Download as xlsx, pdf, or txt
Download as xlsx, pdf, or txt
You are on page 1of 3479

SUB HEAD : 2.

EARTH WORK

Code Earth work in surface excavation not


Description Unit Quantity Rate Amount
exceeding 30 cm in depth but exceeding
1.5 m in width as well as 10 sqm on plan
2.1
including getting out and disposal of
excavated earth upto 50 m and lift upto 1.5
2.1.1
m, as directed by Engineer-in- Charge: All kinds of soil

Details of cost for 100 Sqm


LABOUR
17 Beldar day 6.8 350.00 2380.00
18 Coolie day 5.6 350.00 1960.00
TOTAL 4340.00
Add 1 % Water charges 43.4
4383.40
Add GST (multiplying factor 0.1405) 615.87
TOTAL 4999.27
Add 15 % Contractor's profit and
749.89
overheads
Total 5749.16
Add Cess @ 1% on 57.49
Cost of 100 sqm 5806.65
Cost of 1 sqm 58.07
Say
Earth work in rough excavation, banking excavated earth in layers not exceeding 20 cm in depth,58.10
breaking clods, watering, rolling each layer with ½ tonne roller or wooden or steel rammers, and
2.2 rolling every 3rd and top-most layer with power roller of minimum 8 tonnes and dressing up in
embankments for roads, flood banks, marginal banks and guide banks or filling up ground
2.2.1 depressions, lead upto 50 m and lift upto 1.5 m All
2.2.1 : kinds of soil

Details of cost for 10 cum.


LABOUR
17 Beldar day 5.9 350.00 2065.00
18 Coolie day 3.6 350.00 1260.00
11 Bhisti day 0.4 350.00 140.00
16 Chowkidar day 0.008 350.00 2.80
Roller charges (one roller does 1850 sqm.
of
consolidation per day)
3 Hire charges of Diesel Road Roller 8 to 10 day 0.008 3000 24.00
tonne
9999 Sundries L.S. 2.73 2.00 5.46
TOTAL 3497.26
Add 1 % Water charges 34.9726
TOTAL 3532.23
Add on (multiplying factor 0.1405) 496.28
TOTAL 4028.51
Add 15 % Contractor's profit and
604.28
overheads
Total 4632.79
Add Cess @ 1% on 46.33
Cost of 10 sqm 4679.12
Cost of 1 cum. 467.91
Say 467.90
2.3 Banking excavated earth in layers
not exceeding 20 cm in depth, breaking
clods, watering, rolling each layer with ½
tonne roller, or wooden or steel rammers,
and rolling every 3rd and top-most layer
with power roller of minimum 8 tonnes
and
m anddressing up,1.5
lift upto in mtr.
embankments
: for
2.3.1 roads, flood banks,
All kinds of soil marginal banks, and
guide banks etc., lead upto 50
Details of cost for 10 cum.
LABOUR
17 Beldar day 2.2 350.00 770.00
18 Coolie day 3.6 350.00 1260.00
11 Bhisti day 0.4 350.00 140.00
Roller charges (one roller does 1850 sqm.
of
consolidation per day)
3 Hire charges of Diesel Road Roller 8 to 10 day 0.008 3000 24.00
tonne
16 Chowkidar day 0.008 350.00 2.80
9999 Sundries L.S. 2.73 2 5.46
TOTAL 2202.26
Add 1 % Water charges 22.0226
TOTAL 2224.28
Add GST (multiplying factor 0.1405) 312.51
TOTAL 2536.79
Add 15 % Contractor's profit and
380.52
overheads
Total 2917.31
Add Cess @ 1% on 29.17
Cost of 10 sqm 2946.48
Cost of 1 cum. 294.65
Say 294.70
2.4 Deduct for not rolling with power
roller of minimum 8 tonnes for banking
excavated
earth in layers not exceeding 20 cm in
depth.
Details of cost for 10 cum.

LABOUR
16 Chowkidar day 0.008 350.00 2.80
3 Hire charges of Diesel Road Roller 8 to 10 day 0.008 3000 24.00
9999 Sundries L.S. 1.82 2 3.64
TOTAL 30.44
Add 1 % Water charges 0.3044
TOTAL 30.74
Add GST (multiplying factor 0.1405) 4.32
TOTAL 35.06
Add 15 % Contractor's profit and
5.26
overheads
Total 40.32
Add Cess @ 1% on 0.40
Cost of 10 sqm 40.72
Cost of 1 cum. 4.07
Say 4.10

2.5 Deduct for not watering the


excavated earth for banking
Details of cost for 10 cum.
LABOUR
0011 Bhisti day 0.4 350.00 140.00
TOTAL 140.00
Add 1 % Water charges 1.4
TOTAL 141.40
Add GST (multiplying factor 0.1405) 19.87
TOTAL 161.27
Add 15 % Contractor's profit and
24.19
overheads
Total 185.46
Add Cess @ 1% on 1.85
Cost of 10 sqm 187.31
Cost of 1 cum. 18.73
Say 18.70
2.6 Earth work in excavation by mechanical means (Hydraulic excavator)/manual means over
areas (exceeding 30 cm in depth, 1.5 m in width as well as 10 sqm on plan) including getting out and
disposalAll
2.6.1 of kinds
excavated earth lead upto 50 m and lift upto 1.5 m, as directed by Engineer-in-charge.
of soil

Details of cost for 10 cum.


Average output of Hydraulic Excavator
per
hour = 30cum.
MACHINERY
Hydraulic Excavator (3D) with driver and
20 day 0.041 7000 287.00
fuel.
18 Hire and running charges of loader. day 0.041 5000 205.00
LABOUR
28 Mate day 0.32 350.00 112.00
18 Coolie day 1.2 350.00 420.00
TOTAL 1024.00
Add 1 % Water charges 10.24
TOTAL 1034.24
Add GST (multiplying factor 0.1405) 145.31
TOTAL 1179.55
Add 15 % Contractor's profit and
176.93
overheads
Total 1356.48
Add Cess @ 1% on 13.56
Cost of 10 sqm 1370.04
Cost of 1 cum. 137.00
Say 137.00
2.7 Earth work in excavation by mechanical means (Hydraulic excavator)/manual means over
areas (exceeding 30 cm in depth, 1.5 m in width as well as 10 sqm on plan) including getting out and
disposal of excavated earth lead upto 50 m and lift upto 1.5 m,
as directed by Engineer-in-charge.
2.7.1 Ordinary rock
Details of cost for 10 cum.
MACHINERY
Hydraulic Excavator (3D) with driver and
20 day 0.063 7000 441.00
fuel.
17 Hire and running charges of tipper day 0.063 1700 107.10
32 Rock Excavator day 0.705 350.00 246.75
33 Rock Breaker day 1.59 350.00 556.50
34 Rock Hole Driller day 0.355 350.00 124.25
LABOUR 0.00
17 Beldar day 0.5 350.00 175.00
18 Coolie day 0.55 350.00 192.50
9999 Sundries L.S. 10.79 2 21.58
TOTAL 1864.68
Add 1 % Water charges 18.6468
TOTAL 1883.33
Add GST (multiplying factor 0.1405) 264.61
TOTAL 2147.94
Add 15 % Contractor's profit and
322.19
overheads
Total 2470.13
Add Cess @ 1% on 24.70
Cost of 10 sqm 2494.83
Cost of 1 cum. 249.48
Say 249.50

2.7.2 Hard rock (requiring blasting)

Details of cost for 10 cum.


MACHINERY
Hydraulic Excavator (3D) with driver and
20 day 0.125 7000 875.00
fuel.
17 Hire and running charges of tipper day 0.125 1700 212.50
32 Rock Excavator day 1.06 350.00 371.00
33 Rock Breaker day 2.825 350.00 988.75
34 Rock Hole Driller day 0.885 350.00 309.75
LABOUR
17 Beldar day 0.45 350.00 157.50
18 Coolie day 0.55 350.00 192.50
325 Blasting powder kilogram 3.93 40 157.20
326 Blasting fuse (fuse wire) each 4 15 60.00
9999 Sundries L.S. 16.12 2 32.24
TOTAL 3356.44
Add 1 % Water charges 33.5644
TOTAL 3390.00
Add GST (multiplying factor 0.1405) 476.30
TOTAL 3866.30
Add 15 % Contractor's profit and
579.95
overheads
Total 4446.25
Add Cess @ 1% on 44.46
Cost of 10 sqm 4490.71
Cost of 1 cum. 449.07
Say 449.10

2.7.3 Hard rock (blasting prohibited)

Details of cost for 10 cum.


MACHINERY
Hydraulic Excavator (3D) with driver and
20 day 0.125 7000 875.00
fuel.
17 Hire and running charges of tipper day 0.125 1700 212.50
32 Rock Excavator day 2.47 350.00 864.50
33 Rock Breaker day 6 350.00 2100.00
35 Stone Chiseller day 1.06 421.17 446.44
13 Blacksmith 2nd class day 0.175 403.67 70.64
17 Beldar day 0.75 350.00 262.50
18 Coolie day 1 350.00 350.00
9999 Sundries L.S. 16.12 2 32.24
TOTAL 5213.82
Add 1 % Water charges 52.1382
TOTAL 5265.96
Add GST (multiplying factor 0.1405) 739.87
TOTAL 6005.83
Add 15 % Contractor's profit and
900.87
overheads
Total 6906.70
Add Cess @ 1% on 69.07
Cost of 10 sqm 6975.77
Earth work in excavation by mechanical
Cost
meansof(Hydraulic
1 cum. excavator) / manual 697.58
Say
means in foundation trenches or drains (not 697.60
exceeding 1.5 m in width or 10 sqm on
2.8 plan), including dressing of sides and
ramming of bottoms, lift upto 1.5 m,
2.8.1 including
All kinds getting
of soil. out the excavated soil
and disposal of surplus excavated soil as
directed, within a lead of 50 m.
Details of cost for 10 cum.
MACHINERY
Hydraulic Excavator (3D) with driver and
20 day 0.04125 7000 288.75
fuel.
18 Hire and running charges of loader. day 0.04125 5000 206.25
LABOUR 0.00
28 Mate day 0.4 350.00 140.00
18 Coolie day 2.05 350.00 717.50
TOTAL 1352.50
Add 1 % Water charges 13.525
TOTAL 1366.03
Add GST (multiplying factor 0.1405) 191.93
TOTAL 1557.96
Add 15 % Contractor's profit and
233.69
overheads
Total 1791.65
Add Cess @ 1% on 17.92
Cost of 10 sqm 1809.57
Excavation work by mechanical means
Cost of 1 cum.
(Hydraulic excavator)/ manual means in 180.96
Say
foundation trenches or drains (not 181.00
exceeding 1.5m in width or 10 sqm on
2.9 plan), including dressing of sides and
ramming of bottoms, lift upto 1.5 m,
including
of 50 m. getting out the excavated soil
2.9.1 and disposal
Ordinary rockof surplus excavated soils as
directed, within a lead
Details of cost for 10 cum.
MACHINERY
Hydraulic Excavator (3D) with driver and
20 day 0.0625 7000 437.50
fuel.
17 Hire and running charges of tipper day 0.0625 1700 106.25
LABOUR 0.00
32 Rock Excavator day 0.885 350.00 309.75
33 Rock Breaker day 1.765 350.00 617.75
34 Rock Hole Driller day 0.53 350.00 185.50
17 Beldar day 0.5 350.00 175.00
18 Coolie day 1.3 350.00 455.00
9999 Sundries L.S. 13.52 2 27.04
TOTAL 2313.79
Add 1 % Water charges 23.1379
TOTAL 2336.93
Add GST (multiplying factor 0.1405) 328.34
TOTAL 2665.27
Add 15 % Contractor's profit and
399.79
overheads
Total 3065.06
Add Cess @ 1% on 30.65
Cost of 10 sqm 3095.71
Cost of 1 cum. 309.57
Say 309.60
2.9.2 Hard rock (requiring blasting)
Details of cost for 10 cum.
MACHINERY
Hydraulic Excavator (3D) with driver and
20 day 0.125 7000 875.00
fuel.
17 Hire and running charges of tipper day 0.125 1700 212.50
LABOUR 0.00
32 Rock Excavator day 1.24 350.00 434.00
33 Rock Breaker day 3 350.00 1050.00
34 Rock Hole Driller day 1.06 350.00 371.00
17 Beldar day 0.5 350.00 175.00
18 Coolie day 1.3 350.00 455.00
325 Blasting powder kilogram 6.42 40 256.80
326 Blasting fuse (fuse wire) each 7 15 105.00
9999 Sundries L.S. 18.85 2 37.70
TOTAL 3972.00
Add 1 % Water charges 39.72
TOTAL 4011.72
Add GST (multiplying factor 0.1405) 563.65
TOTAL 4575.37
Add 15 % Contractor's profit and
686.31
overheads
Total 5261.68
Add Cess @ 1% on 52.62
Cost of 10 sqm 5314.30
Cost of 1 cum. 531.43
Say 531.40

2.9.3 Hard rock (blasting prohibited)

Details of cost for 10 cum.


MACHINERY
Hydraulic Excavator (3D) with driver and
20 day 0.125 7000 875.00
fuel.
17 Hire and running charges of tipper day 0.125 1700 212.50
LABOUR 0.00
32 Rock Excavator day 2.65 350.00 927.50
33 Rock Breaker day 6.175 350.00 2161.25
35 Stone Chiseller day 1.06 421.17 446.44
13 Blacksmith 2nd class day 0.175 403.67 70.64
17 Beldar day 0.75 350.00 262.50
18 Coolie day 1.5 350.00 525.00
9999 Sundries L.S. 17.94 2 35.88
TOTAL 5516.71
Add 1 % Water charges 55.1671
TOTAL 5571.88
Add GST (multiplying factor 0.1405) 782.85
TOTAL 6354.73
Add 15 % Contractor's profit and
953.21
overheads
Total 7307.94
Add Cess @ 1% on 73.08
2.10
Cost of 10Excavating
sqm trenches of required 7381.02
width for pipes, cables, etc including
Cost of 1 cum.
excavation for sockets, and dressing of 738.1
Say
sides, ramming of bottoms, depth upto 1.5 738.10
m, including getting out the excavated soil,
and then returning the soil as required, in
layers not exceeding 20 cm in depth,
including
2.10.1 All consolidating each deposited
kinds of soil
layer by ramming, watering, etc. and
disposing
Pipes, of surplus
cables etc, notexcavated
exceedingsoil as
80 mm
2.10.1.1 directed,
Details ofwithin
dia. a lead
cost for 180moflength
50 m :of a pipe
trench
of an average dia. say 40mm.
Slope assumed 1 in 200.
Earth work and filling-
Minimum depth of trench 60cm.
Average depth = (0.6+1.5)/2 = 1.05
Width for this depth 0.45 cm
180x0.45x1.05 = 85.05 cum
Rate as per item no. 2.8.1 of SH: Earth
2.8.1 cum 85.05 180.96 15390.65
work
2.25 Rate as per Item Number 2.25 of SH: Earth cum 85.05 135.8 11549.79
Work
TOTAL 26940.44

Cost of 180m length of pipes trench 26940.44

Cost for 1m. length of pipe trench 149.67

Say 149.70

Pipes, cables etc. exceeding 80 mm dia.


2.10.1.2
but not exceeding 300 mm dia
Details of cost for 110m length of a pipe
trench of an average dia. say 200mm Slope
assumed
1 in 200.
Earth work and filling-
Minimum depth of trench = 0.75+0.20 =
0.95m
Average depth = (1.50+0.95)/2 = 1.225M
Width = 0.40 + 0.20 = 0.60 m
110x0.60x1.225 = 80.85 cum
5% for collars = 4.04 cum
Total = 84.89 cum
Rate as per item no. 2.8.1 of SH: Earth
2.8.1 cum 84.89 180.96 15361.69
work
2.25 Rate as per Item Number 2.25 of SH: Earth cum 84.89 135.8 11528.06

Work
TOTAL 26889.75

Cost of 110m length of pipe trench 26889.75

Cost for 1m length of pipe trench 244.45


Say 244.50

Pipes, cables etc. exceeding 300 mm dia


2.10.1.3
but not exceeding 600 mm
Details of cost for 60m length of a pipe of
an average dia. say 450mm.
Slope assumed 1 in 200. Earth work and
filling-
Minimum depth of trench 0.75+0.45=
1.20m Average depth = (1.50+1.20)/2 =
1.35
Width = 0.40 + 0.45 = 0.85 m
60x0.85x1.35 = 68.85 cum
5% for collars = 3.44 cum
Total = 72.29 cum
Rate as per item no. 2.8.1 of SH: Earth
2.8.1 cum 72.29 180.96 13081.60
work
2.25 Rate as per Item Number 2.25 of SH: Earth cum 72.29 135.8 9816.98
Work

Amount 22898.58

Cost of 60m length of pipe 22898.58

Cost for 1m length of pipe 381.64

Say 381.60

2.11 Extra for excavating trenches for


pipes, cables etc. in all kinds of soil for
depth exceeding 1.5 m, but not exceeding 3
m. (Rate is over corresponding basic item
for depth upto 1.5
metre).
Details of cost for 300m length of pipe of
an average dia. say 200mm (rate in
percentage) Slope assumed 1 in 200.
100x0.60x1.75 = 105.00 cum
200x0.60x2.00 =
240.00 cum.
Total = 345.00 cum.
Collars 5%= 17.25 cum.
Total = 362.25 cum.
Rate as per item no. 2.8.1 of SH: Earth
2.8.1 cum 362.25 180.96 65552.76
work
2.25 Rate as per Item Number 2.25 of cum 362.25 135.8 49193.55
SH: Earth Work
1/2x200x1.60x1 = 160 cum
Rate as per Item Number 2.6.1 of SH:
2.6.1 cum 160 137.00 21920.00
Earth
Work 21728.00
2.25 cum 160 135.8
Rate as per Item Number 2.25 of 0.00
SH: Earth Work
Extra for additional lift
1/2x200x0.60x1.50 = 135.00 cum Collars
5%=6.75 cum.
Total= 141.75 cum
Rate as per Item Number 2.26.1 of SH:
2.26.1 cum 141.75 51.51 7301.54
Earth
Work
Cost for 300 m. length of pipe 165695.85
Rate as per Item Number 2.10.1.2 of
2.10.1.2 metre -300 244.50 -73350.00
SH:Earth
Work
(Cost for 300 m. length of pipe upto 1.5 m 92345.85
depth)
Extra cost for 300 metre = Z = X - Y
Extra cost for one metre = Z/300 307.8195
Percentage increase over item no 2.10.1.2 126.81
#NAME?
Say
2.12 Extra for excavating trenches for 126.8
pipes, cables, etc, in all kinds of soil for
depth exceeding 3 m in depth, but not
exceeding 4.5 m. (Rate is over
corresponding basic
for depth upto 1.5 item
metre.)
Details of cost for a 100m length of a pipe
of
an average dia. say 200mm Slope assumed
1
in 200. Earth work and filling-
1x100x0.60x2 = 120 cum Collars 5% = 6
cum.
Total = 126 cum.
Rate as per item no. 2.8.1 of SH: Earth
2.8.1 cum 126 180.96 22800.96
work
Rate as per item No.2.25 of SH: Earth
2.25 cum 126 135.8 17110.80
work
Earth work
100x1.60x1.25 = 200 cum
Rate as per item no. 2.6.1 of SH: Earth
2.26.1 cum 200 137.00 27400.00
work
Rate as per item No.2.25 of SH: Earth
2.25 cum 200 135.8 27160.00
work
Extra for additional lift
1x100x0.60x1.50 = 90 cum.
2x0.50x100x0.60x0.50 = 30 cum.
Total = 120 cum.
Collars 5% = 6 cum. Total = 126 cum
Rate as per item no. 2.26.1 of SH: Earth
2.26.1 cum 126 51.51 6490.26
work
Cost for 100 m. length of pipe 100962.02
Rate as per Item Number 2.10.1.2 of SH:
2.10.1.2 metre -100 244.50 -24450.00
Earth
work
(Cost for 100 m. length of pipe upto 76512.02
1.5 m depth)
Extra cost for 100 metre = Z = X-Y
Extra cost for one metre = Z/100 765.1202
Excavating trenches over
Percentage increase of required
item nowidth for
2.10.1.2 315.51
pipes, cables, etc, including excavation for
sockets, depth upto 1.5 m, including #NAME?
Say
getting out the excavated materials,
returning the soil as required in layers not
2.13 exceeding 20 cm in depth, including
2.13.1 consolidating
Ordinary rockeach
: deposited layers by
ramming, watering etc., stacking
Pipes, cables
serviceable etc. not
material forexceeding 80 mm
measurements and
2.13.1.1
dia
disposal of unserviceable material as
directed,ofwithin
Details a lead
cost for 180 of
m 50 m: of a pipe
length
of a average dia. say 40mm.
Slope assumed 1:200
Excavation-

Quantity same as in item No.2.10.1.1

2.9.1 Rate as per Item Number 2.9.1 of cum 85.05 309.60 26331.48 A
SH: Earth Work
Refilling, ramming and watering
Rate as per item No.2.25 of SH: Earth
2.25 cum 85.05 135.8 11549.79 A
Work
Extra labour for ramming of rock
17 Beldar day 2 350.00 700.00
TOTAL 38581.27
Add 1 % Water charges except on (A) i.e.
700.00 7
on
TOTAL
Add GST (multiplying factor 0.1405) 707.00 99.33
TOTAL
Add 15 % Contractor's profit and
806.33 120.95
overheads
except on (A)
Total
Add Cess @ 1% on 927.28 9.27
Cost for 180 m. length of pipe 38817.82
Cost for 1m. length of pipe 215.65
Say 215.70

2.13.1.2 Pipes, cables etc. exceeding 80 mm dia but not exceeding 300 mm dia
Details of cost for 80 m length of pipe of
an
average dia. Say 200mm.
Slope assumed 1:200
Excavation-
Minimum depth of trench.
0.75+0.15+0.20 = 1.10m
Average depth = (1.10+1.50)/2 = 1.30m
Minimum width of trench = 0.90m
80x0.90x1.30 = 93.60 cum.
Rate as per item no. 2.9.1 of SH: Earth
2.9.1 cum 93.6 309.60 28978.56 A
Work
Refilling, ramming and watering
Rate as per item No.2.25 of SH: Earth
2.25 cum 93.6 135.8 12710.88 A
Work
Extra labour for ramming of rock
17 Beldar day 2.2 350.00 770.00
TOTAL 42459.44
Add 1 % Water charges i.e. except on (A) 770.00 7.7
TOTAL
Add GST (multiplying factor 0.1405) 777.70 109.27
TOTAL
Add 15 % Contractor's profit and
886.97 133.05
overheads
except on (A)
Total
Add Cess @ 1% on 1020.02 10.20
Cost for 80 m. length of pipe 42719.66
Cost for 1m. length of pipe 534
Say 534.00
2.13.1.3 Pipes, cables exceeding 300 mm dia but not exceeding 600 mm dia
Details of cost for 30 m. length of a pipe of
an
average dia. say 450mm.
Slope assumed 1 in 200.
Excavation-
Minimum depth of trench.
0.75+0.15+0.45 = 1.35m
Average depth = (1.35+1.50)/2 = 1.425m
Minimum width of trench = 0.90m
30x0.90x1.425 = 38.475 cum.
5% for collar = 1.924cum
Total = 40.399cum
Rate as per item no. 2.9.1 of SH: Earth
2.9.1 cum 40.399 309.60 12507.53 A
Work
Rate as per item No.2.25 of SH: Earth
2.25 cum 40.399 135.8 5486.18 A
Work
17 Beldar day 0.94 350.00 329.00
TOTAL 18322.71
Add 1 % Water charges i.e. eccepet on (A) 329.00 3.29
TOTAL
Add GST (multiplying factor 0.1405) 332.29 46.69
TOTAL
Add 15 % Contractor's profit and
378.98 56.85
overheads
except on (A)
Total
Add Cess @ 1% on 435.83 4.36
Cost for 30 m length of a pipe 18433.90
Cost for one m length of a pipe 614.46
Say 614.50

2.13.2 Hard rock (requiring blasting)

2.13.2.1 Pipes, cables etc. not exceeding 80 mm dia


Details of cost for 180 m length of a pipe
of a average dia. say 40mm.
Slope assumed 1:200 Excavation-

Quantity same as in item No.2.10.1.1


Rate as per item no. 2.9.2 of SH: Earth
2.9.2 cum 85.05 531.40 45195.57 A
Work
Refilling, ramming and watering
Rate as per item No.2.25 of SH: Earth
2.25 cum 85.05 135.8 11549.79 A
Work
Extra labour for ramming of rock
17 Beldar day 2.5 350.00 875.00 A
TOTAL 57620.36
Add 1 % Water charges i.e. eccepet on (A) 875.00 8.75
TOTAL
Add GST (multiplying factor 0.1405) 883.75 124.17
TOTAL
Add 15 % Contractor's profit and
1007.92 151.19
overheads
except on (A)
Total
Add Cess @ 1% on 1159.11 11.59
Cost for 180 m. length of pipe 57916.06
Cost for 1m. length of pipe 321.76
Say 321.80
2.13.2.2 Pipes, cables etc. exceeding 80 mm dia but not exceeding 300 mm dia
Details of cost for 80 m length of a pipe of
an
average dia. say 200mm.
Slope assumed 1:200
Excavation-
Quantity same as in item No.2.13.1.2
Rate as per item no. 2.9.2 of SH: Earth
2.9.2 cum 93.6 531.40 49739.04 A
Work
Refilling, ramming and watering 0.00
Rate as per item No.2.25 of SH: Earth
2.25 cum 93.6 135.8 12710.88 A
Work
Extra labour for ramming of rock 0.00
17 Beldar day 2.75 350.00 962.50
TOTAL 63412.42
Add 1 % Water charges i.e. eccepet on (A) 962.50 9.625
TOTAL
Add GST (multiplying factor 0.1405) 972.13 136.58
TOTAL
Add 15 % Contractor's profit and
1108.71 166.31
overheads
except on (A)
Total
Add Cess @ 1% on 1275.01 12.75
Cost for 80 m. length of pipe 63737.69
Cost for 1m. length of pipe 796.72
Say 796.70
2.13.2.3 Pipes, cables etc. exceeding 300 mm dia but not exceeding 600 mm dia
Details of cost for 30 m length of a pipe of
an
average dia. Say 450mm.

Slope assumed 1:200


Excavation-
Quantity same as in item No.2.13.1.3
Rate as per item no. 2.9.2 of SH: Earth
2.9.2 cum 40.399 531.40 21468.03 A
Work
Refilling, ramming and watering 0.00
Rate as per item No.2.25 of SH: Earth
2.25 cum 40.399 135.8 5486.18 A
Work
Extra labour for ramming of rock 0.00
17 Beldar day 1.17 350.00 409.50
TOTAL 27363.71
Add 1 % Water charges i.e. eccepet on (A) 409.50 4.095
TOTAL
Add GST (multiplying factor 0.1405) 413.60 58.11
TOTAL
Add 15 % Contractor's profit and
471.71 70.76
overheads
except on (A)
Total
Add Cess @ 1% on 542.47 5.42
Cost for 30 m. length of pipe 27502.09
Cost for 1m. length of pipe 916.74
Say 916.70

2.13.3 Hard rock (blasting prohibited)

2.13.3.1 Pipes, cables etc. not exceeding 80 mm dia


Details of cost for 180 m length of a pipe
of a average dia. say 40mm.
Slope assumed 1:200

Excavation-

Quantity same as in item No.2.10.1.1

2.9.3 Rate of item no 2.9.3 of SH: Earth Work cum 85.05 738.10 62775.41 A
Refilling, ramming and watering 0.00
Rate as per item No.2.25 of SH: Earth
2.25 cum 85.05 135.8 11549.79 A
Work
Extra labour for ramming of rock 0.00
17 Beldar day 2.5 350.00 875.00
TOTAL 75200.20
Add 1 % Water charges i.e. eccepet on (A) 875.00 8.75
TOTAL
Add GST (multiplying factor 0.1405) 883.75 124.17
TOTAL
Add 15 % Contractor's profit and
1007.92 151.19
overheads
Total
Add Cess @ 1% on
1159.11 11.59
Cost for 180 m. length of pipe 75495.90
Cost for 1m. length of pipe 419.42
Say 419.40
2.13.3.2 Pipes, cables etc. exceeding 80 mm dia but not exceeding 300 mm dia
Details of cost for 80 m length of a pipe of
an
average dia. say 200mm.
Slope assumed 1:200
Excavation-
Quantity same as in item No.2.13.1.2
Rate as per item no. 2.9.3 of SH: Earth
2.9.3 cum 93.6 738.10 69086.16 A
Work
Refilling, ramming and watering
Rate as per item No.2.25 of SH: Earth
2.25 cum 93.6 135.8 12710.88 A
Work
Extra labour for ramming of rock
17 Beldar day 2.75 350.00 962.50
TOTAL 82759.54
Add 1 % Water charges i.e. eccepet on (A) 962.50 9.625
TOTAL
Add GST (multiplying factor 0.1405) 972.13 136.58
TOTAL
Add 15 % Contractor's profit and
1108.71 166.31
overheads
except on (A)
Total
Add Cess @ 1% on 1275.01 12.75
Cost for 80 m. length of pipe 83084.81
Cost for 1m. length of pipe 1038.56
Say 1038.60
2.13.3.3 Pipes, cables etc. exceeding 300 mm dia but not exceeding 600 mm dia
Details of cost for 30 m length of a pipe of
an
average dia. Say 450mm.
Slope assumed 1:200
Excavation-
Quantity same as in item No.2.13.1.3
Rate as per item no. 2.9.3 of SH: Earth
2.9.3 cum 40.399 738.10 29818.50 A
Work
Refilling, ramming and watering
Rate as per item No.2.25 of SH: Earth
2.25 cum 40.399 135.8 5486.18 A
Work
Extra labour for ramming of rock
17 Beldar day 1.17 350.00 409.50
TOTAL 35714.18
Add 1 % Water charges i.e. eccepet on (A) 409.50 4.095
TOTAL
Add GST (multiplying factor 0.1405) 413.60 58.11
TOTAL
Add 15 % Contractor's profit and
471.71 70.76
overheads
except on (A)
Total
Add Cess @ 1% on 542.47 5.42
Cost for 30 m. length of pipe 35852.57
Cost for 1m. length of pipe 1195.09
Say
2.14 Extra for excavating trenches for 1195.10
pipes, cables, etc. in ordinary / hard rock
exceeding 1.5 m in depth but not
exceeding 3 m. (Rate is over corresponding
basic item for depth upto
1.5 metre)
Details of cost for 300m length of a pipe of
an
average dia. say 200mm. Slope assumed 1 in
200
Excavation-
100x0.90x1.50 = 157.50 cum.
200x0.90x20.00 = 360 cum.
Total = 517.50 cum.
Rate as per item no. 2.9.2 of SH: Earth
2.9.2 cum 517.5 531.40 274999.50 A
Work
0.50x200x1.90x1 = 190 cum.
Rate as per item no. 2.7.2 of SH: Earth
2.7.2 cum 190 449.10 85329.00 A
Work
Refilling, ramming and watering
517.50+190.00 = 707.50 cum.
Rate as per item No.2.25 of SH: Earth
2.25 cum 707.5 135.8 96078.50 A
Work
Extra for additional lift
0.5x300x0.9x1.5 = 202.50 cum.
Rate as per item no. 2.26.2 of SH: Earth
2.26.2 cum 202.5 100.70 20391.75 A
Work
Extra labour for ramming of rock
17 Beldar day 16.5 350.00 5775.00
TOTAL 482573.75
Add 1 % Water charges i.e. eccepet on (A) 5775.00 57.75
TOTAL
Add GST (multiplying factor 0.1405) 5832.75 819.50
TOTAL
Add 15 % Contractor's profit and
6652.25 997.84
overheads
except on (A)
Total
Add Cess @ 1% on 7650.09 76.50
Cost for 300m length of pipe 484525.34
Cost for 1m. length of pipe 1615.08
Say 1615.10

2.13.2.2 Rate as per Item No.2.13.2.2 of SH: Earth metre -300 796.70 -239010.00
Work
(cost of 300 m length of pipe upto 1.5m
245515.34
depth)
Extra cost for 300 m = X - Y
Extra cost for one m 818.38

Percentage increase over item 2.13.2.2 = 102.72


(Zx100)/Y
Say
2.15 Extra for excavating trenches for
pipes, cables, etc. in ordinary / hard rock
exceeding 3m in depth but not exceeding
4.5 m. (Rate is over corresponding basic
item for depth upto
1.5 metre)
Details of cost for 100m length of a pipe of
an
average dia. say 200mm. (rate in
percentage)
Slope assumed 1 in 200.
Max depth assumed 3.5m
Excavation-
100x0.90x2 = 180 cum.
Rate as per item no. 2.9.2 of SH: Earth
2.9.2 cum 180 531.40 95652.00 A
Work
100x1.90x1.25 = 237.5
Rate as per item no. 2.7.2 of SH: Earth
2.7.2 cum 237.5 449.10 106661.25 A
Work
Extra for additional lift
1x100x0.90x1.50 = 135
2x0.50x100x0.90x0.50
= 45 Total = 180 cum.
Rate as per item no. 2.26.2 of SH: Earth
2.26.2 cum 180 100.70 18126.00 A
Work
Refilling, ramming and watering
180+237.50 =
417.50 cum.
Rate as per item No.2.25 of SH: Earth
2.25 cum 417.5 135.8 56696.50 A
Work
Extra labour for ramming of rock
17 Beldar day 9.25 350.00 3237.50
TOTAL 280373.25
Add 1 % Water charges i.e. eccepet on (A) 3237.50 32.375
TOTAL
Add GST (multiplying factor 0.1405) 3269.88 459.42
TOTAL
Add 15 % Contractor's profit and
3729.30 559.39
overheads
except on (A)
Total
Add Cess @ 1% on 4288.69 42.89
Cost for 100m length of pipe 281467.33
2.13.2.2 Rate as per item No 2.13.2.2 of SH: Earth metre -100 796.70 -74975.17
Work
(cost of 100 m length of pipe exceeding 206492.16
1.5 m and upto 3 m depth)
Extra cost for 100 m = X - Y
Extra cost for 1 m 2064.92155
Percentage increase over item 2.13.2.2 = (Zx100)Y 259.18
Say 259.20
2.16 Close timbering in trenches
including strutting, shoring and packing
cavities (wherever required) complete.
(Measurements to be taken of the face area
timbered).
2.16.1 Depth not exceeding 1.5 m

Details of cost for a trench 30m long and


1.5m deep area 2x30x1.50=90
sqmMATERIAL
The Material can be used four times on the
same work and after use of material credit
is given @ 75% of cost
Poling boards of
1198 Second class kail wood in planks 10 cudm 21.375 260 5557.50
90x0.038 = 3.42 cum = 3420 cudm
Qty taken for cost of using once after
deducting for credit = 3420x¼x¼ = 213.75
dm³
Wallings l00mmx 100mm of
1197 Second class kail wood in scantling 10 cudm 7.5 260 1950.00
4x30x0.10x0.10 = 1.20cum= 1200 cudm
Qty
taken for cost of using once after deducting
for
credit = 1200x¼x¼ = 75 dm³
302 Safeda ballies 125 mm diameter and 1.5m metre 3.188 40 127.52
long
2x17x1.50 = 51m
Qty taken for cost of using once after
deducting for credit = 51x¼x¼ = 3.1875 m
CARRIAGE
Poling boards = 3.42 cum Walling 1.2
cum.
Balli struts: 3.14/4x(0.125)³x51 = 0.63 cum
Total of carriage = 5.25x¼ = 1.3125 cum.
2204 Carriage of Timber cum 1.3125 121.29 159.19
15 Carpenter 2nd class day 0.5 403.67 201.84
17 Beldar day 1 350.00 350.00
9999 Sundries L.S. 26.91 2 53.82
TOTAL 8399.87
Add 1 % Water charges 83.9987
TOTAL 8483.87
Add GST (multiplying factor 0.1405) 1191.98
TOTAL 9675.85
Add 15 % Contractor's profit and
1451.38
overheads
Total 11127.23
Add Cess @ 1% on 111.27
Cost of 90 Sqm. 11238.50
Cost per sqm. 124.87
Say 124.90

2.16.2 Depth exceeding 1.5 m but not


exceeding 3 m
Details of cost for a trench 30m long and
1.5m deep
Area 2x30x1.50=90 sqm

MATERIAL
The Material can be used four times on the
same work and after use of material credit
is
given @ 75% of cost
Poling boards of
1198 Second class kail wood in planks 10 cudm 21.375 260 5557.50
90x0.038 = 3.42 cum = 3420 cudm 0.00
Qty taken for cost of using once after 0.00
deducting for credit = 3420x¼x¼ = 213.75
0.00
dm³
Walings 100 mmx 100mm of 0.00
1197 Second class kail wood in scantling 10 cudm 7.5 260 1950.00
4x30x0.10x0.10 = 1.20cum = 1200 cudm
0.00
Qty
taken for cost of using once after deducting
0.00
for
credit = 1200x¼x¼ = 75 dm³ 0.00
302 Safeda ballies 125 mm diameter and 1.5m metre 3.1875 40 127.50
long
2x17x1.50 = 51m
Qty taken for cost of using once after
deducting for credit = 51x¼x¼ = 3.1875 m
CARRIAGE
Poling boards = 3.42 cum Walling= 1.20
cum.
Balli struts: 3.14/4x(0.125)³x51 = 0.63
cum
Total of carriage = 5.25x¼ = 1.3125 cum.
2204 Carriage of Timber cum 1.3125 121.29 159.19
15 Carpenter 2nd class day 0.75 403.67 302.75
17 Beldar day 2 350.00 700.00
9999 Sundries L.S. 40.43 2 80.86
TOTAL 8877.80
Add 1 % Water charges 88.778
TOTAL 8966.58
Add GST (multiplying factor 0.1405) 1259.80
TOTAL 10226.38
Add 15 % Contractor's profit and
1533.96
overheads
Total 11760.34
Add Cess @ 1% on 117.60
Cost of 90 Sqm. 11877.94
Cost per sqm. 131.98
Say 132.00

Depth exceeding 3 m but not exceeding 4.5


2.16.3
m
Details of cost for a trench 30m long and
1.5m deep
Area 2x30x1.5=90 sqmMATERIAL
The Material can be used four times on the
same work and after use of material credit
is givenboards
Poling @ 75% ofof cost
1198 Second class kail wood in planks 10 cudm 21.375 260 5557.50
90x0.038 = 3.42 cum = 3420 cudm
Qty taken for cost of using once after
deducting for credit = 3420x¼x¼ = 213.75
dm³
Wallings 100mmx 100mm of
1197 Second class kail wood in scantling 10 cudm 7.5 260 1950.00
4x30x0.10x0.10 = I.20cum = 1200 dm3
Qty
taken for cost of using once after deducting
for
credit = 1200x¼x¼ = 75 dm³
302 Safeda ballies 125 mm diameter and 1.5m metre 3.1875 40 127.50
long
2x17x1.5 = 51m
Qty taken for cost of using once after
deducting for credit = 51x¼x¼ = 3.1875 m
CARRIAGE
Poling boards = 3.42 cum Walling = 1.20
cum.
Balli struts: 3.14/4x(0.125)³x51 = 0.63
cum
Total of carriage = 5.25x¼ = 1.3125 cum.
2204 Carriage of Timber cum 1.3125 121.29 159.19
LABOUR
15 Carpenter 2nd class day 1.5 403.67 605.51
17 Beldar day 4 350.00 1400.00
9999 Sundries L.S. 80.73 2 161.46
TOTAL 9961.16
Add 1 % Water charges 99.6116
TOTAL 10060.77
Add GST (multiplying factor 0.1405) 1413.54
TOTAL 11474.31
Add 15 % Contractor's profit and
1721.15
overheads
Total 13195.46
Add Cess @ 1% on 131.95
Cost of 90 Sqm. 13327.41
Cost per sqm. 148.08
Say 148.10
2.17 Close timbering in case of shafts,
wells, cesspits, manholes and the like
including strutting,
(Measurements shoring
to be andthe
taken of packing
face area
cavities (wherever required) etc. complete.
timbered).
2.17.1 Depth not exceeding 1.5 m

Details of cost for a manhole 1.2m x 1.0m


x1.5m- Surface area: 2x(1.2+1.0)x1.5 =
6.6sqm
MATERIAL
The Material can be used four times on the
same work and after use of material credit
is given @ 75% of cost
Poling boards of
1198 Second class kail wood in planks 10 cudm 1.56875 260 407.88
6.60x0.038 = 0.251 cum = 251 cudm
Qty taken for cost of using once after
deducting for credit = 251x¼x¼ = 15.6875
dm³
Wallings 100mmx 100mm of
1197 Second class kail wood in scantling 10 cudm 0.5125 260 133.25
2x2x1.124x0.1x0.1 = 0.045 cum
2x2x0.924x0.1x0.1 = 0.037 cum.
Total Kail wood = 0.082 cum. = 82dm³
Qty
taken for cost of using once after deducting
for
credit = 82x¼x¼ = 5.125 dm³
302 Safeda ballies 125 mm diameter and 1.50m metre 0.4118 40 16.47
long 2x2x0.924 = 3.696
2x2x0.724 = 2.896
Total of balli = 6.592m
Qty taken for cost of using once after
deducting for credit = 6.592x¼x¼ =
0.4118m
2204 Carriage of Timber cum 0.1035 121.2915 12.55
CARRIAGE
0.251 cum 0.082
Poling boards = =
Walling cum.
Balli struts 3.14/4x(0.125)²x6.59 = 0.081 cum.
Total of carriage = 0.414 cum x¼ = 0.1035
cum
LABOUR
15 Carpenter 2nd class day 0.06 403.67 24.22
17 Beldar day 0.12 350.00 42.00
9999 Sundries L.S. 2.73 2 5.46
TOTAL 641.83
Add 1 % Water charges 6.4183
TOTAL 648.25
Add GST (multiplying factor 0.1405) 91.08
TOTAL 739.33
Add 15 % Contractor's profit and
110.90
overheads
Total 850.23
Add Cess @ 1% on 8.50
Cost of 6.6 sqm. 858.73
Cost per sqm. 130.11
Say 130.10

Depth exceeding 1.5 m but not exceeding 3


2.17.2
m
Details of cost for a manhole 1.2m x 1.0m
x1.5m- Surface area: 2x(1.2+1.0)x1.5 =
6.6sqm
MATERIAL
The Material can be used four times on the
same work and after use of material credit
is given @ 75% of cost
Poling boards of
1198 Second class kail wood in planks 10 cudm 1.56875 260 407.88
6.6x0.038 = 0.251 cum = 251 cudm
Qty taken for cost of using once after
deducting for credit = 251x¼x¼ = 15.6875
dm³
Walling of
1197 Second class kail wood in scantling 10 cudm 0.5125 260 133.25
2x2x1.124x0.1x0.1 = 0.045 cum
2x2x0.924x0.1x0.1 = 0.037 cum.
Total Kail wood = 0.082 cum. = 82dm³
Qty
taken for cost of using once after deducting
for
credit = 82x¼x¼ = 5.125 dm³
302 Safeda ballies 125 mm diameter and 1.5m metre 0.4118 40 16.47
long 2x2x0.924 = 3.696
2x2x0.724 = 2.896
Total of balli = 6.592m
Qty taken for cost of using once after
deducting for credit = 6.592x¼x¼ =
0.4118m
2204 Carriage of Timber cum 0.1035 121.2915 12.55
CARRIAGE
0.251 cum
Poling boards = =
Walling
0.082 cum.
Balli struts 3.14/4x(0.125)²x6.59 = 0.081
cum.
Total of carriage = 0.414 cum x¼ = 0.1035
cum
LABOUR
15 Carpenter 2nd class day 0.12 403.67 48.44
17 Beldar day 0.25 350.00 87.50
9999 Sundries L.S. 5.46 2 10.92
TOTAL 717.01
Add 1 % Water charges 7.1701
TOTAL 724.18
Add GST (multiplying factor 0.1405) 101.75
TOTAL 825.93
Add 15 % Contractor's profit and
123.89
overheads
Total 949.82
Add Cess @ 1% on 9.50
Cost of 6.6 sqm. 959.32
Cost per sqm. 145.35
Say 145.40

2.17.3 Depth exceeding 3 m but not


exceeding 4.5 m
Details of cost for a manhole 1.2m x 1.0m
x1.5m- Surface area: 2x(1.2+1.0)x1.5 =
6.6sqm
MATERIAL
The Material can be used four times on the
same work and after use of material credit
is
given @ 75% of cost
Poling boards of
1198 Second class kail wood in planks 10 cudm 1.56875 260 407.88
6.6x0.038 = 0.251 cum = 251 cudm
Qty taken for cost of using once after
deducting for credit = 251x¼x¼ = 15.6875
dm³
Walling of
1197 Second class kail wood in scantling 10 cudm 0.5125 260 133.25
2x2x1.124x0.10x0.10 = 0.045 cum
2x2x0.924x0.10x0.10 = 0.037 cum.
Total Kail wood= 0.082 cum. = 82dm³ Qty
taken for cost of using once after deducting
for
credit = 82x¼x¼ = 5.125 dm³
302 Safeda ballies 125 mm diameter and 1.50m metre 0.4118 40 16.47
long 2x2x0.924 = 3.696
2x2x0.724 = 2.896
Total of balli = 6.592m
Qty taken for cost of using once after
deducting for credit = 6.592x¼x¼ =
0.4118 m
2204 Carriage of Timber cum 0.1035 121.2915 12.55
CARRIAGE
0.251 cum 0.082
Poling boards = =
Balli struts 3.14/4x(0.125)²x6.59 = 0.081 Walling cum.
cum.
Total of carriage = 0.414 cum x¼ = 0.1035
cum
LABOUR
15 Carpenter 2nd class day 0.19 403.67 76.70
17 Beldar day 0.38 350.00 133.00
9999 Sundries L.S. 8.06 2 16.12
TOTAL 795.97
Add 1 % Water charges 7.9597
TOTAL 803.93
Add GST (multiplying factor 0.1405) 112.95
TOTAL 916.88
Add 15 % Contractor's profit and
137.53
overheads
Total 1054.41
Add Cess @ 1% on 10.54
Cost of 6.6 sqm. 1064.95
Cost per sqm. 161.36
Say
2.18 Close timbering over areas 161.40
including strutting, shoring and packing
cavities (wherever required) etc. complete.
(Measurements to be taken of the face area
timbered):
2.18.1 Depth not exceeding 1.5 m
Details of cost for an area 30m long and
1.50m
deep-Area -30x1.5m = 45 sqm.
MATERIAL
The Material can be used four times on the
same work and after use of material credit
is given @ 75% of cost
Poling boards of
1198 Second class kail wood in planks 10 cudm 10.688 260 2778.88
250x38mm : 45x0.038 = 1.71 cum = 1710
cudm
Qty taken for cost of using once after
deducting for credit = 1710x¼x¼ =
106.875 dm³
Wallings l00mmx 100mm of
1197 Second class kail wood in scantling 10 cudm 1.875 260 487.50
100x100mm : 30x0.10x0.10 = 0.30cum =
300 cudm
Qty taken for cost of using once after
deducting for credit = 300x¼x¼ = 18.75
dm³
Raking struts
302 Safeda ballies 125 mm diameter metre 1.59 40 63.60
Qty taken for cost of using once after
deducting for credit = 25.5x¼x¼ = 1.59 m
2204 Carriage of Timber cum 0.581 121.2915 70.47
CARRIAGE
Poling boards = 1.71 cum
= 0.30
Walling
cum
Raking struts 3.14/4x(0.125)² = 0.313 cum
Total of carriage = 2.323 cum x¼ = 0.581
cum
LABOUR
15 Carpenter 2nd class day 0.25 403.67 100.92
17 Beldar day 0.5 350.00 175.00
9999 Sundries L.S. 31.46 2 62.92
TOTAL 3739.29
Add 1 % Water charges 37.3929
TOTAL 3776.68
Add GST (multiplying factor 0.1405) 530.62
TOTAL 4307.30
Add 15 % Contractor's profit and overheads 646.10
Total 4953.40
Add Cess @ 1% on 49.53
Cost of 45 Sqm. 5002.93
Cost per sqm. 111.18
Say 111.20

2.18.2 Depth exceeding 1.5 m but not


exceeding
Details 3 m for an area 30m long and
of cost
1.5m
deep-Area -30x1.5m = 45 sqm.
MATERIAL
The Material can be used four times on the
same work and after use of material credit
is
given @ 75% of cost
Poling boards of
1198 Second class kail wood in planks 10 cudm 10.6875 260 2778.75
250x38mm : 45x0.038 = 1.71 cum =1710
cudm
Qty taken for cost of using once after
deducting for credit = 1710x¼x¼ =
106.875 dm³
Walling of
1197 Second class kail wood in scantling 10 cudm 1.875 260 487.50
100x100mm : 30x0.10x0.10 =
0.30cum = 300 cudm
Qty taken for cost of using once after
deducting for credit = 300x¼x¼ = 18.75
dm³
Raking struts
302 Safeda ballies 125 mm diameter metre 1.59 40 63.60
17 x 1.5 = 25.5m
Qty taken for cost of using once after
deducting for credit = 25.5x¼x¼ = 1.59 m
2204 Carriage of Timber cum 0.581 121.2915 70.47
CARRIAGE
Poling boards = 1.71 cum Walling = 0.30
cum.
Raking struts 3.14/4x(0.125)² = 0.313 cum
Total of carriage = 2.323 cum x¼
= 0.581 cum
LABOUR
15 Carpenter 2nd class Day 0.5 403.67 201.84
17 Beldar Day 1 350.00 350.00
9999 Sundries L.S. 34.06 2 68.12
TOTAL 4020.28
Add 1 % Water charges 40.2028
TOTAL 4060.48
Add GST (multiplying factor 0.1405) 570.50
TOTAL 4630.98
Add 15 % Contractor's profit and
694.65
overheads
Total 5325.63
Add Cess @ 1% on 53.26
Cost of 45 Sqm. 5378.89
Cost per sqm. 119.53
Say 119.50
2.18.3 Depth exceeding 3 m but not
exceeding 4.5 m
Details of cost for an area 30m long and 1.5m
deep-Area -30x1.5m = 45 sqm.
MATERIAL
The Material can be used four times on the
same work and after use of material credit
is given @ 75% of cost
Poling boards of
1198 Second class kail wood in planks 10 cudm 10.6875 260 2778.75
250x38mm : 45x0.038 =
1.71 cum = 1710 cudm
Qty taken for cost of using once after
deducting for credit = 1710x¼x¼ =
106.875 dm³ Walling of
1197 Second class kail wood in scantling 10 cudm 1.875 260 487.50
100x100mm : 30x0.10x0.10 =
0.30cum = 300 cudm
Qty taken for cost of using once after
deducting for credit = 300x¼x¼ = 18.75 dm³
Raking struts
and 1.5m
302 Safeda ballies 125 mm diameter 1.59 40 63.60
metre
long 17 x 1.50 = 25.5m
Qty taken for cost of using once after
deducting for credit = 25.5x¼x¼ = 1.59 m
2204 Carriage of Timber cum 0.581 121.29 70.47
CARRIAGE
Poling boards = 1.71 cum Walling 0.3
cum.
Raking struts 3.14/4x(0.125)² = 0.313 cum
Total of carriage = 2.323 cum x¼ = 0.581 cum
LABOUR
15 Carpenter 2nd class day 0.75 403.67 302.75
17 Beldar day 1.5 350.00 525.00
9999 Sundries L.S. 47.58 2 95.16
TOTAL 4323.23
Add 1 % Water charges 43.2323
TOTAL 4366.46
Add GST (multiplying factor 0.1405) 613.49
TOTAL 4979.95
Add 15 % Contractor's profit and overheads 746.99
Total 5726.94
Add Cess @ 1% on 57.27
Cost of 45 Sqm. 5784.21
Cost per sqm. 128.54
Say 128.50

Extra for planking, strutting and packing


materials for cavities (in close timbering) if
required to be left permanently in position.
(Face area of timber permanently left to be
measured).
2.19
Details of cost for a trench 30m long and
1.5m deep area 2x30x1.5=90
sqmMATERIAL
Poling boards of
1198 Second class kail wood in planks 10 cudm 299.25 260 77805.00
90x0.038 = 3.42 cum = 3420 cudm
Less @ 1/8 of Qty as timber is supposed to
be
used once before = 3420 - 427.5 =
2992.5 dm ³
Walings 100mmx100mm of
1197 Second class kail wood in scantling 10 cudm 105 260 27300.00
4x30x0.10x0.10 = 1.20cum = 1200 cudm
Less @ 1/8 of Qty as timber is supposed to
be
used once before = 1200 - 150 =
1050 dm ³ Struts of
302 Safeda ballies 125 mm diameter and 1.5m metre 44.63 40 1785.20
long
2x17x1.5 = 51m
Less @ 1/8 of Qty as timber is supposed to
be
used once before = 51 - 6.37 = 44.63 m
2204 Carriage of Timber cum 2.68 121.2915 325.06
Poling boards = 3.42 cum Walling= 1.20
cum.
Balli struts: 3.14/4x(0.125) ² x 51 = 0.63
cum
= 5.25 cum Taking half = 5.25 x ½ = 2.675
cum
TOTAL 107215.26
Add 1 % Water charges 1072.1526
TOTAL 108287.41
Add GST (multiplying factor 0.1405) 15214.38
TOTAL 123501.79
Add 15 % Contractor's profit and
18525.27
overheads
Total 142027.06
Add Cess @ 1% on 1420.27
Cost of 90 Sqm. 143447.33
Cost per sqm. 1593.86
Say 1593.90
2.20 Open timbering in trenches
including strutting and shoring complete
(measurements to
be taken of the face area timbered):

2.20.1 Depth not exceeding 1.5 m


Details of cost for a trench of length 30m
and 1.50m deep surface area - 2x30x1.5 =
90 sqm.
MATERIAL
The Material can be used four times on the
same work and after use of material credit
is given @ 75% of cost
Poling board of
1198 Second class kail wood in planks 10 cudm 7.125 260 1852.50
1.5mx0.25x0.038m
2x40x1.5x0.25x0.038= 1.14cum = 1140
cudm
Qty taken for cost of using once after
deducting for credit = 1140x¼x¼ = 71.25
cudm
1197 Second class kail wood in scantling 10 cudm 7.5 260 1950.00
Walling l00mmxl00mm :
4x30mx0.l0mx0.l0m
= 1.20cum= 1200 cudm
Qty taken for cost of using once after
deducting for credit = 1200x¼x¼ = 75 dm³
Struts of
302 Safeda ballies 125 mm diameter and 1.5m metre 3.18 40 127.20
long
2x17x1.50 = 51m
Qty taken for cost of using once after
deducting for credit = 51x¼x¼ = 3.18 m
2204 Carriage of Timber cum 0.74 121.2915 89.76
CARRIAGE:
Poling boards = 1.14 cum
= 1.20
Walling
cum
Ballies struts 3.14/4x(0.125) ² = 0.63 cum
Total of carriage = 2.97 cum x ¼ = 0.74
LABOUR
15 Carpenter 2nd class day 0.25 403.67 100.92
17 Beldar day 0.5 350.00 175.00
9999 Sundries L.S. 19.76 2 39.52
TOTAL 4334.90
Add 1 % Water charges 43.349
TOTAL (multiplyi 4378.25
Add GST ng factor 615.14
TOTAL 0.1405) 4993.39
Add 15 % Contractor's profit and
749.01
overheads
Total 5742.40
Add Cess @ 1% on 57.42
Cost of 90 Sqm 5799.82
Cost per sqm. 64.44
Say 64.40
Depth exceeding 1.5 m but not exceeding 3
2.20.2
m
Details of cost for a trench of length 30m
and 1.5m deep surface area - 2x30x1.5 =
90 sqm.
MATERIAL
The Material can be used four times on the
same work and after use of material credit
is
given @ 75% of cost
Poling boards of
1198 Second class kail wood in planks 10 cudm 7.125 260 1852.5
1.50mx0.25x0.038m 2x40x1.50x0.25x
0.038= 1.14cum= 1140 cudm
Qty taken for cost of using once after
deducting for credit = 1140x¼x¼ = 71.25
dm³
Wallings of
1197 Second class kail wood in scantling 10 cudm 7.5 260 1950
100mmx 100mm: 4x30mx0.l0mx0.l0m
= 1.20cum= 1200 cudm
Qty taken for cost of using once after
deducting for credit = 1200x¼x¼ = 75 dm³
Struts of
302 Safeda ballies 125 mm diameter and 1.5m metre 3.18 40 127.2
long
2x17x1.5 = 51m
Qty taken for cost of using once after
deducting for credit = 51x¼x¼ = 3.18 m
2204 Carriage of Timber cum 0.74 121.2915 89.76
CARRIAGE:
Poling boards = 1.14 cum
= 1.20
Walling
cum
Ballies struts 3.14/4x(0.125) ² = 0.63 cum
Total of carriage = 2.97 cum x ¼ = 0.74
LABOUR
15 Carpenter 2nd class day 0.5 403.67 187.25
17 Beldar day 1 350.00 350.00
9999 Sundries L.S. 33.15 2 66.3
TOTAL 4593.84
Add 1 % Water charges 45.94
TOTAL (multiplyi 4639.77
Add GST ng factor 651.89
TOTAL 0.1405) 5291.66
Add 15 % Contractor's profit and overheads 793.75
Total 6085.41
Add Cess @ 1% on 60.85
Cost of 90 Sqm 6146.27
Cost per sqm. 68.29
Say 68.3
Depth exceeding 3 m but not exceeding 4.5
2.20.3
m
Details of cost for a trench of length 30m
and 1.5m deep surface area - 2x30x1.5 =
90 sqm.
MATERIAL
The Material can be used four times on the
same work and after use of material credit
is given @ 75% of cost
Poling boards of
1198 Second class kail wood in planks 10 cudm 7.125 260 1852.5
1.50mx0.25x0.038m :
2x40x1.5x0.25x0.038= 1.14 cum =
1140 cudm
Qty taken for cost of using once after
deducting for credit = 1140x¼x¼ = 71.25
dm³
Wallings of
1197 Second class kail wood in scantling 10 cudm 7.5 260 1950
l00mmxl00mm : 4x30mx0.lmx0.lm
= 1.20cum= 1200 cudm
Qty taken for cost of using once after
deducting for credit = 1200x¼x¼ = 75 dm³
Struts of
302 Safeda ballies 125 mm diameter and 1.5m metre 3.18 40 127.2
long
2x17x1.5 = 51m
Qty taken for cost of using once after
deducting for credit = 51x¼x¼ = 3.18 m
2204 Carriage of Timber cum 0.74 121.2915 89.76
CARRIAGE:
Poling boards = 1.14 cum
= 1.20
Walling
cum
Ballies struts 3.14/4x(0.125) ² = 0.63 cum
Total of carriage = 2.97 cum x ¼ = 0.74
LABOUR
15 Carpenter 2nd class day 1 403.67 403.67
17 Beldar day 1.75 350.00 561.45
9999 Sundries L.S. 46.67 2 93.34
TOTAL 5048.75
Add 1 % Water charges 50.49
TOTAL (multiplyi 5099.24
Add GST ng factor 716.44
TOTAL 0.1405) 5815.68
Add 15 % Contractor's profit and
872.35
overheads
Total 6688.03
Add Cess @ 1% on 66.88
Cost of 90 Sqm 6754.91
Cost per sqm. 75.05
Say
Open timbering in case of shafts, wells, 75.05
cesspits, manholes and the like including
2.21 strutting and shoring complete
(Measurements to be taken of the face area
2.21.1 timbered):
Depth not exceeding 1.5 m
Details of cost for a manhole 1.2x 1m x
1.5m -
Surface area 2(1.2+1.0)x1.5 = 6.6 sqm
MATERIAL
The Material can be used four times on the
same work and after use of material credit
is given @ 75% of cost
Polling boards of
1198 Second class kail wood in planks 10 cudm 0.5375 260 139.75
250mm wide and 38mm thick
6x0.25xl.5x0.038 = 0.086 cum = 86cudm
Qty
taken for cost of using once after deducting
for
credit = 86x¼x¼ = 5.3755 dm³
Walling l00mmxl00mm of
1197 Second class kail wood in scantling 10 cudm 0.3 260 78
4x1.2x0.1x0.1 = 0.048 cum = 48 dm³
Qty taken for cost of using once after
deducting for credit = 486x¼x¼ = 3 dm³
Struts
of
302 metre 0.4 40
Safeda ballies 125 mm diameter 16
(4x1.0=4.0)+(2x1.2=2.4) = 6.4m
Qty taken for cost of using once after
deducting for credit = 6.4x¼x¼ = 0.4 m
2204 Carriage of Timber CARRIAGE : cum 0.053 121.2915 6.43
Poling boards = 0.086 cum
= 0.048
Walling
cum
Ballies struts 3.14/4x(0.125) ² x 6.4
= 0.079 cum
Total of carriage = 0.213 cum x¼ = 0.053
cum
LABOUR
15 Carpenter 2nd class day 0.03 403.67 11.24
17 Beldar day 0.06 350.00 19.25
9999 Sundries L.S. 1.82 2 3.64
TOTAL 274.3
Add 1 % Water charges 2.74
TOTAL (multiplyi 277.05
Add GST ng factor 38.93
TOTAL 0.1405) 315.97
Add 15 % Contractor's profit and
47.4
overheads
Total 363.37
Add Cess @ 1% on 3.63
Cost of 6.6 sqm. 367
Cost per sqm. 55.61
Say 55.6
Depth exceeding 1.5 m but not exceeding
2.21.2
3m
Details of cost for a manhole 1.2x 1m x
1.5m - Surface area 2(1.2+1.0)x1.5 = 6.6
sqm
MATERIAL
The Material can be used four times on the
same work and after use of material credit
is
given @ 75% of cost
Polling boards of
Second class kail wood in planks 250mm
1198 10 cudm 0.5375 260 139.75
wide
and 38mm thick :
6x0.25x1.50x0.038 = 0.086 cum = 86cudm
Qty
taken for cost of using once after deducting
for
credit = 86x¼x¼ = 5.3755 dm³
Walling 100mmxl00mm of
1197 Second class kail wood in scantling 10 cudm 0.3 260 78
4x1.20x0.10x0.10 = 0.048 cum = 48 dm³
Qty
taken for cost of using once after deducting
for
credit = 486x¼x¼ = 3 dm³ Struts of
302 Safeda ballies 125 mm diameter metre 0.4 40 16
(4x1.00=4.00)+(2x1.20=2.40) = 6.40m
Qty
taken for cost of using once after deducting
for
credit = 6.40x¼x¼ = 0.40 m
2204 Carriage of Timber CARRIAGE : cum 0.053 121.29 6.43
Poling boards = 0.086 cum
Walling = 0.048 cum
Ballies struts 3.14/4x(0.125) ² x 6.40
= 0.079 cum
Total of carriage = 0.213 cum x¼
= 0.053 cum LABOUR
0015 Carpenter 2nd class day 0.06 403.67 22.47
17 Beldar day 0.12 350.00 38.5
9999 Sundries L.S. 2.73 2 5.46
TOTAL 306.61
Add 1 % Water charges 3.07
TOTAL 309.67
Add GST (multiplying factor 0.1405) 43.51
TOTAL 353.18
Add 15 % Contractor's profit and
52.98
overheads
Total 406.16
Add Cess @ 1% on 4.06
Cost of 6.6 sqm. 410.22
Cost per sqm. 62.15
Say 62.15
Depth exceeding 3 m but not exceeding 4.5
2.21.3
m
Details of cost for a manhole 1.2x 1m x
1.5m - Surface area 2(1.20+1.00)x1.50 =
6.60
sqm
MATERIAL
The Material can be used four times on the
same work and after use of material credit
is given @ 75% of cost Polling boards of
Second class kail wood in planks 250mm
1198 10 cudm 0.5375 260 139.75
wide
and 38mm thick :
6x0.25x1.50x0.038 = 0.086 cum = 86cudm
Qty
taken for cost of using once after deducting
for
credit = 86x¼x¼ = 5.3755 dm³
Walling 100mmxl00mm of
1197 Second class kail wood in scantling 10 cudm 0.3 260 78
4x1.2x0.10x0.10 = 0.048 cum = 48 dm³
Qty
taken for cost of using once after deducting
for
credit = 486x¼x¼ = 3 dm³ Struts of
302 Safeda ballies 125 mm diameter metre 0.4 40 16
(4x1.0=4.0)+(2x1.2=2.4) = 6.4m Qty taken
for
cost of using once after deducting for
credit =
6.4x¼x¼ = 0.4 m
2204 Carriage of Timber CARRIAGE : cum 0.053 121.29 6.43
Poling boards = 0.086 cum
= 0.048
Walling
cum
Ballies struts 3.14/4x(0.125) ² x 6.4 =
0.079 cum
Total of carriage = 0.213 cum x¼ =
0.053 cum
LABOUR
15 Carpenter 2nd class day 0.1 403.67 37.45
17 Beldar day 0.2 350.00 64.17
9999 Sundries L.S. 3.64 2 7.28
TOTAL 349.07
Add 1 % Water charges 3.49
TOTAL 352.57
Add GST (multiplying factor 0.1405) 49.54
TOTAL 402.1
Add 15 % Contractor's profit and
60.32
overheads
Total 462.42
Add Cess @ 1% on 4.62
Cost of 6.6 sqm. 467.04
Cost per sqm. 70.76
Say 70.75

Open timbering over areas including


strutting, shoring etc. complete.
2.22
(Measurements to be taken of the face area
timbered):
2.22.1 Depth not exceeding 1.5 m
Details of cost for an area 30m long and
1.5m
deep area = 30 x 1.5 = 45 sqm.
MATERIAL
The Material can be used four times on the
same work and after use of material credit
is
given @ 75% of cost
Polling boards of
1198 Second class kail wood in planks 10 cudm 3.5625 260 926.25
250mm x 38mm
40x1.50x0.25x0.038 = 0.57cum. = 570
dm³
Qty taken for cost of using once after
deducting for credit = 570x¼x¼ = 35.625
dm³
Raking struts-
302 Safeda ballies 125 mm diameter metre 3.75 40 150
40x1.50 = 60m
Qty taken for cost of using once after
deducting for credit = 60x¼x¼ = 3.75 m
2204 Carriage of Timber CARRIAGE : cum 0.328 121.29 39.72
Poling boards = 0.57 cum
Ballies 40x1.5x3.14/4x0.125² = 0.4 cum.
Total for carriage = 1.31 cum x ¼ =
0.3275 cum
LABOUR
15 Carpenter 2nd class day 0.12 403.67 44.94
17 Beldar day 0.25 350.00 80.21
9999 Sundries L.S. 19.76 2 39.52
TOTAL 1280.64
Add 1 % Water charges 12.81
TOTAL 1293.45
Add GST (multiplying factor 0.1405) 181.73
TOTAL 1475.18
Add 15 % Contractor's profit and
221.28
overheads
Total 1696.45
Add Cess @ 1% on 16.96
Cost of 45 sqm. 1713.42
Cost per sqm. 38.08
Say 38.1

Depth exceeding 1.5 m but not exceeding


2.22.2
3m
Details of cost for an area 30m long and
1.5m
deep area = 30 x 1.5 = 45 sqm.
MATERIAL
The Material can be used four times on the
same work and after use of material credit
is
given @ 75% of cost
Polling boards of
10 cudm
1198 Second class kail wood in planks 260 926.25
3.5625
250mm x 38mm
40x1.50x0.25x0.038 = 0.57cum. = 570
dm³
Qty taken for cost of using once after
deducting for credit = 570x¼x¼ = 35.625
dm³
Raking struts-
302 Safeda ballies 125 mm diameter metre 3.75 40 150
40x1.50 = 60m
Qty taken for cost of using once after
deducting for credit = 60x¼x¼ = 3.75 m
2204 Carriage of Timber CARRIAGE : cum 0.328 121.29 39.72
Poling boards = 0.57 cum
Ballies 40x1.50x3.14/4x0.125² = 0.4 cum.
Total for carriage = 1.31 cum x ¼ = 0.3275
cum
LABOUR
15 Carpenter 2nd class day 0.25 403.67 93.63
17 Beldar day 0.5 350.00 160.42
9999 Sundries L.S. 33.15 2 66.3
TOTAL 1436.31
Add 1 % Water charges 14.36
TOTAL 1450.68
Add GST (multiplying factor 0.1405) 203.82
TOTAL 1654.5
Add 15 % Contractor's profit and
248.17
overheads
Total 1902.67
Add Cess @ 1% on 19.03
Cost of 45 sqm. 1921.7
Cost per sqm. 42.7
Say 42.7
Depth exceeding 3 m but not exceeding 4.5
2.22.3
m
Details of cost for an area 30m long and
1.5m
deep area = 30 x 1.50 = 45 sqm.
MATERIAL
The Material can be used four times on the
same work and after use of material credit
is
given @ 75% of cost
Polling boards of
1198 Second class kail wood in planks 10 cudm 3.5625 260 926.25
250mm x 38mm
40x1.50x0.25x0.038 = 0.57cum. = 570
dm³
Qty taken for cost of using once after
deducting for credit = 570x¼x¼ = 35.625
dm³
Raking struts-
302 Safeda ballies 125 mm diameter metre 3.75 40 150
40x1.50 = 60m
Qty taken for cost of using once after
deducting for credit = 60x¼x¼ = 3.75 m
2204 Carriage of Timber CARRIAGE : cum 0.328 121.29 39.72
Poling boards = 0.57 cum
Ballies 40x1.5x3.14/4x0.125² = 0.4 cum.
Total for carriage = 1.31 cum x ¼ = 0.3275
cum
LABOUR
15 Carpenter 2nd class day 0.5 403.67 187.25
17 Beldar day 0.88 350.00 282.33
9999 Sundries L.S. 47.58 2 95.16
TOTAL 1680.71
Add 1 % Water charges 16.81
TOTAL 1697.52
Add GST (multiplying factor 0.1405) 238.5
TOTAL 1936.02
Add 15 % Contractor's profit and
290.4
overheads
Total 2226.43
Add Cess @ 1% on 22.26
Cost of 45 sqm. 2248.69
Cost per sqm. 49.97
Say 49.95
Extra for planking and strutting in open
timbering if required to be left permanently
2.23
in position. (Face area of the timber
permanently
Details left
of cost fortoabe measured).
trench of length 30m
and
1.5m deep surface area - 2x30x1.5 = 90
sqm.
MATERIAL
Poling boards of
1198 Second class kail wood in planks 10 cudm 99.75 260 25935
1.50mx0.25x0.038
2x40x1.50x0.25x0.038 = 1.14cum =
1140
cudm Less @ 1/8 of Qty as timber is
supposed
to be used once before = 1140 - 142.5 =
997.5
dm ³
Walling 100mmx 100mm of
1197 Second class kail wood in scantling 10 cudm 105 260 27300
4x30mx0.10 mx0.10 m = 1.20cum=
1200
cudm Less @ 1/8 of Qty as timber is
supposed
to be used once before = 1200 - 150 =
1050
dm ³
Struts of Safeda ballies 125 mm diameter
302 metre 44.63 40 1785.2
and
1.5m long 2x17x1.5= 51m
Less @ 1/8 of Qty as timber is supposed to
be
used once before = 51 - 6.37 = 44.63 m
2204 Carriage of Timber cum 1.485 121.29 180.12
Poling boards = 1.14 cum 55200.32
= 1.20
Walling
Ballies struts 51x3.14x¼x0.125² = 0.63 cum
cum
Total of carriage = 2.97 cum Taking half =
2.97 x ½ = 1.485 cum
TOTAL
Add 1 % Water charges 552
TOTAL 55752.32
Add GST (multiplying factor 0.1405) 7833.2
TOTAL 63585.52
Add 15 % Contractor's profit and
9537.83
overheads
Total 73123.35
Add Cess @ 1% on 731.23
Cost of 90 sqm. 73854.58
Cost per sqm. 820.61
Say 820.6
2.24 Extra rates for quantities of works,
executed:
2.24.1 In or under water and/or liquid
mud, including pumping out water as
required
(20 % of
Extra due to slow progress and dewatering: metre
the
therate of
item.
20% of the rate of the item depth
The extra
percentag
eapplicable
in rate is
inofrespect
each
limited
item butto
quantities
work
of
executed
Cost of 1 metre depth in
20.00%
Say 20.00%
2.24.2 In or under foul position,
including pumping out water as required
(25% of
Extra due to slow progress and dewatering: metre the rate of
item. This
25% of the rate of the item depth onlythe
such.
pertains to
Pumping
waterof is
as
envisaged
at the time
of
tendering
and don't
include
those that
covered
for item no. 2.24:- The extra percentage under
contractua
rate is applicable in respect of each item l risk)
but
Costlimited to quantities
of 1 metre depth of work executed 25.00%
in
Saythese difficult conditions. The unit, 25.00%
namely, metre depth, to be considered for
Filling available
payment, shall beexcavated earth
the depth measured from
Note (excluding
the sub soil water level up to plinth,
rock) in trenches, sides
the centre of
2.25 of foundations
gravity oframmingetc.executed
the qty in layersinnot exceeding
difficult
layer
20cm by
in depth, and watering,
consolidating lead up to
condition.
50 m and Theupto
lift depth1.5 shall
m. be each
reckoned
deposited
correct to 0.10 m, 2.05 m or more shall be
taken
Detailsasof0.10
costmfor
and10less
cum.than 0.05 m
ignored.
LABOUR
28 Mate day 0.2 350.00 70.00
18 Coolie day 2.5 350.00 875.00
11 Bhisti day 0.2 350.00 70.00
TOTAL 1015.00
Add 1 % Water charges 10.15
TOTAL 1025.15
Add GST (multiplying factor 0.1405) 144.03
TOTAL 1169.18
Add 15 % Contractor's profit and
175.38
overheads
Total 1344.56
Add Cess @ 1% on 13.45
Cost of 10 cum. 1358.01
Cost of 1 cum. 135.8
Excavating,
Say supplying and filling of local 135.80
earth (including royalty) by mechanical
transport upto a lead of 5km also including
2.25(a)
ramming and watering of the earth in
layers not exceeding 20 cm in trenches,
Detailssides
plinth, of cost
of for 10 cum etc. complete.
foundation
2.6.1 Rate as per item no 2.6.1 of SH: 2 EARTH cum 10 137.00 1310.53 A
WORK
1.2.2 Rate as per item no 1.2.2 of cum -10 101.07 -1010.67 A
SH:1 CARRIAGE OF MATERIALS
Add for ramming and watering in layers
(Ref.
item no 2.27)
17 Beldar (1/2x0.89=0.45 day) day 0.45 350.00 144.37
11 Bhisti day 0.35 350.00 112.29
Carriage of materials upto 5 km
1.1.2 Rate as per item no 1.1.2 of cum 10 152.56 1525.62 A
SH:1 CARRIAGE OF MATERIALS
979 Royalty for good earth cum 10 40 400
TOTAL 2482.14
Add 1 % Water charges except on (A) 656.66 6.57
TOTAL 2488.7
Add GST (multiplying factor 0.1405)
663.23 93.18
except
on (A)
TOTAL 2581.89
Add 15 % Contractor's profit and
756.41 113.46
overheads
except on (A)
Total 2695.35
Add Cess @ 1% except on (A) 869.88 8.7
Cost of 10 cum. 2704.05
Cost of 1 cum. 270.4
Say 270.4
2.26 Extra for every additional lift of
1.5 m or part thereof in excavation /
banking excavated or stacked materials.
2.26.1 All kinds of soil

Details of cost for 10 cum.


LABOUR
28 Mate day 0.1 350.00 32.08
17 Beldar day 1.1 350.00 352.91
TOTAL 385
Add 1 % Water charges 3.85
TOTAL 388.85
Add GST (multiplying factor 0.1405) 54.63
TOTAL 443.48
Add 15 % Contractor's profit and
66.52
overheads
Total 510
Add Cess @ 1% on 5.1
Cost of 10 cum. 515.1
Cost of 1 cum. 51.51
Say 51.5

2.26.2 Ordinary or hard rock

Details of cost for 10 cum.

LABOUR

28 Mate day 0.2 350.00 70.00


17 Beldar day 1.95 350.00 682.50
TOTAL 752.50
Add 1 % Water charges 7.525
TOTAL 760.03
106.78
Add GST (multiplying factor 0.1405) 866.81
TOTAL 130.02
Add 15 % Contractor's profit and
996.82
overheads
Total 9.97
Add Cess @ 1% on 1006.80
Cost of 10 cum. 100.68
Cost of 1 cum. 100.70
Say 100.70
Supplying and filling in plinth with sand
2.27 under floors, including watering, ramming,
consolidating and dressing complete.
Details of cost for 10 cum.
MATERIAL
6501 Sand zone V (Jamuna) cum 10 800 8000.00
2335 Carriage of Sand cum 10 106.13 1061.30
LABOUR 0.00
17 Beldar Day 0.89 350.00 311.50
18 Coolie Day 1.07 350.00 374.50
11 Bhisti Day 0.35 350.00 122.50
TOTAL 9869.80
Add 1 % Water charges 98.698
TOTAL 9968.50
Add GST (multiplying factor 0.1405) 1400.57
TOTAL 11369.07
Add 15 % Contractor's profit and
1705.36
overheads
Total 13074.43
Add Cess @ 1% on 130.74
Cost of 10 cum. 13205.17
Cost of 1 cum. 1320.52
Say 1320.50
1320.50
Surface dressing of the ground including
removing vegetation and in-equalities not
exceeding 15 cm deep and disposal of
rubbish, lead up to 50 m and lift up to 1.5
2.28 m.
2.28.1 All kinds of soil

Details of cost for 100 sqm.

LABOUR
17 Beldar day 1.97 350.00 632.04
18 Coolie day 1.29 350.00 413.87
TOTAL 1045.91
Add 1 % Water charges 10.46
TOTAL 1056.36
Add GST (multiplying factor 0.1405) 148.42
TOTAL 1204.78
Add 15 % Contractor's profit and
180.72
overheads
Total 1385.5
Add Cess @ 1% on 13.86
Cost of 100 sqm. 1399.36
Cost of 1 sqm. 13.99
Say 14
Ploughing the existing ground to a depth
2.29
of 15 cm to 25 cm and watering the same.

2.29.1 All kinds of soil

Details of cost for 100 sqm.


LABOUR
17 Beldar day 2.75 350.00 882.28
11 Bhisti day 0.5 350.00 160.42
TOTAL 1042.7
Add 1 % Water charges 10.43
TOTAL 1053.12
Add GST (multiplying factor 0.1405) 147.96
TOTAL 1201.09
Add 15 % Contractor's profit and
180.16
overheads
Total 1381.25
Add Cess @ 1% on 13.81
Excavating holes more than 0.10 cum &
Cost of 100
upto 0.5 cumsqm.
including getting out the 1395.06
Cost
excavatedsqm.
of 1 soil, then returning the soil as 13.95
Say
required in layers not exceeding 20 cm in 13.95
2.30 depth, including consolidating each
deposited layer by ramming, watering etc,
disposing
2.30.1 All of surplus
kinds ofexcavated
soil soil, as
directed within a lead of 50 m and lift upto
1.5 m.
Details of cost for 10 holes-

Earth work 10 x 0.30 (avg) = 3.0 cum


2.8.1 Rate as per item no. 2.8.1 of SH:
cum 3 180.96 514.2
Earth work
Extra labour for filling and ramming
9999 Sundries L.S. 13.52 2 27.04
TOTAL 541.24
Add 1 % Water charges i.e. on 27.04 0.27
TOTAL 541.51
Add GST (multiplying factor 0.1405) 27.31 3.84
TOTAL 545.35
Add 15 % Contractor's profit and
81.8 12.27
overheads
Total 557.62
Add Cess @ 1% on 94.07 0.94
Cost of 10 holes 558.56
Cost of 1 hole 55.86
Say 55.85
2.30.2 Ordinary rock
Details of cost for 10 holes-
Earth work 10 x 0.3 (avg) = 3.0 cum
2.9.1 Rate as per Item Number 2.9.1 of cum 3 309.60 870.46
SH: Earth Work
Extra labour for filling and ramming
9999 Sundries L.S. 13.52 2 27.04
TOTAL 897.5
Add 1 % Water charges i.e. on 27.04 0.27
TOTAL 897.78
Add GST (multiplying factor 0.1405) 27.31 3.84
TOTAL 901.61
Add 15 % Contractor's profit and
31.15 4.67
overheads
Total 906.28
Add Cess @ 1% on 35.82 0.36
Cost of 10 holes 906.64
Cost of 1 hole 90.66
Say 90.65
2.30.3 Hard rock (requiring blasting)

Details of cost for 10 holes-

Earth work 10 x 0.3 (avg) = 3.0 cum

2.9.2 Rate as per Item Number 2.9.2 of cum 3 531.40 1511.1


SH: Earth Work
Extra labour for filling and ramming
9999 Sundries L.S. 13.52 2 27.04
TOTAL 1538.14
Add 1 % Water charges i.e. on 27.04 0.27
TOTAL 1538.41
Add GST (multiplying factor 0.1405) 27.31 3.84
TOTAL 1542.25
Add 15 % Contractor's profit and
31.15 4.67
overheads
Total 1546.92
Add Cess @ 1% on 35.82 0.36
Cost of 10 holes 1547.28
Cost of 1 hole 154.73
Say 154.75
2.30.4 Hard rock (blasting prohibited)
Details of cost for 10 holes-
Earth work 10 x 0.3 (avg) = 3.0 cum
2.9.3 Rate as per Item Number 2.9.3 of cum 3 738.10 2070.15 A
SH: Earth Work
Extra labour for filling and ramming
9999 Sundries L.S. 13.52 2 27.04
TOTAL 2097.19
Add 1 % Water charges i.e. except on (A) 27.04 0.27
TOTAL 2097.46
Add GST (multiplying factor 0.1405) 27.31 3.84
TOTAL 2101.29
Add 15 % Contractor's profit and
31.15 4.67
overheads
except on (A)
Total 2105.97
Add Cess @ 1% on 35.82 0.36
Cost of 10 holes 2106.32
Clearing
Cost of 1jungle
hole including uprooting of 210.63
rank
Say vegetation, grass, brush wood, trees 210.65
and saplings of girth up to 30 cm measured
2.31
at a height of 1 m above ground level and
removal of rubbish up to a distance of 50
Details
m of cost
outside for 100 sqm.
the periphery of the area cleared.

LABOUR

17 Beldar day 1.08 350.00 346.5


18 Coolie day 0.6 350.00 192.5
TOTAL 538.99
Add 1 % Water charges 5.39
TOTAL 544.38
Add GST (multiplying factor 0.1405) 76.49
TOTAL 620.87
Add 15 % Contractor's profit and
93.13
overheads
Total 714
Add Cess @ 1% on 7.14
Cost of 100 sqm. 721.14
Cost of 1 sqm. 7.21
Say 7.2
2.32 Clearing grass and removal of the
rubbish up to a distance of 50 m outside
the periphery
of the area cleared.

Details of cost for 100 sqm.

LABOUR
17 Beldar day 0.6 350.00 192.5
18 Coolie day 0.25 350.00 80.21
9999 Sundries L.S. 1.82 2 3.64
TOTAL 276.35
Add 1 % Water charges 2.76
TOTAL 279.11
Add GST (multiplying factor 0.1405) 39.21
TOTAL 318.32
Add 15 % Contractor's profit and
47.75
overheads
Total 366.07
Add Cess @ 1% on 3.66
Cost of 100 sqm 369.73
Cost of 1 sqm 3.7
Say
2.33 Felling trees of the girth 3.7
(measured at a height of 1 m above ground
level), including cutting of trunks and
branches, removing the roots and stacking
of
andserviceable
disposal ofmaterial
unserviceable material.
2.33.1 Beyond 30 cm girth upto and
including 60 cm girth
Details of cost for one tree of 15cm dia and
average height 3m
LABOUR quantity of wood-
3.14/4x0.15x0.15x3 = 0.053 cum. Add
20% for branches = 0.011 cum.
Total = 0.064 cum.
Labour for cutting in trees removing the
roots from the soil and then filling in Pit
and depresions.
17 Beldar day 0.33 350.00 105.87
18 Coolie day 0.17 350.00 54.54
9999 Sundries L.S. 2.73 2 5.46
TOTAL 165.88
Add 1 % Water charges 1.66
TOTAL 167.53
Add GST (multiplying factor 0.1405) 23.54
TOTAL 191.07
Add 15 % Contractor's profit and
28.66
overheads
Total 219.73
Add Cess @ 1% on 2.2
Cost of one tree 221.93
Say 221.95
Beyond 60 cm girth upto and including
2.33.2
120 cm girth
Details of cost for a tree of average girth
90cm, average dia. 0.3m and length 5m
LABOUR
quantity of wood-
(22x0.30x0.30x5)/7x4 = 0.35 cum
20% branches = 0.07 cum
Total = 0.42 cum
Labour for cutting trees, removing roots
from
the soil and filling in pit & depressions:
17 Beldar day 1.5 350.00 481.25
18 Coolie day 0.75 350.00 240.62
9999 Sundries L.S. 5.46 2 10.92
TOTAL 732.79
Add 1 % Water charges 7.33
TOTAL 740.12

Add GST (multiplying factor 0.1405) 103.99


TOTAL 844.1
Add 15 % Contractor's profit and
126.62
overheads
Total 970.72
Add Cess @ 1% on 9.71
Cost of one tree 980.42
Say 980.4
2.33.3 Beyond 120 cm girth upto and
including 240 cm girth
Details of cost for a tree of average girth
180cm, average dia. 0.6m and length 7m
LABOUR
quantity of wood-
(22x06x0.60x7)/7x4 = 1.98 cum.+ 20%
branches = 0.40 cum.
Total = 2.38 cum.
Labour for cutting trees, removing roots
from
the soil and filling in pit & depressions:
17 Beldar day 7 350.00 2245.81
18 Coolie day 3.5 350.00 1122.91
9999 Sundries L.S. 8.06 2 16.12
TOTAL 3384.84
Add 1 % Water charges 33.85
TOTAL 3418.68
Add GST (multiplying factor 0.1405) 480.33
TOTAL 3899.01
Add 15 % Contractor's profit and
584.85
overheads
Total 4483.86
Add Cess @ 1% on 44.84
Cost of one tree 4528.7
Say 4528.7

2.33.4 Above 240 cm girth

Details of cost for a tree of average girth


300cm, average dia. 1m and length 10m
LABOUR
quantity of wood-
(22 x 1 x 1 x 10)/7x4 = 7.86 cum
20%
Branches = 1.57 cum.
Total = 9.43 cum.
Labour for cutting trees, removing roots
from
the soil and filling in pit & depressions:
17 Beldar day 14 350.00 4491.62
18 Coolie day 7 350.00 2245.81

9999 Sundries L.S. 26.91 2 53.82


TOTAL 6791.25
Add 1 % Water charges 67.91
TOTAL 6859.16
Add GST (multiplying factor 0.1405) 963.71
TOTAL 7822.87
Add 15 % Contractor's profit and
1173.43
overheads
Total 8996.31
Add Cess @ 1% on 89.96
Cost of one tree 9086.27
Say 9086.25
2.34 Supplying chemical emulsion in
sealed containers including delivery as
specified.
2.34.1 Chlorpyriphos/ Lindane
emulsifiable concentrate of 20%
Details of cost of 100 litres
Chlorpyriphos 20% E.C. / Lindane 20%
7022 litre 100 150 15000
E.C.
2342 Carriage of solvent/ Diesel. quintal 1 10.61 10.61
TOTAL 15010.61
Add 1 % Water charges 150.11
TOTAL 15160.72
Add GST (multiplying factor 0.1405) 2130.08
TOTAL 17290.8
Add 15 % Contractor's profit and
2593.62
overheads
Total 19884.42
Add Cess @ 1% on 198.84
Cost for 100 litres 20083.26
Cost for 1 litre 200.83
Say 200.85
2.35 Diluting and injecting chemical
emulsion for POST-
CONSTRUCTIONAL antitermite
treatment Along
2.35.1 (excluding the cost
external wallof chemical
where the
emulsion)
apron is not: provided using chemical
emulsion @ 7.5 litres / sqm of the vertical
surface
With of the substructure
Chlorpyriphos/ to aE.C.
Lindane depth of
20%
2.35.1.1 300 mm
with 1% including excavation channel
concentration
along the wall & rodding etc. complete:
Details of cost for 10 metres

MATERIAL

Chlorpyriphos 1% concentration = 10.0x


0.30x7.5 = 22.5 litres
Chlorpyriphos 20% required = 22.5/20 =
1.125
litres
Chlorpyriphos 20% E.C. / Lindane 20%
E.C.
1.125 litres (to be supplied free of cost)
LABOUR
17 Beldar day 0.33 350.00 105.87
(for excavating channel) rodding in
chemical
spraying the emulssion and refilling the
same
9999 Sundries, rent of sprayer etc. L.S. 13.52 2 27.04
TOTAL 132.91
Add 1 % Water charges 1.33
TOTAL 134.24
Add GST (multiplying factor 0.1405) 18.86
TOTAL 153.1
Add 15 % Contractor's profit and
22.97
overheads
Total 176.07
Add Cess @ 1% on 1.76
Cost for 10 metres 177.83
Cost for 1 metre 17.78
Say 17.8
2.35.2 Along the external wall below
concrete or masonry apron using chemical
emulsion @ 2.25 litres per linear metre
including drilling andLindane
With Chlorpyriphos/ pluggingE.C.
holes etc.:
20%
2.35.2.1
with
1% concentration
Details of cost for 10 metres
MATERIAL
Chlorpyriphos 1% concentration = 10x
2.25 = 22.5 litres
Chlorpyriphos 20% required = 22.50/
20 = 1.125 litres
Chlorpyriphos 20% E.C. / Lindane 20%
E.C.
1.125 litres (to be supplied free of cost)
LABOUR
17 Beldar day 0.4 350.00 128.33
(for drilling holes and injecting chemical)
Sundries and rent of a sprayer and mortar
9999 L.S. 35.88 2 71.76
and
making good the holes
TOTAL 200.09
Add 1 % Water charges 2
TOTAL 202.09
Add GST (multiplying factor 0.1405) 28.39
TOTAL 230.49
Add 15 % Contractor's profit and
34.57
overheads
Total 265.06
Add Cess @ 1% on 2.65
Cost for 10 metres 267.71
Cost for 1 metre 26.77
Say 26.75
2.35.3 Treatment of soil under existing
floors using chemical emulsion @ one litre
per hole, 300 mm apart including drilling
112:2mm
(1 cement
diameter: 2holes
Coarse
andsand) to match
plugging with
the existing
cement floor: 2.35.3.1 With
mortar
Chlorpyriphos/Lindane E.C. 20% with 1%
concentration
Details of cost for 9 sqm. (3 metre x 3
metre)
No. of holes - 100 nos.

MATERIAL

Chlorpyriphos 1% required 100x1 litre =

100 litres
Chlorpyriphos 20% E.C. = 100/20 = 5.0
litres
Chlorpyriphos 20% E.C. / Lindane 20%
E.C. 5 litres (to be supplied free of cost)
LABOUR
0017 Beldar day 2 350.00 641.66
(For making holes & spraying)
0024 Mason (brick layer) 2nd class day 0.5 403.67 187.25
9999 Sundries, rent of sprayer and mortar L.S. 35.88 2 71.76
TOTAL 900.67
Add 1 % Water charges 9.01
TOTAL 909.68
Add GST (multiplying factor 0.1405) 127.81
TOTAL 1037.49
Add 15 % Contractor's profit and
155.62
overheads
Total 1193.11
Add Cess @ 1% on 11.93
Cost for 9 square metre 1205.04
Cost per square metre 133.89
Treatment of existing masonry using
Say 133.9
chemical emulsion @ one litre per hole at
300 mm interval including drilling holes at
2.35.4
45
Withdegree and plugging them E.C.
Chlorpyriphos/Lindane with 20%
cement
2.35.4.1 mortar
with 1%1:2 (1 cement : 2 coarse sand) to the
concentration
full depth of the hole :
Details of cost for 10 metres

MATERIAL
No. of holes 10.0/0.30 = 33.33+1 = 34.33
holes Say 34 holes
chlorpyriphos 1% concentration required
= 34x1.0 = 34.00 litres
Chlorpyriphos 20% E.C. required
34.00/20 = 1.70 litres
Chlorpyriphos 20% E.C. / Lindane 20%
E.C.
1.7 litres (to be supplied free of cost)
LABOUR
17 Beldar day 0.3 350.00 96.25
24 Mason (brick layer) 2nd class day 0.05 403.67 18.73
9999 Sundries, rent of pump etc. L.S. 17.94 2 35.88
TOTAL 150.85
Add 1 % Water charges 1.51
TOTAL 152.36
Add GST (multiplying factor 0.1405) 21.41
TOTAL 173.77
Add 15 % Contractor's profit and
26.07
overheads
Total 199.83
Add Cess @ 1% on 2
Cost for 10 metres 201.83
Cost for 1 metre 20.18
Say 20.2

Treatment at points of contact of wood


work by chemical emulsion Chlorpyriphos/
Lindane (in oil or kerosene based solution)
@ 0.5 litres per hole by drilling 6 mm dia
holes at downward angle of 45 degree at
150 mm centre to centre and sealing the
same.
2.35.5

Details of cost for 10 metres

MATERIAL

No. of holes 10.0/0.15 = 66.67+1 = 67.67

holes
Say 68 holes

Chlordane 1% concentration required

= 68 x 0.5 = 34.00 litres


E.C.
Chlordane 20%
required
E.C./
34.00/20=1.70 litres
Lindane
Chlordane 20%
20% E.C.
litres (to be supplied free of cost) Kerosene oil 1.7
= 34-1.7 = 32.30 litres
771 Kerosene oil litre 32.3 50 1615
LABOUR
15 Carpenter 2nd class day 0.2 403.67 74.9
(For making holes and plugging the same)
17 Beldar day 0.2 350.00 64.17
for injecting chemical
9999 Sundries L.S. 17.94 2 35.88
TOTAL 1789.95
Add 1 % Water charges 17.9
TOTAL 1807.85
Add GST (multiplying factor 0.1405) 254
TOTAL 2061.85
Add 15 % Contractor's profit and
309.28
overheads
Total 2371.12
Add Cess @ 1% on 23.71
Cost for 10 metres 2394.84
Cost for 1 metre 239.48
Say 239.5

Extra for levelling & neatly dressing of


disposed soil completely as directed by
Engineer-
2.36

in-charge.

Details of cost for 10 cum.

LABOUR
28 Mate day 0.08 350.00 25.67
18 Beldar/ Coolie day 0.8 350.00 256.66
TOTAL 282.33
Add 1 % Water charges 2.82
TOTAL 285.15
Add GST (multiplying factor 0.1405) 40.06
TOTAL 325.22
Add 15 % Contractor's profit and
48.78
overheads
Total 374
Add Cess @ 1% on 3.74
Cost of 10 cum. 377.74
Cost of 1 cum. 37.77
Say
Supply and stacking of Fly ash conforming 37.75
to IRC- 58 at site, including carriage,
2.37 loading , unloading & stacking up to any
lead (measured stacks will be reduced by
20% for
payment).

Details of cost for 1 cum.

Ref :- Based on DAR Item No : 1.1.1 A) ii)


Labour and carriage
1980 Flyash cum 1 10 10
(Available free of cost at thermal power
plant
at Baderpur power plant. Lead = 35 km)
2262 Carriage of Flyash cum 1 106.13 106.13
(1st Lead 0 to 5km) 116.13
TOTAL
Add 1 % Water charges 1.16
TOTAL 117.29
Add GST (multiplying factor 0.1405) 16.48
TOTAL 133.77
Add 15 % Contractor's profit and
20.07
overheads
Total 153.84
Add Cess @ 1% on 1.54
Total 155.37
Cost of 1 cum. 155.37
Say 155.35
(excluding rock) in trenches or
embankment in layers (each layer should
not exceed 15 cm), with intermediate layer
of compacted earth (Soil density of 98%)
after every four layers of compacted depth
2.38 of fly ash, sides & top layer of filling shall
be done with earth having total minimum
compacted
charge. thickness 30 cm or as decided
by Engineer in-charge, including
compacting each layer by rolling/ ramming
Details of costall
and watering, forcomplete
10 cum. as per drawing
and direction of Engineer -in -
Ref :- Based on DAR Item No : 2.25

LABOUR
28 Mate day 0.2 350.00 64.17
18 Coolie day 2.5 350.00 802.08
11 Bhisti day 0.2 350.00 64.17
TOTAL 930.41
Add 1 % Water charges 9.3
TOTAL 939.71
Add GST (multiplying factor 0.1405) 132.03
TOTAL 1071.74
Add 15 % Contractor's profit and
160.76
overheads
Total 1232.5
Add Cess @ 1% on 12.33
Cost of 10 cum. 1244.83
Cost of 1 cum. 124.48
Say 124.5

SUB HEAD : 3.0

MORTAR

Code Description Unit Quantity Rate Amount


3.1 Cement mortar 1:1 (1 cement :
1 fine sand)
Details of cost for 1 cum
MATERIAL
(0.7175 cum. of cement = 1.02 tonne)
Cement
required for cement mortar is 71.25%
367 Portland Cement tonne 1.02 4940 5038.8
2209 Carriage of Cement tonne 1.02 94.34 96.22
983 Fine sand cum 0.7125 900 641.25
2261 Carriage of Fine sand (1 part Fine sand : 2 cum 0.7125 106.13 75.62
parts Sand)
LABOUR
For measuring, carrying, depositing and
mixing-
17 Beldar day 0.75 350.00 240.62
11 Bhisti day 0.07 350.00 22.46
Hire and running charges of mechanical
9999 L.S. 26.9 2 53.8
mixer
9999 Sundries L.S. 13.52 2 27.04
Cost of 1.00 cum 6195.81
Say 6195.8
3.2 Cement mortar 1:2 (1 cement :
2 fine sand).
Details of cost for 1 cum
MATERIAL
(0.475 cum. of cement = 0.68 tonne)
Cement
required for cement mortar is 47.50%
367 Portland Cement tonne 0.68 4940 3359.2
2209 Carriage of Cement tonne 0.68 94.34 64.15
983 Fine sand cum 0.95 900 855
2261 Carriage of Fine sand (1 part Fine sand : 2 cum 0.95 106.13 100.82
parts Sand)
LABOUR
For measuring, carrying, depositing and
mixing-
17 Beldar day 0.75 350.00 240.62
11 Bhisti day 0.07 350.00 22.46
Hire and running charges of mechanical
9999 L.S. 26.91 2 53.82
mixer
9999 Sundries L.S. 13.52 2 27.04
Cost of 1.00 cum 4723.11
Say 4723.1
3.3 Cement mortar 1:3 (1 cement :
3 fine sand).
Details of cost for 1 cum

MATERIAL
(0.357 cum. of cement = 0.51 tonne)
Cement
required for cement mortar is 35.70%
367 Portland Cement tonne 0.51 4940 2519.4
2209 Carriage of Cement tonne 0.51 94.34 48.11
983 Fine sand cum 1.07 900 963
2261 Carriage of Fine sand (1 part Fine sand : 2 cum 1.07 106.13 113.56
parts Sand)
LABOUR
For measuring, carrying, depositing and
mixing-
17 Beldar day 0.75 350.00 240.62
11 Bhisti day 0.07 350.00 22.46
Hire and running charges of mechanical
9999 L.S. 26.91 2 53.82
mixer
9999 Sundries L.S. 13.52 2 27.04
Cost of 1.00 cum 3988.01
Say 3988
3.4 Cement mortar 1:4 (1 cement :
4 fine sand).
Details of cost for 1 cum

MATERIAL
(0.268 cum. of cement = 0.38 tonne)
Cement
required for cement mortar is 26.80%
367 Portland Cement tonne 0.38 4940 1877.2
2209 Carriage of Cement tonne 0.38 94.34 35.85
983 Fine sand cum 1.07 900 963
2261 Carriage of Fine sand (1 part Fine sand : 2 cum 1.07 106.13 113.56
parts Sand)
LABOUR
For measuring, carrying, depositing and
mixing-
17 Beldar day 0.75 350.00 240.62
11 Bhisti day 0.07 350.00 22.46
Hire and running charges of mechanical
9999 L.S. 26.91 2 53.82
mixer
9999 Sundries L.S. 13.52 2 27.04
Cost of 1.00 cum 3333.55
Say 3333.55
3.5 Cement mortar 1:5 (1 cement : 5 fine
sand).
Details of cost for 1 cum
MATERIAL
(0.214 cum. of cement = 0.31 tonne)
Cement
required for cement mortar is 21.40%
367 Portland Cement tonne 0.31 4940 1531.4
2209 Carriage of Cement tonne 0.31 94.34 29.24
983 Fine sand cum 1.07 900 963
2261 Carriage of Fine sand (1 part Fine sand : cum 1.07 106.13 113.56
2 parts Sand)
LABOUR
For measuring, carrying, depositing and
mixing-
17 Beldar day 0.75 350.00 240.62
11 Bhisti day 0.07 350.00 22.46
Hire and running charges of mechanical
9999 L.S. 26.91 2 53.82
mixer
9999 Sundries L.S. 13.52 2 27.04
Cost of 1.00 cum 2981.14
Say 2981.15
3.6 Cement mortar 1:6 (1 cement :
6 fine sand).
Details of cost for 1 cum

MATERIAL
(0.178 cum. of cement = 0.25 tonne)
Cement
required for cement mortar is 17.80%
367 Portland Cement tonne 0.25 4940 1235
2209 Carriage of Cement tonne 0.25 94.34 23.58
983 Fine sand cum 1.07 900 963
2261 Carriage of Fine sand (1 part Fine sand : 2 cum 1.07 106.13 113.56
parts Sand)
LABOUR
For measuring, carrying, depositing and
mixing-
17 Beldar day 0.75 350.00 240.62
11 Bhisti day 0.07 350.00 22.46
Hire and running charges of mechanical
9999 L.S. 26.91 2 53.82
mixer
9999 Sundries L.S. 13.52 2 27.04
Cost of 1.00 cum 2679.08
Say 2679.1
3.7 Cement mortar 1:2 (1 cement :
2 coarse sand).
Details of cost for 1 cum

MATERIAL
(0.476 cum. of cement = 0.68 tonne)
Cement
required for cement mortar is 47.50%
367 Portland Cement tonne 0.68 4940 3359.20
2209 Carriage of Cement tonne 0.68 94.34 64.15
982 Coarse sand cum 0.95 1350 1282.50
2203 Carriage of Coarse sand cum 0.95 106.13 100.82
LABOUR
For measuring, carrying, depositing and
mixing-
17 Beldar day 0.75 350.00 262.50
11 Bhisti day 0.07 350.00 24.50
Hire and running charges of mechanical
9999 L.S. 26.91 2 53.82
mixer
9999 Sundries L.S. 13.52 2 27.04
Cost of 1.00 cum 5174.53
Say 5174.50

3.8 Cement mortar 1:3 (1 cement :


3 coarse sand).
Details of cost for 1 cum

MATERIAL
(0.357 cum. of cement = 0.51 tonne)
Cement
required for cement mortar is 35.70%
367 Portland Cement tonne 0.51 4940 2519.4
2209 Carriage of Cement tonne 0.51 94.34 48.11
982 Coarse sand cum 1.07 1350 1444.5
2203 Carriage of Coarse sand cum 1.07 106.13 113.56
LABOUR
For measuring, carrying, depositing and
mixing-
17 Beldar day 0.75 350.00 240.62
11 Bhisti day 0.07 350.00 22.46
Hire and running charges of mechanical
9999 L.S. 26.91 2 53.82
mixer
9999 Sundries L.S. 13.52 2 27.04
Cost of 1.00 cum 4469.51
Say 4469.5
3.9 Cement mortar 1:4 (1 cement :
4 coarse sand).
Details of cost for 1 cum

MATERIAL
(0.268 cum. of cement = 0.38 tonne)
Cement
required for cement mortar is 26.80%
367 Portland Cement tonne 0.38 4940 1877.2
2209 Carriage of Cement tonne 0.38 94.34 35.85
982 Coarse sand cum 1.07 1350 1444.5
2203 Carriage of Coarse sand cum 1.07 106.13 113.56
LABOUR
For measuring, carrying, depositing and
mixing-
17 Beldar day 0.75 350.00 240.62
11 Bhisti day 0.07 350.00 22.46
Hire and running charges of mechanical
9999 L.S. 26.91 2 53.82
mixer
9999 Sundries L.S. 13.52 2 27.04
Cost of 1.00 cum 3815.05
Say 3815.05
3.10 Cement mortar 1:5 (1 cement :
5 coarse sand).
Details of cost for 1 cum

MATERIAL
(0.214 cum. of cement = 0.31 tonne)
Cement
required for cement mortar is 21.40%
367 Portland Cement tonne 0.31 4940 1531.4
2209 Carriage of Cement tonne 0.31 94.34 29.24
982 Coarse sand cum 1.07 1350 1444.5
2203 Carriage of Coarse sand cum 1.07 106.13 113.56
LABOUR
For measuring, carrying, depositing and
mixing-
17 Beldar day 0.75 350.00 240.62
11 Bhisti day 0.07 350.00 22.46
Hire and running charges of mechanical
9999 L.S. 26.91 2 53.82
mixer
9999 Sundries L.S. 13.52 2 27.04
TOTAL 3462.64
Say 3462.65
3.11 Cement mortar 1:6 (1 cement :
6 coarse sand).
Details of cost for 1 cum

MATERIAL
(0.178 cum. of cement = 0.25 tonne)
Cement required for cement mortar is
367 17.80%
Portland Cement tonne 0.25 4940 1235
2209 Carriage of Cement tonne 0.25 94.34 23.58
982 Coarse sand cum 1.07 1350 1444.5
2203 Carriage of Coarse sand cum 1.07 106.13 113.56
LABOUR
For measuring, carrying, depositing and
mixing-
17 Beldar day 0.75 350.00 240.62
11 Bhisti day 0.07 350.00 22.46
Hire and running charges of mechanical
9999 L.S. 26.91 2 53.82
mixer
9999 Sundries L.S. 13.52 2 27.04
Cost of 1.00 cum 3160.58
Say 3160.6
3.12 Cement mortar 1:2 (1 cement :
2 stone dust).
Details of cost for 1 cum

MATERIAL
(0.475 cum. of cement = 0.68 tonne)
Cement
required for cement mortar is 47.50%
367 Portland Cement tonne 0.68 4940 3359.2
2209 Carriage of Cement tonne 0.68 94.34 64.15
1159 Stone dust cum 0.95 1100 1045
2267 Carriage of Stone dust cum 0.95 106.13 100.82
LABOUR
For measuring, carrying, depositing and
mixing-
17 Beldar day 0.75 350.00 240.62
11 Bhisti day 0.07 350.00 22.46
Hire and running charges of mechanical
9999 L.S. 26.91 2 53.82
mixer
9999 Sundries L.S. 13.52 2 27.04
Cost of 1.00 cum 4913.11
Say 4913.1
3.13 Cement mortar 1:2 (1 cement :
2 marble dust).
Details of cost for 1 cum

MATERIAL
(0.475 cum of cement = 0.68 tonne)
Cement
required for cement mortar is 47.50%
367 Portland Cement tonne 0.68 4940 3359.2
2209 Carriage of Cement tonne 0.68 94.33783 64.15
784 Marble dust/ powder cum 0.95 1130 1073.5
2268 Carriage of Marble dust and marble chips cum 0.95 106.1301 100.82
LABOUR
For measuring, carrying, depositing and
mixing
17 Beldar day 0.75 350.00 240.62
11 Bhisti day 0.07 350.00 22.46
Hire and running charges of mechanical
9999 L.S. 26.91 2 53.82
mixer
9999 Sundries L.S. 13.52 2 27.04
Cost of 1.00 cum 4941.61
Say 4941.6
3.14 Cement mortar 1:5 (1 cement :
5 marble dust).
Details of cost for 1 cum

MATERIAL
(0.214 cum. of cement = 0.31 tonne)
Cement
required for cement mortar is 21.40%
367 Portland Cement tonne 0.31 4940 1531.4
2209 Carriage of Cement tonne 0.31 94.34 29.24
784 Marble dust/ powder cum 1.07 1130 1209.1
2268 Carriage of Marble dust and marble chips cum 1.07 106.13 113.56
LABOUR
For measuring, carrying, depositing and
mixing-
17 Beldar day 0.75 350.00 240.62
11 Bhisti day 0.07 350.00 22.46
Hire and running charges of mechanical
9999 L.S. 26.91 2 53.82
mixer
9999 Sundries L.S. 13.52 2 27.04
Cost of 1.00 cum 3227.24
Say 3227.25
3.15 White cement mortar 1:2 (1
white cement : 2 marble dust).
Details of cost for 1 cum

MATERIAL
(0.475 cum. of white cement = 0.68 tonne)
Cement required for cement mortar is
368 47.50%
White Cement tonne 0.68 11200 7616
2209 Carriage of Cement tonne 0.68 94.34 64.15
784 Marble dust/ powder cum 0.95 1130 1073.5
2268 Carriage of Marble dust and marble chips cum 0.95 106.13 100.82
LABOUR
For measuring, carrying, depositing and
mixing-
17 Beldar day 0.75 350.00 240.62
11 Bhisti day 0.07 350.00 22.46
Hire and running charges of mechanical
9999 L.S. 26.91 2 53.82
mixer
9999 Sundries L.S. 13.52 2 27.04
Cost of 1.00 cum 9198.41
Say 9198.4
3.16 White cement mortar 1:3 (1
white cement : 3 marble dust).
Details of cost for 1 cum

MATERIAL
(0.357 cum. of white cement = 0.51 tonne)
Cement required for cement mortar is
35.70%
368 White Cement tonne 0.51 11200 5712
2209 Carriage of Cement tonne 0.51 94.33783 48.11
784 Marble dust/ powder cum 1.07 1130 1209.1
2268 Carriage of Marble dust and marble chips cum 1.07 106.1301 113.56
LABOUR
For measuring, carrying, depositing and
mixing-
17 Beldar day 0.75 350.00 240.62
11 Bhisti day 0.07 350.00 22.46
Hire and running charges of mechanical
9999 L.S. 26.91 2 53.82
mixer
9999 Sundries L.S. 13.52 2 27.04
Cost of 1.00 cum 7426.71
Say 7426.7
3.17 White cement mortar 1:5 (1
white cement : 5 marble dust).
Details of cost for 1 cum

MATERIAL

(0.214 cum. of white cement = 0.31 tonne)


Cement required for cement mortar is
21.40%
368 White Cement tonne 0.31 11200 3472
2209 Carriage of Cement tonne 0.31 94.34 29.24
784 Marble dust/ powder cum 1.07 1130 1209.1
2268 Carriage of Marble dust and marble chips cum 1.07 106.13 113.56
LABOUR
For measuring, carrying, depositing and
mixing-
17 Beldar day 0.75 350.00 240.62
11 Bhisti day 0.07 350.00 22.46
Hire and running charges of mechanical
9999 L.S. 26.91 2 53.82
mixer
9999 Sundries L.S. 13.52 2 27.04
Cost of 1.00 cum 5167.84
Say 5167.85

3.18 Mud mortar

Detail of cost for one cum

MATERIAL
811 Mud (dry) cum 1.08 165 178.2
LABOUR
17 Beldar day 0.63 350.00 202.12
11 Bhisti day 0.315 350.00 101.06
9999 Sundries L.S. 6.45 2 12.9
TOTAL 494.28
Cost of one cum 494.28
Say 494.3
3.19 Mortar in lime, surkhi (50%
red and 50% light yellow) and marble dust
1:1.5:0.5
Details of cost for 1 cum

MATERIAL

(0.475 cum of lime putty) = 3.01 q of


unslaked lime
1182 Surkhi cum 0.7125 700 498.75
773 Unslaked lime quintal 3.01 300 903
784 Marble dust/ powder cum 0.24 1130 271.2
2268 Marble dust and/or marble chips cum 0.24 106.13 25.47
2208 Carriage of Lime cum 3.01 106.13 319.45
LABOUR
For slaking lime, making lime putty,
grinding
and carrying
17 Beldar day 0.9 350.00 288.75
11 Bhisti day 0.45 350.00 144.37
As cost for running and upkeep of mortar
9999 L.S. 10.35 2 20.7
mill
9999 Sundries L.S. 5.2 2 10.4

Cost of 1.00 cum 2482.09


Say 2482.1
132
53.25

429.25
270.4

4.05
17.15

131.05
235.05

426.55
652.85

171.4
290.15

503.7
690.05
356.5
315.5
200.7

496.95
571.85
302.8

749.75

862.7
390.85

967.8
1113.65
102.55

252.9
130.8
145.7
129.05
143.15
158
110.5
118.25
126.6

1593.85
64.1
124.5
92.3
1880.2
5150.6
SUB HEAD : 4.0
CONCRETE WORK
Code Description Unit Quantity Rate

4.1 Providing and laying in position cement


concrete of specified grade excluding the cost
of centering and shuttering - All work up to
plinth level :
###
### 4.1.2 1:1½:3 (1 Cement: 1½ coarse sand) : 3
graded stone aggregate 20 mm
###
### nominal size)
###
### Details of cost for 1 cum.

###
### MATERIAL

### 295.0 Stone Aggregate (Single size) : 20 mm nominal size cum 0.57 800

### 297.0 Stone Aggregate (Single size) : 10 mm nominal size cum 0.28 810

### 2202.0 Carriage of Stone aggregate below 40 mm nominal cum 0.85 584.88
### size

### 982.0 Coarse sand cum 0.425 800

### 2203.0 Carriage of Coarse sand cum 0.425 584.88

### 367.0 Portland Cement (0.2833 cum) tonne 0.4 4375

### 2209.0 Carriage of Cement tonne 0.4 94.34

### LABOUR

### 40.0 Mason (average) day 0.1 403.67

### 17.0 Beldar day 1.63 350.00

### 11.0 Bhisti day 0.7 350.00

### 2.0 Hire charges of Concrete Mixer 0.25 to day 0.07 800

### 0.40 cum with hooper

### 12.0 Vibrator(Needle type 40mm) day 0.07 370

### 9999.0 Sundries L.S. 14.3 2

### TOTAL

### Add 1 % Water charges on "W"

### TOTAL

### Add GST (multiplying factor 0.1405) on "X"

### TOTAL

### Add 15 % Contractor's profit and overheads on "Y"

### Total

### Add Cess @ 1% on "Z"

### Cost of 1 cum.


### Say

###
###
4.1.3 1:2:4 (1 cement : 2 coarse sand) : 4 graded stone
aggregate 20 mm nominal size)
###
### Details of cost for 1 cum.

###
### MATERIAL

### 295.0 Stone Aggregate (Single size) : 20 mm nominal size cum 0.67 800

### 297.0 Stone Aggregate (Single size) : 10 mm nominal size cum 0.22 810

### 2202.0 Carriage of Stone aggregate below 40 mm nominal cum 0.89 584.88

### size

### 982.0 Coarse sand cum 0.445 800

### 2203.0 Carriage of Coarse sand cum 0.445 584.88

### 367.0 Portland Cement (0.2225 cum) tonne 0.32 4940

### 2209.0 Carriage of Cement tonne 0.32 94.34

### LABOUR

### 40.0 Mason (average) day 0.1 403.67

### 17.0 Beldar day 1.63 350.00

### 11.0 Bhisti day 0.7 350.00

### 2.0 Hire charges of Concrete Mixer 0.25 to day 0.07 800

### 0.40 cum with hooper

### 12.0 Vibrator(Needle type 40mm) day 0.07 370

### 9999.0 Sundries L.S. 14.3 2

### TOTAL

### Add 1 % Water charges on "W"

### TOTAL

### Add GST (multiplying factor 0.1405) on "X"

### TOTAL

### Add 15 % Contractor's profit and overheads on "Y"

### Total

### Add Cess @ 1% on "Z"

### Cost of 1 cum.

### Say

###
### 4.1.4 1:2:4 (1 Cement : 2 coarse sand) : 4 graded
stone aggregate 40 mm nominal size)
###
### Details of cost for 1 cum.

### MATERIAL

### 293.0 Stone Aggregate (Single size) : 40 mm nominal size cum 0.52 760

### 0.56 - (7.5% for voids i.e.) 0.04 = 0.52 cum

### 295.0 Stone Aggregate (Single size) : 20 mm nominal size cum 0.22 800

### 297.0 Stone Aggregate (Single size) : 10 mm nominal size cum 0.11 810

### 2206.0 Carriage of Stone aggregate 40 mm nominal size cum 0.52 115.36
### and above

### 2202.0 Carriage of Stone aggregate below 40 mm nominal cum 0.33 584.88

### size

### 982.0 Coarse sand cum 0.445 800

### 2203.0 Carriage of Coarse sand cum 0.445 584.88

###
###
### 367.0 Portland Cement (0.2225 cum) tonne 0.32 4375

### 2209.0 Carriage of Cement tonne 0.32 94.34

### LABOUR

### 40.0 Mason (average) day 0.1 403.67

### 17.0 Beldar day 1.63 350.00

### 11.0 Bhisti day 0.7 350.00

### 2.0 Hire charges of Concrete Mixer 0.25 to day 0.07 800

### 0.40 cum with hooper

### 12.0 Vibrator(Needle type 40mm) day 0.07 370

### 9999.0 Sundries L.S. 13.52 2

### TOTAL

### Add 1 % Water charges on "W"

### TOTAL

### Add GST (multiplying factor 0.1405) on "X"

### TOTAL

### Add 15 % Contractor's profit and overheads on "Y"

### Total

### Add Cess @ 1% on "Z"

### Cost of 1 cum.

### Say

###
###
4.1.5 1:3:6 (1 Cement : 3 coarse sand) : 6 graded stone
aggregate 20 mm nominal size)
###
### Details of cost for 1 cum.

###
### MATERIAL

### 295.0 Stone Aggregate (Single size) : 20 mm nominal size cum 0.7 800

### 297.0 Stone Aggregate (Single size) : 10 mm nominal size cum 0.24 810

### 2202.0 Carriage of Stone aggregate below 40 mm nominal cum 0.94 584.88

### size

### 982.0 Coarse sand cum 0.47 800

### 2203.0 Carriage of Coarse sand cum 0.47 584.88

### 367.0 Portland Cement (0.15674 cum) tonne 0.22 4940

### 2209.0 Carriage of Cement tonne 0.22 94.34

### LABOUR

### 40.0 Mason (average) day 0.1 403.67


### 17.0 Beldar day 1.63 350.00

### 11.0 Bhisti day 0.7 350.00

### 2.0 Hire charges of Concrete Mixer 0.25 to day 0.07 800

### 0.40 cum with hooper

### 12.0 Vibrator(Needle type 40mm) day 0.07 370

### 9999.0 Sundries L.S. 13.52 2

### TOTAL

### Add 1 % Water charges on "W"

### TOTAL

### Add GST (multiplying factor 0.1405) on "X"

### TOTAL

### Add 15 % Contractor's profit and overheads on "Y"

### Total

### Add Cess @ 1% on "Z"

### Cost of 1 cum.

### Say

###
###
4.1.6 1:3:6 (1 Cement : 3 coarse sand): 6 graded stone
aggregate 40 mm nominal size)
###
### Details of cost for 1 cum.

###
### MATERIAL

### 293.0 Stone Aggregate (Single size) : 40 mm nominal size cum 0.65 760

### (0.70 cum - 7.5% for voids i.e. 0.05 = 0.65 cum)

### 295.0 Stone Aggregate (Single size) : 20 mm nominal size cum 0.24 800

### 2206.0 Carriage of Stone aggregate 40 mm nominal size cum 0.65 115.36

### and above

### 2202.0 Carriage of Stone aggregate below 40 mm nominal cum 0.24 584.88

### size

### 982.0 Coarse sand cum 0.47 800

### 2203.0 Carriage of Coarse sand cum 0.47 584.88

### 367.0 Portland Cement (0.15674 cum) tonne 0.22 4375

### 2209.0 Carriage of Cement tonne 0.22 94.34

### LABOUR

### 40.0 Mason (average) day 0.1 403.67

### 17.0 Beldar day 1.63 350.00

### 11.0 Bhisti day 0.7 350.00

### 2.0 Hire charges of Concrete Mixer 0.25 to day 0.07 800

### 0.40 cum with hooper

### 12.0 Vibrator(Needle type 40mm) day 0.07 370

### 9999.0 Sundries L.S. 13.52 2

### TOTAL

### Add 1 % Water charges on "W"


### TOTAL

### Add GST (multiplying factor 0.1405) on "X"

### TOTAL

### Add 15 % Contractor's profit and overheads on "Y"

### Total

### Add Cess @ 1% on "Z"

### Cost of 1 cum.

### Say

###
###
### 4.1.8 1:4:8 (1 Cement : 4 coarse sand) : 8 graded
stone aggregate 40 mm nominal size)
###
### Details of cost for 1 cum.

### MATERIAL

### 293.0 Stone Aggregate (Single size) : 40 mm nominal size cum 0.65 760

### (0.70 cum - 7.5% for voids i.e. 0.05 = 0.65 cum)

### 295.0 Stone Aggregate (Single size) : 20 mm nominal size cum 0.24 800

### 2206.0 Carriage of Stone aggregate 40 mm nominal size cum 0.65 115.36

### and above

### 2202.0 Carriage of Stone aggregate below 40 mm nominal cum 0.24 584.88

### size

### 982.0 Coarse sand cum 0.47 800

### 2203.0 Carriage of Coarse sand cum 0.47 584.88

### 367.0 Portland Cement (0.1175 cum) tonne 0.17 4940

### 2209.0 Carriage of Cement tonne 0.17 94.34

### LABOUR

### 40.0 Mason (average) day 0.1 403.67

### 17.0 Beldar day 1.63 350.00

### 11.0 Bhisti day 0.7 350.00

### 2.0 Hire charges of Concrete Mixer 0.25 to day 0.07 800

### 0.40 cum with hooper

### 12.0 Vibrator(Needle type 40mm) day 0.07 370

### 9999.0 Sundries L.S. 13.52 2

### TOTAL

### Add 1 % Water charges on "W"

### TOTAL

### Add GST (multiplying factor 0.1405) on "X"

### TOTAL

### Add 15 % Contractor's profit and overheads on "Y"

### Total

### Add Cess @ 1% on "Z"

### Cost of 1 cum.

### Say
###
### 4.1 Providing and laying in position cement
concrete of specified grade excluding the
###
### cost of centering and shuttering - All work up to
plinth level :
### 4.1.10 1:5:10 (1 cement : 5 coarse sand): 10
graded stone aggregate 40 mm nominal size)
###
### Details of cost for 1 cum.

###
### MATERIAL

###
### 293.0 Stone Aggregate (Single size) : 40 mm nominal size cum 0.65 760

### (0.70 cum - 7.5% for voids i.e. 0.05

### = 0.65 cum)

###
295 Stone Aggregate (Single size) : 20 mm nominal size cum 0.24 1350

### 2206.0 Carriage of Stone aggregate 40 mm nominal size cum 0.65 115.36

### and above

### 2202.0 Carriage of Stone aggregate below 40 mm nominal cum 0.24 584.88

### size

### 982.0 Coarse sand cum 0.47 800

### 2203.0 Carriage of Coarse sand cum 0.47 584.88

### 367.0 Portland Cement (0.2225 cum) tonne 0.13 4375

### 2209.0 Carriage of Cement tonne 0.13 94.34

### LABOUR

### 40.0 Mason (average) day 0.1 403.67

### 17.0 Beldar day 1.63 350.00

### 11.0 Bhisti day 0.7 350.00

### 2.0 Hire charges of Concrete Mixer 0.25 to day 0.07 800

### 0.40 cum with hooper

### 12.0 Vibrator(Needle type 40mm) day 0.07 370

### 9999.0 Sundries L.S. 13.52 2

### TOTAL

### Add 1 % Water charges on "W"

### TOTAL

### Add GST (multiplying factor 0.1405) on "X"

### TOTAL

### Add 15 % Contractor's profit and overheads on "Y"

### Total

### Add Cess @ 1% on "Z"

### Cost of 1 cum.

### Say

###
###
4.1.11 1:5:10 (1 cement : 5 fine sand : 10 graded stone
aggregate 40 mm nominal size)
###
### Details of cost for 1 cum.

###
### MATERIAL

### 293.0 Stone Aggregate (Single size) : 40 mm nominal size cum 0.65 760

### (0.70 cum - 7.5% for voids i.e. 0.05 = 0.65 cum)

### 295.0 Stone Aggregate (Single size) : 20 mm nominal size cum 0.24 800

### 2206.0 Carriage of Stone aggregate 40 mm nominal size cum 0.65 115.36

### and above

### 2202.0 Carriage of Stone aggregate below 40 mm nominal cum 0.24 584.88

### size

### 983.0 Fine sand cum 0.47 850


### 2261.0 Carriage of Fine sand (1 part badarpur sand : 2 cum 0.47 106.13

### parts Sand)

### 367.0 Portland Cement (0.2225 cum) tonne 0.13 4940

### 2209.0 Carriage of Cement tonne 0.13 94.34

### LABOUR

### 40.0 Mason (average) day 0.1 403.67

### 17.0 Beldar day 1.63 350.00

### 11.0 Bhisti day 0.7 350.00

### 2.0 Hire charges of Concrete Mixer 0.25 to day 0.07 800

### 0.40 cum with hooper

### 12.0 Vibrator(Needle type 40mm) day 0.07 370

### 9999.0 Sundries L.S. 8.97 2

### TOTAL

### Add 1 % Water charges on "W"

### TOTAL

### Add GST (multiplying factor 0.1405) on "X"

### TOTAL

### Add 15 % Contractor's profit and overheads on "Y"

### Total

### Add Cess @ 1% on "Z"

### Cost of 1 cum.

### Say

###
###
4.1.12 1:2:3½:9 (1 ordinary portland cement : 2 Fly ash : 3½
coarse sand) : 9 graded stone aggregate 40 mm
### nominal size)
### Details of cost for 1 cum.

###
### MATERIAL

### 293.0 Stone Aggregate (Single size) : 40 mm nominal size cum 0.65 760

### (0.70 cum-7.5% for voids i.e. 0.05 = 0.65 cum)

### 295.0 Stone Aggregate (Single size) : 20 mm nominal size cum 0.24 800

### 2206.0 Carriage of Stone aggregate 40 mm nominal size cum 0.65 115.36
### and above

### 2202.0 Carriage of Stone aggregate below 40 mm nominal cum 0.24 584.88

### size

### 982.0 Coarse sand cum 0.37 800

### 2203.0 Carriage of Coarse sand cum 0.37 584.88

### 1980.0 Flyash cum 0.21 10

### 2262.0 Carriage of Flyash cum 0.21 106.13

### 367.0 Portland Cement tonne 0.17 4375

### 2209.0 Carriage of Cement tonne 0.17 94.34

### LABOUR

### 40.0 Mason (average) day 0.1 403.67

### 17.0 Beldar day 1.63 350.00

### 11.0 Bhisti day 0.7 350.00

### 2.0 Hire charges of Concrete Mixer 0.25 to day 0.07 800

### 0.40 cum with hooper

### 12.0 Vibrator(Needle type 40mm) day 0.07 370

### 9999.0 Sundries L.S. 14.3 2

### TOTAL

### Add 1 % Water charges on "W"

### TOTAL

### Add GST (multiplying factor 0.1405) on "X"

### TOTAL

### Add 15 % Contractor's profit and overheads on "Y"

### Total

### Add Cess @ 1% on "Z"

### Cost of one cum.

### Say

###
###
4.1.13 1:2½:4:11 (1 ordinary portland cement : 2½ fly ash : 4
coarse sand) : 11 graded stone aggregate 40 mm
### nominal size)
### Details of cost for 1 cum.

###
### MATERIAL

### 293.0 Stone Aggregate (Single size) : 40 mm nominal size cum 0.65 760

### (0.70 cum-7.5% for voids i.e. 0.05 = 0.65 cum)

### 295.0 Stone Aggregate (Single size) : 20 mm nominal size cum 0.24 800

### 2206.0 Carriage of Stone aggregate 40 mm nominal size cum 0.65 115.36

### and above

### 2202.0 Carriage of Stone aggregate below 40 mm nominal cum 0.24 584.88

### size

### 982.0 Coarse sand cum 0.34 800

### 2203.0 Carriage of Coarse sand cum 0.34 584.88

### 1980.0 Flyash cum 0.21 10


### 2262.0 Carriage of Flyash cum 0.21 106.13

### 367.0 Portland Cement tonne 0.13 4375

### 2209.0 Carriage of Cement tonne 0.13 94.34

### LABOUR

### 40.0 Mason (average) day 0.1 403.67

### 17.0 Beldar day 1.63 350.00

### 11.0 Bhisti day 0.7 350.00

### 2.0 Hire charges of Concrete Mixer 0.25 to day 0.07 800

### 0.40 cum with hooper

### 12.0 Vibrator(Needle type 40mm) day 0.07 370

### 9999.0 Sundries L.S. 14.3 2

### TOTAL

### Add 1 % Water charges on "W"

### TOTAL

### Add GST (multiplying factor 0.1405) on "X"

### TOTAL

### Add 15 % Contractor's profit and overheads on "Y"

### Total

### Add Cess @ 1% on "Z"

### Cost of one cum.

### Say

###
###
4.2 Providing and laying cement concrete in retaining
walls, return walls, walls (any thickness) including
### attached pilasters, columns, piers, abutments, pillars,
### posts,
the coststruts, buttresses,
of centering, string or
shuttering lacing
and courses,
finishing :
###
4.2.2 1:1½:3 (1 cement : 1½ coarse sand) : 3 graded stone
aggregate 20 mm nominal size).
###
### Details of cost for 1 cum.

### MATERIAL

### 295.0 Stone Aggregate (Single size) : 20 mm nominal size cum 0.57 800

### 297.0 Stone Aggregate (Single size) : 10 mm nominal size cum 0.28 810

### 2202.0 Carriage of Stone aggregate below 40 mm nominal cum 0.85 584.88

### size

### 982.0 Coarse sand cum 0.425 800

### 2203.0 Carriage of Coarse sand cum 0.425 584.88

### 367.0 Portland Cement (0.2833 cum) tonne 0.4 4375

### 2209.0 Carriage of Cement tonne 0.4 94.34

### LABOUR

### 17.0 Beldar day 0.9 350.00

### 18.0 Coolie day 0.78 350.00

### 11.0 Bhisti day 0.7 350.00

### 23.0 Mason (brick layer) 1st class day 0.06 505.17

### 24.0 Mason (brick layer) 2nd class day 0.06 403.67
### 2.0 Hire charges of Concrete Mixer 0.25 to day 0.07 800

### 0.40 cum with hooper

### 12.0 Vibrator(Needle type 40mm) day 0.07 370

### 9999.0 Scaffolding L.S. 114.4 2

### 9999.0 Sundries L.S. 14.3 2

### 18.0 Coolie day 1.88 350.00

### (Extra labour for lifting material upto floor

### V level = 0.75 x 2.5 = 1.88)

### TOTAL

### Add 1 % Water charges on "W"

### TOTAL

### Add GST (multiplying factor 0.1405) on "X"

### TOTAL

### Add 15 % Contractor's profit and overheads on "Y"

### Total

### Add Cess @ 1% on "Z"

### Cost of 1 cum.

### Say

###
###
4.2.3 1:2:4 (1 Cement : 2 coarse sand : 4 graded stone
aggregate 20 mm nominal size)
###
### Details of cost for 1 cum.

### MATERIAL

### 296.0 Stone Aggregate (Single size) : 20 mm nominal size cum 0.67 810

### 297.0 Stone Aggregate (Single size) : 10 mm nominal size cum 0.22 810

### 2202.0 Carriage of Stone aggregate below 40 mm nominal cum 0.89 584.88

### size

### 982.0 Coarse sand cum 0.445 800

### 2203.0 Carriage of Coarse sand cum 0.445 584.88

### 367.0 Portland Cement (0.2833 cum) tonne 0.32 4375

### 2209.0 Carriage of Cement tonne 0.32 94.34

### LABOUR

### 17.0 Beldar day 0.9 350.00

### 18.0 Coolie day 0.78 350.00

### 11.0 Bhisti day 0.7 350.00

### 23.0 Mason (brick layer) 1st class day 0.06 505.17

### 24.0 Mason (brick layer) 2nd class day 0.06 403.67

### 2.0 Hire charges of Concrete Mixer 0.25 to day 0.07 800

### 0.40 cum with hooper

### 12.0 Vibrator(Needle type 40mm) day 0.07 370

### 9999.0 Scaffolding L.S. 114.4 2

### 9999.0 Sundries L.S. 14.3 2

### 18.0 Coolie day 1.88 350.00


### (Extra labour for lifting material upto floor

### V level = 0.75 x 2.5 = 1.88)

### TOTAL

### Add 1 % Water charges on "W"

### TOTAL

### Add GST (multiplying factor 0.1405) on "X"

### TOTAL

### Add 15 % Contractor's profit and overheads on "Y"

### Total

### Add Cess @ 1% on "Z"

### Cost of 1 cum.

### Say

###
###
4.2.5 1:3:6 (1 cement : 3 coarse sand : 6 graded stone
aggregate 20 mm nominal size)
###
### Details of cost for 1 cum.

### MATERIAL

### 295.0 Stone Aggregate (Single size) : 20 mm nominal size cum 0.7 800

### 297.0 Stone Aggregate (Single size) : 10 mm nominal size cum 0.24 810

### 2202.0 Carriage of Stone aggregate below 40 mm nominal cum 0.94 584.88

### size

### 982.0 Coarse sand cum 0.47 800

### 2203.0 Carriage of Coarse sand cum 0.47 584.88

### 367.0 Portland Cement (0.15674 cum) tonne 0.22 4375

### 2209.0 Carriage of Cement tonne 0.22 94.34

### LABOUR

### 17.0 Beldar day 0.9 350.00

### 18.0 Coolie day 0.78 350.00

### 11.0 Bhisti day 0.7 350.00

### 23.0 Mason (brick layer) 1st class day 0.06 505.17

### 24.0 Mason (brick layer) 2nd class day 0.06 403.67

### 2.0 Hire charges of Concrete Mixer 0.25 to day 0.07 800

### 0.40 cum with hooper

### 12.0 Vibrator(Needle type 40mm) day 0.07 370

### 9999.0 Scaffolding (17.60x2.5 avg.) L.S. 114.4 2

### 9999.0 Sundries L.S. 13.52 2

### 18.0 Coolie day 1.88 350.00

### (Extra labour for lifting material upto floor

### V level = 0.75 x 2.5 = 1.88)

### TOTAL

### Add 1 % Water charges on "W"

### TOTAL

### Add GST (multiplying factor 0.1405) on "X"


### TOTAL

### Add 15 % Contractor's profit and overheads on "Y"

### Total

### Add Cess @ 1% on "Z"

### Cost of 1 cum.

### Say

###
###
4.2.8 1:5:10 (1 cement : 5 coarse sand) : 10 graded stone
aggregate 40 mm nominal size).
###
### Details of cost for 1 cum.

### MATERIAL

### 293.0 Stone Aggregate (Single size) : 40 mm nominal size cum 0.65 760

### 295.0 Stone Aggregate (Single size) : 20 mm nominal size cum 0.24 800

### 2206.0 Carriage of Stone aggregate 40 mm nominal size cum 0.65 115.36

### and above

### 2202.0 Carriage of Stone aggregate below 40 mm nominal cum 0.24 584.88

### size

### 982.0 Coarse sand cum 0.47 800

### 2203.0 Carriage of Coarse sand cum 0.47 584.88

### 367.0 Portland Cement tonne 0.13 4375

### 2209.0 Carriage of Cement tonne 0.13 94.34

### LABOUR

### 17.0 Beldar day 0.9 350.00

### 18.0 Coolie day 0.78 350.00

### 11.0 Bhisti day 0.7 350.00

### 23.0 Mason (brick layer) 1st class day 0.1 505.17

### 2.0 Hire charges of Concrete Mixer 0.25 to day 0.07 800

### 0.40 cum with hooper

### 12.0 Vibrator(Needle type 40mm) day 0.07 370

### 9999.0 Scaffolding L.S. 114.4 2

### 9999.0 Sundries L.S. 14.3 2

### 18.0 Coolie day 1.88 350.00

### (Extra labour for lifting material upto floor

### V level = 0.75 x 2.5 = 1.88)

### TOTAL

### Add 1 % Water charges on "W"

### TOTAL

### Add GST (multiplying factor 0.1405) on "X"

### TOTAL

### Add 15 % Contractor's profit and overheads on "Y"

### Total

### Add Cess @ 1% on "Z"

### Cost of 1 cum.


### Say

###
###
4.3 Centering and shuttering including strutting,
propping etc. and removal of form work for :
###
###
4.3.1 Foundations, footings, bases for columns
###
### Details of cost for footing size 2.7mx2.7mx1.00m

###
### Contact area = 10.8 sqm.

###
### MATERIAL

###
### Assuming shuttering material will become unserviceable
after use of 40 times Adding for maintenance @ 10% of cost
### after
Takingfullsalvage
use of value
material @ 25% of cost

### 7319.0 Wall form panel 1250x500 mm each 0.34 860

### Qty taken for cost of using once =

### 16x0.85/40 = 0.34

### 7326.0 Corner angle 45x45x5 mm 1.50 m long each 0.085 240
### Qty taken for cost of using once =

### 4x0.85/40 = 0.085

### 7327.0 100 mm channel shoulder 2.5 m long each 0.17 910
### Qty taken for cost of using once =

### 8x0.85/40= 0.17

### 7328.0 Double clip ( bridge clip) each 0.34 76


### Qty taken for cost of using once =

### 16x0.85/40 = 0.34

### 7329.0 Single clip each 0.17 59


### Qty taken for cost of using once =

### 8x0.85/40 = 0.17

### 7330.0 M.S. tube 40 mm dia metre 0.23 215


### Qty taken for cost of using once =

### 10.8x0.85/40 = 0.2295

### 9999.0 Assembly nuts & bolts L.S. 22.1 2


### 9977.0 Carriage L.S. 78 2
### LABOUR

### 19.0 Fitter (grade 1) day 0.75 505.17


### 17.0 Beldar day 1.5 350.00
### 9999.0 Shuttering oil L.S. 52 2
### 9999.0 Sundries L.S. 26 2
### TOTAL

### Add 1 % Water charges on "W"

### TOTAL

### Add GST (multiplying factor 0.1405) on "X"


### TOTAL

### Add 15 % Contractor's profit and overheads on "Y"

### Total

### Add Cess @ 1% on "Z"

### Cost for 10.8 sqm.

### Cost per sqm.

### Say

###
###
4.3.2 Retaining walls, return walls, walls (any thickness)
including attached pilasters, buttresses, plinth and
### string courses fillets, kerbs and steps etc.
### Details for 7.9m long and 1.00m high wall Area of

###
### contact 2x7.9x1.0 = 15.8 sqm.

### MATERIAL

###
### Assuming shuttering material will become unserviceable
after use of 40 times Adding for maintenance @ 10% of cost
### after fullsalvage
Taking use of value
material @ 25% of cost

### 7319.0 Wall form panel 1250x500 mm each 0.51 860

### Qty taken for cost of using once =

### 24x0.85/40 = 0.51

### 7327.0 100 mm channel shoulder 2.5 m long each 0.17 910

### Qty taken for cost of using once =

### 8x0.85/40 = 0.17

### 7328.0 Double clip ( bridge clip) each 0.51 76

### Qty taken for cost of using once =

### 24x0.85/40 = 0.51

### 7329.0 Single clip each 0.255 59

### Qty taken for cost of using once =

### 12x0.85/40 = 0.255

### 7330.0 M.S. tube 40 mm dia metre 0.68 215

### Qty taken for cost of using once =

### 32x0.85/40 = 0.68

### 9999.0 Nut & Bolts L.S. 27.62 2

### 9977.0 Carriage L.S. 78 2

### LABOUR

### 19.0 Fitter (grade 1) day 3.5 505.17

### 17.0 Beldar day 6 350.00

### 9999.0 Shuttering oil L.S. 78 2

### 9999.0 Sundries L.S. 52 2

### TOTAL

### Add 1 % Water charges on "W"

### TOTAL

### Add GST (multiplying factor 0.1405) on "X"


### TOTAL

### Add 15 % Contractor's profit and overheads on "Y"

### Total

### Add Cess @ 1% on "Z"

### Cost for 15.8 sqm.

### Cost per sqm.

### Say

###
###
4.3.3 Columns, piers, abutments, pillars, posts and struts
###
### Detail of cost for

###
### Size of column 450x450mm and 2.5m high Area of

###
### contact = 4x0.45x2.5 = 4.5 sqm.

### MATERIAL

###
### Assuming shuttering will become unserviceable after use of
40 times Add maintenance charges @ 10% of cost of
### material
### Less salvage value of material after full use @ 25% of cost
of material
###
### 7331.0 Wall form panel 1250x450 mm each 0.17 860
### Qty taken for cost of using once =

### 8x0.85/40 = 0.17

### 7332.0 Corner angle 45x45x5 m 2.50 m long each 0.085 255
### Qty taken for cost of using once =

### 4x0.85/40 = 0.085

### 7333.0 Column clamp 450x1070 m each 0.106 965


### Qty taken for cost of using once =

### 5x0.85/40 = 0.1063

### 7334.0 Prop 2 m ( 2-3.5m) each 0.085 635


### Qty taken for cost of using once =

### 4x0.85/40 = 0.085

### 9999.0 Assembly nut & bolt L.S. 27.62 2

### 9977.0 CARRIAGE LABOUR L.S. 52 2

### 19.0 Fitter (grade 1) day 1 505.17

### 17.0 Beldar day 2 350.00

### 9999.0 Shuttering oil L.S. 39 2

### 9977.0 Carriage L.S. 26 2

### TOTAL

### Add 1 % Water charges on "W"

### TOTAL

### Add GST (multiplying factor 0.1405) on "X"


### TOTAL

### Add 15 % Contractor's profit and overheads on "Y"

### Total

### Add Cess @ 1% on "Z"

### Cost for 4.5 sqm.

### Cost per sqm.

### Say

###
###
4.4 Providing and laying cement concrete in kerbs, steps
and the like at or near ground level excluding the
### cost of centering, shuttering and finishing.
###
4.4.1 1:1½:3 (1 Cement: 1½ coarse sand) : 3 graded stone
aggregate 20 mm nominal size)
###
### Details of cost for Plain window sill 15 nos. 15x1m x

###
### 0.20m x 0.15m = 0.45cum. Details of cost for kerb :

###
### 100m long 20cm deep and 30cm wide 100m x

###
### 0.30m x 0.20m = 6.00 cum. Cement concrete 1:2:4

###
###
4.1.2 Rate as per Item No.4.1.2 of cum 6 6051.00

### SH:CONCRETE WORK

###
### Cost for 6 cum.

### Cost per cum.

### Say

###
###
###
###
4.5 Providing and fixing up to floor five level precast
cement concrete string or lacing courses, copings,
###
4.5.1 1:1.5:3
bed (1 cement
plates, anchor:blocks,
1.5 coarse
plain sand)
window: 3 graded
sills, stone
aggregate 20mm nominal size)
### shelves,
Detail louvers,
of cost steps,
for plain stair
window sillcases,
15 No. etc.,
15x1 including
mtrx0.20mt.x0.15mtr,=0.45 Cum
###
### MATERIAL

### Cement concrete 1:1½:3

###
4.1.2 Rate as per Item Number 4.1.2 of SH: Concrete cum 0.45 6051.00

### work

### 18.0 Coolie day 0.51 350.00

### (Extra labour for lifting = 0.45 x 0.45 x

### 2.5 = 0.51)

### Centering and shuttering

### (1) Mould

### (i) Plate 3mm thick


### (2x1x0.15)+(2x0.15x0.20) = 0.36 sqm.

### @ 23.55kg/m2 = 8.48 kg.

### (ii) Flat 10x5mm

### 4x1.0 = 4.0m

### 8x0.2 = 1.6m

### 4x0.15 = 0.60m

### Handle 2x0.25 = 0.5m

### 6.70m @ 0.4kg/m = 2.68 kg.

### Total = 11.16kg. or 0.112 qtl. Assuming shuttering

### will become unserviceable after use of 40 times and

### taking 75% credit.

### Qty taken for cost of using once = 0.112x

### 0.75/40 = 0.0021 qtl = 0.21 kg

### 10.1 Rate as per item no.10.1 S.H. steel work kg 0.21 88.10

### (2) Moulding Platform

### Assuming platform will become unserviceable after

### use of 40 times.

### (i) Brick on edge flooring cement mortar 1:6

### 1x2.0x2.0m = 4 sqm.

### Qty taken for cost of using once =

### 4/40 = 0.1 sqm

###
11.1.2 Rate as per item no. 11.1.2 of sqm 0.1 704.55

### S.H.: Flooring work

### (ii) 25mm thick cement concrete 1:2:4 in pavement

### 2.00x2.00x0.025 = 0.10cum

###
### Qty taken for cost of using once =

### 0.100/40 = 0.0025 cum

### 11.7 Rate as per item no. 11.7 of S.H.: Flooring work cum 0.0025 6281.3

### 9999.0 Mortar and labour for hoisting and finishing L.S. 36.3 2

### TOTAL

### Add 1 % Water charges on "W-A" 251.10


### TOTAL

### Add GST (multiplying factor 0.1405) on "X-A" 253.61


### TOTAL

### Add 15 % Contractor's profit and overheads on "Y- 289.24


### A"

### Total

### Add Cess @ 1% on "Z-A" 332.63


### Cost for 0.45 cum.

### Cost per cum.

### Say

###
### 4.6 Providing and fixing at or near ground level
precast cement concrete in kerbs, edgings etc. as per
### approved pattern and setting in position with cement
### mortar
complete. 1:3 (1 Cement : 3 coarse sand), including the
###
4.6.1 1:1½:3 (1 Cement: 1½ coarse sand) : 3 graded stone
aggregate 20 mm nominal size).
###
### Details of cost for 25 no kerbs, 40x30x20cm

### =25 no x 0.40m x 0.30m x 0.20m = 0.6 cum

### MATERIAL

### Cement concrete 1:1.5:3

###
4.1.2 Rate as per Item No.4.1.2 of cum 0.6 6051.00

### SH:CONCRETE WORK

### Centering and shuttering

### (1) Mould

### (i) Plate 3mm thick

### 0.28 sqm. @ 23.55kg/m2 = 6.59 kg.

### (ii) Flat 10x5mm

### Handle

### 2x0.25 x0.4 = @ 0.4kg/m = 0.20 kg.

### = 6.79kg. or 0.068 qtl.

### Assuming shuttering will become unserviceable

### after use of 40 times and taking 75% credit.

### Qty taken for cost of using once

### = 0.068x0.75/40 = 0.001275 qtl = 0.1275 kg

### 10.1 Rate as per item no.10.1 S.H. steel work kg 0.1275 88.10

### (2) Moulding Platform

### Assuming platform will become unserviceable after

### use of 40 times.

### (i) Brick on edge flooring cement mortar 1:6

### 1x2.0x2.0m = 4 sqm.

### Qty taken for cost of using once = 4/40 = 0.1 sqm

###
11.1.2 Rate as per item no. 11.1.2 S.H.: Flooring work. sqm 0.1 704.55

### (ii) 25mm thick cement concrete 1:2:4 in pavement

### 2.00x2.00x0.025 = 0.100

### Qty taken for cost of using once

### = 0.100/40 = 0.0025 cum

###
### 11.7 Rate as per Item Number 11.7 of SH: Flooring cum 0.003 6281.3

### 9999.0 Mortar and labour for finishing L.S. 30.54 2

### TOTAL

### Add 1 % Water charges on "W-A" 61.08


### TOTAL

### Add GST (multiplying factor 0.1405) on "X-A" 61.69


### TOTAL
### Add 15 % Contractor's profit and overheads on "Y- 70.36
### A"

### Total

### Add Cess @ 1% on "Z-A" 80.91


### Cost for 0.6 cum.

### Cost per cum.

### Say

###
###
4.7 Providing and fixing up to floor five level precast
cement concrete solid block, including hoisting and
### setting in position with cement mortar 1:3 (1 cement :
### 3 coarse
sand), cost of required centering, shuttering
complete :
###
4.7.1 1:1½:3 (1 Cement: 1½ coarse sand) : 3 graded stone
aggregate 20 mm nominal size) .
###
### Details of cost for 25 no blocks, 40x20x30cm =25 no x 0.40m
x 0.30m x 0.20m = 0.6 cum
### MATERIAL

###
### Cement concrete 1:1.5:3

###
4.1.2 Rate as per Item No.4.1.2 of cum 0.6 6051.00

### SH:CONCRETE WORK

### Centering and shuttering

### (1) Mould

### (i) Plate 3mm thick

### 0.28 sqm. @ 23.55kg/m2 = 6.59 kg.

### (ii) Flat 10x5mm

### Handle

### 2x0.25 x0.4 = @ 0.4kg/m = 0.20 kg.

### = 6.79kg. or 0.068 qtl.

### Assuming shuttering will become unserviceable

### after use of 40 times and taking 75% credit.

### Qty taken for cost of using once = 0.068x

### 0.75/80 = 0.001275 qtl = 0.1275 kg

### 10.1 Rate as per item no.10.1 S.H. steel work kg 0.1275 88.10

### (2) Moulding Platform

### Assuming platform will become unserviceable after

### use of 40 times.

### (i) Brick on edge flooring cement mortar 1:6

### 1x2.0x2.0m = 4 sqm.

### Qty taken for cost of using once =

### 4/40 = 0.1 sqm

###
11.1.2 Rate as per item no. 11.1.2 S.H.: Flooring work. sqm 0.1 704.55

### (ii) 25mm thick cement concrete 1:2:4 in pavement

### 2.00x2.00x0.025 = 0.100

### Qty taken for cost of using once


### = 0.100/40 = 0.0025 cum

###
11.7 Rate as per Item Number 11.7 of cum 0.0025 6281.3

### SH:Flooring

### Mortar 1:3 for Fixing

### 0.202/100x25=0.051

### 3.8 Rate as per Item No 3.8 cum 0.051 4469.5

### Extra for Labour for lifting

### (27/100x25=0.675 or 0.68)

### 18.0 Coolie day 0.68 350.00

### Labour for hoisting and setting in position

### 23.0 Mason (brick layer) 1st class day 0.6 505.17

### 17.0 Beldar day 3.6 350.00

### Total

### Add 1 % Water charges on "W-A" 2029.04


### TOTAL

### Add GST (multiplying factor 0.1405) on "X-A" 2049.33


### TOTAL

### Add 15 % Contractor's profit and overheads on "Y- 2337.26


### A"

### Total

### Add Cess @ 1% on "Z-A" 2687.85


### Cost for 0.6 cum.

### Cost per cum.

### Say

###
###
###
### 4.8 Providing and fixing up to floor five level
precast cement concrete hollow block, including
### sand), cost of required centering, shuttering
hoisting and setting in position with cement mortar
complete.
### 1:3 (1 cement
4.8.1 : 3 (1
1:1½:3 coarse
Cement: 1½ coarse sand): 3
graded stone aggregate 20 mm nominal size) .
###
### Details of cost for one block of overall size 1m x 0.50m and
0.10m thick having 6 vertical hollows, 40x20x30cm finished
### 0.05cum = 1mx0.5mx0.1m =
contents
### MATERIAL

###
### Cement concrete 1:1.5:3

###
### Net qty = 0.05[6x0.5x{2x1/2(0.05+7)}x0.074] =

###
### 0.023cum

###
4.1.2 Rate as per Item No.4.1.2 of cum 0.023 6051.00

### SH:CONCRETE WORK

### 9999.0 Centering and shuttering including T&P charges, L.S. 26.91 2
### hire charges of steel mould, table vibrator, rammer,

### bolts nuts & washers etc. Cement mortar 1:2 for

### fixing

### 3.7 Rate as per Item No.3.7 of SH:MORTARS cum 0.002 5174.53

### LABOUR

### Extra Labour for lifting material upto floor V level

### 18.0 Coolie day 0.056 350.00

### Labour for hoisting and setting in position

### 23.0 Mason (brick layer) 1st class day 0.05 505.17

### 17.0 Beldar day 0.3 350.00

### TOTAL

### Add 1 % Water charges on "W-A" 214.03


### TOTAL

### Add GST (multiplying factor 0.1405) on "X-A" 216.17


### TOTAL

### Add 15 % Contractor's profit and overheads on "Y- 246.54


### A"

### Total

### Add Cess @ 1% on "Z-A" 283.52


### Cost for 0.05 cum.

### Cost per cum.

### Say

###
###
4.9 Precasting and placing in position 125 mm dia
Bollards 600 mm high of required shape including
### at specified
providing spacing.
M.S. Pipe Sleeve 50 mm dia 300 mm long in
### the Bollard
Details and
of Cost forM.S. Pipes 40 mm dia and 450mm
one bollard

###
### MATERIAL

###
### Cement concrete 1:2:4

###
### 3.14/4x(0.125)x(0.125)x0.60 = 0.007 cum

###
5.1.3 Rate as per Item no. 5.1.3 SH : RCC cum 0.007 6234.1

### Centering and shuttering

### 3.14x(0.125)x0.60 = 0.24 sqm

###
5.9.1 Rate as per Item no. 5.9.1 SH : RCC sqm 0.24 216.45

### M.S. pipes ( medium class)

### 50 mm dia sleeve =1x0.30x5.10 =1.53 kg

### 40 mm dia pipe =1x0.45x3.61 =1.62 kg

### M.S. plate 3mm thick =(0.15x0.15)x

### 23.55 =0.53 kg

### Total =3.68 kg

### 10.1 Rate as per Item no.10.1SH : Steel work kg 3.68 88.10
### Excavation

### 0.25x0.25x0.45 = 0.03 cum

###
2.8.1 Rate as per Item no. 2.8.1 SH : Earth work Cement cum 0.03 171.4

### concrete 1:3:6

###
4.1.5 Rate as per Item no. 4.1.5 SH : Cement concrete cum 0.03 5424.85

### 6 mm rendering (1:3) (0.24+0.01) = 0.25 sqm

### 5.2 Rate as per Item no. 5.23 SH : RCC sqm 0.25 142.35

### 9988.0 Carriage and fixing charges L.S. 13 2

### TOTAL

### Add 1 % Water charges on "W-A" 26.00


### TOTAL

### Add GST (multiplying factor 0.1405) on "X-A" 26.26


### TOTAL

### Add 15 % Contractor's profit and overheads on "Y- 29.95


### A"

### Total

### Add Cess @ 1% on "Z-A" 34.44


### Cost for one bollard

### Say

###
###
4.10 Providing and laying damp-proof course 40mm thick
with cement concrete 1:2:4 (1 cement : 2 coarse
### Details of cost for 10 sqm
sand): 4 graded stone aggregate 12.5mm nominal
### size)
MATERIAL

### Cement concrete 1:2:4 (1 cement : 2 coarse sand : 4 graded


stone aggregate 12.5 mm nominal size) 10x0.040 = 0.40 cum
###
4.1.3 Rate as per item no 4.1.3 of cum 0.4 5924.90

### SH: Concrete work

### Add deduct for difference of cost between

### 20mm size and 12.5mm size

### 295.0 Stone Aggregate (Single size) : 20 mm nominal size cum -0.67 800

### 296.0 Stone Aggregate (Single size) : 12.5 mm nominal cum 0.67 810

### size Add for delay

### 23.0 Mason (brick layer) 1st class day 0.4 505.17

### 24.0 Mason (brick layer) 2nd class day 0.4 403.67

### 9999.0 Sundries (Form work etc.) L.S. 1.95 2

### TOTAL

### Add 1 % Water charges on "W-A" 374.14


### TOTAL

### Add GST (multiplying factor 0.1405) on "X-A" 377.88


### TOTAL

### Add 15 % Contractor's profit and overheads on "Y-A" 430.97


### Total

### Add Cess @ 1% on "Z-A" 495.62


### Cost for 10 sqm
### Cost for 1 sqm

### Say

###
###
4.11 Providing and laying damp-proof course 50mm thick
with cement concrete 1:2:4 (1 cement : 2 coarse
### Details of cost for 10 sqm
sand) : 4 graded stone aggregate 20mm nominal
### size).
MATERIAL

### Cement concrete 1:2:4 = 10x0.05 = 0.50 cum

###
4.1.3 Rate as per item no 4.1.3 of SH:Concrete work Add cum 0.5 5954.35

### for delay :

### 23.0 Mason (brick layer) 1st class day 0.4 505.17

### 24.0 Mason (brick layer) 2nd class day 0.4 403.67

### 9999.0 Sundries (Form work etc.) L.S. 13.52 2

### TOTAL

### Add 1 % Water charges on "W-A" 390.58


### TOTAL

### Add GST (multiplying factor 0.1405) on "X-A" 394.49


### TOTAL

### Add 15 % Contractor's profit and overheads on "Y-A" 449.92


### Total

### Add Cess @ 1% on "Z-A" 517.41


### Cost for 10 sqm.

### Cost of 1 sqm.

### Say

###
###
4.12 Extra for providing and mixing water proofing
material in cement concrete work in doses by weight
### Details of cost for per bag of 50kg. of cement
of cement as per manufacturer's specification.
### MATERIAL

### Approved waterproofing’materials according to the

### recommended proportions

### 1213.0 Water proofing materials kilo 1 35

### gram

### 9988.0 Carriage of water proofing material and labour for L.S. 3.64 2

### mixing etc.

### TOTAL

### Add 1 % Water charges on "W"

### TOTAL

### Add GST (multiplying factor 0.1405) on "X"

### TOTAL

### Add 15 % Contractor's profit and overheads on "Y"

### Total

### Add Cess @ 1% on "Z"

### Cost per bag of cement of 50kg.

### Say
###
###
4.13 Providing & applying a coat of residual petroleum
bitumen of grade of VG-10 of approved quality using
### Details of cost for 10sqm.
1.7kg per square metre on damp proof course after
### cleaning
MATERIALthe surface with brushes and finally with

### 309.0 Paving bitumen VG-10 of approved quality tonne 0.017 48000

### 771.0 Kerosene oil litre 1.23 50


### Fuel for heating

### 370.0 Coal (steam) quintal 0.035 440

### 2211.0 Carriage of Tar bitumen tonne 0.017 106.13

### LABOUR

### Cleaning surface and applying kerosene oil

### 17.0 Beldar day 0.12 350.00

### Heating the material

### 18.0 Coolie day 0.07 350.00

### Spreading hot tar over damp proof course

### 31.0 Painter day 0.2 403.67

###
### 9988.0 Sundries (Carriage of kerosene, steam coal, L.S. 33.15 2

### brushes, T&P etc.)

### TOTAL

### Add 1 % Water charges on "W"

### TOTAL

### Add GST (multiplying factor 0.1405) on "X"

### TOTAL

### Add 15 % Contractor's profit and overheads on "Y"

### Total

### Add Cess @ 1% on "Z"

### Cost for 10 sqm.

### Cost of 1 sqm.

### Say

###
###
4.14 Extra for concrete work in superstructure above floor
V level for each four floors or part thereof.
### Details of cost per cum.

### Extra labour element required for lifting of

### materials (0.75x2.00 = 1.50)

### 18.0 Coolie day 1.5 350.00

### TOTAL

### Add 1 % Water charges on "W"

### TOTAL

### Add GST (multiplying factor 0.1405) on "X"

### TOTAL

### Add 15 % Contractor's profit and overheads on "Y"

### Total
### Add Cess @ 1% on "Z"

### Cost for 1 cum.

### Say

###
### 4.15 Extra for laying concrete in or under water
and/or liquid mud including cost of pumping or
### bailing out water and removing slush etc. complete.
### Details of cost for 14 cum per 0.3m depth Quantity

###
### of concrete = 14 cum.

### pumping hours = 3 hrs. or 0.375 day.

###
### 11.0 Hire charges of Pumpset of capacity 4000 day 0.375 700

### litres/hour.

### 17.0 Beldar for cleaning slush day 4 350.00

### TOTAL

### Add 1 % Water charges on "W"

### TOTAL

### Add GST (multiplying factor 0.1405) on "X"

### TOTAL

### Add 15 % Contractor's profit and overheads on "Y"

### Total

### Add Cess @ 1% on "Z"

### Cost of 14cum. per 0.30 m depth

### Cost of cum. per m depth

### Say

###
### 4.16 Extra for laying concrete in or under
### foul positions.
### Details of cost for 1 cum.

### Extra labour due to slow progress-

### 23.0 Mason (brick layer) 1st class day 0.02 505.17

### 24.0 Mason (brick layer) 2nd class day 0.02 403.67

### 17.0 Beldar day 0.25 350.00

### 18.0 Coolie day 0.15 350.00

### TOTAL

### Add 1 % Water charges on "W"

### TOTAL

### Add GST (multiplying factor 0.1405) on "X"

### TOTAL

### Add 15 % Contractor's profit and overheads on "Y"

### Total

### Add Cess @ 1% on "Z"

### Cost for 1 cum.


### Say

###
### 4.17 Making plinth protection 50mm thick of
cement concrete 1:3:6 (1 cement : 3 coarse sand : 6
### graded stone aggregate 20 mm nominal size) over
### 75mm thick bed of dry brick ballast 40 mm nominal
smooth.
### Detail of cost for 10 sqm

###
### MATERIAL

### 287.0 Brick Aggregate (Single size) : 40 mm nominal size cum 0.75 650

### 2260.0 Carriage of Brick aggregate cum 0.75 115.36

### 983.0 Fine sand cum 0.06 850


### 2261.0 Carriage of Fine sand (1 part badarpur sand : cum 0.06 106.13

### 2 parts Sand)

### Dressing the gound including cutting and filling upto

### 15cm

### 17.0 Beldar day 0.16 350.00

### 18.0 Coolie day 0.11 350.00

### MATERIAL

### Cement concrete 1:3:6 Qty. of cement concrete

### 1:3:6 on 10 sqm. area = 0.5cum.

### 295.0 Stone Aggregate (Single size) : 20 mm nominal size cum 0.35 800

### 297.0 Stone Aggregate (Single size) : 10 mm nominal size cum 0.12 810

### 2202.0 Carriage of Stone aggregate below 40 mm nominal cum 0.47 584.88

### size

### 982.0 Coarse sand cum 0.23 800

### 2203.0 Carriage of Coarse sand cum 0.23 584.88

### 367.0 Portland Cement tonne 0.11 4375

### 2209.0 Carriage of Cement tonne 0.11 94.34

### Labour (for C.C 1:3:6)

### 17.0 Beldar day 1 350.00

### 23.0 Mason (brick layer) 1st class day 0.05 505.17

### 11.0 Bhisti day 0.33 350.00

### 9999.0 Hire and runing charges of mechanical mixer L.S. 13.39 2

### 9999.0 Sundries L.S. 6.76 2

### LABOUR

### 40.0 Mason (average) day 0.27 403.67

### 17.0 Beldar day 1.08 350.00

### 18.0 Coolie day 1.08 350.00

### TOTAL

### Add 1 % Water charges on "W"

### TOTAL

### Add GST (multiplying factor 0.1405) on "X"

### TOTAL
### Add 15 % Contractor's profit and overheads on "Y"

### Total

### Add Cess @ 1% on "Z"

### Cost of 10.00 sqm

### Cost of 1.00 sqm

### Say

###
### 4.18 Extra for addition of synthetic Polyester
triangular fibre of length 12mm, effective diameter 10-
### 40 microns and specific gravity of 1.34 to 1.40 in
### cement
Charge. concrete/RCC/Flooring/water retaining
### Detail of cost for per bag of 50 kg of cement used in

### concrete

### MATERIAL

###
### 8732.0 Synthetic polyester triangular fibre of length 12mm, kg 0.125 365

### effective dia 10-40 microns and specific gravity of

### 1.34 to 1.40

### TOTAL

### Add 1 % Water charges on "W"

### TOTAL

### Add GST (multiplying factor 0.1405) on "X"

### TOTAL

### Add 15 % Contractor's profit and overheads on "Y"

### Total

### Add Cess @ 1% on "Z"

### Cost per bag of 50 kg of cement

### Say

###
###
###
### 4.19 Providing and laying in position ready
mixed plain cement concrete, using fly ash and
### Note : (1) Excess/less
cement content cement used
as per approved thanmix
design specified
and in
### this
(2) item is
manufactured payable/ recoverable
in fully automatic
Fly ash conforming separately.
to grade Ibatching
of IS 3812plant and
(Part-1)
only be used as part replacement of OPC as per IS :
### 456. Uniform blending with cement is to be ensured
### in accordance
4.19.1 with clauses
All works 5.2 and
upto plinth 5.2.1 of IS: 456 -
level:
###
### 4.19.1.1 M-15 grade plain cement concrete (cement
content considered @ 240 kg/cum)
###
### Details of cost for 1.00 cum

###
### MATERIAL

###
### 293.0 Stone Aggregate (Single size) : 40 mm nominal size cum 0.65 760
### (0.70 - 7.5% for voids i.e. 0.05 = 0.65 cum)

### 295.0 Stone Aggregate (Single size) : 20 mm nominal size cum 0.24 800

### 2206.0 Carriage of Stone aggregate 40 mm nominal size cum 0.65 115.36

### and above

### 2202.0 Carriage of Stone aggregate below 40 mm nominal cum 0.24 584.88

### size

### 982.0 Coarse sand cum 0.37 800

### 2203.0 Carriage of Coarse sand cum 0.37 584.88

### 1980.0 Flyash cum 0.21 10

### 2262.0 Carriage of Flyash cum 0.21 106.13

### 367.0 Portland Cement tonne 0.24 4375

### 2209.0 Carriage of Cement tonne 0.24 94.34

### 7318.0 Plasticizer / super plasticizer kilogra 1.2 36

### m

### Production cost, pumping to respective floors and

### laying in position

### 4.0 Production cost of concrete by batch mix plant. cum 1 350

### 29.0 Carriage of concrete by transit mixer. km/ 10 30

### cum

### 9.0 Pumping charges of concrete including Hire charges cum 1 210

### of pump, piping work & accessories etc.

### Labour for pouring, consolidating & curing

### 40.0 Mason (average) Day 0.17 403.67

### 17.0 Beldar Day 2 350.00

### 11.0 Bhisti Day 0.9 350.00

### 12.0 Vibrator(Needle type 40mm) Day 0.07 370

### 9999.0 Sundries L.S. 13 2

### Total

### Add 1 % Water charges on "W"

### TOTAL

### Add GST (multiplying factor 0.1405) on "X"

### TOTAL

### Add 15 % Contractor's profit and overheads on "Y"

### Total

### Add Cess @ 1% on "Z"

### Cost per 1.00 cum

### Say

###
###
###
### 4.19.1.2 M-10 grade plain cement concrete (cement
content
Details ofconsidered
cost for 1.00 @ 220 kg/cum)
### cum

### MATERIAL
###
### 293.0 Stone Aggregate (Single size) : 40 mm nominal size cum 0.65 760

### (0.70 - 7.5% for voids i.e. 0.05 = 0.65 cum)

### 295.0 Stone Aggregate (Single size) : 20 mm nominal size cum 0.24 800

### 2206.0 Carriage of Stone aggregate 40 mm nominal size cum 0.65 115.36

### and above

### 2202.0 Carriage of Stone aggregate below 40 mm nominal cum 0.24 584.88

### size

### 982.0 Coarse sand cum 0.37 800

### 2203.0 Carriage of Coarse sand cum 0.37 584.88

### 1980.0 Flyash cum 0.21 10

### 2262.0 Carriage of Flyash cum 0.21 106.13

### 367.0 Portland Cement tonne 0.22 4375

### 2209.0 Carriage of Cement tonne 0.22 94.34

### 7318.0 Plasticizer / super plasticizer Production cost, kilogra 1.1 36

### pumping to respec tive floors and laying in position m

### 4.0 Production cost of concrete by batch mix plant. cum 1 350

### 29.0 Carriage of concrete by transit mixer. km/ 10 30

### cum

### 9.0 Pumping charges of concrete including Hire charges cum 1 210

### of pump, piping work & accessories etc.

### Labour for pouring, consolidating & curing

### 40.0 Mason (average) day 0.17 403.67

### 17.0 Beldar day 2 350.00

### 11.0 Bhisti day 0.9 350.00

### 12.0 Vibrator(Needle type 40mm) day 0.07 370

### 9999.0 Sundries L.S. 13 2

### Total

### Add 1 % Water charges on "W"

### TOTAL

### Add GST (multiplying factor 0.1405) on "X"

### TOTAL

### Add 15 % Contractor's profit and overheads on "Y"

### Total

### Add Cess @ 1% on "Z"

### Cost per 1.00 cum

### Say

###
###
###
4.19.2 All works above plinth and upto floor V level:
###
4.19.2.1 M-15 grade plain cement concrete (cement content
considered @ 240 kg. / cum)
###
### Details of cost for 1.00 cum
### MATERIAL

### 293.0 Stone Aggregate (Single size) : 40 mm nominal size cum 0.65 760

### (0.70 - 7.5% for voids i.e. 0.05 = 0.65 cum)

### 295.0 Stone Aggregate (Single size) : 20 mm nominal size cum 0.24 800

### 2206.0 Carriage of Stone aggregate 40 mm nominal size cum 0.65 115.36

### and above

### 2202.0 Carriage of Stone aggregate below 40 mm nominal cum 0.24 584.88

### size

### 982.0 Coarse sand cum 0.37 800

### 2203.0 Carriage of Coarse sand cum 0.37 584.88

### 1980.0 Flyash cum 0.21 10

### 2262.0 Carriage of Flyash cum 0.21 106.13

### 367.0 Portland Cement tonne 0.24 4375

### 2209.0 Carriage of Cement tonne 0.24 94.34

### 7318.0 Plasticizer / super plasticizer kilogra 1.2 36

### Production cost, pumping to respective floors and m

###
### laying in position

### 4.0 Production cost of concrete by batch mix plant. cum 1 350

### 29.0 Carriage of concrete by transit mixer. km/ 10 30

### Labour for pouring, consolidating & curing cum

###
### 40.0 Mason (average) Day 0.17 403.67

### 17.0 Beldar Day 2 350.00

### 11.0 Bhisti Day 0.9 350.00

### 12.0 Vibrator(Needle type 40mm) Day 0.07 370

### 9999.0 Sundries L.S. 13 2

### (Extra labour for lifting material upto floor

### V level = 0.75 x 2.5 = 1.88)

### 18.0 Coolie day 1.88 350.00

### Total

### Add 1 % Water charges on "W"

### TOTAL

### Add GST (multiplying factor 0.1405) on "X"

### TOTAL

### Add 15 % Contractor's profit and overheads on "Y"

### Total

### Add Cess @ 1% on "Z"

### Cost per 1.00 cum

### Say

###
###
###
4.19.2.2 M-10 grade plain cement concrete (cement content
considered @ 220 kg/cum)
### Details of cost for 1.00 cum

### MATERIAL

### 293.0 Stone Aggregate (Single size) : 40 mm nominal size cum 0.65 760

### (0.70 - 7.5% for voids i.e. 0.05 = 0.65 cum)

### 295.0 Stone Aggregate (Single size) : 20 mm nominal size cum 0.24 800

### 2206.0 Carriage of Stone aggregate 40 mm nominal size cum 0.65 115.36

### and above

### 2202.0 Carriage of Stone aggregate below 40 mm nominal cum 0.24 584.88

### size

### 982.0 Coarse sand cum 0.37 800

### 2203.0 Carriage of Coarse sand cum 0.37 584.88

### 1980.0 Flyash cum 0.21 10

### 2262.0 Carriage of Flyash cum 0.21 106.13

### 367.0 Portland Cement tonne 0.22 4375

### 2209.0 Carriage of Cement tonne 0.22 94.34

### 7318.0 Plasticizer / super plasticizer kilogra 1.1 36

### Production cost, pumping to respective floors and m

### laying in position

### 4.0 Production cost of concrete by batch mix plant. cum 1 350

### 29.0 Carriage of concrete by transit mixer. km/ 10 30

### Labour for pouring, consolidating & curing cum

### 40.0 Mason (average) day 0.17 403.67

### 17.0 Beldar day 2 350.00

### 11.0 Bhisti day 0.9 350.00

### 12.0 Vibrator(Needle type 40mm) day 0.07 370

### 9999.0 Sundries L.S. 13 2

### (Extra labour for lifting material upto floor

### V level = 0.75 x 2.5 = 1.88)

### 18.0 Coolie day 1.88 350.00

### Total

### Add 1 % Water charges on "W"

### TOTAL

### Add GST (multiplying factor 0.1405) on "X"

### TOTAL

### Add 15 % Contractor's profit and overheads on "Y"

### Total

### Add Cess @ 1% on "Z"

### Cost per 1.00 cum

### Say

###
###
4.20 Providing and laying in position ready mixed plain
cement concrete, with cement content as per
### 1) Excess/less
approved designcement
mix andused than specified
manufactured in this
in fully
item is payable/ recoverable separately.
###
4.20.1 automatic
All works batching
upto plinthplant
leveland
: transported to site of
###
4.20.1.1 M-15 grade plain cement concrete (cement content
considered @ 240 kg/cum)
###
### Details of cost for 1.00 cum

###
### MATERIAL

### 293.0 Stone Aggregate (Single size) : 40 mm nominal size cum 0.65 760

### (0.70 - 7.5% for voids i.e. 0.05 = 0.65 cum)

### 295.0 Stone Aggregate (Single size) : 20 mm nominal size cum 0.24 800

### 2206.0 Carriage of Stone aggregate 40 mm nominal size cum 0.65 115.36

### and above

### 2202.0 Carriage of Stone aggregate below 40 mm nominal cum 0.24 584.88

### size

### 982.0 Coarse sand cum 0.47 800

### 2203.0 Carriage of Coarse sand cum 0.47 584.88

### 367.0 Portland Cement tonne 0.24 4375

### 2209.0 Carriage of Cement tonne 0.24 94.34

### 7318.0 Plasticizer / super plasticizer kilogra 1.2 36

### Production cost, pumping to respective floors and m

###
### laying in position

### 4.0 Production cost of concrete by batch mix plant. cum 1 350

### 29.0 Carriage of concrete by transit mixer. km/ 10 30

### cum

### 9.0 Pumping charges of concrete including Hire charges cum 1 210

### of pump, piping work & accessories etc.

###
### 40.0 Mason (average) day 0.17 403.67

### 17.0 Beldar day 2 350.00

### 11.0 Bhisti day 0.9 350.00

### 12.0 Vibrator(Needle type 40mm) day 0.07 370

### 9999.0 Sundries L.S. 13 2

### Total

### Add 1 % Water charges on "W"

### TOTAL

### Add GST (multiplying factor 0.1405) on "X"

### TOTAL

### Add 15 % Contractor's profit and overheads on "Y"

### Total

### Add Cess @ 1% on "Z"

### Cost per 1.00 cum

### Say

###
###
4.20.1.2 M-10 grade plain cement concrete (cement content
considered @ 220 kg/cum)
###
### Details of cost for 1.00 cum

### MATERIAL

### 293.0 Stone Aggregate (Single size) : 40 mm nominal size cum 0.65 760

### (0.70 - 7.5% for voids i.e. 0.05 = 0.65 cum)

### 295.0 Stone Aggregate (Single size) : 20 mm nominal size cum 0.24 800

### 2206.0 Carriage of Stone aggregate 40 mm nominal size cum 0.65 115.36

### and above

### 2202.0 Carriage of Stone aggregate below 40 mm nominal cum 0.24 584.88

### size

### 982.0 Coarse sand cum 0.47 800

### 2203.0 Carriage of Coarse sand cum 0.47 584.88

### 367.0 Portland Cement tonne 0.22 4375

### 2209.0 Carriage of Cement tonne 0.22 94.34

### 7318.0 Plasticizer / super plasticizer kilogra 1.1 36

### Production cost, pumping to respective floors and m

###
### laying in position

### 4.0 Production cost of concrete by batch mix plant. cum 1 350

### 29.0 Carriage of concrete by transit mixer. km/ 10 30

### cum

### 9.0 Pumping charges of concrete including Hire charges cum 1 210

### of pump, piping work & accessories etc.

### Labour for pouring, consolidating & curing

### 40.0 Mason (average) day 0.17 403.67

### 17.0 Beldar day 2 350.00

### 11.0 Bhisti day 0.9 350.00

### 12.0 Vibrator(Needle type 40mm) day 0.07 370

### 9999.0 Sundries L.S. 13 2

### Total

### Add 1 % Water charges on "W"

### TOTAL

### Add GST (multiplying factor 0.1405) on "X"

### TOTAL

### Add 15 % Contractor's profit and overheads on "Y"

### Total

### Add Cess @ 1% on "Z"

### Cost per 1.00 cum

### Say

###
###
###
###
###
4.20.2 All works above plinth and upto floor V level :
### 4.20.2.1 M-15 grade plain cement concrete.
### (cement content
Details of cost for 1.00considered
cum @ 240 kg. /cum)
### MATERIAL

### 293.0 Stone Aggregate (Single size) : 40 mm nominal size cum 0.65 760

### (0.70 - 7.5% for voids i.e. 0.05 = 0.65 cum)

### 295.0 Stone Aggregate (Single size) : 20 mm nominal size cum 0.24 800

### 2206.0 Carriage of Stone aggregate 40 mm nominal size cum 0.65 115.36

### and above

### 2202.0 Carriage of Stone aggregate below 40 mm nominal cum 0.24 584.88

### size

### 982.0 Coarse sand cum 0.47 800

### 2203.0 Carriage of Coarse sand cum 0.47 584.88

### 367.0 Portland Cement tonne 0.24 4375

### 2209.0 Carriage of Cement tonne 0.24 94.34

### 7318.0 Plasticizer / super plasticizer kilogra 1.2 36

### Production cost, pumping to respective floors and m

###
### laying in position

### 4.0 Production cost of concrete by batch mix plant. cum 1 350

### 29.0 Carriage of concrete by transit mixer. km/ 10 30

### Labour for pouring, consolidating & curing cum

### 40.0 Mason (average) day 0.17 403.67

### 17.0 Beldar day 2 350.00

### 11.0 Bhisti day 0.9 350.00

### 12.0 Vibrator(Needle type 40mm) day 0.07 370

### 9999.0 Sundries L.S. 13 2

### (Extra labour for lifting material upto floor

### V level = 0.75 x 2.5 = 1.88)

### 18.0 Coolie day 1.88 350.00

### Total

### Add 1 % Water charges on "W"

### TOTAL

### Add GST (multiplying factor 0.1405) on "X"

### TOTAL

### Add 15 % Contractor's profit and overheads on "Y"

### Total

### Add Cess @ 1% on "Z"

### Cost per 1.00 cum

### Say

###
###
###
###
### 4.20.2.2 M-10 grade plain cement concrete
### (cement content
Details of cost considered
for 1.00 cum @ 220 kg/cum)
### 293.0 Stone Aggregate (Single size) : 40 mm nominal size cum 0.65 760

### (0.70 - 7.5% for voids i.e. 0.05 = 0.65 cum)

### 295.0 Stone Aggregate (Single size) : 20 mm nominal size cum 0.24 800

### 2206.0 Carriage of Stone aggregate 40 mm nominal size cum 0.65 115.36

### and above

### 2202.0 Carriage of Stone aggregate below 40 mm nominal cum 0.24 584.88

### size

### 982.0 Coarse sand cum 0.47 800

### 2203.0 Carriage of Coarse sand cum 0.47 584.88

### 367.0 Portland Cement tonne 0.22 4375

### 2209.0 Carriage of Cement tonne 0.22 94.34

### 7318.0 Plasticizer / super plasticizer kilogra 1.1 36

### Production cost, pumping to respective floors and m

### laying in position

### 4.0 Production cost of concrete by batch mix plant. cum 1 350

### 29.0 Carriage of concrete by transit mixer. km/ 10 30

### Labour for pouring, consolidating & curing

### 40.0 Mason (average) day 0.17 403.67

### 17.0 Beldar day 2 350.00

### 11.0 Bhisti day 0.9 350.00

### 12.0 Vibrator(Needle type 40mm) day 0.07 370

### 9999.0 Sundries L.S. 13 2

### (Extra labour for lifting material upto floor

### V level = 0.75 x 2.5 = 1.88)

### 18.0 Coolie day 1.88 350.00

### Total

### Add 1 % Water charges on "W"

### TOTAL

### Add GST (multiplying factor 0.1405) on "X"

### TOTAL

### Add 15 % Contractor's profit and overheads on "Y"

### Total

### Add Cess @ 1% on "Z"

### Cost per 1.00 cum

### Say

###
###
###
###
###
SUB HEAD : 5.0
###
###
REINFORCED CEMENT CONCRETE
###
###
Code Description Unit Quantit Rate
y
###
###
5.1 Providing and laying in position specified
### grade of reinforced cement concrete,
###
5.1.2 excluding the cost of centering, shuttering,
1:1.5:3
finishing(1 and
cement : 1.5 coarse- All
reinforcement sand):
work3 up to
### graded stone aggregate 20 mm
### nominal size)
###
### Details of cost for 1 cum
###
### MATERIAL
### 295.0 Stone Aggregate (Single size) : 20 mm nominal cum 0.57 800
### 297.0 size cum 0.28 810
### Stone Aggregate (Single size) : 10 mm nominal
###2202.0 size
### Carriage of Stone aggregate below 40 mm cum 0.85 584.88
### 982.0 nominal size
### Coarse sand cum 0.425 1350
###2203.0 Carriage of Coarse sand cum 0.425 584.88
### 367.0 Portland Cement (0.2833 cum) tonne 0.4 4375
###2209.0 Carriage of Cement tonne 0.4 94.34
### LABOUR
### 40.0 Mason (average) day 0.17 403.67
### 17.0 Beldar day 2 350.00
### 11.0 Bhisti day 0.9 350.00
### 2.0 Hire charges of Concrete Mixer 0.25 to 0.40 day 0.07 800
### 12.0 cum with hooper
### Vibrator(Needle type 40mm) day 0.07 370
###9999.0 Sundries L.S. 14.3 2
### TOTAL
### Add 1 % Water charges on "W"
### TOTAL
### Add GST (multiplying factor 0.1405) on "X"
### TOTAL
### Add 15 % Contractor's profit and overheads on "Y"
### Total
### Add Cess @ 1% on "Z"
### Cost of 1 cum.
### Say
###
### 5.1.3 1:2:4 (1 cement : 2 coarse sand :
### 4 graded
Details stone
of cost for 1aggregate
cum 20 mm nominal
### size)
MATERIAL
### 295.0 Stone Aggregate (Single size) : 20 mm nominal cum 0.67 800
### 297.0 size cum 0.22 810
### Stone Aggregate (Single size) : 10 mm nominal
2202.0 size
Carriage of Stone aggregate below 40 mm cum 0.89 584.88
982.0 nominal size
Coarse sand cum 0.445 1350
2203.0 Carriage of Coarse sand cum 0.445 584.88
367.0 Portland Cement (0.2225 cum) tonne 0.32 4375
2209.0 Carriage of Cement tonne 0.32 94.34
LABOUR
40.0 Mason (average) day 0.17 403.67
17.0 Beldar day 2 350.00
11.0 Bhisti day 0.9 350.00
2.0 Hire charges of Concrete Mixer 0.25 to 0.40 day 0.07 800
12.0 cum with hooper
Vibrator(Needle type 40mm) day 0.07 370
9999.0 Sundries L.S. 14.3 2
TOTAL
Add 1 % Water charges on "W"
TOTAL
Add GST (multiplying factor 0.1405) on "X"
TOTAL
Add 15 % Contractor's profit and overheads on "Y"
Total
Add Cess @ 1% on "Z"
Cost of 1 cum.
Say

5.2 Reinforced cement concrete work in walls


(any thickness),
reinforcement : including attached
pilasters, buttresses, plinth and string
courses, fillets, columns, pillars, piers,
5.2.2 1:1.5:3 (1 cement : 1.5 coarse sand) : 3
graded stone aggregate 20 mm
nominal size)

Details of cost for 9.18 cum.

MATERIAL
295.0 Stone Aggregate (Single size) : 20 mm nominal cum 5.2326 800
297.0 size cum 2.5704 810
Stone Aggregate (Single size) : 10 mm nominal
size
2202.0 Carriage of Stone aggregate below 40 mm cum 7.803 584.88
982.0 nominal size
Coarse sand cum 3.9015 800
2203.0 Carriage of Coarse sand cum 3.9015 584.88
367.0 Portland Cement (0.2833 cum) tonne 3.672 4375
2209.0 Carriage of Cement tonne 3.672 94.34
LABOUR
17.0 Beldar day 11.29 350.00
18.0 Coolie day 7.53 350.00
11.0 Bhisti day 8.26 350.00
23.0 Mason (brick layer) 1st class day 0.92 505.17
24.0 Mason (brick layer) 2nd class day 0.92 403.67
2.0 Hire charges of Concrete Mixer 0.25 to day 0.64 800
0.40 cum with hooper
12.0 Vibrator(Needle type 40mm) day 0.64 370
9999.0 Sundries L.S. 131.82 2
9999.0 Scaffolding L.S. 420.03 2
Extra labour for lifting of material upto floor V
level:
0.75x9.18x2.5 = 17.21
18.0 Coolie day 17.21 350.00
TOTAL
Add 1 % Water charges on "W"
TOTAL
Add GST (multiplying factor 0.1405) on "X"
TOTAL
Add 15 % Contractor's profit and overheads on "Y"
Total
Add Cess @ 1% on "Z"
Cost for 9.18 cum.
Cost for 1 cum.
Say

5.3 Reinforced cement concrete work in


beams,
aggregate suspended floors, roofs
20 mm nominal size). having
slope up to 15° landings,
Details of cost for 1 cum.
balconies,
shelves, chajjas, lintels, bands, plain

MATERIAL
295.0 Stone Aggregate (Single size) : 20 mm nominal cum cum 0.57 800
size
297.0 Stone Aggregate (Single size) : 10 mm nominal cum 0.28 810
2202.0 size
Carriage of Stone aggregate below 40 mm cum 0.85 584.88
982.0 nominal size
Coarse sand cum 0.425 800
2203.0 Carriage of Coarse sand cum 0.425 584.88
367.0 Portland Cement (0.2833 cum) tonne 0.4 4375
2209.0 Carriage of Cement tonne 0.4 94.34
LABOUR
40.0 Mason (average) day 0.24 403.67
17.0 Beldar day 2.75 350.00
11.0 Bhisti day 0.9 350.00
2.0 Hire charges of Concrete Mixer 0.25 to day 0.08 800
0.40 cum with hooper
12.0 Vibrator(Needle type 40mm) day 0.08 370
9999.0 Sundries L.S. 14.3 2
Extra labour for lifting material upto floor V
level: Coolie (2.5x0.75=1.88)
18.0 Coolie day 1.88 350.00
TOTAL
Add 1 % Water charges on "W"
TOTAL
Add GST (multiplying factor 0.1405) on "X"
TOTAL
Add 15 % Contractor's profit and overheads on "Y"
Total
Add Cess @ 1% on "Z"
Cost for 1 cum.
Say

5.4 Providing and laying up to floor


five level
graded reinforced
stone aggregatecement concrete
20 mm in
nominal
kerbs,
size). steps and the
Details of cost for 1 cum.
like excluding the cost
of centering, shuttering, finishing and

MATERIAL

4.4.1 Cement concrete 1:1.5:3 cum 1 6051

(Rate as per item no 4.4.1 of SH:Concrete


work)
LABOUR

Extra labour for laying CC in RCC work :


17.0 Beldar day 0.1 350.00
11.0 Bhisti day 0.2 350.00
23.0 Mason (brick layer) 1st class day 0.04 505.17
24.0 Mason (brick layer) 2nd class day 0.04 403.67
28.0 Mate day 0.04 350.00
(Extra labour for lifting material upto floor
V level : Coolie = 0.75 x 2.5 = 1.88)
18.0 Coolie day 1.88 350.00
TOTAL
Add 1 % Water charges on "W-A" 813.36
TOTAL
Add GST (multiplying factor 0.1405) on "X-A" 821.49
TOTAL
Add 15 % Contractor's profit and overheads on 936.91
"Y-A"
Total
Add Cess @ 1% on "Z-A" 1077.45
Cost for 1 cum.
Say

5.5 Reinforced cement concrete work


in arches, archribs, domes, vaults, shells,
nominal size).
folded plate and roofs having slope more
than 15° up to floor five level, excluding the
Details of cost for 26.73cum for semicircular arch 6m clear
span and 9m long and 30cm
thick.
Cement concrete 1:1.5:3 =
1x0.50x3.14x6.30x9.00x0.30 = 26.73cum
MATERIAL

295.0 Stone Aggregate (Single size) : 20 mm nominal cum 15.236 800


297.0 size cum 7.484 810
Stone Aggregate (Single size) : 10 mm nominal
2202.0 size
Carriage of Stone aggregate below 40 mm cum 22.703 584.88
982.0 nominal size
Coarse sand cum 11.36 800
2203.0 Carriage of Coarse sand cum 11.36 584.88
367.0 Portland Cement (0.2833 cum) tonne 10.692 4375
2209.0 Carriage of Cement tonne 10.692 94.34
LABOUR
40.0 Mason (average) day 6.42 403.67
17.0 Beldar day 73.51 350.00
11.0 Bhisti day 24.06 350.00
2.0 Hire charges of Concrete Mixer 0.25 to day 2.14 800
0.40 cum with hooper
12.0 Vibrator(Needle type 40mm) day 2.14 370
9999.0 Sundries L.S. 401.89 2
Extra for laying CC over curved surfaces
23.0 Mason (brick layer) 1st class day 5 505.17
24.0 Mason (brick layer) 2nd class day 5 403.67
11.0 Bhisti day 1.5 350.00
18.0 Coolie day 4.5 350.00
(Extra labour for lifting material upto floor V
level : Coolie = 0.75 x 2.5 x 26.73 = 50.12)
18.0 Coolie day 50.12 350.00
TOTAL
Add 1 % Water charges on "W"
TOTAL
Add GST (multiplying factor 0.1405) on "X"
TOTAL
Add 15 % Contractor's profit and overheads on "Y"
Total
Add Cess @ 1% on "Z"
Cost for 26.73 cum.
Cost for 1 cum.
Say

5.6 Reinforced cement concrete work in


chimneys,
Details shafts,
of cost up to floor five level,
for 1 cum.
excluding
MATERIAL
the cost of centering, shuttering,
finishing and reinforcement with 1:1.5:3 (1
RCC 1:1½:3 in chimneys & shafts
5.2.2 Rate as per Item No.5.2.2 of cum 1 7409.20
SH: REINFORCED CEMENT CONCRETE
LABOUR
Extra labour involved for lifting materials
18.0 Coolie day 0.26 350.00
TOTAL
Add 1 % Water charges on "W-A" 91.00
TOTAL
Add GST (multiplying factor 0.1405) on "X-A" 91.91
TOTAL
Add 15 % Contractor's profit and overheads on 104.82
"Y-A"
Total
Add Cess @ 1% on "Z-A" 120.54
Cost for 1 cum.
Say

5.7 Reinforced cement concrete work in well-


steining, excluding the cost of centering,
shuttering, finishing and reinforcement with
coarse sand)
1:1.5:3 (1 : 3 graded
cement : 1.5 stone aggregate 20
mm nominal size).
Details of cost for 1 cum.

MATERIAL
RCC 1:1½:3 in well steining
4.1.2 Rate as per Item No.4.1.2 of SH: CONCRETE cum 1 6376.3
WORK
LABOUR
Extra labour involved :
18.0 Coolie day 0.08 350.00
TOTAL
Add 1 % Water charges on "W-A" 28.00
TOTAL
Add GST (multiplying factor 0.1405) on "X-A" 28.28
TOTAL
Add 15 % Contractor's profit and overheads on "Y-A" 32.25
Total
Add Cess @ 1% on "Z-A"
Cost for 1 cum. 37.09
Say

5.8 Reinforced cement concrete work in


vertical
aggregateand horizontal
20mm finssize).
nominal individually or
forming box louvers, facias and eaves
boards above plinth level up to floor five
Details of cost for 4 RCC Vertical fins 4m high and 1m
center with 2 horizontal fins, all projecting 60cm from
Cement Concrete
face of wall 1:1.5.3
and 5cm thick = 0.66 cum.
4x4x0.60x0.05 = 0.48 cum.
2x3x0.06x0.05 = 0.18 cum.
Total = 0.66 cum.
MATERIAL
295.0 Stone Aggregate (Single size) : 20 mm nominal cum 0.3762 800
297.0 size
Stone Aggregate (Single size) : 10 mm nominal cum 0.1848 810
2202.0 size
Carriage of Stone aggregate below 40 mm cum 0.561 584.88
982.0 nominal size
Coarse sand cum 0.2805 800
2203.0 Carriage of Coarse sand cum 0.2805 584.88
367.0 Portland Cement (0.2833 cum) tonne 0.264 4375
2209.0 Carriage of Cement tonne 0.264 94.34
LABOUR
17.0 Beldar day 0.79 350.00
18.0 Coolie day 0.56 350.00
11.0 Bhisti day 0.6 350.00
23.0 Mason (brick layer) 1st class day 0.06 505.17
24.0 Mason (brick layer) 2nd class day 0.06 403.67
9999.0 Scafolding L.S. 30.16 2
9999.0 Sundries L.S. 9.49 2
2.0 Hire charges of Concrete Mixer 0.25 to day 0.05 800
0.40 cum with hooper
12.0 Vibrator(Needle type 40mm) day 0.05 370
18.0 Coolie day 0.18 350.00
Extra for restricted working in fins
23.0 Mason (brick layer) 1st class day 0.05 505.17
24.0 Mason (brick layer) 2nd class day 0.05 403.67
17.0 Beldar day 0.1 350.00
11.0 Bhisti day 0.15 350.00
TOTAL
Add 1 % Water charges on "W"
TOTAL
Add GST (multiplying factor 0.1405) on "X"
TOTAL
Add 15 % Contractor's profit and overheads on "Y"
Total
Add Cess @ 1% on "Z"
Cost of 0.66 cum.
Cost of 1 cum.

5.9 Centering and shuttering including


strutting, propping
form for all heights etc.
: and removal of
5.9.1 Foundations, footings, bases of columns,
etc. for mass concrete
Details of cost for footing size 2.7mx2.7mx1.00m

Contact area = 10.8 sqm.

MATERIAL

Assuming shuttering material will become unserviceable


after use of 40 times Adding for maintenance @ 10% of cost
Taking salvage value after full use of material @ 25% of cost
7319.0 Wall form panel 1250x500 mm each 0.34 860
Qty taken for cost of using once =
16x0.85/40 = 0.34
7326.0 Corner angle 45x45x5 mm 1.50 m long each 0.085 240
Qty taken for cost of using once =
4x0.85/40 = 0.085
7327.0 100 mm channel shoulder 2.5 m long each 0.17 910
Qty taken for cost of using once =
8x0.85/40= 0.17
7328.0 Double clip ( bridge clip) each 0.34 76
Qty taken for cost of using once =
16x0.85/40 = 0.34
7329.0 Single clip each 0.17 59
Qty taken for cost of using once =
8x0.85/40 = 0.17
7330.0 M.S. tube 40 mm dia metre 0.2295 215
Qty taken for cost of using once = 10.8x
9999.0 0.85/40 = 0.2295
Assembly nuts & bolts L.S. 22.1 2
Qty taken for cost using once = 1040x
0.85/40 = 22.10
9977.0 Carriage L.S. 78 2
LABOUR
19.0 Fitter (grade 1) day 0.75 505.17
17.0 Beldar day 1.5 350.00
9999.0 Shuttering oil L.S. 52 2
9999.0 Sundries L.S. 26 2
TOTAL
Add 1 % Water charges on "W"
TOTAL
Add GST (multiplying factor 0.1405) on "X"
TOTAL
Add 15 % Contractor's profit and overheads on "Y"
Total
Add Cess @ 1% on "Z"
Cost for 10.8 sqm.
Cost per sqm.
Say

5.9.2 Walls (any thickness) including attached


pilasters, butteresses,
string courses etc. plinth and

Details for 7.9m long and 1.00m high wall Area

of contact 2x7.9x1.0 = 15.8 sqm.


MATERIAL
Assuming shuttering material will become unserviceable
after use of 40 times Adding for maintenance @ 10% of cost
7319.0 Wall
Takingform panel
salvage 1250x500
value after fullmm
use 2x3x2x2
of material=@ 25% of cost each 0.51 860
24Nos.
Qty taken for cost of using once =
24x0.85/40 = 0.51
7327.0 100 mm channel shoulder 2.5 m long each 0.17 910
4x2 = 8
Qty taken for cost of using once =
8x0.85/40 = 0.17
7328.0 Double clip ( bridge clip) each 0.51 76
2x6x2 = 24
Qty taken for cost of using once =
24x0.85/40 = 0.51
7329.0 Single clip each 0.255 59
2x3x2 = 12
Qty taken for cost of using once =
12x0.85/40 = 0.255
7330.0 M.S. tube 40 mm dia metre 0.68 215
2x2x8m = 32m
Qty taken for cost of using once =
32x0.85/40 = 0.68
9999.0 Nut & Bolts L.S. 27.62 2
Qty taken for cost using once =
1300x0.85/40 = 27.62
9977.0 Carriage L.S. 78 2
LABOUR
19.0 Fitter (grade 1) day 3.5 505.17
17.0 Beldar day 6 350.00
9999.0 Shuttering oil L.S. 78 2
9999.0 Sundries L.S. 52 2
TOTAL
Add 1 % Water charges on "W"
TOTAL
Add GST (multiplying factor 0.1405) on "X"
TOTAL
Add 15 % Contractor's profit and overheads on "Y"
Total
Add Cess @ 1% on "Z"
Cost for 15.8 sqm.
Cost per sqm.
Say

5.9.3 Suspended floors, roofs,


landings, balconies and access platform
Detail of cost for a room
4.50x3 = 13.50 sqm, height 3.5 m
MATERIAL
Adding for maintenance @ 10% of cost Taking
salvage value after full use of material @ 25%
of cost
1. Plates (size 0.75 x 0.60)
Angle 40x40x5mm
2x0.75 = 1.50 m
2x0.60 = 1.20 m
= 2.70 m @ 3.00 kg/m = 8.1 kg sheet 1.6 mm
thick 0.75x0.60 = 0.45 sqm
0.45 sqm @ 12.55kg/sqm = 5.65kg
Weight of one plate = 13.75kg
Add for wastage @ 5% = 0.69 kg
Total = 14.44kg
Total weight of all plates = 5x6x14.44 = 433.2
kg.
Qty taken for cost using once =
433.2x0.85/40 = 9.2055 kg
10.1 Rate as per item no.10.1 S.H. steel work kg 9.2055 88.10
7342.0 Adjustable span ESO+SI (2.35-3.40) each 0.1063 1480
Qty taken for cost using once =
5x0.85/40 = 0.1063
7343.0 Adjustable telescopic prop 3 m (2.02-3.75 m) each 0.1275 955
Qty taken for cost using once =
6x0.85/40 = 0.1275
9999.0 4. Assembly nut & bolts etc. L.S. 22.1 2
Qty taken for cost using once =
1040x0.85/40 = 22.10
9977.0 Carriage L.S. 130 2
LABOUR
19.0 Fitter (grade 1) day 3 505.17
17.0 Beldar day 6 350.00
9999.0 Shuttering oil L.S. 78 2
9999.0 Sundries, paper tap etc. L.S. 49.7 2
TOTAL
Add 1 % Water charges on "W-A" 4454.19
TOTAL
Add GST (multiplying factor 0.1405) on "X-A" 4498.73
TOTAL
Add 15 % Contractor's profit and overheads on 5130.80
"Y-A"
Total
Add Cess @ 1% on "Z-A" 5900.42
Cost for 13.50 sqm.
Cost per sqm.
Say

5.9.4 Shelves (Cast in situ)


Detail of cost for a room
4.50x3 = 13.50 sqm, height 3.5 m
MATERIAL

Adding for maintenance @ 10% of cost Taking salvage value


after full use of material @ 25%
of cost
1. Plates (size 0.75 x 0.60) Angle 40x40x5mm

2x0.75 = 1.50 m

2x0.60 = 1.20 m

= 2.70 m @ 3.00 kg/m = 8.1 kg sheet 1.6 mm thick


0.75x0.60 = 0.45 sqm

0.45 sqm @ 12.55kg/sqm = 5.65kg Weight of one plate


= 13.75kg Add for wastage @ 5% = 0.69 kg Total =
14.44kg
Total weight of all plates = 5x6x14.44 = 433.2 kg.
Qty taken for cost using once = 433.2x0.85/40 =
9.2055 kg
10.1 Rate as per item no.10.1 S.H. steel work kg 9.2055 88.10
7342.0 Adjustable span ESO+SI (2.35-3.40) each 0.1063 1480
Qty taken for cost using once =
5x0.85/40 = 0.1063
7343.0 Adjustable telescopic prop 3 m (2.02-3.75 m) each 0.1275 955
Qty taken for cost using once =
6x0.85/40 = 0.1275
9999.0 4. Assembly nut & bolts etc. L.S. 22.1 2
Qty taken for cost using once =
1040x0.85/40 = 22.10
9977.0 Carriage L.S. 130 2
LABOUR
19.0 Fitter (grade 1) day 3 505.17
17.0 Beldar day 6 350.00
9999.0 Shuttering oil L.S. 78 2
9999.0 Sundries, paper tap etc. L.S. 49.7 2
TOTAL
Add 1 % Water charges on "W-A" 4454.19
TOTAL
Add GST (multiplying factor 0.1405) on "X-A" 4498.73
TOTAL
Add 15 % Contractor's profit and overheads on 5130.80
"Y-A"
Total
Add Cess @ 1% on "Z-A" 5900.42
Cost for 13.50 sqm.
Cost per sqm.
Say

5.9.5 Lintels, beams, plinth beams, girders,


bressumers
Consider and
a beam of 6cantilevers
m clear span, 0.50 m
deep 0.30 m wide and height 3.5 m from floor Cubical
contents

6.60x0.5x0.3 = 0.99 cum 1x1.30x6.00 = 7.80 sqm


MATERIAL

Assuming shuttering will become unserviceable after use of


40 times Add maintenance charges @ 10% of cost of Less
salvage value of material after full use
@ 25% of cost of material

1. Steel plates for side and bottom


(plate size 1.20 x 0.50m)
Angle 40x40x5mm
2x1.20 = 2.40 m
3x0.50 = 1.50 m
3.90 m @ 3.00 kg/m = 11.70 kg sheet 1.6 mm thick
1.20m x 0.50 m = 0.60 sqm.
0.60 sqm @ 12.55 kg/sqm. = 7.53 kg. Weight
of one plate = 19.23 kg.
Add for wastage @ 5% = 0.96 kg.
Total = 20.19 kg.
Total weight of all plates
3x5x20.19 = 302.85 kg or 3.03 q Qty taken for
cost of using once = 302.85x0.85/40 = 6.4356
10.1 kg.
Rate as per item no.10.1 S.H. steel work
7343.0 Adjustable telescopic prop 3 m (2.02-3.75 m)
Qty taken for cost of using once =
6x0.85/40 = 0.1275 m
7344.0 Beam clamp 300-380 mm (450-1070 mm)
Qty taken for cost of using once =
5x0.85/40 = 0.1063 m kg 6.4356 88.10
9999.0 (iv) Assembly nut & bolts etc. each 0.1275 955.00
Qty taken for cost of using once = each 0.1063 355
1040x0.85/40 = 22.10 set
9977.0 Carriage L.S. 22.1 2
LABOUR L.S. 78 2
19.0 Fitter (grade 1) day 1.25 505.17
17.0 Beldar day 2.5 350.00
9999.0 Shuttering oil L.S. 39 2
9999.0 Sundries, paper tape etc. L.S. 24.61 2
TOTAL
Add 1 % Water charges on "W-A" 1993.38
TOTAL
Add GST (multiplying factor 0.1405) on "X-A" 2013.31
TOTAL
Add 15 % Contractor's profit and overheads on 2296.18
"Y-A"
Total
Add Cess @ 1% on "Z-A" 2640.61
Cost for 7.80 sqm.
Cost per sqm.
Say
Total
5.9.6 Columns, Pillars, Piers, Abutments, Posts
and Struts
Detail of cost for 4.5 sqm
Size of column 450x450mm and 2.5m high
Area of contact = 4x0.45x2.5 = 4.5 sqm.
MATERIAL
Assuming shuttering will become
unserviceable after use of 40 times Add
maintenance charges @ 10% of cost of
Less salvage value of material after full use
@ 25% of cost of material
7331.0 Wall form panel 1250x450 mm each 0.17 860
Qty taken for cost of using once =
8x0.85/40 = 0.17
7332.0 Corner angle 45x45x5 m 2.50 m long each 0.085 255
Qty taken for cost of using once =
4x0.85/40 = 0.085
7333.0 Column clamp 450x1070 m each 0.1063 965
Qty taken for cost of using once =
5x0.85/40 = 0.1063
7334.0 Prop 2 m ( 2-3.5m) each 0.085 635
Qty taken for cost of using once =
4x0.85/40 = 0.085
9999.0 Assembly nut & bolt L.S. 27.62 2
Qty taken for cost of using once =
1300x0.85/40 = 27.62
9977.0 Carriage L.S. 52 2
LABOUR
19.0 Fitter (grade 1) day 1 505.17
17.0 Beldar day 2 350.00
9999.0 Shuttering oil L.S. 39 2
9977.0 Carriage L.S. 26 2
TOTAL
Add 1 % Water charges on "W"
TOTAL
Add GST (multiplying factor 0.1405) on "X"
TOTAL
Add 15 % Contractor's profit and overheads on "Y"
Total
Add Cess @ 1% on "Z"
Cost for 4.5 sqm.
Cost per sqm.
Say

5.9.7 Stairs, (excluding landings) except spiral-


staircases
Details of cost for 5.79 sqm.
Details of staircase, 3.40m clear span including
1m landing.
MATERIAL
(i) Cost of plank 38mm (2nd class kail wood)
Waist 2.69x1.30 = 3.50sqm.
Side shuttering of steps and side of waist-
Steps = 8x1.30x1.15 = 1.56 sqm.
Face of landing
1x1.30x0.15 = 0.20 sqm.
Side of waist
2.69x0.13 = 0.35 sqm.
Side of steps-
8x0.50x0.30x0.15 = 0.18sqm.
Total = 5.79 sqm.
Wastage 5% = 0.29sqm. Total = 6.08 sq.
Cubical content-
6.08x0.038 = 0.231 cum = 231 dm³
Qty taken for cost using once = 231/8=
28.875 cudm
1198.0 Second class kail wood in planks 10 2.8875 260
(ii) Batten 100mm x 75mm cudm
4x1.30x0.100x0.075=0.039 cum = 39 dm³ Qty
taken for cost using once = 39/8 = 4.875 cudm
1197.0 Second class kail wood in scantling 10 0.4875 260
2x4x0.80 = 6.40m cudm

302.0 Qty taken for cost using once = 6.4/8 = 0.8 m metre 0.8 40
Safeda ballies 125 mm diameter Planks =
0.231 cum.Battens = 0.039 cum.
Ballies 6.4x3.142/4x(0.125)² = 0.079cum.
Total = 0.349 cum.
Qty taken for cost using once = 0.349/8 =
0.04363 cum
2204.0 Carriage of Timber cum 0.04363 121.29
LABOUR
For assembling, erection, dismantling and
15.0 cleaning
Carpenter 2nd class day 1.75 403.67
17.0 Beldar day 1 350.00
9999.0 Sundries L.S. 16.12 2
TOTAL
Add 1 % Water charges on "W"
TOTAL
Add GST (multiplying factor 0.1405) on "X"
TOTAL
Add 15 % Contractor's profit and overheads on "Y"
Total
Add Cess @ 1% on "Z"
Cost of 5.79 sqm.
Cost per sqm.
Say

5.9.8 Spiral staircases (including landing)


Detail of cost for 6.28 sqm (For 10 steps)
Treads
10x0.70x0.20(av.) = 1.40 sqm
5.9.5 Rate as per Item Number 5.9.5 of SH: : RCC sqm 1.4 414.60
Riser
2x10x0.70x0.23 = 3.22 sqm
5.9.2 Rate as per item no 5.9.2 of SH : RCC sqm 3.22 434.60
Newal Post (Column)
10x3.14x0.232 = 1.66 sqm
5.9.7 Rate as per item no 5.9.7 of SH: RCC sqm 1.66 463.00

Cost of 6.28 sqm


Cost of 1 sqm
Say

5.9.9 Arches, domes, vaults up to 6 m span


Details of cost for a semicircular arch 3.6m
clear span and 3.6m long.
Area of centering = 22x1.8x3.6=20.37sqm.
MATERIAL
Frame work in 2nd class kail wood Tie-
1x3.6x0.15x0.20 = 0.108cum. Struts-

3x1.8x0.10x0.10 =0.054cum Struts-


2x2.55x0.10x0.10=0.051cum.

Ribs-4x1.38x.075x0.075=0.031cum.
Total = 0.244 cum. Quantity for 7 such frames
7x0.244 = 1.708cum. Strips 5cmx2.5cm =
7.5cm center to center
5.66/0.075x0.05x0.025x3.6 = 0.342cum. Total
= 2.050 cum = 2050 cudm
Qty taken for cost using once = 2050/8 =
1197.0 256.25 cudm
Second class kail wood in scantling 10 25.625 260
Safeda ballies 125 mm dia cudm

7x4x3.6= 100.8m
302.0 Safeda ballies 125 mm diameter G.I. Plain metre 12.6 40
sheet 20.37 sqm m 116kg.
Or 1.16 quintal
Qty taken for cost using once =1.16/8 = 0.145
qtl
992.0 Galvanised steel plain sheets quintal 0.145 6000

Carriage-

Kail wood = 2.05cum.

Ballies - 100.8x(0.125)²/4x3.142 = 1.24cum.

Total = 3.29 cum.

Qty taken for cost using once = 3.29/8 =


2204.0 0.4112 cum
Carriage of Timber cum 0.4112 121.29
G.I. Sheet = 0.116 t
Qty taken for cost using once = 0.116/8 =
0.0145 t
2302.0 Carriage of G.I.sheet and accessories tonne 0.0145 94.34
LABOUR
15.0 Carpenter 2nd class day 16 403.67
17.0 Beldar day 13 350.00
9999.0 Sundries L.S. 11.7 2
TOTAL
Add 1 % Water charges on "W"
TOTAL
Add GST (multiplying factor 0.1405) on "X"
TOTAL
Add 15 % Contractor's profit and overheads on "Y"
Total
Add Cess @ 1% on "Z"
Cost of 20.37sqm.
Cost per sqm.
Say

5.9.10 Extra for arches, domes, vaults exceeding 6


m span
Details of cost for 33.31 sqm
Centering and shuttering for arches and carved
surface exceeding 6m in span
(an average of 8m)
Radius R = 5m 2R-2 = 8 tan -¹ (4/3)=53.28° 2x53.28° =
106°
Surface area =2x22/7x5x3.6x106/360 =33.31sqm.
Arc=9.25m
MATERIAL
Tie-2x8x0.18x0.05=0.144cum Struts-
2x2.5x0.1x0.1 =0.050cum. Struts-
2x1.77x0.1x0.1=0.035cum. Ribs-
6x1.54x0.23x0.1=0.213cum. Struts-
2x1.72x0.1x0.1=0.034cum.
Total=0.='0.2 LABOUR'!H10cum.
For four such frames =0.='0.2 LABOUR'!H10x4 =
1.904 cum. laggings-75x3.6x0.125x0.075=2.531cum.
Brace-3x2x2.14x0.225x0.038=0.110
Tie-2x3.6x0.225x0.038=0.062cum.
Brace-3x4x3.8x0.225x0.038=0.390
Sleepers-4x3.6x0.20x0.15=0.432
Sleepers-2x4x3.6x0.175x0.075=0.378
Vertical post-4x4x3.6x0.15x0.15=1.296
Total =7.103cum. or 7103 cudm
Qty taken 1/8th of qty for cost using once
=7.103/8 = cum = 887.9 Cudm
1197 Second class kail wood in scantling 10 88.79 260
cudm
2204.0 Carriage of Timber Fittings: cum 0.8879 121.29
3 way straps 50mmx10mm = 32 Nos.
32 no. @0.50cm each = 16m
Straps-50mmx10mm = 8 Nos. @
0.25cm each = 2m
Total = 18m
18m, wt @ 3.9kg/m = 70.2 kg. = 0.702q
Qty taken l/8th of qty for cost using once =
0.702/8 = 0.08775
1225.0 Mild steel flat strap fitting quintal 0.0878 4120
Bolts 160 Nos. 254 mm long 16mm
dia.160x.254x 1.58=64.21 kg=0.64q.
Qty taken l/8th of qty for cost using once= 0.702/8 =
0.08775
1034.0 Bolts and nuts upto 300 mm in length quintal 0.08 6800
2202.0 Carriage of G.I.sheet and accessories tonne 0.0168 584.88
Qty taken 1/8th of qty for cost using once
= 0.1342/8 = 0.01677 t say 0.0168 t
LABOUR
15.0 Carpenter 2nd class day 28 403.67
17.0 Beldar day 24 350.00
9999.0 Sundries L.S. 134.55 2
Less Cost of shuttering etc. for an arch
exceeding 6 m span i.e. for an average of 8 m span
5.9.9 Rate as per item no 5.9.9 of SH : RCC sqm -33.31 1255.80
TOTAL
Add 1 % Water charges on "W-A" 44080.52
TOTAL
Add GST (multiplying factor 0.1405) on "X-A" 44521.33
TOTAL
Add 15 % Contractor's profit and overheads on "Y-A" 50776.58
Total
Add Cess @ 1% on "Z-A" 58393.07
Cost of 33.31sqm.
Cost per sqm of soffit area
Say

5.9.11 Chimneys and shafts


Details for 7.9m long and 1.00m high wall Area
of contact 2x7.9x1.0 = 15.8 sqm.
MATERIAL
Adding for maintenance @ 10% of cost Taking
salvage value after full use of material @ 25%
7319.0 of cost
Wall form panel 1250x500 mm each 0.51 860
2x3x2x2 = 24 Nos. Qty taken for cost of using
once = 24x0.85/40 = 0.51
7327.0 100 mm channel shoulder 2.5 m long each 0.17 910
4x2 = 8
Qty taken for cost of using once =
8x0.85/40 = 0.17
7328.0 Double clip ( bridge clip) each 0.51 76
2x6x2 = 24
Qty taken for cost of using once =
24x0.85/40 = 0.51
7329.0 Single clip each 0.255 59
2x3x2 = 12
Qty taken for cost of using once =
12x0.85/40 = 0.255
7330.0 M.S. tube 40 mm dia metre 0.68 215
2x2x8m = 32m
Qty taken for cost of using once =
32x0.85/40 = 0.68
9999.0 Nut & Bolts L.S. 27.63 2
Qty taken for cost of using once =
1300x0.85/40 = 27.63
9977.0 Carriage L.S. 78 2
LABOUR
19.0 Fitter (grade 1) day 3.5 505.17
17.0 Beldar day 6 350.00
9999.0 Shuttering oil L.S. 78 2
9999.0 Sundries L.S. 52 2
TOTAL
Add 1 % Water charges on "W"
TOTAL
Add GST (multiplying factor 0.1405) on "X"
TOTAL
Add 15 % Contractor's profit and overheads on "Y"
Total
Add Cess @ 1% on "Z"
Cost for 15.8 sqm.
Cost per sqm.
Say

5.9.12 Well steining


Details of cost 26.39 sqm.
Surface area
Outside area =22/7x4.40x1.00 - 13.82sqm =
26.39 sqm
MATERIAL
Assuming that the timber will become
unserviceable after being used 8 times Planks
38 mm (Second class kail wood) 26.39x0.038
= 1.00cum.
Wastage 20% = 0.20cum.
Total = 1.20cum. or 1200 cudm.
Qty for cost using once = 1200/8=150 cudm
1198.0 Second class kail wood in planks 10 15 260
2nd class kail wood battens Inside = cudm
2x25x0.50x0.075x0.038 = 0.0712cum.
Outside = 2x28x0.50x0.075x0.038 =
0.0798cum.
Total = 0.1510cum.
Wastage 5% = 0.0076 cum.
= 0.1586 cum = 158.60 cudm
Qty for cost using once = 0.1586/8= 0.0198
1197.0 cudm
Second class kail wood in scantling 10 0.00198 260
302.0 cudm 40
Safeda ballies 125 mm diameter metre 6.625 40
Inside: 25x1.00 = 25.00m
Outside: 28x1.00 = 28.00m
Total = 53.00m
Qty for cost using once = 53/8 =6.625 m
TOTAL
Add for carriage, labour for erectio ad
dismentalig etc @ 1/6 (16.667%) of cost of
material
TOTAL
Add 1 % Water charges on "W"
TOTAL
Add GST (multiplying factor 0.1405) on "X"
TOTAL
Add 15 % Contractor's profit and overheads on "Y"
Total
Add Cess @ 1% on "Z"
Cost for 26.39sqm.
Cost per sqm.
Say

5.9.13 Vertical and horizontal fins


individually
and eaves boardsor forming box louvers band,
facias
Details of cost for fins 4 vertical fins 4 metre high and
at 1 metre centres, with two horizontal fins all
i.e. (4x4x1.25)
projecting 60cm+ (2x3x0.65) = 23.90sqm
from face of wall and 5+cm
5%thick.
1198.0 wastage = 25.10 sqm. MATERIAL
Second class kail wood in planks 10 11.925 260
38mm thick4x4x1.25=20.00 cudm
2x3x0.65 =3.90 Total = 23.90
Wastage @ 5% = 1.20 Total = 25.10sqm.
25.10x0.038=.954 cum or 954 cudm
Qty for cost using once = 954/8 = 119.25 cudm
1197.0 Second class kail wood in scantling 10 3.3625 260
4x2x5x0.60x0.075x0.050=0.090 cudm
3x2x5x1.00x0.075x0.050=0.112
2x6x0.60x0.075x0.100=0.054 = 0.256 Cum.
Wastage® 5% =0.013 cum
= 0.269 cum= 269 cudm
Qty for cost using once = 269/8 = 33.625 cudm
302.0 Safeda ballies 125 mm diameter metre 12.6 40
2x2x6x4.00 =96m
Wastage @5% = 4.8m
Total= 100.8 m
Qty for cost using once = 100.8/8 = 12.6 m
2204.0 Carriage of Timber cum 0.3076 121.29
Planks = 0.954
Battens = 0.269
Bailies 100.8x(0.125)²/4x3.142= 1.238cum.
Total = 2.461 cum
Qty for cost using once = 2.461/8 =
0.3076 cum
LABOUR
For assembling, erection, dismantling and
15.0 cleaning
Carpenter 2nd class day 11 403.67
17.0 Beldar day 11 350.00
9999.0 Sundries L.S. 80.73 2
TOTAL
Add 1 % Water charges on "W"
TOTAL
Add GST (multiplying factor 0.1405) on "X"
TOTAL
Add 15 % Contractor's profit and overheads on "Y"
Total
Add Cess @ 1% on "Z"
Cost for 23.90 sqm.
Cost per sqm.
Say

5.9.14 Extra for shuttering in circular


work
5.9.15 (20% of respective
Small centering
lintels not and1.5 m
exceeding
shuttering
clear items)
span, moulding as in cornices,
the like
window sills, string courses, bands,
copings, bed plates, anchor blocks and
Details of cost for footing size

2.7mx2.7mx1.00m
Contact area = 10.8 sqm.
MATERIAL
Assuming shuttering material will become
unserviceable after use of 40 times
Adding for maintenance @ 10% of cost
Taking salvage value after full use of material
7319.0 @ 25% of cost
Wall form panel 1250x500 mm each 0.34 860
Qty taken for cost of using once =
16x0.85/40 = 0.34
7326.0 Corner angle 45x45x5 mm 1.50 m long each 0.085 240
Qty taken for cost of using once =
4x0.85/40 = 0.085
7327.0 100 mm channel shoulder 2.5 m long each 0.17 910
Qty taken for cost of using once =
8x0.85/40 = 0.17
7328.0 Double clip ( bridge clip) each 0.34 76
Qty taken for cost of using once =
16x0.85/40 = 0.34
7329.0 Single clip each 0.17 59
Qty taken for cost of using once =
8x0.85/40 = 0.17
7330.0 M.S. tube 40 mm dia metre 0.2295 215
4x2.7m = 10.8m
Qty taken for cost of using once =
10.8x0.85/40 =0.2295
9999.0 Assembly nuts & bolts L.S. 22.1 2
Qty taken for cost of using once =
1040x0.85/40 = 22.10
9977.0 Carriage L.S. 78 2
LABOUR
19.0 Fitter (grade 1) day 0.75 505.17
17.0 Beldar day 1.5 350.00
9999.0 Shuttering oil L.S. 52 2
9999.0 Sundries L.S. 26 2
TOTAL
Add 1 % Water charges on "W"
TOTAL
Add GST (multiplying factor 0.1405) on "X"
TOTAL
Add 15 % Contractor's profit and overheads on "Y"
Total
Add Cess @ 1% on "Z"
Cost for 10.8 sqm.
Cost per sqm.
Say

5.9.16 Edges of slabs and breaks in floors and


walls
5.9.16.1 Under 20 cm wide
Details of cost for a 3mx3m slab 15cms thick 12m
edge Length
MATERIAL
Assuming that the timber will become unserviceable after
being used 8 times.
1198.0 Second class kail wood in planks 10 0.7125 260
cudm
(i) Planks 30mm thick (2nd class Kail wood or
equivalent local soft wood) 4x3x0.15x0.030=0.054cum
0.003
Wastagecum.
@5% =
Total = 0.057 cum 57 cudm
Qty taken for cost of using once = 57/8 =7.125 cudm

1197.0 Second class kail wood in scantling(ii) Battens 10 1.9375 260


75mmx100mm (2nd class
Horizontal 2x4x0.075x0.1x0.5=0.030 Horizontal cudm
2x4x0.075x0.1x1.5=0.090
(iii) Vertical battens 16x0.15x0.075x0.030m = 0.0054
(iv) Struts 16x0.25x0.075x0.075=0.0225 Total = 0.1479
Wastage @5% = 0.0074 Total = 0.1553 cum = 155
cudm
Qty taken for cost ef using once = 155/8 =19.375
cudm
2204.0 Carriage of Timber Planks = 0.057 cum. 0.0265 121.29
Battens = 0.155 cum.
Total = 0.212 cum.
Qty taken for cost of using once =
0.212/8 = 0.0265 cum cum 0.0265 121.29
LABOUR
For assembling erection dismantling &
15.0 cleaning.
Carpenter 2nd class day 0.81 403.67
17.0 Beldar day 0.54 350.00
9999.0 Sundries L.S. 5.2 2
TOTAL
Add 1 % Water charges on "W"
TOTAL
Add GST (multiplying factor 0.1405) on "X"
TOTAL
Add 15 % Contractor's profit and overheads on "Y"
Total
Add Cess @ 1% on "Z"
Cost of 12 metres
Cost of one meter
Say

5.9.16.2 Above 20 cm wide


Details of cost for 4mx4xslab 25cms thick 16
metre edge length
Shuttering surface area = 16 x 0.25 = 4 sqm
MATERIAL
1198.0 Second class kail wood in planks
(i) Planks 38mm thick
4x4x0.25x0.038 = 0.152
Wastage @ 5% = 0.008
Total = 0.160 cum. = 160 cudm
Qty taken for cost of using once = 160/8 = 20
1197.0 cudm
Second class kail wood in scantling
(ii) Battens
6x2x0.6x0.075x0.100=0.054
5x2x1.5x0.075x0.100=0.113
Total = 0.167
Wastage @ 5% = 0.008
Total = 0.175 cum. = 175 cudm
Qty taken for cost of using once =
175/8 = 21.88 cudm
2204.0 Carriage of Timber Planks = 0.16 cum.
Battens = 0.175 cum.
Total = 0.335 cum.
Qty taken for cost of using once =
0.335/8 = 0.0419 cum
10 2.00 260.00 520.00 cudm
10 2.188 260.00 568.88 cudm cum 0.0419 121.29
LABOUR
For assembling erection dismantling &
15.0 cleaning.
Carpenter 2nd class day 1 403.67
17.0 Beldar day 0.75 350.00
9999.0 Sundries L.S. 6.5 2
TOTAL
Add 1 % Water charges on "W"
TOTAL
Add GST (multiplying factor 0.1405) on "X"
TOTAL
Add 15 % Contractor's profit and overheads on "Y"
Total
Add Cess @ 1% on "Z"
Cost of 4 sqm.
Cost of 1 sqm.
Say

5.9.17 Cornices and mouldings


Details of cost for 10m long moulding 10cm
projection,
20cm depth and 40cm girth

Area in contact 10x0.4 = 4.0 sqm.


MATERIAL
Assuming that the timber will become
unserviceable after being used 8 times.
1198.0 Second class kail wood in planks (I) Planking 10 2.275 260
30mm thick = 4sqm. cudm
Extra & Wastage 20% = 0.8 sqm.
Total = 4.8 sqm.
4.8x0.038 = 0.182 cum = 182 cudm
Qty taken for cost using once = 182/8 = 22.75
1197.0 cudm
Second class kail wood in scantling 10 2.725 260
(ii) Battens-Joining to Planking 1x10x0.1x0.075 cudm
= 0.075 cum.
From bottom shuttering
10x1.5x0.1x0.075 = 0.113 cum.
Wales
10x0.4mx0.1x0.075 = 0.030 cum.
Total = 0.218 cum = 218 cudm
Qty taken for cost using once = 218/8 = 27.25
2447.0 cudm
Hollock ballies 125 mm diameter (iii) Ballies metre 3.15 35
125 mm dia. Slant 10x0.3 = 3 m ver. 6x3.5 =
21.0 m Total = 24.0 m
Wastage @ 5% = 1.2 m
Total = 25.2 m
Qty taken for cost using once = 25.2/8 = 3.15m
2204.0 Carriage of Timber cum 0.0888 121.29
Planking= 0.188 cum.
Battens & Wales = 0.218 cum.
Ballies
25.2x22/7x(0.125)/4 = 0.310 cum. Total =
0.710 cum.
Qty taken for cost using once = 0.71/8=
0.0888 cum
LABOUR
Labour for assembling, erection, dismantling &
cleaning
15.0 Carpenter 2nd class day 0.63 403.67
17.0 Beldar day 0.63 350.00
9999.0 Sundries L.S. 6.5 2
TOTAL
Add 1 % Water charges on "W"
TOTAL
Add GST (multiplying factor 0.1405) on "X"
TOTAL
Add 15 % Contractor's profit and overheads on "Y"
Total
Add Cess @ 1% on "Z"
Cost of 4 sqm.
Cost of 1 sqm.
Say

5.9.18 Small surfaces such as cantilever


ends, brackets
Details of cost for aand ends of steps, caps and
bracket
bases to pilasters
1.20m projected
and columns and the like

Front area 0.50x0.60m End area 0.50x0.75m

Area in contact with concrete 2x{(0.60.75)/2x1.2} =


1.62 sqm. Front 0.5x0.6
= 0.30 sqm.

Bottom 0.5x1.21 = 0.605 sqm. Total = 2.525 sqm.

MATERIAL
Assuming that the timber will become unserviceable after
being used 8 times.

1198.0 Second class kail wood in planks 10 1.3375 260

Timber IInd class kail wood or equivalent local cudm


soft wood (I) Plank 30mm thick.
Sides 2{(0.60.75)/2x1.238} = 1.6713sqm
Battens 0.576x1.21 = 0.697
Front 0.5x0.638 = 0.319 Total = 2.687 sqm.
Cubical contents
2.687x0.038 = 0.102 cum.
Wastage @ 5% = 0.005 cum.
Total = 0.107 cum.
Qty taken for cost using once = 107/8 =
13.375 cudm
1197.0 Second class kail wood in scantling 10 0.315 260
(ii) Battens-0.05x0.05

2x1.238 #NAME?
2x1.21 = 2.42m
2x0.688 = 1.376m
2x0.838 = 1.676m
3x0.5 = 1.50m
Total = 9.448m
Cubical contents
9.448x0.05x0.05 = 0.024 cum.
Wastage 5% = 0.0012
cum.
Total = 0.0252
cum = 25.2
Qty taken for cost using once = 25.2/8 = 3.15 cudm
2447.0 cudm
Hollock ballies 125 mm diameter (iii) Ballies metre 0.6763 35
125mm dia.
1x2.5 = 2.50m
1x2.65 = 2.65m
Total = 5.15 m
Wastage 5% = 0.26m
Total = 5.41 m
Qty taken for cost using once = 5.41/8= 0.6763
2204.0 m
Carriage of Timber Planks = 0.107 cum. cum 0.0248 121.29
Battens = 0.0252 cum.
Ballies
5.41x22/7x(0.125²/4 = 0.066 cum.
Total = 0.198 cum
Qty taken for cost using once = 0.198/8 =
0.0248 cudm
LABOUR
Labour for assembling, erection, dismantling &
15.0 cleaning
Carpenter 2nd class day 0.8 403.67
17.0 Beldar day 0.8 350.00
9999.0 Sundries L.S. 7.15 2

TOTAL
Add 1 % Water charges on "W"
TOTAL
Add GST (multiplying factor 0.1405) on "X"
TOTAL
Add 15 % Contractor's profit and overheads on "Y"
Total
Add Cess @ 1% on "Z"
Cost of 2.525 sqm.
Cost of 1 sqm.
Say

5.9.19 Weather shade, Chajjas, corbels


etc., including edges
Details of cost for a weather shade
Area of centring and shuttering = 0.954 sqm
For a weather shade over a window of size
1.5mx1.2m
Size of weather shade 1.80x0.45m
Thickness at front = 0.05m
Thickness at fixed edge = 0.07m
Area in contact with concrete Bottom
1x0.45x1.80 = 0.810
1x0.05x1.80 = 0.094
2x0.45x0.0
0.027 Total = 0.954 sqm. 6 =
MATERIAL
Assuming that the timber will become
unserviceable after being used 8 times.
1198.0 Second class kail wood in planks (i) Planking 10 0.5125 260
38mm thick. cudm
Bottom 1x1.876x0.488 = 0.915 sqm.
1x1.876x0.05 = 0.94
sqm.
2x0.45x0.06 = 0.027
sqm.
Total = 1.036
sqm.
Add 5% wastage = 0.052 sqm.
Total = 1.088
sqm.
Cubic contains
1.088x0.038 = 0.041 cum = 41 cudm
Qty taken for cost using once = 41/8 =
5.125 cudm
1197.0 Second class kail wood in scantling 10 0.15 260
(ii) Battens- cudm
2x0.60x0.075x0.10 = 0.009
Ends with bearing center
1x0.45x0.075x0.10 = 0.003
Total= 0.012 cum = 12 cudm
Qty taken for cost using once =12/8=1.50 cudm
2447.0 Hollock ballies 125 mm diameter (iii) Ballies metre 0.5513 35
125mm dia.
2x2.1 = 4.2m
Wastage 5% = 0.21m
Total = 4.41 m
Qty taken for cost using once = 4.41/8 =
2204.0 0.5513 m Carriage:
Carriage of Timber cum 0.01338 121.29
Plank = 0.041
cum.
Battens = 0.012
cum.
Ballies
4.41x22/7x(0.125)²/4 = 0.054 cum.
Total = 0.107 cum
Qty taken for cost using once = 0.107/8 =
0.01338 cum
LABOUR
Labour for assembling, erection, dismantling &
15.0 cleaning
Carpenter 2nd class day 0.3 403.67
17.0 Beldar day 0.25 350.00
9999.0 Sundries L.S. 5.2 2
TOTAL
Add 1 % Water charges on "W"
TOTAL
Add GST (multiplying factor 0.1405) on "X"
TOTAL
Add 15 % Contractor's profit and overheads on "Y"
Total
Add Cess @ 1% on "Z"
Cost for 0.954 sqm.
Cost of 1 sqm.
Say

5.9.20 Suspended floors, roofs,


landings,
Detail of cost for a room and access platform.
balconies
with water proof ply 12 mm thick
4.50x3 = 13.50 sqm, height 3.5 m
MATERIAL
Adding for maintenance @ 10% of cost Taking
salvage value after full use of material @ 25%
10.1 of cost
Rate as per Item No.10.1 of SH:Steel Work kg 5.425 88.10
Plates (size 0.75 x 0.60)
Angle 40x40x5mm
2x0.75 = 1.50 m
2x0.60 = 1.20 m
= 2.70 m @ 3.00 kg/m = 8.1 kg Weight of one
plate = 8.10kg
Add for wastage @ 5% = 0.41 kg
Total = 8.51kg
Total weight of all plates = 5x6x8.51 = 255.30
kg.
Qty taken for cost using once.=
255.30x0.85/40 = 5.425 kg
Welding length = (30x32)/40=24 cm
1215.0 Welding by electric plant cm 24 2

8659.0 Water proof ply 12mm thick. sqm 1.77 517


1x4.50x3.00=13.50sqm
Add wastage @ 5% =0.68sqm
Total 14.18sqm
Qty taken for cost using once 14.18/8 =
15.0 1.77sqm
Carpenter 2nd class day 0.125 403.67
17.0 Beldar day 0.125 350.00
1034.0 Bolts and nuts upto 300 mm in length quintal 0.0021 6800
7342.0 Adjustable span ESO+SI (2.35-3.40) each 0.10625 1480
Qty taken for cost using once =
5x0.85/40 = 0.10625
7343.0 Adjustable telescopic prop 3 m (2.02-3.75 m) each 0.1275 955
Qty taken for cost using once =
6x0.85/40 = 0.1275
9999.0 Assembly nut & bolts etc. L.S. 12.63 2
9977.0 Carriage L.S. 130 2
LABOUR
19.0 Fitter (grade 1) day 3 505.17
17.0 Beldar day 6 350.00
9999.0 Shuttering oil L.S. 78 2
9999.0 Sundries L.S. 52 2
TOTAL
Add 1 % Water charges on "W-A" 5237.34
TOTAL
Add GST (multiplying factor 0.1405) on "X-A" 5289.71
TOTAL
Add 15 % Contractor's profit and overheads on 6032.92
"Y-A"
Total
Add Cess @ 1% on "Z-A" 6937.85
Cost for 13.50 sqm.
Cost per sqm.
Say

5.9.21 Lintels, beams, plinth beams,


girders,
Details of cost for a beamand
bressumers cantilevers.
of 6 m with
clear span, 0.50 m
water0.30
deep proof plyand
m wide 12 height
mm thick
3.5 m from floor Cubical contents

6.60x0.5x0.3 = 0.99 cum

1x1.30x6.00 = 7.80 sqm

MATERIAL

Assuming shuttering will become unserviceable after use of


8 times Add maintenance charges @ 10% of cost of Less
salvage value of material after full use
@ 25% of cost of material

10.1 Rate as per Item No.10.1 of SH:Steel Work Steel kg 3.72 88.10
plates for side and bottom (plate size
1.20 x 0.50m)

Angle 40x40x5mm (both sides) & bottom 2x(2x1.20) =


4.80 +(2x1.2) =7.20m 2x(3x0.50)=3.00+(3x0.30)=3.9m
11.10 m @ 3.00 kg/m =33.30 kg Weight of one

plate = 11.70 kg.


Add for wastage =1.67kg.

Total =34.97 kg.


Total weight of all plates
5x34.97 = 174.85 kg
Qty taken for cost of using once =
174.85x0.85/40 =3.72 kg
Welding length 480/40= 12 cm
1215.0 Welding by electric plant cm 12 2

8659.0 Water proof ply 12mm thick. 1x1.30x6.00 = sqm 1.02 517
7.80 sqm
Add 5% wastage = 0.39 sqm
Total = 8.19 sqm
Qty taken for cost of using once 8.19/8 sqm=
15.0 1.02 sqm
Carpenter 2nd class day 0.125 403.67
17.0 Beldar day 0.125 350.00
1034.0 Bolts and nuts upto 300 mm in length quintal 0.0021 6800
7343.0 Adjustable telescopic prop 3 m (2.02-3.75 m) each 0.1275 955
Qty taken for cost of using once = 6 x0.85/40
7344.0 =0.1275 m 355
Beam clamp 300-380 mm (450-1070 mm) each 0.1063 355
Qty taken for cost of using once = set
5x0.85/40 = 0.1063m
9999.0 Assembly nut & bolts etc. L.S. 11.05 2
9977.0 Carriage L.S. 78 2
LABOUR
19.0 Fitter (grade 1) day 1.25 505.17
17.0 Beldar day 2.5 350.00
9999.0 Shuttering oil L.S. 39 2
9999.0 Sundries, paper tape etc. L.S. 26 2

TOTAL
Add 1 % Water charges on "W-A" 2513.01
TOTAL
Add GST (multiplying factor 0.1405) on "X-A" 2538.14
TOTAL
Add 15 % Contractor's profit and overheads on 2894.75
"Y-A"
Total
Add Cess @ 1% on "Z-A" 3328.96
Cost for 7.80 sqm.
Cost per sqm.
Say

5.10 Providing and fixing tie bolt,


spring
5.10.1 coil12and
mmplastic
dia. &cone
100 mmin wall
length
shuttering complete as per the direction
Details of cost for wall length 7.90mx 1m (24 set)
of
Engineer-in-charge.

MATERIAL

7320.0 Tie bolt 12 mm dia 100 mm length each 24 38


7324.0 Spring coil 12 mm each 48 15
7325.0 Plastic cone 12 mm dia each 48 17
9977.0 Carriage: L.S. 13 2
LABOUR
9999.0 Sundries L.S. 26 2
TOTAL
Add 1 % Water charges on "W"
TOTAL
Add GST (multiplying factor 0.1405) on "X"
TOTAL
Add 15 % Contractor's profit and overheads on "Y"
Total
Add Cess @ 1% on "Z"
Cost for 24 sets
Cost of 1 each set
Say

5.10.2 12 mm dia. & 150 mm length


Details of cost for wall length 7.90mx1m
(24 set)
MATERIAL
7321.0 Tie bolt 12 mm dia 150 mm length each 24 48
7324.0 Spring coil 12 mm each 48 15
7325.0 Plastic cone 12 mm dia each 48 17
9977.0 Carriage: L.S. 13 2
LABOUR
9999.0 Sundries L.S. 26 2
TOTAL
Add 1 % Water charges on "W"
TOTAL
Add GST (multiplying factor 0.1405) on "X"
TOTAL
Add 15 % Contractor's profit and overheads on "Y"
Total
Add Cess @ 1% on "Z"
Cost for 24 sets
Cost of 1 each set
Say

5.10.3 20 mm dia. & 150 mm length

Details of cost for wall length 7.90mx1m (24 set)

MATERIAL

7322.0 Tie bolt 20 mm dia 150 mm length each 24 57


7324.0 Spring coil 12 mm each 48 15
7325.0 Plastic cone 12 mm dia each 48 17
9977.0 Carriage: L.S. 13 2
LABOUR
9999.0 Sundries L.S. 26 2
TOTAL
Add 1 % Water charges on "W"
TOTAL
Add GST (multiplying factor 0.1405) on "X"
TOTAL
Add 15 % Contractor's profit and overheads on "Y"
Total
Add Cess @ 1% on "Z"
Cost for 24 sets
Cost of 1 each set
Say

5.10.4 20 mm dia.& 225 mm length


Details of cost for wall length 7.90mx1m
(24 set)
MATERIAL
7323.0 Tie bolt 20 mm dia 225 mm length each 24 67
7324.0 Spring coil 12 mm each 48 15
7325.0 Plastic cone 12 mm dia each 48 17
9977.0 Carriage: L.S. 13 2
LABOUR
9999.0 Sundries L.S. 26 2
TOTAL
Add 1 % Water charges on "W"
TOTAL
Add GST (multiplying factor 0.1405) on "X"
TOTAL
Add 15 % Contractor's profit and overheads on "Y"
Total
Add Cess @ 1% on "Z"
Cost for 24 sets
Cost of 1 each set
Say

5.11 Extra for additional height in


centering,
5.11.1 shuttering where
Suspended floors,ever required
roofs, landing,
with
beams adequate
and bracing,
balconies propping
(Plan area etc.,
to be
measured)
including cost of de-shuttering and
Details of cost for a Room of size 6mx4.8m =
28.8 sqm.
MATERIAL
Assuming that shuttering material will become
unserviceable after use 40 times
Less salvage value of material after full use @
25% of cost material
Add 10% of cost of material for maintenance
7345.0 Prop 4 m each 0.4463 910
Qty taken for cost using once =
21 x0.85/40 = 0.4463
Deduct the rate of 3m prop
7343.0 Adjustable telescopic prop 3 m (2.02-3.75 m) each -0.4463 955
Qty taken for cost using once =
21x0.85/40 = 0.4463
7330.0 M.S. tube 40 mm dia metre 1.0965 215
Bracing
MS tube 40mm
7x4.8m = 33.60m
3x6.0m = 18.00m
Total = 51.60m
Qty taken for cost using once =
51.6x0.85/40 = 1.0965
7346.0 Double coupler each 0.4463 46
(40x40)
Qty taken for cost using once = 21 x0.85/40 =
9977.0 0.4463
Carriage L.S. 65 2
LABOUR
19.0 Fitter (grade 1) day 3 505.17
17.0 Beldar day 6 350.00
9999.0 Sundries L.S. 130 2
TOTAL
Add 1 % Water charges on "W"
TOTAL
Add GST (multiplying factor 0.1405) on "X"
TOTAL
Add 15 % Contractor's profit and overheads on "Y"
Total
Add Cess @ 1% on "Z"
Cost for 28.8 sqm.
Cost per sqm.
Say

5.12 Providing, hoisting and fixing


above plinth
Details of level
cost for up to floor five level
1 cum.
precast
MATERIAL
reinforced cement concrete work in
string courses, bands, copings, bed plates,
Cement concrete 1:1½:3 in string or lacing
4.5.1 course etc
Rate as per Item No.4.5.1 of cum 1 7306.3
SH:CONCRETE WORK
(NB : Rate has been taken including cost of
fixing in CM 1:2 as precast members are to be
fixesd in CM 1:2)(1 cement : 2 coarse
sand) as per CPWD specifications)
LABOUR
Extra labour for laying CC in RCC work
17.0 Beldar day 0.1 350.00
11.0 Bhisti day 0.2 350.00
23.0 Mason (brick layer) 1st class day 0.04 505.17
24.0 Mason (brick layer) 2nd class day 0.04 403.67
28.0 Mate day 0.04 350.00
TOTAL
Add 1 % Water charges on "W-A" 143.1
TOTAL
Add GST (multiplying factor 0.1405) on "X-A" 144.53
TOTAL
Add 15 % Contractor's profit and overheads on 164.84
Total
Add Cess @ 1% on "Z-A" 189.57
Cost for 1 cum.
Say

5.13 Providing, hoisting and fixing up


to
aggregate 20level
floor five mmprecast
nominalreinforced
size). cement
concrete in small lintels not exceeding 1.5m
clear span up to floor five level, including
Details of cost for a lintel :

Qty = 0.054 cum

MATERIAL

1.5m clear span = 1.8x0.20x0.15 = 0.054 cum.


Cement Concrete 1:1½:3
4.2.2 Rate as per Item No.4.2.2 of SH: Concrete cum 0.054 7529.05
Work
Centring and shuttering
4.3.1 Rate as per item no. 4.3.1 of SH: Concrete sqm 0.6 216.45
work
LABOUR
17.0 Beldar day 0.005 350.00
11.0 Bhisti day 0.01 350.00
23.0 Mason (brick layer) 1st class day 0.002 505.17
24.0 Mason (brick layer) 2nd class day 0.002 403.67
28.0 Mate day 0.002 350.00
TOTAL
Add 1 % Water charges on "W-A" 7.16
TOTAL
Add GST (multiplying factor 0.1405) on "X-A" 7.23
TOTAL
Add 15 % Contractor's profit and overheads on 8.24
"Y-A"
Total
Add Cess @ 1% on "Z-A" 9.48
Cost for 0.054 cum.
Cost per cum
Say

5.14 Providing, hoisting and fixing


above
nominal size).level up to floor five level
plinth
precast reinforced cement concrete in
mouldings as in cornices, windows sills
Details of cost for
1mx0.20x0.15=0.03 cum
MATERIAL
Cement concrete 1:1½:3
4.1.2 Rate as per Item No.4.1.2 of SH: Concrete cum 0.03 6051.00
Work
Extra labour for lifting
0.45 x 0.03 x 2.5 = 0.034
18.0 Coolie day 0.034 350.00
9999.0 Mortar and labour for hoisting and for fixing L.S. 2.73 2
4.3.1 Centring and shuttering
Rate as per Item No.4.3.1 of SH: Concrete sqm 0.36 224.60
9999.0 Work
Add for extra labour for hoisting L.S. 1.61 2
53.82x0.03 = 1.61
LABOUR
Add Extra labour for moulding :
23.0 Mason (brick layer) 1st class day 0.0174 505.17
0.58x0.03
24.0 Mason (brick layer) 2nd class day 0.0174 403.67
0.58x0.03
18.0 Coolie day 0.045 350.00
1.5x0.03
11.0 Bhisti day 0.0018 350.00
0.06x0.03
Extra labour for laying CC in RCC
17.0 Beldar 0.1x0.03 day 0.003 350.00
11.0 Bhisti day 0.006 350.00
0.2x0.03
23.0 Mason (brick layer) 1st class day 0.0012 505.17
0.04x0.03
24.0 Mason (brick layer) 2nd class day 0.0012 403.67
0.04x0.03
28.0 Mate day 0.0012 350.00
0.04x0.03
TOTAL
Add 1 % Water charges on "W-A" 57.43
TOTAL
Add GST (multiplying factor 0.1405) on "X-A" 58.00
TOTAL
Add 15 % Contractor's profit and overheads on 66.15
"Y-A"
Total
Add Cess @ 1% on "Z-A" 76.07
Cost for 0.03 cum
Cost for 1 cum.
Say

5.15 Providing, hoisting and fixing


above plinth level
Details of cost for up6.60m
beam to floor
long five
0.50mlevel
deep and
precast
0.30m
cum.
widereinforced cement
= 6.60x0.50x0.30 concrete
= 0.99 in
lintels, beams and bressumers, including
MATERIAL

Cement concrete 1:1½:3


4.1.2 Rate as per Item No.4.1.2 of SH: Concrete cum 0.99 6376.3
Work
Centring and shuttering
4.3.1 Rate same as per item no. 4.3.1 Of sqm 6.9 216.45
SH: Concrete work
Extra labour for lifting material upto floor V
18.0 level
Coolie day 1.11 350.00
LABOUR
Extra labour for layin cement concrete in RCC
17.0 work
Beldar day 0.099 350.00
0.10x0.99
11.0 Bhisti day 0.198 350.00
0.20x0.99
23.0 Mason (brick layer) 1st class day 0.0396 505.17
0.04x0.99
24.0 Mason (brick layer) 2nd class day 0.0396 403.67
0.04x0.99
28.0 Mate day 0.0396 350.00
0.04x0.99
9999.0 Cement mortar 1:3 for fixing L.S. 89.7 2
9999.0 Labour for hoisting, Transporting and setting in L.S. 269.1 2
position
TOTAL
Add 1 % Water charges on "W-A" 1215.39
TOTAL
Add GST (multiplying factor 0.1405) on "X-A" 1227.55
TOTAL
Add 15 % Contractor's profit and overheads on 1400.02
"Y-A"
Total
Add Cess @ 1% on "Z-A" 1610.02
Cost for 0.99 cum
Cost for 1 cum.
Say

5.16 Providing, hoisting and fixing


above plinth level
Details of cost for up to floor five level
on shelf
precast reinforced cement concrete in
shelves, including setting in cement mortar
0.90x0.45x0.04m thick
= 0.90x0.45x0.04m = 0.0162 cum
Cement concrete 1:1½:3
4.1.2 Rate as per Item No.4.1.2 of SH: Concrete cum 0.0162 6376.3
Work
Finishing
13.2 Rate same as per iem no. 13.18 of sqm 0.85 42.1
Centring and shuttering:
4.3.1 Rate same as per item no. 4.3.1 of sqm 0.108 216.45
SH : concrete work
2x(0.90+0.45)x0.04 = 0.108 sqm
Extra labour for lifting material upto floor V
18.0 level
Coolie day 0.018 350.00
LABOUR
Extra labour for laying cement concrete in RCC
work due to delay etc.
17.0 Beldar day 0.016 350.00
11.0 Bhisti day 0.0032 350.00
23.0 Mason (brick layer) 1st class day 0.0006 505.17
24.0 Mason (brick layer) 2nd class day 0.0006 403.67
28.0 Mate day 0.0006 350.00
9999.0 Cement mortar 1:3 for fixing L.S. 4.42 2
9999.0 Labour for hoisting, Transporting and setting in L.S. 13.52 2
position
TOTAL
Add 1 % Water charges on "W-A" 48.52
TOTAL
Add GST (multiplying factor 0.1405) on "X-A" 49
TOTAL
Add 15 % Contractor's profit and overheads on 55.89
"Y-A"
Total
Add Cess @ 1% on "Z-A" 64.27
Cost for 0.0162 cum
Cost for 1 cum.
Say

5.17 Providing, hoisting and fixing


above
Details ofplinth
cost for level
4 RCC up to floor
vertical fins 4mfive level
high at 1m centre
to centre with
precast two horizontal
reinforced fins, all projecting
cement concrete 60cm
in from
face of wall and 5cm thick cubical contents = 0.66 cum.
vertical & horizontal fins, individually or
MATERIAL
Cement concrete 1:1½:3
4.1.2 Rate as per Item No.4.1.2 of SH: Concrete cum 0.66 6376.3
Work
Centering and shuttering
4.3.1 Rate as per item no. 4.3.1 of SH: Concrete sqm 2.56 216.45
work
Extra labour for lifting material upto floor V
18.0 level
Coolie day 0.75 350.00
LABOUR
Extra labour for laying cement concrete in RCC
work due to delay etc.
17.0 Beldar day 0.066 350.00
11.0 Bhisti day 0.132 350.00
23.0 Mason (brick layer) 1st class day 0.0264 505.17
24.0 Mason (brick layer) 2nd class day 0.0264 403.67
28.0 Mate day 0.0264 350.00
9999.0 Cement mortar 1:3 for fixing L.S. 17.94 2
9999.0 Labour for hoisting, Transporting and setting in L.S. 71.76 2
9999.0 position
Sundries L.S. 17.94 2
TOTAL
Add 1 % Water charges on "W-A" 550.35
TOTAL
Add GST (multiplying factor 0.1405) on "X-A" 555.85
TOTAL
Add 15 % Contractor's profit and overheads on 633.95
"Y-A"
Total
Add Cess @ 1% on "Z-A" 729.04
Cost for 0.66 cum
Cost for 1 cum.
Say

5.18 Providing precast cement


concrete
5.18.1 Jali
50 mm1:2:4 (1 cement : 2 coarse
thick
sand) : 4 graded stone aggregate 6mm
nominal size ), reinforced with 1.6 mm dia
Details of cost for jali

2.00mx0.75m = 1.50 sqm.


768.0 Cement Concrete Jali 50 mm thick sqm 1.5 400
9999.0 Mortar for fixing L.S. 6.24 2
9988.0 Carriage and sundries L.S. 6.2 2
LABOUR
23.0 Mason (brick layer) 1st class day 0.3 505.17
24.0 Mason (brick layer) 2nd class day 0.3 403.67
17.0 Beldar day 1.08 350.00
TOTAL
Add 1 % Water charges on "W"
TOTAL
Add GST (multiplying factor 0.1405) on "X"
TOTAL
Add 15 % Contractor's profit and overheads on "Y"
Total
Add Cess @ 1% on "Z"
Cost of 1.50 sqm.
Cost of 1 sqm.
Say

5.18.2 40 mm thick
Details of cost for 1.2mx0.60m = 0.72 sqm.
769.0 Cement Concrete Jali 40 mm thick sqm 0.72 350
9999.0 Mortar for fixing L.S. 3.64 2
9988.0 Carriage and sundries L.S. 3.64 2
LABOUR
24.0 Mason (brick layer) 2nd class day 0.12 403.67
17.0 Beldar day 0.5 350.00
TOTAL
Add 1 % Water charges on "W"
TOTAL
Add GST (multiplying factor 0.1405) on "X"
TOTAL
Add 15 % Contractor's profit and overheads on "Y"
Total
Add Cess @ 1% on "Z"
Cost of 0.72sqm.
Cost of 1 sqm.
Say

5.18.3 25 mm thick
Details of cost for jali 0.75mx0.5m =
0.375 sqm
770.0 Cement Concrete Jali 25 mm thick sqm 0.375 275
9999.0 Mortar for fixing L.S. 1.82 2
9988.0 Carriage and sundries L.S. 1.82 2
LABOUR
23.0 Mason (brick layer) 1st class day 0.06 505.17
24.0 Mason (brick layer) 2nd class day 0.06 403.67
17.0 Beldar day 0.25 350.00
TOTAL
Add 1 % Water charges on "W"
TOTAL
Add GST (multiplying factor 0.1405) on "X"
TOTAL
Add 15 % Contractor's profit and overheads on "Y"
Total
Add Cess @ 1% on "Z"
Cost of 0.375 sqm.
Cost of 1 sqm.
Say

5.19 Encasing rolled steel sections, in


beams
cost of and columns, with cement concrete
reinforcement.
1:1.5:3 (1 cement : 1.5 coarse sand) : 3
Details of cost for 0.424 cum.
graded stone aggregate 20 mm nominal

Consider 2 R.S. Joist (150mmx80mm) 4.88m


long placed 30cm apart centre to centre
Overall dimensions of the beam 43cmx20cm-
MATERIAL
Concrete work-
4.93x0.43x0.20 = 0.424 cum for 1:1½:3
Cement Concrete (1 cement: 1½ coarse sand
: 3 stone aggregate 20mm nominal size)
4.1.2 Rate as per Item No.4.1.2 of SH: Concrete cum 0.424 6376.3
Work
Extra labour for laying C.C. in RCC work
17.0 Beldar day 0.042 350.00
11.0 Bhisti day 0.085 350.00
23.0 Mason (brick layer) 1st class day 0.017 505.17
24.0 Mason (brick layer) 2nd class day 0.017 403.67
28.0 Mate day 0.017 350.00
Form work-
4.93x0.83 girth = 4.09 sqm.
5.9.5 Rate as per item 5.9.5 of sqm 4.09 387.15
SH: Reinforced cement concrete work
9999.0 Sundries and for lifting materials L.S. 21.58 2
TOTAL
Add 1 % Water charges on "W-A" 103.82
TOTAL
Add GST (multiplying factor 0.1405) on "X-A" 104.86
TOTAL
Add 15 % Contractor's profit and overheads on 119.59
"Y-A"
Total
Add Cess @ 1% on "Z-A" 137.53
Cost of 0.424 cum
Cost of 1 cum.
Say
5.2 Encasing rolled steel section in grillages
with cement
cement : 1.5 concrete 1:1.5:3
coarse sand): (1
3 graded stone
aggregate 20 mm nominal size,
including centering and shuttering but,
excluding cost of expanded metal
and hangers.
Details of cost for the grillage 3.50mx
3.50mx1.00m = 12.25 cum
Cement concrete 1:1½:3
4.1.2 Rate as per Item No.4.1.2 of SH: Concrete cum 12.25 6376.3
Work
Extra labour for laying C.C. in RCC work
17.0 Beldar day 1.225 350.00
11.0 Bhisti day 2.45 350.00
23.0 Mason (brick layer) 1st class day 0.49 505.17
24.0 Mason (brick layer) 2nd class day 0.49 403.67
28.0 Mate day 0.49 350.00
Shuttering :
4.93x0.83 girth =4.09 sqm
5.9.5 Rate as per item 5.9.5 of SH: Reinforced sqm 4.09 387.15
cement concrete work
TOTAL
Add 1 % Water charges on "W-A" 1753
TOTAL
Add GST (multiplying factor 0.1405) on "X-A" 1770.53
TOTAL
Add 15 % Contractor's profit and overheads on 2019.29
Total
Add Cess @ 1% on "Z-A" 2322.19
Cost of 12.25 cum.
Cost of 1 cum.
Say

5.21 Extra for providing and fixing


expanded
hangers. metal mesh of size 20x60 mm
and strands 3.25 mm wide 1.6 mm thick
Deatail of cost for 10 sqm
weighing 3.64 kg per sqm for encasing of
MATERIAL
Expended metal 20 mm x 60 mm and
1.6 mm thick = 10 sqm
Wastage 5% = 0.5 sqm
Total =10.50 sqm
1015.0 Mild steel expanded metal 20x60 mm strands sqm 10.5 32
9977.0 Carriage of expended metal L.S. 13.52 2
9999.0 Wire for tieing L.S. 13.52 2
Cost of bending and placing in position
12.0 Blacksmith 1st class day 0.25 505.17
17.0 Beldar day 0.25 350.00
TOTAL
Add 1 % Water charges on "W"
TOTAL
Add GST (multiplying factor 0.1405) on "X"
TOTAL
Add 15 % Contractor's profit and overheads on "Y"
Total
Add Cess @ 1% on "Z"
Cost of 10 sqm
Cost of 1 sqm.
Say
5.22 Steel reinforcement for R.C.C. work
including
5.22.1 straightening,
Mild cutting, bending,
steel and Medium Tensile
placing in
steel bars position and binding all complete
upto plinth level.
Details of cost for 1 quintal-
MATERIAL
Mild steel bars = 1.00 q
Wastage 5% = 0.05 q
Total = 1.05 q
1004.0 Average rate of Mild steel round bars for quintal 1.05 5500
2205.0 reinforcements
Carriage of Steel 1.05/10 = 0.105t tonne 0.105 94.34
9999.0 Cover block L.S. 26 2
LABOUR
For straightening, cutting, bending, binding and
12.0 placing in position-
Blacksmith 1st class day 1 505.17
17.0 Beldar day 1 350.00
9999.0 Sundries and binding wire L.S. 26.91 2
TOTAL
Add 1 % Water charges on "W"
TOTAL
Add GST (multiplying factor 0.1405) on "X"
TOTAL
Add 15 % Contractor's profit and overheads on "Y"
Total
Add Cess @ 1% on "Z"
Cost of one quintal
Cost of 1 Kg.
Say

5.22.2 Hard drawn steel wire


Details of cost for 1 quintal-
MATERIAL
Hard drawn steel wire = 1.00 q
Wastage 5% = 0.05 q
Total = 1.05 q
1224.0 Hard drawn steel wire quintal 1.05 4800
2205.0 Carriage of Steel 1.05q = 0.105 tonne tonne 0.105 94.34
LABOUR
For cutting and laying in position etc.-
12.0 Blacksmith 1st class day 1 505.17
17.0 Beldar day 1 350.00
9999.0 Sundries L.S. 26.91 2
TOTAL
Add 1 % Water charges on "W"
TOTAL
Add GST (multiplying factor 0.1405) on "X"
TOTAL
Add 15 % Contractor's profit and overheads on "Y"
Total
Add Cess @ 1% on "Z"
Cost of one quintal
Cost of 1 Kg.
Say

5.22.3 Cold twisted bars


Details of cost for 1 quintal-
MATERIAL
Deformed twisted steel bars = 1.00 q
Wastage 5% = 0.05 q
Total = 1.05q
1005.0 Twisted steel / deformed bars quintal 1.05 5500
2205.0 Carriage of Steel 1.05/10 = 0.105t tonne 0.105 94.34
9999.0 Cover block L.S. 26 2
LABOUR
For straightening, cutting, bending, binding and
12.0 placing in position-
Blacksmith 1st class day 1 505.17
17.0 Beldar day 1 350.00
9999.0 Sundries and binding wire L.S. 26.91 2
TOTAL
Add 1 % Water charges on "W"
TOTAL
Add GST (multiplying factor 0.1405) on "X"
TOTAL
Add 15 % Contractor's profit and overheads on "Y"
Total

Wastage 5% = 0.05 q
Total = 1.05q
1005.0 Twisted steel / deformed bars quintal 1.05 5500
2205.0 Carriage of Steel 1.05/10 = 0.105t tonne 0.105 94.34
9999.0 Cover block L.S. 26 2
LABOUR
For straightening, cutting, bending, binding and
12.0 placing in position-
Blacksmith 1st class day 1 505.17
17.0 Beldar day 1 350.00
9999.0 Sundries and binding wire L.S. 26.91 2
TOTAL
Add 1 % Water charges on "W"
TOTAL
Add GST (multiplying factor 0.1405) on "X"
TOTAL
Add 15 % Contractor's profit and overheads on "Y"
Total
Add Cess @ 1% on "Z"
Cost of one quintal
Cost of 1 Kg.
Say

5.22.5 Hard drawn steel wire fabric

Details of cost for 1 quintal-


MATERIAL
Hard drawn steel wire fabric 100kg , 7.75kg per
sqm = 12.903 sqm.
Add 5% wastage = 0.645 sqm. Total =13.548
1021.0 sqm
Hard drawn steel wire fabric sqm 13.548 430
2205.0 Carriage 1.05q = 0.105 tonne tonne 0.105 94.34
9999.0 Cover block L.S. 26 2
LABOUR
For cutting and laying in position.
13.0 Blacksmith 2nd class day 0.2 403.67
17.0 Beldar day 1.5 350.00
9999.0 Sundries and binding wire L.S. 13.52 2
TOTAL
Add 1 % Water charges on "W"
TOTAL
Add GST (multiplying factor 0.1405) on "X"
TOTAL
Add 15 % Contractor's profit and overheads on "Y"
Total
Add Cess @ 1% on "Z"
Cost of one quintal
Cost of 1 Kg.
Say

5.22.6 Thermo-Mechanically Treated bars of grade


Fe-500D or more.
Details of cost for 1 quintal-
MATERIAL
Deformed twisted steel bars = 1.00 q
Wastage 5% = 0.05 q
Total =1.05q
1005.0 Twisted steel / deformed TMT Fe-500D quintal 1.05 5500
2205.0 Carriage of steel 1.05/10 = 0.105t tonne 0.105 94.34
9999.0 Cover block L.S. 26 2
LABOUR
For straightening, cutting, bending, binding and
12.0 placing in position-
Blacksmith 1st class day 1 505.17
17.0 Beldar day 1 350.00
9999.0 Sundries and binding wire L.S. 26.91 2
TOTAL
Add 1 % Water charges on "W"
TOTAL
Add GST (multiplying factor 0.1405) on "X"
TOTAL
Add 15 % Contractor's profit and overheads on "Y"
Total
Add Cess @ 1% on "Z"
Cost of one quintal
Cost of 1 Kg.
Say

5.22A Steel reinforcement for R.C.C. work


including straightening,
bending, placing cutting,
in position and binding all
complete above plinth level.
5.22A.1 Mild steel and Medium Tensile steel bars
Details of cost for 1 quintal-
MATERIAL
Mild steel bars = 1.00 q
Wastage 5% = 0.05 q Total = 1.05 q
1004.0 Average rate of Mild steel round bars for quintal 1.05 5500
2205.0 reinforcements
Carriage of Steel NOS/ 10 = 0.105 t tonne 0.105 94.34
9999.0 Cover block L.S. 26 2
LABOUR
For straightening, cutting, bending, binding and
12.0 placing in position-
Blacksmith 1st class day 1 505.17
17.0 Beldar day 1 350.00
9999.0 Sundries and binding wire L.S. 26.91 2
TOTAL
Add 1 % Water charges on "W"
TOTAL
Add GST (multiplying factor 0.1405) on "X"
TOTAL
Add 15 % Contractor's profit and overheads on "Y"
Total
Add Cess @ 1% on "Z"
Cost of one quintal
Cost of 1 Kg.
Say
5.22A.2 Hard drawn steel wire
Details of cost for 1 quintal-
MATERIAL
Hard drawn steel wire = 1.00 q
Wastage 5% = 0.05 q
Total = 1.05 q
1224.0 Hard drawn steel wire quintal 1.05 4800
2205.0 Carriage of Steel tonne 0.105 94.34
LABOUR
For cutting and laying in position etc.-
12.0 Blacksmith 1st class day 1 505.17
17.0 Beldar day 1 350.00
9999.0 Sundries L.S. 26.91 2
TOTAL
Add 1 % Water charges on "W"
TOTAL
Add GST (multiplying factor 0.1405) on "X"
TOTAL
Add 15 % Contractor's profit and overheads on "Y"
Total
Add Cess @ 1% on "Z"
Cost of one quintal
Cost of 1 Kg.
Say
5.22A.3 Cold twisted bars
Details of cost for 1 quintal-
MATERIAL
Deformed twisted steel bars = 1.00 q
Wastage 5% = 0.05 q
Total = 1.05q
1005.0 Twisted steel / deformed bars quintal 1.05 5500
2205.0 Carriage of Steel tonne 0.105 94.34
9999.0 Cover block L.S. 26 2
LABOUR
For straightening, cutting, bending, binding and
12.0 placing in position-
Blacksmith 1st class day 1 505.17
17.0 Beldar day 1 350.00
9999.0 Sundries and binding wire L.S. 26.91 2
TOTAL
Add 1 % Water charges on "W"
TOTAL
Add GST (multiplying factor 0.1405) on "X"
TOTAL
Add 15 % Contractor's profit and overheads on "Y"
Total
Add Cess @ 1% on "Z"
Cost of one quintal
Cost of 1 Kg.
Say

5.22A.4 Hot rolled deformed bars


Details of cost for 1 quintal-
MATERIAL
Deformed twisted steel bars = 1.00 q
Wastage 5% = 0.05 q
Total = 1.05q
1005.0 Twisted steel / deformed bars quintal 1.05 5500
2205.0 Carriage of Steel tonne 0.105 94.34
9999.0 Cover block L.S. 26 2
LABOUR
For straightening, cutting, bending, binding and
12.0 placing in position-
Blacksmith 1st class day 1 505.17
17.0 Beldar day 1 350.00
9999.0 Sundries and binding wire L.S. 26.91 2
TOTAL
Add 1 % Water charges on "W"
TOTAL
Add GST (multiplying factor 0.1405) on "X"
TOTAL
Add 15 % Contractor's profit and overheads on "Y"
Total
Add Cess @ 1% on "Z"
Cost of one quintal
Cost of 1 Kg.
Say
5.22A.5 Hard drawn steel wire fabric
Details of cost for 1 quintal-
MATERIAL
Hard drawn steel wire fabric 100kg, 7.75kg per
sqm = 12.903 sqm.
Add 5% wastage = 0.645
sqm. Total
1021 =13.548 sqm
Hard drawn steel wire fabric sqm 13.548 430
2205.0 Carriage of Steel tonne 0.105 94.34
9999.0 Cover block L.S. 26 2

LABOUR

For cutting and laying in position.


13.0 Blacksmith 2nd class day 0.2 403.67
17.0 Beldar day 1.5 350.00
9999.0 Sundries and binding wire L.S. 13.52 2
TOTAL
Add 1 % Water charges on "W"
TOTAL
Add GST (multiplying factor 0.1405) on "X"
TOTAL
Add 15 % Contractor's profit and overheads on "Y"
Total
Add Cess @ 1% on "Z"
Cost of one quintal
Cost of 1 Kg.
Say
5.22A.6 Thermo-Mechanically Treated bars of grade
Fe-500D or more.
Details of cost for 1 quintal-
MATERIAL
Deformed twisted steel bars = 1.00 q
Wastage 5% = 0.05 q
Total =1.05q
1005.0 Twisted steel / deformed bars quintal 1.05 5500
2205.0 Carriage of Steel tonne 0.105 94.34
9999.0 Cover block L.S. 26 2
LABOUR
For straightening, cutting, bending, binding and
12.0 placing in position-
Blacksmith 1st class day 1 505.17
17.0 Beldar day 1 350.00
9999.0 Sundries and binding wire L.S. 26.91 2
TOTAL
Add 1 % Water charges on "W"
TOTAL
Add GST (multiplying factor 0.1405) on "X"
TOTAL
Add 15 % Contractor's profit and overheads on "Y"
Total
Add Cess @ 1% on "Z"
Cost of one quintal
Cost of 1 Kg.
Say

5.22B Steel reinforcement for R.C.C. work ready


to use "cutmake
approved and bend" rebars of
from factory/workshop to
construction site including placing
in position and binding all complete upto
5.22B.1 plinth level.
Thermo-Mechanically Treated bars of grade
Fe-500D
Details or more.
of cost for 1 quintal-
MATERIAL
Deformed twisted steel bars = 1.00 q
Total =1.00q
1005.0 Twisted steel / deformed bars quintal 1 5500
2205.0 Carriage of Steel tonne 0.1 94.34
9999.0 Cover block L.S. 26 2
LABOUR
9999.0 For cut and bend L.S. 156 2
For binding and placing in position
12.0 Blacksmith 1st class day 0.6 505.17
17.0 Beldar day 0.6 350.00
9999.0 Sundries and binding wire L.S. 26.91 2
TOTAL
Add 1 % Water charges on "W"
TOTAL
Add GST (multiplying factor 0.1405) on "X"
TOTAL
Add 15 % Contractor's profit and overheads on "Y"
Total
Add Cess @ 1% on "Z"
Cost of one quintal
Cost of 1 Kg.
Say
5.22C Steel reinforcement for R.C.C. work ready
to use "cutmake
approved and bend" rebars of
from factory/workshop to
construction site including placing
in position and binding all complete above
5.22C.1 plinth level.
Thermo-Mechanically Treated bars of grade
Fe-500D
Details or more.
of cost for 1 quintal-
MATERIAL
Deformed twisted steel bars = 1.00 q
Total =1.00q
1005.0 Twisted steel / deformed bars quintal 1 5500
2205.0 Carriage of Steel tonne 0.1 94.338
9999.0 Cover block L.S. 26 2
LABOUR
9999.0 For cut and bend L.S. 156 2
For binding and placing in position
12.0 Blacksmith 1st class day 0.6 505.17
17.0 Beldar day 0.6 350.00
9999.0 Sundries and binding wire L.S. 26.91 2
TOTAL
Add 1 % Water charges on "W"
TOTAL
Add GST (multiplying factor 0.1405) on "X"
TOTAL
Add 15 % Contractor's profit and overheads on "Y"
Total
Add Cess @ 1% on "Z"
Cost of one quintal
Cost of 1 Kg.
Say

5.23 Smooth finishing of the exposed


surface of R.C.C. work with 6 mm thick
cement mortar 1:3 (1 Cement : 3 fine sand).
Details of cost for 10sqm.

MATERIAL
Cement mortar 1 : 3 (1 cement : 3 fine sand)
3.3 Rate as per item No 3.3 of SH: Mortars cum 0.072 3988
40.0 Mason (average) day 0.51 403.67
18.0 Coolie day 0.75 350.00
11.0 Bhisti day 0.92 350.00
9999.0 Extra for removing burrs, cleaning with wire L.S. 13.39 2
brushes pock marking with pointed tool etc.
complete
9999.0 Scaffolding and Sundries L.S. 11.7 2
TOTAL
Add 1 % Water charges on "W"
TOTAL
Add GST (multiplying factor 0.1405) on "X"
TOTAL
Add 15 % Contractor's profit and overheads on "Y"
Total
Add Cess @ 1% on "Z"
Cost of 10 Sqm.
Cost per sqm.
Say

5.24 Extra for rendering smooth the


top of suspended floors, landings and
staircases (treads and risers) with cement
Details of cost for 10sqm.
mortar 1:2 (1 cement : 2 coarse sand),
MATERIAL
Cement mortar 1:2 (1 Cement : 2 Coarse sand)
3.7 Rate as per item No 3.7 of SH: Mortars cum 0.03 5150.6
367.0 Portland Cement tonne 0.0213 4375
2209.0 Carriage of Cement tonne 0.0213 94.34
LABOUR
23.0 Mason (brick layer) 1st class Day 0.2 505.17
24.0 Mason (brick layer) 2nd class Day 0.2 403.67
17.0 Beldar Day 0.25 350.00
9999.0 Spreading earth on floor (7.5mm thick) L.S. 35.49 2
983.0 Spreading sand 15mm thick on floor 850
Fine sand cum 0.15 900
2261.0 Carriage of Fine sand (1 part badarpur sand : 2 cum 0.15 106.13

parts Sand)
9999.0 Disposal of earth spread over floor protectIron L.S. 5.33 2
9999.0 Sundries L.S. 6.24 2
TOTAL
Add 1 % Water charges on "W"
TOTAL
Add GST (multiplying factor 0.1405) on "X"
TOTAL
Add 15 % Contractor's profit and overheads on "Y"
Total
Add Cess @ 1% on "Z"
Cost of 10 Sqm.
Cost per sqm.
Say

5.25 Providing and fixing in position


copper
joints. plate as per design for expansion

Details of cost for 10.56 kg Considering 3.0 m length,


width 250mm and 1.6 mm thick = 0.750 sqm copper
plate.
Weight of copper plate @ 14.08 kg/m2 10.56kg
967 Copper plate

LABOUR
kilo 10.56 527
gram
13.0 Blacksmith 2nd class day 0.25 403.67
9999.0 Sundries L.S. 6.24 2
TOTAL
Add 1 % Water charges on "W"
TOTAL
Add GST (multiplying factor 0.1405) on "X"
TOTAL
Add 15 % Contractor's profit and overheads on "Y"
Total
Add Cess @ 1% on "Z"
Cost of 10.56 kg
Cost per kg.
Say

5.26 Providing and filling in position,


blown
Details of cost for ainjoint
bitumen expansion joints.
of 300m length
2.5cm width and 15cm depth = 1.125 cum
Cubical content of joint-300x0.025x0.150=1.125 cum.
MATERIAL
Bitumen 85/25 @ 1050kg per cum.
1.25x1050kg = 1181.25kg
Add wastage @ 5% = 59.06 kg. = 1240.31 =
313.0 1.240 tonne
Blown type petroleum bitumen of penetration tonne 1.24 34000
85/25 of approved quality
2211.0 Carriage of Tar/ bitumen tonne 1.24 106.13
370.0 Coal (steam) quintal 2.48 440

For heating of bitumen @ 2.0 quintal per tonne

of bitumen. 1.240x2.0=2.48q=0.248t

LABOUR
Labour for heating, mixing and filling-
2200.0 Carriage of Tar/ bitumen tonne 0.248 121.29
23.0 Mason (brick layer) 1st class day 2.52 505.17
24.0 Mason (brick layer) 2nd class day 2.52 403.67
17.0 Beldar day 8.06 350.00
9999.0 Sundries L.S. 121.16 2
TOTAL
Add 1 % Water charges on "W"
TOTAL
Add GST (multiplying factor 0.1405) on "X"
TOTAL
Add 15 % Contractor's profit and overheads on "Y"
Total
Add Cess @ 1% on "Z"
Cost for 1.125 cum
cost for 1.00cum
Say

5.27 Providing and filling in position


bitumen
joints. mix filler of Proportion 80 kg. of
hot bitumen, 1 kg. of cement and 0.25 cubic
metre of coarse sand for expansion
Details of cost for a joint of 300m length 2.5cm width
and 15cm depth = 1.125 cum Cubical content of
joints-300x0.150x0.025=1.125cum.
MATERIAL

Bitumen S-90 = 256.30 kg per cum.


256.30x1.125 = 288.34 kg.
Add for wastage @ 5% = 14.42 kg.
Total = 302.76 kg. or = 0.303 tonne.
309.0 Paving bitumen VG-10 of approved quality tonne 0.303 48000
2211.0 Carriage of Tar bitumen tonne 0.303 106.13
370.0 Coal (steam) for heating of bitumen @ 2.0 quintal 0.606 440
quintal pertonne of bitumen, i.e.
0.303x2.0=0.606q
2200.0 Carriage of steam coal tonne 0.061 121.29
367.0 Portland Cement tonne 0.0036 4375
1/80x228.34=3.6 kg = 0.0036 Tonne
2209.0 Carriage of Cement tonne 0.0036 94.34
982.0 Coarse sand cum 0.9 800
1/4th of the quantity of cement in kg =
3.6/4= 0.90 cum
2203.0 Carriage of Coarse sand cum 0.9 584.88
LABOUR
Labour for heating and filling :
23.0 Mason (brick layer) 1st class day 2.52 505.17
24.0 Mason (brick layer) 2nd class day 2.52 403.67
17.0 Beldar day 8.06 350.00
9999.0 Sundries L.S. 121.16 2
TOTAL
Add 1 % Water charges on "W"
TOTAL
Add GST (multiplying factor 0.1405) on "X"
TOTAL
Add 15 % Contractor's profit and overheads on "Y"
Total
Add Cess @ 1% on "Z"
Cost for 1.125 cum
cost for 1.00cum
Say

5.28 Providing and fixing in position


12mm thick bitumen
in expansion joints. impregnated fiber
board conforming to IS: 1838, including
Details of cost for joint 100m long 10cm deep =
cost of primer, sealing compound Grade-A
10 sqm
MATERIAL
(i) Impregnated fibre board 1x100x
0.075=7.5sqm
339.0 Flame retardent face insulating, Impregnated sqm 7.5 375
fibre board 12 mm thick
(ii) Primere 80m/litter 100m=100/80 x1=1.25 lit
316.0 Bitumen solution primer of approved quality litre 1.25 45
(iii) Sealing compound @ 3 m per litre for
100m = 100/3x1 =33.3 litres
Wastage @ 5% = 1.67
Total = 35.00 litre
(1 litre = 0.9 kg) = 35.00x0.9 = 31.5 kg
314.0 Bitumen hot sealing compound : grade A kilogra 31.5 28
9977.0 m
Carriage L.S. 26.91 2
LABOUR
23.0 Mason (brick layer) 1st class day 0.12 505.17
24.0 Mason (brick layer) 2nd class day 0.12 403.67
17.0 Beldar day 0.25 350.00
9999.0 Sundries L.S. 26.91 2
TOTAL
Add 1 % Water charges on "W"
TOTAL
Add GST (multiplying factor 0.1405) on "X"
TOTAL
Add 15 % Contractor's profit and overheads on "Y"
Total
Add Cess @ 1% on "Z"
Cost for 100m long 10cm deep
Cost per cm depth per 100m long
Say

5.29 Providing and fixing sheet


covering
5.29.1 over expansionfibre
Non-asbestos joints with iron
cement board
screws as per design.
6 mm thick as per IS: 14862.
5.29.1.1 150mm wide

Details of cost for 3m length


MATERIAL
236.0 Non - Asbestos multi purpose fibre (high sqm 0.47 210
impact poly propelene reinforced) cement
board 6mm thick.
2273.0 Carriage of A.C.sheet and accessories tonne 0.0049 94.34
0.45sqm = 0.0049 tonne
9999.0 50mm iron screws with washer and rawl plugs L.S. 40.3 2
LABOUR
15.0 Carpenter 2nd class day 0.2 403.67
17.0 Beldar day 0.2 350.00
TOTAL
Add 1 % Water charges on "W"
TOTAL
Add GST (multiplying factor 0.1405) on "X"
TOTAL
Add 15 % Contractor's profit and overheads on "Y"
Total
Add Cess @ 1% on "Z"
Cost for 3m
Cost per meter
Say

5.29.1.2 200mm wide


Details of cost for 3m length
MATERIAL
236.0 Non - Asbestos multi purpose fibre (high sqm 0.63 210
impact poly propelene reinforced) cement
board 6mm thick.
2273.0 Carriage of A.C.sheet and accessories tonne 0.0065 94.34
0.60sqm. = 0.0065 tonne
9999.0 50mm iron screws with washer and rawl plugs L.S. 53.82 2
LABOUR
15.0 Carpenter 2nd class day 0.27 403.67
17.0 Beldar day 0.27 350.00
TOTAL
Add 1 % Water charges on "W"
TOTAL
Add GST (multiplying factor 0.1405) on "X"
TOTAL
Add 15 % Contractor's profit and overheads on "Y"
Total
Add Cess @ 1% on "Z"
Cost for 3m
Cost per meter
Say

5.29.2 Aluminium fluted strips 3.15 mm


thick.
5.29.2.1 150 mm wide
Details of cost for 1 meter
MATERIAL
2391.0 Strips-Aluminium fluted 3.15mm thick and metre 1 278
639.0 150mm wide
Bright finished or black enamelled mild steel 100 0.06 36
9977.0 screws 25 mm Nos
Carriage of materials L.S. 1.04 2
LABOUR
15.0 Carpenter 2nd class day 0.067 403.67
17.0 Beldar day 0.067 350.00
9999.0 Sundries L.S. 1.82 2
TOTAL
Add 1 % Water charges on "W"
TOTAL
Add GST (multiplying factor 0.1405) on "X"
TOTAL
Add 15 % Contractor's profit and overheads on "Y"
Total
Add Cess @ 1% on "Z"
Cost for 1 metre
Say

5.29.2.2 200 mm wide


Details of cost for 1 meter
MATERIAL
2392.0 Strips Aluminium fluted 3.15mm thick and Metre 1 370
639.0 200mm wide metre
Bright finished or black enamelled mild steel 100 0.06 36
9977.0 screws 25 mm Nos
Carriage of materials L.S. 1.3 2
LABOUR
15.0 Carpenter 2nd class day 0.089 403.67
17.0 Beldar day 0.089 350.00
9999.0 Sundries L.S. 2.34 2
TOTAL
Add 1 % Water charges on "W"
TOTAL
Add GST (multiplying factor 0.1405) on "X"
TOTAL
Add 15 % Contractor's profit and overheads on "Y"
Total
Add Cess @ 1% on "Z"
Cost for 1 metre
Say

5.29.3 Non-asbestos Cement bonded


wood
14276 particle board 6mm thick as per IS :
5.29.3.1 150 mm wide
Details of cost for 3 metre
MATERIAL:
242.0 Multi purpose cement bonded wood particle sqm 0.47 195
2273.0 board 6 mm thick
Carriage of board and accessories tonne 0.005 94.34
0.45sqm = 0.0049 tonne
9999.0 50mm iron screws with washer and rawl plugs L.S 40.3 2
15.0 LABOUR:
Carpenter 2nd class day 0.2 403.67
17.0 Beldar day 0.2 350.00
TOTAL
Add 1 % Water charges on "W"
TOTAL
Add GST (multiplying factor 0.1405) on "X"
TOTAL
Add 15 % Contractor's profit and overheads on "Y"
Total
Add Cess @ 1% on "Z"
Cost of 3 metre
Cost of 1 metre
Say

5.29.3.2 200 mm wide


Details of cost for 3m length
MATERIAL:
242.0 Multi purpose cement bonded wood particle sqm 0.63 195
2273.0 board 6 mm thick
Carriage of board and accessories tonne 0.0065 94.34
0.60sqm = 0.0060 tonne
9999.0 50mm iron screws with washer and rawl plugs L.S 53.82 2
LABOUR:
15.0 Carpenter 2nd class day 0.27 403.67
17.0 Beldar day 0.27 350.00
TOTAL
Add 1 % Water charges on "W"
TOTAL
Add GST (multiplying factor 0.1405) on "X"
TOTAL
Add 15 % Contractor's profit and overheads on "Y"
Total
Add Cess @ 1% on "Z"
Cost of 3 metre
Cost of 1 metre
Say

5.30 Add for plaster drip course/


groove in plastered surface or moulding to
R.C.C. projections.
Details of cost for 30 metre long throating or

plaster or moulding-
LABOUR

23.0 Mason (brick layer) 1st class day 0.5 505.17


24.0 Mason (brick layer) 2nd class day 0.5 403.67
18.0 Coolie day 1 350.00
9999.0 Add for materials (cement mortar etc.) L.S. 26.91 2
TOTAL
Add 1 % Water charges on "W"
TOTAL
Add GST (multiplying factor 0.1405) on "X"
TOTAL
Add 15 % Contractor's profit and overheads on "Y"
Total
Add Cess @ 1% on "Z"
Cost for 30 metre
Cost per meter
Say

5.31 Extra for laying reinforced cement


concrete in or under water and/ or liquid
mud, including cost of pumping or bailing
Details of cost for depth of water 0.30m.
out water and removing slush etc.,
Quantity of concrete = 14 cum.
Analysis same as per item number 4.15
pumping hours = 3 hrs. or 0.375 day.
11.0 Hire charges of Pumpset of capacity 4000 day 0.375 700
litres/hour. for cleaning slush
17.0 Beldar day 4 350.00
TOTAL
Add 1 % Water charges on "W"
TOTAL
Add GST (multiplying factor 0.1405) on "X"
TOTAL
Add 15 % Contractor's profit and overheads on "Y"
Total
Add Cess @ 1% on "Z"
Cost of 14cum. per 0.30m depth
Cost of cum. per m depth
Say

5.32 Extra for laying reinforced cement


concrete in or
Details of cost forunder foul
depth of positions.
water 0.30m.
Details of cost for 1 cum.

ANALYSIS SAME AS ITEM NO 4.16


Extra labour due to slow progress-
23.0 Mason (brick layer) 1st class day 0.02 505.17
24.0 Mason (brick layer) 2nd class day 0.02 403.67
17.0 Beldar day 0.25 350.00
18.0 Coolie day 0.15 350.00
TOTAL
Add 1 % Water charges on "W"
TOTAL
Add GST (multiplying factor 0.1405) on "X"
TOTAL
Add 15 % Contractor's profit and overheads on "Y"
Total
Add Cess @ 1% on "Z"
Cost for 1 cum.
Say

5.33 Providing and laying in position


machine batched and machine mixed
design mix M-25 grade cement concrete for
reinforcedAll
5.33.1 worksconcrete
cement upto plinth level
work, using

Details of cost for 1.00 cum


MATERIAL
295.0 Stone Aggregate (Single size) : 20 mm nominal cum 0.57 800
297.0 size cum 0.28 810
Stone Aggregate (Single size) : 10 mm nominal
2202.0 size
Carriage of Stone aggregate below 40 mm cum 0.85 106.13
982.0 nominal size 800
Coarse sand cum 0.425 1350
2203.0 Carriage of Coarse sand cum 0.425 584.88
367.0 Portland Cement tonne 0.33 4375
2209.0 Carriage of Cement tonne 0.33 94.34
7318.0 Plasticizer / super plasticizer kilogra 1.65 36
0.50% of cement m
Production cost, pumping to respective floors
and laying in position
4.0 Production cost of concrete by batch mix plant. cum 1 350
9.0 Pumping charges of concrete including Hire cum 1 210

charges of pump, piping work & accessories


etc.
LABOUR
Labour for pouring, consolidating & curing
40.0 Mason (average) day 0.17 403.67
17.0 Beldar day 2 350.00
11.0 Bhisti day 0.9 350.00
12.0 Vibrator(Needle type 40mm) day 0.07 370
9999.0 Sundries L.S. 13 2
Total
Add 1 % Water charges on "W"
TOTAL
Add GST (multiplying factor 0.1405) on "X"
TOTAL
Add 15 % Contractor's profit and overheads on "Y"
Total
Cost per 1.00 cum
Say

5.33.2 All works above plinth level upto


floor V level
Details of cost for 1.00 cum
MATERIAL
295.0 Stone Aggregate (Single size) : 20 mm nominal cum 0.57 800
297.0 size cum 0.28 810
Stone Aggregate (Single size) : 10 mm nominal
2202.0 size
Carriage of Stone aggregate below 40 mm cum 0.85 106.13
982.0 nominal size 800
Coarse sand cum 0.425 1350
2203.0 Carriage of Coarse sand cum 0.425 584.88
367.0 Portland Cement tonne 0.33 4375
2209.0 Carriage of Cement tonne 0.33 94.34
7318.0 Plasticizer / super plasticizer kilogra 1.65 36
0.50% of cement m
Production cost, pumping to respective floors
and laying in position
4.0 Production cost of concrete by batch mix plant. cum 1 350
9.0 Pumping charges of concrete including Hire cum 1 210

charges of pump, piping work & accessories


etc.
Labour for pouring, consolidating & curing
40.0 Mason (average) day 0.17 403.67
17.0 Beldar day 2 350.00
11.0 Bhisti day 0.9 350.00
12.0 Vibrator(Needle type 40mm) day 0.07 370
9999.0 Sundries L.S. 13 2
(Extra labour for lifting material upto floor
V level : = 0.75 x 2.5 = 1.88)
18.0 Coolie day 1.88 350.00
Total
Add 1 % Water charges on "W"
TOTAL
Add GST (multiplying factor 0.1405) on "X"
TOTAL
Add 15 % Contractor's profit and overheads on "Y"
Total
Add Cess @ 1% on "Z"
Cost per 1.00 cum
Say

5.34 Extra for providing richer mixes at


all floor
5.34.1 levels. Note:-
Providing Excess/less
M-30 cement
grade concrete
over
insteadthecost
specified
Details of of M-25 cement content used is
for 1grade
cum. BMC/ RMC. (Note:-
payable content
Cement /recoverable separately.
considered in M-30 is @
340 kg/cum)
Cement for M-30 mix = 0.340 t
Cement for M-25 mix = 0.330 t
Difference = 0.010 t
367.0 Portland Cement tonne 0.01 4375
2209.0 Carriage of Cement tonne 0.01 94.34
Plasticizer for M-30 mix = 1.70 Kg
Plasticizer for M-25 mix = 1.65 Kg
Difference = 0.05 kg
7318.0 Plasticizer / super plasticizer kilo 0.05 36
gram
TOTAL
Add 1 % Water charges on "W"
TOTAL
Add GST (multiplying factor 0.1405) on "X"
TOTAL
Add 15 % Contractor's profit and overheads on "Y"
Total
Add Cess @ 1% on "Z"
Cost per cum.
Say

5.34.2 Providing M-35 grade concrete


instead of
Cement M-25 grade
content BMC/ RMC.
considered (Note
in M-35 is @:
350 kg/ cum)
Details of cost for 1 cum.

Cement for M-35 mix = 0.350 t


Cement for M-25 mix = 0.330 t
Difference 0.020 t
367.0 Portland Cement tonne 0.02 4375
2209.0 Carriage of Cement tonne 0.02 94.34
Plasticizer for M-35 mix = 1.75 Kg
Plasticizer for M-25mix = 1.65 Kg
Difference = 0.10 kg
7318 Plasticizer / super plasticizer kilo 0.1 36
TOTAL gram

Add 1 % Water charges on "W"


TOTAL
Add GST (multiplying factor 0.1405) on "X"
TOTAL
Add 15 % Contractor's profit and overheads on "Y"
Total
Add Cess @ 1% on "Z"
Cost per cum.
Say
5.34.3 Providing M-40 grade concrete
instead of M-25 grade
Cement content BMC/ RMC.(Note
considered in M-40 is @:
360 kg/ cum)
Details of cost for 1 cum.

Cement for M-40 mix = 0.360 t


Cement for M-25 mix = 0.330 t
Difference = 0.030 t
367.0 Portland Cement tonne 0.03 4375
2209.0 Carriage of Cement tonne 0.03 94.34
Plasticizer for M-40 mix = 1.80 Kg
Plasticizer for M-25 mix = 1.65 Kg
Difference = 0.15 kg
7318 Plasticizer / super plasticizer kilogra 0.15 36
TOTAL
Add 1 % Water charges on "W"
TOTAL
Add GST (multiplying factor 0.1405) on "X"
TOTAL
Add 15 % Contractor's profit and overheads on "Y"
Total
Add Cess @ 1% on "Z"
Cost per cum.
Say

5.35 Add for using extra cement in the


items
specified cementmix
of design over and
content above the
therein.
Details of cost for 1 quintal

367.0 Portland Cement tonne 0.1 4375


2209.0 Carriage of Cement tonne 0.1 94.34
TOTAL
Add 1 % Water charges on "W"
TOTAL
Add GST (multiplying factor 0.1405) on "X"
TOTAL
Add 15 % Contractor's profit and overheads on "Y"
Total
Add Cess @ 1% on "Z"
Cost per quintal
Say

5.36 Providing and placing in position


precast reinforced cement concrete waffle
Details of cost for 1.38 cum
units, square or rectangular, as per design
Consider a waffle 09. x 0.9 x 0.3m
and shape for floors and roofs in 1:1½:3 (1
Total area covered 4.548x3.636 = 16.54 sqm
Cement concrete in 1 unit
Top 0.8x0.8x0.035 = 0.0224
Sides 2(0.8x0.265x0.0325) = 0.0138
2(0.735x0.265x0.0325) = 0.0127
Total = 0.0489
Flange 4x0.85x0.05x0.035 = 0.0060
Total = 0.0549
Add for Fillets 25% = 0.0137 Total = 0.069
cum.
Quantity for 20 such units = 1.38 cum.
5.2.2 Rate as per item no 5.2.2 of SH : RCC cum 1.38 7633.2
(i) Shuttering and centring
Face in contact
4x0.8x0.265 = 0.848
Inner 4x0.735x0.265 = 0.779
Top (inside) 1x0.735x0.735 = 0.540 Flange
4x0.9x0.035 = 0.126 Total = 2.293 sqm.
Quantity 20 such units 45.86 sqm.
5.9.15 Rate as per item no 5.9.15 of SH : RCC sqm 45.86 216.45
Hooks for lifting 2x1.5 = 3.0m
4x0.01 = 0.04m
Total = 3.04m
@ 3kg per m-9.12Kg or 0.009 t = 9 kg
10.2 Rate as per item no 10.2 of SH : Steel work kg 9 86.65
9988.0 (iii) 10mm dia. Bolts 60mm long with nuts and L.S. 13 2
washers 2x2 = 4 Nos. including carriage of
9999.0 bolts
Sundries L.S. 79.95 2
(iv) Transportation and erection labour for 20
26.0 units
Mason (for ornamental stone work) 1st class day 1 505.17
17.0 Beldar day 6 350.00
(v) Cost of poining flush or deep ruled in
cement mortar 1:2 (1 Cement : 2 fine sand)
13.35.1 Rate as per item no 13.35.1 of SH : Finishing sqm 16.54 92.3
TOTAL
Add 1 % Water charges on "W-A" 2586.88
TOTAL
Add (multiplying factor 0.1405) on "X-A" 2612.75
TOTAL
Add 15 % Contractor's profit and overheads on 2979.84
"Y-A"
Total
Add Cess @ 1% on "Z-A" 3426.82
Total for 20 units
Cost for 1.38 cum.
Cost for 1 cum.
Say

5.37 Providing and laying in position


ready mixed M-25 grade concrete for
reinforced cement concrete work, using
(Note :- Cement content as
considered in this item is
cement content per approved design
@ 330as
used kg/cum.Excess/less
per design mix is cement
payable/recoverable separately).
5.37.1 All works upto plinth level

Details of cost for 1.00 cum


MATERIAL
295.0 Stone Aggregate (Single size) : 20 mm nominal cum 0.57 800
297.0 size cum 0.28 810
Stone Aggregate (Single size) : 10 mm nominal
2202.0 size
Carriage of Stone aggregate below 40 mm cum 0.85 106.13
982.0 nominal size 800
Coarse sand cum 0.425 1350
2203.0 Carriage of Coarse sand cum 0.425 584.88
367.0 Portland Cement tonne 0.33 4375
2209.0 Carriage of Cement tonne 0.33 94.34
7318.0 Plasticizer / super plasticizer kilogra 1.65 36
0.50% of cement m
Production cost, carriage to site, pumping to
4.0 respective floors and laying in position
Production cost of concrete by batch mix plant. cum 1 350
29.0 Carriage of concrete by transit mixer. km/ 10 30
cum
9.0 Pumping charges of concrete including Hire cum 1 210
charges of pump, piping work & accessories
etc.
Labour for pouring, consolidating & curing
40.0 Mason (average) day 0.17 403.67
17.0 Beldar day 2 350.00
11.0 Bhisti day 0.9 350.00
12.0 Vibrator(Needle type 40mm) day 0.07 370
9999.0 Sundries L.S. 13 2
Total
Add 1 % Water charges on "W"
TOTAL
Add GST (multiplying factor 0.1405) on "X"
TOTAL
Add 15 % Contractor's profit and overheads on "Y"
Total
Add Cess @ 1% on "Z"
Cost per 1.00 cum
Say

5.37.2 All works above plinth level upto floor V


level
Details of cost for 1.00 cum
MATERIAL
295.0 Stone Aggregate (Single size) : 20 mm nominal cum 0.57 800
297.0 size cum 0.28 810
Stone Aggregate (Single size) : 10 mm nominal
2202.0 size
Carriage of Stone aggregate below 40 mm cum 0.85 106.13
982.0 nominal size 800
Coarse sand cum 0.425 1350
2203.0 Carriage of Coarse sand cum 0.425 584.88
367.0 Portland Cement tonne 0.33 4375
2209.0 Carriage of Cement tonne 0.33 94.34
7318.0 Plasticizer / super plasticizer kilogra 1.65 36
0.50% of cement m
Production cost, carriage to site, pumping to
4.0 respective floors and laying in position
Production cost of concrete by batch mix plant. cum 1 350
29.0 Carriage of concrete by transit mixer. km/ 10 30
9.0 cum
Pumping charges of concrete including Hire cum 1 210
charges of pump, piping work & accessories
etc.
Labour for pouring, consolidating & curing
40.0 Mason (average) day 0.17 403.67
17.0 Beldar day 2 350.00
11.0 Bhisti day 0.9 350.00
12.0 Vibrator(Needle type 40mm) day 0.07 370
9999.0 Sundries L.S. 13 2
(Extra labour for lifting material upto floor
V level : = 0.75 x 2.5 = 1.88)
18.0 Coolie day 1.88 350.00
Total
Add 1 % Water charges on "W"
TOTAL
Add GST (multiplying factor 0.1405) on "X"
TOTAL
Add 15 % Contractor's profit and overheads on "Y"

MATERIAL
9.0 Pumping charges of concrete including Hire cum 1 210
charges of pump, piping work & accessories
etc.
Total
Add 1 % Water charges on "W"
TOTAL
Add GST (multiplying factor 0.1405) on "X"
TOTAL
Add 15 % Contractor's profit and overheads on "Y"
Total
Add Cess @ 1% on "Z"
Cost for 1 cum
Say

5.40 Providing and laying in position


ready
5.40.1 mixed
All M-25
worksgrade
up toconcrete for
Plinth level.
reinforced cement concrete work, using fly
ash and cement content as per approved
Details of cost for 1.00 cum

MATERIAL
293.0 Stone Aggregate (Single size) : cum 0.65 760
40 mm nominal size
(0.70 - 7.5% for voids i.e. 0.05 = 0.65 cum)
295.0 Stone Aggregate (Single size) : 20 mm nominal cum 0.24 800
2206.0 size
Carriage of Stone aggregate 40 mm nominal cum 0.65 115.36
2202.0 size and above
Carriage of Stone aggregate below 40 mm cum 0.24 106.13
982.0 nominal size 800
Coarse sand cum 0.37 1350
2203.0 Carriage of Coarse sand cum 0.37 584.88
1980.0 Flyash cum 0.21 10
2262.0 Carriage of Flyash cum 0.21 106.13
367.0 Portland Cement tonne 0.33 4375
2209.0 Carriage of Cement tonne 0.33 94.34
7318.0 Plasticizer / super plasticizer kilogra 1.65 36
Production cost, pumping to respective floors m
and laying in position
4.0 Production cost of concrete by batch mix plant. cum 1 350
29.0 Carriage of concrete by transit mixer. km/ 10 30
9.0 cum 210

Pumping charges of concrete including Hire cum 1 210


charges of pump, piping work & accessories
etc.
LABOUR
for pouring, consolidating & curing
40.0 Mason (average) day 0.17 403.67
17.0 Beldar day 2 350.00
11.0 Bhisti day 0.9 350.00
12.0 Vibrator(Needle type 40mm) day 0.07 370
9999.0 Sundries L.S. 13 2
Total
Add 1 % Water charges on "W"
TOTAL
Add GST (multiplying factor 0.1405) on "X"
TOTAL
Add 15 % Contractor's profit and overheads on "Y"
Total
Add Cess @ 1% on "Z"
Cost per 1.00 cum
Say
5.40.2 All works above plinth & up to
floor
DetailsVoflevel.
cost for 1.00 cum
MATERIAL
293.0 Stone Aggregate (Single size) : cum 0.65 760
40 mm nominal size
0.70 - 7.5% for voids i.e. 0.05 = 0.65 cum)
295.0 Stone Aggregate (Single size) : 20 mm nominal cum 0.24 800
2206.0 size
Carriage of Stone aggregate 40 mm nominal cum 0.65 115.36
2202.0 size and above
Carriage of Stone aggregate below 40 mm cum 0.24 106.13
982.0 nominal size 800
Coarse sand cum 0.37 1350
2203.0 Carriage of Coarse sand cum 0.37 584.88
1980.0 Flyash cum 0.21 10
2262.0 Carriage of Flyash cum 0.21 106.13
367.0 Portland Cement tonne 0.33 4375
2209.0 Carriage of Cement tonne 0.33 94.34
7318.0 Plasticizer / super plasticizer kilogra 1.65 36
Production cost, pumping to respective floors m

and laying in position


4.0 Production cost of concrete by batch mix plant. cum 1 350
29.0 Carriage of concrete by transit mixer. km/ 10 30
9.0 cum 210
Pumping charges of concrete including Hire cum 1 210
charges of pump, piping work & accessories
etc.
LABOUR
for pouring, consolidating & curing
40.0 Mason (average) day 0.17 403.67
17.0 Beldar day 2 350.00
11.0 Bhisti day 0.9 350.00
12.0 Vibrator(Needle type 40mm) day 0.07 370
9999.0 Sundries L.S. 13 2
(Extra labour for lifting material upto floor
V level : = 0.75 x 2.5 = 1.88)
18.0 Coolie Day 1.88 350.00
Total
Add 1 % Water charges on "W"
TOTAL
Add GST (multiplying factor 0.1405) on "X"
TOTAL
Add 15 % Contractor's profit and overheads on "Y"
Total
Add Cess @ 1% on "Z"
Cost per 1.00 cum
Say

5.41 Supplying and applying pre tested


and approved
5.41.1 Non water basedwet
pigmented concrete
curing curing
compound
compound to concrete/ masonry surface,
Detail of cost for 10.00 sqm (covering area 5
all as per manufacturer’s specification and

sqm/litre)
MATERIAL

349.0 Curing compound litre 2 38


9977.0 Carriage of material L.S. 1 2
LABOUR
31.0 Painter day 0.33 403.67
17.0 Beldar day 0.17 350.00
9999.0 Sundries, Brush L.S. 3 2
TOTAL
Add 1 % Water charges on "W"
TOTAL
Add GST (multiplying factor 0.1405) on "X"
TOTAL
Add 15 % Contractor's profit and overheads on "Y"
Total
Add Cess @ 1% on "Z"
Cost of 10 sqm
Cost of 1 sqm
Say

5.42 Providing and fixing parallel


threaded couplers
5.42.1 conforming
Coupler for to IS code
16 mm diameter
on “Reinforcement
reinforcement bar Couplers for Mechanical
Splices of Bars for Concrete Reinforcement
Detail of cost for 1 Nos

MATERIAL
2394.0 Coupler 16 mm dia each 1 30
LABOUR
9999.0 For placing in position and fixing L.S. 3.77 2
9999.0 Tapard/Parallel threading charges L.S. 17.77 2
TOTAL
Add 1 % Water charges on "W"
TOTAL
Add GST (multiplying factor 0.1405) on "X"
TOTAL
Add 15 % Contractor's profit and overheads on "Y"
Total
Add Cess @ 1% on "Z"
Total
Cost of 1 no
Say

5.42.2 Coupler for 20 mm diameter


reinforcement
Detail of cost for 1bar
Nos
MATERIAL
2395.0 Coupler 20 mm dia each 1 39
LABOUR
9999.0 For placing in position and fixing L.S. 5.9 2
9999.0 Tapard/Parallel threading charges L.S. 25.17 2
TOTAL
Add 1 % Water charges on "W"
TOTAL
Add GST (multiplying factor 0.1405) on "X"
TOTAL
Add 15 % Contractor's profit and overheads on "Y"
Total
Add Cess @ 1% on "Z"
Cost of 1 no
Say

5.42.3 Coupler for 25 mm diameter


reinforcement
Detail of cost for 1bar
Nos
MATERIAL

2396.0 Coupler 25 mm dia each 1 69.5


LABOUR
9999.0 For placing in position and fixing L.S. 8.69 2
9999.0 Tapard/Parallel threading charges L.S. 29.61 2
TOTAL
Add 1 % Water charges on "W"
TOTAL
Add GST (multiplying factor 0.1405) on "X"
TOTAL
Add 15 % Contractor's profit and overheads on "Y"
Total
Add Cess @ 1% on "Z"
Total
Cost of 1 no
Say

5.42.4 Coupler for 28 mm diameter


reinforcement
Detail of cost for 1bar
Nos
MATERIAL
2397.0 Coupler 28 mm dia each 1 80
LABOUR
9999.0 For placing in position and fixing L.S. 12.84 2
9999.0 Tapard/Parallel threading charges L.S. 32.57 2
TOTAL
Add 1 % Water charges on "W"
TOTAL
Add GST (multiplying factor 0.1405) on "X"
TOTAL
Add 15 % Contractor's profit and overheads on "Y"
Total
Add Cess @ 1% on "Z"
Total
Cost of 1 no
Say

5.42.5 Coupler for 32 mm diameter


reinforcement
Detail of cost for 1bar
Nos
MATERIAL

2398.0 Coupler 32 mm dia each 1 110


LABOUR
9999.0 For placing in position and fixing L.S. 15.48 2
9999.0 Tapard/Parallel threading charges L.S. 32.57 2
TOTAL
Add 1 % Water charges on "W"
TOTAL
Add GST (multiplying factor 0.1405) on "X"
TOTAL
Add 15 % Contractor's profit and overheads on "Y"
Total
Add Cess @ 1% on "Z"
Total
Cost of 1 no
Say

5.43 Providing and fixing in position


Stainless
5.43.1 steel
200 mmGrade 304 plate-1.0 mm
wide.
thick as per design for expansion joints.
Detail of cost for 1 metre
MATERIAL
2393.0 1 mm thick Stainless Steel Cover plate grade kg 1.6 275
304
8647.0 Stainless steal screws 30mm x4mm. 100 0.06 32
9977.0 nos
Carriage of material L.S. 1.3 2
LABOUR
13.0 Blacksmith 2nd class day 0.067 403.67
17.0 Beldar day 0.067 350.00
9999.0 Sundries L.S. 2.34 2
TOTAL
Add 1 % Water charges on "W"
TOTAL
Add GST (multiplying factor 0.1405) on "X"
TOTAL
Add 15 % Contractor's profit and overheads on "Y"
Total
Add Cess @ 1% on "Z"
Total
Cost of 1 metre
Say

5.43.2 300 mm wide.


Detail of cost for 1 metre
MATERIAL
2393.0 1 mm thick Stainless Steel Cover plate grade kg 2.4 275
304
8647.0 Stainless steal screws 30mm x4mm. 100 0.06 32
9977.0 nos
Carriage of material L.S. 1.3 2
LABOUR
13.0 Blacksmith 2nd class day 0.067 403.67
17.0 Beldar day 0.067 350.00
9999.0 Sundries L.S. 2.34 2
TOTAL
Add 1 % Water charges on "W"
TOTAL
Add GST (multiplying factor 0.1405) on "X"
TOTAL
Add 15 % Contractor's profit and overheads on "Y"
Total
Add Cess @ 1% on "Z"
Total
Cost of 1 metre
Say

5.44 Providing and fixing of expansion


joint system related
arrangement with floor
and support plateslocation
etc. asas
per
per drawings
ASTM and
B221-02. Thedirection
system of Engineer-In-
shall be such
Charge. The joints
that it provides system
floor will
to floor be of
/floor to wall
expansion control system for various

5.44.1 Floor Joint of 100 mm gap

Details of Cost of 1 metre.


MATERIALS :
2403.0 Floor Joint of 100 mm Metre 1 3100
2402.0 Epoxy adhesive KG 4.25 150
9977.0 Carriage L.S. 124.9 2
LABOUR :
12.0 Blacksmith 1st class day 0.05 505.17
23.0 Mason (brick layer) 1st class day 0.1 505.17
17.0 Beldar day 0.15 350.00
TOTAL
Add 1 % Water charges on "W"
TOTAL
Add GST (multiplying factor 0.1405) on "X"
TOTAL
Add 15 % Contractor's profit and overheads on "Y"
Total
Add Cess @ 1% on "Z"
Cost of 1 metre.
Say

5.44.2 Floor Joint of 150 mm gap


Details of Cost of 1 metre.
MATERIALS :
2404.0 Floor Joint of 150 mm Mette 1 4000
2402.0 Epoxy adhesive KG 4.5 150
9977.0 Carriage L.S. 124.9 2
LABOUR :
12.0 Blacksmith 1st class day 0.05 505.17
23.0 Mason (brick layer) 1st class day 0.1 505.17
17.0 Beldar day 0.15 350.00
TOTAL
Add 1 % Water charges on "W"
TOTAL
Add GST (multiplying factor 0.1405) on "X"
TOTAL
Add 15 % Contractor's profit and overheads on "Y"
Total
Add Cess @ 1% on "Z"
Cost of 1 metre.
Say

5.44.3 Floor Joint of 200 mm gap


Details of Cost of 1 metre.
MATERIALS :
2405.0 Floor Joint of 200 mm metre 1 5400
2402.0 Epoxy adhesive kg 4.75 150
9977.0 Carriage L.S. 124.9 2
LABOUR :
12.0 Blacksmith 1st class day 0.05 505.17
23.0 Mason (brick layer) 1st class day 0.1 505.17
17.0 Beldar day 0.15 350.00
TOTAL
Add 1 % Water charges on "W"
TOTAL
Add GST (multiplying factor 0.1405) on "X"
TOTAL
Add 15 % Contractor's profit and overheads on "Y"
Total
Add Cess @ 1% on "Z"
Cost of 1 metre.
Say

5.45 Providing and fixing of expansion


joint
5.45.1system related
Wall Joint with wall
of 100 mmjoint
gap(internal/
external) location as per drawings and
direction of Engineer-In-Charge. The joints
Details of Cost of 1 metre.
MATERIALS :
2409.0 Wall Joint of 100 mm metre 1 2400
2402.0 Epoxy adhesive kg 4.25 150
9977.0 Carriage L.S. 124.9 2
LABOUR :
12.0 Blacksmith 1st class day 0.05 505.17
23.0 Mason (brick layer) 1st class day 0.1 505.17
17.0 Beldar day 0.15 350.00
TOTAL
Add 1 % Water charges on "W"
TOTAL
Add GST (multiplying factor 0.1405) on "X"
TOTAL
Add 15 % Contractor's profit and overheads on "Y"
Total
Add Cess @ 1% on "Z"
Cost of 1 metre.
Say

5.45.2 Wall Joint of 150 mm gap


Details of Cost of 1 metre.
MATERIALS :
2410.0 Wall Joint of 150 mm metre 1 2800
2402.0 Epoxy adhesive kg 4.5 150
9977.0 Carriage L.S. 124.9 2
LABOUR :
12.0 Blacksmith 1st class day 0.05 505.17
23.0 Mason (brick layer) 1st class day 0.1 505.17
17.0 Beldar day 0.15 350.00
TOTAL
Add 1 % Water charges on "W"
TOTAL
Add GST (multiplying factor 0.1405) on "X"
TOTAL
Add 15 % Contractor's profit and overheads on "Y"
Total
Add Cess @ 1% on "Z"
Cost of 1 metre.
Say

5.45.3 Wall Joint of 200 mm gap


Details of Cost of 1 metre.
MATERIALS :
2411.0 Wall Joint of 200 mm metre 1 3400
2402.0 Epoxy adhesive kg 4.75 150
9977.0 Carriage L.S. 124.9 2
LABOUR :
12.0 Blacksmith 1st class day 0.05 505.17
23.0 Mason (brick layer) 1st class day 0.1 505.17
17.0 Beldar day 0.15 350.00
TOTAL
Add 1 % Water charges on "W"
TOTAL
Add GST (multiplying factor 0.1405) on "X"
TOTAL
Add 15 % Contractor's profit and overheads on "Y"
Total
Add Cess @ 1% on "Z"
Cost of 1 metre.
Say

5.46 Providing and fixing of expansion


joint
5.46.1system of Joint
Roof approved make
of 100 mm and
gap
manufactures for various roof locations as
per approved drawings and direction of
Details of Cost of 1 metre.
MATERIALS :
2399.0 Complete Roof Joint of 100 mm metre 1 2800
2402.0 Epoxy adhesive kg 4.25 150
9977.0 Carriage L.S. 124.9 2
LABOUR :
12.0 Blacksmith 1st class day 0.05 505.17
23.0 Mason (brick layer) 1st class day 0.1 505.17
17.0 Beldar day 0.15 350.00
TOTAL
Add 1 % Water charges on "W"
TOTAL
Add GST (multiplying factor 0.1405) on "X"
TOTAL
Add 15 % Contractor's profit and overheads on "Y"
Total
Add Cess @ 1% on "Z"
Cost of 1 metre.
Say

5.46.2 Roof Joint of 150 mm gap


Details of Cost of 1 metre.
MATERIALS :
2400.0 Complete Roof Joint of 150 mm metre 1 3200
2402.0 Epoxy adhesive kg 4.5 150
9977.0 Carriage L.S. 124.9 2
LABOUR :
12.0 Blacksmith 1st class day 0.05 505.17
23.0 Mason (brick layer) 1st class day 0.1 505.17
17.0 Beldar day 0.15 350.00
TOTAL
Add 1 % Water charges on "W"
TOTAL
Add GST (multiplying factor 0.1405) on "X"
TOTAL
Add 15 % Contractor's profit and overheads on "Y"
Total
Add Cess @ 1% on "Z"
Cost of 1 metre.
Say

5.46.3 Roof Joint of 200 mm gap


Details of Cost of 1 metre.
MATERIALS :
2401.0 Complete Roof Joint of 200 mm metre 1 4000
2402.0 Epoxy adhesive kg 4.75 150
9977.0 Carriage L.S. 124.9 2
LABOUR :
12.0 Blacksmith 1st class day 0.05 505.17
23.0 Mason (brick layer) 1st class day 0.1 505.17
17.0 Beldar day 0.15 350.00
TOTAL
Add 1 % Water charges on "W"
TOTAL
Add GST (multiplying factor 0.1405) on "X"
TOTAL
Add 15 % Contractor's profit and overheads on "Y"
Total
Add Cess @ 1% on "Z"
Cost of 1 metre.
Say

5.47 Providing and fixing in position


factory
5.47.1 made
Doorprecast RCCmmx
frame 125 M-4060fixing
mm with
hold fast embedded in 1:3:6 concrete block
for doors and windows frames having
Details of cost for 5.20 metre.
MATERIAL
5.33.1 Rate as per Item No.5.33.1 of SH: cum 0.039 6934.9
REINFORCED
CEMENT CONCRETE
5.34.3 Rate as per Item No.5.34.3 of cum 0.039 209.3
SH:REINFORCED CEMENT CONCRETE
Extra for scatter and smaller work @25 % (P +
1005.0 Q ) x 0.25
Twisted steel/ deformed bars quintal 0.0468 5500
596.0 Bright finished or black enameled mild steel 10 Nos 0.6 56
butt hinges 75x47x1.70 mm
4.3.3 Rate as per Item No.4.3.3 of SH: CONCRETE sqm 1.27 514.75
WORK
14.2.1 Rate as per Item No.14.2.1 of SH: REPAIRS each 1 883.05
13.48.2 TO BUILDINGS
Rate as per Item No.13.48.2 of SH. FINISHING sqm 1.27 94.3
9999.0 Sundries L.S. 100.67 2
TOTAL
Add 1 % Water charges on "W-P,Q,R & A" 450.22
TOTAL
Add GST (multiplying factor 0.1405) on "X- 454.72
P,Q,R & A"
TOTAL
Add 15 % Contractor's profit and overheads on 518.61
"Y-PQ& A"
Total
Add Cess @ 1% on "Z-PQ& A" 596.4
Cost of 5.20 metre
Cost of 1 metre
Say

5.47.2 Door frame 100 mmx 60 mm

Details of cost for 5.20 metre.


MATERIAL
5.33.1 Rate as per Item No.5.33.1 of SH: cum 0.031 6934.9
REINFORCED
CEMENT CONCRETE
5.34.3 Rate as per Item No.5.34.3 of SH: cum 0.031 209.3
REINFORCED
CEMENT CONCRETE
Extra for scatter and smaller work @25 % (P +
1005.0 Q ) x 0.25
Twisted steel/ deformed bars quintal 0.0372 5500
596.0 Bright finished or black enameled mild steel 10 Nos 0.6 56
butt hinges 75x47x1.70 mm
4.3.3 Rate as per Item No.4.3.3 of SH: CONCRETE sqm 1.14 514.75
WORK
14.2.1 Rate as per Item No.14.2.1 of SH: REPAIRS each 1 883.05
13.48.2 TO BUILDINGS
Rate as per Item No.13.48.2 of SH. FINISHING sqm 1.14 94.3
9999.0 Sundries L.S. 100.67 2
TOTAL
Add 1 % Water charges on "W-P,Q,R &A" 406.06
TOTAL
Add GST (multiplying factor 0.1405) on "X- 410.12
P,Q,R &A"
TOTAL
Add 15 % Contractor's profit and overheads on 467.74
"Y-PQ&A"
Total
Add Cess @ 1% on "Z-PQ&A" 537.9
Cost of 5.20 metre
Cost of 1 metre
Say

5.47.3 Door frame 85 mmx60 mm


Details of cost for 5.20 metre.
MATERIAL
5.33.1 Rate as per Item No.5.33.1 of SH: REIN- cum 0.027 6934.9
FORCED CEMENT CONCRETE
5.34.2 Rate as per Item No.5.34.2 of SH: cum 0.027 139.55
REINFORCED
CEMENT CONCRETE
Extra for scatter and smaller work @25 % (P +
1005.0 Q ) x 0.25
Twisted steel/ deformed bars quintal 0.0324 5500
596.0 Bright finished or black enameled mild steel 10 Nos 0.6 56
butt hinges 75x47x1.70 mm
4.3.3 Rate as per Item No.4.3.3 of SH: CONCRETE sqm 1.07 514.75
WORK
14.2.1 Rate as per Item No.14.2.1 of SH: REPAIRS each 1 883.05
TO BUILDINGS
13.48.2 Rate as per Item No.13.48.2 of SH. FINISHING sqm 1.07 94.3
9999.0 Sundries L.S. 100.67 2
TOTAL
Add 1 % Water charges on "W-P,Q,R &A" 383.98
TOTAL
Add GST (multiplying factor 0.1405) on "X- 387.82
P,Q,R &A"
TOTAL
Add 15 % Contractor's profit and overheads on 442.31
Total
Add Cess @ 1% on "Z-PQ&A" 508.65
Cost of 5.20 metre
Cost of 1 metre
Say

5.48 Providing and laying Reinforced


cement concrete for construction of piers,
abutments, portal frames, pier caps and
5.48.1 Reinforced
bearing pedestals andCement
seismicConcrete
arresters-M-
50
Detail of cost for 120 cum.
MATERIAL
5.48X Sub Analysis no 5.48X (Annexure) for item each 1 586543.4
5.48.1
Providing M 50 grade reinforced Cement
Concrete data (lot) for 120.00 cum
Add 11 per cent of cost of material, labour
and machinery for form work P x 11 /100 =
608808.70 x 11 /100
Add 1.4 per cent of cost of material, Labour
and machinery excluding formwork to cater for
extra lift
P x 1.4 /100 = 608808.70 x 1.4 /100
TOTAL
Add 1 % Water charges on "W"
TOTAL
Add GST (multiplying factor 0.1405) on "X"
TOTAL
Add 15 % Contractor's profit and overheads on "Y"
Total
Add Cess @ 1% on "Z"
Cost of 120 cum
Rate of 1 cum
Say

5.48.2 Reinforced Cement Concrete -M-


60
Detail of cost for 120 cum.
MATERIAL
5.48Y Sub Analysis no 5.48Y (Annexure) for item each 1 686801.6
5.48.2
Providing M 60 grade reinforced Cement

Concrete data (lot) for 120.00 cum


Add 11 per cent of cost of material, labour
and machinery for formwork
P x 11 /100 = 709546.30 x 11 /100
Add 1.4 per cent of cost of material, Labour
and machinery excluding formwork to cater for
extra lift
P x 1.4 /100 = 709546.30 x 1.4 /100
TOTAL
Add 1 % Water charges on "W"
TOTAL
Add GST (multiplying factor 0.1405) on "X"
TOTAL
Add 15 % Contractor's profit and overheads on "Y"
Total
Add Cess @ 1% on "Z"
Cost of 120 cum
Rate of 1 cum
Say

5.48.3 Extra for using M -50/ M60 Grade


Self-compacting
Detail Cement Concrete
of cost for 1 cum.
MATERIAL
5.5 Sub Analysis no 5.48 (Annexure) for sub each 1 9363.55
5.48.2 analysis 5.48.3X
Rate as per Item No.5.48.2 of cum -1 8607
SH: REINFORCED CEMENT CONCRETE
TOTAL
Rate of 1 cum
Say

5.48.3X M 60 grade Self-compacting Reinforced


Cement
Detail Concrete
of cost for 120 cum.
MATERIAL
5.48Z Sub Analysis no 5.48Z (Annexure) for sub each 1 747170.85
analysis 5.48.3X
Providing M 60 grade reinforced Cement
Concrete data (lot) for 120.00 cum
Add 11 per cent of cost of material, labour
and machinery for formwork P x 11 /100 =
769342.10 x 11 /100
Add 1.4 per cent of cost of material, Labour

and machinery excluding formwork to cater for

extra lift
P x 1.4 /100 = 769342.10 x 1.4 /100

257.0

258.0

29.0
9.0 210

66.0
70.0
52.0
28.0
23.0
17.0

Annexure for item 5.48.1, Providing M50


grade
Code Reinforced Cement Concrete data for
120.00
5.48X
cum
TOTAL
Add 1 % Water charges on "W"
TOTAL
Add GST (multiplying factor 0.1405) on "X"
TOTAL
Add 15 % Contractor's profit and overheads on "Y"
Total
Add Cess @ 1% on "Z"
Cost of 120 cum
Rate of 1 cum
Say

Sub Analysis for use in Item no 5.48.1 Details


of cost for each lot of 120 cum.
RCC Grade M50
Unit = 1 cum
Taking output = 120 cum MATERIALS :
367.0 Portland Cement tonne 57.6 4375
982.0 Coarse sand cum 54 800
295.0 Stone Aggregate (Single size) : 20 mm nominal cum 64.8 800
297.0 size cum 43.2 810
Stone Aggregate (Single size) : 10 mm nominal
7318.0 size
Plasticizer / super plasticizer kilogra 223.2 36
LABOUR : m
Mate day 0.94 350.00
Mason (brick layer) 1 st class day 3.5 505.17
Beldar day 20 350.00
MACHINERY :
Batching and Mixing Plant @ 75 cum per hour hour 1.6 2400
Generator 100 KVA/125 KVA hour 1.6 250
Front end loader 1 cum bucket capacity hour 1.6 900
(incl POL)
Distance = 10 km
Qty= 120.00 cum
Total = 120.00x 10= 1200
Carriage of concrete by transit mixer km/cu 1200 30
m
Pumping charges of concrete including Hire cum 120 210
charges of pump, piping work & accessories
etc.
TOTAL
Cost of each lot of 120 cum.
Say

Code 5.48Y

Annexure for items 5.48.2 for using M 60


grade Self Compacting Reinforced cement
concrete data for 120.00 cum
Sub Analysis for use in Item no 5.48.2

Detail of cost for each


RCC Grade M60
Unit = 1 cum
Taking output = 120 cum MATERIALS :
367.0 Portland Cement tonne 57.6 4375
982.0 Coarse sand cum 54.98 800
295.0 Stone Aggregate (Single size) : 20 mm nominal cum 57.54 800
297.0 size cum 38.22 810
Stone Aggregate (Single size) : 10 mm nominal
7318.0 size
Plasticizer / super plasticizer kilo 230.4 36
8953.0 gram
Micro Silica kg 3600 32
LABOUR :
28.0 Mate day 0.94 350.00
23.0 Mason (brick layer) 1 st class day 3.5 505.17
17.0 Beldar day 20 350.00
MACHINERY :
66.0 Batching and Mixing Plant @ 75 cum per hou hour 1.6 2400
70.0 Generator 100 KVA/125 KVA hour 1.6 250
52.0 Front end loader 1 cum bucket capacity hour 1.6 900
(incl POL)
Distance = 10 km
Qty= 120.00 cum
Total = 120.00x 10= 1200
29.0 Carriage of concrete by transit mixer km/ 1200 30
9.0 cum
Pumping charges of concrete including Hire cum 120 210
charges of pump, piping work & accessories
etc.
TOTAL
Cost of each.
Say
5.48Z Annexure for items 5.48.3. Extra for using
M 60 grade Self Compacting
Reinforced cement concrete data for 120.00
cum
Sub Analysis for use in Item no 5.48.3X Details

of cost for each.


RCC Grade M60 self compacting concrete Using
Batching Plant, Transit Mixer and Conrete Pump
Unit ; cum

Taking Output = 120 cum MATERIALS :

367.0 Portland Cement tonne 57.6 4375


982.0 Coarse sand cum 54 800
295.0 Stone Aggregate (Single size) : 20 mm nominal cum 64.8 800
297.0 size cum 43.2 810
Stone Aggregate (Single size) : 10 mm nominal
7318.0 size
Plasticizer / super plasticizer kilogra 230.4 36
8953.0 m
Micro Silica kg 5040 32
LABOUR :
28.0 Mate day 0.84 350.00
23.0 Mason (brick layer) 1 st class day 3 505.17
17.0 Beldar day 18 350.00
MACHINERY :
66.0 Batching and Mixing Plant @ 75 cum per hour hour 1.6 2400
70.0 Generator 100 KVA/125 KVA hour 1.6 250
52.0 Front end loader 1 cum bucket capacity hour 1.6 900
(incl POL)
Distance = 10 km
Qty= 120.00 cum
Total = 120.00x 10= 1200
29.0 Carriage of concrete by transit mixer km/cu 1200 30
9.0 m
Pumping charges of concrete including Hire cum 120 210
charges of pump, piping work & accessories
etc.
TOTAL
Cost of each.
Say

5.49 Constructing cast-in situ RCC diaphragm


wall by providing and laying machine batched,
Details of cost for 144.0 cum. Analysis for
machine mixed, self compacting, ready mix
reinforced
20x12=240 cement concrete,
Sqmt area of tramie controlled, of M
diaphragm wall Average depth 12 m
Thickness 0.60 m
Total Quantity 20 mx12 m x0.6 m = 144.00
77.0 Excavation of Diaphragm wall by sqm 240 1300
Mechanical Grab
Guide wall RCC 1:2:4
RCC 2x20x(0.45+1.5)x.15 = 11.70 cum
5.1.3 Rate as per Item No.5.1.3 of cum 11.7 6234.1
SH: REINFORCED CEMENT CONCRETE
Reinforcement@ 70 kg/Cum for guide wall=
11.70x 70 kg/cum= 819 kg
5.22.6 Rate as per Item No.5.22.6 of kilogra 819 76.85
SH: REINFORCED CEMENT CONCRETE m

Add for chipping/dismantling top 50 cm contaminated


concrete =20 x 0.50 x

0.60= 6.00 cum

RMC M-30 as per qty=144.00 cum

Add 10% extra for bulges etc. i.e. 14.40 cum


Total=144.00+6.00+14.40= 164.40 cum
5.33.1 Rate as per Item No.5.33.1 of cum 164.4 6934.9
SH: REINFORCED CEMENT CONCRETE
5.34.1 Rate as per Item No.5.34.1 of cum 164.4 69.75
SH: REINFORCED CEMENT CONCRETE
Bentonite @6% of RCC qty
Total Qty= 164.4x06x1400/100= 13810 kg=
7183.0 13.81 tonne
Bentonite tonne 13.81 2960
Add 10 %extra cement due to concreting under
water
164.4x420x0.10=6.90 tonne
367.0 Portland Cement tonne 6.9 4375
Add cement for grouting of wall using nozzles
etc.- 240 sqm @ 0.10 quintal/sqm
=2.40 tonne
367 Portland Cement tonne 2.4 4940
2209.0 Carriage of Cement tonne 2.4 94.34
25.0 Hire and running charges of light crane day 1 3000
Reinforcement @220 kg/cum
164.4x220kg/cum=36168 kg
Extra reinforcement for hooks @
5% of cage 1808.4 kg
Total=1808.4 kg=18.084 qtl
1005.0 Twisted steel/ deformed bars quintal 18.08 5500
Extra for welding reinforcement cage
Reinforcement @ 200 C/C 2 x 101 x 61 = 6161
joints Welding for alternate joint say 50 %
joints 6161 cm
10.2 Rate as per Item No.10.22 of SH: STEEL cm 6161 3.35
9999.0 WORK
Labour for grouting diaphragm wall under L.S. 23530 2
pressure i/c fixing nozzle etc
Add for use retarders / plasticizers for the
diaphragm wall concreting using trimme @
0.4 % cement qty = (164.4 x 420 x 0.4)/
7318.0 100=276.1
Plasticizer / super plasticizer kilo 276.19 36
8954.0 gram
Stop end tubes for diaphragmwall 600 mm dia. sqm 240 4.5
8955.0 Driving end tubes for diaphragm wall 600 mm sqm 240 72
26.0 dia.
Hire and running charges of bentonite pump day 2 3500

Bentonite powder @ 6% of R.C.C. Qty = (164.4 Cum x


0.06)=9.864 cum 9.864 cum x 1400 kg/cum = 13809.6
kg Disposal of bentonite muck
Slurry / Muck vol. 49.32 cum Disposal of bentonite muck

Slurry / Muck vol. 49.32 cum


Add excavated earth = 144.00 cum
Total= 144.00 + 49.32 = 193.32 cum
15.6 Rate as per Item No.15.60 of SH: DISM cum 193.32 142
ANTLING & DEMOLISHING
Disposal of Chipping / Dismantling of
contaminated concrete and guide wall etc. with
all leads as per item no. 15.3 = 2x(20x
0.50x0.60) + 15.00 cum = 20.40 cum
15.3 Rate as per Item No.15.3 of SH: DISM cum 20.4 1465.35
ANTLING & DEMOLISHING
9999.0 Sundries (Extra for concreting by Trimme) L.S. 1177 2
9999.0 Sundries ( Design Charges) L.S. 19200 2
TOTAL
Add 1 % Water charges on "W-A" 608349
TOTAL
Add GST (multiplying factor 0.1405) on "X-A" 614433
TOTAL
Add 15 % Contractor's profit and overheads on 700761
"Y-A"
Total
Add Cess @ 1% on "Z-A" 805875
Cost of 144.0 cum
Rate of 1 cum
Say

MATERIAL
Labour for pouring, consolidating & curing

Add 15 % Contractor's profit and overheads on "Y"

17.0 Beldar day 24 350.00

23.0 Mason (brick layer) 1st class day 0.12 505.17

SH : Finishing
Add Cess @ 1% on "Z"

"Y-PQ&A"
Add Cess @ 1% on "Z"
Cost of one quintal
Cost of 1 Kg.
Say

5.22.4 Hot rolled deformed bars

Details of cost for 1 quintal-


MATERIAL
Deformed twisted steel bars = 1.00 q
Total
Add Cess @ 1% on "Z"
Cost per 1.00 cum
Say

5.38 Extra for R.C.C./ B.M.C/ R.M.C.


work above floor V level for each four floors
or part thereof.

Details of cost for 1 cum

263.0
Amount

456.00

226.80

497.15

340.00
248.57
1750.00
37.74

40.37
570.50
245.00
56.00

25.90
28.60
4522.63 W
45.2263
4567.86 X
641.78
5209.64 Y
781.45
5991.09 Z
59.91
6051.00
6051.00 6376.3

536.00
178.20
520.54

356.00
260.27
1580.80
30.19

40.37
570.50
245.00
56.00

25.90
28.60
4428.37 W
44.2837
4472.65 X
628.41
5101.06 Y
765.16
5866.22 Z
58.66
5924.88
5924.90 5954.35

395.20

176.00
89.10
59.99
193.01

356.00
260.27

1400.00
30.19

40.37
570.50
245.00
56.00

25.90
27.04
3924.57 W
39.2457
3963.82 X
556.92
4520.74 Y
678.11
5198.85 Z
51.99
5250.84
5250.80 5846

560.00
194.40
549.79

376.00
274.89
1086.80
20.75

40.37
570.50
245.00
56.00

25.90
27.04
4027.44 W
40.2744
4067.71 X
571.51
4639.22 Y
695.88
5335.10 Z
53.35
5388.45
5388.50 5424.85

494.00

192.00
74.98

140.37

376.00
274.89
962.50
20.75

40.37
570.50
245.00
56.00

25.90
27.04
3500.30 W
35.003
3535.30 X
496.71
4032.01 Y
604.80
4636.81 Z
46.37
4683.18
4683.20
5291.95

494.00

192.00
74.98

140.37

376.00
274.89
839.80
16.04

40.37
570.50
245.00
56.00

25.90
27.04
3372.89 W
33.7289
3406.62 X
478.63
3885.25 Y
582.79
4468.04 Z
44.68
4512.72
4512.70
494.00

324.00
74.98

140.37

376.00
274.89
568.75
12.26

40.37
570.50
245.00
56.00

25.90
27.04
3230.06 W
32.3006
3262.36 X
458.36
3720.72 Y
558.11
4278.83 Z
42.79
4321.62
4321.60
494.00

192.00
74.98

140.37

399.50
49.88

642.20
12.26

40.37
570.50
245.00
56.00

25.90
17.94
2960.90 W
29.609
2990.51 X
420.17
3410.68 Y
511.60
3922.28 Z
39.22
3961.50
3961.50

494.00

192.00
74.98
140.37

296.00
216.41
2.10
22.29
743.75
16.04

40.37
570.50
245.00
56.00

25.90
28.60
3164.31 W
31.6431
3195.95 X
449.03
3644.98 Y
546.75
4191.73 Z
41.92
4233.65
4233.70

494.00

192.00
74.98

140.37

272.00
198.86
2.10
22.29
568.75
12.26

40.37
570.50
245.00
56.00

25.90
28.60
2943.98 W
29.4398
2973.42 X
417.77
3391.19 Y
508.68
3899.87 Z
39.00
3938.87
3938.90 4467.2

456.00
226.80
497.15

340.00
248.57
1750.00
37.74

315.00
273.00
245.00
30.31
24.22
56.00

25.90
228.80
28.60
658.00

5441.09 W
54.4109
5495.50 X
772.12
6267.62 Y
940.14
7207.76 Z
72.08
7279.84
7279.80

542.70
178.20
520.54

356.00
260.27
1400.00
30.19

315.00
273.00
245.00
30.31
24.22
56.00

25.90
228.80
28.60
658.00
5172.73 W
51.7273
5224.46 X
734.04
5958.50 Y
893.77
6852.27 Z
68.52
6920.79
6920.80

560.00
194.40
549.79

376.00
274.89
962.50
20.75

315.00
273.00
245.00
30.31
24.22
56.00

25.90
228.80
27.04
658.00

4821.60 W
48.216
4869.82 X
684.21
5554.03 Y
833.10
6387.13 Z
63.87
6451.00
6451.00

494.00
192.00
74.98

140.37

376.00
274.89
568.75
12.26

315.00
273.00
245.00
50.52
56.00

25.90
228.80
28.60
658.00

3520.07 W
35.2007
3555.27 X
499.52
4054.79 Y
608.22
4663.01 Z
46.63
4709.64
4709.60

292.40

20.40

154.70

25.84

10.03

49.45

44.20
156.00

378.88
525.00
104.00
52.00
1812.90 W
18.129
1831.03 X
257.26
2088.29 Y
313.24
2401.53 Z
24.02
2425.55
224.60
216.45

438.60

154.70

38.76

15.05

146.20

55.24
156.00

1768.10
2100.00
156.00
104.00
5132.65 W
51.3265
5183.98 X
728.35
5912.33 Y
886.85
6799.18 Z
67.99
6867.17
434.60
411.15

146.20

21.68

102.29

53.98

55.24
104.00
505.17
700.00
78.00
52.00
1818.56 W
18.1856
1836.75 X
258.06
2094.81 Y
314.22
2409.03 Z
24.09
2433.12
540.70
514.75

36306.00

36306.00
6051
6051

2722.95 A

178.50
18.50 A

70.46 A

15.70 A
72.60
3078.71 W
2.511
X

35.63
Y
43.39

Z
3.33
3163.57
7030.16
7030.20 7306.3
3630.60 A

11.23

70.46 A

18.84 A
61.08
3792.21 W
0.6108
X

8.67
Y
10.55

Z
0.81
3812.85
6354.75
6354.80 6677.8

3630.60 A

11.23

70.46 A
15.70 A

227.94

238.00

303.10
1260.00
5757.03 W
20.2904 X

287.93 Y

350.59 Z

26.88
6442.72
10737.87
10737.90 10743.5

139.17 A

53.82
10.35

19.60

25.26
105.00
353.20 W
2.1403
X

30.37
Y
36.98

2.84
425.53
8510.61
8510.60 8342.05

43.64 A

51.95 A

324.21 A
5.14 A

162.75 A

35.59 A
26.00
649.28 W
0.26
X

3.69
Y
4.49

Z
0.34
658.06
658.06
658.10 619.25

2369.96 A

-536.00
542.70

202.07
161.47
3.90
2744.10 W
3.7414
X

53.09
Y
64.65
Z
4.96
2870.54
287.05
287.10 284.2

2977.18 A

202.07
161.47
27.04
3367.76 W
3.9058
X

55.43
Y
67.49
Z
5.17
3499.76
349.98
350.00 346.85

35.00

7.28
W

42.28
0.4228
42.70 X
6.00
48.70 Y
7.31
56.01 Z
0.56
56.57
56.57
56.60 56.55

816.00
61.50

15.40
1.80

42.00

24.50

80.73

66.30

1108.23 W
11.0823
1119.31 X
157.26
1276.57 Y
191.49
1468.06 Z
14.68
1482.74
148.27
148.30 95.85

525.00
525.00 W
5.25
530.25 X
74.50
604.75 Y
90.71
695.46 Z
6.95
702.41
702.41
702.40 643.9

262.50

1400.00
1662.50 W
16.625
1679.13 X
235.92
1915.05 Y
287.26
2202.31 Z
22.02
2224.33
529.6
529.60 492.45

10.10
8.07
87.50
52.50
158.17 W
1.5817
159.75 X
22.45
182.20 Y
27.33
209.53 Z
2.10
211.63
211.63
211.60 194.45

487.50
86.52
51.00
6.37

56.00
38.50

280.00
97.20
274.89

184.00
134.52
481.25
10.38

350.00
25.26
115.50
26.78
13.52

108.99
378.00
378.00
3584.18 W
35.8418
3620.02 X
508.61
4128.63 Y
619.29
4747.92 Z
47.48
4795.40
479.54
479.50 478.85

45.63

45.63
0.4563
46.09 X
6.48
52.57 Y
7.88
60.45 Z
0.60
61.05
61.05
61.10 61.05

494.00
192.00
74.98

140.37

296.00
216.41
2.10
22.29
1050.00
22.64
43.20

350.00
300.00

210.00

68.62
700.00
315.00
25.90
26.00
4549.51 W
45.4951
4595.01 X
645.60
5240.61 Y
786.09
6026.70 Z
60.27
6086.97
6086.97
6087.00 6676.35
494.00

192.00
74.98

140.37

296.00
216.41
2.10
22.29
962.50
20.75
39.60

350.00
300.00

210.00

68.62
700.00
315.00
25.90
26.00
4456.52 W
44.5652
4501.09 X
632.40
5133.49 Y
770.02
5903.51 Z
59.04
5962.55
5962.55
5962.60 6536.8
494.00

192.00
74.98

140.37

296.00
216.41
2.10
22.29
1050.00
22.64
43.20

350.00
300.00

68.62
700.00
315.00
25.90
26.00

658.00
4997.51 W
49.9751
5047.49 X
709.17
5756.66 Y
863.50
6620.16 Z
66.20
6686.36
6686.36
6686.40 7202.35
494.00

192.00
74.98

140.37

296.00
216.41
2.10
22.29
962.50
20.75
39.60

350.00
300.00
0

68.62
700.00
315.00
25.90
26.00

658.00
4904.52 W
49.0452
4953.57 X
695.98
5649.55 Y
847.43
6496.98 Z
64.97
6561.95
6561.95
6562.00 7062.85
494.00

192.00
74.98

140.37

376.00
274.89
1050.00
22.64
43.20

350.00
300.00

210.00

68.62
700.00
315.00
25.90
26.00
4663.60 W
46.636
4710.24 X
661.79
5372.03 Y
805.80
6177.83 Z
61.78
6239.61
6239.61 6838.55
6239.60
494.00

192.00
74.98

140.37

376.00
274.89
962.50
20.75
39.60

350.00
300.00

210.00

68.62
700.00
315.00
25.90
26.00
4570.61
45.7061
4616.32 X
648.59
5264.91 Y
789.74
6054.65 Z
60.55
6115.20
6115.2
6115.20 6699
494.00

192.00
74.98

140.37

376.00
274.89
1050.00
22.64
43.20
0

350.00
300.00

68.62
700.00
315.00
25.90
26.00

658.00
5111.60 W
51.116
5162.72 X
725.36
5888.08 Y
883.21
6771.29 Z
67.71
6839.00
6839
6839.00 7364.55
494.00

192.00
74.98

140.37

376.00
274.89
962.50
20.75
39.60

350.00
300.00

68.62
700.00
315.00
25.90
26.00

658.00
5018.61
50.1861
5068.80 X
712.17
5780.97 Y
867.14
6648.11 Z
66.48
6714.59
6714.59
6714.60 7225.05
Amount

456.00
226.80
0.00
0.00
497.15
0.00
573.75
248.57
1750.00
37.74

68.62
700.00
315.00
56.00
0.00
25.9
28.60
4984.13 W
49.8413
5033.97 X
707.27
5741.24 Y
861.19
6602.43 Z
66.02
6668.45
6668.45
6668.50 6656.05
536.00
178.20

0.00
520.54
0.00
600.75
260.27
1400.00
30.19

68.62
700.00
315.00
56.00
0.00
25.90
28.60
4720.07 W
47.2007
4767.27 X
669.80
5437.07 Y
815.56
6252.63 Z
62.53
6315.16
6315.16
6315.20 6234.1
4186.08
2082.02

4563.82
0.00
3121.20
2281.91
16065.00
346.42

3951.50
2635.50
2891.00
464.76
371.38
512.00

236.80
263.64
840.06

6023.50
50836.59 W
508.3659
51344.96 X
7213.97
58558.93 Y
8783.84
67342.77 Z
673.43
68016.20
7409.17
7409.20 7633.2
456.00

226.80
0.00
497.15
0.00
340.00
248.57
1750.00
37.74
0.00
96.88
962.50
315.00
64.00

29.60
28.60

658.00
5710.84 W
57.1084
5767.95 X
810.40
6578.35 Y
986.75
7565.10 Z
75.65
7640.75
7640.75
7640.80 7835.75

6051.00 A
35.00
70.00
20.21
16.15
14.00

658.00
6864.36 W
8.1336
X

115.42
Y

140.54

10.77
7139.22
7139.22
7139.20 7374.75

12188.80
6062.04
0.00
0.00
13278.53
0.00
9088.00
6644.24
46777.50
1008.68
2591.56
25728.50
8421.00
1712.00

791.80
803.78

2525.85
2018.35
525.00
1575.00

17542.00
159282.63 W
1592.8263
160875.46 X
22603.00
183478.46 Y
27521.77
211000.23 Z
2110.00
213110.23
7972.7
7972.70 8144.9

7409.20 A

91.00
7500.20 W
0.91
X

12.91
Y
15.72

1.21
7530.95
7530.95
7531.00 7744.8

6376.30 A

28.00
6404.30 W
0.28
X

3.97
Y

4.84

0.37
6413.76
6413.76
6413.80 6410.65

300.96
0.00
149.69
0.00
328.12

224.40
164.06
1155.00
24.91
0.00
276.50
196.00
210.00
30.31
24.22
60.32
18.98
40.00
0.00
18.50
63.00
0.00
25.26
20.18
35.00
52.50
3417.91 W
34.1791
3452.09 X
485.02
3937.11 Y
590.57
4527.68 Z
45.28
4572.96
6928.73
6928.70 7195.1
292.40

20.40

154.70

25.84

10.03

49.34

0.00
44.20

156.00

378.88
525.00
104.00
52.00
1812.79 W
18.1279
1830.92 X
257.24
2088.16 Y
313.22
2401.38 Z
24.01
2425.39
224.57
224.60 216.45

438.60

154.70

38.76

15.05

146.20

55.24

156.00

1768.10
2100.00
156.00
104.00
5132.65 W
51.3265
5183.98 X
728.35
5912.33 Y
886.85
6799.18 Z
67.99
6867.17
434.63
434.60 411.15

811.00 A
157.32

121.76

44.20
260.00

1515.51
2100.00
156.00
99.40
5265.19 W
44.5419
X

632.07
Y

769.62

59.00
6770.42
501.51
501.50 468.3

811.00 A
157.32

121.76

44.20

260.00

1515.51
2100.00
156.00
99.40
5265.19 W
44.5419
X

632.07
Y

769.62

59.00
6770.42
501.51
501.50 468.3
566.98 A
121.76
37.74
0.00
44.20
156.00
631.46
875.00
78.00
49.22
2560.36 W
19.9338
X

282.87
Y

344.43

26.41
3234.00
414.62
414.60
387.15
146.20

21.68

102.58

53.98

55.24

104.00

505.17
700.00
78.00
52.00
1818.85 W
18.1885
1837.04 X
258.10
2095.14 Y
314.27
2409.41 Z
24.09
2433.50
540.78
540.80 514.75

750.75

126.75

32.00

5.29

706.42
350.00
32.24
2003.45 W
20.0345
2023.48 X
284.30
2307.78 Y
346.17
2653.95 Z
26.54
2680.49
462.95
463.00 444.4

580.44

1399.41

768.58

2748.43
437.65

437.60 414.6
0.00
6662.50
0.00
0.00
0.00
504.00
0.00
0.00
0.00
0.00
870.00

0.00
49.87
0.00
0.00
0.00
1.37
0.00
6458.72
4550.00
23.40
19119.86 W
191.1986
19311.06 X
2713.20
22024.26 Y
3303.64
25327.90 Z
253.28
25581.18
1255.83
1255.80 1190.75

23085.40
0.00
107.69
0.00

361.74

544.00
9.83
0.00
0.00
0.00
11302.76
8400.00
269.10
0.00
0.00
-41830.70 A
2249.82 W
440.8052
X

6255.25
Y

7616.49
Z

583.93
17146.30
514.75
514.80 512.1

0.00
438.6

154.70

38.76

15.05
146.20

55.26

156.00

1768.10
2100.00
156.00
104.00
5132.67 W
51.3267
5184.00 X
728.35
5912.35 Y
886.85
6799.20 Z
67.99
6867.19
434.63
434.60 411.15

3900.00
0.00
0.51
0.00
265

694.39

4859.90 W
48.599
4908.50 X
689.64
5598.14 Y
839.72
6437.86 Z
64.38
6502.24
246.39 246.4

246.40

0.00
3100.5

874.25
504.00

37.31

0.00
4119.5
3850.00
161.46
12647.02 W
126.4702
12773.49 X
1794.68
14568.17 Y
2185.23
16753.40 Z
167.53
16920.93
641.19
641.20 690.05
0.00
292.4

20.40

154.70

25.84

10.03

49.34

44.20

156.00

378.88
525.00
104.00
52.00
1812.79 W
18.1279
1830.92 X
257.24
2088.16 Y
313.22
2401.38 Z
24.01
2425.39
224.57
224.60 216.45

185.25

503.75

3.21

3.21

0.00
326.97
189.00
10.40
1221.79 W
12.2179
1234.01 X
173.38
1407.39 Y
211.11
1618.50 Z
16.18
1634.68
136.22
136.20 131.5

136.20

0.00

0.00

0.00

5.08

0.00
403.67
262.50
13.00
684.25 W
6.8425
691.09 X
97.10
788.19 Y
118.23
906.42 Z
9.06
915.48
228.87
228.90 576

591.50

0.00
708.5

0.00
110.25
10.77

254.31
220.50
13.00
1908.83 W
19.0883
1927.92 X
270.87
2198.79 Y
329.82
2528.61 Z
25.29
2553.90
638.47
638.50 626.2
347.75

81.90
cudm

0.00
23.67

0.00
3.01
0.00
299.6
280.00
14.30

620.58 W
6.2058
626.79 X
88.06
714.85 Y
107.23
822.08 Z
8.22
830.30
31.46
31.50 544.15

133.25
39.00

19.30

0.00
1.62

0.00
112.35
87.50
10.40
403.42 W
4.0342
407.45 X
57.25
464.70 Y
69.71
534.41 Z
5.34
539.75
565.78
565.80 555.55

0.00

48.00
915.09

0.00
46.81
43.75
14.28
157.25

121.76
25.26
260.00
0
1515.51
2100.00
156.00
104.00
5658.06 W
52.37
5710.43 X
743.2
6453.64 Y
904.94

7358.57 Z
69.38
7427.95
550.22
550.2

327.73 A
24.00
527.34

0.00
46.81
43.75
14.28
121.76

0.00
37.74

22.10
156.00

631.46
875.00
78.00
52.00

2801.5 W
25.13
2826.63 X
356.61
3183.24 Y
434.21

3617.45 Z
33.29
3650.74
468.04
468.05

912.00
720.00
816.00
26.00

52.00
2526.00 W
25.26
2551.26 X
358.45
2909.71 Y
436.46
3346.17 Z
33.46
3379.63
140.82
140.80 140.8

1152.00
720.00
816.00
26.00

52.00
2766.00 W
27.66
2793.66 X
392.51
3186.17 Y
477.93
3664.10 Z
36.64
3700.74
154.2
154.20 154.2

1368.00
720.00
816.00
26.00

52.00
2982.00 W
29.82
3011.82 X
423.16
3434.98 Y
515.25
3950.23 Z
39.50
3989.73
166.24
166.20 166.25

1608.00
720.00
816.00
26.00
52.00
3222.00 W
32.22
3254.22 X
457.22
3711.44 Y
556.72
4268.16 Z
42.68
4310.84
179.62
179.60 179.6

406.13

-426.22

235.75

20.53
0.00
130

1515.51
2100.00
260.00
4241.70 W
42.417
4284.12 X
601.92
4886.04 Y
732.91
5618.95 Z
56.19
5675.14
197.05
197.10 184.85

A
7306.3

35.00
70.00
20.21
16.15
14.00
7449.4 W
1.43
7450.83 X
20.31
7471.14 Y
24.73
7495.86 Z
1.9
7497.76
7497.75

406.57 A

129.87 A

1.75
3.50
1.01
0.81
0.70
543.59 W
0.07
543.67 X
1.02
544.68 Y
1.24

545.92 Z
0.09
546.01
10111.33
10111.35
181.53 A
0.00
0.00
0.00
11.90
5.46
0.00
80.86 A
0.00
3.22
0.00
0.00
0.00
8.79
0.00
7.02
0.00
15.75
0.00
0.63
0.00
0.00
1.05
2.10
0.00
0.61
0.00
0.48
0.00
0.42

319.82 W
0.5743
X

8.15
Y
9.92

Z
0.76
339.22
11307.48
11307.50 11368.4

6312.54 A

1493.51 A

0.00
356.12

0.00
31.76

69.30

20.00

15.99

13.86

179.40
538.20
W
9021.46
12.15
9033.61 X
172.47
9206.08 Y
210
9416.09 Z
16.1
9432.19
9527.46
9527.45

103.30 A

35.79 A

23.38 A

0.00
5.77

5.60
1.12
0.30
0.24
0.21
8.84
27.04
W
210.98
0.49
211.46 X
6.88
218.35 Y
8.38
226.73 Z
0.64
227.37
14035.26
14035.25

4208.36 A

554.11 A

0.00
240.62

23.10
46.20
13.34
10.66
9.24
35.88
143.52
0.00
35.88
5312.83 W
5.5
5318.33 X
78.1
5396.43 Y
95.09

5491.52 Z
7.29
5498.81
8331.54
8331.55

600.00
12.48
12.40

151.55
121.10
378.00
1275.53 W
12.7553
1288.29 X
181.00
1469.29 Y
220.39
1689.68 Z
16.90
1706.58
1137.72
1137.70 1094

252.00
7.28
7.28

48.44
175.00
490.00 W
4.9
494.90 X
69.53
564.43 Y
84.66
649.09 Z
6.49
655.58
910.53
910.50 983.1

103.13
3.64
3.64

30.31
24.22
87.50
252.44 W
2.5244
254.96 X
35.82
290.78 Y
43.62
334.40 Z
3.34
337.74
900.65
900.70 862.15
2703.55 A

14.70
29.75
8.59
6.86
5.95

1583.44 A

43.16
4390.8 W
1.04
4391.84 X
14.73
4406.57 Y
17.94

4424.51 Z
1.38
4425.89
10438.41
10438.40 10438.4
0.00

78109.68 A

428.75
857.50
247.53
197.80
171.50

1583.44 A

81446.12 W
17.53 X
81463.65
248.76
81712.41 Y
302.89
82015.3 Z
23.22
82038.53
6697.02
6697

336.00
27.04
27.04

126.29
87.50
603.87 W
6.0387
609.91 X
85.69
695.60 Y
104.34
799.94 Z
8.00
807.94
80.79
80.80 427.25
5775.00
0.00
9.69
52.00

0.00
505.17
350.00
53.82
6745.68 W
67.4568
6813.14 X
957.25
7770.39 Y
1165.56
8935.95 Z
89.36
9025.31
90.25
90.30 75.4

5040.00
9.91

505.17
350.00
53.82
5958.90 W
59.589
6018.49 X
845.60
6864.09 Y
1029.61
7893.70 Z
78.94
7972.64
79.73
79.70 78.95

5775.00
9.91
52.00

0.00
505.17
350.00
53.82
6745.90 W
67.459
6813.36 X
957.28
7770.64 Y
1165.60
8936.24 Z
89.36
9025.60
90.26
90.30
5775.00
9.91
52.00

0.00
505.17
350.00
53.82
6745.90 W
67.459
6813.36 X
957.28
7770.64 Y
1165.60
8936.24 Z
89.36
9025.60
90.26
90.30 76.85

0.00
5825.64
9.91
52.00

80.73
525.00
27.04
6520.32 W
65.2032
6585.52 X
925.27
7510.79 Y
1126.62
8637.41 Z
86.37
8723.78
87.24
87.20 86.55

5775.00
9.91
52.00

0.00
505.17
350.00
53.82
6745.90 W
67.459
6813.36 X
957.28
7770.64 Y
1165.60
8936.24 Z
89.36
9025.60
90.26
90.30 76.85
5775.00
0.00
9.91
52.00

0.00
505.17
350.00
53.82
6745.90 W
67.459
6813.36 X
957.28
7770.64 Y
1165.60
8936.24 Z
89.36
9025.60
90.26
90.30 75.45

5040.00
9.91

505.17
350.00
53.82
5958.90 W
59.589
6018.49 X
845.60
6864.09 Y
1029.61
7893.70 Z
78.94
7972.64
79.73
79.70 78.95

5775.00
9.91
52.00

0.00
505.17
350.00
53.82
6745.90 W
67.459
6813.36 X
957.28
7770.64 Y
1165.60
8936.24 Z
89.36
9025.60
90.26
90.30 76.85

5775.00
9.91
52.00

0.00
505.17
350.00
53.82
6745.90 W
67.459
6813.36 X
957.28
7770.64 Y
1165.60
8936.24 Z
89.36
9025.60
90.26
90.30 76.85

5825.64
9.91
52.00

80.73
525.00
27.04
6520.32 W
65.2032
6585.52 X
925.27
7510.79 Y
1126.62
8637.41 Z
86.37
8723.78
87.24
87.20 86.55
5775.00
9.91
52.00

0.00
505.17
350.00
53.82
6745.90 W
67.459
6813.36 X
957.28
7770.64 Y
1165.60
8936.24 Z
89.36
9025.60
90.26
90.30 76.85

5500.00
9.43
52.00

312.00

303.10
210.00
53.82
6440.35 W
64.4035
6504.75 X
913.92
7418.67 Y
1112.80
8531.47 Z
85.31
8616.78
86.17
86.20 73.65

5500.00
9.43
52.00

312.00

303.10
210.00
53.82
6440.35 W
64.4035
6504.75 X
913.92
7418.67 Y
1112.80
8531.47 Z
85.31
8616.78
86.17
86.20 73.65
287.14
205.87
262.50
322.00
26.78

23.40
1127.69 W
11.2769
1138.97 X
160.02
1298.99 Y
194.85
1493.84 Z
14.94
1508.78
150.88
150.90 142.35

154.52
93.19
2.01

101.03
80.73
87.50
70.98
0.00
135
15.92

10.66
12.48
764.02 W
7.6402
771.66 X
108.42
880.08 Y
132.01
1012.09 Z
10.12
1022.21
102.22
102.20 101.3

5565.12

100.92
12.48
5678.52 W
56.7852
5735.31 X
805.81
6541.12 Y
981.17
7522.29 Z
75.22
7597.51
719.46
719.50 718.55
0.00
42160

131.60
1091.20

30.08
1273.03
1017.25
2821.00
242.32
48766.48 W
487.6648
49254.14 X
6920.21
56174.35 Y
8426.15
64600.50 Z
646.01
65246.51
57996.9
57996.90 57542.45
14544.00
32.16
266.64

7.40
15.75

0.34
720.00

526.39

1273.03
1017.25
2821.00
242.32
21466.28 W
214.6628
21680.94 X
3046.17
24727.11 Y
3709.07
28436.18 Z
284.36
28720.54
25529.37
25529.40 17086.75

2812.50
56.25

882.00
0.00
53.82

60.62
48.44
87.50
53.82
4054.95 W
40.5495
4095.50 X
575.42
4670.92 Y
700.64
5371.56 Z
53.72
5425.28
542.53
542.50 540.6

98.70

0.46

80.60

80.73
70.00
330.49 W
3.3049
333.79 X
46.90
380.69 Y
57.10
437.79 Z
4.38
442.17
147.39
147.40 142.2

132.30

0.61

107.64

108.99
94.50
444.04 W
4.4404
448.48 X
63.01
511.49 Y
76.72
588.21 Z
5.88
594.09
198.03
198.00 191
278.00
0.00
2.16
0.00
2.08

27.05
23.45
3.64
336.38 W
3.3638
339.74 X
47.73
387.47 Y
58.12
445.59 Z
4.46
450.05
450.05 444.8

450.10

370.00
0.00
2.16
0.00
2.6

35.93
31.15
4.68
446.52 W
4.4652
450.99 X
63.36
514.35 Y
77.15
591.50 Z
5.91
597.41
597.41 590.45

597.40

91.65
0.00
0.47

80.60
0.00
74.9
70.00
317.62 W
3.1762
320.80 X
45.07
365.87 Y
54.88
420.75 Z
4.21
424.96
141.65
141.70 139.05

122.85
0.00
0.61

107.64

108.99
94.50
434.59 W
4.3459
438.94 X
61.67
500.61 Y
75.09
575.70 Z
5.76
581.46
193.82
193.80 186.8

252.59
201.84
350.00
53.82
858.25 W
8.5825
866.83 X
121.79
988.62 Y
148.29
1136.91 Z
11.37
1148.28
38.28
38.30 35.65

262.50

1400.00
1662.50 W
16.625
1679.13 X
235.92
1915.05 Y
287.26
2202.31 Z
22.02
2224.33
535.98
536.00 492.45

10.10
8.07
87.50
52.50
158.17 W
1.5817
159.75 X
22.45
182.20 Y
27.33
209.53 Z
2.10
211.63
211.63 194.45

211.60

456.00
226.80
0.00
90.21
0.00
573.75
248.57
1443.75
31.13
59.40

350.00
210.00

68.62
700.00
315.00
25.90
26.00
4825.13 W
48.2513
4873.38 X
684.71
5558.09 Y
833.71
6391.80 Z
63.92
6455.72 6934.9
6455.72
6455.70

456.00
226.80

0.00
90.21
0.00
573.75
248.57
1443.75
31.13
59.40

350.00
210.00

68.62
700.00
315.00
25.90
26.00

658.00
5483.13 W
54.8313
5537.96 X
778.08
6316.04 Y
947.41
7263.45 Z
72.63
7336.08
7336.08 7741.9

7336.10

43.75
0.94

1.80

46.49 W
0.4649
46.95 X
6.60
53.55 Y
8.03
61.58 Z
0.62
62.20
62.2 69.75

62.20

87.50
1.89

3.60
92.99 W
0.9299
93.92 X
13.20
107.12 Y
16.07
123.19 Z
1.23
124.42
124.42
124.40 139.55
131.25
2.83

5.40
139.48 W
1.3948
140.87 X
19.79
160.66 Y
24.10
184.76 Z
1.85
186.61
186.61 209.3

186.60

437.50
9.43
446.93 W
4.4693
451.40 X
63.42
514.82 Y
77.22
592.04 Z
5.92
597.96
597.96 673.55

598.00

10533.82 A

9926.40 A

779.85 A
26.00

0.00
159.9

0.00
505.17
2100.00
1526.64 A
25353.59 W
25.87
25379.45 X
367.09
25746.55 Y
446.98

26193.52 Z
34.27
26227.79
26227.79
19005.64
19005.65

456.00
226.80

0.00
90.21
0.00
573.75
248.57
1443.75
31.13
59.40

0.00
350
300.00

210.00
68.62
700.00
315.00
25.90
26.00
5125.13 W
51.2513
5176.38 X
727.28
5903.66 Y
885.55
6789.21 Z
67.89
6857.10
6857.1 7336.25

6857.10

456.00
226.80

0.00
90.21
0.00
573.75
248.57
1443.75
31.13
59.40

0.00
350
300.00
0.00
210
68.62
700.00
315.00
25.90
26.00

658.00
5783.13 W
57.8313
5840.96 X
820.66
6661.62 Y
999.24
7660.86 Z
76.61
7737.47
7737.47
7737.50

210.00

W
55759.73 W
557.597265
56317.32 X
7912.58
64229.90 Y
9634.49
73864.39 Z
738.64
74603.03
2826.94 280.95

2826.90

494.00
192.00
0.00
74.98
0.00
25.47
0.00
499.5
216.41
2.10
22.29
1443.75
31.13
59.40

350.00
300.00
0.00
210

68.62
700.00
315.00
25.90
26.00
5056.55 W
50.5655
5107.12 X
717.55
5824.67 Y
873.70
6698.37 Z
66.98
6765.35
6765.35 7304.2

6765.40
494.00

192.00
0.00
74.98
0.00
25.47
0.00
499.5
216.41
2.10
22.29
1443.75
31.13
59.40

350.00
300.00
0.00
210

68.62
700.00
315.00
25.90
26.00

658.00
5714.55 W
57.1455
5771.70 X
810.92
6582.62 Y
987.39
7570.01 Z
75.70
7645.71
7645.71 8111.2

7645.70

76.00
2.00

133.21
59.50
6.00
276.71 W
2.7671
279.48 X
39.27
318.75 Y
47.81
366.56 Z
3.67
370.23
37.02
37.00 35.05

30.00

7.54
35.54
73.08 W
0.7308
73.81 X
10.37
84.18 Y
12.63
96.81 Z
0.97
97.78
97.78
97.80 97.8

39.00

11.80
50.34
101.14 W
1.0114
102.15 X
14.35
116.50 Y
17.48
133.98 Z
1.34
135.32
135.32 135.3

135.30

69.50

17.38
59.22
146.10 W
1.461
147.56 X
20.73
168.29 Y
25.24
193.53 Z
1.94
195.47
195.47
195.50 195.45

80.00

25.68
65.14
170.82 W
1.7082
172.53 X
24.24
196.77 Y
29.52
226.29 Z
2.26
228.55
228.55
228.60 228.55

110.00

30.96
65.14
206.10 W
2.061
208.16 X
29.25
237.41 Y
35.61
273.02 Z
2.73
275.75
275.75
275.80 275.75

440.00

1.92
0.00
2.6

27.05
23.45
4.68
499.70 W
4.997
504.70 X
70.91
575.61 Y
86.34
661.95 Z
6.62
668.57
668.57
668.60 663.35

660.00

1.92
0.00
2.6

27.05
23.45
4.68
719.70 W
7.197
726.90 X
102.13
829.03 Y
124.35
953.38 Z
9.53
962.91
962.91
962.90 957.7

3100.00
637.50
249.80

25.26
50.52
52.50
4115.58 W
41.1558
4156.74 X
584.02
4740.76 Y
711.11
5451.87 Z
54.52
5506.39
5506.39 5494.7

5506.40

4000.00
675.00
249.80

25.26
50.52
52.50
5053.08 W
50.5308
5103.61 X
717.06
5820.67 Y
873.10
6693.77 Z
66.94
6760.71
6760.71 6749

6760.70

5400.00
712.50
249.80

25.26
50.52
52.50
6490.58 W
64.9058
6555.49 X
921.05
7476.54 Y
1121.48
8598.02 Z
85.98
8684.00
8684 8672.3

8684.00

2400.00
637.50
249.80

25.26
50.52
52.50
3415.58 W
34.1558
3449.74 X
484.69
3934.43 Y
590.16
4524.59 Z
45.25
4569.84
4569.84 4558.1

4569.80

2800.00
675.00
249.80

25.26
50.52
52.50
3853.08 W
38.5308
3891.61 X
546.77
4438.38 Y
665.76
5104.14 Z
51.04
5155.18
5155.18 5143.45

5155.20

3400.00
712.50
249.80

25.26
50.52
52.50
4490.58 W
44.9058
4535.49 X
637.24
5172.73 Y
775.91
5948.64 Z
59.49
6008.13
6008.13 5996.4

6008.10

2800.00
637.50
249.80

25.26
50.52
52.50
3815.58 W
38.1558
3853.74 X
541.45
4395.19 Y
659.28
5054.47 Z
50.54
5105.01
5105.01 5093.3

5105.00

3200.00
675.00
249.80

25.26
50.52
52.50
4253.08 W
42.5308
4295.61 X
603.53
4899.14 Y
734.87
5634.01 Z
56.34
5690.35
5690.35 5678.65

5690.40

4000.00
712.50
249.80

25.26
50.52
52.50
5090.58 W
50.9058
5141.49 X
722.38
5863.87 Y
879.58
6743.45 Z
67.43
6810.88
6810.88 6799.15

6810.90

270.46 P

8.16 Q

69.66 R
0.00
215.28
33.60

653.73 A

883.05 A
A
119.76
201.34
2455.05 W
4.5
2459.55 X
63.89

2523.44 Y
77.79
2601.23 Z
5.96
2607.19
501.38
501.4

214.98 P

6.49 Q

55.37 R
0.00
171.12
33.60

586.82 A

883.05 A
A
107.51
201.34
2260.27 W
4.06
2264.33 X
57.62

2321.95 Y
70.16

2392.11 Z
5.38
2397.49
461.06
461.05
187.24 P

3.77 Q

47.75 R
0.00
149.04
33.60

550.78 A

883.05 A

100.90 A
201.34
2157.48 W
3.84
2161.32 X
54.49

2215.8 Y
66.35
2282.15 Z
5.09
2287.24
439.85
439.85

586543.40 P

64519.77
8211.61

659274.78 W
6592.7478
665867.53 X
93554.39
759421.92 Y
113913.29
873335.21 Z
8733.35
882068.56
7350.57
7350.60 7350.55

686801.60 P

75548.18

9615.22
771965.00 W
7719.65
779684.65 X
109545.69
889230.34 Y
133384.55
1022614.89 Z
10226.15
1032841.04
8607.01
8607.00 8607

9363.55

-8607

756.55
756.55
756.55

747170.85 P

82188.79

10460.39

0.00

0.00

0.00
0.00

0.00
0.00
0.00
0.00
0.00
0.00

839820.03 W
8398.2003
848218.23 X
119174.66
967392.89 Y
145108.93
1112501.82 Z
11125.02
1123626.84
42577.75
42577.80 9363.55

252000.00
43200.00
51840.00
34992.00

0.00
8035.2

301.58
1666
6416.6

3840
400
1440
36000

25200

586543.38
586543.38
586543.4

252000.00
43984.00
46032.00
30958.20

0.00
8294.4
0.00
115200

329.00
1768.10
7000.00

3840.00
400.00
1440.00
36000.00
0.00
25200

686801.58
686801.58
686801.6

252000.00
43200.00
51840.00
34992.00

0.00
8294.4
0.00
161280

294.00
1515.51
6300.00

3840.00
400.00
1440.00

36000.00
0.00
25200

747170.84
747170.84
747170.85

312000.00

72938.97 A

62940.15 A

1140097.56 A

11466.90 A

0.00
40877.6
30187.50

11856.00
226.42
3000.00

99440.00

20639.35
0.00
47060

0.00
9942.84
0.00
1080
17280.00
0.00
7000

27451.44 A
29893.14 A

2354.00
38400.00
1973788.19 W
6083.49
1979871.68 X
86327.8
2066199.48 Y
105114.08

2171313.56 Z
8058.75
2179372.31
15134.53
15134.55

839.72

8400.00

60.62

68.66

76.07
7683.18
76.83
76.85

8062.64 Z
80.63
8143.26
8143.25
SUB HEAD : 6.0

BRICK WORK
Code Description Unit Quantity Rate Amount
6.1 Brick work with common burnt
clay F.P.S. (non modular) bricks of
class designation 7.5 in foundation
and plinth in:

6.1.1 Cement mortar 1:4 (1 cement : 4


coarse sand)

Details of cost for 1 cum


MATERIAL
2602 Common burnt clay F.P.S. (non modular) 1000 0.494 5000 2470.00
bricks class designation 7.5 Nos
2201 Carriage of Bricks 1000 0.494 283.01 139.81
Cement mortar 1 : 4 (1 cement : 4 coarse Nos
sand)
3.9 Rate as per item No 3.9 of SH: Mortar cum 0.25 3548.00 887.00
9999 Sundries L.S. 2.73 2 5.46
LABOUR
23 Mason (brick layer) 1st class day 0.36 505.17 181.86
24 Mason (brick layer) 2nd class day 0.36 403.67 145.32
18 Coolie day 1.37 350.00 479.50
11 Bhisti day 0.2 350.00 70.00
TOTAL 4378.95 W
Add 1 % Water charges on "W" 43.7895
TOTAL 4422.74 X
Add GST (multiplying factor 0.1405) on "X" 621.39
TOTAL 5044.13 Y
Add 15 % Contractor's profit and overheads on 756.62
"Y"
Total 5800.75 Z
Add Cess @ 1% on "Z" 58.01
Cost of 1 Cum. 5858.76
Say 5858.76
5858.80
6.1.2 Cement mortar 1:6 (1 cement : 6
coarse sand)
Details of cost for 1 cum
MATERIAL
2602 Common burnt clay F.P.S. (non modular) 1000 0.494 5000 2470.00
bricks class designation 7.5 Nos
2201 Carriage of Bricks 1000 0.494 283.01 139.81
Cement mortar 1 : 6 (1 cement : 6 coarse Nos 0
sand) (Rate as per item No 3.11)
3.11 Rate as per Item No.3.11 of SH: Mortar cum 0.25 2967.00 741.75
9999 Sundries L.S. 2.73 2 5.46
LABOUR
23 Mason (brick layer) 1st class day 0.36 505.17 181.86
24 Mason (brick layer) 2nd class day 0.36 403.67 145.32
18 Coolie day 1.37 350.00 479.50
11 Bhisti day 0.2 350.00 70.00
TOTAL 4233.70 W
Add 1 % Water charges on "W" 42.337
TOTAL 4276.04 X
Add GST (multiplying factor 0.1405) on "X" 600.78
TOTAL 4876.82 Y
Add 15 % Contractor's profit and overheads on 731.52
"Y"
Total 5608.34 Z
Add Cess @ 1% on "Z" 56.08
Cost of 1 Cum. 5664.42
Say 5664.42
5664.40
6.2 Brick work with common burnt clay
modular bricks of class designation 7.5 in

foundation and plinth in:

6.2.1 Cement mortar 1:4 (1 cement : 4


coarse sand)
Details of cost for 1 cum
MATERIAL
7900 Modular common burnt clay bricks of class 1000 0.487 4000 1948.00
designation 7.5 Nos
2201 Carriage of Bricks 1000 0.487 283.01 137.83
Cement mortar 1 : 4 (1 cement : 4 coarse Nos 0
sand)
3.9 Rate as per item No 3.9 of SH: Mortar cum 0.22 3548.00 780.56
9999 Sundries L.S. 2.73 2 5.46
LABOUR 0
23 Mason (brick layer) 1st class day 0.33 505.17 166.71
24 Mason (brick layer) 2nd class day 0.33 403.67 133.21
18 Coolie day 1 350.00 350.00
11 Bhisti day 0.18 350.00 63.00
TOTAL 3584.77 W
Add 1 % Water charges on "W" 35.8477
TOTAL 3620.62 X
Add GST (multiplying factor 0.1405) on "X" 508.70
TOTAL 4129.32 Y
Add 15 % Contractor's profit and overheads on 619.40
"Y"
Total 4748.72 Z
Add Cess @ 1% on "Z" 47.49
Cost of 1 Cum. 4796.21
Say 4796.21
4796.20

6.2.2 Cement Mortar 1:6 (1 cement : 6


coarseofsand).
Details cost for 1 cum
MATERIAL
7900 Modular common burnt clay bricks of class 1000 0.487 4000 1948.00
designation 7.5 Nos
2201 Carriage of Bricks 1000 0.487 283.01 137.83
Cement mortar 1 : 6 (1 cement : 6 coarse Nos
sand)
3.11 Rate as per item No 3.11 of SH: Mortar cum 0.22 2967.00 652.74
9999 Sundries L.S. 2.73 2 5.46
LABOUR 0
23 Mason (brick layer) 1st class day 0.33 505.17 166.71
24 Mason (brick layer) 2nd class day 0.33 403.67 133.21
18 Coolie day 1 350.00 350.00
11 Bhisti day 0.18 350.00 63.00
TOTAL 3456.95 W
Add 1 % Water charges on "W" 34.5695
TOTAL 3491.52 X
Add GST (multiplying factor 0.1405) on "X" 490.56
TOTAL 3982.08 Y
Add 15 % Contractor's profit and overheads on 597.31
"Y"
Total 4579.39 Z
Add Cess @ 1% on "Z" 45.79
Cost of 1 Cum. 4625.18
Say 4625.18
4625.20
6.3 Brick work with common burnt clay
machine moulded perforated bricks of class
designation 12.5 conforming to IS: 2222 in
superstructure above
floor five level plinth level
in cement up to 1:6 (1
mortar
cement : 6 coarse sand) :
6.3.1 With F.P.S.(non modular)
bricks
Details of cost for 1 cum
MATERIAL
7901 Machine moulded perforated common burnt 1000 0.494 4700 2321.80
clay FPS (non modular) bricks of class Nos
designation 12.5
2201 Carriage of Bricks 1000 0.494 283.01 139.81
Cement mortar 1 : 6 (1 cement : 6 coarse Nos 0
sand)
3.11 Rate as per item No 3.11 of SH: Mortar cum 0.25 2967.00 741.75
9999 Sundries L.S. 2.73 2 5.46
LABOUR
23 Mason (brick layer) 1st class day 0.47 505.17 237.43
24 Mason (brick layer) 2nd class day 0.47 403.67 189.72
18 Coolie day 1.8 350.00 630.00
11 Bhisti day 0.2 350.00 70.00
9999 Scaffolding L.S. 22.36 2 44.72
Extra labour element required for lifting of
materials (above floor two level upto floor
five level)
18 Coolie day 1.13 350.00 395.50
TOTAL 4776.19 W
Add 1 % Water charges on "W" 47.7619
TOTAL 4823.95 X
Add GST (multiplying factor 0.1405) on "X" 677.77
TOTAL 5501.72 Y
Add 15 % Contractor's profit and overheads on 825.26
"Y"
Total 6326.98 Z
Add Cess @ 1% on "Z" 63.27
Cost of 1 Cum. 6390.25
Say 6390.25
6390.30
6.3.2 With Modular bricks

Details of cost for 1 cum


MATERIAL
7902 Machine moulded common burnt clay 1000 0.487 5200 2532.40
modular perforated bricks of class Nos
designation 12.5
2201 Carriage of Bricks 1000 0.487 283.01 137.83
Cement mortar 1 : 6 (1 cement : 6 coarse Nos
sand)
3.11 Rate as per item No 3.11 of SH: Mortar cum 0.22 2967.00 652.74
9999 Sundries L.S. 2.73 2 5.46
LABOUR
23 Mason (brick layer) 1st class day 0.44 505.17 222.27
24 Mason (brick layer) 2nd class day 0.44 403.67 177.61
18 Coolie day 1.43 350.00 500.50
11 Bhisti day 0.18 350.00 63.00
9999 Scaffolding L.S. 16.38 2 32.76
Extra labour element required for lifting of
materials (above floor two level upto floor
18 Coolie day 1.13 350.00 395.50
TOTAL 4720.07 W
Add 1 % Water charges on "W" 47.2007
TOTAL 4767.27 X
Add GST (multiplying factor 0.1405) on "X" 669.80
TOTAL 5437.07 Y
Add 15 % Contractor's profit and overheads on 815.56
"Y"
Total 6252.63 Z
Add Cess @ 1% on "Z" 62.53
Cost of 1 Cum. 6315.16
Say 6315.16
6315.20
6.4 Brick work with common burnt clay
F.P.S. (non modular) bricks of class
and sizes in
designation 7.5:in superstructure above plinth
6.4.1 level up to floor
Cement mortar V level in all
1:4 (1 shapes: 4
cement 0.00
coarse sand)
Details of cost for 1 cum
MATERIAL
2602 Common burnt clay F.P.S. (non modular) 1000 0.494 5000 2470.00
bricks class designation 7.5 Nos
Cement mortar 1 : 4 (1 cement : 4 coarse
sand)
3.9 Rate as per Item Number 3.9 of SH: cum 0.25 3548.00 887.00
Mortars
2201 Carriage of Bricks 1000 0.494 283.01 139.81
Nos
9999 Sundries L.S. 2.73 2 5.46
LABOUR
23 Mason (brick layer) 1st class day 0.47 505.17 237.43
24 Mason (brick layer) 2nd class day 0.47 403.67 189.72
"Extra labour element required for lifting of
materials (above floor two level upto floor
five level)"
18 Coolie day 1.8 350.00 630.00
11 Bhisti day 0.2 350.00 70.00
9999 Scaffolding L.S. 22.36 2 44.72
18 Coolie day 1.13 350.00 395.50
TOTAL 5069.64 W
Add 1 % Water charges on "W" 50.6964
TOTAL 5120.34 X
Add GST (multiplying factor 0.1405) on "X" 719.41
TOTAL 5839.75 Y
Add 15 % Contractor's profit and overheads on 875.96
"Y"
Total 6715.71 Z
Add Cess @ 1% on "Z" 67.16
Cost of 1 Cum. 6782.87
Say 6782.87
6782.90
6.4.2 Cement mortar 1:6 (1 cement : 6
coarse sand)
Details of cost for 1 cum
MATERIAL
2602 Common burnt clay F.P.S. (non modular) 1000 0.494 5000 2470.00
bricks class designation 7.5 Cement mortar Nos
1:06
3.11 Rate as per Item Number 3.11 of SH: cum 0.25 2967.00 741.75
Mortars
2201 Carriage of Bricks 1000 0.494 283.01 139.81
Nos
9999 Sundries L.S. 2.73 2 5.46
LABOUR
23 Mason (brick layer) 1st class day 0.47 505.17 237.43
24 Mason (brick layer) 2nd class day 0.47 403.67 189.72
18 Coolie day 1.8 350.00 630.00
11 Bhisti day 0.2 350.00 70.00
9999 Scaffolding L.S. 22.36 2 44.72
Extra labour element required for lifting of
materials (above floor two level upto floor
five level)
18 Coolie day 1.13 350.00 395.50
TOTAL 4924.39 W
49.2439
Add 1 % Water charges on "W" 4973.63
TOTAL 698.80 X
5672.43
Add GST (multiplying factor 0.1405) on "X" 850.87
TOTAL 6523.30 Y
Add 15 % Contractor's profit and overheads on 65.23
"Y"
Total 6588.53 Z
Add Cess @ 1% on "Z" 6588.53
Cost of 1 Cum. 6588.50
Say

6.5 Extra for brick work / AAC block masonry /


Tile brick
Details masonry
of cost for 5.3 in superstructure
cum per four floors .
above floor V level, for each four floors or
37 Mobile crane by mechanical means.
part thereof day 0.125 7500 937.50
TOTAL 937.50 W
Add 1 % Water charges on "W" 9.375
TOTAL 946.88 X
Add GST (multiplying factor 0.1405) on "X" 133.04
TOTAL 1079.92 Y
Add 15 % Contractor's profit and overheads on 161.99
"Y"
Total 1241.91 Z
Add Cess @ 1% on "Z" 12.42
Cost of 5.3 Cum. 1254.33
Cost for 1 cum 236.67
Say 236.70

6.6 Extra for forming cavity 5 cm to 11.5 cm wide in


cavity walls with necessary weep and vent
holes including use of cores and cost of
providing and fixing design.
as per approved bitumastic coated M .S.
Details of cost for 10sqm.

