Timeline Project Management

You might also like

Download as pdf or txt
Download as pdf or txt
You are on page 1of 9

ID Task Name Duration Start Finish % Complete 29 May '22 05 Jun '22 12 Jun '22 19 Jun '22 26 Jun

'22 05 Jun '22 12 Jun '22 19 Jun '22 26 Jun '22


1 Perencanaan 3 days Sun 05/06/22 Tue 07/06/22 100%
2 Pembagian Tugas 3 days Sun 05/06/22 Tue 07/06/22 100%
& Tanggung Jawab
3 Analisa & Design 13 days Wed 08/06/22 Fri 24/06/22 100%
Sistem
4 Analisa proses 3 days Wed 08/06/22 Fri 10/06/22 100%
bisnis Batavia Cafe
(Wawancara)
5 Membuat 3 days Sat 11/06/22 Tue 14/06/22 100%
Flowchart proses
bisnis
6 Membuat Entity 5 days Wed 15/06/22 Tue 21/06/22 100%
Relationship
Diagram (ERD)
7 Membuat kamus 3 days Wed 22/06/22 Fri 24/06/22 100%
data &
Requirement
System
8 Desain Aplikasi 21 days Sat 25/06/22 Fri 22/07/22 100%
9 Membuat desain 7 days Sat 25/06/22 Mon 04/07/22 100%
Landing Page
Sistem
10 Membuat desain 7 days Tue 05/07/22 Wed 13/07/22 100%
Halaman Order
11 Membuat desain 7 days Thu 14/07/22 Fri 22/07/22 100%
Halaman
Manajemen

Task Inactive Summary External Tasks

Split Manual Task External Milestone

Milestone Duration-only Deadline


Project: Timeline PPSI
Summary Manual Summary Rollup Progress
Date: Tue 27/12/22
Project Summary Manual Summary Manual Progress

Inactive Task Start-only

Inactive Milestone Finish-only

Page 1
ID Task Name Duration Start Finish % Complete 29 May '22 05 Jun '22 12 Jun '22 19 Jun '22 26 Jun '22
12 Programming 30 days Sat 23/07/22 Thu 01/09/22 100%
13 Membuat Front 15 days Sat 23/07/22 Thu 11/08/22 100%
End Sistem
14 Membuat Back 15 days Fri 12/08/22 Thu 01/09/22 100%
End Sistem
15 Testing Sistem 20 days Fri 02/09/22 Thu 29/09/22 100%
16 Membuat Test 5 days Fri 02/09/22 Thu 08/09/22 100%
Case
17 Melakukan 6 days Fri 09/09/22 Fri 16/09/22 100%
Usability Testing
18 Melakukan 5 days Mon 19/09/22 Fri 23/09/22 100%
Testing Integrasi
Sistem
19 Memberikan 5 days Sat 24/09/22 Thu 29/09/22 100%
catatan list
outstanding issue
20 Dokumentasi 33 days Fri 30/09/22 Tue 15/11/22 95%
21 Membuat 5 days Fri 30/09/22 Thu 06/10/22 100%
presentasi terkait
sistem
22 Membuat 21 days Fri 07/10/22 Fri 04/11/22 100%
dokumen SRS
23 Membuat 8 days Sat 05/11/22 Tue 15/11/22 80%
dokumen Manual
Book
24 Training & Presentasi9 days Wed 16/11/22 Mon 28/11/22 30%

Task Inactive Summary External Tasks

Split Manual Task External Milestone

Milestone Duration-only Deadline


Project: Timeline PPSI
Summary Manual Summary Rollup Progress
Date: Tue 27/12/22
Project Summary Manual Summary Manual Progress

Inactive Task Start-only

Inactive Milestone Finish-only

Page 2
ID Task Name Duration Start Finish % Complete 29 May '22 05 Jun '22 12 Jun '22 19 Jun '22 26 Jun '22
25 Melakukan 3 days Wed 16/11/22 Fri 18/11/22 0%
presentasi sistem
26 Melakukan 4 days Sat 19/11/22 Wed 23/11/22 0%
pemaparan sistem

