Professional Documents
Culture Documents
22-31 Breaker, Switch Gear Tech Spec
22-31 Breaker, Switch Gear Tech Spec
The LRWWU requires the preventative maintenance services and repairs of circuit breakers existing in-
service 13.2kV and 480V electrical distribution switchgear, switchgear components, and protection
relays. This will include, but not be limited to; inspection, maintenance, and repairs of circuit breakers
and associated circuit breaker equipment within the switchgear for each breaker identified, MV and LV
switchgear (and PLC’s), motor control centers, and protection relay replacement, programming, testing
and commissioning.
CONTRACT PERIOD
The preventative maintenance and repair of circuit breakers, switchgear (and PLC’s), MCC’s, and
protection relays services will be performed on a schedule that is mutually agreeable to both LRWWU
and Contractor. The contract will be issued as a yearly contract based on the workload and availability of
electrical equipment within the distribution network.
SCOPE OF WORK
This section describes the nature and scope of preventative maintenance and repair of circuit breaker,
switchgear and relay services to be provided for LRWWU. The successful bid will demonstrate the
approach and qualifications for the maintenance and repairs of the 13.2kV and 480V electrical
distribution circuit breakers, switchgear & MCC’s, and relays.
This RFP is for circuit breaker preventative maintenance, switchgear, MCC and protection relay services.
Services are to include inspection, testing, maintenance, evaluating and estimating a quote for repair. The
purpose of this Contract is to have functional MV and LV circuit breakers, switchgear, MCC’s, and
protection relays at the LRWWU sites.
The Contractor must be National Electric Code (NEC) Compliant, NFPA 70E, NETA, NESC, national,
and local codes.
This scope of services shall be used as a basis for the deliverables required for the project.
The Scope of Work in the below section applies all circuit breakers, switchgear, and relays listed throughout
the RFP.
1. Response Time Requirements
a. The Contractor should have a service center capable of repairing, rebuilding and retesting
electrical breakers.
b. The Contractor must have an associate dedicated to parts research and availability for the
repair of electrical switch gear components.
c. The Contractor must be able to respond within 4 hours to a request for emergency
services.
d. The Contractor must respond within 5 days of a request for services.
City of Lowell – Lowell Regional Wastewater Utility 3
LRWWU 13.2kV & 480V Circuit Breaker RFP
2. Equipment Requirements
a. The Contractor must have test equipment calibrated to NETA maintenance testing
specifications and is traceable to National Institute of Standards and Technology (NIST).
b. The Contractor must have at least 10 years’ experience using a High Current Test Set and
Secondary Breaker Test Set.
3. Test Reporting Requirements
a. The Contractor must provide detailed field test reports showing the as-found and as-left
equipment conditions, protection settings, etc. for all equipment.
4. Additional Requirements
a. Any and all equipment required performing the aforementioned work scope such as
special lifting; transporting or racking devices will be furnished by the Contractor.
b. Any required power for work to be performed or testing to be conducted will be
furnished by the Contractor when facility power is unavailable.
c. All equipment, labor and materials will be provided by the Contractor as per the quote.
d. The owner will furnish an onsite representative during the scheduled contract
maintenance.
e. The Contractor is required to perform any and all energizing and de-energizing of
electrical equipment and apparatus at the request and coordination with LRWWU.
f. If there is any defective equipment discovered during the de-energizing and energizing of
the equipment LRWWU must be contacted immediately and no additional work is to be
performed without a written authorization signed by the owner’s designated
representative.
g. Any and all manpower, equipment scheduling, travel expense etc. is the responsibility of
the Contractor.
h. A switching agreement will be granted upon request of the Contractor.
i. No additional compensation will be granted for weather or any other unforeseen delay
unless the delay is attributed to the request of and for the convenience of the owner.
j. If any items are determined that they are in need of repair or replacement said items will
be quoted in an itemized quotation which will include but not be limited to additional
testing fees, freight, procurement time, labor, inspection time etc.
k. A preliminary meeting and a close out meeting will be required.
l. Contractor must perform all work items per the most current OSHA and NFPA 70E
requirements to include current Lock-out Tag-out requirements.
m. Contractor to provide LRWWU with details of the contractor’s electrical safety program.
5. Site Meetings
a. The selected Contractor will attend all scheduled site meetings
6. Circuit Breakers, Vacuum, Medium-Voltage (600V-34,500V)
a. Before servicing, each circuit breaker will be operated (manually and electrically), racked
in and out of its cubicle and inspected for proper operation of the mechanisms and
electrical devices.