MATERIAL
Mild steel 25mmx3mm section 30cm long
30 No. = 9 metres @ 0.6kg/m = 5.40 kg
1008 Flats upto 10 mm in thickness quintal 0.054 5300 286.20
9999 Painting the steel Bitumen L.S. 13.52 2 27.04
2205 Carriage of Steel tonne 0.005 94.34 0.47
Extra labour for keeping cavity clear and
fixing wall ties and delay caused:
23 Mason (brick layer) 1st class day 0.37 505.17 186.91
24 Mason (brick layer) 2nd class day 0.37 403.67 149.36
17 Beldar day 0.92 350.00 322.00
9999 Add for use of Core L.S. 4.55 2 9.10
TOTAL 981.08 W
Add 1 % Water charges on "W" 9.8108
TOTAL 990.89 X
Add GST (multiplying factor 0.1405) on "X" 139.22
TOTAL 1130.11 Y
Add 15 % Contractor's profit and overheads on 169.52
"Y"
Total 1299.63 Z
Add Cess @ 1% on "Z" 13.00
Cost for 10 sqm. 1312.63
Cost for 1 sqm. 131.26
Say 131.30

6.7 Providing half brick masonry with common


burnt clay F.P.S. (non modular) bricks of class
cm / 11.4 cm
designation wide
7.5 in bitumen
cement mortar felt type 3
1:3 (1
grade
Cement 1.
: 3 coarse sand) in
Details of cost for 10m lengthsuperstructure for

MATERIAL
Half brick masonry 1:3 (Average)
1x10x0.27 = 2.7
6.12.1 Rate as per item No. 6.12.1 of sqm 2.7 717.70 1937.79 A
SH: Brick Work
Bitumen felt type- 3 grade 1 1x10mx11.4m
= 1.14 sqm. Add for wastage and
overlapping @ 5% = 0.06 sqm.
Total = 1.20 sqm
322 Bitumen felt :Type 3 grade 1 sqm 1.2 70 84.00
LABOUR
23 Mason (brick layer) 1st class day 0.12 505.17 60.62
24 Mason (brick layer) 2nd class day 0.12 403.67 48.44
17 Beldar day 0.06 350.00 21.00
TOTAL 2151.85 W
Add 1 % Water charges on "W-A" 214.06 2.1406
TOTAL X
Add GST (multiplying factor 0.1405) on "X-A" 216.20 30.38
TOTAL Y
Add 15 % Contractor's profit and overheads on 246.58 36.99
"Y-A"
Total
Add Cess @ 1% on "Z-A" 283.57 2.84 Z
Cost of 10 metre 2224.20
Cost for 1 metre 222.42
Say 222.40

6.8 Brick work 7 cm thick with common burnt clay


F.P.S. (non modular) brick of class designation
7.5 in cement mortar 1:3 (1 cement : 3 coarse
sand)
aboveinplinth
superstructure
level and upto floor five
level.
Details of cost for 10sqm.

MATERIAL
2602 Common burnt clay F.P.S. (non modular) 1000 0.377 5000 1885.00
bricks class designation 7.5 Cement mortar Nos
1:03
3.8 Rate as per Item Number 3.8 of SH: cum 0.181 4129.00 747.35
Mortars
2201 Carriage of Bricks 1000 0.377 283.01 106.69
LABOUR Nos
23 Mason (brick layer) 1st class day 0.72 505.17 363.72
24 Mason (brick layer) 2nd class day 0.72 403.67 290.64
18 Coolie day 1.76 350.00 616.00
11 Bhisti day 0.36 350.00 126.00
9999 Sundries and scaffolding L.S. 7.15 2 14.30
Extra labour for lifting of material (above
floor two level up to floor five level)
18 Coolie day 1.29 350.00 451.50
TOTAL 4601.20 W
Add 1 % Water charges on "W" 46.012
TOTAL 4647.21 X
Add GST (multiplying factor 0.1405) on "X" 652.93
TOTAL 5300.14 Y
Add 15 % Contractor's profit and overheads on 795.02
"Y"
Total 6095.16 Z
Add Cess @ 1% on "Z" 60.95
Cost for 10 sqm. 6156.11
Cost for 1 sqm. 615.61
Say 615.60

6.9 Brick work in plain arches in superstructure


above plinth level and upto floor five level
mortar
including1:3 (1 cement
centering : 3 coarse
and shuttering sand).
complete for
span upoftocost
Details 6 metres with common burnt clay
for 1 cum.
MATERIAL
2602 Common burnt clay F.P.S. (non modular) 1000 0.494 5000 2470.00
bricks class designation 7.5 Cement mortar Nos
1:03
3.8 Rate as per Item Number 3.8 of SH: cum 0.25 4129.00 1032.25
Mortars
2201 Carriage of Bricks 1000 0.494 283.01 139.81
Nos
9999 Sundries L.S. 2.73 2 5.46
Centring and shuttering
Taking a semi circular arch 3.6m span,
3.6m long and 0.40m thick Area of
centering = 3.142 x 1.8 x 3.6 = 20.37 sqm.
Brick work in Arch = 3.142x2.00x0.4x3.6 =
9.05cum.
Area per cum = 20.37/9.05 = 2.25 sqm
5.9.9 Rate as per item no 5.9.9 of sqm 2.25 1190.75 2679.19 A
9999 Scaffolding L.S. 18.85 2 37.70
LABOUR
23 Mason (brick layer) 1st class day 0.53 505.17 267.74
24 Mason (brick layer) 2nd class day 0.53 403.67 213.95
18 Coolie day 2.29 350.00 801.50
11 Bhisti day 0.2 350.00 70.00
Extra labour for lifting of material (above
floor two level up to floor five level)
18 Coolie day 1.13 350.00 395.50
TOTAL 8113.10 W
Add 1 % Water charges on "W-A" 5433.91 54.3391
TOTAL X
Add GST (multiplying factor 0.1405) on "X- A" 5488.25 771.10
TOTAL Y
Add 15 % Contractor's profit and overheads on 6259.35 938.90
"Y-A"
Total
Add Cess @ 1% on "Z-A" 7198.25 71.98 Z
Cost for 1 cum. 9949.42
Say 9949.42
9949.40

6.10 Brick work in gauged arches in


superstructure above plinth level and upto floor
modular)
five level in bricks of class
cement mortar 1:3 designation
(1 cement : 3
7.5.
coarse sand) including centering
Details of cost for 1 cum. and

MATERIAL
2602 Common burnt clay F.P.S. (non modular) 1000 0.538 5000 2690.00
bricks class designation 7.5 Cement mortar Nos
1:03 5.46
3.8 Rate as per Item Number 3.8 of SH: cum 0.25 4129.00 1032.25
Mortars
2201 Carriage of Bricks 1000 0.538 283.01 152.26
Nos
9999 Sundries L.S. 2.73 2 5.46
Centring and shuttering (Area same as in
item No. 6.9)
5.9.9 Rate as per item no 5.9.9 of sqm 2.25 1255.80 2825.55 A
SH : Reinforced cement concrete work
9999 Scaffolding L.S. 18.85 2 37.70
LABOUR
23 Mason (brick layer) 1st class day 1.13 505.17 570.84
24 Mason (brick layer) 2nd class day 1.13 403.67 456.15
18 Coolie day 4.42 350.00 1547.00
11 Bhisti day 0.2 350.00 70.00
Extra labour for lifting of material
(above floor two level up to floor five level)
18 Coolie day 1.13 350.00 395.50
TOTAL 9788.17 W
Add 1 % Water charges on "W-A" 6962.62 69.6262
TOTAL X
Add GST (multiplying factor 0.1405) on "X- 7032.25 988.03
A" Y
TOTAL 8020.28 1203.04
Add 15 % Contractor's profit and overheads
7533.04
on "Y-A" 9223.32 92.23 Z
Total 12141.10
Add Cess @ 1% on "Z-A" 12141.1
Cost for 1 cum. 12141.10
Say

6.11 Extra for additional cost of centering for


arches exceeding 6m span including all
shuttering, bolting, wedging and removal
(Area
Detailsof
ofthe
costsoffit to be
for 33.31 measured).
sqm
MATERIAL
Centering and shuttering for arches and carved
surface exceeding 6m in span
(an average of 8m) Radius R = 5m 2R-2=4+4
tan -¹ (4/3)=53.28° 2x53.28°=106°
Surface area =2x22/7x5x3.6x
106/360=33.3sqm.
Arc=9.25m
MATERIAL
Tie-2x8x0.18x0.05 =0.144cum Struts-
2x2.5x0.1x0.1 =0.050cum.
Struts-2x1.77x0.1x0.1=0.035cum. Ribs-
6x1.54x0.23x0.1=0.213cum. Struts-
2x1.72x0.1x0.1=0.034cum.
Total=0.476cum.
For four such frames =0.476x4 = 1.904
cum. laggings-75x3.6x0.125x0.075=2.531cum.
Tie-2x3.6x0.225x0.038=0.062cum. Brace-
3x2x2.14x0.225x0.038=0.110
Brace-3x4x3.8x0.225x0.038=0.390
Sleepers-4x3.6x0.20x0.15=0.432
Sleepers-2x4x3.6x0.175x0.075=0.378
Vertical post-4x4x3.6x0.15x0.15=1.296
Total = 7.103cum.
Qty taken as 1/8th of qty for cost of using
once
= 7.103/8 = 0.8885 cum (887.90 cudm)
1197 Second class kail wood in scantling 10 88.79 260 23085.40
cudm
2204 Carriage of Timber Fittings: cum 0.8879 121.29 107.69
3 way straps 50mmx10mm = 32 Nos.
32 no. @0.50cm each = 16m
Straps-50mmx10mm = 8 Nos. @0.25cm
each = 2m
Total = 18m @ 3.9kg/m = 70.2 kg. =
0.702qtl. Qty taken l/8th of qty for cost
using once = 0.702/8 = 0.0878 qtl.
1225 Mild steel flat strap fitting quintal 0.0878 4120 361.74
Bolts 160 Nos. 254 mm long 16mm
dia.160x 0.254x 1.58=64.21 kg=0.64qtl.
Qty taken 1/8th of qty for cost using once =
0.64/8 = 0.08 qtl
1034 Bolts and nuts upto 300 mm in length quintal 0.08 6800 544.00
Carriage of steel = 0.1342 t
Qty taken 1/8th of qty for cost using once =
0.1342/8 = 0.0168 tonne
2302 Carriage of G.I.sheet and accessories tonne 0.0168 94.34 1.58
LABOUR
15 Carpenter 2nd class day 28 403.67 11302.76
17 Beldar day 24 350.00 8400.00
9999 Sundries L.S. 134.55 2 269.10
Less Cost of shuttering etc. for an arch
exceeding 6 m span i.e. for an average of 8
m span
5.9.9 Rate as per item no 5.9.9 of sqm -33.31 1255.80 -41830.70 A
SH : Reinforced cement concrete work
TOTAL 2241.57 W
Add 1 % Water charges on "W-A" 44072.27 440.7227
TOTAL X
Add GST (multiplying factor 0.1405) on "X-A" 44512.99 6254.08
TOTAL Y
Add 15 % Contractor's profit and overheads on 50767.07 7615.06
"Y-A"
Total
Add Cess @ 1% on "Z-A" 58382.13 583.82 Z
Cost of 33.31sqm. 17135.25
Cost per sqm 514.42
Say 514.40

6.12 Half brick masonry with common


burnt clay F.P.S. (non modular) bricks
6.12.1 of class designation 7.5 in foundations
Cement
and mortar
plinth in : 1:3 (1 cement : 3
coarse sand)
Details of cost for 10 sqm.
MATERIAL
2602 Common burnt clay F.P.S. (non modular) 1000 0.565 5000 2825.00
bricks class designation 7.5 Cement mortar Nos
1:03
3.8 Cement mortar 1:3 (1 cement : 3 coarse cum 0.28 4129.00 1156.12
sand) (Rate as per item No 3.8)
2201 Carriage of Bricks 1000 0.565 283.01 159.90
Nos
9999 Sundries & Scaffolding L.S. 13.52 2 27.04
LABOUR
23 Mason (brick layer) 1st class day 0.45 505.17 227.33
24 Mason (brick layer) 2nd class day 0.45 403.67 181.65
18 Coolie day 1.55 350.00 542.50
11 Bhisti day 0.7 350.00 245.00
TOTAL 5364.54 W
Add 1 % Water charges on "W" 53.6454
TOTAL 5418.19 X
Add GST (multiplying factor 0.1405) on "X" 761.26
TOTAL 6179.45 Y
Add 15 % Contractor's profit and overheads on 926.92
"Y"
Total 7106.37 Z
Add Cess @ 1% on "Z" 71.06
Cost for 10 sqm. 7177.43
Cost for 1 sqm. 717.70
Say

6.12.2 cement mortar 1:4 (1 cement : 4


coarse sand)
Details of cost for 10 sqm.
MATERIAL
2602 Common burnt clay F.P.S. (non modular) 1000 0.565 5000 2825.00
bricks class designation 7.5 Cement mortar Nos
1:04
3.9 Cement mortar 1 : 4 (1 cement : 4 coarse cum 0.28 3548.00 993.44
sand) (Rate as per item No 3.9)
2201 Carriage of Bricks 1000 0.565 283.01 159.90
Nos
9999 Sundries & Scaffolding L.S. 13.52 2 27.04
LABOUR
23 Mason (brick layer) 1st class day 0.45 505.17 227.33
24 Mason (brick layer) 2nd class day 0.45 403.67 181.65
18 Coolie day 1.55 350.00 542.50
11 Bhisti day 0.7 350.00 245.00
TOTAL 5201.86 W
Add 1 % Water charges on "W" 52.0186
TOTAL 5253.88 X
Add GST (multiplying factor 0.1405) on "X" 738.17
TOTAL 5992.05 Y
Add 15 % Contractor's profit and overheads on 898.81
"Y"
Total 6890.86 Z
Add Cess @ 1% on "Z" 68.91
Cost for 10 sqm. 6959.77
Cost for 1 sqm. 696.00
Say

6.13 Half brick masonry with common burnt


clay F.P.S. (non modular) bricks of class 2542.5
designation 7.5 in superstructure above
6.13.1 Cement
plinth mortar
level 1:3 (1
up to floor V cement
level. :3
coarse sand)
Details of cost for 10 sqm.
MATERIAL
2602 Common burnt clay F.P.S. (non modular) 1000 0.565 5000 2825.00
bricks class designation 7.5 Cement mortar Nos
1:03
3.8 Rate as per Item Number 3.8 of SH: cum 0.28 4129.00 1156.12
Mortars
2201 Carriage of Bricks 1000 0.565 283.01 159.90
Nos
9999 Sundries & Scaffolding L.S. 13.52 2 27.04
LABOUR
23 Mason (brick layer) 1st class day 0.6 505.17 303.10
24 Mason (brick layer) 2nd class day 0.6 403.67 242.20
18 Coolie day 2 350.00 700.00
11 Bhisti day 0.7 350.00 245.00
Extra labour for lifting materials:
18 Coolie day 1.29 350.00 451.50
10 x 0.115 x 0.75 x 1.5
TOTAL 6109.86 W
Add 1 % Water charges on "W" 61.0986
TOTAL 6170.96 X
Add GST (multiplying factor 0.1405) on "X" 867.02
TOTAL 7037.98 Y
Add 15 % Contractor's profit and overheads on 1055.70
"Y"
Total 8093.68 Z
Add Cess @ 1% on "Z" 80.94
Cost for 10 sqm. 8174.62
Cost for 1 sqm. 817.50
Say

6.13.2 Cement mortar 1:4 (1 cement :4 coarse


sand) of cost for 10 sqm.
Details
MATERIAL
2602 Common burnt clay F.P.S. (non modular) 1000 0.565 5000 2825.00
bricks class designation 7.5 Cement mortar Nos
3.9 Rate as per Item Number 3.9 of SH: cum 0.28 3548.00 993.44
Mortars
2201 Carriage of Bricks 1000 0.565 283.01 159.90
Nos 641.66
9999 Sundries & Scaffolding L.S. 13.52 2 27.04
LABOUR
23 Mason (brick layer) 1st class day 0.60 505.17 303.10
24 Mason (brick layer) 2nd class day 0.60 403.67 242.20
18 Coolie day 2.00 350.00 700.00
11 Bhisti day 0.70 350.00 245.00
Extra labour for lifting materials:
18 Coolie 10 x 0.115 x 0.75 x 1.5 day 1.29 350.00 451.50
TOTAL 6588.84 W
Add 1 % Water charges on "W" 65.8884
TOTAL 6654.73 X
Add GST (multiplying factor 0.1405) on "X" 934.99
TOTAL 7589.72 Y
Add 15 % Contractor's profit and overheads on 1138.46
"Y"
Total 8728.18 Z
Add Cess @ 1% on "Z" 87.28
Cost for 10 sqm. 8815.46
Cost for 1 sqm. 881.50
Say 881.50

6.14 Extra for half brick masonry in


superstructure,
Details above
of cost for 59.83 sqmfloor V level
per four floorsfor
37
every four floors or part thereof by day 0.125 7500 937.50
Mobile crane
mechanical means.
TOTAL 937.50 W
Add 1 % Water charges on "W" 9.375
TOTAL 946.88 X
Add GST (multiplying factor 0.1405) on "X" 133.04
TOTAL 1079.92 Y
Add 15 % Contractor's profit and overheads on 161.99
"Y"
Total 1241.91 Z
Add Cess @ 1% on "Z" 12.42
Cost of 59.83 sqm. 1254.33
Cost for 1 sqm. 21.00
Say 21.00

6.15 Extra for providing and placing in


position 2 Nos 6mm dia. M.S. bars at every
course of half brick masonry.
third
Details of cost for 10sqm.
6mm dia. M.S. bars (round) 2 Nos. @ 30
meter/10sqm. = 60 metre @ 0.22kg/m =
1002 Mild steel round bar 12 mm dia and below quintal 0.132 5500 726.00
2205 Carriage of Steel tonne 0.0132 94.34 1.25
9999 Sundries L.S. 1.82 2 3.64
TOTAL 730.89 W
Add 1 % Water charges on "W" 7.3089
TOTAL 738.20 X
Add GST (multiplying factor 0.1405) on "X" 103.72
TOTAL 841.92 Y
Add 15 % Contractor's profit and overheads on 126.29
"Y"
Total 968.21 Z
Add Cess @ 1% on "Z" 9.68
Cost of 10.00 sqm. 977.89
Cost for 1 sqm. 97.80
Say 97.80

6.16 Tile brick masonry with common


6.16.1 burnt claymortar
Cement F.P.S. 1:4
(non(1modular)
cement : tile
4
bricks of class
coarse sand) designation 10 in
foundation and plinth in:
Details of cost for 1 cum.
MATERIAL
1984 Common burnt clay F.P.S. (non modular) 1000 0.777 4500 3496.50
bricks tile class designation 10 Cement Nos
mortar 1 : 4
3.9 Rate as per Item Number 3.9 of SH: cum 0.4 3548.00 1419.20
Mortars
2207 Carriage of Brick tiles 1000 0.777 169.81 131.94
Nos
9999 Sundries L.S. 4.55 2 9.10
LABOUR
23 Mason (brick layer) 1st class day 0.7 505.17 353.62
24 Mason (brick layer) 2nd class day 0.7 403.67 282.57
18 Coolie day 1.54 350.00 539.00
11 Bhisti day 0.2 350.00 70.00
TOTAL 6301.93 W
Add 1 % Water charges on "W" 63.0193
TOTAL 6364.95 X
Add GST (multiplying factor 0.1405) on "X" 894.28
TOTAL 7259.23 Y
Add 15 % Contractor's profit and overheads on 1088.88
"Y"
Total 8348.11 Z
Add Cess @ 1% on "Z" 83.48
Cost for 1 cum. 8431.59
Say 8431.60
8431.60

6.16.2 Cement mortar 1:6 (1 cement : 6


coarse
Details ofsand)
cost for 1 cum.
MATERIAL
1984 Common burnt clay F.P.S. (non modular) 1000 0.777 4500 3496.50
bricks tile class designation 10 Cement Nos

mortar 1 : 6
3.11 Rate as per Item Number 3.11 of SH: cum 0.4 2967.00 1186.80
Mortars
2207 Carriage of Brick tiles 1000 0.777 169.81 131.94
Nos
9999 Sundries L.S. 4.55 2 9.10
LABOUR
23 Mason (brick layer) 1st class day 0.7 505.17 353.62
24 Mason (brick layer) 2nd class day 0.7 403.67 282.57
18 Coolie day 1.54 350.00 539.00
11 Bhisti day 0.2 350.00 70.00
TOTAL 6069.53 W
Add 1 % Water charges on "W" 60.6953
TOTAL 6130.23 X
Add GST (multiplying factor 0.1405) on "X" 861.30
TOTAL 6991.53 Y
Add 15 % Contractor's profit and overheads on 1048.73
"Y"
Total 8040.26 Z
Add Cess @ 1% on "Z" 80.40
Cost for 1 cum. 8120.66
Say 8120.70
8120.70

6.17 Tile brick masonry with common burnt clay


machine moulded tile bricks of class
cement
designation mortar 1:6 (1 cement
12.5 conforming : 6 coarse
to IS : 2690 (Part I)
sand).
in foundation
Details of costand
for plinth
1 cum.in
MATERIAL
7904 Machine moulded common burnt clay tile 1000 0.777 4900 3807.30
bricks of class designation 12.5 Nos
2207 Carriage of Brick tiles Cement mortar 1 : 6 1000 0.777 169.81 131.94
Nos
3.11 Rate as per Item Number 3.11 of SH: cum 0.4 2967.00 1186.80
Mortars
9999 Sundries L.S. 4.55 2 9.10
LABOUR
23 Mason (brick layer) 1st class day 0.7 505.17 353.62
24 Mason (brick layer) 2nd class day 0.7 403.67 282.57
18 Coolie day 1.54 350.00 539.00
11 Bhisti day 0.2 350.00 70.00
TOTAL 6380.33 W
Add 1 % Water charges on "W" 63.8033
TOTAL 6444.13 X
Add GST (multiplying factor 0.1405) on "X" 905.40
TOTAL 7349.53 Y
Add 15 % Contractor's profit and overheads on 1102.43
"Y"
Total 8451.96 Z
Add Cess @ 1% on "Z" 84.52
Cost for 1 cum. 8536.48
Say 8536.50
8536.50

6.18 Tile brick masonry with common burnt


clay F.P.S. (non modular) tile bricks of class
mortar
designation1:610(1incement : 6 coarse
superstructure abovesand).
plinth
level upof
Details tocost
floorfor
V level
1 cum.in cement

MATERIAL
1984 Common burnt clay F.P.S. (non modular) 1000 0.777 4500 3496.50
bricks tile class designation 10 Nos
2207 Carriage of Brick tiles Cement mortar 1 : 6 1000 0.777 169.81 131.94
Nos
3.11 Rate as per Item Number 3.11 of SH: cum 0.4 2967.00 1186.80
Mortars
9999 Sundries L.S. 4.55 2 9.10
LABOUR
23 Mason (brick layer) 1st class day 0.9 505.17 454.65
24 Mason (brick layer) 2nd class day 0.9 403.67 363.30
18 Coolie day 1.8 350.00 630.00
11 Bhisti day 0.2 350.00 70.00
Extra labour for lifting of materials
18 Coolie day 1.13 350.00 395.50
9999 Scaffolding L.S. 33.8 2 67.60
TOTAL 6805.39 W
Add 1 % Water charges on "W" 68.0539
TOTAL 6873.44 X
Add GST (multiplying factor 0.1405) on "X" 965.72
TOTAL 7839.16 Y
Add 15 % Contractor's profit and overheads on 1175.87
"Y"
Total 9015.03 Z
Add Cess @ 1% on "Z" 90.15
Cost for 1 cum. 9105.18
Say 9105.20
9105.20

6.20 Tile brick masonry with common burnt clay


F.P.S. (non modular) tile bricks of class
shuttering
designation 10complete.
in plain arch work in
superstructure above
Details of cost for plinth and upto floor five
1 cum.
MATERIAL
1984 Common burnt clay F.P.S. (non modular) 1000 0.777 4500 3496.50
bricks tile class designation 10 Nos
2207 Carriage of Brick tiles Cement mortar 1 : 4 1000 0.777 169.81 131.94
Nos
3.9 Rate as per Item Number 3.9 of SH: cum 0.35 3548.00 1241.80
Mortars
9999 Sundries L.S. 5.46 2 10.92
Centering and shuttering, area same as in
item no. 6.9
5.9.9 Rate as per item no 5.9.9 of sqm 2.25 1255.80 2825.55 A
SH : Reinforced cement concrete work
9999 Scaffolding L.S. 18.85 2 37.70
LABOUR
23 Mason (brick layer) 1st class day 0.79 505.17 399.08
24 Mason (brick layer) 2nd class day 0.79 403.67 318.90
18 Coolie day 3.21 350.00 1123.50
11 Bhisti day 0.2 350.00 70.00
Extra labour for lifting of material (above
floor two level up to floor five level)
18 Coolie day 1.13 350.00 395.50
TOTAL 10051.39 W
Add 1 % Water charges on "W-A" 7225.84 72.2584
TOTAL X
Add GST (multiplying factor 0.1405) on "X- 7298.10 1025.38
A" Y
TOTAL 8323.48 1248.52
Add 15 % Contractor's profit and overheads
8225.51
on "Y-A" Z
Total 9572.00 95.72
Add Cess @ 1% on "Z-A" 12493.27
Cost for 1 cum. 12493.27
Say 12493.30
6.21 Tile brick masonry with common burnt clay
F.P.S. (non modular) tile bricks of class
shuttering
designation 10complete.
in gauged arch work in
superstructure above
Details of cost for plinth and upto floor five
1 cum.
MATERIAL
1984 Common burnt clay F.P.S. (non modular) 1000 0.791 4500 3559.50
bricks tile class designation 10 Nos
2207 Carriage of Brick tiles Cement mortar 1 : 4 1000 0.791 169.81 134.32
Nos
3.9 Rate as per Item Number 3.9 of SH: cum 0.35 3548.00 1241.80
Mortars
9999 Sundries and shuttering L.S. 5.46 2 10.92
Centering and shuttering, area same as in
item no. 6.9
5.9.9 Rate as per item no 5.9.9 of sqm 2.25 1190.75 2679.19 A
SH : Reinforced cement concrete work
9999 Scaffolding L.S. 18.85 2 37.70
LABOUR
23 Mason (brick layer) 1st class day 1.5 505.17 757.76
24 Mason (brick layer) 2nd class day 1.5 403.67 605.51
18 Coolie day 5.33 350.00 1865.50
11 Bhisti day 0.2 350.00 70.00
Extra labour for lifting of material (above
floor two level up to floor five level)
18 Coolie day 1.13 350.00 395.50
TOTAL 11357.70 W
Add 1 % Water charges on "W-A" 8678.51 86.7851
TOTAL X
Add GSTmultiplying factor 0.1405) on "X-A" 8765.30 1231.52
TOTAL Y
Add 15 % Contractor's profit and overheads 9996.82 1499.52
on "Y-A"
Add Cess @ 1% on "Z-A" Z
Cost for 1 cum. 11496.34 114.96
Cost for 1 cum. 14290.49
Say 14290.49
14290.50

6.22 Tile brick masonry work 5 cm thick with


common burnt
Details of cost forclay F.P.S. (non modular)
10 sqm.
tile bricks of class designation 10 in
1984 Common burnt clay
cement mortar 1:3F.P.S. (non modular)
(1 cement : 3 coarse 1000 0.377 4500 1696.50
bricks tile class designation 10 Nos
2207 Carriage of Brick tiles Cement mortar 1:3 1000 0.377 169.81 64.02
Nos
3.8 Rate as per Item Number 3.8 of SH: cum 0.15 4129.00 619.35
Mortars
9999 Sundries and scaffolding L.S. 8.06 2 16.12
LABOUR
23 Mason (brick layer) 1st class day 0.94 505.17 474.86
24 Mason (brick layer) 2nd class day 0.94 403.67 379.45
18 Coolie day 1.88 350.00 658.00
11 Bhisti day 0.33 350.00 115.50
Extra labour for lifting of material (above
floor two level up to floor five level)
18 Coolie day 1.29 350.00 451.50
TOTAL 4475.30 W
Add 1 % Water charges on "W" 44.753
TOTAL 4520.05 X
Add GST (multiplying factor 0.1405) on "X" 635.07
TOTAL 5155.12 Y
Add 15 % Contractor's profit and overheads on 773.27
"Y"
Total 5928.39 Z
Add Cess @ 1% on "Z" 59.28
Cost for 10 cum. 5987.67
Cost per sqm. 5987.70
Say 5987.70

6.23 Honey-comb brick work 10 / 11.4 cm thick


with common burnt clay bricks of class
cement mortar
designation 1:4 (1structure
7.5 in super cementabove
: 4 coarse
plinth
sand).
level upto
Details floorfor
of cost V level
1sqm.with
of Honey comb
brick works-
MATERIAL
Brick work, with bricks of class designation 75, in
cement mortar 1:4 (1 Cement :

4 Coarse sand) in superstructure


1 m x 1 x 0.143 m x 4.5/7.5 = 0.069 cum
6.4.1 Rate as per item No 6.4.1 of SH :- Brick cum 0.069 6782.87 468.02 A
work.
9999 Extra for delay due to fine work L.S. 20.67 2 41.34
TOTAL 509.36 W
Add 1 % Water charges on "W-A" 41.34 0.4134
TOTAL X
Add GST (multiplying factor 0.1405) on "X-A" 41.75 5.87
TOTAL Y
Add 15 % Contractor's profit and overheads 47.62 7.14
on "Y-A" Total
Z
Add Cess @ 1% on "Z-A" 54.76 0.55
523.33
Cost for 1 sqm. 523.33
Say 523.30

6.24 Extra for laying brick work in or under


water
NOTE :- and/or liquid mud
The quantity including
will be calculatedcost
by
of pumping
multiplying or
the bailing
depth out water
measured and
from
Details of cost for depth of water 0.30m sub -
removing
soil slush
water level upetc. complete.
to the centre of gravity
depth.
of brick work under sub - soil water with
Quantity of concrete = 14 cum.

pumping hours = 3 hrs. on 0.375 day.


11 Hire charges of Pumpset of capacity 4000 day 0.375 700 262.50
litres/hour.
17 Beldar day 4 350.00 1400.00
TOTAL 1662.50 W
Add 1 % Water charges on "W" 16.625
TOTAL 1679.13 X
Add GST (multiplying factor 0.1405) on "X" 235.92
TOTAL 1915.05 Y
Add 15 % Contractor's profit and overheads on 287.26
"Y"
Total 2202.31 Z
Add Cess @ 1% on "Z" 22.02
Cost of 14cum. per 0.30m depth 2224.33
Cost of cum. per m depth 529.60
Say 529.60

6.25 Extra for laying brick work in or


under foul
Details of position.
cost for 1 cum.
Extra labour due to slow progress-
23 Mason (brick layer) 1st class day 0.02 505.17 10.10
24 Mason (brick layer) 2nd class day 0.02 403.67 8.07
17 Beldar day 0.25 350.00 87.50
18 Coolie day 0.15 350.00 52.50
TOTAL 158.17 W
Add 1 % Water charges on "W" 1.5817
TOTAL 159.75 X
Add GST (multiplying factor 0.1405) on "X" 22.45
TOTAL 182.20 Y
Add 15 % Contractor's profit and overheads on 27.33
"Y"
Total 209.53 Z
Add Cess @ 1% on "Z" 2.10
Cost for 1 cum. 211.63
Say 211.60
211.60

6.26 Brick work with common burnt clay


6.26.1 selected
From groundF.P.S.level
(nonupto
modular)
plinthbricks
level of
class designation 7.5
Details of cost for 1 cum.
in exposed brick
work including making horizontal and
2602 Common burnt clay F.P.S. (non modular) 1000 0.494 5000 2470.00
bricks class designation 7.5 Nos
2201 Carriage of Bricks 1000 0.494 283.01 139.81
Cement mortar 1 : 6 Nos
3.11 Rate as per Item Number 3.11 of SH: cum 0.25 2967.00 741.75
Mortars
9999 Sundries including steel/wooden strips for L.S. 16.38 2 32.76
making grooves.
LABOUR
For selection of bricks
17 Beldar day 0.5 350.00 175.00
23 Mason (brick layer) 1st class day 0.35 505.17 176.81
24 Mason (brick layer) 2nd class day 0.35 403.67 141.28
18 Coolie day 1.07 350.00 374.50
11 Bhisti day 0.2 350.00 70.00
TOTAL 4321.91 W
Add 1 % Water charges on "W" 43.2191
TOTAL 4365.13 X
613.30
Add GST (multiplying factor 0.1405) on "X" 4978.43 Y
TOTAL 746.76
Add 15 % Contractor's profit and overheads on 5725.19 Z
"Y"
Total 57.25
Add Cess @ 1% on "Z" 5782.44
Cost for 1 cum. 5782.40
Say 5782.40
6.26.2 Above plinth level upto floor V level
Details of cost for 1 cum.
MATERIAL
2602 Common burnt clay F.P.S. (non modular) 1000 0.494 5000 2470.00
bricks class designation 7.5 Nos
2201 Carriage of Bricks 1000 0.494 283.01 139.81
Cement mortar 1 : 6 Nos

3.11 Rate as per Item Number 3.11 of SH: cum 0.25 2967.00 741.75
Mortars
9999 Sundries including steel/wooden strips for L.S. 16.38 2 32.76
making grooves.
LABOUR
For selection of bricks
17 Beldar day 0.5 350.00 175.00
23 Mason (brick layer) 1st class day 0.46 505.17 232.38
24 Mason (brick layer) 2nd class day 0.46 403.67 185.69
18 Coolie day 1.6 350.00 560.00
11 Bhisti day 0.2 350.00 70.00
Extra labour for lifting of material (above
floor two level up to floor five level)
18 Coolie day 1.13 350.00 395.50
9999 Sundries L.S. 22.36 2 44.72
TOTAL 5047.61 W
Add 1 % Water charges on "W" 50.4761
TOTAL 5098.09 X
Add GST (multiplying factor 0.1405) on "X" 716.28
TOTAL 5814.37 Y
Add 15 % Contractor's profit and overheads on 872.15
"Y"
Total 6686.52 Z
Add Cess @ 1% on "Z" 66.87
Cost for 1 cum. 6753.39
Say 6753.40
6753.40

6.27 Brick work with common burnt clay


modular
6.27.1 Frombricks of class
ground designation
level 7.5 in
upto plinth
exposed
level brick work including making
Details of cost
horizontal andforvertical
1 cum. grooves 10mm wide
MATERIAL
7900 Modular common burnt clay bricks of class 1000 0.487 4000 1948
designation 7.5 2201 Carriage of Bricks Nos
Cement mortar 1 : 6 1000 0.487 283.01 137.83
Nos
3.11 Rate as per Item Number 3.11 of SH: cum 0.22 2967.00 652.74
Mortars
9999 Sundries i/c steel / wooden strips for L.S. 16.38 2 32.76
making grooves
LABOUR
23 Mason (brick layer) 1st class day 0.33 505.17 166.71
24 Mason (brick layer) 2nd class day 0.33 403.67 133.21
18 Coolie day 1 350.00 350.00
11 Bhisti day 0.18 350.00 63.00
TOTAL 3484.25 W
Add 1 % Water charges on "W" 34.8425
TOTAL 3519.09 X
Add GST (multiplying factor 0.1405) on "X" 494.43
TOTAL 4013.52 Y
Add 15 % Contractor's profit and overheads on 602.03
"Y"
Total 4615.55 Z
Add Cess @ 1% on "Z" 46.16
Cost for 1 cum. 4661.71
Say 4661.70
4661.70

6.27.2 Above plinth level upto floor V level


Details of cost for 1 cum.
MATERIAL
7900 Modular common burnt clay bricks of class 1000 0.487 4000 1948.00
designation 7.5 Nos
2201 Carriage of Bricks 1000 0.487 283.01 137.83
Cement mortar 1 : 6 (1 cement : 6 coarse Nos
sand)
3.11 Rate as per Item Number 3.11 of SH: cum 0.22 2967.00 652.74
Mortars
9999 Sundries i/c steel / wooden strips for L.S. 16.38 2 32.76
making grooves
LABOUR
23 Mason (brick layer) 1st class day 0.44 505.17 222.27
24 Mason (brick layer) 2nd class day 0.44 403.67 177.61
18 Coolie day 1.43 350.00 500.50
11 Bhisti day 0.18 350.00 63.00
Extra labour for lifting of material (above
floor two level up to floor five level)
18 Coolie day 1.13 350.00 395.50
9999 Sundries L.S. 22.36 2 44.72
TOTAL 4174.93 W
Add 1 % Water charges on "W" 41.7493
TOTAL 4216.68 X
Add GST (multiplying factor 0.1405) on "X" 592.44
TOTAL 4809.12 Y
Add 15 % Contractor's profit and overheads on 721.37
"Y"
Total 5530.49 Z
Add Cess @ 1% on "Z" 55.30
Cost for 1 cum. 5585.79
Say 5585.80
5585.80

6.28 Brick work with common burnt clay machine


moulded modular bricks of class designation
coarse sand).brick work including making
12.5 in exposed
6.28.1 horizontal
From groundandlevel
vertical
uptogrooves 10 mm wide 12
plinth level
Details of cost for 1 cum.
1986 Common burnt clay modular bricks class 1000 0.487 5000 2435.00
designation 12.5 Nos
2201 Carriage of Bricks 1000 0.487 283.01 137.83
Cement mortar 1 : 6 (1 cement : 6 coarse Nos
sand)
3.11 Rate as per Item Number 3.11 of SH: cum 0.22 2967.00 652.74
Mortars
9999 Sundries including steel/wooden strips for L.S. 16.38 2 32.76
making grooves.
LABOUR
23 Mason (brick layer) 1st class day 0.33 505.17 166.71
24 Mason (brick layer) 2nd class day 0.33 403.67 133.21
18 Coolie day 1 350.00 350.00
11 Bhisti day 0.18 350.00 63.00
TOTAL 3971.25 W
Add 1 % Water charges on "W" 39.7125
TOTAL 4010.96 X
Add GST (multiplying factor 0.1405) on "X" 563.54
TOTAL 4574.50 Y
Add 15 % Contractor's profit and overheads on 686.18
"Y"
Total 5260.68 Z
Add Cess @ 1% on "Z" 52.61
Cost for 1 cum. 5313.29
Say 5313.30
5313.30

6.28.2 Above plinth level upto floor V level


Details of cost for 1 cum.
MATERIAL
1986 Common burnt clay modular bricks class 1000 0.487 5000 2435.00
designation 12.5 Nos
2201 Carriage of Bricks 1000 0.487 283.01 137.83
Cement mortar 1 : 6 (1 cement : 6 coarse Nos
sand)
3.11 Rate as per Item Number 3.11 of SH: cum 0.22 2967.00 652.74
9999 Sundries including steel/wooden strips for L.S. 16.38 2 32.76
making grooves.
LABOUR
23 Mason (brick layer) 1st class day 0.44 505.17 222.27
24 Mason (brick layer) 2nd class day 0.44 403.67 177.61
18 Coolie day 1.43 350.00 500.50
11 Bhisti day 0.18 350.00 63.00
Extra labour for lifting of material (above
floor two level up to floor five level)
18 Coolie day 1.13 350.00 395.50
9999 Sundries L.S. 22.36 2 44.72
TOTAL 4661.93 W
Add 1 % Water charges on "W" 46.6193
TOTAL 4708.55 X
Add GST (multiplying factor 0.1405) on "X" 661.55
TOTAL 5370.10 Y
Add 15 % Contractor's profit and overheads on 805.51
"Y"
Total 6175.61 Z
Add Cess @ 1% on "Z" 61.76
Cost for 1 cum. 6237.37
Say 6237.40
6237.40
6.29 Brick work with common burnt clay
6.29.1 machine
From groundmouldedlevelF.P.S.
upto (non
plinthmodular)
level
bricks of class designation
Details of cost for 1 cum.
12.5 in
exposed brick work including making
MATERIAL
7903 Machine moulded common burnt clay FPS 1000 0.494 5000 2470.00
(non modular) bricks of class designation Nos

12.5
2201 Carriage of Bricks 1000 0.494 283.01 139.81
Cement mortar 1 : 6 (1 cement : 6 coarse Nos
sand)
3.11 Rate as per Item Number 3.11 of SH: cum 0.25 2967.00 741.75
Mortars
9999 Sundries i/c steel / wooden strips for L.S. 16.38 2 32.76
making grooves
LABOUR
23 Mason (brick layer) 1st class day 0.36 505.17 181.86
24 Mason (brick layer) 2nd class day 0.36 403.67 145.32
18 Coolie day 1.37 350.00 479.50
11 Bhisti day 0.2 350.00 70.00
TOTAL 4261.00 W
Add 1 % Water charges on "W" 42.61
TOTAL 4303.61 X
Add GST (multiplying factor 0.1405) on "X" 604.66
TOTAL 4908.27 Y
Add 15 % Contractor's profit and overheads on 736.24
"Y"
Total 5644.51 Z
Add Cess @ 1% on "Z" 56.45
Cost for 1 cum. 5700.96
Say 5701.00
5701.00

6.29.2 Above plinth level upto floor V level


Details of cost for 1 cum.
MATERIAL
7903 Machine moulded common burnt clay FPS 1000 0.494 5000 2470.00
(non modular) bricks of class designation Nos
12.5
2201 Carriage of Bricks 1000 0.494 283.01 139.81
Cement mortar 1 : 6 (1 cement : 6 coarse Nos
sand)
3.11 Rate as per Item Number 3.11 of SH: cum 0.25 2967.00 741.75
Mortars
9999 Sundries i/c steel / wooden strips for L.S. 16.38 2 32.76
making grooves
LABOUR
23 Mason (brick layer) 1st class day 0.44 505.17 222.27
24 Mason (brick layer) 2nd class day 0.44 403.67 177.61
18 Coolie day 1.8 350.00 630.00
11 Bhisti day 0.2 350.00 70.00
Extra labour for lifting of material (above
floor two level up to floor five level)
18 Coolie day 1.13 350.00 395.50
9999 Sundries L.S. 22.36 2 44.72
TOTAL 4924.42 W
Add 1 % Water charges on "W" 49.2442
TOTAL 4973.66 X
Add GST (multiplying factor 0.1405) on "X" 698.80
TOTAL 5672.46 Y
Add 15 % Contractor's profit and overheads on 850.87
"Y"
Total 6523.33 Z
Add Cess @ 1% on "Z" 65.23
Cost for 1 cum. 6588.56
Say 6588.60
6588.60

6.30 Brick work with common burnt clay


machine moulded perforated F.P.S. (non
6.30.1 From ground level upto plinth
modular) bricks of class designation 12.5
level
Details of costISfor
conforming 1 cum.
: 2222 in exposed brick
MATERIAL
7901 Machine moulded perforated common burnt clay FPS 1000 0.494 4700 2321.80
(non modular) bricks of class
Nos
designation 12.5 2201 Carriage of Bricks 1000 0.494 283.01 139.81
Nos
Cement mortar 1 : 6 (1 cement : 6 coarse sand)
3.11 Rate as per Item Number 3.11 of SH: cum 0.25 2967.00 741.75
Mortars
9999 Sundries i/c steel / wooden strips for L.S. 16.38 2 32.76
making grooves
LABOUR
23 Mason (brick layer) 1st class day 0.36 505.17 181.86
24 Mason (brick layer) 2nd class day 0.36 403.67 145.32
18 Coolie day 1.37 350.00 479.50
11 Bhisti day 0.2 350.00 70.00
TOTAL 4112.80 W
Add 1 % Water charges on "W" 41.128
TOTAL 4153.93 X
Add GST (multiplying factor 0.1405) on "X" 583.63
TOTAL 4737.56 Y
Add 15 % Contractor's profit and overheads on 710.63
"Y"
Total 5448.19 Z
Add Cess @ 1% on "Z" 54.48
Cost for 1 cum. 5502.67
Say 5502.70
5502.70

6.30.2 Above plinth level upto floor V level


Details of cost for 1 cum.
MATERIAL
7901 Machine moulded perforated common burnt 1000 0.494 4700 2321.80
clay FPS (non modular) bricks of class Nos
designation 12.5
2201 Carriage of Bricks 1000 0.494 283.01 139.81
Cement mortar 1 : 6 (1 cement : 6 coarse Nos
sand)
3.11 Rate as per Item Number 3.11 of SH: cum 0.25 2967.00 741.75
Mortars
9999 Sundries i/c steel / wooden strips for L.S. 16.38 2 32.76
making grooves
LABOUR
23 Mason (brick layer) 1st class day 0.47 505.17 237.43
24 Mason (brick layer) 2nd class day 0.47 403.67 189.72
18 Coolie day 1.8 350.00 630.00
11 Bhisti day 0.2 350.00 70.00
Extra labour for lifting of material (above
floor two level up to floor five level)
18 Coolie day 1.13 350.00 395.50
9999 Sundries L.S. 22.36 2 44.72
TOTAL 4803.49 W
Add 1 % Water charges on "W" 48.0349
TOTAL 4851.52 X
Add GST (multiplying factor 0.1405) on "X" 681.64
TOTAL 5533.16 Y
Add 15 % Contractor's profit and overheads on 829.97
"Y"
Total 6363.13 Z
Add Cess @ 1% on "Z" 63.63
Cost for 1 cum. 6426.76
Say 6426.80
6426.80

6.31 Brick work with common burnt clay machine


moulded perforated modular bricks of class
cement mortar
designation 1:6 (1 cement
12.5 conforming : 6 coarse
to IS : 2222 in
sand).
exposed 6.31.1
brick From
work ground
including
Details of cost for 1 cum. level
making upto
plinth level
MATERIAL
7902 Machine moulded common burnt clay 1000 0.487 5200 2532.40
modular perforated bricks of class Nos
designation 12.5
2201 Carriage of Bricks 1000 0.487 283.01 137.83
Cement mortar 1 : 6 (1 cement : 6 coarse Nos
sand)
3.11 Cement mortar 1 : 6 (1 cement : cum 0.22 2967.00 652.74
6 coarse sand) (Rate as per item No 3.11)
9999 Sundries i/c steel / wooden strips for L.S. 16.38 2 32.76
making grooves
LABOUR
23 Mason (brick layer) 1st class day 0.33 505.17 166.71
24 Mason (brick layer) 2nd class day 0.33 403.67 133.21
18 Coolie day 1 350.00 350.00
11 Bhisti day 0.18 350.00 63.00
TOTAL 4068.65 W
Add 1 % Water charges on "W" 40.6865
TOTAL 4109.34 X
Add GST (multiplying factor 0.1405) on "X" 577.36
TOTAL 4686.70 Y
Add 15 % Contractor's profit and overheads on 703.00
"Y"
Total 5389.70 Z
Add Cess @ 1% on "Z" 53.90
Cost for 1 cum. 5443.60
Say 5443.60
5443.60

6.31.2 Above plinth level upto floor V level


Details of cost for 1 cum.
MATERIAL
7902 Machine moulded common burnt clay 1000 0.487 5200 2532.40
modular perforated bricks of class Nos
designation 12.5
2201 Carriage of Bricks 1000 0.487 283.01 137.83
Cement mortar 1 : 6 (1 cement : 6 coarse Nos
sand)
3.11 Rate as per Item Number 3.11 of SH: cum 0.22 2967.00 652.74
Mortars
9999 Sundries i/c steel / wooden strips for L.S. 16.38 2 32.76
making grooves
LABOUR
23 Mason (brick layer) 1st class day 0.44 505.17 222.27
24 Mason (brick layer) 2nd class day 0.44 403.67 177.61
18 Coolie day 1.43 350.00 500.50
11 Bhisti day 0.18 350.00 63.00
Extra labour for lifting of material (above
floor two level up to floor five level)
18 Coolie day 1.13 350.00 395.50
9999 Sundries L.S. 22.36 2 44.72
TOTAL 4759.33 W
Add 1 % Water charges on "W" 47.5933
TOTAL 4806.92 X
Add GST (multiplying factor 0.1405) on "X" 675.37
TOTAL 5482.29 Y
Add 15 % Contractor's profit and overheads on 822.34
"Y"
Total 6304.63 Z
Add Cess @ 1% on "Z" 63.05
Cost for 1 cum. 6367.68
Say 6367.70
6367.70

6.32 Brick work with clay flyash F.P.S. (non


modular) brick of class designation 7.5 in
6.32.1 Cement mortar 1:4 (1 cement : 4
superstructure above plinth level up to
coarse
Details ofsand)
floor five cost
levelfor
in1: cum.
MATERIAL
7008 F.P.S.(non modular) clay fly ash bricks 1000 0.494 4800 2371.20
class designation 7.5 Nos
Cement mortar 1 : 4 (1 cement : 4 coarse
sand)
3.9 Rate as per Item Number 3.9 of SH: cum 0.25 3548.00 887.00
Mortars
2201 Carriage of Bricks 1000 0.494 283.01 139.81
Nos
9999 Sundries L.S. 2.73 2 5.46
LABOUR
23 Mason (brick layer) 1st class day 0.47 505.17 237.43
24 Mason (brick layer) 2nd class day 0.47 403.67 189.72
18 Coolie day 1.8 350.00 630.00
11 Bhisti day 0.2 350.00 70.00
9999 Scaffolding L.S. 8.97 2 17.94
Extra labour element required for lifting of
materials above floor two level upto floor
V level (0.75 x 1.5 = 1.13)
18 Coolie day 1.13 350.00 395.50
TOTAL 4944.06 W
Add 1 % Water charges on "W" 49.4406
TOTAL 4993.50 X
Add GST (multiplying factor 0.1405) on "X" 701.59
TOTAL 5695.09 Y
Add 15 % Contractor's profit and overheads on 854.26
"Y"
Total 6549.35 Z
Add Cess @ 1% on "Z" 65.49
Cost for 1 cum. 6614.84
Say 6614.80
6614.80

6.32.2 Cement mortar 1:6 (1 cement : 6


coarse
Details ofsand)
cost for 1 cum.
MATERIAL
7008 F.P.S.(non modular) clay fly ash bricks 1000 0.494 4800 2371.20
class designation 7.5 Nos
Cement mortar 1 : 6 (1 cement : 6 coarse
sand)
3.11 Rate as per Item Number 3.11 of SH: cum 0.25 2967.00 741.75
Mortars
2201 Carriage of Bricks 1000 0.494 283.01 139.81
Nos
9999 Sundries L.S. 2.73 2 5.46
LABOUR
23 Mason (brick layer) 1st class day 0.47 505.17 237.43
24 Mason (brick layer) 2nd class day 0.47 403.67 189.72
18 Coolie day 1.8 350.00 630.00
11 Bhisti day 0.2 350.00 70.00
9999 Scaffolding L.S. 8.97 2 17.94
Extra labour element required for lifting of
materials above floor two level upto floor V
level (0.75 x 1.5 = 1.13)
18 Coolie day 1.13 350.00 395.50
TOTAL 4798.81 W
Add 1 % Water charges on "W" 47.9881
TOTAL 4846.80 X
Add GST (multiplying factor 0.1405) on "X" 680.98
TOTAL 5527.78 Y
Add 15 % Contractor's profit and overheads on 829.17
"Y"
Total 6356.95 Z
Add Cess @ 1% on "Z" 63.57
Cost for 1 cum. 6420.52
Say 6420.50
6420.50
6.34 Brick work with non modular fly ash bricks
conforming to IS:12894, class designation 10
average compressive strength in super
structure above plinth level

6.34.1 Cement mortar 1:4 (1 cement : 4


coarse
Details ofsand)
cost for 1 cum.
MATERIAL
7737 Fly ash bricks conforming to I.S. 12894 1000 0.487 4300 2094.10
Cement mortar 1 : 4 (1 cement : 4 coarse Nos
sand)
3.9 Rate as per Item Number 3.9 of SH: cum 0.22 3548.00 780.56
Mortars
2201 Carriage of Bricks 1000 0.487 283.01 137.83
Nos
9999 Sundries L.S. 2.73 2 5.46
LABOUR
23 Mason (brick layer) 1st class day 0.47 505.17 237.43
24 Mason (brick layer) 2nd class day 0.47 403.67 189.72
18 Coolie day 1.8 350.00 630.00
11 Bhisti day 0.2 350.00 70.00
9999 Scaffolding L.S. 22.36 2 44.72
Extra labour element required for lifting of
materials above floor two level upto floor V
level (0.75 x 1.5 = 1.13)
18 Coolie day 1.13 350.00 395.50
TOTAL 4585.32 W
Add 1 % Water charges on "W" 45.8532
TOTAL 4631.17 X
Add GST (multiplying factor 0.1405) on "X" 650.68
TOTAL 5281.85 Y
Add 15 % Contractor's profit and overheads on 792.28
"Y"
Total 6074.13 Z
Add Cess @ 1% on "Z" 60.74
Cost for 1 cum. 6134.87
Say 6134.90
6134.90

6.34.2 Cement mortar 1:6 (1 cement : 6


Coarseofsand)
Details cost for 1 cum.
MATERIAL
7737 Fly ash bricks conforming to I.S. 12894 1000 0.487 4300 2094.10
Cement mortar 1 : 6 (1 cement : 6 coarse Nos
sand)
3.11 Rate as per Item Number 3.11 of SH: cum 0.22 2967.00 652.74
Mortars
2201 Carriage of Bricks 1000 0.487 283.01 137.83
Nos
9999 Sundries L.S. 2.73 2 5.46
LABOUR
23 Mason (brick layer) 1st class day 0.47 505.17 237.43
24 Mason (brick layer) 2nd class day 0.47 403.67 189.72
18 Coolie day 1.8 350.00 630.00
11 Bhisti day 0.2 350.00 70.00
9999 Scaffolding L.S. 22.36 2 44.72
Extra labour element required for lifting of
materials above floor two level upto floor V
level (0.75 x 1.5 = 1.13)
18 Coolie day 1.13 350.00 395.50
TOTAL 4457.50 W
Add 1 % Water charges on "W" 44.575
TOTAL 4502.08 X
Add GST (multiplying factor 0.1405) on "X" 632.54
TOTAL 5134.62 Y
Add 15 % Contractor's profit and overheads on 770.19
"Y"
Total 5904.81 Z
Add Cess @ 1% on "Z" 59.05
Cost for 1 cum. 5963.86
Say 5963.90
5963.90

6.35 Brick work with modular calcium


silicate
6.35.1 bricks
Cement machine moulded
mortar 1:4 (1 cement :
conforming
4 coarse
Details
to
sand)
of cost
IS:4139,
for 1 cum.
class
designation 10 average compressive
MATERIAL
7738 Calcium Silicate Bricks machine moulded 1000 0.487 5400 2629.80
confirming to I.S. 4139 - 1989 Nos
Cement mortar 1 : 4 (1 cement : 4 coarse
sand)
3.9 Rate as per Item Number 3.9 of SH: cum 0.22 3548.00 780.56
Mortars
2201 Carriage of Bricks 1000 0.487 283.01 137.83
Nos
9999 Sundries L.S. 2.73 2 5.46
LABOUR
23 Mason (brick layer) 1st class day 0.47 505.17 237.43
24 Mason (brick layer) 2nd class day 0.47 403.67 189.72
18 Coolie day 1.8 350.00 630.00
11 Bhisti day 0.2 350.00 70.00
9999 Scaffolding L.S. 22.36 2 44.72
Extra labour element required for lifting of
materials above floor two level upto floor V
level (0.75 x 1.5 = 1.13)
18 Coolie day 1.13 350.00 395.50
TOTAL 5121.02 W
Add 1 % Water charges on "W" 51.2102
TOTAL 5172.23 X
Add GST (multiplying factor 0.1405) on "X" 726.70
TOTAL 5898.93 Y
Add 15 % Contractor's profit and overheads on 884.84
"Y"
Total 6783.77 Z
Add Cess @ 1% on "Z" 67.84
Cost for 1 cum. 6851.61
Say 6851.60
6851.60

6.35.2 Cement mortar 1:6 (1 cement : 6


Coarse
Details ofsand)
cost for 1 cum.
MATERIAL

7738 Calcium Silicate Bricks machine moulded 1000 0.487 5400 2629.80
confirming to I.S. 4139 - 1989
Nos
Cement mortar 1 : 6 (1 cement : 6 coarse sand) cum 0.22 3160.6 695.33

3.11 Rate as per Item Number 3.11 of SH:


Mortars
2201 Carriage of Bricks 1000 0.487 283.01 137.83
Nos
9999 Sundries L.S. 2.73 2 5.46
LABOUR 0
23 Mason (brick layer) 1st class day 0.47 505.17 237.43
24 Mason (brick layer) 2nd class day 0.47 403.67 189.72
18 Coolie day 1.8 350.00 630.00
11 Bhisti day 0.2 350.00 70.00
9999 Scaffolding L.S. 22.36 2 44.72
Extra labour element required for lifting of
materials above floor two level upto floor V
level (0.75 x 1.5 = 1.13)
18 Coolie day 1.13 350.00 395.50
TOTAL 5035.79 W
Add 1 % Water charges on "W" 50.3579
TOTAL 5086.15 X
Add GST (multiplying factor 0.1405) on "X" 714.60
TOTAL 5800.75 Y
Add 15 % Contractor's profit and overheads on 870.11
"Y"
Total 6670.86 Z
Add Cess @ 1% on "Z" 66.71
Cost for 1 cum. 6737.57
Say 6737.60
6737.60

6.36 Brick work with modular extruded


6.36.1 brunt
Cement fly ash clay1:4
Mortar sewer bricks : 4
( 1 cement
(Conforming
coarseofsand)
Details
to IS: 4885
cost for 1 cum.
) in foundation
and plinth :
MATERIAL
7736 Extruded burnt flyash clay sewer bricks 1000 0.487 5400 2629.80
conforming to I.S 4885 - 1988 Nos
Cement mortar 1 : 4 (1 cement : 4 coarse
sand)
3.9 Rate as per Item Number 3.9 of SH: cum 0.22 3548.00 780.56
Mortars
2201 Carriage of Bricks 1000 0.487 283.01 137.83
Nos
9999 Sundries L.S. 2.73 2 5.46
LABOUR
23 Mason (brick layer) 1st class day 0.33 505.17 166.71
24 Mason (brick layer) 2nd class day 0.33 403.67 133.21
18 Coolie day 1 350.00 350.00
11 Bhisti day 0.18 350.00 63.00
TOTAL 4266.57 W
Add 1 % Water charges on "W" 42.6657
TOTAL 4309.24 X
Add GST (multiplying factor 0.1405) on "X" 605.45
TOTAL 4914.69 Y
Add 15 % Contractor's profit and overheads on 737.20
"Y"
Total 5651.89 Z
Add Cess @ 1% on "Z" 56.52
Cost for 1 cum. 5708.41
Say 5708.40
5708.40

6.37 Brick work with modular


extruded
Details brunt
of cost for 1fly ash clay sewer
cum.
bricks (conforming to IS : 4885) in
arches in foundation and plinth in
MATERIAL
7736 Extruded burnt flyash clay sewer bricks 1000 0.487 5400 2629.80
conforming to I.S 4885 - 1988 Nos
Cement Mortar 1:3 (1 cement : 3 fine sand).
3.3 Rate as per item no 3.3 SH Mortar cum 0.25 3670.3 917.58
2201 Carriage of Bricks 1000 0.487 283.01 137.83
Nos
9999 Sundries L.S. 2.73 2 5.46
Centering and shuttering
5.9.9 Rate as per item no 5.9.9 of sqm 2.25 1255.80 2825.55 A
SH : Reinforced cement concrete work
LABOUR
23 Mason (brick layer) 1st class day 0.42 505.17 212.17
24 Mason (brick layer) 2nd class day 0.42 403.67 169.54
18 Coolie day 1.86 350.00 651.00
11 Bhisti day 0.2 350.00 70.00
TOTAL 7618.93 W
Add 1 % Water charges on "W-A" 4793.38 47.9338
TOTAL X
Add GST (multiplying factor 0.1405) on "X- 4841.31 680.20
A" Y
TOTAL 5521.51 828.23
Add 15 % Contractor's profit and overheads Z
on "Y-A" 6349.74 63.50
Total 9238.79
Add Cess @ 1% on "Z-A" 9238.79
Cost per cum. 9238.80
Say

6.38 Providing and laying autoclaved aerated


cement blocks masonry with 100 mm thick AAC
Details of super
blocks in cost for 1 cum. above plinth level up
structure
to floor V level in cement mortar 1:4 (1 cement :
MATERIAL
8655 Autoclaved aerated cement (AAC) blocks. cum 1 2600 2600.00
Cement mortar 1 : 4 (1 cement : 4 coarse
sand)
3.9 Rate as per Item Number 3.9 of SH: cum 0.15 3548.00 532.20
Mortars
2208 Carriage of AAC Block cum 1 106.13 106.13
9999 Sundries L.S. 2.73 2 5.46
LABOUR
23 Mason (brick layer) 1st class day 0.36 505.17 181.86
24 Mason (brick layer) 2nd class day 0.36 403.67 145.32
18 Coolie day 1.37 350.00 479.50
11 Bhisti day 0.2 350.00 70.00
Reinforcement bars
5.22.1 Rate as per item no. 5.22.1 of kg 13.2 90.30 1191.96
SH : Reinforced cement concrete work
Extra labour element required for lifting of
materials (above floor two level upto floor
five level)(0.75 x1.5 =1.13).
18 Coolie day 1.13 350.00 395.50
TOTAL 5707.93 W
Add 1 % Water charges on "W-A" 4515.97 45.1597
TOTAL X
Add GST (multiplying factor 0.1405) on "X- 4561.13 640.84
A" Y
TOTAL 5201.97 780.30
Add 15 % Contractor's profit and overheads Z
5133.20
on "Y-A" 5982.27 59.82
Total 7234.05
Add Cess @ 1% on "Z-A" 7234.05
Cost of 1 Cum. 7234.10
Say

6.40 Providing and laying Gypsum panel


partitions 100for
Details of cost mm 10thick
sqm with water proof
Gypsum panels of size 666x500x100 mm,
MATERIAL
made of calcite phosphor Gypsum fixed
8656 Gypsum panel 666 X 500 X 100 mm size. sqm 10 480 4800.00
8657 Bonding plaster for Gypsum panel. kg 25 25 625.00
9999 Sundries & scaffolding L.S. 13.52 2 27.04
LABOUR
23 Mason (brick layer) 1st class day 0.5 505.17 252.59
17 Beldar day 1 350.00 350.00
TOTAL 6054.63 W
Add 1 % Water charges on "W" 60.5463
TOTAL 6115.18 X
Add GST (multiplying factor 0.1405) on "X" 859.18
TOTAL 6974.36 Y
Add 15 % Contractor's profit and overheads on 1046.15
"Y"
Total 8020.51 Z
Add Cess @ 1% on "Z" 80.21
Cost for 10 sqm. 8100.72
Cost for 1 sqm 810.10
Say 810.10
6.41 Extra for Gypsum panel Partitions in
superstructure above floor V level for
four floors or part thereof.
every
Details of cost for 10 sqm. per four floor
Extra labour element for lifting of materials
above floor V level.
18 Coolie day 1.73 350.00 605.50
Total 605.50 W
Add 1 % Water charges on "W" 6.055
TOTAL 611.56 X
Add GST (multiplying factor 0.1405) on "X" 85.92
TOTAL 697.47 Y
Add 15 % Contractor's profit and overheads on 104.62
"Y"
Total 802.09 Z
Add Cess @ 1% on "Z" 8.02
Cost for 10 cum. 810.11
Cost for 1 sqm 81.00
Say 81.00

6.44 Brick edging 7cm wide 11.4 cm deep to plinth


protection with common burnt clay F.P.S. (non
mortar
modular)1:4 (1 cement
bricks : 4 fine sand).
of class designation 7.5
including grouting with cement
Details of cost for 10m length
9999 Excavation and disposal of surplus earth L.S. 2.73 2 5.46
2nd class bricks = 42 nos. + Add wastage
@ 10% = 4.2 nos.
= 46.2 nos.
Say 46.00 nos.
2602 Common burnt clay F.P.S. (non modular) 1000 0.046 5000 230.00
bricks class designation 7.5 Nos
2201 Carriage of Bricks 1000 0.046 283.01 13.02
Cement mortar 1 : 4 (1 cement : 4 fine Nos
sand)
3.4 Rate as per Item Number 3.4 of cum 0.0036 3089.3 11.12

SH: Mortars

LABOUR
40 Mason (average) day 0.1 403.67 40.37
17 Beldar day 0.1 350.00 35.00
11 Bhisti day 0.03 350.00 10.50
9999 Sundries L.S. 2.73 2 5.46
TOTAL 350.93 W
Add 1 % Water charges on "W" 3.5093
TOTAL 354.44 X
Add GST (multiplying factor 0.1405) on "X" 49.80
TOTAL 404.24 Y
Add 15 % Contractor's profit and overheads on 60.64
"Y"
Total 464.88 Z
Add Cess @ 1% on "Z" 4.65
Cost for 10 cum. 469.53
Cost for 1 sqm 47.00
Say 47.00

6.45 Half brick masonry with non modular fly


ash bricks of class designation 10,
6.45.1 Cement mortar 1 : 3 (1 cement : 3
conformingio IS :12894, in super structure
coarse
Details ofsand)
costand
above plinth for 10 sqm.
upto floor V level.
MATERIAL
7737 Fly ash bricks conforming to I.S. 12894 1000 0.565 4300 2429.50
Cement mortar 1:3 (1 cement : 3 coarse Nos
sand)
3.8 Rate as per Item Number 3.8 of SH: cum 0.28 4129.00 1156.12
Mortars
2201 Carriage of Bricks 1000 0.565 283.01 159.90
Nos
9999 Sundries & Scaffolding L.S. 13.52 2 27.04
LABOUR
23 Mason (brick layer) 1st class day 0.6 505.17 303.10
24 Mason (brick layer) 2nd class day 0.6 403.67 242.20
18 Coolie day 2 350.00 700.00
11 Bhisti day 0.7 350.00 245.00
Extra labour for lifting of material (above
floor two level up to floor five level)
18 Coolie day 1.29 350.00 451.50
TOTAL 5714.36 W
Add 1 % Water charges on "W" 57.1436
TOTAL 5771.50 X
Add GST (multiplying factor 0.1405) on "X" 810.90
TOTAL 6582.40 Y
Add 15 % Contractor's profit and overheads on 987.36
"Y"
Total 7569.76 Z
Add Cess @ 1% on "Z" 75.70
Cost for 10 cum. 7645.46
Cost for 1 sqm 764.50
Say 764.50

6.45.2 Cement mortar 1 : 4 (1 cement : 4


coarse
Details ofsand)
cost for 10 sqm.
MATERIAL
7737 Fly ash bricks conforming to I.S. 12894 1000 0.565 4300 2429.50
Cement mortar 1 : 4 (1 cement : 4 coarse Nos
sand)
3.9 Rate as per Item Number 3.9 of SH: cum 0.28 3548.00 993.44
Mortars
2201 Carriage of Bricks 1000 0.565 283.01 159.90
Nos
9999 Sundries & Scaffolding L.S. 13.52 2 27.04
LABOUR
23 Mason (brick layer) 1st class day 0.6 505.17 303.10
24 Mason (brick layer) 2nd class day 0.6 403.67 242.20
18 Coolie day 2 350.00 700.00
11 Bhisti day 0.7 350.00 245.00
Extra labour for lifting of material (above
floor two level up to floor five level)
18 Coolie day 1.29 350.00 451.50
TOTAL 5551.68 W
Add 1 % Water charges on "W" 55.5168
TOTAL 5607.20 X
Add GST (multiplying factor 0.1405) on "X" 787.81
TOTAL 6395.01 Y
Add 15 % Contractor's profit and overheads on 959.25
"Y"
Total 7354.26 Z
Add Cess @ 1% on "Z" 73.54
Cost for 10 cum. 7427.80
Cost for 1 sqm 742.80
Say 742.80

6.47 Providing and laying autoclaved aerated


cement blocks masonry with 150mm/
seperately).
230mm/300 mm thick AAC blocks in super
structure
Details of above plinth
cost for level up to floor V level
1 cum.
MATERIAL
8655 Autoclaved areated cement (AAC) blocks cum 1 2600 2600.00
357 Polymer modified adhesive mortar Kg 30 15 450.00
9999 Sundries L.S. 2.73 2 5.46
LABOUR
23 Mason (brick layer) 1 st class day 0.36 505.17 181.86
24 Mason (brick layer) 2nd class day 0.36 403.67 145.32
18 Coolie day 1.37 350.00 479.50
Extra labour element required for lifting of
materials (above floor two level upto floor
five level) (0.75x1.50 = 1.13)
18 Coolie day 1.13 350.00 395.50
TOTAL 4257.64 W
Add 1 % Water charges on "W" 42.5764
TOTAL 4300.22 X
Add GST (multiplying factor 0.1405) on "X" 604.18
TOTAL 4904.40 Y
Add 15 % Contractor's profit and overheads on 735.66
"Y"
Total 5640.06 Z
Add Cess @ 1% on "Z" 56.40
Cost of 1 cum 5696.46
Say 5696.50
5696.50
5528.25
5309.35
4610.35
6296.15
6230.9
6382.9
6164

236.65
119

211.2
579.7
9550.2
11428.8
512.1
680.4

655.9
772.15
747.65

20.95
80.15

8451.95
8101.7
8517.55

9016.4
12233.1
14038.5
495.75

492.45
194.45

5420.35
6317.9
4646.9
5501.5
5298.45

6153.1
5676.35
6496.85

79.8
5478.05

200

6332.7
5428.75
6283.4
6545.35

6326.45
6054.65
5862
6771.35
6578.75

5715.2
9085.5
6957.55

804.2
74.25
43.1
757.05

732.55
5570.8
1 SUB HEAD : 7.0
2
3 STONE WORK
4
5 Code Description Unit Quantity Rate Amount
6 mm nominal size) upto plinth level
7 7.1 with :
8 Cement mortar 1:6 (1 cement : 6
9 7.1.1 coarse
10
11 sand)
12
13 Details of cost for 1 cum
14
15 MATERIAL
16 1157 Stone
Throughforand
masonry work size 24 x24
bond stone cum 1 1100 1100
17 1154 x39 cm 100 0.07 5000 350
18 Carriage:
Carriage of Soling stone & masonry Nos
19 2215 stone cum 1.16 124.86 144.84
20 7.00x24cmx24cmx39cm = 0.16 cum.
21 1.00cum. + 0.161cum.
Cement mortar : 6 (1=cement
1.16 cum.
:6
22 coarse sand)
23 3.11 Rate as per Item Number 3.11 of cum 0.33 2967.00 1043
24 SH: Mortars
25 LABOUR
Mason (for plain stone work) 2nd
26 25 class) day 1.07 403.67 400.72
27 17 Beldar day 1.07 350.00 343.29
28 18 Coolie day 0.71 350.00 227.79
29 11 Bhisti day 0.09 350.00 28.87
30 9999 Cement concrete 1:6:12 L.S. 45.76 2 91.52
31 9999 Sundries L.S. 4.42 2 8.84
32 TOTAL 3738.87 W
33 Add 1 % Water charges on "W" 37.3887
34 TOTAL
Add GST (multiplying factor 0.1405) 3776.26 X
35 on "X" 530.56
36 TOTAL
Add 15 % Contractor's profit and 4306.82 Y
37 overheads on "Y" 646.02
38 Total 4952.84 Z
39 Add Cess @ 1% on "Z" 49.53
40 Cost of 1 cum. 5002.37
41 Say 5002.40 5002.35
42 5002.40
44
45
46 mm nominal size) at window sills,
47 7.2 ceiling level and
7.2.1 Cement the like.
mortar 1:6 (1 cement :
49 6 coarse sand)
51 Details of cost for 1 cum
52 MATERIAL
53 1157 Stone for masonry work cum 1 1100 1100
54 1154 Through and bond stone size 24 x 100 0.07 5000 350
55 24 x39 cm Nos
56 Carriage
Carriage of
of stone-
Soling stone & masonry
57 2215 stone cum 1.16 124.86 144.84
58 7.00x24cmx24cmx39cm = 0.16 cum.
59 1.00cum. + 0.161cum.
Cement mortar : 6 (1=cement
1.16 cum.
:6
60 coarse sand)
Rate as per Item Number 3.11 of SH:
61 3.11 Mortars cum 0.33 2967.00 1043
62 LABOUR
Mason (for plain stone work) 2nd
63 25 class) day 1.34 403.67 501.83
64 17 Beldar day 1.45 350.00 465.2
65 18 Coolie day 0.71 350.00 227.79
66 11 Bhisti day 0.09 350.00 28.87
67 9999 Cement concrete
Extra labour 1:6:12
for lifting of material L.S. 56.55 2 113.1
68 (above floor two
69 level up to floor five level)
70 18 Coolie day 1.13 350.00 362.54
71 9999 Sundries L.S. 15.21 2 30.42
72 TOTAL 4367.59 W
73 Add 1 % Water charges on "W" 43.6759
74 TOTAL
Add GST (multiplying factor 0.1405) 4411.27 X
75 on "X" 619.78
76 TOTAL
Add 15 % Contractor's profit and 5031.05 Y
77 overheads on "Y" 754.66
78 Total 5785.71 Z
79 Add Cess @ 1% on "Z" 57.86
80 Cost of 1 cum. 5843.57
81 Say 5843.60 5843.55
82 5843.60
83
84
85
86 Extra for random rubble masonry
87 7.4 with hard stone in :
88 7.4.1 Square or rectangular pillars
90 Details of cost for 1 cum
92 LABOUR
Mason (for plain stone work) 2nd
93 25 class) day 0.58 403.67 217.21
94 18 Coolie day 0.27 350.00 86.62
95 TOTAL 303.83 W
96 Add 1 % Water charges on "W" 3.0383
97 TOTAL
Add GST (multiplying factor 0.1405) 306.87 X
98 on "X" 43.11
99 TOTAL
Add 15 % Contractor's profit and 349.98 Y
100 overheads on "Y" 52.50
101 Total 402.48 Z
102 Add Cess @ 1% on "Z" 4.02
103 Cost of 1 cum. 406.50
104 Say 406.50 406.5
105 406.50
106
107 7.4.2 Circular pillars
108 Details of cost for 1 cum
109 1157 Stone forof
Carriage masonry work & masonry
Soling stone cum 0.29 1100 319
110 2215 stone cum 0.29 124.86 36.21
111 LABOUR
Labour for cutting and dressing
112 stones-
Mason (for plain stone work) 2nd
113 25 class) day 1.42 403.67 531.79
114 18 Coolie day 0.35 350.00 112.29
115 Total 999.29 W
116 Add 1 % Water charges on "W" 9.9929
117 TOTAL
Add GST (multiplying factor 0.1405) 1009.28 X
118 on "X" 141.80
119 TOTAL
Add 15 % Contractor's profit and 1151.08 Y
120 overheads on "Y" 172.66
121 Total 1323.74 Z
122 Add Cess @ 1% on "Z" 13.24
123 Cost of 1 cum. 1336.98
124 Say 1337.00 1337
125 1337.00
126 with hard stone curved on plan for a
127 7.5 mean radius not exceeding 6 m.
128 Details of cost for 1 cum
129 1157 Stone forof
Carriage masonry work & masonry cum
Soling stone 0.1 1100 110
130 2215 stone cum 0.1 124.86 12.49
131
133
135 LABOUR
Labour for cutting and dressing
136 stones-(for plain stone work) 2nd
Mason
137 25 class) day 0.27 403.67 101.12
138 18 Coolie day 0.53 350.00 170.04
139 TOTAL 393.65 W
140 Add 1 % Water charges on "W" 3.9365
141 TOTAL
Add GST (multiplying factor 0.1405) 397.59 X
142 on "X" 55.86
143 TOTAL
Add 15 % Contractor's profit and 453.45 Y
144 overheads on "Y" 68.02
145 Total 521.47 Z
146 Add Cess @ 1% on "Z" 5.21
147 Cost of 1 cum. 526.68
148 Say 526.70 526.65
149 526.70
150 with hard stone in foundation and
151 7.6 plinth
Cement with :
mortar 1:6 (1 cement : 6
152 7.6.1 coarse sand)
154 Details of cost for 1 cum
155 MATERIAL
Cement mortar 1 : 6 (1 cement : 6
156 coarse
Rate assand)
per Item Number 3.11 of SH:
157 3.11 Mortars cum 0.3 2967.00 948.18
158 1157 Stone
Throughforand
masonry work size 24 x24 cum
bond stone 1.21 1100 1331
159 1154 x39 cm 100 0.07 5000 350
160 Carriage of Soling stone & masonry Nos
161 2215 stone cum 1.37 124.86 171.06
162 7.00x24cmx24cmx39cm = 0.16 cum.
163 1021+0.16=1.37 Cum
164 LABOUR
Mason (for plain stone work) 2nd
165 25 class) day 2.12 403.67 793.94
166 17 Beldar day 1.24 350.00 397.83
167 18 Coolie day 0.71 350.00 227.79
168 11 Bhisti day 0.09 350.00 28.87
169 9999 Sundries L.S. 13.52 2 27.04
170 TOTAL 4275.71 W
171 Add 1 % Water charges on "W" 42.7571
172 TOTAL
Add GST (multiplying factor 0.1405) 4318.47 X
173 on "X" 606.74
174 TOTAL
Add 15 % Contractor's profit and 4925.21 Y
175 overheads on "Y" 738.78
176 Total 5663.99 Z
178 Add Cess @ 1% on "Z" 56.64
180 Cost of 1 cum. 5720.63
181 Say 5720.60 5720.65
182 5720.60
183
184
185
186 sort) with hard stone in foundation &
187 7.7 plinth
Cement with :
mortar 1:6 (1 cement : 6
188 7.7.1 coarse sand)
189 Details of cost for 1 cum
190
191 MATERIAL
192 coarse sand) 3.11 Rate as per Item
193 Number 3.11 of SH: Mortars
194
195 1157 Stone for masonry work
196 1154 Through and bond stone size 24
197 x
198
199 24 x39 cm Carriage:
200
201
202 cum 0.3 3160.6 948.18
203 cum 1.1 1100 1210
204 100 0.07 5000 350
205 Nos
206 Carriage of Soling stone & masonry
207 2215 stone cum 1.26 124.86 157.32
208 7.00x24cmx24cmx39cm = 0.16 cum.
209 1.10+0.16 cum = 1.26 cum.
210 LABOUR
Mason (for plain stone work) 2nd
211 25 class) day 1.76 403.67 659.12
212 17 Beldar day 1.24 350.00 397.83
213 18 Coolie day 0.71 350.00 227.79
214 11 Bhisti day 0.09 350.00 28.87
215 9999 Sundries L.S. 13.52 2 27.04
216 TOTAL 4006.15 W
217 Add 1 % Water charges on "W" 40.0615
218 TOTAL
Add GST (multiplying factor 0.1405) 4046.21 X
219 on "X" 568.49
220 TOTAL
Add 15 % Contractor's profit and 4614.70 Y
221 overheads on "Y" 692.21
222 Total 5306.91 Z
223 Add Cess @ 1% on "Z" 53.07
224 Cost of 1 cum. 5359.98
225 Say 536.00 5360
226 superstructure above plinth level 536.00
227 and upto floor five level.
228 cement mortar 1:6 (1 cement : 6
229 coarse sand)
230
231 Details of cost for 1 cum
232
233 MATERIAL
234 Cement mortar 1 : 6 (1 cement : 6
235 coarse sand)
236
238 Rate as per Item Number 3.11 of SH:
240 3.11 Mortars cum 0.3 2967.00 948.18
241 1157 Stone
Through and bond stone size 24 x 24 cum
for masonry work 1.21 1100 1331
242 1154 x39 cm 100 0.07 5000 350
243 Nos
Carriage of Soling stone & masonry
244 2215 stone 7.00 x 24 cum 1.37 124.86 171.06
245 cm x24 cm x 39 cm = 0.16 cum.
246 1.21 cum. + 0.16 cum = 1.37 cum
247 LABOUR
Mason (for plain stone work) 2nd
248 25 class) day 2.38 403.67 891.31
249 17 Beldar day 1.59 350.00 510.12
250 18 Coolie day 0.71 350.00 227.79
251 11 Bhisti
Extra labour for lifting of material day 0.09 350.00 28.87
252 (above floor two
253 level up to floor five level)
254 18 Coolie day 1.13 350.00 362.54
255 9999 Sundries, scaffolding etc. L.S. 37.7 2 75.4
256 TOTAL 4896.27 W
257 Add 1 % Water charges on "W" 48.9627
258 TOTAL
Add GST (multiplying factor 0.1405) 4945.23 X
259 on "X" 694.81
260 TOTAL
Add 15 % Contractor's profit and 5640.04 Y
261 overheads on "Y" 846.01
262 Total 6486.05 Z
263 Add Cess @ 1% on "Z" 64.86
264 Cost of 1 cum. 6550.91
265 Say 655.10 6550.9
266 cement mortar 1:6 (1 cement: 6 655.10
267 coarse sand)
268
269 Details of cost for 1 cum
270 MATERIAL
Cement mortar 1 : 6 (1 cement : 6
271 coarse
Rate assand)
per Item Number 3.11 of SH:
272 3.11 Mortars cum 0.3 2967.00 948.18
273 1157 Stone
Throughforand
masonry work size 24 x24
bond stone cum 1.1 1100 1210
274 1154 x39 cm 100 0.07 5000 350
275 Carriage:
Carriage of Soling stone & masonry Nos
276 2215 stone cum 1.26 124.86 157.32
277 7.00x24cmx24cmx39cm = 0.16 cum.
278 1.10+0.16 cum = 1.26 cum.
279
280 LABOUR
281
283 Mason (for plain stone work) 2nd
285 25 class) day 2.02 403.67 756.49
286 17 Beldar day 1.59 350.00 510.12
287 18 Coolie day 0.71 350.00 227.79
288 11 Bhisti
Extra labour for lifting of material day 0.09 350.00 28.87
289 (above floor two
290 level up to floor five level)
291 18 Coolie day 1.13 350.00 362.54
292 9999 Sundries, scaffolding etc. L.S. 37.7 2 75.4
293 TOTAL 2118.53 W
294 Add 1 % Water charges on "W" 21.1853
295 TOTAL
Add GST (multiplying factor 0.1405) 2139.72 X
296 on "X" 300.63
297 TOTAL
Add 15 % Contractor's profit and 2440.35 Y
298 overheads on "Y" 366.05
299 Total 2806.40 Z
300 Add Cess @ 1% on "Z" 28.06
301 Cost of 1 cum. 2834.46
302 Say 283.40 6190.25
303 masonry with hard stone (first or 283.40
304 second sort) in:
305
306 7.10.1 Square or rectangular pillars
307
308 Details of cost for 1 cum
309 LABOUR
0025 Mason (for plain stone work)
310 2nd class) day 0.67 374.5 250.92
311 18 Coolie day 0.27 350.00 86.62
312 TOTAL 9680.28 W
313 Add 1 % Water charges on "W" 96.802759
314 TOTAL
Add GST (multiplying factor 0.1405) 9777.08 X
315 on "X" 1373.68
316 TOTAL
Add 15 % Contractor's profit and 11150.76 Y
317 overheads on "Y" 1672.61
318 Total 12823.37 Z
319 Add Cess @ 1% on "Z" 128.23
320 Cost of 1 cum. 12951.60
321 Say 1295.20 451.6
322 7.10.2 Circular pillars 1295.20
323 Details of cost for 1 cum
324
326
328 1157 Stone forof
Carriage masonry work & masonry
Soling stone cum 0.32 1100 352
329 2215 stone cum 0.32 124.86 39.95
330 LABOUR
331 Labour for cutting
Mason (for and dressing
plain stone work) 2nd:
332 25 class) day 1.67 403.67 625.42
333 18 Coolie day 0.35 350.00 112.29
334 Total 42446.63 W
335 Add 1 % Water charges on "W" 424.46626
336 TOTAL
Add GST (multiplying factor 0.1405) 42871.09 X
337 on "X" 6023.39
338 TOTAL
Add 15 % Contractor's profit and 48894.48 Y
339 overheads on "Y" 7334.17
340 Total 56228.65 Z
341 Add Cess @ 1% on "Z" 562.29
342 Cost of 1 cum. 56790.94
343 Say 5679.10 1511.4
344 second sort) curved on plan for a 5679.10
345 mean radius not exceeding 6 m.
346
347 Details of cost for 1 cum Extra
348
349 1157 Stone forof
Carriage masonry work & masonry
Soling stone cum 0.11 1100 121
350 2215 stone Labour cum 0.11 124.86 13.73
351 for
0025cutting
Masonand(fordressing:
plain stone work)
352 2nd class) day 0.33 374.5 123.59
353 18 Coolie day 0.53 350.00 170.04
354 TOTAL 181597.10 W
355 Add 1 % Water charges on "W" 1815.971
356 TOTAL
Add GST (multiplying factor 0.1405) 183413.07 X
357 on "X" 25769.54
358 TOTAL
Add 15 % Contractor's profit and 209182.61 Y
359 overheads on "Y" 31377.39
360 Total 240560.00 Z
361 Add Cess @ 1% on "Z" 2405.60
362 Cost of 1 cum. 242965.60
363 Say 24296.60 573.1
364 24296.60
366 Code Description Unit Quantity Rate
367 Amount
368 2 stone dust) with an admixture of
369 pigment matching the stone shade :
370
371 7.12.1 One face dressed
372
373 7.12.1.1 Red sand stone
374
375 Details of cost for 10 cudm.
376 MATERIAL
377 Red sand stone
378 Finished work@= 33.3%
Add wastage 10 cudm.+
= 3.33 cudm.
379 Total = 13.33
380 cudm
381 1160 Red sand stone block 10 1.333 79 105.31
382 Carriage of Stone blocks white & red cudm
383 2216 sand stone & tonne 0.031 94.34 2.92
384 kota stone slab = 13.33x2.30 = 30.659
@ 2.30kg/cudm
385 kg =
0.03065 tonne say 0.031 t. Extra
386 labour forupto
materials lifting of V level
floor
387 (0.01x1.50 = 0.015)
388 18 Coolie day 0.015 350.00 4.81
389 Dressing charges
390 LABOUR
Mason (for plain stone work) 2nd
391 25 class) day 0.088 403.67 32.96
392 12 Blacksmith 1st class day 0.006 505.17 2.86
393 17 Beldar day 0.044 350.00 14.12
394 18 Coolie day 0.022 350.00 7.06
395 10 Bandhani day 0.044 350.00 14.12
396 Fixing charges
397 LABOUR
Mason (for plain stone work) 2nd
398 25 class) day 0.044 403.67 16.48
399 12 Blacksmith 1st class day 0.006 505.17 2.86
400 17 Beldar day 0.022 350.00 7.06
401 18 Coolie day 0.022 350.00 7.06
402 10 Bandhani day 0.022 350.00 7.06
403 11 Bhisti day 0.022 350.00 7.06
404 9999 Scafolding L.S. 2.73 2 5.46
405 9999 Mortar for laying and pointing L.S. 8.06 2 16.12
406 TOTAL 140.28 W
407 Add 1 % Water charges on "W" 1.4028
408 TOTAL
Add GST (multiplying factor 0.1405) 141.68 X
409 on "X" 19.91
410 161.59 Y
411 24.24
413 185.83 Z
415 TOTAL 291.77 Y 1.86
Add 15 % Contractor's profit and
416 overheads on "Y" 43.77 187.69
417 Total 335.54 Z 18.80
418 Add Cess @ 1% on "Z" 3.36 18.80
419 Cost of 10 cudm. 338.89
420 Cost of 1 cum. 33889
421 Say 33889
422
423 7.12.1.2 White sand stone
424
425 Details of cost for 10 cudm.
426 MATERIAL
427 1161 White sand stone block 10 1.333 205 273.27
428 Finished work = 10 cudm.+ cudm
429 Add wastage @ 33.3% = 3.33 cudm.
430 Total = 13.33
Carriage cudm.
of Stone blocks white & red
431 2216 sand stone & tonne 0.031 94.34 2.92
432 kota stone slab = 13.33x2.30 = 30.659
@ 2.30kg/cudm
433 kg =
434 0.03065 tonnefor
Extra labour say 0.031
lifting oft.materials
435 upto floor V level.
436 (0.01 x 1.50 =0.015)
437 18 Coolie day 0.015 350.00 4.81
438 Dressing charges
439 LABOUR
Mason (for plain stone work) 2nd
440 25 class) day 0.088 403.67 32.96
441 12 Blacksmith 1st class day 0.006 505.17 2.86
442 17 Beldar day 0.044 350.00 14.12
443 18 Coolie day 0.022 350.00 7.06
444 10 Bandhani day 0.044 350.00 14.12
445 Fixing charges
446 LABOUR
Mason (for plain stone work) 2nd
447 25 class) day 0.044 403.67 16.48
448 12 Blacksmith 1st class day 0.006 505.17 2.86
449 17 Beldar day 0.022 350.00 7.06
450 18 Coolie day 0.022 350.00 7.06
451 10 Bandhani day 0.022 350.00 7.06
452 11 Bhisti day 0.022 350.00 7.06
453 9999 Scaffolding L.S. 2.73 2 5.46
454 9999 Mortar for laying and pointing L.S. 8.06 2 16.12
455 TOTAL 140.28 W
456 Add 1 % Water charges on "W" 1.4028
457 TOTAL 141.68 X
458 19.91
460 Add GST (multiplying factor 0.1405) 161.59 Y
462 on "X" 59.78 24.24
463 TOTAL
Add 15 % Contractor's profit and 485.24 Y 185.83 Z
464 overheads on "Y" 72.79 1.86
465 Total 558.03 Z 187.69
466 Add Cess @ 1% on "Z" 5.58 18.80
467 Cost of 10 cudm. 563.61 18.80
468 Cost of 1 cum. 56361
469 Say 56361
470 7.12.2 Both face dressed 7.12.2.1 Red
471 sand stone
472
473 Details of cost for 10 cudm.
474 MATERIAL
475 1160 Red sand stone block 10 1.333 79 105.31
476 Finished work@= 33.3%
Add wastage 10 cudm.+
= 3.33 cudm. cudm
477 Cost of stone
Carriage of Stone blocks white & red
478 2216 sand stone & tonne 0.031 94.34 2.92
479 kota stone slab = 13.33x2.30 = 30.659
@ 2.30kg/cudm
480 kg =
0.03065 tonne say 0.031 t. Extra
481 labour for lifting
materials upto of V level
floor
482 (0.01x1.50 = 0.015)
483 18 Coolie day 0.015 350.00 4.81
484 Dressing charges
485 LABOUR
Mason (for plain stone work) 2nd
486 25 class) day 0.176 403.67 65.91
487 12 Blacksmith 1st class day 0.012 505.17 5.71
488 17 Beldar day 0.088 350.00 28.23
489 18 Coolie day 0.044 350.00 14.12
490 10 Bandhani day 0.088 350.00 28.23
491 Fixing charges
492 LABOUR
Mason (for plain stone work) 2nd
493 25 class) day 0.044 403.67 16.48
494 12 Blacksmith 1st class day 0.006 505.17 2.86
495 17 Beldar day 0.022 350.00 7.06
496 18 Coolie day 0.022 350.00 7.06
497 10 Bandhani day 0.022 350.00 7.06
498 11 Bhisti day 0.022 350.00 7.06
499 9999 Scafolding L.S. 2.73 2 5.46
500 9999 Mortar for laying and pointing L.S. 8.06 2 16.12
501 TOTAL 211.36 W
502 2.1136
504 213.47 X
506 Add 1 % Water charges on "W" 3.24 29.99
507 TOTAL
Add GST (multiplying factor 0.1405) 327.64 X 243.46 Y
508 on "X" 46.03 36.52
509 TOTAL
Add 15 % Contractor's profit and 373.68 Y 279.98 Z
510 overheads on "Y" 56.05 2.80
511 Total 429.73 Z 282.78
512 Add Cess @ 1% on "Z" 4.3 28.30
513 Cost of 10 cudm. 434.02 28.30
514 Cost of 1 cum. 43402
515 Say 43402
516
517 7.12.2.2 White sand stone
518
Details of cost for 10 cudm or 0.01
519 cum
520 MATERIAL
521 1161 White sand stone block 10 1.333 205 273.27
522 Finished work = 10 cudm.+ cudm
523 Add wastage @ 33.3% = 3.33 cudm.
524 Total = 13.33
Carriage cudm.
of Stone blocks white & red
525 2216 sand stone & tonne 0.031 94.34 2.92
526 kota stone slab = 13.33x2.30 = 30.659
@ 2.30kg/cudm
527 kg =
528 0.03065 tonnefor
Extra labour say 0.031
lifting oft.material
529 upto floor V level.
530 (0.01 x 1.50 = 0.015)
531 18 Coolie day 0.015 350.00 4.81
532 Dressing charges
533 LABOUR
Mason (for plain stone work) 2nd
534 25 class) day 0.176 403.67 65.91
535 12 Blacksmith 1st class day 0.012 505.17 5.71
536 17 Beldar day 0.088 350.00 28.23
537 18 Coolie day 0.044 350.00 14.12
538 10 Bandhani day 0.088 350.00 28.23
539 Fixing charges
540 LABOUR
Mason (for plain stone work) 2nd
541 25 class) day 0.044 403.67 16.48
542 12 Blacksmith 1st class day 0.006 505.17 2.86
543 17 Beldar day 0.022 350.00 7.06
544 18 Coolie day 0.022 350.00 7.06
545 10 Bandhani day 0.022 350.00 7.06
546 11 Bhisti day 0.022 350.00 7.06
547 9999 Scaffolding L.S. 2.73 2 5.46
548
550
552 9999 Mortar for laying and pointing L.S. 8.06 2 16.12
553 TOTAL 145.45 W
554 Add 1 % Water charges on "W" 1.4545
555 TOTAL
Add GST (multiplying factor 0.1405) 146.90 X
556 on "X" 20.64
557 TOTAL
Add 15 % Contractor's profit and 167.54 Y
558 overheads on "Y" 25.13
559 Total 192.67 Z
560 Add Cess @ 1% on "Z" 1.93
561 Cost of 10 cudm. 194.60
562 Cost of 1 cum. 19.50
563 Say 19.50 65874
564 admixture of pigment matching the
565 stone shade.
566 7.13.1 One face dressed 7.13.1.1 Red
567 sand stone
568 Details of cost for 10 cudm or 0.01
569 cum
570 MATERIAL
571 1160 Red sand stone block 10 1.333 79 105.31
572 Finished work = 10 cudm.+ cudm
573 Add wastage @ 33.3% = 3.33 cudm.
574 Total = 13.33
Carriage cudm.
of Stone blocks white & red
575 2216 sand stone & tonne 0.031 94.34 2.92
576 kota stone slab
@ 2.30kg/cudm = 13.33x2.30 = 30.659
577 kg =
578 0.03065 tonne say 0.031 t.
579 Dressing charges
580 LABOUR
Mason (for plain stone work) 2nd
581 25 class) day 0.088 403.67 32.96
582 12 Blacksmith 1st class day 0.006 505.17 2.86
583 17 Beldar day 0.044 350.00 14.12
584 18 Coolie day 0.022 350.00 7.06
585 10 Bandhani day 0.044 350.00 14.12
586 Fixing charges
587 LABOUR
Mason (for plain stone work) 2nd
588 25 class) day 0.044 23 16.48
589 12 Blacksmith 1st class day 0.006 505.17 2.86
590
592
594 17 Beldar day 0.022 350.00 7.06
595 18 Coolie day 0.022 350.00 7.06
596 10 Bandhani day 0.022 350.00 7.06
597 11 Bhisti day 0.022 350.00 7.06
598 9999 Scaffolding L.S. 2.73 2 5.46
599 9999 Mortar for laying and pointing L.S. 8.06 2 16.12
600 9999 Centering and shuttering L.S. 13.52 2 27.04
601 9999 Extra
Extra for using
labour forwhite
liftingcement
of material L.S. 8.06 2 16.12
602 (above floor two
603 level up to floor five level)
604 (0.01 x 1.5 = 0.015)
605 18 Coolie day 0.015 350.00 4.81
606 TOTAL 117.13 W
607 Add 1 % Water charges on "W" 1.1713
608 TOTAL
Add GST (multiplying factor 0.1405) 118.30 X
609 on "X" 16.62
610 TOTAL
Add 15 % Contractor's profit and 134.92 Y
611 overheads on "Y" 20.24
612 Total 155.16 Z
613 Add Cess @ 1% on "Z" 1.55
614 Cost of 10 cudm. 156.71
615 Cost of 1 cum. 15.70
616 Say 15.70 39664
617
618 7.13.1.2 White sand stone
619 Details of cost for 10 cudm or 0.01
620 cum
621 MATERIAL
622 1161 White sand stone block 10 1.333 205 273.27
623 Finished work = 10 cudm.+ cudm
624 Add wastage @ 33.3% = 3.33 cudm.
625 Total = 13.33
Carriage cudm.
of Stone blocks white & red
626 2216 sand stone & tonne 0.031 94.34 2.92
627 kota stone slab = 13.33x2.30=30.659
@ 2.30kg/cudm
628 kg
629 #ERROR!
630 Dressing charges
631 LABOUR
Mason (for plain stone work) 2nd
632 25 class) day 0.088 403.67 32.96
633 12 Blacksmith 1st class day 0.006 505.17 2.86
634
636
638 17 Beldar day 0.044 350.00 14.12
639 18 Coolie day 0.022 350.00 7.06
640 10 Bandhani day 0.044 350.00 14.12
641 Fixing charges
642 LABOUR
Mason (for plain stone work) 2nd
643 25 class) day 0.044 403.67 16.48
644 12 Blacksmith 1st class day 0.006 403.67 2.86
645 17 Beldar day 0.022 350.00 7.06
646 18 Coolie day 0.022 350.00 7.06
647 10 Bandhani day 0.022 350.00 7.06
648 11 Bhisti day 0.022 350.00 7.06
649 9999 Scaffolding L.S. 2.73 2 5.46
650 9999 Mortar for laying and pointing L.S. 8.06 2 16.12
651 9999 Centering and shuttering L.S. 13.52 2 27.04
652 9999 Extra for using white cement L.S. 8.06 2 16.12
653 Extra
(abovelabour for lifting
floor two of material
level up to floor five
654 level)
655 (0.01 x 1.5 = 0.015)
656 18 Coolie day 0.015 350.00 4.81
657 TOTAL 117.13 W
658 Add 1 % Water charges on "W" 1.1713
659 TOTAL
Add GST (multiplying factor 0.1405) 118.30 X
660 on "X" 16.62
661 TOTAL
Add 15 % Contractor's profit and 134.92 Y
662 overheads on "Y" 20.24
663 Total 155.16 Z
664 Add Cess @ 1% on "Z" 1.55
665 Cost of 10 cudm. 156.71
666 Cost of 1 cum. 15.70
667 Say 15.70 62135
668
669 sand
670 stone
671 Details of cost for 10 cudm or 0.01
672 cum
673
674 MATERIAL
675 1160 Red sand stone block Finished
676 work = 10 cudm.+
677
678 Add wastage @ 33.3% = 3.33 cudm.
679
680
681 10 1.333 79.00 105.31 cudm
682
684
686 Total = 13.33
Carriage cudm.
of Stone blocks white & red
687 2216 sand stone & tonne 0.031 94.34 2.92
688 kota stone slab = 13.33x2.30 = 30.659
@ 2.30kg/cudm
689 kg =
690 0.03065 tonne say 0.031 t.
691 Dressing charges
692 LABOUR
Mason (for plain stone work) 2nd
693 25 class) day 0.176 403.67 65.91
694 12 Blacksmith 1st class day 0.012 505.17 5.71
695 17 Beldar day 0.088 350.00 28.23
696 18 Coolie day 0.044 350.00 14.12
697 10 Bandhani day 0.088 350.00 28.23
698 Fixing charges
699 LABOUR
Mason (for plain stone work) 2nd
700 25 class) day 0.044 403.67 16.48
701 12 Blacksmith 1st class day 0.006 505.17 2.86
702 17 Beldar day 0.022 350.00 7.06
703 18 Coolie day 0.022 350.00 7.06
704 10 Bandhani day 0.022 350.00 7.06
705 11 Bhisti day 0.022 350.00 7.06
706 9999 Scaffolding L.S. 2.73 2 5.46
707 9999 Mortar for laying and pointing L.S. 8.06 2 16.12
708 9999 Centering and shuttering L.S. 13.52 2 27.04
709 9999 Extra for using white cement L.S. 8.06 2 16.12
710 Extra
(abovelabour for lifting
floor two of material
level up to floor five
711 level)
712 (0.01 x 1.5 = 0.015)
713 18 Coolie day 0.015 350.00 4.81
714 TOTAL 117.13 W
715 Add 1 % Water charges on "W" 1.1713
716 TOTAL
Add GST (multiplying factor 0.1405) 118.30 X
717 on "X" 16.62
718 TOTAL
Add 15 % Contractor's profit and 134.92 Y
719 overheads on "Y" 20.24
720 Total 155.16 Z
721 Add Cess @ 1% on "Z" 1.55
722 Cost of 10 cudm. 156.71
723 Cost of 1 cum. 15.70
724 Say 15.70 49177
725
726
728 Code Description Unit Quantity Rate
729 Amount
730
731 7.13.2.2 White sand stone
732 Details of cost for 10 cudm or 0.01
733 cum
734 MATERIAL
735 1161 White sand stone block 10 1.333 205 273.27
736 Finished work = 10 cudm. cudm
737 Add wastage @ 33.3% = 3.33 cudm.
738 Total = 13.33
Carriage cudm.
of Stone blocks white & red
739 2216 sand stone & tonne 0.031 94.34 2.92
740 kota stone slab
@ 2.30kg/cudm = 13.33x2.30 = 30.659
741 kg =
742 0.03065 tonne say 0.031 t.
743 Dressing charges
744 LABOUR
Mason (for plain stone work) 2nd
745 25 class) day 0.176 403.67 65.91
746 12 Blacksmith 1st class day 0.012 505.17 5.71
747 17 Beldar day 0.088 350.00 28.23
748 18 Coolie day 0.044 350.00 14.12
749 10 Bandhani day 0.088 350.00 28.23
750 Fixing charges
751 LABOUR
Mason (for plain stone work) 2nd
752 25 class) day 0.044 403.67 16.48
753 12 Blacksmith 1st class day 0.006 505.17 2.86
754 17 Beldar day 0.022 350.00 7.06
755 18 Coolie day 0.022 350.00 7.06
756 10 Bandhani day 0.022 350.00 7.06
757 11 Bhisti day 0.022 350.00 7.06
758 9999 Scaffolding L.S. 2.73 2 5.46
759 9999 Mortar for laying and pointing L.S. 8.06 2 16.12
760 9999 Centering and shuttering L.S. 13.52 2 27.04
761 9999 Extra for using white cement L.S. 8.06 2 16.12
762 Extra
(abovelabour for lifting
floor two of material
level up to floor five
763 level)
764 (0.01 x 1.5 = 0.015)
765 18 Coolie day 0.015 350.00 4.81
766 TOTAL 117.13 W
767 Add 1 % Water charges on "W" 1.1713
768 TOTAL
Add GST (multiplying factor 0.1405) 118.30 X
769 on "X" 16.62
770 TOTAL 134.92 Y
771 20.24
772 155.16 Z
774 1.55
775 Code Description
Add 15 % Contractor's profit and Rate Amount 156.71
776 overheads on "Y" 92.53 15.70
777 Total 709.39 Z 15.70
778 Add Cess @ 1% on "Z" 7.09
779 Cost of 10 cudm. 716.49
780 Cost of 1 cum. 71649
781 Say 71649
782 with white cement mortar 1:2 (1
783 white cement : 2 stone dust)
784 matching the stone shade. 7.14.1 One
785 face dressed
786
787 7.14.1.1 Red sand stone
788 Details of cost for 10 cudm or 0.01
789 cum
790 MATERIAL
791 1160 Red sand stone block 10 1.333 79 105.31
792 Finished work = 10 cudm. cudm
793 Add wastage @ 33.3% = 3.33 cudm.
794 Total = 13.33
Carriage cudm.
of Stone blocks white & red
795 2216 sand stone & tonne 0.031 94.34 2.92
796 kota stone slab = 13.33x2.30=30.659
@ 2.30kg/cudm
797 kg
798 #ERROR!
799 Dressing charges
800 LABOUR
Mason (for plain stone work) 2nd
801 25 class) day 0.176 403.67 65.91
802 12 Blacksmith 1st class stone work)
Mason (for ornamental day 0.006 505.17 2.86
803 26 1st class day 0.176 505.17 83.78
804 17 Beldar day 0.044 350.00 14.12
805 18 Coolie day 0.022 350.00 7.06
806 10 Bandhani day 0.044 350.00 14.12
807 Fixing charges
808 LABOUR
Mason (for plain stone work) 2nd
809 25 class) day 0.044 403.67 16.48
810 12 Blacksmith 1st class day 0.006 505.17 2.86
811 17 Beldar day 0.022 350.00 7.06
812 18 Coolie day 0.022 350.00 7.06
813 10 Bandhani day 0.022 350.00 7.06
814 11 Bhisti day 0.022 350.00 7.06
815 9999 Scaffolding L.S. 2.73 2 5.46
816 9999 Mortar for laying and pointing L.S. 8.06 2 16.12
817 9999 Centring and shuttering L.S. 33.15 2 66.3
818
820 Extra for using white cement Extra
822 9999 labour up to floor five level (0.01 L.S.
for lifting
of material 8.06 2 16.12
823 x 1.5 = 0.015)
824 18 Coolie day 0.015 350.00 4.81
825 TOTAL 156.39 W
826 Add 1 % Water charges on "W" 1.5639
827 TOTAL 157.95 X
Add GST (multiplying factor 0.1405)
828 on "X" 22.19
829 TOTAL
Add 15 % Contractor's profit and 180.14 Y
830 overheads on "Y" 27.02
831 Total 207.16 Z
832 Add Cess @ 1% on "Z" 2.07
833 Cost of 10 cudm. 209.23
834 Cost of 1 cum. 20.90
835 Say 20.90 60534
836
837 7.14.1.2 White sand stone
838 Details of cost for 10 cudm or 0.01
839 cum
840 MATERIAL
841 1161 White sand stone block 10 1.333 205 273.27
842 Finished work = 10 cudm.+ cudm
843 Add wastage @ 33.3% = 3.33 cudm.
844 Total = 13.33
Carriage cudm.
of Stone blocks white & red
845 2216 sand stone & tonne 0.031 94.34 2.92
846 kota stone slab = 13.33x2.30=30.659
@ 2.30kg/cudm
847 kg
848 #ERROR!
849 Dressing charges
850 LABOUR
Mason (for plain stone work) 2nd
851 25 class) day 0.176 403.67 65.91
852 12 Blacksmith 1st class stone work)
Mason (for ornamental day 0.006 505.17 2.86
853 26 1st class day 0.176 505.17 83.78
854 17 Beldar day 0.044 350.00 14.12
855 18 Coolie day 0.022 350.00 7.06
856 10 Bandhani day 0.044 350.00 14.12
857 Fixing charges
858 LABOUR
Mason (for plain stone work) 2nd
859 25 class) day 0.044 403.67 16.48
860 12 Blacksmith 1st class day 0.006 505.17 2.86
861 17 Beldar day 0.022 350.00 7.06
862 18 Coolie day 0.022 350.00 7.06
863 10 Bandhani day 0.022 350.00 7.06
864
866
868 11 Bhisti day 0.022 350.00 7.06
869 9999 Scaffolding L.S. 2.73 2 5.46
870 9999 Mortar for laying and pointing L.S. 8.06 2 16.12
871 9999 Centring and shuttering L.S. 33.15 2 66.3
872 9999 Extra
Extra for using
labour forwhite
liftingcement
of material up L.S. 8.06 2 16.12
873 to floor five
874 level (0.01 x 1.5 = 0.015)
875 18 Coolie day 0.015 350.00 4.81
876 TOTAL 156.39 W
877 Add 1 % Water charges on "W" 1.5639
878 TOTAL
Add GST (multiplying factor 0.1405) 157.95 X
879 on "X" 22.19
880 TOTAL
Add 15 % Contractor's profit and 180.14 Y
881 overheads on "Y" 27.02
882 Total 207.16 Z
883 Add Cess @ 1% on "Z" 2.07
884 Cost of 10 cudm. 209.23
885 Cost of 1 cum. 20.90
886 Say 20.90 83006
887 7.14.2 Both face dressed
888 7.14.2.1 Red sand stone
889 Details of cost for 10 cudm.
890 MATERIAL
891 1160 Red sand stone block 10 1.333 79 105.31
892 Finished work = 10 cudm.+ cudm
893 Add wastage @ 33.3% = 3.33 cudm.
894 Total = 13.33
Carriage cudm.
of Stone blocks white & red
895 2216 sand stone & tonne 0.031 94.34 2.92
896 kota stone slab = 13.33x2.30=30.659
@ 2.30kg/cudm
897 kg
898 #ERROR!
899 Dressing charges
900 LABOUR
Mason (for plain stone work) 2nd
901 25 class) day 0.352 403.67 131.82
902 12 Blacksmith 1st class stone work)
Mason (for ornamental day 0.012 505.17 5.71
903 26 1st class day 0.352 505.17 167.55
904 17 Beldar day 0.088 350.00 28.23
905 18 Coolie day 0.044 350.00 14.12
906
907
909
911 10 Bandhani day 0.088 350.00 28.23
912 Fixing charges
913 LABOUR
Mason (for plain stone work) 2nd
914 25 class) day 0.044 403.67 16.48
915 12 Blacksmith 1st class day 0.006 505.17 2.86
916 17 Beldar day 0.022 350.00 7.06
917 18 Coolie day 0.022 350.00 7.06
918 10 Bandhani day 0.022 350.00 7.06
919 11 Bhisti day 0.022 350.00 7.06
920 9999 Scaffolding L.S. 2.73 2 5.46
921 9999 Mortar for laying and pointing L.S. 8.06 2 16.12
922 9999 Centring and shuttering L.S. 33.15 2 66.3
923 9999 Extra
Extra for using
labour forwhite
liftingcement
of material up L.S. 8.06 2 16.12
924 to floor five
925 level (0.01 x 1.5 = 0.015)
926 18 Coolie day 0.015 350.00 4.81
927 TOTAL 184.62 W
928 Add 1 % Water charges on "W" 1.8462
929 TOTAL
Add GST (multiplying factor 0.1405) 186.47 X
930 on "X" 26.20
931 TOTAL
Add 15 % Contractor's profit and 212.67 Y
932 overheads on "Y" 31.90
933 Total 244.57 Z
934 Add Cess @ 1% on "Z" 2.45
935 Cost of 10 cudm. 247.02
936 Cost of 1 cum. 24.70
937 Say 24.70 85666
938
939 7.14.2.2 White sand stone
940 Details of cost for 10 cudm or 0.01
941 cum
942 MATERIAL
943 1161 White sand stone block 10 1.333 205 273.27
944 Finished work = 10 cudm.+ cudm
945 Add wastage @ 33.3% = 3.33 cudm.
946 Total = 13.33
Carriage cudm.
of Stone blocks white & red
947 2216 sand stone & tonne 0.031 94.34 2.92
948
949 kota stone slab
950 @ 2.30kg/cudm = 13.33x2.30=30.659
951 kg =0.03065 tonne say 0.031 t
952
953 Dressing charges
954
956
958 LABOUR
Mason (for plain stone work) 2nd
959 25 class) day 0.352 403.67 131.82
960 12 Blacksmith 1st class stone work)
Mason (for ornamental day 0.012 505.17 5.71
961 26 1st class day 0.352 505.17 167.55
962 17 Beldar day 0.088 350.00 28.23
963 18 Coolie day 0.044 350.00 14.12
964 10 Bandhani day 0.088 350.00 28.23
965 Fixing charges
966 LABOUR
Mason (for plain stone work) 2nd
967 25 class) day 0.044 403.67 16.48
968 12 Blacksmith 1st class day 0.006 505.17 2.86
969 17 Beldar day 0.022 350.00 7.06
970 18 Coolie day 0.022 350.00 7.06
971 10 Bandhani day 0.022 350.00 7.06
972 11 Bhisti day 0.022 350.00 7.06
973 9999 Scaffolding L.S. 2.73 2 5.46
974 9999 Mortar for laying and pointing L.S. 8.06 2 16.12
975 9999 Centring and shuttering L.S. 33.15 2 66.3
976 9999 Extra
Extra for using
labour forwhite
liftingcement
of material up L.S. 8.06 2 16.12
977 to floor five
978 level (0.01 x 1.5 = 0.015)
979 18 Coolie day 0.015 350.00 4.81
980 TOTAL 184.62 W
981 Add 1 % Water charges on "W" 1.8462
982 TOTAL
Add GST (multiplying factor 0.1405) 186.47 X
983 on "X" 26.20
984 TOTAL
Add 15 % Contractor's profit and 212.67 Y
985 overheads on "Y" 31.90
986 Total 244.57 Z
987 Add Cess @ 1% on "Z" 2.45
988 Cost of 10 cudm. 247.02
989 Cost of 1 cum. 24.70
990 Say 24.70 108137
991 dust) with an admixture of pigment
992 matching the stone shade.
993
994 328
995 Code Description Unit Quantity Rate
996 Amount
997 7.15.1 One face dressed 7.15.1.1 Red
998 sand stone
999 Details of cost for 10 cudm or 0.01
1000 cum
1001 MATERIAL
1002 1160 Red sand stone block 10 1.333 79 105.31
1003 Finished work = 10 cudm.+ cudm
1004 Add wastage @ 33.3% = 3.33 cudm.
1005 Total = 13.33
Carriage cudm.
of Stone blocks white & red
1006 2216 sand stone & tonne 0.031 94.34 2.92
1007 kota stone slab = 13.33x2.30=30.659
@ 2.30kg/cudm
1008 tonne
1009 #ERROR!
1010 Dressing charges
1011 LABOUR
Mason (for plain stone work) 2nd
1012 25 class) day 0.059 403.67 22.1
1013 12 Blacksmith 1st class day 0.006 505.17 2.86
1014 17 Beldar day 0.044 350.00 14.12
1015 18 Coolie day 0.022 350.00 7.06
1016 10 Bandhani day 0.044 350.00 14.12
1017 Fixing charges
1018 LABOUR
Mason (for plain stone work) 2nd
1019 25 class) day 0.044 403.67 16.48
1020 12 Blacksmith 1st class day 0.006 505.17 2.86
1021 17 Beldar day 0.022 350.00 7.06
1022 18 Coolie day 0.022 350.00 7.06
1023 10 Bandhani day 0.022 350.00 7.06
1024 11 Bhisti day 0.022 350.00 7.06
1025 9999 Scaffolding
Mortar for laying and pointing Extra L.S. 2.73 2 5.46
1026 9999 labour for lifting
of materials upto floor V level L.S. 8.06 2 16.12
1027 (0.01x1.50 = 0.015)
1028 18 Coolie day 0.015 350.00 4.81
1029 TOTAL 112.13 W
1030 Add 1 % Water charges on "W" 1.1213
1031 TOTAL 113.25 X
Add GST (multiplying factor 0.1405)
1032 on "X" 15.91
1033 TOTAL
Add 15 % Contractor's profit and 129.16 Y
1034 overheads on "Y" 19.37
1035 148.53 Z
1036 1.49
1038 150.02
1040 Total 321.15 Z 15.00
1041 Add Cess @ 1% on "Z" 3.21 15.00
1042 Cost of 10 cudm. 324.36
1043 Cost of 1 cum. 32436
1044 Say 32436
1045
1046 7.15.1.2 White sand stone
1047 Details of cost for 10 cudm or 0.01
1048 cum
1049 MATERIAL
1050 1161 White sand stone block 10 1.333 205 273.27
1051 Finished work = 10 cudm.+ cudm
1052 Add wastage @ 33.3% = 3.33 cudm.
1053 Total = 13.33
Carriage cudm.
of Stone blocks white & red
1054 2216 sand stone & tonne 0.031 94.34 2.92
1055 kota stone slab
1056 @ 2.30kg/cudm = 13.33x2.30
1057 #ERROR!
1058 Dressing charges
1059 LABOUR
Mason (for plain stone work) 2nd
1060 25 class) day 0.059 403.67 22.1
1061 12 Blacksmith 1st class day 0.006 505.17 2.86
1062 17 Beldar day 0.044 350.00 14.12
1063 18 Coolie day 0.022 350.00 7.06
1064 10 Bandhani day 0.044 350.00 14.12
1065 Fixing charges
1066 LABOUR
Mason (for plain stone work) 2nd
1067 25 class) day 0.044 403.67 16.48
1068 12 Blacksmith 1st class day 0.006 505.17 2.86
1069 17 Beldar day 0.022 350.00 7.06
1070 18 Coolie day 0.022 350.00 7.06
1071 10 Bandhani day 0.022 350.00 7.06
1072 11 Bhisti day 0.022 350.00 7.06
1073 9999 Scaffolding
Mortar for laying and pointing Extra L.S. 2.73 2 5.46
1074 9999 labour for lifting
of materials upto floor V level L.S. 8.06 2 16.12
1075 (0.01x1.50 = 0.015)
1076 18 Coolie day 0.015 350.00 4.81
1077 TOTAL 112.13 W
1078 Add 1 % Water charges on "W" 1.1213
1079 TOTAL 113.25 X
1080 15.91
1082 Add GST (multiplying factor 0.1405) 129.16 Y
1084 on "X" 58.24 19.37
1085 TOTAL
Add 15 % Contractor's profit and 472.73 Y 148.53 Z
1086 overheads on "Y" 70.91 1.49
1087 Total 543.64 Z 150.02
1088 Add Cess @ 1% on "Z" 5.44 15.00
1089 Cost of 10 cudm. 549.08 15.00
1090 Cost of 1 cum. 54908
1091 Say 54908
1092 7.15.2 Both faced punched 7.15.2.1
1093 Red sand stone
1094 Details of cost for 10 cudm or 0.01
1095 cum
1096 MATERIAL
1097 1160 Red sand stone block 10 1.333 79 105.31
1098 Finished work@= 33.3%
Add wastage 10 cudm.
= 3.33 cudm. cudm
1099 Total = 13.33
1100 cudm
Carriage of Stone blocks white & red
1101 2216 sand stone & tonne 0.031 94.34 2.92
1102 kota stone slab = 13.33x2.30 = 30.659
@ 2.30kg/cudm
1103 tonne = kg say 0.031 t. Extra labour
0.03065
1104 for lifting of
materials upto floor V level 0.01x1.50
1105 = 0.015
1106 18 Coolie day 0.015 350.00 4.81
1107 Dressing charges
1108 LABOUR
Mason (for plain stone work) 2nd
1109 25 class) day 0.118 403.67 44.19
1110 12 Blacksmith 1st class day 0.012 505.17 5.71
1111 17 Beldar day 0.088 350.00 28.23
1112 18 Coolie day 0.044 350.00 14.12
1113 10 Bandhani day 0.088 350.00 28.23
1114 Fixing charges
1115 LABOUR
Mason (for plain stone work) 2nd
1116 25 class) day 0.044 403.67 16.48
1117 12 Blacksmith 1st class day 0.006 505.17 2.86
1118 17 Beldar day 0.022 350.00 7.06
1119 18 Coolie day 0.022 350.00 7.06
1120 10 Bandhani day 0.022 350.00 7.06
1121 11 Bhisti day 0.022 350.00 7.06
1122 9999 Scafolding L.S. 2.73 2 5.46
1123
1125
1127 9999 Mortar for laying and pointing L.S. 8.06 2 16.12
1128 TOTAL 302.68 W
1129 Add 1 % Water charges on "W" 3.0268
1130 TOTAL
Add GST (multiplying factor 0.1405) 305.71 X
1131 on "X" 42.95
1132 TOTAL
Add 15 % Contractor's profit and 348.66 Y
1133 overheads on "Y" 52.30
1134 Total 400.96 Z
1135 Add Cess @ 1% on "Z" 4.01
1136 Cost of 10 cudm. 404.97
1137 Cost of 1 cum. 40.50
1138 Say 40.50 40496
1139
1140 7.15.2.2 White sand stone
1141 Details of cost for 10 cudm or 0.01
1142 cum
1143 MATERIAL
1144 1161 White sand stone block 10 1.333 205 273.27
1145 Finished work = 10 cudm. cudm
1146 Add wastage @ 33.3% = 3.33 cudm.
1147 Total = 13.33
Carriage cudm.
of Stone blocks white & red
1148 2216 sand stone & tonne 0.031 94.34 2.92
1149 kota stone slab
1150 @ 2.30kg/cudm = 13.33x2.30
1151 #ERROR!
labour for lifting of material upto
1152 floor V level. (0.01
1153 x 1.50 = 0.015)
1154 18 Coolie day 0.015 350.00 4.81
1155 Dressing charges
1156 LABOUR
Mason (for plain stone work) 2nd
1157 25 class) day 0.118 403.67 44.19
1158 12 Blacksmith 1st class day 0.012 505.17 5.71
1159 17 Beldar day 0.088 350.00 28.23
1160 18 Coolie day 0.044 350.00 14.12
1161 10 Bandhani day 0.088 350.00 28.23
1162 Fixing charges
1163 LABOUR
Mason (for plain stone work) 2nd
1164 25 class) day 0.044 403.67 16.48
1165 12 Blacksmith 1st class day 0.006 505.17 2.86
1166 17 Beldar day 0.022 350.00 7.06
1167 18 Coolie day 0.022 350.00 7.06
1168 10 Bandhani day 0.022 350.00 7.06
1169
1171
1173 11 Bhisti day 0.022 350.00 7.06
1174 9999 Scaffolding L.S. 2.73 2 5.46
1175 9999 Mortar for laying and pointing L.S. 8.06 2 16.12
1176 TOTAL 145.45 W
1177 Add 1 % Water charges on "W" 1.4545
1178 TOTAL
Add GST (multiplying factor 0.1405) 146.90 X
1179 on "X" 20.64
1180 TOTAL
Add 15 % Contractor's profit and 167.54 Y
1181 overheads on "Y" 25.13
1182 Total 192.67 Z
1183 Add Cess @ 1% on "Z" 1.93
1184 Cost of 10 cudm. 194.60
1185 Cost of 1 cum. 19.50
1186 Say 19.50 62968
1187 part
1188 thereof.
1189 above
1190 floor
1191 (above
V level
1192 floor
part
1193 their
1194 s
of)above
1195 floor
2.0 = V
1196 0.020)
0017
1197 Beldar day 0.02 350.00 6.42
1198 charges
TOTAL 6.42 W
1199 on "W" 0.06
1200 TOTAL 6.48 X
1201 Add GST (multiplying factor 0.1405) on "X" 0.91
1202 ds
TOTAL
on 7.39 Y
1203 "Y" 1.11
1204 Total 8.5 Z
1% on
1205 "Z"
10 0.09
1206 cudm.
Cost of 8.59
1207 1 cum. 859
1208 Say
1209 punched
1210 in :
1211 lar
1212 pillars
1213 0.01
1214 cum
material
1215 s L.S. 8.97 2 17.94
1216 TOTAL 17.94 W
1217
1219 charges
1221 on "W" 0.18
1222 0.1405)
TOTAL 18.12 X
1223 on "X" 2.55
1224 ds
TOTAL
on 20.67 Y
1225 "Y" 3.1
1226 1%
Total
on 23.76 Z
1227 "Z"
10 0.24
1228 cudm.
Cost of 24
1229 1 cum. 2400
1230 Say 859
1231 on plan
1232 with a
1233 exceedin
1234 g 6 m.
1235 cudm or
1236 0.01 cum
1237 material
1238 s L.S. 6.24 2 12.48
1239 TOTAL 12.48 W
charges
1240 on "W" 0.12
1241 0.1405)
TOTAL 12.6 X
1242 on "X" 1.77
1243 ds
TOTAL
on 14.38 Y
1244 "Y" 2.16
1245 1%
Total
on 16.53 Z
1246 "Z"
10 0.17
1247 cudm.
Cost of 16.7
1248 1 cum. 1670
1249 Say 2400
1250 soffit to
1251 be
1252 measure
1253 d).
1254 for 33.31
1255 sqm
1256 and
1257 carved
1258 (4/3)=53.
1259 28°
1260 2x53.28=
1261 106°
1262 Arc=9.2
1263 5m
1264 MATER
1265 IAL
1266 =0.050cu
1267 m.
1268
1270 Struts-2x1.77x0.1x0.1=0.035cum.
1272 Ribs-
1273 6x1.54x0.23x0.1=0.213cum.
1274 Struts-2x1.72x0.1x0.1=0.034cum.
1275 Total=0.476cum.
1276 For four such frames
1277 #ERROR!
laggings-
1278 75x3.6x0.125x0.075=2.531cum. Tie-
1279 2x3.6x0.225x0.038=0.062cum.
1280 Brace-3x2x2.14x0.225x0.038=0.110
1281 Brace-3x4x3.8x0.225x0.038=0.390
1282 Sleepers-4x3.6x0.20x0.15=0.432
Sleepers-2x4x3.6x0.175x0.075=0.378
1283 Vertical post-
4x4x3.6x0.15x0.15=1.296 Total =
1284 7.103cum.
1285 1197 Second class kail wood in scantling 10 88.79 260 23085.4
1286 cudm
1287 2204 Carriage of Timber Fittings: cum 0.8879 121.29 107.69
1288 3 way straps 50mmx10mm = 32 Nos.
1289 32 no. @0.50cm each==816m
Straps-50mmx10mm Nos.
1290 @0.25cm each = 2m
1291 Total = 18m
18m, wt @ 3.9kg/m = 70.2 kg. =
1292 0.702q
Qty taken l/8th of qty for cost using
1293 once =
1294 0.702/8 = 0.08775 Qtl
1295 1225 Mild
Boltssteel flat strap
160 Nos. fitting
254 mm long 16mm quintal 0.08775 4120 361.53
1296 dia.160x.254xl
1297 .58=64.21
Qty taken kg=0.64q.
l/8th of qty for cost using
1298 once = 0.64/8 =
1299 0.08
BoltsQtl
and nuts upto 300 mm in
1300 1034 length quintal 0.08 6800 384
1301 Carriage of steel = 0.1342t
Qty taken l/8th of qty for cost using
1302 once =
1303 0.1342/8 = 0.01677 t = 0.0168 t
1304 2302 Carriage of G.I.sheet and tonne 0.0168 94.34 1.58
1305 accessories
LABOUR
1306 15 Carpenter 2nd class day 28 403.67 10486
1307 17 Beldar day 24 350.00 7699.92
1308 9999 Sundries
Less Cost of shuttering etc. for an L.S. 134.55 2 269.1
1309 arch
m exceeding
span 6 average of 8 m
i.e. for an
1310 span
1311 5.9.9 Rate as per item cement
SH : Reinforced no 5.9.9concrete
of sqm -33.31 1255.80 -39663.9 A
1312 work
1313 TOTAL 2731.33 W
1314 Add 1 % Water charges on "W-A" 42395.23 423.95
1315 TOTAL
Add GST (multiplying factor 0.1405) 3155.29 X
1316 on "X-A" 42819.18 6016.1
1317
1318
1320
1322 ds
TOTAL
on 9171.38 Y
1323 "Y- 48835.28 7325.29
1324 A"
1325 1%
Total
on 16496.67 Z
1326 "Z-A"
33.31sq 56160.57 561.61
1327 soffit
m. 17058.28
1328 area 512.11
1329 Say 1670
1330 stone
1331 shade :
1332 sand
1333 stone
1334 Details of cost for 10 cudm or 0.01
1335 cum
1336 MATERIAL
1337 Finished work = 10 cudm.
1338 Add wastage @ 33.3% = 3.33 cudm.
1339 Total = 13.33 cudm.
1340 1160 Red sand stone block 10 1.333 79 105.31
1341 Carriage of Stone blocks white & red cudm
1342 2216 sand stone & tonne 0.031 94.34 2.92
1343 kota stone slab = 13.33x2.30 = 30.659
@ 2.30kg/cudm
1344 kg =
1345 0.03065 tonne say 0.031 t.
1346 9999 Extra for using white cement L.S. 8.06 2 16.12
1347 Dressing charges
1348 LABOUR
Mason (for plain stone work) 2nd
1349 25 class) day 0.291 403.67 108.98
1350 12 Blacksmith 1st class day 0.006 505.17 2.86
1351 17 Beldar day 0.044 350.00 14.12
1352 18 Coolie day 0.022 350.00 7.06
1353 10 Bandhani day 0.044 350.00 14.12
1354 Fixing charges
1355 LABOUR
Mason (for plain stone work) 2nd
1356 25 class) day 0.044 403.67 16.48
1357 12 Blacksmith 1st class day 0.006 505.17 2.86
1358 17 Beldar day 0.022 350.00 7.06
1359 18 Coolie day 0.022 350.00 7.06
1360 10 Bandhani day 0.022 350.00 7.06
1361 11 Bhisti day 0.022 350.00 7.06
1362 9999 Scaffolding L.S. 2.73 2 5.46
1363
1365 Mortar for laying and pointing Extra
1367 9999 labour for lifting
of materials upto floor V level L.S. 8.06 2 16.12
1368 (0.01x1.50=0.015)
1369 18 Coolie day 0.015 350.00 4.81
1370 TOTAL 95.15 W
1371 Add 1 % Water charges on "W" 0.9515
1372 TOTAL
Add GST (multiplying factor 0.1405) 96.10 X
1373 on "X" 13.50
1374 TOTAL
Add 15 % Contractor's profit and 109.60 Y
1375 overheads on "Y" 16.44
1376 Total 126.04 Z
1377 Add Cess @ 1% on "Z" 1.26
1378 Cost of 10 cudm. 127.30
1379 Cost of 1 cum. 12.70
1380 Say 12.70 46217
1381 7.20.2 White
Detailssand stone
of cost for 10 cudm or 0.01
1382 cum
1383 MATERIAL
1384 Finished work = 10 cudm.+
1385 Add wastage @ 33.3% = 3.33 cudm.
1386 Total = 13.33 cudm.
1387 1161 White sand stone block 10 1.333 205 273.27
1388 Carriage of Stone blocks white & red cudm
1389 2216 sand stone & tonne 0.031 94.34 2.92
1390 kota stone slab = 13.33x2.30=30.659
@ 2.30kg/cudm
1391 kg = 0.03065
1392 tonne say 0.031t.
1393 9999 Extra for using white cement L.S. 8.06 2 16.12
1394 Dressing charges
1395 LABOUR
Mason (for plain stone work) 2nd
1396 25 class) day 0.291 403.67 108.98
1397 12 Blacksmith 1st class day 0.006 505.17 2.86
1398 17 Beldar day 0.044 350.00 14.12
1399 18 Coolie day 0.022 350.00 7.06
1400 10 Bandhani day 0.044 350.00 14.12
1401 Fixing charges
1402 LABOUR
Mason (for plain stone work) 2nd
1403 25 class) day 0.044 403.67 16.48
1404 12 Blacksmith 1st class day 0.006 505.17 2.86
1405 17 Beldar day 0.022 350.00 7.06
1406 18 Coolie day 0.022 350.00 7.06
1407
1408
1410
1412 10 Bandhani day 0.022 350.00 7.06
1413 11 Bhisti day 0.022 350.00 7.06
1414 9999 Scaffolding L.S. 2.73 2 5.46
1415 9999 Mortar for laying
Extra labour and pointing
for lifting of materials L.S. 8.06 2 16.12
1416 upto floor V
1417 level0.01x1.50=0.015
1418 18 Coolie day 0.015 350.00 4.81
1419 TOTAL 73.97 W
1420 Add 1 % Water charges on "W" 0.7397
1421 TOTAL
Add GST (multiplying factor 0.1405) 74.71 X
1422 on "X" 10.50
1423 TOTAL
Add 15 % Contractor's profit and 85.21 Y
1424 overheads on "Y" 12.78
1425 Total 97.99 Z
1426 Add Cess @ 1% on "Z" 0.98
1427 Cost of 10 cudm. 98.97
1428 Cost of 1 cum. 9.90
1429 Say 9.90 68689
1430 carved
1431 in :
1432 lar
1433 pillars
1434 Details of cost for 10 cudm or 0.01
1435 cum
1436 9999 LABOUR L.S. 11.7 2 23.4
1437 TOTAL 424.34 W
1438 Add 1 % Water charges on "W" 4.243388
1439 TOTAL
Add GST (multiplying factor 0.1405) 428.58 X
1440 on "X" 60.22
1441 TOTAL
Add 15 % Contractor's profit and 488.80 Y
1442 overheads on "Y" 73.32
1443 Total 562.12 Z
1444 Add Cess @ 1% on "Z" 5.62
1445 Cost of 10 cudm. 567.74
1446 Cost of 1 cum. 56.80
1447 polygon Say 56.80 3131
1448 al pillars Details of cost for 10 cudm or 0.01
1449 cum
1450 9999 LABOUR L.S. 33.15 2 66.3
1451 TOTAL 2818.29 W
1452 28.182909
1454 charges 2846.47 X
1456 on "W" 0.66 399.93
1457 0.1405)
TOTAL 66.96 X 3246.40 Y
1458 on "X" 9.41 486.96
1459 ds
TOTAL
on 76.37 Y 3733.36 Z
1460 "Y" 11.46 37.33
1461 1%
Total
on 87.83 Z 3770.69
1462 "Z"
10 0.88 377.10
1463 cudm.
Cost of 88.71 377.10
1464 1 cum. 8871
1465 Say 512.1
1466 cornices
1467 .
1468 60cm
1469 n
deep
Extra
1470 labour
2nd :
1471 class)
0017 day 0.5 403.67 187.25
1472 Beldar day 0.75 350.00 240.62
1473 charges
TOTAL 427.87 12456.82 W
1474 on "W" 4.28 124.56822
1475 0.1405)
TOTAL 432.15 12581.39 X
1476 on "X" 60.72 1767.69
1477 ds
TOTAL
on 492.87 14349.08 Y
1478 "Y" 73.93 2152.36
1479 1%
Total
on 566.8 16501.44 Z
1480 "Z" 5.67 165.01
15cm
1481 girth
per cm 572.47 16666.45
1482 girth 127.21 1666.60
1483 Say 1666.60 8871
1484 radius
1485 not
1486 exceedin
1487 g 6 m.
1488 for 10
1489 cudm.
1490 material
1491 s L.S. 8.97 2 17.94
1492 charges
TOTAL 17.94 54953.17 W
1493 on "W" 0.18 549.53169
1494 55502.70 X
1496 7798.13
1498 0.1405)
TOTAL 18.12 63300.83 Y
1499 on "X" 2.55 9495.12
1500 ds
TOTAL
on 20.67 72795.95 Z
1501 "Y" 3.1 727.96
1502 1%
Total
on 23.76 73523.91
1503 "Z"
10 0.24 7352.40
1504 cudm.
Cost of 24 7352.40
1505 1 cum. 2400
1506 Say 127.2
1507 includin
1508 g
1509 necessar
1510 y chases.
1511 for one
1512 dowel
1513
1514 9999 Cost of for
Labour stone including
dressing carriage
dowel cutting L.S. 9.1 2 18.2
1515 9999 chase and fixing L.S. 5.33 2 10.66
1516 etc.
Cement mortar 1:2 (1 cement : 2
1517 coarse
Rate assand)
per Item Number 3.7 of SH:
1518 3.7 Mortars cum 0.001 4722.70 5.15
1519 TOTAL 14738.81 W
1520 Add 1 % Water charges on "W" 147.3881
1521 TOTAL
Add GST (multiplying factor 0.1405) 14886.20 X
1522 on "X" 2091.51
1523 TOTAL
Add 15 % Contractor's profit and 16977.71 Y
1524 overheads on "Y" 2546.66
1525 Total 19524.37 Z
1526 Add Cess @ 1% on "Z" 195.24
1527 Cost of each dowel 19719.61
1528 Say 1972.00 45.5
1529 stone 1972.00
1530 shade :
1531 sand
1532 stone :
1533 designati
1534 on 7.5
1535 (finished
1536 work)
1537
1539
1541 MATERIAL
Chisel dressed 80cm sloping length
1542 plus
20cm bearing Area =
1543 2.5xl.00=2.50sqm
Red sand stone slab 40 mmthick (un-
1544 1164 dressed)
Carriage of Stone blocks white & red sqm 2.75 400 550
1545 2216 sand stone & tonne 0.253 94.34 23.87
1546 kota stone slab @ 2.3kg/cudm.
1547 Labour for dressing:
Mason (for plain stone work) 2nd
1548 25 Mild steel round bar 12 mm dia and day
class) 0.5 403.67 187.25
1549 1002 below
Cutting threads and cost of nuts, quintal 0.02 5500 90
1550 9999 washers, etc. L.S. 67.34 2 134.68
Mortar for pointing 1:2 (1 Cement : 2
1551 Stone
Rate asdust)
per Item Number 3.12 of SH:
1552 3.12 Mortars cum 0.009 4552.80 44.22
1553 9999 Pigment L.S. 6.24 2 12.48
1554 9999 Extra cost of white cement L.S. 26.91 2 53.82
1555 LABOUR
Mason (for plain stone work) 2nd
1556 25 class) day 1 403.67 374.5
1557 17 Beldar day 1.5 350.00 481.25
1558 9999 Scaffolding
Brick cover and sundries
support etc. with
4 courses L.S. 16.12 2 32.24
1559 bricks of class
1560 designation 75
1561 4x7+5+5=38cm girth 2.5m length
1562 #ERROR!
1563 9999 Cost
Brickof Brick
work in cover support.
triangular gap above L.S. 104 2 208
1564 cover with bricks
1565 of class designation 7.5 in
1566 cement mortar 1:4
1567 1/2x2.5x0.2x0.07=0.018cum.
Rate as per item No 6.4.1 of SH :-
1568 6.4.1 Brick work. cum 0.018 6382.9 114.89 A
1569 TOTAL 2307.19 W
1570 Add 1 % Water charges on "W-A" 2192.3 21.92
1571 TOTAL
Add GST (multiplying factor 0.1405) 2329.12 X
1572 on "X" 2214.22 311.1
1573 TOTAL
Add 15 % Contractor's profit and 2640.21 Y
1574 overheads on "Y" 2525.32 378.8
1575 Total 3019.01 Z
1576 Add Cess @ 1% on "Z" 2904.12 29.04
1577 Cost of 2 sqm. 3048.05
1578 Cost of 1 sqm. 1524.03
1579 Say 1524.05
1580 sand
1581 stone :
1582 designati
1583 on 7.5
1584 2.00
1585 sqm.
1586
1588
1590 (finished work)
1591 MATERIAL
Chisel dressed 80cm sloping length
1592 plus
20cm bearing Area =
1593 2.5x1.00=2.50sqm
White sand stone slab 40 mm thick
1594 1165 (un-dressed)
Carriage of Stone blocks white & red sqm 2.75 280 550
1595 2216 sand stone & tonne 0.253 94.34 23.87
1596 kota stone slab @ 2.3kg/cudm.
1597 Labour
Mason (forfor dressing:
plain stone work) 2nd
1598 25 class) Labour for day 0.5 403.67 187.25
1599 dressing:
Anchoring steel bars 12mm dia.
1600 45cm long
1601 5 Nos.
Mild @ 0.80kg/m
steel round bar= 12
0.02q
mm dia and
1602 1002 below
Cutting threads and cost of nuts, quintal 0.02 5500 90
1603 washers,
9999 Mortar foretc.
pointing 1:2 (1 Cement : 2 L.S. 67.34 2 134.68
1604 Stone dust)
Rate as per Item Number 3.12 of SH:
1605 3.12 Mortars cum 0.009 4552.80 44.22
1606 9999 Pigment L.S. 6.24 2 12.48
1607 9999 Extra cost of white cement L.S. 26.91 2 53.82
1608 LABOUR
Mason (for plain stone work) 2nd
1609 25 class) day 1 403.67 374.5
1610 17 Beldar day 1.5 350.00 481.25
1611 9999 Scaffolding
Brick cover and sundries
support etc. with
4 courses L.S. 16.12 2 32.24
1612 bricks of class
1613 designation 75
1614 4x7+5+5=38cm girth 2.5m length
1615 #ERROR!
1616 9999 Cost
Brickfor
workBrick cover support
in triangular .
gap above L.S. 104 2 208
1617 cover with bricks
1618 of class designation 5 in
1619 cement mortar 1:4
1620 1/2x2.5x0.2x0.07=0.018cum.
Rate as per item No 6.4.1 of SH :-
1621 6.4.1 Brick work. cum 0.018 6382.9 114.89 A
1622 TOTAL 2307.19 W
1623 Add 1 % Water charges on "W-A" 2192.3 21.92
1624 TOTAL
Add GST (multiplying factor 0.1405) 2329.12 X
1625 on "X-A" 2214.22 311.1
1626 TOTAL
Add 15 % Contractor's profit and 2640.21 Y
1627 overheads on "Y- 2525.32 378.8
1628 A"
1629 Total 3019.01 Z
1630 Add Cess @ 1% on "Z-A" 2904.12 29.04
1631 Cost of 2 sqm. 3048.05
1632 Cost of 1 sqm. 1524.03
1633 Say 1524.05
1634
1635
1637
1639 stone
1640 shade :
1641 sand
1642 stone
1643 Details of cost for (2.5x0.75m) 1.875
1644 sqm.
1645 MATERIAL
1646 Taking 2.5mx75cm projection +
1647 15cm bearing
Red sand = 2.5x0.9
stone slab 40 =mmthick
2.25 sqm.
(un-
1648 1164 dressed)
Carriage of Stone blocks white & red sqm 2.25 400 450
1649 2216 sand stone & tonne 0.227 94.34 21.41
1650 kota stone slab @ 2.3kg/cudm.
1651 Labour for dressing:
Mason (for plain stone work) 2nd
1652 25 class) day 0.45 403.67 168.53
1653 9999 Mortar for pointing 1:2 L.S. 53.82 2 107.64
1654 9999 Pigment L.S. 6.24 2 12.48
1655 9999 Extra cost of white cement L.S. 26.91 2 53.82
1656 LABOUR
Mason (for plain stone work) 2nd
1657 25 class) day 0.6 403.67 224.7
1658 17 Beldar day 0.8 350.00 256.66
1659 9999 Scaffolding and sundries etc. L.S. 13.52 2 27.04
1660 TOTAL 1322.28 W
1661 Add 1 % Water charges on "W" 13.2228
1662 TOTAL
Add GST (multiplying factor 0.1405) 1335.50 X
1663 on "X-A" 187.64
1664 TOTAL
Add 15 % Contractor's profit and 1523.14 Y
1665 overheads on "Y-A" 228.47
1666 Total 1751.61 Z
1667 Add Cess @ 1% on "Z-A" 17.52
1668 Cost of 1.875 sqm. 1769.13
1669 Cost of 1 sqm. 176.90
1670 Say 176.90 943.55
1671 7.29.2 White
Detailssand stone
of cost for (2.5x0.75m) 1.875
1672 sqm.
1673 MATERIAL
1674 Taking 2.5mx75cm projection +
1675 15cm
White bearing = 2.5x0.9
sand stone = 2.25
slab 40 sqm.
mm thick
1676 1165 (un-dressed)
Carriage of Stone blocks white & red sqm 2.25 280 450
1677 2216 sand stone & tonne 0.227 94.34 21.41
1678 kota stone slab @ 2.3kg/cudm.
1679
1680
1682
1684 Labour for dressing:
Mason (for plain stone work) 2nd
1685 25 class) day 0.45 403.67 168.53
1686 9999 Mortar for pointing 1:2 L.S. 53.82 2 107.64
1687 9999 Pigment L.S. 6.24 2 12.48
1688 9999 Extra cost of white cement L.S. 26.91 2 53.82
1689 LABOUR
Mason (for plain stone work) 2nd
1690 25 class) day 0.6 403.67 224.7
1691 17 Beldar day 0.8 350.00 256.66
1692 9999 Scaffolding and sundries etc. L.S. 13.52 2 27.04
1693 TOTAL 1322.28 W
1694 Add 1 % Water charges on "W" 13.2228
1695 TOTAL
Add GST (multiplying factor 0.1405) 1335.50 X
1696 on "X" 187.64
1697 TOTAL
Add 15 % Contractor's profit and 1523.14 Y
1698 overheads on "Y" 228.47
1699 Total 1751.61 Z
1700 Add Cess @ 1% on "Z" 17.52
1701 Cost of 1.875 sqm. 1769.13
1702 Cost of 1 sqm. 176.90
1703 Say 176.90 943.55
1704 cement :
1705 4 coarse
1706 complete
1707 .
1708 and
1709 0.70m
1710 1.12
1711 sqm.
1712 MATER
1713 IAL
1714 Total
1715 area =
1716 =1.36sq
1717 m.
1718 30mm
1719 average
1720 0.53+0.2
1721 3=0.76m
1722 2x0.3x0.
1723 76=0.46
1724 wastage
1725 @10% =
1726
1727 0.18sqm.
1728 2.00
1729 sqm.
1730 Red sand stone slab 30 mmthick (un-
1731 1166 dressed)
Carriage of Stone blocks white & red sqm 2 300 400
1732 2216 sand stone & tonne 0.14 94.34 13.21
1733 kota stone slab
1734 9999 Cement mortar 1 :4 L.S. 13.52 2 27.04
1735 Labour for dressing and fixing:
1736 LABOUR
Mason (for plain stone work) 2nd
1737 25 class) day 0.86 403.67 322.07
1738 17 Beldar day 0.5 350.00 160.42
1739
1741
1742
1743 30 cm
long and
1744 Details of
cost for 1
1745
1747 charges
TOTAL 922.73 922.74 W
1748 on "W" 9.23 9.2274
1749 0.1405)
TOTAL 931.96 931.97 X
1750 on "X" 130.94 130.94
1751 ds
TOTAL
on 1062.9 1062.91 Y
1752 "Y" 159.43 159.44
1753 1%
Total
on 1222.33 1222.35 Z
1754 "Z"
1.12 12.22 12.22
1755 sqm.
Cost of 1234.56 1234.57
1756 1 sqm. 1102.28 123.50
1757 Say 123.50 2400
1758 25x6
1759 mm
1760
1761 Quantity of stone
1 x 55 x 22.5 for=10.056cum
x 45cm bracket or
1762 56 cudm.
1763 Red sand stone = 56 cudm.
1764 Add wastage 10% = 5.6 cudm. Total #ERROR!
1765 61.6 cudm.
1766 1160 Red sand stone block 10 6.16 79 486.64
1767 Carriage of Stone blocks white & red cudm
1768 2216 sand stone & tonne 0.14 94.34 13.21
1769 kota stone slab @ 2.3kg/ cudm.
1770 Dressing charges
1771 LABOUR
Mason (for plain stone work) 2nd
1772 25 class) day 1.7926 403.67 671.33
1773 12 Blacksmith 1st class day 0.037 505.17 17.61
1774 17 Beldar day 0.271 350.00 86.94
1775 18 Coolie day 0.1355 350.00 43.47
1776 10 Bandhani day 0.271 350.00 86.94
1777 373 Cramp Gun metal 25x6x300 mm each 4 80 320
1778 Fixing charges
1779 LABOUR
Mason (for plain stone work) 2nd
1780 25 class) day 0.2464 403.67 92.28
1781 12 Blacksmith 1st class day 0.0336 505.17 15.99
1782 17 Beldar day 0.1232 350.00 39.53
1783 18 Coolie day 0.1232 350.00 39.53
1784 10 Bandhani day 0.1232 350.00 39.53
1785 11 Bhisti day 0.1232 350.00 39.53
1786
1788
1790 9999 Scaffolding L.S. 15.29 2 30.58
1791 9999 Mortar for laying and pointing L.S. 45.14 2 90.28
1792 Extra
Masonlabour for ornamental
(for ornamental stonefinish
work):
1793 26 1st class day 0.95 505.17 452.2
1794 TOTAL 1246.39 W
1795 Add 1 % Water charges on "W" 12.4639
1796 TOTAL
Add GST (multiplying factor 0.1405) 1258.85 X
1797 on "X" 176.87
1798 TOTAL
Add 15 % Contractor's profit and 1435.72 Y
1799 overheads on "Y" 215.36
1800 Total 1651.08 Z
1801 Add Cess @ 1% on "Z" 16.51
1802 Cost for 1 Bracket 1667.59
1803 Say 166.80 3432.6
1804 stone 166.80
1805 shade.
1806 sand
1807 stone
1808 6.75cud
1809 m.
1810 MATER
1811 IAL
1812
1813 Stone work plain ashlar cyclopean
1814 3x3x0.75 = 6.75
Rate as per itemcudm
no 7.12.1.1 of SH :
1815 7.12.1.1 Stone Work cum 0.00675 33889 228.75 A
1816 9999 Extra for using white cement L.S. 5.33 2 10.66
1817 Extra
Masonlabour for making
(for plain the cornices
stone work) 2nd
1818 25 class) day 0.07 403.67 26.22
1819 17 Beldar day 0.07 350.00 22.46
1820 TOTAL 288.08 W
1821 Add 1 % Water charges on "W-A" 59.33 0.59
1822 TOTAL
Add GST (multiplying factor 0.1405) 288.68 X
1823 on "X-A" 59.93 8.42
1824 TOTAL 297.1 Y
Add 15 % Contractor's profit and
1825 overheads on "Y- 68.35 10.25
1826 A"
1827 Total 307.35 Z
1828 Add Cess @ 1% on "Z-A" 78.6 0.79
1829 Cost of 6.75 cudm 308.13
1830
1832 Cost per
1834 cum. 45648.89
1835 Say 1102.3
1836
1837 7.32.2 White
Detailssand stone
of cost for cornices (30cm
1838 long 30cm deep
1839 and 7.5cm project-iron) = 6.75cudm.
1840 MATERIAL
1841 Stone work plain ashlar cyclopean
1842 3x3x0.75
Rate as per= 6.75
itemcudm
no 7.12.2 of SH :
1843 7.12.1.2 Stone Work cum 0.00675 56361 380.44 A
1844 9999 Extra for using white cement L.S. 5.33 2 10.66
1845 Extra
Masonlabour for making
(for plain the cornices
stone work) 2nd
1846 25 class) day 0.07 403.67 26.22
1847 17 Beldar day 0.07 350.00 22.46
1848 TOTAL 439.77 W
1849 Add 1 % Water charges on "W-A" 59.33 0.59
1850 TOTAL
Add GST (multiplying factor 0.1405) 440.36 X
1851 on "X-A" 59.93 8.42
1852 TOTAL
Add 15 % Contractor's profit and 448.78 Y
1853 overheads on "Y- 68.35 10.25
1854 A"
1855 Total 459.03 Z
1856 Add Cess @ 1% on "Z-A" 78.6 0.79
1857 Cost of 6.75 cudm 459.82
1858 Cost per cum. 68121.48
1859 Say 68121.5
1860 chamfer
1861 s etc.
1862 sand
1863 stone
1864
1865 Details of cost for 1 sqm
1866 MATERIAL
Red sand stone slab 40mm = 1.00
1867 sqm Add 10%
1868 wastage = 0.10 sqm.
1869 Total = 1.10
Red sand sqm.slab 40 mm thick
stone
1870 1164 (un-dressed)
Carriage of Stone blocks white & red sqm 1.1 400 220
1871 2216 sand tonne 0.101 94.34 9.53
1872 stone & kota stone slab
1873 LABOUR
1874 For making, dressing and fixing
1875
1877 Mason (for plain stone work) 2nd
1879 25 class) day 7.62 403.67 2853.69
1880 17 Beldar day 5.07 350.00 1626.61
1881 9999 Mortar and Sundries L.S. 80.73 2 161.46
1882 TOTAL 4871.29 W
1883 Add 1 % Water charges on "W" 48.7129
1884 TOTAL
Add GST (multiplying factor 0.1405) 4920.00 X
1885 on "X" 691.26
1886 TOTAL
Add 15 % Contractor's profit and 5611.26 Y
1887 overheads on "Y" 841.69
1888 Total 6452.95 Z
1889 Add Cess @ 1% on "Z" 64.53
1890 Cost of 1 sqm. 6517.48
1891 Say 651.70 6517.5
1892 7.33.2 White sand stone 651.70
1893 Details of cost for 1 sqm
1894 MATERIAL
White sand stone slab 40mm = 1.00
1895 sqm Add 10%
1896 wastage = 0.10 sqm.
1897 Total
White=sand
1.10 stone
sqm. slab 40 mm thick
1898 1165 (un-dressed)
Carriage of Stone blocks white & red sqm 1.1 280 220
1899 2216 sand stone & tonne 0.101 94.34 9.53
1900 kota stone slab
1901 LABOUR
1902 For making,
Mason dressing
(for plain stoneand fixing
work) 2nd
1903 25 class) day 7.62 403.67 2853.69
1904 17 Beldar day 5.07 350.00 1626.61
1905 9999 Mortar and Sundries L.S. 80.73 2 161.46
1906 TOTAL 12692.17 W
1907 Add 1 % Water charges on "W" 126.92173
1908 TOTAL
Add GST (multiplying factor 0.1405) 12819.09 X
1909 on "X" 1801.08
1910 TOTAL
Add 15 % Contractor's profit and 14620.17 Y
1911 overheads on "Y" 2193.03
1912 Total 16813.20 Z
1913 Add Cess @ 1% on "Z" 168.13
1914 Cost of 1 sqm. 16981.33
1915 Say 1698.10 6517.5
1916 complet 1698.10
1917 e.
1918
1920
1922 0.05 m
1923 ignored.
1924 water
1925 0.30m.
1926
1927 Quantity of concrete = 14 cum.
1928 pumping hours
Hire charges of = 3 hrs. on
Pumpset of0.375day.
capacity
1929 11 4000 day 0.375 700 262.5
1930 litres/hour.
1931 17 Beldar day 4 350.00 1283.32
1932 for cleaning slush 1545.82 W
1933 TOTAL 6487.84 W
1934 Add 1 % Water charges on "W" 64.8784
1935 TOTAL
Add GST (multiplying factor 0.1405) 6552.72 X
1936 on "X" 920.66
1937 TOTAL
Add 15 % Contractor's profit and 7473.38 Y
1938 overheads on "Y" 1121.01
1939 Total 8594.39 Z
1940 Add Cess @ 1% on "Z" 85.94
1941 Cost of 14cum. per 0.30m depth 8680.33
1942 Cost of cum. per m depth 868.00
1943 Say 868.00 492.45
1944 foul
1945 position.
1946
1947 Details of cost for 1 cum.
1948 Extra labour due to slow progress-
1949 23 Mason (brick layer) 1st class day 0.02 505.17 9.52
1950 24 Mason (brick layer) 2nd class day 0.02 403.67 7.49
1951 17 Beldar day 0.25 350.00 80.21
1952 18 Coolie day 0.15 350.00 48.12
1953 TOTAL 27836.39 W
1954 Add 1 % Water charges on "W" 278.36385
1955 TOTAL
Add GST (multiplying factor 0.1405) 28114.75 X
1956 on "X" 3950.12
1957 TOTAL
Add 15 % Contractor's profit and 32064.87 Y
1958 overheads on "Y" 4809.73
1959 36874.60 Z
1961 368.75
1963 1%
Total
on 192.53 37243.35
1964 "Z" 1.93 3724.30
1965 Cost for 3724.30
1966 1 cum. 194.46
1967 Say 45648.9
1968 -in-
1969 charge.
1970 40mm
1971 thick
1972 face =
1973 1.00sqm.
1974 .0 = 0.12
1975 sqm.
1976
1977 #ERROR!
1978 Add wastage 5% = 0.04sqm.
1979 Total #ERROR!
1980 1165 White sand stone slab 40 mm thick sqm 0.92 280 184
1981 (un-dressed)
1982 75mm thick
1983 3x0.04x1.0 = 0.12 sqm.
1984 Add wastage 5% = 0.01 sqm.
1985 Total
White sand stone slab 75 mm thick #ERROR!
1986 1163 (un-dressed)
Carriage of Stone blocks white & red sqm 0.13 900 117
1987 2216 sand stoneslab
kota stone & 0.92x0.04 = 0.0368 tonne 0.108 94.34 10.19
1988 cum.
1989 0.13x0.075 = 0.0100 cum.
1990 #ERROR!
1991 468 cudm @ 2.3 kg/cudm = 108 kg
1992 #ERROR!
Cutting marble or sand stone slab
1993 1237 upto 50 mm thick metre 20 10 200
1994 by mechanical device
1995 Assuming 50mm thick strips 20x1.0
1996 #ERROR!
1997 Mortar with coarse sand 1:3 for
(a) stone backing 12mm thick =
1998 0.0144 cum. of stone = 0.40/25 =
(b) for fixing
1999 0.0160 cum.
2000 Total
Rate as= 0.0304 cum.
per Item Number 3.8 of SH:
2001 3.8 chases and making good with mortar cum
Mortars Cutting 0.0304 4129.00 135.87
2002 after insurting
2003 stone
Rate asetc.
per Item Number 18.78 of
2004 18.78 SH: Water metre 3 97.7 293.11 A
2005
2007 White cement and pigment for
2009 9999 pointing L.S. 40.43 2 80.86
2010 LABOUR
Mason (for ornamental stone work)
2011 26 1st
Masonclass
(for plain stone work) 2nd day 0.25 505.17 119
2012 25 class) day 0.25 403.67 93.63
2013 17 Beldar day 0.5 350.00 160.42
2014 11 Bhisti
Sundries and scaffolding brushes day 0.03 350.00 9.62
2015 9999 etc. L.S. 26.91 2 53.82
2016 TOTAL 1457.52 W
2017 Add 1 % Water charges on "W-A" 1164.41 11.64
2018 TOTAL
Add GST (multiplying factor 0.1405) 1469.16 X
2019 on "X-A" 1176.05 165.24
2020 TOTAL
Add 15 % Contractor's profit and 1634.39 Y
2021 overheads on "Y- 1341.29 201.19
2022 A"
2023 Total 1835.59 Z
2024 Add Cess @ 1% on "Z-A" 1542.48 15.42
2025 Cost of 1sqm. 1851.01
2026 Say 1851
2027 the
2028 stone
2029
2030 shade. 1137.8
2031 and
2032 shade
2033
2034 Details of cost for 10sqm.
2035 MATERIAL
2036 Granite
Add 2.5% stone tile ==10.00sqm.
wastage 0.25sqm. Total
2037 =10.25 sqm
2038 2750 8 mm thick granite stone tiles sqm 10.25 700 7175
2039 (mirror polished of all shades)
2040 9977 Carriage of granite
Cement mortar tiles
1:3 (1 cement : 3 L.S. 40.04 2 80.08
2041 coarse sand)
Rate as per Item Number 3.8 of SH:
2042 3.8 Mortars
Portland Cement slurry @ 3.3 cum 0.14 4129.00 625.73
2043 367 kg/sqm tonne 0.033 4375 163.02
2044 9999 Mortar for pointing in white cement L.S. 25.74 2 51.48
2045 LABOUR
2046 Labour for placing and fixing :
2047 23 Mason (brick layer) 1st class day 7.7 505.17 3665.2
2048
2050
2052 17 Beldar
Granular sand particles mixed with day 7.7 350.00 2470.39
2053 9999 araldite
pasted onto each
be side to form L.S. 260 2 520
2054 interlocking
2055 arrangement with cement plaster
2056 9999 Sundries L.S. 171.6 2 343.2
2057 TOTAL 7919.10 W
2058 Add 1 % Water charges on "W" 79.191
2059 TOTAL
Add GST (multiplying factor 0.1405) 7998.29 X
2060 on "X" 1123.76
2061 TOTAL
Add 15 % Contractor's profit and 9122.05 Y
2062 overheads on "Y" 1368.31
2063 Total 10490.36 Z
2064 Add Cess @ 1% on "Z" 104.90
2065 Cost for 10 sqm. 10595.26
2066 Cost of 1 sqm. 1059.50
2067 Say 1059.50 2019.5
2068 black
2069 marble
2070
2071 Details of cost for 10sqm.
2072 MATERIAL
2073 8mm thick Raj Nagar white stone tile
2074 #ERROR!
Add 2.5% wastage = 0.25sqm. Total
2075 =
8mm10.25sqm
thick (mirror polished tiles
2076 7439 machine cut edge) sqm 10.25 500 5125
2077 Raj Nagarofwhite
Carriage Raj Nagar white stone
2078 9977 tiles
Cement mortar 1:3 (1 cement : 3 L.S. 40.04 2 80.08
2079 coarse
Rate assand)
per Item Number 3.8 of SH:
2080 3.8 Mortars
Portland Cement slurry @ 3.3 cum 0.14 4129.00 625.73
2081 367 kg/sqm
Mortar for pointing in white cement tonne 0.033 4375 163.02
2082 9999 Labour for L.S. 25.74 2 51.48
2083 placing and fixing :
2084 23 Mason (brick layer) 1st class day 7.7 505.17 3665.2
2085 17 Beldar
Granular sand particles mixed with day 7.7 350.00 2470.39
2086 9999 araldite
pasted on to each
be side to form L.S. 260 2 520
2087 interlocking
2088 arrangement with cement plaster
2089 9999 Sundries L.S. 171.6 2 343.2
2090 TOTAL 13044.10 W
2091 Add 1 % Water charges on "W" 130.441
2092 TOTAL
Add GST (multiplying factor 0.1405) 13174.54 X
2093 on "X" 1851.02
2094 TOTAL 15025.56 Y
2095 2253.83
2097 ds on 17279.39 Z
2099 "Y" 2253.83 172.79
2100 1%
Total
on 17279.4 17452.18
2101 "Z"
Cost for 172.79 1745.20
2102 10 sqm. 17452.19 1745.20
Cost of
2103 1 sqm. 1745.22
2104 Say 194.45
2105
2106
2108 HEAD :
2109 8.0
2110 TE
2111 WORK
2112
2114 which
2115 shall be
2116 separatel
2117 y).
2118 black
2119 marble.
2120 upto
2121 0.50 sqm
2122
2123 Details of cost for 0.50 sqm.
2124 MATERIAL
2125 Finished work = 0.50sqm.
2126 Add for wastage @ 20% = 0.10 sqm.
2127 Total = 0.60
Raj nagar sqm.
plain white marble (table
2128 7452 rubbed and
polished) 18 mm thick (slab area sqm 0.6 575 345
2129 upto 0.50of
Carriage sqm)
Stone blocks white & red
2130 2216 stone
sand & kota stone slab Cement tonne 0.03 94.34 2.83
2131 mortar 1:3 (1 cement
2132 :Rate
3 coarse
as persand)
Item Number 3.8 of SH:
2133 3.8 Mortars
White cement mortar 1:2 (1 white cum 0.008 4129.00 35.76
2134 cement :
2135 2 marble
Rate dust)
as per Item Number 3.15 of SH:
2136 3.15 Mortars cum 0.0012 9222.30 11.04
2137 LABOUR
2138 For fixing
Mason (for ornamental stone work)
2139 26 1st class day 0.335 505.17 159.46
2140 10 Bandhani day 0.335 350.00 107.48
2141 17 Beldar day 0.335 350.00 107.48
2142 18 Coolie day 0.335 350.00 107.48
2143 11 Bhisti day 0.335 350.00 107.48
2144 28 Mate day 0.165 350.00 52.94
2145 12 Blacksmith 1st class day 0.135 505.17 64.26
2146 9999 Scaffolding L.S. 13.39 2 26.78
2147 TOTAL 780.16 W
2148 Add 1 % Water charges on "W" 7.8016
2149 TOTAL
Add GST (multiplying factor 0.1405) 787.96 X
2150 on "X" 110.71
2151 TOTAL
Add 15 % Contractor's profit and 898.67 Y
2152 overheads on "Y" 134.80
2153 1033.47 Z
2155 10.33
2157 Total 1043.80
2158 Add Cess @ 1% on "Z" 104.40
2159 Cost for 0.50 sqm. 104.40
2160 Cost for one sqm. 3018.32
2161 0.50 Say 3018.3
2162 sqm
2163 Details of cost for 1.00 sqm.
2164 MATERIAL
2165 Finished work = 1.00 sqm.
2166 Add for wastage @ 20% = 0.20 sqm.
2167 Total = 1.20
Raj nagar sqm.
plain white marble (table
2168 7453 rubbed and
polished) 18 mm thick (slab area sqm 1.2 690 828
2169 more than 0.50
2170 sqm)
Carriage of Stone blocks white & red
2171 2216 sand tonne 0.06 94.34 5.66
2172 stone & kota stone slab
Cement mortar 1:3 (1 cement : 3
2173 coarse sand)
2174 3.8 Rate as per Item Number 3.8 of cum 0.0144 4129.00 64.36
2175 SH: Mortars
White cement mortar 1:2 (1 white
2176 cement :
2177 2 marble dust)
2178 3.15 Rate as per Item Number 3.15 of cum 0.0025 9222.30 23
2179 SH: Mortars
2180 LABOUR
2181 For fixing
Mason (for ornamental stone work)
2182 26 1st class day 0.67 505.17 318.92
2183 10 Bandhani day 0.67 350.00 214.96
2184 17 Beldar day 0.67 350.00 214.96
2185 18 Coolie day 0.67 350.00 214.96
2186 11 Bhisti day 0.67 350.00 214.96
2187 28 Mate day 0.33 350.00 105.87
2188 12 Blacksmith 1st class day 0.27 505.17 128.52
2189 9999 Scaffolding L.S. 26.91 2 53.82
2190 TOTAL 1554.33 W
2191 Add 1 % Water charges on "W" 15.5433
2192 TOTAL
Add GST (multiplying factor 0.1405) 1569.87 X
2193 on "X" 220.57
2194 TOTAL
Add 15 % Contractor's profit and 1790.44 Y
2195 overheads on "Y" 268.57
2196 Total 2059.01 Z
2197 Add Cess @ 1% on "Z" 20.59
2198 Cost for 1.00 sqm 2079.60
2199 Cost for one sqm 208.00
2200 208.00
2201
2203
2205 Say 1745.2
2206 e at all
2207 levels.
2208 upto
2209 0.50 sqm
2210
2211 Details of cost for 0.50 sqm.
2212 MATERIAL
2213 Mirror polished Abu plain white =
2214 0.50 sqm.+Wastage 5% 0.025 sqm. =
2215 0.525 sqmplain white marble (table
Raj nagar
2216 7452 rubbed and
polished) 18 mm thick (slab area sqm 0.525 575 301.88
2217 upto 0.50 sqm)
2218 20mm thick Cement mortar 1 : 4
2219 (1 cement : 4 coarse sand)
2220 3.9 Rate as per Item Number 3.9 of cum 0.012 3548.00 45.78
2221 SH: Mortars
2222 LABOUR
2223 23 Mason (brick layer) 1st class day 0.48 505.17 228.48
2224 17 Beldar day 0.2 350.00 64.17
2225 18 Coolie day 0.2 350.00 64.17
2226 9999 Moulding and edge
Sundries apoxy polishing
resin & cutting L.S. 39 2 78
2227 9999 machine etc. L.S. 16.25 2 32.5
2228 TOTAL 814.98 W
2229 Add 1 % Water charges on "W" 8.1498
2230 TOTAL
Add GST (multiplying factor 0.1405) 823.13 X
2231 on "X" 115.65
2232 TOTAL
Add 15 % Contractor's profit and 938.78 Y
2233 overheads on "Y" 140.82
2234 Total 1079.60 Z
2235 Add Cess @ 1% on "Z" 10.80
2236 Cost for 0.50 sqm. 1090.40
2237 Cost for one sqm. 109.00
2238 Say 109.00 2180.75
2239 slab over
2240 0.50 sqm
2241 for 1.00
2242 sqm.
2243 MATER
2244 IAL
2245 plain
2246 white =
2247 .)= 1.05
2248 sqm
2249
2251 Raj nagar plain white marble (table
2253 7453 rubbed and
polished) 18 mm thick (slab area sqm 1.05 690 724.5
2254 more than 0.50
sqm) 20mm thick Cement mortar 1 :
2255 4 (1 cement : 4
2256 coarse sand)
2257 3.9 Rate as per Item Number 3.9 of cum 0.024 3548.00 91.56
2258 SH: Mortars
2259 LABOUR
2260 23 Mason (brick layer) 1st class day 0.72 505.17 342.72
2261 17 Beldar day 0.3 350.00 96.25
2262 18 Coolie day 0.3 350.00 96.25
2263 9999 Moulding and edge
Sundries apoxy polishing
resin & cutting L.S. 78 2 156
2264 9999 machine etc. L.S. 32.5 2 65
2265 TOTAL 1572.28 W
2266 Add 1 % Water charges on "W" 15.7228
2267 TOTAL
Add GST (multiplying factor 0.1405) 1588.00 X
2268 on "X" 223.11
2269 TOTAL
Add 15 % Contractor's profit and 1811.11 Y
2270 overheads on "Y" 271.67
2271 Total 2082.78 Z
2272 Add Cess @ 1% on "Z" 20.83
2273 Cost for 1.00 sqm 2103.61
2274 Say 210.40 2103.6
2275 210.40
upto
2276 0.50 sqm
2277
2278 Details of cost for 0.50 sqm.
2279 MATERIAL
2280 Mirror polished granite= 0.50 sqm.+
2281 Wastage 5% 0.025 sqm.= 0.525 sqm
2282 7295 Granite of upto
(slab area any colour, 18 mm
0.50 sqm) thick
Cement sqm 0.525 1600 840
2283 mortar 1 : 4 (1
2284 cement
Rate as :per
4 coarse sand) 3.9 of SH:
Item Number
2285 3.9 Mortars cum 0.012 3548.00 45.78
2286 LABOUR
2287 23 Mason (brick layer) 1st class day 0.48 505.17 228.48
2288 17 Beldar day 0.2 350.00 64.17
2289 18 Coolie day 0.2 350.00 64.17
2290 9999 Moulding and edge
Sundries apoxy polishing
resin & cutting L.S. 39 2 78
2291 9999 machine etc. L.S. 16.25 2 32.5
2292 TOTAL 1353.10 W
2293 Add 1 % Water charges on "W" 13.531
2294 TOTAL
Add GST (multiplying factor 0.1405) 1366.63 X
2295 on "X" 192.01
2296 1558.64 Y
2298 233.80
2300 ds
TOTAL
on 1558.63 1792.44 Z
2301 "Y" 233.8 17.92
2302 1%
Total
on 1792.43 1810.36
2303 0.50
"Z" 17.92 181.00
2304 sqm.
1.00 1810.35 181.00
2305 sqm 3620.71
2306 Say 3194.95
2307 slab over
2308 0.50 sqm
2309
2310 Details of cost for 2.00 sqm.
2311 MATERIAL
2312 Mirror polished granite= 2.00 sqm.+
2313 Wastage
Granite of5% 0.10sqm.=
any colour, 182.10
mmsqm
thick
2314 7297 (slab area above
0.50 sqm) Cement mortar 1 : 4 (1 sqm 2.1 1800 3780
2315 cement : 4 coarse
2316 sand)
Rate as per Item Number 3.9 of SH:
2317 3.9 Mortars cum 0.048 3548.00 183.12
2318 LABOUR
2319 23 Mason (brick layer) 1st class day 1.44 505.17 685.44
2320 17 Beldar day 0.6 350.00 192.5
2321 18 Coolie day 0.6 350.00 192.5
2322 9999 Moulding and edge
Sundries apoxy polishing
resin & cutting L.S. 78 2 156
2323 9999 machine etc. L.S. 65 2 130
2324 TOTAL 5319.56 W
2325 Add 1 % Water charges on "W" 53.1956
2326 TOTAL
Add GST (multiplying factor 0.1405) 5372.76 X
2327 on "X" 754.87
2328 TOTAL
Add 15 % Contractor's profit and 6127.63 Y
2329 overheads on "Y" 919.14
2330 Total 7046.77 Z
2331 Add Cess @ 1% on "Z" 70.47
2332 Cost for 2.00 sqm. 7117.24
2333 Cost for 1.00 sqm 711.70
2334 Say 711.70 3558.6
2335 -in-
2336 Charge.
2337 Marble
2338 work
2339
2340 Details of cost for 10.00 m
2341 LABOUR
2342 19 Hand Grinder For mirror polish day 1.5 250 375
2343 17 Beldar day 2 350.00 641.66
2344 9999 Sundries Blades & Polished etc. L.S. 78 2 156
2345
2347
2349 TOTAL 9783.77 W
2350 Add 1 % Water charges on "W" 97.837656
2351 TOTAL
Add GST (multiplying factor 0.1405) 9881.60 X
2352 on "X" 1388.37
2353 TOTAL
Add 15 % Contractor's profit and 11269.97 Y
2354 overheads on "Y" 1690.50
2355 Total 12960.47 Z
2356 Add Cess @ 1% on "Z" 129.60
2357 Cost for 10 metre 13090.07
2358 Cost per metre 1309.00
2359 Say 1309.00 156.9
2360 8.3.2 Granite work
2361 Details of cost for 10.00 m
2362 LABOUR
2363 19 Hand Grinder For mirror polish day 2.5 250 625
2364 Polished
17 Beldar day 3.5 350.00 1122.91
2365 etc. L.S. 117 2 234
2366 TOTAL 55108.34 W
2367 Add 1 % Water charges on "W" 551.08341
2368 TOTAL
Add GST (multiplying factor 0.1405) 55659.42 X
2369 on "X" 7820.15
2370 TOTAL
Add 15 % Contractor's profit and 63479.57 Y
2371 overheads on "Y" 9521.94
2372 Total 73001.51 Z
2373 Add Cess @ 1% on "Z" 730.02
2374 Cost for 10 metre 73731.53
2375 Cost per metre 7373.20
2376 Say 7373.20 265.15
2377 includin
2378 g
2379 complete
2380 .
2381 1.5m
2382 long and
2383
2384 0.15m wide
2385 LABOUR
2386 23 Mason (brick layer) 1st class day 0.3 505.17 142.8
2387 18 Coolie day 0.3 350.00 96.25
2388 9999 Scaffolding, expoxy L.S. 39 2 78
2389 Cement mortar 1 : 4 (1 cement :
2390
2392
2394 4 coarse sand)
2395 1.5x0.15x0.02 = 0.005cum.
Rate as per Item Number 3.9 of SH:
2396 3.9 Mortars cum 0.005 3548.00 19.08
2397 TOTAL 336.13 W
2398 Add 1 % Water charges on "W" 3.3613
2399 TOTAL
Add GST (multiplying factor 0.1405) 339.49 X
2400 on "X" 47.70
2401 TOTAL
Add 15 % Contractor's profit and 387.19 Y
2402 overheads on "Y" 58.08
2403 Total 445.27 Z
2404 Add Cess @ 1% on "Z" 4.45
2405 Cost for 1.5 metre 449.72
2406 Cost per metre 45.00
2407 Say 45.00 299.8
2408 rubbing
2409 and
2410 complete
2411 .
2412 size and
2413 shape
2414 LABOU
2415 R
2416 Mason (for ornamental stone work)
2417 26 1st class day 0.4 505.17 190.4
2418 17 Beldar day 0.4 350.00 128.33
2419 9999 Sundries L.S. 15.3 2 30.6
2420 TOTAL 893.50 W
2421 Add 1 % Water charges on "W" 8.935013
2422 TOTAL
Add GST (multiplying factor 0.1405) 902.44 X
2423 on "X" 126.79
2424 TOTAL
Add 15 % Contractor's profit and 1029.23 Y
2425 overheads on "Y" 154.38
2426 Total 1183.61 Z
2427 Add Cess @ 1% on "Z" 11.84
2428 Cost of each 1195.45
2429 Say 119.50 467.4
2430 complet 119.50
2431 e.
2432 for 10
2433 sqm.
2434 LABOU
2435 R
2436 300.00
2437 300.00
2438
2440
2442 17 Beldar day 2.5 350.00 802.08
2443 stones11 Bhisti day 1.5 350.00 481.25
2444 etc. L.S. 65 2 130
2445 TOTAL 2859.62 W
2446 Add 1 % Water charges on "W" 28.596163
2447 TOTAL
Add GST (multiplying factor 0.1405) 2888.21 X
2448 on "X" 405.79
2449 TOTAL
Add 15 % Contractor's profit and 3294.00 Y
2450 overheads on "Y" 494.10
2451 Total 3788.10 Z
2452 Add Cess @ 1% on "Z" 37.88
2453 Cost for 10 sqm. 3825.98
2454 Cost per sqm. 382.60
2455 Say 382.60 229.25
2456 separate
2457 ly).
2458 al
2459 cramps
2460 for 10 no
2461 cramps
2462 MATER
2463 IAL
2464 metal
2465 cramp
2466 13.3 x
2467 10^5
2468 1.4 x
2469 10^5
2470 #ERROR
2471 !
2472 #ERROR
2473 !
2474
2475 Total = 1.08 kg.
2476 7338 Gun metal cramp kilogra 1.08 315 340.2
2477 m
2478 9977 Carriage
Cement mortar 1:2 (1 cement : 2 L.S. 3.9 2 7.8
2479 coarse
Rate assand)
per Item Number 3.7 of SH:
2480 3.7 Mortars cum 0.001 4722.70 5.15
2481 9999 Labour for fixing in position L.S. 65 2 130
2482 TOTAL 483.15 W
2483 Add 1 % Water charges on "W" 4.8315
2484 TOTAL
Add GST (multiplying factor 0.1405) 487.98 X
2485 on "X" 68.56
2486 TOTAL
Add 15 % Contractor's profit and 556.54 Y
2487 overheads on "Y" 83.48
2488 Total 640.02 Z
2489 6.40
2491 1% on 646.42
2493 "Z"
Cost for 6.4 64.60
2494 1.03
Costkg.
per 646.43 64.60
2495 kg 627.6
2496 Say 3620.7
2497 s steel
2498 cramps
2499 for 10
2500 nos
2501 MATER
2502 IAL
2503 steel
2504 cramp
2505 13.3 x
2506 10^5
2507 1.4 x
2508 10^5
2509 #ERROR
2510 !
2511 #ERROR
2512 !
2513
2514 Total = 0.981 kg.
2515 7339 Stainless steel cramp kilogra 0.981 290 284.49
2516 m
2517 9977 Carriage
Cement mortar 1:2 (1 cement : 2 L.S. 3.9 2 7.8
2518 coarse
Rate assand)
per Item Number 3.7 of SH:
2519 3.7 Mortars cum 0.001 4722.70 5.15
2520 9999 Labour for fixing in position L.S. 65 2 130
2521 TOTAL 427.44 W
2522 Add 1 % Water charges on "W" 4.2744
2523 TOTAL
Add GST (multiplying factor 0.1405) 431.71 X
2524 on "X" 60.66
2525 TOTAL
Add 15 % Contractor's profit and 492.37 Y
2526 overheads on "Y" 73.86
2527 Total 566.23 Z
2528 Add Cess @ 1% on "Z" 5.66
2529 Cost for 0.934 kg. 571.89
2530 Cost per kg 57.20
2531 Say 57.20 612.3
2532 complet
2533 e.
2534 expansi
2535 on type
2536 dia 6
2537 mm
2538 Details of cost for 30nos. W.E.H.
2539 fastener
2540 MATERIAL
Wedge expansion hold fastner 1/4"
2541 7430 or 6 mm 36.5mm each 30 11 330
2542 length
Bolts and nuts upto 300 mm in
2543 1034 length quintal 0.0045 6800 21.6
2544 (36.5+10mm)
2545
2547
2549 LABOUR
2550 19 Fitter (grade 1) day 0.25 505.17 119
2551 17 Beldar day 0.25 350.00 80.21
Hire and running charges for hand
2552 9999 drill machine L.S. 32.5 2 65
2553 Sundries, drilling bit scaffolding etc.
2554 TOTAL 615.81 W
2555 Add 1 % Water charges on "W" 6.1581
2556 TOTAL
Add GST (multiplying factor 0.1405) 621.97 X
2557 on "X" 87.39
2558 TOTAL
Add 15 % Contractor's profit and 709.36 Y
2559 overheads on "Y" 106.40
2560 Total 815.76 Z
2561 Add Cess @ 1% on "Z" 8.16
2562 Cost for 30 nos. 823.92
2563 Cost of each 82.40
2564 Say 82.40 27.45
2565 dia 10
2566 mm
2567 Details of cost for 30nos. W.E.H.
2568 fastener
2569 MATERIAL
Wedge expansion hold fastner 3/8"
2570 7431 or 10 mm each 30 11 330
2571 44.5mm
Bolts and length
nuts upto 300 mm in
2572 1034 length quintal 0.006 6800 28.8
2573 (44.5+10mm)
2574 LABOUR
2575 19 Fitter (grade 1) day 0.25 505.17 119
2576 17 Beldar
Hire and running charges for hand day 0.25 350.00 80.21
2577 9999 drill machine L.S. 32.5 2 65
2578 Sundries, drilling bit scaffolding etc.
2579 TOTAL 787.81 W
2580 Add 1 % Water charges on "W" 7.8781
2581 TOTAL
Add GST (multiplying factor 0.1405) 795.69 X
2582 on "X" 111.79
2583 TOTAL
Add 15 % Contractor's profit and 907.48 Y
2584 overheads on "Y" 136.12
2585 Total 1043.60 Z
2586 Add Cess @ 1% on "Z" 10.44
2587 Cost for 30 nos. 1054.04
2588 Cost of each 105.40
2589 105.40
2591
2593 dia 12 Say 27.8
2594 mm Details of cost for 30nos. W.E.H.
2595 fastener
2596 MATERIAL
Wedge expansion hold fastner 1/2"
2597 7432 or 12 mm each 30 27 810
2598 58.7mm
Bolts and length
nuts upto 300 mm in
2599 1034 length quintal 0.0075 6800 36
2600 Length (58.7+10mm) @ 0.05 kg./each
2601 LABOUR
2602 19 Fitter (grade 1) day 0.25 505.17 119
2603 17 Beldar
Hire and running charges for hand day 0.25 350.00 80.21
2604 9999 drill machine L.S. 32.5 2 65
2605 Sundries, drilling bit scaffolding etc.
2606 TOTAL 1321.01 W
2607 Add 1 % Water charges on "W" 13.2101
2608 TOTAL
Add GST (multiplying factor 0.1405) 1334.22 X
2609 on "X" 187.46
2610 TOTAL
Add 15 % Contractor's profit and 1521.68 Y
2611 overheads on "Y" 228.25
2612 Total 1749.93 Z
2613 Add Cess @ 1% on "Z" 17.50
2614 Cost for 30 nos. 1767.43
2615 Cost of each 176.70
2616 Say 176.70 49.5
2617 complet
2618 e.
2619
8mm
2620 thick
2621 black
2622 marble
2623
2624 Details of cost for 1 sqm.
2625 MATERIAL
2626 8mm thick marble tiles.
2627 Qty. = 1.00 sqm. +
2628 Add wastage @ 2.5% = 0.025 sqm.
2629 Total = 1.025 sqm.
2630 2751 8 mm thick marble tiles (polished) sqm 1.025 400 410
2631 Raj Nagar
2632 9977 Carriage of tiles1:3 (1 cement : 3
Cement mortar L.S. 3.95 2 7.9
2633 coarse
Rate assand)
per Item Number 3.8 of SH:
2634 3.8 Mortars cum 0.014 4129.00 62.57
2635
2637
2639 9999 Mortar for pointing L.S. 25.38 2 50.76
2640 367 Portland Cement tonne 0.0033 4375 16.3
2641 23 Mason (brick layer) 1st class day 1 505.17 476
2642 17 Beldar day 1 350.00 320.83
2643 9999 Sundries etc. L.S. 16.9 2 33.8
2644 TOTAL 1378.16 W
2645 Add 1 % Water charges on "W" 13.7816
2646 TOTAL
Add GST (multiplying factor 0.1405) 1391.94 X
2647 on "X" 195.57
2648 TOTAL
Add 15 % Contractor's profit and 1587.51 Y
2649 overheads on "Y" 238.13
2650 Total 1825.64 Z
2651 Add Cess @ 1% on "Z" 18.26
2652 Cost for 1 sqm. 1843.90
2653 and Say 184.40 1843.9
2654 shade 184.40
2655 Details of cost for 1 sqm.
2656 8mm thick Granite tiles.
2657 Qty. = 1.00 sqm. +
2658 Add wastage @ 2.5% = 0.025 sqm.
2659 Total
8 mm =thick
1.025 sqm. stone tiles (mirror
granite
2660 2750 polished of all sqm 1.025 700 717.5
2661 shades)
2662 9977 Carriage of tiles1:3 (1 cement : 3
Cement mortar L.S. 3.95 2 7.9
2663 coarse
Rate assand)
per Item Number 3.8 of SH:
2664 3.8 Mortars cum 0.014 4129.00 62.57
2665 9999 Mortar for pointing L.S. 25.38 2 50.76
2666 367 Portland Cement tonne 0.0033 4375 16.3
2667 23 Mason (brick layer) 1st class day 1 505.17 476
2668 17 Beldar day 1 350.00 320.83
2669 9999 Sundries etc. L.S. 16.9 2 33.8
2670 TOTAL 1870.06 W
2671 Add 1 % Water charges on "W" 18.7006
2672 TOTAL
Add GST (multiplying factor 0.1405) 1888.76 X
2673 on "X" 265.37
2674 TOTAL
Add 15 % Contractor's profit and 2154.13 Y
2675 overheads on "Y" 323.12
2676 Total 2477.25 Z
2677 Add Cess @ 1% on "Z" 24.77
2678 Cost for 1 sqm. 2502.02
2679 Say 250.20 2255.3
2680 250.20
2681
2683
2685 finished
2686 smooth.
2687 Marble
2688 Stone
2689
Details of cost for one No or 0.375
2690 sqm.
2691 MATERIAL
Agaria Marble Stone 1 X 0.75 X 0.50
2692 =
2693 0.375 sqm
2694 Add wastage 20% = 0.075 sqm.
2695 Total
Table =rubbed
0.45sqm.
polished stone 18 mm
2696 7244 thick
(75x50cm) Agaria Marble stone - 18 sqm 0.45 1620 729
2697 mm thick
2698 9999 Cement concrete
Labour for fixing, 1:2:4
edge for filling and
rounding L.S. 21.58 2 43.16
2699 9999 final polishing . L.S. 43.16 2 86.32
2700 9999 Sundries L.S. 21.58 2 43.16
2701 TOTAL 901.64 W
2702 Add 1 % Water charges on "W" 9.0164
2703 TOTAL
Add GST (multiplying factor 0.1405) 910.66 X
2704 on "X" 127.95
2705 TOTAL
Add 15 % Contractor's profit and 1038.61 Y
2706 overheads on "Y" 155.79
2707 Total 1194.40 Z
2708 Add Cess @ 1% on "Z" 11.94
2709 Cost of 0.375sqm 1206.34
2710 Cost of 1.00 sqm 120.60
2711 approve Say 120.60 3216.9
2712 d shade Details of cost for one No or
2713 0.375sqm.
2714 MATERIAL
Granite Stone 1x0.75x0.50 =
2715 0.375sqm.+ Add
2716 wastage 20% = 0.075 sqm.
2717 Total
Table =rubbed
0.45 sqm.
polished stone 18mm
2718 7245 thick (75x50cm) sqm 0.45 1620 729
2719 Granite stone - 18mm thick
2720 9999 Cement concrete
Labour for fixing, 1:2:4
edge for fixing and
rounding L.S. 21.58 2 43.16
2721 9999 final polishing . L.S. 43.16 2 86.32
2722 9999 Sundries L.S. 21.58 2 43.16
2723 TOTAL 3555.51 W
2724 Add 1 % Water charges on "W" 35.555128
2725 TOTAL 3591.07 X
2726 504.55
2727 4095.62 Y
2729 0.1405) 614.34
2731 on "X" 127.95 4709.96 Z
2732 ds
TOTAL
on 1038.6 47.10
2733 "Y" 155.79 4757.06
2734 1%
Total
on 1194.39 475.70
2735 "Z"
0.375 11.94 475.70
2736 sqm
1.00 1206.34
2737 sqm 3216.9
2738 Say 627.6
2739 Rosso
2740 verona,
2741 Empera
2742 dore etc.
2743 for 0.5
2744 sqm
2745
2746 MATERIAL
2747 Finished work= 0.5 sqm
2748 Add for wastage @ 20%=0.1 sqm
2749 Total
18 mm 0.60 sqm
thick Italian Marble stone
2750 1240 slab, Perlato (slab sqm 0.6 3209 1925.4
2751 area up to 0.5 sqm).
2752 2216 Carriage of stone slab tonne 0.03 94.34 2.83
2753 Cement mortar 1:3 (1 Cement:3
2754 Coarse
Rate as sand)
per Item No.3.8 of SH:
2755 3.8 MORTARS cum 0.008 4129.00 35.76
2756 368 White Cement tonne 0.00165 11200 18.48
2757 Slurry @ 3.3kg/sqm
2758 2209 Carriage
Mortar forofpointing
white Cement
in white cement tonne 0.00165 94.34 0.16
2759 9999 (11.22) L.S. 25.35 2 50.7
2760 LABOUR :
2761 FOR
Masonfixing
(for ornamental stone work)
2762 26 1st class day 0.335 505.17 159.46
2763 10 Bandhani day 0.335 350.00 107.48
2764 17 Beldar day 0.335 350.00 107.48
2765 18 Coolie day 0.335 350.00 107.48
2766 11 Bhisti day 0.335 350.00 107.48
2767 28 Mate day 0.165 350.00 52.94
2768 12 Blacksmith 1st class day 0.135 505.17 64.26
2769 9999 Scaffolding L.S. 13.39 2 26.78
2770
2771 367 4375
2772
2774 charges
TOTAL 2766.67 784.22 W
2775 on "W" 27.67 7.8422
2776 0.1405)
TOTAL 2794.34 792.06 X
2777 on "X" 392.6 111.28
2778 ds
TOTAL
on 3186.94 903.34 Y
2779 "Y" 478.04 135.50
2780 1%
Total
on 3664.98 1038.84 Z
2781 "Z"
Cost of 36.65 10.39
2782 0.5
Costsqm
of 3701.63 1049.23
2783 1 sqm 7403.27 104.90
2784 Say 104.90 3216.9
2785 separate
2786 ly) :
2787 rough
2788 backing.
2789 70 mm
2790 thick
2791
2792 Details of cost for 1 sqm.
2793 MATERIAL
2794 Finished work = 70 cudm. +
2795 Add wastage @ 33.3% = 23.33 cudm.
2796 Total = 93.33 cudm.
2797 1160 Red sand stone block 10 9.333 79 737.31
2798 Carriage of Stone blocks white & red cudm
2799 2216 sand stone & tonne 0.215 94.34 20.28
2800 kota
Extrastone slab white
for using @ 2.30kg/cudm
cement
2801 9999 Dressing charges L.S. 26.91 2 53.82
2802 LABOUR
Mason (for plain stone work) 2nd
2803 25 class) day 1.35 403.67 505.58
2804 12 Blacksmith 1st class day 0.032 505.17 15.23
2805 17 Beldar day 0.224 350.00 71.87
2806 18 Coolie day 0.112 350.00 35.93
2807 10 Bandhani day 0.224 350.00 71.87
2808 Fixing charges
2809 LABOUR
Mason (for plain stone work) 2nd
2810 25 class) day 0.448 403.67 167.78
2811 10 Bandhani day 0.336 350.00 107.8
2812 17 Beldar day 0.336 350.00 107.8
2813 18 Coolie day 0.336 350.00 107.8
2814 11 Bhisti
Cutting marble or sand stone slab day 0.336 350.00 107.8
2815 1237 upto 50 mm thick metre 4 10 40
2816 by mechanical device
2817
2818 368
2819
2821 9999 Scaffolding L.S. 19.76 2 39.52
2822 Mortar
Rate asfor
perlaying and pointing
Item Number 3.8 of SH:
2823 3.8 Mortars cum 0.018 4129.00 80.45
2824 TOTAL 830.82 W
2825 Add 1 % Water charges on "W" 8.3082
2826 TOTAL
Add GST (multiplying factor 0.1405) 839.13 X
2827 on "X" 117.90
2828 TOTAL
Add 15 % Contractor's profit and 957.03 Y
2829 overheads on "Y" 143.55
2830 Total 1100.58 Z
2831 Add Cess @ 1% on "Z" 11.01
2832 Cost of 1 sqm. 1111.59
2833 60 mm Say 111.20 3038.2
2834 thick 111.20
2835 Details of cost for 1 sqm.
2836 MATERIAL
2837 Finished work = 60 cudm.
2838 Add wastage @ 33.3% = 20 cudm.
2839 Total = 80 cudm.
2840 1160 Red sand stone block 10 8 79 632
2841 Carriage of Stone blocks white & red cudm
2842 2216 sand stone & tonne 0.184 94.34 17.36
2843 kota stone slab @ 2.30kg/cudm
2844 9999 Extra for using white cement L.S. 26.91 2 53.82
2845 Dressing charges
2846 LABOUR
Mason (for plain stone work) 2nd
2847 25 class) day 1.35 403.67 505.58
2848 12 Blacksmith 1st class day 0.032 505.17 15.23
2849 17 Beldar day 0.224 350.00 71.87
2850 18 Coolie day 0.112 350.00 35.93
2851 10 Bandhani day 0.224 350.00 71.87
2852 Fixing charges
2853 LABOUR
Mason (for plain stone work) 2nd
2854 25 class) day 0.448 403.67 167.78
2855 10 Bandhani day 0.336 350.00 107.8
2856 17 Beldar day 0.336 350.00 107.8
2857 18 Coolie day 0.336 350.00 107.8
2858 11 Bhisti day 0.336 350.00 107.8
Cutting marble or sand stone slab
2859 1237 upto 50 mm thick metre 4 10 40
2860 by mechanical device
2861 9999 Scaffolding L.S. 19.76 2 39.52
2862 and
2863 pointing
2864
2865 369
2866 Rate as per Item Number 3.8 of SH:
2868 3.8 Mortars cum 0.018 4129.00 80.45
2869 TOTAL 758.95 W
2870 Add 1 % Water charges on "W" 7.5895
2871 TOTAL
Add GST (multiplying factor 0.1405) 766.54 X
2872 on "X" 107.70
2873 TOTAL
Add 15 % Contractor's profit and 874.24 Y
2874 overheads on "Y" 131.14
2875 Total 1005.38 Z
2876 Add Cess @ 1% on "Z" 10.05
2877 Cost of 1 sqm. 1015.43
2878 50 mm Say 101.50 2893.4
2879 thick 101.50
2880 Details of cost for 1 sqm.
2881 MATERIAL
2882 Finished work = 50 cudm.
2883 Add wastage @ 33.3% = 16.7 cudm.
2884 Total = 66.7 cudm.
2885 1160 Red sand stone block 10 6.67 79 526.93
2886 cudm
2887 2216 Carriage
red sand of Stone
stone blocks
& kota white
stone & @ tonne
slab 0.153 94.34 14.43
2888 2.30kg/cudm
2889 9999 Extra for using white cement L.S. 26.91 2 53.82
2890 Dressing charges
2891 LABOUR
Mason (for plain stone work) 2nd
2892 25 class) day 1.35 403.67 505.58
2893 12 Blacksmith 1st class day 0.032 505.17 15.23
2894 17 Beldar day 0.224 350.00 71.87
2895 18 Coolie day 0.112 350.00 35.93
2896 10 Bandhani day 0.224 350.00 71.87
2897 Fixing charges
2898 LABOUR
Mason (for plain stone work) 2nd
2899 25 class) day 0.448 403.67 167.78
2900 10 Bandhani day 0.336 350.00 107.8
2901 17 Beldar day 0.336 350.00 107.8
2902 18 Coolie day 0.336 350.00 107.8
2903 11 Bhisti
Cutting marble or sand stone slab day 0.336 350.00 107.8
2904 1237 upto 50 mm thick metre 4 10 40
2905 by mechanical device
2906 9999 Scaffolding L.S. 19.76 2 39.52
2907 Mortar
Rate asfor
perlaying and pointing
Item Number 3.8 of SH:
2908 3.8 Mortars cum 0.018 4129.00 80.45
2909 TOTAL 953.85 W
2910 9.5385
2911 963.39 X
2912 370 135.36
2913 1098.75 Y
2915 Add 1 % Water charges on "W" 164.81
2916 TOTAL
Add GST (multiplying factor 0.1405) 1263.56 Z
2917 on "X" 12.64
2918 TOTAL
Add 15 % Contractor's profit and 1276.20
2919 overheads on "Y" 127.60
2920 Total 127.60
2921 Add Cess @ 1% on "Z" 27.22
2922 Cost of 1 sqm. 2748.92
2923 40 mm Say 2748.9
2924 thick
2925 Details of cost for 1 sqm.
2926 MATERIAL
2927 Finished work = 40 cudm.
2928 Add wastage @ 33.3% = 13.33 cudm.
2929 Total = 53.33 cudm.
2930 1160 Red sand stone block 10 5.333 79 421.31
2931 cudm
2932 2216 Carriage
red sand of Stone
stone blocks
& kota white
stone & @ tonne
slab 0.123 94.34 11.6
2933 2.30kg/cudm
2934 9999 Extra for using white cement L.S. 26.91 2 53.82
2935 Dressing charges
2936 LABOUR
Mason (for plain stone work) 2nd
2937 25 class) day 1.35 403.67 505.58
2938 12 Blacksmith 1st class day 0.032 505.17 15.23
2939 17 Beldar day 0.224 350.00 71.87
2940 18 Coolie day 0.112 350.00 35.93
2941 10 Bandhani day 0.224 350.00 71.87
2942 Fixing charges
2943 LABOUR
Mason (for plain stone work) 2nd
2944 25 class) day 0.448 403.67 167.78
2945 10 Bandhani day 0.336 350.00 107.8
2946 17 Beldar day 0.336 350.00 107.8
2947 18 Coolie day 0.336 350.00 107.8
2948 11 Bhisti
Cutting marble or sand stone slab day 0.336 350.00 107.8
2949 1237 upto 50 mm thick metre 4 10 40
2950 by mechanical device
2951 9999 Scaffolding L.S. 19.76 2 39.52
2952 Mortar
Rate asfor
perlaying and pointing
Item Number 3.8 of SH:
2953 3.8 Mortars cum 0.018 4129.00 80.45
2954 TOTAL 953.85 W
2955 Add 1 % Water charges on "W" 9.5385
2956 TOTAL 963.39 X
2957 135.36
2958 1098.75 Y
2959 371 164.81
2960 Add GST (multiplying factor 0.1405) 1263.56 Z
2962 on "X" 12.64
2963 TOTAL
Add 15 % Contractor's profit and 1276.20
2964 overheads on "Y" 127.60
2965 Total 127.60
2966 Add Cess @ 1% on "Z" 25.78
2967 Cost of 1 sqm. 2603.82
2968 30 mm Say 2603.8
2969 thick
2970 Details of cost for 1 sqm.
2971 MATERIAL
2972 Finished work = 30 cudm.
2973 Add wastage @ 33.3% = 9.99cudm.
2974 Total = 39.99 cudm.
2975 1160 Red sand stone block 10 3.999 79 315.92
2976 cudm
2977 2216 Carriage
red sand of Stone
stone blocks
& kota white
stone & @ tonne
slab 0.092 94.34 8.68
2978 2.30kg/cudm
Extra for using white cement
2979 9999 Dressing charges L.S. 26.91 2 53.82
2980 LABOUR
Mason (for plain stone work) 2nd
2981 25 class) day 1.35 403.67 505.58
2982 12 Blacksmith 1st class day 0.032 505.17 15.23
2983 17 Beldar day 0.224 350.00 71.87
2984 18 Coolie day 0.112 350.00 35.93
2985 10 Bandhani day 0.224 350.00 71.87
2986 Fixing charges
2987 LABOUR
Mason (for plain stone work) 2nd
2988 25 class) day 0.448 403.67 167.78
2989 10 Bandhani day 0.336 350.00 107.8
2990 17 Beldar day 0.336 350.00 107.8
2991 18 Coolie day 0.336 350.00 107.8
2992 11 Bhisti
Cutting marble or sand stone slab day 0.336 350.00 107.8
2993 1237 upto 50 mm thick metre 4 10 40
2994 by mechanical device
2995 9999 Scaffolding L.S. 19.76 2 39.52
2996 Mortar
Rate asfor
perlaying and pointing
Item Number 3.8 of SH:
2997 3.8 Mortars cum 0.018 4129.00 80.45
2998 TOTAL 953.85 W
2999 Add 1 % Water charges on "W" 9.5385
3000 963.39 X
3001 135.36
3002 372 1098.75 Y
3003 164.81
3005 0.1405)
TOTAL 1856.21 1263.56 Z
3006 on "X" 260.8 12.64
3007 ds
TOTAL
on 2117.01 1276.20
3008 "Y" 317.55 127.60
3009 1%
Total
on 2434.56 127.60
3010 "Z"
Cost of 24.35
3011 1 sqm. 2458.91
3012 Say 7403.25
3013 rough
3014 backing.
3015 70 mm
3016 thick
3017
3018 Details of cost for 1 sqm.
3019 MATERIAL
3020 Finished work = 70 cudm.
3021 Add wastage @ 33.3% = 23.33 cudm.
3022 Total = 93.33 cudm.
3023 1160 Red sand stone block 10 9.333 79 737.31
3024 cudm
3025 2216 Carriage
red sand stone & kota stone slab @ tonne
of Stone blocks white & 0.215 94.34 20.28
3026 2.30kg/cudm
3027 9999 Extra for using white cement L.S. 26.91 2 53.82
3028 Dressing charges
3029 LABOUR
Mason (for plain stone work) 2nd
3030 25 class) day 2.7 403.67 1011.15
3031 12 Blacksmith 1st class day 0.064 505.17 30.46
3032 17 Beldar day 0.448 350.00 143.73
3033 18 Coolie day 0.224 350.00 71.87
3034 10 Bandhani day 0.448 350.00 143.73
3035 Fixing charges
3036 LABOUR
Mason (for plain stone work) 2nd
3037 25 class) day 0.448 403.67 167.78
3038 10 Bandhani day 0.336 350.00 107.8
3039 17 Beldar day 0.336 350.00 107.8
3040 18 Coolie day 0.336 350.00 107.8
3041 11 Bhisti
Cutting marble or sand stone slab day 0.336 350.00 107.8
3042 1237 upto 50 mm thick metre 4 10 40
3043 by mechanical device
3044 9999 Scaffolding L.S. 19.76 2 39.52
3045 Mortar
Rate asfor
perlaying and pointing
Item Number 3.8 of SH:
3046 3.8 Mortars cum 0.018 4129.00 80.45
3047 TOTAL 1148.74 W
3048 Add 1 % Water charges on "W" 11.4874
3049 TOTAL 1160.23 X
3050 163.01
3051 373 1323.24 Y
3052 0.1405) 198.49
3054 on "X" 421.64 1521.73 Z
3055 ds
TOTAL
on 3422.65 15.22
3056 "Y" 513.4 1536.95
3057 1%
Total
on 3936.05 153.70
3058 "Z"
Cost of 39.36 153.70
3059 1 sqm. 3975.41
3060 Say 2458.9
3061
60 mm
3062 thick
3063
3064 Details of cost for 1 sqm.
3065 MATERIAL
3066 Finished work = 60 cudm.
3067 Add wastage @ 33.3% = 20 cudm.
3068 Total = 80 cudm.
3069 1160 Red sand stone block 10 8 79 632
3070 cudm
3071 2216 Carriage
red sand of Stone
stone blocks
& kota white
stone & @ tonne
slab 0.184 94.34 17.36
3072 2.30kg/cudm
3073 9999 Extra for using white cement L.S. 26.91 2 53.82
3074 Dressing charges
3075 LABOUR
Mason (for plain stone work) 2nd
3076 25 class) day 2.7 403.67 1011.15
3077 12 Blacksmith 1st class day 0.064 505.17 30.46
3078 17 Beldar day 0.448 350.00 143.73
3079 18 Coolie day 0.224 350.00 71.87
3080 10 Bandhani day 0.448 350.00 143.73
3081 Fixing charges
3082 LABOUR
Mason (for plain stone work) 2nd
3083 25 class) day 0.448 403.67 167.78
3084 10 Bandhani day 0.336 350.00 107.8
3085 17 Beldar day 0.336 350.00 107.8
3086 18 Coolie day 0.336 350.00 107.8
3087 11 Bhisti
Cutting marble or sand stone slab day 0.336 350.00 107.8
3088 1237 upto 50 mm thick metre 4 10 40
3089 by mechanical device
3090 9999 Scaffolding L.S. 19.76 2 39.52
3091 Mortar
Rate asfor
perlaying and pointing
Item Number 3.8 of SH:
3092 3.8 Mortars cum 0.018 4129.00 80.45
3093 TOTAL 1148.74 W
3094 Add 1 % Water charges on "W" 11.4874
3095 TOTAL
Add GST (multiplying factor 0.1405) 1160.23 X
3096 on "X" 163.01
3097 1323.24 Y
3098 374 198.49
3099 1521.73 Z
3101 TOTAL
Add 15 % Contractor's profit and 15.22
3102 overheads on "Y" 1536.95
3103 Total 153.70
3104 Add Cess @ 1% on "Z" 153.70
3105 Cost of 1 sqm. 3830.6
3106 50 mm Say 3830.6
3107 thick
3108 Details of cost for 1 sqm.
3109 MATERIAL
3110 Finished work = 50 cudm.
3111 Add wastage @ 33.3% = 16.7 cudm.
3112 Total = 66.7 cudm.
3113 1160 Red sand stone block 10 6.67 79 526.93
3114 cudm
3115 2216 Carriage
red sand of Stone
stone blocks
& kota white
stone & @ tonne
slab 0.153 94.34 14.43
3116 2.30kg/cudm
3117 9999 Extra for using white cement L.S. 26.91 2 53.82
3118 Dressing charges
3119 LABOUR
Mason (for plain stone work) 2nd
3120 25 class) day 2.7 403.67 1011.15
3121 12 Blacksmith 1st class day 0.064 505.17 30.46
3122 17 Beldar day 0.448 350.00 143.73
3123 18 Coolie day 0.224 350.00 71.87
3124 10 Bandhani day 0.448 350.00 143.73
3125 Fixing charges
3126 LABOUR
Mason (for plain stone work) 2nd
3127 25 class) day 0.448 403.67 167.78
3128 10 Bandhani day 0.336 350.00 107.8
3129 17 Beldar day 0.336 350.00 107.8
3130 18 Coolie day 0.336 350.00 107.8
3131 11 Bhisti
Cutting marble or sand stone slab day 0.336 350.00 107.8
3132 1237 upto 50 mm thick metre 4 10 40
3133 by mechanical device
3134 9999 Scaffolding L.S. 19.76 2 39.52
3135 Mortar
Rate asfor
perlaying and pointing
Item Number 3.8 of SH:
3136 3.8 Mortars cum 0.018 4129.00 80.45
3137 TOTAL 1148.74 W
3138 Add 1 % Water charges on "W" 11.4874
3139 TOTAL
Add GST (multiplying factor 0.1405) 1160.23 X
3140 on "X" 163.01
3141 TOTAL
Add 15 % Contractor's profit and 1323.24 Y
3142 overheads on "Y" 198.49
3143 1521.73 Z
3144 15.22
3145 375 1536.95
3146 153.70
3148 Total 153.70
3149 Add Cess @ 1% on "Z" 36.5
3150 Cost of 1 sqm. 3686.11
3151 40 mm Say 3686.1
3152 thick
3153 Details of cost for 1 sqm.
3154 MATERIAL
3155 Finished work = 40 cudm.
3156 Add wastage @ 33.3% = 13.33 cudm.
3157 Total = 53.33 cudm.
3158 1160 Red sand stone block 10 5.333 79 421.31
3159 cudm
3160 2216 Carriage
red sand stone & kota stone slab @ tonne
of Stone blocks white & 0.123 94.34 11.6
3161 2.30kg/cudm
Extra for using white cement
3162 9999 Dressing charges L.S. 26.91 2 53.82
3163 LABOUR
Mason (for plain stone work) 2nd
3164 25 class) day 2.7 403.67 1011.15
3165 12 Blacksmith 1st class day 0.064 505.17 30.46
3166 17 Beldar day 0.448 350.00 143.73
3167 18 Coolie day 0.224 350.00 71.87
3168 10 Bandhani day 0.448 350.00 143.73
3169 Fixing charges
3170 LABOUR
Mason (for plain stone work) 2nd
3171 25 class) day 0.448 403.67 167.78
3172 10 Bandhani day 0.336 350.00 107.8
3173 17 Beldar day 0.336 350.00 107.8
3174 18 Coolie day 0.336 350.00 107.8
3175 11 Bhisti
Cutting marble or sand stone slab day 0.336 350.00 107.8
3176 1237 upto 50 mm thick metre 4 10 40
3177 by mechanical device
3178 9999 Scaffolding L.S. 19.76 2 39.52
3179 Mortar
Rate asfor
perlaying and pointing
Item Number 3.8 of SH:
3180 3.8 Mortars cum 0.018 4129.00 80.45
3181 TOTAL 1148.74 W
3182 Add 1 % Water charges on "W" 11.4874
3183 TOTAL
Add GST (multiplying factor 0.1405) 1160.23 X
3184 on "X" 163.01
3185 TOTAL
Add 15 % Contractor's profit and 1323.24 Y
3186 overheads on "Y" 198.49
3187 Total 1521.73 Z
3188 Add Cess @ 1% on "Z" 15.22
3189 Cost of 1 sqm. 1536.95
3190 153.70
3191 153.70
3192 376
3193
3195 30 mm Say 3541
3196 thick
3197 Details of cost for 1 sqm.
3198 MATERIAL
3199 Finished work = 30 cudm.
3200 Add wastage @ 33.3% = 9.99cudm.
3201 Total = 39.99 cudm.
3202 1160 Red sand stone block 10 3.999 79 315.92
3203 cudm
3204 2216 Carriage
red sand of Stone
stone blocks
& kota white
stone & @ tonne
slab 0.092 94.34 8.68
3205 2.30kg/cudm
3206 9999 Extra for using white cement L.S. 26.91 2 53.82
3207 Dressing charges
3208 LABOUR
Mason (for plain stone work) 2nd
3209 25 class) day 2.7 403.67 1011.15
3210 12 Blacksmith 1st class day 0.064 505.17 30.46
3211 17 Beldar day 0.448 350.00 143.73
3212 18 Coolie day 0.224 350.00 71.87
3213 10 Bandhani day 0.448 350.00 143.73
3214 Fixing charges
3215 LABOUR
Mason (for plain stone work) 2nd
3216 25 class) day 0.448 403.67 167.78
3217 10 Bandhani day 0.336 350.00 107.8
3218 17 Beldar day 0.336 350.00 107.8
3219 18 Coolie day 0.336 350.00 107.8
3220 11 Bhisti
Cutting marble or sand stone slab day 0.336 350.00 107.8
3221 1237 upto 50 mm thick metre 4 10 40
3222 by mechanical device
3223 9999 Scaffolding L.S. 19.76 2 39.52
3224 Mortar
Rate asfor
perlaying and pointing
Item Number 3.8 of SH:
3225 3.8 Mortars cum 0.018 4129.00 80.45
3226 TOTAL 1148.74 W
3227 Add 1 % Water charges on "W" 11.4874
3228 TOTAL
Add GST (multiplying factor 0.1405) 1160.23 X
3229 on "X" 163.01
3230 TOTAL
Add 15 % Contractor's profit and 1323.24 Y
3231 overheads on "Y" 198.49
3232 Total 1521.73 Z
3233 Add Cess @ 1% on "Z" 15.22
3234 Cost of 1 sqm. 1536.95
3235 153.70
3236 153.70
3237 377
3238
3240 Say 3975.4
3241 70 mm
3242 thick
3243
3244 Details of cost for 1 sqm.
3245 MATERIAL
3246 Finished work = 70 cudm.
3247 Add wastage @ 33.3% = 23.33 cudm.
3248 Total = 93.33 cudm.
3249 1161 White sand stone block 10 9.333 205 1913.27
3250 cudm
3251 2216 Carriage
red sand of Stone
stone blocks
& kota white
stone & @ tonne
slab 0.215 94.34 20.28
3252 2.30kg/cudm
3253 9999 Extra for using white cement L.S. 26.91 2 53.82
3254 Dressing charges
3255 LABOUR
Mason (for plain stone work) 2nd
3256 25 class) day 1.35 403.67 505.58
3257 12 Blacksmith 1st class day 0.032 505.17 15.23
3258 17 Beldar day 0.224 350.00 71.87
3259 18 Coolie Day 0.112 350.00 35.93
3260 10 Bandhani day 0.224 350.00 71.87
3261 Fixing charges
3262 LABOUR
Mason (for plain stone work) 2nd
3263 25 class) day 0.448 403.67 167.78
3264 10 Bandhani day 0.336 350.00 107.8
3265 17 Beldar day 0.336 350.00 107.8
3266 18 Coolie day 0.336 350.00 107.8
3267 11 Bhisti
Cutting marble or sand stone slab day 0.336 350.00 107.8
3268 1237 upto 50 mm thick metre 4 10 40
3269 by mechanical device
3270 9999 Scaffolding L.S. 19.76 2 39.52
3271 Mortar
Rate asfor
perlaying and pointing
Item Number 3.8 of SH:
3272 3.8 Mortars cum 0.018 4129.00 80.45
3273 TOTAL 953.85 W
3274 Add 1 % Water charges on "W" 9.5385
3275 TOTAL
Add GST (multiplying factor 0.1405) 963.39 X
3276 on "X" 135.36
3277 TOTAL
Add 15 % Contractor's profit and 1098.75 Y
3278 overheads on "Y" 164.81
3279 Total 1263.56 Z
3280 Add Cess @ 1% on "Z" 12.64
3281 Cost of 1 sqm. 1276.20
3282 127.60
3283 127.60
3284 378
3285
3287 60 mm Say 4611.6
3288 thick
3289 Details of cost for 1 sqm.
3290 MATERIAL
3291 Finished work = 60 cudm.
3292 Add wastage @ 33.3% = 20 cudm.
3293 Total = 80 cudm.
3294 1161 White sand stone block 10 8 205 1640
3295 Carriage of Stone blocks white & red cudm
3296 2216 sand stone & tonne 0.184 94.34 17.36
3297 kota stone slab @ 2.30kg/cudm
3298 9999 Extra for using white cement L.S. 26.91 2 53.82
3299 Dressing charges
3300 LABOUR
Mason (for plain stone work) 2nd
3301 25 class) day 1.35 403.67 505.58
3302 12 Blacksmith 1st class day 0.032 505.17 15.23
3303 17 Beldar day 0.224 350.00 71.87
3304 18 Coolie day 0.112 350.00 35.93
3305 10 Bandhani day 0.224 350.00 71.87
3306 Fixing charges
3307 LABOUR
Mason (for plain stone work) 2nd
3308 25 class) day 0.448 403.67 167.78
3309 10 Bandhani day 0.336 350.00 107.8
3310 17 Beldar day 0.336 350.00 107.8
3311 18 Coolie day 0.336 350.00 107.8
3312 11 Bhisti
Cutting marble or sand stone slab day 0.336 350.00 107.8
3313 1237 upto 50 mm thick metre 4 10 40
3314 by mechanical device
3315 9999 Scaffolding L.S. 19.76 2 39.52
3316 Mortar
Rate asfor
perlaying and pointing
Item Number 3.8 of SH:
3317 3.8 Mortars cum 0.018 4129.00 80.45
3318 TOTAL 953.85 W
3319 Add 1 % Water charges on "W" 9.5385
3320 TOTAL
Add GST (multiplying factor 0.1405) 963.39 X
3321 on "X" 135.36
3322 TOTAL
Add 15 % Contractor's profit and 1098.75 Y
3323 overheads on "Y" 164.81
3324 Total 1263.56 Z
3325 Add Cess @ 1% on "Z" 12.64
3326 Cost of 1 sqm. 1276.20
3327 Say 127.60 4242.05
3328 50 mm 127.60
3329 thick
3330
3331 379
3332
3334 Details of cost for 1 sqm.
3335 MATERIAL
3336 Finished work = 50 cudm.
3337 Add wastage @ 33.3% = 16.7 cudm.
3338 Total = 66.7 cudm.
3339 1161 White sand stone block 10 6.67 205 1367.35
3340 Carriage of Stone blocks white & red cudm
3341 2216 sand stone & tonne 0.153 94.34 14.43
3342 kota stone slab @ 2.30 kg/cudm.
3343 9999 Extra for using white cement L.S. 26.91 2 53.82
3344 Dressing charges
3345 LABOUR
Mason (for plain stone work) 2nd
3346 25 class) day 1.35 403.67 505.58
3347 12 Blacksmith 1st class day 0.032 505.17 15.23
3348 17 Beldar day 0.224 350.00 71.87
3349 18 Coolie day 0.112 350.00 35.93
3350 10 Bandhani day 0.224 350.00 71.87
3351 Fixing charges
3352 LABOUR
Mason (for plain stone work) 2nd
3353 25 class) day 0.448 403.67 167.78
3354 10 Bandhani day 0.336 350.00 107.8
3355 17 Beldar day 0.336 350.00 107.8
3356 18 Coolie day 0.336 350.00 107.8
3357 11 Bhisti
Cutting marble or sand stone slab day 0.336 350.00 107.8
3358 1237 upto 50 mm thick metre 4 10 40
3359 by mechanical device
3360 9999 Scaffolding L.S. 19.76 2 39.52
3361 Mortar
Rate asfor
perlaying and pointing
Item Number 3.8 of SH:
3362 3.8 Mortars cum 0.018 4129.00 80.45
3363 TOTAL 953.85 W
3364 Add 1 % Water charges on "W" 9.5385
3365 TOTAL
Add GST (multiplying factor 0.1405) 963.39 X
3366 on "X" 135.36
3367 TOTAL
Add 15 % Contractor's profit and 1098.75 Y
3368 overheads on "Y" 164.81
3369 Total 1263.56 Z
3370 Add Cess @ 1% on "Z" 12.64
3371 Cost of 1 sqm. 1276.20
3372 Say 127.60 3873.35
3373 40 mm 127.60
3374 thick
3375
3376 380
3377
3379 Details of cost for 1 sqm.
3380 MATERIAL
3381 Finished work = 40 cudm.
3382 Add wastage @ 33.3% = 13.3 cudm.
3383 Total = 53.3 cudm.
3384 1161 White sand stone block 10 5.33 205 1092.65
3385 Carriage of Stone blocks white & red cudm
3386 2216 sand stone & tonne 0.123 94.34 11.6
3387 kota stone slab @ 2.30 kg/cudm.
3388 9999 Extra for using white cement L.S. 26.91 2 53.82
3389 Dressing charges
3390 LABOUR
Mason (for plain stone work) 2nd
3391 25 class) day 1.35 403.67 505.58
3392 12 Blacksmith 1st class day 0.032 505.17 15.23
3393 17 Beldar day 0.224 350.00 71.87
3394 18 Coolie day 0.112 350.00 35.93
3395 10 Bandhani day 0.224 350.00 71.87
3396 Fixing charges
3397 LABOUR
Mason (for plain stone work) 2nd
3398 25 class) day 0.448 403.67 167.78
3399 10 Bandhani day 0.336 350.00 107.8
3400 17 Beldar day 0.336 350.00 107.8
3401 18 Coolie day 0.336 350.00 107.8
3402 11 Bhisti
Cutting marble or sand stone slab day 0.336 350.00 107.8
3403 1237 upto 50 mm thick metre 4 10 40
3404 by mechanical device
3405 9999 Scaffolding L.S. 19.76 2 39.52
3406 Mortar
Rate asfor
perlaying and pointing
Item Number 3.8 of SH:
3407 3.8 Mortars cum 0.018 4129.00 80.45
3408 TOTAL 953.85 W
3409 Add 1 % Water charges on "W" 9.5385
3410 TOTAL
Add GST (multiplying factor 0.1405) 963.39 X
3411 on "X" 135.36
3412 TOTAL
Add 15 % Contractor's profit and 1098.75 Y
3413 overheads on "Y" 164.81
3414 Total 1263.56 Z
3415 Add Cess @ 1% on "Z" 12.64
3416 Cost of 1 sqm. 1276.20
3417 Say 127.60 3502.05
3418 30 mm 127.60
3419 thick
3420 for 1
3421 sqm.
3422 MATER
3423 IAL
3424
3425 381
3426
3428 Finished work = 30 cudm.
3429 Add wastage @ 33.3% = 9.99 cudm.
3430 Total = 39.99 cudm.
3431 1161 White sand stone block 10 3.999 205 819.8
3432 cudm
Carriage of Stone blocks white & red
3433 2216 sand stone & tonne 0.092 94.34 8.68
3434 kota stone slab @ 2.30 kg/cudm.
3435 9999 Extra for using white cement L.S. 26.91 2 53.82
3436 Dressing charges
3437 LABOUR
Mason (for plain stone work) 2nd
3438 25 class) day 1.35 403.67 505.58
3439 12 Blacksmith 1st class day 0.032 505.17 15.23
3440 17 Beldar day 0.224 350.00 71.87
3441 18 Coolie day 0.112 350.00 35.93
3442 10 Bandhani day 0.224 350.00 71.87
3443 Fixing charges
3444 LABOUR
Mason (for plain stone work) 2nd
3445 25 class) day 0.448 403.67 167.78
3446 10 Bandhani day 0.336 350.00 107.8
3447 17 Beldar day 0.336 350.00 107.8
3448 18 Coolie day 0.336 350.00 107.8
3449 11 Bhisti
Cutting marble or sand stone slab day 0.336 350.00 107.8
3450 1237 upto 50 mm thick metre 4 10 40
3451 by mechanical device
3452 9999 Scaffolding L.S. 19.76 2 39.52
3453 Mortar
Rate asfor
perlaying and pointing
Item Number 3.8 of SH:
3454 3.8 Mortars cum 0.018 4129.00 80.45
3455 TOTAL 953.85 W
3456 Add 1 % Water charges on "W" 9.5385
3457 TOTAL
Add GST (multiplying factor 0.1405) 963.39 X
3458 on "X" 135.36
3459 TOTAL
Add 15 % Contractor's profit and 1098.75 Y
3460 overheads on "Y" 164.81
3461 Total 1263.56 Z
3462 Add Cess @ 1% on "Z" 12.64
3463 Cost of 1 sqm. 1276.20
3464 Say 127.60 3133.05
3465 127.60
rough
3466 backing.
3467 70 mm
3468 thick
3469 for 1
3470 sqm.
3471
3472 382
3473
3475 MATERIAL
3476 Finished work = 70 cudm.
3477 Add wastage @ 33.3% = 23.33 cudm.
3478 Total = 93.33 cudm.
3479 1161 White sand stone block 10 9.333 205 1913.27
3480 cudm
3481 2216 Carriage
red sand stone & kota stone slab @ tonne
of Stone blocks white & 0.215 94.34 20.28
3482 2.30kg/cudm
3483 9999 Extra for using white cement L.S. 26.91 2 53.82
3484 Dressing charges
3485 LABOUR
Mason (for plain stone work) 2nd
3486 25 class) day 2.7 403.67 1011.15
3487 12 Blacksmith 1st class day 0.064 505.17 30.46
3488 17 Beldar day 0.448 350.00 143.73
3489 18 Coolie day 0.224 350.00 71.87
3490 10 Bandhani day 0.448 350.00 143.73
3491 Fixing charges
3492 LABOUR
Mason (for plain stone work) 2nd
3493 25 class) day 0.448 403.67 167.78
3494 10 Bandhani day 0.336 350.00 107.8
3495 17 Beldar day 0.336 350.00 107.8
3496 18 Coolie day 0.336 350.00 107.8
3497 11 Bhisti
Cutting marble or sand stone slab day 0.336 350.00 107.8
3498 1237 upto 50 mm thick metre 4 10 40
3499 by mechanical device
3500 9999 Scaffolding L.S. 19.76 2 39.52
3501 Mortar
Rate asfor
perlaying and pointing
Item Number 3.8 of SH:
3502 3.8 Mortars cum 0.018 4129.00 80.45
3503 TOTAL 1148.74 W
3504 Add 1 % Water charges on "W" 11.4874
3505 TOTAL
Add GST (multiplying factor 0.1405) 1160.23 X
3506 on "X" 163.01
3507 TOTAL
Add 15 % Contractor's profit and 1323.24 Y
3508 overheads on "Y" 198.49
3509 Total 1521.73 Z
3510 Add Cess @ 1% on "Z" 15.22
3511 Cost of 1 sqm. 1536.95
3512 Say 153.70 5548.75
3513 60 mm 153.70
3514 thick
3515 for 1
3516 sqm.
3517 MATER
3518 IAL
3519
3520 383
3521
3523 Finished work = 60 cudm.
3524 Add wastage @ 33.3% = 20 cudm.
3525 Total = 80 cudm.
3526 1161 White sand stone block 10 8 205 1640
3527 cudm
3528 2216 Carriage
red sand of Stone
stone blocks
& kota white
stone & @ tonne
slab 0.184 94.34 17.36
3529 2.30kg/cudm
Extra for using white cement
3530 9999 Dressing charges L.S. 26.91 2 53.82
3531 LABOUR
Mason (for plain stone work) 2nd
3532 25 class) day 2.7 403.67 1011.15
3533 12 Blacksmith 1st class day 0.064 505.17 30.46
3534 17 Beldar day 0.448 350.00 143.73
3535 18 Coolie day 0.224 350.00 71.87
3536 10 Bandhani day 0.448 350.00 143.73
3537 Fixing charges
3538 LABOUR
Mason (for plain stone work) 2nd
3539 25 class) day 0.448 403.67 167.78
3540 10 Bandhani day 0.336 350.00 107.8
3541 17 Beldar day 0.336 350.00 107.8
3542 18 Coolie day 0.336 350.00 107.8
3543 11 Bhisti
Cutting marble or sand stone slab day 0.336 350.00 107.8
3544 1237 upto 50 mm thick metre 4 10 40
3545 by mechanical device
3546 9999 Scaffolding L.S. 19.76 2 39.52
3547 Mortar
Rate asfor
perlaying and pointing
Item Number 3.8 of SH:
3548 3.8 Mortars cum 0.018 4129.00 80.45
3549 TOTAL 1148.74 W
3550 Add 1 % Water charges on "W" 11.4874
3551 TOTAL
Add GST (multiplying factor 0.1405) 1160.23 X
3552 on "X" 163.01
3553 TOTAL
Add 15 % Contractor's profit and 1323.24 Y
3554 overheads on "Y" 198.49
3555 Total 1521.73 Z
3556 Add Cess @ 1% on "Z" 15.22
3557 Cost of 1 sqm. 1536.95
3558 Say 153.70 5179.25
3559 50 mm 153.70
3560 thick
3561 for 1
3562 sqm.
3563 MATER
3564 IAL
3565 work =
3566 50 cudm.
3567 16.7
3568 cudm.
3569 66.7
3570 cudm.
3571
3572 384
3573
3575 1161 White sand stone block 10 6.67 205 1367.35
3576 Carriage of Stone blocks white & red cudm
3577 2216 sand stone & tonne 0.153 94.34 14.43
3578 kota stone slab @ 2.30 kg/cudm.
3579 9999 Extra for using white cement L.S. 26.91 2 53.82
3580 Dressing charges
3581 LABOUR
Mason (for plain stone work) 2nd
3582 25 class) day 2.7 403.67 1011.15
3583 12 Blacksmith 1st class day 0.064 505.17 30.46
3584 17 Beldar day 0.448 350.00 143.73
3585 18 Coolie day 0.224 350.00 71.87
3586 10 Bandhani day 0.448 350.00 143.73
3587 Fixing charges
3588 LABOUR
Mason (for plain stone work) 2nd
3589 25 class) day 0.448 403.67 167.78
3590 10 Bandhani day 0.336 350.00 107.8
3591 17 Beldar day 0.336 350.00 107.8
3592 18 Coolie day 0.336 350.00 107.8
3593 11 Bhisti
Cutting marble or sand stone slab day 0.336 350.00 107.8
3594 1237 upto 50 mm thick metre 4 10 40
3595 by mechanical device
3596 9999 Scaffolding L.S. 19.76 2 39.52
3597 Mortar
Rate asfor
perlaying and pointing
Item Number 3.8 of SH:
3598 3.8 Mortars cum 0.018 4129.00 80.45
3599 TOTAL 1148.74 W
3600 Add 1 % Water charges on "W" 11.4874
3601 TOTAL
Add GST (multiplying factor 0.1405) 1160.23 X
3602 on "X" 163.01
3603 TOTAL
Add 15 % Contractor's profit and 1323.24 Y
3604 overheads on "Y" 198.49
3605 Total 1521.73 Z
3606 Add Cess @ 1% on "Z" 15.22
3607 Cost of 1 sqm. 1536.95
3608 40 mm Say 153.70 4810.55
3609 thick 153.70
3610 Details of cost for 1 sqm.
3611 MATERIAL
3612 Finished work = 40 cudm.
3613 Add wastage @ 33.3% = 13.3 cudm.
3614 Total = 53.3 cudm.
3615 1161 White sand stone block 10 5.33 205 1092.65
3616 cudm
3617
3618
3619 385
3620 Carriage of Stone blocks white & red
3622 2216 sand stone & tonne 0.123 94.34 11.6
3623 kota stone slab @ 2.30 kg/cudm.
3624 9999 Extra for using white cement L.S. 26.91 2 53.82
3625 Dressing charges
3626 LABOUR
Mason (for plain stone work) 2nd
3627 25 class) day 2.7 403.67 1011.15
3628 12 Blacksmith 1st class day 0.064 505.17 30.46
3629 17 Beldar day 0.448 350.00 143.73
3630 18 Coolie day 0.224 350.00 71.87
3631 10 Bandhani day 0.448 350.00 143.73
3632 Fixing charges
3633 LABOUR
Mason (for plain stone work) 2nd
3634 25 class) day 0.448 403.67 167.78
3635 10 Bandhani day 0.336 350.00 107.8
3636 17 Beldar day 0.336 350.00 107.8
3637 18 Coolie day 0.336 350.00 107.8
3638 11 Bhisti
Cutting marble or sand stone slab day 0.336 350.00 107.8
3639 1237 upto 50 mm thick metre 4 10 40
3640 by mechanical device
3641 9999 Scaffolding L.S. 19.76 2 39.52
3642 Mortar
Rate asfor
perlaying and pointing
Item Number 3.8 of SH:
3643 3.8 Mortars cum 0.018 4129.00 80.45
3644 TOTAL 1148.74 W
3645 Add 1 % Water charges on "W" 11.4874
3646 TOTAL
Add GST (multiplying factor 0.1405) 1160.23 X
3647 on "X" 163.01
3648 TOTAL
Add 15 % Contractor's profit and 1323.24 Y
3649 overheads on "Y" 198.49
3650 Total 1521.73 Z
3651 Add Cess @ 1% on "Z" 15.22
3652 Cost of 1 sqm. 1536.95
3653 Say 153.70 4439.2
3654 30 mm 153.70
3655 thick
3656 for 1
3657 sqm.
3658
3659 MATERIAL
3660 Finished work = 30 cudm.
3661 Add wastage @ 33.3% = 9.99 cudm.
3662 Total = 39.99 cudm.
3663 1161 White sand stone block 10 3.999 205 819.8
3664 Carriage of Stone blocks white & red cudm
3665 2216 sand stone & tonne 0.092 94.34 8.68
3666 kota stone slab @ 2.30 kg/cudm.
3667
3668 386
3669
3671 9999 Extra for using white cement L.S. 26.91 2 53.82
3672 Dressing charges
3673 LABOUR
Mason (for plain stone work) 2nd
3674 25 class) day 2.7 403.67 1011.15
3675 12 Blacksmith 1st class day 0.064 505.17 30.46
3676 17 Beldar day 0.448 350.00 143.73
3677 18 Coolie day 0.224 350.00 71.87
3678 10 Bandhani day 0.448 350.00 143.73
3679 Fixing charges
3680 LABOUR
Mason (for plain stone work) 2nd
3681 25 class) day 0.448 403.67 167.78
3682 10 Bandhani day 0.336 350.00 107.8
3683 17 Beldar day 0.336 350.00 107.8
3684 18 Coolie day 0.336 350.00 107.8
3685 11 Bhisti
Cutting marble or sand stone slab day 0.336 350.00 107.8
3686 1237 upto 50 mm thick metre 4 10 40
3687 by mechanical device
3688 9999 Scaffolding L.S. 19.76 2 39.52
3689 Mortar
Rate asfor
perlaying and pointing
Item Number 3.8 of SH:
3690 3.8 Mortars cum 0.018 4129.00 80.45
3691 TOTAL 1148.74 W
3692 Add 1 % Water charges on "W" 11.4874
3693 TOTAL
Add GST (multiplying factor 0.1405) 1160.23 X
3694 on "X" 163.01
3695 TOTAL
Add 15 % Contractor's profit and 1323.24 Y
3696 overheads on "Y" 198.49
3697 Total 1521.73 Z
3698 Add Cess @ 1% on "Z" 15.22
3699 Cost of 1 sqm. 1536.95
3700 saw cut Say 153.70 4070.25
3701 stone 153.70
sand
3702 stone
3703 Details of cost for 1 sqm.
3704 MATERIAL
3705 1.00 sqm + 0.05 sqm
3706 (Add
Whitewastage @ 5%)
sand stone gang= 1.05
saw sqm
cut 30
3707 8684 Carriage
mm thickof Stone blocks white & red sqm 1.05 560 588
3708 2216 sand stone & tonne 0.072 94.34 6.79
3709 kota
Extrastone slab white
for using @ 2.30 kg/cudm.
cement Fixing
3710 9999 charges L.S. 26.91 2 53.82
3711 LABOUR
Mason (for plain stone work) 2nd
3712 25 class day 0.448 403.67 167.78
3713
3714
3715 387
3716
3718 10 Bandhani day 0.336 350.00 107.8
3719 17 Beldar day 0.336 350.00 107.8
3720 18 Coolie day 0.336 350.00 107.8
3721 11 Bhisti
Cutting marble or sand stone slab day 0.336 350.00 107.8
3722 1237 upto 50 mm thick metre 4 10 40
3723 by mechanical device
3724 9999 Scaffolding
Cement mortar 1:3 (1 cement : 3 L.S. 19.76 2 39.52
3725 coarse
Rate assand)
per Item Number 3.8 of SH:
3726 3.8 Mortars cum 0.018 4129.00 80.45
3727 TOTAL 812.77 W
3728 Add 1 % Water charges on "W" 8.1277
3729 TOTAL
Add GST (multiplying factor 0.1405) 820.90 X
3730 on "X" 115.34
3731 TOTAL
Add 15 % Contractor's profit and 936.24 Y
3732 overheads on "Y" 140.44
3733 Total 1076.68 Z
3734 Add Cess @ 1% on "Z" 10.77
3735 Cost of 1 sqm. 1087.45
3736 sand Say 108.70 1883.2
3737 stone 108.70
3738 Details of cost for 1 sqm.
3739 MATERIAL
3740 1.00 sqm + 0.05 sqm
3741 (Add wastage
Red sand @gang
stone 5%) =saw
1.05cut
sqm30 mm
3742 8683 thick
Carriage of Stone blocks white & red sqm 1.05 425 446.25
3743 2216 sand stone & tonne 0.072 94.34 6.79
3744 kota stone slab @ 2.30 kg/cudm.
3745 9999 Extra for using white cement L.S. 26.91 2 53.82
3746 Fixing charges
3747 LABOUR
Mason (for plain stone work) 2nd
3748 25 class day 0.448 403.67 167.78
3749 10 Bandhani day 0.336 350.00 107.8
3750 17 Beldar day 0.336 350.00 107.8
3751 18 Coolie day 0.336 350.00 107.8
3752 11 Bhisti
Cutting marble or sand stone slab day 0.336 350.00 107.8
3753 1237 upto 50 mm thick metre 4 10 40
3754 by mechanical device
3755 9999 Scaffolding
Cement mortar 1:3 (1 cement : 3 L.S. 19.76 2 39.52
3756 coarse
Rate assand)
per Item Number 3.8 of SH:
3757 3.8 Mortars cum 0.018 4129.00 80.45
3758 TOTAL 1265.81 W
3759 Add 1 % Water charges on "W" 12.6581
3760 1278.47 X
3761 179.62
3762 388 1458.09 Y
3763 218.71
3765 0.1405)
TOTAL 1278.46 1676.80 Z
3766 on "X" 179.62 16.77
3767 ds
TOTAL
on 1458.09 1693.57
3768 "Y" 218.71 169.40
3769 Total 1676.8 169.40
1% on
3770 "Z"
Cost of 16.77
3771 1 sqm. 1693.57
3772 Say 3396.1
3773 making
3774 the
3775 required
3776 .
3777 cramp of
3778 0.934kg
3779 steel
3780 cramp
3781 13.3 x
3782 10^5
3783 0.010 x
3784 0.006
3785 #ERROR
3786 !
3787 #ERROR
3788 !
3789 #ERROR
3790 !
3791
3792 Total = 0.981 kg.
3793 7339 Stainless steel cramp kilogra 0.981 290 284.49
3794 m
3795 9977 CARRIAGE
Cement mortar 1:2 (1 cement : 2 L.S. 3.9 2 7.8
3796 coarse
Rate assand)
per Item Number 3.7 of SH:
3797 3.7 Mortars cum 0.001 4722.70 5.15
3798 9999 Labour for fixing in position L.S. 65 2 130
3799 TOTAL 427.44 W
3800 Add 1 % Water charges on "W" 4.2744
3801 TOTAL
Add GST (multiplying factor 0.1405) 431.71 X
3802 on "X" 60.66
3803 TOTAL
Add 15 % Contractor's profit and 492.37 Y
3804 overheads on "Y" 73.86
3805 Total 566.23 Z
3806 Add Cess @ 1% on "Z" 5.66
3807 Cost for 0.934 kg. 571.89
3808 Cost per kg 57.20
3809 Say 57.20 612.3
3810
3811 389
3812
3814 2 coarse
3815 sand),
3816 necessar
3817 y chases.
3818 copper
3819 pin
3820
3821 MATERIAL
3822 873 Copper pins
Labour for 6 mm dia
making pin 7.5 cm
in to long
required each 1 10 10
3823 9999 shape
cuttingand size,in stone and fixing in
chases L.S. 3.9 2 7.8
3824 position
Cement mortar 1:2 (1 cement : 2
3825 coarse
Rate assand)
per Item Number 3.7 of SH:
3826 3.7 Mortars
Sundries including hire charges of cum 0.001 4722.70 5.15
3827 9999 hand cut machine e L.S. 1.95 2 3.9
3828 TOTAL 26.85 W
3829 Add 1 % Water charges on "W" 0.2685
3830 TOTAL
Add GST (multiplying factor 0.1405) 27.12 X
3831 on "X" 3.81
3832 TOTAL
Add 15 % Contractor's profit and 30.93 Y
3833 overheads on "Y" 4.64
3834 Total 35.57 Z
3835 Add Cess @ 1% on "Z" 0.36
3836 Cost of one copper pin 35.93
3837 Say 3.60 35.9
3838 complet 3.60
3839 e as
3840 -in-
3841 charge.
3842 40mm
3843 thick
3844 face =
3845 1.00sqm.
3846 sqm. =
3847 0.88sqm.
3848 5% =
3849 0.04sqm.
3850
3851 Total #ERROR!
3852 1165 White sand stone slab 40 mm thick sqm 0.92 280 184
3853 (un-dressed)
3854 75mm thick
3855 3x0.04x1.0 = 0.12 sqm.
3856 Add wastage 5% = 0.01 sqm.
3857 Total
White sand stone slab 75 mm thick #ERROR!
3858 1163 (un-dressed) sqm 0.13 900 117
3859
3860 390
3861 Carriage of Stone blocks white & red
3863 2216 kota
sandstone
stoneslab
& 0.92x0.04 = 0.0368 tonne 0.108 94.34 10.19
3864 cum.
3865 0.13x0.075 = 0.0100 cum.
3866 #ERROR!
3867 468 cudm @ 2.3 kg/cudm = 108 kg
3868 #ERROR!
Cutting marble or sand stone slab
3869 1237 upto 50 mm thick metre 20 10 200
3870
cal
3871 device
3872 20x1.0 =
3873 20 metre
3874 sand 1:3
3875 for
3876 0.0144
3877 cum.
3878 0.0304
3879 cum.
3880 Rate as per Item Number 3.8 of SH:
3881 3.8 Mortars
chases and making good with mortar cum
Cutting 0.0304 4129.00 135.87
3882 after insurting
3883 stone
Rate as etc.
per Item Number 18.78 of
3884 SH: Water
18.78 White cement and pigment for metre 3 97.7 293.10 A
3885 9999 pointing L.S. 40.43 2 80.86
3886 LABOUR
Mason (for ornamental stone work)
3887 26 1st
Masonclass
(for plain stone work) 2nd day 0.25 505.17 119
3888 25 class) day 0.25 403.67 93.63
3889 17 Beldar day 0.5 350.00 160.42
3890 11 Bhisti
Sundries and scaffolding brushes day 0.03 350.00 9.62
3891 9999 etc. L.S. 26.91 2 53.82
3892 TOTAL 1457.51 W
3893 Add 1 % Water charges on "W-A" 1164.41 11.64
3894 TOTAL
Add GST (multiplying factor 0.1405) 1469.15 X
3895 on "X-A" 1176.05 165.24
3896 TOTAL
Add 15 % Contractor's profit and 1634.39 Y
3897 overheads on "Y-A" 1341.29 201.19
3898 Total 1835.58 Z
3899 Add Cess @ 1% on "Z-A" 1542.48 15.42
3900 Cost of 1sqm. 1851
3901 Say 1851
3902 separate
3903 ly).
3904 25 mm
3905 thick
3906 for
3907 10sqm.
3908
3909 391
3910
3912 MATERIAL
25mm thick kota stone slabs = 10
3913 sqm.
3914 Add 15% wastage = 1.50 sqm.
3915 Total = 11.50
Kotastone sqm.
slab 25mm thick (rough
3916 1169 cheseled)
Carriage of Stone blocks white & red sq.m. 11.5 400 3461.5
3917 2216 sand stone & tonne 0.67 94.34 63.21
3918 kota stone
Cement slab 1:3 (1 cement : 3
mortar
3919 coarse sand)
Rate as per Item Number 3.8 of SH:
3920 3.8 Mortars cum 0.144 4129.00 643.61
3921 9999 Cement mortar for pointing. L.S. 40.43 2 80.86
3922 LABOUR
Mason (for plain stone work) 2nd
3923 25 class) day 6.5 403.67 2434.25
3924 17 Beldar day 6.5 350.00 2085.4
3925 18 Coolie day 4.3 350.00 1379.57
3926 37 Skilled Beldar (for floor rubbing etc.) day 10.8 350.00 3464.96
3927 9999 Sundries L.S. 111.54 2 223.08
3928 TOTAL 13836.44 W
3929 Add 1 % Water charges on "W" 138.3644
3930 TOTAL
Add GST (multiplying factor 0.1405) 13974.80 X
3931 on "X" 1963.46
3932 TOTAL
Add 15 % Contractor's profit and 15938.26 Y
3933 overheads on "Y" 2390.74
3934 Total 18329.00 Z
3935 Add Cess @ 1% on "Z" 183.29
3936 Cost for 10 sqm. 18512.29
3937 Cost of 1 sqm. 1851.20
3938 Say 1851.20 1851.25
3939 part
3940 there of.
3941
3942 Detail of cost for 10 sqm
3943 Analysis same as Item Number 13.74
3944 MATERIAL
3945 9999 Scaffolding L.S. 215.28 2 430.56
3946 23 Mason (brick layer) 1st class day 0.3 505.17 142.8
3947 17 Beldar day 0.3 350.00 96.25
3948 11 Bhisti day 0.15 350.00 48.12
3949 9999 Sundries L.S. 28.6 2 57.2
3950 TOTAL 41501.92 W
3951 Add 1 % Water charges on "W" 415.01919
3952 TOTAL
Add GST (multiplying factor 0.1405) 41916.94 X
3953 on "X" 5889.33
3954 TOTAL 47806.27 Y
3955 7170.94
3956 392 54977.21 Z
3957 ds on 549.77
3959 "Y" 133.9 55526.98
3960 1%
Total
on 1026.55 5552.70
3961 "Z"
Cost for 10.27 5552.70
3962 10 sqm.
Cost of 1036.81
3963 1 sqm. 103.68
3964 Say 1693.55
3965 separate
3966 ly).
3967 saw cut
3968 stone
3969
3970 Details of cost for 1 sqm.
3971 MATERIAL
3972 Red sand stone = 1.00sqm
3973 Add 5% wastage = 0.05sqm
3974 Total = 1.05
Red sand sqmgang saw cut 30 mm
stone
3975 8683 thick
Carriage of Stone blocks white & red sqm 1.05 425 446.25
3976 2216 sand stone & tonne 0.072 94.34 6.79
3977 kota stone slab
3978 @ 2.30kg/cudm
3979 Fixing Charges
3980 LABOUR
Mason (for plain stone work) 2nd
3981 25 class day 0.448 403.67 167.78
3982 10 Bandhani day 0.336 350.00 107.8
3983 17 Beldar day 0.336 350.00 107.8
3984 18 Coolie
Cutting marble or sand stone slab up day 0.336 350.00 107.8
3985 1237 to 50 mm thick metre 4 10 40
3986 by mechanical device
3987 9999 Scaffolding
Fixing including weather sealant and L.S. 19.76 2 39.52
3988 9999 removing L.S. 51.1 2 102.2
3989 9999 Silicon gun/ pump etc. L.S. 68.25 2 136.5
3990 TOTAL 1262.44 W
3991 Add 1 % Water charges on "W" 12.6244
3992 TOTAL
Add GST (multiplying factor 0.1405) 1275.06 X
3993 on "X" 179.15
3994 TOTAL
Add 15 % Contractor's profit and 1454.21 Y
3995 overheads on "Y" 218.13
3996 Total 1672.34 Z
3997 16.72
3998 393 1689.06
3999 168.90
4001 Add Cess @ 1% on "Z" 168.90
4002 Cost of 1 sqm 1689.06
4003 saw cut Say 1689.05
4004 stone
4005 Details of cost for 1 sqm.
4006 MATERIAL
4007 Red sand stone = 1.00sqm
4008 Add 5% wastage = 0.05sqm
4009 Total
White=sand
1.05 stone
sqm gang saw cut 30
4010 8684 mm thickof Stone blocks white & red sqm
Carriage 1.05 560 588
4011 2216 sand stone & tonne 0.072 94.34 6.79
4012 kota stone slab
4013 @ 2.30kg/cudm
4014 Fixing Charges
4015 LABOUR
Mason (for plain stone work) 2nd
4016 25 class day 0.448 403.67 167.78
4017 10 Bandhani day 0.336 350.00 107.8
4018 17 Beldar day 0.336 350.00 107.8
4019 18 Coolie
Cutting marble or sand stone slab up day 0.336 350.00 107.8
4020 1237 to 50 mm thick metre 4 10 40
4021 by mechanical device
4022 9999 Scaffolding
Fixing including weather sealant and L.S. 19.76 2 39.52
4023 9999 removing L.S. 51.1 2 102.2
4024 9999 Silicon gun/ pump etc. L.S. 68.25 2 136.5
4025 TOTAL 1404.19 W
4026 Add 1 % Water charges on "W" 14.0419
4027 TOTAL
Add GST (multiplying factor 0.1405) 1418.23 X
4028 on "X" 199.26
4029 TOTAL
Add 15 % Contractor's profit and 1617.49 Y
4030 overheads on "Y" 242.62
4031 Total 1860.11 Z
4032 Add Cess @ 1% on "Z" 18.60
4033 Cost of 1 sqm 1878.71
4034 Say 187.90 1878.7
4035 187.90
4036
4037 394
4038
4040 ly and
4041 nothing
4042 shall be
4043 paid).
4044 50x25x1
4045 8mm
4046
4047 Vertical 4.0x3.0 mtr = 12.00
4048 Vertical 4.0x3.0x0.93 =11.16 m
4049 Total = 23.16 mtr
4050 Add
Total10% wastage
25.48mtr = 2.32
@ 2.02 m = 51.47
kg/m
4051 kg
Mild steel tubes hot finished welded
4052 4009 type kilogra 51.47 57 2933.79
4053 Angle iron 50x50x6mm m
4054 16x0.60=9.60
4055 16x0.15=2.40
4056 Total=12.00
4057 Add 10% wastage = 1.20m
4058 Total=13.20m
4059 @4.50kg/m=59.40kg or 0.594 q
Structurals such as tees,angles
4060 1007 channels and R.S. quintal 0.594 5300 2732.4
4061 joists
Cement concrete 1:2:4
4062 =16x0.30x0.23x
4063 0.30=0.331 cum
4064 4.1.3 Rate as per item no. 4.1.3 of cum 0.331 5924.90 1970.89 A
4065 SH : concrete work
4066 Making holes in brick work=16nos.
4067 layer) LABOUR
4068 1st
2ndclass day 0.26 403.67 123.76
4069 class day 0.26 403.67 97.37
4070 17 Beldar day 2 350.00 641.66
4071 Welding for frame welding
4072 16x(2.5+5+2.5+5) = 240 cm
4073 16x20cm
4074 = 320cm
4075 Total =
4076 560cm
4077
4078 395
4079
4081 1215 Welding by electric plant cm 560 2 1120
4082 LABOUR
4083 12 Blacksmith 1st class day 1.34 505.17 637.84
4084 10 Bandhani day 0.67 350.00 214.96
4085 17 Beldar day 4.92 350.00 1578.48
4086 9999 Sundries
Painting with epoxy paint over and L.S. 80.73 2 161.46
4087 including priming
4088 coat area 22.80x0.15 = 3.42
4089 12x0.2 = 2.40
4090 Total = 5.82sqm
Rate as per Item no. 13.52.1 of SH:
4091 13.52.1 Finishing sqm 5.82 63.70 771.15 A
4092 9999 For labour scaffocaling etc L.S. 80.73 2 161.46
4093 Total 13145.22 W
4094 Add 1 % Water charges on "W-A" 10403.18 104.03
4095 TOTAL
Add GST (multiplying factor 0.1405) 13249.25 X
4096 on "X-A" 10507.21 1476.26
4097 TOTAL
Add 15 % Contractor's profit and 14725.51 Y
4098 overheads on "Y-A" 11983.47 1797.52
4099 Total 16523.04 Z
4100 Add Cess @ 1% on "Z-A" 13781 137.81
4101 Cost for 100.78 kg 16660.85
4102 Cost for 1 kg 165.32
4103 Say 165.3
4104 required
4105 holes
4106
-in-
4107 charge.
4108 for 10
4109 Nos.
4110 Stainless steel cramps(weight 260
4111 8698 grams) with
bolts and nuts, for dry stone
washer each 10 100 1000
4112 cladding
4113 LABOUR
For making holes, recesses etc. and
4114 fixing of stainless
4115 13 Blacksmith 2nd class day 0.1 403.67 37.45
4116 24 Mason (brick layer) 2nd class day 1 403.67 374.5
4117 17 Beldar
Scaffolding, hire charges of drill day 1.1 350.00 352.91
4118 9999 machine etc. L.S. 20.8 2 41.6
4119 9999 Sundries L.S. 20.8 2 41.6
4120 Total 1848.06 W
4121 18.4806
4122 396 1866.54 X
4123 charges 262.25
4125 on "W" 18.48 2128.79 Y
4126 0.1405)
TOTAL 1866.54 319.32
4127 on "X" 262.25 2448.11 Z
4128 ds
TOTAL
on 2128.79 24.48
4129 "Y" 319.32 2472.59
4130 1%
Total
on 2448.11 247.30
4131 "Z"
Cost for 24.48 247.30
4132 10 Nos.
Cost for 2472.59
4133 1 Nos. 247.26
4134 Say 103.7
4135 walls
4136 etc.
4137
4138 Details of cost for 100 Nos.
4139 MATERIAL
4140 Teak wood (2nd class)
100x(50x50x50)mm = 0.0125cum Add
4141 wastage @
4142 10% = 0.0013 cum.
4143 Total = 0.0138 cum.
4144 Say 14 cudm.
4145 1189 Second class teak wood in scantling 10 1.4 776 1086.4
4146 cudm
4147 2204 Carriage of Timber
Cement mortar 1 : 3 (1 cement : 3 cum 0.014 121.29 1.7
4148 fine sand)
4149 3.3 Rate as per Item Number 3.3 of cum 0.002 3670.3 7.98
4150 SH: Mortars
4151 LABOUR
4152 15 Carpenter 2nd class day 0.75 403.67 280.88
4153 24 Mason (brick layer) 2nd class day 0.75 403.67 280.88
4154 17 Beldar day 0.75 350.00 240.62
4155 TOTAL 1898.46 W
4156 Add 1 % Water charges on "W" 18.9846
4157 TOTAL
Add GST (multiplying factor 0.1405) 1917.44 X
4158 on "X" 269.40
4159 TOTAL
Add 15 % Contractor's profit and 2186.84 Y
4160 overheads on "Y" 328.03
4161 Total 2514.87 Z
4162 Add Cess @ 1% on "Z" 25.15
4163 Cost of 100 nos. 2540.02
4164 Cost of 1 no. 254.00
4165 254.00
4166 397
4167
4169 Say 247.25
4170 work
4171 /CC/
4172 25 mm
4173 long
4174
4175 Details of cost of 10 nos.
4176 MATERIAL
Expandable fastner with plastic
4177 7312 sleeve and M.S. each 10 10 100
4178 screws. 25 drilling
Labour for mm long holes and making
4179 9999 good etc. L.S. 20.8 2 41.6
4180 TOTAL 3189.62 W
4181 Add 1 % Water charges on "W" 31.896246
4182 TOTAL
Add GST (multiplying factor 0.1405) 3221.52 X
4183 on "X" 452.62
4184 TOTAL
Add 15 % Contractor's profit and 3674.14 Y
4185 overheads on "Y" 551.12
4186 Total 4225.26 Z
4187 Add Cess @ 1% on "Z" 42.25
4188 Cost of 10 nos. 4267.51
4189 Cost of 1 no. 426.80
4190 Say 426.80 18.95
4191 8.24.2 32 mm long
4192 Details of cost of 10 nos.
4193 MATERIAL
Expandable fastner with plastic
4194 7313 sleeve and M.S. each 10 10 100
4195 screws. 32 drilling
Labour for mm long holes and making
4196 9999 good etc. L.S. 26 2 52
4197 TOTAL 17471.92 W
4198 Add 1 % Water charges on "W" 174.7192
4199 TOTAL
Add GST (multiplying factor 0.1405) 17646.64 X
4200 on "X" 2479.35
4201 TOTAL
Add 15 % Contractor's profit and 20125.99 Y
4202 overheads on "Y" 3018.90
4203 Total 23144.89 Z
4204 Add Cess @ 1% on "Z" 231.45
4205 Cost of 10 nos. 23376.34
4206 Cost of 1 no. 2337.60
4207 Say 2337.60 20.35
4208 8.24.3 40 mm long
4209 Details of cost of 10 nos.
4210 MATERIAL
4211
4212
4213 398
4214 Expandable fastner with plastic
4216 7314 sleeve and M.S. each 10 13 130
4217 screws. 40 drilling
Labour for mm long holes and making
4218 9999 good etc. L.S. 26 2 52
4219 TOTAL 54628.78 W
4220 Add 1 % Water charges on "W" 546.28778
4221 TOTAL
Add GST (multiplying factor 0.1405) 55175.07 X
4222 on "X" 7752.10
4223 TOTAL
Add 15 % Contractor's profit and 62927.17 Y
4224 overheads on "Y" 9439.07
4225 Total 72366.24 Z
4226 Add Cess @ 1% on "Z" 723.66
4227 Cost of 10 nos. 73089.90
4228 Cost of 1 no. 7309.00
4229 Say 7309.00 24.35
4230 8.24.4 50 mm long
4231 Details of cost of 10 nos.
4232 MATERIAL
Expandable fastner with plastic
4233 7315 sleeve and M.S. each 10 14 140
4234 screws. 50 drilling
Labour for mm long holes and making
4235 9999 good etc. L.S. 26 2 52
4236 TOTAL 296829.48 W
4237 Add 1 % Water charges on "W" 2968.2948
4238 TOTAL
Add GST (multiplying factor 0.1405) 299797.77 X
4239 on "X" 42121.59
4240 TOTAL
Add 15 % Contractor's profit and 341919.36 Y
4241 overheads on "Y" 51287.90
4242 Total 393207.26 Z
4243 Add Cess @ 1% on "Z" 3932.07
4244 Cost of 10 nos. 397139.33
4245 Cost of 1 no. 39713.90
4246 Say 39713.90 25.7
4247 ed
4248 surface.
4249 mm
4250 thick
4251 of cost of
4252 10 nos.
4253 MATER
4254 IAL
4255 0.40cum
4256 +
4257 = 0.04
4258 cum.
4259
4260 399
4261
4263 Total = 0.44 cum.
4264 Say 440 cudm.
4265 1190 Second class teak wood in planks 10 44 791 34804
4266 Extra for selected planks of second cudm
4267 1231 class
Second teakwood
class teak wood plugs 10 44 150 6600
4268 including
work cement mortar 1:3 cudm
cuttinginbrick
and fixing
4269 (1 cement : 3
4270 fine sand)
4271 8.23 Rate as perwork
SH : Wood item and
no 8.23
PVCofwork each 55 25.4 1397.00 A
4272 Priming
Rate coatitem no 13.50.1 of SH :
as per
4273 13.50.1 Finishing sqm 10 40.90 389.50 A
4274 2204 Carriage of Timber cum 0.44 121.29 53.37
4275 LABOUR
4276 For planning and fixing
4277 14 Carpenter 1st class day 2.15 505.17 1023.4
4278 17 Beldar day 1.62 350.00 519.74
4279 9999 Sundries & screws etc. L.S. 53.82 2 107.64
4280 TOTAL 44894.65
4281 Add 1 % Water charges on "W-A" 43108.15 431.08
4282 TOTAL
Add GST (multiplying factor 0.1405) 45325.73 X
4283 on "X-A" 43539.23 6117.26
4284 TOTAL
Add 15 % Contractor's profit and 51443 Y
4285 overheads on "Y-A" 49656.5 7448.47
4286 Total 58891.47 Z
4287 Add Cess @ 1% on "Z-A" 57104.97 571.05
4288 Cost of 10 sqm. 59462.52
4289 Cost of 1 sqm. 5946.25
4290 Say 5946.25
4291 8.25.2 25 mm thick
4292 Details of cost of 10 nos.
4293 MATERIAL
Teak wood 2nd class 10x0.25 =
4294 0.25cum+ Add
4295 wastage @ 10% = 0.025 cum.
4296 Total = 0.275 cum.
4297 Say 275 cudm.
4298 1190 Second class teak wood in planks 10 27.5 791 21752.5
4299 Extra for selected planks of second cudm
4300 1231 class teakwood 10 27.5 150 4125
4301 cudm
4302 2204 Carriage of Timber cum 0.28 121.29 33.36
4303
4304
4305 400
4306 Second class teak wood plugs
4308 including cuttinginbrick
work and fixing cement mortar 1:3
4309 (1 cement : 3
4310 fine sand)
4311 8.23 Rate as per item no 8.23 of each 55 25.4 1397 A
4312 SH : Wood work
4313 Priming coat
4314 13.50.1 Rate as per item no 13.50.1 of sqm 10 40.90 389.52 A
4315 SH : Finishing
4316 LABOUR
4317 14 Carpenter 1st class day 2.15 505.17 1023.4
4318 17 Beldar day 1.62 350.00 519.74
4319 9999 Sundries & screws etc. L.S. 53.82 2 107.64
4320 TOTAL 29348.16
4321 Add 1 % Water charges on "W-A" 27561.64 275.62
4322 TOTAL
Add GST (multiplying factor 0.1405) 29623.78 X
4323 on "X-A" 27837.26 3911.13
4324 TOTAL
Add 15 % Contractor's profit and 33534.91 Y
4325 overheads on "Y-A" 31748.39 4762.26
4326 Total 38297.17 Z
4327 Add Cess @ 1% on "Z-A" 36510.65 365.11
4328 Cost of 10 sqm. 38662.28
4329 Cost of 1.00 sqm. 3866.23
4330 Say 3866.25
4331 8.25.3 20 mm thick
4332 Details of cost of 10 nos.
4333 MATERIAL
4334 Teak wood (2nd class) 10x0.02m
4335 #ERROR!
4336 Add wastage @ 10% = 0.02 cum.
4337 Total = 0.22 cum.
4338 Say 220 cudm.
4339 1190 Second class teak wood in planks 10 22 791 17402
4340 Extra for selected planks of second cudm
4341 1231 class teakwood 10 22 150 3300
4342 cudm
4343 2204 Carriage of Timber
Second class teak wood plugs cum 0.22 121.29 26.68
4344 including
work cuttinginbrick
and fixing cement mortar 1:3
4345 (1 cement : 3
4346 fine
Ratesand)
as per item no 8.23 of SH :
4347 8.23 Wood work Priming each 55 25.4 1397 A
4348 coat
Rate as per item no 13.50.1 of SH : A
4349 13.50.1 Finishing sqm 10 40.90 389.52
4350 LABOU
4351 R
4352
4353 401
4354
4356 14Carpenter 1st class day 1.08 505.17 514.08
4357 15Carpenter 2nd class day 0.8 403.67 299.6
4358 17Beldar day 1.08 350.00 346.5
4359 9999
Sundries & screws etc. L.S. 53.82 2 107.64
4360 TOTAL 23783.02 W
4361 Add 1 % Water charges on "W-A" 21996.5 219.97
4362 TOTAL
Add GST (multiplying factor 0.1405) 24002.99 X
4363 on "X-A" 22216.47 3121.41
4364 TOTAL
Add 15 % Contractor's profit and 27124.4 Y
4365 overheads on "Y-A" 25337.88 3800.68
4366 Total 30925.08 Z
4367 Add Cess @ 1% on "Z-A" 29138.56 291.39
4368 Cost of 10 sqm. 31216.47
4369 Cost of 1 sqm. 3121.65
4370 Say 3121.65
4371 8.25.4 12 mm thick
4372 Details of cost of 10 nos.
4373 Wood-
4374 Second class teak wood
4375 10x0.012 = 0.12 cum+
4376 Add wastage @ 10% = 0.012 cum.
4377 Total = 0.132 cum.
4378 Say 132 cudm.
4379 1190 Second class teak wood in planks 10 13.2 791 10441.2
4380 Extra for selected planks of second cudm
4381 1231 class teakwood 10 13.2 150 1980
4382 cudm
4383 2204 Carriage of Timber
Second class teak wood plugs cum 0.13 121.29 16.01
4384 including
work and fixing inbrick
cutting cement mortar 1:3
4385 (1 cement : 3
4386 fine sand) A
4387 8.23 Rate as per item no 8.23 of each 55 25.4 1397
4388 SH : Wood work
4389 LABOUR
4390 14 Carpenter 1st class day 1.08 505.17 514.08
4391 15 Carpenter 2nd class day 0.8 403.67 299.6
4392 17 Beldar day 1.08 350.00 346.5
4393 Priming coatitem no 13.50.1 of SH :
Rate as per
4394 13.50.1 Finishing sqm 10 40.90 389.52 A
4395
4396
4397 402
4398
4400 9999 Sundries & screws etc. L.S. 53.82 2 107.64
4401 TOTAL 15491.55
4402 Add 1 % Water charges on "W-A" 13705.03 137.05
4403 TOTAL
Add GST (multiplying factor 0.1405) 15628.6 X
4404 on "X-A" 13842.08 1944.81
4405 TOTAL
Add 15 % Contractor's profit and 17573.41 Y
4406 overheads on "Y-A" 15786.89 2368.03
4407 Total 19941.45 Z
4408 Add Cess @ 1% on "Z-A" 18154.92 181.55
4409 Cost of 10 sqm. 20123
4410 Cost of 1 sqm. 2012.3
4411 Say 2012.3
4412 complet
4413 e :
4414
4415 8.26.1 12 mm thick
4416 Details of cost for 10 sqm.
4417 MATERIAL
Particle board (three layer medium
4418 density) 12mm
4419 thick = 10 sqm.
4420 Add wastage @ 10% = 1 sqm.
4421 Total = 11 sqm.
Prelaminated particle board with one
4422 7477 side decorative
and other side balancing lamination, sqm 11 540 5940
4423 flat
layerpressed 3 (medium density)
& graded
4424 Grade I, Type
conforming toIIIS : 12823 (exterior
4425 grade) 12 mm thick
4426 9977 Carriage of particle board L.S. 13.52 2 27.04
4427 9999 Sundries and screws Priming coat L.S. 26.91 2 53.82
4428 13.50.1 Rate as per item no 13.50.1 of sqm 10 40.90 389.52 A
4429 SH : Finishing
4430 LABOUR
4431 15 Carpenter 2nd class day 1.28 403.67 479.36
4432 17 Beldar
Rawl plug 50 mm (designation 10 day 1.43 350.00 458.79
4433 7048 no.) each 55 25 1375
4434 TOTAL 8723.53
4435 Add 1 % Water charges on "W-A" 8334.01 83.34
4436 TOTAL 8806.87 X
4437
4438 403
4439 Add GST (multiplying factor 0.1405)
4441 on "X-A" 8417.35 1182.64
4442 TOTAL
Add 15 % Contractor's profit and 9989.51 Y
4443 overheads on "Y-A" 9599.98 1440
4444 Total 11429.51 Z
4445 Add Cess @ 1% on "Z-A" 11039.98 110.4
4446 Cost of 10 sqm. 11539.91
4447 Cost of 1 sqm. 1153.99
4448 Say 1154
4449 8.26.2 18 mm thick
4450 Details of cost for 10 sqm.
4451 MATERIAL
Particle board (three layer medium
4452 density) 18 mm
4453 thick = 10 sqm.
4454 Add wastage @ 10% = 1 sqm.
4455 Total = 11 sqm.
Prelaminated particle board with one
4456 7478 side decorative
and other side balancing lamination, sqm 11 650 7150
4457 flat
layerpressed 3 (medium density)
& graded
4458 Grade I, Type
conforming toIIIS : 12823 (exterior
4459 grade) 18 mm thick
4460 9977 Carriage of particle board L.S. 13.52 2 27.04
4461 9999 Sundries and screws Priming coat L.S. 26.91 2 53.82
4462 13.50.1 Rate as per item no 13.50.1 of sqm 10 40.90 389.52 A
4463 SH : Finishing
4464 LABOUR
4465 15 Carpenter 2nd class day 1.28 403.67 479.36
4466 17 Beldar
Rawl plug 50 mm (designation 10 day 1.43 350.00 458.79
4467 7048 no.) each 55 25 1375
4468 TOTAL 9933.53 W
4469 Add 1 % Water charges on "W-A" 9544.01 95.44
4470 TOTAL
Add GST (multiplying factor 0.1405) 10028.97 X
4471 on "X-A" 9639.45 1354.34
4472 TOTAL
Add 15 % Contractor's profit and 11383.31 Y
4473 overheads on "Y-A" 10993.79 1649.07
4474 Total 13032.38 Z
4475 Add Cess @ 1% on "Z-A" 12642.86 126.43
4476 Cost of 10 sqm. 13158.81
4477 Cost of 1 sqm. 1315.88
4478 Say 1315.9
4479
4480
4481 404
4482
4484
4485 8.26.3 25 mm thick
4486 Details of cost for 10 sqm.
4487 MATERIAL
Particle board (three layer medium
4488 density) 25 mm
4489 thick = 10 sqm.
4490 Add wastage @ 10% = 1 sqm.
4491 Total = 11 sqm.
Prelaminated particle board with one
4492 7479 andside other
decorative
side balancing lamination, sqm 11 900 9900
4493 flat
layerpressed
& graded 3 (medium density)
4494 Grade I, Type
conforming toIIIS : 12823 (exterior
4495 grade) 25 mm thick
4496 9977 Carriage
Sundries of andparticle
screws board
etc Priming L.S. 13.52 2 27.04
4497 9999 coat
Rate as per item no 13.50.1 of SH : L.S. 26.91 2 53.82
4498 13.50.1 Finishing sqm 10 40.90 389.52 A
4499 LABOUR
4500 15 Carpenter 2nd class day 1.28 403.67 479.36
4501 17 Beldar
Rawl plug 50 mm (designation 10 day 1.43 350.00 458.79
4502 7048 no.) each 55 25 1375
4503 TOTAL 12683.53 W
4504 Add 1 % Water charges on "W-A" 12294.01 122.94
4505 TOTAL
Add GST (multiplying factor 0.1405) 12806.47 X
4506 on "X-A" 12416.95 1744.58
4507 TOTAL
Add 15 % Contractor's profit and 14551.05 Y
4508 overheads on "Y-A" 14161.53 2124.23
4509 Total 16675.28 Z
4510 Add Cess @ 1% on "Z-A" 16285.76 162.86
4511 Cost of 10 sqm. 16838.14
4512 Cost of 1 sqm. 1683.81
4513 Say 1683.8
4514 g
4515 priming
4516 complete
4517 .
4518 hollock
4519 wood
4520 Details of cost for 5 no. battens of
4521 size
4522 500cmx50mmx25mm = 31.25 cudm
4523 MATERIAL
4524 Hollock wood- 5x5.00x0.50x
4525 0.025 = 0.03125
Add wastage @ cum
5% = 0.00156 cum.
4526 Total = 0.03281
4527 cum Say 33 cudm.
4528 2505 Hollock wood in planks 10 3.3 390 1287
4529 cudm
4530 2204 Carriage of Timber cum 0.03 121.29 4
4531
4532 405
4533
4535 LABOUR
4536 14 Carpenter 1st class day 1 505.17 476
4537 17 Beldar day 0.25 350.00 80.21
4538 9999 Sundries
Painting with ready mixed priming L.S. 6.76 2 13.52
4539 coat on ground
4540 5x500x15 cmitem
Rate as per =3.75
nosqm
13.50.1 of SH : A
4541 13.50.1 Finishing
Rawl plug 50 mm (designation 10 sqm 3.75 40.90 146.06
4542 7048 no.)
Labour for drilling holes steel tape each 55 25 1375
4543 9999 sundries etc. L.S. 71.5 2 143
4544 TOTAL 3524.79 W
4545 Add 1 % Water charges on "W-A" 3378.73 33.79
4546 TOTAL
Add GST (multiplying factor 0.1405) 3558.58 X
4547 on "X-A" 3412.52 479.46
4548 TOTAL
Add 15 % Contractor's profit and 4038.04 Y
4549 overheads on "Y-A" 3891.98 583.8
4550 Total 4621.84 Z
4551 Add Cess @ 1% on "Z-A" 4475.77 44.76
4552 Cost of 31.25 cudm. 4666.59
4553 Cost of 1 cum. 149330.88
4554 Say 149330.9
4555 surface
4556 with :
4557 manufac
4558 ture
4559
4560 Details of cost for 10sqm.
4561 MATERIAL
4562 Teak ply wood = 10sqm.
4563 Add for wastage @ 20% = 2 sqm.
4564 Total = 12 sqm.
4565 759 Decorative plywood 4 mm sqm 12 320 3840
4566 9977 Carriage of plyteak
Second class woodwood plugs L.S. 5.46 2 10.92
4567 including
work cuttinginbrick
and fixing cement mortar 1:3
4568 (1 cement: 3 fine
4569 sand)
Rate as per item no 9.32 of SH : 1397.00 A
4570 8.23 Wood work each 55 25.4
4571 LABOUR
4572 14 Carpenter 1st class day 3.8 505.17 1808.8
4573 17 Beldar day 4.6 350.00 1475.82
4574 30 Mistry
20mm nails without head for fixing day 0.6 403.67 285.6
4575 9999 ply L.S. 53.82 2 107.64
4576
4577 406
4578
priming
4580 coat 13.50.1 Rate as per item no 13.50.1
4581 of SH : Finishing sqm 10 40.90 389.52 A
4582 on
TOTAL
"W- 9315.3
4583 A" 7528.78 75.29
4584 0.1405)
TOTAL 9390.59 X
4585 on "X-A" 7604.07 1068.37
4586 ds
TOTAL
on 10458.96 Y
4587 "Y-A" 8672.44 1300.87
4588 1%
Total
on 11759.83 Z
4589 Cost
"Z-A"of 9973.3 99.73
4590 10 sqm.
Cost of 11859.56
4591 1 sqm. 1185.96
4592 Say 25.4
4593 plain
4594 lining
4595 complete
4596 .
4597 for
4598 10sqm.
4599
4600 MATERIAL
Coir veneered board 4mm thick =
4601 10sqm.
4602 Add for wastage @ 20% = 2 sqm.
4603 Total = 12 sqm.
4604 7552 Coir veneered board 4mm thick sqm 12 290 3480
4605 9977 Carriage of Coir
Second class veneered
teak board
wood plugs L.S. 5.46 2 10.92
4606 including cutting brick
work and fixing in cement mortar 1:3
4607 (1 cement: 3 fine
4608 sand)
Rate as per item no 9.32 of SH : A
4609 8.23 Wood work each 55 25.4 1397
4610 LABOUR
4611 14 Carpenter 1st class day 3.8 505.17 1808.8
4612 17 Beldar day 4.6 350.00 1475.82
4613 30 Mistry
20mm nails without head for fixing day 0.6 403.67 285.6
4614 9999ply
Priming coat Painting with ready L.S. 53.82 2 107.64
4615 mixed priming coat
Rate as per item no 13.50.1 of SH :
4616 13.50.1 Finishing sqm 10 40.90 389.52 A
4617 TOTAL 8955.3
4618 Add 1 % Water charges on "W-A" 7168.78 71.69
4619 TOTAL
Add GST (multiplying factor 0.1405) 9026.99 X
4620 on "X-A" 7240.47 1017.29
4621 TOTAL 10044.27 Y
4622
4623 407
4624 ds on
4626 "Y-A" 8257.75 1238.66
4627 1%
Totalon 11282.94 Z
4628 "Z-A"
Cost of 9496.41 94.96
4629 10
Costsqm.
of 11377.9
4630 1 sqm. 1137.79
4631 Say 1185.95
4632 complet
4633 e :
4634 mm
4635 thick
4636 and 30m
4637 long
4638
= 0.2x30=
4639 6 sqm.
4640 MATERI
4641 AL
4642
wastage @
4643 10% =
4644
4645 0.6sqm.
4646
Total =
4647 6.6 sqm.
4648 Prelaminated particle board with one
4649 7478side decorative
and other side balancing lamination, sqm 6.6 650 4290
4650 flat pressed
layer & graded3 (medium density)
4651 Grade I, Type II
4652 9977 Carriage
Rawl plugof50particle board
mm (designation 10 L.S. 8.11 2 16.22
4653 7048 no.) each 102 25 2550
4654 9999 Labour for drilling holes L.S. 130 2 260
4655 LABOUR
For dressing and fixing particle
4656 board to skirting
4657 15 Carpenter 2nd class day 0.77 403.67 288.37
4658 17 Beldar day 0.86 350.00 275.91
4659 9999 Sundries (Screws,
Painting with readysand paper)
mixed priming L.S. 53.82 2 107.64
4660 coat at
Rate asback
per item no 13.50.1 of SH :
4661 13.50.1 Finishing sqm 6 40.90 233.71 A
4662 TOTAL 8021.85 W
4663 Add 1 % Water charges on "W-A" 7788.14 77.88
4664 TOTAL
Add GST (multiplying factor 0.1405) 8099.73 X
4665 on "X-A" 7866.02 1105.18
4666 TOTAL
Add 15 % Contractor's profit and 9204.91 Y
4667 overheads on "Y-A" 8971.2 1345.68
4668 Total 10550.59 Z
4669 Add Cess @ 1% on "Z-A" 10316.88 103.17
4670
4671 408
4672
4674 Cost of 6 sqm. 10653.76
4675 Cost of 1 sqm. 1775.63
4676 Say 1775.65
4677 8.30.2 25 mm thick
Details of cost for skirting 200mm
4678 wide and 30m long
4679 Area = 0.2x30= 6 sqm.
4680 Area = 0.2x30= 6 sqm.
4681 MATERIAL
Teak shade prelaminated Particle
4682 board layer medium density) = 6.0
(three
4683 sqm.+
Add wastage @ 10% = 0.6sqm. Total
4684 = 6.6 sqm.
Prelaminated particle board with one
4685 7479 side decorative
and other side balancing lamination, sqm 6.6 900 5940
4686 flat pressed
layer & graded3 (medium density)
4687 Grade
conforming toIIIS : 12823 (exterior
I, Type
4688 grade) 25 mm thick
4689 9977 Carriage
Rawl plugof50 particle board
mm (designation 10 L.S. 8.11 2 16.22
4690 7048 no.) each 102 25 2550
4691 9999 Labour for drilling holes L.S. 130 2 260
4692 LABOUR
For dressing and fixing particle
4693 board to skirting
4694 15 Carpenter 2nd class day 0.77 403.67 288.37
4695 17 Beldar day 0.86 350.00 275.91
4696 9999 Sundries (Screws,
Painting with readysand paper)
mixed priming L.S. 53.82 2 107.64
4697 coat at back
Rate as per item no 13.50.1 of SH :
4698 13.50.1 Finishing sqm 6 40.90 233.71 A
4699 TOTAL 9671.85 W
4700 Add 1 % Water charges on "W-A" 9438.14 94.38
4701 TOTAL
Add GST (multiplying factor 0.1405) 9766.23 X
4702 on "X-A" 9532.52 1339.32
4703 TOTAL
Add 15 % Contractor's profit and 11105.55 Y
4704 overheads on "Y-A" 10871.84 1630.78
4705 Total 12736.33 Z
4706 Add Cess @ 1% on "Z-A" 12502.62 125.03
4707 Cost of 6 sqm. 12861.36
4708 Cost of 1 sqm. 2143.56
4709 Say 2143.55
4710
4711
4712 409
4713
4715 complete
4716 .
4717 for 1
4718 sqm
4719
4720 MATERIAL
4721 Ceramic Glazed tiles = 1.000 sqm
4722 Add for wastage & breakage @ 2.5 %
4723 #ERROR!
4724 Total = 1.025
Ceramic sqm
Glazed Tiles Ist quality
4725 7800 minimum thickness
5mm in all colours shades and Sq.m. 1.025 350 217.3
4726 designs except
4727 burgundy, bottle green, black
4728 9977 Carriage of tiles
12 mm thick Cement mortar 1:3 (1 L.S. 6.24 2 12.48
4729 cement :
4730 3 coarse
Rate sand)
as per Item Number 3.8 of SH:
4731 3.8 Mortars
Mortar for pointing in white cement cum 0.014 4129.00 62.57
4732 9999 Cement for slurry L.S. 40.43 2 80.86
4733 over bed @ 3.3 kg per
4734 sqm
4735 367 Portland Cement tonne 0.0033 4375 16.3
4736 LABOUR
4737 23 Mason (brick layer) 1st class day 0.25 505.17 119
4738 18 Coolie
Sundries including carriage of day 0.25 350.00 80.21
4739 9988 cement etc L.S. 26.91 2 53.82
4740 TOTAL 642.54 W
4741 Add 1 % Water charges on "W" 6.4254
4742 TOTAL
Add GST (multiplying factor 0.1405) 648.97 X
4743 on "X" 91.18
4744 TOTAL
Add 15 % Contractor's profit and 740.15 Y
4745 overheads on "Y" 111.02
4746 Total 851.17 Z
4747 Add Cess @ 1% on "Z" 8.51
4748 Cost for 1 sqm 859.68
4749 Say 86.00 859.7
4750 includin 86.00
4751 g:
4752 al
4753 design.
4754
4755 410
4756
4758 backer
4759 rods etc.
4760 Galvanis
4761 ed
4762 decimal
4763 places.
4764
4765 Details of cost for 6.72 sqm
4766 Width of the unit 1.6 m
4767 Area
Total of Single
Area 6.72Unit
sqm,6.72
No sqm
of Panels 1
4768 no
Aluminium Weight per sqm = 6.50
4769 Kg/sqm
4770 Vision Height 2.2 m
4771 Sparndrel Height 2.0 m
4772 Details of cost for 6.72 sqm
4773 MATERIALS
Weather Sealant - Non Staining (600
4774 2607 ml) each 2 325 650
4775 2608 Weather Sealant - NormalAlloy
MS Brackets/Aluminium (300 ml) each 2 98 196
4776 2609 Brackets kg 10 100 1000
4777 2611 EPDM Gasket in Kg (Above 60 g / m) kg 0.7 150 105
4778 2612 Anchor
SS Bolt Fastner - M10of different
with washer each 2 10 20
4779 2613 sizes for structural 35
4780 glazing
SS Screws/ ACP Cladding
of sizes for structural each 2 70
4781 2614 glazing / ACP Claddi each 49 3 147
4782
4783 2615 Protective Tape metre 7 20 140
4784
4785 2630 Baker rod metre 5 5 25
4786
4787
4788 411
4789
4791 2616 GI flashing - 1.2 mm Thick kg 4 59 236
4792
4793 2631 4 mm thick ACP sqm 7.06 1100 7766
4794
4795 9999 Sundries L.S. 451 2 902
4796
4797 9999 Sundries (For Fabrication) L.S. 1895.3 2 3790.6
4798
4799 9999 Sundries (For Installation) L.S. 1895.3 2 3790.6
4800
4801 9999 Sundries (Transporation) L.S. 602.25 2 1204.5
4802 Sundries (Scaffolding / Loading /
4803 9999 Unloading) L.S. 473.83 2 947.66
4804
4805 9999 Sundries (Designing charges etc.) L.S. 328.15 2 656.3
4806
4807 TOTAL 19293.66 W
4808 Add 1 % Water charges on "W" 192.9366
4809 TOTAL
Add GST (multiplying factor 0.1405) 19486.60 X
4810 on "X" 2737.87
4811 TOTAL
Add 15 % Contractor's profit and 22224.47 Y
4812 overheads on "Y" 3333.67
4813 Total 25558.14 Z
4814 Add Cess @ 1% on "Z" 255.58
4815 Cost for 6.72 sqm 25813.72
4816 Cost for 1 sqm 2581.40
4817 Say 2581.40 4309.8
4818
4819
4820
4821 412
BASIC RATES
0.1 HIRE CHARGES OF PLANTS & MACHINERY

Note :- These rates are exclusive of contractor’s profit and over heads.

Code Description Unit Rate


No. 1
1 Hire charges of Coaltar Boiler 900 to 1400 litres day 800

2 Hire charges of Concrete Mixer 0.25 to 0.40 cum with day 800
Hopper
3 Hire charges of Diesel Road Roller - 8 to 10 tonne day 3000
4 Production cost of concrete by batch mix plant cum 350
5 Hire
Hire charges
charges of
of Diesel Truck
Spraying - 9 tonne
machine including electric day 2000
6 charges day 250
7 Hire charges of Coaltar Sprayer day 300
8 Hire charges of Barber green, drying, mixing and
day 7700
Asphalt Plant, with accessories, capacity 30/45 tonne
9 Pumping charges of concrete including Hire charges of cum 210
10 pump, pipingof
Hire charges work & accessories
Derrick monkey ropeetc. day 750
11 Hire charges of Pump set of capacity 4000 litres/hour day 700
12 Vibrator (Needle type 40 mm) day 370
13 Machine for rubbing of floors day 300
Hire and running charges of Tripod and Mechanical
14 Front end loader capacity 1.00 cum day 6000
Winch machine complete with power unit and
15 accessories day 1900
16 Mastic Cooker day 750
17 Hire and running charges of tipper day 1700
18 Hire and running charges of loader day 5000
19 Hand Grinder for mirror polish day 250
20 Hydraulic Excavator (3D) with driver and fuel day 7000
21 Pin vibrator day 325
22 Surface Vibrator day 400
Hire and running charges of hydraulic piling rig with
23 Hot
powerBitumen
unit etc.Mixer 0.5 cum
including i/c hand
complete cart
accessories and day 3500
24 shifting at site day 30000
25 Hire and running charges of light crane day 3000
26 Hire and running charges of bentonite pump
day 3500
27 Hire and running charges of vibrating pile driving
day 30000
hammer complete with power urnt and
28 accessories Hire and running charges of crane 20 tonne day 7000
29 capacity Carriage of concrete by transit mixer km/cum 30
30 Generator 250 KVA day 2500
31 Steam curing by using boiler /Heat er cum 500
32 Stressing Machine (jack with pump) day 11500
33 Paint applicator day 750
34 Cutting saw machine day 1350
35 Strands Roller machinery for laying strands day 3500
36 Bed master (Pulling strands) day 3000
37 Mobile crane day 7500
38 Tractor with ripper attachment day 1200
39 Tractor with trolley day 1350
40 Air compressor 250 cfm with two leads for day 1600
41 pneumatic cutters / hammers 0041 Joint cutting machine day 800
with 2-3 blades
42 C.C .batch mix plant day 10000
43 Road sweeper day 550
44 Cost for crane upto 40 tonne capacity day 8000
45 Slip form paver with sensor day 13000
46 Water tanker 5000 litre day 1200
47 Concrete joint cutting machine day 900
48 Texturing machine day 925
49 Dozer D-80-A 12 hour 1500
50 Motor Grader 3.35 metre blade hour 2450
51 Hydraulic Excavator of 1 cum bucket hour 1000
52 Front end loader 1 cum bucket capacity hour 900
53 Tipper-5 Cum tonne km 3
54 Vibratory roller 8 to 10 tonne hour 600
55 Smooth Wheeled Roller 8 to 10 tonne hour 300
56 Tandem Road Roller hour 1200
57 Water Tanker 5 to 6 KL capacity hour 150
58 Air compressor hour 200
59 Wet Mix Plant 60 TPH hour 800
60 Mechanical Broom Hydraulic hour 360
Emulsion Pressure Distributor of capacity 1750 sqm per
61 hour 800
hour
62 Hot mix Plant -120 TPH capacity hour 15000
63 Hot mix Plant 100 TPH Capacity hour 13000
64 Paver finisher Hydrostatic with sensor control 100 TPH hour 1500
65 Paver finisher Mechanical 100 TPH hour 800
66 Batching and Mixing Plant @ 75 cum per hour hour 2400
67 Cost for crane upto 80 tonne capacity day 15000
68 Concrete Paver finisher with 40 HP Motor and sensor hour 3000
69 Generator 250 KVA hour 350
70 Generator 100 KVA/125 KVA hour 250
71 Truck 5.5 cum/10 tonnes tonne km 3
72 Cost for crane having capacity 50MT day 8500
73 Road sweeper (Mechamical Broom) @ 1250 sqm per hour hour
hour day
350
74 Drum Type HMP of 60-90 TPH capacity @ 75 12000
75 tonne perrunning
Hire and hour actual output
charges of drill machine up to 400 mm 7500
76 dia
Pile(including cost ofequipment
Integrity testing mobile oil, diesel consumption in day 3000
ordinary soil and operator)
77 Excavation of Diaphragm wall by Mechanical Grab
sqm day 1300
78 Hire charges of TATA407 or equivalent for local
shifting. day
1200
80 Hire charges of diesel truck - 9 tonne (witout POL) day 1500
81 Using cost of Ultra Violet Radiation tube Hour 189
Compressor, gun, rubber pipes & other accessories- hire
82 charge of plant & machinery i/c necessary fuel day 4000
83 Hire Charges of Suction Jeting machine 2200 PSI day 36000
84 machine i/c POL
Hire charges and machine
of Drill operator upto 30 mm dia day 160
85 Hire charges of sand blasting equipment day 160
86 Hire charges of compressor day 420
87 Welding charges
Hire charges of shear
of plant key to existing
and Machinery can inject 350 each
that reinforcement 5
88 kg/day day 200
89 Hire Charges of Suction Jeting machine 1500 PSI day 8000
machine i/c POL and operator
SUB HEAD : 9.0

WOOD AND P. V. C. WORK

Code Description Unit Quantity Rate Amount

9.1 Providing wood work in frames of doors,


windows, clerestory windows and other
frames, wrought framed and fixed in
position with hold fast lugs or with dash
fasteners of required dia & length ( hold
fast lugs or dash fastener shall be paid for
separately).

9.1.1 Second class teak wood

Details of cost for Chowkhat of a door


206.75x117.5cm
MATERIAL
Superior class teakwood such as Dandeli
Balarshah or Malabar
2x206.75x9.5x7.0cm =0.028cum+
1x117.5x9.5x7.0cm = 0.008cum.
= 0.036cum.+
Add for wastage @ 5% = 0.002cum.
Grand Total = 0.038cum = 38 cudm
1189 Second class teak wood in scantling 10 3.8 776 2948.80
cudm
2204 Carriage of Timber cum 0.038 121.29 4.61
LABOUR
41 Carpenter (average) day 0.72 403.67 290.64
17 Beldar day 0.07 350.00 24.50
TOTAL 3268.55 W
Add 1 % Water charges on "W" 32.6855
TOTAL 3301.24 X
Add GST (multiplying factor 0.1405) on "X" 463.82
TOTAL 3765.06 Y
Add 15 % Contractor's profit and overheads on "Y" 564.76
Total 4329.82 Z
Add Cess @ 1% on "Z" 43.30
Cost of 36 cudm. 4373.12
Cost per cum. 121475.43
Say 121475.40

9.1.2 Sal wood


Details of cost for Chowkhat of a door
206.75x117.5cm.
MATERIAL Salwood
2x206.75x9.5x7.0cm =0.028cum+
1x117.5x9.5x7.0cm = 0.008cum. = 0.036cum.+
Add for wastage @ 5% = 0.002cum. Grand Total =
0.038cum = 38cudm
1199 Sal wood in scantling 10 3.8 600 2280.00
cudm
2204 Carriage of Timber cum 0.038 121.29 4.61
LABOUR
41 Carpenter (average) day 0.72 403.67 290.64
17 Beldar day 0.07 350.00 24.50
TOTAL 2599.75 W
Add 1 % Water charges on "W" 25.9975
TOTAL 2625.75 X
Add GST (multiplying factor 0.1405) on "X" 368.92
TOTAL 2994.67 Y
Add 15 % Contractor's profit and overheads on "Y" 449.20
Total 3443.87 Z
Add Cess @ 1% on "Z" 34.44
Cost of 36 cudm. 3478.31
Cost per cum. 96619.65
Say 96619.70

9.1.3 Kiln seasoned and chemically treated


hollockofwood
Details cost for Chowkhat of a door
206.75x117.5cm.
MATERIAL Hollock wood

2x206.75x9.5x7.0cm =0.028cum+
1x117.5x9.5x7.0cm = 0.008cum.
= 0.036cum.+
Add for wastage @ 5% = 0.002cum.
Grand Total = 0.038cum = 38cudm
2466 Hollock wood in scantling 10 3.8 350 1330.00
cudm
2204 Carriage of Timber cum 0.038 121.29 4.61
2504 Kiln seasoning of timber cum 0.038 750 28.50
9999 Chemical treatment L.S. 8.97 2 17.94
LABOUR
41 Carpenter (average) day 0.72 403.67 290.64
17 Beldar day 0.07 350.00 24.50
TOTAL 366.19 W
Add 1 % Water charges on "W" 3.6619
TOTAL 369.85 X
Add GST (multiplying factor 0.1405) on "X" 51.96
TOTAL 421.81 Y
Add 15 % Contractor's profit and overheads on "Y" 63.27
Total 485.08 Z
Add Cess @ 1% on "Z" 4.85
Cost of 36 cudm. 489.93
Cost per cum. 48.99
Say 49.00

9.2 Providing laminated veneer lumber


conforming to IS:14616 and TAD -15: 2001
be paid for separately).
(Part B) in factory made frames of doors,
Details of cost for Chowkhat of a door
windows, clerestory windows and other
206.75x117.5cm.
MATERIAL
Laminated veneer lumber including wastage @ 5%
2x206.75x9.5x7.0cm =0.028cum+
1x117.5x9.5x7.0cm = 0.008cum.
= 0.036cum.+
Add for wastage @ 5% = 0.002cum.
Grand Total = 0.038cum = 38cudm
7157 Laminated veneer lumber confirming to TADS 10 3.8 700 2660.00
15:1995 manufactured in factory in frames of cudm
2204 doors, windows
Carriage of Timber cum 0.038 121.29 4.61
LABOUR
14 Carpenter 1st class day 0.2 505.17 101.03
15 Carpenter 2nd class day 0.2 403.67 80.73
17 Beldar day 0.2 350.00 70.00
TOTAL 2916.37 W
Add 1 % Water charges on "W" 29.1637
TOTAL 2945.53 X
Add GST (multiplying factor 0.1405) on "X" 413.85
TOTAL 3359.38 Y
Add 15 % Contractor's profit and overheads on "Y" 503.91
Total 3863.29 Z
Add Cess @ 1% on "Z" 38.63
Cost of 36 cudm. 3901.92
Cost per cum. 108386.77
Say 108386.80
9.3 Providing wood work in frames
of false
9.3.1 ceiling, partitions etc. sawn and
Sal wood
fixed in position :
Details of cost for ceiling for a room 3x3m
MATERIAL
Salwood
= 6x3.30x(50/1000)x(125/1000)=
0.1238 cum. +
Cross battens 60mm centre to center 38x50mm.
6x3x(38/1000)x50/1000)=0.0342 cum.
= 0.1580 cum.+
Add for wastage @ 5% = 0.0079 cum.
= 0.1659 cum. say 166 cudm.
1199 Sal wood in scantling 10 16.6 600 9960.00
cudm
2204 Carriage of Timber cum 0.166 121.29 20.13
LABOUR
15 Carpenter 2nd class day 1 403.67 403.67
17 Beldar day 1 350.00 350.00
9999 Sundries screws etc. L.S. 53.82 2 107.64
TOTAL 10841.44 W
Add 1 % Water charges on "W" 108.4144
TOTAL 10949.85 X
Add GST (multiplying factor 0.1405) on "X" 1538.45
TOTAL 12488.30 Y
Add 15 % Contractor's profit and overheads on "Y" 1873.25
Total 14361.55 Z
Add Cess @ 1% on "Z" 143.62
Cost of 158 cudm. 14505.17
Cost per cum. 91804.9
Say 91804.90

9.3.2 Kiln seasoned and chemically treated


hollockofwood
Details cost for ceiling for a room 3x3m
MATERIAL
Hollock wood
= 6x3.30x(50/1000)x(125/1000)=
0.1238 cum. +
Cross battens 60mm centre to center 38x50mm.
6x3x(38/1000)x50/1000)=0.0342 cum.
= 0.1580 cum.+
Add for wastage @ 5% = 0.0079 cum.
= 0.1659 cum. say 166 cudm.
2466 Hollock wood in scantling 10 16.6 350 5810.00
2204 cudm
Carriage of Timber cum 0.166 121.29 20.13
2504 Kiln seasoning of timber cum 0.166 750 124.50
9999 Chemical treatment L.S. 18.2 2 36.40
LABOUR
15 Carpenter 2nd class day 1 403.67 403.67
17 Beldar day 1 350.00 350.00
9999 Sundries screws etc. L.S. 53.82 2 107.64
TOTAL 6852.34 W
Add 1 % Water charges on "W" 68.5234
TOTAL 6920.86 X
Add GST (multiplying factor 0.1405) on "X" 972.38
TOTAL 7893.24 Y
Add 15 % Contractor's profit and overheads on "Y" 1183.99
Total 9077.23 Z
Add Cess @ 1% on "Z" 90.77
Cost of 158 cudm. 9168.00
Cost per cum. 58025.34
Say 58025.30

9.4 Extra for additional labour for circular


9.4.1 works,
Secondsuch asteak
class in frames
wood of fan light
Details of cost for Chowkhat of a door
206.75x117.5cm
Extra Materials and labour for wastage @
10% on quantity of item no 9.1.1
MATERIAL
1189 Second class teak wood in scantling 10 0.38 776 294.88
2204 cudm 0.00
Carriage of Timber cum 0.0038 121.29 0.46
LABOUR 0.00
41 Carpenter (average) day 0.072 403.67 29.06
17 Beldar day 0.007 350.00 2.45
TOTAL 326.85 W
Add 1 % Water charges on "W" 3.2685
TOTAL 330.12 X
Add GST (multiplying factor 0.1405) on "X" 46.38
TOTAL 376.50 Y
Add 15 % Contractor's profit and overheads on "Y" 56.47
Total 432.97 Z
Add Cess @ 1% on "Z" 4.33
Cost of 36 cudm. 437.30
Cost per cum. 12147.18
12147.20

9.4.2 Sal wood

Details of cost for Chowkhat of a door


206.75x117.5cm
Extra Materials and labour for wastage @
10% on quantity of item no 9.1.2
MATERIAL
1199 Sal wood in scantling 10 0.38 600 228.00
2204 cudm 0.00
Carriage of Timber cum 0.0038 121.29 0.46
LABOUR
41 Carpenter (average) day 0.072 403.67 29.06
17 Beldar day 0.007 350.00 2.45
TOTAL 259.97 W
Add 1 % Water charges on "W" 2.5997
TOTAL 262.57 X
Add GST (multiplying factor 0.1405) on "X" 36.89
TOTAL 299.46 Y
Add 15 % Contractor's profit and overheads on "Y" 44.92
Total 344.38 Z
Add Cess @ 1% on "Z" 3.44
Cost of 36 cudm. 347.82
Cost per cum. 9661.66
Say 9661.70

9.4.3 Kiln seasoned and chemically treated


hollockofwood
Details cost for Chowkhat of a door
206.75x117.5cm.
Extra Materials and labour for wastage @
10% on quantity of item no 9.1.3
MATERIAL
2466 Hollock wood in scantling 10 0.38 350 133.00
2204 cudm
Carriage of Timber cum 0.0038 121.29 0.46
2504 Kiln seasoning of timber cum 0.0038 750 2.85
9999 Chemical treatment L.S. 0.9 2 1.80
LABOUR
41 Carpenter (average) day 0.072 403.67 29.06
17 Beldar day 0.007 350.00 2.45
TOTAL 169.62 W
Add 1 % Water charges on "W" 1.6962
TOTAL 171.32 X
Add GST (multiplying factor 0.1405) on "X" 24.07
TOTAL 195.39 Y
Add 15 % Contractor's profit and overheads on "Y" 29.31
Total 224.70 Z
Add Cess @ 1% on "Z" 2.25
Cost of 36 cudm. 226.95
Cost per cum. 6304.06
Say 6304.10

9.5 Providing and fixing panelled or panelled


and glazed shutters for doors, windows
and clerestory windows, including ISI
9.5.1
marked M.S.Second class
pressed buttteak wood
hinges bright

9.5.1.1 35 mm thick shutters


Details of cost for shutters of a Door
(1/3rd glazed and 2/3rd panelled) 200x
108cm = 2.16 sqm)
MATERIAL
Teak wood
Styles 4x200x10.0x3.5cm = 0.028cum+ Rails
Top rails 1x110.5x10.0x3.5cm = 0.004cum.+
Bottom rails 1x110.5x20x3.5cm = 0.008cum+
Lock rails 1x110.5x15x3.5cm = 0.006cum+
Beading 2x186.1x1.9x1.2cm = 0.001cum.
Total = 0.047 cum+
Add for wastage @ 10% = 0.005cum
Grand Total = 0.051 cum = 51 cudm
1190 Second class teak wood in planks 10 cudm 5.1 791 4034.10
2204 Carriage of Timber cum 0.051 121.29 6.19
LABOUR
41 Carpenter (average) day 1.83 403.67 738.72
17 Beldar day 0.76 350.00 266.00
9999 Sundries L.S. 35.88 2 71.76
TOTAL 5116.77 W
Add 1 % Water charges on "W" 51.1677
TOTAL 5167.94 X
Add GST (multiplying factor 0.1405) on "X" 726.10
TOTAL 5894.04 Y
Add 15 % Contractor's profit and overheads on "Y" 884.11
Total 6778.15 Z
Add Cess @ 1% on "Z" 67.78
Cost of 2.16 sqm. 6845.93
3169.41
3169.40

9.5.1.2 30 mm thick shutters


Details of cost for shutters of a Door
(1/3rd glazed and 2/3rd panelled) 200x
108cm = 2.16 sqm)
MATERIAL
Teak wood
Styles : 4x200x10.0x3.0cm = 0.024 cum+
Top rails :1x110.5x9.5x3.0cm = 0.003cum+
Bottom rails : 1x110.5x19.7x3.0cm =
0.007cum+
Lock rails : 1x110.5x15.0x3.0cm =
0.005cum+
Beading : 2x186.1x1.9x1.2cm = 0.001 cum.
Total = 0.040 cum. +
Add for wastage @ 10% = 0.004 cum.
Grand Total = 0.044 cum = 44 cudm
1190 Second class teak wood in planks 10 4.4 791 3480.40
cudm
2204 Carriage of Timber cum 0.044 121.29 5.34
LABOUR
41 Carpenter (average) day 1.83 403.67 738.72
17 Beldar day 0.76 350.00 266.00
9999 Sundries L.S. 35.88 2 71.76
TOTAL 4562.22 W
Add 1 % Water charges on "W" 45.6222
TOTAL 4607.84 X
Add GST (multiplying factor 0.1405) on "X" 647.40
TOTAL 5255.24 Y
Add 15 % Contractor's profit and overheads on "Y" 788.29
Total 6043.53 Z
Add Cess @ 1% on "Z" 60.44
Cost of 2.16 sqm. 6103.97
Cost of 1 sqm. 2825.91
Say 2825.90
9.5.2 Kiln seasoned and chemically treated
9.5.2.1 hollock woodshutters
35 mm thick
Details of cost for shutters of a Door (1/3rd glazed
and 2/3rd panelled) 200x 108cm = 2.16 sqm)
MATERIAL
Hollock wood
Styles 4x200x10.0x3.5cm = 0.028cum+ Rails
Top rails 1x110.5x10.0x3.5cm = 0.004cum.+
Bottom rails 1x110.5x20x3.5cm = 0.008cum+
Lock rails 1x110.5x15x3.5cm = 0.006cum+
Beading 2x186.1x1.9x1.2cm = 0.001cum.
Total = 0.047 cum+
Add for wastage @ 10% = 0.005cum
Grand Total = 0.051 cum = 51 cudm
2505 Hollock wood in planks 10 5.1 390 1989.00
2204 cudm 0.00
Carriage of Timber cum 0.051 121.29 6.19
2504 Kiln seasoning of timber cum 0.051 750 38.25
9999 Chemical treatment L.S. 9.1 2 18.20
LABOUR
41 Carpenter (average) day 1.83 403.67 738.72
17 Beldar day 0.76 350.00 266.00
9999 Sundries L.S. 35.88 2 71.76
TOTAL 3128.12 W
Add 1 % Water charges on "W" 31.2812
TOTAL 3159.40 X
Add GST (multiplying factor 0.1405) on "X" 443.90
TOTAL 3603.30 Y
Add 15 % Contractor's profit and overheads on "Y" 540.50
Total 4143.80 Z
Add Cess @ 1% on "Z" 41.44
Cost of 2.16 sqm. 4185.24
Cost of 1 sqm. 1937.61
Say 1937.60

9.5.2.2 30 mm thick shutters


Details of cost for shutters of a door
(1/3rd glazed and 2/3rd panelled) 200x108cm =
2.16sqm.
MATERIAL Hollock wood

Styles 4x200x10.0x3.0cm = 0.024cum+ Rails


Top rails 1x110.5x9.50x3.0cm = 0.003cum.+

Lock rails 1x110.5x15x3.0cm =


0.005cum+
Bottom rails 1x110.5x19.7x3.0cm =
0.007cum+
Beading 2x186.1x1.9x1.2cm = 0.001cum
Total = 0.040 cum.+
Add for wastage @ 10% = 0.004cum
Grand Total = 0.044 cum or = 44 cudm
2505 Hollock wood in planks 10 4.4 390 1716.00
cudm
2204 Carriage of Timber cum 0.044 121.29 5.34
2504 Kiln seasoning of timber cum 0.044 750 33.00
9999 Chemical treatment L.S. 9.1 2 18.20
LABOUR
41 Carpenter (average) day 1.83 403.67 738.72
17 Beldar day 0.76 350.00 266.00
9999 Sundries L.S. 35.88 2 71.76
TOTAL 2849.02 W
Add 1 % Water charges on "W" 28.4902
TOTAL 2877.51 X
Add GST (multiplying factor 0.1405) on "X" 404.29
TOTAL 3281.80 Y
Add 15 % Contractor's profit and overheads on "Y" 492.27
Total 3774.07 Z
Add Cess @ 1% on "Z" 37.74
Cost of 2.16 sqm. 3811.81
Cost of 1 sqm. 1764.73
Say 1764.70

9.5.3 Kiln seasoned selected planks of


sheesham wood
9.5.3.1 35 mm thick shutters

Details of cost for shutters of a Door


(1/3rd glazed and 2/3rd panelled)
200x108cm = 2.16 sqm)
MATERIAL
Sheesham wood
Styles 4x200x10.0x3.5cm = 0.028cum+ Rails
Top rails 1x110.5x10.0x3.5cm = 0.004cum.+
Lock rails 1x110.5x15x3.5cm = 0.006cum+
Beading 2x186.1x1.9x1.2cm = 0.001cum.
Total = 0.047 cum+
Add for wastage @ 10% = 0.005cum
Grand Total = 0.051 cum or = 51 cudm
1200 Kiln seasoned selected sheesum wood planks 10 5.1 650 3315.00
cudm
2204 Carriage of Timber cum 0.051 121.29 6.19
2504 Kiln seasoning of timber cum 0.051 750 38.25
LABOUR
41 Carpenter (average) day 1.83 403.67 738.72
17 Beldar day 0.76 350.00 266.00
9999 Sundries L.S. 35.88 2 71.76
TOTAL 4435.92 W
Add 1 % Water charges on "W" 44.3592
TOTAL 4480.28 X
Add GST (multiplying factor 0.1405) on "X" 629.48
TOTAL 5109.76 Y
Add 15 % Contractor's profit and overheads on "Y" 766.46
Total 5876.22 Z
Add Cess @ 1% on "Z" 58.76
Cost of 2.16 sqm. 5934.98
Cost of 1 sqm. 2747.68
Say 2747.70

9.5.3.2 30 mm thick shutters


Details of cost for shutters of a door
(1/3rd glazed and 2/3rd panelled) 200x108cm =
2.16sqm.
MATERIAL
Sheesham wood
Styles 4x200x10.0x3.0cm = 0.028cum+ Rails
Top rails 1x110.5x9.50x3.0cm =
0.003cum.+
Lock rails 1x110.5x15.0x3.0cm =
0.005cum+
Bottom rails 1x110.5xl9.7x3.0cm =
0.007cum+
Beading 2x186.1xl.9xl.2cm = 0.001cum
Total = 0.040 cum.+
Add for wastage @ 10% = 0.004cum
Grand Total = 0.044 cum or = 44 cudm"
1200 Kiln seasoned selected sheesum wood planks 10 4.4 650 2860.00
2204 cudm
Carriage of Timber cum 0.044 121.29 5.34
2504 Kiln seasoning of timber cum 0.044 750 33.00
LABOUR
41 Carpenter (average) day 1.83 403.67 738.72
17 Beldar day 0.76 350.00 266.00
9999 Sundries L.S. 35.88 2 71.76
TOTAL 3974.82 W
Add 1 % Water charges on "W" 39.7482
TOTAL 4014.57 X
Add GST (multiplying factor 0.1405) on "X" 564.05
TOTAL 4578.62 Y
Add 15 % Contractor's profit and overheads on "Y" 686.79
Total 5265.41 Z
Add Cess @ 1% on "Z" 52.65
Cost of 2.16 sqm. 5318.06
Cost of 1 sqm. 2462.06
Say 2462.10

9.6 Providing and fixing 35 mm thick factory


9.6.1 made
12 mmlaminated
thick plain veneer
gradelumber door
-1, medium
shutter
density conforming
flattype
pressed to IS : 14616
threeresin and
layeradhesive
particle
with
TADS BWP
15:2001 synthetic
(Part B), including ISI as
board FPT
per IS of
Details : 848 - :I or
cost of
graded wood particle
one shutter 220x108cm =
board FPT- I, IS : 3087 marked, bonded
7137 2.38sqm. MATERIAL 0.00
Factory made 35 mm thick shutters with laminated sqm 2.38 1620 3855.6
veneer lumber styles rails as per TADS IS:1995
and panels of 12 mm thick plain type-I, medium
density flat pressed three layer, graded particle
board (FPT-I) as per IS:3087-1985 bonded with
BWP type synthetic resin adhesive, as per IS:848
9977 Carriage of shutters Fittings : L.S. 29.64 2 59.28
LABOUR
41 Carpenter (average) day 0.52 403.67 209.91
17 Beldar day 0.6 350.00 210.00
9999 Sundries L.S. 35.88 2 71.76
TOTAL 4406.55 W
Add 1 % Water charges on "W" 44.0655
TOTAL 4450.62 X
Add GST (multiplying factor 0.1405) on "X" 625.31
TOTAL 5075.93 Y
Add 15 % Contractor's profit and overheads on "Y" 761.39
Total 5837.32 Z
Add Cess @ 1% on "Z" 58.37
Cost of 2.38 sqm. 5895.69
Cost of 1 sqm. 2477.18
2477.20
9.6.2 12 mm thick pre-laminated
particle board
IS : 12823, Grade (decorative
1, Typelamination
- II markedon :
both sides) grade -1, medium density flat
Details of cost of one shutter 220x108cm = 2.38sqm.
pressed, three layer particle board FPT- I
MATERIAL
7139 Factory made 35 mm thick shutters with laminated sqm 2.38 1800 4284.00
veneer lumber styles rails as per TADS IS:1995
and panels of 12 mm thick both sides
prelaminated type-I, medium density flat pressed
three layer, graded particle board (FPT-I) as per
IS:3087-1985 bonded with BWP type synthetic
resin adhesive, as per IS:848-1974
9977 Carriage of shutters Fittings : L.S. 29.64 2 59.28
LABOUR
41 Carpenter (average) day 0.52 403.67 209.91
17 Beldar day 0.6 350.00 210.00
9999 Sundries L.S. 35.88 2 71.76
TOTAL 4834.95 W
Add 1 % Water charges on "W" 48.3495
TOTAL 4883.30 X
Add GST (multiplying factor 0.1405) on "X" 686.10
TOTAL 5569.40 Y
Add 15 % Contractor's profit and overheads on "Y" 835.41
Total 6404.81 Z
Add Cess @ 1% on "Z" 64.05
Cost of 2.38 sqm. 6468.86
Cost of 1 sqm. 2718.01
Say 2718.00

9.6.3 12 mm thick one side Pre-


laminated
Details particle
of cost board220x108cm
of one shutter (decorative
= 2.38sqm.
lamination
MATERIAL
on one side and other sides
balancing lamination) grade -1, medium
7143 Factory made 35 mm thick shutters with laminated sqm 2.38 1910 4545.80
veneer lumber styles rails as per TADS IS:1995
and panels of 12 mm thick one side prelaminated
type-I, and other side balancing lamination,
medium density flat pressed three layer, graded
particle board (FPT-I) as per IS:3087-1985 bonded
with BWP type synthetic resin adhesive, as per
IS:848-1974
9977 Carriage of shutters Fittings : L.S. 29.64 2 59.28
LABOUR
41 Carpenter (average) day 0.52 403.67 209.91
17 Beldar day 0.6 350.00 210.00
9999 Sundries L.S. 35.88 2 71.76
TOTAL 5096.75 W
Add 1 % Water charges on "W" 50.9675
TOTAL 5147.72 X
Add GST (multiplying factor 0.1405) on "X" 723.25
TOTAL 5870.97 Y
Add 15 % Contractor's profit and overheads on "Y" 880.65
Total 6751.62 Z
Add Cess @ 1% on "Z" 67.52
Cost of 2.38 sqm. 6819.14
Cost of 1 sqm. 2865.18
Say 2865.20

9.7 Providing and fixing panelling or panelling


9.7.1 and glazing
Second classin teak
panelled
woodor panelled and
glazed shutters for doors, windows and
Details of cost for shutters of a door with 2/3rd
clerestory windows (Area of opening for
panelling 200x108cm = 2.16sqm.
Panel area = 4x45.1x36.55cm = 0.66 sqm
MATERIAL
Panels
4x47.2x38.65x1.6cm = 0.0117cum+ Add for
wastage @ 10% = 0.0012cum.
= 0.0129 cum.
1190 Second class teak wood in planks 10 1.29 791 1020.39
2204 cudm
Carriage of Timber cum 0.0129 121.29 1.56
LABOUR
14 Carpenter 1st class day 0.57 505.17 287.95
9999 Sundries L.S. 4.42 2 8.84
TOTAL 1318.74 W
Add 1 % Water charges on "W" 13.1874
TOTAL 1331.93 X
Add GST (multiplying factor 0.1405) on "X" 187.14
TOTAL 1519.07 Y
Add 15 % Contractor's profit and overheads on "Y" 227.86
Total 1746.93 Z
Add Cess @ 1% on "Z" 17.47
Cost of 0.66 sqm. 1764.40
Cost of 1 sqm. 2673.33
Say 2673.30

9.7.2 Kiln seasoned and chemically treated


hollock wood
Details of cost for shutters of a door 200x108cm =
2.16 sqm.
Panel area 4x45.1x36.55cm=0.66sqm.
MATERIAL
Hollock wood panels 4x45.1x36.55cm = 0.0117
cum+ Add for wastage @ 10% = 0.0012cum. =
2505 0.0129 cum = 12.90 cudm
Hollock wood in planks 10 1.29 390 503.1
cudm
2204 Carriage of Timber cum 0.0129 121.29 1.56
2504 Kiln seasoning of timber cum 0.0129 750 9.68
9999 Chemical treatment Labour & sundries L.S. 8.97 2 17.94
14 Carpenter 1st class day 0.57 505.17 287.95
9999 Sundries L.S. 4.42 2 8.84
TOTAL 829.07 W
Add 1 % Water charges on "W" 8.2907
TOTAL 837.36 X
Add GST (multiplying factor 0.1405) on "X" 117.65
TOTAL 955.01 Y
Add 15 % Contractor's profit and overheads on "Y" 143.25
Total 1098.26 Z
Add Cess @ 1% on "Z" 10.98
Cost of 0.66 sqm. 1109.24
Cost of 1 sqm. 1680.67
Say 1680.70

9.7.3 Ply wood 5 ply, 9 mm thick


9.7.3.1 Decorative plywood both side
decorative
Details of costveneer (Type
for shutters of a-door
I) conforming
with 2/3rd to
IS 1328
panelling BWR
200x108cmtype= 2.16sqm.
Panel area = 4x45.1x36.55cm = 0.66sqm.
MATERIAL
Plywood (9mm thick)
4x47.2x38.65cm = 0.73sqm+ Add for wastage @
10% = 0.07sqm.
Total = 0.80 sqm.
2480 Ply wood 5 ply with teak ply on both faces 9 mm sqm 0.8 850 680.00
9977 thick 0.00
Carriage of Plywood L.S. 1.82 2 3.64
LABOUR
14 Carpenter 1st class day 0.57 505.17 287.95
9999 Sundries L.S. 4.42 2 8.84
TOTAL 980.43 W
Add 1 % Water charges on "W" 9.8043
TOTAL 990.23 X
Add GST (multiplying factor 0.1405) on "X" 139.13
TOTAL 1129.36 Y
Add 15 % Contractor's profit and overheads on "Y" 169.40
Total 1298.76 Z
Add Cess @ 1% on "Z" 12.99
Cost of 0.66 sqm. 1311.75
Cost of 1 sqm. 1987.51
Say 1987.50

9.7.3.2 Decorative plywood one side decorative


veneerofand
Details cost commercial
for shutters of aveneer on2/3rd
door with other
face (Type 1) conforming
panelling. 200x108cm = 2.16sqm.
to IS 1328 BWR
Type
Panel area = 4x45.1x36.55cm = 0.66sqm.
MATERIAL
Plywood (9mm thick)
4x47.2x38.65cm = 0.73sqm+ Add for wastage @
10% = 0.07sqm.
Total = 0.80 sqm.
2481 Ply wood 5 ply with teak ply on one face and sqm 0.8 870 696.00
9977 commercial ply on another face 9 mm thick 0.00
Carriage of Plywood L.S. 1.82 2 3.64
LABOUR
14 Carpenter 1st class day 0.57 505.17 287.95
9999 Sundries L.S. 4.42 2 8.84
TOTAL 996.43 W
Add 1 % Water charges on "W" 9.9643
TOTAL 1006.39 X
Add GST (multiplying factor 0.1405) on "X" 141.40
TOTAL 1147.79 Y
Add 15 % Contractor's profit and overheads on "Y" 172.17
Total 1319.96 Z
Add Cess @ 1% on "Z" 13.20
Cost of 0.66 sqm. 1333.16
Cost of 1 sqm. 2019.95
Say 2020.00

9.7.4 Ply wood 7 ply, 9 mm thick


9.7.4.1 Decorative plywood one side decorative
veneer
Details ofand
cost commercial
for shutters of aveneer on2/3rd
door with other
face (Type 1) conforming
panelling 200x108cm = 2.16sqm.
to IS 1328 BWR
Type
Panel area = 4x45.1x36.55cm = 0.66sqm.
MATERIAL
Plywood (9mm thick)
4x47.2x38.65cm = 0.73sqm+ Add for wastage @
10% = 0.07sqm.
Total = 0.80 sqm.
2483 Ply wood 7 ply with teak ply on one face and sqm 0.8 950 760.00
9977 commercial ply on another face 9 mm thick 0.00
Carriage of Plywood L.S. 1.82 2 3.64
LABOUR
14 Carpenter 1st class day 0.57 505.17 287.95
9999 Sundries L.S. 4.42 2 8.84
TOTAL 1060.43 W
Add 1 % Water charges on "W" 10.6043
TOTAL 1071.03 X
Add GST (multiplying factor 0.1405) on "X" 150.48
TOTAL 1221.51 Y
Add 15 % Contractor's profit and overheads on "Y" 183.23
Total 1404.74 Z
Add Cess @ 1% on "Z" 14.05
Cost of 0.66 sqm. 1418.79
Cost of 1 sqm. 2149.69
Say 2149.70

9.7.5 Particle Board 12 mm thick

9.7.5.1 Plain particle board flat pressed, 3 layer or


gradedofwood
Details particle
cost for board
shutters medium
of a door with density
2/3rd
Grade I, IS : 3087 marked
panelling 200x108cm = 2.16sqm.
Panel area = 4x45.1x36.55cm = 0.66sqm.
MATERIAL Particle Board

4x47.2x38.65cm = 0.73sqm+ Add for wastage @


10% = 0.07sqm.
Total = 0.80 sqm.
341 Flat pressed 3 layer particle board (medium sqm 0.8 288 230.40
9977 density) Grade I :12 mm thick 0.00
Carriage of Plywood L.S. 1.82 2 3.64
LABOUR
14 Carpenter 1st class day 0.57 505.17 287.95
9999 Sundries L.S. 4.42 2 8.84
TOTAL 530.83 W
Add 1 % Water charges on "W" 5.3083
TOTAL 536.14 X
Add GST (multiplying factor 0.1405) on "X" 75.33
TOTAL 611.47 Y
Add 15 % Contractor's profit and overheads on "Y" 91.72
Total 703.19 Z
Add Cess @ 1% on "Z" 7.03
Cost of 0.66 sqm. 710.22
Cost of 1 sqm. 1076.09
Say 1076.10

9.7.5.2 Veneered flat pressed three layer or


graded
Details ofwood
cost forparticle
shutters board with
of a door with 2/3rd
commercial veneering on
panelling 200x108cm = 2.16sqm.
both sides
conforming to IS:3097, grade I
Panel area = 4x45.1x36.55cm = 0.66sqm.
MATERIAL
Particle Board
4x47.2x38.65cm = 0.73sqm+
Add for wastage @ 10% = 0.07sqm. Total = 0.80
7468 sqm 0.00
Veneered particle board with commercial sqm 0.8 500 400
9977 veneering on both sides 12 mm thick 0.00
Carriage of Plywood L.S. 1.82 2 3.64
LABOUR
14 Carpenter 1st class day 0.57 505.17 287.95
9999 Sundries L.S. 4.42 2 8.84
TOTAL 700.43 W
Add 1 % Water charges on "W" 7.0043
TOTAL 707.43 X
Add GST (multiplying factor 0.1405) on "X" 99.39
TOTAL 806.82 Y
Add 15 % Contractor's profit and overheads on "Y" 121.02
Total 927.84 Z
Add Cess @ 1% on "Z" 9.28
Cost of 0.66 sqm. 937.12
Cost of 1 sqm. 1419.89
Say 1419.90

9.7.5.3 Pre-laminated particle board with


decorative laminationon
balancing lamination onother
one side
side,and
Grade
I, Type II IS: 12823 marked
Details of cost for shutters of a door with 2/3rd
panelling 200x108cm = 2.16sqm.
Panel area = 4x45.1x36.55cm = 0.66sqm.
MATERIAL
Particle Board
4x47.2x38.65cm = 0.73sqm+
Add for wastage @ 10% = 0.07sqm. Total = 0.80
sqm 0.00
7477 Prelaminated particle board with one side sqm 0.8 540 432.00
decorative and other side balancing lamination, flat
pressed 3 layer & graded (medium density) Grade
I, Type II conforming to IS : 12823 (exterior grade)
9977 12 mm thick 0.00
Carriage of Plywood L.S. 1.82 2 3.64
LABOUR
14 Carpenter 1st class day 0.57 505.17 287.95
9999 Sundries L.S. 4.42 2 8.84
TOTAL 732.43 W
Add 1 % Water charges on "W" 7.3243
TOTAL 739.75 X
Add GST (multiplying factor 0.1405) on "X" 103.94
TOTAL 843.69 Y
Add 15 % Contractor's profit and overheads on "Y" 126.55
Total 970.24 Z
Add Cess @ 1% on "Z" 9.70
Cost of 0.66 sqm. 979.94
Cost of 1 sqm. 1484.76
Say 1484.80

9.7.5.4 Pre-laminated particle board with


decorative lamination on both sides, Grade
I,
Type II, IS:12823 marked
Details of cost for shutters of a door with 2/3rd
panelling 200x108cm = 2.16sqm.
Panel area = 4x45.1x36.55cm = 0.66sqm.
MATERIAL Particle Board

4x47.2x38.65cm = 0.73sqm+
Add for wastage @ 10% = 0.07sqm. Total = 0.80
sqm
7480 Prelaminated particle board with both sides sqm 0.8 575 460.00
decorative lamination, flat pressed 3 layer &
graded (medium density) Grade I, Type II
conforming to IS : 12823 (exterior grade) 12 mm
9977 thick 0.00
Carriage of Plywood L.S. 1.82 2 3.64
LABOUR
14 Carpenter 1st class day 0.57 505.17 287.95
9999 Sundries L.S. 4.42 2 8.84
TOTAL 760.43 W
Add 1 % Water charges on "W" 7.6043
TOTAL 768.03 X
Add GST (multiplying factor 0.1405) on "X" 107.91
TOTAL 875.94 Y
Add 15 % Contractor's profit and overheads on "Y" 131.39
Total 1007.33 Z
Add Cess @ 1% on "Z" 10.07
Cost of 0.66 sqm. 1017.40
Cost of 1 sqm. 1541.52
Say 1541.50

9.7.6 Coir Veneer Board (conforming to IS


14842)
9.7.6.1 12 mm thick

Details of cost for shutters of a door with


2/3 rd panelling 200x108cm = 2.16 sqm
Panel area 4x45.1x36.55cm=0.66sqm
MATERIAL
Coir veneered board 12mm thick
4x47.2x38.65cm = 0.73sqm
Add for wastage @ 10% = 0.07sqm
Total = 0.80 sqm
7555 Coir veneered board 12mm thick sqm 0.8 670 536.00
9977 CARRIAGE LABOUR L.S. 1.82 2 3.64
14 Carpenter 1st class day 0.57 505.17 287.95
9999 Sundries L.S. 4.42 2 8.84
TOTAL 836.43 W
Add 1 % Water charges on "W" 8.3643
TOTAL 844.79 X
Add GST (multiplying factor 0.1405) on "X" 118.69
TOTAL 963.48 Y
Add 15 % Contractor's profit and overheads on "Y" 144.52
Total 1108.00 Z
Add Cess @ 1% on "Z" 11.08
Cost of 0.66 sqm. 1119.08
Cost of 1 sqm. 1695.58
Say 1695.60

9.7.7 Float glass panes

9.7.7.1 4 mm thick glass pane


Details of cost for shutters of a door with 2/3 rd panelling
200x108cm = 2.16 sqm
Panel area 4x45.1x36.55cm=0.66sqm MATERIAL

Float glass sheet of nominal thickness


4 mm 4x47.2x38.65cm = 0.73sqm
Add for wastage @ 10% = 0.07sqm
Total = 0.80 sqm
2406 Float glass sheet of nominal thickness 4 mm sqm 0.8 300 240.00
9977 (weight not less than 10kg/sqm). 0.00
CARRIAGE LABOUR L.S. 1.82 2 3.64
41 Carpenter (average) day 0.57 403.67 230.09
21 Glazier day 0.15 403.67 60.55
17 Beldar day 0.15 350.00 52.50
9999 Sundries L.S. 25.47 2 50.94
TOTAL 637.72 W
Add 1 % Water charges on "W" 6.3772
TOTAL 644.10 X
Add GST (multiplying factor 0.1405) on "X" 90.50
TOTAL 734.60 Y
Add 15 % Contractor's profit and overheads on "Y" 110.19
Total 844.79 Z
Add Cess @ 1% on "Z" 8.45
Cost of 0.66 sqm. 853.24
Cost of 1 sqm. 1292.78
Say 1292.80

9.7.7.2 5.5 mm thick glass panes


Details of cost for shutters of a door with
2/3 rd panelling 200x108cm = 2.16 sqm
Panel area 4x45.1x36.55cm=0.66 sqm
MATERIAL
Float glass sheet of nominal thickness
5.5 mm 4x47.2x38.65cm = 0.73sqm
Add for wastage @ 10% = 0.07sqm
Total = 0.80 sqm
2407 Float glass sheet of nominal thickness sqm 0.8 500 400.00
5.5 mm.(weight not less than 13.50 kg/sqm).
9977 CARRIAGE L.S. 1.82 2 3.64
LABOUR
41 Carpenter (average) day 0.57 403.67 230.09
21 Glazier day 0.15 403.67 60.55
17 Beldar day 0.15 350.00 52.50
9999 Sundries L.S. 25.47 2 50.94
TOTAL 797.72 W
Add 1 % Water charges on "W" 7.9772
TOTAL 805.70 X
Add GST (multiplying factor 0.1405) on "X" 113.20
TOTAL 918.90 Y
Add 15 % Contractor's profit and overheads on "Y" 137.83
Total 1056.73 Z
Add Cess @ 1% on "Z" 10.57
Cost of 0.66 sqm. 1067.30
Cost of 1 sqm. 1617.12
Say 1617.10

9.7.8 Fly proof stainless steel grade 304 wire


gaugeofwith
Details cost0.5 mm dia.
for shutters wire
of a doorand
with 1.4 mm
wide aperture with matching
2/3 rd panelling 200x108cm = 2.16 sqm
wood beading
Panel area 4x45.1x36.55cm=0.66sqm
MATERIAL
Stainless steel wire guage
4x47.2x38.65cm = 0.73sqm
Add for wastage @ 10% = 0.07sqm
Total = 0.80 sqm
8737 Stainless steel wire guage (Grade-304) aperture sqm 0.8 400 320.00
1.4mm and 0.50 mm dia wire
9977 CARRIAGE L.S. 1.82 2 3.64
LABOUR
15 Carpenter 2nd class day 0.57 403.67 230.09
9999 Sundries L.S. 4.42 2 8.84
TOTAL 562.57 W
Add 1 % Water charges on "W" 5.6257
TOTAL 568.20 X
Add GST (multiplying factor 0.1405) on "X" 79.83
TOTAL 648.03 Y
Add 15 % Contractor's profit and overheads on "Y" 97.20
Total 745.23 Z
Add Cess @ 1% on "Z" 7.45
Cost of 0.66 sqm. 752.68
Cost of 1 sqm. 1140.42
Say 1140.40

9.9 Providing and fixing glazed shutters for


doors, windows and clerestory windows
9.9.1 using 4 mm thick float glass panes,
Second class
including teak wood
ISI marked M.S. pressed butt
9.9.1.1 35 mm thick

Details of cost for shutter of a door (glazed)


2000x108cm = 2.16 sqm. MATERIAL Teak wood
(2nd class)
Styles : 4x200x9.5x3.5cm = 0.027cum
Rails
Top & intermediate rails
2x110.5x9.5x3.5cm = 0.008cum
Lock and bottom rails
2x110.5x19.7x3.5cm = 0.015cum
Beadings-
2x186.1x1.9x1.2cm = 0.001cum
4x171.70x1.9x1.2cm = 0.002cum.
Total = 0.053 cum.
Add for wastage @ 10% = 0.005cum.
Grand Total = 0.058 cum = 58 cudm
1190 Second class teak wood in planks 10 5.8 791 4587.80
cudm 0.00
2406 Float glass sheet of nominal thickness sqm 1.27 300 381.00
4 mm (weight not less than 10kg/sqm).
595 Bright finished or black enamelled mild steel butt 10 Nos 0.6 80 48.00
597 hinges 100x58x1.90 mm 0.00
Bright finished or black enamelled mild steel butt 10 Nos 0.2 49 9.80
hinges50x37x1.50 mm 0.00
637 Bright finished or black enamelled mild steel 100 0.48 60 28.80
screws 40 mm Nos 0.00
640 Bright finished or black enamelled mild steel 100 0.08 30 2.40
2204 screws 20 mm Nos 0.00
Carriage of Timber cum 0.058 121.29 7.03
LABOUR 0
41 Carpenter (average) day 1.83 403.67 738.72
21 Glazier day 0.23 403.67 92.84
17 Beldar day 0.77 350.00 269.50
9999 Sundries L.S. 40.43 2 80.86
TOTAL 6246.75 W
Add 1 % Water charges on "W" 62.4675
TOTAL 6309.22 X
Add GST (multiplying factor 0.1405) on "X" 886.45
TOTAL 7195.67 Y
Add 15 % Contractor's profit and overheads on "Y" 1079.35
Total 8275.02 Z
Add Cess @ 1% on "Z" 82.75
Cost of 2.16 sqm. 8357.77
Cost of 1 sqm. 3869.34
Say 3869.30

9.9.1.2 30 mm thick
Details of cost for shutter of a door (glazed)
2000x108cm = 2.16 sqm.
MATERIAL Teak wood
Styles : 4x200x9.5x3.0cm = 0.023cum+
Rails
Top & intermediate rails
2x110.5x9.5x3.0cm = 0.006cum+
Lock and bottom rails
2x110.5x19.7x3.0cm = 0.013cum+
Beadings-
2x186.1x1.9x1.2cm = 0.001cum+
4x171.70x1.9x1.2cm = 0.002cum.
Total = 0.045 cum.+
Add for wastage @ 10% = 0.005cum.
Grand Total = 0.050 cum = 50 cudm
1190 Second class teak wood in planks 10 5 791 3955.00
2406 cudm 0.00
Float glass sheet of nominal thickness sqm 1.27 300 381.00
4 mm (weight not less than 10kg/sqm). 0.00
595 Bright finished or black enamelled mild steel butt 10 Nos 0.6 80 48.00
597 hinges 100x58x1.90 mm 0.00
Bright finished or black enamelled mild steel butt 10 Nos 0.2 49 9.80
hinges50x37x1.50 mm 0.00
637 Bright finished or black enamelled mild steel 100 0.48 60 28.80
screws 40 mm Nos 0.00
640 Bright finished or black enamelled mild steel 100 0.08 30 2.40
2204 screws 20 mm Nos 0.00
Carriage of Timber cum 0.05 121.29 6.06
LABOUR 0.00
41 Carpenter (average) day 1.83 403.67 738.72
21 Glazier day 0.23 403.67 92.84
17 Beldar day 0.77 350.00 269.50
9999 Sundries L.S. 40.43 2 80.86
TOTAL 5612.98 W
Add 1 % Water charges on "W" 56.1298
TOTAL 5669.11 X
Add GST (multiplying factor 0.1405) on "X" 796.51
TOTAL 6465.62 Y
Add 15 % Contractor's profit and overheads on "Y" 969.84
Total 7435.46 Z
Add Cess @ 1% on "Z" 74.35
Cost of 2.16 sqm. 7509.81
Cost of 1 sqm. 3476.76
Say 3476.80

9.9.2 Kiln seasoned and chemically treated


9.9.2.1 hollock wood
35 mm thick
Details of cost for shutters of a door (glazed)
200x108cm = 2.16 sqm.
MATERIAL
Hollock wood Styles :
4x200x9.5x3.5cm = 0.027cum+
Rails
Top & intermediate rails
2x110.5x9.5x3.5cm = 0.008cum+
Lock and bottom rails
2x110.5x19.7x3.5cm = 0.015cum.+
Beadings-
2x186.1x1.9x1.2cm = 0.001cum+
4x171.70x1.9x1.2cm = 0.002cum.
Total = 0.053 cum.+
Add for wastage @ 10% = 0.005cum.
Grand Total = 0.058 cum or = 58 cudm
2505 Hollock wood in planks 10 5.8 390 2262.00
cudm 0.00
2504 Kiln seasoning of timber cum 0.058 750 43.50
9999 (iii) Chemical treatment L.S. 9.1 2 18.20
2406 Float glass sheet of nominal thickness sqm 1.27 300 381.00
4 mm (weight not less than 10kg/sqm). 0.00
595 Bright finished or black enamelled mild steel butt 10 Nos 0.6 80 48.00
hinges 100x58x1.90 mm 0.00
597 Bright finished or black enamelled mild steel butt 10 Nos 0.2 49 9.80
637 hinges50x37x1.50 mm 0.00
Bright finished or black enamelled mild steel 100 0.48 60 28.80
640 screws 40 mm Nos 0.00
Bright finished or black enamelled mild steel 100 0.08 30 2.40
2204 screws 20 mm Nos 0.00
Carriage of Timber cum 0.058 121.29 7.03
LABOUR 0.00
41 Carpenter (average) day 1.83 403.67 738.72
21 Glazier day 0.23 403.67 92.84
17 Beldar day 0.77 350.00 269.50
9999 Sundries L.S. 40.43 2 80.86
TOTAL 3982.65 W
Add 1 % Water charges on "W" 39.8265
TOTAL 4022.48 X
Add GST (multiplying factor 0.1405) on "X" 565.16
TOTAL 4587.64 Y
Add 15 % Contractor's profit and overheads on "Y" 688.15
Total 5275.79 Z
Add Cess @ 1% on "Z" 52.76
Cost of 2.16 sqm. 5328.55
Cost of 1 sqm. 2466.92
Say 2466.90

9.9.2.2 30 mm thick
Details of cost for shutter of door (glazed)
2000x108cm = 2.16 sqm.
MATERIAL Hollock wood

Styles : 4x200x9.5x3.0cm = 0.023cum+


Rails
Top & intermediate rails
2x110.5x19.7x3.0cm = 0.006cum+
Lock and bottom rails
2x110.5x19.7x3.0cm = 0.013cum+
Beadings-
2x186.1x1.9x1.2cm = 0.001cum+
4x171.70x1.9x1.2cm = 0.002cum.
Total = 0.045 cum.+
Add for wastage @ 10% = 0.005cum. Grand Total
= 0.050 = 50 cudm
2505 Hollock wood in planks 10 5 390 1950.00
cudm 0.00
2504 Kiln seasoning of timber cum 0.05 750 37.50
9999 Chemical treatment L.S. 9.1 2 18.20
2406 Float glass sheet of nominal thickness sqm 1.27 300 381.00
4 mm (weight not less than 10kg/sqm). 0.00
595 Bright finished or black enamelled mild steel butt 10 Nos 0.6 80 48.00
hinges 100x58x1.90 mm 0.00
597 Bright finished or black enamelled mild steel butt 10 Nos 0.2 49 9.80
hinges50x37x1.50 mm 0.00
637 Bright finished or black enamelled mild steel 100 0.48 60 28.80
640 screws 40 mm Nos 0.00
Bright finished or black enamelled mild steel 100 0.08 30 2.40
2204 screws 20 mm Nos 0.00
Carriage of Timber cum 0.05 121.29 6.06
LABOUR 0.00
41 Carpenter (average) day 1.83 403.67 738.72
21 Glazier day 0.23 403.67 92.84
17 Beldar day 0.77 350.00 269.50
9999 Sundries L.S. 40.43 2 80.86
TOTAL 3663.68 W
Add 1 % Water charges on "W" 36.6368
TOTAL 3700.32 X
Add GST (multiplying factor 0.1405) on "X" 519.89
TOTAL 4220.21 Y
Add 15 % Contractor's profit and overheads on "Y" 633.03
Total 4853.24 Z
Add Cess @ 1% on "Z" 48.53
Cost of 2.16 sqm. 4901.77
Cost of 1 sqm. 2269.34
Say 2269.30

9.9.3 Kiln seasoned selected planks of


9.9.3.1 sheesham wood
35 mm thick
Details of cost for shutters of a door (glazed)
200x108cm = 2.16 sqm. MATERIAL Sheesham
wood
Styles :
4x200x9.5x3.5cm = 0.027cum+
Rails
Top & intermediate rails
2x110.5x9.5x3.5cm = 0.008cum+
Lock and bottom rails
2x110.5x19.7x3.5cm = 0.015cum.+
Beadings-
2x186.1x1.9x1.2cm = 0.001cum+
4x171.70x1.9x1.2cm = 0.002cum.
Total = 0.053 cum.+
Add for wastage @ 10% = 0.005cum.
Grand Total = 0.058 cum or = 58 cudm
1200 Kiln seasoned selected sheesum wood planks 10 5.8 650 3770.00
2504 cudm 0.00
Kiln seasoning of timber cum 0.058 750 43.50
2406 Float glass sheet of nominal thickness sqm 1.27 300 381.00
4 mm (weight not less than 10kg/sqm).
595 Bright finished or black enamelled mild steel butt 10 Nos 0.6 80 48.00
597 hinges 100x58x1.90 mm 0.00
Bright finished or black enamelled mild steel butt 10 Nos 0.2 49 9.80
637 hinges50x37x1.50 mm 0.00
Bright finished or black enamelled mild steel 100 0.48 60 28.80
640 screws 40 mm Nos 0.00
Bright finished or black enamelled mild steel 100 0.08 30 2.40
screws 20 mm Nos
2204 Carriage of Timber cum 0.058 121.29 7.03
LABOUR
41 Carpenter (average) day 1.83 403.67 738.72
21 Glazier day 0.23 403.67 92.84
17 Beldar day 0.77 350.00 269.50
9999 Sundries L.S. 40.43 2 80.86
TOTAL 5472.45 W
Add 1 % Water charges on "W" 54.7245
TOTAL 5527.17 X
Add GST (multiplying factor 0.1405) on "X" 776.57
TOTAL 6303.74 Y
Add 15 % Contractor's profit and overheads on "Y" 945.56
Total 7249.30 Z
Add Cess @ 1% on "Z" 72.49
Cost of 2.16 sqm. 7321.79
Cost of 1 sqm. 3389.72
Say 3389.70

9.9.3.2 30 mm thick

Details of cost for shutter of door (glazed)


2000x108cm = 2.16 sqm.
MATERIAL
Sheesham wood
Styles : 4x200x9.5x3.0cm = 0.023cum+
Rails
Top & intermediate rails
2x110.5x19.7x3.0cm = 0.006cum+
Lock and bottom rails
2x110.5x19.7x3.0cm = 0.013cum+
Beadings-
2x186.1x1.9x1.2cm = 0.001cum+
4x171.70x1.9x1.2cm = 0.002cum.
Total = 0.045 cum.+
Add for wastage @ 10% = 0.005cum. Grand Total
1200 = 0.050 = 50 cudm 0.00
Kiln seasoned selected sheesum wood planks 10 5 650 3250
2504 cudm
Kiln seasoning of timber cum 0.05 750 37.5
2406 Float glass sheet of nominal thickness sqm 1.27 300 381.00
4 mm (weight not less than 10kg/sqm).
595 Bright finished or black enamelled mild steel butt 10 Nos 0.6 80 48.00
597 hinges 100x58x1.90 mm
Bright finished or black enamelled mild steel butt 10 Nos 0.2 49 9.8
637 hinges50x37x1.50 mm
Bright finished or black enamelled mild steel 100 0.48 60 28.8
screws 40 mm Nos
640 Bright finished or black enamelled mild steel 100 0.08 30 2.40
2204 screws 20 mm Nos
Carriage of Timber cum 0.05 121.29 6.06
LABOUR
41 Carpenter (average) day 1.83 403.67 738.72
21 Glazier day 0.23 403.67 92.84
17 Beldar day 0.77 350.00 269.50
9999 Sundries L.S. 40.43 2 80.86
TOTAL 4945.48 W
Add 1 % Water charges on "W" 49.4548
TOTAL 4994.93 X
Add GST (multiplying factor 0.1405) on "X" 701.79
TOTAL 5696.72 Y
Add 15 % Contractor's profit and overheads on "Y" 854.51
Total 6551.23 Z
Add Cess @ 1% on "Z" 65.51
Cost of 2.16 sqm. 6616.74
Cost of 1 sqm. 3063.31
Say 3063.30

9.10 Providing and fixing factory


made laminated
9.10.1 30 mm veneer lumber glazed
thick shutters
shutter conforming to IS: 14616 and TADS
Details of cost of one shutter 220x108cm =
15:2001 (Part B), using 4 mm thick float
2.38sqm.
MATERIAL
7151 Factory made 30 mm thick shutters with laminated sqm 2.38 1620 3855.60
veneer lumber styles rails as per TADS IS:1995
and panels of sheet glass using 10 kg/ sqm glass
9977 panes 0.00
Carriage of shutters Fittings : L.S. 29.64 2 59.28
LABOUR
41 Carpenter (average) day 0.52 403.67 209.91
17 Beldar day 0.6 350.00 210.00
9999 Sundries L.S. 35.88 2 71.76
TOTAL 4406.55 W
Add 1 % Water charges on "W" 44.0655
TOTAL 4450.62 X
Add GST (multiplying factor 0.1405) on "X" 625.31
TOTAL 5075.93 Y
Add 15 % Contractor's profit and overheads on "Y" 761.39
Total 5837.32 Z
Add Cess @ 1% on "Z" 58.37
Cost of 2.38 sqm. 5895.69
2477.18
Cost of 1 sqm. 2477.20
Say

9.11 Extra for providing heavy sheet


float glass panes instead of ordinary float
glass in glazed doors, windows and
9.11.1 5.5 mm shutters.
clerestory window thick instead
(Areaofof4 mm
thick.
Details of cost for one sqm.
MATERIAL
2407 Float glass sheet of nominal thickness 5.5 sqm 1 500 500.00
mm.(weight not less than 13.50 kg/sqm).
Deduct
2406 Float glass sheet of nominal thickness sqm -1 300 -300.00
4 mm (weight not less than 10kg/sqm).
Total 200.00 W
Add 1 % Water charges on "W" 2
TOTAL 202.00 X
Add GST (multiplying factor 0.1405) on "X" 28.38
TOTAL 230.38 Y
Add 15 % Contractor's profit and overheads on "Y" 34.56
Total 264.94 Z
Add Cess @ 1% on "Z" 2.65
Cost of 1 sqm. 267.59
Say 267.59
267.60

9.12 Extra for providing frosted glass


panes
Cost for 4 mm thick instead of ordinary float
1 sqm.
glass panes 4 mm thick in doors, windows
and clerestory window shutters. (Area of
MATERIAL
7032 Frosted glass sheet of nominal thickness 4 mm sqm 1 460 460.00
2406 (weighing not less than 10 kg/sqm) Deduct 0.00
Float glass sheet of nominal thickness 4 mm sqm -1 300 -300
(weight not less than 10kg/sqm).
TOTAL 160.00 W
Add 1 % Water charges on "W" 1.6
TOTAL 161.60 X
Add GST (multiplying factor 0.1405) on "X" 22.70
TOTAL 184.30 Y
Add 15 % Contractor's profit and overheads on "Y" 27.65
Total 211.95 Z
Add Cess @ 1% on "Z" 2.12
Cost of 1 sqm. 214.07
214.07
Say 214.10

9.13 Deduct for providing pin headed glass


panes
panes instead
weighingof4ordinary
mm thickfloat glass
in doors,
windows(Area
shutters and clerestory
of openingwindows
for glass panes
excluding portion inside rebate shall
be measured).
Cost for 1 sqm.
MATERIAL
2406 Float glass sheet of nominal thickness 4 mm sqm -1 300 -300.00
(weight not less than 10kg/sqm).
Deduct
7451 Glass sheet (Pin headed) 4 mm thick sqm 1 305 305.00
TOTAL 5.00 W
Add 1 % Water charges on "W" 0.05
TOTAL 5.05 X
Add GST (multiplying factor 0.1405) on "X" 0.71
TOTAL 5.76 Y
Add 15 % Contractor's profit and overheads on "Y" 0.86
Total 6.62 Z
Add Cess @ 1% on "Z" 0.07
Cost of 1 sqm. 6.69
Say 6.69
6.70

9.14 Extra for providing ISI marked


Stainless
(Shutter area tobutt
Steel hinges instead of M.S.
be measured).
pressed butt hinges bright finished of
Details of cost for one door shutter of a door
required size with necessary screws.
200x108cm = 2.16 sqm. MATERIAL
8220 Stainless steel butt hinges (heavy weight) 10 Nos 0.6 255 153.00
8218 100x60x2.5 mm IS : 12817 marked
Stainless steel butt hinges 50x37x1.5 mm IS : 10 Nos 0.2 135 27.00
8211 12817 marked
Stainless steel screws 40 mm 100 0.48 215 103.20
Nos
8214 Stainless steel screws 20 mm Deduct 100 0.08 125 10.00
Nos
595 Bright finished or black enamelled mild steel butt 10 Nos -0.6 80 -48.00
hinges 100x58x1.90 mm
597 Bright finished or black enamelled mild steel butt 10 Nos -0.2 49 -9.80
hinges50x37x1.50 mm Black enameled Iron
637 Bright finished or black enamelled mild steel 100 -0.48 60 -28.80
screws 40 mm Nos
640 Bright finished or black enamelled mild steel 100 -0.08 30 -2.40
screws 20 mm Nos
TOTAL 204.20 W
Add 1 % Water charges on "W" 2.042
TOTAL 206.24 X
Add GST (multiplying factor 0.1405) on "X" 28.98
TOTAL 235.22 Y
Add 15 % Contractor's profit and overheads on "Y" 35.28
Total 270.50 Z
Add Cess @ 1% on "Z" 2.71
Cost of 2.16 sqm. 273.21
Cost of 1 sqm. 126.49
Say 126.50

9.15 Deduct for not providing hinges


in doors,
9.15.1 windows
Stainless or steel
clerestory window
butt hinges with
shutters
stainless with
steel: screws :
9.15.1.1 For 2nd class teak wood and
other class
Details of costof
of wood shutters
fittings for shutter of size
200x108cm = 2.16 sqm.
MATERIAL
Anodised aluminum butt hinges
8220 Stainless steel butt hinges (heavy weight) 10 Nos 0.6 255 153.00
8218 100x60x2.5 mm IS : 12817 marked 0.00
Stainless steel butt hinges 50x37x 10 Nos 0.2 135 27.00
1.5 mm IS : 12817 marked 0.00
8211 Stainless steel screws 40 mm 100 0.48 215 103.20
Nos 0.00
8214 Stainless steel screws 20 mm 100 0.08 125 10.00
TOTAL Nos 293.20 W
Add 1 % Water charges on "W" 2.932
TOTAL 296.13 X
Add GST (multiplying factor 0.1405) on "X" 41.61
TOTAL 337.74 Y
Add 15 % Contractor's profit and overheads on "Y" 50.66
Total 388.40 Z
Add Cess @ 1% on "Z" 3.88
Cost of 2.16 sqm. 392.28
Cost of 1 sqm. 181.61
Say 181.60

9.15.2 ISI marked M.S. pressed butt


hinges bright finished of required size.
9.15.2.1 For 2nd class teak wood and other
class of wood shutters
Details of cost of hinges with screws for shutters of
size 200x108cm = 2.16 sqm.
MATERIAL
595 Bright finished or black enamelled mild steel butt 10 Nos 0.6 80 48.00
597 hinges 100x58x1.90 mm 0.00
Bright finished or black enamelled mild steel butt 10 Nos 0.2 49 9.80
637 hinges50x37x1.50 mm 0.00
Bright finished or black enamelled mild steel 100 0.48 60 28.80
640 screws 40 mm Nos 0.00
Bright finished or black enamelled mild steel 100 0.08 30 2.40
screws 20 mm Nos
TOTAL 89.00 W
Add 1 % Water charges on "W" 0.89
TOTAL 89.89 X
Add GST (multiplying factor 0.1405) on "X" 12.63
TOTAL 102.52 Y
Add 15 % Contractor's profit and overheads on "Y" 15.38
Total 117.90 Z
Add Cess @ 1% on "Z" 1.18
Cost of 2.16 sqm. 119.08
Cost of 1 sqm. 55.13
Say 55.10

9.16 Providing and fixing 25 mm thick


shutters
9.16.1 for cup board
Panelled or etc. :
panelled & glazed
shutters
9.16.1.1 : Second class teak wood
including ISI marked
Details of cost for shuttersanodised aluminium
of a cup-board (half
butt hinges
glazed and halfwith
MATERIAL Styles-
necessary
panelled) screws
200x108cm = 2.16 sqm.
4x200x8.0x2.5cm = 0.016 cum+
RailsTop rail-
1x110.5x8.0x2.5cm = 0.0022cum+ Lock and
bottom rail-
2x110.5x8.0x2.5cm = 0.0044 cum.
Panels-
2x48x41x1.6cm = 0.006cum+
Sash bars-
2x114x3.8x2.5cm = 0.003cum+
6x48x3.8x2.5cm = 0.003 cum+
Beading-
16x92x1.4x1.2cm = 0.002cum
Total = 0.0366
Add for wastage @ 10% = 0.0037 cum.
Grand Total = 0.0403 cum or 40 cudm
1190 Second class teak wood in planks 10 4 791 3164.00
2204 cudm 0.00
Carriage of Timber cum 0.04 121.29 4.85
2406 Float glass sheet of nominal thickness 4 mm sqm 0.99 300 297.00
(weight not less than 10kg/sqm). 0.00
Fittings- 0.00
694 Anodised Aluminium butt hinges 75x45x3.2 mm 10 Nos 0.6 196 117.60
586 Chromium plated Brass screws 40 mm 100 0.48 290 139.20
LABOUR Nos 0.00
0.00
14 Carpenter 1st class day 2.4 505.17 1212.41
21 Glazier day 0.18 403.67 72.66
17 Beldar day 0.77 350.00 269.50
9999 Sundries L.S. 40.43 2 80.86
TOTAL 5358.08 W
Add 1 % Water charges on "W" 53.5808
TOTAL 5411.66 X
Add GST (multiplying factor 0.1405) on "X" 760.34
TOTAL 6172.00 Y
Add 15 % Contractor's profit and overheads on "Y" 925.80
Total 7097.80 Z
Add Cess @ 1% on "Z" 70.98
Cost of 2.16 sqm. 7168.78
Cost of 1 sqm. 3318.88
Say 3318.90

9.16.1.2 Second class teak wood


including iSi for
Details of cost marked
shuttersnickel plated bright
of a cup-board (half
glazed andM.S.
finished piano hinges
half panelled) with =necessary
200x108cm 2.16 sqm.
screws
MATERIAL Styles-
4x200x8.0x2.5cm = 0.016 cum+ RailsTop rail- 0.00
1x110.5x8.0x2.5cm = 0.0022cum+ Lock and
bottom rail-
2x110.5x8.0x2.5cm = 0.0044 cum. Panels-
2x48x41x1.6cm = 0.006cum+ Sash bars-
2x114x3.8x2.5cm = 0.003cum+ 6x48x3.8x2.5cm =
0.003 cum+ Beading-
16x92x1.4x1.2cm = 0.002cum Total = 0.0366
Add for wastage @ 10% = 0.0037 cum. Grand Total
= 0.0403 cum or 40 cudm
1190 Second class teak wood in planks 10 4 791 3164.00
cudm
2204 Carriage of Timber cum 0.04 121.29 4.85
2406 Float glass sheet of nominal thickness 4 mm sqm 0.99 300 297.00
(weight not less than 10kg/sqm).
Fittings-
608 Nickel plated mild steel piono hinges 1 mm thick metre 4 39 156.00
25 mm wide 0.00
586 Chromium plated Brass screws 40 mm 100 1.14 290 330.6
LABOUR Nos
14 Carpenter 1st class day 2.4 505.17 1212.41
21 Glazier day 0.18 403.67 72.66
17 Beldar day 0.77 350.00 269.50
9999 Sundries L.S. 40.43 2 80.86
TOTAL 5587.88 W
Add 1 % Water charges on "W" 55.8788
TOTAL 5643.76 X
Add GST (multiplying factor 0.1405) on "X" 792.95
TOTAL 6436.71 Y
Add 15 % Contractor's profit and overheads on "Y" 965.51
Total 7402.22 Z
Add Cess @ 1% on "Z" 74.02
Cost of 2.16 sqm. 7476.24
Cost of 1 sqm. 3461.22
Say 3461.20

9.16.2 Glazed shutters :


9.16.2.1 Second class teak wood
including ISI marked
Details of cost for anodized
shutter of cup-boardaluminium
butt hinges with necessary
2000x108cm = 2.16 sqm. MATERIAL
screws
(i) Teak wood second class
Styles : 4x200x9.5x2.5 cm = 0.019 cum
Rails
Top & intermediate rails
2x110.5x9.5x2.5 cm = 0.006 cum
Lock and bottom rails
2x110.5x19.7x2.5 cm = 0.011 cum
Beadings-
2x186.1x1.9x1.2cm = 0.001cum+
4x171.70x1.9x1.2cm = 0.002cum.
Total = 0.039 cum.
Add for wastage @ 10% = 0.004 cum.
Grand Total = 0.043 cum. 43 cudm
1190 Second class teak wood in planks 10 4.3 791 3401.30
cudm 0.00
2406 Float glass sheet of nominal thickness sqm 1.27 300 381
4 mm (weight not less than 10kg/sqm).
694 Anodised Aluminium butt hinges 75x45x3.2 mm 10 Nos 0.6 196 117.60
639 Bright finished or black enamelled mild steel 100 0.48 36 17.28
2204 screws 25 mm Nos
Carriage of Timber cum 0.04 121.29 5.22
LABOUR
41 Carpenter (average) day 1.83 403.67 738.72
21 Glazier day 0.23 403.67 92.84
17 Beldar day 0.77 350.00 269.50
9999 Sundries L.S. 40.43 2 80.86
TOTAL 5104.32 W
Add 1 % Water charges on "W" 51.0432
TOTAL 5155.36 X
Add GST (multiplying factor 0.1405) on "X" 724.33
TOTAL 5879.69 Y
Add 15 % Contractor's profit and overheads on "Y" 881.95
Total 6761.64 Z
Add Cess @ 1% on "Z" 67.62
Cost of 2.16 sqm. 6829.26
Cost of 1 sqm. 3161.7
Say 3161.70

9.16.2.2 Second class teak wood


including ISI marked nickel plated bright
finished M.S. piano hinges with necessary
Details of cost for shutter of cup-board
screws
2000x108cm = 2.16 sqm.
MATERIAL
(i) Teak wood second class
Styles : 4x200x9.5x2.5 cm = 0.019 cum
Rails
Top & intermediate rails
2x110.5x9.5x2.5 cm = 0.006 cum
Lock and bottom rails
2x110.5x19.7x2.5 cm = 0.011 cum
Beadings-
2x186.1x1.9x1.2cm = 0.001cum+
4x171.70x1.9x1.2cm = 0.002cum.
Total = 0.039 cum.
Add for wastage @ 10% = 0.004 cum.
Grand Total = 0.0403 cum or 43 cudm
1190 Second class teak wood in planks 10 4.3 791 3401.30
cudm 0.00
2406 Float glass sheet of nominal thickness sqm 1.27 300 381.00
4 mm (weight not less than 10kg/sqm). 0.00
608 Nickel plated mild steel piono hinges 1 mm thick metre 4 39 156.00
25 mm wide 0.00
639 Bright finished or black enamelled mild steel 100 1.14 36 41.04
2204 screws 25 mm Nos 0.00
Carriage of Timber cum 0.043 121.29 5.22
LABOUR 0.00
41 Carpenter (average) day 1.83 403.67 738.72
21 Glazier day 0.23 403.67 92.84
17 Beldar day 0.77 350.00 269.50
9999 Sundries L.S. 40.43 2 80.86
TOTAL 5166.48 W
Add 1 % Water charges on "W" 51.6648
TOTAL 5218.14 X
Add GST (multiplying factor 0.1405) on "X" 733.15
TOTAL 5951.29 Y
Add 15 % Contractor's profit and overheads on "Y" 892.69
Total 6843.98 Z
Add Cess @ 1% on "Z" 68.44
Cost of 2.16 sqm. 6912.42
Cost of 1 sqm. 3200.2
Say 3200.20

9.17 Providing and fixing flat pressed 3 layer


9.17.1 particle
12 mmboardthick medium density exterior
grade (Grade I) or graded wood particle
Details of cost for 350x200cm = 7sqm.
board IS : 3087 marked, to frame, backing
MATERIAL
12mm thick particle board = 7.00sqm.+ Add
wastage @ 5% = 0.35 sqm. Total = 7.35 sqm
341 Flat pressed 3 layer particle board (medium sqm 7.35 288 2116.80
9977 density) Grade I :12 mm thick 0.00
Carriage of particle board L.S. 13.52 2 27.04
9999 Sundries and screws L.S. 26.91 2 53.82
LABOUR 0.00
15 Carpenter 2nd class day 0.9 403.67 363.30
17 Beldar day 1 350.00 350.00
TOTAL 2910.96 W
Add 1 % Water charges on "W" 29.1096
TOTAL 2940.07 X
Add GST (multiplying factor 0.1405) on "X" 413.08
TOTAL 3353.15 Y
Add 15 % Contractor's profit and overheads on "Y" 502.97
Total 3856.12 Z
Add Cess @ 1% on "Z" 38.56
Cost of 7 sqm. 3894.68
Cost of 1 sqm. 556.38
Say 556.40

9.17.2 18 mm thick
Details of cost for 350x200cm = 7sqm.
MATERIAL
12mm thick particle board = 7.00sqm.+ Add
wastage @ 5% = 0.35 sqm. Total = 7.35 sqm
7055 Flat pressed 3 layer and graded particle board sqm 7.35 480 3528.00
(medium density) Grade
1 conforming to IS : 3087 - 18 mm thick
9977 Carriage of particle board L.S. 19.76 2 39.52
9999 Sundries and screws L.S. 26.91 2 53.82
LABOUR
15 Carpenter 2nd class day 0.9 403.67 363.30
17 Beldar day 1 350.00 350.00
TOTAL 4334.64 W
Add 1 % Water charges on "W" 43.3464
TOTAL 4377.99 X
Add GST (multiplying factor 0.1405) on "X" 615.11
TOTAL 4993.10 Y
Add 15 % Contractor's profit and overheads on "Y" 748.96
Total 5742.06 Z
Add Cess @ 1% on "Z" 57.42
Cost of 7 sqm. 5799.48
Cost of 1 sqm. 828.5
Say 828.50
9.18 Providing and fixing Pre-
laminated
9.18.1 flat
18 pressed
mm thick3 layer (medium
density) particle board or graded wood
Details of cost for 4 nos. 75x20cm shelves = 0.60
particle
sqm. board IS : 3087 marked, with one
MATERIAL
18mm thick particle board 4x75x20cm = 0.60sqm.

