THE CONSTRUCTION OF EXTENSION TO THE EXISTING

HOLY SPIRIT CATHOLIC CHURCH AT GHALA

Original Month
Activity ID Activity name
Duration 1 2 3 4 5 6 7 8 9 10
CONSTRUCTION OF CLASSROOMS AND LECTURE HALL AT UTAS BRANCH IN NIZWA,
314
DHAKALIYA REGION
MILESTONE (KEY DATES) 314

GM1000 AWARD OF CONTRACT 0


GM1010 ENGINEERING COMENCEMENT 14
GM1020 DURATION OF PROJECT 300
GM1030 PROJECT START 0
GM1040 PROJECT FINISH 0

AUTHORITY APPROVALS 14
SUBMISSION OF DOCUMENT & RECEIPT OF CONSTRUCTION PERMIT APPROVAL FROM
AA1000 14
ENGINEER OF ABDULLA MUKADAM & PARTNER L.L.C.
SUBMISSION OF DOCUMENT & RECEIPT OF EXCAVATION PERMIT APPROVAL FROM FROM
AA1001 14
ENGINEER OF ABDULLA MUKADAM & PARTNER L.L.C.
MOBILIZATION 20
CM1000 INITIAL SITE SURVEY & INVESTIGATION 8

CM1010 RESOURCE MOBILISATION INCLUDING WORKERS & STAFFS 7

CM1020 SITE HORDINGS /SITE ESTABLISHMENT OF CONTRACTORS 10

CM1030 ARRANGING THE NECESSARY PERMITS AND APPROVALS TO CARRY THE WORK 5

ENGINEERING 46

SHOP DRAWINGS 42

CIVIL WORKS 14

ED1000 SUBMISSION OF SHOP DRAWINGS FOR CIVIL WORKS 20

ED1010 APPROVAL OF SHOP DRAWINGS FOR CIVIL WORKS 14

ELECTRICAL & MECHANICAL WORKS 14

ED1020 SUBMISSION OF SHOP DRAWINGS FOR ELECTRICAL & MECANICAL SERVICE 20

ED1030 APPROVAL OF SHOP DRAWINGS FOR ELECTRICAL & MECANICAL SERVICE 14

EXTERNAL WORKS 14
ED1040 SUBMISSION OF SHOP DRAWINGS FOR EXTERNAL WORKS 10

ED1050 APPROVAL OF SHOP DRAWINGS EXTERNAL WORKS DRAWING 14

METHOD STATEMENT 42

CIVIL WORKS 14

ED1000 SUBMISSION OF METHOD STATEMENT FOR CIVIL WORKS 20

ED1010 APPROVAL OF METHOD STATEMENT FOR CIVIL WORKS 14

ELECTRICAL & MECHANICAL WORKS 14

ED1020 SUBMISSION OF METHOD STATEMENT FOR ELECTRICAL & MECANICAL SERVICE 20

ED1030 APPROVAL OF METHOD STATEMENT FOR ELECTRICAL & MECANICAL SERVICE 14

EXTERNAL WORKS 14

ED1040 SUBMISSION OF METHOD STATEMENT FOR EXTERNAL WORKS 10

ED1050 APPROVAL OF METHOD STATEMENT EXTERNAL WORKS 14

PROCUREMENT 35

SUBMISSION OF MAS 30
PS1000 PREPARE & SUBMIT MAS FOR CIVIL MATERIALS 20
PS1010 PREPARE & SUBMIT MAS FOR ELECTRICAL & MECHANICAL MATERIALS 20
PS1020 PREPARE & SUBMIT OF MAS FOR EXTERNAL MATERIALS 20
APPROVAL OF MAS 25
PA1000 REVIEW & APPROVAL OF MAS FOR CIVIL MATERIALS 14
PA1010 REVIEW & APPROVAL OF MAS FOR ELECTRICAL & MECHANICAL MATERIALS 14
PA1020 REVIEW & APPROVAL OF MAS FOR EXTERNAL MATERIALS 14
PROCUREMENT OF MAS 45
PP1000 RAISE PURCHASE ORDER FOR APPROVED MATERIALS - CIVIL 2
PP1010 RAISE PURCHASE ORDER FOR APPROVED MATERIALS - MECHANICAL & ELECTRICAL 2
PP1020 RAISE PURCHASE ORDER FOR APPROVED MATERIALS - EXTERNAL 2
PP1030 MATERIAL DELIVERY FOR REGULAR (CONSUMABLES) 20
PP1040 MATERIAL DELIVERY FOR LONG LEADS 70
CONSTRUCTION 485

