METHOD OF STATEMENT FOR

STRUCTURAL DEFECTS
RECTIFICATION WORKS
This project is located at B Connaught Drive to proposed rectification works of structural
defects which mentioned during the building inspection by Singapore Metro Consulting .

The works involves minor structural reparation works including of spalling of concrete,
reparation of R.C column and PU grouting works.

The location of this project is shown in Figure 1.

REPARATION SPALLING OF
CONCRETE
CONTRUCTION PROCEDURES

1. Obtain all the necessary approvals / permits from the relevant Authorities
prior to carrying out physical works on site.
2. Prior to start work, ensure that all the existing services are diverted or
protected (if diversion is not necessary or to be carried out on later stage)
and ensure that it will not be affected by the proposed works.
3. Mobilize all the necessary plants and equipment to be used in the
construction site.
4. Mark up the defective concrete area

5. Removal of loose concrete cover


– Using high pressure water jet, 1100 bar (large area)
– With hammer drill (medium area)
– Hammer and chisel (small patch repairs)
6. Extent of Concrete Removal – remove concrete minimum 15 mm behind
main bars
7. Cleaning Reinforcement – to remove all the tie wires, rust, mortar /
Concrete and other loose material
8. Application of Corrosion Protection coats( as approved by PE) – apply
two 1 mm thick layers (total 2 mm minimum)*To allow time for the 1st
coat to harden before applying 2nd coat. To allow application to dry
before applying repair mortar.
9. Apply a bonding agent to the affected surface to ensure proper adhesion

10. Patch the hacked area using polymer modified non-shrink cement mortar
11. Curing protection by plastic sheeting

12. Paint (3layers as 2primiers and 1finish coat) over the patched area to
match the rest of area.
13. Dispose off debris and prepare area for permanent works construction.
14. Reinstate all the affected works, where necessary.

REPARATION OF R.C COLUMN


CONTRUCTION PROCEDURES

1. Obtain all the necessary approvals / permits from the relevant Authorities
prior to carrying out physical works on site.
2. Prior to start work, ensure that all the existing services are diverted or
protected (if diversion is not necessary or to be carried out on later stage)
and ensure that it will not be affected by the proposed works.
3. Mobilize all the necessary plants and equipment to be used in the
construction site.

4. Mark up the defective concrete area

5. Removal of loose concrete cover- with hammer drill and hammer and
chisel
– Remove tire wires, nails etc.
– Remove only defective concrete as instructed.
– Do not reduce structural integrity.
6. Extent of concrete removal – remove concrete minimum 15 mm behind
main bars
7. Roughen surface (2 mm minimum), cut sides minimum 90° to avoid
undercutting and maximum 135° to reduce debonding around edges.
Substrate shall be sound with no loose material.

8. Cleaning Reinforcement – to remove all the tie wires, rust, mortar /


Concrete and other loose material

9. Recovering the damaged main column bars along the damaged length
10. Welding the added bar and column bars to each other along the lap length

11. Application of Corrosion Protection coats( as approved by PE) – apply


two 1 mm thick layers (total 2 mm minimum)
– Hopper spray for large applications
– Brush for small applications
– Inspect bars after to ensure full coverage
– Use two brushes simultaneously to ensure full application behind bars

To allow time for the 1st coat to harden before applying 2nd coat. To allow application to dry
before applying repair mortar.