Add wastage @ 5% = 0.03sqm. Total = 0.63 sqm


7478 Prelaminated particle board with one side sqm 0.63 650 409.50
decorative and other side balancing lamination, flat
pressed 3 layer & graded (medium density) Grade
I, Type II conforming to IS : 12823 (exterior grade)
9977 18 mm thick
Carriage of board L.S. 0.91 2 1.82
LABOUR
15 Carpenter 2nd class day 0.11 403.67 44.40
17 Beldar day 0.06 350.00 21.00
9999 Sundries, Painting edges & Screws L.S. 7.8 2 15.60
TOTAL 492.32 W
Add 1 % Water charges on "W" 4.9232
TOTAL 497.24 X
Add GST (multiplying factor 0.1405) on "X" 69.86
TOTAL 567.10 Y
Add 15 % Contractor's profit and overheads on "Y" 85.07
Total 652.17 Z
Add Cess @ 1% on "Z" 6.52
Cost of 0.60 sqm. 658.69
Cost per sqm. 1097.82
Say 1097.80

9.18.2 25 mm thick
Details of cost for 4 nos. 75x20cm shelves = 0.60
sqm.
MATERIAL
25mm thick particle board 4x75x20cm = 0.60sqm.
Add wastage @ 5% = 0.03sqm. Total = 0.63 sqm
7479 Prelaminated particle board with one side sqm 0.63 900 567.00
decorative and other side balancing lamination, flat
pressed 3 layer & graded (medium density) Grade
I, Type II conforming to IS : 12823 (exterior grade)
9977 25 mm thick
Carriage of board L.S. 1.82 2 3.64
LABOUR
15 Carpenter 2nd class day 0.11 403.67 44.40
17 Beldar day 0.06 350.00 21.00
9999 Sundries, Painting edges & Screws L.S. 7.8 2 15.60
TOTAL 651.64 W
Add 1 % Water charges on "W" 6.5164
TOTAL 658.16 X
Add GST (multiplying factor 0.1405) on "X" 92.47
TOTAL 750.63 Y
Add 15 % Contractor's profit and overheads on "Y" 112.59
Total 863.22 Z
Add Cess @ 1% on "Z" 8.63
Cost of 0.60 sqm. 871.85
Cost per sqm. 1453.08
Say 1453.10

9.20 Providing and fixing ISI marked


flush
9.20.1 door shutters
35 mm thick conforming to ISI
including IS : 2202
(Part I) decorative type, core of
marked Stainless Steel butt hinges with block
screws
board construction with frame of 1st class
necessary
Details of cost for 2.2 sqm.
MATERIAL
713 Block board construction flush door with teak wood sqm 2.2 1800 3960.00
9977 ply on both faces 35 mm thick
Carriage of door L.S. 29.64 2 59.28
8220 Stainless steel butt hinges (heavy weight) 10 Nos 0.6 255 153.00
8211 100x60x2.5 mm IS : 12817 marked 0.00
Stainless steel screws 40 mm 100 Nos 0.48 215 103.2
LABOUR
For fixing shutter and fittings
41 Carpenter (average) day 0.55 403.67 222.02
17 Beldar day 0.55 350.00 192.50
TOTAL 4690.00 W
Add 1 % Water charges on "W" 46.9
TOTAL 4736.90 X
Add GST (multiplying factor 0.1405) on "X" 665.53
TOTAL 5402.43 Y
Add 15 % Contractor's profit and overheads on "Y" 810.36
Total 6212.79 Z
Add Cess @ 1% on "Z" 62.13
Cost for 2.2 sqm. 6274.92
Cost of 1 sqm. 2852.24
Say 2852.20
9.20.2 30 mm thick including ISI
marked
screws Stainless Steel butt hinges with
necessary
Details of cost for 2.2 sqm.

MATERIAL
714 Block board construction flush door with teak wood sqm 2.2 1600 3520.00
9977 ply on both faces 30 mm thick
Carriage of door L.S. 29.64 2 59.28
8220 Stainless steel butt hinges (heavy weight) 10 Nos 0.6 255 153.00
8211 100x60x2.5 mm IS : 12817 marked 0.00
Stainless steel screws 40 mm 100 0.48 215 103.2
LABOUR Nos
For fixing shutter and fittings
41 Carpenter (average) day 0.55 403.67 222.02
17 Beldar day 0.55 350.00 192.50
TOTAL 4250.00 W
Add 1 % Water charges on "W" 42.5
TOTAL 4292.50 X
Add GST (multiplying factor 0.1405) on "X" 603.10
TOTAL 4895.60 Y
Add 15 % Contractor's profit and overheads on "Y" 734.34
Total 5629.94 Z
Add Cess @ 1% on "Z" 56.30
Cost for 2.2 sqm. 5686.24
Cost of 1 sqm. 2584.65
Say 2584.70

9.20.3 25 mm thick (for cupboard)


including ISI marked nickel plated bright
finished M.S. Piano hinges IS : 3818
Details of cost for 2.2 sqm.
marked with necessary screws
MATERIAL
715 Block board construction flush door with teak wood sqm 2.2 1400 3080.00
9977 ply on both faces 25 mm thick
Carriage of door L.S. 29.64 2 59.28
Fittings-For a door 2.2x1.0m = 2.20 sqm.
608 Nickel plated mild steel piono hinges 1 mm thick metre 4.4 39 171.60
639 25 mm wide 0.00
Bright finished or black enamelled mild 100 1.25 36 45
steel screws 25 mm Nos
LABOUR
For fixing shutter and fittings
41 Carpenter (average) day 0.55 403.67 222.02
17 Beldar day 0.55 350.00 192.50
TOTAL 3770.40 W
Add 1 % Water charges on "W" 37.704
TOTAL 3808.10 X
Add GST (multiplying factor 0.1405) on "X" 535.04
TOTAL 4343.14 Y
Add 15 % Contractor's profit and overheads on "Y" 651.47
Total 4994.61 Z
Add Cess @ 1% on "Z" 49.95
Cost for 2.2 sqm. 5044.56
Cost of 1 sqm. 2292.98
Say 2293.00

9.21 Providing and fixing ISI marked flush door


shutters conforming to IS : 2202 (Part I)
non-decorative type, core of block board
9.21.1 35with
construction mmframe
thick including ISIhard
of 1st class
marked Stainless Steel butt hinges with
necessary
screws
Details of cost for 2.2 sqm.

MATERIAL
717 Block board construction flush door with sqm 2.2 1150 2530.00
9977 commercial ply on both faces 35 mm thick
Carriage of door L.S. 29.64 2 59.28
Fittings-For a door 2.2x1.0m = 2.20 sqm.
8220 Stainless steel butt hinges (heavy weight) 10 Nos 0.6 255 153.00
8211 100x60x2.5 mm IS : 12817 marked 0.00
Stainless steel screws 40 mm 100 0.48 215 103.2
LABOUR Nos
For fixing shutter and fittings
41 Carpenter (average) day 0.55 403.67 222.02
17 Beldar day 0.55 350.00 192.50
TOTAL 3260.00 W
Add 1 % Water charges on "W" 32.6
TOTAL 3292.60 X
Add GST (multiplying factor 0.1405) on "X" 462.61
TOTAL 3755.21 Y
Add 15 % Contractor's profit and overheads on "Y" 563.28
Total 4318.49 Z
Add Cess @ 1% on "Z" 43.18
Cost for 2.2 sqm. 4361.67
Cost of 1 sqm. 1982.58
Say 1982.60

9.21.2 30 mm thick including ISI marked


Stainless
screws Steel butt hinges with necessary
Details of cost for 2.2 sqm.
MATERIAL
718 Block board construction flush door with sqm 2.2 1150 2530.00
9977 commercial ply on both faces 30 mm thick 0.00
Carriage of door L.S. 29.64 2 59.28
Fittings-For a door 2.2x1.0m = 2.20 sqm. 0.00
8220 Stainless steel butt hinges (heavy weight) 10 Nos 0.6 255 153.00
100x60x2.5 mm IS : 12817 marked 100 0.48 215 103.20
8211 Stainless steel screws 40 mm Nos 0.00
LABOUR 0.00
For fixing shutter and fittings 0.00
41 Carpenter (average) day 0.55 403.67 222.02
17 Beldar day 0.55 350.00 192.50
TOTAL 3260.00 W
Add 1 % Water charges on "W" 32.6
TOTAL 3292.60 X
Add GST (multiplying factor 0.1405) on "X" 462.61
TOTAL 3755.21 Y
Add 15 % Contractor's profit and overheads on "Y" 563.28
Total 4318.49 Z
Add Cess @ 1% on "Z" 43.18
Cost for 2.2 sqm. 4361.67
Cost of 1 sqm. 1982.58
Say 1982.60

9.21.3 25 mm thick (for cupboard) including ISI


marked
Details of nickel
cost for plated
2.2 sqm.bright finished M.S.
piano
MATERIAL
hinges with necessary screws
719 Block board construction flush door with sqm 2.2 1100 2420.00
9977 commercial ply on both faces 25 mm thick
Carriage of door L.S. 29.64 2 59.28
Fittings-For a door 2.2x1.0m = 2.20 sqm.
608 Nickel plated mild steel piono hinges 1 mm thick metre 4.4 39 171.60
639 25 mm wide 0.00
Bright finished or black enamelled mild 100 1.25 36 45
steel screws 25 mm Nos
LABOUR
For fixing shutter and fittings
41 Carpenter (average) day 0.55 403.67 222.02
17 Beldar day 0.55 350.00 192.50
TOTAL 3110.40 W
Add 1 % Water charges on "W" 31.104
TOTAL 3141.50 X
Add GST (multiplying factor 0.1405) on "X" 441.38
TOTAL 3582.88 Y
Add 15 % Contractor's profit and overheads on "Y" 537.43
Total 4120.31 Z
Add Cess @ 1% on "Z" 41.20
Cost for 2.2 sqm. 4161.51
Cost of 1 sqm. 1891.6
1891.60

9.22 Extra for Providing and fixing flush doors


9.22.1 with
On onedecorative
side only veneering instead of non
decorative ISI marked
Details of cost for 1sqm.
flush door shutters
conforming to IS: 2202 (Part I)
7307 For flush door shutters Extra for providing teak sqm 1 330 330.00
veneering on one side instead of commercial
veneering
TOTAL 330.00 W
Add 1 % Water charges on "W" 3.3
TOTAL 333.30 X
Add GST (multiplying factor 0.1405) on "X" 46.83
TOTAL 380.13 Y
Add 15 % Contractor's profit and overheads on "Y" 57.02
Total 437.15 Z
Add Cess @ 1% on "Z" 4.37
Cost for 1 sqm. 441.52
Say 441.52
441.50

9.23 Extra for providing lipping with 2nd class


teak wood battens 25 mm minimum depth
measured).
on all edges of flush door shutters (over all
Details of cost for 1 sqm. of door area
area of door shutter to be
752 Block board construction flush door lipping sqm of 1 300 300.00
door
TOTAL 300.00 W
Add 1 % Water charges on "W" 3
TOTAL 303.00 X
Add GST (multiplying factor 0.1405) on "X" 42.57
TOTAL 345.57 Y
Add 15 % Contractor's profit and overheads on "Y" 51.84
Total 397.41 Z
Add Cess @ 1% on "Z" Cost for 1 sqm. 3.97
Total 401.38
401.38
Say 401.40

9.24 Extra for providing vision panel not


exceeding 0.1 sqm in all type of flush
doors (cost of glass excluded) (overall area
of door shutter to be measured):
9.24.1 Rectangular or square

Details of cost for 1 sqm. of door area

753 Square vision panel (upto 0.10 sqm) in Block board sqm of 1 130 130.00
construction flush door
door
TOTAL 130.00 W
Add 1 % Water charges on "W" 1.3
TOTAL 131.30 X
Add GST (multiplying factor 0.1405) on "X" 18.45
TOTAL 149.75 Y
Add 15 % Contractor's profit and overheads on "Y" 22.46
Total 172.21 Z
Add Cess @ 1% on "Z" 1.72
Cost for 1 sqm. 173.93
Say 173.93
173.90

9.24.2 Circular

Details of cost for 1 sqm. of door area


754 Circular vision panel (upto 0.10 sqm) in Block board sqm of 1 135 135.00
construction flush door
door
TOTAL 135.00 W
Add 1 % Water charges on "W" 1.35
TOTAL 136.35 X
Add GST (multiplying factor 0.1405) on "X" 19.16
TOTAL 155.51 Y
Add 15 % Contractor's profit and overheads on "Y" 23.33
Total 178.84 Z
Add Cess @ 1% on "Z" 1.79
Cost for 1 sqm. 180.63
Say 180.63
180.60

9.25 Extra if louvers (not exceeding 0.2 sqm)


9.25.1 are providedtype
Decorative in flush
doordoor shutters (overall
area of door shutters to be measured).
Details of cost for 1 sqm. of door area
755 Decorative type Louvers (upto 0.20 sqm) in Block sqm of 1 265 265.00
board construction flush door
door
TOTAL 265.00 W
Add 1 % Water charges on "W" 2.65
TOTAL 267.65 X
Add GST (multiplying factor 0.1405) on "X" 37.60
TOTAL 305.25 Y
Add 15 % Contractor's profit and overheads on "Y" 45.79
Total 351.04 Z
Add Cess @ 1% on "Z" 3.51
Cost for 1 sqm. 354.55
Say 354.55
354.60

9.26 Extra for cutting rebate in flush door


shutters (Total area of the shutter to be
measured).
Details of cost for 1 sqm. of door area
757 Rebate cutting in Block board construction flush sqm of 1 70 70.00
door
door
TOTAL 70.00 W
Add 1 % Water charges on "W" 0.7
TOTAL 70.70 X
Add GST (multiplying factor 0.1405) on "X" 9.93
TOTAL 80.63 Y
Add 15 % Contractor's profit and overheads on "Y" 12.09
Total 92.72 Z
Add Cess @ 1% on "Z" 0.93
Cost for 1 sqm. 93.65
Say 93.65
93.70

9.27 Providing and fixing wire gauge shutters


using galvanized M.S. wire gauge of
average width of aperture 1.4 mm in both
directions with wire of dia 0.63 mm, for
9.27.1 35 mm thick shutters
9.27.1.1 with ISI marked M.S. pressed butt hinges
bright finished
Second of teak
class required
woodsize
Details of cost for door shutters 2.00x1.08m = 2.16
sqm.
MATERIAL
Teak wood (2nd class)
Styles 4x200x9.5x3.5cm = 0.0266cum+
Top Rail - 1x110.5x9.5x3.5cm = 0.0036cum+ Lock
and bottom rail
2x110.5x19.7x3.5cm = 0.0152 cum.+ Beadings -
(2x312+2x150)x(1.2)x (1.2)cm = 0.001 cum. Total
= 0.0464 cum.+
Add for wastage @ 10% = 0.005 cum. Total =
0.0514 cum.
Say 51.4 cudm.

1190 Second class teak wood in planks 10 cudm 5.14 791 4065.74
Wire gauge 2x160x40cm = 1.28 sqm.+ Add
wastage @ 10% = 0.13 sqm. Total = 1.41 sqm.
7029 Galvanised wire mesh of average width of aperture sqm 1.41 250 352.50
1.4 mm and nominal dia. of wire 0.63 mm 0.00
595 Bright finished or black enamelled mild steel butt 10 Nos 0.6 80 48.00
hinges 100x58x1.90 mm 0.00
597 Bright finished or black enamelled mild steel butt 10 Nos 0.2 49 9.80
hinges50x37x1.50 mm 0.00
637 Bright finished or black enamelled mild steel 100 0.48 60 28.80
640 screws 40 mm Nos 0.00
Bright finished or black enamelled mild steel 100 0.08 30 2.40
2204 screws 20 mm Nos 0.00
Carriage of Timber cum 0.0514 121.29 6.23
LABOUR 0.00
14 Carpenter 1st class day 1.3 505.17 656.72
15 Carpenter 2nd class day 0.9 403.67 363.30
17 Beldar day 1.05 350.00 367.50
30 Mistry day 0.105 505.17 53.04
9999 Sundries L.S. 33.8 2 67.60
TOTAL 6021.63 W
Add 1 % Water charges on "W" 60.2163
TOTAL 6081.85 X
Add GST (multiplying factor 0.1405) on "X" 854.50
TOTAL 6936.35 Y
Add 15 % Contractor's profit and overheads on "Y" 1040.45
Total 7976.80 Z
Add Cess @ 1% on "Z" 79.77
Cost of 2.16 sqm. 8056.57
Cost of 1 sqm. 3729.89
Say 3729.90

9.27.1.1.2 Kiln seasoned and chemically treated


hollockofwood
Details cost for door shutters 2.00x1.08m = 2.16
sqm.
MATERIAL
Hollock wood
Styles 4x200x9.5x3.5cm = 0.0266cum+
Top Rail - 1x110.5x9.5x3.5cm = 0.0036cum
Lock and bottom rail
2x110.5x19.7x3.5cm = 0.0152 cum.+ Beadings -
(2x312+2x150)x(1.2)x (1.2)cm = 0.001 cum. Total
= 0.0464 cum.+
Add for wastage @ 10% = 0.005 cum.
Total = 0.0514 cum.
Say 51.4 cudm.
2505 Hollock wood in planks 10 5.14 390 2004.60
2204 cudm 0.00
Carriage of Timber cum 0.0514 121.29 6.23
2504 Kiln seasoning of timber cum 0.0514 750 38.55
9999 Chemical treatment L.S. 8.97 2 17.94
Wire gauge 2x160x40cm = 1.28 sqm.+ Add
wastage @ 10% = 0.13 sqm.
Total = 1.41 sqm.
7029 Galvanised wire mesh of average width of aperture sqm 1.41 250 352.50
1.4 mm and nominal dia. of wire 0.63 mm
595 Bright finished or black enamelled mild steel butt 10 Nos 0.6 80 48.00
597 hinges 100x58x1.90 mm 0.00
Bright finished or black enamelled mild steel butt 10 Nos 0.2 49 9.80
637 hinges50x37x1.50 mm 0.00
Bright finished or black enamelled mild steel 100 0.48 60 28.80
640 screws 40 mm Nos 0.00
Bright finished or black enamelled mild steel 100 0.08 30 2.40
screws 20 mm Nos 0.00
LABOUR 0.00
14 Carpenter 1st class day 1.3 505.17 656.72
15 Carpenter 2nd class day 0.9 403.67 363.30
17 Beldar day 1.05 350.00 367.50
30 Mistry day 0.105 505.17 53.04
9999 Sundries L.S. 33.8 2 67.60
TOTAL 4016.98 W
Add 1 % Water charges on "W" 40.1698
TOTAL 4057.15 X
Add GST (multiplying factor 0.1405) on "X" 570.03
TOTAL 4627.18 Y
Add 15 % Contractor's profit and overheads on "Y" 694.08
Total 5321.26 Z
Add Cess @ 1% on "Z" 53.21
Cost of 2.16 sqm. 5374.47
Cost of 1 sqm. 2488.18
Say 2488.20

9.27.1.1.3 Kiln seasoned selected class of


sheesham wood
Details of cost for door shutters 2.00x1.08m = 2.16

sqm.
MATERIAL

Hollock wood
Styles 4x200x9.5x3.5cm = 0.0266cum+
Top Rail - 1x110.5x9.5x3.5cm = 0.0036cum+
Lock and bottom rail
2x110.5x19.7x3.5cm = 0.0152 cum.+ Beadings -
(2x312+2x150)x(1.2)x (1.2)cm = 0.001 cum. Total
= 0.0464 cum.+
Add for wastage @ 10% = 0.005 cum.
Total = 0.0514 cum.
Say 51.4 cudm.
1200 Kiln seasoned selected sheesum wood planks 10 5.14 650 3341.00
2204 cudm 0.00
Carriage of Timber cum 0.0514 121.29 6.23
2504 Kiln seasoning of timber cum 0.0514 750 38.55
Wire gauge 2x160x40cm = 1.28 sqm.+ Add 0.00
wastage @ 10% = 0.13 sqm. 0.00
Total = 1.41 sqm. 0.00
7029 Galvanised wire mesh of average width of sqm 1.41 250 352.50
aperture 1.4 mm and nominal dia. of wire 0.63 mm 0.00
595 Bright finished or black enamelled mild steel butt 10 Nos 0.6 80 48.00
597 hinges 100x58x1.90 mm 0.00
Bright finished or black enamelled mild steel butt 10 Nos 0.2 49 9.80
637 hinges50x37x1.50 mm 0.00
Bright finished or black enamelled mild steel 100 0.48 60 28.80
640 screws 40 mm Nos 0.00
Bright finished or black enamelled mild 100 0.08 30 2.40
steel screws 20 mm Nos 0.00
LABOUR 0.00
14 Carpenter 1st class day 1.3 505.17 656.72
15 Carpenter 2nd class day 0.9 403.67 363.30
17 Beldar day 1.05 350.00 367.50
30 Mistry day 0.105 505.17 53.04
9999 Sundries L.S. 33.8 2 67.60
TOTAL 5335.44 W
Add 1 % Water charges on "W" 53.3544
TOTAL 5388.79 X
Add GST (multiplying factor 0.1405) on "X" 757.13
TOTAL 6145.92 Y
Add 15 % Contractor's profit and overheads on "Y" 921.89
Total 7067.81 Z
Add Cess @ 1% on "Z" 70.68
Cost of 2.16 sqm. 7138.49
Cost of 1 sqm. 3304.86
Say 3304.90

9.27.1.2 With ISI marked stainless steel butt hinges


of required size teak wood
Second class
Details of cost for door shutters 2.00x1.08m = 2.16
sqm.
MATERIAL
Second class Teak wood
Styles 4x200x9.5x3.5cm = 0.0266cum+
Top Rail - 1x110.5x9.5x3.5cm = 0.0036cum+ Lock
and bottom rail
2x110.5x19.7x3.5cm = 0.0152 cum.+ Beadings -
(2x312+2x150)x(1.2)x (1.2)cm = 0.001 cum. Total
= 0.0464 cum.+
Add for wastage @ 10% = 0.005 cum. Total =
0.0514 cum.
Say 51.4 cudm.
1190 Second class teak wood in planks 10 5.14 791 4065.74
Wire gauge 2x160x40cm = 1.28 sqm.+ Add cudm
wastage @ 10% = 0.13 sqm. Total = 1.41 sqm.

7029 Galvanised wire mesh of average width of aperture sqm 1.41 250 352.50
1.4 mm and nominal dia. of wire 0.63 mm 0.00
8220 Stainless steel butt hinges (heavy weight) 10 Nos 0.6 255 153.00
8218 100x60x2.5 mm IS : 12817 marked 0.00
Stainless steel butt hinges 50x37x 10 Nos 0.2 135 27.00
1.5 mm IS : 12817 marked 0.00
8211 Stainless steel screws 40 mm 100 Nos 0.48 215 103.20
8214 Stainless steel screws 20 mm 100 Nos 0.08 125 10.00
2204 Carriage of Timber cum 0.0514 121.29 6.23
LABOUR 0.00
14 Carpenter 1st class day 1.3 505.17 656.72
15 Carpenter 2nd class day 0.9 403.67 363.30
17 Beldar day 1.05 350.00 367.50
30 Mistry day 0.105 505.17 53.04
9999 Sundries L.S. 33.8 2 67.60
TOTAL 6225.83 W
Add 1 % Water charges on "W" 62.2583
TOTAL 6288.09 X
Add GST (multiplying factor 0.1405) on "X" 883.48
TOTAL 7171.57 Y
Add 15 % Contractor's profit and overheads on "Y" 1075.74
Total 8247.31 Z
Add Cess @ 1% on "Z" 82.47
Cost of 2.16 sqm. 8329.78
Cost of 1 sqm. 3856.38
Say 3856.40

9.27.1.2.2 Kiln seasoned and chemically treated


hollock wood
Details of cost for door shutters 2.00x1.08m = 2.16
sqm.
MATERIAL Hollock wood

Styles 4x200x9.5x3.5cm = 0.0266cum+


Top Rail - 1x110.5x9.5x3.5cm = 0.0036cum+ Lock
and bottom rail
2x110.5x19.7x3.5cm = 0.0152 cum.+ Beadings -
(2x312+2x150)x(1.2)x (1.2)cm = 0.001 cum. Total
= 0.0464 cum.+
Add for wastage @ 10% = 0.005 cum.
Total = 0.0514 cum.
Say 51.4 cudm.
2505 Hollock wood in planks 10 5.14 390 2004.60
2504 cudm
Kiln seasoning of timber cum 0.0514 750 38.55
9999 Chemical treatment L.S. 8.97 2 17.94
Wire gauge 2x160x40cm = 1.28 sqm.+ Add
wastage @ 10% = 0.13 sqm.
Total = 1.41 sqm.
7029 Galvanised wire mesh of average width of aperture sqm 1.41 250 352.50
1.4 mm and nominal dia. of wire 0.63 mm
8220 Stainless steel butt hinges (heavy weight) 10 Nos 0.6 255 153.00
8218 100x60x2.5 mm IS : 12817 marked
Stainless steel butt hinges 50x37x 10 Nos 0.2 135 27
1.5 mm IS : 12817 marked
8211 Stainless steel screws 40 mm 100 0.48 215 103.20
8214 Nos
Stainless steel screws 20 mm 100 0.08 125 10
2204 Nos
Carriage of Timber cum 0.0514 121.29 6.23
LABOUR
14 Carpenter 1st class day 1.3 505.17 656.72
15 Carpenter 2nd class day 0.9 403.67 363.30
17 Beldar day 1.05 350.00 367.50
30 Mistry day 0.105 505.17 53.04
9999 Sundries L.S. 33.8 2 67.60
TOTAL 4221.18 W
Add 1 % Water charges on "W" 42.2118
TOTAL 4263.39 X
Add GST (multiplying factor 0.1405) on "X" 599.01
TOTAL 4862.40 Y
Add 15 % Contractor's profit and overheads on "Y" 729.36
Total 5591.76 Z
Add Cess @ 1% on "Z" 55.92
Cost of 2.16 sqm. 5647.68
Cost of 1 sqm. 2614.67
Say 2614.70

9.27.1.2.3 Kiln seasoned selected class of


sheesham
Details of costwood
for door shutters 2.00x1.08m = 2.16
sqm.
MATERIAL Hollock wood

Styles 4x200x9.5x3.5cm = 0.0266cum+


Top Rail - 1x110.5x9.5x3.5cm = 0.0036cum+
Lock and bottom rail
2x110.5x19.7x3.5cm = 0.0152 cum.+ Beadings -
(2x312+2x150)x(1.2)x (1.2)cm = 0.001 cum. Total
= 0.0464 cum.+
Add for wastage @ 10% = 0.005 cum.
Total = 0.0514 cum.
Say 51.4 cudm.
1200 Kiln seasoned selected sheesum wood planks 10 5.14 650 3341.00
2504 cudm
Kiln seasoning of timber cum 0.0514 750 38.55
Wire gauge 2x160x40cm = 1.28 sqm.+ Add
wastage @ 10% = 0.13 sqm.
Total = 1.41 sqm.
7029 Galvanised wire mesh of average width of aperture sqm 1.41 250 352.50
1.4 mm and nominal dia. of wire 0.63 mm
8220 Stainless steel butt hinges (heavy weight) 10 Nos 0.6 255 153.00
8218 100x60x2.5 mm IS : 12817 marked
Stainless steel butt hinges 50x37x 10 Nos 0.2 135 27
1.5 mm IS : 12817 marked
8211 Stainless steel screws 40 mm 100 0.48 215 103.20
8214 Nos
Stainless steel screws 20 mm 100 0.08 125 10
2204 Nos
Carriage of Timber cum 0.0514 121.29 6.23
LABOUR
14 Carpenter 1st class day 1.3 505.17 656.72
15 Carpenter 2nd class day 0.9 403.67 363.30
17 Beldar day 1.05 350.00 367.50
30 Mistry day 0.105 505.17 53.04
9999 Sundries L.S. 33.8 2 67.60
TOTAL 5539.64 W
Add 1 % Water charges on "W" 55.3964
TOTAL 5595.04 X
Add GST (multiplying factor 0.1405) on "X" 786.10
TOTAL 6381.14 Y
Add 15 % Contractor's profit and overheads on "Y" 957.17
Total 7338.31 Z
Add Cess @ 1% on "Z" 73.38
Cost of 2.16 sqm. 7411.69
Cost of 1 sqm. 3431.34
Say 3431.30

9.27.2 30 mm thick shutters


9.27.2.1 with ISI marked M.S. pressed butt hinges
bright
Second finished of required
class teak wood size
Details of cost for door shutters 2.00x1.08m = 2.16
sqm.
MATERIAL
Teak wood (2nd class)
Styles 4x209x9.5x3cm = 0.023 cum+
Top Rail - 1x110.5x9.5x3cm = 0.003cum+
Lock and bottom rail
2x110.5x19.7x3cm = 0.013 cum+ Beadings -
(2x312+2x150)x(1.2)x (1.2)cm = 0.001 cum.
Total = 0.040 cum+
Add for wastage @ 10% = 0.004 cum.
Total = 0.44 cum.
Say 44 cudm.
1190 Second class teak wood in planks 10 4.4 791 3480.40
2204 cudm
Carriage of Timber cum 0.044 121.29 5.34
Wire gauge 2x160x40cm = 1.28 sqm.+ Add
wastage @ 10% = 0.13 sqm.
Total = 1.41 sqm.
7029 Galvanised wire mesh of average width of aperture sqm 1.41 250 352.50
1.4 mm and nominal dia. of wire 0.63 mm
595 Bright finished or black enamelled mild steel butt 10 Nos 0.6 80 48.00
597 hinges 100x58x1.90 mm
Bright finished or black enamelled mild steel butt 10 Nos 0.2 49 9.8
637 hinges50x37x1.50 mm
Bright finished or black enamelled mild steel 100 0.48 60 28.8
640 screws 40 mm Nos
Bright finished or black enamelled mild 100 0.08 30 2.4
steel screws 20 mm Nos
LABOUR
14 Carpenter 1st class day 1.2 505.17 606.20
15 Carpenter 2nd class day 0.8 403.67 322.94
17 Beldar day 1 350.00 350.00
30 Mistry day 0.1 505.17 50.52
9999 Sundries L.S. 33.8 2 67.60
TOTAL 5324.50 W
Add 1 % Water charges on "W" 53.245
TOTAL 5377.75 X
Add GST (multiplying factor 0.1405) on "X" 755.57
TOTAL 6133.32 Y
Add 15 % Contractor's profit and overheads on "Y" 920.00
Total 7053.32 Z
Add Cess @ 1% on "Z" 70.53
Cost of 2.16 sqm. 7123.85
Cost of 1 sqm. 3298.08
Say 3298.10

9.27.2.1.2 Kiln seasoned and chemically treated


hollock
Details ofwood
cost for door shutters 2.00x1.08m = 2.16
sqm.
MATERIAL
Hollock wood
Styles 4x209x9.5x3cm = 0.023 cum+
Top Rail - 1x110.5x9.5x3cm = 0.003cum+
Lock and bottom rail
2x110.5x19.7x3cm = 0.013 cum+ Beadings -
(2x312+2x150)x(1.2)x (1.2)cm = 0.001 cum.
Total = 0.040 cum+
Add for wastage @ 10% = 0.004 cum.
Total = 0.44 cum.
Say 44 cudm.
2505 Hollock wood in planks 10 4.4 390 1716.00
2204 cudm
Carriage of Timber cum 0.044 121.29 5.34
2504 Kiln seasoning of timber cum 0.044 750 33.00
9999 Chemical treatment L.S. 9.1 2 18.20
Wire gauge 2x160x40cm = 1.28 sqm.+ Add
wastage @ 10% = 0.13 sqm.
Total = 1.41 sqm.
7029 Galvanised wire mesh of average width of aperture sqm 1.41 250 352.50
1.4 mm and nominal dia. of wire 0.63 mm
595 Bright finished or black enamelled mild steel butt 10 Nos 0.6 80 48.00
597 hinges 100x58x1.90 mm
Bright finished or black enamelled mild steel butt 10 Nos 0.2 49 9.8
637 hinges50x37x1.50 mm
Bright finished or black enamelled mild steel 100 0.48 60 28.8
640 screws 40 mm Nos
Bright finished or black enamelled mild 100 0.08 30 2.4
steel screws 20 mm Nos
LABOUR
14 Carpenter 1st class day 1.2 505.17 606.20
15 Carpenter 2nd class day 0.8 403.67 322.94
17 Beldar day 1 350.00 350.00
30 Mistry day 0.1 505.17 50.52
9999 Sundries L.S. 33.8 2 67.60
TOTAL 3611.30 W
Add 1 % Water charges on "W" 36.113
TOTAL 3647.41 X
Add GST (multiplying factor 0.1405) on "X" 512.46
TOTAL 4159.87 Y
Add 15 % Contractor's profit and overheads on "Y" 623.98
Total 4783.85 Z
Add Cess @ 1% on "Z" 47.84
Cost of 2.16 sqm. 4831.69
Cost of 1 sqm. 2236.89
Say 2236.90

9.27.2.1.3 Kiln seasoned selected class of


sheesham
Details of costwood
for door shutters 2.00x1.08m = 2.16
sqm.
MATERIAL Hollock wood

Styles 4x209x9.5x3cm = 0.023 cum+


Top Rail - 1x110.5x9.5x3cm = 0.003cum+
Lock and bottom rail
2x110.5x19.7x3cm = 0.013 cum+ Beadings -
(2x312+2x150)x(1.2)x (1.2)cm = 0.001 cum.
Total = 0.040 cum+
Add for wastage @ 10% = 0.004 cum.
Total = 0.44 cum.
Say 44 cudm.
1200 Kiln seasoned selected sheesum wood planks 10 4.4 650 2860.00
2204 cudm
Carriage of Timber cum 0.044 121.29 5.34
2504 Kiln seasoning of timber cum 0.044 750 33.00
Wire gauge 2x160x40cm = 1.28 sqm.+ Add
wastage @ 10% = 0.13 sqm.
Total = 1.41 sqm.
7029 Galvanised wire mesh of average width of aperture sqm 1.41 250 352.50
1.4 mm and nominal dia. of wire 0.63 mm
595 Bright finished or black enamelled mild steel butt 10 Nos 0.6 80 48.00
597 hinges 100x58x1.90 mm
Bright finished or black enamelled mild steel butt 10 Nos 0.2 49 9.8
637 hinges50x37x1.50 mm
Bright finished or black enamelled mild steel 100 0.48 60 28.8
640 screws 40 mm Nos
Bright finished or black enamelled mild 100 0.08 30 2.4
steel screws 20 mm Nos
LABOUR
14 Carpenter 1st class day 1.2 505.17 606.20
15 Carpenter 2nd class day 0.8 403.67 322.94
17 Beldar day 1 350.00 350.00
30 Mistry day 0.1 505.17 50.52
9999 Sundries L.S. 33.8 2 67.60
TOTAL 4737.10 W
Add 1 % Water charges on "W" 47.371
TOTAL 4784.47 X
Add GST (multiplying factor 0.1405) on "X" 672.22
TOTAL 5456.69 Y
Add 15 % Contractor's profit and overheads on "Y" 818.50
Total 6275.19 Z
Add Cess @ 1% on "Z" 62.75
Cost of 2.16 sqm. 6337.94
Cost of 1 sqm. 2934.23
Say 2934.20

9.27.2.2 With ISI marked stainless steel butt hinges


9.27.2.2.1 of required size teak wood
Second class
Details of cost for door shutters 2.00x1.08m = 2.16
sqm. MATERIAL Teak wood (2nd class)
Styles 4x209x9.5x3cm = 0.023 cum+
Top Rail - 1x110.5x9.5x3cm = 0.003cum+
Lock and bottom rail
2x110.5x19.7x3cm = 0.013 cum+ Beadings -
(2x312+2x150)x(1.2)x (1.2)cm = 0.001 cum.
Total = 0.040 cum+
Add for wastage @ 10% = 0.004 cum.
Total = 0.44 cum.
Say 44 cudm.
1190 Second class teak wood in planks 10 4.4 791 3480.40
2204 cudm
Carriage of Timber cum 0.044 121.29 5.34
Wire gauge 2x160x40cm = 1.28 sqm.+ Add
wastage @ 10% = 0.13 sqm.
Total = 1.41 sqm.
7029 Galvanised wire mesh of average width of aperture sqm 1.41 250 352.50
1.4 mm and nominal dia. of wire 0.63 mm
8220 Stainless steel butt hinges (heavy weight) 10 Nos 0.6 255 153.00
8218 100x60x2.5 mm IS : 12817 marked
Stainless steel butt hinges 50x37x 10 Nos 0.2 135 27
1.5 mm IS : 12817 marked
8211 Stainless steel screws 40 mm 100 0.48 215 103.20
8214 Nos
Stainless steel screws 20 mm 100 0.08 125 10
LABOUR Nos
14 Carpenter 1st class day 1.2 505.17 606.20
15 Carpenter 2nd class day 0.8 403.67 322.94
17 Beldar day 1 350.00 350.00
30 Mistry day 0.1 505.17 50.52
9999 Sundries L.S. 33.8 2 67.60
TOTAL 5528.70 W
Add 1 % Water charges on "W" 55.287
TOTAL 5583.99 X
Add GST (multiplying factor 0.1405) on "X" 784.55
TOTAL 6368.54 Y
Add 15 % Contractor's profit and overheads on "Y" 955.28
Total 7323.82 Z
Add Cess @ 1% on "Z" 73.24
Cost of 2.16 sqm. 7397.06
Cost of 1 sqm. 3424.56
Say 3424.60

9.27.2.2.2 Kiln seasoned and chemically treated


hollockofwood
Details cost for door shutters 2.00x1.08m = 2.16
sqm.
MATERIAL Hollock wood

Styles 4x209x9.5x3cm = 0.023 cum+


Top Rail - 1x110.5x9.5x3cm = 0.003cum+
Lock and bottom rail
2x110.5x19.7x3cm = 0.013 cum+ Beadings -
(2x312+2x150)x(1.2)x (1.2)cm = 0.001 cum.
Total = 0.040 cum+
Add for wastage @ 10% = 0.004 cum.
Total = 0.44 cum.
Say 44 cudm.
2505 Hollock wood in planks 10 4.4 390 1716.00
cudm 0.00
2504 Kiln seasoning of timber cum 0.044 750 33.00
9999 Chemical treatment L.S. 8.97 2 17.94
2204 Carriage of Timber cum 0.044 121.29 5.34
Wire gauge 2x160x40cm = 1.28 sqm.+ Add
wastage @ 10% = 0.13 sqm.
Total = 1.41 sqm.
7029 Galvanised wire mesh of average width of aperture sqm 1.41 250 352.50
1.4 mm and nominal dia. of wire 0.63 mm
8220 Stainless steel butt hinges (heavy weight) 10 Nos 0.6 255 153.00
8218 100x60x2.5 mm IS : 12817 marked
Stainless steel butt hinges 50x37x 10 Nos 0.2 135 27
1.5 mm IS : 12817 marked
8211 Stainless steel screws 40 mm 100 0.48 215 103.20
8214 Nos
Stainless steel screws 20 mm 100 0.08 125 10
LABOUR Nos
14 Carpenter 1st class day 1.2 505.17 606.20
15 Carpenter 2nd class day 0.8 403.67 322.94
17 Beldar day 1 350.00 350.00
30 Mistry day 0.1 505.17 50.52
9999 Sundries L.S. 33.8 2 67.60
TOTAL 3815.24 W
Add 1 % Water charges on "W" 38.1524
TOTAL 3853.39 X
Add GST (multiplying factor 0.1405) on "X" 541.40
TOTAL 4394.79 Y
Add 15 % Contractor's profit and overheads on "Y" 659.22
Total 5054.01 Z
Add Cess @ 1% on "Z" 50.54
Cost of 2.16 sqm. 5104.55
Cost of 1 sqm. 2363.22
Say 2363.20

9.27.2.2.3 Kiln seasoned selected class of sheesham


wood
Details of cost for door shutters 2.00x1.08m = 2.16
sqm.
MATERIAL
Hollock wood
Styles 4x209x9.5x3cm = 0.023 cum+
Top Rail - 1x110.5x9.5x3cm = 0.003cum+
Lock and bottom rail
2x110.5x19.7x3cm = 0.013 cum+ Beadings -
(2x312+2x150)x(1.2)x (1.2)cm = 0.001 cum.
Total = 0.040 cum+
Add for wastage @ 10% = 0.004 cum.
Total = 0.44 cum.
Say 44 cudm.
1200 Kiln seasoned selected sheesum wood planks 10 4.4 650 2860.00
2504 cudm
Kiln seasoning of timber cum 0.044 750 33
2204 Carriage of Timber cum 0.044 121.29 5.34
Wire gauge 2x160x40cm = 1.28 sqm.+ Add
wastage @ 10% = 0.13 sqm.
Total = 1.41 sqm.
7029 Galvanised wire mesh of average width of aperture sqm 1.41 250 352.50
1.4 mm and nominal dia.
of wire 0.63 mm
8220 Stainless steel butt hinges (heavy weight) 10 Nos 0.6 255 153.00
8218 100x60x2.5 mm IS : 12817 marked
Stainless steel butt hinges 50x37x 10 Nos 0.2 135 27
1.5 mm IS : 12817 marked
8211 Stainless steel screws 40 mm 100 0.48 215 103.20
8214 Nos
Stainless steel screws 20 mm 100 0.08 125 10
LABOUR Nos
14 Carpenter 1st class day 1.2 505.17 606.20
15 Carpenter 2nd class day 0.8 403.67 322.94
17 Beldar day 1 350.00 350.00
30 Mistry day 0.1 505.17 50.52
9999 Sundries L.S. 33.8 2 67.60
TOTAL 4941.30 W
Add 1 % Water charges on "W" 49.413
TOTAL 4990.71 X
Add GST (multiplying factor 0.1405) on "X" 701.20
TOTAL 5691.91 Y
Add 15 % Contractor's profit and overheads on "Y" 853.79
Total 6545.70 Z
Add Cess @ 1% on "Z" 65.46
Cost of 2.16 sqm. 6611.16
Cost of 1 sqm. 3060.72
Say 3060.70

9.31 Providing and fixing wire gauge laminated


9.31.1 veneer
35 mm lumber shutters conforming to IS :
thick shutters
14616, and as per TADS 15 :2001 (Part B)
Details of cost of one shutter 220x108cm =
using galvanised wire gauge with average
2.38sqm.
MATERIAL
7154 Factory made 35 mm thick shutters with laminated sqm 2.38 1620 3855.60
veneer lumber styles rails as per TADS IS:1995
and panels of galvanised wire gauge with average
width of aperture
1.4 mm on both directions with wire of dia 0.63 mm
9977 Carriage of shutters Fittings : L.S. 29.64 2 59.28
LABOUR
41 Carpenter (average) day 0.52 403.67 209.91
17 Beldar day 0.6 350.00 210.00
9999 Sundries L.S. 35.88 2 71.76
TOTAL 35987.91 W
Add 1 % Water charges on "W" 359.87912
TOTAL 36347.79 X
Add GST (multiplying factor 0.1405) on "X" 5106.86
TOTAL 41454.65 Y
Add 15 % Contractor's profit and overheads on "Y" 6218.20
Total 47672.85 Z
Add Cess @ 1% on "Z" 476.73
Cost of 2.38 sqm. 48149.58
Cost of 1 sqm. 22291.47
Say 22291.50

9.31.2 30 mm thick shutters


Details of cost of one shutter 220x108cm =
2.38sqm.
MATERIAL
7155 Factory made 30 mm thick shutters with laminated sqm 2.38 1430 3403.40
veneer lumber styles rails as per TADS IS:1995
and panels of galvanised wire gauge with average
width of aperture
1.4 mm on both directions with wire of dia 0.63 mm
9977 Carriage of shutters Fittings : L.S. 29.64 2 59.28
LABOUR
41 Carpenter (average) day 0.52 403.67 209.91
17 Beldar day 0.6 350.00 210.00
9999 Sundries L.S. 35.88 2 71.76
TOTAL 3954.35 W
Add 1 % Water charges on "W" 39.5435
TOTAL 3993.89 X
Add GST (multiplying factor 0.1405) on "X" 561.14
TOTAL 4555.03 Y
Add 15 % Contractor's profit and overheads on "Y" 683.26
Total 5238.29 Z
Add Cess @ 1% on "Z" 52.38
Cost of 2.38 sqm. 5290.67
Cost of 1 sqm. 2222.97
Say 2223.00

9.40 Providing and fixing wooden moulded


9.40.1 beading toteak
2nd class doorwood
and window frames with
9.40.1.1 iron screws, plugs and priming coat on
50x12 mm
unexposed surface etc. complete :
Details of cost for beading for a window of size
140x110cm i.e. 500cm long (5 metre)
MATERIAL
Teak wood IInd class in planks 500x5x1.2cm = 0.003 cum+

Add for wastage @ 10% = 0.0003 cum.


Total = 0.0033 cum. Say 3.3 cudm.
1190 Second class teak wood in planks 10 0.33 791 261.03
cudm
2204 Carriage of Timber cum 0.0033 121.29 0.4
637 Bright finished or black enamelled mild 100 0.36 60 21.60
steel screws 40 mm Nos
Painting with priming coat Area =
500(5+1.2+1.2) = 0.37 sqm
13.50.1 Rate as per item no 13.50.1 of SH : Finishing sqm 0.37 38.95 14.41 A
LABOUR
For plaining, fixing and making design
14 Carpenter 1st class day 0.53 505.17 267.74
TOTAL 565.18 W
Add 1 % Water charges on "W-A" 550.77 5.5077
TOTAL X
Add GST (multiplying factor 0.1405) on "X-A" 556.28 78.16
TOTAL Y
Add 15 % Contractor's profit and overheads on "Y- 634.44 95.17
A"
Total
Add Cess @ 1% on "Z-A" 729.61 7.30 Z
Cost of 5 m. 751.32
Cost of 1 metre 150.26
Say 150.30

9.40.1.2 50 x 20 mm
Details of cost for beading of a window of size
140x110cm i.e. 500cm. long (5metre)
MATERIAL
Teak wood IInd class in planks 500x5x2.0cm = 0.005cum+

Add for wastage @ 10% = 0.0005 cum.


Total = 0.0055 cum. Say 5.5 cudm.
1190 Second class teak wood in planks 10 0.55 791 435.05
2204 cudm
Carriage of Timber cum 0.0055 121.29 0.67
637 Bright finished or black enamelled mild 100 0.36 60 21.60
steel screws 40 mm Nos
Painting with priming coat Area
= 500(5+2+2) = 0.45 sqm
13.50.1 Rate as per item no 13.50.1 of sqm 0.45 38.95 17.53 A
SH : Finishing
LABOUR
For plaining, fixing and making design
14 Carpenter 1st class day 0.53 505.17 267.74
TOTAL 742.59 W
Add 1 % Water charges on "W-A" 742.59 7.4259
TOTAL X
Add GST (multiplying factor 0.1405) on "X-A" 750.02 105.38
TOTAL Y
Add 15 % Contractor's profit and overheads on "Y- 855.40 128.31
A"
Total 983.71 9.84 Z
Add Cess @ 1% on "Z-A" 993.55
Cost of 5 m. 198.71
Cost of 1 metre 198.70
Say

9.40.2 Kiln seasoned and chemically treated


9.40.2.1 hollock
50x12 mmwood
Details of cost for beading for a window of size
140x110cm i.e. 500cm long (5 metre)
MATERIAL
Hollock wood
500x5x1.2cm = 0.003 cum+
Add for wastage @ 10% = 0.0003 cum.
Total = 0.0033 cum. Say 3.3 cudm.
2505 Hollock wood in planks 10 0.33 390 128.70
2204 cudm
Carriage of Timber cum 0.0033 121.29 0.4
637 Bright finished or black enamelled mild 100 0.36 60 21.60
steel screws 40 mm Nos
Painting with priming coat Area
= 500(5+1.2+1.2) = 0.37 sqm
13.50.1 Rate as per item no 13.50.1 of sqm 0.37 38.95 14.41 A
SH : Finishing
LABOUR
For plaining, fixing and making design
14 Carpenter 1st class day 0.53 505.17 267.74
TOTAL 432.85 W
Add 1 % Water charges on "W-A" 418.44 4.1844
TOTAL X
Add GST (multiplying factor 0.1405) on "X-A" 422.62 59.38
TOTAL Y
Add 15 % Contractor's profit and overheads on "Y- 482.00 72.30
A"
Total 554.30 5.54 Z
Add Cess @ 1% on "Z-A" 574.25
Cost of 5 m. 114.85
Cost of 1 metre 114.90
Say

9.40.2.2 50x20 mm

Details of cost for beading for a window of size


140x110cm i.e. 500cm long (5 metre)
MATERIAL
Hollock wood
500x50x200mm = 0.005 cum
Add for wastage @ 10% = 0.0005 cum.
Total = 0.0055 cum. Say 5.5 cudm.
2505 Hollock wood in planks 10 0.55 390 214.50
2204 cudm
Carriage of Timber cum 0.0055 121.29 0.67
637 Bright finished or black enamelled mild 100 0.36 60 21.60
steel screws 40 mm Nos
Painting with priming coat Area
= 500(5+2+2) = 0.45 sqm
13.50.1 Rate as per item no 13.50.1 of SH : Finishing sqm 0.45 38.95 17.53 A
LABOUR
For plaining, fixing and making design
14 Carpenter 1st class day 0.53 505.17 267.74
TOTAL 522.04
Add 1 % Water charges on "W-A" 482.91 4.8291
TOTAL X
Add GST (multiplying factor 0.1405) on "X-A" 487.74 68.53
TOTAL Y
Add 15 % Contractor's profit and overheads on "Y- 556.27 83.44
A"
Total 639.71 6.40 Z
Add Cess @ 1% on "Z-A" 685.24
Cost of 5 m. 137.05
Cost of 1 metre 137.10
Say

9.41 Providing and fixing wooden moulded


9.41.1 beading
Secondtoclass
doorteakand wood
window frames with
iron screws, plugs and priming coat on
Details of cost of a jaffri 200x110cm = 2.2sqm.
unexposed surface etc. complete :
MATERIAL
Teakwood IInd class
Jaffri 210x120x1.0cm = 0.025cum.+ Beading
660x5x1.2cm = 0.004cum.
Total = 0.029 cum.+
Add wastage @ 10% = 0.003 cum.
Total = 0.032 cum. Say 32 cudm.
1190 Second class teak wood in planks 10 3.2 791 2531.20
2204 cudm 0.00
Carriage of Timber cum 0.032 121.29 3.88
LABOUR 0.00
14 Carpenter 1st class day 0.75 505.17 378.88
15 Carpenter 2nd class day 1 403.67 403.67
17 Beldar day 0.5 350.00 175.00
30 Mistry day 0.1 505.17 50.52
9999 Sundries L.S. 33.8 2 67.60
TOTAL 3610.75 W
Add 1 % Water charges on "W" 36.1075
TOTAL 3646.86 X
Add GST (multiplying factor 0.1405) on "X" 512.38
TOTAL 4159.24 Y
Add 15 % Contractor's profit and overheads on "Y" 623.89
Total 4783.13 Z
Add Cess @ 1% on "Z" 47.83
Cost of 2.2 sqm. 4830.96
Cost of 1 sqm. 2195.89
Say 2195.90

9.42 Providing and fixing 18 mm thick, 150 mm


wide pelmet of flat pressed 3 layer or
graded wood particle board medium
density grade I, IS : 3087 marked,
including top cover of 6 mm commercial
ply wood conforming to IS: 303 BWR
grade, nickel plated M.S. pipe 20 mm dia
( heavy type) curtain rod with nickel plated
brackets, including fixing with 25x3 mm
M.S. flat 10 cm long fixed to pelmet with
hollock wood cleats of size 100 mm x 40
Details of cost for a pelmet 2m long
MATERIAL
(i) 18mm thick particle board (medium
density exterior grade)
Front-1x1.7x0.15= 0.255sqm.+ Sides-
2x0.15x0.15= 0.045sqm.
Total = 0.300sqm.+
Add wastage @5% = 0.015sqm.
Total = 0.315sqm. Say 0.32 sqm.

7055 Flat pressed 3 layer and graded particle board sqm 0.32 480 153.60
(medium density) Grade 1 conforming to IS : 3087 - 0.00
18 mm thick 6mm thick commercial ply wood Top- 0.00
1x1.7x0.15= 0.255sqm.+ 0.00
Add wastage @ 5% = 0.013 sqm. 0.00
= 0.268 sqm. Say 0.27 sqm. 0.00
2412 Ply wood 5 ply with commercial ply on both faces 6 sqm 0.27 300 81.00
mm thick 0.00
7034 Nickle plated M.S. pipe 20 mm dia. metre 1.65 72 118.80
7035 Nickle plated M.S. Brackets for curtain rod 20 mm each 2 7 14.00
9977 Carriage of material L.S. 0.52 2 1.04
9999 M.S. flat 25x3mm and 10cm long over brackets L.S. 8.06 2 16.12
2505 Hollock wood in planks 10 0.032 390 12.48
7048 cudm 0.00
Rawl plug 50 mm (designation 10 no.) each 2 25 50.00
LABOUR 0.00
15 Carpenter 2nd class day 0.18 403.67 72.66
17 Beldar day 0.18 350.00 63.00
30 Mistry day 0.11 505.17 55.57
9999 Sundries L.S. 2.73 2 5.46
TOTAL 643.73 W
Add 1 % Water charges on "W" 6.4373
TOTAL 650.17 X
Add GST (multiplying factor 0.1405) on "X" 91.35
TOTAL 741.52 Y
Add 15 % Contractor's profit and overheads on "Y" 111.23
Total 852.75 Z
Add Cess @ 1% on "Z" 8.53
Cost of 2 m 861.28
Cost of 1 metre 430.64
Say 430.60

9.43 Providing and fixing 18 mm thick, 150 mm


wide pelmet
rawl plugs 75ofmmcoirlong
veneer
etc. board ISI
all complete.
marked IS : 14842, including
Details of cost for a pelmet 2m long
top cover of 6
mm coir veneer board, nickle plated M.S.
MATERIAL
(i) 18mm thick Coir veneered board
Front-1x1.7x0.15= 0.255sqm.+ Sides-
2x0.15x0.15= 0.045sqm.
Total = 0.300sqm.+
Add wastage @5% = 0.015sqm.
Total = 0.315sqm. Say 0.32 sqm.
7556 Coir veneered board 18mm thick sqm 0.32 1000 320.00
6mm thick commercial ply wood Top-1x1.7x0.15=
0.255sqm.+
Add wastage @ 5% = 0.013 sqm.
Total = 0.268 sqm. Say 0.27 sqm.
7553 Coir veneered board 6mm thick sqm 0.27 385 103.95
7034 Nickle plated M.S. pipe 20 mm dia. metre 1.65 72 118.80
7035 Nickle plated M.S. Brackets for curtain rod 20 mm each 2 7 14.00
9977 Carriage of material L.S. 0.52 2 1.04
9999 M.S. flat 25x3mm and 10cm long over brackets L.S. 8.06 2 16.12
2505 Hollock wood in planks 10 0.032 390 12.48
7048 cudm 0.00
Rawl plug 50 mm (designation 10 no.) each 2 25 50.00
LABOUR
15 Carpenter 2nd class day 0.18 403.67 72.66
17 Beldar day 0.18 350.00 63.00
30 Mistry day 0.11 505.17 55.57
9999 Sundries L.S. 2.73 2 5.46
TOTAL 833.08 W
Add 1 % Water charges on "W" 8.3308
TOTAL 841.41 X
Add GST (multiplying factor 0.1405) on "X" 118.22
TOTAL 959.63 Y
Add 15 % Contractor's profit and overheads on "Y" 143.94
Total 1103.57 Z
Add Cess @ 1% on "Z" 11.04
Cost of 2 m 1114.61
Cost of 1 metre 557.31
Say 557.30

9.44 Extra for using veneered particle board


conforming to IS thick
of pelmet 18mm 3097150mm
Grade I,wide.
in item
9.44.1 Non decorative veneer on both sides
Details of cost for a pelmet 2m long
MATERIAL
(i) 18mm thick particle board (medium density
exterior grade)
Front-1x1.7x0.15= 0.255sqm.+ Sides-
2x0.15x0.15= 0.045sqm. Total = 0.300sqm.+
Add wastage @5% = 0.015sqm.
Total = 0.315sqm. Say 0.32 sqm.
347 Extra for veneered particle board with : sqm 0.32 155 49.60
Commercial veneering on both sides
TOTAL 49.60 W
Add 1 % Water charges on "W" 0.496
TOTAL 50.10 X
Add GST (multiplying factor 0.1405) on "X" 7.04
TOTAL 57.14 Y
Add 15 % Contractor's profit and overheads on "Y" 8.57
Total 65.71 Z
Add Cess @ 1% on "Z" 0.66
Cost of 2 m 66.37
Cost of 1 metre 33.18
Say 33.20

9.44.2 Particle board with decorative veneering


on both
Details of sides
cost for a pelmet 2m long
MATERIAL
(i) 18mm thick particle board (medium
density exterior grade)
Front-1x1.7x0.15= 0.255sqm.+ Sides-
2x0.15x0.15= 0.045sqm.
Total = 0.300sqm.+
Add wastage @5% = 0.015sqm.
Total = 0.315sqm. Say 0.32 sqm.
348 Extra for veneered particle board with : Teak sqm 0.32 500 160.00
veneering on both sides
TOTAL 160.00 W
Add 1 % Water charges on "W" 1.6
TOTAL 161.60 X
Add GST (multiplying factor 0.1405) on "X" 22.70
TOTAL 184.30 Y
Add 15 % Contractor's profit and overheads on "Y" 27.65
Total 211.95 Z
Add Cess @ 1% on "Z" 2.12
Cost of 2m 214.07
Cost of 1 metre 107.04
Say 107.00

9.45 Providing and fixing teak wood lipping of


size 25x3 mm in pelmet.
Details of cost for 10 metre
MATERIAL
7349 Teak wood lipping of size 25x3 mm in pelmets metre 10 14 140.00
LABOUR
15 Carpenter 2nd class day 0.25 403.67 100.92
17 Beldar day 0.25 350.00 87.50
TOTAL 328.42 W
Add 1 % Water charges on "W" 3.2842
TOTAL 331.70 X
Add GST (multiplying factor 0.1405) on "X" 46.60
TOTAL 378.30 Y
Add 15 % Contractor's profit and overheads on "Y" 56.75
Total 435.05 Z
Add Cess @ 1% on "Z" 4.35
Cost for 10 meter 439.40
Cost of 1 metre 43.94
Say 43.90

9.46 Providing and fixing curtain rods of 1.25


9.46.1 mm 12thick
mm chromium
dia plated brass plate,
with two chromium plated brass brackets
Details of cost
fixed with for 2m
C.P. longscrews and wooden
brass
MATERIAL
590 Chromium plated Brass curtain rod 12 mm dia metre 2 185 370.00
1.25mm thick 0.00
7023 Chromium plated brackets ( curtain rods) each 2 7 14.00
9999 C.P. brass screws L.S. 4.03 2 8.06
9999 CARRIAGE L.S. 1.56 2 3.12
Wooden plugs including cutting brick work and 0.00
fixing in cement mortar 1:3 (1 cement : 0.00
3 fine sand) 0.00
458 PVC cleeves for screws each 2 2 4.00
9999 LABOUR L.S. 2.73 2 5.46
9999 Sundries L.S. 1.56 2 3.12
TOTAL 407.76 W
Add 1 % Water charges on "W" 4.0776
TOTAL 411.84 X
Add GST (multiplying factor 0.1405) on "X" 57.86
TOTAL 469.70 Y
Add 15 % Contractor's profit and overheads on "Y" 70.45
Total 540.15 Z
Add Cess @ 1% on "Z" 5.40
Cost of 2m 545.55
Cost of 1 metre 272.77
Say 272.80

9.46.2 20 mm dia

Details of cost for 2m long


MATERIAL
591 Chromium plated Brass curtain rod 20 mm dia metre 2 260 520.00
1.25mm thick 0.00
7023 Chromium plated brackets ( curtain rods) each 2 7 14.00
9999 C.P. brass screws L.S. 4.03 2 8.06
9999 CARRIAGE L.S. 1.56 2 3.12
Wooden plugs including cutting brick work and
fixing in cement mortar 1:3 (1 cement :
3 fine sand)
458 PVC cleeves for screws each 2 2 4.00
9999 LABOUR L.S. 2.73 2 5.46
9999 Sundries L.S. 1.56 2 3.12
TOTAL 557.76 W
Add 1 % Water charges on "W" 5.5776
TOTAL 563.34 X
Add GST (multiplying factor 0.1405) on "X" 79.15
TOTAL 642.49 Y
Add 15 % Contractor's profit and overheads on "Y" 96.37
Total 738.86 Z
Add Cess @ 1% on "Z" 7.39
Cost of 2m 746.25
Cost of 1 metre 373.12
Say 373.10

9.46.3 25 mm dia
Details of cost for 2m long
MATERIAL
592 Chromium plated Brass curtain rod 25 mm dia metre 2 340 680.00
1.25mm thick 0.00
7023 Chromium plated brackets ( curtain rods) each 2 7 14.00
9999 C.P. brass screws L.S. 4.03 2 8.06
9999 CARRIAGE L.S. 1.56 2 3.12
Wooden plugs including cutting brick work and 0.00
fixing in cement mortar 1:3 (1 cement : 0.00
3 fine sand) 0.00
458 PVC cleeves for screws each 2 2 4.00
9999 LABOUR L.S. 2.73 2 5.46
9999 Sundries L.S. 1.56 2 3.12
TOTAL 717.76 W
Add 1 % Water charges on "W" 7.1776
TOTAL 724.94 X
Add GST (multiplying factor 0.1405) on "X" 101.85
TOTAL 826.79 Y
Add 15 % Contractor's profit and overheads on "Y" 124.02
Total 950.81 Z
Add Cess @ 1% on "Z" 9.51
Cost of 2m 960.32
Cost of 1 metre 480.16
Say 480.20

9.47 Providing and fixing nickel plated M.S.


9.47.1 pipe
20 curtain
mm diarods withtype)
(heavy nickel plated
brackets :
Details of cost for 2m long
MATERIAL
7034 Nickle plated M.S. pipe 20 mm dia. metre 2 72 144.00
7035 Nickle plated M.S. Brackets for curtain each 2 7 14.00
9999 rod 20 mm 0.00
Screws L.S. 4.03 2 8.06
9999 CARRIAGE L.S. 1.56 2 3.12
7048 Rawl plug 50 mm (designation 10 no.) each 2 25 50.00
9999 Labour including fixing rawl plug L.S. 5.2 2 10.40
9999 Sundries L.S. 1.56 2 3.12
TOTAL 232.70 W
Add 1 % Water charges on "W" 2.327
TOTAL 235.03 X
Add GST (multiplying factor 0.1405) on "X" 33.02
TOTAL 268.05 Y
Add 15 % Contractor's profit and overheads on "Y" 40.21
Total 308.26 Z
Add Cess @ 1% on "Z" 3.08
Cost for 2 meter 311.34
Cost of 1 metre 155.67
Say 155.70

9.47.2 25 mm dia (heavy type)

Details of cost for 2m long


MATERIAL
7033 Nickel plated M.S. pipe 25mm dia metre 2 76 152.00
7036 Nickle plated M.S. Brackets for curtain rod 25 mm each 2 8 16.00
9999 Screws L.S. 4.03 2 8.06
9999 CARRIAGE L.S. 1.56 2 3.12
7048 Rawl plug 50 mm (designation 10 no.) each 2 25 50.00
9999 Labour including fixing rawl plug L.S. 5.2 2 10.40
9999 Sundries L.S. 1.56 2 3.12
TOTAL 242.70 W
Add 1 % Water charges on "W" 2.427
TOTAL 245.13 X
Add GST (multiplying factor 0.1405) on "X" 34.44
TOTAL 279.57 Y
Add 15 % Contractor's profit and overheads on "Y" 41.94
Total 321.51 Z
Add Cess @ 1% on "Z" 3.22
Cost for 2 meter 324.73
Cost of 1 metre 162.36
Say 162.40

9.48 Providing and fixing nickel plated M.S.


pipe curtain
brackets : rods with nickel plated
9.48.1 Fixed to steel windows by welding
Details of cost for a grill 90x120cm = 1.08sqm.
MATERIAL
M.S. bar 16mm dia. metre- 11x86cm = 9.46m. @
1.58kg/m = 14.95kg+
Add wastage @ 10% = 1.50kg.
Total = 16.45kg. Say 0.165q
1003 Mild steel round bar above 12 mm dia quintal 0.165 5500 907.50
M.S. flat 25x3.15mm 2x120cm = 2.40m+
2x90cm = 1.80m+
1x120cm = 1.20m+
2x15cm = 0.30m
Total =5.70m
5.70m @ 0.63kg/m = 3.59kg+ Add wastage @
10% = 0.36kg.
Total = 3.95kg. Say 4 kg. or 0.04q
1008 Flats upto 10 mm in thickness quintal 0.04 5300 212.00
2205 Carriage of Steel tonne 0.02 94.34 1.89
0.165 + 0.04 = 0.205 q = 0.0205 t
Say 0.02 tonne
9999 Sundries L.S. 26.91 2 53.82
9999 Welding charges Priming coat: L.S. 19.76 2 39.52
Area=1x0.9x1.2x1=1.08 sqm
13.50.3 Rate as per Item No.13.50.3 of SH: Finishing sqm 1.08 33.3 35.96 A
LABOUR
12 Blacksmith 1st class day 0.86 505.17 434.45
17 Beldar day 1.1 350.00 385.00
TOTAL 2070.14 W
Add 1 % Water charges on "W-A" 2034.18 20.3418
TOTAL X
Add GST (multiplying factor 0.1405) on "X-A" 2054.52 288.66
TOTAL Y
Add 15 % Contractor's profit and overheads on "Y- 2343.18 351.48
A"
Total Z
Add Cess @ 1% on "Z-A" 2694.66 26.95
Cost for 18.54 kg. 2757.57
Cost for 1 kg. 148.74
Say 148.70

9.48.2 Fixed to openings /wooden frames with


rawl
Detailsplugs
of costscrews
for a grilletc.
90x120cm = 1.08sqm.
MATERIAL
M.S. bar 16mm dia. metre- 11x86cm = 9.46m.
@ 1.58kg/m = 14.95kg+
Add wastage @ 10% = 1.50kg.
Total = 16.45kg. Say 0.165q
1003 Mild steel round bar above 12 mm dia quintal 0.165 5500 907.50
M.S. flat 25x3.15mm 2x120cm = 2.40m+
2x90cm = 1.80m+
1x120cm = 1.20m+
2x15cm = 0.30m
Total =5.70m
5.70m @ 0.63kg/m = 3.59kg+ Add wastage @
10% = 0.36kg.
Total = 3.95kg. Say 4 kg. or 0.04q
1008 Flats upto 10 mm in thickness quintal 0.04 5300 212.00
2205 Carriage of Steel tonne 0.02 94.34 1.89
0.165 + 0.04 = 0.205 q = 0.0205 t 0.00
Say 0.02 tonne 0.00
9999 Sundries L.S. 26.91 2 53.82
9999 Welding charges Priming coat: L.S. 19.76 2 39.52
Area=1x0.9x1.2x1=1.08 sqm 0.00
13.50.3 Rate as per Item No.13.50.3 of sqm 1.08 33.3 35.96 A
SH:Finishing 0.00
LABOUR 0.00
12 Blacksmith 1st class day 0.86 505.17 434.45
17 Beldar day 1.1 350.00 385.00
7048 Rawl plug 50 mm (designation 10 no.) each 8 25 200.00
9999 Fixing of rawl plugs L.S. 26 2 52.00
TOTAL 2322.14 W
Add 1 % Water charges on "W-A" 2286.18 22.8618
TOTAL X
Add GST (multiplying factor 0.1405) on "X-A" 2309.04 324.42
TOTAL Y
Add 15 % Contractor's profit and overheads on "Y- 2633.46 395.02
A"
Total Z
Add Cess @ 1% on "Z-A" 3028.48 30.28
Cost for 18.54 kg. 3094.72
Cost for 1 kg. 166.92
Say 166.90

9.49 Providing and fixing expanded metal


20x60
wood and mmpriming
strandscoat
3.25with
mmapproved
wide and steel
1.6
mm thick
primer
Details ofall
for windows
complete.
cost
etc. including 62
for a window of size 140x110cm
x19
mm beading of II nd class teak
=1.54sqm.
MATERIAL
Expended metal -20x60mm mesh 3.2mm
wide = 1.4x1.1m = 1.54sqm.+ Add wastage @ 10%
= 0.15sqm.
Total = 1.69 sqm.
1015 Mild steel expanded metal 20x60 mm strands sqm 1.69 280 473.20
9977 Carriage L.S. 1.82 2 3.64
Priming coat
Area=1.40x1.10x1.00=1.54sqm
13.50.3 Rate as per Item No.13.50.3 of sqm 1.54 33.3 51.28 A
SH: FINISHING
Second class teak wood beading
5mx62mmx19mm = 0.0059cum.
Add wastage @ 10% = 0.00059cum.
Total = 0.00649cum. Say 6 cudm.
1190 Second class teak wood in planks 10 0.6 791 474.60
2204 cudm 0.00
Carriage of Timber cum 0.006 121.29 0.73
LABOUR 0.00
15 Carpenter 2nd class day 0.33 403.67 133.21
17 Beldar day 0.25 350.00 87.50
9999 Sundries L.S. 26.91 2 53.82
TOTAL 1277.98 W
Add 1 % Water charges on "W-A" 1226.70 12.267
TOTAL X
Add GST (multiplying factor 0.1405) on "X-A" 1238.97 174.07
TOTAL Y
Add 15 % Contractor's profit and overheads on "Y- 1413.04 211.96
A"
Total Z
Add Cess @ 1% on "Z-A" 1625.00 16.25
Cost of 1.54 sqm. 1692.53
Cost of 1 sqm. 1099.04
Say 1099.00
9.50 Providing and fixing hard drawn steel
wire
primerfabric 75x25 mm mesh of weight not
all complete.
less than 7.75 Kg per sqm to window
Details of cost for a window of size 140x110cm
frames etc. including 62x19 mm beading of
=1.54sqm.
MATERIAL
Hard drawn steel wire fabric -20x60mm mesh
3.2mm wide = 1.4x1.1m = 1.54sqm.+ Add wastage
@ 10% = 0.15sqm. Total = 1.69 sqm.
1021 Hard drawn steel wire fabric sqm 1.69 430 726.70
9977 Carriage of wire fabric L.S. 1.82 2 3.64
Priming coat 0.00
Area=1.40x1.10x1.00=1.54sqm 0.00
13.50.3 Rate as per Item No.13.50.3 of sqm 1.54 33.3 51.28 A
SH:FINISHING 0.00
Second class teak wood beading 0.00
5mx62mmx19mm = 0.0059cum. 0.00
Add wastage @ 10% = 0.00059cum. 0.00
Total = 0.00649cum. Say 6 cudm. 0.00
1190 Second class teak wood in planks 10 0.6 791 474.60
2204 cudm 0.00
Carriage of Timber cum 0.006 121.29 0.73
LABOUR 0.00
15 Carpenter 2nd class day 0.33 403.67 133.21
17 Beldar day 0.25 350.00 87.50
9999 Sundries L.S. 19.76 2 39.52
TOTAL 1517.18 W
Add 1 % Water charges on "W-A" 1465.90 14.659
TOTAL X
Add GST (multiplying factor 0.1405) on "X-A" 1480.56 208.02
TOTAL Y
Add 15 % Contractor's profit and overheads on "Y- 1688.58 253.29
A"
Total Z
Add Cess @ 1% on "Z-A" 1941.87 19.42
Cost of 1.54 sqm. 2012.57
Cost of 1 sqm. 1306.86
Say 1306.90

9.51 Providing and fixing fly proof galvanized


M.S. wire gauge
clerestory windows to windows
using wireandgauge with
average
both directions with wire of dia 0.63inmm all
width of aperture 1.4 mm
complete.
9.51.1 With 2nd class teak wood
beading
Details of cost for amm
62X19 window of size 140x110cm
=1.54sqm.
MATERIAL
Wire gauze -20x60mm mesh 3.2mm wide =
1.4x1.1m = 1.54sqm.+ Add wastage @ 10% =
0.15sqm.
Total = 1.69 sqm.
7029 Galvanised wire mesh of average width of aperture sqm 1.69 250 422.50
1.4 mm and nominal dia.
of wire 0.63 mm
9977 Carriage of wire fabric L.S. 1.82 2 3.64
Second class teak wood beading
5mx62mmx19mm = 0.0059cum.
Add wastage @ 10% = 0.00059cum.
Total = 0.00649cum. Say 6 cudm.
1190 Second class teak wood in planks 10 0.6 791 474.60
2204 cudm
Carriage of Timber cum 0.006 121.29 0.73
LABOUR
15 Carpenter 2nd class day 0.33 403.67 133.21
17 Beldar day 0.25 350.00 87.50
9999 Sundries L.S. 19.76 2 39.52
TOTAL 1161.70 W
Add 1 % Water charges on "W" 11.617
TOTAL 1173.32 X
Add GST (multiplying factor 0.1405) on "X" 164.85
TOTAL 1338.17 Y
Add 15 % Contractor's profit and overheads on "Y" 200.73
Total 1538.90 Z
Add Cess @ 1% on "Z" 15.39
Cost of 1.54 sqm. 1554.29
Cost of 1 sqm. 1009.28
Say 1009.30

9.51.2 With 12 mm mild steel U beading


Details of cost for a window of size 140x110cm
=1.54sqm.
MATERIAL
Wire gauze -20x60mm mesh 3.2mm wide =
1.4x1.1m = 1.54sqm.+ Add wastage @ 10% =
0.15sqm.
Total = 1.69 sqm.
7029 Galvanised wire mesh of average width of aperture sqm 1.69 250 422.50
1.4 mm and nominal dia. of wire 0.63 mm
9977 Carriage of wire fabric L.S. 1.82 2 3.64
7349 12 mm M.S. 'U' beading metre 5 14 70.00
LABOUR
15 Carpenter 2nd class day 0.33 403.67 133.21
17 Beldar day 0.25 350.00 87.50
9999 Sundries L.S. 19.76 2 39.52
TOTAL 756.37 W
Add 1 % Water charges on "W" 7.5637
TOTAL 763.93 X
Add GST (multiplying factor 0.1405) on "X" 107.33
TOTAL 871.26 Y
Add 15 % Contractor's profit and overheads on "Y" 130.69
Total 1001.95 Z
Add Cess @ 1% on "Z" 10.02
Cost of 1.54 sqm. 1011.97
Cost of 1 sqm. 657.13
Say 657.10

9.52 Deduct for fixing 75x25 mm hard drawn


steel wiresheet
of glass fabric4 of
mm weight
thick.not less than
7.75 Kg per sqm in
Details of cost for 1 sqm.
panelled and glazed
door and window shutter instead
MATERIAL
1021 Hard drawn steel wire fabric sqm 1 430 430.00
2406 Float glass sheet of nominal thickness sqm -1 300 -300.00
4 mm (weight not less than 10kg/sqm).
Difference of cost 130.00 W
Add 1 % Water charges on "W" 1.3
TOTAL 131.30 X
Add GST (multiplying factor 0.1405) on "X" 18.45
TOTAL 149.75 Y
Add 15 % Contractor's profit and overheads on "Y" 22.46
Total 172.21 Z
Add Cess @ 1% on "Z" 1.72
Extra cost for 1 sqm. 173.93
Say 173.93
173.90
9.53 Providing 40x5 mm flat iron hold fast
40 cm long including
stone aggregate 20mm fixing to frame
nominal with 10
size).
mm diameter bolts, nuts and wooden plugs
Details of cost for 1 hold fast
and embedding in cement concrete block
MATERIAL
M.S.flat 40x5mm 40cm long @
1.68 kg/m = 0.672 kg = 0.0067 qunital
1008 Flats upto 10 mm in thickness quintal 0.0067 5300 35.51
9977 Carriage of steel L.S. 1.82 2 3.64
Cement concrete 1:3:6
30x10x15cm= 0.0045cum.+
Add wastage @ 10% = 0.00045cum.
Total = 0.00495cum. Say 0.005cum.
4.2.5 Rate as per item no 4.2.5 of SH : Concrete work cum 0.005 6577.55 32.89 A
9999 Bolts and nuts L.S. 5.46 2 10.92
LABOUR
13 Blacksmith 2nd class day 0.03 403.67 12.11
23 Mason (brick layer) 1st class day 0.03 505.17 15.16
17 Beldar day 0.03 350.00 10.50
TOTAL 120.73 W
Add 1 % Water charges on "W-A" 87.84 0.8784
TOTAL X
Add GST (multiplying factor 0.1405) on "X-A" 88.72 12.46
TOTAL Y
Add 15 % Contractor's profit and overheads on "Y- 101.18 15.18
A"
Total Z
Add Cess @ 1% on "Z-A" 116.36 1.16
Cost for 1 no 150.41
Say 150.41
150.40
9.54 Providing beams including hoisting, fixing
9.54.1 in position
Sal wood and applying wood preservative
for the unexposed surfaces, etc. complete
Details
with : of cost for a beam
450x30x15cm = 0.203cum. or 203cudm.
MATERIAL
Sal wood = 203 cudm.+
Add wastage @ 2% = 4.06cudm.
Total = 207.06cudm. Say 207.1 cudm.
1199 Sal wood in scantling 10 20.71 600 12426.00
2204 cudm
Carriage of Timber cum 0.2071 121.29 25.12
Priming coat (wood preservative)
13.57.1 Rate as per item no 13.57.1 SH : Finishing sqm 0.54 33.65 18.17 A
LABOUR
15 Carpenter 2nd class day 0.7 403.67 282.57
17 Beldar day 1.45 350.00 507.50
10 Bandhani day 0.7 350.00 245.00
9999 Sundries L.S. 26.91 2 53.82
TOTAL 13558.18 W
Add 1 % Water charges on "W-A" 13540.01 135.4001
TOTAL X
Add GST (multiplying factor 0.1405) on "X-A" 13675.41 1921.40
TOTAL Y
Add 15 % Contractor's profit and overheads on "Y- 15596.81 2339.52
A"
Total Z
Add Cess @ 1% on "Z-A" 17936.33 179.36
Cost for 203 cudm. 18133.86
Cost of 1 cum. 89329.36
Say 89329.40

9.54.2 Hollock wood


Details of cost for a beam 450x30x15cm =
0.203cum. or 203cudm.
MATERIAL
Hollock wood = 203 cudm.+
Add wastage @ 2% = 4.06cudm.
Total = 207.06cudm. Say 207.1 cudm.
2466 Hollock wood in scantling 10 20.71 350 7248.50
2204 cudm
Carriage of Timber cum 0.207 121.29 25.11
Priming coat (wood preservative)
13.57.1 Rate as per item no 13.57.1 SH : Finishing sqm 0.54 33.65 18.17 A
LABOUR
15 Carpenter 2nd class day 0.7 403.67 282.57
17 Beldar day 1.45 350.00 507.50
10 Bandhani day 0.7 350.00 245.00
9999 Sundries L.S. 26.91 2 53.82
TOTAL 8380.67 W
Add 1 % Water charges on "W-A" 8362.50 83.625
TOTAL X
Add GST (multiplying factor 0.1405) on "X-A" 8446.13 1186.68
TOTAL Y
Add 15 % Contractor's profit and overheads on "Y- 9632.81 1444.92
A" Z
Total 11077.73 110.78
Add Cess @ 1% on "Z-A" 11206.68
Cost for 203 cudm. 55205.3
Cost of 1 cum. 55205.30
Say

9.55 Providing and fixing ISI marked M.S.


pressed
necessarybutt hingesetc.
screws bright finished
complete : with
9.55.1 125x65x2.12 mm
Details of cost for ten hinges
MATERIAL
594 Bright finished or black enamelled mild steel butt 10 Nos 1 135 135.00
635 hinges 125x65x2.12 mm
Bright finished or black enamelled mild steel 100 0.8 75 60
9977 screws 50 mm Nos
Carriage of materials L.S. 2.73 2 5.46
LABOUR
15 Carpenter 2nd class day 0.14 403.67 56.51
17 Beldar day 0.09 350.00 31.50
TOTAL 288.47 W
Add 1 % Water charges on "W" 2.8847
TOTAL 291.35 X
Add GST (multiplying factor 0.1405) on "X" 40.94
TOTAL 332.29 Y
Add 15 % Contractor's profit and overheads on "Y" 49.84
Total 382.13 Z
Add Cess @ 1% on "Z" 3.82
Cost of 10 nos. 385.95
Cost of 1 no 38.6
Say 38.60

9.55.2 100x58x1.90 mm
Details of cost for ten hinges
MATERIAL
595 Bright finished or black enamelled mild steel butt 10 Nos 1 80 80.00
637 hinges 100x58x1.90 mm 0.00
Bright finished or black enamelled mild steel 100 0.8 60 48
9977 screws 40 mm Nos
Carriage of materials L.S. 2.73 2 5.46
LABOUR
15 Carpenter 2nd class day 0.14 403.67 56.51
17 Beldar day 0.09 350.00 31.50
TOTAL 221.47 W
Add 1 % Water charges on "W" 2.2147
TOTAL 223.68 X
Add GST (multiplying factor 0.1405) on "X" 31.43
TOTAL 255.11 Y
Add 15 % Contractor's profit and overheads on "Y" 38.27
Total 293.38 Z
Add Cess @ 1% on "Z" 2.93
Cost of 10 nos. 296.31
Cost of 1 no 29.63
Say 29.60
9.55.3 75x47x1.70 mm
Details of cost for ten hinges
MATERIAL
596 Bright finished or black enamelled mild steel butt 10 Nos 1 56 56.00
638 hinges75x47x1.70 mm 0.00
Bright finished or black enamelled mild steel 100 0.6 45 27.00
9977 screws 30 mm Nos 0.00
Carriage of materials L.S. 1.82 2 3.64
LABOUR 0.00
15 Carpenter 2nd class day 0.14 403.67 56.51
17 Beldar day 0.09 350.00 31.50
TOTAL 174.65 W
Add 1 % Water charges on "W" 1.7465
TOTAL 176.40 X
Add GST (multiplying factor 0.1405) on "X" 24.78
TOTAL 201.18 Y
Add 15 % Contractor's profit and overheads on "Y" 30.18
Total 231.36 Z
Add Cess @ 1% on "Z" 2.31
Cost of 10 nos. 233.67
Cost of 1 no 23.37
Say 23.40

9.55.4 50x37x1.50 mm
Details of cost for ten hinges
MATERIAL
597 Bright finished or black enamelled mild steel butt 10 Nos 1 49 49.00
640 hinges50x37x1.50 mm
Bright finished or black enamelled mild steel 100 0.4 30 12
9977 screws 20 mm Nos
Carriage of materials L.S. 0.91 2 1.82
LABOUR
15 Carpenter 2nd class day 0.08 403.67 32.29
TOTAL 95.11 W
Add 1 % Water charges on "W" 0.9511
TOTAL 96.06 X
Add GST (multiplying factor 0.1405) on "X" 13.50
TOTAL 109.56 Y
Add 15 % Contractor's profit and overheads on "Y" 16.43
Total 125.99 Z
Add Cess @ 1% on "Z" 1.26
Cost of 10 nos. 127.25
Cost of 1 no 12.73
Say 12.70

9.56 Providing and fixing ISI marked, IS :


1341, M.S.screws
necessary heavy weight butt hinges
etc. complete : with
9.56.1 125x90x4.00 mm
Details of cost for ten hinges
MATERIAL
8222 M.S. heavy weight but hinges 125x90x 4.0mm IS : 10 Nos 1 210 210.00
635 1341 marked.
Bright finished or black enamelled mild steel 100 0.8 75 60
9977 screws 50 mm Nos
Carriage of materials L.S. 2.73 2 5.46
LABOUR
15 Carpenter 2nd class day 0.14 403.67 56.51
17 Beldar day 0.09 350.00 31.50
TOTAL 363.47 W
Add 1 % Water charges on "W" 3.6347
TOTAL 367.10 X
Add GST (multiplying factor 0.1405) on "X" 51.58
TOTAL 418.68 Y
Add 15 % Contractor's profit and overheads on "Y" 62.80
Total 481.48 Z
Add Cess @ 1% on "Z" 4.81
Cost of 10 nos. 486.29
Cost of 1 no 48.63
Say 48.60

9.56.2 100x75x3.50 mm

Details of cost for ten hinges


MATERIAL
8223 M.S. heavy weight butt hinges 100x75x 10 Nos 1 160 160.00
3.5 mm IS: 1341 marked
637 Bright finished or black enamelled mild steel 100 0.8 60 48.00
9977 screws 40 mm Nos
Carriage of materials L.S. 2.73 2 5.46
LABOUR
15 Carpenter 2nd class day 0.14 403.67 56.51
17 Beldar day 0.09 350.00 31.50
TOTAL 301.47 W
Add 1 % Water charges on "W" 3.0147
TOTAL 304.48 X
Add GST (multiplying factor 0.1405) on "X" 42.78
TOTAL 347.26 Y
Add 15 % Contractor's profit and overheads on "Y" 52.09
Total 399.35 Z
Add Cess @ 1% on "Z" 3.99
Cost of 10 nos. 403.34
Cost of 1 no 40.33
Say 40.30

9.56.3 75x60x3.10 mm

Details of cost for ten hinges


MATERIAL
8224 M.S. heavy weight butt hinges 75x60x 10 Nos 1 95 95.00
3.1 mm IS: 1341 marked
638 Bright finished or black enamelled mild steel 100 0.6 45 27.00
9977 screws 30 mm Nos
Carriage of materials L.S. 1.82 2 3.64
LABOUR
15 Carpenter 2nd class day 0.14 403.67 56.51
17 Beldar day 0.09 350.00 31.50
TOTAL 213.65 W
Add 1 % Water charges on "W" 2.1365
TOTAL 215.79 X
Add GST (multiplying factor 0.1405) on "X" 30.32
TOTAL 246.11 Y
Add 15 % Contractor's profit and overheads on "Y" 36.92
Total 283.03 Z
Add Cess @ 1% on "Z" 2.83
Cost of 10 nos. 285.86
Cost of 1 no 28.59
Say 28.60

9.56.4 50x40x2.50 mm
Details of cost for ten hinges
MATERIAL
8225 M.S. heavy weight butt hinges 50x40x 10 Nos 1 80 80.00
2.5 mm IS : 1341 marked
640 Bright finished or black enamelled mild steel 100 0.4 30 12.00
9977 screws 20 mm Nos
Carriage of materials L.S. 0.91 2 1.82
LABOUR
15 Carpenter 2nd class day 0.08 403.67 32.29
TOTAL 126.11 W
Add 1 % Water charges on "W" 1.2611
TOTAL 127.37 X
Add GST (multiplying factor 0.1405) on "X" 17.90
TOTAL 145.27 Y
Add 15 % Contractor's profit and overheads on "Y" 21.79
Total 167.06 Z
Add Cess @ 1% on "Z" 1.67
Cost of 10 nos. 168.73
Cost of 1 no 16.87
Say 16.90

9.57 Providing and fixing ISI marked oxidised


M.S. pressed
necessary butt hinges
screws with
etc. complete.
9.57.1 125x65x2.12 mm
Details of cost for 10 nos.
MATERIAL
642 Oxidised mild steel butt hinges 125x 65x2.12 mm 10 Nos 1 130 130.00
682 Oxidised mild steel screws 50 mm 100 0.8 76 60.80
9977 Nos
Carriage of materials L.S. 3.64 2 7.28
LABOUR
15 Carpenter 2nd class day 0.14 403.67 56.51
17 Beldar day 0.09 350.00 31.50
TOTAL 286.09 W
Add 1 % Water charges on "W" 2.8609
TOTAL 288.95 X
Add GST (multiplying factor 0.1405) on "X" 40.60
TOTAL 329.55 Y
Add 15 % Contractor's profit and overheads on "Y" 49.43
Total 378.98 Z
Add Cess @ 1% on "Z" 3.79
Cost of 10 nos. 382.77
Cost of 1 no 38.28
Say 38.30

9.57.2 100x58x1.90 mm
Details of cost for 10 nos.
MATERIAL
643 Oxidised mild steel butt hinges 100x 58x1.90 mm 10 Nos 1 85 85.00
683 Oxidised mild steel screws 40 mm 100 0.8 62 49.60
9977 Nos
Carriage of materials L.S. 2.73 2 5.46
LABOUR
15 Carpenter 2nd class day 0.14 403.67 56.51
17 Beldar day 0.09 350.00 31.50
TOTAL 228.07 W
Add 1 % Water charges on "W" 2.2807
TOTAL 230.35 X
Add GST (multiplying factor 0.1405) on "X" 32.36
TOTAL 262.71 Y
Add 15 % Contractor's profit and overheads on "Y" 39.41
Total 302.12 Z
Add Cess @ 1% on "Z" 3.02
Cost of 10 nos. 305.14
Cost of 1 no 30.51
Say 30.50

9.57.3 75x47x1.70 mm
Details of cost for 10 nos.
MATERIAL
644 Oxidised mild steel butt hinges75x 47x1.70 mm 10 Nos 1 63 63.00
684 Oxidised mild steel screws 30 mm 100 0.6 49 29.40
9977 Nos 0.00
Carriage of materials L.S. 1.82 2 3.64
LABOUR 0.00
15 Carpenter 2nd class day 0.14 403.67 56.51
17 Beldar day 0.09 350.00 31.50
TOTAL 184.05 W
Add 1 % Water charges on "W" 1.8405
TOTAL 185.89 X
Add GST (multiplying factor 0.1405) on "X" 26.12
TOTAL 212.01 Y
Add 15 % Contractor's profit and overheads on "Y" 31.80
Total 243.81 Z
Add Cess @ 1% on "Z" 2.44
Cost of 10 nos. 246.25
Cost of 1 no 24.63
Say 24.60

9.57.4 50x37x1.50 mm
Details of cost for 10 nos.
MATERIAL
645 Oxidised mild steel butt hinges50x37x 10 Nos 1 53 53.00
1.50 mm
686 Oxidised mild steel screws 20 mm 100 0.4 32 12.80
9977 Nos
Carriage of materials L.S. 0.91 2 1.82
LABOUR
15 Carpenter 2nd class day 0.08 403.67 32.29
TOTAL 99.91 W
Add 1 % Water charges on "W" 0.9991
TOTAL 100.91 X
Add GST (multiplying factor 0.1405) on "X" 14.18
TOTAL 115.09 Y
Add 15 % Contractor's profit and overheads on "Y" 17.26
Total 132.35 Z
Add Cess @ 1% on "Z" 1.32
Cost of 10 nos. 133.67
Cost of 1 no 13.37
Say 13.40

9.58 Providing and fixing ISI marked oxidised


M.S.necessary
with pressed Parliamentary hinges :
screws etc. complete
9.58.1 150x125x27x2.80 mm
Details of cost for 10 nos.
MATERIAL
646 Oxidised mild steel parliamentary hinges 10 Nos 1 334 334.00
683 150x125x27x2.8 mm
Oxidised mild steel screws 40 mm 100 0.8 62 49.6
9977 Nos
Carriage of materials L.S. 2.73 2 5.46
LABOUR
15 Carpenter 2nd class day 0.14 403.67 56.51
17 Beldar day 0.14 350.00 49.00
TOTAL 494.57 W
Add 1 % Water charges on "W" 4.9457
TOTAL 499.52 X
Add GST (multiplying factor 0.1405) on "X" 70.18
TOTAL 569.70 Y
Add 15 % Contractor's profit and overheads on "Y" 85.45
Total 655.15 Z
Add Cess @ 1% on "Z" 6.55
Cost of 10 nos. 661.70
Cost of 1 no 66.17
Say 66.20
9.58.2 125x125x27x2.80 mm
Details of cost for 10 nos.
MATERIAL
647 Oxidised mild steel parliamentary hinges 10 Nos 1 309 309.00
683 125x125x27x2.8 mm
Oxidised mild steel screws 40 mm 100 0.8 62 49.6
9977 Nos
Carriage of materials L.S. 2.73 2 5.46
LABOUR
15 Carpenter 2nd class day 0.14 403.67 56.51
17 Beldar day 0.14 350.00 49.00
TOTAL 469.57 W
Add 1 % Water charges on "W" 4.6957
TOTAL 474.27 X
Add GST (multiplying factor 0.1405) on "X" 66.63
TOTAL 540.90 Y
Add 15 % Contractor's profit and overheads on "Y" 81.13
Total 622.03 Z
Add Cess @ 1% on "Z" 6.22
Cost of 10 nos. 628.25
Cost of 1 no 62.82
Say 62.80

9.58.3 100x125x27x2.80 mm
Details of cost for 10 nos.
MATERIAL
648 Oxidised mild steel parliamentary hinges 10 Nos 1 231 231.00
683 100x125x27x2.8 mm
Oxidised mild steel screws 40 mm 100 0.8 62 49.6
9977 Nos
Carriage of materials L.S. 2.73 2 5.46
LABOUR
15 Carpenter 2nd class day 0.14 403.67 56.51
17 Beldar day 0.14 350.00 49.00
TOTAL 391.57 W
Add 1 % Water charges on "W" 3.9157
TOTAL 395.49 X
Add GST (multiplying factor 0.1405) on "X" 55.57
TOTAL 451.06 Y
Add 15 % Contractor's profit and overheads on "Y" 67.66
Total 518.72 Z
Add Cess @ 1% on "Z" 5.19
Cost of 10 nos. 523.91
Cost of 1 no 52.39
Say 52.40

9.58.4 75x100x20x2.24 mm
Details of cost for 10 nos.
MATERIAL
649 Oxidised mild steel parliamentary hinges 10 Nos 1 196 196.00
684 75x100x20x2.24 mm 0.00
Oxidised mild steel screws 30 mm 100 0.6 49 29.4
Nos
9977 Carriage of materials L.S. 2.73 2 5.46
LABOUR
15 Carpenter 2nd class day 0.14 403.67 56.51
17 Beldar day 0.14 350.00 49.00
TOTAL 336.37 W
Add 1 % Water charges on "W" 3.3637
TOTAL 339.73 X
Add GST (multiplying factor 0.1405) on "X" 47.73
TOTAL 387.46 Y
Add 15 % Contractor's profit and overheads on "Y" 58.12
Total 445.58 Z
Add Cess @ 1% on "Z" 4.46
Cost of 10 nos. 450.04
Cost of 1 no 45
Say 45.00

9.59 Providing and fixing ISI marked oxidised


9.59.1 M.S. single acting spring hinges with
150 mm
necessary screws etc. complete :
Details of cost for 10 nos.
MATERIAL
650 Oxidised mild steel single acting spring hinges 150 each 10 138 1380.00
682 mm
Oxidised mild steel screws 50 mm 100 0.8 76 60.8
9977 Nos
Carriage of materials L.S. 2.73 2 5.46
LABOUR
15 Carpenter 2nd class day 0.4 403.67 161.47
17 Beldar day 0.2 350.00 70.00
TOTAL 1677.73 W
Add 1 % Water charges on "W" 16.7773
TOTAL 1694.51 X
Add GST (multiplying factor 0.1405) on "X" 238.08
TOTAL 1932.59 Y
Add 15 % Contractor's profit and overheads on "Y" 289.89
Total 2222.48 Z
Add Cess @ 1% on "Z" 22.22
Cost of 10 nos. 2244.70
Cost of 1 no 224.47
Say 224.50

9.59.2 125 mm

Details of cost for 10 nos.


MATERIAL
651 Oxidised mild steel single acting spring hinges 125 each 10 118 1180.00
682 mm
Oxidised mild steel screws 50 mm 100 0.8 76 60.8
9977 Nos
Carriage of materials L.S. 2.73 2 5.46
LABOUR
15 Carpenter 2nd class day 0.4 403.67 161.47
17 Beldar day 0.2 350.00 70.00
TOTAL 1477.73 W
Add 1 % Water charges on "W" 14.7773
TOTAL 1492.51 X
Add GST (multiplying factor 0.1405) on "X" 209.70
TOTAL 1702.21 Y
Add 15 % Contractor's profit and overheads on "Y" 255.33
Total 1957.54 Z
Add Cess @ 1% on "Z" 19.58
Cost of 10 nos. 1977.12
Cost of 1 no 197.71
Say 197.70

9.59.3 100 mm

Details of cost for 10 nos.


MATERIAL
652 Oxidised mild steel single acting spring hinges 100 each 10 98 980.00
683 mm
Oxidised mild steel screws 40 mm 100 0.8 62 49.6
9977 Nos
Carriage of materials L.S. 2.73 2 5.46
LABOUR
15 Carpenter 2nd class day 0.4 403.67 161.47
17 Beldar day 0.2 350.00 70.00
TOTAL 1266.53 W
Add 1 % Water charges on "W" 12.6653
TOTAL 1279.20 X
Add GST (multiplying factor 0.1405) on "X" 179.73
TOTAL 1458.93 Y
Add 15 % Contractor's profit and overheads on "Y" 218.84
Total 1677.77 Z
Add Cess @ 1% on "Z" 16.78
Cost of 10 nos. 1694.55
Cost of 1 no 169.45
Say 169.50

9.6 Providing and fixing oxidised M.S. double


acting spring hinges with necessary screws
9.60.1 150 mm
etc. complete.
Details of cost for 10 nos.
MATERIAL
653 Oxidised mild steel double acting spring hinges each 10 157 1570.00
682 150 mm 0.00
Oxidised mild steel screws 50 mm 100 0.8 76 60.80
9977 Nos 0.00
Carriage of materials L.S. 2.73 2 5.46
LABOUR 0.00
15 Carpenter 2nd class day 0.4 403.67 161.47
17 Beldar day 0.2 350.00 70.00
TOTAL 1867.73 W
Add 1 % Water charges on "W" 18.6773
TOTAL 1886.41 X
Add GST (multiplying factor 0.1405) on "X" 265.04
TOTAL 2151.45 Y
Add 15 % Contractor's profit and overheads on "Y" 322.72
Total 2474.17 Z
Add Cess @ 1% on "Z" 24.74
Cost of 10 nos. 2498.91
Cost of 1 no 249.89
Say 249.90

9.60.2 125 mm
Details of cost for 10 nos.
MATERIAL
654 Oxidised mild steel double acting spring hinges each 10 135 1350.00
682 125 mm
Oxidised mild steel screws 50 mm 100 0.8 76 60.8
9977 Nos
Carriage of materials L.S. 2.73 2 5.46
LABOUR
15 Carpenter 2nd class day 0.4 403.67 161.47
17 Beldar day 0.2 350.00 70.00
TOTAL 1647.73 W
Add 1 % Water charges on "W" 16.4773
TOTAL 1664.21 X
Add GST (multiplying factor 0.1405) on "X" 233.82
TOTAL 1898.03 Y
Add 15 % Contractor's profit and overheads on "Y" 284.70
Total 2182.73 Z
Add Cess @ 1% on "Z" 21.83
Cost of 10 nos. 2204.56
Cost of 1 no 220.46
Say 220.50

9.60.3 100 mm
Details of cost for 10 nos.
MATERIAL
655 Oxidised mild steel double acting spring hinges each 10 118 1180.00
683 100 mm
Oxidised mild steel screws 40 mm 100 0.8 62 49.6
9977 Nos
Carriage of materials L.S. 2.73 2 5.46
LABOUR
15 Carpenter 2nd class day 0.4 403.67 161.47
17 Beldar day 0.2 350.00 70.00
TOTAL 1466.53 W
Add 1 % Water charges on "W" 14.6653
TOTAL 1481.20 X
Add GST (multiplying factor 0.1405) on "X" 208.11
TOTAL 1689.31 Y
Add 15 % Contractor's profit and overheads on "Y" 253.40
Total 1942.71 Z
Add Cess @ 1% on "Z" 19.43
Cost of 10 nos. 1962.14
Cost of 1 no 196.21
Say 196.20
9.61 Providing M.S. Piano hinges ISI marked IS :
9.61.1 3818Overall
finished with35
width nickel
mm plating and fixing with
necessary screws etc., complete.
Details of cost for 1 meter
MATERIAL
656 Nickel plated mild steel piono hinges 1 mm thick metre 1 44 44.00
686 35 mm wide 0.00
Oxidised mild steel screws 20 mm 100 0.3 32 9.6
9977 Nos
Carriage of materials L.S. 1.82 2 3.64
LABOUR
15 Carpenter 2nd class day 0.14 403.67 56.51
17 Beldar day 0.09 350.00 31.50
TOTAL 341.45 W
Add 1 % Water charges on "W" 3.4145
TOTAL 344.86 X
Add GST (multiplying factor 0.1405) on "X" 48.45
TOTAL 393.31 Y
Add 15 % Contractor's profit and overheads on "Y" 59.00
Total 452.31 Z
Add Cess @ 1% on "Z" 4.52
Cost for 1 metre 456.83
Say 191.95
192.00

9.61.2 Overall width 50 mm


Details of cost for 1 meter
MATERIAL
7485 Oxidised M. S. hinges finished with nickel plating metre 1 40 40.00
686 50 mm (Over all width) 0.00
Oxidised mild steel screws 20 mm 100 0.3 32 9.6
9977 Nos
Carriage of materials L.S. 1.82 2 3.64
LABOUR
15 Carpenter 2nd class day 0.14 403.67 56.51
17 Beldar day 0.09 350.00 31.50
TOTAL 141.25 W
Add 1 % Water charges on "W" 1.4125
TOTAL 142.66 X
Add GST (multiplying factor 0.1405) on "X" 20.04
TOTAL 162.70 Y
Add 15 % Contractor's profit and overheads on "Y" 24.41
Total 187.11 Z
Add Cess @ 1% on "Z" 1.87
Cost for 1 metre 188.98
Say 188.98
189.00

9.61.3 Overall width 65 mm


Details of cost for 1 meter
MATERIAL
7486 Oxidised M. S. hinges finished with nickel plating metre 1 52 52.00
686 65 mm (Over all width) 0.00
Oxidised mild steel screws 20 mm 100 0.3 32 9.6
9977 Nos
Carriage of materials L.S. 1.82 2 3.64
LABOUR
15 Carpenter 2nd class day 0.14 403.67 56.51
17 Beldar day 0.09 350.00 31.50
TOTAL 153.25 W
Add 1 % Water charges on "W" 1.5325
TOTAL 154.78 X
Add GST (multiplying factor 0.1405) on "X" 21.75
TOTAL 176.53 Y
Add 15 % Contractor's profit and overheads on "Y" 26.48
Total 203.01 Z
Add Cess @ 1% on "Z" 2.03
Cost for 1 metre 205.04
Say 205.04
205.00

9.62 Providing and fixing ISI marked oxidised M.S.


9.62.1 sliding door bolts with nuts and screws etc.
300x16 mm
complete :
Details of cost for 10 nos.
MATERIAL
660 Oxidised mild steel sliding door bolt each 10 93 930.00
300x16 mm
7040 Oxidised mild steel screws 35 mm 100 1.2 48 57.60
Nos
641 Bright finished or black enamelled mild steel bolts each 40 5 200.00
9988 and nuts 50x6 mm
Carriage of materials & sundries L.S. 6.37 2 12.74
LABOUR
15 Carpenter 2nd class day 0.25 403.67 100.92
TOTAL 1301.26 W
Add 1 % Water charges on "W" 13.0126
TOTAL 1314.27 X
Add GST (multiplying factor 0.1405) on "X" 184.66
TOTAL 1498.93 Y
Add 15 % Contractor's profit and overheads on "Y" 224.84
Total 1723.77 Z
Add Cess @ 1% on "Z" 17.24
Cost of 10 nos. 1741.01
Cost of 1 no. 174.1
Say 174.10

9.62.2 250x16 mm
Details of cost for 10 nos.
MATERIAL
661 Oxidised mild steel sliding door bolt each 10 84 840.00
250x16 mm
7040 Oxidised mild steel screws 35 mm 100 1 48 48.00
641 Nos 0.00
Bright finished or black enamelled mild steel bolts each 40 5 200
9988 and nuts 50x6 mm
Carriage of materials & sundries L.S. 6.37 2 12.74
LABOUR 0
15 Carpenter 2nd class Day 0.25 403.67 100.92
TOTAL 1201.66 W
Add 1 % Water charges on "W" 12.0166
TOTAL 1213.68 X
Add GST (multiplying factor 0.1405) on "X" 170.52
TOTAL 1384.20 Y
Add 15 % Contractor's profit and overheads on "Y" 207.63
Total 1591.83 Z
Add Cess @ 1% on "Z" 15.92
Cost of 10 nos. 1607.75
Cost of 1 no. 160.77
Say 160.80

9.63 Providing and fixing ISI marked oxidised


9.63.1 M.S. tower bolt black finish, (Barrel type) with
250x10 mm
necessary screws etc. complete :
Details of cost for 10 nos.
MATERIAL
664 Oxidised mild steel tower bolt (barrel type) each 10 43 430.00
250x10 mm
684 Oxidised mild steel screws 30 mm 100 1 49 49.00
9977 Nos
Carriage of material L.S. 3.64 2 7.28
LABOUR
15 Carpenter 2nd class day 0.1 403.67 40.37
TOTAL 526.65 W
Add 1 % Water charges on "W" 5.2665
TOTAL 531.92 X
Add GST (multiplying factor 0.1405) on "X" 74.73
TOTAL 606.65 Y
Add 15 % Contractor's profit and overheads on "Y" 91.00
Total 697.65 Z
Add Cess @ 1% on "Z" 6.98
Cost of 10 nos. 704.63
Cost of 1 no. 70.46
Say 70.50

9.63.2 200x10 mm
Details of cost for 10 nos.
MATERIAL
665 Oxidised mild steel tower bolt (barrel type) each 10 34 340.00
200x10 mm
684 Oxidised mild steel screws 30 mm 100 0.8 49 39.20
9977 Nos
Carriage of material L.S. 2.73 2 5.46
LABOUR
15 Carpenter 2nd class day 0.1 403.67 40.37
TOTAL 425.03 W
Add 1 % Water charges on "W" 4.2503
TOTAL 429.28 X
Add GST (multiplying factor 0.1405) on "X" 60.31
TOTAL 489.59 Y
Add 15 % Contractor's profit and overheads on "Y" 73.44
Total 563.03 Z
Add Cess @ 1% on "Z" 5.63
Cost of 10 nos. 568.66
Cost of 1 no. 56.87
Say 56.90

9.63.3 150x10 mm
Details of cost for 10 nos.
MATERIAL
666 Oxidised mild steel tower bolt (barrel type) each 10 29 290.00
150x10 mm
684 Oxidised mild steel screws 30 mm 100 0.6 49 29.40
9977 Nos
Carriage of material L.S. 2.73 2 5.46
LABOUR
15 Carpenter 2nd class day 0.1 403.67 40.37
TOTAL 365.23 W
Add 1 % Water charges on "W" 3.6523
TOTAL 368.88 X
Add GST (multiplying factor 0.1405) on "X" 51.83
TOTAL 420.71 Y
Add 15 % Contractor's profit and overheads on "Y" 63.11
Total 483.82 Z
Add Cess @ 1% on "Z" 4.84
Cost of 10 nos. 488.66
Cost of 1 no. 48.87
Say 48.90

9.63.4 100x10 mm
Details of cost for 10 nos.
MATERIAL
667 Oxidised mild steel tower bolt (barrel type) each 10 20 200.00
100x10 mm
684 Oxidised mild steel screws 30 mm 100 0.6 49 29.40
9977 Nos
Carriage of material L.S. 2.73 2 5.46
LABOUR
15 Carpenter 2nd class day 0.08 403.67 32.29
TOTAL 267.15 W
Add 1 % Water charges on "W" 2.6715
TOTAL 269.82 X
Add GST (multiplying factor 0.1405) on "X" 37.91
TOTAL 307.73 Y
Add 15 % Contractor's profit and overheads on "Y" 46.16
Total 353.89 Z
Add Cess @ 1% on "Z" 3.54
Cost of 10 nos. 357.43
Cost of 1 no. 35.74
Say 35.70

9.64 Providing and fixing ISI marked 85x42 mm


oxidised M.S. pull bolt lock conforming to IS :
7534 with necessary screws bolts, nut and
washers etc. complete.
Details of cost for 10 nos.

MATERIAL
2449 Oxidised mild steel pull bolt lock each 10 60 600.00
(locking bolt) of size 85 mm x 42 mm with
9988 screws,bolts,nuts and washers complete
Carriage of materials & sundries L.S. 6.37 2 12.74
LABOUR
15 Carpenter 2nd class day 0.25 403.67 100.92
TOTAL 713.66 W
Add 1 % Water charges on "W" 7.1366
TOTAL 720.80 X
Add GST (multiplying factor 0.1405) on "X" 101.27
TOTAL 822.07 Y
Add 15 % Contractor's profit and overheads on "Y" 123.31
Total 945.38 Z
Add Cess @ 1% on "Z" 9.45
Cost of 10 nos. 954.83
Cost of 1 no. 95.48
Say 95.50

9.65 Providing and fixing ISi marked


oxidised M.S. door latches conforming to
IS:5930 with screws etc. complete :
9.65.1 300x20x6 mm

Details of cost for 10 nos.


MATERIAL
662 Oxidised mild steel door latch 300x20x6 mm each 10 49 490.00
685 Oxidised mild steel screws 25 mm 100 0.9 36 32.40
9977 Nos
Carriage of materials L.S. 3.64 2 7.28
LABOUR
15 Carpenter 2nd class day 0.12 403.67 48.44
TOTAL 578.12 W
Add 1 % Water charges on "W" 5.7812
TOTAL 583.90 X
Add GST (multiplying factor 0.1405) on "X" 82.04
TOTAL 665.94 Y
Add 15 % Contractor's profit and overheads on "Y" 99.89
Total 765.83 Z
Add Cess @ 1% on "Z" 7.66
Cost of 10 nos. 773.49
Cost of 1 no. 77.35
Say 77.40

9.65.2 250x20x6 mm

Details of cost for 10 nos.


MATERIAL
663 Oxidised mild steel door latch 250x20x6 mm each 10 39 390.00
685 Oxidised mild steel screws 25 mm 100 0.9 36 32.40
9977 Nos
Carriage of materials L.S. 3.64 2 7.28
LABOUR
15 Carpenter 2nd class day 0.12 403.67 48.44
TOTAL 478.12 W
Add 1 % Water charges on "W" 4.7812
TOTAL 482.90 X
Add GST (multiplying factor 0.1405) on "X" 67.85
TOTAL 550.75 Y
Add 15 % Contractor's profit and overheads on "Y" 82.61
Total 633.36 Z
Add Cess @ 1% on "Z" 6.33
Cost of 10 nos. 639.69
Cost of 1 no. 63.97
Say 64.00

9.66 Providing and fixing ISI marked oxidised


M.S. handles conforming to IS:4992 with
necessary screws etc. complete :
9.66.1 125 mm

Details of cost for 10 nos.


MATERIAL
668 Oxidised mild steel handles 125 mm each 10 20 200.00
685 Oxidised mild steel screws 25 mm 100 0.4 36 14.40
Nos
9977 Carriage of materials L.S. 2.73 2 5.46
LABOUR
15 Carpenter 2nd class day 0.06 403.67 24.22
TOTAL 244.08 W
Add 1 % Water charges on "W" 2.4408
TOTAL 246.52 X
Add GST (multiplying factor 0.1405) on "X" 34.64
TOTAL 281.16 Y
Add 15 % Contractor's profit and overheads on "Y" 42.17
Total 323.33 Z
Add Cess @ 1% on "Z" 3.23
Cost of 10 nos. 326.56
Cost of 1 no. 32.66
Say 32.70

9.66.2 100 mm
Details of cost for 10 nos.
MATERIAL
669 Oxidised mild steel handles 100 mm each 10 15 150.00
685 Oxidised mild steel screws 25 mm 100 0.4 36 14.40
9977 Nos 0.00
Carriage of materials L.S. 1.82 2 3.64
LABOUR
15 Carpenter 2nd class day 0.06 403.67 24.22
TOTAL 192.26 W
Add 1 % Water charges on "W" 1.9226
TOTAL 194.18 X
Add GST (multiplying factor 0.1405) on "X" 27.28
TOTAL 221.46 Y
Add 15 % Contractor's profit and overheads on "Y" 33.22
Total 254.68 Z
Add Cess @ 1% on "Z" 2.55
Cost of 10 nos. 257.23
Cost of 1 no. 25.72
Say 25.70

9.66.3 75 mm
Details of cost for 10 nos.
MATERIAL
670 Oxidised mild steel handles75 mm each 10 12 120.00
685 Oxidised mild steel screws 25 mm 100 0.4 36 14.40
9977 Carriage of materials L.S. 1.82 2 3.64
LABOUR
15 Carpenter 2nd class day 0.06 403.67 24.22
TOTAL 162.26 W
Add 1 % Water charges on "W" 1.6226
TOTAL 163.88 X
Add GST (multiplying factor 0.1405) on "X" 23.03
TOTAL 186.91 Y
Add 15 % Contractor's profit and overheads on "Y" 28.04
Total 214.95 Z
Add Cess @ 1% on "Z" 2.15
Cost of 10 nos. 217.10
Cost of 1 no. 21.71
Say 21.70

9.67 Providing and fixing oxidised M.S. hasp


9.67.1 and staple (safety type) conforming to IS : 363
150 mm
with necessary screws etc. complete :

Details of cost for 10 nos.


MATERIAL
679 Oxidised mild steel hasps and staples (safety type) 10 Nos 1 128 128.00
685 150 mm
Oxidised mild steel screws 25 mm 100 0.8 36 28.8
9977 Nos
Carriage of materials L.S. 1.82 2 3.64
LABOUR
15 Carpenter 2nd class day 0.08 403.67 32.29
TOTAL 192.73 W
Add 1 % Water charges on "W" 1.9273
TOTAL 194.66 X
Add GST (multiplying factor 0.1405) on "X" 27.35
TOTAL 222.01 Y
Add 15 % Contractor's profit and overheads on "Y" 33.30
Total 255.31 Z
Add Cess @ 1% on "Z" 2.55
Cost of 10 nos. 257.86
Cost of 1 no. 25.79
Say 25.80

9.67.2 115 mm
Details of cost for 10 nos.
MATERIAL
680 Oxidised mild steel hasps and staples (safety type) 10 Nos 1 108 108.00
685 115 mm
Oxidised mild steel screws 25 mm 100 0.7 36 25.2
9977 Nos
Carriage of materials L.S. 1.82 2 3.64
LABOUR
15 Carpenter 2nd class day 0.08 403.67 32.29
TOTAL 169.13 W
Add 1 % Water charges on "W" 1.6913
TOTAL 170.82 X
Add GST (multiplying factor 0.1405) on "X" 24.00
TOTAL 194.82 Y
Add 15 % Contractor's profit and overheads on "Y" 29.22
Total 224.04 Z
Add Cess @ 1% on "Z" 2.24
Cost of 10 nos. 226.28
Cost of 1 no. 22.63
Say 22.60

9.67.3 90 mm
Details of cost for 10 nos.
MATERIAL
681 Oxidised mild steel hasps and staples (safety type) 10 Nos 1 79 79.00
685 90 mm
Oxidised mild steel screws 25 mm 100 0.7 36 25.2
9977 Nos
Carriage of materials L.S. 1.82 2 3.64
LABOUR
15 Carpenter 2nd class day 0.08 403.67 32.29
TOTAL 140.13 W
Add 1 % Water charges on "W" 1.4013
TOTAL 141.53 X
Add GST (multiplying factor 0.1405) on "X" 19.89
TOTAL 161.42 Y
Add 15 % Contractor's profit and overheads on "Y" 24.21
Total 185.63 Z
Add Cess @ 1% on "Z" 1.86
Cost of 10 nos. 187.49
Cost of 1 no. 18.75
Say 18.80

9.68 Providing and fixing oxidised M.S.


casement stays (straight peg type) with
9.68.1 300 mm weighing not less than
necessary screws etc. complete.
200 gms
Details of cost for 10 nos.
MATERIAL
7063 Oxidised M.S.casement stay (straight peg type) each 10 35 350.00
684 300 mm not less than 0.33 kg 49 0.00
Oxidised mild steel screws 30 mm 100 0.4 49 19.6
9977 Nos
Carriage of materials L.S. 0.91 2 1.82
LABOUR
15 Carpenter 2nd class day 0.1 403.67 40.37
TOTAL 411.79 W
Add 1 % Water charges on "W" 4.1179
TOTAL 415.91 X
Add GST (multiplying factor 0.1405) on "X" 58.44
TOTAL 474.35 Y
Add 15 % Contractor's profit and overheads on "Y" 71.15
Total 545.50 Z
Add Cess @ 1% on "Z" 5.45
Cost of 10 nos. 550.95
Cost of 1 no. 55.09
Say 55.10

9.68.2 250 mm weighing not less than


150 gms
Details of cost for 10 nos.
MATERIAL
7064 Oxidised M.S.casement stay (straight peg type) each 10 30 300.00
685 250 mm not less than 0.28 kg
Oxidised mild steel screws 25 mm 100 0.4 36 14.4
9977 Nos
Carriage of materials L.S. 0.91 2 1.82
LABOUR
15 Carpenter 2nd class day 0.1 403.67 40.37
TOTAL 356.59 W
Add 1 % Water charges on "W" 3.5659
TOTAL 360.16 X
Add GST (multiplying factor 0.1405) on "X" 50.60
TOTAL 410.76 Y
Add 15 % Contractor's profit and overheads on "Y" 61.61
Total 472.37 Z
Add Cess @ 1% on "Z" 4.72
Cost of 10 nos. 477.09
Cost of 1 no. 47.71
Say 47.70

9.68.3 200 mm weighing not less than 120


gms
Details of cost for 10 nos.
MATERIAL
7065 Oxidised M.S.casement stay (straight peg type) each 10 25 250.00
685 200 mm not less than 0.24 kg
Oxidised mild steel screws 25 mm 100 0.4 36 14.4
9977 Nos
Carriage of materials L.S. 0.91 2 1.82
LABOUR
15 Carpenter 2nd class day 0.1 403.67 40.37
TOTAL 306.59 W
Add 1 % Water charges on "W" 3.0659
TOTAL 309.66 X
Add GST (multiplying factor 0.1405) on "X" 43.51
TOTAL 353.17 Y
Add 15 % Contractor's profit and overheads on "Y" 52.97
Total 406.14 Z
Add Cess @ 1% on "Z" 4.06
Cost of 10 nos. 410.20
Cost of 1 no. 41.02
Say 41.00

9.69 Providing and fixing oxidised M.S.


Safety chain
Details of cost with
for 10necessary
nos. fixtures for doors,
(weighting not less than 450 gms)

MATERIAL
7184 Oxidised M.S. safety chain (weighing not less than each 10 57 570.00
685 450 gms) for door
Oxidised mild steel screws 25 mm 100 0.6 36 21.6
9977 Nos
Carriage of materials L.S. 0.91 2 1.82
LABOUR
15 Carpenter 2nd class day 0.1 403.67 40.37
TOTAL 633.79 W
Add 1 % Water charges on "W" 6.3379
TOTAL 640.13 X
Add GST (multiplying factor 0.1405) on "X" 89.94
TOTAL 730.07 Y
Add 15 % Contractor's profit and overheads on "Y" 109.51
Total 839.58 Z
Add Cess @ 1% on "Z" 8.40
Cost of 10 nos. 847.98
Cost of 1 no. 84.8
Say 84.80
9.70 Providing and fixing IS : 12817 marked
9.70.1 stainless steel butt hinges with stainless steel
125x64x1.90 mm
screws etc. complete :
Details of cost for 10 nos.
MATERIAL
8215 Stainless steel butt hinges 125x64x 10 Nos 1 265 265.00
1.9 mm IS : 12817 marked
8210 Stainless steel screws 50 mm 100 0.8 270 216.00
9977 Nos
Carriage of materials L.S. 2.73 2 5.46
LABOUR
15 Carpenter 2nd class day 0.14 403.67 56.51
17 Beldar day 0.09 350.00 31.50
TOTAL 574.47 W
Add 1 % Water charges on "W" 5.7447
TOTAL 580.21 X
Add GST (multiplying factor 0.1405) on "X" 81.52
TOTAL 661.73 Y
Add 15 % Contractor's profit and overheads on "Y" 99.26
Total 760.99 Z
Add Cess @ 1% on "Z" 7.61
Cost of 10 nos. 768.60
Cost of 1 no. 76.86
Say 76.90

9.70.2 100X58X1.90 mm
Details of cost for 10 nos.
MATERIAL
8216 Stainless steel butt hinges 100x58x1.9 mm IS : 10 Nos 1 235 235.00
8211 12817 marked
Stainless steel screws 40 mm 100 Nos 0.8 215 172
9977 Carriage of materials L.S. 2.73 2 5.46
LABOUR
15 Carpenter 2nd class day 0.14 403.67 56.51
17 Beldar day 0.09 350.00 31.50
TOTAL 500.47 W
Add 1 % Water charges on "W" 5.0047
TOTAL 505.47 X
Add GST (multiplying factor 0.1405) on "X" 71.02
TOTAL 576.49 Y
Add 15 % Contractor's profit and overheads on "Y" 86.47
Total 662.96 Z
Add Cess @ 1% on "Z" 6.63
Cost of 10 nos. 669.59
Cost of 1 no. 66.96
Say 67.00

9.70.3 75x47x1.80 mm
Details of cost for 10 nos.
MATERIAL
8217 Stainless steel butt hinges 75x47x1.8 mm IS : 10 Nos 1 160 160.00
8212 12817 marked
Stainless steel screws 30 mm 100 0.6 190 114
9977 Nos
Carriage of materials L.S. 1.82 2 3.64
LABOUR
15 Carpenter 2nd class day 0.14 403.67 56.51
17 Beldar day 0.09 350.00 31.50
TOTAL 365.65 W
Add 1 % Water charges on "W" 3.6565
TOTAL 369.31 X
Add GST (multiplying factor 0.1405) on "X" 51.89
TOTAL 421.20 Y
Add 15 % Contractor's profit and overheads on "Y" 63.18
Total 484.38 Z
Add Cess @ 1% on "Z" 4.84
Cost of 10 nos. 489.22
Cost of 1 no. 48.92
Say 48.90

9.70.4 50x37x1.50 mm
Details of cost for 10 nos.
MATERIAL
8218 Stainless steel butt hinges 50x37x1.5 mm IS : 10 Nos 1 135 135.00
8214 12817 marked
Stainless steel screws 20 mm 100 0.4 125 50
9977 Nos
Carriage of materials L.S. 0.91 2 1.82
LABOUR
15 Carpenter 2nd class day 0.08 403.67 32.29
TOTAL 219.11 W
Add 1 % Water charges on "W" 2.1911
TOTAL 221.30 X
Add GST (multiplying factor 0.1405) on "X" 31.09
TOTAL 252.39 Y
Add 15 % Contractor's profit and overheads on "Y" 37.86
Total 290.25 Z
Add Cess @ 1% on "Z" 2.90
Cost of 10 nos. 293.15
Cost of 1 no. 29.32
Say 29.30

9.71 Providing and fixing IS : 12817


marked stainless steel butt hinges (heavy
9.71.1 125x64x2.50 mm
weight) with stainless steel screws etc.
Details
completeof cost
: for 10 nos.
MATERIAL
8219 Stainless steel butt hinges (heavy weight) 10 Nos 1 350 350.00
8210 125x64x2.5 mm IS : 12817 marked 0.00
Stainless steel screws 50 mm 100 0.8 270 216
9977 Nos
Carriage of materials L.S. 2.73 2 5.46
LABOUR
15 Carpenter 2nd class day 0.14 403.67 56.51
17 Beldar day 0.09 350.00 31.50
TOTAL 659.47 W
Add 1 % Water charges on "W" 6.5947
TOTAL 666.06 X
Add GST (multiplying factor 0.1405) on "X" 93.58
TOTAL 759.64 Y
Add 15 % Contractor's profit and overheads on "Y" 113.95
Total 873.59 Z
Add Cess @ 1% on "Z" 8.74
Cost of 10 nos. 882.33
Cost of 1 no. 88.23
Say 88.20

9.71.2 100x60x2.50 mm
Details of cost for 10 nos.
MATERIAL
8220 Stainless steel butt hinges (heavy weight) 10 Nos 1 255 255.00
8211 100x60x2.5 mm IS : 12817 marked
Stainless steel screws 40 mm 100 0.8 215 172
9977 Nos
Carriage of materials L.S. 2.73 2 5.46
LABOUR
15 Carpenter 2nd class day 0.14 403.67 56.51
17 Beldar day 0.09 350.00 31.50
TOTAL 520.47 W
Add 1 % Water charges on "W" 5.2047
TOTAL 525.67 X
Add GST (multiplying factor 0.1405) on "X" 73.86
TOTAL 599.53 Y
Add 15 % Contractor's profit and overheads on "Y" 89.93
Total 689.46 Z
Add Cess @ 1% on "Z" 6.89
Cost of 10 nos. 696.35
Cost of 1 no. 69.64
Say 69.60

9.71.3 75x50x2.50 mm
Details of cost for 10 nos.
MATERIAL
8221 Stainless steel butt hinges (heavy weight) 10 Nos 1 205 205.00
8212 75x50x2.5 mm IS : 12817 marked
Stainless steel screws 30 mm 100 0.6 190 114
9977 Nos
Carriage of materials L.S. 1.82 2 3.64
LABOUR
15 Carpenter 2nd class day 0.14 403.67 56.51
17 Beldar day 0.09 350.00 31.50
TOTAL 410.65 W
Add 1 % Water charges on "W" 4.1065
TOTAL 414.76 X
Add GST (multiplying factor 0.1405) on "X" 58.27
TOTAL 473.03 Y
Add 15 % Contractor's profit and overheads on "Y" 70.95
Total 543.98 Z
Add Cess @ 1% on "Z" 5.44
Cost of 10 nos. 549.42
Cost of 1 no. 54.94
Say 54.90

9.72 Providing and fixing bright finished brass


butt hinges with necessary screws etc.
complete :
9.72.1 125x85x5.5 mm (heavy type)

Details of cost for 10 nos.


MATERIAL
382 Brass butt hinges (heavy type) : 125x85x5.5 10 Nos 1 1309 1309.00
449 mm(.70)kg
Brass screws 50 mm 100 1 220 220
9977 Nos
Carriage of material L.S. 3.64 2 7.28
LABOUR
14 Carpenter 1st class day 0.14 505.17 70.72
17 Beldar day 0.1 350.00 35.00
TOTAL 1642.00 W
Add 1 % Water charges on "W" 16.42
TOTAL 1658.42 X
Add GST (multiplying factor 0.1405) on "X" 233.01
TOTAL 1891.43 Y
Add 15 % Contractor's profit and overheads on "Y" 283.71
Total 2175.14 Z
Add Cess @ 1% on "Z" 21.75
Cost of 10 nos. 2196.89
Cost of 1 no. 219.69
Say 219.70

9.72.2 125x70x4 mm (ordinary type)


Details of cost for 10 nos.
MATERIAL
378 Brass butt hinges (light/ordinary type) : 10 Nos 1 775 775.00
125x70x4 mm
449 Brass screws 50 mm 100 1 220 220.00
9977 Nos
Carriage of material L.S. 3.64 2 7.28
LABOUR
14 Carpenter 1st class day 0.14 505.17 70.72
17 Beldar day 0.1 350.00 35.00
TOTAL 1108.00 W
Add 1 % Water charges on "W" 11.08
TOTAL 1119.08 X
Add GST (multiplying factor 0.1405) on "X" 157.23
TOTAL 1276.31 Y
Add 15 % Contractor's profit and overheads on "Y" 191.45
Total 1467.76 Z
Add Cess @ 1% on "Z" 14.68
Cost of 10 nos. 1482.44
Cost of 1 no. 148.24
Say 148.20
9.72.3 100x85x5.5 mm (heavy type)

Details of cost for 10 nos.


MATERIAL
383 Brass butt hinges (heavy type) : 100x85x5.5 10 Nos 1 997 997.00
450 mm(.56)kg
Brass screws 40 mm 100 0.8 170 136
9977 Nos
Carriage of material L.S. 2.73 2 5.46
LABOUR
14 Carpenter 1st class day 0.14 505.17 70.72
17 Beldar day 0.1 350.00 35.00
TOTAL 1244.18 W
Add 1 % Water charges on "W" 12.4418
TOTAL 1256.62 X
Add GST (multiplying factor 0.1405) on "X" 176.56
TOTAL 1433.18 Y
Add 15 % Contractor's profit and overheads on "Y" 214.98
Total 1648.16 Z
Add Cess @ 1% on "Z" 16.48
Cost of 10 nos. 1664.64
Cost of 1 no. 166.46
Say 166.50

9.72.4 100x70x4 mm (ordinary type)


Details of cost for 10 nos.
MATERIAL
379 Brass butt hinges (light/ordinary type) : 10 Nos 1 625 625.00
100x70x4 mm
450 Brass screws 40 mm 100 0.8 170 136.00
9977 Nos
Carriage of material L.S. 2.73 2 5.46
LABOUR
14 Carpenter 1st class day 0.14 505.17 70.72
17 Beldar day 0.1 350.00 35.00
TOTAL 872.18 W
Add 1 % Water charges on "W" 8.7218
TOTAL 880.90 X
Add GST (multiplying factor 0.1405) on "X" 123.77
TOTAL 1004.67 Y
Add 15 % Contractor's profit and overheads on "Y" 150.70
Total 1155.37 Z
Add Cess @ 1% on "Z" 11.55
Cost of 10 nos. 1166.92
Cost of 1 no. 116.69
Say 116.70

9.72.5 75x65x4 mm (heavy type)


Details of cost for 10 nos.
MATERIAL
384 Brass butt hinges (heavy type) : 75x65x4.0 10 Nos 1 838 838.00
mm(.20)kg
451 Brass screws 30 mm 100 0.6 140 84.00
9977 Nos
Carriage of material L.S. 2.73 2 5.46
LABOUR
14 Carpenter 1st class day 0.14 505.17 70.72
17 Beldar day 0.1 350.00 35.00
TOTAL 1033.18 W
Add 1 % Water charges on "W" 10.3318
TOTAL 1043.51 X
Add GST (multiplying factor 0.1405) on "X" 146.61
TOTAL 1190.12 Y
Add 15 % Contractor's profit and overheads on "Y" 178.52
Total 1368.64 Z
Add Cess @ 1% on "Z" 13.69
Cost of 10 nos. 1382.33
Cost of 1 no. 138.23
Say 138.20

9.72.6 75x40x2.5 mm (ordinary type)

Details of cost for 10 nos.


MATERIAL
380 Brass butt hinges (light/ordinary type) : 75x40x2.5 10 Nos 1 380 380.00
451 mm 0.00
Brass screws 30 mm 100 0.6 140 84
9977 Nos
Carriage of material L.S. 2.73 2 5.46
LABOUR
14 Carpenter 1st class day 0.14 505.17 70.72
17 Beldar day 0.1 350.00 35.00
TOTAL 575.18 W
Add 1 % Water charges on "W" 5.7518
TOTAL 580.93 X
Add GST (multiplying factor 0.1405) on "X" 81.62
TOTAL 662.55 Y
Add 15 % Contractor's profit and overheads on "Y" 99.38
Total 761.93 Z
Add Cess @ 1% on "Z" 7.62
Cost of 10 nos. 769.55
Cost of 1 no. 76.96
Say 77.00

9.72.7 50x40x2.5 mm (ordinary type)

Details of cost for 10 nos.


MATERIAL
381 Brass butt hinges (light/ordinary type) : 50x40x2.5 10 Nos 1 155 155.00
453 mm 0.00
Brass screws 20 mm 100 0.4 95 38
9977 Nos
Carriage of material L.S. 1.82 2 3.64
LABOUR
14 Carpenter 1st class day 0.08 505.17 40.41
TOTAL 237.05 W
Add 1 % Water charges on "W" 2.3705
TOTAL 239.42 X
Add GST (multiplying factor 0.1405) on "X" 33.64
TOTAL 273.06 Y
Add 15 % Contractor's profit and overheads on "Y" 40.96
Total 314.02 Z
Add Cess @ 1% on "Z" 3.14
Cost of 10 nos. 317.16
Cost of 1 no. 31.72
Say 31.70

9.73 Providing and fixing bright finished


9.73.1 brass150x125x27x5
parliamentarymm
hinges with necessary
screws etc. complete :
Details of cost for 10 nos.
MATERIAL
385 Brass parliamentary hinges 150x125x27x5 mm 10 Nos 1 2610 2610.00
450 Brass screws 40 mm 100 0.8 170 136.00
9977 Nos
Carriage of materials L.S. 2.73 2 5.46
LABOUR
14 Carpenter 1st class day 0.14 505.17 70.72
17 Beldar day 0.14 350.00 49.00
TOTAL 2871.18 W
Add 1 % Water charges on "W" 28.7118
TOTAL 2899.89 X
Add GST (multiplying factor 0.1405) on "X" 407.43
TOTAL 3307.32 Y
Add 15 % Contractor's profit and overheads on "Y" 496.10
Total 3803.42 Z
Add Cess @ 1% on "Z" 38.03
Cost of 10 nos. 3841.45
Cost of 1 no. 384.15
Say 384.20

9.73.2 125x125x27x5 mm

Details of cost for 10 nos.


MATERIAL
386 Brass parliamentary hinges 125x125x27x5 mm 10 Nos 1 2300 2300.00
450 Brass screws 40 mm 100 0.8 170 136.00
9977 Nos
Carriage of materials L.S. 2.73 2 5.46
LABOUR
14 Carpenter 1st class day 0.14 505.17 70.72
17 Beldar day 0.14 350.00 49.00
TOTAL 2561.18 W
Add 1 % Water charges on "W" 25.6118
TOTAL 2586.79 X
Add GST (multiplying factor 0.1405) on "X" 363.44
TOTAL 2950.23 Y
Add 15 % Contractor's profit and overheads on "Y" 442.53
Total 3392.76 Z
Add Cess @ 1% on "Z" 33.93
Cost of 10 nos. 3426.69
Cost of 1 no. 342.67
Say 342.70

9.73.3 100x125x27x5 mm

Details of cost for 10 nos.


MATERIAL
387 Brass parliamentary hinges 100x125x27x5 mm 10 Nos 1 2090 2090.00
450 Brass screws 40 mm 100 0.8 170 136.00
9977 Nos
Carriage of materials L.S. 2.73 2 5.46
LABOUR
14 Carpenter 1st class day 0.14 505.17 70.72
17 Beldar day 0.14 350.00 49.00
TOTAL 2351.18 W
Add 1 % Water charges on "W" 23.5118
TOTAL 2374.69 X
Add GST (multiplying factor 0.1405) on "X" 333.64
TOTAL 2708.33 Y
Add 15 % Contractor's profit and overheads on "Y" 406.25
Total 3114.58 Z
Add Cess @ 1% on "Z" 31.15
Cost of 10 nos. 3145.73
Cost of 1 no. 314.57
Say 314.60

9.73.4 75x100x20x3.2 mm
Details of cost for 10 nos.
MATERIAL
388 Brass parliamentary hinges 75x100x20x3.2 mm 10 Nos 1 1870 1870.00
451 Brass screws 30 mm 100 0.6 140 84.00
9977 Nos
Carriage of materials L.S. 2.73 2 5.46
LABOUR
14 Carpenter 1st class day 0.14 505.17 70.72
17 Beldar day 0.14 350.00 49.00
TOTAL 2079.18 W
Add 1 % Water charges on "W" 20.7918
TOTAL 2099.97 X
Add GST (multiplying factor 0.1405) on "X" 295.05
TOTAL 2395.02 Y
Add 15 % Contractor's profit and overheads on "Y" 359.25
Total 2754.27 Z
Add Cess @ 1% on "Z" 27.54
Cost of 10 nos. 2781.81
Cost of 1 no. 278.18
Say 278.20

9.74 Providing and fixing bright finished


brass tower bolts (barrel type) with
necessary screws etc. complete :
9.74.1 250x10 mm

Details of cost for 10 nos.


MATERIAL
400 Brass tower bolt (barrel type) 250x10 mm each 10 257 2570.00
451 Brass screws 30 mm 100 1 140 140.00
9977 Nos
Carriage of materials L.S. 4.55 2 9.1
LABOUR
14 Carpenter 1st class day 0.1 505.17 50.52
TOTAL 2769.62 W
Add 1 % Water charges on "W" 27.6962
TOTAL 2797.32 X
Add GST (multiplying factor 0.1405) on "X" 393.02
TOTAL 3190.34 Y
Add 15 % Contractor's profit and overheads on "Y" 478.55
Total 3668.89 Z
Add Cess @ 1% on "Z" 36.69
Cost of 10 nos. 3705.58
Cost of 1 no. 370.56
Say 370.60

9.74.2 200x10 mm
Details of cost for 10 nos.
MATERIAL
401 Brass tower bolt (barrel type) 200x10 mm each 10 205 2050.00
451 Brass screws 30 mm 100 0.8 140 112.00
9977 Nos
Carriage of materials L.S. 2.73 2 5.46
LABOUR
14 Carpenter 1st class day 0.1 505.17 50.52
TOTAL 2217.98 W
Add 1 % Water charges on "W" 22.1798
TOTAL 2240.16 X
Add GST (multiplying factor 0.1405) on "X" 314.74
TOTAL 2554.90 Y
Add 15 % Contractor's profit and overheads on "Y" 383.23
Total 2938.13 Z
Add Cess @ 1% on "Z" 29.38
Cost of 10 nos. 2967.51
Cost of 1 no. 296.75
Say 296.80
9.74.3 150x10 mm

Details of cost for 10 nos.


MATERIAL
402 Brass tower bolt (barrel type) 150x10 mm each 10 154 1540.00
451 Brass screws 30 mm 100 0.8 140 112.00
9977 Nos
Carriage of materials L.S. 2.73 2 5.46
LABOUR
14 Carpenter 1st class day 0.1 505.17 50.52
TOTAL 1707.98 W
Add 1 % Water charges on "W" 17.0798
TOTAL 1725.06 X
Add GST (multiplying factor 0.1405) on "X" 242.37
TOTAL 1967.43 Y
Add 15 % Contractor's profit and overheads on "Y" 295.11
Total 2262.54 Z
Add Cess @ 1% on "Z" 22.63
Cost of 10 nos. 2285.17
Cost of 1 no. 228.52
Say 228.50

9.74.4 100x10 mm
Details of cost for 10 nos.
MATERIAL
403 Brass tower bolt (barrel type) 100x10 mm each 10 103 1030.00
451 Brass screws 30 mm 100 0.6 140 84.00
9977 Nos
Carriage of materials L.S. 2.73 2 5.46
LABOUR
14 Carpenter 1st class day 0.1 505.17 50.52
TOTAL 1169.98 W
Add 1 % Water charges on "W" 11.6998
TOTAL 1181.68 X
Add GST (multiplying factor 0.1405) on "X" 166.03
TOTAL 1347.71 Y
Add 15 % Contractor's profit and overheads on "Y" 202.16
Total 1549.87 Z
Add Cess @ 1% on "Z" 15.50
Cost of 10 nos. 1565.37
Cost of 1 no. 156.54
Say 156.50

9.75 Providing and fixing bright finished


brass door latch with necessary screws
9.75.1 etc. complete :
300x16x5 mm
Details of cost for 10 nos.
MATERIAL
411 Brass door latch 300x16x5 mm (0.380 kg) each 10 185 1850.00
452 Brass screws 25 mm 100 0.9 100 90.00
9977 Nos
Carriage of materials L.S. 3.64 2 7.28
LABOUR
14 Carpenter 1st class day 0.12 505.17 60.62
TOTAL 2007.90 W
Add 1 % Water charges on "W" 20.079
TOTAL 2027.98 X
Add GST (multiplying factor 0.1405) on "X" 284.93
TOTAL 2312.91 Y
Add 15 % Contractor's profit and overheads on "Y" 346.94
Total 2659.85 Z
Add Cess @ 1% on "Z" 26.60
Cost of 10 nos. 2686.45
Cost of 1 no. 268.64
Say 268.60

9.75.2 250x16x5 mm
Details of cost for 10 nos.
MATERIAL
412 Brass door latch 250x16x5 mm (0.350 kg) each 10 175 1750.00
452 Brass screws 25 mm 100 Nos 0.9 100 90.00
9977 Carriage of materials L.S. 3.64 2 7.28
LABOUR
14 Carpenter 1st class day 0.12 505.17 60.62
TOTAL 1907.90 W
Add 1 % Water charges on "W" 19.079
TOTAL 1926.98 X
Add GST (multiplying factor 0.1405) on "X" 270.74
TOTAL 2197.72 Y
Add 15 % Contractor's profit and overheads on "Y" 329.66
Total 2527.38 Z
Add Cess @ 1% on "Z" 25.27
Cost of 10 nos. 2552.65
Cost of 1 no. 255.26
Say 255.30

9.76 Providing and fixing bright finished


brass
etc. 100 mm mortice latch and lock with
complete.
6 levers and a pair of lever handles of
Details of cost for one No
approved quality with necessary screws
MATERIAL
413 Brass mortice latch and lock 100x65 mm with 6 each 1 400 400.00
levers and a pair of brass lever handles
LABOUR
14 Carpenter 1st class day 0.17 505.17 85.88
9999 Sundries (screws, carriage etc.) L.S. 3.64 2 7.28
TOTAL 493.16 W
Add 1 % Water charges on "W" 4.9316
TOTAL 498.09 X
Add GST (multiplying factor 0.1405) on "X" 69.98
TOTAL 568.07 Y
Add 15 % Contractor's profit and overheads on "Y" 85.21
Total 653.28 Z
Add Cess @ 1% on "Z" 6.53
Cost of 1 no 659.81
Say 659.81
659.80

9.77 Providing and fixing bright finished brass


100
Details of mortice
mm latch
cost for one Nowith one dead bolt and a
pair of lever handles of approved quality with
MATERIAL
necessary screws etc. complete.
414 Brass mortice latch 100x65mm with a pair of brass each 1 310 310.00
lever handles
LABOUR
14 Carpenter 1st class day 0.17 505.17 85.88
9999 Sundries (screws, carriage etc.) L.S. 3.64 2 7.28
TOTAL 403.16 W
Add 1 % Water charges on "W" 4.0316
TOTAL 407.19 X
Add GST (multiplying factor 0.1405) on "X" 57.21
TOTAL 464.40 Y
Add 15 % Contractor's profit and overheads on "Y" 69.66
Total 534.06 Z
Add Cess @ 1% on "Z" 5.34
Cost of 1 no 539.40
Say 539.4
539.40
9.78 Providing and fixing bright finished brass
night latch of for
Details of cost approved
one No quality including
necessary screws etc. complete.

MATERIAL
438 Brass Night latch each 1 610 610.00
LABOUR
14 Carpenter 1st class day 0.17 505.17 85.88
9999 Sundries (screws, carriage etc.) L.S. 3.64 2 7.28
TOTAL 703.16 W
Add 1 % Water charges on "W" 7.0316
TOTAL 710.19 X
Add GST (multiplying factor 0.1405) on "X" 99.78
TOTAL 809.97 Y
Add 15 % Contractor's profit and overheads on "Y" 121.50
Total 931.47 Z
Add Cess @ 1% on "Z" 9.31
Cost of 1 no 940.78
Say 940.78
940.80
9.79 Providing and fixing special quality bright
finished brass cupboard or ward robe locks
with four levers of approved quality including
9.79.1 40 mm screws etc. complete.
necessary

Details of cost for one No


MATERIAL
2451 Brass cupboard lock 6 levers (best make each 1 55 55.00
of approved quality) 40 mm size
LABOUR
14 Carpenter 1st class day 0.17 505.17 85.88
9999 Sundries & screws L.S. 3.64 2 7.28
TOTAL 148.16 W
Add 1 % Water charges on "W" 1.4816
TOTAL 149.64 X
Add GST (multiplying factor 0.1405) on "X" 21.02
TOTAL 170.66 Y
Add 15 % Contractor's profit and overheads on "Y" 25.60
Total 196.26 Z
Add Cess @ 1% on "Z" 1.96
Cost of 1 no 198.22
Say 198.22
198.20
9.79.2 50 mm
Details of cost for one No
MATERIAL
2452 Brass cupboard lock 6 levers (best make each 1 85 85.00
of approved quality) 50 mm size
LABOUR
14 Carpenter 1st class day 0.17 505.17 85.88
9999 Sundries & screws L.S. 3.64 2 7.28
TOTAL 178.16 W
Add 1 % Water charges on "W" 1.7816
TOTAL 179.94 X
Add GST (multiplying factor 0.1405) on "X" 25.28
TOTAL 205.22 Y
Add 15 % Contractor's profit and overheads on "Y" 30.78
Total 236.00 Z
Add Cess @ 1% on "Z" 2.36
Cost of 1 no 238.36
Say 238.36
238.40
9.79.3 65 mm

Details of cost for one No


MATERIAL
2453 Brass cupboard lock 6 levers (best make each 1 90 90.00
of approved quality) 65 mm size
LABOUR
14 Carpenter 1st class day 0.17 505.17 85.88
9999 Sundries & screws L.S. 3.64 2 7.28
TOTAL 183.16 W
Add 1 % Water charges on "W" 1.8316
TOTAL 184.99 X
Add GST (multiplying factor 0.1405) on "X" 25.99
TOTAL 210.98 Y
Add 15 % Contractor's profit and overheads on "Y" 31.65
Total 242.63 Z
Add Cess @ 1% on "Z" 2.43
Cost of 1 no 245.06
Say 245.06
245.10
9.79.4 75 mm

Details of cost for one No


MATERIAL
2454 Brass cupboard lock 6 levers (best make of each 1 105 105.00
approved quality) 75 mm size
LABOUR
14 Carpenter 1st class day 0.17 505.17 85.88
9999 Sundries & screws L.S. 3.64 2 7.28
TOTAL 198.16 W
Add 1 % Water charges on "W" 1.9816
TOTAL 200.14 X
Add GST (multiplying factor 0.1405) on "X" 28.12
TOTAL 228.26 Y
Add 15 % Contractor's profit and overheads on "Y" 34.24
Total 262.50 Z
Add Cess @ 1% on "Z" 2.63
Cost of 1 no 265.13
Say 265.13
265.10
9.80 Providing and fixing 50 mm bright finished
brass cup board or wardrobe knob of approved
quality with necessary screws.
Details of cost for 10 nos.

MATERIAL
447 Brass cupboard knob or ward robe knob 50 mm each 10 36 360.00
9977 Carriage of material L.S. 2.73 2 5.46
LABOUR
14 Carpenter 1st class day 0.14 505.17 70.72
TOTAL 436.18 W
Add 1 % Water charges on "W" 4.3618
TOTAL 440.54 X
Add GST (multiplying factor 0.1405) on "X" 61.90
TOTAL 502.44 Y
Add 15 % Contractor's profit and overheads on "Y" 75.37
Total 577.81 Z
Add Cess @ 1% on "Z" 5.78
Cost of 10 nos 583.59
Cost of 1 no 58.36
Say 58.40

9.81 Providing and fixing bright finished brass


9.81.1 handles with screws etc. complete:
125 mm
Details of cost for 10 nos.
MATERIAL
408 Brass handles 125 mm with plate 175x32 mm each 10 144 1440.00
452 Brass screws 25 mm 100 0.4 100 40.00
9977 Nos
Carriage of material L.S. 2.73 2 5.46
LABOUR
14 Carpenter 1st class day 0.06 505.17 30.31
TOTAL 1515.77 W
Add 1 % Water charges on "W" 15.1577
TOTAL 1530.93 X
Add GST (multiplying factor 0.1405) on "X" 215.10
TOTAL 1746.03 Y
Add 15 % Contractor's profit and overheads on "Y" 261.90
Total 2007.93 Z
Add Cess @ 1% on "Z" 20.08
Cost of 10 nos 2028.01
Cost of 1 no 202.8
Say 202.80

9.81.2 100 mm
Details of cost for 10 nos.
MATERIAL
409 Brass handles 100 mm with plate 150x32 mm each 10 133 1330.00
452 Brass screws 25 mm 100 0.4 100 40.00
9977 Nos
Carriage of material L.S. 0.91 2 1.82
LABOUR
14 Carpenter 1st class day 0.06 505.17 30.31
TOTAL 1402.13 W
Add 1 % Water charges on "W" 14.0213
TOTAL 1416.15 X
Add GST (multiplying factor 0.1405) on "X" 198.97
TOTAL 1615.12 Y
Add 15 % Contractor's profit and overheads on "Y" 242.27
Total 1857.39 Z
Add Cess @ 1% on "Z" 18.57
Cost of 10 nos 1875.96
Cost of 1 no 187.6
Say 187.60

9.81.3 75 mm
Details of cost for 10 nos.
MATERIAL
410 Brass handles75 mm with plate 125x32 mm each 10 103 1030.00
452 Brass screws 25 mm 100 0.4 100 40.00
9977 Nos
Carriage of material L.S. 0.91 2 1.82
LABOUR
14 Carpenter 1st class day 0.06 505.17 30.31
TOTAL 1102.13 W
Add 1 % Water charges on "W" 11.0213
TOTAL 1113.15 X
Add GST (multiplying factor 0.1405) on "X" 156.40
TOTAL 1269.55 Y
Add 15 % Contractor's profit and overheads on "Y" 190.43
Total 1459.98 Z
Add Cess @ 1% on "Z" 14.60
Cost of 10 nos 1474.58
Cost of 1 no 147.46
Say 147.50

9.82 Providing and fixing bright finished brass


hanging
Details of type floor
cost for 10 door stopper
hanging floor with necessary
screws, etc. complete.
door stopper
MATERIAL
2455 Brass hanging type door stopper 150 mm each 10 75 750.00
452 Brass screws 25 mm 100 0.2 100 20.00
9977 Nos
Carriage of material L.S. 2.73 2 5.46
LABOUR
14 Carpenter 1st class day 0.03 505.17 15.16
TOTAL 790.62 W
Add 1 % Water charges on "W" 7.9062
TOTAL 798.53 X
Add GST (multiplying factor 0.1405) on "X" 112.19
TOTAL 910.72 Y
Add 15 % Contractor's profit and overheads on "Y" 136.61
Total 1047.33 Z
Add Cess @ 1% on "Z" 10.47
Cost of 10 nos 1057.80
Cost of 1 no 105.78
Say 105.80

9.83 Providing and fixing aluminium die cast body


tubular
Details oftype
costuniversal
for 10 nos.hydraulic door closer
(having brand logo with ISI, IS : 3564,
embossed on the body, door weight upto 35 kg
MATERIAL
2456 Hydraulic door closer bottle type M.S. body with each 10 673 6730.00
451 necessary accessories and screws complete
Brass screws 30 mm 100 0.6 140 84
9977 Nos
Carriage of material L.S. 3.64 2 7.28
LABOUR
15 Carpenter 2nd class day 1 403.67 403.67
TOTAL 7224.95 W
Add 1 % Water charges on "W" 72.2495
TOTAL 7297.20 X
Add GST (multiplying factor 0.1405) on "X" 1025.26
TOTAL 8322.46 Y
Add 15 % Contractor's profit and overheads on "Y" 1248.37
Total 9570.83 Z
Add Cess @ 1% on "Z" 95.71
Cost of 10 nos 9666.54
Cost of 1 no 966.65
Say 966.70

9.84 Providing and fixing aluminium extruded


section
Details ofbody tubular
cost for type universal hydraulic
10 nos.
door closer (having brand logo with ISi, IS :
MATERIAL
3564, embossed on the body, door weight upto
7060 Hydraulic door closer tubular type Aluminium each 10 560 5600.00
451 section body
Brass screws 30 mm 100 0.6 140 84
9977 Nos
Carriage of material L.S. 1.04 2 2.08
LABOUR
15 Carpenter 2nd class day 1 403.67 403.67
TOTAL 6089.75 W
Add 1 % Water charges on "W" 60.8975
TOTAL 6150.65 X
Add GST (multiplying factor 0.1405) on "X" 864.17
TOTAL 7014.82 Y
Add 15 % Contractor's profit and overheads on "Y" 1052.22
Total 8067.04 Z
Add Cess @ 1% on "Z" 80.67
Cost of 10 nos 8147.71
Cost of 1 no 814.77
Say 814.80

9.85 Providing and fixing bright finished brass


casement window fastener with necessary
screws etc. complete.
Details of cost for 10 nos.
MATERIAL
423 Brass casement window fastener Each 10 45 450.00
452 Brass screws 25 mm 100 0.4 100 40.00
9977 Nos
Carriage of material L.S. 0.91 2 1.82
LABOUR
14 Carpenter 1st class day 0.1 505.17 50.52
TOTAL 542.34 W
Add 1 % Water charges on "W" 5.4234
TOTAL 547.76 X
Add GST (multiplying factor 0.1405) on "X" 76.96
TOTAL 624.72 Y
Add 15 % Contractor's profit and overheads on "Y" 93.71
Total 718.43 Z
Add Cess @ 1% on "Z" 7.18
Cost of 10 nos 725.61
Cost of 1 no 72.56
Say 72.60

9.86 Providing and fixing bright finished brass


casement stays (straight peg type) with
necessary screws etc. complete :
9.86 300 mm weighing not less than 330
gms
Details of cost for 10 nos.
MATERIAL
424 Brass casement stays (straight peg type ) 300 mm each 10 126 1260.00
451 weighing not less than 0.33 kg
Brass screws 30 mm 100 0.4 140 56
9977 Nos
Carriage of material L.S. 0.91 2 1.82
LABOUR
14 Carpenter 1st class day 0.1 505.17 50.52
TOTAL 1368.34 W
Add 1 % Water charges on "W" 13.6834
TOTAL 1382.02 X
Add GST (multiplying factor 0.1405) on "X" 194.17
TOTAL 1576.19 Y
Add 15 % Contractor's profit and overheads on "Y" 236.43
Total 1812.62 Z
Add Cess @ 1% on "Z" 18.13
Cost of 10 nos 1830.75
Cost of 1 no 183.08
Say 183.10

9.86.2 250 mm weighing not less than 280


gms of cost for 10 nos.
Details
MATERIAL
425 Brass casement stays (straight peg type ) 250 mm each 10 100 1000.00
452 weighing not less than 0.28 kg
Brass screws 25 mm 100 0.4 100 40
9977 Nos
Carriage of material L.S. 0.91 2 1.82
LABOUR
14 Carpenter 1st class day 0.1 505.17 50.52
TOTAL 1092.34 W
Add 1 % Water charges on "W" 10.9234
TOTAL 1103.26 X
Add GST (multiplying factor 0.1405) on "X" 155.01
TOTAL 1258.27 Y
Add 15 % Contractor's profit and overheads on "Y" 188.74
Total 1447.01 Z
Add Cess @ 1% on "Z" 14.47
Cost of 10 nos 1461.48
Cost of 1 no 146.15
Say 146.20

9.86.3 200 mm weighing not less than 240


gms
Details of cost for 10 nos.
MATERIAL
426 Brass casement stays (straight peg type ) 200 each 10 95 950.00
452 mmweighing not less than 0.24 kg
Brass screws 25 mm 100 0.4 100 40
9977 Nos
Carriage of material L.S. 0.91 2 1.82
LABOUR
14 Carpenter 1st class day 0.1 505.17 50.52
TOTAL 1042.34 W
Add 1 % Water charges on "W" 10.4234
TOTAL 1052.76 X
Add GST (multiplying factor 0.1405) on "X" 147.91
TOTAL 1200.67 Y
Add 15 % Contractor's profit and overheads on "Y" 180.10
Total 1380.77 Z
Add Cess @ 1% on "Z" 13.81
Cost of 10 nos 1394.58
Cost of 1 no 139.46
Say 139.50

9.87 Providing and fixing bright finished brass


9.87.1 hasp and staple (safety type) with necessary
150 mm
screws etc. complete :
Details of cost for 10 nos.
MATERIAL
431 Brass hasps and staples (safety type) 150 mm 10 Nos 1 740 740.00
452 Brass screws 25 mm 100 0.8 100 80.00
Nos
9977 Carriage of material L.S. 1.82 2 3.64
LABOUR
14 Carpenter 1st class day 0.08 505.17 40.41
TOTAL 864.05 W
Add 1 % Water charges on "W" 8.6405
TOTAL 872.69 X
Add GST (multiplying factor 0.1405) on "X" 122.61
TOTAL 995.30 Y
Add 15 % Contractor's profit and overheads on "Y" 149.30
Total 1144.60 Z
Add Cess @ 1% on "Z" 11.45
Cost of 10 nos 1156.05
Cost of 1 no 115.61
Say 115.60

9.87.2 115 mm
Details of cost for 10 nos.
MATERIAL
432 Brass hasps and staples (safety type) 115 mm 10 Nos 1 670 670.00
453 Brass screws 20 mm 100 0.7 95 66.50
9977 Nos
Carriage of material L.S. 1.82 2 3.64
LABOUR
14 Carpenter 1st class day 0.08 505.17 40.41
TOTAL 780.55 W
Add 1 % Water charges on "W" 7.8055
TOTAL 788.36 X
Add GST (multiplying factor 0.1405) on "X" 110.76
TOTAL 899.12 Y
Add 15 % Contractor's profit and overheads on "Y" 134.87
Total 1033.99 Z
Add Cess @ 1% on "Z" 10.34
Cost of 10 nos 1044.33
Cost of 1 no 104.43
Say 104.40

9.87.3 90 mm
Details of cost for 10 nos.
MATERIAL
433 Brass hasps and staples (safety type) 90 mm 10 Nos 1 670 670.00
453 Brass screws 20 mm 100 0.7 95 66.50
Nos 0.00
9977 Carriage of material L.S. 1.82 2 3.64
LABOUR 0.00
14 Carpenter 1st class day 0.08 505.17 40.41
TOTAL 780.55 W
Add 1 % Water charges on "W" 7.8055
TOTAL 788.36 X
Add GST (multiplying factor 0.1405) on "X" 110.76
TOTAL 899.12 Y
Add 15 % Contractor's profit and overheads on "Y" 134.87
Total 1033.99 Z
Add Cess @ 1% on "Z" 10.34
Cost of 10 nos 1044.33
Cost of 1 no 104.43
Say 104.40

9.88 Providing and fixing chromium plated


brass 100 mm mortice latch and lock with 6
levers and a pair of lever handles of approved
complete.
quality with necessary screws etc.
Details of cost for one No

MATERIAL
558 Chromium plated Brass mortice latch and lock each 1 470 470.00
100x65 mm with6 levers and a pair of
brass lever handles
LABOUR
14 Carpenter 1st class day 0.17 505.17 85.88
9999 Sundries (screws, carriage etc.) L.S. 3.64 2 7.28
TOTAL 563.16 W
Add 1 % Water charges on "W" 5.6316
TOTAL 568.79 X
Add GST (multiplying factor 0.1405) on "X" 79.92
TOTAL 648.71 Y
Add 15 % Contractor's profit and overheads on "Y" 97.31
Total 746.02 Z
Add Cess @ 1% on "Z" 7.46
Cost of 1 no 753.48
Say 753.48
753.50

9.89 Providing and fixing chromium plated


brass
Detailsnight latch
of cost of approved
for one No quality including
necessary screws etc. complete.
MATERIAL
583 Chromium plated Brass Night latch each 1 500 500.00
LABOUR
14 Carpenter 1st class day 0.17 505.17 85.88
9999 Sundries (screws, carriage etc.) L.S. 3.64 2 7.28
TOTAL 593.16 W
Add 1 % Water charges on "W" 5.9316
TOTAL 599.09 X
Add GST (multiplying factor 0.1405) on "X" 84.17
TOTAL 683.26 Y
Add 15 % Contractor's profit and overheads on "Y" 102.49
Total 785.75 Z
Add Cess @ 1% on "Z" 7.86
Cost of 1 no 793.61
Say 793.61
793.60
9.90 Providing and fixing special quality
chromium plated brass cupboard locks with six
9.90.1 Size 40 mm
levers of approved quality including necessary
Details of cost for one No
screws etc. complete.
MATERIAL
2468 Nickled Chromium Brass cupboard lock each 1 60 60.00
40 mm size LABOUR
14 Carpenter 1st class day 0.17 505.17 85.88
9999 Sundries & screws L.S. 3.64 2 7.28
TOTAL 153.16 W
Add 1 % Water charges on "W" 1.5316
TOTAL 154.69 X
Add GST (multiplying factor 0.1405) on "X" 21.73
TOTAL 176.42 Y
Add 15 % Contractor's profit and overheads on "Y" 26.46
Total 202.88 Z
Add Cess @ 1% on "Z" 2.03
Cost of 1 no 204.91
Say 204.91
204.90

9.90.2 Size 50 mm
Details of cost for one No
MATERIAL
2469 Nickled Chromium Brass cupboard lock each 1 70 70.00
50 mm size LABOUR
14 Carpenter 1st class day 0.17 505.17 85.88
9999 Sundries & screws L.S. 3.64 2 7.28
TOTAL 163.16 W
Add 1 % Water charges on "W" 1.6316
TOTAL 164.79 X
Add GST (multiplying factor 0.1405) on "X" 23.15
TOTAL 187.94 Y
Add 15 % Contractor's profit and overheads on "Y" 28.19
Total 216.13 Z
Add Cess @ 1% on "Z" 2.16
Cost of 1 no 218.29
Say 218.29
218.30
9.90.3 Size 65 mm
Details of cost for one No
MATERIAL
2470 Nickled Chromium Brass cupboard lock each 1 95 95.00
65 mm size
LABOUR
14 Carpenter 1st class day 0.17 505.17 85.88
9999 Sundries & screws L.S. 3.64 2 7.28
TOTAL 188.16 W
Add 1 % Water charges on "W" 1.8816
TOTAL 190.04 X
Add GST (multiplying factor 0.1405) on "X" 26.70
TOTAL 216.74 Y
Add 15 % Contractor's profit and overheads on "Y" 32.51
Total 249.25 Z
Add Cess @ 1% on "Z" 2.49
Cost of 1 no 251.74
Say 251.74
251.70
9.90.4 Size 75 mm

Details of cost for one


MATERIAL
2471 Nickled Chromium Brass cupboard lock 75 mm size each 1 120 120.00
LABOUR
14 Carpenter 1st class day 0.17 505.17 85.88
9999 Sundries & screws L.S. 3.64 2.00 7.28
TOTAL 213.16 W
Add 1 % Water charges on "W" 2.1316
TOTAL 215.29 X
Add GST (multiplying factor 0.1405) on "X" 30.25
TOTAL 245.54 Y
Add 15 % Contractor's profit and overheads on "Y" 36.83
Total 282.37 Z
Add Cess @ 1% on "Z" 2.82
Cost of 1 no 285.19
Say 285.19
285.20
9.91 Providing and fixing chromium
plated brass 50 mm cupboard or wardrobe
nuts complete.
knobs with
Details of cost for 10 nos.
MATERIAL
584 Chromium plated Brass Wardrobe Knobe 50 mm each 10 80 800.00
9977 Carriage of material L.S. 2.73 2 5.46
LABOUR
14 Carpenter 1st class day 0.14 505.17 70.72
TOTAL 876.18 W
Add 1 % Water charges on "W" 8.7618
TOTAL 884.94 X
544 Add GST (multiplying factor 0.1405) on "X" 124.33
TOTAL 1009.27 Y
Add 15 % Contractor's profit and overheads on "Y" 151.39
Total 1160.66 Z
Add Cess @ 1% on "Z" 11.61
Cost of 10 nos 1172.27
Cost of 1 no 117.23
Say 117.20

9.92 Providing and fixing chromium plated brass


handles with necessary screws etc.
complete:
9.92.1 125 mm
Details of cost for 10 nos.
MATERIAL
555 Chromium plated Brass handles 125 mm with each 10 160 1600.00
452 plate 175 x32 mm 0.00
Brass screws 25 mm 100 0.4 100 40
9977 Nos
Carriage of material L.S. 2.73 2 5.46
LABOUR
14 Carpenter 1st class day 0.06 505.17 30.31
TOTAL 1675.77 W
Add 1 % Water charges on "W" 16.7577
TOTAL 1692.53 X
Add GST (multiplying factor 0.1405) on "X" 237.80
TOTAL 1930.33 Y
Add 15 % Contractor's profit and overheads on "Y" 289.55
Total 2219.88 Z
Add Cess @ 1% on "Z" 22.20
Cost of 10 nos 2242.08
Cost of 1 no 224.21
Say 224.20

9.92.2 100 mm
Details of cost for 10 nos.
MATERIAL
556 Chromium plated Brass handles each 10 140 1400.00
100 mm with plate 150 x 32 mm
545
452 Brass screws 25 mm 100 0.4 100 40.00
9977 Nos
Carriage of material L.S. 0.91 2 1.82
LABOUR
14 Carpenter 1st class day 0.06 505.17 30.31
TOTAL 1472.13 W
Add 1 % Water charges on "W" 14.7213
TOTAL 1486.85 X
Add GST (multiplying factor 0.1405) on "X" 208.90
TOTAL 1695.75 Y
Add 15 % Contractor's profit and overheads on "Y" 254.36
Total 1950.11 Z
Add Cess @ 1% on "Z" 19.50
Cost of 10 nos 1969.61
Cost of 1 no 196.96
Say 197.00
9.92.3 75 mm
Details of cost for 10 nos.
MATERIAL
557 Chromium plated Brass handles 75mm with plate each 10 125 1250.00
452 125x32 mm 0.00
Brass screws 25 mm 100 0.4 100 40
9977 Nos
Carriage of material L.S. 0.91 2 1.82
LABOUR
14 Carpenter 1st class day 0.06 505.17 30.31
TOTAL 1322.13 W
Add 1 % Water charges on "W" 13.2213
TOTAL 1335.35 X
Add GST (multiplying factor 0.1405) on "X" 187.62
TOTAL 1522.97 Y
Add 15 % Contractor's profit and overheads on "Y" 228.45
Total 1751.42 Z
Add Cess @ 1% on "Z" 17.51
Cost of 10 nos 1768.93
Cost of 1 no 176.89
Say 176.90

9.93 Providing and fixing chromium plated


brass casement
necessary window
screws fastener with
etc. complete.
Details of cost for 10 nos.
546
MATERIAL
568 Chromium plated brass casement window fastner each 10 90 900.00
588 Chromium plated Brass screws 25 mm 100 Nos 0.4 180 72.00
9977 Carriage of material L.S. 0.91 2 1.82
LABOUR
14 Carpenter 1st class day 0.1 505.17 50.52
TOTAL 1024.34 W
Add 1 % Water charges on "W" 10.2434
TOTAL 1034.58 X
Add GST (multiplying factor 0.1405) on "X" 145.36
TOTAL 1179.94 Y
Add 15 % Contractor's profit and overheads on "Y" 176.99
Total 1356.93 Z
Add Cess @ 1% on "Z" 13.57
Cost of 10 nos 1370.50
Cost of 1 no 137.05
Say 137.10
9.94 Providing and fixing chromium plated
brass casementscrews
with necessary stays (straight peg type)
etc. complete :
9.94.1 300 mm weighing not less than 330
gms
Details of cost for 10 nos.

MATERIAL
569 Chromium plated Brass casement stays (straight each 10 140 1400.00
588 peg type ) 300 mmweighing not less than 0.33 kg
Chromium plated Brass screws 25 mm 100 0.4 180 72
9977 Nos
Carriage of material L.S. 0.91 2 1.82
LABOUR
14 Carpenter 1st class day 0.1 505.17 50.52
TOTAL 1524.34 W
Add 1 % Water charges on "W" 15.2434
TOTAL 1539.58 X
Add GST (multiplying factor 0.1405) on "X" 216.31
TOTAL 1755.89 Y
Add 15 % Contractor's profit and overheads on "Y" 263.38
Total 2019.27 Z
Add Cess @ 1% on "Z" 20.19
Cost of 10 nos 2039.46
Cost of 1 no 203.95
Say 204.00

9.94.2 250 mm weighing not less than 280 gms


Details of cost for 10 nos.
MATERIAL
570 Chromium plated Brass casement stays (straight each 10 120 1200.00
peg type ) 250 mmweighing not less than 0.28 kg
588 Chromium plated Brass screws 25 mm 100 0.4 180 72
Nos
9977 Carriage of material L.S. 0.91 2 1.82
LABOUR
14 Carpenter 1st class day 0.1 505.17 50.52
TOTAL 1324.34 W
Add 1 % Water charges on "W" 13.2434
TOTAL 1337.58 X
Add GST (multiplying factor 0.1405) on "X" 187.93
TOTAL 1525.51 Y
Add 15 % Contractor's profit and overheads on "Y" 228.83
Total 1754.34 Z
Add Cess @ 1% on "Z" 17.54
Cost of 10 nos 1771.88
Cost of 1 no 177.19
Say 177.20

9.94.3 200 mm weighing not less than 240


gms
Details of cost for 10 nos.
MATERIAL
571 Chromium plated Brass casement stays (straight each 10 100 1000.00
588 peg type ) 200 mmweighing not less than 0.24 kg
Chromium plated Brass screws 25 mm 100 0.4 180 72
9977 Nos
Carriage of material L.S. 0.91 2 1.82
LABOUR
14 Carpenter 1st class day 0.1 505.17 50.52
TOTAL 1124.34 W
Add 1 % Water charges on "W" 11.2434
TOTAL 1135.58 X
Add GST (multiplying factor 0.1405) on "X" 159.55
TOTAL 1295.13 Y
Add 15 % Contractor's profit and overheads on "Y" 194.27
Total 1489.40 Z
Add Cess @ 1% on "Z" 14.89
Cost of 10 nos 1504.29
Cost of 1 no 150.43
Say 150.40

9.95 Providing and fixing ISI marked aluminium


butt hinges anodised (anodic coating not less
than grade AC 10 as per IS: 1868) transparent
with necessary
or dyed screws
to required etc.orcomplete:
colour shade
9.95.1 125x75x4 mm
Details of cost for 10 nos.
MATERIAL
687 Anodised Aluminium butt hinges 125x75x4 mm 10 Nos 1 560 560.00
585 Chromium plated Brass screws 50 mm 100 1 300 300.00
9977 Nos
Carriage of materials L.S. 3.64 2 7.28
LABOUR
14 Carpenter 1st class day 0.14 505.17 70.72
17 Beldar day 0.09 350.00 31.50
TOTAL 969.50 W
Add 1 % Water charges on "W" 9.695
TOTAL 979.20 X
Add GST (multiplying factor 0.1405) on "X" 137.58
TOTAL 1116.78 Y
Add 15 % Contractor's profit and overheads on "Y" 167.52
Total 1284.30 Z
Add Cess @ 1% on "Z" 12.84
Cost of 10 nos 1297.14
Cost of 1 no 129.71
Say 129.70

9.95.2 125x63x4 mm
Details of cost for 10 nos.
MATERIAL
688 Anodised Aluminium butt hinges 125x63x4 mm 10 Nos 1 393 393.00
585 Chromium plated Brass screws 50 mm 100 1 300 300.00
9977 Nos
Carriage of materials L.S. 3.64 2 7.28
LABOUR
14 Carpenter 1st class day 0.14 505.17 70.72
17 Beldar day 0.09 350.00 31.50
TOTAL 802.50 W
Add 1 % Water charges on "W" 8.025
TOTAL 810.53 X
Add GST (multiplying factor 0.1405) on "X" 113.88
549 924.41 Y
TOTAL 138.66
Add 15 % Contractor's profit and overheads on "Y" 1063.07 Z
Total 10.63
Add Cess @ 1% on "Z" 1073.70
Cost of 10 nos 107.37
Cost of 1 no 107.40
Say

9.95.3 100x75x4 mm
Details of cost for 10 nos.
MATERIAL
689 Anodised Aluminium butt hinges 100x75x4 mm 10 Nos 1 393 393.00
586 Chromium plated Brass screws 40 mm 100 0.8 290 232.00
9977 Nos
Carriage of materials L.S. 2.73 2 5.46
LABOUR
14 Carpenter 1st class day 0.14 505.17 70.72
17 Beldar day 0.09 350.00 31.50
TOTAL 732.68 W
Add 1 % Water charges on "W" 7.3268
TOTAL 740.01 X
Add GST (multiplying factor 0.1405) on "X" 103.97
TOTAL 843.98 Y
Add 15 % Contractor's profit and overheads on "Y" 126.60
Total 970.58 Z
Add Cess @ 1% on "Z" 9.71
Cost of 10 nos 980.29
Cost of 1 no 98.03
Say 98.00

9.95.4 100x63x4 mm
Details of cost for 10 nos.
MATERIAL
691 Anodised Aluminium butt hinges 100x63x4 mm 10 Nos 1 324 324.00
586 Chromium plated Brass screws 40 mm 100 0.8 290 232.00
9977 Nos
Carriage of materials L.S. 2.73 2 5.46
LABOUR
14 Carpenter 1st class day 0.14 505.17 70.72
550
17 Beldar day 0.09 350.00 31.50
TOTAL 663.68 W
Add 1 % Water charges on "W" 6.6368
TOTAL 670.32 X
Add GST (multiplying factor 0.1405) on "X" 94.18
TOTAL 764.50 Y
Add 15 % Contractor's profit and overheads on "Y" 114.67
Total 879.17 Z
Add Cess @ 1% on "Z" 8.79
Cost of 10 nos 887.96
Cost of 1 no 88.8
Say 88.80

9.95.5 100x63x3.2 mm
Details of cost for 10 nos.
MATERIAL
690 Anodised Aluminium butt hinges 100x63x3.2 mm 10 Nos 1 270 270.00
586 Chromium plated Brass screws 40 mm 100 0.8 290 232.00
9977 Nos
Carriage of materials L.S. 2.73 2 5.46
LABOUR
14 Carpenter 1st class day 0.14 505.17 70.72
17 Beldar day 0.09 350.00 31.50
TOTAL 609.68 W
Add 1 % Water charges on "W" 6.0968
TOTAL 615.78 X
Add GST (multiplying factor 0.1405) on "X" 86.52
TOTAL 702.30 Y
Add 15 % Contractor's profit and overheads on "Y" 105.34
Total 807.64 Z
Add Cess @ 1% on "Z" 8.08
Cost of 10 nos 815.72
Cost of 1 no 81.57
Say 81.60

9.95.6 75x63x4 mm
Details of cost for 10 nos.
MATERIAL
692 Anodised Aluminium butt hinges 75x63x4 mm 10 Nos 1 275 275.00
587 Chromium plated Brass screws 30 mm 100 0.6 240 144.00
9977 Nos
Carriage of materials L.S. 1.82 2 3.64
LABOUR
14 Carpenter 1st class day 0.14 505.17 70.72
17 Beldar day 0.09 350.00 31.50
TOTAL 524.86 W
Add 1 % Water charges on "W" 5.2486
TOTAL 530.11 X
Add GST (multiplying factor 0.1405) on "X" 74.48
TOTAL 604.59 Y
Add 15 % Contractor's profit and overheads on "Y" 90.69
Total 695.28 Z
Add Cess @ 1% on "Z" 6.95
Cost of 10 nos 702.23
Cost of 1 no 70.22
Say 70.20
9.95.7 75x63x3.2 mm
Details of cost for 10 nos.
MATERIAL
693 Anodised Aluminium butt hinges 75x63x3.2 mm 10 Nos 1 226 226.00
587 Chromium plated Brass screws 30 mm 100 0.6 240 144.00
9977 Nos
Carriage of materials L.S. 1.82 2 3.64
LABOUR
14 Carpenter 1st class day 0.14 505.17 70.72
17 Beldar day 0.09 350.00 31.50
TOTAL 475.86 W
Add 1 % Water charges on "W" 4.7586
TOTAL 480.62 X
Add GST (multiplying factor 0.1405) on "X" 67.53
TOTAL 548.15 Y
Add 15 % Contractor's profit and overheads on "Y" 82.22
Total 630.37 Z
552 6.30
Add Cess @ 1% on "Z" 636.67
Cost of 10 nos 63.67
Cost of 1 no 63.70
Say

9.95.8 75x45x3.2 mm
Details of cost for 10 nos.
MATERIAL
694 Anodised Aluminium butt hinges 75x45x3.2 mm 10 Nos 1 196 196.00
587 Chromium plated Brass screws 30 mm 100 0.6 240 144.00
9977 Nos
Carriage of materials L.S. 1.82 2 3.64
LABOUR
14 Carpenter 1st class day 0.14 505.17 70.72
17 Beldar day 0.09 350.00 31.50
TOTAL 445.86 W
Add 1 % Water charges on "W" 4.4586
TOTAL 450.32 X
Add GST (multiplying factor 0.1405) on "X" 63.27
TOTAL 513.59 Y
Add 15 % Contractor's profit and overheads on "Y" 77.04
Total 590.63 Z
Add Cess @ 1% on "Z" 5.91
Cost of 10 nos 596.54
Cost of 1 no 59.65
Say 59.70

9.96 Providing and fixing aluminium sliding door


9.96.1 bolts, ISI marked anodised (anodic coating not
300x16 mm
less than grade AC 10 as per IS : 1868),
transparent or dyed to required colour or
Details of cost for 10 nos.
MATERIAL
696 Anodised Aluminium sliding door bolt 300x16 mm each 10 147 1470.00
588 Chromium plated Brass screws 25 mm 100 0.4 180 72.00
Nos
9977 Carriage of materials L.S. 5.46 2 10.92
LABOUR
14 Carpenter 1st class day 0.5 505.17 252.59
TOTAL 1805.51 W
Add 1 % Water charges on "W" 18.0551
TOTAL 1823.57 X
Add GST (multiplying factor 0.1405) on "X" 256.21
TOTAL 2079.78 Y
Add 15 % Contractor's profit and overheads on "Y" 311.97
Total 2391.75 Z
Add Cess @ 1% on "Z" 23.92
Cost of 10 nos 2415.67
Cost of 1 no 241.57
Say 241.60

9.96.2 250x16 mm
Details of cost for 10 nos.
MATERIAL
697 Anodised Aluminium sliding door bolt 250x16 mm each 10 128 1280.00
588 Chromium plated Brass screws 25 mm 100 0.4 180 72.00
9977 Nos
Carriage of materials L.S. 5.46 2 10.92
LABOUR
14 Carpenter 1st class day 0.5 505.17 252.59
TOTAL 1615.51 W
Add 1 % Water charges on "W" 16.1551
TOTAL 1631.67 X
Add GST (multiplying factor 0.1405) on "X" 229.25
TOTAL 1860.92 Y
Add 15 % Contractor's profit and overheads on "Y" 279.14
Total 2140.06 Z
Add Cess @ 1% on "Z" 21.40
Cost of 10 nos 2161.46
Cost of 1 no 216.15
Say 216.20

9.97 Providing and fixing aluminium tower bolts,


9.97.1 ISI marked, anodised (anodic coating not less
300x10 mm
than grade AC 10 as per IS : 1868 )
transparent or dyed to required colour or
Details of cost for 10 nos.
MATERIAL
698 Anodised Aluminium tower bolt (barrel 10 Nos 1 580 580.00
587 type)300x10 mm
Chromium plated Brass screws 30 mm 100 0.8 240 192
Nos
554 0.00
9977 Carriage of materials L.S. 4.42 2 8.84
LABOUR
14 Carpenter 1st class day 0.125 505.17 63.15
TOTAL 843.99 W
Add 1 % Water charges on "W" 8.4399
TOTAL 852.43 X
Add GST (multiplying factor 0.1405) on "X" 119.77
TOTAL 972.20 Y
Add 15 % Contractor's profit and overheads on "Y" 145.83
Total 1118.03 Z
Add Cess @ 1% on "Z" 11.18
Cost of 10 nos 1129.21
Cost of 1 no 112.92
Say 112.90

9.97.2 250x10 mm
Details of cost for 10 nos.
MATERIAL
699 Anodised Aluminium tower bolt (barrel 10 Nos 1 481 481.00
587 type)250x10 mm
Chromium plated Brass screws 30 mm 100 0.8 240 192
9977 Nos
Carriage of materials L.S. 4.42 2 8.84
LABOUR
14 Carpenter 1st class day 0.125 505.17 63.15
TOTAL 744.99 W
Add 1 % Water charges on "W" 7.4499
TOTAL 752.44 X
Add GST (multiplying factor 0.1405) on "X" 105.72
TOTAL 858.16 Y
Add 15 % Contractor's profit and overheads on "Y" 128.72
Total 986.88 Z
Add Cess @ 1% on "Z" 9.87
Cost of 10 nos 996.75
Cost of 1 no 99.67
Say 99.70

9.97.3 200x10 mm
Details of cost for 10 nos.
MATERIAL
700 Anodised Aluminium tower bolt (barrel 10 Nos 1 383 383.00
type)200x10 mm
587 Chromium plated Brass screws 30 mm 100 0.8 240 192
Nos
9977 Carriage of materials L.S. 2.73 2 5.46
LABOUR
14 Carpenter 1st class day 0.125 505.17 63.15
TOTAL 643.61 W
Add 1 % Water charges on "W" 6.4361
TOTAL 650.05 X
Add GST (multiplying factor 0.1405) on "X" 91.33
TOTAL 741.38 Y
Add 15 % Contractor's profit and overheads on "Y" 111.21
Total 852.59 Z
Add Cess @ 1% on "Z" 8.53
Cost of 10 nos 861.12
Cost of 1 no 86.11
Say 86.10

9.97.4 150x10 mm
Details of cost for 10 nos.
MATERIAL
701 Anodised Aluminium tower bolt (barrel 10 Nos 1 304 304.00
587 type)150x10 mm
Chromium plated Brass screws 30 mm 100 0.8 240 192
9977 Nos
Carriage of materials L.S. 2.73 2 5.46
LABOUR
14 Carpenter 1st class day 0.08 505.17 40.41
TOTAL 541.87 W
Add 1 % Water charges on "W" 5.4187
TOTAL 547.29 X
Add GST (multiplying factor 0.1405) on "X" 76.89
TOTAL 624.18 Y
Add 15 % Contractor's profit and overheads on "Y" 93.63
Total 717.81 Z
Add Cess @ 1% on "Z" 7.18
Cost of 10 nos 724.99
Cost of 1 no 72.5
Say 72.50

9.97.5 100x10 mm
Details of cost for 10 nos.
MATERIAL
702 Anodised Aluminium tower bolt (barrel 10 Nos 1 226 226.00
587 type)100x10 mm
Chromium plated Brass screws 30 mm 100 0.6 240 144
9977 Nos
Carriage of materials L.S. 2.73 2 5.46
LABOUR
14 Carpenter 1st class day 0.08 505.17 40.41
TOTAL 415.87 W
Add 1 % Water charges on "W" 4.1587
TOTAL 420.03 X
Add GST (multiplying factor 0.1405) on "X" 59.01
TOTAL 479.04 Y
Add 15 % Contractor's profit and overheads on "Y" 71.86
Total 550.90 Z
Add Cess @ 1% on "Z" 5.51
Cost of 10 nos 556.41
Cost of 1 no 55.64
Say 55.60

9.98 Providing and fixing aluminium pull bolt


lock, ISI marked, anodised (anodic coating not
less than grade AC 10 as per IS : 1868)
transparent or dyed to required colour and
Details of cost for 10 pull bolt lock
MATERIAL
2464 Anodised Aluminium pull bolt lock (locking bolt) of each 10 46 460.00
size 85 mmx42 mm with screws,bolts,nuts and
9977 washers complete
Carriage of materials L.S. 6.37 2 12.74
LABOUR
15 Carpenter 2nd class day 0.25 403.67 100.92
TOTAL 573.66 W
Add 1 % Water charges on "W" 5.7366
TOTAL 579.40 X
Add GST (multiplying factor 0.1405) on "X" 81.41
TOTAL 660.81 Y
Add 15 % Contractor's profit and overheads on "Y" 99.12
Total 759.93 Z
Add Cess @ 1% on "Z" 7.60
Cost of 10 nos 767.53
Cost of 1 no 76.75
Say 76.80

9.99 Providing and fixing 50 cm long aluminium


kicking
requiredplate of size
colour 100x3.15
or shade, with mm, anodised
necessary
(anodic
screws coating
etc. not less than grade AC 10 as
Details costcomplete.
per IS :of1868) for 10 nos.
transparent or dyed to
MATERIAL
706 Anodised Aluminium kicking plate 50 cm each 10 142 1420.00
588 long100x3.15 mm
Chromium plated Brass screws 25 mm 100 0.4 180 72
9977 Nos
Carriage of materials L.S. 5.46 2 10.92
LABOUR
14 Carpenter 1st class day 0.07 505.17 35.36
17 Beldar day 0.05 350.00 17.50
TOTAL 1555.78 W
Add 1 % Water charges on "W" 15.5578
TOTAL 1571.34 X
Add GST (multiplying factor 0.1405) on "X" 220.77
TOTAL 1792.11 Y
Add 15 % Contractor's profit and overheads on "Y" 268.82
Total 2060.93 Z
Add Cess @ 1% on "Z" 20.61
Cost of 10 nos 2081.54
Cost of 1 no 208.15
Say 208.20

9.1 Providing and fixing aluminium handles, ISI


9.100.1 marked, anodised (anodic coating not less
125 mm
than grade AC 10 as per IS : 1868) transparent
Details
or dyedoftocost for 10 nos.
required colour or shade, with
MATERIAL
558
703 Anodised Aluminium handles 125 mm with plate 10 Nos 1 324 324.00
588 175 x 32 mm
Chromium plated Brass screws 25 mm 100 0.4 180 72
9977 Nos
Carriage of materials L.S. 2.73 2 5.46
LABOUR
14 Carpenter 1st class day 0.06 505.17 30.31
TOTAL 431.77 W
Add 1 % Water charges on "W" 4.3177
TOTAL 436.09 X
Add GST (multiplying factor 0.1405) on "X" 61.27
TOTAL 497.36 Y
Add 15 % Contractor's profit and overheads on "Y" 74.60
Total 571.96 Z
Add Cess @ 1% on "Z" 5.72
Cost of 10 nos 577.68
Cost of 1 no 57.77
Say 57.80
9.100.2 100 mm
Details of cost for 10 nos.
MATERIAL
704 Anodised Aluminium handles 100 mm with plate 10 Nos 1 275 275.00
588 150 x 32 mm
Chromium plated Brass screws 25 mm 100 0.4 180 72
9977 Nos
Carriage of materials L.S. 1.82 2 3.64
LABOUR
14 Carpenter 1st class day 0.06 505.17 30.31
TOTAL 380.95 W
Add 1 % Water charges on "W" 3.8095
TOTAL 384.76 X
Add GST (multiplying factor 0.1405) on "X" 54.06
TOTAL 438.82 Y
Add 15 % Contractor's profit and overheads on "Y" 65.82
Total 504.64 Z
Add Cess @ 1% on "Z" 5.05
Cost of 10 nos 509.69
Cost of 1 no 50.97
Say 51.00

9.100.3 75 mm
Details of cost for 10 nos.
MATERIAL
705 Anodised Aluminium handles 75mm with plate 125 10 Nos 1 231 231.00
589 x 32 mm 0.00
Chromium plated Brass screws 20 mm 100 0.4 160 64.00
9977 Nos 0.00
Carriage of materials L.S. 1.82 2 3.64
LABOUR 0.00
Carpenter 1st class day 0.06 505.17 30.31
TOTAL 328.95 W
Add 1 % Water charges on "W" 3.2895
TOTAL 332.24 X
Add GST (multiplying factor 0.1405) on "X" 46.68
TOTAL 378.92 Y
Add 15 % Contractor's profit and overheads on "Y" 56.84
Total 435.76 Z
Add Cess @ 1% on "Z" 4.36
Cost of 10 nos 440.12
Cost of 1 no 44.01
Say 44.00

9.101 Providing and fixing aluminium hanging floor


door
Singlestopper,
rubber ISI marked, anodised (anodic
stopper
9.101.1 coating not less than grade AC 10 as per IS :
Details of cost for 10or
1868) transparent nos.
dyed to required colour
MATERIAL

2459 Anodised Aluminium hanging type door stopper 10 19 190.00


588 Chromium plated Brass screws 25 mm 0.2 180 36.00
Nos 0.00
9977 Carriage of materials L.S. 2.73 2 5.46
LABOUR 0.00
14 Carpenter 1st class day 0.03 505.17 15.16
TOTAL 246.62 W
Add 1 % Water charges on "W" 2.4662
TOTAL 249.09 X
Add GST (multiplying factor 0.1405) on "X" 35.00
TOTAL 284.09 Y
Add 15 % Contractor's profit and overheads on "Y" 42.61
Total 326.70 Z
Add Cess @ 1% on "Z" 3.27
Cost of 10 nos 329.97
Cost of 1 no 33
Say 33.00

9.101.2 Twin rubber stopper


Details of cost for 10 nos.
MATERIAL
7059 Aluminium hanging floor door stopper with twin each 10 40 400.00
588 rubber & stopper
Chromium plated Brass screws 25 mm 100 0.2 180 36
9977 Nos
Carriage of materials L.S. 2.73 2 5.46
LABOUR
14 Carpenter 1st class day 0.03 505.17 15.16
TOTAL 456.62 W
Add 1 % Water charges on "W" 4.5662
TOTAL 461.19 X
Add GST (multiplying factor 0.1405) on "X" 64.80
TOTAL 525.99 Y
Add 15 % Contractor's profit and overheads on "Y" 78.90
Total 604.89 Z
Add Cess @ 1% on "Z" 6.05
Cost of 10 nos 610.94
Cost of 1 no 61.09
Say 61.10

9.102 Providing and fixing aluminium casement


stays, ISI marked, anodised (anodic coating
not less than grade AC 10 as per IS : 1868)
Details of costorfordyed
transparent 10 nos.
to required colour and
MATERIAL
2465 Anodised Aluminium Casement stay 250 mm each 10 32 320.00
588 Chromium plated Brass screws 25 mm 100 Nos 0.4 180 72.00
9977 Carriage of materials L.S. 0.91 2 1.82
LABOUR
14 Carpenter 1st class day 0.1 505.17 50.52
TOTAL 444.34 W
Add 1 % Water charges on "W" 4.4434
TOTAL 448.78 X
Add GST (multiplying factor 0.1405) on "X" 63.05
TOTAL 511.83 Y
Add 15 % Contractor's profit and overheads on "Y" 76.78
Total 588.61 Z
Add Cess @ 1% on "Z" 5.89
Cost of 10 nos 594.50
Cost of 1 no 59.45
Say 59.50

9.103 Providing and fixing bright finished brass 100


mm mortice latch and lock, ISI marked, with six
levers and a pair of anodised (anodic coating
Details
not lessofthan
cost for 1 lock
grade AC 10 as per IS : 1868)

MATERIAL
7001 Brass 100mm mortice latch and lock with6 levers each 1 210 210.00
7003 without pair of handles 0.00
Pair of Anodised Aluminium lever handles each 1 215 215
for 100mm mortice latch and lock
LABOUR
14 Carpenter 1st class day 0.17 505.17 85.88
9988 Sundries including carriage of materials L.S. 4.55 2.00 9.10
TOTAL 519.98 W
Add 1 % Water charges on "W" 5.1998
TOTAL 525.18 X
Add GST (multiplying factor 0.1405) on "X" 73.79
TOTAL 598.97 Y
Add 15 % Contractor's profit and overheads on "Y" 89.85
Total 688.82 Z
Add Cess @ 1% on "Z" 6.89
Cost of 1 lock 695.71
Say 695.71
695.70
9.104 Providing and fixing aluminium tee channels
(heavy duty)
Details of cost with rollers
for 2m long & stop end in pelmets
as curtain rod.
MATERIAL
7056 Aluminium tee channel (heavy duty) with rollers metre 2 100 200.00
and stop end
562
9999 LABOUR L.S. 2.73 2 5.46
9999 Sundries L.S. 1.43 2 2.86
TOTAL 208.32 W
Add 1 % Water charges on "W" 2.0832
TOTAL 210.40 X
Add GST (multiplying factor 0.1405) on "X" 29.56
TOTAL 239.96 Y
Add 15 % Contractor's profit and overheads on "Y" 35.99
Total 275.95 Z
Add Cess @ 1% on "Z" 2.76
Cost of 2 metre 278.71
Cost of 1 metre 139.36
Say 139.40

9.105 Providing and fixing partition upto ceiling


height
required consisting of G.I. frame
board, including and and
providing
fixing
section ofpower
frame pressed/
work made rollofform
special
G.I. sheet
with zinc coating of 120 gms/
sqm(both side inclusive), consisting of floor
and
havingceiling
equalchannel
flanges50mm of 32 wide
mm and 0.50
mm thick, fixed to the
at the spacing of 610 mm centre floor and ceiling
to centre
with dash fastener of 12.5
meter 50 mm length or suitable anchor mm dia
fastener
plugs andorthe metal
studs screws
48 mm with nylon
wide having
one flange of 34 mm and other
36 mm and 0.50 mm thick fixed vertically flange
within
channel flanges of flooratand
and placed ceiling of 610
a spacing
9.105.1 mmmm
75 centre to thickness
overall centre bypartition
6 mm dia withbolts
12.5 and
mm
nuts,double
thick including
skinfixing of studs
fire rated boardalong both to
conforming
563
ends
IS: of partition
2095: part I fixed flush to wall with
Details of cost for 6.00x3.65m = 21.9 sqm
(Partition Panel)
MATERIAL
7366 Glass reinforced Gyp sum ( GRG) board sqm 43.8 240 10512.00
8.5 mm thick
2x6.00x3.65=43.80sqm
7367 Galvanised M.S. sheet 0.5 mm thick pressed metre 12 57 684.00
channel section of size 50x32 mm
50mm floor and ceiling channel 2x6.00
=12m
7369 Galvanised M.S. sheet 0.50 mm thick pressed metre 40.15 71 2850.65
stud. 48x34x36 mm 48mm stud-72x34x36x0.5mm
(6.00/0.61)+1 = 11x3.65 = 40.15m
7020 All drive screws ( for gypsum board) 100 3.92 58 227.36
[(3.65/0.30)+1]x11x2 = 308 Nos
[(6.00/0.30)+1]x2x2=84
Total = 392
7388 Dash hold fastener 12.5 mm dia, 40 mm each 22 11 242.00
long with 6 mm dia bolt [(6.00/0.61)+1]x2=22
7048 Rawl plug 50 mm (designation 10 no.) each 18 25 450.00
869 [(3.65/0.45)+1]x2= 18 0.00
Plaster of Paris kilogra 19.27 5 96.35
(88/100)x21.9 = 19.27 m
763 Glue kilogra 4.82 75 361.50
(22/100)x21.90=4.82 m
7018 Joint tape roll roll 0.584 100 58.40
(120m roll) (300/100)x21.90/120
= 0.584 Nos
7021 Primer ( for gypsum board) (36/100)x21.90 = 7.88 litre 7.88 85 669.80
1022 litre
Galvanised steel bolts & nuts 6 mm dia and 25 10 Nos 4.4 38 167.2
1211 mmlong round head with slots 11x2x2=44 0.00
G.I. plain washer for seam bolts 100 0.44 32 14.08
9977 Nos
Sundries carriage L.S. 52 2.00 104
9999 Sundries scaffolding L.S. 130 2.00 260.00
Labour for 21.90 sqm.
14 Carpenter 1st class day 6.57 505.17 3318.97
0.3x21.90=6.57
15 Carpenter 2nd class day 2.847 403.67 1149.25
0.13x21.90=2.847
31 Painter day 1.095 403.67 442.02
0.05x21.90=1.095
17 Beldar day 7.665 350.00 2682.75
0.35x21.90=7.665
TOTAL 24290.33 W
Add 1 % Water charges on "W" 242.9033
564 TOTAL 24533.23 X
Add GST (multiplying factor 0.1405) on "X" 3446.92
TOTAL 27980.15 Y
Add 15 % Contractor's profit and overheads on "Y" 4197.02
Total 32177.17 Z
Add Cess @ 1% on "Z" 321.77
Cost for 21.90 sqm 32498.94
Cost for 1 sqm. 1483.97
Say 1484.00

9.105.2 75mm overall thickness partition with 12.5 mm


thick
Detailsdouble
of costskin tapered edged
for 6.00x3.65m = 21.9plain
sqm Gypsum
(Partition
plaster board conforming to IS: 2095: (part I)
Panel)
MATERIAL
2011 (Board with BIS Certification marks)
7009 12.5 mm thick tapered edge plain sqm 43.8 155 6789.00
gypsum plaster board confirming to
IS 2095 (Part I) : 2011.
2x6.00x3.65=43.80sqm
7367 Galvanised M.S. sheet 0.5 mm thick pressed metre 12 57 684.00
channel section of size 50x32 mm
50mm floor and ceiling channel 2x6.00
=12m
7369 Galvanised M.S. sheet 0.50 mm thick pressed metre 40.15 71 2850.65
stud. 48x34x36 mm 48mm stud-72x34x36x0.5mm
(6.00/0.61)+1 = 11x3.65 = 40.15m
7020 All drive screws ( for gypsum board) 100 3.92 58 227.36
[(3.65/0.30)+1]x11x2 = 308 Nos
[(6.00/0.30)+1]x2x2=84
Total = 392
7388 Dash hold fastener 12.5 mm dia, 40 mm each 22 11 242.00
long with 6 mm dia bolt [(6.00/0.61)+1]x2=22
7048 Rawl plug 50 mm (designation 10 no.) each 18 25 450.00
869 [(3.65/0.45)+1]x2= 18 0.00
Plaster of Paris kilogra 19.27 5 96.35
(88/100)x21.9 = 19.27 m
763 Glue kilogra 4.82 75 361.50
(22/100)x21.90=4.82 m
7018 Joint tape roll roll 0.584 100 58.40
(120m roll) (300/100)x21.90/120 = 0.584 Nos
7021 Primer ( for gypsum board) (36/100)x21.90 = 7.88 litre 7.88 85 669.80
1022 litre
Galvanised steel bolts & nuts 6 mm dia and 25 10 Nos 4.4 38 167.2
1211 mmlong round head with slots 11x2x2=44 0.00
G.I. plain washer for seam bolts 100 0.44 32 14.08
Nos
565
9977 Sundries carriage L.S. 52 2.00 104.00
9999 Sundries scaffolding L.S. 130 2.00 260.00
Labour for 21.90 sqm. 0
14 Carpenter 1st class day 6.57 505.17 3318.97
0.3x21.90=6.57
15 Carpenter 2nd class day 2.847 403.67 1149.25
0.13x21.90=2.847
31 Painter day 1.095 403.67 442.02
0.05x21.90=1.095
17 Beldar day 7.665 350.00 2682.75
0.35x21.90=7.665
TOTAL 20567.33 W
Add 1 % Water charges on "W" 205.6733
TOTAL 20773.00 X
Add GST (multiplying factor 0.1405) on "X" 2918.61
TOTAL 23691.61 Y
Add 15 % Contractor's profit and overheads on "Y" 3553.74
Total 27245.35 Z
Add Cess @ 1% on "Z" 272.45
Cost for 21.90 sqm 27517.80
Cost for 1 sqm. 1256.52
Say 1256.50

9.105.3 66mm overall thickness Partition with 8mm


thick
Detailsdouble
of costskin Calcium =Silicate
for 6.00x3.65 21.9 sqmBoard made
with Calcareous & Siliceous materials
(Partition
reinforced Panel)
with cellulose fiber manufactured
MATERIAL
8699 8 mm thick tapered edge calcium silicate board . sqm 43.8 400 17520.00
2x6.00x3.65=43.80sqm 0.00
7367 Galvanised M.S. sheet 0.5 mm thick pressed metre 12 57 684.00
channel section of size 50x32 mm 50mm floor and 0.00
7369 ceiling channel 2x6.00 =12m 0.00
Galvanised M.S. sheet 0.50 mm thick pressed metre 40.15 71 2850.65
stud. 48x34x36 mm 0.00
48mm stud-72x34x36x0.5mm (6.00/0.61)+1 = 0.00
7020 11x3.65 = 40.15m 0.00
All drive screws ( for gypsum board) 100 3.92 58 227.36
[(3.65/0.30)+1]x11x2 = 308 Nos 0.00
[(6.00/0.30)+1]x2x2=84 0.00
Total = 392 0.00
7388 Dash hold fastener 12.5 mm dia, each 22 11 242.00
40 mm long with 6 mm dia bolt 0.00
566 0.00
[(6.00/0.61)+1]x2=22 0.00
7048 Rawl plug 50 mm (designation 10 no.) each 18 25 450.00
869 [(3.65/0.45)+1]x2= 18 0.00
Plaster of Paris kilogra 19.27 5 96.35
(88/100)x21.9 = 19.27 m 0.00
763 Glue kilogra 4.82 75 361.50
(22/100)x21.90=4.82 m 0.00
7018 Joint tape roll roll 0.584 100 58.40
(120m roll) (300/100)x21.90/120 = 0.584 Nos 0.00
7021 Primer ( for gypsum board) (36/100)x21.90 = 7.88 litre 7.88 85 669.80
1022 litre 0.00
Galvanised steel bolts & nuts 6 mm dia and 10 Nos 4.4 38 167.20
25 mmlong round head with slots 0.00
11x2x2=44 0.00
1211 G.I. plain washer for seam bolts 100 0.44 32 14.08
9977 Nos
Sundries carriage L.S. 52 2.00 104.00
9999 Sundries scaffolding L.S. 130 2.00 260.00
Labour for 21.90 sqm. 0.00
14 Carpenter 1st class day 6.57 505.17 3318.97
0.3x21.90=6.57 0.00
15 Carpenter 2nd class day 2.847 403.67 1149.25
0.13x21.90=2.847 0.00
31 Painter day 1.095 403.67 442.02
0.05x21.90=1.095 0.00
17 Beldar day 7.665 350.00 2682.75
0.35x21.90=7.665
TOTAL 31298.33 W
Add 1 % Water charges on "W" 312.9833
TOTAL 31611.31 X
Add GST (multiplying factor 0.1405) on "X" 4441.39
TOTAL 36052.70 Y
Add 15 % Contractor's profit and overheads on "Y" 5407.91
Total 41460.61 Z
Add Cess @ 1% on "Z" 414.61
Cost for 21.90 sqm 41875.22
Cost for 1 sqm. 1912.11
Say 1912.10

9.105.4 66mm overall thickness partition using


8mm thick double
cementboard skin multipurpose
reinforced with cellulose
fibre manufactured through
autoclaving process (High pressure steam
567 cured) as per IS : 14862 with suitable fibre
cement screws
Details of cost for 6.00x3.65 = 21.9 sqm
(Partition Panel)
MATERIAL
237 Multi purpose fibre sqm 43.8 220 9636.00
(high impact poly propelene reinforced) cement
board 8mm thick. 2x6.00x3.65=43.80sqm
7367 Galvanised M.S. sheet 0.5 mm thick pressed metre 12 57 684.00
channel section of size 50x32 mm 50mm floor and
ceiling channel 2x6.00
=12m
7369 Galvanised M.S. sheet 0.50 mm thick pressed metre 40.15 71 2850.65
stud. 48x34x36 mm 48mm stud-72x34x36x0.5mm
(6.00/0.61)+1 = 11x3.65 = 40.15m
7020 All drive screws ( for gypsum board) 100 3.92 58 227.36
[(3.65/0.30)+1]x11x2 = 308 Nos
[(6.00/0.30)+1]x2x2=84
Total = 392
7388 Dash hold fastener 12.5 mm dia, each 22 11 242.00
40 mm long with 6 mm dia bolt
[(6.00/0.61)+1]x2=22
7048 Rawl plug 50 mm (designation 10 no.) each 18 25 450.00
869 [(3.65/0.45)+1]x2= 18 0.00
Plaster of Paris kilogra 19.27 5 96.35
(88/100)x21.9 = 19.27 m
763 Glue kilogra 4.82 75 361.50
(22/100)x21.90=4.82 m
7018 Joint tape roll roll 0.584 100 58.40
(120m roll) (300/100)x21.90/120 = 0.584 Nos
7021 Primer ( for gypsum board) (36/100)x21.90 = 7.88 litre 7.88 85 669.80
1022 litre
Galvanised steel bolts & nuts 6 mm dia and 25 10 Nos 4.4 38 167.2
1211 mmlong round head with slots 11x2x2=44
G.I. plain washer for seam bolts 100 0.44 32 14.08
9977 Nos
Sundries carriage L.S. 52 2.00 104
9999 Sundries scaffolding L.S. 130 2.00 260.00
Labour for 21.90 sqm.
14 Carpenter 1st class day 6.57 505.17 3318.97
0.3x21.90=6.57
15 Carpenter 2nd class day 2.847 403.67 1149.25
0.13x21.90=2.847
31 Painter day 1.095 403.67 442.02
0.05x21.90=1.095
17 Beldar day 7.665 350.00 2682.75
0.35x21.90=7.665
TOTAL 23414.33 W
Add 1 % Water charges on "W" 234.1433
TOTAL 23648.47 X
Add GST (multiplying factor 0.1405) on "X" 3322.61
TOTAL 26971.08 Y
Add 15 % Contractor's profit and overheads on "Y" 4045.66
Total 31016.74 Z
Add Cess @ 1% on "Z" 310.17
Cost for 21.90 sqm 31326.91
Cost for 1 sqm. 1430.45
Say 1430.50
9.105.5 66 mm overall thickness partition using 8
mm thick double skin multipurpose
cement bonded wood particle board
manufactured asbonded
suitable cement per IS: board
14276screws
with
Details of cost for 21.90 sqm
MATERIAL:
243 Multipurpose cement bonded wood particle board sqm 43.8 215 9417.00
7367 8 mm thick 847.46 0.00
Galvanised M.S. sheet 0.5 mm thick pressed metre 12 57 684
7369 channel section of size 50x32 mm 2x6.00 =12m metre 40.15 71 2850.65
Galvanised M.S. sheet 0.50 mm thick pressed stud
: 48x34x36 mm (6.00/0.61)+1 = 11x3.65 = 40.15m
7020 All drive screws ( for gypsum board) 100 nos 3.92 58 227.36
[(3.65/0.30)+1]x11x2 = 308
[(6.00/0.30)+1]x2x2=84
Total = 392
7388 Dash hold fastener 12.5 mm dia, 50 mm each 22 11 242.00
long with 6 mm dia bolt [(6.00/0.61)+1]x2=22
7048 Rawl plug 50 mm (designation 10 nos) each 18 25 450.00
869 [(3.65/0.45)+1]x2= 18 0.00
Plaster of Paris kg 19.27 5 96.35
(88/100)x21.9 = 19.27
763 Glue kg 4.82 75 361.50
(22/100)x21.90=4.82
7018 Joint tape roll roll 0.584 100 58.40
(120m roll) (300/100)x21.90/120 = 0.584 No
7021 Primer ( for gypsum board (36/100x21.90 = 7.88 litre 7.88 85 669.80
1022 litre
Galvanised steel bolts & nuts 6 mm dia and 25 10 Nos 4.4 38 167.2
mm long round head with slots 11x2x2=44
1211 nos=4.40 tens
G.I. plain washer for seam bolts =0 .44 hundreds 100 0.44 32 14.08
9999 Nos 0.00
Sundries carriage L.S 52 2.00 104
9999 Sundries scaffolding Labour for 21.90 sqm. L.S 130 2.00 260.00
14 Carpenter 1 st class day 6.57 505.17 3318.97
0.3x21.90
569 0.00
15 Carpenter 2nd class day 2.847 403.67 1149.25
0.13x21.90
31 Painter day 1.095 403.67 442.02
0.05x21.90
17 Beldar day 7.665 350.00 2682.75
0.35x21.90
TOTAL 23195.33 W
Add 1 % Water charges on "W" 231.9533
TOTAL 23427.28 X
Add GST (multiplying factor 0.1405) on "X" 3291.53
TOTAL 26718.81 Y
Add 15 % Contractor's profit and overheads on "Y" 4007.82
Total 30726.63 Z
Add Cess @ 1% on "Z" 307.27
Cost for 21.90 sqm 31033.90
Cost for 1 sqm. 1417.07
Say 1417.10

9.106 Providing and fixing PTMT handles with


9.106.1 necessary
125x34x24screws etc. complete.
mm weighing not less than 23 gms
Details of cost for ten Nos.
MATERIAL
7512 PTMT handle 125x34x24mm each 10 24 240.00
639 Bright finished or black enamelled mild steel 100 0.4 36 14.40
9977 screws 25 mm Nos
Carriage of materials L.S. 2.73 2 5.46
LABOUR
15 Carpenter 2nd class day 0.06 403.67 24.22
TOTAL 284.08 W
Add 1 % Water charges on "W" 2.8408
TOTAL 286.92 X
Add GST (multiplying factor 0.1405) on "X" 40.31
TOTAL 327.23 Y
Add 15 % Contractor's profit and overheads on "Y" 49.08
Total 376.31 Z
Add Cess @ 1% on "Z" 3.76
Cost of 10 Nos 380.07
Cost of 1 No 38.01
Say 38.00

9.106.2 150x34x24 mm weighing not less than 26


gms
Details of cost for ten Nos.
MATERIAL
7513 PTMT handle 150x34x24mm each 10 24 240.00
639 Bright finished or black enamelled mild steel 100 0.4 36 14.40
9977 screws 25 mm Nos
Carriage of materials L.S. 2.73 2 5.46
LABOUR
15 Carpenter 2nd class day 0.06 403.67 24.22
TOTAL 284.08 W
Add 1 % Water charges on "W" 2.8408
TOTAL 286.92 X
Add GST (multiplying factor 0.1405) on "X" 40.31
TOTAL 327.23 Y
Add 15 % Contractor's profit and overheads on "Y" 49.08
Total 376.31 Z
Add Cess @ 1% on "Z" 3.76
Cost of 10 Nos 380.07
Cost of 1 No 38.01
Say 38.00

9.107 Providing and fixing PTMT Butt hinges with


9.107.1 necessary
75x60x10 mmscrews etc.
fitted complete.
with 5.5 mm dia M.S.
Bright
Details Bar Rod
of cost forweighing
ten Nos. not less than 34 gms
MATERIAL
7514 PTMT butt hinges 75x60x10mm each 10 33 330.00
638 Bright finished or black enamelled mild steel 100 0.6 45 27.00
9977 screws 30 mm Nos
Carriage of materials L.S. 1.82 2 3.64
LABOUR
15 Carpenter 2nd class day 0.14 403.67 56.51
17 Beldar day 0.09 350.00 31.50
TOTAL 448.65 W
Add 1 % Water charges on "W" 4.4865
TOTAL 453.14 X
Add GST (multiplying factor 0.1405) on "X" 63.67
TOTAL 516.81 Y
Add 15 % Contractor's profit and overheads on "Y" 77.52
Total 594.33 Z
Add Cess @ 1% on "Z" 5.94
Cost of 10 Nos 600.27
Cost of 1 No 60.03
Say 60.00

9.107.2 100x75x10 mm fitted with 5.5 mm dia MS


Bright Bar Rod weighing not less than 53 gms
Details of cost for ten Nos.
MATERIAL
7515 PTMT butt hinges 100x75x10mm each 10 43 430.00
637 Bright finished or black enamelled mild steel 100 0.8 60 48.00
9977 screws 40 mm Nos
Carriage of materials L.S. 2.73 2 5.46
LABOUR
15 Carpenter 2nd class day 0.14 403.67 56.51
17 Beldar day 0.09 350.00 31.50
TOTAL 571.47 W
Add 1 % Water charges on "W" 5.7147
TOTAL 577.18 X
Add GST (multiplying factor 0.1405) on "X" 81.09
TOTAL 658.27 Y
Add 15 % Contractor's profit and overheads on "Y" 98.74
Total 757.01 Z
Add Cess @ 1% on "Z" 7.57
Cost of 10 Nos 764.58
Cost of 1 No 76.46
Say 76.50

9.108 Providing and fixing PTMT Tower Bolts


with 12 mmscrews
necessary one pieceetc.,rod inside and
complete.
9.108.1 152x42x18 mm weighing not less than 60
gms
Details of cost for ten Nos.
MATERIAL
7516 PTMT Tower bolt 152x42x18mm each 10 48 480.00
572
638 Bright finished or black enamelled mild steel 100 0.6 45 27.00
9977 screws 30 mm Nos
Carriage of materials L.S. 2.73 2 5.46
LABOUR
15 Carpenter 2nd class day 0.08 403.67 32.29
TOTAL 544.75 W
Add 1 % Water charges on "W" 5.4475
TOTAL 550.20 X
Add GST (multiplying factor 0.1405) on "X" 77.30
TOTAL 627.50 Y
Add 15 % Contractor's profit and overheads on "Y" 94.12
Total 721.62 Z
Add Cess @ 1% on "Z" 7.22
Cost of 10 Nos 728.84
Cost of 1 No 72.88
Say 72.90

9.108.2 202x42x18 mm weighing not less than 78


gms of cost for ten Nos.
Details
MATERIAL
7517 PTMT Tower bolt 202x42x18mm each 10 67 670.00
638 Bright finished or black enamelled mild steel 100 0.8 45 36.00
9977 screws 30 mm Nos
Carriage of materials L.S. 2.73 2 5.46
LABOUR
15 Carpenter 2nd class day 0.1 403.67 40.37
TOTAL 751.83 W
Add 1 % Water charges on "W" 7.5183
TOTAL 759.35 X
Add GST (multiplying factor 0.1405) on "X" 106.69
TOTAL 866.04 Y
Add 15 % Contractor's profit and overheads on "Y" 129.91
Total 995.95 Z
Add Cess @ 1% on "Z" 9.96
Cost of 10 Nos 1005.91
Cost of 1 No 100.59
Say 100.60

9.109 Providing and fixing PTMT door catcher of


length 72 mmwashers
with suitable and dia.weighing
of 42 mmnot less
than 33
Details of gms
cost for ten Nos.
MATERIAL
7518 PTMT door catcher 72x42mm each 10 24 240.00
639 Bright finished or black enamelled mild steel 100 0.2 36 7.20
9977 screws 25 mm Nos
Carriage of materials L.S. 2.73 2 5.46
LABOUR
14 Carpenter 1st class day 0.03 505.17 15.16
TOTAL 267.82 W
Add 1 % Water charges on "W" 2.6782
TOTAL 270.50 X
Add GST (multiplying factor 0.1405) on "X" 38.00
TOTAL 308.50 Y
Add 15 % Contractor's profit and overheads on "Y" 46.27
Total 354.77 Z
Add Cess @ 1% on "Z" 3.55
Cost of 10 Nos 358.32
Cost of 1 No 35.83
Say 35.80

9.11 Providing and fixing Bamboo jaffery/


fencing
mm dia consisting
(Average) ofhalfsuperior qualityplaced
cut bamboo 25
vertically and fixed
three numbers together
horizontal with members
running
of hollock
section woodmm,
50X25 in scantling ofnails and G.I
fixed with
wire ondirection
as per existing of
support complete
Engineer-in-charge.
Details of cost for a bamboo jaffery of size
1.00m x 2.10m = 2.10 sqm
MATERIAL
Bamboo 25mm of 100/ 2.50 = 40 nos
Half cut off = 40/2 .=20 nos. x 2.10 = 42.00m
Add wastage @ 15% = 6.30 m
Total = 48.30m
Rate of Bamboo 25 mm dia 2.5 metre long for one
score i.e. 20nos is Rs. 192 for 48.30m qty 48.30 /(
305 2.5 * 20) = 0.966
Bamboo 25 mm dia 2.5 metre long score 0.966 400 386.4
9977 Carriage of Bamboo L.S. 4.83 2 9.66
2466 Hollock wood in scantling 10 0.394 350 137.90
3 nos. (1.00 x 0.05 x 0.05) = 0.00375 cm cudm
Add wastage @ 5% = 0.00019 cm
Total = 0.00394 cm or 3.94 cudm
2204 Carriage of Timber cum 0.00394 121.29 0.48
574
9999 Nails and wire L.S. 20.25 2 40.50
LABOUR
15 Carpenter 2nd class day 0.25 403.67 100.92
17 Beldar day 0.25 350.00 87.50
9999 Sundries L.S. 10.05 2 20.10
TOTAL 783.46 W
Add 1 % Water charges on "W" 7.8346
TOTAL 791.29 X
Add GST (multiplying factor 0.1405) on "X" 111.18
TOTAL 902.47 Y
Add 15 % Contractor's profit and overheads on "Y" 135.37
Total 1037.84 Z
Add Cess @ 1% on "Z" 10.38
Cost for 2.10 sqm 1048.22
Cost for 1 sqm 499.15
Say 499.20

9.111 Providing and fixing wooden moulded


corner
the beading
junction of triangular
of panelling etc. shape to
with iron
screws, plugs and priming coat
unexposed surface etc. complete 2ndon
9.111.1 class
50x50teak
mm wood.
(base and height)
Details of cost for beading = 5.00 m
MATERIAL
Teak wood 2nd class in plan ks
500 x 5 x 5 mm / 2 = 0.000625 cum Add wastage
@ 10% = 0.00063 total = 0.00688 cum say 6.88
1190 cudm
Second class teak wood in planks 10 0.688 791 544.21
2204 cudm
Carriage of Timber cum 0.00688 121.29 0.83
637 Bright finished or black enamelled mild 100 0.06 60 3.60
steel screws 40 mm Nos
Priming coat
Area 5.0 x (.05 +.05) = 0.50 sqm
13.50.1 Rate as per item no 13.50.1 of SH : Finishing sqm 0.5 38.95 19.48 A
LABOUR
For plaining, fixing & making design
14 Carpenter 1st class day 0.75 505.17 378.88
TOTAL 947.00 W
Add 1 % Water charges on "W-A" 927.52 9.2752
TOTAL X
Add GST (multiplying factor 0.1405) on "X-A" 936.80 131.62
TOTAL Y
Add 15 % Contractor's profit and overheads on "Y- 1068.42 160.26
A"
Total Z
Add Cess @ 1% on "Z-A" 1228.68 12.29
Cost for 5 metre 1260.45
Cost for 1 metre 252.09
Say 252.10

9.112 Providing and fixing 2nd class teak wood


lipping/
Details ofmoulded beading
cost for 10.00 m or taj beading of size
18X5 mm fixed with wooden adhesive of
approved quality and screws/ nails on the
MATERIAL
8719 2nd class teak wood lipping/ moulded metre 10 28 280.00
beadibg or Taj beading of size 18X5mm
LABOUR
15 Carpenter 2nd class day 0.25 403.67 100.92
17 Beldar day 0.25 350.00 87.50
TOTAL 468.42 W
Add 1 % Water charges on "W" 4.6842
TOTAL 473.10 X
Add GST (multiplying factor 0.1405) on "X" 66.47
TOTAL 539.57 Y
Add 15 % Contractor's profit and overheads on "Y" 80.94
Total 620.51 Z
Add Cess @ 1% on "Z" 6.21
Cost for 10 metre 626.72
Cost for 1 metre 62.67
Say 62.70

9.113 Providing and fixing bright finished 100 mm


mortice lock with
pair of handles of6approved
levers without
quality for
aluminium
etc complete door, withdirection
as per necessary screws
of Engineer-
in-charge.
Details of cost for 1 no.
8716 100 mm mostice lock with 6 levers for aluminium each 1 375 375.00
door.
LABOUR
14 Carpenter 1st class day 0.13 505.17 65.67
576
9999 Sundries( screws, carriage etc) L.S. 2.6 2.00 5.20
TOTAL 445.87 W
Add 1 % Water charges on "W" 4.4587
TOTAL 450.33 X
Add GST (multiplying factor 0.1405) on "X" 63.27
TOTAL 513.60 Y
Add 15 % Contractor's profit and overheads on "Y" 77.04
Total 590.64 Z
Add Cess @ 1% on "Z" 5.91
Cost for 1 no 596.55
Say 596.5

9.114 Providing and fixing magnetic catcher of


approved quality
robe shutters, in cupboard
including fixing /with
ward
9.114.1 necessary screwstype
Triple strip vertical etc. complete.
Details of cost for 1 no.
MATERIAL
8714 Magenatic catcher triple strip verticle type. each 1 24 24.00
9999 Sundries including screws and fixing charges. L.S. 2.6 2.00 5.20
TOTAL 29.20 W
Add 1 % Water charges on "W" 0.292
TOTAL 29.49 X
Add GST (multiplying factor 0.1405) on "X" 4.14
TOTAL 33.63 Y
Add 15 % Contractor's profit and overheads on "Y" 5.04
Total 38.67 Z
Add Cess @ 1% on "Z" 0.39
Cost for 1 no 39.06
Cost for 1 no 39.1
Say 39.10

9.114.2 Double strip (horizontal type)


Details of cost for 1 no.
MATERIAL
8715 Magenatic catcher double strip horizontal type. each 1 18 18.00
9999 Sundries including screws and fixing charges. L.S. 2.6 2.00 5.20
TOTAL 23.20 W
Add 1 % Water charges on "W" 0.232
TOTAL 23.43 X
Add GST (multiplying factor 0.1405) on "X" 3.29
TOTAL 26.72 Y
577 4.01
Add 15 % Contractor's profit and overheads on "Y" 30.73 Z
Total 0.31
Add Cess @ 1% on "Z" 31.04
Cost for 1 no 31.04
Say 31.00

9.115 Providing and fixing powder coated telescopic


drawer
Details ofchannels 300
cost for 10 mm long with necessary
sets.
screws etc. complete as per directions of
MATERIAL
Engineer- in-charge.
8703 Telescopic drawer channels 300mm long . set 10 230 2300.00
9977 CARRIAGE L.S. 19.5 2 39.00
9999 Sundries including screws and fixing charges. L.S. 100.1 2.00 200.20
TOTAL 2539.20 W
Add 1 % Water charges on "W" 25.392
TOTAL 2564.59 X
Add GST (multiplying factor 0.1405) on "X" 360.33
TOTAL 2924.92 Y
Add 15 % Contractor's profit and overheads on "Y" 438.74
Total 3363.66 Z
Add Cess @ 1% on "Z" 33.64
Cost for 10 sets 3397.30
Cost for 1 set 339.73
Say 339.70

9.116 Providing and fixing sliding arrangement in


racks/
Details cupboards/cabinets
of cost for 1 No. shutter by with
stainless steel rollers to run inside C or E
MATERIAL
aluminium channel section (The payment of C
8704 Stainless steel roller for sliding arrangment in each 1 9 9.00
racks/ cupboards/ cabinets shutter .
9999 Labour for fixing L.S. 1.04 2 2.08
TOTAL 11.08 W
Add 1 % Water charges on "W" 0.1108
TOTAL 11.19 X
Add GST (multiplying factor 0.1405) on "X" 1.57
TOTAL 12.76 Y
Add 15 % Contractor's profit and overheads on "Y" 1.91
Total 14.67 Z
Add Cess @ 1% on "Z" 0.15
Cost for 1 No. 14.82
Cost for 1 No. 14.82
Say 14.80

9.117 Providing and fixing factory made uPVC


door frame
sections madeanofoverall
having uPVC dimension
extruded as
below (tolerance
thickness 2.0 mm±1mm), with wall
(± 0.2 mm), corners of
the door frame to be Jointed with
galvanized brackets and stainless steel
screws,
welded. joints mitred
The hinge andvertical
side Plasticof the
frames
tube reinforced
of size bymm
19 X 19 galvanized
and 1mm M.S.
(± 0.1
mm) wall steel
stainless thickness and
hinges 3 nos.
fixed to the frame
complete as per manufacturer’s
specification and direction of Engineer- in-
9.117.1 charge
Extruded section profile size 48x40 mm
Detail of cost for 5 metre
MATERIAL
8010 48mmX40mmX1.5mm thick Factory made door metre 5 125.79 628.95
frame of PVC extruded sections in white, grey or
wooden finish
LABOUR
41 Carpenter (average) day 0.15 403.67 60.55
17 Beldar day 0.15 350.00 52.50
9999 Sundries L.S. 4.68 2 9.36
TOTAL 751.36 W
Add 1 % Water charges on "W" 7.5136
TOTAL 758.87 X
Add GST (multiplying factor 0.1405) on "X" 106.62
TOTAL 865.49 Y
Add 15 % Contractor's profit and overheads on "Y" 129.82
Total 995.31 Z
Add Cess @ 1% on "Z" 9.95
Cost of 5 metre 1005.26
Cost for 1 metre 201.05
Say 201.10

9.117.2 Extruded section profile size 42x50 mm


Detail of cost for 5 metre
MATERIAL
8705 50mmX42mmX2mm thick Factory made door metre 5 160 800.00
frame of PVC extruded sections in white, grey or
wooden finish
LABOUR
41 Carpenter (average) day 0.15 403.67 60.55
17 Beldar day 0.15 350.00 52.50
579
9999 Sundries L.S. 4.68 2 9.36
TOTAL 922.41 W
Add 1 % Water charges on "W" 9.2241
TOTAL 931.63 X
Add GST (multiplying factor 0.1405) on "X" 130.89
TOTAL 1062.52 Y
Add 15 % Contractor's profit and overheads on "Y" 159.38
Total 1221.90 Z
Add Cess @ 1% on "Z" 12.22
Cost of 5 metre 1234.12
Cost for 1 metre 246.82
Say 246.80

9.118 Providing and fixing to existing door


9.118.1 frames.
24 mm thick factory made PVC door
shutters made of styles and rails of a
uPVC hollow section of size 59x24 mm
and
with wall thickness
inbuilt edging on 2 mm
both(±sides.
0.2 mm)The
styles and rails mitred and
corners by means of M.S. galvanised/joint at the
plastic
having brackets of size1.0
wall thickness 75x220
mm and mmstainless
steel screws.
shutter The styles
reinforced of the galvanised
by inserting
M.S.(±tube
mm 0.1 of
mm)sizewall
20x20 mm and
thickness. 1 lock
The
rail made up of 'H' section, a
hollow section of size 100x24 mm and 2 uPVC
mm (± 0.2 mm)
the shutter styleswall
by thickness,
means of fixed to
plastic/galvanised
frame filled with a uPVC M.S. 'U' cleats. The
multi-chambered
shutter
single panel over
of size
mm, having all not less than
thickness 620mm
of 20
and
The 1 mm (±filled
panels 0.1 vertically
mm) wall andthickness.
tie bar at
two places by inserting horizontally
mm galvanised M.S. rod and fastened 6 with
nuts and washers,
manufacturer's complete and
specification as perdirection
of Engineer-in-charge.
and bathroom door shutter). (For W.C.
Detail of cost for one door shutter
2.20x1.08m = 2.38 sqm
MATERIAL
8001 24 mm thick Factory made shutters with frame, sqm 2.38 1085.93 2584.51
rails and panels of PVC extruded
sections in white, grey or wooden finish
580

LABOUR
41 Carpenter (average) day 0.4 403.67 161.47
17 Beldar day 0.4 350.00 140.00
9999 Sundries L.S. 20.36 2.00 40.72
TOTAL 2926.70 W
Add 1 % Water charges on "W" 29.267
TOTAL 2955.97 X
Add GST (multiplying factor 0.1405) on "X" 415.31
TOTAL 3371.28 Y
Add 15 % Contractor's profit and overheads on "Y" 505.69
Total 3876.97 Z
Add Cess @ 1% on "Z" 38.77
Cost of 2.38 sqm 3915.74
Cost of 1 sqm 1645.27
Say 1645.30

9.118.2 30 mm thick factory made Polyvinyl


Chloride
and rails (PVC) doorhollow
of a uPVC shuttersection
made ofof styles
size
60x30 mm and wall thickness
(± 0.2 mm), with inbuilt decorative2 mm
moulding edgingand
and rails mitred on one
joint side.
at theThe stylesby
corners
means of M.S. galvanised/ plastic
brackets of size 75x220 mm having wall
thickness
screws. The 1.0styles
mm and stainless
of the shuttersteel
reinforced
by inserting galvanised M.S. tube
of size 25x20 mm and 1 mm (± 0.1 mm)
wall thickness.
'H' section, The lock
a uPVC hollowrailsection
made up of
of size
100x30
wall mm and
thickness 2 mm
fixed (± 0.2
to the mm)styles by
shutter
means
'U' of plastic/
cleats. galvanised
The shutter M.S. with a
frame filled
uPVC multi-chambered single
of size not less than 620 mm, having panel over
all
0.1thickness
mm) wall of 20 mm and
thickness . The1 panels
mm (± filled
vertically and tie bar at
inserting horizontally two places
6 mm by
galvanised
M.S. rod and fastened with nuts and
washers, complete as per
manufacturer's
Engineer-in-charge. specification and
direction of
Detail of cost for one door shutter
2.20x1.08m = 2.38 sqm
MATERIAL
8002 30 mm thick Factory made shutters with frame, sqm 2.38 1248.82 2972.19
rails and panels of PVC extruded
sections in white, grey or wooden finish
LABOUR
41 Carpenter (average) day 0.4 403.67 161.47
17 Beldar day 0.4 350.00 140.00
9999 Sundries L.S. 20.36 2.00 40.72
Total 3314.38 W
Add 1 % Water charges on "W" 33.1438
TOTAL 3347.52 X
Add GST (multiplying factor 0.1405) on "X" 470.33
TOTAL 3817.85 Y
Add 15 % Contractor's profit and overheads on "Y" 572.68
Total 4390.53 Z
Add Cess @ 1% on "Z" 43.91
Cost of 2.38 sqm 4434.44
Cost of 1 sqm 1863.21
Say 1863.20

9.118.3 25 mm thick PVC flush door shutters made


out of a one
extruded PVC piece Multiofchamber
section the size of 762
mm X 25 mmwith
requirement or less as per wall thickness
an average
of 1 of
cap mm (± 23x10
size 0.3 mm).mmPVCare foam end on
provided
both vertical edges to ensure the
thickness of 25 mm. M.S. tube having overall
dimensions
(± 0.1 mm) is 19inserted
mm x 19 mm the
along andhinge
1.0 mm
side
of the door. Core of the door
shutter should be filled with High Density
Polyurethane
Bottom edgesfoam.of theThe Topare
shutter & covered
with an end-cap of the size 25 mm X
11 mm. Door shutter shall be reinforced
with
as perspecial polymeric specification
manufacturer’s reinforcements and
direction of Engineer-in-charge
up necessary hardware and fixtures. to take
Stickers
hardwareindicating the locations
will be pasted of
at appropriate
places
Detail of cost for one door shutter
2.20x1.08m = 2.38 sqm
MATERIAL
8706 25mm thick factory made PVC flash foor shutter i/c sqm 2.38 1700 4046.00
carriage.
LABOUR
41 Carpenter (average) day 0.4 403.67 161.47
17 Beldar day 0.4 350.00 140.00
9999 Sundries L.S. 20.36 2.00 40.72
TOTAL 4388.19 W
Add 1 % Water charges on "W" 43.8819
TOTAL 4432.07 X
Add GST (multiplying factor 0.1405) on "X" 622.71
TOTAL 5054.78 Y
Add 15 % Contractor's profit and overheads on "Y" 758.22
Total 5813.00 Z
582 58.13
Add Cess @ 1% on "Z" 5871.13
Cost of 2.38 sqm 2466.86
Cost of 1 sqm 2466.90
Say

9.119 Providing and fixing factory made P.V.C.


door frame of size
wall thickness of 5 50x47
mm, made mm with a
out of
extruded
mitred at 5mm rigid
corners PVC
and foam
joined sheet,
with 2 Nos of
150 mm long brackets of 15x15 mm
M.S. square tube, the vertical door frame
profiles
mm M.S. tosquare
be reinforced
tube of with 19x19 EPDM
19 gauge,
rubber
provided gasket weather
through out theseal to beThe door
frame.
frame to be fixed
M.S. screws to themm
of 65/100 wallsize,
usingcomplete
as
andper manufacturer’s
direction of Engineer-specification
in-Charge.
Details of cost for one door frame of 5 metre
MATERIAL
8011 Factory made door frame PVC extruded sheet i/c metre 5 251.58 1257.90
carriage
LABOUR
41 Carpenter (average) day 0.15 403.67 60.55
17 Beldar day 0.15 350.00 52.50
9999 Sundries L.S. 7.8 2.00 15.60
TOTAL 1386.55 W
Add 1 % Water charges on "W" 13.8655
TOTAL 1400.42 X
Add GST (multiplying factor 0.1405) on "X" 196.76
TOTAL 1597.18 Y
Add 15 % Contractor's profit and overheads on "Y" 239.58
Total 1836.76 Z
Add Cess @ 1% on "Z" 18.37
Cost of 5 metres 1855.13
Cost of 1 metre 371.03
Say 371.00

9.120 Providing and fixing factory made panel


PVC
madedoorout ofshutter consisting
M.S. tubes of 19ofgauge
frame
thickness
styles andand 15x15sizemmof 19
for mm
top &x 19 mm for
bottom
rails.
steel M.S.
primersframe shall have
of approved a coat
make andof
manufacture.
mm thick heatM.S. framePVC
moulded covered with 5 of
'C' channel
size
out of30which
mm thickness,
50 mm shall 70 be
mm width
flat and 20
mmboth
on shallside
be tapered
forming in 45 degree
styles and 5 mm angle
thick, 95
which 75 mm
mm wideshall PVC
be flatsheet
and out
20 mmof shall
be tapered in 45 degree on the
side to form top and bottom rail and 115 inner
mm
mm wide PVC
shall be flatsheet outmm
and 20 of which 75
shall be
9.120.1 tapered
30 mm thickon both
plain sides
PVC doorto form lock rail.
shutters
Top, bottom and lock rails shall
Details of cost for one door shutter
be
provided both side of the panel. 10 mm (5
2.20x1.08m = 2.38 sqm
MATERIAL
8003 Factory made PVC rigid foam panelled shutter i/c sqm 2.38 1547.45 3682.93
8100 carriage 0.00
Powder coated M.S. butt hinges 10 Nos 0.4 123 49.2
100mm X58mmX1.9mm
637 Bright finished or black enamelled mild steel 100 0.48 60 28.80
640 screws 40 mm Nos
Bright finished or black enamelled mild 100 0.08 30 2.4
steel screws 20 mm Nos
LABOUR
41 Carpenter (average) day 0.4 403.67 161.47
17 Beldar day 0.4 350.00 140.00
9999 Sundries L.S. 20.36 2.00 40.72
TOTAL 4105.52 W
Add 1 % Water charges on "W" 41.0552
TOTAL 4146.58 X
Add GST (multiplying factor 0.1405) on "X" 582.59
TOTAL 4729.17 Y
Add 15 % Contractor's profit and overheads on "Y" 709.37
Total 5438.54 Z
Add Cess @ 1% on "Z" 54.39
Cost of 2.38 sqm 5492.93
Cost of 1 sqm 2307.95
Say 2308.00

9.120.2 30 mm thick pre laminated PVC door shutters


Details of cost for one door shutter
2.20x1.08m = 2.38 sqm
MATERIAL
8004 Factory made PVC rigid foam panelled shutter as sqm 2.38 1547.45 3682.93
8100 per IS : 4020 i/c carriage 0.00
Powder coated M.S. butt hinges 10 Nos 0.4 123 49.2
100mm X58mmX1.9mm
637 Bright finished or black enamelled mild steel 100 0.48 60 28.80
640 screws 40 mm Nos
Bright finished or black enamelled mild 100 0.08 30 2.4
steel screws 20 mm Nos
LABOUR
41 Carpenter (average) day 0.4 403.67 161.47
17 Beldar day 0.4 350.00 140.00
9999 Sundries L.S. 20.36 2.00 40.72
TOTAL 4105.52 W
Add 1 % Water charges on "W" 41.0552
TOTAL 4146.58 X
Add GST (multiplying factor 0.1405) on "X" 582.59
TOTAL 4729.17 Y
Add 15 % Contractor's profit and overheads on "Y" 709.37
Total 5438.54 Z
Add Cess @ 1% on "Z" 54.39
Cost of 2.38 sqm 5492.93
Cost of 1 sqm 2307.95
Say 2308.00

9.121 Providing and fixing Fiber Glass


Reinforced
resistant gradeplastic (FRP) Door
unsaturated Framesresin
polyester of
crosssection
and chopped
Details
90 mm
of cost format.
x 45 mm
Doorframe
one door frame having
of 5laminate
metre
single
rebate
shall beof232
mm mm x 15
thick andmm to receive
shall be filled with
MATERIAL
suitable wooden block in all the three legs.
8707 Factory made glass reinforced plastic door frame metre 5 467 2335.00
90x45 mm i/c carriage.
LABOUR
41 Carpenter (average) day 0.15 403.67 60.55
17 Beldar day 0.15 350.00 52.50
9999 Sundries L.S. 7.8 2.00 15.60
TOTAL 2463.65 W
Add 1 % Water charges on "W" 24.6365
TOTAL 2488.29 X
Add GST (multiplying factor 0.1405) on "X" 349.60
TOTAL 2837.89 Y
Add 15 % Contractor's profit and overheads on "Y" 425.68
Total 3263.57 Z
Add Cess @ 1% on "Z" 32.64
Cost of 5 metres 3296.21
Cost of 1 metre 659.24
Say 659.20

9.122 Providing and fixing to existing door


9.122.1 frames.
30 mm thick Glass Fibre Reinforced Plastic
(FRP) panelled
required doorapproved
colour and shutter ofbrand and
manufacture, made with
retardant grade unsaturated fire polyester
-
resin, moulded
laminate to 3 mm
for forming thick
hollow FRP
rails and styles,
with wooden frame and suitable
blocks of seasoned wood inside at
required places
monolithically for 5fixing
with of fittings,
mm thick FRP cast
laminate for panels
14856, including conforming
fixing to frames. to IS:
Details of cost for one door shutter
2.20x1.08m = 2.38 sqm
MATERIAL
8708 30 mm thick factory madeglass fiber reinforced sqm 2.38 2326 5535.88
plastic panel door shutter i/c carriage.
8100 Powder coated M.S. butt hinges 10 Nos 0.4 123 49.20
100mm X58mmX1.9mm
637 Bright finished or black enamelled mild steel 100 0.48 60 28.80
640 screws 40 mm Nos
Bright finished or black enamelled mild 100 0.08 30 2.4
steel screws 20 mm Nos
LABOUR
41 Carpenter (average) day 0.4 403.67 161.47
17 Beldar day 0.4 350.00 140.00
9999 Sundries L.S. 20.36 2.00 40.72
TOTAL 5958.47 W
Add 1 % Water charges on "W" 59.5847
TOTAL 6018.05 X
Add GST (multiplying factor 0.1405) on "X" 845.54
TOTAL 6863.59 Y
Add 15 % Contractor's profit and overheads on "Y" 1029.54
Total 7893.13 Z
Add Cess @ 1% on "Z" 78.93
Cost of 2.38 sqm 7972.06
Cost of 1 sqm 3349.61
Say 3349.60

9.122.2 30 mm thick Fiberglass Reinforced


Plastic(F.R.P.)
different plain and flush doorfinish
wood shutter in with
made
fire retardant
polyester resin,grade unsaturated
moulded to 3 mm thick
FRP laminate all around,
wooden blocks inside at requiredwith suitable
places
for fixing of fittings and polyurethane
foam (PUF)/ Polystyrene foam to be used
as fillerpanel,
hollow material throughout
casted the
monolithically with
testing parameters of F.R.P. laminate
conforming to table - 3 of IS: 14856,
complete
charge. as per direction of Engineer-in-
Details of cost for one door shutter
2.20x1.08m = 2.38 sqm
MATERIAL
8730 30 mm thick factory made glass fiber reinforced sqm 2.38 2675 6366.50
plastic flush door shutter i/c carriage.
8100 Powder coated M.S. butt hinges 10 Nos 0.4 123 49.20
100mm X58mmX1.9mm
637 Bright finished or black enamelled mild steel 100 0.48 60 28.80
640 screws 40 mm Nos
Bright finished or black enamelled mild 100 0.08 30 2.4
steel screws 20 mm Nos
LABOUR
41 Carpenter (average) day 0.4 403.67 161.47
17 Beldar day 0.4 350.00 140.00
9999 Sundries L.S. 20.36 2.00 40.72
TOTAL 6789.09 W
Add 1 % Water charges on "W" 67.8909
TOTAL 6856.98 X
Add GST (multiplying factor 0.1405) on "X" 963.41
TOTAL 7820.39 Y
Add 15 % Contractor's profit and overheads on "Y" 1173.06
Total 8993.45 Z
Add Cess @ 1% on "Z" 89.93
Cost of 2.38 sqm 9083.38
Cost of 1 sqm 3816.55
Say 3816.60

9.123 Providing and fixing factory made door


frame (single
single rebate) made
piece extruded out offoam
solid PVC
profile
structure having smooth outercellular
with homogenous fine integral skin
having 62 mm width & 32 mm
thickness, frame will be mitred & Jointed
with self38driven
of size mm xself
4 mmtapping
& PVC screws
solvent
cement, including fixing the frame to wall
with suitable dia & length anchor fastener
as
andper manufacturer's
direction specification
of Engineer-in-charge.
Details of cost for one door frame of 5 metre
MATERIAL
8710 Factory made solid PVC door frame 60 x 30mm i/c metre 5 315 1575.00
carriage.
LABOUR
41 Carpenter (average) day 0.15 403.67 60.55
17 Beldar day 0.15 350.00 52.50
9999 Sundries L.S. 7.8 2.00 15.60
TOTAL 1703.65 W
Add 1 % Water charges on "W" 17.0365
TOTAL 1720.69 X
Add GST (multiplying factor 0.1405) on "X" 241.76
TOTAL 1962.45 Y
Add 15 % Contractor's profit and overheads on "Y" 294.37
Total 2256.82 Z
Add Cess @ 1% on "Z" 22.57
Cost of 5 metres 2279.39
Cost of 1 meter 455.88
Say 455.90

9.124 Providing and fixing factory made 30 mm


thick
foam door shutter
profile. made &
The styles ofrails
solidshall
PVCbe of
size 75 mm
thickness x 30 The
5 mm. mm styles,
having top
wall& bottom
rails shall have
thickness of 15 onemm side wall extruded on
integrally
the hinge
better screwsideholding
of the power.
profile for
The styles and
rails shall be reinforced
tubes of size 33 mm x 17 mmx with M.S.1 mm,
painted with primer , all four
reinforcement to be welded or sealed. corners of
Solid
type) PVC
will beextruded
set inside bidding (pushand
the styles fit the
rails
piecewith a cavity,
extruded 5 mmto receive
PVC sheetsingleas panel.
The styles and rails will be mitred
cut and joint with the help of PVC solvent
cement
screws. & self driven
Single piece self tapping
extruded solid PVC
lock rail of size 100 mm x 30
wall thickness 5 mm & 15 mm integrally mm with
extruded in the middle of the lock rail
& fixed with styles with the help of PVC
solvent
tapping cement
screws of& self
sizedriven
100 mm selfx 8 mm
complete as per
specifications andmanufacturer's
direction of Engineer-in-
9.124.1 charge.
Non decorative finish
Details of cost for one door shutter
2.20x1.08m = 2.38 sqm
MATERIAL
8712 30 mm thick factory made solid PVC profile sqm 2.38 2000 4760.00
panelled door single piece extruded profile non
8100 decorative finish. 0.00
Powder coated M.S. butt hinges 10 Nos 0.4 123 49.2
100mm X58mmX1.9mm
637 Bright finished or black enamelled mild steel 100 0.48 60 28.80
640 screws 40 mm Nos
Bright finished or black enamelled mild 100 0.08 30 2.4
steel screws 20 mm Nos
LABOUR
41 Carpenter (average) day 0.4 403.67 161.47
17 Beldar day 0.4 350.00 140.00
9999 Sundries L.S. 20.36 2.00 40.72
TOTAL 5182.59 W
Add 1 % Water charges on "W" 51.8259
TOTAL 5234.42 X
Add GST (multiplying factor 0.1405) on "X" 735.44
TOTAL 5969.86 Y
Add 15 % Contractor's profit and overheads on "Y" 895.48
Total 6865.34 Z
Add Cess @ 1% on "Z" 68.65
Cost of 2.38 sqm 6933.99
Cost of 1 sqm 2913.44
Say 2913.40

9.124.2 Decorative finish (both side wood grained


finish)
Details of cost for one door shutter
2.20x1.08m = 2.38 sqm
MATERIAL
8709 30 mm thick factory made solid PVC profile sqm 2.38 2100 4998.00
panelled door single piece extruded profile
decorative finish (wood grain printed on both side)
8100 Powder coated M.S. butt hinges 10 Nos 0.4 123 49.20
100mm X58mmX1.9mm
637 Bright finished or black enamelled mild steel 100 0.48 60 28.80
640 screws 40 mm Nos
Bright finished or black enamelled mild 100 0.08 30 2.4
steel screws 20 mm Nos
LABOUR
41 Carpenter (average) day 0.4 403.67 161.47
17 Beldar day 0.4 350.00 140.00
9999 Sundries L.S. 20.36 2.00 40.72
TOTAL 5420.59 W
Add 1 % Water charges on "W" 54.2059
TOTAL 5474.80 X
Add GST (multiplying factor 0.1405) on "X" 769.21
TOTAL 6244.01 Y
Add 15 % Contractor's profit and overheads on "Y" 936.60
Total 7180.61 Z
Add Cess @ 1% on "Z" 71.81
Cost of 2.38 sqm 7252.42
Cost of 1 sqm 3047.23
Say 3047.20

9.125 Providing and fixing PVC rigid foam sheet


1 mm thick
shutters on existing
(bathroom anddoor
W.C. doors) using
synthetic rubber based adhesive.
Details of cost for 1.0x0.3m = 0.3 sqm
MATERIAL
PVC rigid foam shet 1mm thick = 0.30 sqm
Add wastage @ 10% = 0.03 sqm
8006 Factory made PVC rigid foam sheet sqm 0.33 155.8 51.41
1mm thick
PVC rigid foam sheet1mm thick = 0.30 sqm
Add wastage @ 10% = 0.03 sqm Total = 0.33 sqm
9999 Rubber adhesive L.S. 21.84 2 43.68
LABOUR
14 Carpenter 1st class day 0.11 505.17 55.57
17 Beldar day 0.14 350.00 49.00
30 Mistry day 0.02 505.17 10.10
TOTAL 209.76 W
Add 1 % Water charges on "W" 2.0976
TOTAL 211.86 X
Add GST (multiplying factor 0.1405) on "X" 29.77
TOTAL 241.63 Y
Add 15 % Contractor's profit and overheads on "Y" 36.24
Total 277.87 Z
Add Cess @ 1% on "Z" 2.78
Cost of 0.30 sqm 280.65
Cost of 1 sqm 935.49
Say 935.50

9.126 Providing and fixing 12 mm thick panelling


or
or panelling and glazed
panelled and glazingshutters
in panelled
for doors,
windows and clerestory windows
(area of opening for panel inserts
excluding portion inside
to be measured). grooves
Panelling or rebates
for panelled or
panelled and glazed
to 40 mm thick. shutters 25 mm
9.126.1 Marine plywood conforming to IS: 710
Details of cost for shutters of a door with 2/ 3rd
panelling 200x108cm = 2.16sqm.
Panel area = 4x45.1x36.55cm = 0.66sqm.
MATERIAL
Plywood 4x47.2x38.65cm = 0.73sqm+ Add for
wastage @ 10% = 0.07sqm.
Total = 0.80 sqm.
8724 12mm thick marine plywood conforming to IS:710 sqm 0.8 695 556.00
9977 Carriage of Plywood L.S. 1.82 2 3.64
LABOUR
14 Carpenter 1st class day 0.57 505.17 287.95
9999 Sundries L.S. 4.42 2.00 8.84
TOTAL 856.43 W
Add 1 % Water charges on "W" 8.5643
TOTAL 864.99 X
Add GST (multiplying factor 0.1405) on "X" 121.53
TOTAL 986.52 Y
Add 15 % Contractor's profit and overheads on "Y" 147.98
Total 1134.50 Z
Add Cess @ 1% on "Z" 11.35
Cost of 0.66 sqm. 1145.85
Cost of 1 sqm. 1736.14
Say 1736.10

9.126.2 Fire retardant plywood conforming to IS: 5509


Details of cost for shutters of a door with 2/3rd
panelling 200x108cm = 2.16sqm.
Panel area = 4x45.1x36.55cm = 0.66sqm.
MATERIAL
Plywood 4x47.2x38.65cm = 0.73sqm+ Add for
wastage @ 10% = 0.07sqm.
Total = 0.80 sqm.
8725 12mm thick fire retardant plywood conforming to sqm 0.8 850 680.00
IS: 5509.
9977 Carriage of Plywood L.S. 1.82 2 3.64
LABOUR
14 Carpenter 1st class day 0.57 505.17 287.95
9999 Sundries L.S. 4.42 2.00 8.84
TOTAL 980.43 W
Add 1 % Water charges on "W" 9.8043
TOTAL 990.23 X
Add GST (multiplying factor 0.1405) on "X" 139.13
TOTAL 1129.36 Y
Add 15 % Contractor's profit and overheads on "Y" 169.40
Total 1298.76 Z
Add Cess @ 1% on "Z" 12.99
Cost of 0.66 sqm. 1311.75
Cost of 1 sqm. 1987.51
Say 1987.50

9.127 Providing & Fixing decorative high


pressure laminated
grain in gloss / matt/sheet
suedeoffinish
plain with
/ wood
high
density protective surface layer
and reverse side of adhesive bonding
quality conforming to IS : 2046 Type S,
including cost of adhesive of approved
9.127.1 quality.
1.5 mm thick
Details of cost for 5.00 sqm
MATERIAL
Decorative laminate = 5.00 sqm
Add wastage @ 10% = 0.50 sqm
Total = 5.50 sqm
8726 1.5mm thick decorative laminated sheet sqm 5.5 365 2007.50
9999 Adhesive L.S. 195 2 390.00
LABOUR
14 Carpenter 1st class day 0.5 505.17 252.59
17 Beldar day 0.5 350.00 175.00
9999 Sundries i/c nails etc. L.S. 52 2.00 104.00
TOTAL 2929.09 W
Add 1 % Water charges on "W" 29.2909
TOTAL 2958.38 X
Add GST (multiplying factor 0.1405) on "X" 415.65
TOTAL 3374.03 Y
Add 15 % Contractor's profit and overheads on "Y" 506.10
Total 3880.13 Z
Add Cess @ 1% on "Z" 38.80
Cost for 5.00 sqm 3918.93
Cost for 1 sqm 783.79
Say 783.80

9.127.2 1.0 mm thick


Details of cost for 5.00 sqm
MATERIAL
Decorative laminate = 5.00 sqm
Add wastage @ 10% = 0.50 sqm
Total = 5.50 sqm
8727 1.0mm thick decorative laminated sheet sqm 5.5 280 1540.00
9999 Adhesive L.S. 195 2 390.00
LABOUR
14 Carpenter 1st class day 0.5 505.17 252.59
17 Beldar day 0.5 350.00 175.00
9999 Sundries i/c nails etc. L.S. 52 2.00 104.00
TOTAL 2461.59 W
Add 1 % Water charges on "W" 24.6159
TOTAL 2486.21 X
Add GST (multiplying factor 0.1405) on "X" 349.31
TOTAL 2835.52 Y
Add 15 % Contractor's profit and overheads on "Y" 425.33
Total 3260.85 Z
Add Cess @ 1% on "Z" 32.61
Cost for 5.00 sqm 3293.46
Cost for 1 sqm 658.69
Say 658.70

9.128 Providing and fixing factory made


Fiberglass
chajja 4 mm Reinforced plasticscolour,
thick of required (F.R.P.)
size
and design made by Resin
Moulding (RTM) Machine Technology, Transfer
resulting in voidhaving
in single piece, free compact
smoothlaminate
gradual
slope
water and duly reinforced by 2 nosof
curvature for easy drainage
vertically
thick M.S.andflat 1with
nos12 horizontally
mm in built50x2
holemm
for
grouting
with on mm
the 50 the existing wall along
flanges duly inserted and
sealedpiece
single in thecasted
wall complete in one
monolithically,
including
Chajja should be manufactured. The
all necessary fittings usingFRP
unsaturated Polyester resin as per IS:
6746, duly reinforced with fibre glass
chopped strand mat
11551 complete with(CSM) as per
protective GelIS:
coat
U/V coating on Top for
resistance from the extreme of complete
temperature,
Detail of cost for weather & sunlight.
a chajja 0.90 x 0.60 =
0.54 sqm
MATERIAL
8713 Fiber glass reinforced plastic chajja sqm 0.54 3000 1620.00
9977 Carriage L.S. 26 2 52.00
9999 fixing charges including sundries. L.S. 143 2 286.00
TOTAL 1958.00 W
Add 1 % Water charges on "W" 19.58
TOTAL 1977.58 X
Add GST (multiplying factor 0.1405) on "X" 277.85
TOTAL 2255.43 Y
Add 15 % Contractor's profit and overheads on "Y" 338.31
Total 2593.74 Z
Add Cess @ 1% on "Z" 25.94
Cost for 0.54 sqm 2619.68
Cost for 1 sqm 4851.26
Say 4851.30

9.129 Providing and fixing cup board shutters 25


mm thick,three
pressed with layer
Pre-laminated flat or
particle board
graded
marked,wood particle
exterior grade board
(Grade IS: l12823
Type ll),
having one side decorative
and other side balancing lamination,lamination
including
25 mm wide IIndx12
class
mm teak wood
thick withlipping of
necessary
screws and hinges,
steel piano bright finished
complete stainless
as per
direction of the Engineer-in-Charge
Details of cost for one shutter 2.20x1.00m =
2.20sqm.
MATERIAL
7272 25 mm thick melamine faced prelaminated three sqm 2.2 900 1980.00
9977 layer particle board 0.00
CARRIAGE L.S. 29.64 2 59.28
8678 1mm thick 35mm wide bright finished stainless metre 4.4 42 184.80
685 steel piano hinges . 0.00
Oxidised mild steel screws 25 mm 100 1.25 36 45.00
LABOUR Nos 0.00
14 Carpenter 1st class day 0.5 505.17 252.59
17 Beldar day 0.5 350.00 175.00
30 Mistry day 0.07 505.17 35.36
7271 IInd class teak wood lipping 25 mm wide x 12 mm t metre 7 29 203.00
TOTAL 2935.03 W
Add 1 % Water charges on "W" 29.3503
TOTAL 2964.38 X
Add GST (multiplying factor 0.1405) on "X" 416.50
TOTAL 3380.88 Y
Add 15 % Contractor's profit and overheads on "Y" 507.13
Total 3888.01 Z
Add Cess @ 1% on "Z" 38.88
Cost for 2.20sqm. 3926.89
Cost of 1 sqm 1784.95
Say 1785.00

9.13 Providing and fixing cup board shutters


with 25 mm thick veneered particle board
IS : 3097 marked, exterior grade (Grade I),
9.130.1 With decorative veneering onIInd
oneclass
side and
of approved make, including
commercial veneering on other side
Details of cost for one shutter 2.20x1.00m =
2.20sqm.
MATERIAL
7269 25 mm thick particle board sqm 2.2 460 1012.00
346 Extra for veneered particle board with : Teak sqm 2.2 230 506.00
veneering on one side and commercial veneered 0.00
9977 on other side 0.00
CARRIAGE L.S. 29.64 2 59.28
8678 1mm thick 35mm wide bright finished stainless stee metre 4.4 42 184.80
685 Oxidised mild steel screws 25 mm 100 Nos 1.25 36 45.00
LABOUR 0.00
14 Carpenter 1st class day 0.5 505.17 252.59
17 Beldar day 0.5 350.00 175.00
30 Mistry day 0.07 505.17 35.36
7271 IInd class teak wood lipping 25 mm wide x 12 mm t metre 7 29 203.00
TOTAL 2473.03 W
Add 1 % Water charges on "W" 24.7303
TOTAL 2497.76 X
Add GST (multiplying factor 0.1405) on "X" 350.94
TOTAL 2848.70 Y
Add 15 % Contractor's profit and overheads on "Y" 427.31
Total 3276.01 Z
Add Cess @ 1% on "Z" 32.76
Cost for 2.20sqm. 3308.77
Cost of 1 sqm 1503.99
Say 1504.00
9.130.2 With non decorative veneering on both sides
Details of cost for one shutter 2.20x1.00m = 2.20sq
MATERIAL
7269 25 mm thick particle board sqm 2.2 460 1012.00
347 Extra for veneered particle board with: Commercial sqm 2.2 155 341.00
9977 veneering on both sides
CARRIAGE L.S. 29.64 2 59.28
8678 1mm thick 35mm wide bright finished stainless stee metre 4.4 42 184.80
685 Oxidised mild steel screws 25 mm 100 Nos 1.25 36 45.00
LABOUR
14 Carpenter 1st class day 0.5 505.17 252.59
17 Beldar day 0.5 350.00 175.00
30 Mistry day 0.07 505.17 35.36
7271 IInd class teak wood lipping 25 mm wide x 12 mm t metre 7 29 203.00
TOTAL 2308.03 W
Add 1 % Water charges on "W" 23.0803
TOTAL 2331.11 X
Add GST (multiplying factor 0.1405) on "X" 327.52
TOTAL 2658.63 Y
Add 15 % Contractor's profit and overheads on "Y" 398.79
Total 3057.42 Z
Add Cess @ 1% on "Z" 30.57
Cost for 2.20sqm. 3087.99
Cost of 1 sqm 1403.63
Say 1403.60

9.131 Providing and fixing factory made shutters


of Pre-laminated
pressed three layer particle boardwood
or graded flat
particle board
finish and otherwithsideone side decorative
balancing lamination
conforming
Type ll, of approved design, andl edges
to IS: 12823 Grade
sealed withaluminium
lipped with water resistant paint
'U' type edgeand
beading
fixing withall-angle
round the shutter,
cleat, including
grip strip, cadmium
platedofsteel
fixing screws,hinges
aluminium including
100x63x4 mm
etc. complete
drawing as per architectural
and direction of Engineer-in-
Charge
will be paid for separately). and hinges
(Cost of 'U' beading
9.131.1 25 mm thick
Details of cost for 2.10sqm.
(Door size 2.1x1.00 = 2.10sqm.)
MATERIAL
Prelaminated particle board = 2.10sqm. + Add for
wastage @ 5% = 0.11sqm.
Total = 2.21sqm.
7445 25 mm prelaminated flush door both side sqm 2.21 800 1768.00
7443 decorative 0.00
Aluminium single cleat of size 30x32x3 each 4 14 56
7444 Aluminium grip strip of size 50x12x2 each 8 11 88.00
834 Synthetic enamel paint in all shades except black litre 0.15 160 24.00
9988 or chocolate shade 0.00
Carriage of materials including loading and L.S. 19.5 2 39
9999 unloading 0.00
Sundries and screws etc. L.S. 39 2.00 78
LABOUR
15 Carpenter 2nd class day 0.27 403.67 108.99
17 Beldar day 0.3 350.00 105.00
TOTAL 2266.99 W
Add 1 % Water charges on "W" 22.6699
TOTAL 2289.66 X
Add GST (multiplying factor 0.1405) on "X" 321.70
TOTAL 2611.36 Y
Add 15 % Contractor's profit and overheads on "Y" 391.70
Total 3003.06 Z
Add Cess @ 1% on "Z" 30.03
Cost for 2.10sqm. 3033.09
Cost of 1 sqm 1444.33
Say 1444.30

9.132 Providing and fixing aluminum U beading


of required
flush size to Pre-laminated/
door shutter, including fixing etc.
complete
charge. as per direction of Engineerin
Details of cost for 1kg.
MATERIAL
Aluminum U beading = 1.00kg + Add 10%
7449 wastage = 0.10 Total = 1.10kg. 0.00
Aluminium U beading kilogra 1.1 210 231
9999 m 0.00
Anodized 15 micron L.S. 65 2 130
9999 Sundries including screws, fixing, carriage etc. L.S. 13 2.00 26.00
TOTAL 387.00 W
Add 1 % Water charges on "W" 3.87
TOTAL 390.87 X
Add GST (multiplying factor 0.1405) on "X" 54.92
TOTAL 445.79 Y
Add 15 % Contractor's profit and overheads on "Y" 66.87
Total 512.66 Z
Add Cess @ 1% on "Z" 5.13
Cost for 1 kg. 517.79
Cost for 1 kg. 517.79
Say 517.80

9.133 Providing and fixing, in position concealed G.I.


9.133.1 section
Taperedfor wallcalcium
edge panelingsilicate
using board
board made
of with
required thickness
calcareous & fixed
siliceous on the
materials 'W' profile (0.55
reinforced with cellulose
mm thick) having fiber
a knurled webmanufactured
of 51.55 mm
through autoclaving process to give
stable crystalline structure with compressive
strength 225 kg/ sq.cm, Bending strength
100 kg/sq.cm.
9.133.1.1 10mm thick
Details of cost for 3.66 m x 3.05 m = 11.16 sqm.
MATERIAL
Calcium silicate board 10mm thick.
= 11.16 sqm
Add wastage @ 10% = 1.12 sqm. Total = 12.28
8700 sqm 0.00
10 mm thick calcium silicate board. sqm 12.28 420 5157.6
8720 Ceiling sections 0.55 mm thick having a knurled metre 19.66 35 688.10
web of 51.55mm and two flanges of 26mm each
8721 with lips of 10.55mm.
Perimeter channel having one flange of 20mm and metre 9.6 22 211.2
another flange of 30mm with
thickness of 0.55mm and web of length
27mm
8722 Nylon sleeves & wooden screws (40mm) each 42 2 84.00
8723 Counter sunk ribbed head screw 25 mm 100 1.76 68 119.68
Nos
9999 Jointing compound L.S. 20.8 2 41.60
7018 Joint tape roll roll 0.19 100 19.00
9999 Sundries i/c rawl plug, scaffolfing etc. L.S. 52 2.00 104.00
9977 Carriage of materials L.S. 26 2 52.00
LABOUR
14 Carpenter 1st class day 3.8 505.17 1919.65
17 Beldar day 4.6 350.00 1610.00
TOTAL 10006.83 W
Add 1 % Water charges on "W" 100.0683
TOTAL 10106.90 X
Add GST (multiplying factor 0.1405) on "X" 1420.02
TOTAL 11526.92 Y
Add 15 % Contractor's profit and overheads on "Y" 1729.04
Total 13255.96 Z
Add Cess @ 1% on "Z" 132.56
Cost for 11.16 sqm 13388.52
Cost for 1 sqm 1199.69
Say 1199.70

9.133.2 Multipurpose cement board reinforced with


9.133.2.1 with
8 mmsuitable fibre cement
thick cement screw.
fibre board as per IS :
14862
Details of cost for 3.66 m x 3.05 m = 11.16 sqm.
MATERIAL
Multipurpose non asbestos fibre cement board
8mm thick.= 11.16 sqm
Add wastage @ 10% = 1.12 sqm. Total = 12.28
sqm 0.00
237 Multi purpose fibre (high impact poly propelene sqm 12.28 220 2701.6
reinforced) cement board 8mm thick.
8720 Ceiling sections 0.55 mm thick having a knurled metre 19.66 35 688.10
web of 51.55mm and two flanges of 26mm each
8721 with lips of 10.55mm.
Perimeter channel having one flange of 20mm and metre 9.6 22 211.2
another flange of 30mm with thickness of 0.55mm
8722 and web of length 27mm. 0.00
Nylon sleeves & wooden screws (40mm) each 42 2 84
8723 Counter sunk ribbed head screw 25 mm 100 1.76 68 119.68
Nos
9999 Jointing compound L.S. 20.8 2 41.60
7018 Joint tape roll roll 0.19 100 19.00
9999 Sundries i/c rawl plug, scaffolfing etc. L.S. 52 2.00 104.00
9977 Carriage of materials L.S. 26 2 52.00
LABOUR
14 Carpenter 1st class day 3.8 505.17 1919.65
17 Beldar day 4.6 350.00 1610.00
TOTAL 7550.83 W
Add 1 % Water charges on "W" 75.5083
TOTAL 7626.34 X
Add GST (multiplying factor 0.1405) on "X" 1071.50
TOTAL 8697.84 Y
Add 15 % Contractor's profit and overheads on "Y" 1304.68
Total 10002.52 Z
Add Cess @ 1% on "Z" 100.03
Cost for 11.16 sqm 10102.55
Cost for 1 sqm 905.25
Say 905.30

9.133.2.2 8 mm thick Cement bonded wood particle


board of
Details ascost
perforIS:14276
3.66 m x 3.05 m =11.16 sqm
MATERIAL:

243 Multipurpose cement bonded wood particle board Sqm 12.28 215 2640.20
8mm thick 0.00
Add wastage @ 10% =1.12 sqm. Total = 12.28 sqm 0.00
8720 Ceiling sections 0.55 mm thick having a knurled metre 19.66 35 688.10
web of 51.55 mm and two flanges of 26 mm each
8721 with lips of 10.55 mm
Perimeter channel having one flange of 20 mm metre 9.6 22 211.2
and another flange of 30 mm with
thickness of 0.55 mm and web of length 27 mm
8722 Nylon sleeves & wooden screws (40 mm) each 42 2 84.00
8723 Counter sunk ribbed head screw 25 mm 100 1.76 68 119.68
Nos
9999 Jointing compound L.S 20.8 2 41.60
7018 Joint tape roll each roll 0.19 100 19.00
9999 Sundries i/c rawl plug. Scaffolding etc. L.S 52 2.00 104.00
9999 Carriage of materials L.S 26 2 52.00
LABOUR:
14 Carpenter 1 st class day 3.8 505.17 1919.65
17 Beldar day 4.6 350.00 1610.00
TOTAL 7489.43 W
Add 1 % Water charges on "W" 74.8943
TOTAL 7564.32 X
Add GST (multiplying factor 0.1405) on "X" 1062.79
TOTAL 8627.11 Y
Add 15 % Contractor's profit and overheads on "Y" 1294.07
Total 9921.18 Z
Add Cess @ 1% on "Z" 99.21
Cost for 11.16 sqm 10020.39
Cost for 1 sqm 897.88
Say 897.90

9.133.3 Plain Gypsum plaster board


conforming
9.133.3.1 12.5 mm thick to IS: 2095 (Part -1) : 2011
(Board with BIS
Details of cost for 3.66certification marks).
m x 3.05 m = 11.16 sqm.
MATERIAL
Glass fibre reinforced gypsum board 12.5 mm
thick.= 11.16 sqm
Add wastage @ 10% = 1.12 sqm. Total = 12.28
7009 sqm 0.00
12.5 mm thick Plain Gypsum plaster sqm 12.28 155 1903.40
8720 board 0.00
Ceiling sections 0.55 mm thick having a knurled metre 19.66 35 688.10
web of 51.55mm and two flanges of 26mm each 0.00
8721 with lips of 10.55mm. 0.00
Perimeter channel having one flange of 20mm and metre 9.6 22 211.20
another flange of 30mm with thickness of 0.55mm 0.00
and web of length 27mm.
8722 Nylon sleeves & wooden screws (40mm) each 42 2 84.00
8723 Counter sunk ribbed head screw 25 mm 100 1.76 68 119.68
Nos
9999 Jointing compound L.S. 20.8 2 41.60
7018 Joint tape roll roll 0.19 100 19.00
9999 Sundries i/c rawl plug, scaffolfing etc. L.S. 52 2.00 104.00
9977 Carriage of materials L.S. 26 2 52.00
LABOUR
14 Carpenter 1st class day 3.8 505.17 1919.65
17 Beldar day 4.6 350.00 1610.00
TOTAL 6752.63 W
Add 1 % Water charges on "W" 67.5263
TOTAL 6820.16 X
Add GST (multiplying factor 0.1405) on "X" 958.23
TOTAL 7778.39 Y
Add 15 % Contractor's profit and overheads on "Y" 1166.76
Total 8945.15 Z
Add Cess @ 1% on "Z" 89.45
Cost for 11.16 sqm 9034.60
Cost for 1 sqm 809.55
Say 809.60

9.134 Providing and fixing wire gauge shutters


using stainless
gauge with wiresteel
of diagrade 304and
0.5 mm wireaverage
width of aperture
directions 1.4windows
for doors, mm in both
and
9.134.1 clerestory windows
35 mm thick shutters with necessary screws
9.134.1.1 with ISI marked M.S. pressed butt hinges
9.134.1.1. bright
Second finished of required
class teak wood size
1 Details of cost for door shutters 2.00x1.08m = 2.16
MATERIAL
Teak wood (2nd class)
Styles 4x200x9.5x3.5cm = 0.0266cum+
Top Rail - 1x110.5x9.5x3.5cm = 0.0036cum+ Lock
and bottom rail
2x110.5x19.7x3.5cm = 0.0152 cum.+ Beadings -
(2x312+2x150)x(1.2)x(1.2)cm = 0.001 cum. Total =
0.0464 cum.+
Add for wastage @ 10% = 0.005 cum. Total =
0.0514 cum.
602
Say 51.4 cudm.
1190 Second class teak wood in planks
Wire gauge 2x160x40cm = 1.28 sqm.+ Add
wastage @ 10% = 0.13 sqm. Total = 1.41 sqm.
10 5.14 791.00 4065.74 cudm 10 cudm 5.14 791 4065.74
8737 Stainless steel wire guage (Grade-304) aperture sqm 1.41 400 564.00
1.4mm and 0.50 mm dia wire 0.00
595 Bright finished or black enamelled mild steel butt 10 Nos 0.6 80 48.00
597 hinges 100x58x1.90 mm 0.00
Bright finished or black enamelled mild steel butt 10 Nos 0.2 80 16.00
637 hinges50x37x1.50 mm 0.00
Bright finished or black enamelled mild steel 100 0.48 60 28.80
640 screws 40 mm Nos 0.00
Bright finished or black enamelled mild steel 100 0.08 30 2.40
2204 screws 20 mm Nos 0.00
Carriage of Timber cum 0.05 121.29 6.06
LABOUR 0.00
14 Carpenter 1st class day 1.3 505.17 656.72
15 Carpenter 2nd class day 0.9 403.67 363.30
17 Beldar day 1.05 350.00 367.50
30 Mistry day 0.11 505.17 55.57
9999 Sundries L.S. 33.8 2.00 67.60
TOTAL 6241.69 W
Add 1 % Water charges on "W" 62.4169
TOTAL 6304.11 X
Add GST (multiplying factor 0.1405) on "X" 885.73
TOTAL 7189.84 Y
Add 15 % Contractor's profit and overheads on "Y" 1078.48
Total 8268.32 Z
Add Cess @ 1% on "Z" 82.68
Cost of 2.16 sqm. 8351.00
Cost of 1 sqm. 3866.2
Say 3866.20

9.134.1.1. Kiln seasoned and chemically treated hollock wood


2 Details of cost for door shutters 2.00x1.08m = 2.16
MATERIAL
Hollock wood
Styles 4x200x9.5x3.5cm = 0.0266cum+
Top Rail - 1x110.5x9.5x3.5cm = 0.0036cum+ Lock
and bottom rail
2x110.5x19.7x3.5cm = 0.0152 cum.+ Beadings -
(2x312+2x150)x(1.2)x (1.2)cm = 0.001 cum. Total
= 0.0464 cum.+
Add for wastage @ 10% = 0.005 cum.
603
Total = 0.0514 cum.
Say 51.4 cudm.
2505 Hollock wood in planks 10 5.14 390 2004.60
2204 cudm
Carriage of Timber cum 0.0514 121.29 6.23
2504 Kiln seasoning of timber cum 0.0514 750 38.55
9999 Chemical treatment L.S. 8.97 2 17.94
Wire gauge 2x160x40cm = 1.28 sqm.+ Add
wastage @ 10% = 0.13 sqm.
Total = 1.41 sqm.
8737 Stainless steel wire guage (Grade-304) aperture sqm 1.41 400 564.00
1.4mm and 0.50 mm dia wire
595 Bright finished or black enamelled mild steel butt 10 Nos 0.6 80 48.00
597 hinges 100x58x1.90 mm
Bright finished or black enamelled mild steel butt 10 Nos 0.2 80 9.8
637 hinges50x37x1.50 mm
Bright finished or black enamelled mild steel 100 0.48 60 28.8
640 screws 40 mm Nos
Bright finished or black enamelled mild 100 0.08 30 2.4
steel screws 20 mm Nos
LABOUR
14 Carpenter 1st class day 1.3 505.17 656.72
15 Carpenter 2nd class day 0.9 403.67 363.30
17 Beldar day 1.05 350.00 367.50
30 Mistry day 0.105 505.17 53.04
9999 Sundries L.S. 33.8 2.00 67.60
TOTAL 4228.48 W
Add 1 % Water charges on "W" 42.2848
TOTAL 4270.76 X
Add GST (multiplying factor 0.1405) on "X" 600.04
TOTAL 4870.80 Y
Add 15 % Contractor's profit and overheads on "Y" 730.62
Total 5601.42 Z
Add Cess @ 1% on "Z" 56.01
Cost of 2.16 sqm. 5657.43
Cost of 1 sqm. 2377.07
Say 2377.10

9.134.1.1. Kiln seasoned selected class of sheesham wood


3 Details of cost for door shutters 2.00x1.08m = 2.16
MATERIAL
Hollock wood
Styles 4x200x9.5x3.5cm = 0.0266cum+
Top Rail - 1x110.5x9.5x3.5cm = 0.0036cum+
Lock and bottom rail
2x110.5x19.7x3.5cm = 0.0152 cum.+ Beadings -
(2x312+2x150)x(1.2)x (1.2)cm = 0.001 cum. Total
= 0.0464 cum.+
Add for wastage @ 10% = 0.005 cum.
Total = 0.0514 cum.
Say 51.4 cudm.
1200 Kiln seasoned selected sheesum wood planks 10 5.14 650 3341.00
2204 cudm
Carriage of Timber cum 0.0514 121.29 6.23
2504 Kiln seasoning of timber cum 0.0514 750 38.55
Wire gauge 2x160x40cm = 1.28 sqm.+ Add
wastage @ 10% = 0.13 sqm.
Total = 1.41 sqm.
8737 Stainless steel wire guage (Grade-304) aperture sqm 1.41 400 564.00
1.4mm and 0.50 mm dia wire
595 Bright finished or black enamelled mild steel butt 10 Nos 0.6 80 48.00
597 hinges 100x58x1.90 mm
Bright finished or black enamelled mild steel butt 10 Nos 0.2 80 9.8
637 hinges50x37x1.50 mm
Bright finished or black enamelled mild steel 100 0.48 60 28.8
640 screws 40 mm Nos
Bright finished or black enamelled mild 100 0.08 30 2.4
steel screws 20 mm Nos
LABOUR
14 Carpenter 1st class day 1.3 505.17 656.72
15 Carpenter 2nd class day 0.9 403.67 363.30
17 Beldar day 1.05 350.00 367.50
30 Mistry day 0.105 505.17 53.04
9999 Sundries L.S. 33.8 2.00 67.60
TOTAL 5546.94 W
Add 1 % Water charges on "W" 55.4694
TOTAL 5602.41 X
Add GST (multiplying factor 0.1405) on "X" 787.14
TOTAL 6389.55 Y
Add 15 % Contractor's profit and overheads on "Y" 958.43
Total 7347.98 Z
Add Cess @ 1% on "Z" 73.48
Cost of 2.16 sqm. 7421.46
Cost of 1 sqm. 3435.86
Say 3435.90

9.134.1.2 With ISI marked stainless steel butt hinges of


9.134.1.2.1 required size teak wood
Second class
Details of cost for door shutters 2.00x1.08m = 2.16
sqm.
MATERIAL
Second class Teak wood
Styles 4x200x9.5x3.5cm = 0.0266cum+
Top Rail - 1x110.5x9.5x3.5cm = 0.0036cum+
Lock and bottom rail
2x110.5x19.7x3.5cm = 0.0152 cum.+ Beadings -
(2x312+2x150)x(1.2)x (1.2)cm = 0.001 cum. Total
= 0.0464 cum.+
Add for wastage @ 10% = 0.005 cum. Total =
0.0514 cum.
Say 51.4 cudm.
1190 Second class teak wood in planks 10 5.14 791 4065.74
Wire gauge 2x160x40cm = 1.28 sqm.+ Add cudm
wastage @ 10% = 0.13 sqm. Total = 1.41 sqm.
10 5.14 791.00 4065.74 cudm
8737 Stainless steel wire guage (Grade-304) aperture sqm 1.41 400 564.00
1.4mm and 0.50 mm dia wire
8220 Stainless steel butt hinges (heavy weight) 10 Nos 0.6 255 153.00
8218 100x60x2.5 mm IS : 12817 marked 0.00
Stainless steel butt hinges 50x37x1.5 mm IS : 10 Nos 0.2 135 27.00
8211 12817 marked 0.00
Stainless steel screws 40 mm 100 0.48 215 103.20
8214 Nos 0.00
Stainless steel screws 20 mm 100 0.08 125 10.00
2204 Nos 0.00
Carriage of Timber cum 0.0514 121.29 6.23
LABOUR 0.00
14 Carpenter 1st class day 1.3 505.17 656.72
15 Carpenter 2nd class day 0.9 403.67 363.30
17 Beldar day 1.05 350.00 367.50
30 Mistry day 0.105 505.17 53.04
9999 Sundries L.S. 33.8 2.00 67.60
TOTAL 6437.33 W
Add 1 % Water charges on "W" 64.3733
TOTAL 6501.70 X
Add GST (multiplying factor 0.1405) on "X" 913.49
TOTAL 7415.19 Y
Add 15 % Contractor's profit and overheads on "Y" 1112.28
Total 8527.47 Z
Add Cess @ 1% on "Z" 85.27
Cost of 2.16 sqm. 8612.74
Cost of 1 sqm. 3987.38
Say 3987.40

9.134.1.2. Kiln seasoned and chemically treated hollock wood


2 Details of cost for door shutters 2.00x1.08m = 2.16
MATERIAL
Hollock wood
Styles 4x200x9.5x3.5cm = 0.0266cum+
Top Rail - 1x110.5x9.5x3.5cm = 0.0036cum+
Lock and bottom rail
2x110.5x19.7x3.5cm = 0.0152 cum.+ Beadings -
(2x312+2x150)x(1.2)x (1.2)cm = 0.001 cum. Total
= 0.0464 cum.+
Add for wastage @ 10% = 0.005 cum.
Total = 0.0514 cum.
Say 51.4 cudm.
2505 Hollock wood in planks 10 5.14 390 2004.60
cudm 0.00
2504 Kiln seasoning of timber cum 0.0514 750 38.55
9999 Chemical treatment L.S. 8.97 2 17.94
Wire gauge 2x160x40cm = 1.28 sqm.+ Add 0.00
wastage @ 10% = 0.13 sqm. 0.00
Total = 1.41 sqm. 0.00
8737 Stainless steel wire guage (Grade-304) aperture sqm 1.41 400 564.00
1.4mm and 0.50 mm dia wire 0.00
8220 Stainless steel butt hinges (heavy weight) 10 Nos 0.6 255 153.00
8218 100x60x2.5 mm IS : 12817 marked 0.00
Stainless steel butt hinges 50x37x1.5 mm IS : 10 Nos 0.2 135 27.00
8211 12817 marked 0.00
Stainless steel screws 40 mm 100 0.48 215 103.20
8214 Nos 0.00
Stainless steel screws 20 mm 100 0.08 125 10.00
2204 Nos 0.00
Carriage of Timber cum 0.0514 121.29 6.23
LABOUR 0.00
14 Carpenter 1st class day 1.3 505.17 656.72
15 Carpenter 2nd class day 0.9 403.67 363.30
17 Beldar day 1.05 350.00 367.50
30 Mistry day 0.105 505.17 53.04
9999 Sundries L.S. 33.8 2.00 67.60
TOTAL 4432.68 W
Add 1 % Water charges on "W" 44.3268
TOTAL 4477.01 X
Add GST (multiplying factor 0.1405) on "X" 629.02
TOTAL 5106.03 Y
Add 15 % Contractor's profit and overheads on "Y" 765.90
Total 5871.93 Z
Add Cess @ 1% on "Z" 58.72
Cost of 2.16 sqm. 5930.65
Cost of 1 sqm. 2745.67
Say 2745.70

9.134.1.2. Kiln seasoned selected class of sheesham wood


3 Details of cost for door shutters 2.00x1.08m = 2.16
sqm.
MATERIAL
Hollock wood
Styles 4x200x9.5x3.5cm = 0.0266cum+
Top Rail - 1x110.5x9.5x3.5cm = 0.0036cum+
Lock and bottom rail
2x110.5x19.7x3.5cm = 0.0152 cum.+ Beadings -
(2x312+2x150)x(1.2)x (1.2)cm = 0.001 cum. Total
= 0.0464 cum.+
Add for wastage @ 10% = 0.005 cum.
Total = 0.0514 cum.
Say 51.4 cudm.
1200 Kiln seasoned selected sheesum wood planks 10 5.14 650 3341.00
cudm 0.00
2504 Kiln seasoning of timber cum 0.0514 750 38.55
Wire gauge 2x160x40cm = 1.28 sqm.+ Add 0.00
wastage @ 10% = 0.13 sqm. 0.00
Total = 1.41 sqm. 0.00
8737 Stainless steel wire guage (Grade-304) aperture sqm 1.41 400 564.00
1.4mm and 0.50 mm dia wire 0.00
8220 Stainless steel butt hinges (heavy weight) 10 Nos 0.6 255 153.00
8218 100x60x2.5 mm IS : 12817 marked 0.00
Stainless steel butt hinges 50x37x 10 Nos 0.2 135 27.00
1.5 mm IS : 12817 marked 0.00
8211 Stainless steel screws 40 mm 100 0.48 215 103.20
8214 Nos 0.00
Stainless steel screws 20 mm 100 0.08 125 10.00
2204 Nos 0.00
Carriage of Timber cum 0.0514 121.29 6.23
LABOUR 0.00
14 Carpenter 1st class day 1.3 505.17 656.72
15 Carpenter 2nd class day 0.9 403.67 363.30
17 Beldar day 1.05 350.00 367.50
30 Mistry day 0.105 505.17 53.04
9999 Sundries L.S. 33.8 2.00 67.60
TOTAL 5751.14 W
Add 1 % Water charges on "W" 57.5114
TOTAL 5808.65 X
Add GST (multiplying factor 0.1405) on "X" 816.12
TOTAL 6624.77 Y
Add 15 % Contractor's profit and overheads on "Y" 993.72
Total 7618.49 Z
Add Cess @ 1% on "Z" 76.18
Cost of 2.16 sqm. 7694.67
Cost of 1 sqm. 3562.35
Say 3562.40

9.134.2 30 mm thick shutters


9.134.2.1 with ISI marked M.S. pressed butt
hinges of
Details bright finished
cost for of required
door shutters size = 2.16
2.00x1.08m
9.134.2.1.1
sqm. Second class teak wood
MATERIAL
Teak wood (2nd class)
Styles 4x209x9.5x3cm = 0.023 cum+
Top Rail - 1x110.5x9.5x3cm = 0.003cum+
Lock and bottom rail
2x110.5x19.7x3cm = 0.013 cum+ Beadings -
(2x312+2x150)x(1.2)x (1.2)cm = 0.001 cum.
Total = 0.040 cum+
Add for wastage @ 10% = 0.004 cum.
Total = 0.44 cum.
Say 44 cudm.
1190 Second class teak wood in planks 10 4.4 791 3480.40
2204 cudm
Carriage of Timber cum 0.044 121.29 5.34
Wire gauge 2x160x40cm = 1.28 sqm.+ Add
wastage @ 10% = 0.13 sqm.
Total = 1.41 sqm.
8737 Stainless steel wire guage (Grade-304) aperture sqm 1.41 400 564.00
1.4mm and 0.50 mm dia wire
595 Bright finished or black enamelled mild steel butt 10 Nos 0.6 80 48.00
597 hinges 100x58x1.90 mm
Bright finished or black enamelled mild steel butt 10 Nos 0.2 80 9.8
637 hinges50x37x1.50 mm
Bright finished or black enamelled mild steel 100 0.48 60 28.8
screws 40 mm Nos
640 Bright finished or black enamelled mild steel 100 0.08 30 2.40
screws 20 mm Nos
LABOUR
14 Carpenter 1st class day 1.2 505.17 606.20
15 Carpenter 2nd class day 0.8 403.67 322.94
17 Beldar day 1 350.00 350.00
30 Mistry day 0.1 505.17 50.52
9999 Sundries L.S. 33.8 2.00 67.60
TOTAL 5536.00 W
Add 1 % Water charges on "W" 55.36
TOTAL 5591.36 X
Add GST (multiplying factor 0.1405) on "X" 785.59
TOTAL 6376.95 Y
Add 15 % Contractor's profit and overheads on "Y" 956.54
Total 7333.49 Z
Add Cess @ 1% on "Z" 73.33
Cost of 2.16 sqm. 7406.82
Cost of 1 sqm. 3429.08
Say 3429.10

9.134.2.1. Kiln seasoned and chemically treated hollock wood


2 Details of cost for door shutters 2.00x1.08m = 2.16
sqm.
MATERIAL
Hollock wood
Styles 4x209x9.5x3cm = 0.023 cum+
Top Rail - 1x110.5x9.5x3cm = 0.003cum+
Lock and bottom rail
2x110.5x19.7x3cm = 0.013 cum+ Beadings -
(2x312+2x150)x(1.2)x (1.2)cm = 0.001 cum.
Total = 0.040 cum+
Add for wastage @ 10% = 0.004 cum.
Total = 0.44 cum.
Say 44 cudm.
2505 Hollock wood in planks 10 4.4 390 1716.00
cudm 0.00
2204 Carriage of Timber cum 0.044 121.29 5.34
2504 Kiln seasoning of timber cum 0.044 750 33.00
9999 Chemical treatment L.S. 8.97 2 17.94
Wire gauge 2x160x40cm = 1.28 sqm.+ Add 0.00
wastage @ 10% = 0.13 sqm. 0.00
Total = 1.41 sqm. 0.00
8737 Stainless steel wire guage (Grade-304) aperture sqm 1.41 400 564.00
1.4mm and 0.50 mm dia wire 0.00
595 Bright finished or black enamelled mild steel butt 10 Nos 0.6 80 48.00
597 hinges 100x58x1.90 mm 0.00
Bright finished or black enamelled mild steel butt 10 Nos 0.2 80 16.00
637 hinges50x37x1.50 mm 0.00
Bright finished or black enamelled mild steel 100 0.48 60 28.80
640 screws 40 mm Nos 0.00
Bright finished or black enamelled mild 100 0.08 30 2.40
steel screws 20 mm Nos 0.00
LABOUR 0.00
14 Carpenter 1st class day 1.2 505.17 606.20
15 Carpenter 2nd class day 0.8 403.67 322.94
17 Beldar day 1 350.00 350.00
0.00
30 Mistry day 0.1 505.17 50.52
9999 Sundries L.S. 33.8 2.00 67.60
TOTAL 3828.74 W
Add 1 % Water charges on "W" 38.2874
TOTAL 3867.03 X
Add GST (multiplying factor 0.1405) on "X" 543.32
TOTAL 4410.35 Y
Add 15 % Contractor's profit and overheads on "Y" 661.55
Total 5071.90 Z
Add Cess @ 1% on "Z" 50.72
Cost of 2.16 sqm. 5122.62
Cost of 1 sqm. 2371.58
Say 2371.60

9.134.2.1. Kiln seasoned selected class of sheesham


3 wood

Details of cost for door shutters 2.00x1.08m = 2.16


MATERIAL
Hollock wood
Styles 4x209x9.5x3cm = 0.023 cum+
Top Rail - 1x110.5x9.5x3cm = 0.003cum+
Lock and bottom rail
2x110.5x19.7x3cm = 0.013 cum+ Beadings -
(2x312+2x150)x(1.2)x (1.2)cm = 0.001 cum.
Total = 0.040 cum+
Add for wastage @ 10% = 0.004 cum.
Total = 0.44 cum.
Say 44 cudm.
1200 Kiln seasoned selected sheesum wood planks 10 4.4 650 2860.00
2204 cudm 0.00
Carriage of Timber cum 0.044 121.29 5.34
2504 Kiln seasoning of timber cum 0.044 750 33.00
Wire gauge 2x160x40cm = 1.28 sqm.+ Add 0.00
wastage @ 10% = 0.13 sqm. 0.00
Total = 1.41 sqm. 0.00
8737 Stainless steel wire guage (Grade-304) aperture sqm 1.41 400 564.00
1.4mm and 0.50 mm dia wire 0.00
595 Bright finished or black enamelled mild steel butt 10 Nos 0.6 80 48.00
597 hinges 100x58x1.90 mm 0.00
Bright finished or black enamelled mild steel butt 10 Nos 0.2 80 16.00
637 hinges50x37x1.50 mm 0.00
Bright finished or black enamelled mild steel 100 0.48 60 28.80
screws 40 mm Nos 0.00
0.00
640 Bright finished or black enamelled mild 100 0.08 30 2.40
steel screws 20 mm Nos 0.00
LABOUR 0.00
14 Carpenter 1st class day 1.2 505.17 606.20
15 Carpenter 2nd class day 0.8 403.67 322.94
17 Beldar day 1 350.00 350.00
30 Mistry day 0.1 505.17 50.52
9999 Sundries L.S. 33.8 2.00 67.60
TOTAL 4954.80 W
Add 1 % Water charges on "W" 49.548
TOTAL 5004.35 X
Add GST (multiplying factor 0.1405) on "X" 703.11
TOTAL 5707.46 Y
Add 15 % Contractor's profit and overheads on "Y" 856.12
Total 6563.58 Z
Add Cess @ 1% on "Z" 65.64
Cost of 2.16 sqm. 6629.22
Cost of 1 sqm. 3069.08
Say 3069.10

9.134.2.2 With ISI marked stainless steel butt hinges of


required
Details of size 9.134.2.2.1
cost for Second
door shutters class teak
2.00x1.08m = 2.16
wood
MATERIAL
Teak wood (2nd class)
Styles 4x209x9.5x3cm = 0.023 cum+
Top Rail - 1x110.5x9.5x3cm = 0.003cum+
Lock and bottom rail
2x110.5x19.7x3cm = 0.013 cum+ Beadings -
(2x312+2x150)x(1.2)x (1.2)cm = 0.001 cum.
Total = 0.040 cum+
Add for wastage @ 10% = 0.004 cum.
Total = 0.44 cum.
Say 44 cudm.
1190 Second class teak wood in planks 10 4.4 791 3480.40
2204 cudm 0.00
Carriage of Timber cum 0.044 121.29 5.34
Wire gauge 2x160x40cm = 1.28 sqm.+ Add wastage 0.00
@ 10% = 0.13 sqm.
Total = 1.41 sqm. 0.00
8737 Stainless steel wire guage (Grade-304) aperture sqm 1.41 400 564.00
1.4mm and 0.50 mm dia wire 0.00
8220 Stainless steel butt hinges (heavy weight) 10 Nos 0.6 255 153.00
8218 100x60x2.5 mm IS : 12817 marked 0.00
Stainless steel butt hinges 50x37x1.5 mm IS : 10 Nos 0.2 135 27.00
8211 12817 marked 0.00
Stainless steel screws 40 mm 100 0.48 215 103.20
8214 Nos 0.00
Stainless steel screws 20 mm 100 0.08 125 10.00
LABOUR Nos 0.00
14 Carpenter 1st class day 1.2 505.17 606.20
15 Carpenter 2nd class day 0.8 403.67 322.94
17 Beldar day 1 350.00 350.00
30 Mistry day 0.1 505.17 50.52
9999 Sundries L.S. 33.8 2.00 67.60
TOTAL 5740.20 W
Add 1 % Water charges on "W" 57.402
TOTAL 5797.60 X
Add GST (multiplying factor 0.1405) on "X" 814.56
TOTAL 6612.16 Y
Add 15 % Contractor's profit and overheads on "Y" 991.82
Total 7603.98 Z
Add Cess @ 1% on "Z" 76.04
Cost of 2.16 sqm. 7680.02
Cost of 1 sqm. 3555.57
Say 3555.60

9.134.2.2. Kiln seasoned and chemically treated hollock wood


2 Details of cost for door shutters 2.00x1.08m = 2.16
sqm.
MATERIAL
Hollock wood
Styles 4x209x9.5x3cm = 0.023 cum+
Top Rail - 1x110.5x9.5x3cm = 0.003cum+
Lock and bottom rail
2x110.5x19.7x3cm = 0.013 cum+ Beadings -
(2x312+2x150)x(1.2)x (1.2)cm = 0.001 cum.
Total = 0.040 cum+
Add for wastage @ 10% = 0.004 cum.
Total = 0.44 cum.
Say 44 cudm.
2505 Hollock wood in planks 10 4.4 390 1716.00
cudm 0.00
2504 Kiln seasoning of timber cum 0.044 750 33.00
0.00
9999 Chemical treatment L.S. 9.1 2 18.20
2204 Carriage of Timber cum 0.044 121.29 5.34
Wire gauge 2x160x40cm = 1.28 sqm.+ Add
wastage @ 10% = 0.13 sqm.
Total = 1.41 sqm.
8737 Stainless steel wire guage (Grade-304) aperture sqm 1.41 400 564.00
1.4mm and 0.50 mm dia wire
8220 Stainless steel butt hinges (heavy weight) 10 Nos 0.6 255 153.00
8218 100x60x2.5 mm IS : 12817 marked
Stainless steel butt hinges 50x37x1.5 mm IS : 10 Nos 0.2 135 27
8211 12817 marked
Stainless steel screws 40 mm 100 0.48 215 103.2
8214 Nos
Stainless steel screws 20 mm 100 0.08 125 10
LABOUR Nos
14 Carpenter 1st class day 1.2 505.17 606.20
15 Carpenter 2nd class day 0.8 403.67 322.94
17 Beldar day 1 350.00 350.00
30 Mistry day 0.1 505.17 50.52
9999 Sundries L.S. 33.8 2.00 67.60
TOTAL 4027.00 W
Add 1 % Water charges on "W" 40.27
TOTAL 4067.27 X
Add GST (multiplying factor 0.1405) on "X" 571.45
TOTAL 4638.72 Y
Add 15 % Contractor's profit and overheads on "Y" 695.81
Total 5334.53 Z
Add Cess @ 1% on "Z" 53.35
Cost of 2.16 sqm. 5387.88
Cost of 1 sqm. 2494.39
Say 2494.40

9.134.2.2. Kiln seasoned selected class of sheesham wood


3 Details of cost for door shutters 2.00x1.08m = 2.16
MATERIAL
Hollock wood
Styles 4x209x9.5x3cm = 0.023 cum+ Top Rail -
1x110.5x9.5x3cm = 0.003cum+ Lock and bottom rail
2x110.5x19.7x3cm = 0.013 cum+ Beadings -
(2x312+2x150)x(1.2)x (1.2)cm = 0.001 cum. Total =
0.040 cum+
Add for wastage @ 10% = 0.004 cum. Total = 0.44
cum.
Say 44 cudm.
1200 Kiln seasoned selected sheesum wood planks 10 4.4 650 2860.00
2504 cudm 0.00
Kiln seasoning of timber cum 0.044 750 33.00
2204 Carriage of Timber cum 0.044 121.29 5.34
Wire gauge 2x160x40cm = 1.28 sqm.+ Add
wastage @ 10% = 0.13 sqm.
Total = 1.41 sqm.
8737 Stainless steel wire guage (Grade-304) aperture sqm 1.41 400 564.00
1.4mm and 0.50 mm dia wire
8220 Stainless steel butt hinges (heavy weight) 10 Nos 0.6 255 153.00
8218 100x60x2.5 mm IS : 12817 marked
Stainless steel butt hinges 50x37x 10 Nos 0.2 135 27
1.5 mm IS : 12817 marked 0
8211 Stainless steel screws 40 mm 100 0.48 215 103.20
8214 Nos
Stainless steel screws 20 mm 100 0.08 125 10
LABOUR Nos
14 Carpenter 1st class day 1.2 505.17 606.20
15 Carpenter 2nd class day 0.8 403.67 322.94
17 Beldar day 1 350.00 350.00
30 Mistry day 0.1 505.17 50.52
9999 Sundries L.S. 33.8 2.00 67.60
TOTAL 5152.80 W
Add 1 % Water charges on "W" 51.528
TOTAL 5204.33 X
Add GST (multiplying factor 0.1405) on "X" 731.21
TOTAL 5935.54 Y
Add 15 % Contractor's profit and overheads on "Y" 890.33
Total 6825.87 Z
Add Cess @ 1% on "Z" 68.26
Cost of 2.16 sqm. 6894.13
Cost of 1 sqm. 3191.73
Say 3191.70

9.135 Providing and fixing fly proof stainless steel


grade 304 wirewindows
and clerestory gauge, tousing
windows
wire gauge
with
mm in both directions with wire1.4
average width of aperture of dia. 0.50
9.135.1 mm all complete.
With 2nd class teak wood beading 62X19
mm
Details of cost for a window of size 140x110cm
=1.54sqm.
MATERIAL
Wire gauze -20x60mm mesh 3.2mm wide =
1.4x1.1m = 1.54sqm.+ Add wastage @ 10% =
0.15sqm.
Total = 1.69 sqm.
8737 Stainless steel wire guage (Grade-304) aperture sqm 1.69 400 676.00
1.4mm and 0.50 mm dia wire
9977 Carriage of wire fabric L.S. 1.82 2 3.64
Second class teak wood beading
5mx62mmx19mm = 0.0059cum.
Add wastage @ 10% = 0.00059cum.
Total = 0.00649cum. Say 6 cudm.
1190 Second class teak wood in planks 10 0.6 791 474.60
2204 cudm 121.29 0.00
Carriage of Timber cum 0.006 121.29 0.73
LABOUR
15 Carpenter 2nd class day 0.33 403.67 133.21
17 Beldar day 0.25 350.00 87.50
9999 Sundries L.S. 19.76 2.00 39.52
TOTAL 1415.20 W
Add 1 % Water charges on "W" 14.152
TOTAL 1429.35 X
Add GST (multiplying factor 0.1405) on "X" 200.82
TOTAL 1630.17 Y
Add 15 % Contractor's profit and overheads on "Y" 244.53
Total 1874.70 Z
Add Cess @ 1% on "Z" 18.75
Cost of 1.54 sqm. 1893.45
Cost of 1 sqm. 1229.51
Say 1229.50

9.135.2 With 12 mm mild steel U beading


Details of cost for a window of size 140x110cm
=1.54sqm.
MATERIAL
Wire gauze -20x60mm mesh 3.2mm wide =
1.4x1.1m = 1.54sqm.+ Add wastage @ 10% =
0.15sqm.
Total = 1.69 sqm.
8737 Stainless steel wire guage (Grade-304) aperture sqm 1.69 400 676.00
1.4mm and 0.50 mm dia wire
9977 Carriage of wire fabric L.S. 1.82 2 3.64
7349 12 mm M.S. 'U' beading metre 5 14 70.00
LABOUR
15 Carpenter 2nd class day 0.33 403.67 133.21
17 Beldar day 0.25 350.00 87.50
9999 Sundries L.S. 19.76 2.00 39.52
TOTAL 1009.87 W
Add 1 % Water charges on "W" 10.0987
TOTAL 1019.97 X
Add GST (multiplying factor 0.1405) on "X" 143.31
TOTAL 1163.28 Y
Add 15 % Contractor's profit and overheads on "Y" 174.49
Total 1337.77 Z
Add Cess @ 1% on "Z" 13.38
Cost of 1.54 sqm. 1351.15
Cost of 1 sqm. 877.37
Say 877.40

9.136 Providing and fixing fire resistant door


frame
built inof section
rebate made143out
x 57 ofmm having
16 SWG G.I.
sheet (zinc coating not less
gm/sqm) duly filled with vermuculitethan 120
based
mounting concrete mix, suitable
60 minutes fire ratedfordoor
shutters.
intumuscent Thefireframe is fitted
seal strip with
of size 10x4 mm
(minimum) alround the frame and
fixing with dash fastener of approved size
and make, including
of approved applying
brand fire a coat
resistant primer etc.
complete as per direction of
Engineer-in-charge (Dash fastener to be
paid for separately).
Details of cost for 3300/2750mm Door (9.10 metre
length)

MATERIAL
8738 Factory made door frame fire rated ( 60 minutes) metre 9.1 1050 9555.00
made with 16 SWG G.I. Sheet of section 143 mm
x 57 mm duly filled with
vermuculite based concrete mix
LABOUR
9999 Labour for fixing L.S. 130 2 260.00
9988 Sundries and carriage L.S. 4.23 2.00 8.46
TOTAL 9823.46 W
Add 1 % Water charges on "W" 98.2346
TOTAL 9921.69 X
Add GST (multiplying factor 0.1405) on "X" 1394.00
TOTAL 11315.69 Y
Add 15 % Contractor's profit and overheads on "Y" 1697.35
Total 13013.04 Z
Add Cess @ 1% on "Z" 130.13
Cost of 9.10 metres 13143.17
Cost of 1.00 metre 1444.3
Say 1444.30

9.137 Providing and fixing 50 mm thick glazed


fire resistant
minutes door shutters
fire rating conformingof 60to IS:3614
(Part-II), tested and certified
laboratory approved by Engineer-in- as per
charge, with suitable
frame, consisting mounting
of vertical on door
styles, lock
rail, top rail 100 mm wide,
200 mm wide, made out of 16 SWG bottom rail
G.I.sheet
gm/m2) duly (zinc coating
filled not less than
FR insulation 120
material
and
steelfixing with necessary
ball bearing hinges ofstainless
approved
make, including
approved applying
fire resistant a coat
primer of all
etc.
complete
charge as per direction
(panneling of Engineer-in-
to be paid for
separately).
Details of cost for 3.50 sqm (Door size1710x2050 m
MATERIAL
8739 Fire rated door shuttere made with 16 SWG sqm 3.5 4500 15750.00
G.I. sheet( 60 minutes) without panel
LABOUR
9999 Labour for fixing L.S. 180 2 360.00
9988 Sundries & Carriage L.S. 10 2.00 20.00
TOTAL 16130.00 W
Add 1 % Water charges on "W" 161.3
TOTAL 16291.30 X
Add GST (multiplying factor 0.1405) on "X" 2288.93
TOTAL 18580.23 Y
Add 15 % Contractor's profit and overheads on "Y" 2787.03
Total 21367.26 Z
Add Cess @ 1% on "Z" 213.67
Cost of 3.50 sqm 21580.93
Cost of 1 sqm 6165.98
Say 6166.00

9.138 Providing and fixing glazing in fire resistant


door shutters,
partitions etc., fixed panels
with G.I. &
beading made out
of 1.6 mm thick G.I. sheet (zinc
coating not less than 120 gm/m²) of size
20
SS xscrews
33 mmatscrewed
distancewith
75 mm M4 xfrom
38 mm
the
edges and 150 mm c/c , including
applying a coat of approved fire resistant
primer/powder
than 30 micron coating
on G.I. of not less& special
beading,
ceramic tape
complete in allofrespect
5 x 20 mmas persize etc 2016,
NBC
IS 16231 (Part 3):2016 and as per
direction of Engineer-in-charge with glass
of required
minutes thickness
of fire having
resistance both60integrity &
radiation
minimum control
20 minutes(EW60) and
of insulation (EI20).
The manufacturer have to give test
report/certification of fire glass and the
glass should
the value of E,have
EWthe stamp
& EI. The showing
glass shall be
tested in approved NABL accredited
lab or by any other accreditation body
which
ISO/IEC operates
17011 in andaccordance with as per
accredits labs
ISO/IEC
calibration17025
scopes for shall
testingbeand
eligible. The
maximum glazing size
more than 1100x2200 mm (w shall not be or 2.42
x h)
sqm
Details of cost for 2.46 sqm (Door size
1710 mm x 2050 mm) Glazing area =
2x0.679x1.808= 2.46sqm.
MATERIAL
8760 Glass panes of required thickness having sqm 2.46 22500 55350.00
60 minutes of fire resistance both integrity
and radiation control (EW 60) and
minimum 20 minutes of Insulation
2641 (EI 20)
G.I. U beading of 1.6 mm thick G.I. Sheet with metre 9.91 245 2427.95
2642 M4x38mm SS screws 0.00
Ceramic tape 5x20 mm size metre 19.82 410 8126.20
9999 For fixing in position all complete L.S. 180 2 360.00
9988 Sundries & Carriage L.S. 10 2.00 20.00
TOTAL 66284.15 W
Add 1 % Water charges on "W" 662.8415
TOTAL 66946.99 X
Add GST (multiplying factor 0.1405) on "X" 9406.05
TOTAL 76353.04 Y
Add 15 % Contractor's profit and overheads on "Y" 11452.96
Total 87806.00 Z
Add Cess @ 1% on "Z" 878.06
Cost of 2.46 sqm 88684.06
Cost of 1 sqm 36050.43
Say 36050.40

9.139 Providing and fixing panic bar / latch


(Double
Trim Latch point)
& Lockfittedonwith
backa single
side ofbody,
the
Panic Latch of reputed brand
manufacture to be approved by the and
Engineer-
Details in-forcharge,
of cost 1 Nos all complete.
MATERIAL
8744 Panic Bar / latch (Double point) each 1 5200 5200.00
LABOUR 0.00
14 Carpenter 1st class day 0.17 505.17 85.88
9977 Sundries (screws and carriage) L.S. 3.64 2.00 7.28
TOTAL 5293.16 W
Add 1 % Water charges on "W" 52.9316
TOTAL 5346.09 X
Add GST (multiplying factor 0.1405) on "X" 751.13
TOTAL 6097.22 Y
Add 15 % Contractor's profit and overheads on "Y" 914.58
Total 7011.80 Z
Add Cess @ 1% on "Z" 70.12
Total 7081.92
Cost of 1 No 7081.92
Say 7081.90

9.140 Providing and fixing plain lining with


9.140.1 necessary
12mm thickscrews/nuts
commercial&ply bolts/ nails, to
conforming
including
IS : 1328
Details
a coat
BWR
of cost
of
type
for 10
approved
sqm
primer on one
face, and fixed on wooden /steel frame
MATERIAL
2413 12 mm commercial ply Priming coat sqm 11 500 5500.00
13.50.1 Rate as per Item Number 13.50.1 of SH: Finishing sqm 10 38.95 389.50 A
9999 Sundries and screws etc. L.S. 40.1 2.00 80.20
LABOUR
41 Carpenter (average) day 1.28 403.67 516.70
17 Beldar day 1.43 350.00 500.50
9988 Sundries and carriage L.S. 33.56 2.00 67.12
TOTAL 7054.02 W
Add 1 % Water charges on "W-A" 6664.52 66.6452
TOTAL X
Add GST (multiplying factor 0.1405) on "X-A" 6731.17 945.73
TOTAL Y
Add 15 % Contractor's profit and overheads on "Y- 7676.90 1151.53
A"
Total Z
Add Cess @ 1% on "Z-A" 8828.43 88.28
Cost of 10 sqm 9306.21
Cost of 1 sqm 930.62
Say 930.60

9.141 Providing and fixing PVC Door Frame of


size 50x47
of 5 mm (± mm with amade
0.2 mm), wall thickness
out of single
piece
cut extruded
joints PVC
and joint profile,
with 2 noswith mitred
of PVC
bracket
arms of of sizesection
cross 190 mm x 100
size 35 xmm15 long
mm &
self driven self taping screws, the
vertical door profiles to be reinforced with
40x20
0.8 mmmm M.S. rectangular
, including providing tube
EPDM of rubber
gasket weather seal
frame, including throughout
jointing 5 mm PVC the frame
strip with of
the back PVCthesolvent
profile. cement
The door onframe to
be
longfixed to the
anchor wall using
fasteners 8 x100 mm
complete, all as per
manufacturer's specification
direction of Engineer -in- charge. and
Details of cost for one door frame of 5 metre
MATERIAL
8014 Factory made door frame of size 50x47mm with meter 5 298.74 1493.70
wall thickness 5 mm made of single
piecs extruded profile
LABOUR
41 Carpenter (average) day 0.15 403.67 60.55
17 Beldar day 0.15 350.00 52.50
9999 Sundries L.S. 11.65 2.00 23.30
TOTAL 1630.05 W
Add 1 % Water charges on "W" 16.3005
TOTAL 1646.35 X
Add GST (multiplying factor 0.1405) on "X" 231.31
TOTAL 1877.66 Y
Add 15 % Contractor's profit and overheads on "Y" 281.65
Total 2159.31 Z
Add Cess @ 1% on "Z" 21.59
Cost of 5 metres 2180.90
Cost of 1 metre 436.18
Say 436.20

9.142 35 mm thick factory made Solid panel PVC


Door
piece shutter,
extrudedmade soildout
PVC of profiles,
single 5 mm (±
0.2 mm)lock
(except thick, having
rail) of sizestyles & rails
95 mmx 35 mm x
5 mm, out of which 75 mm shall
flat and 20 mm shall be tapered (on both be
side), having one
mm integrally side thickness
extruded of 15side of
on the hinge
the profile
power, for better
including screw holding
reinforcing with MS tube
of size 40 mm X 20 mm x 1 mm,
joints of styles & rails to be mitered cut &
joint withself
cement, the driven
help ofself
PVC solvent
tapping screws &
M.S. rectangular pipes bracket
size 190 mm X 100 mm of cross section of
size 35 Single
corner. mm x 17 mmextruded
piece x 1 mm at eachthick
5 mm
solid
35 mm,PVC outLock rail of75
of which size
mm115 mmflat
to be x and
20 mm 15
having to bemmtapered at both
solid core ends, of rail
in middle
section
styles &integrally
rails with extruded,
the help offixing the and
solvent
self driven
125 mm x 11 selfmm,
tapping screws
including of
providing 5
mm Single
sheet inserted piece soliddoor
in the PVCasextruded
panel, all
complete as per manufacturer's
specification and direction of Engineer-in-
9.142.1 charge.
Non decorative finish (matt finish)
Details of cost for of one shutter
2.20x1.08m = 2.38 sqm
MATERIAL
8735 35 mm thick factory made solid panel sqm 2.38 2150 5117.00
PVC door shutter of single pieceextruded profile
8100 non decorative finished (Matt finished) 0.00
Powder coated M.S. butt hinges 10 Nos 0.4 123 49.2
100mm X58mmX1.9mm
637 Bright finished or black enamelled mild steel 100 0.48 60 28.80
640 screws 40 mm Nos 0.00
Bright finished or black enamelled mild 100 0.08 30 2.4
steel screws 20 mm Nos
LABOUR
41 Carpenter (average) day 0.4 403.67 161.47
17 Beldar day 0.4 350.00 140.00
9999 Sundries L.S. 30.35 2.00 60.70
TOTAL 5559.57 W
Add 1 % Water charges on "W" 55.5957
TOTAL 5615.17 X
Add GST (multiplying factor 0.1405) on "X" 788.93
TOTAL 6404.10 Y
Add 15 % Contractor's profit and overheads on "Y" 960.61
Total 7364.71 Z
Add Cess @ 1% on "Z" 73.65
Cost of 2.38 sqm 7438.36
Cost of 1 sqm 3125.36
Say 3125.40

9.142.2 Decorative finish (wood grained finish)


Details of cost for of one shutter
2.20x1.08m = 2.38 sqm
MATERIAL
8736 35 mm thick factory made solid panel PVC door sqm 2.38 2600 6188.00
shutter of single pieceextruded profile decorative
8100 finished (Wood grand finished) 0.00
Powder coated M.S. butt hinges 10 Nos 0.4 123 49.2
100mm X58mmX1.9mm
637 Bright finished or black enamelled mild steel 100 0.48 60 28.80
640 screws 40 mm Nos 0.00
Bright finished or black enamelled mild 100 0.08 30 2.4
steel screws 20 mm Nos
LABOUR
41 Carpenter (average) day 0.4 403.67 161.47
17 Beldar day 0.4 350.00 140.00
9999 Sundries L.S. 30.35 2.00 60.70
TOTAL 6630.57 W
Add 1 % Water charges on "W" 66.3057
TOTAL 6696.88 X
Add GST (multiplying factor 0.1405) on "X" 940.91
TOTAL 7637.79 Y
Add 15 % Contractor's profit and overheads on "Y" 1145.67
Total 8783.46 Z
Add Cess @ 1% on "Z" 87.83
Cost of 2.38 sqm 8871.29
Cost of 1 sqm 3727.43
Say 3727.40

9.143 Providing and Fixing factory made uPVC


door
Detailsframe, made
of cost for of uPVC
one door frame exturded
of 5 metre
sections, of size 65 mm x 55 mm with wall
thickness 2.0 mm (± 0.2 mm), corners of
MATERIAL
8745 65mm x 55mm x 2mm thick Factory made door metre 5 355 1775.00
frame of PVC extruded section in
white,grey or wooden finish
LABOUR
41 Carpenter (average) day 0.15 403.67 60.55
17 Beldar day 0.15 350.00 52.50
9999 Sundries L.S. 4.68 2.00 9.36
TOTAL 1897.41 W
Add 1 % Water charges on "W" 18.9741
TOTAL 1916.38 X
Add GST (multiplying factor 0.1405) on "X" 269.25
TOTAL 2185.63 Y
Add 15 % Contractor's profit and overheads on "Y" 327.85
Total 2513.48 Z
Add Cess @ 1% on "Z" 25.13
Cost of 5 metres 2538.61
Cost of 1 metre 507.72
Say 507.70

9.144 Providing and fixing 37 mm thick factory


made PVC of
rails made door
PVC shutter,
hollowstyles and
section of size
100 mm x 37 mm with wall thickness
2 mm (± 0.2 mm), with inbuilt bead on one
side, styles
and joint andcorners
at the rails mitered cut of 2 nos
by means
of
220plastic
mm at brackets
each cornerof size 75stainless
and mm x steel
screws,
of style byreinforcing
inserting thePVC hinge side
profile of size 28
mm x 30 mm, with wall thickness
mm ( ± 0.2 mm). Lockrail of size 100 2 mm x
37
mm) mm,
willwall thickness
be fixed to the2vertical
mm (+ styles.
0.2
Providing
panel of size with100
PVC mm snapfit beads
x 20 mm, and
and
inserting
fastening2with nos tie
nutsbarand
of 6 washers
mm dia and
complete,
specification alland
as direction
per manufacturer's
of Engineer-in-
charge.
Details of cost for of one shutter
2.20x1.08m = 2.38 sqm
MATERIAL
8746 37 mm thick Factory made shutter with style,rails sqm 2.38 2400 5712.00
and panels of PVC extruded
section in white or grey finish i/c carriage
LABOUR
41 Carpenter (average) day 0.4 403.67 161.47
17 Beldar day 0.4 350.00 140.00
9999 Sundries L.S. 20.36 2.00 40.72
TOTAL 6054.19 W
Add 1 % Water charges on "W" 60.5419
TOTAL 6114.73 X
Add GST (multiplying factor 0.1405) on "X" 859.12
TOTAL 6973.85 Y
Add 15 % Contractor's profit and overheads on "Y" 1046.08
Total 8019.93 Z
Add Cess @ 1% on "Z" 80.20
Cost of 2.38 sqm 8100.13
Cost of 1 sqm 3403.42
Say 3403.40

9.145 Providing and Fixing factory made PVC


door frame
sections made
of size 75ofmm
PVC extruded
x 53 mm, having
wall thickness 2.0 mm (± 0.2
Both verticals sides of the frame mm).reinforced
with PVC profile of cross section
size 28 mm x 30 mm x 2 mm thickness (±
0.2 mm) and
including 75 mm both
reinforcing x 200ends
mm of
long,
the top
frame with PVC profile. PVC Door
Frame and PVC reinforcement profile to be
mitred
weldedcut, jointedincluding
together, and fusion
providing and
fixing 3 nos of 125 mm long
steel hinges to frame, fixing the stainless
frame with
jamb with
anchor required
dash nosall
fastener, & complete
sizes of as per
manufacturer's specification
direction of engineer- and
in-charge.
Details of cost for one door frame of 5 metre
MATERIAL
8747 75mm x 53mm x 2.0mm thick Factory made door metre 5 400 2000.00
frame of PVC extruded section
in white,grey or wooden finish
LABOUR
41 Carpenter (average) day 0.15 403.67 60.55
17 Beldar day 0.15 350.00 52.50
9999 Sundries L.S. 4.68 2.00 9.36
TOTAL 2122.41 W
Add 1 % Water charges on "W" 21.2241
TOTAL 2143.63 X
Add GST (multiplying factor 0.1405) on "X" 301.18
TOTAL 2444.81 Y
Add 15 % Contractor's profit and overheads on "Y" 366.72
Total 2811.53 Z
Add Cess @ 1% on "Z" 28.12
Cost of 5 metres 2839.65
Cost of 1 metre 567.93
Say 567.90
9.146 Providing and fixing 37 mm thick factory
made PVC of
rails made DoorPVC shutter,
hollowstyles
extrudedandprinted
and
overalllaminated
dimension section
115 mmhavingx 37 mm with
wall
inbuilt beading on one side,mm)
thickness 2 mm (± 0.2 with and
the styles
railsinserting
by mitred cut
2 nosandPVCjointprofile
at corners
reinforcement
cross of size
section size 75mm
of 28 mmxx30 200mmmm
long with
having wall thickness 2 mm (± 0.2 mm).
Styles, rails and reinforcements to be
fusion
verticalwelded
style totogether. Only hinge
be reinforced side
with PVC
profile
Printedreinforcement
and laminatedinPVC full length.
lock rail of size
110 mm x 37 mm having wall
thickness 2 mm (± 0.2 mm) to be welded
horizontally
after inserting withPVCtheprofile
vertical styles
reinforcement as
in styles and rails, providing with
PVC snap fit beading, panels of 100 x 20
mm
2 nosprinted
6 mm &dia laminated androd
bright steel inserting
horizontally
with both side threaded and
tightened with check nuts and washers
complete,
specification all and
as per manufacturer's
direction of engineer-in-
charge.
Details of cost for of one shutter
2.20x1.08m = 2.38 sqm
MATERIAL
8748 37 mm thick Factory made fusion welded shutter sqm 2.38 2600 6188.00
with style,rails and panels of PVC
extruded section in wooden finish.
LABOUR
41 Carpenter (average) day 0.4 403.67 161.47
17 Beldar day 0.4 350.00 140.00
9999 Sundries L.S. 20.36 2.00 40.72
TOTAL 6530.19 W
Add 1 % Water charges on "W" 65.3019
TOTAL 6595.49 X
Add GST (multiplying factor 0.1405) on "X" 926.67
TOTAL 7522.16 Y
Add 15 % Contractor's profit and overheads on "Y" 1128.32
Total 8650.48 Z
Add Cess @ 1% on "Z" 86.50
Cost of 2.38 sqm 8736.98
Cost of 1 sqm 3671
Say 3671.00

9.147A Providing and fixing factory made uPVC


white colour casement/casement
fixed glazed windows comprising of cumuPVC
multi-chambered frame, sash and
mullion (where ever required) extruded
profiles
mm thick duly reinforced
galvanized with
mild 1.60section
steel ± 0.2
made from
required roll forming
length (shape &process of
size according to
uPVC profile), uPVC extruded
glazing beads of appropriate dimension,
EPDM
grade) gasket, stainless
friction hinges, zincsteel (SS
alloy 304
(white
powder
fasteners coated)
100 x 8 casement
mm size handles,
for fixing G.I
frame
to finished wall, plastic packers,
plastic caps and necessary stainless steel
screws
shall beetc.
mitredProfile
cut ofandframe
fusion & welded
sash at all
corners,
be mullion
also fusion (if required)
welded including shall
drilling of
holes for fixing hardware's and
drainage of water etc. After fixing frame
the gap between
finished wall shallframe andwith
be filled adjacent
weather
proof
of required size and of approved rod
silicon sealant over backer quality, all
complete as per approved drawing
& direction of Engineer-in-Charge. (Single /
double
sealant glass
shall be panes
paidand silicon
separately)
Note: For uPVC frame, sash and mullion
extruded
dimensionprofiles minus&5%
i.e. in depth widthtolerance in
of profile
shall
profilebedimension
acceptable. Variation
in higher sideinshall be
accepted
this account butshall
no extra payment on
be made.
9.147A.1 Casement window single panel with S.S.
friction
made ofhinges(small(300
series)x 19frame
x 1.947 mm),
x 50 mm
& sash 47 x 68 mm both having
thickness of 1.9 ± 0.2 mm and single glass wall
pane glazing
dimension. beadofofwindow
(Area appropriateupto 0.75
sqm.)
Detail of Cost for uPVC casement window size 0.50
x 1.35 m = 0.68 sqm
MATERIAL
8121 uPVC extruded (small series) casement metre 3.89 258.3 1004.79
window frame size 47x50mm i/c 5% wastage
8122 uPVC extruded (small series) casement metre 3.68 282.9 1041.07
window sash/window mullion size 47x68 mm i/c
8125 5% wastage 0.00
uPVC extruded glazing bead of appropriate metre 3.49 98.4 343.42
dimension for small series casement
window Sash
Galvanized iron reinforcement for :-
3991 Galvanized iron (1.6 ± 0.2 mm) thick reinforcement metre 6.97 66 460.02
for small series casement
window frame, sash, mullion i/c 5% wastage
Window Frame = 3.59 M + Window
Sash = 3.38 M
Total = 6.97 M
7390 EPDM Gasket for uPVC window i/c 5% wastage metre 14.55 19 276.45
3995 G.I fasteners 100 x 8 mm each 8 14 112.00
8757 Stainless steel friction hinges (SS-304 grade) size each 2 245 490.00
300 x 19 x 1.9 mm for uPVC window
8750 Zinc alloy (white powder coated) casement handle each 1 130 130.00
for uPVC window
9999 Sundries, plastic packers, plastic caps, L.S. 170 2.00 340.00
SS screws and carriage of material
LABOUR
46 Labour for fabrication of uPVC extruded casement sqm 0.68 485.00 329.80
windows including drilling holes, fixing of fittings &
hardwares, hire charges of drill machine and
47 electricity charges etc. 0.00
Labour for installation of uPVC extruded casement sqm 0.68 430 292.4
windows including scaffolding
TOTAL 4819.95 W
Add 1 % Water charges on "W" 48.1995
TOTAL 4868.15 X
Add GST (multiplying factor 0.1405) on "X" 683.98
TOTAL 5552.13 Y
Add 15 % Contractor's profit and overheads on "Y" 832.82
Total 6384.95 Z
Add Cess @ 1% on "Z" 63.85
Cost of 0.68 sqm 6448.80
Cost of 1.00 sqm 9483.53
Say 9483.50

9.147A.2 Casement window double panels with


S.S.
mm) friction
made of hinges
(small(300 x 19 frame
series) x 1.9 47
x 50 mm,
mullion 47sash
x 68 47
mmx 68 mm & wall
all having
thickness
glazing of 1.9
bead ± 0.2 mm and
of appropriate single
dimension.
(Area of window above 0.75 sqm upto 1.50
sqm).
Detail of cost for uPVC casement window size 1.00
x 1.35 m = 1.35 sqm.
MATERIAL
8121 uPVC extruded (small series) casement metre 4.94 258.3 1276.00
window frame size 47x50mm i/c 5% wastage
8122 uPVC extruded (small series) casement metre 8.86 282.9 2506.49
window sash/window Mullion size 47x68
mm i/c 5% wastage
Window Sash = 7.44 M + Window Mullion
= 1.42 M
Total = 8.86 M
8125 uPVC extruded glazing bead of appropriate metre 7.06 98.4 694.70
dimension for small series casement
window Sash i/c 5% wastage
Galvanized iron reinforcement for
3991 Galvanized iron (1.6 ± 0.2 mm) thick reinforcement metre 12.63 66 833.58
for small series casement
window frame, sash, mullion i/c 5% wastage
Window Frame = 4.64 M + Window Sash =

6.64 M + Window Mullion = 1.35 M 0.00


Total = 12.63 M
7390 EPDM Gasket for uPVC window i/c 5% wastage metre 27.91 19 530.29
3995 G.I fasteners 100 x 8 mm each 10 14 140.00
8757 Stainless steel friction hinges (SS-304 grade) size each 4 245 980.00
300 x 19 x 1.9 mm for uPVC window
8750 Zinc alloy (white powder coated) casement handle each 2 130 260.00
for uPVC window
9999 Sundries, plastic packers, plastic caps, L.S. 170 2.00 340.00
SS screws and carriage of material
LABOUR
46 Labour for fabrication of uPVC extruded casement sqm 1.35 485.00 654.75
windows including drilling holes, fixing of fittings &
hardwares, hire charges of drill machine and
47 electricity charges etc. 0.00
Labour for installation of uPVC extruded casement sqm 1.35 430 580.5
windows
including scaffolding
TOTAL 8796.31 W
Add 1 % Water charges on "W" 87.9631
TOTAL 8884.27 X
Add GST (multiplying factor 0.1405) on "X" 1248.24
TOTAL 10132.51 Y
Add 15 % Contractor's profit and overheads on "Y" 1519.88
Total 11652.39 Z
Add Cess @ 1% on "Z" 116.52
Cost of 1.35 sqm 11768.91
Cost of 1.00 sqm 8717.71
Say 8717.70

9.147A.3 Casement window double panels with top


fixed
19 withmm)
x 1.9 S.S.made
friction
of hinges (350 x frame
(small series)
47 x 50 47
mullion mm, sash
x 68 mm47allx having
68 mmwall
&
thickness of 1.9 ± 0.2 mm and
glazing bead of appropriate dimension.single
(Detail
Areaofof window
cost for uPVC upto 2.50 sqm).
casement window size 1.20
x 1.80 m = 2.16 sqm
MATERIAL
8121 uPVC extruded (small series) casement metre 6.3 258.3 1627.29
window frame size 47x50mm i/c 5% wastage
8122 uPVC extruded (small series) casement metre 9.8 282.9 2772.42
window sash/window Mullion size 47x68
mm i/c 5% wastage Window Sash = 7.28 M +
Window Mullion = 2.52 M
Total = 9.80 M
8125 uPVC extruded glazing bead of appropriate metre 10.62 98.4 1045.01
dimension for small series
casement window Sash i/c 5% wastage
3991 Galvanized iron reinforcement for :- metre 15.05 66 993.30
Galvanized iron (1.6 ± 0.2 mm) thick reinforcement
for small series casement
window frame, sash, mullion i/c 5% wastage
Window Frame = 6.00 M + Window Sash =
6.68 M + Window Mullion = 2.37 M
Total = 15.05 M
7390 EPDM Gasket for uPVC window i/c 5% wastage metre 37.34 19 709.46
3995 G.I fasteners 100 x 8 mm each 12 14 168.00
8758 Stainless steel friction hinges (SS-304 grade) size each 4 345 1380.00
8750 350 x 19 x 1.9 mm for uPVC window
Zinc alloy (white powder coated) casement handle each 2 130 260
for uPVC window
9999 Sundries, plastic packers, plastic caps, L.S. 170 2.00 340.00
SS screws and carriage of material
LABOUR
46 Labour for fabrication of uPVC extruded casement sqm 2.16 485.00 1047.60
windows including drilling holes, fixing of fittings &
hardwares, hire charges of drill machine and
47 electricity charges etc. 0.00
Labour for installation of uPVC extruded casement sqm 2.16 430 928.8
windows including scaffolding
TOTAL 11271.88 W
Add 1 % Water charges on "W" 112.7188
TOTAL 11384.60 X
Add GST (multiplying factor 0.1405) on "X" 1599.54
TOTAL 12984.14 Y
Add 15 % Contractor's profit and overheads on "Y" 1947.62
Total 14931.76 Z
Add Cess @ 1% on "Z" 149.32
Cost of 2.16 sqm 15081.08
Cost of 1.00 sqm 6981.98
Say 6982.00

9.147A.4 Casement window single panel with S.S.


friction
made ofhinges (400 x 19 x 1.9
(big series)frame 67 xmm)
60 mm &
sash 67 x 80 mm both having wall
thickness of 2.3 ± 0.2 mm and single
glazing beaddimension.
appropriate / double glazing bead
(Area of of
window
aboveof0.75
Detail sqm.)
cost for uPVC casement window size 0.70
x 1.35 m = 0.95 sqm
MATERIAL
8126 uPVC extruded (big series) casement metre 4.31 319.8 1378.34
window frame size 67x60 mm i/c 5% wastage
8128 uPVC extruded (big series) casement metre 4.02 426.4 1714.13
window sash/window mullion size 67x80 mm i/c
8130 5% wastage 0.00
uPVC extruded glazing bead of appropriate metre 3.83 123 471.09
dimension for big series casement window
sash i/c 5% wastage
Galvanized iron reinforcement for :-
3992 Galvanized iron (1.6 ± 0.2 mm) thick reinforcement metre 7.73 71 548.83
for big series casement window frame, sash,
mullion, i/c 5%
wastage
Window Frame = 4.01 M + Window Sash =
3.72 M
Total = 7.73 M
7390 EPDM Gasket for uPVC window i/c 5% wastage metre 15.99 19 303.81
3995 G.I fasteners 100 x 8 mm each 10 14 140.00
8759 Stainless steel friction hinges (SS-304 grade) size each 2 365 730.00
8750 400 x 19 x 1.9 mm for uPVC window
Zinc alloy (white powder coated) casement handle each 1 130 130
for uPVC window
9999 Sundries, plastic packers, plastic caps, L.S. 170 2.00 340.00
SS screws and carriage of material
LABOUR
46 Labour for fabrication of uPVC extruded casement sqm 0.95 485.00 460.75
windows including drilling holes, fixing of fittings &
hardwares, hire charges of drill machine and
47 electricity charges etc. 0.00
Labour for installation of uPVC extruded casement sqm 0.95 430 408.5
windows including scaffolding
TOTAL 6625.45 W
Add 1 % Water charges on "W" 66.2545
TOTAL 6691.70 X
Add GST (multiplying factor 0.1405) on "X" 940.18
TOTAL 7631.88 Y
Add 15 % Contractor's profit and overheads on "Y" 1144.78
Total 8776.66 Z
Add Cess @ 1% on "Z" 87.77
Cost of 0.95 sqm 8864.43
Cost of 1.00 sqm 9330.98
Say 9331.00

9.147A.5 Casement window double panels with S.S.


friction
made ofhinges (350 x 19 x 1.9
(big series)frame 67 xmm)
60 mm &
sash / mullion 67 x 80 mm both
wall thickness of 2.3 ± 0.2 mm and having
single
glazing bead/ double glazing bead
appropriate dimension. (Area of window of
above 1.50 sqm).
Detail of Cost for uPVC casement window size 1.20
x 1.35 m = 1.62 sqm.

MATERIAL
8126 uPVC extruded (big series) casement metre 5.36 319.8 1714.13
window frame size 67x60 mm i/c 5% wastage
8128 uPVC extruded (big series) casement metre 9.13 426.4 3893.03
window sash/window mullion size 67x
80 mm i/c 5% wastage
Window Sash = 7.71 M + Window Mullion =
1.42 M
Total = 9.13 M
8130 uPVC extruded glazing bead of appropriate metre 7.34 123 902.82
dimension for big series casement window
sash i/c 5% wastage
Galvanized iron reinforcement for :-
3992 Galvanized iron (1.6 ± 0.2 mm) thick reinforcement metre 13.83 71 981.93
for big series casement window frame, sash,
mullion i/c 5%
wastage
Window Frame = 5.31 M + Window Sash =
7.11 M + Window Mullion = 1.41 M
Total = 13.83 M
7390 EPDM Gasket for uPVC window i/c 5% wastage metre 30.62 19 581.78
3995 G.I fasteners 100 x 8 mm each 12 14 168.00
8758 Stainless steel friction hinges (SS-304 grade) size each 4 345 1380.00
8750 350 x 19 x 1.9 mm for uPVC window
Zinc alloy (white powder coated) casement handle each 2 130 260
for uPVC window
9999 Sundries, plastic packers, plastic caps, L.S. 170 2.00 340.00
SS screws and carriage of material
LABOUR
46 Labour for fabrication of uPVC extruded casement sqm 1.62 485.00 785.70
windows including drilling holes, fixing of fittings &
hardwares, hire charges of drill machine and
electricity charges etc.
47 Labour for installation of uPVC extruded casement sqm 1.62 430.00 696.60
windows including scaffolding
TOTAL 11703.99 W
Add 1 % Water charges on "W" 117.0399
TOTAL 11821.03 X
Add GST (multiplying factor 0.1405) on "X" 1660.85
TOTAL 13481.88 Y
Add 15 % Contractor's profit and overheads on "Y" 2022.28
Total 15504.16 Z
Add Cess @ 1% on "Z" 155.04
Cost of 1.62 sqm 15659.20
Cost of 1.00 sqm 9666.17
Say 9666.20

9.147A.6 Casement cum fixed panel window having


both
middleend single
fixed casement
panels and at panel,
top completely
fixed ventilator
hinges (350 x 19 with S.S made
x 1.9) frictionof (big
series)
mm , & frame
mullion6767x x6080mm
mm, sash 67 x 80
all having wall
thickness of 2.3 ± 0.2 mm and
glazing bead/double glazing bead of single
appropriate
above 3.00 sqm dimension.
upto 5.00(Area of window
sqm).
Detail of cost for uPVC casement cum fixed window
size 2.50 x 1.60 m = 4.00 sqm.
MATERIAL
8126 uPVC extruded (big series) casement metre 8.61 319.8 2753.48
window frame size 67x60 mm i/c 5% wastage
8128 uPVC extruded (big series) casement metre 15.17 426.4 6468.49
window sash/window mullion size 67x
80 mm i/c 5% wastage
Window Sash = 6.24 M + Window Mullion =
8.93 M
Total = 15.17 M
8130 uPVC extruded glazing bead of appropriate metre 27.85 123 3425.55
dimension for big series casement window
sash i/c 5% wastage
Galvanized iron reinforcement for :-
3992 Galvanized iron (1.6 ± 0.2 mm) thick reinforcement metre 21.9 71 1554.90
for big series casement window frame, sash,
mullion, big & small series sliding window frame i/c
5%
wastage
Window Frame = 8.31 M + Window Sash =
5.64 M + Window Mullion = 7.95 M
Total = 21.90 M
7390 EPDM Gasket for uPVC window/door i/c 5% metre 83.45 19 1585.55
3995 wastage 0.00
G.I fasteners 100 x 8 mm each 16 14 224
8758 Stainless steel friction hinges (SS-304 grade) size each 4 345 1380.00
8750 350 x 19 x 1.9 mm for uPVC window
Zinc alloy (white powder coated) casement handle each 2 130 260
for uPVC window
9999 Sundries, plastic packers, plastic caps, L.S. 170 2.00 340.00
SS screws and carriage of material
LABOUR
46 Labour for fabrication of uPVC extruded casement sqm 4 485.00 1940.00
windows including drilling holes, fixing of fittings &
hardwares, hire charges of drill machine and
47 electricity charges etc.
Labour for installation of uPVC extruded casement sqm 4 430 1720
windows including scaffolding
TOTAL 21651.97 W
Add 1 % Water charges on "W" 216.5197
TOTAL 21868.49 X
Add GST (multiplying factor 0.1405) on "X" 3072.52
TOTAL 24941.01 Y
Add 15 % Contractor's profit and overheads on "Y" 3741.15
Total 28682.16 Z
Add Cess @ 1% on "Z" 286.82
Cost of 4.00 sqm 28968.98
Cost of 1.00 sqm 7242.24
Say 7242.20

9.147B Providing and fixing factory made uPVC


white colourcomprising
ventilators fixed glazed windows/
of uPVC multi-
chambered frame and mullion
ever required) extruded profiles duly (where
reinforced with
galvanized mild1.60
steel±section
0.2 mmmade thick from
roll forming
length (shape process
& sizeof required to uPVC
according
profile), , uPVC extruded
beads of appropriate dimension, glazing EPDM
gasket,
for fixingG.I fasteners
frame 100 xwall,
to finished 8 mm size
plastic
packers,
stainless plastic caps and
steel screws etc.necessary
Profile of frame
shall be mitred cut and fusion
welded at all corners, mullion (if required)
shall be also
including fusion
drilling welded
of holes for fixing
hardware's and drainage
fixing frame the gap between of water
frameetc. After
and
adjacent
with weather finished
proofwall shallsealant
silicon be filledover
backer rod of required size and of
approved quality, all complete as per
approved drawing &(Single
Engineer-in-Charge. direction of glass
/ double
Note: panes and silicon sealant shall be
paid separately).
For uPVC frame, sash and mullion
extruded profiles
dimension minus&5%
i.e. in depth tolerance
width in
of profile
shall bedimension
profile acceptable. Variation
in higher sideinshall be
accepted but no extra payment
this account shall be made. on
9.147B.1 Fixed window / ventilator made of (small
series)
47 x 68frame 47 xhaving
mm both 50 mmwall
& mullion
thickness of
1.9 ± 0.2 mm and single glazing
bead of appropriate dimension. (Area upto
0.75 sqm.)
Detail of cost for uPVC fixed window size 1.20 x
0.50 m = 0.60 sqm.

MATERIAL
8121 uPVC extruded (small series) fixed window frame metre 3.57 258.3 922.13
8122 size 47x50mm metre 0.53 282.9 149.94
uPVC extruded (small series) fixed window mullion
8125 size 47x68 mm 0.00
uPVC extruded glazing bead of appropriate metre 3.99 98.4 392.62
dimension for small series fixed window
Sash
Galvanized iron reinforcement for :-
3991 Galvanized iron (1.6 ± 0.2 mm) thick reinforcement metre 4.25 66 280.50
for small series fixed window
frame and mullion i/c 5% wastage
Window Frame = 3.27 M + Window Mullion = 0.98
M
Total = 4.25 M
7390 EPDM Gasket for uPVC window i/c 5% wastage metre 8.38 19 159.22
3995 G.I fasteners 100 x 8 mm each 8 14 112.00
9999 Sundries, plastic packers, plastic caps, L.S. 170 2.00 340.00
SS screws and carriage of material
LABOUR
46 Labour for fabrication of uPVC extruded fixed sqm 0.6 485.00 291.00
windows including drilling holes, fixing of fittings &
hardwares,
hire charges of drill machine and electricity
47 charges etc.
Labour for installation of uPVC extruded fixed sqm 0.6 430 258
windows including scaffolding
TOTAL 2905.41 W
Add 1 % Water charges on "W" 29.0541
TOTAL 2934.46 X
Add GST (multiplying factor 0.1405) on "X" 412.29
TOTAL 3346.75 Y
Add 15 % Contractor's profit and overheads on "Y" 502.01
Total 3848.76 Z
Add Cess @ 1% on "Z" 38.49
Cost of 0.60 sqm 3887.25
Cost of 1.00 sqm 6478.76
Say 6478.80

9.147C Providing and fixing factory made uPVC


white colour
cum fixed casement/
glazed Casement of uPVC
door comprising
multi-chambered
mullion (where ever frame, sash and
required) extruded
profiles duly reinforced with
mm thick galvanized mild steel section 1.60 ± 0.2
made
requiredfrom roll forming
length (shape & process of
size according to
uPVC profile),uPVC extruded
glazing beads of appropriate dimension,
EPDM
powdergasket,
coated)zinc alloy (white
3D hinges and one handle
on each side of panels along
zinc plated mild steel multi point withlocking
having
with keepstransmission
and one side gear,key,cylinder
G.I fasteners
100 x 8 mm
finished wall size
and for fixing frame
necessary to steel
stainless
screws,
shall be etc. Profile
mitred of frame
cut and fusion&welded
sash at all
corners, mullion (if required) shall
be also fusion welded including drilling of
holes
drainagefor fixing
of waterhardware's
etc. Afterand fixing frame
the gap between frame and
finished wall shall be filled with adjacent
weather
proof
of required size and of approved rod
silicon sealent over backer quality, all
complete as per approved drawing
& direction of Engineer-in-Charge. (Single /
double
sealent glass panes
shall be paidand silicon
separately).
Note: For uPVC frame, sash and mullion
extruded
dimensionprofiles minus&5%
i.e. in depth tolerance
width in
of profile
shall
profilebedimension
acceptable. Variation
in higher sideinshall be
accepted
this account butshall
no extra payment on
be made.
9.147C.1 Casement door with 3D hinges made of
(big
67 x series)
110 mm frame
both 67 x 64 wall
having mm thickness
& sash of
2.3
bead ± 0.2 mm and
/ double single
glazing glazing
bead of appropriate
dimension.
sqm). (Area of door upto 2.00
Detail of cost for uPVC casement door size 0.90 x
2.10 m = 1.89 sqm.
MATERIAL
8127 uPVC extruded (big series) casement door frame metre 5.36 360.8 1933.89
8129 size 67x64 mm i/c 5% wastage 0.00
uPVC extruded (big series) casement door sash metre 6.02 516.6 3109.93
8130 size 67x110 mm i/c 5% wastage
uPVC extruded glazing bead of appropriate metre 5.22 123 642.06
dimension for big series casement door
sash i/c 5% wastage
Galvanized iron reinforcement for :-
3992 Galvanized iron (1.6 ± 0.2 mm) thick reinforcement metre 5.14 71 364.94
for big series casement window/door frame, sash,
mullion, i/c 5% wastage
3993 Galvanized iron (1.6 ± 0.2 mm) thick reinforcement metre 5.72 97 554.84
for big series casement door sash i/c 5% wastage
7390 EPDM Gasket for uPVC window/door i/c 5% metre 22.91 19 435.29
3995 wastage
G.I fasteners 100 x 8 mm each 10 14 140
8116 Zinc alloy (white powder coated) 3D Hinges for each 3 451 1353.00
8117 uPVC door 0.00
Zinc alloy (white powder coated) handles with zinc each 1 2296 2296
plated mild steel multi point locking having set
transmission gear, cylinder with keeps and one
9999 side key for uPVC casement door 0.00
Sundries, plastic packers, plastic caps, L.S. 170 2.00 340
SS screws and carriage of material
LABOUR
46 Labour for fabrication of uPVC extruded sqm 1.89 485.00 916.65
casement/fixed windows/and door
including drilling holes, fixing of fittings &
hardwares, hire charges of drill machine and
47 electricity charges etc.
Labour for installation of uPVC extruded casement sqm 1.89 430 812.7
windows and doors including scaffolding
TOTAL 12899.30 W
Add 1 % Water charges on "W" 128.993
TOTAL 13028.29 X
Add GST (multiplying factor 0.1405) on "X" 1830.48
TOTAL 14858.77 Y
Add 15 % Contractor's profit and overheads on "Y" 2228.82
Total 17087.59 Z
Add Cess @ 1% on "Z" 170.88
Cost of 1.89 sqm 17258.47
Cost of 1.00 sqm 9131.47
Say 9131.50

9.147C.2 Casement door with top hung ventilator


with
19 x 3D
1.9 and
mm)S.S. friction
made hinges
of (big (400
series) x
frame
67 x 64 67
mullion mm, sash
x 80 mm67allx having
110 mm &
wall
thickness
glazing beadof 2.3 ±. 0.2 glazing
/ double mm andbeadsingle
of
appropriate dimension.(Area of door
upto 2.50 sqm)
Detail of cost for uPVC casement door size
0.90 x 2.70 m = 2.43 sqm
MATERIAL
8127 uPVC extruded (big series) casement door frame metre 6.3 360.8 2273.04
8129 size 67x64 mm i/c 5% wastage 0.00
uPVC extruded (big series) casement door sash metre 6.01 516.6 3104.77
8128 size 67x110 mm i/c 5% wastage 0.00
uPVC extruded (big series) casement door metre 3.55 426.4 1513.72
sash/mullion size 67x80 mm i/c 5% wastage Door
sash (67 mm x 80 mm) = 2.60 M +
Door mullion (67 mm x 80 mm ) = 0.95 M Total =
8130 3.55 M
uPVC extruded glazing bead of appropriate metre 8.06 123 991.38
dimension for big series casement door sash i/c
5% wastage
Galvanized iron reinforcement for :-
3992 Galvanized iron (1.6 ± 0.2 mm) thick reinforcement metre 9.26 71 657.46
for big series casement door
frame, sash, mullion, i/c 5% wastage
Door Frame = 6.08 M + Ventilator Sash =
2.30 M + Mullion = 0.88 M
Total = 9.26 M
3993 Galvanized iron (1.6 ± 0.2 mm) thick reinforcement metre 5.71 97 553.87
for big series casement door sash i/c 5% wastage
7390 EPDM Gasket for uPVC window/door i/c 5% metre 31.98 19 607.62
3995 wastage
G.I fasteners 100 x 8 mm each 12 14 168
8116 Zinc alloy (white powder coated) 3D Hinges for each 3 451 1353.00
8117 uPVC door 0.00
Zinc alloy (white powder coated) handles with zinc each 1 2296 2296
plated mild steel multi point locking having set
transmission gear, cylinder with keeps and one
8759 side key for uPVC casement door 0.00
Stainless steel friction hinges (SS-304 grade) size each 2 365 730
8750 400 x 19 x 1.9 mm for uPVC window
Zinc alloy (white powder coated) casement handle each 1 130 130
for uPVC window/ door
9999 Sundries, plastic packers, plastic caps, L.S. 170 2.00 340.00
SS screws and carriage of material
LABOUR
637 60 0.00
46 Labour for fabrication of uPVC extruded casement sqm 2.43 485.00 1178.55
doors including drilling holes, fixing of fittings &
hardwares, hire charges of drill machine and
47 electricity charges etc.
Labour for installation of uPVC extruded casement sqm 2.43 430 1044.9
ventilator and doors including scaffolding
TOTAL 16942.31 W
Add 1 % Water charges on "W" 169.4231
TOTAL 17111.73 X
Add GST (multiplying factor 0.1405) on "X" 2404.20
TOTAL 19515.93 Y
Add 15 % Contractor's profit and overheads on "Y" 2927.39
Total 22443.32 Z
Add Cess @ 1% on "Z" 224.43
Cost of 2.43 sqm 22667.75
Cost of 1.00 sqm 9328.29
Say 9328.30

9.147D Providing and fixing factory made uPVC


white1.50
upto colour m in sliding
height glazed window
dimension
comprising
with in-built of uPVC
roller trackmulti-chambered
and sash extruded
frame duly reinforced with 1.60 ±
profiles
0.2 mm thick galvanized mild steel section
made
required from roll forming
length (shapeprocess& sizeofaccording
to uPVC of
dimension profile),appropriate
uPVC extruded glazing
beads and uPVC
EPDM gasket, wool extruded
pile, zincinterlocks,
alloy (white
powder coated) touch locks
hook, zinc alloy body with single nylon with
rollers
40 kg),(weight bearing100
G.I fasteners capacity
x 8 mm tosize
be for
fixing framestainless
necessary to finished wall
steel and etc.
screws
Profile
cut andoffusion
framewelded
& sashatshall be mitred
all corners,
including
hardware's drilling of holes for
and drainage fixing etc. After
of water
fixing frame the
and adjacent gap between
finished wall shall frame
be filled
with weather proof silicon
over backer rod of required size and of sealent
approved
approved quality,
drawingall & complete
direction of asEngineer-
per
in-Charge.
panes, wire (Single
mesh and / double
siliconglass
sealent shall
Note: be paid
For uPVC separately)
frame and sash extruded
profiles
i.e. minus
in depth 5% tolerance
& width of profileinshall
dimension
be
acceptable. Variation in profile
dimension in higher side shall be accepted
but no extra
account shallpayment
be made. on this
9.147D.1 Two track two panels sliding window made
of (small32series)
& sash x 60 mm frame both52having
x 44 mm wall
thickness of 1.9± 0.2 mm
glazing bead of appropriate dimension. and single
(Area
Detail ofofcost
window
for uPVC upto 1.75
sliding sqm)size 1.20 x
window
1.35 m = 1.62 sqm.
MATERIAL
8133 uPVC extruded (small series) 2 track metre 5.36 285 1527.60
sliding window frame size 52x44 mm i/c 5%
8137 wastage 265 0.00
uPVC extruded (small series) 2 track metre 7.9 265 2093.5
sliding window sash size 32x60mm i/c 5%
8140 wastage 325 0.00
uPVC extruded interlock of appropriate metre 2.69 80 215.2
dimension for small series sliding window sash i/c
8131 5% wastage
uPVC extruded glazing bead of appropriate metre 6.92 60 415.2
dimension for small series sliding window
sash i/c 5% wastage
Galvanized iron reinforcement for
3991 Galvanized iron (1.6 ± 0.2 mm) thick reinforcement metre 12.36 66 815.76
for small series 2 track sliding window frame and
sash i/c 5%
wastage
2 Track Sliding (Window Frame = 5.06 M +
Window Sash = 7.30 M)
Total = 12.36 M
7390 EPDM Gasket for uPVC window/door i/c 5% metre 13.84 19 262.96
8773 wastage 0.00
Wool pile/ weather pile strip for uPVC sliding metre 18.48 20 369.6
3995 window i/c 5% wastage
G.I fasteners 100 x 8 mm each 12 14 168
8751 Zinc alloy (white powder coated) touch lock with each 2 105 210.00
hook for uPVC window
8752 Zinc alloy body with single nylon roller each 4 56 224.00
(weight bearing capacity to be 40 Kg) for uPVC
9999 sliding window
Sundries, plastic packers, plastic caps, L.S. 170 2.00 340
SS screws and carriage of material
LABOUR
46 Labour for fabrication of uPVC extruded sliding sqm 1.62 485.00 785.70
windows including drilling holes, fixing of fittings &
hardwares, hire charges of drill machine and
electricity charges etc.
47 Labour for installation of uPVC extruded sliding sqm 1.62 430.00 696.60
windows including scaffolding
TOTAL 8124.12 W
Add 1 % Water charges on "W" 81.2412
TOTAL 8205.36 X
Add GST (multiplying factor 0.1405) on "X" 1152.85
TOTAL 9358.21 Y
Add 15 % Contractor's profit and overheads on "Y" 1403.73
Total 10761.94 Z
639 Add Cess @ 1% on "Z" 107.62
Cost of 1.62 sqm 10869.56
Cost of 1.00 sqm 6709.61
Say 6709.60

9.147D.2 Three track three panels sliding window


with
glazedfly &
proof
one SS no.wire
wiremesh
mesh(Two nos.
panels) made
of (small series) frame 92
sash 32 x 60 mm both having wall x 44 mm &
thickness of 1.9 ± 0.2
bead of appropriate mm and single
dimension (Area of
glazing
window
Detail upto
of cost for1.75
uPVCsqm).
sliding window size 1.20 x
1.35 m = 1.62 sqm.
MATERIAL
8135 uPVC extruded (small series) 3 track metre 5.06 380 1922.80
sliding window frame size 92x44 mm i/c 5%
8137 wastage 0.00
uPVC extruded (small series) 3 track sliding metre 11.84 265 3137.6
8140 window sash size 32x60mm i/c 5% wastage 80 0.00
uPVC extruded interlock of appropriate metre 4.04 80 323.2
dimension for small series sliding window sash i/c
8131 5% wastage
uPVC extruded glazing bead of appropriate metre 10.38 60 622.8
dimension for small series sliding window
sash i/c 5% wastage
Galvanized iron reinforcement for
3991 Galvanized iron (1.6 ± 0.2 mm) thick reinforcement metre 20.46 66 1350.36
for small series sliding
window frame and sash i/c 5% wastage
3 Track Sliding (Window Frame = 9.52 m +
Window Sash = 10.94 m)
Total = 20.46 M
7390 EPDM Gasket for uPVC window i/c 5% wastage metre 20.76 19 394.44
8773 Wool pile/ weather pile strip for uPVC sliding metre 27.72 20 554.40
3995 window i/c 5% wastage
G.I fasteners 100 x 8 mm each 12 14 168
8751 Zinc alloy (white powder coated) touch lock with each 2 105 210.00
hook for uPVC window
8752 Zinc alloy body with single nylon roller each 6 56 336.00
(weight bearing capacity to be 40 Kg) for uPVC
9999 sliding window
Sundries, plastic packers, plastic caps, SS screws L.S. 170 2.00 340
and carriage of material
LABOUR
46 Labour for fabrication of uPVC extruded sliding sqm 1.62 485.00 785.70
windows including drilling holes, fixing of fittings &
hardwares, hire charges of drill machine and
47 electricity charges etc.
Labour for installation of uPVC extruded sliding sqm 1.62 430 696.6
windows including scaffolding
TOTAL 10841.90 W
Add 1 % Water charges on "W" 108.419
TOTAL 10950.32 X
Add GST (multiplying factor 0.1405) on "X" 1538.52
TOTAL 12488.84 Y
Add 15 % Contractor's profit and overheads on "Y" 1873.33
Total 14362.17 Z
Add Cess @ 1% on "Z" 143.62
Cost of 1.62 sqm 14505.79
Cost of 1.00 sqm 8954.19
Say 8954.20

9.147D.3 Two track two panels sliding window made


of (big46series)
sash x 62 mmframe
both67having
x 50 mmwall&
thickness of 2.3
bead / double ± 0.2 mm
glazing beadand single
of appropriate
glazing
dimension . (Area
1.75 sqm upto 2.50ofsqm).
window above
Detail of cost for uPVC sliding window size
1.50 x 1.35 m = 2.03sqm
MATERIAL
8134 uPVC extruded (big series) 2 track sliding metre 5.99 385 2306.15
window frame size 67x50mm i/c 5% wastage
8138 uPVC extruded (big series) 2 track sliding metre 8.36 325 2717.00
window sash size 46x62mm i/c 5% wastage
8141 uPVC extruded interlock of appropriate metre 2.65 90 238.50
dimension for big series sliding window sash i/c
8132 5% wastage
uPVC extruded glazing bead of appropriate metre 7.64 85 649.4
dimension for big series of sliding window
Sash i/c 5% wastage
Galvanized iron reinforcement for :-
3992 Galvanized iron (1.6 ± 0.2 mm) thick reinforcement metre 5.69 71 403.99
for big series sliding window frame (2 track sliding
window frame i/c 5% wastage)
3994 Galvanized iron (1.6 ± 0.2 mm) thick reinforcement metre 7.76 86 667.36
for big series sliding window sash (2 track sliding
7390 window sash i/c 5% wastage) 0.00
EPDM Gasket for uPVC window i/c 5% wastage metre 15.28 19 290.32
8773 Wool pile/ weather pile strip for uPVC sliding metre 19.37 20 387.40
3995 window i/c 5% wastage
G.I fasteners 100 x 8 mm each 14 14 196
8751 Zinc alloy (white powder coated) touch lock with each 2 105 210.00
hook for uPVC window
8752 Zinc alloy body with single nylon roller each 4 56 224.00
(weight bearing capacity to be 40 Kg) for uPVC
9999 sliding window
Sundries, plastic packers, plastic caps, L.S. 170 2.00 340
SS screws and carriage of material
LABOUR
641 0.00

46 Labour for fabrication of uPVC extruded sliding sqm 2.03 485.00 984.55
windows including drilling holes, fixing of fittings &
hardwares, hire charges of drill machine and
47 electricity charges etc.
Labour for installation of uPVC extruded sliding sqm 2.03 430 872.9
windows including scaffolding
TOTAL 10487.57 W
Add 1 % Water charges on "W" 104.8757
TOTAL 10592.45 X
Add GST (multiplying factor 0.1405) on "X" 1488.24
TOTAL 12080.69 Y
Add 15 % Contractor's profit and overheads on "Y" 1812.10
Total 13892.79 Z
Add Cess @ 1% on "Z" 138.93
Cost of 2.03 sqm 14031.72
Cost of 1.00 sqm 6912.18
Say 6912.20

9.147D.4 Three track three panels sliding window


with
nos. fly proof&S.S
glazed onewire
no. mesh (Twopanels)
wire mesh
made
mm & of (big46
sash series) frame
x 62 mm 116
both x 45 wall
having
thickness of 2.3
glazing bead ± 0.2 mm
/ double andbead
glazing single
of
appropriate dimension.
above 1.75 sqm). (Area of window
Detail of cost for uPVC sliding window size 1.80 x
1.35 m = 2.43 sqm.
MATERIAL
8136 uPVC extruded (big series) 3 track sliding metre 6.62 530 3508.60
window frame size 116x45mm i/c 5% wastage
8139 uPVC extruded (big series) 3 track sliding metre 13.49 325 4384.25
window sash size 46x62mm i/c 5% wastage
8141 uPVC extruded interlock of appropriate metre 3.98 90 358.20
dimension for big series sliding window sash i/c
8132 5% wastage
uPVC extruded glazing bead of appropriate metre 11.91 85 1012.35
dimension for big series of sliding window
Sash i/c 5% wastage
Galvanized iron reinforcement for
3992 Galvanized iron (1.6 ± 0.2 mm) thick reinforcement metre 12.64 71 897.44
for big series sliding window frame (3 track sliding
window frame i/c 5% wastage)
3994 Galvanized iron (1.6 ± 0.2 mm) thick reinforcement metre 12.59 86 1082.74
for big series sliding window sash
(3 track sliding window sash i/c 5% wastage)
7390 EPDM Gasket for uPVC window i/c 5% wastage metre 23.81 19 452.39
8773 Wool pile/ weather pile strip for uPVC sliding metre 30.96 20 619.20
3995 window i/c 5% wastage
G.I fasteners 100 x 8 mm each 16 14 224

8751 Zinc alloy (white powder coated) touch lock with each 2 105 210.00
hook for uPVC window
8752 Zinc alloy body with single nylon roller each 6 56 336.00
(weight bearing capacity to be 40 Kg) for uPVC
9999 sliding window
Sundries, plastic packers, plastic caps, L.S. 170 2.00 340
SS screws and carriage of material
LABOUR
46 Labour for fabrication of uPVC extruded sliding sqm 2.43 485.00 1178.55
windows including drilling holes, fixing of fittings &
hardwares, hire charges of drill machine and
47 electricity charges etc.
Labour for installation of uPVC extruded sqm 2.43 430 1044.9
casement/ sliding windows including scaffolding
TOTAL 15648.62 W
Add 1 % Water charges on "W" 156.4862
TOTAL 15805.11 X
Add GST (multiplying factor 0.1405) on "X" 2220.62
TOTAL 18025.73 Y
Add 15 % Contractor's profit and overheads on "Y" 2703.86
Total 20729.59 Z
Add Cess @ 1% on "Z" 207.30
Cost of 2.43 sqm 20936.89
Cost of 1.00 sqm 8616
Say 8616.00

9.147D.5 Three track three panels sliding window


made
mm & of (big46
sash series) frame
x 62 mm 116
both x 45 wall
having
thickness of 2.3
glazing bead ± 0.2 mm
/ double andbead
glazing single
of
appropriate dimension.
above 1.75 sqm) (Area of window

Detail of cost for uPVC sliding window size 1.80 x


1.35 m = 2.43 sqm.