CIVIL WORKS-1 270


SUBSTRUCTURE 120
CS1000 SETTING OUT & MARKING 10
CS1010 EXCAVATION 15
CS1020 PCC WORKS 10
CS1030 COMBINED & ISOLATED FOOTING 10
CS1040 COLUMN PEDASTALS 10
CS1050 BLOCK WORK UPTO PLINTH BOTTOM 8
CS1060 PLINTH BEAM 8
CS1070 MEP WORK FOR UNDERGROUND SERVICES 8
CS1080 BITUMEN PROTECTION 6
CS1090 BACK FILL, COMPACT, ANTITERMITE 15
CS1100 FLOOR PCC 10
CS1110 LAYING MEP CONCEALED WORKS 10
CS1120 REINFORCEMENT FOR SLAB EXCLUDING LIFT PITS & CUTOUTS
CS1130 FLOOR CONCRETE 10
SUPER STRUCTURE 150
GROUND FLOOR 65
CSG1000 REINFORCEMENT FOR COLUMNS 5
CSG1010 CONCRETE COLUMNS 5
CSG1020 SETTING OUT FOR STAIRS BASE MARKINGS 5
CSG1030 PCC FOR STAIRS, COLUMN 5
CSG1040 REINFORCEMENT FOR STAIRS, COLUMN 5
CSG1050 CONCRETE STAIRS, COLUMN 5
CSG1060 BLOCK WORK FOR STAIR ENCLOSURE 5
CSG1070 BLOCK WORKS FOR WALLS 5
CSG1080 REINFORCEMENT FOR BEAMS 5
CSG1090 CONCRETE BEAMS 5
CSG1100 REINFORCEMENT FOR SLAB EXCLUDING DUCTS & CUTOUTS 5
CSG1110 REINFORCEMENT FOR RAMP 5
CSG1120 MEP CONCEALED WORKS FIRST FIX 5
CSG1130 FLOOR & RAMP CONCRETE 5
FIRST FLOOR 55
CSF1000 REINFORCEMENT FOR COLUMNS 5
CSF1010 CONCRETE COLUMNS 5
CSF1020 SETTING OUT FOR STAIRS BASE MARKINGS 5
CSF1030 PCC FOR STAIRS, COLUMN 5
CSF1040 REINFORCEMENT FOR STAIRS, COLUMN 5
CSF1050 CONCRETE STAIRS, COLUMN 5
CSF1060 BLOCK WORK FOR STAIR ENCLOSURE. 5
CSF1070 BLOCK WORKS FOR WALLS 5
CSF1080 REINFORCEMENT FOR BEAMS 3
CSF1090 CONCRETE BEAMS 2
CSF1100 REINFORCEMENT FOR SLAB EXCLUDING DUCTS & CUTOUTS 3
CSF1110 MEP CONCEALED WORKS FIRST FIX 2
CSF1120 CONCRETE SLAB 5
SECOND FLOOR 55
CSF1000 REINFORCEMENT FOR COLUMNS 5
CSF1010 CONCRETE COLUMNS 5
CSF1020 SETTING OUT FOR STAIRS BASE MARKINGS 5
CSF1030 PCC FOR STAIRS, COLUMN 5
CSF1040 REINFORCEMENT FOR STAIRS, COLUMN 5
CSF1050 CONCRETE STAIRS, COLUMN 5
CSF1060 BLOCK WORK FOR STAIR ENCLOSURE. 5
CSF1070 BLOCK WORKS FOR WALLS 5
CSF1080 REINFORCEMENT FOR BEAMS 3
CSF1090 CONCRETE BEAMS 2
CSF1100 REINFORCEMENT FOR SLAB EXCLUDING DUCTS & CUTOUTS 3
