girder conse- the action of external prestressing. Furthermore, the st-
quently; the stiffness of the girder increases, so the defor- ructural stability of the extra dosed bridge is ensured due
mations are lesser compared to cable stayed bridge (Fig- to the high compression force which is acting on both the
ure 5). In extra dosed bridges, the fan cable configuration left and right side of the deck from the pylon position.
is used to load the tower in axial compression only, and
the backstay cables steady the tower and control girder 5.3 Shear Force
deflections due to live load. With this system, the girder A cable arrangement is selected, and sized accord-
span to depth ratios of upto 500 is possible [7]. With stiff ing to maximum load for the allowable cable stress, and
towers, the girder can still be made very slender, with the girder is designed to resist the bending moment be-
span to depth ratios upto around 200, but backstay cables tween cables under dead load, and compatibility mo-
are not required. A harp cable configuration favors stiff ments under live load, caused by the distribution of
towers since live load at the quarter points of the main
span will cause significant bending in towers, regardless
of tower stiffness. The vertical displacement was mar-
ginally high in the cable stayed bridge across the span with
maximum difference of 40% with extra dosed bridge due
to cable anchorage angle with pylon [8].

5.2 Axial Force


The advantage of low angle cables in the extra dosed
bridge with the cable anchorages lead to lesser axis with
the deck, so the axial force is higher. As the fan type, ca- Figure 5. Vertical displacement (Fz) in m.
Structural Robustness of a Single Span Extra Dosed Bridge over Cable Stayed Bridge 417

Table 3. Calculation of force distribution ratio


Extra dosed bridge Cable stayed bridge
Max axial force (SW) = 2166 ton(deck) Max axial force (SW) = 3203 ton (deck)
Deflection = 73 mm @ mid span Deflection = 83mm @ mid span
Reaction = 15589.29 ton Reaction = 14147 ton
Cable force = 4394 ton Cable force = 8131.6 ton
b = 0.282 b = 0.570
Force taken by the cable = 28% Force taken by the cable = 57%

Figure 6. Axial force (Fx) in Ton.

axial loads to several nearby cables. Finally, the cross 5.4 Bending Moment
section was checked for buckling at the pier under com- A detailed study was conducted by varying the tower
bined bending and axial compression in the deck. This height, depth of deck, and length of the side span on the
process resulted in a bridge that has a two lane bridge of total extra dosed cable area, the force distribution in the
150 m main span with the cable mass required to sup- cables, and the bending moment in the deck. The mo-
port half of the span for both in negative and positive ment of inertia of the girder of extra dosed bridges at
bending for the behavior of box girder section of given mid-span varies considerably, especially for bridges with
depth (Figure 7). a span at 150 m. Its structural behavior appears to be

Figure 7. Shear force (Fz) in Ton.