MATERIAL
8136 uPVC extruded (big series) 3 track sliding window metre 6.62 530 3508.60
frame size 116x45mm i/c 5% wastage
8139 uPVC extruded (big series) 3 track sliding metre 11.85 325 3851.25
window sash size 46x62mm i/c 5% wastage
8141 uPVC extruded interlock of appropriate metre 5.3 90 477.00
dimension for big series sliding window sash i/c
8132 5% wastage
uPVC extruded glazing bead of appropriate metre 10.26 85 872.1
dimension for big series of sliding window
Sash i/c 5% wastage
Galvanized iron reinforcement for :-
3992 Galvanized iron (1.6 ± 0.2 mm) thick reinforcement metre 12.64 71 897.44
for big series sliding window frame (3 track sliding
window frame i/c 5% wastage)

3994 Galvanized iron (1.6 ± 0.2 mm) thick reinforcement metre 10.95 86 941.70
for big series sliding window sash (3 track sliding
7390 window sash i/c 5% wastage) 0.00
EPDM Gasket for uPVC window i/c 5% wastage metre 20.52 19 389.88
8773 Wool pile/ weather pile strip for uPVC sliding metre 29 20 580.00
3995 window i/c 5% wastage
G.I fasteners 100 x 8 mm each 16 14 224
8751 Zinc alloy (white powder coated) touch lock with each 2 105 210.00
hook for uPVC window
8752 Zinc alloy body with single nylon roller each 6 56 336.00
(weight bearing capacity to be 40 Kg) for uPVC
9999 sliding window
Sundries, plastic packers, plastic caps, L.S. 170 2.00 340
SS screws and carriage of material
LABOUR
46 Labour for fabrication of uPVC extruded sliding sqm 2.43 485.00 1178.55
windows including drilling holes, fixing of fittings &
hardwares, hire charges of drill machine and
47 electricity charges etc.
Labour for installation of uPVC extruded sliding sqm 2.43 430 1044.9
windows including scaffolding
TOTAL 14851.42 W
Add 1 % Water charges on "W" 148.5142
TOTAL 14999.93 X
Add GST (multiplying factor 0.1405) on "X" 2107.49
TOTAL 17107.42 Y
Add 15 % Contractor's profit and overheads on "Y" 2566.11
Total 19673.53 Z
Add Cess @ 1% on "Z" 196.74
Cost of 2.43 sqm 19870.27
Cost of 1.00 sqm 8177.07
Say 8177.10

9.147E Providing and fixing factory made uPVC


white colour
above 1.50 msliding glazed
in height window
dimension
comprising of uPVC multi-chambered
with in-built roller track and sash extruded
frame duly reinforced with 1.60 ±
profiles
0.2 mm thick galvanized mild steel section
made
required from roll forming
length (shapeprocess
& sizeofaccording
to uPVC of
dimension profile),
uPVCappropriate
extruded glazing
beads, uPVC extruded
uPVC extruded Inline sash interlocks
adaptorand (if
required), EPDM gasket, wool
alloy (white powder coated) handle on one pile, zinc
side of extreme
zinc plated mild panel alongpoint
steel multi with locking
having
zinc alloytransmission
(white powder gearcoated)
with keeps,
touch lock
with hook (if required for
mesh panel), stainless steel (SS 304wire
grade) body with
rollers (weight adjustable
bearing double
capacity to be nylon
120
kg), G.I fasteners 100 x 8 mm
fixing frame to finished wall and necessarysize for
stainless
of frame &steel sashscrews
shall beetc. Profile
mitred cut and
fusion welded at all corners, including
drilling of holes for fixing hardware's and
drainage
frame theofgap water etc. After
between framefixing
and adjacent
finished wall
weather proofshall be filled
silicon sealentwith
over backer
rod of required size and of
quality, all complete as per approved approved
drawing
Charge. & direction
(Single of Engineer-in-
/ double glass panes, wire
mesh and silicon
paid separately). sealent shall be
Note: For uPVC frame and sash extruded
profiles minus
i.e. in depth 5% tolerance
& width of profileinshall
dimension
be
acceptable. Variation in profile
dimension in higher side shall be accepted
but no extra
account shallpayment
be made.on this
9.147E.1 Two track two panels sliding window made
of (big46series)
sash x 62 mmframe 67having
both x 50 mm
wall&
thickness
glazing beadof 2.3 ± 0.2 glazing
/ double mm andbeadsingle
of
appropriate dimension. (Area
above 2.50 sqm upto 4.00 sqm.) of window
Detail of cost for uPVC sliding window size 1.50 x
2.40 m = 3.60 sqm.
MATERIAL
8134 uPVC extruded (big series) 2 track sliding metre 8.19 385 3153.15
window frame size 67x50mm i/c 5% wastage
8138 uPVC extruded (big series) 2 track sliding metre 12.77 325 4150.25
window sash size 46x62mm i/c 5% wastage
8141 uPVC extruded interlock of appropriate metre 4.86 90 437.40
dimension for big series sliding window sash i/c
8132 5% wastage
uPVC extruded glazing bead of appropriate metre 12.04 85 1023.4
dimension for big series of sliding window
Sash i/c 5% wastage
Galvanized iron reinforcement for
3992 Galvanized iron (1.6 ± 0.2 mm) thick reinforcement metre 7.89 71 560.19
for big series sliding window frame (2 track sliding
window frame i/c 5% wastage)

3994 Galvanized iron (1.6 ± 0.2 mm) thick reinforcement metre 12.17 86 1046.62
for big series sliding window sash (2 track sliding
7390 window sash i/c 5% wastage) 0.00
EPDM Gasket for uPVC window i/c 5% wastage metre 24.08 19 457.52
8773 Wool pile/ weather pile strip for uPVC sliding metre 30.4 20 608.00
3995 window i/c 5% wastage
G.I fasteners 100 x 8 mm each 16 14 224
8118 Zinc alloy (white powder coated) handles along each 2 1394 2788.00
with zinc plated mild steel multi point locking set
having transmission gear with keeps for uPVC
8753 sliding window
Stainless Steel (SS - 304) with adjustable double each 4 95 380
nylon roller (weight bearing capacity to be 120 Kg)
9999 for uPVC sliding window
Sundries, plastic packers, plastic caps, SS screws L.S. 170 2.00 340
and carriage of material
LABOUR
46 Labour for fabrication of uPVC extruded sliding sqm 3.6 485.00 1746.00
windows including drilling holes, fixing of fittings &
hardwares, hire charges of drill machine and
electricity charges etc.
47 Labour for installation of uPVC extruded sliding sqm 3.6 430.00 1548.00
windows including scaffolding
TOTAL 18462.53 W
Add 1 % Water charges on "W" 184.6253
TOTAL 18647.16 X
Add GST (multiplying factor 0.1405) on "X" 2619.93
TOTAL 21267.09 Y
Add 15 % Contractor's profit and overheads on "Y" 3190.06
Total 24457.15 Z
Add Cess @ 1% on "Z" 244.57
Cost of 3.60 sqm 24701.72
Cost of 1.00 sqm 6861.59
Say 6861.60

9.147E.2 Two track four panels sliding window made


of (big46series)
sash x 62 mmframe
both67having
x 50 mmwall&
thickness of 2.3
bead / double ± 0.2 mm
glazing beadand single
of appropriate
glazing
dimension. (Area of sqm).
window above
4.00 sqm upto 8.00
Detail of cost for uPVC sliding window size 3.00 x
2.40 m = 7.20 sqm.
MATERIAL
8134 uPVC extruded (big series) 2 track sliding window metre 11.34 385 4365.90
frame size 67x50mm i/c 5% wastage
8138 uPVC extruded (big series) 2 track sliding metre 25.75 325 8368.75
window sash size 46x62mm i/c 5% wastage
8141 uPVC extruded interlock of appropriate metre 9.71 90 873.90
dimension for big series sliding window sash i/c
5% wastage
8142 uPVC extruded inline adaptor of metre 2.4 90 216.00
appropriate dimension for big series sliding
8132 window sash i/c 5% wastage
uPVC extruded glazing bead of appropriate metre 24.31 85 2066.35
dimension for big series of sliding window
Sash i/c 5% wastage
Galvanized iron reinforcement for
3992 Galvanized iron (1.6 ± 0.2 mm) thick reinforcement metre 11.04 71 783.84
for big series sliding window frame (2 track sliding
window frame i/c 5% wastage)
3994 Galvanized iron (1.6 ± 0.2 mm) thick reinforcement metre 24.55 86 2111.30
for big series sliding window sash (2 track sliding
7390 window sash i/c 5% wastage) 0.00
EPDM Gasket for uPVC window i/c 5% wastage metre 48.62 19 923.78
8773 Wool pile/ weather pile strip for uPVC sliding metre 61.21 20 1224.20
3995 window i/c 5% wastage
G.I fasteners 100 x 8 mm each 24 14 336
8118 Zinc alloy (white powder coated) handles along each 2 1394 2788.00
with zinc plated mild steel multi point locking set
having transmission gear with keeps for uPVC
8753 sliding window
Stainless Steel (SS - 304) with adjustable double each 8 95 760
nylon roller (weight bearing capacity to be 120 Kg)
8754 for uPVC sliding window 0.00
Zinc alloy (white powder coated) cresent lock for each 2 115 230
uPVC sliding window
9999 Sundries, plastic packers, plastic caps, L.S. 170 2.00 340.00
SS screws and carriage of material
LABOUR
46 Labour for fabrication of uPVC extruded sliding sqm 7.2 485.00 3492.00
windows including drilling holes, fixing of fittings &
hardwares, hire charges of drill machine and
electricity charges etc.
47 Labour for installation of uPVC extruded sliding sqm 7.2 430.00 3096.00
windows including scaffolding
TOTAL 31976.02 W
Add 1 % Water charges on "W" 319.7602
TOTAL 32295.78 X
Add GST (multiplying factor 0.1405) on "X" 4537.56
TOTAL 36833.34 Y
Add 15 % Contractor's profit and overheads on "Y" 5525.00
Total 42358.34 Z
Add Cess @ 1% on "Z" 423.58
Cost of 7.20 sqm 42781.92
Cost of 1.00 sqm 5941.93
Say 5941.90

9.147F Providing and fixing factory made uPVC


white colourofsliding
comprising uPVCglazed door
multi-chambered
frame withprofiles
extruded in-builtduly
roller track andwith
reinforced sash1.60
± 0.2 mm thick galvanized mild
steel section made from roll forming
process
accordingoftorequired length (shape & size
uPVC profile),appropriate
dimension
beads, uPVC uPVC extruded
extruded glazing
interlock and uPVC
extruded Inline sash adaptor (if
required), EPDM gasket, wool pile, zinc
alloy (white
with key on powder
one sidecoated)
of extremehandle
panels
along with zinc plated mild steel multi
point locking having transmission gear with
keeps,
coated)zinc alloylock
cresent (white powder stainless
(if required),
steel (SS 304 grade) body with
adjustable double nylon rollers (weight
bearing
fasteners capacity
100 x 8tomm be size
120 for
kg),fixing
G.I frame
to finishedsteel
stainless wallscrews
and necessary
etc. Profile of frame
& sash shall be mitred
fusion welded at all corners, cut and including
drilling
and of holes
drainage offor fixing
water etc.hardware's
After fixing
frame thefinished
adjacent gap between frame
wall shall be and
filled with
weather proof silicon sealent
backer rod of required size and of over
approved
approved quality,
drawingall & complete
direction of asEngineer-
per
inCharge.
panes, wire(Single
mesh /and double glass
silicon sealent shall
Note: be paid separately).
For uPVC frame and sash extruded
profiles minus
i.e. in depth 5% tolerance
& width of profileinshall
dimension
be
acceptable. Variation in profile
dimension in higher side shall be accepted
but no extra
account shallpayment
be made. on this
9.147F.1 Two track two panels sliding door made of
(big
sashseries)
46 x 82frame
mm both67 x having
50 mm wall &
thickness of 2.3
bead / double ± 0.2 mm
glazing beadand single
of appropriate
glazing
dimension. (Area of door above 2.00
sqm upto 5.00 sqm)
Detail of cost for sliding door size 2.00 x 2.10 m =
4.20 sqm.

MATERIAL
8134 uPVC extruded (big series) 2 track sliding door metre 8.61 385 3314.85
8143 frame size 67x50mm i/c 5% wastage
uPVC extruded 2 track sliding door sash (big metre 12.6 350 4410
8141 series) size 46x82mm i/c 5% wastage
uPVC extruded interlock of appropriate metre 4.23 90 380.7
dimension for big series sliding door sash i/c 5%
8132 wastage
uPVC extruded glazing bead of appropriate metre 11.54 85 980.9
dimension for big series of sliding door
Sash i/c 5% wastage
Galvanized iron reinforcement for
3992 Galvanized iron (1.6 ± 0.2 mm) thick reinforcement metre 8.31 71 590.01
for big series sliding door frame (2 track sliding
3994 door frame i/c 5% wastage) metre 12 86 1032.00
Galvanized iron (1.6 ± 0.2 mm) thick reinforcement
for big series sliding door sash (2 track sliding door
7390 sash i/c 5% wastage) 0.00
EPDM Gasket for uPVC door i/c 5% wastage metre 23.08 19 438.52

8773 Wool pile/ weather pile strip for uPVC sliding door metre 29.43 20 588.60
3995 i/c 5% wastage
G.I fasteners 100 x 8 mm each 18 14 252
8119 Zinc alloy (white powder coated) handles with key each 2 1150 2300.00
along with zinc plated mild steel multi point locking set
having transmission gear with keeps for uPVC
8753 sliding door
Stainless Steel (SS - 304) with adjustable double each 4 95 380
nylon roller (weight bearing capacity to be 120 Kg)
9999 for uPVC sliding door 0.00
Sundries, plastic packers, plastic caps, L.S. 170 2.00 340
SS screws and carriage of material
LABOUR
46 Labour for fabrication of uPVC extruded sliding sqm 4.2 485.00 2037.00
doors including drilling holes, fixing of fittings &
hardwares, hire charges of drill machine and
47 electricity charges etc.
Labour for installation of uPVC extruded sliding sqm 4.2 430 1806
doors including scaffolding
TOTAL 18850.58 W
Add 1 % Water charges on "W" 188.5058
TOTAL 19039.09 X
Add GST (multiplying factor 0.1405) on "X" 2674.99
TOTAL 21714.08 Y
Add 15 % Contractor's profit and overheads on "Y" 3257.11
Total 24971.19 Z
Add Cess @ 1% on "Z" 249.71
Cost of 4.20 sqm 25220.90
Cost of 1.00 sqm 6004.98
Say 6005.00

9.147F.2 Two track four panels sliding door made of


(big
sashseries)
46 x 82frame 67 x having
mm both 50 mm wall
&
thickness of 2.3
bead / double ± 0.2 mm
glazing beadand single
of appropriate
glazing
dimension. (Areasqm).
of door above 8.00
sqm upto 10.00

Detail of cost for uPVC sliding door size 4.00 x 2.10


m = 8.40 sqm.

MATERIAL
8134 uPVC extruded (big series) 2 track sliding door metre 12.81 385 4931.85
8143 frame size 67x50mm i/c 5% wastage
uPVC extruded 2 track sliding door sash (big metre 25.42 350 8897
8141 series) size 46x82mm i/c 5% wastage
uPVC extruded interlock of appropriate metre 8.45 90 760.5
dimension for big series sliding door sash i/c 5%
8142 wastage
uPVC extruded inline adaptor of metre 2.1 90 189
appropriate dimension for big series sliding door
sash

8132 uPVC extruded glazing bead of appropriate metre 23.3 85 1980.50


dimension for big series of sliding door Sash
3992 Galvanized iron reinforcement for :- metre 12.51 71 888.21
Galvanized iron (1.6 ± 0.2 mm) thick reinforcement
for big series sliding door frame (2 track sliding
3994 door frame i/c 5% wastage) metre 24.22 86 2082.92
Galvanized iron (1.6 ± 0.2 mm) thick reinforcement
for big series sliding door sash (2 track sliding door
7390 sash i/c 5% wastage) 0.00
EPDM Gasket for uPVC door i/c 5% wastage metre 46.6 19 885.4
8773 Wool pile/ weather pile strip for uPVC sliding door metre 59.29 20 1185.80
3995 i/c 5% wastage
G.I fasteners 100 x 8 mm each 26 14 364
8119 Zinc alloy (white powder coated) handles with key each 2 1150 2300.00
along with zinc plated mild steel multi point locking set
having transmission gear with keeps for uPVC
8753 sliding door
Stainless Steel (SS - 304) with adjustable double each 8 95 760
nylon roller (weight bearing capacity to be 120 Kg)
8754 for uPVC sliding door 0.00
Zinc alloy (white powder coated) cresent lock for each 2 115 230
uPVC sliding door
9999 Sundries, plastic packers, plastic caps, SS screws L.S. 170 2.00 340.00
and carriage of material
LABOUR
46 Labour for fabrication of uPVC extruded sliding sqm 8.4 485.00 4074.00
doors including drilling holes, fixing of fittings &
hardwares, hire charges of drill machine and
47 electricity charges etc.
Labour for installation of uPVC extruded sliding sqm 8.4 430 3612
doors including scaffolding
TOTAL 33481.18 W
Add 1 % Water charges on "W" 334.8118
TOTAL 33815.99 X
Add GST (multiplying factor 0.1405) on "X" 4751.15
TOTAL 38567.14 Y
Add 15 % Contractor's profit and overheads on "Y" 5785.07
Total 44352.21 Z
Add Cess @ 1% on "Z" 443.52
Cost of 8.40 sqm 44795.73
Cost of 1.00 sqm 5332.83
Say 5332.80

9.147F.3 Three track three panels sliding door made


of (big46series)
sash x 82 mm frame
both116 x 45 mm
having wall &
thickness of 2.3 ± 0.2 mm and single
glazing
bead/ double glazing bead of appropriate
dimension. (Area
Detail of cost for ofsliding
uPVC door door
above
size5.00
3.00 xsqm)
2.10
m = 6.30 sqm.
MATERIAL
8136 uPVC extruded (big series) 3 track sliding metre 10.71 530 5676.30
door frame size 116x45mm i/c 5% wastage
8143 uPVC extruded 3 track sliding door sash (big metre 19.09 350 6681.50
8141 series) size 46x82mm i/c 5% wastage
uPVC extruded interlock of appropriate metre 8.45 90 760.5
dimension for big series sliding door sash i/c 5%
8132 wastage 0.00
uPVC extruded glazing bead of appropriate metre 17.51 85 1488.35
dimension for big series of sliding door
i/c 5% wastage
Galvanized iron reinforcement for :-
3992 Galvanized iron (1.6 ± 0.2 mm) thick reinforcement metre 20.82 71 1478.22
for big series sliding door frams (3 track sliding
3994 door frame i/c 5% wastage) metre 18.19 86 1564.34
Galvanized iron (1.6 ± 0.2 mm) thick reinforcement
for big series sliding door sash
(3 track sliding door sash i/c 5% wastage)
7390 EPDM Gasket for uPVC door i/c 5% wastage metre 35.01 19 665.19
8773 Wool pile/ weather pile strip for uPVC sliding door metre 46.63 20 932.60
3995 i/c 5% wastage
G.I fasteners 100 x 8 mm each 24 14 336
8119 Zinc alloy (white powder coated) handles with key each 2 1150 2300.00
along with zinc plated mild steel multi point locking set
having transmission gear with keeps for uPVC
8753 sliding door
Stainless Steel (SS - 304) with adjustable double each 6 95 570
nylon roller (weight bearing capacity to be 120 Kg)
9999 for uPVC sliding door 0.00
Sundries, plastic packers, plastic caps, L.S. 170 2.00 340
SS screws and carriage of material
LABOUR
46 Labour for fabrication of uPVC extruded sliding sqm 6.3 485.00 3055.50
doors including drilling holes, fixing of fittings &
hardwares, hire charges of drill machine and
47 electricity charges etc.
Labour for installation of uPVC extruded sliding sqm 6.3 430 2709
doors including scaffolding
TOTAL 28557.50 W
Add 1 % Water charges on "W" 285.575
TOTAL 28843.07 X
Add GST (multiplying factor 0.1405) on "X" 4052.45
TOTAL 32895.52 Y
Add 15 % Contractor's profit and overheads on "Y" 4934.33
Total 37829.85 Z
Add Cess @ 1% on "Z" 378.30
Cost of 6.30 sqm 38208.16
Cost of 1.00 sqm 6064.79
Say 6064.80

9.147F.4 Three track three panels sliding door with


fly proof&S.S
glazed onewire meshmesh
no. wire (Twopanels)
nos. made
of (big46series)frame
sash x 82 mm both 116having
x 45 mm
wall&
thickness
glazing of 2.3
bead ± 0.2 mm
/ double andbead
glazing singleof
appropriate dimension.
above 2.00 sqm upto 5.00 sqm)(Area of door
Detail of cost for uPVC sliding door size
2.00 x 2.10 m = 4.20 sqm
MATERIAL
8136 uPVC extruded (big series) 3 track sliding door metre 8.61 530 4563.30
8143 frame size 116x45mm i/c 5% wastage 0.00
uPVC extruded 3 track sliding door sash (big metre 18.9 350 6615
8141 series) size 46x82mm i/c 5% wastage
uPVC extruded interlock of appropriate metre 6.34 90 570.6
dimension for big series sliding door sash i/c 5%
8132 wastage 0.00
uPVC extruded glazing bead of appropriate metre 17.82 85 1514.7
dimension for big series of sliding door
Sash i/c 5% wastage
Galvanized iron reinforcement for :-
3992 Galvanized iron (1.6 ± 0.2 mm) thick reinforcement metre 8.31 71 590.01
for big series sliding door frame (3 track sliding
3994 door frame i/c 5% wastage) metre 18 86 1548.00
Galvanized iron (1.6 ± 0.2 mm) thick reinforcement
for big series sliding door sash
(3 track sliding door sash i/c 5% wastage)
7390 EPDM Gasket for uPVC door i/c 5% wastage metre 36.64 19 696.16
8773 Wool pile/ weather pile strip for uPVC sliding door metre 44.14 20 882.80
3995 i/c 5% wastage
G.I fasteners 100 x 8 mm each 18 14 252
8119 Zinc alloy (white powder coated) handles with key each 2 1150 2300.00
along with zinc plated mild steel multi point locking set
having transmission gear with keeps for uPVC
8749 sliding door 120 0.00
Zinc alloy (white powder coated) touch lock with each 1 120 120
hook for wire mesh shutter
8753 Stainless Steel (SS - 304) with adjustable double each 6 95 570.00
nylon roller (weight bearing capacity to be 120 Kg)
9999 for uPVC sliding door 0.00
Sundries, plastic packers, plastic caps, SS screws L.S. 170 2.00 340
and carriage of material
LABOUR
46 Labour for fabrication of uPVC extruded sliding sqm 4.2 485.00 2037.00
doors including drilling holes, fixing of fittings &
hardwares, hire charges of drill machine and
47 electricity charges etc.
Labour for installation of uPVC extruded sliding sqm 4.2 430 1806
doors including scaffolding
TOTAL 24405.57 W
Add 1 % Water charges on "W" 244.0557
TOTAL 24649.63 X
Add GST (multiplying factor 0.1405) on "X" 3463.27
TOTAL 28112.90 Y
Add 15 % Contractor's profit and overheads on "Y" 4216.93
Total 32329.83 Z
Add Cess @ 1% on "Z" 323.30
Cost of 4.20 sqm 32653.13
Cost of 1.00 sqm 7774.55
Say 7774.60

9.148 Providing and fixing stainless steel (SS-


304hung
top grade) friction
uPVC hinges of
windows, to approved
the side/
quality, with necessary stainless steel
screws etc. as per direction of Engineer-in-
9.148.1 charge.
200 x 19 x 1.9 mm
Details of cost for 10 Nos
MATERIAL
8755 Stainless steel friction hinge of size each 10 205 2050.00
200 mm x 19 x 1.9 mm for uPVC windows
8647 Stainless steal screws 30mm x4mm. 100 0.4 32 12.80
9977 Nos
Carriage of materials L.S. 2.73 2 5.46
LABOUR
15 Carpenter 2nd class day 0.14 403.67 56.51
17 Beldar day 0.14 350.00 49.00
TOTAL 2173.77 W
Add 1 % Water charges on "W" 21.7377
TOTAL 2195.51 X
Add GST (multiplying factor 0.1405) on "X" 308.47
TOTAL 2503.98 Y
Add 15 % Contractor's profit and overheads on "Y" 375.60
Total 2879.58 Z
Add Cess @ 1% on "Z" 28.80
Cost of 10 Nos 2908.38
Cost of 1 No 290.84
Say 290.80

9.148.2 250 x 19 x 1.9 mm


Details of cost for 10 Nos
MATERIAL
8756 Stainless steel friction hinge of size each 10 230 2300.00
250 mm x 19 x 1.9 mm for uPVC windows

8647 Stainless steal screws 30mm x4mm. 100 0.4 32 12.80


9977 Nos
Carriage of materials L.S. 2.73 2 5.46
LABOUR
15 Carpenter 2nd class day 0.14 403.67 56.51
17 Beldar day 0.14 350.00 49.00
TOTAL 2423.77 W
Add 1 % Water charges on "W" 24.2377
TOTAL 2448.01 X
Add GST (multiplying factor 0.1405) on "X" 343.95
TOTAL 2791.96 Y
Add 15 % Contractor's profit and overheads on "Y" 418.79
Total 3210.75 Z
Add Cess @ 1% on "Z" 32.11
Cost of 10 Nos 3242.86
Cost of 1 No 324.29
Say 324.30
9.148.3 300 x 19 x 1.9 mm
Details of cost for 10 Nos
MATERIAL
8757 Stainless steel friction hinge of size each 10 245 2450.00
300 mm x 19 x 1.9 mm for uPVC windows
8647 Stainless steal screws 30mm x4mm. 100 0.4 32 12.80
9977 Nos
Carriage of materials L.S. 2.73 2 5.46
LABOUR
15 Carpenter 2nd class day 0.14 403.67 56.51
17 Beldar day 0.14 350.00 49.00
TOTAL 2573.77 W
Add 1 % Water charges on "W" 25.7377
TOTAL 2599.51 X
Add GST (multiplying factor 0.1405) on "X" 365.23
TOTAL 2964.74 Y
Add 15 % Contractor's profit and overheads on "Y" 444.71
Total 3409.45 Z
Add Cess @ 1% on "Z" 34.09
Cost of 10 Nos 3443.54
Cost of 1 No 344.35
Say 344.40

9.148.4 350 x 19 x 1.9 mm


Details of cost for 10 Nos
MATERIAL
8758 Stainless steel friction hinge of size each 10 345 3450.00
350 mm x 19 x 1.9 mm for uPVC windows
8647 Stainless steal screws 30mm x4mm. 100 0.4 32 12.80
9977 Nos
Carriage of materials L.S. 2.73 2 5.46
LABOUR
15 Carpenter 2nd class day 0.14 403.67 56.51
17 Beldar day 0.14 350.00 49.00
TOTAL 3573.77 W
Add 1 % Water charges on "W" 35.7377
TOTAL 3609.51 X
Add GST (multiplying factor 0.1405) on "X" 507.14
TOTAL 4116.65 Y
Add 15 % Contractor's profit and overheads on "Y" 617.50
Total 4734.15 Z
Add Cess @ 1% on "Z" 47.34
Cost of 10 Nos 4781.49
Cost of 1 No 478.15
Say 478.20

9.148.5 400 x 19 x 1.9 mm


Details of cost for 10 Nos
MATERIAL
8759 Stainless steel friction hinge of size each 10 365 3650.00
400 mm x 19 x 1.9 mm for uPVC windows
8647 Stainless steal screws 30mm x4mm. 100 0.4 32 12.80
9977 Nos
Carriage of materials L.S. 2.73 2 5.46
LABOUR
15 Carpenter 2nd class day 0.14 403.67 56.51
17 Beldar day 0.14 350.00 49.00
TOTAL 3773.77 W
Add 1 % Water charges on "W" 37.7377
TOTAL 3811.51 X
Add GST (multiplying factor 0.1405) on "X" 535.52
TOTAL 4347.03 Y
Add 15 % Contractor's profit and overheads on "Y" 652.05
Total 4999.08 Z
Add Cess @ 1% on "Z" 49.99
Cost of 10 Nos 5049.07
Cost of 1 No 504.91
Say 504.90

9.149 Providing and fixing casement handle


made offor
coated) zinc alloyed
uPVC (white powder
casement window with
necessary screws etc. complete.
Details of cost for 10 Nos
MATERIAL
8750 Zinc alloy (white powder coated) casement handle each 10 130 1300.00
for uPVC windows
9977 Carriage of materials L.S. 4.42 2 8.84
9999 Sundries(Screws) L.S. 3 2.00 6.00
LABOUR
41 Carpenter (average) day 0.125 403.67 50.46
TOTAL 1365.30 W
Add 1 % Water charges on "W" 13.653
TOTAL 1378.95 X
Add GST (multiplying factor 0.1405) on "X" 193.74
TOTAL 1572.69 Y
Add 15 % Contractor's profit and overheads on "Y" 235.90
Total 1808.59 Z
Add Cess @ 1% on "Z" 18.09
Cost of 10 Nos 1826.68
Cost of 1 No 182.67
Say 182.70

9.15 Providing and fixing zinc alloyed (white


powder coated)with
sliding window touch lock for uPVC
necessary screws etc.
complete.
Details of cost for 10 Nos
MATERIAL
8751 Zinc alloy (white powder coated) Touch Lock for each 10 105 1050.00
uPVC windows
9977 Carriage of materials L.S. 4.42 2 8.84
9999 Sundries(Screws) L.S. 3 2.00 6.00
LABOUR
41 Carpenter (average) day 0.125 403.67 50.46
TOTAL 1115.30 W
Add 1 % Water charges on "W" 11.153
TOTAL 1126.45 X
Add GST (multiplying factor 0.1405) on "X" 158.27
TOTAL 1284.72 Y
Add 15 % Contractor's profit and overheads on "Y" 192.71
Total 1477.43 Z
Add Cess @ 1% on "Z" 14.77
Cost of 10 Nos 1492.20
Cost of 1 No 149.22
Say 149.20

9.151 Providing and fixing steel roller for uPVC


sliding
screwswindow with necessary
etc. complete.
Details of cost for 10 Nos
MATERIAL
8752 Zinc alloy rollers for uPVC windows each 10 56 560.00
9977 Carriage of materials L.S. 4.42 2 8.84
9999 Sundries(Screws) L.S. 3 2.00 6.00
LABOUR
41 Carpenter (average) day 0.125 403.67 50.46
TOTAL 625.30 W
Add 1 % Water charges on "W" 6.253
TOTAL 631.55 X
Add GST (multiplying factor 0.1405) on "X" 88.73
TOTAL 720.28 Y
Add 15 % Contractor's profit and overheads on "Y" 108.04
Total 828.32 Z
Add Cess @ 1% on "Z" 8.28
Cost of 10 Nos 836.60
Cost of 1 No 83.66
Say 83.70

9.152 Providing and fixing steel roller for uPVC


sliding door with necessary screws
etc. complete.
Details of cost for 10 Nos
MATERIAL
8753 Zinc alloy rollers for uPVC door each 10 95 950.00
9977 Carriage of materials L.S. 4.42 2 8.84
9999 Sundries(Screws) L.S. 3 2.00 6.00
LABOUR
41 Carpenter (average) day 0.125 403.67 50.46
TOTAL 1015.30 W
Add 1 % Water charges on "W" 10.153
1025.45 X
TOTAL 144.08
Add GST (multiplying factor 0.1405) on "X" 1169.53 Y
TOTAL 175.43
Add 15 % Contractor's profit and overheads on "Y" 1344.96 Z
Total 13.45
Add Cess @ 1% on "Z" 1358.41
Cost of 10 Nos 135.84
Cost of 1 No 135.80
Say

9.153 Providing and fixing steel (white power


coated)
window/crescent
door withlock for uPVC
necessary slidingetc.
screws
complete.
Details of cost for 10 Nos
MATERIAL
8754 Zinc alloy (white powder coated) casement lock for each 10 115 1150.00
uPVC windows
9977 Carriage of materials L.S. 4.42 2 8.84
9999 Sundries(Screws) L.S. 3 2.00 6.00
LABOUR
41 Carpenter (average) day 0.125 403.67 50.46
TOTAL 1215.30 W
Add 1 % Water charges on "W" 12.153
TOTAL 1227.45 X
Add GST (multiplying factor 0.1405) on "X" 172.46
TOTAL 1399.91 Y
Add 15 % Contractor's profit and overheads on "Y" 209.99
Total 1609.90 Z
Add Cess @ 1% on "Z" 16.10
Cost of 10 Nos 1626.00
Cost of 1 No 162.6
Say 162.60

9.154 Providing and fixing frame work for


partitions/ wall lining etc. made of
50x50x1.6 mm hollow MS tube, placed
along the walls, ceiling and floor in a
grid pattern with spacing @ 60 cm centre
to centre both ways (vertically &
horizontally) or at required spacing near
opening, with necessary welding at
junctions and fixing the frame to wall/
ceiling/ floors with steel dash fasteners
of 8 mm dia, 75 mm long bolt, including
making provision for opening for
doors, windows, electrical conduits, switch
boards etc., including providing
with two coats of approved steel primer
etc. complete, all as per direction of
Engineer-in-charge.

Details of cost for 2.4x2.4 m panel=5.76m² or 58.35


Kg
MATERIAL
M.S.Pipe section @ 10.13 kg/sqm=
58.35 Kg+
Add 5% wastage = 2.92 Kg
Total = 61.27 Kg
4009 Mild steel tubes hot finished welded type kilo 61.27 57 3492.39
8776 gram 0.00
Stainless steel dash fastener of 8 mm dia and 75 each 20 15 300
mm long bolt
Steel primer
5 x 2 x 2.40 x 0.05 x 4 = 4.80 sqm
13.50.3 Rate as per Item No.13.50.3 of sqm 4.8 33.3 159.84
SH:FINISHING
LABOUR
19 Fitter (grade 1) day 0.4 505.17 202.07
13 Blacksmith 2nd class day 0.53 403.67 213.95
17 Beldar day 1.23 350.00 430.50
10 Bandhani day 0.06 350.00 21.00
9999 Sundries L.S. 33.56 2.00 67.12
TOTAL 4886.87 W
Add 1 % Water charges on "W-A" 4727.03 47.2703
TOTAL X
Add GST (multiplying factor 0.1405) on "X-A" 4774.30 670.79
TOTAL Y
Add 15 % Contractor's profit and overheads on "Y- 5445.09 816.76
A"
Total Z
Add Cess @ 1% on "Z-A" 6261.85 62.62
Cost of 58.35 kg 6484.31
Cost of 1 kg 111.13
Say 111.10

Providing and fixing panelling or paneling


and glazing
Details in panelled
of cost for 0.66 sqm or panelled and
glazed shutters for doors, windows and
Detail of cost for a door with 2/3rd paneling. 200 x
clerestory windows
108 cm = 2.16 sqm ( area of opening for
Pannel area 4x45.1x36.55cm = 0.66 sqm
MATERIAL
Both side laminated 12mm thick
MDF Board 4x47.2x38.65 cm = 0.73 sqm
Adding 10% wastage = 0.07 sqm
Total= 0.80 sqm
2484 Pre-laminated with decorative lamination on both sqm 0.8 460 368.00
side exterior Grade - I MDF Board 12 mm thick
9999 confirming to IS:14587 0.00
Sundries (Carriage of MDF board) L.S. 1.82 2.00 3.64
LABOUR
14 Carpenter 1 st class day 0.57 505.17 287.95
9999 Sundries L.S. 4.42 2.00 8.84
TOTAL 668.43 W
Add 1 % Water charges on "W" 6.6843
TOTAL 675.11 X
Add GST (multiplying factor 0.1405) on "X" 94.85
TOTAL 769.96 Y
Add 15 % Contractor's profit and overheads on "Y" 115.49
Total 885.45 Z
Add Cess @ 1% on "Z" 8.85
Cost of 0.66 sqm. 894.30
Cost of 1 sqm. 1355.01
Say 1355.00

9.156 Providing and fixing Pre -laminated


medium
(Grade-I)density fibre board
IS:14587:1998 exterior
marked, to grade
frame,
backing or studding with screws etc.
complete ( Frames, backing or studding to
9.156.1 be paid separately).
Pre-laminated with decorative lamination
on both side exterior Grade - I to
Board 12 mm thick confirming MDFIS:14587
Details of cost for 7.00 sqm
Detail of cost for 350x200 cm = 7sqm
MATERIAL
12 mm thick both side laminated board
= 7.00 sqm
Add for wastage @5% = 0.35 sqm
Total= 7.35 sqm
2484 Pre-laminated with decorative lamination on both sqm 7.35 460 3381.00
side exterior Grade - I MDF Board 12 mm thick
9999 confirming to IS:14587 0.00
Sundries (Carriage of MDF board) L.S. 13.52 2.00 27.04
9999 Sundries and screws L.S. 26.91 2.00 53.82
LABOUR
15 Carpenter 2nd class day 0.9 403.67 363.30

17 Beldar day 1 350.00 350.00


TOTAL 4175.16 W
Add 1 % Water charges on "W" 41.7516
TOTAL 4216.91 X
Add GST (multiplying factor 0.1405) on "X" 592.48
TOTAL 4809.39 Y
Add 15 % Contractor's profit and overheads on "Y" 721.41
Total 5530.80 Z
Add Cess @ 1% on "Z" 55.31
Cost of 7.00 sqm. 5586.11
Cost of 1 sqm. 798.02
Say 798.00
9.156.2 Pre-laminated with decorative lamination
on both18side
Board mmexterior Grade - I to
thick confirming MDFIS:14587
Detail of cost for 350x200 cm = 7 sqm
MATERIAL
18 mm thick both side laminated board
= 7.00 sqm
Add for wastage @5% = 0.35 sqm
Total= 7.35 sqm
2485 Pre-laminated with decorative lamination on both sqm 7.35 597 4387.95
side exterior Grade - I MDF Board 18 mm thick
9999 confirming to IS:14587 0.00
Sundries (Carriage of MDF board) L.S. 19.76 2.00 39.52
9999 Sundries and screws L.S. 26.91 2.00 53.82
LABOUR
15 Carpenter 2nd class day 0.9 403.67 363.30
17 Beldar day 1 350.00 350.00
TOTAL 5194.59 W
Add 1 % Water charges on "W" 51.9459
TOTAL 5246.54 X
Add GST (multiplying factor 0.1405) on "X" 737.14
TOTAL 5983.68 Y
Add 15 % Contractor's profit and overheads on "Y" 897.55
Total 6881.23 Z
Add Cess @ 1% on "Z" 68.81
Cost of 7.00 sqm. 6950.04
Cost of 1 sqm. 992.86
Say 992.90

9.157 Providing and fixing Pre-laminated medium


density
marked,fibrewithboard
one sideIS: decorative
14587:1998
lamination other grade)
Grade-I(exterior side balancing
in shelves lamination
with
screws and fittings wherever
edges to be sealed with PVC edge required,
bending tape 2.00
brand (fittings to bemm thick
paid of approved
separately).
9.157.1 Pre-laminated with decorative lamination
one side and
lamination other Grade
exterior side balancing
- I MDF Board
18 mm thick confirming
Details of cost for 0.60 sqm. to IS:14587
Detail of cost for 4 Nos. 75x20 cm shelves
= 0.60 sqm
MATERIAL
18 mm Thick MDF Board out side laminated =
0.60 sqm
Add wastage @ 5% = 0.03 sqm
Total= 0.63 sqm
2488 Pre-laminated with decorative lamination one side sqm 0.63 565 355.95
and other side balancing lamination exterior Grade
- I MDF Board
18 mm thick confirming to IS:14587
PVC edge bending tape 2.00 mm thick
4X0.75 =3.00 metre
2489 PVC edge bending tape 2.00 mm thick metre 3 20 60.00
9999 Sundries (Carriage of MDF board) L.S. 0.91 2.00 1.82
LABOUR
15 Carpenter 2nd class day 0.11 403.67 44.40
17 Beldar day 0.06 350.00 21.00
9999 Sundries and screws L.S. 7.8 2.00 15.60
TOTAL 498.77 W
Add 1 % Water charges on "W" 4.9877
TOTAL 503.76 X
Add GST (multiplying factor 0.1405) on "X" 70.78
TOTAL 574.54 Y
Add 15 % Contractor's profit and overheads on "Y" 86.18
Total 660.72 Z
Add Cess @ 1% on "Z" 6.61
Cost of 0.60 sqm. 667.33
Cost of 1 sqm. 1112.21
Say 1112.20

9.157.2 Pre-laminated with decorative lamination


one side and
lamination other Grade
exterior side balancing
- I MDF Board
25 mmofthick
Details confirming
cost for to IS:14587
0.60 sqm. Detail of cost for 4 Nos.
75x20 cm
shelves = 0.60 sqm
MATERIAL
25 mm Thick MDF Board outside laminated =
0.60 sqm
Add wastage @ 5% = 0.03 sqm
Total= 0.63 sqm
2486 Pre-laminated with decorative lamination one side sqm 0.63 860 541.80
and other side balancing lamination exterior Grade
- I MDF Board 25 mm thick confirming to IS:14587
PVC edge bending tape 2.00 mm thick 4X 0.75
2489 =3.00 metre 0.00
PVC edge bending tape 2.00 mm thick metre 3 20 60
9999 Sundries (Carriage of MDF board) L.S. 1.82 2.00 3.64
LABOUR
15 Carpenter 2nd class day 0.11 403.67 44.40
17 Beldar day 0.06 350.00 21.00
9999 Sundries and screws L.S. 7.8 2.00 15.60
TOTAL 686.44 W
Add 1 % Water charges on "W" 6.8644
TOTAL 693.30 X
Add GST (multiplying factor 0.1405) on "X" 97.41
TOTAL 790.71 Y
Add 15 % Contractor's profit and overheads on "Y" 118.61
Total 909.32 Z
Add Cess @ 1% on "Z" 9.09
Cost of 0.60 sqm. 918.41
Cost of 1 sqm. 1530.69
Say 1530.70

9.158 Providing and fixing in wall lining medium


density
marked,fibre board IS: 14587:1998
Pre-laminated one side
decorative lamination and other side
balancing lamination, with necessary fixing
arrangement
complete. and screws etc.
9.158.1 12 mm thick.
Details of cost for 10.00 sqm
MATERIAL
12 mm thick MDF Board Grade-I ,one side 0.00
laminated = 10.00 sqm
Add wastage @10 % = 1.00 sqm
Total= 11.00 sqm
2487 Pre-laminated with decorative lamination one side sqm 11 430 4730.00
and other side balancing lamination exterior Grade
- I MDF Board 12 mm thick confirming to IS:14587
9999 Sundries (Carriage of MDF board) L.S. 13.52 2.00 27.04
9999 Sundries and screws L.S. 26.91 2.00 53.82
LABOUR
15 Carpenter 2nd class day 1.28 403.67 516.70
17 Beldar day 1.43 350.00 500.50
7048 Rawl plug 50 mm (designation 10 nos) each 55 25 1375.00
TOTAL 7203.06 W
Add 1 % Water charges on "W" 72.0306
TOTAL 7275.09 X
Add GST (multiplying factor 0.1405) on "X" 1022.15
TOTAL 8297.24 Y
Add 15 % Contractor's profit and overheads on "Y" 1244.59
Total 9541.83 Z
Add Cess @ 1% on "Z" 95.42
Cost of 10.00 sqm. 9637.25
Cost of 1 sqm. 963.73
Say 963.70

9.158.2 18 mm thick.
Details of cost for 10.00 sqm
MATERIAL
18 mm thick MDF Board Grade-I ,one side
laminated = 10.00 sqm
Add wastage @10 % = 1.00 sqm
Total= 11.00 sqm
2488 Pre-laminated with decorative lamination one side sqm 11 565 6215.00
and other side balancing lamination exterior Grade
- I MDF Board 18 mm thick confirming to IS:14587
9999 Sundries (Carriage of MDF board) L.S. 13.52 2.00 27.04
9999 Sundries and screws L.S. 26.91 2.00 53.82
LABOUR
15 Carpenter 2nd class day 1.28 403.67 516.70
17 Beldar day 1.43 350.00 500.50
7048 Rawl plug 50 mm (designation 10 nos) each 55 25 1375.00
TOTAL 8688.06 W
Add 1 % Water charges on "W" 86.8806
8774.94 X
TOTAL 1232.88
Add GST (multiplying factor 0.1405) on "X" 10007.82 Y
TOTAL 1501.17
Add 15 % Contractor's profit and overheads on "Y" 11508.99 Z
Total 115.09
Add Cess @ 1% on "Z" 11624.08
Cost of 10.00 sqm. 1162.41
Cost of 1 sqm. 1162.40
Say

9.158.3 25 mm thick.
Details of cost for 10.00 sqm
MATERIAL
25 mm thick MDF Board Grade-I ,one side
laminated = 10.00 sqm
Add wastage @10 % = 1.00 sqm
Total= 11.00 sqm
2486 Pre-laminated with decorative lamination one side sqm 11 860 9460.00
and other side balancing lamination exterior Grade
- I MDF Board 25 mm thick confirming to IS:14587
9999 Sundries (Carriage of MDF board) L.S. 13.52 2.00 27.04
9999 Sundries and screws L.S. 26.91 2.00 53.82
LABOUR
15 Carpenter 2nd class day 1.28 403.67 516.70
17 Beldar day 1.43 350.00 500.50
7048 Rawl plug 50 mm (designation 10 nos) each 55 25 1375.00
TOTAL 11933.06 W
Add 1 % Water charges on "W" 119.3306
TOTAL 12052.39 X
Add GST (multiplying factor 0.1405) on "X" 1693.36
TOTAL 13745.75 Y
Add 15 % Contractor's profit and overheads on "Y" 2061.86
Total 15807.61 Z
Add Cess @ 1% on "Z" 158.08
Cost of 10.00 sqm. 15965.69
Cost of 1 sqm. 1596.57
Say 1596.60

9.159 Providing and fixing 25mm thick pre-


laminated medium
exterior grade density
( Grade-I) fibre board
IS:14587:1998
marked with
other side one sidelamination
balancing decorativeforand
cupboard
PVC edgeshutters
bendingedges to bemm
tape 2.00 sealed
thickwith
of
approved brand including ISI marked
nickel plated bright finishing M.S. piano
hinges conforming
with necessary to IS:3818
screw marked
etc all complete.
Detail of Cost for 2.20 sqm
(2.20 m x 1.00 m)
MATERIAL
2486 Pre-laminated with decorative lamination one side sqm 2.2 860 1892.00
and other side balancing lamination exterior Grade
- I MDF Board 25 mm thick confirming to IS:14587
9999 Sundries (Carriage of MDF board) L.S. 26.94 2.00 53.88
PVC edge bending tape 2.00 mm thick
2x(2.20+1.00)=6.40 metre
2489 PVC edge bending tape 2.00 mm thick metre 6.4 20 128.00
Fitting for a door of 2.20 m x1.00 m
Total = 2( 2.20) = 4.40 metre
608 Nickel plated bright finished mild steel piano metre 4.4 39 171.60
639 hinges 1 mm thick 25 mm wide 36
Bright finished or black enameled mild steel 100 1.25 36 45
screws 25 mm Nos
LABOUR
For fixing shutter and fittings
41 Carpenter (average) day 0.55 403.67 222.02
17 Beldar day 0.55 350.00 192.50
TOTAL 2705.00 W
Add 1 % Water charges on "W" 27.05
TOTAL 2732.05 X
Add GST (multiplying factor 0.1405) on "X" 383.85
TOTAL 3115.90 Y
Add 15 % Contractor's profit and overheads on "Y" 467.39
Total 3583.29 Z
Add Cess @ 1% on "Z" 35.83
Cost of 2.20 sqm. 3619.12
Cost of 1 sqm. 1645.05
Say 1645.10

9.16 Providing and fixing skirting with Pre-


laminated medium
exterior grade density
(Grade-I) fibre board
conforming to IS:
14587:1998 marked, with (one side
decorative and other side balancing
lamination and edges to be sealed with
PVC edge bending tape 2.00 mm thick of
approved brand with necessary
fixing arrangements and screws, including
drilling necessary
plugs etc. holes for rawl
all complete.
9.160.1 18 mm thick.
Details of cost for 6.00 sqm
Detail of cost for skirting 200 mm wide &
30 m long
Area 0.20 mx30 m = 6.0 sqm
Area 0.20 m x30 m = 6.0 sqm
Add wastage @ 10 % = 0.60 sqm
Total = 6.60 sqm
MATERIAL
2488 Pre-laminated with decorative lamination one side sqm 6.6 565 3729.00
and other side balancing lamination exterior Grade
- I MDF Board 18 mm thick confirming to IS:14587
9999 Sundries (Carriage of MDF board) L.S. 8.11 2.00 16.22
2489 PVC edge bending tape 2.00 mm thick metre 30 20 600.00
7048 Rawl plug 50 mm (designation 10 nos) each 102 25 2550.00
9999 Sundries (Labour for drilling hole) L.S. 130 2.00 260.00
LABOUR
15 Carpenter 2nd class day 0.77 403.67 310.83
17 Beldar day 0.86 350.00 301.00
9999 Sundries ( screws and sand paper) L.S. 53.82 2.00 107.64
TOTAL 7874.69 W
Add 1 % Water charges on "W" 78.7469
TOTAL 7953.44 X
Add GST (multiplying factor 0.1405) on "X" 1117.46
TOTAL 9070.90 Y
Add 15 % Contractor's profit and overheads on "Y" 1360.63
Total 10431.53 Z
Add Cess @ 1% on "Z" 104.32
Cost of 6.00 sqm. 10535.85
Cost of 1 sqm. 1755.97
Say 1756.00

9.160.2 25 mm thick.
Details of cost for 6.00 sqm
Detail of cost for skirting 200 mm wide & 30 m long
Area 0.20 mx30 m = 6.0 sqm MATERIAL: Area 0.20
m x30 m = 6.0 sqm
Add wastage @ 10 % = 0.60 sqm Total = 6.60 sqm

MATERIAL
2486 Pre-laminated with decorative lamination one side sqm 6.6 860 5676.00
and other side balancing lamination exterior Grade
- I MDF Board 25 mm thick confirming to IS:14587
9999 Sundries (Carriage of MDF board) L.S. 8.11 2.00 16.22
2489 PVC edge bending tape 2.00 mm thick metre 30 20 600.00
7048 Rawl plug 50 mm (designation 10 nos) each 102 25 2550.00
9999 Sundries (Labour for drilling hole) L.S. 130 2.00 260.00
LABOUR
15 Carpenter 2nd class day 0.77 403.67 310.83
17 Beldar day 0.86 350.00 301.00
9999 Sundries ( screws and sand paper) L.S. 53.82 2.00 107.64
TOTAL 9821.69 W
Add 1 % Water charges on "W" 98.2169
TOTAL 9919.91 X
Add GST (multiplying factor 0.1405) on "X" 1393.75
TOTAL 11313.66 Y
Add 15 % Contractor's profit and overheads on "Y" 1697.05
Total 13010.71 Z
Add Cess @ 1% on "Z" 130.11
Cost of 6.00 sqm. 13140.82
Cost of 1 sqm. 2190.14
Say 2190.10

9.161 Providing and fixing fire resistant door frame


of section 50 x 60 mm on horizontal side & 35
horizontal
x 60 mm onside & 35
vertical x 60having
sides mm on vertical
built in
sides
rebate
of having
1.6 mm built
madethick
out GI in
of 1.6rebate made
mm(thick
sheet ZincGI out not
sheet
coating
less than
Details 120gm/m²)
of cost suitable
for 5.81 metre (1.71 +for
2.05) (Door
size-1710 x 2050 mm)
MATERIAL:
8017 Fire Rated door Frame made with 1.6 mm thick metre 5.81 1000 5810.00
G.I. Sheet (120 minutes)
LABOUR:
9999 For fixing in position all complete L.S. 130 2 260.00
9999 Sundries and carriage ( Fasteners, sims, Hole L.S. 250 2.00 500.00
Plugs etc)
Total 6570.00 W
Add 1 % Water
Providing and charges
fixing 60onmm
"W"thick glazed fire 65.7
resistant door shutters of 120 min Fire Rating
TOTAL 6635.70 X
confirming to IS:3614 (Part II) or EN1634-
Add GST (multiplying factor 0.1405) on "X" 932.32
1:1999, tested and certified as per laboratory
approved by Engineer-in-charge, with suitable
TOTAL 7568.02 Y
mounting on door frame, consisting of vertical
Add 15 % Contractor's profit and overheads on "Y"
styles, top rail & side rail 60 mm x 60 mm wide 1135.20
and bottom rail of 110 mm x 60 mm made out
Total 8703.22 Z
of
Add1.6mm
Cess @ thick G.I."Z"sheet (zinc coating not less
1% on 87.03
than 120gm/m²) duly filled mineral wool
Cost of 5.81having
insulation metre density min 96 kg/m³ and 8790.25
fixing with necessary
Cost of 1 metre stainless steel ball 1512.95
bearing hinges of size 100x89x3mm of
Say 1513.00
approved make, including applying a coat of
approved fire resistant primer or powder
coating not less than 30 micron etc all
complete as per direction of Engineer-in-
9.162 charge (panelling to be paid for seperately).
Details of cost for 3.50 sqm (Door size-
1710 x 2050 mm) material
MATERIAL:
8018 Fire Rated door shutter made with 1.6 mm thick sqm 3.5 5000 17500.00
Sheet (120 minutes), including hinges
but without glass panels but including wastages
8101 Stainless steel ball bearing hinges of size each 8 450 3600.00
9999 100x89x3mm LABOUR: 0.00
For fixing in position all complete L.S. 130 2 260
9999 Sundries and carriage L.S. 280 2.00 560.00
Total 21920.00 W
Add 1 % Water charges on "W" 219.2
TOTAL 22139.20 X
Add GST (multiplying factor 0.1405) on "X" 3110.56
TOTAL 25249.76 Y
Add 15 % Contractor's profit and overheads on "Y" 3787.46
Total 29037.22 Z
Add Cess @ 1% on "Z" 290.37
Cost of 3.5 sqm 29327.59
Cost of 1 sqm 8379.31
Say 8379.30

9.163 Providing and fixing non load bearing fixed


frame
Partitionforfor
fire120
resistant
minutes glazed
Fire Rating, made
out to a profile of dimension
x 70 mm of 1.6 mm thick galvanised 60mm steel
sheet as fire
for fixing per rated
test evidence
glass forsuitable
120 minutes of
both integrity & radiation
(EW120) & minimum 20 minutes of control
insulation (EI20).The
to the supporting profile has
construction bytomeans
be fixed
of
anchor fasteners of size
every 150 mm from the edges and M10 x 80,
every 500 mmof(approx)
measurement frame shall c/c.beLinear
measured
for payment.
filled The frame
with mineral shall be of density
wool insulation
min 96kg/ fire
approved m³ and finished
resistant withora Powder
primer
coating
desired shade as per NBC micron
of not less than 30 2016, ISin16231
(Part
Engineer3):2016
- in- and directions of
charge.
Details of cost for 5.81 metre (2.05+1.71+2.05)
(Door size-1710 x 2050 mm)
MATERIAL:
8017 Fire Rated door Frame made with 1.6 mm metre 5.81 1000 5810.00
thick G.I. Sheet (120 minutes)
LABOUR:
9999 For fixing in position all complete L.S. 130 2 260.00
9999 Sundries and carriage ( Fasteners, sims, Hole L.S. 250 2.00 500.00
Plugs etc)
Total 6570.00 W
Add 1 % Water charges on "W" 65.7
TOTAL 6635.70 X
Add GST (multiplying factor 0.1405) on "X" 932.32
TOTAL 7568.02 Y
Add 15 % Contractor's profit and overheads on "Y" 1135.20
Total 8703.22 Z
Add Cess @ 1% on "Z" 87.03
Cost of 5.81 mtere 8790.25
Cost of 1 metre 1512.95
Say 1513.00
9.164 Providing and fixing glazing in fire resistant
door shutters,
partitions etc., fixed panels
with G.I. &
beading made out
of 1.6 mm
coating notthick
less G.I.
thansheet (zinc of size
120 gm/m²)
20 xscrews
SS 33 mmatscreweddistancewith
75 mmM4 xfrom
38 mm
the
edges and 150 mm c/c , including
applying a coat of approved fire resistant
primer/
than 30 powder
micron on coating of not less
G.I. beading, & special
ceramic tape of 5 x 20 mm size
complete in all respect as per NBC 2016, etc
IS 16231 of
direction (Part 3):2016 and as with
Engineer-incharge per glass of
required
minutes of thickness having both
fire resistance 120 integrity &
radiation
minimum control
20 minutes(EW120) and
of insulation (EI20).
The manufacturer have to give
report/certification of fire glass and thetest
glass should
the value of E,have
EWthe stamp
& EI. The showing
glass shall be
tested in approved NABL accredited
lab or by any other accreditation body
which
ISO/IEC operates
17011 in andaccordance with as per
accredits labs
ISO/IEC
calibration 17025
scopes for shall
testing
beand
eligible. The
maximum glazing
more than 1100x2200 mm (wsize shall not be or 2.42
x h)
sqm.
Details of cost for glazing portion 2.46 sqm (Door
size 1710 mm x 2050 mm)
Glazing area- 2x0.679x1.808= 2.46 sqm
MATERIAL:
2640 Glass pans of required thicknes having 120 sqm 2.46 25000 61500.00
miuntes of fire resistance both integrity and
radition control (EW 120) & minimum 20 minuts of
2641 insulationClear( EI 20)
G.I. U beading of 1.6 mm thick G.I. Sheet with metre 9.91 245 2427.95
2642 M4x38mm SS screws
Ceramic tape 5x20 mm size metre 19.82 410 8126.2
LABOUR:
9999 For fixing in position all complete L.S. 180 2 360.00
9999 Sundries and carriage & Calcium Silicate Blocks L.S. 10 2.00 20.00
Total 72434.15 W
Add 1 % Water charges on "W" 724.3415
TOTAL 73158.49 X
Add GST (multiplying factor 0.1405) on "X" 10278.77
TOTAL 83437.26 Y
Add 15 % Contractor's profit and overheads on "Y" 12515.59
Total 95952.85 Z
Add Cess @ 1% on "Z" 959.53
Cost of 2.46 sqm 96912.38
Cost of 1 sqm 39395.28
Say 39395.30
9.165 Providing and fixing bright /matt finished
Stainless Steel handles of approved
quality & make with necessary screws etc
9.165.1 all complete.
125mm
Details of cost for ten nos (125 mm)
554 Stainless steel fancy handles (125mm) for kitchen 10 Nos 1 640 640.00
8214 cabinet
SS screws 20mm 100 0.4 125 50
9999 Nos.
Carriage of material LS 1.82 2 3.64
LABOUR
14 Carpenter 1st class day 0.06 505.17 30.31
TOTAL 723.95 W
Add 1 % Water charges on "W" 7.2395
TOTAL 731.19 X
Add GST (multiplying factor 0.1405) on "X" 102.73
TOTAL 833.92 Y
Add 15 % Contractor's profit and overheads on "Y" 125.09
Total 959.01 Z
Add Cess @ 1% on "Z" 9.59
Cost for 10nos 968.60
Cost for1 no 96.86
Say 96.90

9.165.2 100mm
Details of cost for ten nos (100 mm)
MATERIAL
553 Stainless steel fancy handles (100mm) for kitchen 10 Nos 1 455 455.00
8214 cabinet 0.00
SS screws 20mm 100 0.4 125 50.00
9999 Nos. 0.00
Carriage of material L.S. 1.82 2 3.64
LABOUR 0.00
14 Carpenter 1st class day 0.06 505.17 30.31
TOTAL 538.95 W
Add 1 % Water charges on "W" 5.3895
TOTAL 544.34 X
Add GST (multiplying factor 0.1405) on "X" 76.48
TOTAL 620.82 Y
Add 15 % Contractor's profit and overheads on "Y" 93.12
Total 713.94 Z
Add Cess @ 1% on "Z" 7.14
Cost for 10nos 721.08
Cost for1 no 72.11
Say 72.10

9.165.3 75 mm
Details of cost for ten nos (75 mm)
MATERIAL
552 Stainless steel fancy handles (75mm) for kitchen 10 Nos 1 255 255.00
8214 cabinet
SS screws 20mm 100 0.4 125 50
9999 Nos.
Carriage of material LS 1.82 2 3.64
LABOUR
14 Carpenter 1st class day 0.06 505.17 30.31
TOTAL 338.95 W
Add 1 % Water charges on "W" 3.3895
TOTAL 342.34 X
Add GST (multiplying factor 0.1405) on "X" 48.10
TOTAL 390.44 Y
Add 15 % Contractor's profit and overheads on "Y" 58.57
Total 449.01 Z
Add Cess @ 1% on "Z" 4.49
Cost for 10nos 453.50
Cost for1 no 45.35
Say 45.40
673
120619.05

95763.05
62182.4

107736.4
91310.9
57531.35
12061.94

9576.4
6218.35
3122.6

2779.1
1890.8
1717.95
2415.25
2415.25

2458.81
2592.6
2846.8

2639.6
1646.95
1953.8

1986.25
2115.95
1042.4

1386.2
1451.05
1507.8

1661.9
1241.35
1565.7

1106.75
3818.2
3425.65
2415.8
2218.2
3338.6
3012.2
2458.8

267.6
214.05

6.7
126.5
181.6

55.15
3258.35
3400.7
3110.55
3149.05
545.8

817.9
1086.75
1442.05

2832.75
2565.15
2273.45
1695.5

1628.6
1591.1

441.5
401.4

173.95
180.6

354.55

93.65
3669.3
2427.55
3244.25
3795.75
2554.05
3370.75
3242.05
2180.9
2878.2
3368.55
2307.2
3004.7
2458.8

2204.6
146.1
193.4
110.7

134.35
2154.2
421.45
548.15
33.2

107.05
42

272.8
373.15
480.15

155.65
162.35
129.2
147.4

1084.35
1292.15
994.55
642.45

173.95
139.7
88781.45

54657.35
37.7

28.75
22.45
12.4

47.75
39.45

27.7
16.55

37.4
29.6

23.75
13.05

65.1
61.75
51.3

43.9
222.15

195.35
167.1

247.55
218.1

193.85
185.35
180

196.05
173.1

159.8
70.05

56.5
48.45

35.45
94.5
76.9

63.5
32.4

25.5
21.5

25.45
22.3

18.45
54.7

47.3
40.65

84.4
75.95
66.05

48
29

87.35
68.75

54.05
218.75

147.3
165.55
115.75

137.3
76

31.4
383.05

341.6
313.5

277.1
370.15

296.35
228.15
156.15

268.2
254.8

653.2

532.75
934.15

191.6
231.75

238.4
258.5

57.8
202.55

187.35
147.2

105.65
962.75

810.85
72.15
182.7

145.75
139.05

115.3
104.1

91.4
746.85

786.95

198.3
211.65

245.1
278.55

116.7
223.95

196.75
176.65

136.65
203.55
176.8

150.05
128.8

106.45
97.15

87.9
80.65

69.35
62.75
58.75

239.6
214.2

112.45
99.2

85.6
72.2

55.35
75.8
207.7

57.55
50.75

43.8
32.9

61
59.05

689.05
139.35
1451.6
1224.15
1518.45
1398.05
1384.7

37.75
37.75

59.15
75.55
72.55

100.2
35.7
489.85

246.25
60.7

591.5
39.05

31.05
339.75

14.8
198.7

244.5
1632.15
1850.1
2453.75
368.7
2294.85

2294.85
656.9
3336.5
3803.45

453.55
2900.3
3034.1
900.4

1702.4
1953.8
776

650.9
4851.25
1765.95

1485
1384.65
1433.75
517.8
1170.3
875.85

868.5
780.2
3800.3
2558.55
3375.25
3926.75
2685.05
3501.75
3373.05
2311.75
3009.2
3499.55
2438.35
3135.7
1214.8

862.65
1444.3
6166
36050.45

7075.3
920.05
433.85
3112.25

3714.3
505.4
3390.3

565.6
3657.9
9483.5
8717.7
6982
9331
9666.2
7242.25
6478.75
9131.45
9328.3
6709.6
8954.2
6912.15
8616
8177.05
6861.6
5941.95
6005
5332.85
6064.8
7774.55
289.75

323.2
343.25
477.05

503.8
182.2

148.75
83.15

135.35
162.1
109.65
1321.3

787.4
982.25
1101.15
1519.65
953.15

1151.85
1586
1625.55
1745.35
2179.55

1512.95
8379.3

1512.95
39395.3
96.65
71.85

45.1
SUB HEAD : 10.0 350.00

STEEL WORK
Code 10.1 Structural steel work in single section, fixed Unit
Description Quantity Rate Amount
with or without connecting plate, including cutting,
hoisting, fixing in position and applying a priming
coat of
approved steel primer all complete.

Details of cost for one qunital

MATERIAL
Steel = 1.00q
Add wastage @ 5% = 0.05q
Total = 1.05q
1007 Structurals such as tees,angles channels and R.S. quintal 1.05 5300 5565.00
joists
2205 Carriage of Steel tonne 0.105 94.34 9.91
LABOUR
19 Fitter (grade 1) day 0.5 505.17 252.59
13 Blacksmith 2nd class day 0.75 403.67 302.75
17 Beldar day 1 350.00 350.00
Priming Coat
13.50.3 Rate as per Item Number 13.50.3 of SH:Finishing sqm 3 33.3 99.90 A
9999 Sundries L.S. 20.67 2 41.34
TOTAL 6621.49 W
Add 1 % Water charges on "W-A" 6480.25 64.8025
TOTAL X
Add GST (multiplying factor 0.1405) on "X-A" 6545.05 919.58
TOTAL Y
Add 15 % Contractor's profit and overheads on "Y-A" 7464.63 1119.69
Total Z
Add Cess @ 1% on "Z-A" 8584.32 85.84
Cost of 1qunital 8811.40
Cost of 1 Kg. 88.11
Say 88.10 77.55

10.2 Structural steel work riveted, bolted or


welded in built up sections, trusses and framed
work, including cutting, hoisting, fixing in position
and applying a priming
coat of approved steel primer all complete.

Details of cost for a truss 7.6m clear span


(weight = 3.95 quintal)
MATERIAL
(i) Principal rafter (T-iron)
100x100x10mm @15kg/m = 142.50Kg+
Struts (angles)40x40x6mm
2x1.35=2.70m @ 3.5kg/m = 9.45kg
Total =151.95kg+
Add wastage @ 5% = 7.60kg
Total = 159.55kg. = 1.60q
1007 Structurals such as tees,angles channels and R.S. quintal 1.6 5300 8480.00
joists
(ii) Ties (flats) 50x12mm
2x2.7 = 5.4m @4.7kg/m = 25.38kg+
Ties central (flats) 50x10mm
1x2.28 = 2.8m @3.90kg/m = 10.92kg.+
Braces (flats)40x10mm
2x1.84 = 3.68m @3.9kg/m = 14.35kg.
Total = 50.65kg+
Add wastage @ 5% = 2.53kg. Total = 53.18kg. =
0.53q
1009 Flats exceeding 10 mm in thickness quintal 0.53 5300 2809.00
(iii) Gusset plates 10mm thick 1x0.74x0.35m =
0.259sqm.+ shoe 4x0.46x0.46 = 0.845sqm.
Total = 1.104 sqm.
1.104sqm.@ 78.4kg/m = 86.55kg.
12mm plates at the point of principal
rafter and strut-
2x0.3x0.2 = 0.12sqm.+
Tie beam, brace and strut2x0.5x0.3 = 0.30sqm.+
Sole plates-
2x0.46x0.46 = 0.42sqm.+
Anchor plate-
2x0.46x0.1 = 0.09sqm.
Total = 0.93 sqm.
Say 1.00 sqm.
1.0sqm. @ 94.4kg/m = 94.40kg. Total = 180.95kg.
Add wastage @ 5% = 9.05kg. Total = 190.00kg or
1.90q
1010 Mild steel plates quintal 1.9 5300 10070.00
(iv) 16mm dia. 50mm long rivets = 56 nos.+ Add
wastage @ 5 % = 2.8 nos.
Total = 58.8 nos.
1020 Mild steel rivets quintal 0.0684 5000 342.00
(v) 20mm dia. holding down bolts
4 Nos.x460mm = 1840mm +
Add wastage @ 5% = 92mm
Total =1932 mm
1221 20 mm dia holding down bolts quintal 0.0529 6100 322.69
2205 Carriage of Steel tonne 0.415 94.34 39.15
(0.160+0.053+0.091 +0.099+
0.007+0.005)
=0.415 tonne
LABOUR
19 Fitter (grade 1) day 2.7 505.17 1363.96
13 Blacksmith 2nd class day 3.6 403.67 1453.21
37 Skilled Beldar (for floor rubbing etc.) day 5.4 350.00 1890.00
17 Beldar day 3.6 350.00 1260.00
10 Bandhani day 0.44 350.00 154.00
Applying priming coatT.Iron 9.5x0.4 = 3.80sqm.+
Struts 2.70x0.16 = 0.43sqm.+
Ties 5.4x0.124 = 0.67sqm.+ Braces 2x1.84x0.12 =
0.44 sqm.+ Ties 2.8x0.12 = 0.34 sqm.
Total = 5.68 sqm.
13.50.3 Rate as per item no 13.50.3 of SH : Finishing sqm 5.68 33.3 189.14
9999 Sundries L.S. 80.73 2 161.46
TOTAL 28534.61 W
Add 1 % Water charges on "W-A" 28345.47 283.4547
TOTAL X
Add GST (multiplying factor 0.1405) on "X-A" 28628.92 4022.36
TOTAL Y
Add 15 % Contractor's profit and overheads on "Y-A" 32651.28 4897.69
Total Z
Add Cess @ 1% on "Z-A" 37548.97 375.49
Quantity of net steel (151.95+50.65+180.95+6.5+5.04) = 395.09
38113.60
kg= 3.95 quintal
Cost of per kg. 96.49
Say 96.50 86.65

10.3 Providing and fixing in position collapsible


steel shutters with vertical channels 20x10x2 mm
and braced with flat iron diagonals 20x5 mm size,
with top and bottom rail of T-iron 40x40x6 mm, with
40 mm
coat of dia steel pulleys,
approved complete with bolts, nuts,
steel primer.
locking arrangement, stoppers, handles, including
Details of cost for a gate 2.4mx1.5m = 3.6sqm.
applying a priming
MATERIAL
M.S. channels 18 Nos. on both sides
20x10x2mm @ 0.56kg/m
2x18x2.4 = 86.40m+
Add wastage @ 10% = 8.64m
Total = 95.04m
95.04m@0.56kg/m =53.22kg=0.53q
1007 Structurals such as tees,angles channels and R.S. quintal 0.53 5300 2809.00
joists
M.S. Tee-40x40x6mm for bottom-1.570m+ for top =
1.725m
Total =3.295m Say 3.3m
3.3m @ 3.5kg/m = 11.55kg+ Add wastage @ 10%
= 1.155 Kg. Total = 12.705Kg. Say 0.13q
1007 Structurals such as tees,angles channels and R.S. quintal 0.13 5300 689.00
joists
20mmx5mm flat iron diagonals 4 Nos.
4x32x0.5334 = 68.275m
68.275m @ 0.8kg/m = 54.62kg+
Add wastage @10% = 5.46kg
Total = 60.08kg = 0.60q
1008 Flats upto 10 mm in thickness quintal 0.6 4500 2700.00
2205 Carriage of Steel tonne 0.126 94.34 11.89
(0.053+0.013+0.060=0.126 tonne)
9999 Cost of rivets fixing hooks and washers L.S. 269.1 2 538.20
9999 Cost of locking arrangements and handles L.S. 67.34 2 134.68
4013 Pully 40 mm dia each 10 30 300.00
Priming coat-
Channel - 36x0.076x2.4 = 6.57sqm.+ Tee-0.16x3.3
= 0.53sqm.+ Flats-0.05x68 = 3.40sqm.
Total = 10.50sqm.
13.50.3 Rate as per item no 13.50.3 of sqm 10.5 33.3 349.65 A
SH : Finishing
LABOUR
19 Fitter (grade 1) day 3 505.17 1515.51
12 Blacksmith 1st class day 6 505.17 3031.02
13 Blacksmith 2nd class day 6 403.67 2422.02
23 Mason (brick layer) 1st class day 0.5 505.17 252.59
24 Mason (brick layer) 2nd class day 0.5 403.67 201.84
17 Beldar day 8 350.00 2800.00
9999 Sundries L.S. 161.46 2 322.92
TOTAL 18078.32 W
Add 1 % Water charges on "W-A" 17728.67 177.2867
TOTAL X
Add GST (multiplying factor 0.1405) on "X-A" 17905.96 2515.79
TOTAL Y
Add 15 % Contractor's profit and overheads on "Y- 20421.75 3063.26
A" Z
Total 23485.01 234.85
Add Cess @ 1% on "Z-A" 24069.51
Cost of 3.6sqm. 6685.97
Cost per sqm. 6686.00
10.4
Say
Providing and fixing 1 mm thick M.S. sheet 6254.1
sliding-shutters, with frame and diagonal braces of
40x40x6 mm angle iron, 3 mm M.S. gusset plates at
the junctions and corners, 25 mm dia pulley,
40x40x6 mm angle and T- iron guide at the top and
steel primer.
bottomofrespectively,
Details including
cost for one double applying
leaf door a priming
size 2.4x2.4m =
coat of approved
5.76sqm.

MATERIAL
(i) M.S. sheet 1mm thick
5.76sqm. @ 7.85kg/sqm. = 45.216kg.+ Add
wastage @ 10% = 4.522kg. Total = 49.738kg =
0.497 q
1013 Mild steel sheets for tanks quintal 0.497 4600 2286.20
(ii) Gusset plates 3.00mm thick
Area of one gusset plates
0.3x0.04 = 0.0120+
1/2x0.26(0.04+0.3) = 0.0442
Total = 0.0562sqm.+
8x0.0562 = 0.4496sqm.+
2x22/7x1/4x0.3x0.3=0.1414sqm.
Total = 0.5910sqm.
0.5910sqm.@23.55kg/sqm.=13.92kg.+
Add wastage @ 10% = 1.39kg
Total = 15.31kg. or 0.153q
1010 Mild steel plates quintal 0.153 5300 810.90
(iii) Angle iron
40x40x6mm @ 3.5kg/m
Sides-4x2.4=9.6m+
Bottom & top 4x1.2 = 4.8m+
Diagonals-2x2.5=5.0m+

2x2.45 = 4.9m+

Top and bottom guides 2x4.8 = 9.6m

Top guide supports 7x0.8 = 2.1m Total = 36.0m


36m @3.5kg. per m. = 126kg.+ Add wastage @
10% = 12.6kg. Total = 138.6kg. or 1.39q
1007 Structurals such as tees,angles channels and R.S. quintal 1.39 5300 7367.00
joists
Channel 25x25x6mm @ 3.05kg/m
Bottom-2.4m : 2.4x3.05
Channel 40x40x6mm @ 5.56kg/m 0.5x5.56 =
2.78kg.
Total = 10.1kg.+
Add wastage @ 10% = 1.101kg. Total = 11.11kg.
or 0.11q
1007 Structurals such as tees,angles channels and R.S. quintal 0.11 5300 583.00
joists
2205 Carriage of Steel tonne 0.216 94.34 20.38
(0.0497+0.015+0.139+0.11=0.2157 tonne)
9999 (iv) Pully guide blocks including drilling holes L.S. 269.1 2 538.20
969 Pully 25 mm dia each 8 48 384.00
9999 (vi) Handles and locking arrangements L.S. 167.75 2 335.50
9999 (vii) Bolts and rivets L.S. 269.1 2 538.20
9999 (viii)Cement concrete L.S. 13.52 2 27.04
Priming coat-
M.S. Sheet 2x5.76 = 11.52+
Angle iron 0.16x36 = 5.76+
Channel-0.15x2.4=0.36+
0.24x0.5=0.12
Total = 17.76 Say 18.0sqm.
13.50.3 Rate as per item no 13.50.3 of sqm 18 33.3 599.40 A
SH : Finishing
LABOUR
19 Fitter (grade 1) day 2 505.17 1010.34
12 Blacksmith 1st class day 3 505.17 1515.51
13 Blacksmith 2nd class day 4 403.67 1614.68
17 Beldar day 4 350.00 1400.00
23 Mason (brick layer) 1st class day 0.06 505.17 30.31
24 Mason (brick layer) 2nd class day 0.06 403.67 24.22
9999 Sundries L.S. 161.46 2 322.92
TOTAL 19407.80 W
Add 1 % Water charges on "W-A" 18808.40 188.084
TOTAL X
Add GST (multiplying factor 0.1405) on "X-A" 18996.48 2669.01
TOTAL Y
Add 15 % Contractor's profit and overheads on "Y- 21665.49 3249.82
A" Z
Total 24915.31 249.15
Add Cess @ 1% on "Z-A" 25763.86
Cost of 5.76 sqm. 4472.89
Cost per sqm. 4472.90
Say 4122.35

10.5 Providing and fixing 1mm thick M.S. sheet


door with frame of 40x40x6 mm angle iron and 3
mm M.S. gusset plates at the junctions and
corners, all necessary fittings complete, including
applying a priming
10.5.1 Using coat of 40x40x6
M.S. angels approvedmm
steel
forprimer.
diagonal
braces
Details of cost for a double leaf door of size
2.4mx2.4m=5.76sqm.

MATERIAL
(i) M.S. sheet 1mm thick
5.76sqm. @ 7.85kg/sqm. = 45.216kg.+ Add
wastage @ 10% = 4.522kg. Total = 49.738kg =
0.497 q
1013 Mild steel sheets for tanks quintal 0.497 4600 2286.20
(ii) Gusset plates 3.00mm thick
Area of one gusset plates
0.3x0.04 = 0.0120+
1/2x0.26(0.04+0.3) = 0.0442
Total = 0.0562sqm.+
8x0.0562 = 0.4496sqm.+
2x22/7x1/4x0.3x0.3=0.1414sqm.
Total = 0.5910sqm.
0.5910sqm.@23.55kg/sqm.=13.92kg.+
Add wastage @ 10% = 1.39kg
Total = 15.31kg. or 0.153q
1013 Mild steel sheets for tanks quintal 0.153 4600 703.80
(iii) Angle iron:40x40x6mm @3.5kg/m
Sides-4x2.40 = 9.6m+
Top & bottom-4x1.20=4.8m+
Diagonals-2x2.5=5.0m+
2x2.45 = 4.9m+
Total = 24.30m+
Add wastage @ 10% = 2.43m
Total =26.73m
26.73m @ 3.5kg. per m. = 93.56kg=0.936q
1007 Structurals such as tees,angles channels and R.S. quintal 0.936 5300 4960.80
joists
2205 Carriage of Steel tonne 0.1586 94.34 14.96
(0.0497+0.0153+0.0936 tonne) = 0.1586 t
1036 Iron pintels including welded pin each 4 37 148.00
1222 Mild steel sheets with bolts and nuts to rest on each 4 120 480.00
pintels
1019 Mild steel hooks each 2 32 64.00
9999 Locking arrangements and handles L.S. 167.7 2 335.40
9999 Rivets L.S. 269.1 2 538.20
Priming coatM.S. sheet = 11.52
Angle iron-0.16x24.3 = 3.89
Total = 15.41
13.50.3 Rate as per item no 13.50.3 of sqm 15.41 33.3 513.15 A
SH : Finishing
LABOUR
19 Fitter (grade 1) day 2 505.17 1010.34
12 Blacksmith 1st class day 3 505.17 1515.51
13 Blacksmith 2nd class day 4 403.67 1614.68
23 Mason (brick layer) 1st class day 0.06 505.17 30.31
24 Mason (brick layer) 2nd class day 0.06 403.67 24.22
17 Beldar day 5 350.00 1750.00
9999 Sundries L.S. 161.46 2 322.92
TOTAL 16312.49 W
Add 1 % Water charges on "W-A" 15799.34 157.9934
TOTAL X
Add GST (multiplying factor 0.1405) on "X-A" 15957.33 2242.01
TOTAL Y
Add 15 % Contractor's profit and overheads on "Y- 18199.34 2729.90
A" Z
Total 20929.24 209.29
Add Cess @ 1% on "Z-A" 21651.68
Cost of 5.76 sqm. 3758.97
Cost per sqm. 3759.00
Say 3511.1

10.5.2 Using flats 30x6mm for diagonal braces


and central cross piece
Details of cost for a double leaf door of size 2.4x2.4m =
5.76sqm.

MATERIAL
(i) M.S. sheet 1mm thick
5.76sqm. @ 7.85kg/sqm. = 45.216kg.+ Add
wastage @ 10% = 4.522kg. Total = 49.738kg =
0.497 q
1013 Mild steel sheets for tanks quintal 0.497 4600 2286.20
(ii) Gussets plates-3.00mm thick vide (ii) in item
10.6 = 0.5910sqm.+ at mid height = 4x0.0528 =
0.2112sqm.
Total = 0.8022sqm.+
Add wastage @ 10% = 0.0802sqm.
Total =0.8824sqm.@ 23.55 kg/sqm
=20.78 kg
Grand Total = 0.2078 qtl
1010 Mild steel plates quintal 0.2078 5300 1101.34
(iii) Angle iron:40x40x6mm @3.5kg/m
Sides-4x2.40 = 9.6m+
Top & bottom-4x1.20=4.8m+
Total = 14.40m+
Add wastage @ 10% = 1.44m
Total = 15.84m
15.84m @ 3.5kg. per m. = 55.44kg = 0.554qtl
1007 Structurals such as tees,angles channels and R.S. quintal 0.554 5300 2936.20
joists
(iv) Flats 30x6mm @1.4kg/m
4x2.45=9.80m+
2x1.20=2.40m
Total = 12.20m+
Add wastage @ 10% = 1.22m
Total = 13.42m
13.42m @ 1.4kg. per m. = 18.788kg.
= 0.188q
1008 Flats upto 10 mm in thickness quintal 0.188 4500 846.00
Carriage of (i) (ii) and (iv)
0.0497+0.0208+0.0554+0.0188=0.1447 tonne
2205 Carriage of Steel tonne 0.1447 94.34 13.65
1036 Iron pintels including welded pin each 4 37 148.00
1222 Mild steel sheets with bolts and nuts to rest on each 4 120 480.00
pintels
1019 Mild steel hooks each 2 32 64.00
9999 Locking arrangements and handles L.S. 167.7 2 335.40
9999 Rivets L.S. 269.1 2 538.20
Applying priming coatM.S. sheet = 11.52
Angle iron-0.16x24.3 = 3.89
0.16x14.40 = 2.30+
Flats 0.072x12.2 = 0.88 Total = 14.70sqm.
13.50.3 Rate as per item no 13.50.3 of sqm 14.7 33.3 489.51
SH : Finishing
LABOUR
19 Fitter (grade 1) day 2 505.17 1010.34
12 Blacksmith 1st class day 3 505.17 1515.51
13 Blacksmith 2nd class day 4 403.67 1614.68
23 Mason (brick layer) 1st class day 0.06 505.17 30.31
24 Mason (brick layer) 2nd class day 0.06 403.67 24.22
17 Beldar day 5 350.00 1750.00
9999 Sundries L.S. 161.46 2 322.92
TOTAL 15506.48 W
Add 1 % Water charges on "W-A" 15016.97 150.1697
TOTAL X
Add GST (multiplying factor 0.1405) on "X-A" 15167.14 2130.98
TOTAL Y
Add 15 % Contractor's profit and overheads on "Y- 17298.12 2594.72
Total Z
Add Cess @ 1% on "Z-A" 19892.84 198.93
10.6 Supplying
Cost of 5.76 sqm. and fixing rolling shutters of 20581.28
approved make, made of required size M.S. laths,
Cost per sqm.
interlocked together through their entire length and 3573.14
jointed together at the end by end locks, mounted
Say 3573.10 3363.25
on specially designed pipe shaft with brackets, side
guides and arrangements for inside and outside
locking with push and pull operation complete,
including the cost of providing and fixing
10.6.1
necessary 80x1.25
27.5 cmmmlongM.S.wire
laths with 1.25
springs mm thick
manufactured
top cover
from high tensile steel wire of adequate strength
conforming to IS: 4454 - part 1 and M.S. top cover
Details of cost for a shutter of size 3mx2.5m = 7.5sqm.
of required thickness for rolling shutters.

MATERIAL
973 Rolling shutter made of 80x1.25 mm machine rolled sqm 7.5 1400 10500.00
laths
974 Top cover for rolling shutters 1.25 mm thick metre 2.5 800 2000.00
975 27.5 cm long wire spring grade no 2 for rolling each 1 300 300.00
shutters
9977 CARRIAGE LABOUR L.S. 53.82 2 107.64
19 Fitter (grade 1) day 2.55 505.17 1288.18
17 Beldar day 2.55 350.00 892.50
23 Mason (brick layer) 1st class day 0.12 505.17 60.62
24 Mason (brick layer) 2nd class day 0.12 403.67 48.44
9999 Sundries L.S. 60.58 2 121.16
TOTAL 15318.54 W
Add 1 % Water charges on "W" 153.1854
TOTAL 15471.73 X
Add GST (multiplying factor 0.1405) on "X" 2173.78
TOTAL 17645.51 Y
Add 15 % Contractor's profit and overheads on "Y" 2646.83
Total 20292.34 Z
Add Cess @ 1% on "Z" 202.92
Cost of 7.5 sqm. 20495.26
Cost per sqm. 2732.7
Say 2732.70 2704.9

10.6.2 80x1.20 mm M.S. laths with 1.20 mm thick


top cover

Details of cost for a shutter of size 3mx2.5m = 7.5sqm.

MATERIAL
7045 Rolling shutters of 80x1.2 mm laths sqm 7.5 1375 10312.50
7047 Top cover of Rolling shutters 1.20 mm thick metre 2.5 560 1400.00
975 27.5 cm long wire spring grade no 2 for rolling each 1 300 300.00
shutters
9977 CARRIAGE LABOUR L.S. 53.82 2 107.64
19 Fitter (grade 1) day 2.55 505.17 1288.18
17 Beldar day 2.55 350.00 892.50
23 Mason (brick layer) 1st class day 0.12 505.17 60.62
24 Mason (brick layer) 2nd class day 0.12 403.67 48.44
9999 Sundries L.S. 60.58 2 121.16
TOTAL 14531.04 W
Add 1 % Water charges on "W" 145.3104
TOTAL 14676.35 X
Add GST (multiplying factor 0.1405) on "X" 2062.03
TOTAL 16738.38 Y
Add 15 % Contractor's profit and overheads on "Y" 2510.76
Total 19249.14 Z
Add Cess @ 1% on "Z" 192.49
Cost of 7.5 sqm. 19441.63
Cost per sqm. 2592.22
Say 2592.20 2564.45

10.6.3 80x0.90 mm M.S. laths with 0.90 mm thick


top cover

Details of cost for a shutter of size 3mx2.5m = 7.5sqm.

MATERIAL
7044 Rolling shutters of 80x0.90 mm laths sqm 7.5 1300 9750.00
7046 Top cover of Rolling shutters 0.90 mm thick metre 2.5 450 1125.00
975 27.5 cm long wire spring grade no each 1 300 300.00
2 for rolling shutters 0
9977 CARRIAGE LABOUR L.S. 53.82 2 107.64
19 Fitter (grade 1) day 2.55 505.17 1288.18
17 Beldar day 2.55 350.00 892.50
23 Mason (brick layer) 1st class day 0.12 505.17 60.62
24 Mason (brick layer) 2nd class day 0.12 403.67 48.44
9999 Sundries L.S. 60.58 2 121.16
TOTAL 2410.90 W
Add 1 % Water charges on "W" 24.109
TOTAL 2435.01 X
Add GST (multiplying factor 0.1405) on "X" 342.12
TOTAL 2777.13 Y
Add 15 % Contractor's profit and overheads on "Y" 416.57
Total 3193.70 Z
Add Cess @ 1% on "Z" 31.94
Cost of 7.5 sqm. 3225.64
Cost per sqm. 3225.64
Say 3225.60 2415.05

10.7 Providing and fixing ball bearing for rolling


shutters.

Details of cost for 1 No.


976 Ball bearing for rolling shutters each 1 260 260.00
9999 Sundries L.S. 26.91 2 53.82
TOTAL 313.82 W
Add 1 % Water charges on "W" 3.1382
TOTAL 316.96 X
Add GST (multiplying factor 0.1405) on "X" 44.53
TOTAL 361.49 Y
Add 15 % Contractor's profit and overheads on "Y" 54.22
Total 415.71 Z
Add Cess @ 1% on "Z" 4.16
Cost of 1 no. 419.87
Say 419.87 419.85
419.90
10.8 Extra for providing mechanical device chain
and crank
10.8.1 operation
Exceeding for operating
10.00 rolling
sqm and upto shutters.
16.80 sqm in
the area

Details of cost for one sqm.


977 Extra for mechanical devices chain and cranked sqm 1 800 800.00
operation for operatingrolling shutters : exceeding
10.00 sq.m and upto
16.80 sq.m area of door
9999 Sundries L.S. 13.52 2 27.04
TOTAL 827.04 W
Add 1 % Water charges on "W" 8.2704
TOTAL 835.31 X
Add GST (multiplying factor 0.1405) on "X" 117.36
TOTAL 952.67 Y
Add 15 % Contractor's profit and overheads on "Y" 142.90
Total 1095.57 Z
Add Cess @ 1% on "Z" 10.96
Cost of 1 no. 1106.53
Say 1106.53 1106.55
1106.50
10.8.2 Exceeding 16.80 sqm in area

Details of cost for one sqm.


978 Extra for mechanical devices chain and cranked sqm 1 800 800.00
operation for operating rolling shutters : exceeding
16.80 sq.m area of door
9999 Sundries L.S. 13.52 2 27.04
TOTAL 827.04 W
Add 1 % Water charges on "W" 8.2704
TOTAL 835.31 X
Add GST (multiplying factor 0.1405) on "X" 117.36
TOTAL 952.67 Y
Add 15 % Contractor's profit and overheads on "Y" 142.90
Total 1095.57 Z
Add Cess @ 1% on "Z" 10.96
Cost of 1 no. 1106.53
Say 1106.53 1106.55
10.9 Extra for providing grilled rolling shutters 1106.50
manufactured out of 8 mm dia M.S. bar instead of
laths as per design approved by Engineer-in-
Details
charge, of (area
cost for
ofa grill
shutter
to of
bewidth 2.5m and grill height 0.6m
measured).
Grill Area = 1.50sqm.
MATERIAL
7068 Extra for providing grilled rolling shutters with 8 mm sqm 1.5 500 750.00
dia M.S. rod
TOTAL 750.00 W
Add 1 % Water charges on "W" 7.5
TOTAL 757.50 X
Add GST (multiplying factor 0.1405) on "X" 106.43
TOTAL 863.93 Y
Add 15 % Contractor's profit and overheads on "Y" 129.59
Total 993.52 Z
Add Cess @ 1% on "Z" 9.94
Cost of 1.5 sqm. 1003.46
Cost per sqm.
10.10 Fixing standard steel glazed doors, 668.97
windows and ventilators in walls, including fixing
Say 669.00 668.95
of float glass panes with glazing clips and special
metal-sash putty of approved make, or metal
beading with screws, (only steel windows, glass
10.10.1
panes cutFixing with
to size and15x3 mmclips
glazing lugs or
10 metal
cm long
embedded in cement concrete block 15x10x10
beading with screws, shall be supplied by cm
of C.C. 1:3:6 (1 Cement
department free of cost. : 3 coarse sand : 6 graded
stone aggregate
20 mm nominal size)

Details of cost for one door 2x0.76m =

1.52sqm.(weight 15 kg)
MATERIAL
Cement concrete blocks
15x10x10cm = 0.009 cum
4.2.5 Rate as per item no 4.2.5 of cum 0.009 6451.00 58.06 A
SH : Concrete work
LABOUR
12 Blacksmith 1st class day 0.17 505.17 85.88
23 Mason (brick layer) 1st class day 0.08 505.17 40.41
24 Mason (brick layer) 2nd class day 0.08 403.67 32.29
17 Beldar day 0.5 350.00 175.00
9977 Sundries for carriage of material L.S. 67.28 2 134.56
TOTAL 526.20 W
Add 1 % Water charges on "W-A" 468.14 4.6814
TOTAL X
Add GST (multiplying factor 0.1405) on "X-A" 472.82 66.43
TOTAL Y
Add 15 % Contractor's profit and overheads on "Y-A" 539.25 80.89
Total Z
Add Cess @ 1% on "Z-A" 620.14 6.20
Cost of 15 kg 684.40
Cost per kg 45.63
Say 45.60
43.55

10.10.2 Fixing with carbon steel galvanised dash fastener


of required dia and size (to be paid for separately)

Details of cost for one door 2x0.76m =


1.52sqm.(weight 15 kg)
LABOUR
23 Mason (brick layer) 1st class day 0.17 505.17 85.88
17 Beldar day 0.17 350.00 59.50
9977 Sundries for Carriage of material L.S. 67.28 2 134.56
TOTAL 279.94 W
Add 1 % Water charges on "W" 2.7994
TOTAL 282.74 X
Add GST (multiplying factor 0.1405) on "X" 39.72
TOTAL 322.46 Y
Add 15 % Contractor's profit and overheads on "Y" 48.37
Total 370.83 Z
Add Cess @ 1% on "Z" 3.71
10.11
Cost of 15Providing
kg and fixing factory made ISI 374.54
marked steel glazed doors, windows and
Cost per kg
ventilators, side /top /centre hung, with beading 24.97
and all members such as F7D, F4B, K11 B and K12
Say 25.00 24.1
B etc. complete of standard rolled steel sections,
joints mitred and flash butt welded and sash bars
tenoned and riveted, including providing and fixing
10.11.1
of hinges,Fixing
pivots, with 15x3 mm
including lugs 10
priming cmof
coat long
embedded in cement concrete block
approved steel primer, but excluding the cost of 15x10x10 cm
of C.C. 1:3:6 (1 Cement : 3 coarse sand
other fittings, complete all as per approved design, : 6 graded
stone aggregate 20
(sectional of mm nominal size) shall be
Details of costweight
for a double only
leaf steel
door members
of size 2.075x1.175m = 2.44 sqm.
measured
(weight 30 kg).for payment).
MATERIAL
1011 Steel glazed door,window/ ventilator, all members kg 30 55 1650.00
like as F7D, F4B, K11 and K12B etc.
9977 Carriage of Steel Door Labour for fabrication L.S. 40.37 2 80.74
13 Blacksmith 2nd class day 0.17 403.67 68.62
19 Fitter (grade 1) day 0.26 505.17 131.34
17 Beldar day 0.34 350.00 119.00
9999 Sundries L.S. 15.37 2 30.74
Fixing with CC 1:3:6 blocks, wooden plugs and
screws or rawl plugs and screws or with fixing clips
and bolts and nuts as required including metal sash
putty for glass fixing A
10.10.1 Rate as per Item No.10.10.1 kg 30 43.55 1306.50
Apply steel primer (2.44x1.00 for both sides)=2.44
sqm A
13.50.3 Rate as per item no 13.50.3 of SH : Finishing sqm 2.44 33.3 81.25
TOTAL 3468.19 W
Add 1 % Water charges on "W-A" 2080.44 20.8044
TOTAL X
Add GST (multiplying factor 0.1405) on "X-A" 2101.24 295.22
TOTAL Y
Add 15 % Contractor's profit and overheads on "Y- 2396.46 359.47
A" Z
Total 2755.93 27.56
Add Cess @ 1% on "Z-A" 4171.24
Cost for 30 kg. 139.04
Cost of 1 kg. 139.00
Say 136.7

10.11.2 Fixing with carbon steel galvanised dash


fastener of required dia and size (to be paid for
separately)
Details of cost for a double leaf door of size
2.075x1.175m = 2.44 sqm. (weight 30 kg).
MATERIAL
1011 Steel glazed door,window/ ventilator, all members kg 30 55 1650.00
like as F7D, F4B, K11 and K12B etc.
9977 Carriage of Steel Door Labour for fabrication L.S. 40.37 2 80.74
13 Blacksmith 2nd class day 0.17 403.67 68.62
19 Fitter (grade 1) day 0.26 505.17 131.34
17 Beldar day 0.34 350.00 119.00
9999 Sundries L.S. 15.37 2 30.74
Labour for fixing
17 Beldar day 0.027 350.00 9.45
18 Collie day 0.0195 350.00 6.83
30 Mistry day 0.0084 505.17 4.24
28 Mate day 0.0012 350.00 0.42
9999 Hire charges of drill machine, scaffolding and l.S. 12.22 2 24.44
sundries
Apply steel primer (2.44x1.00 for both sides)=2.44
sqm
13.50.3 Rate as per item no 13.50.3 of SH : Finishing sqm 2.44 33.3 81.25 A
TOTAL 2207.07 W
Add 1 % Water charges on "W-A" 2125.82 21.2582
TOTAL X
Add GST (multiplying factor 0.1405) on "X-A" 2147.08 301.66
TOTAL Y
Add 15 % Contractor's profit and overheads on "Y- 2448.74 367.31
A" Z
Total 2816.05 28.16
Add Cess @ 1% on "Z-A" 2925.46
Cost for 30 kg. 97.52
Cost of 1 kg. 97.50
Cost of 1 kg. 95.1
Say
10.12 Extra for providing and fixing steel beading
of size 10 x 10 x 1.6 mm (box type), approved shape
and section with screws instead of glazing clips
and metal sash putty, in steel doors, windows,
ventilators and composite units.
Detail of cost for 1 metre beading for doors,
windows, Ventilators and composit units
1143 Steel beading size 10 x 10 x 1.6 mm (box type) metre 1 27 27.00
9999 Applying priming coat L.S. 0.46 2 0.92
9999 Fixing charges L.S. 3.01 2 6.02
TOTAL 33.94 W
Add 1 % Water charges on "W" 0.3394
TOTAL 34.28 X
Add GST (multiplying factor 0.1405) on "X" 4.82
TOTAL 39.10 Y
Add 15 % Contractor's profit and overheads on "Y" 5.86
Total 44.96 Z
Add Cess @ 1% on "Z" 0.45
Cost of 1 metre 45.41
Say 45.41 45.4
10.13 Providing and fixing T-iron frames for
doors, windows and ventilators of mild steel Tee- 45.40
10.13.1
sections,Fixing
joints with 15x3
mitred andmm lugs 10
welded, cm longfixing
including
embedded in cement concrete block 15x10x10
of necessary butt hinges and screws and applying cm
of C.C. 1:3:6 (1 Cement : 3 coarse
a priming coat of approved steel primer.sand : 6 graded
Details
stone of cost for 17.5Kg.
aggregate 20 mm nominal size)
MATERIAL
Tee iron 40x40x6mm = 2m+2m+
1m = 5 metres
5 metres @3.5Kg/m = 17.5kg.+ Add wastage @
5% = 0.87Kg.
Total = 18.37 kg. Say 0.18 qunital
1007 Structurals such as tees,angles channels and R.S. quintal 0.18 5300 954.00
joists
M.S. bars 10mm = 1x1m = 1 metre 1 metre @
0.60kg/m = 0.60Kg.+ Add wastage @ 5% =
0.03Kg.
Total = 0.63 Kg. Say = 0.006 qunital
1002 Mild steel round bar 12 mm dia and below quintal 0.006 5500 33.00
M.S. flat 15x3mm = 6x10cm = 0.60 metre 0.6 metre
@ 0.35kg/m = 0.21Kg+ Add wastage @ 5% = 0.01
Kg.
Total = 0.22 kg = 0.002q.
1008 Flats upto 10 mm in thickness quintal 0.002 4500 9.00
Cement concrete block 1:3:6- 6x15x
10x10cm= 0.009 cum
4.2.5 Rate as per item no 4.2.5 of SH : Concrete work cum 0.009 6577.55 59.20 A
595 Bright finished or black enamelled mild steel butt 10 Nos 0.6 80 48.00
hinges 100x58x1.90 mm
9999 For screws and nuts and bolts L.S. 35.88 2 71.76
9999 For applying steel primer L.S. 17.94 2 35.88
9977 Carriage of material L.S. 5.33 2 10.66
LABOUR
13 Blacksmith 2nd class day 0.1 403.67 40.37
19 Fitter (grade 1) day 0.15 505.17 75.78
17 Beldar day 0.2 350.00 70.00
9999 Sundries L.S. 8.97 2 17.94
TOTAL 1425.59 W
Add 1 % Water charges on "W-A" 1366.39 13.6639
TOTAL X
Add GST (multiplying factor 0.1405) on "X-A" 1380.05 193.90
TOTAL Y
Add 15 % Contractor's profit and overheads on "Y- 1573.95 236.09
A" Z
Total 1810.04 18.10
Add Cess @ 1% on "Z-A" 1887.34
Cost for 17.5Kg. 107.85
Cost for 1 Kg. 107.90
Say 96.75

10.13.2 Fixing with carbon steel galvanised dash


fastener of required dia and size (to be paid for
separately)
Details of cost for 17.5Kg.

MATERIAL

Tee iron 40x40x6mm = 2m+2m+1m =

5 metres

5 metres @3.5Kg/m = 17.5kg.+ Add wastage @

5% = 0.87Kg.
Total = 18.37 kg. Say 0.18 qunital

1007 Structurals such as tees,angles channels and R.S. quintal 0.18 5300 954.00
joists
M.S. bars 10mm = 1x1m = 1 metre 1 metre @
0.60kg/m = 0.60Kg.+ Add wastage @ 5% =
0.03Kg.
Total = 0.63 Kg. Say = 0.006 qunital
1002 Mild steel round bar 12 mm dia and below quintal 0.006 5500 33.00
595 Bright finished or black enamelled mild steel butt 10 Nos 0.6 80 48.00
hinges 100x58x1.90 mm
9999 For screws and nuts and bolts L.S. 35.88 2 71.76
9999 For applying steel primer L.S. 17.94 2 35.88
9977 Carriage of material L.S. 5.33 2 10.66
LABOUR
13 Blacksmith 2nd class day 0.1 403.67 40.37
19 Fitter (grade 1) day 0.15 505.17 75.78
17 Beldar day 0.2 350.00 70.00
9999 Sundries L.S. 8.97 2 17.94
TOTAL 1357.39 W
Add 1 % Water charges on "W" 13.5739
TOTAL 1370.96 X
Add GST (multiplying factor 0.1405) on "X" 192.62
TOTAL 1563.58 Y
Add 15 % Contractor's profit and overheads on "Y" 234.54
Total 1798.12 Z
Add Cess @ 1% on "Z" 17.98
Cost for 17.5Kg. 1816.10
Cost for 1 Kg. 103.78
Say 103.80 92.7

Providing and fixing pressed steel door frames


10.14 conforming tofrom
IS: commercial
4351,
manufactured mild steel sheet of
1.60 mm thickness, including
hinges, jamb, lock jamb, bead and if required angle
threshold of mild steel angle
of section 50x25 mm, or base ties of 1.60 mm,
pressed mild steel
fixed together welded or rigidly
by mechanical means, including M.S.
pressed butt hinges 2.5 mm
thick with mortar guards, lock strike-plate and
shock
applyingabsorbers
a coat ofas specifiedsteel
approved and primer after pre-
treatment of the surface as
directed by Engineer-in-charge:
10.14.1 Profile B 0.00
10.14.1.1 Fixing with adjustable lugs with split end
tail to each jamb
Details of cost for 5 metre
MATERIAL
4006 Pressed steel door frames (mild steel sheet metre 5 190 950.00
1.60mm) Profile "B" frame =2+2+1m=5m
595 Bright finished or black enamelled mild steel butt 10 Nos 0.6 80 48.00
hinges 100x58x1.90 mm
9999 Screws, nuts and bolts L.S. 35.88 2 71.76
50x25x5mm. M.S. Angle for threshold 1 metre @
2.75kg per uds =2.75kg. Say 0.03q
1007 Structurals such as tees,angles channels and R.S. quintal 0.03 5300 159.00
joists
9977 Carriage of material L.S. 5.33 2 10.66
LABOUR
19 Fitter (grade 1) day 0.15 505.17 75.78
17 Beldar day 0.2 350.00 70.00
9999 Sundries L.S. 8.97 2 17.94
Steel primer
500x2(2x1.2+2x6.0+1x12.50cm)=2.69sqm
13.50.3 Rate as per item no 13.50.3 of SH : Finishing sqm 2.69 33.3 89.58 A
TOTAL 1492.72 W
Add 1 % Water charges on "W-A" 1403.14 14.0314
TOTAL X
Add GST (multiplying factor 0.1405) on "X-A" 1417.17 199.11
TOTAL Y
Add 15 % Contractor's profit and overheads on "Y- 1616.28 242.44
A" Z
Total 1858.72 18.59
Add Cess @ 1% on "Z-A" 1966.89
Cost for 5 metres 393.38
Cost for 1 metre 393.40
Say 385.05

10.14.1. Fixing with carbon steel galvanised dash fastener 0.00


2 of required dia and size (to be paid for separately)

Details of cost for 5 metre

MATERIAL
4006 Pressed steel door frames (mild steel sheet metre 5 190 950.00
1.60mm) Profile "B" frame =2+2+1m=5m
9999 Deduct sundries for not providing adjustable lugs L.S. -20 2 -40.00
595 Bright finished or black enamelled mild steel butt 10 Nos 0.6 80 48.00
hinges 100x58x1.90 mm
9999 Screws, nuts and bolts L.S. 35.88 2 71.76
50x25x5mm. M.S. Angle for threshold 1 metre @
2.75kg per uds =2.75kg. Say 0.03q
1007 Structurals such as tees,angles channels and R.S. quintal 0.03 5300 159.00
joists
9977 Carriage of material L.S. 5.33 2 10.66
LABOUR
19 Fitter (grade 1) day 0.15 505.17 75.78
17 Beldar day 0.2 350.00 70.00
9999 Sundries L.S. 8.97 2 17.94
Steel primer
500x2(2x1.2+2x6.0+1x12.50cm)=2.69sqm
13.50.3 Rate as per item no 13.50.3 of SH : Finishing sqm 2.69 33.3 89.58 A
TOTAL 1452.72 W
Add 1 % Water charges on "W-A" 1363.14 13.6314
TOTAL X
Add GST (multiplying factor 0.1405) on "X-A" 1376.77 193.44
TOTAL Y
Add 15 % Contractor's profit and overheads on "Y- 1570.21 235.53
A" Z
Total 1805.74 18.06
Add Cess @ 1% on "Z-A" 1913.38
Cost for 5 metres 382.68
Cost for 1metre 382.70
Say 374.3

10.14.2 Profile C 0.00

10.14.2.1 Fixing with adjustable lugs with split end


tail to each jamb

Details of cost for 5 metre

MATERIAL
4007 Pressed steel door frames (mild steel sheet metre 5 210 1050.00
1.60mm) Profile "C"
2+2+1m=5m
595 Bright finished or black enamelled mild steel butt 10 Nos 0.6 80 48.00
hinges 100x58x1.90 mm
9999 Screws, nuts and bolts L.S. 35.88 2 71.76
50x25x5mm. M.S. Angle for threshold 1 metre @ 0
2.75kg per uds =2.75kg. Say 0.03q
1007 Structurals such as tees,angles channels and R.S. quintal 0.03 5300 159.00
joists
9977 Carriage of material L.S. 5.33 2 10.66
LABOUR
19 Fitter (grade 1) day 0.15 505.17 75.78
17 Beldar day 0.2 350.00 70.00
9999 Sundries L.S. 8.97 2 17.94
Steel primer
500x2(2x1.2+2x6.0+1x12.50cm)=2.69sqm
13.50.3 Rate as per item no 13.50.3 of SH : Finishing sqm 2.69 33.3 89.58 A
TOTAL 1592.72 W
Add 1 % Water charges on "W-A" 1503.14 15.0314
TOTAL X
Add GST (multiplying factor 0.1405) on "X-A" 1518.17 213.30
TOTAL Y
Add 15 % Contractor's profit and overheads on "Y- 1731.47 259.72
A" Z
Total 1991.19 19.91
Add Cess @ 1% on "Z-A" 2100.68
Cost for 5 metres 420.14
Cost for 1metre 420.10
Say 411.8

10.14.2.2 Fixing with carbon steel galvanised dash


fastener of required dia and size (to be paid for
separately)
Details of cost for 5 metre

MATERIAL
4007 Pressed steel door frames (mild steel sheet metre 5 210 1050.00
1.60mm) Profile "C"
2+2+1m=5m
9999 Sundries for not providing adjustable lugs(-) L.S. -20 2 -40.00
595 Bright finished or black enamelled mild steel butt 10 Nos 0.6 80 48.00
hinges 100x58x1.90 mm
9999 Screws, nuts and bolts L.S. 35.88 2 71.76
50x25x5mm. M.S. Angle for threshold 1 metre @
2.75kg per uds =2.75kg. Say 0.03q
1007 Structurals such as tees,angles channels and R.S. quintal 0.03 5300 159.00
joists
9977 Carriage of material L.S. 5.33 2 10.66
LABOUR
19 Fitter (grade 1) day 0.15 505.17 75.78
17 Beldar day 0.2 350.00 70.00
9999 Sundries L.S. 8.97 2 17.94
Steel primer
500x2(2x1.2+2x6.0+1x12.50cm)=2.69sqm
13.50.3 Rate as per item no 13.50.3 of SH : Finishing sqm 2.69 33.3 89.58 A
TOTAL 1552.72 W
Add 1 % Water charges on "W-A" 1463.14 14.6314
TOTAL X
Add GST (multiplying factor 0.1405) on "X-A" 1477.77 207.63
TOTAL Y
Add 15 % Contractor's profit and overheads on "Y- 1685.40 252.81
A" Z
Total 1938.21 19.38
Add Cess @ 1% on "Z-A" 2047.17
Cost for 5 metres 409.43
Cost for 1metre 409.40
Say 401.1

10.14.3 Profile E
10.14.3.1 Fixing with adjustable lugs with split end
tail to each jamb
Details of cost for 5 metre
MATERIAL
4008 Pressed steel door frames (mild steel sheet metre 5 240 1200.00
1.60mm) Profile "E"
2+2+1m=5m
595 Bright finished or black enamelled mild steel butt 10 Nos 0.6 80 48.00
hinges 100x58x1.90 mm
9999 Screws, nuts and bolts L.S. 35.88 2 71.76
50x25x5mm. M.S. Angle for threshold 1 metre @
2.75kg per uds =2.75kg. Say 0.03q
1007 Structurals such as tees,angles channels and R.S. quintal 0.03 5300 159.00
joists
9977 Carriage of material L.S. 5.33 2 10.66
LABOUR
19 Fitter (grade 1) day 0.15 505.17 75.78
17 Beldar day 0.2 350.00 70.00
9999 Sundries L.S. 8.97 2 17.94
Steel primer
500x2(2x1.2+2x6.0+1x12.50cm)=2.69sqm
13.50.3 Rate as per item no 13.50.3 of SH : Finishing sqm 2.69 33.3 89.58 A
TOTAL 1742.72 W
Add 1 % Water charges on "W-A" 1653.14 16.5314
TOTAL X
Add GST (multiplying factor 0.1405) on "X-A" 1669.67 234.59
TOTAL Y
Add 15 % Contractor's profit and overheads on "Y- 1904.26 285.64
A" Z
Total 2189.90 21.90
Add Cess @ 1% on "Z-A" 2301.38
Cost for 5 metres 460.28
Cost for 1metre 460.30
Say 451.9

10.14.3. Fixing with carbon steel galvanised dash fastener


2 of required dia and size (to be paid for separately)

Details of cost for 5 metre

MATERIAL
4008 Pressed steel door frames (mild steel sheet metre 5 240 1200.00
1.60mm) Profile "E"
2+2+1m=5m
9999 Sundries for not providing adjustable lugs (-) L.S. -20 2 -40.00
595 Bright finished or black enamelled mild steel butt 10 Nos 0.6 80 48.00
hinges 100x58x1.90 mm
9999 Screws, nuts and bolts L.S. 35.88 2 71.76

50x25x5mm. M.S. Angle for threshold 1 metre @ 2.75kg per uds


=2.75kg. Say 0.03q
1007 Structurals such as tees,angles channels and R.S. quintal 0.03 5300 159.00
joists
9999 Carriage of material L.S. 5.33 2 10.66
LABOUR
19 Fitter (grade 1) day 0.15 505.17 75.78
17 Beldar day 0.2 350.00 70.00
9999 Sundries L.S. 8.97 2 17.94
Steel primer
500x2(2x1.2+2x6.0+1x12.50cm)=2.69sqm
13.50.3 Rate as per item no 13.50.3 of SH : Finishing sqm 2.69 33.3 89.58 A
TOTAL 1702.72 W
Add 1 % Water charges on "W-A" 1613.14 16.1314
TOTAL X
Add GST (multiplying factor 0.1405) on "X-A" 1629.27 228.91
TOTAL Y
Add 15 % Contractor's profit and overheads on "Y- 1858.18 278.73
A" Z
Total 2136.91 21.37
Add Cess @ 1% on "Z-A" 2247.86
Cost for 5 metres 449.57
Cost for 1metre 449.60
Say 441.2
10.15 Providing and fixing M.S. Tubular frames
for doors, windows, ventilators and cupboard with
rectangular/ L-Type sections, made of 1.60 mm
10.15.1
thick M.S.Fixing
Sheet,with 15x3
joints mm lugs
mitred, 10 cm
welded andlong
grinded
embedded
finish, with profiles of required size, including cm
in cement concrete block 15x10x10
of C.C.of1:3:6
fixing (1 Cement
necessary butt:hinges
3 coarse sand
and : 6 graded
screws and
20 mm
stone nominal
aggregate size)
applying a priming coat of approved steel primer.
Details of cost for 7.13Kg.
MATERIAL
L- section - 32x22x28mm 1.60mm thick 2.00+2.00+1.00 = 5.00 m
Width of MS sheet = 32+24.80+22+ 24.80+10mm = 113.60mm =
0.1136 m Area of MS sheet = 0.1136x5.00x 0.0016 = 0.0009088
sqm
Weight of Sheet = 0.0009088x7850 =
7.134 kg
Add wastage @ 5% = 0.357Kg.
Total = 7.491 kg Say 7.49 kg
4011 Mild steel tubes electric resistant or inductionbutt kilogra 7.49 47 352.03
welded m
M.S. bars 10mm = 1x1m = 1 metre 1 metre @
0.60kg/m = 0.60Kg.
Add wastage @ 5% = 0.03Kg.
Total = 0.63 Kg. Say = 0.006 qunital
1002 Mild steel round bar 12 mm dia and below quintal 0.006 5500 33.00
M.S. flat 15x3mm = 6x10cm = 0.60 metre 0.6 metre
@ 0.35kg/m = 0.21Kg Add wastage @ 5% = 0.01
Kg. Total = 0.22 kg = 0.002q
1008 Flats upto 10 mm in thickness quintal 0.002 4500 9.00
Cement concrete block 1:3:6- 6x15x
10x10cm= 0.009 cum

4.2.5 Rate as per item no 4.2.5 of SH : Concrete work cum 0.009 6451.00 58.06 A

595 Bright finished or black enamelled mild steel butt 10 Nos 0.6 80 48.00
hinges 100x58x1.90 mm
9999 For screws and nuts and bolts L.S. 35.88 2 71.76
9999 For applying steel primer L.S. 17.94 2 35.88
9977 Carriage of material L.S. 5.33 2 10.66
LABOUR 0
13 Blacksmith 2nd class day 0.04 403.67 16.15
19 Fitter (grade 1) day 0.06 505.17 30.31
17 Beldar day 0.08 350.00 28.00
9999 Sundries L.S. 3.64 2 7.28
TOTAL 700.13 W
Add 1 % Water charges on "W-A" 642.07 6.4207
TOTAL X
Add GST (multiplying factor 0.1405) on "X-A" 648.49 91.11
TOTAL Y
Add 15 % Contractor's profit and overheads on "Y- 739.60 110.94
A" Z
Total 850.54 8.51
Add Cess @ 1% on "Z-A" 917.11
Cost for 7.13Kg. 128.63
Cost for 1 Kg. 128.60
Say 126.65

10.15.2 Fixing with carbon steel galvanised dash


fastener of required dia and size (to be

paid for separately)

Details of cost for 7.13Kg.


MATERIAL
L- section - 32x22x28mm 1.60mm thick
2.00+2.00+1.00 = 5.00 m
Width of MS sheet = 32+24.80+22+24.80+
10mm = 113.60mm = 0.1136 m
Area of MS sheet = 0.1136x5.00x
0.0016 = 0.0009088 sqm
Weight of Sheet = 0.0009088x7850 =
7.134 kg
Add wastage @ 5% = 0.357Kg.
Total = 7.491 kg Say 7.49 kg
4011 Mild steel tubes electric resistant or inductionbutt kilogra 7.49 47 352.03
welded m
M.S. bars 10mm = 1x1m = 1 metre 1 metre @
0.60kg/m = 0.60Kg.
Add wastage @ 5% = 0.03Kg.
Total = 0.63 Kg. Say = 0.006 qunital
1002 Mild steel round bar 12 mm dia and below quintal 0.006 5500 33.00
595 Bright finished or black enamelled mild steel butt 10 Nos 0.6 80 48.00
hinges 100x58x1.90 mm
9999 For screws and nuts and bolts L.S. 35.88 2 71.76
9999 For applying steel primer L.S. 17.94 2 35.88
9977 Carriage of material L.S. 5.33 2 10.66
LABOUR
13 Blacksmith 2nd class day 0.04 403.67 16.15
19 Fitter (grade 1) day 0.06 505.17 30.31
17 Beldar day 0.08 350.00 28.00
9999 Sundries L.S. 3.64 2 7.28
TOTAL 633.07 W
Add 1 % Water charges on "W" 6.3307
TOTAL 639.40 X
Add GST (multiplying factor 0.1405) on "X" 89.84
TOTAL 729.24 Y
Add 15 % Contractor's profit and overheads on "Y" 109.39
Total 838.63 Z
Add Cess @ 1% on "Z" 8.39
Cost for 7.13Kg. 847.02
Cost for 1 Kg. 118.8
Say 118.80 116.7
Steel work in built up tubular (round, square or
rectangular hollow tubes etc.) trusses etc.,
including cutting, hoisting, fixing in position and
10.16
applying a priming coat of approved steel primer,
including welding and bolted with special shaped
washers etc. complete.
10.16.1 Hot finished welded type tubes
Details of cost for a truss of span 8 metre weight = 119 kg.
MATERIAL
50mm dia. tube
Tie beam-1x8.0m = 8.00m+
Principal rafter 2x4.30m = 8.60m
Total = 16.60m
16.60m @ 5.10kg./m = 84.66kg.
40mm dia. tube
Members = 2(0.45+1.25+0.90+2.15)
Total = 2x4.75=9.50m
9.50m @ 3.61kg/m = 34.60Kg. Total = 118.96kg.
Add wastage @ 5% = 5.94Kg.
Total = 124.90Kg. Say 125 kg
4009 Mild steel tubes hot finished welded type kilo 125 57 7125.00
gram
2205 Carriage of Steel tonne 0.125 94.34 11.79
Priming coat
50mm dia. tube 16.60x0.157m = 1.61sqm.
40mm dia. tube 9.50x0.125m = 1.91 sqm.
Total = 2.80 sqm.
13.50.3 Rate as per item no 13.50.3 of sqm 2.8 33.3 93.24 A
SH : Finishing
Welding charges:-
Rafter:- 4x22/7x6.03 = 75.80cm.+
Ties:- 2x22/7x6.03=37.90cm.+
Members:- 2x4x2x22/7x4.83=242.87cm
Total= 356.57cm say 357cm
1215 Welding by electric plant cm 357 2 714.00
LABOUR
For cutting, assembling & erection
12 Blacksmith 1st class day 1.5 505.17 757.76
10 Bandhani day 0.75 350.00 262.50
17 Beldar day 5.5 350.00 1925.00
9999 Sundries L.S. 80.73 2 161.46
TOTAL 11050.75 W
Add 1 % Water charges on "W-A" 10957.51 109.5751
TOTAL X
Add GST (multiplying factor 0.1405) on "X-A" 11067.09 1554.93
TOTAL Y
Add 15 % Contractor's profit and overheads on "Y- 12622.02 1893.30
A" Z
Total 14515.32 145.15
Add Cess @ 1% on "Z-A" 14753.71
Cost for 119 Kg. 123.98
Cost for 1 Kg. 124.00
Say 121.45

10.16.2 Hot finished seamless type tubes

Details of cost for a truss of span 8 metre weight = 119 kg.


MATERIAL
50mm dia. tube
Tie beam- 1 x 8.0m = 8.00m +
Principal rafter 2x4.30m = 8.60m = 16.60m 16.60m
@ 5.10kg./ m = 84.66 kg. 40mm dia. tube
Members = 2(0.45+1.25+0.90+2.15)
Total= 2x 4.75 = 9.50m 9.50m @ 3.61kg/m =
34.60kg. Total = 118.96kg.
Add wastage @ 5% = 5.94kg.
Total=124.90kg. say 125 kg
4010 Mild steel tubes hot finished seamless type kilo 125 67 8375.00
gram
2205 Carriage of Steel tonne 0.125 94.34 11.79
Priming coat
50mm dia. tube 16.60x0.157 m = 1.61 sqm. 40mm
dia. tube 9.50x 10125m = 1.91 sqm. =2.80 sqm.
13.50.3 Rate as per item no 13.50.3 of sqm 2.8 33.3 93.24 A
SH : Finishing
Welding charges:-
Rafter:- 4x22/7x6.03 = 75.80cm.+
Ties :- 2x22/7x6.03=37.90cm.+
Members :- 2x4x2x22/7x4.83 = 242.87cm
Total= 356.57 cm say 357 cm
1215 Welding by electric plant cm 357 2 714.00
LABOUR
12 Blacksmith 1st class day 1.5 505.17 757.76
10 Bandhani day 0.75 350.00 262.50
17 Beldar day 5.5 350.00 1925.00
9999 Sundries L.S. 80.73 2 161.46
Total 12300.75 W
Add 1 % Water charges on "W-A" 12207.51 122.0751
TOTAL X
Add GST (multiplying factor 0.1405) on "X-A" 12329.59 1732.31
TOTAL Y
Add 15 % Contractor's profit and overheads on "Y- 14061.90 2109.28
A" Z
Total 16171.18 161.71
Add Cess @ 1% on "Z-A" 16426.13
Cost for 119 Kg. 138.03
Cost for 1 Kg. 138.00
Say 135.5

10.16.3 Electric resistance or induction butt welded tubes


Details of cost for a truss of span 8 metre weight = 119 kg.
MATERIAL
50mm dia. tube
Tie beam-1x8.0m = 8.00m+
Principal rafter 2x4.30m = 8.60m
Total = 16.60m
16.60m @ 5.10kg./m = 84.66kg. 40mm dia. tube
Members = 2(0.45+1.25+0.90+2.15)
Total = 2x4.75=9.50m
9.50m @ 3.61kg/m = 34.60Kg. Total = 118.96kg.
Add wastage @ 5% = 5.94Kg.
Total = 124.90Kg. say 125 kg
4011 Mild steel tubes electric resistant or inductionbutt kilogra 125 47 5875.00
welded m
2205 Carriage of Steel tonne 0.125 94.34 11.79
Priming coat
50mm dia. tube 16.60x0.157m = 1.61sqm.
40mm dia. tube 9.50x0.125m = 1.91 sqm.
Total = 2.80 sqm.
13.50.3 Rate as per item no 13.50.3 of sqm 2.8 33.3 93.24 A
SH : Finishing
Welding charges:-
Rafter:- 4x22/7x6.03 = 75.80cm.+
Ties:- 2x22/7x6.03=37.90cm.+
Members:- 2x4x2x22/7x4.83=242.87cm
Total= 356.57cm say 357cm
1215 Welding by electric plant cm 357 2 714.00
LABOUR
12 Blacksmith 1st class day 1.5 505.17 757.76
10 Bandhani day 0.75 350.00 262.50
17 Beldar day 5.5 350.00 1925.00
9999 Sundries L.S. 80.73 2 161.46
TOTAL 9800.75 W
Add 1 % Water charges on "W-A" 9845.51 98.4551
TOTAL X
Add GST (multiplying factor 0.1405) on "X-A" 9943.97 1397.13
TOTAL Y
Add 15 % Contractor's profit and overheads on "Y- 11341.10 1701.16
Total Z
Add Cess @ 1% on "Z-A" 13042.26 130.42
Cost for 119 Kg. 13127.92
Cost for 1 Kg. 110.32
Say 110.30 107.4
10.17 Providing and fixing M.S. fan clamp type I
or II of 16 mm dia M.S. bar, bent to shape with
hooked ends in R.C.C. slabs or beams during
laying, including
painting the exposed portion of loop, all as per
standard design complete.

Details of cost for 1 clamp

MATERIAL
16mm dia. M.S. bar 1m @ 1.58 kg/m
1x1.58 = 1.58Kg+
Add wastage @ 5% = 0.08 Kg.
Total = 1.66 Kg.
Say 1.70kg. or 0.017q
1003 Mild steel round bar above 12 mm dia quintal 0.017 5500 93.50
LABOUR
13 Blacksmith 2nd class day 0.04 403.67 16.15
17 Beldar day 0.04 350.00 14.00
9988 Sundries (Carriage, fixing and painting etc.) L.S. 1.82 2 3.64
TOTAL 127.29 W
Add 1 % Water charges on "W" 1.2729
TOTAL 128.56 X
Add GST (multiplying factor 0.1405) on "X" 18.06
TOTAL 146.62 Y
Add 15 % Contractor's profit and overheads on "Y" 21.99
Total 168.61 Z
Add Cess @ 1% on "Z" 1.69
10.18
Cost for 1Providing
clamp and fixing circular/ Hexagonal 170.30
cast
Say
iron or M.S. sheet box for ceiling fan clamp, of 170.3 142.15
internal dia 140 mm, 73 mm height, top lid of 1.5
mm thick M.S. sheet with its top surface hacked for 170.30
proper bonding, top lid shall be screwed into the
cast iron/ M.S. sheet box by means of 3.3 mm dia
round headed screws, one lock at the corners.
Details of cost of one box clamp
Clamp shall be made of 12 mm dia M.S. bar bent to
shape as per standard drawing.
MATERIAL
4012 Circular C.I. Box for ceiling fan each 1 95 95.00
12mm dia. M.S. bar 80cm @
0.9kg/m = 0.72kg+
Add wastage @ 5% = 0.036
Total = 0.756 kg. Say 0.008 q
1002 Mild steel round bar 12 mm dia and below quintal 0.008 5500 44.00
LABOUR
13 Blacksmith 2nd class day 0.03 403.67 12.11
17 Beldar day 0.03 350.00 10.50
9988 Sundries (Carriage, fixing and painting etc.) L.S. 1.82 2 3.64
TOTAL 165.25 W
Add 1 % Water charges on "W" 1.6525
TOTAL 166.90 X
Add GST (multiplying factor 0.1405) on "X" 23.45
TOTAL 190.35 Y
Add 15 % Contractor's profit and overheads on "Y" 28.55
Total 218.90 Z
Add Cess @ 1% on "Z" 2.19
Cost for 1 box clamp 221.09
Say 221.09 150.5
221.10
Providing and fixing mild steel round holding down
10.19
bolts with nuts and washer

plates complete.

Details of cost for one bolt 16mm dia. and 1200mm long.

MATERIAL
l .2m @ 1.58kg/m = 1.895 kg = 0.019q
1035 Bolts and nuts above 300 mm in length Plate- quintal 0.019 6500 123.50
100x100x6mm @ 47kg/sqm. Wt. = 0.47kg. =
0.005q
1010 Mild steel plates quintal 0.005 5300 26.50
LABOUR
13 Blacksmith 2nd class day 0.03 403.67 12.11
9988 Carriage and labour for fixing L.S. 4.55 2 9.10
TOTAL 171.21 W
Add 1 % Water charges on "W" 1.7121
TOTAL 172.92 X
Add GST (multiplying factor 0.1405) on "X" 24.30
TOTAL 197.22 Y
Add 15 % Contractor's profit and overheads on "Y" 29.58
Total 226.80 Z
Add Cess @ 1% on "Z" 2.27
Cost of 0.024q 229.07
Cost of 1 kg. 95.45
Say 95.50 78.75

10.20 Providing and fixing bolts including nuts


and washers complete.

Details of cost for 0.10q of nuts and washers


MATERIAL
1034 Bolts and nuts upto 300 mm in length quintal 0.1 6800 680.00
2205 Carriage of Steel tonne 0.01 94.34 0.94
LABOUR
13 Blacksmith 2nd class day 0.38 403.67 153.39
17 Beldar day 0.38 350.00 133.00
9999 Sundries L.S. 4.55 2 9.10
TOTAL 976.43 W
Add 1 % Water charges on "W" 9.7643
TOTAL 986.19 X
Add GST (multiplying factor 0.1405) on "X" 138.56
TOTAL 1124.75 Y
Add 15 % Contractor's profit and overheads on "Y" 168.71
Total 1293.46 Z
Add Cess @ 1% on "Z" 12.93
Cost of 0.10q 1306.39
Cost of 1 kg. 130.64
Say 130.60 100.9

10.21 Providing and fixing M.S. rivets of sizes in


position.

Details of cost for 0.10q of rivets

MATERIAL
1020 Mild steel rivets quintal 0.1 5000 500.00
2205 Carriage of Steel tonne 0.01 94.34 0.94
LABOUR
19 Fitter (grade 1) day 0.83 505.17 419.29
37 Skilled Beldar (for floor rubbing etc.) day 0.83 350.00 290.50
9999 Sundries L.S. 10.79 2 21.58
TOTAL 1232.31 W
Add 1 % Water charges on "W" 12.3231
TOTAL 1244.63 X
Add GST (multiplying factor 0.1405) on "X" 174.87
TOTAL 1419.50 Y
Add 15 % Contractor's profit and overheads on "Y" 212.93
Total 1632.43 Z
Add Cess @ 1% on "Z" 16.32
Cost of 0.10q 1648.75
Cost of 1 kg. 164.88 158.4
Say 164.90

10.22 Welding by gas or electric plant including


transportation of plant at site etc.

complete.

Details of cost for one cm.


1214 Welding by gas plant cm 1 2 2.00
including transportation of welding plant at site etc.
complete
9999 Sundries L.S. 0.26 2 0.52
TOTAL 2.52 W
Add 1 % Water charges on "W" 0.0252
TOTAL 2.55 X
Add GST (multiplying factor 0.1405) on "X" 0.36
TOTAL 2.91 Y
Add 15 % Contractor's profit and overheads on "Y" 0.44
Total 3.35 Z
Add Cess @ 1% on "Z" 0.03
Cost of 1cm. 3.38
Total 3.38 3.35
Say 3.40
10.25 Steel work welded in built up sections/
framed work, including cutting, hoisting, fixing in
position and applying a priming coat of approved
steel primer using
structural steel etc. as required.
10.25.1 In stringers, treads, landings etc. of stair
cases, including use of chequered plate wherever
required, all complete
Detail of cost for 5.331 Qtls.

Consider a flight of staircase of 2.8m height with tread and


riser of 200mm & 0.60m wide.

MATERIAL
(i) Unequal angles as stringers-75x50x6mm
4x12.69x5.6 = 284.25 Kg.
Add wastage @ 5% = 14.21 Kg.
Total = 298.46kg. Say 2.985q
(ii) unequal angles at sides -50x30x5mm
2x14x0.2x3.00=16.8kg.
Add wastage @ 5% = 0.84kg.
Total = 17.64 kg. Say 0.176q
Total = 3.161q
1007 Structurals such as tees,angles channels and R.S. quintal 3.161 5300 16753.30
joists
(iii) plate for tread 8mm thick
14x7.5 = 105.00kg+
Add wastage @ 5% = 5.25kg.
Total = 110.25kg. Say 1.103q
1010 Mild steel plates quintal 1.103 5300 5845.90
(iv) G.I. pipe for rolling 40mm
2x12.69m = 25.38m+
Add wastage @ 5% = 1.27m
Total = 26.65m
1549 G.I. pipes 40 mm dia metre 26.65 250 6662.50
(v) M.S. round bars 16mm dia. 15x0.75x2x1.58 =
35.55kg.+ Add wastage @ 5% = 1.78kg.
Total = 37.33 Kg. Say 0.373q
1003 Mild steel round bar above 12 mm dia quintal 0.373 5500 2051.50
2205 Carriage of Steel tonne 0.4637 94.34 43.75
(3.I61 + 1.103+0.373)=4.637q = 0.4637 tonne
2271 Carriage of G.I. pipes below 100 mm dia approx. tonne 0.0991 94.34 9.35
wt. 3.72x26.65=99.14kg = 0.0991q.
1215 Welding by electric plant cm 2320 2 4640.00
23.20 m = 2320cm
LABOUR
12 Blacksmith 1st class day 1.85 505.17 934.56
17 Beldar day 1.25 350.00 437.50
10 Bandhani day 0.6 350.00 210.00
Applying priming coat
(i) steps 2.4x14 = 33.60sqm.+

(ii) angles-4x12.69x0.25 = 12.69sqm.+

(iii) Bars and other components =

2.00 sqm. (L.S.)


Total = 48.29 sqm
13.50.3 Rate as per item no 13.50.3 of SH : Finishing sqm 48.29 33.3 1608.06 A
9999 Sundries L.S. 110.89 2 221.78
TOTAL 39418.20 W
Add 1 % Water charges on "W-A" 37810.14 378.1014
TOTAL X
Add GST (multiplying factor 0.1405) on "X-A" 38188.24 5365.45
TOTAL Y
Add 15 % Contractor's profit and overheads on "Y-A" 43553.69 6533.05
Total Z
Add Cess @ 1% on "Z-A" 50086.74 500.87
Cost of 5.331 qunital 52195.67
Cost per kg. 97.91
Say 97.90 89.65

In gratings, frames, guard bar, ladder, railings,


10.25.2 brackets, gates and similar works
Details of 1mx1m framed guard bar grating.
MATERIAL
(i) M.S. flat 50x6mm 2.4kg/per metre
5.75x2.40 = 13.8kg.+
Add wastage @ 5% = 0.69kg.
Total = 14.49kg. Say 14.5 kg.
1008 Flats upto 10 mm in thickness quintal 0.145 5500 797.50
(ii) 12mm dia. bars @ 0.89 kg/m 9x1= 9metre @
0.89kg/m = 8.01kg+ Add wastage @ 5% = 0.40kg.
Total = 8.41 kg. Say 0.084q
1002 Mild steel round bar 12 mm dia and below quintal 0.084 5500 462.00
2205 Carriage of Steel tonne 0.0229 94.34 2.16
1215 Welding by electric plant cm 60 2 120.00
60 cm
LABOUR
12 Blacksmith 1st class day 0.7 505.17 353.62
17 Beldar day 0.5 350.00 175.00
10 Bandhani day 0.25 350.00 87.50
Applying priming coat 0.6 sqm.
13.50.3 Rate as per item no 13.50.3 of SH : Finishing sqm 0.6 33.3 19.98 A
9999 Sundries L.S. 4.55 2 9.10
TOTAL 2026.86 W
Add 1 % Water charges on "W-A" 2006.88 20.0688
TOTAL X
Add GST (multiplying factor 0.1405) on "X-A" 2026.95 284.79
TOTAL Y
Add 15 % Contractor's profit and overheads on "Y-A" 2311.74 346.76
Total Z
Add Cess @ 1% on "Z-A" 2658.50 26.58
Cost of 0.218 qunital 2705.06
Cost per kg 124.09
Say 124.10 107.45

10.26 Providing and fixing hand rail of approved


size by welding etc. to steel ladder railing, balcony
railing, staircase railing and similar works,
including applying priming coat of approved steel
primer.
10.26.1 M.S. tube 0.00

Detail of cost for 19.49 Kg.

Details of cost for hand rail of railing of two flights of staircase,


length of hand rail = 5.40m

MATERIAL
M.S. tube 40mm nominal bore (medium) =
5.40m @ 3.6lkg/m= 19.49kg
Add wastage @ 5% = 0.97 kg
Total = 20.46 kg
4009 Mild steel tubes hot finished welded type kilo 20.46 57 1166.22
gram
2205 Carriage of Steel tonne 0.0205 94.34 1.93
20.46kg = 0.205q
Priming coat 40mm dia.Tube
5.4x22/7x0.0483 = 0.82 sqm
13.50.3 Rate as per item no 13.50.3 of SH : Finishing sqm 0.82 33.3 27.31 A
1215 Welding by electric plant cm 72 2 144.00
(joints of hand rail and ballustards)
18x4x1.00 = 72cm
Labour for cutting assembling & erection
LABOUR
12 Blacksmith 1st class day 0.24 505.17 121.24
17 Beldar day 0.9 350.00 315.00
10 Bandhani day 0.12 350.00 42.00
9999 Sundries L.S. 12.48 2 24.96
TOTAL 1842.66 W
Add 1 % Water charges on "W-A" 1815.35 18.1535
TOTAL X
Add GST (multiplying factor 0.1405) on "X-A" 1833.50 257.61
TOTAL Y
Add 15 % Contractor's profit and overheads on "Y-A" 2091.11 313.67
Total Z
Add Cess @ 1% on "Z-A" 2404.78 24.05
Cost of 19.49 Kg. 2456.14
Cost per 1 kg. 138.69
Say 138.70 123.5

10.26.2 E.R.W. tubes 0.00


Detail of cost for 17.71 Kg.
Details of cost for hand rail of railing of two flights of staircase,
length of hand rail =5.40m
MATERIAL
E.R.W. tube 40mm nominal bore =
5.40m @
3.28kg/m= 17.71kg
Add wastage @ 5% = 0.88 kg
Total = 18.59 kg
4011 Mild steel tubes electric resistant or inductionbutt kilogra 18.59 47 873.73
welded m
2205 Carriage of Steel tonne 0.0186 94.34 1.75
18.59kg = 0.0186q
Priming coat 40mm dia.Tube
5.4x22/7x0.0483 = 0.82 sqm
13.50.3 Rate as per item no 13.50.3 of SH : Finishing sqm 0.82 33.3 27.31 A

1215 Welding by electric plant cm 72 2 144.00


(joints of hand rail and ballustards)
18x4x1.00 = 72cm
Labour for cutting assembling & erection
LABOUR
12 Blacksmith 1st class day 0.24 505.17 121.24
17 Beldar day 0.9 350.00 315.00
10 Bandhani day 0.12 350.00 42.00
9999 Sundries L.S. 12.48 2 24.96
TOTAL 1549.99 W
Add 1 % Water charges on "W-A" 1522.68 15.2268
TOTAL X
Add GST (multiplying factor 0.1405) on "X-A" 1537.91 216.08
TOTAL Y
Add 15 % Contractor's profit and overheads on "Y-A" 1753.99 263.10
Total Z
Add Cess @ 1% on "Z-A" 2017.09 20.17
Cost of 17.71 Kg. 2064.57
Cost per 1 kg. 116.58
Say 116.60 113.8

10.26.3 G.I. pipes


Details of cost for hand rail of railing of two flights
of staircase, length of hand rail =
5.40m i.e. 20.09 kg
MATERIAL
G.I. pipe 40mm nominal bore = 5.40m
Add wastage @ 5% = 0.27m
Total = 5.67m
1549 G.I. pipes 40 mm dia metre 5.67 250 1417.50
2271 Carriage of G.I. pipes below 100 mm dia tonne 0.0211 94.34 1.99
(5.67m @ 3.72 kg/m = 21.09kg)
Priming coat 40mm dia.Tube
5.4x22/7x0.0483 = 0.82 sqm
13.50.3 Rate as per item no 13.50.3 of SH : Finishing sqm 0.82 33.3 27.31 A
1215 Welding by electric plant cm 72 2 144.00
(joints of hand rail and ballustards)
18x4x1.00 = 72cm
LABOUR
Labour for cutting assembling & erection
12 Blacksmith 1st class day 0.24 505.17 121.24
17 Beldar day 0.9 350.00 315.00
10 Bandhani day 0.12 350.00 42.00
9999 Sundries L.S. 12.48 2 24.96
TOTAL 2094.00
Add 1 % Water charges on "W-A" 66.96 0.6696
TOTAL X
Add GST (multiplying factor 0.1405) on "X-A" 67.63 9.50
TOTAL Y
Add 15 % Contractor's profit and overheads on "Y-A" 77.13 11.57
Total Z
Add Cess @ 1% on "Z-A"
Cost of 20.09 Kg. 88.70 0.89
Cost per 1 kg. 2116.63
10.27 Providing and fixing carbon steel
galvanised ( minimum coating 5 micron) dash
Say 2116.63 136.55
fastener of 10 mm dia double threaded 6.8 grade 2116.60
(yield strength 480 N/mm2), counter sunk head,
comprising of 10 m dia polyamide PA 6 grade
sleeve, including drilling of hole in frame ,
10.27.1 concrete/
10 x 60 mm masonry, etc. as per direction of 0.00
Engineer-in-charge.
Details of cost for 10 nos.
MATERIAL
2506 Carben Steel galvanised dash fastner (min 5 10 nos 1 260 260.00
micron) of 10 mm dia double threaded 6.8 grade
counter sunk head screw comprising of 10 mm dia
polyamide PA 6 grade
sleave. Size 10mm x 60mm
LABOUR
24 Mason (brick layer) 2nd class day 0.4 403.67 161.47
17 Beldar day 0.4 350.00 140.00
9977 Sundries for carriage of material L.S. 10 2 20.00
TOTAL 581.47 W
Add 1 % Water charges on "W" 5.8147
TOTAL 587.28 X
Add GST (multiplying factor 0.1405) on "X" 82.51
TOTAL 669.79 Y
Add 15 % Contractor's profit and overheads on "Y" 100.47
Total 770.26 Z
Add Cess @ 1% on "Z" 7.70
Cost of 10 Nos. 777.96
Cost of 1 no 77.8
Say 77.80 74.65
10.27.2 10 x 80 mm
Details of cost for 10 nos.
MATERIAL
2507 Carben Steel galvanised dash fastner (min 5 10 nos 1 300 300.00
micron) of 10 mm dia double threaded 6.8 grade
counter sunk head screw comprising of 10 mm dia
polyamide PA 6 grade
sleave. Size 10mm x 80mm
LABOUR
24 Mason (brick layer) 2nd class day 0.4 403.67 161.47
17 Beldar day 0.4 350.00 140.00
9977 Sundries for carriage of material L.S. 10 2 20.00
TOTAL 621.47 W
Add 1 % Water charges on "W" 6.2147
TOTAL 627.68 X
Add GST (multiplying factor 0.1405) on "X" 88.19
TOTAL 715.87 Y
Add 15 % Contractor's profit and overheads on "Y" 107.38
Total 823.25 Z
Add Cess @ 1% on "Z" 8.23
Cost of 10 Nos. 831.48
Cost of 1 no 83.15
Say 83.20 80.05

10.27.3 10 x 120 mm
Details of cost for 10 nos.
MATERIAL
2508 Carben Steel galvanised dash fastner (min 5 10 nos 1 365 365.00
micron) of 10 mm dia double threaded 6.8 grade
counter sunk head screw comprising of 10 mm dia
polyamide PA 6 grade
sleave. Size 10mm x 120mm
LABOUR
24 Mason (brick layer) 2nd class day 0.5 403.67 201.84
17 Beldar day 0.5 350.00 175.00
9977 Sundries for carriage of material L.S. 10 2 20.00
TOTAL 761.84 W
Add 1 % Water charges on "W" 7.6184
TOTAL 769.46 X
Add GST (multiplying factor 0.1405) on "X" 108.11
TOTAL 877.57 Y
Add 15 % Contractor's profit and overheads on "Y" 131.64
Total 1009.21 Z
Add Cess @ 1% on "Z" 10.09
Cost of 10 Nos. 1019.30
Cost of 1 no 101.93
Say 101.90 98.05

10.27.4 10 x 140 mm 0.00

Details of cost for 10 nos.

MATERIAL
2509 Carben Steel galvanised dash fastner (min 5 10 nos 1 450 450.00
micron) of 10 mm dia double threaded 6.8 grade
counter sunk head screw comprising of 10 mm dia
polyamide PA 6 grade
sleave. Size 10mm x 140mm
LABOUR
24 Mason (brick layer) 2nd class day 0.5 403.67 201.84
17 Beldar day 0.5 350.00 175.00
9977 Sundries for carriage of material L.S. 10 2 20.00
TOTAL 846.84 W
Add 1 % Water charges on "W" 8.4684
TOTAL 855.31 X
Add GST (multiplying factor 0.1405) on "X" 120.17
TOTAL 975.48 Y
Add 15 % Contractor's profit and overheads on "Y" 146.32
Total 1121.80 Z
Add Cess @ 1% on "Z" 11.22
Cost of 10 Nos. 1133.02
Cost of 1 no 113.3
Say 113.30 109.4
10.27.5 10 x 160 mm
Details of cost for 10 nos.
MATERIAL
2510 Carben Steel galvanised dash fastner (min 5 10 nos 1 575 575.00
micron) of 10 mm dia double threaded 6.8 grade
counter sunk head screw comprising of 10 mm dia
polyamide PA 6 grade sleave. Size 10mm x 160mm
LABOUR
24 Mason (brick layer) 2nd class day 0.6 403.67 242.20
17 Beldar day 0.6 350.00 210.00
9977 Sundries for Carriage of material L.S. 10 2 20.00
TOTAL 1047.20 W
Add 1 % Water charges on "W" 10.472
TOTAL 1057.67 X
Add GST (multiplying factor 0.1405) on "X" 148.60
TOTAL 1206.27 Y
Add 15 % Contractor's profit and overheads on "Y" 180.94
Total 1387.21 Z
10.28
Add CessProviding
@ 1% on "Z" and fixing stainless steel ( Grade 13.87
304) railing
Cost of 10 Nos.made of Hollow tubes, channels, plates 1401.08
etc., including welding, grinding, buffing, polishing
Cost of 1 no
and making curvature (wherever required) and 140.11
fitting the same with necessary stainless steel nuts
Say 140.10 135.45
and bolts complete, i/c fixing the railing with
necessary accessories & stainless steel dash
fasteners , stainless steel bolts etc., of required
size, on the top of the floor or the side of waist slab
with
bolts,suitable
fastenersarrangement
etc.). as per approval of
Engineer-in-charge, (for payment purpose only
weight of stainless steel members shall be
Details of cost for 2kg
considered excluding fixing accessories such as
MATERIAL
nuts,
Qty= 2kg +
Add wastage @ 5% = 0.10
Total = 2.1 kg
4001 Stainless steel (Grade-304)hollow section kg 2.1 220 462.00
round/square tubes
4002 Stainless steel bolts/square bar and plates kg 1 115 115.00
LABOUR
for fabrication, assembling, errection, welding, curva
12 Blacksmith 1st class day 0.06 505.17 30.31
17 Beldar day 0.2 350.00 70.00
10 Bandhani day 0.02 350.00 7.00
9999 Welding of stainless steel section L.S. 30 2 60.00
9999 Curvaturing, grinding, finishing, buffing L.S. 20 2 40.00
9999 Sundries for making good wall and floors L.S. 7.5 2 15.00
TOTAL 799.31 W
Add 1 % Water charges on "W" 7.9931
TOTAL 807.30 X
Add GST (multiplying factor 0.1405) on "X" 113.43
TOTAL 920.73 Y
Add 15 % Contractor's profit and overheads on "Y" 138.11
Total 1058.84 Z
Add Cess @ 1% on "Z" 10.59
Cost of 2 kg 1069.43
Cost of 1 kg. 534.72
Say 534.70 529.25

10.29 Providing & fixing fly proof wire gauze to


windows, clerestory windows & doors with M.S.
Flat 15x3 mm and nuts & bolts complete.
Galvanised M.S. Wire gauze with 0.63 mm dia wire
10.29.1 and 1.4 mm aperture on both sides 0.00
Details of cost for a window shutter

1.40x1.10=1.54 sqm
MATERIAL
Wire gauze 1.40x1.10=1.54 sqm
Add wastage @ 10 %=0.15 sqm
Total=1.69 sqm
7029 Galvanised wire mesh of average width of aperture sqm 1.69 250 422.50
1.4 mm and nominal dia. of wire 0.63 mm
9977 CARRIAGE L.S. 1.82 2 3.64
M.S. Flat 15x3=2x(1.40+1.10)=5.0 metre
Add wastage @ 5%=0.25 m
Total=5.25 m
5.25@0.35kg/m=1.84 kg
1008 Flats upto 10 mm in thickness quintal 0.0184 4500 82.80
9977 CARRIAGE LABOUR L.S. 1.82 2 3.64
13 Blacksmith 2nd class day 0.17 403.67 68.62
15 Carpenter 2nd class day 0.17 403.67 68.62
17 Beldar day 0.06 350.00 21.00
9999 Sundries L.S. 19.76 2 39.52
TOTAL 710.34 W
Add 1 % Water charges on "W" 7.1034
TOTAL 717.44 X
Add GST (multiplying factor 0.1405) on "X" 100.80
TOTAL 818.24 Y
Add 15 % Contractor's profit and overheads on "Y" 122.74
Total 940.98 Z
Add Cess @ 1% on "Z" 9.41
Cost of 1.54 sqm. 950.39
Cost of 1 sqm. 617.14
Say 617.10 607

10.29.2 Stainless steel (grade 304) wire gauze of


0.5 mm dia wire and 1.4 mm aperture on both sides
Details of cost for a window shutter
1.40x1.10=1.54 sqm
MATERIAL
Wire gauze 1.40x1.10=1.54 sqm Add wastage @
10 %=0.15 sqm
Total=1.69 sqm
8737 Stainless steel wire guage (Grade-304) aperture sqm 1.69 400 676.00
1.4mm and 0.50 mm dia wire
9977 CARRIAGE L.S. 1.82 2 3.64
M.S. Flat 15x3=2x(1.40+1.10)=5.0 metre
Add wastage @ 5%=0.25 m
Total=5.25 m
5.25@0.35kg/m=1.84 kg
1008 Flats upto 10 mm in thickness quintal 0.0184 4500 82.80
9977 CARRIAGE L.S. 1.82 2 3.64
LABOUR
13 Blacksmith 2nd class day 0.17 403.67 68.62
15 Carpenter 2nd class day 0.17 403.67 68.62
17 Beldar day 0.06 350.00 21.00
9999 Sundries L.S. 19.76 2 39.52
TOTAL 963.84 W
Add 1 % Water charges on "W" 9.6384
TOTAL 973.48 X
Add GST (multiplying factor 0.1405) on "X" 136.77
TOTAL 1110.25 Y
Add 15 % Contractor's profit and overheads on "Y" 166.54
Total 1276.79 Z
Add Cess @ 1% on "Z" 12.77
Cost of 1.54 sqm. 1289.56
Cost of 1 sqm. 837.38
Say 837.40 827.25

10.30 Providing & fixing glass panes with putty


and glazing clips in steel doors, windows,
clerestory windows, all complete with :
10.30.1 4.0 mm thick glass panes
Details of cost for 10 glass panes

(area of each pane = 0.10 sqm)

MATERIAL

Area of glass panes =1.00 sqm +

Add wastage @ 10% = 0.10


Total =1.10 sqm
2406 Float glass sheet of nominal thickness 4 mm sqm 1.1 300 330.00
(weight not less than 10kg/sqm).
9977 CARRIAGE LABOUR L.S. 1.82 2 3.64
21 Glazier day 0.13 403.67 52.48
9999 Sundries, putty, glazing clips, scaffolding etc. L.S. 125.58 2 251.16
TOTAL 637.28 W
Add 1 % Water charges on "W" 6.3728
TOTAL 643.65 X
Add GST (multiplying factor 0.1405) on "X" 90.43
TOTAL 734.08 Y
Add 15 % Contractor's profit and overheads on "Y" 110.11
Total 844.19 Z
Add Cess @ 1% on "Z" 8.44
Total 852.63
Cost of 1.0 sqm 852.63
Say 852.60 847.55

5.5 mm thick glass panes


10.30.2
Details of cost for 10 glass panes
(area of each pane = 0.10 sqm)
MATERIAL
Area of glass panes =1.00 sqm +
Add wastage @ 10% = 0.10
Total =1.10 sqm
2407 Float glass sheet of nominal thickness sqm 1.1 500 550.00
5.5 mm.(weight not less than 13.50 kg/sqm).
9977 CARRIAGE L.S. 1.82 2 3.64
LABOUR
21 Glazier day 0.13 403.67 52.48
9999 Sundries, putty, glazing clips, scaffolding etc. L.S. 125.58 2 251.16
TOTAL 857.28 W
Add 1 % Water charges on "W" 8.5728
TOTAL 865.85 X
Add GST (multiplying factor 0.1405) on "X" 121.65
TOTAL 987.50 Y
Add 15 % Contractor's profit and overheads on "Y" 148.13
Total 1135.63 Z
Add Cess @ 1% on "Z" 11.36
Total 1146.99
10.31of 1.0
Cost Providing
sqm and fixing angle iron frames for 1146.99
doors, windows and ventilators of mild steel Angle
Say 1147.00 1141.9
sections of size 35x35x5 mm, joints mitred and
welded by angle iron 35x35x5 mm or 35x 5 mm flat
pieces to the existing T-iron frame or to the wall
with dash fastener, including fixing of necessary
butt hinges and screws and applying a priming
Details of cost for 17.50 kg
coat of approved steel primer, all complete as per
the direction of Engineer-In-charge.
MATERIAL
Angle/Tee iron 40x40x6 mm= 2+2+1 = 5 m 5
Meters @3.5 Kg/m = 17.5 Kg+ Add Wastage @5%
=0.87Kg.“Total =18.37 Kg.
Say 0.18 Quintal
1007 Structural steel such as tees, angles, channels and quintal 0.18 5300 954.00
R.S. Joists
1008 M.S. Flats 3x5 mm for fixing frame quintal 0.0037 4500 16.65
6x0.05= 0.3 Metre @1.18 Kg/m= 0.354 Kg
Add wastage @5% = 0.018 Kg Total=
0.37Kg. Say 0.0037
Qunital
1002 M.S. Bars 10mm =1x1 m = 1Metre 1 Metre quintal 0.006 5500 33.00
@0.60Kg/m =0.60Kg + Add wastage @5%
= 0.03 Kg.Total =0.63 Kg, say 0.006 Quintal
Mild steel round bars 10mm dia and below
9999 For applying steel primer L.S. 17.94 2 35.88
9999 Carriage of material L.S. 5.33 2 10.66
1215 Welding by electric plant cm 16 2 32.00
LABOUR
13 Blacksmith 2nd Class day 0.1 403.67 40.37
19 Fitter (Grade-I) day 0.15 505.17 75.78
17 Beldar day 0.2 350.00 70.00
9999 Sundries L.S. 8.97 2 17.94
TOTAL 1286.28 W
Add 1 % Water charges on "W" 12.8628
TOTAL 1299.14 X
Add GST (multiplying factor 0.1405) on "X" 182.53
TOTAL 1481.67 Y
Add 15 % Contractor's profit and overheads on "Y" 222.25
Total 1703.92 Z
Add Cess @ 1% on "Z" 17.04
Cost for 17.50 kg 1720.96 1526.78
Cost for 1.00 kg 98.34
98.30
SUB HEAD : 11.0

FLOORING
Code Description Unit Quantity Rate Amount

11.1 Brick on edge flooring with bricks of class


designation 7.5 on a bed of 12 mm cement
mortar, including filling the joints with same
mortar, with common burnt clay non modular
bricks:

11.1.1 1:4 (1 cement : 4 coarse sand)

Details of cost for 10 sqm.


MATERIAL
2602 Common burnt clay F.P.S. (non modular) bricks 1000 Nos 0.565 5000 2825.00
class designation 7.5
2201 Carriage of Bricks 1000 Nos 0.565 283.01 159.90
Cement mortar 1 : 4 (1 cement : 4 coarse sand)
3.9 Rate as per Item Number 3.9 of SH: Mortars cum 0.434 3548.00 1539.83
367 Portland Cement tonne 0.02 4375 87.50
2209 Carriage of Cement tonne 0.02 94.34 1.89
LABOUR
24 Mason (brick layer) 2nd class day 1.08 403.67 435.96
17 Beldar day 0.25 350.00 87.50
18 Coolie day 1.62 350.00 567.00
11 Bhisti day 0.27 350.00 94.50
TOTAL 5799.08
Add 1 % Water charges on "W" 57.9908
TOTAL 5857.07
Add GST (multiplying factor 0.1405) on "X" 822.92
TOTAL 6679.99
Add 15 % Contractor's profit and overheads on "Y" 1002.00
Total 7681.99
Add Cess @ 1% on "Z" 76.82
Cost of 10 sqm. 7758.81
Cost of 1 sqm. 775.88
Say 775.90

11.1.2 1:6 (1cement : 6 coarse sand)


Details of cost for 10 sqm.
MATERIAL
2602 Common burnt clay F.P.S. (non modular) bricks 1000 Nos 0.565 5000 2825.00
class designation 7.5
2201 Carriage of Bricks 1000 Nos 0.565 283.01 159.90
Cement mortar 1 : 6 (1 cement : 6 coarse sand)
3.11 Rate as per Item Number 3.11 of SH: Mortars cum 0.434 2967.00 1287.68
367 Portland Cement tonne 0.02 4375 87.50
2209 Carriage of Cement tonne 0.02 94.34 1.89
LABOUR
24 Mason (brick layer) 2nd class day 1.08 403.67 435.96
17 Beldar day 0.25 350.00 87.50
18 Coolie day 1.62 350.00 567.00
11 Bhisti day 0.27 350.00 94.50
TOTAL 5546.93
Add 1 % Water charges on "W" 55.4693
TOTAL 5602.40
Add GST (multiplying factor 0.1405) on "X" 787.14
TOTAL 6389.54
Add 15 % Contractor's profit and overheads on "Y" 958.43
Total 7347.97
Add Cess @ 1% on "Z" 73.48
Cost of 10 sqm. 7421.45
Cost of 1 sqm. 742.14
Say 742.10

11.2 Dry brick on edge flooring in required


pattern
commonwith bricks
burnt clayofnon
class designation
modular bricks.7.5
on a bed of 12 mm mud
Details of cost for 10 sqm.
mortar, including
filling joints with Sand, with
MATERIAL
2602 Common burnt clay F.P.S. (non modular) bricks 1000 Nos 0.645 5000 3225.00
class designation 7.5
2201 Carriage of Bricks 1000 Nos 0.645 283.01 182.54
983 Fine sand cum 0.15 850 127.50
2261 Carriage of Fine sand (1 part badarpur cum 0.15 106.13 15.92
sand : 2 parts Sand) Mud Mortar 0
3.18 Rate as per Item Number 3.18 of cum 0.15 521.90 78.29
SH: Mortars
LABOUR
24 Mason (brick layer) 2nd class day 0.9 403.67 363.30
18 Coolie day 1.98 350.00 693.00
11 Bhisti day 0.05 350.00 17.50
TOTAL 4703.05
Add 1 % Water charges on "W" 47.0305
TOTAL 4750.08
Add GST (multiplying factor 0.1405) on "X" 667.39
TOTAL 5417.47
Add 15 % Contractor's profit and overheads on "Y" 812.62
Total 6230.09
Add Cess @ 1% on "Z" 62.30
Cost of 10 sqm. 6292.39
Cost of 1 sqm. 629.24
Say 629.20

11.3 Cement concrete flooring 1:2:4 (1 cement :


11.3.1 2 coarse
40 mm sandthick :with
4 graded
20 mmstone aggregate)
nominal size
finished with
stone aggregate
Details
a floating
of cost for 10 sqm.
coat of neat cement,
including cement slurry, but excluding the
MATERIAL
295 Stone Aggregate (Single size) : 20 mm nominal s cum 0.267 800 213.60
297 Stone Aggregate (Single size) : 10 mm nominal s cum 0.089 810 72.09
2202 Carriage of Stone aggregate below 40 mm nomin cum 0.356 584.88 208.22
982 Coarse sand cum 0.178 800 142.40
2203 Carriage of Coarse sand cum 0.178 584.88 104.11
367 Portland Cement tonne 0.17 4375 743.75
2209 Carriage of Cement tonne 0.17 94.34 16.04
LABOUR 0
24 Mason (brick layer) 2nd class day 0.8 403.67 322.94
17 Beldar day 1.4 350.00 490.00
11 Bhisti day 1.04 350.00 364.00
27 Driver (for Road Roller, Concrete Mixer, Truck day 0.03 421.17 12.64
etc.)
2 Hire charges of Concrete Mixer 0.25 to day 0.03 800 24.00
0.40 cum with hooper
9999 Sundries L.S. 40.43 2 80.86
TOTAL 2794.65
Add 1 % Water charges on "W" 27.9465
TOTAL 2822.60
Add GST (multiplying factor 0.1405) on "X" 396.57
TOTAL 3219.17
Add 15 % Contractor's profit and overheads on "Y" 482.87
Total 3702.04
Add Cess @ 1% on "Z" 37.02
Cost of 10 sqm. 3739.06
Cost of 1 sqm. 373.91
Say 373.90

11.4 52 mm thick cement concrete flooring with


concrete hardener topping, under layer 40
mm thick cement concrete 1:2:4 (1 cement :
Details of cost for 10 sqm.
2 coarse sand : 4 graded stone aggregate 20
MATERIAL
295 Stone Aggregate (Single size) : 20 mm nominal cum 0.267 800 213.60
size
297 Stone Aggregate (Single size) : 10 mm nominal cum 0.089 810 72.09
size
2202 Carriage of Stone aggregate below 40 mm cum 0.356 584.88 208.22
nominal size
982 Coarse sand cum 0.178 800 142.40
2203 Carriage of Coarse sand cum 0.178 584.88 104.11
298 Stone Aggregate (Single size) : 06 mm nominal cum 0.115 825 94.88
size
2202 Carriage of Stone aggregate below 40 mm cum 0.115 584.88 67.26
nominal size
367 Portland Cement tonne 0.211 4375 923.13
367 Portland Cement tonne 0.02 4375 87.50
2209 Carriage of Cement tonne 0.231 94.34 21.79
7254 Hardening compound litre 2.44 38 92.72
9977 Carriage of hard crete L.S. 2.73 2 5.46
LABOUR
24 Mason (brick layer) 2nd class day 2.15 403.67 867.89
17 Beldar day 1.6 350.00 560.00
18 Coolie day 1.88 350.00 658.00
11 Bhisti day 0.27 350.00 94.50
9999 Sundries L.S. 53.82 2 107.64
TOTAL 4321.19
Add 1 % Water charges on "W" 43.2119
TOTAL 4364.40
Add GST (multiplying factor 0.1405) on "X" 613.20
TOTAL 4977.60
Add 15 % Contractor's profit and overheads on "Y" 746.64
Total 5724.24
Add Cess @ 1% on "Z" 57.24
Cost of 10 sqm. 5781.48
Cost of 1 sqm. 578.15
Say 578.20
11.5 62 mm thick cement concrete flooring with
concrete hardener topping, under layer 50
mm thick cement concrete 1:2:4 (1 cement :
Details of cost for 10 sqm.
2 coarse sand : 4 graded stone aggregate
MATERIAL
295 Stone Aggregate (Single size) : 20 mm nominal cum 0.334 800 267.20
size
297 Stone Aggregate (Single size) : 10 mm nominal cum 0.111 810 89.91
size
2202 Carriage of Stone aggregate below 40 mm cum 0.445 584.88 260.27
nominal size
982 Coarse sand cum 0.222 800 177.60
2203 Carriage of Coarse sand cum 0.222 584.88 129.84
298 Stone Aggregate (Single size) : 06 mm nominal cum 0.115 825 94.88
size
2202 Carriage of Stone aggregate below 40 mm cum 0.115 584.88 67.26
nominal size
367 Portland Cement tonne 0.243 4375 1063.13
367 Portland Cement tonne 0.02 4375 87.50
2209 Carriage of Cement tonne 0.263 94.34 24.81
7254 Hardening compound litre 2.44 38 92.72
9977 Carriage of Hardening compound L.S. 2.73 2 5.46
LABOUR
24 Mason (brick layer) 2nd class day 2.15 403.67 867.89
17 Beldar day 1.86 350.00 651.00
18 Coolie day 1.88 350.00 658.00
11 Bhisti day 0.27 350.00 94.50
9999 Sundries L.S. 53.82 2 107.64
TOTAL 4739.61
Add 1 % Water charges on "W" 47.3961
TOTAL 4787.01
Add GST (multiplying factor 0.1405) on "X" 672.57
TOTAL 5459.58
Add 15 % Contractor's profit and overheads on "Y" 818.94
Total 6278.52
Add Cess @ 1% on "Z" 62.79
Cost of 10 sqm. 6341.31
Cost of 1 sqm. 634.13
Say 634.10

11.6 Cement plaster skirting up to 30 cm


height, with cement mortar 1:3 (1 cement : 3
coarse sand), finished with a floating coat of
neat cement.
11.6.1 18 mm thick

Details of cost for 10 sqm.


MATERIAL
Cement mortar 1:3 = 0.205 cum+ Add for
rounding corners = 0.030 cum = 0.235 cum.
Cement mortar 1:3 (1 cement : 3 coarse sand)
3.8 Rate as per Item Number 3.8 of SH: Mortars cum 0.235 4129.00 970.32
367 Portland Cement tonne 0.02 4375 87.50
2209 Carriage of Cement tonne 0.02 94.34 1.89
LABOUR
24 Mason (brick layer) 2nd class day 1.88 403.67 758.90
18 Coolie day 1.88 350.00 658.00
11 Bhisti day 0.54 350.00 189.00
9999 Sundries L.S. 19.76 2 39.52
TOTAL 2705.13
Add 1 % Water charges on "W" 27.0513
TOTAL 2732.18
Add GST (multiplying factor 0.1405) on "X" 383.87
TOTAL 3116.05
Add 15 % Contractor's profit and overheads on "Y" 467.41
Total 3583.46
Add Cess @ 1% on "Z" 35.83
Cost of 10 sqm. 3619.29
Cost of 1 sqm. 361.93
Say 361.90

11.7 Cement concrete pavement with 1:2:4 (1


cement
Details of :cost
2 coarse sand : 4 graded stone
for one cum.
aggregate
MATERIAL
20 mm nominal size), including
finishing complete.
Cement concrete 1:2:4
4.1.3 Rate as per item No.4.1.3 of S.H.Concrete Work cum 1 5924.90 5924.90
Extra labour for laying in floors etc.
24 Mason (brick layer) 2nd class day 0.35 403.67 141.28
17 Beldar day 0.18 350.00 63.00
11 Bhisti day 0.05 350.00 17.50
9999 Sundries L.S. 19.76 2 39.52
TOTAL 6186.20
Add 1 % Water charges on "W-A" 261.30 2.613
TOTAL
Add GST (multiplying factor 0.1405) on "X-A" 263.91 37.08
TOTAL
Add 15 % Contractor's profit and overheads on 300.99 45.15
"Y-A"
Total 346.14 3.46
Add Cess @ 1% on "Z-A" 6274.50
Cost of 1 Cum. 6274.5
Say 6274.50

11.8 Extra for making chequers of approved


patternofon
Details costcement concrete floors, steps,
for 10 sqm.
landing,
LABOUR
pavements etc.
24 Mason (brick layer) 2nd class day 0.36 403.67 145.32
17 Beldar day 0.36 350.00 126.00
9999 Chequered plate etc. L.S. 13.52 2 27.04
TOTAL 298.36
Add 1 % Water charges on "W" 2.9836
TOTAL 301.34
Add GST (multiplying factor 0.1405) on "X" 42.34
TOTAL 343.68
Add 15 % Contractor's profit and overheads on "Y" 51.55
Total 395.23
Add Cess @ 1% on "Z" 3.95
Cost of 10 sqm. 399.18
Cost of 1 sqm. 39.92
Say 39.90

11.9 40 mm thick marble chips flooring


rubbed and polished to granolithic finish,
under layer 34 mm thick cement concrete
marble
1:2:4 (1chips)
cementby: volume,
2 coarseincluding
sand : 4 cement
graded
slurry etc. complete :
11.9.1 Dark shade pigment with ordinary
cement
Details of cost for 10 sqm.
MATERIAL
For under layer of 34mm thick
296 Stone Aggregate (Single size) : 12.5 mm cum 0.227 810 183.87
nominal size
297 Stone Aggregate (Single size) : 10 mm nominal cum 0.076 810 61.56
size
2202 Carriage of Stone aggregate below 40 mm cum 0.303 584.88 177.22
nominal size
982 Coarse sand cum 0.151 800 120.80
2203 Carriage of Coarse sand cum 0.151 584.88 88.32
367 Portland Cement tonne 0.109 4375 476.88
367 Portland Cement tonne 0.02 4375 87.50
2209 Carriage of Cement for top layer 6mm thick tonne 0.129 94.34 12.17
785 Marble chips upto 4mm and downsize White & quintal 0.872 189 164.81
black
2268 Carriage of Marble dust and marble chips cum 0.051 106.13 5.41
367 Portland Cement tonne 0.0405 4375 177.19
2209 Carriage of Cement tonne 0.0405 94.34 3.82
784 Marble dust/ powder cum 0.007 1130 7.91
874 Black colour dark shade pigment kilogram 2.84 70 198.80
3.5kg/ 50kg of cement
= 40.5x3.5/50=2.84kg
9977 Carriage of pigment & marble powder etc. L.S. 3.64 2 7.28
LABOUR
24 Mason (brick layer) 2nd class day 1.79 403.67 722.57
17 Beldar day 1.99 350.00 696.50
11 Bhisti day 1.04 350.00 364.00
37 Skilled Beldar (for floor rubbing etc.) day 1 350.00 350.00
27 Driver (for Road Roller, Concrete Mixer, Truck day 0.03 421.17 12.64
etc.)
2 Hire charges of Concrete Mixer 0.25 to day 0.03 800 24.00
0.40 cum with hooper
13 Machine for rubbing of floors day 1.6 300 480.00
9999 Sundries L.S. 161.46 2 322.92
Total 4746.17
Add 1 % Water charges on "W" 47.4617
TOTAL 4793.63
Add GST (multiplying factor 0.1405) on "X" 673.51
TOTAL 5467.14
Add 15 % Contractor's profit and overheads on "Y" 820.07
Total 6287.21
Add Cess @ 1% on "Z" 62.87
Cost of 10 sqm. 6350.08
Cost of 1 sqm. 635.01
Say 635.00

11.9.2 Light shade pigment with white cement


Details of cost for 10 sqm.
11.9.1 Rate as per item no 11.9.1 of SH: Flooring Add sqm 10 635.00 6350.00
difference of cost due to using light shade
pigment instead of dark shade pigment Add for
875 Red, chocolate, orange, buff or yellow kilogram 2.84 60 170.40
(red oxide of iron) light shade pigment Deduct 0
for
874 Black colour dark shade pigment kilogram -2.84 70 -198.80
Addd difference of cost due to using white
cement instead of grey cement Add for
368 White Cement Deduct for tonne 0.0405 11200 453.60
367 Portland Cement tonne -0.0405 4375 -177.19
Total 6598.01
Add 1 % Water charges on "W-A" 248.01 2.4801
TOTAL
Add GST (multiplying factor 0.1405) on "X-A" 250.49 35.19
TOTAL
Add 15 % Contractor's profit and overheads on "Y-A" 285.68 42.85
Total
Add Cess @ 1% on "Z-A" 328.53 3.29
Cost of 10 sqm 6681.82
Cost of 1 sqm 668.18
Say 668.20

11.9.3 Medium shade pigment with 50% white


cement
Details of and 50%
cost for ordinary cement
10 sqm.
11.9.1 Rate as per item no 11.9.1 of SH: Flooring Add sqm 10 635.00 6350.00
difference of cost due to using light shade
pigment instead of dark shade pigment Add for
876 Green or blue medium shade pigment Deduct kilogram 2.84 56 159.04
for
874 Black colour dark shade pigment kilogram -2.84 70 -198.80
Add difference of cost due to using white
cement instead of grey cement Add for
368 White Cement Deduct for tonne 0.0203 11200 227.36
367 Portland Cement tonne -0.0203 4375 -88.81
Total 6448.79
Add 1 % Water charges on "W-A" 98.79 0.9879
TOTAL
Add GST (multiplying factor 0.1405) on "X-A" 99.78 14.02
TOTAL
Add 15 % Contractor's profit and overheads on "Y-A" 113.80 17.07
Total
Add Cess @ 1% on "Z-A" 130.87 1.31
Cost of 10 sqm 6482.18
Cost of 1 sqm 648.22
Say 648.20

11.9.4 White cement without any pigment


Details of cost for 10 sqm.
MATERIAL
For under layer of 34mm thick
296 Stone Aggregate (Single size) : 12.5 mm cum 0.227 810 183.87
nominal size
297 Stone Aggregate (Single size) : 10 mm nominal cum 0.076 810 61.56
size
2202 Carriage of Stone aggregate below 40 mm cum 0.303 584.88 177.22
nominal size
982 Coarse sand cum 0.151 800 120.80
2203 Carriage of Coarse sand cum 0.151 584.88 88.32
367 Portland Cement tonne 0.109 4375 476.88
367 Portland Cement tonne 0.02 4375 87.50
2209 Carriage of Cement for top layer 6mm thick tonne 0.129 94.34 12.17
785 Marble chips upto 4mm and downsize White & quintal 0.958 189 181.06
black
2268 Carriage of Marble dust and marble chips cum 0.056 106.13 5.94
368 White Cement tonne 0.0405 11200 453.60
2209 Carriage of Cement tonne 0.0405 94.34 3.82
784 Marble dust/ powder cum 0.007 1130 7.91
LABOUR
24 Mason (brick layer) 2nd class day 1.79 403.67 803.30
17 Beldar day 1.99 0.00
11 Bhisti day 1.04 0.00
37 Skilled Beldar (for floor rubbing etc.) day 1 350.00 10.50
27 Driver (for Road Roller, Concrete Mixer, Truck day 0.03 421.17 12.64
etc.)
2 Hire charges of Concrete Mixer 0.25 to day 0.03 800 129168.00
0.40 cum with hooper
13 Machine for rubbing of floors day 1.6 300 #REF!
9999 Sundries L.S. 161.46 #REF!
Total
Add 1 % Water charges on "W"
TOTAL

Add GST (multiplying factor 0.1405) on "X"

TOTAL

Add 15 % Contractor's profit and overheads on "Y"

Total

Add Cess @ 1% on "Z"

Cost of 10 sqm

Cost of 1 sqm

Say

11.9.5 Light shade pigment with ordinary


cement
Details of cost for 10 sqm.
11.9.1 Rate as per item no 11.9.1 of SH: Flooring Add sqm 0.00
difference of cost due to using light shade
pigment instead of dark shade pigment Add for
875 Red, chocolate, orange, buff or yellow kilogram 60 0.00
(red oxide of iron) light shade pigment Deduct
for
874 Black colour dark shade pigment kilogram 0.00
Total
Add 1 % Water charges on "W-A" -28.4
TOTAL
Add GST (multiplying factor 0.1405) on "X-A" -28.68
TOTAL

Quantity Rate Amount


0.007 1130 7.91
1.79 403.67 722.57
1.99 350.00 696.50
1.04 350.00 364.00
1 350.00 350.00
0.03 392 11.76
0.03 800 24.00
1.6 300 480.00
161.46 2 322.92
4764.83 W 2979.66
47.65 29.7966
4812.48 X 3009.46
676.15 422.83
5488.63 Y 3432.29
823.29 514.84
6311.92 Z 3947.13
63.12 39.47
6375.04 3986.60
637.5 398.66
637.5 398.70
10 628.9 6289.00 A 0.00
2.84 60 170.4 0.00
-2.84 70 -198.80
6260.60 W
-0.28
6260.32 X
-4.03
6256.29 Y

Add 15 % Contractor's profit and overheads on -32.71 -4.91


"Y-A"
Total 6251.38
Add Cess @ 1% on "Z-A" -37.62 -0.38
Cost of 10 sqm 6251
Cost of 1 sqm 625.1
Say

11.9.6 Ordinary cement without any


pigment
Details of cost for 10 sqm.
11.9.1 Rate as per item no 11.9.1 of SH: Flooring sqm 10 635.00 6350.00
Less cost of dark shade pigment
Deduct for
874 Black colour dark shade pigment kilogram -2.84 70 -198.80
9999 Deduct for carriage of pigment L.S. -7.38 2 -14.76
Total 6136.44
Add 1 % Water charges on "W-A" -213.56 -2.1356
TOTAL
Add GST (multiplying factor 0.1405) on "X-A" -215.70 -30.31
TOTAL
Add 15 % Contractor's profit and overheads on -246.01 -36.90
"Y-A"
Total -282.91 -2.83
Add Cess @ 1% on "Z-A" 6064.26
Cost of 10 sqm 606.43
Cost of 1 sqm 606.40
Say

11.10 40 mm thick marble chips flooring,


rubbed
11.10.1 and polished
Dark shadetopigment
granolithic
withfinish,
Ordinary
under
cement
Details
layer 31 mm thick
of cost for 10 sqm
cement concrete
1:2:4 (1 cement : 2 coarse sand : 4 graded
MATERIAL
For Under layer of 31 mm thick
296 Stone Aggregate (Single size) : 12.5 mm cum 0.21 810 170.10
nominal size
297 Stone Aggregate (Single size) : 10 mm nominal cum 0.07 810 56.70
size
2202 Carriage of Stone aggregate below 40 mm cum 0.28 584.88 163.77
nominal size
982 Coarse sand cum 0.14 800 112.00
2203 Carriage of Coarse sand cum 0.14 584.88 81.88
367 Portland Cement tonne 0.1005 4375 439.69
367 Portland Cement tonne 0.02 4375 87.50
2209 Carriage of Cement for top layer 9mm thick tonne 0.1205 94.34 11.37
788 Marble chips large size above 4 mm White & quintal 1.4 250 350.00
black
2268 Carriage of Marble dust and marble chips cum 0.082 106.13 8.70
367 Portland Cement tonne 0.0578 4375 252.88
2209 Carriage of Cement tonne 0.0578 94.34 5.45
784 Marble dust/ powder cum 0.012 1130 13.56
874 Black colour dark shade pigment kilogram 4.05 70 283.50
3.5kg/ 50kg of cement
= 57.80x3.5/50=4.05kg
9977 Carriage of pigment & marble powder etc. L.S. 5.46 2 10.92
LABOUR
24 Mason (brick layer) 2nd class day 1.79 403.67 722.57
17 Beldar day 1.99 350.00 696.50
11 Bhisti day 1.04 350.00 364.00
37 Skilled Beldar (for floor rubbing etc.) day 1 350.00 350.00
27 Driver (for Road Roller, Concrete Mixer, Truck day 0.03 421.17 12.64
etc.)
2 Hire charges of Concrete Mixer 0.25 to day 0.03 800 24.00
0.40 cum with hooper
13 Machine for rubbing of floors day 1.6 300 480.00
9999 Sundries L.S. 134.55 2 269.10
Total 4966.83
Add 1 % Water charges on "W" 49.6683
TOTAL 5016.50
Add GST (multiplying factor 0.1405) on "X" 704.82
TOTAL 5721.32
Add 15 % Contractor's profit and overheads on "Y" 858.20
Total 6579.52
Add Cess @ 1% on "Z" 65.80
Cost of 10 sqm 6645.32
Cost of 1 sqm 664.53
Say 664.50

11.10.2 Light shade pigment with white cement


Details of cost for 10 sqm
11.10.1 Rate as per item no 11.10.1 of SH: Flooring sqm 10 664.50 6645.00
Add difference of cost due to using light shade
pigment instead of dark shade pigment Add for
875 Red, chocolate, orange, buff or yellow kilogram 4.05 60 243.00
(red oxide of iron) light shade pigment Deduct
for
874 Black colour dark shade pigment kilogram -4.05 70 -283.50
Add difference of cost due to using white
cement instead of grey cement Add for
368 White Cement Deduct for tonne 0.0578 11200 647.36
367 Portland Cement tonne -0.0578 4375 -252.88
Total 6998.98
Add 1 % Water charges on "W-A" 353.98 3.5398
TOTAL
Add GST (multiplying factor 0.1405) on "X-A" 357.52 50.23
TOTAL
Add 15 % Contractor's profit and overheads on " 407.75 61.16
Total
Add Cess @ 1% on "Z-A" 468.91 4.69
Cost of 10 sqm 7118.60
Cost of 1 sqm 711.86
Say 711.90

11.10.3 Medium shade pigment with 50% white


cement
Details of and 50%
cost for ordinary cement
10 sqm
11.10.1 Rate as per item no 11.10.1 of SH: Flooring Add sqm 10 664.50 6645.00
876 Green or blue medium shade pigment Deduct for kilogram 4.05 56 226.80
874 Black colour dark shade pigment kilogram -4.05 70 -283.50
Add difference of cost due to using white
cement instead of grey cement Add for
368 White Cement Deduct for tonne 0.0289 11200 323.68
367 Portland Cement tonne -0.0289 4375 -126.44
Total 6785.54
Add 1 % Water charges on "W-A" 140.54 1.4054
TOTAL
Add GST (multiplying factor 0.1405) on "X-A" 141.95 19.94
TOTAL
Add 15 % Contractor's profit and overheads on "Y-A" 161.89 24.28
Total
Add Cess @ 1% on "Z-A" 186.17 1.86
Cost of 10 sqm 6833.03
Cost of 1 sqm 683.3
Say 683.30

11.10.4 White cement without any pigment


Details of cost for 10 sqm
MATERIAL
For Under layer of 31 mm thick
296 Stone Aggregate (Single size) : 12.5 mm cum 0.21 810 170.10
nominal size
297 Stone Aggregate (Single size) : 10 mm nominal cum 0.07 810 56.70
size
2202 Carriage of Stone aggregate below 40 mm cum 0.28 584.88 163.77
nominal size
982 Coarse sand cum 0.14 800 112.00
2203 Carriage of Coarse sand cum 0.14 584.88 81.88
367 Portland Cement tonne 0.1005 4375 439.69
367 Portland Cement tonne 0.02 4375 87.50
2209 Carriage of Cement for top layer 9mm thick tonne 0.1205 94.34 11.37
788 Marble chips large size above 4 mm White & quintal 1.4 250 350.00
black
2268 Carriage of Marble dust and marble chips cum 0.082 106.13 8.70
368 White Cement tonne 0.0578 11200 647.36
2209 Carriage of Cement tonne 0.0578 94.34 5.45
784 Marble dust/ powder cum 0.012 1130 13.56
LABOUR
24 Mason (brick layer) 2nd class day 1.79 403.67 722.57
17 Beldar day 1.99 350.00 696.50
11 Bhisti day 1.04 350.00 364.00
37 Skilled Beldar (for floor rubbing etc.) day 1 350.00 350.00
27 Driver (for Road Roller, Concrete Mixer, Truck day 0.03 421.17 12.64
etc.)
2 Hire charges of Concrete Mixer 0.25 to day 0.03 800 24.00
0.40 cum with hooper
13 Machine for rubbing of floors day 1.6 300 480.00
9999 Sundries L.S. 161.46 2 322.92
Total 5120.71
Add 1 % Water charges on "W" 51.2071
TOTAL 5171.92
Add GST (multiplying factor 0.1405) on "X" 726.65
TOTAL 5898.57
Add 15 % Contractor's profit and overheads on "Y" 884.79
Total 6783.36
Add Cess @ 1% on "Z" 67.83
Cost of 10 sqm 6851.19
Cost of 1 sqm 685.12
Say 685.10

11.10.5 Light shade pigment with ordinary cement


Details of cost for 10 sqm
11.10.1 Rate as per item no 11.10.1 of SH: Flooring Add sqm 10 664.50 6645.00
difference of cost due to using light shade
pigment instead of dark shade pigment Add for
875 Red, chocolate, orange, buff or yellow kilogram 2.84 60 170.40
(red oxide of iron) light shade pigment Deduct
for
874 Black colour dark shade pigment kilogram -2.84 70 -198.80
Total 6616.60
Add 1 % Water charges on "W-A" -28.40 -0.284
TOTAL
Add GST (multiplying factor 0.1405) on "X-A" -28.68 -4.03
TOTAL
Add 15 % Contractor's profit and overheads on -32.71 -4.91
"Y-A"
Total -37.62 -0.38
Add Cess @ 1% on "Z-A" 6607.00
Cost of 10 sqm 660.7
Cost of 1 sqm 660.70
Say

11.10.6 Ordinary cement without any


pigment
Details of cost for 10 sqm
MATERIAL
For under layer 31 mm thick
296 Stone Aggregate (Single size) : 12.5 mm cum 0.21 810 170.10
nominal size
297 Stone Aggregate (Single size) : 10 mm nominal cum 0.07 810 56.70
size
2202 Carriage of Stone aggregate below 40 mm cum 0.28 584.88 163.77
nominal size
982 Coarse sand cum 0.14 800 112.00
2203 Carriage of Coarse sand cum 0.14 584.88 81.88
367 Portland Cement tonne 0.1005 4375 439.69
367 Portland Cement tonne 0.02 4375 87.50
2209 Carriage of Cement for top layer 9mm thick tonne 0.1205 94.34 11.37
788 Marble chips large size above 4 mm White & quintal 1.4 250 350.00
black
2268 Carriage of Marble dust and marble chips cum 0.082 106.13 8.70
367 Portland Cement tonne 0.0578 4375 252.88
2209 Carriage of Cement tonne 0.0578 94.34 5.45
784 Marble dust/ powder cum 0.012 1130 13.56
LABOUR
24 Mason (brick layer) 2nd class day 1.79 403.67 722.57
17 Beldar day 1.99 350.00 696.50
11 Bhisti day 1.04 350.00 364.00
37 Skilled Beldar (for floor rubbing etc.) day 1 350.00 350.00
27 Driver (for Road Roller, Concrete Mixer, Truck day 0.03 421.17 12.64
etc.)
2 Hire charges of Concrete Mixer 0.25 to day 0.03 800 24.00
0.40 cum with hooper
13 Machine for rubbing of floors day 1.6 300 480.00
9999 Sundries L.S. 134.55 2 269.10
Total 4672.41
Add 1 % Water charges on "W" 46.7241
TOTAL 4719.13
Add GST (multiplying factor 0.1405) on "X" 663.04
TOTAL 5382.17
Add 15 % Contractor's profit and overheads on "Y" 807.33
Total 6189.50
Add Cess @ 1% on "Z" 61.90
Cost of 10 sqm 6251.40
Cost of 1 sqm 625.14
Say 625.10

11.11 40 mm thick marble chips flooring,


rubbed
11.11.1 and polished
Dark shadetopigment
granolithic
withfinish,
ordinary
under
cement
Details
layer 28 mm thick
of cost for 10 sqm
cement concrete
1:2:4 (1 cement : 2 coarse sand : 4 graded
MATERIAL
For under layer 28 mm thick
296 Stone Aggregate (Single size) : 12.5 mm cum 0.19 810 153.90
nominal size
297 Stone Aggregate (Single size) : 10 mm nominal cum 0.06 810 48.60
size
2202 Carriage of Stone aggregate below 40 mm cum 0.25 584.88 146.22
nominal size
982 Coarse sand cum 0.125 800 100.00
2203 Carriage of Coarse sand cum 0.125 584.88 73.11
367 Portland Cement tonne 0.0897 4375 392.44
367 Portland Cement tonne 0.02 4375 87.50
2209 Carriage of Cement tonne 0.1097 94.34 10.35
For top layer 12mm thick
788 Marble chips large size above 4 mm White & quintal 1.734 250 433.50
black
2268 Carriage of Marble dust and marble chips cum 0.102 106.13 10.83
367 Portland Cement tonne 0.081 4375 354.38
2209 Carriage of Cement tonne 0.081 94.34 7.64
784 Marble dust/ powder cum 0.017 1130 19.21
874 Black colour dark shade pigment kilogram 5.67 70 396.90
@ 3.5kg/50kg of cement
= 81x3.5/50=5.67kg
9977 Carriage of pigment and marble powder etc. L.S. 6.24 2 12.48
LABOUR 0
24 Mason (brick layer) 2nd class day 1.79 403.67 722.57
17 Beldar day 1.99 350.00 696.50
11 Bhisti day 1.04 350.00 364.00
37 Skilled Beldar (for floor rubbing etc.) day 1 350.00 350.00
27 Driver (for Road Roller, Concrete Mixer, Truck day 0.03 421.17 12.64
etc.)
2 Hire charges of Concrete Mixer 0.25 to day 0.03 800 24.00
0.40 cum with hooper 0
13 Machine for rubbing of floors day 1.6 300 480.00
9999 Sundries L.S. 156.13 2 312.26
TOTAL 5209.03
Add 1 % Water charges on "W" 52.0903
TOTAL 5261.12
Add GST (multiplying factor 0.1405) on "X" 739.19
TOTAL 6000.31
Add 15 % Contractor's profit and overheads on "Y" 900.05
Total 6900.36
Add Cess @ 1% on "Z" 69.00
Cost of 10 sqm 6969.36
Cost of 1 sqm 696.94
Say 696.90

11.11.2 Light shade pigment with white cement

Details of cost for 10 sqm


11.11.1 Rate as per Item Number 11.11.1 of sqm 10 696.90 6969.00
SH: Flooring
Add difference of cost due to using light shade
pigment instead of dark shade pigment
875 Red, chocolate, orange, buff or yellow kilogram 5.67 60 340.20
(red oxide of iron) light shade pigment Deduct
874 Black colour dark shade pigment kilogram -5.67 70 -396.90
Add Difference of cost due to using white
cement instead of grey cement Add for
368 White Cement Deduct for tonne 0.081 11200 907.20
367 Portland Cement tonne -0.081 4375 -354.38
TOTAL 7465.12
Add 1 % Water charges on "W-A" 496.12 4.9612
TOTAL
Add GST (multiplying factor 0.1405) on "X-A" 501.08 70.40
TOTAL
Add 15 % Contractor's profit and overheads on"Y-A" 571.48 85.72
Total
Add Cess @ 1% on "Z-A" 657.20 6.57
Cost of 10 sqm 7632.77
Cost of 1 sqm 763.28
Say 763.30

11.11.3 Medium shade pigment with 50% white


cement
Details of and 50%
cost for ordinary cement
10 sqm
11.11.1 Rate as per Item Number 11.11.1 of sqm 10 696.90 6969.00
SH: Flooring
Add difference of cost due to using Medium
shade pigment instead of dark shade pigment
Add for
876 Green or blue medium shade pigment Deduct kilogram 5.67 56 317.52
for
874 Black colour dark shade pigment kilogram -5.67 70 -396.90
Add Difference of cost due to using white
cement instead of grey cement Add for
368 White Cement Deduct for tonne 0.0405 11200 453.60
367 Portland Cement tonne -0.0405 4375 -177.19
TOTAL 7166.03
Add 1 % Water charges on "W-A" 197.03 1.9703
TOTAL
Add GST (multiplying factor 0.1405) on "X-A" 199.00 27.96
TOTAL
Add 15 % Contractor's profit and overheads on 226.96 34.04
"Y-A"
Total 261.00 2.61
Add Cess @ 1% on "Z-A" 7232.61
Cost of 10 sqm 723.26
Cost of 1 sqm 723.30
Say

11.11.4 White cement without any pigment


Details of cost for 10 sqm
MATERIAL
For under layer 28 mm thick
296 Stone Aggregate (Single size) : 12.5 mm cum 0.19 810 153.90
nominal size
297 Stone Aggregate (Single size) : 10 mm nominal cum 0.06 810 48.60
size
2202 Carriage of Stone aggregate below 40 mm cum 0.25 584.88 146.22
nominal size
982 Coarse sand cum 0.125 800 100.00
2203 Carriage of Coarse sand cum 0.125 584.88 73.11
367 Portland Cement tonne 0.0897 4375 392.44
367 Portland Cement tonne 0.02 4375 87.50
2209 Carriage of Cement tonne 0.1097 94.34 10.35
For Top layer 12 mm thick
788 Marble chips large size above 4 mm White & quintal 1.916 250 479.00
black
2268 Carriage of Marble dust and marble chips cum 0.1128 106.13 11.97
368 White Cement tonne 0.081 11200 907.20
2209 Carriage of Cement tonne 0.081 94.34 7.64
784 Marble dust/ powder cum 0.017 1130 19.21
LABOUR
24 Mason (brick layer) 2nd class day 1.79 403.67 722.57
17 Beldar day 1.99 350.00 696.50
11 Bhisti day 1.04 350.00 364.00
37 Skilled Beldar (for floor rubbing etc.) day 1 350.00 350.00
27 Driver (for Road Roller, Concrete Mixer, Truck day 0.03 421.17 12.64
etc.)
2 Hire charges of Concrete Mixer 0.25 to day 0.03 800 24.00
0.40 cum with hooper
13 Machine for rubbing of floors day 1.6 300 480.00
9999 Sundries L.S. 134.55 2 269.10
TOTAL 5355.95
Add 1 % Water charges on "W" 53.5595
TOTAL 5409.51
Add GST (multiplying factor 0.1405) on "X" 760.04
TOTAL 6169.55
Add 15 % Contractor's profit and overheads on "Y" 925.43
Total 7094.98
Add Cess @ 1% on "Z" 70.95
Cost of 10 sqm 7165.93
Cost of 1 sqm 716.59
Say 716.60

11.11.5 Light shade pigment with ordinary cement


Details of cost for 10 sqm
11.11.1 Rate as per Item Number 11.11.1 of sqm 10 696.90 6969.00
SH:Flooring
Add difference of cost due to using Light shade
pigment instead of dark shade pigment Add for
875 Red, chocolate, orange, buff or yellow kilogram 5.67 60 340.20
(red oxide of iron) light shade pigment Deduct
for
874 Black colour dark shade pigment kilogram -5.67 70 -396.90
TOTAL 6912.30
Add 1 % Water charges on "W-A" -56.70 -0.567
TOTAL
Add GST (multiplying factor 0.1405) on "X-A" -57.27 -8.05
TOTAL
Add 15 % Contractor's profit and overheads on -65.32 -9.80
"Y-A"
Total -75.12 -0.75
Add Cess @ 1% on "Z-A" 6893.13
Cost of 10 sqm 689.31
Cost of 1 sqm 689.30
Say

11.11.6 Ordinary cement without any pigment


Details of cost for 10 sqm
MATERIAL
For under layer 28 mm thick
296 Stone Aggregate (Single size) : 12.5 mm cum 0.19 810 153.90
nominal size
297 Stone Aggregate (Single size) : 10 mm nominal cum 0.06 810 48.60
size
2202 Carriage of Stone aggregate below 40 mm cum 0.25 584.88 146.22
nominal size
982 Coarse sand cum 0.125 800 100.00
2203 Carriage of Coarse sand cum 0.125 584.88 73.11
367 Portland Cement tonne 0.0897 4375 392.44
367 Portland Cement tonne 0.02 4375 87.50
2209 Carriage of Cement tonne 0.1097 94.34 10.35
For Top layer 12mm thick
788 Marble chips large size above 4 mm White & quintal 1.916 250 479.00
black
2268 Carriage of Marble dust and marble chips cum 0.1128 106.13 11.97
367 Portland Cement tonne 0.081 4375 354.38
2209 Carriage of Cement tonne 0.081 94.34 7.64
784 Marble dust/ powder cum 0.017 1130 19.21
LABOUR
24 Mason (brick layer) 2nd class day 1.79 403.67 722.57
17 Beldar day 1.99 350.00 696.50
11 Bhisti day 1.04 350.00 364.00
37 Skilled Beldar (for floor rubbing etc.) day 1 350.00 350.00
27 Driver (for Road Roller, Concrete Mixer, Truck day 0.03 421.17 12.64
etc.)
2 Hire charges of Concrete Mixer 0.25 to day 0.03 800 24.00
0.40 cum with hooper
13 Machine for rubbing of floors day 1.6 300 480.00
9999 Sundries L.S. 134.55 2 269.10
TOTAL 4803.13
Add 1 % Water charges on "W" 48.0313
TOTAL 4851.16
Add GST (multiplying factor 0.1405) on "X" 681.59
TOTAL 5532.75
Add 15 % Contractor's profit and overheads on "Y" 829.91
Total 6362.66
Add Cess @ 1% on "Z" 63.63
Cost of 10 sqm 6426.29
Cost of 1 sqm 642.63
Say 642.60

11.12 Marble chips skirting up to 30 cm


height,
11.12.1rubbed 18 mm and polished
thick to granolithic
with under layer 12
finish,
mm top
thick layer
in 6
cement mm thick
plaster with
1:3 white,
(1 cementblack,
:3
11.12.1.1
chocolate, Dark
grey, shade
yellow pigment
or green with ordinary
marble
coarse
cement sand) :
Details of cost for 10 sqm
MATERIAL
For under layer of 12mm thick Cement mortar
1:3 (1 cement : 3 coarse sand) = 0.144 + Extra
for rounding = 0.03 =0.174
3.8 Rate as per Item Number 3.8 of SH: Mortars cum 0.174 4129.00 718.45
Top layer 6mm thick
785 Marble chips upto 4mm and downsize White & quintal 0.872 189 164.81
black
2268 Carriage of Marble dust and marble chips cum 0.051 106.13 5.41
367 Portland Cement tonne 0.0405 4375 177.19
2209 Carriage of Cement tonne 0.0405 94.34 3.82
784 Marble dust/ powder cum 0.007 1130 7.91
874 Black colour dark shade pigment kilogram 2.84 70 198.80
@ 3.5kg/50kg of cement
=40.5x3.5/50=2.84kg
9977 Carriage of pigment & marble powder etc. L.S. 3.64 2 7.28
LABOUR
24 Mason (brick layer) 2nd class day 3 403.67 1211.01
17 Beldar day 3 350.00 1050.00
11 Bhisti day 1 350.00 350.00
37 Skilled Beldar (for floor rubbing etc.) day 7 350.00 2450.00
9999 Sundries L.S. 201.89 2 403.78
TOTAL 6748.46
Add 1 % Water charges on "W" 67.4846
TOTAL 6815.94
Add GST (multiplying factor 0.1405) on "X" 957.64
TOTAL 7773.58
Add 15 % Contractor's profit and overheads on "Y" 1166.04
Total 8939.62
Add Cess @ 1% on "Z" 89.40
Cost of 10 sqm 9029.02
Cost of 1 sqm 902.9
Say 902.90

11.12.1.2 Light shade pigment with white cement


Details of cost for 10 sqm
11.12.1.1 Rate as per Item Number 11.12.1.1 of sqm 10 902.90 9029.00
SH: Flooring
Add difference of cost due to using light shade
pigment instead of dark shade pigment Add for
875 Red, chocolate, orange, buff or yellow kilogram 2.84 60 170.40
(red oxide of iron) light shade pigment Deduct
for
874 Black colour dark shade pigment kilogram -2.84 70 -198.80
Add Difference of cost due to using white
cement instead of grey cement
Add for
368 White Cement Deduct for tonne 0.0405 11200 453.60
367 Portland Cement tonne -0.0405 4375 -177.19
TOTAL 9277.01
Add 1 % Water charges on "W-A" 248.01 2.4801
TOTAL
Add GST (multiplying factor 0.1405) on "X-A" 250.49 35.19
TOTAL
Add 15 % Contractor's profit and overheads on "Y-A" 285.68 42.85
Total
Add Cess @ 1% on "Z-A" 328.53 3.29
Cost of 10 sqm 9360.82
Cost of 1 sqm 936.08
Say 936.10

11.12.1.3 Medium shade pigment with 50% white


cement
Details of and 50%
cost for ordinary cement
10 sqm
11.12.1.1 Rate as per Item Number 11.12.1.1 of sqm 10 902.90 9029.00
SH:Flooring
Add difference of cost due to using medium
shade pigment instead of dark shade pigment
Add for
876 Green or blue medium shade pigment Deduct kilogram 2.84 56 159.04
for
874 Black colour dark shade pigment kilogram -2.84 70 -198.80
Add Difference of cost due to using white
cement instead of grey cement Add for
368 White Cement Deduct for tonne 0.0203 11200 227.36
367 Portland Cement tonne -0.0203 4375 -88.81
TOTAL 9127.79
Add 1 % Water charges on "W-A" 98.79 0.9879
TOTAL
Add GST (multiplying factor 0.1405) on "X-A" 99.78 14.02
TOTAL
Add 15 % Contractor's profit and overheads on "Y-A" 113.80 17.07
Total
Add Cess @ 1% on "Z-A" 130.87 1.31
Cost of 10 sqm 9161.18
Cost of 1 sqm 916.12
Say 916.10

11.12.1.4 White cement without any pigment


Details of cost for 10 sqm
MATERIAL
For under layer of 12mm thick Cement mortar
1:3 (1 cement : 3 coarse sand) =
0.144+
Extra for rounding = 0.03
Total =0.174
3.8 Rate as per Item Number 3.8 of SH: Mortars cum 0.174 4129.00 718.45
Top layer 6mm thick
785 Marble chips upto 4mm and downsize White & quintal 0.958 189 181.06
black
2268 Carriage of Marble dust and marble chips cum 0.056 106.13 5.94
368 White Cement tonne 0.0405 11200 453.60
2209 Carriage of Cement tonne 0.0405 94.34 3.82
784 Marble dust/ powder cum 0.007 1130 7.91
LABOUR
24 Mason (brick layer) 2nd class day 3 403.67 1211.01
17 Beldar day 3 350.00 1050.00
11 Bhisti day 1 350.00 350.00
37 Skilled Beldar (for floor rubbing etc.) day 7 350.00 2450.00
9999 Sundries L.S. 201.89 2 403.78
TOTAL 6835.57
Add 1 % Water charges on "W" 68.3557
TOTAL 6903.93
Add GST (multiplying factor 0.1405) on "X" 970.00
TOTAL 7873.93
Add 15 % Contractor's profit and overheads on "Y" 1181.09
Total 9055.02
Add Cess @ 1% on "Z" 90.55
Cost of 10 sqm 9145.57
Cost of 1 sqm 914.56
Say 914.60

11.12.1.5 Light shade pigment with ordinary cement


Details of cost for 10 sqm
11.12.1.1 Rate as per Item Number 11.12.1.1 of sqm 10 902.90 9029.00
SH: Flooring
Add difference of cost due to using Light shade
pigment instead of dark shade pigment Add for
875 Red, chocolate, orange, buff or yellow kilogram 2.84 60 170.40
(red oxide of iron) light shade pigment Deduct
for
874 Black colour dark shade pigment kilogram -2.84 70 -198.80
TOTAL 9000.60
Add 1 % Water charges on "W-A" -28.40 -0.284
TOTAL
Add GST (multiplying factor 0.1405) on "X-A" -28.68 -4.03
TOTAL
Add 15 % Contractor's profit and overheads on -32.71 -4.91
"Y-A"
Total -37.62 -0.38
Add Cess @ 1% on "Z-A" 8991.00
Cost of 10 sqm 899.1
Cost of 1 sqm 899.10
Say

11.12.1.6 Ordinary cement without any pigment


Details of cost for 10 sqm
11.12.1.1 Rate as per Item Number 11.12.1.1 of sqm 10 902.90 9029.00
SH: Flooring
Less cost of dark shade pigment
Deduct for
874 Black colour dark shade pigment kilogram -2.84 70 -198.80
9999 Deduct for Carriage of pigment L.S. -3.64 2 -7.28
2268 Marble dust and/or marble chips cum 0.007 106.13 0.74
TOTAL 8823.66
Add 1 % Water charges on "W-A" -205.34 -2.0534
TOTAL
Add GST (multiplying factor 0.1405) on "X-A" -207.39 -29.14
TOTAL
Add 15 % Contractor's profit and overheads on -236.53 -35.48
"Y-A"
Total -272.01 -2.72
Add Cess @ 1% on "Z-A" 8754.27
Cost of 10 sqm 875.43
Cost of 1 sqm 875.40
Say

11.13 Providing and fixing glass strips in joints


11.13.1 of 40
terrazo/ cement
mm wide and concrete floors.
4 mm thick
Details of cost for 10 metre length
MATERIAL
Glass strips = 10m
Add 10% for wastage = 1m
Total = 11m
1149 Glass strip 4 mm thick40 mm deep metre 11 20 220.00
9977 Carriage of glass L.S. 2.73 2 5.46
LABOUR
24 Mason (brick layer) 2nd class day 0.25 403.67 100.92
17 Beldar day 0.25 350.00 87.50
9999 Sundries L.S. 13.52 2 27.04
TOTAL 440.92
Add 1 % Water charges on "W" 4.4092
TOTAL 445.33
Add GST (multiplying factor 0.1405) on "X" 62.57
TOTAL 507.90
Add 15 % Contractor's profit and overheads on "Y" 76.18
Total 584.08
Add Cess @ 1% on "Z" 5.84
Cost of 10 sqm 589.92
Cost of 1 sqm 58.99
Say 59.00

11.14 Extra for laying terrazo flooring on


staircase treads cost
width, including not exceeding
of forming,30 cm inetc.
nosing
Details of cost for 10 sqm.
LABOUR
24 Mason (brick layer) 2nd class day 0.3 403.67 121.10
17 Beldar day 0.3 350.00 105.00
18 Coolie day 0.3 350.00 105.00
TOTAL 331.10
Add 1 % Water charges on "W" 3.311
TOTAL 334.41
Add GST (multiplying factor 0.1405) on "X" 46.98
TOTAL 381.39
Add 15 % Contractor's profit and overheads on "Y" 57.21
Total 438.60
Add Cess @ 1% on "Z" 4.39
Cost of 10 sqm 442.99
Cost of 1 sqm 44.3
Say 44.30

11.15 Crazy marble stone flooring,


including filling
11.15.1 18 mm thethick
gapscrazy
with marble
light shade
stone
pigment
white, withorwhite
black cement marble powder
as specified
mixture (3 parts of white cement : 1 part of
Details of cost for 10 sqm.
Under layer 25mm thick of cement Concree
1:2:4 -10x0.025=0.25 cum
11.7 Rate as per Item Number 11.7 of SH: Flooring cum 0.25 6274.50 1568.63
Cement slurry for subgrade and under large
cement
367 Portland Cement tonne 0.04 4375 175.00
2209 Carriage of Cement tonne 0.04 94.34 3.77
Labour for applying cement slurry
LABOUR
17 Beldar day 0.5 350.00 175.00
Top layer with marble pieces and gap filling
with marble powder mixture
Marble pieces for crazy flooring
(Assume 70% of marble stone are and 30% of
joint filer/mixture
7sqmx0.02m = 0.14 cum
0.872x0.14/0.051 = 2.40q
2710 White marble makranasecondquality plain quintal 2.4 150 360.00
veined stone pieces for crazy flooring
368 White Cement tonne 0.0405 11200 453.60
784 Marble dust/ powder cum 0.007 1130 7.91
875 Red, chocolate, orange, buff or yellow kilogram 2.84 60 170.40
(red oxide of iron) light shade pigment
@ 3.5kg/50kg of cement =
40.5x3.5/50=2.84kg
785 Marble chips upto 4mm and downsize White & quintal 0.872 189 164.81
black
2268 Carriage of Marble dust and marble chips cum 0.051 106.13 5.41
2209 Carriage of Cement tonne 0.0405 94.34 3.82
9977 Carriage of pigment & marble powder L.S. 3.64 2 7.28
2216 Carriage of Stone blocks white & red sand stone tonne 0.24 94.34 22.64
& kota stone slab
Labour for finishing, polishing and fixing-
23 Mason (brick layer) 1st class day 1.2 505.17 606.20
17 Beldar day 1 350.00 350.00
18 Coolie day 1 350.00 350.00
37 Skilled Beldar (for floor rubbing etc.) day 5 350.00 1750.00
9999 Sundries including carborandum etc. L.S. 134.55 2 269.10
11 Bhisti day 0.54 350.00 189.00
13 Machine for rubbing of floors day 4 300 1200.00

TOTAL 7832.57
Add 1 % Water charges on "W-A" 6263.94 62.6394
TOTAL
Add GST (multiplying factor 0.1405) on "X-A" 6326.58 888.88
TOTAL
Add 15 % Contractor's profit and overheads on 7215.46 1082.32
"Y-A"
Total 8297.78 82.98
Add Cess @ 1% on "Z-A" 9949.39
Cost of 10 sqm 994.94
Cost of 1 sqm 994.90
Say

11.16 Precast terrazo tiles 22 mm thick


with graded marble chips of size upto 12
mm, laid in floors, and landings, jointed with
11.16.1 Light
neat cement shade
slurry pigment
mixed using white
with pigment to
cement
Details of cost for 10 sqm.
MATERIAL
1201 Precast terrazo tiles 22 mm thick sqm 11 285 3135.00
(light shade) including 10% wastage
9977 Carriage of tiles L.S. 40.43 2 80.86
Cement mortar 1 : 4 (1 cement : 4 coarse sand)
3.9 Rate as per Item Number 3.9 of SH: Mortars cum 0.224 3548.00 794.75
367 Portland Cement tonne 0.044 4375 192.50
Grey cement for slurry @ 4.4kg/sqm.
368 White Cement for grouting tonne 0.044 11200 492.80
2209 Carriage of Cement tonne 0.088 94.34 8.30
875 Red, chocolate, orange, buff or yellow kilogram 3.08 60 184.80
(red oxide of iron) light shade pigment
LABOUR
24 Mason (brick layer) 2nd class day 1.6 403.67 645.87
18 Coolie day 2 350.00 700.00
37 Skilled Beldar (for floor rubbing etc.) day 1 350.00 350.00
11 Bhisti day 1 350.00 350.00
13 Machine for rubbing of floors day 1.6 300 480.00
9999 Sundries including carborandum stone etc. L.S. 161.98 2 323.96
TOTAL 7738.84
Add 1 % Water charges on "W" 77.3884
TOTAL 7816.23
Add GST (multiplying factor 0.1405) on "X" 1098.18
TOTAL 8914.41
Add 15 % Contractor's profit and overheads on "Y" 1337.16
Total 10251.57
Add Cess @ 1% on "Z" 102.52
Cost of 10 sqm 10354.09
Cost of 1 sqm 1035.41
Say 1035.40
11.16.2 Medium shade pigment using 50%
white cement
Details of cost forand 50% ordinary cement
10 sqm.
MATERIAL
1202 Precast terrazo tiles 22 mm thick sqm 11 265 2915.00
(medium shade) including 10% wastage
9977 Carriage of tiles L.S. 40.43 2 80.86
Cement mortar 1 : 4 (1 cement : 4 coarse sand)
3.9 Rate as per Item Number 3.9 of cum 0.224 3548.00 794.75
SH: Mortars
Grey cement
(i) for slurry @ 4.4kg/sqm =44 kg.+ (ii) 50% for
grouting = 22kg.
Total =66kg or 0.066 tonne
367 Portland Cement tonne 0.066 4375 288.75
50% white cement for grouting
368 White Cement tonne 0.022 11200 246.40
2209 Carriage of Cement tonne 0.088 94.34 8.30
876 Green or blue medium shade pigment kilogram 3.08 56 172.48
LABOUR
24 Mason (brick layer) 2nd class day 1.6 403.67 645.87
18 Coolie day 2 350.00 700.00
37 Skilled Beldar (for floor rubbing etc.) day 1 350.00 350.00
11 Bhisti day 1 350.00 350.00
13 Machine for rubbing of floors day 1.6 300 480.00
9999 Sundries including carborandum stone etc. L.S. 161.98 2 323.96
TOTAL 7356.37
Add 1 % Water charges on "W" 73.5637
TOTAL 7429.93
Add GST (multiplying factor 0.1405) on "X" 1043.91
TOTAL 8473.84
Add 15 % Contractor's profit and overheads on "Y" 1271.08
Total 9744.92
Add Cess @ 1% on "Z" 97.45
Cost of 10 sqm 9842.37
Cost of 1 sqm 984.24
Say 984.20

11.16.3 Dark shade pigment using ordinary


cement
Details of cost for 10 sqm.
MATERIAL
1203 Precast terrazo tiles 22 mm thick (dark shade) sqm 11 245 2695.00
including 10% wastage
9977 Carriage of tiles L.S. 40.43 2 80.86
Cement mortar 1 : 4 (1 cement : 4 coarse sand)
3.9 Rate as per Item Number 3.9 of SH: Mortars cum 0.224 3548.00 794.75
Ordinary cement for
(i) Cement slurry @ 4.4kg/sqm = 44kg+ (ii)
Grouting = 44 kg.
Total = 88kg or 0.088 tonne
367 Portland Cement tonne 0.088 4375 385.00
2209 Carriage of Cement tonne 0.088 94.34 8.30
874 Black colour dark shade pigment kilogram 3.08 70 215.60
LABOUR
24 Mason (brick layer) 2nd class day 1.6 403.67 645.87
18 Coolie day 2 350.00 700.00
37 Skilled Beldar (for floor rubbing etc.) day 1 350.00 350.00
11 Bhisti day 1 350.00 350.00
13 Machine for rubbing of floors day 1.6 300 480.00
9999 Sundries including carborandum stone etc. L.S. 161.98 2 323.96
TOTAL 7029.34
Add 1 % Water charges on "W" 70.2934
TOTAL 7099.63
Add GST (multiplying factor 0.1405) on "X" 997.50
TOTAL 8097.13
Add 15 % Contractor's profit and overheads on "Y" 1214.57
Total 9311.70
Add Cess @ 1% on "Z" 93.12
Cost of 10 sqm 9404.82
Cost of 1 sqm 940.48
Say 940.50

11.16.4 Ordinary cement without any


pigment
Details of cost for 10 sqm.
MATERIAL
1203 Precast terrazo tiles 22 mm thick (dark shade) sqm 11 245 2695.00
including 10% wastage
9977 Carriage of tiles L.S. 40.43 2 80.86
Cement mortar 1 : 4 (1 cement : 4 coarse sand)
3.9 Rate as per Item Number 3.9 of SH: Mortars cum 0.224 3548.00 794.75
Ordinary cement for
(i) Cement slurry @ 4.4kg/sqm = 44kg+ (ii)
Grouting = 44 kg.
Total = 88kg or 0.088 tonne
367 Portland Cement tonne 0.088 4375 385.00
2209 Carriage of Cement tonne 0.088 94.34 8.30
874 Black colour dark shade pigment kilogram 3.08 70 215.60
LABOUR
24 Mason (brick layer) 2nd class day 1.6 403.67 645.87
18 Coolie day 2 350.00 700.00
37 Skilled Beldar (for floor rubbing etc.) day 1 350.00 350.00
11 Bhisti day 1 350.00 350.00
13 Machine for rubbing of floors day 1.6 300 480.00
9999 Sundries including carborandum stone etc. L.S. 161.98 2 323.96
874 Black colour dark shade pigment kilogram -5.92 70 -414.40
TOTAL 6614.94
Add 1 % Water charges on "W" 66.1494
TOTAL 6681.09
Add GST (multiplying factor 0.1405) on "X" 938.69
TOTAL 7619.78
Add 15 % Contractor's profit and overheads on "Y" 1142.97
Total 8762.75
Add Cess @ 1% on "Z" 87.63
Cost of 10 sqm 8850.38
Cost of 1 sqm 885.04
Say 885.00

11.17 Extra if terrazo tiles are laid in


treads
Details ofofcost
steps not
for 10 exceeding 30 cm in
sqm.
width.
LABOUR
24 Mason (brick layer) 2nd class day 0.22 403.67 88.81
18 Coolie day 0.22 350.00 77.00
37 Skilled Beldar (for floor rubbing etc.) day 0.65 350.00 227.50
TOTAL 393.31
Add 1 % Water charges on "W" 3.9331
TOTAL 397.24
Add GST (multiplying factor 0.1405) on "X" 55.81
TOTAL 453.05
Add 15 % Contractor's profit and overheads on "Y" 67.96
Total 521.01
Add Cess @ 1% on "Z" 5.21
Cost of 10 sqm 526.22
Cost of 1 sqm 52.62
Say 52.60
11.18 Precast terrazo tiles 22 mm thick
with graded
11.18.1 marble
Light chips
shade of sizes
pigment upto
using 12
white
mm, in
cement skirting and risers of steps not
exceeding 30 cm in height, on 12 mm thick
Details of cost for 10 sqm.
MATERIAL
1201 Precast terrazo tiles 22 mm thick (light shade) sqm 11 285 3135.00
including 10% wastage
9977 Carriage of tiles L.S. 40.43 2 80.86
Cement mortar 1:3 (1 cement : 3 coarse sand)
3.8 Rate as per Item Number 3.8 of SH: Mortars cum 0.144 4129.00 594.58
368 White Cement tonne 0.066 11200 739.20
For slurry
For buttering tiles bed sides =44 kg. + For
grouting =22 kg. Total = 66 kg
2209 Carriage of Cement tonne 0.066 94.34 6.23
875 Red, chocolate, orange, buff or yellow kilogram 4.62 60 277.20
(red oxide of iron) light shade pigment
66x3.5/50 = 4.62
LABOUR
24 Mason (brick layer) 2nd class day 3.25 403.67 1311.93
18 Coolie day 3.25 350.00 1137.50
37 Skilled Beldar (for floor rubbing etc.) day 7.6 350.00 2660.00
9999 Sundries including carborandum stone and L.S. 161.46 2 322.92
polishing powder etc.
TOTAL 10265.42
Add 1 % Water charges on "W" 102.6542
TOTAL 10368.07
Add GST (multiplying factor 0.1405) on "X" 1456.71
TOTAL 11824.78
Add 15 % Contractor's profit and overheads on "Y" 1773.72
Total 13598.50
Add Cess @ 1% on "Z" 135.99
Cost of 10 sqm 13734.49
Cost of 1 sqm 1373.45
Say 1373.50

11.18.2 Medium shades pigment using


50%
Detailswhite
of costcement and 50% ordinary cement
for 10 sqm.
MATERIAL
1202 Precast terrazo tiles 22 mm thick sqm 11 265 2915.00
(medium shade)
including wastage & breakage
9977 Carriage of tiles L.S. 40.43 2 80.86
Cement mortar 1:3 (1 cement : 3 coarse sand)
3.8 Rate as per Item Number 3.8 of SH: Mortars cum 0.144 4129.00 594.58
50% white cement for slurry
368 White Cement tonne 0.033 11200 369.60
367 Portland Cement tonne 0.033 4375 144.38
2209 Carriage of Cement tonne 0.066 94.34 6.23
876 Green or blue medium shade pigment kilogram 4.62 56 258.72
LABOUR
24 Mason (brick layer) 2nd class day 3.25 403.67 1311.93
18 Coolie day 3.25 350.00 1137.50
37 Skilled Beldar (for floor rubbing etc.) day 7.6 350.00 2660.00
9999 Sundries including carborandum stone and L.S. 161.46 2 322.92
polishing powder etc.
TOTAL 9801.72
Add 1 % Water charges on "W" 98.0172
TOTAL 9899.74
Add GST (multiplying factor 0.1405) on "X" 1390.91
TOTAL 11290.65
Add 15 % Contractor's profit and overheads on "Y" 1693.60
Total 12984.25
Add Cess @ 1% on "Z" 129.84
Cost of 10 sqm 13114.09
Cost of 1 sqm 1311.41
Say 1311.40

11.18.3 Dark shade pigment using ordinary


cement
Details of cost for 10 sqm.
MATERIAL
1203 Precast terrazo tiles 22 mm thick (dark shade) sqm 11 245 2695.00
including wastage & breakage
9977 Carriage of tiles L.S. 40.43 2 80.86
Cement mortar 1:3 (1 cement : 3 coarse sand)
3.8 Rate as per Item Number 3.8 of SH: Mortars cum 0.144 4129.00 594.58
Grey cement for slurry
367 Portland Cement tonne 0.066 4375 288.75
2209 Carriage of Cement tonne 0.066 94.34 6.23
874 Black colour dark shade pigment kilogram 4.62 70 323.40
LABOUR
24 Mason (brick layer) 2nd class day 3.25 403.67 1311.93
18 Coolie day 3.25 350.00 1137.50
37 Skilled Beldar (for floor rubbing etc.) day 7.6 350.00 2660.00
9999 Sundries including carborandum stone and L.S. 161.46 2 322.92
polishing powder etc.
TOTAL 9421.17
Add 1 % Water charges on "W" 94.2117
TOTAL 9515.38
Add GST (multiplying factor 0.1405) on "X" 1336.91
TOTAL 10852.29
Add 15 % Contractor's profit and overheads on 1627.84
"Y" 12480.13
Total 124.80
Add Cess @ 1% on "Z" 12604.93
Cost of 10 sqm 1260.49
Cost of 1 sqm 1260.50
Say

11.18.4 Ordinary cement without any


pigment
Details of cost for 10 sqm.
MATERIAL
1203 Precast terrazo tiles 22 mm thick (dark shade) sqm 11 245 2695.00
including wastage & breakage
9977 Carriage of tiles L.S. 40.43 2 80.86

Cement mortar 1:3 (1 cement : 3 coarse sand)


3.8 Rate as per Item Number 3.8 of SH: Mortars cum 0.144 4129.00 594.58
Grey cement for sturry
367 Portland Cement tonne 0.066 4375 288.75
2209 Carriage of Cement tonne 0.066 94.34 6.23
874 Black colour dark shade pigment kilogram 4.62 70 323.40
LABOUR
24 Mason (brick layer) 2nd class day 3.25 403.67 1311.93
18 Coolie day 3.25 350.00 1137.50
37 Skilled Beldar (for floor rubbing etc.) day 7.6 350.00 2660.00
9999 Sundries including carborandum stone and L.S. 161.46 2 322.92
polishing powder etc.
Less for dark shade pigment
[4.62+2.84 (for tiles)]
874 Black colour dark shade pigment kilogram -7.46 70 -522.20
TOTAL 8898.97
Add 1 % Water charges on "W" 88.9897
TOTAL 8987.96
Add GST (multiplying factor 0.1405) on "X" 1262.81
TOTAL 10250.77
Add 15 % Contractor's profit and overheads on "Y" 1537.62
Total 11788.39
Add Cess @ 1% on "Z" 117.88
Cost of 10 sqm 11906.27
Cost of 1 sqm 1190.63
Say 1190.60

11.19 Chequered terrazo tiles 22 mm


thick
11.19.1with graded marble
Light shade chips of
pigment sizewhite
using up to 6
mm in
cement floors, jointed with
Details of cost for 10 sqm.
neat cement slurry
mixed with pigment to match the shade of
MATERIAL
1227 Chequered terrazo tiles 22 mm thick sqm 11 275 3025.00
(light shade) including 10% wastage
9977 Carriage of tiles L.S. 40.43 2 80.86
Cement mortar 1 : 4 (1 cement : 4 coarse sand)
3.9 Rate as per Item Number 3.9 of SH: Mortars cum 0.224 3548.00 794.75
Grey cement for slurry @ 4.4kg/sqm
367 Portland Cement tonne 0.044 4375 192.50
White cement for grouting
368 White Cement tonne 0.044 11200 492.80
2209 Carriage of Cement tonne 0.088 94.34 8.30
875 Red, chocolate, orange, buff or yellow kilogram 3.08 60 184.80
(red oxide of iron) light shade pigment
LABOUR
24 Mason (brick layer) 2nd class day 1.6 403.67 645.87
18 Coolie day 2 350.00 700.00
37 Skilled Beldar (for floor rubbing etc.) day 1 350.00 350.00
11 Bhisti day 1 350.00 350.00
13 Machine for rubbing of floors day 1.6 300 480.00
9999 Sundries including carborandum stone etc. L.S. 161.98 2 323.96
TOTAL 7628.84
Add 1 % Water charges on "W" 76.2884
TOTAL 7705.13
Add GST (multiplying factor 0.1405) on "X" 1082.57
TOTAL 8787.70
Add 15 % Contractor's profit and overheads on "Y" 1318.15
Total 10105.85
Add Cess @ 1% on "Z" 101.06
Cost of 10 sqm 10206.91
Cost of 1 sqm 1020.69
Say 1020.70

11.19.2 Medium shade pigment using 50%


white cement,
Details of cost for 50% ordinary cement
10 sqm.
MATERIAL
1228 Chequered terrazo tiles 22 mm thick sqm 11 300 3300.00
(medium shade) including 10% wastage
9977 Carriage of tiles L.S. 40.43 2 80.86
Cement mortar 1 : 4 (1 cement : 4 coarse sand)
3.9 Rate as per Item Number 3.9 of SH: Mortars cum 0.224 3548.00 794.75
Grey cement
(i) for slurry @ 4.4kg/sqm =44 kg.+ (ii) 50% for
grouting = 22kg.
Total =66kg or 0.066 tonne
367 Portland Cement tonne 0.066 4375 288.75
50% white cement for grouting
368 White Cement tonne 0.022 11200 246.40
2209 Carriage of Cement tonne 0.088 94.34 8.30
876 Green or blue medium shade pigment Labour kilogram 3.08 56 172.48
and sundries
24 Mason (brick layer) 2nd class day 1.6 403.67 645.87
18 Coolie day 2 350.00 700.00
37 Skilled Beldar (for floor rubbing etc.) day 1 350.00 350.00
11 Bhisti day 1 350.00 350.00
13 Machine for rubbing of floors day 1.6 300 480.00
9999 Sundries including carborandum stone etc. L.S. 161.98 2 323.96
TOTAL 7741.37
Add 1 % Water charges on "W" 77.4137
TOTAL 7818.78
Add GST (multiplying factor 0.1405) on "X" 1098.54
TOTAL 8917.32
Add 15 % Contractor's profit and overheads on "Y" 1337.60
Total 10254.92
Add Cess @ 1% on "Z" 102.55
Cost of 10 sqm 10357.47
Cost of 1 sqm 1035.75
Say 1035.80

11.19.3 Dark shade pigment using ordinary


cement
Details of cost for 10 sqm.
MATERIAL
1229 Chequered terrazo tiles 22 mm thick sqm 11 260 2860.00
(dark shade) including 10% wastage
9977 Carriage of tiles L.S. 40.43 2 80.86
Cement mortar 1 : 4 (1 cement : 4 coarse sand)
3.9 Rate as per Item Number 3.9 of SH: Mortars cum 0.224 3548.00 794.75
Ordinary cement for
(i) Cement slurry @ 4.4kg/sqm = 44kg+ (ii)
Grouting = 44 kg.
Total = 88kg or 0.088 tonne
367 Portland Cement tonne 0.088 4375 385.00
2209 Carriage of Cement tonne 0.088 94.34 8.30
874 Black colour dark shade pigment Labour & kilogram 3.08 70 215.60
sundries
24 Mason (brick layer) 2nd class day 1.6 403.67 645.87
18 Coolie day 2 350.00 700.00
37 Skilled Beldar (for floor rubbing etc.) day 1 350.00 350.00
11 Bhisti day 1 350.00 350.00
13 Machine for rubbing of floors day 1.6 300 480.00
9999 Sundries including carborandum stone etc. L.S. 161.98 2 323.96
TOTAL 7194.34
Add 1 % Water charges on "W" 71.9434
TOTAL 7266.28
Add GST (multiplying factor 0.1405) on "X" 1020.91
TOTAL 8287.19
Add 15 % Contractor's profit and overheads on "Y" 1243.08
Total 9530.27
Add Cess @ 1% on "Z" 95.30
Cost of 10 sqm 9625.57
Cost of 1 sqm 962.56
Say 962.60

11.19.4 Ordinary cement without any


pigment
Details of cost for 10 sqm.
MATERIAL
1229 Chequered terrazo tiles 22 mm thick sqm 11 260 2860.00
(dark shade) including 10% wastage
9977 Carriage of tiles L.S. 40.43 2 80.86
Cement mortar 1 : 4 (1 cement : 4 coarse sand)
3.9 Rate as per Item Number 3.9 of SH: Mortars cum 0.224 3548.00 794.75
Ordinary cement for
(i) Cement slurry @ 4.4kg/sqm = 44kg+ (ii)
Grouting = 44 kg.
Total = 88kg or 0.088 tonne
367 Portland Cement tonne 0.088 4375 385.00
2209 Carriage of Cement tonne 0.088 94.34 8.30
874 Black colour dark shade pigment Labour & kilogram 3.08 70 215.60
sundries
24 Mason (brick layer) 2nd class day 1.6 403.67 645.87
18 Coolie day 2 350.00 700.00
37 Skilled Beldar (for floor rubbing etc.) day 1 350.00 350.00
11 Bhisti day 1 350.00 350.00
13 Machine for rubbing of floors day 1.6 300 480.00
9999 Sundries including carborandum stone etc. Less L.S. 162.59 2 325.18
for dark shade pigment [3.08+2.84(for tiles)]
874 Black colour dark shade pigment kilogram -5.92 70 -414.40
TOTAL 6781.16
Add 1 % Water charges on "W" 67.8116
TOTAL 6848.97
Add GST (multiplying factor 0.1405) on "X" 962.28
TOTAL 7811.25
Add 15 % Contractor's profit and overheads on "Y" 1171.69
Total 8982.94
Add Cess @ 1% on "Z" 89.83
Cost of 10 sqm 9072.77
Cost of 1 sqm 907.28
Say 907.30

11.20 Chequerred precast cement


concrete
11.20.1 tiles
Light22shade
mm thick in footpath
pigment &
using white
courtyard,
cement jointed with neat cement slurry
mixed with pigment to match the shade of
Details of cost for 10 sqm.
MATERIAL
7070 Chequered precast cement concrete tiles sqm 11 400 4400.00
22mm thick using marble chips of size 6mm -
Light shade using white cement including 10%
wastage
9977 Carriage of tiles L.S. 40.43 2 80.86
Cement mortar 1 : 4 (1 cement : 4 coarse sand)
3.9 Rate as per Item Number 3.9 of SH: Mortars cum 0.22 3548.00 780.56
Grey cement slury @ 4.4kg @sqm
367 Portland Cement tonne 0.044 4375 192.50
White cement for grouting
368 White Cement tonne 0.048 11200 537.60
2209 Carriage of Cement tonne 0.092 94.34 8.68
875 Red, chocolate, orange, buff or yellow kilogram 3.08 60 184.80
(red oxide of iron) light shade pigment
LABOUR
24 Mason (brick layer) 2nd class day 1.6 403.67 645.87
18 Coolie day 2 350.00 700.00
11 Bhisti day 1 350.00 350.00
TOTAL 7880.87
Add 1 % Water charges on "W" 78.8087
TOTAL 7959.68
Add GST (multiplying factor 0.1405) on "X" 1118.33
TOTAL 9078.01
Add 15 % Contractor's profit and overheads on "Y" 1361.70
Total 10439.71
Add Cess @ 1% on "Z" 104.40
Cost of 10 sqm 10544.11
Cost of 1 sqm 1054.41
Say 1054.40

11.20.2 Medium shade pigment using 50%


white
Details cement
of cost for50% Grey cement
10 sqm.
MATERIAL
7237 Precast chequered cement tiles 22 mm thick sqm 11 335 3685.00
medium shade using 50% white
cement, 50% ordinary cement including 10%
wastage
9977 Carriage of tiles L.S. 40.43 2 80.86
Cement mortar 1 : 4 (1 cement : 4 coarse sand)
3.9 Rate as per Item Number 3.9 of SH: Mortars cum 0.22 3548.00 780.56
Grey cement for slurry @ 4.4kg/sqm.
= 44 kg.+ grey cement for grouting 2.4kg/sqm. =
24kg.
Total = 68 kg
367 Portland Cement tonne 0.068 4375 297.50
White cement for grouting @ 2.4kg/sqm. = 24
kg
368 White Cement tonne 0.024 11200 268.80
2209 Carriage of Cement tonne 0.092 94.34 8.68
876 Green or blue medium shade pigment kilogram 3.08 56 172.48
LABOUR
24 Mason (brick layer) 2nd class day 1.6 403.67 645.87
18 Coolie day 2 350.00 700.00
11 Bhisti day 1 350.00 350.00
TOTAL 6989.75
Add 1 % Water charges on "W" 69.8975
TOTAL 7059.65
Add GST (multiplying factor 0.1405) on "X" 991.88
TOTAL 8051.53
Add 15 % Contractor's profit and overheads on "Y" 1207.73
Total 9259.26
Add Cess @ 1% on "Z" 92.59
Cost of 10 sqm 9351.85
Cost of 1 sqm 935.18
Say 935.20

11.20.3 Dark shade pigment using ordinary


cement
Details of cost for 10 sqm.
MATERIAL
7236 Precast chequered cement tiles 22 mm thick sqm 11 225 2475.00
Dark shade using ordinary cement including
10% wastage
9977 Carriage of tiles L.S. 40.43 2 80.86
Cement mortar 1 : 4 (1 cement : 4 coarse sand)
3.9 Rate as per Item Number 3.9 of cum 0.22 3548.00 780.56
SH: Mortars
Grey cement for slurry @ 4.4kg/sqm. = 44 kg.+
For grouting = 48 kg.
Total=92 kg. say 0.092 tonne
367 Portland Cement tonne 0.092 4375 402.50
2209 Carriage of Cement tonne 0.092 94.34 8.68
874 Black colour dark shade pigment kilogram 3.08 70 215.60
LABOUR
24 Mason (brick layer) 2nd class day 1.6 403.67 645.87
18 Coolie day 2 350.00 700.00
11 Bhisti day 1 350.00 350.00
TOTAL 5659.07
Add 1 % Water charges on "W" 56.5907
TOTAL 5715.66
Add GST (multiplying factor 0.1405) on "X" 803.05
TOTAL 6518.71
Add 15 % Contractor's profit and overheads on "Y" 977.81
Total 7496.52
Add Cess @ 1% on "Z" 74.97
Cost of 10 sqm 7571.49
Cost of 1 sqm 757.15
Say 757.20

11.20.4 Ordinary cement without any


pigment
Details of cost for 10 sqm.
MATERIAL
7236 Precast chequered cement tiles 22 mm thick sqm 11 225 2475.00
Dark shade using ordinary cement including
10% wastage
9977 Carriage of tiles L.S. 40.43 2 80.86
Cement mortar 1 : 4 (1 cement : 4 coarse sand)
3.9 Rate as per Item Number 3.9 of SH: Mortars cum 0.22 3548.00 780.56
Grey cement for slurry @ 4.4kg/sqm. = 44 kg +
For grouting = 48 kg.
Total = 92 kg. Say 0.092 tonne
367 Portland Cement tonne 0.092 4375 402.50
2209 Carriage of Cement tonne 0.092 94.34 8.68
874 Black colour dark shade pigment kilogram 3.08 70 215.60
LABOUR
24 Mason (brick layer) 2nd class day 1.6 403.67 645.87
18 Coolie day 2 350.00 700.00
11 Bhisti day 1 350.00 350.00
Less for dark shade pigment [3.08+2.84 (for
tiles)]
874 Black colour dark shade pigment kilogram -5.92 70 -414.40
TOTAL 5244.67
Add 1 % Water charges on "W" 52.4467
TOTAL 5297.12
Add GST (multiplying factor 0.1405) on "X" 744.24
TOTAL 6041.36
Add 15 % Contractor's profit and overheads on "Y" 906.20
Total 6947.56
Add Cess @ 1% on "Z" 69.48
Cost of 10 sqm 7017.04
Cost of 1 sqm 701.7
Say 701.70
11.21 Providing and fixing 10 mm thick
acid and/or alkali
the direction resistant tiles
of Engineer-in- of approved
Charge.
make and colour using acid and/or alkali
11.21.1 In flooring
resisting mortar on a bed
bedding, and of 10 mm
joints filledthick
with
mortar 1:4 (1 acid proof cement : 4
11.21.1.1 Acid and alkali resistant tile coarse
sand)
Details of cost for 1 sqm.
MATERIAL
Acid proof tiles of size 300x300mm,
10mm thick = 11.11nos+
Add wastage and breakage @ 2.5% = 0.28 nos.
Total = 11.39 nos. Say 12 nos.
7077 Acid and alkali resistant tiles 300x300 mm size, 10 Nos 1.2 520 624.00
10 mm thick
9977 Carriage L.S. 6.24 2 12.48
10mm thick Cement mortar 1 : 4
(1 cement : 4 coarse sand)
3.9 Rate as per Item Number 3.9 of SH: Mortars cum 0.012 3548.00 42.58
9999 Mortar for pointing in acid/alkali resistant cement L.S. 40.43 2 80.86
Cement for slurry over bed @ 3.3kg per sqm
367 Portland Cement tonne 0.0033 4375 14.44
Difference of cost for using acid proof cement
instead of ordinary cement Add
7024 Acid Proof cement Deduct tonne 0.0079 7800 61.62
367 Portland Cement tonne -0.0079 4375 -34.56
LABOUR
23 Mason (brick layer) 1st class day 0.2 505.17 101.03
18 Coolie day 0.2 350.00 70.00
9988 Sundries including carriage of cement etc. L.S. 26.91 2 53.82
TOTAL 1026.27
Add 1 % Water charges on "W" 10.2627
TOTAL 1036.53
Add GST (multiplying factor 0.1405) on "X" 145.63
TOTAL 1182.16
Add 15 % Contractor's profit and overheads on "Y" 177.32
Total 1359.48
Add Cess @ 1% on "Z" 13.59
Cost of 1 sqm 1373.07
Say 1373.07
1373.10

11.21.2 In dado/skirting on 12 mm thick


mortar 1:4 (1
11.21.2.1 acidand
Acid proof cement
alkali : 4 coarse
resistant tile
sand) 11.21.2.1 Acid and alkali resistant tile
Details of cost for 1 sqm.
MATERIAL
Acid proof tiles of size 300x300mm,
10mm thick = 11.11nos+
Add wastage and breakage @ 2.5% = 0.28 nos.
Total = 11.39 nos. Say 12 nos.
7077 Acid and alkali resistant tiles 300x300 mm size, 10 Nos 1.2 520 624.00
10 mm thick
9977 Carriage of tiles L.S. 6.24 2 12.48
12mm thick Cement mortar 1 : 4
(1 cement : 4 coarse sand)
3.9 Rate as per Item Number 3.9 of SH: Mortars cum 0.014 3548.00 49.67
Difference of cost for using acid proof
cement instead of ordinary cement Add
7024 Acid Proof cement Deduct tonne 0.0086 7800 67.08
367 Portland Cement tonne -0.0086 4375 -37.63
9999 Mortar for pointing in acid proof cement L.S. 40.43 2 80.86
Acid proof cementfor slurry over plaster 3.3kg/sq
7024 Acid Proof cement tonne 0.0033 7800 25.74
LABOUR
23 Mason (brick layer) 1st class day 0.25 505.17 126.29
18 Coolie day 0.25 350.00 87.50
9988 Sundries including carriage of cement etc. L.S. 26.91 2 53.82
TOTAL 1089.81
Add 1 % Water charges on "W" 10.8981
TOTAL 1100.71
Add GST (multiplying factor 0.1405) on "X" 154.65
TOTAL 1255.36
Add 15 % Contractor's profit and overheads on "Y" 188.30
Total 1443.66
Add Cess @ 1% on "Z" 14.44
Cost of 1 sqm 1458.10
Say 1458.1
1458.10

11.22 Tile work in skirting, risers of steps


and dadoofup
pigment to 2 m height
matching shadeover 12 mm thick
complete.
bed of cement mortar 1:3 (1 cement
11.22.1 Marble tiles (polished) Raj Nagar :3
coarse sand) and jointed with grey cement
11.22.1. 8 mm thick
1 Details of cost for 1 sqm.
MATERIAL
2751 8 mm thick marble tiles (polished) Raj Nagar sqm 1.061 400 424.40
including wastage
9977 Carriage of tiles L.S. 3.9 2 7.80
12mm thick Cement mortar 1:3 (1 cement :
3 coarse sand)
3.8 Rate as per Item Number 3.8 of SH: Mortars cum 0.014 4129.00 57.81
9999 Mortar for pointing in white cement Cement for L.S. 25.35 2 50.70
slurry @ 3.3kg/sqm
367 Portland Cement tonne 0.0033 4375 14.44
9999 Pigment L.S. 2.08 2 4.16
LABOUR
23 Mason (brick layer) 1st class day 0.25 505.17 126.29
18 Coolie day 0.25 350.00 87.50
9988 Sundries including carriage of cement etc. L.S. 16.9 2 33.80
TOTAL 806.90
Add 1 % Water charges on "W" 8.069
TOTAL 814.97
Add GST (multiplying factor 0.1405) on "X" 114.50
TOTAL 929.47
Add 15 % Contractor's profit and overheads on "Y" 139.42
Total 1068.89
Add Cess @ 1% on "Z" 10.69
Cost of 1 sqm 1079.58
Say 1079.58
1079.60

11.23 Marble stone flooring with 18 mm thick


11.23.1 marble stone,
Makrana whiteassecond
per sample of marble
quality
approved by Engineer-in-charge, over 20
mm (average) thick base of cement mortar
Details of cost for 10 sqm.
MATERIAL
20mm thick marble slab = 10.00sqm.+ Add for
wastage 15% = 1.50sqm.
Total = 11.50sqm.
6001 White marble slab Makrana second quality plain sqm 11.5 1430 16445.00
veined 18 mm thick
Base Cement mortar 1 : 4 (1 cement : 4 coarse
sand)
3.9 Rate as per Item Number 3.9 of cum 0.224 3548.00 794.75
SH: Mortars
Cement for slurry @4.4kg/sqm. (i) for bedding =
44 kg+ (ii) for jointing = 6 kg. Total = 50 kg
367 Portland Cement tonne 0.05 4375 218.75
9977 Carriage of marble slab L.S. 26.91 2 53.82
LABOUR
(for finishing, polishing and fixing)
23 Mason (brick layer) 1st class day 1.2 505.17 606.20
17 Beldar day 1 350.00 350.00
18 Coolie day 1 350.00 350.00
37 Skilled Beldar (for floor rubbing etc.) day 5 350.00 1750.00
13 Machine for rubbing of floors day 4 300 1200.00
9988 Sundries and carriage of cement etc. L.S. 134.55 2 269.10
TOTAL 22037.62
Add 1 % Water charges on "W" 220.3762
TOTAL 22258.00
Add GST (multiplying factor 0.1405) on "X" 3127.25
TOTAL 25385.25
Add 15 % Contractor's profit and overheads on "Y" 3807.79
Total 29193.04
Add Cess @ 1% on "Z" 291.93
Cost of 10 sqm. 29484.97
Cost of 1 sqm. 2948.5
Say 2948.50

11.23.2 Raj Nagar plain


Details of cost for 10 sqm.
MATERIAL
20mm thick marble slab = 10.00sqm.+ Add for
wastage 15% = 1.50sqm.
Total = 11.50sqm.
7071 White marble Raj Nagar plain 18 mm thick upto sqm 11.5 600 6900.00
0.50 sqm area
Base Cement mortar 1 : 4 (1 cement : 4 coarse
sand)
3.9 Rate as per Item Number 3.9 of SH: Mortars cum 0.224 3548.00 794.75
Cement for slurry @, 4.4kg sqm. (i) for bedding
= 44 kg+ (ii) for jointing = 6 kg. Total = 50 kg
367 Portland Cement tonne 0.05 4375 218.75
9977 Carriage of marble slab L.S. 26.91 2 53.82
LABOUR
(for finishing, polishing and fixing)
23 Mason (brick layer) 1st class day 1.2 505.17 606.20
17 Beldar day 1 350.00 350.00
18 Coolie day 1 350.00 350.00
37 Skilled Beldar (for floor rubbing etc.) day 5 350.00 1750.00
13 Machine for rubbing of floors day 4 300 1200.00
9988 Sundries and carriage of cement etc. L.S. 134.55 2 269.10
TOTAL 12492.62
Add 1 % Water charges on "W" 124.9262
TOTAL 12617.55
Add GST (multiplying factor 0.1405) on "X" 1772.77
TOTAL 14390.32
Add 15 % Contractor's profit and overheads on "Y" 2158.55
Total 16548.87
Add Cess @ 1% on "Z" 165.49
Cost of 10 sqm. 16714.36
Cost of 1 sqm. 1671.44
Say 1671.40

11.23.3 Agaria White


Details of cost for 10 sqm.
MATERIAL
20mm thick marble slab = 10.00sqm.+ Add for
wastage 15% = 1.50sqm.
Total = 11.50sqm.
7850 Agaria White marble slab plain 18mm thick sqm 11.5 1100 12650.00
Base Cement mortar 1 : 4 (1 cement : 4 coarse
sand)
3.9 Rate as per Item Number 3.9 of cum 0.224 3548.00 794.75
SH: Mortars
Cement for slurry @, 4.4kg sqm. (i) for bedding
= 44 kg+ (ii) for jointing = 6 kg. Total = 50 kg
367 Portland Cement tonne 0.05 4375 218.75
9977 Carriage of marble slab L.S. 26.91 2 53.82
LABOUR
(for finishing, polishing and fixing)
23 Mason (brick layer) 1st class day 1.2 505.17 606.20
17 Beldar day 1 350.00 350.00
18 Coolie day 1 350.00 350.00
37 Skilled Beldar (for floor rubbing etc.) day 5 350.00 1750.00
13 Machine for rubbing of floors day 4 300 1200.00
9988 Sundries and carriage of cement etc. L.S. 134.55 2 269.10
TOTAL 18242.62
Add 1 % Water charges on "W" 182.4262
TOTAL 18425.05
Add GST (multiplying factor 0.1405) on "X" 2588.72
TOTAL 21013.77
Add 15 % Contractor's profit and overheads on "Y" 3152.06
Total 24165.83
Add Cess @ 1% on "Z" 241.66
Cost of 10 sqm. 24407.49
Cost of 1 sqm. 2440.75
Say 2440.80

11.23.4 Black Zebra


Details of cost for 10 sqm.
MATERIAL
20mm thick marble slab = 10.00sqm.+ Add for
wastage 15% = 1.50sqm.
Total = 11.50sqm.
6019 Black Zebra marble slab plain 18mm thick Base sqm 11.5 900 10350.00
Cement mortar 1 : 4 (1 cement : 4 coarse sand)
3.9 Rate as per Item Number 3.9 of SH: Mortars cum 0.224 3548.00 794.75
Cement for slurry @, 4.4kg sqm. (i) for bedding
= 44 kg+ (ii) for jointing = 6 kg. Total = 50 kg
367 Portland Cement tonne 0.05 4375 218.75
9977 Carriage of marble slab L.S. 26.91 2 53.82
LABOUR
(for finishing, polishing and fixing)
23 Mason (brick layer) 1st class day 1.2 505.17 606.20
17 Beldar day 1 350.00 350.00
18 Coolie day 1 350.00 350.00
37 Skilled Beldar (for floor rubbing etc.) day 5 350.00 1750.00
13 Machine for rubbing of floors day 4 300 1200.00
9988 Sundries and carriage of cement etc. L.S. 134.55 2 269.10
TOTAL 15942.62
Add 1 % Water charges on "W" 159.4262
TOTAL 16102.05
Add GST (multiplying factor 0.1405) on "X" 2262.34
TOTAL 18364.39
Add 15 % Contractor's profit and overheads on "Y" 2754.66
Total 21119.05
Add Cess @ 1% on "Z" 211.19
Cost of 10 sqm. 21330.24
Cost of 1 sqm. 2133.02
Say 2133.00
11.23.5 Udaipur green marble
Details of cost for 10 sqm.
MATERIAL
20mm thick marble slab = 10.00sqm.+ Add for
wastage 15% = 1.50sqm.
Total = 11.50sqm.
6010 Udaypur green marble slab plain 18mm thick sqm 11.5 620 7130.00
Base Cement mortar 1 : 4 (1 cement : 4 coarse
sand)
3.9 Rate as per Item Number 3.9 of SH: Mortars cum 0.224 3548.00 794.75
Cement for slurry @, 4.4kg sqm. (i) for bedding
= 44 kg+ (ii) for jointing = 6 kg. Total = 50 kg
367 Portland Cement tonne 0.05 5700 285.00
9977 Carriage of marble slab L.S. 26.91 2 53.82
LABOUR
(for finishing, polishing and fixing)
23 Mason (brick layer) 1st class day 1.2 505.17 606.20
17 Beldar day 1 350.00 350.00
18 Coolie day 1 350.00 350.00
37 Skilled Beldar (for floor rubbing etc.) day 5 350.00 1750.00
13 Machine for rubbing of floors day 4 300 1200.00
9988 Sundries and carriage of cement etc. L.S. 134.55 2 269.10
TOTAL 12788.87
Add 1 % Water charges on "W" 127.8887
TOTAL 12916.76
Add GST (multiplying factor 0.1405) on "X" 1814.80
TOTAL 14731.56
Add 15 % Contractor's profit and overheads on "Y" 2209.73
Total 16941.29
Add Cess @ 1% on "Z" 169.41
Cost of 10 sqm. 17110.70
Cost of 1 sqm. 1711.07
Say 1711.10

11.23.6 Pink plain marble


Details of cost for 10 sqm.
MATERIAL
20mm thick marble slab = 10.00sqm.+ Add for
wastage 15% = 1.50sqm.
Total = 11.50sqm.
6007 Pink marble slab plain 18mm thick Base sqm 11.5 645 7417.50
Cement mortar 1 : 4 (1 cement : 4 coarse sand)
3.9 Rate as per Item Number 3.9 of SH: Mortars cum 0.224 3548.00 794.75
Cement for slurry @, 4.4kg sqm. (i) for bedding
= 44 kg+ (ii) for jointing = 6 kg. Total = 50 kg
367 Portland Cement tonne 0.05 4375 218.75
9977 Carriage of marble slab L.S. 26.91 2 53.82
LABOUR
(for finishing, polishing and fixing)
23 Mason (brick layer) 1st class day 1.2 505.17 606.20
17 Beldar day 1 350.00 350.00
18 Coolie day 1 350.00 350.00
37 Skilled Beldar (for floor rubbing etc.) day 5 350.00 1750.00
13 Machine for rubbing of floors day 4 300 1200.00
9988 Sundries and carriage of cement etc. L.S. 134.55 2 269.10
TOTAL 13010.12
Add 1 % Water charges on "W" 130.1012
TOTAL 13140.22
Add GST (multiplying factor 0.1405) on "X" 1846.20
TOTAL 14986.42
Add 15 % Contractor's profit and overheads on "Y" 2247.96
Total 17234.38
Add Cess @ 1% on "Z" 172.34
Cost of 10 sqm. 17406.72
Cost of 1 sqm. 1740.67
Say 1740.70

11.24 Extra for pre finished nosing to


treads of steps of marble stone.
Details of cost for 10m
LABOUR
26 Mason (for ornamental stone work) 1st class day 2 505.17 1010.34
17 Beldar day 1.5 350.00 525.00
37 Skilled Beldar (for floor rubbing etc.) day 2.5 350.00 875.00
9999 Sundries L.S. 53.82 2 107.64
TOTAL 2517.98
Add 1 % Water charges on "W" 25.1798
TOTAL 2543.16
Add GST (multiplying factor 0.1405) on "X" 357.31
TOTAL 2900.47
Add 15 % Contractor's profit and overheads on "Y" 435.07
Total 3335.54
Add Cess @ 1% on "Z" 33.36
Cost of 10 sqm. 3368.90
Cost of 1 sqm. 336.89
Say 336.90

11.25 Extra for marble stone flooring in


treads
Details ofofcost
steps and risers using single length
for 10sqm.
up to
LABOUR
2.00 metre.
23 Mason (brick layer) 1st class day 1.95 505.17 985.08
17 Beldar day 1.4 350.00 490.00
18 Coolie day 0.75 350.00 262.50
37 Skilled Beldar (for floor rubbing etc.) day 3.18 350.00 1113.00
9999 Sundries L.S. 26.91 2 53.82
TOTAL 2904.40
Add 1 % Water charges on "W" 29.044
TOTAL 2933.44
Add GST (multiplying factor 0.1405) on "X" 412.15
TOTAL 3345.59
Add 15 % Contractor's profit and overheads on "Y" 501.84
Total 3847.43
Add Cess @ 1% on "Z" 38.47
Cost of 10 sqm. 3885.90
Cost of 1 sqm. 388.59
Say 388.60

11.26 Kota stone slab flooring over 20 mm


(average)
cement : 4thick base
coarse laid :over and jointed
sand)
with grey cement slurry mixed with pigment
11.26.1 25 mm thick
to match the shade of the slab, including
Details of cost for 10sqm.
MATERIAL
1168 Kota stone slab 20 mm to 25 mm thick sqm 11.5 350 4025.00
(semi-polished) including 15% wastage
2216 Carriage of Stone blocks white & red sand tonne 0.67 94.34 63.21
stone & kota stone slab
Cement mortar 1 : 4 (1 cement : 4 coarse sand)
3.9 Rate as per Item Number 3.9 of SH: Mortars cum 0.224 3548.00 794.75
Cement for slurry-(i) for bedding = 44kg+
(ii) for joints = 20 kg.Total = 64 kg. or 0.064
tonne
367 Portland Cement tonne 0.064 4375 280.00
2209 Carriage of Cement tonne 0.064 94.34 6.04
874 Black colour dark shade pigment kilogram 4.5 70 315.00
Removing white or colour wash by scrapping
and sand papering and preparing the surface
smooth including necessary repairs to
scratches etc. complete
24 Mason (brick layer) 2nd class day 1.2 403.67 484.40
17 Beldar day 1 350.00 350.00
18 Coolie day 1 350.00 350.00
37 Skilled Beldar (for floor rubbing etc.) day 5 350.00 1750.00
13 Machine for rubbing of floors day 4 300 1200.00
9999 Sundries L.S. 208.13 2 416.26
TOTAL 10034.66
Add 1 % Water charges on "W" 100.3466
TOTAL 10135.01
Add GST (multiplying factor 0.1405) on "X" 1423.97
TOTAL 11558.98
Add 15 % Contractor's profit and overheads on "Y" 1733.85
Total 13292.83
Add Cess @ 1% on "Z" 132.93
Cost of 10 sqm. 13425.76
Cost of 1 sqm. 1342.58
Say 1342.60

11.27 Kota stone slabs 20 mm thick in


risers
slabs, of steps, skirting,
including rubbing dado and pillars laid
and polishing
on 12 mm
complete. (average) thick cement mortar 1:3
(1 cement: 3 coarse sand) and jointed with
Details of cost for 10sqm.

MATERIAL
1168 Kota stone slab 20 mm to 25 mm thick sqm 11.5 350 4025.00
(semi-polished) including 15% wastage
2216 Carriage of Stone blocks white & red sand tonne 0.67 94.34 63.21
stone & kota stone slab
Cement mortar 1:3 (1 cement : 3 coarse sand)
3.8 Rate as per Item Number 3.8 of SH: Mortars cum 0.144 4129.00 594.58
367 Portland Cement for slurry tonne 0.064 4375 280.00
2209 Carriage of Cement tonne 0.064 94.34 6.04
874 Black colour dark shade pigment kilogram 4.5 70 315.00
LABOUR
24 Mason (brick layer) 2nd class day 3 403.67 1211.01
17 Beldar day 3 350.00 1050.00
18 Coolie day 1 350.00 350.00
37 Skilled Beldar (for floor rubbing etc.) day 7 350.00 2450.00
9999 Sundries L.S. 174.98 2 349.96
TOTAL 10694.80
Add 1 % Water charges on "W" 106.948
TOTAL 10801.75
Add GST (multiplying factor 0.1405) on "X" 1517.65
TOTAL 12319.40
Add 15 % Contractor's profit and overheads on "Y" 1847.91
Total 14167.31
Add Cess @ 1% on "Z" 141.67
Cost of 10 sqm. 14308.98
Cost of 1 sqm. 1430.9
Say 1430.90

11.28 40 mm thick fine dressed stone


flooring
11.28.1 over
Red 20sand
mm stone
(average) thick base of
cement mortar 1:5 (1 cement : 5 coarse
sand) with joints finished flush.
Details of cost for 10sqm.
MATERIAL
Finished work = 10 sqm
Add for wastage @ 10% = 1 sqm
Total = 11 sqm
1164 Red sand stone slab 40 mmthick (un-dressed) sqm 11 400 4400.00
9977 Carriage L.S. 34.06 2 68.12
Cement mortar 1 : 5 (1 cement :
5 coarse sand)
(i) for beading = 0.224 cum+ (ii) for joining =
0.026 cum.
Total=0.250cum.
3.1 Rate as per Item Number 3.10 of SH: Mortars cum 0.25 3235.20 808.80
LABOUR
23 Mason (brick layer) 1st class day 3.1 505.17 1566.03
10 Bandhani day 1.1 350.00 385.00
18 Coolie day 0.55 350.00 192.50
11 Bhisti day 0.27 350.00 94.50
9999 Sundries L.S. 10.79 2 21.58
TOTAL 7536.53
Add 1 % Water charges on "W" 75.3653
TOTAL 7611.90
Add GST (multiplying factor 0.1405) on "X" 1069.47
TOTAL 8681.37
Add 15 % Contractor's profit and overheads on "Y" 1302.20
Total 9983.57
Add Cess @ 1% on "Z" 99.84
Cost of 10 sqm. 10083.41
Cost of 1 sqm. 1008.34
Say 1008.30

11.28.2 White sand stone


Details of cost for 10sqm.
MATERIAL
Finished work = 10 sqm
Add for wastage @ 10% = 1 sqm
Total = 11 sqm
1165 White sand stone slab 40 mm thick (un- sqm 11 400 4400.00
dressed)
9977 Carriage L.S. 34.06 2 68.12
Cement mortar 1 : 5 (1 cement : 5 coarse sand)
(i) for beading = 0.224 cum+ (ii) for joining =
0.026 cum.
Total=0.250cum.
3.1 Rate as per Item Number 3.10 of SH: Mortars cum 0.25 3235.20 808.80
LABOUR
23 Mason (brick layer) 1st class day 3.1 505.17 1566.03
10 Bandhani day 1.1 350.00 385.00
18 Coolie day 0.55 350.00 192.50
11 Bhisti day 0.27 350.00 94.50
9999 Sundries L.S. 10.79 2 21.58
TOTAL 7536.53
Add 1 % Water charges on "W" 75.3653
TOTAL 7611.90
Add GST (multiplying factor 0.1405) on "X" 1069.47
TOTAL 8681.37
Add 15 % Contractor's profit and overheads on "Y" 1302.20
Total 9983.57
Add Cess @ 1% on "Z" 99.84
Cost of 10 sqm. 10083.41
Cost of 1 sqm. 1008.34
Say 1008.30

11.29 40 mm thick fine dressed stone


flooring over 20 mm (average) thick base of
cement mortar 1:5 (1 cement : 5 coarse
sand), including pointing with cement mortar
shade of stone.
11.29.1 Red sand stone
Details of cost for 10sqm.
MATERIAL
Finished work = 10 sqm
Add for wastage @ 10% = 1 sqm
Total = 11 sqm
1164 Red sand stone slab 40 mmthick (un-dressed) sqm 11 400 4400.00
9977 Carriage L.S. 34.06 2 68.12
Cement mortar 1 : 5 (1 cement :
5 coarse sand)
(i) for beading = 0.224 cum+ (ii) for joining =
0.026 cum.
Total=0.250cum.
3.1 Rate as per Item Number 3.10 of SH: Mortars cum 0.25 3235.20 808.80
Cement mortar 1:2 (1 Cement : 2 stone dust for
pointing)
3.12 Rate as per Item Number 3.12 of SH: Mortars cum 0.023 4552.80 104.71
LABOUR
23 Mason (brick layer) 1st class day 3.9 505.17 1970.16
10 Bandhani day 1.1 350.00 385.00
18 Coolie day 1.4 350.00 490.00
11 Bhisti day 0.55 350.00 192.50
9999 Sundries L.S. 26.91 2 53.82
TOTAL 8473.11
Add 1 % Water charges on "W" 84.7311
TOTAL 8557.84
Add GST (multiplying factor 0.1405) on "X" 1202.38
TOTAL 9760.22
Add 15 % Contractor's profit and overheads on "Y" 1464.03
Total 11224.25
Add Cess @ 1% on "Z" 112.24
Cost of 10 sqm. 11336.49
Cost of 1 sqm. 1133.65
Say 1133.70

11.29.2 White sand stone


Details of cost for 10sqm.
MATERIAL
Finished work = 10 sqm
Add for wastage @ 10% = 1 sqm
Total = 11 sqm
1165 White sand stone slab 40 mm thick (un- sqm 11 400 4400.00
dressed)
9977 Carriage L.S. 34.06 2 68.12
Cement mortar 1 : 5 (1 cement :
5 coarse sand)
(i) for beading = 0.224 cum+ (ii) for joining =
0.026 cum.
Total=0.250cum.
3.1 Rate as per Item Number 3.10 of SH: Mortars cum 0.25 3235.20 808.80
Cement mortar 1:2 (1 Cement : 2 stone dust for
pointing)
3.12 Rate as per Item Number 3.12 of SH: Mortars cum 0.023 4552.80 104.71
LABOUR
23 Mason (brick layer) 1st class day 3.9 505.17 1970.16
10 Bandhani day 1.1 350.00 385.00
18 Coolie day 1.4 350.00 490.00
11 Bhisti day 0.55 350.00 192.50
9999 Sundries L.S. 26.91 2 53.82
TOTAL 8473.11
Add 1 % Water charges on "W" 84.7311
TOTAL 8557.84
Add GST (multiplying factor 0.1405) on "X" 1202.38
TOTAL 9760.22
Add 15 % Contractor's profit and overheads on "Y" 1464.03
Total 11224.25
Add Cess @ 1% on "Z" 112.24
Cost of 10 sqm. 11336.49
Cost of 1 sqm. 1133.65
Say 1133.70

11.30 40 mm thick rubbed stone flooring


over 20 mm
11.30.1 Red (average) thick base of cement
sand stone
mortar 1:5 (1 cement
Details of cost for 10sqm.
: 5 coarse sand) with
joints 3 mm thick, side buttered with cement
MATERIAL
Finished work = 10 sqm
Add for wastage @ 10% = 1 sqm
Total = 11 sqm
1164 Red sand stone slab 40 mmthick (un-dressed) sqm 11 400 4400.00
9977 Carriage L.S. 34.06 2 68.12
Cement mortar 1 : 5 (1 cement : 5 coarse sand)
(i) for beading = 0.224 cum+ (ii) for joining =
0.026 cum.
Total=0.250cum.
3.1 Rate as per Item Number 3.10 of SH: Mortars cum 0.25 3235.20 808.80
Cement mortar 1:2 (1 Cement : 2 stone dust for
pointing)
3.12 Rate as per Item Number 3.12 of SH: Mortars cum 0.023 4552.80 104.71
LABOUR
23 Mason (brick layer) 1st class day 3.9 505.17 1970.16
10 Bandhani day 1.1 350.00 385.00
18 Coolie day 1.4 350.00 490.00
11 Bhisti day 0.55 350.00 192.50
9999 Sundries L.S. 26.91 2 53.82
Labour for rubbing of stone
37 Skilled Beldar (for floor rubbing etc.) day 0.618 350.00 216.30
13 Machine for rubbing of floors day 0.988 300 296.40
TOTAL 8985.81
Add 1 % Water charges on "W" 89.8581
TOTAL 9075.67
Add GST (multiplying factor 0.1405) on "X" 1275.13
TOTAL 10350.80
Add 15 % Contractor's profit and overheads on "Y" 1552.62
Total 11903.42
Add Cess @ 1% on "Z" 119.03
Cost of 10 sqm. 12022.45
Cost of 1 sqm. 1202.24
Say 1202.20

11.30.2 White sand stone


Details of cost for 10sqm.
MATERIAL
Finished work = 10 sqm
Add for wastage @ 10% = 1 sqm
Total = 11 sqm
1165 White sand stone slab 40 mm thick (un- sqm 11 400 4400.00
dressed)
9977 Carriage L.S. 34.06 2 68.12
Cement mortar 1 : 5 (1 cement :
5 coarse sand)
(i) for beading = 0.224 cum+ (ii) for joining =
0.026 cum.
Total=0.250cum.
3.1 Rate as per Item Number 3.10 of SH: Mortars cum 0.25 3235.20 808.80
Cement mortar 1:2 (1 Cement : 2 stone dust for
pointing)
3.12 Rate as per Item Number 3.12 of SH: Mortars cum 0.023 4552.80 104.71
LABOUR 0
23 Mason (brick layer) 1st class day 3.9 505.17 1970.16
10 Bandhani day 1.1 350.00 385.00
18 Coolie day 1.4 350.00 490.00
11 Bhisti day 0.55 350.00 192.50
9999 Sundries L.S. 26.91 2 53.82
Labour for rubbing of stone
37 Skilled Beldar (for floor rubbing etc.) day 0.618 350.00 216.30
13 Machine for rubbing of floors day 0.988 300 296.40
TOTAL 8985.81
Add 1 % Water charges on "W" 89.8581
TOTAL 9075.67
Add GST (multiplying factor 0.1405) on "X" 1275.13
TOTAL 10350.80
Add 15 % Contractor's profit and overheads on 1552.62
"Y" 11903.42
Total 119.03
Add Cess @ 1% on "Z" 12022.45
Cost of 10 sqm. 1202.24
Cost of 1 sqm. 1202.20
Say

11.31 Extra for pre finished nosing in


treads
Details ofofcost
steps of Kota stone/ sand stone
for 10m
slab.
LABOUR
26 Mason (for ornamental stone work) 1st class day 1.5 505.17 757.76
TOTAL 757.76
Add 1 % Water charges on "W" 7.5776
TOTAL 765.34
Add GST (multiplying factor 0.1405) on "X" 107.53
TOTAL 872.87
Add 15 % Contractor's profit and overheads on "Y" 130.93
Total 1003.80
Add Cess @ 1% on "Z" 10.04
Cost of 10 sqm. 1013.84
Cost of 1 sqm. 101.38
Say 101.40
11.32 Extra for Kota stone/ sand stone in
treads of steps
length up and
to 1.05 risers using single
metre.
Details of cost for 10sqm.
LABOUR
24 Mason (brick layer) 2nd class day 0.2 403.67 80.73
17 Beldar day 0.2 350.00 70.00
TOTAL 150.73
Add 1 % Water charges on "W" 1.5073
TOTAL 152.24
Add GST (multiplying factor 0.1405) on "X" 21.39
TOTAL 173.63
Add 15 % Contractor's profit and overheads on "Y" 26.04
Total 199.67
Add Cess @ 1% on "Z" 2.00
Cost of 10 sqm. 201.67
Cost of 1 sqm. 20.17
Say 20.20

11.33 25 mm wooden planking, tongued


and grooved
11.33.1 in flooring,
Second including
class teak woodfixing with
iron screws complete with :
Details of cost for 2.5x4=10 sqm.
MATERIAL
Second class indian teak wood No of joints = 4000/138
= 28.97 Total = (29-1) = 28 nos
Qty of wood required 2.5(4+0.336)x0.025 = 0.271 cum
Add wastage @ 10 % = 0.027 cum
Total = 0.2981 cum = 298.1 cudm
1190 Second class teak wood in planks 10 cudm 29.81 791 23579.71
1231 Extra for selected planks of second class 10 cudm 29.81 150 4471.50
teakwood
2204 Carriage of Timber cum 0.2981 121.29 36.16
682 Oxidised mild steel screws 50 mm 100 Nos 2 76 152.00
(slotted counters sunk head type)
LABOUR
14 Carpenter 1st class day 2.68 505.17 1353.86
17 Beldar day 1.35 350.00 472.50
9999 Sundries for glue etc. L.S. 33.28 2 66.56
TOTAL 30132.29
Add 1 % Water charges on "W" 301.3229
TOTAL 30433.61
Add GST (multiplying factor 0.1405) on "X" 4275.92
TOTAL 34709.53
Add 15 % Contractor's profit and overheads on "Y" 5206.43
Total 39915.96
Add Cess @ 1% on "Z" 399.16
Cost of 10 sqm. 40315.12
Cost of 1 sqm. 4031.51
Say 4031.50

11.33.2 Second class deodar wood


Details of cost for 2.5x4=10 sqm.
MATERIAL
First class deodar wood planks
No of joints = 4000/138 = 28.97
Total = (29-1) = 28 nos
Qty of wood required
2.5(4+0.336)x0.025 = 0.271 cum
Add wastage @ 10 % = 0.027 cum
Total = 0.2981 cum = 298.1 cudm
1194 Second class deodar wood in planks 10 cudm 29.81 500 14905.00
2500 Extra for selected planks of second class 10 cudm 29.81 110 3279.10
deodarwood
2204 Carriage of Timber cum 0.2981 121.29 36.16
682 Oxidised mild steel screws 50 mm 100 Nos 2 76 152.00
(slotted counters sunk head type)
LABOUR
14 Carpenter 1st class day 2.16 505.17 1091.17
17 Beldar day 1.08 350.00 378.00
9999 Sundries for glue etc. L.S. 26.91 2 53.82
TOTAL 19895.25
Add 1 % Water charges on "W" 198.9525
TOTAL 20094.20
Add GST (multiplying factor 0.1405) on "X" 2823.24
TOTAL 22917.44
Add 15 % Contractor's profit and overheads on "Y" 3437.62
Total 26355.06
Add Cess @ 1% on "Z" 263.55
Cost of 10 sqm. 26618.61
Cost of 1 sqm. 2661.86
Say 2661.90

11.34 38 mm thick wood block flooring of


first class
Details teak
of cost wood laid over 25 mm thick
for 1sqm.
leveling layer of cement concrete 1:2:4 (1
cement : 2 coarse sand : 4 graded stone
Bitumen blown type
i) For bed layer @ 2.45kg/sqm. = 2.45kg+ ii) For
dipping blocks L.S. = 2.00Kg.
Total = 4.45kg.
313 Blown type petroleum bitumen of penetration tonne 0.0044 53000 233.20
85/25 of approved quality
2211 Carriage of Tar bitumen tonne 0.0044 106.13 0.47
1st class teal wood in scanting for wooden
blocks
1 sqm x 0.038 m = 0.038 cum
Add 10 % wastage = 0.0038 cum
Total = 0.0418 cum or 41.8 cudm
1187 First class teak wood in scantling 10 cudm 4.18 880 3678.40
2204 Carriage of Timber cum 0.0418 121.29 5.07
LABOUR
14 Carpenter 1st class day 1.75 505.17 884.05
17 Beldar day 2.25 350.00 787.50
18 Coolie day 1.5 350.00 525.00
30 Mistry day 0.1 505.17 50.52
9999 Sundries such as fuel, kerosene oil, sand paper L.S. 80.73 2 161.46
etc.
TOTAL 6325.67
Add 1 % Water charges on "W" 63.2567
TOTAL 6388.93
Add GST (multiplying factor 0.1405) on "X" 897.64
TOTAL 7286.57
Add 15 % Contractor's profit and overheads on "Y" 1092.99
Total 8379.56
Add Cess @ 1% on "Z" 83.80
Cost for 1 sqm. 8463.36
Say 8463.36
8463.40

11.35 Providing and fixing M.S. angle


50x50x5
approvedmm to act
primer on as nosingsurface
exposed with lugs of
etc.
M.S. flat 10x5 mm, 10 cm long, forked at end
complete.
60cm apart (minimum three lugs to be
Details of cost for 3m (11.40+0.24kg
= 11.64kg)
MATERIAL
Angle iron 50x50x5 mm =3 m
Add wastage @ 5% = 0.15 m
Total =3.15 m @ 3.80 kg per m =
11.97 kg Say 0.12 qtl
1007 Structurals such as tees,angles channels and quintal 0.12 5300 636.00
R.S. joists
Lugs 10x5 mm flat = 6x0.10 = 0.60 m@
0.40 kg per m = 0.24 kg
Add wastage @ 5% = 0.012 kg
Total 0.252 kg or 0.0025 qtl
1008 Flats upto 10 mm in thickness quintal 0.0025 5300 13.25
2205 Carriage of Steel tonne 0.016 94.34 1.51
1215 Welding by electric plant 6cm (lugs) cm 6 2 12.00
9999 Sundries L.S. 9.1 2 18.20
LABOUR
13 Blacksmith 2nd class day 0.09 403.67 36.33
23 Mason (brick layer) 1st class day 0.45 505.17 227.33
17 Beldar day 0.25 350.00 87.50
Priming coat 3x0.20 = 0.60 sqm
13.50.3 Rate as per item no 13.50.3 of SH : Finishing sqm 0.6 33.3 19.98
TOTAL 1052.10
Add 1 % Water charges on "W-A" 1032.12 10.3212
TOTAL
Add GST (multiplying factor 0.1405) on "X-A" 1042.44 146.46
TOTAL
Add 15 % Contractor's profit and overheads on"Y-A" 1188.90 178.34
Total
Add Cess @ 1% on "Z-A" 1367.24 13.67
Cost for 11.64 kg. 1400.89
Cost per 1 Kg. 140.09
Say 140.10

11.37 Providing and laying Ceramic


glazed
matching floor tiles ofetc.,
pigment sizecomplete.
300x300 mm
(thickness to be specified
Details of cost for 1 sqm
by the
manufacturer) of 1st quality conforming to
MATERIAL
Glazed Ceramic floor tiles 300x300 mm size =
1.000 sqm
Add for wastage & breakage @ 2.5 %
= 0.025 sqm
Total = 1.025 sqm
7801 Ceramic Glazed Tiles Ist quality 300 x 300mm in Sq.m. 1.025 400 410.00
all shades and designs of White, Ivory, grey,
Fuem Red brown etc.
9977 Carriage of tiles L.S. 6.24 2 12.48
20 mm thick Cement mortar 1 : 4
(1 cement : 4 coarse sand)
3.9 Rate as per Item Number 3.9 of SH: Mortars cum 0.024 3548.00 85.15
9999 Mortar for pointing in white cement L.S. 20.2 2 40.40
Cement for slurry over bed @ 3.3 kg per sqm
367 Portland Cement tonne 0.0033 4375 14.44
LABOUR
23 Mason (brick layer) 1st class day 0.2 505.17 101.03
18 Coolie day 0.2 350.00 70.00
9988 Sundries including carriage of cement etc L.S. 26.91 2 53.82
TOTAL 787.32
Add 1 % Water charges on "W" 7.8732
TOTAL 795.19
Add GST (multiplying factor 0.1405) on "X" 111.72
TOTAL 906.91
Add 15 % Contractor's profit and overheads on "Y" 136.04
Total 1042.95
Add Cess @ 1% on "Z" 10.43
Cost for 1 sqm 1053.38
Say 1053.38
1053.40

11.37A Providing and fixing 1st quality ceramic


glazed floor tiles conforming to IS : 15622
(thickness to be specified by the
Detail of Cost for 1.00 Sqm Material
manufacturer ) of approved make in all

7801 Glazed Ceramic Floor Tile = 1.00 Sqm Add for sqm 1.025 400 410.00
wastage and breakage @2.5%
= 0.025 Sqm =1.025 Sqm
9999 Carriage of Tiles L.S. 6.24 2 12.48
3.8 Cement mortar 1:3 (1 Cement: 3 Coarse Sand) cum 0.014 4129.00 57.81
9999 Mortar for pointing in white cement L.S. 3.64 2 7.28
367 Cement for slurry over bed @3.3 Kg/Sqm tonne 0.0033 4375 14.44
Labour
23 Mason 1st Class day 0.25 505.17 126.29
18 Coolie day 0.25 350.00 87.50
9999 Sundries includding carriage of Cement etc L.S. 26.91 2 53.82
Total 769.62
Add 1 % Water charges on "W" 7.6962
TOTAL 777.32
Add GST (multiplying factor 0.1405) on "X" 109.21
TOTAL 886.53
Add 15 % Contractor's profit and overheads on "Y" 132.98
Total 1019.51
Add Cess @ 1% on "Z" 10.20
Cost for 1 sqm 1029.71
Say 1029.71
1029.70

11.38 Providing and laying Ceramic


glazed
Details offloor tiles
cost for of size 300x300 mm
1 sqm
(thickness
MATERIAL
to be specified by the
manufacturer), of 1st quality conforming to IS
Glazed Ceramic floor tiles 300x300 mm size =
1.000 sqm
Add for wastage & breakage @ 2.5 %
= 0.025 sqm
Total = 1.025 sqm
7802 Ceramic Glazed Tiles Ist quality 300 x 300 in all sq.m. 1.025 350 358.75
shades designs except White, Ivory, Grey,
Fuem Red Brown etc.
9977 Carriage of tiles L.S. 6.24 2 12.48
785 Marble chips upto 4mm and downsize White & quintal 189 0.00
20 mm thick Cement mortar 1 : 4
(1 cement : 4 coarse sand)
3.9 Rate as per Item Number 3.9 of SH: Mortars cum 0.024 3548.00 85.15
9999 Mortar for pointing in white cement Cement for L.S. 20.2 2 40.40
slurry over bed @ 3.3 kg per
sqm
367 Portland Cement tonne 0.0033 4375 14.44
LABOUR
23 Mason (brick layer) 1st class day 0.2 505.17 101.03
18 Coolie day 0.2 350.00 70.00
9988 Sundries including carriage of cement etc L.S. 26.91 2 53.82
TOTAL 736.07
Add 1 % Water charges on "W" 7.3607
TOTAL 743.43
Add GST (multiplying factor 0.1405) on "X" 104.45
TOTAL 847.88
Add 15 % Contractor's profit and overheads on 127.18
Total 975.06
Add Cess @ 1% on "Z" 9.75
Cost for 1 sqm 984.81
Say 984.81
984.80
11.39 Providing and laying rectified
Glazed
Details of Ceramic floor tiles of size 300x300
cost for 1 sqm
mm or
MATERIAL
more (thickness to be specified by the
manufacturer), of 1st quality conforming to IS
Rectified Ceramic Glazed floor tiles 300x
300 mm size = 1.000 sqm
Add for wastage & breakage @ 2.5 %
= 0.025 sqm
Total = 1.025 sqm
7803 Rectified Ceramic Glazed Tiles Ist quality sq.m. 1.025 400 410.00
300x300mm or more in all shades designs
White, Ivory, Grey, Fuem Red Brown etc.
9977 Carriage of tiles L.S. 6.24 2 12.48
20 mm thick Cement mortar 1 : 4
(1 cement : 4 coarse sand)
3.9 Rate as per Item Number 3.9 of SH: Mortars cum 0.024 3548.00 85.15
9999 Mortar for pointing in white cement Cement for L.S. 13.47 2 26.94
slurry over bed @ 3.3 kg per
sqm
367 Portland Cement tonne 0.0033 4375 14.44
LABOUR
23 Mason (brick layer) 1st class day 0.2 505.17 101.03
18 Coolie day 0.2 350.00 70.00
9988 Sundries including carriage of cement etc L.S. 26.91 2 53.82
TOTAL 773.86
Add 1 % Water charges on "W" 7.7386
TOTAL 781.60
Add GST (multiplying factor 0.1405) on "X" 109.81
TOTAL 891.41
Add 15 % Contractor's profit and overheads on "Y" 133.71
Total 1025.12
Add Cess @ 1% on "Z" 10.25
Cost for 1 sqm 1035.37
Say 1035.37
1035.40

11.40 Providing and laying rectified


Glazed Ceramic floor tiles of size 300x300
mm or more (thickness to be specified by the
Details of cost for 1 sqm
manufacturer), of 1st quality conforming to IS
MATERIAL
Rectified Ceramic Glazed floor tiles
300x300 mm size or more = 1.000 sqm
Add for wastage & breakage @ 2.5 %
= 0.025 sqm
Total = 1.025 sqm
7804 Rectified Ceramic Glazed Tiles Ist quality sq.m. 1.025 450 461.25
300x300mm or more in all shades designs
except White, Ivory, Grey, Fuem Red Brown etc.
9977 Carriage of tiles L.S. 6.24 2 12.48
20 mm thick Cement mortar 1 : 4
(1 cement : 4 coarse sand)
3.9 Rate as per Item Number 3.9 of SH: Mortars cum 0.024 3548.00 85.15
9999 Mortar for pointing in white cement Cement for L.S. 13.47 2 26.94
slurry over bed @ 3.3 kg per
sqm
367 Portland Cement tonne 0.0033 4375 14.44
LABOUR
23 Mason (brick layer) 1st class day 0.2 505.17 101.03
18 Coolie day 0.2 350.00 70.00
9988 Sundries including carriage of cement etc L.S. 26.91 2 53.82
TOTAL 825.11
Add 1 % Water charges on "W" 8.2511
TOTAL 833.36
Add GST (multiplying factor 0.1405) on "X" 117.09
TOTAL 950.45
Add 15 % Contractor's profit and overheads on "Y" 142.57
Total 1093.02
Add Cess @ 1% on "Z" 10.93
Cost for 1 sqm 1103.95
Say 1103.95
1104.00

11.41 Providing and laying vitrified floor


tiles in different
11.41.1 Size of sizes
Tile (thickness
500x500 mm to be
specified by the manufacturer)
Details of cost for 1 sqm
with water
absorption less than 0.08% and conforming
MATERIAL
Vitrified floor tiles 50x50 cm size = 1.000 sqm
Add for wastage & breakage @ 2.5 %
= 0.025 sqm
Total = 1.025 sqm
8620 Vitrified floor tile 50x50 cm sqm 1.025 550 563.75
9977 Carriage of tiles L.S. 6.24 2 12.48
20 mm thick Cement mortar 1 : 4
(1 cement : 4 coarse sand)
3.9 Rate as per Item Number 3.9 of SH: Mortars cum 0.024 3548.00 85.15
9999 Mortar for pointing in white cement Cement for L.S. 3.64 2 7.28
slurry over bed @ 3.3 kg per
sqm
367 Portland Cement tonne 0.0033 4375 14.44
LABOUR
23 Mason (brick layer) 1st class day 0.2 505.17 101.03
18 Coolie day 0.2 350.00 70.00
9988 Sundries including carriage of cement etc L.S. 26.91 2 53.82
TOTAL 907.95
Add 1 % Water charges on "W" 9.0795
TOTAL 917.03
Add GST (multiplying factor 0.1405) on "X" 128.84
TOTAL 1045.87
Add 15 % Contractor's profit and overheads on "Y" 156.88
Total 1202.75
Add Cess @ 1% on "Z" 12.03
Cost for 1 sqm 1214.78
Say 1214.78
1214.80

11.41.2 Size of Tile 600x600 mm


Details of cost for 1 sqm
MATERIAL
Vitrified floor tiles 60x60 cm size = 1.000 sqm
Add for wastage & breakage @ 2.5 %
= 0.025 sqm
Total = 1.025 sqm
8621 Vitrified floor tile 60x60 cm sqm 1.025 750 768.75
9977 Carriage of tiles L.S. 6.24 2 12.48
20 mm thick Cement mortar 1 : 4
(1 cement : 4 coarse sand)
3.9 Rate as per Item Number 3.9 of SH: Mortars cum 0.024 3548.00 85.15
9999 Mortar for pointing in white cement Cement for L.S. 3.64 2 7.28
slurry over bed @ 3.3 kg per
sqm
367 Portland Cement tonne 0.0033 4375 14.44
LABOUR
23 Mason (brick layer) 1st class day 0.2 505.17 101.03
18 Coolie day 0.2 350.00 70.00
9988 Sundries including carriage of cement etc L.S. 26.91 2 53.82
TOTAL 1112.95
Add 1 % Water charges on "W" 11.1295
TOTAL 1124.08
Add GST (multiplying factor 0.1405) on "X" 157.93
TOTAL 1282.01
Add 15 % Contractor's profit and overheads on "Y" 192.30
Total 1474.31
Add Cess @ 1% on "Z" 14.74
Cost for 1 sqm 1489.05
Say 1489.05
1489.10

11.41.3 Size of Tile 800x800 mm


Details of cost for 1 sqm
MATERIAL
Vitrified floor tiles 80x80 cm size = 1.000 sqm
Add for wastage & breakage @ 2.5 %
= 0.025 sqm
Total = 1.025 sqm
8622 Vitrified floor tile 80x80 cm sqm 1.025 850 871.25
9977 Carriage of tiles L.S. 6.24 2 12.48
20 mm thick Cement mortar 1 : 4
(1 cement : 4 coarse sand)
3.9 Rate as per Item Number 3.9 of SH: Mortars cum 0.024 3548.00 85.15
9999 Mortar for pointing in white cement Cement for L.S. 2.6 2 5.20
slurry over bed @ 3.3 kg per
sqm
367 Portland Cement tonne 0.0033 4375 14.44
LABOUR
23 Mason (brick layer) 1st class day 0.2 505.17 101.03
18 Coolie day 0.2 350.00 70.00
9988 Sundries including carriage of cement etc L.S. 26.91 2 53.82
TOTAL 1213.37
Add 1 % Water charges on "W" 12.1337
TOTAL 1225.50
Add GST (multiplying factor 0.1405) on "X" 172.18
TOTAL 1397.68
Add 15 % Contractor's profit and overheads on "Y" 209.65
Total 1607.33
Add Cess @ 1% on "Z" 16.07
Cost for 1 sqm 1623.40
Say 1623.4
1623.40

11.41.4 Size of Tile 1000x1000 mm


Details of cost for 1 sqm
MATERIAL
Vitrified floor tiles 100x100 cm size
= 1.000 sqm
Add for wastage & breakage @ 2.5 %
= 0.025 sqm
Total = 1.025 sqm
8623 Vitrified floor tile 100x100 cm sqm 1.025 1390 1424.75
9977 Carriage of tiles L.S. 6.24 2 12.48
20 mm thick Cement mortar 1 : 4
(1 cement : 4 coarse sand)
3.9 Rate as per Item Number 3.9 of SH: Mortars cum 0.024 3548.00 85.15
9999 Mortar for pointing in white cement Cement for L.S. 2.6 2 5.20
slurry over bed @ 3.3 kg per
sqm
367 Portland Cement tonne 0.0033 4375 14.44
LABOUR
23 Mason (brick layer) 1st class day 0.2 505.17 101.03
18 Coolie day 0.2 350.00 70.00
9988 Sundries including carriage of cement etc L.S. 26.91 2 53.82
TOTAL 1766.87
Add 1 % Water charges on "W" 17.6687
TOTAL 1784.54
Add GST (multiplying factor 0.1405) on "X" 250.73
TOTAL 2035.27
Add 15 % Contractor's profit and overheads on "Y" 305.29
Total 2340.56
Add Cess @ 1% on "Z" 23.41
Cost for 1 sqm 2363.97
Say 2363.97
2364.00

11.42 Deduct for not using 20 mm thick cement


mortar
Details of1:4
cost(1forcement
1 sqm : 4 coarse sand)
bedding
MATERIAL
in laying of floor tiles and jointing
with grey cement slurry @ 3.3 kg/ sqm.
Cement mortar 1 : 4 (1 cement : 4 coarse sand)
3.9 Rate as per Item Number 3.9 of SH: Mortars cum 0.024 3548.00 85.15
9999 Mortar for pointing in white cement L.S. 40.43 2 80.86
Cement for slurry over bed @ 3.3 kg per sqm
367 Portland Cement tonne 0.0033 4375 14.44
LABOUR
23 Mason (brick layer) 1st class day 0.2 505.17 101.03
18 Coolie day 0.2 350.00 70.00
9988 Sundries i/c carriage of cement etc. L.S. 26.91 2 53.82
Total 405.30
Add 1 % Water charges on "W" 4.053
TOTAL 409.35
Add GST (multiplying factor 0.1405) on "X" 57.51
TOTAL 466.86
Add 15 % Contractor's profit and overheads on "Y" 70.03
Total 536.89
Add Cess @ 1% on "Z" 5.37
Cost for 1 sqm 542.26
Say 542.26
542.30

11.43 Fixing glazed/ Ceramic/ Vitrified


floor tiles3mm
average with cement
thickness.based high polymer
modified quick-set tile
Details of cost for 1 sqm
adhesive (Water
based) conforming to IS: 15477, in
MATERIAL
8731 High polymer modified quickset tile adhesive. per kg 5 9 45.00
9999 Mortar for pointing in white cement L.S. 40.43 2 80.86
LABOUR
23 Mason (brick layer) 1st class day 0.2 505.17 101.03
18 Coolie day 0.2 350.00 70.00
9988 Sundries i/c carriage of cement etc. L.S. 26.91 2 53.82
Total 350.71
Add 1 % Water charges on "W" 3.5071
TOTAL 354.22
Add GST (multiplying factor 0.1405) on "X" 49.77
TOTAL 403.99
Add 15 % Contractor's profit and overheads on "Y" 60.60
Total 464.59
Add Cess @ 1% on "Z" 4.65
Cost for 1 sqm 469.24
Say 469.24
469.20

11.44 Crazy ceramic tile flooring, with


under layer 12 mm thick cement mortar 1:4
(1 cement: 4 coarse sand), with joints not
exceeding 5 mm, including filling the gaps
Details of cost for 10 sqm.
MATERIAL
Under layer 12 mm thick Cement mortar 1:4 (1
cement : 4 coarse sand).
3.9 Rate as per Item No.3.9 of SH:Mortar cum 0.14 3548.00 496.72
LABOUR
24 Mason (brick layer) 2nd class day 0.67 403.67 270.46
17 Beldar day 0.75 350.00 262.50
11 Bhisti day 0.92 350.00 322.00
9999 Sundries L.S. 8.97 2 17.94
Cement slurry for subgrade
367 Portland Cement tonne 0.04 4375 175.00
2209 Carriage of Cement tonne 0.04 94.34 3.77
Labour for applying cement slurry
17 Beldar day 0.5 350.00 175.00
Top layer with tile piece and gap filling with
cement motar:
Ceramic tile piece for crazy flooring assuming
70% tile area and 30% of joint filler/mixture.
(7.00x0.010)=0.07
0.872x0.07/0.051=1.20 qtl
2709 Ceremic Tiles Pieces for Crazy Flooring quintal 1.2 135 162.00
9977 Carriage of tiles L.S. 62.4 2 124.80
Cement motar 1:4 for filling of crazy tile
:(300x0.01=0.03)
3.9 Rate as per Item No.3.9 of SH:Mortar Synthetic cum 0.03 3548.00 106.44
polyster triangular
4.18 Rate as per Item No.4.18 of per bag 61.10 0.00
SH: CONCRETE WORK of 50kg 1.38 61.05 84.25
Water proofing compound of cement
4.12 Rate as per Item No.4.12 of per bag of 56.60 0.00
SH:CONCRETE WORK 50 kg of 1.38 56.55 78.04
cement
23 Mason (brick layer) 1st class day 1.2 505.17 606.20
17 Beldar day 1 350.00 350.00
18 Coolie day 1 350.00 350.00
11 Bhisti day 0.54 350.00 189.00
9999 Sundries L.S. 67.25 2 134.50
TOTAL 3908.62
Add 1 % Water charges on "W-A" 3746.33 37.4633
TOTAL
Add GST (multiplying factor 0.1405) on "X-A" 3783.79 531.62
TOTAL
Add 15 % Contractor's profit and overheads on 4315.41 647.31
"Y-A"
Total 4962.72 49.63
Add Cess @ 1% on "Z-A" 5174.64
Cost of 10 sqm. 517.46
Cost of 1 sqm. 517.50
Say

11.45 Providing and laying 500x500x40


mm thick Turf paver (Turfpave XD) on 150
mm thick sub grade of compacted bed of 20
of
mm Engineer-in-charge.
thick nominal size stone aggregate and

Details of cost for 10 sqm.

MATERIAL
295 Stone Aggregate (Single size) : 20 mm nominal cum 1.5 800 1200.00
size
1 x 10 x 0.15 = 1.5cum
2202 Stone aggregate below 40 mm nominal size cum 1.5 584.88 877.32
LABOUR
for spreading ramming and consolidation of sub
grade
17 Beldar day 0.7 350.00 245.00
18 Coolie day 0.52 350.00 182.00
11 Bhisti day 0.36 350.00 126.00
Providing and filling Sand
2.27 Rate as per Item No.2.27 of cum 1.5 1320.50 1980.75
SH: EARTH WORK
2708 Truf Paver (500 x 500 x 40 mm) Labour for sqm 10 500 5000.00
laying of Turf pave
23 Mason (brick layer) 1st class day 0.5 505.17 252.59
17 Beldar day 1 350.00 350.00
9999 Sundries L.S. 50 2 100.00
TOTAL 10313.66
Add 1 % Water charges on "W-A" 8332.91 83.3291
TOTAL
Add (multiplying factor 0.1405) on "X-A" 8416.24 1182.48
TOTAL
Add 15 % Contractor's profit and overheads on 9598.72 1439.81
"Y-A"
Total 11038.53 110.39
Add Cess @ 1% on "Z-A" 13129.67
Cost of 10 sqm. 1312.97
Cost of 1 sqm. 1313.00
Say

11.46 Providing and laying Vitrified tiles in


different
11.46.1 sizes
Size(thickness to be specified
of Tile 500x500 mm by
manufacturer), with water absorption less
than 0.08 % and conforming to I.S. 15622, of
Details of cost for 1 sqm
MATERIAL
Vitrified floor tiles 50 x 50 cm size
= 1.00 sqm+
Add wastage & breakage @ 2.5%
= 0.025 sqm
Total = 1.025 sqm
8620 Vitrified floor tile 50x50 cm sqm 1.025 550 563.75
9977 Carriage of tiles L.S. 6.24 2 12.48
12 mm thick Cement mortar 1 : 3
(1 cement : 3 coarse sand)
3.8 Rate as per Item No.3.8 of SH:Mortars cum 0.014 4129.00 57.81
9999 Mortar for pointing in white cement L.S. 3.64 2 7.28
Cement slurry over bed @ 3.3 kg per sqm
367 Portland Cement tonne 0.0033 4375 14.44
LABOUR
23 Mason (brick layer) 1st class day 0.25 505.17 126.29
18 Coolie day 0.25 350.00 87.50
9988 Sundries including carriage of quick set polymer L.S. 26.91 2 53.82
TOTAL 923.37
Add 1 % Water charges on "W" 9.2337
TOTAL 932.60
Add GST (multiplying factor 0.1405) on "X" 131.03
TOTAL 1063.63
Add 15 % Contractor's profit and overheads on "Y" 159.55
Total 1223.18
Add Cess @ 1% on "Z" 12.23
Cost for 1 sqm 1235.41
Say 1235.41
1235.40

11.46.2 Size of Tile 600x600 mm


Details of cost for 1 sqm
MATERIAL
Vitrified floor tiles 60 x 60 cm size
= 1.00 sqm+
Add wastage & breakage @ 2.5%
= 0.025 sqm
Total = 1.025 sqm
8621 Vitrified floor tile 60x60 cm sqm 1.025 750 768.75
9977 Carriage of tiles L.S. 6.24 2 12.48
12 mm thick Cement mortar 1 : 3
(1 cement : 3 coarse sand)
3.8 Rate as per Item No.3.8 of SH:Mortars cum 0.014 4129.00 57.81
9999 Mortar for pointing in white cement L.S. 3.64 2 7.28
Cement slurry over bed @ 3.3 kg per sqm
367 Portland Cement tonne 0.0033 4375 14.44
LABOUR
23 Mason (brick layer) 1st class day 0.25 505.17 126.29
18 Coolie day 0.25 350.00 87.50
9988 Sundries including carriage of quick set polymer L.S. 26.91 2 53.82
TOTAL 1128.37
Add 1 % Water charges on "W" 11.2837
TOTAL 1139.65
Add GST (multiplying factor 0.1405) on "X" 160.12
TOTAL 1299.77
Add 15 % Contractor's profit and overheads on "Y" 194.97
Total 1494.74
Add Cess @ 1% on "Z" 14.95
Cost for 1 sqm 1509.69
Say 1509.69
1509.70

11.46.3 Size of Tile 800x800 mm


Details of cost for 1 sqm
MATERIAL
Vitrified floor tiles 80 x 80 cm size
= 1.00 sqm+
Add wastage & breakage @ 2.5%
= 0.025 sqm
Total = 1.025 sqm
8622 Vitrified floor tile 80x80 cm sqm 1.025 850 871.25
9977 Carriage of tiles L.S. 6.24 2 12.48
12 mm thick Cement mortar 1 : 3
(1 cement : 3 coarse sand)
3.8 Rate as per Item No.3.8 of SH:Mortars cum 0.014 4129.00 57.81
9999 Mortar for pointing in white cement L.S. 3.64 2 7.28
Cement slurry over bed @ 3.3 kg per sqm
367 Portland Cement tonne 0.0033 4375 14.44
LABOUR
23 Mason (brick layer) 1st class day 0.25 505.17 126.29
18 Coolie day 0.25 350.00 87.50
9988 Sundries including carriage of quick set polymer L.S. 26.91 2 53.82
TOTAL 1230.87
Add 1 % Water charges on "W" 12.3087
TOTAL 1243.18
Add GST (multiplying factor 0.1405) on "X" 174.67
TOTAL 1417.85
Add 15 % Contractor's profit and overheads on "Y" 212.68
Total 1630.53
Add Cess @ 1% on "Z" 16.31
Cost for 1 sqm 1646.84
Say 1646.84
1646.80

11.46.4 Size of Tile 1000x1000 mm


Details of cost for 1 sqm
MATERIAL
Vitrified floor tiles 100 x 100 cm size
= 1.00 sqm+
Add wastage & breakage @ 2.5% = 0.025 sqm
Total = 1.025 sqm
8623 Vitrified floor tile 100x100 cm sqm 1.025 1390 1424.75
9977 Carriage of tiles L.S. 6.24 2 12.48
12 mm thick Cement mortar 1 : 3
(1 cement : 3 coarse sand)
3.8 Rate as per Item No.3.8 of SH:MORTARS cum 0.014 4129.00 57.81
9999 Mortar for pointing in white cement L.S. 3.64 2 7.28
Cement slurry over bed @ 3.3 kg per sqm
367 Portland Cement tonne 0.0033 4375 14.44
LABOUR
23 Mason (brick layer) 1st class day 0.25 505.17 126.29
18 Coolie day 0.25 350.00 87.50
9988 Sundries including carriage of quick set polymer L.S. 26.91 2 53.82
TOTAL 1784.37
Add 1 % Water charges on "W" 17.8437
TOTAL 1802.21
Add GST (multiplying factor 0.1405) on "X" 253.21
TOTAL 2055.42
Add 15 % Contractor's profit and overheads on "Y" 308.31
Total 2363.73
Add Cess @ 1% on "Z" 23.64
Cost for 1 sqm 2387.37
Say 2387.37
2387.40

11.46A Providing and fixing glazed screen printed


border tile
Details for 75mm
1sqm wide having
(i.e. 13.33m length) thickness
5mm,
Material
of approved quality & make, in all
shades, design and prints, in dado, over
8624 Border tiles 200x75mm size 5mm thick Tile each 68 16 1088.00
required=1.00/(0.20x0.075)=66.70 tile. Add
9977 2.5% wastage = 1.67 tile 2 0.00
Total 68.37 say 68 tiles Carriage L.S. 6.24 12.48
3.8 Cement mortar 1:3 for 12mm base cum 0.014 4129.00 57.81
9999 Mortar for pointing in white cement L.S. 40.43 2 80.86
367 Cement for slurry over bed@ 3.3kg/sqm Labour MT 0.0033 4375 14.44
23 Mason 1st class each 0.25 505.17 126.29
18 Coolie each 0.25 350.00 87.50
9999 Sundries 26.91-0.16=26.75 L.S. 26.75 2 53.50
Total 1520.88
Add 1 % Water charges on "W" 15.2088
TOTAL 1536.09
Add GST (multiplying factor 0.1405) on "X" 215.82
TOTAL 1751.91
Add 15 % Contractor's profit and overheads on "Y" 262.79
Total 2014.70
Add Cess @ 1% on "Z" 20.15
Details of cost for 1sqm i.e. 13.33 mts 2034.85
Cost per mtr 152.65
Say 152.70

11.47 Providing and laying Vitrified tiles in


different
11.47.1 sizesSize (thickness to be mm
of Tile 500x500 specified by
the manufacturer), with water absorption less
Details of cost for 1 sqm
than 0.08% and conforming to IS: 15622, of
MATERIAL
Vitrified floor tiles 50 x 50 cm size
= 1.00 sqm+
Add wastage & breakage @ 2.5%
= 0.025 sqm
Total = 1.025 sqm
8620 Vitrified floor tile 50x50 cm sqm 1.025 550 563.75
9977 Carriage of tiles L.S. 6.24 2 12.48
8731 High polymer modified quickset tile adhesive. per kg 10 9 90.00
LABOUR
23 Mason (brick layer) 1st class day 0.25 505.17 126.29
18 Coolie day 0.5 350.00 175.00
9988 Sundries including carriage of quick set polymer L.S. 26.91 2 53.82
etc.
TOTAL 1021.34
Add 1 % Water charges on "W" 10.2134
TOTAL 1031.55
Add GST (multiplying factor 0.1405) on "X" 144.93
TOTAL 1176.48
Add 15 % Contractor's profit and overheads on "Y" 176.47
Total 1352.95
Add Cess @ 1% on "Z" 13.53
Cost for 1 sqm 1366.48
Say 1366.48
1366.50

11.47.2 Size of Tile 600x600 mm


Details of cost for 1 sqm
MATERIAL
Vitrified floor tiles 60 x 60 cm size
= 1.00 sqm+
Add wastage & breakage @ 2.5%
= 0.025 sqm
Total = 1.025 sqm
8621 Vitrified floor tile 60x60 cm sqm 1.025 750 768.75
9977 Carriage of tiles L.S. 6.24 2 12.48
8731 High polymer modified quickset tile adhesive. per kg 10 9 90.00
LABOUR
23 Mason (brick layer) 1st class day 0.25 505.17 126.29
18 Coolie day 0.5 350.00 175.00
9988 Sundries including carriage of quick set polymer L.S. 26.91 2 53.82
etc.
TOTAL 1226.34
Add 1 % Water charges on "W" 12.2634
TOTAL 1238.60
Add GST (multiplying factor 0.1405) on "X" 174.02
TOTAL 1412.62
Add 15 % Contractor's profit and overheads on "Y" 211.89
Total 1624.51
Add Cess @ 1% on "Z" 16.25
Cost for 1 sqm 1640.76
Say 1640.76
1640.80

11.47.3 Size of Tile 800x800 mm


Details of cost for 1 sqm
MATERIAL
Vitrified floor tiles 80 x 80 cm size
= 1.00 sqm+
Add wastage & breakage @ 2.5%
= 0.025 sqm
Total = 1.025 sqm
8622 Vitrified floor tile 80x80 cm sqm 1.025 850 871.25
9977 Carriage of tiles L.S. 6.24 2 12.48
8731 High polymer modified quickset tile adhesive. per kg 10 9 90.00
LABOUR
23 Mason (brick layer) 1st class day 0.25 505.17 126.29
18 Coolie day 0.5 350.00 175.00
9988 Sundries including carriage of quick set polymer L.S. 26.91 2 53.82
etc.
TOTAL 1328.84
Add 1 % Water charges on "W" 13.2884
TOTAL 1342.13
Add GST (multiplying factor 0.1405) on "X" 188.57
TOTAL 1530.70
Add 15 % Contractor's profit and overheads on "Y" 229.60
Total 1760.30
Add Cess @ 1% on "Z" 17.60
Cost for 1 sqm 1777.90
Say 1777.9
1777.90

11.47.4 Size of Tile 1000x1000 mm


Details of cost for 1 sqm
MATERIAL
Vitrified floor tiles 100 x 100 cm size
= 1.00 sqm+
Add wastage & breakage @ 2.5%
= 0.025 sqm
Total = 1.025 sqm
8623 Vitrified floor tile 100x100 cm sqm 1.025 1390 1424.75
9977 Carriage of tiles L.S. 6.24 2 12.48
8731 High polymer modified quickset tile adhesive. per kg 10 9 90.00
LABOUR
23 Mason (brick layer) 1st class day 0.25 505.17 126.29
18 Coolie day 0.5 350.00 175.00
9988 Sundries including carriage of quick set polymer L.S. 26.91 2 53.82
etc.
TOTAL 1882.34
Add 1 % Water charges on "W" 18.8234
TOTAL 1901.16
Add GST (multiplying factor 0.1405) on "X" 267.11
TOTAL 2168.27
Add 15 % Contractor's profit and overheads on "Y" 325.24
Total 2493.51
Add Cess @ 1% on "Z" 24.94
Cost for 1 sqm 2518.45
Say 2518.45
2518.50

11.48 Grouting the joints of flooring tiles having


joints
11.48.1of 3 Size
mm width, using epoxy
of Tile 500x500 mm grout mix
of 0.70 kg of organic
Details of cost for 1 sqm
coated filler of desired
shade (0.10 kg of hardener and 0.20 kg of
MATERIAL
8682 Epoxy Grout Kg 0.21 371 77.91
LABOUR
23 Mason (brick layer) 1st class day 0.1 505.17 50.52
18 Coolie day 0.1 350.00 35.00
9988 Sundries including carriage L.S. 5 2 10.00
TOTAL 173.43
Add 1 % Water charges on "W" 1.7343
TOTAL 175.16
Add GST (multiplying factor 0.1405) on "X" 24.61
TOTAL 199.77
Add 15 % Contractor's profit and overheads on "Y" 29.97
Total 229.74
Add Cess @ 1% on "Z" 2.30
Cost for 1 sqm 232.04
Say 232.04
232.00
11.48.2 Size of Tile 600x600 mm
Details of cost for 1 sqm
MATERIAL
8682 Epoxy Grout Kg 0.18 371 66.78
LABOUR
23 Mason (brick layer) 1st class day 0.08 505.17 40.41
18 Coolie day 0.08 350.00 28.00
9988 Sundries including carriage L.S. 5 2 10.00
TOTAL 145.19
Add 1 % Water charges on "W" 1.4519
TOTAL 146.64
Add GST (multiplying factor 0.1405) on "X" 20.60
TOTAL 167.24
Add 15 % Contractor's profit and overheads on "Y" 25.09
Total 192.33
Add Cess @ 1% on "Z" 1.92
Cost for 1 sqm 194.25
Say 194.25
194.30

11.48.3 Size of Tile 800x800 mm


Details of cost for 1 sqm
MATERIAL
8682 Epoxy Grout Kg 0.15 371 55.65
LABOUR
23 Mason (brick layer) 1st class day 0.06 505.17 30.31
18 Coolie day 0.06 350.00 21.00
9988 Sundries ladders etc L.S. 5 2 10.00
TOTAL 116.96
Add 1 % Water charges on "W" 1.1696
TOTAL 118.13
Add GST (multiplying factor 0.1405) on "X" 16.60
TOTAL 134.73
Add 15 % Contractor's profit and overheads on 20.21
"Y" 154.94
Total 1.55
Add Cess @ 1% on "Z" 156.49
Cost for 1 sqm 156.49
Say 156.50
11.48.4 Size of Tile 1000x1000 mm
Details of cost for 1 sqm
MATERIAL
8682 Epoxy Grout Kg 0.11 371 40.81
LABOUR
23 Mason (brick layer) 1st class day 0.04 505.17 20.21
18 Coolie day 0.04 350.00 14.00
9988 Sundries including carriage of quick set polymer L.S. 5 2 10.00
etc.
TOTAL 85.02
Add 1 % Water charges on "W" 0.8502
TOTAL 85.87
Add GST (multiplying factor 0.1405) on "X" 12.06
TOTAL 97.93
Add 15 % Contractor's profit and overheads on "Y" 14.69
Total 112.62
Add Cess @ 1% on "Z" 1.13
Cost for 1 sqm 113.75
Say 113.75
113.80

11.49 Providing and laying Vitrified tiles in floor


with different
11.49.1 Sizesizes (thickness
of Tile 500x500tomm be specified
by the manufacturer),
Details of cost for 1 sqm
with water absorption
less than 0.08% and conforming to IS:15622,
MATERIAL
Vitrified floor tiles 50 x 50 cm size
= 1.00 sqm+
Add wastage & breakage @ 2.5%
= 0.025 sqm
Total = 1.025 sqm
8620 Vitrified floor tile 50x50 cm sqm 1.025 550 563.75
9977 Carriage of tiles L.S. 6.24 2 12.48
8731 High polymer modified quickset tile adhesive. per kg 10 9 90.00
LABOUR
23 Mason (brick layer) 1st class day 0.2 505.17 101.03
18 Coolie day 0.4 350.00 140.00
9988 Sundries including carriage of quick set polymer L.S. 26.91 2 53.82
etc.
TOTAL 961.08
Add 1 % Water charges on "W" 9.6108
TOTAL 970.69
Add GST (multiplying factor 0.1405) on "X" 136.38
TOTAL 1107.07
Add 15 % Contractor's profit and overheads on "Y" 166.06
Total 1273.13
Add Cess @ 1% on "Z" 12.73
Cost for 1 sqm 1285.86
Say 1285.86
1285.90

11.49.2 Size of Tile 600x600 mm


Details of cost for 1 sqm
MATERIAL
Vitrified floor tiles 60 x 60 cm size
= 1.00 sqm+
Add wastage & breakage @ 2.5%
= 0.025 sqm
Total = 1.025 sqm
8621 Vitrified floor tile 60x60 cm sqm 1.025 750 768.75
9977 Carriage of tiles L.S. 6.24 2 12.48
8731 High polymer modified quickset tile adhesive. per kg 10 9 90.00
LABOUR
23 Mason (brick layer) 1st class day 0.2 505.17 101.03
18 Coolie day 0.4 350.00 140.00
9988 Sundries including carriage of quick set polymer L.S. 26.91 2 53.82
etc.
TOTAL 1166.08
Add 1 % Water charges on "W" 11.6608
TOTAL 1177.74
Add GST (multiplying factor 0.1405) on "X" 165.47
TOTAL 1343.21
Add 15 % Contractor's profit and overheads on "Y" 201.48
Total 1544.69
Add Cess @ 1% on "Z" 15.45
Cost for 1 sqm 1560.14
Say 1560.14
1560.10

11.49.3 Size of Tile 800x800 mm


Details of cost for 1 sqm
MATERIAL
Vitrified floor tiles 80 x 80 cm size
= 1.00 sqm+
Add wastage & breakage @ 2.5%
= 0.025 sqm
Total = 1.025 sqm
8622 Vitrified floor tile 80x80 cm sqm 1.025 850 871.25
9977 Carriage of tiles L.S. 6.24 2 12.48
8731 High polymer modified quickset tile adhesive. per kg 10 9 90.00
LABOUR
23 Mason (brick layer) 1st class day 0.2 505.17 101.03
18 Coolie day 0.4 350.00 140.00
9988 Sundries including carriage of quick set polymer L.S. 26.91 2 53.82
etc.
TOTAL 1268.58
Add 1 % Water charges on "W" 12.6858
TOTAL 1281.27
Add GST (multiplying factor 0.1405) on "X" 180.02
TOTAL 1461.29
Add 15 % Contractor's profit and overheads on "Y" 219.19
Total 1680.48
Add Cess @ 1% on "Z" 16.80
Cost for 1 sqm 1697.28
Say 1697.28
1697.30

11.49.4 Size of Tile 1000x1000 mm


Details of cost for 1 sqm
MATERIAL
Vitrified floor tiles 100 x 100 cm size
= 1.00 sqm+
Add wastage & breakage @ 2.5%
= 0.025 sqm
Total = 1.025 sqm
8623 Vitrified floor tile 100x100 cm sqm 1.025 1390 1424.75
9977 Carriage of tiles L.S. 6.24 2 12.48
8731 High polymer modified quickset tile adhesive. per kg 10 9 90.00
LABOUR
23 Mason (brick layer) 1st class day 0.2 505.17 101.03
18 Coolie day 0.4 350.00 140.00
9988 Sundries including carriage of quick set polymer L.S. 26.91 2 53.82
etc.
TOTAL 1822.08
Add 1 % Water charges on "W" 18.2208
TOTAL 1840.30
Add GST (multiplying factor 0.1405) on "X" 258.56
TOTAL 2098.86
Add 15 % Contractor's profit and overheads on "Y" 314.83
Total 2413.69
Add Cess @ 1% on "Z" 24.14
Cost for 1 sqm 2437.83
Say 2437.83
2437.80

11.50 Deduct for not grouting the joints with white


cement and
the items matching
of fixing pigment
of vitrified in
tiles.
Details of cost for 1 sqm
MATERIAL
9999 Mortar for pointing in white cement with L.S. 3.12 2 6.24
matching pigment
9999 LABOUR L.S. 1 2 2.00
TOTAL 8.24
Add 1 % Water charges on "W" 0.0824
TOTAL 8.32
Add GST (multiplying factor 0.1405) on "X" 1.17
TOTAL 9.49
Add 15 % Contractor's profit and overheads on "Y" 1.42
Total 10.91
Add Cess @ 1% on "Z" 0.11
Cost for 1 sqm 11.02
Say 11.02
11.00

11.51 Providing and laying machine cut,


mirror
11.51.1polished,
18 mmItalian
thick Marble stone flooring
Italian Marble stone
laid
slab,in required
Perlato,etc. pattern in linear
Rosso verona, Fire portion
Red orof the
Emperadore
building all complete as per architectural
Dark
Details of cost per 10 sqm
MATERIAL
18 mm thick italian marble stone slab 10.00 sqm 0.00
Add for wastage 15%= 1.50 sqm
Total: 11.50 sqm
1240 18 mm thick Italian Marble stone slab, sqm 11.5 3209 36903.50
Base mortar1:4 (1 cement :4 coarse sand)
3.9 Rate as per Item No.3.9 of SH: MORTARS cum 0.224 3548.00 794.75
Cemnt for slurry@, 4.4 kg/sqm

(i) for bedding=44 kg+

(ii) for jointing= 6 kg Total=50 kg

368 White Cement tonne 0.05 11200 560.00


2209 Carriage of white Cement tonne 0.05 94.34 4.72
9999 carriage of marble slab L.S. 26.91 2 53.82
LABOUR :
(for finishing , polishing and fixing)
23 Mason (brick layer) 1st class day 1.2 505.17 606.20
17 Beldar day 1 350.00 350.00
18 Coolie day 1 350.00 350.00
37 Skilled Beldar (for floor rubbing etc.) day 5 350.00 1750.00
13 Machine for rubbing of floors day 4 300 1200.00
9999 Mortar for pointing in white cement L.S. 25.74 2 51.48
TOTAL 42624.47
Add 1 % Water charges on "W" 426.2447
TOTAL 43050.71
Add GST (multiplying factor 0.1405) on "X" 6048.63
TOTAL 49099.34
Add 15 % Contractor's profit and overheads on "Y" 7364.90
Total 56464.24
Add Cess @ 1% on "Z" 564.64
Cost of 10 sqm. 57028.88
Cost of 1 sqm. 5702.89
Say 5702.90

11.52 Providing and laying machine cut,


mirror polished Marble stone flooring, in
required design (Simple geometrical,
11.52.1 18 mm
abstract etc.) and thick Italian in
in patterns Marble stone
combination
slab, Perlato,
Emperadore etc. Rosso verona, Fire Red or
Dark
Details of cost per 10 sqm
MATERIAL
18 mm thick italian marble stone slab 10.00 sqm
Add for wastage 20%= 2 sqm
Total: 12 sqm
1240 18 mm thick Italian Marble stone slab, sqm 12 3209 38508.00
Base mortar1:4 (1 cement :4 coarse sand)
3.9 Rate as per Item No.3.9 of SH: MORTARS cum 0.224 3548.00 794.75
Cemnt for slurry@, 4.4 kg/sqm
(i) for bedding=44 kg+
(ii) for jointing= 6 kg
Total=50 kg
368 White Cement tonne 0.05 11200 560.00
2209 Carriage of white Cement tonne 0.05 94.34 4.72
9999 carriage of marble slab L.S. 26.91 2 53.82
LABOUR :
(for finishing , polishing and fixing)
23 Mason (brick layer) 1st class day 1.75 505.17 884.05
17 Beldar day 1.25 350.00 437.50
18 Coolie day 1 350.00 350.00
37 Skilled Beldar (for floor rubbing etc.) day 5 350.00 1750.00
13 Machine for rubbing of floors day 4 300 1200.00
9999 Mortar for pointing in white cement L.S. 25.74 2 51.48
TOTAL 44594.32
Add 1 % Water charges on "W" 445.9432
TOTAL 45040.26
Add GST (multiplying factor 0.1405) on "X" 6328.16
TOTAL 51368.42
Add 15 % Contractor's profit and overheads on "Y" 7705.26
Total 59073.68
Add Cess @ 1% on "Z" 590.74
Cost of 10 sqm. 59664.42
Cost of 1 sqm. 5966.44
Say 5966.40

11.53 Providing and fixing Glass mossaic


tiles on finished
required pattern plain wall surface
approved of size 20
by Engineer-in-
mm x
Charge: 20 mm x 4 mm
Details of cost per 8 sqm
in all colour, design ,
fixing in customize design as per direction of
MATERIAL
Glass mossaic tiles (20 mm x 20 mm x 4mm)
Add for wastage 2.5%= 0.2 sqm
Total: 8.20 sqm
1242 Glass mossaic tiles (20 mm x 20 mm x 4 mm) sqm 8.2 2049 16801.80
1243 Tile fixing chemical adhesive kg 20 8.7 174.00
1244 Cement Polymer Grout Compound kg 10 16 160.00
1245 Acid for cleaning tiles litre 4 18 72.00
9999 carriage of marble slab L.S. 49.92 2 99.84
LABOUR :
(for finishing , polishing and fixing)
23 Mason (brick layer) 1st class day 1.6 505.17 808.27
18 Coolie day 1.6 350.00 560.00
9999 Sundries including carriage of adhesive etc. L.S. 26.91 2 53.82
TOTAL 18729.73
Add 1 % Water charges on "W" 187.2973
TOTAL 18917.03
Add GST (multiplying factor 0.1405) on "X" 2657.84
TOTAL 21574.87
Add 15 % Contractor's profit and overheads on "Y" 3236.23
Total 24811.10
Add Cess @ 1% on "Z" 248.11
Cost for 8.00 sqm 25059.21
Cost for 1.00 sqm 3132.4
Say 3132.40

11.54 Providing and fixing removable


raised/false
(a) access
Providing at flooring
requiredwith system
spacing and
to form
its components of approved make
modular framework, pedestals made out of for
different
GI tube of plenum
thickness height with possible
minimum height
2 mm and 25
(b) Stringers system in all
mm outer diameter, fully welded on to the steel
construction hot dipped galvanized of
rectangular size 570x20x30x0.80mm thick
(c) Providing
having holes at bothandends
fixingfor
Access Floor
securing the
panel of 600x600x32 mm medium grade
Filled Steel anti static high pressure
11.54.1
Lamination300 mm Finished
of 800H Floor Height
grade (FS800H). Access
(FFH)
Details of Cost for : 100.00 Sqm
MATERIALS :
2711 FS800H Grade Flooring Panel (i/c) 5% wastage each 292 750 219000.00
2712 Zinc Electroplated Pedestals - 300 mm each 360 140 50400.00
2714 Zinc Electroplated Tube Stinger each 570 66 37620.00
2715 Machine Screw for Fixing each 1140 2 2280.00
7048 Rawl Plug fl0or pedestal grouting on floor each 1440 25 36000.00
9999 Carriage of material L.S. 490 2 980.00
LABOUR :
14 Carpenter 1st class day 25 505.17 12629.25
17 Beldar day 25 350.00 8750.00
9999 Sundries L.S. 329 2 658.00
TOTAL 368317.25
Add 1 % Water charges on "W" 3683.1725
TOTAL 372000.42
Add GST (multiplying factor 0.1405) on "X" 52266.06
TOTAL 424266.48
Add 15 % Contractor's profit and overheads on "Y" 63639.97
Total 487906.45
Add Cess @ 1% on "Z" 4879.06
Cost of 100 sqm. 492785.51
Cost of 1 sqm 4927.86
Say 4927.90

11.54.2 450 mm Finished Floor Height (FFH).


Details of Cost for : 100.00 Sqm
MATERIALS :
2711 FS800H Grade Flooring Panel each 292 750 219000.00
2713 Zinc Electroplated Pedestals - 450 mm each 360 200 72000.00
2714 Zinc Electroplated Tube Stinger each 570 66 37620.00
2715 Machine Screw for Fixing each 1140 2 2280.00
7048 Rawl plug 50 mm (designation 10 no.) each 1440 25 36000.00
9999 Carriage of material L.S. 490 2 980.00
LABOUR :
14 Carpenter 1st class day 25 505.17 12629.25
17 Beldar day 25 350.00 8750.00
9999 Sundries L.S. 329 2 658.00
TOTAL 389917.25
Add 1 % Water charges on "W" 3899.1725
TOTAL 393816.42
Add GST (multiplying factor 0.1405) on "X" 55331.21
TOTAL 449147.63
Add 15 % Contractor's profit and overheads on "Y" 67372.14
Total 516519.77
Add Cess @ 1% on "Z" 5165.20
Cost of 100 sqm. 521684.97
Cost of 1 sqm 5216.85
Say 5216.90

11.55 Providing and laying flamed finish


Granite
11.55.1stone Flamedflooring
finishingranite
required design
stone slaband
patterns,
Jet Black,
Details
in linear
Cherry
of cost
as
per 10 Red,
well as curvilinear
sqm Elite Brown, Cat Eye
portions of the building all complete as per
or equivalent.
MATERIAL
18mm thick - Flamed finish granite slab = 10.00
sqm+Add for wastage 15% =1.50 sqm, Total
11.50 sqm
Total: 11.50 sqm
1239 18mm thick - Flamed finish granite slab sqm 11.5 1000 11500.00
Base mortar1:4 (1 cement :4 coarse sand)
2216 Carriage of Stone blocks white & red sand stone tonne 0.67 94.34 63.21
& kota stone slab
3.9 Rate as per Item No.3.9 of SH: MORTARS cum 0.224 3548.00 794.75
Cemnt for slurry@, 4.4 kg/sqm
(i) for bedding=44 kg+
(ii) for jointing= 6 kg
Total=50 kg
367 Portland Cement tonne 0.05 4375 218.75
874 Black colour dark shade pigment kilogram 4.5 70 315.00
2209 Carriage of white Cement tonne 0.05 94.34 4.72
9999 Mortar for pointing in white cement L.S. 25.35 2 50.70
LABOUR :
(for finishing , polishing and fixing)
24 Mason (brick layer) 2nd class day 1.2 403.67 484.40
17 Beldar day 1 350.00 350.00
18 Coolie day 1 350.00 350.00
37 Skilled Beldar (for floor rubbing etc.) day 5 350.00 1750.00
9999 Sundries L.S. 208.13 2 416.26
TOTAL 16297.79
Add 1 % Water charges on "W" 162.9779
TOTAL 16460.77
Add GST (multiplying factor 0.1405) on "X" 2312.74
TOTAL 18773.51
Add 15 % Contractor's profit and overheads on "Y" 2816.03
Total 21589.54
Add Cess @ 1% on "Z" 215.90
Cost of 10 sqm. 21805.44
Cost of 1 sqm. 2180.54
Say 2180.50

11.56 Providing and laying Polished Granite


stone
11.56.1 flooring in required
Polished Granitedesign
stone and
slab jet
patterns,
Black, in
Cherry
Details of
linear
cost perRed,
as well as curvilinear
Elite Brown,
10 sqm Cat Eye or
portions
equivalent.of the building all complete as per
MATERIAL
18 mm thick polished finish granite stone slab
10.00 sqm + 1.50 (Add for wastage 15%)=
Total: 11.50 sqm
7297 Granite of any colour. 18 mm thick ( slab area sqm 11.5 1800 20700.00
2216 above 0.50 sqm) tonne 0.67 94.34 63.21
Carriage of Stone blocks white & red sand stone
& kota stone slab
3.9 Rate as per Item No.3.9 of SH: MORTARS cum 0.224 3548.00 794.75
367 Portland Cement tonne 0.05 4375 218.75
874 Black colour dark shade pigment kilogram 4.5 70 315.00
2209 Carriage of white Cement tonne 0.05 94.34 4.72
9999 Mortar for pointing in white cement (11.22) L.S. 25.35 2 50.70
LABOUR :
(for finishing , polishing and fixing)
24 Mason (brick layer) 2nd class day 1.2 403.67 484.40
17 Beldar day 1 350.00 350.00
18 Coolie day 1 350.00 350.00
37 Skilled Beldar (for floor rubbing etc.) day 2 350.00 700.00
19 Machine for cutting (hand grinding) day 2 250 500.00
9999 Sundries L.S. 208.13 2 416.26
TOTAL 24947.79
Add 1 % Water charges on "W" 249.4779
TOTAL 25197.27
Add GST (multiplying factor 0.1405) on "X" 3540.22
TOTAL 28737.49
Add 15 % Contractor's profit and overheads on "Y" 4310.62
Total 33048.11
Add Cess @ 1% on "Z" 330.48
Cost of 10 sqm. 33378.59
Cost of 1 sqm. 3337.86
Say 3337.90
814
W

742.55
W

704.55
W

575.1

Z
378.95

579.05
W

637.65
W

357.35

W
X

6281.3

37.1
W

628.9
A

659

Y
Z

640.6
W

625.1

A
W

600.35
W

658.8

Y
Z

701.8

675.4
W

675.05

A
W

655
W

619.4
W

691.75

Y
Z

752

715.05
W

705.3

A
W

684.15
W

637.45
W

859.25

Z
889.35

870.95
W

867.85

Z
855.45

831.8

W
X

57.05

40.8

A
W

Z
962.05

1024.9
W

975.35
W

933.3
W

877.85

48.35
W

1325
W

1265.45
W

1217

X
Y

1147.15

Z
1010.15

1026.9
W

955.35
W

900.1
W

1047.65
W

930.25

Z
754

698.55
W

1358.3
W

1437.1
W

1068.95
W

2928.3
W

1651.2

X
Y

2420.55

2112.8
W

1687.05
W

1720.45

Z
313.45

360.2
W

1215.7
W

1279.95

X
Y

702

702
W

820.9
W

820.9
W

887.1
W

887.1

95.55
W

18.6

Y
Z

4015.8

2649.2
W

8132.95
A
W

107.8
W

787.05

Y
Z

757.25

856.85
W

948.55
W

1030.85
W

1127.95
W

1360.7

1618.9
W

2359.45
W

537.75

453.6
A

Y
Z

500.9

Z
1399.2

1142.5
W

1375.25
W

1636.2

X
Y

2376.75

151.85
W

1254.95

Y
Z

1487.7

1748.65
W

2489.2

224.25
W

188

151.8
W

110.6

X
Y

1180.15

W
W

1412.9
W

1673.85

W
W
X

2414.4

11
W

5678.9
W

5939.3
W

3116.8

Z
4908.35

5197.35
W

2160.3
W

3329.35
ROOFING
SUB HEAD : 12.0
1 Code Description Unit Quantity Rate Amount
2 12.1 Providing corrugated G.S. sheet roofing including
vertical / curved surface fixed with polymer coated J or L
hooks, bolts and nuts 8 mm diameter with bitumen and G.I.
limpet washers or with G.I. limpet washers filled with white
lead, including a coat of approved steel primer and two coats
of approved paint on overlapping of sheets complete (up to
any pitch in horizontal/ vertical or curved surfaces),
excluding the cost of purlins, rafters and trusses and
including cutting to size and shape wherever required.