CSF1110 MEP CONCEALED WORKS FIRST FIX 2
CSF1120 CONCRETE SLAB 5
ROOF FLOOR 30
CSR1000 STAIRS CLOSING TOP SLAB 3
CSR1010 PCC FOR STAIRS, COLUMN 2
CSR1020 REINFORCEMENT FOR STAIRS, COLUMN 2
CSR1030 CONCRETE STAIRS, COLUMN & LIFT MACHINE ROOM WALLS 3
CSR1040 BLOCK WORK FOR STAIR ENCLOSURE. 3
CSR1050 BLOCK WORK FOR PUMP ROOM, GRP WATER TANK ROOM & STORE 3
CSR1060 200 MM CONCRETE BASE FOR GRP WATER TANK 3
CSR1070 REINFORCEMENT FOR BEAMS 2
CSR1080 CONCRETE BEAMS 3
CSR1090 REINFORCEMENT FOR STAIRCASE ROOF SLAB EXCLUDING CATLADDER CUTOUT 2
CSR1110 MEP CONCEALED WORKS FIRST FIX 3
CSR1120 CONCRETE ROOF SLAB 3
CSR1000 500MM HEIGHT PEDESTAL FOR OVERHEAD WATER TANK 3
CSR1010 INSTALL INSULATED GRP SECTIONAL OVER HEAD WATER TANK 3
CSR1130 PARAPETS BLOCK WORK 5
CSR1140 INSTALL CAT LADDER FOR ROOF TOP 2
MECHANICAL WORKS - FIRST FIX 50
PLUMBING 30
GROUND FLOOR 12
MEP1000 MARKING & WALL CHASING FOR WATER SUPPLY, DRAINAGE WORKS 3
MEP1010 PROVIDING SUPPORTS FOR HIGH LEVEL WATER SUPPLY, DRAINAGE WORKS 3
MEP1020 DRAINAGE PIPING WORKS ALONG WITH THE ACCESSORIES 2
MEP1030 WATER SUPPLY PIPING WORKS ALONG WITH THE ACCESSORIES
FIRST FLOOR 12
MEP1000 MARKING & WALL CHASING FOR WATER SUPPLY, DRAINAGE WORKS
MEP1010 PROVIDING SUPPORTS FOR HIGH LEVEL WATER SUPPLY, DRAINAGE WORKS
MEP1020 DRAINAGE PIPING WORKS ALONG WITH THE ACCESSORIES
MEP1030 WATER SUPPLY PIPING WORKS ALONG WITH THE ACCESSORIES
SECOND FLOOR 12
MEP1050 MARKING & WALL CHASING FOR WATER SUPPLY, DRAINAGE WORKS 3
MEP1060 PROVIDING SUPPORTS FOR HIGH LEVEL WATER SUPPLY, DRAINAGE WORKS 3
MEP1070 DRAINAGE PIPING WORKS ALONG WITH THE ACCESSORIES 2
MEP1080 WATER SUPPLY PIPING WORKS ALONG WITH THE ACCESSORIES
ROOF FLOOR 12
MEP1050 MARKING & WALL CHASING FOR WATER SUPPLY, DRAINAGE WORKS 3
MEP1060 PROVIDING SUPPORTS FOR HIGH LEVEL WATER SUPPLY, DRAINAGE WORKS 3
MEP1070 DRAINAGE PIPING WORKS ALONG WITH THE ACCESSORIES 2
MEP1080 WATER SUPPLY PIPING WORKS ALONG WITH THE ACCESSORIES

