MATERIAL TAKE-OFF LIST

REV.
DESCRIPTION QTY I/U DWG. CODE REMARKS
CODE

WALLS

EXTERIOR CMU WALL 5599.972 SM R

INTERIOR CMU WALL 1613.976 SM R

INTERIOR FIRE RATED CMU WALL 2HR 4297.228 SM R

INTERIOR FIRE RATED CMU WALL 1HR 408.72 SM R

DOUBLE SIDED GYPSUM BOARD PARTITION WALLS 1138.02 SM R

GLAZED PARTITION WALL 754.52 SM R

EXTERIOR FINISHES

EXTERIOR PAINT FINISH 1218.174 SM R

EXTERIOR METAL CLADDING 199.99 SM R

EXTERIOR TERRACOTTA FINISH 587.95 SM R

FABRIC VIRTICAL LOUVERS 44 EA R

FABRIC HORIZONTAL LOUVERS 62.916 SM R

LIGHTWEIGHT CANOPY STRUCTURE WITH CLADDING BY VENDOR 104.9 SM R

SKYLIGHTS

5900 X 1000 MM 2 SET R

7100 X 1000 1 SET R

NOTES:
Contractor shall verify quantities before construction with reference to design drawings and documents.

APPROVAL REFERENCE DRAWING


COMPILED BY REV.
CHECKED DATE PROJECT ENGR DATE
NZM 02G AHC 07/09/2020 DHH 07/09/2020 RR-ARC003 001 RR-ARC004 001
RR-ARC005 001 RR-ARC011 001
B.I. EWO PHASE ENG. ITEM AREA START-UP DATE PRELIMINARY REVISION
200 05/13/2020 FINAL x REVISION 02G
INDEX Materials for SHEET 1 OF 11
R PETROLEUM CONVERSION RESEARCH CENTER
PLANT MTOAR004
- SAUDI ARABIA
MATERIAL TAKE-OFF LIST

REV.
DESCRIPTION QTY I/U DWG. CODE REMARKS
CODE

SKYLIGHTS

5900 X 3925 MM 1 SET R

9870 X 3925 MM 1 SET R

6300 X 1000 1 SET R

CEILINGS

EXPOSED CONCRETE 4165.69 SM R

ACIDRESISTANT PAINT 176.4 SM R

ACCOUSTIC TILES 2639.55 SM R

GYPSUM BOARD 653.58 SM R

WALL FINISHES

PAINT 8852.15 SM R

WOODEN WALL COVERING 283.92 SM R

PORCELAIN MOSAIC TILES 1060.8 SM R

CURTAIN GLASS 1211.19 SM R

ACIDRESISTANT PAINT 511.836 SM R

NOTES:
Contractor shall verify quantities before construction with reference to design drawings and documents.

APPROVAL REFERENCE DRAWING


COMPILED BY REV.
CHECKED DATE PROJECT ENGR DATE
NZM 02G AHC 07/09/2020 DHH 07/09/2020 RR-ARC018 001 RR-ARC007 001
RR-ARC008 001 RR-ARC009 001
B.I. EWO PHASE ENG. ITEM AREA START-UP DATE PRELIMINARY REVISION
200 05/13/2020 FINAL x REVISION 02G
INDEX Materials for SHEET 2 OF 11
R PETROLEUM CONVERSION RESEARCH CENTER
PLANT MTOAR004
- SAUDI ARABIA
MATERIAL TAKE-OFF LIST