3
4 1.00 mm thick with zinc coating not less than 275 gm/m²
12.1.1
5
6
7 Details of cost for a roof with each sloping side
8 18.09x5.10m and slop being flatter
9 than 1 vertical to 2.5 horizontal
10 Area of roof = 2x18.09x5.10 = 184.518 sqm.
11 MATERIAL
12 C.G.S. sheets 2x27 =54 nos. of size 2.5x0.9
13 metre @19.35 Kg each =1044.90Kg.
14 2x27=54 nos. of size
15 2.8x0.9@21.67kg. each =1170.18Kg.+
16 Total = 2215.08Kg.+
17 Add 5% Wastage = 110.75Kg.
18 Total = 2325.83 Kg = 23.26 quintals
19 3050 Galvanised steel corrugated sheets quintal 23.26 5600 130256.00
20 2302 Carriage of G.I. sheet and accessories tonne 2.326 94.34 219.43
21 G.I.Seam bolts and nuts 60cm centre to centre
22 zig-zag i.e. 30cm
23 centre to centre straight
24 Breadth is 5.1metre
25 No. of bolts in one lap 5.1/0.3 =17 nos.
26 2x26(laps)x17 nos. = 884 nos.
27 1022 Galvanised steel bolts & nuts 6 mm dia and 25 10 Nos 88.4 38 3359.20
28 mm long round head with slots G.I.,J or L
29 hooks 8mm dia.
30 (No. of purlins to be used 5 on either
31 side)2x5x27
32 (No. of sheets)x23 nos. of bolts in each sheet
33 = 810 nos.
34 1023 Galvanised steel J or L hooks 8 mm dia 10 Nos 81 120 9720.00
35 1207 G.I. Limpet washer 100 Nos 16.94 21 355.74
36 (total of seam and J bolts)
37 884+810=1694
38 1208 Bitumen washer 100 Nos 16.94 30 508.20
39 9977 Carriage of bolts and washers L.S. 26.91 2 53.82
40 9999 Sundries L.S. 53.82 2 107.64
50 LABOUR
51 30 Mistry day 1.3 403.67 524.77
52 15 Carpenter 2nd class day 15.5 403.67 6256.89
53 17 Beldar day 15.5 350.00 5425.00
54 4202 Red oxide Zinc chromate primer litre 2.53 110 278.30
55 9977 Carriage of material L.S. 0.52 2 1.04
56 31 Painter day 1.13 403.67 456.15
57 18 Coolie day 1.13 350.00 395.50
58 9999 Brushes, sand papers i/c sundries L.S. 50.57 2 101.14
59 845 Roofing paint for iron sheets in red colour litre 3.75 120 450.00
60 9977 Carriage of paint L.S. 6.76 2 13.52
61 31 Painter day 2.53 403.67 1021.29
62 18 Coolie day 2.53 350.00 885.50
63 9999 Brushes and Sandpapers L.S. 31.98 2 63.96
64 9999 Sundries L.S. 38.09 2 76.18
65 TOTAL 160529.27 W
66 Add 1 % Water charges on "W" 1605.2927
67 TOTAL 162134.56 X
68 Add GST (multiplying factor 0.1405) on "X" 22779.91
69 TOTAL 184914.47 Y
70 Add 15 % Contractor's profit and overheads on "Y" 27737.17
71 Total 212651.64 Z
72 Add Cess @ 1% on "Z" 2126.52
73 Cost of 184.518 Sqm. 214778.16
74 Cost of 1 Sqm. 1164
75 Say 1164.00
76
77
78 12.1.2 0.80 mm thick with zinc coating not less than 275
79 gm/m²
Details of cost for a roof with each sloping side 18.09x5.10m and slop being flatter

80 than 1 vertical to 2.5 horizonta


81 Area of roof = 2x18.09x5.1 = 184.518 sqm.
82
83 Details of length and breadth. Length
84 26(laps)x0.135(each lap)=3.51 Width of Corrugator sheet with 10

85
86 corrugation measured end to end = 0.8 metres 27 (nos. of sheets)x0.80
(width of sheet) = 21.60 length
87
88
89 Less laps = 3.51
90
91 Length = 18.09
92
93 Breadth on one side
106 C.G.S. Sheet 1 No. of = 2.5 metres length+
107 C.G.S. Sheet 1 No. of = 2.8 metres length
108 Total = 5.3 metres
109 Deduct end lap of 20cm (-)0.2 metres
110 breadth = 5.1 m
111 MATERIAL
112 C.G.I.Sheets 0.8mm thick
113 2x27=54nos. @15.82Kg.each
114 Total = 854.38Kg(X)
115 2.5mx0.9m is the size of plain G.I.sheet
116 which on being corrugated will become
117 2.5mx0.8m
118 (The size of plain sheet is taken because
119 the weight is available only of plain sheets)
120 (Refer I.S. Code 277-1962)
121 2x27=54nos. of size.
122 2.8x0.9@17.72Kg each = 956.8Kg (Y)
123 Total of (X)+(Y) = 1811.16Kg.
124 Add wastage @5% = 90.56Kg.
125 3050 Galvanised steel corrugated sheets quintal 19.02 5600 106512.00
126 2302 Carriage of G.I. sheet and accessories G.I. tonne 1.902 94.34 179.43
127 scam bolts and nuts 60cm centre to centre zig
128 zag i.e. 30cm.
129 centre to centre straight
130 Breadth is 5.1metre
131 No. of bolts in one lap 5.1/0.3 =17 nos.
132 2x26(laps)x17 nos. = 884 nos.
133 1022 Galvanised steel bolts & nuts 6 mm dia and 25 10 Nos 88.4 38 3359.20
134 mmlong round head with slots
135 1023 Galvanised steel J or L hooks 8 mm dia (No. 10 Nos 81 120 9720.00
136 of purlins to be used 5 on either side)2x5x27
137 (No. of sheets)x23 Nos. of bolts in each sheet
138 = 810 Nos
139 1207 G.I. Limpet washer 100 Nos 16.94 21 355.74
140 (total of seam and J bolts)
141 884+810=1694
142 1208 Bitumen washer 100 Nos 16.94 30 508.20
143 9977 Carriage of bolts and washers L.S. 26.91 2 53.82
144 9999 Sundries L.S. 53.82 2 107.64
145 LABOUR
146 30 Mistry day 1.3 403.67 524.77
147 15 Carpenter 2nd class day 15.5 403.67 6256.89
148 17 Beldar day 15.5 350.00 5425.00
149 4202 Red oxide Zinc chromate primer litre 2.53 110 278.30
150 9977 Carriage of material L.S. 0.52 2 1.04
151 31 Painter day 1.13 403.67 456.15
152 18 Coolie day 1.13 350.00 395.50
153 9999 Brushes, sand papers i/c sundries L.S. 50.57 2 101.14
154 845 Roofing paint for iron sheets in red colour litre 3.75 120 450.00
155 9977 Carriage of paint L.S. 6.76 2 13.52
164 31 Painter day 2.53 403.67 1021.29
165 18 Coolie day 2.53 350.00 885.50
166 9999 Brushes and Sandpapers L.S. 31.98 2 63.96
167 9999 Sundries L.S. 38.09 2 76.18
168 TOTAL 136745.27 W
169 Add 1 % Water charges on "W" 1367.4527
170 TOTAL 138112.72 X
171 Add GST (multiplying factor 0.1405) on "X" 19404.84
172 TOTAL 157517.56 Y
173 Add 15 % Contractor's profit and overheads on "Y" 23627.63
174 Total 181145.19 Z
175 Add Cess @ 1% on "Z" 1811.45
176 Cost of 184.518 Sqm. 182956.64
177 Cost of 1 Sqm. 991.54
178 Say 991.50
179
180
181
182 12.1.3 0.63 mm thick with zinc coating not less than 275
183 gm/ m²of cost for a roof with each sloping side 18.09x5.10m and slop
Details
being flatter than 1
184 vertical to 2.5 horizontal
185 Area of roof = 2x18.09x5.1 = 184.518 sqm.
186 Details of length and breadth.
187
188 Length = 26(laps)x0.135(each lap)=3.51 Width of Corrugator sheet with 10
corrugation measured end to end = 0.8 metres 27 (nos. of
189 sheets)x0.80
190 (width of sheet) = 21.60 length Less laps = 3.51
191
192 Length = 18.09 Breadth on one side-

193 C.G.S. Sheet 1 No. of = 2.5 metres length+ C.G.S. Sheet 1 No. of = 2.8
metres length
194
195 = 5.3 metres
196
197 Deduct end lap of 20cm (-)0.2 metres breadth = 5.1m
198
199 MATERIAL
200
201 C.G.I.Sheets 0.8mm thick 2x27=54nos. @12.82Kg.each = 692.28 Kg(X)
202 2.5mx0.9m is the size of plain G.I.sheet which
203
204 on being corrugated will become 2.5mx0.8m
205
206 (The size of plain sheet is taken because the weight is available only of plain sheets)
(Refer I.S. Code 277-1962) 2x27=54nos. of size. 2.8x0.9@13.38Kg each = 775.44Kg (Y)
207 of (X)+(Y) = 1467.72Kg.
Total
208 Add wastage @5% = 73.39Kg. Total = 1541.11Kg = 15.41q
217 3050 Galvanised steel corrugated sheets quintal 15.41 5600 86296.00
218 2302 Carriage of G.I. sheet and accessories G.I. tonne 1.54 94.34 145.28
219 scam bolts and nuts 60cm centre to centre zig
220 zag i.e. 30cm.
221 centre to centre straight
222 Breadth is 5.1metre
223 No. of bolts in one lap 5.1/0.3 =17 nos.
224 2x26(laps)x17 nos. = 884 nos.
225 1022 Galvanised steel bolts & nuts 6 mm dia and 25 10 Nos 88.4 38 3359.20
226 mm long round head with slots
227 1023 Galvanised steel J or L hooks 8 mm dia (No. 10 Nos 81 120 9720.00
228 of purlins to be used 5 on either side)2x5x27
229 (No. of sheets)x23 Nos. of bolts in each sheet
230 = 810 Nos
231 1207 G.I. Limpet washer 100 Nos 16.94 21 355.74
232 (total of seam and J bolts)
233 884+810= 1694
234 1208 Bitumen washer 100 Nos 16.94 30 508.20
235 9977 Carriage of bolts and washers L.S. 26.91 2 53.82
236 9999 Sundries L.S. 53.82 2 107.64
237 LABOUR
238 30 Mistry day 1.3 403.67 524.77
239 15 Carpenter 2nd class day 15.5 403.67 6256.89
240 17 Beldar day 15.5 350.00 5425.00
241 4202 Red oxide Zinc chromate primer litre 2.53 110 278.30
242 9977 Carriage of material L.S. 0.52 2 1.04
243 31 Painter day 1.13 403.67 456.15
244 18 Coolie day 1.13 350.00 395.50
245 9999 Brushes, sand papers i/c sundries L.S. 50.57 2 101.14
246 845 Roofing paint for iron sheets in red colour litre 3.75 120 450.00
247 9977 Carriage of paint L.S. 6.76 2 13.52
248 31 Painter day 2.53 403.67 1021.29
249 18 Coolie day 2.53 350.00 885.50
250 9999 Brushes and Sandpapers L.S. 31.98 2 63.96
251 9999 Sundries L.S. 38.09 2 76.18
252 TOTAL 116495.12 W
253 Add 1 % Water charges on "W" 1164.9512
254 TOTAL 117660.07 X
255 Add GST (multiplying factor 0.1405) on "X" 16531.24
256 TOTAL 134191.31 Y
257 Add 15 % Contractor's profit and overheads on "Y" 20128.70
258 Total 154320.01 Z
259 Add Cess @ 1% on "Z" 1543.20
260 Cost of 184.518 Sqm. 155863.21
261 Cost of 1 Sqm. 844.7
262 Say 844.70
263
264
275
276
277 12.2 Extra for straight cutting in C.G.S. sheet roofing for
278 making opening
exceeding 40 sq.of area
decimeter for chimney stacks, sky light etc.:
279 12.2.1 1.00 mm thick
280
281 Details of cost for 3 metres periphery Assuming a hole of 10dmx5dm area of the hole
50dm2 and the perimeter of the hole
282
283 3 metre
284
285 LABOUR
286
287 12 Blacksmith 1st class day 0.15 505.17 75.78
288 17 Beldar day 0.15 350.00 52.50
289 TOTAL 128.28 W
290 Add 1 % Water charges on "W" 1.2828
291 TOTAL 129.56 X
292 Add GST (multiplying factor 0.1405) on "X" 18.20
293 TOTAL 147.76 Y
294 Add 15 % Contractor's profit and overheads on "Y" 22.16
295 Total 169.92 Z
296 Add Cess @ 1% on "Z" 1.70
297 Cost of 3.00 metres 171.62
298 Cost of 1.00 metre 57.21
299 Say 57.20
300
301
302 12.2.2 0.80 mm thick
303 Details of cost for 3 metres periphery Assuming a hole of 10dmx5dm area of the hole
50dm2 and the perimeter of the hole 3
304 metre
305 LABOUR
306
307 12 Blacksmith 1st class day 0.12 505.17 60.62
308 17 Beldar day 0.12 350.00 42.00
309 TOTAL 102.62 W
310 Add 1 % Water charges on "W" 1.0262
311 TOTAL 103.65 X
312 Add GST (multiplying factor 0.1405) on "X" 14.56
313 TOTAL 118.21 Y
314 Add 15 % Contractor's profit and overheads on "Y" 17.73
315 Total 135.94 Z
316 Add Cess @ 1% on "Z" 1.36
317 Cost of 3.00 metres 137.30
318 Cost of 1.00 metre 45.77
319 Say 45.80
320
321
327 12.2.3 0.63 mm thick
329 Details of cost for 3 metres periphery
330 Assuming a hole of 10dmx5dm area of the
331 hole 50dm2 and the perimeter of the hole 3
332 metre
333 LABOUR
334 12 Blacksmith 1st class day 0.12 505.17 60.62
335 17 Beldar day 0.12 350.00 42.00
336 TOTAL 102.62 W
337 Add 1 % Water charges on "W" 1.0262
338 TOTAL 103.65 X
339 Add GST (multiplying factor 0.1405) on "X" 14.56
340 TOTAL 118.21 Y
341 Add 15 % Contractor's profit and overheads on "Y" 17.73
342 Total 135.94 Z
343 Add Cess @ 1% on "Z" 1.36
344 Cost of 3.00 metres 137.30
345 Cost of 1.00 metre 45.77
346 Say 45.80
347
348
349 12.3 Extra for circular cutting in C.G.S. sheet roofing for
350 making opening
exceeding 40 sq.of area
decimeter:
351 12.3.1 1.00 mm thick
352 Details of cost for 10 holes of 0.5 metre dia-
353 metre
354 Perimetre of 10 nos 10x22/7x0.5 = 15.71
355 metre
356 LABOUR
357 12 Blacksmith 1st class day 3.13 505.17 1581.18
358 17 Beldar day 6.26 350.00 2191.00
359 TOTAL 3772.18 W
360 Add 1 % Water charges on "W" 37.7218
361 TOTAL 3809.90 X
362 Add GST (multiplying factor 0.1405) on "X" 535.29
363 TOTAL 4345.19 Y
364 Add 15 % Contractor's profit and overheads on "Y" 651.78
365 Total 4996.97 Z
366 Add Cess @ 1% on "Z" 49.97
367 Cost of 15.71 metres 5046.94
368 Cost of 1.00 metre 321.26
369 Say 321.30
370
379
380 12.3.2 0.80 mm thick
381
382 Details of cost for 10 holes of 0.5 metre dia-metre
383 Perimetre of 10 nos 10x22/7x0.5 =
384 15.71 metre
385 LABOUR
386 12 Blacksmith 1st class day 2.5 505.17 1262.93
387 17 Beldar day 5 350.00 1750.00
388 TOTAL 3012.93 W
389 Add 1 % Water charges on "W" 30.1293
390 TOTAL 3043.06 X
391 Add GST (multiplying factor 0.1405) on "X" 427.55
392 TOTAL 3470.61 Y
393 Add 15 % Contractor's profit and overheads on "Y" 520.59
394 Total 3991.20 Z
395 Add Cess @ 1% on "Z" 39.91
396 Cost of 15.71 metres 4031.11
397 Cost of 1.00 metre 256.6
398 Say 256.60
399
400
401 12.3.3 0.63 mm thick
402 Details of cost for 10 holes of 0.5 metre dia-metre
403 Perimetre of 10 nos 10x22/7x0.5 = 15.71 metre
404 LABOUR
405 12 Blacksmith 1st class day 2.5 505.17 1262.93
406 17 Beldar day 5 350.00 1750.00
407 TOTAL 3012.93 W
408 Add 1 % Water charges on "W" 30.1293
409 TOTAL 3043.06 X
410 Add GST (multiplying factor 0.1405) on "X" 427.55
411 TOTAL 3470.61 Y
412 Add 15 % Contractor's profit and overheads on "Y" 520.59
413 Total 3991.20 Z
414 Add Cess @ 1% on "Z" 39.91
415 Cost of 15.71 metres 4031.11
416 Cost of 1.00 metre 256.6
417 Say 256.60
418
419
429
430
431 12.4 Providing ridges or hips of width 60 cm overall width
432 plain G.S.washers
bitumen sheet fixed with polymer coated J or L hooks, bolts
complete.
433 and nuts 8 mm dia G.I. limpet and
434 12.4.1 0.80 mm thick with zinc coating not less than 275
435 gm/m²
436 Details of cost for 10.35 metres long ridge
437
438 0.80mm thick with zinc coating not less than 275gm/m2
439
440 Consider the length of the ridge 10.35 metres.
441
442 The ridge will be made out of plain
443 G.I. Sheets
444 0.9mx1.8m
445 Three pieces will be 0.9m long and 0.60m
446 wide overlapping 22.5cm.
447 MATERIAL
448 G.I. plain sheets 0.80 thick
449 1.80x0.90m size 5 nos. @ 11.39Kg. sheet =
450 56.95Kg + Add 2% wastage = 1.14 Kg.
451 Total = 58.09 Kg. or 0.58 q.
452 992 Galvanised steel plain sheets quintal 0.58 6000 3480.00
453 2302 Carriage of G.I. sheet and accessories tonne 0.058 94.34 5.47
454 222 Seam bolts and nuts 6 mm dia and 10 Nos 2.8 10 28.00
455 25 mm long
456 25mmx6mm (There are 14 joints)
457 1211 G.I. plain washer for seam bolts 100 Nos 0.28 32 8.96
458 1208 Bitumen washer 100 Nos 0.28 30 8.40
459 9977 Carriage of seam bolts and washers L.S. 1.82 2 3.64
460 9999 Sundries L.S. 13.52 2 27.04
461 LABOUR
462 30 Mistry day 0.4 403.67 161.47
463 12 Blacksmith 1st class day 1.2 505.17 606.20
464 13 Blacksmith 2nd class day 0.8 403.67 322.94
465 17 Beldar day 2.4 350.00 840.00
466 TOTAL 5492.12 W
467 Add 1 % Water charges on "W" 54.9212
468 TOTAL 5547.04 X
469 Add GST (multiplying factor 0.1405) on "X" 779.36
470 TOTAL 6326.40 Y
471 Add 15 % Contractor's profit and overheads on "Y" 948.96
472 Total 7275.36 Z
473 Add Cess @ 1% on "Z" 72.75
474 Cost of 10.35 metres 7348.11
475 Cost of 1.00 metre 709.96
476 Say 710.00
477
478
488 12.4.2 0.63 mm thick with zinc coating not less than 275
489 gm/m²
490 Details of cost for 10.35 metre long ridge.
491 G.I.plain sheets 0.63mm thick 1.8x0.9m size 5
492 nos. @9.23 Kg.
493 per sheet = 46.15 Kg. + Add 2% wastage =
494 0.91 Kg.
495 Total = 47.07 Kg.
496 Say 47 Kg.
497 992 Galvanised steel plain sheets quintal 0.47 6000 2820.00
498 2302 Carriage of G.I. sheet and accessories tonne 0.047 94.34 4.43
499 222 Seam bolts and nuts 6 mm dia and 10 Nos 2.8 10 28.00
500 25 mm long
501 25mmx6mm (There are 14 joints)
502 1211 G.I. plain washer for seam bolts 100 Nos 0.28 32 8.96
503 1208 Bitumen washer 100 Nos 0.28 30 8.40
504 9977 Carriage of seam bolts and washers L.S. 1.82 2 3.64
505 9999 Sundries L.S. 13.52 2 27.04
506 LABOUR
507 30 Mistry day 0.4 403.67 161.47
508 12 Blacksmith 1st class day 1.2 505.17 606.20
509 13 Blacksmith 2nd class day 0.8 403.67 322.94
510 17 Beldar day 2.4 350.00 840.00
511 TOTAL 4831.08 W
512 Add 1 % Water charges on "W" 48.3108
513 TOTAL 4879.39 X
514 Add GST (multiplying factor 0.1405) on "X" 685.55
515 TOTAL 5564.94 Y
516 Add 15 % Contractor's profit and overheads on "Y" 834.74
517 Total 6399.68 Z
518 Add Cess @ 1% on "Z" 64.00
519 Cost of 10.35 metres 6463.68
520 Cost of 1.00 metre 624.51
521 Say 624.50
522
523
524 12.5 Providing valleys of 90 cm wide overall in plain G.S.
525 sheet fixed
washers with polymer
complete : coated J, or L hooks, bolts and nuts
526 8 mm dia G.I. limpet and bitumen
12.5.1 1.60 mm thick with zinc coating not less than 350
527 gm/m²
528 Details of cost for 9.325m
529 MATERIAL
530 G.I. plain sheets 2.5x0.9m
531 4 nos. @ 29.95Kg/sheet =119.80Kg.+ Add 2%
532 wastage = 2.40Kg.
533 Total = 122.20 kg. or 1.222q.
534 992 Galvanised steel plain sheets quintal 1.222 6000 7332.00
535 2302 Carriage of G.I. sheet and accessories tonne 0.12 94.34 11.32
543 222 Seam bolts and nuts 6 mm dia and 10 Nos 1.2 10 12.00
544 25 mm long
545 25mmx6mm (There are 14 joints)
546 1211 G.I. plain washer for seam bolts 100 Nos 0.12 32 3.84
547 1208 Bitumen washer 100 Nos 0.12 30 3.60
548 9977 Carriage of bolts, nuts and washers L.S. 0.91 2 1.82
549 9999 Sundries L.S. 13.52 2 27.04
550 LABOUR
551 30 Mistry day 0.4 403.67 161.47
552 12 Blacksmith 1st class day 1.2 505.17 606.20
553 13 Blacksmith 2nd class day 0.8 403.67 322.94
554 17 Beldar day 2.4 350.00 840.00
555 TOTAL 9322.23 W
556 Add 1 % Water charges on "W" 93.2223
557 TOTAL 9415.45 X
558 Add GST (multiplying factor 0.1405) on "X" 1322.87
559 TOTAL 10738.32 Y
560 Add 15 % Contractor's profit and overheads on "Y" 1610.75
561 Total 12349.07 Z
562 Add Cess @ 1% on "Z" 123.49
563 Cost of 9.325 metres 12472.56
564 Cost of 1.00 metre 1337.54
565 Say 1337.50
566
567
568 12.6 Providing and fixing of 40 cm overall width plain G.S.
569 sheet
sand).fixed with polymer coated J or L hooks, bolts and nuts,
570 G.l. limpet and bitumen washer complete, bent to shape and
12.6.1 1.00 with
fixed in wall mm thick with
cement zinc coating
mortar not less
1:3 (1 cement : 3than 275
coarse
571 gm/m²
Details of cost for 12.125m
572 Consider a length of flashing 12.125 metres.
573 MATERIAL
574 G.I. plain sheet 1.25mm thick 3.2x0.75m
575 2 nos. @ 20.64 Kg. = 41.28 Kg.+
576 Add 2% wastage = 0.83 Kg
577 Total = 42.11 Kg. or 0.4211 quintal
578 992 Galvanised steel plain sheets quintal 0.4211 6000 2526.60
579 2302 Carriage of G.I. sheet and accessories tonne 0.041 94.34 3.87
580 222 Seam bolts and nuts 6 mm dia and 10 Nos 0.6 10 6.00
581 25 mm long
582 (taking 2 bolts per joints)
583 1207 G.I. Limpet washer 100 Nos 0.06 21 1.26
584 1208 Bitumen washer 100 Nos 0.06 30 1.80
585 9977 Carriage of G.I. seam bolts and washers L.S. 0.39 2 0.78
595 9999 Sundries L.S. 10.79 2 21.58
596 LABOUR
597 30 Mistry day 0.5 403.67 201.84
598 12 Blacksmith 1st class day 1.48 505.17 747.65
599 13 Blacksmith 2nd class day 1 403.67 403.67
600 17 Beldar day 3 350.00 1050.00
601 TOTAL 4965.05 W
602 Add 1 % Water charges on "W" 49.6505
603 TOTAL 5014.70 X
604 Add GST (multiplying factor 0.1405) on "X" 704.57
605 TOTAL 5719.27 Y
606 Add 15 % Contractor's profit and overheads on "Y" 857.89
607 Total 6577.16 Z
608 Add Cess @ 1% on "Z" 65.77
609 Cost of 12.125 metres 6642.93
610 Cost of 1.00 metre 547.87
611 Say 547.90
612
613
614
615 12.7 Providing and fixing 15 cm wide, 45 cm overall semi-
616 circular plain G.S. sheet
making necessary gutter with
connections withiron
rain brackets 40x3mm
water pipes
617 size, bolts, nuts and washers etc., including
complete.
12.7.1 0.80 mm thick with zinc coating not less than 275
618 gm/m²
619 Details of cost for 9.04m
620
621 0.80mm thick with zinc coating not less than 275gm/m2
622
623 Consider a length of 9.04m Sheet used =
624
625 2.5x0.90m = 2 nos.
626 Wt. = 2x15.82=31.64 Kg. = 0.3164q Total = 0.3164quintal
627
628 MATERIAL
629
630 992 Galvanised steel plain sheets quintal 0.3164 6000 1898.40
631 2302 Carriage of G.I. sheet and accessories tonne 0.0316 94.34 2.98
632 1008 Flats upto 10 mm in thickness quintal 0.0749 5300 396.97
633 1022 Galvanised steel bolts & nuts 6 mm dia and 25 10 Nos 2 38 76.00
634 mmlong round head with slots
635 1024 Galvanised steel bolts & nuts 10 mm dia and each 30 9 270.00
636 125 mm long round head with slots
637 1210 G.I. plain washer thin 100 Nos 0.7 21 14.70
638 1208 Bitumen washer 100 Nos 0.4 30 12.00
639 9977 Carriage of G.I. seam bolts and washers L.S. 2.73 2 5.46
640 9999 Sundries L.S. 5.33 2 10.66
649 LABOUR
650 12 Blacksmith 1st class day 0.5 505.17 252.59
651 17 Beldar day 0.5 350.00 175.00
652 9999 Sundries L.S. 12.61 2 25.22
653 30 Mistry day 0.28 403.67 113.03
654 12 Blacksmith 1st class day 0.84 505.17 424.34
655 15 Carpenter 2nd class day 0.62 403.67 250.28
656 17 Beldar day 1.68 350.00 588.00
657 TOTAL 4515.63 W
658 Add 1 % Water charges on "W" 45.1563
659 TOTAL 4560.79 X
660 Add GST (multiplying factor 0.1405) on "X" 640.79
661 TOTAL 5201.58 Y
662 Add 15 % Contractor's profit and overheads on "Y" 780.24
663 Total 5981.82 Z
664 Add Cess @ 1% on "Z" 59.82
665 Cost of 9.0400 metres 6041.64
666 Cost of 1.00 metre 668.32
667 Say 668.30
668
669
670 12.7.2 0.63 mm thick with zinc coating not less than 275
671 gm/m²
Details of cost for 9.04m
672 0.63mm thick with zinc coating not less than
673 275gm/m2
674 Consider a length of 9.04m Sheet used =
675 2.5x0.90m = 2 nos.
676 Wt. = 2x11.82=23.64 Kg. = 0.2364q
677 Total = 0.2364quintal
678 MATERIAL
679 992 Galvanised steel plain sheets quintal 0.2364 6000 1418.40
680 2302 Carriage of G.I. sheet and accessories tonne 0.0236 94.34 2.23
681 1008 Flats upto 10 mm in thickness quintal 0.0749 5300 396.97
682 1022 Galvanised steel bolts & nuts 6 mm dia and 25 10 Nos 2 38 76.00
683 mmlong round head with slots
684 1024 Galvanised steel bolts & nuts 10 mm dia and each 30 9 270.00
685 125 mm long round head with slots
686 1210 G.I. plain washer thin 100 Nos 0.7 21 14.70
687 1208 Bitumen washer 100 Nos 0.4 30 12.00
688 9977 Carriage of G.I. seam bolts and washers L.S. 2.73 2 5.46
689 9999 Sundries L.S. 5.33 2 10.66
690 LABOUR
691 12 Blacksmith 1st class day 0.5 505.17 252.59
700 17 Beldar day 0.5 350.00 175.00
701 9999 Sundries L.S. 12.61 2 25.22
702 30 Mistry day 0.28 403.67 113.03
703 12 Blacksmith 1st class day 0.84 505.17 424.34
704 15 Carpenter 2nd class day 0.62 403.67 250.28
705 17 Beldar day 1.68 350.00 588.00
706 TOTAL 4034.88 W
707 Add 1 % Water charges on "W" 40.3488
708 TOTAL 4075.23 X
709 Add GST (multiplying factor 0.1405) on "X" 572.57
710 TOTAL 4647.80 Y
711 Add 15 % Contractor's profit and overheads on "Y" 697.17
712 Total 5344.97 Z
713 Add Cess @ 1% on "Z" 53.45
714 Cost of 9.04 metres 5398.42
715 Cost of 1.00 metre 597.17
716 Say 597.20
717
718
719 12.8 Providing reinforced by organic fibres and/or
720 inorganic synthetic
including cutting fibrestocement
sheets size and6 mm thick
shape corrugated
wherever required.
721 sheets (as per IS: 14871) roofing up
Details of cost for 216.14 sqm area of roof
to any pitch and fixing
with polymer coated J, or L hooks, bolts and nuts 8 mm dia.
722 upto 60° pitch
723 Upto 60 degree pitch
724
725 Consider a shed of 20x10 metres.
726 (External dimensions of plinth).
727 Area of roof-
728 20.2x10.70m = 216.14 sqm.
729 MATERIAL
730 Sheets used = 2x20 nos.x3.00mx1.05m
731 =126.00sqm+
732 2x20nos.x2.50mx1.05m=105.00sqm.
733 Total = 231.00sqm. + Add 3% wastage = 6.93
734 Total = 237.93sqm.
735 223 Oorganic fibres and/or inorganic synthetic sqm 237.93 225 53534.25
736 fibres
737 2x20x0.42147 = 1.68588 +
738 2x20x0.35123= 1.4049
739 Total = 3.0908+
740 Add 3 % wastage = 0.092
741 Total = 3.1835 Say 3.184 t
749 2273 Carriage of A.C.sheet and accessories tonne 3.184 94.34 300.38
750 1023 Galvanised steel J or L hooks 8 mm dia 10 Nos 47.6 120 5712.00
751 1208 Bitumen washer 100 Nos 4.76 30 142.80
752 1209 G.I. plain washer thick 100 Nos 4.76 35 166.60
753 9977 Carriage of bolts and nuts, washers etc. L.S. 8.06 2 16.12
754 9999 Sundries L.S. 39.52 2 79.04
755 LABOUR
756 30 Mistry day 2.34 403.67 944.59
757 15 Carpenter 2nd class day 9.34 403.67 3770.28
758 17 Beldar day 9.34 350.00 3269.00
759 TOTAL 67935.06 W
760 Add 1 % Water charges on "W" 679.3506
761 TOTAL 68614.41 X
762 Add GST (multiplying factor 0.1405) on "X" 9640.32
763 TOTAL 78254.73 Y
764 Add 15 % Contractor's profit and overheads on "Y" 11738.21
765 Total 89992.94 Z
766 Add Cess @ 1% on "Z" 899.93
767 Cost of 216.14 sqm. 90892.87
768 Cost of 1.00 sqm. 420.53
769 Say 420.50
770
771
772
773 12.9 Extra for straight cutting in reinforced by organic
774 fibres
stacks,and/or inorganic
skylights etc. synthetic fibres cement corrugated,
775 semi corrugated 6 mm thick sheet roofing for making
Details of cost for 3 metres of periphery Area
openings of area exceeding 40 square decimeter for chimney
776
777 of cutting 0.9mx0.6m=0.54sqm. Perimeter = 3 metres
778
779 LABOUR
780 14 Carpenter 1st class day 0.12 505.17 60.62
781 17 Beldar day 0.12 350.00 42.00
782 TOTAL 102.62 W
783 Add 1 % Water charges on "W" 1.0262
784 TOTAL 103.65 X
785 Add GST (multiplying factor 0.1405) on "X" 14.56
786 TOTAL 118.21 Y
787 Add 15 % Contractor's profit and overheads on "Y" 17.73
788 Total 135.94 Z
789 Add Cess @ 1% on "Z" 1.36
790 Cost of 3.00 metres of periphery 137.30
791 Cost of 1.00 metre of periphery 45.77
792 Say 45.80
793
801
802
803
804 12.10 Extra for circular cutting in reinforced by organic
805 fibres and/or
Details of inorganic
cost for 4 holes of synthetic
0.72 metric fibres cement corrugated/
806 semi corrugated 6 mm thick
diameter i.e. 9.05 metric periphery
sheet roofing for making
openings of area exceeding 40 square decimeter.
807 LABOUR
808
809 14 Carpenter 1st class day 1 505.17 505.17
810 17 Beldar day 1 350.00 350.00
811 TOTAL 855.17 W
812 Add 1 % Water charges on "W" 8.5517
813 TOTAL 863.72 X
814 Add GST (multiplying factor 0.1405) on "X" 121.35
815 TOTAL 985.07 Y
816 Add 15 % Contractor's profit and overheads on "Y" 147.76
817 Total 1132.83 Z
818 Add Cess @ 1% on "Z" 11.33
819 Cost of 9.05 metres of periphery 1144.16
820 Cost of 1.00 metre of periphery 126.43
821 Say 126.40
822
823
824 12.11 Extra for providing and fixing wind ties of 40x 6 mm
825 flat iron
Details section.
of cost for 30 metres
826 Extra for providing and fixing wind ties of
827 40x6mm flat iron section.
828 M.S. flat 40x6mm = 30 metres+ wastage @
829 5% = 1.5 metres
830 = 31.50 metres @ 1.9 Kg per metre
831 = 59.85 Kg. = 0.5985 quintal
832 1008 Flats upto 10 mm in thickness quintal 0.5985 5300 3172.05
833 2205 Carriage of Steel tonne 0.06 94.34 5.66
834 9999 Sundries L.S. 20.67 2 41.34
835 12 Blacksmith 1st class day 0.5 505.17 252.59
836 17 Beldar day 0.5 350.00 175.00
837 TOTAL 3646.64 W
838 Add 1 % Water charges on "W" 36.4664
839 TOTAL 3683.11 X
840 Add GST (multiplying factor 0.1405) on "X" 517.48
841 TOTAL 4200.59 Y
842 Add 15 % Contractor's profit and overheads on "Y" 630.09
843 Total 4830.68 Z
844 Add Cess @ 1% on "Z" 48.31
845 Cost of 30.00 metres 4878.99
846 Cost of 1.00 metre 162.63
847 Say 162.60
848
855
856
857
858
859 12.12 Providing and fixing ridges and hips in fibre cement
860 reinforced
12.12.1 by organicserrated
Corrugated fibres and/or inorganic
adjustable synthetic fibres
ridges
861 roofing with suitable fixing accessories
Details of cost for length of ridge 20.2 metres
or self drilling
fastener and EPDM washer etc. complete.
862 One piece corrugated serrated adjustable
863 ridges
864 Consider a shed of 20x10m (external
865 dimensions at plinth).
866 Length of ridges 20.2 metre
867 MATERIAL
868 Ridge piece required each of 1.22mm
869 length = 19 nos. +
870 Add 5% wastage = 0.95 No.
871 Nos x 1.22 = 24.339 metre
872 225 Organic fibres and/or inorganic synthetic fibres metre 24.339 210 5111.19
873 roofing
874 9977 Carriage (The ridge is to be fixed with the L.S. 13.52 2 27.04
875 same hooks as the Sheets)
876 9999 Sundries L.S. 6.76 2 13.52
877 LABOUR 0
878 30 Mistry day 0.14 403.67 56.51
879 15 Carpenter 2nd class day 0.55 403.67 222.02
880 17 Beldar day 1.64 350.00 574.00
881 TOTAL 6004.28 W
882 Add 1 % Water charges on "W" 60.0428
883 TOTAL 6064.32 X
884 Add GST (multiplying factor 0.1405) on "X" 852.04
885 TOTAL 6916.36 Y
886 Add 15 % Contractor's profit and overheads on "Y" 1037.45
887 Total 7953.81 Z
888 Add Cess @ 1% on "Z" 79.54
889 Cost of 20.20 metre 8033.35
890 Cost of 1.00 metre 397.69
891 Say 397.70
892
893
894
895 12.12.2 Plain wing adjustable ridges
896 Details of cost for length of ridge 20.20 metres Plain wing adjustable ridges
897 Consider a shed of 20x10m (external
898 dimensions at plinth). Length of ridges 20.2 metre

899 MATERIAL
900 Ridge piece required each of 1.22m length
912 = 19 nos. +
913 Add 5% wastage = 0.95 No. nos x 1.22 =
914 24.339 metre
915 226 Non - Asbestos fibre (high impact poly metre 24.339 210 5111.19
916 propelene reinforced) cement plain wing
917 adjustable ridge.
918 9977 Carriage (The ridge is to be fixed with the L.S. 13.52 2 27.04
919 same hooks as the Sheets)
920 9999 Sundries L.S. 6.76 2 13.52
921 LABOUR
922 30 Mistry day 0.14 403.67 56.51
923 15 Carpenter 2nd class day 0.55 403.67 222.02
924 17 Beldar day 1.64 350.00 574.00
925 TOTAL 6004.28 W
926 Add 1 % Water charges on "W" 60.0428
927 TOTAL 6064.32 X
928 Add GST (multiplying factor 0.1405) on "X" 852.04
929 TOTAL 6916.36 Y
930 Add 15 % Contractor's profit and overheads on "Y" 1037.45
931 Total 7953.81 Z
932 Add Cess @ 1% on "Z" 79.54
933 Cost of 20.20 metre 8033.35
934 Cost of 1.00 metre 397.69
935 Say 397.70
936
937
938 12.12.3 Close fitting adjustable ridges
939 Details of cost for length of ridge 20.2 metres
940 Close fitting adjustable ridges Consider a shed
941 of 20x10m (external dimensions at plinth).
942 Length of ridges 20.2 metre
943 No. of ridge pairs required, of length
944 1.22m each = 22.00 nos. + Add 5% wastage =
945 1.10 Nos.
946 = 23.10 nos.x 1.22= 28.182 metre
947 224 Non - Asbestos fibre (high impact poly metre 28.182 210 5918.22
948 propelene reinforced) cement close fitting
949 adjustable ridge.
950 9977 Carriage L.S. 16.12 2 32.24
951 9999 Sundries L.S. 7.15 2 14.30
952 LABOUR
953 30 Mistry day 0.14 403.67 56.51
954 15 Carpenter 2nd class day 0.55 403.67 222.02
955 17 Beldar day 1.64 350.00 574.00
956 TOTAL 6817.29 W
957 Add 1 % Water charges on "W" 68.1729
958 TOTAL 6885.46 X
959 Add GST (multiplying factor 0.1405) on "X" 967.41
960 TOTAL 7852.87 Y
961 Add 15 % Contractor's profit and overheads on "Y" 1177.93
962 832 Total 9030.80 Z
963 Add Cess @ 1% on "Z" 90.31
964 Cost of 20.20 metre 9121.11
966 Cost of 1.00 metre 451.54
967 Say 451.50
974
975
976
977
978 12.12.4 Unserrated adjustable hips
979 Details of cost for a shed with hip as 20.2 metres
980 Unserrated adjustable hips
982 Consider a shed with hip as 20.2 metres No. of hi pieces required = 19 pairs
Length of each pair 1.22 metres
984 Add 5 % wastage
986 = 0.95 pairs
988 = 19.95 pairs x 1.22 = 24.339 metre
990 227 Non - Asbestos fibre (high impact poly metre 24.339 210 5111.19
991 propelene reinforced) cement unserrated
992 adjustable ridge for hips.
993 9977 Carriage L.S. 6.76 2 13.52
994 9999 Sundries L.S. 6.63 2 13.26
995 LABOUR
996 30 Mistry day 0.14 403.67 56.51
997 15 Carpenter 2nd class day 0.55 403.67 222.02
998 17 Beldar day 1.64 350.00 574.00
999 TOTAL 5990.50 W
1000 Add 1 % Water charges on "W" 59.905
1001 TOTAL 6050.41 X
1002 Add GST (multiplying factor 0.1405) on "X" 850.08
1003 TOTAL 6900.49 Y
1004 Add 15 % Contractor's profit and overheads on "Y" 1035.07
1005 Total 7935.56 Z
1006 Add Cess @ 1% on "Z" 79.36
1007 Cost of 20.20 metre 8014.92
1008 Cost of 1.00 metre 396.78
1009 Say 396.80
1010
1011
1018
1019 12.13 Providing and fixing fibre cement reinforced by
1020 organic fibres and/or inorganic synthetic fibres roofing
1021 accessories in all colours with polymer coated J or L hooks,
complete:
bolts and nuts and or G.I. seam bolts and nuts, G.I. plain and
1022 12.13.1 Corrugated apron pieces
1023 Details for shed of 20.2 metres completed length
1024 MATERIAL
1025 Corrugated appron pieces of 1.12 metre
1026 length = 20 nos.+
1027 Add 5% wastage = 1.0 No.
1028 Total = 21 nos.x 1.12=23.52 metre
1029 228 Organic fibres and/or inorganic synthetic fibres metre 23.52 210 4939.20
1030 roofing accessories appron piece.
1031 9977 Carriage of appron pieces. (The appron pieces L.S. 3.25 2 6.50
1032 are to be fixed with the same hooks as the
1033 sheets)
1034 9999 Sundries L.S. 3.25 2 6.50
1035 LABOUR
1036 30 Mistry day 0.07 403.67 28.26
1037 15 Carpenter 2nd class day 0.28 403.67 113.03
1038 17 Beldar day 0.82 350.00 287.00
1039 TOTAL 5380.49 W
1040 Add 1 % Water charges on "W" 53.8049
1041 TOTAL 5434.29 X
1042 Add GST (multiplying factor 0.1405) on "X" 763.52
1043 TOTAL 6197.81 Y
1044 Add 15 % Contractor's profit and overheads on "Y" 929.67
1045 Total 7127.48 Z
1046 Add Cess @ 1% on "Z" 71.27
1047 Cost of 20.20 metre 7198.75
1048 Cost of 1.00 metre 356.37
1049 Say 356.40

1050 12.13.2 Eave's filler pieces


1051 Details of eaves filler for a shed of 20.2 metres complete length
1052 MATERIAL
1053 Organic fibres and/or inorganic synthetic fibres
1054 roofing filler pieces of 0.16 metres length = 20
1055 nos.+
1056 Add 5% wastage = 1.0 No.
1057 Total = 21 nos.
1058 229 Non - Asbestos fibre (high impact poly each 21 175 3675.00
1059 propelene reinforced) cement eaves filler
1060 piece.
1069 9999 The eaves filler pieces are to be fixed with the L.S. 3.25 2 6.50
1070 same hooks as the sheets
1071 9999 Sundries L.S. 3.25 2 6.50
1072 LABOUR
1073 30 Mistry day 0.07 403.67 28.26
1074 15 Carpenter 2nd class day 0.28 403.67 113.03
1075 17 Beldar day 0.82 350.00 287.00
1076 TOTAL 4116.29 W
1077 Add 1 % Water charges on "W" 41.1629
1078 TOTAL 4157.45 X
1079 Add GST (multiplying factor 0.1405) on "X" 584.12
1080 TOTAL 4741.57 Y
1081 Add 15 % Contractor's profit and overheads on "Y" 711.24
1082 Total 5452.81 Z
1083 Add Cess @ 1% on "Z" 54.53
1084 Cost of 20.20 metre 5507.34
1085 Cost of 1.00 metre 272.64
1086 Say 272.60
1087
1088
1089
1090 12.13.3 North light curves
1091 Details of North light curve 20.2 metres long complete length
1092 MATERIAL
1093 North light curves of 1.016 metres nominal
1094 length = 20 nos. + Add 5% wastage = 1.0 No.
1095 = 21 nos.x 1.016 = 21.336 metre
1096 230 Organic fibres and/or inorganic synthetic fibres metre 21.336 280 5974.08
1097 roofing cement north light curves.
1098 1023 Galvanised steel J or L hooks 8 mm dia 10 Nos 4 120 480.00
1099 1209 G.I. plain washer thick 100 Nos 0.4 35 14.00
1100 1208 Bitumen washer 100 Nos 0.4 30 12.00
1101 9977 Carriage of hooks, nuts, washers and curves L.S. 9.88 2 19.76
1102 9999 Sundries L.S. 6.24 2 12.48
1103 LABOUR
1104 30 Mistry day 0.1 403.67 40.37
1105 15 Carpenter 2nd class day 0.3 403.67 121.10
1106 17 Beldar day 1 350.00 350.00
1107 TOTAL 7023.79 W
1108 Add 1 % Water charges on "W" 70.2379
1109 TOTAL 7094.03 X
1110 Add GST (multiplying factor 0.1405) on "X" 996.71
1111 TOTAL 8090.74 Y
1112 Add 15 % Contractor's profit and overheads on "Y" 1213.61
1113 835 Total 9304.35 Z
1114 Add Cess @ 1% on "Z" 93.04
1115 Cost of 20.20 metre 9397.39
1117 Cost of 1.00 metre 465.22
1118 Say 465.20
1126
1127
1128
1129
1130
1131 12.13.4 Ventilator curves
1132 Details of ventilator curve 20.2 metres long complete length
1133 MATERIAL
1134 North light curves of 1.016 metres nominal length = 20 nos. + Add 5%
wastage = 1.0 No.
1135
1136 Total = 21 nos.x 1.016 = 21.336 metre
1137 231 Organic fibres and/or inorganic synthetic fibres each 21.336 310 6614.16
1138 roofing cement ventilator curves.
1139 1023 Galvanised steel J or L hooks 8 mm dia 10 Nos 4 120 480.00
1140 1209 G.I. plain washer thick 100 Nos 0.4 35 14.00
1141 1208 Bitumen washer 100 Nos 0.4 30 12.00
1142 9977 Carriage of hooks, nuts, washers and curves L.S. 9.88 2 19.76
1143 9999 Sundries L.S. 6.24 2 12.48
1144 LABOUR
1145 30 Mistry day 0.1 403.67 40.37
1146 15 Carpenter 2nd class day 0.3 403.67 121.10
1147 17 Beldar day 1 350.00 350.00
1148 TOTAL 7663.87 W
1149 Add 1 % Water charges on "W" 76.6387
1150 TOTAL 7740.51 X
1151 Add GST (multiplying factor 0.1405) on "X" 1087.54
1152 TOTAL 8828.05 Y
1153 Add 15 % Contractor's profit and overheads on "Y" 1324.21
1154 Total 10152.26 Z
1155 Add Cess @ 1% on "Z" 101.52
1156 Cost of 20.20 metre 10253.78
1157 Cost of 1.00 metre 507.61
1158 Say 507.60
1159
1160
1167
1168
1169 12.13.5 Barge boards
1170 Details of cost for 9.70 metres
1171 Completed length of barge boards
1172 MATERIAL
1173 Barge boards 2.50metres = 4 nos. x 2.50
1174 = 10.00 metre
1175 Add 5% wastage = 0.50 metre.
1176 Total = 10.50 metre.
1177 232 Organic fibres and/or inorganic synthetic fibres metre 10.5 400 4200.00
1178 roofing cement barge boards 6 mm thick.
1179 222 Seam bolts and nuts 6 mm dia and 25 mm 10 Nos 0.5 10 5.00
1180 long
1181 1211 G.I. plain washer for seam bolts 100 Nos 0.1 32 3.20
1182 1208 Bitumen washer 100 Nos 0.05 30 1.50
1183 9977 Carriage of barge boards, bolts, nuts and L.S. 9.36 2 18.72
1184 washers
1185 9999 Sundries L.S. 6.76 2 13.52
1186 LABOUR
1187 30 Mistry day 0.04 403.67 16.15
1188 15 Carpenter 2nd class day 0.06 403.67 24.22
1189 17 Beldar day 0.4 350.00 140.00
1190 TOTAL 4422.31 W
1191 Add 1 % Water charges on "W" 44.2231
1192 TOTAL 4466.53 X
1193 Add GST (multiplying factor 0.1405) on "X" 627.55
1194 TOTAL 5094.08 Y
1195 Add 15 % Contractor's profit and overheads on "Y" 764.11
1196 Total 5858.19 Z
1197 Add Cess @ 1% on "Z" 58.58
1198 Cost of 9.70 metre 5916.77
1199 Cost of 1.00 metre 609.98
1200 Say 610.00

1201 12.13.6 Ridge finials


1202 Details of a pair of ridge final
1203 MATERIAL
1204 Ride final = pair
1205 Add 5% wastage = 0.05pair. Total = 1.05 pair
1206 233 Organic fibres and/or inorganic synthetic fibres pair 1.05 165 173.25
1207 roofing cement ridge finial .
1217 9988 Carriage, sundries, fixing charges including L.S. 10.79 2 21.58
1218 providing and fixing, seam bolts and nuts, with
1219 G.I. and bitumen washers
1220 TOTAL 194.83 W
1221 Add 1 % Water charges on "W" 1.9483
1222 TOTAL 196.78 X
1223 Add GST (multiplying factor 0.1405) on "X" 27.65
1224 TOTAL 224.43 Y
1225 Add 15 % Contractor's profit and overheads on "Y" 33.66
1226 Total 258.09 Z
1227 Add Cess @ 1% on "Z" 2.58
1228 Cost of 1.00 pair 260.67
1229 Say 260.67
1230 260.70

1231
1232 12.13.7 Special north light curves
1233 Details of special north light ventilator curve
1234 20.2 metres long complete length
1235 MATERIAL
1236 Special north light curves of 1.016 metres
1237 nominal length = 20 nos. + Add 5% wastage =
1238 1.0 No.
1239 Total = 21 nos.
1240 234 Organic fibres and/or inorganic synthetic fibres each 21 555 11655.00
1241 roofing cement special north light curves.
1242 1023 Galvanised steel J or L hooks 8 mm dia 10 Nos 4 120 480.00
1243 1209 G.I. plain washer thick 100 Nos 0.4 35 14.00
1244 1208 Bitumen washer 100 Nos 0.4 30 12.00
1245 9977 Carriage of hooks, nuts, washers and curves L.S. 9.88 2 19.76
1246 9999 Sundries L.S. 6.24 2 12.48
1247 LABOUR
1248 30 Mistry day 0.1 403.67 40.37
1249 15 Carpenter 2nd class day 0.3 403.67 121.10
1250 17 Beldar day 1 350.00 350.00
1251 TOTAL 12704.71 W
1252 Add 1 % Water charges on "W" 127.0471
1253 TOTAL 12831.76 X
1254 Add GST (multiplying factor 0.1405) on "X" 1802.86
1255 TOTAL 14634.62 Y
1256 Add 15 % Contractor's profit and overheads on "Y" 2195.19
1257 Total 16829.81 Z
1258 Add Cess @ 1% on "Z" 168.30
1259 Cost of 20 nos 16998.11
1260 Cost of 1.00 no 849.91
1261 Say 849.90
1262
1269
1270
1271 12.13.8 S type louvers
1272 Details of cost for 8.74 metres
1273 MATERIAL
1274 S type louvers = 5 nos.+ Add 5% wastage =
1275 0.25 nos.
1276 Total = 5.25 nos.
1277 235 Organic fibres and/or inorganic synthetic fibres each 5.25 260 1365.00
1278 roofing cement S type louvers.
1279 9977 Carriage L.S. 10.79 2 21.58
1280 1031 Galvanised steel bolts & nuts 10 mm dia and each 6 20 120.00
1281 27 cm long both sides threaded with 4
1282 galvanised steel nuts
1283 1032 Galvanised steel bolts 10 mm dia and each 6 6 36.00
1284 7 cm long with nuts
1285 1208 Bitumen washer 100 Nos 0.18 30 5.40
1286 1210 G.I. plain washer thin 100 Nos 0.36 21 7.56
1287 9977 Carriage of bolts and nuts and washers L.S. 2.73 2 5.46
1288 9999 Sundries L.S. 13.39 2 26.78
1289 LABOUR
1290 14 Carpenter 1st class day 1 505.17 505.17
1291 17 Beldar day 1 350.00 350.00
1292 12 Blacksmith 1st class day 0.12 505.17 60.62
1293 TOTAL 2503.57 W
1294 Add 1 % Water charges on "W" 25.0357
1295 TOTAL 2528.61 X
1296 Add GST (multiplying factor 0.1405) on "X" 355.27
1297 TOTAL 2883.88 Y
1298 Add 15 % Contractor's profit and overheads on 432.58
1299 Total 3316.46 Z
1300 Add Cess @ 1% on "Z" 33.16
1301 Cost of 8.74 metres 3349.62
1302 Cost of 1.00 metre 383.25
1303 Say 383.30
1304
1305
1306
1307
1308 12.14 Providing flat iron brackets 50x3 mm size with
1309 necessary bolts,
washers etc. nuts and
for fixing G.S. sheets gutters with purlins.
1310 Detail of cost for 20 metres
1311 MATERIAL
1312 Flat 50x3mm size
1313 1008 Flats upto 10 mm in thickness quintal 0.1163 5300 616.39
1314 1025 Mild stel bolts 6 mm dia and 25 mm long with 10 Nos 3.8 10 38.00
1315 hexagonal head
1323 1210 G.I. plain washer thin 100 Nos 0.19 21 3.99
1324 9999 Sundries L.S. 1.04 2 2.08
1325 12 Blacksmith 1st class day 0.38 505.17 191.96
1326 17 Beldar day 0.38 350.00 133.00
1327 TOTAL 985.42 W
1328 Add 1 % Water charges on "W" 9.8542
1329 TOTAL 995.27 X
1330 Add GST (multiplying factor 0.1405) on "X" 139.84
1331 TOTAL 1135.11 Y
1332 Add 15 % Contractor's profit and overheads on "Y" 170.27
1333 Total 1305.38 Z
1334 Add Cess @ 1% on "Z" 13.05
1335 Cost of 20.00 metres 1318.43
1336 Cost of 1.00 metre 65.92
1337 Say 65.90
1338
1339
1340
1341 12.15 Painting top of roofs with bitumen of approved
1342 quality
soaked @ in 17kg per 10
kerosene oilsqm impregnated
complete : with a coat of coarse
1343 sand at 60 cudm per 10 sqm, including cleaning the slab
12.15.1
surface withWithbrushes
residualand
type petroleum
finally with abitumen
piece of of grade
cloth VG -
lightly
1344 10
Details of cost for 10 Sqm.
1345 MATERIAL
1346 Bitumen 80/100
1347 309 Paving bitumen VG-10 of approved quality tonne 0.017 48000 816.00
1348 771 Kerosene oil litre 1.22 50 61.00
1349 370 Coal (steam) quintal 0.035 440 15.40
1350 2211 Carriage of Tar bitumen tonne 0.017 106.13 1.80
1351 982 Coarse sand cum 0.06 800 48.00
1352 2203 Carriage of Coarse sand cum 0.06 106.13 6.37
1353 LABOUR
1354 17 Beldar day 0.38 350.00 133.00
1355 (for cleaning the surface, applying kerosene
1356 oil, heating materials and carrying the hot tar
1357 over the roof
1358 31 Painter day 0.15 403.67 60.55
1359 9999 Sundries (Brushes and T and P) L.S. 13.52 2 27.04
1360 TOTAL 1169.16 W
1361 Add 1 % Water charges on "W" 11.6916
1362 TOTAL 1180.85 X
1363 Add GST (multiplying factor 0.1405) on "X" 165.91
1364 TOTAL 1346.76 Y
1365 Add 15 % Contractor's profit and overheads on "Y" 202.01
1366 Total 1548.77 Z
1368 Add Cess @ 1% on "Z" 15.49
1369 Cost of 10.00 sqm. 1564.26
1370 Cost of 1 Sqm. 156.43
1371 Say 156.40
1372
1373
1374
1375
1376
1377
1378
1379 12.16 10 cm thick (average) mud phaska of damped brick
1380 earth
weightonofroofs laidand
cement to slope consolidated
finished neat: and plastered with
1381 25 mm thick mud mortar mixed with bhusa @ 35 kg per cum
12.16.1 Withgobri
of earth and commonleapingburnt clay
with mixF.P.S.(non
1:1 (1 claymodular) brick
: 1 cow dung)
1382 tile of class designation 10
1383 Details of cost for (mud) 10.00sqm.
1384 MATERIAL
1385 Mud Phuska = 1.048 cum. +
1386 Wastage 20% = 0.209 = 1.257 cum.
1387 811 Mud (dry) cum 1.257 165 207.41
1388 Mud mortar for 25 mm thick plaster over
1389 phuska
1390 3.18 Rate as per Item Number 3.18 of SH: Mortars cum 0.263 521.90 137.26
1391 Bhusa 0.263x35 = 9.20 +
1392 5% wastage = 0.46
1393 Total = 9.66 Kg. say 10 kg = 0.1 q
1394 308 Bhusa quintal 0.1 500 50.00
1395 9999 Cowdung L.S. 5.33 2 10.66
1396 9999 Mud mortar for gobri leaping L.S. 8.06 2 16.12
1397 9977 Carriage of bhusa and cowdung Tile bricks L.S. 2.73 2 5.46
1398 22.9x11.4x4.4cm of designation 100
1399 1984 Common burnt clay F.P.S. (non modular) 1000 Nos 0.38 4500 1710.00
1400 bricks tile class designation 10
1401 2207 Carriage of Brick tiles 1000 Nos 0.38 169.81 64.53
1402 Cement mortar for grouting 1:3
1403 (1 cement : 3 fine sand)
1404 3.3 Rate as per Item Number 3.3 of SH: Mortars cum 0.061 3670.3 223.89
1405 Integral water proofing compound 2% by
1406 weight of cement
1407 1213 Water proofing materials kilogram 0.006 35 0.21
1408 9999 Sundries L.S. 6.76 2 13.52
1409 LABOUR
1410 24 Mason (brick layer) 2nd class day 1.3 403.67 524.77
1418 17 Beldar day 3.75 350.00 1312.50
1419 11 Bhisti day 1.1 350.00 385.00
1420 TOTAL 4661.33 W
1421 Add 1 % Water charges on "W" 46.6133
1422 TOTAL 4707.94 X
1423 Add GST (multiplying factor 0.1405) on "X" 661.47
1424 TOTAL 5369.41 Y
1425 Add 15 % Contractor's profit and overheads on "Y" 805.41
1426 Total 6174.82 Z
1427 Add Cess @ 1% on "Z" 61.75
1428 Cost of 10.00 sqm. 6236.57
1429 Cost of 1 Sqm. 623.66
1430 Say 623.70
1431
1432
1433 12.17 10cm thick (average) mud phaska of damped brick
1434 earth
weightonofroofs laidand
cement to slope consolidated
finished neat. and plastered with
1435 25 mm thick mud mortar with bhusha @ 35 kg per cum of
12.17.1
earth andWith
gobrimachine
leaping moulded
with mix common
1:1 (1 clayburnt clay F.P.S.and
: 1 cow-dung)
1436 (non modular) brick tiles of
class designation 12.5, conforming to IS 2690
1437 Details of cost for (mud) 10.00sqm.
1438
1439 MATERIAL
1440 Mud Phuska = 1.048 cum. Wastage 20% =
1441 0.209 = 1.257 cum.
1442 811 Mud (dry) cum 1.257 165 207.41
1443 Mud mortar for 25 mm thick plaster over
1444 phuska
1445 3.18 Rate as per Item Number 3.18 of cum 0.263 521.90 137.26
1446 SH: Mortars
1447 Bhusa 0.263x35 = 9.20
1448 5% wastage = 0.46
1449 Total = 9.66 Kg. say 10 kg = 0.1 q
1450 308 Bhusa quintal 0.1 500 50.00
1451 9999 Cowdung L.S. 5.33 2 10.66
1452 9999 Mud mortar for gobri leaping L.S. 8.06 2 16.12
1453 9977 Carriage of bhusa and cowdung L.S. 2.73 2 5.46
1454 7904 Machine moulded common burnt clay tile 1000 Nos 0.38 4900 1862.00
1455 bricks of class designation 12.5
1456 2207 Carriage of Brick tiles 1000 Nos 0.38 169.81 64.53
1457 Cement mortar for grouting 1:3 (1 cement :
1458 3 fine sand)
1459 3.3 Rate as per Item Number 3.3 of SH: Mortars cum 0.061 3670.3 223.89
1460 Integral water proofing compound 2% by
1461 weight of cement
1462 1213 Water proofing materials kilogram 0.006 35 0.21
1470 9999 Sundries L.S. 6.76 2 13.52
1471 LABOUR
1472 24 Mason (brick layer) 2nd class day 1.3 403.67 524.77
1473 17 Beldar day 3.75 350.00 1312.50
1474 11 Bhisti day 1.1 350.00 385.00
1475 TOTAL 4813.33 W
1476 Add 1 % Water charges on "W" 48.1333
1477 TOTAL 4861.46 X
1478 Add GST (multiplying factor 0.1405) on "X" 683.04
1479 TOTAL 5544.50 Y
1480 Add 15 % Contractor's profit and overheads on "Y" 831.68
1481 Total 6376.18 Z
1482 Add Cess @ 1% on "Z" 63.76
1483 Cost of 10.00 sqm. 6439.94
1484 Cost of 1 Sqm. 643.99
1485 Say 644.00
1486
1487
1488 12.18 Extra for every additional 1 cm thickness of mud
1489 phaska.
Detail of cost for 10 sqm
1490 MATERIAL
1491 For 10 cm thickness
1492 Mud Phuska = 1.048 cum. + Wastage 20% =
1493 0.209 = 1.257 cum.
1494 Quantity for 1 cm thickness 1.257/10
1495 = 0.1257 cum say 0.13 cum
1496 811 Mud (dry) cum 0.13 165 21.45
1497 17 Beldar day 0.07 350.00 24.50
1498 11 Bhisti day 0.04 350.00 14.00
1499 9999 Labour for leaping and carring to roof L.S. 26.91 2 53.82
1500 TOTAL 113.77 W
1501 Add 1 % Water charges on "W" 1.1377
1502 TOTAL 114.91 X
1503 Add GST (multiplying factor 0.1405) on "X" 16.14
1504 TOTAL 131.05 Y
1505 Add 15 % Contractor's profit and overheads on "Y" 19.66
1506 Total 150.71 Z
1507 Add Cess @ 1% on "Z" 1.51
1508 Cost of 10.00 sqm. 152.22
1509 Cost of 1 Sqm. 15.22
1510 Say 15.20
1511
1512
1521
1522
1523 12.19 Providing and laying brick tiles over mumty roofs,
1524 grouted
cement :with cement
3 fine sand) mortar 1:3 (1 cement
and finished neat: : 3 fine sand)
1525 mixed with 2% of integral water proofing compound by
weight of cement, over 12 mm layer of cement mortar 1:3 (1
1526 12.19.1 With common burnt clay F.P.S. (non modular) brick
1527 tiles of class designation
1528 10
1529 Details of cost for 10 sqm.
1530
1531 MATERIAL
1532 1984 Common burnt clay F.P.S. (non modular) 1000 Nos 0.38 4500 1710.00
1533 bricks tile class designation 10
1534 2207 Carriage of Brick tiles 1000 Nos 0.38 169.81 64.53
1535 Cement mortar for grouting 1:3 (1 cement :
1536 3 fine sand)
1537 3.3 Rate as per Item Number 3.3 of SH: Mortars cum 0.179 3670.3 656.98
1538 Integral water proofing compound 2% by
1539 weight of cement
1540 1213 Water proofing materials kilogram 0.005 35 0.18
1541 LABOUR
1542 24 Mason (brick layer) 2nd class day 0.81 403.67 326.97
1543 18 Coolie day 1.08 350.00 378.00
1544 11 Bhisti day 0.27 350.00 94.50
1545 9999 Sundries L.S. 1.82 2 3.64
1546 TOTAL 3234.80 W
1547 Add 1 % Water charges on "W" 32.348
1548 TOTAL 3267.15 X
1549 Add GST (multiplying factor 0.1405) on "X" 459.03
1550 TOTAL 3726.18 Y
1551 Add 15 % Contractor's profit and overheads on "Y" 558.93
1552 Total 4285.11 Z
1553 Add Cess @ 1% on "Z" 42.85
1554 Cost of 10.00 sqm. 4327.96
1555 Cost of 1 Sqm. 432.8
1556 Say 432.80
1557
1558
1559
1560 12.20 Providing and laying pressed clay tiles (as per
1561 approved
and finished pattern
neat 20 mm nominal thickness of approved size)
complete.
1562 on roofs jointed with
Details of cost for 10 sqm.
cement mortar 1:4 (1 cement : 4 coarse
sand) mixed with 2% integral water proofing compound, laid
1563 MATERIAL
1572 Details of cost for 10 metres cement concrete

1573
1575 7266 Pressed clay tiles 20 mm thick 1000 Nos 0.16 8600 1376.00
1576 250 x 250 mm size
1577 2207 Carriage of Brick tiles 1000 Nos 0.16 169.81 27.17
1578 Cement mortar 1 : 4 (1 cement : 4 coarse
1579 sand)
1580 3.9 Rate as per Item Number 3.9 of SH: Mortars cum 0.037 3548.00 131.28
1581 Integral water proofing compound 2% by
1582 weight of cement
1583 1213 Water proofing materials kilogram 0.01 35 0.35
1584 Cement mortar 1 : 4 (1 cement : 4 coarse
1585 sand)
1586 3.9 Rate as per Item Number 3.9 of cum 0.224 3548.00 794.75
1587 SH: Mortars
1588 LABOUR
1589 23 Mason (brick layer) 1st class day 0.6 505.17 303.10
1590 17 Beldar day 2.6 350.00 910.00
1591 9999 Sundries L.S. 13 2 26.00
1592 TOTAL 3568.65 W
1593 Add 1 % Water charges on "W" 35.6865
1594 TOTAL 3604.34 X
1595 Add GST (multiplying factor 0.1405) on "X" 506.41
1596 TOTAL 4110.75 Y
1597 Add 15 % Contractor's profit and overheads on 616.61
1598 "Y" 4727.36 Z
1599 Total 47.27
1600 Add Cess @ 1% on "Z" 4774.63
1601 Cost of 10.00 sqm. 477.46
1602 Cost of 1 Sqm. 477.50
1603 Say
1604
1605
1606
1607 12.21 Providing gola 75x75 mm in cement concrete 1:2:4 (1
1608 cement
12.21.1 : In
2 coarse sanddeep
75x75 mm : 4 stone
chaseaggregate 10 mm and down
1609 gauge), including finishing with cement mortar 1:3 (1
cement : 3 fine sand) as per standard design :
1610 297 Stone Aggregate (Single size) : 10 mm cum 0.0836 810 67.72
1611 nominal size
1612 2202 Carriage of Stone aggregate below 40 mm cum 0.0836 106.13 8.87
1613 nominal size
1614 982 Coarse sand cum 0.0418 800 33.44
1615 2203 Carriage of Coarse sand cum 0.0418 106.13 4.44
1616 367 Portland Cement (OPC-43 grade) tonne 0.03 4375 131.25
1617 2209 Carriage of Cement tonne 0.03 94.34 2.83
1618 17 Beldar day 0.085 350.00 29.75
1619 18 Coolie day 0.056 350.00 19.60
1629 11 Bhisti day 0.025 350.00 8.75
1630 23 Mason (brick layer) 1st class day 0.005 505.17 2.53
1631 24 Mason (brick layer) 2nd class day 0.005 403.67 2.02
1632 28 Mate day 0.0037 350.00 1.30
1633 9999 Hire and running charge of mechanical mixer L.S. 2.47 2 4.94
1634 9999 Sundries L.S. 1.3 2 2.60
1635 23 Mason (brick layer) 1st class day 0.15 505.17 75.78
1636 24 Mason (brick layer) 2nd class day 0.15 403.67 60.55
1637 9999 Sundries L.S. 5.07 2 10.14
1638 23 Mason (brick layer) 1st class day 0.25 505.17 126.29
1639 24 Mason (brick layer) 2nd class day 0.25 403.67 100.92
1640 17 Beldar day 1 350.00 350.00
1641 9977 Carriage L.S. 8.06 2 16.12
1642 Cement mortar for grouting 1:3
1643 (1 cement : 3 fine sand)
1644 3.3 Rate as per Item Number 3.3 of cum 0.009 3670.3 33.03
1645 SH: Mortars
1646 40 Mason (average) day 0.081 403.67 32.70
1647 18 Coolie day 0.101 350.00 35.35
1648 11 Bhisti day 0.033 350.00 11.55
1649 9999 Hire and running charges of mechanical mixer L.S. 1.69 2 3.38
1650 9999 Sundries L.S. 1.43 2 2.86
1651 TOTAL 1178.71 W
1652 Add 1 % Water charges on "W" 11.7871
1653 TOTAL 1190.50 X
1654 Add GST (multiplying factor 0.1405) on "X" 167.26
1655 TOTAL 1357.76 Y
1656 Add 15 % Contractor's profit and overheads on "Y" 203.66
1657 Total 1561.42 Z
1658 Add Cess @ 1% on "Z" 15.61
1659 Cost of 10.00 sqm. 1577.03
1660 Cost of 1 Sqm. 157.7
1661 Say 157.70
1662
1663
1675
1676
1677
1678 12.22 Making khurras 45x45 cm with average minimum
1679 thickness
rounding the of 5edges
cm cement concrete
and making and1:2:4 (1 cement
finishing : 2 coarse
the outlet
1680 sand :
complete.4 graded stone
Details of cost for 1 no.
aggregate of 20 mm nominal size) over
P.V.C. sheet 1 m x1 m x 400 micron, finished with 12 mm
1681
1682 295 Stone Aggregate (Single size) : 20 mm cum 0.0067 800 5.36
1683 nominal size
1684 297 Stone Aggregate (Single size) : 10 mm cum 0.0022 810 1.78
1685 nominal size
1686 2202 Carriage of Stone aggregate below 40 mm cum 0.0089 106.13 0.94
1687 nominal size
1688 982 Coarse sand cum 0.0044 800 3.52
1689 2203 Carriage of Coarse sand cum 0.0044 106.13 0.47
1690 367 Portland Cement (OPC-43 grade) tonne 0.0032 4375 14.00
1691 2209 Carriage of Cement tonne 0.0032 94.34 0.30
1692 17 Beldar day 0.009 350.00 3.15
1693 18 Coolie day 0.006 350.00 2.10
1694 11 Bhisti day 0.0027 350.00 0.95
1695 23 Mason (brick layer) 1st class day 0.0005 505.17 0.25
1696 24 Mason (brick layer) 2nd class day 0.0005 403.67 0.20
1697 28 Mate day 0.0004 350.00 0.14
1698 9999 Hire and running charge of mechanical mixer L.S. 0.26 2 0.52
1699 9999 Sundries L.S. 0.13 2 0.26
1700 3002 Polyvinyle chloride sheet 400 micron thick sqm 1 40 40.00
1701 Cement mortar 1:3 (1 cement : 3 coarse sand)
1702 3.8 Rate as per Item Number 3.8 of SH: Mortars cum 0.0041 4129.00 16.93
1703 40 Mason (average) day 0.0235 403.67 9.49
1704 18 Coolie day 0.0235 350.00 8.23
1705 11 Bhisti day 0.0078 350.00 2.73
1706 9999 Sundries L.S. 0.39 2 0.78
1707 367 Portland Cement (OPC-43 grade) tonne 0.0006 4375 2.63
1708 2209 Carriage of Cement tonne 0.0006 94.34 0.06
1709 40 Mason (average) day 0.008 403.67 3.23
1710 18 Coolie day 0.008 350.00 2.80
1711 9999 Rounding of edges and making outlet L.S. 0.26 2 0.52
1712 9999 Sundries L.S. 13.52 2 27.04
1713 TOTAL 148.38 W
1714 Add 1 % Water charges on "W" 1.4838
1715 TOTAL 149.86 X
1716 Add GST (multiplying factor 0.1405) on "X" 21.06
1717 TOTAL 170.92 Y
1718 Add 15 % Contractor's profit and overheads on "Y" 25.64
1719 Total 196.56 Z
1720 Add Cess @ 1% on "Z" 1.97
1721 Cost of 1 no. 198.53
1722 Say 198.53
1723 198.50
1731
1732
1733
1734 12.23 Providing sand stone slab for roofing and laying
1735 them
cementin :cement mortar
3 fine sand 1 : 4 (1 cement
) complete : 4Red
: 12.23.1 coarse sand)
sand over
stone slab
1736 wooden karries or R.C.C. battens or structural steel sections
(Karries or battens or structural steel sections to be paid
1737 12.23.1.1 40 to 50 mm thick
1738
1739 Details of cost for 10 sqm.
1740 MATERIAL
1741 1174 Red sand stone slab 45 mm and 50 mm thick sqm 11 350 3850.00
1742 (un-dressed)
1743 including wastage @ 10% = 11 sqm
1744 2216 Carriage of Stone blocks white & red sand tonne 1.27 94.34 119.81
1745 stone & kota stone slab
1746 Cement mortar 1 : 4 (1 cement : 4 coarse
1747 sand)
1748 3.9 Rate as per Item Number 3.9 of cum 0.0095 3548.00 33.71
1749 SH: Mortars
1750 Cement mortar for grouting 1:3
1751 (1 cement : 3 fine sand)
1752 3.3 Rate as per Item Number 3.3 of cum 0.0075 3670.3 27.53
1753 SH: Mortars
1754 LABOUR
1755 40 Mason (average) day 1.52 403.67 613.58
1756 10 Bandhani day 1.82 350.00 637.00
1757 18 Coolie day 1.52 350.00 532.00
1758 11 Bhisti day 0.3 350.00 105.00
1759 9999 Sundries L.S. 16.12 2 32.24
1760 TOTAL 5950.87 W
1761 Add 1 % Water charges on "W" 59.5087
1762 TOTAL 6010.38 X
1763 Add GST (multiplying factor 0.1405) on "X" 844.46
1764 TOTAL 6854.84 Y
1765 Add 15 % Contractor's profit and overheads on "Y" 1028.23
1766 Total 7883.07 Z
1767 Add Cess @ 1% on "Z" 78.83
1768 Cost of 10.00 sqm. 7961.90
1769 Cost of 1 Sqm. 796.19
1770 Say 796.20
1771
1772
1780
1781 12.23.2 White sand stone slab 12.23.2.1 40 to 50 mm thick
1782 Details of cost for 10 sqm.
1783 MATERIAL
1784 1175 White sand stone slab 45 mm and 50 mm sqm 11 300 3300.00
1785 thick (un-dressed)
1786 including wastage @ 10% = 11sqm
1787 2216 Carriage of Stone blocks white & red sand tonne 1.27 94.34 119.81
1788 stone & kota stone slab
1789 Cement mortar 1 : 4 (1 cement : 4 coarse
1790 sand)
1791 3.9 Rate as per Item Number 3.9 of SH: Mortars cum 0.0095 3548.00 33.71
1792 LABOUR
1793 40 Mason (average) day 1.52 403.67 613.58
1794 10 Bandhani day 1.82 350.00 637.00
1795 18 Coolie day 1.52 350.00 532.00
1796 11 Bhisti day 0.3 350.00 105.00
1797 9999 Sundries L.S. 16.12 2 32.24
1798 Cement mortar for grouting 1:3 (1 cement :
1799 3 fine sand)
1800 3.3 Rate as per Item Number 3.3 of SH: Mortars cum 0.0075 3670.3 27.53
1801 TOTAL 5400.87 W
1802 Add 1 % Water charges on "W" 54.0087
1803 TOTAL 5454.88 X
1804 Add GST (multiplying factor 0.1405) on "X" 766.41
1805 TOTAL 6221.29 Y
1806 Add 15 % Contractor's profit and overheads on "Y" 933.19
1807 Total 7154.48 Z
1808 Add Cess @ 1% on "Z" 71.54
1809 Cost of 10.00 sqm. 7226.02
1810 Cost of 1 Sqm. 722.6
1811 Say 722.60
1812
1813
1814 12.24 Providing and fixing insulating board ceiling of
1815 12.24.1 approved quality
Natural colour with necessary
insulating board nails etc. complete (frame
1816 work to be paid separately) :
1817 12.24.1.1 12 mm thick
1818
1819 Details of cost for 10 sqm.
1820 MATERIAL
1831 332 Natural colour insulating board:12 mm thick sqm 11 210 2310.00
1832 including 10% wastage = 11.00 sqm
1833 9977 Carriage of material L.S. 17.55 2 35.10
1834 9999 Nails L.S. 26.91 2 53.82
1835 LABOUR
1836 14 Carpenter 1st class day 2.5 505.17 1262.93
1837 17 Beldar day 2 350.00 700.00
1838 9999 Scaffolding L.S. 31.07 2 62.14
1839 9999 Sundries L.S. 31.07 2 62.14
1840 TOTAL 4486.13 W
1841 Add 1 % Water charges on "W" 44.8613
1842 TOTAL 4530.99 X
1843 Add GST (multiplying factor 0.1405) on "X" 636.60
1844 TOTAL 5167.59 Y
1845 Add 15 % Contractor's profit and overheads on "Y" 775.14
1846 Total 5942.73 Z
1847 Add Cess @ 1% on "Z" 59.43
1848 Cost of 10.00 sqm. 6002.16
1849 Cost of 1 Sqm. 600.22
1850 Say 600.20
1851

1852 12.24.2 White face insulating board 12.24.2.1 12 mm thick


1853 Details of cost for 10 sqm.
1854 MATERIAL
1855 328 White face insulating board:12 mm thick sqm 11 235 2585.00
1856 including 10% wastage = 11.00 sqm
1857 9977 Carriage of material L.S. 17.55 2 35.10
1858 9999 Nails L.S. 26.91 2 53.82
1859 LABOUR
1860 14 Carpenter 1st class day 2.5 505.17 1262.93
1861 17 Beldar day 2 350.00 700.00
1862 9999 Scaffolding L.S. 31.07 2 62.14
1863 9999 Sundries L.S. 31.07 2 62.14
1864 TOTAL 4761.13 W
1865 Add 1 % Water charges on "W" 47.6113
1866 TOTAL 4808.74 X
1867 Add GST (multiplying factor 0.1405) on "X" 675.63
1868 TOTAL 5484.37 Y
1869 Add 15 % Contractor's profit and overheads on "Y" 822.66
1870 Total 6307.03 Z
1871 Add Cess @ 1% on "Z" 63.07
1872 Cost of 10.00 sqm. 6370.10
1873 Cost of 1 Sqm. 637.01
1874 Say 637.00
1875
1876
1883
1884
1885 12.24.3 Flame retardant face insulating board
1886 12.24.3.1 12 mm thick
1887 Details of cost for 10 sqm.
1888 MATERIAL
1889 336 Flame retardent face insulating board: sqm 11 320 3520.00
1890 12 mm thick
1891 including 10% wastage = 11.00 sqm
1892 9977 Carriage of material L.S. 17.55 2 35.10
1893 9999 Nails L.S. 26.91 2 53.82
1894 LABOUR
1895 14 Carpenter 1st class day 2.5 505.17 1262.93
1896 17 Beldar day 2 350.00 700.00
1897 9999 Scaffolding L.S. 31.07 2 62.14
1898 9999 Sundries L.S. 31.07 2 62.14
1899 TOTAL 5696.13 W
1900 Add 1 % Water charges on "W" 56.9613
1901 TOTAL 5753.09 X
1902 Add GST (multiplying factor 0.1405) on "X" 808.31
1903 TOTAL 6561.40 Y
1904 Add 15 % Contractor's profit and overheads on "Y" 984.21
1905 Total 7545.61 Z
1906 Add Cess @ 1% on "Z" 75.46
1907 Cost of 10.00 sqm. 7621.07
1908 Cost of 1 Sqm. 762.11
1909 Say 762.10
1910
1911
1912
1913 12.25 Providing and fixing flat pressed 3 layer medium
1914 density
12.25.1 particle
12 mm board
thick or graded particle board (Grade I) IS:
1915 3087 marked, in ceiling with necessary nails etc. complete
Details of cost for 10 sqm.
(frame work to be paid separately):
1916 MATERIAL
1917 341 Flat pressed 3 layer particle board (medium sqm 11 288 3168.00
1918 density) Grade I :12 mm thick including 10%
1919 wastage = 11.00 sqm
1920 9977 Carriage L.S. 14.95 2 29.90
1921 9999 Nails L.S. 26.91 2 53.82
1922 LABOUR
1923 14 Carpenter 1st class day 2.5 505.17 1262.93
1924 17 Beldar day 2 350.00 700.00
1933 9999 Scaffolding L.S. 31.07 2 62.14
1934 9999 Sundries L.S. 31.07 2 62.14
1935 TOTAL 2087.21 W
1936 Add 1 % Water charges on "W" 20.8721
1937 TOTAL 2108.08 X
1938 Add GST (multiplying factor 0.1405) on "X" 296.19
1939 TOTAL 2404.27 Y
1940 Add 15 % Contractor's profit and overheads on "Y" 360.64
1941 Total 2764.91 Z
1942 Add Cess @ 1% on "Z" 27.65
1943 Cost of 10.00 sqm. 2792.56
1944 Cost of 1 Sqm. 279.26
1945 Say 279.30

1946
1947
1948
1949 12.26 Providing and fixing plain multipurpose cement
1950 board(Hight
12.26.1 6 mm pressure steam cured)
thick Cement with suitable
fiber board as per IS:screws
14862 for
1951 cement particle board
Details of cost for 10 sqm.
in ceiling etc. complete (frame work to
be paid seperatately).
1952 MATERIAL
1953 236 plain multipurpose cement board(Hight sqm 11 210 2310.00
1954 pressure steam cured) cement board 6mm
1955 thick.
1956 including 10% wastage = 11.00 sqm
1957 9977 Carriage L.S. 14.95 2 29.90
1958 9999 Nails L.S. 26.91 2 53.82
1959 LABOUR
1960 14 Carpenter 1st class day 2.5 505.17 1262.93
1961 17 Beldar day 2 350.00 700.00
1962 9999 Scaffolding L.S. 31.07 2 62.14
1963 9999 Sundries L.S. 31.07 2 62.14
1964 TOTAL 4480.93 W
1965 Add 1 % Water charges on "W" 44.8093
1966 TOTAL 4525.74 X
1967 Add GST (multiplying factor 0.1405) on "X" 635.87
1968 TOTAL 5161.61 Y
1969 Add 15 % Contractor's profit and overheads on "Y" 774.24
1970 Total 5935.85 Z
1971 Add Cess @ 1% on "Z" 59.36
1972 Cost of 10.00 sqm. 5995.21
1973 Cost of 1 Sqm. 599.52
1974 Say 599.50
1975
1976
1983
1984 12.26.2 6 mm thick Cement bonded wood particle board as
1986 per IS:14276
Details of cost for 10 sqm.
1987 MATERIAL
1988 242 6 mm thick multi purpose cement bonded sqm 11 195 2145.00
1989 wood particle board
1990 10.00 sqm + 1.00 sqm (Add wastage 10%)
1991 Total = 11.00 sqm
1992 9977 Carriage L.S. 14.95 2 29.90
1993 9999 Nails L.S. 26.91 2 53.82
1994 LABOUR
1995 14 Carpenter 1st class day 2.5 505.17 1262.93
1996 17 Beldar day 2 350.00 700.00
1997 9999 Scaffolding L.S. 31.07 2 62.14
1998 9999 Sundries L.S. 31.07 2 62.14
1999 TOTAL 4315.93 W
2000 Add 1 % Water charges on "W" 43.1593
2001 TOTAL 4359.09 X
2002 Add GST (multiplying factor 0.1405) on "X" 612.45
2003 TOTAL 4971.54 Y
2004 Add 15 % Contractor's profit and overheads on "Y" 745.73
2005 Total 5717.27 Z
2006 Add Cess @ 1% on "Z" 57.17
2007 Cost of 10.00 sqm. 5774.44
2008 Cost of 1 Sqm. 577.44
2009 Say 577.40
2010
2011
2012
2013 12.27 Extra for Circular cutting including wastages in
2014 ceiling
12.27.1 with:
2nd class teak wood planks 20 mm thick
2015 Details of cost for 10 holes of 0.5m dia each
2016 (15.71m)
2017 MATERIAL
2018 0.5 metre dia. each = 10x22/7x0.5=15.71m
2019 Area = 10x(22/7)/4x0.5x0.5 = 1.96sqm. +
2020 Wastage @ 10% = 0.19 sqm.
2021 = 2.15 sqm x 20mm = 0.043 cum
2022 1190 Second class teak wood in planks 10 cudm 4.3 791 3401.30
2023 2204 Carriage of Timber cum 0.041 121.29 4.97
2024 637 Bright finished or black enamelled mild 100 Nos 0.31 60 18.60
2025 steel screws 40 mm
2026 LABOUR
2027 14 Carpenter 1st class day 2.65 505.17 1338.70
2028 15 Carpenter 2nd class day 0.145 403.67 58.53
2029 17 Beldar day 2.79 350.00 976.50
2030 9999 Scaffolding L.S. 7.8 2 15.60
2031 9999 Sundries L.S. 14.69 2 29.38
2040 TOTAL 5843.58 W
2041 Add 1 % Water charges on "W" 58.4358
2042 TOTAL 5902.02 X
2043 Add GST (multiplying factor 0.1405) on "X" 829.23
2044 TOTAL 6731.25 Y
2045 Add 15 % Contractor's profit and overheads on "Y" 1009.69
2046 Total 7740.94 Z
2047 Add Cess @ 1% on "Z" 77.41
2048 Cost of 15.71 metre 7818.35
2049 Cost of 1.00 metre 497.67
2050 Say 497.70

2051 12.27.2 Natural colour insulating board


2052 12.27.2.1 12 mm thick
2053 Details of cost for 10 holes of 0.5m dia each
2054 Details of cost for 15.71 metre
2055 MATERIAL
2056 0.5 metre dia. each = 10x22/7x0.5=15.71m
2057 Area = 10x(22/7)/4x0.5x0.5 = 1.96sqm. +
2058 Wastage @ 10% = 0.19 sqm.
2059 Total = 2.15 sqm.
2060 332 Natural colour insulating board:12 mm thick sqm 2.15 210 451.50
2061 9977 Carriage L.S. 3.38 2 6.76
2062 9999 Nails L.S. 5.33 2 10.66
2063 LABOUR
2064 14 Carpenter 1st class day 0.49 505.17 247.53
2065 17 Beldar day 0.39 350.00 136.50
2066 9999 Scaffolding L.S. 6.11 2 12.22
2067 9999 Sundries L.S. 6.11 2 12.22
2068 14 Carpenter 1st class day 2.5 505.17 1262.93
2069 17 Beldar day 2.5 350.00 875.00
2070 9999 Scaffolding L.S. 10.79 2 21.58
2071 TOTAL 3036.90 W
2072 Add 1 % Water charges on "W" 30.369
2073 TOTAL 3067.27 X
2074 Add GST (multiplying factor 0.1405) on "X" 430.95
2075 TOTAL 3498.22 Y
2076 Add 15 % Contractor's profit and overheads on "Y" 524.73
2077 Total 4022.95 Z
2078 Add Cess @ 1% on "Z" 40.23
2079 Cost of 15.71 metre 4063.18
2080 Cost of 1.00 metre 258.64
2081 Say 258.60
2082
2083
2092
2093
2094 12.27.3 White face insulating board: 12.27.3.1 12 mm thick
2095 Details of cost for 15.71 metre
2096 MATERIAL
2097 0.5 metre dia. each = 10x22/7x0.5=15.71m
2098 Area = 10x(22/7)/4x0.5x0.5 = 1.96sqm. +
2099 Wastage @ 10% = 0.19 sqm.
2100 Total = 2.15 sqm.
2101 328 White face insulating board:12 mm thick sqm 2.15 235 505.25
2102 9977 Carriage L.S. 3.38 2 6.76
2103 9999 Nails L.S. 5.33 2 10.66
2104 LABOUR
2105 14 Carpenter 1st class day 0.49 505.17 247.53
2106 17 Beldar day 0.39 350.00 136.50
2107 9999 Scaffolding L.S. 6.11 2 12.22
2108 9999 Sundries L.S. 6.11 2 12.22
2109 14 Carpenter 1st class day 2.5 505.17 1262.93
2110 17 Beldar day 2.5 350.00 875.00
2111 9999 Scaffolding L.S. 10.79 2 21.58
2112 TOTAL 3090.65 W
2113 Add 1 % Water charges on "W" 30.9065
2114 TOTAL 3121.56 X
2115 Add GST (multiplying factor 0.1405) on "X" 438.58
2116 TOTAL 3560.14 Y
2117 Add 15 % Contractor's profit and overheads on "Y" 534.02
2118 Total 4094.16 Z
2119 Add Cess @ 1% on "Z" 40.94
2120 Cost of 15.71 metre 4135.10
2121 Cost of 1.00 metre 263.21
2122 Say 263.20
2123
2124
2125 12.27.4 Flame retardant face insulating board:
2126 12.27.4.1 12 mm thick
2127 Details of cost for 15.71 metre
2128 MATERIAL
2129 0.5 metre dia. each = 10x22/7x0.5=15.71m
2130 Area = 10x(22/7)/4x0.5x0.5 = 1.96sqm. +
2131 Wastage @ 10% = 0.19 sqm.
2132 Total = 2.15 sqm.
2133 336 Flame retardent face insulating board: 12 mm sqm 2.15 320 688.00
2134 thick
2135 9977 Carriage L.S. 3.38 2 6.76
2144 9999 Nails L.S. 5.33 2 10.66
2145 LABOUR
2146 14 Carpenter 1st class day 0.49 505.17 247.53
2147 17 Beldar day 0.39 350.00 136.50
2148 9999 Scaffolding L.S. 6.11 2 12.22
2149 9999 Sundries L.S. 6.11 2 12.22
2150 14 Carpenter 1st class day 2.5 505.17 1262.93
2151 17 Beldar day 2.5 350.00 875.00
2152 9999 Scaffolding L.S. 10.79 2 21.58
2153 TOTAL 3273.40 W
2154 Add 1 % Water charges on "W" 32.734
2155 TOTAL 3306.13 X
2156 Add GST (multiplying factor 0.1405) on "X" 464.51
2157 TOTAL 3770.64 Y
2158 Add 15 % Contractor's profit and overheads on "Y" 565.60
2159 Total 4336.24 Z
2160 Add Cess @ 1% on "Z" 43.36
2161 Cost of 15.71 metre 4379.60
2162 Cost of 1.00 metre 278.78
2163 Say 278.80

2164 12.27.5 Standard quality hard board sheet:


2165 12.27.5.1 3 mm thick
2166 Details of cost for 15.71 metre
2167 MATERIAL
2168 0.5 metre dia. each = 10x22/7x0.5=15.71m
2169 Area = 10x(22/7)/4x0.5x0.5 = 1.96sqm. +
2170 Wastage @ 10% = 0.19 sqm.
2171 Total = 2.15 sqm.
2172 994 Standard quality hard board sheet 3 mm thick sqm 2.15 135 290.25
2173 9977 Carriage L.S. 2.73 2 5.46
2174 9999 Nails L.S. 5.33 2 10.66
2175 LABOUR
2176 14 Carpenter 1st class day 0.49 505.17 247.53
2177 17 Beldar day 0.39 350.00 136.50
2178 9999 Scaffolding L.S. 6.11 2 12.22
2179 9999 Sundries L.S. 6.11 2 12.22
2180 14 Carpenter 1st class day 2.5 505.17 1262.93
2181 17 Beldar day 2.5 350.00 875.00
2182 9999 Scaffolding L.S. 10.79 2 21.58
2183 TOTAL 2874.35 W
2184 Add 1 % Water charges on "W" 28.7435
2185 TOTAL 2903.09 X
2186 Add GST (multiplying factor 0.1405) on "X" 407.88
2187 TOTAL 3310.97 Y
2188 Add 15 % Contractor's profit and overheads on "Y" 496.65
2189 Total 3807.62 Z
2190 Add Cess @ 1% on "Z" 38.08
2191 Cost of 15.71 metre 3845.70
2192 Cost of 1.00 metre 244.79
2194 Say 244.80
2195
2196
2197
2198
2199
2200
2201
2202 12.27.5.2 4.5 mm thick
2203 Details of cost for 15.71 metre
2204 MATERIAL
2205 0.5 metre dia. each = 10x22/7x0.5=15.71m
2206 Area = 10x(22/7)/4x0.5x0.5 = 1.96sqm. +
2207 Wastage @ 10% = 0.19 sqm.
2208 Total = 2.15 sqm.
2209 996 Standard quality hard board sheet sqm 2.15 210 451.50
2210 4.5 mm thick
2211 9977 Carriage L.S. 2.86 2 5.72
2212 9999 Nails L.S. 5.33 2 10.66
2213 LABOUR
2214 14 Carpenter 1st class day 0.49 505.17 247.53
2215 17 Beldar day 0.39 350.00 136.50
2216 9999 Scaffolding L.S. 6.11 2 12.22
2217 9999 Sundries L.S. 6.11 2 12.22
2218 14 Carpenter 1st class day 2.5 505.17 1262.93
2219 17 Beldar day 2.5 350.00 875.00
2220 9999 Scaffolding L.S. 10.79 2 21.58
2221 TOTAL 3035.86 W
2222 Add 1 % Water charges on "W" 30.3586
2223 TOTAL 3066.22 X
2224 Add GST (multiplying factor 0.1405) on "X" 430.80
2225 TOTAL 3497.02 Y
2226 Add 15 % Contractor's profit and overheads on "Y" 524.55
2227 Total 4021.57 Z
2228 Add Cess @ 1% on "Z" 40.22
2229 Cost of 15.71 metre 4061.79
2230 Cost of 1.00 metre 258.55
2231 Say 258.60
2232
2233
2234
2235 12.28 Extra for providing and fixing ceiling to curved
2236 surfaces
Details in narrow
of cost widths
for 10 sqm.
2237 LABOUR
2245 14 Carpenter 1st class day 1 505.17 505.17
2246 15 Carpenter 2nd class day 1 403.67 403.67
2247 17 Beldar day 2 350.00 700.00
2248 TOTAL 1608.84 W
2249 Add 1 % Water charges on "W" 16.0884
2250 TOTAL 1624.93 X
2251 Add GST (multiplying factor 0.1405) on "X" 228.30
2252 TOTAL 1853.23 Y
2253 Add 15 % Contractor's profit and overheads on "Y" 277.98
2254 Total 2131.21 Z
2255 Add Cess @ 1% on "Z" 21.31
2256 Cost of 10.00 sqm. 2152.52
2257 Cost of 1.00 sqm. 215.25
2258 Say 215.30
2259
2260
2261 12.31 Providing 10 mm thick plaster of Paris (gypsum
2262 anhydrous)
12.31.1 Flatceiling up to a height of 5 m above floor level,
surfaces
2263 over first class kail wood strips 25x6 mm with 10 mm gap in
between and reinforced with rabbit wire mesh fixed to
2264 Details of cost for 4.00x2.5=10sqm.
2265 MATERIAL
2266 Wooden strips of 1st class kail wood
2267 72x40x0.25x0.06 = 43.20 cudm. + Add 10%
2268 wastage = 4.32 cudm. Total = 47.52
2269 1196 First class kail wood in planks 10 cudm 4.752 300 1425.60
2270 2204 Carriage of Timber cum 0.0475 121.29 5.76
2271 1219 Wire nails required for fixing the laths to frame kilogram 0.75 58 43.50
2272 work including breakage and wastage of nails
2273 Rabbit wire mesh required for reinforcement
2274 =2.5x4 = 10.00sqm.+ Add 2% wastage = 0.20
2275 sqm.
2276 Total = 10.2 sqm.
2277 1220 Wire mesh (rabbit) Plaster of paris - sqm 10.2 42 428.40
2278 2.5x4.0x10x1121/1000 = 112.10 kg.
2279 Add for plaster of paris joining into the side of
2280 the laths-
2281 2.5x4.0x4.0032x1121/1000 = 44.87 kg.
2282 Total = 156.97+
2283 Add 40% wastage = 62.79
2284 Total = 219.76 kg
2285 869 Plaster of Paris kilogram 219.76 5 1098.80
2286 2308 Carriage of Plaster of paris tonne 0.22 94.34 20.75
2287 9977 Carriage of wiremesh and nails etc. L.S. 2.73 2 5.46
2288 LABOUR
2289 14 Carpenter 1st class day 1.6 505.17 808.27
2298 17 Beldar day 1.6 350.00 560.00
2299 For doing plaster of paris over wooden strips
2300 22 Mason (for plaster of paris work) 1st class day 3.23 505.17 1631.70
2301 17 Beldar day 3.23 350.00 1130.50
2302 11 Bhisti day 0.54 350.00 189.00
2303 9999 Scaffolding L.S. 83.98 2 167.96
2304 9999 Sundries L.S. 53.82 2 107.64
2305 TOTAL 7623.34 W
2306 Add 1 % Water charges on "W" 76.2334
2307 TOTAL 7699.57 X
2308 Add GST (multiplying factor 0.1405) on "X" 1081.79
2309 TOTAL 8781.36 Y
2310 Add 15 % Contractor's profit and overheads on "Y" 1317.20
2311 Total 10098.56 Z
2312 Add Cess @ 1% on "Z" 100.99
2313 Cost of 10.00 sqm. 10199.55
2314 Cost of 1.00 sqm. 1019.96
2315 Say 1020.00
2316
2317
2318 12.31.2 Curved surfaces
2319 Details of cost for 4.00x2.5=10sqm.
2320 MATERIAL
2321 Wooden strips of 1st class kail wood
2322 72x40x0.25x0.06 = 43.20 cudm. + Add 10%
2323 wastage = 4.32 cudm. Total = 47.52 cudm
2324 1196 First class kail wood in planks 10 cudm 4.752 300 1425.60
2325 2204 Carriage of Timber cum 0.0475 121.29 5.76
2326 1219 Wire nails required for fixing the laths to frame kilogram 0.75 58 43.50
2327 work including breakage and wastage of nails
2328 Rabbit wire mesh required for reinforcement
2329 =2.5x4 = 10.00sqm.+ Add 2% wastage = 0.20
2330 sqm.
2331 Total = 10.2 sqm.
2332 1220 Wire mesh (rabbit) Plaster of paris - sqm 10.2 42 428.40
2333 2.5x4.0x10x1121/1000 = 112.10 kg.
2343 Add for plaster of paris joining into the side of
2344 the laths-
2345 2.5x4.0x4.0032x1121/1000 = 44.87 kg.
2346 Total = 156.97+
2347 Add 40% wastage = 62.79
2348 Total = 219.76 kg
2349 869 Plaster of Paris kilogram 219.76 5 1098.80
2350 2308 Carriage of Plaster of paris tonne 0.22 94.34 20.75
2351 9977 Carriage of wiremesh and nails etc. L.S. 2.73 2 5.46
2352 LABOUR
2353 14 Carpenter 1st class day 1.6 505.17 808.27
2354 17 Beldar day 1.6 350.00 560.00
2355 22 Mason (for plaster of paris work) 1st class day 3.23 505.17 1631.70
2356 17 Beldar day 3.23 350.00 1130.50
2357 11 Bhisti day 0.54 350.00 189.00
2358 9999 Scaffolding L.S. 83.98 2 167.96
2359 9999 Sundries L.S. 53.82 2 107.64
2360 14 Carpenter 1st class day 0.5 505.17 252.59
2361 22 Mason (for plaster of paris work) 1st class day 1 505.17 505.17
2362 17 Beldar day 1.5 350.00 525.00
2363 TOTAL 8906.10 W
2364 Add 1 % Water charges on "W" 89.061
2365 TOTAL 8995.16 X
2366 Add GST (multiplying factor 0.1405) on "X" 1263.82
2367 TOTAL 10258.98 Y
2368 Add 15 % Contractor's profit and overheads on "Y" 1538.85
2369 Total 11797.83 Z
2370 Add Cess @ 1% on "Z" 117.98
2371 Cost of 10.00 sqm. 11915.81
2372 Cost of 1.00 sqm. 1191.58
2373 Say 1191.60
2374
2375
2376
2377
2378 12.32 Extra for sunk or raised mouldings in the plaster
2379 of Paris (Gypsum
anhydrous) ceiling.
2380 Details of cost for 10 sqm.
2381 869 Plaster of Paris kilogram 109.88 5 549.40
2382 2308 Carriage of Plaster of paris tonne 0.11 94.34 10.38
2383 LABOUR
2384 22 Mason (for plaster of paris work) 1st class day 2 505.17 1010.34
2385 17 Beldar day 2 350.00 700.00
2386 11 Bhisti day 0.25 350.00 87.50
2395 9999 Scaffolding and Sundries L.S. 13.52 2 27.04
2396 TOTAL 2384.66 W
2397 Add 1 % Water charges on "W" 23.8466
2398 TOTAL 2408.51 X
2399 Add GST (multiplying factor 0.1405) on "X" 338.40
2400 TOTAL 2746.91 Y
2401 Add 15 % Contractor's profit and overheads on "Y" 412.04
2402 Total 3158.95 Z
2403 Add Cess @ 1% on "Z" 31.59
2404 Cost of 10.00 sqm. 3190.54
2405 Cost of 1.00 sqm. 319.05
2406 Say 319.10
2407
2408
2409
2410 12.33 Extra for providing plaster of Paris (Gypsum
2411 anhydrous) ceiling
metres height from above 5
floor level.
2412 Details of cost for 10sqm/metre height
2413 9999 Scaffolding L.S. 13.52 2 27.04
2414 LABOUR
2415 22 Mason (for plaster of paris work) 1st class day 1 505.17 505.17
2416 17 Beldar day 1 350.00 350.00
2417 11 Bhisti day 0.25 350.00 87.50
2418 TOTAL 969.71 W
2419 Add 1 % Water charges on "W" 9.6971
2420 TOTAL 979.41 X
2421 Add GST (multiplying factor 0.1405) on "X" 137.61
2422 TOTAL 1117.02 Y
2423 Add 15 % Contractor's profit and overheads on "Y" 167.55
2424 Total 1284.57 Z
2425 Add Cess @ 1% on "Z" 12.85
2426 Cost of 10.00 sqm. 1297.42
2427 Cost of 1.00 sqm. 129.74
2428 Say 129.70
2429
2430
2431
2432 12.34 Providing fixing thermal insulation of ceiling (under
2433 deck insulation)
wire mesh, for top with Resin
most Bonded
ceiling Fibre glass wool
of building.
2434 conforming to IS : 8183, density 24kg / m3, 50mm thick,
Details of cost for 10.00sqm.
wrapped in 200 G Virgin Polythene bags, fixed to ceiling with
2435
2436 Area for 10.00sqm. (Finished surface)
2437
2438 = 10.00sqm.+
2439
2440 Add 10% for overlappings & wastage = 1.00sqm.
2448 Total = 11.00sqm.
2449 7232 Resin Bonded Glass wool 24 kg/m³ 50 mm sqm 11 143 1573.00
2450 thick
2451 9999 Sundries including GI wire 20 SWG and Virgin L.S. 104 2 208.00
2452 polythene bags 200 gram
2453 9999 GI chiken mesh 12.5mm x 24 SWG L.S. 351 2 702.00
2454 LABOUR
2455 14 Carpenter 1st class day 1 505.17 505.17
2456 17 Beldar day 2 350.00 700.00
2457 TOTAL 3688.17 W
2458 Add 1 % Water charges on "W" 36.8817
2459 TOTAL 3725.05 X
2460 Add GST (multiplying factor 0.1405) on "X" 523.37
2461 TOTAL 4248.42 Y
2462 Add 15 % Contractor's profit and overheads on "Y" 637.26
2463 Total 4885.68 Z
2464 Add Cess @ 1% on "Z" 48.86
2465 Cost of 10.00 sqm. 4934.54
2466 Cost of 1.00 sqm. 493.45
2467 Say 493.50
2468
2469
2470 12.35 Providing and fixing thermal insulation with Resin
2471 Bonded
Details Fibre
of cost forglass wool conforming to IS: 8183. Density 16
10.00sqm.
2472 kg/m³, 50 mm thick, wrapped in 200G Virgin Polythene bags
Area for 10.00sqm. (Finished surface)
placed over existing false ceiling and held in position by
2473 = 10.00sqm.+
2474 Add 10% for overlappings & wastage =
2475 1.00sqm.
2476 Total = 11.00sqm.
2477 7231 Resin Bonded Glass wool 16 kg/m³ 50 mm sqm 11 100 1100.00
2478 thick
2479 9999 Sundries including GI wire 20 SWG and L.S. 52 2 104.00
2480 Virgin polythene bags 200 gram
2481 LABOUR
2482 14 Carpenter 1st class Day 0.5 505.17 252.59
2483 17 Beldar Day 0.5 350.00 175.00
2484 TOTAL 1631.59 W
2485 Add 1 % Water charges on "W" 16.3159
2486 TOTAL 1647.91 X
2487 Add GST (multiplying factor 0.1405) on "X" 231.53
2488 TOTAL 1879.44 Y
2489 Add 15 % Contractor's profit and overheads on "Y" 281.92
2490 Total 2161.36 Z
2491 Add Cess @ 1% on "Z" 21.61
2492 Cost of 10.00 sqm. 2182.97
2493 Cost of 1.00 sqm. 218.3
2494 Say 218.30
2502
2503
2504
2505
2506 12.36 Thermal Insulation of roofing with Expanded
2507 polystyrene
12.36.1 With fixed
Typewith
N -suitable
Normal adhesive to the false ceiling
50 mm thick
2508 as per the directions of
Details of cost for 10.00sqm.
the Engineer-in-charge:
2509 Cost of materials :
2510 Expanded Polystyrens 1x10=10.00sqm. + Add
2511 wastage 10% = 1.00sqm.
2512 Total = 11.00sqm.
2513 7090 Expanded polystyrene type N- Normal sqm 11 125 1375.00
2514 314 Bitumen hot sealing compound : grade A kilogram 0.25 28 7.00
2515 9999 Sundries L.S. 13 2 26.00
2516 LABOUR
2517 14 Carpenter 1st class day 0.5 505.17 252.59
2518 17 Beldar day 0.5 350.00 175.00
2519 TOTAL 1835.59 W
2520 Add 1 % Water charges on "W" 18.3559
2521 TOTAL 1853.95 X
2522 Add GST (multiplying factor 0.1405) on "X" 260.48
2523 TOTAL 2114.43 Y
2524 Add 15 % Contractor's profit and overheads on "Y" 317.16
2525 Total 2431.59 Z
2526 Add Cess @ 1% on "Z" 24.32
2527 Cost of 10.00 sqm. 2455.91
2528 Cost of 1.00 sqm. 245.59
2529 Say 245.60
2530
2531
2532 12.36.2 With Type SE - Self Extinguishing type 50 mm thick
2533 Details of cost for 10.00sqm.
2534 Cost of materials :
2535 Expanded Polystyrens 1x10=10.00sqm. + Add
2536 wastage 10% = 1.00sqm.
2537 Total = 11.00sqm.
2538 7091 Expanded polystyrene type - SE sqm 11 150 1650.00
2539 314 Bitumen hot sealing compound : grade A kilogram 0.25 28 7.00
2540 9999 Sundries L.S. 13 2 26.00
2541 LABOUR
2542 14 Carpenter 1st class day 0.5 505.17 252.59
2551 17 Beldar day 0.5 350.00 175.00
2552 TOTAL 2110.59 W
2553 Add 1 % Water charges on "W" 21.1059
2554 TOTAL 2131.70 X
2555 Add GST (multiplying factor 0.1405) on "X" 299.50
2556 TOTAL 2431.20 Y
2557 Add 15 % Contractor's profit and overheads on "Y" 364.68
2558 Total 2795.88 Z
2559 Add Cess @ 1% on "Z" 27.96
2560 Cost of 10.00 sqm. 2823.84
2561 Cost of 1.00 sqm. 282.38
2562 Say 282.40
2563
2564
2565
2566 12.37 Providing and fixing 100 mm diameter and 60 cm
2567 long rain Stone
12.37.1 water ware
spoutspout
in cement mortar 1:4 (1 cement : 4 fine
2568 sand).
Details of cost for 10 stone ware spout of
2569 60cm long
2570 MATERIAL
2571 3004 Stone ware spouts 100 mm dia 60 cm long each 10 40 400.00
2572 9977 CARRIAGE L.S. 13.52 2 27.04
2573 9999 Mortar L.S. 13.52 2 27.04
2574 Labour for fixing and placing in position
2575 24 Mason (brick layer) 2nd class day 0.4 403.67 161.47
2576 17 Beldar day 0.4 350.00 140.00
2577 9999 Sundries L.S. 5.33 2 10.66
2578 TOTAL 766.21 W
2579 Add 1 % Water charges on "W" 7.6621
2580 TOTAL 773.87 X
2581 Add GST (multiplying factor 0.1405) on "X" 108.73
2582 TOTAL 882.60 Y
2583 Add 15 % Contractor's profit and overheads on "Y" 132.39
2584 Total 1014.99 Z
2585 Add Cess @ 1% on "Z" 10.15
2586 Cost of 10.00 sqm. 1025.14
2587 Cost of 1.00 sqm. 102.51
2588 Say 102.50
2589
2590
2591
2592 12.38 Providing and fixing M.S. holder bat clamps of
2600 approved design
12.38.1 100 mm to C.I. or S.C.I. rain water pipes embedded
diameter
in and including cement concrete blocks 10x10x10 cm of
1:2:4 mix (1 cement : 2 coarse sand : 4 graded stone
2601
2602 Details of cost of 5 nos.
2603 MATERIAL
2604 1331 M.S.Holder bat clamp of approved design for each 5 30 150.00
2605 100 mm S.C.I. pipe
2606 C.C. block 5x0.1x0.1x0.1 = 0.005 cum
2607 9977 Carriage of bat clamps L.S. 2.47 2 4.94
2608 9999 Sundries L.S. 7.15 2 14.30
2609 LABOUR
2610 19 Fitter (grade 1) day 0.125 505.17 63.15
2611 24 Mason (brick layer) 2nd class day 0.75 403.67 302.75
2612 17 Beldar day 0.5 350.00 175.00
2613 295 Stone Aggregate (Single size) : 20 mm cum 0.0033 800 2.64
2614 nominal size
2615 297 Stone Aggregate (Single size) : 10 mm cum 0.0011 810 0.89
2616 nominal size
2617 2202 Carriage of Stone aggregate below 40 mm cum 0.0044 106.13 0.47
2618 nominal size
2619 982 Coarse sand cum 0.0022 800 1.76
2620 2203 Carriage of Coarse sand cum 0.0022 106.13 0.23
2621 367 Portland Cement (OPC-43 grade) tonne 0.0016 4375 7.00
2622 2209 Carriage of Cement tonne 0.0016 94.34 0.15
2623 17 Beldar day 0.0045 350.00 1.58
2624 18 Coolie day 0.0032 350.00 1.12
2625 11 Bhisti day 0.0014 350.00 0.49
2626 23 Mason (brick layer) 1st class day 0.0003 505.17 0.15
2627 24 Removing white or colour wash by scrapping day 0.0003 403.67 0.12
2628 and sand papering and preparing the
2629 surface smooth including necessary repairs
2630 to scratches etc. complete
2631 28 Mate day 0.0002 350.00 0.07
2632 9999 Hire charges of machine etc. L.S. 0.26 2 0.52
2633 9999 Sundries L.S. 0.13 2 0.26
2634 9999 Sundries L.S. 0.13 2 0.26
2635 TOTAL 727.85 W
2636 Add 1 % Water charges on "W" 7.2785
2637 TOTAL 735.13 X
2638 Add GST (multiplying factor 0.1405) on "X" 103.29
2639 TOTAL 838.42 Y
2640 Add 15 % Contractor's profit and overheads on "Y" 125.76
2641 Total 964.18 Z
2642 Add Cess @ 1% on "Z" 9.64
2643 Cost of 5.00 bat clamps 973.82
2644 Cost of 1.00 bat clamp 194.76
2645 Say 194.80
2646
2655
2656
2657 12.38.2 150 mm diameter
2658 Details of cost of 5 nos.
2659 MATERIAL
2660 886 Standard holdar bat clamps for sand cast iron each 5 45 225.00
2661 or cast iron pipes 150 mm dia C.C. block
2662 5x0.1x0.1x0.1 = 0.005 cum
2663 9977 Carriage of bat clamps L.S. 2.47 2 4.94
2664 9999 Sundries L.S. 7.15 2 14.30
2665 LABOUR
2666 19 Fitter (grade 1) day 0.125 505.17 63.15
2667 24 Mason (brick layer) 2nd class day 0.75 403.67 302.75
2668 17 Beldar day 0.5 350.00 175.00
2669 295 Stone Aggregate (Single size) : 20 mm cum 0.0033 800 2.64
2670 nominal size
2671 297 Stone Aggregate (Single size) : 10 mm cum 0.0011 810 0.89
2672 nominal size
2673 2202 Carriage of Stone aggregate below 40 mm cum 0.0044 106.13 0.47
2674 nominal size
2675 982 Coarse sand cum 0.0022 800 1.76
2676 2203 Carriage of Coarse sand cum 0.0022 106.13 0.23
2677 367 Portland Cement (OPC-43 grade) tonne 0.0016 4375 7.00
2678 2209 Carriage of Cement tonne 0.0016 94.34 0.15
2679 17 Beldar day 0.0045 350.00 1.58
2680 18 Coolie day 0.0032 350.00 1.12
2681 11 Bhisti day 0.0014 350.00 0.49
2682 23 Mason (brick layer) 1st class day 0.0003 505.17 0.15
2683 24 Mason (brick layer) 2nd class day 0.0003 403.67 0.12
2684 28 Mate day 0.0002 350.00 0.07
2685 9999 Hire charges of machine etc. L.S. 0.26 2 0.52
2686 9999 Sundries L.S. 0.13 2 0.26
2687 9999 Sundries L.S. 0.13 2 0.26
2688 TOTAL 802.85 W
2689 Add 1 % Water charges on "W" 8.0285
2690 TOTAL 810.88 X
2691 Add GST (multiplying factor 0.1405) on "X" 113.93
2692 TOTAL 924.81 Y
2693 Add 15 % Contractor's profit and overheads on "Y" 138.72
2694 Total 1063.53 Z
2695 Add Cess @ 1% on "Z" 10.64
2696 Cost of 5.00 bat clamps 1074.17
2697 Cost of 1.00 bat clamp 214.83
2698 Say 214.80
2699
2706
2707
2708
2709
2710 12.39 Providing lead caulked joints to sand cast iron rain
water pipes and fittings:
2711 12.39.1 100 mm dia Pipe
2712 Details of cost for one joint.
2713 MATERIAL
2714 865 Pig lead kilogram 0.98 130 127.40
2715 1001 Spun yarn kilogram 0.11 50 5.50
2716 9999 Kerosene oil fuel and sundries L.S. 13.52 2 27.04
2717 9977 Carriage of materials L.S. 1.43 2 2.86
2718 LABOUR
2719 19 Fitter (grade 1) day 0.06 505.17 30.31
2720 20 Assistant Fitter or 2nd class Fitter day 0.06 403.67 24.22
2721 17 Beldar day 0.12 350.00 42.00
2722 TOTAL 259.33 W
2723 Add 1 % Water charges on "W" 2.5933
2724 TOTAL 261.92 X
2725 Add GST (multiplying factor 0.1405) on "X" 36.80
2726 TOTAL 298.72 Y
2727 Add 15 % Contractor's profit and overheads on "Y" 44.81
2728 Total 343.53 Z
2729 Add Cess @ 1% on "Z" 3.44
2730 Cost of 1.00 joint 346.97
2731 Say 346.97
2732 347.00
2733
2734 12.39.2 150 mm dia Pipe
2735 Details of cost for one joint.
2736 MATERIAL
2737 865 Pig lead kilogram 1.48 130 192.40
2738 1001 Spun yarn kilogram 0.17 50 8.50
2739 9999 Kerosene oil fuel and sundries L.S. 13.52 2 27.04
2740 9977 Carriage of materials L.S. 2.73 2 5.46
2741 LABOUR
2742 19 Fitter (grade 1) day 0.08 505.17 40.41
2743 20 Assistant Fitter or 2nd class Fitter day 0.08 403.67 32.29
2744 17 Beldar day 0.15 350.00 52.50
2745 TOTAL 358.60 W
2746 Add 1 % Water charges on "W" 3.586
2747 TOTAL 362.19 X
2748 Add GST (multiplying factor 0.1405) on "X" 50.89
2749 TOTAL 413.08 Y
2750 Add 15 % Contractor's profit and overheads on "Y" 61.96
2751 Total 475.04 Z
2753 Add Cess @ 1% on "Z" 4.75
2754 Cost of 1.00 joint 479.79
2755 Say 479.79
2756 479.80

2762
2763
2764 12.40 Providing, fixing and embedding sand cast iron
2765 accessories
12.40.1 Sandfor castrain water
iron plainpipes in :the
shoes masonry
12.40.1.1 150surrounded
mm
2766 with 12
diameter mm thick cement
Details of cost for one shoe
mortar of the same mix, as that of
masonry (lead caulking will be paid for separately):
2767 966 Sand Cast iron plain shoe 150 mm dia each 1 285 285.00
2768 9988 Carriage, fixing and mortar L.S. 17.55 2 35.10
2769 TOTAL 320.10 W
2770 Add 1 % Water charges on "W" 3.201
2771 TOTAL 323.30 X
2772 Add GST (multiplying factor 0.1405) on "X" 45.42
2773 TOTAL 368.72 Y
2774 Add 15 % Contractor's profit and overheads on "Y" 55.31
2775 Total 424.03 Z
2776 Add Cess @ 1% on "Z" 4.24
2777 Cost of 1.00 joint 428.27
2778 Say 428.27
2779 428.30
2780
2781
2782 12.41 Providing and fixing on wall face unplasticised Rigid
2783 PVC rain water pipes conforming to IS : 13592 Type A,
pipes.
2784 including jointing with seal ring conforming to IS : 5382,
12.41.1
leaving 1075mm
mmgap
diameter
for thermal expansion, (i) Single socketed
2785
2786 Details of cost for 6.00 metres
2787
2788 7188 U-PVC pipes (working pressure 4 kg / sqcm.) metre 6 220 1320.00
2789 Single socketed pipe 75 mm dia.
2790 7190 U-PVC pipes (working pressure 4 kg / sqcm.) each 1 15 15.00
2791 Rubber (Seal) Ring 75 mm dia.
2792 9977 Carriage of materials L.S. 13.52 2 27.04
2793 9999 Adhesive, and sundries etc. L.S. 6.76 2 13.52
2794 LABOUR
2803 19 Fitter (grade 1) day 0.19 505.17 95.98
2804 17 Beldar day 0.37 350.00 129.50
2805 10 Bandhani day 0.08 350.00 28.00
2806 9999 Scaffolding etc. L.S. 18.59 2 37.18
2807 TOTAL 1666.22 W
2808 Add 1 % Water charges on "W" 16.6622
2809 TOTAL 1682.88 X
2810 Add GST (multiplying factor 0.1405) on "X" 236.44
2811 TOTAL 1919.32 Y
2812 Add 15 % Contractor's profit and overheads on "Y" 287.90
2813 Total 2207.22 Z
2814 Add Cess @ 1% on "Z" 22.07
2815 Cost of 6.00 metre 2229.29
2816 Cost of 1.00 metre 371.55
2817 Say 371.60
2818
2819
2820 12.41.2 110 mm diameter
2821 Details of cost for 6.00 metres
2822 7189 U-PVC pipes (working pressure 4 kg / sqcm) metre 6 250 1500.00
2823 Single socketed pipe 110 mm dia.
2824 7191 U-PVC pipes (working pressure 4 kg / sqcm.) each 1 20 20.00
2825 Rubber (Seal) Ring 110 mm dia.
2826 9977 Carriage of materials L.S. 17.55 2 35.10
2827 9999 Adhesive, and sundries etc. L.S. 8.06 2 16.12
2828 LABOUR
2829 19 Fitter (grade 1) day 0.23 505.17 116.19
2830 17 Beldar day 0.45 350.00 157.50
2831 10 Bandhani day 0.11 350.00 38.50
2832 9999 Scaffolding etc. L.S. 18.59 2 37.18
2833 TOTAL 1920.59 W
2834 Add 1 % Water charges on "W" 19.2059
2835 TOTAL 1939.80 X
2836 Add GST (multiplying factor 0.1405) on "X" 272.54
2837 TOTAL 2212.34 Y
2838 Add 15 % Contractor's profit and overheads on "Y" 331.85
2839 Total 2544.19 Z
2840 Add Cess @ 1% on "Z" 25.44
2841 Cost of 6.00 metre 2569.63
2842 Cost of 1.00 metre 428.27
2843 Say 428.30
2844
2845
2852
2853
2854 12.42 Providing and fixing on wall face unplasticised - PVC
2855 moulded
10 mm gap fittings/ accessories
for thermal for unplasticised
expansion. Rigid PVC
12.42.1 Coupler
2856 rain water pipes conforming to IS : 13592 Type A, including
jointing with seal ring conforming to IS : 5382, leaving
2857 12.42.1.1 75 mm
2858
2859 Details of cost for 1 coupler
2860 7192 UPVC coupler for UPVC drainage pipes 75 each 1 18 18.00
2861 mm
2862 7190 U-PVC pipes (working pressure 4 kg / sqcm.) each 2 15 30.00
2863 Rubber (Seal) Ring 75 mm dia.
2864 9999 Adhesive, and sundries etc. L.S. 2.73 2 5.46
2865 LABOUR
2866 9988 Carriage and fixing charges L.S. 9.36 2 18.72
2867 TOTAL 72.18 W
2868 Add 1 % Water charges on "W" 0.7218
2869 TOTAL 72.90 X
2870 Add GST (multiplying factor 0.1405) on "X" 10.24
2871 TOTAL 83.14 Y
2872 Add 15 % Contractor's profit and overheads on "Y" 12.47
2873 Total 95.61 Z
2874 Add Cess @ 1% on "Z" 0.96
2875 Cost of 1 coupler 96.57
2876 Say 96.57
2877 96.60
2878
2879 12.42.1.2 110 mm
2880 Details of cost for 1 coupler
2881 7193 UPVC coupler for UPVC drainage pipes 110 each 1 150 150.00
2882 mm
2883 7191 U-PVC pipes (working pressure 4 kg / sqcm) each 2 20 40.00
2884 Rubber (Seal) Ring 110 mm dia.
2885 9999 Adhesive, and sundries etc. L.S. 2.73 2 5.46
2886 LABOUR
2887 9988 Carriage and fixing charges L.S. 10.79 2 21.58
2888 TOTAL 217.04 W
2889 Add 1 % Water charges on "W" 2.1704
2890 TOTAL 219.21 X
2891 Add GST (multiplying factor 0.1405) on "X" 30.80
2892 TOTAL 250.01 Y
2893 Add 15 % Contractor's profit and overheads on "Y" 37.50
2894 Total 287.51 Z
2895 Add Cess @ 1% on "Z" 2.88
2896 Cost of 1 coupler 290.39
2897 Say 290.39
2898 290.40
2906
2907
2908 12.42.2 Single pushfit Coupler
2909 12.42.2.1 75 mm
2910 Details of cost for 1 coupler
2911 7194 UPVC pushfit coupler (single) 75 mm thick each 1 110 110.00
2912 7190 U-PVC pipes (working pressure 4 kg / sqcm.) each 2 15 30.00
2913 Rubber (Seal) Ring 75 mm dia.
2914 9999 Adhesive, and sundries etc. L.S. 2.73 2 5.46
2915 9988 Carriage and fixing charges L.S. 9.36 2 18.72
2916 TOTAL 164.18 W
2917 Add 1 % Water charges on "W" 1.6418
2918 TOTAL 165.82 X
2919 Add GST (multiplying factor 0.1405) on "X" 23.30
2920 TOTAL 189.12 Y
2921 Add 15 % Contractor's profit and overheads on "Y" 28.37
2922 Total 217.49 Z
2923 Add Cess @ 1% on "Z" 2.17
2924 Cost of 1 coupler 219.66
2925 Say 219.66
219.70

2926 12.42.2.2 110 mm


2927 Details of cost for 1 coupler
2928 7195 UPVC pushfit coupler (single) 110 mm thick each 1 150 150.00
2929 7191 U-PVC pipes (working pressure 4 kg / sq.cm) each 2 20 40.00
2930 Rubber (Seal) Ring 110 mm dia.
2931 9999 Adhesive, and sundries etc. L.S. 2.73 2 5.46
2932 9988 Carriage and fixing charges L.S. 10.79 2 21.58
2933 TOTAL 217.04 W
2934 Add 1 % Water charges on "W" 2.1704
2935 TOTAL 219.21 X
2936 Add GST (multiplying factor 0.1405) on "X" 30.80
2937 TOTAL 250.01 Y
2938 Add 15 % Contractor's profit and overheads on "Y" 37.50
2939 Total 287.51 Z
2940 Add Cess @ 1% on "Z" 2.88
2941 Cost of 1 coupler 290.39
2942 Say 290.39
2943 290.40
2944
2952
2953 12.42.3 Single tee with door
2954 12.42.3.1 75x75x75 mm
2955 Details of cost for 1 tee
2956 MATERIAL
2957 7198 UPVC single equal Tee (with door) 75x75x75 each 1 120 120.00
2958 mm
2959 7190 U-PVC pipes (working pressure 4 kg / sqcm) each 3 15 45.00
2960 Rubber (Seal) Ring 75 mm dia.
2961 9988 Adhesive, Carriage of material rubber washer L.S. 10.76 2 21.52
2962 etc. including fixing charges
2963 TOTAL 186.52 W
2964 Add 1 % Water charges on "W" 1.8652
2965 TOTAL 188.39 X
2966 Add GST (multiplying factor 0.1405) on "X" 26.47
2967 TOTAL 214.86 Y
2968 Add 15 % Contractor's profit and overheads on "Y" 32.23
2969 Total 247.09 Z
2970 Add Cess @ 1% on "Z" 2.47
2971 Cost of 1 tee 249.56
2972 Say 249.56
249.60

2973 12.42.3.2 110x110x110 mm


2974 Details of cost for 1 tee
2975 MATERIAL
2976 7199 UPVC single equal Tee (with door) each 1 150 150.00
2977 110x110x110 mm
2978 7191 U-PVC pipes (working pressure 4 kg / sqcm) each 3 20 60.00
2979 Rubber (Seal) Ring 110 mm dia.
2980 9988 Adhesive, Carriage of material rubber washer L.S. 13.47 2 26.94
2981 etc. including fixing charges
2982 TOTAL 236.94 W
2983 Add 1 % Water charges on "W" 2.3694
2984 TOTAL 239.31 X
2985 Add GST (multiplying factor 0.1405) on "X" 33.62
2986 TOTAL 272.93 Y
2987 Add 15 % Contractor's profit and overheads on "Y" 40.94
2988 Total 313.87 Z
2989 Add Cess @ 1% on "Z" 3.14
2990 Cost of 1 tee 317.01
2991 Say 317.01
2992 317.00
2993
3000 12.42.4 Single tee without door
3001 12.42.4.1 75x75x75 mm
3003 Details of cost for 1 tee
3004 MATERIAL
3005 7196 UPVC single equal Tee (with door) 75x75x75 each 1 150 150.00
3006 mm
3007 7190 U-PVC pipes (working pressure 4 kg / sqcm) each 3 15 45.00
3008 Rubber (Seal) Ring 75 mm dia.
3009 9988 Adhesive, Carriage of material rubber washer L.S. 10.76 2 21.52
3010 etc. including fixing charges
3011 TOTAL 216.52 W
3012 Add 1 % Water charges on "W" 2.1652
3013 TOTAL 218.69 X
3014 Add GST (multiplying factor 0.1405) on "X" 30.73
3015 TOTAL 249.42 Y
3016 Add 15 % Contractor's profit and overheads on "Y" 37.41
3017 Total 286.83 Z
3018 Add Cess @ 1% on "Z" 2.87
3019 Cost of 1 tee 289.70
3020 Say 289.7
289.70

3021 12.42.4.2 110x110x110 mm


3022 Details of cost for 1 tee
3023 MATERIAL
3024 7197 UPVC single equal Tee (with door) each 1 150 150.00
3025 110x110x110 mm
3026 7191 U-PVC pipes (working pressure 4 kg / sqcm) each 3 20 60.00
3027 Rubber (Seal) Ring 110 mm dia.
3028 9988 Adhesive, Carriage of material rubber washer L.S. 13.47 2 26.94
3029 etc. including fixing charges
3030 TOTAL 236.94 W
3031 Add 1 % Water charges on "W" 2.3694
3032 TOTAL 239.31 X
3033 Add GST (multiplying factor 0.1405) on "X" 33.62
3034 TOTAL 272.93 Y
3035 Add 15 % Contractor's profit and overheads on "Y" 40.94
3036 Total 313.87 Z
3037 Add Cess @ 1% on "Z" 3.14
3038 Cost of 1 tee 317.01
3039 Say 317.01
317.00

3040 12.42.5 Bend 87.5°


3041 12.42.5.1 75 mm bend
3042 Details of cost for 1 bend
3043 7208 UPVC bend 87.5° 75 mm bend each 1 150 150.00
3053 7190 U-PVC pipes (working pressure 4 kg / sqcm) each 1 15 15.00
3054 Rubber (Seal) Ring 75 mm dia.
3055 9999 Adhesive, and sundries etc. L.S. 2.73 2 5.46
3056 9988 Carriage and fixing charges L.S. 9.36 2 18.72
3057 TOTAL 189.18 W
3058 Add 1 % Water charges on "W" 1.8918
3059 TOTAL 191.07 X
3060 Add GST (multiplying factor 0.1405) on "X" 26.85
3061 TOTAL 217.92 Y
3062 Add 15 % Contractor's profit and overheads on "Y" 32.69
3063 Total 250.61 Z
3064 Add Cess @ 1% on "Z" 2.51
3065 Cost of 1 bend 253.12
3066 Say 253.12
253.10

3067 12.42.5.2 110 mm bend


3068 Details of cost for 1 bend
3069 7209 UPVC bend 87.5° 110 mm bend each 1 180 180.00
3070 7191 U-PVC pipes (working pressure 4 kg / sqcm) each 1 20 20.00
3071 Rubber (Seal) Ring 110 mm dia.
3072 9999 Adhesive, and sundries etc. L.S. 2.73 2 5.46
3073 9988 Carriage and fixing charges L.S. 10.79 2 21.58
3074 TOTAL 227.04 W
3075 Add 1 % Water charges on "W" 2.2704
3076 TOTAL 229.31 X
3077 Add GST (multiplying factor 0.1405) on "X" 32.22
3078 TOTAL 261.53 Y
3079 Add 15 % Contractor's profit and overheads on "Y" 39.23
3080 Total 300.76 Z
3081 Add Cess @ 1% on "Z" 3.01
3082 Cost of 1 bend 303.77
3083 Say 303.77
303.80

3084 12.42.6 Shoe (Plain)


3085 12.42.6.1 75 mm Shoe
3086 Details of cost for 1 shoe
3087 7212 UPVC plain shoe 75 mm bend each 1 150 150.00
3088 7190 U-PVC pipes (working pressure 4 kg / sqcm) each 1 15 15.00
3089 Rubber (Seal) Ring 75 mm dia.
3098 9999 Adhesive, and sundries etc. L.S. 2.73 2 5.46
3099 9988 Carriage and fixing charges L.S. 9.36 2 18.72
3100 TOTAL 189.18 W
3101 Add 1 % Water charges on "W" 1.8918
3102 TOTAL 191.07 X
3103 Add GST (multiplying factor 0.1405) on "X" 26.85
3104 TOTAL 217.92 Y
3105 Add 15 % Contractor's profit and overheads on "Y" 32.69
3106 Total 250.61 Z
3107 Add Cess @ 1% on "Z" 2.51
3108 Cost of 1 shoe 253.12
3109 Say 253.12
253.10

3110 12.42.6.2 110 mm Shoe


3111 Details of cost for 1 shoe
3112 7213 UPVC plain shoe 110 mm bend each 1 180 180.00
3113 7191 U-PVC pipes (working pressure 4 kg / sqcm) each 1 20 20.00
3114 Rubber (Seal) Ring 110 mm dia.
3115 9999 Adhesive, and sundries etc. L.S. 2.73 2 5.46
3116 9988 Carriage and fixing charges L.S. 10.79 2 21.58
3117 TOTAL 227.04 W
3118 Add 1 % Water charges on "W" 2.2704
3119 TOTAL 229.31 X
3120 Add GST (multiplying factor 0.1405) on "X" 32.22
3121 TOTAL 261.53 Y
3122 Add 15 % Contractor's profit and overheads on "Y" 39.23
3123 Total 300.76 Z
3124 Add Cess @ 1% on "Z" 3.01
3125 Cost of 1 shoe 303.77
3126 Say 303.77
3127 303.80
3128
3129
3130
3131 12.43 Providing and fixing unplasticised -PVC pipe clips of
3132 approved
12.43.1 75 design
mm to unplasticised PVC rain water pipes by
3133 means of 50x50x50 mm hard wood plugs, screwed with M.S.
Details of cost for 5 nos.
screws of required length, including cutting brick work and
3134 MATERIAL
3135
3136 7214 UPVC pipe clip 75 mm bend each 5 30 150.00
3145 9977 Carriage of U-PVC pipe clips L.S. 2.47 2 4.94
3146 870 Plug each 10 10 100.00
3147 LABOUR
3148 19 Fitter (grade 1) day 0.125 505.17 63.15
3149 24 Mason (brick layer) 2nd class day 0.75 403.67 302.75
3150 17 Beldar day 0.5 350.00 175.00
3151 9999 Sundries L.S. 7.15 2 14.30
3152 9999 Sundries L.S. 0.91 2 1.82
3153 9999 Sundries cement mortar 1:4 (1Cement : 4 L.S. 3.9 2 7.80
3154 Coarse sand)
3155 TOTAL 819.76 W
3156 Add 1 % Water charges on "W" 8.1976
3157 TOTAL 827.96 X
3158 Add GST (multiplying factor 0.1405) on "X" 116.33
3159 TOTAL 944.29 Y
3160 Add 15 % Contractor's profit and overheads on "Y" 141.64
3161 Total 1085.93 Z
3162 Add Cess @ 1% on "Z" 10.86
3163 Cost of 5 Nos. 1096.79
3164 Cost of 1 No. 219.36
3165 Say 219.40
3166
3167
3168 12.43.2 110 mm
3169 Details of cost for 5 nos.
3170 MATERIAL
3171 7215 UPVC pipe clip 110 mm bend each 5 40 200.00
3172 9977 Carriage of U-PVC pipe clips L.S. 2.47 2 4.94
3173 870 Plug each 10 10 100.00
3174 LABOUR
3175 19 Fitter (grade 1) day 0.125 505.17 63.15
3176 24 Mason (brick layer) 2nd class day 0.75 403.67 302.75
3177 17 Beldar day 0.5 350.00 175.00
3178 9999 Sundries L.S. 7.15 2 14.30
3179 9999 Sundries L.S. 0.91 2 1.82
3180 9999 Sundries cement mortar 1:4 (1Cement : 4 Coar L.S. 3.9 2 7.80
3181 TOTAL 869.76 W
3182 Add 1 % Water charges on "W" 8.6976
3183 TOTAL 878.46 X
3184 Add GST (multiplying factor 0.1405) on "X" 123.42
3185 TOTAL 1001.88 Y
3186 Add 15 % Contractor's profit and overheads on "Y" 150.28
3187 Total 1152.16 Z
3188 Add Cess @ 1% on "Z" 11.52
3189 Cost of 5 Nos. 1163.68
3190 Cost of 1 No. 116.37
3191 Say 116.40
3199
3200
3201
3202
3203 12.44 Providing and fixing to the inlet mouth of rain water
3204 pipe cast ironand
cm diameter grating 15 not less than 440 grams.
weighing
3205 Details of cost for 1 grating
3206 MATERIAL
3207 7187 C.I. grating 150 mm dia. (Weighing not less each 1 27 27.00
3208 than 440 gm)
3209 9977 Carriage of material and fixing charges L.S. 4.16 2 8.32
3210 TOTAL 35.32 W
3211 Add 1 % Water charges on "W" 0.3532
3212 TOTAL 35.67 X
3213 Add GST (multiplying factor 0.1405) on "X" 5.01
3214 TOTAL 40.68 Y
3215 Add 15 % Contractor's profit and overheads on "Y" 6.10
3216 Total 46.78 Z
3217 Add Cess @ 1% on "Z" 0.47
3218 Cost of each grating 47.25
3219 Say 47.25
47.30

3220
3221 12.45 Providing and fixing false ceiling at all height
3236 including
of size 3.5providing
x 25 mm atand
230fixing of frame
mm c/c, work jointing
including made ofand
special
3237 sections,
finishing power pressed
to a flush finish from M.S.
of tapered sheets
and and
square galvanized
edges of the
12.45.1
with zinc 12.5 mmof
coating thick
120tapered
gms/sqm edge gypsum
(both plain board
side inclusive) as per
3238 board with recommended
conforming to IS: 2095- (Part jointing compound , jointing
tapes , finishing with jointing compound in 3 layers covering
3239 I) : 2011 (Board with BIS Certification marks)
3240
3241 Details of cost for 10.8x9.6m = 103.68sqm.
3242
3243 MATERIAL
3244 Gypsum board 12.5mm thick = 103.68 sqm.+
3245 Add wastage @ 5% = 5.18sqm.
3246 Total = 108.86 sqm.
3247 7009 12.5 mm thick tapered edge gypsum plain sqm 108.86 155 16873.30
3248 borad
3249 7010 Galvanised Steel ceiling section (size metre 238.14 46 10954.44
3250 80x26x0.50mm)
3251 7011 Galvanised Steel perimetre Channel (Size metre 41.84 22 920.48
3252 20x27x30x0.50mm)
3253 7012 Galvanised Steel intermediate Channel metre 90.72 38 3447.36
3254 (Size 15x45x15x0.90mm)
3255 Strap hanger
3256 7013 Galvanised Steel angle hanger metre 10.8 12 129.60
3257 (Celling angle) (Size 25x10x0.50mm)
3258 7014 Galvanised Steel connecting clips each 189 4 756.00
3259 (2.64mm dia and 230 mm long GI wire)
3260 1022 Galvanised steel bolts & nuts 6 mm dia and 25 10 Nos 21.6 38 820.80
3261 mm long round head with slots
3262 7015 Galvanised Steel soffit cleat (Size each 72 3 216.00
3263 27x37x25x0.60mm)
3264 7020 All drive screws ( for gypsum board) 100 Nos 10 58 580.00
3265 7016 Joint filler kilogram 22.81 26 593.06
3266 7017 Joint finisher kilogram 34.21 23 786.83
3267 7018 Joint tape roll roll 1.27 100 127.00
3268 7021 Primer ( for gypsum board) litre 18.66 85 1586.10
3269 7388 Dash hold fastener 12.5 mm dia, 40 mm long each 72 11 792.00
3270 with 6 mm dia bolt
3271 9999 Sundries like rawl plug scaffolding etc L.S. 807.3 2 1614.60
3272 9977 Carriage of material etc. L.S. 447.2 2 894.40
3273 LABOUR :-
3274 15 Carpenter 2nd class day 31.104 403.67 12555.75
3275 17 Beldar day 31.104 350.00 10886.40
3276 31 Painter day 10.368 403.67 4185.25
3277 TOTAL 68719.37 W
3278 Add 1 % Water charges on "W" 687.1937
3279 TOTAL 69406.56 X
3280 Add GST (multiplying factor 0.1405) on "X" 9751.62
3281 TOTAL 79158.18 Y
3282 Add 15 % Contractor's profit and overheads on "Y" 11873.73
3283 Total 91031.91 Z
3284 Add Cess @ 1% on "Z" 910.32
3285 Cost for 103.68 sqm. 91942.23
3286 Cost of 1 Sqm. 9194.22
3288 Say 9194.20
3298
3299 12.45.2 12.5 mm thick tapered edge Glass Reinforced
3300 Gypsum (GRG)
Details of cost board conforming
for 10.8x9.6m = 103.68sqm.to IS: 2095- (Part 3) : 1996
3301 (Board
MATERIAL
with BIS Certification marks)
3302 Gypsum board 12.5mm thick = 103.68 sqm.+
3303 Add wastage @ 5% = 5.18sqm.
3304 Total = 108.86 sqm.
3305 7366 12.5 mm thick tapered edge gypsum fire sqm 108.86 240 26126.40
3306 resistant board
3307 7010 Galvanised Steel ceiling section (size metre 238.14 46 10954.44
3308 80x26x0.50mm)
3309 7011 Galvanised Steel perimetre Channel (Size metre 41.84 22 920.48
3310 20x27x30x0.50mm)
3311 7012 Galvanised Steel intermediate Channel (Size metre 90.72 38 3447.36
3312 15x45x15x0.90mm)
3313 7013 Galvanised Steel angle hanger metre 10.8 12 129.60
3314 (Celling angle) (Size 25x10x0.50mm)
3315 7014 Galvanised Steel connecting clips each 189 4 756.00
3316 (2.64mm dia and 230 mm long GI wire)
3317 1022 Galvanised steel bolts & nuts 6 mm dia and 25 10 Nos 21.6 38 820.80
3318 mmlong round head with slots
3319 7015 Galvanised Steel soffit cleat (Size each 72 3 216.00
3320 27x37x25x0.60mm)
3321 7020 All drive screws ( for gypsum board) 100 Nos 10 58 580.00
3322 7016 Joint filler kilogram 22.81 26 593.06
3323 7017 Joint finisher kilogram 34.21 23 786.83
3324 7018 Joint tape roll roll 1.27 100 127.00
3325 7021 Primer ( for gypsum board) litre 18.66 85 1586.10
3326 7388 Dash hold fastener 12.5 mm dia, 40 mm long each 72 11 792.00
3327 with 6 mm dia bolt
3328 9999 Sundries like rawl plug scaffolding etc L.S. 807.3 2 1614.60
3329 9977 Carriage of material etc. L.S. 447.2 2 894.40
3330 LABOUR :-
3331 15 Carpenter 2nd class day 31.104 403.67 12555.75
3332 17 Beldar day 31.104 350.00 10886.40
3333 31 Painter day 10.37 403.67 4186.06
3334 TOTAL 77973.28 W
3335 Add 1 % Water charges on "W" 779.7328
3336 TOTAL 78753.01 X
3337 Add GST (multiplying factor 0.1405) on "X" 11064.80
3338 879 TOTAL 89817.81 Y
3339 Add 15 % Contractor's profit and overheads on "Y" 13472.67
3340 Total 103290.48 Z
3342 Add Cess @ 1% on "Z" 1032.90
3343 Cost for 103.68 sqm. 104323.38
3344 Cost of 1 Sqm. 1006.21
3345 Say 1006.20
3346
3350
3351
3352
3353
3354 12.45.3 12.5 mm thick tapered edge gypsum moisture
3355 resistant board
Details of cost for 10.8x9.6m = 103.68sqm.
3356 MATERIAL
3357 Gypsum board 12.5mm thick = 103.68 sqm.+
3358 Add wastage @ 5% = 5.18sqm.
3359 Total = 108.86 sqm.
3360 7031 12.5 mm thick tapered edge gypsum moisture sqm 108.86 275 29936.50
3361 resistant board
3362 7010 Galvanised Steel ceiling section (size metre 238.14 46 10954.44
3363 80x26x0.50mm)
3364 7011 Galvanised Steel perimetre Channel (Size metre 41.84 22 920.48
3365 20x27x30x0.50mm)
3366 7012 Galvanised Steel intermediate Channel (Size metre 90.72 38 3447.36
3367 15x45x15x0.90mm)
3368 7013 Galvanised Steel angle hanger metre 10.8 12 129.60
3369 (Celling angle) (Size 25x10x0.50mm)
3370 7014 Galvanised Steel connecting clips each 189 4 756.00
3371 (2.64mm dia and 230 mm long GI wire)
3372 1022 Galvanised steel bolts & nuts 6 mm dia and 25 10 Nos 21.6 38 820.80
3373 mmlong round head with slots
3374 7015 Galvanised Steel soffit cleat (Size each 72 3 216.00
3375 27x37x25x0.60mm)
3376 7020 All drive screws ( for gypsum board) 100 Nos 10 58 580.00
3377 7016 Joint filler kilogram 22.81 26 593.06
3378 7017 Joint finisher kilogram 34.21 23 786.83
3379 7018 Joint tape roll roll 1.27 100 127.00
3380 7021 Primer ( for gypsum board) litre 18.66 85 1586.10
3381 7388 Dash hold fastener 12.5 mm dia, 40 mm long each 72 11 792.00
3382 with 6 mm dia bolt
3383 9999 Sundries like rawl plug scaffolding etc L.S. 807.3 2 1614.60
3384 9977 Carriage of material etc. L.S. 447.2 2 894.40
3385 LABOUR
3386 15 Carpenter 2nd class day 31.104 403.67 12555.75
3395 17 Beldar day 31.104 350.00 10886.40
3396 31 Painter day 10.37 403.67 4186.06
3397 TOTAL 81783.38 W
3398 Add 1 % Water charges on "W" 817.8338
3399 TOTAL 82601.21 X
3400 Add GST (multiplying factor 0.1405) on "X" 11605.47
3401 TOTAL 94206.68 Y
3402 Add 15 % Contractor's profit and overheads on "Y" 14131.00
3403 Total 108337.68 Z
3404 Add Cess @ 1% on "Z" 1083.38
3405 Cost for 103.68 sqm. 109421.06
3406 Cost of 1 Sqm. 1055.37
3407 Say 1055.40
3408
3409
3410 12.45.4 Fully Perforated Gypsum Plaster Board of size 1200
x 2400x12.5 mm having approx. 15 % perforated area with
perforation size and pattern as approved by the Engineer-
incharge and as per manufacturer's specification, with all 4
side tapered and backed by acoustical tissue with NRC value
not less than 0.60

3411 Details of cost for 10.8x9.6m = 103.68sqm.


3412 MATERIAL
3413 Gypsum board 12.5mm thick = 103.68 sqm.+
3414 Add wastage @ 5% = 5.18sqm.
3415 Total = 108.86 sqm.
3416 7028 12.5 mm thick Fully Perforated gypsum board sqm 108.86 410 44632.60
3417 7010 Galvanised Steel ceiling section (size metre 238.14 46 10954.44
3418 80x26x0.50mm)
3419 7011 Galvanised Steel perimetre Channel (Size metre 41.84 22 920.48
3420 20x27x30x0.50mm)
3421 7012 Galvanised Steel intermediate Channel (Size metre 90.72 38 3447.36
3422 15x45x15x0.90mm)
3423 7013 Galvanised Steel angle hanger (Celling angle) metre 10.8 12 129.60
3424 (Size 25x10x0.50mm)
3425 7014 Galvanised Steel connecting clips each 189 4 756.00
3426 (2.64mm dia and 230 mm long GI wire)
3427 1022 Galvanised steel bolts & nuts 6 mm dia and 25 10 Nos 21.6 38 820.80
3428 mmlong round head with slots
3429 7015 Galvanised Steel soffit cleat (Size each 72 3 216.00
3430 27x37x25x0.60mm)
3431 7020 All drive screws ( for gypsum board) 100 Nos 10 58 580.00
3432 7016 Joint filler kilogram 22.81 26 593.06
3433 7017 Joint finisher kilogram 34.21 23 786.83
3434 7018 Joint tape roll roll 1.27 100 127.00
3435 7021 Primer ( for gypsum board) litre 18.66 85 1586.10
3444 7388 Dash hold fastener 12.5 mm dia, 40 mm long each 72 11 792.00
3445 with 6 mm dia bolt
3446 9999 Sundries like rawl plug scaffolding etc L.S. 807.3 2 1614.60
3447 9977 Carriage of material etc. L.S. 447.2 2 894.40
3448 LABOUR :-
3449 15 Carpenter 2nd class day 31.104 403.67 12555.75
3450 17 Beldar day 31.104 350.00 10886.40
3451 31 Painter day 10.37 403.67 4186.06
3452 TOTAL 96479.48 W
3453 Add 1 % Water charges on "W" 964.7948
3454 TOTAL 97444.27 X
3455 Add GST (multiplying factor 0.1405) on "X" 13690.92
3456 TOTAL 111135.19 Y
3457 Add 15 % Contractor's profit and overheads on "Y" 16670.28
3458 Total 127805.47 Z
3459 Add Cess @ 1% on "Z" 1278.05
3460 Cost for 103.68 sqm. 129083.52
3461 Cost of 1 Sqm. 1245.02
3462 Say 1245.00
3463
3464
3465 12.46 Providing and fixing to the inlet mouth of rain water
3466 pipe
of 8 mmPTMTand(an Engineering
weighing Thermoplastic)
not less grating square
than 100 gms.
3467 (Slit) 150 mm square with
Details of cost for 1 grating
a height
3468 MATERIAL
3469 7857 P.T.M.T. Grating square slit 150mm each 1 66.75 66.75
3470 9977 Carriage of material and fixing charges L.S. 4.16 2 8.32
3471 TOTAL 75.07 W
3472 Add 1 % Water charges on "W" 0.7507
3473 TOTAL 75.82 X
3474 Add GST (multiplying factor 0.1405) on "X" 10.65
3475 TOTAL 86.47 Y
3476 Add 15 % Contractor's profit and overheads on "Y" 12.97
3477 Total 99.44 Z
3478 Add Cess @ 1% on "Z" 0.99
3479 Cost of each grating 100.43
3480 Say 100.43
3481 100.40
3491
3492
3493
3494
3495 12.47 Providing & fixing UV stabilised fiberglass reinforced
3496 plastic
texturedsheet roofingasupspecified.
or smooth to any pitch, including fixing with
3497 polymer coated 'J' or 'L' hooks, bolts & nuts 8mm dia. G.I
12.47.1 2 mmwashers
plain/bitumen thick corrugated
complete(2.5" or 4.2" or the
but excluding 6") or step-
cost of
3498 down (2"
specified or 3" or 6" ) as
3499 Details of cost for area of roof.
3500
3501 2x18.09x5.1 = 184.518 sqm.
3502 MATERIAL
3503 8668 UV stabilised 2 mm thick corrugated FRP sqm 240.408 485 116597.88
3504 sheet
3505 9977 Carriage of sheet L.S. 104 2 208.00
3506 G.I.Seam bolts and nuts 60cm centre to centre
3507 zig-zag i.e. 30cm
3508 centre to centre straight
3509 Breadth is 5.1metre
3510 No. of bolts in one lap 5.1/0.3 =17 nos.
3511 2x26(laps)x17 nos. = 884 nos.
3512 1022 Galvanised steel bolts & nuts 6 mm dia and 25 10 Nos 88.4 38 3359.20
3513 mmlong round head with slots G.I.,J or L
3514 hooks 8mm dia.
3515 (No. of purlins to be used 5 on either
3516 side)2x5x27
3517 (No. of sheets)x23 nos. of bolts in each sheet
3518 = 810 nos.
3519 1023 Galvanised steel J or L hooks 8 mm dia 10 Nos 81 120 9720.00
3520 1207 G.I. Limpet washer 100 Nos 16.94 21 355.74
3521 (total of seam and J bolts)
3522 884+810= 1694
3523 1208 Bitumen washer 100 Nos 16.94 30 508.20
3524 9977 Carriage of bolts and washers L.S. 26.91 2 53.82
3525 9999 Sundries L.S. 53.82 2 107.64
3526 LABOUR
3527 30 Mistry day 1.3 403.67 524.77
3528 15 Carpenter 2nd class day 15.5 403.67 6256.89
3529 17 Beldar day 15.5 350.00 5425.00
3530 TOTAL 143117.14 W
3531 Add 1 % Water charges on "W" 1431.1714
3532 TOTAL 144548.31 X
3533 Add GST (multiplying factor 0.1405) on "X" 20309.04
3534 TOTAL 164857.35 Y
3535 Add 15 % Contractor's profit and overheads on "Y" 24728.60
3536 Total 189585.95 Z
3537 Add Cess @ 1% on "Z" 1895.86
3538 Cost of 184.518 Sqm. 191481.81
3539 883 Cost of 1 Sqm. 1037.74
3540 Say 1037.70
3550
3551
3552
3553 12.47.2 2 mm thick flat
3554 Details of cost for area of roof.
3555 2x18.09x5.1 = 184.518 sqm.
3556 MATERIAL
3557 8667 UV stabilised 2 mm thick plain FRP sheet sqm 240.408 430 103375.44
3558 9977 Carriage of sheet L.S. 104 2 208.00
3559 G.I.Seam bolts and nuts 60cm centre to centre
3560 zig-zag i.e. 30cm
3561 centre to centre straight
3562 Breadth is 5.1metre
3563 No. of bolts in one lap 5.1/0.3 =17 nos.
3564 2x26(laps)x17 nos. = 884 nos.
3565 1022 Galvanised steel bolts & nuts 6 mm dia and 25 10 Nos 88.4 38 3359.20
3566 mmlong round head with slots G.I.,J or L
3567 hooks 8mm dia.
3568 (No. of purlins to be used 5 on either
3569 side)2x5x27
3570 (No. of sheets)x23 nos. of bolts in each sheet
3571 = 810 nos.
3572 1023 Galvanised steel J or L hooks 8 mm dia 10 Nos 81 120 9720.00
3573 1207 G.I. Limpet washer 100 Nos 16.94 21 355.74
3574 (total of seam and J bolts)
3575 884+810= 1694
3576 1208 Bitumen washer 100 Nos 16.94 30 508.20
3577 9977 Carriage of bolts and washers L.S. 26.91 2 53.82
3578 9999 Sundries L.S. 53.82 2 107.64
3579 LABOUR
3580 30 Mistry day 1.3 403.67 524.77
3581 15 Carpenter 2nd class day 15.5 403.67 6256.89
3582 17 Beldar day 15.5 350.00 5425.00
3583 TOTAL 129894.70 W
3584 Add 1 % Water charges on "W" 1298.947
3585 TOTAL 131193.65 X
3586 Add GST (multiplying factor 0.1405) on "X" 18432.71
3587 TOTAL 149626.36 Y
3588 Add 15 % Contractor's profit and overheads on "Y" 22443.95
3589 Total 172070.31 Z
3590 Add Cess @ 1% on "Z" 1720.70
3591 Cost of 184.518 Sqm. 173791.01
3593 Cost of 1 Sqm. 941.86
3594 Say 941.90
3595
3596
3602
3603
3604 12.48 Providing & fixing on roof pressed clay tile
3605 (Mangalore
work complete tile)(steel
of 20 frame
mm nominal
work tothickness and of approved
be paid separately).
3606 size and as per approved
Details of cost for 10 sqm
pattern on steel frame
3607 MATERIAL
3608 8670 Mangalore tiles 20 mm thick each 160 8 1280.00
3609 2207 Carriage of Brick tiles 1000 Nos 0.16 169.81 27.17
3610 LABOUR
3611 23 Mason (brick layer) 1st class day 0.3 505.17 151.55
3612 17 Beldar day 1.56 350.00 546.00
3613 9999 Sundries L.S. 13 2 26.00
3614 Total 2030.72 W
3615 Add 1 % Water charges on "W" 20.3072
3616 TOTAL 2051.03 X
3617 Add GST (multiplying factor 0.1405) on "X" 288.17
3618 TOTAL 2339.20 Y
3619 Add 15 % Contractor's profit and overheads on "Y" 350.88
3620 Total 2690.08 Z
3621 Add Cess @ 1% on "Z" 26.90
3622 Cost of 10 sqm 2716.98
3623 Cost of 1 sqm 271.7
3624 Say 271.70
3625
3626
3627
3628
3629 12.49 Providing & laying on roof pressed clay tile ridge
3630 (Mangalore
work to be paidtile) separately).
of 20mm thickness and of approved pattern
3631 on steel frame work complete (steel frame
Details of cost for 3.60 metre
3632 MATERIAL
3633 8669 Mangalore ridge tiles 20 mm thick each 12 8 96.00
3634 2207 Carriage of Brick tiles 1000 Nos 0.012 169.81 2.04
3635 LABOUR
3636 23 Mason (brick layer) 1st class day 0.01 505.17 5.05
3645 17 Beldar day 0.15 350.00 52.50
3646 9999 Sundries L.S. 2.6 2 5.20
3647 Total 160.79 W
3648 Add 1 % Water charges on "W" 1.6079
3649 TOTAL 162.40 X
3650 Add GST (multiplying factor 0.1405) on "X" 22.82
3651 TOTAL 185.22 Y
3652 Add 15 % Contractor's profit and overheads on "Y" 27.78
3653 Total 213.00 Z
3654 Add Cess @ 1% on "Z" 2.13
3655 Cost of 3.60 metre 215.13
3656 Cost for 1 metre 59.76
3657 Say 59.80
3658
3659
3660 12.50 Providing and fixing precoated galvanised iron
3661 profile
Details ofsheets
cost of (size, shape and pitch of corrugation as
216.14 sqm.
3662 approved by Engineer-in-charge)
Consider a shed of 20x10 metres.
0.50 mm (+ 0.05 %) total
coated thickness with zinc coating 120 grams per sqm as per
3663 (External dimensions of plinth).
3664 Area of roof-
3665 20.2x10.70m = 216.14 sqm.
3666 MATERIAL
3667 Sheets used = 20 nos.x10.70mx1.06m
3668 = 226.84sqm
3669 Add 3% wastage = 6.81 Total = 233.65sqm.
3670 8671 Precoated galvanised iron profile sheet sqm 233.65 650 151872.50
3671 0.50 mm TCT
3672 9977 Carriage of sheets L.S. 104 2 208.00
3673 1023 Galvanised steel J or L hooks 8 mm dia 10 Nos 47.6 120 5712.00
3674 1208 Bitumen washer 100 Nos 4.76 30 142.80
3675 1209 G.I. plain washer thick 100 Nos 4.76 35 166.60
3676 9977 Carriage of bolts and nuts, washers etc. L.S. 8.06 2 16.12
3677 9999 Sundries L.S. 39.52 2 79.04
3686 LABOUR
3687 30 Mistry day 2.34 403.67 944.59
3688 15 Carpenter 2nd class day 9.34 403.67 3770.28
3689 17 Beldar day 9.34 350.00 3269.00
3690 TOTAL 166180.93 W
3691 Add 1 % Water charges on "W" 1661.8093
3692 TOTAL 167842.74 X
3693 Add GST (multiplying factor 0.1405) on "X" 23581.90
3694 TOTAL 191424.64 Y
3695 Add 15 % Contractor's profit and overheads on "Y" 28713.70
3696 Total 220138.34 Z
3697 Add Cess @ 1% on "Z" 2201.38
3698 Cost of 216.14 sqm. 222339.72
3699 Cost of 1.00 sqm. 1028.68
3700 Say 1028.70
3701
3702
3703 12.51 Providing and fixing precoated galvanised steel
sheet roofing accessories 0.50 mm (+ 0.05 %) total coated
thickness, Zinc coating 120 grams per sqm as per IS: 277, in
240 mpa steel grade, 5-7 microns epoxy primer on both side
3704 screws complete :
3705 12.51.1 Ridges plain (500 - 600mm)
3706 Detail of cost for 20.20 metre
3707 One piece plain ridges
3708 Consider a shed of 20x10m (external
3709 dimensions at plinth).
3710 Length of ridges 20.2 metre + 5% wastage =
3711 23.11 metre.
3712 MATERIAL
3713 8672 Precoated galvanised steel plain ridges metre 23.11 450 10399.50
3714 0.50 mm TCT and 500 -600 mm wide 0
3715 9977 Carriage (The ridge is to be fixed with the L.S. 13.52 2 27.04
3716 same hooks as the Sheets)
3717 9999 Sundries L.S. 6.76 2 13.52
3718 LABOUR
3719 30 Mistry day 0.14 403.67 56.51
3720 15 Carpenter 2nd class day 0.55 403.67 222.02
3721 17 Beldar day 1.64 350.00 574.00
3722 TOTAL 11292.59 W
3723 Add 1 % Water charges on "W" 112.9259
3724 TOTAL 11405.52 X
3725 Add GST (multiplying factor 0.1405) on "X" 1602.47
3726 TOTAL 13007.99 Y
3727 Add 15 % Contractor's profit and overheads on "Y" 1951.20
3728 Total 14959.19 Z
3729 Add Cess @ 1% on "Z" 149.59
3730 Cost of 20.20 metre 15108.78
3731 887 Cost of 1.00 metre 747.96
3732 Say 748.00
3733
3740
3741
3742
3743 12.51.2 Flashings/ Aprons.( Upto 600 mm)
3744 Details for shed of 20.2 metres completed length
3745 MATERIAL
3746 8673 Precoated galvanised steel flashings/ aprons metre 23.11 450 10399.50
3747 0.50mm TCT and wide upto 600 mm
3748 20.20 + 5% wastage = 23.11 metre
3749 9977 Carriage of appron pieces. (The appron pieces L.S. 3.25 2 6.50
3750 are to be fixed with the same hooks as the
3751 sheets)
3752 9999 Sundries L.S. 3.25 2 6.50
3753 LABOUR
3754 30 Mistry day 0.07 403.67 28.26
3755 15 Carpenter 2nd class day 0.28 403.67 113.03
3756 17 Beldar day 0.82 350.00 287.00
3757 TOTAL 10840.79 W
3758 Add 1 % Water charges on "W" 108.4079
3759 TOTAL 10949.20 X
3760 Add GST (multiplying factor 0.1405) on "X" 1538.36
3761 TOTAL 12487.56 Y
3762 Add 15 % Contractor's profit and overheads on "Y" 1873.13
3763 Total 14360.69 Z
3764 Add Cess @ 1% on "Z" 143.61
3765 Cost of 20.20 metre 14504.30
3766 Cost of 1.00 metre 718.03
3767 Say 718.00
3768
3769
3770
3771 12.51.3 North light curves
3772 Details of North light curve 20.20 metres long complete length
3773 MATERIAL
3774 8675 Precoated galvanised steel north light curves metre 23.11 230 5315.30
3775 20.20 + 5% wastage = 23.11 metre
3776 1023 Galvanised steel J or L hooks 8 mm dia 10 Nos 4 120 480.00
3777 1209 G.I. plain washer thick 100 Nos 0.4 35 14.00
3778 1208 Bitumen washer 100 Nos 0.4 30 12.00
3779 9977 Carriage of hooks, nuts, washers and curves L.S. 9.88 2 19.76
3780 9999 Sundries L.S. 6.24 2 12.48
3781 LABOUR
3790 30 Mistry day 0.1 403.67 40.37
3791 15 Carpenter 2nd class day 0.3 403.67 121.10
3792 17 Beldar day 1 350.00 350.00
3793 TOTAL 6365.01 W
3794 Add 1 % Water charges on "W" 63.6501
3795 TOTAL 6428.66 X
3796 Add GST (multiplying factor 0.1405) on "X" 903.23
3797 TOTAL 7331.89 Y
3798 Add 15 % Contractor's profit and overheads on "Y" 1099.78
3799 Total 8431.67 Z
3800 Add Cess @ 1% on "Z" 84.32
3801 Cost of 20.20 metre 8515.99
3802 Cost of 1.00 metre 421.58
3803 Say 421.60
3804
3805
3806 12.51.4 Barge board (Upto 300 mm)
3807 Details of cost for 8.23 metres
3808 Completed length of barge boards
3809 = 8.23 + 5% wastage = 8.64 metre
3810 MATERIAL
3811 8676 Precoated galvanised steel barge board metre 8.64 215 1857.60
3812 222 Seam bolts and nuts 6 mm dia and 25 mm 10 Nos 0.5 10 5.00
3813 long
3814 1211 G.I. plain washer for seam bolts 100 Nos 0.1 32 3.20
3815 1208 Bitumen washer 100 Nos 0.05 30 1.50
3816 9977 Carriage of barge boards, bolts, nuts and L.S. 9.36 2 18.72
3817 washers
3818 9999 Sundries L.S. 6.76 2 13.52
3819 LABOUR
3820 30 Mistry day 0.04 403.67 16.15
3821 15 Carpenter 2nd class day 0.06 403.67 24.22
3822 17 Beldar day 0.4 350.00 140.00
3823 TOTAL 2079.91 W
3824 Add 1 % Water charges on "W" 20.7991
3825 TOTAL 2100.71 X
3826 Add GST (multiplying factor 0.1405) on "X" 295.15
3827 TOTAL 2395.86 Y
3828 Add 15 % Contractor's profit and overheads on "Y" 359.38
3829 Total 2755.24 Z
3830 Add Cess @ 1% on "Z" 27.55
3831 Cost of 8.23 metre 2782.79
3832 Cost of 1.00 metre 338.13
3833 Say 338.10
3834
3835
3843
3844 12.51.5 Crimp curve
3845 Details of crimp curve 20.2 metres long complete length, Area 20.20 x 1.06
3847 =21.412 sqm
3848 MATERIAL
3849 8677 Precoated galvanised steel crimp curve sqm 22.483 230 5171.09
3850 1023 Galvanised steel J or L hooks 8 mm dia 10 Nos 4 120 480.00
3851 1209 G.I. plain washer thick 100 Nos 0.4 35 14.00
3852 1208 Bitumen washer 100 Nos 0.4 30 12.00
3853 9977 Carriage of hooks, nuts, washers and curves L.S. 9.88 2 19.76
3854 9999 Sundries L.S. 6.24 2 12.48
3855 LABOUR
3856 30 Mistry day 0.1 403.67 40.37
3857 15 Carpenter 2nd class day 0.3 403.67 121.10
3858 17 Beldar day 1 350.00 350.00
3859 TOTAL 6220.80 W
3860 Add 1 % Water charges on "W" 62.208
3861 TOTAL 6283.01 X
3862 Add GST (multiplying factor 0.1405) on "X" 882.76
3863 TOTAL 7165.77 Y
3864 Add 15 % Contractor's profit and overheads on "Y" 1074.87
3865 Total 8240.64 Z
3866 Add Cess @ 1% on "Z" 82.41
3867 Cost of 21.412 sqm 8323.05
3868 Cost of 1.00 sqm 388.71
3869 Say 388.70
3870
3871
3872 12.51.6 Gutter (600 mm over all girth)
3873 Detail of cost of 10 metre
3874 0.63mm thick with zinc coating not less
3875 than 275gm/sqm
3876 Consider a length of 10.00m
3877 Sheet used = 10x1.06m x 0.60 = 6.36 sqm.
3878 Total = 6.36 metre
3879 8674 Precoated galvanised steel gutter metre 10 420 4200.00
3880 9977 Carriage of gutter L.S. 1.04 2 2.08
3881 1008 Flats upto 10 mm in thickness quintal 0.0749 5300 396.97
3882 1022 Galvanised steel bolts & nuts 6 mm dia and 25 10 Nos 2 38 76.00
3883 mmlong round head with slots
3884 1024 Galvanised steel bolts & nuts 10 mm dia and each 30 9 270.00
3885 125 mm long round head with slots
3886 1210 G.I. plain washer thin 100 Nos 0.7 21 14.70
3887 1208 Bitumen washer 100 Nos 0.4 30 12.00
3888 9977 Carriage of G.I. seam bolts and washers L.S. 2.73 2 5.46
3889 9999 Sundries L.S. 5.33 2 10.66
3890 LABOUR
3899 12 Blacksmith 1st class day 0.5 505.17 252.59
3900 17 Beldar day 0.5 350.00 175.00
3901 9999 Sundries L.S. 12.61 2 25.22
3902 30 Mistry day 0.28 403.67 113.03
3903 12 Blacksmith 1st class day 0.84 505.17 424.34
3904 15 Carpenter 2nd class day 0.62 403.67 250.28
3905 17 Beldar day 1.68 350.00 588.00
3906 TOTAL 6816.33 W
3907 Add 1 % Water charges on "W" 68.1633
3908 TOTAL 6884.49 X
3909 Add GST (multiplying factor 0.1405) on "X" 967.27
3910 TOTAL 7851.76 Y
3911 Add 15 % Contractor's profit and overheads on "Y" 1177.76
3912 Total 9029.52 Z
3913 Add Cess @ 1% on "Z" 90.30
3914 Cost of 10.00 metres 9119.82
3915 Cost of 1.00 metre 911.98
3916 Say 912.00
3917
3918 12.52 Providing and fixing tiled false ceiling of specified
3934 materials
12.52.1 GI of Metal
size 595x595
Ceiling mm in plain
Lay in true horizontal level,
Tegular edge Global
3936 suspended
white color on
tilesinter
of locking
size metal
595x595 grid
mm, of
and hot
0.5 dipped
mm thick with 8
factory
galvanizedpainted
steelafter bending.
sections ( galvanized @ 120 grams/ sqm,
3938 mm drop; made of G I
Details of cost for 100 sqm.
sheet having galvanizing of 100
gms/sqm (both sides inclusive) and electro statically
3940 MATERIAL
3941 Celling Area =100 sqm
3942 Add wastage @ 5% = 0.05 sqm.
3943 Total=100.05 sqm
3944 8599 GI Metal Tile Lay-in Plain Tegular edge global sqm 105 612 64260.00
3945 white color tiles of Size 595x595mm and 0.5
3946 mm thick
3947 8611 Main T ceiling sections 24x38x0.3 mm each 29.5 115 3392.50
3948 (3 metre long)
3949 Including Wastage @ 10%
3950 8612 Perimeter wall angle 24x24x0.3mm each 13.5 80 1080.00
3951 (3 metre long)
3952 Including Wastage @ 10%
3953 8613 Intermediate cross T-section 24x25x each 147 35 5145.00
3954 0.3mm (1.2 mtrs long)
3955 Including Wastage @ 10% on Grid for cut outs
3956 8614 Intermediate cross T-section 24x25x each 147 17 2499.00
3957 0.3mm (0.6 mtrs long)
3958 Including Wastage @ 10% on Grid for cut outs
3959 8615 Hanger rod 4 mm thick each 72 8 576.00
3960 8616 Adjustment clip 85x30x0.8mm each 72 5 360.00
3961 8617 Soffit cleat (Size 27x37x25x1.60mm) each 72 4 288.00
3962 7388 Dash hold fastener 12.5 mm dia, 40 mm long each 72 11 792.00
3963 with 6 mm dia bolt
3964 9999 Sundries i.e. scaffolding etc. L.S. 187.95 2 375.90
3965 9977 Carriage of materials etc. L.S. 89.28 2 178.56
3966 LABOUR
3967 14 Carpenter 1st class day 28 505.17 14144.76
3968 17 Beldar day 23 350.00 8050.00
3969 TOTAL 101141.72 W
3970 Add 1 % Water charges on "W" 1011.4172
3971 TOTAL 102153.14 X
3972 Add GST (multiplying factor 0.1405) on "X" 14352.52
3973 TOTAL 116505.66 Y
3974 Add 15 % Contractor's profit and overheads on "Y" 17475.85
3975 Total 133981.51 Z
3976 Add Cess @ 1% on "Z" 1339.82
3977 Cost of 100 sqm. 135321.33
3978 Cost of 1 sqm. 1353.21
3979 Say 1353.20
3980
3987
3988
3989
3990 12.52.2 GI Metal Ceiling Lay in perforated Tegular edge
3991 global white fiber
black Glass coloracoustical
tiles of size 595x595 mm and 0.5 mm thick
fleece.
3992 with 8 mm drop; made
Details of cost for 100 sqm.
of GI sheet having galvanizing of 100
gms/ sqm (both sides inclusive) and 20% perforation area
3993 MATERIAL
3994 Celling Area =100 sqm
3995 Add wastage @ 5% = 0.05 sqm.
3996 Total=100.05 sqm
3997 8600 GI Metal Tile Lay-in Perforated Tegular edge sqm 105 715 75075.00
3998 global white color tiles of Size
3999 595x595mm and 0.5 mm thick
4000 8611 Main T ceiling sections 24x38x0.3 mm each 29.5 115 3392.50
4001 (3 metre long)
4002 Including Wastage @ 10%
4003 8612 Perimeter wall angle 24x24x0.3mm each 13.5 80 1080.00
4004 (3 metre long)
4005 Including Wastage @ 10%
4006 8613 Intermediate cross T-section 24x25x each 147 35 5145.00
4007 0.3mm (1.2 mtrs long)
4008 Including Wastage @ 10% on Grid for cut outs
4009 8614 Intermediate cross T-section 24x25x each 147 17 2499.00
4010 0.3mm (0.6 mtrs long)
4011 Including Wastage @ 10% on Grid for cut outs
4012 8615 Hanger rod 4 mm thick each 72 8 576.00
4013 8616 Adjustment clip 85x30x0.8mm each 72 5 360.00
4014 8617 Soffit cleat (Size 27x37x25x1.60mm) each 72 4 288.00
4015 7388 Dash hold fastener 12.5 mm dia, 40 mm long each 72 11 792.00
4016 with 6 mm dia bolt
4017 9999 Sundries i.e. scaffolding etc. L.S. 187.95 2 375.90
4018 9977 Carriage of materials etc. L.S. 89.28 2 178.56
4019 LABOUR
4020 14 Carpenter 1st class day 28 505.17 14144.76
4021 17 Beldar day 23 350.00 8050.00
4022 TOTAL 111956.72 W
4023 Add 1 % Water charges on "W" 1119.5672
4024 TOTAL 113076.29 X
4025 Add GST (multiplying factor 0.1405) on "X" 15887.22
4026 TOTAL 128963.51 Y
4027 Add 15 % Contractor's profit and overheads on "Y" 19344.53
4028 Total 148308.04 Z
4029 Add Cess @ 1% on "Z" 1483.08
4030 Cost of 100 sqm. 149791.12
4031 Cost of 1 sqm. 1497.91
4032 Say 1497.90
4033
4041
4042
4043
4044
4045
4046 12.52.3 12.5 mm thick square edge PVC Laminated Gypsum
4047 Tile
so asoftosize 595x595
make mm,
the tile made of Gypsum
a completely plasterboard,
sealed unit.
4048 manufactured from natural
Details of cost for 100 sqm.
gypsum as per IS 2095 part I and
laminated with white 0.16mm thick fire retardant PVC film on
4049 MATERIAL
4050 Celling Area =100 sqm
4051 Add wastage @ 5% = 0.05 sqm.
4052 Total=100.05 sqm
4053 8601 PVC Laminated Gypsum Tiles (Square edge) sqm 105 880 92400.00
4054 of Size 595x595 mm and 12.5 mm thick
4055 8611 Main T ceiling sections 24x38x0.3 mm each 29.5 115 3392.50
4056 (3 metre long)
4057 Including Wastage @ 10%
4058 8612 Perimeter wall angle 24x24x0.3mm each 13.5 80 1080.00
4059 (3 metre long)
4060 Including Wastage @ 10%
4061 8613 Intermediate cross T-section 24x25x each 147 35 5145.00
4062 0.3mm (1.2 mtrs long)
4063 Including Wastage @ 10% on Grid for cut outs
4064 8614 Intermediate cross T-section 24x25x each 147 17 2499.00
4065 0.3mm (0.6 mtrs long)
4066 Including Wastage @ 10% on Grid for cut outs
4067 8615 Hanger rod 4 mm thick each 72 8 576.00
4068 8616 Adjustment clip 85x30x0.8mm each 72 5 360.00
4069 8617 Soffit cleat (Size 27x37x25x1.60mm) each 72 4 288.00
4070 7388 Dash hold fastener 12.5 mm dia, 40 mm long each 72 11 792.00
4071 with 6 mm dia bolt
4072 9999 Sundries i.e. scaffolding etc. L.S. 187.95 2 375.90
4073 9977 Carriage of materials etc. L.S. 89.28 2 178.56
4074 LABOUR
4075 14 Carpenter 1st class day 28 505.17 14144.76
4076 17 Beldar day 23 350.00 8050.00
4077 TOTAL 129281.72 W
4078 Add 1 % Water charges on "W" 1292.8172
4079 TOTAL 130574.54 X
4080 Add GST (multiplying factor 0.1405) on "X" 18345.72
4081 TOTAL 148920.26 Y
4082 Add 15 % Contractor's profit and overheads on "Y" 22338.04
4083 Total 171258.30 Z
4085 Add Cess @ 1% on "Z" 1712.58
4086 Cost of 100 sqm. 172970.88
4087 Cost of 1 sqm. 1729.71
4088 Say 1729.70

4094
4095
4096
4097 12.52.4 12.5 mm thick fully Perforated Gypsum Board tile
4098 made
bondedfrom
glassplasterboard having glass fibre conforming to IS:
wool backing.
4099 2095 part I, of size 595x595 mm, having perforation of 9.7x9.7
mm at 19.4 mm c/c with center borders of 48 mm and the side
4100 Details of cost for 100 sqm.
4101
4102 MATERIAL
4103 Celling Area =100 sqm
4104 Add wastage @ 5% = 0.05 sqm.
4105 Total=100.05 sqm
4106 8602 Gypsum Tiles Fully Perforated Square edge of sqm 105 375 39375.00
4107 Size 595x595 mm and 12.5 mm thick
4108 8611 Main T ceiling sections 24x38x0.3 mm each 29.5 115 3392.50
4109 (3 metre long)
4110 Including Wastage @ 10%
4111 8612 Perimeter wall angle 24x24x0.3mm each 13.5 80 1080.00
4112 (3 metre long)
4113 Including Wastage @ 10%
4114 8613 Intermediate cross T-section each 147 35 5145.00
4115 24x25x0.3mm (1.2 mtrs long)
4116 Including Wastage @ 10% on Grid for cut outs
4117 8614 Intermediate cross T-section each 147 17 2499.00
4118 24x25x0.3mm (0.6 mtrs long)
4119 Including Wastage @ 10% on Grid for cut outs
4120 8615 Hanger rod 4 mm thick each 72 8 576.00
4121 8616 Adjustment clip 85x30x0.8mm each 72 5 360.00
4122 8617 Soffit cleat (Size 27x37x25x1.60mm) each 72 4 288.00
4123 7388 Dash hold fastener 12.5 mm dia, 40 mm long each 72 11 792.00
4124 with 6 mm dia bolt
4125 9999 Sundries i.e. scaffolding etc. L.S. 187.95 2 375.90
4126 9977 Carriage of materials etc. L.S. 89.28 2 178.56
4127 LABOUR
4136 14 Carpenter 1st class day 28 505.17 14144.76
4137 17 Beldar day 23 350.00 8050.00
4138 TOTAL 76256.72 W
4139 Add 1 % Water charges on "W" 762.5672
4140 TOTAL 77019.29 X
4141 Add GST (multiplying factor 0.1405) on "X" 10821.21
4142 TOTAL 87840.50 Y
4143 Add 15 % Contractor's profit and overheads on "Y" 13176.07
4144 Total 101016.57 Z
4145 Add Cess @ 1% on "Z" 1010.17
4146 Cost of 100 sqm. 102026.74
4147 Cost of 1 sqm. 1020.27
4148 Say 1020.30
4149
4150
4151 12.53 Providing and Fixing 15 mm thick densified tegular
4152 edged
mm made ecooffriendly
0.40 mm light weight
thick calciumsheet
(minimum) silicate false
with the ceiling
help of
4154 tiles
rawl of approved
plugs at 450 texture
mm
Details of cost for 100 sqm.
of
centre size
to 595
centrex 595
with mm
25 in
mm true
long dry
horizontal
wall screws level,
@ suspended
230 mm on inter
interval and locking
laying 15metal
mm grid of hot
thick
4156 MATERIAL
densified edges calicum silicate ceiling tiles of approved
4167 8589 Calcium Silicate tegular edged celling tiles sqm 105 685 71925.00
4168 495x495 mm and 15 mm thick Area = 100 sqm
4169 + Add 5% wastage =
4170 5 sqm Total = 105 sqm
4171 8590 Galvanised Steel main Tee ceiling section each 29.5 120 3540.00
4172 Size 24x38x0.33mm (3.00 metre long)
4173 8591 Galvanised Steel perimeter wall Angle Size 24 each 13.5 65 877.50
4174 x 24 x 0.40 mm (3.00 metre long)
4175 8592 Galvanised Steel intermediate cross T section each 147 40 5880.00
4176 Size 24 x 25 x 0.33 mm (1.2 metre long)
4177 8593 Galvanised Steel intermediate cross T section each 147 20 2940.00
4178 Size 24 x 25 x 0.33.
4179 ( 0.6 metre long)
4180 8615 Hanger rod 4 mm thick each 72 8 576.00
4181 8616 Adjustment clip 85x30x0.8mm each 72 5 360.00
4182 7388 Dash hold fastener 12.5 mm dia, 40 mm long each 72 11 792.00
4183 with 6 mm dia bolt
4184 8617 Soffit cleat (Size 27x37x25x1.60mm) each 72 4 288.00
4185 8595 Wooden screws with plastic rawl plugs 35x8 each 100 1 100.00
4186 mm
4187 9999 scaffolding etc. L.S. 498.65 2 997.30
4188 9977 Carriage of materials etc. L.S. 237.48 2 474.96
4189 9999 Sundries L.S. 310.7 2 621.40
4190 LABOUR
4191 14 Carpenter 1st class day 28 505.17 14144.76
4192 17 Beldar day 23 350.00 8050.00
4193 111566.92 W
4194 Add 1 % Water charges on "W" 1115.6692
4195 TOTAL 112682.59 X
4196 Add GST (multiplying factor 0.1405) on "X" 15831.90
4197 TOTAL 128514.49 Y
4198 Add 15 % Contractor's profit and overheads on "Y" 19277.17
4199 Total 147791.66 Z
4200 Add Cess @ 1% on "Z" 1477.92
4201 Cost of 100 sqm. 149269.58
4202 Cost of 1 sqm. 1492.7
4203 Say 1492.70
4204
4205
4224
4226
4227 12.54 Providing and fixing Gl Clip in Metal Ceiling System
of 600x600 mm module which includes providing and fixing
'C' wall angle of size 20x30x20 mm made of 0.5 mm thick pre
painted steel along the perimeter of the room with help of
nylon sleeves and wooden screws at 300 mm center to
centre, suspending the main C carrier of size 10x38x10 mm
made of G.I steel 0.7 mm thick from the soffit with help of
soffit cleat 37x27x25x1.6 mm, rawl plugs of size 38x12 mm
and C carrier suspension clip and main carrier bracket at
1000 mm c/c. Inverted triangle shaped Spring Tee having
height of 24 mm and width of 34 mm made of Gl steel 0.45
mm thick is then fixed to the main C carrier and in direction
perpendicular to it at 600 mm centers with help of
suspension brackets. Wherever the main C carrier and spring
T have to join, C carrier and spring T connectors have to be
used. All sections to be galvanized @ 120 gms/ sqm (both
side inclusive), fixing with clip in tiles into spring T with :

4229 12.54.1 GI Metal Ceiling Clip in plain Beveled edge global


4230 white color tiles of size 600x600 and 0.5 mm thick with 25 mm
4231 height, made of G I sheet having galvanizing of 100 gms/ sqm
factory painted
(both sides after bending
inclusive) and electro statically polyester powder
4232
4233 Details of cost for 100 sqm.
4234
4235 MATERIAL
4236 Celling Area =100 sqm
4237
4238 Add wastage @ 5% = 5 sqm.
4239
4240 Total=105 sqm
4241
4242 8597 GI Metal Tile Clip in Plain Beveled sqm 105 677 71085.00
4243 edge global white colour tiles of size
4244 600x600 mm and 0.5mm thick
4245 8604 Spring T-section 24x34x0.45 mm (3.00 meter metre 60 190 11400.00
4246 long) Including Wastage @ 10%
4247 8605 C Wall angle section 20x30x20x metre 27.7 95 2631.50
4248 0.50 mm (3.00 meter long)
4249 Including Wastage @ 10%
4250 8606 Main C Carrier Size 10x38x10x0.70mm (3.00 metre 33 115 3795.00
4251 meter long) Including Wastage @ 10% on Grid
4252 for
4253 cut outs
4254 8607 Spring T-connector each 44 5 220.00
4255 8608 C Carrier Connector each 44 11 484.00
4256 8609 C Suspension Clip each 88 8 704.00
4257 8610 Wire Coupling Clip each 333 9 2997.00
4258 8615 Hanger rod 4 mm thick each 80 8 640.00
4259 8616 Adjustment clip 85x30x0.8mm each 80 5 400.00
4260 8617 Soffit cleat (Size 27x37x25x1.60mm) each 80 4 320.00
4261 7388 Dash hold fastener 12.5 mm dia, each 80 11 880.00
4262 40 mm long with 6 mm dia bolt
4263 9999 Sundries i.e. scaffolding etc. L.S. 188 2 376.00
4264 9977 Carriage of materials etc. L.S. 90 2 180.00
4273 LABOUR
4274 14 Carpenter 1st class day 28 505.17 14144.76
4275 17 Beldar day 23 350.00 8050.00
4276 TOTAL 118307.26 W
4277 Add 1 % Water charges on "W" 1183.0726
4278 TOTAL 119490.33 X
4279 Add GST (multiplying factor 0.1405) on "X" 16788.39
4280 TOTAL 136278.72 Y
4281 Add 15 % Contractor's profit and overheads on "Y" 20441.81
4282 Total 156720.53 Z
4283 Add Cess @ 1% on "Z" 1567.21
4284 Cost of 100 sqm. 158287.74
4285 Cost of 1 sqm. 1582.88
4286 Say 1582.90

4287
4288
4289 12.54.2 GI Metal Ceiling Clip in plain Beveled edge global
4290 white color tiles
after bending and ofperforation.
size 600x600 and 0.5 mm thick with 25 mm
4291 height, made of G I sheet having galvanizing of 100 gms/ sqm
Details of cost for 100 sqm.
(both sides inclusive) and 20% perforation area with 1.8 mm
4292
4293 MATERIAL
4294 Celling Area =100 sqm
4295 Add wastage @ 5% = 5 sqm. Total=105 sqm
4296 8598 GI Metal Tile Clip in Perforated Beveled edge sqm 105 782 82110.00
4297 global white colour tiles of size 600x600 mm
4298 and 0.5mm thick
4299 8604 Spring T-section 24x34x0.45 mm metre 60 190 11400.00
4300 (3.00 meter long)
4301 Including Wastage @ 10%
4302 8605 C Wall angle section 20x30x20x0.50 mm metre 27.7 95 2631.50
4303 (3.00 meter long)
4304 Including Wastage @ 10%
4305 8606 Main C Carrier Size 10x38x10x0.70mm metre 33 115 3795.00
4306 (3.00 meter long)
4307 Including Wastage @ 10% on Grid for cut outs
4308 8607 Spring T-connector each 44 5 220.00
4309 8608 C Carrier Connector each 44 11 484.00
4310 8609 C Suspension Clip each 88 8 704.00
4311 8610 Wire Coupling Clip each 333 9 2997.00
4312 8615 Hanger rod 4 mm thick each 80 8 640.00
4313 8616 Adjustment clip 85x30x0.8mm each 80 5 400.00
4323 8617 Soffit cleat (Size 27x37x25x1.60mm) each 80 4 320.00
4324 7388 Dash hold fastener 12.5 mm dia, 40 mm long each 80 11 880.00
4325 with 6 mm dia bolt
4326 9999 Sundries i.e. scaffolding etc. L.S. 188 2 376.00
4327 9977 Carriage of materials etc. L.S. 90 2 180.00
4328 LABOUR
4329 14 Carpenter 1st class day 28 505.17 14144.76
4330 17 Beldar day 23 350.00 8050.00
4331 TOTAL 129332.26 W
4332 Add 1 % Water charges on "W" 1293.3226
4333 TOTAL 130625.58 X
4334 Add GST (multiplying factor 0.1405) on "X" 18352.89
4335 TOTAL 148978.47 Y
4336 Add 15 % Contractor's profit and overheads on "Y" 22346.77
4337 Total 171325.24 Z
4338 Add Cess @ 1% on "Z" 1713.25
4339 Cost of 100 sqm. 173038.49
4340 Cost of 1 sqm. 1730.38
4341 Say 1730.40
4342
4343
4344
4345 12.55 Providing and fixing Heat Resistant Terrace Tiles
4346 (300
samemm x 300 mm x 20 mm) with SRI (solar refractive index)
manner.
4347 > 78, solar reflection > 0.70 and initial emittance > 0.75 on
Details of cost for 10 sqm
waterproof and sloped surface of terrace, laid on 20 mm thick
4348
4349 Area= 10 sqm+
4350 Add wastage @ 3%=0.3 sqm
4351 Total=10.30 sqm
4352 MATERIAL
4353 1204 Precast heat resistant terrace tiles sqm 10.3 409 4212.70
4354 (size 300x300mm) and 20mm thick Cement 0.00
4355 mortar 1:4 (1 cement : 4 coarse sand) 0.00
4356 3.9 Rate as per Item No.3.9 of SH:Mortar cum 0.224 3548.00 794.75
4357 367 Portland Cement (OPC-43 grade) tonne 0.044 4375 192.50
4358 368 White Cement tonne 0.044 11200 492.80
4359 2209 Carriage of Cement tonne 0.088 94.34 8.30
4360 875 Red, chocolate, orange, buff or yellow kilogram 3.08 60 184.80
4361 (red oxide of iron) light shade pigment 0.00
4362 LABOUR 0.00
4363 24 Mason (brick layer) 2nd class day 1.6 403.67 645.87
4364 18 Coolie day 2 350.00 700.00
4373 37 Skilled Beldar (for floor rubbing etc.) day 1 350.00 350.00
4374 11 Bhisti day 1 350.00 350.00
4375 13 Machine for rubbing of floors day 1.6 300 480.00
4376 9999 Sundries including carborandum stone etc. L.S. 169.98 2 339.96
4377 Total 8751.68 W
4378 Add 1 % Water charges on "W" 87.5168
4379 TOTAL 8839.20 X
4380 Add GST (multiplying factor 0.1405) on "X" 1241.91
4381 TOTAL 10081.11 Y
4382 Add 15 % Contractor's profit and overheads on "Y" 1512.17
4383 Total 11593.28 Z
4384 Add Cess @ 1% on "Z" 115.93
4385 Cost of 10 sqm 11709.21
4386 Cost of 1 sqm 1170.92
4387 Say 1170.90
4388
4389
4390
4391
4392 12.56 Providing and laying roof insulation with 40 mm thick
impervious sprayed, closed cell free Rigid Polyurethane foam
over deck insulation conforming to IS - 12432 Pt. III (density
of foam being 40-45 kg/ cum), over a coat of polyurethane
4393 per direction of Engineer-in-Charge.
4394 Details of cost for 1 sqm
4395 MATERIAL
4396 7050 PU Primer sqm 1 60 60.00
4397 Area for PU Spray = 1 sqm+
4398 Add for wastage @ 10%=0.10 sqm
4399 Total=1.10 sqm
4400 7051 40 mm (average) PU spray having sqm 1.1 400 440.00
4401 40-45 kg/m3 density
4402 7052 GI wire netting 3/4" x 24 G sqm 1 26 26.00
4403 9999 Sundries L.S. 6.71 2 13.42
4404 9999 Polymerized mastic for all joints L.S. 20.13 2 40.26
4405 7053 400 G polythene sheet sqm 1 14 14.00
4406 9999 Cement L.S. 44.67 2 89.34
4407 9999 Graded stone L.S. 13.75 2 27.50
4408 9999 Sand L.S. 21.48 2 42.96
4409 9977 Carriage of material L.S. 16.78 2 33.56
4410 LABOUR 0
4411 9999 For PU spray L.S. 80.54 2 161.08
4412 9999 For cement screed with Polythene sheet L.S. 53.69 2 107.38
4413 Total 995.50 W
4414 Add 1 % Water charges on "W" 9.955
4415 TOTAL 1005.46 X
4416 Add GST (multiplying factor 0.1405) on "X" 141.27
4417 TOTAL 1146.73 Y
4418 Add 15 % Contractor's profit and overheads on "Y" 172.01
4419 Total 1318.74 Z
4420 Add Cess @ 1% on "Z" 13.19
4422 Total 1331.93
4423 Cost of 1 sqm 1331.93
4424 Say 1331.90
4425
4431
4432
4433
4434
4435 12.57 Providing and fixing thermal insulation with Resin
4436 Bonded Fibre glass wool conforming to IS: 8183 having
of Engineer-in-Charge.
4437 density 24 kg/m3, 50 mm thick, wrapped in 200G Virgin
Details of cost for 10 sqm
Polythene Bags fixed to wall with screw, rawel plug &
4438 MATERIAL
4439 Area for 10.00sqm. (Finished surface) =
4440 10.00sqm.+
4441 Add Wastage @ 10% =1.00 sqm
4442 Total =11.00sqm
4443 7232 Resin Bonded Glass wool 24 kg/m³ 50 mm sqm 11 143 1573.00
4444 thick
4445 9999 Sundries including GL wire 20 SWg and Virgin L.S. 52 2 104.00
4446 polythene bags 200 gram
4447 LABOUR
4448 14 Carpenter 1st class day 0.5 505.17 252.59
4449 17 Beldar day 0.5 350.00 175.00
4450 9999 Sundries (screws and washers) L.S. 20 2 40.00
4451 Total 2144.59 W
4452 Add 1 % Water charges on "W" 21.4459
4453 TOTAL 2166.04 X
4454 Add GST (multiplying factor 0.1405) on "X" 304.33
4455 TOTAL 2470.37 Y
4456 Add 15 % Contractor's profit and overheads on "Y" 370.55
4457 Total 2840.92 Z
4458 Add Cess @ 1% on "Z" 28.41
4459 Cost of 10 sqm 2869.33
4460 Cost of 1 sqm 286.93
4461 Say 286.90
4462
4474
4475 12.58 Providing and fixing tiled false ceiling of specified
4478 materials
12.58.1 of sizethick
8 mm 595x595
fullymm in true horizontal
perforated level, suspended
calcium silicate board made
on
with interlocking
Calcareousmetal grid of materials
& Siliceous hot dipped galvanized
reinforced steel
with sections
cellulose
4479 backing.
(fiber
galvanized
manufactured through autoclaving process to give stable of
@ 120 grams/ sqm, both side inclusive) consisting
4480 Details of cost for 100 sqm Ceiling area = 100 sq.m
crystalline structure with minimum compressive strength 225 kg/
4481 Add wastage @ 5% = 0.05 Sqm
4482 Total =100.05 Sq.m MATERIALS :
4483 8784 8mm thick Calcium silicate perforated tiles of sqm 100.05 833 83341.65
4484 size 595 x595mm
4485 8611 Main T ceiling sections 24x38x0.3 mm (3 each 29.5 115 3392.50
4486 metre long)
4487 8612 Perimeter wall angle 24x24x0.3mm (3 metre each 13.5 80 1080.00
4488 long)
4489 8613 Intermediate cross T-section 24x25x each 147 35 5145.00
4490 0.3mm (1.2 mtrs long)
4491 8614 Intermediate cross T-section 24x25x each 147 17 2499.00
4492 0.3mm (0.6 mtrs long)
4493 8615 Hanger rod 4 mm thick each 72 8 576.00
4494 8616 Adjustment clip 85x30x0.8mm each 72 5 360.00
4495 8617 Soffit cleat (Size 27x37x25x1.60mm) each 72 4 288.00
4496 7388 Dash hold fastener 12.5 mm dia, 40 mm long each 72 11 792.00
4497 with 6 mm dia bolt
4498 9977 Sundries L.S. 89.28 2 178.56
4499 9999 Sundries i.e scaffolding etc. L.S. 187.95 2 375.90
4508 LABOUR :
4509 14 Carpenter 1st class day 28 505.17 14144.76
4510 17 Beldar day 23 350.00 8050.00
4511 TOTAL 120223.37 W
4512 Add 1 % Water charges on "W" 1202.2337
4513 TOTAL 121425.60 X
4514 Add GST (multiplying factor 0.1405) on "X" 17060.30
4515 TOTAL 138485.90 Y
4516 Add 15 % Contractor's profit and overheads on "Y" 20772.89
4517 Total 159258.79 Z
4518 Add Cess @ 1% on "Z" 1592.59
4519 Cost of 100 sqm. 160851.38
4520 Cost of 1 sqm. 1608.51
4521 Say 1608.50
4522
4523
4524
4525 12.59 Providing & fixing false ceiling at all height including
4526 providing
12.59.1 & 8 fixing
mm thickof framework
Calcium made of special
Silicate Board section, power
made with
pressed from M.S. sheets and galvanised with zinc coating of 120
4527 Calcareous
process. & Siliceous materials reinforced with cellulose
gms/ sqm (both side inclusive) as per IS : 277 and consisting of
4529 fiber manufactured through autoclaving
Details of cost for 10.8 m x 9.6m = 103.68 sqmMATERIALS:Area = 103.68
sq.m + Add. Wastage of5% = 5.18 Sq.m Total =
4531 108.86 Sqm
4533 MATERIALS :
4543 8699 8 mm thick tapered edge calcium silicate sqm 108.86 400 43544.00
4544 board
4545 7010 G.I Ceiling Section (80 x26mm x26mm x metre 238.14 46 10954.44
4546 10.5mm each lip x 0.55 mm)
4547 7011 Galvanised Steel perimetre Channel (Size metre 41.84 22 920.48
4548 20x27x30x0.50mm)
4549 7012 Galvanised Steel intermediate Channel (Size metre 90.72 38 3447.36
4550 15x45x15x0.90mm)
4551 7013 Galvanised Steel angle hanger metre 10.8 12 129.60
4552 (Celling angle) (Size 25x10x0.50mm)
4553 7014 Galvanised Steel connecting clips each 189 4 756.00
4554 (2.64mm dia and 230 mm long GI wire)
4555 1022 Galvanised steel bolts & nuts 6 mm dia and 25 10 Nos 21.6 38 820.80
4556 mmlong round head with slots
4557 8617 Soffit cleat (Size 27x37x25x1.60mm) each 72 4 288.00
4558 7020 All drive screws ( for gypsum board) 100 Nos 10 58 580.00
4559 7016 Joint filler kilogram 22.81 26 593.06
4560 7017 Joint finisher kilogram 34.21 23 786.83
4561 7388 Dash hold fastener 12.5 mm dia, 40 mm long each 72 11 792.00
4562 with 6 mm dia bolt
4563 7018 Joint Tape roll (120mm Roll) roll 1.27 100 127.00
4564 7021 Primer ( for gypsum board// calcium silicate litre 18.66 85 1586.10
4565 board)
4566 9977 Carriage L.S. 447.2 2 894.40
4567 9999 Sundries i.e rawl plug, scaffolding etc. L.S. 807.3 2 1614.60
4568 LABOUR :
4569 15 Carpenter 2nd class day 31.1 403.67 12554.14
4570 17 Beldar day 31.1 350.00 10885.00
4571 31 Painter day 10.37 403.67 4186.06
4572 TOTAL 95459.87 W
4573 Add 1 % Water charges on "W" 954.5987
4574 TOTAL 96414.47 X
4575 Add GST (multiplying factor 0.1405) on "X" 13546.23
4576 TOTAL 109960.70 Y
4577 Add 15 % Contractor's profit and overheads on "Y" 16494.10
4578 Total 126454.80 Z
4579 Add Cess @ 1% on "Z" 1264.55
4580 Cost of 103.68 sqm. 127719.35
4581 Cost of 1 sqm. 1231.86
4582 Say 1231.90
4583
4597
4598
4599
4600
4601 12.60 Providing and fixing thermal insulation of ceiling
4602 (under
mesh, fordecktopinsulation) with
most ceiling ofResin Bonded Rockwool
building.
4603 conforming to IS: 8183,density 48 kg/
Details of cost for 10 sqm Area for 10.00 sqm.
m3, 50 mm thick,
wrapped in 200 G Virgin Polythene bags fixed to ceiling with
4604 (Finished surface)=10.00sqm.+ Add 10% for
4605 ovelappings &wastage= 1.00sqm. Total=
4606 11.00sqm
4607 7273 Resin Bonded Rockwool 48 kg/m3 sqm 11 120 1320.00
4608 9999 Sundries including GI wire 20 SWG and L.S. 104 2 208.00
4609 polythene bags 200gms
4610 9999 GI chiken mesh 12.5mm x 24 SWG L.S. 351 2 702.00
4611 LABOUR
4612 14 Carpenter 1st class day 1 505.17 505.17
4613 17 Beldar day 2 350.00 700.00
4614 TOTAL 3435.17 W
4615 Add 1 % Water charges on "W" 34.3517
4616 TOTAL 3469.52 X
4617 Add GST (multiplying factor 0.1405) on "X" 487.47
4618 TOTAL 3956.99 Y
4619 Add 15 % Contractor's profit and overheads on "Y" 593.55
4620 Total 4550.54 Z
4621 Add Cess @ 1% on "Z" 45.51
4622 Cost of 10 sqm. 4596.05
4623 Cost of 1 sqm. 459.61
4624 Say 459.60
4625
4626
4627
4628 12.61 Providing and fixing thermal insulation with Resin
4629 bonded rock wool
crisscrossing conforming to IS: 8183, density 48 kg/m3,
Gl wire.
4630 50 mm thick, wrapped
Details of cost for 10 sqm
in 200 G virgin Polythene bags placed
over existing false ceilng and held in position by
4631
4632 Area for 10.00sqm. (Finished
4633 surface)=10.00sqm.+ Add 10% for
4634 ovelappings &wastage= 1.00sqm. Total=
4635 11.00sqm
4636 7273 Resin Bonded Rockwool 48 kg/m3 sqm 11 120 1320.00
4637 9999 Sundries including GI wire 20 SWG and L.S. 52 2 104.00
4638 polythene bags 200gms
4639 LABOUR
4640 14 Carpenter 1st class day 0.5 505.17 252.59
4641 17 Beldar day 0.5 350.00 175.00
4642 TOTAL 1851.59 W
4643 Add 1 % Water charges on "W" 18.5159
4644 TOTAL 1870.11 X
4645 Add GST (multiplying factor 0.1405) on "X" 262.75
4646 TOTAL 2132.86 Y
4647 Add 15 % Contractor's profit and overheads on "Y" 319.93
4648 Total 2452.79 Z
4649 Add Cess @ 1% on "Z" 24.53
4651 Cost of 10 sqm. 2477.32
4652 Cost of 1 sqm. 247.73
4653 Say 247.70
4654
4661
4662
4663
4664
4665 12.62 Providing and fixing thermal insulation with Resin
4666 Bonded rock wool conforming to IS: 8183, having density 48
of Engineer-in-Charge.
4667 kg/m3,50 mm thick,wrapped in 200 G Virgin Polythene Bags
Details of cost for 10 sqm
fixed to wall wirh screw, rawel plug & washers and held and
4668 Area for 10.00sqm. (Finished
4669 surface)=10.00sqm.+ Add 10% for
4670 ovelappings &wastage= 1.00sqm. Total=
4671 11.00sqm
4672 7273 Resin Bonded Rockwool 48 kg/m3 sqm 11 120 1320.00
4673 9999 Sundries including GI wire 20 SWG and L.S. 52 2 104.00
4674 Virgin polythene bags 200 gram and Carriage
4675 LABOUR
4676 14 Carpenter 1st class fay 0.5 505.17 252.59
4677 17 Beldar fay 0.5 350.00 175.00
4678 9999 Sundries (screws & washers) L.S. 20 2 40.00
4679 TOTAL 1891.59 W
4680 Add 1 % Water charges on "W" 18.9159
4681 TOTAL 1910.51 X
4682 Add GST (multiplying factor 0.1405) on "X" 268.43
4683 TOTAL 2178.94 Y
4684 Add 15 % Contractor's profit and overheads on "Y" 326.84
4685 Total 2505.78 Z
4686 Add Cess @ 1% on "Z" 25.06
4687 Cost of 10 sqm. 2530.84
4688 Cost of 1 sqm. 253.08
4689 Say 253.10
4690
4703
4705
4706 12.63 Providing and applying two coats of High Albedo
4707 paint having minimum Solar Reflective Index (SRI) 108 (with
4708 solar reflectance & thermal emittance tested as per ASTM) C
Details of cost for 10 Sqm. MATERIALS :
1549 and ASTM C 1371 respectively), VOC less than 10
4709 7238 High Albedo paint kg 7.17 230 1649.10
4710 9977 Carriage of paint L.S. 4.53 2 9.06
4711 LABOUR :
4712 17 Beldar (for cleanign the surface) day 0.54 350.00 189.00
4713 31 Painter day 0.54 403.67 217.98
4714 9999 Sundries (Brushes & T&P etc. L.S. 13.52 2 27.04
4715 MACHINERY : TOTAL 2092.18 W
4716 Add 1 % Water charges on "W" 20.9218
4717 TOTAL 2113.10 X
4718 Add GST (multiplying factor 0.1405) on "X" 296.89
4719 TOTAL 2409.99 Y
4720 Add 15 % Contractor's profit and overheads on "Y" 361.50
4721 Total 2771.49 Z
4722 Add Cess @ 1% on "Z" 27.71
4723 Cost of 10 sqm. 2799.20
4724 Cost of 1 sqm. 279.92
4725 Say 279.90
4726
4727
4747

4749
4750
4751
4752
4753
SUB HEAD : 13.0
4754
FINISHING
4756
4757
4758
4759
4760 13.1 12 mm cement plaster of mix :
4761 13.1.1 1:4 (1 cement: 4 fine sand)
4762 Detail of cost for 10 sqm
4763 MATERIAL
4764 Cement mortar 1 : 4 (1 cement : 4 fine sand)
4765 3.4 Rate as per Item Number 3.4 of SH: Mortars cum 0.144 3089.3 444.86
4766 LABOUR
4767 40 Mason (average) day 0.67 403.67 270.46
4768 18 Coolie day 0.75 350.00 262.50
4769 11 Bhisti day 0.92 350.00 322.00
4770 9999 Scaffolding and sundries L.S. 12.61 2 25.22
4771 TOTAL 1325.04 W
4772 Add 1 % Water charges on "W" 13.2504
4773 TOTAL 1338.29 X
4774 Add GST (multiplying factor 0.1405) on "X" 188.03
4775 TOTAL 1526.32 Y
4776 Add 15 % Contractor's profit and overheads on "Y" 228.95
4777 Total 1755.27 Z
4778 Add Cess @ 1% on "Z" 17.55
4779 Cost of 10.00 sqm 1772.82
4780 Cost of 1.00 sqm 177.28
4781 Say 177.30
4782
4783
4784 13.1.2 1:6 (1 cement: 6 fine sand)
4785 Detail of cost for 10 sqm
4786 MATERIAL
4787 Cement mortar 1 : 6 (1 cement : 6 fine sand)
4788 3.6 Rate as per Item Number 3.6 of SH: Mortars cum 0.144 2508.3 361.20
4789 LABOUR
4790 40 Mason (average) day 0.67 403.67 270.46
4791 18 Coolie day 0.75 350.00 262.50
4792 11 Bhisti day 0.92 350.00 322.00
4793 9999 Scaffolding and sundries L.S. 12.61 2 25.22
4794 TOTAL 1241.38 W
4795 Add 1 % Water charges on "W" 12.4138
4796 TOTAL 1253.79 X
4797 Add GST (multiplying factor 0.1405) on "X" 176.16
4798 TOTAL 1429.95 Y
4799 Add 15 % Contractor's profit and overheads on "Y" 214.49
4800 Total 1644.44 Z
4801 Add Cess @ 1% on "Z" 16.44
4802 Cost of 10.00 sqm 1660.88
4803 Cost of 1.00 sqm 166.09
4804 Say 166.10
4805
4813
4814
4815
4816
4817 13.2 15 mm cement plaster on the rough side of single or
4818 half
13.2.1 1:4wall
brick of mix : 4 fine sand)
(1 cement:
4819 Detail of cost for 10 sqm
4820 MATERIAL
4821 Cement mortar 1 : 4 (1 cement : 4 fine sand)
4822 3.4 Rate as per Item Number 3.4 of SH: Mortars cum 0.172 3089.3 531.36
4823 LABOUR
4824 40 Mason (average) day 0.8 403.67 322.94
4825 18 Coolie day 0.88 350.00 308.00
4826 11 Bhisti day 0.99 350.00 346.50
4827 9999 Scaffolding and sundries L.S. 12.61 2 25.22
4828 TOTAL 1534.02 W
4829 Add 1 % Water charges on "W" 15.3402
4830 TOTAL 1549.36 X
4831 Add GST (multiplying factor 0.1405) on "X" 217.69
4832 TOTAL 1767.05 Y
4833 Add 15 % Contractor's profit and overheads on "Y" 265.06
4834 Total 2032.11 Z
4835 Add Cess @ 1% on "Z" 20.32
4836 Cost of 10.00 sqm 2052.43
4837 Cost of 1.00 sqm 205.24
4838 Say 205.20
4839
4840
4841 13.2.2 1:6 (1 cement: 6 fine sand)
4842 Detail of cost for 10 sqm
4843 MATERIAL
4844 Cement mortar 1 : 6 (1 cement : 6 fine sand)
4845 3.6 Rate as per Item Number 3.6 of SH: Mortars cum 0.172 2508.3 431.43
4846 LABOUR
4847 40 Mason (average) day 0.8 403.67 322.94
4856 18 Coolie day 0.88 350.00 308.00
4857 11 Bhisti day 0.99 350.00 346.50
4858 9999 Scaffolding and sundries L.S. 12.61 2 25.22
4859 TOTAL 1434.09 W
4860 Add 1 % Water charges on "W" 14.3409
4861 TOTAL 1448.43 X
4862 Add GST (multiplying factor 0.1405) on "X" 203.50
4863 TOTAL 1651.93 Y
4864 Add 15 % Contractor's profit and overheads on "Y" 247.79
4865 Total 1899.72 Z
4866 Add Cess @ 1% on "Z" 19.00
4867 Cost of 10.00 sqm 1918.72
4868 Cost of 1.00 sqm 191.87
4869 Say 191.90
4870
4871
4872
4873 13.3 20 mm cement plaster of mix :
4874 13.3.1 1:4 (1 cement: 4 fine sand)
4875 Detail of cost for 10 sqm
4876 MATERIAL
4877 Cement mortar 1 : 4 (1 cement : 4 fine sand)
4878 3.4 Rate as per Item Number 3.4 of SH: Mortars cum 0.224 3089.3 692.00
4879 LABOUR
4880 40 Mason (average) day 0.94 403.67 379.45
4881 18 Coolie day 1.02 350.00 357.00
4882 11 Bhisti day 1.1 350.00 385.00
4883 9999 Scaffolding and sundries L.S. 12.61 2 25.22
4884 TOTAL 1838.67 W
4885 Add 1 % Water charges on "W" 18.3867
4886 TOTAL 1857.06 X
4887 Add GST (multiplying factor 0.1405) on "X" 260.92
4888 TOTAL 2117.98 Y
4889 Add 15 % Contractor's profit and overheads on "Y" 317.70
4890 Total 2435.68 Z
4891 Add Cess @ 1% on "Z" 24.36
4892 Cost of 10.00 sqm 2460.04
4893 Cost of 1.00 sqm 246
4894 Say 246.00
4895
4905
4906
4907 13.3.2 1:6 (1 cement: 6 fine sand)
4908 Detail of cost for 10 sqm
4909 MATERIAL
4910 Cement mortar 1 : 6 (1 cement : 6 fine sand)
4911 3.6 Rate as per Item Number 3.6 of SH: Mortars cum 0.224 2508.3 561.86
4912 LABOUR
4913 40 Mason (average) day 0.94 403.67 379.45
4914 18 Coolie day 1.02 350.00 357.00
4915 11 Bhisti day 1.1 350.00 385.00
4916 9999 Scaffolding and sundries L.S. 12.61 2 25.22
4917 TOTAL 1708.53 W
4918 Add 1 % Water charges on "W" 17.0853
4919 TOTAL 1725.62 X
4920 Add GST (multiplying factor 0.1405) on "X" 242.45
4921 TOTAL 1968.07 Y
4922 Add 15 % Contractor's profit and overheads on "Y" 295.21
4923 Total 2263.28 Z
4924 Add Cess @ 1% on "Z" 22.63
4925 Cost of 10.00 sqm 2285.91
4926 Cost of 1.00 sqm 228.59
4927 Say 228.60
4928
4929
4930
4931 13.4 12 mm cement plaster of mix :
4932 13.4.1 1:4 (1 cement: 4 coarse sand)
4933 Detail of cost for 10 sqm
4934 MATERIAL
4935 Cement mortar 1 : 4 (1 cement : 4 coarse sand)
4936 3.9 Rate as per Item Number 3.9 of SH: Mortars cum 0.144 3548.00 510.91
4937 LABOUR
4938 40 Mason (average) day 0.67 403.67 270.46
4939 18 Coolie day 0.75 350.00 262.50
4940 11 Bhisti day 0.92 350.00 322.00
4941 9999 Scaffolding and sundries L.S. 12.61 2 25.22
4942 TOTAL 1391.09 W
4943 Add 1 % Water charges on "W" 13.9109
4944 TOTAL 1405.00 X
4945 Add GST (multiplying factor 0.1405) on "X" 197.40
4946 TOTAL 1602.40 Y
4947 Add 15 % Contractor's profit and overheads on "Y" 240.36
4948 Total 1842.76 Z
4949 Add Cess @ 1% on "Z" 18.43
4950 Cost of 10.00 sqm 1861.19
4951 Cost of 1.00 sqm 186.12
4952 Say 186.10
4954
4955
4961
4962 13.4.2 1:6 (1 cement: 6 coarse sand)
4963 Detail of cost for 10 sqm
4964 MATERIAL
4965 Cement mortar 1 : 6 (1 cement : 6 coarse sand)
4966 3.11 Rate as per Item Number 3.11 of SH: Mortars cum 0.144 2967.00 427.25
4967 LABOUR
4968 40 Mason (average) day 0.67 403.67 270.46
4969 18 Coolie day 0.75 350.00 262.50
4970 11 Bhisti day 0.92 350.00 322.00
4971 9999 Scaffolding and sundries L.S. 12.61 2 25.22
4972 TOTAL 1307.43 W
4973 Add 1 % Water charges on "W" 13.0743
4974 TOTAL 1320.50 X
4975 Add GST (multiplying factor 0.1405) on "X" 185.53
4976 TOTAL 1506.03 Y
4977 Add 15 % Contractor's profit and overheads on "Y" 225.91
4978 Total 1731.94 Z
4979 Add Cess @ 1% on "Z" 17.32
4980 Cost of 10.00 sqm 1749.26
4981 Cost of 1.00 sqm 174.93
4982 Say 174.90
4983
4984
4985
4986
4987 13.5 15 mm cement plaster on rough side of single or half
4988 brick
13.5.1 1:4of(1mix:
wall cement: 4 coarse sand)
4989 Detail of cost for 10 sqm
4990 MATERIAL
4991
4992 Cement mortar 1 : 4 (1 cement : 4 coarse sand)
4993
4994 3.9 Rate as per Item Number 3.9 of cum 0.172 3548.00 610.26
5004 SH: Mortars
5005 LABOUR
5006 40 Mason (average) day 0.8 403.67 322.94
5007 18 Coolie day 0.88 350.00 308.00
5008 11 Bhisti day 0.99 350.00 346.50
5009 9999 Scaffolding and sundries L.S. 12.61 2 25.22
5010 TOTAL 1612.92 W
5011 Add 1 % Water charges on "W" 16.1292
5012 TOTAL 1629.05 X
5013 Add GST (multiplying factor 0.1405) on "X" 228.88
5014 TOTAL 1857.93 Y
5015 Add 15 % Contractor's profit and overheads on "Y" 278.69
5016 Total 2136.62 Z
5017 Add Cess @ 1% on "Z" 21.37
5018 Cost of 10.00 sqm 2157.99
5019 Cost of 1.00 sqm 215.8
5020 Say 215.80
5021
5022
5023 13.5.2 1:6 (1 cement: 6 coarse sand)
5024 Detail of cost for 10 sqm
5025 MATERIAL
5026 Cement mortar 1 : 6 (1 cement : 6 coarse sand)
5027 3.11 Rate as per Item Number 3.11 of SH: Mortars cum 0.172 2967.00 510.32
5028 LABOUR
5029 40 Mason (average) day 0.8 403.67 322.94
5030 18 Coolie day 0.88 350.00 308.00
5031 11 Bhisti day 0.99 350.00 346.50
5032 9999 Scaffolding and sundries L.S. 12.61 2 25.22
5033 TOTAL 1512.98 W
5034 Add 1 % Water charges on "W" 15.1298
5035 TOTAL 1528.11 X
5036 Add GST (multiplying factor 0.1405) on "X" 214.70
5037 TOTAL 1742.81 Y
5038 Add 15 % Contractor's profit and overheads on "Y" 261.42
5039 Total 2004.23 Z
5040 Add Cess @ 1% on "Z" 20.04
5041 Cost of 10.00 sqm 2024.27
5042 Cost of 1.00 sqm Say 202.43
5043 202.40
5044
5058
5059
5060
5061 13.6 20 mm cement plaster of mix :
5062 13.6.1 1:4 (1 cement: 4 coarse sand)
5063 Detail of cost for 10 sqm
5064 MATERIAL
5065 Cement mortar 1 : 4 (1 cement : 4 coarse sand)
5066 3.9 Rate as per Item Number 3.9 of SH: Mortars cum 0.224 3548.00 794.75
5067 LABOUR
5068 40 Mason (average) day 0.94 403.67 379.45
5069 18 Coolie day 1.02 350.00 357.00
5070 11 Bhisti day 1.1 350.00 385.00
5071 9999 Scaffolding and sundries L.S. 12.61 2 25.22
5072 TOTAL 1941.42 W
5073 Add 1 % Water charges on "W" 19.4142
5074 TOTAL 1960.83 X
5075 Add GST (multiplying factor 0.1405) on "X" 275.50
5076 TOTAL 2236.33 Y
5077 Add 15 % Contractor's profit and overheads on "Y" 335.45
5078 Total 2571.78 Z
5079 Add Cess @ 1% on "Z" 25.72
5080 Cost of 10.00 sqm 2597.50
5081 Cost of 1.00 sqm 259.75
5082 Say 259.80
5083
5084
5085 13.6.2 1:6 (1 cement: 6 coarse sand)
5086 Detail of cost for 10 sqm
5087 MATERIAL
5088 Cement mortar 1 : 6 (1 cement : 6 coarse sand)
5089 3.11 Rate as per Item Number 3.11 of SH: Mortars cum 0.224 2967.00 664.61
5090 LABOUR
5091 40 Mason (average) day 0.94 403.67 379.45
5092 18 Coolie day 1.02 350.00 357.00
5093 11 Bhisti day 1.1 350.00 385.00
5094 9999 Scaffolding and sundries L.S. 12.61 2 25.22
5095 TOTAL 1811.28 W
5096 Add 1 % Water charges on "W" 18.1128
5097 TOTAL 1829.39 X
5098 Add GST (multiplying factor 0.1405) on "X" 257.03
5099 TOTAL 2086.42 Y
5100 Add 15 % Contractor's profit and overheads on "Y" 312.96
5101 Total 2399.38 Z
5102 Add Cess @ 1% on "Z" 23.99
5103 Cost of 10.00 sqm 2423.37
5104 Cost of 1.00 sqm 242.34
5105 Say 242.30
5107
5108
5115
5116
5117
5118 13.7 12 mm cement plaster finished with a floating coat of
5119 neat
13.7.1 1:3 (1of
cement mix : 3 fine sand)
cement:
5120 Detail of cost for 10 sqm
5121 MATERIAL
5122 Cement mortar 1 : 3 (1 cement : 3 fine sand)
5123 3.3 Rate as per Item Number 3.3 of SH: Mortars cum 0.144 3670.3 528.52
5124 LABOUR
5125 40 Mason (average) day 0.67 403.67 270.46
5126 18 Coolie day 0.75 350.00 262.50
5127 11 Bhisti day 0.92 350.00 322.00
5128 9999 Scaffolding and sundries L.S. 12.61 2 25.22
5129 367 Portland Cement (OPC-43 grade) tonne 0.02 4375 87.50
5130 2209 Carriage of Cement tonne 0.02 94.34 1.89
5131 40 Mason (average) day 0.27 403.67 108.99
5132 18 Coolie day 0.27 350.00 94.50
5133 9999 Scaffolding and sundries L.S. 8.06 2 16.12
5134 TOTAL 1717.70 W
5135 Add 1 % Water charges on "W" 17.177
5136 TOTAL 1734.88 X
5137 Add GST (multiplying factor 0.1405) on "X" 243.75
5138 TOTAL 1978.63 Y
5139 Add 15 % Contractor's profit and overheads on "Y" 296.79
5140 Total 2275.42 Z
5141 Add Cess @ 1% on "Z" 22.75
5142 Cost of 10.00 sqm 2298.17
5143 Cost of 1.00 sqm 229.82
5144 Say 229.80
5145
5146
5147
5148
5149 13.7.2 1:4 (1 cement: 4 fine sand)
5150 Detail of cost for 10 sqm
5151 MATERIAL
5152 Cement mortar 1 : 4 (1 cement : 4 fine sand)
5162 3.4 Rate as per Item Number 3.4 of SH: Mortars cum 0.144 3089.3 444.86
5163 LABOUR
5164 40 Mason (average) day 0.67 403.67 270.46
5165 18 Coolie day 0.75 350.00 262.50
5166 11 Bhisti day 0.92 350.00 322.00
5167 9999 Scaffolding and sundries L.S. 12.61 2 25.22
5168 367 Portland Cement (OPC-43 grade) tonne 0.02 4375 87.50
5169 2209 Carriage of Cement tonne 0.02 94.34 1.89
5170 40 Mason (average) day 0.27 403.67 108.99
5171 18 Coolie day 0.27 350.00 94.50
5172 9999 Scaffolding and sundries L.S. 8.06 2 16.12
5173 TOTAL 1634.04 W
5174 Add 1 % Water charges on "W" 16.3404
5175 TOTAL 1650.38 X
5176 Add GST (multiplying factor 0.1405) on "X" 231.88
5177 TOTAL 1882.26 Y
5178 Add 15 % Contractor's profit and overheads on "Y" 282.34
5179 Total 2164.60 Z
5180 Add Cess @ 1% on "Z" 21.65
5181 Cost of 10.00 sqm 2186.25
5182 Cost of 1.00 sqm 218.63
5183 Say 218.60
5184
5185
5186
5187 13.8 15 mm cement plaster on rough side of single or half
5188 brick
13.8.1 1:3finished
wall with3afine
(1 cement: floating
sand)coat of neat cement of mix :
5189 Detail of cost for 10 sqm
5190 MATERIAL
5191 Cement mortar 1 : 3 (1 cement : 3 fine sand)
5192 3.3 Rate as per Item Number 3.3 of SH: Mortars cum 0.172 3670.3 631.29
5193 LABOUR
5194 40 Mason (average) day 0.8 403.67 322.94
5195 18 Coolie day 0.88 350.00 308.00
5196 11 Bhisti day 0.99 350.00 346.50
5197 9999 Scaffolding and sundries L.S. 12.61 2 25.22
5198 367 Portland Cement (OPC-43 grade) tonne 0.02 4375 87.50
5199 2209 Carriage of Cement tonne 0.02 94.34 1.89
5200 40 Mason (average) day 0.27 403.67 108.99
5201 18 Coolie day 0.27 350.00 94.50
5202 9999 Scaffolding and sundries L.S. 8.06 2 16.12
5203 TOTAL 1942.95 W
5204 Add 1 % Water charges on "W" 19.4295
5205 TOTAL 1962.38 X
5206 Add GST (multiplying factor 0.1405) on "X" 275.71
5207 TOTAL 2238.09 Y
5208 Add 15 % Contractor's profit and overheads on "Y" 335.71
5209 Total 2573.80 Z
5210 Add Cess @ 1% on "Z" 25.74
5212 Cost of 10.00 sqm 2599.54
5213 Cost of 1.00 sqm 259.95
5214 Say 260.00

5221
5222 13.8.2 1:4 (1 cement: 4 fine sand)
5223 Detail of cost for 10 sqm
5224 MATERIAL
5225 Cement mortar 1 : 4 (1 cement : 4 fine sand)
5226 3.4 Rate as per Item Number 3.4 of SH: Mortars cum 0.172 3089.3 531.36
5227 LABOUR
5228 40 Mason (average) day 0.8 403.67 322.94
5229 18 Coolie day 0.88 350.00 308.00
5230 11 Bhisti day 0.99 350.00 346.50
5231 9999 Scaffolding and sundries L.S. 12.61 2 25.22
5232 367 Portland Cement (OPC-43 grade) tonne 0.02 4375 87.50
5233 2209 Carriage of Cement tonne 0.02 94.34 1.89
5234 40 Mason (average) day 0.27 403.67 108.99
5235 18 Coolie day 0.27 350.00 94.50
5236 9999 Scaffolding and sundries L.S. 8.06 2 16.12
5237 TOTAL 1843.02 W
5238 Add 1 % Water charges on "W" 18.4302
5239 TOTAL 1861.45 X
5240 Add GST (multiplying factor 0.1405) on "X" 261.53
5241 TOTAL 2122.98 Y
5242 Add 15 % Contractor's profit and overheads on "Y" 318.45
5243 Total 2441.43 Z
5244 Add Cess @ 1% on "Z" 24.41
5245 Cost of 10.00 sqm 2465.84
5246 Cost of 1.00 sqm 246.58
5247 Say 246.60
5248
5259
5260
5261 13.9 Cement plaster 1:3 (1 cement: 3 coarse sand) finished
5262 with
neat cement. coat of
a floating
5263 13.9.1 12 mm cement plaster
5264 Detail of cost for 10 sqm
5265 MATERIAL
5266 Cement mortar 1:3 (1 cement : 3 coarse sand)
5267 3.8 Rate as per Item Number 3.8 of SH: Mortars cum 0.144 4129.00 594.58
5268 LABOUR
5269 40 Mason (average) day 0.67 403.67 270.46
5270 18 Coolie day 0.75 350.00 262.50
5271 11 Bhisti day 0.92 350.00 322.00
5272 9999 Scaffolding and sundries L.S. 12.61 2 25.22
5273 367 Portland Cement (OPC-43 grade) tonne 0.02 4375 87.50
5274 2209 Carriage of Cement tonne 0.02 94.34 1.89
5275 40 Mason (average) day 0.27 403.67 108.99
5276 18 Coolie day 0.27 350.00 94.50
5277 9999 Scaffolding and sundries L.S. 8.06 2 16.12
5278 TOTAL 1783.76 W
5279 Add 1 % Water charges on "W" 17.8376
5280 TOTAL 1801.60 X
5281 Add GST (multiplying factor 0.1405) on "X" 253.12
5282 TOTAL 2054.72 Y
5283 Add 15 % Contractor's profit and overheads on "Y" 308.21
5284 Total 2362.93 Z
5285 Add Cess @ 1% on "Z" 23.63
5286 Cost of 10.00 sqm 2386.56
5287 Cost of 1.00 sqm 238.66
5288 Say 238.70
5289
5290
5291 13.9.2 20 mm cement plaster
5292 Detail of cost for 10 sqm
5293 MATERIAL
5294 Cement mortar 1:3 (1 cement : 3 coarse sand)
5295 3.8 Rate as per Item Number 3.8 of SH: Mortars cum 0.224 4129.00 924.90
5296 LABOUR
5297 40 Mason (average) day 0.94 403.67 379.45
5298 18 Coolie day 1.02 350.00 357.00
5299 11 Bhisti day 1.1 350.00 385.00
5300 9999 Scaffolding and sundries L.S. 12.61 2 25.22
5301 367 Portland Cement (OPC-43 grade) tonne 0.02 4375 87.50
5302 2209 Carriage of Cement tonne 0.02 94.34 1.89
5303 40 Mason (average) day 0.27 403.67 108.99
5314 18 Coolie day 0.27 350.00 94.50
5315 9999 Scaffolding and sundries L.S. 8.06 2 16.12
5316 TOTAL 2380.57 W
5317 Add 1 % Water charges on "W" 23.8057
5318 TOTAL 2404.38 X
5319 Add GST (multiplying factor 0.1405) on "X" 337.81
5320 TOTAL 2742.19 Y
5321 Add 15 % Contractor's profit and overheads on "Y" 411.33
5322 Total 3153.52 Z
5323 Add Cess @ 1% on "Z" 31.54
5324 Cost of 10.00 sqm 3185.06
5325 Cost of 1.00 sqm 318.51
5326 Say 318.50
5327
5328
5329 13.10 15 mm cement plaster 1:3 (1 cement: 3 coarse sand)
5330 finished
Detail with
of cost fora10floating
sqm coat of neat cement on the rough side
5331 of single
MATERIAL
or half brick wall.
5332 Cement mortar 1:3 (1 cement : 3 coarse sand)
5333 3.8 Rate as per Item Number 3.8 of SH: Mortars cum 0.172 4129.00 710.19
5334 LABOUR
5335 40 Mason (average) day 0.8 403.67 322.94
5336 18 Coolie day 0.88 350.00 308.00
5337 11 Bhisti day 0.99 350.00 346.50
5338 9999 Scaffolding and sundries L.S. 12.61 2 25.22
5339 367 Portland Cement (OPC-43 grade) tonne 0.02 4375 87.50
5340 2209 Carriage of Cement tonne 0.02 94.34 1.89
5341 40 Mason (average) day 0.27 403.67 108.99
5342 18 Coolie day 0.27 350.00 94.50
5343 9999 Scaffolding and sundries L.S. 8.06 2 16.12
5344 TOTAL 2021.85 W
5345 Add 1 % Water charges on "W" 20.2185
5346 TOTAL 2042.07 X
5347 Add GST (multiplying factor 0.1405) on "X" 286.91
5348 TOTAL 2328.98 Y
5349 Add 15 % Contractor's profit and overheads on "Y" 349.35
5350 Total 2678.33 Z
5351 Add Cess @ 1% on "Z" 26.78
5352 Cost of 10.00 sqm 2705.11
5353 Cost of 1.00 sqm 270.51
5354 Say 270.50
5355
5364
5365
5366
5367 13.11 18 mm cement plaster in two coats under layer 12 mm
5368 thick
plaster 1:6 (1 plaster
cement cement1:5
: 6 (1 cement
fine sand).: 5 coarse sand) finished
5369 with a top layer 6 mm thick cement
5370 Detail of cost for 10 sqm
5371
5372 MATERIAL
5373 Under layer Cement mortar
5374 1 : 5 (1 cement : 5 coarse sand)
5375 3.10 Rate as per Item Number 3.10 of SH: Mortars cum 0.144 3235.20 465.87
5376 Top layer Cement mortar 1 : 6
5377 (1 cement : 6 fine sand)
5378 3.6 Rate as per Item Number 3.6 of SH: Mortars cum 0.072 2508.3 180.60
5379 LABOUR
5380 40 Mason (average) day 1.21 403.67 488.44
5381 18 Coolie day 1.29 350.00 451.50
5382 11 Bhisti day 1.05 350.00 367.50
5383 9999 Scaffolding and sundries L.S. 12.61 2 25.22
5384 TOTAL 1979.13 W
5385 Add 1 % Water charges on "W" 19.7913
5386 TOTAL 1998.92 X
5387 Add GST (multiplying factor 0.1405) on "X" 280.85
5388 TOTAL 2279.77 Y
5389 Add 15 % Contractor's profit and overheads on "Y" 341.97
5390 Total 2621.74 Z
5391 Add Cess @ 1% on "Z" 26.22
5392 Cost of 10.00 sqm 2647.96
5393 Cost of 1.00 sqm 264.8
5394 Say 264.80
5395
5396
5397
5398 13.12 18 mm cement plaster in two coats under layer 12 mm
5399 thick of
Detail cement
cost forplaster
10 sqm 1:5 (1 cement : 5 coarse sand) and a top
5400 layer 6
MATERIAL
mm thick cement plaster 1:3 (1 cement : 3 coarse
sand) finished rough with sponge.
5401 Under layer Cement mortar 1 : 5
5402 (1 cement : 5 coarse sand)
5403 3.10 Rate as per Item Number 3.10 of SH: Mortars cum 0.144 3235.20 465.87
5414 Top layer Cement mortar 1:3
5415 (1 cement : 3 coarse sand)
5416 3.8 Rate as per Item Number 3.8 of SH: Mortars cum 0.072 4129.00 297.29
5417 LABOUR
5418 40 Mason (average) day 1.21 403.67 488.44
5419 18 Coolie day 1.29 350.00 451.50
5420 11 Bhisti day 1.05 350.00 367.50
5421 9999 Scaffolding and sundries L.S. 12.61 2 25.22
5422 TOTAL 2095.82 W
5423 Add 1 % Water charges on "W" 20.9582
5424 TOTAL 2116.78 X
5425 Add GST (multiplying factor 0.1405) on "X" 297.41
5426 TOTAL 2414.19 Y
5427 Add 15 % Contractor's profit and overheads on "Y" 362.13
5428 Total 2776.32 Z
5429 Add Cess @ 1% on "Z" 27.76
5430 Cost of 10.00 sqm 2804.08
5431 Cost of 1.00 sqm 280.41
5432 Say 280.40
5433
5434
5435 13.13 12 mm cement plaster 1:2 (1 cement : 2 stone dust).
5436 Detail of cost for 10 sqm
5437 MATERIAL
5438 Cement mortar 1:2 (1 Cement : 2 stone dust)
5439 3.12 Rate as per Item Number 3.12 of SH: Mortars cum 0.144 4552.80 655.60
5440 LABOUR
5441 40 Mason (average) day 0.67 403.67 270.46
5442 18 Coolie day 0.75 350.00 262.50
5443 11 Bhisti day 0.92 350.00 322.00
5444 9999 Scaffolding and sundries L.S. 12.61 2 25.22
5445 TOTAL 1535.78 W
5446 Add 1 % Water charges on "W" 15.3578
5447 TOTAL 1551.14 X
5448 Add GST (multiplying factor 0.1405) on "X" 217.93
5449 TOTAL 1769.07 Y
5450 Add 15 % Contractor's profit and overheads on "Y" 265.36
5451 Total 2034.43 Z
5452 Add Cess @ 1% on "Z" 20.34
5453 Cost of 10.00 sqm 2054.77
5454 Cost of 1.00 sqm 205.48
5455 Say 205.50
5456
5464
5465
5466
5467 13.14 15 mm cement plaster 1:2 (1 cement : 2 stone dust) on
the rough side of
5468 single or half brick wall.
5469
5470 Detail of cost for 10 sqm
5471 MATERIAL
5472 Cement mortar 1:2 (1 Cement : 2 stone dust)
5473 3.12 Rate as per Item Number 3.12 of SH: Mortars cum 0.172 5102.5 877.63
5474 LABOUR
5475 40 Mason (average) day 0.8 403.67 322.94
5476 18 Coolie day 0.88 350.00 308.00
5477 11 Bhisti day 0.99 350.00 346.50
5478 9999 Scaffolding and sundries L.S. 12.61 2 25.22
5479 TOTAL 1880.29 W
5480 Add 1 % Water charges on "W" 18.8029
5481 TOTAL 1899.09 X
5482 Add GST (multiplying factor 0.1405) on "X" 266.82
5483 TOTAL 2165.91 Y
5484 Add 15 % Contractor's profit and overheads on "Y" 324.89
5485 Total 2490.80 Z
5486 Add Cess @ 1% on "Z" 24.91
5487 Cost of 10.00 sqm 2515.71
5488 Cost of 1.00 sqm 251.57
5489 Say 251.60
5490
5491
5492 13.15 20 mm cement plaster 1:2 (1 cement : 2 stone dust).
5493 Detail of cost for 10 sqm
5494 MATERIAL
5495 Cement mortar 1:2 (1 Cement : 2 stone dust)
5496 3.12 Rate as per Item Number 3.12 of SH: Mortars cum 0.224 4552.80 1019.83
5497 LABOUR
5498 40 Mason (average) day 0.94 403.67 379.45
5499 18 Coolie day 1.02 350.00 357.00
5500 11 Bhisti day 1.1 350.00 385.00
5501 9999 Scaffolding and sundries L.S. 12.61 2 25.22
5502 TOTAL 2166.50 W
5503 Add 1 % Water charges on "W" 21.665
5504 TOTAL 2188.16 X
5505 Add GST (multiplying factor 0.1405) on "X" 307.44
5506 TOTAL 2495.60 Y
5507 Add 15 % Contractor's profit and overheads on "Y" Total 374.34
5508 Add Cess @ 1% on "Z" 2869.94 Z
5509 Cost of 10.00 sqm 28.70
5510 2898.64
5511 Cost of 1.00 sqm 289.86
5512 Say 289.90
5513
5536
5537
5538
5539 13.16 6 mm cement plaster of mix :
5540 13.16.1 1:3 (1 cement : 3 fine sand)
5541 Detail of cost for 10 sqm
5542 MATERIAL
5543 Cement mortar 1 : 3 (1 cement : 3 fine sand)
5544 3.3 Rate as per Item Number 3.3 of SH: Mortars cum 0.072 3670.3 264.26
5545 LABOUR
5546 40 Mason (average) day 0.51 403.67 205.87
5547 18 Coolie day 0.75 350.00 262.50
5548 11 Bhisti day 0.92 350.00 322.00
5549 9999 Extra for removing burrs, cleaning with wire L.S. 13.39 2 26.78
5550 brushes, pock making with pointed tool etc.
5551 9999 complete. 0.00
5552 Scaffolding and sundries L.S. 11.7 2 23.4
5553 TOTAL 1104.81 W
5554 Add 1 % Water charges on "W" 11.0481
5555 TOTAL 1115.86 X
5556 Add GST (multiplying factor 0.1405) on "X" 156.78
5557 TOTAL 1272.64 Y
5558 Add 15 % Contractor's profit and overheads on "Y" 190.90
5559 Total 1463.54 Z
5560 Add Cess @ 1% on "Z" 14.64
5561 Cost of 10.00 sqm 1478.18
5562 Cost of 1.00 sqm 147.82
5563 Say 147.80
5564
5565
5566
5567
5568 13.17 6 mm cement plaster 1:3 (1 cement : 3 fine sand)
5569 finished
bearing of with a floating
R.C.C. slabs coat of neat cement and thick coat of
and beams.
5570 Lime wash on top of
Detail of cost for 10 sqm
walls when dry for
5571 MATERIAL
5572 Cement mortar 1 : 3 (1 cement : 3 fine sand)
5573 3.3 Rate as per Item Number 3.3 of SH: Mortars cum 0.072 3670.3 264.26
5574 LABOUR
5583 40 Mason (average) day 0.51 403.67 205.87
5584 18 Coolie day 0.75 350.00 262.50
5585 11 Bhisti day 0.92 350.00 322.00
5586 9999 Extra for removing burrs, cleaning with wire L.S. 13.39 2 26.78
5587 brushes, pock making with pointed tool etc.
5588 9999 complete. 0.00
5589 Scaffolding and sundries L.S. 11.7 2 23.4
5590 367 Portland Cement (OPC-43 grade) tonne 0.02 4375 87.50
5591 2209 Carriage of Cement tonne 0.02 94.34 1.89
5592 40 Mason (average) day 0.27 403.67 108.99
5593 18 Coolie day 0.27 350.00 94.50
5594 9999 Scaffolding and sundries L.S. 8.06 2 16.12
5595 776 Satna lime quintal 0.01 370 3.70
5596 9999 Indigo gum etc L.S. 2.08 2 4.16
5597 9999 Sundries ladder etc. L.S. 0.52 2 1.04
5598 38 White Washer day 0.07 350.00 24.50
5599 18 Coolie day 0.07 350.00 24.50
5600 9999 Sundries L.S. 2.73 2 5.46
5601 TOTAL 1477.17 W
5602 Add 1 % Water charges on "W" 14.7717
5603 TOTAL 1491.94 X
5604 Add GST (multiplying factor 0.1405) on "X" 209.62
5605 TOTAL 1701.56 Y
5606 Add 15 % Contractor's profit and overheads on "Y" 255.23
5607 Total 1956.79 Z
5608 Add Cess @ 1% on "Z" 19.57
5609 Cost of 10.00 sqm 1976.36
5610 Cost of 1.00 sqm 197.64
5611 Say 197.60
5612
5613
5614 13.18 Neat cement punning.
5615 Detail of cost for 10 sqm
5616 LABOUR
5617 367 Portland Cement (OPC-43 grade) tonne 0.022 4375 96.25
5618 2209 Carriage of Cement tonne 0.022 94.34 2.08
5619 40 Mason (average) day 0.27 403.67 108.99
5620 18 Coolie day 0.27 350.00 94.50
5621 9999 Scaffolding and sundries L.S. 8.06 2 16.12
5624 TOTAL 317.94 W
5625 Add 1 % Water charges on "W" 3.1794
5626 TOTAL 321.12 X
5627 Add GST (multiplying factor 0.1405) on "X" 45.12
5628 TOTAL 366.24 Y
5629 Add 15 % Contractor's profit and overheads on "Y" 54.94
5630 Total 421.18 Z
5631 Add Cess @ 1% on "Z" 4.21
5632 Cost of 10.00 sqm 425.39
5633 Cost of 1.00 sqm 42.54
5635 Say 42.50
5642
5643
5644
5645 13.19 Rough cast plaster upto 10 m height above ground
5646 level
volume of acement.
with mixture of sand and gravel or crushed stone from
5647 6 mm to 10 mm nominal size, dashed over and including the
13.19.1 Ordinary cement finish using ordinary
fresh plaster in two layers, under layer cement
12 mm cement plaster
5648 Detail of cost for 10 sqm
5649 MATERIAL
5650 Under layer 12 mm thick cement plaster Cement
5651 3.9 mortar 1 : 4 (1 cement : 4 coarse sand) 0.00
5652 Rate as per Item Number 3.9 of cum 0.144 3815.05 549.37
5653 SH: Mortars
5654 LABOUR
5655 40 Mason (average) day 0.67 403.67 270.46
5656 17 Beldar day 0.75 350.00 262.50
5657 11 Bhisti day 0.92 350.00 322.00
5658 9999 Scaffolding and sundries L.S. 9.88 2 19.76
5659 Top layer 10 mm thick cement plaster Cement
5660 3.3 mortar 1 : 3 (1 cement : 3 fine sand) 0.00
5661 Rate as per Item Number 3.3 of SH: Mortars cum 0.12 3988 478.56
5662 40 Mason (average) day 0.61 403.67 246.24
5663 17 Beldar day 0.69 350.00 241.50
5664 11 Bhisti day 0.85 350.00 297.50
5665 9999 Scaffolding and sundries L.S. 9.88 2 19.76
5666 1179 Crushed stone 2.36 mm to 12.5 mm size cum 0.1 900 90.00
5667 11 Bhisti day 0.01 350.00 3.50
5668 777 Dry hydrated lime (factory made) quintal 0.09 290 26.10
5669 9977 Carriage of lime L.S. 3.64 2 7.28
5670 40 Mason (average) day 0.5 403.67 201.84
5671 17 Beldar day 0.5 350.00 175.00
5672 11 Bhisti day 0.1 350.00 35.00
5673 9999 Scaffolding and sundries Labour for scooping L.S. 9.88 2 19.76
5674 23 Mason (brick layer) 1st class day 0.25 505.17 126.29
5684 17 Beldar day 0.25 350.00 87.50
5685 TOTAL 3479.92 W
5686 Add 1 % Water charges on "W" 34.7992
5687 TOTAL 3514.72 X
5688 Add GST (multiplying factor 0.1405) on "X" 493.82
5689 TOTAL 4008.54 Y
5690 Add 15 % Contractor's profit and overheads on "Y" 601.28
5691 Total 4609.82 Z
5692 Add Cess @ 1% on "Z" 46.10
5693 Cost of 10.00 sqm 4655.92
5694 Cost of 1.00 sqm 465.59
5695 Say 465.60
5696
5697
5698
5699 13.20 Pebble dash plaster upto 10 m height above ground
5700 level with
hydrated limea mixture of washed
by volume pebble or crushed stone 6 mm
of cement.
5701 to 12.5 mm nominal
Detail of cost for 10 sqm
size, dashed over and including fresh
plaster in two layers under layer 12 mm cement plaster 1:4 (1
5702
5703 MATERIAL
5704 Under layer 12 mm thick cement plaster Cement
5705 3.9 mortar 1 : 4 (1 cement : 4 coarse sand) 0.00
5706 Rate as per Item Number 3.9 of SH: Mortars cum 0.144 3815.05 549.37
5707 LABOUR
5708 40 Mason (average) day 0.67 403.67 270.46
5709 17 Beldar day 0.75 350.00 262.50
5710 11 Bhisti day 0.92 350.00 322.00
5711 9999 Scaffolding and sundries L.S. 9.88 2 19.76
5712 Top layer 10 mm thick cement plaster
5713 Cement mortar 1 : 3 (1 cement : 3 fine sand)
5714 3.3 Rate as per Item Number 3.3 of SH: Mortars cum 0.12 3670.3 440.44
5715 40 Mason (average) day 0.61 403.67 246.24
5716 17 Beldar day 0.69 350.00 241.50
5717 11 Bhisti day 0.85 350.00 297.50
5718 9999 Scaffolding and sundries L.S. 9.88 2 19.76
5719 1179 Crushed stone 2.36 mm to 12.5 mm size cum 0.1 900 90.00
5720 11 Bhisti day 0.01 350.00 3.50
5721 777 Dry hydrated lime (factory made) quintal 0.09 290 26.10
5722 9977 Carriage of lime L.S. 3.64 2 7.28
5723 40 Mason (average) day 0.5 403.67 201.84
5724 17 Beldar day 0.5 350.00 175.00
5725 11 Bhisti day 0.1 350.00 35.00
5726 9999 Scaffolding and sundries L.S. 9.88 2 19.76
5727 9999 Scaffolding and sundries L.S. 4.42 2 8.84
5728 TOTAL 3236.85 W
5729 Add 1 % Water charges on "W" 32.3685
5730 TOTAL 3269.22 X
5731 Add GST (multiplying factor 0.1405) on "X" 459.33
5732 TOTAL 3728.55 Y
5733 Add 15 % Contractor's profit and overheads on "Y" 559.28
5734 Total 4287.83 Z
5735 927 Add Cess @ 1% on "Z" 42.88
5736 Cost of 10.00 sqm 4330.71
5737 Cost of 1.00 sqm 433.07
5739 Say 433.10
5740
5748
5749 13.21 Extra for providing and mixing water proofing material
5751 in cement
Detail of costplaster work
for 12mm in proportion
cement plaster 1:3 (1 recommended by the
5752 manufacturers.
cement :3 sand) = 10 sqm or 1.48 bags of cement
5753 used in the mix.
5754 Cement required for 10 sqm = 73.89kg. Water
5755 proofing material required @ 1 kg per 50 kg of
5756 1213 cement = 1.48 kg. 0.00
5757 Water proofing materials kilogram 1.48 35 51.8
5758 9999 Sundries L.S. 7.15 2 14.30
5759 TOTAL 66.10 W
5760 Add 1 % Water charges on "W" 0.661
5761 TOTAL 66.76 X
5762 Add GST (multiplying factor 0.1405) on "X" 9.38
5763 TOTAL 76.14 Y
5764 Add 15 % Contractor's profit and overheads on "Y" 11.42
5765 Total 87.56 Z
5766 Add Cess @ 1% on "Z" 0.88
5767 Cost of 1.48 bags of cement used in the mix. 88.44
5768 Cost of 1.00 bag of 50 kg cement used in the mix. 59.76
5769 Say 59.80
5770
5771
5772 13.22 Extra for plastering exterior walls of height more than
5773 10
Detail of costground
m from level for every additional height of 3 m or
for 10 sqm
5774 part thereof.
Scaffolding and sundries L.S. 53.82 2
9999 107.64
5775 LABOUR
5776 40 Mason (average) day 0.2 403.67 80.73
5777 18 Coolie day 0.3 350.00 105.00
5778 11 Bhisti day 0.1 350.00 35.00
5779 9999 Sundries L.S. 7.15 2 14.30
5780 TOTAL 342.67 W
5781 Add 1 % Water charges on "W" 3.4267
5782 TOTAL 346.10 X
5783 Add GST (multiplying factor 0.1405) on "X" 48.63
5784 TOTAL 394.73 Y
5785 Add 15 % Contractor's profit and overheads on "Y" 59.21
5786 Total 453.94 Z
5787 Add Cess @ 1% on "Z" 4.54
5788 Cost of 10.00 sqm 458.48
5789 Cost of 1.00 sqm 45.85
5790 Say 45.90
5791
5798
5799
5800
5801
5802 13.23 Extra for plastering on circular work not exceeding 6
5803 m in radius:
13.23.1 In one coat
5804 Detail of cost for 10 sqm
5805 LABOUR
5806 40 Mason (average) day 0.2 403.67 80.73
5807 17 Beldar day 0.2 350.00 70.00
5808 9999 Sundries L.S. 7.15 2 14.30
5809 TOTAL 165.03 W
5810 Add 1 % Water charges on "W" 1.6503
5811 TOTAL 166.68 X
5812 Add GST (multiplying factor 0.1405) on "X" 23.42
5813 TOTAL 190.10 Y
5814 Add 15 % Contractor's profit and overheads on "Y" 28.52
5815 Total 218.62 Z
5816 Add Cess @ 1% on "Z" 2.19
5817 Cost of 10.00 sqm 220.81
5818 Cost of 1.00 sqm 22.08
5819 Say 22.10
5820
5821
5822 13.23.2 In two coats
5823 Detail of cost for 10 sqm
5824 LABOUR
5825 40 Mason (average) day 0.3 403.67 121.10
5826 17 Beldar day 0.3 350.00 105.00
5827 9999 Sundries L.S. 13.39 2 26.78
5828 TOTAL 252.88 W
5829 Add 1 % Water charges on "W" 2.5288
5830 TOTAL 255.41 X
5831 Add GST (multiplying factor 0.1405) on "X" 35.88
5832 TOTAL 291.29 Y
5833 Add 15 % Contractor's profit and overheads on "Y" 43.69
5834 Total 334.98 Z
5835 Add Cess @ 1% on "Z" 3.35
5836 Cost of 10.00 sqm 338.33
5837 Cost of 1.00 sqm 33.83
5838 Say 33.80
5839
5848
5849
5850
5851 13.24 Extra for plastering done on moulding, cornices or
5852 architraves including
13.24.1 In one coat neat finish to line and level:
5853
5854 Detail of cost for 10 sqm
5855 LABOUR
5856 40 Mason (average) day 3 403.67 1211.01
5857 17 Beldar day 2 350.00 700.00
5858 18 Coolie day 1 350.00 350.00
5859 11 Bhisti day 0.25 350.00 87.50
5860 9999 Sundries L.S. 13.39 2 26.78
5861 TOTAL 2375.29 W
5862 Add 1 % Water charges on "W" 23.7529
5863 TOTAL 2399.04 X
5864 Add GST (multiplying factor 0.1405) on "X" 337.07
5865 TOTAL 2736.11 Y
5866 Add 15 % Contractor's profit and overheads on "Y" 410.42
5867 Total 3146.53 Z
5868 Add Cess @ 1% on "Z" 31.47
5869 Cost of 10.00 sqm 3178.00
5870 Cost of 1.00 sqm 317.8
5871 Say 317.80
5872
5873
5874 13.24.2 In two coats
5875 Detail of cost for 10 sqm
5876 LABOUR
5877 40 Mason (average) day 5 403.67 2018.35
5878 17 Beldar day 3 350.00 1050.00
5879 18 Coolie day 2 350.00 700.00
5880 11 Bhisti day 0.33 350.00 115.50
5881 9999 Sundries L.S. 13.39 2 26.78
5882 TOTAL 3910.63 W
5883 Add 1 % Water charges on "W" 39.1063
5884 TOTAL 3949.74 X
5885 Add GST (multiplying factor 0.1405) on "X" 554.94
5886 TOTAL 4504.68 Y
5887 Add 15 % Contractor's profit and overheads on "Y" 675.70
5888 Total 5180.38 Z
5889 Add Cess @ 1% on "Z" 51.80
5890 Cost of 10.00 sqm 5232.18
5891 Cost of 1.00 sqm 523.22
5892 Say 523.20
5893
5902
5903
5904
5905 13.25 Extra for plastering:
5906 13.25.1 Spherical ceiling
5907 Detail of cost for 10 sqm
5908 LABOUR
5909 40 Mason (average) day 0.75 403.67 302.75
5910 17 Beldar day 0.74 350.00 259.00
5911 9999 Sundries L.S. 26.91 2 53.82
5912 TOTAL 615.57 W
5913 Add 1 % Water charges on "W" 6.1557
5914 TOTAL 621.73 X
5915 Add GST (multiplying factor 0.1405) on "X" 87.35
5916 TOTAL 709.08 Y
5917 Add 15 % Contractor's profit and overheads on "Y" 106.36
5918 Total 815.44 Z
5919 Add Cess @ 1% on "Z" 8.15
5920 Cost of 10.00 sqm 823.59
5921 Cost of 1.00 sqm 82.36
5922 Say 82.40
5923
5924
5925 13.25.2 Groined ceiling
5926 Detail of cost for 10 sqm
5927 LABOUR
5928 40 Mason (average) day 0.8 403.67 322.94
5929 17 Beldar day 0.8 350.00 280.00
5930 9999 Sundries L.S. 34.06 2 68.12
5931 TOTAL 671.06 W
5932 Add 1 % Water charges on "W" 6.7106
5933 TOTAL 677.77 X
5934 Add GST (multiplying factor 0.1405) on "X" 95.23
5935 TOTAL 773.00 Y
5936 Add 15 % Contractor's profit and overheads on "Y" 115.95
5937 Total 888.95 Z
5938 Add Cess @ 1% on "Z" 8.89
5939 Cost of 10.00 sqm 897.84
5940 Cost of 1.00 sqm 89.78
5941 Say 89.80
5942
5943
5952
5953 13.25.3 Flewing soffits
5954 Detail of cost for 10 sqm
5956 LABOUR
5957 40 Mason (average) day 0.5 403.67 201.84
5958 17 Beldar day 0.5 350.00 175.00
5959 9999 Sundries L.S. 13.39 2 26.78
5960 TOTAL 403.62 W
5961 Add 1 % Water charges on "W" 4.0362
5962 TOTAL 407.66 X
5963 Add GST (multiplying factor 0.1405) on "X" 57.28
5964 TOTAL 464.94 Y
5965 Add 15 % Contractor's profit and overheads on "Y" 69.74
5966 Total 534.68 Z
5967 Add Cess @ 1% on "Z" 5.35
5968 Cost of 10.00 sqm 540.03
5969 Cost of 1.00 sqm 54
5970 Say 54.00
5971
5972
5973
5974 13.26 Providing and applying plaster of paris putty of 2 mm
5975 thickness over
plastered surface to prepare the surface even and smooth
5976 complete.
Detail of cost for 10 sqm
5977 MATERIAL
5978 Plaster of paris 10x0.002x1121 = 22.42kg
5979 Add 2% wastage= 0.45kg
5980 Total = 22.87kg
5981 Say23kg
5982 869 Plaster of Paris kilogram 23 5 115.00
5983 9977 Carriage of plaster of paris L.S. 3.9 2 7.80
5984 LABOUR
5985 22 Mason (for plaster of paris work) 1st class day 0.91 505.17 459.70
5986 17 Beldar day 0.91 350.00 318.50
5987 9999 Scaffolding and sundries L.S. 83.98 2 167.96
5988 TOTAL 1068.96 W
5989 Add 1 % Water charges on "W" 10.6896
5990 TOTAL 1079.65 X
5991 Add GST (multiplying factor 0.1405) on "X" 151.69
5992 TOTAL 1231.34 Y
5993 Add 15 % Contractor's profit and overheads on "Y" 184.70
5994 Total 1416.04 Z
5995 Add Cess @ 1% on "Z" 14.16
5996 Cost of 10.00 sqm 1430.20
5997 Cost of 1.00 sqm 143.02
5998 Say 143.00
5999
6000
6009
6010 13.27 Extra for lining out plaster to imitate stone or
6012 concrete
Detail blocks
of cost walling.
for 10 sqm
6013 LABOUR
6014 40 Mason (average) day 0.5 403.67 201.84
6015 17 Beldar day 0.5 350.00 175.00
6016 9999 Solution of lime putty L.S. 1.82 2 3.64
6017 TOTAL 380.48 W
6018 Add 1 % Water charges on "W" 3.8048
6019 TOTAL 384.28 X
6020 Add GST (multiplying factor 0.1405) on "X" 53.99
6021 TOTAL 438.27 Y
6022 Add 15 % Contractor's profit and overheads on "Y" 65.74
6023 Total 504.01 Z
6024 Add Cess @ 1% on "Z" 5.04
6025 Cost of 10.00 sqm 509.05
6026 Cost of 1.00 sqm 50.91
6027 Say 50.90
6028
6029
6030
6031 13.28 12 mm thick plain cement mortar bands in cement
6032 mortar 1:4
13.28.1 (1 cement
Flush Band : 4 fine sand):
6033 Detail of cost for 10 metre long and 10 cm wide band
6034 MATERIAL
6035 Cement mortar 1 : 4 (1 cement : 4 fine sand)
6036 3.4 Rate as per Item Number 3.4 of SH: Mortars cum 0.014 3089.3 43.25
6037 LABOUR
6038 40 Mason (average) day 0.27 403.67 108.99
6039 18 Coolie day 0.27 350.00 94.50
6040 11 Bhisti day 0.05 350.00 17.50
6041 9999 Sundries L.S. 1.43 2 2.86
6042 TOTAL 267.10 W
6043 Add 1 % Water charges on "W" 2.671
6044 TOTAL 269.77 X
6045 Add GST (multiplying factor 0.1405) on "X" 37.90
6046 TOTAL 307.67 Y
6047 Add 15 % Contractor's profit and overheads on "Y" 46.15
6048 Total 353.82 Z
6049 Add Cess @ 1% on "Z" 3.54
6050 Cost of 10.00 metre long and 10 cm wide band 357.36
6051 Cost of 1.00 metre long and 1 cm wide band 3.57
6052 Say 3.60
6053
6062
6063 13.28.2 Sunk Band
6065 Detail of cost for 10 metre long and 10 cm wide band
6066 MATERIAL
6067 Cement mortar 1 : 4 (1 cement : 4 fine sand)
6068 3.4 Rate as per Item Number 3.4 of SH: Mortars cum 0.014 3089.3 43.25
6069 LABOUR
6070 40 Mason (average) day 0.3 403.67 121.10
6071 18 Coolie day 0.3 350.00 105.00
6072 11 Bhisti day 0.05 350.00 17.50
6073 9999 Sundries L.S. 2.08 2 4.16
6074 TOTAL 291.01 W
6075 Add 1 % Water charges on "W" 2.9101
6076 TOTAL 293.92 X
6077 Add GST (multiplying factor 0.1405) on "X" 41.30
6078 TOTAL 335.22 Y
6079 Add 15 % Contractor's profit and overheads on "Y" 50.28
6080 Total 385.50 Z
6081 Add Cess @ 1% on "Z" 3.86
6082 Cost of 10.00 metre long and 10 cm wide band 389.36
6083 Cost of 1.00 metre long and 1 cm wide band 3.89
6084 Say 3.90
6085
6086
6087 13.28.3 Raised Band
6088 Detail of cost for 10 metre long and 10 cm wide band
6089 MATERIAL
6090 Cement mortar 1 : 4 (1 cement : 4 fine sand)
6091 3.4 Rate as per Item Number 3.4 of SH: Mortars cum 0.014 3089.3 43.25
6092 LABOUR
6093 40 Mason (average) day 0.35 403.67 141.28
6094 18 Coolie day 0.35 350.00 122.50
6095 11 Bhisti day 0.05 350.00 17.50
6096 9999 Sundries L.S. 2.73 2 5.46
6097 TOTAL 329.99 W
6098 Add 1 % Water charges on "W" 3.2999
6099 TOTAL 333.29 X
6100 Add GST (multiplying factor 0.1405) on "X" 46.83
6101 TOTAL 380.12 Y
6102 Add 15 % Contractor's profit and overheads on "Y" 57.02
6103 Total 437.14 Z
6104 Add Cess @ 1% on "Z" 4.37
6105 Cost of 10.00 metre long and 10 cm wide band 441.51
6106 Cost of 1.00 metre long and 1 cm wide band 4.42
6107 Say 4.40
6108
6117
6118
6119 13.28.4 Moulded Band
6120 Detail of cost for 10 metre long and 10 cm wide band
6121 MATERIAL
6122 Cement mortar 1 : 4 (1 cement : 4 fine sand)
6123 3.4 Rate as per Item Number 3.4 of SH: Mortars cum 0.014 3089.3 43.25
6124 LABOUR
6125 40 Mason (average) day 0.65 403.67 262.39
6126 18 Coolie day 0.65 350.00 227.50
6127 11 Bhisti day 0.05 350.00 17.50
6128 9999 Sundries L.S. 1.56 2 3.12
6129 TOTAL 553.76 W
6130 Add 1 % Water charges on "W" 5.5376
6131 TOTAL 559.30 X
6132 Add GST (multiplying factor 0.1405) on "X" 78.58
6133 TOTAL 637.88 Y
6134 Add 15 % Contractor's profit and overheads on "Y" 95.68
6135 Total 733.56 Z
6136 Add Cess @ 1% on "Z" 7.34
6137 Cost of 10.00 metre long and 10 cm wide band 740.90
6138 Cost of 1.00 metre long and 1 cm wide band 7.41
6139 Say 7.40
6140
6141
6142 13.29 18 mm thick plain cement mortar band in cement
6143 mortar 1:4 (1 cement
13.29.1 Flush Band : 4 fine sand):
6144
6145 Detail of cost for 10 metre long and 10 cm wide band
6146 MATERIAL
6147 Cement mortar 1 : 4 (1 cement : 4 fine sand)
6148 3.4 Rate as per Item Number 3.4 of SH: Mortars cum 0.02 3089.3 61.79
6149 LABOUR
6150 40 Mason (average) day 0.32 403.67 129.17
6151 18 Coolie day 0.32 350.00 112.00
6152 11 Bhisti day 0.06 350.00 21.00
6153 9999 Sundries L.S. 2.08 2 4.16
6154 TOTAL 328.12 W
6155 Add 1 % Water charges on "W" 3.2812
6156 TOTAL 331.40 X
6157 Add GST (multiplying factor 0.1405) on "X" 46.56
6158 TOTAL 377.96 Y
6159 Add 15 % Contractor's profit and overheads on "Y" 56.69
6160 Total 434.65 Z
6161 Add Cess @ 1% on "Z" 4.35
6162 Cost of 10.00 metre long and 10 cm wide band 439.00
6163 Cost of 1.00 metre long and 1 cm wide band 4.39
6164 Say 4.40
6165
6166
6174
6175 13.29.2 Sunk Band
6176
6177 Detail of cost for 10 metre long and 10 cm wide band
6178 MATERIAL
6179 Cement mortar 1 : 4 (1 cement : 4 fine sand)
6180 3.4 Rate as per Item Number 3.4 of SH: Mortars cum 0.02 3089.3 61.79
6181 LABOUR
6182 40 Mason (average) day 0.36 403.67 145.32
6183 18 Coolie day 0.36 350.00 126.00
6184 11 Bhisti day 0.06 350.00 21.00
6185 9999 Sundries L.S. 2.73 2 5.46
6186 TOTAL 359.57 W
6187 Add 1 % Water charges on "W" 3.5957
6188 TOTAL 363.17 X
6189 Add GST (multiplying factor 0.1405) on "X" 51.02
6190 TOTAL 414.19 Y
6191 Add 15 % Contractor's profit and overheads on "Y" 62.13
6192 Total 476.32 Z
6193 Add Cess @ 1% on "Z" 4.76
6194 Cost of 10.00 metre long and 10 cm wide band 481.08
6195 Cost of 1.00 metre long and 1 cm wide band 4.81
6196 Say 4.80
6197
6198
6199 13.29.3 Raised Band
6200 Detail of cost for 10 metre long and 10 cm wide band
6201 MATERIAL
6202 Cement mortar 1 : 4 (1 cement : 4 fine sand)
6203 3.4 Rate as per Item Number 3.4 of SH: Mortars cum 0.02 3089.3 61.79
6204 LABOUR
6205 40 Mason (average) day 0.42 403.67 169.54
6206 18 Coolie day 0.42 350.00 147.00
6207 11 Bhisti day 0.06 350.00 21.00
6208 9999 Sundries L.S. 4.42 2 8.84
6209 TOTAL 408.17 W
6210 Add 1 % Water charges on "W" 4.0817
6211 TOTAL 412.25 X
6212 Add GST (multiplying factor 0.1405) on "X" 57.92
6213 TOTAL 470.17 Y
6214 Add 15 % Contractor's profit and overheads on "Y" 70.53
6215 Total 540.70 Z
6216 Add Cess @ 1% on "Z" 5.41
6217 Cost of 10.00 metre long and 10 cm wide band 546.11
6218 Cost of 1.00 metre long and 1 cm wide band 5.46
6219 Say 5.50
6220
6221
6230
6231 13.29.4 Moulded Band
6232
6233 Detail of cost for 10 metre long and 10 cm wide band
6234 MATERIAL
6235 Cement mortar 1 : 5 (1 cement : 5 coarse sand)
6236 3.10 Rate as per Item Number 3.10 of SH: Mortars cum 0.024 3235.20 77.64
6237 LABOUR
6238 40 Mason (average) day 0.86 403.67 347.16
6239 18 Coolie day 0.86 350.00 301.00
6240 11 Bhisti day 0.05 350.00 17.50
6241 9999 Sundries L.S. 2.73 2 5.46
6242 TOTAL 748.76 W
6243 Add 1 % Water charges on "W" 7.4876
6244 TOTAL 756.25 X
6245 Add GST (multiplying factor 0.1405) on "X" 106.25
6246 TOTAL 862.50 Y
6247 Add 15 % Contractor's profit and overheads on "Y" 129.37
6248 Total 991.87 Z
6249 Add Cess @ 1% on "Z" 9.92
6250 Cost of 10.00 metre long and 10 cm wide band 1001.79
6251 Cost of 1.00 metre long and 1 cm wide band 10.02
6252 Say 10.00
6253
6254
6255 13.30 18 mm thick moulded cement mortar band in two
6256 coatsofunder
Detail layer
cost for 12 mm
10 metre longthick
and 10with cement
cm wide band mortar 1:5 (1
6257 cement
MATERIAL
: 5 coarse sand) top layer 6 mm thick with cement
mortar 1:4 (1 cement : 4 fine sand).
6258 Cement mortar 1 : 5 (1 cement : 5 coarse sand)
6259 3.10 Rate as per Item Number 3.10 of cum 0.014 3235.20 45.29
6260 SH: Mortars
6261 Cement mortar 1 : 4 (1 cement : 4 fine sand)
6262 3.4 Rate as per Item Number 3.4 of SH: Mortars cum 0.01 3089.3 30.89
6263 LABOUR
6264 40 Mason (average) day 0.86 403.67 347.16
6265 18 Coolie day 0.86 350.00 301.00
6266 11 Bhisti day 0.05 350.00 17.50
6267 9999 Sundries L.S. 2.73 2 5.46
6268 TOTAL 747.30 W
6269 Add 1 % Water charges on "W" 7.473
6270 TOTAL 754.77 X
6271 Add GST (multiplying factor 0.1405) on "X" 106.05
6272 TOTAL 860.82 Y
6273 Add 15 % Contractor's profit and overheads on "Y" 129.12
6274 Total 989.94 Z
6275 Add Cess @ 1% on "Z" 9.90
6276 Cost of 10.00 metre long and 10 cm wide band 999.84
6277 Cost of 1.00 metre long and 1 cm wide band 99.98
6278 Say 100.00
6279
6280
6288
6289
6290
6291 13.31 Pointing on brick work or brick flooring with cement
6292 mortar
13.31.1 1:3 (1 cement
Flush / Ruled/: 3Struck
fine sand):
or weathered pointing
6293 Detail of cost for 10 sqm
6294 MATERIAL
6295 Cement mortar 1 : 3 (1 cement : 3 fine sand)
6296 3.3 Rate as per Item Number 3.3 of SH: Mortars cum 0.03 3670.3 110.11
6297 LABOUR
6298 40 Mason (average) day 0.5 403.67 201.84
6299 18 Coolie day 0.6 350.00 210.00
6300 11 Bhisti day 0.93 350.00 325.50
6301 9999 Sundries L.S. 7.15 2 14.30
6302 9999 Scaffolding and racking out joints including L.S. 14.3 2 28.60
6303 sundries
6304 TOTAL 890.35 W
6305 Add 1 % Water charges on "W" 8.9035
6306 TOTAL 899.25 X
6307 Add GST (multiplying factor 0.1405) on "X" 126.35
6308 TOTAL 1025.60 Y
6309 Add 15 % Contractor's profit and overheads on "Y" 153.84
6310 Total 1179.44 Z
6311 Add Cess @ 1% on "Z" 11.79
6312 Cost of 10.00 sqm 1191.23
6313 Cost of 1.00 sqm 119.12
6314 Say 119.10
6315
6316
6317
6318 13.31.2 Raised and cut pointing
6319 Detail of cost for 10 sqm
6320 MATERIAL
6321
6322 Cement mortar 1 : 3 (1 cement : 3 fine sand)
6333 3.3 Rate as per Item Number 3.3 of SH: Mortars cum 0.046 3670.3 168.83
6334 LABOUR
6335 40 Mason (average) day 1.07 403.67 431.93
6336 18 Coolie day 1.31 350.00 458.50
6337 11 Bhisti day 1 350.00 350.00
6338 9999 Sundries L.S. 7.15 2 14.30
6339 9999 Scaffolding and racking out joints including L.S. 16.12 2 32.24
6340 sundries
6341 TOTAL 1455.80 W
6342 Add 1 % Water charges on "W" 14.558
6343 TOTAL 1470.36 X
6344 Add GST (multiplying factor 0.1405) on "X" 206.59
6345 TOTAL 1676.95 Y
6346 Add 15 % Contractor's profit and overheads on "Y" 251.54
6347 Total 1928.49 Z
6348 Add Cess @ 1% on "Z" 19.28
6349 Cost of 10.00 sqm 1947.77
6350 Cost of 1.00 sqm 194.78
6351 Say 194.80
6352
6353
6354
6355 13.32 Pointing on tile brick work with cement mortar 1:3 (1
6356 cement
13.32.1 :Flush/
3 fine Ruled/
sand): Struck or weathered pointing
6357 Detail of cost for 10 sqm
6358 MATERIAL
6359 Cement mortar 1 : 3 (1 cement : 3 fine sand)
6360 3.3 Rate as per Item Number 3.3 of SH: Mortars cum 0.046 3670.3 168.83
6361 9999 Sundries L.S. 7.15 2 14.30
6362 LABOUR
6363 40 Mason (average) day 0.67 403.67 270.46
6364 18 Coolie day 0.8 350.00 280.00
6365 11 Bhisti day 1.28 350.00 448.00
6366 9999 Scaffolding and racking out joints including L.S. 16.12 2 32.24
6367 sundries sundries
6368 TOTAL 1213.83 W
6369 Add 1 % Water charges on "W" 12.1383
6370 TOTAL 1225.97 X
6371 Add GST (multiplying factor 0.1405) on "X" 172.25
6372 TOTAL 1398.22 Y
6373 Add 15 % Contractor's profit and overheads on "Y" 209.73
6374 Total 1607.95 Z
6375 939 Add Cess @ 1% on "Z" 16.08
6376 Cost of 10.00 sqm 1624.03
6377 Cost of 1.00 sqm 162.4
6378 Say 162.40

6389
6390
6391 13.33 Pointing on stone work with cement mortar 1:3 (1
6392 cement
13.33.1 :Flush/
3 fine Ruled
sand) :pointing
6393
6394 Detail of cost for 10 sqm
6395 MATERIAL
6396 Cement mortar 1 : 3 (1 cement : 3 fine sand)
6397 3.3 Rate as per Item Number 3.3 of SH: Mortars cum 0.023 3670.3 84.42
6398 9999 Sundries L.S. 7.15 2 14.30
6399 LABOUR
6400 40 Mason (average) day 0.92 403.67 371.38
6401 18 Coolie day 1.37 350.00 479.50
6402 11 Bhisti day 0.93 350.00 325.50
6403 9999 Scaffolding and racking out joints including L.S. 16.12 2 32.24
6404 sundries
6405 TOTAL 1307.34 W
6406 Add 1 % Water charges on "W" 13.0734
6407 TOTAL 1320.41 X
6408 Add GST (multiplying factor 0.1405) on "X" 185.52
6409 TOTAL 1505.93 Y
6410 Add 15 % Contractor's profit and overheads on "Y" 225.89
6411 Total 1731.82 Z
6412 Add Cess @ 1% on "Z" 17.32
6413 Cost of 10.00 sqm 1749.14
6414 Cost of 1.00 sqm 174.91
6415 Say 174.90
6416
6417
6426
6427
6428 13.33.2 Raised and cut pointing
6429 Detail of cost for 10 sqm
6430 MATERIAL
6431 Cement mortar 1 : 3 (1 cement : 3 fine sand)
6432 3.3 Rate as per Item Number 3.3 of SH: Mortars cum 0.038 3670.3 139.47
6433 9999 Sundries L.S. 7.15 2 14.30
6434 LABOUR
6435 40 Mason (average) day 2 403.67 807.34
6436 18 Coolie day 2.96 350.00 1036.00
6437 11 Bhisti day 1 350.00 350.00
6438 9999 Scaffolding and racking out joints including L.S. 16.12 2 32.24
6439 TOTAL 2239.88 W
6440 Add 1 % Water charges on "W" 22.3988
6441 TOTAL 2262.28 X
6442 Add GST (multiplying factor 0.1405) on "X" 317.85
6443 TOTAL 2580.13 Y
6444 Add 15 % Contractor's profit and overheads on "Y" 387.02
6445 Total 2967.15 Z
6446 Add Cess @ 1% on "Z" 29.67
6447 Cost of 10.00 sqm 2996.82
6448 Cost of 1.00 sqm 299.68
6449 Say 299.70
6450
6451
6452
6453 13.34 Raised and cut pointing on stone work in white
6454 cement
cement mortar 1:3 dust).
: 3 marble (1 white
6455 Detail of cost for 10 sqm
6456
6457 MATERIAL
6458 White Cement mortar 1:3 (1 white cement :
6459 3 marble dust)
6460 3.16 Rate as per Item Number 3.16 of SH: Mortars cum 0.038 7450.60 283.12
6461 9999 Sundries L.S. 7.15 2 14.30
6462 LABOUR
6463 40 Mason (average) day 2 403.67 807.34
6464 18 Coolie day 2.96 350.00 1036.00
6465 11 Bhisti day 1 350.00 350.00
6466 9999 Scaffolding and racking out joints including L.S. 16.12 2 32.24
6467 sundries
6468 TOTAL 2523.00 W
6469 Add 1 % Water charges on "W" 25.23
6470 TOTAL 2548.23 X
6471 Add GST (multiplying factor 0.1405) on "X" 358.03
6472 TOTAL 2906.26 Y
6473 Add 15 % Contractor's profit and overheads on "Y" 435.94
6474 Total 3342.20 Z
6475 Add Cess @ 1% on "Z" 33.42
6476 Cost of 10.00 sqm 3375.62
6477 Cost of 1.00 sqm 337.56
6478 Say 337.60
6479
6487
6488
6489
6490 13.35 Pointing on stone slab ceiling with cement mortar 1:2
6491 (1 cement : 2 fine
13.35.1 Flush/ sand):
Ruled pointing
6492 Detail of cost for 10 sqm
6493 MATERIAL
6494 Cement mortar 1:2 (1 cement : 2 fine sand)
6495 3.2 Rate as per Item Number 3.2 of SH: Mortars cum 0.015 3670.3 55.05
6496 LABOUR
6497 40 Mason (average) day 0.47 403.67 189.72
6498 18 Coolie day 0.69 350.00 241.50
6499 11 Bhisti day 0.59 350.00 206.50
6500 9999 Scaffolding and racking out joints including L.S. 16.12 2 32.24
6501 sundries
6502 TOTAL 725.01 W
6503 Add 1 % Water charges on "W" 7.2501
6504 TOTAL 732.26 X
6505 Add GST (multiplying factor 0.1405) on "X" 102.88
6506 TOTAL 835.14 Y
6507 Add 15 % Contractor's profit and overheads on "Y" 125.27
6508 Total 960.41 Z
6509 Add Cess @ 1% on "Z" 9.60
6510 Cost of 10.00 sqm 970.01
6511 Cost of 1.00 sqm 97
6512 Say 97.00
6513
6514
6515
6516 13.36 Extra for pointing on walls on the outside at height
6517 moreof
Detail than
cost10
for m
10 from
sqm ground level for every additional height
6518 of 3 m
LABOUR
or part there of.
6519 9999 Scaffolding L.S. 13.39 2 26.78
6520 9999 Sundries L.S. 13.39 2 26.78
6521 TOTAL 53.56 W
6522 Add 1 % Water charges on "W" 0.5356
6523 TOTAL 54.10 X
6524 Add GST (multiplying factor 0.1405) on "X" 7.60
6525 TOTAL 61.70 Y
6526 Add 15 % Contractor's profit and overheads on "Y" 9.25
6527 Total 70.95 Z
6528 Add Cess @ 1% on "Z" 0.71
6529 Cost of 10.00 sqm 71.66
6530 Cost of 1.00 sqm 7.17
6531 Say 7.20
6532
6533
6542
6543
6544 13.37 White washing with lime to give an even shade :
6545 13.37.1 New work (three or more coats)
6546 Detail of cost for 10 sqm
6547 MATERIAL
6548 775 Dehradun white lime quintal 0.03 600 18.00
6549 9977 Carriage of lime L.S. 0.91 2 1.82
6550 LABOUR
6551 38 White Washer day 0.2 350.00 70.00
6552 18 Coolie day 0.1 350.00 35.00
6553 9999 Indigo gum etc L.S. 4.42 2 8.84
6554 9999 Sundries ladders etc L.S. 2.73 2 5.46
6555 TOTAL 139.12 W
6556 Add 1 % Water charges on "W" 1.3912
6557 TOTAL 140.51 X
6558 Add GST (multiplying factor 0.1405) on "X" 19.74
6559 TOTAL 160.25 Y
6560 Add 15 % Contractor's profit and overheads on "Y" 24.04
6561 Total 184.29 Z
6562 Add Cess @ 1% on "Z" 1.84
6563 Cost of 10.00 sqm 186.13
6564 Cost of 1.00 sqm 18.61
6565 Say 18.60
6566
6567
6568
6569
6570 13.38 Satna lime wash on walls with one coat.
6571 Detail of cost for 10 sqm
6572 MATERIAL
6573 776 Satna lime quintal 0.01 370 3.70
6584 9977 Carriage of lime L.S. 2.08 2 4.16
6585 9999 Indigo gum etc L.S. 0.52 2 1.04
6586 LABOUR
6587 38 White Washer day 0.08 350.00 28.00
6588 18 Coolie day 0.04 350.00 14.00
6589 9999 Sundries ladders etc L.S. 2.73 2 5.46
6590 TOTAL 56.36 W
6591 Add 1 % Water charges on "W" 0.5636
6592 TOTAL 56.92 X
6593 Add GST (multiplying factor 0.1405) on "X" 8.00
6594 TOTAL 64.92 Y
6595 Add 15 % Contractor's profit and overheads on "Y" 9.74
6596 Total 74.66 Z
6597 Add Cess @ 1% on "Z" 0.75
6598 Cost of 10.00 sqm 75.41
6599 Cost of 1.00 sqm 7.54
6600 Say 7.50
6601
6602
6603
6604 13.39 Colour washing such as green, blue or buff to give an
6605 even
13.39.1 New: work (two or more coats) with a base coat of
shade
6606 white
Detail ofwashing with
cost for 10 sqmlime
6607 MATERIAL
6608 775 Dehradun white lime quintal 0.03 600 18.00
6609 9977 Carriage of lime L.S. 8.06 2 16.12
6610 9999 Add for colouring stuff L.S. 0.91 2 1.82
6611 LABOUR
6612 38 White Washer day 0.3 350.00 105.00
6613 18 Coolie day 0.1 350.00 35.00
6614 9999 Indigo gum etc L.S. 4.42 2 8.84
6615 9999 Sundries ladders etc L.S. 2.73 2 5.46
6616 TOTAL 190.24 W
6617 Add 1 % Water charges on "W" 1.9024
6618 TOTAL 192.14 X
6619 Add GST (multiplying factor 0.1405) on "X" 27.00
6620 TOTAL 219.14 Y
6621 Add 15 % Contractor's profit and overheads on "Y" 32.87
6622 Total 252.01 Z
6623 Add Cess @ 1% on "Z" 2.52
6624 Cost of 10.00 sqm 254.53
6625 Cost of 1.00 sqm 25.45
6626 Say 25.50
6627
6636
6637
6638
6639 13.39.2 New work (two or more coats) with a base coat of
6640 whiting
Detail of cost for 10 sqm
6641 MATERIAL
6642 775 Dehradun white lime quintal 0.03 600 18.00
6643 9977 Carriage of lime L.S. 8.06 2 16.12
6644 9999 Add for colouring stuff L.S. 0.91 2 1.82
6645 LABOUR
6646 38 White Washer day 0.3 350.00 105.00
6647 18 Coolie day 0.1 350.00 35.00
6648 9999 Indigo gum etc L.S. 2.73 2 5.46
6649 9999 Sundries ladders etc L.S. 2.73 2 5.46
6650 TOTAL 152.74 W
6651 Add 1 % Water charges on "W" 1.5274
6652 TOTAL 154.27 X
6653 Add GST (multiplying factor 0.1405) on "X" 21.67
6654 TOTAL 175.94 Y
6655 Add 15 % Contractor's profit and overheads on "Y" 26.39
6656 Total 202.33 Z
6657 Add Cess @ 1% on "Z" 2.02
6658 Cost of 10.00 sqm 204.35
6659 Cost of 1.00 sqm 20.43
6660 Say 20.40
6661
6662
6663
6664 13.40 Distempering with dry distemper of approved brand
6665 and
thinnable priming(two
manufacture coator
tomore coats)
give an evenofshade.
required shade on
6666 new work, over and
Detail of cost for 10 sqm
including water
6667
6668 MATERIAL
6669 808 Water thinnable cement primer for interior wall litre 0.7 50 35.00
6670 9999 surface, having VOC content less than 50 gms/lit. 0.00
6671 Putty, glue etc L.S. 2.73 2 5.46
6672 For distempering
6673 815 Dry distemper kilogram 1.5 30 45.00
6674 9977 Carriage of material L.S. 1.56 2 3.12
6684 9999 Brushes, sand paper etc L.S. 7.15 2 14.30
6685 LABOUR
6686 31 Painter day 0.8 403.67 322.94
6687 18 Coolie day 0.4 350.00 140.00
6688 9999 Sundries L.S. 5.33 2 10.66
6689 TOTAL 576.48 W
6690 Add 1 % Water charges on "W" 5.7648
6691 TOTAL 582.24 X
6692 Add GST (multiplying factor 0.1405) on "X" 81.81
6693 TOTAL 664.05 Y
6694 Add 15 % Contractor's profit and overheads on "Y" 99.61
6695 Total 763.66 Z
6696 Add Cess @ 1% on "Z" 7.64
6697 Cost of 10.00 sqm 771.30
6698 Cost of 1.00 sqm 77.13
6699 Say 77.10
6700
6701
6702
6703 13.41 Distempering with oil bound washable distemper of
6704 approved brand
manufacture and an even shade :
to give
6705 13.41.1 New work (two or more coats) over and including
6706 water thinnable priming coat with cement primer
6707 Detail of cost for 10 sqm
6708
6709 MATERIAL
6710 808 Water thinnable cement primer for interior wall litre 0.7 50 35.00
6711 9999 surface, having VOC content less than 50 gms/lit. 0.00
6712 Brushes, putty etc L.S. 7.15 2 14.3
6713 9988 Sundries including Carriage L.S. 8.06 2 16.12
6714 816 Oil bound washable distemper/ Acrylic distemper kilogram 1.5 50 75.00
6715 9977 Carriage of material L.S. 4.42 2 8.84
6716 9999 Brushes, sand paper and putty for filling holes L.S. 11.7 2 23.40
6717 LABOUR
6718 31 Painter day 1 403.67 403.67
6719 18 Coolie day 0.5 350.00 175.00
6720 9999 Sundries L.S. 8.06 2 16.12
6721 TOTAL 767.45 W
6722 Add 1 % Water charges on "W" 7.6745
6723 TOTAL 775.12 X
6724 Add GST (multiplying factor 0.1405) on "X" 108.90
6725 TOTAL 884.02 Y
6726 Add 15 % Contractor's profit and overheads on "Y" 132.60
6727 Total 1016.62 Z
6728 Add Cess @ 1% on "Z" 10.17
6729 Cost of 10.00 sqm 1026.79
6730 Cost of 1.00 sqm 102.68
6731 Say 102.70
6732
6733
6741
6742
6743 13.42 Distempering with 1st quality acrylic distemper (ready
6744 mixed) of approved
13.42.1 Two manufacturer,
or more coats on newofwork
required shade and
6745 colour complete, as per manufacturer's specification.
6746 Detail of cost for 10 sqm
6747 MATERIAL
6748 816 Oil bound washable distemper/ Acrylic distemper kilogram 1.5 50 75.00
6749 9977 Carriage of material L.S. 4.42 2 8.84
6750 9999 Brushes, sand paper and putty for filling holes L.S. 11.57 2 23.14
6751 LABOUR
6752 31 Painter day 0.4 403.67 161.47
6753 17 Beldar day 0.46 350.00 161.00
6754 9999 Sundries L.S. 8.06 2 16.12
6755 TOTAL 445.57 W
6756 Add 1 % Water charges on "W" 4.4557
6757 TOTAL 450.03 X
6758 Add GST (multiplying factor 0.1405) on "X" 63.23
6759 TOTAL 513.26 Y
6760 Add 15 % Contractor's profit and overheads on "Y" 76.99
6761 Total 590.25 Z
6762 Add Cess @ 1% on "Z" 5.90
6763 Cost of 10.00 sqm 596.15
6764 Cost of 1.00 sqm 59.61
6765 Say 59.60
6766
6767
6768 13.43 Applying one coat of water thinnable cement primer
6769 of
manufacturebrand
approved and
on wall surface :
6770 13.43.1 Water thinnable cement primer
6771 Detail of cost for 10 sqm
6772 MATERIAL
6773 808 Water thinnable cement primer for interior wall litre 0.7 50 35.00
6774 9999 surface, having VOC content less than 50 gms/lit. 0.00
6775 Brushes, putty etc L.S. 7.15 2 14.3
6776 LABOUR
6777 31 Painter day 0.4 403.67 161.47
6778 18 Coolie day 0.2 350.00 70.00
6779 9988 Sundries including carriage L.S. 8.06 2 16.12
6780 TOTAL 296.89 W
6781 Add 1 % Water charges on "W" 2.9689
6782 TOTAL 299.86 X
6783 Add GST (multiplying factor 0.1405) on "X" 42.13
6784 TOTAL 341.99 Y
6785 Add 15 % Contractor's profit and overheads on "Y" 51.30
6786 Total 393.29 Z
6787 Add Cess @ 1% on "Z" 3.93
6788 Cost of 10.00 sqm 397.22
6789 947 Cost of 1.00 sqm 39.72
6790 Say 39.70
6791
6799
6800
6801
6802 13.44 Finishing walls with water proofing cement paint of
6803 required shade
13.44.1 New : (Two or more coats applied @ 3.84 kg/10
work
6804 sqm)
6805 Detail of cost for 10 sqm
6806 MATERIAL
6807 851 Water proofing cement paint kilogram 3.84 38 145.92
6808 9977 Carriage of material L.S. 1.56 2 3.12
6809 LABOUR
6810 31 Painter day 0.46 403.67 185.69
6811 18 Coolie day 0.23 350.00 80.50
6812 11 Bhisti day 0.1 350.00 35.00
6813 9999 Brushes, sand paper etc L.S. 7.15 2 14.30
6814 9999 Sundries L.S. 8.06 2 16.12
6815 TOTAL 480.65 W
6816 Add 1 % Water charges on "W" 4.8065
6817 TOTAL 485.46 X
6818 Add GST (multiplying factor 0.1405) on "X" 68.21
6819 TOTAL 553.67 Y
6820 Add 15 % Contractor's profit and overheads on "Y" 83.05
6821 Total 636.72 Z
6822 Add Cess @ 1% on "Z" 6.37
6823 Cost of 10.00 sqm 643.09
6824 Cost of 1.00 sqm 64.31
6825 Say 64.30
6826
6827
6828 13.45 Finishing walls with textured exterior paint of
6829 required
13.45.1 New shade : (Two or more coats applied @ 3.28 ltr/10
work
6830 sqm) over and including priming coat of exterior primer
6831 applied @ 2.20kg/10 sqm
Detail of cost for 10 sqm
6832 MATERIAL
6833 8507 Textured exterior paint litre 3.28 240 787.20
6834 809 Exterior primer kilogram 2.2 140 308.00
6835 9977 Carriage of material L.S. 1.56 2 3.12
6845 LABOUR
6846 31 Painter day 0.6 403.67 242.20
6847 18 Coolie day 0.3 350.00 105.00
6848 11 Bhisti day 0.05 350.00 17.50
6849 9999 Brushes, sand paper etc L.S. 7.02 2 14.04
6850 9999 Sundries L.S. 8.06 2 16.12
6851 TOTAL 1493.18 W
6852 Add 1 % Water charges on "W" 14.9318
6853 TOTAL 1508.11 X
6854 Add GST (multiplying factor 0.1405) on "X" 211.89
6855 TOTAL 1720.00 Y
6856 Add 15 % Contractor's profit and overheads on "Y" 258.00
6857 Total 1978.00 Z
6858 Add Cess @ 1% on "Z" 19.78
6859 Cost of 10.00 sqm 1997.78
6860 Cost of 1.00 sqm 199.78
6861 Say 199.80
6862
6863
6864 13.46 Finishing walls with Acrylic Smooth exterior paint of
6865 required
13.46.1 New shade : (Two or more coat applied @ 1.67 ltr/10
work
6866 sqm over and including priming coat of exterior primer
6867 applied @ 2.20 kg/10 sqm)
Detail of cost for 10 sqm
6868 MATERIAL
6869 8505 Acrylic exterior paint litre 1.67 170 283.90
6870 809 Exterior Primer Kg 2.2 140 308.00
6871 9977 Carriage of material L.S. 1.56 2 3.12
6872 LABOUR
6873 31 Painter day 0.6 403.67 242.20
6874 18 Coolie day 0.3 350.00 105.00
6875 11 Bhisti day 0.05 350.00 17.50
6876 9999 Brushes, sand paper etc L.S. 7.15 2 14.30
6877 9999 Sundries L.S. 8.06 2 16.12
6878 TOTAL 990.14 W
6879 Add 1 % Water charges on "W" 9.9014
6880 TOTAL 1000.04 X
6881 Add GST (multiplying factor 0.1405) on "X" 140.51
6882 TOTAL 1140.55 Y
6883 Add 15 % Contractor's profit and overheads on "Y" 171.08
6884 Total 1311.63 Z
6885 Add Cess @ 1% on "Z" 13.12
6886 Cost of 10.00 sqm 1324.75
6887 Cost of 1.00 sqm 132.48
6888 Say 132.50
6889
6899
6900
6901 13.47 Finishing walls with Premium Acrylic Smooth exterior
6902 paint with
13.47.1 New Silicone additives
work (Two of required
or more shade:@ 1.43 ltr/10
coats applied
6903 sqm over and including priming coat of exterior primer
6904 applied @ 2.20 kg/10 sqm)
Detail of cost for 10 sqm
6905 MATERIAL
6906 8506 Premium Acrylic exterior paint litre 1.43 180 257.40
6907 809 Exterior primer kilogram 2.2 140 308.00
6908 9977 Carriage of material L.S. 1.56 2 3.12
6909 LABOUR
6910 31 Painter day 0.6 403.67 242.20
6911 18 Coolie day 0.3 350.00 105.00
6912 11 Bhisti day 0.05 350.00 17.50
6913 9999 Brushes, sand paper etc L.S. 7.15 2 14.30
6914 9999 Sundries L.S. 8.06 2 16.12
6915 TOTAL 963.64 W
6916 Add 1 % Water charges on "W" 9.6364
6917 TOTAL 973.28 X
6918 Add GST (multiplying factor 0.1405) on "X" 136.75
6919 TOTAL 1110.03 Y
6920 Add 15 % Contractor's profit and overheads on "Y" 166.50
6921 Total 1276.53 Z
6922 Add Cess @ 1% on "Z" 12.77
6923 Cost of 10.00 sqm 1289.30
6924 Cost of 1.00 sqm 128.93
6925 Say 128.90
6926
6927
6928 13.48 Finishing with Deluxe Multi surface paint system for
6929 interiors and or
13.48.1 Two exteriors usingapplied
more coats Primer on
as walls
per manufacturers
@ 1.25 ltr/10
6930 specifications :
sqm over and including one
6931 coat of Special primer applied @ 0.75 ltr /10 sqm
6932 Detail of cost for 10 sqm
6943 MATERIAL
6944 8504 Multi surface paint litre 1.25 255 318.75
6945 8509 Special Primer (C.W.) litre 0.75 140 105.00
6946 9977 Carriage of material L.S. 1.56 2 3.12
6947 LABOUR
6948 31 Painter day 0.6 403.67 242.20
6949 18 Coolie day 0.3 350.00 105.00
6950 11 Bhisti day 0.05 350.00 17.50
6951 9999 Brushes, sand paper etc L.S. 7.02 2 14.04
6952 9999 Sundries L.S. 8.06 2 16.12
6953 TOTAL 821.73 W
6954 Add 1 % Water charges on "W" 8.2173
6955 TOTAL 829.95 X
6956 Add GST (multiplying factor 0.1405) on "X" 116.61
6957 TOTAL 946.56 Y
6958 Add 15 % Contractor's profit and overheads on "Y" 141.98
6959 Total 1088.54 Z
6960 Add Cess @ 1% on "Z" 10.89
6961 Cost of 10.00 sqm 1099.43
6962 Cost of 1.00 sqm 109.94
6963 Say 109.90
6964
6965
6966 13.48.2 Painting wood work with Deluxe Multi Surface Paint
6967 of required
Detail shade.
of cost for Two or more coat applied @ 0.90 ltr/10
10 sqm
6968 sqm over
MATERIAL
an under coat of primer applied @0.75 ltr/10 sqm of
approved brand and manufacture
6969 8504 Multi surface paint litre 0.9 255 229.50
6970 8509 Special Primer (C.W.) litre 0.75 140 105.00
6971 9977 Carriage of material L.S. 1.56 2 3.12
6972 LABOUR
6973 31 Painter day 0.6 403.67 242.20
6974 18 Coolie day 0.3 350.00 105.00
6975 11 Bhisti day 0.05 350.00 17.50
6976 9999 Brushes, sand paper etc L.S. 7.02 2 14.04
6977 9999 Sundries L.S. 8.06 2 16.12
6978 TOTAL 732.48 W
6979 Add 1 % Water charges on "W" 7.3248
6980 TOTAL 739.80 X
6981 Add GST (multiplying factor 0.1405) on "X" 103.94
6982 TOTAL 843.74 Y
6983 Add 15 % Contractor's profit and overheads on "Y" 126.56
6984 Total 970.30 Z
6985 Add Cess @ 1% on "Z" 9.70
6986 Cost of 10.00 sqm 980.00
6987 Cost of 1.00 sqm 98
6988 Say 98.00
6989
6998
6999
7000 13.48.3 Painting Steel work with Deluxe Multi Surface Paint
7001 to give
Detail an even
of cost for 10shade.
sqm Two or more coat applied @ 0.90 ltr/10
sqm over an under coat of primer applied @ 0.80 ltr/10 sqm
of approved brand and manufacture
7002 MATERIAL
7003 8504 Multi surface paint litre 0.9 255 229.50
7004 8510 Metal Primer (U.G.) litre 0.8 90 72.00
7005 9977 Carriage of material L.S. 1.56 2 3.12
7006 LABOUR
7007 31 Painter day 0.6 403.67 242.20
7008 18 Coolie day 0.3 350.00 105.00
7009 11 Bhisti day 0.05 350.00 17.50
7010 9999 Brushes, sand paper etc L.S. 7.02 2 14.04
7011 9999 Sundries L.S. 8.06 2 16.12
7012 TOTAL 699.48 W
7013 Add 1 % Water charges on "W" 6.9948
7014 TOTAL 706.47 X
7015 Add GST (multiplying factor 0.1405) on "X" 99.26
7016 TOTAL 805.73 Y
7017 Add 15 % Contractor's profit and overheads on "Y" 120.86
7018 Total 926.59 Z
7019 Add Cess @ 1% on "Z" 9.27
7020 Cost of 10.00 sqm 935.86
7021 Cost of 1.00 sqm 93.59
7022 Say 93.60

7023 13.48A Finishing walls with 100% Premium acrylic emulsion paint
7024 having
than 50VOC lessand UV resistance as per IS 15489:2004,
gm/litre
7025 Alkali & fungal
resistance, dirt resistance exterior paint of required shade
7026 13.48A.1 (Company
Depot Tinted) with silicon additives.
7027 New work (Two or more coats applied @ 1.43 litre/ 10 sqm.
7028 Over and priming coat of exterior primer applied @ 0.90
including
7029 litre/10ofsqm.
Details cost for 10 sqm (Based on item no 13.47
7042 MATERIAL
7043 836 100% Premium acrylic dirt resistance, Silicone litre 1.43 270 386.10
7044 837 additives exterior paint
7045 Acrylic Exterior Primer litre 0.9 100 90
7046 9977 Carriage of material L.S. 1.56 2 3.12
7047 LABOUR
7048 31 Painter day 0.45 403.67 181.65
7049 11 Bhisti day 0.45 350.00 157.50
7050 9999 Brushes, sand paper etc L.S. 7.15 2 14.30
7051 9999 Sundries L.S. 8.06 2 16.12
7052 TOTAL 848.79 W
7053 Add 1 % Water charges on "W" 8.4879
7054 TOTAL 857.28 X
7055 Add GST (multiplying factor 0.1405) on "X" 120.45
7056 TOTAL 977.73 Y
7057 Add 15 % Contractor's profit and overheads on "Y" 146.66
7058 Total 1124.39 Z
7059 Add Cess @ 1% on "Z" 11.24
7060 Cost of 10.00 sqm 1135.63
7061 Cost of 1.00 sqm 113.56
7062 Say 113.60
7063
7064
7065
7066 13.50 Applying priming coat:
7067 13.50.1 With ready mixed pink or Grey primer of approved
7068 brand and manufacture
wood work onwood)
(hard and soft
7069 Detail of cost for 10 sqm
7070
7071 MATERIAL
7072 823 Pink primer (for wood) litre 0.75 105 78.75
7073 9999 Putty L.S. 2.73 2 5.46
7074 9977 Carriage L.S. 0.39 2 0.78
7075 LABOUR
7076 31 Painter day 0.25 403.67 100.92
7077 18 Coolie day 0.25 350.00 87.50
7078 9999 Brushes, sand paper etc L.S. 5.33 2 10.66
7079 9999 Sundries L.S. 10.79 2 21.58
7080 TOTAL 305.65 W
7081 Add 1 % Water charges on "W" 3.0565
7082 TOTAL 308.71 X
7083 Add GST (multiplying factor 0.1405) on "X" 43.37
7084 TOTAL 352.08 Y
7085 Add 15 % Contractor's profit and overheads on "Y" 52.81
7086 Total 404.89 Z
7087 Add Cess @ 1% on "Z" 4.05
7088 Cost of 10.00 sqm 408.94
7089 Cost of 1.00 sqm 40.89
7090 Say 40.90
7091
7100
7101
7102
7103 13.50.2 With ready mixed aluminium primer of approved
7104 brand andwood
resinous manufacture on
and plywood
7105 Detail of cost for 10 sqm
7106
7107 MATERIAL
7108 4201 Aluminium primer litre 0.75 110 82.50
7109 9999 Putty L.S. 2.73 2 5.46
7110 9977 Carriage L.S. 0.39 2 0.78
7111 LABOUR
7112 31 Painter day 0.25 403.67 100.92
7113 18 Coolie day 0.25 350.00 87.50
7114 9999 Brushes, sand paper etc L.S. 5.33 2 10.66
7115 9999 Sundries L.S. 10.79 2 21.58
7116 TOTAL 309.40 W
7117 Add 1 % Water charges on "W" 3.094
7118 TOTAL 312.49 X
7119 Add GST (multiplying factor 0.1405) on "X" 43.91
7120 TOTAL 356.40 Y
7121 Add 15 % Contractor's profit and overheads on "Y" 53.46
7122 Total 409.86 Z
7123 Add Cess @ 1% on "Z" 4.10
7124 Cost of 10.00 sqm 413.96
7125 Cost of 1.00 sqm 41.4
7126 Say 41.40
7127
7128
7129 13.50.3 With ready mixed red oxide zinc chromate primer of
7130 approved
Detail of costbrand
for 10 and
sqm manufacture on steel galvanised iron/
7131 steel works
MATERIAL
7132 4202 Red oxide Zinc chromate primer litre 0.54 110 59.40
7133 9977 Carriage L.S. 0.52 2 1.04
7134 LABOUR
7135 31 Painter day 0.24 403.67 96.88
7136 18 Coolie day 0.24 350.00 84.00
7137 9999 Brushes,sand paper including sundries L.S. 10.79 2 21.58
7138 TOTAL 262.90 W
A= 26.29
7139 Add 1 % Water charges on "W" 2.629
7140 TOTAL 265.53 X
7141 Add GST (multiplying factor 0.1405) on "X" 37.31
7142 TOTAL 302.84 Y
7143 Add 15 % Contractor's profit and overheads on "Y" 45.43
7144 Total 348.27 Z
7145 Add Cess @ 1% on "Z" 3.48
7146 Cost of 10.00 sqm 351.75
7147 Cost of 1.00 sqm 35.17
7148 Say 35.20
7150
7151
7158
7159 13.50.4With ready mixed red oxide zinc chromate primer of
7160 approved brand and manufacture on steel work (second coat)
7161 Detail of cost for 10 sqm
7162 MATERIAL
7163 4202 Red oxide Zinc chromate primer litre 0.36 110 39.60
7164 9977 Carriage L.S. 0.39 2 0.78
7165 LABOUR
7166 31 Painter day 0.12 403.67 48.44
7167 18 Coolie day 0.12 350.00 42.00
7168 9999 Brushes,sand paper including L.S. 7.15 2 14.30
7169 TOTAL 145.12 W
7170 Add 1 % Water charges on "W" 1.4512
7171 TOTAL 146.57 X
7172 Add GST (multiplying factor 0.1405) on "X" 20.59
7173 TOTAL 167.16 Y
7174 Add 15 % Contractor's profit and overheads on "Y" 25.07
7175 Total 192.23 Z
7176 Add Cess @ 1% on "Z" 1.92
7177 Cost of 10.00 sqm 194.15
7178 Cost of 1.00 sqm 19.42
7179 Say 19.40
7180
7181
7182
7183 13.51 Painting with silicon & acrylic emulsion based water
7184 thinnable
13.51.1 One sealer
coatof approved brand and manufacture on wet
7185 or patchy portion of plastered surfaces :
Detail of cost for 10 sqm
7186 MATERIAL
7187 801 Silicon and acrylic emulsion litre 1.8 130 234.00
7188 9977 Carriage of material L.S. 0.52 2 1.04
7189 9999 Putty etc L.S. 2.73 2 5.46
7199 LABOUR
7200 31 Painter day 0.27 403.67 108.99
7201 18 Coolie day 0.27 350.00 94.50
7202 9999 Brushes, sand paper etc L.S. 5.33 2 10.66
7203 9999 Sundries L.S. 10.79 2 21.58
7204 TOTAL 476.23 W
7205 Add 1 % Water charges on "W" 4.7623
7206 TOTAL 480.99 X
7207 Add GST (multiplying factor 0.1405) on "X" 67.58
7208 TOTAL 548.57 Y
7209 Add 15 % Contractor's profit and overheads on "Y" 82.29
7210 Total 630.86 Z
7211 Add Cess @ 1% on "Z" 6.31
7212 Cost of 10.00 sqm 637.17
7213 Cost of 1.00 sqm 63.72
7214 Say 63.70
7215
7216
7217 13.51.2 Two coats
7218 Detail of cost for 10 sqm
7219 MATERIAL
7220 801 Silicon and acrylic emulsion litre 2.88 130 374.40
7221 9977 Carriage of material L.S. 0.52 2 1.04
7222 9999 Putty etc L.S. 2.73 2 5.46
7223 LABOUR
7224 31 Painter day 0.43 403.67 173.58
7225 18 Coolie day 0.43 350.00 150.50
7226 9999 Brushes, sand paper etc L.S. 8.53 2 17.06
7227 9999 Sundries L.S. 17.26 2 34.52
7228 TOTAL 756.56 W
7229 Add 1 % Water charges on "W" 7.5656
7230 TOTAL 764.13 X
7231 Add GST (multiplying factor 0.1405) on "X" 107.36
7232 TOTAL 871.49 Y
7233 Add 15 % Contractor's profit and overheads on "Y" 130.72
7234 Total 1002.21 Z
7235 Add Cess @ 1% on "Z" 10.02
7236 Cost of 10.00 sqm 1012.23
7237 Cost of 1.00 sqm 101.22
7238 Say 101.20
7239
7240
7249
7250
7251 13.52 Finishing with Epoxy paint (two or more coats) at all
7252 locations
13.52.1 Onprepared and applied as per manufacturer's
steel work
7253 specifications including appropriate priming coat,
preparation of surface, etc. complete.
7254 Detail of cost for 10 sqm
7255 PRIMING COAT
7256 MATERIAL
7257 4202 Red oxide Zinc chromate primer litre 0.75 110 82.50
7258 9999 Putty L.S. 2.73 2 5.46
7259 9977 Carriage L.S. 0.39 2 0.78
7260 LABOUR
7261 31 Painter day 0.25 403.67 100.92
7262 18 Coolie day 0.25 350.00 87.50
7263 9999 Brushes, sand paper etc L.S. 5.46 2 10.92
7264 9999 Sundries L.S. 10.66 2 21.32
7265 EPOXY PAINTING
7266 MATERIAL
7267 7239 Epoxy paint litre 1.25 230 287.50
7268 9977 Carriage of material L.S. 1.43 2 2.86
7269 LABOUR
7270 31 Painter day 0.54 403.67 217.98
7271 18 Coolie day 0.54 350.00 189.00
7272 9999 Putty, brushes, sand paper etc L.S. 6.76 2 13.52
7273 9999 Sundries L.S. 8.06 2 16.12
7274 TOTAL 1036.38 W
7275 Add 1 % Water charges on "W" 10.3638
7276 TOTAL 1046.74 X
7277 Add GST (multiplying factor 0.1405) on "X" 147.07
7278 TOTAL 1193.81 Y
7279 Add 15 % Contractor's profit and overheads on "Y" 179.07
7280 Total 1372.88 Z
7281 Add Cess @ 1% on "Z" 13.73
7282 Cost of 10.00 sqm 1386.61
7283 Cost of 1.00 sqm 138.66
7284 Say 138.70
7285
7286 13.52.2 On concrete work
7297 Detail of cost for 10 sqm
7298 PRIMING COAT MATERIAL
7299 821 Distemper primer litre 0.84 70 58.80
7300 9999 Putty L.S. 13.52 2 27.04
7301 9977 Carriage L.S. 0.52 2 1.04
7302 LABOUR
7303 31 Painter day 0.25 403.67 100.92
7304 18 Coolie day 0.25 350.00 87.50
7305 9999 Brushes, sand paper etc L.S. 2.73 2 5.46
7306 9999 Sundries L.S. 8.06 2 16.12
7307 EPOXY PAINTING
7308 MATERIAL
7309 7239 Removing white or colour wash by scrapping and litre 1.21 230 278.30
7310 9999 Materials for filling in holes and cracks L.S. 6.76 2 13.52
7311 9977 Carriage of material L.S. 1.43 2 2.86
7312 LABOUR 0
7313 31 Painter day 0.54 403.67 217.98
7314 18 Coolie day 0.54 350.00 189.00
7315 9999 Putty, brushes, sand paper etc L.S. 10.79 2 21.58
7316 9999 Sundries L.S. 6.76 2 13.52
7317 TOTAL 1033.64 W
7318 Add 1 % Water charges on "W" 10.3364
7319 TOTAL 1043.98 X
7320 Add GST (multiplying factor 0.1405) on "X" 146.68
7321 TOTAL 1190.66 Y
7322 Add 15 % Contractor's profit and overheads on "Y" 178.60
7323 Total 1369.26 Z
7324 Add Cess @ 1% on "Z" 13.69
7325 Cost of 10.00 sqm 1382.95
7326 Cost of 1.00 sqm 138.29
7327 Say 138.30
7328
7329
7330 13.53 Painting on G.S. sheet with synthetic enamel paint of
7331 approved brand
manufacture and
of required colour to give an even shade :
7332
7333 13.53.1 New work (two or more coats) including a coat of
7334 approved steel primer but excluding a coat of mordant
7335 solution
Detail of cost for 10 sqm
7336
7337 PRIMING COAT
7347 MATERIAL
7348 4202 Red oxide Zinc chromate primer litre 0.36 110 39.60
7349 9977 Carriage L.S. 0.39 2 0.78
7350 LABOUR
7351 31 Painter day 0.12 403.67 48.44
7352 17 Beldar day 0.12 350.00 42.00
7353 9999 Brushes, sand paper etc L.S. 7.15 2 14.30
7354 EPOXY PAINTING
7355 MATERIAL
7356 834 Synthetic enamel paint in all shades except black litre 0.8 160 128.00
7357 9977 or chocolate shade 2 0.00
7358 Carriage L.S. 1.43 2 2.86
7359 LABOUR 0
7360 31 Painter day 0.54 403.67 217.98
7361 18 Coolie day 0.54 350.00 189.00
7362 9999 Putty, brushes, sand paper etc L.S. 6.76 2 13.52
7363 9999 Sundries L.S. 8.06 2 16.12
7364 TOTAL 712.60 W
7365 Add 1 % Water charges on "W" 7.126
7366 TOTAL 719.73 X
7367 Add GST (multiplying factor 0.1405) on "X" 101.12
7368 TOTAL 820.85 Y
7369 Add 15 % Contractor's profit and overheads on "Y" 123.13
7370 Total 943.98 Z
7371 Add Cess @ 1% on "Z" 9.44
7372 Cost of 10.00 sqm 953.42
7373 Cost of 1.00 sqm 95.34
7374 Say 95.30
7375
7376
7377 13.54 Applying a coat of mordant solution on G.S. sheet:
7378 13.54.1 With a solution of 38 gms of copper acetate in a litre
7379 of soft water
7380 Detail of cost for 25 sqm
7381 MATERIAL
7382 4203 Copper acetate kilogram 0.038 285 10.83
7383 9999 Soft Water L.S. 1.82 2 3.64
7384 9977 Carriage L.S. 0.91 2 1.82
7385 LABOUR
7386 31 Painter day 0.6 403.67 242.20
7387 18 Coolie day 0.6 350.00 210.00
7388 9999 Brushes, sand paper etc L.S. 35.88 2 71.76
7389 9999 Sundries L.S. 35.88 2 71.76
7390 TOTAL 612.01 W
7391 Add 1 % Water charges on "W" 6.1201
7392 TOTAL 618.13 X
7393 Add GST (multiplying factor 0.1405) on "X" 86.85
7394 TOTAL 704.98 Y
7395 Add 15 % Contractor's profit and overheads on "Y" 105.75
7396 Total 810.73 Z
7397 959 Add Cess @ 1% on "Z" 8.11
7398 Cost of 25 sqm 818.84
7399 Cost of 1.00 sqm 32.75
7401 Say 32.80
7402
7403
7410
7411 13.54.2 With a solution made of 13 gms of hydrochloric acid
7412 in a solution of 13 gms each of copper chloride, copper
7413 nitrate and ammonium chloride dissolved in
a litre of soft water
7414
7415 Detail of cost for 25 sqm
7416
7417 MATERIAL
7418 4204 Hydrochloric acid kilogram 0.013 33 0.43
7419 4205 Copper chloride kilogram 0.013 270 3.51
7420 4206 Copper nitrate kilogram 0.013 210 2.73
7421 4207 Ammonium chloride kilogram 0.013 20 0.26
7422 9999 Soft Water L.S. 1.82 2 3.64
7423 9977 Carriage L.S. 0.91 2 1.82
7424 LABOUR
7425 31 Painter day 0.6 403.67 242.20
7426 18 Coolie day 0.6 350.00 210.00
7427 9999 Brushes, sand paper etc L.S. 35.88 2 71.76
7428 9999 Sundries L.S. 35.88 2 71.76
7429 TOTAL 608.11 W
7430 Add 1 % Water charges on "W" 6.0811
7431 TOTAL 614.19 X
7432 Add GST (multiplying factor 0.1405) on "X" 86.29
7433 TOTAL 700.48 Y
7434 Add 15 % Contractor's profit and overheads on "Y" 105.07
7435 Total 805.55 Z
7436 Add Cess @ 1% on "Z" 8.06
7437 Cost of 25 sqm 813.61
7438 Cost of 1.00 sqm 32.54
7439 Say 32.50
7440
7452
7454
7455 13.55 Painting (two or more coats) on rain water, soil, waste
7456 and vent pipes and fittings with black anticorrosive
7457 bitumastic paint of approved brand and manufacture, over
13.55.1 100 mm diameter pipes
and including a priming of ready mixed zinc chromate yellow
7458
7459 Detail of cost for 30 mtrs
7460 Area=22/7 x106.4mm x30m =10.032sqm
7461 MATERIAL
7462 4202 Red oxide Zinc chromate primer litre 0.54 110 59.40
7463 9977 Carriage L.S. 0.52 2 1.04
7464 LABOUR
7465 31 Painter day 0.24 403.67 96.88
7466 18 Coolie day 0.24 350.00 84.00
7467 9999 Brushes, sand paper etc L.S. 10.79 2 21.58
7468 MATERIAL
7469 828 Anticorrosive bituminous paint (black) litre 0.95 100 95.00
7470 9977 Carriage L.S. 1.43 2 2.86
7471 LABOUR
7472 31 Painter day 0.54 403.67 217.98
7473 18 Coolie day 0.54 350.00 189.00
7474 9999 Putty, sand paper etc L.S. 5.33 2 10.66
7475 9999 Sundries L.S. 8.06 2 16.12
7476 9999 Wire brushes for cleaning L.S. 5.33 2 10.66
7477 9999 Extra for delays L.S. 61.1 2 122.20
7478 TOTAL 927.38 W
7479 Add 1 % Water charges on "W" 9.2738
7480 TOTAL 936.65 X
7481 Add GST (multiplying factor 0.1405) on "X" 131.60
7482 TOTAL 1068.25 Y
7483 Add 15 % Contractor's profit and overheads on "Y" 160.24
7484 Total 1228.49 Z
7485 Add Cess @ 1% on "Z" 12.28
7486 Cost of 30.00 mtrs 1240.77
7487 Cost of 1.00 metre 41.36
7488 Say 41.40
7489
7490
7491
7492 13.55.2 150 mm diameter pipes
7493 Detail of cost for 30 mtrs
7494 Area=22/7 x0.1572 m x30m =14.82sqm
7496 MATERIAL
7498 4202 Red oxide Zinc chromate primer litre 0.8 110 88.00
7508 LABOUR
7509 31 Painter day 0.36 403.67 145.32
7510 18 Coolie day 0.36 350.00 126.00
7511 9999 Brushes, sand paper etc L.S. 15.99 2 31.98
7512 9977 Carriage L.S. 0.91 2 1.82
7513 MATERIAL
7514 828 Anticorrosive bituminous paint (black) litre 1.41 100 141.00
7515 9977 Carriage L.S. 2.08 2 4.16
7516 LABOUR
7517 31 Painter day 0.8 403.67 322.94
7518 18 Coolie day 0.8 350.00 280.00
7519 9999 Putty, sand paper etc L.S. 8.06 2 16.12
7520 9999 Sundries L.S. 11.96 2 23.92
7521 9999 Wire brushes for cleaning L.S. 7.15 2 14.30
7522 9999 Extra for delays L.S. 94.12 2 188.24
7523 TOTAL 1383.80 W
7524 Add 1 % Water charges on "W" 13.838
7525 TOTAL 1397.64 X
7526 Add GST (multiplying factor 0.1405) on "X" 196.37
7527 TOTAL 1594.01 Y
7528 Add 15 % Contractor's profit and overheads on "Y" 239.10
7529 Total 1833.11 Z
7530 Add Cess @ 1% on "Z" 18.33
7531 Cost of 30.00 mtrs 1851.44
7532 Cost of 1.00 metre 61.71
7533 Say 61.70
7534
7535
7536
7537 13.56 Painting (two or more coats) on rain water, soil, waste
7538 and vent
13.56.1 100 pipesmmand fittingspipes
diameter with synthetic enamel paint of
7539 approved brand and
Detail of cost for 30 mtrs
manufacture and required colour over a
priming coat of approved steel primer on new work.
7540 Area=22/7x0.1064m x30m =10.032sqm
7541 MATERIAL
7542 4202 Red oxide Zinc chromate primer litre 0.54 110 59.40
7543 9977 Carriage L.S. 0.52 2 1.04
7544 LABOUR
7545 31 Painter day 0.24 403.67 96.88
7554 18 Coolie day 0.24 350.00 84.00
7555 9999 Sundries L.S. 10.79 2 21.58
7556 MATERIAL
7557 833 Synthetic enamel paint in black or chocolate litre 1.16 170 197.20
7558 shade
7559 9977 Carriage L.S. 1.43 2 2.86
7560 9999 Putty, sand paper etc L.S. 5.33 2 10.66
7561 LABOUR
7562 31 Painter day 0.54 403.67 217.98
7563 18 Coolie day 0.54 350.00 189.00
7564 9999 Sundries L.S. 6.76 2 13.52
7565 9999 Wire brushes for cleaning L.S. 11.96 2 23.92
7566 9999 Extra for delays L.S. 66.43 2 132.86
7567 TOTAL 1050.90 W
7568 Add 1 % Water charges on "W" 10.509
7569 TOTAL 1061.41 X
7570 Add GST (multiplying factor 0.1405) on "X" 149.13
7571 TOTAL 1210.54 Y
7572 Add 15 % Contractor's profit and overheads on "Y" 181.58
7573 Total 1392.12 Z
7574 Add Cess @ 1% on "Z" 13.92
7575 Cost of 30.00 mtrs 1406.04
7576 Cost of 1.00 metre 46.87
7577 Say 46.90
7578
7579
7580 13.56.2 150 mm diameter pipes
7581 Detail of cost for 30 mtrs
7582 Area=22/7 x157.2mm x30m =14.82sqm
7583 MATERIAL
7584 4202 Red oxide Zinc chromate primer litre 0.8 110 88.00
7585 9977 Carriage L.S. 0.65 2 1.30
7586 LABOUR
7587 31 Painter day 0.36 403.67 145.32
7588 18 Coolie day 0.36 350.00 126.00
7589 9999 Sundries L.S. 15.99 2 31.98
7590 MATERIAL
7591 833 Synthetic enamel paint in black or chocolate litre 1.72 170 292.40
7592 shade
7593 9977 Carriage L.S. 2.08 2 4.16
7594 9999 Putty, sand paper etc L.S. 7.93 2 15.86
7595 LABOUR
7596 31 Painter day 0.8 403.67 322.94
7597 18 Coolie day 0.8 350.00 280.00
7607 9999 Sundries L.S. 10.01 2 20.02
7608 9999 Wire brushes for cleaning L.S. 17.81 2 35.62
7609 9999 Extra for delays L.S. 101.4 2 202.80
7610 TOTAL 1566.40 W
7611 Add 1 % Water charges on "W" 15.664
7612 TOTAL 1582.06 X
7613 Add GST (multiplying factor 0.1405) on "X" 222.28
7614 TOTAL 1804.34 Y
7615 Add 15 % Contractor's profit and overheads on "Y" 270.65
7616 Total 2074.99 Z
7617 Add Cess @ 1% on "Z" 20.75
7618 Cost of 30.00 mtrs 2095.74
7619 Cost of 1.00 metre 69.86
7620 Say 69.90
7621
7622
7623
7624 13.57 Painting with oil type wood preservative of approved
7625 brand and
13.57.1 manufacture
New : more coats)
work (two or
7626 Detail of cost for 10 sqm
7627 MATERIAL
7628 859 Oil type wood preservative litre 1 130 130.00
7629 9977 Carriage of material L.S. 0.52 2 1.04
7630 LABOUR
7631 31 Painter day 0.15 403.67 60.55
7632 18 Coolie day 0.15 350.00 52.50
7633 9999 Brushes etc L.S. 4.16 2 8.32
7634 9999 Sundries L.S. 3.9 2 7.80
7635 TOTAL 260.21 W
7636 Add 1 % Water charges on "W" 2.6021
7637 TOTAL 262.81 X
7638 Add GST (multiplying factor 0.1405) on "X" 36.93
7639 TOTAL 299.74 Y
7640 Add 15 % Contractor's profit and overheads on "Y" 44.96
7641 Total 344.70 Z
7642 Add Cess @ 1% on "Z" 3.45
7643 Cost of 10.00 sqm 348.15
7644 Cost of 1.00 sqm 34.82
7645 Say 34.80
7646
7647
7657
7658
7659 13.58 Providing and applying two coats of fire retardant
7660 paint of
Detail oncost
cleaned wood / ply surface @ 3.5 sqm per litre per
for 10 sqm
7661 coat including
MATERIAL
preparation of base surface as per
recommendations of manufacturer to make the surface fire
7662 7240 Fire retardant paint litre 5.7 260 1482.00
7663 9977 Carriage of material L.S. 1.43 2 2.86
7664 LABOUR
7665 31 Painter day 0.54 403.67 217.98
7666 17 Beldar day 0.54 350.00 189.00
7667 9999 Putty, brushes, sand paper etc L.S. 6.76 2 13.52
7668 9999 Sundries L.S. 8.06 2 16.12
7669 TOTAL 1921.48 W
7670 Add 1 % Water charges on "W" 19.2148
7671 TOTAL 1940.69 X
7672 Add GST (multiplying factor 0.1405) on "X" 272.67
7673 TOTAL 2213.36 Y
7674 Add 15 % Contractor's profit and overheads on "Y" 332.00
7675 Total 2545.36 Z
7676 Add Cess @ 1% on "Z" 25.45
7677 Cost of 10.00 sqm 2570.81
7678 Cost of 1.00 sqm 257.08
7679 Say 257.10
7680
7681
7682
7683 13.59 Coal tarring two coats on new work using 0.16 Litre
7684 and 0.12 litre
Detail of cost forcoal tar per sqm in the first coat and second
10 sqm
7685 coat respectively.
MATERIAL
7686 9999 Lime L.S. 1.43 2 2.86
7687 324 Coal Tar litre 2.8 30 84.00
7688 9977 Carriage of material L.S. 1.43 2 2.86
7689 771 Kerosene oil litre 0.5 50 25.00
7690 LABOUR
7691 17 Beldar day 0.43 350.00 150.50
7692 9999 Brushes etc L.S. 5.33 2 10.66
7693 9999 Sundries L.S. 5.33 2 10.66
7694 TOTAL 286.54 W
7695 Add 1 % Water charges on "W" 2.8654
7696 TOTAL 289.41 X
7697 Add GST (multiplying factor 0.1405) on "X" 40.66
7698 TOTAL 330.07 Y
7699 Add 15 % Contractor's profit and overheads on "Y" 49.51
7700 Total 379.58 Z
7701 Add Cess @ 1% on "Z" 3.80
7702 Cost of 10.00 sqm 383.38
7703 Cost of 1.00 sqm 38.34
7705 Say 38.30
7706
7707
7714
7715
7716 13.60 Wall painting with acrylic emulsion paint of approved
7717 brand and manufacture
to give an even shade :
7718 13.60.1 Two or more coats on new work
7719 Detail of cost for 10 sqm
7720 MATERIAL
7721 835 Plastic emulsion paint litre 1.21 200 242.00
7722 9999 MATERIAL L.S. 6.76 2 13.52
7723 9977 Carriage of material L.S. 1.43 2 2.86
7724 LABOUR
7725 31 Painter day 0.54 403.67 217.98
7726 18 Coolie day 0.54 350.00 189.00
7727 9999 Brushes, sand paper etc L.S. 10.79 2 21.58
7728 9999 Sundries L.S. 6.76 2 13.52
7729 TOTAL 700.46 W
7730 Add 1 % Water charges on "W" 7.0046
7731 TOTAL 707.46 X
7732 Add GST (multiplying factor 0.1405) on "X" 99.40
7733 TOTAL 806.86 Y
7734 Add 15 % Contractor's profit and overheads on "Y" 121.03
7735 Total 927.89 Z
7736 Add Cess @ 1% on "Z" 9.28
7737 Cost of 10.00 sqm 937.17
7738 Cost of 1.00 sqm 93.72
7739 Say 93.70
7740
7741
7742 13.61 Painting with synthetic enamel paint of approved
7743 brand and
13.61.1 Twomanufacture to give
or more coats an even
on new workshade :
7744 Detail of cost for 10 sqm
7755 MATERIAL
7756 833 Synthetic enamel paint in black or chocolate litre 1.16 170 197.20
7757 shade
7758 9999 MATERIAL L.S. 5.33 2 10.66
7759 9977 Carriage L.S. 1.43 2 2.86
7760 LABOUR
7761 31 Painter day 0.54 403.67 217.98
7762 18 Coolie day 0.54 350.00 189.00
7763 9999 Brushes, sand paper etc L.S. 6.76 2 13.52
7764 9999 Sundries L.S. 8.06 2 16.12
7765 TOTAL 647.34 W
7766 Add 1 % Water charges on "W" 6.4734
7767 TOTAL 653.81 X
7768 Add GST (multiplying factor 0.1405) on "X" 91.86
7769 TOTAL 745.67 Y
7770 Add 15 % Contractor's profit and overheads on "Y" 111.85
7771 Total 857.52 Z
7772 Add Cess @ 1% on "Z" 8.58
7773 Cost of 10.00 sqm 866.10
7774 Cost of 1.00 sqm 86.61
7775 Say 86.60
7776
7777
7778
7779 13.62 Painting with synthetic enamel paint of approved
7780 brand and
13.62.1 manufacture
Two of required
or more coats on new colour to give
work over an even
an under coat
7781 shade
of :
suitable shade with
Detail of cost for 10 sqm ordinary paint of approved brand and
7782 manufacture
MATERIAL
7783 823 Pink primer (for wood) litre 0.75 105 78.75
7784 9999 Putty L.S. 2.73 2 5.46
7785 9977 Carriage L.S. 0.39 2 0.78
7786 LABOUR
7787 31 Painter day 0.25 403.67 100.92
7788 18 Coolie day 0.25 350.00 87.50
7789 9999 Brushes, sand paper etc L.S. 5.33 2 10.66
7790 9999 Sundries L.S. 10.79 2 21.58
7791 MATERIAL
7792 833 Synthetic enamel paint in black or chocolate litre 1.16 170 197.20
7793 shade
7794 9977 Carriage of paint and material L.S. 1.43 2 2.86
7795 LABOUR
7796 31 Painter day 0.54 403.67 217.98
7797 18 Coolie day 0.54 350.00 189.00
7798 9999 Brushes, sand paper etc L.S. 6.76 2 13.52
7808 9999 Sundries L.S. 8.06 2 16.12
7809 TOTAL 942.33 W
7810 Add 1 % Water charges on "W" 9.4233
7811 TOTAL 951.75 X
7812 Add GST (multiplying factor 0.1405) on "X" 133.72
7813 TOTAL 1085.47 Y
7814 Add 15 % Contractor's profit and overheads on "Y" 162.82
7815 Total 1248.29 Z
7816 Add Cess @ 1% on "Z" 12.48
7817 Cost of 10.00 sqm 1260.77
7818 Cost of 1.00 sqm 126.08
7819 Say 126.10
7820
7821
7822 13.63 Painting with aluminium paint of approved brand and
7823 manufacture
13.63.1 Two toor give
morean evenon
coats shade .
new work
7824
7825 Detail of cost for 10 sqm
7826 MATERIAL
7827 826 Aluminium paint litre 0.8 150 120.00
7828 9977 Carriage of paint and material L.S. 1.43 2 2.86
7829 9999 Putty etc L.S. 5.33 2 10.66
7830 LABOUR
7831 31 Painter day 0.54 403.67 217.98
7832 18 Coolie day 0.54 350.00 189.00
7833 9999 Brushes, sand paper etc L.S. 6.76 2 13.52
7834 9999 Sundries L.S. 11.96 2 23.92
7835 TOTAL 577.94 W
7836 Add 1 % Water charges on "W" 5.7794
7837 TOTAL 583.72 X
7838 Add GST (multiplying factor 0.1405) on "X" 82.01
7839 TOTAL 665.73 Y
7840 Add 15 % Contractor's profit and overheads on "Y" 99.86
7841 Total 765.59 Z
7842 Add Cess @ 1% on "Z" 7.66
7843 Cost of 10.00 sqm 773.25
7844 Cost of 1.00 sqm 77.32
7845 Say 77.30
7846
7847
7848 13.64 Painting with acid proof paint of approved brand and
7849 manufacture
13.64.1 Two ofor required colour
more coats to give
on new workan even shade :
7850
7851 Detail of cost for 10 sqm
7852 MATERIAL
7864 827 Acid proof paint (chocolate or black) litre 1.16 225 261.00
7865 9977 Carriage of paint L.S. 1.43 2 2.86
7866 9999 Putty etc L.S. 5.33 2 10.66
7867 LABOUR
7868 31 Painter day 0.54 403.67 217.98
7869 18 Coolie day 0.54 350.00 189.00
7870 9999 Brushes, sand paper etc L.S. 6.76 2 13.52
7871 9999 Sundries L.S. 8.06 2 16.12
7872 TOTAL 711.14 W
7873 Add 1 % Water charges on "W" 7.1114
7874 TOTAL 718.25 X
7875 Add GST (multiplying factor 0.1405) on "X" 100.91
7876 TOTAL 819.16 Y
7877 Add 15 % Contractor's profit and overheads on "Y" 122.87
7878 Total 942.03 Z
7879 Add Cess @ 1% on "Z" 9.42
7880 Cost of 10.00 sqm 951.45
7881 Cost of 1.00 sqm 95.15
7882 Say 95.20
7883
7884
7885 13.65 Painting with black anti-corrosive bitumastic paint of
7886 approved brand
13.65.1 Two and manufacture
or more coats on newtowork
give an even shade :
7887
7888 Detail of cost for 10 sqm
7889 MATERIAL
7890 828 Anticorrosive bituminous paint (black) litre 0.95 100 95.00
7891 9977 Carriage L.S. 1.43 2 2.86
7892 LABOUR
7893 31 Painter day 0.54 403.67 217.98
7894 18 Coolie day 0.54 350.00 189.00
7895 9999 Putty, brushes, sand paper etc L.S. 5.33 2 10.66
7896 9999 Sundries L.S. 8.06 2 16.12
7897 TOTAL 531.62 W
7898 Add 1 % Water charges on "W" 5.3162
7899 TOTAL 536.94 X
7900 Add GST (multiplying factor 0.1405) on "X" 75.44
7901 TOTAL 612.38 Y
7902 Add 15 % Contractor's profit and overheads on "Y" 91.86
7903 Total 704.24 Z
7904 Add Cess @ 1% on "Z" 7.04
7905 Cost of 10.00 sqm 711.28
7906 Cost of 1.00 sqm 71.13
7907 Say 71.10
7908
7909
7917
7918
7919 13.66 Floor painting with floor enamel paint of approved
7920 brand and manufacture
required colour of even shade :
to give an
7921 13.66.1 Two or more coats on new work
7922 Detail of cost for 10 sqm
7923 MATERIAL
7924 831 Floor enamel paint in all shades except green litre 1.48 250 370.00
7925 9977 Carriage L.S. 1.43 2 2.86
7926 9999 Putty etc L.S. 5.33 2 10.66
7927 LABOUR
7928 31 Painter day 0.54 403.67 217.98
7929 18 Coolie day 0.54 350.00 189.00
7930 9999 Brushes, sand paper etc L.S. 6.76 2 13.52
7931 9999 Sundries L.S. 8.06 2 16.12
7932 TOTAL 820.14 W
7933 Add 1 % Water charges on "W" 8.2014
7934 TOTAL 828.34 X
7935 Add GST (multiplying factor 0.1405) on "X" 116.38
7936 TOTAL 944.72 Y
7937 Add 15 % Contractor's profit and overheads on "Y" 141.71
7938 Total 1086.43 Z
7939 Add Cess @ 1% on "Z" 10.86
7940 Cost of 10.00 sqm 1097.29
7941 Cost of 1.00 sqm 109.73
7942 Say 109.70
7943
7944
7945 13.67 Varnishing with varnish of approved brand and
7946 manufacture : more coats of glue sizing with copal varnish
13.67.1 Two or
7947 over an under coat of
7948 flatting varnish
7949
7950 Detail of cost for 10 sqm
7951 MATERIAL
7952 856 Ordinary varnish litre 0.7 100 70.00
7953 763 Glue kilogram 0.07 75 5.25
7954 857 Superior copal varnish litre 1.16 115 133.40
7955 9977 Carriage L.S. 1.43 2 2.86
7956 9999 Putty for repair to holes etc L.S. 5.33 2 10.66
7957 LABOUR
7958 31 Painter day 0.9 403.67 363.30
7959 (0.36+0.54=0.90)
7969 18 Coolie day 0.9 350.00 315.00
7970 (0.36+0.54=0.90)
7971 9999 Brushes, sand paper etc L.S. 6.76 2 13.52
7972 9999 Sundries L.S. 7.15 2 14.30
7973 TOTAL 928.29 W
7974 Add 1 % Water charges on "W" 9.2829
7975 TOTAL 937.57 X
7976 Add GST (multiplying factor 0.1405) on "X" 131.73
7977 TOTAL 1069.30 Y
7978 Add 15 % Contractor's profit and overheads on "Y" 160.40
7979 Total 1229.70 Z
7980 Add Cess @ 1% on "Z" 12.30
7981 Cost of 10.00 sqm 1242.00
7982 Cost of 1.00 sqm 124.2
7983 Say 124.20
7984
7985
7986 13.67.2 Two or more coats glue sizing with spar varnish or
7987 an under
Detail coat
of cost of sqm
for 10 flatting varnish
7988 MATERIAL
7989 856 Ordinary varnish litre 0.7 100 70.00
7990 763 Glue kilogram 0.07 75 5.25
7991 858 Superior spar varnish litre 1.26 115 144.90
7992 9977 Carriage L.S. 1.43 2 2.86
7993 9999 Repair etc L.S. 2.73 2 5.46
7994 LABOUR
7995 31 Painter day 0.9 403.67 363.30
7996 (0.36+0.54=0.90)
7997 18 Coolie day 0.9 350.00 315.00
7998 (0.36+0.54=0.90)
7999 9999 Brushes, sand paper etc L.S. 6.76 2 13.52
8000 9999 Sundries L.S. 7.15 2 14.30
8001 TOTAL 934.59 W
8002 Add 1 % Water charges on "W" 9.3459
8003 TOTAL 943.94 X
8004 Add GST (multiplying factor 0.1405) on "X" 132.62
8005 TOTAL 1076.56 Y
8006 Add 15 % Contractor's profit and overheads on "Y" 161.48
8007 Total 1238.04 Z
8008 Add Cess @ 1% on "Z" 12.38
8009 Cost of 10.00 sqm 1250.42
8010 Cost of 1.00 sqm 125.04
8011 Say 125.00
8012
8021
8022
8023 13.68 French spirit polishing :
8024 13.68.1 Two or more coats on new works including a coat of
8025 wood filler
8026 Detail of cost for 10 sqm
8027 MATERIAL
8028 1000 Spirit litre 1.63 48 78.24
8029 9999 Pigment L.S. 7.15 2 14.30
8030 999 Shellac kilogram 0.24 300 72.00
8031 9977 Carriage of material L.S. 2.73 2 5.46
8032 9999 White woolen cloth, putty L.S. 16.12 2 32.24
8033 9999 Sand paper cotton etc L.S. 13.39 2 26.78
8034 9999 Lineseed oil L.S. 1.43 2 2.86
8035 LABOUR
8036 31 Painter day 3.5 403.67 1412.85
8037 9999 Sundries L.S. 8.06 2 16.12
8038 TOTAL 1660.85 W
8039 Add 1 % Water charges on "W" 16.6085
8040 TOTAL 1677.46 X
8041 Add GST (multiplying factor 0.1405) on "X" 235.68
8042 TOTAL 1913.14 Y
8043 Add 15 % Contractor's profit and overheads on "Y" 286.97
8044 Total 2200.11 Z
8045 Add Cess @ 1% on "Z" 22.00
8046 Cost of 10.00 sqm 2222.11
8047 Cost of 1.00 sqm 222.21
8048 Say 222.20
8049
8050
8051 13.69 Polishing on wood work with ready mixed wax polish
8052 13.69.1 of
New work brand and manufacture :
approved
8053 Detail of cost for 10 sqm
8054 MATERIAL
8055 855 Wax polish (ready made) kilogram 0.5 230 115.00
8056 9977 Carriage L.S. 0.39 2 0.78
8057 LABOUR
8058 31 Painter day 0.8 403.67 322.94
8059 18 Coolie day 0.8 350.00 280.00
8060 9999 Soap, brushes, cloth etc L.S. 4.16 2 8.32
8061 9999 Sundries L.S. 7.15 2 14.30
8062 TOTAL 741.34 W
8063 Add 1 % Water charges on "W" 7.4134
8064 TOTAL 748.75 X
8065 Add GST (multiplying factor 0.1405) on "X" 105.20
8066 TOTAL 853.95 Y
8067 Add 15 % Contractor's profit and overheads on "Y" 128.09
8068 Total 982.04 Z
8069 972 Add Cess @ 1% on "Z" 9.82
8070 Cost of 10.00 sqm 991.86
8071 Cost of 1.00 sqm 99.19
8073 Say 99.20
8074
8083
8084
8085 13.70 Floor polishing on masonry or concrete floors with
8086 wax
Detailpolish of approved
of cost for 10 sqm brand and manufacture.
8087 MATERIAL
8088 855 Wax polish (ready made) kilogram 0.1 230 23.00
8089 LABOUR
8090 31 Painter day 0.4 403.67 161.47
8091 18 Coolie day 0.4 350.00 140.00
8092 9999 Acetic acid soap, cloth etc L.S. 5.33 2 10.66
8093 9988 Sundries including Carriage L.S. 8.06 2 16.12
8094 TOTAL 351.25 W
8095 Add 1 % Water charges on "W" 3.5125
8096 TOTAL 354.76 X
8097 Add GST (multiplying factor 0.1405) on "X" 49.84
8098 TOTAL 404.60 Y
8099 Add 15 % Contractor's profit and overheads on "Y" 60.69
8100 Total 465.29 Z
8101 Add Cess @ 1% on "Z" 4.65
8102 Cost of 10.00 sqm 469.94
8103 Cost of 1.00 sqm 46.99
8104 Say 47.00
8105
8106
8107 13.71 Lettering with black Japan paint of approved brand
8108 and manufacture
Detail of cost for 100 letters of 15 cm height
8109 MATERIAL
8110 829 Black Japan paint litre 0.56 90 50.40
8111 9977 Carriage L.S. 0.91 2 1.82
8112 LABOUR
8113 31 Painter day 6 403.67 2422.02
8123 18 Coolie day 2 350.00 700.00
8124 9999 Painting brushes, turpentine, stencil etc L.S. 13.39 2 26.78
8125 9999 Sundries L.S. 8.06 2 16.12
8126 TOTAL 3217.14 W
8127 Add 1 % Water charges on "W" 32.1714
8128 TOTAL 3249.31 X
8129 Add GST (multiplying factor 0.1405) on "X" 456.53
8130 TOTAL 3705.84 Y
8131 Add 15 % Contractor's profit and overheads on "Y" 555.88
8132 Total 4261.72 Z
8133 Add Cess @ 1% on "Z" 42.62
8134 Cost of 100 letters of 15 cm height 4304.34
8135 Cost of 1 letters of 1 cm height 2.87
8136 Say 2.90
8137
8138
8139 13.72 Washed stone grit plaster on exterior walls height
8140 upto
groovesmetre
10 above
shall be ground
made level, in two layers, under layer
separately).
8141 12 mm cement plaster 1:4 (1 cement : 4 coarse sand ),
furrowing the under layer with scratching tool, applying
8142 Detail of cost for 10 sqm
8143
8144 MATERIAL
8145 Under layer 12 mm cement plaster with Cement
8146 3.9 mortar 1 : 4 (1 cement : 4 coarse sand) 0.00
8147 Rate as per Item Number 3.9 of SH: Mortars cum 0.144 3815.05 549.37
8148 LABOUR
8149 40 Mason (average) day 0.67 403.67 270.46
8150 17 Beldar day 0.75 350.00 262.50
8151 11 Bhisti day 0.92 350.00 322.00
8152 9999 Scaffolding L.S. 8.97 2 17.94
8153 Applying cement slurry
8154 367 Portland Cement (OPC-43 grade) tonne 0.02 4375 87.50
8155 2209 Carriage of Cement tonne 0.02 94.34 1.89
8156 17 Beldar day 0.25 350.00 87.50
8157 Top layer 15 mm thick stone chipping plaster
8158 Quantity required = 0.172 cum including wastage
8159 Preparation of cement concrete mix 1:1/2:2 (1 cement : 1/2 coarse sand :
8170 2 stone chipping
8171 10 mm nominal size)
8172 2911 Stone chippings/ screenings 10/ 11.2 mm nominal cum 0.14 1150 161.00
8173 2202 size 0.00
8174 Carriage of Stone aggregate below 40 mm cum 0.14 106.13 14.86
8175 982 nominal size
8176 Coarse sand cum 0.04 1350 54
8177 2203 Carriage of Coarse sand cum 0.04 106.13 4.25
8178 367 Portland Cement (OPC-43 grade) tonne 0.1 4375 437.50
8179 2209 Carriage of Cement tonne 0.1 94.34 9.43
8180 17 Beldar day 0.1 350.00 35.00
8181 11 Bhisti day 0.05 350.00 17.50
8182 9999 Hire and running charges of mechanical mixer L.S. 4.29 2 8.58
8183 9999 Sundries L.S. 2.08 2 4.16
8184 LABOUR
8185 23 Mason (brick layer) 1st class Day 1.75 505.17 884.05
8186 17 Beldar Day 1.75 350.00 612.50
8187 11 Bhisti Day 0.3 350.00 105.00
8188 9999 Scaffolding L.S. 24.44 2 48.88
8189 Labour for washing
8190 23 Mason (brick layer) 1st class Day 1 505.17 505.17
8191 18 Coolie Day 0.5 350.00 175.00
8192 9999 Sundries soft brushes etc L.S. 25.22 2 50.44
8193 TOTAL 4726.48 W
8194 Add 1 % Water charges on "W" 47.2648
8195 TOTAL 4773.74 X
8196 Add GST (multiplying factor 0.1405) on "X" 670.71
8197 TOTAL 5444.45 Y
8198 Add 15 % Contractor's profit and overheads on "Y" 816.67
8199 Total 6261.12 Z
8200 Add Cess @ 1% on "Z" 62.61
8201 Cost of 10.00 sqm 6323.73
8202 Cost of 1.00 sqm 632.37
8203 Say 632.40
8204
8205
8206 13.73 Forming groove of uniform size in the top layer of
8207 washed
13.73.1 stone
15 mmgrit
wideplaster asmm
and 15 per deep
approved pattern using
groove
8208 wooden battens, nailed to the under layer, including removal
of wooden battens, repair to the edges of panels and
8209 Detail of cost for 30 mtrs
8220 Second class kail wood in plank
8221 30 x0.015 x0.015m =6.75cudm
8222 Wastage @ 10% = 0.68
8223 Total = 7.43 cudm
8224 Assuming that the battens shall become
8225 unserviceable after using 5 times
8226 Cost for using once = 7.43 / 5 = 1.48 cudm
8227 MATERIAL
8228 1198 Second class kail wood in planks 10 cudm 0.148 260 38.48
8229 9977 Carriage of wood L.S. 0.39 2 0.78
8230 Labour for making battens
8231 15 Carpenter 2nd class day 0.15 403.67 60.55
8232 17 Beldar day 0.15 350.00 52.50
8233 9999 Sundries L.S. 2.86 2 5.72
8234 Labour for nailing the battens to under layer and
8235 23 finishing and repairing grooves 0.00
8236 Mason (brick layer) 1st class day 0.7 476 333.2
8237 17 Beldar day 0.7 350.00 245.00
8238 9999 Nails and cement mortar L.S. 71.76 2 143.52
8239 TOTAL 879.75 W
8240 Add 1 % Water charges on "W" 8.7975
8241 TOTAL 888.55 X
8242 Add GST (multiplying factor 0.1405) on "X" 124.84
8243 TOTAL 1013.39 Y
8244 Add 15 % Contractor's profit and overheads on "Y" 152.01
8245 Total 1165.40 Z
8246 Add Cess @ 1% on "Z" 11.65
8247 Cost of 30.00 mtrs 1177.05
8248 Cost of 1.00 metre 39.23
8249 Say 39.20
8250
8251
8252 13.73.2 20 mm wide and 15 mm deep groove
8253 Detail of cost for 30 mtrs
8254 Second class kail wood in plank
8255 30 x0.02 x0.015m =9.00 cudm
8256 Wastage @ 10% = 0.90
8257 Total = 9.90 cudm
8258 Assuming that the battens shall become
8259 unserviceable after using 5 times
8260 Cost for using once = 9.9 / 5 = 1.98 cudm
8261 MATERIAL
8262 1198 Second class kail wood in planks 10 cudm 0.198 260 51.48
8263 9977 Carriage of wood L.S. 0.52 2 1.04
8264 Labour for making battens
8274 15 Carpenter 2nd class day 0.15 403.67 60.55
8275 17 Beldar day 0.15 350.00 52.50
8276 9999 Sundries L.S. 2.86 2 5.72
8277 Labour for nailing the battens to under layer and
8278 23 finishing and repairing grooves 0.00
8279 Mason (brick layer) 1st class day 0.7 476 333.2
8280 17 Beldar day 0.7 350.00 245.00
8281 9999 Nails and cement mortar L.S. 71.76 2 143.52
8282 TOTAL 893.01 W
8283 Add 1 % Water charges on "W" 8.9301
8284 TOTAL 901.94 X
8285 Add GST (multiplying factor 0.1405) on "X" 126.72
8286 TOTAL 1028.66 Y
8287 Add 15 % Contractor's profit and overheads on "Y" 154.30
8288 Total 1182.96 Z
8289 Add Cess @ 1% on "Z" 11.83
8290 Cost of 30.00 mtrs 1194.79
8291 Cost of 1.00 metre 39.83
8292 Say 39.80
8293
8294
8295 13.74 Extra for washed grit plaster on exterior walls of
8296 height
Detail of more than
cost for 10 m from ground level for every additional
10 sqm
8297 height
MATERIAL
of 3 m or part thereof.
8298 9999 Scaffolding L.S. 215.28 2 430.56
8299 23 Mason (brick layer) 1st class day 0.3 505.17 151.55
8300 17 Beldar day 0.3 350.00 105.00
8301 11 Bhisti day 0.15 350.00 52.50
8302 9999 Sundries L.S. 28.6 2 57.20
8303 TOTAL 796.81 W
8304 Add 1 % Water charges on "W" 7.9681
8305 TOTAL 804.78 X
8306 Add GST (multiplying factor 0.1405) on "X" 113.07
8307 TOTAL 917.85 Y
8308 Add 15 % Contractor's profit and overheads on "Y" 137.68
8309 Total 1055.53 Z
8310 Add Cess @ 1% on "Z" 10.56
8311 Cost of 10.00 sqm 1066.09
8312 Cost of 1.00 sqm 106.61
8313 Say 106.60
8314
8315
8324
8325 13.75 Extra for washed stone grit plaster on circular work
8326 not exceeding 6 m in radius (in two coats).
8327 Detail of cost for 10 sqm
8328 LABOUR
8329 0023 Mason (brick layer) 1st class day 0.5 476 238
8330 17 Beldar day 0.5 350.00 175.00
8331 9999 Sundries L.S. 53.82 2 107.64
8332 TOTAL 520.64 W
8333 Add 1 % Water charges on "W" 5.2064
8334 TOTAL 525.85 X
8335 Add GST (multiplying factor 0.1405) on "X" 73.88
8336 TOTAL 599.73 Y
8337 Add 15 % Contractor's profit and overheads on "Y" 89.96
8338 Total 689.69 Z
8339 Add Cess @ 1% on "Z" 6.90
8340 Cost of 10.00 sqm 696.59
8341 Cost of 1.00 sqm 69.66
8342 Say 69.70
8343
8344
8345 13.76 Forming groove of uniform size from 12x12 mm and
8346 upto 25x15 mm
Detail of cost for 30in the top layer of washed stone grit
mtrs
8347 plastered surface as per approved pattern, including
Aluminium channel section 15 x 15 x 2 mm
providing and fixing aluminum channels of appropriate size
8348 (weight 0.221 kg/mtr)
8349 Qty = 30 + 5% wastage = 31.5 m @ 0.221 kg/m =
8350 7306 6.96 kg. 0.00
8351 Aluminium T or L sections kilogram 6.96 190 1322.4
8352 9977 Carriage of timber Labour for fixing L.S. 38.98 2 77.96
8353 20 Assistant Fitter or 2nd class Fitter day 0.46 403.67 185.69
8354 17 Beldar day 0.15 350.00 52.50
8355 9999 Sundries L.S. 2.86 2 5.72
8356 9999 Nails and cement mortar L.S. 71.76 2 143.52
8357 TOTAL 1787.79 W
8358 Add 1 % Water charges on "W" 17.8779
8359 TOTAL 1805.67 X
8360 Add GST (multiplying factor 0.1405) on "X" 253.70
8361 TOTAL 2059.37 Y
8362 Add 15 % Contractor's profit and overheads on "Y" 308.91
8363 Total 2368.28 Z
8364 Add Cess @ 1% on "Z" 23.68
8365 Cost of 30.00 mtrs 2391.96
8366 Cost of 1.00 metre 79.73
8367 Say 79.70
8368
8376
8377 13.77 Extra for using white cement in place of ordinary
8378 cement in the top layer of the item of washed stone grit
8379 plaster.
Detail of cost for 10 sqm
8380 MATERIAL
8381 Add for
8382 368 White Cement tonne 0.1 11200 1120.00
8383 Deduct for ordinary cement
8384 367 Portland Cement (OPC-43 grade) tonne -0.1 4375 -437.50
8385 TOTAL 682.50 W
8386 Add 1 % Water charges on "W" 6.825
8387 TOTAL 689.33 X
8388 Add GST (multiplying factor 0.1405) on "X" 96.85
8389 TOTAL 786.18 Y
8390 Add 15 % Contractor's profit and overheads on "Y" 117.93
8391 Total 904.11 Z
8392 Add Cess @ 1% on "Z" 9.04
8393 Cost of 10.00 sqm 913.15
8394 Cost of 1.00 sqm 91.31
8395 Say 91.30
8396
8397
8398 13.78 Providing and applying 12 mm thick (average)
8399 premixed formulated one coat gypsum lightweight plaster
etc. complete.
8400 having additives and light weight aggregates as vermiculite/
perlite respectively conforming to IS: 2547 (Part - 1 & II) 1976,
8401 Detail of cost for 10 sqm
8402
8403 MATERIAL
8404 Premixed super white gypsum plaster @
8405 16.14kg /sqm = 61.40 + 5% wastage
8406 = 161.40+8.07= 169.47 kg
8407 868 Premixed super white gypsum plaster. kg 169.47 6 1016.82
8408 LABOUR
8409 40 Mason (average) day 1.2 403.67 484.40
8410 18 Coolie day 1.2 350.00 420.00
8420 9999 Scaffolding and sundries L.S. 12.61 2 25.22
8421 TOTAL 1946.44 W
8422 Add 1 % Water charges on "W" 19.4644
8423 TOTAL 1965.90 X
8424 Add GST (multiplying factor 0.1405) on "X" 276.21
8425 TOTAL 2242.11 Y
8426 Add 15 % Contractor's profit and overheads on "Y" 336.32
8427 Total 2578.43 Z
8428 Add Cess @ 1% on "Z" 25.78
8429 Cost of 10.00 sqm 2604.21
8430 Cost of 1.00 sqm 260.42
8431 Say 260.40
8432
8433
8434
8435 13.79 Extra for addition of synthetic Polyester triangular
8436 fibre of
Detail length
of cost 6 mm,
for per effective
bag of diameter
50 kg of cement used10-40 microns and
in mortar
8437 specific
MATERIAL
gravity of 1.34 to 1.40 in cement plaster/ mortar by
using 125 gms. of synthetic Polyester triangular fibre for 50
8438
8439 8733 Synthetic ployster triangular fibre of length 6 mm, kg 0.125 400 50.00
8440 effective diameter 10-40 microns and specific
8441 gravity of 1.34 to 1.40
8442 including labour for mixing
8443 TOTAL 50.00 W
8444 Add 1 % Water charges on "W" 0.5
8445 TOTAL 50.50 X
8446 Add GST (multiplying factor 0.1405) on "X" 7.10
8447 TOTAL 57.60 Y
8448 Add 15 % Contractor's profit and overheads on "Y" 8.64
8449 Total 66.24 Z
8450 Add Cess @ 1% on "Z" 0.66
8451 Cost per bag of cement 66.90
8452 Say 66.9
8453 66.90
8454
8455
8456 13.80 Providing and applying white cement based putty of
8457 average thickness
Detail of cost 1 mm, of approved brand and
for 10 sqm
8458 manufacturer,
MATERIAL
over the plastered wall surface to prepare the
surface even and smooth complete.
8468 824 Cement base wall care putty kg 14.58 13 189.54
8469 10x0.001x1429 = 14.29kg
8470 Add 2% wastage= 0.29kg
8471 Total = 14.58kg Say 14.58 kg
8472 9977 Carriage L.S. 3.9 2 7.80
8473 LABOUR
8474 22 Mason (for plaster of paris work) 1st class day 0.45 505.17 227.33
8475 17 Beldar day 0.45 350.00 157.50
8476 9999 Scaffolding and sundries L.S. 40 2 80.00
8477 TOTAL 662.17 W
8478 Add 1 % Water charges on "W" 6.6217
8479 TOTAL 668.79 X
8480 Add GST (multiplying factor 0.1405) on "X" 93.97
8481 TOTAL 762.76 Y
8482 Add 15 % Contractor's profit and overheads on "Y" 114.41
8483 Total 877.17 Z
8484 Add Cess @ 1% on "Z" 8.77
8485 Cost of 10.00 sqm 885.94
8486 Cost of 1.00 sqm 88.59
8487 Say 88.60
8488
8489
8490 13.81 Distempering with 1st quality acrylic distemper,
8491 having
achieve even(Volatile
VOC shade andOrganic Compound ) content less than
colour.
8492 50 grams/ litre, of approved brand and manufacture,
13.81.1 One coat applying additional coats wherever required, to
including
8493 Detail of cost for 10 sqm
8494 MATERIAL
8495 802 Acrylic distemper 1st quality , having VOC content Kg 0.62 36 22.32
8496 9999 less than 50 gm/kg 0.00
8497 Brushes, putty etc. L.S. 0.52 2 1.04
8498 9988 Sundries including carriage L.S. 10.79 2 21.58
8499 LABOUR
8500 31 Painter day 0.33 403.67 133.21
8501 18 Coolie day 0.17 350.00 59.50
8502 9999 Scaffolding and sundries L.S. 7.15 2 14.30
8503 TOTAL 251.95 W
8504 Add 1 % Water charges on "W" 2.5195
8505 TOTAL 254.47 X
8506 Add GST (multiplying factor 0.1405) on "X" 35.75
8507 TOTAL 290.22 Y
8508 Add 15 % Contractor's profit and overheads on "Y" 43.53
8509 Total 333.75 Z
8510 Add Cess @ 1% on "Z" 3.34
8511 Cost of 10.00 sqm 337.09
8512 Cost of 1.00 sqm 33.71
8513 Say 33.70
8514
8521
8522 13.81.2 Two coats
8523 Detail of cost for 10 sqm
8524 MATERIAL
8525 802 Acrylic distemper 1st quality, having VOC content Kg 0.99 36 35.64
8526 9999 less than 50 gm/kg 0.00
8527 Brushes, putty etc. L.S. 11.57 2 23.14
8528 9988 Sundries including carriage L.S. 4.42 2 8.84
8529 LABOUR
8530 31 Painter day 0.4 403.67 161.47
8531 18 Coolie day 0.46 350.00 161.00
8532 9999 Scaffolding and sundries L.S. 8.06 2 16.12
8533 TOTAL 406.21 W
8534 Add 1 % Water charges on "W" 4.0621
8535 TOTAL 410.27 X
8536 Add GST (multiplying factor 0.1405) on "X" 57.64
8537 TOTAL 467.91 Y
8538 Add 15 % Contractor's profit and overheads on "Y" 70.19
8539 Total 538.10 Z
8540 Add Cess @ 1% on "Z" 5.38
8541 Cost of 10.00 sqm 543.48
8542 Cost of 1.00 sqm 54.35
8543 Say 54.40
8544
8545
8546 13.82 Wall painting with acrylic emulsion paint, having VOC
8547 (Volatile
13.82.1 OneOrganic
coatCompound ) content less than 50 grams/
8548 litre, of approved brand and manufacture, including applying
additional coats wherever required, to achieve even shade
8549 Detail of cost for 10 sqm
8550 MATERIAL
8551 803 Acrylic emulsion , having VOC content less than litre 0.53 94 49.82
8552 9999 50 gm/ltr 0.00
8553 MATERIAL L.S. 0.52 2 1.04
8554 9977 Carriage of material L.S. 5.33 2 10.66
8555 LABOUR
8556 31 Painter day 0.36 403.67 145.32
8557 18 Coolie day 0.36 350.00 126.00
8568 9999 Brushes, sand paper etc. L.S. 8.06 2 16.12
8569 9999 Sundries L.S. 6.76 2 13.52
8570 TOTAL 362.48 W
8571 Add 1 % Water charges on "W" 3.6248
8572 TOTAL 366.10 X
8573 Add GST (multiplying factor 0.1405) on "X" 51.44
8574 TOTAL 417.54 Y
8575 Add 15 % Contractor's profit and overheads on "Y" 62.63
8576 Total 480.17 Z
8577 Add Cess @ 1% on "Z" 4.80
8578 Cost of 10.00 sqm 484.97
8579 Cost of 1.00 sqm 48.5
8580 Say 48.50
8581
8582
8583 13.82.2 Two coats
8584 Detail of cost for 10 sqm
8585 MATERIAL
8586 803 Acrylic emulsion , having VOC content less than litre 0.84 94 78.96
8587 9999 50 gm/ltr 0.00
8588 MATERIAL L.S. 1.43 2 2.86
8589 9977 Carriage of material L.S. 6.76 2 13.52
8590 LABOUR
8591 31 Painter day 0.54 403.67 217.98
8592 18 Coolie day 0.54 350.00 189.00
8593 9999 Brushes, sand paper etc. L.S. 10.79 2 21.58
8594 9999 Sundries L.S. 6.76 2 13.52
8595 TOTAL 537.42 W
8596 Add 1 % Water charges on "W" 5.3742
8597 TOTAL 542.79 X
8598 Add GST (multiplying factor 0.1405) on "X" 76.26
8599 TOTAL 619.05 Y
8600 Add 15 % Contractor's profit and overheads on "Y" 92.86
8601 Total 711.91 Z
8602 Add Cess @ 1% on "Z" 7.12
8603 Cost of 10.00 sqm 719.03
8604 Cost of 1.00 sqm 71.9
8605 Say 71.90
8606
8607
8608 13.83 Wall painting with premium acrylic emulsion paint of
8609 interior
13.83.1 grade,
One coathaving VOC (Volatile Organic Compound )
8619 content less than 50 grams/ litre of approved brand and
Detail of cost for 10 sqm
manufacture, including applying additional coats wherever
8620 MATERIAL
8621 804 Premium acrylic emulsion of interior grade, having litre 0.38 220 83.60
8622 9999 VOC content less than 50 gm/ltr. 0.00
8623 MATERIAL L.S. 0.52 2 1.04
8624 9977 Carriage of material L.S. 0.91 2 1.82
8625 LABOUR
8626 31 Painter day 0.36 403.67 145.32
8627 18 Coolie day 0.36 350.00 126.00
8628 9999 Brushes, sand paper etc. L.S. 8.06 2 16.12
8629 9999 Sundries L.S. 6.76 2 13.52
8630 TOTAL 387.42 W
8631 Add 1 % Water charges on "W" 3.8742
8632 TOTAL 391.29 X
8633 Add GST (multiplying factor 0.1405) on "X" 54.98
8634 TOTAL 446.27 Y
8635 Add 15 % Contractor's profit and overheads on "Y" 66.94
8636 Total 513.21 Z
8637 Add Cess @ 1% on "Z" 5.13
8638 Cost of 10.00 sqm 518.34
8639 Cost of 1.00 sqm 51.83
8640 Say 51.80
8641
8642 13.83.2 Two coats
8643 Detail of cost for 10 sqm
8644 MATERIAL
8645 804 Premium acrylic emulsion of interior grade, having litre 0.6 220 132.00
8646 9999 VOC content less than 50 gm/ltr. 0.00
8647 MATERIAL L.S. 1.43 2 2.86
8648 9977 Carriage of material L.S. 6.76 2 13.52
8649 LABOUR
8650 31 Painter day 0.54 403.67 217.98
8651 18 Coolie day 0.54 350.00 189.00
8652 9999 Brushes, sand paper etc. L.S. 10.79 2 21.58
8653 9999 Sundries L.S. 6.76 2 13.52
8654 TOTAL 590.46 W
8655 Add 1 % Water charges on "W" 5.9046
8656 TOTAL 596.36 X
8657 Add GST (multiplying factor 0.1405) on "X" 83.79
8658 TOTAL 680.15 Y
8659 Add 15 % Contractor's profit and overheads on "Y" 102.02
8660 Total 782.17 Z
8661 Add Cess @ 1% on "Z" 7.82
8662 Cost of 10.00 sqm 789.99
8663 Cost of 1.00 sqm 79
8664 Say 79.00
8665
8666
8675
8676
8677
8678 13.85 Applying priming coats with primer of approved
8679 brand and manufacture,
13.85.1 With having
ready mixed low
pink or VOC
grey (Volatile
primer Organic
on wood work
8680 Compound
(hard and ) content.
soft wood)
having VOC content less than 50 grams/ litre
8681
8682 Detail of cost for 10 sqm
8683
8684 MATERIAL
8685 806 Ready mixed pink or grey primer on wood work litre 0.75 105 78.75
8686 (hard and soft wood) having VOC content less
8687 9999 than 50 gms/lit. 0.00
8688 Putty L.S. 2.73 2 5.46
8689 9977 Carriage of material L.S. 0.39 2 0.78
8690 LABOUR
8691 31 Painter day 0.25 403.67 100.92
8692 18 Coolie day 0.25 350.00 87.50
8693 9999 Brushes, sand paper etc. L.S. 5.33 2 10.66
8694 9999 Sundries L.S. 10.79 2 21.58
8695 TOTAL 305.65 W
8696 Add 1 % Water charges on "W" 3.0565
8697 TOTAL 308.71 X
8698 Add GST (multiplying factor 0.1405) on "X" 43.37
8699 TOTAL 352.08 Y
8700 Add 15 % Contractor's profit and overheads on "Y" 52.81
8701 Total 404.89 Z
8702 Add Cess @ 1% on "Z" 4.05
8703 Cost of 10.00 sqm 408.94
8704 Cost of 1.00 sqm 40.89
8705 Say 40.90
8706
8707
8708
8709 13.85.3 With water thinnable cement primer on wall surface
8710 having VOC content
Detail of cost for 10 sqm less than 50 grams/litre
8711 MATERIAL
8712 808 Water thinnable cement primer for interior wall litre 0.7 50 35.00
8713 9977 surface, having VOC content less than 50 gms/lit. 2 0.00
8714 Carriage of material L.S. 8.06 2 16.12
8715 LABOUR
8716 31 Painter day 0.4 403.67 161.47
8717 18 Coolie day 0.2 350.00 70.00
8718 9999 Brushes, sand paper etc. L.S. 7.15 2 14.30
8719 TOTAL 296.89 W
8720 Add 1 % Water charges on "W" 2.9689
8721 TOTAL 299.86 X
8722 Add GST (multiplying factor 0.1405) on "X" 42.13
8723 TOTAL 341.99 Y
8724 Add 15 % Contractor's profit and overheads on "Y" 51.30
8725 Total 393.29 Z
8726 Add Cess @ 1% on "Z" 3.93
8727 Cost of 10.00 sqm 397.22
8728 Cost of 1.00 sqm 39.72
8729 Say 39.70
8730
8740
8741 13.86 6 mm plaster on cement concrete or reinforced
8742 cement concrete work with white cement based polymer
8743 modified self curing mortar of approved make as per the
Detail of cost for 10 sqm
direction of Engineer-In-Charge.
8744 MATERIAL
8745 772 White cement based polymer modified self curing kg 46 15 690.00
8746 9977 compound in powder form i/c 2% wastage 2 0.00
8747 Carriage of white cement based polymer modified L.S. 7.8 2 15.6
8748 self curing compound in
8749 powder form
8750 LABOUR
8751 40 Mason (average) day 0.51 403.67 205.87
8752 18 Coolie day 0.75 350.00 262.50
8753 9999 Extra for removing burrs, cleaning with wire L.S. 13.39 2 26.78
8754 9999 brushes and pock making with pointed tools etc. 0.00
8755 Scaffolding and sunderies L.S. 11.7 2
8756 TOTAL 1202.75 W
8757 Add 1 % Water charges on "W" 12.0275
8758 TOTAL 1214.78 X
8759 Add GST (multiplying factor 0.1405) on "X" 170.68
8760 TOTAL 1385.46 Y
8761 Add 15 % Contractor's profit and overheads on "Y" 207.82
8762 Total 1593.28 Z
8763 Add Cess @ 1% on "Z" 15.93
8764 Cost of 10.00 sqm 1609.21
8765 Cost of 1.00 sqm 160.92
8766 Say 160.90
8767
8768
8769 13.87 White washing with lime to give an even shade :
8770 13.87.1 Old work (two or more coats)
8771
8772 Detail of cost for 10 sqm
8773 MATERIAL
8774 775 Dehradun white lime quintal 0.02 600 12.00
8775 9977 Carriage of lime L.S. 0.52 2 1.04
8776 LABOUR
8777 38 White Washer day 0.11 350.00 38.50
8778
8779
8781 18 Coolie day 0.06 350.00 21.00
8782 9999 Indigo gum etc L.S. 2.73 2 5.46
8783 9999 Sundries ladders etc L.S. 2.73 2 5.46
8784 TOTAL 83.46 W
8785 Add 1 % Water charges on "W" 0.8346
8786 TOTAL 84.29 X
8787 Add GST (multiplying factor 0.1405) on "X" 11.84
8788 TOTAL 96.13 Y
8789 Add 15 % Contractor's profit and overheads on "Y" 14.42
8790 Total 110.55 Z
8791 Add Cess @ 1% on "Z" 1.11
8792 Cost of 10.00 sqm 111.66
8793 Cost of 1.00 sqm 11.17
8794 Say 11.20
8795
8796
8797 13.87.2 Old work (one or more coats)
8798 Detail of cost for 10 sqm
8799 MATERIAL
8800 775 Dehradun white lime quintal 0.01 600 6.00
8801 9977 Carriage of lime L.S. 0.52 2 1.04
8802 LABOUR
8803 38 White Washer day 0.07 350.00 24.50
8804 18 Coolie day 0.03 350.00 10.50
8805 9999 Indigo gum etc L.S. 2.08 2 4.16
8806 9999 Sundries ladders etc L.S. 2.73 2 5.46
8807 TOTAL 51.66 W
8808 Add 1 % Water charges on "W" 0.5166
8809 TOTAL 52.18 X
8810 Add GST (multiplying factor 0.1405) on "X" 7.33
8811 TOTAL 59.51 Y
8812 Add 15 % Contractor's profit and overheads on "Y" 8.93
8813 Total 68.44 Z
8814 Add Cess @ 1% on "Z" 0.68
8815 Cost of 10.00 sqm 69.12
8816 Cost of 1.00 sqm 6.91
8817 Say 6.90
8818
8819
8820 13.88 Removing white or colour wash by scrapping and
8821 sand papering
complete and preparing the surface smooth including
8822 necessary repairs to scratches etc.
8823 Details of cost for 10 sqm.
8825 LABOUR
8826 17 Beldar day 0.09 350.00 31.50
8827 18 Coolie day 0.04 350.00 14.00
8836 11 Bhisti day 0.04 350.00 14.00
8837 9999 Sundries such as sand paper and scrapper L.S. 2.73 2 5.46
8838 9999 Repair to scraches L.S. 1.82 2 3.64
8839 TOTAL 68.60 W
8840 Add 1 % Water charges on "W" 0.686
8841 TOTAL 69.29 X
8842 Add GST (multiplying factor 0.1405) on "X" 9.73
8843 TOTAL 79.02 Y
8844 Add 15 % Contractor's profit and overheads on "Y" 11.85
8845 Total 90.87 Z
8846 Add Cess @ 1% on "Z" 0.91
8847 Cost of 10.00 sqm 91.78
8848 Cost of 1.00 sqm 9.18
8849 Say 9.20
8850
8851
8852 13.89 Distempering with dry distemper of approved brand
8853 and manufacture (one or more coats) and of required shade
Details of cost for 10 sqm.
8854 on old work to give an even shade.
MATERIAL
8855 815 Dry distemper kilogram 1 30 30.00
8856 9977 Carriage of distemper L.S. 0.91 2 1.82
8857 9999 Brushes, sand-paper etc. L.S. 5.33 2 10.66
8858 LABOUR
8859 31 Painter day 0.33 403.67 133.21
8860 18 Coolie day 0.17 350.00 59.50
8861 9999 Sundries L.S. 4.42 2 8.84
8862 TOTAL 244.03 W
8863 Add 1 % Water charges on "W" 2.4403
8864 TOTAL 246.47 X
8865 Add GST (multiplying factor 0.1405) on "X" 34.63
8866 TOTAL 281.10 Y
8867 Add 15 % Contractor's profit and overheads on "Y" 42.17
8868 Total 323.27 Z
8869 Add Cess @ 1% on "Z" 3.23
8870 Cost of 10.00 sqm 326.50
8871 Cost of 1.00 sqm 32.65
8872 Say 32.70
8873
8874
8875 13.9 Distempering with oil bound washable distemper of
8876 approved brand
13.90.1 Old workand manufacture
(one to give an even shade :
or more coats)
8877 Details of cost for 10 sqm.
8888 MATERIAL
8889 816 Oil bound washable distemper/ Acrylic distemper kilogram 1 50 50.00
8890 9999 Brushes, putty etc. L.S. 0.52 2 1.04
8891 9988 Sundries including carriage L.S. 10.79 2 21.58
8892 LABOUR
8893 31 Painter day 0.33 403.67 133.21
8894 18 Coolie day 0.17 350.00 59.50
8895 9999 Sundries L.S. 7.15 2 14.30
8896 TOTAL 279.63 W
8897 Add 1 % Water charges on "W" 2.7963
8898 TOTAL 282.43 X
8899 Add GST (multiplying factor 0.1405) on "X" 39.68
8900 TOTAL 322.11 Y
8901 Add 15 % Contractor's profit and overheads on "Y" 48.32
8902 Total 370.43 Z
8903 Add Cess @ 1% on "Z" 3.70
8904 Cost of 10.00 sqm 374.13
8905 Cost of 1.00 sqm 37.41
8906 Say 37.40
8907
8908
8909 13.91 Removing dry or oil bound distemper, water proofing
8910 cement paint
necessary and the
repairs like by scrapping,
to scratches sand papering and
etc. complete.
8911 preparing the surface smooth including
8912 Details of cost for 10 sqm.
8913 LABOUR
8914 17 Beldar day 0.11 350.00 38.50
8915 18 Coolie day 0.05 350.00 17.50
8916 11 Bhisti day 0.05 350.00 17.50
8917 9999 Scrapper, sand paper etc. L.S. 6.24 2 12.48
8918 9999 Sundries including mortar to repair the surface L.S. 1.82 2 3.64
8919 TOTAL 89.62 W
8920 Add 1 % Water charges on "W" 0.8962
8921 TOTAL 90.52 X
8922 Add GST (multiplying factor 0.1405) on "X" 12.72
8923 TOTAL 103.24 Y
8924 Add 15 % Contractor's profit and overheads on "Y" 15.49
8925 Total 118.73 Z
8926 Add Cess @ 1% on "Z" 1.19
8927 Cost of 10.00 sqm 119.92
8928 Cost of 1.00 sqm 11.99
8929 Say 12.00
8930
8931 13.92 Painting on G.S. sheet with synthetic enamel paint of
8941 approved brand
13.92.1 Old workand manufacture
(one of required colour to give
or more coats)
8942 an even shade :
8943 Details of cost for 10 sqm.
8944 MATERIAL
8945 845 Roofing paint for iron sheets in red colour litre 0.46 120 55.20
8946 9977 Carriage L.S. 0.52 2 1.04
8947 LABOUR
8948 31 Painter day 0.36 403.67 145.32
8949 18 Coolie day 0.36 350.00 126.00
8950 9999 Putty, brushes sand paper etc. L.S. 6.76 2 13.52
8951 9999 Sundries L.S. 8.06 2 16.12
8952 TOTAL 357.20 W
8953 Add 1 % Water charges on "W" 3.572
8954 TOTAL 360.77 X
8955 Add GST (multiplying factor 0.1405) on "X" 50.69
8956 TOTAL 411.46 Y
8957 Add 15 % Contractor's profit and overheads on "Y" 61.72
8958 Total 473.18 Z
8959 Add Cess @ 1% on "Z" 4.73
8960 Cost of 10.00 sqm 477.91
8961 Cost of 1.00 sqm 47.79
8962 Say 47.80
8963
8964
8965 13.93 Painting (two or more coats) on rain water, soil, waste
8966 and vent75
13.93.1 pipes
mm and fittings
diameter with black anticorrosive
pipes
8967 bitumastic paint of approved brand and manufacture over
and including a priming coat of ready mixed zinc chromate
8968 Detail of cost for 30 metres
8969 Area=22/7 x0.0814m x30m =7.67 sqm
8970 MATERIAL
8971 4202 Red oxide Zinc chromate primer litre 0.41 110 45.10
8972 9977 Carraige L.S. 0.39 2 0.78
8973 LABOUR
8974 31 Painter day 0.18 403.67 72.66
8975 18 Coolie day 0.18 350.00 63.00
8976 9999 Brushes, sand paper etc L.S. 8.19 2 16.38
8977 MATERIAL
8978 828 Anticorrosive bituminous paint (black) litre 0.73 100 73.00
8979 9977 Carraige L.S. 1.04 2 2.08
8989 LABOUR
8990 31 Painter day 0.41 403.67 165.50
8991 18 Coolie day 0.41 350.00 143.50
8992 9999 Putty, sand paper etc L.S. 4.16 2 8.32
8993 9999 Sundries L.S. 6.24 2 12.48
8994 9999 Wire brushes for cleaning L.S. 4.42 2 8.84
8995 9999 Extra for delays L.S. 40.3 2 80.60
8996 TOTAL 692.24 W
8997 Add 1 % Water charges on "W" 6.9224
8998 TOTAL 699.16 X
8999 Add GST (multiplying factor 0.1405) on "X" 98.23
9000 TOTAL 797.39 Y
9001 Add 15 % Contractor's profit and overheads on "Y" 119.61
9002 Total 917.00 Z
9003 Add Cess @ 1% on "Z" 9.17
9004 Cost of 30.00 metres 926.17
9005 Cost of 1.00 metre 30.87
9006 Say 30.90
9007
9008
9009 13.94 Painting (one or more coats) on rain water, soil, waste
9010 and vent pipes
manufacture onand
old fittings
work : with black anticorrosive
9011 bitumastic paint of approved brand and
13.94.1 75 mm diameter pipes
9012 Detail of cost for 30 metres
9013 Area=22/7 x0.0814m x30m =7.67 sqm
9014 MATERIAL
9015 828 Anticorrosive bituminous paint (black) litre 0.43 100 43.00
9016 9977 Carriage L.S. 0.39 2 0.78
9017 LABOUR
9018 31 Painter day 0.27 403.67 108.99
9019 18 Coolie day 0.27 350.00 94.50
9020 9999 Putty, sand paper etc L.S. 4.16 2 8.32
9021 9999 Sundries L.S. 6.24 2 12.48
9022 9999 Wire brushes for cleaning L.S. 4.42 2 8.84
9023 9999 Extra for delays L.S. 26.91 2 53.82
9024 TOTAL 330.73 W
9025 Add 1 % Water charges on "W" 3.3073
9026 TOTAL 334.04 X
9027 Add GST (multiplying factor 0.1405) on "X" 46.93
9028 TOTAL 380.97 Y
9029 Add 15 % Contractor's profit and overheads on "Y" 57.15
9030 Total 438.12 Z
9031 Add Cess @ 1% on "Z" 4.38
9032 Cost of 30.00 metres 442.50
9033 Cost of 1.00 metre 14.75
9034 Say 14.80
9035
9036
9043
9044 13.94.2 100 mm diameter pipes
9045
9046 Details of cost for 30 metres
9047 Area = 22/7x106.4 mmx30 m = 10.032 sqm
9048 MATERIAL
9049 828 Anticorrosive bituminous paint (black) litre 0.57 100 57.00
9050 9977 Carriage L.S. 0.52 2 1.04
9051 LABOUR
9052 31 Painter day 0.36 403.67 145.32
9053 18 Coolie day 0.36 350.00 126.00
9054 9999 Putty, sand paper brushes etc. L.S. 5.33 2 10.66
9055 9999 Sundries L.S. 8.06 2 16.12
9056 9999 Wire brushes for cleaning L.S. 5.33 2 10.66
9057 9999 Extra for delay L.S. 34.06 2 68.12
9058 TOTAL 434.92 W
9059 Add 1 % Water charges on "W" 4.3492
9060 TOTAL 439.27 X
9061 Add GST (multiplying factor 0.1405) on "X" 61.72
9062 TOTAL 500.99 Y
9063 Add 15 % Contractor's profit and overheads on "Y" 75.15
9064 Total 576.14 Z
9065 Add Cess @ 1% on "Z" 5.76
9066 Cost of 30.00 metres 581.90
9067 Cost of 1.00 metre 19.4
9068 Say 19.40
9069
9070
9071 13.94.3 150 mm diameter pipes
9072 Details of cost for 30 metres
9073 Area = 22/7x157.2 mmx30 m = 14.82 sqm
9074 MATERIAL
9075 828 Anticorrosive bituminous paint (black) litre 0.85 100 85.00
9076 9977 Carriage L.S. 0.65 2 1.30
9077 LABOUR
9078 31 Painter day 0.53 403.67 213.95
9079 18 Coolie day 0.53 350.00 185.50
9080 9999 Putty, sand paper brushes etc. L.S. 8.06 2 16.12
9081 9999 Sundries L.S. 11.96 2 23.92
9082 9999 Wire brushes for cleaning L.S. 7.14 2 14.28
9083 9999 Extra for delay L.S. 40.3 2 80.60
9094 TOTAL 620.67 W
9095 Add 1 % Water charges on "W" 6.2067
9096 TOTAL 626.88 X
9097 Add GST (multiplying factor 0.1405) on "X" 88.08
9098 TOTAL 714.96 Y
9099 Add 15 % Contractor's profit and overheads on "Y" 107.24
9100 Total 822.20 Z
9101 Add Cess @ 1% on "Z" 8.22
9102 Cost of 30.00 metres 830.42
9103 Cost of 1.00 metre 27.68
9104 Say 27.70
9105
9106
9107 13.95 Painting (two or more coats) on rain water, soil, waste
9108 and vent
13.95.1 75pipes
mm and fittings
diameter with aluminium paint of approved
pipes
9109 brand and manufacture over a priming coat of ready mixed
zinc chromate yellow primer on new work :
9110 Detail of cost for 30 metres
9111 Area=22/7 x0.0814m x30m =7.67 sqm
9112 MATERIAL
9113 4202 Red oxide Zinc chromate primer litre 0.41 110 45.10
9114 9977 Carriage L.S. 0.39 2 0.78
9115 LABOUR
9116 31 Painter day 0.18 403.67 72.66
9117 18 Coolie day 0.18 350.00 63.00
9118 9999 Sundries L.S. 8.19 2 16.38
9119 MATERIAL
9120 826 Aluminium paint litre 0.61 150 91.50
9121 9977 Carriage L.S. 1.04 2 2.08
9122 9999 Putty, sand paper etc L.S. 4.16 2 8.32
9123 LABOUR
9124 31 Painter day 0.41 403.67 165.50
9125 18 Coolie day 0.41 350.00 143.50
9126 9999 Sundries L.S. 5.2 2 10.40
9127 9999 Wire brushes for cleaning L.S. 9.1 2 18.20
9128 9999 Extra for delays L.S. 44.85 2 89.70
9129 TOTAL 727.12 W
9130 Add 1 % Water charges on "W" 7.2712
9131 TOTAL 734.39 X
9132 Add GST (multiplying factor 0.1405) on "X" 103.18
9133 TOTAL 837.57 Y
9134 Add 15 % Contractor's profit and overheads on "Y" 125.64
9135 Total 963.21 Z
9136 Add Cess @ 1% on "Z" 9.63
9137 Cost of 30.00 metres 972.84
9138 Cost of 1.00 metre 32.43
9139 Say 32.40
9140
9141
9149 13.95.2 100 mm diameter pipes
9150
9151 Detail of cost for 30 metres
9152 Area=22/7 x106.4x30m =10.032sqm
9153 MATERIAL
9154 4202 Red oxide Zinc chromate primer litre 0.54 110 59.40
9155 9977 Carriage L.S. 0.52 2 1.04
9156 LABOUR
9157 31 Painter day 0.24 403.67 96.88
9158 0.18 x 10.032 / 7.67 = 0.24
9159 18 Coolie day 0.24 350.00 84.00
9160 9999 Sundries MATERIAL L.S. 10.79 2 21.58
9161 826 Aluminium paint litre 1.16 150 174.00
9162 0.61 x 10.032 / 7.67 = 0.80
9163 9977 Carriage L.S. 1.43 2 2.86
9164 9999 Putty, sand paper etc L.S. 5.33 2 10.66
9165 LABOUR
9166 31 Painter day 0.54 403.67 217.98
9167 0.41 x 10.032 / 7.67 = 0.54
9168 18 Coolie day 0.54 350.00 189.00
9169 9999 Sundries L.S. 6.76 2 13.52
9170 9999 Wire brushes for cleaning L.S. 11.96 2 23.92
9171 9999 Extra for delays L.S. 66.43 2 132.86
9172 TOTAL 1027.70 W
9173 Add 1 % Water charges on "W" 10.277
9174 TOTAL 1037.98 X
9175 Add GST (multiplying factor 0.1405) on "X" 145.84
9176 TOTAL 1183.82 Y
9177 Add 15 % Contractor's profit and overheads on "Y" 177.57
9178 Total 1361.39 Z
9179 Add Cess @ 1% on "Z" 13.61
9180 Cost of 30.00 metres 1375.00
9181 Cost of 1.00 metre 45.83
9182 Say 45.80
9183
9184
9185 13.95.3 150 mm diameter pipes
9195 Detail of cost for 30 metres
9196 Area=22/7 x157.12x30m =14.82 sqm
9197 MATERIAL
9198 4202 Red oxide Zinc chromate primer litre 0.8 110 88.00
9199 9977 Carriage L.S. 0.65 2 1.30
9200 LABOUR
9201 31 Painter Day 0.36 403.67 145.32
9202 0.18 x 14.82 / 7.67 = 0.36
9203 18 Coolie Day 0.36 350.00 126.00
9204 9999 Sundries L.S. 15.99 2 31.98
9205 MATERIAL
9206 826 Aluminium paint litre 1.72 150 258.00
9207 0.61 x 14.82 / 7.67 = 1.72
9208 9977 Carriage L.S. 2.08 2 4.16
9209 9999 Putty, sand paper etc L.S. 7.93 2 15.86
9210 LABOUR
9211 31 Painter day 0.8 403.67 322.94
9212 0.41 x 14.82 / 7.67 = 0.80
9213 18 Coolie day 0.8 350.00 280.00
9214 9999 Sundries L.S. 10.01 2 20.02
9215 9999 Wire brushes for cleaning L.S. 17.81 2 35.62
9216 9999 Extra for delays L.S. 101.4 2 202.80
9217 TOTAL 1532.00 W
9218 Add 1 % Water charges on "W" 15.32
9219 TOTAL 1547.32 X
9220 Add GST (multiplying factor 0.1405) on "X" 217.40
9221 TOTAL 1764.72 Y
9222 Add 15 % Contractor's profit and overheads on "Y" 264.71
9223 Total 2029.43 Z
9224 Add Cess @ 1% on "Z" 20.29
9225 Cost of 30.00 metres 2049.72
9226 Cost of 1.00 metre 68.32
9227 Say 68.30
9228
9229
9230 13.96 Painting (one or more coats) on rain water, soil, waste
9231 and vent colour
required pipes and fittings
on old workwith
: synthetic enamel paint of
9232 approved brand and manufacture and
9233 13.96.1 75 mm diameter pipes
9234
9235 Details of cost for 30 metres
9236
9237 Area = 22/7x0.0814 mmx30 m = 7.67 sqm
9238
9239 MATERIAL
9249 826 Aluminium paint litre 0.35 150 52.50
9250 9999 Putty, sand paper etc. L.S. 0.39 2 0.78
9251 9977 Carriage L.S. 2.08 2 4.16
9252 LABOUR
9253 31 Painter day 0.28 403.67 113.03
9254 18 Coolie day 0.28 350.00 98.00
9255 9999 Putty, sand paper brushes etc. L.S. 4.16 2 8.32
9256 9999 Sundries L.S. 6.24 2 12.48
9257 9999 Wire brushes for cleaning L.S. 4.42 2 8.84
9258 9999 Extra for delay L.S. 26.91 2 53.82
9259 TOTAL 351.93 W
9260 Add 1 % Water charges on "W" 3.5193
9261 TOTAL 355.45 X
9262 Add GST (multiplying factor 0.1405) on "X" 49.94
9263 TOTAL 405.39 Y
9264 Add 15 % Contractor's profit and overheads on "Y" 60.81
9265 Total 466.20 Z
9266 Add Cess @ 1% on "Z" 4.66
9267 Cost of 30.00 metres 470.86
9268 Cost of 1.00 metre 15.7
9269 Say 15.70
9270
9271 13.96.2 100 mm diameter pipes
9272
9273 Details of cost for 30 metres
9274 Area = 22/7x106.4 mmx30 m = 10.032 sqm
9275 MATERIAL
9276 826 Aluminium paint litre 0.46 150 69.00
9277 9999 Putty, sand paper etc. L.S. 0.52 2 1.04
9278 9977 Carriage L.S. 2.73 2 5.46
9279 LABOUR
9280 31 Painter day 0.36 403.67 145.32
9281 18 Coolie day 0.36 350.00 126.00
9282 9999 Putty, sand paper brushes etc. L.S. 5.33 2 10.66
9283 9999 Sundries L.S. 8.06 2 16.12
9284 9999 Wire brushes for cleaning L.S. 5.33 2 10.66
9285 9999 Extra for delay L.S. 34.06 2 68.12
9286 TOTAL 452.38 W
9287 Add 1 % Water charges on "W" 4.5238
9288 TOTAL 456.90 X
9289 Add GST (multiplying factor 0.1405) on "X" 64.19
9290 TOTAL 521.09 Y
9291 Add 15 % Contractor's profit and overheads on "Y" 78.16
9292 Total 599.25 Z
9293 Add Cess @ 1% on "Z" 5.99
9294 Cost of 30.00 metres 605.24
9295 Cost of 1.00 metre 20.17
9296 Say 20.20
9297
9304
9305
9306
9307 13.96.3 150 mm diameter pipes
9308 Details of cost for 30 metres
9309 Area = 22/7x157.2 mmx30 m = 14.82 sqm
9310 MATERIAL
9311 826 Aluminium paint litre 0.68 150 102.00
9312 9999 Putty, sand paper etc. L.S. 0.65 2 1.30
9313 9977 Carriage L.S. 3.9 2 7.80
9314 LABOUR
9315 31 Painter day 0.53 403.67 213.95
9316 18 Coolie day 0.53 350.00 185.50
9317 9999 Putty, sand paper brushes etc. L.S. 7.93 2 15.86
9318 9999 Sundries L.S. 11.96 2 23.92
9319 9999 Wire brushes for cleaning L.S. 7.15 2 14.30
9320 9999 Extra for delay L.S. 40.3 2 80.60
9321 TOTAL 645.23 W
9322 Add 1 % Water charges on "W" 6.4523
9323 TOTAL 651.68 X
9324 Add GST (multiplying factor 0.1405) on "X" 91.56
9325 TOTAL 743.24 Y
9326 Add 15 % Contractor's profit and overheads on "Y" 111.49
9327 Total 854.73 Z
9328 Add Cess @ 1% on "Z" 8.55
9329 Cost of 30.00 metres 863.28
9330 Cost of 1.00 metre 28.78
9331 Say 28.80
9332
9333
9334 13.97 Painting with oil type wood preservative of approved
9335 brand and
13.97.1 Oldmanufacture:
work (one or more coats)
9336
9337 Detail of cost for 10 sqm
9338 MATERIAL
9339 859 Oil type wood preservative litre 0.81 130 105.30
9340 9977 Carriage of material L.S. 0.52 2 1.04
9341 LABOUR
9342 31 Painter day 0.11 403.67 44.40
9343 18 Coolie day 0.11 350.00 38.50
9354 9999 Brushes etc L.S. 2.73 2 5.46
9355 9999 Sundries L.S. 2.73 2 5.46
9356 TOTAL 200.16 W
9357 Add 1 % Water charges on "W" 2.0016
9358 TOTAL 202.16 X
9359 Add GST (multiplying factor 0.1405) on "X" 28.40
9360 TOTAL 230.56 Y
9361 Add 15 % Contractor's profit and overheads on "Y" 34.58
9362 Total 265.14 Z
9363 Add Cess @ 1% on "Z" 2.65
9364 Cost of 10.00 sqm 267.79
9365 Cost of 1.00 sqm 26.78
9366 Say 26.80
9367
9368
9369 13.98 Wall painting with plastic emulsion paint of approved
9370 brand and
13.98.1 Onemanufacture to give
or more coats an even
on old work shade:
9371
9372 Detail of cost for 10 sqm
9373 MATERIAL
9374 835 Plastic emulsion paint litre 0.73 200 146.00
9375 9999 Material for filling holes and cracks (putty etc.) L.S. 0.52 2 1.04
9376 9977 Carriage of material L.S. 5.33 2 10.66
9377 LABOUR
9378 31 Painter day 0.36 403.67 145.32
9379 18 Coolie day 0.36 350.00 126.00
9380 9999 Brushes, sand paper etc L.S. 8.06 2 16.12
9381 9999 Sundries L.S. 6.76 2 13.52
9382 TOTAL 458.66 W
9383 Add 1 % Water charges on "W" 4.5866
9384 TOTAL 463.25 X
9385 Add GST (multiplying factor 0.1405) on "X" 65.09
9386 TOTAL 528.34 Y
9387 Add 15 % Contractor's profit and overheads on "Y" 79.25
9388 Total 607.59 Z
9389 Add Cess @ 1% on "Z" 6.08
9390 Cost of 10.00 sqm 613.67
9391 Cost of 1.00 sqm 61.37
9392 Say 61.40
9393
9404
9405 13.99 Painting with synthetic enamel paint of approved
9406 brand and manufacture of required colour to give an even
9407 shade :
13.99.1 One or more coats on old work
9408
9409 Detail of cost for 10 sqm
9410 MATERIAL
9411 833 Synthetic enamel paint in black or chocolate litre 0.7 170 119.00
9412 shade
9413 9977 Carriage of paint and materials L.S. 0.52 2 1.04
9414 LABOUR
9415 31 Painter day 0.36 403.67 145.32
9416 18 Coolie day 0.36 350.00 126.00
9417 9999 Putty L.S. 2.73 2 5.46
9418 9999 Brushes sand paper etc. L.S. 5.33 2 10.66
9419 9999 Sundries L.S. 8.06 2 16.12
9420 TOTAL 423.60 W
9421 Add 1 % Water charges on "W" 4.236
9422 TOTAL 427.84 X
9423 Add GST (multiplying factor 0.1405) on "X" 60.11
9424 TOTAL 487.95 Y
9425 Add 15 % Contractor's profit and overheads on "Y" 73.19
9426 Total 561.14 Z
9427 Add Cess @ 1% on "Z" 5.61
9428 Cost of 10.00 sqm 566.75
9429 Cost of 1.00 sqm 56.67
9430 Say 56.70
9431
9432
9433
9434 13.1 Painting with aluminium paint of approved brand and
9435 manufacture
13.100.1 One to
or give
morean evenon
coats shade:
old work
9436 Detail of cost for 10 sqm
9437 MATERIAL
9438 826 Aluminium paint litre 0.46 150 69.00
9439 9977 Carriage of paint and material L.S. 0.52 2 1.04
9440 9999 Putty etc L.S. 2.73 2 5.46
9441 LABOUR
9442 31 Painter day 0.36 403.67 145.32
9443 18 Coolie day 0.36 350.00 126.00
9444 9999 Brushes, sand paper etc L.S. 5.33 2 10.66
9445 9999 Sundries L.S. 8.06 2 16.12
9455 TOTAL 373.60 W
9456 Add 1 % Water charges on "W" 3.736
9457 TOTAL 377.34 X
9458 Add GST (multiplying factor 0.1405) on "X" 53.02
9459 TOTAL 430.36 Y
9460 Add 15 % Contractor's profit and overheads on "Y" 64.55
9461 Total 494.91 Z
9462 Add Cess @ 1% on "Z" 4.95
9463 Cost of 10.00 sqm 499.86
9464 Cost of 1.00 sqm 49.99
9465 Say 50.00

9466 13.101 Painting with acid proof paint of approved brand and
9467 manufacture
colour to giveofan
required
even shade :
9468 13.101.1 One or more coats on old work
9469 Detail of cost for 10 sqm
9470 MATERIAL
9471 827 Acid proof paint (chocolate or black) litre 0.7 225 157.50
9472 9977 Carriage of paint L.S. 0.52 2 1.04
9473 9999 Putty etc L.S. 2.73 2 5.46
9474 LABOUR
9475 31 Painter day 0.36 403.67 145.32
9476 18 Coolie day 0.36 350.00 126.00
9477 9999 Brushes, sand paper etc L.S. 5.33 2 10.66
9478 9999 Sundries L.S. 8.06 2 16.12
9479 TOTAL 462.10 W
9480 Add 1 % Water charges on "W" 4.621
9481 TOTAL 466.72 X
9482 Add GST (multiplying factor 0.1405) on "X" 65.57
9483 TOTAL 532.29 Y
9484 Add 15 % Contractor's profit and overheads on "Y" 79.84
9485 Total 612.13 Z
9486 Add Cess @ 1% on "Z" 6.12
9487 Cost of 10.00 sqm 618.25
9488 Cost of 1.00 sqm 61.83
9489 Say 61.80
9490
9491
9492 13.102 Painting with black anti-corrosive bitumastic paint of
approved brand and manufacture to give an even shade :
9493 13.102.1 One or more coats on old work
9494 Detail of cost for 10 sqm
9505 MATERIAL
9506 828 Anticorrosive bituminous paint (black) litre 0.57 100 57.00
9507 9977 Carriage L.S. 0.52 2 1.04
9508 LABOUR 0
9509 31 Painter day 0.36 403.67 145.32
9510 18 Coolie day 0.36 350.00 126.00
9511 9999 Putty, brushes, sand paper etc L.S. 5.33 2 10.66
9512 9999 Sundries L.S. 8.06 2 16.12
9513 TOTAL 356.14 W
9514 Add 1 % Water charges on "W" 3.5614
9515 TOTAL 359.70 X
9516 Add GST (multiplying factor 0.1405) on "X" 50.54
9517 TOTAL 410.24 Y
9518 Add 15 % Contractor's profit and overheads on "Y" 61.54
9519 Total 471.78 Z
9520 Add Cess @ 1% on "Z" 4.72
9521 Cost of 10.00 sqm 476.50
9522 Cost of 1.00 sqm 47.65
9523 Say 47.70

9524 13.103 French spirit polishing :


9525 13.103.1 One or more coats on old work
9526 Detail of cost for 10 sqm
9527 MATERIAL
9528 1000 Spirit litre 0.98 48 47.04
9529 999 Shellac kilogram 0.13 300 39.00
9530 9977 Carriage of materials L.S. 0.91 2 1.82
9531 9999 Turpentine oil sand paper cotton/woolen cloth L.S. 10.79 2 21.58
9532 9999 putty etc. 0.00
9533 Linseed oil L.S. 0.52 2 1.04
9534 LABOUR
9535 31 Painter day 1.76 403.67 710.46
9536 9999 Sundries L.S. 8.06 2 16.12
9537 TOTAL 837.06 W
9538 Add 1 % Water charges on "W" 8.3706
9539 TOTAL 845.43 X
9540 Add GST (multiplying factor 0.1405) on "X" 118.78
9541 TOTAL 964.21 Y
9542 Add 15 % Contractor's profit and overheads on "Y" 144.63
9543 Total 1108.84 Z
9544 Add Cess @ 1% on "Z" 11.09
9545 Cost of 10.00 sqm 1119.93
9546 Cost of 1.00 sqm 111.99
9547 Say 112.00
9548
9557
9558 13.104 Polishing on wood work with ready made wax polish of
9559 approved brand
manufacture : and
9560 13.104.1 Old work
9561 Detail of cost for 10 sqm
9562 MATERIAL
9563 855 Wax polish (ready made) kilogram 0.25 230 57.50
9564 9977 Caariage L.S. 0.39 2 0.78
9565 LABOUR
9566 31 Painter day 0.4 403.67 161.47
9567 18 Coolie day 0.4 350.00 140.00
9568 9999 Soap, brushes, cloth etc L.S. 4.16 2 8.32
9569 9999 Sundries L.S. 4.42 2 8.84
9570 TOTAL 376.91 W
9571 Add 1 % Water charges on "W" 3.7691
9572 TOTAL 380.68 X
9573 Add GST (multiplying factor 0.1405) on "X" 53.49
9574 TOTAL 434.17 Y
9575 Add 15 % Contractor's profit and overheads on "Y" 65.13
9576 Total 499.30 Z
9577 Add Cess @ 1% on "Z" 4.99
9578 Cost of 10.00 sqm 504.29
9579 Cost of 1.00 sqm 50.43
9580 Say 50.40

9581 13.105 Re-lettering with black Japan paint of approved brand and
9582 manufacture.
Detail of cost for 100 letters of 15 cm height
9583 MATERIAL
9584 829 Black Japan paint litre 0.37 90 33.30
9585 9977 Carriage L.S. 0.52 2 1.04
9586 LABOUR
9598 31 Painter day 4 403.67 1614.68
9599 18 Coolie day 1 350.00 350.00
9600 9999 Painting brushes, turpentine, stencil etc L.S. 7.15 2 14.30
9601 9999 Sundries L.S. 8.06 2 16.12
9602 TOTAL 2029.44 W
9603 Add 1 % Water charges on "W" 20.2944
9604 TOTAL 2049.73 X
9605 Add GST (multiplying factor 0.1405) on "X" 287.99
9606 TOTAL 2337.72 Y
9607 Add 15 % Contractor's profit and overheads on "Y" 350.66
9608 Total 2688.38 Z
9609 Add Cess @ 1% on "Z" 26.88
9610 Cost of 100 letters of 15 cm height 2715.26
9611 Cost per letter per cm height 1.81
9612 Say 1.80
9613 13.106 Painting (one or more coats) with black Japan paint of
9614 approved brand
manufacture and an even shade.
to give
9615 Detail of cost for 10 sqm
9616 MATERIAL
9617 829 Black Japan paint litre 0.7 90 63.00
9618 9977 Carriage L.S. 0.52 2 1.04
9619 9999 Putty etc. L.S. 2.73 2 5.46
9620 LABOUR
9621 31 Painter day 0.36 403.67 145.32
9622 18 Coolie day 0.36 350.00 126.00
9623 9999 Brushes, sand paper etc. L.S. 5.33 2 10.66
9624 9999 Sundries L.S. 8.06 2 16.12
9625 TOTAL 303.56 W
9626 Add 1 % Water charges on "W" 3.0356
9627 TOTAL 306.60 X
9628 Add GST (multiplying factor 0.1405) on "X" 43.08
9629 TOTAL 349.68 Y
9630 Add 15 % Contractor's profit and overheads on "Y" 52.45
9631 Total 402.13 Z
9632 Add Cess @ 1% on "Z" 4.02
9633 Cost of 10.00 sqm 406.15
9634 Cost of 1sqm 40.61
9635 Say 40.60
9636
9645
9646
9647 13.107 Providing and fixing C.P. brass chain and rubber plug
9648 complete for sink or
wash basin:
9649 13.107.1 32 mm dia
9650 Detail of cost for 1 no.
9651 MATERIAL
9652 1314 C.P.brass chain with 32 mm dia rubber plug each 1 40 40.00
9653 9988 Carriage of materials and fixing charges L.S. 8.06 2 16.12
9654 TOTAL 56.12 W
9655 Add 1 % Water charges on "W" 0.5612
9656 TOTAL 56.68 X
9657 Add GST (multiplying factor 0.1405) on "X" 7.96
9658 TOTAL 64.64 Y
9659 Add 15 % Contractor's profit and overheads on "Y" 9.70
9660 Total 74.34 Z
9661 Add Cess @ 1% on "Z" 0.74
9662 Cost of each 75.08
9663 Say 75.08
75.10

9664 13.107.2 40 mm dia


9665 Detail of cost for 1 no.
9666 MATERIAL
9667 1315 C.P.brass chain with 40 mm dia rubber plug each 1 40 40.00
9668 9988 Carriage of materials and fixing charges L.S. 8.06 2 16.12
9669 TOTAL 56.12 W
9670 Add 1 % Water charges on "W" 0.5612
9671 TOTAL 56.68 X
9672 Add GST (multiplying factor 0.1405) on "X" 7.96
9673 TOTAL 64.64 Y
9674 Add 15 % Contractor's profit and overheads on "Y" 9.70
9675 Total 74.34 Z
9676 Add Cess @ 1% on "Z" 0.74
9677 Cost of each 75.08
9678 Say 75.08
9679 75.10
9680
9681
9682
9683 13.108 Distempering with 1st quality acrylic washable distemper
9684 (ready
13.108.1made)
One or of more
approved
coatsmanufacturer
on old work and of required
9685 shade and colour complete.
Detail of cost for 10 sqm
as per manufacturer's
specification.
9686 MATERIAL
9687
9688 816 Oil bound washable distemper/ Acrylic distemper kilogram 1 50 50.00
9699 9999 Brushes, putty etc L.S. 0.52 2 1.04
9700 9988 Sundries including carriage of material L.S. 10.76 2 21.52
9701 LABOUR
9702 31 Painter day 0.22 403.67 88.81
9703 17 Beldar day 0.22 350.00 77.00
9704 9999 Sundries L.S. 7.15 2 14.30
9705 TOTAL 252.67 W
9706 Add 1 % Water charges on "W" 2.5267
9707 TOTAL 255.20 X
9708 Add GST (multiplying factor 0.1405) on "X" 35.86
9709 TOTAL 291.06 Y
9710 Add 15 % Contractor's profit and overheads on "Y" 43.66
9711 Total 334.72 Z
9712 Add Cess @ 1% on "Z" 3.35
9713 Cost of 10.00 sqm 338.07
9714 Cost of 1.00 sqm 33.81
9715 Say 33.80

9716 13.109 Finishing walls with water proofing cement paint of required
9717 13.109.1 shade
Old work : (one or more coats applied @ 2.20 kg/10 sqm) over
9718 priming coat of@ 0.80 litrs/10 sqm complete including cost of
primer applied
9719 Priming
Detail coat.
of cost for 10 sqm
9720 MATERIAL
9721 851 Water proofing cement paint kilogram 2.2 38 83.60
9722 8508 Primer for cement paint litre 0.8 79 63.20
9723 9977 Carriage of material L.S. 1.56 2 3.12
9724 LABOUR
9725 31 Painter day 0.46 403.67 185.69
9726 18 Coolie day 0.23 350.00 80.50
9727 11 Bhisti day 0.05 350.00 17.50
9728 9999 Brushes, sand paper etc L.S. 7.15 2 14.30
9729 9999 Sundries L.S. 8.06 2 16.12
9730 TOTAL 464.03 W
9731 Add 1 % Water charges on "W" 4.6403
9732 TOTAL 468.67 X
9733 Add GST (multiplying factor 0.1405) on "X" 65.85
9734 TOTAL 534.52 Y
9735 Add 15 % Contractor's profit and overheads on "Y" 80.18
9736 Total 614.70 Z
9737 Add Cess @ 1% on "Z" 6.15
9738 Cost of 10.00 sqm 620.85
9739 Cost of 1.00 sqm 62.09
9740 Say 62.10
9741
9750
9751
9752
9753 13.109.2 Old work (one or more coats @ 2.20 kg/10 sqm)
9754 complete.
Detail of cost for 10 sqm
9755 MATERIAL
9756 851 Water proofing cement paint kilogram 2.2 38 83.60
9757 9977 Carriage of material L.S. 1.1 2 2.20
9758 LABOUR
9759 31 Painter day 0.35 403.67 141.28
9760 18 Coolie day 0.12 350.00 42.00
9761 11 Bhisti day 0.05 350.00 17.50
9762 9999 Brushes, sand paper etc L.S. 3.15 2 6.30
9763 9999 Sundries L.S. 8.06 2 16.12
9764 TOTAL 309.00 W
9765 Add 1 % Water charges on "W" 3.09
9766 TOTAL 312.09 X
9767 Add GST (multiplying factor 0.1405) on "X" 43.85
9768 TOTAL 355.94 Y
9769 Add 15 % Contractor's profit and overheads on "Y" 53.39
9770 Total 409.33 Z
9771 Add Cess @ 1% on "Z" 4.09
9772 Cost of 10.00 sqm 413.42
9773 Cost of 1.00 sqm 41.34
9774 Say 41.30