418 M. Vinayagamoorthy et al.

more like a cable-stayed bridge, despite having a cable stress the deck, not only to provide vertical support as in
inclination of an extra dosed bridge [9]. It can also be ob- a cable-stayed bridge. But also characterized by a low
served that there is a distinct difference between the mo- live load stress range in the stay cables. Analysis results
ment of inertia of cable-stayed bridges and box-girders such as element forces and stresses and the majority of
in which box girder have slabs stiffened by edge beams. data entries associated with elements are expressed in
In this cable-stayed bridges and extra dosed bridge all the local coordinate system (Figure 9). The following re-
box girders are centrally suspended, while all slab or presents a general equation applied to calculate the bend-
stiffened slab bridges are laterally supported [10]. The ing stress of a section [15].
flexible deck results in large deflections throughout each
M Y - M Z ( I yz / I zz ) M Z - M y (I yz / I yy )
stage of construction, and correspondingly large varia- fb = 2
×z+ 2
×y
tions in bending moment (Figure 8) [11]. Under perma- I yy - (I yz / I zz ) I yy - ( I yz / I yy )
nent loads, the moment distribution across the deck re- where, Iyy: area moment of inertia about the ECS y-axis,
sembles that of a continuous beam on simple supports, Izz: area moment of inertia about the ECS z-axis, Iyz:
while under live load a point load is distributed into near- area product moment of inertia, Y: distance from the
by cables [12]. The vertical deflection of the girder at neutral axis to the location of bending stress calculation
mid span is 863 mm under a combination of self-weight in the ECS y-axis direction, Z: distance from the neutral
and uniformly distributed load of 117.7 kN/m2. The 40% axis to the location of bending stress calculation in the
of the total deflection occurs due to the rotation of the ECS z-axis direction, My: bending moment about the
piers, while 60% results from the elastic extension of the ECS y-axis, Mz: bending moment about the ECS z-axis.
cables which resulted in an upward displacement of 60
mm in the adjacent spans [13]. From the forces, it is ob- 6. Stay Cable Forces
served that in the extra dosed bridge the horizontal force
component is higher and the vertical force component is The stay cables can be anchored near the webs, and
lesser at the anchorage point, and vice versa for cable the vertical component of the stay cable force (which is
stayed bridge [14]. From the moments, it is seen that in small in comparison to a cable-stayed bridge) is trans-
the extra dosed bridge, the load is carried through flex- ferred directly to the girders without the need for a trans-
ural behavior of the deck and for cable stayed bridge by verse diaphragm at the anchorage location [16]. As with
the cables and the tower. external prestressing, extra dosed bridges can use the nor-
mal prestressing anchorages instead of the high-stress
5.5 Bending Stresses range type used for cable-stayed bridges [17].
Thus, the function of the extra dosed cables is to pre- The effect of cable inclination on the force compo-

Figure 8. Bending moment (My) in Ton-m.


Structural Robustness of a Single Span Extra Dosed Bridge over Cable Stayed Bridge 419

Figure 9. Bending stresses in Ton/m2 along span.

nents in a stay cable is examined. For a constant cable Table 4. Cable forces
force, the vertical component of force is increased al- Element Cable stayed bridge Extra dosed bridge
most linearly with an increase in inclination from 0° to No. (Ton) (Ton)
30° [18]. But the horizontal force is decreased only by 9 -490.5 -98.6
13% (Table 4). 11 4615 -22.7
The extradosed bridge has 17% of vertical compo- 13 10555 82.9
nent and 83% of horizontal component of the stay cable 15 15775 211.1
17 18995 360.4
forces. This leads to the high shear force so the deflec-
19 18955 550.6
tion has been controlled. Because of these reasons the 22 13590 972.4
bending capacity of the deck is high. Also the cable force 39 13570 974.7
is 35% less in extradosed bridge so the material used for 41 19040 554.0
the cables is less and tension force reduced which lead 43 19135 363.3
the less dimensions of pylon and the foundations accord- 45 15925 212.9
47 10655 83.0
ingly. 49 4592 -24.5
51 -730.9 -102.8
7. Conclusion
dge is achieved with the following conclusions:
The extra dosed bridge has been analyzed with low (1) In the extra dosed bridge, the deck is flexible resulted
towers which attained the flexible girders and stiff pylon in high bending moments and shear forces (330% of
and it depends on the axial force couple between stay ca- the bending moment and 500% of the shear force of
bles and girder to carry the live load. Further the behav- cable stayed bridge). But this additional deck forces
ior was compared with cable stayed bridge. The FEM are minimized on the pylon due to balanced cantile-
model was developed for this study. The cable bridges ver action of the deck.
with high piers (cable-stayed bridge) and short tower st- (2) The vertical displacement was 40% lesser in the ex-
ructure (extra dosed bridge) stress are comparable based tra dosed bridge due to cable anchorage angle with
on the present parametric study. So structural robustness pylon.
of a single span extra dosed bridge over cable stayed bri- (3) Vertical force taken by the cable is 28% for extra
420 M. Vinayagamoorthy et al.