REV.
DESCRIPTION QTY I/U DWG. CODE REMARKS
CODE

FLOOR FINISH

E.P: EPOXY FLOORING 2744 SM R

R.T:RESILIENT FLOORING TILES 52 SM R

P.C.T:PORCELAIN/CERAMIC TILES 1339.8 SM R

C.T:CARPET ROLL 1651.2 SM R

A.R.P:ACID RESISTAND EPOXY PAINT 1824.6 SM R

WINDOWS

W1:12000X1300 MM HT FIXED SINGLE GLAZED 2 SET R

W2:11000X1300 MM HT FIXED SINGLE GLAZED 2 SET R

W3:5400X1300MM HT FIXED DOUBLE GLAZED 2 SET R

W4:4200X1300MM HT FIXED DOUBLE GLAZED 3 SET R

W5:2400X1300 MM HT FIXED DOUBLE GLAZED 1 SET R

W6:1000X2000 MM HT FIXED DOUBLE GLAZED 4 SET R

W7:2000X10600MM HT FIXED DOUBLE GLAZED 3 SET R

W8:14000X2100MM HT FIXED SINGLE GLAZED 1 SET R

W9:2400X1900MM HT METAL FRAME W/ METAL SHUTTER AUTO


2 SET R
OPENABLE EMERGANCY WINDOW

W10:1500X1300MM HT FIXED DOUBLE GLAZED 4 SET R

NOTES:
Contractor shall verify quantities before construction with reference to design drawings and documents.

APPROVAL REFERENCE DRAWING


COMPILED BY REV.
CHECKED DATE PROJECT ENGR DATE RR-ARC020 001
NZM 02G AHC 07/09/2020 DHH 07/09/2020 RR-ARC018 001 RR-ARC007 001
RR-ARC008 001 RR-ARC009 001
B.I. EWO PHASE ENG. ITEM AREA START-UP DATE PRELIMINARY REVISION
200 05/13/2020 FINAL x REVISION 02G
INDEX Materials for SHEET 3 OF 11
R PETROLEUM CONVERSION RESEARCH CENTER
PLANT MTOAR004
- SAUDI ARABIA
MATERIAL TAKE-OFF LIST

REV.
DESCRIPTION QTY I/U DWG. CODE REMARKS
CODE

DOORS

GD1:900X2200 MM HT ALUM. FRAME GLASS DOOR 2 SET R

GD2:1800X2200 MM HT ALUM. FRAME GLASS DOOR 3 SET R

GD3:900X2200 MM HT CLEAR GLASS DOOR 33 SET R

GD4:1800X2200 MM HT CLEAR GLASS DOOR FIRE RATED 2 SET R

GD5:900X2200 MM HT FIBER GLASS DOOR 2 SET R

HD1:900X2200 MM HT WOODEN VINYL HOLLOW METAL 4 SET R

HD2:1800X2200 MM HT WOODEN VINYL HOLLOW METAL 5 SET R

HD3:900X2200 MM HT WOODEN VINYL HOLLOW METAL 90 MIN FR 4 SET R

HD4:900X2200 MM HT WOODEN VINYL HOLLOW METAL 90 MIN FR 10 SET R

HD5:1800X2200 MM HT WOODEN VINYL HOLLOW METAL 90 MIN FR 17 SET R

HD6:1800X2200 MM HT WOODEN VINYL HOLLOW METAL 90 MIN FR 14 SET R

HD7:900X2200 MM HT WOODEN VINYL HOLLOW METAL 45 MIN FR 6 SET R

HD8:1100X2200 MM HT WOODEN VINYL HOLLOW METAL 90 MIN FR 3 SET R

WD1:900X2200 MM HTVINYL WOODEN DOOR AND FRAME 16 SET R

WD2:1800X2200 MM HTVINYL WOODEN DOOR AND FRAME 3 SET R

NOTES:
Contractor shall verify quantities before construction with reference to design drawings and documents.