9775 13.11 Finishing walls with textured exterior paint of required


9776 13.110.1 shade
Old work: (Two or more coats on existing cement paint
9777 surface applied @ 3.28
ltr/10 sqm.
9778 Detail of cost for 10 sqm
9779 MATERIAL
9780 8507 Textured exterior paint litre 3.28 240 787.20
9781 9977 Carriage of material L.S. 1.56 2 3.12
9782 LABOUR
9783 31 Painter day 0.46 403.67 185.69
9784 18 Coolie day 0.23 350.00 80.50
9785 9999 Brushes, sand paper etc L.S. 7.15 2 14.30
9786 9999 Sundries L.S. 8.06 2 16.12
9797 TOTAL 1066.8 1086.93 W
9798 Add 1 % Water charges on "W" 10.67 10.8693
9799 TOTAL 1077.47 1097.80 X
9800 Add GST (multiplying factor 0.1405) on "X" 151.38 154.24
9801 TOTAL 1228.85 1252.04 Y
9802 Add 15 % Contractor's profit and overheads on "Y" 184.33 187.81
9803 Total 1413.18 1439.85 Z
9804 Add Cess @ 1% on "Z" 14.13 14.40
9805 Cost of 10.00 sqm 1427.31 1454.25
9806 Cost of 1.00 sqm 142.73 145.42
9807 Say 145.40
9808
9809
9810 13.110.2 Old work (One or more coats) applied @ 1.82 ltr/10
9811 sqm.
Detail of cost for 10 sqm
9812 MATERIAL
9813 8507 Textured exterior paint litre 1.82 240 436.80
9814 9977 Carriage of material L.S. 0.52 2 1.04
9815 LABOUR
9816 31 Painter day 0.33 403.67 133.21
9817 18 Coolie day 0.17 350.00 59.50
9818 9999 Brushes, sand paper etc L.S. 7.15 2 14.30
9819 9999 Sundries L.S. 8.06 2 16.12
9820 TOTAL 660.97 W
9821 Add 1 % Water charges on "W" 6.6097
9822 TOTAL 667.58 X
9823 Add GST (multiplying factor 0.1405) on "X" 93.79
9824 TOTAL 761.37 Y
9825 Add 15 % Contractor's profit and overheads on "Y" 114.21
9826 Total 875.58 Z
9827 Add Cess @ 1% on "Z" 8.76
9828 Cost of 10.00 sqm 884.34
9829 Cost of 1.00 sqm 88.43
9830 Say 88.40

9831 13.111 Finishing walls with Acrylic Smooth exterior paint of required
shade :
9832 13.111.1 Old work (Two or more coat applied @ 1.67 ltr/ 10 sqm) on
9833 existing cement
paint surface
9834 Detail of cost for 10 sqm
9835 MATERIAL
9836 8505 Acrylic exterior paint litre 1.67 170 283.90
9837 9977 Carriage of material L.S. 0.91 2 1.82
9838 LABOUR
9848 31 Painter day 0.46 403.67 185.69
9849 18 Coolie day 0.23 350.00 80.50
9850 9999 Brushes, sand paper etc L.S. 4.81 2 9.62
9851 9999 Sundries L.S. 5.33 2 10.66
9852 TOTAL 572.19 W
9853 Add 1 % Water charges on "W" 5.7219
9854 TOTAL 577.91 X
9855 Add GST (multiplying factor 0.1405) on "X" 81.20
9856 TOTAL 659.11 Y
9857 Add 15 % Contractor's profit and overheads on "Y" 98.87
9858 Total 757.98 Z
9859 Add Cess @ 1% on "Z" 7.58
9860 Cost of 10.00 sqm 765.56
9861 Cost of 1.00 sqm 76.56
9862 Say 76.60
9863
9864
9865 13.111.2 Old work (One or more coat applied @ 0.90 ltr/10
9866 sqm).
Detail of cost for 10 sqm
9867 MATERIAL
9868 8505 Acrylic exterior paint litre 0.9 170 153.00
9869 9977 Carriage of material L.S. 0.52 2 1.04
9870 LABOUR
9871 31 Painter day 0.33 403.67 133.21
9872 18 Coolie day 0.17 350.00 59.50
9873 9999 Brushes, sand paper etc L.S. 7.15 2 14.30
9874 9999 Sundries L.S. 8.06 2 16.12
9875 TOTAL 377.17 W
9876 Add 1 % Water charges on "W" 3.7717
9877 TOTAL 380.94 X
9878 Add GST (multiplying factor 0.1405) on "X" 53.52
9879 TOTAL 434.46 Y
9880 Add 15 % Contractor's profit and overheads on "Y" 65.17
9881 Total 499.63 Z
9882 Add Cess @ 1% on "Z" 5.00
9883 Cost of 10.00 sqm 504.63
9884 Cost of 1.00 sqm 50.46
9885 Say 50.50
9886
9887
9888 13.112 Finishing walls with Premium Acrylic Smooth exterior paint
9898 13.112.1 with Silicone
Old work (Twoadditives
or more of required
coats shade
applied @ 1.43 ltr/ 10 sqm) over
9899 existing cement paint surface
9900 Detail of cost for 10 sqm
9901
9902 MATERIAL
9903 8506 Premium Acrylic exterior paint litre 1.43 180 257.40
9904 9977 Carriage of material L.S. 1.04 2 2.08
9905 LABOUR
9906 31 Painter day 0.46 403.67 185.69
9907 18 Coolie day 0.23 350.00 80.50
9908 9999 Brushes, sand paper etc L.S. 7.15 2 14.30
9909 9999 Sundries L.S. 8.06 2 16.12
9910 TOTAL 556.09 W
9911 Add 1 % Water charges on "W" 5.5609
9912 TOTAL 561.65 X
9913 Add GST (multiplying factor 0.1405) on "X" 78.91
9914 TOTAL 640.56 Y
9915 Add 15 % Contractor's profit and overheads on "Y" 96.08
9916 Total 736.64 Z
9917 Add Cess @ 1% on "Z" 7.37
9918 Cost of 10.00 sqm 744.01
9919 Cost of 1.00 sqm 74.4
9920 Say 74.40
9921
9922
9923 13.112.2 Old work (one or more coats applied @ 0.83 ltr/10
9924 sqm).
Detail of cost for 10 sqm
9925 MATERIAL
9926 8506 Premium Acrylic exterior paint litre 0.83 180 149.40
9927 9977 Carriage of material L.S. 0.91 2 1.82
9928 LABOUR
9929 31 Painter day 0.33 403.67 133.21
9930 18 Coolie day 0.17 350.00 59.50
9931 9999 Brushes, sand paper etc L.S. 7.15 2 14.30
9932 9999 Sundries L.S. 8.06 2 16.12
9933 TOTAL 374.35 W
9934 Add 1 % Water charges on "W" 3.7435
9935 TOTAL 378.09 X
9936 Add GST (multiplying factor 0.1405) on "X" 53.12
9937 TOTAL 431.21 Y
9938 Add 15 % Contractor's profit and overheads on "Y" 64.68
9939 Total 495.89 Z
9940 Add Cess @ 1% on "Z" 4.96
9941 Cost of 10.00 sqm 500.85
9942 Cost of 1.00 sqm 50.09
9943 Say 50.10
9944
9952
9953 13.113 Varnishing with varnish of approved brand and manufacture:
9954 13.113.1 One or more coats with copal varnish
9955 Detail of cost for 10 sqm
9956 MATERIAL
9957 857 Superior copal varnish litre 0.7 115 80.50
9958 9977 Carriage L.S. 0.52 2 1.04
9959 9999 Repair to the surface L.S. 2.73 2 5.46
9960 LABOUR
9961 31 Painter day 0.36 403.67 145.32
9962 18 Coolie day 0.36 350.00 126.00
9963 9999 Brushes, sand paper etc L.S. 5.33 2 10.66
9964 9999 Sundries L.S. 2.73 2 5.46
9965 TOTAL 374.44 W
9966 Add 1 % Water charges on "W" 3.7444
9967 TOTAL 378.18 X
9968 Add GST (multiplying factor 0.1405) on "X" 53.13
9969 TOTAL 431.31 Y
9970 Add 15 % Contractor's profit and overheads on "Y" 64.70
9971 Total 496.01 Z
9972 Add Cess @ 1% on "Z" 4.96
9973 Cost of 10.00 sqm 500.97
9974 Cost of 1.00 sqm 50.1
9975 Say 50.10

9976 13.113.2 One or more coats with spar varnish


9977 Detail of cost for 10 sqm
9978 MATERIAL
9979 858 Superior spar varnish litre 0.75 115 86.25
9980 9977 Carriage L.S. 0.52 2 1.04
9981 9999 Repair etc L.S. 2.73 2 5.46
9982 LABOUR
9983 31 Painter day 0.36 403.67 145.32
9984 18 Coolie day 0.36 350.00 126.00
9985 9999 Brushes, sand paper etc L.S. 2.73 2 5.46
9986 9999 Sundries L.S. 4.16 2 8.32
9987 TOTAL 377.85 W
9988 Add 1 % Water charges on "W" 3.7785
9989 TOTAL 381.63 X
9990 Add GST (multiplying factor 0.1405) on "X" 53.62
9991 TOTAL 435.25 Y
9992 Add 15 % Contractor's profit and overheads on "Y" 65.29
9993 Total 500.54 Z
9994 1010 Add Cess @ 1% on "Z" 5.01
9995 Cost of 10.00 sqm 505.55
9996 Cost of 1.00 sqm 50.55
9998 Say 50.60
9999
10007
10008 13.114 Melamine polishing on wood work (one or more coat).
10009 Detail of cost for 10 sqm
10010 MATERIAL
10011 7241 Melamine polish litre 0.65 280 182.00
10012 6 Hire charges of Spraying machine including day 0.78 250 195.00
10013 9988 electric charges 0.00
10014 Carriage charge of Machine & Marerial L.S. 4.42 2 8.84
10015 LABOUR
10016 31 Painter day 0.35 403.67 141.28
10017 17 Beldar day 0.35 350.00 122.50
10018 9999 Sundries L.S. 4.42 2 8.84
10019 TOTAL 658.46 W
10020 Add 1 % Water charges on "W" 6.5846
10021 TOTAL 665.04 X
10022 Add GST (multiplying factor 0.1405) on "X" 93.44
10023 TOTAL 758.48 Y
10024 Add 15 % Contractor's profit and overheads on "Y" 113.77
10025 Total 872.25 Z
10026 Add Cess @ 1% on "Z" 8.72
10027 Cost of 10.00 sqm 880.97
10028 Cost of 1.00 sqm 88.1
10029 Say 88.10

10030 13.115 Varnishing with flatting varnish of approved brand and


10031 manufacture one
more coats on oldorwork.
10032 Detail of cost for 10 sqm
10033 MATERIAL
10034 856 Ordinary varnish litre 0.7 100 70.00
10035 9999 Glue, putty etc L.S. 2.73 2 5.46
10036 9977 Carriage L.S. 1.82 2 3.64
10037 9999 Painting brushes, turpentine, stencil etc L.S. 24.18 2 48.36
10038 LABOUR
10039 31 Painter day 0.36 403.67 145.32
10049 18 Coolie day 0.36 350.00 126.00
10050 TOTAL 398.78 W
10051 Add 1 % Water charges on "W" 3.9878
10052 TOTAL 402.77 X
10053 Add GST (multiplying factor 0.1405) on "X" 56.59
10054 TOTAL 459.36 Y
10055 Add 15 % Contractor's profit and overheads on "Y" 68.90
10056 Total 528.26 Z
10057 Add Cess @ 1% on "Z" 5.28
10058 Cost of 10.00 sqm 533.54
10059 Cost of 1.00 sqm 53.35
10060 Say 53.40
10061
10062
1012
1156.55
984.1
837.3
53.3

42.65
42.65
297.95

237.95
237.95
622.15
550.9
1147.95
487.75
597.75
538.45
418.2
42.65
117.8

140
394.15
394.15
448
393.2
339
270.85
463.2
505.6
608.5
260.65
847.85
373.8
58.2
107.85
601.3
621.6

14.8
431.95
474.3
160.9
209.5
592.4
614.8
582.65
619.45
744.55
696.75
581.95
559.9
483.8
244.05
248.6
264.15
230.2
243.95

199.65
980.15
1140.05

302.45
120.95
481.75
214.4
241.7
278.5

99.4
185.15
205.25
337.6
467.7

428.25
165.15
260.55
77.85
117.8

77.85
108.45
139.85

203.3
122.45
188.55

89.9
129.85
79.2

113.8
188.55
187.2
47.25
859.45
978.9
1028.05
1217.7
100.45
1031.85
936
264.45

58
592.45
377.05
348.9
419.55
336.4
386.8
890.5
1333.3
1478
1709.8
1000.35
1472.8
1562.95
1710.5
1160.4
1412.2
283.05
1588.6
1014.9
447.9
243.85
249.2
275.7
172.85

160.25
200.45
185.4
241.4
221.75

182.15
169.5
211.5
196.45
255.8

236.2
226.2
213.6
256.25
241.2
235.5
316.15
267.35
256.95
274.2

203.3
236.8
288.7
142.35
191.05
42.1
441.8
416.3
59.75
43.5
20.5

31.5
293.4
482.9

76.55
83.55

50.1
135.9
47
3.4

3.7
4.15
6.95
4.2

4.55
5.2
9.4
9.4
112.5
183.55

153.65
163.3
296.7
314.2
92.3

7.15
17.45
7.05
23.9
23.45
72.45
96.85

56.25
37.4
61.2
196.05
128.75
125.2
106.25

94.3
89.9
110.05
38.95
39.45
33.3

18.5
61.6
97.85
132.5
132.15
90.2
30.9
30.65
39.35
58.7
44.85
66.85
33.65
252.85
36.65
89.5
82.4
119.9

73.1
90.95
66.9
105.5
117.15
118
208.55

92.95
43.85
2.65
610.05
37.95
38.55

103.7
67.7
78.95
83.75

251.05
66.9
85.1
31.75

51
45.7
67.7
49
74.8
38.95

37.4
158.85
10.5
6.5
8.5

30.7
35.45
11.15
45
29.35

14.05
18.45
26.3
30.9
43.8
65.3
14.95

19.25
27.4
25.9
58.55
53.85
47.2

59
44.85
105.1
47.3

1.7
46.35
75.1

75.1
32.1
59.2
39.3
142.75

86.5
73.85
48.5
71.7

48.15
47.3
47.75
85.35

50.55
SUB HEAD : 14.0

REPAIRS TO BUILDING
2
3 14.1 Repairs to plaster of thickness 12
5 mm to 20
14.1.1 mmcement
With in patches of area
mortar 1:4 (12.5 sq. :
cement
7 4 fineofsand)
Detail cost for 10 sqm
9 MATERIAL
11 Cement mortar 1 : 4 (1 cement : 4 fine sand)
13 3.4 Rate as per Item Number 3.4 of SH: Mortars cum 0.183 3333.55
14 LABOUR
15 40 Mason (average) day 1.21 403.67
16 18 Coolie day 1.29 350.00
17 17 Beldar day 0.54 350.00
18 11 Bhisti day 0.92 350.00
19 9999 Scaffolding and sundries L.S. 15.21 2
20 TOTAL
21 Add 1 % Water charges on "W"
22 TOTAL
23 Add GST (multiplying factor 0.1405) on "X"
24 TOTAL
25 Add 15 % Contractor's profit and overheads on "Y"
26 Total
27 Add Cess @ 1% on "Z"
28 Cost of 10.00 sqm
29 Cost of 1.00 sqm
30 Say
31
32
33 14.1.2 With cement mortar 1:4 (1cement: 4
34 coarse sand)
Detail of cost for 10 sqm
35
36 MATERIAL
37
38 Cement mortar 1 : 4 (1 cement : 4 coarse sand)
49 3.9 Rate as per Item Number 3.9 of SH: Mortars cum 0.183 3815.05
50 LABOUR
51 40 Mason (average) day 1.21 403.67
52 18 Coolie day 1.29 350.00
53 17 Beldar day 0.54 350.00
54 11 Bhisti day 0.92 350.00
55 9999 Scaffolding and sundries L.S. 15.21 2
56 TOTAL
57 Add 1 % Water charges on "W"
58 TOTAL
59 Add GST (multiplying factor 0.1405) on "X"
60 TOTAL
61 Add 15 % Contractor's profit and overheads on "Y"
62 Total
63 Add Cess @ 1% on "Z"
64 Cost of 10.00 sqm
65 Cost of 1.00 sqm
66 Say
67
68
69 14.2 Fixing chowkhats in existing opening
70 including embedding
14.2.1 Door chowkhatschowkhats in floors
71
72 Detail of cost for each
73 295 Stone Aggregate (Single size) : 20 mm cum 0.021 1350
74 297 nominal size
75 Stone Aggregate (Single size) : 10 mm cum 0.0072 1350
76 2202 nominal size
77 Carriage of Stone aggregate below 40 mm cum 0.0282 106.13
78 982 nominal size
79 Coarse sand cum 0.0141 1350
80 2203 Carriage of Coarse sand cum 0.0141 584.88
81 367 Portland Cement (OPC-43 grade) tonne 0.0066 4940
82 2209 Carriage of Cement tonne 0.0066 94.34
83 17 Beldar day 0.027 350.00
84 18 Coolie day 0.0195 350.00
93 30 Mistry day 0.0084 505.17
94 23 Mason (brick layer) 1st class day 0.0018 505.17
95 24 Mason (brick layer) 2nd class day 0.0018 403.67
96 28 Mate day 0.0012 350.00
97 9999 Scaffolding L.S. 1.43 2
98 9999 Hire and running charges of mechanical L.S. 0.78 2
99 mixer
100 9999 Sundries L.S. 0.39 2
101 Cement mortar 1 : 6 (1 cement : 6 fine sand)
102 3.6 Rate as per Item Number 3.6 of SH: Mortars cum 0.01 2679.1
103 9999 Cement concrete 1:2:4 filled in chase cut L.S. 24.18 2
104 9999 Painting two coats of coaltar L.S. 13.52 2
105 9999 Disposal of mulba L.S. 1.82 2
106 40 Mason (average) day 0.5 403.67
107 17 Beldar day 0.75 350.00
108 9999 Sundries L.S. 2.73 2
109 TOTAL
110 Add 1 % Water charges on "W"
111 TOTAL
112 Add GST (multiplying factor 0.1405) on "X"
113 TOTAL
114 Add 15 % Contractor's profit and overheads on "Y"
115 Total
116 Add Cess @ 1% on "Z"
117 Cost of each
118 Say
119
120
121 14.2.2 Window chowkhats
122 Detail of cost for each
123 295 Stone Aggregate (Single size) : 20 mm cum 0.014 1350
124 297 nominal size
125 Stone Aggregate (Single size) : 10 mm cum 0.0048 1350
126 2202 nominal size
127 Carriage of Stone aggregate below 40 mm cum 0.0188 106.13
128 982 nominal size
129 Coarse sand cum 0.0094 1350
130 2203 Carriage of Coarse sand cum 0.0094 584.88
131 367 Portland Cement (OPC-43 grade) tonne 0.0044 4940
132 2209 Carriage of Cement tonne 0.0044 94.34
133 17 Beldar day 0.018 350.00
134 18 Coolie day 0.013 350.00
135 30 Mistry day 0.0056 505.17
146 23 Mason (brick layer) 1st class day 0.0012 505.17
147 24 Mason (brick layer) 2nd class day 0.0012 403.67
148 28 Mate day 0.0008 350.00
149 9999 Scaffolding and sundries L.S. 0.91 2
150 9999 Hire and running charges of mechanical L.S. 0.52 2
151 mixer
152 9999 Sundries L.S. 0.26 2
153 Cement mortar 1 : 6 (1 cement : 6 fine sand)
154 3.6 Rate as per Item Number 3.6 of SH: Mortars cum 0.006 2679.1
155 9999 Cement concrete 1:2:4 L.S. 9.88 2
156 9999 Painting two coats of coaltar L.S. 0.91 2
157 40 Mason (average) day 0.33 403.67
158 17 Beldar day 0.5 350.00
159 TOTAL
160 Add 1 % Water charges on "W"
161 TOTAL
162 Add GST (multiplying factor 0.1405) on "X"
163 TOTAL
164 Add 15 % Contractor's profit and overheads on "Y"
165 Total
166 Add Cess @ 1% on "Z"
167 Cost of each
168 Say
169
170
171 14.2.3 Clerestory window chowkhats
172 Detail of cost for each
173 295 Stone Aggregate (Single size) : 20 mm cum 0.007 1350
174 297 nominal size
175 Stone Aggregate (Single size) : 10 mm cum 0.0024 1350
176 2202 nominal size
177 Carriage of Stone aggregate below 40 mm cum 0.0094 106.13
178 982 nominal size
179 Coarse sand cum 0.0047 1350
180 2203 Carriage of Coarse sand cum 0.0047 584.88
181 367 Portland Cement (OPC-43 grade) tonne 0.0022 4940
182 2209 Carriage of Cement tonne 0.0022 94.34
183 17 Beldar day 0.009 350.00
184 18 Coolie day 0.0065 350.00
185 30 Mistry day 0.0028 505.17
196 23 Mason (brick layer) 1st class day 0.0006 505.17
197 24 Mason (brick layer) 2nd class day 0.0006 403.67
198 28 Mate day 0.0004 350.00
199 9999 Scaffolding and sundries L.S. 0.52 2
200 9999 Hire and running charges of mechanical L.S. 0.26 2
201 9999 mixer
202 Sundries L.S. 0.13 2
203 Cement mortar 1 : 6 (1 cement : 6 fine sand)
204 3.6 Rate as per Item Number 3.6 of SH: Mortars cum 0.003 2679.1
205 9999 Cement concrete 1:2:4 filled in chase cut L.S. 8.06 2
206 9999 Painting two coats of coaltar L.S. 0.91 2
207 40 Mason (average) day 0.17 403.67
208 17 Beldar day 0.5 350.00
209 9999 Sundries L.S. 2.73 2
210 TOTAL
211 Add 1 % Water charges on "W"
212 TOTAL
213 Add GST (multiplying factor 0.1405) on "X"
214 TOTAL
215 Add 15 % Contractor's profit and overheads on "Y"
216 Total
217 Add Cess @ 1% on "Z"
218 Cost of each
219 Say
220
221
222 14.3 Fixing chowkhat in existing opening in
223 brick/ RCC
Details of costwall
for 1with dash fasteners/
chowkhat.
224 17 Beldar day 0.027 350.00
225 18 Coolie day 0.0195 350.00
226 30 Mistry day 0.0084 505.17
227 28 Mate day 0.0012 350.00
228 9999 Disposal of mulba L.S. 1.82 2
229 7019 Dash fastner/ chemical fastener each 6 14
230 9999 Hire charges of drill machine hire charges, L.S. 12.22 2
231 Scaffolding and Sundries
232 TOTAL
233 Add 1 % Water charges on "W"
234 TOTAL
235 Add GST (multiplying factor 0.1405) on "X"
236 TOTAL
237 Add 15 % Contractor's profit and overheads on "Y"
238 Total
240 Add Cess @ 1% on "Z"
241 Cost of each
242 Say
250
251
252 14.4 Making the opening in brick masonry
253 including dismantling in floor or walls by
254 14.4.1 For door/ window/ clerestory
255 window
256 Details of cost for one opening of size 0.90x2.10m =
1.89 sqm
257
258 Cement mortar 1:6 (1 cement: 6 fine sand)
259
260 3.6 Rate as per Item Number 3.6 of SH: Mortars cum 0.01 2679.1
261 9999 Cement concrete 1:2:4 filled in chase cut L.S. 24.57 2
262 24 Mason (brick layer) 2nd class day 0.5 403.67
263 17 Beldar day 1.2 350.00
264 18 Coolie day 0.4 350.00
265 9999 Scaffolding and Sundries L.S. 3.5 2
266 TOTAL
267 Add 1 % Water charges on "W"
268 TOTAL
269 Add GST (multiplying factor 0.1405) on "X"
270 TOTAL
271 Add 15 % Contractor's profit and overheads on "Y"
272 Total
273 Add Cess @ 1% on "Z"
274 Cost of 1.89sqm.
275 Cost of 1.00 sqm.
276 Say
277
286
287
288
289
290 14.5 Renewing glass panes, with putty and
291 14.5.1 nails
Floatwherever necessary
glass panes including
of thickness 4 mm
292 (weight not less than 10kg/sqm).
Detail of cost for 10 glasses area each 0.1sqm.
293 MATERIAL
295 2406 Float glass sheet of nominal thickness 4 mm sqm 1.1 300
296 (weight not less than 10kg/sqm).
297 1.00 sqm + 10% wastage= 1.10 Sqm
298 9988 Carriage including sundries L.S. 1.82 2
299 863 Putty for wood work kilogram 0.68 30
300 9999 Painting or varnishing or beewaxing L.S. 5.33 2
301 9999 Sundries Nails etc. L.S. 6.76 2
302 21 Glazier day 0.23 403.67
303 17 Beldar day 0.23 350.00
304 9999 Sundries such as Rag, cotton etc L.S. 1.43 2
305 TOTAL
306 Add 1 % Water charges on "W"
307 TOTAL
308 Add GST (multiplying factor 0.1405) on "X"
309 TOTAL
310 Add 15 % Contractor's profit and overheads on "Y"
311 Total
312 Add Cess @ 1% on "Z"
313 Cost of 1.00 sqm
314 Say
315
316
317
318 14.5.2 Float glass panes of thickness 5.0 mm
319 (weight not for
Detail of cost less than 12.50
10 glasses kg/sqm)
area each 0.1sqm.
320 MATERIAL
321 2407 Float glass sheet of nominal thickness 5.0 sqm 1.1 500
322 mm.(weight not less than 12.50 kg/sqm).
323 1.00 sqm + 10% wastage= 1.10 Sqm
324 9988 Carriage including sundries L.S. 1.82 2
325 863 Putty for wood work kilogram 0.68 30
326 9999 Painting or varnishing or beewaxing L.S. 5.33 2
327 9999 Sundries Nails etc. L.S. 6.76 2
328 21 Glazier day 0.23 403.67
329 17 Beldar day 0.23 350.00
330 9999 Sundries such as Rag, cotton etc L.S. 1.43 2
331 TOTAL
332 Add 1 % Water charges on "W"
333 TOTAL
334 Add GST (multiplying factor 0.1405) on "X"
335 TOTAL
336 Add 15 % Contractor's profit and overheads on "Y"
337 Total
338 Add Cess @ 1% on "Z"
340 Cost of 1.00 sqm
341 Say
342
350
351
352
353 14.6 Renewing glass panes, with wooden
354 14.6.1 fillets wherever
Float glass panesnecessary:
of thickness 4 mm
355 (weight not for
Detail of cost less than 10kg/sqm)
10 glasses area each 0.1sqm.
356
357 MATERIAL
358 2406 Float glass sheet of nominal thickness 4 mm sqm 1.1 300
359 (weight not less than 10kg/sqm).
360 1.00 sqm + 10% wastage= 1.10 Sqm
361 1189 Second class teak wood in scantling 10 cudm 0.025 776
362 1194 Second class deodar wood in planks 10 cudm 0.025 500
363 1196 First class kail wood in planks 10 cudm 0.025 300
364 9999 Painting or varnishing or beewaxing L.S. 4.42 2
365 9999 Sundries Nails etc. L.S. 2.73 2
366 15 Carpenter 2nd class day 0.2 403.67
367 21 Glazier day 0.25 403.67
368 17 Beldar day 0.45 350.00
369 9999 Sundries such as Rag, cotton etc L.S. 1.82 2
370 TOTAL
371 Add 1 % Water charges on "W"
372 TOTAL
373 Add GST (multiplying factor 0.1405) on "X"
374 TOTAL
375 Add 15 % Contractor's profit and overheads on "Y"
376 Total
377 Add Cess @ 1% on "Z"
378 Cost of 1.00 sqm
379 Say
380
381
382
383 14.6.2 Float glass panes of thickness 5.0 mm
384 (weight not for
Detail of cost less than 12.50
10 glasses kg/sqm)
area each 0.1sqm.
385 MATERIAL
386 2407 Float glass sheet of nominal thickness 5.0 sqm 1.1 500
387 mm.(weight not less than 12.50 kg/sqm).
388 1.00 sqm + 10% wastage= 1.10 Sqm
389 1189 Second class teak wood in scantling 10 cudm 0.025 776
390 1194 Second class deodar wood in planks 10 cudm 0.025 500
399 1196 First class kail wood in planks 10 cudm 0.025 300
400 9999 Painting or varnishing or beewaxing L.S. 4.42 2
401 9999 Sundries Nails etc. L.S. 2.73 2
402 15 Carpenter 2nd class day 0.2 403.67
403 21 Glazier day 0.25 403.67
404 17 Beldar day 0.45 350.00
405 9999 Sundries such as Rag, cotton etc L.S. 1.82 2
406 TOTAL
407 Add 1 % Water charges on "W"
408 TOTAL
409 Add GST (multiplying factor 0.1405) on "X"
410 TOTAL
411 Add 15 % Contractor's profit and overheads on "Y"
412 Total
413 Add Cess @ 1% on "Z"
414 Cost of 1.00 sqm
415 Say
416
417
418
419 14.7 Renewing glass panes and refixing
420 14.7.1 existing wooden
Float glass panes fillets:
of thickness 4 mm
421 (weight not for
Detail of cost less than 10kg/sqm)
10 glasses area each 0.1sqm.
422 MATERIAL
423 2406 Float glass sheet of nominal thickness 4 mm sqm 1.1 300
424 (weight not less than 10kg/sqm).
425 1.00 sqm + 10% wastage= 1.10 Sqm
426 9977 Carriage of glasspanes and other materials L.S. 2.73 2
427 9999 Sundries Nails etc. L.S. 9.88 2
428 9999 Methylated spirit L.S. 5.33 2
429 21 Glazier day 0.3 403.67
430 17 Beldar day 0.3 350.00
431 9999 Sundries L.S. 1.43 2
432 TOTAL
433 Add 1 % Water charges on "W"
434 TOTAL
435 Add GST (multiplying factor 0.1405) on "X"
436 TOTAL
437 Add 15 % Contractor's profit and overheads on "Y"
438 Total
439 Add Cess @ 1% on "Z"
440 Cost of 1.00 sqm
441 Say
442
444
452
453 14.7.2 Float glass panes of thickness 5.0 mm
454 (weight not less than 12.50 kg/sqm)
455 Detail of cost for 10 glasses area each 0.1sqm.
456 MATERIAL
457 2407 Float glass sheet of nominal thickness 5.0 sqm 1.1 500
458 mm.(weight not less than 12.50 kg/sqm).
459 1.00 sqm + 10% wastage= 1.10 Sqm
460 9977 Carriage of glasspanes and other materials L.S. 2.73 2
461 9999 Sundries Nails etc. L.S. 9.88 2
462 9999 Methylated spirit L.S. 5.33 2
463 21 Glazier day 0.3 403.67
464 17 Beldar day 0.3 350.00
465 9999 Sundries L.S. 1.43 2
466 TOTAL
467 Add 1 % Water charges on "W"
468 TOTAL
469 Add GST (multiplying factor 0.1405) on "X"
470 TOTAL
471 Add 15 % Contractor's profit and overheads on "Y"
472 Total
473 Add Cess @ 1% on "Z"
474 Cost of 1.00 sqm
475 Say
477
478
479 14.8 Supplying and fixing new wooden fillets
480 14.8.1 wherever
2nd classnecessary:
teak wood fillets
481 Details of cost for 10 metres length
482 MATERIAL
483 1190 Second class teak wood in planks 10 cudm 0.115 791
484 10.00x0.01x0.01 = 1.00 cudm
485 Add 15% wastage = 0.15 cudm
486 Total = 1.15 cudm
487 9999 Nails L.S. 26.91 2
488 LABOUR
489 15 Carpenter 2nd class day 0.25 403.67
498 17 Beldar day 0.25 350.00
499 9999 Sundries L.S. 2.73 2
500 TOTAL
501 Add 1 % Water charges on "W"
502 TOTAL
503 Add GST (multiplying factor 0.1405) on "X"
504 TOTAL
505 Add 15 % Contractor's profit and overheads on "Y"
505.17 Total
506 Add Cess @ 1% on "Z"
507 Cost of 10.00 metre
508 Cost of 1.00 metre
509 Say
510
511
512
513 14.8.2 Hollock wood fillets
514 Details of cost for 10 metres length
515 MATERIAL
516 2466 Hollock wood in scantling 10 cudm 0.115 350
517 10.00x0.01x0.01 = 1.00 cudm
518 Add 15% wastage = 0.15 cudm
519 Total = 1.15 cudm
520 9999 Nails L.S. 26.91 2
521 LABOUR
522 15 Carpenter 2nd class day 0.25 403.67
523 17 Beldar day 0.25 350.00
524 9999 Sundries L.S. 2.73 2
525 TOTAL
526 Add 1 % Water charges on "W"
527 TOTAL
528 Add GST (multiplying factor 0.1405) on "X"
529 TOTAL
530 Add 15 % Contractor's profit and overheads on "Y"
531 Total
532 Add Cess @ 1% on "Z"
533 Cost of 10.00 metre
534 Cost of 1.00 metre
535 Say
536
545
546 14.9 Renewal of old putty of glass panes
(length)
547
548 Details of cost for 13 metres length
549 MATERIAL
550 863 Putty for wood work kilogram 0.68 30
551 9999 Nails L.S. 7.15 2
552 9999 Spirit L.S. 2.73 2
553 LABOUR
554 15 Carpenter 2nd class day 0.3 403.67
555 17 Beldar day 0.3 350.00
556 9999 Sundries L.S. 1.43 2
557 TOTAL
558 Add 1 % Water charges on "W"
559 TOTAL
560 Add GST (multiplying factor 0.1405) on "X"
561 TOTAL
562 Add 15 % Contractor's profit and overheads on "Y"
563 Total
564 Add Cess @ 1% on "Z"
565 Cost of 13.00 metres
566 Cost of 1.00 metre
567 Say
568
569
570 14.10 Refixing old glass panes with putty and
571 nails
Details of cost for 1 sqm
572 863 Putty for wood work kilogram 0.68 30
573 9999 Spirit L.S. 2.73 2
574 9999 Nails L.S. 7.15 2
575 LABOUR
576 21 Glazier day 0.3 403.67
577 17 Beldar day 0.3 350.00
578 9999 Sundries L.S. 1.43 2
579 TOTAL
580 Add 1 % Water charges on "W"
581 TOTAL
582 Add GST (multiplying factor 0.1405) on "X"
583 TOTAL
584 Add 15 % Contractor's profit and overheads on "Y"
585 Total
586 Add Cess @ 1% on "Z"
587 Cost of 1.00 sqm
588 Say
589
598
599
600 14.11 Fixing old glass panes with wooden fillets
601 (excluding
Detail of cost cost of fillets)
for 1 sqm
602 LABOUR
603 21 Glazier day 0.3 403.67
604 17 Beldar day 0.3 350.00
605 9999 Sundries L.S. 1.43 2
606 9999 Nails L.S. 3.9 2
607 TOTAL
608 Add 1 % Water charges on "W"
609 TOTAL
610 Add GST(multiplying factor 0.1405) on "X"
611 TOTAL
612 Add 15 % Contractor's profit and overheads on "Y"
613 Total
614 Add Cess @ 1% on "Z"
615 Cost of 1.00 sqm
616 Say
617
618
619 14.12 Providing and fixing 16 mm M.S. Fan
620 clamps
Details of of standard
cost shape
for each fan and size in
clamp.
621 MATERIAL
622 M.S.bar 16mm dia = 40cm (including
623 1003 wastage) @ 1.58 kg/m = 0.632 kg
624 Mild steel round bar above 12 mm dia quintal 0.00632 4400
625 9999 Cement concrete 1:2:4 (1 Cement : 2 L.S. 13.52 2
626 Coarse sand : 4 graded stone aggregate
627 20mm nominal size) mortar for rendering or
628 9999 plastering
629 Painting two or more coats to exposed L.S. 7.15 2
630 portion of the clamp including priming coat
631 12 Labour for fixing
632 Blacksmith 1st class day 0.03 505.17
633 24 Mason (brick layer) 2nd class day 0.12 403.67
634 17 Beldar day 0.25 350.00
644 9999 Sundries L.S. 2.73 2
645 TOTAL
646 Add 1 % Water charges on "W"
647 TOTAL
648 Add GST (multiplying factor 0.1405) on "X"
649 TOTAL
650 Add 15 % Contractor's profit and overheads on "Y"
651 Total
652 Add Cess @ 1% on "Z"
653 Cost of each
654 Say
655
659
660 14.13 Regrading terracing of mud phaska
661 covered with
Detail of cost fortiles or brick, in cement
10 sqm
662 (i) Dismantling tiles/bricks in cement mortar including
removing mud plaster and
663 cleaning the tiles/bricks
664 LABOUR
665 40 Mason (average) day 0.54 403.67
666 17 Beldar day 0.54 350.00
667 (ii) Preparing the surface, for mud phuska to
668 proper slope, relaying mud plaster gobri
669 40 leeping.
670 Mason (average) day 0.27 403.67
671 25mm thick mud plaster including gobri
672 leaping
673 MATERIAL
674 Mud mortar
675 3.18 Rate as per Item Number 3.18 of SH: Mortars cum 0.24 494.3
676 308 Bhusa quintal 0.084 500
677 Gobri mortar
678 3.18 Rate as per Item Number 3.18 of cum 0.12 494.3
679 SH: Mortars
680 LABOUR
681 17 Beldar day 0.25 350.00
682 3.3 (iii) relaying tiles/bricks (Rate as per item No cum 0.061 3988
683 3.3) including Cement mortar 1:3 (1 Cement :
692 3 fine sand) for grouting
693 LABOUR
694 40 Mason (average) day 1.2 403.67
695 17 Beldar day 1.5 350.00
696 11 Bhisti day 1 350.00
697 9999 Disposal of mulba L.S. 5.33 2
698 9999 Sundries L.S. 2.73 2
699 TOTAL
700 Add 1 % Water charges on "W"
701 TOTAL
702 Add GST (multiplying factor 0.1405) on "X"
703 TOTAL
704 Add 15 % Contractor's profit and overheads on "Y"
705 Total
706 Add Cess @ 1% on "Z"
707 Cost of 10.00 sqm
708 Cost of 1.00 sqm
709 Say
710
711
712 14.14 Replacing sand stone slabs in roofing,
713 14.14.1 laid
Red/inwhite
cementsand mortar
stone1:4 (1 cement
slabs 30 to 50: mm
4
714 thick
Detail of cost for 10 sqm
715 Dismantling existing stone, slabs roofing
716 17 1x10 sqmx0.05m = 0.50 cum.
717 Beldar day 0.885 350.00
718 18 Coolie day 0.375 350.00
719 9999 Sundries L.S. 4.03 2
720 9999 Cleaning the surface including necessary L.S. 40.43 2
721 repairs
722 1174 Red sand stone slab 45 mm and 50 mm thick sqm 11 225
723 (un-dressed)
724 2216 Carriage of Stone blocks white & red sand tonne 1.41 94.34
725 stone & kota stone slab
726 Cement mortar 1 : 4 (1 cement : 4 coarse
727 3.9 sand)
728 Rate as per Item Number 3.9 of SH: Mortars cum 0.0105 3815.05
729 3.3 Cement mortar 1 : 3 (1 cement : 3 fine sand) 3670.3
730 Rate as per Item Number 3.3 of SH: Mortars cum 0.0075 3988
731 40 Mason (average) day 1.69 403.67
732 10 Bandhani day 2.03 350.00
733 18 Coolie day 1.69 350.00
743 11 Bhisti day 0.34 350.00
744 9999 Sundries L.S. 16.12 2
745 2264 Carriage of Rubbish cum 0.5 94.34
746 TOTAL
747 Add 1 % Water charges on "W"
748 TOTAL
749 Add GST (multiplying factor 0.1405) on "X"
750 TOTAL
751 Add 15 % Contractor's profit and overheads on "Y"
752 Total
753 Add Cess @ 1% on "Z"
754 Cost of 10.00 sqm
755 Cost of 1.00 sqm
756 Say
757
758
759 14.15 Renewing wooden battens in roofs,
760 14.15.1 including making good the holes in wall
Sal wood battens
761 Details of cost for 10 battens i.e. 300 cudm
762 3 metres long of 100x100mm
763 10x3x0.1x0.1 = 0.3cum =300cudm
764 Add wastage @ 2%= 6 cudm, Total
765 = 306 cudm
766 MATERIAL
767 1199 Sal wood in scantling 10 cudm 30.6 600
768 2204 Carriage of Timber cum 0.306 121.29
769 LABOUR
770 Taking out the existing battens and refixing
771 15 new one including supporting the roof
772 Carpenter 2nd class day 0.5 403.67
773 17 Beldar day 2 350.00
774 9999 Disposal of mulba L.S. 5.33 2
775 9999 Making good the holes including sundries L.S. 80.73 2
776 859 Oil type wood preservative litre 1.22 130
777 31 Painter day 0.183 403.67
778 18 Coolie day 0.183 350.00
779 9977 Carriage L.S. 0.78 2
780 9999 Brushes L.S. 5.07 2
781 9999 Sundries L.S. 4.81 2
791 TOTAL
792 Add 1 % Water charges on "W"
793 TOTAL
794 Add GST (multiplying factor 0.1405) on "X"
795 TOTAL
796 Add 15 % Contractor's profit and overheads on "Y"
797 Total
798 Add Cess @ 1% on "Z"
799 Cost of 300 Cudm
800 Cost of 1.00 cum
801 Say
802
803
804 14.16 Renewing wooden beams in roofs
805 14.16.1 including making
Not exceeding good
4.00 the in
metres holes in walls
length.
806 14.16.1.1 Sal wood beams
807 Details of cost for 300 cudm or 0.3 cum
808 Consider one beam i.e. 300 cudm.
809 0.25 x 0.30m x 4.0m (long) = 0.30 cum
810 Add wastage @ 2% (0.006 cum)
811 = 0.306 cum =306 cudm
812 (i) Propping the roof
813 MATERIAL
814 100mm diameter ballies 4m long 10 nos.
815 100x100mm salwood battens 1.0 metre long
816 5 nos.x1.0x0.1x0.1 =0.05cum = 50 cudm.
817 These materials can be used for 16 times
818 Hence qty for one operation 1/16
819 = 3.125 cudm
820 1199 Sal wood in scantling 10 cudm 0.3125 600
821 2204 Carriage of Timber cum 0.0228 121.29
822 LABOUR
823 15 Carpenter 2nd class day 0.25 403.67
824 17 Beldar day 0.25 350.00
825 (ii) Taking out the existing beams etc.
826 LABOUR
827 40 Mason (average) day 0.13 403.67
828 10 Bandhani day 0.5 350.00
829 17 Beldar day 0.33 350.00
830 (iii) Renewal
831 Materials and Labour
832 1199 Sal wood in scantling 10 cudm 30.6 600
842 2204 Carriage of Timber cum 0.306 121.29
843 15 Carpenter 2nd class day 1 403.67
844 10 Bandhani day 0.5 350.00
845 17 Beldar day 1 350.00
846 Painting with oil preservative
847 (4x1.1) +( 2.0x0.25x0.30) =4.4 + 0.15= 4.55
848 sqm @ 1 ltr / 10 sqm=0.455 litre.
849 859 Oil type wood preservative litre 0.455 130
850 31 Painter day 0.07 403.67
851 18 Coolie day 0.07 350.00
852 9999 Sundries L.S. 0.13 2
853 9977 Carriage L.S. 1.82 2
854 9999 Brushes L.S. 1.82 2
855 9999 Making good the holes L.S. 20.67 2
856 9999 Sundries L.S. 26.91 2
857 302 Safeda ballies 125 mm diameter metre 2.5 40
858 TOTAL
859 Add 1 % Water charges on "W"
860 TOTAL
861 Add GST (multiplying factor 0.1405) on "X"
862 TOTAL
863 Add 15 % Contractor's profit and overheads on "Y"
864 Total
865 Add Cess @ 1% on "Z"
866 Cost of 300 Cudm
867 Cost of 1.00 cum
868 Say
869
870
871 14.16.1.2 Hollock wood beams
872 Details of cost for 300 cudm or 0.3 cum
873 Consider one beam
874 0.25 x 0.30m x 4.0m (long) = 0.30 cum
875 = 300 cudm
876 Add wastage @ 2% (0.006 cum)
877 = 0.306 cum =306cudm
878 (I) Propping the roof
879 MATERIAL
880 100mm diameter ballies 4m long 10 nos.
881 100x100mm salwood battens 1.0metre long 5
882 nos.x1.0x0.1x0.1 =0.05cum = 50 cudm.
883 These materials can be used for 16 times
884 hence qty for one operation 1/16 = 3.125
885 2466 cudm
886 Hollock wood in scantling 10 cudm 0.3125 350
887 2204 Carriage of Timber cum 0.0228 121.29
898 LABOUR
899 15 Carpenter 2nd class day 0.25 403.67
900 17 Beldar day 0.25 350.00
901 (ii) Taking out the existing beams etc.
902 LABOUR
903 40 Mason (average) day 0.13 403.67
904 10 Bandhani day 0.5 350.00
905 17 Beldar day 0.33 350.00
906 (iii) Renewal
907 Materials and Labour
908 2466 Hollock wood in scantling 10 cudm 30.6 350
909 2204 Carriage of Timber cum 0.306 121.29
910 15 Carpenter 2nd class day 1 403.67
911 10 Bandhani day 0.5 350.00
912 17 Beldar day 1 350.00
913 Painting with oil preservative
914 (4x1.1) +( 2.0x0.25x0.30) =4.4 + 0.15= 4.55
915 sqm @ 1 ltr / 10 sqm=0.455 litre.
916 859 Oil type wood preservative litre 0.455 130
917 31 Painter day 0.07 403.67
918 18 Coolie day 0.07 350.00
919 9999 Sundries L.S. 0.13 2
920 9977 Carriage L.S. 1.82 2
921 9999 Brushes L.S. 1.82 2
922 9999 Making good the holes L.S. 20.67 2
923 9999 Sundries L.S. 26.91 2
924 302 Safeda ballies 125 mm diameter metre 2.5 40
925 TOTAL
926 Add 1 % Water charges on "W"
927 TOTAL
928 Add GST (multiplying factor 0.1405) on "X"
929 TOTAL
930 Add 15 % Contractor's profit and overheads on "Y"
931 Total
932 Add Cess @ 1% on "Z"
933 Cost of 300 Cudm
934 Cost of 1.00 cum
935 Say
936
946
947
948 14.16.2 Above 4.00 metres and upto 5.00 metres
949 length.
14.16.2.1 Sal wood beams
950 Details of cost for 375 cudm or 0.375 cum
952 Consider one beam i.e. 375 cudm. 0.25 x 0.30m x
5.0m (long) = 0.375 cum
954 Add wastage @ 2% (0.008 cum) = 0.383 cum =
383cudm
956 (i) Propping the roof
958 MATERIAL
959 125mm diameter ballies 5m long 12 nos
960 100x100mm salwood battens 1.0 metre long
961 6 nos. x1.0x0.1x0.1 = 60 cudm. These
962 materials can be used for 16 times hence qty
963 1199 for one operation 1/16 = 3.75 cudm
964 Sal wood in scantling 10 cudm 0.375 600
965 2204 Carriage of Timber cum 0.0498 121.29
966 LABOUR
967 15 Carpenter 2nd class day 0.25 403.67
968 17 Beldar day 0.25 350.00
969 (ii) Taking out the existing beams etc.
970 LABOUR
971 40 Mason (average) day 0.25 403.67
972 10 Bandhani day 0.63 350.00
973 17 Beldar day 0.5 350.00
974 (iii) Renewal
975 Materials and Labour
976 1199 Sal wood in scantling 10 cudm 38.3 600
977 2204 Carriage of Timber cum 0.383 121.29
978 15 Carpenter 2nd class day 1 403.67
979 10 Bandhani day 1 350.00
980 17 Beldar day 2 350.00
981 Painting with oil preservative
982 (2x5x0.25)+3.0 + 2.0x0.25x0.30
983 = 5.5 + 0.15 = 5.65 sqm @ 1 litre / 10 sqm =0.565 litre.
984 859 Oil type wood preservative litre 0.565 130
985 31 Painter day 0.08 403.67
986 18 Coolie day 0.08 350.00
987 9999 Sundries L.S. 0.26 2
988 9977 Carriage L.S. 2.34 2
989 9999 Brushes L.S. 2.21 2
990 9999 Making good the holes L.S. 20.67 2
991 9999 Sundries L.S. 33.15 2
992 302 Safeda ballies 125 mm diameter metre 3.75 40
1003 TOTAL
1004 Add 1 % Water charges on "W"
1005 TOTAL
1006 Add GST (multiplying factor 0.1405) on "X"
1007 TOTAL
1008 Add 15 % Contractor's profit and overheads on "Y"
1009 Total
1010 Add Cess @ 1% on "Z"
1011 Cost of 375 Cudm
1012 Cost of 1.00 cum
1013 Say

1014 14.16.2.2 Hollock wood beams


1015 Details of cost for 375 cudm or 0.375 cum
1016 Consider one beam i.e. 375 cudm.
1017 0.25 x 0.30m x 5.0m (long) = 0.375 cum
1018 Add wastage @ 2% (0.008 cum)
1019 = 0.383 cum = 383cudm
1020 (i) Propping the roof
1021 MATERIAL
1022 125mm diameter ballies 5m long 12 nos
1023 100x100mm salwood battens 1.0 metre long
1024 6 nos. x1.0x0.1x0.1 = 60 cudm. These
1025 materials can be used for 16 times hence qty
1026 for one operation 1/16 = 3.75 cudm
1027 2466 Hollock wood in scantling 10 cudm 0.375 350
1028 2204 Carriage of Timber cum 0.0375 121.29
1029 LABOUR
1030 15 Carpenter 2nd class day 0.25 403.67
1031 17 Beldar day 0.25 350.00
1032 (ii) Taking out the existing beams etc.
1033 LABOUR
1034 40 Mason (average) day 0.25 403.67
1035 10 Bandhani day 0.63 350.00
1036 17 Beldar day 0.5 350.00
1037 (iii) Renewal
1038 Materials and Labour
1039 2466 Hollock wood in scantling 10 cudm 38.3 350
1040 2204 Carriage of Timber cum 0.383 121.29
1041 15 Carpenter 2nd class day 1 403.67
1042 10 Bandhani day 1 350.00
1043 17 Beldar day 2 350.00
1044 Painting with oil preservative
1055 (2x5x0.25)+3.0 + 2.0x0.25x0.30
1056 = 5.5 + 0.15 = 5.65 sqm @ 1 litre / 10 sqm =0.565 litre.
1057 859 Oil type wood preservative litre 0.565 130
1058 31 Painter day 0.08 403.67
1059 18 Coolie day 0.08 350.00
1060 9999 Sundries L.S. 0.26 2
1061 9977 Carriage L.S. 2.34 2
1062 9999 Brushes L.S. 2.21 2
1063 9999 Making good the holes L.S. 20.67 2
1064 9999 Sundries L.S. 33.15 2
1065 302 Safeda ballies 125 mm diameter metre 3.75 40
1066 TOTAL
1067 Add 1 % Water charges on "W"
1068 TOTAL
1069 Add GST (multiplying factor 0.1405) on "X"
1070 TOTAL
1071 Add 15 % Contractor's profit and overheads on "Y"
1072 Total
1073 Add Cess @ 1% on "Z"
1074 Cost of 375 Cudm
1075 Cost of 1.00 cum
1076 Say
1077
1078
1079 14.17 Raking out joints in lime or cement mortar
1080 and
Detailpreparing the
of cost for 10 surface for repointing or
sqm
1081 LABOUR
1082 17 Beldar day 0.53 350.00
1083 18 Coolie day 0.08 350.00
1084 11 Bhisti day 0.07 350.00
1085 9999 Sundries L.S. 1.43 2
1086 TOTAL
1087 Add 1 % Water charges on "W"
1088 TOTAL
1089 Add GST(multiplying factor 0.1405) on "X"
1090 TOTAL
1091 Add 15 % Contractor's profit and overheads on "Y"
1092 Total
1093 Add Cess @ 1% on "Z"
1094 Cost of 10.00 sqm
1095 Cost of 1.00 sqm
1096 Say
1097
1098
1107 14.18 Flush pointing with cement mortar 1:3 (1
1108 cement : 3 fine sand) mixed with 2% of
1109 14.18.1 With F.P.S. brick tiles
1110 Detail of cost for 10 sqm
1111 MATERIAL
1112 Cement mortar 1 : 3 (1 cement : 3 fine sand)
1113 3.3 Rate as per Item Number 3.3 of SH: Mortars cum 0.015 3988
1114 1213 Water proofing materials kilogram 0.153 35
1115 2% of wt. of cement
1116 LABOUR
1117 18 Coolie day 0.36 350.00
1118 24 Mason (brick layer) 2nd class day 0.36 403.67
1119 11 Bhisti day 0.36 350.00
1120 9999 Sundries L.S. 18.85 2
1121 TOTAL
1122 Add 1 % Water charges on "W"
1123 TOTAL
1124 Add GST (multiplying factor 0.1405) on "X"
1125 TOTAL
1126 Add 15 % Contractor's profit and overheads on "Y"
1127 Total
1128 Add Cess @ 1% on "Z"
1129 Cost of 10.00 sqm
1130 Cost of 1.00 sqm
1131 Say

1132 14.18.2 With modular brick tiles


1133 Detail of cost for 10 sqm
1134 MATERIAL
1135 Cement mortar 1 : 3 (1 cement : 3 fine sand)
1136 3.3 Rate as per Item Number 3.3 of SH: Mortars cum 0.017 3988
1137 1213 Water proofing materials kilogram 0.173 35
1138 2% of wt. of cement
1139 LABOUR
1140 18 Coolie day 0.36 350.00
1141 24 Mason (brick layer) 2nd class day 0.36 403.67
1142 11 Bhisti day 0.36 350.00
1143 9999 Sundries L.S. 18.85 2
1144 TOTAL
1145 Add 1 % Water charges on "W"
1146 TOTAL
1147 Add GST (multiplying factor 0.1405) on "X"
1148 TOTAL
1149 Add 15 % Contractor's profit and overheads on "Y"
1151 Total
1152 Add Cess @ 1% on "Z"
1153 Cost of 10.00 sqm
1154 Cost of 1.00 sqm
1155 Say
1156
1165
1166
1167
1168
1169 14.19 Taking out wind ties from roof including
1170 cutting
Details ofout
costrusted bolts,
for 30 mtrs nuts 63
of weight etc.
kgsand
M.S.
Flats 40x6mm @ 1.9kg./m
1171 = 30x1.9 = 57 kg. (A)
1172 J' hook bolts @ 30cm centre to centre = 101 Nos. x
0.15 m = 15.15 m @ 0.40kg./ m = 6.06kg (B)
1173 Total (A+B) = 63.06 kg Say 63 kg
1174
1175 LABOUR
1176
1177 13 Blacksmith 2nd class day 0.09 403.67
1178 10 Bandhani day 0.06 350.00
1179 17 Beldar day 0.16 350.00
1180 TOTAL
1181 Add 1 % Water charges on "W"
1182 TOTAL
1183 Add GST (multiplying factor 0.1405) on "X"
1184 TOTAL
1185 Add 15 % Contractor's profit and overheads on "Y"
1186 Total
1187 Add Cess @ 1% on "Z"
1188 Cost for 63 kg.
1189 Cost of 1.00 kg
1190 Say
1191
1200
1201 14.20 Fixing of old wind tie with new fittings
1203 including painting
Detail of cost for 20.2 mtwo ortiemore coats with
wind
1205 MATERIAL
1206 1023 Galvanised steel J or L hooks 8 mm dia 10 Nos 6.8 120
1207 @ 30 cm center to center = 68 Nos
1208 1208 Bitumen washer 100 Nos 0.68 30
1209 1209 G.I. plain washer thick 100 Nos 0.68 35
1210 9977 Carriage of bolts, nuts and washers etc. L.S. 1.17 2
1211 LABOUR
1212 12 Blacksmith 1st class day 0.34 505.17
1213 17 Beldar day 0.34 350.00
1214 9999 Sundries L.S. 13.91 2
1215 Applying priming coat with ready mixed zink
1216 chromate yellow primer 20.2x2x(0.04+0.006)
1217 13.50.3 = 1.86 sqm
1218 Rate as per item no 13.50.3 of sqm 1.86 33.3
1219 SH : Finishing
1220 Painting with ready mixed black antcorrosive
1221 13.65.1 bitumastic paint
1222 Rate as per item No.13.65.1 SH: Finishing sqm 1.86 66.9
1223 TOTAL
1224 Add 1 % Water charges on "W-A" 1161.28
1225 TOTAL
1226 Add GST (multiplying factor 0.1405) on "X-A" 1172.9
1227 TOTAL
1228 Add 15 % Contractor's profit and overheads 1337.69
1229 on "Y-A"
1230 Total
1231 Add Cess @ 1% on "Z-A" 1538.34
1232 Cost of 20.2 metres
1233 Cost of 1.00 metre
1234 Say
1235
1236
1237
1238 14.21 Renewing bottom rail and/or top runner
1239 of collapsible
yellow primer gate including
of approved making
brand andgood
1240 manufacturer.
Detail of cost for gate of size 1.52x2.4 m
1241
1242 (weight 11.55 kg)
1243 MATERIAL
1244 M.S. Tee 40x40x6 mm
1245 Top rail = 1.725 m
1246 Bottom rail = 1.570 m
1247 Total = 3.295 m say 3.30 m @ 3.5 kg/m
1248 = 11.55 kg
1249 Add 10% wastage = 1.155 kg
1250 Total = 12.705 kg = 0.1270 q say 0.13 q
1251 1007 Structurals such as tees,angles channels and 0.13 4600
1252 quintal
R.S. joists
1261 2205 Carriage of Steel tonne 0.013 94.34
1262 Taking out collapsible gate including frame
1263 15.12.2 (Rate as per item no 15.12.2 of each 1 214.85
1264 SH Dismantling and Demolishing) Refixing of
1265 collapsible gate including mending good the
1266 demaged floor, wall etc.frame
1267 Cement concrete 1:3:6 (1 cement : 3 coarse
1268 sand : 6 graded stone aggregate 20 mm
1269 4.2.5 nominal size)
1270 Rate as per item no 4.2.5 of cum 0.03 6577.55
1271 SH : Concrete work
1272 3.6 Cement mortar 1 : 6 (1 cement : cum 0.01 2508.3
1273 6 fine sand) (Rate as per item No 3.6)
1274 9999 Cement concrete 1:2:4 filled in chase cut L.S. 24.18 2
1275 9999 Disposal of mulba L.S. 1.82 2
1276 Priming coat on Tees 0.16x3.3 = 0.53 sqm
1277 13.50.3 Rate as per item no 13.50.3 of sqm 0.53 33.3
1278 SH : Finishing
1279 LABOUR
1280 Labour for fixing the gate
1281 40 Mason (average) day 0.5 403.67
1282 17 Beldar day 0.75 350.00
1283 9999 Sundries L.S. 2.6 2
1284 TOTAL
1285 Add 1 % Water charges on "W-A" 1111.09
1286 TOTAL
1287 Add GST (multiplying factor 0.1405) on "X-A" 1122.2
1288 TOTAL
1289 Add 15 % Contractor's profit and overheads 1279.87
1290 on "Y-A"
1291 Total
1292 Add Cess @ 1% on "Z-A" 1471.85
1293 Cost of 11.55 kg
1294 Cost of 1.00 kg
1295 Say
1296
1297
1298
1299 14.22 Renewing Wrought iron or M.S. Wheel or
1300 14.22.1 roller
Wheelof50steel
mm door or gate
dia and belowand fitting and
1301 Detail of cost for 10 nos wheels of 40 mm dia.
1303 MATERIAL
1305 Weight of 10 nos wheels
10x[3.14x{(4/2)x(4/2)}x4]x7.850/1000 = 3.94 kg
1306
1307 Weight of 10 nos clamps 6 mm thick =10x lenth of clamp
=10x0.17m @ 1.90kg/m =
1316 3.23 kg
1317 Weight of 10 nos 10 mm dia. Bolts, 10 cm
1318 long 10x0.10m = 1m @ 0.60 kg/m = 0.60 kg
1319 Total = 7.70 kg say 8 kg Labour for
1320 13 dismantling :
1321 13 Blacksmith 2nd class day 0.01 403.67
1322 10 Bandhani day 0.01 350.00
1323 17 Beldar day 0.02 350.00
1324 9999 Sundries L.S. 0.39 2
1325 Renewing the wheels with clamps :-
1326 MATERIAL
1327 7442 Wheel 75 mm dia. 40 mm wide each 10 62
1328 10 nos clamps out of M.S. flat 40x6 mm, 170
1329 mm long = 10x0.17m = 1.70m @ 1.9 kg/m =
1330 3.23 kg
1331 Add 5% wastage = 0.16 kg
1332 Total = 3.39 kg say 3.50 kg
1333 1008 Flats upto 10 mm in thickness quintal 0.035 4500
1334 M.S. bolt/pin 10 mm dia 10 cm long 10 Nos
1335 10x0.06 = 0.6 kg = 0.006 q
1336 1034 Bolts and nuts upto 300 mm in length quintal 0.006 6800
1337 1215 Welding by electric plant cm 80 2
1338 length = 10x(2x4) = 80cm
1339 LABOUR
1340 Labour for cutting, assembling and errection
1341 12 charges
1342 Blacksmith 1st class day 0.03 505.17
1343 10 Bandhani day 0.02 350.00
1344 17 Beldar day 0.11 350.00
1345 Priming coat : = 10x2(0.06+0.008)x0.25m =
1346 13.50.3 0.34 sqm on Tees 0.16x3.3 = 0.53 sqm
1347 Rate as per item no 13.50.3 of SH : Finishing sqm 0.165 33.3
1348 9999 Sundries L.S. 1.69 2
1349 TOTAL
1350 Add 1 % Water charges on "W-A" 1039.82
1351 TOTAL
1352 Add GST (multiplying factor 0.1405) on "X-A" 1050.22
1353 TOTAL
1354 Add 15 % Contractor's profit and overheads 1197.77
1355 on "Y-A"
1356 Total
1357 Add Cess @ 1% on "Z-A" 1377.44
1358 Cost of 10 nos wheels
1359 Cost per wheel
1360 Say
1361
1362 14.22.2 Wheel above 50 mm dia
1363 Detail of cost for 10 nos wheels
1373 Considering average wheel dia =75 mm
1374 Width of wheel = 40 mm M.S. flat for clamp =
1375 60x8 mm Bolt size 16 mm dia.
1376 Lenth of one clamp :
1377 2x(0.04+0.0375+0.02)+0.05 =0.195+0.05
1378 =0.245m say 0.25m
1379 MATERIAL
1380 Weight of 10 nos wheels
1381 10x[3.14x{(7.5/2)x(7.5/2)}x4]x7.850/1000
1382 = 13.87 kg
1383 Weight of 10 nos clamps 8 mm thick
1384 =10x0.25 m @ 3.8kg/m = 9.50 kg
1385 Weight of 10 nos 16 mm dia. Bolts, 10 cm
1386 long 10x0.10 m @ 1.60 kg/m = 1.60 kg Total
1387 = 24.97 kg say 25 kg
1388 Labour for dismantling :
1389 13 Blacksmith 2nd class day 0.04 403.67
1390 10 Bandhani day 0.03 350.00
1391 17 Beldar day 0.06 350.00
1392 9999 Sundries L.S. 1.04 2
1393 Renewing the wheels with clamps :-
1394 MATERIAL
1395 7442 Wheel 75 mm dia. 40 mm wide each 10 62
1396 10 nos clamps out of M.S. flat 60x8 mm
1397 = 10x0.25 m @ 3.8 kg/m = 9.5 kg
1398 Add 5% wastage = 0.48 kg
1399 Total = 9.98 kg say 10 kg
1400 1008 Flats upto 10 mm in thickness quintal 0.1 4500
1401 M.S. bolt/pin 16 mm dia 10 cm long 10 Nos quintal 0.016 4800
1402 10x0.16= 1.6 kg = 0.016 q cm 120 2
1403 1034 Bolts and nuts upto 300 mm in length day 0.1 505.17
1404 1215 Welding by electric plant length = 10x(2x6) day 0.05 350.00
1405 LABOUR day 0.36 350.00
1406 Labour for cutting, assembling and errection sqm 0.34 33.3
1407 12 charges L.S. 5.33 2
1408 Blacksmith 1st class
1409 10 Bandhani
1410 17 Beldar
1411 Priming coat : = 10x2(0.06+0.008)x0.25m =
1412
1413 0.34 sqm on Tees 0.16x3.3 = 0.53 sqm
1414 13.50.3 Rate as per item no 13.50.3 of SH :
Finishing
1416 9999 Sundries
1417
1418 TOTAL
1419
1420 Add 1 % Water charges on "W-A"
1421
1422 TOTAL
1423
1424 Add GST (multiplying factor 0.1405) on "X-A"
1425
1426
1427 Unit Quantity Rate Amount
1471
1472 1622.54
1473
1474 1638.76
1485 TOTAL
1486 Add 15 % Contractor's profit and overheads 1869.01
1487 on "Y-A"
1488 Total
1489 Add Cess @ 1% on "Z-A" 2149.36
1490 Cost of 10 nos wheels
1491 Cost per wheel
1492 Say
1493

1494
1495 14.23 Pumping out water caused by springs,
1496 tidal
mains oror
river seepage,
drains broken
and the like. water
1497
1498 Details for 10.91 kilolitre
1499
1500 Pumping hours 3 hrs. or 0.375 days
1501 11 Hire charges of Pumpset of capacity 4000 day 0.375 700
1502 17 litres/hour.
1503 Beldar day 2 350.00
1504 for clearing slush
1505 TOTAL
1506 Add 1 % Water charges on "W"
1507 TOTAL
1508 Add GST (multiplying factor 0.1405) on "X"
1509 TOTAL
1510 Add 15 % Contractor's profit and overheads on "Y"
1511 Total
1512 Add Cess @ 1% on "Z"
1513 Cost of 10.91 kilolitre
1514 Cost of 1 kilolitre
1515 Say
1516
1517
1518 14.24 Mud mortar made with local clay good
1519 earth.
Detail of cost for 1 cum
1520 MATERIAL
1521 811 Mud (dry) cum 1.08 165
1522 LABOUR
1523 17 Beldar day 0.63 350.00
1524 11 Bhisti day 0.315 350.00
1525 9999 Sundries L.S. 6.45 2
1526 TOTAL
1527 Cost of 1 cum
1528 Say
1529
1530
1531
1532
1533
1534
1535
1537
1538
1539
1540
1541
1542
1543 14.25 Brick work with common burnt clay bricks
1544 of class designation 7.5 in mud
mortar
1545 Details of cost for 1 cum.
1546
1547 MATERIAL
1548 2602 Common burnt clay F.P.S. (non modular) 1000 Nos 0.494 5000
1549 bricks class designation 7.5 Mud mortar
1550 3.18 Rate as per Item Number 3.18 of SH: Mortars cum 0.25 494.3
1551 2201 Carriage of Bricks 1000 Nos 0.494 283.01
1552 9999 Sundries L.S. 2.73 2
1553 LABOUR
1554 23 Mason (brick layer) 1st class day 0.36 505.17
1555 24 Mason (brick layer) 2nd class day 0.36 403.67
1556 18 Coolie day 1.37 350.00
1557 11 Bhisti day 0.2 350.00
1558 TOTAL
1559 Add 1 % Water charges on "W"
1560 TOTAL
1561 Add GST (multiplying factor 0.1405) on "X"
1562 TOTAL
1563 Add 15 % Contractor's profit and overheads on "Y"
1564 Total
1565 Add Cess @ 1% on "Z"
1566 Cost of 1 Cum.
1567 Say
1568
1569
1570
1571
1572 14.26 Providing and fixing 25 mm thick shutters
1573 14.26.1 for cup board
Panelled etc. : & glazed shutters :
or panelled
1574 14.26.1.1 Superior class teak wood including nickel
1575 platedofbright
Details finished
cost for M.S.
shutter of piano200x108cm
cup-board hinges =
2.16 sqm.
1577 MATERIAL
1579 Styles
1581 4x200x8.0x2.5cm = 0.016 cum+ Rails
1583 Top rail
1584
1585 1x110.5x8.0x2.5cm = 0.0022cum+ Lock and
1586
1587 bottom rails
1588 2x110.5x8.0x2.5 cm = 0.0044 cum Panels
1589
1590 2x48x41x1.6cm = 0.006cum+ Sash bars
1591
1592 2x114x3.8x2.5cm = 0.0022cum+ 6x48x3.8x2.5cm =
0.003 cum+ Beading
1601 16x92x1.4x1.2cm = 0.002cum
1602 Total = 0.0358
1603 Add for wastage @ 10% = 0.0036 cum.
1604 Grand Total = 0.0394 cum = 39.40 cudm
1605 1186 say 39 cudm
1606 Superior class teak wood such as Dandeli, 10 cudm 3.9 1100
1607 2204 Balarshah or Malabar in planks
1608 Carriage of Timber cum 0.04 121.29
1609 2406 Float glass sheet of nominal thickness 4 mm sqm 0.99 300
1610 (weight not less than 10kg/sqm).
1611 Fittings-
1612 608 Nickel plated mild steel piono hinges 1 mm metre 4 39
1613 639 thick 25 mm wide
1614 Bright finished or black enamelled mild 100 Nos 1.2 36
1615 steel screws 25 mm
1616 LABOUR
1617 14 Carpenter 1st class day 2.4 505.17
1618 21 Glazier day 0.18 403.67
1619 17 Beldar day 0.77 350.00
1620 9999 Sundries L.S. 40.43 2
1621 TOTAL
1622 Add 1 % Water charges on "W"
1623 TOTAL
1624 Add GST (multiplying factor 0.1405) on "X"
1625 TOTAL
1626 Add 15 % Contractor's profit and overheads on "Y"
1627 Total
1628 Add Cess @ 1% on "Z"
1629 Cost of 2.16 sqm.
1630 Cost of 1 sqm.
1631 Say
1632
1633
1634
1635
1636
1637 14.26.1.2 Ist class teak wood including nickel plated
1638 bright of
Details finished M.S. piano
cost for shutters hinges with
of a cup-board (half
glazed and half panelled) 200x108cm =
1639 2.16 sqm.
1640 MATERIAL Styles
1641 4x200x8.0x2.5cm = 0.016 cum+ Rails
1642 Top rail
1644 1x110.5x8.0x2.5cm = 0.0022cum+ Lock and
1646 bottom rail
1648 2x110.5x8.0x2.5cm = 0.0044 cum. Panels
1650 2x48x41x1.6cm = 0.006cum+
1659 Sash bars
1660 2x114x3.8x2.5cm = 0.0022cum+
1661 6x48x3.8x2.5cm = 0.003 cum+
1662 Beading
1663 16x92x1.4x1.2cm = 0.002cum
1664 Total = 0.0358
1665 Add for wastage @ 10% = 0.0036 cum.
1666 Grand Total = 0.0394 cum = 39.40 cudm
1667 1188 say 39 cudm
1668 First class teak wood in planks 10 cudm 3.9 850
1669 2204 Carriage of Timber cum 0.04 121.29
1670 2406 Float glass sheet of nominal thickness 4 mm sqm 0.99 300
1671 (weight not less than 10kg/sqm).
1672 Fittings
1673 608 Nickel plated mild steel piono hinges 1 mm metre 4 39
1674 639 thick 25 mm wide
1675 Bright finished or black enamelled mild 100 Nos 1.2 36
1676 steel screws 25 mm
1677 LABOUR
1678 14 Carpenter 1st class day 2.4 505.17
1679 21 Glazier day 0.18 403.67
1680 17 Beldar day 0.77 350.00
1681 9999 Sundries L.S. 40.43 2
1682 TOTAL
1683 Add 1 % Water charges on "W"
1684 TOTAL
1685 Add GST (multiplying factor 0.1405) on "X"
1686 TOTAL
1687 Add 15 % Contractor's profit and overheads on "Y"
1688 Total
1689 Add Cess @ 1% on "Z"
1690 Cost of 2.16 sqm.
1691 Cost of 1 sqm.
1692 Say
1693

1694
1695 14.26.2 Glazed shutters :
1696 14.26.2.1 Superior class teak wood
1697 including nickel
Details of cost plated
for shutter of bright finished M.S.
cup-board
1698
1699 200x108cm = 2.16 sqm.
1700 MATERIAL
1701
1702 (i) Teak wood first class
1703
1704 Styles : 4x200x9.5x2.5 cm = 0.019 cum Rails
1705
1706 Top & intermediate rails 2x110.5x9.5x2.5 cm = 0.005
cum
1715 Lock and bottom rails
1716 2x110.5x19.7x2.5 cm = 0.011 cum
1717 Beadings-
1718 2x186.1x1.9x1.2cm = 0.001cum+
1719 4x171.70x1.9x1.2cm = 0.002cum.
1720 Total = 0.038 cum.
1721 Add for wastage @ 10% = 0.0038 cum.
1722 1186 Grand Total = 0.0418 cum = 42 cudm
1723 Superior class teak wood such as Dandeli, 10 cudm 4.2 1100
1724 2406 Balarshah or Malabar in planks
1725 Float glass sheet of nominal thickness 4 mm sqm 1.27 300
1726 608 (weight not less than 10kg/sqm).
1727 Nickel plated mild steel piono hinges metre 4 39
1728 1 mm thick 25 mm wide
1729 75x45x3.2 mm
1730 639 Bright finished or black enamelled mild steel 100 Nos 1.2 36
1731 597 screws 25 mm
1732 Bright finished or black enamelled mild steel 10 Nos 0.2 49
1733 640 butt hinges50x37x1.50 mm 30
1734 Bright finished or black enamelled mild steel 100 Nos 0.08 30
1735 2204 screws 20 mm
1736 Carriage of Timber cum 0.043 121.29
1737 LABOUR
1738 41 Carpenter (average) day 1.83 403.67
1739 21 Glazier day 0.23 403.67
1740 17 Beldar day 0.77 350.00
1741 9999 Sundries L.S. 40.43 2
1742 TOTAL
1743 Add 1 % Water charges on "W"
1744 TOTAL
1745 Add GST (multiplying factor 0.1405) on "X"
1746 TOTAL
1747 Add 15 % Contractor's profit and overheads on "Y"
1748 Total
1749 Add Cess @ 1% on "Z"
1750 Cost of 2.16 sqm.
1751 Cost of 1 sqm.
1752 Say
1753
1754
1755
1756
1757 14.26.2.2 Ist class teak wood including nickel plated
1758 bright finished
Details of M.S. piano
cost for shutter hinges with
of cup-board
1759 200x108cm = 2.16 sqm.
1760 MATERIAL
1761 (i) Teak wood first class
1763 Styles : 4x200x9.5x2.5 cm = 0.019 cum Rails
1765 Top & intermediate rails 2x110.5x9.5x2.5 cm = 0.005
cum
1774 Lock and bottom rails
1775 2x110.5x19.7x2.5 cm = 0.011 cum
1776 Beadings-
1777 2x186.1x1.9x1.2cm = 0.001cum+
1778 4x171.70x1.9x1.2cm = 0.002cum.
1779 Total = 0.038 cum.
1780 Add for wastage @ 10% = 0.0038 cum.
1781 1188 Grand Total = 0.0418 cum = 42 cudm
1782 First class teak wood in planks 10 cudm 4.2 850
1783 2406 Float glass sheet of nominal thickness 4 mm sqm 1.27 300
1784 608 (weight not less than 10kg/sqm).
1785 Nickel plated mild steel piono hinges metre 4 39
1786 1 mm thick 25 mm wide
1787 75x45x3.2 mm
1788 639 Bright finished or black enamelled mild steel 100 Nos 1.2 36
1789 597 screws 25 mm
1790 Bright finished or black enamelled mild steel 10 Nos 0.2 49
1791 640 butt hinges50x37x1.50 mm 30
1792 Bright finished or black enamelled mild steel 100 Nos 0.08 30
1793 2204 screws 20 mm
1794 Carriage of Timber cum 0.043 121.29
1795 LABOUR
1796 41 Carpenter (average) day 1.83 403.67
1797 21 Glazier day 0.23 403.67
1798 17 Beldar day 0.77 350.00
1799 9999 Sundries L.S. 40.43 2
1800 TOTAL
1801 Add 1 % Water charges on "W"
1802 TOTAL
1803 Add GST (multiplying factor 0.1405) on "X"
1804 TOTAL
1805 Add 15 % Contractor's profit and overheads on "Y"
1806 Total
1807 Add Cess @ 1% on "Z"
1808 Cost of 2.16 sqm.
1809 Cost of 1 sqm.
1810 Say
1811
1812
1813 14.27 Providing and fixing plain jaffri door and
1814 14.27.1 window shutters
Second class teakincluding
wood bright or/and
1815 Details of cost of a jaffri shutter 176x86 cm
1816 = 1.51 sqm
1817 MATERIAL
1818 Teak wood 2nd class
1819 Styles 2x176x7.5x3.5 cm = 0.0092 cum
1833 Rails 3x86x7.5x3.5 = 0.0068 cum
1834 Total 0.0160 cum
1835 Add wastage @ 10 % =0.0016 cum Total =
1836 1190 0.0176 cum Say 18 cudm
1837 Second class teak wood in planks 10 cudm 1.8 791
1838 2204 Carriage of Timber Palain Jaffri work cum 0.018 121.29
1839 9.41.1 Rate as per Item Number 9.41.1 of SH:Wood sqm 1.51 2154.2
1840 595 and PVC work
1841 Bright finished or black enamelled mild steel 10 Nos 0.6 80
1842 597 butt hinges 100x58x1.90 mm 49
1843 Bright finished or black enamelled mild steel 10 Nos 0.2 49
1844 637 butt hinges50x37x1.50 mm 60
1845 Bright finished or black enamelled mild steel 100 Nos 0.48 60
1846 640 screws 40 mm
1847 Bright finished or black enamelled mild 100 Nos 0.08 30
1848 steel screws 20 mm
1849 LABOUR
1850 For making frame and fixing fitting
1851 15 Carpenter 2nd class day 0.3 403.67
1852 TOTAL
1853 Add 1 % Water charges on "W-A" 1627.33
1854 TOTAL
1855 Add GST (multiplying factor 0.1405) on "X-A" 1643.61
1856 TOTAL
1857 Add 15 % Contractor's profit and overheads 1874.53
1858 on "Y-A"
1859 Total
1860 Add Cess @ 1% on "Z-A" 2155.71
1861 Cost of 1.51 sqm.
1862 Cost of 1 sqm.
1863 Say
1864
1865
1866 14.28 Providing and fixing brass curtain rods of
1867 wall thickness
necessary 1.25 mm with two brass
complete.
1868 14.28.1 20 mm diameter.
1869 Detail of cost for 2 metre long
1870 MATERIAL
1871 444 Brass curtain rod 20 mm dia 1.25 mm thick metre 2 140
1872 446 Brass brackets (curtain rods) 20 mm each 2 45
1873 9999 Screws L.S. 2.73 2
1874 9977 Carriage L.S. 1.56 2
1875 Wooden plugs including cutting brick work
1876 and fixing in cement mortar
1886 8.23 Rate as per item no 8.23 of SH : Cladding each 2 25.4
1887 work
1888 9999 LABOUR L.S. 2.73 2
1889 9999 Sundries L.S. 1.56 2
1890 TOTAL
1891 Add 1 % Water charges on "W-A" 387.16
1892 TOTAL
1893 Add GST (multiplying factor 0.1405) on "X-A" 391.03
1894 TOTAL
1895 Add 15 % Contractor's profit and overheads 445.97
1896 on "Y-A"
1897 Total
1898 Add Cess @ 1% on "Z-A" 512.87
1899 Cost of 2 metres
1900 Cost of 1 metre
1901 Say

1902 14.28.2 25 mm diameter.


1903 Detail of cost for 2 metre long
1904 MATERIAL
1905 445 Brass curtain rod 25 mm dia 1.25 mm thick metre 2 190
1906 446 Brass brackets (curtain rods) 20 mm each 2 45
1907 9999 Screws L.S. 2.73 2
1908 9977 Carriage L.S. 1.56 2
1909 Wooden plugs including cutting brick work
1910 8.23 and fixing in cement mortar
1911 Rate as per item no 8.23 of SH : Cladding each 2 25.4
1912 work
1913 9999 LABOUR L.S. 2.73 2
1914 9999 Sundries L.S. 1.56 2
1915 TOTAL
1916 Add 1 % Water charges on "W-A" 487.16
1917 TOTAL
1918 Add GST (multiplying factor 0.1405) on "X-A" 492.03
1919 TOTAL
1920 Add 15 % Contractor's profit and overheads 561.16
1921 on "Y-A"
1922 Total
1923 Add Cess @ 1% on "Z-A" 645.34
1924 Cost of 2 metres
1925 Cost of 1 metre
1926 Say
1927
1928
1938
1939
1940 14.29 Providing and fixing M.S. round or square
1941 bars
Detailswith M.S.
of cost for flats
33.67 at
kg.required spacing in
1942 Details of cost for window -140x110cm
1943 MATERIAL
1944 M.S. bar 16 mm dia 13x136 cm
1945 = 17.68 m @ 1.58 kg/m = 27.93 kg
1946 Add for wastage @ 10% =2.79 kg
1947 Total = 30.72 kg or 0.307 q
1948 1003 Mild steel round bar above 12 mm dia quintal 0.307 5500
1949 M.S. flat 40x6mm 2x96cm = 192cm+
1950 1x110cm = 110cm
1951 = 302cm+
1952 Add wastage @ 10% = 30cm
1953 Total = 332cm.@ 1.90 kg/m = 6.31 kg Say
1954 1008 0.063 q
1955 Flats upto 10 mm in thickness quintal 0.063 4500
1956 2205 Carriage of Steel tonne 0.037 94.34
1957 (0.307+0.063 = 0.37 q = 0.037 t)
1958 9999 Sundries L.S. 26.91 2
1959 LABOUR
1960 13 Blacksmith 2nd class day 0.35 403.67
1961 15 Carpenter 2nd class day 0.2 403.67
1962 17 Beldar day 0.45 350.00
1963 TOTAL
1964 Add 1 % Water charges on "W"
1965 TOTAL
1966 Add GST (multiplying factor 0.1405) on "X"
1967 TOTAL
1968 Add 15 % Contractor's profit and overheads on "Y"
1969 Total
1970 Add Cess @ 1% on "Z"
1971 Cost of 33.67 kg.(5.74+27.93=33.67kg)
1972 Cost of 1 kg.
1973 Say
1974
1975
1976
1977
1978
1979 14.30 Providing joists (karries) including
1980 14.30.1 hoisting,
Sal wood fixing in position and applying
1981 Details of cost for 300cudm.
1982 MATERIAL
1983 Sal wood
1984 10x0.1mx0.1mx3.0m = 0.30 cum. or = 300 cudm
1994 Add wastage @ 2% = 6.00 cudm.
1995 Total = 306 cudm.
1996 1199 Sal wood in scantling 10 cudm 30.6 600
1997 2204 Carriage of Timber cum 0.306 121.29
1998 LABOUR
1999 15 Carpenter 2nd class day 0.7 403.67
2000 17 Beldar day 1.45 350.00
2001 10 Bandhani day 0.7 350.00
2002 Priming coat (Wood preservative)
2003 13.57.1 Rate as per item no 13.57.1 SH : Finishing sqm 0.8 33.65
2004 9999 Sundries L.S. 26.91 2
2005 TOTAL
2006 Add 1 % Water charges on "W-A" 19402.87
2007 TOTAL
2008 Add GST (multiplying factor 0.1405) on "X-A" 19596.9
2009 TOTAL
2010 Add 15 % Contractor's profit and overheads 22350.26
2011 on "Y-A"
2012 Total
2013 Add Cess @ 1% on "Z-A" 25702.8
2014 Cost of 300 cudm.
2015 Cost of 1 cum.
2016 Say

2017 14.30.2 Hollock wood


2018 Details of cost for 300cudm.
2019 MATERIAL
2020 Hollock wood in scantling
2021 10x0.1mx0.1mx3.0m = 0.30 cum. or
2022 = 300 cudm
2023 Add wastage @ 2% = 6.00 cudm.
2024 Total = 306 cudm.
2025 2466 Hollock wood in scantling 10 cudm 30.6 350
2026 2204 Carriage of Timber cum 0.306 121.29
2027 LABOUR
2028 15 Carpenter 2nd class day 0.7 403.67
2029 17 Beldar day 1.45 350.00
2030 10 Bandhani day 0.7 350.00
2031 Priming coat (Wood preservative)
2032 13.57.1 Rate as per item no 13.57.1 SH : Finishing sqm 0.8 33.65
2033 9999 Sundries L.S. 26.91 2
2044 TOTAL
2045 Add 1 % Water charges on "W-A" 11752.87
2046 TOTAL
2047 Add GST (multiplying factor 0.1405) on "X-A" 1667.79
2048 11870.40
TOTAL
2049 Add 15 % Contractor's profit and overheads 13538.19
2050 on "Y-A"
2051 Total
2052 Add Cess @ 1% on "Z-A" 15568.92
2053 Cost of 300 cudm. 15751.53
2054 Cost of 1 cum. 52505.1
2055 Say
2056
2057
2058 14.31 Providing and fixing bright finished brass
2059 14.31.1 single
150 mm acting spring hinges with necessary
2060
2061 Details of cost for 10 nos.
2062 MATERIAL
2063 389 Brass single acting spring hinges 150 mm each 10 425
2064 449 Brass screws 50 mm 100 Nos 0.8 220
2065 9977 Carriage of materials L.S. 3.64 2
2066 LABOUR
2067 14 Carpenter 1st class day 0.4 505.17
2068 17 Beldar day 0.2 350.00
2069 TOTAL
2070 Add 1 % Water charges on "W"
2071 TOTAL
2072 Add GST (multiplying factor 0.1405) on "X"
2073 TOTAL
2074 Add 15 % Contractor's profit and overheads on "Y"
2075 Total
2076 Add Cess @ 1% on "Z"
2077 Cost of 10 hinges
2078 Cost of each
2079 Say
2080
2081
2082 14.31.2 125 mm
2083 Details of cost for 10 nos.
2084 MATERIAL
2085 390 Brass single acting spring hinges 125 mm each 10 285
2086 449 Brass screws 50 mm 100 Nos 0.8 220
2094 9977 Carriage of materials L.S. 3.64 2
2095 LABOUR
2096 14 Carpenter 1st class day 0.4 505.17
2097 17 Beldar day 0.2 350.00
2098 TOTAL
2099 Add 1 % Water charges on "W"
2100 TOTAL
2101 Add GST (multiplying factor 0.1405) on "X"
2102 TOTAL
2103 Add 15 % Contractor's profit and overheads on "Y"
2104 Total
2105 Add Cess @ 1% on "Z"
2106 Cost of 10 hinges
2107 Cost of each
2108 Say

2109 14.31.3 100 mm


2110 Details of cost for 10 nos.
2111 MATERIAL
2112 391 Brass single acting spring hinges 100 mm each 10 250
2113 450 Brass screws 40 mm 100 Nos 0.8 170
2114 9977 Carriage of materials L.S. 3.64 2
2115 LABOUR
2116 14 Carpenter 1st class day 0.4 505.17
2117 17 Beldar day 0.2 350.00
2118 TOTAL
2119 Add 1 % Water charges on "W"
2120 TOTAL
2121 Add GST (multiplying factor 0.1405) on "X"
2122 TOTAL
2123 Add 15 % Contractor's profit and overheads on "Y"
2124 Total
2125 Add Cess @ 1% on "Z"
2126 Cost of 10 hinges
2127 Cost of each
2128 Say
2129
2130 14.32 Providing and fixing bright finished
2131 brass double acting spring hinges with
2132 14.32.1 150 mm
2143 Details of cost for 10 nos.
2144 MATERIAL
2145 392 Brass double acting spring hinges 150 mm each 10 480
2146 449 Brass screws 50 mm 100 Nos 0.8 220
2147 9977 Carriage of materials L.S. 3.64 2
2148 LABOUR
2149 14 Carpenter 1st class day 0.4 505.17
2150 17 Beldar day 0.2 350.00
2151 TOTAL
2152 Add 1 % Water charges on "W"
2153 TOTAL
2154 Add GST (multiplying factor 0.1405) on "X"
2155 TOTAL
2156 Add 15 % Contractor's profit and overheads on "Y"
2157 Total
2158 Add Cess @ 1% on "Z"
2159 Cost of 10 hinges
2160 Cost of each
2161 Say

2162 14.32.2 125 mm


2163 Details of cost for 10 nos.
2164 MATERIAL
2165 393 Brass double acting spring hinges 125 mm each 10 400
2166 449 Brass screws 50 mm 100 Nos 0.8 220
2167 9977 Carriage of materials L.S. 3.64 2
2168 LABOUR
2169 14 Carpenter 1st class day 0.4 505.17
2170 17 Beldar day 0.2 350.00
2171 TOTAL
2172 Add 1 % Water charges on "W"
2173 TOTAL
2174 Add GST (multiplying factor 0.1405) on "X"
2175 TOTAL
2176 Add 15 % Contractor's profit and overheads on "Y"
2177 Total
2178 Add Cess @ 1% on "Z"
2179 Cost of 10 hinges
2180 Cost of each
2181 Say
2182
2191
2192 14.32.3 100 mm
2193 Details of cost for 10 nos.
2194 MATERIAL
2195 394 Brass double acting spring hinges 100 mm each 10 390
2196 450 Brass screws 40 mm 100 Nos 0.8 170
2197 9977 Carriage of materials L.S. 3.64 2
2198 LABOUR
2199 14 Carpenter 1st class day 0.4 505.17
2200 17 Beldar day 0.2 350.00
2201 TOTAL
2202 Add 1 % Water charges on "W"
2203 TOTAL
2204 Add GST (multiplying factor 0.1405) on "X"
2205 TOTAL
2206 Add 15 % Contractor's profit and overheads on "Y"
2207 Total
2208 Add Cess @ 1% on "Z"
2209 Cost of 10 hinges
2210 Cost of each
2211 Say
2212
2213
2214
2215
2216 14.33 Providing and fixing bright finished brass
2217 flush
screwsbolts
etc.with necessary
complete : brass
2218 14.33.1 250 mm
2219 Details of cost for 10 nos.
2220 MATERIAL
2221 404 Brass flush bolt 250 mm each 10 150
2222 452 Brass screws 25 mm 100 Nos 0.6 100
2223 9977 Carriage of materials L.S. 3.64 2
2224 LABOUR
2225 14 Carpenter 1st class Day 0.2 505.17
2235 TOTAL
2236 Add 1 % Water charges on "W"
2237 TOTAL
2238 Add GST (multiplying factor 0.1405) on "X"
2239 TOTAL
2240 Add 15 % Contractor's profit and overheads on "Y"
2241 Total
2242 Add Cess @ 1% on "Z"
2243 Cost of 10 hinges
2244 Cost of each
2245 Say

2246 14.33.2 150 mm


2247 Details of cost for 10 nos.
2248 MATERIAL
2249 405 Brass flush bolt 150 mm each 10 130
2250 452 Brass screws 25 mm 100 Nos 0.6 100
2251 9977 Carriage of materials L.S. 2.73 2
2252 LABOUR
2253 14 Carpenter 1st class day 0.17 505.17
2254 TOTAL
2255 Add 1 % Water charges on "W"
2256 TOTAL
2257 Add GST (multiplying factor 0.1405) on "X"
2258 TOTAL
2259 Add 15 % Contractor's profit and overheads on "Y"
2260 Total
2261 Add Cess @ 1% on "Z"
2262 Cost of 10 hinges
2263 Cost of each
2264 Say
2265

2274 14.33.3 100 mm


2276 Details of cost for 10 nos.
2277 MATERIAL
2278 406 Brass flush bolt 100 mm each 10 90
2279 452 Brass screws 25 mm 100 Nos 0.6 100
2280 9977 Carriage of materials L.S. 2.73 2
2281 LABOUR
2282 14 Carpenter 1st class day 0.17 505.17
2283 TOTAL
2284 Add 1 % Water charges on "W"
2285 TOTAL
2286 Add GST (multiplying factor 0.1405) on "X"
2287 TOTAL
2288 Add 15 % Contractor's profit and overheads on "Y"
2289 Total
2290 Add Cess @ 1% on "Z"
2291 Cost of 10 hinges
2292 Cost of each
2293 Say

2294
2295
2296 14.34 Providing and fixing 150 mm bright
2297 finished floor
Details of cost forbrass
10 nos.door stopper with
2298 MATERIAL
2299 417 Brass 150 mm floor door stopper (0.357kg) each 10 160
2300 450 Brass screws 40 mm 100 Nos 0.4 170
2301 9977 Carriage of material L.S. 2.73 2
2302 LABOUR
2303 14 Carpenter 1st class day 0.07 505.17
2304 9999 Sundries (wooden plugs including fixing in L.S. 6.37 2
2305 the floor)
2306 TOTAL
2307 Add 1 % Water charges on "W"
2308 TOTAL
2309 Add GST (multiplying factor 0.1405) on "X"
2310 TOTAL
2311 Add 15 % Contractor's profit and overheads on "Y"
2312 Total
2313 Add Cess @ 1% on "Z"
2314 Cost of 10 Nos
2315 Cost of each
2316 Say
2317
2326
2327 14.35 Providing and fixing bright finished brass
2328 hard drawn hooks and eyes :
2329 14.35.1 300 mm
2330 Details of cost for 10 nos.
2331 MATERIAL
2332 418 Brass hard drawn hooks and eyes 300 mm 10 Nos 1 600
2333 9977 Carriage of material L.S. 0.91 2
2334 LABOUR
2335 14 Carpenter 1st class day 0.06 505.17
2336 TOTAL
2337 Add 1 % Water charges on "W"
2338 TOTAL
2339 Add GST (multiplying factor 0.1405) on "X"
2340 TOTAL
2341 Add 15 % Contractor's profit and overheads on "Y"
2342 Total
2343 Add Cess @ 1% on "Z"
2344 Cost of 10 Nos
2345 Cost of each
2346 Say

2347 14.35.2 250 mm


2348 Details of cost for 10 nos.
2349 MATERIAL
2350 419 Brass hard drawn hooks and eyes 250 mm 10 Nos 1 574
2351 9977 Carriage of material L.S. 0.91 2
2352 LABOUR
2353 14 Carpenter 1st class day 0.06 505.17
2354 TOTAL
2355 Add 1 % Water charges on "W"
2356 TOTAL
2357 Add GST (multiplying factor 0.1405) on "X"
2358 TOTAL
2359 Add 15 % Contractor's profit and overheads on "Y"
2360 Total
2361 Add Cess @ 1% on "Z"
2362 Cost of 10 hooks and eyes
2363 Cost of 1 hook and eye
2364 Say
2366
2374
2375 14.35.3 200 mm
2376 Details of cost for 10 nos.
2377 MATERIAL
2378 420 Brass hard drawn hooks and eyes 200 mm 10 Nos 510
2379 9977 Carriage of material L.S.
2380 LABOUR
2381 14 Carpenter 1st class day 505.17
2382 TOTAL
2383 Add 1 % Water charges on "W"
2384 TOTAL
2385 Add GST (multiplying factor 0.1405) on "X"
2386 TOTAL
2387 Add 15 % Contractor's profit and overheads on "Y"
2388 Total
2389 Add Cess @ 1% on "Z"
2390 Cost of 10 Nos
2391 Cost of each
2392 Say

2393 14.35.4 150 mm


2394 Details of cost for 10 nos.
2395 MATERIAL
2396 421 Brass hard drawn hooks and eyes 150 mm 10 Nos 400
2397 9977 Carriage of material L.S.
2398 LABOUR
2399 14 Carpenter 1st class day 505.17
2400 TOTAL
2402 Add 1 % Water charges on "W"
2404 TOTAL
2406 Add GST (multiplying factor 0.1405) on "X"
2408 TOTAL
2410 Add 15 % Contractor's profit and overheads on "Y"
2474 Total
2475 Add Cess @ 1% on "Z"
2476 Cost of 10 Nos
2477 Cost of each
2478 Say
2479 14.35.5 100 mm
2480 Details of cost for 10 nos.
2481 MATERIAL
2482 422 Brass hard drawn hooks and eyes 100 mm 10 Nos 1 345
2483 9977 Carriage of material L.S. 0.91 2
2484 LABOUR
2485 14 Carpenter 1st class day 0.06 505.17
2486 TOTAL
2487 Add 1 % Water charges on "W"
2488 TOTAL
2489 Add GST (multiplying factor 0.1405) on "X"
2490 TOTAL
2491 Add 15 % Contractor's profit and overheads on "Y"
2492 Total
2493 Add Cess @ 1% on "Z"
2494 Cost of 10 Nos
2495 Cost of each
2496 Say
2497
2498
2499
2500
2501 14.36 Providing and fixing bright finished brass
2502 fan light
brass pivot etc.
screws withcomplete.
necessary
2503 Details of cost for 10 nos.
2504 MATERIAL
2505 429 Brass fanlight pivot 10 Nos 1 168
2506 450 Brass screws 40 mm 100 Nos 0.4 170
2507 9977 Carriage of material L.S. 0.91 2
2508 LABOUR
2509 14 Carpenter 1st class day 0.08 505.17
2510 TOTAL
2511 Add 1 % Water charges on "W"
2512 TOTAL
2513 Add GST (multiplying factor 0.1405) on "X"
2514 TOTAL
2515 Add 15 % Contractor's profit and overheads on "Y"
2516 Total
2517 Add Cess @ 1% on "Z"
2518 Cost of 10 Nos
2519 Cost of each
2520 Say
2521
2530
2531
2532 14.37 Providing and fixing 300 mm long bright
2533 finished brass chain with hook for fan light
2534 Details of cost for 10 nos.
2535 MATERIAL
2536 430 Brass chain with hook for fan light catch each 10 36
2537 452 Brass screws 25 mm 100 Nos 0.4 100
2538 9977 Carriage of material L.S. 0.91 2
2539 LABOUR
2540 14 Carpenter 1st class day 0.1 505.17
2541 TOTAL
2542 Add 1 % Water charges on "W"
2543 TOTAL
2544 Add GST (multiplying factor 0.1405) on "X"
2545 TOTAL
2546 Add 15 % Contractor's profit and overheads on "Y"
2547 Total
2548 Add Cess @ 1% on "Z"
2549 Cost of 10 Nos
2550 Cost of each
2551 Say
2552

2553 14.38 Providing and fixing bright finished


2554 brass quadrant stay 300 mm long with
2555 Details of cost for 10 nos.
2556 MATERIAL
2557 427 Brass quadrant stays 300 mm each 10 110
2558 452 Brass screws 25 mm 100 Nos 0.4 100
2559 9977 Carriage of material L.S. 0.91 2
2560 LABOUR
2561 14 Carpenter 1st class day 0.1 505.17
2562 TOTAL
2563 Add 1 % Water charges on "W"
2564 TOTAL
2565 Add GST (multiplying factor 0.1405) on "X"
2566 TOTAL
2567 Add 15 % Contractor's profit and overheads on "Y"
2568 Total
2569 Add Cess @ 1% on "Z"
2571 Cost of 10 quadrant stayes
2572 Cost of each
2573 Say
2584
2585
2586
2587 14.39 Providing and fixing bright finished brass
2588 helical
quality).door spring (superior
2589 Details of cost for 10 nos.
2590 MATERIAL
2591 442 Brass helical spring 150 mm each 10 290
2592 449 Brass screws 50 mm 100 Nos 0.4 220
2593 452 Brass screws 25 mm 100 Nos 0.2 100
2594 9977 Carriage of material L.S. 3.84 2
2595 LABOUR
2596 14 Carpenter 1st class day 0.4 505.17
2597 17 Beldar day 0.2 350.00
2598 TOTAL
2599 Add 1 % Water charges on "W"
2600 TOTAL
2601 Add GST (multiplying factor 0.1405) on "X"
2602 TOTAL
2603 Add 15 % Contractor's profit and overheads on "Y"
2604 Total
2605 Add Cess @ 1% on "Z"
2606 Cost of 10 Nos
2607 Cost of each
2608 Say
2609
2610
2611 14.40 Providing and fixing chromium plated
2612 14.40.1 brass butt hinges
125x70x4 with necessary
mm (ordinary type)
2613
2614 Details of cost for 10 nos.
2615 MATERIAL
2616 525 Chromium plated Brass butt hinges 10 Nos 1 805
2617 (light/ordinary) type 125x70x4 mm
2626 585 Chromium plated Brass screws 50 mm 100 Nos 1 300
2627 9977 Carriage of material L.S. 3.64 2
2628 LABOUR
2629 14 Carpenter 1st class day 0.14 505.17
2630 17 Beldar day 0.1 350.00
2631 TOTAL
2632 Add 1 % Water charges on "W"
2633 TOTAL
2634 Add GST (multiplying factor 0.1405) on "X"
2635 TOTAL
2636 Add 15 % Contractor's profit and overheads on "Y"
2637 Total
2638 Add Cess @ 1% on "Z"
2639 Cost of 10 Nos
2640 Cost of each
2641 Say

2642 14.40.2 100x70x4 mm (ordinary type)


2643 Details of cost for 10 nos.
2644 MATERIAL
2645 526 Chromium plated Brass butt hinges 10 Nos 1 690
2646 586 (light/ordinary) type 100x70x4 mm
2647 Chromium plated Brass screws 40 mm 100 Nos 0.8 290
2648 9977 Carriage of material L.S. 3.64 2
2649 LABOUR
2650 14 Carpenter 1st class day 0.14 505.17
2651 17 Beldar day 0.1 350.00
2652 TOTAL
2653 Add 1 % Water charges on "W"
2654 TOTAL
2655 Add GST (multiplying factor 0.1405) on "X"
2656 TOTAL
2657 Add 15 % Contractor's profit and overheads on "Y"
2658 Total
2659 Add Cess @ 1% on "Z"
2660 Cost of 10 Nos
2661 Cost of each
2662 Say
2663
2664
2665
2666
2667
2668
2669
2670
2671
2672 14.40.3 75x65x4 mm (heavy type)
2675 Details of cost for 10 nos.
2677 MATERIAL
2678 524 Chromium plated Brass butt hinges (heavy) 10 Nos 1 905
2679 587 type 75x65x4 .0 mm (200gms)
2680 Chromium plated Brass screws 30 mm 100 Nos 0.6 240
2681 9977 Carriage of material L.S. 1.82 2
2682 LABOUR
2683 14 Carpenter 1st class day 0.14 505.17
2684 17 Beldar day 0.1 350.00
2685 TOTAL
2686 Add 1 % Water charges on "W"
2687 TOTAL
2688 Add GST (multiplying factor 0.1405) on "X"
2689 TOTAL
2690 Add 15 % Contractor's profit and overheads on "Y"
2691 Total
2692 Add Cess @ 1% on "Z"
2693 Cost of 10 Nos
2694 Cost of each
2695 Say

2696 14.40.4 75x40x2.5 mm (ordinary type)


2697 Detail of cost for 10 Nos.
2698 MATERIAL
2699 527 Chromium plated Brass butt hinges 10 Nos 1 421
2700 587 (light/ordinary) type 75x40x2.5 mm
2701 Chromium plated Brass screws 30 mm 100 Nos 0.6 240
2702 9977 Carriage of material L.S. 1.82 2
2703 LABOUR
2704 14 Carpenter 1st class day 0.14 505.17
2705 17 Beldar day 0.1 350.00
2706 TOTAL
2707 Add 1 % Water charges on "W"
2708 TOTAL
2709 Add GST (multiplying factor 0.1405) on "X"
2710 TOTAL
2711 Add 15 % Contractor's profit and overheads on "Y"
2712 Total
2713 Add Cess @ 1% on "Z"
2714 Cost of 10 Nos
2715 Cost of each
2716 Say
2717
2718
2727 14.40.5 50x40x2.5 mm (ordinary type)
2728 Details of cost for 10 nos.
2729 MATERIAL
2730 528 Chromium plated Brass butt hinges 10 Nos 1 180
2731 589 (light/ordinary) type 50x40x2.5 mm
2732 Chromium plated Brass screws 20 mm 100 Nos 0.4 160
2733 9977 Carriage of material L.S. 0.91 2
2734 LABOUR
2735 14 Carpenter 1st class day 0.08 505.17
2736 TOTAL
2737 Add 1 % Water charges on "W"
2738 TOTAL
2739 Add GST (multiplying factor 0.1405) on "X"
2740 TOTAL
2741 Add 15 % Contractor's profit and overheads on "Y"
2742 Total
2743 Add Cess @ 1% on "Z"
2744 Cost of 10 Nos
2745 Cost of each
2746 Say
2747

2748
2749 14.41 Providing and fixing 85x42 mm chromium
2750 plated brass
Details of pull
cost for 10 bolt
Nos lock with necessary
2751 MATERIAL
2752 2467 Chromium plated Brass pull bolt lock each 10 165
2753 (locking bolt) of size 85 mmx42 mm with
2754 9988 screws,bolts,nuts and washers complete
2755 Carriage of materials & sundries L.S. 6.37 2
2756 LABOUR
2757 15 Carpenter 2nd class day 0.25 403.67
2758 TOTAL
2759 Add 1 % Water charges on "W"
2760 TOTAL
2761 Add GST (multiplying factor 0.1405) on "X"
2762 TOTAL
2763 Add 15 % Contractor's profit and overheads on "Y"
2764 Total
2765 Add Cess @ 1% on "Z"
2766 Cost of 10 Nos
2767 Cost of each
2768 Say
2769
2779
2780 14.42 Providing and fixing double
2781 scaffolding system (cup lock type) on the
2782 .The payment will be made once
2783 irrespective
deduction forofscaffolding
duration ofin
scaffolding.
the existing
2784 item to be done.
2785 Details of cost for area 22.5m x 9.0m = 202.5 sqm
2786
2787 14.42X Rate as per Item No.14.72X of SH:Repairs to each 1 7676.5
2788 2205 Buildings 94.34
2789 Carriage of Steel tonne 6.054 94.34
2790 40mm dia MS pipe = 3765.42 kg
2791 25mm spigot = 123.98 kg
2792 Nuts & bolts = 37.80 kg
2793 Clamp = 120 nos @ 1.00kg each = 120.00 kg
2794 Challies = 90 nos @ 15.00kg each
2795 = 1350.00 kg
2796 Cup locks = 1314 nos @ 0.50kg each
2797 = 657.00 kg
2798 Total = 6054.20 kg = 6.054 tonne
2799 LABOUR
2800 19 Fitter (grade 1) day 15.5 505.17
2801 17 Beldar day 31 350.00
2802 9999 Sundries L.S. 1035 2
2803 TOTAL
2804 Add 1 % Water charges on "W"
2805 TOTAL
2806 Add GST (multiplying factor 0.1405) on "X"
2807 TOTAL
2808 Add 15 % Contractor's profit and overheads on "Y"
2809
2810 Add Cess @ 1% on "Z"
2811 Detail of cost for 202.50 sqm
2812 Cost of per Sqm
2813 Say
2814
2823
2824
2825 14.42X Scaffolding
2826 Details of cost for area 22.5 x 9.0
2827 = 202.50 sqm
2828 MATERIAL
2829 Assuming shuttering material will become
2830 7397 unserviceable after use of 40 times
2831 Base jack each 14 145
2832 7x2=14 nos
2833 4009 Mild steel tubes hot finished welded type kilogram 3765.42 57
2834 40mm dia M.S. Tube
2835 Vertical standard 2.5m length
2836 = 7x2x9x2.5 = 315.00 m
2837 Bracing ledder 1.5m length = 7x2x9x4.0873
2838 = 513.00 m
2839 Side support 6.00m length = 3x2x6.00
2840 = 36.00 m
2841 Horizontal support 3.00m length
2842 = 18x3x3.00 = 162.00 m
2843 Total = 1026.00m @ 3.67 kg/m = 3765.42 kg
2844 7387 Spigot for standard jointing kg 123.98 43
2845 7x2x9 = 126 nos x 0.40m length = 50.40m
2846 50.40m @ 2.46kg/m = 123.98kg
2847 1034 Bolts and nuts upto 300 mm in length quintal 0.378 4800
2848 2x7x2x9 = 252 nos @ 0.15 kg each
2849 = 37.80 kg = 0.378 q
2850 7346 Double coupler each 120 46
2851 2x3x2 + 2x18x3 = 120 nos
2852 7398 Challies each 90 765
2853 3 nos x 18 lines = 54 nos
2854 Two level plate challies = 2x 18 lines
2855 = 36 nos, Total = 90 nos
2856 7399 Cup lock each 1314 48
2857 Vertical standards 5x7x2x9 = 630.00 Nos.
2858 2x18x19 = 684 Nos.
2859 Total =1314 Nos.
2860 TOTAL
2861 Add 10% for maintenance on P
2862 Less 25% salvage value on P
2863 TOTAL (P+Q+R)
2864 Considering that scaffolding shall be
2865 unserviceable after using 40 times, cost of
2866 using once
2867 Say
2868
2869
2884
2885 14.43 Providing and fixing bright finished brass
2886 casement window fasteners or peg stays
2887 Details of cost for 10 nos (10 x 0.20 = 2.00
2888 kg)
2889 MATERIAL
2890
2891 423 Brass casement window fastener each 10 45
2892 9999 Fixing charges including welding and L.S. 125.58 2
2893 9977 materials etc.
2894 Carriage of materials L.S. 3.64 2
2895 TOTAL
2896 Add 1 % Water charges on "W"
2897 TOTAL
2898 Add GST (multiplying factor 0.1405) on "X"
2899 TOTAL
2900 Add 15 % Contractor's profit and overheads on "Y"
2901 Total
2902 Add Cess @ 1% on "Z"
2903 Cost of 2.00kg window fasteners
2904 Cost of 1 kg window fastener
2905 Say
2906
2907
2908 14.44 Providing and fixing 14 mm bright
2909 finished brass
Details of cost for spring
10 nos catch to steel centre
2910 MATERIAL
2911 428 Brass fanlight catch 10 Nos 1 170
2912 9999 Fixing charges including welding and L.S. 125.58 2
2913 9977 materials etc.
2914 Carriage of materials L.S. 3.64 2
2915 TOTAL
2916 Add 1 % Water charges on "W"
2917 TOTAL
2918 Add GST (multiplying factor 0.1405) on "X"
2919 TOTAL
2920 Add 15 % Contractor's profit and overheads on "Y"
2921 Total
2922 Add Cess @ 1% on "Z"
2923 Cost of 10 window fasteners
2924 Cost of each
2925 Say
2926
2939
2940
2941 14.45 Repair to plaster of thickness 12mm to 20
2942 mm inofpatches
Details of sqm
cost for 10 area 2.5 sqm and under,
2943 MATERIAL
2944 772 White cement based polymer modified self kg 125 15
2945 curing compound in powder form i/c 2%
2946 9977 wastage
2947 Carriage of white cement based polymer L.S. 21.1 2
2948 modified self curing compound in powder
2949 form
2950 LABOUR
2951 40 Mason (average) day 1.21 403.67
2952 17 Beldar day 0.54 350.00
2953 18 Coolie day 1.29 350.00
2954 9999 Scaffolding and sunderies L.S. 15.21 2
2955 TOTAL
2956 Add 1 % Water charges on "W"
2957 TOTAL
2958 Add GST (multiplying factor 0.1405) on "X"
2959 TOTAL
2960 Add 15 % Contractor's profit and overheads on "Y"
2961 Total
2962 Add Cess @ 1% on "Z"
2963 Cost of 10 sqm
2964 Cost of 1 sqm
2965 Say
2966
2990
2991
2992
2993 14.46 Cleaning of terrace/loft water storage
2997 tank
Details(inside surface
of cost for area) upto 2000 litre
10 tanks
2998 1 tank is of 500 litres capacity i.e. 5000 litres
2999 MATERIAL
3000 1301 Bleaching powder quintal 0.025 1800
3001 2264 Carriage of Rubbish cum 0.25 94.34
3002 (asuming 0.040m depth of silt)
3003 9999 Marking with paint i/c removal of existing L.S. 30 2
3004 markings
3005 LABOUR
3006 20 Assistant Fitter or 2nd class Fitter for opening day 1 403.67
3007 ball cock wheel valve and other fittings
3008 17 Beldar day 1 350.00
3009 for cleaning disinfecting etc
3010 TOTAL
3011 Add 1 % Water charges on "W"
3012 TOTAL
3013 Add GST (multiplying factor 0.1405) on "X"
3014 TOTAL
3015 Add 15 % Contractor's profit and overheads on "Y"
3016 Total
3017 Add Cess @ 1% on "Z"
3018 Cost of 5000 litres
3019 Cost of 1 litre
3020 Say
3021
3022
3023
3024
3025 14.47 Cleaning and desilting of gully trap
3026 chamber, including
Details of cost removal of rubbish
for 10 Nos.
3027 LABOUR
3028 29 Sewerman day 1 350.00
3029 9999 T & P Bamboo, bucket, whell barrow etc. L.S. 11.2 2
3039 TOTAL
3040 Add 1 % Water charges on "W"
3041 TOTAL
3042 Add GST (multiplying factor 0.1405) on "X"
3043 TOTAL
3044 Add 15 % Contractor's profit and overheads on "Y"
3045 Total
3046 Add Cess @ 1% on "Z"
3047 Cost of 10 nos
3048 Cost of each
3049 Say
3050
3051
3052 14.48 Cleaning of chocked sewer line by diesel
3053 running vehicle
Details of Cost mounting
for 208 metres hydraulic
3054 MATERIAL
3055 9999 Soap, brush, cloths & sundries L.S. 345 2
3056 8500 Water for jetting / blowback Machineries 1000 litre 0.002 1500
3057 83 Hire Charges of Suction Jeting machine day 1 36000
3058 2200 PSI machine i/c POL and operator
3059 LABOUR
3060 37 Skilled Beldar (for floor rubbing etc.) day 4 350.00
3061 44 Technician day 1 403.67
3062 TOTAL
3063 Add 1 % Water charges on "W"
3064 TOTAL
3065 Add GST (multiplying factor 0.1405) on "X"
3066 TOTAL
3067 Add 15 % Contractor's profit and overheads on "Y"
3068 Total
3069 Add Cess @ 1% on "Z"
3070 Cost of 208 metres
3071 Cost of 1.00 metre
3072 Say
3073
3083
3084
3085
3086 14.49 Cleaning of under ground sump, Over
3087 Head R.C.C.
slit and otherTank ( independent staging)
deposits.
3088 (ii) Entire surface area of the sump shall
3089 then scrubbed thoroughly with wire brush
3090 (iii) Chlorination of RCC internal surface by
3091 liquid chlorine.
3092 (iv) The treated surface shall be dried using
3093 air jetting and all loose particles shall be
3094 (v) Finally the surface shall be treated with
3095 ultraviolet radiation etc. as per direction of
3096 Let a underground tank of capacity 272000
3097 litre or 272 KL and area of tank is 570sqm
3098 (a) Dewater and slit cleaning
3099 Considering through pumping 20% of water
3100 to be lifted, water discharge =(272 x 20/
3101 100=54.40KL)
3102 Cost of pumping water with pump of capacity
3103 4000 litres per hours , = (54.4/4 = 13.6 hours
3104 11 = @ 8 hours/ day = 1.7 day)
3105 Hire charges of Pump set of capacity 4000 day 1.7 700
3106 17 litres/hour
3107 Beldar day 10.88 350.00
3108 (b) Scrabing the internal surface of tank
3109 17 Beldar day 5.13 350.00
3110 18 Coolie day 2.28 350.00
3111 11 Bhisti day 2.28 350.00
3112 9999 Sundries L.S. 142.5 2
3113 (c) Bleaching
3114 1301 Bleaching powder quintal 0.57 1800
3115 6 Hire charges of Spraying machine including day 14.25 250
3116 36 electric charges
3117 Sprayer (for bitumen, tar etc.) (d) Air jetting day 14.25 350.00
3118 58 Air compressor hour 2 200
3119 17 Beldar day 0.25 350.00
3120 (e) Ultra Violet Radiation
3121 81 Using cost of Ultra Violet Radiation tube hour 0.5 189
3122 17 Beldar day 0.0625 350.00
3123 TOTAL
3124 Add 1 % Water charges on "W"
3125 TOTAL
3126 Add GST (multiplying factor 0.1405) on "X"
3127 TOTAL
3134 Add 15 % Contractor's profit and overheads on "Y"
3135 Total
3136 Add Cess @ 1% on "Z"
3137 Cost of 570 sqm
3138 Cost of 1 sqm
3139 Say
3140
3141
3142
3143 14.5 Disconnecting damaged overhead/terrace
3144 PVC waterwater
size from storage tankline
supply of any
and removing
3145 from theatterrace
shifting ground including
level as per direction of
3146 Engineer-in-charge.
Details of cost for 1 No
3147 LABOUR
3148 For disconnecting & dismantling of existing
3149 20 W/s line of water storage tanks on terrace of
3150 20 Assistant Fitter or 2nd class Fitter day 0.1 403.67
3151 17 Beldar day 0.1 350.00
3152 For Bringing the tank at Ground Level
3153 17 Beldar day 0.2 350.00
3154 9999 Sundries L.S. 1.1 2
3155 TOTAL
3156 Add 1 % Water charges on "W"
3157 TOTAL
3158 Add GST (multiplying factor 0.1405) on "X"
3159 TOTAL
3160 Add 15 % Contractor's profit and overheads on "Y"
3161 Total
3162 Add Cess @ 1% on "Z"
3163 Cost for each
3164 Say
3165

3174
3176 14.51 Providing & fixing White vitreous china
3177 water closet squatting pan (Indian type)
3178 14.51.1 Long pattern W.C Pan of size 580x440
3179 mm
Details of cost for 1 no.
3180 MATERIAL
3181 1953 Vitreous china Indian type W.C. pan size each 1 450
3182 580 mm
3183 1970 Vitreous china foot rests 250x125x25 mm pair 1 100
3184 1890 Centrifugally sand cast (spun) S&S "P" or "S" each 1 300
3185 trap
3186 9999 Cement sand & grit etc. L.S. 13.36 2
3187 9977 Carriage of materials Less for L.S. 13.52 2
3188 1880 Dismantled "P" or "S" trap scrap (app. Wt 2 kg -2 22
3189 kg.)
3190 LABOUR
3191 (a) For dismantling WC seat and P or S trap
3192 29 Sewerman day 0.05 350.00
3193 17 Beldar day 0.2 350.00
3194 (b) For Fixing WC seat and "P" or "S" trap
3195 26 Mason 1st class day 0.8 505.17
3196 17 Beldar day 0.8 350.00
3197 TOTAL
3198 Add 1 % Water charges on "W"
3199 TOTAL
3200 Add GST (multiplying factor 0.1405) on "X"
3201 TOTAL
3202 Add 15 % Contractor's profit and overheads on "Y"
3203 Total
3204 Add Cess @ 1% on "Z"
3205 Cost for each
3206 Say
3207
3208
3209 14.51.2 Orissa pattern W.C Pan of size 580x440
3210 mm
Details of cost for 1 no.
3211 MATERIAL
3212 1954 Vitreous china orrisa type W.C. pan size each 1 1200
3213 580 mm
3214 1890 Centrifugally sand cast (spun) S&S "P" or "S" each 1 300
3215 9999 trap
3216 Cement sand & grit etc. L.S. 13.36 2
3217 9977 Carriage of materials Less for L.S. 13.52 2
3218 1880 Dismantled "P" or "S" trap scrap kg -2 22
3228 (app. Wt 2 kg.)
3229 LABOUR
3230 (a) For dismantling WC seat and P or S trap
3231 29 Sewerman day 0.05 350.00
3232 17 Beldar day 0.125 350.00
3233 (b) For Fixing WC seat and "P" or "S" trap
3234 26 Mason 1st class day 0.8 505.17
3235 17 Beldar day 0.8 350.00
3236 TOTAL
3237 Add 1 % Water charges on "W"
3238 TOTAL
3239 Add GST (multiplying factor 0.1405) on "X"
3240 TOTAL
3241 Add 15 % Contractor's profit and overheads on "Y"
3242 Total
3243 Add Cess @ 1% on "Z"
3244 Cost for each
3245 Say
3246
3247
3248
3249
3250
3251
3252 14.52 Cutting holes of required size in brick
3253 masonry wall
Detail of Cost forfor fixing of exhaust fan
10 holes
3254 Size 0.30x0.30x0.23 m wall
3255 MATERIAL
3256 12 mm plaster 1:4 (1 Cement: 4 Coarse sand)
3257 Actual Area (10x4x0.3x0.23) = 0.296 + 0.24
3258 L.S. For corners/sides = 3.00 Sqm
3259 13.4.1 Rate as per Item No.13.4.1 of SH:FINISHING sqm 3 182.15
3260 7752 PVC slotted pipe 200 mm dia as per IS: metre 0.25 840
3261 9999 12818
3262 Sundries L.S. 8.06 2
3263 LABOUR
3264 Proportionate labour taken as actually
3265 23 required at site
3266 Mason (brick layer) 1st class (0.16/0.0306)= day 0.11 505.17
3267 24 0.11 Nos.
3268 Mason (brick layer) 2nd class day 0.11 403.67
3269 17 (0.16/0.030)x0.207 = 0.11 Nos.
3270 Beldar day 1.1 350.00
3271
3272 (1.25x0.207)/0.0306 =1.10 Nos.
3281 9999 Add L.S. For Delay L.S. 16.12 2
3282 TOTAL
3283 Add 1 % Water charges on "W-A" 704.83
3284 TOTAL
3285 Add GST (multiplying factor 0.1405) on "X-A" 711.88
3286 TOTAL
3287 Add 15 % Contractor's profit and overheads 811.89
3288 on "Y-A"
3289 Total
3290 Add Cess @ 1% on "Z-A" 933.68
3291 Cost of 10 nos
3292 Cost of each
3293 Say

3294
3295
3296 14.53 Dismantling W.C. Pan of all sizes including
3297 disposal of dismantled
Details of cost for 1 no. materials i/c malba
3298 LABOUR
3299 17 Beldar day 0.125 350.00
3300 9999 Sundries L.S. 1 2
3301 TOTAL
3302 Add 1 % Water charges on "W"
3303 TOTAL
3304 Add GST(multiplying factor 0.1405) on "X"
3305 TOTAL
3306 Add 15 % Contractor's profit and overheads on "Y"
3307 Total
3308 Add Cess @ 1% on "Z"
3309 Cost of each
3310 Say
3311
3312
3313
3314 14.54 Hacking of CC flooring including
3315 cleaning for for
Details of cost surface
10 Sqmetc. complete as per
3316 LABOUR
3317 17 Beldar day 0.03 350.00
3318 9999 Sundries L.S. 1 2
3319 TOTAL
3320 Add 1 % Water charges on "W"
3321 TOTAL
3322 Add GST (multiplying factor 0.1405) on "X"
3323 TOTAL
3324 Add 15 % Contractor's profit and overheads on "Y"
3325 Total
3326 Add Cess @ 1% on "Z"
3328 Cost of 10 sqm
3329 Cost of 1 sqm
3330 Say
3331
3332
3340
3341 14.55 Dismantling 15 to 40 mm dia G.I. pipe
3343 including
(a) stacking
Internal ofExposed
Work- dismantled
on pipes
wall
3345 Details of cost for 10 metre
3346 LABOUR
3347 9999 Dismantling of G.I. Pipe and stacking etc. L.S. 10 2
3348 TOTAL
3349 Add 1 % Water charges on "W"
3350 TOTAL
3351 Add GST (multiplying factor 0.1405) on "X"
3352 TOTAL
3353 Add 15 % Contractor's profit and overheads on "Y"
3354 Total
3355 Add Cess @ 1% on "Z"
3356 Cost of 10 metres
3357 Cost of 1 metre
3358 Say

3359
3360 14.56 Taking out existing wooden door shutter,
3362 repair bycost
Details of cutting,
for onepainting etc.
shutter (2.2 and refixing
sqm)
3363 Normal exiting size of shutter
3364 1.00x2.02m =2.02sqm
3365 MATERIAL
3366 637 Bright finished or black enameled mild steel 100 Nos 0.24 60
3367 screws 40 mm
3368 Assuming old hinges fixed in Tee iron frames
3370 Half qty = 48/2=24 needs replacement
3372 LABOUR
3381 41 Carpenter (average) day 0.18 403.67
3382 17 Beldar day 0.18 350.00
3383 TOTAL
3384 Add 1 % Water charges on "W"
3385 TOTAL
3386 Add GST (multiplying factor 0.1405) on "X"
3387 TOTAL
3388 Add 15 % Contractor's profit and overheads on "Y"
3389 Total
3390 Add Cess @ 1% on "Z"
3391 Cost for 2.2 sqm or each shutter
3392 Cost for 2.02 sqm or each shutter
3393 Say
3394
3395 14.57 Providing and laying in situ seven course
3396 water proofing treatment with APP (Atactic
3397 Details of cost for 30 sqm
3398
3399 MATERIAL
3400 APP modified polymeric felt (two layers)
3401 1.5 mm thick = 2x30 = 60 sqm
3402 Add 10% wastage = 6 sqm Total = 66 sqm
3403 8200 A.P.P. modified polymeric felt (two layers) sqm 66 80
3404 1.5 mm thick
3405 316 Bitumen solution primer of approved quality litre 12 45
3406 0.4x30 = 12
3407 313 Blown type petroleum bitumen of penetration tonne 0.108 53000
3408 85/25 of approved quality
3409 3x36 =108 kg = 0.108 tonne
3410 2211 Carriage of Tar bitumen tonne 0.12 106.13
3411 9977 Carriage of polymeric felt L.S. 7.8 2
3421 370 Coal (steam) quintal 0.174 440
3422 2200 Carriage of steam coal tonne 0.0174 121.29
3423 9999 Preparing roof surface, cutting grooves L.S. 134.55 2
3424 and making good the same
3425 LABOUR
3426 31 Painter day 2.16 403.67
3427 17 Beldar day 3.24 350.00
3428 30 Mistry day 0.18 505.17
3429 9999 Sundries, brushes etc L.S. 6.76 2
3430 TOTAL
3431 Add 1 % Water charges on "W"
3432 TOTAL
3433 Add GST (multiplying factor 0.1405) on "X"
3434 TOTAL
3435 Add 15 % Contractor's profit and overheads on "Y"
3436 Total
3437 Add Cess @ 1% on "Z"
3438 Cost for 30 sqm
3439 Cost for 1 sqm
3440 Say
3441
3442 14.58 Providing and laying in situ five course
3443 water proofing treatment with APP (Atactic
3444 Details of cost for 30 sqm
3445 MATERIAL
3446 APP modified polymeric felt (two layers)
3447 2.0 mm thick = 30 sqm
3448 Add 10% wastage = 3 sqm
3449 Total = 33 sqm
3450 8201 A.P.P. modified polymeric felt (two layers) 2 sqm 33 100
3451 mm thick
3460 316 Bitumen solution primer of approved quality litre 12 45
3461 0.4x30 = 12
3462 313 Blown type petroleum bitumen of penetration tonne 0.072 53000
3463 85/25 of approved quality
3464 1.20x30x2 =72 kg = 0.072 tonne
3465 2211 Carriage of Tar bitumen tonne 0.084 106.13
3466 9977 Carriage of polymeric felt L.S. 7.8 2
3467 370 Coal (steam) quintal 0.174 440
3468 2200 Carriage of steam coal tonne 0.0174 121.29
3469 9999 Preparing roof surface, cutting grooves L.S. 134.55 2
3470 and making good the same
3471 LABOUR
3472 31 Painter day 1.58 403.67
3473 17 Beldar day 2.37 350.00
3474 30 Mistry day 0.13 505.17
3475 9999 Sundries, brushes etc L.S. 6.76 2
3476 TOTAL
3477 Add 1 % Water charges on "W"
3478 TOTAL
3479 Add GST (multiplying factor 0.1405) on "X"
3480 TOTAL
3481 Add 15 % Contractor's profit and overheads on "Y"
3482 Total
3483 Add Cess @ 1% on "Z"
3484 Cost for 30 sqm
3485 Cost for 1 sqm
3486 Say
3487
3488 14.59 Providing and laying in situ seven course
3489 water proofing treatment with APP (Atactic
3490 Details of cost for 30 sqm
3491
3492 MATERIAL
3493
3494 APP modified polymeric felt (two layers)
3495
3496 2.0 mm thick = 2x30 = 60 sqm Add 10% wastage = 6
sqm
3506 Total = 66 sqm
3507 8201 A.P.P. modified polymeric felt (two layers) 2 sqm 66 100
3508 316 mm thick
3509 Bitumen solution primer of approved quality litre 12 45
3510 0.4x30 = 12
3511 313 Blown type petroleum bitumen of penetration tonne 0.108 53000
3512 85/25 of approved quality 3course x 36 = 108
3513 2211 kg = 0.108 tonne
3514 Carriage of Tar bitumen tonne 0.12 106.13
3515 9977 Carriage of polymeric felt L.S. 7.8 2
3516 370 Coal (steam) quintal 0.174 440
3517 2200 Carriage of steam coal tonne 0.0174 121.29
3518 9999 Preparing roof surface, cutting grooves L.S. 134.55 2
3519 and making good the same
3520 LABOUR
3521 31 Painter day 2.16 403.67
3522 17 Beldar day 3.24 350.00
3523 30 Mistry day 0.18 505.17
3524 9999 Sundries, brushes etc L.S. 6.76 2
3525 TOTAL
3526 Add 1 % Water charges on "W"
3527 TOTAL
3528 Add GST (multiplying factor 0.1405) on "X"
3529 TOTAL
3530 Add 15 % Contractor's profit and overheads on "Y"
3531 Total
3532 Add Cess @ 1% on "Z"
3533 Cost for 30 sqm
3534 Cost for 1 sqm
3535 Say

3536
3537 14.60 Providing and fixing APP (Atactic
3549 14.60.1 Polypropylene Polymer)
2mm (for corrugated roofmodified
sheets)
3550 Detail of cost for 30 sqm
3551 MATERIAL
3552 A.P.P. modified 2 mm thick - 30 sqm
3553 Add 10% for wastage - 3 sqm
3554 Total = 33 sqm
3555 8203 A.P.P. modified 2 mm thick membrance sqm 33 126.67
3556 8206 reinforced with glass fibre matt
3557 Bitumen primer for bitumen membrance litre 12 80
3558 2211 Carriage of Tar bitumen tonne 0.012 106.13
3559 9977 Carriage of bitumen membrance L.S. 7.8 2
3560 1241 Commercial LPG in cylinder kg 7 82
3561 9999 Preparing roof surface, cutting grooves L.S. 49.53 2
3562 LABOUR
3563 43 Skilled torch operator for laying tack day 2.16 403.67
3564 30 Mistry day 0.18 505.17
3565 17 Beldar day 3.24 350.00
3566 9999 Sundries, brushes, bitumen torch etc L.S. 23.4 2
3567 TOTAL
3568 Add 1 % Water charges on "W"
3569 TOTAL
3570 Add GST (multiplying factor 0.1405) on "X"
3571 TOTAL
3572 Add 15 % Contractor's profit and overheads on "Y"
3573 Total
3574 Add Cess @ 1% on "Z"
3575 Cost for 30 sqm
3576 Cost for 1 sqm
3577 Say
3578
3579 14.61 Providing and laying APP (Atactic
3580 Polypropylene Polymer) modified
3592 14.61.1 3 mm thick
3593 Detail of cost for 30 sqm
3594 MATERIAL
3595 A.P.P. modified 2 mm thick - 30 sqm
3596 Add 10% for wastage - 3 sqm
3597 Total = 33 sqm
3598 8204 A.P.P. modified 3 mm thick membrance sqm 33 190
3599 8206 reinforced with glass fibre matt
3600 Bitumen primer for bitumen membrance litre 12 80
3601 2211 Carriage of Tar bitumen tonne 0.012 106.13
3602 9977 Carriage of bitumen membrance L.S. 7.8 2
3603 1241 Commercial LPG in cylinder kg 7 82
3604 9999 Preparing roof surface, cutting grooves L.S. 49.53 2
3605 LABOUR
3606 43 Skilled torch operator for laying tack day 2.16 403.67
3607 30 Mistry day 0.18 505.17
3608 17 Beldar day 3.24 350.00
3609 9999 Sundries, brushes, bitumen torch etc L.S. 23.4 2
3610 TOTAL
3611 Add 1 % Water charges on "W"
3612 TOTAL
3613 Add GST (multiplying factor 0.1405) on "X"
3614 TOTAL
3615 Add 15 % Contractor's profit and overheads on "Y"
3616 Total
3617 Add Cess @ 1% on "Z"
3618 Cost for 30 sqm
3619 Cost for 1 sqm
3620 Say
3650
3651
3652 14.62 Providing and laying APP (Atactic
3653 Polypropylene Polymer) modified
3654
3655
3656 14.62.1 3 mm thick
3657 Detail of cost for 30 sqm
3658 MATERIAL
3659 A.P.P. modified 2 mm thick - 30 sqm
3660 Add 10% for wastage - 3 sqm
3661 Total = 33 sqm
3662 8205 A.P.P. modified 3 mm thick membrance sqm 33 205
3663 8206 reinforced with polyster matt
3664 Bitumen primer for bitumen membrance litre 12 80
3665 2211 Carriage of Tar bitumen tonne 0.012 106.13
3666 9977 Carriage of bitumen membrance Fuel L.S. 7.8 2
3667 1241 Commercial LPG in cylinder kg 7 82
3668 9999 Preparing roof surface, cutting grooves L.S. 49.53 2
3669 LABOUR
3670 43 Skilled torch operator for laying tack day 2.16 403.67
3671 30 Mistry day 0.18 505.17
3672 17 Beldar day 3.24 350.00
3673 9999 Sundries, brushes, bitumen torch etc L.S. 23.4 2
3674 TOTAL
3675 Add 1 % Water charges on "W"
3676 TOTAL
3677 Add GST (multiplying factor 0.1405) on "X"
3678 TOTAL
3679 Add 15 % Contractor's profit and overheads on "Y"
3680 Total
3681 Add Cess @ 1% on "Z"
3682 Cost for 30 sqm
3683 Cost for 1 sqm
3684 Say
3685
3695
3696 14.63 Extra for covering top of membrane with
3698 Geotextile, 120 gsm non woven, 100%
recommendation.
3700 Detail of cost for 30 sqm
3702 MATERIAL
3703 Geotextile 120 gsm membrance - 30 sqm
3704 Add 5% for wastage - 1.50 sqm
3705 Total = 31.50 sqm
3706 8207 Geotextile 120 gsm membrance sqm 31.5 45
3707 9977 Carriage of Geotextile L.S. 7.8 2
3708 LABOUR
3709 43 Skilled torch operator for laying tack or fitter day 0.43 403.67
3710 30 2.16 / 5 = 0.43
3711 Mistry day 0.04 505.17
3712 0.18 / 5 = 0.04
3713 17 Beldar day 0.65 350.00
3714 3.24-5 / 0.65
3715 9999 Sundries, torch, LPG etc L.S. 46.8 2
3716 TOTAL
3717 Add 1 % Water charges on "W"
3718 TOTAL
3719 Add GST (multiplying factor 0.1405) on "X"
3720 TOTAL
3721 Add 15 % Contractor's profit and overheads on "Y"
3722 Total
3723 Add Cess @ 1% on "Z"
3724 Cost for 30 sqm
3725 Cost for 1 sqm
3726 Say

3727
3728
3729 14.64 Providing round the clock security guard
3730 without
Details of gun for1watch
cost for & ward
job (8hour's of
duty)
3731 48 Security guard (without gun) day 1 359.33
3732 9999 Lathi, torch, dress & other sundries L.S. 10 2
3733 TOTAL
3734 Add 15 % Contractor's profit and overheads on "Y"
3735 Total
3736 Add Cess @ 1% on "Z"
3737 Cost for 30 sqm
3738 Cost for 1 sqm
3739 Say
3740
3747
3748 14.65 Providing round the clock security guard
3750 with
Detailsgun for for
of cost watch
1 job & ward duty)
(8hour's of Government
3752 49 Security guard (with gun) day 1 403.67
3753 9999 Lathi, torch, uniform, wooden stick & other L.S. 10 2
3754 miscellaneous items
3755 TOTAL
3756 Add 15 % Contractor's profit and overheads on "Y"
3757 Cost of 1 job
3758 Say
3759
3809
3810
3811
3812
SUB HEAD : 15.0
3813
3814
3815
DISMANTLING AND
3816
3817
3818
3819 15.1 Demolishing lime concrete manually/ by
3820 mechanical means and disposal of material
3821 Detail of cost for 1 cum
3822 LABOUR
3823 17 Beldar day 0.44 350.00
3824 18 Coolie day 0.37 350.00
3825 9999 Sundries L.S. 1.04 2
3826 TOTAL
3827 Add 1 % Water charges on "W"
3828 TOTAL
3829 Add GST(multiplying factor 0.1405) on "X"
3830 TOTAL
3831 Add 15 % Contractor's profit and overheads on "Y"
3832 Total
3833 Add Cess @ 1% on "Z"
3834 Cost of 1.00 cum
3835 Say
3836
3837 15.2 Demolishing cement concrete manually/ by
3838 mechanical means including disposal of
3839
3840
3841 15.2.1 Nominal concrete 1:3:6 or richer mix (i/c
3842 equivalent design mix) charge.
3843 Detail of cost for 1 cum
3844 LABOUR
3845 17 Beldar day 1.59 350.00
3846 18 Coolie day 0.72 350.00
3847 9999 Sundries L.S. 4.81 2
3848 TOTAL
3849 Add 1 % Water charges on "W"
3850 TOTAL
3851 Add GST (multiplying factor 0.1405) on "X"
3852 TOTAL
3853 Add 15 % Contractor's profit and overheads on "Y"
3854 Total
3855 Add Cess @ 1% on "Z"
3856 Cost of 1.00 cum
3858 Say
3859
3860
3861
3862
3863
3864
3865
3866
3867 15.2.2 Nominal concrete 1:4:8 or leaner mix (i/c
3868 equivalent design mix)
3869 Detail of cost for 1 cum
3870 LABOUR
3871 17 Beldar day 0.88 350.00
3872 18 Coolie day 0.55 350.00
3873 9999 Sundries L.S. 1.95 2
3874 TOTAL
3875 Add 1 % Water charges on "W"
3876 TOTAL
3877 Add GST(multiplying factor 0.1405) on "X"
3878 TOTAL
3879 Add 15 % Contractor's profit and overheads on "Y"
3880 Total
3881 Add Cess @ 1% on "Z"
3882 Cost of 1.00 cum
3883 Say
3884
3885
3886
3887 15.3 Demolishing R.C.C. work manually/ by
3888 mechanical
metres lead means includingof
as per direction stacking of -
Engineer
3889 in- charge.
Detail of cost for 1 cum
3890 LABOUR
3891 17 Beldar day 2.65 350.00
3892 18 Coolie day 0.72 350.00
3893 9999 Sundries L.S. 7.02 2
3894 TOTAL
3895 Add 1 % Water charges on "W"
3896 TOTAL
3897 Add GST(multiplying factor 0.1405) on "X"
3898 TOTAL
3899 Add 15 % Contractor's profit and overheads on "Y"
3900 Total
3901 Add Cess @ 1% on "Z"
3902 Cost of 1.00 cum
3909 Say
3910
3911
3912
3913
3914
3915 15.4 Demolishing R.B. work manually/ by
3916 mechanical means
as per direction including stacking
of Engineer-in- charge.of
3917
3918 Detail of cost for 1 cum
3919 LABOUR
3920 17 Beldar day 2.12 350.00
3921 18 Coolie day 0.9 350.00
3922 9999 Sundries L.S. 4.68 2
3923 TOTAL
3924 Add 1 % Water charges on "W"
3925 TOTAL
3926 Add GST(multiplying factor 0.1405) on "X"
3927 TOTAL
3928 Add 15 % Contractor's profit and overheads on "Y"
3929 Total
3930 Add Cess @ 1% on "Z"
3931 Cost of 1.00 cum
3932 Say
3933
3934 15.5 Extra for cutting reinforcement bars
3935 manually/ by mechanical means in R.C.C.
3936 R.C.C. or R.B. work) as per direction of
3937 Engineer-in-charge.
3938 Detail of cost for 1 cum
3939 R.C.C. or R.B. work Reinforced area
3940 considering 1% reinforcement = 0.01sqm
3941 LABOUR
3942 For cutting 0.01 sqm reinforcement
3943 13 Blacksmith 2nd class day 0.5 403.67
3944 17 Beldar day 0.5 350.00
3945 9999 Sundries L.S. 13.39 2
3946 TOTAL
3947 Add 1 % Water charges on "W"
3948 TOTAL
3949 Add GST (multiplying factor 0.1405) on "X"
3956 TOTAL
3957 Add 15 % Contractor's profit and overheads on "Y"
3958 Total
3959 Add Cess @ 1% on "Z"
3960 Cost of 1.00 sqm
3961 Say
3962
3963
3964
3965
3966 15.6 Extra for scrapping, cleaning and
3967 straightening reinforcement from R.C.C.
3968 or R.B. work.
3969
3970 Detail of cost for 10 Nos
3971
3972 6 metres long 16 mm dia bars @
3973 1.58 kg/metre
3974 Total weight = 94.80 kg = 0.948 quintal
3975 LABOUR
3976 13 Blacksmith 2nd class day 0.25 403.67
3977 17 Beldar day 0.5 350.00
3978 9999 Sundries L.S. 13.39 2
3979 TOTAL
3980 Add 1 % Water charges on "W"
3981 TOTAL
3982 Add GST (multiplying factor 0.1405) on "X"
3983 TOTAL
3984 Add 15 % Contractor's profit and overheads on "Y"
3985 Total
3986 Add Cess @ 1% on "Z"
3987 Cost of 94.80 kg
3988 Cost of 1.00 kg
3989 Say
3990
3991 15.7 Demolishing brick work manually/ by
3992 mechanical means including stacking of
3993 15.7.1 In mud mortar
3994
3995 Detail of cost for 1 cum
3996 LABOUR
3997 17 Beldar day 0.3 350.00
3998 18 Coolie day 0.37 350.00
3999 9999 Sundries L.S. 1.04 2
4001 TOTAL
4002 Add 1 % Water charges on "W"
4003 TOTAL
4004 Add GST(multiplying factor 0.1405) on "X"
4005 TOTAL
4006 Add 15 % Contractor's profit and overheads on "Y"
4007 Total
4008 Add Cess @ 1% on "Z"
4009 Cost of 1.00 cum
4010 Say
4011
4012
4013
4014
4015
4016
4017 15.7.2 In lime mortar with old mughal bricks
4018 Detail of cost for 1 cum
4019 LABOUR
4020 17 Beldar day 1.24 350.00
4021 18 Coolie day 0.46 350.00
4022 9999 Sundries L.S. 1.04 2
4023 TOTAL
4024 Add 1 % Water charges on "W"
4025 TOTAL
4026 Add GST(multiplying factor 0.1405) on "X"
4027 TOTAL
4028 Add 15 % Contractor's profit and overheads on "Y"
4029 Total
4030 Add Cess @ 1% on "Z"
4031 Cost of 1.00 cum
4032 Say
4033
4034 15.7.3 In lime mortar
4035 Detail of cost for 1 cum
4036 LABOUR
4037 17 Beldar day 0.44 350.00
4038 18 Coolie day 0.37 350.00
4049 9999 Sundries L.S. 1.04 2
4050 TOTAL
4051 Add 1 % Water charges on "W"
4052 TOTAL
4053 Add GST(multiplying factor 0.1405) on "X"
4054 TOTAL
4055 Add 15 % Contractor's profit and overheads on "Y"
4056 Total
4057 Add Cess @ 1% on "Z"
4058 Cost of 1.00 cum
4059 Say
4060
4061 15.7.4 In cement mortar
4062 Detail of cost for 1 cum
4063 LABOUR
4064 17 Beldar day 1.06 350.00
4065 18 Coolie day 0.9 350.00
4066 9999 Sundries L.S. 2.47 2
4067 TOTAL
4068 Add 1 % Water charges on "W"
4069 TOTAL
4070 Add GST(multiplying factor 0.1405) on "X"
4071 TOTAL
4072 Add 15 % Contractor's profit and overheads on "Y"
4073 Total
4074 Add Cess @ 1% on "Z"
4075 Cost of 1.00 cum
4076 Say
4077
4078 15.8 Removing mortar from bricks and cleaning
4079 bricks including stacking within a lead of
4080 15.8.1 From brick work in mud mortar
4081
4082 Detail of cost for 1000 Nos
4083 LABOUR
4084 17 Beldar day 2.4 350.00
4085 18 Coolie day 1.6 350.00
4086 24 Mason (brick layer) 2nd class day 0.4 403.67
4087 9999 Sundries L.S. 1.82 2
4088 TOTAL
4089 Add 1 % Water charges on "W"
4090 TOTAL
4092 Add GST (multiplying factor 0.1405) on "X"
4093 TOTAL
4094 Add 15 % Contractor's profit and overheads on "Y"
4095 Total
4096 Add Cess @ 1% on "Z"
4097 Cost of 1000 Nos
4098 Say
4099
4100
4101
4102
4103
4104
4105 15.8.2 From brick work in lime mortar
4106 Detail of cost for 1000 Nos
4107 LABOUR
4108 17 Beldar day 2.8 350.00
4109 18 Coolie day 1.4 350.00
4110 24 Mason (brick layer) 2nd class day 0.8 403.67
4111 9999 Sundries L.S. 8.97 2
4112 TOTAL
4113 Add 1 % Water charges on "W"
4114 TOTAL
4115 Add GST (multiplying factor 0.1405) on "X"
4116 TOTAL
4117 Add 15 % Contractor's profit and overheads on "Y"
4118 Total
4119 Add Cess @ 1% on "Z"
4120 Cost of 1000 Nos
4121 Say
4122
4123 15.8.3 From brick work in cement mortar
4124 Detail of cost for 1000 Nos
4125 LABOUR
4126 17 Beldar day 3.5 350.00
4127 18 Coolie day 1.5 350.00
4128 24 Mason (brick layer) 2nd class day 1.24 403.67
4129 9999 Sundries L.S. 8.06 2
4130 TOTAL
4131 Add 1 % Water charges on "W"
4132 TOTAL
4133 Add GST (multiplying factor 0.1405) on "X"
4134 TOTAL
4135 Add 15 % Contractor's profit and overheads on "Y"
4136 Total
4138 Add Cess @ 1% on "Z"
4139 Cost of 1000 Nos
4140 Say
4141
4142
4143
4144
4145 15.9 Demolishing stone rubble masonry
4146 manually/ by mechanical means including
4147 15.9.1 In lime mortar
4148 Detail of cost for 1 cum
4149 LABOUR
4150 17 Beldar day 0.61 350.00
4151 18 Coolie day 0.49 350.00
4152 9999 Sundries L.S. 1.95 2
4153 TOTAL
4154 Add 1 % Water charges on "W"
4155 TOTAL
4156 Add GST(multiplying factor 0.1405) on "X"
4157 TOTAL
4158 Add 15 % Contractor's profit and overheads on "Y"
4159 Total
4160 Add Cess @ 1% on "Z"
4161 Cost of 1.00 cum
4162 Say
4163
4164
4165
4166
4167
4168 15.9.2 In cement mortar
4169 Detail of cost for 1 cum
4170 LABOUR
4171 17 Beldar day 1.3 350.00
4172 18 Coolie day 1.04 350.00
4173 9999 Sundries L.S. 2.73 2
4174 TOTAL
4175 Add 1 % Water charges on "W"
4176 TOTAL
4177 Add GST(multiplying factor 0.1405) on "X"
4178 TOTAL
4179 Add 15 % Contractor's profit and overheads on "Y"
4180 Total
4181 Add Cess @ 1% on "Z"
4182 Cost of 1.00 cum
4184 Say
4185
4186
4187
4188
4189
4190
4191
4192
4193
4194 15.10 Dismantling dressed stone work ashlar
4196 15.10.1 face stone
In lime work, marble work or precast
mortar
4197 Detail of cost for 1 cum
4198 LABOUR
4199 17 Beldar day 0.78 350.00
4200 18 Coolie day 0.61 350.00
4201 9999 Sundries L.S. 2.73 2
4202 TOTAL
4203 Add 1 % Water charges on "W"
4204 TOTAL
4205 Add GST(multiplying factor 0.1405) on "X"
4206 TOTAL
4207 Add 15 % Contractor's profit and overheads on "Y"
4208 Total
4209 Add Cess @ 1% on "Z"
4210 Cost of 1.00 cum
4211 Say
4212
4213
4214 15.10.2 In cement mortar
4215 Detail of cost for 1 cum
4216 LABOUR
4217 17 Beldar day 1.55 350.00
4218 18 Coolie day 1.19 350.00
4219 9999 Sundries L.S. 2.73 2
4220 TOTAL
4221 Add 1 % Water charges on "W"
4222 TOTAL
4223 Add GST(multiplying factor 0.1405) on "X"
4224 TOTAL
4225 Add 15 % Contractor's profit and overheads on "Y"
4226 Total
4227 Add Cess @ 1% on "Z"
4228 Cost of 1.00 cum
4229 Say
4230
4232
4233
4234
4235
4236
4237
4238
4239
4240
4241 15.11 Removing mortar from and cleaning
4242 stones and concrete articles (net quantity
4243 15.11.1 In lime mortar
4244 Detail of cost for 1 cum
4245 LABOUR
4246 24 Mason (brick layer) 2nd class day 0.05 403.67
4247 17 Beldar day 0.2 350.00
4248 18 Coolie day 0.2 350.00
4249 9999 Sundries L.S. 0.52 2
4250 TOTAL
4251 Add 1 % Water charges on "W"
4252 TOTAL
4253 Add GST (multiplying factor 0.1405) on "X"
4254 TOTAL
4255 Add 15 % Contractor's profit and overheads on "Y"
4256 Total
4257 Add Cess @ 1% on "Z"
4258 Cost of 1.00 cum
4259 Say
4260
4261
4262
4263
4264 15.11.2 In cement mortar
4265 Detail of cost for 1 cum
4266 LABOUR
4267 24 Mason (brick layer) 2nd class day 0.05 403.67
4268 17 Beldar day 0.4 350.00
4269 18 Coolie day 0.2 350.00
4270 9999 Sundries L.S. 0.91 2
4271 TOTAL
4272 Add 1 % Water charges on "W"
4273 TOTAL
4274 Add GST (multiplying factor 0.1405) on "X"
4275 TOTAL
4276 Add 15 % Contractor's profit and overheads on "Y"
4278 Total
4279 Add Cess @ 1% on "Z"
4280 Cost of 1.00 cum
4281 Say
4282
4283
4284
4285
4286
4287 15.12 Dismantling doors, windows and
4288 clerestory windows
stacking within (steel or
50 metres wood)
lead shutter
: 15.12.1 Of
4289 area 3 sq. metres and below
4290 Detail of cost for each
4291 LABOUR
4292 24 Mason (brick layer) 2nd class day 0.1 403.67
4293 17 Beldar day 0.18 350.00
4294 13 Blacksmith 2nd class day 0.05 403.67
4295 9999 Sundries L.S. 1.43 2
4296 TOTAL
4297 Add 1 % Water charges on "W"
4298 TOTAL
4299 Add GST (multiplying factor 0.1405) on "X"
4300 TOTAL
4301 Add 15 % Contractor's profit and overheads on "Y"
4302 Total
4303 Add Cess @ 1% on "Z"
4304 Cost of each
4305 Say
4306
4307
4308 15.12.2 Of area beyond 3 sq. metres
4309 Detail of cost for each
4310 LABOUR
4311 24 Mason (brick layer) 2nd class day 0.13 403.67
4312 17 Beldar day 0.25 350.00
4313 13 Blacksmith 2nd class day 0.07 403.67
4314 9999 Sundries L.S. 2.73 2
4315 TOTAL
4316 Add 1 % Water charges on "W"
4317 TOTAL
4318 Add GST (multiplying factor 0.1405) on "X"
4319 TOTAL
4320 Add 15 % Contractor's profit and overheads on "Y"
4321 Total
4322 Add Cess @ 1% on "Z"
4323 Cost of each
4324 Say
4325
4326
4328
4329
4330
4331
4332
4333
4334
4335
4336 15.13 Taking out doors, windows and clerestory
4337 window shutters (steel or wood) including
4338 15.13.1 Of area 3 sq. metres and below
4339
4340 Detail of cost for each
4341 LABOUR
4342 15 Carpenter 2nd class day 0.05 403.67
4343 17 Beldar day 0.08 350.00
4344 9999 Sundries L.S. 0.52 2
4345 TOTAL
4346 Add 1 % Water charges on "W"
4347 TOTAL
4348 Add GST (multiplying factor 0.1405) on "X"
4349 TOTAL
4350 Add 15 % Contractor's profit and overheads on "Y"
4351 Total
4352 Add Cess @ 1% on "Z"
4353 Cost of each
4354 Say

4355 15.13.2 Of area beyond 3 sq. metres


4356 Detail of cost for each
4357 LABOUR
4358 15 Carpenter 2nd class day 0.07 403.67
4359 17 Beldar day 0.1 350.00
4360 9999 Sundries L.S. 0.91 2
4361 TOTAL
4362 Add 1 % Water charges on "W"
4363 TOTAL
4364 Add GST (multiplying factor 0.1405) on "X"
4365 TOTAL
4366 Add 15 % Contractor's profit and overheads on "Y"
4367 Total
4368 Add Cess @ 1% on "Z"
4369 Cost of each
4377 Say
4378
4379
4380
4381
4382 15.14 Dismantling wood work in frames, trusses,
4383 purlins and rafters up to 10 metres span
4384 metres lead :
4385
4386 15.14.1 Of sectional area 40 square centimetres
4387 and above
4388 Detail of cost for 1 cum
4389 LABOUR
4390 15 Carpenter 2nd class day 2 403.67
4391 17 Beldar day 2 350.00
4392 9999 Sundries L.S. 13.39 2
4393 TOTAL
4394 Add 1 % Water charges on "W"
4395 TOTAL
4396 Add GST (multiplying factor 0.1405) on "X"
4397 TOTAL
4398 Add 15 % Contractor's profit and overheads on "Y"
4399 Total
4400 Add Cess @ 1% on "Z"
4401 Cost of 1.00 cum
4402 Say

4403 15.14.2 Of sectional area below 40 square


4404 centimetres
Detail of cost for 10 metre
4405 LABOUR
4406 15 Carpenter 2nd class day 0.08 403.67
4407 17 Beldar day 0.08 350.00
4408 9999 Sundries L.S. 0.52 2
4409 TOTAL
4410 Add 1 % Water charges on "W"
4411 TOTAL
4412 Add GST (multiplying factor 0.1405) on "X"
4413 TOTAL
4414 Add 15 % Contractor's profit and overheads on "Y"
4415 Total
4416 Add Cess @ 1% on "Z"
4417 Cost of 10.00 metre
4418 Cost of 1.00 metre
4425 Say
4426
4427
4428
4429
4430 15.15 Extra for dismantling trusses, rafters,
4431 purlins etc. of wood work for every
4432 15.15.1 Of sectional area 40 square centimetres
4433 and above
4434 Detail of cost for 1cum for every additional
4435
4436 span of 1 metre
4437 LABOUR
4438
4439 13 Blacksmith 2nd class day 0.2 403.67
4440 17 Beldar day 0.3 350.00
4441 9999 Sundries L.S. 13.39 2
4442 TOTAL
4443 Add 1 % Water charges on "W"
4444 TOTAL
4445 Add GST (multiplying factor 0.1405) on "X"
4446 TOTAL
4447 Add 15 % Contractor's profit and overheads on "Y"
4448 Total
4449 Add Cess @ 1% on "Z"
4450 Cost of 1.00 cum per metre span
4451 Say
4452
4453 15.15.2 Of sectional area below 40 square
4454 centimetres
Detail of cost for 10 metre for every
4455 additional span of 1 metre
4456 LABOUR
4457 13 Blacksmith 2nd class day 0.006 403.67
4458 17 Beldar day 0.008 350.00
4459 9999 Sundries L.S. 0.39 2
4460 TOTAL
4461 Add 1 % Water charges on "W"
4462 TOTAL
4463 Add GST (multiplying factor 0.1405) on "X"
4464 TOTAL
4465 Add 15 % Contractor's profit and overheads on "Y"
4466 Total
4467 Add Cess @ 1% on "Z"
4468 Cost of 10.00 metre per metre span
4469 Cost of 1.00 metre per metre span
4478
4479
4480 Say
4481
4482 15.16 Extra for dismantling trusses, rafters,
4483 purlins etc. of wood work for every
4484 15.16.1 Of sectional area 40 square centimetres
4485 and above
4486 Detail of cost for 1 cum for every additional
4487 LABOUR
4488 13 Blacksmith 2nd class day 0.25 403.67
4489 17 Beldar day 0.5 350.00
4490 9999 Sundries L.S. 13.39 2
4491 TOTAL
4492 Add 1 % Water charges on "W"
4493 TOTAL
4494 Add GST (multiplying factor 0.1405) on "X"
4495 TOTAL
4496 Add 15 % Contractor's profit and overheads on "Y"
4497 Total
4498 Add Cess @ 1% on "Z"
4499 Cost of 1.00 cum per metre height
4500 Say
4501
4502 15.16.2 Of sectional area below 40 square
4503 centimetres
Detail of cost for 10 metre for every
4504 additional height of 1 metre
4505 LABOUR
4506 13 Blacksmith 2nd class day 0.01 403.67
4507 17 Beldar day 0.02 350.00
4508 9999 Sundries L.S. 0.39 2
4509 TOTAL
4510 Add 1 % Water charges on "W"
4511 TOTAL
4512 Add GST (multiplying factor 0.1405) on "X"
4513 TOTAL
4514 Add 15 % Contractor's profit and overheads on "Y"
4515 Total
4516 Add Cess @ 1% on "Z"
4517 Cost of 10.00 metre per metre height
4526 Cost of 1.00 metre per metre height
4527 Say
4528
4529
4530 15.17 Dismantling steel work in single sections
4531 including dismembering and stacking
4532 15.17.1 R.S. Joists
4533
4534 Detail of cost for 1 quintal
4535 LABOUR
4536 13 Blacksmith 2nd class day 0.05 403.67
4537 10 Bandhani day 0.1 350.00
4538 17 Beldar day 0.15 350.00
4539 9999 Sundries L.S. 2.73 2
4540 TOTAL
4541 Add 1 % Water charges on "W"
4542 TOTAL
4543 Add GST (multiplying factor 0.1405) on "X"
4544 TOTAL
4545 Add 15 % Contractor's profit and overheads on "Y"
4546 Total
4547 Add Cess @ 1% on "Z"
4548 Cost of 1.00 quintal
4549 Cost of 1.00 kg
4550 Say
4551 15.17.2 Channels, angles, tees and flats
4552 Detail of cost for 1 quintal
4553 LABOUR
4554 13 Blacksmith 2nd class day 0.05 403.67
4555 10 Bandhani day 0.05 350.00
4556 17 Beldar day 0.1 350.00
4557 9999 Sundries L.S. 2.73 2
4558 TOTAL
4559 Add 1 % Water charges on "W"
4560 TOTAL
4561 Add GST (multiplying factor 0.1405) on "X"
4562 TOTAL
4563 Add 15 % Contractor's profit and overheads on "Y"
4564 Total
4565 Add Cess @ 1% on "Z"
4574 Cost of 1.00 quintal
4575 Cost of 1.00 kg
4576 Say
4577
4578
4579 15.18 Dismantling steel work in built up sections
4580 in angles, tees, flats and channels
4581 including dismembering and stacking
4582 within 50 metres lead.
4583 Detail of cost for 1 quintal
4584 LABOUR
4585 13 Blacksmith 2nd class day 0.15 403.67
4586 10 Bandhani day 0.1 350.00
4587 17 Beldar day 0.25 350.00
4588 9999 Sundries L.S. 4.16 2
4589 TOTAL
4590 Add 1 % Water charges on "W"
4591 TOTAL
4592 Add GST (multiplying factor 0.1405) on "X"
4593 TOTAL
4594 Add 15 % Contractor's profit and overheads on "Y"
4595 Total
4596 Add Cess @ 1% on "Z"
4597 Cost of 1.00 quintal
4598 Cost of 1.00 kg
4599 Say
4600
4601 15.19 Dismantling steel work manually/ by
4605 mechanical means
Detail of cost for in built up sections
1 quintal
4606
4607 LABOUR
4608 10 Bandhani day 0.1 350.00
4609 17 Beldar day 0.25 350.00
4610 9999 Sundries L.S. 2.73 2
4611 TOTAL
4612 Add 1 % Water charges on "W"
4613 TOTAL
4614 Add GST (multiplying factor 0.1405) on "X"
4615 TOTAL
4624 Add 15 % Contractor's profit and overheads on "Y"
4625 Total
4626 Add Cess @ 1% on "Z"
4627 Cost of 1.00 quintal
4628 Cost of 1.00 kg
4629 Say
4630
4631
4632 15.20 Extra for dismantling trusses, rafters,
4633 purlins etc. of steel work for every
4634 Detail of cost for 1 quintal for every
4635 additional span of 1 metre beyond 10 metre
4636 LABOUR
4637 10 Bandhani day 0.02 350.00
4638 17 Beldar day 0.06 350.00
4639 9999 Sundries L.S. 0.39 2
4640 TOTAL
4641 Add 1 % Water charges on "W"
4642 TOTAL
4643 Add GST(multiplying factor 0.1405) on "X"
4644 TOTAL
4645 Add 15 % Contractor's profit and overheads on "Y"
4646 Total
4647 Add Cess @ 1% on "Z"
4648 Cost of 1.00 quintal per metre span
4649 Cost of 1.00 kg per metre span
4650 Say
4651
4652 15.21 Extra for dismantling trusses, rafters,
4653 purlins etc. of steel work for every
4654 Detail of cost for 1 quintal for every
4655 additional height of 1 metre beyond 5 metre
4656 LABOUR
4657 10 Bandhani day 0.02 350.00
4658 17 Beldar day 0.06 350.00
4659 9999 Sundries L.S. 0.39 2
4660 TOTAL
4661 Add 1 % Water charges on "W"
4662 TOTAL
4671 Add GST (multiplying factor 0.1405) on "X"
4672 TOTAL
4673 Add 15 % Contractor's profit and overheads on "Y"
4674 Total
4675 Add Cess @ 1% on "Z"
4676 Cost of 1.00 quintal per metre height
4677 Cost of 1.00 kg per metre height
4678 Say
4679
4680
4681 15.22 Extra for marking of structural steel work
4682 required to be re-erected.
4683 Detail of cost for 1 quintal
4684 LABOUR
4685 30 Mistry day 0.2 505.17
4686 17 Beldar day 0.2 350.00
4687 TOTAL
4688 Add 1 % Water charges on "W"
4689 TOTAL
4690 Add GST(multiplying factor 0.1405) on "X"
4691 TOTAL
4692 Add 15 % Contractor's profit and overheads on "Y"
4693 Total
4694 Add Cess @ 1% on "Z"
4695 Cost of 1.00 quintal
4696 Cost of 1.00 kg
4697 Say
4698
4699 15.23 Dismantling tile work in floors and roofs
4700 laid in cement mortar including stacking
4701 15.23.1 For thickness of tiles 10 mm to 25 mm
4702
4703 Detail of cost for 10 sqm
4704 LABOUR
4705 24 Mason (brick layer) 2nd class day 0.3 403.67
4706 17 Beldar day 0.12 350.00
4707 18 Coolie day 0.24 350.00
4708 9999 Sundries L.S. 2.73 2
4709 TOTAL
4719 Add 1 % Water charges on "W"
4720 TOTAL
4721 Add GST (multiplying factor 0.1405) on "X"
4722 TOTAL
4723 Add 15 % Contractor's profit and overheads on "Y"
4724 Total
4725 Add Cess @ 1% on "Z"
4726 Cost of 10.00 sqm
4727 Cost of 1.00 sqm
4728 Say
4729
4730 15.23.2 For thickness of tiles above 25 mm and up
4731 to 40 of
Detail mmcost for 10 sqm
4732 LABOUR
4733 24 Mason (brick layer) 2nd class day 0.59 403.67
4734 17 Beldar day 0.18 350.00
4735 18 Coolie day 0.24 350.00
4736 9999 Sundries L.S. 2.73 2
4737 TOTAL
4738 Add 1 % Water charges on "W"
4739 TOTAL
4740 Add GST (multiplying factor 0.1405) on "X"
4741 TOTAL
4742 Add 15 % Contractor's profit and overheads on "Y"
4743 Total
4744 Add Cess @ 1% on "Z"
4745 Cost of 10.00 sqm
4746 Cost of 1.00 sqm
4747 Say
4748

4749 15.24 Demolishing dry brick pitching in floors,


4750 drains etc. including stacking serviceable
4751 metres lead :
4752
4753 Detail of cost for 1 cum
4754
4755 LABOUR
4756 17 Beldar day 0.25 350.00
4757 18 Coolie day 1 350.00
4767 9999 Sundries L.S. 2.73 2
4768 TOTAL
4769 Add 1 % Water charges on "W"
4770 TOTAL
4771 Add GST (multiplying factor 0.1405) on "X"
4772 TOTAL
4773 Add 15 % Contractor's profit and overheads on "Y"
4774 Total
4775 Add Cess @ 1% on "Z"
4776 Cost of 1.00 cum
4777 Say
4778
4779 15.25 Dismantling stone slab flooring laid in
4780 cement mortar including stacking of
metres lead.
4783 Detail of cost for 10 sqm
4784 LABOUR
4785 17 Beldar day 1.77 350.00
4786 18 Coolie day 0.75 350.00
4787 9999 Sundries L.S. 8.06 2
4788 TOTAL
4789 Add 1 % Water charges on "W"
4790 TOTAL
4791 Add GST(multiplying factor 0.1405) on "X"
4792 TOTAL
4793 Add 15 % Contractor's profit and overheads on "Y"
4794 Total
4795 Add Cess @ 1% on "Z"
4796 Cost of 10.00 sqm
4797 Cost of 1.00 sqm
4798 Say
4799
4800
4801 15.26 Demolishing brick tile covering in terracing
4802 including stacking of serviceable material
metres lead.
4806 Detail of cost for 10 sqm
4807 LABOUR
4808 24 Mason (brick layer) 2nd class day 0.54 403.67
4809 17 Beldar day 0.16 350.00
4810 18 Coolie day 0.24 350.00
4811 9999 Sundries L.S. 2.47 2
4812 TOTAL
4813 Add 1 % Water charges on "W"
4822
4823 TOTAL
4824 Add GST (multiplying factor 0.1405) on "X"
4825 TOTAL
4826 Add 15 % Contractor's profit and overheads on "Y"
4827 Total
4828 Add Cess @ 1% on "Z"
4829 Cost of 10.00 sqm
4830 Cost of 1.00 sqm
4831 Say
4832
4833 15.27 Demolishing mud phaska in terracing and
4834 disposal of material within 50
metres lead.
4838 Detail of cost for 1 cum
4839 LABOUR
4840 17 Beldar day 0.25 350.00
4841 18 Coolie day 0.62 350.00
4842 9999 Sundries L.S. 1.04 2
4843 TOTAL
4844 Add 1 % Water charges on "W"
4845 TOTAL
4846 Add GST(multiplying factor 0.1405) on "X"
4847 TOTAL
4848 Add 15 % Contractor's profit and overheads on "Y"
4849 Total
4850 Add Cess @ 1% on "Z"
4851 Cost of 1.00 cum
4852 Say
4853
4854 15.28 Dismantling roofing including ridges, hips,
4855 15.28.1 valleys and gutters etc., and stacking the
G.S. Sheet
4858 Detail of cost for 10 sqm
4859 LABOUR
4860 15 Carpenter 2nd class day 0.5 403.67
4861 17 Beldar day 1 350.00
4862 9999 Sundries L.S. 6.76 2
4863 TOTAL
4864 Add 1 % Water charges on "W"
4865 TOTAL
4866 Add GST (multiplying factor 0.1405) on "X"
4876 TOTAL
4877 Add 15 % Contractor's profit and overheads on "Y"
4878 Total
4879 Add Cess @ 1% on "Z"
4880 Cost of 10.00 sqm
4881 Cost of 1.00 sqm
4882 Say
4883
4884 15.28.2 Asbestos sheet
4885 Detail of cost for 10 sqm
4886 LABOUR
4887 15 Carpenter 2nd class day 0.2 403.67
4888 17 Beldar day 0.5 350.00
4889 9999 Sundries L.S. 5.33 2
4890 TOTAL
4891 Add 1 % Water charges on "W"
4892 TOTAL
4893 Add GST (multiplying factor 0.1405) on "X"
4894 TOTAL
4895 Add 15 % Contractor's profit and overheads on "Y"
4896 Total
4897 Add Cess @ 1% on "Z"
4898 Cost of 10.00 sqm
4899 Cost of 1.00 sqm
4900 Say
4901

4902 15.29 Dismantling stone slab roofing over


4903 wooden
within 50karries
metresorlead.
R.C.C. battens
4907 Detail of cost for 1 cum
4908 LABOUR
4909 17 Beldar day 1.77 350.00
4910 18 Coolie day 0.75 350.00
4911 9999 Sundries L.S. 8.06 2
4912 TOTAL
4913 Add 1 % Water charges on "W"
4914 TOTAL
4915 Add GST (multiplying factor 0.1405) on "X"
4922 TOTAL
4923 Add 15 % Contractor's profit and overheads on "Y"
4924 Total
4925 Add Cess @ 1% on "Z"
4926 Cost of 1.00 cum
4927 Say
4928
4929
4930
4931
4932 15.3 Dismantling jack arch roofing and floors
4934 including stacking
Detail of cost of serviceable material
for 10 sqm
4935 LABOUR
4936 17 Beldar day 1.19 350.00
4937 18 Coolie day 1.21 350.00
4938 9999 Sundries L.S. 8.06 2
4939 TOTAL
4940 Add 1 % Water charges on "W"
4941 TOTAL
4942 Add GST(multiplying factor 0.1405) on "X"
4943 TOTAL
4944 Add 15 % Contractor's profit and overheads on "Y"
4945 Total
4946 Add Cess @ 1% on "Z"
4947 Cost of 10.00 sqm
4948 Cost of 1.00 sqm
4949 Say
4950
4951 15.31 Dismantling tiled roofing with battens,
4952 boarding
within 50 etc. complete
metres lead. including stacking
4956 Detail of cost for 10 sqm
4957 LABOUR
4958 17 Beldar day 1.73 350.00
4959 18 Coolie day 0.25 350.00
4960 9999 Sundries L.S. 8.06 2
4971 TOTAL
4972 Add 1 % Water charges on "W"
4973 TOTAL
4974 Add GST (multiplying factor 0.1405) on "X"
4975 TOTAL
4976 Add 15 % Contractor's profit and overheads on "Y"
4977 Total
4978 Add Cess @ 1% on "Z"
4979 Cost of 10.00 sqm
4980 Cost of 1.00 sqm
4981 Say
4982
4983 15.32 Demolishing thatch roofing including mats,
4984 bamboo, jaffari 50
material within etc.metres
complete
lead.including
4987 Detail of cost for 10 sqm
4988 LABOUR
4989 17 Beldar day 0.54 350.00
4990 9999 Sundries L.S. 3.64 2
4991 TOTAL
4992 Add 1 % Water charges on "W"
4993 TOTAL
4994 Add GST(multiplying factor 0.1405) on "X"
4995 TOTAL
4996 Add 15 % Contractor's profit and overheads on "Y"
4997 Total
4998 Add Cess @ 1% on "Z"
4999 Cost of 10.00 sqm
5000 Cost of 1.00 sqm
5001 Say
5002
5003 15.33 Dismantling wooden ballies in posts and
5004 struts including
50 metres lead. stacking within
5005 Detail of cost for 50 metre
5018 LABOUR
5019 17 Beldar day 0.5 350.00
5020 18 Coolie day 0.5 350.00
5021 9999 Sundries L.S. 0.52 2
5022 TOTAL
5023 Add 1 % Water charges on "W"
5024 TOTAL
5025 Add GST (multiplying factor 0.1405) on "X"
5026 TOTAL
5027 Add 15 % Contractor's profit and overheads on "Y"
5028 Total
5029 Add Cess @ 1% on "Z"
5030 Cost of 50.00 metre
5031 Cost of 1.00 metre
5032 Say
5033
5034 15.34 Dismantling and stacking within 50 metres
5036 15.34.1 lead, fencing
T' or 'L' posts
iron or pipe or struts including all
5038 Detail of cost for each
5039 LABOUR
5040 17 Beldar day 0.107 350.00
5041 18 Coolie day 0.067 350.00
5042 9999 Excavation, transporting and stacking the L.S. 0.26 2
5043 posts to the required place within 50 metre s
5044 lead, refilling the pit and dressing the same
5045 9999 Extra for lifting of R.C.C. posts being heavier L.S. 13.39 2
5046 than L iron and cleaning the posts
5047 of stacking concrete
5048 9999 Sundries L.S. 1.43 2
5049 TOTAL
5050 Add 1 % Water charges on "W"
5051 TOTAL
5052 Add GST (multiplying factor 0.1405) on "X"
5053 TOTAL
5054 Add 15 % Contractor's profit and overheads on "Y"
5055 Total
5056 Add Cess @ 1% on "Z"
5064 Cost of each
5065 Say
5066
5067
5068 15.34.2 R.C.C.
5069 Detail of cost for each
5070 LABOUR
5071 17 Beldar day 0.097 350.00
5072 18 Coolie day 0.06 350.00
5073 9999 Sundries L.S. 0.26 2
5074 9999 Excavation, transporting and stacking the L.S. 13.39 2
5075 posts to the required place within 50 metre s
5076 lead, refilling the pit and dressing the same
5077 9999 Extra for lifting of R.C.C. posts being heavier L.S. 8.06 2
5078 than L iron and cleaning the posts
5079 of stacking concrete
5080 9999 Sundries L.S. 2.73 2
5081 TOTAL
5082 Add 1 % Water charges on "W"
5083 TOTAL
5084 Add GST (multiplying factor 0.1405) on "X"
5085 TOTAL
5086 Add 15 % Contractor's profit and overheads on "Y"
5087 Total
5088 Add Cess @ 1% on "Z"
5089 Cost of each
5090 Say
5091
5092 15.35 Cutting ballies or wooden posts of fencing
5094 at theofpoint
Detail of 1projection
cost for ballie (post) above the
5095 9999 Cutting L.S. 2.73 2
5096 9999 Transporting and stacking L.S. 1.43 2
5097 TOTAL
5098 Add 1 % Water charges on "W"
5099 TOTAL
5100 Add GST (multiplying factor 0.1405) on "X"
5101 TOTAL
5109 Add 15 % Contractor's profit and overheads on "Y"
5110 Total
5111 Add Cess @ 1% on "Z"
5112 Cost of each
5113 Say
5114
5115
5116
5117 15.36 Dismantling barbed wire or flexible wire
5118 rope in fencing including making rolls and
5119 Detail of cost for 1 quintal
5120 LABOUR
5121 17 Beldar day 3.5 350.00
5122 9999 Sundries L.S. 5.33 2
5123 TOTAL
5124 Add 1 % Water charges on "W"
5125 TOTAL
5126 Add GST(multiplying factor 0.1405) on "X"
5127 TOTAL
5128 Add 15 % Contractor's profit and overheads on "Y"
5129 Total
5130 Add Cess @ 1% on "Z"
5131 Cost of 1.00 quintal
5132 Cost of 1.00 kg
5133 Say
5134
5135 15.37 Dismantling wooden trellis work excluding
5136 frames but for
Detail of cost including
1 quintal stacking the
5139 LABOUR
5140 24 Mason (brick layer) 2nd class day 0.1 403.67
5141 17 Beldar day 0.25 350.00
5142 18 Coolie day 0.25 350.00
5143 9999 Sundries L.S. 2.73 2
5144 TOTAL
5145 Add 1 % Water charges on "W"
5146 TOTAL
5147 Add GST (multiplying factor 0.1405) on "X"
5148 TOTAL
5149 Add 15 % Contractor's profit and overheads on "Y"
5150 Total
5157 Add Cess @ 1% on "Z"
5158 Cost of 10.00 sqm
5159 Cost of 1.00 sqm
5160 Say
5161
5162
5163
5164 15.38 Dismantling expanded metal or I.R.C.
5165 fabrics with necessary battens and
5166 Detail of cost for 10 sqm
5167 LABOUR
5168 15 Carpenter 2nd class day 0.1 403.67
5169 17 Beldar day 0.4 350.00
5170 18 Coolie day 0.2 350.00
5171 9999 Sundries L.S. 4.16 2
5172 TOTAL
5173 Add 1 % Water charges on "W"
5174 TOTAL
5175 Add GST (multiplying factor 0.1405) on "X"
5176 TOTAL
5177 Add 15 % Contractor's profit and overheads on "Y"
5178 Total
5179 Add Cess @ 1% on "Z"
5180 Cost of 10.00 sqm
5181 Cost of 1.00 sqm
5182 Say
5183
5184 15.39 Dismantling wooden boardings in lining of
5185 15.39.1 walls
Up to and partitions,
10 mm thick excluding supporting
5188 Detail of cost for 10 sqm
5189 LABOUR
5190 15 Carpenter 2nd class day 0.15 403.67
5191 17 Beldar day 0.2 350.00
5192 18 Coolie day 0.2 350.00
5193 9999 Sundries L.S. 5.33 2
5194 TOTAL
5195 Add 1 % Water charges on "W"
5196 TOTAL
5197 Add GST (multiplying factor 0.1405) on "X"
5198 TOTAL
5204 Add 15 % Contractor's profit and overheads on "Y"
5205 Total
5206 Add Cess @ 1% on "Z"
5207 Cost of 10.00 sqm
5208 Cost of 1.00 sqm
5209 Say
5210
5211
5212
5213 15.39.2 Thickness above 10 mm up to 25 mm
5214 Detail of cost for 10 sqm
5215 LABOUR
5216 15 Carpenter 2nd class day 0.2 403.67
5217 17 Beldar day 0.25 350.00
5218 18 Coolie day 0.25 350.00
5219 9999 Sundries L.S. 6.76 2
5220 TOTAL
5221 Add 1 % Water charges on "W"
5222 TOTAL
5223 Add GST (multiplying factor 0.1405) on "X"
5224 TOTAL
5225 Add 15 % Contractor's profit and overheads on "Y"
5226 Total
5227 Add Cess @ 1% on "Z"
5228 Cost of 10.00 sqm
5229 Cost of 1.00 sqm
5230 Say

5231 15.39.3 Thickness above 25 mm up to 40 mm


5232 Detail of cost for 10 sqm
5233 LABOUR
5234 15 Carpenter 2nd class day 0.2 403.67
5235 17 Beldar day 0.3 350.00
5236 18 Coolie day 0.3 350.00
5237 9999 Sundries L.S. 13.39 2
5238 TOTAL
5239 Add 1 % Water charges on "W"
5240 TOTAL
5241 Add GST (multiplying factor 0.1405) on "X"
5242 TOTAL
5243 Add 15 % Contractor's profit and overheads on "Y"
5244 Total
5253 Add Cess @ 1% on "Z"
5254 Cost of 10.00 sqm
5255 Cost of 1.00 sqm
5256 Say
5257
5258
5259
5260 15.4 Dismantling precast concrete or stone
5261 slabs in walls, partition walls etc. including
5262 15.40.1 Thickness up to 40 mm
5264 Detail of cost for 10 sqm
5265 LABOUR
5266 24 Mason (brick layer) 2nd class day 0.2 403.67
5267 17 Beldar day 2 350.00
5268 18 Coolie day 0.5 350.00
5269 9999 Sundries L.S. 13.39 2
5270 TOTAL
5271 Add 1 % Water charges on "W"
5272 TOTAL
5273 Add GST (multiplying factor 0.1405) on "X"
5274 TOTAL
5275 Add 15 % Contractor's profit and overheads on "Y"
5276 Total
5277 Add Cess @ 1% on "Z"
5278 Cost of 10.00 sqm
5279 Cost of 1.00 sqm
5280 Say
5281 15.40.2 Thickness above 40 mm up to 75 mm
5282 Detail of cost for 10 sqm
5283 LABOUR
5284 24 Mason (brick layer) 2nd class day 0.3 403.67
5285 17 Beldar day 3 350.00
5286 18 Coolie day 0.75 350.00
5287 9999 Sundries L.S. 18.85 2
5288 TOTAL
5289 Add 1 % Water charges on "W"
5290 TOTAL
5291 Add GST (multiplying factor 0.1405) on "X"
5292 TOTAL
5301 Add 15 % Contractor's profit and overheads on "Y"
5302 Total
5303 Add Cess @ 1% on "Z"
5304 Cost of 10.00 sqm
5305 Cost of 1.00 sqm
5306 Say
5307
5308
5309
5310 15.41 Dismantling cement asbestos or other hard
5311 board ceiling or partition walls including
5312 Detail of cost for 10 sqm.
5313 LABOUR
5314 15 Carpenter 2nd class day 0.2 403.67
5315 17 Beldar day 0.3 350.00
5316 9999 Sundries L.S. 5.33 2
5317 TOTAL
5318 Add 1 % Water charges on "W"
5319 TOTAL
5320 Add GST (multiplying factor 0.1405) on "X"
5321 TOTAL
5322 Add 15 % Contractor's profit and overheads on "Y"
5323 Total
5324 Add Cess @ 1% on "Z"
5325 Cost of 10.00 sqm
5326 Cost of 1.00 sqm
5327 Say
5328
5329 15.42 Dismantling C.I. or asbestos rain water
5330 15.42.1 pipe
75 towith fittings
80 mm and clamps including
dia pipe
5333 Detail of cost for 10 metre
5335 LABOUR
5336 17 Beldar day 0.36 350.00
5337 18 Coolie day 0.36 350.00
5338 9999 Sundries L.S. 0.91 2
5339 TOTAL
5340 Add 1 % Water charges on "W"
5341 TOTAL
5342 Add GST (multiplying factor 0.1405) on "X"
5343 TOTAL
5352 Add 15 % Contractor's profit and overheads on "Y"
5353 Total
5354 Add Cess @ 1% on "Z"
5355 Cost of 10.00 metre
5356 Cost of 1.00 metre
5357 Say
5358
5359
5360 15.42.2 100 mm dia pipe
5361 Detail of cost for 10 metre
5362 LABOUR
5363 17 Beldar day 0.36 350.00
5364 18 Coolie day 0.38 350.00
5365 9999 Sundries L.S. 1.56 2
5366 TOTAL
5367 Add 1 % Water charges on "W"
5368 TOTAL
5369 Add GST(multiplying factor 0.1405) on "X"
5370 TOTAL
5371 Add 15 % Contractor's profit and overheads on "Y"
5372 Total
5373 Add Cess @ 1% on "Z"
5374 Cost of 10.00 metre
5375 Cost of 1.00 metre
5376 Say

5377 15.42.3 150 mm dia pipe


5378 Detail of cost for 10 metre
5379 LABOUR
5380 17 Beldar day 0.36 350.00
5381 18 Coolie day 0.4 350.00
5382 9999 Sundries L.S. 2.08 2
5383 TOTAL
5384 Add 1 % Water charges on "W"
5385 TOTAL
5386 Add GST(multiplying factor 0.1405) on "X"
5387 TOTAL
5388 Add 15 % Contractor's profit and overheads on "Y"
5389 Total
5397 Add Cess @ 1% on "Z"
5398 Cost of 10.00 metre
5399 Cost of 1.00 metre
5400 Say
5401
5402
5403
5404 15.43 Dismantling manually/ by mechanical
5405 15.43.1 means including
Water bound stacking
macadam of serviceable
road
5408 Detail of cost for 36 sqm
5409 Consider a road 6 metres wide and 6 metres
5410 length wise 25 cm average depth =
5411 9.00 cubic metre
5412 LABOUR
5413 For cutting road taking out soiling and
5414 metalling including sorting and screening
5415 17 Beldar day 4.8 350.00
5416 18 Coolie day 2.4 350.00
5417 9999 Labour for stacking of serviceable material L.S. 89.7 2
5418 and disposal of unserviceable material
5419 within 50 metres lead
5420 TOTAL
5421 Add 1 % Water charges on "W"
5422 TOTAL
5423 Add GST (multiplying factor 0.1405) on "X"
5424 TOTAL
5425 Add 15 % Contractor's profit and overheads on "Y"
5426 Total
5427 Add Cess @ 1% on "Z"
5428 Cost of 36.00 sqm
5429 Cost of 1.00 sqm
5430 Say
5431 15.43.2 bituminous road
5432 Detail of cost for 36 sqm
5433 Consider a road 6 metres wide and 6 metres
5434 length wise 30 cm average depth =
5435 10.80 cubic metre
5436 LABOUR
5437 For cutting road taking out soiling and
5438 metalling including sorting and screening
5439 17 Beldar day 9.6 350.00
5440 18 Coolie day 4.8 350.00
5441 9999 Labour for stacking of serviceable material L.S. 107.64 2
5442 and disposal of unserviceable material
5452 within 50 metres lead
5453 TOTAL
5454 Add 1 % Water charges on "W"
5455 TOTAL
5456 Add GST (multiplying factor 0.1405) on "X"
5457 TOTAL
5458 Add 15 % Contractor's profit and overheads on "Y"
5459 Total
5460 Add Cess @ 1% on "Z"
5461 Cost of 36.00 sqm
5462 Cost of 1.00 sqm
5463 Say
5464
5465 15.44 Dismantling G.I. pipes (external work)
5468 15.44.1 including
15 mm to excavation and refilling
40 mm nominal bore trenches
5469
5470 Detail of cost for 10 metre
5471 LABOUR
5472 Trenching and refilling etc
5473 17 Beldar day 0.66 350.00
5474 18 Coolie day 0.66 350.00
5475 9999 Dismantling G.I. pipe and stacking etc L.S. 35.88 2
5476 TOTAL
5477 Add 1 % Water charges on "W"
5478 TOTAL
5479 Add GST (multiplying factor 0.1405) on "X"
5480 TOTAL
5481 Add 15 % Contractor's profit and overheads on "Y"
5482 Total
5483 Add Cess @ 1% on "Z"
5484 Cost of 10.00 metre
5485 Cost of 1.00 metre
5486 Say
5487
5488 15.44.2 Above 40 mm nominal bore
5489 Detail of cost for 10 metre
5501 LABOUR
5502 Trenching and refilling etc
5503 17 Beldar day 0.66 350.00
5504 18 Coolie day 0.66 350.00
5505 9999 Dismantling G.I. pipe and stacking etc L.S. 71.76 2
5506 TOTAL
5507 Add 1 % Water charges on "W"
5508 TOTAL
5509 Add GST (multiplying factor 0.1405) on "X"
5510 TOTAL
5511 Add 15 % Contractor's profit and overheads on "Y"
5512 Total
5513 Add Cess @ 1% on "Z"
5514 Cost of 10.00 metre
5515 Cost of 1.00 metre
5516 Say
5517
5518 15.45 Dismantling C.I. pipes including
5519 15.45.1 excavation anddiameter
Up to 150 mm refilling trenches after
5523 Detail of cost for 40.26 metre or 11 nos joints Earth work in
excavation for dismantling
5524 pipes including refilling of excavated earth
5526 1x40.26x0.55x0.75 m =16.61cum
5527 Deduct for pipes of average 100 mm dia
5528 =1x40.26x(22/7)/4x(0.118)x(0.118)
5529 =0.44cum
5530 Total =16.17cum
5531 LABOUR
5532 2.8.1 Rate as per Item No.2.8.1 of cum 16.17 181.00
5533 SH: EARTH WORK
5534 2.25 Rate as per Item No.2.25 of cum 16.17 124.5
5535 SH: EARTH WORK
5536 761 Fuel wood quintal 0.46 500
5537 771 Kerosene oil litre 0.38 50
5538 20 Assistant Fitter or 2nd class Fitter day 0.63 403.67
5539 17 Beldar day 4.5 350.00
5549 9977 Carriage L.S. 53.82 2
5550 TOTAL
5551 Add 1 % Water charges on "W-A"
5552 TOTAL
5553 Add GST (multiplying factor 0.1405) on "X-
5554 A"
5555 TOTAL
5556 Add 15 % Contractor's profit and overheads
5557 on "Y-A"
5558 Total
5559 Add Cess @ 1% on "Z-A"
5560 Cost of 40.26 metre
5561 Cost of 1.00 metre
5562 Say
5563 15.42.2 Above 150 mm dia up to 300 mm dia
5564 Detail of cost for 40.26 metre or 11 nos
5565 joints Earth work in excavation for
5566 dismantling
5567 pipes including refilling of excavated earth
5568 1x40.26x0.65x0.75 m =19.63cum
5569 Deduct for pipes of average 250 mm dia
5570 =1x40.26x(22/7)/4x(0.274)x(0.274)
5571 =2.37cum
5572 Total =17.26cum
5573 LABOUR
5574 2.8.1 Rate as per Item No.2.8.1 of cum 17.26 181.00
5575 SH: EARTH WORK
5576 2.25 Rate as per Item No.2.25 of cum 17.26 124.5
5577 SH: EARTH WORK
5578 761 Fuel wood quintal 1.03 500
5579 771 Kerosene oil litre 1.14 50
5580 20 Assistant Fitter or 2nd class Fitter day 1.3 403.67
5581 17 Beldar day 7.5 350.00
5582 9977 Carriage L.S. 80.73 2
5583 TOTAL
5584 Add 1 % Water charges on "W-A"
5585 TOTAL
5586 Add GST (multiplying factor 0.1405) on "X-A"
5587 TOTAL
5596 Add 15 % Contractor's profit and overheads
5597 on "Y-A"
5598 Total
5599 Add Cess @ 1% on "Z-A"
5600 Cost of 40.26 metre
5601 Cost of 1.00 metre
5602 Say
5603
5604
5605 15.45.3 Above 300 mm diameter
5606 Detail of cost for 40.26 metre or 11 nos
5607 joints Earth work in excavation for
5608 dismantling
5609 pipes including refilling of excavated earth
5610 1x40.26x0.85x0.75 m =25.67cum
5611 Deduct for pipes of average 450 mm dia
5612 =1x40.26x(22/7)/4x(0.48)x(0.48) =7.29cum
5613 Total =18.38cum
5614 LABOUR
5615 2.8.1 Rate as per Item No.2.8.1 of cum 18.38 181.00
5616 SH: EARTH WORK
5617 2.25 Rate as per Item No.2.25 of cum 18.38 124.5
5618 SH: EARTH WORK
5619 761 Fuel wood quintal 1.4 500
5620 771 Kerosene oil litre 2.27 50
5621 20 Assistant Fitter or 2nd class Fitter day 2.25 403.67
5622 17 Beldar day 11.5 350.00
5623 9988 Carriage and sundries L.S. 134.55 2
5624 TOTAL
5625 Add 1 % Water charges on "W-A"
5626 TOTAL
5627 Add GST (multiplying factor 0.1405) on "X-
5628 A"
5629 TOTAL
5630 Add 15 % Contractor's profit and overheads
5631 on "Y-A"
5632 Total
5633 Add Cess @ 1% on "Z-A"
5634 Cost of 40.26 metre
5635 Cost of 1.00 metre
5645 Say
5647
5648
5649 15.46 Dismantling steel cylinder R.C. pipes
5650 15.46.1 including
Up to 600 excavation
mm diameter and refilling trenches
5653 Detail of cost for 40.26 metre or 11 nos joints Earth work in
excavation for
5654 dismantling pipes including refilling of excavated
earth
5657 1x40.26x1.30x1.65 m =86.36cum Deduct for pipes of
average 450 mm dia
5659 =1x40.26x(22/7)/4x(0.48)x(0.48) =7.29cum
Total=79.07cum
5660
5661 LABOUR
5662
5663 17 Beldar day 5.32 350.00
5664 18 Coolie day 5.46 350.00
5665 11 Bhisti day 0.31 350.00
5666 761 Fuel wood quintal 1.4 500
5667 771 Kerosene oil litre 2.27 50
5668 20 Assistant Fitter or 2nd class Fitter day 2.25 403.67
5669 17 Beldar day 11.5 350.00
5670 9988 Carriage and sundries L.S. 134.55 2
5671 TOTAL
5672 Add 1 % Water charges on "W"
5673 TOTAL
5674 Add GST (multiplying factor 0.1405) on "X"
5675 TOTAL
5676 Add 15 % Contractor's profit and overheads on "Y"
5677 Total
5678 Add Cess @ 1% on "Z"
5679 Cost of 40.26 metre
5680 Cost of 1.00 metre
5681 Say
5682
5683 15.46.2 Above 600 mm diameter
5685 Detail of cost for 40.26 metre or 11 nos joints Earth
work in excavation for dismantling
5694 pipes including refilling of excavated earth
5695 1x40.26x1.30x1.65 m =86.36cum
5696 Deduct for pipes of average 450 mm dia
5697 =1x40.26x(22/7)/4x(1.00)x(1.00) =31.63cum
5698 Total=54.73cum
5699 LABOUR
5700 17 Beldar day 15.82 350.00
5701 18 Coolie day 16.25 350.00
5702 11 Bhisti day 0.93 350.00
5703 761 Fuel wood quintal 3.08 500
5704 771 Kerosene oil litre 5 50
5705 20 Assistant Fitter or 2nd class Fitter day 10 403.67
5706 17 Beldar day 20 350.00
5707 9988 Carriage and sundries L.S. 179.4 2
5708 TOTAL
5709 Add 1 % Water charges on "W"
5710 TOTAL
5711 Add GST (multiplying factor 0.1405) on "X"
5712 TOTAL
5713 Add 15 % Contractor's profit and overheads on "Y"
5714 Total
5715 Add Cess @ 1% on "Z"
5716 Cost of 40.26 metre
5717 Cost of 1.00 metre
5718 Say
5719
5720 15.47 Dismantling asbestos cement pressure
5724 15.47.1 pipes
Up to including excavation and refilling
150 mm diameter
5725 Detail of cost for 10 metre or 11 nos joints
5728 Earth work in excavation for dismantling pipes including
refilling of excavated earth
5729 10.00x0.55x0.75 m =4.125cum
5730 Deduct for pipes of average 100 mm dia
5731 =1x10x(22/7)/4x(0.118)x(0.118) =0.109cum
5736 Total=4.016cum
5737 LABOUR
5739 17 Beldar day 1.16 350.00
5748 18 Coolie day 1.19 350.00
5749 11 Bhisti day 0.07 350.00
5750 17 Beldar day 0.36 350.00
5751 18 Coolie day 0.38 350.00
5752 9988 Carriage and sundries L.S. 1.56 2
5753 TOTAL
5754 Add 1 % Water charges on "W"
5755 TOTAL
5756 Add GST (multiplying factor 0.1405) on "X"
5757 TOTAL
5758 Add 15 % Contractor's profit and overheads on "Y"
Total
5759 TOTAL
5760 Add Cess @ 1% on "Z"
5761 Cost of 10.00 metre
5762 Cost of 1.00 metre
5763 Say
5764
5765 15.47.2 Above 150 mm diameter
5766 Detail of cost for 10 metre or 11 nos joints
5767 Earth work in excavation for dismantling pipes including
refilling of excavated earth
5768 10.00x0.65x0.75 m =4.88cum
5772 Deduct for pipes of average 250 mm dia
=1x10x(22/7)/4x(0.274)x(0.274) =0.590cum
5773 Total=4.29cum
5776 LABOUR
5778 17 Beldar day 1.24 350.00
5779 18 Coolie day 1.28 350.00
5780 11 Bhisti day 0.07 350.00
5781 17 Beldar day 0.36 350.00
5782 18 Coolie day 0.88 350.00
5783 9988 Carriage and sundries L.S. 3.77 2
5784 TOTAL
5785 Add 1 % Water charges on "W"
5786 TOTAL
5787 Add GST (multiplying factor 0.1405) on "X"
5788 TOTAL
5789 Add 15 % Contractor's profit and overheads on "Y"
5790 Total
5791 Add Cess @ 1% on "Z"
5792 Cost of 10.00 metre
5793 Cost of 1.00 metre
5794 Say
5795
5796
5797
5798
5799
5800
5801
5802
5803
5804
5805
5806
5807
5808
5809
5810
5811
5812
5814
5829
5831
5833
5835
5837
5839
5841
5843
5845
5847
5849
5851
5853
5855
5863
5864
5865
5866
5867
5868 15.48 Taking out C.I. cover with frame from
5870 Details of top
R.C.C. cost slab of hole
for 1 man manholes ofofvarious
Demolition R.C.C. slab
1.3x1.2x0.15 m =0.234cum
5871 Less cover 0.61x0.455x0.15 m =0.042cum
5873 =0.192cum
5874 LABOUR
5876 17 Beldar day 0.5 350.00
5877 18 Coolie day 0.14 350.00
5878 9999 Removel of C.I. Cover with frame including L.S. 1.3 2
5879 stacking
5880 9999 Sundries L.S. 7.15 2
5881 TOTAL
5882 Add 1 % Water charges on "W"
5883 TOTAL
5884 Add GST (multiplying factor 0.1405) on "X"
5885 TOTAL
5886 Add 15 % Contractor's profit and overheads on "Y"
5887 Total
5888 Add Cess @ 1% on "Z"
5889 Cost of each
5890 Say
5891

5892 15.49 Taking out C.I. cover with frame from


5896 R.C.C.
Detail of top
costslab of inspection
for 1 man hole chambers of
5898 Demolition of R.C.C. slab 1.1x0.9x0.15 m =0.148cum
5900 Less cover 0.61x0.455x0.15 m =0.042cum =0.106cum
Say 0.11cum
5902 LABOUR
5913 17 Beldar day 0.29 350.00
5914 18 Coolie day 0.08 350.00
5915 9999 Removel of C.I. Cover with frame including L.S. 0.65 2
5916 stacking
5917 9999 Sundries L.S. 5.33 2
5918 TOTAL
5919 Add 1 % Water charges on "W"
5920 TOTAL
5921 Add GST (multiplying factor 0.1405) on "X"
5922 TOTAL
5923 Add 15 % Contractor's profit and overheads on "Y"
5924 Total
5925 Add Cess @ 1% on "Z"
5926 Cost of each
5927 Say
5928
5929 15.5 Dismantling of R.C.C. spun vent shaft
5930 including excavating
materials within the cement
50 metres lead. concrete
5931 Detail of cost for each Dismantling cement concrete
1:4:8 0.90x0.90x1.35m =1.094cum
5936 Less shaft 1/4x22/7x(0.450)x(0.450)x 1.10 m
=0.175cum
5937 =0.919cum Say 0.92cum Dismantling cement
concrete 1:2:4 0.90x0.90x0.15m =0.122cum Less
5938 =0.098cum Say 0.10cum
5940 LABOUR
5941 17 Beldar day 0.81 350.00
5942 18 Coolie day 0.51 350.00
5943 9999 Sundries L.S. 1.82 2
5944 17 Beldar day 0.16 350.00
5945 18 Coolie day 0.07 350.00
5946 9999 Sundries L.S. 0.52 2
5947 30 Mistry day 0.25 505.17
5948 23 Mason (brick layer) 1st class day 0.12 505.17
5957 24 Mason (brick layer) 2nd class day 0.12 403.67
5958 10 Bandhani day 1 350.00
5959 17 Beldar day 1 350.00
5960 9999 Sundries for scaffolding etc L.S. 53.82 2
5961 TOTAL
5962 Add 1 % Water charges on "W"
5963 TOTAL
5964 Add GST (multiplying factor 0.1405) on "X"
5965 TOTAL
5966 Add 15 % Contractor's profit and overheads on "Y"
5967 Total
5968 Add Cess @ 1% on "Z"
5969 Cost of each
5970 Say
5971

5972 15.51 Dismantling of road gully chamber of


5977 various sizes
Detail of cost for including C.I. grating with
one chamber
5978 Dismantling cement concrete
5979 a) 1:5:10 1.05x1.00x0.15m =0.16cum
5980 Dismantling brick work in cement mortar
5981 2.70x0.20x0.45m =0.24cum Dismantling
5982 cement concrete
5983 b) 1:2:4 2.70x0.20x0.15m =0.08cum
5984 LABOUR
5985 17 Beldar day 0.14 350.00
5986 18 Coolie day 0.09 350.00
5987 9999 Sundries L.S. 0.26 2
5988 17 Beldar day 0.25 350.00
5989 18 Coolie day 0.22 350.00
5990 9999 Sundries L.S. 0.52 2
5991 17 Beldar day 0.13 350.00
5992 18 Coolie day 0.06 350.00
5993 9999 Sundries for scaffolding etc L.S. 0.39 2
5994 9999 Dismantling C.I. Grating L.S. 7.15 2
5995 TOTAL
5996 Add 1 % Water charges on "W"
6003 TOTAL
6004 Add GST (multiplying factor 0.1405) on "X"
6005 TOTAL
6006 Add 15 % Contractor's profit and overheads on "Y"
6007 Total
6008 Add Cess @ 1% on "Z"
6009 Cost of each
6010 Say
6011
6012
6013
6014 15.52 Dismantling of flushing cistern of all types
6018 (C.I./PVC/Vitrious
Detail of cost for eachChina) including
6019 LABOUR
6020 19 Fitter (grade 1) day 0.25 505.17
6021 17 Beldar day 0.5 350.00
6022 9999 Sundries L.S. 17.94 2
6023 TOTAL
6024 Add 1 % Water charges on "W"
6025 TOTAL
6026 Add GST (multiplying factor 0.1405) on "X"
6027 TOTAL
6028 Add 15 % Contractor's profit and overheads on "Y"
6029 Total
6030 Add Cess @ 1% on "Z"
6031 Cost of each
6032 Say
6033

6034 15.53 Dismantling of C.I. sluice valve including


6035 stacking of for
Detail of cost useful materials
dismantling within
10 sluice a lead
valves (ace.)
100mm
6036 LABOUR
6042 19 Fitter (grade 1) day 0.6 505.17
6043 20 Assistant Fitter or 2nd class Fitter day 0.4 403.67
6044 17 Beldar day 1.6 350.00
6045 9999 Sundries for removing the R.C.C. cover etc L.S. 89.7 2
6046 for dismantling sluice valve
6056 TOTAL
6057 Add 1 % Water charges on "W"
6058 TOTAL
6059 Add GST (multiplying factor 0.1405) on "X"
6060 TOTAL
6061 Add 15 % Contractor's profit and overheads on "Y"
6062 Total
6063 Add Cess @ 1% on "Z"
6064 Cost of 10 Nos
6065 Cost of each
6066 Say
6067 15.53.2 Above 150 mm diameter
6068 Detail of cost for dismantling 10 sluice
6069 valves (ace.) 100mm
6070 LABOUR
6071 19 Fitter (grade 1) day 2.4 505.17
6072 20 Assistant Fitter or 2nd class Fitter day 1.54 403.67
6073 17 Beldar day 6.4 350.00
6074 9999 Sundries for removing the R.C.C. cover etc L.S. 89.7 2
6075 for dismantling sluice valve
6076 TOTAL
6077 Add 1 % Water charges on "W"
6078 TOTAL
6079 Add GST (multiplying factor 0.1405) on "X"
6080 TOTAL
6081 Add 15 % Contractor's profit and overheads on "Y"
6082 Total
6083 Add Cess @ 1% on "Z"
6084 Cost of 10 Nos
6085 Cost of each
6086 Say
6087
6088 15.54 Dismantling of spindle fire hydrant
6093 including stacking
Detail of cost for 10 Nosof useful materials
6094 LABOUR
6095 19 Fitter (grade 1) day 1.5 505.17
6096 20 Assistant Fitter or 2nd class Fitter day 1 403.67
6107 17 Beldar day 4 350.00
6108 TOTAL
6109 Add 1 % Water charges on "W"
6110 TOTAL
6111 Add GST (multiplying factor 0.1405) on "X"
6112 TOTAL
6113 Add 15 % Contractor's profit and overheads on "Y"
6114 Total
6115 Add Cess @ 1% on "Z"
6116 Cost of 10 Nos
6117 Cost of each
6118 Say
6119
6120 15.55 Dismantling of cement concrete platform
6121 15.55.1 along withcm
120 x 120 curtain walls
(outside toand base concrete
outside)
6122 Detail of cost for one platform Dismantling cement
concrete 1:5:10 4.00x0.35x0.12m =0.168cum
6123 Dismantling brick work in cement mortar
4.00x0.20x0.30m =0.24cum 4.00x0.10x0.20m
6129 Dismantling 40 mm C.C. flooring 1:2:4
1.00x1.00x0.04m =0.04cum
6130 LABOUR
6132 17 Beldar day 0.19 350.00
6133 18 Coolie day 0.12 350.00
6134 9999 Sundries L.S. 0.39 2
6135 17 Beldar day 0.35 350.00
6136 18 Coolie day 0.3 350.00
6137 9999 Sundries L.S. 0.91 2
6138 17 Beldar day 0.06 350.00
6139 18 Coolie day 0.03 350.00
6140 9999 Sundries for scaffolding etc L.S. 0.13 2
6141 TOTAL
6150
6151 Add 1 % Water charges on "W"
6152 TOTAL
6153 Add GST (multiplying factor 0.1405) on "X"
6154 TOTAL
6155 Add 15 % Contractor's profit and overheads on "Y"
6156 Total
6157 Add Cess @ 1% on "Z"
6158 Cost of each
6159 Say
6160
6161 15.55.2 210 x 120 cm (outside to outside)
6162 Detail of cost for one platform Dismantling cement
concrete 1:5:10 5.80x0.35x0.12m =0.243cum
6163 Dismantling brick work in cement mortar
5.80x0.20x0.30m =0.348cum 6.20x0.10x0.20m
6164 Dismantling 40 mm C.C. flooring 1:2:4
1.90x1.00x0.04m =0.08cum
6170 LABOUR
6171 17 Beldar day 0.31 350.00
6172 18 Coolie day 0.19 350.00
6173 9999 Sundries L.S. 0.65 2
6174 17 Beldar day 0.5 350.00
6175 18 Coolie day 0.42 350.00
6176 9999 Sundries L.S. 1.3 2
6177 17 Beldar day 0.13 350.00
6178 18 Coolie day 0.06 350.00
6179 9999 Sundries for scaffolding etc L.S. 0.39 2
6180 TOTAL
6181 Add 1 % Water charges on "W"
6182 TOTAL
6183 Add GST (multiplying factor 0.1405) on "X"
6184 TOTAL
6185 Add 15 % Contractor's profit and overheads on "Y"
6186 Total
6194 Add Cess @ 1% on "Z"
6195 Cost of each
6196 Say
6197
6198
6199
6200 15.55.3 320 x 120 cm (outside to outside)
6202 Detail of cost for one platform
6203 Dismantling cement concrete 1:5:10
6204 8.00x0.35x0.12m =0.336cum
6205 2.80x0.80x0.075m =0.168cum
6206 =0.504cum Say 0.50cum
6207 Dismantling brick work in cement mortar
6208 8.00x0.20x0.30m =0.48cum
6209 8.40x0.10x0.20m =0.168cum
6210 =0.648cum Say 0.65cum
6211 Dismantling 40 mm C.C. flooring 1:2:4
6212 3.00x1.00x0.04m =0.12cum
6213 LABOUR
6214 17 Beldar day 0.44 350.00
6215 18 Coolie day 0.28 350.00
6216 9999 Sundries L.S. 0.91 2
6217 17 Beldar day 0.69 350.00
6218 18 Coolie day 0.59 350.00
6219 9999 Sundries L.S. 1.56 2
6220 17 Beldar day 0.19 350.00
6221 18 Coolie day 0.09 350.00
6222 9999 Sundries for scaffolding etc L.S. 0.52 2
6223 TOTAL
6224 Add 1 % Water charges on "W"
6225 TOTAL
6226 Add GST (multiplying factor 0.1405) on "X"
6227 TOTAL
6228 Add 15 % Contractor's profit and overheads on "Y"
6229 Total
6230 Add Cess @ 1% on "Z"
6231 Cost of each
6232 Say
6233
6243
6245 15.56 Dismantling old plaster or skirting raking
6246 out
Detailjoints
of costand cleaning
for 10 sqm the surface for
6251 LABOUR
6252 17 Beldar day 0.36 350.00
6253 18 Coolie day 0.08 350.00
6254 11 Bhisti day 0.07 350.00
6255 9999 Sundries for scaffolding etc L.S. 1.43 2
6256 TOTAL
6257 Add 1 % Water charges on "W"
6258 TOTAL
6259 Add GST (multiplying factor 0.1405) on "X"
6260 TOTAL
6261 Add 15 % Contractor's profit and overheads on "Y"
6262 Total
6263 Add Cess @ 1% on "Z"
6264 Cost of 10.00 sqm
6265 Cost of 1.00 sqm
6266 Say
6267
6268 15.57 Dismantling aluminium/ Gypsum
6273 partitions,
Detail of costdoors, windows, fixed glazing
for 10 sqm
6274 LABOUR
6275 15 Carpenter 2nd class day 0.2 403.67
6276 17 Beldar day 0.3 350.00
6277 9999 Sundries L.S. 5.38 2
6278 TOTAL
6279 Add 1 % Water charges on "W"
6280 TOTAL
6281 Add GST (multiplying factor 0.1405) on "X"
6282 TOTAL
6283 Add 15 % Contractor's profit and overheads on "Y"
6284 Total
6285 Add Cess @ 1% on "Z"
6286 Cost of 10.00 sqm
6287 Cost of 1.00 sqm
6288 Say
6289
6299
6301 15.58 Demolishing R.C.C. work by mechanical
6302 means
Details ofand
coststockpiling
for 1 cum at designated
6307 LABOUR
6308 28 Mate day 0.03 350.00
6309 Labour for operating pneumatic tools
6310 37 Skilled Beldar (for floor rubbing etc.) day 0.5 350.00
6311 17 Beldar day 0.5 350.00
6312 Labour for cutting reinforcement bars.
6313 13 Blacksmith 2nd class day 0.5 403.67
6314 17 Beldar day 0.5 350.00
6315 MACHINERY
6316 40 Air compressor 250 cfm with two leads for day 0.125 1600
6317 pneumatic cutters/ hammers.
6318 39 Tractor with trolley . day 0.05 1350
6319 41 Joint cutting machine with 2-3 blades day 0.125 800
6320 TOTAL
6321 Add 1 % Water charges on "W"
6322 TOTAL
6323 Add GST (multiplying factor 0.1405) on "X"
6324 TOTAL
6325 Add 15 % Contractor's profit and overheads on "Y"
6326 Total
6327 Add Cess @ 1% on "Z"
6328 Cost of 1 cum
6329 Say
6330
6331 15.59 Dismantling of flexible pavement
6332 (bituminous courses)
Details of cost for 1 cum by mechanical
6337 LABOUR
6338 28 Mate day 0.01 350.00
6339 17 Beldar day 0.3 350.00
6340 MACHINERY
6341 39 Tractor with trolley . day 0.0475 1350
6342 38 Tractor with ripper attachment. day 0.002 1200
6352 TOTAL
6353 Add 1 % Water charges on "W"
6354 TOTAL
6355 Add GST (multiplying factor 0.1405) on "X"
6356 TOTAL
6357 Add 15 % Contractor's profit and overheads on "Y"
6358 Total
6359 Add Cess @ 1% on "Z"
6360 Cost of 1 cum
6361 Say
6362

6363 15.6 Disposal of building rubbish / malba /


6364 similar
Details ofunserviceable,
cost for 1 cum dismantled or waste
6369 2264 Carriage of Rubbish cum 1 106.13
6370 TOTAL
6371 Add 1 % Water charges on "W"
6372 TOTAL
6373 Add GST (multiplying factor 0.1405) on "X"
6374 TOTAL
6375 Add 15 % Contractor's profit and overheads on "Y"
6376 Total
6377 Add Cess @ 1% on "Z"
6378 Cost of 1 cum
6379 Say
6380
610.04

488.44
451.50
189.00
322.00
30.42
2091.40 W
20.914
2112.31 X
296.78
2409.09 Y
361.36
2770.45 Z
27.70
2798.15
279.82
279.80 264.35

698.15

488.44
451.50
189.00
322.00
30.42
2179.51 W
21.7951
2201.31 X
309.28
2510.59 Y
376.59
2887.18 Z
28.87
2916.05
291.6
291.60 276.15

28.35
0.00
9.72
0.00
2.99
0.00
19.04
8.25
32.60
0.62
9.45
6.83
4.24
0.91
0.73
0.42
2.86
1.56

0.78

26.79
48.36
27.04
3.64
201.84
262.50
5.46
704.98 W
7.0498
712.03 X
100.04
812.07 Y
121.81
933.88 Z
9.34
943.22
943.22 883.05
943.20

18.90
0.00
6.48
0.00
2
0.00
12.69
5.50
21.74
0.42
6.30
4.55
2.83
0.61
0.48
0.28
1.82
1.04

0.52

16.07
19.76
1.82
133.21
175.00
432.02 W
4.3202
436.34 X
61.31
497.65 Y
74.65
572.30 Z
5.72
578.02
578.02 538.05

9.45
0.00
3.24
0.00
1
0.00
6.35
2.75
10.87
0.21
3.15
2.28
1.41
0.30
0.24
0.14
1.04
0.52
0.00
0.26

8.04
16.12
1.82
68.62
175.00
5.46
318.27 W
3.1827
321.45 X
45.16
366.61 Y
54.99
421.60 Z
4.22
425.82
425.82 395.9
9.45
6.83
4.24
0.42
3.64
84.00
24.44

133.02 W
1.3302
134.35 X
18.88
153.23 Y
22.98
176.21 Z
1.76
177.97 175.8
177.97

26.79
49.14
201.84
420.00
140.00
7.00
844.77 W
8.4477
853.22 X
119.88
973.10 Y
145.96
1119.06 Z
11.19
1130.25
598.01
598.00 554.65

330.00

3.64
20.40
10.66
13.52
92.84
80.50
2.86
554.42 W
5.5442
559.96 X
78.67
638.63 Y
95.80
734.43 Z
7.34
741.77
741.77 723.85
741.80

550.00

3.64
20.40
10.66
13.52
92.84
80.50
2.86
774.42 W
7.7442
782.16 X
109.89
892.05 Y
133.81
1025.86 Z
10.26
1036.12 1018.2
1036.12
1036.10

330.00

19.40
12.50
7.50
8.84
5.46
80.73
100.92
157.50
3.64
726.49 W
7.2649
733.75 X
103.09
836.84 Y
125.53
962.37 Z
9.62
971.99
971.99 936.9
972.00

550.00

19.40
12.50
7.50
8.84
5.46
80.73
100.92
157.50
3.64
946.49 W
9.4649
955.95 X
134.31
1090.26 Y
163.54
1253.80 Z
12.54
1266.34
1266.34 1231.2
1266.30

330.00

5.46
19.76
10.66
121.10
105.00
2.86
594.84 W
5.9484
600.79 X
84.41
685.20 Y
102.78
787.98 Z
7.88
795.86
795.86
795.90

550.00

5.46
19.76
10.66
121.10
105.00
2.86
814.84 W
8.1484
822.99 X
115.63
938.62 Y
140.79
1079.41 Z
10.79
1090.20
1090.2 1066.8
1090.20

90.97
53.82

100.92
87.50
5.46
338.67 W
3.3867
342.06 X
48.06
390.12 Y
58.52
448.64 Z
4.49
453.13
45.31
45.30 43.35

40.25

53.82

100.92
87.50
5.46
287.95 W
2.8795
290.83 X
40.86
331.69 Y
49.75
381.44 Z
3.81
385.25
38.52
38.50 36.55
20.40
14.30
5.46

121.10
105.00
2.86
269.12 W
2.6912
271.81 X
38.19
310.00 Y
46.50
356.50 Z
3.57
360.07
27.7
27.70 25.9

20.40
5.46
14.30

121.10
105.00
2.86
324.52 W
3.2452
327.77 X
46.05
373.82 Y
56.07
429.89 Z
4.30
434.19
434.19
434.20 336.65
121.10
105.00
2.86
7.80
236.76 W
2.3676
239.13 X
33.60
272.73 Y
40.91
313.64 Z
3.14
316.78
316.78 293.35
316.80

0.00
27.81
27.04

0.00
14.3

0.00
14.28
48.44
87.50
5.46
224.83 W
2.2483
227.08 X
31.90
258.98 Y
38.85
297.83 Z
2.98
300.81
300.81 286.35
300.80

217.98
189.00

0.00
101.12

118.63
42.00

59.32

87.50
243.27

484.40
525.00
350.00
10.66
5.46
2434.34 W
24.3434
2458.68 X
345.45
2804.13 Y
420.62
3224.75 Z
32.25
3257.00
325.7
325.70 306.05
0.00

0.00
283.93
131.25
8.06
80.86

2475.00

133.02

0.00
40.06
0.00
29.91
682.20
710.50
591.50
119.00
32.24
47.17
5364.70 W
53.647
5418.35 X
761.28
6179.63 Y
926.94
7106.57 Z
71.07
7177.64
717.76
717.80 694.65

0.00
18360.00
37.11
0.00
0.00
0.00
201.84
700.00
10.66
161.46
158.60
73.87
64.05
1.56
10.14
9.62
19788.91 W
197.8891
19986.80 X
2808.15
22794.95 Y
3419.24
26214.19 Z
262.14
26476.33
88254.43
88254.40 87881.6

0.00
0.00
187.50
2.77

100.92
87.50

52.48
175.00
115.50

18360.00
37.11
403.67
175.00
350.00

59.15
28.26
24.50
0.26
3.64
3.64
41.34
53.82
100.00
20362.06 W
203.6206
20565.68 X
2889.48
23455.16 Y
3518.27
26973.43 Z
269.73
27243.16
90810.54
90810.50 90277.15
0.00
109.38
2.77

100.92
87.50

52.48
175.00
115.50

10710.00
37.11
403.67
175.00
350.00

59.15
28.26
24.50
0.26
3.64
3.64
41.34
53.82
100.00
12633.94 W
126.3394
12760.28 X
1792.82
14553.10 Y
2182.96
16736.06 Z
167.36
16903.42
56344.73
56344.70 55811.3

0.00
225
6.04

100.92
87.50

100.92
220.50
175.00

22980.00
46.45
403.67
350.00
700.00

73.45
32.29
28.00
0.52
4.68
4.42
41.34
66.30
150.00
25797.00 W
257.97
26054.97 X
3660.72
29715.69 Y
4457.35
34173.04 Z
341.73
34514.77
92039.39
92039.40 91410.8

131.25
4.55

100.92
87.50

100.92
220.50
175.00
13405.00
46.45
403.67
350.00
700.00

73.45
32.29
28.00
0.52
4.68
4.42
41.34
66.30
150.00
16126.76 W
161.2676
16288.03 X
2288.47
18576.50 Y
2786.47
21362.97 Z
213.63
21576.60
57537.59
57537.60 56909

185.50
28.00
24.50
2.86
240.86 W
2.4086
243.27 X
34.18
277.45 Y
41.62
319.07 Z
3.19
322.26
32.23
32.20 29.55

0.00

59.82
5.36

126.00
145.32
126.00
37.70
500.20 W
5.002
505.20 X
70.98
576.18 Y
86.43
662.61 Z
6.63
669.24
66.92
66.90 62.7

0.00

67.80
6.06

126.00
145.32
126.00
37.70
508.88 W
5.0888
513.97 X
72.21
586.18 Y
87.93
674.11 Z
6.74
680.85
68.08
68.10 63.85

36.33
21.00
56.00
113.33 W
1.1333
114.46 X
16.08
130.54 Y
19.58
150.12 Z
1.50
151.62
2.41
2.40 2.2

816.00
20.40
23.80
2.34

171.76
119.00
27.82

0.00

0.00

1347.66
11.61
1359.27 X
164.79
1524.07 Y
200.65

1724.72 Z
15.38
1740.1
86.14
86.15

598.00
1.23

214.85

0.00

25.08

48.36
3.64

17.65 A

201.84
262.50
5.20
1540.92 W
11.11
1552.03 X
157.67
1709.7 Y
191.98

1901.68 Z
14.72
1916.39
165.92
165.9

0.00
0.00
4.04
3.50
7.00
0.78

620.00

157.50

40.80
160.00

0.00
14.28
7.00
38.50

0.00 A
5.49
3.38
1045.31 W
10.4
1055.71 X
147.56
1203.27 Y
179.67

1382.93 Z
13.77
1396.71
139.67
139.65
0.00

14.98
9.62
19.25
2.08

620

450
76.8
240
47.6
16.04
115.5
11.32 A
10.66

0.00
0.00
0.00

1633.86 W
16.23
1650.08 X
230.25
1880.33 Y
280.35

2160.68 Z
21.49
2182.17
218.22
218.2

262.50
0.00
641.66

904.16 W
9.0416
913.20 X
128.30
1041.50 Y
156.23
1197.73 Z
11.98
1209.71
110.88
110.90 110.9

178.20

220.50
110.25
12.90
494.28
494.28
494.3

2470.00

123.58
139.81
5.46

181.86
145.32
479.50
70.00
3615.53 W
36.1553
3651.69 X
513.06
4164.75 Y
624.71
4789.46 Z
47.89
4837.35
4837.35 4417.5
4837.40

0.00
0.00

0.00
4290
0.00
4.85
297.00

156.00
0.00
43.2
1212.41
72.66
269.50
80.86
6426.48 W
64.2648
6490.74 X
911.95
7402.69 Y
1110.40
8513.09 Z
85.13
8598.22
3980.66
3980.70 3920.15

0.00
3315
4.85
297.00
156.00
0.00
43.2

1212.41
72.66
269.50
80.86
5451.48 W
54.5148
5505.99 X
773.59
6279.58 Y
941.94
7221.52 Z
72.22
7293.74
3376.73
3376.70 3316.2

0.00
4620
0.00
381
0.00
156

43.20
0.00
9.8
0.00
2.4
0.00
5.22

738.72
92.84
269.50
80.86
6399.54 W
63.9954
6463.54 X
908.13
7371.67 Y
1105.75
8477.42 Z
84.77
8562.19
3963.97
3964.00 3912.85
0.00
3570
381.00
0.00
156

43.20
0.00
9.8
0.00
2.4
0.00
5.22

738.72
92.84
269.50
80.86
5349.54 W
53.4954
5403.04 X
759.13
6162.17 Y
924.32
7086.49 Z
70.86
7157.35
3313.59
3313.60 3262.45

0.00

0.00
1423.8
2.18
3252.84
0.00
48
0.00
9.8
0.00
28.8
0.00
2.4

121.10
4880.17 W
16.27
4896.45 X
230.93
5127.37 Y
281.18

5408.55 Z
21.56
5430.11
3596.1
3596.1

0.00

280.00
90.00
5.46
3.12

50.80 A

5.46
3.12
437.96 W
3.87
441.83 X
54.94
496.77 Y
66.9

563.67 Z
5.13
568.8
284.4
284.4

0.00

380.00
90.00
5.46
3.12

0.00 A
50.8

5.46
3.12
537.96 W
4.87
542.83 X
69.13
611.96 Y
84.17

696.14 Z
6.45
702.59
351.29
351.3
1688.50

0.00
283.5
3.49

53.82

141.28
80.73
157.50
2408.82 W
24.0882
2432.91 X
341.82
2774.73 Y
416.21
3190.94 Z
31.91
3222.85
105.08
105.10 81.15

18360.00
37.11
282.57
507.50
245.00

26.92 A
53.82
19429.79 W
194.03
19623.82 X
2753.36
22377.19 Y
3352.54

25729.72 Z
257.03
25986.75
86622.51
86622.5

10710.00
37.11

282.57
507.50
245.00

26.92 A
53.82
11779.79 W
117.53
11897.32 X

13565.11 Y
2030.73
15595.84 Z
155.69

52505.1

0.00

4250.00
176.00
7.28

202.07
70.00
4705.35 W
47.0535
4752.40 X
667.71
5420.11 Y
813.02
6233.13 Z
62.33
6295.46
629.55
629.60 627.2

2850.00
176.00
7.28

202.07
70.00
3305.35 W
33.0535
3338.40 X
469.05
3807.45 Y
571.12
4378.57 Z
43.79
4422.36
442.24
442.20 439.9

2500.00
136.00
7.28

202.07
70.00
2915.35 W
29.1535
2944.50 X
413.70
3358.20 Y
503.73
3861.93 Z
38.62
3900.55
390.06
390.10 387.7

0.00

4800.00
176.00
7.28

202.07
70.00
5255.35 W
52.5535
5307.90 X
745.76
6053.66 Y
908.05
6961.71 Z
69.62
7031.33
703.13
703.10 700.8

0.00

4000.00
176.00
7.28

202.07
70.00
4455.35 W
44.5535
4499.90 X
632.24
5132.14 Y
769.82
5901.96 Z
59.02
5960.98
596.1
596.10 593.75

0.00

3900.00
136.00
7.28

202.07
70.00
4315.35 W
43.1535
4358.50 X
612.37
4970.87 Y
745.63
5716.50 Z
57.17
5773.67
577.37
577.40 575.05

0.00

1500.00
60.00
7.28

101.03
1668.31 W
16.6831
1684.99 X
236.74
1921.73 Y
288.26
2209.99 Z
22.10
2232.09
223.21
223.20 222.45

0.00

1300.00
60.00
5.46

85.88
1451.34 W
14.5134
1465.85 X
205.95
1671.80 Y
250.77
1922.57 Z
19.23
1941.80
194.18
194.20 193.5

0.00

900.00
60.00
5.46

85.88
1051.34 W
10.5134
1061.85 X
149.19
1211.04 Y
181.66
1392.70 Z
13.93
1406.63
140.66
140.70 140

1600.00
68.00
5.46

35.36
12.74

1721.56 W
17.2156
1738.78 X
244.30
1983.08 Y
297.46
2280.54 Z
22.81
2303.35
230.33
230.30 230.05

0.00

600.00
1.82

30.31
632.13 W
6.3213
638.45 X
89.70
728.15 Y
109.22
837.37 Z
8.37
845.74
84.57
84.60 84.35

0.00

574.00
1.82

30.31
606.13 W
6.0613
612.19 X
86.01
698.20 Y
104.73
802.93 Z
8.03
810.96
81.1
81.10

0.00

0.00
0.00

0.00
0.00 W
0
0.00 X
0.00
0.00 Y
0.00
0.00 Z
0.00
0.00
0
0.00

0.00

0.00
0.00

0.00

570.12 Z
5.7
575.82
57.58
57.6
0.00

345.00
1.82

30.31
377.13 W
3.7713
380.90 X
53.52
434.42 Y
65.16
499.58 Z
5.00
504.58
50.46
50.50 50.2

168.00
68.00
1.82

40.41
278.23 W
2.7823
281.01 X
39.48
320.49 Y
48.07
368.56 Z
3.69
372.25
37.23
37.20 36.9
360.00
40.00
1.82

50.52
452.34 W
4.5234
456.86 X
64.19
521.05 Y
78.16
599.21 Z
5.99
605.20
60.52
60.50 60.15

1100.00
40.00
1.82

50.52
1918.56 W
19.185634
1937.75 X
272.25
2210.00 Y
331.50
2541.50 Z
25.41
2566.91
256.69
256.70 159.15
2900.00
88.00
20.00
7.68

202.07
70.00
3287.75 W
32.8775
3320.63 X
466.55
3787.18 Y
568.08
4355.26 Z
43.55
4398.81
439.88
439.90 437.55

805.00

300.00
7.28

70.72
35.00
1218.00 W
12.18
1230.18 X
172.84
1403.02 Y
210.45
1613.47 Z
16.13
1629.60
162.96
163.00 162

690.00
0.00
232
7.28

70.72
35.00
1035.00 W
10.35
1045.35 X
146.87
1192.22 Y
178.83
1371.05 Z
13.71
1384.76
138.48
138.50 137.55
0.00

905.00
0.00
144
3.64
70.72
35.00
1158.36 W
11.5836
1169.94 X
164.38
1334.32 Y
200.15
1534.47 Z
15.34
1549.81
154.98
155.00 154.05

0.00

421.00
0.00
144
3.64

70.72
35.00
2534.15 W
25.341536
2559.50 X
359.61
2919.11 Y
437.87
3356.98 Z
33.57
3390.55
339.05
339.10 89.3

0.00

180.00
0.00
64
1.82

40.41
286.23 W
2.8623
289.09 X
40.62
329.71 Y
49.46
379.17 Z
3.79
382.96
38.3
38.30 38

1650.00

0.00
12.74

100.92
1763.66 W
17.6366
1781.30 X
250.27
2031.57 Y
304.73
2336.30 Z
23.36
2359.66
235.97
236.00 235
7676.50
0.00
571.12

7830.14
10850.00
2070.00
28997.76 W
289.9776
29287.74 X
4114.93
33402.67 Y
5010.40
38413.07 Z
384.13
38797.20
191.59
191.60 182.65

0.00
2030

214628.94
5331.14
0.00
0.00
1814.40
0.00
0.00
5520.00
0.00
68850.00
0.00
0.00
0.00
63072.00
144587.54 P

14458.754 Q
144587.29
303633.584

7590.8396
7590.80
7676.5

450.00
251.16
0.00
7.28
708.44 W
7.0844
715.52 X
100.53
816.05 Y
122.41
938.46 Z
9.38
947.84
473.92
473.90 473.9

170.00
251.16
0.00
7.28
428.44 W
4.2844
432.72 X
60.80
493.52 Y
74.03
567.55 Z
5.68
573.23
57.32
57.30 57.3

1875.00

0.00
42.2

488.44
189.00
451.50
30.42
3076.56 W
30.7656
3107.33 X
436.58
3543.91 Y
531.59
4075.50 Z
40.75
4116.25
411.62
411.60 399.75

45.00
23.59

60.00

403.67

350.00

882.26 W
8.8226
891.08 X
125.20
1016.28 Y
152.44
1168.72 Z
11.69
1180.41
0.24
0.20 0.2
350.00
22.40
372.40 W
3.724
376.12 X
52.85
428.97 Y
64.35
493.32 Z
4.93
498.25
49.83
49.80 45.9

690.00
3.00
36000.00

1400.00
403.67
38496.67 W
384.9667
38881.64 X
5462.87
44344.51 Y
6651.68
50996.19 Z
509.96
51506.15
247.63
247.60 246.7
0.00
1190
0.00
3490.63

1795.50
798.00
798.00
285.00

1026.00
3562.50
0.00
4571.83
400.00
87.50

94.50
21.88
18121.34 W
181.2134
18302.55 X
2571.51
20874.06 Y
3131.11
24005.17 Z
240.05
24245.22
42.54
42.50 41.85

0.00
40.37
35.00

70.00
2.20
147.57 W
1.4757
149.05 X
20.94
169.99 Y
25.50
195.49 Z
1.95
197.44
197.44 181.8
197.40

450.00

100.00
300.00

26.72
27.04
-44.00
17.50
70.00

404.14
280.00
1631.40 W
16.314
1647.71 X
231.50
1879.21 Y
281.88
2161.09 Z
21.61
2182.70
2182.7 2110.5
2182.70

1200.00

300.00
0.00
26.72
27.04
-44.00

17.50
43.75

404.14
280.00
2255.15 W
22.5515
2277.70 X
320.02
2597.72 Y
389.66
2987.38 Z
29.87
3017.25
301.73 2947.95
301.70

546.45
210.00
0.00
16.12

0.00
52.36
0.00
41.2
0.00
352.91

32.24
1251.28 W
7.05
1258.33 X
100.02
1358.35 Y
121.78

1480.13 Z
9.34
1489.47
148.95
148.95
43.75
2.00
45.75 W
0.4575
46.21 X
6.49
52.70 Y
7.90
60.60 Z
0.61
61.21
61.21 56.35
61.20

10.50
2.00
12.50 W
0.125
12.63 X
1.77
14.40 Y
2.16
16.56 Z
0.17
16.73
1.67
1.70 1.55

20.00
20.00 W
0.2
20.20 X
2.84
23.04 Y
3.46
26.50 Z
0.27
26.77
2.68
2.70 2.7

14.40

72.66
63.00
150.06 W
1.5006
151.56 X
21.29
172.85 Y
25.93
198.78 Z
1.99
200.77
91.26
91.30 171.45

5280.00

540.00

5724.00
12.74
15.60
76.56
2.11
269.10

871.93
1134.00
90.93
13.52
14030.49 W
140.3049
14170.79 X
1991.00
16161.79 Y
2424.27
18586.06 Z
185.86
18771.92
625.73
625.70 526.95

3300.00

540.00

3816.00

8.91
15.60
76.56
2.11
269.10
637.80
829.50
65.67
13.52
9574.77 W
95.7477
9670.52 X
1358.71
11029.23 Y
1654.38
12683.61 Z
126.84
12810.45
427.01
427.00 360.7

6600.00
0.00
540

5724.00

0.00
12.74
15.60
76.56
2.11
269.10

871.93
1134.00
90.93
13.52
15350.49 W
153.5049
15503.99 X
2178.31
17682.30 Y
2652.35
20334.65 Z
203.35
20538.00
684.6
684.60 585.85

0.00

4180.11
0.00
960
1.27
15.60
574.00
99.06

871.93
90.93
1134.00
46.80
7973.70 W
79.737
8053.44 X
1131.51
9184.95 Y
1377.74
10562.69 Z
105.63
10668.32
355.61
355.60 348.35
0.00

6270.00
0.00
960
1.27
15.60
574.00
99.06

871.93
90.93
1134.00
46.80
10063.59 W
100.6359
10164.23 X
1428.07
11592.30 Y
1738.84
13331.14 Z
133.31
13464.45
448.81
448.80 441.55

0.00

6765.00
0.00
960
1.27
15.60
574.00
99.06

871.93
90.93
1134.00
46.80
10558.59 W
105.5859
10664.18 X
1498.32
12162.50 Y
1824.37
13986.87 Z
139.87
14126.74
470.89
470.90 463.65

1417.50
15.60

173.58
0.00
19.04

227.50

93.60
1946.82 W
19.4682
1966.29 X
276.26
2242.55 Y
336.38
2578.93 Z
25.79
2604.72
86.82
86.80 85.4

359.33
20.00
379.33 W
3.7933
383.12 X
53.83
436.95 Y
65.54
502.49 Z 436.25

403.67
20.00
423.67 W
4.2367
427.91 X
60.12
453.7
154.00
129.50
2.08
285.58 W
2.8558
288.44 X
40.53
328.97 Y
49.34
378.31 Z
3.78
382.09
382.09 350.5
382.10

556.50
252.00
9.62
818.12 W
8.1812
826.30 X
116.10
942.40 Y
141.36
1083.76 Z
10.84
1094.60
1094.6
1094.60 1004.45
308.00
192.50
3.90
504.40 W
5.044
509.44 X
71.58
581.02 Y
87.15
668.17 Z
6.68
674.85
674.85 619.05
674.90

927.50
252.00
14.04
1193.54 W
11.9354
1205.48 X
169.37
1374.85 Y
206.23
1581.08 Z
15.81
1596.89
1596.89
1596.90 1465.35
742.00
315.00
9.36
1066.36 W
10.6636
1077.02 X
151.32
1228.34 Y
184.25
1412.59 Z
14.13
1426.72
1426.72 1308.85
1426.70

201.84
175.00
26.78
403.62 W
4.0362
407.66 X
57.28
464.94 Y
69.74
534.68 Z
5.35
540.03
540.03 501
540.00
500.98
100.92
175.00
26.78
302.70 W
3.027
305.73 X
42.95
348.68 Y
52.30
400.98 Z
4.01
404.99
4.27
4.30 3.95

105.00
129.50
2.08
236.58 W
2.3658
238.95 X
33.57
272.52 Y
40.88
313.40 Z
3.13
316.53
316.53 290.4
316.50
434.00
161.00
2.08
597.08 W
5.9708
603.05 X
84.73
687.78 Y
103.17
790.95 Z
7.91
798.86
798.86 732.5
798.90

154.00
129.50
2.08
285.58 W
2.8558
288.44 X
40.53
328.97 Y
49.34
378.31 Z
3.78
382.09
382.09
382.10 350.5

371.00
315.00
4.94
690.94 W
6.9094
697.85 X
98.05
795.90 Y
119.38
915.28 Z
9.15
924.43
924.43 847.95
924.40

0.00

840.00
560.00
161.47
3.64
1565.11 W
15.6511
1580.76 X
222.10
1802.86 Y
270.43
2073.29 Z
20.73
2094.02
2094.02 1922.3
2094.00

980.00
490.00
322.94
17.94
1810.88 W
18.1088
1828.99 X
256.97
2085.96 Y
312.89
2398.85 Z
23.99
2422.84
2422.84
2422.80 2227.7

1225.00
525.00
500.55
16.12
2266.67 W
22.6667
2289.34 X
321.65
2610.99 Y
391.65
3002.64 Z
30.03
3032.67
3032.67
3032.70 2789.15

213.50
171.50
3.90
388.90 W
3.889
392.79 X
55.19
447.98 Y
67.20
515.18 Z
5.15
520.33
520.33 477.4
520.30

455.00
364.00
5.46
824.46 W
8.2446
832.70 X
116.99
949.69 Y
142.45
1092.14 Z
10.92
1103.06
1103.06
1103.10 1011.75

273.00
213.50
5.46
491.96 W
4.9196
496.88 X
69.81
566.69 Y
85.00
651.69 Z
6.52
658.21
658.21 603.95
658.20

542.50
416.50
5.46
964.46 W
9.6446
974.10 X
136.86
1110.96 Y
166.64
1277.60 Z
12.78
1290.38
1290.38
1290.40 1183.45

0.00

20.18
70.00
70.00
1.04
161.22 W
1.6122
162.83 X
22.88
185.71 Y
27.86
213.57 Z
2.14
215.71
215.71 198.15
215.70

20.18
140.00
70.00
1.82
1308.41 W
13.084066
1321.49 X
185.67
1507.16 Y
226.07
1733.23 Z
17.33
1750.56
1750.56
1750.60 285.05

40.37
63.00
20.18
2.86
126.41 W
1.2641
127.67 X
17.94
145.61 Y
21.84
167.45 Z
1.67
169.12
167.45 156.25
167.50

52.48
87.50
28.26
5.46
173.70 W
1.737
175.44 X
24.65
200.09 Y
30.01
230.10 Z
2.30
232.40
232.4
232.40 214.85

20.18
28.00
1.04
49.22 W
0.4922
49.71 X
6.98
56.69 Y
8.50
65.19 Z
0.65
65.84
65.84 60.8
65.80

28.26
35.00
1.82
65.08 W
0.6508
65.73 X
9.24
74.97 Y
11.25
86.22 Z
0.86
87.08
87.08
87.10 80.45

807.34
700.00
26.78
1534.12 W
15.3412
1549.46 X
217.70
1767.16 Y
265.07
2032.23 Z
20.32
2052.55
2052.55 1896.45
2052.60

32.29
28.00
1.04
61.33 W
0.6133
61.94 X
8.70
70.64 Y
10.60
81.24 Z
0.81
82.05
8.21 7.6
8.20

80.73
105.00
26.78
212.51 W
2.1251
214.64 X
30.16
244.80 Y
36.72
281.52 Z
2.82
284.34
284.34 264.8
284.30

2.42
2.80
0.78
6.00 W
0.06
6.06 X
0.85
6.91 Y
1.04
7.95 Z
0.08
8.03
0.80 0.75
0.80

100.92
175.00
26.78
302.70 W
3.027
305.73 X
42.95
348.68 Y
52.30
400.98 Z
4.01
404.99
404.99 375.7
405.00

4.04
7.00
0.78
11.82 W
0.1182
11.94 X
1.68
13.62 Y
2.04
15.66 Z
0.16
15.82
1.58 1.45
1.60

20.18
35.00
52.50
5.46
113.14 W
1.1314
114.27 X
16.06
130.33 Y
19.55
149.88 Z
1.50
151.38
1.51
1.50 1.4
20.18
17.50
35.00
5.46
78.14 W
0.7814
78.92 X
11.09
90.01 Y
13.50
103.51 Z
1.04
104.55
1.05
1.10 0.95

60.55
35.00
87.50
8.32
191.37 W
1.9137
193.28 X
27.16
220.44 Y
33.07
253.51 Z
2.54
256.05
2.56
2.60 2.35
35.00
87.50
5.46
127.96 W
1.2796
129.24 X
18.16
147.40 Y
22.11
169.51 Z
1.70
171.21
1.71
1.70 1.6

7.00
21.00
0.78
28.78 W
0.2878
29.07 X
4.08
33.15 Y
4.97
38.12 Z
0.38
38.50
0.38
0.40 0.35

7.00
21.00
0.78
28.78 W
0.2878
29.07 X
4.08
33.15 Y
4.97
38.12 Z
0.38
38.50
0.38
0.40 0.35

101.03
70.00
171.03 W
1.7103
172.74 X
24.27
197.01 Y
29.55
226.56 Z
2.27
228.83
2.29
2.30 2.15

121.10
42.00
84.00
5.46
252.56 W
2.5256
255.09 X
35.84
290.93 Y
43.64
334.57 Z
3.35
337.92
33.79
33.80 31.2

238.17
63.00
84.00
5.46
390.63 W
3.9063
394.54 X
55.43
449.97 Y
67.49
517.46 Z
5.17
522.63
52.26
52.30 48.3

87.50
350.00
5.46
442.96 W
4.4296
447.39 X
62.86
510.25 Y
76.54
586.79 Z
5.87
592.66
592.66 543.85
592.70

619.50
262.50
16.12
898.12 W
8.9812
907.10 X
127.45
1034.55 Y
155.18
1189.73 Z
11.90
1201.63
120.16
120.20 110.35

217.98
56.00
84.00
4.94
362.92 W
3.6292
366.55 X
51.50
418.05 Y
62.71
480.76 Z
4.81
485.57
48.56
48.60 44.9
87.50
217.00
2.08
306.58 W
3.0658
309.65 X
43.51
353.16 Y
52.97
406.13 Z
4.06
410.19
410.19 376.25
410.20

201.84
350.00
13.52
565.36 W
5.6536
571.01 X
80.23
651.24 Y
97.69
748.93 Z
7.49
756.42
75.64
75.60 69.8

80.73
175.00
10.66
266.39 W
2.6639
269.05 X
37.80
306.85 Y
46.03
352.88 Z
3.53
356.41
35.64
35.60 32.9

619.50
262.50
16.12
898.12 W
8.9812
907.10 X
127.45
1034.55 Y
155.18
1189.73 Z
11.90
1201.63
1201.63
1201.60 1103.3

416.50
423.50
16.12
4460.98 W
44.609812
4505.59 X
633.04
5138.63 Y
770.79
5909.42 Z
59.09
5968.51
596.85
596.90 105.2

605.50
87.50
16.12
709.12 W
7.0912
716.21 X
100.63
816.84 Y
122.53
939.37 Z
9.39
948.76
94.88
94.90 87.15

189.00
7.28
196.28 W
1.9628
198.24 X
27.85
226.09 Y
33.91
260.00 Z
2.60
262.60
26.26
26.30 24.15
175.00
175.00
1.04
351.04 W
3.5104
354.55 X
49.81
404.36 Y
60.65
465.01 Z
4.65
469.66
9.39
9.40 8.6

37.45
23.45
0.52

26.78

2.86
91.06 W
0.9106
91.97 X
12.92
104.89 Y
15.73
120.62 Z
1.21
121.83
121.83
121.80 115.05

33.95
21.00
0.52
26.78

16.12

5.46
103.83 W
1.0383
104.87 X
14.73
119.60 Y
17.94
137.54 Z
1.38
138.92
138.92 132.8
138.90

5.46
2.86
8.32 W
0.0832
8.40 X
1.18
9.58 Y
1.44
11.02 Z
0.11
11.13
11.13
11.10 11.15

1225.00
10.66
1235.66 W
12.3566
1248.02 X
175.35
1423.37 Y
213.50
1636.87 Z
16.37
1653.24
16.53
16.50 15.15

40.37
87.50
87.50
5.46
220.83 W
2.2083
223.04 X
31.34
254.38 Y
38.16
292.54 Z
2.93
295.47
29.55
29.60 27.2

40.37
140.00
70.00
8.32
258.69 W
2.5869
261.28 X
36.71
297.99 Y
44.70
342.69 Z
3.43
346.12
34.61
34.60 31.9

60.55
70.00
70.00
10.66
211.21 W
2.1121
213.32 X
29.97
243.29 Y
36.49
279.78 Z
2.80
282.58
28.26
28.30 26.1

80.73
87.50
87.50
13.52
269.25 W
2.6925
271.94 X
38.21
310.15 Y
46.52
356.67 Z
3.57
360.24
36.02
36.00 33.3

80.73
105.00
105.00
26.78
317.51 W
3.1751
320.69 X
45.06
365.75 Y
54.86
420.61 Z
4.21
424.82
42.48 39.35
42.50

80.73
700.00
175.00
26.78
982.51 W
9.8251
992.34 X
139.42
1131.76 Y
169.76
1301.52 Z
13.02
1314.54
131.45
131.50 120.9
121.10
1050.00
262.50
37.70
1471.30 W
14.713
1486.01 X
208.78
1694.79 Y
254.22
1949.01 Z
19.49
1968.50
196.85
196.90 181.05

80.73
105.00
10.66
196.39 W
1.9639
198.35 X
27.87
226.22 Y
33.93
260.15 Z
2.60
262.75
26.28
26.30 24.3
126.00
126.00
1.82
253.82 W
2.5382
256.36 X
36.02
292.38 Y
43.86
336.24 Z
3.36
339.60
33.96
34.00 31.15

126.00
133.00
3.12
262.12 W
2.6212
264.74 X
37.20
301.94 Y
45.29
347.23 Z
3.47
350.70
35.07
35.10 32.2

126.00
140.00
4.16
270.16 W
2.7016
272.86 X
38.34
311.20 Y
46.68
357.88 Z
3.58
361.46
36.15
36.20 33.2

1680.00
840.00
179.40

2699.40 W
26.994
2726.39 X
383.06
3109.45 Y
466.42
3575.87 Z
35.76
3611.63
100.32
100.30 92.5

3360.00
1680.00
215.28

5255.28 W
52.5528
5307.83 X
745.75
6053.58 Y
908.04
6961.62 Z
69.62
7031.24
195.31
195.30 179.7

231.00
231.00
71.76
533.76 W
5.3376
539.10 X
75.74
614.84 Y
92.23
707.07 Z
7.07
714.14
71.41
71.40 66.25

231.00
231.00
143.52
605.52 W
6.0552
611.58 X
85.93
697.51 Y
104.63
802.14 Z
8.02
810.16
81.02
81.00 75.85

2926.77 A

2013.17

230.00
19.00
254.31
1575.00
107.64
7125.89 W
71.2589
7197.15 X
1011.20
8208.35 Y
1231.25
9439.60 Z
94.40
9534.00
236.81
236.80 186.5
3124.06 A

2148.87 A

515.00
57.00
524.77
2625.00
161.46
9156.16 W
91.5616
9247.72 X
1299.30
10547.02 Y
1582.05
12129.07 Z
121.29
12250.36
122.50
304.28 247.4
304.30

3326.78 A

2288.31 A
700.00
113.50
908.26
4025.00
269.10
11630.95 W
116.3095
11747.26 X
1650.49
13397.75 Y
2009.66
15407.41 Z
154.07
15561.48
155.61
386.52 321.7
386.50

1862.00
1911.00
108.50
700.00
113.50
908.26
4025.00
269.10
9897.36 W
98.9736
9996.33 X
1404.48
11400.81 Y
1710.12
13110.93 Z
131.11
13242.04
328.91
328.90 304.85

5537.00
5687.50
325.50
1540.00
250.00
4036.70
7000.00
358.80
24735.50 W
247.355
24982.86 X
3510.09
28492.95 Y
4273.94
32766.89 Z
327.67
33094.56
822.02
822.00 760.95

406.00
416.50
24.50
126.00
133.00
3.12
1109.12 W
11.0912
1120.21 X
157.39
1277.60 Y
191.64
1469.24 Z
14.69
1483.93
148.39 136.05
148.40

434.00
448.00
24.50
126.00
308.00
7.54
1348.04 W
13.4804
1361.52 X
191.29
1552.81 Y
232.92
1785.73 Z
17.86
1803.59
180.36 165.4
180.40
175.00
49.00
2.60

14.30
240.90 W
2.409
243.31 X
34.18
277.49 Y
41.62
319.11 Z
3.19
322.30
322.3 297.35
322.30

101.50
28.00
1.30

10.66
141.46 W
1.4146
142.87 X
20.07
162.94 Y
24.44
187.38 Z
1.87
189.25
189.25 174.8
189.30

283.50
178.50
3.64
56.00
24.50
1.04
126.29
60.62
48.44
350.00
350.00
107.64
1590.17 W
15.9017
1606.07 X
225.65
1831.72 Y
274.76
2106.48 Z
21.06
2127.54
2127.54 1969.9
2127.50

49.00
31.50
0.52
87.50
77.00
1.04
45.50
21.00
0.78
14.30
328.14 W
3.2814
331.42 X
46.56
377.98 Y
56.70
434.68 Z
4.35
439.03
439.03 404.3
439.00
126.29
175.00
35.88
337.17 W
3.3717
340.54 X
47.85
388.39 Y
58.26
446.65 Z
4.47
451.12
451.12 421.85
451.10

303.10
161.47
560.00
179.40

1203.97 W
12.0397
1216.01 X
170.85
1386.86 Y
208.03
1594.89 Z
15.95
1610.84
161.08
161.10 150.95

1212.41
621.65
2240.00
179.40

4253.46 W
42.5346
4295.99 X
603.59
4899.58 Y
734.94
5634.52 Z
56.35
5690.87
569.09
569.10 528.75

757.76
403.67
1400.00
2561.43 W
25.6143
2587.04 X
363.48
2950.52 Y
442.58
3393.10 Z
33.93
3427.03
342.7
342.70 317.35

66.50
42.00
0.78
122.50
105.00
1.82
21.00
10.50
0.26
370.36 W
3.7036
374.06 X
52.56
426.62 Y
63.99
490.61 Z
4.91
495.52
495.52
495.50 454.55

108.50
66.50
1.30
175.00
147.00
2.60
45.50
21.00
0.78
568.18 W
5.6818
573.86 X
80.63
654.49 Y
98.17
752.66 Z
7.53
760.19
760.19
760.20 697.35
154.00
98.00
1.82
241.50
206.50
3.12
66.50
31.50
1.04
803.98 W
8.0398
812.02 X
114.09
926.11 Y
138.92
1065.03 Z
10.65
1075.68
1075.68 986.7
1075.70

126.00
28.00
24.50
2.86
181.36 W
1.8136
183.17 X
25.74
208.91 Y
31.34
240.25 Z
2.40
242.65
24.27
24.30 22.25

80.73
105.00
10.76
196.49 W
1.9649
198.45 X
27.88
226.33 Y
33.95
260.28 Z
2.60
262.88
26.29
26.30 24.35

10.50

175.00
175.00

201.84
175.00

200.00

67.50
100.00
1104.84 W
11.0484
1115.89 X
156.78
1272.67 Y
190.90
1463.57 Z
14.64
1478.21
1478.21 1398.95
1478.20

3.50
105.00

64.13
2.40
175.03 W
1.7503
176.78 X
24.84
201.62 Y
30.24
231.86 Z
2.32
234.18
234.18 222.05
234.20

106.13
106.13 W
1.0613
107.19 X
15.06
122.25 Y
18.34
140.59 Z
1.41
142.00
142
142.00 142
SUB HEAD : 3.0

MORTAR

Code Description Unit Quantity


1 3.1 Cement mortar 1:1 (1 cement : 1 fine sand)
2
3 Details of cost for 1 cum
4 MATERIAL
5 (0.7175 cum. of cement = 1.02 tonne) Cement
6 required for cement mortar is 71.25%
7 367 Portland Cement tonne 1.02
8 2209 Carriage of Cement tonne 1.02
9 983 Fine sand cum 0.7125
10 2261 Carriage of Fine sand (1 part Fine sand : 2 cum 0.7125
11 parts Sand)
12 LABOUR
13 For measuring, carrying, depositing and mixing-
14 17 Beldar day 0.75
15 11 Bhisti day 0.07
16 9999 Hire and running charges of mechanical mixer L.S. 26.9
17 9999 Sundries L.S. 13.52
18 Cost of 1.00 cum
19 Say
20
21 3.2 Cement mortar 1:2 (1 cement : 2 fine sand).
22
23 Details of cost for 1 cum
24
25 MATERIAL
26
27 (0.475 cum. of cement = 0.68 tonne) Cement
28
29 required for cement mortar is 47.50%
30 367 Portland Cement tonne 0.68
31 2209 Carriage of Cement tonne 0.68
32 983 Fine sand cum 0.95
33 2261 Carriage of Fine sand (1 part Fine sand : 2 cum 0.95
34 parts Sand)
35 LABOUR
36 For measuring, carrying, depositing and mixing-
37 17 Beldar day 0.75
38 11 Bhisti day 0.07
39 9999 Hire and running charges of mechanical mixer L.S. 26.91
40 9999 Sundries L.S. 13.52
41 Cost of 1.00 cum
42 Say
43
44 3.3 Cement mortar 1:3 (1 cement : 3 fine sand).
45
46 Details of cost for 1 cum
47
48 MATERIAL
49
50 (0.357 cum. of cement = 0.51 tonne) Cement
51
52 required for cement mortar is 35.70%
53 367 Portland Cement tonne 0.51
54 2209 Carriage of Cement tonne 0.51
55 983 Fine sand cum 1.07
56 2261 Carriage of Fine sand (1 part Fine sand : 2 cum 1.07
57 parts Sand)
58 LABOUR
59 For measuring, carrying, depositing and mixing-
60 17 Beldar day 0.75
61 11 Bhisti day 0.07
62 9999 Hire and running charges of mechanical mixer L.S. 26.91
63 9999 Sundries L.S. 13.52
64 Cost of 1.00 cum
65 Say
66
67 3.4 Cement mortar 1:4 (1 cement : 4 fine sand).
68
69 Details of cost for 1 cum
70
71 MATERIAL
72
73 (0.268 cum. of cement = 0.38 tonne) Cement
74
75 required for cement mortar is 26.80%
76 367 Portland Cement tonne 0.38
77 2209 Carriage of Cement tonne 0.38
78 983 Fine sand cum 1.07
79 2261 Carriage of Fine sand (1 part Fine sand : 2 cum 1.07
80 parts Sand)
81 LABOUR
82 For measuring, carrying, depositing and mixing-
83 17 Beldar day 0.75
84 11 Bhisti day 0.07
85 9999 Hire and running charges of mechanical mixer L.S. 26.91
86 9999 Sundries L.S. 13.52
87 Cost of 1.00 cum
88 Say
89
90 3.5 Cement mortar 1:5 (1 cement : 5 fine sand).
91
92 Details of cost for 1 cum
93 MATERIAL
94 (0.214 cum. of cement = 0.31 tonne) Cement
95 required for cement mortar is 21.40%
96 367 Portland Cement tonne 0.31
97 2209 Carriage of Cement tonne 0.31
98 983 Fine sand cum 1.07
99 2261 Carriage of Fine sand (1 part Fine sand : cum 1.07
100 2 parts Sand)
101 LABOUR
102 For measuring, carrying, depositing and mixing-
103 17 Beldar day 0.75
104 11 Bhisti day 0.07
105 9999 Hire and running charges of mechanical mixer L.S. 26.91
106 9999 Sundries L.S. 13.52
107 Cost of 1.00 cum
108 Say
109
110 3.6 Cement mortar 1:6 (1 cement : 6 fine sand).
111
112 Details of cost for 1 cum
113
114 MATERIAL
115
116 (0.178 cum. of cement = 0.25 tonne) Cement
117
118 required for cement mortar is 17.80%
119 367 Portland Cement tonne 0.25
120 2209 Carriage of Cement tonne 0.25
121 983 Fine sand cum 1.07
122 2261 Carriage of Fine sand (1 part Fine sand : 2 cum 1.07
123 parts Sand)
124 LABOUR
125 For measuring, carrying, depositing and mixing-
126 17 Beldar day 0.75
127 11 Bhisti day 0.07
128 9999 Hire and running charges of mechanical mixer L.S. 26.91
129 9999 Sundries L.S. 13.52
130 Cost of 1.00 cum
131 Say
132
133 3.7 Cement mortar 1:2 (1 cement : 2 coarse sand).
134
135 Details of cost for 1 cum
136
137 MATERIAL
138
139 (0.476 cum. of cement = 0.68 tonne) Cement
140
141 required for cement mortar is 47.50%
142 367 Portland Cement tonne 0.68
143 2209 Carriage of Cement tonne 0.68
144 982 Coarse sand cum 0.95
145 2203 Carriage of Coarse sand cum 0.95
146 LABOUR
147 For measuring, carrying, depositing and mixing-
148 17 Beldar day 0.75
149 11 Bhisti day 0.07
150 9999 Hire and running charges of mechanical mixer L.S. 26.91
151 9999 Sundries L.S. 13.52
152 Cost of 1.00 cum
153 Say
154
155 3.8 Cement mortar 1:3 (1 cement : 3 coarse sand).
156
157 Details of cost for 1 cum
158
159 MATERIAL
160
161 (0.357 cum. of cement = 0.51 tonne) Cement
162
163 required for cement mortar is 35.70%
164 367 Portland Cement tonne 0.51
165 2209 Carriage of Cement tonne 0.51
166 982 Coarse sand cum 1.07
167 2203 Carriage of Coarse sand cum 1.07
168 LABOUR
169 For measuring, carrying, depositing and mixing-
170 17 Beldar day 0.75
171 11 Bhisti day 0.07
172 9999 Hire and running charges of mechanical mixer L.S. 26.91
173 9999 Sundries L.S. 13.52
174 Cost of 1.00 cum
175 Say
176
177
178 3.9 Cement mortar 1:4 (1 cement : 4 coarse sand).
179 Details of cost for 1 cum
180
181 MATERIAL
182
183 (0.268 cum. of cement = 0.38 tonne) Cement
184
185 required for cement mortar is 26.80%
186 367 Portland Cement tonne 0.38
187 2209 Carriage of Cement tonne 0.38
188 982 Coarse sand cum 1.07
189 2203 Carriage of Coarse sand cum 1.07
190 LABOUR
191 For measuring, carrying, depositing and mixing-
192 17 Beldar day 0.75
193 11 Bhisti day 0.07
194 9999 Hire and running charges of mechanical mixer L.S. 26.91
195 9999 Sundries L.S. 13.52
196 Cost of 1.00 cum
197 Say
198
199 3.10 Cement mortar 1:5 (1 cement : 5 coarse sand).
200
201 Details of cost for 1 cum
202
203 MATERIAL
204
205 (0.214 cum. of cement = 0.31 tonne) Cement
206
207 required for cement mortar is 21.40%
208 367 Portland Cement tonne 0.31
209 2209 Carriage of Cement tonne 0.31
210 982 Coarse sand cum 1.07
211 2203 Carriage of Coarse sand cum 1.07
212 LABOUR
213 For measuring, carrying, depositing and mixing-
214 17 Beldar day 0.75
215 11 Bhisti day 0.07
216 9999 Hire and running charges of mechanical mixer L.S. 26.91
217 9999 Sundries L.S. 13.52
218 TOTAL
219 Say
220
221 3.11 Cement mortar 1:6 (1 cement : 6 coarse sand).
222
223 Details of cost for 1 cum
224
225 MATERIAL
226
227 (0.178 cum. of cement = 0.25 tonne) Cement
228 367 required
Portland for cement mortar is 17.80%
Cement tonne 0.25
229 2209 Carriage of Cement tonne 0.25
230 982 Coarse sand cum 1.07
231 2203 Carriage of Coarse sand cum 1.07
232 LABOUR
233 For measuring, carrying, depositing and mixing-
234 17 Beldar day 0.75
235 11 Bhisti day 0.07
236 9999 Hire and running charges of mechanical mixer L.S. 26.91
237 9999 Sundries L.S. 13.52
238 Cost of 1.00 cum
239 Say
240
241 3.12 Cement mortar 1:2 (1 cement : 2 stone dust).
242
243 Details of cost for 1 cum
244
245 MATERIAL
246
247 (0.475 cum. of cement = 0.68 tonne) Cement
248
249 required for cement mortar is 47.50%
250 367 Portland Cement tonne 0.68
251 2209 Carriage of Cement tonne 0.68
252 1159 Stone dust cum 0.95
253 2267 Carriage of Stone dust cum 0.95
254 LABOUR
255 For measuring, carrying, depositing and mixing-
256 17 Beldar day 0.75
257 11 Bhisti day 0.07
258 9999 Hire and running charges of mechanical mixer L.S. 26.91
259 9999 Sundries L.S. 13.52
260 Cost of 1.00 cum
261 Say
262 3.13 Cement mortar 1:2 (1 cement : 2 marble dust).
263
264 Details of cost for 1 cum
265
266 MATERIAL
267 (0.475 cum of cement = 0.68 tonne) Cement
268 required for cement mortar is 47.50%
269 367 Portland Cement tonne 0.68
270 2209 Carriage of Cement tonne 0.68
271 784 Marble dust/ powder cum 0.95
272 2268 Carriage of Marble dust and marble chips cum 0.95
273 LABOUR
274 For measuring, carrying, depositing and mixing
275 17 Beldar day 0.75
276 11 Bhisti day 0.07
277 9999 Hire and running charges of mechanical mixer L.S. 26.91
278 9999 Sundries L.S. 13.52
279 Cost of 1.00 cum
280 Say
281
282 3.14 Cement mortar 1:5 (1 cement : 5 marble dust).
283
284 Details of cost for 1 cum
285
286 MATERIAL
287
288 (0.214 cum. of cement = 0.31 tonne) Cement
289
290 required for cement mortar is 21.40%
291 367 Portland Cement tonne 0.31
292 2209 Carriage of Cement tonne 0.31
293 784 Marble dust/ powder cum 1.07
294 2268 Carriage of Marble dust and marble chips cum 1.07
295 LABOUR
296 For measuring, carrying, depositing and mixing-
297 17 Beldar day 0.75
298 11 Bhisti day 0.07
299 9999 Hire and running charges of mechanical mixer L.S. 26.91
300 9999 Sundries L.S. 13.52
301 Cost of 1.00 cum
302 Say
303
304 3.15 White cement mortar 1:2 (1 white cement : 2
305 marble dust).
306 Details of cost for 1 cum
307
308 MATERIAL
309
310 (0.475 cum. of white cement = 0.68 tonne) Cement
311 368 required for cement mortar is 47.50%
White Cement tonne 0.68
312 2209 Carriage of Cement tonne 0.68
313 784 Marble dust/ powder cum 0.95
314 2268 Carriage of Marble dust and marble chips cum 0.95
315 LABOUR
316 For measuring, carrying, depositing and mixing-
317 17 Beldar day 0.75
318 11 Bhisti day 0.07
319 9999 Hire and running charges of mechanical mixer L.S. 26.91
320 9999 Sundries L.S. 13.52
321 Cost of 1.00 cum
322 Say
323
324 3.16 White cement mortar 1:3 (1 white cement : 3
325 marble dust).
326 Details of cost for 1 cum
327
328 MATERIAL
329
330 (0.357 cum. of white cement = 0.51 tonne) Cement
331 required for cement mortar is 35.70%
332 368 White Cement tonne 0.51
333 2209 Carriage of Cement tonne 0.51
334 784 Marble dust/ powder cum 1.07
335 2268 Carriage of Marble dust and marble chips cum 1.07
336 LABOUR
337 For measuring, carrying, depositing and mixing-
338 17 Beldar day 0.75
339 11 Bhisti day 0.07
340 9999 Hire and running charges of mechanical mixer L.S. 26.91
341 9999 Sundries L.S. 13.52
342 Cost of 1.00 cum
343 Say
344
345 3.17 White cement mortar 1:5 (1 white cement : 5
346 marble dust).
347 Details of cost for 1 cum
348
349 MATERIAL
350
351 (0.214 cum. of white cement = 0.31 tonne)
352 Cement required for cement mortar is 21.40%
353 368 White Cement tonne 0.31
354 2209 Carriage of Cement tonne 0.31
355 784 Marble dust/ powder cum 1.07
356 2268 Carriage of Marble dust and marble chips cum 1.07
357 LABOUR
358 For measuring, carrying, depositing and mixing-
359 17 Beldar day 0.75
360 11 Bhisti day 0.07
361 9999 Hire and running charges of mechanical mixer L.S. 26.91
362 9999 Sundries L.S. 13.52
363 Cost of 1.00 cum
364 Say
365
366 3.18 Mud mortar
367
368 Detail of cost for one cum
369
370 MATERIAL
371 811 Mud (dry) cum 1.08
372 LABOUR
373 17 Beldar day 0.63
374 11 Bhisti day 0.315
375 9999 Sundries L.S. 6.45
376 TOTAL
377 Cost of one cum
378 Say
379
380 3.19 Mortar in lime, surkhi (50% red and 50%
381 light yellow) and marble dust 1:1.5:0.5

382 Details of cost for 1 cum


383
384 MATERIAL
385
386 (0.475 cum of lime putty) = 3.01 q of
387 unslaked lime
388 1182 Surkhi cum 0.7125
389 773 Unslaked lime quintal 3.01
390 784 Marble dust/ powder cum 0.24
391 2268 Marble dust and/or marble chips cum 0.24
392 2208 Carriage of Lime cum 3.01
393 LABOUR
394 For slaking lime, making lime putty, grinding
395 and carrying
396 17 Beldar day 0.9
397 11 Bhisti day 0.45
398 9999 As cost for running and upkeep of mortar mill L.S. 10.35
399 9999 Sundries L.S. 5.2
400
401 Cost of 1.00 cum
402 Say
132
Rate Amount

4375 4462.5
94.34 96.23
850 605.63
106.13 75.62

350.00 262.5
350.00 24.5
2 53.8
2 27.04
5607.82
5607.8 6195.8

4375 2975
94.34 64.15
850 807.5
106.13 100.82

350.00 262.5
350.00 24.5
2 53.82
2 27.04
4315.33
4315.3
4375 2231.25
94.34 48.11
850 909.5
106.13 113.56

350.00 262.5
350.00 24.5
2 53.82
2 27.04
3670.28
3670.3 3988

4375 1662.5
94.34 35.85
850 909.5
106.13 113.56

350.00 262.5
350.00 24.5
2 53.82
2 27.04
3089.27
3089.3 3333.55

4375 1356.25
94.34 29.25
850 909.5
106.13 113.56
350.00 262.5
350.00 24.5
2 53.82
2 27.04
2776.42
2776.4 2981.15

4375 1093.75
94.34 23.59
850 909.5
106.13 113.56

350.00 262.5
350.00 24.5
2 53.82
2 27.04
2508.26
2508.3 2679.1

4375 2975
94.34 64.15
800 760
584.88 555.64

350.00 262.5
350.00 24.5
2 53.82
2 27.04
4722.65
4722.70 5150.6
4375 2231.25
94.34 48.11
800 856
584.88 625.82

350.00 262.5
350.00 24.5
2 53.82
2 27.04
4129.04
4129.00 4469.5

4375 1662.5
94.34 35.85
800 856
584.88 625.82

350.00 262.5
350.00 24.5
2 53.82
2 27.04
3548.03
3548.00 3815.05
4375 1356.25
94.34 29.25
800 856
584.88 625.82

350.00 262.5
350.00 24.5
2 53.82
2 27.04
3235.18
3235.20 3462.65

4375 1093.75
94.34 23.59
800 856
584.88 625.82

350.00 262.5
350.00 24.5
2 53.82
2 27.04
2967.02
2967.00 3160.6

4375 2975
94.34 64.15
1100 1045
106.13 100.82

350.00 262.5
350.00 24.5
2 53.82
2 27.04
4552.83
4552.80 4913.1

4375 2975
94.34 64.15
1130 1073.5
106.13 100.82

350.00 262.5
350.00 24.5
2 53.82
2 27.04
4581.33
4581.30 4941.6

4375 1356.25
94.34 29.25
1130 1209.1
106.13 113.56

350.00 262.5
350.00 24.5
2 53.82
2 27.04
3076.02
3076.00 3227.25

11200 7616
94.34 64.15
1130 1073.5
106.13 100.82

350.00 262.5
350.00 24.5
2 53.82
2 27.04
9222.33
9222.30 9198.4

11200 5712
94.34 48.11
1130 1209.1
106.13 113.56

350.00 262.5
350.00 24.5
2 53.82
2 27.04
7450.63
7450.60 7426.7

11200 3472
94.34 29.25
1130 1209.1
106.13 113.56

350.00 262.5
350.00 24.5
2 53.82
2 27.04
5191.77
5191.80 5167.85
165 178.2

350.00 220.5
350.00 110.25
2 12.9
521.85
521.90
494.3

700 498.75
300 903
1130 271.2
106.13 25.47
106.13 319.45

350.00 315
350.00 157.5
2 20.7
2 10.4

2521.47
2521.50 2482.1
(Carriage for 5.0 km lead by Mechanical Transport including loading, Unlo

Code No. Description Unit Lead Up to 5.00 KM Beyong 5 km upto 10 km per Km.

Lead Rate Amount Lead Rate i/c Basic


cp/oh Rate

2200 Carriage of Steam coal tonne 5.00 5.00 121.29 121.29 0.00 11.51 10.01
5.00 5.00 283.01 0.00
2201 Carriage of Bricks 1000 Nos 283.01
26.85 23.35
Carriage of Stone aggregate below 69.00 5.00 106.13 5.00 10.07
2202 cum 106.13
40 mm nominal size 8.76
2203 Carriage of Coarse sand cum
69.00 5.00
106.13
106.13 5.00 10.07 8.76
2204 Carriage of Timber cum
5.00 5.00
121.29
121.29 0.00 11.51 10.01
2205 Carriage of Steel tonne 5.00 5.00 94.34 94.34 0.00 8.95 7.78
Carriage of Stone aggregate 40 mm 5.00 5.00 115.36 0.00
2206 cum 115.36
nominal size and above 10.94 9.51
5.00 5.00 169.81 0.00
2207 Carriage of Brick tiles 1000 Nos 169.81 16.11 14.01
2208 Carriage of Lime cum 5.00 5.00 106.13 106.13 0.00 10.07 8.76
2209 Carriage of Cement tonne 5.00 5.00 94.34 94.34 0.00 8.95 7.78
2211 Carriage of Tar / Bitumen tonne 5.00 5.00 106.13 106.13 0.00 10.07 8.76
Carriage of Soling stone & masonry 5.00 5.00 124.86 0.00
2215 stone cum 124.86 11.84 10.3
5.00 5.00 94.34 0.00
Carriage of Stone blocks white & red
2216 sand stone & kota stone slab tonne 94.34 8.95 7.78
2224 Carriage of S.W. pipes 100 mm dia 100 metre 5.00 5.00 141.51 141.51 0.00
13.42 11.67
2225 Carriage of S.W. pipes 150 mm dia 100 metre 5.00 5.00 283.01 283.01 0.00 26.85 23.35
2226 Carriage of S.W. pipes 200 mm dia 100 metre 5.00 5.00 471.69 471.69 0.00 44.74 38.9
Carriage of S.W. pipes 250 mm dia 100 metre 5.00 5.00 808.61 0.00 76.70 66.7
2228 808.61
2229 Carriage of S.W. pipes 300 mm dia 100 metre 5.00 5.00 1010.76 1010.76 0.00 95.88 83.37
2241 Carriage of Good earth cum 5.00 5.00 132.66 132.66 0.00 12.58 10.94
Carriage of Dump manure by
5.00 5.00 115.36 0.00 10.94 9.51
2242 mechanical transport upto 5 km lead cum 115.36
2260 Carriage of Brick aggregate cum 5.00 5.00 115.36 115.36 0.00 10.94 9.51
2261 Carriage of Fine sand cum 5.00 5.00 106.13 106.13 0.00 10.07 8.76
2262 Carriage of Flyash cum 5.00 5.00 106.13 106.13 0.00 10.07 8.76
5.00 5.00 106.13 0.00 10.07 8.76
2264 Carriage of Rubbish cum 106.13
5.00 5.00 106.13 0.00 10.07 8.76
2265 Carriage of Moorum cum 106.13
2266 Carriage of Surkhi cum 5.00 5.00 106.13 106.13 0.00 10.07 8.76
5.00 5.00 106.13 0.00 10.07 8.76
2267 Carriage of Stone dust cum 106.13
Carriage of Marble dust and/or 5.00 5.00 106.13 0.00 10.07
2268
marble chips
cum 106.13 8.76
2271 Carriage of G.I. pipes below 100 tonne 5.00 5.00 94.34 94.34 0.00 8.95 7.78
mm dia
2272 Carriage of Stainless Steel pipes tonne 5.00 5.00 94.34 94.34 0.00 8.95 7.78
below 100 mm dia
2273 Carriage of A.C.sheet and tonne 5.00 5.00 94.34 94.34 0.00 8.95 7.78
accessories
2275 Carriage of R.C.C. pipes 100 mm 100 metre 5.00 5.00 231.98 231.98 0.00 22 19.13
dia
Carriage of R.C.C. pipes 150 mm 5.00 5.00 386.63 0.00 36.67
2281 100 metre 386.63 31.89
dia
2287 Carriage of R.C.C. pipes 250 mm 100 metre 5.00 5.00 893.73 893.73 0.00 84.78 73.72
dia
2290 Carriage of R.C.C. pipes 300 mm 100 metre 5.00 5.00 1104.66 1104.66 0.00 104.78 91.11
dia
2299 Carriage of R.C.C. pipes 450 & 500 100 metre 5.00 5.00 2577.54 2577.54 0.00 244.50 212.61
mm dia
2302 Carriage of G.I. sheet and tonne 5.00 5.00 94.34 94.34 0.00 8.95 7.78
accessories
Carriage of R.C.C. pipes
5.00 5.00 3866.3 0.00 366.74 318.9
2303 600,700,750 & 800 mm dia 100 metre 3866.3
2308 Carriage of Plaster of paris tonne 5.00 5.00 94.34 94.34 0.00 8.95 7.78
2309 Carriage of Cast Iron fittings tonne 5.00 5.00 94.34 94.34 0.00 8.95 7.78
5.00 5.00 106.13 0.00 10.07 8.76
2311 Carriage of bajri cum 106.13
2314 Carriage of Barbed wire tonne 5.00 5.00 94.34 94.34 0.00 8.95 7.78
5.00 5.00 115.36 0.00 10.94 9.51
2317 Carriage of Sludge cum 115.36
2319 Carriage of Spun iron S & S pipes 100 metre 5.00 5.00 231.98 231.98 0.00 22 19.13
100 mm dia
2320 Carriage of Spun iron S & S pipes 100 metre 5.00 5.00 309.87 309.87 0.00 29.39 25.56
125 mm dia
Carriage of Spun iron S & S pipes 5.00 5.00 386.63 0.00 36.67
2321 100 metre 386.63 31.89
150 mm dia
Carriage of Spun iron S & S pipes 5.00 5.00 628.92 0.00 59.66 51.88
2322 100 metre 628.92
200 mm dia
2323 Carriage of Spun iron S & S pipes 100 metre 5.00 5.00 893.73 893.73 0.00 84.78 73.72
250 mm dia
Carriage of Spun iron S & S pipes 5.00 5.00 1104.66 1104.66 0.00 104.78 91.11
2324 100 metre
300 mm dia
Carriage of Spun iron S & S pipes 5.00 5.00 1546.52 1546.52 0.00 146.70 127.57
2325 100 metre
350 mm dia
Carriage of Spun iron S & S pipes 5.00 5.00 2108.89 2108.89 0.00 200.04 173.95
2326 100 metre
400 mm dia
Carriage of Spun iron S & S pipes 5.00 5.00 2577.54 2577.54 0.00 244.50 212.61
2327 100 metre
450 mm dia
Carriage of Spun iron S & S pipes 5.00 5.00 2577.54 2577.54 0.00 244.50 212.61
2328 100 metre
500 mm dia
Carriage of Spun iron S & S pipes 5.00 5.00 3866.3 0.00 318.9
2329
600mm dia
100 metre 3866.3 366.74
2330 Carriage of C.I. pipes 500 mm dia 100 metre 5.00 5.00 2577.54 2577.54 0.00 244.50 212.61
Carriage of R.C.C. pipes 900 mm 5.00 5.00 5799.46 5799.46 0.00 478.36
2331
dia
100 metre 550.11
Carriage of R.C.C. pipes 1000 mm 5.00 5.00 7732.61 7732.61 0.00 637.82
2332
dia
100 metre 733.49
Carriage of R.C.C. pipes 1100 mm 5.00 5.00 7732.61 7732.61 0.00 637.82
2333
dia
100 metre 733.49
Carriage of R.C.C. pipes 1200 mm 5.00 5.00 7732.61 7732.61 0.00 637.82
2334
dia
100 metre 733.49
2335 Carriage of sand cum 5.00 5.00 106.13 106.13 0.00 10.07 8.76
Carriage of R.C.C. pipe above 1200
5.00 5.00 7732.61 0.00 733.49 637.82
2336 mm dia and upto 1800 mm dia 100 metre 7732.61
2341 Carriage of Pig lead tonne 5.00 5.00 94.34 94.34 0.00 8.95 7.78
2342 Carriage of Solvent / Diesel. quintal 5.00 5.00 10.61 10.61 0.00 1.01 0.88
2343 Carriage of Ductile Iron pipes (k7) 100 metre 5.00 5.00 231.98 231.98 0.00 22 19.13
100 mm dia
Carriage of Cast iron pipes 150 mm 5.00 5.00 386.63 0.00 36.67
2344 100 metre 386.63 31.89
dia
Carriage of Cast iron pipes 200 mm 5.00 5.00 628.92 0.00 59.66 51.88
2345 100 metre 628.92
dia
Carriage of Cast iron pipes 250 mm 5.00 5.00 893.73 0.00 84.78 73.72
2346 100 metre 893.73
dia
Carriage of Cast iron pipes 300 mm 5.00 5.00 1104.66 1104.66 0.00 104.78 91.11
2347 100 metre
dia
Carriage of Cast iron pipes 350 mm 5.00 5.00 1546.52 1546.52 0.00 146.70 127.57
2348 100 metre
dia
Carriage of Cast iron pipes 400 mm 5.00 5.00 2108.89 2108.89 0.00 200.04 173.95
2349 100 metre
dia
Carriage of Cast iron pipes 450 mm 5.00 5.00 2577.54 2577.54 0.00 244.50 212.61
2350 100 metre
dia
Carriage of Cast iron pipes 500 mm 5.00 5.00 2577.54 2577.54 0.00 244.50 212.61
2351 100 metre
dia
Carriage of Cast iron pipes 600 mm 5.00 5.00 3866.3 0.00 318.9
2352
dia
100 metre 3866.3 366.74
Carriage of Cast iron pipes 700 mm 5.00 5.00 3866.3 0.00 318.9
2353
dia
100 metre 3866.3 366.74
Carriage of Cast iron pipes 800 mm 5.00 5.00 3866.3 0.00 318.9
2355
dia
100 metre 3866.3 366.74
Carriage of Cast iron pipes 900 mm 5.00 5.00 5799.46 5799.46 0.00 478.36
2356
dia
100 metre 550.11
Carriage of Cast iron pipes 1000 5.00 5.00 7732.61 0.00 733.49 637.82
2357 100 metre 7732.61
mm dia
Transport including loading, Unloading and stacking).

pto 10 km per Km. Beyond 10 km upto 20 km per km Beyond 20 km per additional 1 Amount
km. of extra
carriage
Amount Lead Rate i/c Basic Amount Lead Rate i/c Basic Amount
cp/oh Rate cp/oh Rate

0 0.00 9.83 8.55 0 0.00 8.4 7.3 0 121.29


0 0.00 0 0.00 0 283.01
22.93 19.94 19.61 17.05
43.8 10.00 8.60 74.8 49.00 360.15 584.88
7.48 7.35 6.39
43.8 10.00 8.60 7.48 74.8 49.00 7.35 6.39 360.15 584.88
0 0.00 9.83 8.55 0 0.00 8.4 7.3 0 121.29
0 0.00 7.64 6.64 0 0.00 6.54 5.69 0 94.34
0 0.00 0 0.00 0 115.36
9.35 8.13 7.99 6.95
0 0.00 13.76 0 0.00 11.77 0 169.81
11.97 10.23
0 0.00 8.60 7.48 0 0.00 7.35 6.39 0 106.13
0 0.00 7.64 6.64 0 0.00 6.54 5.69 0 94.34
0 0.00 8.60 7.48 0 0.00 7.35 6.39 0 106.13
0 0.00 10.11 0 0.00 8.65 0 124.86
8.79 7.52
0 0.00 0 0.00 6.54 0 94.34

7.64 6.64 5.69


0 0.00 11.46 0 0.00 9.80 0 141.51
9.97 8.52
0 0.00 22.93 19.94 0 0.00 19.61 17.05 0 283.01
0 0.00 38.28 33.29 0 0.00 32.68 28.42 0 471.69
0 0.00 65.51 56.97 0 0.00 56.03 48.72 0 808.61
0 0.00 81.88 71.2 0 0.00 70.03 60.9 0 1010.76
0 0.00 10.75 9.35 0 0.00 9.19 7.99 0 132.66
0 0.00 9.35 8.13 0 0.00 7.99 6.95 0 115.36
0 0.00 9.35 8.13 0 0.00 7.99 6.95 0 115.36
0 0.00 8.60 7.48 0 0.00 7.35 6.39 0 106.13
0 0.00 8.60 7.48 0 0.00 7.35 6.39 0 106.13
0 0.00 8.60 7.48 0 0.00 7.35 6.39 0 106.13
0 0.00 8.60 7.48 0 0.00 7.35 6.39 0 106.13
0 0.00 8.60 7.48 0 0.00 7.35 6.39 0 106.13
0 0.00 8.60 7.48 0 0.00 7.35 6.39 0 106.13
0 0.00 8.60 7.48 0 0.00 7.35 6.39 0 106.13
0 0.00 7.64 6.64 0 0.00 6.54 5.69 0 94.34
0 0.00 7.64 6.64 0 0.00 6.54 5.69 0 94.34
0 0.00 7.64 6.64 0 0.00 6.54 5.69 0 94.34
0 0.00 18.79 16.34 0 0.00 16.07 13.97 0 231.98
0 0.00 31.32 27.23 0 0.00 26.79 23.3 0 386.63
0 0.00 72.40 62.96 0 0.00 61.92 53.84 0 893.73
0 0.00 89.49 77.82 0 0.00 76.54 66.56 0 1104.66
0 0.00 208.81 181.57 0 0.00 178.59 155.3 0 2577.54
0 0.00 7.64 6.64 0 0.00 6.54 5.69 0 94.34
0 0.00 313.21 272.36 0 0.00 267.89 232.95 0 3866.30
0 0.00 7.64 6.64 0 0.00 6.54 5.69 0 94.34
0 0.00 7.64 6.64 0 0.00 6.54 5.69 0 94.34
0 0.00 8.60 7.48 0 0.00 7.35 6.39 0 106.13
0 0.00 7.64 6.64 0 0.00 6.54 5.69 0 94.34
0 0.00 9.35 8.13 0 0.00 7.99 6.95 0 115.36
0 0.00 18.79 16.34 0 0.00 16.07 13.97 0 231.98
0 0.00 25.10 21.83 0 0.00 21.47 18.67 0 309.87
0 0.00 31.32 27.23 0 0.00 26.79 23.3 0 386.63
0 0.00 50.95 44.3 0 0.00 43.58 37.9 0 628.92
0 0.00 72.40 62.96 0 0.00 61.92 53.84 0 893.73
0 0.00 89.49 77.82 0 0.00 76.54 66.56 0 1104.66
0 0.00 125.28 108.94 0 0.00 107.15 93.17 0 1546.52
0 0.00 170.84 148.56 0 0.00 146.12 127.06 0 2108.89
0 0.00 208.81 181.57 0 0.00 178.59 155.3 0 2577.54
0 0.00 208.81 181.57 0 0.00 178.59 155.3 0 2577.54
0 0.00 313.21 272.36 0 0.00 267.89 232.95 0 3866.30
0 0.00 208.81 181.57 0 0.00 178.59 155.3 0 2577.54
0 0.00 469.82 408.54 0 0.00 401.83 349.42 0 5799.46
0 0.00 626.42 544.71 0 0.00 535.77 465.89 0 7732.61
0 0.00 626.42 544.71 0 0.00 535.77 465.89 0 7732.61
0 0.00 626.42 544.71 0 0.00 535.77 465.89 0 7732.61
0 0.00 8.60 7.48 0 0.00 7.35 6.39 0 106.13
0 0.00 626.42 544.71 0 0.00 535.77 465.89 0 7732.61
0 0.00 7.64 6.64 0 0.00 6.54 5.69 0 94.34
0 0.00 0.86 0.75 0 0.00 0.74 0.64 0 10.61
0 0.00 18.79 16.34 0 0.00 16.07 13.97 0 231.98
0 0.00 31.32 27.23 0 0.00 26.79 23.3 0 386.63
0 0.00 50.95 44.3 0 0.00 43.58 37.9 0 628.92
0 0.00 72.40 62.96 0 0.00 61.92 53.84 0 893.73
0 0.00 89.49 77.82 0 0.00 76.54 66.56 0 1104.66
0 0.00 125.28 108.94 0 0.00 107.15 93.17 0 1546.52
0 0.00 170.84 148.56 0 0.00 146.12 127.06 0 2108.89
0 0.00 208.81 181.57 0 0.00 178.59 155.3 0 2577.54
0 0.00 208.81 181.57 0 0.00 178.59 155.3 0 2577.54
0 0.00 313.21 272.36 0 0.00 267.89 232.95 0 3866.30
0 0.00 313.21 272.36 0 0.00 267.89 232.95 0 3866.30
0 0.00 313.21 272.36 0 0.00 267.89 232.95 0 3866.30
0 0.00 469.82 408.54 0 0.00 401.83 349.42 0 5799.46
0 0.00 626.42 544.71 0 0.00 535.77 465.89 0 7732.61
BASIC RATES

0.2 LABOUR

Note :- These rates are exclusive of contractor’s profit and over heads and are inclusive of wages for
weekly day of rest.
Code No. Description Unit Rate Excluding Rate including Rate including
Paid Holiday 1/6th Paid 1/6th Paid
Holiday Holiday

10 Bandhani day 275 300 320.83 350.00


11 Bhisti day 275 300 320.83 350.00
12 Blacksmith 1st class day 408 433 476 505.17
13 Blacksmith 2nd class day 321 346 374.5 403.67
14 Carpenter 1st class day 408 433 476 505.17
15 Carpenter 2nd class day 321 346 374.5 403.67
16 Chowkidar day 275 300 320.83 350.00
17 Beldar day 275 300 320.83 350.00
18 Coolie day 275 300 320.83 350.00
19 Fitter (grade 1) day 408 433 476 505.17
20 Assistant Fitter or 2nd class Fitter day 321 346 374.5 403.67
21 Glazier day 321 346 374.5 403.67

22 Mason (for plaster of paris work) 1st class day 408 433 476 505.17

23 Mason (brick layer) 1 st class day 408 433 476 505.17


24 Mason (brick layer) 2nd class day 321 346 374.5 403.67
25 Mason (for plain stone work) 2nd class day 321 346 374.5 403.67
26 Mason (for ornamental stone work) 1st class day 408 433 476 505.17
Driver (for Road Roller, Concrete Mixer,
27 Truck etc.) day 336 361 392 421.17
28 Mate day 275 300 320.83 350.00
29 Sewer man day 275 300 320.83 350.00
30 Mistry day 408 346 476 403.67
31 Painter day 321 346 374.5 403.67
32 Rock Excavator day 275 300 320.83 350.00
33 Rock Breaker day 275 300 320.83 350.00
34 Rock Hole Driller day 275 300 320.83 350.00
35 Stone Chiseller day 336 361 392 421.17
36 Sprayer (for bitumen, tar etc.) day 275 300 320.83 350.00
37 Skilled Beldar (for floor rubbing etc.) day 275 300 320.83 350.00
38 White Washer day 275 300 320.83 350.00
39 Nozzel man/ gun man day 321 346 374.5 403.67
40 Mason (average) day 321 346 374.5 403.67
41 Carpenter (average) day 321 346 374.5 403.67
42 Operator (Pile/ Special machine) day 336 361 392 421.17
43 Skilled torch operator for laying tack day 321 346 374.5 403.67
Helper (Technician) Labour for fabrication
44 Technician day 321 346 374.5 403.67
of uPVC extruded casement/ sliding
45 windows and doors day 275 300 320.83 350.00
46 including drilling holes, fixing of fittings &
hardwares, hire charges of drill machine and
electricity charges etc. Labour for sqm 485 485 485 485.00
installation of uPVC extruded

47 casement/ sliding windows and doors sqm 430 430 430 430.00
including scaffolding
Security guard without gun (8 hours shift
48 day 308 308 359.33 359.33
duty per day)
Security guard with gun (8 hours shift duty
49 day 321 321 374.5 374.50
per day)
BASIC RATES
0.3 MATERIALS
Note :- These rates are exclusive of contractor’s profit and over heads charges,
carriage, octroi, excise duty (ED), sales taxUnit
Code Description (GST) etc.
Rate at Rate at
No. market Site
222 Seam bolts and nuts 6 mm dia and 25 mm long 10 Nos 10 10

223 Fibre (reinforced by organic fibres and / or inorganic synthetic fibre) sqm 225 225
cement corrugated sheet 6 mm thick
224 Fibre (reinforced by organic fibres and / or inorganic synthetic fibre) metre 210 210
cement close fitting adjustable ridge
225 Fibre (reinforced by organic fibres and / or inorganic synthetic fibre) metre 210 210
cement corrugate serrated adjustable ridge

226 Fibre (reinforced by organic fibres and / or inorganic synthetic fibre) metre 210 210
cement plain wing adjustable ridge
227 Fibre (reinforced by organic fibres and / or inorganic synthetic fibre) metre 210 210
cement unserrated adjustable ridge for hips

228 Fibre (reinforced by organic fibres and / or inorganic synthetic fibre) metre 200 200
cement corrugated apron piece
229 Fibre (reinforced by organic fibres and / or inorganic synthetic fibre) each 175 175
cement eaves filler piece
230 Fibre (reinforced by organic fibres and / or inorganic synthetic fibre) metre 280 280
cement north light curves
231 Fibre (reinforced by organic fibres and / or inorganic synthetic fibre) each 310 310
cement north light curves
232 Fibre (reinforced by organic fibres and / or inorganic synthetic fibre) metre 400 400
cement barge boards boards 6 mm thick
233 Fibre (reinforced by organic fibres and / or inorganic synthetic fibre) pair 165 165
cement ridge finial
234 Fibre (reinforced by organic fibres and / or inorganic synthetic fibre) each 555 555
cement special north light curves
235 Fibre (reinforced by organic fibres and / or inorganic synthetic fibre) each 260 260
cement S type louvers
236 Multi purpose fibre (reinforced by organic fibres and / or inorganic sqm 210 210
synthetic fibre) cement board 6 mm thick
237 Multi purpose fibre (reinforced by organic fibres and / or inorganic sqm 220 220
synthetic fibre) cement board 8 mm thick
238 6 mm thick heavy duty fiber cement board sqm 470 470

239 8mm thick heavy duty fiber cement board sqm 300 300

240 9 mm thick heavy duty fiber cement board sqm 625 625

241 12.5 mm thick Gypsum plaster board sqm 170 170

242 6 mm thick mulitipurpose cement bonded wood particle board sqm 195 195
conforming to IS : 14276
243 8 mm thick mulitipurpose cement bonded wood particle board sqm 215 215
conforming to IS : 14276
244 Factory made light weight composite non asbestos fibre reinforced sqm 634 634
aerated cement sandwitched wall/roof panel (50mm thick). The outer
face on both sides of the panels will be non asbestos fibre cement
board (minimum 4mm thick) confirming to IS 14862:2000

245 Factory made light weight composite non asbestos fibre reinforced sqm 789 789
aerated cement sandwitched wall/roof panel (50mm thick). The outer
face on both sides of the panels will be non asbestos fibre cement
board (minimum 4mm thick) confirming to IS 14862:2000

246 Factory made light weight non asbestos fibre reinforced aerated sqm 10 10
cement sandwitched wall/roof panel (75mm thick). The outer face on
247 both sides
2mm thickof thepad
sim panels will be non asbestos fibre cement board each 15 15
(minimum 5mm thick) confirming to IS 14862:2000
248 5mm thick sim pad each 25 25

285 Brick Aggregate (Single size) : 63 mm cum 650 650


nominal
286 Brick Aggregate (Single size) : sizemm
50 cum 650 650
nominal
287 Brick Aggregate (Single size) : size
40 mm cum 650 650
nominal
291 Stone Aggregate (Single size) sizemm
63 cum 700 700
nominal
292 Stone Aggregate (Single size) sizemm
50 cum 730 730
nominal
293 Stone Aggregate (Single size) sizemm
40 cum 760 760
nominal
294 Stone Aggregate (Single size) sizemm
25 cum 790 790
nominal
295 Stone Aggregate (Single size) sizemm
20 cum 800 800
nominal
296 Stone Aggregate (Single size) size mm
12.5 cum 810 810
nominal
297 Stone Aggregate (Single size) sizemm
10 cum 810 810
nominal
298 Stone Aggregate (Single size) sizemm
06 cum 825 825
nominal
302 Safeda ballies 125 mm diameter size metre 40 40

303 Cowdung cum 50 50

304 Bajri cum 1000 1000

305 Bamboo 25 mm dia 2.5 metre long score 400 400

308 Bhusa quintal 500 500

309 Paving bitumen of grade VG-10 of approved quality tonne 48000 48000

310 Bitumen emulsion tonne 50000 50000

312 Bitumen grade PMB - 40 tonne 52000 52000

313 Blown type petroleum bitumen of penetration 85/25 of approved tonne 53000 53000
quality
314 Bitumen hot sealing compound : grade A kg 28 28

316 Bitumen solution primer of approved quality litre 45 45

317 Premoulded joint filler 12 mm thick sqm 360 360


318 Bitumen felt fibre base (vegetable or animal):As per IS 7193 Grade I sqm 70 70

319 Bitumen felt as per IS 7193 Grade II sqm 80 80

322 Bitumen felt :Type 3 grade 1 sqm 70 70

323 Separation Membrane of impermeable plastic sheeting 125 micron sqm 12 12


thick
324 Coal Tar litre 30 30

325 Blasting powder kg 40 40

326 Blasting fuse (fuse wire) each 15 15

328 White face insulating board: 12 mm thick sqm 235 235

332 Natural colour insulating board : 12 mm sqm 210 210


thick
336 Flame retardant face insulating board: 12 mm thick sqm 320 320

339 Flame retardant face insulating, Impregnated fibre board 12 mm sqm 375 375
thick
341 Flat pressed 3 layer particle board (medium density) Grade 1, 12 mm sqm 288 288
thick
346 Extra for veneered particle board with Teak veneering on one side sqm 230 230
and commercial veneering on other side
347 Extra for veneered particle board with Commercial veneering on sqm 155 155
both sides
348 Extra for veneered particle board with Teak veneering on both sides sqm 500 500

349 Curing compound litre 38 38

351 Integral crystalline slurry kg 238 238

352 Integral crystalline admixture kg 272 272

353 Crystalline mortar kg 215 215

354 Integral crystalline dry shake kg 360 360

355 Swellable type water stop tape metre 365 365

356 Primer for swellable type water stop tape litre 1540 1540

357 Polymer modified adhesive mortar kg 15 15

362 Brick bats cum 1000 1000

364 Wire brush each 20 20

365 Soft brush each 20 20

367 Portland Cement (OPC-43 Grade) tonne 4375 4375

368 White Cement tonne 11200 11200

369 Plastic sheat,1.25 mm thick for dowel bars sqm 25 25

370 Coal (steam) quintal 440 440

371 Sealant primer kg 130 130

373 Cramp Gun metal 25x6x300 mm each 80 80


374 Pre moulded Joint filler, 25 mm thick for expansion joint. sqm 400 400

378 Brass butt hinges (light/ordinary type) : 125x70x4 mm 10 Nos 775 775

379 Brass butt hinges (light/ordinary type) : 100x70x4 mm 10 Nos 625 625

380 Brass butt hinges (light/ordinary type) : 75x40x2.5 mm 10 Nos 380 380

381 Brass butt hinges (light/ordinary type) : 50x40x2.5 mm 10 Nos 155 155

382 Brass butt hinges (heavy type) : 125x85x5.5 mm(0.70 kg) 10 Nos 1309 1309

383 Brass butt hinges (heavy type) : 100x85x5.5 mm(0.56 kg) 10 Nos 997 997

384 Brass butt hinges (heavy type) :75x65x4.0 mm (weighing not less 10 Nos 838 838
than 0.20 kg)
385 Brass parliamentary hinges 150x125x27x5 mm 10 Nos 2610 2610

386 Brass parliamentary hinges 125x125x27x5 mm 10 Nos 2300 2300

387 Brass parliamentary hinges 100x125x27x5 mm 10 Nos 2090 2090

388 Brass parliamentary hinges 75x100x20x3.2 mm 10 Nos 1870 1870

389 Brass single acting spring hinges 150 mm each 425 425

390 Brass single acting spring hinges 125 mm each 285 285

391 Brass single acting spring hinges 100 mm each 250 250

392 Brass double acting spring hinges 150 mm each 480 480

393 Brass double acting spring hinges 125 mm each 400 400

394 Brass double acting spring hinges 100 mm each 390 390

400 Brass tower bolt (barrel type) 250x10 mm each 257 257

401 Brass tower bolt (barrel type) 200x10 mm each 205 205

402 Brass tower bolt (barrel type) 150x10 mm each 154 154

403 Brass tower bolt (barrel type) 100x10 mm each 103 103

404 Brass flush bolt 250 mm each 150 150

405 Brass flush bolt 150 mm each 130 130

406 Brass flush bolt 100 mm each 90 90

408 Brass handles 125 mm with plate 175x32 mm each 144 144

409 Brass handles 100 mm with plate 150x32 mm each 133 133

410 Brass handles 75 mm with plate 125x32 mm each 103 103

411 Brass door latch 300x16x5 mmweighing not less than 0.380 kg each 185 185

412 Brass door latch 250x16x5 mm weighing not less than 0.350 kg each 175 175

413 Brass mortice latch and lock 100x65 mm with 6 levers and a pair of each 400 400
brass lever handles
414 Brass mortice latch 100x65mm with a pair of brass lever handles each 310 310
417 Brass 150 mm floor door stopper weighing not less than 0.357kg each 160 160

418 Brass hard drawn hooks and eyes 300 mm 10 Nos 600 600

419 Brass hard drawn hooks and eyes 250 mm 10 Nos 574 574

420 Brass hard drawn hooks and eyes 200 mm 10 Nos 510 510

421 Brass hard drawn hooks and eyes 150 mm 10 Nos 400 400

422 Brass hard drawn hooks and eyes 100 mm 10 Nos 345 345

423 Brass casement window fastener each 45 45

424 Brass casement stays (straight peg type) 300 mm weighing not less each 126 126
than 0.33 kg
425 Brass casement stays (straight peg type) 250 mm weighing not less each 100 100
than 0.28 kg
426 Brass casement stays (straight peg type) 200 mm weighing not less each 95 95
than 0.24 kg
427 Brass quadrant stays 300 mm each 110 110

428 Brass fanlight catch 10 Nos 170 170

429 Brass fanlight pivot 10 Nos 168 168

430 Brass chain with hook for fan light catch each 36 36

431 Brass hasps and staples (safety type) 150 mm 10 Nos 740 740

432 Brass hasps and staples (safety type) 115 mm 10 Nos 670 670

433 Brass hasps and staples (safety type) 90 mm 10 Nos 575 575

438 Brass night latch each 610 610

442 Brass helical spring 150 mm each 290 290

444 Brass curtain rod 20 mm dia 1.25 mm thick metre 140 140

445 Brass curtain rod 25 mm dia 1.25 mm thick metre 190 190

446 Brass brackets (curtain rods) 20 mm each 45 45

447 Brass cupboard knob or wardrobe knob 50 mm each 36 36

449 Brass screws 50 mm 100 Nos 220 220

450 Brass screws 40 mm 100 Nos 170 170

451 Brass screws 30 mm 100 Nos 140 140

452 Brass screws 25 mm 100 Nos 100 100

453 Brass screws 20 mm 100 Nos 95 95

454 Stainless steel SS grade 304 , curtain rod 20 mm dia 1.20mm thick Metre 125 125

455 Stainless steel SS grade 304, curtain rod 25 mm dia 1.20mm thick Metre 170 170

456 Stainless steel SS grade 304, brackets ( curtain rod) 20 mm dia each 46 46
1.20mm thick
457 Stainless steel SS grade 304, brackets ( curtain rod) 25 mm dia each 55 55
1.20mm thick
458 plastic sleeves for screw each 2 2

524 Chromium plated Brass butt hinges (heavy) type 75x65x4 mm 10 Nos 905 905
weighing not less than 200gms
525 Chromium plated Brass butt hinges (light/ordinary) type 10 Nos 805 805
125x70x4mm
526 Chromium plated Brass butt hinges (light/ordinary) type 100x70x4 10 Nos 690 690
mm
527 Chromium plated Brass butt hinges (light/ordinary) type 75x40x2.5 10 Nos 421 421
mm
528 Chromium plated Brass butt hinges (light/ordinary) type 50x40x2.5 10 Nos 180 180
mm
552 75mm SS fancy handles for kitchen cabinet 10 Nos. 255 255

553 100mm SS fancy handles for kitchen cabinet 10 Nos 455 455

554 125mm SS fancy handles for kitchen cabinet 10 Nos 640 640

555 Chromium plated Brass handles 125 mm with plate 175 x32 mm each 160 160

556 Chromium plated Brass handles 100 mm with plate 150 x 32 mm each 140 140

557 Chromium plated Brass handles 75mm with plate 125x32 mm each 125 125

558 Chromium plated Brass mortice latch and lock 100x65 mm with 6 each 470 470
levers and a pair of brass lever handles
568 Chromium plated brass casement window fastener each 90 90

569 Chromium plated Brass casement stays (straight peg type) 300 mm each 140 140
weighing not less than 0.33 kg
570 Chromium plated Brass casement stays (straight peg type) 250 mm each 120 120
weighing not less than 0.28 kg
571 Chromium plated Brass casement stays (straight peg type) 200 mm each 100 100
weighing not less than 0.24 kg
583 Chromium plated Brass Night latch each 500 500

584 Chromium plated Brass Wardrobe Knob 50 mm each 80 80

585 Chromium plated Brass screws 50 mm 100 Nos 300 300

586 Chromium plated Brass screws 40 mm 100 Nos 290 290

587 Chromium plated Brass screws 30 mm 100 Nos 240 240

588 Chromium plated Brass screws 25 mm 100 Nos 180 180

589 Chromium plated Brass screws 20 mm 100 Nos 160 160

590 Chromium plated Brass curtain rod 12 mm dia 1.25mm thick metre 185 185

591 Chromium plated Brass curtain rod 20 mm dia 1.25mm thick metre 260 260

592 Chromium plated Brass curtain rod 25 mm dia 1.25mm thick metre 340 340

593 C.P. Brass Extension Nipple (1/2"x2" size) each 40 40

594 Bright finished or black enameled mild steel butt hinges 125x65x 10 Nos 135 135
2.12 mm
595 Bright finished or black enameled mild steel butt hinges 100x58x 10 Nos 80 80
1.90 mm
596 Bright finished or black enameled mild steel butt hinges 75x47x 1.70 10 Nos 56 56

597 mm Bright finished or black enameled mild steel butt hinges 50x37x 10 Nos 49 49
1.50
608 mm Nickel plated bright finished mild steel piano hinges 1 mm thick metre 39 39
25 mm wide
635 Bright finished or black enameled mild steel screws 50 mm 100 Nos 75 75

637 Bright finished or black enameled mild steel screws 40 mm 100 Nos 60 60

638 Bright finished or black enameled mild steel screws 30 mm 100 Nos 45 45

639 Bright finished or black enameled mild steel screws 25 mm 100 Nos 36 36

640 Bright finished or black enameled mild steel screws 20 mm 100 Nos 30 30

641 Bright finished or black enameled mild steel bolts and nuts 50x6 mm each 5 5

642 Oxidised mild steel butt hinges 125x65x2.12 mm 10 Nos 130 130

643 Oxidised mild steel butt hinges 100x58x1.90 mm 10 Nos 85 85

644 Oxidised mild steel butt hinges 75x47x1.70 mm 10 Nos 63 63

645 Oxidised mild steel butt hinges 50x37x1.50 mm 10 Nos 53 53

646 Oxidised mild steel parliamentary hinges 150x125x27x2.8 mm 10 Nos 334 334

647 Oxidised mild steel parliamentary hinges 125x125x27x2.8 mm 10 Nos 309 309

648 Oxidised mild steel parliamentary hinges 100x125x27x2.8 mm 10 Nos 231 231

649 Oxidised mild steel parliamentary hinges 75x100x20x2.24 mm 10 Nos 196 196

650 Oxidised mild steel single acting spring hinges 150 mm each 138 138

651 Oxidised mild steel single acting spring hinges 125 mm each 118 118

652 Oxidised mild steel single acting spring hinges 100 mm each 98 98

653 Oxidised mild steel double acting spring hinges 150 mm each 157 157

654 Oxidised mild steel double acting spring hinges 125 mm each 135 135

655 Oxidised mild steel double acting spring hinges 100 mm each 118 118

656 Nickel plated mild steel piano hinges 1 mm thick 35 mm wide metre 44 44

660 Oxidised mild steel sliding door bolt 300x16 mm each 93 93

661 Oxidised mild steel sliding door bolt 250x16 mm each 84 84

662 Oxidised mild steel door latch 300x20x6 mm each 49 49

663 Oxidised mild steel door latch 250x20x6 mm each 39 39

664 Oxidised mild steel tower bolt (barrel type) 250x10 mm each 43 43

665 Oxidised mild steel tower bolt (barrel type) 200x10 mm each 34 34

666 Oxidised mild steel tower bolt (barrel type) 150x10 mm each 29 29

667 Oxidised mild steel tower bolt (barrel type) 100x10 mm each 20 20

668 Oxidised mild steel handles 125 mm each 20 20

669 Oxidised mild steel handles 100 mm each 15 15


670 Oxidised mild steel handles 75 mm each 12 12

679 Oxidised mild steel hasps and staples (safety type) 150 mm 10 Nos 128 128

680 Oxidised mild steel hasps and staples (safety type) 115 mm 10 Nos 108 108

681 Oxidised mild steel hasps and staples (safety type) 90 mm 10 Nos 79 79

682 Oxidised mild steel screws 50 mm 100 Nos 76 76

683 Oxidised mild steel screws 40 mm 100 Nos 62 62

684 Oxidised mild steel screws 30 mm 100 Nos 49 49

685 Oxidised mild steel screws 25 mm 100 Nos 36 36

686 Oxidised mild steel screws 20 mm 100 Nos 32 32

687 Anodised Aluminium butt hinges 125x75x4 mm 10 Nos 560 560

688 Anodised Aluminium butt hinges 125x63x4 mm 10 Nos 393 393

689 Anodised Aluminium butt hinges 100x75x4 mm 10 Nos 393 393

690 Anodised Aluminium butt hinges 100x63x3.2 mm 10 Nos 270 270

691 Anodised Aluminium butt hinges 100x63x4 mm 10 Nos 324 324

692 Anodised Aluminium butt hinges 75x63x4 mm 10 Nos 275 275

693 Anodised Aluminium butt hinges 75x63x3.2 mm 10 Nos 226 226

694 Anodised Aluminium butt hinges 75x45x3.2 mm 10 Nos 196 196

696 Anodised Aluminium sliding door bolt 300x16 mm each 147 147

697 Anodised Aluminium sliding door bolt 250x16 mm each 128 128

698 Anodised Aluminium tower bolt (barrel type) 300x10 mm 10 Nos 580 580

699 Anodised Aluminium tower bolt (barrel type) 250x10 mm 10 Nos 481 481

700 Anodised Aluminium tower bolt (barrel type) 200x10 mm 10 Nos 383 383

701 Anodised Aluminium tower bolt (barrel type) 150x10 mm 10 Nos 304 304

702 Anodised Aluminium tower bolt (barrel type) 100x10 mm 10 Nos 226 226

703 Anodised Aluminium handles 125 mm with plate 175 x 32 mm 10 Nos 324 324

704 Anodised Aluminium handles 100 mm with plate 150 x 32 mm 10 Nos 275 275

705 Anodised Aluminium handles 75mm with plate 125 x 32 mm 10 Nos 231 231

706 Anodised Aluminium kicking plate 50 cm long 100x3.15 mm each 142 142

713 Block board construction flush door with teak wood ply on both sqm 1800 1800
faces 35 mm thick
714 Block board construction flush door with teak wood ply on both sqm 1600 1600
faces 30 mm thick
715 Block board construction flush door with teak wood ply on both sqm 1400 1400
faces 25 mm thick
717 Block board construction flush door with commercial ply on both sqm 950 1150
faces 35 mm thick
718 Block board construction flush door with commercial ply on both sqm 900 1150
faces 30 mm thick
719 Block board construction flush door with commercial ply on both sqm 890 1100
faces 25 mm thick
752 Block board construction flush door lipping 25 mm thick sqm of door 300 400
area
753 Square vision panel in Block board construction flush door not sqm of door 130 130
exceeding 0.10 sqm area
754 Circular vision panel in Block board construction flush door sqm of door 135 135
area
755 Decorative type louvers in Block board construction flush door sqm of door 265 265
area
757 Rebate cutting in block board construction flush door sqm of door 70 70
area
759 Decorative plywood 4 mm sqm 320 320

761 Fuel wood quintal 500 500

763 Glue kg 75 75

764 Calcium silicate base compound for jointing calcium silicate tiles kg 26 26

765 Hessian cloth sqm 35 35

768 Cement Concrete Jali 50 mm thick sqm 400 400

769 Cement Concrete Jali 40 mm thick sqm 350 350

770 Cement Concrete Jali 25 mm thick sqm 275 275

771 Kerosene oil litre 50 50

772 White cement based polymer modified self curing compound in kg 15 15


powder form
773 Unslaked lime quintal 300 300

775 Dehradun white lime quintal 600 600

776 Satna lime quintal 370 370

777 Dry hydrated lime (factory made) quintal 290 290

784 Marble dust/ powder cum 1130 1130

785 Marble chips up to 4 mm and down size White & black quintal 189 189

788 Marble chips large size above 4 mm White & black quintal 250 250

801 Silicon and acrylic emulsion litre 130 130

802 Acrylic distemper 1st quality , having VOC content less than 50 Kg 36 36
grams/ litre
803 Acrylic emulsion, having VOC content less than 50 grams/ litre litre 94 94

804 Premium acrylic emulsion of interior grade, having VOC content litre 220 220
less than 50 grams/ litre
806 Ready mixed pink or grey primer on wood work (hard and soft litre 105 105
wood) having VOC content less than 50 grams/ litre
808 Water thinnable cement primer for interior wall surface, having litre 50 50
VOC content less than 50 grams/ litre
809 Exterior primer kg 140 140

810 Moorum cum 500 500


811 Mud (dry) cum 165 165

815 Dry distemper kg 30 30

816 Oil bound washable distemper/ Acrylic distemper kg 50 50

818 Linseed oil (double boiled) litre 200 200

820 Cement primer litre 80 80

821 Distemper primer litre 70 70

823 Pink primer (for wood) litre 105 105

824 White cement based putty kg 13 13

826 Aluminium paint litre 150 150

827 Acid proof paint (chocolate or black) litre 225 225

828 Anticorrosive bituminous paint (black) litre 100 100

829 Black Japan paint litre 90 90

830 Enamel paint litre 165 165

831 Floor enamel paint in all shades except green litre 250 250

833 Synthetic enamel paint in black or chocolate shade litre 170 170

834 Synthetic enamel paint in all shades except black or chocolate shade litre 160 160

835 Plastic emulsion paint litre 200 200

836 100% Premium acrylic dirt resistance, Silicone additives exterior litre 270 270
paint
837 Acrylic Exterior Primer litre 100 100

845 Roofing paint for iron sheets in red colour litre 120 120

850 White lead kg 170 170

851 Water proofing cement paint kg 38 38

855 Wax polish (ready made) kg 230 230

856 Ordinary varnish litre 100 100

857 Superior copal varnish litre 115 115

858 Superior spar varnish litre 115 115

859 Oil type wood preservative litre 130 130

863 Putty for wood work kg 30 30

865 Pig lead kg 130 130

868 Premixed super white gypsum plaster kg 6 6

869 Plaster of Paris kg 5 5

870 Plug each 10 10


873 Copper pins 6 mm dia 7.5 cm long each 10 10

874 Black colour dark shade pigment kg 70 70

875 Red, chocolate, orange, buff or yellow (red oxide of iron) light shade kg 60 60
pigment
876 Green or blue medium shade pigment kg 56 56

886 Standard holder bat clamps for sand cast iron or cast iron pipes 150 each 45 45
mm dia
966 Sand Cast iron plain shoe 150 mm dia each 285 285

967 Copper plate kg 527 527

969 Pulley 25 mm dia each 48 48

973 Rolling shutter made of 80x1.25 mm machine rolled laths sqm 1400 1400

974 Top cover for rolling shutters 1.25 mm thick metre 800 800

975 27.5 cm long wire spring grade No. 2 for rolling shutters each 300 300

976 Ball bearing for rolling shutters each 260 260

977 Extra for mechanical devices chain and cranked operation for sqm 800 800
operating rolling shutters: exceeding 10.00 sqm and up to 16.80sqm
978 area offor
Extra door
mechanical devices chain and cranked operation for sqm 800 800
operating rolling shutters: exceeding 16.80 sqm area of door
979 Royalty for good earth cum 40 40

980 Royalty for sludge cum 90 90

982 Coarse sand cum 800 800

983 Fine sand cum 850 850

992 Galvanised steel plain sheets quintal 6000 6000

993 FY-1860 grade wire strands quintal 5700 5700

994 Standard quality hard board sheet 3 mm thick sqm 135 135

996 Standard quality hard board sheet 4.5 mm thick sqm 210 210

999 Shellac kg 300 300

1000 Spirit litre 48 48

1001 Spun yarn kg 50 50

1002 Mild steel round bar 12 mm dia and below quintal 5100 5500

1003 Mild steel round bar above 12 mm dia quintal 5100 5500

1004 Average rate of Mild steel round bars for reinforcement quintal 5100 5500

1005 Twisted steel/ deformed TMT bars Fe-500D quintal 5254 5500

1006 Mild steel square bars quintal 5500 5500

1007 Structural steel such as tees, angles channels and R.S. joists quintal 4900 5300

1008 Flats up to 10 mm in thickness quintal 4900 5300


1009 Flats exceeding 10 mm in thickness quintal 4870 5300

1010 Mild steel plates quintal 4950 5300

1011 Steel glazed door, window/ ventilator, all members viz. F7D, F4B, kg 54 55
K11 and K12B etc.
1012 Pregalvanized high tensile steel confirming to IS:277-199 kg 90 90

1013 Mild steel sheets of 1.00 mm thickness for tanks quintal 4600 4600

1015 Mild steel expanded metal 20x60 mm strands 3.25 mm wide 1.60 sqm 280 280
mm thick
1019 Mild steel hooks each 32 32

1020 Mild steel rivets quintal 5000 5000

1021 Hard drawn steel wire fabric 75 x 25 mm mesh of weight not less sqm 430 430
than 7.75 kg/sqm
1022 Galvanised steel bolts & nuts 6 mm dia and 25 mm long round head 10 Nos 38 38
with slots
1023 Galvanised steel J or L hooks 8 mm dia 10 Nos 120 120

1024 Galvanised steel bolts & nuts 10 mm dia and 125 mm long round each 9 9
head with slots
1025 Mild steel bolts 6 mm dia and 25 mm long with hexagonal head 10 Nos 10 10

1027 Erection Bolts ( Minimum 04 nos for each element) each 25 25

1028 Straining bolts each 80 80

1029 Galvanised steel barbed wire of 9.8 kg /100metre quintal 5500 5500

1030 Galvanised steel turn buckles each 25 25

1031 Galvanised steel bolts & nuts 10 mm dia and 27 cm long both sides each 20 20
threaded with 4 galvanised steel nuts
1032 Galvanised steel bolts 10 mm dia and 7 cm long with nuts each 6 6

1034 Bolts and nuts up to 300 mm in length quintal 6800 6800

1035 Bolts and nuts above 300 mm in length quintal 6500 6500

1036 Iron pintels including welded pin each 37 37

1143 Steel beading 10x10x1.6mm (box type) metre 27 27

1145 Aluminium Plain Strip edging 38x12x3 mm metre 90 90

1149 Glass strip 4 mm thick 40 mm deep metre 20 20

1151 Boundary stone top chisel dressed 15x15x90 cm each 80 80

1154 Through and bond stone 100 Nos 5000 5000

1157 Stone for masonry work cum 1100 1100

1158 Stone for pitching 15 cm x 22.5 cm cum 600 600

1159 Stone dust cum 1100 1100

1160 Red sand stone block 10 cudm 79 79

1161 White sand stone block 10 cudm 205 205


1163 White sand stone slab 75 mm thick (un-dressed) sqm 900 900

1164 Red sand stone slab 40 mm thick (un-dressed) sqm 200 400

1165 White sand stone slab 40 mm thick (un-dressed) sqm 200 280

1166 Red sand stone slab 30 mm thick (un-dressed) sqm 200 300

1168 Kota stone slab 20 mm to 25 mm thick (semi-polished) sqm 280 350

1169 Kota stone slab 25mm thick (rough chiseled) sqm 301 400

1174 Red sand stone slab 45 mm to 50 mm thick (un-dressed) sqm 225 350

1175 White sand stone slab 45 mm to 50 mm thick (un-dressed) sqm 240 300

1177 Stone grit 6 mm and down size or pea sized gravel cum 800 800

1179 Crushed stone 2.36 mm to 12.5 mm size cum 900 900

1182 Surkhi cum 700 700

1186 Superior class teak wood such as Dandeli, Balarshah or Malabar in 10 cudm 1100 1100
planks
1187 First class teak wood in scantling 10 cudm 880 880

1188 First class teak wood in planks 10 cudm 850 850

1189 Second class teak wood in scantling 10 cudm 776 776

1190 Second class teak wood in planks 10 cudm 791 791

1191 Marandi wood in planks 10 cudm 440 440

1192 Marandi wood in scantling 10 cudm 431 431

1194 Second class deodar wood in planks 10 cudm 500 500

1196 First class kail wood in planks 10 cudm 300 300

1197 Second class kail wood in scantling 10 cudm 260 260

1198 Second class kail wood in planks 10 cudm 260 260

1199 Sal wood in scantling 10 cudm 600 600

1200 Kiln seasoned selected sheesham wood planks 10 cudm 650 650

1201 Precast terrazzo tiles 22 mm thick (light shade) sqm 285 285

1202 Precast terrazzo tiles 22 mm thick (medium shade) sqm 265 265

1203 Precast terrazzo tiles 22 mm thick (dark shade) sqm 245 245

1204 Precast heat resistant terrace tiles (size 300x300 mm) and 20 mm sqm 409 409
thick
1207 G.I. Limpet washer 100 Nos 21 21

1208 Bitumen washer 100 Nos 30 30

1209 G.I. plain washer thick 100 Nos 35 35

1210 G.I. plain washer thin 100 Nos 21 21


1211 G.I. plain washer for seam bolts 100 Nos 32 32

1213 Water proofing materials kilogram 35 35

1214 Welding by gas plant cm 2 2

1215 Welding by electric plant cm 2 2

1216 Whiting quintal 600 600

1217 GI Wire mesh 100x100 mm Kg 75 75

1218 Shear stud each 50 50

1219 Wire nails kilogram 58 58

1220 Wire mesh (rabbit) sqm 42 42

1221 20 mm dia holding down bolts quintal 6100 6100

1222 Mild steel sheets with bolts and nuts to rest on pintels each 120 120

1223 Steel weld mesh sqm 150 150

1224 Hard drawn steel wire quintal 4800 4800

1225 Mild steel flat strap fitting quintal 4120 4120

1227 Chequered terrazzo tiles 22 mm thick (light shade) sqm 275 275

1228 Chequered terrazzo tiles 22 mm thick (medium shade) sqm 300 300

1229 Chequered terrazzo tiles 22 mm thick (dark shade) sqm 260 260

1231 Extra for selected planks of second class teakwood 10 cudm 150 150

1234 Aluminium Plain Strip edging 57x12x3 mm metre 135 135

1235 Diesel litre 73.5 73.5

1237 Cutting marble or sand stone slab up to 50 mm thick by mechanical metre 10 10


device
1238 Extra for selected planks of first class teakwood 10 cudm 150 150

1239 18 mm thick Flamed finish granite stone slab sqm 1000 1000

1240 18 mm thick Italian Marble stone slab, Perlato (slab area up to 0.5 sqm 3209 3209
sqm).
1241 Commercial LPG in cylinder kg 82 82

1242 Glass mossaic tiles (20 mm x 20 mm x 4 mm) sqm 2049 2049

1243 Tile fixing chemical adhesive kg 8.7 8.7

1244 Cement Polymer Grout Compound kg 16 16

1245 Acid for cleaning tiles litre 18 18

1246 Silicon based Joint Sealant for Tiles kg 160 160

1247 Rubber base Adhesive kg 223 223

1248 Epoxy based sealing Compound kg 535 535


1249 Acrylic based sealing compound kg 500 500

1250 Non woven reinforcement Tape metre 0.14 0.14

1251 M-60 grade cemetitious grout (Non Shrink) kg 28 28

1252 Cementitious polymer base adhesive confirming to EOTA ETAG kg 34 34


004 (European Technical Approval)
1253 Polypropylene mechanical fastener with plastic pin confirming to each 30 30
EOTA ETAG 014 (European Technical Approval) having dia 10mm
1254 & L=200mm
Moisture cure Polyurethane Foam 750 ml 600 600

1255 PVC Corner Bead of size 25mmx25mm fixed with glass fibre mesh metre 90 90
(100mm x 100mm)
1256 Cementitious polymer base coat confirming to EOTA ETAG 004 kg 40 40
(European Technical Approval)
1257 Fiberglass mesh with alkali-resistant coating having mass per unit sqm 75 75
area ?145 g/m2, mesh size: 3.9x4.0 mm ±10%
1301 Bleaching powder quintal 1800 1800

1304 Surface box for stop cock each 125 125

1305 Surface box for sluice valve each 210 210

1307 Surface box for water meter each 250 250

1309 C.I. bracket for wash basin and sinks pair 88 88

1313 8 mm dia C.P. Brass/ S.S. Jet with flexible tube upto 1 metre long each 200 200
with S.S. tringular plate for Eureopean type W.C.
1314 C.P.brass chain with 32 mm dia rubber plug each 40 40

1315 C.P.brass chain with 40 mm dia rubber plug each 40 40

1316 50mmx50mm hardwood plug each 75 75

1330 Clamps and M.S. stays including bolts and nuts for 100 mm pipe each 67.5 67.5

1331 M.S. Holder bat clamp of approved design for 100 mm S.C.I. pipe each 30 30

1332 M.S. Holder bat clamp of approved design for 75 mm S.C.I. pipe each 27 27

1334 Clamps and M.S. stays including bolts and nuts for 50 mm pipe each 35 35

1335 Clamps and M.S. stays including bolts and nuts for 75 mm pipe each 37 37

1336 Clearing eye with chain and lid 100 mm dia each 44 44

1337 Clearing eye with chain and lid 150 mm dia each 50 50

1339 Brass bib-cock 15 mm dia each 210 210

1340 Brass bib-cock 20 mm dia each 225 225

1342 Brass stop-cock 15 mm dia each 210 210

1343 Brass stop-cock 20 mm dia each 225 225

1350 Mosquito proof coupling of approved design each 30 30

1352 C.I. cover and frame 300x300 mm inside each 477 477

1353 C.I. cover without frame 300x300 mm inside i/c cover of 4.50 kg each 477 477
1354 Rectangular cover 455x610 mm with frame (low duty) each 1400 1400

1355 Rectangular cover 455x610 mm without frame (low duty) each 910 910

1356 500 mm dia cover with frame (medium duty) each 4400 4400

1357 500 mm dia cover without frame (medium duty) each 2300 2300

1360 C.I. mouth, brass ferrule 15 mm dia each 140 140

1361 C.I. mouth, brass ferrule 20 mm dia each 160 160

1362 C.l. mouth, brass ferrule 25 mm dia each 220 220

1363 Vitreous china foot rests 250x130x30 mm pair 100 100

1364 C.I. grating 100x100 mm each 40.22 40.22

1366 C.I. grating 150x150 mm each 54.42 54.42

1367 C.I. grating 180x180 mm each 65 65

1369 S.C.I. gully or nahani grating 100 mm dia each 25 25

1373 Rubber insertions for 75 mm dia pipe joints each 16 16

1374 Rubber insertions for 100 mm dia pipe joints each 18 18

1375 Rubber insertions for 125 mm dia pipe joints each 20 20

1376 Rubber insertions for 150 mm dia pipe joints each 20 20

1377 Rubber insertions for 200 mm dia pipe joints each 25 25

1378 Rubber insertions for 250 mm dia pipe joints each 40 40

1379 Rubber insertions for 300 mm dia pipe joints each 45 45

1380 Rubber insertions for 350 mm dia pipe joints each 50 50

1381 Rubber insertions for 400 mm dia pipe joints each 73 73

1382 Rubber insertions for 450 mm dia pipe joints each 92 92

1383 Rubber insertions for 500 mm dia pipe joints each 110 110

1384 Rubber insertions for 600 mm dia pipe joints each 125 125

1392 Mirror of superior make glass 60x45 cm each 400 400

1396 Vitreous china pedestal for wash basin each 900 900

1397 Pig lead kg 176 176

1464 S & S.C.I. standard specials upto 300 mm dia (heavy class) quintal 3600 3600

1466 S & S.C.I. standard specials over 300 mm dia (heavy class) quintal 3700 3700

1468 Flanged C.I. standard specials upto 300 mm dia (heavy class) quintal 5500 5500

1470 Flanged C.I. standard specials over 300 mm dia (heavy class) quintal 5500 5500

1472 Casing pipe 100 mm dia metre 335 335


1532 Flush pipe with union spreaders and clamps all in C.P. brass for each 270 270
single stall
1533 Flush pipe with union spreaders and clamps all in C.P. brass for each 400 400
double stall
1534 Flush pipe with union spreaders and clamps all in C.P. brass for each 520 520
range of three stall
1535 Flush pipe with union spreaders and clamps all in C.P. brass for each 600 600
range of four stall
1540 Flush pipe and spreaders G.l. for single set of one squatting plate each 175 175
urinal
1541 Flush pipe and spreaders G.l. for range of two squatting plates urinal each 250 250

1542 Flush pipe and spreaders G.l. for range of three squatting plates each 300 300
urinal
1543 Flush pipe and spreaders G.l. for range of four squatting plates urinal each 390 390

1545 G.I. pipes 15 mm dia metre 91 91

1546 G.I. pipes 20 mm dia metre 120 120

1547 G.I. pipes 25 mm dia metre 171 171

1548 G.I. pipes 32 mm dia metre 215 215

1549 G.I. pipes 40 mm dia metre 250 250

1550 G.I. pipes 50 mm dia metre 310 310

1551 G.I. pipes 65 mm dia metre 395 395

1552 G.I. pipes 80 mm dia metre 505 505

1555 G.I. back (jam) nuts 25 mm dia each 15 15

1559 G.I. back (jam) nuts 65 mm dia each 25 25

1608 G.I. tees (equal) 25 mm each 50 50

1612 G.I. tees (equal) 65 mm each 452 452

1614 G.I. inlet connection each 60 60

1616 S.C.I. soil, waste and vent single socketed pipe 1.80 metres long: 75 each 1050 1050
mm dia
1617 S.C.I. soil, waste and vent single socketed pipe 1.80 metres long: each 1135 1135
100 mm dia
1618 S.C.I. soil, waste and vent single socketed pipe 1.80 metres long: each 1750 1750
150 mm dia
1620 S.C.I. plain bend 75 mm dia each 210 210

1621 S.C.I. plain bend 100 mm dia each 258 258

1622 S.C.I. plain bend 150 mm dia each 460 460

1624 S.C.I. bend with access door 75 mm dia each 240 240

1625 S.C.I. bend with access door 100 mm dia each 300 300

1627 S.C.I. plain single equal junctions 75x75x75 mm dia each 278 278

1628 S.C.I. plain single equal junctions 100x100x100 mm dia each 360 360

1630 S.C.I. single equal junctions 75x75x75 mm dia with access door each 320 320
1631 S.C.I. single equal junctions 100x100x100 mm dia with access door each 405 405

1633 S.C.I. plain double equal junctions 75x75x75x75 mm dia each 382 382

1634 S.C.I. plain double equal junctions 100x100x100x100 mm dia each 590 590

1636 S.C.I. double equal junctions 75x75x75x75 mm dia with access door each 500 500

1637 S.C.I. double equal junctions 100x100x100x100 mm dia with access each 715 715
door
1639 Slotted cowl (terminal guard) 75 mm dia each 191 191

1640 Slotted cowl (terminal guard) 100 mm dia each 239 239

1641 G.I. Union 15 mm nominal bore each 30 30

1642 G.I. Union 20 mm nominal bore each 49 49

1643 G.I. Union 25 mm nominal bore each 108 108

1644 G.I. Union 32 mm nominal bore each 141 141

1645 G.I. Union 40 mm nominal bore each 192 192

1646 G.I. Union 50 mm nominal bore each 249 249

1647 G.I. Union 65 mm nominal bore each 504 504

1648 G.I. Union 80 mm nominal bore each 563 563

1649 Polyethylene water storage tank with cover and suitable locking per litre 5.5 5.5
arrangement
1653 Sand cast iron S&S plain single unequal junctions: 100x100x75 mm each 494 494
dia
1656 Sand cast iron S&S single unequal junctions: 100x100x75 mm dia each 550 550
with access door
1659 Sand cast iron S&S plain double unequal junctions: 100x100x75x75 each 615 615
mm dia
1662 Sand cast iron S&S double unequal junctions: 100x100x75x75 mm each 700 700
dia with access door
1666 Sand cast iron heel rest bend 75 mm dia each 274 274

1667 Sand cast iron heel rest bend 100 mm dia each 347 347

1669 S.C.I. single equal invert branch of required degree 75x75x75 mm each 320 320
dia
1670 S.C.I. single equal invert branch of required degree 100x100x 100 each 410 410
mm dia
1672 S.C.I. double equal invert branch of required degree 75x75x75x 75 each 410 410
mm dia
1673 S.C.I. double equal invert branch of required degree 100x100x each 550 550
100x100 mm dia
1674 S.C.I. single unequal invert branch of required degree 100x100x 75 each 495 495
mm dia
1677 S.C.I. double unequal invert branch of required degree 100x100x each 570 570
75x75 mm dia
1682 S.C.I. door pieces 75 mm dia each 283 283

1683 S.C.I. door pieces 100 mm dia each 475 475

1685 S.C.I. collar 75 mm dia each 177 177

1686 S.C.I. collar 100 mm dia each 246 246


1687 Unplasticised P.V.C. connection pipe with brass union 30 cm long each 30 30
15 mm bore
1688 Unplasticised P.V.C. connection pipe with brass union 30 cm long each 35 35
20 mm bore
1689 Unplasticised P.V.C. connection pipe with brass union 45 cm long each 35 35
15 mm bore
1690 Unplasticised P.V.C. connection pipe with brass union 45 cm long each 48 48
20 mm bore
1693 S.C.I. hand pump each 670 670

1700 R.C.C. pipes NP2 class 100 mm dia metre 200 200

1701 R.C.C. pipes NP2 class 150 mm dia metre 212 212

1702 R.C.C. pipes NP2 class 250 mm dia metre 350 350

1703 R.C.C. pipes NP2 class 300 mm dia metre 445 445

1704 R.C.C. pipes NP2 class 450 mm dia metre 750 750

1705 R.C.C. pipes NP2 class 500 mm dia metre 925 925

1706 R.C.C. pipes NP2 class 600 mm dia metre 1100 1100

1707 R.C.C. pipes NP2 class 700 mm dia metre 1485 1485

1709 R.C.C. pipes NP2 class 800 mm dia metre 1800 1800

1710 R.C.C. pipes NP2 class 900 mm dia metre 2500 2500

1711 R.C.C. pipes NP2 class 1000 mm dia metre 2900 2900

1712 R.C.C. pipes NP2 class 1100 mm dia metre 3200 3200

1713 R.C.C. pipes NP2 class 1200 mm dia metre 3510 3510

1714 R.C.C. collars NP2 class 100 mm dia each 30 30

1715 R.C.C. collars NP2 class 150 mm dia each 35 35

1716 R.C.C. collars NP2 class 250 mm dia each 50 50

1717 R.C.C. collars NP2 class 300 mm dia each 55 55

1718 R.C.C. collars NP2 class 450 mm dia each 100 100

1719 R.C.C. collars NP2 class 500 mm dia each 115 115

1720 R.C.C. collars NP2 class 600 mm dia each 140 140

1721 R.C.C. collars NP2 class 700 mm dia each 150 150

1723 R.C.C. collars NP2 class 800 mm dia each 200 200

1724 R.C.C. collars NP2 class 900 mm dia each 235 235

1725 R.C.C. collars NP2 class 1000 mm dia each 280 280

1726 R.C.C. collars NP2 class 1100 mm dia each 300 300

1727 R.C.C. collars NP2 class 1200 mm dia each 350 350

1728 RCC pipe 450 mm dia NP-3 spigot metre 1496 1496
1729 RCC pipe 600 mm dia NP-3 spigot metre 1995 1995

1730 RCC pipe 900 mm dia NP-3 spigot metre 3150 3150

1731 RCC pipe 1000 mm dia NP-3 spigot metre 3885 3885

1732 RCC pipe 1200 mm dia NP-3 spigot metre 5040 5040

1733 RCC pipe 1800 mm dia NP-3 spigot metre 9450 9450

1734 RCC pipe 450 mm dia NP-4 spigot metre 1733 1733

1735 RCC pipe 600 mm dia NP-4 spigot metre 2310 2310

1736 RCC pipe 900 mm dia NP-4 spigot metre 4494 4494

1737 RCC pipe 1000 mm dia NP-4 spigot metre 5565 5565

1738 RCC pipe 1200 mm dia NP-4 spigot metre 6510 6510

1739 RCC pipe 1800 mm dia NP-4 spigot metre 13650 13650

1854 Stoneware pipes grade A (60 cm long) 100 mm dia each 55 55

1855 Stoneware pipes grade A (60 cm long) 150 mm dia each 100 100

1856 Stoneware pipes grade A (60 cm long) 200 mm dia each 200 200

1857 Stoneware pipes grade A (60 cm long) 230 mm dia each 250 250

1858 Stoneware pipes grade A (60 cm long) 250 mm dia each 320 320

1859 Stoneware pipes grade A (60 cm long) 300 mm dia each 478 478

1863 Fire clay kitchen sink: 600x450x250 mm each 1283 1283

1871 White vitreous china laboratory sink 450x300x150 mm each 1500 1500

1872 White vitreous china laboratory sink 600x450x200 mm each 2500 2500

1875 White plastic seat (solid) with lid C.P. brass hinges and rubber each 400 400
buffers
1876 Black plastic seat (solid) with lid C.P. brass hinges and rubber each 310 310
buffers
1878 Shower rose C.P. brass for 15 to 20 mm inlet 100 mm dia each 100 100

1879 Shower rose C.P. brass for 15 to 20 mm inlet 150 mm dia each 125 125

1880 Dismenteled P or S trap scrap (approx wt 2kg) kg 22 22

1881 Spun yarn kg 50 50

1882 Strainer brass 40 mm dia 1.5 metre long each 600 600

1885 15 mm C.P. brass tap each 207 207

1889 C.P. brass toilet paper holder of standard size each 225 225

1890 Centrifugally SCI(spun) S & S P or S trap each 300 300

1891 C.I. trap for standard urinal with vent arm with operating and other each 170 170
couplings in C.P. brass: 50 mm dia
1893 C.I. trap for standard urinal with vent arm with operating and other each 225 225
couplings in C.P. brass: 80 mm dia
1895 C.P. brass trap 40 mm dia each 300 300

1896 100 mm S.C.I. trap with vent heel each 320 320

1897 100 mm S.C.I. trap with 100 mm inlet and 100 mm outlet each 271 271

1898 100 mm S.C.I. trap with 100 mm inlet and 75 mm outlet each 218 218

1900 S.W. gully trap P type 100x100 mm each 100 100

1902 S.W. gully trap P type 150x100 mm each 130 130

1904 S.W. gully trap P type 180x150 mm each 225 225

1913 Vitreous china lipped front urinal each 460 460

1915 Vitreous china squatting plate urinal each 1053 1053

1922 H.P. or L.P. ball valve with polythene floats: 15 mm dia each 210 210

1923 H.P. or L.P. ball valve with polythene floats: 20 mm dia each 235 235

1924 H.P. or L.P. ball valve with polythene floats: 25 mm dia each 230 230

1926 20 mm dia Gunmetal gate valve with wheel each 325 325

1927 Brass full way valve with C.I. wheel (screwed end) 25 mm dia each 350 350

1928 Brass full way valve with C.I. wheel (screwed end) 32 mm dia each 410 410

1929 Brass full way valve with C.I. wheel (screwed end) 40 mm dia each 480 480

1930 Brass full way valve with C.I. wheel (screwed end) 50 mm dia each 620 620

1931 Brass full way valve with C.I. wheel (screwed end) 65 mm dia each 1080 1080

1932 Brass full way valve with C.I. wheel (screwed end) 80 mm dia each 1620 1620

1933 Gunmetal non-return valve-horizontal (screwed end) 25 mm dia each 330 330

1934 Gunmetal non-return valve-horizontal (screwed end) 32 mm dia each 450 450

1935 Gunmetal non-return valve-horizontal (screwed end) 40 mm dia each 560 560

1936 Gunmetal non-return valve-horizontal (screwed end) 50 mm dia each 820 820

1937 Gunmetal non-return valve-horizontal (screwed end) 65 mm dia each 1490 1490

1938 Gunmetal non-return valve-horizontal (screwed end) 80 mm dia each 2120 2120

1940 C.I. sluice valve (with caps) class I: 100 mm dia each 2410 2410

1941 C.I. sluice valve (with caps) class I : 125 mm dia each 2600 2600

1942 C.I. sluice valve (with caps) class I: 150 mm dia each 3600 3600

1943 C.I. sluice valve (with caps) class I : 200 mm dia each 7500 7500

1944 C.I. sluice valve (with caps) class I : 250 mm dia each 10980 10980

1945 C.I. sluice valve (with caps) class I: 300 mm dia each 15500 15500

1947 Vitreous china flat back wash basin 630x450 mm each 725 725
1949 Vitreous china angle back wash basin 600x480 mm each 725 725

1950 Vitreous china angle back wash basin 400x400 mm each 425 425

1951 C.P. brass waste 32 mm each 80 80

1952 C.P. brass waste 40 mm each 95 95

1953 Vitreous china Indian type W.C. pan of size 580 mm each 450 450

1954 Vitreous china orrisa type W.C. pan of size 580 mm each 1200 1200

1955 Vitreous china pedestal type water closet each 1000 1000

1956 Bolts and nuts 16 mm dia 60 mm long each 11 11

1957 Bolts and nuts 16 mm dia 65 mm long each 12 12

1958 Bolts and nuts 20 mm dia 65 mm long each 15 15

1959 Bolts and nuts 20 mm dia 70 mm long each 17 17

1960 Bolts and nuts 20 mm dia 75 mm long each 16 16

1961 Bolts and nuts 20 mm dia 80 mm long each 18 18

1962 Bolts and nuts 24 mm dia 85 mm long each 28 28

1963 Bolts and nuts 24 mm dia 90 mm long each 32 32

1964 Bolts and nuts 27 mm dia 100 mm long each 38 38

1965 White vitreous china dual purpose closet (Anglo Indian W.C.) each 2500 2500
suitable for use as squatting pan or European type water closet as per
1966 manufacturer's
Floor mounted specifications
white vitrous china double trap syphonic WC with 10 each 9500 9500
litre cistern and all fittings & fixtures,seat cover etc
1970 Vitreous china foot rests 250x125x25 mm pair 100 100

1980 Fly ash cum 10 10

1984 Common burnt clay F.P.S. bricks tile class designation 10 1000 Nos 4500 4500

1986 Common burnt clay modular bricks class designation 12.5 1000 Nos 5000 5000

2200 Carriage of Steam coal tonne 121.29 121.29

2201 Carriage of Bricks 1000 Nos 283.01 283.01

2202 Carriage of Stone aggregate below 40 mm nominal size cum 106.13 106.13

2203 Carriage of Coarse sand cum 106.13 106.13

2204 Carriage of Timber cum 121.29 121.29

2205 Carriage of Steel tonne 94.34 94.34

2206 Carriage of Stone aggregate 40 mm nominal size and above cum 115.36 115.36

2207 Carriage of Brick tiles 1000 Nos 169.81 169.81

2208 Carriage of Lime cum 106.13 106.13

2209 Carriage of Cement tonne 94.34 94.34


2211 Carriage of Tar / Bitumen tonne 106.13 106.13

2215 Carriage of Soling stone & masonry stone cum 124.86 124.86

2216 Carriage of Stone blocks white & red sand stone & kota stone slab tonne 94.34 94.34

2224 Carriage of S.W. pipes 100 mm dia 100 metre 141.51 141.51

2225 Carriage of S.W. pipes 150 mm dia 100 metre 283.01 283.01

2226 Carriage of S.W. pipes 200 mm dia 100 metre 471.69 471.69

2228 Carriage of S.W. pipes 250 mm dia 100 metre 808.61 808.61

2229 Carriage of S.W. pipes 300 mm dia 100 metre 1010.76 1010.76

2241 Carriage of Good earth cum 132.66 132.66

2242 Carriage of Dump manure by mechanical transport upto 5 km lead cum 115.36 115.36

2260 Carriage of Brick aggregate cum 115.36 115.36

2261 Carriage of Fine sand cum 106.13 106.13

2262 Carriage of Flyash cum 106.13 106.13

2264 Carriage of Rubbish cum 106.13 106.13

2265 Carriage of Moorum cum 106.13 106.13

2266 Carriage of Surkhi cum 106.13 106.13

2267 Carriage of Stone dust cum 106.13 106.13

2268 Carriage of Marble dust and/or marble chips cum 106.13 106.13

2271 Carriage of G.I. pipes below 100 mm dia tonne 94.34 94.34

2272 Carriage of Stainless Steel pipes below 100 mm dia tonne 94.34 94.34

2273 Carriage of A.C.sheet and accessories tonne 94.34 94.34

2275 Carriage of R.C.C. pipes 100 mm dia 100 metre 231.98 231.98

2281 Carriage of R.C.C. pipes 150 mm dia 100 metre 386.63 386.63

2287 Carriage of R.C.C. pipes 250 mm dia 100 metre 893.73 893.73

2290 Carriage of R.C.C. pipes 300 mm dia 100 metre 1104.66 1104.66

2299 Carriage of R.C.C. pipes 450 & 500 mm dia 100 metre 2577.54 2577.54

2302 Carriage of G.I. sheet and accessories tonne 94.34 94.34

2303 Carriage of R.C.C. pipes 600,700,750 & 800 mm dia 100 metre 3866.3 3866.3

2308 Carriage of Plaster of paris tonne 94.34 94.34

2309 Carriage of Cast Iron fittings tonne 94.34 94.34

2311 Carriage of bajri cum 106.13 106.13

2314 Carriage of Barbed wire tonne 94.34 94.34


2317 Carriage of Sludge cum 115.36 115.36

2319 Carriage of Spun iron S & S pipes 100 mm dia 100 metre 231.98 231.98

2320 Carriage of Spun iron S & S pipes 125 mm dia 100 metre 309.87 309.87

2321 Carriage of Spun iron S & S pipes 150 mm dia 100 metre 386.63 386.63

2322 Carriage of Spun iron S & S pipes 200 mm dia 100 metre 628.92 628.92

2323 Carriage of Spun iron S & S pipes 250 mm dia 100 metre 893.73 893.73

2324 Carriage of Spun iron S & S pipes 300 mm dia 100 metre 1104.66 1104.66

2325 Carriage of Spun iron S & S pipes 350 mm dia 100 metre 1546.52 1546.52

2326 Carriage of Spun iron S & S pipes 400 mm dia 100 metre 2108.89 2108.89

2327 Carriage of Spun iron S & S pipes 450 mm dia 100 metre 2577.54 2577.54

2328 Carriage of Spun iron S & S pipes 500 mm dia 100 metre 2577.54 2577.54

2329 Carriage of Spun iron S & S pipes 600mm dia 100 metre 3866.3 3866.3

2330 Carriage of C.I. pipes 500 mm dia 100 metre 2577.54 2577.54

2331 Carriage of R.C.C. pipes 900 mm dia 100 metre 5799.46 5799.46

2332 Carriage of R.C.C. pipes 1000 mm dia 100 metre 7732.61 7732.61

2333 Carriage of R.C.C. pipes 1100 mm dia 100 metre 7732.61 7732.61

2334 Carriage of R.C.C. pipes 1200 mm dia 100 metre 7732.61 7732.61

2335 Carriage of sand cum 106.13 106.13

2336 Carriage of R.C.C. pipe above 1200 mm dia and upto 1800 mm dia 100 metre 7732.61 7732.61

2341 Carriage of Pig lead tonne 94.34 94.34

2342 Carriage of Solvent / Diesel. quintal 10.61 10.61

2343 Carriage of Ductile Iron pipes (k7) 100 mm dia 100 metre 231.98 231.98

2344 Carriage of Cast iron pipes 150 mm dia 100 metre 386.63 386.63

2345 Carriage of Cast iron pipes 200 mm dia 100 metre 628.92 628.92

2346 Carriage of Cast iron pipes 250 mm dia 100 metre 893.73 893.73

2347 Carriage of Cast iron pipes 300 mm dia 100 metre 1104.66 1104.66

2348 Carriage of Cast iron pipes 350 mm dia 100 metre 1546.52 1546.52

2349 Carriage of Cast iron pipes 400 mm dia 100 metre 2108.89 2108.89

2350 Carriage of Cast iron pipes 450 mm dia 100 metre 2577.54 2577.54

2351 Carriage of Cast iron pipes 500 mm dia 100 metre 2577.54 2577.54

2352 Carriage of Cast iron pipes 600 mm dia 100 metre 3866.3 3866.3

2353 Carriage of Cast iron pipes 700 mm dia 100 metre 3866.3 3866.3
2355 Carriage of Cast iron pipes 800 mm dia 100 metre 3866.3 3866.3

2356 Carriage of Cast iron pipes 900 mm dia 100 metre 5799.46 5799.46

2357 Carriage of Cast iron pipes 1000 mm dia 100 metre 7732.61 7732.61

2358 Carriage of Bamboo Mat corrugated sheets and accessories tonne 11500 11500

2391 Strips-Aluminium fluted 3.15 mm thick and 150 mm wide metre 278 278

2392 Strips Aluminium fluted 3.15 mm thick and 200 mm wide metre 370 370

2393 1 mm thick Stainless Steel Cover plate grade 304 kg 275 275

2394 Coupler 16 mm dia each 30 30

2395 Coupler 20 mm dia each 39 39

2396 Coupler 25 mm dia each 69.5 69.5

2397 Coupler 28 mm dia each 80 80

2398 Coupler 32 mm dia each 110 110

2399 Complete Roof Joint of 100 mm metre 2800 2800

2400 Complete Roof Joint of 150 mm metre 3200 3200

2401 Complete Roof Joint of 200 mm metre 4000 4000

2402 Epoxy adhesive kg 150 150

2403 Floor Joint of 100 mm metre 3100 3100

2404 Floor Joint of 150 mm metre 4000 4000

2405 Floor Joint of 200 mm metre 5400 5400

2406 Float glass sheet of nominal thickness 4 mm (weight not less than 10 sqm 300 300
kg/sqm)
2407 Float glass sheet of nominal thickness 5.5 mm (weight not less than sqm 500 500
13.50 kg/sqm)
2408 Float glass sheet of nominal thickness 8 mm (weight not less than sqm 610 610
20.00 kg/sqm)
2409 Wall Joint of 100 mm metre 2400 2400

2410 Wall Joint of 150 mm metre 2800 2800

2411 Wall Joint of 200 mm metre 3400 3400

2412 Ply wood 5 ply with commercial ply on both faces 6 mm thick sqm 300 300

2413 12 mm commercial ply sqm 500 500

2414 18 mm thick block board with commercial ply veneering on both sqm 760 760
side
2415 21 mm thick clear toughened Laminated glass for fins with holes sqm 6000 6000

2447 Hollock ballies 125 mm diameter metre 35 35

2449 Oxidised mild steel pull bolt lock (locking bolt) of size 85 mm x 42 each 60 60
mm with screws, bolts, nuts and washers complete
2451 Brass cupboard lock 6 levers of approved quality, 40 mm size each 55 55
2452 Brass cupboard lock 6 levers of approved quality, 50 mm size each 85 85

2453 Brass cupboard lock 6 levers of approved quality, 65 mm size each 90 90

2454 Brass cupboard lock 6 levers of approved quality, 75 mm size each 105 105

2455 Brass hanging type door stopper 150 mm each 75 75

2456 Hydraulic door closer bottle type M.S. body with necessary each 673 673
accessories and screws complete
2459 Anodised Aluminium hanging type door stopper each 19 19

2464 Anodised Aluminium pull bolt lock (locking bolt) of size 85 mm x each 46 46
42 mm with screws, bolts, nuts and washers complete
2465 Anodised Aluminium Casement stay 250 mm each 32 32

2466 Hollock wood in scantling 10 cudm 350 350

2467 Chromium plated Brass pull bolt lock (locking bolt) of size 85 mm x each 165 165
42 mm with screws, bolts, nuts and washers complete
2468 Nickled Chromium Brass cupboard lock 40 mm size each 60 60

2469 Nickled Chromium Brass cupboard lock 50 mm size each 70 70

2470 Nickled Chromium Brass cupboard lock 65 mm size each 95 95

2471 Nickled Chromium Brass cupboard lock 75 mm size each 120 120

2480 Ply wood 5 ply with teak ply on both faces 9 mm thick sqm 850 850

2481 Ply wood 5 ply with teak ply on one face and commercial ply on sqm 870 870
another face 9 mm thick
2483 Ply wood 7 ply with teak ply on one face and commercial ply on sqm 950 950
another face 9 mm thick
2484 Pre-laminated with decorative lamination on both side exterior Grade sqm 460 460
I MDF Board 12 mm thick confirming to IS: 14587
2485 Pre-laminated with decorative lamination on both side sqm 597 597
exteriorGrade-I MDF Board 18 mm thick confirming to IS: 14587
2486 Pre-laminated with decorative lamination one side and other side sqm 860 860
balancing lamination exterior Grade-I MDF Board 25 mm thick
2487 confirming to IS:
Pre-laminated with14587
decorative lamination one side and other side sqm 430 430
balancing lamination exterior Grade-I MDF Board 12 mm thick
2488 confirming to IS:14587
Pre-laminated with decorative lamination one side and other side sqm 565 565
balancing lamination exterior Grade-I MDF Board 18 mm thick
2489 confirming
PVC to IS:14587
edge bending tape 2.00 mm thick metre 20 20

2491 Pre laminated both side solid foam uPVC profile (45x20mm) metre 130 130

2492 Solid foam uPVC sheet 20mm thick pre laminated on both side sqm 2090 2090

2493 PVC edge beading metre 31 31

2494 Expandable fastner with plastic sleeve each 5 5

2500 Extra for selected planks of second class deodar wood 10 cudm 110 110

2504 Kiln seasoning of timber cum 750 750

2505 Hollock wood in planks 10 cudm 390 390

2506 Carben Steel galvanised (min 5 micron) dash fastner (min 5 micron) 10 Nos 260 260
of 10 mm dia double threaded 6.8 grade counter sunk head screw
2507 comprising
Carben Steelofgalvanised
10 mm dia(min
polyamide PA dash
5 micron) 6 grade sleave.
fastner (minSize 10 mm
5 micron) 10 Nos 300 300
x 60
of 10mm
mm dia double threaded 6.8 grade counter sunk head screw
comprising of 10 mm dia polyamide PA 6 grade sleave. Size 10mm
x 80 mm
2508 Carben Steel galvanised (min 5 micron) dash fastner (min 5 micron) 10 Nos 365 365
of 10 mm dia double threaded 6.8 grade counter sunk head screw
2509 comprising
Carben Steelofgalvanised
10 mm dia(min
polyamide PA dash
5 micron) 6 grade sleave.
fastner (minSize 10 mm
5 micron) 10 Nos 450 450
x 120
of mm dia double threaded 6.8 grade counter sunk head screw
10 mm
2510 comprising
Carben Steelofgalvanised
10 mm dia(min
polyamide PA dash
5 micron) 6 grade sleave.
fastner (minSize 10 mm
5 micron) 10 Nos 575 575
x 140
of mm dia double threaded 6.8 grade counter sunk head screw
10 mm
2602 comprisingburnt
Common of 10clay
mmF.P.S.
dia polyamide PA 6 bricks
(non modular) grade sleave. Size 10 mm
class designation 1000 Nos 5000 5000
x 160
7.5 mm burnt clay F.P.S. (non modular) bricks class
Common
2603 designation 5.0 Weather/structural non sag elastomeric PU sealant 1000 Nos 5000 5000
(600ml Sausage) for joints in RCC/ Brick/ Stone/ wood/ Ceramic/
2604 each 532 532

2605 Structural sealant - 6 mm x 12 mm metre 30 30

2606 Spacer tape 6.4 mm thick x 6 mm wide metre 20 20

2607 Weather Sealant - Non Staining (600 ml) each 325 325

2608 Weather Sealant - Normal (300 ml) each 98 98

2609 MS Brackets/Aluminium Alloy Brackets kg 100 100

2610 Silicon Gasket in Kg (Above 50 g / m) kg 465 465

2611 EPDM Gasket in Kg (Above 60 g / m) kg 150 150

2612 Anchor Fastner - M10 each 10 10

2613 SS Bolt with washer of different sizes for structural glazing / ACP each 35 35
Cladding
2614 SS Screws of sizes for structural glazing / ACP Cladding each 3 3

2615 Protective Tape metre 20 20

2616 GI flashing - 1.2 mm Thick kg 59 59

2617 6 mm thick High performance glass sqm 1000 1000

2618 6 mm thick clear heat strengthened glass sqm 650 650

2619 6 mm thick clear heat strengthened glass each 128 128

2620 ARMS GS HD - Top Hung -20"- Type P- Couple pair 1350 1350

2621 Connection Block for vision glass panel each 35 35

2622 Curtain wall striker for vision glass panel each 85 85

2623 Adjustable Fastening Pawl for vision glass panel each 35 35

2624 Corner drive for vision glass panel each 255 255

2625 Top wedge Block for vision glass panel each 120 120

2626 Glass wool of denisity @ 48 Kg / cum with black glass tissue (BGT) sqm 250 250

2627 SS Screws - # 8 x 19 each 6 6

2628 Weather Sealant - DC 789 cartridge 120 120

2629 Cement Board sqm 235 235

2630 Baker rod metre 5 5


2631 4 mm thick ACP sqm 1100 1100

2632 Fire Stop metre 480 480

2634 GI/Aluminium Sheet (0.8 mm thick) kg 55 55

2635 GI Screws of gauge 10, length 25 mm for fixing cement fibre board each 3 3
to C section
2636 GI Screws of gauge 10, length 45 mm for fixing cement fibre board each 3 3
to C section
2637 Vapour barrier sqm 175 175

2640 Clear.toughned interlayed,non-wired fire resistant glass panes of sqm 25000 25000
minimum 11 mm thickness (120 minutes fire rating)
2641 G. I U beading of 1.6 mm thick G. I sheet with ceramic tape. metre 245 245

2642 Ceramic tape 5 x20 mm size metre 410 410

2704 Aluminium Strip 40 mm wide and 2 mm thick kg 240 240

2708 T ruf Paver (500 x 500 x 40 mm) sqm 500 500

2709 Ceremic Tiles Pieces for Crazy Flooring quintal 135 135

2710 White marble makrana second quality plain veined stone pieces for quintal 150 150
crazy flooring
2711 FS800H Grade Flooring Panel (Size 600 mm x600 mm x32 mm) each 750 750

2712 Zinc Electroplated Pedestals - 300 mm each 140 140

2713 Zinc Electroplated Pedestals - 450 mm each 200 200

2714 Zinc Electroplated Tube Stinger each 66 66

2715 Machine Screw for Fixing each 2 2

2750 8 mm thick granite stone tiles (mirror polished of all shades) sqm 700 700

2751 8 mm thick marble tiles (polished) Raj Nagar sqm 400 400

2901 Stone Aggregate (Single size): 100 mm nominal size cum 1350 1350

2902 Stone Aggregate (Single size): 80 mm nominal size cum 1350 1350

2903 Stone chippings/ screenings 4.75 mm nominal size cum 1400 1400

2904 Stone chippings/ screenings 150 micron nominal size cum 1400 1400

2908 Over burnt (Jhama) Brick Aggregate: 120 mm to 40 mm size cum 500 500

2909 Over burnt (Jhama) Brick Aggregate: 90 mm to 40 mm size cum 480 480

2910 Stone chippings/ screenings 12.5/ 13.2 mm nominal size cum 1150 1150

2911 Stone chippings/ screenings 10/ 11.2 mm nominal size cum 1150 1150

2914 Solvent kg 25 25

2916 Paving Asphalt VG 10 of approved quality tonne 24000 24000

3002 Polyvinyl chloride sheet 400 micron thick sqm 40 40

3004 Stone ware spouts 100 mm dia 60 cm long each 40 40


3050 Galvanised steel corrugated sheets quintal 5600 5600

3080 Gunmetal non-return valve - vertical (screwed end) 25 mm dia each 350 350

3084 Gunmetal non-return valve - vertical (screwed end) 32 mm dia each 500 500

3088 Gunmetal non-return valve - vertical (screwed end) 40 mm dia each 700 700

3092 Gunmetal non-return valve - vertical (screwed end) 50 mm dia each 900 900

3096 Gunmetal non-return valve - vertical (screwed end) 65 mm dia each 1500 1500

3213 Vitreous china Surgeon type wash basin of size 660x460 mm each 1000 1000

3228 600x120 mm glass shelf with anodised aluminium angle frame, C.P. each 250 250
brass brackets and guard rail of standard size
3229 Vitreous china flat back wash basin 550x400 mm each 545 545

3300 Gunmetal non-return valve - vertical (screwed end) 80 mm dia each 2500 2500

3311 C.I. sluice valve (with caps) class II 100 mm each 2700 2700
dia
3314 C.I. sluice valve (with caps) class II 125 mm each 3200 3200
dia
3317 C.I. sluice valve (with caps) class II 150 mm each 4000 4000
dia
3320 C.I. sluice valve (with caps) class II 200 mm each 8900 8900
dia
3321 C.I. sluice valve (with caps) class II 250 mm each 14500 14500
dia
3326 C.I. sluice valve (with caps) class II 300 mm each 18200 18200
dia
3327 15 mm Battery Based Sensor Pillar Cock each 5800 5800

3617 C.P. Brass union 40mm dia each 200 200

3620 C.C.I. (spun) socketed soil, waste 100 mm dia and vent each 1200 1200
pipe 1.80
3621 C.C.I. (spun) socketed soil, waste 75 mm dia metres
and vent each 1100 1100
long:1.80
pipe
3624 S.C.I. S&S bends with access door metres
100 mm each 300 300
long:
dia
3625 S.C.I. S&S bends with access door 75 mm each 250 250
dia
3628 S.C.I. S&S bend 100 mm dia each 265 265

3629 S.C.I. S&S bend 75 mm dia each 195 195

3634 S.C.I. S&S heel rest sanitary bend 100 mm dia each 296 296

3635 S.C.I. S&S heel rest sanitary bend 75 mm dia each 250 250

3640 S.C.I. S&S single equal junctions 100x100x100 mm each 472 472

3641 S.C.I. S&S single equal junctions 75x75x75 mm each 330 330

3644 S.C.I. S&S single equal junctions with access door 100x100x 100 each 495 495
mm
3645 S.C.I. S&S single equal junctions with access door 75x75x75 mm each 373 373

3650 S.C.I. S&S double equal junctions 100x100x100x100 mm each 620 620

3651 S.C.I. S&S double equal junctions 75x75x75x75 mm each 462 462
3654 S.C.I. S&S double equal junctions with access door each 615 615
100x100x100x100 mm
3655 S.C.I. S&S double equal junctions with access door 75x75x75x75 each 480 480
mm
3660 S.C.I. S&S single unequal junctions 100x100x75 mm each 570 570

3664 S.C.I. S&S single unequal junctions with access door 100x100x75 each 640 640
mm
3670 S.C.I. S&S double unequal junctions 100x100x75x75 mm each 800 800

3674 S.C.I. S&S double unequal junctions with access door 100x100x each 850 850
75x75 mm
3681 S.C.I. S&S single equal invert 100x100x100 mm dia branch of each 425 425
required
3682 S.C.I. S&S single equal invert branch of required degree 75x75x 75 degree each 323 323
mm dia
3685 S.C.I. S&S double equal invert branch of required degree each 530 530
100x100x100x100 mm dia
3686 S.C.I. S&S double equal invert branch of required degree 75x75x each 425 425
75x75 mm dia
3690 S.C.I. S&S single unequal invert branch of required degree each 545 545
100x100x75 mm dia
3695 S.C.I. S&S double unequal invert branch of required degree each 725 725
100x100x75x75 mm dia
3699 S.C.I. S&S, 75 mm offset for 75 mm dia pipe each 225 225

3707 S.C.I. S&S, 150 mm offset for 75 mm dia pipe each 285 285

3708 S.C.I. S&S, 150 mm offset for 100 mm dia pipe each 390 390

3712 S.C.I. S&S, 114 mm offset for 75 mm dia pipe each 300 300

3713 S.C.I. S&S, 114 mm offset for 100 mm dia pipe each 383 383

3716 S.C.I. S&S, 152 mm offset for 75 mm dia pipe each 358 358

3717 S.C.I. S&S, 152 mm offset for 100 mm dia pipe each 455 455

3728 S.C.I. S&S door pieces 100 mm dia each 400 400

3729 S.C.I. S&S door pieces 75 mm dia each 295 295

3733 S.C.I. S&S, Slotted Cowl (Terminal Guard) 100 mm each 264 264

3734 S.C.I. S&S, Slotted Cowl (Terminal Guard) 75 mm each 210 210

3738 S.C.I. S&S, collars 100 mm each 279 279

3739 S.C.I. S&S, collars 75 mm each 170 170

3746 S.C.I. S&S, 75 mm offset for 75 mm dia pipe each 218 218

3747 S.C.I. S&S, 75 mm offset for 100 mm dia pipe each 363 363

3749 Vitreous china toilet paper holder of standard size each 100 100

3860 560 mm dia cover with frame (Heavy duty) each 9000 9000

3861 560 mm dia cover without frame (Heavy duty) each 5000 5000

3991 Galvanized iron (1.6 ± 0.2 mm) thick reinforcement for metre 66 66
small series casement window/door frame, sash,
3992 Galvanized iron series
mullion & small (1.6 ± sliding
0.2 mm) thick reinforcement
window frame for metre 71 71
big series casement window/door frame, sash, mullion,
big & small series sliding window frame
3993 Galvanized iron (1.6 ± 0.2 mm) thick reinforcement for metre 97 97
big series casement door sash
3994 Galvanized iron (1.6 ± 0.2 mm) thick reinforcement for metre 86 86
big series sliding window / door sash
3995 G. I fasteners 100 x 8 mm each 14 14

4001 Stainless steel (Grade-304)hollow section kg 220 220


round/square tubes
4002 Stainless steel bolts/square bar and plates kg 115 115

4006 Pressed steel door frames (mild steel sheet 1.60 mm) metre 190 190
Profile "B"
4007 Pressed steel door frames (mild steel sheet 1.60 mm) metre 210 210
Profile "C"
4008 Pressed steel door frames (mild steel sheet 1.60 mm) metre 240 240
Profile "E"
4009 Mild steel tubes hot finished welded type kg 57 57

4010 Mild steel tubes hot finished seamless type kg 67 67

4011 Mild steel tubes electric resistant or induction butt kg 47 47


welded
4012 Circular C.I. Box for ceiling fan internal dia 140 mm, 73 each 52 95
mm height, toplid of 1.5mm thick MS sheet
4013 Pulley 40 mm dia each 30 30

4201 Aluminium primer litre 110 110

4202 Red oxide Zinc chromate primer litre 110 110

4203 Copper acetate kg 285 285

4204 Hydrochloric acid kg 33 33

4205 Copper chloride kg 270 270

4206 Copper nitrate kg 210 210

4207 Ammonium chloride kg 20 20

5001 Mobil oil litre 315 315

5050 SS pipe 304 grades with press fit technology as per metre 650 650
JIS 3448 Standard 48.60 mm outer dia
5743 Coloured inter locking C.C. paver Block sqm 480 480

6001 White marble slab Makrana second quality plain sqm 1430 1430
veined 18 mm thick
6007 Pink marble slab plain 18 mm thick sqm 645 645