dosed bridge but this was high in the cable stayed [9] Ouyang, Y. J. (2006) Low tower cable-stayed bridge
bridge (57%). structure parameter analysis, Steel Structure, Engine-
(4) Stay cable which is placed above the deck is acting as ering Research and Applications 24(4), 38-42.
the external prestress due to its lower angle, so the [10] Konstantinos, and K. Mermigas (2008) Behaviour and
horizontal force is considerably high in the extra Design of Extra Dosed Bridge, University of Toronto,
dosed bridge (537 Ton) than cable stayed bridge Theoretical and Experimental Verification 01, 102-
(510.67 Ton) which is 20%. 135.
[11] Cheng, C. C., K. T. Hsu, and C. P. Yu (2010) Evalua-
References tion of the Dynamic Characteristics of an Extradosed
Bridge Using Microwave Interferometer, Chaoyang
[1] Song, J., J. Zhou, J. Yang, and Z. Chen (2013) Based University of Technology, Taichung, Taiwan, 04(22),
on the theory of reliability high piers short towers ca- 1012-1024.
ble-stayed bridge characteristic parameter analysis, [12] Straupea, V., and A. Paeglitisb (2013) Analysis of geo-
Journal of Modern Applied Science 7, 41-46. doi: 10. metrical and mechanical properties of cable-stayed bri-
5539/mas.v7n4p41 dge, 11th International Conference on Modern Build-
[2] Steven, L. (2010) On the Development of the Extra ing Materials, Structures and Techniques, 57, 1086–
dosed Bridge Concept, PhD Dissertation, University 1093. doi: 10.1016/j.proeng.2013.04.137
of South Florida, 25(3), 35-114. [13] Chen, D W., L. C. Fan, and Q. Zhang (1996) Study on
[3] Matthias, S. (2012) Design and construction of the parameters and general arrangement of single tower
Deh Cho Bridge challenges, innovation, opportunities, cable-stayed bridges, China Civil Engineering Jour-
Conference of the Transportation Association of Can- nal, 6, 34-40.
ada. [14] Chen, H. J., K. Wang, and C. Y. Li (2002) Preliminary
[4] Jan, B., O. Jaroslav, and V. Josef (2013) Extradosed analysis of partial cable-stayed bridge, Journal of Bri-
bridge, theoretical and experimental verification, Pro- dge Construction 1, 44-47.
cedia Engineering 65, 327-334. doi: 10.1016/j.proeng. [15] Liu, F. K., P. Z. Lin, Q. Chen, and S. Z. Liu (2004) In-
2013.09.050 vestigation of characteristic parameters of cable-stayed
[5] José, B., C. Gustavo, and M. Esperanza (2010) Struc- bridge with low towers, Journal of Engineering Me-
tural behavior and design criteria of extra dosed bri- chanics 21(2), 199-203.
dges general insight and state of the art, Industrial Uni- [16] Takami, K., and S. Hamada (2005) Behavior of extra
versity of Santander, COLOMBIA, Journal of Con- dosed bridge with composite girder, ASCE Journal of
struction Engineering 25(3), 383-398. Bridge Engineering 11, 65-74.
[6] Lin, P. Z., H. H. Sun, and F. K. Liu (2005) West Lake [17] Otsuka, H., T. Wakasa, J. Ogata, W. Yabuki, and D.
of low-pylon cable-stayed bridge research and charac- Takemura (2002) Comparison of structural character-
teristic parameters, Journal of Highway and Transpor- istics for different types of cable-supported prestressed
tation 22(10), 56-59. concrete bridges, Structural Concrete 3(1), 3-21. doi:
[7] Sardesai, M. V., and A. K. Desai (2013) Investigation 10.1680/stco.2002.3.1.3
into cable-structure interaction for extra dosed bridge, [18] Au, F. T. K., Y. S. Cheng, Y. K. Cheung, and D. Y.
International Journal of Engineering Research and Zheng (2002) On determination of natural frequency
Applications 3, 1424-1429. and mode shapes of cable stayed bridges, Applied Ma-
[8] Zheng, Y. F., Q. Huang, and L. Z. Zhang (2003) Par- thematical Modeling 25(12), 1099-1115. doi: 10.1016/
tial Cable-stayed Bridge Structural Parameter Analy- S0307-904X(01)00035-X
sis, Technology of Highway and Transport, Published
by Canadian Center of Science and Education, 23(6), Manuscript Received: Aug. 14, 2018
60-64. Accepted: May 7, 2019

View publication stats

You might also like