HVAC 15

GROUND FLOOR 10

MEHV1000 INSTALATION OF NECESSARY DUCTING, CONDENSING PIPES & DRAIN PIPES 10

MEHV1001 INSTALATION OF REFREGERANT PIPES & TOILET AIR DUCTS

FIRST FLOOR 10

MEHV1010 INSTALATION OF NECESSARY DUCTING, CONDENSING PIPES & DRAIN PIPES 10

MEHV1011 INSTALATION OF REFREGERANT PIPES & TOILET AIR DUCTS

SECOND FLOOR 5

MEHV1020 INSTALATION OF NECESSARY DUCTING, CONDENSING PIPES & DRAIN PIPES 5


INSTALATION OF REFREGERANT PIPES & TOILET AIR DUCTS

ROOF FLOOR 5

MEHV1020 INSTALATION OF NECESSARY DUCTING, CONDENSING PIPES & DRAIN PIPES 5

MEHV1021 INSTALATION OF REFREGERANT PIPES & TOILET AIR DUCTS


FIRE FIGHTING 5
GROUND FLOOR 3
MEF1000 INSTALLATION OF FIRE FIGHTING PIPES & FITTINGS 3

FIRST FLOOR 3

MEF1000 INSTALLATION OF FIRE FIGHTING PIPES & FITTINGS 3

SECOND FLOOR 2

MEF1010 INSTALLATION OF FIRE FIGHTING PIPES & FITTINGS 2

ROOF FLOOR 2

MEF1020 INSTALLATION OF FIRE FIGHTING PIPES & FITTINGS 2

ELECTRICAL & ELV WORK-FIRST FIX 50

GROUND FLOOR 22
MARKING & WALL CHASING FOR CONDUITS/BACK BOX/JUNCTION BOX/SMALL
ELE1000 4
POWER/EARTHING/LIGHTING/ELV SERVICES/HVAC/FIRE FIGTING SERVICES
FIXING CONDUITS/BACK BOX/JUNCTION BOX/SMALL POWER/ EARTHING/LIGHTING /ELV
ELE1010 4
SERVICES/HVAC/FIRE FIGTING SERVICES
ELE1020 MARKING & PROVIDING SUPPORT FOR CABLE TRAYS & TRUNKING 4

ELE1030 FIXING OF CABLE TRAYS & TRUNKINGS 4

FIRST FLOOR 22
MARKING & WALL CHASING FOR CONDUITS/BACK BOX/JUNCTION BOX/SMALL
ELE1000 4
POWER/EARTHING/LIGHTING/ELV SERVICES/HVAC/FIRE FIGTING SERVICES
FIXING CONDUITS/BACK BOX/JUNCTION BOX/SMALL POWER/ EARTHING/LIGHTING /ELV
ELE1010 4
SERVICES/HVAC/FIRE FIGTING SERVICES
ELE1020 MARKING & PROVIDING SUPPORT FOR CABLE TRAYS & TRUNKING 4

ELE1030 FIXING OF CABLE TRAYS & TRUNKINGS 4

SECOND FLOOR 22
MARKING & WALL CHASING FOR CONDUITS/BACK BOX/JUNCTION BOX/SMALL
ELE1060 4
POWER/EARTHING/LIGHTING/ELV SERVICES/HVAC/FIRE FIGTING SERVICES
FIXING CONDUITS/BACK BOX/JUNCTION BOX/SMALL POWER/ EARTHING/LIGHTING /ELV
ELE1070 4
SERVICES/HVAC/FIRE FIGTING SERVICES
ELE1080 MARKING & PROVIDING SUPPORT FOR CABLE TRAYS & TRUNKING 4

ELE1090 FIXING OF CABLE TRAYS & TRUNKINGS 4

ROOF FLOOR 5
MARKING & WALL CHASING FOR CONDUITS/BACK BOX/JUNCTION BOX/SMALL
ELE1110 3
POWER/EARTHING/LIGHTING/ELV SERVICES/HVAC/FIRE FIGTING SERVICES
FIXING CONDUITS/BACK BOX/JUNCTION BOX/SMALL POWER/ EARTHING/LIGHTING /ELV
ELE1120 2
SERVICES/HVAC/FIRE FIGTING SERVICES
CIVIL WORKS-2 120
METAL WORKS 45