6010 Udaypur green marble slab plain 18 mm thick sqm 620 620

6019 Black Zebra marble slab plain 18 mm thick sqm 900 900

6501 Sand zone V (Jamuna) cum 800 800

7001 Brass 100mm mortice latch and lock with 6 levers each 210 210
without pair of handles
7003 Pair of Anodised Aluminium lever handles for 100 mm each 215 215
mortice latch and lock
7004 Vitreous china flat back wash basin 450x300 mm each 310 310

7005 Vitreous china 10 litres low level cistern without fittings each 715 715
7006 Vitreous china 10 litres low level cistern with fittings each 1240 1240

7008 F.P.S. (non modular) clay fly ash bricks class 1000 Nos 4800 4800
designation 7.5
7009 12.5 mm thick tapered edge gypsum plain borad sqm 155 155

7010 Galvanised Steel ceiling section (size 80x26x0.50 mm) metre 46 46

7011 Galvanised Steel perimetre Channel (Size metre 22 22


20x27x30x0.50 mm)
7012 Galvanised Steel intermediate Channel (Size metre 38 38
15x45x15x0.90 mm)
7013 Galvanised Steel angle hanger (Celling angle) (Size metre 12 12
25x10x0.50 mm)
7014 Galvanised Steel connecting clips (2.64 mm dia and each 4 4
230 mm long GI wire)
7015 Galvanised Steel soffit cleat (Size 27x37x25x0.60 mm) each 3 3

7016 Joint filler kg 26 26

7017 Joint finisher kg 23 23

7018 Joint tape roll roll 100 100

7019 Dash fastener / Chemical fastener each 14 14

7020 All drive screws (for gypsum board) 100 Nos 58 58

7021 Primer (for gypsum board) litre 85 85

7022 Chlorpyriphos 20% E.C. / Lindane 20% E.C. litre 150 150

7023 Chromium plated brackets (curtain rods) each 7 7

7024 Acid Proof cement tonne 7800 7800

7025 Self tapping pan head nickel coated mild steel screws 1000 Nos 525 525
of size 13 x 3.2 mm
7026 Fibre joint tape 50 mm wide (90 metre) roll each roll 165 165

7027 M.S. Butt hinges 125x90x4 mm 10 Nos 105 105

7028 12.5 mm thick Fully Perforated gypsum board sqm 410 410

7029 Galvanised wire mesh of average width of aperture 1.4 sqm 250 250
mm and nominal dia of wire 0.63 mm
7030 12.5 mm thick tapered edge gypsum fire resistant sqm 255 255
board
7031 12.5 mm thick tapered edge gypsum moisture resistant sqm 275 275
board
7032 Frosted glass sheet of nominal thickness 4 mm sqm 460 460
(weighing not less than 10 kg/sqm)
7033 Nickel plated M.S. pipe 25 mm dia metre 76 76

7034 Nickel plated M.S. pipe 20 mm dia metre 72 72

7035 Nickel plated M.S. Brackets for curtain rod 20 mm each 7 7

7036 Nickel plated M.S - Brackets for curtain rod 25 mm each 8 8

7040 Oxidised mild steel screws 35 mm 100 Nos 48 48

7042 Mild steel conduit pipe (heavy type) ISI marked-20 mm metre 42 42
dia
7043 Mild steel conduit pipe (heavy type) ISI marked-25 mm metre 54 54
dia
7044 Rolling shutters of 80x0.90 mm laths sqm 1300 1300

7045 Rolling shutters of 80x1.2 mm laths sqm 1375 1375

7046 Top cover of Rolling shutters 0.90 mm thick metre 450 450

7047 Top cover of Rolling shutters 1.20 mm thick metre 560 560

7048 Rawl plug 50 mm (designation 10 nos) each 25 25

7049 Teak wood lipping of size 25x3 mm in pelmets metre 14 14

7050 PU Primer sqm 60 60

7051 40 mm (average) PU spray having 40-45 kg/m3 sqm 400 400


density
7052 GI wire netting 3/4" x 24 G sqm 26 26

7053 400 G polythene sheet sqm 14 14

7055 Flat pressed 3 layer and graded particle board sqm 480 480
(medium density) Grade 1 conforming to IS : 3087 - 18
7056 Aluminium
mm thick tee channel (heavy duty) with rollers and metre 100 100
stop end
7059 Aluminium hanging floor door stopper with twin rubber each 40 40
& stopper
7060 Hydraulic door closer tubular type Aluminium section each 560 560
body
7063 Oxidised M.S.casement stay (straight peg type) 300 each 35 35
mm not less than 0.33 kg
7064 Oxidised M.S.casement stay (straight peg type) 250 each 30 30
mm not less than 0.28 kg
7065 Oxidised M.S. casement stay (straight peg type) 200 each 25 25
mm not less than 0.24 kg
7068 Extra for providing grilled rolling shutters with 8 mm dia sqm 500 500
M.S. rod
7070 Chequered precast cement concrete tiles 22 mm thick sqm 400 400
using marble chips of size 6mm - Light shade using
7071 White marble Raj Nagar plain 18 mm thick upto 0.50
white cement sqm 600 600
sqm area
7072 Wall mounted water closet of size 780 x 370x690 mm each 6000 6000

7073 Adjustable Vitreous China Cistern with fittings of each 1900 1900
flushing capacity 3 litre/ 6litre 9adjustibla to 4
7074 White Vetrious China Waterless Urinal of size
litre/8litre) each 9650 9650
600x330x315 mm
7075 Cistern with fittings for Waterless Urinal each 2290 2290

7076 Battery based infrared sensor operated white Vitreous each 4500 4500
Urinal of aprox.size 610x390x370 mm
7077 Acid and alkali resistant tiles 300x300 mm size, 10 mm 10 Nos 520 520
thick
7087 S.C.I. Tee 150 mm each 570 570

7090 Expanded polystyrene type N- Normal 50 mm thick sqm 125 125

7091 Expanded polystyrene type - SE 50 mm thick sqm 150 150

7095 Stainless steel kitchen sink - with drain board bowl each 2480 2480
depth 250 mm
7096 Stainless steel kitchen sink - with drain board 510 x each 3000 3000
1040 mmbowl depth 225 mm
7097 Stainless steel kitchen sink - with drain board 510 x each 2800 2800
1040 mm bowl depth 200 mm
7098 Stainless steel kitchen sink - with drain board each 2500 2500
510x1040 mm bowl depth 178 mm
7101 Stainless steel kitchen sink - without drain board each 1800 1800
610x510 mm bowl depth 200 mm
7102 Stainless steel kitchen sink - without drain board each 1200 1200
610x460 mm bowl depth 200 mm
7103 Stainless steel kitchen sink - without drain board each 1050 1050
470x420 mm bowl depth 178 mm
7104 Coloured Orissa pattern W.C. pan 580x440 mm each 1830 1830

7105 Coloured Pedestal type W.C. pan 580x440 mm each 860 860
(European type)
7106 Coloured Vitreous china 10 lit. low level cistern each 1050 1050

7107 Coloured (other than black) solid P.V.C. seat in each 390 390
European W.C. pan
7112 Circular shape 450 mm dia Mirror with Plastic moulded each 430 430
frame
7113 Rectangular shape 453x357 mm Mirror with Plastic each 290 290
moulded frame
7114 Oval shape 450x350 mm (outer dimensions) Mirror each 340 340
with Plastic moulded frame
7115 Rectangular shape 1500x450 mm Mirror with Plastic each 670 670
moulded frame
7116 Hard board 6 mm thick sqm 115 115

7117 Semi Rigid PVC waste pipe for sink and wash basin 32 each 25 25
mm dia with length not less than 700 mm i/c PVC
7118 Semi
wasteRigid PVC waste pipe for sink and wash basin 40
fittings each 33 33
mm dia with length not less than 700 mm i/c PVC
7119 Flexible (coil shaped) PVC waste pipe for sink and
waste fittings each 35 35
wash basin 32 mm dia with length not less than 700
7120 Flexible
mm i/c PVC(coilwaste
shaped) PVC waste pipe for sink and
fittings each 35 35
wash basin 40 mm dia with length not less than 700
7121 Bottle
mm i/cTrap
PVC waste fittings each 620 620

7122 CP Brass Single lever telephonic wall mixer of each 4500 4500
approved make
7123 Coloured High density polyethylene / poly propylene each 550 550
10 lit. (full flush) capacity controlled low level flushing
7126 White
cisternVitreous china 10 litre (full flush) capacity
with fittings each 700 700
controlled low level flushing cistern with all fittings
7127 Coloured Vitreous china 10 litre (full flush) capacity each 1150 1150
controlled low level flushing cistern with all fittings
7128 S.W. intercepting trap 100 mm dia each 185 185

7129 S.W. intercepting trap 150 mm dia each 240 240

7130 Rectangular shape 600x450 mm precast R.C.C. each 675 675


manhole cover with frame - L.D. - 25
7131 Square shape 450x450 mm precast R.C.C. manhole each 575 575
cover with frame - L.D. - 25
7132 Circular shape 450 mm dia precast R.C.C. manhole each 575 575
cover with frame - L.D. - 25
7133 Rectangular shape 500x500 mm precast R.C.C. each 670 670
manhole cover with frame - M.D. - 10
7134 Circular shape 500 mm dia precast R.C.C. manhole each 575 575
cover with frame- M.D.-10
7135 Circular shape 560 mm dia precast R.C.C. manhole each 880 880
cover with frame - H.D. - 20
7136 Circular shape 560 mm dia precast R.C.C. manhole each 1170 1170
cover with frame - E.H.D. - 35
7137 Factory made 35 mm thick shutters with laminated sqm 1620 1620
veneer lumber styles & rails as per TADS 15:1995 and
7139 Factory
panels ofmade 35 thick
12 mm mm thick
plainshutters with laminated
type-I, medium density flat sqm 1720 1720
veneer
pressedlumber stylesgraded
three layer, & rails particle
as per TADS
board 15:1995 and
(FPT-I) as
7143 Factory
panels ofmade 35 thick
12 mm mm thick
both shutters with laminated
sides prelaminated type-I, sqm 1910 1910
veneer
mediumlumber
densitystyles & rails as
flat pressed perlayer,
three TADSgraded
15:1995 and
7151 Factory
panels ofmade 30 thick
12 mm mm thick shutters
one side with laminated
prelaminated type-I, sqm 1620 1620
veneer lumber
and other styles & rails
side balancing as per TADS
lamination, medium 15:1995 and
density
7154 Factory
panels ofmade
sheet35glass
mm using
thick shutters withglass
10 kg/ sqm laminated
panes sqm 1620 1620
veneer lumber styles & rails as per TADS 15:1995 and
7155 Factory
panels ofmade 30 mmwire
galvanised thickgauge
shutters
withwith laminated
average width of sqm 1430 1430
veneer
aperturelumber
1.4 mmstyles & rails
in both as per with
directions TADS 15:1995
wire and
of dia 0.63
7157 Laminated veneer lumber
panels of galvanised confirming
wire gauge with to TADS width
average 15:1995of 10 cudm 700 700
manufactured
aperture 1.4 mm in factory
in both in frames of
directions doors,
with wirewindows
of dia 0.63
7178 Chemical ASTMC-type I kg 105 105

7181 C.I. pile shoe kg 48 48

7182 M.S. clamps for pile shoe of 35 kg per pile kg 43 43

7183 Bentonite of 35 kg per pile tonne 2960 2960

7184 Oxidised M.S. safety chain (weighing not less than 450 each 57 57
gms) for door
7187 C.I. grating 150 mm dia, weighing not less than 440 each 27 27
gm
7188 U-PVC pipes (working pressure 4 kg / cm2) Single metre 70 220
socketed pipe 75 mm dia
7189 U-PVC pipes (working pressure 4 kg / cm2) Single metre 130 250
socketed pipe 110 mm dia
7190 U-PVC pipes (working pressure 4 kg / cm2) Rubber each 8 15
(Seal) Ring 75 mm dia
7191 U-PVC pipes (working pressure 4 kg / cm2) Rubber each 11 20
(Seal) Ring 110 mm dia
7192 uPVC coupler for UPVC drainage pipes 75 mm each 18 18

7193 uPVC coupler for UPVC drainage pipes 110 mm each 39 150

7194 uPVC pushfit coupler (single) 75 mm thick each 18 110

7195 uPVC pushfit coupler (single) 110 mm thick each 32 150

7196 uPVC single equal Tee (without door) 75x75x75 mm each 46 150

7197 uPVC single equal Tee (without door) 110x110x110 each 81 150
mm
7198 uPVC single equal Tee (with door) 75x75x75 mm each 59 120

7199 uPVC single equal Tee (with door) 110x110x110 mm each 92 150

7208 UPVC bend 87.5° 75 mm bend each 35 150

7209 UPVC bend 87.5° 110 mm bend each 59 180

7212 UPVC plain shoe 75 mm bend each 27 150


7213 UPVC plain shoe 110 mm bend each 47 180

7214 UPVC pipe clip 75 mm bend each 15 30

7215 UPVC pipe clip 110 mm bend each 14 40

7231 Resin Bonded Glass wool 16 kg/m3 : 50 mm thick sqm 100 100

7232 Resin Bonded Glass wool 24 kg/irP : 50 mm thick sqm 143 143

7233 Fibre glass tissue reinforcement Type II Grade i sqm 82 82

7236 Precast chequered cement tiles 22 mm thick Dark sqm 225 225
shade using ordinary cement
7237 Precast chequered cement tiles 22 mm thick medium sqm 335 335
shade using 50% white cement 50% ordinary cement
7238 High Albedo paint kg 230 230

7239 Epoxy paint litre 230 230

7240 Fire retardant paint litre 260 260

7241 Melamine polish litre 280 280

7244 Table rubbed polished stone 18 mm thick (75x50cm) sqm 1620 1620
Agaria Marble stone - 18 mm thick
7245 Table rubbed polished stone 18mm thick (75x50cm) sqm 1620 1620
Granite stone-18 mm thick
7246 Vertical load testing (initial) of piles in accordance with per test 40000 40000
IS : 2911 (Part-IV) including installation of loading
7247 platform and preparation of pile head or construction of per test 45000 45000
test cap and dismantling of test cap after test etc.
7248 Vertical load testing (initial) of piles in accordance with per test 50000 50000
IS : 2911 (Part-IV) including installation of loading
7249 Cyclic
platformvertical load testingofofpile
and preparation piles in accordance
head or constructionwithof - per test 15000 15000
IS
test: 2911 (Part
cap and IV) including
dismantling preparation
of test cap afteroftest
pileetc.
head
7250 Cyclic
etc. forvertical loadup
Single pile testing
to 50of pilescapacity
tonne in accordance with - per test 23000 23000
IS : 2911 (Part IV) including preparation of pile head
7251 Cyclic
etc. forvertical loadabove
Single pile testing50 oftonne
piles in accordance
capacity pile andwithup - per test 29500 29500
IS : 2911
to 100 (Part
tonne IV) including
capacity pile preparation of pile head
7252 Lateral
etc. for load
Group testing
of twoofpiles
single
uppile in tonne
to 50 accordance
capacitywith per test 15000 15000
IS : 2911 part -IV for determining safe allowable lateral
each
7253 Lateral
load on load testing
pile up to 50oftonne
singlecapacity
pile in accordance with per test 23600 23600
IS : 2911 part -IV for determining safe allowable lateral
7254 Hardening
load on pilecompound
above 50 tonne capacity litre 38 38

7255 Road marking paint (spirit based) litre 115 115

7256 Superior quality road marking paint (water based) litre 135 135

7257 C.P. Brass bibcock 15 mm each 290 290

7258 C.P. Brass long nose bibcock 15 mm each 430 430

7259 C.P. Brass long body bibcock 15 mm each 385 385

7260 C.P. Brass stop cock (concealed) 15 mm each 430 430

7261 C.P. Brass angle valve 15 mm each 375 375

7266 Pressed clay tiles 20mm thick 250x250 mm size 1000 Nos 8600 8600

7267 Plain ceiling tiles (BWP type phenol formaldehyde each 115 115
synthetic resin bonded) (600x600x12 mm)
7268 Semi perforated ceiling tiles (600x600x12 mm) each 107 107

7269 25 mm thick particle board sqm 460 460

7270 30 mm thick prelaminated flush door shutter sqm 810 810

7271 Second class teak wood lipping 25 mm wide x 12 mm metre 29 29


thick
7272 25 mm thick melamine faced prelaminated three layer sqm 900 900
particle board
7273 Resin Bonded Rockwool 48 kg/m3 sqm 120 120

7274 Glass wool 50 mm thick sqm 238 238

7280 Waste plastic additive tonne 40000 40000

7281 Chemical ASTMC-type II kg 165 165

7295 Granite of any colour, 18 mm thick (slab area upto sqm 1600 1600
0.50 sqm)
7296 Granite of any colour, 30 mm thick (slab area upto sqm 1800 1800
0.50 sqm)
7297 Granite of any colour, 18 mm thick (slab area above sqm 1800 1800
0.50 sqm)
7306 Aluminium T or L sections kg 190 190

7307 For flush door shutters Extra for providing teak sqm 330 330
veneering on one side instead of commercial
7309 Paving Asphalt of grade VG-30 of approved quality
veneering tonne 39570 39570

7312 Expandable fastener with plastic sleeve and M.S. each 10 10


screws : 25 mm long
7313 Expandable fastener with plastic sleeve and M.S. each 10 10
screws : 32 mm long
7314 Expandable fastener with plastic sleeve and M.S. each 13 13
screws : 40 mm long
7315 Expandable fastener with plastic sleeve and M.S. each 14 14
screws. 50 mm long
7318 Plasticizer / super plasticizer kg 36 36

7319 Wall form panel 1250x500 mm each 860 860

7320 Tie bolt 12 mm dia 100 mm length each 38 38

7321 Tie bolt 12 mm dia 150 mm length each 48 48

7322 Tie bolt 20 mm dia 150 mm length each 57 57

7323 Tie bolt 20 mm dia 225 mm length each 67 67

7324 Spring coil 12 mm each 15 15

7325 Plastic cone 12 mm dia each 17 17

7326 Corner angle 45x45x5 mm 1.50 m long each 240 240

7327 100 mm channel shoulder 2.5 m long each 910 910

7328 Double clip (bridge clip) each 76 76

7329 Single clip each 59 59

7330 M.S. tube 40 mm dia metre 215 215


7331 Wall form panel 1250x450 mm each 860 860

7332 Corner angle 45x45x5 mm 2.50 m long each 255 255

7333 Column clamp 450x1070 mm each 965 965

7334 Prop 2 m ( 2-3.5 m) each 635 635

7335 Binding wire kg 46 46

7336 Lock Bar (E 250) - 10 thick MS Plate kg 76 76

7338 Gun metal cramp kg 315 315

7339 Stainless steel cramp kg 290 290

7340 Stainless steel pin kg 182 182

7342 Adjustable span ESO+SI (2.35-3.40) each 1480 1480

7343 Adjustable telescopic prop 3 m (2.02-3.75 m) each 955 955

7344 Beam clamp 300-380 mm (450-1070 mm) each set 355 355

7345 Prop 4 m each 910 910

7346 Double coupler each 46 46

7347 Cadmium plated full threaded steel screws (30x4 mm 100 Nos 27 27
dia)
7348 Aluminium washer 2 mm thick 15 mm dia 100 Nos 10 10

7349 12 mm M.S. 'U' beading metre 14 14

7354 Plastic encapsulated M.S. foot rest 30x20x15 cm each 110 110

7358 Flushing Cistern P.V.C. 10 litre capacity (low level) each 575 575
(White) (with fittings, accessories and flush pipe)
7359 P.V.C. automatic flushing cistern 5 litre capacity each 470 470

7361 P.V.C. automatic flushing cistern 10 litre capacity each 510 510

7363 15 mm C.P. brass tap with elbow operation lever each 430 430

7364 White glazed fire clay draining board 600x450x25 mm each 525 525

7366 Glass reinforced Gypsum ( GRG) board 12.5 mm thick sqm 240 240

7367 Galvanised M.S. sheet 0.5 mm thick pressed channel metre 57 57


section of size 50x32 mm
7368 GFRG Panel of 124 mm thick sqm 847.46 847.46

7369 Galvanised M.S. sheet 0.50 mm thick pressed stud : metre 71 71


48x34x36 mm
7375 G.I. flush pipe and C.P. brass spreader including C.P. each 445 445
connecting pipe Single lipped urinal
7376 G.I. flush pipe and C.P. brass spreader including C.P. each 765 765
connecting pipe Range of two lipped urinals
7377 G.i. flush pipe and C.P. brass spreader including C.P. each 1050 1050
connecting pipe Range of three lipped urinals
7378 G.I. flush pipe and C.P. brass spreader including C.P. each 1430 1430
connecting pipe Range of four lipped urinals
7379 White vitreous china clay half stall urinal flat back each 865 865
580x380x350 mm or angle back 450x375x350 mm
with waste fittings as per IS:2556
7380 Precast R.C.C. grating with frame 500x450 mm each 620 620
horizontal grating
7381 Precast R.C.C. grating with frame 450x100 mm each 235 235
vertical grating
7382 Bitumen emulsion rapid setting (R.S.) confirming to IS : tonne 19000 19000
8887
7383 12 mm dia 50 mm long wedge type expanded zinc each 7 7
alloy dash fastener
7385 3 mm thick translucent white acrylic plastic sheet sqm 550 550

7386 12 mm thick particle board ceiling tile sqm 110 110

7387 Spigot for standard jointing kg 43 43

7388 Dash hold fastener 12.5 mm dia, 50 mm long with 6 each 11 11


mm dia bolt
7389 Anodising 15 microns on aluminium sections kg 38 38

7390 EPDM Gasket for uPVC window/door metre 19 19

7391 Anodising 25 microns on aluminium sections kg 48 48

7392 Powder coating 50 microns on aluminium sections kg 61 61

7393 Polyester powder coating 50 microns on aluminium kg 67 67


sections
7394 Double action hydraulic floor spring with stainless steel each 1500 1500
cover plate
7395 6 mm dia G.I. adjustable hangers including clips (up to each 20 20
1.2 m length)
7396 Double action hydraulic floor spring with brass cover each 1620 1620
plate
7397 Base Jack each 145 145

7398 Challies each 765 765

7399 Cup locks each 48 48

7400 15 mm PTMT bib cock each 71 71

7401 15 mm PTMT bib cock with flange (fancy) each 105 105

7402 15 mm PTMT bib cock long body with flange each 116 116

7403 15 mm dia PTMT stop cock (male thread) each 71 71

7405 20 mm dia PTMT stop cock each 97 97

7406 PTMT pillar cock each 125 125

7407 PTMT push cock 15 mm dia each 62 62

7408 PTMT push cock 12 mm dia 20 mm BSP each 57 57

7409 PTMT grating 100 mm dia each 20 20

7410 PTMT Pillar cock (fancy) 15 mm foam flow each 138 138

7411 125 mm grating with waste hole each 30 30

7412 Rectangular type with openable circular lid 150 mm each 118 118
size 18 mm high with 100 mm dia (110 gm)
7415 Double acting air valve 50 mm each 3715 3715
7416 Double acting air valve 80 mm each 4525 4525

7417 Double acting air valve 100 mm each 5910 5910

7418 Water meter (including testing charges) 80 mm each 2030 2030

7419 Water meter (including testing charges) 100 mm each 3143 3143

7420 Water meter (including testing charges) 150 mm each 4765 4765

7421 Water meter (including testing charges) 200 mm each 5145 5145

7422 Dirt box strainer 80 mm each 2680 2680

7423 Dirt box strainer 100 mm each 4370 4370

7424 Dirt box strainer 150 mm each 5540 5540

7425 Dirt box strainer 200 mm each 7860 7860

7426 Cat's eye each 100 100

7427 Water stops Serrated with central bulb (225 mm wide, metre 200 200
8-11 mm thick)
7428 Water stops Dumb bell with central bulb metre 160 160

7429 Kickers metre 185 185

7430 Wedge expansion hold fastener 1/4" or 6 mm each 11 11

7431 Wedge expansion hold fastener 3/8" or 10 mm each 11 11

7432 Wedge expansion hold fastener 1/2" or 12 mm each 27 27

7439 8mm thick (mirror polished tiles machine cut edge) Raj sqm 500 500
Nagar white
7442 Wheel 75 mm dia. 40 mm wide each 62 62

7443 Aluminium single cleat of size 30x32x3 mm each 14 14

7444 Aluminium grip strip of size 50x12x2 mm each 11 11

7445 25 mm thick prelaminated flush door shutter both side sqm 800 800
decorative
7449 Aluminium U beading kg 210 210

7451 Glass sheet (Pin headed) 4 mm thick sqm 305 305

7452 Raj nagar plain white marble (table rubbed and sqm 575 575
polished) 18 mm thick (slab area upto 0.50 sqm)
7453 Raj nagar plain white marble (table rubbed and sqm 690 690
polished) 18 mm thick (slab area more than 0.50 sqm)
7466 Second class deodar teak wood lipping 30 mm wide x metre 24 24
12 mm thick
7468 Veneered particle board with commercial veneering on sqm 500 500
both sides 12 mm thick
7477 Prelaminated particle board with one side decorative sqm 540 540
and other side balancing lamination, flat pressed 3
7478 Prelaminated
layer & gradedparticle
(mediumboard with one
density) Gradeside decorative
i, Type II sqm 650 650
and other side
conforming balancing
to IS : 12823 lamination, flat pressed
(exterior grade) 3
12 mm thick
7479 Prelaminated particle board with one side
layer & graded (medium density) Grade I, Type II decorative sqm 900 900
and other side
conforming balancing
to IS : 12823 lamination, flat pressed
(exterior grade) 3
18 mm thick
7480 Prelaminated
layer & gradedparticle
(mediumboard with both
density) Grade sides decorative
I, Type II sqm 575 575
lamination,
conforming flat pressed
to IS : 128233 (exterior
layer & graded
grade) (medium
25 mm thick
density) Grade I, Type II conforming to IS : 12823
(exterior grade) 12 mm thick
7485 Oxidised M. S. hinges finished with nickel plating 50 40 40
mm (Over all width)
7486 Oxidised M. S. hinges finished with nickel plating 65 52 52
mm (Over all width)
7491 PTMT - Waste Coupling 31/32 mm each 34 34

7492 PTMT - Waste Coupling 38/40 mm each 48 48

7493 PTMT - Bottle Trap 31/32 mm each 210 210

7494 PTMT - Bottle Trap 38/40 mm each 220 220

7495 PTMT Ball Cock 15mm complete with Epoxy Coated each 100 100
Aluminium Rod & H.D. Ball
7496 PTMT Ball Cock 20mm complete with Epoxy Coated each 135 135
Aluminium Rod & H.D. Ball
7497 PTMT Ball Cock 25mm complete with Epoxy Coated each 290 290
Aluminium Rod & H.D. Ball
7498 PTMT Ball Cock 40mm complete with Epoxy Coated each 480 480
Aluminium Rod & H.D. Ball
7499 PTMT Ball Cock 50mm complete with Epoxy Coated each 870 870
Aluminium Rod & H.D. Ball
7500 PTMT Angle Stop cock with Flange 15 mm each 100 100

7501 PTMT Swiveling shower 15 mm each 70 70

7503 PTMT Liquid Soap Container of 400 ml capacity each 105 105

7504 PTMT - Towel Ring 215x200x37 mm each 130 130

7505 PTMT - Towel Rail (450 mm long ) each 135 135

7506 PTMT - Towel Rail (600 mm long) each 165 165

7507 PTMT Shelf 450x124x36 mm each 200 200

7508 PTMT - Urinal Spreader 15 mm each 76 76

7509 PTMT Soap Dish/Holder 138x102x75 mm each 84 84

7512 PTMT handle 125x34x24 mm each 24 24

7513 PTMT handle 150x34x24 mm each 24 24

7514 PTMT butt hinges 75x60x10 mm each 33 33

7515 PTMT butt hinges 100x75x10 mm each 43 43

7516 PTMT Tower bolt 152x42x18 mm each 48 48

7517 PTMT Tower bolt 202x42x18 mm each 67 67

7518 PTMT door catcher 72x42 mm each 24 24

7552 Coir veneered board 4 mm thick sqm 290 290

7553 Coir veneered board 6 mm thick sqm 385 385

7555 Coir veneered board 12 mm thick sqm 670 670

7556 Coir veneered board 18 mm thick sqm 1000 1000

7621 Hubless centrifugally cast (spun) iron pipes as per IS metre 700 700
15905 - 100 mm dia (3000 mm length pipe)
7622 Hubless centrifugally cast (spun) iron pipes as per IS metre 570 570
15905 - 75 mm dia (3000 mm length pipe)
7623 Hubless centrifugally cast (spun) iron plain bend as per each 230 230
IS 15905 -100 mm dia
7624 Hubless centrifugally cast (spun) iron plain bend as per each 160 160
IS 15905 -75 mm dia
7625 Hubless centrifugally cast (spun) iron double equal each 510 510
plain junction as per IS 15905 - 100x100x100x100 mm
7626 Hubless
dia centrifugally cast (spun) iron double equal each 275 275
plain junction asper IS 15905 - 75x75x75x75 mm dia
7627 Hubless centrifugally cast (spun) iron single equal each 400 400
plain junction as per IS 15905 - 100x100x100 mm dia
7628 Hubless centrifugally cast (spun) iron single equal each 215 215
plain junction as per IS 15905 - 75x75x75 mm dia
7629 Hubless centrifugally cast (spun) iron double unequal each 400 400
plain junction as per IS 15905 - 100x100x75x75 mm
7630 Hubless
dia centrifugally cast (spun) iron single unequal each 375 375
plain junction as per IS 15905 - 100x100x75 mm dia
7631 Hubless centrifugally cast (spun) iron double equal each 625 625
plain invert branch as per IS 15905 -
7632 Hubless centrifugally
100x100x100x100 mm cast
dia(spun) iron single equal each 390 390
plain invert branch as per IS 15905 - 100x100x100 mm
7633 Hubless
dia centrifugally cast (spun) iron single equal each 260 260
plain invert branch as per IS 15905 - 75x75x75 mm dia
7634 Hubless centrifugally cast (spun) iron single unequal each 430 430
plain invert branch 45 degree as per IS 15905 -
7635 Hubless
100x100x75centrifugally
mm dia cast (spun) iron 65 mm offset each 360 360
with 100 mm dia pipe as per IS 15905
7636 Hubless centrifugally cast (spun) iron 65 mm offset each 295 295
with 75 mm dia pipe as per IS 15905
7637 Hubless centrifugally cast (spun) iron 130 mm offset each 440 440
with 100 mmdia pipe as per IS 15905
7638 Hubless centrifugally cast (spun) iron 130 mm offset each 310 310
with 75 mm dia pipe as per IS 15905
7639 Hubless centrifugally cast (spun) iron bend with access each 365 365
door - 100 mm dia as per IS 15905
7640 Hubless centrifugally cast (spun) iron bend with access each 290 290
door - 75 mm dia as per IS 15905
7641 Hubless centrifugally cast (spun) iron terminal guard each 270 270
(slotted cowl) -100 mm dia as per IS 15905
7642 Hubless centrifugally cast (spun) iron trap with 100 each 540 540
mm inlet and 100 mm outlet as per IS 15905
7643 Hubless centrifugally cast (spun) iron trap with 100 each 385 385
mm inlet and 75 mm outlet as per IS 15905
7644 SS 304 grade shielded coupling with EPDM rubber each 275 275
gasket for 100 mm dia Hubless centrifugally cast
7645 SS 304iron
(spun) grade shielded coupling with EPDM rubber each 250 250
gasket for 75 mm dia Hubless centrifugally cast (spun)
7651 Ductile
iron Iron class K - 9 pipe Conforming to I.S. 8329 metre 765 765
100 mm dia
7652 Ductile Iron class K - 9 pipe Conforming to I.S. 8329 - metre 1150 1150
150 mm dia
7653 Ductile Iron class K - 9 pipe Conforming to I.S. 8329 - metre 1575 1575
200 mm dia
7654 Ductile Iron class K - 9 pipe Conforming to I.S. 8329 - metre 2200 2200
250 mm dia
7655 Ductile Iron class K - 9 pipe Conforming to 1.S. 8329 - metre 2750 2750
300 mm dia
7656 Ductile Iron class K - 9 pipe Conforming to I.S. 8329 - metre 3350 3350
350 mm dia
7657 Ductile Iron class K - 9 pipe Conforming to 1.S. 8329 - metre 4300 4300
400 mm dia
7658 Ductile Iron class K - 9 pipe Conforming to 1.S. 8329 - metre 5000 5000
450 mm dia
7659 Ductile Iron class K - 9 pipe Conforming to I.S. 8329 - metre 6270 6270
500 mm dia
7660 Ductile Iron class K -9 pipe Conforming to I.S. 8329 - metre 7560 7560
600 mm dia
7661 Ductile Iron class K - 9 pipe Conforming to I.S. 8329 - metre 10500 10500
700 mm dia
7662 Ductile Iron class K - 9 pipe Conforming to I.S. 8329 - metre 11350 11350
750 mm dia
7663 Ductile Iron class K - 9 pipe Conforming to I.S. 8329 - metre 11450 11450
800 mm dia
7664 Ductile Iron class K - 9 pipe Conforming to I.S. 8329 - metre 13900 13900
900 mm dia
7665 Ductile Iron class K - 9 pipe Conforming to I.S. 8329 - metre 15550 15550
1000 mm dia
7666 Rubber Gaskets Conforming to I.S 5382 of S.B.R each 29 29
quality 100 mm dia
7668 Rubber Gaskets Conforming to I.S 5382 of S.B.R each 36 36
quality 150 mm dia
7669 Rubber Gaskets Conforming to I.S 5382 of S.B.R each 63 63
quality 200 mm dia
7670 Rubber Gaskets Conforming to I.S 5382 of S.B.R each 74 74
quality 250 mm dia
7671 Rubber Gaskets Conforming to I.S 5382 of S.B.R each 110 110
quality 300 mm dia
7672 Rubber Gaskets Conforming to I.S 5382 of S.B.R each 126 126
quality 350 mm dia
7673 Rubber Gaskets Conforming to I.S 5382 of S.B.R each 230 230
quality 400 mm dia
7674 Rubber Gaskets Conforming to I.S 5382 of S.B.R each 270 270
quality 450 mm dia
7675 Rubber Gaskets Conforming to I.S 5382 of S.B.R each 290 290
quality 500 mm dia
7676 Rubber Gaskets Conforming to I.S 5382 of S.B.R each 365 365
quality 600 mm dia
7677 Rubber Gaskets Conforming to I.S 5382 of S.B.R each 550 550
quality 700 mm dia
7678 Rubber Gaskets Conforming to I.S 5382 of S.B.R each 660 660
quality 750 mm dia
7679 Rubber Gaskets Conforming to I.S 5382 of S.B.R each 725 725
quality 800 mm dia
7680 Rubber Gaskets Conforming to I.S 5382 of S.B.R each 960 960
quality 900 mm dia
7681 Rubber Gaskets Conforming to I.S 5382 of S.B.R each 1145 1145
quality 1000 mm dia
7682 Ductile Iron K - 12 specials suitable for push on jointing quintal 12400 12400
up to 600 mm dia
7683 Ductile Iron K - 12 specials suitable for push on jointing quintal 17200 17200
over 600 mm dia
7684 Ductile Iron specials suitable for mechanical jointing as quintal 13050 13050
per I.S. 9523 - up to 600 mm dia
7685 Ductile Iron Specials suitable for mechanical jointing quintal 18750 18750
as per I.S. 9523 over 600 mm dia
7686 Ductile Iron Pipe Class K-9 flanges and welding 100 metre 1100 1100
mm dia
7687 Ductile Iron Pipe Class K-9 flanges and welding 150 metre 1650 1650
mm dia
7688 Ductile Iron Pipe Class K-9 flanges and welding 200 metre 2075 2075
mm dia
7689 Ductile Iron Pipe Class K-9 flanges and welding 250 metre 2950 2950
mm dia
7690 Ductile Iron Pipe Class K-9 flanges and welding 300 metre 3790 3790
mm dia
7691 Ductile Iron Pipe Class K-9 flanges and welding 350 metre 4780 4780
mm dia
7692 Ductile Iron Pipe Class K-9 flanges and welding 400 metre 6150 6150
mm dia
7693 Ductile Iron Pipe Class K-9 flanges and welding 450 metre 6453 6453
mm dia
7694 Ductile Iron Pipe Class K-9 flanges and welding 500 metre 9180 9180
mm dia
7695 Ductile Iron Pipe Class K-9 flanges and welding 600 metre 12150 12150
mm dia
7696 Ductile Iron Pipe Class K-9 flanges and welding 700 metre 14370 14370
mm dia
7697 S&S Centrifugally (Spun) C.I. Pipe class LA 100 mm metre 857 857
dia
7698 S&S Centrifugally (Spun) C.I. Pipe class LA 125 mm metre 1067 1067
dia
7699 S&S Centrifugally (Spun) C.I. Pipe class LA 150 mm metre 1286 1286
dia
7700 S&S Centrifugally (Spun) C.I. Pipe class LA 200 mm metre 2190 2190
dia
7701 S&S Centrifugally (Spun) C.I. Pipe class LA 250 mm metre 2857 2857
dia
7702 S&S Centrifugally (Spun) C.I. Pipe class LA 300 mm metre 3857 3857
dia
7703 S&S Centrifugally (Spun) C.I. Pipe class LA 350 mm metre 4619 4619
dia
7704 S&S Centrifugally (Spun) C.I. Pipe class LA 400 mm metre 6095 6095
dia
7705 S&S Centrifugally (Spun) C.I. Pipe class LA 450 mm metre 7381 7381
dia
7706 S&S Centrifugally (Spun) C.I. Pipe class LA 500 mm metre 8571 8571
dia
7707 S&S Centrifugally (Spun) C.I. Pipe class LA 600 mm metre 11995 11995
dia
7708 S&S Centrifugally (Spun) C.I. Pipe Specials as per IS quintal 5190 5190
1538 suitable for lead jointing up to 300 mm dia
7709 S&S Centrifugally (Spun) C.I. Pipe Specials as per IS quintal 6200 6200
1538 suitable for lead jointing over 300 mm dia
7710 S&S Centrifugally (Spun) C.I. Pipe specials suitable for quintal 8571 8571
mechanical joint as per I.S. 13382 up to 300 mm dia
7711 S&S Centrifugally (Spun) C.I. Pipe Specials suitable quintal 9048 9048
for mechanical joint as per I.S. 13382 over 300 mm dia
7712 Screwed double flanged centrifugally cast (spun) C.I. metre 1310 1310
Pipe of Class B conforming to I.S. 1536, - 100 mm dia
7713 Screwed double flanged centrifugally cast (spun) C.I. metre 2048 2048
Pipe of Class B conforming to I.S. 1536, - 150 mm dia
7714 Screwed double flanged centrifugally cast (spun) C.I. metre 3238 3238
Pipe of Class B conforming to I.S. 1536, - 200 mm dia
7715 Screwed double flanged centrifugally cast (spun) C.I. metre 3905 3905
Pipe of Class B conforming to I.S. 1536, - 250 mm dia
7716 Screwed double flanged centrifugally cast (spun) C.I. metre 4990 4990
Pipe of ClassB conforming to I.S. 1536, - 300 mm dia
7717 Screwed double flanged centrifugally cast (spun) C.I. metre 6286 6286
Pipe of ClassB conforming to I.S. 1536, - 350 mm dia
7718 Screwed double flanged centrifugally cast (spun) C.I. metre 8143 8143
Pipe of Class B conforming to I.S. 1536, - 400 mm dia
7719 Screwed double flanged centrifugally cast (spun) C.I. metre 10381 10381
Pipe of Class B conforming to I.S. 1536, - 450 mm dia
7720 Screwed double flanged centrifugally cast (spun) C./. metre 12914 12914
Pipe of Class B conforming to I.S. 1536, - 500 mm dia
7721 Screwed double flanged centrifugally cast (spun) C.I. metre 17905 17905
Pipe of Class B conforming to I.S. 1536, - 600 mm dia
7722 Ductile Iron Class K- 7 pipe conforming to I.S. 8329 - metre 800 800
100 mm dia
7723 Ductile Iron Class K- 7 pipe conforming to I.S. 8329 - metre 1140 1140
150 mm dia
7724 Ductile Iron Class K- 7 pipe conforming to I.S. 8329 - metre 1400 1400
200 mm dia
7725 Ductile Iron Class K- 7 pipe conforming to I.S. 8329 - metre 1800 1800
250 mm dia
7726 Ductile Iron Class K- 7 pipe conforming to i.S. 8329 - metre 2250 2250
300 mm dia
7727 Ductile Iron Class K- 7 pipe conforming to i.S. 8329 - metre 2650 2650
350 mm dia
7728 Ductile Iron Class K- 7 pipe conforming to I.S. 8329 - metre 3175 3175
400 mm dia
7729 Ductile Iron Class K- 7 pipe conforming to I.S. 8329 - metre 3852 3852
450 mm dia
7730 Ductile Iron Class K- 7 pipe conforming to I.S. 8329 - metre 4350 4350
500 mm dia
7731 Ductile Iron Class K- 7 pipe conforming to I.S. 8329 - metre 5600 5600
600 mm dia
7732 Ductile Iron Class K- 7 pipe conforming to I.S. 8329 - metre 7300 7300
700 mm dia
7733 Ductile Iron Class K- 7 pipe conforming to I.S. 8329 - metre 9100 9100
800 mm dia
7734 Ductile Iron Class K- 7 pipe conforming to I.S. 8329 - metre 11800 11800
900 mm dia
7735 Ductile Iron Class K- 7 pipe conforming to I.S. 8329 - metre 12300 12300
1000 mm dia
7736 Extruded burnt flyash clay sewer bricks conforming to 1000 Nos 5400 5400
I.S 4885
7737 Fly ash bricks conforming to I.S. 12894 1000 Nos 4300 4300

7738 Calcium Silicate Bricks machine moulded conforming 1000 Nos 5400 5400
to I.S. 4139
7739 Modified Bitumen Refinery produced CRMB - 55 tonne 29995 29995

7741 Modified Bitumen Refinery produced CRMB - 60 tonne 30536 30536

7742 Bitumen emulsion medium setting (M.S.) conforming tonne 27909 27909
to IS : 8887
7743 M.S. pipe 150 mm dia casing pipe metre 1126 1126

7744 M.S. pipe 200 mm dia casing pipe metre 1400 1400

7745 PVC blind pipe 150 mm dia as per IS: 12818 metre 508.62 508.62

7746 PVC blind pipe 200 mm dia as per IS: 12818 metre 788.12 788.12

7747 M.S. cap 150 mm dia each 150 150

7748 M.S. cap 200 mm dia each 200 200

7749 M.S bail plug 150 mm dia each 200 200

7750 M.S bail plug 200 mm dia each 220 220

7751 PVC slotted pipe 150 mm dia as per IS: 12818 metre 550 550

7752 PVC slotted pipe 200 mm dia as per IS: 12818 metre 840 840

7753 Stone Boulder 50 mm to 200 mm cum 850 850

7754 Gravel 5 mm to 10 mm cum 850 850

7755 Gravel 1.5 mm to 2 mm cum 850 850

7756 Gravel 3 mm to 6 mm cum 850 850


7757 M.S. pipe 100 mm dia casing pipe metre 800 800

7758 uPVC blind pipe 100 mm dia as per IS: 12818 metre 442 442

7759 uPVC slotted pipe 100 mm dia as per IS: 12818 metre 480 480

7760 M.S. cap 100 mm dia each 135 135

7761 M.S. bail plug 100 mm dia each 160 160

7762 Precast R.C.C. perforated slab each 875 875

7763 Water supply tanker of 5000 litre capacity each 900 900

7764 M.S. socket 100 mm dia each 125 125

7765 M.S. socket 150 mm dia each 205 205

7766 M.S. socket 200 mm dia each 265 265

7767 Stone cleaning chemical approved by ASI litre 295 295

7768 Water repallent chemical approved by ASI litre 1200 1200

7769 Stone surface strengthening chemical approved by litre 900 900


ASI
7770 Turpentine oil litre 55 55

7771 Liquid Ammonia 5% litre 160 160

7772 Pea Gravel cum 950 950

7773 Coloured inter locking C.C. paver Block (60 mm thick, sqm 450 450
M-35)
7774 Stone size 10x10x7.50cm each 10 10

7775 Sodium pentachlorophenate kg 550 550

7776 Concrete paver block of grade M-30 made of C&D 317.22 317.22
waste (60mm thickness)
7800 Ceramic Glazed Tiles 1st quality minimum thickness sqm 212 350
5mm in all colours shades and designs except
7801 Ceramic
burgundy,Glazed Tiles 1st
bottle green, quality 300 x 300 mm in all
black sqm 209.1 400
shades and designs of White, Ivory, grey, Fume Red
7802 Ceramic
brown etc.Glazed Tiles 1st quality 300 x 300 in all sqm 260 350
shades designs except White, Ivory, Grey, Fume Red
7803 Rectified
Brown etc.Ceramic Glazed Tiles 1st quality 300 x 300 sqm 340 400
mm or more in all shades designs White, Ivory, Grey,
7804 Rectified
Fume Red Ceramic Glazed Tiles 1st quality 300 x 300
Brown etc. sqm 400 450
mm or more in all shades designs except White, Ivory,
7805 Salem Stainless
Grey, Fume Red steel
Brown AISI
etc.- 304 (18/8) Orrisa pattern each 4500 4500
W.C. pan 724 mm X 578 mm
7806 Salem Stainless steel AISI - 304 (18/8) Round basin each 1500 1500
405mm X 355 mm
7807 Salem Stainless steel AISI - 304 (18/8) Wash basin each 2000 2000
530mm X 345 mm
7808 Centrifugally cast (spun) iron S&S 100 mm inlet and each 450 450
100 mm outlet
7809 Centrifugally cast (spun) iron S&S 100 mm inlet and 75 each 500 500
mm outlet
7850 Agaria White marble slab plain 18 mm thick sqm 1100 1100

7857 P.T.M.T. Grating square slit 150 mm each 66.75 66.75


7858 P.T.M.T. Urinal cock 15 mm dia each 106.5 106.5

7859 P.T.M.T. Bib cock with nozzle 15 mm each 154.5 154.5

7861 P.T.M.T. Stop cock (concealed) 15 mm each 133.5 133.5

7862 15 mm nominal bore and 30 cm length PVC each 46.5 46.5


connection pipe with P.T.M.T. Nuts
7863 15 mm nominal bore and 45 cm length PVC each 57 57
connection pipe with P.T.M.T. Nuts
7864 P.T.M.T. extension nipple 15 mm dia each 30 30

7865 P.T.M.T. extension nipple 20 mm dia each 54 54

7866 P.T.M.T. extension nipple 25 mm dia each 78 78

7893 Tactile tile sqm 1000 1000

7895 Matt finished vitrified tile 100x100 x16 mm sqm 1000 1000

7896 Vitrified tile sqm 500 500

7900 Modular common burnt clay bricks of class designation 1000 Nos 4000 4000
7.5
7901 Machine moulded perforated common burnt clay FPS 1000 Nos 4700 4700
(non modular) bricks of class designation 12.5
7902 Machine moulded common burnt clay modular 1000 Nos 5200 5200
perforated bricks of
7903 Machine moulded common burnt clay FPS (non 1000 Nos 5000 5000
modular) bricks of class designation 12.5
7904 Machine moulded common burnt clay tile bricks of 1000 Nos 4900 4900
class designation 12.5
7911 Chemical Rust Remover litre 210 210
7912 Hire charges of Drill machine upto 30 mm dia day 160 160
7913 Epoxy kg 585 585
7914 SBR Polymer kg 190 190
7915 Woven PVC cloth sqm 25 25
7916 Hire charges of sand blasting equipment day 420 420
7917 Hire charges of compressure day 645 645
7918 25mm thick cement concrete shotcrete(guniting) with sqm 105 105
compressor
7919 50mm thick cement concrete shotcrete(guniting) with sqm 160 160
compressor
7920 75mm thick cement concrete shotcrete(guniting) with sqm 266 266
compressor
7921 Adhesive chemical ml 22
7922 Bit of drilling machine for Hole upto 30mm dia each 500 500
7923 GI injection nipple 12mm dia, 75mm long each 42 42
7924 Blowing compressed air for cleaning holes upto 30mm each 10 10
dia
7925 L shaped 100mm long, 10mm dia mild steel shear key kg 67 67
7926 Welding charges of shear key to existing reinforcement each 22
7927 Acrylic Polymer chemical for cracks kg 31 31
7928 Hire charges of Plant and machinery, it can inject - day 100 100
350kg/day
7929 Shear loops (6mm dia GI wire rope) (For vertical each 192 192
joints) 6 nos on each side
7930 dowel tubes (Corrugated GI pipes 50 to 80mm dia) metre 120 120
(For horizontal joints)
7931 Hooks for lifting (Alloy steel) having 2.5 tonne capacity each 250 250
7996 Factory made EPS light weight composite sandwitched sqm 735.25 735.25
wall/roof panel (50mm thick) having core material of
7997 each. Factoryballs/beads
EPS granule made EPS (conforming
light weight composite
to IS 4671:1984 sqm 845 845
sandwitched
and shall have wall/roof
density not less than 15kg per cum).
panel (60mm thick) having core material of EPS 0
granule balls/beads (conforming to IS 4671:1984 and
each
shall have density not less than 15kg per cum). The 0
outer face on both sides of the panels will be non
7998 Factory made EPS light weight composite sqm 1047.46 1047.46
sandwitched wall/roof panel (75mm thick) having core
each 7999
material of EPSFactory made
granule EPS light(conforming
balls/beads weight composite
to IS sqm 1268 1268
sandwitched
4671:1984 and wall/roof panel
shall have (90mm
density thick)
not less having core
than 15kg
8000 Factory made EPS light weight composite sandwitched
material of EPS granule balls/beads (conforming to IS sqm 1512.37 1512.37
wall/roof
4671:1984 panel
and (100mm
shall havethick) having
density not core
less material
than 15kg of
8001 24
EPS mm thick Factory
granule made
balls/beads shutters with
(conforming style,
to IS rails
4671:1984 sqm 1085.93 1085.93
and
and shall have density not less than 15kg per cum). or
panels of PVC extruded sections in white, grey
8002 30 mm thick
wooden finishFactory made shutters with style, rails sqm 1248.82 1248.82
and panels of PVC extruded sections in white, grey or
8003 Factory
wooden made
finish PVC rigid foam panelled shutter i/c sqm 1547.45 1547.45
carriage
8004 Factory made PVC rigid foam panelled shutter as per sqm 1547.45 1547.45
IS : 4020 i/c carriage
8006 Factory made PVC rigid foam sheet 1 mm thick sqm 155.8 155.8

8007 Factory made PVC rigid foam sheet 5 mm thick sqm 632 632

8008 Factory made prelaminated PVC rigid foam sheet 5 sqm 752 752
mm thick
8010 48mmX40mmX1.5mm thick Factory made door frame metre 125.79 125.79
of PVC extruded sections in white, grey or wooden
8011 Factory
finish made door frame PVC extruded sheet i/c metre 251.58 251.58
carriage
8012 Adhesive solvent cement kg 140 140

8013 Factory made EPS Core wallpanel /roof panel sqm 1650 1650
sandwiched between two Engineered welded wire
8014 Factory made
fabric mesh of door
3 mmframe of size
dia G.I. wire50x47 mm with
mesh,with wall
50 mm metre 298.74 298.74
thickness 5 mm
pitch in both the made of single
directions, keptpiece extruded
at 120-135 mmprofile
gap
8015 Expanded poly ethylene Foam sheet 4mm thick of sqm 18 18
Density 40kg/m3
8016 High Density expanded poly ethylene (EPE) Foam sqm 8.5 8.5
1mm thick
8017 Fire rated door frame made with 1.6 mm thick G.I metre 1000 1000
sheet (120 minutes fire rating)
8018 Fire rated door shutter made with 1.6 mm thick G.I sqm 5000 5000
sheet (120 minutes fire rating) including hinges
8019 GI sheet 0.8
( without mm
glass thick confirming to IS 277:1992
panels) kg 75 75

8020 Factory made EPS Core wall panel /roof panel sqm 600 600
sandwiched between two Engineered welded wire
8021 Bamboo wood
fabric mesh of 3Tile
mm Flooring
dia G.I.14mm thick of
wire mesh, minimum
with 50 mm sqm 3470 3470
size
pitch1800mm x 130mm
in both the directions, connected by G.I. wire of
8022 Bamboo wood Quarter Round 18mm thick of size metre 112 112
1900mm x 18mm
8023 Bamboo wood door reducer 14mm thick of size metre 255 255
1900mm x 44mm
8024 Bamboo wood Skirting 14mm thick of Size 1900mm x sqm 300 300
85mm
8025 Bamboo wood Tile Wall Cladding 10mm thick of size sqm 3385 3385
1900mm x 135mm
8026 Bamboo wood T-mold 14mm thick of size 1900mm x metre 250 250
44mm
8027 Bamboo wood Threshold 14mm thick of size 1900mm metre 255 255
x 44mm
8028 Bamboo wood shutter of doors 10 cudm 1700 1700

8029 Bamboo wood panelling (10mm thick) 10 cudm 1680 1680

8030 Superior class Bamboo wood door frame 65 mm thick, 10 cudm 1675 1675

8031 Aluminium sheets Grade 5052, 4 mm thick for wall sqm 8500 8500
panel/deck panel/ WRB panel/Kicker Panels/door
8032 Aluminium sheets
closing panels ( forGrade 5052, 4 mm thick for Internal
form work) sqm 11500 11500
Corner/ Column Corners/ ( for form work)
8033 Aluminium sheets Grade 5052, 4 mm thick for Mid sqm 32000 32000
Soldier/End soldier ( for form work)
8034 Accessories for aluminium form work External each 1400 1400
corner 2050 mm
8035 External corner 825 mm each 590 590

8036 soldier tie 370mm each 290 290

8037 Adjustable prop-2.0 x2.0 m each 1080 1080

8038 Pin-50 each 15 15

8039 Pin-127 each 55 55

8040 wedge each 14 14

8041 wall tie-150 (355 mm ) each 45 45

8042 Polythene Sleeve 90 x 150mm each 3 3

8043 Polythene Roll - 150mm Long. each 6 6

8044 Vertical Soldier -1100mm each 365 365

8045 Wall Attached Bracket 600x1000mm each 985 985

8046 Allignment Pipe - 3.00 Mtr. each 995 995

8047 Allignment Bracket each 475 475

8048 Tie Rod for Bracket - 500mm each 115 115

8049 Anchor Wing Nut 0100 mm each 64 64

8050 Debit Pin - 250mm each 60 60

8051 PVC Pipe 020mm - 150mm long each 5 5

8052 PVC Cone each 5 5

8053 Bolt+Nut - 16 x 80 mm each 30 30

8054 Flat Washer 016, 3mm thik each 5 5


8055 Bolt+Nut - 16 x 30 mm each 18 18

8056 Door spacer 45x45x5-1135mm Long each 360 360

8057 Door spacer 45x45x5 - 985mm long each 315 315

8100 Powder coated M.S. butt hinges 100 mm X58 mmX1.9 10 Nos 123 123
mm
8101 SS ball bearing of size 100 x89x3mm each 450 450

8116 Zinc alloy (white powder coated) 3D Hinges for uPVC each 451 451
door
8117 Zinc alloy (white powder coated) handles with zinc each set 2296 2296
plated mild steel
8118 multi point locking having transmission gear, cylinder each set 1394 1394
with keeps and one side key for uPVC casement door
8119 steel multi(white
Zinc alloy point locking
powderhaving
coated)transmission gear
handles along with
with each set 1150 1150
keeps for uPVC
zinc plated mild sliding window Zinc alloy (white
8121 plated mild steel multi point locking having
powder coated) handles with key along with zinc metre 258.3 258.3
transmission gear with keeps for uPVC sliding door
8122 47x50mm
uPVC extrudeduPVC(small
extruded (small
series) series) window
casement casement
frame metre 282.9 282.9
window
size sash/window
8125 mullion size 47x68 mm uPVC extruded glazing bead of metre 98.4 98.4
appropriate dimension for small
8126 series casement window Sash uPVC extruded (big metre 319.8 319.8
series) casement window frame size 67x60 mm
8127 uPVC extruded (big series) casement door frame size metre 360.8 360.8
67x64 mm
8128 uPVC extruded (big series) casement window metre 426.4 426.4
sash/window mullion/
8129 door mullion size 67x80 mm uPVC extruded (big metre 516.6 516.6
series) casement door sash size 67x110 mm
8130 uPVC extruded glazing bead of appropriate dimension metre 123 123
for big
8131 seriescasement window/door sash uPVC extruded metre 60 60
glazing bead of appropriate dimension for small
8132 series sliding window sash uPVC extruded glazing metre 85 85
bead of appropriate dimension for big series
8133 of sliding window/ door sash uPVC extruded (small metre 285 285
series) 2 track sliding window frame size 52x
8134 uPVC extruded (big series) 2 track sliding window/door metre 385 385
frame size 67x 50mm
8135 uPVC extruded (small series) 3 track sliding window metre 380 380
frame size 92x 44 mm
8136 uPVC extruded (big series) 3 track sliding window/door metre 530 530
frame size 116x45mm
8137 uPVC extruded (small series) 2 track sliding window metre 265 265
sash/3 track sliding window sash size 32x60mm
8138 uPVC extruded (big series) 2 track sliding window metre 325 325
sash size 46x62mm
8139 uPVC extruded (big series) 3 track sliding window metre 325 325
sash size 46x62mm
8140 uPVC extruded interlock of appropriate dimension for metre 80 80
small series sliding window sash
8141 uPVC extruded interlock of appropriate dimension for metre 90 90
big series sliding window/ door sash
8142 uPVC extruded inline adaptor of appropriate dimension metre 90 90
for big series sliding window/door sash
8143 uPVC extruded 2 track sliding door sash/ 3 track metre 350 350
sliding door sash (big series) size 46x82mm
8144 Bamboo Mat corrugated sheets 3.5 to 4mm thick sqm 2648 2648
conforming to IS 15476:2004
8145 Bamboo Mat Ridge cap 3.5 to 4mm thick conforming metre 2570 2570
to IS 15476:2004
8146 3mm thick Bamboo Mat Board conforming to IS sqm 1508 1508
13958:1994
8147 4mm thick Bamboo Mat Board conforming to IS sqm 1738 1738
13958:1994
8148 6mm thick Bamboo Mat Board conforming to IS sqm 2098 2098
13958:1994
8149 9mm thick Bamboo Mat Board conforming to IS sqm 2688 2688
13958:1994
8150 12mm thick Bamboo Mat Board conforming to IS sqm 3115 3115
13958:1994
8200 A.P.P. modified polymeric felt (two layers) 1.5 mm sqm 80 80
thick
8201 A.P.P. modified polymeric felt (two layers) 2 mm thick sqm 100 100

8203 A.P.P. modified 2 mm thick membrane reinforced with sqm 126.67 126.67
glass fibre matt
8204 A.P.P. modified 3 mm thick membrane reinforced with sqm 190 190
glass fibre matt
8205 A.P.P. modified 3 mm thick membrane reinforced with sqm 205 205
polyester matt
8206 Bitumen primer for bitumen membrane litre 80 80

8207 Geotextile 120 grams per sqm membrane sqm 45 45

8210 Stainless steel screws 50 mm 100 Nos 270 270

8211 Stainless steel screws 40 mm 100 Nos 215 215

8212 Stainless steel screws 30 mm 100 Nos 190 190

8214 Stainless steel screws 20 mm 100 Nos 125 125

8215 Stainless steel butt hinges 125x64x1.9 mm IS : 12817 10 Nos 265 265
marked
8216 Stainless steel butt hinges 100x58x1.9 mm IS : 12817 10 Nos 235 235
marked
8217 Stainless steel butt hinges 75x47x1.8 mm IS : 12817 10 Nos 160 160
marked
8218 Stainless steel butt hinges 50x37x1.5 mm IS : 12817 10 Nos 135 135
marked
8219 Stainless steel butt hinges (heavy weight) 125x64x2.5 10 Nos 350 350
mm IS : 12817 marked
8220 Stainless steel butt hinges (heavy weight) 100x60x2.5 10 Nos 255 255
mm IS : 12817 marked
8221 Stainless steel butt hinges (heavy weight) 75x50x2.5 10 Nos 205 205
mm IS : 12817 marked
8222 M.S. heavy weight butt hinges 125x90x4.0 mm IS: 10 Nos 210 210
1341 marked.
8223 M.S. heavy weight butt hinges 100x75x3.5 mm IS: 10 Nos 160 160
1341 marked
8224 M.S. heavy weight butt hinges 75x60x3.1 mm IS: 1341 10 Nos 95 95
marked
8225 M.S. heavy weight butt hinges 50x40x2.5 mm IS : 10 Nos 80 80
1341 marked
8226 Concealed zinc coated hinges 19-20 mm thick with 10 Nos 420 420
mounting plate
8300 1216 mm PE-AL-PE Composite pressure pipe metre 62 62

8301 1620 mm PE-AL-PE Composite pressure pipe metre 78 78

8302 2025 mm PE-AL-PE Composite pressure pipe metre 110 110

8303 2532 mm PE-AL-PE Composite pressure pipe metre 157 157


8304 3240 mm PE-AL-PE Composite pressure pipe metre 235 235

8305 4050 mm PE-AL-PE Composite pressure pipe metre 330 330

8306 PPR Union 20 mm each 48 48

8307 PPR Union 25 mm each 97 97

8308 PPR Union 32 mm each 137.2 137.2

8309 PPR Union 40 mm each 184.8 184.8

8310 PPR Union 50 mm each 352.8 352.8

8311 PPR Union 63 mm each 483.6 483.6

8312 PPR Union 75 mm each 933 933

8500 Water for jetting / blowback 1000 litre 1500 1500

8501 Polymer modified cementation coating kg 140 140

8502 Fibre glass cloth sqm 25 25

8504 Multi surface paint litre 255 255

8505 Acrylic exterior paint litre 170 170

8506 Premium Acrylic exterior paint litre 180 180

8507 Textured exterior paint litre 240 240

8508 Primer for cement paint litre 79 79

8509 Special Primer (C.W.) litre 140 140

8510 Metal Primer (U.G.) litre 90 90

8511 Fibre reinforced elastomeric liquid water proofing litre 198.69 198.69
membrane
8512 Cementitious water proofing coating with elastic kg 189.13 189.13
polymers
8513 Acrylic modified resin based texture kg 36 36

8514 40 mm long S.S screws with plastic rawl plugs each 40 40

8515 Galavanised MS 8 mm outer diameter M-6 dash each 31 31


fastener 50mm long
8516 ZMB 60/equivalent kg 105 105

8517 ZMB thinner litre 205 205

8518 Zycoprime / equivalent litre 210 210

8519 Zycosil / equivalent litre 1800 1800

8520 Elastobar / equivalent kg 300 300

8552 Mineral fibre beveled tegular edged ceiling tiles 595 sqm 830 830
x595mm,16 mm thick
8553 Mineral fibre beveled tegular edged ceiling tiles 595 sqm 920 920
x595mm,16 mm thick with bio-block conforming to ISO
8554 Mineral
5 (class fiber
100) beveled tegular edged ceiling tiles 595
specifications. sqm 1040 1040
x595mm,20 mm thick.
8555 G. I main runner 15 x32 mm of 3000 mm length, 0.33 each 185 185
mm thick
8556 G.I cross-T 15 x32 mm of 1200 mm length, 0.33 mm each 78 78
thick
8557 G.I cross-T 15 x32 mm of 600 mm length, 0.33 mm each 35 35
thick
8558 G.I hanger rod 6mm dia fully threaded upto 1000 mm each 26 26
length
8559 Stainless steel U Channel of size (50x25x2mm) metre 160 160

8560 Non staining water resistant clear silicon metre 65 65

8561 Extruded polystyrene rigid insulation board 50 mm sqm 525 525


thick
8562 Expanded Polystyrene insulation board 120 mm thick sqm 800 800
confirming to IS 4671-1984, Fire retardant property
8563 15 mm thick, light type
self-extinguishing weight, integral
as per densified micro look
EN 13501-1 sqm 720 720
edged,false ceiling tiles of size 595x595 mm.
8564 15 mm thick, light weight,fully perforated square/butt sqm 900 900
edge integral densified,false ceiling tiles of size
8565 Galavanised
595x595 mm.MS hanger rod 6 mm dia MS fully each 26 26
threaded up to 1000 mm length
8566 Powder coated steel section main-T ceiling sections each 235 235
15x42x0.40 mm (3000 mm long)
8567 Galvanized mild steel perimeter wall angle 22x19x0.40 each 115 115
mm (3000 mm long)
8568 Powder coated Galvanised Iron intermediate cross-T each 95 95
section 15x42x0.40 mm (1200 mm long)
8569 Powder coated Galvanized Iron intermediate cross-T each 47 47
section 15x42x0.40mm (600 mm long )
8570 GI Main T ceiling section 30x25x0.3 mm (3 metre long) each 187 187

8571 GI Perimeter wall angle 25x25x0.4 mm (3 metre long) each 157 157

8572 GI Intermediate cross T section 25x25x0.3 mm (1.2 each 72 72


metre long)
8573 GI Intermediate cross T section 25x25x0.3 mm (0.6 each 34 34
metre long)
8576 Crates made of Mesh type 10x12 (D=100 mm) Zinc sqm 190 190
coated. (Mesh wire diameter 3.00 mm).
8577 Crates made of Mesh type 10x12 (D=100 mm) sqm 220 220
Zn+PVC coated. Mesh wire diameter 2.70/3.70 mm
8578 Crates
(ID/OD).made of Mesh type 10x12 (D=100 mm) sqm 290 290
Zn+10% Al alloy + PVC coated. Mesh wire diameter
8579 Cold form mm
2.70/3.70 light(ID/OD).
gauge Steel C-section of thickness kg 130 130
0.75mm i/c zink coating/sliting etc.
8580 Wastage of cold form light gauge steel kg 17 17

8581 12 mm thick micro tegular edged semi perforated GRG sqm 510 510
(Glass Fibre Reinforced Gypsum) false celing tiles of
8582 12 mm
Size thick micro
595x595 mm tegular edged fully perforated GRG sqm 600 600
(Glass Fibre Reinforced Gypsum) false celing tiles of
8583 10 mm
Size thick square
595x595 mm edge fully perforated GRG(Glass sqm 750 750
Fibre Reinforced Gypsum) false celing tiles of Size
8587 Galvanized
595x595 mmiron intermediate cross-T section each 35 35
15x32x0.33 mm (600 mm long)
8588 Galavanised MS hanger rod 6mm dia MS fully each 26 26
threaded up to 1000 mm length
8589 Calcium Silicate tegular edged celling tiles 595x595 sqm 685 685
mm and 15 mm thick on edges
8590 Galvanised Steel main Tee ceiling section Size each 120 120
24x38x0.33 mm (3 metre long)
8591 Galvanised Steel perimeter wall Angle Size 24 x 24 x each 65 65
0.40 mm (3.00metre long)
8592 Galvanised Steel intermediate cross T section Size 24 each 40 40
x 25 x 0.33 mm (1.2 metre long)
8593 Galvanised Steel intermediate cross T section Size 24 each 20 20
x 25 x 0.33 mm ( 0.6 metre long)
8594 Galvanised Steel soffit cleat size 25x35x1.60 mm each 4 4

8595 Wooden screws with plastic rawl plugs 35x8 mm each 1 1

8596 Galvanised MS 8mm outer diameter M-6 dash fastener each 32 32


25mm long
8597 Gi Metal Tile Clip in Plain Beveled edge global white sqm 677 677
colour tiles ofsize 600x600 mm and 0.5 mm thick
8598 GI Metal Tile Clip in Perforated Beveled edge global sqm 782 782
white colour tiles of size 600x600 mm and 0.5 mm
8599 GI Metal Tile Lay-in Plain Tegular edge global white
thick sqm 612 612
color tiles of Size 595x595 mm and 0.5 mm thick
8600 GI Metal Tile Lay-in Perforated Tegular edge global sqm 715 715
white color tiles of Size 595x595 mm and 0.5 mm thick
8601 PVC Laminated Gypsum Tiles (Square edge) of Size sqm 880 880
595x595 mm and 12.5 mm thick
8602 Gypsum Tiles Fully Perforated Square edge of Size sqm 375 375
595x595 mm and 12.5 mm thick
8604 Spring T-section 24x34x0.45 mm (3.00 meter long) metre 190 190

8605 C Wall angle section 20x30x20x0.50 mm (3.00 meter metre 95 95


long)
8606 Main C Carrier Size 10x38x10x0.70 mm (3.00 meter metre 115 115
long)
8607 Spring T-connector each 5 5

8608 C Carrier Connector each 11 11

8609 C Suspension Clip each 8 8

8610 Wire Coupling Clip each 9 9

8611 Main T ceiling sections 24x38x0.3 mm (3 metre long) each 115 115

8612 Perimeter wall angle 24 x 24 x 0.3 mm (3 metre long) each 80 80

8613 Intermediate cross T-Section 24x25x0.3 mm (1.2 m each 35 35


long)
8614 Intermediate cross T-Section 24x25x0.3 mm (0.6 m each 17 17
long)
8615 Hanger rod 4 mm thick each 8 8

8616 Adjustment clip 85x30x0.8 mm each 5 5

8617 Soffit cleat (Size 27x37x25x1.60 mm) each 4 4

8618 Dash fastener 6 mm dia 50 mm long each 8 8

8619 Galavanised MS L-shape level adjuster of size each 15 15


85x25x2 mm
8620 Vitrified floor tile 50x50 cm conforming to IS sqm 490 550
15622:2006 group (B1a)
8621 Vitrified floor tile 60x60 cm conforming to IS sqm 659.72 750
15622:2006 group (B1a)
8622 Vitrified floor tile 80x80 cm conforming to IS sqm 850 850
15622:2006 group (B1a)
8623 Vitrified floor tile 100x100 cm conforming to IS sqm 1390 1390
15622:2006 group (B1a)
8624 "Border tiles 200x75mm size each 16 16
8626 Poly propylene- Random - Co - Polymer (PPR) pipes metre 43.27 43.27
PN-16 (SDR 7.4) - 20 mm Outer dia
8627 Poly propylene- Random - Co - Polymer (PPR) pipes metre 66.8 66.8
PN-16 (SDR 7.4) - 25 mm Outer dia
8628 Poly propylene- Random - Co - Polymer (PPR) pipes metre 107.47 107.47
PN-16 (SDR 7.4) - 32 mm Outer dia
8629 Poly propylene- Random - Co - Polymer (PPR) pipes metre 161.07 161.07
PN-16 (SDR 7.4) - 40 mm Outer dia
8630 Poly propylene- Random - Co - Polymer (PPR) pipes metre 252.22 252.22
PN-10 (SDR 11) - 50 mm Outer dia
8631 Poly propylene- Random - Co - Polymer (PPR) pipes metre 281.73 281.73
PN-10 (SDR 11) - 63 mm Outer dia
8632 Poly propylene- Random - Co - Polymer (PPR) pipes metre 418.18 418.18
PN-10 (SDR 11) - 75 mm Outer dia
8633 Poly propylene- Random - Co - Polymer (PPR) pipes metre 597.63 597.63
PN-10 (SDR 11) - 90 mm Outer dia
8634 Poly propylene- Random - Co - Polymer (PPR) pipes metre 885.83 885.83
PN-10 (SDR 11) - 110 mm Outer dia
8635 Poly propylene- Random - Co - Polymer (PPR) pipes metre 2557.3 2557.3
PN-10 (SDR 11) - 160 mm Outer dia
8636 Chlorinated Polyvinyl - chloride (CPVC) pipe 15 mm metre 48.55 48.55
outer dia
8637 Chlorinated Polyvinyl - chloride (CPVC) pipe 20 mm metre 77.8 77.8
outer dia
8638 Chlorinated Polyvinyl - chloride (CPVC) pipe 25 mm metre 113.6 113.6
outer dia
8639 Chlorinated Polyvinyl - chloride (CPVC) pipe 32 mm metre 163.65 163.65
outer dia
8640 Chlorinated Polyvinyl - chloride (CPVC) pipe 40 mm metre 228.7 228.7
outer dia
8641 Chlorinated Polyvinyl - chloride (CPVC) pipe 50 mm metre 375.25 375.25
outer dia
8642 Chlorinated Polyvinyl - chloride (CPVC) pipe 62.5 mm metre 793.3 793.3
inner dia
8643 Chlorinated Polyvinyl - chloride (CPVC) pipe 75 mm metre 1031.05 1031.05
inner dia
8644 Chlorinated Polyvinyl - chloride (CPVC) pipe 100 mm metre 1466.75 1466.75
inner dia
8645 Chlorinated Polyvinyl - chloride (CPVC) pipe 150 mm metre 3145.15 3145.15
inner dia
8646 Silicon sealant cartridge 100 100

8647 Stainless steel screws 30 mm x4 mm 100 Nos 32 32

8648 Hermetically sealed double glazed unit made with 6 sqm 2150 2150
mm thick clear float glass both side having 12 mm air
8649 Stainless
gap steel (SS 304 grade) adjustable friction each 172 172
window stay 205 x 19 mm
8650 Stainless steel (SS 304 grade) adjustable friction each 222 222
window stay 255 x 19 mm
8651 Stainless steel (SS 304 grade) adjustable friction each 195 195
window stay 355 x 19 mm
8652 Stainless steel (SS 304 grade) adjustable friction each 525 525
window stay 510 x 19 mm
8653 Stainless steel (SS 304 grade) adjustable friction each 900 900
window stay 710 x 19 mm
8654 Masking tape metre 1.95 1.95

8655 Autoclaved aerated cement (AAC) blocks cum 2600 2600

8656 Gypsum panel 666 X 500 X 100 mm size sqm 480 480

8657 Bonding plaster for Gypsum panel kg 25 25


8658 Precast C&D waste concrete block 1000 Nos 25150 25150

8659 Water proof ply 12 mm thick sqm 517 517

8660 Aluminium casement window fastener (Anodised AC each 44 44


15)
8661 Aluminium casement window fastener (powder each 47 47
coated )
8662 Aluminium casement window fastener (polyester each 46 46
powder coated)
8663 Aluminium round shape handle (anodised AC 15) each 53 53
outer dia 100 mm
8664 Aluminium round shape handle (powder coated) outer each 56 56
dia 100 mm
8665 Aluminium round shape handle (polyester powder each 60 60
coated) outer dia 100 mm
8666 Stainless steel screws 25 mm x4 mm 100 Nos 38 38

8667 UV stabilised 2 mm thick plain FRP sheet sqm 430 430

8668 UV stabilised 2 mm thick corrugated FRP sheet sqm 485 485

8669 Mangalore ridge tiles 20 mm thick each 8 8

8670 Mangalore tiles 20 mm thick each 8 8

8671 Precoated galvanised iron profile sheet 0.50 mm TCT sqm 350 650

8672 Precoated galvanised steel plain ridges 0.50 mm TCT metre 210 450
and 500600mm wide
8673 Precoated galvanised steel flashings/aprons 0.50 mm metre 210 450
TCT and upto 600mm wide
8674 Precoated galvanised steel gutter 600mm overall girth metre 420 420

8675 Precoated galvanised steel north light curves metre 230 230

8676 Precoated galvanised steel barge board (upto metre 215 215
300mm )
8677 Precoated galvanised steel crimp curve sqm 230 230

8678 1 mm thick 35 mm wide bright finished stainless steel metre 42 42


piano hinges
8682 Epoxy Grout kg 371 371

8683 Red sand stone gang saw cut 30 mm thick sqm 425 425

8684 White sand stone gang saw cut 30 mm thick sqm 560 560

8685 Delineator each 300 300

8686 Precast C.C. Kerb stone M - 25 cum 5500 5500

8687 Thermoplastic paint kg 65 65

8688 Glass beads kg 70 70

8689 Interlocking C.C. paver block ( 60 mm thick, M-30) sqm 400 400

8690 High intensity retro - reflective sheet as per IRC 67- sqm 1300 1300
2001
8691 Punched tape concertina coil 600 mm dia 10 m bundle 600 600
openable length (Total length 90 m)
8692 RBT reinforced barbed wire metre 6.5 6.5
8693 Turn buckle and strengthening bolt each set 40 40

8694 Precast pavement slab 450 x 450 x 50 mm (M - 30) each 135 135

8695 Chain link fabric fencing mesh of size 50x50 mm made sqm 280 280
of G.I. wire of dia 4 mm
8696 Chain link fabric fencing mesh of size 50x50 mm made sqm 300 300
of G.I. wire of dia 4 mm, PVC coated to outer dia 5 mm
8697 Chain link fabric fencing mesh of size 25x25 mm made sqm 360 360
of G.I. wire of dia 3 mm
8698 Stainless steel cramps(weight 260 grams) with nuts, each 100 100
bolts and washer for dry stone cladding
8699 8 mm thick tapered edge calcium silicate board sqm 265 265

8700 10 mm thick calcium silicate board sqm 420 420

8701 SS pipe 304 grades with press fit technology as per metre 610 610
JIS 3448 standard 48.60 mm outer dia
8702 Coupling/Socket fittings for 15.88 mm outer dia each 59 59
SS pipe
8703 Telescopic drawer channels 300 mm long set 230 230

8704 Stainless steel roller for sliding arrangement in racks/ each 9 9


cupboards/ cabinets shutter
8705 50 mmX42 mmX2 mm thick Factory made door frame metre 160 160
of PVC extruded sections in white, grey or wooden
8706 25 mm thick factory made PVC flush door
finish sqm 1700 1700
shutter i/c carriage
8707 Factory made glass reinforced plastic door metre 467 467
frame 90x45 mm i/c carriage
8708 30 mm thick factory made glass fiber reinforced plastic sqm 2326 2326
panel doorshutter i/c carriage
8709 30 mm thick factory made solid PVC profile panelled sqm 2100 2100
door single piece extruded profile decorative finish
8710 Factory made
(wood grain solid
printed onPVC door frame 60 x 30 mm
both side) metre 315 315
i/c carriage
8711 20 mm factory made solid PVC panel door sqm 2050 2050
shutter i/c carriage
8712 30 mm thick factory made solid PVC profile panelled sqm 2000 2000
door single piece extruded profile non decorative finish
8713 Fiber glass reinforced plastic chajja sqm 3000 3000

8714 Magnetic catcher triple strip vertical type each 24 24

8715 Magnetic catcher double strip horizontal type each 18 18

8716 100 mm mortice lock with 6 levers for aluminium each 375 375
door
8717 12.5 mm thick Glass fibre reinforced Gypsum sqm 195 195
board
8719 2nd class teak wood moulded beading or Taj metre 28 28
beading/ornamental bleading of size 18X5 mm
8720 Ceiling sections 0.55 mm thick having a knurled web of metre 35 35
51.55 mm and two flanges of 26 mm each with lips of
8721 Perimeter
10.55 mm channel having one flange of 20 mm and metre 22 22
another flange of 30 mm with thickness of 0.55 mm
8722 Nylon
and web sleeves &27
of length wooden
mm screws (40 mm) each 2 2

8723 Counter sunk ribbed head screw 25 mm 100 Nos 68 68

8724 12 mm thick marine plywood conforming to IS: sqm 695 695


710
8725 12 mm thick fire retardant plywood conforming sqm 850 850
to IS: 5509
8726 1.5 mm thick decorative laminated sheet sqm 365 365

8727 1.0 mm thick decorative laminated sheet sqm 280 280

8730 30 mm thick factory made glass fiber reinforced plastic sqm 2675 2675
flush door shutter i/c carriage
8731 High polymer modified quickset tile adhesive kg 9 9

8732 Synthetic ployster triangular fibre of length 12 mm, kg 365 365


effective diameter 10-40 microns and specific gravity
8733 Synthetic
of 1.34 to ployster
1.40 triangular fibre of length 6 mm, kg 400 400
effective diameter 10-40 microns and specific gravity
8734 P.V.C.
of 1.34 Single
to 1.40piece extruded door frame of profile size metre 255 255
50 mm x 47 mm with wall thickness of 5 mm
8735 35 mm thick factory made solid panel PVC door sqm 2150 2150
shutter of singlepiece extruded profile non decorative
8736 35 mm thick
finished (Mattfactory made solid panel PVC door
finished) sqm 2600 2600
shutter of single piece extruded profile decorative
8737 Stainless steel wire guage
finished (wood grain finished) (Grade-304) aperture 1.4 sqm 400 400
mm and 0.50 mm dia wire
8738 Factory made door frame fire rated (60 minutes) made metre 1050 1050
with 16 SWG G.I. Sheet of section 143 mm x 57 mm
8739 Fire
duly rated doorvermuculite
filled with shuttere made
basedwithconcrete
16 SWGmixG.I. sheet sqm 4500 4500
(60 minutes) without panel
8740 Fire seal Putty kg 295 295

8741 Clear fire resistant glass panes 6mm thick (60 sqm 21500 21500
minutes)
8742 G.I. U beading of 16 SWG G.I. sheet (zinc coating metre 295 295
>120gm/ m2) with ceramic tape of suitable thickness
8743 Matrix
and fire Mineral
resistant Board
primer coating metre 68 68

8744 Panic Bar / latch (Double point) each 5200 5200

8745 65 mm x 55 mm x 2 mm thick Factory made door metre 355 355


frame of PVC extruded section in white, grey or
8746 37 mm thick
wooden finishFactory made shutter with style,rails and sqm 2400 2400
panels of PVC extruded section in white or grey finish
8747 75 mm x 53 mm x 2.0 mm thick Factory made door
i/c carriage metre 400 400
frame of PVC extruded section in white, grey or
8748 37 mm thick
wooden finishFactory made fusion welded shutter with sqm 2600 2600
style, rails and panels of PVC extruded section in
8749 Zinc
woodenalloyfinish
(white powder coated) touch lock with hook sqm 120 120
for wire mesh shutter
8750 Zinc alloy (white powder coated) casement each 130 130
handle for uPVC window/door
8751 Zinc alloy (white powder coated) touch lock with hook each 105 105
for uPVC window/door
8752 Zinc alloy body with single nylon roller (weight bearing each 56 56
capacity to be 40 Kg) for uPVC sliding window
8753 Stainless Steel (SS - 304) with adjustable double nylon each 95 95
roller (weight bearing capacity to be 120 Kg) for uPVC
8754 Zinc alloy
sliding (white powder coated) cresent lock for uPVC
door/window each 115 115
sliding door/window
8755 Stainless steel friction hinge of size 200 mm x 19 x 1.9 each 205 205
mm for uPVC windows
8756 Stainless steel friction hinge of size 250 mm x 19 x 1.9 each 230 230
mm for uPVC windows
8757 Stainless steel friction hinges (SS-304 grade) size 300 each 245 245
x 19 x 1.9 mm for uPVC window
8758 Stainless steel friction hinges (SS-304 grade) size 350 each 345 345
x 19 x 1.9 mm for uPVC window
8759 Stainless steel friction hinges (SS-304 grade) size 400 each 365 365
x 19 x 1.9 mm for uPVC window
8760 Glass panes of required thickness having 60 minutes sqm 22500 22500
of fire resistance both integrity and radiation control
8761 Scaffolding
(EW 60) andnet made of20
minimum high density
minutes of polyethylene
insulation (EIUV
20) sqm 21.5 21.5
stabilized having density 100gm/ sqm.
8772 Aluminium Track on bottom rail for uPVC window metre 30 30

8773 Wool pile/ weather pile strip for uPVC sliding window metre 20 20

8774 Aluminium Grill as per IS 1868 kg 260 260

8775 Steel Galvanised tubular reinforcement for uPVC door/ metre 60 60


window
8776 Stainless steel dash fastener of 8 mm dia and 75 mm each 15 15
long bolt
8777 GI Fastener 100x8 mm each 15 15

8778 Toughened glass 12 mm thickness sqm 1747 1747

8779 SS pipe 304 grades with press fit technology as per metre 130 130
JIS 3448 standard 15.88 mm outer dia
8780 SS pipe 304 grades with press fit technology as per metre 243 243
JIS 3448 standard 22.22 mm outer dia
8781 SS pipe 304 grades with press fit technology as per metre 297 297
JIS 3448 standard 28.58 mm outer dia
8782 SS pipe 304 grades with press fit technology as per metre 423 423
JIS 3448 standard 34.00 mm outer dia
8783 SS pipe 304 grades with press fit technology as per metre 441 441
JIS 3448 standard 42.70 mm outer dia
8784 8 mm thick Calcium silicate perforated tiles of size 595 sqm 833 833
x595 mm
8785 Interlocking C.C. paver block ( 80 mm thick, M-30) sqm 470 470

8786 Coupling/Socket fittings for 22.22 mm outer dia SS each 63 63


pipe
8787 Coupling/Socket fittings for 28.58 mm outer dia SS each 89 89
pipe
8788 Coupling/Socket fittings for 34.00 mm outer dia SS each 131 131
pipe
8789 Coupling/Socket fittings for 42.70 mm outer dia SS each 158 158
pipe
8790 Coupling/Socket fittings for 48.60 mm outer dia SS each 180 180
pipe
8791 Reducer for 22.22 mm X 15.88 mm outer Dia SS pipe each 103 103

8792 Reducer for 28.58 mm X 15.88 mm outer Dia SS pipe each 141 141

8793 Reducer for 28.58 mm X 22.22 mm outer Dia SS pipe each 145 145

8794 Reducer for 34.00 mm X 15.88 mm outer Dia SS pipe each 184 184

8795 Reducer for 34.00 mm X 22.22 mm outer Dia SS pipe each 187 187

8796 Reducer for 34.00 mm X 28.58 mm outer Dia SS pipe each 190 190

8797 Reducer for 42.70 mm X 15.88 mm outer Dia SS pipe each 359 359

8798 Reducer for 42.70 mm X 22.22 mm outer Dia SS pipe each 362 362

8799 Reducer for 42.70 mm X 28.58 mm outer Dia SS pipe each 362 362

8800 Reducer for 42.70 mm X 34.00 mm outer Dia SS pipe each 387 387

8801 Reducer for 48.60 mm X 15.88 mm outer Dia SS pipe each 410 410
8802 Reducer for 48.60 mm X 22.22 mm outer Dia SS pipe each 410 410

8803 Reducer for 48.60 mm X 28.58 mm outer Dia SS pipe each 410 410

8804 Reducer for 48.60 mm X 34.00 mm outer Dia SS pipe each 410 410

8805 Reducer for48.60 mm X 42.70 mm outer Dia SS pipe each 410 410

8806 Slip Coupling / Socket 15.88 mm outer dia SS pipe each 47 47

8807 Slip Coupling / Socket 22.22 mm outer dia SS pipe each 63 63

8808 Slip Coupling / Socket 28.58 mm outer dia SS pipe each 89 89

8809 Slip Coupling / Socket 34.00 mm outer dia SS pipe each 131 131

8810 Slip Coupling / Socket 42.70 mm outer dia SS pipe each 158 158

8811 Slip Coupling / Socket 48.60 mm outer dia SS pipe each 170 170

8812 Elbow 90° for 15.88 mm outer dia SS pipe each 58 58

8813 Elbow 90° for 22.22 mm outer dia SS pipe each 63 63

8814 Elbow 90° for 28.58 mm outer dia SS pipe each 96 96

8815 Elbow 90° for 34.00 mm outer dia SS pipe each 109 109

8816 Elbow 90° for 42.70 mm outer dia SS pipe each 116 116

8817 Elbow 90° for 48.60 mm outer dia SS pipe each 150 150

8818 Reducing Elbow 90° for 22.22 mm X 15.88 mm outer each 148 148
dia SS pipe
8819 Reducing Elbow 90° for 28.58 mm X 15.88 mm outer each 191 191
dia SS pipe
8820 Reducing Elbow 90° for 28.58 mm X 22.22 mm outer each 221 221
dia SS pipe
8821 Reducing Elbow 90° for 34.00 mm X 22.22 mm outer each 287 287
dia SS pipe
8822 Reducing Elbow 90° for 34.00 mm X 28.58 mm outer each 345 345
dia SS pipe
8823 Reducing Elbow 90° for 42.70 mm X 34.00 mm outer each 179 179
dia SS pipe
8824 Equal Tee for 15.88 mm outer dia SS pipe each 159 159

8825 Equal Tee for 22.22 mm outer dia SS pipe each 231 231

8826 Equal Tee for 28.58 mm outer dia SS pipe each 273 273

8827 Equal Tee for 34.00 mm outer dia SS pipe each 437 437

8828 Equal Tee for 42.70 mm outer dia SS pipe each 683 683

8829 Equal Tee for 48.60 mm outer dia SS pipe each 887 887

8830 Reducing Tee for 22.22 mm X 15.88 mm outer dia SS each 179 179

8831 Reducing Tee for 28.58 mm X 15.88 mm outer dia SS each 273 273
pipe
8832 Reducing Tee for 28.58 mm X 22.22 mm outer dia SS each 273 273
pipe
8833 Reducing Tee for 34.00 mm X 15.88 mm outer dia SS each 437 437
pipe
8834 Reducing Tee for 34.00 mm X 22.22 mm outer dia SS each 437 437
pipe
8835 Reducing Tee for 34.00 mm X 28.58 mm outer dia SS each 437 437
pipe
8836 Reducing Tee for 42.70 mm X 15.88 mm outer dia SS each 683 683
pipe
8837 Reducing Tee for 42.70 mm X 22.22 mm outer dia SS each 683 683
pipe
8838 Reducing Tee for 42.70 mm X 28.58 mm outer dia SS each 683 683
pipe
8839 Reducing Tee for 42.70 mm X 34.00 mm outer dia SS each 683 683
pipe
8840 Reducing Tee for 48.60 mm X 15.88 mm outer dia SS each 887 887
pipe
8841 Reducing Tee for 48.60 mm X 22.22 mm outer dia SS each 887 887
pipe
8842 Reducing Tee for 48.60 mm X 28.58 mm outer dia SS each 887 887
pipe
8843 Reducing Tee for 48.60mm X 34.00 mm outer dia SS each 887 887
pipe
8844 Reducing Tee for 48.60mm X 42.70mm outer dia SS each 887 887
pipe
8845 Stainless steel Male thread Tee for 15.88 mm outer dia each 179 179
X 15 mm nominal dia threaded
8846 Stainless steel Male thread Tee for 22.22 mm outer dia each 200 200
X 15 mm nomina dia threaded
8847 Stainless steel Male thread Tee for 22.22 mm outer dia each 205 205
X 20 mm nominal dia threaded
8848 Stainless steel Male thread Tee for 28.58 mm outer dia each 273 273
X 15 mm l nomina dia threaded
8849 Stainless steel Male thread Tee for 28.58 mm outer dia each 273 273
X 20 mm nominal dia threaded
8850 Stainless steel Male thread Tee for 28.58 mm outer dia each 273 273
X 25 mm nominal dia threaded
8851 Stainless steel Male thread Tee for 34.00 mm outer dia each 437 437
X 15 mm nominal dia threaded
8852 Stainless steel Male thread Tee for 34.00 mm outer dia each 437 437
X 20 mm nominal dia threaded
8853 Stainless steel Male thread Tee for 34.00 mm outer dia each 437 437
X 25 mm nominal dia threaded
8854 Stainless steel Male thread Tee for 34.00 mm outer dia each 437 437
X 32 mm nominal dia threaded
8855 Stainless steel Male thread Tee for 42.70 mm outer dia each 683 683
X 15 mm nominal dia threaded
8856 Stainless steel Male thread Tee for 42.70 mm outer dia each 683 683
X 20 mm nominal dia threaded
8857 Stainless steel Male thread Tee for 42.70 mm outer dia each 683 683
X 25 mm nominal dia threaded
8858 Stainless steel Male thread Tee for 42.70 mm outer dia each 683 683
X 32 mm nominal dia threaded
8859 Stainless steel Male thread Tee for 42.70 mm outer dia each 683 683
X 40 mmnominal dia threaded
8860 Stainless steel Male thread Tee for 48.60 mm outer dia each 887 887
X 15 mm nominal dia threaded
8861 Stainless steel Male thread Tee for 48.60 mm outer dia each 887 887
X 20 mm nominal dia threaded
8862 Stainless steel Male thread Tee for 48.60 mm outer dia each 887 887
X 25 mm nominal dia threaded
8863 Stainless steel Male thread Tee for 48.60 mm outer dia each 887 887
X 32 mm nominal dia threaded
8864 Stainless steel Male thread Tee for 48.60 mm outer dia each 887 887
X 40 mm nominal dia threaded
8865 Stainless steel Male thread Tee for 48.60 mm outer dia each 887 887
X 50 mm nominal dia threaded
8866 Stainless steel Female thread Tee for 15.88 mm outer each 179 179
dia X 15 mm nominal dia threaded
8867 Stainless steel Female thread Tee for 22.22 mm outer each 200 200
dia X 15 mm nominal dia threaded
8868 Stainless steel Female thread Tee for 22.22 mm outer each 200 200
dia X 20 mm nominal dia threaded
8869 Stainless steel Female thread Tee for 28.58 mm outer each 273 273
dia X 15 mm nominal dia threaded
8870 Stainless steel Female thread Tee for 28.58 mm outer each 273 273
dia X 20 mm nominal dia threaded
8871 Stainless steel Female thread Tee for 28.58 mm outer each 273 273
dia X 25 mm nominal dia threaded
8872 Stainless steel Female thread Tee for 34.00 mm outer each 437 437
dia X 15 mmnominal dia threaded
8873 Stainless steel Female thread Tee for 34.00 mm outer each 437 437
dia X 20 mm nominal dia threaded
8874 Stainless steel Female thread Tee for 34.00 mm outer each 437 437
dia X 25 mm nominal dia threaded
8875 Stainless steel Female thread Tee for 34.00 mm outer each 437 437
dia X 32 mm nominal dia threaded
8876 Stainless steel Female thread Tee for 42.70 mm outer each 683 683
dia X 15 mm nominal dia threaded
8877 Stainless steel Female thread Tee for 42.70 mm outer each 683 683
dia X 20 mmnominal dia threaded
8878 Stainless steel Female thread Tee for 42.70 mm outer each 683 683
dia X 25 mm nominal dia threaded
8879 Stainless steel Female thread Tee for 42.70 mm outer each 683 683
dia X 32 mm nominal dia threaded
8880 Stainless steel Female thread Tee for 42.70 mm outer each 683 683
dia X 40 mm nominal dia threaded
8881 Stainless steel Female thread Tee for 48.60 mm outer each 887 887
dia X 15 mm nominal dia threaded
8882 Stainless steel Female thread Tee for 48.60 mm outer each 887 887
dia X 20 mm nominal dia threaded
8883 Stainless steel Female thread Tee for 48.60 mm outer each 887 887
dia X 25 mm nominal dia threaded
8884 Stainless steel Female thread Tee for 48.60 mm outer each 887 887
dia X 32 mmnominal dia threaded
8885 Stainless steel Female thread Tee for 48.60 mm outer each 887 887
dia X 40 mm nominal dia threaded
8886 Stainless steel Female thread Tee for 48.60 mm outer each 887 887
dia X 50 mm nominal dia threaded
8887 Stainless steel Female threaded Connector/Adapter each 190 190
for 15.88 mm outer dia X 15 mm nominal threaded
8888 Stainless steel Female threaded Connector/Adapter each 230 230
for 22.22 mm outer dia X 15 mm nominal threaded
8889 Stainless steel Female threaded Connector/Adapter each 237 237
for 22.22 mm outer dia X 20 mm nominal threaded
8890 Stainless steel Female threaded Connector/Adapter each 277 277
for 28.58 mm outer dia X 15 mm nominal threaded
8891 Stainless steel Female threaded Connector/Adapter each 286 286
for 28.58 mm outer dia X 20 mm nominal threaded
8892 Stainless steel Female threaded Connector/Adapter each 337 337
for 28.58 mm outerdia X 25 mm nominal threaded
8893 Stainless steel Female threaded Connector/Adapter each 409 409
for 34.00 mm outer dia X 25 mm nominal threaded
8894 Stainless steel Female threaded Connector/Adapter each 538 538
for 34.00 mm outer dia X 32 mm nominal threaded
8895 Stainless steel Female threaded Connector/Adapter each 576 576
for 42.70 mm outer dia X 32 mm nominal threaded
8896 Stainless steel Female threaded Connector/Adapter each 681 681
for 42.70 mm outerdia X 40 mm nominal threaded
8897 Stainless steel Female threaded Connector/Adapter each 838 838
for 48.60 mm outer dia X 40 mm nominal threaded
8898 Stainless steel Female threaded Connector/Adapter each 965 965
for 48.60 mm outer dia X 50 mm nominal threaded
8899 Stainless steel Male threaded Connector/Adapter for each 193 193
15.88 mm outer dia X 15 mm nominal threaded
8900 Stainless steel Male threaded Connector/Adapter for each 227 227
22.22 mm outer dia X 15 mm nominal threaded
8901 Stainless steel Male threaded Connector/Adapter for each 248 248
22.22 mm outer dia X 20 mm nominal threaded
8902 Stainless steel Male threaded Connector/Adapter for each 313 313
28.58 mm outer dia X 20 mm nominal threaded
8903 Stainless steel Male threaded Connector/Adapter for each 320 320
28.58 mm outer dia X 25 mm nominal threaded
8904 Stainless steel Male threaded Connector/Adapter for each 461 461
34.00 mm outer dia X 25 mm nominal threaded
8905 Stainless steel Male threaded Connector/Adapter for each 565 565
34.00 mm outer dia X 32 mm nominal threaded
8906 Stainless steel Male threaded Connector/Adapter for each 649 649
42.70 mm outer dia X 32 mm nominal threaded
8907 Stainless steel Male threaded Connector/Adapter for each 726 726
42.70 mm outer dia X 40 mm nominal threaded
8908 Stainless steel Male threaded Connector/Adapter for each 840 840
48.60 mm outer dia X 40 mm nominal threaded
8909 Stainless steel Male threaded Connector/Adapter for each 1138 1138
48.60 mm outer dia X 50 mm nominal threaded
8910 Stainless steel Valve Connector for 15.88 mm outer each 234 234
dia X 15 mm nominal dia threaded
8911 Stainless steel Valve Connector for 22.22 mm outer each 276 276
dia X 15 mm nominal dia threaded
8912 Stainless steel Valve Connector for 22.22 mm outer each 295 295
dia X 20 mm nominal dia threaded
8913 Stainless steel Valve Connector for 28.58 mm outer each 424 424
dia X 25 mm nominal dia threaded
8914 Stainless steel Valve Connector for 34.00 mm outer each 629 629
dia X 32 mm nominal dia threaded
8915 Stainless steel Valve Connector for 42.70 mm outer each 875 875
dia X 40 mm nominal dia threaded
8916 Stainless steel Valve Connector for 48.60 mm outer each 1176 1176
dia X 50 mm nominal dia threaded
8917 SS Female Threaded Elbow 90o for 15.88 mm outer each 150 150
dia X 15 mm nominal dia threaded
8918 Stainless steel Female Threaded Elbow 90o for 22.22 each 191 191
mm outer dia X 15 mm nominal dia threaded
8919 Stainless steel Female Threaded Elbow 90o for 22.22 each 191 191
mm outer dia X 20 mm nominal dia threaded
8920 Stainless steel Female Threaded Elbow 90o for 28.58 each 205 205
mm outer dia X 25 mm nominal dia threaded
8921 Stainless steel Female Threaded Elbow 90o for 34.00 each 287 287
mm outer dia X 32 mm nominal dia threaded
8922 Stainless steel Female Threaded Elbow 90o for 42.70 each 478 478
mm outer dia X 32 mm nominal dia threaded
8923 Stainless steel Female Threaded Elbow 90o for 42.70 each 478 478
mm outer dia X40 mm nominal dia threaded
8924 Stainless steel Female Threaded Elbow 90o for 48.60 each 683 683
mm outer dia X 40 mm nominal dia threaded
8925 Stainless steel Female Threaded Elbow 90o for 48.60 each 683 683
mm outer dia X 50 mm nominal dia threaded
8926 Stainless steel Male Threaded Elbow 90o for 15.88 each 191 191
mm outer dia X 15 mm nominal dia threaded
8927 Stainless steel Male Threaded Elbow 90o for 22.22 each 205 205
mm outer dia X 15 mm nominal dia threaded
8928 Stainless steel Male Threaded Elbow 900 for 22.22 each 205 205
mm outer dia X 20 mm nominal dia threaded
8929 Stainless steel Male Threaded Elbow 900 for 28.58 each 205 205
mm outer dia X 25 mm nominal dia threaded
8930 Stainless steel MaleThreaded Elbow 900 for 34.00 mm each 287 287
outer dia X 25 mm nominal dia threaded
8931 Stainless steel Male Threaded Elbow 900 for 34.00 each 287 287
mm outer dia X 32 mm nominal dia threaded
8932 Stainless steel Male Threaded Elbow 900 for 42.70 each 478 478
mm outer dia X 32 mm nominal dia threaded
8933 Stainless steel Male Threaded Elbow 900 for 42.70 each 478 478
mm outer dia X 40 mm nominal dia threaded
8934 Stainless steel Male Threaded Elbow 900 for 48.60 each 683 683
mm outer dia X 40 mm nominal dia threaded
8935 Stainless steel Male Threaded Elbow 900 for 48.60 each 683 683
mm outer dia X 50 mm nominal dia threaded
8936 Stainless steel Cap for 15.88 mm outer dia pipe each 45 45

8937 Stainless steel Cap for 22.22 mm outer dia pipe each 64 64

8938 Stainless steel Cap for 28.58 mm outer dia pipe each 84 84

8939 Stainless steel Cap for 34.00 mm outer dia pipe each 163 163

8940 Stainless steel Cap for 42.70 mm outer dia pipe each 236 236

8941 Stainless steel Cap for 48.60 mm outer dia pipe each 299 299

8942 Stainless steel Pipe Bridge for 15.88 mm outer dia each 214 214
pipe
8943 Stainless steel Pipe Bridge for 15.88 mm outer dia each 271 271
pipe
8944 Stainless steel Pipe Bridge for 28.58 mm outer dia each 407 407
pipe
8945 4 Point facade glass bracket without flat head bolts Nos 3318 3318

8946 2 Point facade glass bracket (wall mounted with out Nos 1659 1659
flat head bolt)
8947 1 Point facade glass bracket (wall mounted with out Nos 1300 1300
flat head bolt)
8948 Flate head bolt for brackets of spider glazing Nos 651 651

8949 400 mm long fin plate without fastners pair 5931 5931

8953 Micro Silica kg 32 32

8954 Stop end tubes for diaphragmwall 600 mm dia. sqm 4.5 4.5

8955 Driving end tubes for diaphragm wall 600 mm dia. sqm 72 72

8956 Bi-Axial Extruded GeoGrids of Minimum Tensile sqm 100 100


Strength 15 kN/m in the longitudinal and transverse
8957 Bi-Axial
directionExtruded GeoGrids of Minimum Tensile sqm 115 115
Strength 20kN/m in the longitudinal and transverse
8958 Bi-Axial
directionExtruded GeoGrids of Minimum Tensile sqm 185 185
Strength 30kN/m in the longitudinal and transverse
8959 Bi-Axial
directionExtruded GeoGrids of Minimum Tensile sqm 275 275
Strength 40kN/m in the longitudinal and transverse
8960 Geosynthetic
direction Drainage with two filtering nonwoven sqm 530 530
geotextiles having a “W” configuration as longitudinal
8961 Geosynthetic Drainage
parallel channels. Composite
Minimum having
thickness to be 7.2mm, sqm 630 630
thermobonding
with two filteringaUV
draining corepolypropylene
stabilized - HDPE geonet
8962 Synthetic
comprises of two sets of parallel overlayedstrength-
Geogrid having Ultimate tensile ribs sqm 220 220
100 kN/mconnected to have a rhomboidal shape with
integrally
8963 Synthetic Geogrid Ultimate tensile strength- 150 kN/m sqm 230 230
8964 Synthetic Geogrid Ultimate tensile strength- 200 kN/m sqm 320 320

8965 Synthetic Geogrid Ultimate tensile strength- 250 kN/m sqm 355 355

8966 Synthetic Geogrid Ultimate tensile strength- 300kN/m sqm 365 365

8967 Synthetic Geogrid Ultimate tensile strength- 350kN/m sqm 370 370

8968 Synthetic Geogrid Ultimate tensile strength- 400kN/m sqm 475 475

8969 Synthetic Geogrid Ultimate tensile strength- 500kN/m sqm 535 535

8970 Synthetic Geogrid Ultimate tensile strength- 600kN/m sqm 550 550

8971 Synthetic Geogrid Ultimate tensile strength- 700kN/m sqm 685 685

8972 Synthetic Geogrid Ultimate tensile strength- 800kN/m sqm 750 750

8973 Synthetic Geogrid Ultimate tensile strength- 900kN/m sqm 900 900

8974 Synthetic Geogrid Ultimate tensile strength- 1000kN/m sqm 1025 1025

8975 Synthetic Geogrid Ultimate tensile strength- 1100kN/m sqm 1000 1000

8976 Synthetic Geogrid Ultimate tensile strength- 1200kN/m sqm 1088 1088

8977 Aluminium profile industrial troughed sheet of Alloy sqm 600 600
31500/31000/40800, conforming to IS 1254, IS 737, IS
8978 Aluminium
2676, 0.71 profile industrial
mm thick, troughed
the profile detailsheet
widthof Alloy
1044/920 sqm 785 785
31500/31000/ 40800,
mm, cover width conforming
1000/875 mm. to IS 1254, IS 737,
9001 C.P. Brass
IS 2676, Centre
0.91 Hole Basin
mm thick, Mixerdetail
the profile Withwidth
Cast Spout each 1600 1600
1044/920 mm, cover width 1000/875 mm.
9977 Carriage L.S. 2 2

9988 Carriage and sundries L.S. 2 2

9999 Sundries L.S. 2 2

Add item
10001 Sqm 400
6 mm thick square edge Everest fibre
cement board ceiling Tile of size 595x595
mm,
10002 kg 65
B.P. sheet 1.66 mm to 2mm thick
10003 Sqm 4900

Eco 4000 series(Double Rebate) window &


Single Rebate and Double Rebate Door
Frames including double shutter frame .
10004 Stainless Steel 32 gauge Fly mesh of 304 grades with Sqm 450
144 holes per square Inch.
10005 Grill made of 10mm sq. MS Bars welded to at 150mm Sqm 870
center-to-center, 6mm x 12mm MS flat. Total grill unit
should be powder coated and fixed to window frame
with screws.
10006 Door frame fabricated from sections roll formed out of Rmt 720
1.2mm thick galvanized steel (Base steel as per IS
513) with zinc of 120
gms/sq.mtr.

10007 Door frame double revate fabricated from sections roll Rmt 795
formed out of 1.2mm thick galvanized steel (Base steel
as per IS 513) with zinc of 120
gms/sq.mtr.

10008 uni stone cladding 12mm Sqm 500

10009 U-PVC pipes (working pressure 4 kg / cm2) Single metre 330


socketed pipe 115 mm dia
10010 150 mm dia PVC single equal branch with oval access Each 350
door, bolts and nuts etc.
10011 110 mm dia PVC single equal branch with oval access Each 275
door, bolts and nuts etc.
10012 75 mm dia PVC single equal branch with oval access Each 225
door, bolts and nuts etc.
10013 150 mm dia PVC door bend with oval access door, Each 350
bolts and nuts etc.
10014 110 mm dia PVC door bend with oval access door, Each 275
bolts and nuts etc.
10015 75 mm dia PVC door bend with oval access door, bolts Each 225
and nuts etc.
10016 150 mm dia PVC single equal branch plain door, bolts Each 330
and nuts etc.
10017 110 mm dia PVC door bend bolts and nuts etc. Each 200

10018 75 mm dia PVC door bend , bolts and nuts Each 180

10019 etc.
150 mm dia PVC double equal branch with oval Each 350
access door, bolts and nuts etc.
10020 110 mm dia PVC double equal branch bolts and nuts Each 250
etc.
10021 75 mm dia PVC double equal branch , bolts and nuts Each 180
etc.
10022 150 mm dia PVC collers, bolts and nuts etc. Each 200