27 Membuat video 3 days Thu 24/11/22 Mon 28/11/22 100%


tutorial &
presentasi sistem

Task Inactive Summary External Tasks

Split Manual Task External Milestone

Milestone Duration-only Deadline


Project: Timeline PPSI
Summary Manual Summary Rollup Progress
Date: Tue 27/12/22
Project Summary Manual Summary Manual Progress

Inactive Task Start-only

Inactive Milestone Finish-only

Page 3
26 Jun '22 03 Jul '22 10 Jul '22 17 Jul '22 24 Jul '22 31 Jul '22 07 Aug '22 14 Aug '22 21 Aug '22 28 Aug '22 04 Sep '22 11 Sep '22

Task Inactive Summary External Tasks

Split Manual Task External Milestone

Milestone Duration-only Deadline


Project: Timeline PPSI
Summary Manual Summary Rollup Progress
Date: Tue 27/12/22
Project Summary Manual Summary Manual Progress

Inactive Task Start-only

Inactive Milestone Finish-only

Page 4
26 Jun '22 03 Jul '22 10 Jul '22 17 Jul '22 24 Jul '22 31 Jul '22 07 Aug '22 14 Aug '22 21 Aug '22 28 Aug '22 04 Sep '22 11 Sep '22

Task Inactive Summary External Tasks

Split Manual Task External Milestone

Milestone Duration-only Deadline


Project: Timeline PPSI
Summary Manual Summary Rollup Progress
Date: Tue 27/12/22
Project Summary Manual Summary Manual Progress

Inactive Task Start-only

Inactive Milestone Finish-only

Page 5
26 Jun '22 03 Jul '22 10 Jul '22 17 Jul '22 24 Jul '22 31 Jul '22 07 Aug '22 14 Aug '22 21 Aug '22 28 Aug '22 04 Sep '22 11 Sep '22

Task Inactive Summary External Tasks

Split Manual Task External Milestone

Milestone Duration-only Deadline


Project: Timeline PPSI
Summary Manual Summary Rollup Progress
Date: Tue 27/12/22
Project Summary Manual Summary Manual Progress

Inactive Task Start-only

Inactive Milestone Finish-only

Page 6
18 Sep '22 25 Sep '22 02 Oct '22 09 Oct '22 16 Oct '22 23 Oct '22 30 Oct '22 06 Nov '22 13 Nov '22 20 Nov '22 27 Nov '22 04 Dec '22

Task Inactive Summary External Tasks

Split Manual Task External Milestone

Milestone Duration-only Deadline


Project: Timeline PPSI
Summary Manual Summary Rollup Progress
Date: Tue 27/12/22
Project Summary Manual Summary Manual Progress

Inactive Task Start-only

Inactive Milestone Finish-only

Page 7
18 Sep '22 25 Sep '22 02 Oct '22 09 Oct '22 16 Oct '22 23 Oct '22 30 Oct '22 06 Nov '22 13 Nov '22 20 Nov '22 27 Nov '22 04 Dec '22

Task Inactive Summary External Tasks

Split Manual Task External Milestone

Milestone Duration-only Deadline


Project: Timeline PPSI
Summary Manual Summary Rollup Progress
Date: Tue 27/12/22
Project Summary Manual Summary Manual Progress

Inactive Task Start-only

Inactive Milestone Finish-only

Page 8
18 Sep '22 25 Sep '22 02 Oct '22 09 Oct '22 16 Oct '22 23 Oct '22 30 Oct '22 06 Nov '22 13 Nov '22 20 Nov '22 27 Nov '22 04 Dec '22

Task Inactive Summary External Tasks

Split Manual Task External Milestone

Milestone Duration-only Deadline


Project: Timeline PPSI
Summary Manual Summary Rollup Progress
Date: Tue 27/12/22
Project Summary Manual Summary Manual Progress

Inactive Task Start-only

Inactive Milestone Finish-only

Page 9