GROUND FLOOR 15

CM1000 INSTALL HANDRAILS FOR STAIRS & RAMPS 10

CM1010 INSTALL METAL DOORS 5

FIRST FLOOR 15

CM1000 INSTALL HANDRAILS FOR STAIRS 10

CM1010 INSTALL METAL DOORS 5

SECOND FLOOR 15

CM1020 INSTALL HANDRAILS FOR STAIRS 10

CM1030 INSTALL METAL DOORS 5

ROOF FLOOR 15

CM1040 INSTALL HANDRAILS FOR STAIRS 10

CM1050 INSTALL METAL DOORS 5

DOORS & WINDOWS 35


GROUND FLOOR 15

CD1000 INSTALL DOORS & WINDOWS 15

FIRST FLOOR 15

CD1000 INSTALL DOORS & WINDOWS 15

SECOND FLOOR 15

CD1010 INSTALL DOORS & WINDOWS 15

ROOF FLOOR 5

CD1020 INSTALL DOORS & WINDOWS 5

FINISHES 120

GROUND FLOOR 50

CF1000 PLASTERING INTERNAL/EXTERNAL 20

CF1010 FLOORING DRY AREA 10

CF1020 TILING FLOOR & WALL ON WET AREAS 10

CF1030 TILING FLOOR ON DRY AREAS 10

FIRST FLOOR 50

CF1000 PLASTERING INTERNAL/EXTERNAL 20

CF1010 FLOORING DRY AREA 10


CF1020 TILING FLOOR & WALL ON WET AREAS 10

CF1030 TILING FLOOR ON DRY AREAS 10

SECOND FLOOR 50

CF1040 PLASTERING INTERNAL/EXTERNAL 20

CF1050 FLOORING DRY AREA 10

CF1060 TILING FLOOR & WALL ON WET AREAS 10

CF1070 TILING FLOOR ON DRY AREAS 10

ROOF FLOOR 20

CF1080 PLASTERING INTERNAL/EXTERNAL 10

CF1081 PLASTERING PARAPETS 11

CF1090 WHITE CEMENT ROOF TILING 10

PAINTING & DECORATIONS 75

GROUND FLOOR 30

CP1000 INTERNAL PAINTING 15

CP1010 EXTERNAL PAINTING 15

FIRST FLOOR 30

CP1000 INTERNAL PAINTING 15

CP1010 EXTERNAL PAINTING 15

SECOND FLOOR 30

CP1020 EXTERNAL PAINTING 15

CP1030 EXTERNAL PAINTING 15

ROOF FLOOR 15

CP1040 INTERNAL & EXTERNAL PAINTING 15

MECHANICAL WORKS - SECOND & FINAL FIX 100

PLUMBING 60

GROUND FLOOR 25

MEP1120 LEAK TEST 7

MEP1130 DISINFECTION & STERLIZATION 8

MEP1140 INSTALLATION OF SANITARY FIXTURE & OTHER ACCESSORIES 10


MEP1030 WATER SUPPLY PIPING WORKS ALONG WITH VALVES & ACCESSORIES 2
MEP1040 LABELING 2
FIRST FLOOR 25

MEP1150 LEAK TEST 7

MEP1160 DISINFECTION & STERLIZATION 8

MEP1170 INSTALLATION OF SANITARY FIXTURE & OTHER ACCESSORIES 10


MEP1080 WATER SUPPLY PIPING WORKS ALONG WITH VALVES & ACCESSORIES 2
MEP1090 LABELING 2
SECOND FLOOR 25

MEP1150 LEAK TEST 7

MEP1160 DISINFECTION & STERLIZATION 8

MEP1170 INSTALLATION OF SANITARY FIXTURE & OTHER ACCESSORIES 10


MEP1080 WATER SUPPLY PIPING WORKS ALONG WITH VALVES & ACCESSORIES 2
MEP1090 LABELING 2
ROOF FLOOR 10

MEP1180 INSTALLATION OF GRP SECTIONAL TANKS 5

MEP1190 CONNECTION OF WATER SUPPLY TO TANK AND OTHER CONNECTIONS OUTGOING 8

MEP1200 INSTALLATION OF RAINWATER PIPE, WASTE WATER PIPE 5


MEP1210 WATER SUPPLY PIPING WORKS ALONG WITH VALVES & ACCESSORIES 3
MEP1220 LABELING 2
HVAC 40

GROUND FLOOR 15

MEHV1000 INSTALLATION OF SPLIT INDOOR UNITS

MEHV1010 INSTALLATION OF SPLIT CASSETTE UNITS

MEHV1020 INSTALLATION OF THERMOSTATS, FIRE DANPERS & VOLUME CONTROL DAMPERS

MEHV1030 INSTALLATION OF CEILING AIR DIFFUSER SUPPLY & RETURN


INSTALLATION DOOR TRANSFER GRILLS, EXTRACTION FANS & EXHAUST FANS (WALL
MEHV1040
MOUNTED)
MEHV1050 INSTALLATION OF DAMPERS , ATTENUATORS & AIR GRILLS

FIRST FLOOR 15

MEHV1000 INSTALLATION OF SPLIT INDOOR UNITS

MEHV1010 INSTALLATION OF SPLIT CASSETTE UNITS

MEHV1020 INSTALLATION OF THERMOSTATS, FIRE DANPERS & VOLUME CONTROL DAMPERS

MEHV1030 INSTALLATION OF CEILING AIR DIFFUSER SUPPLY & RETURN


INSTALLATION DOOR TRANSFER GRILLS, EXTRACTION FANS & EXHAUST FANS (WALL
MEHV1040
MOUNTED)
MEHV1050 INSTALLATION OF DAMPERS , ATTENUATORS & AIR GRILLS

