Download as docx, pdf, or txt
Download as docx, pdf, or txt
You are on page 1of 13

Decision Tree Examples

Example 1:
A company is trying to decide whether to bid for a certain contract or not.
They estimate that merely preparing the bid will cost £10,000. If their
company bid then they estimate that there is a 50% chance that their bid
will be put on the "short-list", otherwise their bid will be rejected.
Once "short-listed" the company will have to supply further detailed
information (entailing costs estimated at £5,000). After this stage their bid
will either be accepted or rejected.
The company estimate that the labour and material costs associated with
the contract are £127,000. They are considering three possible bid prices,
namely £155,000, £170,000 and £190,000. They estimate that the
probability of these bids being accepted (once they have been short-listed)
is 0.90, 0.75 and 0.35 respectively.
What should the company do and what is the expected monetary value of
your suggested course of action?

Solution
The decision tree for the problem is shown below.
Below we carry out step 1 of the decision tree solution procedure which
(for this example) involves working out the total profit for each of the
paths from the initial node to the terminal node (all figures in £'000).
Step 1
 path to terminal node 7 - the company do nothing
Total profit = 0
 path to terminal node 8 - the company prepare the bid but fail to
make the short-list
Total cost = 10 Total profit = -10
 path to terminal node 9 - the company prepare the bid, make the
short-list and their bid of £155K is accepted
Total cost = 10 + 5 + 127 Total revenue = 155 Total profit = 13
 path to terminal node 10 - the company prepare the bid, make the
short-list but their bid of £155K is unsuccessful
Total cost = 10 + 5 Total profit = -15
 path to terminal node 11 - the company prepare the bid, make the
short-list and their bid of £170K is accepted
Total cost = 10 + 5 + 127 Total revenue = 170 Total profit = 28
 path to terminal node 12 - the company prepare the bid, make the
short-list but their bid of £170K is unsuccessful
Total cost = 10 + 5 Total profit = -15
 path to terminal node 13 - the company prepare the bid, make the
short-list and their bid of £190K is accepted
Total cost = 10 + 5 + 127 Total revenue = 190 Total profit = 48
 path to terminal node 14 - the company prepare the bid, make the
short-list but their bid of £190K is unsuccessful
Total cost = 10 + 5 Total profit = -15
 path to terminal node 15 - the company prepare the bid and make the
short-list and then decide to abandon bidding (an implicit option
available to the company)
Total cost = 10 + 5 Total profit = -15
Hence we can arrive at the table below indicating for each branch the total
profit involved in that branch from the initial node to the terminal node.
Terminal node Total profit £
7 0
8 -10
9 13
10 -15
11 28
11 -15
13 48
14 -15
15 -15

We can now carry out the second step of the decision tree solution
procedure where we work from the right-hand side of the diagram back to
the left-hand side.
Step 2
Consider chance node 4 with branches to terminal nodes 9 and 10
emanating from it. The expected monetary value for this chance node is
given by 0.90(13) + 0.10(-15) = 10.2
Similarly the EMV for chance node 5 is given by 0.75(28) + 0.25(-15) =
17.25
The EMV for chance node 6 is given by 0.35(48) + 0.65(-15) = 7.05
Hence at the bid price decision node we have the four alternatives
(1) bid £155K EMV = 10.2
(2) bid £170K EMV = 17.25
(3) bid £190K EMV = 7.05
(4) abandon the bidding EMV = -15
Hence the best alternative is to bid £170K leading to an EMV of 17.25
Hence at chance node 2 the EMV is given by 0.50(17.25) + 0.50(-10) =
3.625
Hence at the initial decision node we have the two alternatives
(1) prepare bid EMV = 3.625
(2) do nothing EMV = 0
Hence the best alternative is to prepare the bid leading to an EMV of
£3625. In the event that the company is short-listed then (as discussed
above) it should bid £170,000.
Example 2:
Your company is considering whether it should tender for two contracts (C1 and C2) on offer
from a government department for the supply of certain components. If tenders are submitted,
the company will have to provide extra facilities, the cost of which will have to be entirely
recouped from the contract revenue. The risk, of course, is that if the tenders are unsuccessful
then the company will have to write off the cost of these facilities.