APPROVAL REFERENCE DRAWING


COMPILED BY REV.
CHECKED DATE PROJECT ENGR DATE
NZM 02G AHC 07/09/2020 DHH 07/09/2020 RR-ARC019 001 RR-ARC007 001
RR-ARC008 001 RR-ARC009 001
B.I. EWO PHASE ENG. ITEM AREA START-UP DATE PRELIMINARY REVISION
200 05/13/2020 FINAL x REVISION 02G
INDEX Materials for SHEET 4 OF 11
R PETROLEUM CONVERSION RESEARCH CENTER
PLANT MTOAR004
- SAUDI ARABIA
MATERIAL TAKE-OFF LIST

REV.
DESCRIPTION QTY I/U DWG. CODE REMARKS
CODE

RD1:6000X6000 MM HT METAL ROLLUP DOOR 1 SET R

RD2:3500X3000 MM HT METAL ROLLUP DOOR 3 SET R

RD3:2500X3000MM HT METAL ROLLUP DOOR 7 SET R

RD4:3000X3000 MM HT METAL ROLLUP DOOR 5 SET R

PD1:900X2000 MM HT PHENOLIC DOOR 12 SET R

PD2:1200X2000 MM HT PHENOLIC DOOR 6 SET R

ELEVATORS

SERVISE ELEVATOR 1 EA R

ELEVATOR 2 EA R

SMALL ELEVATOR 1 EA R

NOTES:
Contractor shall verify quantities before construction with reference to design drawings and documents.

APPROVAL REFERENCE DRAWING


COMPILED BY REV.
CHECKED DATE PROJECT ENGR DATE
NZM 02G AHC 07/09/2020 DHH 07/09/2020 RR-ARC019 001 RR-ARC007 001
RR-ARC008 001 RR-ARC009 001
B.I. EWO PHASE ENG. ITEM AREA START-UP DATE PRELIMINARY REVISION
200 05/13/2020 FINAL x REVISION 02G
INDEX Materials for SHEET 5 OF 11
R PETROLEUM CONVERSION RESEARCH CENTER
PLANT MTOAR004
- SAUDI ARABIA
MATERIAL TAKE-OFF LIST

REV.
DESCRIPTION QTY I/U DWG. CODE REMARKS
CODE

ROOF

SINGLE PLY. 2MM REINFORCED PVC SINGLE MEMBRANE 2982.83 SM R

EXPOSED ROOFING WITH WHITE HIGH (SOLAR REFLECTANT

INDEX) SRI OF 111% FULLY ADHERED TO TAPERED

POLYSCYANURATE (ISO)- BOARD (RIGID CELL INSULATION -

BOOARD WITH MIN.THICKNESS OF 100MM MAINTAINED AT

LOW POINT) OVER SLOPPED-TO-DRAIN LIGHT WEIGH

SCREED,OVER STRUCTURAL CONCRETE DECK

ROOF DRAIN 21 EA R

SECONDARY ROOF DRAIN 21 EA R

NOTES:
Contractor shall verify quantities before construction with reference to design drawings and documents.

APPROVAL REFERENCE DRAWING


COMPILED BY REV.
CHECKED DATE PROJECT ENGR DATE
NZM 02G AHC 07/09/2020 DHH 07/09/2020 RR-ARC006 001

B.I. EWO PHASE ENG. ITEM AREA START-UP DATE PRELIMINARY REVISION
200 05/03/2020 FINAL x REVISION 02G
INDEX Materials for SHEET 6 OF 11
R PETROLEUM CONVERSION RESEARCH CENTER
PLANT MTOAR004
- SAUDI ARABIA
MATERIAL TAKE-OFF LIST

REV.
DESCRIPTION QTY I/U DWG. CODE REMARKS
CODE

FURNITURE

CH01:GUEST CHAIR WITH LOW BACK 51 EA R

CH02:OFFICE CHAIR ADJUSTABLE ARMS AND BACK 31 EA R

CH03:OFFICE GUEST CHAIR 83 EA R

CT:COUNTER TOP 1 EA R

D01:RECTANGULAR OFFICE DESK 31 EA R

LBS:LOW BOOK STORAGE 28 EA R

OCS:OFFICE CREDENZA STORAGE 31 EA R

PB:PLANTER 6 EA R

PS:PROJECTION SCREEN 5 EA R

SC:CORBU SOFA TABLE 10 EA R

PRT:MOVABLE PARTITION 1 EA R

PM:PRAYER MATT 170 EA R

T01:ROUND SOFA TABLE 5 EA R

T02:LOBBY ROUND TABLE 2 EA R

T03:HIGH SQUARE TABLE 19 EA R

NOTES:
Contractor shall verify quantities before construction with reference to design drawings and documents.