SECOND FLOOR 15

MEHV1000 INSTALLATION OF SPLIT INDOOR UNITS

MEHV1010 INSTALLATION OF SPLIT CASSETTE UNITS

MEHV1020 INSTALLATION OF THERMOSTATS, FIRE DANPERS & VOLUME CONTROL DAMPERS

MEHV1030 INSTALLATION OF CEILING AIR DIFFUSER SUPPLY & RETURN


INSTALLATION DOOR TRANSFER GRILLS, EXTRACTION FANS & EXHAUST FANS (WALL
MEHV1040
MOUNTED)
MEHV1050 INSTALLATION OF DAMPERS , ATTENUATORS & AIR GRILLS

ROOF FLOOR 10

MEHV1050 INSTALLATION OF OUTDOOR AC UNITS, EXTRACT FANS ON FOUNDATIONS

MEHV1060 INSTALLATION OF OTHER UNITS

FIRE FIGHTING 5
GROUND FLOOR 3
MEF1030 INSTALLATION OF FIRE HOSE REEL , FIRE EXTINGUISHERS & BLANKET 3

FIRST FLOOR 2

MEF1040 INSTALLATION OF FIRE HOSE REEL , FIRE EXTINGUISHERS & BLANKET 2

ROOF FLOOR 2

MEF1050 INSTALLATION OF FIRE HOSE REEL , FIRE EXTINGUISHERS & BLANKET 2

ELECTRICAL & ELV WORK - SECOND & FINAL FIX 75

GROUND FLOOR 70

ELE1130 LIGHTING & POWER DB’S, PANELS & CONTROL BOARD WORKS 10

ELE1140 INSTALLATION OF MCC PANEL ETC. 10

ELE1150 FLEXIBLE DROP WORKS FOR LIGHTING / ELV SERVICES ETC. 10

ELE1160 INSTALLATION OF SUSPENSION RODS FOR LIGHT FITTINGS

ELE1170 CABLE WIRE PULLING 4

ELE1180 ELV CABLING WORK 2

ELE1190 EARTHING CABLING WORKS

ELE1200 INSTALLATION OF LIGHT FITTINGS 10


INSTALLATION OF ELV DEVICES SUCH AS TELECOMUNICATION , COMPUTER SYSTEMS &
ELE1210 10
ACCESORIES
ELE1220 INSTALLATION OF SMALL POWER ACCESSORIES LIKE SWITCHES, SOCKETS,ISOLATORS 12
INSTALLATION OF FIRE FIGHTING EQUIPMENT SUCH AS FIRE ALARM ,SMOKE DETECTORS
ELE1230
EMERGENCY /EXIT LIGHTS & OTHER ACCESSORIES
ELE1240 LABELLING 8

FIRST FLOOR 70

ELE1200 LIGHTING & POWER DB’S, PANELS & CONTROL BOARD WORKS 10

ELE1210 INSTALLATION OF MCC PANEL ETC. 10

ELE1220 FLEXIBLE DROP WORKS FOR LIGHTING / ELV SERVICES ETC. 10

ELE1230 INSTALLATION OF SUSPENSION RODS FOR LIGHT FITTINGS

ELE1240 CABLE WIRE PULLING

ELE1250 ELV CABLING WORK

ELE1260 EARTHING CABLING WORKS

ELE1270 INSTALLATION OF LIGHT FITTINGS 10


INSTALLATION OF ELV DEVICES SUCH AS TELECOMUNICATION , COMPUTER SYSTEMS &
ELE1280 10
ACCESORIES

ELE1290 INSTALLATION OF SMALL POWER ACCESSORIES LIKE SWITCHES, SOCKETS,ISOLATORS 4

INSTALLATION OF FIRE FIGHTING EQUIPMENT SUCH AS FIRE ALARM ,SMOKE DETECTORS


ELE1300 2
EMERGENCY /EXIT LIGHTS & OTHER ACCESSORIES

ELE1310 LABELLING

ROOF FLOOR 5

ELE1270 LIGHTING & POWER DB’S, PANELS & CONTROL BOARD WORKS 5

ELE1280 INSTALLATION OF MCC PANEL ETC.

ELE1290 FLEXIBLE DROP WORKS FOR LIGHTING / ELV SERVICES ETC.