The extra facilities necessary to meet the requirements of contract C1 would cost £50,000.
These facilities would, however, provide sufficient capacity for the requirements of contract C2
to be met also. In addition the production costs would be £18,000. The corresponding
production costs for contract C2 would be £10,000.

If a tender is made for contract C2 only, then the necessary extra facilities can be provided at a
cost of only £24,000. The production costs in this case would be £12,000.

It is estimated that the tender preparation costs would be £2,000 if tenders are made for
contracts C1 or C2 only and £3,000 if a tender is made for both contracts C1 and C2.

For each contract, possible tender prices have been determined. In addition, subjective
assessments have been made of the probability of getting the contract with a particular tender
price as shown below. Note here that the company can only submit one tender and cannot, for
example, submit two tenders (at different prices) for the same contract.

Possible Probability
tender of getting
prices (£) contract
Tendering for C1 only 120,000 0.30
110,000 0.85
Tendering for C2 only 70,000 0.10
65,000 0.60
60,000 0.90
Tendering for both C1 and C2 190,000 0.05
140,000 0.65
100,000 0.95

In the event that the company tenders for both C1 and C2 it will either win both contracts (at the
price shown above) or no contract at all.

 What do you suggest the company should do and why?


 What is the "downside" of your suggested course of action?
Solution
The decision tree for the problem is shown below.

Below we carry out step 1 of the decision tree solution procedure which (for this example)
involves calculating the total profit for each of the paths from the initial node to the terminal
nodes.

Step 1

 path to terminal node 12 - we decide to tender for C1 only at a price of 120K and are
successful

Total revenue = 120

Total cost = 50 + 18 + 2 = 70

Total profit = 50 (all figures in £K)


 path to terminal node 13 - we decide to tender for C1 only at a price of 120K but are
unsuccessful

Total revenue = 0

Total cost = 50 + 2 = 52

Total profit = -52

 path to terminal node 14 - we decide to tender for C1 only at a price of 110K and are
successful

Total revenue = 110

Total cost = 50 + 18 + 2 = 70

Total profit = 40

 path to terminal node 15 - we decide to tender for C1 only at a price of 110K but are
unsuccessful

Total revenue = 0

Total cost = 50 + 2 = 52

Total profit = -52

 path to terminal node 16 - we decide to tender for C2 only at a price of 70K and are
successful

Total revenue = 70

Total cost = 24 + 12 + 2 = 38

Total profit = 32

 path to terminal node 17 - we decide to tender for C2 only at a price of 70K but are
unsuccessful

Total revenue = 0

Total cost = 24 + 2 = 26

Total profit = -26

 path to terminal node 18 - we decide to tender for C2 only at a price of 65K and are
successful
Total revenue = 65

Total cost = 24 + 12 + 2 = 38

Total profit = 27

 path to terminal node 19 - we decide to tender for C2 only at a price of 65K but are
unsuccessful

Total revenue = 0

Total cost = 24 + 2 = 26

Total profit = -26

 path to terminal node 20 - we decide to tender for C2 only at a price of 60K and are
successful

Total revenue = 60

Total cost = 24 + 12 + 2 = 38

Total profit = 22

 path to terminal node 21 - we decide to tender for C2 only at a price of 60K but are
unsuccessful

Total revenue = 0

Total cost = 24 + 2 = 26

Total profit = -26

 path to terminal node 22 - we decide to tender for C1/C2 at a price of 190K and are
successful

Total revenue = 190

Total cost = 50 + 18 + 10 + 3 = 81

Total profit = 109

 path to terminal node 23 - we decide to tender for C1/C2 at a price of 190K but are
unsuccessful

