Professional Documents
Culture Documents
Lecture 9 Slides After Lecture Version
Lecture 9 Slides After Lecture Version
Lecture 9 Slides After Lecture Version
1
Learning objectives
Week 8 costing products & services:
• Total Absorption Costing
• Activity Based Costing
• Labour and Time
• Pricing Strategies
2
Relevant Costing
• Make future decisions (special order, product mix, make or buy, replacement of equipment)
• A cost that has been incurred in the past is totally irrelevant for decision making
• Only consider those cash flows which will alter if the project is accepted. This includes cash
flows which would occur if the project does not go ahead (Opportunity Cost)
• Accept a project if it yields a higher net cash inflow than the best alternative course of action.
3
Irrelevant Cost to Ignore
• Sunk costs which are costs that have already been incurred
• Committed costs which are costs that you will have to pay whether
you do the project or not
4
Example: Parser Limited
The managing director of Parser Limited, a small business, is considering
undertaking a one-off contract. She has asked her inexperienced accountant to
advise on what costs are likely to be incurred so that she can price at a profit. The
following schedule has been prepared:
£
Direct wages 28,500
Supervisor costs 11,500
General overheads 4,000
Machine overheads 18,000
Total Costs 98,300
5
A special order
What is the Relevant Cost?
Are the current two skilled labour free?
Direct wages of £28,500 comprise the
wages of two employees, particularly skilled
in the labour process for this job. They could No
Yes
be transferred from another department to
undertake the work on the special order.
They are fully occupied in their usual £28,500 What to do?
department and sub-contracting staff would Irrelevant
have to be brought in to undertake the work Committed
left behind. Sub-contracting costs would be Use these Find two
Cost
£32,000 for the period of the work. Other two skilled special sub-
sub-contractors who are skilled in the workers and constructors
special-order techniques are also available find general
to work on the special order. The costs for this
sub- special
associated with this would amount to constructors
£31,300. project
for what they £31,300
are doing
However, how about the quality and customer
now
satisfaction?
£32,000 Relevant
Cost
6
What is the Relevant Cost?
A supervisor would have to work on the special order. The cost of £11,500 is
made up of £8,000 normal payments plus a £3,500 additional bonus for working
on the special order. Normal payments refer to the fixed salary of the supervisor.
In addition, the supervisor would lose incentive payments in his normal work
amounting to £2,500. It is not anticipated that any replacement costs relating to
the supervisors' work on other jobs would arise.
7
What is the Relevant Cost?
A supervisor would have to work on the special order. The cost of £11,500 is
made up of £8,000 normal payments plus a £3,500 additional bonus for working
on the special order. Normal payments refer to the fixed salary of the supervisor.
In addition, the supervisor would lose incentive payments in his normal work
amounting to £2,500. It is not anticipated that any replacement costs relating to
the supervisors' work on other jobs would arise.
8
Are these Relevant Costs?
9
What is the Relevant Cost?
Machine overheads of £18,000 (for running costs such as electricity) are
charged at £3 per hour. It is estimated that 6,000 hours will be needed for the
special order. The machine has 4,000 hours available capacity. The further
2,000 hours required will mean an existing job is taken off the machine resulting
in lost contributions to profits of £2 per hour.
6,000 Hours x £3 per hour = £18,000 These are variable costs (incremental)
10
To Sum up
The relevant costing schedule would compare to the original as follows:
11
Relevant Costing Critique
Benefits Issues
Enables visibility of the net Not easy for managers to
cash impact of decisions calculate
Considers exactly what will Not easy to collect all the costs
change within the company as information
a result of the decision Cannot always see the indirect
Considers indirect consequences of a decision
consequences of a decision
e.g. opportunity costs
Cost Volume Profit Analysis
13
Recap: Fixed and Variable Costs
Total Cost =
Total Fixed Cost +
Total Variable Cost
14
The Break-even point
Analysing the relationship between activity, costs and profit
Profit =
Total Revenue -
Total Cost
Break-even point is
the point that the
company neither
made profits or losses
16
Calculating the break-even point
Contribution Per Unit = Sales Price per unit – Variable Cost per unit
17
Example break-even calculation
• Sales price £5 per unit
• Variable costs £3.50 per unit
• Fixed costs £30,000
Contribution = £5 - £3.50 = £1.50
Break Even = Fixed Costs £30,000 / £1.50 = 20,000 units
18
Margin of Safety example
• Expected sales £200,000
• Expected sales volume 20,000 units
• Total costs £185,000
• Fixed costs included in above £45,000
NP = px – (a + bx)
NP = Net profit
p = Sales price
x = volume / units sold
a = total fixed costs
b = variable costs / unit
20
If a single product is made and sold…
• Direct material cost £6 per unit
• Direct labour cost £7 per unit
• Variable production overhead cost £10 per unit
• Sales price £28
• Fixed costs £58,000 per annum
NP = Px – (a + bx)
35,000 = P x 20,000 – (85,000 + 45 x 20,000)
35,000 + 85,000 + 900,000 = 20,000 P
Price = £51 per unit
23
CVP Critique
Benefits Issues
Easy to calculate and Only fit for a single product or
understand constant sales mix
Help Company to set the price Hard to split costs into fixed and
of products to achieve target variable elements
profit Does not consider human
Consider margin of safety for behaviour and other alternatives
company to adjust of business strategy
Next Steps this week…
25
Looking Ahead to week 10…
26