APPROVAL REFERENCE DRAWING


COMPILED BY REV.
CHECKED DATE PROJECT ENGR DATE
NZM 02G AHC 07/09/2020 DHH 07/09/2020 RN-ARC024 001 RN-ARC026 001
RN-ARC025 001
B.I. EWO PHASE ENG. ITEM AREA START-UP DATE PRELIMINARY REVISION
200 05/13/2020 FINAL x REVISION 02G
INDEX Materials for SHEET 7 OF 11
R PETROLEUM CONVERSION RESEARCH CENTER
PLANT MTOAR004
- SAUDI ARABIA
MATERIAL TAKE-OFF LIST

REV.
DESCRIPTION QTY I/U DWG. CODE REMARKS
CODE

T04:OFFICE ROUND TABLE FOR GUEST 36 EA R

CS:CURVED SOFA WITH HIGH BACK 2 EA R

MS:MOBILE STAND 4 EA R

CH06:LOUNGE CHAIR WITH LOW BACK 12 EA R

CH07:MANAGER MEETING CHAIR 18 EA R

CH08:MANAGER DESK CHAIR 6 EA R

CH11:MEETING CHAIR 40 EA R

MT01: SMALL ROUND MEETING TABLE 6 EA R

MT02: SMALL MEETING TABLE 2 EA R

MT03: BIG MEETING TABLE 2 EA R

RO:REECTANGLE OTTOMAN 2 EA R

RS:ROUND STOOL FOR IDEATION 13 EA R

SSC:OFFICE SHELVING STORAGE CABINET 28 EA R

T06:UNDER SOFA TABLE 12 EA R

T07:UNDER SOFA LAPTOP TABLE 4 EA R

WB01:SMALL WHITE BOARD 6 EA R

NOTES:
Contractor shall verify quantities before construction with reference to design drawings and documents.

APPROVAL REFERENCE DRAWING


COMPILED BY REV.
CHECKED DATE PROJECT ENGR DATE
NZM 02G AHC 07/09/2020 DHH 07/09/2020 RN-ARC024 001 RN-ARC026 001
RN-ARC025 001
B.I. EWO PHASE ENG. ITEM AREA START-UP DATE PRELIMINARY REVISION
200 05/13/2020 FINAL x REVISION 02G
INDEX Materials for SHEET 8 OF 11
R PETROLEUM CONVERSION RESEARCH CENTER
PLANT MTOAR004
- SAUDI ARABIA
MATERIAL TAKE-OFF LIST

REV.
DESCRIPTION QTY I/U DWG. CODE REMARKS
CODE

WB02:BIG WHITE BOARD 7 EA R

WD:WORKSTATION DESK 74 EA R

MD:MANAGER OFFICE DESK 6 EA R

MC:MANAGER OFFICE CABINET 6 EA R

CH04:ARMLESS ADJUSTABLE HEIGHT CHAIR 62 EA R

CH05:HIGH COUNTER STOOL 2 EA R

CH10:LAB DESK CHAIR 6 EA R

CH12:WORKSTATION ADJUSTABLE DESK CHAIR 20 EA R

LC:LOUNGE CHAIR 8 EA R

LD:LAB DESK 2 EA R

LT:LAB TABLE 2 EA R

RD:MAIN RECEPTION DESK 1 EA R

SC01:SEATING CUBE WIYHOUT BACK 1 EA R

SC02:SEATING CUBE WITH BACK 3 EA R

SC03:SEATING CUBE WITH CORNER BACK 1 EA R

SO01:CORBU TWO SEATER SOFA 4 EA R

NOTES:
Contractor shall verify quantities before construction with reference to design drawings and documents.