ELE1300 INSTALLATION OF SUSPENSION RODS FOR LIGHT FITTINGS

ELE1310 CABLE WIRE PULLING

ELE1320 EARTHING CABLING WORKS

ELE1330 INSTALLATION OF LIGHT FITTINGS

ELE1340 INSTALLATION OF SMALL POWER ACCESSORIES LIKE SWITCHES, SOCKETS,ISOLATORS


INSTALLATION OF FIRE FIGHTING EQUIPMENT SUCH AS FIRE ALARM ,SMOKE DETECTORS
ELE1350
EMERGENCY /EXIT LIGHTS & OTHER ACCESSORIES

ELE1360 LABELLING

EXT. PH WORKS 70

EPH1000 CONSTRUCTION OF SECONDARY SUBSTATION 10


EPH1010 PLINTH PROTECTION WORK 10

EPH1020 INTERLOCK PAVING TILE WORKS 10

EPH1030 WATER CONNECTION WORKS FROM THE EXISTING COLD WATER MAIN. 10

EPH1040 WATER DISTRIBUTION NETWORKS FOR DOMESTIC INSTALLATIONS. 10

EXCAVATE & INSTALL RCC MANHOLES , PITS & DUCTS FOR ELECTRIC CABLES, TELEPHONE,
EPH1050
WATER & DRAINAGE PIPING WORKS

EPH1060 DRAINAGE INSTALATION OF R.C.C HOLDING TANKS , AIR VENTS 10

HILL CUTTING & LEVELLING OF PLOT WITH GRADED EARTH MATERIAL SUB SEQUENT TO
EPH1070 10
PLINTH FILLING

DRAINAGE NETWORK FOR THE DOMESTIC SEWAGE TO BE CONSTRUCTED AND


EPH1080 10
CONNECTED TO EXISTING SEWER NETWORK.

STORM WATER/SURFACE RUN OFF DRAINS INCLUDING DISCHARGE INSTALLATIONS AT THE


EPH1090 10
PLOT LIMITS.

EPH1100 LABELING & IDENTIFICATION OF ALL INSTALLED ITEMS 5

EXT. ELE WORKS 70

INSTALLATION OF RMU, 11KV/0.433 TRANSFORMERS AND FEEDER PILLERS INCLUDING ALL


EW1010 15
NECESSARY CABLES AND TERMINATIONS.
ELECTRICAL CONNECTION WORKS BETWEEN THE ENTIRE EXISTING AND
EW1020
PROPOSED NETWORK.
TRANSFORMER IN ORDER TO COMPLETE THE RING MAIN AND ENSURE THE
EW1030
AVAILABILITY OF THE REQUIRED POWER.
ELECTRICAL CONNECTION WORKS BETWEEN ALL THE SUBSTATIONS AND THE
EW1040
LV PANELS INCLUDING ALL TERMINATION, CONNECTION, ETC.
ELECTRICAL DISTRIBUTION WORKS AMONG ALL THE LV PANELS, MAIN
EW1050
PANELS, DISTRIBUTION BOARDS, AND THE LIKE.
10 PAIR JELLY FILLED CABLE FROM THE EXISTING UTILITY NETWORK UP TO
EW1060 MAIN TELEPHONE DP BOX AND NECESSARY MODIFICATION/ALTERNATION OF 10
EXISTING INCOMING CABLE AS PER SITE CONDITION.
FIRE ALARM CONNECTION WORKS BETWEEN ALL THE BUILDING AND
EW1070 PROVISION OF SPARES/DUCTS FOR CABLING AND ALL OTHER TERMINATION, 10
CONNECTION, ETC.
EW1080 GAS DISTRIBUTION WORKS IN THE KITCHEN BUILDING.

EW1090 LABELING & IDENTIFICATION OF ALL INSTALLED ITEMS 10

FINAL TESTING & COMMISSIONING 64

TC1010 ALL MECHANICAL CONNECTIONS (PLUMBING,HVAC,FIRE FIGHTING) 8

TC1020 ALL ELECTRICAL CONNECTIONS (ELECTRIVAL , ELV, EARTHING,FIRE FIGHTING) 8


DEMOBILIZATION 64

DM1000 REMOVAL OF ALL THE TEMP. OFFICE AND OTHER ESTABLISHMENTS 10

DM1010 REMOVAL OF ALL SIGN BOARDS, BARRICADES AND OTHERS 5

DM1020 PREPARATION & SUBMISSION OF AS-BUILT DRAWINGS 10

DM1030 PREPARATION & SUBMISSION OF O & M MANUAL 10

DM1040 APPROVAL OF AS-BUILT DRAWINGS 14

DM1050 APPROVAL OF O & M MANUAL 14

DM1060 ISSUE COMPLETION CERTIFICATE 1

PROJECT CLOSEOUT 0

PC1000 PROJECT HANDOVER 0