1) Visual and mechanical Inspection
i. Inspect physical and mechanical condition
ii. Prior to cleaning the unit, perform as-found tests, if required
iii. Clean the unit
iv. Inspect vacuum bottle assemblies
v. Inspect vacuum bellows operation
vi. Use appropriate lubrication on moving current-carrying parts and on
moving and sliding surfaces
vii. Record as-found and as-left operation counter readings
City of Lowell – Lowell Regional Wastewater Utility 4
LRWWU 13.2kV & 480V Circuit Breaker RFP
2) Electrical tests
i. Perform insulation-resistance tests for one minute on each pole, phase-to-
phase and phase-to-ground with circuit breaker closed and across each
pole with the breaker open. Apply voltage in accordance with
manufacturer’s published data. In the absence of manufacturer’s
published data, use industry standard
ii. Perform a contact/pole-resistance test
iii. With breaker in a test position, perform the following tests
Trip and close breaker with the control switch
Trip breaker by operating each of its protective relays
Verify mechanism charge, trip-free, and anti-pump functions
iv. Perform a vacuum bottle integrity (dielectric withstand voltage) test
across each vacuum bottle with the breaker in the open position in strict
accordance with manufacturer’s specifications
v. Test data will be included as part of the Engineering Appraisal Report.
7. Circuit Breakers, Low Voltage (600V)
a. Before servicing, each circuit breaker will be operated (manually and electrically), racked
in and out of its cubicle and inspected for proper operation of the mechanisms and
electrical devices.
1) The circuit breaker will be inspected for contact alignment and correct wipe and
gap measurements.
2) Operating mechanisms will be cleaned (including removal of old grease),
lubricated, and inspected for proper operation.
3) The primary intermediate and arcing contacts will be cleaned and inspected for
excessive arcing, pitting or abnormal wear.
4) The primary disconnecting device contacts will be cleaned and lubricated with
the appropriate contact lubricant.
5) Secondary disconnect and auxiliary relays will be inspected for arcing, abnormal
wear and proper operation.
6) Circuit breaker interlocks, mechanical and electrical, will be checked for proper
operation.
7) The primary contact resistance of each phase will be measured with a low
reading ohmmeter.
8) After cleaning, a phase-to-phase and phase-to-ground insulation resistance test
will be performed in accordance with ANSI standards.
9) The circuit breakers equipped with series or solid state overcurrent trip devices
will be high current tested to verify calibration of the trip devices.
10) The circuit breakers equipped with solid state overcurrent trip devices will be
tested with their respective factory test sets.
11) Test data will be included as part of the Engineering Appraisal Report.
8. MV and LV Switchgear and MCC’s Onsite Maintenance Testing
a. MV Switchgear
1) Initial Documentation
i. Enter nameplate data into hand-held data collection unit and/or record on
test and inspection forms
ii. Record the substation identification
iii. Record the number of cubicles and breakers
iv. Record space heater resistance and voltage
2) Furnish an Arc Flash Risk Assessment Study per the requirements set
forth in the NFPA 70E Standard for Electrical Safety in the Workplace. The
arc flash risk assessment shall be performed according to the IEEE Standard
1584, the IEEE Guide for Performing Arc-Flash Calculations in accordance
with this Section and applicable reference standards listed in Article 1.03.
The scope of the studies shall include new distribution equipment supplied
by the Contractor and modified electrical distribution equipment under
this Contract.
BID SUBMITTAL
1. Contractor must submit a Bid based on the scope of work included herein.
2. Contractor must submit the attached Bid Sheet (see the end of this bid) filled out and signed by
the Contractor representative.
3. Optional services will have separate line items within the Bid Sheet to cover the costs for these
services.
4. Contractor must submit a list of 3 references for similar work performed within the last 5 years.
DELIVERABLES
1. Signed Bid Sheet
2. Final Report
a. Individual Component/System Testing Reports
PROJECT ADMINISTRATION
Aaron Fox or his designee will act as Project Manager and will be the point of contact throughout the
project. All questions, correspondence and invoices will be addressed to the Project Manager.
TIME OF COMPLETION
The project is budgeted for December 1, 2021 ending December 31, 2022. The Contractor shall propose a
timeline for completing this work in their Bid considering the refurbishing of all circuit breakers.
____________________ ____________________________________
(Total Amount per Year) (Total Amount in Words)
____________________ ____________________________________
(Total Amount per hour) (Total Amount in Words for 80 Hours)
____________________ ____________________________________
(Total Amount per Year) (Total Amount in Words)
____________________ ____________________________________
(Total Amount per hour) (Total Amount in Words for Eight Hours)
____________________ ____________________________________
(Total Amount per hour) (Total Amount in Words for Eight Hours)
________________________________________________
________________________________________________
________________________________________________
Telephone # ________________________________________________