CLIENT: PGB P 2025 - ALOR GAJAH CITY GATE RECTIFICATION WORKS

P.O NO: 4120113513

ID Task Name Duration Start Finish % Complete Predecessors December 2014 January 2015 February 2015 March 2015 April 2015 May 2015 June 2015 July 2015 August 2015 September
W-1 W1 W2 W3 W4 W5 W6 W7 W8 W9 W10 W11 W12 W13 W14 W15 W16 W17 W18 W19 W20 W21 W22 W23 W24 W25 W26 W27 W28 W29 W30 W31 W32 W33 W34 W35 W36 W37 W38 W39 W40 W41 W42
24/11 01/12 08/12 15/12 22/12 29/12 05/01 12/01 19/01 26/01 02/02 09/02 16/02 23/02 02/03 09/03 16/03 23/03 30/03 06/04 13/04 20/04 27/04 04/05 11/05 18/05 25/05 01/06 08/06 15/06 22/06 29/06 06/07 13/07 20/07 27/07 03/08 10/08 17/08 24/08 31/08 07/09 14/09
1 PROJECT SUMMARY 64 days Fri 26/06/15 Sun 20/09/15 80%

2 PROJECT MANAGEMENT 9 days Tue 30/06/15 Fri 10/07/15 100%

3 PO AWARD 1 day Tue 30/06/15 Tue 30/06/15 100%

4 CONTRACT STUDY & ACKNOWLEDGEMENT 8 days Wed 01/07/15 Fri 10/07/15 100% 3

5 PROCUREMENT OF VALVES 52 days Wed 01/07/15 Thu 10/09/15 89%

6 REQUEST FOR QUOTATION FROM SUPPLIER 6 days Wed 01/07/15 Wed 08/07/15 100%

7 BIDDING ANALYSIS 1 day Thu 09/07/15 Thu 09/07/15 100% 6

8 PLACE ORDER 1 day Fri 10/07/15 Fri 10/07/15 100% 7

9 DOCUMENTATION (GA DRAWING,VDML,ITP) 29 days Mon 13/07/15 Thu 20/08/15 100% 8

10 ITEMS TO BE READY AT FACTORY 35 days Mon 13/07/15 Fri 28/08/15 100% 8

11 ITEMS TO ARRIVE AT DOGSB 5 days Mon 31/08/15 Fri 04/09/15 0% 10

12 LEAK TEST 1 day Mon 07/09/15 Mon 07/09/15 0% 11

13 BLASTING & PAINTING 3 days Tue 08/09/15 Thu 10/09/15 0% 12

14 TRAINING 1 day Fri 26/06/15 Fri 26/06/15 100%

15 WORK LEADER TRAINING 1 day Fri 26/06/15 Fri 26/06/15 100%

16 DOCUMENTATION 3 days Wed 26/08/15 Fri 28/08/15 100%

17 JOB METHOD STATEMENT SUBMISSION 3 days Wed 26/08/15 Fri 28/08/15 100%

18 JOB HAZARD ANALYSIS SUBMISSION 3 days Wed 26/08/15 Fri 28/08/15 100%

19 PTO/PTI 30 days Mon 27/07/15 Fri 04/09/15 82%

20 PTI APPLICATION & APPROVAL 30 days Mon 27/07/15 Fri 04/09/15 82%

21 SPOOL FABRICATION 30 days Mon 27/07/15 Fri 04/09/15 77%

22 PROCUREMENT OF RAW MATERIALS 14 days Mon 27/07/15 Thu 13/08/15 100%

23 WELDING OF FLANGES AND BRANCH FITTINGS TO PIPE BODY 8 days Fri 14/08/15 Tue 25/08/15 100% 22

24 NDT 1 day Wed 26/08/15 Wed 26/08/15 100% 23

25 VISUAL AND DIMENSIONAL INSPECTION 1 day Wed 26/08/15 Wed 26/08/15 100% 23

26 HYDROTEST OF THE ASSEMBLED UNIT 2 days Thu 27/08/15 Fri 28/08/15 0% 25

27 BLASTING & PAINTING 5 days Mon 31/08/15 Fri 04/09/15 0% 26

28 HOOK UP & INSTALLATION 3 days Fri 18/09/15 Sun 20/09/15 0%

29 INSTALLATION OF SPOOL #1 AND SPOOL #2, LEAK TEST & 1 day Fri 18/09/15 Fri 18/09/15 0% 27FS+4
COMMISSIONING days

30 SPARE DAY 1 day Sat 19/09/15 Sat 19/09/15 0% 29

31 INSTALLATION OF SPOOL #3, LEAK TEST & COMMISSIONING 1 day Sun 20/09/15 Sun 20/09/15 0%

32 BLASTING & PAINTING OF THE WHOLE STATION 10 days Tue 01/09/15 Sun 13/09/15 0%

33 BLASTING & PAINTING ACTIVITY 2 wks Tue 01/09/15 Sun 13/09/15 0%

Task Split Progress Milestone Summary Project Summary External Tasks External Milestone Deadline

DOCUMENT NO: Page 1


REVISION NO: REV. E
UPDATE DATE: 28th Aug 2015