BILL of QUANTITY

JOB : Recosntruction of boundary wall with concrete panel Date : 15 Februari 2024

LOC : At north side beside clean water pump house

NO DESCRIPTION UNIT QTY RATE AMOUNT

A CONTRACTOR COST

I Civil Work
1 Excavation for foundation m3 5,06 300.000 1.518.000

2 Strouss dia 30 cm - 3 m & 1 m m1 48,00 150.000 7.200.000

3 Site Mix Concrete 1:2:3 m3 13,23 1.450.000 19.183.500

4 Shuttering Concrete sloof, beam & Column Structure m2 47,78 175.000 8.361.500

5 Reinforcement ( Labour ) + b. Wire kg 1.200,00 8.500 10.200.000

6 Supply & Fixing Concrete precast Fence m1 25,00 650.000 16.250.000

- Ex.Multi Karya beton or similar standart product

- Concrete K250 , Precast Prestressed

- Column 20cm x 20 cm x 4.5 m high , center to center column 2,5 m

- Concrete Fence t 5cm x 50 cm x 3,5 high , 7 panels

Cleaning after the jobs

TOTAL : 62.713.000

NB : DP 50% Dari Harga yg telah disepakati