APPROVAL REFERENCE DRAWING


COMPILED BY REV.
CHECKED DATE PROJECT ENGR DATE
NZM 02G AHC 07/09/2020 DHH 07/09/2020 RN-ARC024 001 RN-ARC026 001
RN-ARC025 001
B.I. EWO PHASE ENG. ITEM AREA START-UP DATE PRELIMINARY REVISION
200 05/13/2020 FINAL x REVISION 02G
INDEX Materials for SHEET 9 OF 11
R PETROLEUM CONVERSION RESEARCH CENTER
PLANT MTOAR004
- SAUDI ARABIA
MATERIAL TAKE-OFF LIST

REV.
DESCRIPTION QTY I/U DWG. CODE REMARKS
CODE

SC04:FREE SEATING CUBE 2 EA R

T05:SMALL ROUND SIDE TABLE 4 EA R

LAB WORK BENCH: 2000MM x 600MM 77 EA R

LAB SHELF: 2000MM x 300MM 9 EA R

LAB PPE STORE CABINET 5 EA R

FIXTURES

WESTERN CLOSET 13 EA R

COAT HANGER 19 EA R

BIN 23 EA R

TOILET PAPER DISPENCER 19 EA R

SINK ON COUNTER TOP 15 EA R

JAN. SINK 3 EA R

ABLUTION CHAIRS 8 EA R

ABLUTION FAUCET 8 EA R

HANDICAP WESTERN CLOSET 6 EA R

PANTRY FLOOR FIXED KITCHEN CABINETS WITH COUNTER TOP 5 LM R

NOTES:
Contractor shall verify quantities before construction with reference to design drawings and documents.

APPROVAL REFERENCE DRAWING


COMPILED BY REV.
CHECKED DATE PROJECT ENGR DATE
NZM 02G AHC 07/09/2020 DHH 07/09/2020 RN-ARC024 001 RN-ARC026 001
RN-ARC025 001
B.I. EWO PHASE ENG. ITEM AREA START-UP DATE PRELIMINARY REVISION
200 05/13/2020 FINAL x REVISION 02G
INDEX Materials for SHEET 10 OF 11
R PETROLEUM CONVERSION RESEARCH CENTER
PLANT MTOAR004
- SAUDI ARABIA
MATERIAL TAKE-OFF LIST

REV.
DESCRIPTION QTY I/U DWG. CODE REMARKS
CODE

PANTRY WITH COUNTER TOP IN FIRST FLOOR LOBBY AS PER


2.19 LM R
VENDOR

KITCHEN SINK WITH FAUCET AND ACCESSORIES 2 SET R

LAB HAND BASIN WITH FAUCET AND ACCESSORIES 19 SET R

LAB SINK WITH FAUCET AND ACCESSORIES 19 SET R

LAB PPE STORE CABINET 5 EA R

EYE WASH 16 EA R

SAFETY SHOWER 8 EA R

LAB FUME CUPBOARD 1000MM X 3000MM 12 EA R

LAB FUME CUPBOARD 2000MM X 6000MM 1 EA R

NOTES:
Contractor shall verify quantities before construction with reference to design drawings and documents.

APPROVAL REFERENCE DRAWING


COMPILED BY REV.
CHECKED DATE PROJECT ENGR DATE
NZM 02G AHC 07/09/2020 DHH 07/09/2020 RN-ARC024 001 RN-ARC026 001
RN-ARC025 001
B.I. EWO PHASE ENG. ITEM AREA START-UP DATE PRELIMINARY REVISION
200 05/13/2020 FINAL x REVISION 02G
INDEX Materials for SHEET 11 OF 11
R PETROLEUM CONVERSION RESEARCH CENTER
PLANT MTOAR004