Total revenue = 0
Total cost = 50 + 3 = 53

Total profit = -53

 path to terminal node 24 - we decide to tender for C1/C2 at a price of 140K and are
successful

Total revenue = 140

Total cost = 50 + 18 + 10 + 3 = 81

Total profit = 59

 path to terminal node 25 - we decide to tender for C1/C2 at a price of 140K but are
unsuccessful

Total revenue = 0

Total cost = 50 + 3 = 53

Total profit = -53

 path to terminal node 26 - we decide to tender for C1/C2 at a price of 100K and are
successful

Total revenue = 100

Total cost = 50 + 18 + 10 + 3 = 81

Total profit = 19

 path to terminal node 27 - we decide to tender for C1/C2 at a price of 100K but are
unsuccessful

Total revenue = 0

Total cost = 50 + 3 = 53

Total profit = -53

 path to terminal node 28 - we decide not to tender at all

Total revenue = 0

Total cost = 0

Total profit = 0
Hence we can form the table below indicating for each branch the total profit involved in that
branch from the initial node to the terminal node.

Terminal node Total profit (£K)


12 50
13 -52
14 40
15 -52
16 32
17 -26
18 27
19 -26
20 22
21 -26
22 109
23 -53
24 59
25 -53
26 19
27 -53
28 0

We can now carry out the second step of the decision tree solution procedure where we work
from the right-hand side of the diagram back to the left-hand side.

Step 2

Consider chance node 1 (with branches to terminal nodes 12 and 13 emanating from it). The
expected monetary value (EMV) for this chance node is given by 0.3 x (50) + 0.7 x (-52) = -
21.4

Consider chance node 2, the EMV for this chance node is given by 0.85 x (40) + 0.15 x (-52) =
26.2

Then for the decision node relating to the price for C1 we have the two alternatives:

(5) price 120K EMV = -21.4

(6) price 110K EMV = 26.2

It is clear that, in £ terms, alternative 6 is the most attractive alternative and so we can discard
the other alternative.

Continuing the process the EMV for chance node 3 is given by 0.10 x (32) + 0.9 x (-26) = -20.2

The EMV for chance node 4 is given by 0.60 x (27) + 0.40 x (-26) = 5.8
The EMV for chance node 5 is given by 0.90 x (22) + 0.10 x (-26) = 17.2

Hence for the decision node relating to the price for C2 we have the three alternatives:

(7) price 70K EMV = -20.2

(8) price 65K EMV = 5.8

(9) price 60K EMV = 17.2

It is clear that, in £ terms, alternative 9 is the most attractive alternative and so we can discard
the other two alternatives.

Continuing the process the EMV for chance node 6 is given by 0.05 x (109) + 0.95 x (-53) = -
44.9

The EMV for chance node 7 is given by 0.65 x (59) + 0.35 x (-53) = 19.8

The EMV for chance node 8 is given by 0.95 x (19) + 0.05 x (-53) = 15.4

Hence for the decision node relating to the price to charge for C1 and C2 we have the three
alternatives:

(10) price 190K EMV = -44.9

(11) price 140K EMV = 19.8

(12) price 100K EMV = 15.4

It is clear that, in £ terms, alternative 11 is the most attractive alternative and so we can discard
the other two alternatives.

Hence for the decision node relating to the tender decision we have the four alternatives:

(1) C1 only EMV = 26.2

(2) C2 only EMV = 17.2

(3) C1 and C2 EMV = 19.8

(4) no tender EMV = 0

It is clear that, in £ terms, alternative 1 is the most attractive alternative and so we can discard
the other three alternatives.

Hence we recommend that the company tenders for contract C1 only, with a tender price of
£110K because this alternative has the highest EMV of £26.2K.
If the company follows this recommendation the actual outcome will be one of the terminal
nodes 14 or 15 (depending upon chance events) i.e. the outcome will be one of [40, -52]. Hence
the downside is that the company may lose £52K (if their tender is unsuccessful).

You might also like