ID Task Name Duration Start Finish % Complete Predecessors December 2014 January 2015 February 2015 March 2015 April 2015 May 2015 June 2015 July 2015 August 2015 September
W-1 W1 W2 W3 W4 W5 W6 W7 W8 W9 W10 W11 W12 W13 W14 W15 W16 W17 W18 W19 W20 W21 W22 W23 W24 W25 W26 W27 W28 W29 W30 W31 W32 W33 W34 W35 W36 W37 W38 W39 W40 W41 W42
24/11 01/12 08/12 15/12 22/12 29/12 05/01 12/01 19/01 26/01 02/02 09/02 16/02 23/02 02/03 09/03 16/03 23/03 30/03 06/04 13/04 20/04 27/04 04/05 11/05 18/05 25/05 01/06 08/06 15/06 22/06 29/06 06/07 13/07 20/07 27/07 03/08 10/08 17/08 24/08 31/08 07/09 14/09
1 PROJECT SUMMARY 64 days Fri 26/06/15 Sun 20/09/15 80%
4 CONTRACT STUDY & ACKNOWLEDGEMENT 8 days Wed 01/07/15 Fri 10/07/15 100% 3
6 REQUEST FOR QUOTATION FROM SUPPLIER 6 days Wed 01/07/15 Wed 08/07/15 100%
17 JOB METHOD STATEMENT SUBMISSION 3 days Wed 26/08/15 Fri 28/08/15 100%
18 JOB HAZARD ANALYSIS SUBMISSION 3 days Wed 26/08/15 Fri 28/08/15 100%
20 PTI APPLICATION & APPROVAL 30 days Mon 27/07/15 Fri 04/09/15 82%
23 WELDING OF FLANGES AND BRANCH FITTINGS TO PIPE BODY 8 days Fri 14/08/15 Tue 25/08/15 100% 22
25 VISUAL AND DIMENSIONAL INSPECTION 1 day Wed 26/08/15 Wed 26/08/15 100% 23
29 INSTALLATION OF SPOOL #1 AND SPOOL #2, LEAK TEST & 1 day Fri 18/09/15 Fri 18/09/15 0% 27FS+4
COMMISSIONING days
31 INSTALLATION OF SPOOL #3, LEAK TEST & COMMISSIONING 1 day Sun 20/09/15 Sun 20/09/15 0%
32 BLASTING & PAINTING OF THE WHOLE STATION 10 days Tue 01/09/15 Sun 13/09/15 0%