10023 110 mm dia PVC collers bolts and nuts etc. Each 170

10024 75 mm dia PVC collers , bolts and nuts etc. Each 140

10025 110 mm X 75 mm PVC floor trap of self cleaning Each 250


design
17887 day -0.58 320.83 -186.08
17654 day -0.41 320.83 -131.54
17028 tonne 0.011 4940 54.34
17029 tonne 0.011 94.34 1.04
17030 cum 0.015 900 13.5
17031 cum 0.015 106.13 1.59
21553 tonne 0.016 4940 79.04
21554 tonne 0.016 94.34 1.51
21555 cum 0.022 900 19.8
21556 cum 0.022 106.13 2.33
18923 1006 0.024
21581 tonne 0.025 4940 123.5
21582 tonne 0.025 94.34 2.36
21583 cum 0.033 900 29.7
21584 cum 0.033 106.13 3.5
17657 day 0.06 476 28.56
17658 day 0.06 374.5 22.47
17898 day 0.08 476 38.08
17899 day 0.08 374.5 29.96
17026 100 0.1 1104.66 110.47
21551 100 0.1 3866.3 386.63
21580 100 metr 0.1 5799.46 579.95
17636 cum 0.16 5954.35 952.70 A
17035 day 0.2 320.83 64.17
17653 cum 0.22 7835.75 1723.86 A
17004 day 0.23 320.83 73.79
17869 cum 0.25 5954.35 1488.59 A
17644 sqm 0.25 235.5 58.87 A
17876 cum 0.31 7835.75 2429.08 A
21560 day 0.33 320.83 105.87
17626 cum 0.34 5715.2 1943.17 A
17656 sqm 0.44 468.3 206.05 A
21557 day 0.46 476 218.96
21558 day 0.46 374.5 172.27
17850 cum 0.55 4955.2 2725.36 A
18340 0.557
17032 day 0.59 476 280.84
17033 day 0.59 374.5 220.96
21589 day 0.625 476 297.5
17893 sqm 0.88 468.3 412.11 A
17860 cum 0.93 5715.2 5315.14 A
17659 each 1 1400 1400
17034 day 1.16 320.83 372.16
21559 day 1.83 320.83 587.12
17875 sqm 2.19 235.5 515.74 A
17025 each 4 55 220
17660 L.S. 6.76 2 13.52
17661 Add
L.S. 1 % Water 6.76 2 13.52
15562 charges
Add Cesson@"W"
1% 6.83
15568 on "Z" 9.05
17024 metre 10 445 4450
21550 metre 10 2310 23100
21579 metre 10 4494 44940
17655 kg 10.57 75.4 797.02 A
17662 L.S. 13.52 2 27.04
17888 factor
kg 0.1405) on 24.83 75.4 1872.18 A
15564 "X" 96.92
18 9999 100
52 9999 100
76 9999 100
111 9999 100
148 9999 100
172 9999 100
1449 9999 100
1476 9999 100
1510 9999 100
1570 9999 100
1605 9999 100
472 100
1535 profit and 100
15566 overheads on "Y" 118.01
15561 TOTAL 683 W
15563 TOTAL 689.83 X
15565 TOTAL 786.75 Y
15567 Total 904.76 Z
20128 Say 2688.3
18172 Say 6458.75
20967 charges
Say on "W- 7026.95
A"
22178 factor 0.1405) on 9001.27 90.01
22180 "X-A"
overheads on "Y- 9091.28 1277.33
22182 A"
overheads on "Y- 10368.61 1555.29
22222 A"
Add Cess @ 1% 11306.76 1696.01
22184 on "Z-A"on "W-
charges 11923.9 119.24
22522 A"
factor 0.1405) on 12698.38 126.98
22524 "X-A"
Add Cess @ 1% 12825.36 1801.96
22224 on "Z-A" on "Y-
overheads 13002.77 130.03
22526 A"
overheads on "Y- 14627.33 2194.1
22567 A"
Add Cess @ 1% 14660.73 2199.11
22528 on
Add"Z-A"
Cess @ 1% 16821.43 168.21
22569 on "Z-A" 16859.84 168.6
factor 0.1405) on
22990 "X-A"
overheads on "Y- 19389.35 2724.2
22992 A"
Add Cess @ 1% 22113.55 3317.03
22994 on "Z-A"
Add Cess @ 1% 25430.59 254.31
23036 on "Z-A" on "Y-
overheads 25430.59 254.31
21948 A"
factor 0.1405) on 33245.92 4986.89
22478 "X-A"
Add Cess @ 1% 36387.38 5112.43
21950 on "Z-A" 38232.81 382.33
23181 overheads
Say on "Y- 39469.15
22480 A"
Add Cess @ 1% 41499.81 6224.97
22482 on "Z-A" 47724.78 477.25
16000 - (3.14 x D² / 4)
16020 - (3.14 x D² / 4)
16051 - (3.14 x D² / 4)
16071 - (3.14 x D² / 4)
597 - 32 mm Outer dia
21002 13.9.1 :prepration
2.40x1.00 of m pile
= 2.40 sqm
head
23069 etc. for
prepration of pile head
23112 etc. for
prepration of pile head
23160 etc. for
prepration of pile head
23190 etc. for
prepration of pile head
23205 etc. for
prepration of pile head
23225 etc. forin cement mortar
:4885
18199 1:4 (1 cement
( 1 cement : 1.5: coarse
20336 sand : 3 : 2 coarse sand
( 1 cement
20277 : 4 graded stone
18522 (-) = 0.037 cum
17793 #ERROR! (-) 0.008 cum
17943 #ERROR! (-) 0.008 cum
17701 (-)
(-) 0.008
0.008 cum
cum Total= 0.340
17558 #ERROR! cum
17564 #ERROR! (-) 0.02 cum
17801 #ERROR! (-) 0.021 cum
17581 #ERROR! (-) 0.042 cum
6125 (-)0.006cum.
6155 (-)0.009cum.
6175 (-)0.014cum.
6207 (-)0.014cum.
6227 (-)0.029cum.
6276 (-)0.0640cum.
(0.06+0.04) = 0.10 cum @
20711 80 kg/cum : 1.5 coarse
(1 cement
21073 sand : 3 graded
(1 cement stone
: 4 coarse
17538 sand : 8 graded stone
18419 (1 cement : 4 coarse sand)
7497 (110
(116162gm)- 2484.3) sqmm =
16170 #ERROR! 113677.7 sqmm Say
16138 - (3.14/2)R²
16101 (3.14/2)R²
(confirming to IS 4885) in
18905 cement mortar
(For cutting holes1:4average
(1
19496 size
(For 30x30
cuttingcm in 23
holes cm
average
19543 size
(For 30x30
cuttingcm in 23
holes cm
average
19587 size 30x30
(i) Earth cm in
work in 23 cm
5370 excavation including
(i) Earth work in
5440 excavation
(i) Earth workincluding
in
5523 excavation including
excavation including
5151 refilling
excavationandincluding
5215 refilling
excavationandincluding
5299 refilling
1:5:10 (1andCement : 5 fine
5156 sand :
work in cement mortar 1:
5226 4(1
work in cement mortar
5161 1:4
work (1in cement mortar
5309 1:4
work (1in cement mortar
5380 1:4
work (1in cement mortar
5461 1:4 (1in cement mortar
work
5533 1:4 (1
17521 (inside)
(inside) with locking
5544 arrangement
(iv) 12mm cement plaster
5166 1:3 12mm
(iv) (1 Cement : 3 Coarse
cement plaster
5385 1:3 (1 Cement : 3 Coarse
5196 (ix)
reinforcement for RCC
5413 slab steel @ for RCC
reinforcement
5262 work etc.
reinforcement for RCC
5331 work etc.
reinforcement for RCC
5484 work etc.
17520 (low duty)
19160 (medium
(Rate as perduty)
item no
10326 13.4.1 13.4.1 of
(Rate as per item no sqm 1.2 186.10
5751 13.99.1 14.54.1
(Rate asof S.H.
per itemRepair
no to sqm 0.673 56.70
5779 13.99.1 14.54.1
(Rate asof S.H.
per itemRepair
no to sqm 0.845 56.70
5798 13.99.1 14.54.1
(Rate as per item no to
of S.H. Repair sqm 1.061 56.70
5817 13.99.1 14.54.1
(Rate asof S.H.
per itemRepair
no to sqm 1.334 56.70
5846 13.99.1 14.54.1
(Rate asof S.H.
per itemRepair
no to sqm 1.52 56.70
5865 13.99.1 14.54.1
(Rate asof S.H.
per itemRepair
no to sqm 1.894 56.70
7530 18.30.1 18.30.1 of
(Rate as per item no each 10 132.4
7553 18.30.1 18.30.1
18.30.1 ofof SH : Water each 10 132.4
7623 18.30.1 Supply)
18.30.1 of SH : Water each 2 132.4
7734 18.30.1 Supply)
20.47.5 of SH : Water each 2 132.4
7702 18.30.5 Supply)
20.47.5 of SH : Water each 2 297.9
7806 18.30.5 Supply)
(Rate as per item No. each 2 297.9
4797 18.24 18.24
(Rate as Ofper
SH:item
Water No. quintal 5.63 296.4
4885 18.24 18.24 Of SH: Water quintal 7.25 296.4
(Rate as per item No.
4959 18.24 18.24 Ofper
(Rate as SH:item
WaterNo. quintal 12.15 296.4
4985 18.24 18.24 Ofper
(Rate as SH:item
WaterNo. quintal 15.05 296.4
5021 18.24 18.24 Of SH: Water
18.24 Of SH: Water quintal 17.99 296.4
4762 18.24 Supply)
18.24 Of SH: Water quintal 4.43 296.4
4824 18.24 Supply)
18.24 Of SH: Water quintal 5.63 296.4
4859 18.24 Supply)
18.24 Of SH: Water quintal 6.83 296.4
4922 18.24 Supply)
18.24 Of SH: Water quintal 8.65 296.4
5057 18.24 Supply)
18.24 Of SH: Water quintal 22.99 296.4
5083 18.24 Supply)
18.24 Of SH: Water quintal 24.24 296.4
5119 18.24 Supply)
(Rate as per item no. 2.8.1 quintal 30.34 296.4
21117 (Rate as per item no. 2.8.1 cum
of 1.73 181.00
11138 2.8.1 of SH:as
(Rate Earth
per work)
item no. 2.8.1 cum 16.31 181.00
11179 2.8.1 of SH:as
(Rate Earth
per work)
item no. 2.8.1 cum 16.17 181.00
11210 2.8.1 of SH:as
(Rate Earth
per work)
item no. 2.8.1 cum 15.96 181.00
11250 2.8.1 of SH: Earth work)
(Rate as per item no. 2.8.1 cum 15.7 181.00
11292 2.8.1 of SH:as
(Rate Earth
per work)
item no. 2.8.1 cum 16.56 181.00
11323 2.8.1 of SH:as
(Rate Earth
per work)
item no. 2.8.1 cum 17.26 181.00
11361 2.8.1 of SH:as
(Rate Earth
per work)
item no. 2.8.1 cum 17.79 181.00
11403 2.8.1 of SH: Earth work)
(Rate as per item no. 2.8.1 cum 18.14 181.00
11444 2.8.1 of SH:as
(Rate Earth
per work)
item no. 2.8.1 cum 18.23 181.00
11475 2.8.1 of SH:as
(Rate Earth
per work)
item no. 2.8.1 cum 18.38 181.00
11516 2.8.1 of SH:as
(Rate Earth
per work)
item no. 2.8.1 cum 18.24 181.00
11557 2.8.1 of
(Rate as per item no. 2.8.1 cum
SH: Earth work) 17.44 181.00
5154 of SH: Earthsub-heads
No.13.65.1 work) cum 0.3 181.00
5896 13.65.1 finishing)
No.13.65.1 sub-heads sqm 0.673 71.10
5914 13.65.1 finishing) sub-heads
No.13.65.1 sqm 0.845 71.10
5942 13.65.1 finishing)
No.13.65.1 sub-heads sqm 1.061 71.10
5960 13.65.1 finishing)
No.13.65.1 sub-heads sqm 1.334 71.10
5978 13.65.1 finishing)
No.13.65.1 sub-heads sqm 1.52 71.10
6005 13.65.1 finishing) sub-heads
No.13.65.1 sqm 1.894 71.10
6023 13.65.1 finishing)
No.13.65.1 sub-heads sqm 2.387 71.10
6052 13.65.1 finishing)
No.15.2.1 of SH. sqm 2.796 71.10
20259 15.2.1 dismantling
(Rate as per and
item cum 1.18 1094.60
4998 No.18.20.5 Of
(Rate as per itemSH: Water each 20 297.9
7586 18.30.2 No.18.30.2 Of
(Rate as per item each 10 214.3
4765 No.18.30.2
(Rate as perOf SH: Water each
item 20 214.3
4801 No.18.30.2
No.18.30.2 OfOf SH: Water each
SH:Water 20 214.3
7755 18.30.2 Supply)
(Rate as per item each 2 214.3
7646 18.30.2 No.18.30.2)
(Rate as per item each 2 214.3
4827 No.18.30.3
(Rate as perOfitem each 20 227.7
4862 No.18.30.3
(Rate as perOfitem each 20 227.7
4900 No.18.30.4
(Rate as perOf SH: Water each
item 20 269.8
4925 No.18.30.4
No.18.30.4 Of SH:
Of SH: Water
Water each 20 269.8
7679 18.30.4 Supply)
No.18.30.4 Of SH:Water each 2 269.8
7785 18.30.4 Supply) each 2 269.8
(Rate as per item
4963 No.18.30.5
(Rate as perOf SH: Water each
item 20 297.9
5025 No.18.30.6
(Rate as perOf SH: Water each
item 20 413.15
5060 No.18.30.6 Of
(Rate as per item SH: Water each 20 413.15
5097 No.18.30.7
(Rate as perOf SH: Water each
item 20 419.85
5122 No.18.30.7
(Rate as perOf Water each
SH:No.2.25
item 20 419.85
11139 2.25 of SH Earth
(Rate item No.2.25 cum
as perwork) 16.31 135.80
11180 2.25 of
(Rate as per item No.2.25 cum
SH Earth work) 16.17 135.80
11211 2.25 of SH Earth
(Rate item No.2.25 cum
as perwork) 15.96 135.80
11251 2.25 of SH Earth
(Rate item No.2.25 cum
as perwork) 15.7 135.80
11293 2.25 of SH Earth
(Rate item No.2.25 cum
as perwork) 16.56 135.80
11324 2.25 of
(Rate as per item No.2.25 cum
SH Earth work) 17.26 135.80
11362 2.25 of SH Earth
(Rate as perwork)
item No.2.25 cum 17.79 135.80
11404 2.25 of SH Earth
(Rate as perwork)
item No.2.25 cum 18.14 135.80
11445 of SH Earth
2.25 (Rate as perwork)
item No.2.25 cum 18.23 135.80
11476 2.25 of SH Earth work)
(Rate as per item No.2.25 cum 18.38 135.80
11517 2.25 of SH Earth
(Rate as perwork)
item No.2.25 cum 18.24 135.80
11558 2.25 of
no.SH Earth work)
18.40.1) Making cum 17.44 135.80
2316 chases
(Rate same as per item metre 10 6.65
2347 no. 18.40.2 Of SH Water
(spun) C.I. Pipe of Class B metre 10 7.8
8622 conforming to of Class B
(spun) C.I. Pipe
8658 conforming to of Class B
(spun) C.I. Pipe
8683 conforming
(spun) to of Class B
C.I. Pipe
8718 conforming to of Class B
(spun) C.I. Pipe
8754 conforming to of Class B
(spun) C.I. Pipe
8779 conforming to of Class B
(spun) C.I. Pipe
8814 conforming
(spun) to of Class B
C.I. Pipe
8851 conforming to of Class B
(spun) C.I. Pipe
8876 conforming to of Class B
(spun) C.I. Pipe
8910 conforming to box
(v) C.I. surface
5543 400x200x200mm
(v) C.I. surface box with
5246 hinged cover
5173 (vi)
5249 (vi)
(vi) Carriage of C.I. surface
5320 9977 box
(vi) Carriage of C.I. surface L.S. 8.06 2
5392 9977 box
(vi) Carriage of C.I. surface L.S. 8.06 2
5473 9977 box
(vi) Carriage of C.I. surface L.S. 53.82 2
5546 9977 box
(vii) Cement concrete L.S. 13.52 2
5321 1:2:4 (1 Cement
(vii) Cement concrete:
5547 1:2:4 (1 Cement
(vii) Cement :
concrete
5175 1:2:4 (1 Cement
(vii) Cement :2
concrete
5251 1:2:4 (1 Cement
(vii) Cement :2
concrete
5393 1:2:4Cement
(vii) (1 Cement :2
concrete
5474 1:2:4 (1 Cement
lifting the materilas: 2 upto
5183 floor
lifting the materilas upto
5259 floor
lifting the materilas upto
5328 floor
lifting the materilas upto
5410 floor
lifting the materilas upto
5481 floor
lifting the materilas upto
5554 floor
5334 (x) Form work
5417 (x) Form work
5487 (x) Form work
5569 (x) Form work
5268 (xi)
5338 (xi)
5421 (xi)
5491 (xi)
5573 (xi)
19532 )) finished with a floating
19492 coat of neat
) finished cement
with a floating
19539 coat of neat cement
) finished with a floating
19573 coat of neat cement
5551 )0.018 cum.
5478 )0.0375 cum.
[(2x8.133)/
18259 360]x(4/3)x3.14x(0.45)³
360]x(4/3)x3.14x(0.45)³
18357 =0.017 cum
[(2x8.133)/
18508 360]x(4/3)x3.14x(0.61)³
[(2x8.133)/
20281 360]x(4/3)x3.14x(0.61)³
360]x(4/3)x3.14x(0.76)³
18741 =0.083 cum
[1/2x0.166x(1.20+0.72)] =
16517 0.159 sqm
[1/2x0.166x(1.20+0.72)] =
16574 0.159 sqm
[1/2x0.166x(1.20+0.72)] =
16629 0.159 sqm say 0.16 sqm
[1/2x0.337x(1.20+0.60)] =
16463 0.303 sqm
[1/2x0.358x(1.20+0.40)] =
16353 0.286 sqm
[1/2x0.358x(1.20+0.40)] =
16405 0.286 sqm
[116162 say 0.29
+ 8281 sqm
(1/0.4081
16152 #ERROR! -157°48'
180° x 3.14/180)]
16156 #ERROR! sqmm
[116162 + 8281 x (-0.30)]
16168 #ERROR! sqmm
[116162 + 8281 x (2.45-
16158 #ERROR! 2.75)] sqmm
[R²/2(3.14/2-Q)] -
16134 - (3.14/2)R²
21778 @ 35 kg per pile
21856 @ 35 kg per pile
21887 @ 35 kg per pile
21926 @ 35 kg per pile
21964 @ 35 kg per pile
22002 @ 35 kg per pile
22033 @ 35 kg per pile
22856 @ 35 kg per pile
22890 @ 35 kg per pile
22970 @ 35 kg per pile
23012 @ 35 kg per pile
20938 @ 48.06 kg/cum
6342 1472 @ Rs. per metre
6374 @ Rs. per metre
6399 @ Rs. per metre
22813 @35 kg per pile
16847 367 0.005 tonne
16982 983 0.015cum
18965 1003 0.018 q
19905 0.02 cum
17066 367 0.024 tonne
20666 6.1.1 0.0535 cum Say 0.54 cum
20609 0.06 cum
20684 0.06
0.062cum
cum @ 80 kg/cum =
20620 4.96 kg
0.075x0.075x10 m =
10408 0.05625 cum
20330 0.089 cum@ 48.06 kg/cum
0.13 cum
20866 = 6.25 kg
0.131cumx80kg/cum. =
5485 10.48kg.
0.15 = 0.57 sqm Total=
18379 1.75 sqm
0.155÷3x[0.09+0.032+(0.0
16557 9x0.032)1/2]
0.155÷3x[0.09+0.032+(0.0
16612 9x0.032)1/2]
0.156mx0.18m =
5397 (-)0.0034 cum.
17981 0.15x0.15 m = 0.03 cum
18080 0.15x0.15 m = 0.03 cum=
0.165cum.x80kg/cum.
5263 13.2kg
5254 0.1685 cum.
box 0.61x0.41mx0.15m=
5477 (-
4036 0.17x 10 =1.70 kg
15844 0.18x50 = 9 kg m = 0.004
0.20x0.20x0.10
18932 cum
0.20x0.20x0.10 m = 0.004
18974 cum
0.20x0.20x0.10 m = 0.004
19055 cum
0.20x0.20x0.10 m = 0.004
19089 cum
0.20x0.20x0.23 = 0.009
19634 cum
0.20x0.20x0.23 = 0.009
19709 cum
4062 0.20x10=2.00 kg
17583 #ERROR! 0.215 cum@Say
0.22 cum 0.22kg/cum
48.06 cum
17509 =0.223cum.x80kg/cum.
10.57 kg =
5567 17.84 kg.
4097 0.23x10=2.30
0.241 cum. Lesskgsurface
5550 box 0.42x0.22mx0.2m = (-
17803 #ERROR! 0.249 cum say 0.25 =
0.274cum.x80kg/cum.
5332 21.92
0.2774kg.
cum. Less surface
5324 box
10429 0.2x0.2x10 m = 0.40 cum
5169 0.30x0.30=0.09sqm.
0.061 cum Total =0.107
16498 cum
0.061 cum Total=0.107
16335 cum
0.061 cum Total=0.107
16385 cum
0.061 cum Total=0.107
16555 cum
0.061 cum Total=0.107
16610 cum
0.31 cum @ 80.09 kg/cum
17741 =0.322÷3x[0.09+0.023+(0.0
24.83 kg
16500 9x0.023)1/2]
17990 5.22.1 0.33 cum = 26.43 kg.
0.345÷3x[0.09+0.01+(0.09
16337 x0.01)1/2]
0.345÷3x[0.09+0.01+(0.09
16387 x0.01)1/2]
20222 0.378 cum Say 0.38 cum
4123 0.3x10=3.00
0.40x0.25x0.40kg = 0.040
19642 cum
0.40x0.45x1.00 mm =
19781 0.18 cum
0.40x0.45x1.05 m = 0.189
19641 cum
0.4133 cum. Less surface
5396 box 0.7854x0.156mx =
0.41cum.x80kg/cum.
5415 32.80kg.
20598 0.45x0.10 m = 0.045
0.45x0.25x0.45 sqm
= 0.0510
19717 cum
0.45x0.45 m = 0.202 sqm
20615 0.45x0.20 m = 0.09
0.45x0.45x0.075 m =sqm
0.02
21075 cum
0.45x0.50x1.00 mm =
19827 0.225 cum
0.45x0.50x1.15 m = 0.259
19716 cum
4158 0.4x10=4 00 kg
4194 0.54x10 =5.40 kg = (-)
0.575x0.575x0.15
19246 0.0496 cum
0.60mx0.45m=0.27sqm.
5541 Total=1.32sq
5570 0.60mx0.45m=0.27sqm.+
0.60mx0.60m=0.36sqm.+
5488 3.32mx0.15m
0.61x0.455x0.15 = 0.50
m = sqm.
(-)
20923 0.042 cum
0.61x0.45x0.15 m = (-)
20843 0.042 cum
4220 0.62x10=6.20 kg
0.68x0.68x0.075m=0.035c
5159 um. Say 0.04 cum.
0.68x0.68x0.10 m = 0.046
16333 cum
0.68x0.68x0.10 m = 0.046
16383 cum
0.68x0.68x0.10 m = 0.046
16496 cum
0.68x0.68x0.10 m = 0.046
16553 cum
0.68x0.68x0.10 m = 0.046
16608 cum
0.68x0.68x0.65m=0.301cu
5153 2.8.1 m.
20342 0.70x0.15 =(-) 0.089
0.725x0.725x0.15 = cum
19244 0.0788 cum
4258 0.74x10=7.40 kg
6123 0.756 cum.+
6153 0.777 cum.+
0.7854x0.156mx0.156mx
5325 0.18m = (-)0.0034 cum.
0.7854x0.156mx0.156mx
5256 0.18 = (-)0.0034 cum.
0.7854x1.020x1.020x0.15
20287 m =0.123 cum
4292 0.79x10=7.90 kg
17945 #ERROR! 0.803 cum Say 0.80 cum
6173 0.804 cum.+ = (-) 0.096
0.80x0.80x0.15
19323 cum
6205 0.82 cum.+
6225 0.858 cum.+ = (-)
0.85x0.70x0.15
19219 0.0893 cum
4318 0.85x10=8.50
0.88x0.96x0.075 kg m =
20683 0.063 cum Say
0.90mx0.90m=0.81sqm.+
5335 4.52mx0.15m
external = 0.68
surface shallsqm.
be
18224 19.9.1 paid for separately)
0.91x0.91x0.075 m = :
20608 0.062 cum Say
17795 #ERROR! 0.934 cum Say 0.93
0.95x0.95x0.15 cum
= 0.1354
19321 cum
17971 0.96x0.96 m =0.922 sqm
18070 0.96x0.96 m =0.922 sqm
8715 1 m pipes = 85.30 Kg
19613 1 metre
22996 Cost of 1 metre pile 7343.97
23038 Cost of 1 metre( pile
1:1.5:3 1 cement : 1.5
20919 coarse
coarse sand ::33graded
sand graded
20839 stone
coarse sand : 3 graded
20606 stone
1:4 (1 cement : 4 coarse
17698 sand)
1:4 (1 cement : 4 coarse
19708 sand)
1:4 (1 Cement : 4 Coarse
20193 sand)
1:4 (1 for
cement :4 coarse
16396 sand)
1.00x0.85x0.15 = 0.1275
19217 cum
1.02 * 12.30 = 12.546 kg =
2389 0.012546
1.02 * 15.90tonne
= 16.218 kg =
2426 0.016218
1.02 * 24.60tonne
= 25.092 kg =
2453 0.025092 tonne
1.02 * 31.70 = 32.334 kg =
2491 0.032334
1.02 * 36.50tonne
= 37.23 kg =
2526 0.03723 tonne
1.02 * 51.70 = 52.73 kg =
2552 0.05273 tonne
1.02 * 66.30 = 67.626 kg =
2590 0.067626 tonne
1.02 * 86.40 = 88.128 kg =
2627 0.088128 tonne
4353 1.02x10=10.20
1.11mx1.06mx0.15 kg m=
20518 0.176*cum
1.15 12.30Say 0.18 cum
= 14.145 kg =
2112 0.014145 tonne
1.15 * 12.30 = 14.145 kg =
2302 0.014145 tonne
1.15 * 15.90= 18.285 kg =
2138 0.018285 tonne
1.15 * 15.90= 18.285 kg =
2342 0.018285 tonne
1.15 * 24.60 = 28.29 kg =
2175 0.02829 tonne
1.15 * 31.70 = 36.455 kg =
2200 0.036455 tonne
1.15 * 36.50 = 41.975 kg =
2237 0.041975 tonne
1.15 * 51.70 = 59.455 kg =
2274 0.059455 tonne= 0.167
1.16x0.96x0.15
20841 cum
1.20mx1.20m=1.44sqm.
5388 Total=6.42sqm.
5418 1.20mx1.20m=1.44sqm.+
5168 1.20x0.50=0.60sqm
17993 1.20x0.90 = 1.08 sqm
18092 1.20x0.90 = 1.08 sqm
1.21x1.06x0.1m=0.128cu
5531 m. Say 0.13 cum. =
1.21X1.06X0.85M
5525 1.09cum.
1.21x1.21x0.1m=0.146cu
5224 m. Say 0.15 cum.
1.21x1.21x0.1m=0.146cu
5459 m. Say 0.15 cum.
5442 1.21X1.21X1.00M
1.21x1.21x1.00m=1.464cu
5217 m.
1.22mx1.065mx0.15 m=
20762 0.195 cum
20080 1.29 cum
21120 1.2x1.2x1.2 = 1.73 cum
19790 1.30x1.00 m = 1.30 sqm
19662 1.30x1.05 m = 1.36 sqm
1.31mx1.11mx0.15 m=
20823 0.22 cum
1.31x1.06x0.15 = 0.208
20921 cum
6255 1.359 cum.+
1.36mx1.06mx0.15 =
20032 0.216 cum
6274 1.418 cum.+
19746 1.450x1.15 m = 1.67 sqm
19837 1.45x1.00 m = 1.45 sqm
1.46mx1.21mx0.15 m=
20893 0.26 cum
1.51x1.41x0.20 m = 0.426
17540 cum Say 0.43 cum
1.51x1.51x0.1m=0.228cu
5307 m. Say 0.23 cum. =
1.51X1.51X1.25M
5301 2.85cum.
1.66mx0.115x0.50m=0.09
5163 5cum.
1.66x0.115x0.04 m =
16349 0.008 cum
1.66x0.115x0.04 m=
16401 0.008 cum
1.66x0.115x0.04 m =
16459 0.008 cum
1.66x0.115x0.04 m=
16513 0.008 cum
1.66x0.115x0.04 m
16570 =0.008 cum
1.66x0.115x0.04 m
16625 =0.008 cum
1.66x0.115x0.675 m=
16345 0.129
1.66x0.115x0.675 mcum
cum say 0.13 =
16397 0.129 cum say 0.13mcum
1.66x0.115x0.675 =
16455 0.129 cum say 0.13
1.66x0.115x0.675 m = cum
16509 0.129 cum say 0.13mcum
1.66x0.115x0.675 =
16566 0.129 cum say 0.13 cum
1.66x0.115x0.675 m =
16621 0.129 cum say 0.13
1.66x1.36x0.15 cum
= 0.339
20383 cum
1.66x1.36x0.15 = 0.339
20392 cum
1.66x1.36x0.15 = 0.339
20432 cum
1.66x1.36x0.15 = 0.339
20441 cum
1.67x1.67x0.225 m = 0.63
18233 cum
the external surface shall
18459 19.11.1 be paid for separately)
1.71mx1.11mx0.15 m=
20657 0.285 cum Say 0.29 cum
19615 1.8 =0.55556 Nos
16314 4.1.10 1.80 cum
1.81x1.51x0.20 m = 0.547
17694 cum Say
1.81x1.51x0.200.55 cum
m = 0.547
18034 cum Say 0.55 cum
1.81x1.51x0.20 m = 0.547
19935 cum Say 0.55 cum
1.81x1.81x0.1m=0.328cu
5378 m. Say 0.33 cum.
5372 1.81X1.81X1.25M
1.91 m x 0.23m x0.45 m =
20661 0.199 cum
1/2x3.14x0.10x0.10x1.00
19783 =1/2x3.14x0.10x0.10x1.50
0.008 cum
19645 = 0.012 cum
1/2x3.14x0.15x0.15x1.00
19829 =1/4x3.14x0.15x0.15x1.50
0.018 cum
19720 =½x3.14x1.13x0.80x0.23m
0.027 cum
20205 =½x3.14x1.13x0.80x0.23m
0.327 cum
20220 = 0.327
10 gradedcumstone
5157 aggregate
aggregate 40 mm nominal
16332 size)
aggregate 40 mm nominal
16382 size)
aggregate 40 mm nominal
16495 size)
aggregate 40 mm nominal
16552 size)
aggregate 40 mm nominal
16607 size)
10 m of 200 mm dia C.I.
3504 pipe class 'A'
6070 10 metre long.
6266 10 metre long.
7640 100 mm
7577 18.59.3 100 mm dia
7746 18.61.2 100 mm dia
21155 19.34.1 100 mm dia
3685 100 mm dia metre
4757 100 mm dia
4782 100 mm dia
8625 100 mm dia
9375 100 mm dia metre
9852 100 mm dia metre
12096 100 mm dia
12135 100 mm dia
15787 100 mm dia
21067 100 mm dia
100 mm dia C.I. Double
8614 18.71.1 Flanged
100 mm Pipedia Ductile Iron
8931 18.72.1 Class K-7
100 mm dia pipes
Ductile Iron
9357 18.72.15 Class K-9
100 mm dia pipes
Ductile Iron
9842 18.73.1 Double Flanged
7635 18.60.2 100 mm dia nominal bore
3675 18.27.1 100 mm dia pipe
8213 18.70.1 100
100 mm
mm dia dia pipes
sand cast iron
19607 19.22.1 drop connection
100 mm dia. cast iron
8618 pipes
100 mm double flangediron
dia. ductile
9846 pipes double flanged
16828 19.6.1 100 mm dia. R.C.C. pipe
3455 18.22.1 100 mm diameter
4752 18.31.1 100 mm diameter
15782 19.1.1 100 mm diameter
16655 19.5.1 100
100 mm
mm diameter
diameter C.I.
10484 18.80.2 pipe
100 mm diameter C.I.
10828 18.81.2 pipe
100 mm diameter C.I.
11170 18.82.2 pipe
100 mm diameter C.I.
11610 18.83.2 pipe
4023 18.28.1 100 mm diameter pipe
4434 18.30.2 100 mm diameter pipe
6284 18.41.9 100
100 mm
mm diameter
diameter pipe
S.W.
15995 19.2.1 pipe
100 mm diameter S.W.
16089 19.3.1 pipe
7447 18.58.1.1 100
100 mm
mm nominal
nominal dia
inner dia
2028 18.9.9 Pipes
1000 mm dia Ductile Iron
9333 18.72.14 Class
1000 K-7
mmpipes
dia Ductile Iron
9805 18.72.29 Class K-9 pipes
21955 20.1.6 1000 mm dia piles
23000 20.5.6 1000 mm dia piles
8590 18.70.15 1000 mm
(Laying bydia pipes
mannual/
21335 19.35.4 machanical means)
(Laying by mannual/
21614 19.36.4 machanical
1000 mm dia. means)
cast iron
9337 pipes
1000 mm dia.mcast
(in 5.5 lengths)
iron
9809 pipes (in 5.5 m lengths)
17308 19.6.11 1000 mm dia. R.C.C. pipe
9814 2334 1000mm dia
9342 2357 1000mm dia
9373 2319 100mm dia
9850 2319 100mm dia
8950 2343 100mm
100mm dia dia. cast iron 100 0.1 231.98
8946 pipes (india.
100mm 5.5 cast
m lengths)
iron
9360 pipes (in 5.5 m lengths)
100mm dia. spun iron
3679 pipes (in 5.5 m lengths)
16322 19.4.1 100x100 mm size P type
5247 100x100x75mm (inside)
3865 1031.00
10x0.15x0.15x0.15Kg m=
10367 0.033 cum
10x0.30x0.30x0.344m =
10317 0.309
10x2x0.3x0.3m cum = 1.80
10323 sqm
1069 110 mm Outer dia
17353 19.6.12 1100 mm dia. R.C.C. pipe
16105 12
12 =mm 124cement
mm plaster 1:3
20534 (121 mm cement : 3 coarse
cement plaster 1:3
20590 (121 mm cement : 3 coarse
cement plaster 1:3
20668 (121 mm cement : 3 coarse
cement plaster 1:3
20772 (121 mm cement : 3 coarse
cement plaster 1:3
20831 (121 mmcement : 3 coarse
cement plaster 1:3
17712 (1 cement
12 : 3 plaster 1:3
mm cement
17964 (1
12cement : 3 plaster 1:3
mm cement
18054 (1
12cement : 3 plaster 1:3
mm cement
18372 (1
12cement : 3 plaster 1:3
mm cement
19651 (1 cement
12 : 3 plaster 1:3
mm cement
18186 (1 cement
12 mm cement : 3 4.20x1 m 1:3
plaster =
16351 (1
12cement : 3 coarse
mm cement plaster 1:3
16403 (1 cement : 3 coarse
12 mm cement plaster 1:3
16461 (1 cement
12 : 3 coarse
mm cement plaster 1:3
16515 (1 cement : 3 coarse
12 mm cement plaster 1:3
16572 (1
12cement : 3 coarse
mm cement plaster 1:3
16627 (1 cement : 3 coarse
12 mm cement plaster 1:3
18139 (1 cement
12 : 3 coarse
mm cement plaster 1:3
18156 (1 cement : 3 coarse
12 mm cement plaster 1:3
18203 (1
12cement : 3 coarse
mm cement plaster 1:3
18284 (1 cement : 3 coarse
12 mm cement plaster 1:3
18525 (1 cement
12 : 3 coarse
mm cement plaster 1:3
18754 (1 cement : 3 coarse
12 mm cement plaster 1:3
18848 (1
12cement : 3 coarse
mm cement plaster 1:3
19727 (1 cement : 3 coarse
12 mm cement plaster 1:3
20981 (1
12cement : 3 coarse
mm cement plaster 1:3
21000 (1 cement : 3 coarse
12 mm cement plaster 1:3
21029 (1
12cement : 3 coarse
mm cement plaster 1:3
18909 (1 cement: 3 coarse
12 mm cement plaster 1:4
10321 (1
12cement :
mm cement plater 1:3
19491 (121 mm
cement
cement platersand
: 3 coarse 1:3
19538 (121 mm
cement : 3 coarse sand
cement plater 1:3
19572 ( 1 cement : 3 coarse sand
16005 1200 mm
16025 1200 mm
16076 1200 mm
21986 20.1.7 1200 mm dia piles
(Laying by mannual/
21363 19.35.5 machanical means)
(Laying by mannual/
21651 19.36.5 machanical means)
17387 19.6.13 1200 mm dia. R.C.C. pipe
12 18.1.1 1216 (16 mm OD) pipe
204 18.2.1 1216 (16 mm OD) pipe
347 18.3.1 1216
1216 (16
mmmm OD) pipe
PE-AL-PE
16 8300 Composit
1216 mm PE-AL-PE pipe
pressure metre 10 62
208 8300 Composit pressure pipe
1216 mm PE-AL-PE metre 10 62
351 8300 Composit pressure pipe metre 10 62
3711 125 mm dia
4819 125 mm dia
4854 125 mm dia
3701 18.27.2 125 mm dia pipe
4814 18.31.2 125
125 mm
mm diameter
diameter C.I.
10518 18.80.3 pipe
125 mm diameter C.I.
10862 18.81.3 pipe
125 mm diameter C.I.
11201 18.82.3 pipe
125 mm diameter C.I.
11628 18.83.3 pipe
4057 18.28.2 125 mm diameter pipe
4457 18.30.3 125
125 mm
mm diameter
grating pipe
7475 7411 withwaste hole dia with
125 mm nominal each 1 30
7472 18.58.1.2 25 mm waste
125mm holeiron
dia. spun
3705 pipes (in 5.5 m lengths)1:3
12mm cement plaster
18424 (1 cement
12mm :
cement plaster 1:3
18448 (1 cement :
12mm cement plaster 1:3
5231 (1 Cement
12mm : 3 Coarse
cement plaster 1:3
5313 (1 Cement : 3 Coarse
12mm cement plaster 1:3
5466 (1 Cement
12mm : 3 Coarse
cement plaster 1:3
5538 (1 Cement : 3 Coarse
12mm cement plaster 1:3
18674 (1 cement
12mm : 3 coarse
cement plaster 1:3
18686 (1 cement : 3 coarse
15 mm Battery Based
11848 3327 Sensor Pillar Cock each 1 5800
2094 18.10.1 15 mm dia nominal bore
2296 18.11.1 15 mm dia nominal bore
2383 18.12.1 15
15 mm
mm diadia nominal
PTMT stopbore
7403 cock
15 mm(male thread)stop
dia PTMT each 1 71
7288 18.55.1 cock (male thread)
5588 18.38.1 15 mm diameter pipe
5747 18.39.1 15 mm diameter pipe
5892 18.40.1 15 mm diameter pipe
6068 18.41.1 15 mm diameter pipe
2734 18.15.1 15 mm nominal bore
2780 18.16.1 15 mm nominal bore
2972 18.18.1 15 mm nominal bore
3301 18.20.1 15 mm nominal bore
3374 18.21.1.1 15 mm nominal bore
6504 18.46.1 15 mm nominal bore
6703 18.47.1 15 mm nominal bore
6971 18.49.1 15 mm nominal bore
6990 18.50.1 15 mm nominal bore
7019 18.51.1 15 mm nominal bore
7038 18.52.1 15 mm nominal bore
11844 18.84.1 15
15 mm
mm nominal
nominal bore
bore and
7862 30 cm length
15 mm nominal bore and each 1 46.5
7863 45
15 cm
mmlength
nominal bore with each 1 57
10185 18.74.1 30cm
15 mmlength
nominal bore with
10215 18.74.2 45 cm length
mm long, weighing not
7829 18.62.1 less
122mmthanlong,
138 weighing
gms
7137 18.54.2 not less than
weighing not 99
lessgms
than
7381 18.56.2 120 gms
mm long, weighing not
7164 18.54.3 less
mm than
long,110 gms not
weighing
7427 18.57.2 less
mm than
long,46 gms not
weighing
7269 18.54.4 less than
mm long,93 gms not
weighing
7400 18.57.1 less
weighing notgms
than 75 less than 32
10235 18.75.1 gms
15 mm nominal outer dia
1433 18.7.1 Pipes
15 mm nominal outer dia
1627 18.8.1 Pipes
15 mm nominal outer dia
1769 18.9.1 Pipes
7104 7400 15 mm PTMT bib cock each 1 71
7100 18.54.1 15
15 mm
mm PTMT
PTMT bibbib cock
cock
7168 7402 15
long
mm body
PTMTwithbib
flange each 1 116
7141 7401 cockwith flange (fancy) each 1 105
12092 15.88
15.88 mm
mm outer
outer dia
12086 18.86.1 dia .Pipes.
11873 18.85.1 15.88
15.88 mm
mm outer
outer dia
dia pipe
X 15
14637 mm nominal dia threaded
2174 15% for fiitings =
2199 15% for fiitings =
2236 15% for fiitings =
2273 15% for fiitings =
2341 15% for fiitings =
7673 150 mm
7776 18.61.3 150 mm dia
21193 19.34.2 150 mm dia
4880 150 mm dia
4917 150 mm dia
9401 150 mm dia metre
9878 150 mm dia metre
15832 150
150 mm
mm dia
dia C.I. Double
8650 18.71.2 Flanged Pipe
150 mm dia Ductile Iron
8966 18.72.2 Class
150 mmK-7diapipes
Ductile Iron
9391 18.72.16 Class K-9 pipes
150 mm dia Ductile Iron
9868 18.73.2 Double Flanged
7668 18.60.3 150 mm dia nominal bore
3736 18.27.3 150 mm dia pipe
8235 18.70.2 150
150 mm
mm diadia pipes
sand cast iron
19693 19.22.2 drop connection
150 mm dia. cast iron
8970 pipes
150 mm (in dia.
5.5 m lengths)
cast iron
9395 pipes (in 5.5 m lengths)
150 mm dia. cast iron
8654 pipes
150 mm double flangediron
dia. ductile
9872 pipes double flanged
16872 19.6.2 150 mm dia. R.C.C. pipe
3483 18.22.2 150 mm diameter
4875 18.31.3 150 mm diameter
15818 19.1.2 150 mm diameter
16673 19.5.2 150
150 mm
mm diameter
diameter C.I.
10540 18.80.4 pipe
150 mm diameter C.I.
10882 18.81.4 pipe
150 mm diameter C.I.
11241 18.82.4 pipe
150 mm diameter C.I.
11645 18.83.4 pipe
4092 18.28.3 150 mm diameter pipe
4490 18.30.4 150 mm diameter pipe
6312 18.41.10 150
150 mm
mm diameter
diameter pipe
S.W.
16016 19.2.2 pipe
150 mm diameter S.W.
16128 19.3.2 pipe
150 mm nominal inner dia
2064 18.9.10 Pipes
16428 19.4.2 150 x 100 mm size P type
22024 20.1.8 1500 mm dia piles
9399 2321 150mm dia
8974 2344 150mm
150mm dia dia. spun iron
3740 pipes (in 5.5 m lengths)
3938 1512.70 Kg for lead
1538 suitable
8021 2309 jointing upto 300mm dia
7057 18.53.1 15mm nominal bore
372 18.3.2 1620 (20 mm OD ) pipe
36 18.1.2 1620 (20 mm OD) pipe
239 18.2.2 1620
1620 (20
mmmm OD) pipe
PE-AL-PE
50 8301 1620 mm PE-AL-PE pipe metre
Composit pressure 10 78
243 8301 Composit pressure pipe metre
1620 mm PE-AL-PE 10 78
376 8301 Composit pressure pipe metre 10 78
16259 180°+ 29°26')] sqmm
21405 1800 mm
(Laying bydia
mannual/ metre
21680 19.36.6 machanical means)
(Laying by mannual/
21399 19.35.6 machenical means)
16542 19.4.3 180x150 mm size P type
1x0.25x0.25 m = 0.0625
19654 Say 0.06 sqmm = 0.0625
1x0.25x0.25
19729 Say 0.06 sqm
1x0.56x0.23x0.15 m=
18039 0.019 cum
1x0.79x0.23x0.15 = 0.027
18040 cum
1x40.26x.65x0.75
11319 m=19.63 cum
1x40.26x.70x0.75
11357 m=21.14 cum
1x40.26x.75x0.75
11399 m=22.65 cum
1x40.26x.80x0.75
11440 m=24.16 cum
1x40.26x.85x0.75
11471 m=25.67 cum
1x40.26x.90x0.75
11512 m=27.18 cum
1x40.26x1.00x0.75
11553 m=30.20 cum
1x40.26x55x0.75 m=16.61
11134 cum
1x40.26x55x0.75 m=16.61
11175 cum
1x40.26x55x0.75 m=16.61
11206 cum
1x40.26x55x0.75 m=16.61
11246 cum
1x40.26x60x0.75 m=18.12
11288 cum
11885 2 * X / 100
11924 2 * X / 100
11951 2 * X / 100
11989 2 * X / 100
12028 2 * X / 100
12067 2 * X / 100
12111 2 * X / 100
12141 2
2 *Coarse
X / 100
sand ; 4 graded
5322 stone aggregate
2 Coarse sand ; 4 graded
5548 stone
2 aggregate
coarse sand ; 4 graded
10365 stone aggregate
2 coarse sand : 4 grade
19319 stone
2 coarseaggregate
sand : 4 graded
18047 stone aggregate
2 coarse sand : 4 graded
18276 stone
2 aggregate
coarse sand : 4 graded
18364 stone aggregate
2 coarse sand : 4 graded
18517 stone aggregate
5540 2.10mx0.50m=1.05sqm.
20983 13.9.1 2.13x1.00 m = 2.13 sqm
17810 #ERROR! 2.19 sqm
2.20mx0.23mx0.70 m=
20662 0.354 cum
20707 2.20x0.15
the external m surface
= 0.330 shall
sqm
18695 19.13.1 be paid for separately)
2.40mx0.75m=1.80sqm.“
5468 0.90mx0.90m =0.36sqm.“
20194 2.45 depth
19080 2.47 kg/m =0.018
2.74x2.74x0.30 m q= 2.25
18798 cum
2.82 m x 0.23m x0.45 m =
20522 0.29 cum
21031 13.9.1 2.90x1.00 m = 2.90 sqm
2490 2% for fiitings =
2525 2% for fiitings =
2551 2% for fiitings =
2589 2% for fiitings =
16248 20 + 20 = 290 mm
22995 Cost of 20 metre pile 146879.38
23037 Cost of 20
20 metre
mm diapileGunmetal gate
2846 1926 valve with wheel each 1 325
2132 18.10.2 20 mm dia nominal bore
2335 18.11.2 20 mm dia nominal bore
2420 18.12.2 20
20 mm
mm dia
dia.nominal
PTMT stopbore
7319 7405 cock each 1 97
5619 18.38.2 20 mm diameter pipe
5766 18.39.2 20 mm diameter pipe
5910 18.40.2 20 mm diameter pipe
6113 18.41.2 20 mm diameter pipe
2843 18. 17.1A 20 mm nominal bore
2751 18.15.2 20 mm nominal bore
2797 18.16.2 20 mm nominal bore
3000 18.18.2 20 mm nominal bore
3327 18.20.2 20 mm nominal bore
3390 18.21.1.2 20 mm nominal bore
3436 18.21.2.2 20 mm nominal bore
6534 18.46.2 20 mm nominal bore
6733 18.47.2 20
mmmm nominal
long, bore
weighing not
7847 18.62.2 less than 198 gms
mm long, weighing not
7315 18.55.2 less than 88
weighing notgms
less than 40
10261 18.80.1 gms
20 mm nominal outer dia
1467 18.7.2 Pipes
20 mm nominal outer dia
1664 18.8.2 Pipes
20 mm nominal outer dia
1807 18.9.2 Pipes
19320 20 mm nominal size )
10366 20 mm nominal size)
10407 20 mm nominal size)
18277 20 mm nominal size)
18365 20 mm nominal size)
18518 20 mm nominal size)
18841 20 mm nominal size)
18931 20 mm nominal size)
18973 20 mm nominal size)
19088 20 mm nominal size)
20382 20 mm nominal size)
20431 20
20 mm
mm nominal
nominal size)
size) for
18048 benching
payment shall be
22063 20.2 measured up to
7696 200 mm
7797 18.61.4 200 mm dia
3781 200 mm dia metre
4954 200 mm dia
4980 200 mm dia
8695 200 mm dia
9436 200 mm dia metre
9914 200 mm dia metre
15865 200
200 mm
mm diadia C.I. Double
8675 18.71.3 Flanged Pipe
200 mm dia Ductile Iron
9000 18.72.3 Class
200 mmK-7dia
pipes
Ductile Iron
9426 18.72.17 Class K-9
200 mm dia pipes
Ductile Iron
9904 18.73.3 Double Flanged
7691 18.60.4 200 mm dia nominal bore
3762 18.27.4 200 mm dia pipe
8267 18.70.3 200
200 mm
mm diadia.pipes
cast iron
9004 pipes (in 5.5 m
200 mm dia. cast lengths)
iron
9430 pipes (in 5.5 m lengths)
200 mm dia. cast iron
8679 pipesmm
200 double flangediron
dia. ductile
9908 pipes double flanged
4949 18.31.4 200 mm diameter
15861 19.1.3 200 mm diameter
16701 19.5.3 200
200 mm
mm diameter
diameter C.I.
10571 18.80.5 pipe
200 mm diameter C.I.
10915 18.81.5 pipe
200 mm diameter C.I.
11283 18.82.5 pipe
200 mm diameter C.I.
11671 18.83.5 pipe
4118 18.28.4 200 mm diameter pipe
4513 18.30.5 200
200 mm
mm diameter
diameter pipe
S.W.
16047 19.2.3 pipe
200 mm diameter S.W.
16182 19.3.3 pipe
9434 2322 200mm dia
9912 2322 200mm dia
9008 2345 200mm
200mm dia dia. spun iron
3775 pipes (in 5.5 m lengths)
406 18.3.3 2025 (25 mm OD ) pipe
70 18.1.3 2025 (25 mm OD) pipe
264 18.2.3 2025
2025 (25
mmmm OD) pipe
PE-AL-PE
74 8302 2025 mm PE-AL-PE pipe
Composit pressure metre 10 110
267 8302 Composit pressure pipe
2025 mm PE-AL-PE metre 10 110
410 8302 Composit
20mm dia.pressure pipe
pipe 10 metre metre 10 110
6115 long.
slab =
5177 0.53mx0.53mx0.075m
slab =
5549 1.06mx0.91mx0.25m
slab = =
5253 1.06mx1.06mx0.15m
slab = =
5476 1.06mx1.06mx0.15m =
slab =
5323 1.36mx1.36mx0.15m
slab = =
5395 1.66mx1.66mx0.15m =
799 20xP/100
865 20xP/100
904 20xP/100
932 20xP/100
970 20xP/100
1003 20xP/100
1032 20xP/100
1071 20xP/100
11912 18.85.2 22.22 mm outer dia Pipe
12127 18.86.2 22.22
20mmmm Outerdia
nominal dia pipes
14672 threaded
16154 #ERROR! 22°12')] sqmm
3053 9988 25 mm dia
2168 18.10.3 25 mm dia nominal bore
2447 18.12.3 25 mm dia nominal bore
5641 18.38.3 25 mm diameter pipe
5794 18.39.3 25 mm diameter pipe
5938 18.40.3 25 mm diameter pipe
6143 18.41.3 25 mm diameter pipe
2826 18.17.1 25 mm nominal bore
3018 18.18.3 25 mm nominal bore
3048 18.19.1 25 mm nominal bore
3344 18.20.3 25 mm nominal bore
6554 18.46.3 25 mm nominal bore
6753 18.47.3 25 mm nominal
152mm bore
long, weighing
7876 18.62.3 not lessnominal
25 mm than 440outer
gms dia
1503 18.7.3 Pipes
25 mm nominal outer dia
1701 18.8.3 Pipes
25 mm nominal outer dia
1832 18.9.3 Pipes
25 to 40 mm nominal
2650 18.13.1 bore
5016 250 mm dia
5052 250 mm dia
8721 250 mm dia metre
9462 250 mm dia metre
9949 250
250 mm
mm dia
dia C.I. Double metre
8710 18.71.4 Flanged Pipe
250 mm dia Ductile Iron
9024 18.72.4 Class
250 mmK-7dia
pipes
Ductile Iron
9452 18.72.18 Class K-9 pipes
250 mm dia Ductile Iron
9930 18.73.4 Double Flanged
3797 18.27.5 250 mm dia pipe
8289 18.70.4 250
pipesmm dia pipes
double flanged
8714 Weight of
250 mm dia. ductile iron
9934 pipes double flanged
16916 19.6.3 250 mm dia. R.C.C. pipe
5011 18.31.5 250 mm diameter
16719 19.5.4 250 mm diameter
15904 19.7.2.1 250
250 mm mm diameter
diameter C.I.
10603 18.80.6 pipe
250 mm diameter C.I.
10935 18.81.6 pipe
250 mm diameter C.I.
11314 18.82.6 pipe
250 mm diameter C.I.
11689 19.31.3 pipe
4153 18.28.5 250 mm diameter pipe
4546 18.30.6 250
250 mm mm diameter
diameter pipe
S.W.
16067 19.2.4 pipe
250 mm diameter S.W.
16226 19.3.4 pipe
9460 2323 250mm dia
9032 2346 250mm dia
9938 250mm
250mm dia dia. cast iron
9028 pipes
pipes (in 5.5
(in 5.5 m
m lengths)
lengths)
9456 Weight
250mm dia. spun iron
3801 pipes (in 5.5 m lengths)
441 18.3.4 2532 (32 mm OD ) pipe
105 18.1.4 2532 (32 mm OD) pipe
299 18.2.4 2532
2532 (32 mmmm OD) pipe
PE-AL-PE
109 8303 2532
Composit pressure pipe metre
mm PE-AL-PE 10 157
303 8303 Composit pressure pipe metre
2532 mm PE-AL-PE 10 157
445 8303 Composit
25mm dia.pressure pipe metre
pipe 10 metre 10 157
6145 long.
weighing not less than 62
10278 18.75.3 gms
11940 18.85.3 28.58 mm outer
determining safedia Pipe
23254 allowable
determining lateral
safe load
23271 allowable
2nd class bricklateral load laid
edging
21088 length wise with half
21048 2nd class bricks
2x 3.14/4x(0.525)²x0.150
22497 =2x0.065 cum
3.14/4x(0.7)²x0.30 =
22540 0.23 cum
2x 3.14/4x(0.788)²x0.337
22581 =2x0.329 cum
3.14/4x(0.875)²x0.375
22621 =2x0.23x0.20x0.20
0.451 cum m = (-)
20665 0.018 cum Nte Qty=
19493 13.9.1 2x0.35x0.35 =0.25sqm
2x0.40x0.05x0.10 m=
19647 0.004 cum
19540 2x0.40x0.40
2x0.55x0.55 =0.32
=0.605sqmsqm
19574 Say 0.60 sqm
17968 2x0.56x0.15
2x1.20x(0.90/2)m =x0.17 sqm
17707 (0.30+0.20)/2 = 2.70 cum
2x1.20x(0.90/2)x(0.30+0.2
18049 0)/2 = 0.27 cum
2x1.4x(0.90/2)x(0.20+0.30
20242 )/2 = 0.315 cum
2x1.4x0.90/2x(0.20+0.30)
20025 /2 = 0.315 cum
2x1/2x3.14x0.25 m
20082 x0.230x0.10
2x1/2x3.14x0.25m m
20273 x0.23x0.10 m
2x1/2x3.14x0.25 m
18734 x0.460x0.10
2x1/2x3.14x0.25m m
18817 x0.460x0.10 m
2x1/2x3.14x0.25mx0.23x0
20267 .10 m= 0.018 cum= 0.09
2x½x0.90x0.10m
17969 sqm
2x½x0.90x0.10m = 0.09
18068 sqm
2x½x3.14x0.25 m
18250 x0.230x0.10
2x½x3.14x0.25 mm
18350 x0.230x0.10
2x½x3.14x0.25 mm
18501 x0.230x0.10 m
2x½x3.14x0.25mx0.230x0
18243 .10 m = 0.018 cum
2x½x3.14x0.25mx0.230x0
18342 .10 m = 0.018 cum
2x½x3.14x0.25mx0.23x0.
20076 10 m = 0.018 cum
2x½x3.14x0.25mx0.23x0.
20018 1m = 0.018 cum
2x½x3.14x0.25mx0.23x0.
20200 1m = 0.018 cum
2x½x3.14x0.25mx0.23x0.
20206 1m = 0.018 cum
2x½x3.14x0.25mx0.46x0.
18726 10 m = 0.036 cum
2x½x3.14x0.25mx0.46x0.
18808 10 m = 0.036 cum
2x½x3.14x0.70mx0.23x0.
20215 1m = 0.051 cum
2x½x3.14x0.70mx0.23x0.
20221 1m = 0.051 cum Total ==
2x3.14/4(0.15)²x0.23m
20201 0.008 cum
2x3.14/4x(0.10)²x0.23 m=
20769 (-) 0.004 cum
2x3.14/4x(0.15)²x0.23 =
20077 0.008 cum
2x3.14/4x(0.15)²x0.23 =
20268 0.008 cum
2x3.14/4x(0.15)²x0.230 =
18244 0.008 cum
2x3.14/4x(0.15)²x0.230 =
18343 0.008 cum
2x3.14/4x(0.15)²x0.460 =
18727 0.016 cum
2x3.14/4x(0.15)²x0.460 =
18809 0.016 cum Total= 0.052=
2x3.14/4x(0.60)²x0.23
20216 0.130
3 coarsecum sand : 6 graded
10406 stone
3 coarseaggregate
sand : 6 graded
18231 stone aggregate
3 coarse sand : 6 graded
18930 stone
3 coarseaggregate
sand : 6 graded
18972 stone aggregate
3 coarse sand : 6 graded
19087 stone
3 coarseaggregate
sand) finished
18449 with floating
3 coarse sand) coat of neat
finished
18425 with neat cement.
3.02mx0.23mx0.50m=0.3
5535 47cum.
3.02mx0.25m=0.76sqm.
5571 Total
3.05 m = 1.03sqm.
x 0.23m x0.30 m =
20767 0.210 cum
3.05 m x 0.23m x1.00 m =
20979 0.70 cum
16257 3.14 + Q)
3.14/4(1.020)²x0.15 m
18621 =0.123 cum
3.14/4x(0.124)²x0.47 =
16389 0.006 cum Total =
0.006 cum Total= 0.0210.021
16339 cum
3.14/4x(0.124)²x0.485 =
16448 0.006 cum Total = 0.023
3.14/4x(0.124)²x0.485 =
16502 0.006 cum Total= 0.023
3.14/4x(0.182)²x0.70
16559 =0.018 cum
3.14/4x(0.182)²x0.70
16614 =0.018 cum
18521 3.14/4x(0.28)² x 0.15 m
3.14/4x(0.625)²x0.15 :
= (-)
19282 0.0460 cum
3.14/4x(0.775)²x0.15 =
19280 0.0708 cum
3.14/4x(0.8)²x0.15 = (-)
19348 0.0754 cum
3.14/4x(0.80)²x0.15 =(-)
20385 0.075 cum
3.14/4x(0.9)²x0.15 = (-)
19387 0.0955 cum
3.14/4x(0.9)²x0.15 = (-)
19426 0.0955 cum
3.14/4x(0.90)²x0.15 =(-)
20434 0.095 cum
3.14/4x(0.91+0.82)²x0.20
18258 =3.14/4x(0.91+0.82)²x0.20
0.118 cum
18356 =3.14/4x(0.95)²x0.15
0.118 cum =
19346 0.1064 cum
3.14/4x(0.985)²x0.15 =
20491 0.114 cum Less portion
3.14/4x(1.020)²x0.15 m
18279 =0.123 cum
3.14/4x(1.020)²x0.15 m
18367 =0.123 cum
3.14/4x(1.020)²x0.15 m
18749 =0.123 cum
3.14/4x(1.020)²x0.15 m
18843 =0.123 cum
3.14/4x(1.020)²x0.15 m
18520 =0.123 cum Less cover
3.14/4x(1.05)²x0.15 =
19385 0.1299 cum
3.14/4x(1.22)²x0.20 =
18507 0.234 cum
3.14/4x(1.22)²x0.20 =
20280 0.234 cum
3.14/4x(1.52)²x0.20 =
18740 0.363 cum
3.14x(0.80)²/4-
18289 0.80x0.15+0.80x½x
3.14x(0.80)²/4-
18378 0.80x0.15+0.80x½x3.14x
3.14x(0.80+0.56)/2x0.49 =
18286 1.05 sqm
3.14x(0.80+0.56)/2x0.49 =
18375 1.05 sqm
3.14x(1.136)²/4-
18529 1.136x1/2x3.14x0.15
3.14x(1.136)²/4-
18630 1.136x1/2x3.14x0.15
3.14x(1.136+0.56)/
18527 2x1.216 = 3.241 sqm
3.14x(1.136+0.56)/
18628 2x1.216 = 3.241 sqm
3.14x(1.14+0.79)/
18240 2x0.711x0.23 = 0.496
3.14x(1.14+0.79)/
18339 2x0.711x0.23 = 0.496
3.14x(1.45+0.79)/
20074 2x1.32x0.23 = 1.069
3.14x(1.45+0.79)/ 1.32
20264 2x1.32x0.23 = 1.069
3.14x(1.454)²/4-
18759 1.454x0.15+1.454x1/2x
3.14x(1.454)²/4-
18853 1.454x0.15+1.454x1/2x
3.14x(1.454+0.56)/
18756 2x1.799 = 5.694 sqm
3.14x(1.454+0.56)/
18850 2x1.799 = 5.694 sqm
3.14x(1.98+0.905)/
18723 2x0.345x1.93 = 3.019 cum
3.14x(1.98+0.905)/
18805 2x0.345x1.93 = 3.019 cum
18290 3.14x0.15 = 0.57 sqm
18760 3.14x0.15 =1.786 sqm
18854 3.14x0.15 =1.786 sqm
3.14x0.56x0.075 = 0.13
18287 sqm
3.14x0.56x0.075 = 0.13
18376 sqm
3.14x0.56x0.075 = 0.13
18528 sqm
3.14x0.56x0.075 = 0.13
18629 sqm
3.14x0.56x0.075 = 0.13
18757 sqm
3.14x0.56x0.075 = 0.13
18851 sqm
3.14x1.14x0.074x0.23 =
18239 0.061
3.14x1.14x0.074x0.23 =
18338 0.061
3.14x1.45x0.85x0.23 =
20263 0.891
3.14x1.98x0.25x0.46 =
18722 0.716 cum
3.14x1.98x0.25x0.46 =
18804 0.716 cum
5116 2309 3.304t.
3.32 m x 0.23m x0.30 m =
20827 0.229
3.32 mcum Less pipe
x 0.23m x1.00 m =
20998 0.76 cum
3.32mx0.15m=0.50sqm. =
5266 0.86 sqm.
3.32mx0.23mx0.75m=0.5
5228 73cum.
3.32mx0.23mx0.75m=0.5
5463 73cum.
18141 13.9.1 3.40x1 m = 3.40 sqm
18158 13.9.1 3.40x1 m =m3.40
3.50x0.15 sqm sqm
= 0.525
20545 Say 0.53 sqm
3.60mx1.00m=3.60sqm.“
5315 0.90mx0.90m
3.82 m x 0.23m=0.81sqm.
x0.30 m =
20897 0.26 cum
3.92mx0.23mx1.15m =
20197 1.037 cum
3.92mx0.23mx2.95m =
20212 2.660 cum
353 30 * X / 100
378 30 * X / 100
412 30 * X / 100
447 30 * X / 100
507 30 * X / 100
1777 30 * X / 100
1814 30 * X / 100
1838 30 * X / 100
1874 30 * X / 100
1911 30 * X / 100
1937 30 * X / 100
1972 30 * X / 100
2009 30 * X / 100
2035 30 * X / 100
2071 30 * X / 100
3373 18.21.1 30 cm length
3842 300 mm dia metre
5078 300 mm dia
5114 300 mm dia
8757 300 mm dia metre
9497 300 mm dia metre
9975 300 mm dia metre
15954 300
300 mm
mm diadia C.I. Double
8747 18.71.5 Flanged
300 mm Pipe
dia Ductile Iron
9059 18.72.5 Class K-7
300 mm diapipes
Ductile Iron
9487 18.72.19 Class K-9 pipes
300 mm dia Ductile Iron
9965 18.73.5 Double Flanged
22490 20.3.1 300 mm dia piles
22650 20.4.1 300 mm dia piles
3832 18.27.6 300 mm dia pipe
8321 18.70.5 300
300 mm
mm diadia.pipes
cast iron
8750 pipes double flangediron
300 mm dia. ductile
9969 pipes double flanged
16969 19.6.4 300 mm dia. R.C.C. pipe
5073 18.31.6 300 mm diameter
15949 19.1.5 300 mm diameter
16746 19.5.5 300
300 mm
mm diameter
diameter C.I.
10626 18.80.7 pipe
300 mm diameter C.I.
10968 18.81.7 pipe
300 mm diameter C.I.
11353 18.82.7 pipe
300 mm diameter C.I.
11717 18.83.7 pipe
4189 18.28.6 300 mm diameter pipe
4569 18.30.7 300
300 mm
mm diameter
diameter pipe
S.W.
16275 19.3.5 pipe
8093 2309 300mm dia
9495 2324 300mm dia
9973 2324 300mm dia
9067 2347 300mm
300mm diadia. cast iron
9063 pipes (in
300mm dia.5.5 cast
m lengths)
iron
9491 pipes (in 5.5 m lengths)
300mm dia. spun iron
3836 pipes (in 5.5 m lengths)
3097 9988 32 mm dia
2194 18.10.4 32 mm dia nominal bore
2484 18.12.4 32 mm dia nominal bore
5673 18.38.4 32 mm diameter pipe
5813 18.39.4 32 mm diameter pipe
5956 18.40.4 32 mm diameter pipe
6163 18.41.4 32 mm diameter pipe
3091 18.19.2 32 mm nominal bore
6583 18.46.4 32 mm nominal bore
6782 18.47.4 32 mm nominal bore
2859 18.17.2 32
32 mm
mm nominal
nominal bore.
outer dia
1528 18.7.4 Pipes
32 mm nominal outer dia
1728 18.8.4 Pipes
32 mm nominal outer dia
1867 18.9.4 Pipes
466 18.3.5 3240 (40 mm OD ) pipe
129 18.1.5 3240
3240 (40
mmmm OD) pipe
PE-AL-PE
135 8304 Composit pressure pipe
3240 mm PE-AL-PE metre 10 235
470 8304 Composit
32mm dia.pressure pipe
pipe 10 metre metre 10 235
6165 long.
11977 18.85.4 34.00
34.00 mmmm outer
outer dia
dia Pipe
X 25
14745 mm nominal dia threaded
34.00 mm outer dia X 32
14762 mm nominal dia threaded
3879 350 mm dia
8782 350 mm dia metre
9533 350 mm dia metre
10011 350
350 mm
mm dia
dia C.I. Double metre
8772 18.71.6 Flanged Pipe
350 mm dia Ductile Iron
9083 18.72.6 Class
350 mm K-7dia
pipes
Ductile Iron
9513 18.72.20 Classmm
350 K-9dia
pipes
Ductile Iron
10001 18.73.6 Double Flanged
3858 18.27.7 350 mm dia pipe
8343 18.70.6 350
350 mm
mm dia
dia.pipes
cast iron
8775 pipesmm
350 double flangediron
dia. ductile
10005 pipes double flanged
16764 19.5.6 350
350 mm
mm diameter
diameter C.I.
10659 18.80.8 pipe
350 mm diameter C.I.
10988 18.81.8 pipe
350 mm diameter C.I.
11394 18.82.8 pipe
350 mm diameter C.I.
11735 18.83.8 pipe
4215 18.28.7 350 mm diameter pipe
4603 18.30.8 350 mm diameter pipe
9531 2325 350mm dia
10009 2325 350mm dia
9091 2348 350mm
350mm dia dia. cast iron
9087 pipes (india.
350mm 5.5 spun
m lengths)
iron
3862 pipes (in 5.5 m lengths)
20430 3aggregate stone m =
3x0.45x0.05x0.10
19722 0.004 cum
3x3.14/4x(100/10)²x(100x
10489 100)/1000x0.5 gms
3x3.14/4x(125/10)²x(100x
10523 100)/1000x0.5 gms
3x3.14/4x(150/10)²x(100x
10553 100)/1000x0.5 gms
3x3.14/4x(200/10)²x(100x
10576 100)/1000x0.5 gms
3x3.14/4x(250/10)²x(100x
10608 100)/1000x0.5 gms
3x3.14/4x(300/10)²x(100x
10631 100)/1000x0.5 gms
3x3.14/4x(350/10)²x(100x
10664 100)/1000x0.5 gms
3x3.14/4x(450/10)²x(100x
10724 100)/1000x0.5 gms
3x3.14/4x(500/10)²x(100x
10756 100)/1000x0.5 gms
3x3.14/4x(600/10)²x(100x
10779 100)/1000x0.5 gms
3x3.14/4x(80/10)²x(100x1
10466 00)/1000x0.5 gms m =
3x3.14x(0.10)²x0.23
20828 (-) 0.005 cum
18136 4 coarse sand )
18200 4 coarse sand )
10322 4 coarse sand)
18237 4 coarse sand)
18907 4
4 coarse sand)aggregate
grade stone
19216 20 mm nominal
4 grade size )
stone aggregate
19243 20 mm nominal size )
4 grade stone aggregate
19279 20 mm nominal
4 grade size )
stone aggregate
19345 20 mm nominal
4 grade size )
stone aggregate
19384 20 mm nominal
4 graded size )
stone 20mm
18422 4.1.3 nominal size)
4 graded stone 20mm
18446 4.1.3 nominal size)
18840 4
4 graded
graded stone
stone aggregate
aggregate
20541 20graded
4 mm nominal
stone aggregate
16348 20 mm nominal
4 graded size)
stone aggregate
16400 20 mm nominal
4 graded size)
stone aggregate
16458 20 mm nominal
4 graded size)
stone aggregate
16512 20graded
4 mm nominal size)
stone aggregate
16569 20 mm nominal size)
4 graded stone aggregate
16624 20 mm nominal
4 graded size)
stone aggregate
18619 20 mm nominal
4 graded size)
stone aggregate
20024 20graded
4 mm nominal size)
stone aggregate
20678 20 mm nominal size)
4 graded stone aggregate
17705 20 mm nominal
4 graded size) for
stone aggregate
20603 20mm nominal size)
18187 13.9.1 4.20 sqm
17967 4.20mx0.35m = 1.47 sqm
18205 4.20x1 m = 4.20 sqm
20191 4.25m deep m = 0.994
4.32x0.23x1.0
18137 cum Say 0.99 cum
4.32x0.23x1.0 m = 0.994
18154 cum Say 0.99 cum
4.32x0.23x1.0m = 0.994
20138 cum Say 0.99 cum
4.52mx0.23mx1.00m=1.0
5311 4cum.
5387 4.80mx1.00m=4.80sqm.
3141 9988 40 mm dia
2230 18.10.5 40 mm dia nominal bore
2520 18.12.5 40 mm dia nominal bore
5694 18.38.5 40 mm diameter pipe
5842 18.39.5 40 mm diameter pipe
5974 18.40.5 40 mm diameter pipe
6184 18.41.5 40 mm diameter pipe
2888 18.17.3 40 mm nominal bore
3135 18.19.3 40 mm nominal bore
6603 18.46.5 40 mm nominal bore
6802 18.47.5 40 mm nominal bore
206mm long, weighing
7894 18.62.4 not lessnominal
40 mm than 690outer
gms dia
1563 18.7.5 Pipes
40 mm nominal outer dia
1904 18.9.5 Pipes
18232 40 mm nominal size)
621 40 mm Outer dia
3904 400 mm dia metre
8817 400 mm dia metre
9559 400 mm dia metre
10038 400
400 mm
mm dia
dia C.I. Double
8807 18.71.7 Flanged Pipe
400 mm dia Ductile Iron
9118 18.72.7 Class
400 mmK-7dia
pipes
Ductile Iron
9549 18.72.21 Class K-9 pipes
400 mm dia Ductile Iron
10027 18.73.7 Double Flanged
21769 20.1.1 400 mm dia piles
22533 20.3.2 400 mm dia piles
22689 20.4.2 400 mm dia piles
22788 20.5.1 400 mm dia piles
3894 18.27.8 400 mm dia pipe
8375 18.70.7 400
400 mm
mm dia
dia.pipes
cast iron
8810 pipes double flangediron
400 mm dia. ductile
10031 pipes double flanged
16782 19.5.7 400
400 mm
mm diameter
diameter C.I.
10682 18.80.9 pipe
400 mm diameter C.I.
11021 18.81.9 pipe
400 mm diameter C.I.
11425 18.82.9 pipe
400 mm diameter C.I.
11763 18.83.9 pipe
4252 18.28.8 400 mm diameter pipe
4626 18.30.9 400 mm diameter pipe
9557 2326 400mm dia
10035 2326 400mm dia
9126 2349 400mm
400mm diadia. cast iron
9122 pipes (in
400mm dia.5.5 cast
m lengths)
iron
9553 pipes (in 5.5 m lengths)
400mm dia. spun iron
3898 pipes (in 5.5 m lengths)
501 18.3.6 4050 (50 mm OD ) pipe
166 18.1.6 4050
4050 (50
mmmm OD) pipe
PE-AL-PE
170 8305 Composit pressure pipe
4050 mm PE-AL-PE metre 10 330
505 8305 40mm dia.pressure
Composit pipe
pipe 10 metre metre 10 330
6198 long.
5158 40mm nominal size)
5223 40mm nominal size)
5306 40mm nominal size)
5377 40mm nominal size)
5530 40mm nominal size)
12016 18.85.5 42.70 mm outer dia Pipe
42.70 mm outer dia X 32
14788 mm
42.70nominal
mm outerdia dia
threaded
X 40
14805 mm nominal dia threaded
3407 18.21.2 45 cm length
3942 450 mm dia metre
8854 450 mm dia metre
9595 450 mm dia metre
10071 450
450 mmmm dia
dia C.I. Double metre
8843 18.71.8 Flanged Pipe
450 mm dia Ductile Iron
9142 18.72.8 Class
450 mm K-7dia
pipes
Ductile Iron
9584 18.72.22 Class K-9 pipes
450 mm dia Ductile Iron
10062 18.73.8 Double Flanged
21800 20.1.2 450 mm dia piles
22069 20.2.1 450 mm dia piles
22574 20.3.3 450 mm dia piles
22835 20.5.2 450 mm dia piles
3931 18.27.9 450 mm dia pipe
8397 18.70.8 450 mm dia pipes
21223 19.35.1 450 mm dia RCC pipes.
21441 19.36.1 450
450 mmmm dia
dia.RCC
castpipes.
iron
8847 pipes double flanged
450 mm dia. ductile iron
10065 pipes double flanged
17057 19.6.5 450 mm dia. R.C.C. pipe
16808 19.5.8 450
450 mmmm diameter
diameter C.I.
10719 18.80.10 pipe
450 mm diameter C.I.
11041 18.81.10 pipe
450 mm diameter C.I.
11466 18.82.10 pipe
450 mm diameter C.I.
11781 18.83.10 pipe
4287 18.28.9 450 mm diameter pipe
4659 18.30.10 450 mm diameter pipe
9593 2327 450mm dia
10069 2327 450mm dia
9162 2350 450mm
450mm dia dia. cast iron
9588 pipes (in
450mm dia. 5.5 spun
m lengths)
iron
3935 pipes
450x100 mmmvertical
(in 5.5 lengths)
20718 grating
C.I. cover (light duty) the
19120 19.18.1 weight of the cover to be
12045 18.85.6 48.60
48.60 mmmm outer
outer dia
dia Pipe
X 40
14822 mm nominal dia
48.60 mm outer dia threaded
X 50
14849 nominal dia threaded
5 fine sand : 10 graded
5305 stone
5 fine aggregate
sand : 10 graded
5447 stone aggregate
5 fine sand : 10 graded
5529 stone aggregate
20997 5 fine sand)
5.12x0.23x0.65 m = 0.765
18038 cum
5.12x0.23x0.80 m = 0.942
17699 cum
5.12x0.23x0.80 m = 0.942
19940 cum
5.12x0.23x1.0 m = 1.178
18182 cum Say 1.18 cum
5.12x0.23x1.0 m = 1.178
18201 cum Say 1.18 cum
5.12x0.23x1.0m = 1.178
20159 cum Say 1.18 cum
5.52mx0.23mx1.20m =
20196 1.524 cum
5.52mx0.23mx1.20m =
20211 1.524 cum
5.72mx0.15m=0.86 sqm.
5419 Total = 2.30sqm.
5.72mx0.23mx1.00m=1.3
5382 16cum.
3183 9988 50 mm dia
7521 18.59.1 50 mm dia
2268 18.10.6 50 mm dia nominal bore
2546 18.12.6 50 mm dia nominal bore
5715 18.38.6 50 mm diameter pipe
5861 18.39.6 50 mm diameter pipe
6001 18.40.6 50 mm diameter pipe
6215 18.41.6 50 mm diameter pipe
2906 18.17.4 50 mm nominal bore
3169 18.19.4 50 mm nominal bore
6632 18.46.6 50 mm nominal bore
6831 18.47.6 50 mm nominal
242mm bore
long, weighing
7923 18.62.5 not lessnominal
50 mm than 1240 gmsdia
outer
1598 18.7.6 Pipes
50 mm nominal outer dia
1930 18.9.6 Pipes
656 50
50 mm
to 80Outer dia
mm nominal
2681 18.13.2 bore
3969 500 mm dia
8879 500 mm dia metre
9622 500 mm dia metre
10107 500
500 mm
mm dia
dia C.I. Double metre
8869 18.71.9 Flanged
500 mm Pipe
dia cover with
17751 1356 frame (medium
500 mm dia cover duty)
with each 1 4400
17910 1356 frame
500 mm (medium
dia cover without each
duty) 1 4400
19159 1357 frame
500 mm dia Ductile Iron each 1 2300
9178 18.72.9 Class
500 mmK-7dia
pipes
Ductile Iron
9611 18.72.23 Class K-9 pipes
500 mm dia Ductile Iron
10087 18.73.9 Double Flanged
21838 20.1.3 500 mm dia piles
22108 20.2.2 500 mm dia piles
22877 20.5.3 500 mm dia piles
3958 18.27.10 500 mm dia pipe
8429 18.70.9 500
500 mm
mm dia
dia.pipes
cast iron
8872 pipesmm
500 double flangediron
dia. ductile
10101 pipes double flanged
17090 19.6.6 500 mmofdia.
weight theR.C.C.
coverpipe
to be
19152 19.18.2 not
500 mm diameter C.I.
10751 18.80.11 pipe
500 mm diameter C.I.
11074 18.81.11 pipe
500 mm diameter C.I.
11507 18.82.11 pipe
500 mm diameter C.I.
11798 18.83.11 pipe
4313 18.28.10 500 mm diameter pipe
4682 18.30.11 500 mm diameter pipe
9620 2328 500mm dia
10105 2328 500mm dia
9187 2351 500mm
500mm diadia. cast iron
9182 pipes (in
500mm dia.5.5 cast
m lengths)
iron
9615 pipes (in 5.5 m lengths)
500mm dia. spun iron
3962 pipes (in 5.5 m lengths)
500x450 mm horizontal
20715 grating
50mm dia. pipe 10 metre
6217 long.
756 50xP/100
21878 20.1.4 550 mm dia piles
22608 20.3.4 550 mm dia piles
22750 20.4.4 550 mm dia piles
22918 20.5.4 550 mm dia piles
56.3x10=563kg=
4784 0.563t=0.56t
560 mm dia cover with
18001 3860 frame
560 mm (Heavy duty)with
dia cover each 1 9000
18100 3860 560
framemm(Heavy duty)without each
dia cover 1 9000
19182 3861 frame (Heavy duty) to be each
weight of the cover 1 5000
19175 19.18.3 not
5x0.40x0.05x0.10 m =
19785 0.010 cum
5x0.45x0.05x0.10 m=
19831 0.011
6 cumstone aggregate
graded
19054 20 mm nominal
6 graded size)
stone aggregate
18797 40
600mmmmnominal size)
dia C.I. Double
8903 18.71.10 Flanged
600 mm Pipe
dia Ductile Iron
9213 18.72.10 Classmm
600 K-7dia
pipes
Ductile Iron
9648 18.72.24 Class K-9 pipes
600 mm dia Ductile Iron
10123 18.73.10 Double Flanged
22149 20.2.3 600 mm dia piles
3994 18.27.11 600 mm dia pipe
8451 18.70.10 600 mm dia pipes
21260 19.35.2 600 mm dia RCC pipes.
21479 19.36.2 600
600 mm
mm dia
dia.RCC
castpipes.
iron
8906 pipes double flangediron
600 mm dia. ductile
10127 pipes double flanged
17133 19.6.7 600
600 mm
mm dia. R.C.C.C.I.
diameter pipe
10774 18.80.12 pipe
600 mm diameter C.I.
11094 18.81.12 pipe
600 mm diameter C.I.
11548 18.82.12 pipe
600 mm diameter C.I.
11824 18.83.12 pipe
4348 18.28.11 600 mm diameter pipe
4715 18.30.12 600 mm diameter pipe
9657 2329 600mm dia
10131 2329 600mm dia
9222 2352 600mm dia
4005 600mm dia metre
8913 600mm dia metre
9659 600mm dia metre
10133 600mm
600mm dia dia. cast iron metre
9217 pipes (in
600mm dia. 5.5 cast
m lengths)
iron
9652 pipes (in 5.5 m lengths)
600mm dia. spun iron
3998 pipes
62.50 (in
mm5.5 m lengths)
nominal inner
1965 18.95.21 dia Pipes
3216 65 mm dia
2583 18.12.7 65 mm dia nominal bore
6019 18.40.7 65 mm diameter pipe
6236 18.41.7 65 mm diameter pipe
2934 18.17.5 65 mm nominal bore
3211 18.19.5 65 mm nominal bore
6652 18.46.7 65 mm nominal bore
6851 18.47.7 65 mm nominal bore
8483 18.70.11 650
700 mmmm diadia pipes
Ductile Iron
9238 18.72.11 Classmm
700 K-7dia
pipes
Ductile Iron
9675 18.72.25 Class K-9 pipes
700 mm dia Ductile Iron
10159 18.73.11 Double Flanged
8505 18.70.12 700
700 mmmm diadia.pipes
ductile iron
10163 pipes double flanged
17177 19.6.8 700 mm dia. R.C.C. pipe
9694 2330 700mm dia
10167 2330 700mm dia
9247 2353 700mm
700mm dia dia. cast iron
9242 pipes (in
700mm dia. 5.5 cast
m lengths)
iron
9689 pipes (in 5.5 m lengths)
210 75 * X / 100
245 75 * X / 100
269 75 * X / 100
305 75 * X / 100
1644 75 * X / 100
1671 75 * X / 100
1708 75 * X / 100
1735 75
75 *inXfoundation
/ 100 & plinth
17697 in cement mortar
75 mm nominal inner dia
1991 18.9.8 Pipes
750 mm dia Ductile Iron
9710 18.72.26 Class K-9 pipes
21917 20.1.5 750 mm dia piles
22189 20.2.4 750 mm dia piles
22958 20.5.5 750 mm dia piles
9719 2331 750mm
750mm diadia. cast iron
9714 pipes (in 5.5 m lengths)
697 75xP/100
722 75xP/100
827 75xP/100
8 graded stone aggregate
17693 40 mm nominal size)
7617 80 mm
7544 18.59.2 80 mm dia
7725 18.61.1 80 mm dia
3261 80 mm dia
2611 18.12.8 80 mm dia nominal bore
7602 18.60.1 80 mm dia nominal bore
10461 18.80.2 80 mm diameter C.I. pipe
10808 18.81.1 80 mm diameter C.I. pipe
11129 18.82.1 80 mm diameter C.I. pipe
11581 18.83.1 80 mm diameter C.I. pipe
4402 18.30.1 80 mm diameter pipe
6048 18.40.8 80 mm diameter pipe
6264 18.41.8 80 mm diameter pipe
2952 18.17.6 80 mm nominal bore
3254 18.19.6 80 mm nominal bore
6681 18.46.8 80 mm nominal bore
6881 18.47.8 80 mm nominal bore
17185 800 mm dia metre
17228 800
800 mm
mm diadia Ductile Iron metre
9274 18.72.12 Class K-7
800 mm diapipes
Ductile Iron
9745 18.72.27 Class K-9 pipes
8536 18.70.13 800
800 mm
mm diadia.pipes
cast iron
9749 pipes (in 5.5 m lengths)
17221 19.6.9 800 mm dia. R.C.C. pipe
9754 2332 800mm dia
9283 2355 800mm
800mm diadia. cast iron
9278 pipes (in 5.5 m lengths)
5414 80kg/cum.
19931 90 cm deep
1030 90
900mm
mmOuter dia Iron
dia Ductile
9299 18.72.13 Class K-7 pipes
900 mm dia Ductile Iron
9770 18.72.28 Class K-9 pipes
8558 18.70.14 900 mm dia pipes
21299 19.35.3 900 mm dia RCC pipes.
21525 19.36.3 900
900 mm
mm diadia.RCC
castpipes.
iron
9774 pipes (in 5.5 m lengths)
pipes (in 5.5 m lengths)
9303 Weight
17265 19.6.10 900 mm dia. R.C.C. pipe
9779 2333 900mm dia
9307 2356 900mm dia
16370 A"
16422 A"
16481 A"
16536 A"
16592 A"
16645 A"
17531 A"
17679 A"
17761 A"
17920 A"
18020 A"
18120 A"
18307 A"
18405 A"
18556 A"
18649 A"
18786 A"
18871 A"
18954 A"
18986 A"
19024 A"
19069 A"
19112 A"
19231 A"
19267 A"
19293 A"
19359 A"
19398 A"
19437 A"
19508 A"
19555 A"
19599 A"
19677 A"
19762 A"
19813 A"
19862 A"
19924 A"
19979 A"
20046 A"
20113 A"
20148 A"
20169 A"
20313 A"
20368 A"
20408 A"
20457 A"
20504 A"
20557 A"
20631 A"
20726 A"
20808 A"
20879 A"
20952 A"
21102 A"
21147 A"
8035 18.66.2 Above 300 mm dia
8087 18.67.2 Above
Above 300 mm dia
50 tonne and upto
23267 20.8.2 100 tonne capacity pile
100 tonne Safe capacity
23202 20.7.1.2 pile
8136 18.68.2 Above 600 mm dia
8184 18.69.2 Above
Above 600 mm dia
the pipe =
6074 150mm+
Above the pipe =
6119 150mm+
Above the pipe =
6149 150mm+
Above the pipe =
6169 150mm+
Above the pipe =
6201 150mm+
Above the pipe =
6221 150mm+
Above the pipe =
6270 150mm+
Above the pipe =
6290 150mm+
6340 accessories
6372 accessories
6397 accessories
22805 Add
Add (multiplying factor
17528 0.1405) on "X-A" factor
Add (multiplying 1387.31
19759 0.1405)
Add 1 %on "X-A"charges on
Water 4090.14
219 "W-A"
Add 1 % Water charges on 1701
254 "W-A"
Add 1 % Water charges on 1981
288 "W-A"
Add 1 % Water charges on 2541 25.41
314 "W-A"
Add 1 % Water charges on 3363.5
706 "W-A"
Add 1 % Water charges on 1373.22
740 "W-A"
Add 1 % Water charges on 1785
765 "W-A"
Add 1 % Water charges on 2228.05
1653 "W-A"
Add 1 % Water charges on 1465.62
1680 "W-A"
Add 1 % Water charges on 1977.5
1717 "W-A"
Add 1 % Water charges on 2604
1754 "W-A"
Add 1 % Water charges on 3479.87
2324 "W-A"
Add 1 % Water charges on 1679.95
2368 "W-A" 2013.84
Add 1 % Water charges on
3577 "W-A"
Add 1 % Water charges on 3609.43
3598 "W-A"
Add 1 % Water charges on 3709.43
3633 "W-A"
Add 1 % Water charges on 5509.43
3654 "W-A"
Add 1 % Water charges on 5509.43
3690 "W-A"
Add 1 % Water charges on 8593.2
3725 "W-A"
Add 1 % Water charges on 10700.99 107.01
3750 "W-A"
Add 1 % Water charges on 12898.66
3786 "W-A"
Add 1 % Water charges on 21962.89
3811 "W-A"
Add 1 % Water charges on 28659.37
3847 "W-A"
Add 1 % Water charges on 38680.47
3883 "W-A"
Add 1 % Water charges on 46344.65
3909 "W-A"
Add 1 % Water charges on 61160.89
3947 "W-A"
Add 1 % Water charges on 74067.75
3973 "W-A"
Add 1 % Water charges on 85967.75
4010 "W-A"
Add 1 % Water charges on 120336.63
4768 "W-A"
Add 1 % Water charges on 24141.51
4804 "W-A"
Add 1 % Water charges on 27052.83
4830 "W-A"
Add 1 % Water charges on 26052.83
4865 "W-A"
Add 1 % Water charges on 32064.15
4903 "W-A"
Add 1 % Water charges on 36067.92
4928 "W-A"
Add 1 % Water charges on 40081.6
4966 "W-A"
Add 1 % Water charges on 75115.09
5001 "W-A"
Add 1 % Water charges on 89141.51
5028 "W-A"
Add 1 % Water charges on 109969.81 1099.7
5063 "W-A"
Add 1 % Water charges on 145216.98 1452.17
5100 "W-A"
Add 1 % Water charges on 155228.3 1552.28
5125 "W-A"
Add 1 % Water charges on 182285.84 1822.86
5199 "W-A"
Add 1 % Water charges on 123.99
5271 "W-A"
Add 1 % Water charges on 139.57
5341 "W-A"
Add 1 % Water charges on 78.62
5424 "W-A"
Add 1 % Water charges on -4.8
5494 "W-A"
Add 1 % Water charges on 256.76
5576 "W-A"
Add 1 % Water charges on 161.62
5598 "W-A"
Add 1 % Water charges on 27.04
5630 "W-A"
Add 1 % Water charges on 27.04
5652 "W-A"
Add 1 % Water charges on 40.56
5684 "W-A"
Add 1 % Water charges on 40.56
5704 "W-A"
Add 1 % Water charges on 53.82
5734 "W-A"
Add 1 % Water charges on 53.82
5755 "W-A"
Add 1 % Water charges on 16.12
5783 "W-A"
Add 1 % Water charges on 16.12
5802 "W-A"
Add 1 % Water charges on 21.58
5831 "W-A"
Add 1 % Water charges on 21.84 0.22
5850 "W-A"
Add 1 % Water charges on 27.04
5869 "W-A" 27.04
Add 1 % Water charges on
5899 "W-A"
Add 1 % Water charges on 16.12
5917 "W-A"
Add 1 % Water charges on 16.12
5945 "W-A"
Add 1 % Water charges on 21.58
5963 "W-A"
Add 1 % Water charges on 21.58
5990 "W-A"
Add 1 % Water charges on 24.44 0.24
6008 "W-A"
Add 1 % Water charges on 24.44
6026 "W-A"
Add 1 % Water charges on 27.04
6055 "W-A"
Add 1 % Water charges on 29.64
7533 "W-A"
Add 1 % Water charges on 37280
7556 "W-A"
Add 1 % Water charges on 45380
7589 "W-A"
Add 1 % Water charges on 59256
7625 "W-A"
Add 1 % Water charges on 2420
7648 "W-A"
Add 1 % Water charges on 3559
7681 "W-A"
Add 1 % Water charges on 5285
7704 "W-A"
Add 1 % Water charges on 5769
7736 "W-A"
Add 1 % Water charges on 2810
7757 "W-A"
Add 1 % Water charges on 4526
7787 "W-A"
Add 1 % Water charges on 5748
7808 "W-A"
Add 1 % Water charges on 8172
8025 "W-A"
Add 1 % Water charges on 5199.43
8045 "W-A"
Add 1 % Water charges on 6209.43
8077 "W-A"
Add 1 % Water charges on 8580.43
8097 "W-A"
Add 1 % Water charges on 9057.43
8127 "W-A"
Add 1 % Water charges on 12409.43
8144 "W-A"
Add 1 % Water charges on 17209.43
8175 "W-A"
Add 1 % Water charges on 13059.43
8192 "W-A"
Add 1 % Water charges on 18759.43
8629 "W-A"
Add 1 % Water charges on 6561.6
8664 "W-A"
Add 1 % Water charges on 10259.33
8699 "W-A"
Add 1 % Water charges on 16221.45
8726 "W-A"
Add 1 % Water charges on 19569.69
8762 "W-A"
Add 1 % Water charges on 25005.23
8797 "W-A"
Add 1 % Water charges on 31507.33
8822 "W-A"
Add 1 % Water charges on 40820.44
8859 "W-A"
Add 1 % Water charges on 52033.88
8884 "W-A"
Add 1 % Water charges on 64698.88
8918 "W-A"
Add 1 % Water charges on 89718.32
8955 "W-A"
Add 1 % Water charges on 8023.2
8979 "W-A"
Add 1 % Water charges on 11438.66
9013 "W-A"
Add 1 % Water charges on 14062.89
9037 "W-A"
Add 1 % Water charges on 18089.37
9072 "W-A"
Add 1 % Water charges on 22610.47
9107 "W-A"
Add 1 % Water charges on 26654.65 266.55
9131 "W-A"
Add 1 % Water charges on 31960.89
9167 "W-A" 38777.75
Add 1 % Water charges on
9192 "W-A"
Add 1 % Water charges on 43757.75
9227 "W-A"
Add 1 % Water charges on 56386.63
9252 "W-A"
Add 1 % Water charges on 73386.63
9288 "W-A"
Add 1 % Water charges on 91386.63
9322 "W-A"
Add 1 % Water charges on 118579.95 1185.8
9347 "W-A"
Add 1 % Water charges on 123773.26
9380 "W-A"
Add 1 % Water charges on 7673.2
9406 "W-A"
Add 1 % Water charges on 11538.66
9441 "W-A"
Add 1 % Water charges on 15812.89
9476 "W-A"
Add 1 % Water charges on 22089.37 220.89
9502 "W-A"
Add 1 % Water charges on 27610.47
9538 "W-A"
Add 1 % Water charges on 33654.65
9564 "W-A"
Add 1 % Water charges on 43210.89
9600 "W-A"
Add 1 % Water charges on 50257.75
9637 "W-A"
Add 1 % Water charges on 62957.75 629.58
9664 "W-A"
Add 1 % Water charges on 75986.63
9699 "W-A"
Add 1 % Water charges on 105257.75 1052.58
9724 "W-A"
Add 1 % Water charges on 114079.95
9759 "W-A"
Add 1 % Water charges on 115273.26
9794 "W-A"
Add 1 % Water charges on 139773.26 1397.73
9819 "W-A"
Add 1 % Water charges on 156273.26
9857 "W-A"
Add 1 % Water charges on 5511.6
9883 "W-A"
Add 1 % Water charges on 8269.33
9919 "W-A"
Add 1 % Water charges on 10406.45
9954 "W-A"
Add 1 % Water charges on 14794.69
9980 "W-A"
Add 1 % Water charges on 19005.23
10016 "W-A"
Add 1 % Water charges on 23977.33
10042 "W-A"
Add 1 % Water charges on 30855.44
10076 "W-A"
Add 1 % Water charges on 32393.88
10112 "W-A"
Add 1 % Water charges on 46028.88
10138 "W-A"
Add 1 % Water charges on 60943.32
10172 "W-A"
Add 1 % Water charges on 71978.88
10331 "W-A"
Add 1 % Water charges on 585.48
10377 "W-A"
Add 1 % Water charges on 1607.78
10413 "W-A"
Add 1 % Water charges on 533.46
10435 "W-A"
Add 1 % Water charges on 27.04
11149 "W-A"
Add 1 % Water charges on 1783.66
11190 "W-A"
Add 1 % Water charges on 2039.26
11230 "W-A"
Add 1 % Water charges on 2300.57
11261 "W-A"
Add 1 % Water charges on 2583.45
11303 "W-A"
Add 1 % Water charges on 3089.65
11343 "W-A"
Add 1 % Water charges on 3624.36
11372 "W-A"
Add 1 % Water charges on 4112.8
11414 "W-A"
Add 1 % Water charges on 4600.79
11455 "W-A" 5107.48
Add 1 % Water charges on
11496 "W-A"
Add 1 % Water charges on 5614.92
11527 "W-A"
Add 1 % Water charges on 6121.11
11568 "W-A"
Add 1 % Water charges on 7135.74
12117 "W-A"
Add 1 % Water charges on 1981.28
12147 "W-A"
Add 1 % Water charges on 3168
16365 "W-A"
Add 1 % Water charges on 626.22
16408 "W-A"
Add 1 % Water charges on 626.22
16467 "W-A"
Add 1 % Water charges on 670.42
16521 "W-A"
Add 1 % Water charges on 670.42
16578 "W-A"
Add 1 % Water charges on 776
16632 "W-A"
Add 1 % Water charges on 776
17526 "W-A"
Add 1 % Water charges on 1373.57
17674 "W-A"
Add 1 % Water charges on 1373.57 13.74
17756 "W-A"
Add 1 % Water charges on 4342.28
17915 "W-A"
Add 1 % Water charges on 4342.28
18006 "W-A"
Add 1 % Water charges on 8950.25
18115 "W-A"
Add 1 % Water charges on 8950.25 89.5
18302 "W-A"
Add 1 % Water charges on 978.61
18400 "W-A"
Add 1 % Water charges on 978.61
18542 "W-A"
Add 1 % Water charges on 1012.63
18644 "W-A"
Add 1 % Water charges on 1012.63
18781 "W-A"
Add 1 % Water charges on 1012.63
18866 "W-A"
Add 1 % Water charges on
18949 "W-A"
Add 1 % Water charges on 214.22 2.14
18981 "W-A"
Add 1 % Water charges on 185.42
19019 "W-A"
Add 1 % Water charges on 214.1
19064 "W-A"
Add 1 % Water charges on 255.78
19107 "W-A"
Add 1 % Water charges on 226.98
19226 "W-A"
Add 1 % Water charges on 715.56
19262 "W-A"
Add 1 % Water charges on 615.56
19288 "W-A"
Add 1 % Water charges on 615.56
19329 "W-A"
Add 1 % Water charges on 716.8
19354 "W-A"
Add 1 % Water charges on 621.8
19393 "W-A"
Add 1 % Water charges on 947.6
19432 "W-A"
Add 1 % Water charges on 1237.6
19503 "W-A"
Add 1 % Water charges on 222.57
19550 "W-A"
Add 1 % Water charges on 223.61
19594 "W-A"
Add 1 % Water charges on 295.77
19672 "W-A"
Add 1 % Water charges on 2878.78
19757 "W-A"
Add 1 % Water charges on 4049.64
19808 "W-A"
Add 1 % Water charges on 718.49
19857 "W-A"
Add 1 % Water charges on 1073.76
19919 "W-A"
Add 1 % Water charges on 14.3
19974 "W-A"
Add 1 % Water charges on 14.3
20041 "W-A" 30.42
Add 1 % Water charges on
20108 "W-A"
Add 1 % Water charges on 30.42
20143 "W-A"
Add 1 % Water charges on 3.64
20164 "W-A"
Add 1 % Water charges on 3.64
20308 "W-A"
Add 1 % Water charges on 30.48
20363 "W-A"
Add 1 % Water charges on 41.34 0.41
20403 "W-A"
Add 1 % Water charges on 47.58
20452 "W-A"
Add 1 % Water charges on 54.86
20499 "W-A"
Add 1 % Water charges on 56.68
20552 "W-A"
Add 1 % Water charges on 644.96
20626 "W-A"
Add 1 % Water charges on 240.09
20721 "W-A"
Add 1 % Water charges on 901.17
20803 "W-A"
Add 1 % Water charges on 1455.64
20874 "W-A"
Add 1 % Water charges on 1378.64
20947 "W-A"
Add 1 % Water charges on 1352.97
21097 "W-A"
Add 1 % Water charges on 13431.69 134.32
21142 "W-A"
Add 1 % Water charges on 1327.21
21789 "W-A"
Add 1 % Water charges on 18046.9
21827 "W-A"
Add 1 % Water charges on 21390.14
21867 "W-A"
Add 1 % Water charges on 25264.74
21906 "W-A"
Add 1 % Water charges on 24948.5
21937 "W-A"
Add 1 % Water charges on 28861.69
21975 "W-A"
Add 1 % Water charges on 29080.26
22013 "W-A"
Add 1 % Water charges on 28621.16
22051 "W-A"
Add 1 % Water charges on 32671.31
22097 "W-A"
Add 1 % Water charges on 7366.58
22138 "W-A"
Add 1 % Water charges on 7663.9
22210 "W-A"
Add 1 % Water charges on 9815.71
22322 "W-A"
Add 1 % Water charges on 28651.27
22361 "W-A"
Add 1 % Water charges on 28155.71
22398 "W-A"
Add 1 % Water charges on 28932.26
22439 "W-A"
Add 1 % Water charges on 29505.6
22469 "W-A"
Add 1 % Water charges on 36027.11
22556 "W-A"
Add 1 % Water charges on 12727.38
22597 "W-A"
Add 1 % Water charges on 12681.76
22637 "W-A"
Add 1 % Water charges on 12738.04
22679 "W-A"
Add 1 % Water charges on 1004.23
22714 "W-A"
Add 1 % Water charges on 1013.11
22740 "W-A"
Add 1 % Water charges on 1019.03
22775 "W-A"
Add 1 % Water charges on 1059.95
22823 "W-A"
Add 1 % Water charges on 19197.38
22866 "W-A"
Add 1 % Water charges on 22150.39
22907 "W-A"
Add 1 % Water charges on 19197.38
22946 "W-A"
Add 1 % Water charges on 19197.38
22980 "W-A"
Add 1 % Water charges on 19197.38
23022 "W-A" 19197.38
Add 1 % Water charges on
25 "W"
Add 1 % Water charges on
59 "W"
Add 1 % Water charges on
83 "W"
Add 1 % Water charges on
118 "W"
Add 1 % Water charges on
155 "W"
Add 1 % Water charges on
179 "W"
Add 1 % Water charges on
361 "W"
Add 1 % Water charges on
395 "W"
Add 1 % Water charges on
420 "W"
Add 1 % Water charges on
455 "W"
Add 1 % Water charges on
490 "W"
Add 1 % Water charges on
515 "W"
Add 1 % Water charges on
550 "W"
Add 1 % Water charges on
573 "W"
Add 1 % Water charges on
606 "W"
Add 1 % Water charges on
641 "W"
Add 1 % Water charges on
665 "W"
Add 1 % Water charges on
807 "W"
Add 1 % Water charges on
845 "W"
Add 1 % Water charges on
873 "W"
Add 1 % Water charges on
912 "W"
Add 1 % Water charges on
950 "W"
Add 1 % Water charges on
978 "W"
Add 1 % Water charges on
1011 "W"
Add 1 % Water charges on
1050 "W"
Add 1 % Water charges on 81.72
1079 "W"
Add 1 % Water charges on
1334 "W"
Add 1 % Water charges on
1401 "W"
Add 1 % Water charges on
1419 "W"
Add 1 % Water charges on
1456 "W"
Add 1 % Water charges on
1483 "W"
Add 1 % Water charges on
1517 "W"
Add 1 % Water charges on
1552 "W"
Add 1 % Water charges on
1577 "W"
Add 1 % Water charges on
1612 "W"
Add 1 % Water charges on
1785 "W"
Add 1 % Water charges on
1822 "W"
Add 1 % Water charges on
1856 "W"
Add 1 % Water charges on
1882 "W"
Add 1 % Water charges on
1919 "W"
Add 1 % Water charges on
1954 "W"
Add 1 % Water charges on 54.84
1980 "W"
Add 1 % Water charges on
2017 "W"
Add 1 % Water charges on
2043 "W"
Add 1 % Water charges on
2079 "W"
Add 1 % Water charges on
2121 "W"
Add 1 % Water charges on
2147 "W"
Add 1 % Water charges on
2184 "W"
Add 1 % Water charges on
2219 "W"
Add 1 % Water charges on
2246 "W"
Add 1 % Water charges on
2283 "W"
Add 1 % Water charges on
2399 "W"
Add 1 % Water charges on
2436 "W"
Add 1 % Water charges on
2473 "W"
Add 1 % Water charges on
2501 "W"
Add 1 % Water charges on
2536 "W"
Add 1 % Water charges on
2572 "W"
Add 1 % Water charges on
2600 "W"
Add 1 % Water charges on
2637 "W"
Add 1 % Water charges on
2662 "W"
Add 1 % Water charges on
2693 "W"
Add 1 % Water charges on
2722 "W"
Add 1 % Water charges on
2741 "W"
Add 1 % Water charges on
2758 "W"
Add 1 % Water charges on
2787 "W"
Add 1 % Water charges on
2804 "W"
Add 1 % Water charges on
2834 "W"
Add 1 % Water charges on
2849 "W"
Add 1 % Water charges on
2867 "W"
Add 1 % Water charges on
2896 "W"
Add 1 % Water charges on
2914 "W"
Add 1 % Water charges on
2942 "W"
Add 1 % Water charges on
2960 "W"
Add 1 % Water charges on
2990 "W"
Add 1 % Water charges on 2.53
3008 "W"
Add 1 % Water charges on
3026 "W"
Add 1 % Water charges on
3056 "W"
Add 1 % Water charges on
3072 "W"
Add 1 % Water charges on
3100 "W"
Add 1 % Water charges on
3116 "W"
Add 1 % Water charges on
3144 "W"
Add 1 % Water charges on
3160 "W"
Add 1 % Water charges on
3186 "W"
Add 1 % Water charges on
3202 "W"
Add 1 % Water charges on
3219 "W"
Add 1 % Water charges on
3244 "W"
Add 1 % Water charges on
3264 "W"
Add 1 % Water charges on
3289 "W"
Add 1 % Water charges on
3308 "W"
Add 1 % Water charges on
3334 "W"
Add 1 % Water charges on
3351 "W"
Add 1 % Water charges on
3381 "W"
Add 1 % Water charges on
3397 "W"
Add 1 % Water charges on
3427 "W"
Add 1 % Water charges on
3443 "W"
Add 1 % Water charges on
3473 "W"
Add 1 % Water charges on 1.14
3491 "W"
Add 1 % Water charges on
3522 "W"
Add 1 % Water charges on
3543 "W"
Add 1 % Water charges on
4046 "W"
Add 1 % Water charges on
4072 "W"
Add 1 % Water charges on
4107 "W"
Add 1 % Water charges on
4142 "W"
Add 1 % Water charges on
4168 "W"
Add 1 % Water charges on
4204 "W"
Add 1 % Water charges on
4241 "W"
Add 1 % Water charges on
4267 "W"
Add 1 % Water charges on
4302 "W"
Add 1 % Water charges on
4337 "W"
Add 1 % Water charges on
4363 "W"
Add 1 % Water charges on
4390 "W"
Add 1 % Water charges on
4414 "W"
Add 1 % Water charges on
4446 "W"
Add 1 % Water charges on
4469 "W"
Add 1 % Water charges on
4502 "W"
Add 1 % Water charges on
4525 "W"
Add 1 % Water charges on
4558 "W"
Add 1 % Water charges on
4592 "W"
Add 1 % Water charges on 31.38
4615 "W"
Add 1 % Water charges on
4648 "W"
Add 1 % Water charges on
4671 "W"
Add 1 % Water charges on
4704 "W"
Add 1 % Water charges on
4727 "W"
Add 1 % Water charges on
6104 "W"
Add 1 % Water charges on
6346 "W"
Add 1 % Water charges on
6378 "W"
Add 1 % Water charges on
6403 "W"
Add 1 % Water charges on
6434 "W"
Add 1 % Water charges on
6470 "W"
Add 1 % Water charges on
6492 "W"
Add 1 % Water charges on
6524 "W"
Add 1 % Water charges on
6544 "W"
Add 1 % Water charges on
6573 "W"
Add 1 % Water charges on
6593 "W"
Add 1 % Water charges on
6622 "W"
Add 1 % Water charges on
6642 "W"
Add 1 % Water charges on
6671 "W"
Add 1 % Water charges on 6.27
6691 "W"
Add 1 % Water charges on
6723 "W"
Add 1 % Water charges on
6743 "W"
Add 1 % Water charges on
6772 "W"
Add 1 % Water charges on
6792 "W"
Add 1 % Water charges on
6821 "W"
Add 1 % Water charges on
6841 "W"
Add 1 % Water charges on
6871 "W"
Add 1 % Water charges on
6891 "W"
Add 1 % Water charges on
6924 "W"
Add 1 % Water charges on
6946 "W"
Add 1 % Water charges on
6978 "W"
Add 1 % Water charges on
6997 "W"
Add 1 % Water charges on
7026 "W"
Add 1 % Water charges on
7045 "W"
Add 1 % Water charges on
7072 "W"
Add 1 % Water charges on
7088 "W"
Add 1 % Water charges on
7276 "W"
Add 1 % Water charges on
7295 "W"
Add 1 % Water charges on
7322 "W"
Add 1 % Water charges on
7342 "W"
Add 1 % Water charges on
7371 "W"
Add 1 % Water charges on
7388 "W"
Add 1 % Water charges on
7408 "W"
Add 1 % Water charges on
7434 "W"
Add 1 % Water charges on
7453 "W"
Add 1 % Water charges on
7478 "W"
Add 1 % Water charges on
7500 "W"
Add 1 % Water charges on
7837 "W"
Add 1 % Water charges on
7855 "W"
Add 1 % Water charges on
7884 "W"
Add 1 % Water charges on
7902 "W"
Add 1 % Water charges on
7931 "W"
Add 1 % Water charges on
7951 "W"
Add 1 % Water charges on
7978 "W"
Add 1 % Water charges on
7995 "W"
Add 1 % Water charges on
8224 "W"
Add 1 % Water charges on
8246 "W"
Add 1 % Water charges on
8278 "W"
Add 1 % Water charges on
8300 "W"
Add 1 % Water charges on
8332 "W"
Add 1 % Water charges on
8354 "W"
Add 1 % Water charges on
8386 "W"
Add 1 % Water charges on
8408 "W"
Add 1 % Water charges on
8440 "W"
Add 1 % Water charges on
8462 "W"
Add 1 % Water charges on
8494 "W"
Add 1 % Water charges on
8516 "W"
Add 1 % Water charges on
8547 "W"
Add 1 % Water charges on
8569 "W"
Add 1 % Water charges on
8601 "W"
Add 1 % Water charges on
10205 "W"
Add 1 % Water charges on
10223 "W"
Add 1 % Water charges on
10242 "W"
Add 1 % Water charges on
10268 "W"
Add 1 % Water charges on
10285 "W"
Add 1 % Water charges on
10474 "W"
Add 1 % Water charges on
10508 "W"
Add 1 % Water charges on 8.08
10531 "W"
Add 1 % Water charges on
10561 "W"
Add 1 % Water charges on
10584 "W"
Add 1 % Water charges on
10616 "W"
Add 1 % Water charges on
10649 "W"
Add 1 % Water charges on
10672 "W"
Add 1 % Water charges on
10709 "W"
Add 1 % Water charges on
10732 "W"
Add 1 % Water charges on
10764 "W"
Add 1 % Water charges on
10796 "W"
Add 1 % Water charges on 40.49
10818 "W"
Add 1 % Water charges on
10852 "W"
Add 1 % Water charges on
10872 "W"
Add 1 % Water charges on
10905 "W"
Add 1 % Water charges on
10925 "W"
Add 1 % Water charges on
10958 "W"
Add 1 % Water charges on
10978 "W"
Add 1 % Water charges on
11011 "W"
Add 1 % Water charges on
11031 "W"
Add 1 % Water charges on
11064 "W"
Add 1 % Water charges on
11084 "W"
Add 1 % Water charges on
11117 "W"
Add 1 % Water charges on
11590 "W"
Add 1 % Water charges on
11618 "W"
Add 1 % Water charges on
11636 "W"
Add 1 % Water charges on
11661 "W"
Add 1 % Water charges on
11679 "W"
Add 1 % Water charges on
11697 "W"
Add 1 % Water charges on
11725 "W"
Add 1 % Water charges on
11743 "W"
Add 1 % Water charges on
11771 "W"
Add 1 % Water charges on
11789 "W"
Add 1 % Water charges on
11814 "W"
Add 1 % Water charges on 4.29
11832 "W"
Add 1 % Water charges on
11851 "W"
Add 1 % Water charges on
11891 "W"
Add 1 % Water charges on
11930 "W"
Add 1 % Water charges on
11966 "W"
Add 1 % Water charges on
11995 "W"
Add 1 % Water charges on
12034 "W"
Add 1 % Water charges on
12073 "W"
Add 1 % Water charges on
12177 "W"
Add 1 % Water charges on
12194 "W"
Add 1 % Water charges on
12220 "W"
Add 1 % Water charges on
12237 "W"
Add 1 % Water charges on
12266 "W"
Add 1 % Water charges on
12282 "W"
Add 1 % Water charges on 1.8
12312 "W"
Add 1 % Water charges on
12329 "W"
Add 1 % Water charges on
12346 "W"
Add 1 % Water charges on
12372 "W"
Add 1 % Water charges on
12389 "W"
Add 1 % Water charges on
12416 "W"
Add 1 % Water charges on
12433 "W"
Add 1 % Water charges on
12450 "W"
Add 1 % Water charges on
12477 "W"
Add 1 % Water charges on
12494 "W"
Add 1 % Water charges on
12521 "W"
Add 1 % Water charges on
12538 "W"
Add 1 % Water charges on
12566 "W"
Add 1 % Water charges on
12581 "W"
Add 1 % Water charges on
12607 "W"
Add 1 % Water charges on 4.1
12627 "W"
Add 1 % Water charges on
12651 "W"
Add 1 % Water charges on
12667 "W"
Add 1 % Water charges on
12683 "W"
Add 1 % Water charges on
12709 "W"
Add 1 % Water charges on
12725 "W"
Add 1 % Water charges on
12758 "W"
Add 1 % Water charges on
12774 "W"
Add 1 % Water charges on
12798 "W"
Add 1 % Water charges on
12814 "W"
Add 1 % Water charges on
12830 "W"
Add 1 % Water charges on
12856 "W"
Add 1 % Water charges on
12879 "W" 1.48
Add 1 % Water charges on
12905 "W"
Add 1 % Water charges on
12920 "W"
Add 1 % Water charges on
12947 "W"
Add 1 % Water charges on 2.87
12964 "W"
Add 1 % Water charges on 3.45
12981 "W"
Add 1 % Water charges on 1.79
13011 "W"
Add 1 % Water charges on
13027 "W"
Add 1 % Water charges on
13053 "W"
Add 1 % Water charges on
13069 "W"
Add 1 % Water charges on
13095 "W"
Add 1 % Water charges on
13111 "W"
Add 1 % Water charges on
13141 "W"
Add 1 % Water charges on 1.79
13158 "W"
Add 1 % Water charges on
13175 "W"
Add 1 % Water charges on
13201 "W"
Add 1 % Water charges on
13218 "W"
Add 1 % Water charges on
13246 "W"
Add 1 % Water charges on
13263 "W"
Add 1 % Water charges on
13280 "W"
Add 1 % Water charges on
13308 "W"
Add 1 % Water charges on
13325 "W"
Add 1 % Water charges on
13352 "W"
Add 1 % Water charges on
13369 "W"
Add 1 % Water charges on
13396 "W"
Add 1 % Water charges on
13413 "W"
Add 1 % Water charges on 8.87
13430 "W"
Add 1 % Water charges on 8.87
13462 "W"
Add 1 % Water charges on
13479 "W"
Add 1 % Water charges on
13506 "W"
Add 1 % Water charges on
13523 "W"
Add 1 % Water charges on
13540 "W"
Add 1 % Water charges on
13566 "W"
Add 1 % Water charges on
13583 "W"
Add 1 % Water charges on
13610 "W"
Add 1 % Water charges on
13627 "W"
Add 1 % Water charges on
13656 "W"
Add 1 % Water charges on
13673 "W"
Add 1 % Water charges on
13690 "W"
Add 1 % Water charges on
13718 "W"
Add 1 % Water charges on
13735 "W"
Add 1 % Water charges on
13762 "W"
Add 1 % Water charges on
13779 "W"
Add 1 % Water charges on
13796 "W"
Add 1 % Water charges on
13823 "W"
Add 1 % Water charges on
13840 "W"
Add 1 % Water charges on
13868 "W"
Add 1 % Water charges on
13885 "W"
Add 1 % Water charges on
13917 "W"
Add 1 % Water charges on
13934 "W"
Add 1 % Water charges on
13960 "W"
Add 1 % Water charges on 2
13977 "W"
Add 1 % Water charges on
13994 "W"
Add 1 % Water charges on
14019 "W"
Add 1 % Water charges on
14036 "W"
Add 1 % Water charges on
14053 "W"
Add 1 % Water charges on
14080 "W"
Add 1 % Water charges on
14097 "W"
Add 1 % Water charges on
14124 "W"
Add 1 % Water charges on
14141 "W"
Add 1 % Water charges on
14158 "W"
Add 1 % Water charges on
14185 "W"
Add 1 % Water charges on
14202 "W"
Add 1 % Water charges on
14230 "W"
Add 1 % Water charges on
14249 "W"
Add 1 % Water charges on
14276 "W"
Add 1 % Water charges on
14293 "W"
Add 1 % Water charges on
14310 "W"
Add 1 % Water charges on
14337 "W"
Add 1 % Water charges on
14359 "W"
Add 1 % Water charges on
14386 "W"
Add 1 % Water charges on
14405 "W"
Add 1 % Water charges on
14432 "W"
Add 1 % Water charges on
14451 "W"
Add 1 % Water charges on
14479 "W"
Add 1 % Water charges on 3.37
14497 "W"
Add 1 % Water charges on 4.09
14515 "W"
Add 1 % Water charges on
14544 "W"
Add 1 % Water charges on 5.76
14562 "W"
Add 1 % Water charges on 6.81
14591 "W"
Add 1 % Water charges on 8.38
14609 "W"
Add 1 % Water charges on
14639 "W"
Add 1 % Water charges on 1.93
14657 "W"
Add 1 % Water charges on
14683 "W"
Add 1 % Water charges on 2.48
14701 "W"
Add 1 % Water charges on
14719 "W"
Add 1 % Water charges on
14747 "W"
Add 1 % Water charges on 4.61
14764 "W"
Add 1 % Water charges on 5.65
14790 "W"
Add 1 % Water charges on
14807 "W"
Add 1 % Water charges on 7.26
14834 "W" 8.4
Add 1 % Water charges on
14851 "W"
Add 1 % Water charges on 11.38
14882 "W"
Add 1 % Water charges on 2.34
14899 "W"
Add 1 % Water charges on
14916 "W"
Add 1 % Water charges on
14944 "W"
Add 1 % Water charges on
14961 "W"
Add 1 % Water charges on
14988 "W"
Add 1 % Water charges on 8.75
15005 "W"
Add 1 % Water charges on
15035 "W"
Add 1 % Water charges on 1.5
15052 "W"
Add 1 % Water charges on
15067 "W"
Add 1 % Water charges on
15093 "W"
Add 1 % Water charges on 2.05
15110 "W"
Add 1 % Water charges on 2.87
15138 "W"
Add 1 % Water charges on
15155 "W"
Add 1 % Water charges on 4.78
15172 "W"
Add 1 % Water charges on 6.83
15200 "W"
Add 1 % Water charges on 6.83
15443 "W"
Add 1 % Water charges on 2.87
15591 "W"
Add 1 % Water charges on
15605 "W"
Add 1 % Water charges on
15630 "W"
Add 1 % Water charges on
15644 "W"
Add 1 % Water charges on
15658 "W"
Add 1 % Water charges on
15682 "W"
Add 1 % Water charges on
15702 "W"
Add 1 % Water charges on
15730 "W"
Add 1 % Water charges on
15745 "W"
Add 1 % Water charges on
15807 "W"
Add 1 % Water charges on
15851 "W"
Add 1 % Water charges on
15893 "W"
Add 1 % Water charges on
15938 "W"
Add 1 % Water charges on
15973 "W"
Add 1 % Water charges on
16662 "W"
Add 1 % Water charges on
16680 "W"
Add 1 % Water charges on
16708 "W"
Add 1 % Water charges on
16726 "W"
Add 1 % Water charges on
16753 "W"
Add 1 % Water charges on
16771 "W"
Add 1 % Water charges on
16797 "W"
Add 1 % Water charges on
16815 "W"
Add 1 % Water charges on
16861 "W"
Add 1 % Water charges on
16905 "W"
Add 1 % Water charges on
16992 "W"
Add 1 % Water charges on
17079 "W"
Add 1 % Water charges on
17122 "W"
Add 1 % Water charges on
17166 "W"
Add 1 % Water charges on
17211 "W"
Add 1 % Water charges on
17254 "W"
Add 1 % Water charges on
17289 "W"
Add 1 % Water charges on
17330 "W"
Add 1 % Water charges on
17376 "W"
Add 1 % Water charges on
17420 "W"
Add 1 % Water charges on
19133 "W"
Add 1 % Water charges on
19165 "W"
Add 1 % Water charges on
19187 "W"
Add 1 % Water charges on
19454 "W"
Add 1 % Water charges on
21173 "W"
Add 1 % Water charges on
21211 "W"
Add 1 % Water charges on
21249 "W"
Add 1 % Water charges on
21288 "W"
Add 1 % Water charges on
21316 "W"
Add 1 % Water charges on
21352 "W"
Add 1 % Water charges on
21388 "W"
Add 1 % Water charges on
21417 "W"
Add 1 % Water charges on
21457 "W"
Add 1 % Water charges on
21603 "W"
Add 1 % Water charges on
21631 "W"
Add 1 % Water charges on
21669 "W"
Add 1 % Water charges on
21706 "W"
Add 1 % Water charges on
23055 "W"
Add 1 % Water charges on
23072 "W"
Add 1 % Water charges on 150
23100 "W"
Add 1 % Water charges on
23116 "W"
Add 1 % Water charges on
23146 "W"
Add 1 % Water charges on
23163 "W"
Add 1 % Water charges on 295
23193 "W"
Add 1 % Water charges on
23209 "W"
Add 1 % Water charges on
23228 "W"
Add 1 % Water charges on 295
23257 "W"
Add 1 % Water charges on 150
23274 "W"
Add 1 % Water charges on 236
23310 "W"
profit and overheads on
16369 "Y-
profit and overheads on 721.35
16421 "Y-
profit and overheads on 721.35 108.2
16480 "Y-
profit and overheads on 772.26 115.84
16535 "Y-
profit and overheads on 772.26 115.84
16591 "Y-
profit and overheads on 893.88 134.08
16644 "Y-
profit and overheads on 893.88 134.08
17530 "Y-
profit and overheads on 1582.22
17678 "Y-
profit and overheads on 1582.22 237.33
17760 "Y- 5001.89
profit and overheads on
17919 "Y-
profit and overheads on 5001.89
18019 "Y-
profit and overheads on 10309.83 1546.47
18119 "Y-
profit and overheads on 10309.83 1546.47
18306 "Y-
profit and overheads on 1127.27
18404 "Y-
profit and overheads on 1127.27
18555 "Y-
profit and overheads on 1166.45 174.97
18648 "Y-
profit and overheads on 1166.45
18785 "Y-
profit and overheads on 1166.45
18870 "Y-
profit and overheads on 1166.45
18953 "Y-
profit and overheads on 246.77 37.01
18985 "Y-
profit and overheads on 213.59
19023 "Y-
profit and overheads on 246.62
19068 "Y-
profit and overheads on 294.64
19111 "Y-
profit and overheads on 261.46
19230 "Y-
profit and overheads on 824.26
19266 "Y-
profit and overheads on 709.07
19292 "Y-
profit and overheads on 709.07
19333 "Y-
profit and overheads on 825.69
19358 "Y-
profit and overheads on 716.25
19397 "Y-
profit and overheads on 1091.55
19436 "Y-
profit and overheads on 1425.6
19507 "Y-
profit and overheads on 256.38
19554 "Y-
profit and overheads on 257.57
19598 "Y-
profit and overheads on 340.7
19676 "Y-
profit and overheads on 3316.08
19761 "Y-
profit and overheads on 4664.8
19812 "Y-
profit and overheads on 827.64
19861 "Y-
profit and overheads on 1236.87
19923 "Y-
profit and overheads on 16.47
19978 "Y-
profit and overheads on 16.47
20045 "Y-
profit and overheads on 35.04
20112 "Y-
profit and overheads on 35.04
20147 "Y-
profit and overheads on 4.19
20168 "Y-
profit and overheads on 4.19
20312 "Y-
profit and overheads on 35.11
20367 "Y-
profit and overheads on 47.62 7.14
20407 "Y-
profit and overheads on 54.81
20456 "Y-
profit and overheads on 63.19
20503 "Y-
profit and overheads on 65.29
20556 "Y-
profit and overheads on 742.93
20630 "Y-
profit and overheads on 276.56
20725 "Y-
profit and overheads on 1038.06
20807 "Y-
profit and overheads on 1676.76
20878 "Y-
profit and overheads on 1588.06
20951 "Y- 1558.5
profit and overheads on
21101 "Y-
profit and overheads on 15472.03 2320.8
21146 "Y-
profit and overheads on 1528.81
223 "Y-A"
profit and overheads on 1959.39
258 "Y-A"
profit and overheads on 2281.92
292 "Y-A"
profit and overheads on 2926.99 439.05
318 "Y-A"
profit and overheads on 3874.43
710 "Y-A"
profit and overheads on 1581.82
744 "Y-A"
profit and overheads on 2056.15
769 "Y-A"
profit and overheads on 2566.5
1657 "Y-A"
profit and overheads on 1688.26
1694 "Y-A"
profit and overheads on 2277.89
1721 "Y-A"
profit and overheads on 2999.56
1758 "Y-A"
profit and overheads on 4008.48
2328 "Y-A"
profit and overheads on 1935.15
2372 "Y-A"
profit and overheads on 2319.76
3581 "Y-A"
profit and overheads on 4157.72
3602 "Y-A"
profit and overheads on 4272.92
3637 "Y-A"
profit and overheads on 6346.34
3658 "Y-A"
profit and overheads on 6346.34
3694 "Y-A"
profit and overheads on 9898.55
3729 "Y-A"
profit and overheads on 12326.52 1848.98
3754 "Y-A"
profit and overheads on 14858.03
3790 "Y-A"
profit and overheads on 25299.16
3825 "Y-A"
profit and overheads on 33012.87
3851 "Y-A"
profit and overheads on 44556.22
3887 "Y-A"
profit and overheads on 53384.64
3913 "Y-A"
profit and overheads on 70451.53
3951 "Y-A"
profit and overheads on 85319.02
3987 "Y-A"
profit and overheads on 99026.69 14854
4014 "Y-A"
profit and overheads on 138616.37
4772 "Y-A"
profit and overheads on 27808.72
4808 "Y-A"
profit and overheads on 31162.29
4834 "Y-A"
profit and overheads on 30010.38
4869 "Y-A"
profit and overheads on 36934.85
4907 "Y-A"
profit and overheads on 41546.82
4932 "Y-A"
profit and overheads on 46170.2
4970 "Y-A"
profit and overheads on 86525.45
5005 "Y-A"
profit and overheads on 102682.55 15402.38
5032 "Y-A"
profit and overheads on 126674.77 19001.22
5067 "Y-A"
profit and overheads on 167276.16 25091.42
5104 "Y-A"
profit and overheads on 178808.25 26821.24
5129 "Y-A"
profit and overheads on 209975.97 31496.4
5203 "Y-A"
profit and overheads on 142.82
5275 "Y-A"
profit and overheads on 160.78
5345 "Y-A" 90.56
profit and overheads on
5428 "Y-A"
profit and overheads on -5.53
5498 "Y-A"
profit and overheads on 295.76
5580 "Y-A"
profit and overheads on 186.17
5602 "Y-A"
profit and overheads on 31.15
5634 "Y-A"
profit and overheads on 31.15
5656 "Y-A"
profit and overheads on 46.72
5688 "Y-A"
profit and overheads on 46.72
5708 "Y-A"
profit and overheads on 62
5738 "Y-A"
profit and overheads on 62
5759 "Y-A"
profit and overheads on 18.57
5787 "Y-A"
profit and overheads on 18.57
5806 "Y-A"
profit and overheads on 24.86
5835 "Y-A"
profit and overheads on 25.16 3.77
5854 "Y-A"
profit and overheads on 31.15
5883 "Y-A"
profit and overheads on 31.15
5903 "Y-A"
profit and overheads on 18.57
5921 "Y-A"
profit and overheads on 18.57
5949 "Y-A"
profit and overheads on 24.86
5967 "Y-A"
profit and overheads on 24.86
5994 "Y-A"
profit and overheads on 28.15 4.22
6012 "Y-A"
profit and overheads on 28.15
6041 "Y-A"
profit and overheads on 31.15
6059 "Y-A"
profit and overheads on 34.14
7537 "Y-A"
profit and overheads on 42943.02
7570 "Y-A"
profit and overheads on 52273.45
7593 "Y-A"
profit and overheads on 68257.28
7629 "Y-A"
profit and overheads on 2787.61
7652 "Y-A"
profit and overheads on 4099.63
7685 "Y-A"
profit and overheads on 6087.82
7708 "Y-A"
profit and overheads on 6645.34
7740 "Y-A"
profit and overheads on 3236.85
7770 "Y-A"
profit and overheads on 5213.52 782.03
7791 "Y-A"
profit and overheads on 6621.15
7821 "Y-A"
profit and overheads on 9413.37 1412.01
8049 "Y-A"
profit and overheads on 7152.68
8081 "Y-A"
profit and overheads on 9883.84
8101 "Y-A"
profit and overheads on 10433.3
8131 "Y-A"
profit and overheads on 14294.49
8148 "Y-A"
profit and overheads on 19823.63
8179 "Y-A"
profit and overheads on 15043.23
8196 "Y-A"
profit and overheads on 21609.09
8643 "Y-A"
profit and overheads on 7558.34
8668 "Y-A"
profit and overheads on 11817.78
8703 "Y-A"
profit and overheads on 18685.56
8730 "Y-A" 22542.42
profit and overheads on
8766 "Y-A"
profit and overheads on 28803.65
8801 "Y-A"
profit and overheads on 36293.45
8826 "Y-A"
profit and overheads on 47021.27
8863 "Y-A"
profit and overheads on 59938.08
8897 "Y-A"
profit and overheads on 74526.96
8922 "Y-A"
profit and overheads on 103346.98 15502.05
8959 "Y-A"
profit and overheads on 9241.96
8983 "Y-A"
profit and overheads on 13176.25
9017 "Y-A"
profit and overheads on 16199.12
9052 "Y-A"
profit and overheads on 20837.24
9076 "Y-A"
profit and overheads on 26045.11
9111 "Y-A"
profit and overheads on 30703.63 4605.54
9135 "Y-A"
profit and overheads on 36815.91
9171 "Y-A"
profit and overheads on 44668.29
9196 "Y-A"
profit and overheads on 50404.78
9231 "Y-A"
profit and overheads on 64952.04
9267 "Y-A"
profit and overheads on 84534.43
9292 "Y-A"
profit and overheads on 105268.72
9326 "Y-A"
profit and overheads on 136592.83 20488.92
9351 "Y-A"
profit and overheads on 142575.04
9384 "Y-A"
profit and overheads on 8838.79
9410 "Y-A"
profit and overheads on 13291.44
9445 "Y-A"
profit and overheads on 18214.95
9480 "Y-A"
profit and overheads on 25444.86 3816.73
9506 "Y-A"
profit and overheads on 31804.63
9542 "Y-A"
profit and overheads on 38766.96
9568 "Y-A"
profit and overheads on 49774.84
9604 "Y-A"
profit and overheads on 57892.16
9641 "Y-A"
profit and overheads on 72521.35 10878.2
9668 "Y-A"
profit and overheads on 87529.38
9703 "Y-A"
profit and overheads on 121246.93 18187.04
9728 "Y-A"
profit and overheads on 131409.26
9763 "Y-A"
profit and overheads on 132783.85
9798 "Y-A"
profit and overheads on 161005.52 24150.83
9823 "Y-A"
profit and overheads on 180011.95
9861 "Y-A"
profit and overheads on 6348.84
9897 "Y-A"
profit and overheads on 9525.48 1428.82
9923 "Y-A"
profit and overheads on 11987.24
9958 "Y-A"
profit and overheads on 17042.07
9984 "Y-A"
profit and overheads on 21892.22
10020 "Y-A"
profit and overheads on 27619.6
10056 "Y-A"
profit and overheads on 35542.54
10080 "Y-A"
profit and overheads on 37314.67
10116 "Y-A"
profit and overheads on 53020.89
10152 "Y-A" 70200.91 10530.14
profit and overheads on
10176 "Y-A"
profit and overheads on 82912.83
10335 "Y-A"
profit and overheads on 674.41
10381 "Y-A"
profit and overheads on 1852.01
10417 "Y-A"
profit and overheads on 614.49
10439 "Y-A"
profit and overheads on 31.15
11153 "Y-A"
profit and overheads on 2054.61
11194 "Y-A"
profit and overheads on 2349.03
11234 "Y-A"
profit and overheads on 2650.03
11265 "Y-A"
profit and overheads on 2975.88
11307 "Y-A"
profit and overheads on 3558.98
11347 "Y-A"
profit and overheads on 4174.92
11387 "Y-A"
profit and overheads on 4737.55
11418 "Y-A"
profit and overheads on 5299.67
11459 "Y-A"
profit and overheads on 5883.33
11500 "Y-A"
profit and overheads on 6467.85
11531 "Y-A"
profit and overheads on 7050.93
11572 "Y-A"
profit and overheads on 8219.69
12121 "Y-A"
profit and overheads on 2282.25
12161 "Y-A"
profit and overheads on 3649.23
21793 "Y-A"
profit and overheads on 20788.31
21831 "Y-A"
profit and overheads on 24639.41
21871 "Y-A"
profit and overheads on 29102.58
21910 "Y-A"
profit and overheads on 28738.3
21979 "Y-A"
profit and overheads on 33497.7
22017 "Y-A"
profit and overheads on 32968.85
22055 "Y-A"
profit and overheads on 37634.25
22101 "Y-A"
profit and overheads on 8485.59
22142 "Y-A"
profit and overheads on 8828.08
22326 "Y-A"
profit and overheads on 33003.54
22365 "Y-A"
profit and overheads on 32432.7
22402 "Y-A"
profit and overheads on 33327.21
22443 "Y-A"
profit and overheads on 33987.64
22601 "Y-A"
profit and overheads on 14608.18
22641 "Y-A"
profit and overheads on 14673.01
22683 "Y-A"
profit and overheads on 1156.78
22718 "Y-A"
profit and overheads on 1167.01
22744 "Y-A"
profit and overheads on 1173.83
22779 "Y-A"
profit and overheads on 1220.96
22827 "Y-A"
profit and overheads on 22113.55
22870 "Y-A"
profit and overheads on 25515.15
22911 "Y-A"
profit and overheads on 22113.55
22950 "Y-A"
profit and overheads on 22113.55
23026 "Y-A"
profit and overheads on 22113.55
29 "Y"
profit and overheads on
63 "Y"
profit and overheads on
87 "Y"
profit and overheads on
122 "Y"
profit and overheads on
159 "Y"
profit and overheads on
183 "Y"
profit and overheads on
365 "Y"
profit and overheads on
399 "Y"
profit and overheads on
424 "Y"
profit and overheads on
459 "Y"
profit and overheads on
494 "Y"
profit and overheads on
519 "Y"
profit and overheads on
554 "Y"
profit and overheads on
586 "Y"
profit and overheads on
610 "Y"
profit and overheads on
645 "Y"
profit and overheads on
669 "Y"
profit and overheads on
811 "Y"
profit and overheads on
849 "Y"
profit and overheads on
877 "Y"
profit and overheads on
916 "Y"
profit and overheads on
954 "Y"
profit and overheads on
982 "Y"
profit and overheads on
1015 "Y"
profit and overheads on
1054 "Y"
profit and overheads on 1412.04
1083 "Y"
profit and overheads on
1338 "Y"
profit and overheads on
1405 "Y"
profit and overheads on
1423 "Y"
profit and overheads on
1460 "Y"
profit and overheads on
1496 "Y"
profit and overheads on 302.84
1521 "Y"
profit and overheads on
1556 "Y"
profit and overheads on
1581 "Y"
profit and overheads on
1616 "Y"
profit and overheads on
1800 "Y"
profit and overheads on 197.68
1826 "Y"
profit and overheads on
1860 "Y"
profit and overheads on
1886 "Y"
profit and overheads on
1923 "Y"
profit and overheads on
1958 "Y"
profit and overheads on 947.52
1984 "Y"
profit and overheads on
2021 "Y"
profit and overheads on
2057 "Y"
profit and overheads on 3467.53
2083 "Y"
profit and overheads on
2125 "Y"
profit and overheads on
2161 "Y" 359.26
profit and overheads on
2188 "Y"
profit and overheads on
2223 "Y"
profit and overheads on
2250 "Y"
profit and overheads on
2287 "Y"
profit and overheads on
2403 "Y"
profit and overheads on
2440 "Y"
profit and overheads on
2477 "Y"
profit and overheads on
2505 "Y"
profit and overheads on
2540 "Y"
profit and overheads on
2576 "Y"
profit and overheads on
2604 "Y"
profit and overheads on
2641 "Y"
profit and overheads on
2675 "Y"
profit and overheads on 58.51
2697 "Y"
profit and overheads on
2726 "Y"
profit and overheads on
2745 "Y"
profit and overheads on
2772 "Y"
profit and overheads on 42.16
2791 "Y"
profit and overheads on
2808 "Y"
profit and overheads on
2838 "Y"
profit and overheads on
2853 "Y"
profit and overheads on
2882 "Y"
profit and overheads on 75.07
2900 "Y"
profit and overheads on
2918 "Y"
profit and overheads on
2946 "Y"
profit and overheads on
2964 "Y"
profit and overheads on
2994 "Y"
profit and overheads on 43.74
3012 "Y"
profit and overheads on
3030 "Y"
profit and overheads on
3060 "Y"
profit and overheads on
3076 "Y"
profit and overheads on
3104 "Y"
profit and overheads on
3120 "Y"
profit and overheads on
3148 "Y"
profit and overheads on
3164 "Y"
profit and overheads on
3190 "Y"
profit and overheads on
3206 "Y"
profit and overheads on
3232 "Y"
profit and overheads on
3248 "Y"
profit and overheads on
3268 "Y"
profit and overheads on
3293 "Y"
profit and overheads on
3312 "Y"
profit and overheads on
3338 "Y"
profit and overheads on
3355 "Y"
profit and overheads on
3385 "Y"
profit and overheads on
3401 "Y"
profit and overheads on
3431 "Y"
profit and overheads on
3447 "Y"
profit and overheads on
3477 "Y"
profit and overheads on 19.61
3495 "Y"
profit and overheads on
3526 "Y"
profit and overheads on
3547 "Y"
profit and overheads on
4050 "Y"
profit and overheads on
4085 "Y"
profit and overheads on
4111 "Y"
profit and overheads on
4146 "Y"
profit and overheads on
4172 "Y"
profit and overheads on
4208 "Y"
profit and overheads on
4245 "Y"
profit and overheads on
4271 "Y"
profit and overheads on
4306 "Y"
profit and overheads on
4341 "Y"
profit and overheads on
4367 "Y"
profit and overheads on
4394 "Y"
profit and overheads on
4418 "Y"
profit and overheads on
4450 "Y"
profit and overheads on
4473 "Y"
profit and overheads on
4506 "Y"
profit and overheads on
4539 "Y"
profit and overheads on
4562 "Y"
profit and overheads on
4596 "Y"
profit and overheads on 542.19
4619 "Y"
profit and overheads on
4652 "Y"
profit and overheads on
4675 "Y"
profit and overheads on
4708 "Y"
profit and overheads on
4731 "Y"
profit and overheads on
6108 "Y"
profit and overheads on
6350 "Y"
profit and overheads on
6382 "Y"
profit and overheads on
6407 "Y"
profit and overheads on
6438 "Y"
profit and overheads on
6474 "Y"
profit and overheads on
6496 "Y"
profit and overheads on
6528 "Y"
profit and overheads on
6548 "Y"
profit and overheads on
6577 "Y"
profit and overheads on
6597 "Y"
profit and overheads on
6626 "Y"
profit and overheads on
6646 "Y"
profit and overheads on
6675 "Y" 108.37
profit and overheads on
6695 "Y"
profit and overheads on
6727 "Y"
profit and overheads on
6747 "Y"
profit and overheads on
6776 "Y"
profit and overheads on
6796 "Y"
profit and overheads on
6825 "Y"
profit and overheads on
6845 "Y"
profit and overheads on
6875 "Y"
profit and overheads on
6895 "Y"
profit and overheads on
6928 "Y"
profit and overheads on
6950 "Y"
profit and overheads on
6982 "Y"
profit and overheads on
7001 "Y"
profit and overheads on
7030 "Y"
profit and overheads on
7049 "Y"
profit and overheads on
7076 "Y"
profit and overheads on
7092 "Y"
profit and overheads on
7280 "Y"
profit and overheads on
7299 "Y"
profit and overheads on
7326 "Y"
profit and overheads on
7346 "Y"
profit and overheads on
7375 "Y"
profit and overheads on
7392 "Y"
profit and overheads on
7421 "Y"
profit and overheads on 13.5
7438 "Y"
profit and overheads on
7457 "Y"
profit and overheads on
7482 "Y"
profit and overheads on
7504 "Y"
profit and overheads on
7841 "Y"
profit and overheads on
7870 "Y"
profit and overheads on
7888 "Y"
profit and overheads on
7917 "Y"
profit and overheads on
7935 "Y"
profit and overheads on
7955 "Y"
profit and overheads on
7982 "Y"
profit and overheads on
7999 "Y"
profit and overheads on
8029 "Y"
profit and overheads on 5989.25
8228 "Y"
profit and overheads on
8250 "Y"
profit and overheads on
8282 "Y"
profit and overheads on
8304 "Y"
profit and overheads on
8336 "Y"
profit and overheads on
8358 "Y"
profit and overheads on
8390 "Y"
profit and overheads on
8422 "Y"
profit and overheads on
8444 "Y"
profit and overheads on
8466 "Y"
profit and overheads on
8498 "Y"
profit and overheads on
8520 "Y"
profit and overheads on
8551 "Y"
profit and overheads on
8573 "Y"
profit and overheads on
8605 "Y"
profit and overheads on
10209 "Y"
profit and overheads on
10227 "Y"
profit and overheads on
10255 "Y"
profit and overheads on 6.35
10272 "Y"
profit and overheads on
10289 "Y"
profit and overheads on
10478 "Y"
profit and overheads on
10512 "Y"
profit and overheads on 139.62
10535 "Y"
profit and overheads on
10565 "Y"
profit and overheads on
10588 "Y"
profit and overheads on
10620 "Y"
profit and overheads on
10653 "Y"
profit and overheads on
10676 "Y"
profit and overheads on
10713 "Y"
profit and overheads on
10736 "Y"
profit and overheads on
10768 "Y"
profit and overheads on
10800 "Y"
profit and overheads on 699.64
10822 "Y"
profit and overheads on
10856 "Y"
profit and overheads on
10876 "Y"
profit and overheads on
10909 "Y"
profit and overheads on
10929 "Y"
profit and overheads on
10962 "Y"
profit and overheads on
10982 "Y"
profit and overheads on
11015 "Y"
profit and overheads on
11035 "Y"
profit and overheads on
11068 "Y"
profit and overheads on
11088 "Y"
profit and overheads on
11121 "Y"
profit and overheads on
11594 "Y"
profit and overheads on
11622 "Y"
profit and overheads on
11640 "Y"
profit and overheads on
11665 "Y"
profit and overheads on
11683 "Y"
profit and overheads on
11711 "Y"
profit and overheads on 37.21
11729 "Y"
profit and overheads on
11747 "Y"
profit and overheads on
11775 "Y"
profit and overheads on
11793 "Y"
profit and overheads on
11818 "Y"
profit and overheads on 74.1
11836 "Y"
profit and overheads on
11865 "Y"
profit and overheads on 1004.94
11895 "Y"
profit and overheads on
11934 "Y"
profit and overheads on
11970 "Y"
profit and overheads on
11999 "Y"
profit and overheads on
12038 "Y"
profit and overheads on
12077 "Y"
profit and overheads on
12181 "Y"
profit and overheads on
12198 "Y"
profit and overheads on
12224 "Y"
profit and overheads on
12241 "Y"
profit and overheads on
12270 "Y"
profit and overheads on
12286 "Y"
profit and overheads on 31.1
12316 "Y"
profit and overheads on
12333 "Y"
profit and overheads on
12359 "Y"
profit and overheads on 25.05
12376 "Y"
profit and overheads on
12393 "Y"
profit and overheads on
12420 "Y"
profit and overheads on
12437 "Y"
profit and overheads on
12464 "Y"
profit and overheads on 62.55
12481 "Y"
profit and overheads on
12498 "Y"
profit and overheads on
12525 "Y"
profit and overheads on
12542 "Y"
profit and overheads on
12570 "Y"
profit and overheads on
12585 "Y"
profit and overheads on
12611 "Y"
profit and overheads on 70.84
12631 "Y"
profit and overheads on
12655 "Y"
profit and overheads on
12671 "Y"
profit and overheads on
12697 "Y"
profit and overheads on 22.63
12713 "Y"
profit and overheads on
12729 "Y"
profit and overheads on
12762 "Y"
profit and overheads on
12778 "Y"
profit and overheads on
12802 "Y"
profit and overheads on
12818 "Y"
profit and overheads on
12844 "Y"
profit and overheads on 20.04
12860 "Y"
profit and overheads on
12892 "Y"
profit and overheads on 25.57
12909 "Y"
profit and overheads on
12924 "Y"
profit and overheads on
12951 "Y"
profit and overheads on 49.59
12968 "Y"
profit and overheads on 59.61
12995 "Y"
profit and overheads on 30.93
13015 "Y"
profit and overheads on
13041 "Y"
profit and overheads on 39.91
13057 "Y"
profit and overheads on
13073 "Y"
profit and overheads on
13099 "Y"
profit and overheads on
13115 "Y"
profit and overheads on
13145 "Y"
profit and overheads on 30.93
13162 "Y"
profit and overheads on
13179 "Y"
profit and overheads on
13205 "Y"
profit and overheads on
13222 "Y"
profit and overheads on
13250 "Y"
profit and overheads on
13267 "Y"
profit and overheads on
13295 "Y"
profit and overheads on 118.01
13312 "Y"
profit and overheads on
13329 "Y"
profit and overheads on
13356 "Y"
profit and overheads on
13373 "Y"
profit and overheads on
13400 "Y"
profit and overheads on
13417 "Y"
profit and overheads on 153.26
13434 "Y"
profit and overheads on 153.26
13466 "Y"
profit and overheads on
13483 "Y"
profit and overheads on
13510 "Y"
profit and overheads on
13527 "Y"
profit and overheads on
13553 "Y"
profit and overheads on 47.17
13570 "Y"
profit and overheads on
13587 "Y"
profit and overheads on
13614 "Y"
profit and overheads on
13631 "Y"
profit and overheads on
13660 "Y"
profit and overheads on
13677 "Y"
profit and overheads on
13705 "Y"
profit and overheads on 118.01
13722 "Y"
profit and overheads on
13739 "Y"
profit and overheads on
13766 "Y"
profit and overheads on
13783 "Y"
profit and overheads on
13810 "Y"
profit and overheads on 153.26
13827 "Y"
profit and overheads on
13844 "Y"
profit and overheads on
13872 "Y"
profit and overheads on
13889 "Y"
profit and overheads on
13921 "Y"
profit and overheads on
13938 "Y"
profit and overheads on
13964 "Y"
profit and overheads on 34.56
13981 "Y"
profit and overheads on
13998 "Y"
profit and overheads on
14023 "Y"
profit and overheads on
14040 "Y"
profit and overheads on
14067 "Y"
profit and overheads on 75.51
14084 "Y"
profit and overheads on
14101 "Y"
profit and overheads on
14128 "Y"
profit and overheads on
14145 "Y"
profit and overheads on
14172 "Y"
profit and overheads on 118.01
14189 "Y"
profit and overheads on
14206 "Y"
profit and overheads on
14234 "Y"
profit and overheads on
14253 "Y"
profit and overheads on
14280 "Y"
profit and overheads on
14297 "Y"
profit and overheads on
14324 "Y"
profit and overheads on 153.26
14341 "Y"
profit and overheads on
14372 "Y"
profit and overheads on 32.83
14390 "Y"
profit and overheads on
14409 "Y"
profit and overheads on
14436 "Y"
profit and overheads on
14455 "Y"
profit and overheads on
14483 "Y"
profit and overheads on 58.23
14501 "Y"
profit and overheads on 70.67
14519 "Y"
profit and overheads on
14548 "Y"
profit and overheads on 99.52
14566 "Y"
profit and overheads on 117.67
14595 "Y"
profit and overheads on 144.79
14613 "Y"
profit and overheads on
14643 "Y"
profit and overheads on 33.35
14661 "Y"
profit and overheads on
14687 "Y"
profit and overheads on 42.85
14705 "Y"
profit and overheads on
14734 "Y"
profit and overheads on 55.29
14751 "Y"
profit and overheads on 79.65
14768 "Y"
profit and overheads on 97.62
14794 "Y"
profit and overheads on
14811 "Y"
profit and overheads on 125.44
14838 "Y"
profit and overheads on 145.14
14855 "Y" 196.63
profit and overheads on
14886 "Y"
profit and overheads on 40.43
14903 "Y"
profit and overheads on
14920 "Y"
profit and overheads on
14948 "Y"
profit and overheads on
14965 "Y"
profit and overheads on
14992 "Y"
profit and overheads on 151.19
15009 "Y"
profit and overheads on
15039 "Y"
profit and overheads on 25.92
15056 "Y"
profit and overheads on
15071 "Y"
profit and overheads on
15097 "Y"
profit and overheads on 35.42
15114 "Y"
profit and overheads on 49.59
15142 "Y"
profit and overheads on
15159 "Y"
profit and overheads on 82.59
15187 "Y"
profit and overheads on 118.01
15204 "Y"
profit and overheads on 118.01
15245 "Y"
profit and overheads on 33
15447 "Y"
profit and overheads on 49.59
15511 "Y"
profit and overheads on 82.59
15595 "Y"
profit and overheads on
15609 "Y"
profit and overheads on
15634 "Y"
profit and overheads on
15648 "Y"
profit and overheads on
15662 "Y"
profit and overheads on
15686 "Y"
profit and overheads on
15706 "Y"
profit and overheads on
15734 "Y"
profit and overheads on
15749 "Y"
profit and overheads on
15811 "Y"
profit and overheads on
15855 "Y"
profit and overheads on
15897 "Y"
profit and overheads on
15942 "Y"
profit and overheads on
15986 "Y"
profit and overheads on 5660.6
16666 "Y"
profit and overheads on
16693 "Y"
profit and overheads on 52.11
16712 "Y"
profit and overheads on
16730 "Y"
profit and overheads on
16757 "Y"
profit and overheads on
16775 "Y"
profit and overheads on
16801 "Y"
profit and overheads on
16819 "Y"
profit and overheads on
16865 "Y"
profit and overheads on
16909 "Y"
profit and overheads on
17083 "Y"
profit and overheads on
17126 "Y"
profit and overheads on
17170 "Y"
profit and overheads on
17215 "Y"
profit and overheads on
17258 "Y"
profit and overheads on
17302 "Y"
profit and overheads on
17334 "Y"
profit and overheads on
17380 "Y"
profit and overheads on
17424 "Y"
profit and overheads on
19137 "Y"
profit and overheads on
19169 "Y"
profit and overheads on
19191 "Y"
profit and overheads on
19458 "Y"
profit and overheads on
21187 "Y"
profit and overheads on 41.78
21215 "Y"
profit and overheads on
21253 "Y"
profit and overheads on
21292 "Y"
profit and overheads on
21328 "Y"
profit and overheads on 5856.31
21356 "Y"
profit and overheads on
21392 "Y"
profit and overheads on
21431 "Y"
profit and overheads on 17459.13
21461 "Y"
profit and overheads on
21607 "Y"
profit and overheads on
21635 "Y"
profit and overheads on
21673 "Y"
profit and overheads on
21710 "Y"
profit and overheads on
23059 "Y"
profit and overheads on
23076 "Y"
profit and overheads on 2591.79
23104 "Y"
profit and overheads on
23120 "Y"
profit and overheads on
23150 "Y"
profit and overheads on
23167 "Y"
profit and overheads on 5097.18
23197 "Y"
profit and overheads on
23213 "Y"
profit and overheads on
23261 "Y"
profit and overheads on 2591.79
23278 "Y"
profit and overheads on 4077.74
23314 "Y"
Add 15% for fittings,
622 clamps
Add 15% and
for fittings,
657 clamps and
Add 2% for special T&P
11883 and
Add sundries etc. T&P
2% for special
11922 and
Add sundries etc. T&P
2% for special
11949 and
Add sundries etc. T&P
2% for special
11987 and
Add sundries etc. T&P
2% for special
12026 and sundries
Add etc. T&P
2% for special
12065 and sundries etc. T&P
Add 2% for special
12100 and
Add sundries etc. T&P
2% for special
12139 and sundries etc.
Add 20% for fittings,
598 clamps
clamps and
and wastage etc.
798 on P,
clamps and wastage etc.
826 on P, and wastage etc.
clamps 133.6
864 on P, and wastage etc.
clamps
903 on P, and wastage etc.
clamps
931 on P, and wastage etc.
clamps
969 on P, and wastage etc.
clamps
1002 on P, and wastage etc.
clamps
1031 on P, and wastage etc.
clamps
1070 on
AddP,3% for pipe inserted
11880 into
Add fitting
3% forandpipe inserted
11919 into fitting and
Add 3% for pipe inserted
11946 into
Add fitting
3% forandpipe inserted
11984 into fitting
Add 3% forandpipe inserted
12023 into fitting and
Add 3% for pipe inserted
12052 into
Add fitting
3% forandpipe inserted
12093 into fitting and
Add 3% for pipe inserted
12132 into fitting
Add 30% for andfittings and
352 wastage etc. on (X) and
Add 30% for fittings
377 wastage
Add 30%etc. on (X) and
for fittings
411 wastage
Add 30%etc. on (X) and
for fittings
446 wastage
Add 30%etc. on (X) and
for fittings
506 wastage etc. on (X) and
Add 30% for fittings
1776 wastage
Add 30%etc. on (X) and
for fittings
1813 wastage
Add 30%etc. on (X) and
for fittings
1837 wastage
Add 30%etc. on (X) and
for fittings
1873 wastage etc. on (X) and
Add 30% for fittings
1910 wastage
Add 30%etc. on (X) and
for fittings
1936 wastage
Add 30%etc. on (X) and
for fittings
1971 wastage
Add 30%etc. on (X) and
for fittings
2008 wastage etc. on (X) and
Add 30% for fittings
2034 wastage
Add 30%etc. on (X) and
for fittings
2070 wastage
wastage etc.
etc. on
on (X)
(X) 30 *
17 X /
wastage etc. on (X) 30 *
51 X /
wastage etc. on (X) 30 *
75 X /
wastage etc. on (X) 30 *
110 X /
wastage etc. on (X) 30 *
147 X /
wastage etc. on (X) 30 *
171 X /
wastage etc. on (X) 30 *
471 X /
wastage etc. on (X) 30 *
1448 X /
wastage etc. on (X) 30 *
1475 X/
wastage etc. on (X) 30 *
1509 X /
wastage etc. on (X) 30 *
1534 X /
wastage etc. on (X) 30 *
1569 X/
wastage etc. on (X) 30 *
1604 X / 30% for fittings,
Add
542 clamps
Add 30%and
for fittings,
565 clamps
clamps and
and wastage etc.
755 on P, and wastage etc.
clamps
209 on (X) and wastage etc.
clamps
244 on (X) and wastage etc.
clamps
268 on (X) and wastage etc.
clamps
304 on (X) and wastage etc.
clamps
1643 on (X) and wastage etc.
clamps
1670 on (X) and wastage etc.
clamps
1707 on (X) and wastage etc.
clamps
1734 on (X) and wastage etc.
clamps
696 on P, and wastage etc.
clamps
721 on P,
225 Add Cess @ 1% on "Z-A" 2253.3
260 Add Cess @ 1% on "Z-A" 2624.21
294 Add Cess @ 1% on "Z-A" 3366.04 33.66
320 Add Cess @ 1% on "Z-A" 4455.59
712 Add Cess @ 1% on "Z-A" 1819.1
746 Add Cess @ 1% on "Z-A" 2364.57
771 Add Cess @ 1% on "Z-A" 2951.47
1659 Add Cess @ 1% on "Z-A" 1941.5
1696 Add Cess @ 1% on "Z-A" 2619.57
1723 Add Cess @ 1% on "Z-A" 3449.49
1760 Add Cess @ 1% on "Z-A" 4609.76
2330 Add Cess @ 1% on "Z-A" 2225.42
2374 Add Cess @ 1% on "Z-A" 2667.72
3583 Add Cess @ 1% on "Z-A" 4781.38
3604 Add Cess @ 1% on "Z-A" 4913.85
3639 Add Cess @ 1% on "Z-A" 7298.3
3660 Add Cess @ 1% on "Z-A" 7298.3
3696 Add Cess @ 1% on "Z-A" 11383.33
3731 Add Cess @ 1% on "Z-A" 14175.5 141.75
3756 Add Cess @ 1% on "Z-A" 17086.74
3792 Add Cess @ 1% on "Z-A" 29094.04
3827 Add Cess @ 1% on "Z-A" 37964.81
3853 Add Cess @ 1% on "Z-A" 51239.66
3889 Add Cess @ 1% on "Z-A" 61392.33
3915 Add Cess @ 1% on "Z-A" 81019.26
3953 Add Cess @ 1% on "Z-A" 98116.87
3989 Add Cess @ 1% on "Z-A" 113880.69 1138.81
4016 Add Cess @ 1% on "Z-A" 159408.82
4774 Add Cess @ 1% on "Z-A" 31980.03
4810 Add Cess @ 1% on "Z-A" 35836.63
4836 Add Cess @ 1% on "Z-A" 34511.94
4871 Add Cess @ 1% on "Z-A" 42475.08
4909 Add Cess @ 1% on "Z-A" 47778.84
4945 Add Cess @ 1% on "Z-A" 53095.73
4972 Add Cess @ 1% on "Z-A" 99504.27
5007 Add Cess @ 1% on "Z-A" 118084.93 1180.85
5034 Add Cess @ 1% on "Z-A" 145675.99 1456.76
5069 Add Cess @ 1% on "Z-A" 192367.59 1923.68
5106 Add Cess @ 1% on "Z-A" 205629.49 2056.29
5131 Add Cess @ 1% on "Z-A" 241472.37 2414.72
5205 Add Cess @ 1% on "Z-A" 164.25
5277 Add Cess @ 1% on "Z-A" 184.89
5357 Add Cess @ 1% on "Z-A" 104.14 1.04
5430 Add Cess @ 1% on "Z-A" -6.36
5500 Add Cess @ 1% on "Z-A" 340.13
5582 Add Cess @ 1% on "Z-A" 214.1
5604 Add Cess @ 1% on "Z-A" 35.82
5636 Add Cess @ 1% on "Z-A" 35.82
5658 Add Cess @ 1% on "Z-A" 53.73
5690 Add Cess @ 1% on "Z-A" 53.73
5710 Add Cess @ 1% on "Z-A" 71.29
5740 Add Cess @ 1% on "Z-A" 71.29
5761 Add Cess @ 1% on "Z-A" 21.35
5789 Add Cess @ 1% on "Z-A" 21.35
5808 Add Cess @ 1% on "Z-A" 28.59
5837 Add Cess @ 1% on "Z-A" 28.93 0.29
5856 Add Cess @ 1% on "Z-A" 35.82
5885 Add Cess @ 1% on "Z-A" 35.82
5905 Add Cess @ 1% on "Z-A" 21.35
5923 Add Cess @ 1% on "Z-A" 21.35
5951 Add Cess @ 1% on "Z-A" 28.59
5969 Add Cess @ 1% on "Z-A" 28.59
5996 Add Cess @ 1% on "Z-A" 32.38 0.32
6014 Add Cess @ 1% on "Z-A" 32.38
6043 Add Cess @ 1% on "Z-A" 35.82
6061 Add Cess @ 1% on "Z-A" 39.26
7539 Add Cess @ 1% on "Z-A" 49384.47
7572 Add Cess @ 1% on "Z-A" 60114.47
7595 Add Cess @ 1% on "Z-A" 78495.88
7631 Add Cess @ 1% on "Z-A" 3205.75
7654 Add Cess @ 1% on "Z-A" 4714.57
7687 Add Cess @ 1% on "Z-A" 7000.99
7719 Add Cess @ 1% on "Z-A" 7642.14 76.42
7742 Add Cess @ 1% on "Z-A" 3722.38
7772 Add Cess @ 1% on "Z-A" 5995.55 59.96
7793 Add Cess @ 1% on "Z-A" 7614.32
7823 Add Cess @ 1% on "Z-A" 10825.37 108.25
8061 Add Cess @ 1% on "Z-A" 8225.58 82.26
8083 Add Cess @ 1% on "Z-A" 11366.42
8112 Add Cess @ 1% on "Z-A" 11998.3 119.98
8133 Add Cess @ 1% on "Z-A" 16438.66
8150 Add Cess @ 1% on "Z-A" 22797.18
8181 Add Cess @ 1% on "Z-A" 17299.71
8198 Add Cess @ 1% on "Z-A" 24850.45
8645 Add Cess @ 1% on "Z-A" 8692.09
8670 Add Cess @ 1% on "Z-A" 13590.44
8705 Add Cess @ 1% on "Z-A" 21488.4
8732 Add Cess @ 1% on "Z-A" 25923.78
8768 Add Cess @ 1% on "Z-A" 33124.2
8803 Add Cess @ 1% on "Z-A" 41737.46
8828 Add Cess @ 1% on "Z-A" 54074.47
8865 Add Cess @ 1% on "Z-A" 68928.8
8899 Add Cess @ 1% on "Z-A" 85706
8924 Add Cess @ 1% on "Z-A" 118849.02 1188.49
8961 Add Cess @ 1% on "Z-A" 10628.26
8985 Add Cess @ 1% on "Z-A" 15152.69
9019 Add Cess @ 1% on "Z-A" 18628.98
9054 Add Cess @ 1% on "Z-A" 23962.82
9078 Add Cess @ 1% on "Z-A" 29951.87
9113 Add Cess @ 1% on "Z-A" 35309.17 353.09
9137 Add Cess @ 1% on "Z-A" 42338.29
9173 Add Cess @ 1% on "Z-A" 51368.53
9198 Add Cess @ 1% on "Z-A" 57965.49
9233 Add Cess @ 1% on "Z-A" 74694.85
9269 Add Cess @ 1% on "Z-A" 97214.59
9294 Add Cess @ 1% on "Z-A" 121059.02
9328 Add Cess @ 1% on "Z-A" 157081.76 1570.82
9353 Add Cess @ 1% on "Z-A" 163961.29
9386 Add Cess @ 1% on "Z-A" 10164.61
9412 Add Cess @ 1% on "Z-A" 15285.16
9447 Add Cess @ 1% on "Z-A" 20947.19
9482 Add Cess @ 1% on "Z-A" 29261.59 292.62
9508 Add Cess @ 1% on "Z-A" 36575.33
9544 Add Cess @ 1% on "Z-A" 44582.01
9570 Add Cess @ 1% on "Z-A" 57241.07
9606 Add Cess @ 1% on "Z-A" 66575.98
9643 Add Cess @ 1% on "Z-A" 83399.55 834
9670 Add Cess @ 1% on "Z-A" 100658.79
9705 Add Cess @ 1% on "Z-A" 139433.97 1394.34
9740 Add Cess @ 1% on "Z-A" 151120.65 1511.21
9765 Add Cess @ 1% on "Z-A" 152701.42
9800 Add Cess @ 1% on "Z-A" 185156.35 1851.56
9825 Add Cess @ 1% on "Z-A" 207013.74
9863 Add Cess @ 1% on "Z-A" 7301.16
9899 Add Cess @ 1% on "Z-A" 10954.31 109.54
9925 Add Cess @ 1% on "Z-A" 13785.32
9960 Add Cess @ 1% on "Z-A" 19598.38
9986 Add Cess @ 1% on "Z-A" 25176.06
10022 Add Cess @ 1% on "Z-A" 31762.54
10058 Add Cess @ 1% on "Z-A" 40873.92
10082 Add Cess @ 1% on "Z-A" 42911.87
10118 Add Cess @ 1% on "Z-A" 60974.03
10154 Add Cess @ 1% on "Z-A" 80731.05 807.31
10178 Add Cess @ 1% on "Z-A" 95349.75
10337 Add Cess @ 1% on "Z-A" 775.58
10383 Add Cess @ 1% on "Z-A" 2129.81
10419 Add Cess @ 1% on "Z-A" 706.66
10441 Add Cess @ 1% on "Z-A" 35.82
11165 Add Cess @ 1% on "Z-A" 2362.8 23.63
11196 Add Cess @ 1% on "Z-A" 2701.39
11236 Add Cess @ 1% on "Z-A" 3047.54
11278 Add Cess @ 1% on "Z-A" 3422.27 34.22
11309 Add Cess @ 1% on "Z-A" 4092.82
11349 Add Cess @ 1% on "Z-A" 4801.16
11389 Add Cess @ 1% on "Z-A" 5448.18
11420 Add Cess @ 1% on "Z-A" 6094.62
11461 Add Cess @ 1% on "Z-A" 6765.82
11502 Add Cess @ 1% on "Z-A" 7438.03
11533 Add Cess @ 1% on "Z-A" 8108.57
11574 Add Cess @ 1% on "Z-A" 9452.64
12123 Add Cess @ 1% on "Z-A" 2624.59
12163 Add Cess @ 1% on "Z-A" 4196.62
16372 Add Cess @ 1% on "Z-A" 829.55
16424 Add Cess @ 1% on "Z-A" 829.55 8.3
16483 Add Cess @ 1% on "Z-A" 888.1 8.88
16538 Add Cess @ 1% on "Z-A" 888.1 8.88
16594 Add Cess @ 1% on "Z-A" 1027.96 10.28
16647 Add Cess @ 1% on "Z-A" 1027.96 10.28
17533 Add Cess @ 1% on "Z-A" 1819.56
17681 Add Cess @ 1% on "Z-A" 1819.56 18.2
17763 Add Cess @ 1% on "Z-A" 5752.18
17922 Add Cess @ 1% on "Z-A" 5752.18
18022 Add Cess @ 1% on "Z-A" 11856.31 118.56
18122 Add Cess @ 1% on "Z-A" 11856.31 118.56
18309 Add Cess @ 1% on "Z-A" 1296.36
18407 Add Cess @ 1% on "Z-A" 1296.36
18558 Add Cess @ 1% on "Z-A" 1341.42 13.41
18651 Add Cess @ 1% on "Z-A" 1341.42
18788 Add Cess @ 1% on "Z-A" 1341.42
18873 Add Cess @ 1% on "Z-A" 1341.42
18956 Add Cess @ 1% on "Z-A" 283.78 2.84
18988 Add Cess @ 1% on "Z-A" 245.63
19026 Add Cess @ 1% on "Z-A" 283.62
19071 Add Cess @ 1% on "Z-A" 338.83
19114 Add Cess @ 1% on "Z-A" 300.68
19233 Add Cess @ 1% on "Z-A" 947.9
19269 Add Cess @ 1% on "Z-A" 815.43
19295 Add Cess @ 1% on "Z-A" 815.43
19335 Add Cess @ 1% on "Z-A" 949.54
19370 Add Cess @ 1% on "Z-A" 823.69 8.24
19400 Add Cess @ 1% on "Z-A" 1255.28
19439 Add Cess @ 1% on "Z-A" 1639.44
19510 Add Cess @ 1% on "Z-A" 294.83
19557 Add Cess @ 1% on "Z-A" 296.21
19601 Add Cess @ 1% on "Z-A" 391.81
19679 Add Cess @ 1% on "Z-A" 3813.5
19764 Add Cess @ 1% on "Z-A" 5364.52
19815 Add Cess @ 1% on "Z-A" 951.78
19864 Add Cess @ 1% on "Z-A" 1422.4
19926 Add Cess @ 1% on "Z-A" 18.94
19981 Add Cess @ 1% on "Z-A" 18.94
20048 Add Cess @ 1% on "Z-A" 40.3
20115 Add Cess @ 1% on "Z-A" 40.3
20150 Add Cess @ 1% on "Z-A" 4.82
20171 Add Cess @ 1% on "Z-A" 4.82
20315 Add Cess @ 1% on "Z-A" 40.38
20370 Add Cess @ 1% on "Z-A" 54.76 0.55
20419 Add Cess @ 1% on "Z-A" 63.03 0.63
20459 Add Cess @ 1% on "Z-A" 72.67
20506 Add Cess @ 1% on "Z-A" 75.08
20559 Add Cess @ 1% on "Z-A" 854.37
20633 Add Cess @ 1% on "Z-A" 318.04
20728 Add Cess @ 1% on "Z-A" 1193.77
20810 Add Cess @ 1% on "Z-A" 1928.27
20881 Add Cess @ 1% on "Z-A" 1826.27
20954 Add Cess @ 1% on "Z-A" 1792.27
21104 Add Cess @ 1% on "Z-A" 17792.84 177.93
21149 Add Cess @ 1% on "Z-A" 1758.14
21795 Add Cess @ 1% on "Z-A" 23906.56
21833 Add Cess @ 1% on "Z-A" 28335.32
21873 Add Cess @ 1% on "Z-A" 33467.97
21912 Add Cess @ 1% on "Z-A" 33049.05
21981 Add Cess @ 1% on "Z-A" 38522.35
22019 Add Cess @ 1% on "Z-A" 37914.18
22057 Add Cess @ 1% on "Z-A" 43279.38
22103 Add Cess @ 1% on "Z-A" 9758.43
22144 Add Cess @ 1% on "Z-A" 10152.29
22328 Add Cess @ 1% on "Z-A" 37954.07
22367 Add Cess @ 1% on "Z-A" 37297.6
22404 Add Cess @ 1% on "Z-A" 38326.3
22445 Add Cess @ 1% on "Z-A" 39085.79
22603 Add Cess @ 1% on "Z-A" 16799.41
22643 Add Cess @ 1% on "Z-A" 16873.96
22685 Add Cess @ 1% on "Z-A" 1330.29
22720 Add Cess @ 1% on "Z-A" 1342.06
22746 Add Cess @ 1% on "Z-A" 1349.9
22781 Add Cess @ 1% on "Z-A" 1404.11
22829 Add Cess @ 1% on "Z-A" 25430.59
22872 Add Cess @ 1% on "Z-A" 29342.42
22913 Add Cess @ 1% on "Z-A" 25430.59
22952 Add Cess @ 1% on "Z-A" 25430.59
31 Add Cess @ 1% on "Z"
65 Add Cess @ 1% on "Z"
100 Add Cess @ 1% on "Z" 28.76
124 Add Cess @ 1% on "Z"
161 Add Cess @ 1% on "Z"
195 Add Cess @ 1% on "Z" 71.12
367 Add Cess @ 1% on "Z"
401 Add Cess @ 1% on "Z"
436 Add Cess @ 1% on "Z" 25.74
461 Add Cess @ 1% on "Z"
496 Add Cess @ 1% on "Z"
521 Add Cess @ 1% on "Z"
556 Add Cess @ 1% on "Z"
588 Add Cess @ 1% on "Z"
612 Add Cess @ 1% on "Z"
647 Add Cess @ 1% on "Z"
671 Add Cess @ 1% on "Z"
813 Add Cess @ 1% on "Z"
851 Add Cess @ 1% on "Z"
890 Add Cess @ 1% on "Z" 24.51
918 Add Cess @ 1% on "Z"
956 Add Cess @ 1% on "Z"
984 Add Cess @ 1% on "Z"
1017 Add Cess @ 1% on "Z"
1056 Add Cess @ 1% on "Z" 108.26
1085 Add Cess @ 1% on "Z"
1340 Add Cess @ 1% on "Z"
1407 Add Cess @ 1% on "Z"
1425 Add Cess @ 1% on "Z"
1462 Add Cess @ 1% on "Z"
1498 Add Cess @ 1% on "Z" 23.22
1523 Add Cess @ 1% on "Z"
1558 Add Cess @ 1% on "Z"
1593 Add Cess @ 1% on "Z" 53.67
1618 Add Cess @ 1% on "Z"
1802 Add Cess @ 1% on "Z" 15.16
1828 Add Cess @ 1% on "Z"
1862 Add Cess @ 1% on "Z"
1888 Add Cess @ 1% on "Z"
1925 Add Cess @ 1% on "Z"
1960 Add Cess @ 1% on "Z" 72.64
1986 Add Cess @ 1% on "Z"
2023 Add Cess @ 1% on "Z"
2059 Add Cess @ 1% on "Z" 265.84
2085 Add Cess @ 1% on "Z"
2127 Add Cess @ 1% on "Z"
2163 Add Cess @ 1% on "Z" 27.54
2190 Add Cess @ 1% on "Z"
2225 Add Cess @ 1% on "Z"
2252 Add Cess @ 1% on "Z"
2289 Add Cess @ 1% on "Z"
2415 Add Cess @ 1% on "Z" 19.25
2442 Add Cess @ 1% on "Z"
2479 Add Cess @ 1% on "Z"
2516 Add Cess @ 1% on "Z"
2542 Add Cess @ 1% on "Z"
2578 Add Cess @ 1% on "Z"
2606 Add Cess @ 1% on "Z"
2643 Add Cess @ 1% on "Z"
2677 Add Cess @ 1% on "Z" 4.49
2699 Add Cess @ 1% on "Z"
2728 Add Cess @ 1% on "Z"
2747 Add Cess @ 1% on "Z"
2774 Add Cess @ 1% on "Z" 3.23
2793 Add Cess @ 1% on "Z"
2810 Add Cess @ 1% on "Z"
2840 Add Cess @ 1% on "Z"
2855 Add Cess @ 1% on "Z"
2884 Add Cess @ 1% on "Z" 5.75
2902 Add Cess @ 1% on "Z"
2920 Add Cess @ 1% on "Z"
2948 Add Cess @ 1% on "Z"
2966 Add Cess @ 1% on "Z"
2996 Add Cess @ 1% on "Z" 3.35
3014 Add Cess @ 1% on "Z"
3042 Add Cess @ 1% on "Z" 3.9
3062 Add Cess @ 1% on "Z"
3078 Add Cess @ 1% on "Z"
3106 Add Cess @ 1% on "Z"
3122 Add Cess @ 1% on "Z"
3150 Add Cess @ 1% on "Z"
3166 Add Cess @ 1% on "Z"
3192 Add Cess @ 1% on "Z"
3208 Add Cess @ 1% on "Z"
3234 Add Cess @ 1% on "Z"
3250 Add Cess @ 1% on "Z"
3279 Add Cess @ 1% on "Z"
3295 Add Cess @ 1% on "Z"
3323 Add Cess @ 1% on "Z" 2.92
3340 Add Cess @ 1% on "Z"
3357 Add Cess @ 1% on "Z"
3387 Add Cess @ 1% on "Z"
3403 Add Cess @ 1% on "Z"
3433 Add Cess @ 1% on "Z"
3449 Add Cess @ 1% on "Z"
3479 Add Cess @ 1% on "Z" 1.5
3497 Add Cess @ 1% on "Z"
3528 Add Cess @ 1% on "Z"
3549 Add Cess @ 1% on "Z"
4052 Add Cess @ 1% on "Z"
4087 Add Cess @ 1% on "Z"
4113 Add Cess @ 1% on "Z"
4148 Add Cess @ 1% on "Z"
4184 Add Cess @ 1% on "Z" 58.06
4210 Add Cess @ 1% on "Z"
4247 Add Cess @ 1% on "Z"
4273 Add Cess @ 1% on "Z"
4308 Add Cess @ 1% on "Z"
4343 Add Cess @ 1% on "Z"
4369 Add Cess @ 1% on "Z"
4396 Add Cess @ 1% on "Z"
4420 Add Cess @ 1% on "Z"
4452 Add Cess @ 1% on "Z"
4475 Add Cess @ 1% on "Z"
4508 Add Cess @ 1% on "Z"
4541 Add Cess @ 1% on "Z"
4564 Add Cess @ 1% on "Z"
4598 Add Cess @ 1% on "Z" 41.57
4621 Add Cess @ 1% on "Z"
4654 Add Cess @ 1% on "Z"
4677 Add Cess @ 1% on "Z"
4710 Add Cess @ 1% on "Z"
4733 Add Cess @ 1% on "Z"
6110 Add Cess @ 1% on "Z"
6352 Add Cess @ 1% on "Z"
6384 Add Cess @ 1% on "Z"
6418 Add Cess @ 1% on "Z" 30.07
6440 Add Cess @ 1% on "Z"
6476 Add Cess @ 1% on "Z"
6498 Add Cess @ 1% on "Z"
6530 Add Cess @ 1% on "Z"
6550 Add Cess @ 1% on "Z"
6579 Add Cess @ 1% on "Z"
6599 Add Cess @ 1% on "Z"
6628 Add Cess @ 1% on "Z"
6648 Add Cess @ 1% on "Z"
6677 Add Cess @ 1% on "Z" 8.31
6697 Add Cess @ 1% on "Z"
6729 Add Cess @ 1% on "Z"
6749 Add Cess @ 1% on "Z"
6778 Add Cess @ 1% on "Z"
6798 Add Cess @ 1% on "Z"
6827 Add Cess @ 1% on "Z"
6847 Add Cess @ 1% on "Z"
6877 Add Cess @ 1% on "Z"
6897 Add Cess @ 1% on "Z"
6930 Add Cess @ 1% on "Z"
6952 Add Cess @ 1% on "Z"
6984 Add Cess @ 1% on "Z"
7003 Add Cess @ 1% on "Z"
7032 Add Cess @ 1% on "Z"
7051 Add Cess @ 1% on "Z"
7078 Add Cess @ 1% on "Z"
7094 Add Cess @ 1% on "Z"
7265 Add Cess @ 1% on "Z" 1.75
7282 Add Cess @ 1% on "Z"
7301 Add Cess @ 1% on "Z"
7328 Add Cess @ 1% on "Z"
7348 Add Cess @ 1% on "Z"
7377 Add Cess @ 1% on "Z"
7394 Add Cess @ 1% on "Z"
7423 Add Cess @ 1% on "Z" 1.03
7440 Add Cess @ 1% on "Z"
7469 Add Cess @ 1% on "Z"
7484 Add Cess @ 1% on "Z"
7506 Add Cess @ 1% on "Z"
7843 Add Cess @ 1% on "Z"
7872 Add Cess @ 1% on "Z"
7890 Add Cess @ 1% on "Z"
7919 Add Cess @ 1% on "Z"
7937 Add Cess @ 1% on "Z"
7967 Add Cess @ 1% on "Z" 1.54
7984 Add Cess @ 1% on "Z"
8010 Add Cess @ 1% on "Z" 1.29
8031 Add Cess @ 1% on "Z" 6887.64
8230 Add Cess @ 1% on "Z"
8252 Add Cess @ 1% on "Z"
8284 Add Cess @ 1% on "Z"
8306 Add Cess @ 1% on "Z"
8338 Add Cess @ 1% on "Z"
8360 Add Cess @ 1% on "Z"
8392 Add Cess @ 1% on "Z"
8424 Add Cess @ 1% on "Z"
8446 Add Cess @ 1% on "Z"
8478 Add Cess @ 1% on "Z" 370.24
8500 Add Cess @ 1% on "Z"
8522 Add Cess @ 1% on "Z"
8553 Add Cess @ 1% on "Z"
8575 Add Cess @ 1% on "Z"
8607 Add Cess @ 1% on "Z"
10211 Add Cess @ 1% on "Z"
10229 Add Cess @ 1% on "Z"
10257 Add Cess @ 1% on "Z" 0.49
10274 Add Cess @ 1% on "Z"
10291 Add Cess @ 1% on "Z"
10480 Add Cess @ 1% on "Z"
10514 Add Cess @ 1% on "Z" 10.7
10537 Add Cess @ 1% on "Z"
10567 Add Cess @ 1% on "Z"
10599 Add Cess @ 1% on "Z" 21.74
10622 Add Cess @ 1% on "Z"
10655 Add Cess @ 1% on "Z"
10678 Add Cess @ 1% on "Z"
10715 Add Cess @ 1% on "Z"
10738 Add Cess @ 1% on "Z"
10770 Add Cess @ 1% on "Z"
10802 Add Cess @ 1% on "Z" 53.64
10824 Add Cess @ 1% on "Z"
10858 Add Cess @ 1% on "Z"
10878 Add Cess @ 1% on "Z"
10911 Add Cess @ 1% on "Z"
10931 Add Cess @ 1% on "Z"
10964 Add Cess @ 1% on "Z"
10984 Add Cess @ 1% on "Z"
11017 Add Cess @ 1% on "Z"
11037 Add Cess @ 1% on "Z"
11070 Add Cess @ 1% on "Z"
11090 Add Cess @ 1% on "Z"
11123 Add Cess @ 1% on "Z"
11606 Add Cess @ 1% on "Z" 0.68
11624 Add Cess @ 1% on "Z"
11642 Add Cess @ 1% on "Z"
11667 Add Cess @ 1% on "Z"
11685 Add Cess @ 1% on "Z"
11713 Add Cess @ 1% on "Z" 2.85
11731 Add Cess @ 1% on "Z"
11749 Add Cess @ 1% on "Z"
11777 Add Cess @ 1% on "Z"
11795 Add Cess @ 1% on "Z"
11820 Add Cess @ 1% on "Z" 5.68
11838 Add Cess @ 1% on "Z"
11867 Add Cess @ 1% on "Z" 77.05
11897 Add Cess @ 1% on "Z"
11936 Add Cess @ 1% on "Z"
11972 Add Cess @ 1% on "Z"
12001 Add Cess @ 1% on "Z"
12040 Add Cess @ 1% on "Z"
12079 Add Cess @ 1% on "Z"
12183 Add Cess @ 1% on "Z"
12209 Add Cess @ 1% on "Z" 0.83
12226 Add Cess @ 1% on "Z"
12243 Add Cess @ 1% on "Z"
12272 Add Cess @ 1% on "Z"
12288 Add Cess @ 1% on "Z" 2.38
12318 Add Cess @ 1% on "Z"
12335 Add Cess @ 1% on "Z"
12361 Add Cess @ 1% on "Z" 1.92
12378 Add Cess @ 1% on "Z"
12395 Add Cess @ 1% on "Z"
12422 Add Cess @ 1% on "Z"
12439 Add Cess @ 1% on "Z"
12466 Add Cess @ 1% on "Z" 4.8
12483 Add Cess @ 1% on "Z"
12510 Add Cess @ 1% on "Z" 5.13
12527 Add Cess @ 1% on "Z"
12555 Add Cess @ 1% on "Z" 5.43
12572 Add Cess @ 1% on "Z"
12587 Add Cess @ 1% on "Z"
12613 Add Cess @ 1% on "Z" 5.43
12633 Add Cess @ 1% on "Z"
12657 Add Cess @ 1% on "Z"
12673 Add Cess @ 1% on "Z"
12699 Add Cess @ 1% on "Z" 1.74
12715 Add Cess @ 1% on "Z"
12731 Add Cess @ 1% on "Z"
12764 Add Cess @ 1% on "Z"
12780 Add Cess @ 1% on "Z"
12804 Add Cess @ 1% on "Z"
12820 Add Cess @ 1% on "Z"
12846 Add Cess @ 1% on "Z" 1.54
12862 Add Cess @ 1% on "Z"
12894 Add Cess @ 1% on "Z" 1.96
12911 Add Cess @ 1% on "Z"
12926 Add Cess @ 1% on "Z"
12953 Add Cess @ 1% on "Z" 3.8
12970 Add Cess @ 1% on "Z" 4.57
12997 Add Cess @ 1% on "Z" 2.37
13017 Add Cess @ 1% on "Z"
13043 Add Cess @ 1% on "Z" 3.06
13059 Add Cess @ 1% on "Z"
13075 Add Cess @ 1% on "Z"
13101 Add Cess @ 1% on "Z"
13117 Add Cess @ 1% on "Z"
13147 Add Cess @ 1% on "Z" 2.37
13164 Add Cess @ 1% on "Z"
13190 Add Cess @ 1% on "Z" 3.62
13207 Add Cess @ 1% on "Z"
13224 Add Cess @ 1% on "Z"
13252 Add Cess @ 1% on "Z"
13269 Add Cess @ 1% on "Z"
13297 Add Cess @ 1% on "Z" 9.05
13314 Add Cess @ 1% on "Z"
13341 Add Cess @ 1% on "Z" 9.05
13358 Add Cess @ 1% on "Z"
13375 Add Cess @ 1% on "Z"
13402 Add Cess @ 1% on "Z"
13419 Add Cess @ 1% on "Z" 11.75
13447 Add Cess @ 1% on "Z" 11.75
13468 Add Cess @ 1% on "Z"
13485 Add Cess @ 1% on "Z"
13512 Add Cess @ 1% on "Z"
13529 Add Cess @ 1% on "Z"
13555 Add Cess @ 1% on "Z" 3.62
13572 Add Cess @ 1% on "Z"
13599 Add Cess @ 1% on "Z" 5.79
13616 Add Cess @ 1% on "Z"
13633 Add Cess @ 1% on "Z"
13662 Add Cess @ 1% on "Z"
13679 Add Cess @ 1% on "Z"
13707 Add Cess @ 1% on "Z" 9.05
13724 Add Cess @ 1% on "Z"
13741 Add Cess @ 1% on "Z"
13768 Add Cess @ 1% on "Z"
13785 Add Cess @ 1% on "Z"
13812 Add Cess @ 1% on "Z" 11.75
13829 Add Cess @ 1% on "Z"
13857 Add Cess @ 1% on "Z" 11.75
13874 Add Cess @ 1% on "Z"
13891 Add Cess @ 1% on "Z"
13923 Add Cess @ 1% on "Z"
13940 Add Cess @ 1% on "Z"
13966 Add Cess @ 1% on "Z" 2.65
13983 Add Cess @ 1% on "Z"
14000 Add Cess @ 1% on "Z"
14025 Add Cess @ 1% on "Z"
14042 Add Cess @ 1% on "Z"
14069 Add Cess @ 1% on "Z" 5.79
14086 Add Cess @ 1% on "Z"
14103 Add Cess @ 1% on "Z"
14130 Add Cess @ 1% on "Z"
14147 Add Cess @ 1% on "Z"
14174 Add Cess @ 1% on "Z" 9.05
14191 Add Cess @ 1% on "Z"
14219 Add Cess @ 1% on "Z" 9.05
14236 Add Cess @ 1% on "Z"
14255 Add Cess @ 1% on "Z"
14282 Add Cess @ 1% on "Z"
14299 Add Cess @ 1% on "Z"
14326 Add Cess @ 1% on "Z" 11.75
14343 Add Cess @ 1% on "Z"
14374 Add Cess @ 1% on "Z" 2.52
14392 Add Cess @ 1% on "Z"
14411 Add Cess @ 1% on "Z"
14438 Add Cess @ 1% on "Z"
14457 Add Cess @ 1% on "Z"
14485 Add Cess @ 1% on "Z" 4.46
14503 Add Cess @ 1% on "Z" 5.42
14532 Add Cess @ 1% on "Z" 7.13
14550 Add Cess @ 1% on "Z" 7.63
14568 Add Cess @ 1% on "Z" 9.02
14597 Add Cess @ 1% on "Z" 11.1
14615 Add Cess @ 1% on "Z"
14645 Add Cess @ 1% on "Z" 2.56
14663 Add Cess @ 1% on "Z"
14689 Add Cess @ 1% on "Z" 3.29
14707 Add Cess @ 1% on "Z"
14736 Add Cess @ 1% on "Z" 4.24
14753 Add Cess @ 1% on "Z" 6.11
14770 Add Cess @ 1% on "Z" 7.48
14796 Add Cess @ 1% on "Z"
14813 Add Cess @ 1% on "Z" 9.62
14840 Add Cess @ 1% on "Z" 11.13
14857 Add Cess @ 1% on "Z" 15.07
14888 Add Cess @ 1% on "Z" 3.1
14905 Add Cess @ 1% on "Z"
14922 Add Cess @ 1% on "Z"
14950 Add Cess @ 1% on "Z"
14967 Add Cess @ 1% on "Z"
14994 Add Cess @ 1% on "Z" 11.59
15011 Add Cess @ 1% on "Z"
15041 Add Cess @ 1% on "Z" 1.99
15058 Add Cess @ 1% on "Z"
15082 Add Cess @ 1% on "Z" 2.53
15099 Add Cess @ 1% on "Z" 2.72
15116 Add Cess @ 1% on "Z" 3.8
15144 Add Cess @ 1% on "Z"
15161 Add Cess @ 1% on "Z" 6.33
15189 Add Cess @ 1% on "Z" 9.05
15206 Add Cess @ 1% on "Z" 9.05
15247 Add Cess @ 1% on "Z" 2.53
15449 Add Cess @ 1% on "Z" 3.8
15513 Add Cess @ 1% on "Z" 6.33
15597 Add Cess @ 1% on "Z"
15611 Add Cess @ 1% on "Z"
15636 Add Cess @ 1% on "Z"
15650 Add Cess @ 1% on "Z"
15674 Add Cess @ 1% on "Z"
15688 Add Cess @ 1% on "Z"
15708 Add Cess @ 1% on "Z"
15736 Add Cess @ 1% on "Z"
15751 Add Cess @ 1% on "Z"
15813 Add Cess @ 1% on "Z"
15857 Add Cess @ 1% on "Z"
15899 Add Cess @ 1% on "Z"
15944 Add Cess @ 1% on "Z"
15988 Add Cess @ 1% on "Z" 433.98
16668 Add Cess @ 1% on "Z"
16695 Add Cess @ 1% on "Z" 4
16714 Add Cess @ 1% on "Z"
16732 Add Cess @ 1% on "Z"
16759 Add Cess @ 1% on "Z"
16777 Add Cess @ 1% on "Z"
16803 Add Cess @ 1% on "Z"
16821 Add Cess @ 1% on "Z"
16867 Add Cess @ 1% on "Z"
16911 Add Cess @ 1% on "Z"
17051 Add Cess @ 1% on "Z" 76.69
17085 Add Cess @ 1% on "Z"
17128 Add Cess @ 1% on "Z"
17172 Add Cess @ 1% on "Z"
17217 Add Cess @ 1% on "Z"
17260 Add Cess @ 1% on "Z"
17304 Add Cess @ 1% on "Z"
17336 Add Cess @ 1% on "Z"
17382 Add Cess @ 1% on "Z"
17426 Add Cess @ 1% on "Z"
19139 Add Cess @ 1% on "Z"
19171 Add Cess @ 1% on "Z"
19193 Add Cess @ 1% on "Z"
19460 Add Cess @ 1% on "Z"
21189 Add Cess @ 1% on "Z" 3.2
21217 Add Cess @ 1% on "Z"
21255 Add Cess @ 1% on "Z"
21294 Add Cess @ 1% on "Z"
21330 Add Cess @ 1% on "Z" 448.98
21358 Add Cess @ 1% on "Z"
21394 Add Cess @ 1% on "Z"
21433 Add Cess @ 1% on "Z" 1338.53
21463 Add Cess @ 1% on "Z"
21609 Add Cess @ 1% on "Z"
21637 Add Cess @ 1% on "Z"
21675 Add Cess @ 1% on "Z"
21712 Add Cess @ 1% on "Z"
23061 Add Cess @ 1% on "Z"
23106 Add Cess @ 1% on "Z"
23122 Add Cess @ 1% on "Z"
23152 Add Cess @ 1% on "Z"
23169 Add Cess @ 1% on "Z" 390.78
23199 Add Cess @ 1% on "Z"
23215 Add Cess @ 1% on "Z"
23263 Add Cess @ 1% on "Z" 198.7
23280 Add Cess @ 1% on "Z" 312.63
23316 Add
Add Cess
extra@ 1% on "Z"
concreting
17980 1x(0.56+0.79)x
Add extra concreting
18079 1x(0.56+0.79)x
5596 9999 Add for delay L.S. 13.52 2
5628 9999 Add for delay L.S. 13.52 2
5650 9999 Add for delay L.S. 20.28 2
5682 9999 Add for delay L.S. 20.28 2
5702 9999 Add for delay L.S. 26.91 2
5732 9999 Add for delay L.S. 26.91 2
5897 9999 Add for delay L.S. 8.06 2
5915 9999 Add for delay L.S. 8.06 2
5943 9999 Add for delay L.S. 10.79 2
5961 9999 Add for delay L.S. 10.79 2
5979 9999 Add for delay L.S. 12.22 2
6006 9999 Add for delay L.S. 12.22 2
6024 9999 Add for delay L.S. 13.52 2
6053 9999 Add for delay L.S. 14.82 2
10328 9999 Add for delay L.S. 16.12 2
5753 Add for delay L.S. 8.06 2
5781 Add for delay L.S. 8.06 2
5800 Add for delay L.S. 10.79 2
5819 Add for delay L.S. 10.92 2
5848 Add for delay L.S. 13.52 2
5867 Add for delay L.S. 13.52 2
10374 Add
Add for
for delay
delay sundries L.S. 40.3 2
19501 etc.
9999 Add for delay sundries L.S. 20.15 2
19548 9999 etc.
Add for delay sundries L.S. 20.67 2
19592 9999 etc.
Add GST (multiplying L.S. 26.91 2
221 factor
Add GST0.1405) on "X-A"
(multiplying 1718.01
256 factor
Add 0.1405)
GST on "X-A"
(multiplying 2000.81
290 factor 0.1405) on "X-A"
Add GST (multiplying 2566.41 360.58
316 factor
Add GST0.1405) on "X-A"
(multiplying 3397.13
708 factor 0.1405) on "X-A" 1386.96
Add GST (multiplying
742 factor
Add GST0.1405) on "X-A"
(multiplying 1802.85
767 factor
Add GST0.1405) on "X-A"
(multiplying 2250.33
1655 factor 0.1405) on "X-A"
Add GST (multiplying 1480.28
1682 factor
Add GST0.1405) on "X-A"
(multiplying 1997.27
1719 factor
Add GST0.1405) on "X-A"
(multiplying 2630.04
1756 factor
Add GST0.1405) on "X-A"
(multiplying 3514.67
2326 factor 0.1405) on "X-A"
Add GST (multiplying 1696.75
2370 factor
Add GST0.1405) on "X-A"
(multiplying 2033.98
3579 factor
Add GST0.1405) on "X-A"
(multiplying 3645.53
3600 factor
Add GST0.1405) on "X-A"
(multiplying 3746.53
3635 factor 0.1405) on "X-A"
Add GST (multiplying 5564.53
3656 factor
Add GST0.1405) on "X-A"
(multiplying 5564.53
3692 factor
Add GST0.1405) on "X-A"
(multiplying 8679.13
3727 factor
Add 0.1405)
GST on "X-A"
(multiplying 10808 1518.52
3752 factor 0.1405) on "X-A"
Add GST (multiplying 13027.65
3788 factor
Add GST0.1405) on "X-A"
(multiplying 22182.52
3813 factor
Add GST0.1405) on "X-A"
(multiplying 28945.97
3849 factor
Add 0.1405)
GST on "X-A"
(multiplying 39067.27
3885 factor 0.1405) on "X-A"
Add GST (multiplying 46808.1
3911 factor
Add GST0.1405) on "X-A"
(multiplying 61772.5
3949 factor
Add GST0.1405) on "X-A"
(multiplying 74808.43
3985 factor
Add 0.1405)
GST on "X-A"
(multiplying 86827.43 12199.25
4012 factor 0.1405) on "X-A"
Add GST (multiplying 121540
4770 factor
Add GST0.1405) on "X-A"
(multiplying 24382.92
4806 factor
Add GST0.1405) on "X-A"
(multiplying 27323.36
4832 factor
Add 0.1405)
GST on "X-A"
(multiplying 26313.36
4867 factor 0.1405) on "X-A"
Add GST (multiplying 32384.79
4905 factor
Add GST0.1405) on "X-A"
(multiplying 36428.6
4930 factor
Add GST0.1405) on "X-A"
(multiplying 40482.42
4968 factor
Add 0.1405)
GST on "X-A"
(multiplying 75866.24
5003 factor 0.1405) on "X-A"
Add GST (multiplying 90032.92
5030 factor
Add GST0.1405) on "X-A"
(multiplying 111069.51 15605.27
5065 factor
Add GST0.1405) on "X-A"
(multiplying 146669.15 20607.02
5102 factor 0.1405) on "X-A"
Add GST (multiplying 156780.58 22027.67
5127 factor
Add GST0.1405) on "X-A"
(multiplying 184108.7 25867.27
5201 factor
Add GST0.1405) on "X-A"
(multiplying 125.23
5273 factor
Add GST0.1405) on "X-A"
(multiplying 140.97
5343 factor 0.1405) on "X-A"
Add GST (multiplying 79.4
5426 factor
Add GST0.1405) on "X-A"
(multiplying -4.85
5496 factor
Add GST0.1405) on "X-A"
(multiplying 259.33
5578 factor
Add GST0.1405) on "X-A"
(multiplying 163.24
5600 factor
Add 0.1405)
GST on "X-A"
(multiplying 27.31
5632 factor 0.1405) on "X-A"
Add GST (multiplying 27.31
5654 factor
Add GST0.1405) on "X-A"
(multiplying 40.97
5686 factor 0.1405) on "X-A" 40.97
Add GST (multiplying
5706 factor
Add GST0.1405) on "X-A"
(multiplying 54.36
5736 factor
Add GST0.1405) on "X-A"
(multiplying 54.36
5757 factor 0.1405) on "X-A"
Add GST (multiplying 16.28
5785 factor
Add GST0.1405) on "X-A"
(multiplying 16.28
5804 factor
Add GST0.1405) on "X-A"
(multiplying 21.8
5833 factor
Add GST0.1405) on "X-A"
(multiplying 22.06 3.1
5852 factor 0.1405) on "X-A"
Add GST (multiplying 27.31
5871 factor
Add GST0.1405) on "X-A"
(multiplying 27.31
5901 factor
Add GST0.1405) on "X-A"
(multiplying 16.28
5919 factor
Add GST0.1405) on "X-A"
(multiplying 16.28
5947 factor 0.1405) on "X-A"
Add GST (multiplying 21.8
5965 factor
Add GST0.1405) on "X-A"
(multiplying 21.8
5992 factor
Add GST0.1405) on "X-A"
(multiplying 24.68 3.47
6010 factor
Add 0.1405)
GST on "X-A"
(multiplying 24.68
6028 factor 0.1405) on "X-A"
Add GST (multiplying 27.31
6057 factor
Add GST0.1405) on "X-A"
(multiplying 29.94
7535 factor
Add GST0.1405) on "X-A"
(multiplying 37652.8
7568 factor
Add 0.1405)
GST on "X-A"
(multiplying 45833.8
7591 factor 0.1405) on "X-A"
Add GST (multiplying 59848.56
7627 factor
Add GST0.1405) on "X-A"
(multiplying 2444.2
7650 factor
Add GST0.1405) on "X-A"
(multiplying 3594.59
7683 factor
Add 0.1405)
GST on "X-A"
(multiplying 5337.85
7706 factor 0.1405) on "X-A"
Add GST (multiplying 5826.69
7738 factor
Add GST0.1405) on "X-A"
(multiplying 2838.1
7759 factor
Add GST0.1405) on "X-A"
(multiplying 4571.26
7789 factor
Add 0.1405)
GST on "X-A"
(multiplying 5805.48
7810 factor 0.1405) on "X-A"
Add GST (multiplying 8253.72
8047 factor
Add GST0.1405) on "X-A"
(multiplying 6271.53
8079 factor
Add GST0.1405) on "X-A"
(multiplying 8666.24
8099 factor
Add 0.1405)
GST on "X-A"
(multiplying 9148.01
8129 factor 0.1405) on "X-A"
Add GST (multiplying 12533.53
8146 factor
Add GST0.1405) on "X-A"
(multiplying 17381.53
8177 factor
Add GST0.1405) on "X-A"
(multiplying 13190.03
8194 factor 0.1405) on "X-A"
Add GST (multiplying 18947.03
8641 factor
Add GST0.1405) on "X-A"
(multiplying 6627.21
8666 factor
Add GST0.1405) on "X-A"
(multiplying 10361.92
8701 factor
Add GST0.1405) on "X-A"
(multiplying 16383.66
8728 factor 0.1405) on "X-A"
Add GST (multiplying 19765.38
8764 factor
Add GST0.1405) on "X-A"
(multiplying 25255.29
8799 factor
Add GST0.1405) on "X-A"
(multiplying 31822.4
8824 factor
Add GST0.1405) on "X-A"
(multiplying 41228.65
8861 factor
Add 0.1405)
GST on "X-A"
(multiplying 52554.22
8895 factor 0.1405) on "X-A"
Add GST (multiplying 65345.87
8920 factor
Add GST0.1405) on "X-A"
(multiplying 90615.5
8957 factor 0.1405) on "X-A" 8103.43
Add GST (multiplying
8981 factor
Add GST0.1405) on "X-A"
(multiplying 11553.05
9015 factor
Add GST0.1405) on "X-A"
(multiplying 14203.52
9039 factor 0.1405) on "X-A"
Add GST (multiplying 18270.27
9074 factor
Add GST0.1405) on "X-A"
(multiplying 22836.57
9109 factor
Add GST0.1405) on "X-A"
(multiplying 26921.2 3782.43
9133 factor
Add GST0.1405) on "X-A"
(multiplying 32280.5
9169 factor 0.1405) on "X-A"
Add GST (multiplying 39165.53
9194 factor
Add GST0.1405) on "X-A"
(multiplying 44195.33
9229 factor
Add GST0.1405) on "X-A"
(multiplying 56950.5
9265 factor
Add GST0.1405) on "X-A"
(multiplying 74120.5
9290 factor 0.1405) on "X-A"
Add GST (multiplying 92300.5
9324 factor
Add GST0.1405) on "X-A"
(multiplying 119765.75 16827.09
9349 factor
Add GST0.1405) on "X-A"
(multiplying 125010.99
9382 factor
Add 0.1405)
GST on "X-A"
(multiplying 7749.93
9408 factor 0.1405) on "X-A"
Add GST (multiplying 11654.05
9443 factor
Add GST0.1405) on "X-A"
(multiplying 15971.02
9478 factor
Add GST0.1405) on "X-A"
(multiplying 22310.27 3134.59
9504 factor
Add 0.1405)
GST on "X-A"
(multiplying 27886.57
9540 factor 0.1405) on "X-A"
Add GST (multiplying 33991.2
9566 factor
Add GST0.1405) on "X-A"
(multiplying 43643
9602 factor
Add GST0.1405) on "X-A"
(multiplying 50760.33
9639 factor
Add 0.1405)
GST on "X-A"
(multiplying 63587.33 8934.02
9666 factor 0.1405) on "X-A"
Add GST (multiplying 76746.5
9701 factor
Add GST0.1405) on "X-A"
(multiplying 106310.33 14936.6
9726 factor
Add GST0.1405) on "X-A"
(multiplying 115220.75
9761 factor
Add 0.1405)
GST on "X-A"
(multiplying 116425.99
9796 factor 0.1405) on "X-A"
Add GST (multiplying 141170.99 19834.52
9821 factor
Add GST0.1405) on "X-A"
(multiplying 157835.99
9859 factor
Add GST0.1405) on "X-A"
(multiplying 5566.71
9885 factor
Add 0.1405)
GST on "X-A"
(multiplying 8352.02
9921 factor 0.1405) on "X-A"
Add GST (multiplying 10510.51
9956 factor
Add GST0.1405) on "X-A"
(multiplying 14942.63
9982 factor
Add GST0.1405) on "X-A"
(multiplying 19195.29
10018 factor 0.1405) on "X-A"
Add GST (multiplying 24217.1
10054 factor
Add GST0.1405) on "X-A"
(multiplying 31164
10078 factor
Add GST0.1405) on "X-A"
(multiplying 32717.82
10114 factor
Add GST0.1405) on "X-A"
(multiplying 46489.17
10140 factor 0.1405) on "X-A"
Add GST (multiplying 61552.75
10174 factor
Add GST0.1405) on "X-A"
(multiplying 72698.67
10333 factor
Add GST0.1405) on "X-A"
(multiplying 591.33
10379 factor
Add GST0.1405) on "X-A"
(multiplying 1623.86
10415 factor
Add 0.1405)
GST on "X-A"
(multiplying 538.79
10437 factor 0.1405) on "X-A"
Add GST (multiplying 27.31
11151 factor
Add GST0.1405) on "X-A"
(multiplying 1801.5
11192 factor 0.1405) on "X-A" 2059.65
Add GST (multiplying
11232 factor
Add GST0.1405) on "X-A"
(multiplying 2323.57
11263 factor
Add GST0.1405) on "X-A"
(multiplying 2609.28
11305 factor 0.1405) on "X-A"
Add GST (multiplying 3120.54
11345 factor
Add GST0.1405) on "X-A"
(multiplying 3660.6
11374 factor
Add GST0.1405) on "X-A"
(multiplying 4153.92
11416 factor
Add GST0.1405) on "X-A"
(multiplying 4646.8
11457 factor 0.1405) on "X-A"
Add GST (multiplying 5158.55
11498 factor
Add GST0.1405) on "X-A"
(multiplying 5671.07
11529 factor
Add GST0.1405) on "X-A"
(multiplying 6182.32
11570 factor
Add GST0.1405) on "X-A"
(multiplying 7207.09
12119 factor 0.1405) on "X-A"
Add GST (multiplying 2001.09
12159 factor
Add GST0.1405) on "X-A"
(multiplying 3199.68
16367 factor
Add GST0.1405) on "X-A"
(multiplying 632.48
16419 factor
Add 0.1405)
GST on "X-A"
(multiplying 632.48 88.86
16478 factor 0.1405) on "X-A"
Add GST (multiplying 677.12 95.14
16533 factor
Add GST0.1405) on "X-A"
(multiplying 677.12 95.14
16589 factor
Add GST0.1405) on "X-A"
(multiplying 783.76 110.12
16634 factor
Add 0.1405)
GST on "X-A"
(multiplying 783.76
17676 factor 0.1405) on "X-A"
Add GST (multiplying 1387.31 194.92
17758 factor
Add GST0.1405) on "X-A"
(multiplying 4385.7
17917 factor
Add GST0.1405) on "X-A"
(multiplying 4385.7
18017 factor
Add 0.1405)
GST on "X-A"
(multiplying 9039.75 1270.08
18117 factor 0.1405) on "X-A"
Add GST (multiplying 9039.75 1270.08
18304 factor
Add GST0.1405) on "X-A"
(multiplying 988.4
18402 factor
Add GST0.1405) on "X-A"
(multiplying 988.4
18553 factor
Add 0.1405)
GST on "X-A"
(multiplying 1022.76 143.7
18646 factor 0.1405) on "X-A"
Add GST (multiplying 1022.76
18783 factor
Add GST0.1405) on "X-A"
(multiplying 1022.76
18868 factor
Add GST0.1405) on "X-A"
(multiplying 1022.76
18951 factor
Add 0.1405)
GST on "X-A"
(multiplying 216.37 30.4
18983 factor 0.1405) on "X-A"
Add GST (multiplying 187.28
19021 factor
Add GST0.1405) on "X-A"
(multiplying 216.24
19066 factor
Add GST0.1405) on "X-A"
(multiplying 258.34
19109 factor 0.1405) on "X-A"
Add GST (multiplying 229.25
19228 factor
Add GST0.1405) on "X-A"
(multiplying 722.72
19264 factor
Add GST0.1405) on "X-A"
(multiplying 621.72
19290 factor
Add GST0.1405) on "X-A"
(multiplying 621.72
19331 factor 0.1405) on "X-A"
Add GST (multiplying 723.97
19356 factor
Add GST0.1405) on "X-A"
(multiplying 628.02
19395 factor
Add GST0.1405) on "X-A"
(multiplying 957.08
19434 factor
Add GST0.1405) on "X-A"
(multiplying 1249.98
19505 factor
Add 0.1405)
GST on "X-A"
(multiplying 224.79
19552 factor 0.1405) on "X-A"
Add GST (multiplying 225.84
19596 factor
Add GST0.1405) on "X-A"
(multiplying 298.73
19674 factor 0.1405) on "X-A" 2907.57
Add GST (multiplying
19810 factor
Add GST0.1405) on "X-A"
(multiplying 725.68
19859 factor
Add GST0.1405) on "X-A"
(multiplying 1084.49
19921 factor 0.1405) on "X-A"
Add GST (multiplying 14.44
19976 factor
Add GST0.1405) on "X-A"
(multiplying 14.44
20043 factor
Add GST0.1405) on "X-A"
(multiplying 30.72
20110 factor
Add GST0.1405) on "X-A"
(multiplying 30.72
20145 factor 0.1405) on "X-A"
Add GST (multiplying 3.68
20166 factor
Add GST0.1405) on "X-A"
(multiplying 3.68
20310 factor
Add GST0.1405) on "X-A"
(multiplying 30.78
20365 factor
Add GST0.1405) on "X-A"
(multiplying 41.75 5.87
20405 factor 0.1405) on "X-A"
Add GST (multiplying 48.06
20454 factor
Add GST0.1405) on "X-A"
(multiplying 55.41
20501 factor
Add GST0.1405) on "X-A"
(multiplying 57.25
20554 factor
Add 0.1405)
GST on "X-A"
(multiplying 651.41
20628 factor 0.1405) on "X-A"
Add GST (multiplying 242.49
20723 factor
Add GST0.1405) on "X-A"
(multiplying 910.18
20805 factor
Add GST0.1405) on "X-A"
(multiplying 1470.2
20876 factor
Add 0.1405)
GST on "X-A"
(multiplying 1392.43
20949 factor 0.1405) on "X-A"
Add GST (multiplying 1366.5
21099 factor
Add GST0.1405) on "X-A"
(multiplying 13566.01 1906.02
21144 factor
Add GST0.1405) on "X-A"
(multiplying 1340.48
21791 factor
Add 0.1405)
GST on "X-A"
(multiplying 18227.37
21829 factor 0.1405) on "X-A"
Add GST (multiplying 21604.04
21869 factor
Add GST0.1405) on "X-A"
(multiplying 25517.39
21908 factor
Add GST0.1405) on "X-A"
(multiplying 25197.99
21939 factor
Add 0.1405)
GST on "X-A"
(multiplying 29150.3
21977 factor 0.1405) on "X-A"
Add GST (multiplying 29371.06
22015 factor
Add GST0.1405) on "X-A"
(multiplying 28907.37
22053 factor
Add GST0.1405) on "X-A"
(multiplying 32998.02
22099 factor
Add 0.1405)
GST on "X-A"
(multiplying 7440.24
22140 factor 0.1405) on "X-A"
Add GST (multiplying 7740.53
22212 factor
Add GST0.1405) on "X-A"
(multiplying 9913.86
22324 factor
Add GST0.1405) on "X-A"
(multiplying 28937.78
22363 factor 0.1405) on "X-A"
Add GST (multiplying 28437.26
22400 factor
Add GST0.1405) on "X-A"
(multiplying 29221.58
22441 factor
Add GST0.1405) on "X-A"
(multiplying 29800.65
22558 factor
Add GST0.1405) on "X-A"
(multiplying 12854.65
22599 factor 0.1405) on "X-A"
Add GST (multiplying 12808.58
22639 factor
Add GST0.1405) on "X-A"
(multiplying 12865.42
22681 factor
Add GST0.1405) on "X-A"
(multiplying 1014.27
22716 factor
Add GST0.1405) on "X-A"
(multiplying 1023.24
22742 factor
Add 0.1405)
GST on "X-A"
(multiplying 1029.22
22777 factor 0.1405) on "X-A"
Add GST (multiplying 1070.55
22825 factor
Add GST0.1405) on "X-A"
(multiplying 19389.35
22868 factor 0.1405) on "X-A" 22371.9
Add GST (multiplying
22909 factor
Add GST0.1405) on "X-A"
(multiplying 19389.35
22948 factor
Add GST0.1405) on "X-A"
(multiplying 19389.35
23024 factor 0.1405) on "X-A"
Add GST (multiplying 19389.35
27 factor
Add GST0.1405) on "X"
(multiplying
61 factor
Add GST0.1405) on "X"
(multiplying
85 factor
Add GST0.1405) on "X"
(multiplying
120 factor 0.1405) on "X"
Add GST (multiplying
157 factor
Add GST0.1405) on "X"
(multiplying
181 factor
Add GST0.1405) on "X"
(multiplying
363 factor
Add GST0.1405) on "X"
(multiplying
397 factor 0.1405) on "X"
Add GST (multiplying
422 factor
Add GST0.1405) on "X"
(multiplying
457 factor
Add GST0.1405) on "X"
(multiplying
492 factor
Add 0.1405)
GST on "X"
(multiplying
517 factor 0.1405) on "X"
Add GST (multiplying
552 factor
Add GST0.1405) on "X"
(multiplying
575 factor
Add GST0.1405) on "X"
(multiplying
608 factor
Add 0.1405)
GST on "X"
(multiplying
643 factor 0.1405) on "X"
Add GST (multiplying
667 factor
Add GST0.1405) on "X"
(multiplying
809 factor
Add GST0.1405) on "X"
(multiplying
847 factor
Add 0.1405)
GST on "X"
(multiplying
875 factor 0.1405) on "X"
Add GST (multiplying
914 factor
Add GST0.1405) on "X"
(multiplying
952 factor
Add GST0.1405) on "X"
(multiplying
980 factor
Add 0.1405)
GST on "X"
(multiplying
1013 factor 0.1405) on "X"
Add GST (multiplying
1052 factor
Add GST0.1405) on "X"
(multiplying 1159.68
1081 factor
Add GST0.1405) on "X"
(multiplying
1336 factor
Add 0.1405)
GST on "X"
(multiplying
1403 factor 0.1405) on "X"
Add GST (multiplying
1421 factor
Add GST0.1405) on "X"
(multiplying
1458 factor
Add GST0.1405) on "X"
(multiplying
1494 factor 0.1405) on "X"
Add GST (multiplying 248.72
1519 factor
Add GST0.1405) on "X"
(multiplying
1554 factor
Add GST0.1405) on "X"
(multiplying
1579 factor
Add GST0.1405) on "X"
(multiplying
1614 factor 0.1405) on "X"
Add GST (multiplying
1798 factor
Add GST0.1405) on "X"
(multiplying 162.35
1824 factor
Add GST0.1405) on "X"
(multiplying
1858 factor
Add GST0.1405) on "X"
(multiplying
1884 factor
Add 0.1405)
GST on "X"
(multiplying
1921 factor 0.1405) on "X"
Add GST (multiplying
1956 factor
Add GST0.1405) on "X"
(multiplying 778.18
1982 factor 0.1405) on "X"
Add GST (multiplying
2019 factor
Add GST0.1405) on "X"
(multiplying
2055 factor
Add GST0.1405) on "X"
(multiplying 2847.81
2081 factor 0.1405) on "X"
Add GST (multiplying
2123 factor
Add GST0.1405) on "X"
(multiplying
2149 factor
Add GST0.1405) on "X"
(multiplying
2186 factor
Add GST0.1405) on "X"
(multiplying
2221 factor 0.1405) on "X"
Add GST (multiplying
2248 factor
Add GST0.1405) on "X"
(multiplying
2285 factor
Add GST0.1405) on "X"
(multiplying
2401 factor
Add GST0.1405) on "X"
(multiplying
2438 factor 0.1405) on "X"
Add GST (multiplying
2475 factor
Add GST0.1405) on "X"
(multiplying
2503 factor
Add GST0.1405) on "X"
(multiplying
2538 factor
Add 0.1405)
GST on "X"
(multiplying
2574 factor 0.1405) on "X"
Add GST (multiplying
2602 factor
Add GST0.1405) on "X"
(multiplying
2639 factor
Add GST0.1405) on "X"
(multiplying
2673 factor
Add 0.1405)
GST on "X"
(multiplying 48.05
2695 factor 0.1405) on "X"
Add GST (multiplying
2724 factor
Add GST0.1405) on "X"
(multiplying
2743 factor
Add GST0.1405) on "X"
(multiplying
2760 factor
Add 0.1405)
GST on "X"
(multiplying
2789 factor 0.1405) on "X"
Add GST (multiplying
2806 factor
Add GST0.1405) on "X"
(multiplying
2836 factor
Add GST0.1405) on "X"
(multiplying
2851 factor
Add 0.1405)
GST on "X"
(multiplying
2880 factor 0.1405) on "X"
Add GST (multiplying 61.65
2898 factor
Add GST0.1405) on "X"
(multiplying
2916 factor
Add GST0.1405) on "X"
(multiplying
2944 factor
Add 0.1405)
GST on "X"
(multiplying
2962 factor 0.1405) on "X"
Add GST (multiplying
2992 factor
Add GST0.1405) on "X"
(multiplying 35.92
3010 factor
Add GST0.1405) on "X"
(multiplying
3028 factor 0.1405) on "X"
Add GST (multiplying
3058 factor
Add GST0.1405) on "X"
(multiplying
3074 factor
Add GST0.1405) on "X"
(multiplying
3102 factor
Add GST0.1405) on "X"
(multiplying
3118 factor 0.1405) on "X"
Add GST (multiplying
3146 factor
Add GST0.1405) on "X"
(multiplying
3162 factor
Add GST0.1405) on "X"
(multiplying
3188 factor
Add GST0.1405) on "X"
(multiplying
3204 factor
Add 0.1405)
GST on "X"
(multiplying
3230 factor 0.1405) on "X"
Add GST (multiplying
3246 factor
Add GST0.1405) on "X"
(multiplying
3266 factor 0.1405) on "X"
Add GST (multiplying
3291 factor
Add GST0.1405) on "X"
(multiplying
3310 factor
Add GST0.1405) on "X"
(multiplying
3336 factor 0.1405) on "X"
Add GST (multiplying
3353 factor
Add GST0.1405) on "X"
(multiplying
3383 factor
Add GST0.1405) on "X"
(multiplying
3399 factor
Add GST0.1405) on "X"
(multiplying
3429 factor 0.1405) on "X"
Add GST (multiplying
3445 factor
Add GST0.1405) on "X"
(multiplying
3475 factor
Add GST0.1405) on "X"
(multiplying 16.11
3493 factor
Add GST0.1405) on "X"
(multiplying
3524 factor 0.1405) on "X"
Add GST (multiplying
3545 factor
Add GST0.1405) on "X"
(multiplying
4048 factor
Add GST0.1405) on "X"
(multiplying
4074 factor
Add 0.1405)
GST on "X"
(multiplying
4109 factor 0.1405) on "X"
Add GST (multiplying
4144 factor
Add GST0.1405) on "X"
(multiplying
4170 factor
Add GST0.1405) on "X"
(multiplying
4206 factor
Add 0.1405)
GST on "X"
(multiplying
4243 factor 0.1405) on "X"
Add GST (multiplying
4269 factor
Add GST0.1405) on "X"
(multiplying
4304 factor
Add GST0.1405) on "X"
(multiplying
4339 factor
Add 0.1405)
GST on "X"
(multiplying
4365 factor 0.1405) on "X"
Add GST (multiplying
4392 factor
Add GST0.1405) on "X"
(multiplying
4416 factor
Add GST0.1405) on "X"
(multiplying
4448 factor
Add 0.1405)
GST on "X"
(multiplying
4471 factor 0.1405) on "X"
Add GST (multiplying
4504 factor
Add GST0.1405) on "X"
(multiplying
4527 factor
Add GST0.1405) on "X"
(multiplying
4560 factor
Add 0.1405)
GST on "X"
(multiplying
4594 factor 0.1405) on "X"
Add GST (multiplying 445.29
4617 factor
Add GST0.1405) on "X"
(multiplying
4650 factor
Add GST0.1405) on "X"
(multiplying
4673 factor 0.1405) on "X"
Add GST (multiplying
4706 factor
Add GST0.1405) on "X"
(multiplying
4729 factor
Add GST0.1405) on "X"
(multiplying
6106 factor
Add GST0.1405) on "X"
(multiplying
6348 factor 0.1405) on "X"
Add GST (multiplying
6380 factor
Add GST0.1405) on "X"
(multiplying
6405 factor
Add GST0.1405) on "X"
(multiplying
6436 factor
Add GST0.1405) on "X"
(multiplying
6472 factor
Add 0.1405)
GST on "X"
(multiplying
6494 factor 0.1405) on "X"
Add GST (multiplying
6526 factor
Add GST0.1405) on "X"
(multiplying
6546 factor 0.1405) on "X"
Add GST (multiplying
6575 factor
Add GST0.1405) on "X"
(multiplying
6595 factor
Add GST0.1405) on "X"
(multiplying
6624 factor 0.1405) on "X"
Add GST (multiplying
6644 factor
Add GST0.1405) on "X"
(multiplying
6673 factor
Add GST0.1405) on "X"
(multiplying 89
6693 factor
Add GST0.1405) on "X"
(multiplying
6725 factor 0.1405) on "X"
Add GST (multiplying
6745 factor
Add GST0.1405) on "X"
(multiplying
6774 factor
Add GST0.1405) on "X"
(multiplying
6794 factor
Add GST0.1405) on "X"
(multiplying
6823 factor 0.1405) on "X"
Add GST (multiplying
6843 factor
Add GST0.1405) on "X"
(multiplying
6873 factor
Add GST0.1405) on "X"
(multiplying
6893 factor
Add 0.1405)
GST on "X"
(multiplying
6926 factor 0.1405) on "X"
Add GST (multiplying
6948 factor
Add GST0.1405) on "X"
(multiplying
6980 factor
Add GST0.1405) on "X"
(multiplying
6999 factor
Add 0.1405)
GST on "X"
(multiplying
7028 factor 0.1405) on "X"
Add GST (multiplying
7047 factor
Add GST0.1405) on "X"
(multiplying
7074 factor
Add GST0.1405) on "X"
(multiplying
7090 factor
Add 0.1405)
GST on "X"
(multiplying
7278 factor 0.1405) on "X"
Add GST (multiplying
7297 factor
Add GST0.1405) on "X"
(multiplying
7324 factor
Add GST0.1405) on "X"
(multiplying
7344 factor
Add 0.1405)
GST on "X"
(multiplying
7373 factor 0.1405) on "X"
Add GST (multiplying
7390 factor
Add GST0.1405) on "X"
(multiplying
7419 factor
Add GST0.1405) on "X"
(multiplying 11.09
7436 factor
Add 0.1405)
GST on "X"
(multiplying
7455 factor 0.1405) on "X"
Add GST (multiplying
7480 factor
Add GST0.1405) on "X"
(multiplying
7502 factor
Add GST0.1405) on "X"
(multiplying
7839 factor 0.1405) on "X"
Add GST (multiplying
7857 factor
Add GST0.1405) on "X"
(multiplying
7886 factor
Add GST0.1405) on "X"
(multiplying
7904 factor
Add GST0.1405) on "X"
(multiplying
7933 factor 0.1405) on "X"
Add GST (multiplying
7953 factor
Add GST0.1405) on "X"
(multiplying
7980 factor
Add GST0.1405) on "X"
(multiplying
7997 factor
Add GST0.1405) on "X"
(multiplying
8027 factor
Add 0.1405)
GST on "X"
(multiplying 5251.43
8226 factor 0.1405) on "X"
Add GST (multiplying
8248 factor
Add GST0.1405) on "X"
(multiplying
8280 factor 0.1405) on "X"
Add GST (multiplying
8302 factor
Add GST0.1405) on "X"
(multiplying
8334 factor
Add GST0.1405) on "X"
(multiplying
8356 factor 0.1405) on "X"
Add GST (multiplying
8388 factor
Add GST0.1405) on "X"
(multiplying
8410 factor
Add GST0.1405) on "X"
(multiplying
8442 factor
Add GST0.1405) on "X"
(multiplying
8464 factor 0.1405) on "X"
Add GST (multiplying
8496 factor
Add GST0.1405) on "X"
(multiplying
8518 factor
Add GST0.1405) on "X"
(multiplying
8549 factor
Add GST0.1405) on "X"
(multiplying
8571 factor 0.1405) on "X"
Add GST (multiplying
8603 factor
Add GST0.1405) on "X"
(multiplying
10207 factor
Add GST0.1405) on "X"
(multiplying
10225 factor
Add 0.1405)
GST on "X"
(multiplying
10253 factor 0.1405) on "X"
Add GST (multiplying 5.22
10270 factor
Add GST0.1405) on "X"
(multiplying
10287 factor
Add GST0.1405) on "X"
(multiplying
10476 factor
Add 0.1405)
GST on "X"
(multiplying
10510 factor 0.1405) on "X"
Add GST (multiplying 114.67
10533 factor
Add GST0.1405) on "X"
(multiplying
10563 factor
Add GST0.1405) on "X"
(multiplying
10586 factor
Add 0.1405)
GST on "X"
(multiplying
10618 factor 0.1405) on "X"
Add GST (multiplying
10651 factor
Add GST0.1405) on "X"
(multiplying
10674 factor
Add GST0.1405) on "X"
(multiplying
10711 factor
Add 0.1405)
GST on "X"
(multiplying
10734 factor 0.1405) on "X"
Add GST (multiplying
10766 factor
Add GST0.1405) on "X"
(multiplying
10798 factor
Add GST0.1405) on "X"
(multiplying 574.6
10820 factor
Add 0.1405)
GST on "X"
(multiplying
10854 factor 0.1405) on "X"
Add GST (multiplying
10874 factor
Add GST0.1405) on "X"
(multiplying
10907 factor
Add GST0.1405) on "X"
(multiplying
10927 factor 0.1405) on "X"
Add GST (multiplying
10960 factor
Add GST0.1405) on "X"
(multiplying
10980 factor
Add GST0.1405) on "X"
(multiplying
11013 factor
Add GST0.1405) on "X"
(multiplying
11033 factor 0.1405) on "X"
Add GST (multiplying
11066 factor
Add GST0.1405) on "X"
(multiplying
11086 factor
Add GST0.1405) on "X"
(multiplying
11119 factor
Add GST0.1405) on "X"
(multiplying
11592 factor
Add 0.1405)
GST on "X"
(multiplying
11620 factor 0.1405) on "X"
Add GST (multiplying
11638 factor
Add GST0.1405) on "X"
(multiplying
11663 factor 0.1405) on "X"
Add GST (multiplying
11681 factor
Add GST0.1405) on "X"
(multiplying
11709 factor
Add GST0.1405) on "X"
(multiplying 30.56
11727 factor 0.1405) on "X"
Add GST (multiplying
11745 factor
Add GST0.1405) on "X"
(multiplying
11773 factor
Add GST0.1405) on "X"
(multiplying
11791 factor
Add GST0.1405) on "X"
(multiplying
11816 factor 0.1405) on "X"
Add GST (multiplying 60.85
11834 factor
Add GST0.1405) on "X"
(multiplying
11853 factor
Add GST0.1405) on "X"
(multiplying
11893 factor
Add GST0.1405) on "X"
(multiplying
11932 factor 0.1405) on "X"
Add GST (multiplying
11968 factor
Add GST0.1405) on "X"
(multiplying
11997 factor
Add GST0.1405) on "X"
(multiplying
12036 factor
Add 0.1405)
GST on "X"
(multiplying
12075 factor 0.1405) on "X"
Add GST (multiplying
12179 factor
Add GST0.1405) on "X"
(multiplying
12196 factor
Add GST0.1405) on "X"
(multiplying
12222 factor
Add 0.1405)
GST on "X"
(multiplying
12239 factor 0.1405) on "X"
Add GST (multiplying
12268 factor
Add GST0.1405) on "X"
(multiplying
12284 factor
Add GST0.1405) on "X"
(multiplying 25.54
12314 factor
Add 0.1405)
GST on "X"
(multiplying
12331 factor 0.1405) on "X"
Add GST (multiplying
12357 factor
Add GST0.1405) on "X"
(multiplying 20.58
12374 factor
Add GST0.1405) on "X"
(multiplying
12391 factor
Add 0.1405)
GST on "X"
(multiplying
12418 factor 0.1405) on "X"
Add GST (multiplying
12435 factor
Add GST0.1405) on "X"
(multiplying
12462 factor
Add GST0.1405) on "X"
(multiplying 51.37
12479 factor
Add 0.1405)
GST on "X"
(multiplying
12496 factor 0.1405) on "X"
Add GST (multiplying
12523 factor
Add GST0.1405) on "X"
(multiplying
12540 factor
Add GST0.1405) on "X"
(multiplying
12568 factor 0.1405) on "X"
Add GST (multiplying
12583 factor
Add GST0.1405) on "X"
(multiplying
12609 factor
Add GST0.1405) on "X"
(multiplying 58.18
12629 factor
Add GST0.1405) on "X"
(multiplying
12653 factor 0.1405) on "X"
Add GST (multiplying
12669 factor
Add GST0.1405) on "X"
(multiplying
12685 factor
Add GST0.1405) on "X"
(multiplying
12711 factor
Add GST0.1405) on "X"
(multiplying
12727 factor
Add 0.1405)
GST on "X"
(multiplying
12760 factor 0.1405) on "X"
Add GST (multiplying
12776 factor
Add GST0.1405) on "X"
(multiplying
12800 factor 0.1405) on "X"
Add GST (multiplying
12816 factor
Add GST0.1405) on "X"
(multiplying
12842 factor
Add GST0.1405) on "X"
(multiplying 16.46
12858 factor 0.1405) on "X"
Add GST (multiplying
12890 factor
Add GST0.1405) on "X"
(multiplying 21
12907 factor
Add GST0.1405) on "X"
(multiplying
12922 factor
Add GST0.1405) on "X"
(multiplying
12949 factor 0.1405) on "X"
Add GST (multiplying 40.73
12966 factor
Add GST0.1405) on "X"
(multiplying 48.96
12993 factor
Add GST0.1405) on "X"
(multiplying 25.4
13013 factor
Add GST0.1405) on "X"
(multiplying
13029 factor 0.1405) on "X"
Add GST (multiplying
13055 factor
Add GST0.1405) on "X"
(multiplying
13071 factor
Add GST0.1405) on "X"
(multiplying
13097 factor
Add 0.1405)
GST on "X"
(multiplying
13113 factor 0.1405) on "X"
Add GST (multiplying
13143 factor
Add GST0.1405) on "X"
(multiplying 25.4
13160 factor
Add GST0.1405) on "X"
(multiplying
13177 factor
Add 0.1405)
GST on "X"
(multiplying
13203 factor 0.1405) on "X"
Add GST (multiplying
13220 factor
Add GST0.1405) on "X"
(multiplying
13248 factor
Add GST0.1405) on "X"
(multiplying
13265 factor
Add 0.1405)
GST on "X"
(multiplying
13293 factor 0.1405) on "X"
Add GST (multiplying 96.92
13310 factor
Add GST0.1405) on "X"
(multiplying
13327 factor
Add GST0.1405) on "X"
(multiplying
13354 factor
Add 0.1405)
GST on "X"
(multiplying
13371 factor 0.1405) on "X"
Add GST (multiplying
13398 factor
Add GST0.1405) on "X"
(multiplying
13415 factor
Add GST0.1405) on "X"
(multiplying 125.87
13432 factor
Add 0.1405)
GST on "X"
(multiplying 125.87
13464 factor 0.1405) on "X"
Add GST (multiplying
13481 factor
Add GST0.1405) on "X"
(multiplying
13508 factor
Add GST0.1405) on "X"
(multiplying
13525 factor 0.1405) on "X"
Add GST (multiplying
13551 factor
Add GST0.1405) on "X"
(multiplying 38.74
13568 factor
Add GST0.1405) on "X"
(multiplying
13585 factor
Add GST0.1405) on "X"
(multiplying
13612 factor 0.1405) on "X"
Add GST (multiplying
13629 factor
Add GST0.1405) on "X"
(multiplying
13658 factor
Add GST0.1405) on "X"
(multiplying
13675 factor
Add GST0.1405) on "X"
(multiplying
13692 factor
Add 0.1405)
GST on "X"
(multiplying
13720 factor 0.1405) on "X"
Add GST (multiplying
13737 factor
Add GST0.1405) on "X"
(multiplying
13764 factor 0.1405) on "X"
Add GST (multiplying
13781 factor
Add GST0.1405) on "X"
(multiplying
13808 factor
Add GST0.1405) on "X"
(multiplying 125.87
13825 factor 0.1405) on "X"
Add GST (multiplying
13842 factor
Add GST0.1405) on "X"
(multiplying
13870 factor
Add GST0.1405) on "X"
(multiplying
13887 factor
Add GST0.1405) on "X"
(multiplying
13919 factor 0.1405) on "X"
Add GST (multiplying
13936 factor
Add GST0.1405) on "X"
(multiplying
13962 factor
Add GST0.1405) on "X"
(multiplying 28.38
13979 factor
Add GST0.1405) on "X"
(multiplying
13996 factor 0.1405) on "X"
Add GST (multiplying
14021 factor
Add GST0.1405) on "X"
(multiplying
14038 factor
Add GST0.1405) on "X"
(multiplying
14055 factor
Add 0.1405)
GST on "X"
(multiplying
14082 factor 0.1405) on "X"
Add GST (multiplying
14099 factor
Add GST0.1405) on "X"
(multiplying
14126 factor
Add GST0.1405) on "X"
(multiplying
14143 factor
Add 0.1405)
GST on "X"
(multiplying
14170 factor 0.1405) on "X"
Add GST (multiplying 96.92
14187 factor
Add GST0.1405) on "X"
(multiplying
14204 factor
Add GST0.1405) on "X"
(multiplying
14232 factor
Add 0.1405)
GST on "X"
(multiplying
14251 factor 0.1405) on "X"
Add GST (multiplying
14278 factor
Add GST0.1405) on "X"
(multiplying
14295 factor
Add GST0.1405) on "X"
(multiplying
14322 factor
Add 0.1405)
GST on "X"
(multiplying 125.87
14339 factor 0.1405) on "X"
Add GST (multiplying
14361 factor
Add GST0.1405) on "X"
(multiplying
14388 factor
Add GST0.1405) on "X"
(multiplying
14407 factor
Add 0.1405)
GST on "X"
(multiplying
14434 factor 0.1405) on "X"
Add GST (multiplying
14453 factor
Add GST0.1405) on "X"
(multiplying
14481 factor
Add GST0.1405) on "X"
(multiplying 47.82
14499 factor 0.1405) on "X"
Add GST (multiplying 58.04
14517 factor
Add GST0.1405) on "X"
(multiplying
14546 factor
Add GST0.1405) on "X"
(multiplying 81.74
14564 factor
Add GST0.1405) on "X"
(multiplying 96.64
14593 factor 0.1405) on "X"
Add GST (multiplying 118.92
14611 factor
Add GST0.1405) on "X"
(multiplying
14641 factor
Add GST0.1405) on "X"
(multiplying 27.39
14659 factor
Add GST0.1405) on "X"
(multiplying
14685 factor
Add 0.1405)
GST on "X"
(multiplying 35.19
14703 factor 0.1405) on "X"
Add GST (multiplying
14721 factor
Add GST0.1405) on "X"
(multiplying
14749 factor 0.1405) on "X" 65.42
Add GST (multiplying
14766 factor
Add GST0.1405) on "X"
(multiplying 80.18
14792 factor
Add GST0.1405) on "X"
(multiplying
14809 factor 0.1405) on "X"
Add GST (multiplying 103.02
14836 factor
Add GST0.1405) on "X"
(multiplying 119.2
14853 factor
Add GST0.1405) on "X"
(multiplying 161.49
14884 factor
Add GST0.1405) on "X"
(multiplying 33.21
14901 factor 0.1405) on "X"
Add GST (multiplying
14918 factor
Add GST0.1405) on "X"
(multiplying
14946 factor
Add GST0.1405) on "X"
(multiplying
14963 factor
Add GST0.1405) on "X"
(multiplying
14990 factor 0.1405) on "X"
Add GST (multiplying 124.17
15007 factor
Add GST0.1405) on "X"
(multiplying
15037 factor
Add GST0.1405) on "X"
(multiplying 21.29
15054 factor
Add 0.1405)
GST on "X"
(multiplying
15069 factor 0.1405) on "X"
Add GST (multiplying
15095 factor
Add GST0.1405) on "X"
(multiplying 29.09
15112 factor
Add GST0.1405) on "X"
(multiplying 40.73
15140 factor
Add 0.1405)
GST on "X"
(multiplying
15157 factor 0.1405) on "X"
Add GST (multiplying 67.83
15174 factor
Add GST0.1405) on "X"
(multiplying 96.92
15202 factor
Add GST0.1405) on "X"
(multiplying 96.92
15445 factor
Add 0.1405)
GST on "X"
(multiplying 40.73
15593 factor 0.1405) on "X"
Add GST (multiplying
15607 factor
Add GST0.1405) on "X"
(multiplying
15632 factor
Add GST0.1405) on "X"
(multiplying
15646 factor
Add 0.1405)
GST on "X"
(multiplying
15660 factor 0.1405) on "X"
Add GST (multiplying
15684 factor
Add GST0.1405) on "X"
(multiplying
15704 factor
Add GST0.1405) on "X"
(multiplying
15732 factor
Add 0.1405)
GST on "X"
(multiplying
15747 factor 0.1405) on "X"
Add GST (multiplying
15809 factor
Add GST0.1405) on "X"
(multiplying
15853 factor
Add GST0.1405) on "X"
(multiplying
15895 factor 0.1405) on "X"
Add GST (multiplying
15940 factor
Add GST0.1405) on "X"
(multiplying
15975 factor
Add GST0.1405) on "X"
(multiplying
16664 factor
Add GST0.1405) on "X"
(multiplying
16682 factor 0.1405) on "X"
Add GST (multiplying
16710 factor
Add GST0.1405) on "X"
(multiplying
16728 factor
Add GST0.1405) on "X"
(multiplying
16755 factor
Add GST0.1405) on "X"
(multiplying
16773 factor
Add 0.1405)
GST on "X"
(multiplying
16799 factor 0.1405) on "X"
Add GST (multiplying
16817 factor
Add GST0.1405) on "X"
(multiplying
16863 factor 0.1405) on "X"
Add GST (multiplying
16907 factor
Add GST0.1405) on "X"
(multiplying
17081 factor
Add GST0.1405) on "X"
(multiplying
17124 factor 0.1405) on "X"
Add GST (multiplying
17168 factor
Add GST0.1405) on "X"
(multiplying
17213 factor
Add GST0.1405) on "X"
(multiplying
17256 factor
Add GST0.1405) on "X"
(multiplying
17291 factor 0.1405) on "X"
Add GST (multiplying
17332 factor
Add GST0.1405) on "X"
(multiplying
17378 factor
Add GST0.1405) on "X"
(multiplying
17422 factor
Add GST0.1405) on "X"
(multiplying
19135 factor 0.1405) on "X"
Add GST (multiplying
19167 factor
Add GST0.1405) on "X"
(multiplying
19189 factor
Add GST0.1405) on "X"
(multiplying
19456 factor
Add 0.1405)
GST on "X"
(multiplying
21175 factor 0.1405) on "X"
Add GST (multiplying
21213 factor
Add GST0.1405) on "X"
(multiplying
21251 factor
Add GST0.1405) on "X"
(multiplying
21290 factor
Add 0.1405)
GST on "X"
(multiplying
21318 factor 0.1405) on "X"
Add GST (multiplying
21354 factor
Add GST0.1405) on "X"
(multiplying
21390 factor
Add GST0.1405) on "X"
(multiplying
21429 factor
Add 0.1405)
GST on "X"
(multiplying 14338.79
21459 factor 0.1405) on "X"
Add GST (multiplying
21605 factor
Add GST0.1405) on "X"
(multiplying
21633 factor
Add GST0.1405) on "X"
(multiplying
21671 factor
Add 0.1405)
GST on "X"
(multiplying
21708 factor 0.1405) on "X"
Add GST (multiplying
23057 factor
Add GST0.1405) on "X"
(multiplying
23074 factor
Add GST0.1405) on "X"
(multiplying 2128.58
23102 factor
Add 0.1405)
GST on "X"
(multiplying
23118 factor 0.1405) on "X"
Add GST (multiplying
23148 factor
Add GST0.1405) on "X"
(multiplying
23165 factor
Add GST0.1405) on "X"
(multiplying 4186.2
23195 factor 0.1405) on "X"
Add GST (multiplying
23211 factor
Add GST0.1405) on "X"
(multiplying
23259 factor
Add GST0.1405) on "X"
(multiplying 2128.58
23276 factor
Add GST0.1405) on "X"
(multiplying 3348.96
23312 factor
Add Rate as peronitem
0.1405) "X" no
22841 5.19 5.19 SH : RCC
Add Rate as per item no cum 3.18 10438.40
22883 5.19 5.19 SH : RCC
Add Rate as per item no cum 3.925 10438.40
22924 5.19 5.19 SH : RCC
Add Rate as per item no cum 4.75 10438.40
22964 5.19 Add
5.19 Rate
SH : RCC
as per item no cum 10.88 10438.40
23006 5.19 5.19 SH : RCC
Added 10% allowance for cum 15.7 10438.40
15788 breakage
Added 10% allowance for
15790 breakage metre
Added 10% allowance for
15833 breakage
Added 10% allowance for
15866 breakage
Added 10% allowance for
15909 breakage
Added 10% allowance for
15912 breakage
Added 10% allowance for
15955 breakage
Added 10% allowance for
15957 Added 10% allowance for metre
breakage
15835 breakage
Added 2%Cement
wastageofand50 metre
6452 fitting
aggregate 20 mm nominal
20278 size For benching
aggregate 20 mm :nominal
20607 size)
aggregate 20 mm nominal
20840 size)
aggregate 20 mm nominal
21074 size)
aggregate 40 mm nominal
17539 size)
20381 aggregate stone
with V-profile or M-profile
12866 and with O
with V-profile or M-profile
15582 and
withwith O or M-profile
V-profile
15692 and with Ofor breakage in
allowance
15868 itemsbenching
work (I) & (ii) and metre
19751 making
22087 and accessories
22119 and accessories
22160 and accessories
22200 and
and accessories
making good the
12098 same
and making good the
12137 same
20204 arch
16027 Area
16058 Area
16078 Area
Area = 1.40x2.925 m = 4.1
21050 sqm
Area = 10x0.0845 sqm. =
5623 0.845
Area =sqm. Primingsqm.
10x0.1061 coat-
=
5645 1.061 sqm. Priming
Area = 10x0.1334 sqm. = coat-
5677 1.334
Area =sqm. Primingsqm.
10x0.1520 coat-
=
5697 1.520 sqm. Priming
Area = 10x0.1894 sqm. coat-
=
5727 1.894 sqm. Priming
Area = 424 x 162 + (62)²coat-
16112 (Cot
AreaQ= -5903.14 + Q)+ (145)²
x 295
16256 (Cot
AreaQ= -W x W/2 + ½ x
15999 (3.14
Area =x W W²x/W/2
4) + ½ x
16019 (3.14
Area =x W W²x/W/2
4) + ½ x
16050 (3.14
Area =x W W²x/W/2
4) + ½ x
16070 (3.14 x W² / 4)
16007 Area=
Area=10x0.0673m =
5591 0.673sqm. Priming
as per I.S. 9523 uptocoat-
8171 2309 600mm
as per ISdia1538 suitable for
8040 lead jointing over 300mm
ash clay sewer bricks
18335 (Confirming
ash clay sewer to IS 4885)
bricks
18348 conforming
ash clay sewer to IS : 4885
bricks in in
18815 cement mortar 1:3
ash clay sewer bricks in( 1
18801 cement
Assistantmortar 1:42nd
Fitter or (1
22 20 class FitterFitter or 2nd
Assistant day 0.66 403.67
56 20 class FitterFitter or 2nd
Assistant day 0.82 403.67
80 20 class FitterFitter or 2nd
Assistant day 0.98 403.67
115 20 class FitterFitter or 2nd
Assistant day 0.98 403.67
152 20 class FitterFitter or 2nd
Assistant day 1.31 403.67
176 20 class FitterFitter or 2nd
Assistant day 1.31 403.67
216 20 class FitterFitter or 2nd
Assistant day 0.66 403.67
251 20 class FitterFitter or 2nd
Assistant day 0.66 403.67
275 20 class FitterFitter or 2nd
Assistant day 0.66 403.67
311 class FitterFitter or 2nd
20 Assistant day 0.66 403.67
547 20 class FitterFitter or 2nd
Assistant day 0.82 403.67
570 20 class FitterFitter or 2nd
Assistant day 0.98 403.67
603 20 class FitterFitter or 2nd
Assistant day 0.98 403.67
638 class FitterFitter or 2nd
20 Assistant day 1.31 403.67
662 20 class FitterFitter or 2nd
Assistant day 1.31 403.67
703 20 class FitterFitter or 2nd
Assistant day 0.66 403.67
737 20 class FitterFitter or 2nd
Assistant day 0.66 403.67
762 20 Assistant
class FitterFitter or 2nd day 0.66 403.67
1453 20 class FitterFitter or 2nd
Assistant day 0.82 403.67
1480 20 class FitterFitter or 2nd
Assistant day 0.98 403.67
1514 20 class FitterFitter or 2nd
Assistant day 0.98 403.67
1549 20 Assistant
class FitterFitter or 2nd day 0.98 403.67
1574 20 class FitterFitter or 2nd
Assistant day 1.31 403.67
1609 20 class FitterFitter or 2nd
Assistant day 1.31 403.67
1650 20 class FitterFitter or 2nd
Assistant day 0.66 403.67
1677 20 Assistant
class FitterFitter or 2nd day 0.66 403.67
1714 20 class FitterFitter or 2nd
Assistant day 0.66 403.67
1751 20 class FitterFitter or 2nd
Assistant day 0.66 403.67
2118 20 class FitterFitter or 2nd
Assistant day 0.66 403.67
2144 class FitterFitter or 2nd
20 Assistant day 0.82 403.67
2181 20 class FitterFitter or 2nd
Assistant day 0.98 403.67
2216 20 class FitterFitter or 2nd
Assistant day 0.98 403.67
2243 20 class FitterFitter or 2nd
Assistant day 1.31 403.67
2280 class FitterFitter or 2nd
20 Assistant day 1.64 403.67
2321 20 class FitterFitter or 2nd
Assistant day 0.66 403.67
2355 20 class FitterFitter or 2nd
Assistant day 0.66 403.67
3508 20 class FitterFitter or 2nd
Assistant day 0.17 403.67
3539 20 Assistant
class FitterFitter or 2nd day 0.62 403.67
4043 20 class FitterFitter or 2nd
Assistant day 1 403.67
4069 20 class FitterFitter or 2nd
Assistant day 1.5 403.67
4104 20 class Fitter day 1.5 403.67
Assistant Fitter or 2nd
4139 20 class FitterFitter or 2nd
Assistant day 2 403.67
4165 20 class FitterFitter or 2nd
Assistant day 2.5 403.67
4201 20 class FitterFitter or 2nd
Assistant day 3 403.67
4238 20 class FitterFitter or 2nd
Assistant day 3 403.67
4264 20 class FitterFitter or 2nd
Assistant day 4 403.67
4299 20 class FitterFitter or 2nd
Assistant day 4.5 403.67
4325 20 class FitterFitter or 2nd
Assistant day 4.75 403.67
4360 20 class FitterFitter or 2nd
Assistant day 6.5 403.67
4411 20 class FitterFitter or 2nd
Assistant day 0.15 403.67
4443 20 class FitterFitter or 2nd
Assistant day 0.25 403.67
4466 20 class FitterFitter or 2nd
Assistant day 0.25 403.67
4499 20 class FitterFitter or 2nd
Assistant day 0.3 403.67
4522 20 class FitterFitter or 2nd
Assistant day 0.3 403.67
4555 class FitterFitter or 2nd
20 Assistant day 0.4 403.67
4578 20 class FitterFitter or 2nd
Assistant day 0.4 403.67
4612 20 class FitterFitter or 2nd
Assistant day 0.5 403.67
4645 20 class FitterFitter or 2nd
Assistant day 0.5 403.67
4668 class FitterFitter or 2nd
20 Assistant day 0.6 403.67
4701 20 class FitterFitter or 2nd
Assistant day 0.65 403.67
4724 20 class FitterFitter or 2nd
Assistant day 0.75 403.67
8221 20 class FitterFitter or 2nd
Assistant day 1 403.67
8243 20 Assistant
class FitterFitter or 2nd day 1.5 403.67
8275 20 class FitterFitter or 2nd
Assistant day 2 403.67
8297 20 class FitterFitter or 2nd
Assistant day 2.5 403.67
8329 20 class FitterFitter or 2nd
Assistant day 3 403.67
8351 20 Assistant
class FitterFitter or 2nd day 3 403.67
8383 20 class FitterFitter or 2nd
Assistant day 4 403.67
8405 20 class FitterFitter or 2nd
Assistant day 4.5 403.67
8437 20 class FitterFitter or 2nd
Assistant day 4.75 403.67
8459 20 Assistant
class FitterFitter or 2nd day 6.5 403.67
8491 20 class FitterFitter or 2nd
Assistant day 7.7 403.67
8513 20 class FitterFitter or 2nd
Assistant day 7.7 403.67
8544 20 class FitterFitter or 2nd
Assistant day 8.5 403.67
8566 class FitterFitter or 2nd
20 Assistant day 10 403.67
8598 20 class FitterFitter or 2nd
Assistant day 11 403.67
11145 20 class FitterFitter or 2nd
Assistant day 0.5 403.67
11186 20 class FitterFitter or 2nd
Assistant day 0.63 403.67
11226 class FitterFitter or 2nd
20 Assistant day 0.75 403.67
11257 20 class FitterFitter or 2nd
Assistant day 0.88 403.67
11299 20 class FitterFitter or 2nd
Assistant day 1.1 403.67
11339 20 class FitterFitter or 2nd
Assistant day 1.3 403.67
11368 20 Assistant
class FitterFitter or 2nd day 1.5 403.67
11410 20 class FitterFitter or 2nd
Assistant day 1.75 403.67
11451 20 class FitterFitter or 2nd
Assistant day 2 403.67
11482 20 class Fitter day 2.25 403.67
Assistant Fitter or 2nd
11523 20 class FitterFitter or 2nd
Assistant day 2.5 403.67
11564 20 class FitterFitter or 2nd
Assistant day 3 403.67
11888 20 class Fitter
Assistant Fitter or 2nd day 0.66 403.67
11927 20 class FitterFitter or 2nd
Assistant day 0.66 403.67
11963 20 class FitterFitter or 2nd
Assistant day 0.66 403.67
11992 20 class FitterFitter or 2nd
Assistant day 0.66 403.67
12031 20 class Fitter
Assistant Fitter or 2nd day 0.66 403.67
12070 20 class FitterFitter or 2nd
Assistant day 0.66 403.67
12114 20 class FitterFitter or 2nd
Assistant day 0.66 403.67
12144 20 class Fitter day 0.66 403.67
10359 Average size 15x15x15
Bed : 0.45x0.45 m = 0.202 cm
20593 sqm
Bed : 0.45x0.50 m = 0.225
20537 sqm
Bed : 0.61x0.455 m =
20775 0.278: 0.70x0.50
Bed sqm m = 0.35
20834 sqm
Bed : 0.85x0.60 m = 0.51
20914 sqm
Bed : 1.10x0.50 m = 0.55
20672 sqm
23 17 Beldar day 0.66 350.00
57 17 Beldar day 0.66 350.00
81 17 Beldar day 0.66 350.00
116 17 Beldar day 0.98 350.00
153 17 Beldar day 1.31 350.00
177 17 Beldar day 1.31 350.00
217 17 Beldar day 0.66 350.00
252 17 Beldar day 0.66 350.00
276 17 Beldar day 0.66 350.00
312 17 Beldar day 0.66 350.00
356 17 Beldar day 0.16 350.00
358 17 Beldar day 0.66 350.00
390 17 Beldar day 0.16 350.00
392 17 Beldar day 0.66 350.00
415 17 Beldar day 0.16 350.00
417 17 Beldar day 0.66 350.00
450 17 Beldar day 0.16 350.00
452 17 Beldar day 0.66 350.00
475 17 Beldar day 0.33 350.00
487 17 Beldar day 0.66 350.00
510 17 Beldar day 0.33 350.00
512 17 Beldar day 0.66 350.00
548 17 Beldar day 0.66 350.00
571 17 Beldar day 0.66 350.00
604 17 Beldar day 0.66 350.00
639 17 Beldar day 1.31 350.00
663 17 Beldar day 1.31 350.00
704 17 Beldar day 0.66 350.00
738 17 Beldar day 0.66 350.00
763 17 Beldar day 0.66 350.00
802 17 Beldar day 0.16 350.00
804 17 Beldar day 0.66 350.00
840 17 Beldar day 0.25 350.00
842 17 Beldar day 0.66 350.00
868 17 Beldar day 0.25 350.00
870 17 Beldar day 0.66 350.00
907 17 Beldar day 0.33 350.00
909 17 Beldar day 0.66 350.00
945 17 Beldar day 0.33 350.00
947 17 Beldar day 0.66 350.00
973 17 Beldar day 0.66 350.00
975 17 Beldar day 0.66 350.00
1006 17 Beldar day 0.66 350.00
1008 17 Beldar day 0.66 350.00
1035 17 Beldar day 0.97 350.00
1037 17 Beldar day 0.8 350.00
1074 17 Beldar day 0.97 350.00
1076 17 Beldar day 0.8 350.00
1332 17 Beldar day 0.11 350.00
1389 17 Beldar day 0.11 350.00
1417 17 Beldar day 0.11 350.00
1454 17 Beldar day 0.66 350.00
1481 17 Beldar day 0.66 350.00
1515 17 Beldar day 0.66 350.00
1550 17 Beldar day 0.98 350.00
1575 17 Beldar day 1.31 350.00
1610 17 Beldar day 1.31 350.00
1651 17 Beldar day 0.66 350.00
1678 17 Beldar day 0.66 350.00
1715 17 Beldar day 0.66 350.00
1752 17 Beldar day 0.66 350.00
1780 17 Beldar day 0.16 350.00
1782 17 Beldar day 0.66 350.00
1817 17 Beldar day 0.16 350.00
1819 17 Beldar day 0.66 350.00
1851 17 Beldar day 0.25 350.00
1853 17 Beldar day 0.66 350.00
1877 17 Beldar day 0.25 350.00
1879 17 Beldar day 0.66 350.00
1914 17 Beldar day 0.33 350.00
1916 17 Beldar day 0.66 350.00
1940 17 Beldar day 0.33 350.00
1942 17 Beldar day 0.66 350.00
1975 17 Beldar day 0.66 350.00
1977 17 Beldar day 0.66 350.00
2012 17 Beldar day 0.66 350.00
2014 17 Beldar day 0.66 350.00
2038 17 Beldar day 0.97 350.00
2040 17 Beldar day 0.8 350.00
2074 17 Beldar day 1.54 350.00
2076 17 Beldar day 1.2 350.00
2119 17 Beldar day 0.66 350.00
2145 17 Beldar day 0.66 350.00
2182 17 Beldar day 0.66 350.00
2217 17 Beldar day 0.98 350.00
2244 17 Beldar day 1.31 350.00
2281 17 Beldar day 1.64 350.00
2322 17 Beldar day 0.66 350.00
2366 17 Beldar day 0.66 350.00
2394 17 Beldar day 0.16 350.00
2396 17 Beldar day 0.66 350.00
2431 17 Beldar day 0.16 350.00
2433 17 Beldar day 0.66 350.00
2468 17 Beldar day 0.25 350.00
2470 17 Beldar day 0.66 350.00
2496 17 Beldar day 0.25 350.00
2498 17 Beldar day 0.66 350.00
2531 17 Beldar day 0.33 350.00
2533 17 Beldar day 0.66 350.00
2557 17 Beldar day 0.33 350.00
2559 17 Beldar day 0.66 350.00
2595 17 Beldar day 0.66 350.00
2597 17 Beldar day 0.66 350.00
2632 17 Beldar day 0.66 350.00
2634 17 Beldar day 0.66 350.00
2660 17 Beldar day 0.33 350.00
2691 17 Beldar day 0.45 350.00
2720 17 Beldar day 0.33 350.00
3519 17 Beldar day 1.33 350.00
3540 17 Beldar day 2.48 350.00
4044 17 Beldar day 2 350.00
4070 17 Beldar day 3 350.00
4105 17 Beldar day 3 350.00
4140 17 Beldar day 4 350.00
4166 17 Beldar day 5 350.00
4202 17 Beldar day 6 350.00
4239 17 Beldar day 6 350.00
4265 17 Beldar day 8 350.00
4300 17 Beldar day 9 350.00
4335 17 Beldar day 9.5 350.00
4361 17 Beldar day 13 350.00
4412 17 Beldar day 0.8 350.00
4444 17 Beldar day 1 350.00
4467 17 Beldar day 1 350.00
4500 17 Beldar day 1.1 350.00
4523 17 Beldar day 1.1 350.00
4556 17 Beldar day 1.3 350.00
4579 17 Beldar day 1.3 350.00
4613 17 Beldar day 1.5 350.00
4646 17 Beldar day 1.5 350.00
4669 17 Beldar day 1.7 350.00
4702 17 Beldar day 1.8 350.00
4725 17 Beldar day 2 350.00
6101 17 Beldar day 0.09 350.00
6338 17 Beldar day 3 350.00
6370 17 Beldar day 3.5 350.00
6395 17 Beldar day 4 350.00
6431 17 Beldar day 0.17 350.00
6467 17 Beldar day 0.75 350.00
6489 17 Beldar day 0.1 350.00
6522 17 Beldar day 0.11 350.00
6542 17 Beldar day 0.11 350.00
6571 17 Beldar day 0.11 350.00
6591 17 Beldar day 0.11 350.00
6620 17 Beldar day 0.11 350.00
6640 17 Beldar day 0.15 350.00
6660 17 Beldar day 0.15 350.00
6689 17 Beldar day 0.15 350.00
6721 17 Beldar day 0.33 350.00
6741 17 Beldar day 0.33 350.00
6770 17 Beldar day 0.33 350.00
6790 17 Beldar day 0.33 350.00
6819 17 Beldar day 0.33 350.00
6839 17 Beldar day 0.45 350.00
6869 17 Beldar day 0.45 350.00
6889 17 Beldar day 0.45 350.00
8222 17 Beldar day 1 350.00
8244 17 Beldar day 3 350.00
8276 17 Beldar day 4 350.00
8298 17 Beldar day 5 350.00
8330 17 Beldar day 6 350.00
8352 17 Beldar day 6 350.00
8384 17 Beldar day 8 350.00
8406 17 Beldar day 9 350.00
8438 17 Beldar day 9.5 350.00
8460 17 Beldar day 13 350.00
8492 17 Beldar day 15.4 350.00
8514 17 Beldar day 15.4 350.00
8545 17 Beldar day 17 350.00
8567 17 Beldar day 20 350.00
8599 17 Beldar day 22 350.00
10314 17 Beldar day 1.25 350.00
10363 17 Beldar day 1.67 350.00
10394 17 Beldar day 1 350.00
10471 17 Beldar day 1.31 350.00
10494 17 Beldar day 1.64 350.00
10528 17 Beldar day 1.97 350.00
10558 17 Beldar day 2.3 350.00
10581 17 Beldar day 2.95 350.00
10613 17 Beldar day 3.61 350.00
10636 17 Beldar day 3.94 350.00
10669 17 Beldar day 4.27 350.00
10706 17 Beldar day 4.59 350.00
10729 17 Beldar day 4.92 350.00
10761 17 Beldar day 5.25 350.00
10784 17 Beldar day 5.91 350.00
10815 17 Beldar day 0.49 350.00
10849 17 Beldar day 0.57 350.00
10869 17 Beldar day 0.66 350.00
10902 17 Beldar day 0.74 350.00
10922 17 Beldar day 0.9 350.00
10955 17 Beldar day 1.1 350.00
10975 17 Beldar day 1.3 350.00
11008 17 Beldar day 1.5 350.00
11028 17 Beldar day 1.7 350.00
11061 17 Beldar day 1.9 350.00
11081 17 Beldar day 2.1 350.00
11114 17 Beldar day 2.5 350.00
11146 17 Beldar day 4 350.00
11187 17 Beldar day 4.5 350.00
11227 17 Beldar day 5 350.00
11258 17 Beldar day 5.5 350.00
11300 17 Beldar day 6.5 350.00
11340 17 Beldar day 7.5 350.00
11369 17 Beldar day 8.5 350.00
11411 17 Beldar day 9.5 350.00
11452 17 Beldar day 10.5 350.00
11483 17 Beldar day 11.5 350.00
11524 17 Beldar day 12.5 350.00
11565 17 Beldar day 14.5 350.00
11587 17 Beldar day 0.06 350.00
11615 17 Beldar day 0.08 350.00
11633 17 Beldar day 0.11 350.00
11658 17 Beldar day 0.15 350.00
11676 17 Beldar day 0.2 350.00
11694 17 Beldar day 0.25 350.00
11722 17 Beldar day 0.3 350.00
11740 17 Beldar day 0.35 350.00
11768 17 Beldar day 0.4 350.00
11786 17 Beldar day 0.45 350.00
11802 17 Beldar day 0.5 350.00
11829 17 Beldar day 0.6 350.00
11889 17 Beldar day 0.66 350.00
11928 17 Beldar day 0.66 350.00
11964 17 Beldar day 0.66 350.00
11993 17 Beldar day 0.66 350.00
12032 17 Beldar day 0.66 350.00
12071 17 Beldar day 0.66 350.00
12115 17 Beldar day 0.66 350.00
12145 17 Beldar day 0.66 350.00
15804 17 Beldar day 3 350.00
15848 17 Beldar day 4 350.00
15890 17 Beldar day 4.5 350.00
15935 17 Beldar day 5.5 350.00
15970 17 Beldar day 6 350.00
16659 17 Beldar day 0.49 350.00
16677 17 Beldar day 0.49 350.00
16705 17 Beldar day 0.49 350.00
16723 17 Beldar day 0.49 350.00
16750 17 Beldar day 0.49 350.00
16768 17 Beldar day 0.6 350.00
16794 17 Beldar day 0.66 350.00
16812 17 Beldar day 0.66 350.00
16858 17 Beldar day 0.63 350.00
16902 17 Beldar day 0.78 350.00
16934 17 Beldar day 1.5 350.00
16989 17 Beldar 350.00
17076 17 Beldar day 1.5 350.00
17119 17 Beldar day 1.62 350.00
17163 17 Beldar day 1.83 350.00
17208 17 Beldar day 2.06 350.00
17251 17 Beldar day 2.28 350.00
17286 17 Beldar day 3 350.00
17327 17 Beldar day 4.33 350.00
17373 17 Beldar day 6.3 350.00
17417 17 Beldar day 8.67 350.00
18928 17 Beldar day 0.1 350.00
18937 17 Beldar day 0.05 350.00
18970 17 Beldar day 0.1 350.00
18979 17 Beldar day 0.05 350.00
19017 17 Beldar day 0.05 350.00
19052 17 Beldar day 0.1 350.00
19062 17 Beldar day 0.1 350.00
19085 17 Beldar day 0.1 350.00
19105 17 Beldar day 0.1 350.00
19131 17 Beldar day 0.12 350.00
19163 17 Beldar day 0.12 350.00
19185 17 Beldar day 0.12 350.00
19452 17 Beldar day 0.03 350.00
19500 17 Beldar day 0.25 350.00
19547 17 Beldar day 0.25 350.00
19591 17 Beldar day 0.33 350.00
19670 17 Beldar day 2.7 350.00
19755 17 Beldar day 3.5 350.00
19806 17 Beldar day 0.04 350.00
19855 17 Beldar day 0.05 350.00
21094 17 Beldar day 3 350.00
21139 17 Beldar day 0.5 350.00
21170 17 Beldar day 0.06 350.00
21208 17 Beldar day 0.08 350.00
21246 17 Beldar day 2.41 350.00
21285 17 Beldar day 1.83 350.00
21313 17 Beldar day 3 350.00
21349 17 Beldar day 4.33 350.00
21385 17 Beldar day 8.67 350.00
21414 17 Beldar day 13 350.00
21454 17 Beldar day 2.41 350.00
21505 17 Beldar 350.00
21600 17 Beldar day 3 350.00
21628 17 Beldar day 4.33 350.00
21666 17 Beldar day 8.67 350.00
21703 17 Beldar day 13 350.00
21787 17 Beldar day 2 350.00
21825 17 Beldar day 2 350.00
21865 17 Beldar day 2 350.00
21904 17 Beldar day 2 350.00
21935 17 Beldar day 3.5 350.00
21973 17 Beldar day 4 350.00
22011 17 Beldar day 4.5 350.00
22049 17 Beldar day 5 350.00
22095 17 Beldar day 2.5 350.00
22136 17 Beldar day 2.5 350.00
22168 17 Beldar day 3 350.00
22208 17 Beldar day 3.5 350.00
22320 17 Beldar day 3 350.00
22359 17 Beldar day 3.5 350.00
22396 17 Beldar day 4 350.00
22437 17 Beldar day 4.5 350.00
22467 17 Beldar day 5 350.00
22511 17 Beldar day 2 350.00
22554 17 Beldar day 2 350.00
22595 17 Beldar day 2 350.00
22635 17 Beldar day 2 350.00
22677 17 Beldar day 1 350.00
22705 17 Beldar day 1 350.00
22738 17 Beldar day 1 350.00
22773 17 Beldar day 1 350.00
22821 17 Beldar day 3 350.00
22864 17 Beldar day 10.78 350.00
22905 17 Beldar day 3 350.00
22944 17 Beldar day 3 350.00
22978 17 Beldar day 3 350.00
23020 17 Beldar day 3 350.00
17706 benching
18288 Benching
18377 Benching
18758 Benching
18852 Benching
18257 benching :
22075 7183 Bentonite tonne 0.25 2960
22114 7183 Bentonite tonne 0.28 2960
22155 7183 Bentonite tonne 0.33 2960
22195 7183 Bentonite tonne 0.3 2960
22307 7183 Bentonite tonne 0.33 2960
22346 7183 Bentonite tonne 0.3 2960
22376 7183 Bentonite tonne 0.35 2960
22415 7183 Bentonite tonne 0.385 2960
22454 7183 Bentonite tonne 0.45 2960
22500 7183 Bentonite tonne 0.08 2960
22543 7183 Bentonite tonne 0.15 2960
22584 7183 Bentonite tonne 0.19 2960
22624 7183 Bentonite tonne 0.2 2960
22667 7183 Bentonite tonne 0.003 2960
22695 7183 Bentonite tonne 0.006 2960
22728 7183 Bentonite tonne 0.008 2960
22763 7183 Bentonite
Beyond 12 m and up to 18 tonne 0.01 2960
6389 18.42.3 m depth6 m and up to 12
Beyond
6357 18.42.2 m depth
15805 11 Bhisti day 1 350.00
15849 11 Bhisti day 1 350.00
15891 11 Bhisti day 1.25 350.00
15936 11 Bhisti day 1.5 350.00
15971 11 Bhisti day 1.5 350.00
16859 11 Bhisti day 0.16 350.00
16903 11 Bhisti day 0.16 350.00
16945 11 Bhisti 350.00
16990 11 Bhisti 350.00
17077 11 Bhisti day 0.33 350.00
17120 11 Bhisti day 0.33 350.00
17164 11 Bhisti day 0.33 350.00
17209 11 Bhisti day 0.42 350.00
17252 11 Bhisti day 0.42 350.00
17287 11 Bhisti day 0.5 350.00
17328 11 Bhisti day 0.5 350.00
17374 11 Bhisti day 0.6 350.00
17418 11 Bhisti day 0.67 350.00
21171 11 Bhisti day 0.02 350.00
21209 11 Bhisti day 0.03 350.00
21247 11 Bhisti day 0.33 350.00
21286 11 Bhisti day 0.33 350.00
21314 11 Bhisti day 0.5 350.00
21350 11 Bhisti day 0.5 350.00
21386 11 Bhisti day 0.67 350.00
21415 11 Bhisti day 1 350.00
21455 11 Bhisti day 0.33 350.00
21507 11 Bhisti 350.00
21601 11 Bhisti day 0.5 350.00
21629 11 Bhisti day 0.5 350.00
21667 11 Bhisti day 0.67 350.00
21704 11 Bhisti day 1 350.00
18969 13 Blacksmith 2nd class day 0.1 403.67
19051 13 Blacksmith 2nd class day 0.1 403.67
19084 13 Blacksmith 2nd class day 0.1 403.67
18927 Blacksmith 2nd class day 0.1 403.67
10468 1301 Bleaching powder quintal 0.008 1800
10491 1301 Bleaching powder quintal 0.012 1800
10525 1301 Bleaching powder quintal 0.018 1800
10555 1301 Bleaching powder quintal 0.027 1800
10578 1301 Bleaching powder quintal 0.047 1800
10610 1301 Bleaching powder quintal 0.074 1800
10633 1301 Bleaching powder quintal 0.106 1800
10666 1301 Bleaching powder quintal 0.144 1800
10703 1301 Bleaching powder quintal 0.189 1800
10726 1301 Bleaching powder quintal 0.239 1800
10758 1301 Bleaching powder quintal 0.295 1800
10781 1301 Bleaching powder quintal 0.424 1800
10812 1301 Bleaching powder quintal 0.003 1800
10834 1301 Bleaching powder quintal 0.004 1800
10866 1301 Bleaching powder quintal 0.006 1800
10888 1301 Bleaching powder quintal 0.009 1800
10919 1301 Bleaching powder quintal 0.016 1800
10941 1301 Bleaching powder quintal 0.025 1800
10972 1301 Bleaching powder quintal 0.035 1800
10994 1301 Bleaching powder quintal 0.048 1800
11025 1301 Bleaching powder quintal 0.063 1800
11047 1301 Bleaching powder quintal 0.08 1800
11078 1301 Bleaching powder quintal 0.098 1800
11100 1301 Bleaching powder quintal 0.141 1800
10465 Bleaching powder
10488 Bleaching powder
10522 Bleaching powder
10552 Bleaching powder
10575 Bleaching powder
10607 Bleaching powder
10630 Bleaching powder
10663 Bleaching powder
10723 Bleaching powder
10755 Bleaching powder
10778 Bleaching powder
Block = 1.92x0.23x0.15 =
20679 0.07 cum
Block = 3x(0.75)³ = 0.001
20604 cum
Bolts and nuts 16 mm dia
4407 1956 60 mm
Bolts long
and nuts 16 mm dia each 40 11
4439 1956 60 mm long
Bolts and nuts 16 mm dia each 80 11
4462 1957 65 mm
Bolts long
and nuts 20 mm dia each 80 12
4495 1958 65 mm long
Bolts and nuts 20 mm dia each 80 15
4518 1959 70 mm
Bolts long
and nuts 20 mm dia each 80 17
4551 1960 75 mm long
Bolts and nuts 20 mm dia each 120 16
4574 1960 75 mm
Bolts long
and nuts 20 mm dia each 120 16
4608 1961 80 mm long
Bolts and nuts 24 mm dia each 160 18
4631 1962 Bolts
85 mm long
and nuts 24 mm dia each 160 28
4664 1962 85 mm long
Bolts and nuts 24 mm dia each 200 28
4697 1963 90 mm
Bolts long
and nuts 27 mm dia each 200 32
4720 1964 100 mm long each 200 38
tube well is lowered and
6331 18.42 tested
measured : upto to the
22488 20.3 bottom of pile cap)
situ reinforced cement:
22290 20.2A concrete
2738 1339 Brass bib-cock 15 mm dia each 1 210
2755 1340 Brass bib-cock
C.I. wheel 20 mm
(screwed dia each
end) 1 225
2830 1927 25
C.I. wheel (screwed end) each 1 350
2863 1928 32
C.I. wheel (screwed end) each 1 410
2892 1929 40
C.I. wheel (screwed end) each 1 480
2910 1930 50
C.I. wheel (screwed end) each 1 620
2938 1931 65
C.I. wheel (screwed end) each 1 1080
2956 1932 80
Brass stop-cock 15 mm each 1 1620
2784 1342 dia
Brass stop-cock 20 mm each 1 210
2801 1343 dia
Breaking lead caulked each 1 225
11140 joints, blocks
Breaking leadand stacking
caulked
11181 joints, blocks and
Breaking lead caulked stacking
11212 joints,
Breaking blocks
leadand stacking
caulked
11252 joints,
Breaking blocks
leadand stacking
caulked
11294 joints, blocks
Breaking leadand stacking
caulked
11325 joints, blocks and
Breaking lead caulked stacking
11363 joints,
Breaking blocks
leadand stacking
caulked
11405 joints,
Breaking blocks
leadand stacking
caulked
11446 joints, blocks
Breaking leadand stacking
caulked
11477 joints, blocks and
Breaking lead caulked stacking
11518 joints,
Breaking blocks
leadand stacking
caulked
11559 joints, blocks and(Single
Brick Aggregate stacking
21065 287 Brick
size) :Aggregate
40 mm nominal(Singlesize cum 6.91 650
21062 285 size)
Brick aggregate 40 mmsize cum
: 63 mm nominal 4.13 650
21063 nominal size 50 to 80
Brick aggregate
21060 mm nominal size
21059 362 Brick bats cum 2.74 1000
21119 362 Brick bats
3.14/4x(1.2)²x2.925m cum 1.73 1000
21056 =3.33 cum
21125 1854 brick
brick depth
depth 3.14x2.6 m
21089 16.8.1 =8.17 m
19803 23 brick
brick work
work benching and
19667 23 channel
20081 Brick
Brick work
work inin arches
arches with
18732 7.5 class designation
Brick work in arches with brick
18499 75 class designation
modular extruded brunt brick
18347 fly
modular extruded brunt
18814 fly
Brick work in Archis with
18248 7.5 class
Brick workdesignation
in bricks ofbrick
clas
20895 designation 7.5 in
Brick work in bricks of clas
20977 designation
Brick work in7.5 in of clas
bricks
20995 designation 7.5 in
Brick work in bricks of clas
20520 designation
Brick work in75bricks
in cement
of clas
20659 designation 75 in cement
Brick work in bricks of clas
20765 designation
Brick work in75bricks
in cement
of clas
20825 designation 75 in
Brick work in cement cement
19707 mortar
Brick work in cement
19622 mortar 1:4 in foundation
Brick work
18417 with 75
Brick workclass designation
with 7.5 class
16343 designation
designation brick in
brick in
16453 cement
designation brick in
16564 cement
modular extruded brunt
18800 fly
Brick work with bricks of
17696 class
Brick designation
work with bricks of
18134 class designation
Brick work with bricks7.5 inof
18180 class designation
Brick 7.5 inof
work with bricks
18671 class designation
Brick work with bricks7.5 inof
18719 class
Brick designation 7.5 inof
work with bricks
10315 class
Brick designation 75 inof
work with bricks
18235 class modular
with designation 75 in
extruted
18334 brunt
extruded brunt fly ash
18151 clay
extruded brunt fly ash
18197 clay
Brick work with modular
16394 extruted
bricks burnt fly ash
conforming to clay
16507 IS:4885
bricks conforming to
16619 IS:4885
bricks conforming to
17542 IS:4885
bricks in cement mortar
18418 1:4
5752 9999 Building)
5780 9999 Building)
5799 9999 Building)
5818 9999 Building)
5847 9999 Building)
5866 9999 Building)
22693 Bulb - 0.063 cum
22726 Bulb - 0.081 cum
22761 Bulb - 0.102 cum
3.14/4x(0.75)²x0.075 =
22496 0.033 cum
Bulb -3.14/4x(1.00)²x0.1 =
22539 0.079 cum
3.14/4x(1.125)²x0.113 =
22580 0.112 cum
3.14/4x(1.25)²x0.125 =
22620 0.153
C.C workcum1:2:4 ( 1
20489 cement
C.I. cover: 2and
coarse
framesand : 4
16329 1352 300x300
C.I. covermm andinside
frame each 1 477
16379 1352 C.I.
300x300
covermm andinside
frame each 1 477
16435 1352 300x300 mm inside
C.I. cover and frame each 1 477
16492 1352 300x300
C.I. covermm andinside
frame each 1 477
16549 1352 300x300 mm inside each 1 477
C.I. cover and frame
16604 1352 300x300 mm inside each 1 477
16328 1364 C.I. grating 100x100 mm each 1 40.22
16378 1364 C.I. grating 100x100 mm each 1 40.22
16434 1366 C.I. grating 150x150 mm each 1 54.42
16491 1366 C.I. grating 150x150 mm each 1 54.42
16548 1367 C.I. grating 180x180 mm each 1 65
16603 1367 C.I.
C.I. grating
pile shoe 180x180
of 80 kgmmper each 1 65
21776 7181 pile @ 80 kg per pile
C.I. pile shoe of 80 kg per kilogram 80 48
21814 7181 pile @ 80
C.I. pile kg per
shoe pile
of 80 kg per kilogram 80 48
21845 7181 pile @ 80 kg per pile
C.I. pile shoe of 80 kg per kilogram 80 48
21885 7181 pile @ 80
C.I. pile kg per
shoe pile
of 80 kg per kilogram 80 48
21924 7181 pile @ 80 kg per pile
C.I. pile shoe of 80 kg per kilogram 80 48
21962 7181 pile @ 80
C.I. pile kg per
shoe pile
of 80 kg per kilogram 80 48
22000 pile pile
7181 C.I. @ 80 kg per
shoe pile
of 80 kg per kilogram 80 48
22031 7181 pile @ 80 kg per pile
C.I. pile shoe of 80 kg per kilogram 80 48
22811 7181 pile @ 80
C.I. pile kg per
shoe pile
of 80 kg per kilogram 80 48
22854 7181 pile @ 80 kg per pile
C.I. pile shoe of 80 kg per kilogram 80 48
22888 pile pile
7181 C.I. @ 80 kg per
shoe pile
of 80 kg per kilogram 80 48
22928 7181 pile @ 80 kg per pile
C.I. pile shoe of 80 kg per kilogram 80 48
22968 7181 pile @ 80
C.I. pile kg per
shoe pile
of 80 kg per kilogram 80 48
23010 7181 pile @ 80 kg per pile
C.I.cover without frame kilogram 80 48
19448 1353 C.I.mouth,
300x300mm inside
brass ferrule each 1 477
3305 1360 15 mm dia
C.I.mouth, brass ferrule each 1 140
3331 1361 20 mm dia brass ferrule
C.I.mouth, each 1 160
3348 1362 25 mm diavalve (with caps)
C.I.sluice each 1 220
4756 1940 C.I.sluice
class I : valve (with caps) each 10 2410
4818 1941 class I : valve (with caps)
C.I.sluice each 10 2600
4879 1942 class I : valve (with caps)
C.I.sluice each 10 3600
4953 1943 class I : valve (with caps)
C.I.sluice each 10 7500
5015 1944 C.I.sluice
class I : valve (with caps) each 10 10980
5077 1945 class I : valve (with caps)
C.I.sluice each 10 15500
4781 3311 class II : valve (with caps)
C.I.sluice each 10 2700
4853 3314 class II : valve (with caps)
C.I.sluice each 10 3200
4916 class II : valve (with caps)
3317 C.I.sluice each 10 4000
4979 3320 class II : valve (with caps)
C.I.sluice each 10 8900
5051 3321 class II : valve (with caps)
C.I.sluice each 10 14500
5113 3326 class II : angle valve 15
C.P. Brass each 10 18200
7069 7261 mm each 1 375
6975 7257 C.P.
C.P. Brass
Brass bibcock
Extension15 mm each 1 290
7085 593 Nipple
C.P. Brass(1/2"x2" size)
long body each 1 40
7023 7259 bibcock
C.P. Brass 15long
mmnose each 1 385
6994 7258 C.P.
bibcock
Brass 15stop
mmcock each 1 430
7042 7260 (concealed) 15 mm each 1 430
15585 Cap
6486 9977 Carriage L.S. 13.52 2
18299 9977 CARRIAGE L.S. 6.89 2
18397 9977 CARRIAGE L.S. 6.89 2
18539 9977 CARRIAGE L.S. 6.89 2
18641 9977 CARRIAGE L.S. 6.89 2
18778 9977 CARRIAGE L.S. 6.89 2
18863 CARRIAGE
Carriage and fixing L.S. 6.89 2
7070 9988 charges
Carriage and other L.S. 11.31 2
19010 9988 sundries L.S. 1.82 2
19450 9988 Carriage
Carriage for cover
of 40mm L.S. 2.7 2
6451 pipe(36.5kg)
7526 9977 Carriage of air valves L.S. 26 2
7549 9977 Carriage of air valves L.S. 26 2
7582 9977 Carriage
Carriage ofof air valves
Brick L.S. 26 2
21069 2260 aggregate
Carriage of Brick cum 13.78 115.36
21121 2260 aggregate
Carriage of brick bats and cum 1.73 115.36
21068 aggregate
21070 2201 Carriage of Bricks 1000 0.145 283.01
19161 9977 Carriage of C.I. cover L.S. 13.47 2
19183 9977 Carriage
Carriage ofof C.I.
C.I. cover
cover & L.S. 16.12 2
17522 9977 frame
Carriage of C.I. cover & L.S. 6.76 2
17615 9977 frame
Carriage of C.I. cover & 2
17752 9977 frame
Carriage of C.I. cover & L.S. 6.76 2
17911 9977 frame
Carriage of C.I. cover & L.S. 6.76 2
18002 9977 frame
Carriage of C.I. cover & L.S. 13.52 2
18101 9977 frame
Carriage of C.I. Cover and L.S. 13.52 2
20870 frame
Carriage of C.I. Cover and L.S. 7.15 2
20943 frame
Carriage of C.I. Manhole L.S. 7.15 2
19129 cover
Carriage of C.I. pipes 500 L.S. 7.15 2
9695 2299 mm dia Labour
Carriage for laying
of C.I. pipes 500 100 0.1 2577.54
10168 mm dia Labour
Carriage for laying
of C.I. surface 100 0.05 2577.54
5174 9977 box
Carriage of C.I. surface L.S. 1.43 2
5250 9977 box
Carriage of C.I.cover and L.S. 8.06 2
20790 frame
Carriage of Cast iron L.S. 7.15 2
4760 2309 fittings
Carriage of Cast iron tonne 0.44 94.34
4785 2309 fittings
Carriage of Cast iron tonne 0.56 94.34
4822 2309 fittings
Carriage of Cast iron tonne 0.56 94.34
4857 2309 fittings
Carriage of Cast iron tonne 0.68 94.34
4883 2309 fittings
Carriage of Cast iron tonne 0.72 94.34
4920 2309 fittings
Carriage of Cast iron tonne 0.865 94.34
4957 2309 fittings
Carriage of Cast iron tonne 1.22 94.34
4983 2309 fittings
Carriage of Cast iron tonne 1.5 94.34
5019 2309 fittings
Carriage of Cast iron tonne 1.8 94.34
5055 2309 fittings
Carriage of Cast iron tonne 2.3 94.34
5081 2309 fittings
Carriage of Cast iron tonne 2.42 94.34
3562 fittings tonne 0.1 94.34
Carriage of Cast iron
3593 fittings
Carriage of Cast iron tonne 0.1 94.34
3628 fittings
Carriage of Cast iron tonne 0.1 94.34
3649 fittings
Carriage of Cast iron tonne 0.1 94.34
5117 fittings
Carriage of Cast iron tonne 3.03 94.34
8074 2309 fittings
CarriageLabour
of Castfor laying
iron tonne 0.1 94.34
8189 2309 fittings
CarriageLabour
of Castfor laying
iron tonne 0.1 94.34
8022 fittings Labour for
Carriage of Cast ironlaying tonne 0.1 94.34
8042 fittings
CarriageLabour
of Castfor laying
iron tonne 0.1 94.34
8094 fittings
CarriageLabour
of Castfor Laying
iron tonne 0.1 94.34
8124 fittings
CarriageLabour
of Castfor laying
iron tonne 0.1 94.34
8141 fittings Labour for
Carriage of Cast ironlaying tonne 0.1 94.34
8172 fittings
CarriageLabour
of castfor laying
iron pipes tonne 0.1 94.34
9343 1000 mm dia Labour for
Carriage of cast iron pipes 100 0.1 7732.61
8975 150 mm dia
Carriage of cast iron pipes 100 0.1 386.63
9009 200 mm dia Labour
Carriage of cast ironfor
pipes 100 0.1 628.92
9033 250 mm dia Labour for
Carriage of cast iron pipes 100 0.1 893.73
9068 300 mm dia
Carriage Labour
of cast ironfor
pipes 100 0.1 1104.66
9092 350 mm dia
Carriage Labour
of cast ironfor
pipes 100 0.1 1546.52
9127 400 mm dia Labour for
Carriage of cast iron pipes 100 0.1 2108.89
9163 450 mm dia
Carriage Labour
of cast ironfor
pipes 100 0.1 2577.54
9188 500 mm dia Labour for
Carriage of cast iron pipes 100 0.1 2577.54
9223 600 mm dia
Carriage Labour
of cast ironfor
pipes 100 0.1 3866.3
9248 700 mm dia Labour for
Carriage of cast iron pipes 100 0.1 3866.3
9284 800 mm dia
Carriage Labour
of cast ironfor
pipes 100 0.1 3866.3
9308 900 mm dia Labour for 100 0.1 5799.46
15794 2209 Carriage of Cement tonne 0.019 94.34
15839 2209 Carriage of Cement tonne 0.036 94.34
15880 2209 Carriage of Cement tonne 0.053 94.34
15915 2209 Carriage of Cement tonne 0.094 94.34
15961 2209 Carriage of Cement tonne 0.125 94.34
16849 2209 Carriage of Cement tonne 0.005 94.34
16893 2209 Carriage of Cement tonne 0.006 94.34
16927 2209 Carriage of Cement tonne 0.009 94.34
16980 2209 Carriage of Cement 94.34
17068 2209 Carriage of Cement tonne 0.024 94.34
17110 2209 Carriage of Cement tonne 0.026 94.34
17144 2209 Carriage of Cement tonne 0.032 94.34
17190 2209 Carriage of Cement tonne 0.037 94.34
17233 2209 Carriage of Cement tonne 0.042 94.34
17277 2209 Carriage of Cement tonne 0.049 94.34
17318 2209 Carriage of Cement tonne 0.055 94.34
17364 2209 Carriage of Cement tonne 0.061 94.34
17408 2209 Carriage of Cement tonne 0.068 94.34
21162 2209 Carriage of Cement tonne 0.0013 94.34
21200 2209 Carriage of Cement tonne 0.0019 94.34
21239 2209 Carriage of Cement tonne 0.012 94.34
21268 2209 Carriage of Cement tonne 0.016 94.34
21306 2209 Carriage of Cement tonne 0.025 94.34
21342 2209 Carriage of Cement tonne 0.028 94.34
21370 2209 Carriage of Cement tonne 0.034 94.34
21407 2209 Carriage of Cement tonne 0.049 94.34
21447 2209 Carriage of Cement tonne 0.012 94.34
21492 2209 Carriage of Cement 94.34
21532 2209 Carriage of Cement 94.34
21621 2209 Carriage of Cement tonne 0.028 94.34
21659 2209 Carriage of Cement tonne 0.034 94.34
21697 2209 Carriage
Carriage of
of Cement
dirt box tonne 0.049 94.34
7730 9977 strainer
Carriage of dirt box L.S. 26 2
7751 9977 strainer
Carriage of dirt box L.S. 26 2
7781 9977 strainer
Carriage of dirt box L.S. 39 2
7802 9977 strainer
pipes (k7) 100 mm dia L.S. 52 2
8951 Labour
Carriage of Fine sand (1
16853 part badarpur
2261 Carriage of Fine sand (1 cum 0.006 106.13
16984 2261 part badarpur
Carriage of Fine sand (1 106.13
17281 2261 part badarpur
Carriage of Fine sand (1 cum 0.066 106.13
17412 2261 part badarpur
Carriage of Fine sand (1 cum 0.092 106.13
21241 2261 Carriage
part badarpur
of Fine sand (1 cum 0.017 106.13
21280 2261 part badarpur
Carriage of Fine sand (1 cum 0.022 106.13
21308 2261 part badarpur
Carriage of Fine sand (1 cum 0.033 106.13
21380 2261 part badarpur
Carriage of Fine sand (1 cum 0.046 106.13
21449 2261 Carriage
part badarpur
of Fine sand (1 cum 0.017 106.13
21534 2261 part badarpur
Carriage of Fine sand (1 106.13
21661 2261 part badarpur
Carriage of Fine sand (1 cum 0.046 106.13
15796 2261 part
Carriage of Finesand
badarpur sand: 2(1 cum 0.01 106.13
15841 2261 Carriage
part badarpur
of Finesand
sand: 2(1 cum 0.019 106.13
15882 2261 part
Carriage of Fine sand: 2(1
badarpur sand cum 0.028 106.13
15917 2261 part badarpur
Carriage of Finesand
sand: 2(1 cum 0.05 106.13
15963 2261 part badarpur
Carriage of Finesand
sand: 2(1 cum 0.075 106.13
16897 2261 Carriage of Fine sand: 2(1
part badarpur sand cum 0.008 106.13
17071 2261 part badarpur
Carriage of Finesand
sand: 2(1 cum 0.033 106.13
17114 2261 part badarpur
Carriage of Finesand
sand: 2(1 cum 0.036 106.13
17158 2261 part badarpur
Carriage of Finesand
sand: 2(1 cum 0.043 106.13
17322 2261 Carriage of Fine sand: 2(1
part badarpur sand cum 0.074 106.13
17368 2261 part badarpur
Carriage of Finesand
sand: 2(1 cum 0.082 106.13
21164 2261 part badarpur
Carriage of Finesand
sand: 2(1 cum 0.001 106.13
21202 2261 part badarpur
Carriage of Finesand
sand: 2(1 cum 0.0014 106.13
21344 2261 Carriage
part badarpur
of Finesand
sand: 2(1 cum 0.037 106.13
21409 2261 part
Carriage of Fine sand: 2(1
badarpur sand cum 0.055 106.13
21496 2261 part badarpur
Carriage of Finesand
sand: 2(1 106.13
21623 2261 part badarpur sand : 2 cum 0.037 106.13
Carriage of Fine sand (1
21699 2261 part
part badarpur
badarpur sand
sand :: 2
2 cum 0.055 106.13
16930 2261 parts
part badarpur sand : 2 cum 0.012 106.13
17194 2261 parts
part badarpur sand : 2 cum 0.05 106.13
17237 2261 parts
Carriage of G.I. pipes cum 0.057 106.13
2113 2271 below
Carriage100
of mm dia
G.I. pipes tonne 0.014145 94.34
2139 2271 below
Carriage100
of mm dia
G.I. pipes tonne 0.018285 94.34
2176 2271 below 100 mm dia
Carriage of G.I. pipes tonne 0.02829 94.34
2201 2271 below
Carriage100
of mm dia
G.I. pipes tonne 0.036455 94.34
2238 2271 below
Carriage100
of mm dia
G.I. pipes tonne 0.041975 94.34
2275 2271 below
Carriage100
of mm dia
G.I. pipes tonne 0.059455 94.34
2303 2271 below 100 mm dia
Carriage of G.I. pipes tonne 0.014145 94.34
2343 2271 below
Carriage100
of mm dia
G.I. pipes tonne 0.018285 94.34
2390 2271 below
Carriage100
of mm dia
G.I. pipes tonne 0.012546 94.34
2427 below 100
2271 Carriage of mm dia
G.I. pipes tonne 0.016218 94.34
2454 2271 below 100 mm dia
Carriage of G.I. pipes tonne 0.025092 94.34
2492 2271 below
Carriage100
of mm dia
G.I. pipes tonne 0.032334 94.34
2527 2271 below
Carriage100
of mm dia
G.I. pipes tonne 0.03723 94.34
2553 below 100
2271 Carriage of mm dia
G.I. pipes tonne 0.052734 94.34
2591 2271 below 100 mm dia
Carriage of G.I. pipes tonne 0.067626 94.34
2628 2271 below
Carriage100
of mm dia
G.I. pipes tonne 0.088128 94.34
6453 2271 below 100 mm dia tonne 0.03723 94.34
19241 9977 Carriage of manhole cover L.S. 6.76 2
19277 9977 Carriage of manhole cover L.S. 6.76 2
19317 9977 Carriage of manhole cover L.S. 6.76 2
19343 9977 Carriage of manhole cover L.S. 6.76 2
19382 9977 Carriage of manhole cover L.S. 13.52 2
19412 9977 Carriage
Carriage of
of manhole cover L.S.
material and 13.52 2
19778 9977 fixing charges
Carriage Cement
of material and L.S. 13.39 2
19824 9977 fixing charges Cement L.S. 13.39 2
4040 9977 Carriage of materials L.S. 5.33 2
4066 9977 Carriage of materials L.S. 9.49 2
4101 9977 Carriage of materials L.S. 10.79 2
4136 9977 Carriage of materials L.S. 13.52 2
4162 9977 Carriage of materials L.S. 17.55 2
4198 9977 Carriage of materials L.S. 20.28 2
4235 9977 Carriage of materials L.S. 24.18 2
4261 9977 Carriage of materials L.S. 26.91 2
4296 9977 Carriage of materials L.S. 31.07 2
4322 9977 Carriage of materials L.S. 33.67 2
4357 9977 Carriage of materials L.S. 40.3 2
4408 9977 Carriage of materials L.S. 2.73 2
4440 9977 Carriage of materials L.S. 4.16 2
4463 9977 Carriage of materials L.S. 4.16 2
4496 9977 Carriage of materials L.S. 4.16 2
4519 9977 Carriage of materials L.S. 4.16 2
4552 9977 Carriage of materials L.S. 5.33 2
4575 9977 Carriage of materials L.S. 5.33 2
4609 9977 Carriage of materials L.S. 5.33 2
4632 9977 Carriage of materials L.S. 8.06 2
4665 9977 Carriage of materials L.S. 8.06 2
4698 9977 Carriage of materials L.S. 8.06 2
4721 9977 Carriage of materials L.S. 9.49 2
16330 9977 Carriage of materials L.S. 4.5 2
16380 9977 Carriage of materials L.S. 4.5 2
16436 9977 Carriage of materials L.S. 4.5 2
16493 9977 Carriage of materials L.S. 4.5 2
16550 9977 Carriage of materials L.S. 4.5 2
16605 9977 Carriage
Carriage of
of materials
materials and L.S. 4.5 2
2739 fixing charges
9988 Carriage of materials and L.S. 8.06 2
2756 9988 fixing charges
Carriage of materials and L.S. 9.49 2
2785 9988 fixing charges
Carriage of materials and L.S. 8.06 2
2802 9988 fixing charges
Carriage of materials and L.S. 9.49 2
2832 fixing charges
9988 Carriage of materials and L.S. 10.79 2
3217 9988 fixing charges
Carriage of materials and L.S. 18.85 2
3262 9988 fixing charges
Carriage of materials and L.S. 20.28 2
3306 9988 fixing charges
Carriage of materials and L.S. 40.3 2
3332 9988 Carriage
fixing charges
of materials and L.S. 47.19 2
3349 9988 fixing charges
Carriage of materials and L.S. 53.82 2
3461 9988 fixing charges
Carriage of materials and L.S. 6.76 2
7105 9988 fixing charges
Carriage of materials and L.S. 8.06 2
7142 9988 Carriage
fixing charges
of materials and L.S. 8.06 2
7169 9988 fixing charges
Carriage of materials and L.S. 8.06 2
7274 9988 fixing charges
Carriage of materials and L.S. 8.06 2
7293 9988 fixing charges
Carriage of materials and L.S. 8.06 2
7320 9988 Carriage
fixing charges
of materials and L.S. 8.06 2
7340 9988 fixing charges
Carriage of materials and L.S. 8.06 2
7369 9988 fixing charges
Carriage of materials and L.S. 9.49 2
7386 9988 fixing charges
Carriage of materials and L.S. 9.49 2
7406 9988 fixing charges
Carriage of materials and L.S. 8.06 2
7432 9988 fixing charges
Carriage of materials and L.S. 8.06 2
7451 9988 fixing charges
Carriage of materials and L.S. 4.16 2
7476 9988 fixing charges
Carriage of materials and L.S. 4.16 2
7498 9988 fixing charges
Carriage of materials and L.S. 4.16 2
7835 9988 fixing charges
Carriage of materials and L.S. 21.58 2
7853 9988 fixing charges
Carriage of materials and L.S. 26.91 2
7882 9988 fixing charges
Carriage of materials and L.S. 32.24 2
7900 9988 Carriage
fixing charges
of materials and L.S. 32.24 2
7929 9988 fixing charges
Carriage of materials and L.S. 32.24 2
7949 9988 fixing charges
Carriage of materials and L.S. 8.06 2
7976 9988 fixing charges L.S. 6.76 2
Carriage of materials and
7993 9988 fixing charges
Carriage of materials and L.S. 6.76 2
10203 9988 fixing charges
Carriage of materials and L.S. 12.22 2
10221 9988 fixing charges
Carriage of materials and L.S. 13.52 2
10240 9988 fixing charges
Carriage of materials and L.S. 3.38 2
10266 9988 fixing charges
Carriage of materials and L.S. 3.38 2
10283 9988 fixing charges
Carriage of materials and L.S. 3.38 2
11849 9988 fixing charges
Carriage of materials and L.S. 8.06 2
2865 fixing charges
Carriage of materials and L.S. 12.22 2
2894 fixing charges
Carriage of materials and L.S. 13.52 2
2912 fixing charges
Carriage of materials and L.S. 14.82 2
2940 fixing charges
Carriage of materials and L.S. 16.12 2
2958 fixing charges
Carriage of materials and L.S. 18.85 2
2978 fixing charges
Carriage of materials and L.S. 21.58 2
3006 fixing charges
Carriage of materials and L.S. 26.91 2
3024 fixing charges
Carriage of materials and L.S. 32.24 2
3054 fixing charges
Carriage of materials and L.S. 13.52 2
3070 fixing charges
Carriage of materials and L.S. 13.52 2
3098 fixing charges
Carriage of materials and L.S. 14.82 2
3114 fixing charges
Carriage of materials and L.S. 14.82 2
3142 fixing charges
Carriage of materials and L.S. 16.12 2
3158 fixing charges
Carriage of materials and L.S. 16.12 2
3184 fixing charges
Carriage of materials and L.S. 17.55 2
3200 fixing charges
Carriage of materials and L.S. 17.55 2
3242 fixing charges
Carriage of materials and L.S. 18.85 2
3287 fixing charges
Carriage of materials and L.S. 20.28 2
3379 fixing charges
Carriage of materials and L.S. 12.22 2
3395 fixing charges
Carriage of materials and L.S. 12.22 2
3425 fixing charges
Carriage of materials and L.S. 13.52 2
3441 fixing charges
Carriage of materials and L.S. 13.52 2
3489 fixing charges
Carriage of materials and L.S. 8.06 2
2657 9988 sundries
Carriage of materials and L.S. 5.33 2
2688 9988 sundries
Carriage of materials and L.S. 5.33 2
2708 9988 sundries
Carriage of materials and L.S. 5.33 2
6519 9988 sundries
Carriage of materials and L.S. 1.82 2
6539 9988 sundries
Carriage of materials and L.S. 1.82 2
6568 9988 sundries
Carriage of materials and L.S. 1.82 2
6588 9988 sundries
Carriage of materials and L.S. 1.82 2
6608 9988 sundries
Carriage of materials and L.S. 1.82 2
6637 9988 sundries
Carriage of materials and L.S. 1.82 2
6657 9988 sundries
Carriage of materials and L.S. 1.82 2
6686 9988 sundries
Carriage of materials and L.S. 1.82 2
6708 9988 sundries
Carriage of materials and L.S. 1.82 2
6738 9988 sundries
Carriage of materials and L.S. 1.82 2
6758 9988 sundries
Carriage of materials and L.S. 1.82 2
6787 9988 sundries L.S. 1.82 2
Carriage of materials and
6816 9988 sundries
Carriage of materials and L.S. 1.82 2
6836 9988 sundries
Carriage of materials and L.S. 1.82 2
6866 9988 sundries
Carriage of materials and L.S. 1.82 2
6886 9988 sundries
Carriage of materials and L.S. 1.82 2
1386 9999 sundries
Carriage of materials and L.S. 1.82 2
1414 9999 sundries
Carriage of metrial and L.S. 1.82 2
2847 9977 fixing charge L.S. 9.49 2
4388 2341 Carriage
Carriage of
of Pig
pipelead
Cutting tonne 0.1 94.34
19616 9977 charges
Carriage of pipe Cutting L.S. 1.43 2
19702 9977 charges
Carriage of R.C.C cover L.S. 1.82 2
19223 9977 with frame L.S. 6.76 2
20716 9977 Carriage of R.C.C. grating L.S. 7.15 2
20549 Carriage
Carriage of
of R.C.C.
R.C.C. grating
pipes L.S. 7.15 2
16845 100 mm dia
2275 Carriage Cement
of R.C.C. of 5
pipes 100 0.1 231.98
17314 2332 1000 mm dia
Carriage of R.C.C. pipes 100 0.1 7732.61
21340 2332 1000 mmofdia
Carriage R.C.C. pipes 100 metr 0.1 7732.61
21619 2332 1000 mmofdia
Carriage R.C.C. pipes 100 metr 0.1 7732.61
9755 1000 mmofdia
Carriage Labour
R.C.C. for
pipes 100 0.1 7732.61
17359 2333 1100 mm dia
Carriage of R.C.C. pipes 100 0.1 7732.61
9780 1100 mmofdia
Carriage Labour
R.C.C. for
pipes 100 0.1 7732.61
17403 2334 1200 mmofdia
Carriage R.C.C. pipes 100 0.1 7732.61
21368 2334 Carriage
1200 mmofdia R.C.C. pipes 100 metr 0.1 7732.61
21656 2334 1200 mm dia
Carriage of R.C.C. pipes 100 0.1 7732.61
9815 1200 mmofdia
Carriage Labour
R.C.C. for
pipes 100 0.1 7732.61
16879 2281 150 mm dia
Carriage of R.C.C. pipes 100 0.1 386.63
16922 2287 Carriage
250 mm diaof R.C.C. pipes 100 0.1 893.73
16976 2290 300 mm dia
Carriage of R.C.C. pipes
17063 2299 450 & 500
Carriage ofmm diapipes
R.C.C. 100 0.1 2577.54
17105 2299 450 & 500
Carriage ofmm diapipes
R.C.C. 100 0.1 2577.54
21236 2299 Carriage
450 & 500 ofmm diapipes
R.C.C. 100 0.1 2577.54
21445 2299 450 & 500 mm
Carriage of R.C.C.diapipes 100 metr 0.1 2577.54
17184 2303 600, 700,of750
Carriage & pipes
R.C.C. 100 0.1 3866.3
17227 2303 600, 700,of750
Carriage & pipes
R.C.C. 100 0.1 3866.3
21265 600, 700, 750 & 800
2303 Carriage of R.C.C. mm
pipes 100 0.1 3866.3
21487 2303 600, 700, 750&&800
600,700,750 800mmmm 3866.3
17139 2303 dia
Carriage of R.C.C. pipes 100 0.1 3866.3
17272 2331 900 mm dia
Carriage of R.C.C. pipes 100 0.1 5799.46
21304 900 mm dia
2331 Carriage of R.C.C. pipes 100 metr 0.1 5799.46
9720 900 mm dia
above 1200 mm Labour
dia for
and 100 0.1 5799.46
21404 2336 upto
Carriage of S.W. pipes 100 100 0.1 7732.61
15789 2224 mm dia of S.W. pipes 150
Carriage 100 0.33 141.51
15834 2225 Carriage
mm dia of S.W. pipes 200 100 0.33 283.01
15867 2226 mm dia Added
Carriage of S.W.10%
pipes 250 100 0.33 471.69
15910 2228 mm dia
Carriage of S.W. pipes 300 100 0.33 808.61
15956 2229 mm dia 100 0.33 1010.76
6100 2335 Carriage of Sand Labour: cum 1 106.13
4758 Carriage of sluice valves
4783 Carriage of sluice valves
4820 Carriage of sluice valves
4855 Carriage of sluice valves
4881 Carriage of sluice valves
4918 Carriage of sluice valves
4955 Carriage of sluice valves
4981 Carriage of sluice valves
5017 Carriage of sluice valves
5053 Carriage of sluice valves
5079 Carriage
Carriage of of sluice
sluice valves
valves
5115 wt.
Carriage of Spun iron S &=
= 303.4x10=3034kg
3684 S pipes of Spun iron S &
2319 Carriage 100 0.1 231.98
8624 2319 SCarriage pipes of Spun iron S & 100 0.05 231.98
3710 2320 SCarriage pipes of Spun iron S & 100 0.1 309.87
3780 2322 SCarriage pipes of Spun iron S & 100 0.1 628.92
8694 S pipes of Spun iron S &
2322 Carriage 100 0.05 628.92
8720 2323 SCarriage pipes of Spun iron S & 100 0.05 893.73
9948 2323 SCarriage pipes of Spun iron S & 100 0.05 893.73
3841 2324 SCarriage pipes of Spun iron S & 100 0.1 1104.66
8756 2324 Carriage
S pipes of Spun iron S & 100 0.05 1104.66
3868 2325 SCarriage pipes of Spun iron S & 100 0.1 1546.52
8781 2325 SCarriage pipes of Spun iron S & 100 0.05 1546.52
3903 2326 SCarriage pipes of Spun iron S & 100 0.1 2108.89
8816 2326 Carriage
S pipes of Spun iron S & 100 0.05 2108.89
3941 2327 SCarriage pipes of Spun iron S & 100 0.1 2577.54
8853 2327 SCarriage pipes of Spun iron S & 100 0.05 2577.54
3968 2328 SCarriage pipes of Spun iron S & 100 0.1 2577.54
8878 2328 Carriage
S pipes of Spun iron S & 100 0.05 2577.54
4004 2329 SCarriage pipes of Spun iron S & 100 0.1 3866.3
8912 2329 SCarriage pipes of Spun iron S & 100 0.05 3866.3
9374 SCarriage pipes of Spun iron S & 100 0.1 231.98
9400 SCarriage pipes of Spun iron S & 100 0.1 386.63
9435 SCarriage pipes of Spun iron S & 100 0.1 628.92
9461 SCarriage pipes of Spun iron S & 100 0.1 893.73
9496 SCarriagepipes of Spun iron S & 100 0.1 1104.66
9532 SCarriage
pipes of Spun iron S & 100 0.1 1546.52
9558 SCarriage
pipes of Spun iron S & 100 0.1 2108.89
9594 SCarriage
pipes of Spun iron S & 100 0.1 2577.54
9621 SCarriage
pipes of Spun iron S & 100 0.1 2577.54
9658 S pipes of Spun iron S &
Carriage 100 0.1 3866.3
9851 SCarriage
pipes of Spun iron S & 100 0.05 231.98
9877 SCarriage
pipes of Spun iron S & 100 0.05 386.63
9913 S pipes 100 0.05 628.92
Carriage of Spun iron S &
9974 SCarriage
pipes of Spun iron S & 100 0.05 1104.66
10010 SCarriage
pipes of Spun iron S & 100 0.05 1546.52
10036 SCarriage
pipes of Spun iron S & 100 0.05 2108.89
10070 SCarriage
pipes of Spun iron S & 100 0.05 2577.54
10106 SCarriage
pipes of Spun iron S & 100 0.05 2577.54
10132 SCarriage
pipes of Spun iron S & 100 0.05 3866.3
3745 2321 SCarriagepipes 150 mm dia
of Spun iron S & 100 0.1 386.63
8660 2321 SCarriagepipes 150 mm dia
of Spun iron S & 100 0.05 386.63
3806 2323 SCarriagepipes 250 mm dia Steel
of Stainless 100 0.1 893.73
12095 2272 pipes of Stainless Steel tonne
below
Carriage 0.00301 94.34
12134 2272 pipes Carriage of Stainless Steel tonne
below 0.00529 94.34
12051 2272 pipes below
Carriage 100 mmSteel
of Stainless dia tonne 0.0142 94.34
11879 pipes below
Carriage 100 mmSteel
of Stainless dia tonne 0.00301 94.34
11918 pipes below
Carriage 100 mmSteel
of Stainless dia tonne 0.00529 94.34
11945 pipes below 100 mm dia tonne
Carriage of Stainless Steel 0.00687 94.34
11983 pipes below
Carriage 100 mmSteel
of Stainless dia tonne 0.0098 94.34
12022 pipes below 100 mm dia tonne 0.0124 94.34
21160 9977 Carriage of trap L.S. 1.04 2
21198 9977 Carriage of trap L.S. 2.08 2
7619 9977 Carriage of water meter L.S. 26 2
7642 9977 Carriage of water meter L.S. 26 2
7675 9977 Carriage of water meter L.S. 39 2
7698 9977 Carriage of water meter L.S. 52 2
6428 9977 Carriage to site L.S. 13.52 2
6921 Carriage to site L.S. 179.4 2
6943 Carriage to siteLABOUR L.S.
other sundries 179.4 2
18925 9988 for Carriage,painting, and L.S. 1.82 2
18967 9988 other sundries
Carriage,painting, and L.S. 1.82 2
19049 9988 other sundries
Carriage,painting, and L.S. 1.82 2
19082 9988 Carrigeother sundries
of material and L.S. 1.82 2
6976 9988 fixing charges
Carrige of material and L.S. 11.57 2
6995 9988 fixing Carrigecharges
of material and L.S. 16.25 2
7024 9988 fixing Carrigecharges
of material and L.S. 13.91 2
7043 9988 fixing charges L.S. 11.57 2
6375 1472 Casing pipe 100 mm dia metre 0.12 335
6400 1472 Casing pipe 100 mm dia metre 0.12 335
6343 Casing pipe 100 mm dia metre 0.12 335
17966 cement
18185 cement
18374 cement
19653 cement
18816 cement : 3 fine sand )
18802 cement : 4 coarse sand)
19939 cement Cement :: 44 coarse
coarse sand)
sand) in
5162 foundations and plinth
Cement : 4 coarse sand) in
5462 foundations and plinth
Cement : 4 coarse sand) in
5534 foundations and plinth
Cement : 4coarse sand) in
5227 foundations and plinth
Cement : 4coarse sand) in
5310 foundations and plinth
Cement : 4coarse sand) in
5381 foundations
Cement concreteand plinth
1:2:4
19483 mix ( 1 cement : 2
Cement concrete 1:1.5:3coarse (
20780 1 cement : 1.5 coarse
Cement concrete 1:2:4 ( 1
19318 cement
Cement :concrete 1:2:4 ( 1
16399 4.2.3 cement
Cement :concrete sand (: 1 cum
2 coarse 1:2:4 0.008 6920.80
16347 cement
Cement :concrete
2 coarse 1:2:4
sand (: 1
16457 cement : 2 coarse
Cement concrete 1:2:4 sand (: 1
16511 cement
Cement :concrete
2 coarse 1:2:4
sand (: 1
16568 cement
Cement :concrete
2 coarse 1:2:4
sand (: 1
16623 cement :concrete
Cement 2 coarse 1:2:4
sand (: 1
19215 cement : 2 coarse
Cement concrete 1:2:4 sand (: 1
19242 cement
Cement :concrete
2 coarse 1:2:4
sand (: 1
19278 cement
Cement :concrete
2 coarse 1:2:4
sand (: 1
19344 cement :concrete
Cement 2 coarse 1:2:4
sand (: 1
19383 cement : 2 coarse
cement concrete 1:2:4 sand (: 1
19946 cement
cement :concrete
2 coarse1:2:4
sand (: 1
20023 cement
Cement :concrete
2 coarse 1:2:4
sand (: 1
20540 cement :concrete
Cement 2 coarse 1:2:4
sand (: 1
20602 cement : 2 coarse
Cement concrete 1:2:4 sand (: 1
20677 cement
Cement :concrete
2 coarse 1:2:4
sand (1
:
10364 cement
Cement :concrete 1:2:4 (1
18046 cement :concrete 1:2:4 (1
Cement
18266 cement
Cement :concrete 1:2:4 (1
18363 cement
Cement :concrete 1:2:4 (1
18516 cement
Cement :concrete 1:2:4 (1
17704 cement :concrete
Cement 2 coarse 1:2:4
sand (1
:
18421 cement : 2 coarse sand
Cement concrete 1:2:4 (1 :
18445 cement
Cement :concrete
2 coarse 1:2:4
sand (1
:
18618 cement
Cement :concrete
2 coarse 1:2:4
sand (1
:
18839 cement
Cement concrete 1:2:4 :
: 2 coarse sand
19530 mix ( 1 cement
Cement concrete : 21:2:4
coarse
19565 mix ( 1 cement
Cement concrete : 21:2:4(1
coarse
18255 cement
Cement :concrete
2 coarse 1:2:4(1
sand : 4
18353 cement : 2 coarse
Cement concrete 1:3:6 sand : 4
19011 (Cement
0.30x0.20x15
concrete 1:3:6 ( 1
18971 cement :
Cement concrete 1:3:6 ( 1
19086 cement
Cement :concrete 1:3:6 ( 1
19053 cement :concrete
Cement 3 coarse 1:3:6
sand (1
:
10405 cement :
Cement concrete 1:3:6 (1
18230 cement
Cement :concrete 1:3:6 (1
18929 cement :
Cement concrete 1:3:6 (1
18796 cement
Cement :concrete3 coarse 1:3:6
sand (1
:
10427 cement
Cement :concrete3 coarse 1:4:8
sand (1
:6
17692 cement
Cement concrete 1:5:10:
: 4 coarse sand
16438 4.1.11 (Cement1 cement : 5 fine1:5:10
concrete sand :
16331 (Cement
1 cement : 5 fine1:5:10
concrete sand :
16381 (Cement
1 cement : 5 fine1:5:10
concrete sand :
16494 (Cement
1 cement : 5 fine sand :
concrete 1:5:10
16551 (Cement
1 cement : 5 fine1:5:10
concrete sand :
16606 (Cement
1 cement : 5 fine1:5:10
concrete sand :
5304 (1 Cement
Cement :
concrete 1:5:10
5446 (1 Cement :
Cement concrete 1:5:10
5528 (1 Cement :
(1 Cement : 5 fine sand :
5221 10
(1 Cement : 5 fine sand :
5375 10
(1 cement : 5 fine sand :
19639 10
(1 cement : 5 fine sand :
19714 10
(1 cement : 5 fine sand :
20516 10
(1 cement : 5 fine sand :
20655 10
(1 cement : 5 fine sand :
20760 10
(1 cement : 5 fine sand :
20821 10
(1 cement : 5 fine sand :
20891 10
Cement for 50 joints =
15792 0.019 tonne
Cement mortar 1:2 for
22808 3.7 grout Cement mortar 1:2 for cum 0.025 4722.70
22843 3.7 grout Cement mortar 1:2 for cum 0.025 4722.70
22885 3.7 grout cement mortar 1:3 ( 1 cum 0.025 4722.70
18349 cement mortar
cement : 3 fine sand
1:4 ( 1)
20896 cement
cement mortar 1:4sand)
: 4 coarse (1
20978 cement : 4 coarse
cement mortar 1:4 (1 sand)
18135 cement
cement :mortar 1:4 (1
18236 cement mortar
cement : 1:4 (1
18720 cement : 4
cement mortar 1:4 (1
18181 cement
cement :mortar
4 coarse1:4sand
(1 )
10316 cement
cement :mortar
4 coarse1:4sand)
(1
16344 cement
cement mortar 1:4sand)
: 4 coarse (1
18336 cement : 4 coarse
cement mortar 1:4 (1 sand)
18672 cement
cement :mortar
4 coarse1:4sand)
(1
20261 Cement : 4 Coarse
cement mortar 1:5 ( 1 sand)
20996 cement
Cement :of 4 joints =
16977 4x0.00185
Cement of 4 joints =
17064 4x0.0041
Cement of=40.0164
joints =cum = metre
17106 4x0.0045
Cement of 4 joints = metre
17140 4x0.0054
Cement of 4 joints = metre
17187 4x0.0062
Cement of 4 joints =
17230 4x0.0072
Cement of 4 joints =
17273 4x0.0082 metre
Cement of 4 joints =
17315 4x0.0092
Cement of 4 joints =
17361 4x0.0103
Cement of 4 joints =
17404 4x0.0114
Cement of 5 joints = metre
16880 5x0.0008
Cement of 5 joints = metre
16923 5x0.0012
Cement of 50 joints = metre
15869 0.053
Cementtonne
of 50 joints =
15913 0.094
Cementtonne
of 50 joints =
15959 0.125 tonne
cement plaster 1:3 (1
18626 cement : 3 coarse sand)
11882 9999 Cement, sand and grit L.S. 2.73 2
11921 9999 Cement, sand and grit L.S. 2.73 2
11948 9999 Cement, sand and grit L.S. 4.16 2
11986 9999 Cement, sand and grit L.S. 4.16 2
12025 9999 Cement, sand and grit L.S. 5.33 2
12054 9999 Cement, sand and grit L.S. 5.33 2
19 Cement, sand and grit L.S. 2.73 2
53 Cement, sand and grit L.S. 2.73 2
77 Cement, sand and grit L.S. 2.73 2
112 Cement, sand and grit L.S. 4.16 2
149 Cement, sand and grit L.S. 5.33 2
173 Cement, sand and grit L.S. 5.33 2
544 Cement, Sand and grit L.S. 2.73 2
567 Cement, Sand and grit L.S. 2.73 2
600 Cement, Sand and grit L.S. 4.16 2
624 Cement, Sand and grit L.S. 5.33 2
659 Cement, Sand and grit L.S. 5.33 2
1546 9999 Cement, sand and grit etc. L.S. 4.16 2
2115 9999 Cement, sand and grit etc. L.S. 2.73 2
2141 9999 Cement, sand and grit etc. L.S. 2.73 2
2178 9999 Cement, sand and grit etc. L.S. 4.16 2
2203 9999 Cement, sand and grit etc. L.S. 4.16 2
2240 9999 Cement, sand and grit etc. L.S. 5.33 2
2277 9999 Cement, sand and grit etc. L.S. 5.33 2
1450 Cement, sand and grit etc. L.S. 2.73 2
1477 Cement, sand and grit etc. L.S. 2.73 2
1511 Cement, sand and grit etc. L.S. 2.73 2
1571 Cement, sand and grit etc. L.S. 5.33 2
1606 Cement, sand and grit etc. L.S. 5.33 2
18906 cement:
18450 13.9.1 cement.
19752 23 channel
10391 23 chases
chloride (CPVC) pipe 100
2032 8644 mm
chloride (CPVC) pipe 15 metre 10 1466.75
1437 8636 mm
chloride (CPVC) pipe 15 metre 10 48.55
1631 8636 mm metre 10 48.55
chloride (CPVC) pipe 15
1774 8636 mm
chloride (CPVC) pipe 150 metre 10 48.55
2068 8645 mm
chloride (CPVC) pipe 20 metre 10 3145.15
1473 8637 mm
chloride (CPVC) pipe 20 metre 10 77.8
1668 8637 mm
chloride (CPVC) pipe 20 metre 10 77.8
1811 8637 mm
chloride (CPVC) pipe 25 metre 10 77.8
1507 8638 mm
chloride (CPVC) pipe 25 metre 10 113.6
1705 8638 mm
chloride (CPVC) pipe 25 metre 10 113.6
1835 8638 mm
chloride (CPVC) pipe 32 metre 10 113.6
1532 8639 mm
chloride (CPVC) pipe 32 metre 10 163.65
1732 8639 mm
chloride (CPVC) pipe 32 metre 10 163.65
1871 8639 mm
chloride (CPVC) pipe 40 metre 10 163.65
1567 8640 mm
chloride (CPVC) pipe 40 metre 10 228.7
1908 8640 mm
chloride (CPVC) pipe 50 metre 10 228.7
1602 8641 mm
chloride (CPVC) pipe 50 metre 10 375.25
1934 8641 mm
chloride (CPVC) pipe metre 10 375.25
1969 8642 62.5mm
chloride (CPVC) pipe 75 metre 10 793.3
2006 8643 mm
diameter and 1.68 m metre 10 1031.05
20052 19.24.4 deep
1.68 m depth (up to 2.29
20253 19.25.4 m
diadepth)
with circular cover 600
20463 19.26.4 mm dia of
Circular grade
shape EHD
450 mm-
19275 7132 dia precast
Circular R.C.C.
shape 450 mm each 1 575
19272 19.19.1.3 internal shape
Circular diameter
500 mm
19341 7134 dia precast R.C.C.
Circular shape 500 mm each 1 575
19338 19.19.2.2 internal diameter
Circular shape 560 mm
18297 7135 dia precast R.C.C.
Circular shape 560 mm each 1 880
18395 7135 Circular
dia precast R.C.C.
shape 560 mm each 1 880
18639 7135 dia precast R.C.C.
Circular shape 560 mm each 1 880
18767 7135 dia precast
Circular R.C.C.
shape 560 mm each 1 880
19380 7135 dia precast
Circular R.C.C.
shape 560 mm each 1 880
19410 7136 dia precast R.C.C. each 1 1170
7446 18.58.1 Circular type
21055 class designation 7.5 Nos
4753 18.31.1.1 Class I
4815 18.31.2.1 Class I
4876 18.31.3.1 Class I
4950 18.31.4.1 Class I
5012 18.31.5.1 Class I
5074 18.31.6.1 Class I
4778 18.31.1.2 Class II
4850 18.31.2.2 Class II
4913 18.31.3.2 Class II
4976 18.31.4.2 Class II
5048 18.31.5.2 Class II
5110 18.31.6.2 Class II
3561 2309 class)
3592 2309 class)
Clearing eye with chain
19618 1336 and
Clearing lid 100
eyemm
withdia chain each 1 44
19704 1337 and lid 150
Coarse sand ; 4 graded mm dia each 1 50
5176 stone
Coarseaggregate sand ; 4 graded
5252 stone aggregate
Coarse sand ; 4 graded
5394 stone
Coarseaggregate sand ; 4 graded
5475 stone
coarseaggregate sand : 3 graded
17731 stone
coarseaggregate 20 mm
sand : 3 graded
17977 stone
coarseaggregate 20 mm
sand : 4 aggregate
20480 stone
coarse20 mm: 4nominal
sand graded
18076 stone
coarse sand (Zoneaggregate 20-III):
mm3
20327 aggregate
coarse sand stone 20 mm
8 : aggregate
19933 stone
coarse40 mmfinished
sand) nominalwith
17965 floatingsand)
coarse coat of neat with
finished
18184 floating coat
coarse sand) finished of neat with
18373 floating
coarse sand) coat of neat with
finished
19652 floating
Commoncoat of neat
burnt clay F.P.S.
21054 2602 (non modular) bricks 1000 0.145 5000
21440 complete
specification & above 50
23097 tonne
specification and up& group of
23143 two
specification or more and upto
23052 50MT
mm capacity
long, weighing not
7332 18.55.3 less than
3.14/4x(0.45)²x20 = 3.18
22839 cum
3.14/4x(0.50)²x20 = 3.925
22881 cum
3.14/4x(0.55)²x20 = 4.75
22922 cum
3.14/4x(0.75)²x20 = 10.88
22962 cum
3.14/4x(1.00)²x20 = 15.70
23004 cum
3.14/4x0.40²x20 = 2.51
21773 cum
3.14/4x0.45²x20 = 3.18
21811 cum
concrete 1:2:4 (1 cement :
18746 2
concrete coarse sand : 4 cement
1:2:4(1 graded :
18253 2
concrete coarse sand : 4 cement
1:2:4(1 graded :
18504 2
concrete coarse sand : 4 cement
1:2:4(1 graded :
18737 2
concrete 1:5:10 (1graded
coarse sand : 4 cement
19779 :concrete 5 fine sand : 10 graded
1:5:10 (1 cement
19825 :Concrete5 fine sand : 10 graded
3.14/4x0.45²x20
22073 =Concrete3.18 cum 3.14/4x0.50²x20
21842 =Concrete
3.925 cum 3.14/4x0.50²x20
22112 =Concrete
3.925cum 3.14/4x0.55²x20
21882 =Concrete
4.75 cum 3.14/4x0.60²x20
22153 =Concrete
5.65 cum 3.14/4x0.60²x20
22305 = 5.65 cum
Concrete 3.14/4x0.75²x15
21921 =Concrete
6.62 cum 3.14/4x0.75²x15
22193 =Concrete
6.62 cum 3.14/4x0.75²x15
22344 = 6.62 cum
Concrete 3.14/4x1.00²x10
21959 =Concrete
7.85 cum3.14/4x1.00²x10
22374 =Concrete
7.85 cum3.14/4x1.20²x9
22413 =Concrete
10.17 cum
3.14/4x1.2²x10
21997 =Concrete
10.17 cum
3.14/4x1.50²x9
22452 =Concrete
15.90 cum
3.14/4x1.5²x9 =
22028 15.90 cum
16334 Concrete around trap
16384 Concrete around trap
16497 Concrete around trap
16554 Concrete around trap
16609 Concrete
complete around trap
as per standard
20755 19.3 design:
complete as per standard
18457 19.11 design : as per standard
complete
18693 design : all complete as
19.13 cement,
18211 19.9 per neatstandard design : as
cement complete
17455 19.7 per withstandard
frame and design :
vertical
20648 19.29 grating
completecomplete as
as per standard
20563 19.28 with design :
frame complete as
20510 19.27 per standard design : as
neat cement complete
5362 18.35 per standard
cement design
complete as per
5145 18.32 standard design :
neat cement complete as
5517 18.37 neat per standard design : as
cement complete
5209 18.33 per standard
complete as perdesign :
standard
5434 18.36 design :
neat cement complete as
5281 18.34 per diameter anddesign
standard 1.20 m long
21109 19.33 complete as per standard
359 18 Coolie day 0.66 350.00
393 18 Coolie day 0.66 350.00
418 18 Coolie day 0.66 350.00
453 18 Coolie day 0.66 350.00
488 18 Coolie day 0.66 350.00
513 18 Coolie day 0.66 350.00
805 18 Coolie day 0.66 350.00
843 18 Coolie day 0.66 350.00
871 18 Coolie day 0.66 350.00
910 18 Coolie day 0.66 350.00
948 18 Coolie day 0.66 350.00
976 18 Coolie day 0.66 350.00
1009 18 Coolie day 0.66 350.00
1038 18 Coolie day 0.8 350.00
1077 18 Coolie day 0.8 350.00
1783 18 Coolie day 0.66 350.00
1820 18 Coolie day 0.66 350.00
1854 18 Coolie day 0.66 350.00
1880 18 Coolie day 0.66 350.00
1917 18 Coolie day 0.66 350.00
1943 18 Coolie day 0.66 350.00
1978 18 Coolie day 0.66 350.00
2015 18 Coolie day 0.66 350.00
2041 18 Coolie day 0.8 350.00
2077 18 Coolie day 1.2 350.00
2397 18 Coolie day 0.66 350.00
2434 18 Coolie day 0.66 350.00
2471 18 Coolie day 0.66 350.00
2499 18 Coolie day 0.66 350.00
2534 18 Coolie day 0.66 350.00
2570 18 Coolie day 0.66 350.00
2598 18 Coolie day 0.66 350.00
2635 18 Coolie day 0.66 350.00
6102 18 Coolie day 0.11 350.00
16660 18 Coolie day 0.36 350.00
16678 18 Coolie day 0.45 350.00
16706 18 Coolie day 0.51 350.00
16724 18 Coolie day 0.57 350.00
16751 18 Coolie day 0.63 350.00
16769 18 Coolie day 0.69 350.00
16795 18 Coolie day 0.75 350.00
16813 18 Coolie day 0.81 350.00
17507 18 Coolie day -0.41 350.00
17587 18 Coolie 350.00
17739 18 Coolie day -0.58 350.00
17822 18 Coolie 350.00
17988 18 Coolie day -0.62 350.00
18087 18 Coolie day -0.62 350.00
21095 18 Coolie day 3 350.00
5185 Coolie day -0.038 350.00
5261 Coolie day -0.32 350.00
5330 Coolie day -0.51 350.00
5412 Coolie day -0.77 350.00
5483 Coolie day -0.24 350.00
5556 Coolie day -0.41 350.00
20613 Coolie day -0.113 350.00
20688 Coolie day -0.113 350.00
20864 Coolie day -0.24 350.00
20928 Coolie day -0.32 350.00
18677 Cost for 0.61 metre
18689 Cost for 0.61 metre
18427 Cost for 0.76 metre
18453 Cost for 0.76 metre
19511 Cost for 1 connection
19558 Cost for 1 connection
19602 Cost for 1 connection
19140 Cost for 1 cover
19461 Cost for 1 cover
7794 Cost for 1 dirt box stainer
20250 Cost for 1 metre depth
15100 Cost for 1 no. 274.28
15117 Cost for 1 no. 383.99
15752 Cost for 1 no.
18957 Cost for 1 no. 312.93
18989 Cost for 1 no.
19027 Cost for 1 no.
19072 Cost for 1 no.
19115 Cost for 1 no.
19172 Cost for 1 no.
19194 Cost for 1 no.
19234 Cost for 1 no.
19270 Cost for 1 no.
19296 Cost for 1 no.
19336 Cost for 1 no.
19371 Cost for 1 no. 1010.56
19401 Cost for 1 no.
19440 Cost for 1 no.
19441 Cost for 1 no.
18428 Cost for 1.00 metre
18454 Cost for 1.00 metre
18678 Cost for 1.00 metre
18690 Cost for 1.00 metre
18898 Cost for 1.00 metre
18913 Cost for 1.00 metre
20249 Cost for 1.8 metre depth
18897 Cost for 1.88 metre
18912 Cost
Cost for
for 1.88 metre
10 dirt box
7824 stainer 11529.42
4421 Cost for 10 joints
4453 Cost for 10 joints
4486 Cost for 10 joints 2276.87
4509 Cost for 10 joints
4542 Cost for 10 joints
4565 Cost for 10 joints
4599 Cost for 10 joints 4198.37
4622 Cost for 10 joints
4655 Cost for 10 joints
4678 Cost for 10 joints
4711 Cost for 10 joints
4734 Cost for 10 joints
6140 Cost for 10 metre
6160 Cost for 10 metre
6180 Cost for 10 metre
6212 Cost for 10 metre
6232 Cost for 10 metre
6477 Cost for 10 metre
6931 Cost for 500 litre
6953 Cost for 500 litre
6499 Cost for one hand pump
4422 Cost for one joint
4454 Cost for one joint
4487 Cost for one joint 227.69
4510 Cost for one joint
4543 Cost for one joint
4566 Cost for one joint
4600 Cost for one joint 419.84
4623 Cost for one joint
4656 Cost for one joint
4679 Cost for one joint
4712 Cost for one joint
4735 Cost for one joint
6141 Cost for one metre
6161 Cost for one metre
6181 Cost for one metre
6213 Cost for one metre
6233 Cost for one metre
18144 Cost for one metre
18161 Cost for one metre
18190 Cost for one metre
18208 Cost for one metre
20151 Cost for one metre
20182 Cost for one metre 1005.45
6531 Cost for one no.
6551 Cost for one no.
6580 Cost for one no.
6600 Cost for one no.
6629 Cost for one no.
6649 Cost for one no.
6678 Cost for one no. 839.11
6698 Cost for one no.
6730 Cost for one no.
6750 Cost for one no.
6779 Cost for one no.
6799 Cost for one no.
6828 Cost for one no.
6848 Cost for one no.
6878 Cost for one no.
6898 Cost for one no.
20371 Cost for qne No. 1847.23
22830 Cost of 20 metre pile
22831 Cost of 1 metre pile
22873 Cost of 20 metre pile
22874 Cost of 1 metre pile
22914 Cost of 20 metre pile
22915 Cost of 1 metre pile
22953 Cost of 20 metre pile
22954 Cost of 1 metre pile
7541 Cost of 1 air valve
7574 Cost of 1 air valve
7597 Cost of 1 air valve
22686 Cost of 1 bulb
22721 Cost of 1 bulb
22747 Cost of 1 bulb
22782 Cost of 1 bulb
7773 Cost of 1 dirt box stainer 6484.1
1341 Cost of 1 each
1408 Cost of 1 each
1426 Cost of 1 each
10339 Cost of 1 hole
10385 Cost of 1 hole
8232 Cost of 1 joint
8254 Cost of 1 joint
8286 Cost of 1 joint
8318 Cost of 1 joint 198.83
8340 Cost of 1 joint
8372 Cost of 1 joint 288.37
8394 Cost of 1 joint
8426 Cost of 1 joint
8448 Cost of 1 joint
8480 Cost of 1 joint 747.88
8502 Cost of 1 joint
8533 Cost of 1 joint 1190.49
8555 Cost of 1 joint
8587 Cost of 1 joint 1683.7
8609 Cost of 1 joint
33 Cost of 1 metre
67 Cost of 1 metre
102 Cost of 1 metre 290.51
126 Cost of 1 metre
163 Cost of 1 metre
197 Cost of 1 metre 718.29
227 Cost of 1 metre
262 Cost of 1 metre
296 Cost of 1 metre 437.67
322 Cost of 1 metre
369 Cost of 1 metre
403 Cost of 1 metre
438 Cost of 1 metre 259.95
463 Cost of 1 metre
498 Cost of 1 metre
523 Cost of 1 metre
558 Cost of 1 metre
590 Cost of 1 metre
614 Cost of 1 metre
649 Cost of 1 metre
673 Cost of 1 metre
714 Cost of 1 metre
748 Cost of 1 metre
784 Cost of 1 metre 395.8
815 Cost of 1 metre
853 Cost of 1 metre
892 Cost of 1 metre 247.58
920 Cost of 1 metre
958 Cost of 1 metre
986 Cost of 1 metre
1019 Cost of 1 metre
1058 Cost of 1 metre 1093.39
1087 Cost of 1 metre
1464 Cost of 1 metre
1500 Cost of 1 metre 234.5
1525 Cost of 1 metre
1560 Cost of 1 metre
1595 Cost of 1 metre 542.1
1620 Cost of 1 metre
1661 Cost of 1 metre
1698 Cost of 1 metre
1725 Cost of 1 metre
1762 Cost of 1 metre
1804 Cost of 1 metre 153.07
1830 Cost of 1 metre
1864 Cost of 1 metre
1890 Cost of 1 metre
1927 Cost of 1 metre
1962 Cost of 1 metre 733.7
1988 Cost of 1 metre
2025 Cost of 1 metre
2061 Cost of 1 metre 2685.03
2087 Cost of 1 metre
2129 Cost of 1 metre
2165 Cost of 1 metre 278.19
2192 Cost of 1 metre
2227 Cost of 1 metre
2264 Cost of 1 metre 533.12
2291 Cost of 1 metre
2332 Cost of 1 metre
2376 Cost of 1 metre
2417 Cost of 1 metre 194.4
2444 Cost of 1 metre
2481 Cost of 1 metre
2518 Cost of 1 metre
2544 Cost of 1 metre
2580 Cost of 1 metre
2608 Cost of 1 metre
2645 Cost of 1 metre
10421 Cost of 1 metre
10443 Cost of 1 metre
11909 Cost of 1 metre 265.81
11938 Cost of 1 metre
11974 Cost of 1 metre
12003 Cost of 1 metre
12042 Cost of 1 metre
12081 Cost of 1 metre
12125 Cost of 1 metre
12165 Cost of 1 metre
15815 Cost of 1 metre
15859 Cost of 1 metre
15901 Cost of 1 metre
15946 Cost of 1 metre
15990 Cost of 1 metre 1461.06
16670 Cost of 1 metre
16697 Cost of 1 metre 40.35
16716 Cost of 1 metre
16743 Cost of 1 metre 45.5
16761 Cost of 1 metre
16779 Cost of 1 metre
16805 Cost of 1 metre
16823 Cost of 1 metre
16869 Cost of 1 metre
16913 Cost of 1 metre
17053 Cost of 1 metre 774.54
17087 Cost of 1 metre
17130 Cost of 1 metre
17174 Cost of 1 metre
17219 Cost of 1 metre
17262 Cost of 1 metre
17306 Cost of 1 metre
17349 Cost of 1 metre 4542.42
17384 Cost of 1 metre
17428 Cost of 1 metre
21797 Cost of 1 metre pile
21835 Cost of 1 metre pile
21875 Cost of 1 metre pile
21914 Cost of 1 metre pile
21983 Cost of 1 metre pile
22021 Cost of 1 metre pile
22059 Cost of 1 metre pile
22105 Cost of 1 metre pile
22146 Cost of 1 metre pile
22330 Cost of 1 metre pile
22369 Cost of 1 metre pile
22406 Cost of 1 metre pile
22447 Cost of 1 metre pile
22605 Cost of 1 metre pile
22645 Cost of 1 metre pile
6985 Cost of 1 no.
7004 Cost of 1 no.
7033 Cost of 1 no.
7052 Cost of 1 no.
7079 Cost of 1 no.
7095 Cost of 1 no.
7266 Cost of 1 no. 176.77
7283 Cost of 1 no.
7302 Cost of 1 no.
7329 Cost of 1 no.
7349 Cost of 1 no.
7378 Cost of 1 no.
7395 Cost of 1 no.
7424 Cost of 1 no. 104.52
7441 Cost of 1 no.
7470 Cost of 1 no.
7485 Cost of 1 no.
7507 Cost of 1 no.
12184 Cost of 1 no.
12210 Cost of 1 no. 84.29
12227 Cost of 1 no.
12244 Cost of 1 no.
12273 Cost of 1 no.
12289 Cost of 1 no. 240.83
12319 Cost of 1 no.
12336 Cost of 1 no.
12362 Cost of 1 no. 194
12379 Cost of 1 no.
12396 Cost of 1 no.
12423 Cost of 1 no.
12440 Cost of 1 no.
12467 Cost of 1 no. 484.33
12484 Cost of 1 no.
12511 Cost of 1 no. 517.78
12528 Cost of 1 no.
12556 Cost of 1 no. 548.55
12573 Cost of 1 no.
12588 Cost of 1 no.
12614 Cost of 1 no. 548.55
12634 Cost of 1 no.
12658 Cost of 1 no.
12674 Cost of 1 no.
12700 Cost of 1 no. 175.27
12716 Cost of 1 no.
12732 Cost of 1 no.
12765 Cost of 1 no.
12781 Cost of 1 no.
12805 Cost of 1 no.
12821 Cost of 1 no.
12847 Cost of 1 no. 155.2
12863 Cost of 1 no.
12895 Cost of 1 no. 198.01
12912 Cost of 1 no.
12927 Cost of 1 no.
12954 Cost of 1 no. 383.99
12971 Cost of 1 no. 461.59
12998 Cost of 1 no. 239.49
13018 Cost of 1 no.
13044 Cost of 1 no. 309.06
13060 Cost of 1 no.
13076 Cost of 1 no.
13102 Cost of 1 no.
13118 Cost of 1 no.
13148 Cost of 1 no. 239.49
13165 Cost of 1 no.
13191 Cost of 1 no. 365.26
13208 Cost of 1 no.
13225 Cost of 1 no.
13253 Cost of 1 no.
13270 Cost of 1 no.
13298 Cost of 1 no. 913.81
13315 Cost of 1 no.
13342 Cost of 1 no. 913.81
13359 Cost of 1 no.
13376 Cost of 1 no.
13403 Cost of 1 no.
13420 Cost of 1 no. 1186.75
13448 Cost of 1 no. 1186.75
13469 Cost of 1 no.
13486 Cost of 1 no.
13513 Cost of 1 no.
13530 Cost of 1 no.
13556 Cost of 1 no. 365.26
13573 Cost of 1 no.
13600 Cost of 1 no. 584.68
13617 Cost of 1 no.
13634 Cost of 1 no.
13663 Cost of 1 no.
13680 Cost of 1 no.
13708 Cost of 1 no. 913.81
13725 Cost of 1 no.
13742 Cost of 1 no.
13769 Cost of 1 no.
13786 Cost of 1 no.
13813 Cost of 1 no. 1186.75
13830 Cost of 1 no.
13858 Cost of 1 no. 1186.75
13875 Cost of 1 no.
13892 Cost of 1 no.
13924 Cost of 1 no.
13941 Cost of 1 no.
13967 Cost of 1 no. 267.59
13984 Cost of 1 no.
14001 Cost of 1 no.
14026 Cost of 1 no.
14043 Cost of 1 no.
14070 Cost of 1 no. 584.68
14087 Cost of 1 no.
14104 Cost of 1 no.
14131 Cost of 1 no.
14148 Cost of 1 no.
14175 Cost of 1 no. 913.81
14192 Cost of 1 no.
14220 Cost of 1 no. 913.81
14237 Cost of 1 no.
14256 Cost of 1 no.
14283 Cost of 1 no.
14300 Cost of 1 no.
14327 Cost of 1 no. 1186.75
14344 Cost of 1 no.
14375 Cost of 1 no. 254.21
14393 Cost of 1 no.
14412 Cost of 1 no.
14439 Cost of 1 no.
14458 Cost of 1 no.
14486 Cost of 1 no. 450.88
14504 Cost of 1 no. 547.22
14533 Cost of 1 no. 719.81
14551 Cost of 1 no. 770.65
14569 Cost of 1 no. 911.14
14598 Cost of 1 no. 1121.19
14616 Cost of 1 no.
14646 Cost of 1 no. 258.22
14664 Cost of 1 no.
14690 Cost of 1 no. 331.81
14708 Cost of 1 no.
14737 Cost of 1 no. 428.14
14754 Cost of 1 no. 616.79
14771 Cost of 1 no. 755.93
14797 Cost of 1 no.
14814 Cost of 1 no. 971.34
14841 Cost of 1 no. 1123.87
14858 Cost of 1 no. 1522.57
14889 Cost of 1 no. 313.08
14906 Cost of 1 no.
14934 Cost of 1 no. 394.69
14951 Cost of 1 no.
14968 Cost of 1 no.
14995 Cost of 1 no. 1170.7
15012 Cost of 1 no.
15042 Cost of 1 no. 200.69
15059 Cost of 1 no.
15083 Cost of 1 no. 255.55
15145 Cost of 1 no.
15162 Cost of 1 no. 639.53
15190 Cost of 1 no. 913.81
15207 Cost of 1 no. 913.81
15248 Cost of 1 no. 255.55
15450 Cost of 1 no. 383.99
15514 Cost of 1 no. 639.53
15579 Cost of 1 no.
15598 Cost of 1 no.
15612 Cost of 1 no.
15637 Cost of 1 no.
15651 Cost of 1 no.
15675 Cost of 1 no.
15689 Cost of 1 no.
15709 Cost of 1 no.
15737 Cost of 1 no.
8032 Cost of 1 quintal
8062 Cost of 1 quintal 8604.24
8084 Cost of 1 quintal
8113 Cost of 1 quintal 12414.69
8134 Cost of 1 quintal
8151 Cost of 1 quintal
8182 Cost of 1 quintal
8199 Cost of 1 quintal
4776 Cost of 1 valve
4812 Cost of 1 valve
4848 Cost of 1 valve
4873 Cost of 1 valve
4911 Cost of 1 valve
4947 Cost of 1 valve
4974 Cost of 1 valve
5009 Cost of 1 valve
5046 Cost of 1 valve
5071 Cost of 1 valve
5108 Cost of 1 valve
5133 Cost of 1 valve
7632 Cost of 1 water meter
7655 Cost of 1 water meter
7688 Cost of 1 water meter
7720 Cost of 1 water meter 8314.35
7743 Cost of 1 water meter
6441 Cost of 1.5 metre
7540 Cost of 10 air valves
7573 Cost of 10 air valves
7596 Cost of 10 air valves
10338 Cost of 10 holes
10384 Cost of 10 holes
4053 Cost of 10 joints
4088 Cost of 10 joints
4114 Cost of 10 joints
4149 Cost of 10 joints
4185 Cost of 10 joints 5863.65
4211 Cost of 10 joints
4248 Cost of 10 joints
4274 Cost of 10 joints
4309 Cost of 10 joints
4344 Cost of 10 joints
4370 Cost of 10 joints
32 Cost of 10 metre
66 Cost of 10 metre
101 Cost of 10 metre 2905.06
125 Cost of 10 metre
162 Cost of 10 metre
196 Cost of 10 metre 7182.88
226 Cost of 10 metre
261 Cost of 10 metre
295 Cost of 10 metre 4376.73
321 Cost of 10 metre
368 Cost of 10 metre
402 Cost of 10 metre
437 Cost of 10 metre 2599.49
462 Cost of 10 metre
497 Cost of 10 metre
522 Cost of 10 metre
557 Cost of 10 metre
589 Cost of 10 metre
613 Cost of 10 metre
648 Cost of 10 metre
672 Cost of 10 metre
713 Cost of 10 metre
747 Cost of 10 metre
783 Cost of 10 metre 3957.99
814 Cost of 10 metre
852 Cost of 10 metre
891 Cost of 10 metre 2475.8
919 Cost of 10 metre
957 Cost of 10 metre
985 Cost of 10 metre
1018 Cost of 10 metre
1057 Cost of 10 metre 10933.91
1086 Cost of 10 metre
1463 Cost of 10 metre
1499 Cost of 10 metre 2345
1524 Cost of 10 metre
1559 Cost of 10 metre
1594 Cost of 10 metre 5420.95
1619 Cost of 10 metre
1660 Cost of 10 metre
1697 Cost of 10 metre
1724 Cost of 10 metre
1761 Cost of 10 metre
1803 Cost of 10 metre 1530.68
1829 Cost of 10 metre
1863 Cost of 10 metre
1889 Cost of 10 metre
1926 Cost of 10 metre
1961 Cost of 10 metre 7336.96
1987 Cost of 10 metre
2024 Cost of 10 metre
2060 Cost of 10 metre 26850.27
2086 Cost of 10 metre
2128 Cost of 10 metre
2164 Cost of 10 metre 2781.87
2191 Cost of 10 metre
2226 Cost of 10 metre
2253 Cost of 10 metre
2290 Cost of 10 metre
2331 Cost of 10 metre
2375 Cost of 10 metre
2416 Cost of 10 metre 1943.96
2443 Cost of 10 metre
2480 Cost of 10 metre
2517 Cost of 10 metre
2543 Cost of 10 metre
2579 Cost of 10 metre
2607 Cost of 10 metre
2644 Cost of 10 metre
3697 Cost of 10 metre
3732 Cost of 10 metre 14722.57
3757 Cost of 10 metre
3793 Cost of 10 metre
3828 Cost of 10 metre
3854 Cost of 10 metre
3890 Cost of 10 metre
3916 Cost of 10 metre
3954 Cost of 10 metre
3990 Cost of 10 metre 117801.74
4017 Cost of 10 metre
5605 Cost of 10 metre
5637 Cost of 10 metre
5659 Cost of 10 metre
5691 Cost of 10 metre
5711 Cost of 10 metre
5741 Cost of 10 metre
5762 Cost of 10 metre
5790 Cost of 10 metre
5809 Cost of 10 metre
5838 Cost of 10 metre 101.05
5857 Cost of 10 metre
5886 Cost of 10 metre
5906 Cost of 10 metre
5924 Cost of 10 metre
5952 Cost of 10 metre
5970 Cost of 10 metre
5997 Cost of 10 metre 134.39
6015 Cost of 10 metre
6044 Cost of 10 metre
6062 Cost of 10 metre
6093 Cost of 10 metre
6261 Cost of 10 metre
6281 Cost of 10 metre
6299 Cost of 10 metre
8962 Cost of 10 metre
8986 Cost of 10 metre
9020 Cost of 10 metre
9055 Cost of 10 metre
9079 Cost of 10 metre
9114 Cost of 10 metre 36699.11
9138 Cost of 10 metre
9174 Cost of 10 metre
9199 Cost of 10 metre
9234 Cost of 10 metre
9270 Cost of 10 metre
9295 Cost of 10 metre
9329 Cost of 10 metre 163093.74
9354 Cost of 10 metre
9387 Cost of 10 metre
9422 Cost of 10 metre 15850.71
9448 Cost of 10 metre
9483 Cost of 10 metre 30308.27
9509 Cost of 10 metre
9545 Cost of 10 metre
9580 Cost of 10 metre 59302.77
9607 Cost of 10 metre
9644 Cost of 10 metre 86267.66
9671 Cost of 10 metre
9706 Cost of 10 metre
9741 Cost of 10 metre 156443.05
9766 Cost of 10 metre
9801 Cost of 10 metre 192055.31
9826 Cost of 10 metre
10420 Cost of 10 metre
10442 Cost of 10 metre
11898 Cost of 10 metre
11937 Cost of 10 metre
11973 Cost of 10 metre
12002 Cost of 10 metre
12041 Cost of 10 metre
12080 Cost of 10 metre
12124 Cost of 10 metre
12164 Cost of 10 metre
21982 Cost of 10 metre pile
22405 Cost of 10 metre pile
22604 Cost of 10 metre pile
22644 Cost of 10 metre pile
16012 Cost of 10 metres
16033 Cost of 10 metres
16063 Cost of 10 metres
16083 Cost of 10 metres 11433.22
16124 Cost of 10 metres
16179 Cost of 10 metres
16221 Cost of 10 metres
16272 Cost of 10 metres
16316 Cost of 10 metres
16669 Cost of 10 metres
16696 Cost of 10 metres 403.5
16715 Cost of 10 metres
16742 Cost of 10 metres 455.01
16760 Cost of 10 metres
16778 Cost of 10 metres
16804 Cost of 10 metres
16822 Cost of 10 metres
16868 Cost of 10 metres
16912 Cost of 10 metres
17052 Cost of 10 metres 7745.4
17086 Cost of 10 metres
17129 Cost of 10 metres
17173 Cost of 10 metres
17218 Cost of 10 metres
17261 Cost of 10 metres
17305 Cost of 10 metres
17348 Cost of 10 metres 45424.18
17383 Cost of 10 metres
17427 Cost of 10 metres
4775 Cost of 10 valves
4811 Cost of 10 valves
4847 Cost of 10 valves
4872 Cost of 10 valves
4910 Cost of 10 valves
4946 Cost of 10 valves
4973 Cost of 10 valves
5008 Cost of 10 valves
5035 Cost of 10 valves
5070 Cost of 10 valves
5107 Cost of 10 valves
5132 Cost of 10 valves
10481 Cost of 100 metre
10515 Cost of 100 metre 1081.11
10538 Cost of 100 metre
10568 Cost of 100 metre
10600 Cost of 100 metre 2196.05
10623 Cost of 100 metre
10656 Cost of 100 metre
10679 Cost of 100 metre
10716 Cost of 100 metre
10748 Cost of 100 metre 4199.84
10771 Cost of 100 metre
10803 Cost of 100 metre 5417.53
10825 Cost of 100 metre
10859 Cost of 100 metre
10879 Cost of 100 metre
10912 Cost of 100 metre
10932 Cost of 100 metre
10965 Cost of 100 metre
10985 Cost of 100 metre
11018 Cost of 100 metre
11038 Cost of 100 metre
11071 Cost of 100 metre
11091 Cost of 100 metre
11124 Cost of 100 metre
22368 Cost of 15 metre pile
21796 Cost of 20 metre pile
21834 Cost of 20 metre pile
21874 Cost of 20 metre pile
21913 Cost of 20 metre pile
22104 Cost of 20 metre pile
22145 Cost of 20 metre pile
22329 Cost of 20 metre pile
15814 Cost of 30 metre
15858 Cost of 30 metre
15900 Cost of 30 metre
15945 Cost of 30 metre
15989 Cost of 30 metre 43831.88
11166 Cost of 40.26 metre 7212.67
11197 Cost of 40.26 metre
11237 Cost of 40.26 metre
11279 Cost of 40.26 metre 8102.23
11310 Cost of 40.26 metre
11350 Cost of 40.26 metre
11390 Cost of 40.26 metre
11421 Cost of 40.26 metre
11462 Cost of 40.26 metre
11503 Cost of 40.26 metre
11534 Cost of 40.26 metre
11575 Cost of 40.26 metre
8646 Cost of 5 metre
8671 Cost of 5 metre
8706 Cost of 5 metre
8733 Cost of 5 metre
8769 Cost of 5 metre
8804 Cost of 5 metre
8829 Cost of 5 metre
8866 Cost of 5 metre
8900 Cost of 5 metre
8925 Cost of 5 metre
9864 Cost of 5 metre
9900 Cost of 5 metre 11319.92
9926 Cost of 5 metre
9961 Cost of 5 metre
9987 Cost of 5 metre
10023 Cost of 5 metre
10059 Cost of 5 metre
10083 Cost of 5 metre
10119 Cost of 5 metre
10155 Cost of 5 metre 83101.48
10179 Cost of 5 metre
3529 Cost of 5.14 quintal
8231 Cost of 50 joints
8253 Cost of 50 joints
8285 Cost of 50 joints
8307 Cost of 50 joints
8339 Cost of 50 joints
8371 Cost of 50 joints 14418.26
8393 Cost of 50 joints
8425 Cost of 50 joints
8447 Cost of 50 joints
8479 Cost of 50 joints 37394.07
8501 Cost of 50 joints
8532 Cost of 50 joints 59524.35
8554 Cost of 50 joints
8576 Cost of 50 joints
8608 Cost of 50 joints
6353 Cost of 6 metre
6385 Cost of 6 metre
6419 Cost of 6 metre 3037.2
3550 Cost of 7 quintal
22020 Cost of 9 metre pile
22058 Cost of 9 metre pile
22446 Cost of 9 metre pile
16373 Cost of each
16425 Cost of each 2101.12
16484 Cost of each 2094.41
16539 Cost of each 2118.71
16595 Cost of each 2202.7
16648 Cost of each 2227
16649 Cost of each 2227
17534 Cost of each
17682 Cost of each 9650.16
17764 Cost of each
17923 Cost of each
18023 Cost of each 26146.28
18123 Cost of each 26295.84
11607 Cost of each cut 68.84
11625 Cost of each cut
11643 Cost of each cut
11668 Cost of each cut
11686 Cost of each cut
11714 Cost of each cut 288.09
11732 Cost of each cut
11750 Cost of each cut
11778 Cost of each cut
11796 Cost of each cut
11821 Cost of each cut 573.75
11839 Cost
Cost of
of each cut 0.61m
manhole
20316 depth
8647 Cost of metre
8672 Cost of metre
8707 Cost of metre
16013 Cost of metre
16044 Cost of metre 848.12
16064 Cost of metre
16084 Cost of metre 1143.32
20560 Cost of one chamber
20644 Cost of one chamber 4887.16
20729 Cost of one chamber
20811 Cost of one chamber
20882 Cost of one chamber
20955 Cost of one chamber
2678 Cost of one connection 453.04
2700 Cost of one connection
6111 Cost
Cost of
of one
one cum.
drop
19689 connection
Cost of one drop 6999.74
19765 connection
Cost of one drop
19816 connection
Cost of one drop
19865 connection
4054 Cost of one joint
4089 Cost of one joint
4115 Cost of one joint
4150 Cost of one joint
4186 Cost of one joint 586.36
4212 Cost of one joint
4249 Cost of one joint
4284 Cost of one joint 948.77
4310 Cost of one joint
4345 Cost of one joint
4371 Cost of one joint
6932 Cost of one litre
6964 Cost of one litre 8.8
5206 Cost of one manhole
5278 Cost of one manhole
5359 Cost of one manhole 13212.46
5431 Cost of one manhole
5501 Cost of one manhole
5583 Cost of one manhole
18310 Cost of one manhole
18408 Cost of one manhole
18559 Cost of one manhole 18164.59
18652 Cost of one manhole
18789 Cost of one manhole
18874 Cost
Cost of
of one
one manhole
meter with
2729 stop cock.
3698 Cost of one metre
3733 Cost of one metre 1472.26
3758 Cost of one metre
3794 Cost of one metre
3829 Cost of one metre
3855 Cost of one metre
3891 Cost of one metre
3917 Cost of one metre
3955 Cost of one metre
3991 Cost of one metre 11780.17
4018 Cost of one metre
5606 Cost of one metre
5638 Cost of one metre
5660 Cost of one metre
5692 Cost of one metre
5712 Cost of one metre
5742 Cost of one metre
5763 Cost of one metre
5791 Cost of one metre
5810 Cost of one metre
5839 Cost of one metre 10.11
5858 Cost of one metre
5887 Cost of one metre
5907 Cost of one metre
5935 Cost of one metre 7.81
5953 Cost of one metre
5971 Cost of one metre
5998 Cost of one metre 13.44
6016 Cost of one metre
6045 Cost of one metre
6063 Cost of one metre
6094 Cost of one metre
6262 Cost of one metre
6282 Cost of one metre
6300 Cost of one metre
6354 Cost of one metre
6386 Cost of one metre
6420 Cost of one metre 506.2
6442 Cost of one metre
6478 Cost of one metre
11167 Cost of one metre 179.15
11198 Cost of one metre
11238 Cost of one metre
11280 Cost of one metre 201.25
11311 Cost of one metre
11351 Cost of one metre
11391 Cost of one metre
11422 Cost of one metre
11463 Cost of one metre
11504 Cost of one metre
11535 Cost of one metre
11576 Cost of one metre
8011 Cost of one no 130.48
19927 Cost of one no
19982 Cost of one no
20049 Cost of one no
20116 Cost of one no
20420 Cost of one no 2894.05
20460 Cost of one no
20507 Cost of one no
2748 Cost of one no.
2775 Cost of one no. 326.43
2794 Cost of one no.
2811 Cost of one no.
2841 Cost of one no.
2856 Cost of one no.
2885 Cost of one no. 581.25
2903 Cost of one no.
2921 Cost of one no.
2949 Cost of one no.
2967 Cost of one no.
2997 Cost of one no. 338.71
3015 Cost of one no.
3043 Cost of one no. 394
3063 Cost of one no.
3088 Cost of one no. 504.46
3107 Cost of one no.
3123 Cost of one no.
3151 Cost of one no.
3167 Cost of one no.
3193 Cost of one no.
3209 Cost of one no.
3235 Cost of one no.
3251 Cost of one no.
3280 Cost of one no.
3296 Cost of one no.
3324 Cost of one no. 295.15
3341 Cost of one no.
3358 Cost of one no.
3388 Cost of one no.
3404 Cost of one no.
3434 Cost of one no.
3450 Cost of one no.
3480 Cost of one no. 151.88
3498 Cost of one no.
7844 Cost of one no.
7873 Cost of one no.
7891 Cost of one no.
7920 Cost of one no.
7938 Cost of one no.
7968 Cost of one no. 155.36
7985 Cost of one no.
10212 Cost of one no.
10230 Cost of one no.
10258 Cost of one no. 49.18
10275 Cost of one no.
10302 Cost of one no. 113.4
11868 Cost of one no. 7781.61
21190 Cost of one no. 323.52
21218 Cost of one no.
3530 Cost of one quintal
3551 Cost of one quintal
3584 Cost of one quintal
3605 Cost of one quintal
3640 Cost of one quintal
3661 Cost of one quintal
4397 Cost of one quintal
21105 Cost of one soak pit
21150 Cost of one soak pit
8745 Cost per metre
8770 Cost per metre
8805 Cost per metre
8830 Cost per metre
8867 Cost per metre
8901 Cost per metre
8926 Cost per metre
8963 Cost per metre
8987 Cost per metre
9021 Cost per metre
9056 Cost per metre
9080 Cost per metre
9115 Cost per metre 3669.91
9139 Cost per metre
9175 Cost per metre
9210 Cost per metre 6021.98
9235 Cost per metre
9271 Cost per metre
9296 Cost per metre
9330 Cost per metre 16309.37
9355 Cost per metre
9388 Cost per metre
9423 Cost per metre 1585.07
9449 Cost per metre
9484 Cost per metre 3030.83
9510 Cost per metre
9546 Cost per metre
9581 Cost per metre 5930.28
9608 Cost per metre
9645 Cost per metre 8626.77
9672 Cost per metre
9707 Cost per metre
9742 Cost per metre 15644.31
9767 Cost per metre
9802 Cost per metre 19205.53
9827 Cost per metre
9865 Cost per metre
9901 Cost per metre 2263.98
9927 Cost per metre
9962 Cost per metre
9988 Cost per metre
10024 Cost per metre
10060 Cost per metre
10084 Cost per metre
10120 Cost per metre
10156 Cost per metre 16620.3
10180 Cost per metre
16125 Cost per metre
16180 Cost per metre
16222 Cost per metre
16273 Cost per metre
16317 Cost per metre
20986 Cost per metre
21005 Cost per metre
21035 Cost per metre
20317 Cost per metre depth
23062 Cost per test
23107 Cost per test
23153 Cost per test
23170 Cost per test 39469.16
23200 Cost per test
23216 Cost per test
23264 Cost per test 20069.06
23281 Cost per test 31575.33
23317 Cost per test
12170 Coupling/Socket
Coupling/Socket fittings
12174 8702 for 15.88 mm outer
Coupling/Socket dia SS
fittings each 1 59
12191 8786 for 22.22 mm outer
Coupling/Socket fittings dia SS each 1 63
12217 8787 for 28.58 mm outer
Coupling/Socket dia SS
fittings each 1 89
12234 8788 for 34.00 mm outer
Coupling/Socket dia SS
fittings each 1 131
12263 for 48.60
8789 for 42.70 mmmm outer
outer dia
dia SS
SS each 1 158
12280 8790 pip each 1 180
20492 cover with frame 0.85x0.70x0.15
20329 cover with frame
Item Number portion
18.41.1A of =(-)
6127 SH:Water
Item Number 18.41.1A of cum 0.75 1866.8
6157 SH:Water
Item Number 18.41.1A of cum 0.77 1866.8
18.41.1A of 6177 SH:Water cum 0.79 1866.8
6324 SH:Water cum 2.13 1866.8
16390 cum
16449 cum
16503 cum
18810 cum
5180 cum.
18238 Curved on plan
18337 Curved on plan
18721 Curved on plan
18803 Curved on plan
20262 Curved
complete onso plan
as to make it
10355 18.77 leak proof.
cm in walls including
10305 18.76 making
includinggood the same:
preparation of
23183 pile head etc for.
20.7 of piles in accordance
23189 7249 with IS in accordance
of piles per test 1 15000
23111 7250 with IS in accordance
of piles per test 1 23000
23204 7250 with IS in accordance
of piles per test 1 23000
23068 with IS in
7249 of piles peraccordance
test 1 15000 15000
23159 7251 with IS in
of piles peraccordance
test 1 29500 29500
23224 7251 with IS per test 1 29500 29500
16022 D
D += X
100 + 12 + 12 = 124
16003 mm
D or 12.4
= 150 + 16cm+ 16 = 182
16023 mm or 18.2 cm
D = 200 + 17 + 17 = 234
16054 mm or 23.4
D = 250 + 20cm+ 20X == 300
290
16074 mm or 29.0 cm
D1 = Depth = 100 + (½ x
16107 124)
D1 = =Depth
162 mm
= 150 + (½ x
16250 290)
1166 Beldar day 1.54 350.00
1168 Beldar day 1.2 350.00
1189 Beldar day 0.11 350.00
1287 Beldar day 0.11 350.00
1305 Beldar day 0.11 350.00
1369 Beldar day 0.11 350.00
1169 Coolie day 1.2 350.00
1165 Fitter (grade 1) day 0.58 505.17
1188 Fitter (grade 1) day 0.11 505.17
1286 Fitter (grade 1) day 0.11 505.17
1304 Fitter (grade 1) day 0.11 505.17
1368 Fitter
Deduct (grade 1)
= 0.45x0.45x2.925 day 0.11 505.17
21057 m = 0.59 cum
Deduct 2x0.20x0.20 m =
20674 (-) 0.08 sqm
Deduct arch ring and
20199 portion
Deduct archof pipering and
20214 portion of pipe
20842 Deduct cover
20922 Deduct
Deduct cover
cover : 0.61x0.455
20859 m
Deduct coversqm
= (-) 0.278 : 0.61x0.455
20934 m = (-) 0.278
Deduct for pipesqm
11135 1x40.26x3.14/4x(0.098)²
Deduct for pipe
11176 1x40.26x3.14/4x(0.118)²
Deduct for pipe
11207 1x40.26x3.14/4x(0.144)²
Deduct for pipe
11247 1x40.26x3.14/4x(0.17)²
Deduct for pipe
11289 1x40.26x3.14/4x(0.222)²
Deduct for pipe
11320 1x40.26x3.14/4x(0.274)²
Deduct for pipe
11358 1x40.26x3.14/4x(0.326)²
Deduct for pipe
11400 1x40.26x3.14/4x(0.378)²
Deduct for pipe
11441 1x40.26x3.14/4x(0.429)²
Deduct for pipe
11472 1x40.26x3.14/4x(0.48)²
Deduct for pipe
11513 1x40.26x3.14/4x(0.532)²
Deduct for pipe
11554 1x40.26x3.14/4x(0.635)²
20664 Deduct lintel portion
20597 Deduct
Deduct opening
Rate as per item
22807 5.1.3 no 5.1.3
Deduct Rate SH : asRCCper item cum -2.51 6315.20
22842 5.1.3 no 5.1.3 SH
Deduct Rate as : RCCper item cum -3.18 6315.20
22884 5.1.3 no 5.1.3 SH : RCC
Deduct Rate as per item cum -3.925 6315.20
22925 5.1.3 no 5.1.3Rate
Deduct SH : asRCCper item cum -4.75 6315.20
22965 5.1.3 no 5.1.3 SH : RCC
Deduct Rate as per item cum -10.88 6315.20
23007 5.1.3 no 5.1.3 SH : RCC cum -15.7 6315.20
16336 Deduct:
16386 Deduct:
16499 Deduct:
16556 Deduct:
16611 Deduct:
demolishing Dismantling
20276 cemnet concrete
Demolishing) 1:2:4
Dismantling
20260 IInd class brick@work
Depreciation 2% ofinthe
6341 cost of casing@
Depreciation pipe
2%6metre
of the
6373 cost of casing pipe 6metre
Depreciation @ 2% of the
6398 cost of casing pipe 6metre
6072 Depth of sand filling
6117 Depth of sand filling
6147 Depth of sand filling
6167 Depth of sand filling
6219 Depth of sand filling
6268 Depth of sand filling
6288 Depth of sand filling
21233 Detail for 10 metre
21262 Detail for 10 metre
21301 Detail for 10 metre
21337 Detail for 10 metre
21365 Detail for 10 metre
21401 Detail for 10 metre
21442 Detail for 10 metre
21527 Detail for 10 metre
21616 Detail for 10 metre
21653 Detail for 10 metre
21682 Detail for 10 metre
21256 Detail of cost for 10 metre
21295 Detail of cost for 10 metre
21331 Detail of cost for 10 metre 45347.36
21359 Detail of cost for 10 metre
21395 Detail of cost for 10 metre
21434 Detail of cost for 10 metre 135191.88
21464 Detail of cost for 10 metre
21610 Detail of cost for 10 metre
21647 Detail of cost for 10 metre 78576.27
21676 Detail of cost for 10 metre
21713 Detail of cost for 10 metre
5912 Detail of cost for 10 sqm
5940 Detail of cost for 10 sqm
5958 Detail of cost for 10 sqm
5976 Detail of cost for 10 sqm
6003 Detail of cost for 10 sqm
6021 Detail of cost for 10 sqm
11612 Detail of cost for one cut.
11630 Detail of cost for one cut.
11646 Detail of cost for one cut.
11673 Detail of cost for one cut.
11691 Detail of cost for one cut.
11719 Detail of cost for one cut.
11737 Detail of cost for one cut.
11765 Detail of cost for one cut.
11783 Detail of cost for one cut.
11799 Detail of cost for one cut.
11826 Detail
Detail of
of cost
cost for one m
of 0.76 cut.
18416 depth
extra depth Brick work
18903 with
Detaila of cost of one
16376 gully tarp
22691 Details of cost for 1 bulb.
22724 Details
Details of
of cost
cost for
for 1
1 bulb.
17690 manhole
Details of cost for 1
17767 manhole
Details of cost for 1
18228 manhole
Details of cost for 1
18794 manhole
manhole Cement
17537 concrete 1:4:8
2844 Details of cost for 1 No.
7083 Details of cost for 1 no.
7102 Details of cost for 1 no.
7139 Details of cost for 1 no.
7166 Details of cost for 1 no.
7271 Details of cost for 1 no.
7290 Details of cost for 1 no.
7317 Details of cost for 1 no.
7383 Details of cost for 1 no.
7429 Details of cost for 1 no.
7448 Details of cost for 1 no.
7473 Details of cost for 1 no.
7493 Details of cost for 1 no.
12172 Details of cost for 1 no.
12189 Details of cost for 1 no.
12215 Details of cost for 1 no.
12232 Details of cost for 1 no.
12278 Details of cost for 1 no.
12307 Details of cost for 1 no.
12324 Details of cost for 1 no.
12341 Details of cost for 1 no.
12367 Details of cost for 1 no.
12384 Details of cost for 1 no.
12411 Details of cost for 1 no.
12428 Details of cost for 1 no.
12445 Details of cost for 1 no.
12472 Details of cost for 1 no.
12489 Details of cost for 1 no.
12516 Details of cost for 1 no.
12533 Details of cost for 1 no.
12561 Details of cost for 1 no.
12576 Details of cost for 1 no.
12603 Details of cost for 1 no.
12623 Details of cost for 1 no.
12647 Details of cost for 1 no.
12663 Details of cost for 1 no.
12679 Details of cost for 1 no.
12705 Details of cost for 1 no.
12721 Details of cost for 1 no.
12754 Details of cost for 1 no.
12770 Details of cost for 1 no.
12794 Details of cost for 1 no.
12810 Details of cost for 1 no.
12826 Details of cost for 1 no.
12852 Details of cost for 1 no.
12874 Details of cost for 1 no.
12900 Details of cost for 1 no.
12915 Details of cost for 1 no.
12942 Details of cost for 1 no.
12959 Details of cost for 1 no.
12976 Details of cost for 1 no.
13007 Details of cost for 1 no.
13023 Details of cost for 1 no.
13049 Details of cost for 1 no.
13065 Details of cost for 1 no.
13107 Details of cost for 1 no.
13127 Details of cost for 1 no.
13153 Details of cost for 1 no.
13170 Details of cost for 1 no.
13196 Details of cost for 1 no.
13213 Details of cost for 1 no.
13258 Details of cost for 1 no.
13275 Details of cost for 1 no.
13303 Details of cost for 1 no.
13320 Details of cost for 1 no.
13347 Details of cost for 1 no.
13364 Details of cost for 1 no.
13408 Details of cost for 1 no.
13425 Details of cost for 1 no.
13457 Details of cost for 1 no.
13474 Details of cost for 1 no.
13501 Details of cost for 1 no.
13518 Details of cost for 1 no.
13535 Details of cost for 1 no.
13561 Details of cost for 1 no.
13578 Details of cost for 1 no.
13605 Details of cost for 1 no.
13622 Details of cost for 1 no.
13668 Details of cost for 1 no.
13685 Details of cost for 1 no.
13713 Details of cost for 1 no.
13730 Details of cost for 1 no.
13757 Details of cost for 1 no.
13774 Details of cost for 1 no.
13791 Details of cost for 1 no.
13818 Details of cost for 1 no.
13835 Details of cost for 1 no.
13863 Details of cost for 1 no.
13880 Details of cost for 1 no.
13912 Details of cost for 1 no.
13929 Details of cost for 1 no.
13946 Details of cost for 1 no.
13972 Details of cost for 1 no.
13989 Details of cost for 1 no.
14014 Details of cost for 1 no.
14031 Details of cost for 1 no.
14048 Details of cost for 1 no.
14075 Details of cost for 1 no.
14092 Details of cost for 1 no.
14119 Details of cost for 1 no.
14136 Details of cost for 1 no.
14153 Details of cost for 1 no.
14180 Details of cost for 1 no.
14197 Details of cost for 1 no.
14225 Details of cost for 1 no.
14244 Details of cost for 1 no.
14271 Details of cost for 1 no.
14288 Details of cost for 1 no.
14305 Details of cost for 1 no.
14332 Details of cost for 1 no.
14353 Details of cost for 1 no.
14380 Details of cost for 1 no.
14426 Details of cost for 1 no.
14445 Details of cost for 1 no.
14463 Details of cost for 1 no.
14491 Details of cost for 1 no.
14509 Details of cost for 1 no.
14538 Details of cost for 1 no.
14556 Details of cost for 1 no.
14585 Details of cost for 1 no.
14603 Details of cost for 1 no.
14634 Details of cost for 1 no.
14651 Details of cost for 1 no.
14669 Details of cost for 1 no.
14695 Details of cost for 1 no.
14713 Details of cost for 1 no.
14742 Details of cost for 1 no.
14759 Details of cost for 1 no.
14785 Details of cost for 1 no.
14802 Details of cost for 1 no.
14819 Details of cost for 1 no.
14846 Details of cost for 1 no.
14867 Details of cost for 1 no.
14894 Details of cost for 1 no.
14911 Details of cost for 1 no.
14939 Details of cost for 1 no.
14956 Details of cost for 1 no.
14973 Details of cost for 1 no.
15000 Details of cost for 1 no.
15021 Details of cost for 1 no.
15047 Details of cost for 1 no.
15062 Details of cost for 1 no.
15088 Details of cost for 1 no.
15105 Details of cost for 1 no.
15150 Details of cost for 1 no.
15167 Details of cost for 1 no.
15195 Details of cost for 1 no.
15587 Details of cost for 1 no.
15601 Details of cost for 1 no.
15626 Details of cost for 1 no.
15640 Details of cost for 1 no.
15654 Details of cost for 1 no.
15678 Details of cost for 1 no.
15697 Details of cost for 1 no.
15725 Details of cost for 1 no.
15740 Details
Details of
of cost
cost for
for 1
1 no.
no.
7748 dirt box stainer
Details of cost for 1 no.
7778 dirt boxofstainer
Details cost for 1
3558 quintal
Details of cost for 1
3589 quintal
Details of cost for 1
3624 quintal
Details of cost for 1
3645 quintal
Details of cost for 1
4385 quintal
Details of cost for 1
8018 quintal
Details of cost for 1
8037 quintal
Details of cost for 1
8069 quintal
Details of cost for 1
8089 quintal
Details of cost for 1
8120 quintal
Details of cost for 1
8137 quintal
Details of cost for 1
8168 quintal
Details of cost for 1
8185 quintal
23047 Details of cost for 1 test
23067 Details of cost for 1 test
23110 Details of cost for 1 test
23138 Details of cost for 1 test
23158 Details of cost for 1 test
23188 Details of cost for 1 test
23203 Details of cost for 1 test
23223 Details of cost for 1 test
23269 Details
Details of
of cost
cost for
for 1
10test
10309 holes
Details of cost for 10
4033 joints
Details of cost for 10
4059 joints
Details of cost for 10
4094 joints
Details of cost for 10
4120 joints
Details of cost for 10
4155 joints
Details of cost for 10
4191 joints
Details of cost for 10
4217 joints
Details of cost for 10
4254 joints
Details of cost for 10
4289 joints
Details of cost for 10
4315 joints
Details of cost for 10
4350 joints
Details of cost for 10
4404 joints
Details of cost for 10
4436 joints
Details of cost for 10
4459 joints
Details of cost for 10
4492 joints
Details of cost for 10
4515 joints
Details of cost for 10
4548 joints
Details of cost for 10
4571 joints
Details of cost for 10
4605 joints
Details of cost for 10
4628 joints
Details of cost for 10
4661 joints
Details of cost for 10
4684 joints
Details of cost for 10
4717 joints
Details of cost for 10 m
21957 length
Details of
of pile
cost for 10 m
22372 length of pile
Details of cost for 10
14 metre
Details of cost for 10
72 metre
Details of cost for 10
107 metre
Details of cost for 10
168 metre
Details of cost for 10
206 metre
Details of cost for 10
241 metre
Details of cost for 10
265 metre
Details of cost for 10
301 metre
Details of cost for 10
349 metre
Details of cost for 10
374 metre
Details of cost for 10
408 metre
Details of cost for 10
443 metre
Details of cost for 10
468 metre
Details of cost for 10
503 metre
Details of cost for 10
538 metre
Details of cost for 10
561 metre
Details of cost for 10
593 metre
Details of cost for 10
617 metre
Details of cost for 10
652 metre
Details of cost for 10
717 metre
Details of cost for 10
751 metre
Details of cost for 10
998 metre
Details of cost for 10
1435 metre
Details of cost for 10
1505 metre
Details of cost for 10
1530 metre
Details of cost for 10
1565 metre
Details of cost for 10
1600 metre
Details of cost for 10
1629 metre
Details of cost for 10
1666 metre
Details of cost for 10
1703 metre
Details of cost for 10
1730 metre
Details of cost for 10
1809 metre
Details of cost for 10
1833 metre
Details of cost for 10
1869 metre
Details of cost for 10
1906 metre
Details of cost for 10
1932 metre
Details of cost for 10
1967 metre
Details of cost for 10
2030 metre
Details of cost for 10
2066 metre
Details of cost for 10
2134 metre
Details of cost for 10
2170 metre
Details of cost for 10
2195 metre
Details of cost for 10
2232 metre
Details of cost for 10
2269 metre
Details of cost for 10
2298 metre
Details of cost for 10
2337 metre
Details of cost for 10
2385 metre
Details of cost for 10
2422 metre
Details of cost for 10
2449 metre
Details of cost for 10
2486 metre
Details of cost for 10
2521 metre
Details of cost for 10
2547 metre
Details of cost for 10
2585 metre
Details of cost for 10
3677 metre
Details of cost for 10
3703 metre
Details of cost for 10
3738 metre
Details of cost for 10
3773 metre
Details of cost for 10
3799 metre
Details of cost for 10
3834 metre
Details of cost for 10
3860 metre
Details of cost for 10
3896 metre
Details of cost for 10
3933 metre
Details of cost for 10
3960 metre
Details of cost for 10
3996 metre
Details of cost for 10
5621 metre
Details of cost for 10
5643 metre
Details of cost for 10
5675 metre
Details of cost for 10
5695 metre
Details of cost for 10
5725 metre
Details of cost for 10
5749 metre
Details of cost for 10
5796 metre
Details of cost for 10
5815 metre
Details of cost for 10
5844 metre
Details of cost for 10
5863 metre
Details of cost for 10
5894 metre
Details of cost for 10
6050 metre
Details of cost for 10
8968 metre
Details of cost for 10
9002 metre
Details of cost for 10
9026 metre
Details of cost for 10
9061 metre
Details of cost for 10
9085 metre
Details of cost for 10
9120 metre
Details of cost for 10
9180 metre
Details of cost for 10
9215 metre
Details of cost for 10
9240 metre
Details of cost for 10
9276 metre
Details of cost for 10
9301 metre
Details of cost for 10
9335 metre
Details of cost for 10
9358 metre
Details of cost for 10
9393 metre
Details of cost for 10
9428 metre
Details of cost for 10
9454 metre
Details of cost for 10
9489 metre
Details of cost for 10
9551 metre
Details of cost for 10
9586 metre
Details of cost for 10
9613 metre
Details of cost for 10
9650 metre
Details of cost for 10
9712 metre
Details of cost for 10
9747 metre
Details of cost for 10
9772 metre
Details of cost for 10
9807 metre
Details of cost for 10
11875 metre
Details of cost for 10
11914 metre
Details of cost for 10
11941 metre
Details of cost for 10
11979 metre
Details of cost for 10
12018 metre
Details of cost for 10
12047 metre
Details of cost for 10
12088 metre
Details of cost for 10
12128 metre
Details of cost for 10
16018 metre
Details of cost for 10
16049 metre
Details of cost for 10
16069 metre
Details of cost for 10
16657 metre
Details of cost for 10
16675 metre
Details of cost for 10
16703 metre
Details of cost for 10
16721 metre
Details of cost for 10
16748 metre
Details of cost for 10
16766 metre
Details of cost for 10
16792 metre
Details of cost for 10
16810 metre
Details of cost for 10
16874 metre
Details of cost for 10
16918 metre
Details of cost for 10
16971 metre
Details of cost for 10
17058 metre
Details of cost for 10
17092 metre
Details of cost for 10
17135 metre
Details of cost for 10
17179 metre
Details of cost for 10
17222 metre
Details of cost for 10
17267 metre
Details of cost for 10
17309 metre
Details of cost for 10
17354 metre
Details of cost for 10
16183 metre
Detailslength
of costpipe
for 10
16276 metre Perimeter
metre length pipe= 0.0673
5590 metre
Details of cost for 10
10426 metres
Details of cost for 10
22492 metres
Details of cost for 10
22535 metres
Details of cost for 10
22576 metres
Details of cost for 10
22616 metres
Details of cost for 10
10390 metres Labour
Details of for 10
cost for making
no.
7523 double acting air valves
Details of cost for 10 no.
7546 double acting
Details of costair
forvalves
10 no.
7579 double
Details of cost forvalves
acting air 10
4754 sluice valves
Details of cost for 10
4779 sluice
Detailsvalves
of cost for 10
4816 sluice valves
Details of cost for 10
4851 sluice
Detailsvalves
of cost for 10
4877 sluice valves
Details of cost for 10
4914 sluice
Detailsvalves
of cost for 10
4951 sluice valves
Details of cost for 10
4977 sluice valves
Details of cost for 10
5013 sluice
Detailsvalves
of cost for 10
5049 sluice valves
Details of cost for 10
5075 sluice valves
Details of cost for 10
5111 sluice valves
Details of cost for 100
10463 metres
Details of cost for 100
10486 metres
Details of cost for 100
10520 metres
Details of cost for 100
10541 metres
Details of cost for 100
10573 metres
Details of cost for 100
10605 metres
Details of cost for 100
10628 metres
Details of cost for 100
10661 metres
Details of cost for 100
10721 metres
Details of cost for 100
10753 metres
Details of cost for 100
10776 metres
Details of cost for 100
10810 metres
Details of cost for 100
10864 metres
Details of cost for 100
10917 metres
Details of cost for 100
10970 metres
Details of cost for 100
11023 metres
Details of cost for 100
11076 metres
Details of cost for 15 m
21919 length
Details of
of pile
cost for 15 m
22191 length
Details of pile
of cost for 15 m
22342 length of pile
1383 Details of cost for 1No.
1411 Details
Details of
of cost
cost for
for 1No.
20 m
21771 length of
Details of pile
cost for 20 m
21809 length
Details of
of pile
cost for 20 m
21840 length of pile
Details of cost for 20 m
21880 length of pile
Details of cost for 20 m
22071 length
Details of
of pile
cost for 20 m
22110 length of pile
Details of cost for 20 m
22151 length
Details of
of pile
cost for 20 m
22303 length of pile
Details of cost for 20 m
22837 length
Details of
of pile
cost for 20 m
22879 length of pile
Details of cost for 20 m
22920 length
Details of
of pile
cost for 20 m
22960 length of pile
Details of cost for 20 m
23002 length
Details of
of pile
cost for 30
15784 metre
Details of cost for 30
15862 metre
Details of cost for 30
15906 metre
Details of cost for 30
15951 metre
Details of cost for 40.26 m
11172 or 11 nos.
Details joints.
of cost forEarth
40.26 m
11203 or 11 nos. joints. Earth
Details of cost for 40.26 m
11243 or 11 nos.
Details joints.
of cost forEarth
40.26 m
11285 or 11 nos. joints. Earth
Details of cost for 40.26 m
11316 or 11 nos.
Details joints.
of cost forEarth
40.26 m
11354 or 11 nos. joints. Earth
Details of cost for 40.26 m
11396 or 11 nos.
Details joints.
of cost forEarth
40.26 m
11468 or 11 nos. joints. Earth
Details of cost for 40.26 m
11509 or 11 nos.
Details joints.
of cost forEarth
40.26 m
11550 or 11 nos. joints. Earth
8616 Details of cost for 5 metre
8652 Details of cost for 5 metre
8677 Details of cost for 5 metre
8712 Details of cost for 5 metre
8748 Details of cost for 5 metre
8773 Details of cost for 5 metre
8808 Details of cost for 5 metre
8845 Details of cost for 5 metre
8870 Details of cost for 5 metre
8904 Details of cost for 5 metre
9844 Details of cost for 5 metre
9870 Details of cost for 5 metre
9906 Details of cost for 5 metre
9932 Details of cost for 5 metre
9967 Details of cost for 5 metre
10003 Details of cost for 5 metre
10029 Details of cost for 5 metre
10063 Details of cost for 5 metre
10125 Details of cost for 5 metre
10161 Details
Details of
of cost
cost for
for 5 metre
5.14
3503 quintal
Details of cost for 50
8215 Joints
Details of cost for 50
8237 Joints
Details of cost for 50
8269 Joints
Details of cost for 50
8291 Joints
Details of cost for 50
8323 Joints
Details of cost for 50
8345 Joints
Details of cost for 50
8377 Joints
Details of cost for 50
8399 Joints
Details of cost for 50
8431 Joints
Details of cost for 50
8453 Joints
Details of cost for 50
8485 Joints
Details of cost for 50
8507 Joints
Details of cost for 50
8538 Joints
Details of cost for 50
8560 Joints
Details of cost for 50
8592 Joints
Details of cost for 6m
6335 depth
Details of cost for 6m
6367 depth
Details of cost for 6m
6391 depth
quintal 10 Nos. Tee
3535 200x150mm
Details of cost for 9 m
21995 length
Details of
of pile
cost for 9 m
22026 length of pile
Details of cost for 9 m
22411 length
Details of
of pile
cost for 9 m
22450 length of
Details of pile
cost for on no.
7727 dirt box strainer
Details of cost for one
5149 chamber
Details of cost for one
5213 chamber
Details of cost for one
5368 chamber
Details of cost for one
5438 chamber
Details of cost for one
5521 chamber
Details of cost for one
20514 chamber
Details of cost for one
20654 chamber
Details of cost for one
20759 chamber
Details of cost for one
19481 connection
Details of cost for one
19563 connection
Details of cost for one
2652 connection.
Details of cost for one
2683 connection.
Details of cost for one
19446 cover
Details of cost for one
19609 drop
Detailsconnection
of cost for one
19695 drop
Detailsconnection
of cost for one M.S
18920 foot rests
Details of cost for one M.S
18962 foot rests
Details of cost for one M.S
19077 foot rests
Details of cost for one
18132 meter
Details of cost for one
18149 meter
Details of cost for one
18178 meter
Details of cost for one
18195 meter
Details of cost for one
2705 meter
Detailswith stop
of cost forcock
one
19773 metre
Details of cost for one
19819 metre
Details of cost for one
20135 metre
Details of cost for one
20156 metre
Details of cost for one
20976 metre
Details of cost for one
20994 metre
7990 Details of cost for one no
2736 Details of cost for one no.
2753 Details of cost for one no.
2782 Details of cost for one no.
2799 Details of cost for one no.
2828 Details of cost for one no.
2861 Details of cost for one no.
2890 Details of cost for one no.
2908 Details of cost for one no.
2936 Details of cost for one no.
2954 Details of cost for one no.
2974 Details of cost for one no.
3002 Details of cost for one no.
3020 Details of cost for one no.
3050 Details of cost for one no.
3066 Details of cost for one no.
3094 Details of cost for one no.
3110 Details of cost for one no.
3138 Details of cost for one no.
3154 Details of cost for one no.
3171 Details of cost for one no.
3196 Details of cost for one no.
3213 Details of cost for one no.
3238 Details of cost for one no.
3258 Details of cost for one no.
3283 Details of cost for one no.
3303 Details of cost for one no.
3329 Details of cost for one no.
3346 Details of cost for one no.
3375 Details of cost for one no.
3391 Details of cost for one no.
3437 Details of cost for one no.
3457 Details of cost for one no.
3485 Details of cost for one no.
6536 Details of cost for one no.
6556 Details of cost for one no.
6585 Details of cost for one no.
6605 Details of cost for one no.
6634 Details of cost for one no.
6654 Details of cost for one no.
6683 Details of cost for one no.
6705 Details of cost for one no.
6735 Details of cost for one no.
6755 Details of cost for one no.
6784 Details of cost for one no.
6804 Details of cost for one no.
6833 Details of cost for one no.
6883 Details of cost for one no.
6973 Details of cost for one no.
6992 Details of cost for one no.
7021 Details of cost for one no.
7040 Details of cost for one no.
7067 Details of cost for one no.
7831 Details of cost for one no.
7849 Details of cost for one no.
7878 Details of cost for one no.
7896 Details of cost for one no.
7925 Details of cost for one no.
7973 Details of cost for one no.
10217 Details of cost for one no.
10237 Details of cost for one no.
10263 Details of cost for one no.
10280 Details of cost for one no.
11846 Details of cost for one no.
19211 Details of cost for one no.
19237 Details of cost for one no.
19273 Details of cost for one no.
19339 Details of cost for one no.
19378 Details of cost for one no.
19408 Details
Details of
of cost
cost for
for one
one no.
no.
7799 dirt box stainer
Details of cost for one no.
6939 tank of of
Details 500 litres
cost for one no.
7637 water meter
Details of cost for one no.
7670 water
Detailsmeter
of cost for one no.
7693 water meter
Details of cost for one
6483 pump
Details of cost for one
21042 soak pitof cost for one
Details
6425 strainer
Details of1.5 long
cost of a
19930 manhole
Details of cost of and
120x90 one
20890 chamber
Details of cost of one gully
16326 tarp
Details of cost of one gully
16432 tarp
Details of cost of one gully
16489 tarp
Details of cost of one gully
16546 tarp
Details of cost of one gully
16601 tarp
20820 Details of cost of one no.
21157 Details of cost of one no.
21195 Details
Details of
of cost
cost of
of one
sandno.
6114 filling
Detailsalround
of cost of sand
6144 filling
Detailsalround
of cost of sand
6164 filling alround
Details of cost of sand
6197 filling
Detailsalround
of cost of sand
6216 filling alround
Details of cost of sand
6285 filling
filling alround
alround 100mm dia.
15mm dia.
6069 pipe
filling alround 65mm dia.
6265 pipe
21266 367 dia metre
21686 367 dia metre
8041 2309 dia
9876 2321 dia
2977 9988 dia
3005 9988 dia
3023 9988 dia
3488 9988 dia
3460 dia
19621 dia
12877 dia SS pipe
12903 dia SS pipe
12918 dia SS pipe
12945 dia SS pipe
12962 dia SS pipe
12979 dia
dia SS pipe
X 15 mm nominal dia
13460 threaded
dia X 15 mm nominal dia
13477 threaded
dia X 15 mm nominal dia
13521 threaded
dia X 15 mm nominal dia
13581 threaded
dia X 15 mm nominal dia
13671 threaded
dia X 15 mm nominal dia
13777 threaded
dia X 15 mm nominal dia
14870 threaded
dia X 15 mm nominal dia
14897 threaded
dia X 15 mm nominal dia
15024 threaded
dia X 20 mm nominal dia
13504 threaded
dia X 20 mm nominal dia
13538 threaded
dia X 20 mm nominal dia
13564 threaded
dia X 20 mm nominal dia
13608 threaded
dia X 20 mm nominal dia
13688 threaded
dia X 20 mm nominal dia
13794 threaded
dia X 20 mm nominal dia
14914 threaded
dia X 25 mm nominal dia
13625 threaded
dia X 25 mm nominal dia
13716 threaded
dia X 25 mm nominal dia
13821 threaded
dia X 25 mm nominal dia
14942 threaded
dia X 32 mm nominal dia
13654 threaded
dia X 32 mm nominal dia
13733 threaded
dia X 32 mm nominal dia
13838 threaded
dia X 32 mm nominal dia
14959 threaded
dia X 40 mm nominal dia
13760 threaded
dia X 40 mm nominal dia
13866 threaded
dia X 40 mm nominal dia
14976 threaded
dia X 50 mm nominal dia
13883 threaded
dia X 50 mm nominal dia
15003 threaded
3627 2309 dia(heavy class)
3648 2309 dia(heavy class)
20105 9999 diameter (medium duty)
7750 7423 Dirt box srainer 100 mm each 1 4370
7780 7424 Dirt box srainer 150 mm each 1 5540
7801 7425 Dirt box srainer 200 mm each 1 7860
7729 7422 Dirt box srainer
disinfected main80 mm in each
tested 1 2680
10459 18.8 the
brickmunicipal laboratory.
work in cement
20192 mortar
dismantling manhole
20304 19.24.4 1.68m deep of C.C slab of
Dismantling
20479 1:2:4 (1 cement
concrete 1:4:8 (1: 2cement :
19932 4
into municipal dumps
19869 19.24 materials
within 50 into
m lead as per
municipal
16653 19.5 dumps :
Dismantling of R.C.C slab
20326 of 1:1.5:3 (1 of
Dismantling cement
second : 1.5
20136 class brick work
Dismantling in cement
of second
20157 class
at sitebrick
leadwork
up toin50cement
11127 18.82 metre:
10433 9999 Disposal of malba L.S. 13.52 2
5152 disposal of surplus earth
5216 disposal of surplus earth
5300 disposal of surplus
Double acting earth
air valve
7581 7417 100 mmacting air valve 50 each
Double 10 5910
7525 7415 mm
Double acting air valve 80 each 10 3715
7548 7416 mm
pipe Conforming to I.S. each 10 4525
9372 7651 8329
pipe Conforming to I.S. metre 10 765
9398 7652 8329
pipe Conforming to I.S. metre 10 1150
9433 7653 8329
pipe Conforming to I.S. metre 10 1575
9459 7654 pipe
8329Conforming
- to I.S. metre 10 2200
9494 7655 8329 -
pipe Conforming to I.S. metre 10 2750
9530 7656 8329 -
pipe Conforming to I.S. metre 10 3350
9556 7657 8329 - metre 10 4300
pipe Conforming to I.S.
9592 7658 8329 -
pipe Conforming to I.S. metre 10 5000
9619 7659 8329 -
pipe Conforming to I.S. metre 10 6270
9656 7660 8329 -
pipe Conforming to I.S. metre 10 7560
9693 7661 8329 -
pipe Conforming to I.S. metre 10 10500
9718 7662 8329 -
pipe Conforming to I.S. metre 10 11350
9753 7663 8329 -
pipe Conforming to I.S. metre 10 11450
9778 7664 8329 -
pipe Conforming to I.S. metre 10 13900
9813 7665 8329 -
pipe conforming to I.S. metre 10 15550
8949 7722 8329 -
pipe conforming to I.S. metre 10 800
8973 7723 8329 -
pipe conforming to I.S. metre 10 1140
9007 7724 8329 -
pipe conforming to I.S. metre 10 1400
9031 7725 8329 -
pipe conforming to I.S. metre 10 1800
9066 7726 8329 -
pipe conforming to I.S. metre 10 2250
9090 8329conforming
7727 pipe - to I.S. metre 10 2650
9125 7728 8329 -
pipe conforming to I.S. metre 10 3175
9161 7729 8329 -
pipe conforming to I.S. metre 10 3852
9186 7730 8329 -
pipe conforming to I.S. metre 10 4350
9221 8329conforming
7731 pipe - to I.S. metre 10 5600
9246 7732 8329 -
pipe conforming to I.S. metre 10 7300
9282 7733 8329 -
pipe conforming to I.S. metre 10 9100
9306 7734 8329 -
pipe conforming to I.S. metre 10 11800
9341 7735 Ductile
8329 - Iron K - 12 specials metre 10 12300
8122 7682 suitable for push
Ductile Iron K - 12on
specials quintal 1 12400
8139 7683 suitable for push
Ductile Iron on K-9 quintal
Pipe Class 1 17200
9849 7686 flanges and welding
Ductile Iron Pipe Class K-9 metre 5 1100
9911 7688 Ductile
flanges Iron Pipe Class K-9 metre
and welding 5 2075
9937 7689 flanges
Ductile Iron Pipe Class K-9 metre
and welding 5 2950
9972 7690 flanges Pipe Class K-9 metre
and welding
Ductile Iron 5 3790
10008 7691 flanges Pipe Class K-9 metre
and welding
Ductile Iron 5 4780
10034 7692 Ductile
flanges Iron Pipe Class K-9 metre
and welding 5 6150
10068 7693 flanges
Ductile Iron Pipe Class K-9 metre
and welding 5 6453
10104 7694 flanges Pipe Class K-9 metre
and welding
Ductile Iron 5 9180
10130 7695 flanges and welding
Ductile Iron Pipe Class K-9 metre 5 12150
10166 flanges and welding
7696 Ductile Iron Pipe Class K-9 metre 5 14370
9875 7687 flanges and welding
Ductile Iron Specials 150 metre 5 1650
8187 7685 suitable
suitable for
for mechanical quintal 1 18750
8170 7684 jointing
Duduct arch ring and quintal 1 13050
18242 portion of pipe
Duduct arch ring and
18341 portion of pipe
Duduct arch ring and
18725 portion of pipe
Duduct arch ring and
18807 portion of pipe
Duduct arch ring and
20075 portion arch
Duduct of pipe
ring and
20266 portion of pipe
19128 9977 duty)
20789 9977 duty)
20869 9977 duty)
20942 PPR Union 9977 duty)
1185 20mm
PPR Union each 1 48 48
1283 25mm
PPR Union each 1 97 97
1301 32mm
PPR Union each 1 137.2 137.2
1319 40mm
PPR Union each 1 184.8 184.8
1365 50mm
Elbow 90O for each 1 352.8 352.8
15228 15.88
Elbow 90O for each 1 191 191
15292 22.22
Elbow 90O for each 1 205 205
15309 22.22
Elbow 90O for each 1 205 205
15396 28.58
Elbow 90O for each 1 205 205
15413 34.00
Elbow 90O for each 1 287 287
15430 34.00
Elbow 90O for each 1 287 287
42.70 90O for each
15466 Elbow 1 478 478
15493 42.70
Elbow 90O for each 1 478 478
15530 48.60
Elbow 90O for each 1 683 683
15557 48.60 each
Earth work in excavation 1 683 683
21043 including
Earth workdisposal of
in excavation
21115 including disposal of
19404 19.19.4 EHD
Elbow- 35
90° for 15.88 mm
12756 8812 outer
Elbow 90°SS
dia forpipe
22.22 mm each 1 58
12772 8813 Elbow
outer dia
90°SS forpipe
28.58 mm each 1 63
12796 8814 outer
Elbow 90° for 34.00 mm each
dia SS pipe 1 96
12812 8815 outer
Elbowdia
90°SS forpipe
42.70 mm each 1 109
12828 8816 outer
Elbowdia
90°SS forpipe
48.60 mm each 1 116
12854 8817 necessary
outer dia SS pipefor inlet, each
holes 1 150
6936 outlet &
Epoxy Coated Aluminium
7834 Road
Epoxy&Coated
H.D. BallAluminium
7852 Road & H.D. Ball
Epoxy Coated Aluminium
7881 Road &Coated
Epoxy H.D. BallAluminium
7899 Road & H.D. Ball
Epoxy Coated Aluminium
7928 Road
Equal & H.D.
Tee forBall
15.88 mm
13009 8824 outer dia SS pipe
Equal Tee for 22.22 mm each 1 159
13025 8825 outer
Equal dia
TeeSS forpipe
28.58 mm each 1 231
13051 8826 outer dia SS pipe
Equal Tee for 34.00 mm each 1 273
13067 8827 outer
Equal dia
TeeSS forpipe
42.70 mm each 1 437
13093 8828 outer
Equal dia
TeeSS forpipe
48.60 mm each 1 683
13109 outer dia SS pipe
8829 of pile for payment shall each 1 887
22297 be
internal dia (at bottom)
18412 19.1 beyond
internal 0.91
dia (at m bottom)
to 1.67 m
18655 19.12 beyond
internal 1.68
dia (at m bottom)
to 2.29 m :
18877 19.14 cm
beyond 2.30masonry
of brick m:
20970 19.31 chamber :
Extra for depth for
18126 19.8 manholes :
Extra for depth of
20131 19.25 manholes dismantled :
drop connection
19769 19.23 complete:
water tested in the
10806 18.81 municipal
Extra labourlaboratory :
for making
17516 channel :
Extra labour for making
17748 channel : for making
Extra labour
17998 channel : for making
Extra labour
18097 channel : for making
Extra labour
18294 channel : for making
Extra labour
18382 channel : for making
Extra labour
18534 channel : for making
Extra labour
18635 channel : for making
Extra labour
18764 channel : for making
Extra labour
18858 channel
the nos. :of extra bulbs are
22648 20.4 to be paid)
18926 13 fabrication
15795 983 Fine sand cum 0.01 850
15840 983 Fine sand cum 0.019 850
15881 983 Fine sand cum 0.028 850
15916 983 Fine sand cum 0.05 850
15962 983 Fine sand cum 0.075 850
16852 983 Fine sand cum 0.006 850
16896 983 Fine sand cum 0.008 850
16929 983 Fine sand cum 0.012 850
17070 983 Fine sand cum 0.033 850
17113 983 Fine sand cum 0.036 850
17157 983 Fine sand cum 0.043 850
17193 983 Fine sand cum 0.05 850
17236 983 Fine sand cum 0.057 850
17280 983 Fine sand cum 0.066 850
17321 983 Fine sand cum 0.074 850
17367 983 Fine sand cum 0.082 850
17411 983 Fine sand cum 0.092 850
21163 983 Fine sand cum 0.001 850
21201 983 Fine sand cum 0.0014 850
21240 983 Fine sand cum 0.017 850
21269 983 Fine sand cum 0.022 850
21307 983 Fine sand cum 0.033 850
21343 983 Fine sand cum 0.037 850
21379 983 Fine sand cum 0.046 850
21408 983 Fine sand cum 0.055 850
21448 983 Fine sand cum 0.017 850
21494 983 Fine sand 850
21533 983 Fine sand 850
21622 983 Fine sand cum 0.037 850
21660 983 Fine sand cum 0.046 850
21698 983 Fine sand cum 0.055 850
16983 Fine
Fine sand
sand for 4 joint =
16981 0.0037x4
Fine sand =for
0.0148
4 jointsay
=
17069 0.0082x4 = 0.033 cum=
Fine sand for 4 joints
17111 0.0089x4
Fine sand for 4 joints =
17145 0.0108x4
Fine sand for 4 joints =
17191 0.0124x4
Fine sand for 4 joints =
17234 0.0143x4
Fine sand for 4 joints =
17278 0.0164x4
Fine sand for 4 joints =
17319 0.0185x4
Fine sand for 4 joints =
17365 0.0206x4
Fine sand for 4 joints =
17409 0.0229x4
Fine sand for 5 joint =
16850 0.0013x5
Fine sand for 5 joint =
16894 0.0016x5
Fine sand for 5 joint =
16928 0.0024x5with
finished = 0.012 cumcoat
floating
18627 of neat cement
Finishing top and bottom
10372 9999 and making the holes leak L.S. 121.16 2
21 19 Fitter (grade 1) day 0.33 505.17
55 19 Fitter (grade 1) day 0.33 505.17
79 19 Fitter (grade 1) day 0.33 505.17
114 19 Fitter (grade 1) day 0.33 505.17
151 19 Fitter (grade 1) day 0.33 505.17
175 19 Fitter (grade 1) day 0.33 505.17
215 19 Fitter (grade 1) day 0.33 505.17
250 19 Fitter (grade 1) day 0.33 505.17
274 19 Fitter (grade 1) day 0.33 505.17
310 19 Fitter (grade 1) day 0.33 505.17
355 19 Fitter (grade 1) day 0.08 505.17
389 19 Fitter (grade 1) day 0.08 505.17
414 19 Fitter (grade 1) day 0.08 505.17
449 19 Fitter (grade 1) day 0.08 505.17
474 19 Fitter (grade 1) day 0.16 505.17
509 19 Fitter (grade 1) day 0.16 505.17
546 19 Fitter (grade 1) day 0.33 505.17
569 19 Fitter (grade 1) day 0.33 505.17
602 19 Fitter (grade 1) day 0.33 505.17
637 19 Fitter (grade 1) day 0.33 505.17
661 19 Fitter (grade 1) day 0.33 505.17
702 19 Fitter (grade 1) day 0.33 505.17
736 19 Fitter (grade 1) day 0.33 505.17
761 19 Fitter (grade 1) day 0.33 505.17
801 19 Fitter (grade 1) day 0.08 505.17
839 19 Fitter (grade 1) day 0.12 505.17
867 19 Fitter (grade 1) day 0.12 505.17
906 19 Fitter (grade 1) day 0.16 505.17
934 19 Fitter (grade 1) day 0.16 505.17
972 19 Fitter (grade 1) day 0.25 505.17
1005 19 Fitter (grade 1) day 0.25 505.17
1034 19 Fitter (grade 1) day 0.37 505.17
1073 19 Fitter (grade 1) day 0.37 505.17
1331 19 Fitter (grade 1) day 0.11 505.17
1388 19 Fitter (grade 1) day 0.11 505.17
1416 19 Fitter (grade 1) day 0.11 505.17
1452 19 Fitter (grade 1) day 0.33 505.17
1479 19 Fitter (grade 1) day 0.33 505.17
1513 19 Fitter (grade 1) day 0.33 505.17
1548 19 Fitter (grade 1) day 0.33 505.17
1573 19 Fitter (grade 1) day 0.33 505.17
1608 19 Fitter (grade 1) day 0.33 505.17
1649 19 Fitter (grade 1) day 0.33 505.17
1676 19 Fitter (grade 1) day 0.33 505.17
1713 19 Fitter (grade 1) day 0.33 505.17
1750 19 Fitter (grade 1) day 0.33 505.17
1779 19 Fitter (grade 1) day 0.08 505.17
1816 19 Fitter (grade 1) day 0.08 505.17
1850 19 Fitter (grade 1) day 0.12 505.17
1876 19 Fitter (grade 1) day 0.12 505.17
1913 19 Fitter (grade 1) day 0.16 505.17
1939 19 Fitter (grade 1) day 0.16 505.17
1974 19 Fitter (grade 1) day 0.25 505.17
2011 19 Fitter (grade 1) day 0.25 505.17
2037 19 Fitter (grade 1) day 0.37 505.17
2073 19 Fitter (grade 1) day 0.58 505.17
2117 19 Fitter (grade 1) day 0.33 505.17
2143 19 Fitter (grade 1) day 0.33 505.17
2180 19 Fitter (grade 1) day 0.33 505.17
2215 19 Fitter (grade 1) day 0.33 505.17
2242 19 Fitter (grade 1) day 0.33 505.17
2279 19 Fitter (grade 1) day 0.33 505.17
2320 19 Fitter (grade 1) day 0.33 505.17
2354 19 Fitter (grade 1) day 0.33 505.17
2393 19 Fitter (grade 1) day 0.08 505.17
2430 19 Fitter (grade 1) day 0.08 505.17
2467 19 Fitter (grade 1) day 0.12 505.17
2495 19 Fitter (grade 1) day 0.12 505.17
2530 19 Fitter (grade 1) day 0.16 505.17
2556 19 Fitter (grade 1) day 0.16 505.17
2594 19 Fitter (grade 1) day 0.25 505.17
2631 19 Fitter (grade 1) day 0.25 505.17
2659 19 Fitter (grade 1) day 0.33 505.17
2690 19 Fitter (grade 1) day 0.45 505.17
2710 19 Fitter (grade 1) day 0.33 505.17
3507 19 Fitter (grade 1) day 0.17 505.17
3538 19 Fitter (grade 1) day 0.93 505.17
4042 19 Fitter (grade 1) day 1 505.17
4068 19 Fitter (grade 1) day 1.5 505.17
4103 19 Fitter (grade 1) day 1.5 505.17
4138 19 Fitter (grade 1) day 2 505.17
4164 19 Fitter (grade 1) day 2.5 505.17
4200 19 Fitter (grade 1) day 3 505.17
4237 19 Fitter (grade 1) day 3 505.17
4263 19 Fitter (grade 1) day 4 505.17
4298 19 Fitter (grade 1) day 4.5 505.17
4324 19 Fitter (grade 1) day 4.75 505.17
4359 19 Fitter (grade 1) day 6.5 505.17
4410 19 Fitter (grade 1) day 0.15 505.17
4442 19 Fitter (grade 1) day 0.25 505.17
4465 19 Fitter (grade 1) day 0.25 505.17
4498 19 Fitter (grade 1) day 0.3 505.17
4521 19 Fitter (grade 1) day 0.3 505.17
4554 19 Fitter (grade 1) day 0.4 505.17
4577 19 Fitter (grade 1) day 0.4 505.17
4611 19 Fitter (grade 1) day 0.5 505.17
4644 19 Fitter (grade 1) day 0.5 505.17
4667 19 Fitter (grade 1) day 0.6 505.17
4700 19 Fitter (grade 1) day 0.65 505.17
4723 19 Fitter (grade 1) day 0.75 505.17
6337 19 Fitter (grade 1) day 0.5 505.17
6369 19 Fitter (grade 1) day 0.62 505.17
6394 19 Fitter (grade 1) day 0.75 505.17
6430 19 Fitter (grade 1) day 0.17 505.17
6466 19 Fitter (grade 1) day 0.33 505.17
6488 19 Fitter (grade 1) day 0.1 505.17
6521 19 Fitter (grade 1) day 0.11 505.17
6541 19 Fitter (grade 1) day 0.11 505.17
6570 19 Fitter (grade 1) day 0.11 505.17
6590 19 Fitter (grade 1) day 0.11 505.17
6619 19 Fitter (grade 1) day 0.11 505.17
6639 19 Fitter (grade 1) day 0.15 505.17
6659 19 Fitter (grade 1) day 0.15 505.17
6688 19 Fitter (grade 1) day 0.15 505.17
6720 19 Fitter (grade 1) day 0.33 505.17
6740 19 Fitter (grade 1) day 0.33 505.17
6769 19 Fitter (grade 1) day 0.33 505.17
6789 19 Fitter (grade 1) day 0.33 505.17
6818 19 Fitter (grade 1) day 0.33 505.17
6838 19 Fitter (grade 1) day 0.45 505.17
6868 19 Fitter (grade 1) day 0.45 505.17
6888 19 Fitter (grade 1) day 0.45 505.17
8220 19 Fitter (grade 1) day 1 505.17
8242 19 Fitter (grade 1) day 1.5 505.17
8274 19 Fitter (grade 1) day 2 505.17
8296 19 Fitter (grade 1) day 2.5 505.17
8328 19 Fitter (grade 1) day 3 505.17
8350 19 Fitter (grade 1) day 3 505.17
8382 19 Fitter (grade 1) day 4 505.17
8404 19 Fitter (grade 1) day 4.5 505.17
8436 19 Fitter (grade 1) day 4.75 505.17
8458 19 Fitter (grade 1) day 6.5 505.17
8490 19 Fitter (grade 1) day 7.7 505.17
8512 19 Fitter (grade 1) day 7.7 505.17
8543 19 Fitter (grade 1) day 8.5 505.17
8565 19 Fitter (grade 1) day 10 505.17
8597 19 Fitter (grade 1) day 11 505.17
10470 19 Fitter (grade 1) day 0.33 505.17
10493 19 Fitter (grade 1) day 0.49 505.17
10527 19 Fitter (grade 1) day 0.66 505.17
10557 19 Fitter (grade 1) day 0.82 505.17
10580 19 Fitter (grade 1) day 1.15 505.17
10612 19 Fitter (grade 1) day 1.48 505.17
10635 19 Fitter (grade 1) day 1.64 505.17
10668 19 Fitter (grade 1) day 1.8 505.17
10705 19 Fitter (grade 1) day 1.97 505.17
10728 19 Fitter (grade 1) day 2.13 505.17
10760 19 Fitter (grade 1) day 2.3 505.17
10783 19 Fitter (grade 1) day 2.62 505.17
10814 19 Fitter (grade 1) day 0.11 505.17
10848 19 Fitter (grade 1) day 0.16 505.17
10868 19 Fitter (grade 1) day 0.22 505.17
10901 19 Fitter (grade 1) day 0.27 505.17
10921 19 Fitter (grade 1) day 0.58 505.17
10954 19 Fitter (grade 1) day 0.6 505.17
10974 19 Fitter (grade 1) day 0.6 505.17
11007 19 Fitter (grade 1) day 0.7 505.17
11027 19 Fitter (grade 1) day 0.8 505.17
11060 19 Fitter (grade 1) day 0.9 505.17
11080 19 Fitter (grade 1) day 1 505.17
11113 19 Fitter (grade 1) day 1.2 505.17
11586 19 Fitter (grade 1) day 0.06 505.17
11614 19 Fitter (grade 1) day 0.08 505.17
11632 19 Fitter (grade 1) day 0.11 505.17
11657 19 Fitter (grade 1) day 0.15 505.17
11675 19 Fitter (grade 1) day 0.2 505.17
11693 19 Fitter (grade 1) day 0.25 505.17
11721 19 Fitter (grade 1) day 0.3 505.17
11739 19 Fitter (grade 1) day 0.35 505.17
11767 19 Fitter (grade 1) day 0.4 505.17
11785 19 Fitter (grade 1) day 0.45 505.17
11801 19 Fitter (grade 1) day 0.5 505.17
11828 19 Fitter (grade 1) day 0.6 505.17
11887 19 Fitter (grade 1) day 0.33 505.17
11926 19 Fitter (grade 1) day 0.33 505.17
11953 19 Fitter (grade 1) day 0.33 505.17
11991 19 Fitter (grade 1) day 0.33 505.17
12030 19 Fitter (grade 1) day 0.33 505.17
12069 19 Fitter (grade 1) day 0.33 505.17
12113 19 Fitter (grade 1) day 0.33 505.17
12143 19 Fitter (grade 1) day 0.33 505.17
5184 18 five level
5260 18 five level
5329 18 five level
5411 18 five level
5482 18 five level
5555 18 five level
20612 18 five level
20687 18 five level
20863 18 five level
20927 18 five level
Fixing and carriage of
20624 R.C.C. grating L.S. 20.67 2
20550 9999 Fixing
meter R.C.C.
and stopgrating
cock to be L.S. 5.33 2
2703 18.14 Flanged
paid separately).
C.I. standard
3647 1470 specials over 300 mm
Flanged C.I. standard quintal 1 5500
3626 1468 specials
acting airupto 300with
valves mm quintal 1 5500
7528 bolts,
acting air valves with
7551 bolts,
acting air valves with
7584 bolts,
18089 For
For 0.33
10 mcum
length= 26.43
qty. ofkg
16268 concrete
For 10 m length qty. of
16217 concrete
concrete reqd.
reqd. =
16121 0.07034x10
concrete reqd. = 0.180x10
16313 =For 10 m length qty. of
16031 concrete
For 100 mmreqd.
dia=sand
1.81 cast
cum
19771 19.23.1 iron15.88
For drop connection
mm outer dia
15586 18.101.1 pipe
For 15.88 mm outer dia
15696 18.102.1 pipe
For 15.88 mm outer dia
12171 18.87.1 pipe
For 15.88 mm outer dia
12621 18.89.1 pipe
For 15.88 mm outer dia
13005 18.92.1 pipe
for 15.88 mm outer dia X
14356 15
15 mm
mm nominal
nominal dia
dia
13455 18.94.1 threaded
15 mm nominal dia
14351 18.96.1 threaded
15 mm nominal dia
14632 18.97.1 threaded
15 mm nominal dia
14865 18.98.1 threaded
15 mm nominal dia
15019 18.99.1 threaded
x15 mm nominal dia
13910 18.95.1 threaded
For 15.88mm outer dia
12752 18.90.1 pipe
For 150 mm dia sand cast
19818 19.23.2 iron drop connection
For 22.22 mm outer dia
15600 18.101.2 pipe
For 22.22 mm outer dia
15724 18.102.2 pipe
For 22.22 mm outer dia
12187 18.87.2 pipe
For 22.22 mm outer dia
12637 18.89.2 pipe
For 22.22 mm outer dia
12768 18.90.2 pipe
For 22.22 mm outer dia
13021 18.92.2 pipe
for 22.22 mm outer dia X
14383 15 mm
for nominal
22.22 dia dia X
mm outer
14654 15
15 mm nominal dia
mm nominal dia
13472 18.94.2 threaded
15 mm nominal dia
13927 18.95.2 threaded
15 mm nominal dia
14649 18.97.2 threaded
15 mm nominal dia
14892 18.98.2 threaded
15 mm nominal dia
15045 18.99.2 threaded
15 mmnominal dia
14378 18.96.2 threaded
for 22.22 mm outer dia X
14402 20 mm
20 mm nominal
nominal dia
dia
13499 20.1 threaded
20 mm nominal dia
13944 18.95.3 threaded
20 mm nominal dia
14396 18.96.3 threaded
20 mm nominal dia
14667 18.97.3 threaded
20 mm nominal dia
14909 18.98.3 threaded
20 mm nominal dia
15061 18.99.3 threaded
For 22.22 mm x 15.88 mm
12296 18.88.1 outer dia pipe
For 22.22 mm x 15.88 mm
13125 18.93.1 outer
25 mmdia pipe dia
nominal
15086 18.99.4 threaded
For 28.58 mm outer dia
15625 18.101.3 pipe
For 28.58 mm outer dia
15739 18.102.3 pipe
For 28.58 mm outer dia
12213 18.87.3 pipe
For 28.58 mm outer dia
12661 18.89.3 pipe
For 28.58 mm outer dia
12784 18.90.3 pipe
For 28.58 mm outer dia
13047 18.92.3 pipe
for 28.58 mm outer dia X
14429 15 mm
15 mm nominal
nominal dia
dia
13516 18.94.4 threaded
15 mm nominal dia
13970 18.95.4 threaded
15 mm nominal dia
14415 18.96.4 threaded
for 28.58 mm outer dia X
14448 20
for mm nominal
28.58 dia dia X
mm outer
14698 20
20 mm
mm nominal
nominal dia
dia
13533 18.94.5 threaded
20 mm nominal dia
13987 18.95.5 threaded
20 mm nominal dia
14443 18.96.5 threaded
20 mm nominal dia
14693 18.97.4 threaded
for 28.58 mm outer dia X
14466 25
for mm nominal
28.58 dia dia X
mm outer
14716 25
25 mm
mm nominal
nominal dia
dia
13559 18.94.6 threaded
25 mm nominal dia
14013 18.95.6 threaded
25 mm nominal dia
14461 18.96.6 threaded
25 mm nominal dia
14711 18.97.5 threaded
25 mm nominal dia
14937 18.98.4 threaded
For 28.58 mm x 15.88 mm
12898 18.91.2 outer
For dia pipe
28.58 mm x 15.88 mm
13151 18.93.2 outer dia pipe
For 28.58 mm x 15.88 mm
12322 18.94.19 outer dia pipe
For 28.58 mm x 22.22 mm
12339 18.88.3 outer dia pipe
For 28.58 mm x 22.22 mm
12914 18.91.3 outer
For dia pipe
28.58 mm x 22.22 mm
13168 18.93.3 outer dia pipe
For 34.00 mm outer dia
15639 18.101.4 pipe
For 34.00 mm outer dia
12230 18.87.4 pipe
For 34.00 mm outer dia
12677 18.89.4 pipe
For 34.00 mm outer dia
12808 18.90.4 pipe
For 34.00 mm outer dia
13063 18.92.4 pipe
15 mm nominal dia
13576 18.94.7 threaded
15 mm nominal dia
14029 18.95.7 threaded
20 mm nominal dia
13603 18.94.8 threaded
20 mm nominal dia
14046 18.95.8 threaded
for 34.00 mm outer dia X
14494 25
25 mm
mm nominal
nominal dia
dia
13620 18.94.9 threaded
25 mm nominal dia
14073 18.95.9 threaded
25 mm nominal dia
14489 18.96.7 threaded
25 mm nominal dia
14740 18.97.6 threaded
for 34.00 mm outer dia X
14512 32
32 mm
mm nominal
nominal dia
dia
13637 18.94.10 threaded
32 mm nominal dia
14090 18.95.10 threaded
32 mm nominal dia
14507 18.96.8 threaded
32 mm nominal dia
14757 18.97.7 threaded
32 mm nominal dia
14954 18.98.5 threaded
32 mm nominal dia
15103 18.99.5 threaded
For 34.00 mm x 15.88 mm
12365 18.88.4 outer dia pipe
For 34.00 mm x 15.88 mm
13194 18.93.4 outer
For dia pipe
34.00 mm x 22.22 mm
12382 18.88.5 outer dia pipe
For 34.00 mm x 22.22 mm
12940 18.91.4 outer dia pipe
For 34.00 mm x 22.22 mm
13211 18.93.5 outer dia pipe
For 34.00 mm x 28.58 mm
12409 18.88.6 outer dia pipe
For 34.00 mm x 28.58 mm
12957 18.91.5 outer dia pipe
For 34.00 mm x 28.58 mm
13228 18.93.6 outer dia pipe
For 42.70 mm outer dia
15653 18.101.5 pipe
For 42.70 mm outer dia
12247 18.87.5 pipe
For 42.70 mm outer dia
12703 18.89.5 pipe
For 42.70 mm outer dia
12824 18.90.5 pipe
For 42.70 mm outer dia
13079 18.92.5 pipe
15 mm nominal dia
13666 18.94.11 threaded
15 mm nominal dia
14117 18.95.11 threaded
20 mm nominal dia
13683 18.94.12 threaded
20 mm nominal dia
14134 18.95.12 threaded
25 mm nominal dia
13711 18.94.13 threaded
25 mm nominal dia
14151 18.95.13 threaded
for 42.70 mm outer dia X
14541 32
32 mm
mm nominal
nominal dia
dia
13728 18.94.14 threaded
32 mm nominal dia
14178 18.95.14 threaded
32 mm nominal dia
14536 18.96.9 threaded
32 mm nominal dia
14774 18.97.8 threaded
32 mm nominal dia
15120 18.99.6 threaded
for 42.70 mm outer dia X
14559 40
40 mm
mm nominal
nominal dia
dia
13755 18.94.15 threaded
40 mm nominal dia
14195 18.95.15 threaded
40 mm nominal dia
14554 18.96.10 threaded
40 mm nominal dia
14800 18.97.9 threaded
40 mm nominal dia
14971 18.98.6 threaded
40 mm nominal dia
15148 18.99.7 threaded
For 42.70 mm x 15.88 mm
12426 18.88.7 outer dia pipe
For 42.70 mm x 15.88 mm
13256 18.93.7 outer dia pipe
For 42.70 mm x 22.22 mm
12443 18.88.8 outer
For dia pipe
42.70 mm x 22.22 mm
13273 18.93.8 outer dia pipe
For 42.70 mm x 28.58 mm
12470 18.88.9 outer dia pipe
For 42.70 mm x 28.58 mm
13301 18.93.9 outer dia pipe
For 42.70 mm x 34.00 mm
12487 18.88.10 outer dia pipe
For 42.70 mm x 34.00 mm
12974 18.91.6 outer dia pipe
For 42.70 mm x 34.00 mm
13318 18.93.10 outer dia pipe
20972 19.31.1 For
For 455x610
48.60 mmmm sizedia
outer
15677 18.101.6 pipe
For 48.60 mm outer dia
12276 18.87.6 pipe
For 48.60 mm outer dia
12719 18.89.6 pipe
For 48.60 mm outer dia
12850 18.90.6 pipe
For 48.60 mm outer dia
13105 18.92.6 pipe
15 mm nominal dia
13772 18.94.16 threaded
15 mm nominal dia
14223 18.95.16 threaded
20 mm nominal dia
13789 18.94.17 threaded
20 mm nominal dia
14242 18.95.17 threaded
25 mm nominal dia
13816 18.94.18 threaded
25 mm nominal dia
14269 18.95.18 threaded
32 mm nominal dia
13833 18.94.20 threaded
32 mm nominal dia
14286 18.95.19 threaded
for 48.60 mm outer dia X
14588 40
40 mm
mm nominal
nominal dia
dia
13861 18.94.20 threaded
40 mm nominal dia
14303 18.95.20 threaded
40 mm nominal dia
14583 18.96.11 threaded
40 mm nominal dia
14817 18.97.10 threaded
40 mm nominal dia
15165 18.99.8 threaded
for 48.60 mm outer dia X
14606 50
50 mm
mm nominal
nominal dia
dia
13878 18.94.21 threaded
50 mm nominal dia
14330 18.95.22 threaded
50 mm nominal dia
14601 18.96.12 threaded
50 mm nominal dia
14844 18.97.11 threaded
50 mm nominal dia
14998 18.98.7 threaded
50 mm nominal dia
15193 18.99.9 threaded
For 48.60 mm x 15.88 mm
12514 18.88.11 outer dia pipe
For 48.60 mm x 15.88 mm
13345 18.93.11 outer dia pipe
For 48.60 mm x 22.22 mm
12531 18.88.12 outer dia pipe
For 48.60 mm x 22.22 mm
13362 18.93.12 outer
For dia pipe
48.60 mm x 28.58 mm
12559 18.88.13 outer dia pipe
For 48.60 mm x 28.58 mm
13379 18.93.13 outer dia pipe
For 48.60 mm x 34.00 mm
12575 18.88.14 outer dia pipe
For 48.60 mm x 34.00 mm
13406 18.93.14 outer
For dia pipe
48.60 mm x 42.70 mm
12602 18.88.15 outer dia pipe
For 48.60 mm x 42.70 mm
13423 18.93.15 outer dia pipe
20990 19.31.2 For 500x700 mm size
21008 19.31.4 For 600x850 mm size
18355 For benching :
18506 For benching :
18739 For benching :
20279 For
For benching
boring and: removing
6393 the pipe- 5 cm deep in
For cutting
19851 alternate
For cuttingcourse
holes of
45brick
holes
19750 5 cm deep toothing in
deep in alternate course
19666 of
deep in alternate course
19802 of
rest cutting holes and
19058 fixing
rest cutting holes and
19101 fixing
21138 For filling brick bats
17970 For fixing cover
18069 For
For fixing
fixing cover
cover : 3.14/4 x
18278 d² x thickness
For fixing cover : 3.14/4 x
18366 d²
Forx fixing
thickness
cover : 3.14/4 x
18519 d² x thickness
For fixing cover : 3.14/4 x
18620 d²
Forx fixing
thickness
cover : 3.14/4 x
18748 d² x thickness
For fixing cover : 3.14/4 x
18842 d²
Forx fixing
thickness
cover : 3.14/4 x
20286 d2 x thickness
8952 18.23 for laying metre
3595 For laying
3630 For laying
3651 For laying
3.142/4(0.115)²x10 =
6294 (-)0.10cum.
For pipes 100 to 250 mm
19479 19.21.1 diameter
For pipes 250 to 300 mm
19514 19.21.2 diameter
For pipes 350 to 450 mm
19561 19.21.4 diameter
For raised slab =
20339 1.36x1.26x0.15
1.36x1.26x0.15m = 0.257
19911 cum
1.66x1.36x0.15m = 0.339
17733 cum
1.66x1.36x0.15m = 0.339
17979 cum
1.66x1.36x0.15m = 0.339
18078 cum
1.66x1.36x0.15m = 0.339
19966 cum
For22.22 mm x 15.88 mm
12872 18.91.1 outer dia pipe
19661 Form work
19736 Form work
19789 Form work
19836 Form work
20544 Form work
20614 Form work
20704 Form work
20785 Form work
20846 Form work
20929 Form
Form work
work = 0.90x0.80 =
17511 0.72 sqm
Form work = 0.90x0.80 =
20346 0.72
Formsqm work = 1.20x0.90 =
17743 1.08
Formsqm work = 1.2x0.90 =
20397 1.08 sqm
Form work = 1.2x0.90 =
20446 1.08
Formsqm work
5265 0.60mx0.60m=0.36sqm.+
Form work inside area of
17992 man-hole
Form work inside area of
18091 man-hole
4037 761 Fuel wood quintal 0.28 500
4063 761 Fuel wood quintal 0.37 500
4098 761 Fuel wood quintal 0.42 500
4124 761 Fuel wood quintal 0.56 500
4159 761 Fuel wood quintal 0.65 500
4195 761 Fuel wood quintal 0.75 500
4221 761 Fuel wood quintal 0.93 500
4257 761 Fuel wood quintal 1.12 500
4293 761 Fuel wood quintal 1.21 500
4319 761 Fuel wood quintal 1.31 500
4354 761 Fuel wood quintal 1.68 500
11142 761 Fuel wood quintal 0.373 500
11183 761 Fuel wood quintal 0.466 500
11223 761 Fuel wood quintal 0.559 500
11254 761 Fuel wood quintal 0.653 500
11296 761 Fuel wood quintal 0.84 500
11336 761 Fuel wood quintal 1.026 500
11365 761 Fuel wood quintal 1.12 500
11407 761 Fuel wood quintal 1.213 500
11448 761 Fuel wood quintal 1.306 500
11479 761 Fuel wood quintal 1.4 500
11520 761 Fuel wood quintal 1.492 500
11561 761 Fuel wood(jam) nuts 25
G.I. back quintal 1.68 500
2656 mmback
1555 G.I. dia (jam) nuts 25 each 1 15
2707 1555 mm dia
G.I. back (jam) nuts 65 each 1 15
2687 1559 mm dia each 1 25
2100 1545 G.I. pipes 15 mm dia metre 11.5 91
2300 1545 G.I. pipes 15 mm dia metre 11.5 91
2387 1545 G.I. pipes 15 mm dia metre 10.2 91
2136 1546 G.I. pipes 20 mm dia metre 11.5 120
2339 1546 G.I. pipes 20 mm dia metre 11.5 120
2424 1546 G.I. pipes 20 mm dia metre 10.2 120
2172 1547 G.I. pipes 25 mm dia metre 11.5 171
2451 1547 G.I. pipes 25 mm dia metre 10.2 171
2197 1548 G.I. pipes 32 mm dia metre 11.5 215
2488 1548 G.I. pipes 32 mm dia metre 10.2 215
2234 1549 G.I. pipes 40 mm dia metre 11.5 250
2523 1549 G.I. pipes 40 mm dia metre 10.2 250
6450 1549 G.I. pipes 40 mm dia metre 10.2 250
2271 1550 G.I. pipes 50 mm dia metre 11.5 310
2549 1550 G.I. pipes 50 mm dia metre 10.2 310
2587 1551 G.I. pipes 65 mm dia metre 10.2 395
2624 1552 G.I. pipes 80 mm dia metre 10.2 505
2655 1608 G.I. tees (equal) 25 mm each 1 50
2686 1612 G.I.
G.I. tees
Union(equal)
15 mm65nominal
mm each 1 452
6518 1641 bore
G.I. Union 15 mm nominal each 1 30
6707 1641 bore
G.I. Union 20 mm nominal each 1 30
6538 1642 G.I.
boreUnion 20 mm nominal each 1 49
6737 1642 bore
G.I. Union 25 mm nominal each 1 49
6558 1643 bore
G.I. Union 25 mm nominal each 1 108
6757 1643 bore each 1 108
G.I. Union 32 mm nominal
6587 1644 bore
G.I. Union 32 mm nominal each 1 141
6786 1644 bore
G.I. Union 40 mm nominal each 1 141
6607 1645 bore
G.I. Union 40 mm nominal each 1 192
6806 1645 bore
G.I. Union 50 mm nominal each 1 192
6636 1646 bore
G.I. Union 50 mm nominal each 1 249
6835 1646 bore
G.I. Union 65 mm nominal each 1 249
6656 1647 bore
G.I. Union 65 mm nominal each 1 504
6865 1647 bore
G.I. Union 80mm nominal each 1 504
6685 1648 bore
G.I. Union 80mm nominal each 1 563
6885 1648 bore each 1 563
2350 18.78 good the same
grade stone aggregate 20
19910 mm
gradenominal size)
stone aggregate 20
19965 mm nominal size)
grade stone aggregate 20
20031 mm nominal size)
5222 graded stone aggregate
5376 graded
graded stone
stone aggregate
aggregate
20337 20 mm
graded stone aggregate
18354 20 mm nominal
graded size )
stone aggregate
20391 20 mm nominal size )
graded stone aggregate
20440 20 mm nominal
graded size )
stone aggregate
20490 20 mm nominal
graded size )
stone aggregate
18256 20 mm nominal
graded size ) For
stone aggregate
10428 20 mm nominal size)
graded stone aggregate
20682 20 mm nominal
graded size)
stone aggregate
19640 40 mm nominal
graded size)
stone aggregate
19715 40 mm nominal
graded size)
stone aggregate
20517 40 mm nominal size)
graded stone aggregate
20656 40 mm nominal
graded size)
stone aggregate
20761 40 mm nominal
graded size)
stone aggregate
20822 40 mm nominal
graded size)
stone aggregate
20892 40
Group of two or size)
mm nominal more
23219 20.7.2 piles
piles upto 50 tonne Safe
23134 20.6.3 capacity
Group of two piles upto
23161 50 tonne
Group capacity
of two pileseach
upto
23226 50 tonne capacity each
valve-horizontal (screwed
3052 1933 end)
valve-horizontal (screwed each 1 330
3096 1934 end)
valve-horizontal (screwed each 1 450
3140 1935 end)
valve-horizontal (screwed each 1 560
3182 1936 end)
valve-horizontal (screwed each 1 820
3215 1937 end)
valve-horizontal (screwed each 1 1490
3260 1938 end)
valve-vertical (screwed each 1 2120
3068 3080 valve-vertical
end) 25 (screwed each 1 350
3112 3084 end) 32
valve-vertical (screwed each 1 500
3156 3088 end) 40
valve-vertical (screwed each 1 700
3198 3092 end) 50 each 1 900
valve-vertical (screwed
3240 3096 end) 65
valve-vertical (screwed each 1 1500
3285 3300 end) 80 each 1 2500
19374 19.19.3 H D -or
H.P. 20L.P. ball valve with
2976 1922 polythene
H.P. or L.P.floats: 15 mm
ball valve with each 1 210
3004 1923 polythene floats: 20 mm
H.P. or L.P. ball valve with each 1 235
3022 1924 polythene
power unitfloats:
and 25 mm each 1 230
22816 accessories
power unit and .
22859 accessories
power unit and .
22900 accessories
power unit and .
22932 accessories
power unit and .
22973 accessories
power unit and .
23015 accessories .
Helper (Technician)
23306 45 Miscllaneous day 0.1 350.00
16111 Hence Tan Q = 0.3057
16255 Hence
Hence,TanQtyQ= =1 0.5635
/ 1.8 =
19777 0.55556 Nos.
Hence, Qty = 1 / 1.8 =
19823 0.55556
Hire and Nos.
running charges
22089 of bentonite
26 Hire and runningpump. charges day 0.38 3500
22121 26 of bentonite pump.
Hire and running charges day 0.38 3500
22162 26 of bentonite
Hire and runningpump. charges day 0.38 3500
22202 26 of bentonite pump.
Hire and running charges day 0.75 3500
22314 26 Hire
of bentonite
and runningpump. charges day 0.38 3500
22353 26 of bentonite pump.
Hire and running charges day 0.75 3500
22390 26 of bentonite
Hire and runningpump. charges day 0.75 3500
22422 26 of bentonite pump.
Hire and running charges day 0.75 3500
22461 26 Hire
of bentonite
and runningpump. charges day 0.96 3500
22507 26 of bentonite pump.
Hire and running charges day 0.02 3500
22550 26 of bentonite
Hire and runningpump. charges day 0.02 3500
22591 26 of bentonite pump.
Hire and running charges day 0.02 3500
22631 26 Hire
of bentonite
and runningpump. charges day 0.02 3500
22673 26 of bentonite pump.
Hire and running charges day 0.01 3500
22701 26 of bentonite
Hire and runningpump. charges day 0.01 3500
22734 26 of bentonite pump.
Hire and running charges day 0.01 3500
22769 26 of
of bentonite
crane 20 tonnepump. day 0.02 3500
22817 28 capacity.
of crane 20 tonne day 0.06 7000
22860 28 capacity.
of crane 20 tonne day 0.06 7000
22901 28 capacity.
of crane 20 tonne day 0.06 7000
22933 28 capacity.
of crane 20 tonne day 0.06 7000
22974 28 capacity.
of crane 20 tonne day 0.06 7000
23016 28 capacity.
Hire and running charges day 0.06 7000
21780 24 of hydraulic
Hire pilingcharges
and running rig with day 0.36 30000
21818 24 Hire
of hydraulic pilingcharges
and running rig with day 0.48 30000
21858 24 of hydraulic piling
Hire and running chargesrig with day 0.6 30000
21889 24 of hydraulic
Hire pilingcharges
and running rig with day 0.6 30000
21928 24 of hydraulic piling rig with day 0.7 30000
Hire and running charges
21966 24 of hydraulic
Hire pilingcharges
and running rig with day 0.68 30000
22004 24 of hydraulic
Hire pilingcharges
and running rig with day 0.67 30000
22042 24 of hydraulic piling rig with
Hire and running charges day 0.77 30000
22310 24 of hydraulic
Hire pilingcharges
and running rig with day 0.75 30000
22349 24 of hydraulic
Hire pilingcharges
and running rig with day 0.7 30000
22386 24 of hydraulic
Hire pilingcharges
and running rig with day 0.69 30000
22418 24 of hydraulic piling rig with
Hire and running charges day 0.67 30000
22457 24 of hydraulic
Hire pilingcharges
and running rig with day 0.77 30000
22503 24 of hydraulic
Hire pilingcharges
and running rig with day 0.36 30000
22546 24 of hydraulic
Hire pilingcharges
and running rig with day 0.36 30000
22587 24 of hydraulic piling rig with
Hire and running charges day 0.36 30000
22627 24 of hydraulic
Hire pilingcharges
and running rig with day 0.36 30000
22669 24 of hydraulic
Hire pilingcharges
and running rig with day 0.02 30000
22697 of hydraulic
24 Hire pilingcharges
and running rig with day 0.02 30000
22730 24 of hydraulic piling rig with
Hire and running charges day 0.02 30000
22765 24 of hydraulic
Hire pilingcharges
and running rig with day 0.02 30000
21783 25 of light
Hire andcrane.
running charges day 0.06 3000
21821 of light
25 Hire andcrane.
running charges day 0.06 3000
21861 25 of light crane.
Hire and running charges day 0.06 3000
21892 25 of light
Hire andcrane.
running charges day 0.06 3000
21931 25 of light crane.
Hire and running charges day 0.06 3000
21969 25 Hire
of light
andcrane.
running charges day 0.06 3000
22007 25 of light crane.
Hire and running charges day 0.06 3000
22045 25 of light
Hire andcrane.
running charges day 0.1 3000
22088 25 of light crane.
Hire and running charges day 0.06 3000
22120 25 Hire
of light
andcrane.
running charges day 0.06 3000
22161 25 of light crane.
Hire and running charges day 0.06 3000
22201 25 of light
Hire andcrane.
running charges day 0.06 3000
22313 25 of light crane.
Hire and running charges day 0.06 3000
22352 25 Hire
of light
andcrane.
running charges day 0.06 3000
22389 25 of light crane.
Hire and running charges day 0.06 3000
22421 25 of light
Hire andcrane.
running charges day 0.06 3000
22460 25 of light crane.
Hire and running charges day 0.1 3000
22506 25 of light
Hire andcrane.
running charges day 0.03 3000
22549 25 of light crane.
Hire and running charges day 0.06 3000
22590 25 of light
Hire andcrane.
running charges day 0.06 3000
22630 25 of light crane.
Hire and running charges day 0.06 3000
22672 25 of light
Hire andcrane.
running charges day 0.01 3000
22700 25 of light crane.
Hire and running charges day 0.01 3000
22733 25 of light
Hire andcrane.
running charges day 0.01 3000
22768 25 of light crane.
Hire and running charges day 0.01 3000
22090 18 Hire
of loader
and running charges day 0.3 5000
22132 18 of loader
Hire and running charges day 0.3 5000
22164 18 of loader
Hire and running charges day 0.3 5000
22204 18 of loader day 0.3 5000
Hire and running charges
22315 18 of loader
Hire and running charges day 0.3 5000
22354 18 of loader
Hire and running charges day 0.3 5000
22391 18 of loader
Hire and running charges day 0.4 5000
22462 18 of loader
Hire and running charges day 0.75 5000
22423 18 of loader.
Hire and running charges day 0.5 5000
22091 17 of tipper
Hire and running charges day 0.3 1700
22122 17 of tipper
Hire and running charges day 0.3 1700
22163 17 of tipper
Hire and running charges day 0.3 1700
22203 17 of tipper
Hire and running charges day 0.3 1700
22316 17 of tipper
Hire and running charges day 0.3 1700
22355 17 of tipper
Hire and running charges day 0.3 1700
22392 17 of tipper
Hire and running charges day 0.4 1700
22424 17 of tipper
Hire and running charges day 0.5 1700
22463 of tipper
17 Hire and running charges day 0.75 1700
22085 15 of Tripod and
Hire and running charges day 0.94 1900
22117 15 of Tripod and
Hire and running charges day 1.2 1900
22158 15 of Tripod
Hire and
and running charges day 1.5 1900
22198 of Tripod
15 Hire and
and running charges day 1.4 1900
22815 27 of vibrating pile driving
Hire and running charges day 0.38 30000
22858 27 of vibrating
Hire pile driving
and running charges day 0.38 30000
22899 27 of vibrating pile driving
Hire and running charges day 0.38 30000
22931 27 Hire
of vibrating pile driving
and running charges day 0.38 30000
22972 27 of vibrating pile driving
Hire and running charges day 0.38 30000
23014 27 of vibrating
Hire chargespile driving
of Derrick day 0.38 30000
6339 10 monkey ropeof
Hire charges and other
Derrick day 0.5 750
6371 10 Derrickmonkey
monkey rope and other
rope and day 0.62 750
6396 10 other day 0.75 750
3049 18.19.1.1 Horizontal
3093 18.19.2.1 Horizontal
3137 18.19.3.1 Horizontal
3170 18.19.4.1 Horizontal
3212 18.19.5.1 Horizontal
3256 18.19.6.1 Horizontal
20548 9977 horizontal grating
19449 i.e.cover
I.S. 13382ofupto
4.50300mm
kg
8073 dia
8623 I.S. 1536, - 100mm dia
8659 I.S. 1536, - 150mm dia
8693 I.S. 1536, - 200mm dia
8719 I.S. 1536, - 250mm dia
8755 I.S. 1536, - 300mm dia
8780 I.S. 1536, - 350mm dia
8815 I.S. 1536, - 400mm dia
8852 I.S. 1536, - 450mm dia
8877 I.S. 1536, - 500mm dia
8911 I.S. 1536, - mortar
in cement 600mm1:3 dia( 1
18249 cement
in cement : 3mortar
fine sand1:3) ( 1
18500 cement
in cement mortar 1:3) ( 1
: 3 fine sand
18733 cement
in cement : 3mortar
fine sand1:4) (1
16620 cement
in cement : 4mortar
coarse 1:4
sand)(1
16508 cement :4 coarse
in cement mortar 1:4 (1 sand)
17543 cement :4 coarse sand)
15584 in-charge.
15694 in-charge.
Initial test (Test Load 2.5
23092 20.6.2.1 times the Safe capacity)
1970 inner dia.
2007 inner dia.
2033 inner dia.
2069 inner
Insidedia.
area of chamber :
20847 0.70x0.50
Inside areamof chamber :
20930 0.85x0.60
455x610 mm m and 45 cm
20757 19.30.1 deep
deep for
for single pipe
pipe line line :
with
20814 19.30.2 onepipe
for or two
line with three or
20886 19.30.3 more
of cover 108: kg and
inlets
17926 19.7.3 weight
and weightof frame 100 kg)
of frame 58 :
17686 19.7.2 kg)
and: weight of frame 15
17457 19.7.1 kg) :direction of Engineer-
per
23297 20.9 incharge.
536 Internal
includingExposed on walls
installation of
23094 loading
8118 IS : 9523 :
12091 JIS
JIS 3448
3448 standard
standard 15.88
11878 2272 mm outer dia
JIS 3448 standard 22.22
11917 2272 mm outer dia
JIS 3448 standard 22.22
12131 mm3448
JIS outer dia
standard 28.58
11944 2272 mm outer dia
JIS 3448 standard 34.00
11982 2272 mm outer
JIS 3448 dia
standard 42.70
12021 2272 mm outer dia
JIS 3448 standard 48.60
12050 mm outer dia
8140 2309 jointing over 600mm dia
8123 2309 jointing upto 600 mm dia
15837 367 joints
0.00325 = 0.036
cum =tonne
0.0048 t
16846 say metre
4038 771 Kerosene oil litre 0.38 50
4064 50 Kerosene oil litre 0.76 50
4099 771 Kerosene oil litre 0.76 50
4125 771 Kerosene oil litre 0.76 50
4160 771 Kerosene oil litre 1.14 50
4196 771 Kerosene oil litre 1.52 50
4222 771 Kerosene oil litre 1.7 50
4259 771 Kerosene oil litre 1.7 50
4294 771 Kerosene oil litre 2.27 50
4320 771 Kerosene oil litre 2.27 50
4355 771 Kerosene oil litre 2.84 50
11143 771 Kerosene oil litre 0.379 50
11184 771 Kerosene oil litre 0.379 50
11224 771 Kerosene oil litre 0.568 50
11255 771 Kerosene oil litre 0.568 50
11297 771 Kerosene oil litre 0.7576 50
11337 771 Kerosene oil litre 1.1365 50
11366 771 Kerosene oil litre 1.515 50
11408 771 Kerosene oil litre 1.515 50
11449 771 Kerosene oil litre 1.894 50
11480 771 Kerosene oil litre 2.273 50
11521 771 Kerosene oil litre 2.652 50
11562 771 Kerosene oil litre 3.41 50
19199 19.19.1 LCarriage
D- 2.5 of materials and
1186 sundries
Carriage of materials and L.S. 1.82 2
1284 sundries
Carriage of materials and L.S. 1.82 2
1302 sundries
Carriage of materials and L.S. 1.82 2
1320 sundries
Carriage of materials and L.S. 1.82 2
1366 sundries L.S. 1.82 2
3683 LA 100mm dia
3709 LA 125mm dia
3744 LA 150mm dia
3779 LA 200mm dia
3805 LA 250mm dia
3840 LA 300mm dia
3867 LA 350mm dia
3902 LA 400mm dia
3940 LA 450mm dia
3967 LA 500mm dia
4003 LA 600mm dia
20 LABOUR
54 LABOUR
78 LABOUR
113 LABOUR
150 LABOUR
174 LABOUR
214 LABOUR
249 LABOUR
273 LABOUR
309 LABOUR
354 LABOUR
379 LABOUR
413 LABOUR
448 LABOUR
473 LABOUR
508 LABOUR
1451 LABOUR
1478 LABOUR
1512 LABOUR
1547 LABOUR
1572 LABOUR
1607 LABOUR
1648 LABOUR
1675 LABOUR
1712 LABOUR
1749 LABOUR
1778 LABOUR
1815 LABOUR
1839 LABOUR
1875 LABOUR
1912 LABOUR
1938 LABOUR
1973 LABOUR
2010 LABOUR
2036 LABOUR
2072 LABOUR
2116 LABOUR
2142 LABOUR
2179 LABOUR
2214 LABOUR
2241 LABOUR
2278 LABOUR
2319 LABOUR
2353 LABOUR
2392 LABOUR
2429 LABOUR
2466 LABOUR
2494 LABOUR
2529 LABOUR
2555 LABOUR
2593 LABOUR
2630 LABOUR
2658 LABOUR
2689 LABOUR
2709 LABOUR
3574 LABOUR
3594 LABOUR
3629 LABOUR
3650 LABOUR
4041 LABOUR
4067 LABOUR
4102 LABOUR
4137 LABOUR
4163 LABOUR
4199 LABOUR
4236 LABOUR
4262 LABOUR
4297 LABOUR
4323 LABOUR
4358 LABOUR
4409 LABOUR
4441 LABOUR
4464 LABOUR
4497 LABOUR
4520 LABOUR
4553 LABOUR
4576 LABOUR
4610 LABOUR
4633 LABOUR
4666 LABOUR
4699 LABOUR
4722 LABOUR
6392 LABOUR
6429 LABOUR
6455 LABOUR
6487 LABOUR
6520 LABOUR
6540 LABOUR
6569 LABOUR
6589 LABOUR
6609 LABOUR
6638 LABOUR
6658 LABOUR
6687 LABOUR
6709 LABOUR
6739 LABOUR
6768 LABOUR
6788 LABOUR
6817 LABOUR
6837 LABOUR
6867 LABOUR
6887 LABOUR
8219 Labour
8241 Labour
8273 LABOUR
8295 LABOUR
8327 LABOUR
8349 LABOUR
8381 LABOUR
8403 LABOUR
8435 LABOUR
8457 LABOUR
8489 LABOUR
8511 LABOUR
8542 LABOUR
8564 LABOUR
8596 LABOUR
10469 LABOUR
10492 LABOUR
10526 LABOUR
10556 LABOUR
10579 LABOUR
10611 LABOUR
10634 LABOUR
10667 LABOUR
10704 LABOUR
10727 LABOUR
10759 LABOUR
10782 LABOUR
10813 LABOUR
10867 LABOUR
10920 LABOUR
10973 LABOUR
11026 LABOUR
11079 LABOUR
11144 LABOUR
11185 LABOUR
11225 LABOUR
11256 LABOUR
11298 LABOUR
11338 LABOUR
11367 LABOUR
11409 LABOUR
11450 LABOUR
11481 LABOUR
11522 LABOUR
11563 LABOUR
11585 LABOUR
11613 LABOUR
11631 LABOUR
11656 LABOUR
11674 LABOUR
11692 LABOUR
11720 LABOUR
11738 LABOUR
11766 LABOUR
11784 LABOUR
11800 LABOUR
11827 LABOUR
11886 LABOUR
11925 LABOUR
11952 LABOUR
11990 LABOUR
12029 LABOUR
12068 LABOUR
12112 LABOUR
12142 LABOUR
15801 LABOUR
15845 LABOUR
15887 LABOUR
15967 LABOUR
16658 LABOUR
16676 LABOUR
16704 LABOUR
16722 LABOUR
16749 LABOUR
16767 LABOUR
16793 LABOUR
16811 LABOUR
16855 LABOUR
16899 LABOUR
16931 LABOUR
16986 LABOUR
17073 LABOUR
17116 LABOUR
17160 LABOUR
17205 LABOUR
17238 LABOUR
17283 LABOUR
17324 LABOUR
17370 LABOUR
17414 LABOUR
17515 LABOUR
17747 LABOUR
17997 LABOUR
18096 LABOUR
18293 LABOUR
18381 LABOUR
18533 LABOUR
18634 LABOUR
18763 LABOUR
18857 LABOUR
18976 LABOUR
19014 LABOUR
19057 LABOUR
19100 LABOUR
19130 LABOUR
19162 LABOUR
19184 LABOUR
19451 LABOUR
19495 LABOUR
19542 LABOUR
19576 LABOUR
19665 LABOUR
19749 LABOUR
19801 LABOUR
19840 LABOUR
21091 LABOUR
21128 LABOUR
21167 LABOUR
21205 LABOUR
21243 LABOUR
21282 LABOUR
21310 LABOUR
21346 LABOUR
21382 LABOUR
21411 LABOUR
21451 LABOUR
21536 LABOUR
21625 LABOUR
21663 LABOUR
21701 LABOUR
21784 LABOUR
21822 LABOUR
21862 LABOUR
21901 LABOUR
21932 LABOUR
21970 LABOUR
22008 LABOUR
22046 LABOUR
22092 LABOUR
22133 LABOUR
22165 LABOUR
22205 LABOUR
22317 LABOUR
22356 LABOUR
22393 LABOUR
22434 LABOUR
22464 LABOUR
22508 LABOUR
22551 LABOUR
22592 LABOUR
22632 LABOUR
22674 LABOUR
22702 LABOUR
22735 LABOUR
22770 LABOUR
22818 LABOUR
22861 LABOUR
22902 LABOUR
22934 LABOUR
22975 LABOUR
23017 LABOUR
23304 LABOUR
LABOUR For boring and
6336 removing
LABOUR for theboring
pipe- and
6368 removing
Labour forthe pipe-C.I.
cutting
11579 18.83 pipe with steel saw.
10311 Labour for cutting holes
10360 Labour for cutting holes
18968 Labour for fabrication
19050 Labour for fabrication
19083 Labour
LABOURforforfabrication
fixing M.S.
18934 foot rests
Labour for fixing precast
20719 9999 R.C.C. grating and frame L.S. 34.06 2
3687 Labour for laying
3712 Labour for laying
3746 Labour for laying metre
3783 LABOUR for laying
3807 LABOUR for laying metre
3844 LABOUR for laying
3880 Labour for laying
3906 LABOUR for laying
3944 LABOUR for laying
3970 LABOUR for laying
4007 LABOUR for laying
8626 Labour for laying
8661 Labour for laying
8696 Labour for laying
8723 Labour for laying
8759 Labour for laying
8784 Labour for laying
8819 Labour for laying
8856 Labour for laying
8881 Labour for laying
8915 Labour for laying
9377 Labour for laying
9403 Labour for laying
9438 Labour for laying
9464 Labour for laying
9499 Labour for laying
9535 Labour for laying
9561 Labour for laying
9597 Labour for laying
9624 Labour for laying
9661 Labour for laying
9854 Labour for laying
9880 Labour for laying
9916 Labour for laying
9951 Labour for laying
9977 Labour for laying
10013 Labour for laying
10039 Labour for laying
10073 Labour for laying
10109 Labour for laying
10135 Labour
Labour for
for laying
laying dirt box
7731 strainer
9999 Labour for laying dirt box L.S. 39 2
7752 9999 strainer
Labour for laying dirt box L.S. 52 2
7782 9999 strainer
Labour for laying dirt box L.S. 65 2
7803 9999 strainer
Labour for laying double L.S. 104 2
7527 9999 acting
Labourair
forvalve
layingProviding
double L.S. 39 2
7550 9999 acting air valve Providing
Labour for laying double L.S. 39 2
7583 9999 acting air valve Providing L.S. 52 2
3506 LABOUR
LABOUR forfor laying
laying pipe
sluice
4761 valve
LABOUR for laying sluice
4786 valve
LABOUR for laying sluice
4823 valve
LABOUR for laying sluice
4858 valve
LABOUR for laying sluice
4884 valve
LABOUR for laying sluice
4921 valve
LABOUR for laying sluice
4958 valve
LABOUR for laying sluice
4984 valve
LABOUR for laying sluice
5020 valve
LABOUR for laying sluice
5056 valve
LABOUR for laying sluice
5082 valve
LABOUR for laying sluice
5118 valve
3537 LABOUR
Labour for forlaying
layingwater
tee-
7620 9999 meter
Labour for laying water L.S. 39 2
7643 9999 meter
Labour for laying water L.S. 52 2
7676 9999 meter
Labour for laying water L.S. 65 2
7699 9999 meter
materilas upto floor five L.S. 104 2
17506 level
materilas upto floor five
17738 level
materilas upto floor five
17987 level
materilas upto floor five
18086 level
545 LABOUR:
568 LABOUR:
601 LABOUR:
636 LABOUR:
660 LABOUR:
701 LABOUR:
735 LABOUR:
760 LABOUR:
800 LABOUR:
838 LABOUR:
866 LABOUR:
905 LABOUR:
933 LABOUR:
971 LABOUR:
1004 LABOUR:
1033 LABOUR:
1072 LABOUR:
1330 LABOUR:
1387 LABOUR:
1415 LABOUR:
single pile in accordance
23253 7252 with
singleISpile
: per test
in accordance 1 15000 15000
23270 7253 with
with IS
IS :Code
per test
of practice IS 1 23600 23600
23245 20.8 : 2911
9010 18.23 laying metre
9034 18.23 laying metre
9069 18.23 laying metre
9093 18.23 laying metre
9128 18.23 laying metre
9164 18.23 laying metre
9189 18.23 laying metre
9224 18.23 laying metre
9249 18.23 laying metre
9285 18.23 laying metre
9721 18.23 laying metre
9816 18.23 laying metre
9309 laying metre
9344 laying metre
9756 laying metre
9781 laying
iron S&S or flanged pipes metre
3501 18.23 (excluding
(excluding cost cost of
of pipe).
3533 18.24 specials).
16974 1717 length = 4 Nos.)
17061 1718 length = 4 Nos.)
17095 1719 length = 4 Nos.)
17182 1721 length = 4 Nos.)
17225 1723 length = 4 Nos.)
17270 1724 length = 4 Nos.)
17312 1725 length = 4 Nos.)
17357 1726 length = 4 Nos.)
17401 1727 length
Length =of4pipe Nos.)= 1m.
19700 Hence, Qty
Length of pipe = 1m.
19614 Hence,
Les 33%Qty for =pipe
1 / etc. = (-)
10368 0.011
Les 33% cum
for pipe etc. = (-)
10409 0.01856
Les cumpipe etc. = (-)
33% for
10318 0.102 cum
Les 33% for pipe etc. = (-)
10324 0.59 sqm
3.14x(0.15)²/4x10 = (-)
10430 0.177 cum
Less cover = 0.60x0.45
20347 =(-) 0.27
Less sqm
cover = 0.61x0.455m
17512 =3.14/4x(0.50)²
(-) 0.278 sqm= (-) 0.196
17744 sqm
3.14/4x(0.50)² =(-) 0.196
20398 sqm
3.14/4x(0.56)² = (-) 0.246
17994 sqm
3.14/4x(0.56)² = (-) 0.246
18093 sqm
3.14/4x(0.56)² =(-) 0.246
20447 sqm
Less cover
20483 =3.14/4x(0.90)²x0.15
Less cover 3.14/4x(0.28)²
18280 xLess 0.15 m 3.14/4x(0.28)²
cover
18368 xLess 0.15 m 3.14/4x(0.28)²
cover
18622 xLess0.15 m : (-)
cover 3.14/4x(0.28)²
18750 xLess
0.15 m : (-)
cover 3.14/4x(0.28)²
18844 x 0.15
Less m : (-)
cover 3.14/4x(0.28)²
20288 xLess
0.15cover (-)0.037 cum
m : =
20033 3.14/4x(0.50)²x0.15m
Less cover 3.14/4x(0.56)²
17973 = (-) 0.246 sqm
Less cover 3.14/4x(0.56)²
18072 = (-) 0.246 sqm
19218 Less cover with frame
19245 Less cover with frame
19281 Less cover with frame
19322 Less cover with frame
19347 Less cover with frame
19386 Less cover with frame
19425 Less
Less cover with frame
for cover
19912 0.61x0.455x0.15m
Less for cover
17734 0.7854x(0.50)²x0.15m
Less for cover
17983 0.7854x(0.56)²x0.15m
Less for cover
18082 0.7854x(0.56)²x0.15m
Less for cover
19967 3.14/4x(0.50)²x0.15m
3.142/4(21.8)²x10 =
6078 (-)0.004
Less cum.
for pipe
6124 =3.142/4(27.3)²x10
Less for pipe =
17708 1.20x3.14/4x(0.15m)²
Less for pipe
18050 1.20x3.14/4x(0.15m)²
Less for pipe
19959 1.20x3.14/4x(0.15m)²
Less for pipe
19941 2x3.14x(0.15m)²x0.23
Less for pipe m
18042 2x3.14x(0.15m)²x0.23m
Less for pipe
17700 2x3.14x(0.15m)²x0.23m
Less for pipe =
6154 3.142/4(34.2)²x10
Less for pipe =
6174 3.142/4(42.9)²x10
Less for pipe =
6206 3.142/4(48.8)²x10
Less for pipe =
6226 3.142/4(60.8)²x10
3.142/4(76.6)²x10 ==
6256 (-)0.046cum.
Less for pipe
6275 3.142/4(89.9)²x10
Less for R.C.C cover= with
20384 frame
Less for R.C.C cover with
20433 frame
Less labour for not lifting
20611 the materials
Less labour forupto
not floor
lifting
20686 the materials upto floor
Less labour for not lifting
20862 the
Lessmaterilas
labour forupto
not floor
lifting
20926 the materilas upto floor
20768 Less
Less pipe
pipe :
18359 0.91x3.14/4x(0.15)²
Less pipe :
18262 0.91x3.14/4x(0.15)2²
pipe :1.22x3.14/4x(0.15)²(
18511 -)
pipe :1.22x3.14/4x(0.15)²(
20284 -)
pipe= 0.0216 cum
:1.4x3.14/4x(0.15)²(-)
20243 =pipe
0.025 cum
:1.52x3.14/4x(0.15)²(
18743 -) = 0.027
Less pipe =cum
19487 1/2x3.14x0.23x0.23x0.23
Less pipe =
19534 1/2x3.14x0.30x0.30x0.30
Less pipe =
19568 1/2x3.14x0.45x0.45x0.30
1.4x3.14/4x(0.15)² = (-)
20026 0.025 cum
Less pipe
19635 1/2x3.14x0.10x0.10x0.23
Less pipe
19710 1/2x3.14x0.15x0.15x0.23
Less pipe 2x3.14/4x(0.10)²
20777 =Less(-) 0.016 sqm
pipe 3x3.14/4x(0.10)²
20836 =Less
(-) 0.02 sqm
pipe 5x3.14/4x(0.10)²
20916 =5x3.14x(0.10)²x0.23
(-) 0.04 sqm m=
20898 (-) 0.009 cum
19644 Less pipe portion
19719 Less pipe portion
19782 Less pipe portion
19828 Less
Less pipe portion
portion cover with
20393 frame
Less portion cover with
20442 frame
Less portion cover with
20341 frame = 0.85x
0.112x0.112x0.076
5179 =(-)0.00094
Less surface box
5255 3.142/4xd2x0.18m -
19299 19.19.2 M D - 10 qty. of concrete
m length
16081 4.1.10 reqd.
M.S. 20 = 2.44
mm cum
square bar
19046 0.75 m @ 3.137
M.S. 20 mm square kg/mbar
18922 0.75 m @ 3.137 kg/m =
22889 7182 M.S.
M.S. clamps
clamps for
for pile
pile shoe
shoe kilogram 35 43
22929 7182 @ M.S.35clamps
kg per pile
for pile shoe kilogram 35 43
21777 7182 of M.S.35clamps
kg per pile
for pile shoe kilogram 35 43
21855 7182 M.S.
of 35clamps
kg per pile
for pile shoe kilogram 35 43
21886 7182 of M.S. clamps for pile shoe kilogram
35 kg per pile 35 43
21925 7182 of M.S.35clamps
kg per pile
for pile shoe kilogram 35 43
21963 7182 of M.S.35clamps
kg per pile
for pile shoe kilogram 35 43
22001 7182 M.S.
of 35clamps for pile shoe kilogram
kg per pile 35 43
22032 7182 of M.S. clamps for pile shoe kilogram
35 kg per pile 35 43
22812 7182 of M.S.35clamps for pile shoe kilogram
kg per pile 35 43
22855 7182 of M.S.35clamps for pile shoe kilogram
kg per pile 35 43
22969 7182 M.S.
of 35clamps for pile shoe kilogram
kg per pile 35 43
23011 7182 of of 35 kg per pile @ 35 kg kilogram
35 kg per pile 35 43
21815 7182 perM.S. roumd bars 20 mm kilogram 35 43
19079 dia
M.S.0.75
roundm@ brass 20 mm
18964 dia 0.75 m @ 2.47kgfor
M.S.reinforcement /m=
20865 slab
M.S.reinforcement for
20937 slab for 0.17 cum
21779 MACHINERY
21817 MACHINERY
21857 MACHINERY
21888 MACHINERY
21927 MACHINERY
21965 MACHINERY
22003 MACHINERY
22041 MACHINERY
22084 MACHINERY
22116 MACHINERY
22157 MACHINERY
22197 MACHINERY
22309 MACHINERY
22348 MACHINERY
22378 MACHINERY
22417 MACHINERY
22456 MACHINERY
22502 MACHINERY
22545 MACHINERY
22586 MACHINERY
22626 MACHINERY
22668 MACHINERY
22696 MACHINERY
22729 MACHINERY
22764 MACHINERY
22814 MACHINERY
22857 MACHINERY
22898 MACHINERY
22930 MACHINERY
22971 MACHINERY
23013 MACHINERY
direction of Engineer-in-
7082 charge.
matching surface after
10388 18.78 housing G.I. pipe
Making chases etc.7.5 x
upto
211 7.5 cm. in
Making wallsupto
chases and 7.5 x
246 7.5 cm. in
Making wallsupto
chases and 7.5 x
270 7.5 cm. in walls
Making chases uptoand 7.5 x
306 7.5 cm. in
Making wallsupto
chases and 7.5 x
698 7.5 cm. in
Making wallsupto
chases and 7.5 x
723 7.5 cm. in
Making wallsupto
chases and 7.5 x
757 7.5 cm. in walls
Making chases uptoand 7.5 x
1645 7.5 cm. in
Making wallsupto
chases and 7.5 x
1672 7.5 cm. in
Making wallsupto
chases and 7.5 x
1709 7.5 cm. in walls
Making chases uptoand 7.5 x
1736 7.5 cm. in
Making wallsupto
chases and
12097 7.5x7.5
Making cm.in
chaseswalls
upto
12136 7.5x7.5 cm.in walls
7.5x7.5cm in walls and
2349 making
necessary channels for
19477 19.21 the drain
cutting etc.
and complete
threading :
the
2648 18.13 pipe etc. complete :
212 18.78 making good the same
247 18.78 making good the same
271 18.78 making good the same
307 18.78 making good the same
699 18.78 making good the same
724 18.78 making good the same
758 18.78 making good the same
1646 18.78 making good the same
1673 18.78 making good the same
1710 18.78 making good the same
1737 making
includinggood the same
disposal of
10424 18.79 malba.
long complete as per
21038 19.32 standard design.with
manhole cover
19411 frame
manhole- E.H.D.
cover- with
35
18298 frame
manhole- H.D. - 20with
cover
18396 frame - H.D.
manhole cover - 20with
18640 frame
manhole- H.D. - 20with
cover
18768 frame
manhole- H.D. - 20with
cover
19381 frame - H.D.
manhole - 20with
cover
19240 frame - L.D.
manhole cover - 25with
19276 frame
manhole- L.D. - 25with
cover
19342 frame
Mason- (brick
M.D. -layer)
10 1st
10312 23 class
Mason (brick layer) 1st day 0.16 505.17
10361 23 class
Mason (brick layer) 1st day 0.83 505.17
15802 23 class
Mason (brick layer) 1st day 1 505.17
15846 23 class
Mason (brick layer) 1st day 1.5 505.17
15888 23 class
Mason (brick layer) 1st day 1.75 505.17
15933 23 class
Mason (brick layer) 1st day 2.25 505.17
15968 23 class
Mason (brick layer) 1st day 2.5 505.17
16856 23 class
Mason (brick layer) 1st day 0.32 505.17
16900 23 class
Mason (brick layer) 1st day 0.39 505.17
16932 23 class
Mason (brick layer) 1st day 0.54 505.17
16987 23 class
Mason (brick layer) 1st
17074 23 class
Mason (brick layer) 1st day 0.75 505.17
17117 23 class
Mason (brick layer) 1st day 0.81 505.17
17161 23 class
Mason (brick layer) 1st day 0.92 505.17
17206 23 class
Mason (brick layer) 1st day 1.03 505.17
17239 23 class
Mason (brick layer) 1st day 1.14 505.17
17284 23 class
Mason (brick layer) 1st day 1.25 505.17
17325 23 class
Mason (brick layer) 1st day 1.36 505.17
17371 23 class
Mason (brick layer) 1st day 1.47 505.17
17415 23 class
Mason (brick layer) 1st day 1.59 505.17
17517 23 class
Mason (brick layer) 1st day 0.06 505.17
17605 23 class
Mason (brick layer) 1st
17749 23 class
Mason (brick layer) 1st day 0.08 505.17
17999 23 class
Mason (brick layer) 1st day 0.08 505.17
18098 23 class
Mason (brick layer) 1st day 0.08 505.17
18295 23 class
Mason (brick layer) 1st day 0.06 505.17
18393 23 class
Mason (brick layer) 1st day 0.06 505.17
18535 23 class day 0.1 505.17
Mason (brick layer) 1st
18636 23 class
Mason (brick layer) 1st day 0.1 505.17
18765 23 class
Mason (brick layer) 1st day 0.1 505.17
18859 23 class
Mason (brick layer) 1st day 0.1 505.17
18935 23 class
Mason (brick layer) 1st day 0.02 505.17
18977 23 class
Mason (brick layer) 1st day 0.02 505.17
19015 23 class
Mason (brick layer) 1st day 0.02 505.17
19060 23 class
Mason (brick layer) 1st day 0.05 505.17
19589 23 class
Mason (brick layer) 1st day 0.16 505.17
21092 23 class
Mason (brick layer) 1st day 0.5 505.17
21168 23 class
Mason (brick layer) 1st day 0.02 505.17
21206 23 class
Mason (brick layer) 1st day 0.03 505.17
21244 23 class
Mason (brick layer) 1st day 0.375 505.17
21283 23 class
Mason (brick layer) 1st day 0.46 505.17
21311 23 class
Mason (brick layer) 1st day 0.625 505.17
21347 23 class
Mason (brick layer) 1st day 0.68 505.17
21383 23 class
Mason (brick layer) 1st day 0.795 505.17
21412 23 class
Mason (brick layer) 1st day 1.15 505.17
21452 23 class
Mason (brick layer) 1st day 0.375 505.17
21501 23 class
Mason (brick layer) 1st
21537 23 class
Mason (brick layer) 1st
21626 23 class
Mason (brick layer) 1st day 0.68 505.17
21664 23 class
Mason (brick layer) 1st day 0.795 505.17
21702 23 class
Mason (brick layer) 1st day 1.15 505.17
10392 class
Mason (brick layer) 1st day 0.25 505.17
19103 class
Mason (brick layer) 1st day 0.05 505.17
19498 class
Mason (brick layer) 1st day 0.12 505.17
19545 class
Mason (brick layer) 1st day 0.12 505.17
19668 class
Mason (brick layer) 1st day 0.7 505.17
19753 class
Mason (brick layer) 1st day 0.85 505.17
19804 class
Mason (brick layer) 1st day 0.04 505.17
19853 class
Mason (brick layer) 2nd day 0.05 505.17
10313 24 class
Mason (brick layer) 2nd day 0.16 403.67
10362 24 class
Mason (brick layer) 2nd day 0.83 403.67
10393 24 class
Mason (brick layer) 2nd day 0.25 403.67
15803 24 class
Mason (brick layer) 2nd day 1 403.67
15847 24 class
Mason (brick layer) 2nd day 1.5 403.67
15889 24 class
Mason (brick layer) 2nd day 1.75 403.67
15934 24 class
Mason (brick layer) 2nd day 2.25 403.67
15969 24 class
Mason (brick layer) 2nd day 2.5 403.67
16857 24 class
Mason (brick layer) 2nd day 0.32 403.67
16901 24 class
Mason (brick layer) 2nd day 0.39 403.67
16933 24 class
Mason (brick layer) 2nd day 0.54 403.67
16988 24 class
Mason (brick layer) 2nd
17075 24 class
Mason (brick layer) 2nd day 0.75 403.67
17118 24 class day 0.81 403.67
Mason (brick layer) 2nd
17162 24 class
Mason (brick layer) 2nd day 0.92 403.67
17207 24 class
Mason (brick layer) 2nd day 1.03 403.67
17240 24 class
Mason (brick layer) 2nd day 1.14 403.67
17285 24 class
Mason (brick layer) 2nd day 1.25 403.67
17326 24 class
Mason (brick layer) 2nd day 1.36 403.67
17372 24 class
Mason (brick layer) 2nd day 1.47 403.67
17416 24 class
Mason (brick layer) 2nd day 1.59 403.67
17518 24 class
Mason (brick layer) 2nd day 0.06 403.67
17607 24 class
Mason (brick layer) 2nd
17750 24 class
Mason (brick layer) 2nd day 0.08 403.67
18000 24 class
Mason (brick layer) 2nd day 0.08 403.67
18099 24 class
Mason (brick layer) 2nd day 0.08 403.67
18536 24 class
Mason (brick layer) 2nd day 0.1 403.67
18637 24 class
Mason (brick layer) 2nd day 0.1 403.67
18860 24 class
Mason (brick layer) 2nd day 0.1 403.67
18936 24 class
Mason (brick layer) 2nd day 0.02 403.67
18978 24 class
Mason (brick layer) 2nd day 0.02 403.67
19016 24 class
Mason (brick layer) 2nd day 0.2 403.67
19061 24 class
Mason (brick layer) 2nd day 0.05 403.67
19104 24 class
Mason (brick layer) 2nd day 0.05 403.67
19499 24 class
Mason (brick layer) 2nd day 0.12 403.67
19546 24 class
Mason (brick layer) 2nd day 0.12 403.67
19590 24 class
Mason (brick layer) 2nd day 0.16 403.67
19669 24 class
Mason (brick layer) 2nd day 0.7 403.67
19754 24 class
Mason (brick layer) 2nd day 0.85 403.67
19805 24 class
Mason (brick layer) 2nd day 0.04 403.67
19854 24 class
Mason (brick layer) 2nd day 0.05 403.67
21093 24 class
Mason (brick layer) 2nd day 0.5 403.67
21169 24 class
Mason (brick layer) 2nd day 0.02 403.67
21207 24 class
Mason (brick layer) 2nd day 0.03 403.67
21245 24 class
Mason (brick layer) 2nd day 0.375 403.67
21284 24 class
Mason (brick layer) 2nd day 0.46 403.67
21312 24 class
Mason (brick layer) 2nd day 0.625 403.67
21348 24 class
Mason (brick layer) 2nd day 0.68 403.67
21384 24 class
Mason (brick layer) 2nd day 0.795 403.67
21413 24 class
Mason (brick layer) 2nd day 1.15 403.67
21453 24 class
Mason (brick layer) 2nd day 0.375 403.67
21503 24 class
Mason (brick layer) 2nd
21599 24 class
Mason (brick layer) 2nd day 0.625 403.67
21627 24 class
Mason (brick layer) 2nd day 0.68 403.67
21665 24 class
Mason (brick layer) 2nd day 0.795 403.67
18296 24 Mason
class S.F.R.C
(brickcover
layer) 2nd day 0.06 403.67
18394 24 class S.F.R.C cover
Mason (brick layer) 2nd day 0.06 403.67
18766 24 class S.F.R.C cover day 0.1 403.67
15 MATERIAL
49 MATERIAL
73 MATERIAL
108 MATERIAL
169 MATERIAL
207 MATERIAL
242 MATERIAL
266 MATERIAL
302 MATERIAL
350 MATERIAL
375 MATERIAL
409 MATERIAL
444 MATERIAL
469 MATERIAL
504 MATERIAL
1436 MATERIAL
1506 MATERIAL
1531 MATERIAL
1566 MATERIAL
1601 MATERIAL
1630 MATERIAL
1667 MATERIAL
1704 MATERIAL
1731 MATERIAL
1773 MATERIAL
1810 MATERIAL
1834 MATERIAL
1870 MATERIAL
1907 MATERIAL
1933 MATERIAL
1968 MATERIAL
2031 MATERIAL
2067 MATERIAL
2135 MATERIAL
2171 MATERIAL
2196 MATERIAL
2233 MATERIAL
2270 MATERIAL
2299 MATERIAL
2338 MATERIAL
2386 MATERIAL
2423 MATERIAL
2450 MATERIAL
2487 MATERIAL
2522 MATERIAL
2548 MATERIAL
2586 MATERIAL
2623 MATERIAL
2654 MATERIAL
2685 MATERIAL
2706 MATERIAL
2737 MATERIAL
2754 MATERIAL
2783 MATERIAL
2800 MATERIAL
2829 MATERIAL
2845 MATERIAL
2862 MATERIAL
2891 MATERIAL
2909 MATERIAL
2937 MATERIAL
2955 MATERIAL
2975 MATERIAL
3003 MATERIAL
3021 MATERIAL
3051 MATERIAL
3067 MATERIAL
3095 MATERIAL
3111 MATERIAL
3139 MATERIAL
3155 MATERIAL
3172 MATERIAL
3197 MATERIAL
3214 MATERIAL
3239 MATERIAL
3259 MATERIAL
3284 MATERIAL
3304 MATERIAL
3330 MATERIAL
3347 MATERIAL
3376 MATERIAL
3392 MATERIAL
3422 MATERIAL
3438 MATERIAL
3458 MATERIAL
3486 MATERIAL
3559 MATERIAL
3590 MATERIAL
3625 MATERIAL
3646 MATERIAL
3678 MATERIAL
3704 MATERIAL
3739 MATERIAL
3774 MATERIAL
3835 MATERIAL
3861 MATERIAL
3897 MATERIAL
3934 MATERIAL
3961 MATERIAL
3997 MATERIAL
4034 MATERIAL
4060 MATERIAL
4095 MATERIAL
4121 MATERIAL
4156 MATERIAL
4192 MATERIAL
4218 MATERIAL
4255 MATERIAL
4290 MATERIAL
4316 MATERIAL
4351 MATERIAL
4386 MATERIAL
4405 MATERIAL
4437 MATERIAL
4460 MATERIAL
4493 MATERIAL
4516 MATERIAL
4549 MATERIAL
4572 MATERIAL
4606 MATERIAL
4629 MATERIAL
4662 MATERIAL
4685 MATERIAL
4718 MATERIAL
4755 MATERIAL
4780 MATERIAL
4817 MATERIAL
4852 MATERIAL
4878 MATERIAL
4915 MATERIAL
4952 MATERIAL
4978 MATERIAL
5014 MATERIAL
5050 MATERIAL
5076 MATERIAL
5112 MATERIAL
5150 MATERIAL
5214 MATERIAL
5298 MATERIAL
5369 MATERIAL
5439 MATERIAL
5522 MATERIAL
5913 MATERIAL
5941 MATERIAL
5959 MATERIAL
5977 MATERIAL
6004 MATERIAL
6022 MATERIAL
6098 MATERIAL
6426 MATERIAL
6449 MATERIAL
6484 MATERIAL
6517 MATERIAL
6537 MATERIAL
6557 MATERIAL
6586 MATERIAL
6606 MATERIAL
6635 MATERIAL
6655 MATERIAL
6684 MATERIAL
6706 MATERIAL
6736 MATERIAL
6756 MATERIAL
6785 MATERIAL
6805 MATERIAL
6834 MATERIAL
6884 MATERIAL
6918 MATERIAL
6940 MATERIAL
6974 MATERIAL
6993 MATERIAL
7022 MATERIAL
7041 MATERIAL
7068 MATERIAL
7084 MATERIAL
7103 MATERIAL
7140 MATERIAL
7167 MATERIAL
7272 MATERIAL
7291 MATERIAL
7318 MATERIAL
7338 MATERIAL
7367 MATERIAL
7384 MATERIAL
7404 MATERIAL
7430 MATERIAL
7449 MATERIAL
7474 MATERIAL
7494 MATERIAL
7524 MATERIAL
7547 MATERIAL
7580 MATERIAL
7638 MATERIAL
7671 MATERIAL
7694 MATERIAL
7728 MATERIAL
7749 MATERIAL
7779 MATERIAL
7800 MATERIAL
7832 MATERIAL
7850 MATERIAL
7879 MATERIAL
7897 MATERIAL
7926 MATERIAL
7947 MATERIAL
7974 MATERIAL
7991 MATERIAL
8019 MATERIAL
8038 MATERIAL
8070 MATERIAL
8090 MATERIAL
8121 MATERIAL
8138 MATERIAL
8169 MATERIAL
8186 MATERIAL
8216 MATERIAL
8238 MATERIAL
8270 MATERIAL
8292 MATERIAL
8324 MATERIAL
8346 MATERIAL
8378 MATERIAL
8400 MATERIAL
8432 MATERIAL
8454 MATERIAL
8486 MATERIAL
8508 MATERIAL
8539 MATERIAL
8561 MATERIAL
8593 MATERIAL
8617 MATERIAL
8653 MATERIAL
8678 MATERIAL
8713 MATERIAL
8749 MATERIAL
8774 MATERIAL
8809 MATERIAL
8846 MATERIAL
8871 MATERIAL
8905 MATERIAL
8969 MATERIAL
9003 MATERIAL
9027 MATERIAL
9062 MATERIAL
9086 MATERIAL
9121 MATERIAL
9181 MATERIAL
9216 MATERIAL
9241 MATERIAL
9277 MATERIAL
9302 MATERIAL
9336 MATERIAL
9359 MATERIAL
9394 MATERIAL
9429 MATERIAL
9455 MATERIAL
9490 MATERIAL
9552 MATERIAL
9587 MATERIAL
9614 MATERIAL
9651 MATERIAL
9688 MATERIAL
9713 MATERIAL
9748 MATERIAL
9773 MATERIAL
9808 MATERIAL
9845 MATERIAL
9871 MATERIAL
9907 MATERIAL
9933 MATERIAL
9968 MATERIAL
10004 MATERIAL
10030 MATERIAL
10064 MATERIAL
10100 MATERIAL
10126 MATERIAL
10162 MATERIAL
10218 MATERIAL
10238 MATERIAL
10264 MATERIAL
10281 MATERIAL
10464 MATERIAL
10487 MATERIAL
10521 MATERIAL
10542 MATERIAL
10574 MATERIAL
10606 MATERIAL
10629 MATERIAL
10662 MATERIAL
10722 MATERIAL
10754 MATERIAL
10777 MATERIAL
10811 MATERIAL
10865 MATERIAL
10918 MATERIAL
10971 MATERIAL
11024 MATERIAL
11077 MATERIAL
11141 MATERIAL
11182 MATERIAL
11222 MATERIAL
11253 MATERIAL
11295 MATERIAL
11326 MATERIAL
11364 MATERIAL
11406 MATERIAL
11447 MATERIAL
11478 MATERIAL
11519 MATERIAL
11560 MATERIAL
11847 MATERIAL
11876 MATERIAL
11915 MATERIAL
11942 MATERIAL
11980 MATERIAL
12019 MATERIAL
12048 MATERIAL
12089 MATERIAL
12129 MATERIAL
12173 MATERIAL
12190 MATERIAL
12216 MATERIAL
12233 MATERIAL
12279 MATERIAL
12308 MATERIAL
12325 MATERIAL
12342 MATERIAL
12368 MATERIAL
12385 MATERIAL
12412 MATERIAL
12429 MATERIAL
12446 MATERIAL
12473 MATERIAL
12490 MATERIAL
12517 MATERIAL
12534 MATERIAL
12562 MATERIAL
12577 MATERIAL
12604 MATERIAL
12624 MATERIAL
12648 MATERIAL
12664 MATERIAL
12680 MATERIAL
12706 MATERIAL
12722 MATERIAL
12755 MATERIAL
12771 MATERIAL
12795 MATERIAL
12811 MATERIAL
12827 MATERIAL
12853 MATERIAL
12875 MATERIAL
12901 MATERIAL
12916 MATERIAL
12943 MATERIAL
12960 MATERIAL
12977 MATERIAL
13008 MATERIAL
13024 MATERIAL
13050 MATERIAL
13066 MATERIAL
13092 MATERIAL
13108 MATERIAL
13128 MATERIAL
13154 MATERIAL
13171 MATERIAL
13197 MATERIAL
13214 MATERIAL
13242 MATERIAL
13259 MATERIAL
13276 MATERIAL
13304 MATERIAL
13321 MATERIAL
13348 MATERIAL
13365 MATERIAL
13409 MATERIAL
13426 MATERIAL
13458 MATERIAL
13475 MATERIAL
13502 MATERIAL
13519 MATERIAL
13536 MATERIAL
13562 MATERIAL
13579 MATERIAL
13606 MATERIAL
13623 MATERIAL
13669 MATERIAL
13686 MATERIAL
13714 MATERIAL
13731 MATERIAL
13758 MATERIAL
13775 MATERIAL
13792 MATERIAL
13819 MATERIAL
13836 MATERIAL
13864 MATERIAL
13881 MATERIAL
13913 MATERIAL
13930 MATERIAL
13947 MATERIAL
13973 MATERIAL
13990 MATERIAL
14015 MATERIAL
14032 MATERIAL
14049 MATERIAL
14076 MATERIAL
14093 MATERIAL
14120 MATERIAL
14137 MATERIAL
14154 MATERIAL
14181 MATERIAL
14198 MATERIAL
14226 MATERIAL
14245 MATERIAL
14272 MATERIAL
14289 MATERIAL
14306 MATERIAL
14333 MATERIAL
14354 MATERIAL
14381 MATERIAL
14400 MATERIAL
14427 MATERIAL
14446 MATERIAL
14464 MATERIAL
14492 MATERIAL
14510 MATERIAL
14539 MATERIAL
14557 MATERIAL
14586 MATERIAL
14604 MATERIAL
14635 MATERIAL
14652 MATERIAL
14670 MATERIAL
14696 MATERIAL
14714 MATERIAL
14743 MATERIAL
14760 MATERIAL
14786 MATERIAL
14803 MATERIAL
14820 MATERIAL
14847 MATERIAL
14868 MATERIAL
14895 MATERIAL
14912 MATERIAL
14940 MATERIAL
14957 MATERIAL
14974 MATERIAL
15001 MATERIAL
15022 MATERIAL
15048 MATERIAL
15063 MATERIAL
15089 MATERIAL
15106 MATERIAL
15151 MATERIAL
15168 MATERIAL
15196 MATERIAL
15588 MATERIAL
15602 MATERIAL
15627 MATERIAL
15641 MATERIAL
15655 MATERIAL
15679 MATERIAL
15698 MATERIAL
15726 MATERIAL
15741 MATERIAL
15785 MATERIAL
15830 MATERIAL
15863 MATERIAL
15907 MATERIAL
15952 MATERIAL
16841 MATERIAL
16875 MATERIAL
16919 MATERIAL
16972 MATERIAL
17059 MATERIAL
17093 MATERIAL
17136 MATERIAL
17180 MATERIAL
17223 MATERIAL
17268 MATERIAL
17310 MATERIAL
17355 MATERIAL
17399 MATERIAL
17691 MATERIAL
17768 MATERIAL
18133 MATERIAL
18150 MATERIAL
18179 MATERIAL
18196 MATERIAL
18229 MATERIAL
18795 MATERIAL
18921 MATERIAL
18963 MATERIAL
19008 MATERIAL
19078 MATERIAL
19126 MATERIAL
19158 MATERIAL
19181 MATERIAL
19212 MATERIAL
19238 MATERIAL
19274 MATERIAL
19340 MATERIAL
19379 MATERIAL
19409 MATERIAL
19447 MATERIAL
19482 MATERIAL
19564 MATERIAL
19610 MATERIAL
19696 MATERIAL
19774 MATERIAL
19820 MATERIAL
20515 MATERIAL
21158 MATERIAL
21196 MATERIAL
21772 MATERIAL
21810 MATERIAL
21841 MATERIAL
21881 MATERIAL
21920 MATERIAL
21958 MATERIAL
21996 MATERIAL
22027 MATERIAL
22072 MATERIAL
22111 MATERIAL
22152 MATERIAL
22192 MATERIAL
22304 MATERIAL
22343 MATERIAL
22373 MATERIAL
22412 MATERIAL
22451 MATERIAL
22493 MATERIAL
22536 MATERIAL
22577 MATERIAL
22617 MATERIAL
22692 MATERIAL
22725 MATERIAL
22760 MATERIAL
22838 MATERIAL
22880 MATERIAL
22921 MATERIAL
22961 MATERIAL
23003 MATERIAL
539 MATERIAL:
562 MATERIAL:
594 MATERIAL:
618 MATERIAL:
653 MATERIAL:
718 MATERIAL:
752 MATERIAL:
999 MATERIAL:
1384 MATERIAL:
1412 MATERIAL:
3800 MATERIALS
21234 MATERIALS :
21263 MATERIALS :
21302 MATERIALS :
21338 MATERIALS :
21366 MATERIALS :
21402 MATERIALS :
21443 MATERIALS :
21528 MATERIALS :
21617 MATERIALS :
21654 MATERIALS :
21683 MATERIALS
Max. external : dia of pipe
6291 =Max. 115mmexternal dia of pipe
6075 = 21.8mm
Max. external dia of pipe
6120 =Max. 27.3mm
external dia of pipe
6150 =Max. 34.2mm
external dia of pipe
6170 =Max.42.9mm
external dia of pipe
6202 = 48.8mm
Max. external dia of pipe
6222 =Max.
60.8mm
external dia of pipe
6271 =measured
89.9mm up to bottom of
22298 pile cap). jointing as per
mechancial
8188 I.S.
machine over
9523 600mm
complete withdia
22086 power
machine unit
complete with
22118 power unit
machine complete with
22159 power
machine unit
complete with
22199 Polymer (PPR) power unit
1159 pipes metre metres long: 100mm dia = 10 2557.3 25573.00 P
19612 38+30+33
metres long: =101 cm say
100mm dia
19776 Length of pipe = 1m.
19698 metresmetres long:
long: 150mm
150mm diadia
19822 Length of pipe = 1m.
Mild steel reinforcement
20619 for
MildR.C.C
steelwork
reinforcement
20710 for R.C.C work
Mild steel reinforcement
17508 for
Mildslab : reinforcement
steel
17740 for
Mildslab : round bar
steel
19081 1003 above
Mild steelmm
12 diabar
round quintal 0.018 5500
18966 above 12 mm dia quintal 0.018 5500
18924 1006 Mild steel square bars quintal 0.024 5500
19048 Mild steel square bars quintal 0.024 5500
21786 30 Mistry day 0.08 403.67
21824 30 Mistry day 0.08 403.67
21864 30 Mistry day 0.08 403.67
21903 30 Mistry day 0.08 403.67
21934 30 Mistry day 0.14 403.67
21972 30 Mistry day 0.16 403.67
22010 30 Mistry day 0.18 403.67
22048 30 Mistry day 0.2 403.67
22094 30 Mistry day 0.12 403.67
22135 30 Mistry day 0.12 403.67
22167 30 Mistry day 0.12 403.67
22207 30 Mistry day 0.14 403.67
22319 30 Mistry day 0.12 403.67
22358 30 Mistry day 0.14 403.67
22395 30 Mistry day 0.16 403.67
22436 30 Mistry day 0.18 403.67
22466 30 Mistry day 0.25 403.67
22510 30 Mistry day 0.08 403.67
22553 30 Mistry day 0.08 403.67
22594 30 Mistry day 0.08 403.67
22634 30 Mistry day 0.08 403.67
22676 30 Mistry day 0.02 403.67
22704 30 Mistry day 0.02 403.67
22737 30 Mistry day 0.02 403.67
22772 30 Mistry day 0.02 403.67
22820 30 Mistry day 0.12 403.67
22863 30 Mistry day 1.08 403.67
22904 30 Mistry day 0.12 403.67
22936 30 Mistry day 0.12 403.67
22977 30 Mistry day 0.12 403.67
23019 30 Mistry
mm as trench depth is day 0.12 403.67
16055 less
2864 9988 mm dia
2893 9988 mm dia
2911 9988 mm dia
2939 9988 mm dia
2957 9988 mm dia
3069 9988 mm dia
3113 9988 mm dia
3157 9988 mm dia
3199 9988 mm dia
3241 9988 mm dia
3286 9988 mm dia
2831 mm
mm dia
outer dia X 15 mm
15050 nominal
mm outer diadia
threaded
X 20 mm
15065 nominal dia
mm outer dia threaded
X 25 mm
15091 nominal dia threaded
mm outer dia X 32 mm
15108 nominal
mm outer diadia
threaded
X 32 mm
15136 nominal dia threaded
mm outer dia X 40 mm
15170 nominal
mm outer diadia
threaded
X 50 mm
15198 nominal dia threaded
mm outer dia X40 mm
15153 nominal
modular dia threaded
exturded burnt
18904 fly ash sewer
mortar 1:1 (1 bricks
cement : 1
19660 fine sand)
mortar 1:1 (1 cement : 1
19735 fine sand)
mortar 1:4 ( 1 cement : 4
20521 coarse
mortar sand)
1:4 ( 1 cement : 4
20660 coarse sand)
mortar 1:4 ( 1 cement : 4
20766 coarse sand)
mortar 1:4 ( 1 cement : 4
20826 fine sand)
mortar 1:4 (1 cement : 4
18153 coarse
mortar 1:4 (1) cement : 4
sand
16565 coarse sand)
mortar 1:4 (1 cement :4
16454 coarse sand)
mortar 1:4 (1 cement :4
18037 coarse
mortar sand)
1:5 (1 Cement : 5
20137 fine sand)
mortar 1:5 (1 Cement : 5
20158 fine 0.225-0.029
Net sand) = 0.196
19833 cum Say 0.20 cum
Net 2.561 - 0.026 = 2.535
20203 cum Say 2.54
Net 4.184 cum=Qty
- 0.181 in
4.003
20218 cum Say 4.00 cum
Net difference = 0.49 -
20245 0.29difference
Net = 0.20 cum= 4.38 -
20224 2.89 = 1.49
Net qty cumcum Say
= 0.168
20343 5.3 0.17 cum
20027 Net qty = 0.290 cum
19969 Net qty = 0.31 cum
20348 5.9.3 Net
Net qty
qty == 0.45
0.934sqmcum Say
19943 0.93 cum
Net qty = 2.54+0.35 =
20020 2.89 cum
Net qty 0.244 cum Say
20435 0.24 cum
Net qty 0.264 cum Say
20386 0.26 cum
Net Qty 0.310-0.031 =
19724 0.279 cum
Net qty. = 1.592 (-) 0.045
20599 = 1.547 cum
19712 Net
Net Qty=
Qty= 0.005
0.009 cum
- 0.002 =
19637 0.007 cum
Net qty= 0.019 cum Say
20485 0.02 cum0.019 cum Say
Net qty=
20494 0.02 cum
Net qty= 0.086 cum Say
20289 0.09
Net Qty= cum 0.125 cum Say
20844 0.13 cum
19906 Net
Net qty= Qty= 0.16
0.166cum
cum Say
20924 0.17 cum
Net Qty= 0.18-0.018 =
19787 0.162
Net Qty= cum0.206
Say 0.16
cumcum
Say
20770 0.21 cum
Net qty= 0.215 cum Say
19914 0.22
Net Qty= cum 0.224 cum Say
20829 0.22
Net Qty= cum 0.229-0.016 =
19649 0.213
Net qty= cum Say 0.21
0.244 cum cum
Say
20444 0.24 cum
Net Qty= 0.255 cum Say
20899 6.1.1 0.26
Net qty= cum0.264 cum Say
20395 0.26
Net qty= cum0.834 sqm
20448 Say
Net .83 qty=sqm
0.884 sqm
20399 Say .88
Net Qty=sqm
0.901 sqm Say
20778 0.90 sqm
Net Qty= 0.908 sqm Say
20935 0.91 sqm
20837 Net Qty= 1.05 sqm
20917 Net Qty= 1.34 sqm
20675 Net Qty= 2.36 sqm
21058 Net
Net qty= qty==2.74 cumcum Say
0.2554
20285 0.26 cum
Net qty=0.168 cum Say
20331 0.17quantity
Net cum 0.107 cum (-)
16340 0.021 cum 0.107 cum (-)
Net quantity
16391 0.021 cum 0.107 cum (-)
Net quantity
16450 0.023 cum 0.107 cum (-)
Net quantity
16504 0.023
Net cum 0.107 cum (-)
quantity
16561 0.026 cum 0.107 cum (-)
Net quantity
16616 0.026 cum 0.557-0.026
Net quantity
18246 =Net 0.531 Say 0.53
quantity 0.557-0.026
18345 = 0.531
Net Say 0.53
quantity 1.320-0.026
20079 =Net 1.294 Say
quantity 1.96-0.026 =
20270 1.934
Net quantity 3.735-0.052
18729 =Net3.683 cum 3.735-0.052
quantity
18811 =Net
3.683 cum 0.086 cum
Quantity=
18846 Say 0.09 cum
19102 23 new M.S. foot rests
19059 new M.S. foot rests
20338 nominal size )
17732 nominal size)
17978 nominal size)
18077 nominal size) = 0.257
1.36x1.26x0.15
20328 cum Lessof brick =
Number
21051 4.1x487x0.066
nuts and rubber= insertion
131.78
4764 18.30.2 etc.
nuts and rubber insertion
4800 18.30.2 etc.
nuts and rubber insertion
4826 18.30.3 etc.
nuts and rubber insertion
4861 18.30.3 etc.
nuts and rubber insertion
4899 18.30.4 etc.
nuts and rubber insertion
4924 18.30.4 etc.
nuts and rubber insertion
4962 18.30.5 etc.
nuts and rubber insertion
4997 18.30.5 etc.
nuts and rubber insertion
5024 18.30.6 etc.
nuts and rubber insertion
5059 18.30.6 etc.
nuts and rubber insertion
5096 18.30.7 etc.
nuts and rubber insertion
5121 18.30.7 etc.
nuts and rubber insertions
7529 etc.
nuts and rubber insertions
7552 etc.
nuts and rubber insertions
7585 etc.
9304 of 1 m pipes = 282.74 Kg
9457 of
on1pile.
m pipes
Above = 48.00 Kg
50 tonne
23272 capacity
on pile. Upto 50 tonne
23255 capacity
11884 on X
11923 on X
11950 on X
11988 on X
12027 on X
12066 on X
12110 on X
12140 on X
or plain gaskin @ 0.09 kg
15799 perplain
or jointgaskin @ 0.24 kg
15885 per
outerjoint
dia X 15 mm
13915 nominal
outer diadia threaded
X 15 mm
13932 nominal dia threaded
outer dia X 15 mm
13975 nominal
outer diadia threaded
X 15 mm
14034 nominal dia threaded
outer dia X 15 mm
14122 nominal
outer diadia threaded
X 15 mm
14228 nominal dia threaded
outer dia X 20 mm
13949 nominal
outer diadia threaded
X 20 mm
13992 nominal dia threaded
outer dia X 20 mm
14051 nominal
outer diadia threaded
X 20 mm
14139 nominal dia threaded
outer dia X 20 mm
14247 nominal
outer diadia threaded
X 25 mm
14017 nominal dia threaded
outer dia X 25 mm
14078 nominal
outer diadia threaded
X 25 mm
14156 nominal dia threaded
outer dia X 25 mm
14274 nominal
outer diadia threaded
X 32 mm
14095 nominal dia threaded
outer dia X 32 mm
14183 nominal
outer diadia threaded
X 32 mm
14291 nominal dia threaded
outer dia X 40 mm
14200 nominal
outer diadia
X 40threaded
mm
14308 nominal dia threaded
outer dia X 50 mm
14335 nominal dia threaded
1438 outer dia.
1474 outer dia.
1508 outer dia.
1533 outer dia.
1568 outer dia.
1603 outer dia.
1632 outer dia.
1669 outer dia.
1706 outer dia.
1733 outer dia.
1775 outer dia.
1812 outer dia.
1836 outer dia.
1872 outer dia.
1909 outer dia.
1935 outer
Outer dia.
periphery
20706 3.50x0.075 m = 0.263 sqm
Outer periphery
20786 3.73x0.15 m = 0.56 sqm
Outer periphery
20849 4.00x0.15
Outer m = 0.60 sqm
periphery
20932 4.50x0.15
outside slabm :=3.40x0.075
0.675 sqm
20616 m = 0.255 sqm
3587 18.25.2 Over 300 mm dia
3643 18.26.2 Over 300for
fixtures mm diashall be
tank
6937 paid
P.T.M.T. Bib cock with
7273 7859 nozzle extension nipple each
15mm
P.T.M.T. 1 154.5
10239 7864 15mm
P.T.M.T. extension nipple each 1 30
10265 7865 P.T.M.T.
20mm extension nipple each 1 54
10282 7866 25mm
P.T.M.T. Stop cock each 1 78
7339 7861 (concealed) 15mm each 1 133.5
5594 13.61.1 paint on new work.
5626 13.61.1 paint on new work.
5648 13.61.1 paint on new work.
5680 13.61.1 paint on new work.
5700 13.61.1 paint on new work.
5730 13.61.1 paint on new work.
anti-corrosive bitumastic
2314 paint
anti-corrosive bitumastic
2345 paint
of approved quality for
5586 18.38 new
paintwork :
of approved
5890 18.4 Painting
quality : of C.I. cover &
17523 9999 frame with
Painting coalcover
of C.I. tar & L.S. 6.76 2
17753 9999 frame with
Painting coalcover
of C.I. tar & L.S. 6.76 2
17912 9999 frame with coal tar L.S. 6.76 2
Painting of C.I. cover &
18003 9999 frame
Paintingwith coalcover
of C.I. tar & L.S. 6.76 2
18102 9999 frame
Paintingwith coalCover
of C.I. tar and L.S. 6.76 2
20791 9999 frame with coal tar and
Painting of C.I. Cover L.S. 7.15 2
20871 9999 frame
Paintingwith coalCover
of C.I. tar and L.S. 7.15 2
20944 9999 frame
Paintingwith
onecoal
coattarwith L.S. 7.15 2
5750 white paint
Painting oneon oldwith
coat work.
5778 white paint on old
Painting one coat withwork.
5797 white paint
Painting oneon oldwith
coat work.
5816 white paint
Painting oneon oldwith
coat work.
5845 white paint
Painting oneon oldwith
coat work.
5864 white paint on old
excluding priming coatwork.
5593 with whitepriming coat
excluding
5625 with whitepriming coat
excluding
5647 with whitepriming coat
excluding
5679 with whitepriming coat
excluding
5699 with whitepriming coat
excluding
5729 with white
Painting with anti-
5895 corrosivewith
Painting paintanti-
two coats.
6051 corrosive paint two coats.
15797 1881 parts Sand)
15842 1881 parts Sand)
15883 1881 parts Sand)
15918 1881 parts Sand)
21165 1881 parts Sand)
21203 1881 parts Sand)
15964 parts Sand)
16898 parts Sand)
17072 parts Sand)
17115 parts Sand)
17159 parts Sand)
17323 parts Sand)
17369 parts Sand)
21345 parts Sand)
21410 parts Sand)
21624 parts Sand)
21700 parts Sand)
5622 Perimeter = 0.0845 metre
5644 Perimeter = 0.1061 metre
5676 Perimeter = 0.1334 metre
5696 Perimeter = 0.1520 metre
5726 Perimeter
perimetre == 0.1894 metre
4x0.35 =1.40
21049 m
4387 1397 Pig lead kilogram 100 176
21816 pile
Pile Integrity testing
23303 76 equipment day 0.1 3000
23053 pile.
length below pile cap, to
22291 carry a
12175 pipe
12192 pipe
12218 pipe
12235 pipe
12264 pipe
12310 pipe
12327 pipe
12344 pipe
12370 pipe
12387 pipe
12414 pipe
12431 pipe
12448 pipe
12475 pipe
12492 pipe
12519 pipe
12536 pipe
12564 pipe
12579 pipe
13411 pipe
13428 pipe
15700 pipe
15728 pipe
15743 pipe
6286 pipe 10 metre long.
19657 12.39.1 pipe and special
19732 12.39.2 pipe and special
15695 Pipe
pipesBridge
including refilling of
11133 excavated earthrefilling of
pipes including
11174 excavated earthrefilling of
pipes including
11205 excavated earthrefilling of
pipes including
11245 excavated earthrefilling of
pipes including
11287 excavated earthrefilling of
pipes including
11318 excavated earthrefilling of
pipes including
11356 excavated earthrefilling of
pipes including
11398 excavated earthrefilling of
pipes including
11470 excavated earthrefilling of
pipes including
11511 excavated earthrefilling of
pipes including
11552 excavated earth
6922 9999 Placing at terrace L.S. 89.7 2
6944 9999 Placing
Plastic encapsuled M.S. L.S.
at terrace 89.7 2
19009 7354 foot rest
of pile 30x20x15
head or cm each 1 110
23095 construction of
of pile head or
23050 construction of
of pile head or
23141 construction
PN - 10 Pipe, of
110 mm OD
1061 18.6.9 (SDR-11)
PN - 10 Pipe, 160 mm OD
1090 18.6.10 (SDR-11)
PN - 10 Pipe, 50 mm OD
923 18.6.5 (SDR-11)
PN - 10 Pipe, 63 mm OD
961 18.6.6 (SDR-11)
PN - 10 Pipe, 75 mm OD
988 18.6.7 (SDR-11)
PN - 10 Pipe, 90 mm OD
1022 18.6.8 (SDR-11)
PN - 16 Pipe, 20mm OD
537 18.4.1 (SDR-7.4)
PN - 16 Pipe, 20mm OD
688 18.5.1 (SDR-7.4)
PN - 16 Pipe, 20mm OD
790 18.6.1 (SDR-7.4)
PN - 16 Pipe, 25 mm OD
818 18.6.2 (SDR-7.4)
PN - 16 Pipe, 25mm OD
560 18.4.2 (SDR-7.4)
PN - 16 Pipe, 25mm OD
716 18.5.2 (SDR-7.4)
PN - 16 Pipe, 32 mm OD
856 18.6.3 (SDR-7.4)
PN - 16 Pipe, 32mm OD
592 18.4.3 (SDR-7.4)
PN - 16 Pipe, 32mm OD
750 18.5.3 (SDR-7.4)
PN - 16 Pipe, 40 mm OD
895 18.6.4 (SDR-7.4)
PN - 16 Pipe, 40mm OD
616 18.4.4 (SDR-7.4)
PN - PN - 10 Pipe, 50mm
651 18.4.5 OD (SDR-11)
655 PN-10 (SDR 11) -
1029 PN-10 (SDR 11) -
1068 PN-10
PN-10 (SDR
(SDR 11)
11) -- 50 mm
930 Outer
PN-10 dia
(SDR 11) - 63 mm
968 Outer dia
PN-10 (SDR 11) - 75 mm
1001 Outer dia
596 PN-16 (SDR 7.4)
620 PN-16
PN-16 (SDR
(SDR 7.4)
7.4) -- 20 mm
541 Outer
PN-16 dia
(SDR 7.4) - 20 mm
695 Outer dia
PN-16 (SDR 7.4) - 20 mm
797 Outer dia
PN-16 (SDR 7.4) - 25 mm
720 Outer
PN-16 dia
(SDR 7.4) - 25 mm
825 Outer dia
PN-16 (SDR 7.4) - 25mm
564 Outer
PN-16 dia
(SDR 7.4) - 32 mm
754 Outer dia
PN-16 (SDR 7.4) - 32 mm
863 Outer
PN-16 dia
(SDR 7.4) - 40 mm
902 Outer dia
Poly propylene- Random -
694 8626 Co
Poly- Polymer (PPR)
propylene- pipes -
Random metre 10 43.27
796 8626 Co
Poly- Polymer (PPR)
propylene- pipes -
Random metre 10 43.27
719 8627 Co
Poly- Polymer (PPR)
propylene- pipes -
Random metre 10 66.8
595 8628 Co
Poly- Polymer (PPR)
propylene- pipes -
Random metre 10 107.47
753 8628 Poly
Co - Polymer (PPR)
propylene- pipes -
Random metre 10 107.47
862 8628 Co - Polymer (PPR)
Poly propylene- Randompipes - metre 10 107.47
619 8629 Co
Poly- Polymer (PPR)
propylene- pipes -
Random metre 10 161.07
901 8629 Co - Polymer (PPR) pipes metre 10 161.07
Poly propylene- Random -
654 8630 Co
Poly- Polymer (PPR)
propylene- pipes -
Random metre 10 252.22
929 8630 Co
Poly- Polymer (PPR)
propylene- pipes -
Random metre 10 252.22
967 8631 Co - Polymer (PPR) pipes -
Poly propylene- Random metre 10 281.73
1000 8632 Co
Poly- Polymer (PPR)
propylene- pipes -
Random metre 10 418.18
1028 8633 Co
Poly- Polymer (PPR)
propylene- pipes -
Random metre 10 597.63
1067 8634 Co
Co -- Polymer
Polymer (PPR)
(PPR) pipes
pipes metre 10 885.83
824 8627 metre
Poly propylene- Random - 10 66.8 668.00 P
540 8626 Co
Poly-Polymer (PPR)
propylene- pipes -
Random metre 10 43.27
563 8627 Co -Polymer
storage tank (PPR) pipes
with cover metre 10 66.8
6919 1649 and
storage tank with cover per litre 500 5.5
6941 1649 and
Portland Cement (OPC-43 per litre 500 5.5
15793 367 grade)
Portland Cement (OPC-43 tonne 0.019 4940
15870 367 grade)
Portland Cement (OPC-43 tonne 0.053 4940
15914 367 grade)
Portland Cement (OPC-43 tonne 0.094 4940
15960 367 grade)
Portland Cement (OPC-43 tonne 0.125 4940
16892 367 grade)
Portland Cement (OPC-43 tonne 0.006 4940
16926 367 grade)
Portland Cement (OPC-43 tonne 0.009 4940
16979 367 grade)
Portland Cement (OPC-43
17109 367 grade)
Portland Cement (OPC-43 tonne 0.026 4940
17143 367 grade)
Portland Cement (OPC-43 tonne 0.032 4940
17189 367 grade)
Portland Cement (OPC-43 tonne 0.037 4940
17232 367 grade)
Portland Cement (OPC-43 tonne 0.042 4940
17276 367 grade)
Portland Cement (OPC-43 tonne 0.049 4940
17317 367 grade)
Portland Cement (OPC-43 tonne 0.055 4940
17363 367 grade)
Portland Cement (OPC-43 tonne 0.061 4940
17407 367 grade)
Portland Cement (OPC-43 tonne 0.068 4940
21161 367 grade)
Portland Cement (OPC-43 tonne 0.0013 4940
21199 367 grade)
Portland Cement (OPC-43 tonne 0.0019 4940
21305 367 grade)
Portland Cement (OPC-43 tonne 0.025 4940
21341 367 grade)
Portland Cement (OPC-43 tonne 0.028 4940
21369 367 grade)
Portland Cement (OPC-43 tonne 0.034 4940
21406 367 grade)
Portland Cement (OPC-43 tonne 0.049 4940
21446 367 grade)
Portland Cement (OPC-43 tonne 0.012 4940
21490 367 grade)
Portland Cement (OPC-43
21531 367 grade)
Portland Cement (OPC-43
21620 367 grade)
Portland Cement (OPC-43 tonne 0.028 4940
15838 grade)
Portland Cement (OPC-43 tonne 0.036 4940
16848 grade)
Portland Cement (OPC-43 tonne 0.005 4940
17067 grade)
Portland Cement (OPC-43 tonne 0.024 4940
21238 grade)
Portland Cement (OPC-43 tonne 0.012 4940
21267 grade)
Portland Cement (OPC-43 tonne 0.016 4940
21658 grade)
Portland Cement (OPC-43 tonne 0.034 4940
21687 grade)
power unit etc. including tonne 0.049 4940
21781 complete
power unitaccessories and
etc. including
21819 complete accessories and
power unit etc. including
21859 complete
power unitaccessories and
etc. including
21890 complete
power unitaccessories and
etc. including
21929 complete accessories
power unit etc. including and
21967 complete
power unitaccessories and
etc. including
22005 complete
power unitaccessories and
etc. including
22043 complete
power unitaccessories and
etc. including
22311 complete accessories
power unit etc. including and
22350 complete
power unitaccessories and
etc. including
22387 complete
power unitaccessories and
etc. including
22419 complete
power unitaccessories and
etc. including
22458 complete accessories
power unit etc. including and
22504 complete
power unitaccessories and
etc. including
22547 complete
power unitaccessories and
etc. including
22588 complete
power unitaccessories and
etc. including
22628 complete accessories
power unit etc. including and
22670 complete
power unitaccessories and
etc. including
22698 complete
power unitaccessories and
etc. including
22731 complete
power unitaccessories and
etc. including
22766 complete accessories and
1385 8311 PPR Union 50mm each 1 483.6
1382 18.6A.6 PPR Union 50mm
1413 8312 PPR Union 75mm each 1 933
1410 18.6A.7 PPR Union 75mm
Precast R.C.C. grating with
20714 7380 frame
Precast R.C.C. grating with each 1 620
20717 7381 frame
Precast R.C.C. grating with each 1 235
20622 7381 Precast
frame 450x100 mm with each
R.C.C. grating 1 235
20547 7380 frame 500x450
cover with frame mm - H.D. - each 1 620
18538 20
10373 9999 proof
having foam flow
11842 18.84 technology.
the G.I. pipes in external
6066 18.41 work
as per: direction of
526 18.4 Engineer-in-Charge.
as per direction of
788 18.6 Engineer-in-Charge.
complete as per direction
686 18.5 of Engineer-in-Charge.
pressure, with plastic
2970 18.18 floats complete
bib cock of approved:
2732 18.15 quality :
cover including boring
3299 18.2 and tapping the main :
stop cock of approved
2778 quality :
18.16 insertions etc. complete
7723 18.61 conforming to IS
if required will be: paid
2373 :
7519 18.59 separately)
tail pieces if:required will
4750 18.31 be paid separately)
of approved quality :
7055 18.53 approved
conforming to IS:8931
quality
6967 18.49 conforming to IS:8931
(size 15mmx50mm) of
7081 18.53A approved
standards and weighing
7017 18.51 not less than 690 gms.
standards and weighing
6988 18.5 not
brassless than 810
shower rosegms.with 15
3453 18.22 or 20 mm inlet
make conforming to :
7036 18.52 IS:8931.
as per direction of
1765 18.9 Engineer
completeinasCharge.
per direction
1623 18.8 of Engineer in
Engineer in Charge.Charge.
1429 18.7 Internal
pieces if work - will be
required
7600 18.6 paid separately) :
the walls etc. Internal
2090 18.1 work
paint,-cutting chases and
2294 18.11 making good the wall :
fittings including
2379 18.12 trenching
same completeand refilling
whereveretc.
6701 18.47 required :
making long screws etc.
6502 18.46 complete (New work)
wheel of approved :
quality
2824 18.17 (screwed
approved end) :
quality
3046 (screwed
18.19 of required end) : and
shape
19197 19.19 approved quality
direction of the engineer
200 18.2 in
as charge.
per direction of the
343 18.3 engineer in charge.
as per direction of the
8 Engineerbore,
18.1 nominal in charge.
weighing
7941 18.63 not
withless
L.P./ H.P.H.D. plastic
7827 18.62 ball.
bib cock of approved
7098 18.54 quality
approved andquality
colour.and
10233 18.75 colour.
grating of approved
7444 18.58 quality andofcolour.
pillar cock approved
7352 18.56 quality and colour.
arrangements, weighing
7988 18.65 not
stopless
cockthan 106 gms.
of approved
7286 18.55 nominal
quality and colour.
bore, weighing
7971 18.64 not
approved qualitygms
less than 40 and
7398 18.57 colour.
polyethylene water
6934 18.48A storage
Fitting ofloft tankfit design
press
15581 18.101 Fitting
of gradeof press fit design
15691 18.102 of grade
Fitting of press fit design
12865 18.91 of gradeof Engineer-in-
dirction
12292 18.88 charge.
direction of Engineer-in-
15210 18.1 charge.
direction of Engineer-in-
12617 18.89 charge.
direction of Engineer-in-
12748 18.9 charge.
direction of Engineer-in-
13001 18.92 charge.
direction of Engineer-in-
13121 18.93 charge.
direction of Engineer-in-
13451 18.94 charge.
direction of Engineer-in-
13895 18.95 charge.
direction of Engineer-in-
14347 18.96 charge.
direction of Engineer-in-
14619 18.97 charge.
direction of Engineer-in-
14861 18.98 charge.
direction of Engineer-in-
15015 18.99 charge.
direction of Engineer-in-
12168 20.7.1 charge.
sand) including testing of
21153 19.34 joints
not lessetc. complete
than 2.70 kg: as
16320 19.4 per standard
payment) design:
Inernal work -
11871 18.85 Exposed on wall
payment) Internal work -
12084 18.86 Concealed Pipe and
including cleaning
6445 18.44 priming
mm nominal the tubeborewell.
with
10183 18.74 30cm length
connection pipe with
3361 18.21 brass unions
including bed: concrete as
15993 19.2 per standard
concrete as per design :
standard
16087 19.3 design
suitable: for mechanical
8164 18.69 jointing
suitable asforper IS : 9523 :
push-on
8116 18.68 jointing as per
Centrifugally (Spun) Cast
8612 18.71 Iron, Class
of Class K -B9 (IS : 1536) :
conforming
9830 18.73 to IS : 8329
flanged :
jointing as per IS :
3620 1538 :including testing of
18.26 sand)
21221 19.35 joints etc.testing
including complete of joints
21438 19.36 etc.
including testing of joints
16826 19.6 etc. complete
suitable :
for flanged
8014 jointingcaps
18.66 tapers, as per IS (Heavy
etc. : 1538 :
3554 18.25 class):
suitable for mechanical
8065 19.21.3 jointing as per
Ductile Iron IS : 13382 :
Pipes
8929 18.72 conforming to IS LA)
iron pipes (Class : 8329 :
3673 18.27 brass
conforming
strainer toof IS approved
- 1536 :
6423 18.43 quality.
complete with all
6481 18.45 accessories.
but without fittings and
6914 18.48 the base support
Providing flanged for tank.
joints to
7621 double acting
Providing flangedair valves
joints to
7644 double
Providing acting
flangedair valves
joints to
7677 double acting air valves
Providing flanged joints to
7700 double
Providing acting
flangedair valves
joints to
7732 double acting
Providing flangedair valves
joints to
7753 double acting air valves
Providing flanged joints to
7783 double
Providing acting
flangedair valves
joints to
7804 double acting
pipes and specials, air valves
4400 18.3 including
Providing testing
flangedofjointsjointsto:
4763 sluice valves
Providing with bolts,
flanged joints to
4799 sluice valves with bolts,
Providing flanged joints to
4825 sluice valves
Providing with bolts,
flanged joints to
4860 sluice valves
Providing flanged with bolts,
joints to
4898 sluice valves with bolts,
Providing flanged joints to
4923 sluice valves
Providing with bolts,
flanged joints to
4961 sluice valves with bolts,
Providing flanged joints to
4996 sluice valves
Providing with bolts,
flanged joints to
5023 sluice valves with bolts,
Providing flanged joints to
5058 sluice valves
Providing with bolts,
flanged joints to
5095 sluice valves with bolts,
Providing flanged joints to
5120 sluice valves
Providing with
joint bolts,
to S.W.
19659 9999 pipe with cement
Providing joint to S.W. L.S. 26.91 2
19734 9999 pipe with cement
joints to 100 mm L.S. 39.91 2
19656 diameter
joints to 150 mm
19731 diameter
but excluding the cost of
4021 18.28 pig lead :size) as per
nominal
18916 19.15 standard
aggregatedesign
20 mm: nominal
19002 19.16 size)
testing of joints and the
8202 18.7 cost of rubber
complete as per gasket :
standard
19605 19.22 design
shoe toand thespecifications
bottom of pile:
21767 20.2 cap) :
shoe to the bottom of pile
22786 20.5 cap).
including testing of joints
15780 19.1 etc.
PTMT complete
Angle Stop : cock
7948 with Flenge
7500 PTMT 15mm
Ball Cock 15mm each 1 100
7833 7495 Complete with
PTMT Ball Cock 20mm each 1 100
7851 7496 Complete
PTMT Ball withCock 25mm dach 1 135
7880 7497 Complete
PTMT Ball withCock 40mm each 1 290
7898 Complete
7498 PTMT Ball with
Cock 50mm each 1 480
7927 7499 Complete with each 1 870
7450 7409 PTMT grating 100 mm dia. each 1 20
7368 7406 PTMT pillar cock each 1 125
7354 18.56.1 PTMT
PTMT pillar
pillar cock
cock (fancy)
7385 7410 15 mm foam
PTMT push cock flow.12 mm each 1 138
7431 7408 dia.
PTMT 20push
mm cock
BSP 15 mm each 1 57
7405 7407 dia.
PTMT Soap Dish/Holder each 1 62
7992 7509 PTMT Swiveling shower each
138x102x75mm 1 84
7975 7501 15mm
PVC connection pipe with each 1 70
10220 P.T.M.T. Nuts
20195 Qty for 2.45m depth
20210 Qty for 4.25m depth
20219 Qty in arch
20272 Qty
qty. in
of arch
concrete reqd. =
16010 4.1.10 1.48 cum
qty. of concrete reqd. =
16061 2.11 cum
17003 Unit Quantity Rate Amount
17620 Unit Quantity Rate Amount
17844 Unit Quantity Rate Amount
21540 Unit Quantity
10x0.30x0.247 = 0.744 Rate Amount
6077 cum.
Quantity of sand =
6122 10x0.30x0.252
Quantity of sand ==
6152 10x0.30x0.259
Quantity of sand ==
6172 10x0.30x0.268
Quantity of sand ==
6204 10x0.30x0.274
Quantity of sand ==
6224 10x0.30x0.286
Quantity of sand ==
6254 10x0.45x0.302 =
Quantity of sand =
6273 10x0.45x0.315
10x0.45x0.34 ==1.53 cum.
6293 + Less
16252 R = 145 mm
16108 R = 62 mm
22494 R.C.C
22537 R.C.C
22578 R.C.C
22618 R.C.C
cement : 1.5coarse sand :
20380 3
R.C.C slab of 1:1.5:3(1
20429 cement
R.C.C slab: 1.5 coarse(1sand :
of 1:2:4
19909 cement
R.C.C slab of 1:2:4 sand
: 2 coarse (1 : 4
19964 cement
R.C.C slab: 2ofcoarse
1:2:4 sand
(1 : 4
20030 cement
cement :: 2 coarse
1.5 coarse sand
sand: 4:
20390 3
cement :1.5 coarse sand :
20439 3
R.C.C. 1:1.5:3 (1 cement :
20681 1.5 coarse
R.C.C. sand
collars NP2 : 3class
16844 100 mm
R.C.C. dia 5NP2
collars Nos.class each 5 30
17313 1000 mm
R.C.C. dia NP2
collars 4 Nos.class each 4 280
17358 1100 mm dia 4 Nos.
R.C.C. collars NP2 class each 4 300
17402 1200
R.C.C.mm dia NP2
collars 4 Nos.class each 4 350
16878 150 mm
R.C.C. dia 5NP2
collars Nos.class each 5 35
16921 1716 R.C.C.
250 mm dia 5NP2
collars Nos.class each 5 50
16975 300 mm dia 4 Nos.
R.C.C. collars NP2 class
17062 450 mm
R.C.C. dia 4NP2
collars Nos.class each 4 100
17096 500 mm
R.C.C. dia 4NP2
collars Nos.class each 4 115
17138 1720 R.C.C.
600 mm dia 4NP2
collars Nos.class each 4 140
17183 700 mm dia 4 Nos.
R.C.C. collars NP2 class each 4 150
17226 800 mm
R.C.C. dia 4NP2
collars Nos.class each 4 200
17271 900 mm
R.C.C. dia 4 Nos.
manhole cover with each 4 235
18862 9977 R.C.C.
frame manhole
- H.D. - 20cover with
19214 frame - L.D. - 25cover with
R.C.C. manhole
19316 frame - M.D. - 10
21530 2331 R.C.C.
R.C.C. pipes
pipes 900
NP2 mmclassdia
100
16842 mm dia (in 2 m. length
1700 R.C.C. pipes NP2 class metre 10 200
17311 1711 1000 mm dia (in
R.C.C. pipes NP2 class2.5 m. metre 10 2900
17356 1712 1100
R.C.C.mmpipesdiaNP2
(in 2.5
classm. metre 10 3200
17400 1713 1200
R.C.C.mmpipesdiaNP2
(in 2.5
classm.150 metre 10 3510
16876 mm dia (in 2 m. length
1701 R.C.C. pipes NP2 class 250 metre 10 212
16920 1702 mm diapipes
R.C.C. (in 2NP2
m. length = metre
class 300 10 350
16973 1703 mm diapipes
R.C.C. (in 2.5
NP2 m.class 450
17060 1704 mm diapipes
R.C.C. (in 2.5
NP2 m.class 500 metre 10 750
17094 1705 R.C.C.
mm diapipes
(in 2.5
NP2 m.class 600 metre 10 925
17137 1706 mm
R.C.C. pipes NP2 class 700 metre
dia 10 1100
17181 1707 mm diapipes
R.C.C. (in 2.5
NP2 m.class 800 metre 10 1485
17224 1709 mm dia (in 2.5 m. metre 10 1800
R.C.C. pipes NP2 class 900
17269 1710 mm dia (in 2.5
R.C.C.slabs 7.5 m.
cm thick in metre 10 2500
21072 cement
(Raising concrete 1:1.5:3
depth of manhole
20320 19.26 to
Rate as per item no :
be paid separately)
5592 13.50.3 13.50.3 of SH
Rate as per : Finishing
item no sqm 0.673 33.3
5624 13.50.3 13.50.3 of SH
Rate as per : Finishing
item no sqm 0.845 33.3
5646 13.50.3 13.50.3 of SH
Rate as per : Finishing
item no sqm 1.061 33.3
5678 13.50.3 13.50.3 of SH :
Rate as per item noFinishing sqm 1.334 33.3
5698 13.50.3 13.50.3 of SH
Rate as per : Finishing
item no sqm 1.52 33.3
5728 13.50.3 13.50.3 of SH
Rate as per : Finishing
item no sqm 1.894 33.3
5595 13.61.1 of SH
Rate as per : Finishing
item no sqm 0.673 82.4
5627 13.61.1 of SH :
Rate as per item noFinishing sqm 0.845 82.4
5649 13.61.1 of SH
Rate as per : Finishing
item no sqm 1.061 82.4
5681 13.61.1 of SH
Rate as per : Finishing
item no sqm 1.334 82.4
5701 13.61.1
Rate of SH
as per : Finishing
item no sqm 1.52 82.4
5731 13.61.1 of SH : Finishing
Rate as per item no 13.9.1 sqm 1.894 82.4
5171 13.9.1 of SHas
Rate : Finishing
per item no 13.9.1 sqm 0.7 235.5
5245 13.9.1 of SHas
Rate : Finishing
per item no 13.9.1 sqm 2.16 235.5
5542 13.9.1 of SHas
Rate : Finishing
per item no 13.9.1 sqm 1.32 235.5
16355 13.9.1 of SH : Finishing
Rate as per item no 13.9.1 sqm 0.29 235.5
16406 13.9.1 of SHas
Rate : Finishing
per item no 13.9.1 sqm 0.29 235.5
16465 13.9.1 of SHas
Rate : Finishing
per item no 13.9.1 sqm 0.3 235.5
16519 13.9.1 of SHas
Rate : Finishing
per item no 13.9.1 sqm 0.3 235.5
16576 13.9.1 of
Rate as per item no 13.9.1 sqm
SH : Finishing 0.16 235.5
16630 13.9.1 of SHas
Rate : Finishing
per item no 13.9.1 sqm 0.16 235.5
17729 13.9.1 of SHas
Rate : Finishing
per item no 13.9.1 sqm 2.19 235.5
17975 13.9.1 of SHas
Rate per item no 13.9.1 sqm
: Finishing 2.41 235.5
18074 13.9.1 Rate as per item no 13.9.1 sqm
of SH : Finishing 2.41 235.5
18206 13.9.1 of SHas
Rate per item no 13.9.1 sqm
: Finishing 4.2 235.5
18292 13.9.1 of SHas
Rate per item no 13.9.1 sqm
: Finishing 1.75 235.5
18380 13.9.1 of SHas
Rate per item no 13.9.1 sqm
: Finishing 1.75 235.5
18426 13.9.1 Rate as per item no 13.9.1 sqm
of SH : Finishing 2.33 235.5
18532 13.9.1 of SHas
Rate per item no 13.9.1 sqm
: Finishing 4.48 235.5
18633 13.9.1 of SHas
Rate : Finishing
per item no 13.9.1 sqm 4.48 235.5
18676 13.9.1 of SH : Finishing
Rate as per item no 13.9.1 sqm 2.56 235.5
18688 13.9.1 of SHas
Rate : Finishing
per item no 13.9.1 sqm 2.56 235.5
18762 13.9.1 of SHas
Rate : Finishing
per item no 13.9.1 sqm 7.61 235.5
18856 13.9.1 of SHas
Rate : Finishing
per item no 13.9.1 sqm 7.61 235.5
18896 13.9.1 of SH : Finishing
Rate as per item no 13.9.1 sqm 8.99 235.5
18911 13.9.1 of SHas
Rate : Finishing
per item no 13.9.1 sqm 8.99 235.5
19541 13.9.1 of SHas
Rate : Finishing
per item no 13.9.1 sqm 0.32 235.5
19575 13.9.1 of SHas
Rate : Finishing
per item no 13.9.1 sqm 0.6 235.5
19655 13.9.1 of SHas
Rate : Finishing
per item no 13.9.1 sqm 0.06 235.5
19730 13.9.1 of
Rate as per item no 13.9.1 sqm
SH : Finishing 0.06 235.5
20539 13.9.1 of SHas
Rate : Finishing
per item no 13.9.1 sqm 1.08 235.5
20601 13.9.1 of SH : Finishing sqm 1.55 235.5
Rate as per item no 13.9.1
20676 13.9.1 of SHas
Rate : Finishing
per item no 13.9.1 sqm 2.36 235.5
20779 13.9.1 of SHas
Rate : Finishing
per item no 13.9.1 sqm 0.9 235.5
18142 of
Rate as per item no 13.9.1 sqm
SH : Finishing 3.4 235.5
18159 of SHas
Rate per item no 13.9.1 sqm
: Finishing 3.4 235.5
18188 of SHas
Rate per item no 13.9.1 sqm
: Finishing 4.2 235.5
18451 of SHas
Rate per item no 13.9.1 sqm
: Finishing 2.33 235.5
19494 Rate as per item no 13.9.1 sqm
of SH : Finishing 0.25 235.5
20984 of SHas
Rate per item no 13.9.1 sqm
: Finishing 2.13 235.5
21003 of SHas
Rate per item no 13.9.1 sqm
: Finishing 2.4 235.5
21032 of SHas
Rate per item no 13.9.1 sqm
: Finishing 2.9 235.5
5317 13.9.1 of
Rate as per item (v)
SH : Finishing 13.9.1 sqm
no C.I. 4.41 235.5
5389 13.9.1 of SHas
Rate : Finishing
per item (v)
no C.I.
13.9.1 sqm 6.42 235.5
5470 of SHas
Rate : Finishing
per item (v)
no C.I.
13.9.1 sqm 2.16 235.5
20838 13.9.1 of SHas
Rate : Finishing
per item R.C.C
no 13.9.1 sqm 1.05 235.5
20918 13.9.1 of SH : Finishing R.C.C
3 graded stone aggregate sqm 1.34 235.5
17577 13.9.1 20 mm 1:1.5:3 (1
concrete
17487 13.9.1 cement : 1.5item no 15.2.1
Rate as per
20102 15.2.1 of as per item no 15.2.1 cum
Rate 0.35 1004.45
20246 15.2.1 of
Rate as per item no 15.2.1 cum 0.2 1004.45
20291 15.2.1 of
Rate as per item no 15.2.1 cum 0.35 1004.45
20061 15.2.1 of SHas
Rate : Dismantling
per item no 15.3 cum 1.18 1004.45
19915 15.3 Rate
of as per item no 15.3 cum 0.22 1465.35
19970 15.3 of
Rate as per item no 15.3 cum 0.31 1465.35
20036 15.3 of
Rate as per item no 15.3 cum 0.19 1465.35
20436 15.3 of
Rate as per item no 15.7.4 cum 0.24 1465.35
20275 15.7.4 of SH : Dismantling
18.83.2 of SH: Water and cum 1.97 847.95
19617 18.83.2 supply
18.83.4 of SH Water each cut 3 92.6
19703 18.83.4 Rate as per item no 4.1.10 each cut
Supply 3 174.2
16219 4.1.10 of SHas
Rate per item no 4.1.10 cum
: Concrete 1.34 4685.75
16270 4.1.10 of SHas
Rate per item no 4.1.10 cum
: Concrete 1.56 4685.75
16032 4.1.10 of no 4.1.10 cum
Rate as per item Work
SH : Concrete 1.81 4685.75
16062 4.1.10 of SHas
Rate : Concrete no 4.1.10 cum
per item Work 2.11 4685.75
16178 4.1.10 of SHas
Rate : Concrete
per item Work
no 4.1.10 cum 1.14 4685.75
16011 of SH : Concrete Work
Rate as per item no 4.1.10 cum 1.48 4685.75 4685.75
16082 of SHas
Rate : Concrete
per item Work
no 4.1.10 cum 2.44 11433.22
16123 of SHas
Rate : Concrete
per item Work
no 4.1.10 cum 0.7034 4685.75
16315 of SHas
Rate : Concrete
per item Work
no 4.1.11 cum 1.8 4685.75
19834 4.1.11 of
Rate as per item no 4.1.11 cum 0.2 4390.6
19726 4.1.11 of SHas
Rate : Concrete
per item no 4.1.11 cum 0.28 4390.6
5160 4.1.11 of SHas
Rate : Concrete
per item work
no 4.1.11 cum 0.04 4390.6
5225 4.1.11 of SHas
Rate : Concrete
per item Work
no 4.1.11 cum 0.15 4390.6
5308 4.1.11 of SHas
Rate : Concrete
per item Work
no 4.1.11 cum 0.23 4390.6
5379 4.1.11 of
Rate as per item no 4.1.11 cum
SH : Concrete Work 0.33 4390.6
5460 4.1.11 of SHas
Rate : Concrete
per item Work
no 4.1.11 cum 0.15 4390.6
5532 4.1.11 of SH : Concrete Work cum 0.13 4390.6
Rate as per item no 4.1.11
16342 4.1.11 of SHas
Rate : Concrete
per item Work
no 4.1.11 cum 0.09 4390.6
16393 4.1.11 of SHas
Rate : Concrete
per item Work
no 4.1.11 cum 0.09 4390.6
16506 4.1.11 of
Rate as per item no 4.1.11 cum
SH : Concrete Work 0.08 4390.6
16563 4.1.11 of SHas
Rate : Concrete no 4.1.11 cum
per item Work 0.08 4390.6
16618 4.1.11 of SHas
Rate : Concrete no 4.1.11 cum
per item Work 0.08 4390.6
19650 4.1.11 of SHas
Rate : Concrete no 4.1.11 cum
per item Work 0.21 4390.6
19788 4.1.11 Rate as per item no 4.1.11 cum
of SH : Concrete Work 0.16 4390.6
20519 4.1.11 of SHas
Rate : Concrete no 4.1.11 cum
per item Work 0.18 4390.6
20658 4.1.11 of SHas
Rate : Concrete no 4.1.11 cum
per item Work 0.29 4390.6
20764 4.1.11 of SHas
Rate : Concrete no 4.1.11 cum
per item Work 0.2 4390.6
20824 4.1.11 Rate as per item no 4.1.11 cum
of SH : Concrete Work 0.22 4390.6
20894 4.1.11 of SHas
Rate : Concrete
per item Work
no 4.1.11 cum 0.26 4390.6
16452 of
clasSHdesignation
: Concrete 75
Work
in cum 0.08 4390.6
20573 4.1.11 cement
Rate as per item no 4.1.3
18423 of SHas
Rate : Concrete
per item Work
no 4.1.3 cum 0.01 5954.35
18447 of SHas
Rate : Concrete
per item Work
no 4.1.6 cum 0.01 5954.35
18234 4.1.6 of SHas
Rate : Concrete
per item Work
no 4.1.6 cum 0.63 5291.95
18333 4.1.6 of SHas
Rate : Concrete
per item Work
no 4.1.6 cum 0.63 5291.95
18473 4.1.6 of SH : Concrete Work
Rate as per item no 4.1.6 cum 1.18 5291.95
18576 4.1.6 of SHas
Rate : Concrete
per item Work
no 4.1.6 cum 1.18 5291.95
18709 4.1.6 of SHas
Rate : Concrete
per item Work
no 4.1.6 cum 2.25 5291.95
18799 4.1.6 of SHas
Rate : Concrete
per item Work
no 4.1.8 cum 2.25 5291.95
17541 4.1.8 of
Rate as per item no 4.1.8 cum
SH : Concrete Work 0.43 4955.2
17695 4.1.8 of SHas
Rate : Concrete
per item Work
no 4.1.8 cum 0.55 4955.2
17785 4.1.8 of SHas
Rate : Concrete
per item Work
no 4.1.8
17936 4.1.8 of SHas
Rate : Concrete no 4.1.8 cum
per item Work 0.55 4955.2
18035 4.1.8 2130.74 A Brick work with cum
of SH : Concrete Work 0.55 4955.2
17465 4.1.8 bricks
Rate asofper
class designation
item no 4.2.3
18753 4.2.3 Rate as per item no 4.2.3 cum
of SH : Concrete 0.09 7107.1
18847 4.2.3 of SHas
Rate per item no 4.2.3 cum
: Concrete 0.09 7107.1
20495 4.2.3 Rate as per item no 4.2.3 cum
of SH : Concrete 0.02 7107.1
20543 4.2.3 of SHas
Rate per item no 4.2.3 cum
: Concrete 0.1 7107.1
18625 4.2.3 of SHas
Rate : Concrete
per item 12
no mm
4.2.3 cum 0.09 7107.1
20605 4.2.3 of SH : Concrete R.C.C.
Rate as per item no 4.2.3 cum 0.001 7107.1
16350 4.2.3 of SHas
Rate : Concrete
per item Work
no 4.2.3 cum 0.008 7107.1
16460 4.2.3 of SHas
Rate : Concrete
per item Work
no 4.2.3 cum 0.008 7107.1
16514 4.2.3 of SHas
Rate : Concrete
per item Work
no 4.2.3 cum 0.008 7107.1
16571 4.2.3 of SH : Concrete Work
Rate as per item no 4.2.3 cum 0.008 7107.1
16626 4.2.3 of SHas
Rate : Concrete
per item Work
no 4.2.3 cum 0.008 7107.1
18283 4.2.3 of SHas
Rate : Concrete
per item Work
no 4.2.3 cum 0.09 7107.1
18371 4.2.3 of SHas
Rate : Concrete
per item Work
no 4.2.3 cum 0.09 7107.1
18524 4.2.3 of SHas
Rate : Concrete
per item Work
no 4.2.3 cum 0.09 7107.1
20680 4.2.3 of
Rate as per item no 4.2.3 cum
SH : Concrete Work 0.07 7107.1
16402 of SHas
Rate : Concrete
per item Work
no 4.2.5
10411 4.2.5 of SH : Concrete work cum 0.04 6577.55
Rate as per item no 4.2.5
10432 4.2.5 of SHas
Rate : Concrete
per item work
no 4.2.5 cum 0.22 6577.55
18933 4.2.5 of SHas
Rate : Concrete
per item work
no 4.2.5 cum 0.004 6577.55
18975 4.2.5 of
Rate as per item no 4.2.5 cum
SH : Concrete work 0.004 6577.55
19013 4.2.5 of SHas
Rate : Concrete no 4.2.5 cum
per item work 0.009 6577.55
19056 4.2.5 of SHas
Rate : Concrete no 4.2.5 cum
per item work 0.004 6577.55
19099 4.2.5 of SHas
Rate : Concrete no 5.12 cum
per item work 0.004 6577.55
21076 5.12 of
Rate as per item no 5.19 cum
SH : RCC 0.02 7497.75
22806 5.19 of SHas
Rate per item no 5.3 of cum
: RCC 2.51 10438.4
20784 5.3 (SH
Rate: as
RCC ) item no 5.3 of cum
per 0.11 7835.75
20396 5.3 SH
Rate: RCC item no 5.3 of cum
Work
as per 0.26 7835.75
20445 5.3 SH
Rate as per item no 5.3 of cum
: RCC Work 0.24 7835.75
17505 5.3 SH
Rate: RCC Work
as per Less
item no 5.3 of cum 0.22 7835.75
17737 5.3 SH
Rate: RCC Work
as per Less
item no 5.3 of cum 0.31 7835.75
17986 SH : RCC
5.3 Rate Work
as per Less
item no 5.3 of cum 0.33 7835.75
18085 5.3 SH : RCC Work Less
materilas upto floor five cum 0.33 7835.75
17585 5.3 level
materilas upto floor five
17817 5.3 level
Rate as per item no 5.33.1
21774 5.33.1 of SHas
Rate : RCC
per Work
item no 5.33.1 cum 2.51 6934.9
21812 5.33.1 of SH : RCC Work
Rate as per item no 5.33.1 cum 3.18 6934.9
21843 5.33.1 of SHas
Rate : RCC
per Work
item no 5.33.1 cum 3.925 6934.9
21883 5.33.1 of SHas
Rate : RCC
per Work
item no 5.33.1 cum 4.75 6934.9
21922 5.33.1 of SHas
Rate : RCC
per Work
item no 5.33.1 cum 6.62 6934.9
21960 5.33.1 of
Rate as per item no 5.33.1 cum
SH : RCC Work 7.85 6934.9
21998 5.33.1 of SHas
Rate : RCC
per Work
item no 5.33.1 cum 10.17 6934.9
22029 5.33.1 of SHas
Rate : RCC
per Work
item no 5.33.1 cum 15.9 6934.9
22074 5.33.1 of SHas
Rate : RCC item no 5.33.1 cum
per Work 3.18 6934.9
22113 5.33.1 Rate as per item no 5.33.1 cum
of SH : RCC Work 3.925 6934.9
22154 5.33.1 of SHas
Rate : RCC item no 5.33.1 cum
per Work 5.65 6934.9
22194 5.33.1 of SHas
Rate : RCC item no 5.33.1 cum
per Work 6.62 6934.9
22306 5.33.1 of SHas
Rate : RCC item no 5.33.1 cum
per Work 5.65 6934.9
22345 5.33.1 Rate as per item no 5.33.1 cum
of SH : RCC Work 6.62 6934.9
22375 5.33.1 of SHas
Rate : RCC item no 5.33.1 cum
per Work 7.85 6934.9
22414 5.33.1 of SHas
Rate : RCC
per Work
item no 5.33.1 cum 10.17 6934.9
22453 5.33.1 of SH : RCC Work
Rate as per item no 5.33.1 cum 15.9 6934.9
22499 5.33.1 of SHas
Rate : RCC
per Work
item no 5.33.1 cum 0.778 6934.9
22542 5.33.1 of SHas
Rate : RCC
per Work
item no 5.33.1 cum 1.478 6934.9
22583 5.33.1 of SHas
Rate : RCC
per Work
item no 5.33.1 cum 1.906 6934.9
22623 5.33.1 of SH : RCC Work
Rate as per item no 5.33.1 cum 2.4 6934.9
22666 5.33.1 of SHas
Rate : RCC
per Work
item no 5.33.1 cum 0.033 6934.9
22694 5.33.1 of SHas
Rate : RCC
per Work
item no 5.33.1 cum 0.063 6934.9
22727 5.33.1 of SHas
Rate : RCC
per Work
item no 5.33.1 cum 0.081 6934.9
22762 5.33.1 of SHas
Rate : RCC
per Work
item no 5.33.1 cum 0.102 6934.9
22796 5.33.1 of
Rate as per item no 5.33.1 cum
SH : RCC Work 2.51 6934.9
22840 5.33.1 of SHas
Rate : RCC
per Work
item no 5.33.1 cum 3.18 6934.9
22882 5.33.1 of SH : RCC Work cum 3.925 6934.9
Rate as per item no 5.33.1
22923 5.33.1 of SHas
Rate : RCC
per Work
item no 5.33.1 cum 4.75 6934.9
22963 5.33.1 of SHas
Rate : RCC
per Work
item no 5.33.1 cum 10.88 6934.9
23005 5.33.1 of
Rate as per item no 5.9.2 cum
SH : RCC Work 15.7 6934.9
19663 5.9.2 of SHas
Rate per item no 5.9.2 sqm
: RCC 1.36 411.15
19747 5.9.2 of SHas
Rate per item no 5.9.2 sqm
: RCC 1.67 411.15
19799 5.9.2 of SHas
Rate per item no 5.9.2 sqm
: RCC 1.3 411.15
19838 5.9.2 Rate as per item no 5.9.2 sqm
of SH : RCC 1.45 411.15
20546 5.9.2 of SHas
Rate per item no 5.9.2 sqm
: RCC 0.53 411.15
20618 5.9.2 of SHas
Rate per item no 5.9.2 sqm
: RCC 0.55 411.15
20709 5.9.2 of SHas
Rate per item no 5.9.2 sqm
: RCC 0.91 411.15
20787 5.9.2 Rate as per item no 5.9.2 sqm
of SH : RCC 0.56 411.15
20861 5.9.2 of SHas
Rate : RCC
per item no 5.9.2 sqm 0.67 411.15
20936 5.9.2 of SHas
Rate : RCC
per item no 5.9.3 sqm 0.91 411.15
20349 of
Rate as per item no 5.9.3 sqm 0.45
17514 5.9.3 of SHas
Rate : RCC
per Work
item no 5.9.3 sqm 0.44 468.3
17599 5.9.3 of SHas
Rate : RCC
per Work
item no 5.9.3
17746 5.9.3 of SH : RCC Work
Rate as per item no 5.9.3 sqm 0.88 468.3
17833 5.9.3 of SHas
Rate : RCC
per Work
item no 5.9.3
17996 5.9.3 of SH : RCC Work
Rate as per item no 5.9.3 sqm 0.83 468.3
18095 5.9.3 of SHas
Rate : RCC
per Work
item no 5.9.3 sqm 0.83 468.3
20400 5.9.3 of SHas
Rate : RCC
per work
item no 5.9.3 sqm 0.88 468.3
20449 5.9.3 of SHas
Rate : RCC
per work
item no 6.1.1 sqm 0.83 468.3
5165 6.1.1 of SH : Brick Workno 6.1.1 cum
Rate as per item 0.1 5528.25
5384 6.1.1 of SHas
Rate : Brick Workno 6.1.1 cum
per item 1.32 5528.25
16346 6.1.1 of SHas
Rate : Brick Workno 6.1.1 cum
per item 0.13 5528.25
16456 6.1.1 of SHas
Rate : Brick Workno 6.1.1 cum
per item 0.13 5528.25
16567 6.1.1 of SH : Brick Workno 6.1.1 cum
Rate as per item 0.13 5528.25
17703 6.1.1 of SHas
Rate : Brick Workno 6.1.1 cum
per item 0.93 5528.25
18247 6.1.1 of SHas
Rate : Brick Workno 6.1.1 cum
per item 0.53 5528.25
18420 6.1.1 of SHas
Rate : Brick Workno 6.1.1 cum
per item 0.63 5528.25
18498 6.1.1 of SH : Brick Workno 6.1.1 cum
Rate as per item 1.29 5528.25
18673 6.1.1 of SHas
Rate : Brick Workno 6.1.1 cum
per item 0.66 5528.25
18731 6.1.1 of SHas
Rate : Brick Workno 6.1.1 cum
per item 3.68 5528.25
19638 6.1.1 of SH : Brick Workno 6.1.1 cum
Rate as per item 0.007 5528.25
19713 6.1.1 of SHas
Rate : Brick Workno 6.1.1 cum
per item 0.005 5528.25
20523 6.1.1 of SHas
Rate : Brick Workno 6.1.1 cum
per item 0.29 5528.25
20589 6.1.1 of SHas
Rate : Brick Workno 6.1.1 cum
per item 0.43 5528.25
20771 6.1.1 of SH : Brick Workno 6.1.1 cum
Rate as per item 0.21 5528.25
20830 6.1.1 of SHas
Rate : Brick Workno 6.1.1 cum
per item 0.22 5528.25
20980 6.1.1 of SHas
Rate : Brick Workno 6.1.1 cum
per item 0.7 5528.25
20999 6.1.1 of SHas
Rate : Brick Workno 6.1.1 cum
per item 0.76 5528.25
21018 6.1.1 of SHas
Rate : Brick Workno 6.1.1 cum
per item 0.88 5528.25
20667 of SH : Brick Workno 6.1.1 cum
Rate as per item 0.54 5528.25
20900 of SHas
Rate : Brick Workno 6.1.1 cum
per item 0.26 5528.25
5230 6.1.1 of SH : Brick Work (iv) cum 0.57 5528.25
Rate as per item no 6.1.1
5312 6.1.1 of SHas
Rate : Brick Workno(iv)
per item 6.1.1 cum 1.04 5528.25
5465 6.1.1 of SH : Brick Work (iv)
Rate as per item no 6.1.1 cum 0.57 5528.25
5537 6.1.1 of SH : Brick
Cement Work1:2:4
concrete (iv) (1 cum 0.35 5528.25
17472 6.1.1 cement
Cement :concrete
2 coarse 1:2:4
sand (1
:
17947 6.1.1 cement
mm cement : 2 coarse
plastersand
1:3 :(1
18885 6.1.1 cement:
Rate as per 3 coarse
item No
16398 6.36.1 6.36.1 of
Rate as per SHitem
: Brick
NoWork cum 0.13 5715.2
16510 6.36.1 6.36.1
Rate asofper SHitem
: Brick
NoWork cum 0.13 5715.2
16622 6.36.1 6.36.1
Rate asofper SHitem
: Brick
NoWork cum 0.13 5715.2
17559 6.36.1 6.36.1
Rate asofper SHitem
: Brick
NoWork
18045 6.36.1 6.36.1
Rate as per item NoWork
of SH : Brick cum 0.8 5715.2
18155 6.36.1 6.36.1
Rate asofper SHitem
: Brick
NoWork cum 0.99 5715.2
18202 6.36.1 6.36.1
Rate asofper SHitem
: Brick
NoWork cum 1.18 5715.2
18346 6.36.1 6.36.1asofper
Rate SHitem
: Brick
NoWork cum 0.53 5715.2
18435 6.36.1 6.36.1
Rate as per item NoWork
of SH : Brick cum 0.63 5715.2
18590 6.36.1 6.36.1
Rate asofper SHitem
: Brick
NoWork cum 1.29 5715.2
18685 6.36.1 6.36.1
Rate asofper SHitem
: Brick
NoWork cum 0.66 5715.2
18813 6.36.1 6.36.1asofper
Rate SHitem
: Brick
NoWork cum 3.68 5715.2
18908 6.36.1 6.36.1 of SH : Brick
graded stone aggregate Work cum 5.26 5715.2
17797 6.36.1 20 mm
Rate as nominal
per itemsize) for
No 6.37
18352 6.37 of SHas
Rate : Brick WorkNo 6.37
per item cum 0.02 9085.5
18819 6.37 Cement
of SH : Brick Work1:2:4(1
concrete cum 0.04 9085.5
18598 6.37 cement : 2 coarse
Rate as per item No sand :4
6.4.1
10320 6.4.1 of SHas
Rate :- Brick work.
per item no 6.9 of cum 0.21 6382.9
18252 6.9 SH : Brick Work Cement
Rate as per item no 6.9 of cum 0.02 9550.2
18503 6.9 Rate
SH : Brick
as perWork
itemCement
no 6.9 of cum 0.02 9550.2
18736 6.9 SH : Brick Work
Rate as per item no. Cement cum 0.04 9550.2
19658 12.39.1
Rate as perof SH : Roofing
item no. each 4 337.6
19733 12.39.2 of SH :
Rate as per item no. Roofing each 4 467.7
19907 15.2.1 15.2.1asofper item no.
Rate cum 0.16 1004.45
19962 15.2.1 15.2.1
Rate asofper item no. cum 0.25 1004.45
20028 15.2.1 15.2.1
Rate asofper item no. cum 0.29 1004.45
19881 15.2.2 15.2.2
Rate asofper item no. cum 0.43 619.05
19936 15.2.2 15.2.2
445.72of A SH : Dismantling cum 0.55 619.05
19996 15.2.2 and demolishing
Rate as per item no. 15.3
20332 15.3 of
Rate as per item no. 15.3 cum 0.17
20387 15.3 of
Rate as per item no. 15.3 cum 0.26 1465.35
20486 15.3 of
Rate as per item no. cum 0.02 1465.35
19891 15.7.4 15.7.4
Rate asofper item no. cum 0.34 847.95
19944 15.7.4 15.7.4
Rate asofper item no. cum 0.93 847.95
20021 15.7.4 15.7.4
Rate asofper item no. cum 2.89 847.95
20086 15.7.4 15.7.4asofper item no.
Rate cum 1.31 847.95
20139 15.7.4 15.7.4
Rate asofper item no. cum 0.99 847.95
20160 15.7.4 15.7.4
Rate asofper item no. cum 1.18 847.95
20225 15.7.4 15.7.4 of cum 1.49 847.95
Rate as per item no.
21122 16.8.1 16.8.1
Rate asofper item no. metre 5.2 40.9
21090 16.8.1
18.24 Of of SH:
SH :Water
Road work metre 8.17 40.9
3575 18.24 Supply
18.24 Of SH: Water quintal 1 296.4
3596 18.24 Supply
Rate as per item No. quintal 1 296.4
3631 18.24 18.24
Rate asofper
SH:item
WaterNo.Supply quintal 1 296.4
3652 18.24 18.24
Rate asofper
SH:item
Water 18.78 quintal
no.Supply 1 296.4
2351 Rate as per item no. 18.78 metre
Of SH Water 10 97.7
2318 18.78 Of SHasWater
Rate no. 18.78 metre
Supply
per item 10 97.7
1748 18.78 of SH:aswater
Rate no. 18.78 metre
Supply
per item 10 97.7
213 of SH:asWater
Rate no. 18.78 metre
Supply
per item 10 97.7
248 Rate as per item no. 18.78 metre
of SH: water Supply 10 97.7
272 of SH:aswater
Rate Supply
per item no. 18.78 metre 10 97.7
308 of SH:aswater
Rate Supply
per item no. 18.78 metre 10 97.7
1647 of SH:aswater
Rate Supply
per item no. 18.78 metre 10 97.7
1674 of SH: water Supply
Rate as per item no. 18.78 metre 10 97.7
1711 of SH:aswater
Rate Supply
per item no. metre 10 97.7
21046 2.26.1 2.26.1
Rate asofperSHitem
: Earth
no.work
2.8.1 cum 7.37 51.5
5219 2.8.1 of SH:asEarth
Rate workno. 2.8.1 cum
per item 1.46 171.4
5302 2.8.1 of SH: Earth workno. 2.8.1 cum
Rate as per item 2.85 171.4
5373 2.8.1 of SH:asEarth
Rate workno. 2.8.1 cum
per item 4.1 171.4
5444 2.8.1 of SH:asEarth
Rate workno. 2.8.1 cum
per item 1.46 171.4
5526 2.8.1 of SH:asEarth
Rate workno. 2.8.1 cum
per item 1.09 171.4
21045 of SH: Earth workno. 4.1.3 cum
Rate as per item 14.73 171.4
10370 4.1.3 of SHas
Rate : concrete
per item no. 4.1.3 cum 0.02 5954.35
18514 4.1.3 of SHas
Rate : concrete
per item no. 4.1.3 cum 0.26 5954.35
18838 4.1.3 of SHas
Rate per item no. 4.1.3 cum
: concrete 0.42 5954.35
19221 4.1.3 Rate as per item no. 4.1.3 cum
of SH : Concrete 0.04 5954.35
19248 4.1.3 of SHas
Rate per item no. 4.1.3 cum
: Concrete 0.03 5954.35
19284 4.1.3 of SHas
Rate per item no. 4.1.3 cum
: Concrete 0.03 5954.35
19325 4.1.3 of SHas
Rate per item no. 4.1.3 cum
: Concrete 0.04 5954.35
19350 4.1.3 Rate as per item no. 4.1.3 cum
of SH : Concrete 0.03 5954.35
19389 4.1.3 of SHas
Rate per item no. 4.1.3 cum
: Concrete 0.03 5954.35
19428 4.1.3 of SHas
Rate : Concrete
per item no. 4.1.3 cum 0.03 5954.35
19490 4.1.3 of SH : Concrete
Rate as per item no. 4.1.3 cum 0.01 5954.35
18745 4.1.3 of SHas
Rate : concrete
per item Cement
no. 4.1.3 cum 0.42 5954.35
17480 4.1.3 of SHas
Rate : Concrete
per item Work
no. 4.1.3 cum 0.16 5954.35
17568 4.1.3 of SHas
Rate : Concrete
per item Work
no. 4.1.3
17711 4.1.3 of
Rate as per item Work
SH : Concrete no. 4.1.3 cum 0.25 5954.35
17805 4.1.3 of SH : Concrete Work
Rate as per item no. 4.1.3
17963 4.1.3 of SHas
Rate : Concrete
per item Work
no. 4.1.3 cum 0.25 5954.35
18053 4.1.3 of SHas
Rate : Concrete
per item Work
no. 4.1.3 cum 0.25 5954.35
18265 4.1.3 of SHas
Rate : concrete
per item Work
no. 4.1.3 cum 0.12 5954.35
18362 4.1.3 of
Rate as per item no. 4.1.3 cum
SH : concrete Work 0.12 5954.35
18617 4.1.3 of SHas
Rate : concrete
per item Work
no. 4.1.3 cum 0.26 5954.35
19537 4.1.3 of SH : Concrete Work cum 0.02 5954.35
Rate as per item no. 4.1.3
19571 4.1.3 of
RateSHas : Concrete
per item Work
no. 5.13 cum 0.03 5954.35
20703 5.13 of
RateSHas : RCC
per work
item no. cum 0.04 10111.35
5333 5.22.1 5.22.1 of SH :
Rate as per item no.RCC work kg 21.92 75.4
5416 5.22.1 5.22.1
Rate asofper SHitem work kg
: RCCno. 32.8 75.4
5486 5.22.1 5.22.1
Rate asofper SHitem work kg
: RCCno. 10.48 75.4
5568 5.22.1 5.22.1
Rate asofper SHitem work kg
: RCCno. 17.84 75.4
17510 5.22.1 5.22.1 of SH :
Rate as per item no.RCC work kg 10.57 75.4
17593 5.22.1 5.22.1
Rate asofper SHitem
: RCCno.
work
17742 5.22.1 5.22.1
Rate asofper SHitem work kg
: RCCno. 24.83 75.4
17828 5.22.1 5.22.1
Rate asofper SHitem
: RCCno.
work
18090 5.22.1 5.22.1 of SH :
Rate as per item no.RCC work kg 26.43 75.4
20621 5.22.1 5.22.1
Rate asofper SHitem
: RCCno.
work kg 4.96 75.4
20713 5.22.1 5.22.1
Rate asofper SHitem
: RCCno.
work kg 8 75.4
20867 5.22.1 5.22.1asofper
Rate SHitem
: RCCno.
work kg 6.25 75.4
20940 5.22.1 5.22.1 of SH :
Rate as per item no.RCC work kg 8.17 75.4
21087 5.22.1 5.22.1
Rate asofper SHitem
: RCCno.
work kg 1.6 75.4
17991 5.22.1
5.22.1 of of SH
SH :: RCC
RCC work
work kg 26.43 75.4
5264 5.22.1 (x) kg 13.2 75.4
20344 Rate as per item no.
Rate as per item no. 5.3 of 5.3 of cum 0.17
20610 5.3 SH
Rate : RCC
as perwork
item no. 5.3 of cum 0.06 7835.75
20685 5.3 SH
Rate : RCC
as perwork
item no. 5.3 of cum 0.06 7835.75
20845 5.3 Rate
SH : RCCas perwork
item no. 5.3 of cum 0.13 7835.75
20925 5.3 SH
Rate as per item no. 6.1.1 cum
: RCC work 0.17 7835.75
18138 6.1.1 of
RateS.Has: brick workno. 6.1.1 cum
per item 0.99 5528.25
18183 6.1.1 of
RateS.Has: brick workNo.18.78 cum
per Item 1.18 5528.25
12138 18.78 Rate
of SH:asWATER
per Item No.18.78 metre
SUPPLY 10 97.7
12099 18.78 of SH:WATER
Rate as per Item SUPPLY metre 10 97.7
20305 No.19.24.4 of each -1 2688.3
5155 2.25 Rate
Rate as as per
per item
item No.2.25
No.2.25 cum 0.3 124.5
5220 2.25 Rate
of SH:asEarth WorkNo.2.25
per item (ii) cum 1.46 124.5
5303 2.25 of
Rate as per item No.2.25 cum
SH: Earth work (ii) 2.85 124.5
5374 2.25 of
RateSH:asEarth workNo.2.25
per item (ii) cum 4.1 124.5
5445 2.25 of
RateSH:asEarth workNo.2.25
per item (ii) cum 1.46 124.5
5527 of SH: Earth work (ii)
2.25 Rate as per item No.5.3 cum 1.09 124.5
5258 5.3 Of
RateSH:asRCCper item No.5.3 cum 0.17 7835.75
5327 5.3 Of
RateSH:asRCCper item No.5.3 cum 0.27 7835.75
5399 5.3 Of
RateSH:asRCCper item No.5.3 cum 0.41 7835.75
5480 Of SH: RCC
5.3 Rate as per item No.5.3 cum 0.13 7835.75
5553 5.3 Of
RateSH:asRCCper item No.5.3 cum 0.22 7835.75
5182 5.3 SH
Rate : R.C.C
as per item No.5.9.3 cum 0.02 7835.75
5267 5.9.3 Of
RateSH:asRCCper item No.5.9.3 sqm 0.86 468.3
5420 5.9.3 Of SH:asRCC
Rate per item No.5.9.3 sqm 2.3 468.3
5572 5.9.3 Of
Rate as per item No.5.9.3 sqm
SH: RCC 1.03 468.3
5337 Of
RateSH:asRCCper item No.5.9.3 sqm 1.49 468.3
5490 Of SH: RCC sqm 0.86 468.3
Rate as per Item Number
9310 18.23 18.23
Rate asofper
SH:Item
Water Supply quintal
Number 28.27 157.1
9345 18.23 18.23
Rate asofper
SH:Item
Water Supply quintal
Number 34.82 157.1
9378 18.23 18.23 of SH: Water Supply quintal
Rate as per Item Number 1.776 157.1
9404 18.23 18.23
Rate asofper
SH:Item
Water Supply quintal
Number 2.627 157.1
9439 18.23 18.23
Rate asofper
SH:Item
Water Supply quintal
Number 3.615 157.1
9465 18.23 18.23
Rate asofper
SH:Item
Water Supply quintal
Number 4.8 157.1
9500 18.23 18.23 of SH: Water Supply quintal
Rate as per Item Number 6.049 157.1
9536 18.23 18.23
Rate asofper
SH:Item
Water Supply quintal
Number 7.973 157.1
9562 18.23 18.23
Rate asofper
SH:Item
Water Supply quintal
Number 9.48 157.1
9598 18.23 18.23
Rate asofper
SH:Item
Water Supply quintal
Number 11.097 157.1
9625 18.23 18.23 of SH: Water Supply quintal
Rate as per Item Number 12.948 157.1
9662 18.23 18.23
Rate asofper
SH:Item
Water Supply quintal
Number 16.868 157.1
9757 18.23 18.23
Rate asofper
SH:Item
Water Supply quintal
Number 26.71 157.1
9782 18.23asofper
18.23 Rate SH:Item
Water Supply quintal
Number 32.129 157.1
9855 18.23 18.23 of SH: Water Supply quintal
Rate as per Item Number 1.09 157.1
9881 18.23 18.23
Rate asofper
SH:Item
Water Supply quintal
Number 1.63 157.1
9917 18.23 18.23
Rate asofper
SH:Item
Water Supply quintal
Number 2.21 157.1
9952 18.23asofper
18.23 Rate SH:Item
Water Supply quintal
Number 2.97 157.1
9978 18.23 18.23 of SH: Water Supply quintal
Rate as per Item Number 3.82 157.1
10014 18.23 18.23
Rate asofper
SH:Item
Water Supply quintal
Number 4.57 157.1
10040 18.23 18.23
Rate asofper
SH:Item
Water Supply quintal
Number 5.4 157.1
10074 18.23 Rate
18.23asofper
SH:Item
Water Supply quintal
Number 6.39 157.1
10110 18.23 18.23 of SH: Water Supply quintal
Rate as per Item Number 7.4 157.1
10136 18.23 18.23
Rate asofper
SH:Item
Water Supply quintal
Number 9.95 157.1
9250 18.23
Rate asofper
SH:Item
Water Supply quintal
Number 18.89 157.1
9286 18.23asofper
Rate SH:Item
Water Supply quintal
Number 24.35 157.1
9697 18.23 of SH: Water Supply quintal
Rate as per Item Number 21.754 157.1
9722 18.23
Rate asofper
SH:Item
Water Supply quintal
Number 24.26 157.1
9817 18.23
Rate asofper
SH:Item
Water Supply quintal
Number 38.019 157.1
10170 18.23asofper
Rate SH:Item
Water Supply quintal
Number 12.75 157.1
8023 18.24 18.24 of SH: Water Supply quintal
Rate as per Item Number 1 296.4
8043 18.24 18.24
Rate asofper
SH:Item
Water Supply quintal
Number 1 296.4
8075 18.24 18.24
Rate asofper
SH:Item
Water Supply quintal
Number 1 296.4
8095 18.24 of SH: Water Supply quintal
18.24 Rate as per Item Number 1 296.4
8125 18.24 18.24
Rate asofper
SH:Item
Water Supply quintal
Number 1 296.4
8142 18.24 18.24
Rate asofper
SH:Item
Water Supply quintal
Number 1 296.4
8173 18.24 18.24
Rate asofper
SH:Item
Water Supply quintal
Number 1 296.4
8190 18.24 of SH: Water Supply quintal
18.24 Rate as per Item Number 1 296.4
6080 18. 41.1A 18.41.1A
Rate as perof Item
SH:Water
Number cum 0.74 1866.8
6209 18. 41.1A 18.41.1A
Rate as perof Item
SH:Water
Number cum 0.8 1866.8
6229 18. 41.1A 18.41.1A
Rate as perof Item
SH:Water
Number cum 0.83 1866.8
6258 18. 41.1A 18.41.1A
Rate as perof Item
SH:Water
Number cum 1.31 1866.8
6278 18. 41.1A 18.41.1A
Rate as per Item Number cum
of SH:Water 1.35 1866.8
6296 18. 41.1A 18.41.1A
Rate as perof Item
SH:Water
Number cum 1.43 1866.8
700 18.78 of SH: Water supply L.S. 10 97.7
Rate as per Item Number
725 18.78
Rate asofper
SH:Item
Water supply L.S.
Number 10 97.7
759 18.78
Rate asofper
SH:Item
Water supply L.S.
Number 10 97.7
22926 3.7 3.7
Rate as per Item Number cum
of SH: Mortars 0.025 5150.6
22966 3.7 3.7
RateofasSH: Item Number cum
perMortars 0.025 5150.6
23008 3.7 3.7
RateofasSH: Item Number cum
perMortars 0.025 5150.6
22809 3.7
RateofasSH:
perMortars
Item Number
22852 3.7
Rate as perMortars
of SH: Item Number
22886 3.7 of SH: Mortars
21257 Rate per metre
21296 Rate per metre
21332 Rate per metre 4534.74
21360 Rate per metre
21396 Rate per metre
21435 Rate per metre 13519.19
21611 Rate per metre
21648 Rate per metre 7857.63
21677 Rate per metre
21714 Rate
Rate per
samemetre
as per item no
3688 18.23 18.23
Rate same asWater
of SH: Supply
per item no quintal 1.98 157.1
3713 18.23 18.23 of SH:asWater
Rate same Supply
per item no quintal 2.58 157.1
3748 18.23 18.23 of SH:asWater
Rate same Supply
per item no quintal 3.22 157.1
3784 18.23 Rate
18.23same
of SH:asWater Supply
per item no quintal 4.71 157.1
3809 18.23 18.23
Rate same as per item no quintal
of SH: Water Supply 6.35 157.1
3845 18.23 18.23 of SH:asWater
Rate same Supply
per item no quintal 8.18 157.1
3881 18.23 18.23 of SH:asWater
Rate same Supply
per item no quintal 10.31 157.1
3907 18.23 Rate
18.23same
of SH:asWater no quintal
Supply
per item 12.55 157.1
3945 18.23 18.23
Rate same as per item no quintal
of SH: Water Supply 15.13 157.1
3971 18.23 18.23 of SH:asWater
Rate same no quintal
Supply
per item 17.71 157.1
4008 18.23 18.23 of SH:asWater
Rate same no quintal
Supply
per item 23.6 157.1
8627 18.23 Rate
18.23same
of SH:asWater no quintal
Supply
per item 1.35 157.1
8662 18.23 18.23
Rate same as per item no quintal
of SH: Water Supply 2.21 157.1
8697 18.23 18.23 of SH:asWater
Rate same no quintal
Supply
per item 3.18 157.1
8724 18.23 18.23 of SH:asWater
Rate same Supply
per item no quintal 4.27 157.1
8760 18.23 of SH: Water Supply
18.23 Rate same as per item no quintal 5.5 157.1
8785 18.23 18.23 of SH:asWater
Rate same Supply
per item no quintal 6.79 157.1
8820 18.23 18.23 of SH:asWater
Rate same Supply
per item no quintal 8.34 157.1
8857 18.23 18.23 of SH:asWater
Rate same Supply
per item no quintal 10.08 157.1
8882 18.23 of SH: Water Supply
18.23 Rate same as per item no quintal 11.74 157.1
8916 18.23 18.23 of SH:asWater
Rate same Supply
per item no quintal 15.77 157.1
8953 18.23 of SH:asWater
Rate same Supply
per item no quintal 1.54 157.1
8977 18.23 of SH:asWater
Rate same Supply
per item no quintal 2.28 157.1
9011 18.23same
Rate of SH:asWater Supply
per item no quintal 3.01 157.1
9035 18.23
Rate same as per item no quintal
of SH: Water Supply 3.93 157.1
9070 18.23 of SH:asWater
Rate same Supply
per item no quintal 4.84 157.1
9094 18.23 of SH: Water Supply quintal 6.6 157.1
Rate same as per item no
9129 18.23 of SH:asWater
Rate same Supply
per item no quintal 7.83 157.1
9165 18.23 of SH:asWater
Rate same Supply
per item no quintal 9.14 157.1
9190 18.23
Rate same as per item no quintal
of SH: Water Supply 10.66 157.1
9225 18.23 of SH:
RCC pipe 1000Water
mm Supply
dia quintal 13.86 157.1
21339 1731 NP-3 spigot
RCC pipe 1000 mm dia metre 10 3885
21618 1737 pipe NP-41200
RCC pipe spigotmm dia metre 10 5565
21367 1732 NP-3 spigot
RCC pipe 1200 mm dia metre 10 5040
21655 1738 pipe NP-41800
RCC pipe spigotmm dia metre 10 6510
21403 1733 NP-3 spigot
RCC pipe 1800 mm dia metre 10 9450
21684 1739 pipe NP-4450
RCC pipe mm dia NP- metre
spigot 10 13650
21235 1728 3
RCC pipe 450 mm dia NP- metre
spigot 10 1496
21444 1734 4 spigot
RCC pipe 600 mm dia NP- metre 10 1733
21264 1729 3 spigot
RCC pipe 600 mm dia pipe metre 10 1995
21485 NP-4pipe
1735 RCC spigot
900 mm dia NP-
21303 1730 3 spigot
RCC pipe 900 mm dia pipe metre 10 3150
21529 1736 NP-4 spigot
RCC pipe above 1200 mm
21685 2336 dia and upto
manhole 140x90 1800cm mmand 100 0.1 7732.61
19985 19.24.3 2.45 m deep
beyond 2.45 m depth (up
20185 19.25.3 to
Rectangular cover
17519 1354 455x610 mmcover
Rectangular with frame each 1 1400
17609 1354 455x610
455x610 mmmm with
with frame
frame
20788 1354 (low
455x610 mm with frame each 1 1400
20868 1354 (low
455x610 mm with frame each 1 1400
20941 1354 (low
455x610mm without each 1 1400
19127 1355 frame
120x90(low
cm and 90 cm each 1 910
19929 19.24.2 deep
120x90 cm and beyond 90
20154 19.25.2 cm depth
cover 500 mm dia of
20374 19.26.2 grade MD mm dia of
cover 560
20423 19.26.3 grade HD manhole
Rectangular
19873 19.24.1 90x80 cm
90x80 cm and
and beyond
45 cm deep45
20133 19.25.1 cm depth
rectangular cover 600 x
20322 19.26.1 450 mm of grade
Rectangular shapeLD - 2.5
19315 7133 500x500
600x450 mmmm precast
internal each 1 670
19210 19.19.1.1 dimensions
Rectangular shape
19213 7130 600x450 mmtype
Rectangular precast
with each 1 675
7488 18.58.2 openable
openable circular
circular lid
lid 150
7495 7412 mm
Reducer for 22.22 mm X each 1 118
12309 8791 15.88
Reducermm forouter
28.58DiammSS X each 1 103
12326 8792 15.88
Reducermm forouter
28.58DiammSS X each 1 141
12343 8793 22.22
Reducermm forouter
34.00DiammSS X each 1 145
12369 8794 15.88
Reducermm forouter
34.00DiammSS X each 1 184
12386 8795 Reducer
22.22 mm forouter
34.00DiammSS X each 1 187
12413 8796 28.58 mm outer Dia
Reducer for 42.70 mm SS X each 1 190
12430 8797 15.88
Reducermm forouter
42.70DiammSS X each 1 359
12447 8798 22.22 mm outer Dia SS each 1 362
Reducer for 42.70 mm X
12474 8799 28.58
Reducer mm forouter
42.70DiammSS X each 1 362
12491 8800 34.00
Reducer mm forouter
48.60DiammSS X each 1 387
12518 8801 15.88 mm outer
Reducer for 48.60 mm Dia SS X each 1 410
12535 8802 22.22
Reducer mm forouter
48.60DiammSS X each 1 410
12563 8803 28.58
Reducer mm forouter
48.60DiammSS X each 1 410
12578 8804 34.00
42.70 mmmm outer
outer Dia
Dia SS
SS each 1 410
12605 8805 pipe each
22.22 mm X 15.88 mm 1 410 410
12876 8818 outer
28.58 mm each X 15.88 mm 1 148 148
12902 8819 outer
28.58 mm X 22.22 mm each 1 191
12917 8820 outer
34.00 mm X 22.22 mm each 1 221
12944 8821 outer each
34.00 mm X 28.58 mm 1 287 287
12961 8822 outer
42.70 mm each X 34.00 mm 1 345 345
12978 8823 outer each
Reducing Tee for 22.22 1 179 179
13129 mm X 15.88
8830 Reducing Teemmfor outer
28.58dia each 1 179
13155 8831 mm
Reducing Tee for 28.58dia each
X 15.88 mm outer 1 273
13172 8832 mm X 22.22
Reducing Teemmfor outer
34.00dia each 1 273
13198 8833 mm X 15.88
Reducing Teemmfor outer
34.00dia each 1 437
13215 mm X 22.22
8834 Reducing Teemmfor outer
34.00dia each 1 437
13243 8835 mm
Reducing Tee for 42.70dia each
X 28.58 mm outer 1 437
13260 8836 mm X 15.88
Reducing Teemmfor outer
42.70dia each 1 683
13277 8837 mm X 22.22
Reducing Teemmfor outer
42.70dia each 1 683
13305 8838 Reducing
mm X 28.58 Teemmfor outer
42.70dia each 1 683
13322 8839 mm
Reducing Tee for 48.60dia each
X 34.00 mm outer 1 683
13349 8840 mm X 15.88
Reducing Teemmfor outer
48.60dia each 1 887
13366 8841 mm X 22.22
Reducing Teemmfor outer
48.60dia each 1 887
13393 8842 48.60mm
mm X 28.58 mm dia each
mm outer
X 34.00 1 887
13410 8843 outer dia SS
48.60mm X 42.70mm each 1 887 887
13427 8844 outer diaand
refilling SS disposal
each of 1 887 887
5371 surplus
refilling earth
and disposal of
5441 surplus earth
refilling and disposal of
5524 surplus earth
concrete 1:1.5:3 (1
17730 cement
concrete: 1.5 1:1.5:3 (1
17976 cement : 1.5
3 graded stone aggregate
17814 13.9.1 20 mm 1:2:4 (1 cement :
concrete
18075 2
Reinforcement @ 80
21086 kg/cum
boring with= 0.02x80 =1.6 kg
bentonite
22293 solution
Removaland of C.I. Cover with
19917 9999 frame
Removal of C.I. Cover with L.S. 7.15 2
19972 9999 frame
Removal of C.I. Cover with L.S. 7.15 2
20038 9999 frame L.S. 7.15 2
20039 9999 Removal
Removal of of M.S
M.S.foot
footrest L.S. 8.06 2
20106 rests
Removal of M.S. foot L.S. 8.06 2
20303 9999 rests Deduct cost
Removal of R.C.C cover of L.S. 8.09 2
20389 9999 and frameof R.C.C cover
Removal L.S. 7.15 2
20438 9999 and frame L.S. 7.15 2
Removal of R.C.C cover
20488 9999 and frameof R.C.C cover
Removal L.S. 8.06 2
20334 and frameof R.C.C work
Removal L.S. 7.15 2
20335 1:1.5:3
Removal of S.F.R.C cover
20104 9999 with frame size 560 mm L.S. 7.15 2
20302 9999 Removal
RemovingofofSFRC
M.S.cover
foot L.S. 7.15 2
20141 9999 rests
Removing of M.S. foot L.S. 1.82 2
20162 9999 rests
one coat of approved L.S. 1.82 2
5745 18.39 quality
graded :stone aggregate
19030 19.17 20 mm nominal size):
23307 9999 Reporting charges= 1.56
reqd. = 0.156x10 L.S. 100.67 2
16269 cum
required dia as per
15583 direction of Engineer-
required dia as per
15693 direction of Engineer-
1.5 times the Safe
23109 20.6.2.2 capacity)
Rubber insertions for 100
4438 1374 mm dia insertions
Rubber pipe jointsfor 125 each 10 18
4461 1375 mm dia insertions
Rubber pipe jointsfor 150 each 10 20
4494 1376 mm dia insertions
Rubber pipe jointsfor 200 each 10 20
4517 mm dia insertions
1377 Rubber pipe jointsfor 250 each 10 25
4550 1378 mm dia pipe jointsfor 300
Rubber insertions each 10 40
4573 1379 mm dia insertions
Rubber pipe jointsfor 350 each 10 45
4607 1380 mm dia insertions
Rubber pipe jointsfor 400 each 10 50
4630 1381 Rubber
mm dia insertions
pipe jointsfor 450 each 10 73
4663 1382 mm dia pipe jointsfor 500
Rubber insertions each 10 92
4686 1383 mm dia insertions
Rubber pipe jointsfor 600 each 10 110
4719 1384 mm dia insertions
Rubber pipe jointsfor 80 each 10 125
4406 1373 Ruber
mm diaGaskets
pipe joints each 10 16
8217 7666 Conforming
Ruber Gaskets to I.S 5382 of each 50 29
8239 7668 Conforming
Ruber Gaskets to I.S 5382 of each 50 36
8271 7669 Conforming
Ruber Gaskets to I.S 5382 of each 50 63
8293 7670 Ruber
Conforming to I.S 5382 of
Gaskets each 50 74
8325 7671 Conforming
Ruber Gaskets to I.S 5382 of each 50 110
8347 7672 Conforming
Ruber Gaskets to I.S 5382 of each 50 126
8379 7673 Conforming
Ruber Gaskets to I.S 5382 of each 50 230
8401 Conforming
7674 Ruber Gaskets to I.S 5382 of each 50 270
8433 7675 Conforming
Ruber Gaskets to I.S 5382 of each 50 290
8455 7676 Conforming
Ruber Gaskets to I.S 5382 of each 50 365
8487 7677 Conforming
Ruber Gaskets to I.S 5382 of each 50 550
8509 Conforming
7678 Ruber Gaskets to I.S 5382 of each 50 660
8540 7679 Conforming
Ruber Gaskets to I.S 5382 of each 50 725
8562 7680 Conforming
Ruber Gaskets to I.S 5382 of each 50 960
8594 7681 Conforming to I.S 5382
S & S.C.I.standard of
specials each 50 1145
3591 1466 Sover 300 mm dia (heavy
& S.C.I.standard specials quintal 1 3700
3560 1464 upto 300 mm dia (heavy quintal 1 3600
8595 S.B.R quality 1000mm dia
8218 S.B.R quality 100mm dia
8240 S.B.R quality 150mm dia
8272 S.B.R quality 200mm dia
8294 S.B.R quality 250mm dia
8326 S.B.R quality 300mm dia
8348 S.B.R quality 350mm dia
8380 S.B.R quality 400mm dia
8402 S.B.R quality 450mm dia
8434 S.B.R quality 500mm dia
8456 S.B.R quality 600mm dia
8488 S.B.R quality 700mm dia
8510 S.B.R quality 750mm dia
8541 S.B.R quality 800mm dia
8563 S.B.R quality 900mm dia
6485 1693 S.C.I.
S.C.I. hand pump100 mm each
plain bend 1 670
19619 1621 dia
S.C.I. plain bend 150 mm each 1 258
19705 1622 dia
junctions 100x100x100 each 1 460
19620 1628 mm
S.C.I. soil, waste and vent each 1 360
19611 singlesoil,
1617 S.C.I. socketed
wastepipe
and 1.80
vent each 0.55556 1135
19775 1617 single socketed pipe 1.80
S.C.I. soil, waste and vent each 0.55556 1135
19697 1618 single socketed
S.C.I. soil, wastepipe
and 1.80
vent each 0.55556 1750
19821 1618 single socketed pipe 1.80 each 0.55556 1750
19706 7087 S.C.I.
S.F.R.C Tee 150Circular
cover mm each 1 570
18861 7135 shape 560 mm dia
S.F.R.C manhole cover precast each 1 880
18638 and frame
Circular shape 560 mm
18537 7135 dia
S.W. gully trap P type each 1 880
16327 1900 S.W.
100x100gullymmtrap P type each 1 100
16377 1900 100x100 mm
S.W. gully trap P type each 1 100
16433 1902 150x100
S.W. gullymm trap P type each 1 130
16490 1902 150x100
S.W. gullymm trap P type each 1 130
16547 1904 S.W.
180x150gullymmtrap P type each 1 225
16602 1904 180x150
S.W. intercepting trap 100 each
mm 1 225
21159 7128 mm
S.W.diaintercepting trap 150 each 1 185
21197 7129 mm
S&S dia
Centrifugally (Spun) each 1 240
3682 C.I. Pipe class
7697 S&S Centrifugally (Spun) metre 10 857
3708 7698 C.I. Pipe class
S&S Centrifugally (Spun) metre 10 1067
3743 7699 C.I.
S&SPipe class
Centrifugally (Spun) metre 10 1286
3778 7700 C.I.
S&SPipe class
Centrifugally (Spun) metre 10 2190
3804 C.I. Pipe class
7701 S&S Centrifugally (Spun) metre 10 2857
3839 7702 C.I.
S&SPipe class
Centrifugally (Spun) metre 10 3857
3866 7703 C.I.
S&SPipe class
Centrifugally (Spun) metre 10 4619
3901 7704 C.I.
S&SPipe class
Centrifugally (Spun) metre 10 6095
3939 7705 S&S
C.I. Pipe class
Centrifugally (Spun) metre 10 7381
3966 7706 C.I.
S&S Centrifugally (Spun) metre
Pipe class 10 8571
4002 7707 C.I.
S&SPipe class
Centrifugally (Spun) metre 10 11995
8039 7709 C.I. Pipe Specials quintal 1 6200
S&S Centrifugally (Spun)
8071 7710 C.I.
S&SPipe specials (Spun) quintal
Centrifugally 1 8571
8091 7711 C.I.
S&SPipe Specials (Spun) quintal
Centrifugally 1 9048
8020 7708 C.I.
excludingSpecials
Pipe as per
the cost of IS quintal 1 5190
22292 steel
16854 sand : 2 parts Sand)
16985 sand : 2 parts Sand)
17282 sand : 2 parts Sand)
17413 sand : 2 parts Sand)
21242 sand : 2 parts Sand)
21281 sand : 2 parts Sand)
21309 sand : 2 parts Sand)
21381 sand : 2 parts Sand)
21450 sand : 2 parts Sand)
21535 sand : 2 parts Sand)
21662 sand
sand :: 23 parts
gradedSand)
stone
20781 aggregate 20 mm
sand : 4 grade stone nominal
19484 aggregate
aggregate 20 20 mm
mm nominal
nominal
19531 size
aggregate 20 mm nominal
19566 size
sand finished with floating
21001 coat
sand of neat cement
finished Wall
with floating
20982 coat
sand of neat cementWall
finished with floating:
21030 coat of neat cementWall :
6099 6501 Sand zone
floating V (Jamuna)
coat of neat cum 1 1225
5167 cement.
floating coat of neat
5314 cement.
floating coat of neat
5386 cement.
floating coat of neat
5467 cement.
floating coat of neat
5539 cement.
floating coat of neat
18140 cement
floating coat of neat
18157 cement
floating coat of neat
18204 cement
floating coat of neat
18285 cement
floating coat of neat
18526 cement
floating coat of neat
18755 cement
floating coat of neat
18849 cement
floating coat of neat
18910 cement
floating coat of neat
19728 cement
floating coat of neat
20535 cement
floating coat of neat
20591 cement
floating coat of neat
20669 cement
floating coat of neat
20773 cement
floating coat of neat
20832 cement
floating coat of neat
16352 cement
floating :coat of neat
16404 cement
floating :coat of neat
16462 cement :
floating coat of neat
16516 cement
floating :coat of neat
16573 cement
floating :coat of neat
16628 cement
floating :coat of neat
18675 cement.
floating coat of neat
18687 cement.
34 Say
68 Say
103 Say
127 Say
164 Say
198 Say
228 Say
263 Say
297 Say
323 Say
370 Say
404 Say
439 Say
464 Say
499 Say
524 Say
559 Say
591 Say
615 Say
650 Say
684 Say
715 Say
749 Say
785 Say
816 Say
854 Say
893 Say
921 Say
959 Say
987 Say
1020 Say
1059 Say
1088 Say
1342 Say
1409 Say
1427 Say
1465 Say
1501 Say
1526 Say
1561 Say
1596 Say
1621 Say
1662 Say
1699 Say
1726 Say
1763 Say
1805 Say
1831 Say
1865 Say
1902 Say
1928 Say
1963 Say
1989 Say
2026 Say
2062 Say
2088 Say
2130 Say
2166 Say
2193 Say
2228 Say
2265 Say
2292 Say
2333 Say
2377 Say
2418 Say
2445 Say
2482 Say
2519 Say
2545 Say
2581 Say
2609 Say
2646 Say
2679 Say
2701 Say
2730 Say
2749 Say
2776 Say
2795 Say
2812 Say
2842 Say
2857 Say
2886 Say
2904 Say
2932 Say
2950 Say
2968 Say
2998 Say
3016 Say
3044 Say
3064 Say
3089 Say
3108 Say
3124 Say
3152 Say
3168 Say
3194 Say
3210 Say
3236 Say
3252 Say
3281 Say
3297 Say
3325 Say
3342 Say
3359 Say
3389 Say
3405 Say
3435 Say
3451 Say
3481 Say
3499 Say
3531 Say
3552 Say
3585 Say
3606 Say
3641 Say
3671 Say
3699 Say
3734 Say
3759 Say
3795 Say
3830 Say
3856 Say
3892 Say
3918 Say
3956 Say
3992 Say
4019 Say
4055 Say
4090 Say
4116 Say
4151 Say
4187 Say
4213 Say
4250 Say
4285 Say
4311 Say
4346 Say
4372 Say
4398 Say
4423 Say
4455 Say
4488 Say
4511 Say
4544 Say
4567 Say
4601 Say
4624 Say
4657 Say
4680 Say
4713 Say
4736 Say
4777 Say
4813 Say
4849 Say
4874 Say
4912 Say
4948 Say
4975 Say
5010 Say
5047 Say
5072 Say
5109 Say
5134 Say
5207 Say
5279 Say
5360 Say
5432 Say
5502 Say
5584 Say
5607 Say
5639 Say
5671 Say
5693 Say
5713 Say
5743 Say
5764 Say
5792 Say
5811 Say
5840 Say
5859 Say
5888 Say
5908 Say
5936 Say
5954 Say
5972 Say
5999 Say
6017 Say
6046 Say
6064 Say
6095 Say
6112 Say
6142 Say
6162 Say
6182 Say
6214 Say
6234 Say
6263 Say
6283 Say
6301 Say
6355 Say
6387 Say
6421 Say
6443 Say
6479 Say
6500 Say
6532 Say
6552 Say
6581 Say
6601 Say
6630 Say
6650 Say
6679 Say
6699 Say
6731 Say
6751 Say
6780 Say
6800 Say
6829 Say
6849 Say
6879 Say
6899 Say
6933 Say
6965 Say
6986 Say
7005 Say
7034 Say
7053 Say
7080 Say
7096 Say
7267 Say
7284 Say
7313 Say
7330 Say
7350 Say
7379 Say
7396 Say
7425 Say
7442 Say
7471 Say
7486 Say
7517 Say
7542 Say
7575 Say
7598 Say
7633 Say
7656 Say
7689 Say
7721 Say
7744 Say
7774 Say
7795 Say
7825 Say
7845 Say
7874 Say
7892 Say
7921 Say
7939 Say
7969 Say
7986 Say
8012 Say
8033 Say
8063 Say
8085 Say
8114 Say
8135 Say
8152 Say
8183 Say
8200 Say
8233 Say
8265 Say
8287 Say
8319 Say
8341 Say
8373 Say
8395 Say
8427 Say
8449 Say
8481 Say
8503 Say
8534 Say
8556 Say
8588 Say
8610 Say
8648 Say
8673 Say
8708 Say
8746 Say
8771 Say
8806 Say
8831 Say
8868 Say
8902 Say
8927 Say
8964 Say
8998 Say
9022 Say
9057 Say
9081 Say
9116 Say
9140 Say
9176 Say
9211 Say
9236 Say
9272 Say
9297 Say
9331 Say
9356 Say
9389 Say
9424 Say
9450 Say
9485 Say
9511 Say
9547 Say
9582 Say
9609 Say
9646 Say
9673 Say
9708 Say
9743 Say
9768 Say
9803 Say
9828 Say
9866 Say
9902 Say
9928 Say
9963 Say
9989 Say
10025 Say
10061 Say
10085 Say
10121 Say
10157 Say
10181 Say
10213 Say
10231 Say
10259 Say
10276 Say
10303 Say
10352 Say
10386 Say
10422 Say
10444 Say
10482 Say
10516 Say
10539 Say
10569 Say
10601 Say
10624 Say
10657 Say
10680 Say
10717 Say
10749 Say
10772 Say
10804 Say
10826 Say
10860 Say
10880 Say
10913 Say
10933 Say
10966 Say
10986 Say
11019 Say
11039 Say
11072 Say
11092 Say
11125 Say
11168 Say
11199 Say
11239 Say
11281 Say
11312 Say
11352 Say
11392 Say
11423 Say
11464 Say
11505 Say
11546 Say
11577 Say
11608 Say
11626 Say
11644 Say
11669 Say
11687 Say
11715 Say
11733 Say
11751 Say
11779 Say
11797 Say
11822 Say
11840 Say
11869 Say
11910 Say
11939 Say
11975 Say
12014 Say
12043 Say
12082 Say
12126 Say
12166 Say
12185 Say
12211 Say
12228 Say
12245 Say
12274 Say
12290 Say
12320 Say
12337 Say
12363 Say
12380 Say
12407 Say
12424 Say
12441 Say
12468 Say
12485 Say
12512 Say
12529 Say
12557 Say
12574 Say
12600 Say
12615 Say
12635 Say
12659 Say
12675 Say
12701 Say
12717 Say
12733 Say
12766 Say
12782 Say
12806 Say
12822 Say
12848 Say
12864 Say
12896 Say
12913 Say
12938 Say
12955 Say
12972 Say
12999 Say
13019 Say
13045 Say
13061 Say
13077 Say
13103 Say
13119 Say
13149 Say
13166 Say
13192 Say
13209 Say
13226 Say
13254 Say
13271 Say
13299 Say
13316 Say
13343 Say
13360 Say
13377 Say
13404 Say
13421 Say
13449 Say
13470 Say
13497 Say
13514 Say
13531 Say
13557 Say
13574 Say
13601 Say
13618 Say
13635 Say
13664 Say
13681 Say
13709 Say
13726 Say
13743 Say
13770 Say
13787 Say
13814 Say
13831 Say
13859 Say
13876 Say
13893 Say
13925 Say
13942 Say
13968 Say
13985 Say
14002 Say
14027 Say
14044 Say
14071 Say
14088 Say
14105 Say
14132 Say
14149 Say
14176 Say
14193 Say
14221 Say
14238 Say
14267 Say
14284 Say
14301 Say
14328 Say
14345 Say
14376 Say
14394 Say
14413 Say
14440 Say
14459 Say
14487 Say
14505 Say
14534 Say
14552 Say
14581 Say
14599 Say
14617 Say
14647 Say
14665 Say
14691 Say
14709 Say
14738 Say
14755 Say
14772 Say
14798 Say
14815 Say
14842 Say
14859 Say
14890 Say
14907 Say
14935 Say
14952 Say
14969 Say
14996 Say
15013 Say
15043 Say
15060 Say
15084 Say
15101 Say
15118 Say
15146 Say
15163 Say
15191 Say
15208 Say
15249 Say
15329 Say
15451 Say
15515 Say
15580 Say
15599 Say
15613 Say
15638 Say
15652 Say
15676 Say
15690 Say
15710 Say
15738 Say
15753 Say
15816 Say
15860 Say
15902 Say
15947 Say
15991 Say
16014 Say
16045 Say
16065 Say
16085 Say
16126 Say
16181 Say
16223 Say
16274 Say
16318 Say
16374 Say
16426 Say
16485 Say
16540 Say
16596 Say
16650 Say
16671 Say
16698 Say
16717 Say
16744 Say
16762 Say
16780 Say
16806 Say
16824 Say
16870 Say
16914 Say
17054 Say
17088 Say
17131 Say
17175 Say
17220 Say
17263 Say
17307 Say
17350 Say
17385 Say
17429 Say
17535 Say
17683 Say
17765 Say
17924 Say
18024 Say
18124 Say
18145 Say
18191 Say
18209 Say
18311 Say
18409 Say
18429 Say
18455 Say
18560 Say
18653 Say
18679 Say
18691 Say
18790 Say
18875 Say
18899 Say
18914 Say
18958 Say
18990 Say
19028 Say
19073 Say
19116 Say
19141 Say
19173 Say
19195 Say
19235 Say
19271 Say
19297 Say
19337 Say
19372 Say
19402 Say
19442 Say
19462 Say
19512 Say
19559 Say
19603 Say
19690 Say
19766 Say
19817 Say
19866 Say
19928 Say
19983 Say
20050 Say
20152 Say
20183 Say
20251 Say
20318 Say
20372 Say
20421 Say
20461 Say
20508 Say
20561 Say
20645 Say
20730 Say
20812 Say
20883 Say
20987 Say
21006 Say
21036 Say
21106 Say
21151 Say
21191 Say
21219 Say
21258 Say
21297 Say
21333 Say
21361 Say
21397 Say
21436 Say
21612 Say
21649 Say
21678 Say
21715 Say
21798 Say
21836 Say
21876 Say
21915 Say
21984 Say
22022 Say
22060 Say
22106 Say
22147 Say
22331 Say
22370 Say
22407 Say
22448 Say
22606 Say
22646 Say
22687 Say
22722 Say
22748 Say
22783 Say
22832 Say
22875 Say
22916 Say
22955 Say
23063 Say
23108 Say
23154 Say
23201 Say
23217 Say
23265 Say
23282 Say
23318 Say
20763 Say .20 cum
5164 Say 0.10 cum.
20783 say 0.11 cum
16575 say 0.16 sqm
16518 say 0.160 sqm
16312 Say 0.180 sqm
16030 Say 0.181 sqm
19725 Say 0.28 cum
16354 say 0.29 sqm
16464 say 0.30 sqm
5536 Say 0.35 cum.
5229 Say 0.57 cum.
5464 Say 0.57 cum.
20085 Say 1.131 cum
16177 Say 1.14 cum
5383 Say 1.32 cum.
5218 Say 1.46 cum.
20600 Say 1.55 cum
20271 Say
Say 1.93 cumsqmm or
133817
16216 0.134 sqm
Say 155968 sqmm or
16267 0.156 sqm
18730 Say 3.68 cum
18812 Say
Say 3.68
70341cumsqmm or
16120 0.070341 sqm flanged
Screwed double
8621 7712 centrigually
Screwed double cast flanged metre 5 1310
8657 7713 centrigually
Screwed double cast flanged metre 5 2048
8682 centrigually
7714 Screwed cast flanged metre
double 5 3238
8717 7715 centrigually
Screwed double cast flanged metre 5 3905
8753 7716 centrigually
Screwed double cast flanged metre 5 4990
8778 7717 centrigually
Screwed double cast flanged metre 5 6286
8813 centrigually
7718 Screwed cast flanged metre
double 5 8143
8850 7719 centrigually
Screwed double cast flanged metre 5 10381
8875 7720 centrigually
Screwed double cast flanged metre 5 12914
8909 7721 centrigually cast work in metre
secon class brick 5 17905
19938 cement class
Second mortar 1:4edging
brick (1
21124 laid length wise with half
6938 separately.
sewer brick in (confirming
16395 to IS 4885)
sewer brickscement mortar
conforming
18198 to IS bricks conforming
sewer
18152 to IS : 4885
sewer bricksinconforming
cement
18036 to IS:4885 in cement
19835 SH
SH :: Concrete
DemolishingWorkand
19916 dismantling
SH : Demolishing and
19971 dismantling
SH : Demolishing and
20037 dismantling
SH : Demolishing and
20103 dismantling
SH : Demolishing and
20247 dismantling
20292 SH
SH :: Dismantling
Dismantling and
20333 9999 demolishing
SH : Dismantling and
20388 demolishing
SH : Dismantling and
20437 demolishing
SH : Dismantling and
20487 demolishing
demolishing Dismantling
19908 of
demolishing Dismantling
19937 of
demolishing Dismantling
19963 of
demolishing Dismantling
20029 of
10327 SH : Finishing)
20350 9999 SH : RCC work
20345 SH : RCC work
21123 SH : Road work
7531 SH : Water Supply)
7554 SH
SH ::dismantling
Water Supply) and
20140 dimolishing
SH :dismantling and
20161 dimolishing
SH :dismantling and
20226 dimolishing
SH :dismantling and
19945 dimolishing
SH :dismantlingDismantling
and
20022 dimolishing Dismantling
20306 SH: DRAINAGE
21118 SH: Earth work)
4828 SH: Water Supply)
4863 SH: Water Supply)
7587 SH:Water Supply)
21782 shifting at site.
21820 shifting at site.
21860 shifting at site.
21891 shifting at site.
21930 shifting at site.
21968 shifting at site.
22006 shifting at site.
22044 shifting at site.
22312 shifting at site.
22351 shifting at site.
22388 shifting at site.
22420 shifting at site.
22459 shifting at site.
22505 shifting at site.
22548 shifting at site.
22589 shifting at site.
22629 shifting at site.
22671 shifting at site.
22699 shifting at site.
22732 shifting at site.
22767 shifting
15 to 20atmm site.
inlet 100
3459 1878 mm
15 to 20 mm inlet 150 each 1 100
3487 1879 mm
Sides : 2x0.20x0.10 m = each 1 125
20595 0.04
Sin Qsqm
= (2x145)/590 =
16253 0.49154
Sin Q = (2x62)/424 =
16109 0.292
Single therefor Q
matting 2.5x2.5 m=
21071 9999 6.25 sqm Precast L.S. 112.14 2
23185 20.7.2 Single
and uptopile100 tonne Safe
23090 20.6.2 capacity
Single pile above 50 tonne
23113 capacity
Single pilepile and upto
above 100
50 tonne
23206 capacity pile and upto 100
Single pile upto 50 tonne
23070 capacity
Single pile upto 50 tonne
23191 capacity
Single pile upto 50 tonne
23043 20.6.1 Safe capacity
18174 19.8.2 Size 120x90
size 18 cm with 100
mm high
7496 mm dia. cm in 34 cm
Size 30x30
10310 wall
18128 19.8.1 Size 90x80 cm
19485 size)
19934 size)
20481 size)
size) 3.05x0.23x0.15 =
20782 0.105 cum
size)2.82x0.23x0.15 m=
20542 0.097 cum Say 0.10
Slab bottom 0.50x0.65 mcum
20705 =15.88
0.325mmsqm
outer dia SS
12625 pipe mm outer dia SS
8806 22.22 each 1 47
12649 8807 pipe
28.58 mm outer dia SS each 1 63
12665 8808 pipe
34.00 mm outer dia SS each 1 89
12681 8809 pipe
42.70 mm outer dia SS each 1 131
12707 8810 pipe
48.60 mm outer dia SS each 1 158
12723 8811 pipe each 1 170
4035 1881 Spun yarn kilogram 1.7 50
4061 1881 Spun yarn kilogram 2 50
4096 1881 Spun yarn kilogram 2.3 50
4122 1881 Spun yarn kilogram 3 50
4157 1881 Spun yarn kilogram 4 50
4193 1881 Spun yarn kilogram 5.4 50
4219 1881 Spun yarn kilogram 6.2 50
4256 1881 Spun yarn kilogram 7.4 50
4291 1881 Spun yarn kilogram 7.9 50
4317 1881 Spun yarn kilogram 8.5 50
4352 1881 Spun yarn kilogram 10.2 50
15798 Spun yarn kilogram 4.5 50
15884 Spun yarn kilogram 12 50
15919 Spun yarn kilogram 15 50
21166 Spun yarn kilogram 0.09 50
21204 Spun
Spun yarn
yarn or plain gaskin kilogram 0.18 50
15843 @ 0.18 kg per
Spun yarn jointgaskin
or plain = kilogram 9 50
15965 1881 @ 0.36sqm
0.148 kg /For
joint
10 m kilogram 18 50
16009 length
0.211 sqm For 10 m
16060 length
16114 sqmm
16116 sqmm
16209 sqmm
16211 sqmm
16263 sqmm
Square shape 450 mm
19236 19.19.1.2 internal dimensions
Square shape 450x450
19239 7131 mm precast R.C.C. each 1 575
13130 SS
Elbow 90O for 15.88 mm
15023 8917 outer each 1 150
13156 SS pipe
13173 SS pipe
13199 SS pipe
13216 SS pipe
13244 SS pipe
13261 SS pipe
13278 SS pipe
13306 SS pipe
13323 SS pipe
13350 SS pipe
13367 SS pipe
13394 SS
SS pipe
pipe 304 grades with
12049 8701 press fit304
SS pipe technology as per metre
grades with 10 610
11877 8779 press fit304
SS pipe technology as per metre
grades with 10 130
12090 press
8779 SS fit304
pipe technology as per metre
grades with 10 130
11916 8780 press fit technology
SS pipe 304 grades with as per metre 10 243
12130 8780 press fit304
SS pipe technology as per metre
grades with 10 243
11943 8781 press fit304
SS pipe technology as per metre
grades with 10 297
11981 8782 SS
press fit304
pipe technology as per metre
grades with 10 423
12020 8783 press fit technology
Stainless steel Cap for as per metre 10 441
15589 8936 15.88 mmsteel
Stainless outer diafor
Cap pipe each 1 45
15603 8937 22.22 mmsteel
Stainless outer diafor
Cap pipe each 1 64
15628 8938 Stainless
28.58 mmsteelouter pipe each
diafor
Cap 1 84
15642 8939 34.00 mm outer dia
Stainless steel Cap for pipe each 1 163
15656 8940 42.70 mmsteel
Stainless outer pipe each
diafor
Cap 1 236
15680 8941 48.60 mmsteel
Stainless outer dia pipe each
Female 1 299
13914 8866 Stainless
thread Tee 15.88 mm each
for Female
steel 1 179
13931 8867 thread Tee for 22.22 mm each
Stainless steel Female 1 200
13948 8868 thread Tee
Stainless 22.22 mm each
for Female
steel 1 200
13974 8869 thread Tee
Stainless for Female
steel 28.58 mm each 1 273
13991 thread Tee for 28.58 mm each
8870 Stainless steel Female 1 273
14016 8871 thread Tee
Stainless for Female
steel 28.58 mm each 1 273
14033 8872 thread Tee
Stainless for Female
steel 34.00 mm each 1 437
14050 8873 thread Tee
Stainless for Female
steel 34.00 mm each 1 437
14077 thread Tee for 34.00 mm each
8874 Stainless steel Female 1 437
14094 8875 thread Tee
Stainless for Female
steel 34.00 mm each 1 437
14121 8876 thread Tee
Stainless for Female
steel 42.70 mm each 1 683
14138 8877 thread Tee
Stainless for Female
steel 42.70 mm each 1 683
14155 8878 Stainless
thread Tee for Female
steel 42.70 mm each 1 683
14182 8879 thread Tee for 42.70 mm each
Stainless steel Female 1 683
14199 8880 thread Tee
Stainless for Female
steel 42.70 mm each 1 683
14227 8881 thread Tee for 48.60 mm each 1 887
Stainless steel Female
14246 8882 thread Tee
Stainless for Female
steel 48.60 mm each 1 887
14273 8883 thread Tee
Stainless for Female
steel 48.60 mm each 1 887
14290 8884 thread Tee for 48.60 mm
Stainless steel Female each 1 887
14307 8885 thread Tee
Stainless for Female
steel 48.60 mm each 1 887
14334 8886 thread Tee for 48.60 mm
threaded each 1 887
14355 8887 Connector/Adapter
threaded each 1 190
14382 8888 Connector/Adapter
threaded each 1 230
14401 8889 Connector/Adapter
threaded each 1 237
14428 8890 Connector/Adapter
threaded each 1 277
14447 8891 Connector/Adapter
threaded each 1 286
14465 8892 Connector/Adapter
threaded each 1 337
14511 8894 Connector/Adapter
threaded each 1 538
14605 8898 Connector/Adapter
Connector/Adapter each 1 965
14493 8893 each
Connector/Adapter 1 409 409
14540 8895 each
Connector/Adapter 1 576 576
14558 8896 each
Connector/Adapter 1 681 681
14587 8897 each
Threaded Elbow 90O for 1 838 838
15049 8918 22.22
Threaded Elbow 90O for each 1 191
15064 8919 22.22
Threaded Elbow 90O for each 1 191
15090 8920 25.58
Threadedeach
Elbow 90O for 1 205 205
15107 8921 34.00 each
Threaded Elbow 90O for 1 287 287
15135 8922 42.70
Threaded Elbow 90O for each 1 478
15152 8923 42.70
Threadedeach
Elbow 90O for 1 478 478
15169 8924 48.60 each
Threaded Elbow 90O for 1 683 683
15197 8925 48.60 eachfor 15.88 mm
thread Tee 1 683 683
13459 8845 outer
thread Tee for 22.22 mm each 1 179
13476 8846 outer
thread Tee for 22.22 mm each 1 200
13503 8847 outer
thread Tee for 28.58 mm each 1 205
13520 8848 outer
thread Tee for 28.58 mm each 1 273
13537 8849 outer
thread Tee for 28.58 mm each 1 273
13563 8850 outer
thread Tee for 34.00 mm each 1 273
13580 8851 outer
thread Tee for 34.00 mm each 1 437
13607 8852 outer
thread Tee for 34.00 mm each 1 437
13624 8853 outer
thread Tee for 34.00 mm each 1 437
13653 8854 outer
thread Tee for 42.70 mm each 1 437
13670 8855 outer
thread Tee for 42.70 mm each 1 683
13687 8856 outer
thread Tee for 42.70 mm each 1 683
13715 8857 outer
thread Tee for 42.70 mm each 1 683
13732 8858 outer
thread Tee for 42.70 mm each 1 683
13759 8859 outer
thread Tee for 48.60 mm each 1 683
13776 8860 outer
thread Tee for 48.60 mm each 1 887
13793 8861 outer
thread Tee for 48.60 mm each 1 887
13820 8862 outer
thread Tee for 48.60 mm each 1 887
13837 8863 outer
thread Tee for 48.60 mm each 1 887
13865 8864 outer each 1 887
thread Tee for 48.60 mm
13882 8865 outer
threaded Connector/ each 1 887
14653 8900 Adapter
threaded Connector/ each 1 227
14697 8902 Adapter
threaded Connector/ each 1 313
14715 8903 Adapter
threaded Connector/ each 1 320
14787 8906 Adapter
threadedfor Connector/ each 1 649
14636 8899 Adapter
threadedfor each
Connector/ 1 193 193
14671 8901 Adapter for each
threaded Connector/ 1 248 248
14744 8904 Adapter
threadedfor each
Connector/ 1 461 461
14761 8905 Adapter
threadedfor each
Connector/ 1 565 565
14804 8907 Adapter
threadedfor each
Connector/ 1 726 726
14821 8908 Adapter for each
threaded Connector/ 1 840 840
14848 8909 Adapter
Stainlessforsteeleach
Pipe Bridge 1 1138 1138
15699 8942 for 15.88 mm outer dia each
Stainless steel Pipe Bridge 1 214
15727 for 15.88 steel
8943 Stainless mm outer dia each
Pipe Bridge 1 271
15742 8944 for
Connector for 15.88 dia
28.58 mm outer mm each 1 407
14869 8910 outer
Connector for 22.22 mm each 1 234
14896 8911 outer
Connector for 22.22 mm each 1 276
14913 8912 outer
Connector for 28.58 mm each 1 295
14941 8913 outer
Connector for 34.00 mm each 1 424
14958 8914 outer
Connector for 42.70 mm each 1 629
14975 8915 outer
Connector for 48.60 mm each 1 875
15002 8916 outer
Steel reinforcement for each 1 1176
18088 slab
Steel@reinforcement
80.09 Kg/cumfor
17989 slab @ 80.09 Kg/cum =For
3.14/4x(0.30)²x9.625
22495 0.680 cum
Stem -3.14/4x(0.40)²x9.30
22538 = 1.169 cum
3.14/4x(0.45)²x9.212 =
22579 1.465 cum
3.14/4x(0.50)²x9.125 =
22619 1.792 cum
stone aggregate 20 mm
18254 nominal size )
stone aggregate 20 mm
18505 nominal
stone size ) 20 mm
aggregate
18738 nominal size ) 20 mm
stone aggregate
18747 nominal size) 20 mm
stone aggregate
20920 nominal size) 40 mm
stone aggregate
19780 nominal size) 40 mm
stone aggregate
19826 nominal
Stoneware size)
pipes grade A
15786 1854 (60 cm long)
Stoneware pipes grade A each 55 55
21066 1854 (60 cm long)pipes grade A each
Stoneware 3 55
15831 (60 cm long)pipes grade A each
1855 Stoneware 55 100
15864 1856 (60 cm long)pipes grade A each
Stoneware 55 200
15953 1859 (60 cm long)pipes grade A each
Stoneware 55 478
21126 (60 cm long)pipes
Stoneware 100 grade
mm dia A each 2 55
15908 1858 Strainer
(60 cm long)
brass250 40 mm
mm dia
dia each 55 320
6427 1882 1.5
Sub analysis item for sand each
metre long 1 600
6096 18. 41.1A filling component
Sub analysis item for sand
6097 filling component
suitabe for mechanical
8092 joint as per
suitable for IS 13382 over
mechanical
8072 joint as per
suitable locking
6920 9977 arrangement
suitable locking
6942 9977 arrangement
Sundreis including hamp
6432 9999 white lead etc. L.S. 7.15 2
3520 9999 Sundries L.S. 16.12 2
3541 9999 Sundries L.S. 40.17 2
4039 9999 Sundries L.S. 6.76 2
4065 9999 Sundries L.S. 9.49 2
4100 9999 Sundries L.S. 10.79 2
4126 9999 Sundries L.S. 13.52 2
4161 9999 Sundries L.S. 17.55 2
4197 9999 Sundries L.S. 20.28 2
4223 9999 Sundries L.S. 24.18 2
4260 9999 Sundries L.S. 26.91 2
4295 9999 Sundries L.S. 31.07 2
4321 9999 Sundries L.S. 33.67 2
4356 9999 Sundries L.S. 40.3 2
5197 9999 Sundries L.S. 4.16 2
5269 9999 Sundries L.S. 8.06 2
5339 9999 Sundries L.S. 8.06 2
5422 9999 Sundries L.S. 8.06 2
5492 9999 Sundries L.S. 8.06 2
5574 9999 Sundries L.S. 8.06 2
6344 9999 Sundries L.S. 13.52 2
6376 9999 Sundries L.S. 13.52 2
6401 9999 Sundries L.S. 13.52 2
6468 9999 Sundries L.S. 7.25 2
6490 9999 Sundries L.S. 4.42 2
7086 9999 Sundries L.S. 2.89 2
10329 9999 Sundries L.S. 8.06 2
10375 9999 Sundries L.S. 21.58 2
11588 9999 Sundries L.S. 1.82 2
11616 9999 Sundries L.S. 2.73 2
11634 9999 Sundries L.S. 4.42 2
11659 9999 Sundries L.S. 5.33 2
11677 9999 Sundries L.S. 7.15 2
11695 9999 Sundries L.S. 8.06 2
11723 9999 Sundries L.S. 9.88 2
11741 9999 Sundries L.S. 10.79 2
11769 9999 Sundries L.S. 12.48 2
11787 9999 Sundries L.S. 13.52 2
11803 9999 Sundries L.S. 15.21 2
11830 9999 Sundries L.S. 16.12 2
17524 9999 Sundries L.S. 13.52 2
17754 9999 Sundries L.S. 16.64 2
17913 9999 Sundries L.S. 16.64 2
18004 9999 Sundries L.S. 20.28 2
18103 9999 Sundries L.S. 20.28 2
18300 9999 Sundries L.S. 16.9 2
18398 9999 Sundries L.S. 16.9 2
18540 9999 Sundries L.S. 16.9 2
18642 9999 Sundries L.S. 16.9 2
18779 9999 Sundries L.S. 16.9 2
18864 9999 Sundries L.S. 16.9 2
19224 9999 Sundries L.S. 13.52 2
19250 9999 Sundries L.S. 13.52 2
19286 9999 Sundries L.S. 13.52 2
19327 9999 Sundries L.S. 16.64 2
19352 9999 Sundries L.S. 16.64 2
19391 9999 Sundries L.S. 20.28 2
19430 9999 Sundries L.S. 20.28 2
19800 9999 Sundries L.S. 7.15 2
19839 9999 Sundries L.S. 8.09 2
20401 9999 Sundries L.S. 16.64 2
20450 9999 Sundries L.S. 20.28 2
20497 9999 Sundries L.S. 20.28 2
20801 9999 Sundries L.S. 13.52 2
20872 9999 Sundries L.S. 13.52 2
20945 9999 Sundries L.S. 13.52 2
21127 9999 Sundries L.S. 25.84 2
21140 9999 Sundries L.S. 13.52 2
21775 9999 Sundries L.S. 521.08 2
21813 9999 Sundries L.S. 392.7 2
21844 9999 Sundries L.S. 530 2
21884 9999 Sundries L.S. 371.88 2
21923 9999 Sundries L.S. 573.57 2
21961 9999 Sundries L.S. 897.89 2
21999 9999 Sundries L.S. 733.37 2
22030 9999 Sundries L.S. 1113.48 2
22076 9999 Sundries L.S. 230.69 2
22115 9999 Sundries L.S. 87.95 2
22156 9999 Sundries L.S. 317.43 2
22196 9999 Sundries L.S. 131.58 2
22308 9999 Sundries L.S. 317.43 2
22347 9999 Sundries L.S. 131.58 2
22377 9999 Sundries L.S. 175.89 2
22416 9999 Sundries L.S. 290.79 2
22455 9999 Sundries L.S. 593.48 2
22501 9999 Sundries L.S. 410.92 2
22544 9999 Sundries L.S. 276.82 2
22585 9999 Sundries L.S. 194.81 2
22625 9999 Sundries L.S. 208.15 2
22810 9999 Sundries L.S. 442 2
20351 Sundries L.S. 13.52
11147 9988 Sundries and carriage L.S. 53.82 2
11188 9988 Sundries and carriage L.S. 53.82 2
11228 9988 Sundries and carriage L.S. 53.82 2
11259 9988 Sundries and carriage L.S. 67.21 2
11301 9988 Sundries and carriage L.S. 67.21 2
11341 9988 Sundries and carriage L.S. 80.73 2
11370 9988 Sundries and carriage L.S. 94.12 2
11412 9988 Sundries and carriage L.S. 107.64 2
11453 9988 Sundries and carriage L.S. 121.03 2
11494 9988 Sundries and carriage L.S. 134.55 2
11525 9988 Sundries and carriage L.S. 147.94 2
11566 9988 Sundries
Sundries and carriage
including L.S. 174.85 2
19748 carriage including
9988 Sundries of bends etc. L.S. 34.06 2
19664 9988 carriage of bends etc.
Sundries including testing L.S. 26.91 2
10472 9999 of samples
Sundries including testing L.S. 9.88 2
10495 9999 of samples
Sundries including testing L.S. 13.52 2
10529 9999 Sundries
of samples
including testing L.S. 17.94 2
10559 9999 of samples
Sundries including testing L.S. 22.88 2
10582 9999 of samples
Sundries including testing L.S. 31.46 2
10614 9999 of samples
Sundries including testing L.S. 40.3 2
10647 9999 Sundries
of samples
including testing L.S. 44.46 2
10670 9999 of samples
Sundries including testing L.S. 48.36 2
10707 9999 of samples
Sundries including testing L.S. 53.82 2
10730 9999 of samples
Sundries including testing L.S. 58.24 2
10762 9999 Sundries
of samples
including testing L.S. 63.7 2
10785 9999 of samples
Sundries including testing L.S. 71.37 2
10816 9999 of samples
Sundries including testing L.S. 4.42 2
10850 9999 of samples
Sundries including testing L.S. 4.42 2
10870 9999 of samples
Sundries including testing L.S. 5.46 2
10903 9999 of samples
Sundries including testing L.S. 7.15 2
10923 9999 of samples
Sundries including testing L.S. 9.88 2
10956 9999 of samples
Sundries including testing L.S. 10.79 2
10976 9999 of samples
Sundries including testing L.S. 13.52 2
11009 9999 of samples
Sundries including testing L.S. 16.12 2
11029 9999 of samples
Sundries including testing L.S. 17.94 2
11062 9999 of samples
Sundries including testing L.S. 20.67 2
11082 9999 Sundries
of samples
including testing L.S. 23.27 2
11115 9999 of samples L.S. 26 2
2352 Supply
6081 supply
6128 supply
6158 supply
6178 supply
6210 supply
6230 supply
6259 supply
6279 supply
6297 supply
2348 Supply)
4766 Supply)
4798 Supply)
4802 Supply)
4901 Supply)
4926 Supply)
4960 Supply)
4964 Supply)
4995 Supply)
4999 Supply)
5022 Supply)
5026 Supply)
5061 Supply)
5098 Supply)
5123 Supply))
the weight of cover to be
19444 19.2 not
coverless than 4.5
without kg for
frame
19118 19.18 manholes : lead at site
Supplying pig
4374 18.29 Surface
of work.box for sluice
5248 1305 valve
Surface box for sluice each 1 210
5319 valve
Surface box for sluice each 1 210
5391 valve
Surface box for sluice each 1 210
5472 valve each 1 210
5172 1304 Surface box for stop
Surface box for water cock each 1 125
5545 1307 meter
surface box with chained each 1 250
5390 1305 lid
surface box with chained
5471 1305 lid
surface box with chained
5318 1305 lid.
surplus earth
21116 2.8.1 1.2x1.2x1.2m
3.14/4x(2.5)²x3m = 1.73 cum
= 14.73
21044 2.8.1 cum
Take 25mm dia as an
2653 average
Take 65mm size.dia as an
2684 average size.
23305 44 Technician
complete, including day 0.1 374.5
22296 removal
setting outofand removal of
22294 samecap
test andand dismantling
23051 of
test capcap
test andafter test etc.
dismantling
23096 of
testtest
capcap
andafter test etc.
dismantling
23142 of test cap after test etc.
7618 9999 Testing charges L.S. 130 2
7641 9999 Testing charges L.S. 130 2
7674 9999 Testing charges L.S. 156 2
7697 9999 Testing charges L.S. 156 2
16056 than 1200
cap etc. bymmCrawler
22295 mounted,
16254 therefor
thick wallQand
= 29°26'
making
19497 23 channel etc.)
thick wall and making
19544 23 channel
thick walletc.)
and making
19588 channel etc.)
14357 threaded
14384 threaded
14403 threaded
14430 threaded
14449 threaded
14467 threaded
14495 threaded
14513 threaded
14542 threaded
14560 threaded
14589 threaded
14607 threaded
14655 threaded
14699 threaded
14717 threaded
23098 to 100 tonne
23114 tonne capacity pile
23207 tonne capacity pile
19646 Toothing portion
19721 Toothing portion
19784 Toothing portion
19830 Toothing portionm = 0.09
Top : 0.45x0.20
20594 sqm
24 TOTAL
26 TOTAL
28 TOTAL
30 Total
58 TOTAL
60 TOTAL
62 TOTAL
64 Total
82 TOTAL
84 TOTAL
86 TOTAL
99 Total 2876.3
117 TOTAL
119 TOTAL
121 TOTAL
123 Total
154 TOTAL
156 TOTAL
158 TOTAL
160 Total
178 TOTAL
180 TOTAL
182 TOTAL
184 Total
218 TOTAL
220 TOTAL
222 TOTAL
224 Total
253 TOTAL
255 TOTAL
257 TOTAL
259 Total
277 TOTAL
289 TOTAL 3543.44
291 TOTAL 3904.02
293 Total 4343.07
313 TOTAL
315 TOTAL
317 TOTAL
319 Total
360 TOTAL
362 TOTAL
364 TOTAL
366 Total
394 TOTAL
396 TOTAL
398 TOTAL
400 Total
419 TOTAL
421 TOTAL
423 TOTAL
425 Total
454 TOTAL
456 TOTAL
458 TOTAL
460 Total
489 TOTAL
491 TOTAL
493 TOTAL
495 Total
514 TOTAL
516 TOTAL
518 TOTAL
520 Total
549 TOTAL
551 TOTAL
553 TOTAL
555 Total
572 TOTAL
574 TOTAL
585 TOTAL
587 Total
605 TOTAL
607 TOTAL
609 TOTAL
611 Total
640 TOTAL
642 TOTAL
644 TOTAL
646 Total
664 TOTAL
666 TOTAL
668 TOTAL
670 Total
705 TOTAL
707 TOTAL
709 TOTAL
711 Total
739 TOTAL
741 TOTAL
743 TOTAL
745 Total
764 TOTAL
766 TOTAL
768 TOTAL
770 Total
806 TOTAL
808 TOTAL
810 TOTAL
812 Total
844 TOTAL
846 TOTAL
848 TOTAL
850 Total
872 TOTAL
874 TOTAL
876 TOTAL
889 Total 2451.29
911 TOTAL
913 TOTAL
915 TOTAL
917 Total
949 TOTAL
951 TOTAL
953 TOTAL
955 Total
977 TOTAL
979 TOTAL
981 TOTAL
983 Total
1010 TOTAL
1012 TOTAL
1014 TOTAL
1016 Total
1039 TOTAL
1051 TOTAL 8253.94
1053 TOTAL 9413.61
1055 Total 10825.66
1078 TOTAL
1080 TOTAL
1082 TOTAL
1084 Total
1333 TOTAL
1335 TOTAL
1337 TOTAL
1339 Total
1400 TOTAL
1402 TOTAL
1404 TOTAL
1406 Total
1418 TOTAL
1420 TOTAL
1422 TOTAL
1424 Total
1455 TOTAL
1457 TOTAL
1459 TOTAL
1461 Total
1482 TOTAL
1493 TOTAL 1770.22
1495 TOTAL 2018.94
1497 Total 2321.78
1516 TOTAL
1518 TOTAL
1520 TOTAL
1522 Total
1551 TOTAL
1553 TOTAL
1555 TOTAL
1557 Total
1576 TOTAL
1578 TOTAL
1580 TOTAL
1582 Total
1611 TOTAL
1613 TOTAL
1615 TOTAL
1617 Total
1652 TOTAL
1654 TOTAL
1656 TOTAL
1658 Total
1679 TOTAL
1681 TOTAL
1683 TOTAL
1695 Total
1716 TOTAL
1718 TOTAL
1720 TOTAL
1722 Total
1753 TOTAL
1755 TOTAL
1757 TOTAL
1759 Total
1784 TOTAL
1786 TOTAL
1799 TOTAL 1317.85
1801 Total 1515.52
1821 TOTAL
1823 TOTAL
1825 TOTAL
1827 Total
1855 TOTAL
1857 TOTAL
1859 TOTAL
1861 Total
1881 TOTAL
1883 TOTAL
1885 TOTAL
1887 Total
1918 TOTAL
1920 TOTAL
1922 TOTAL
1924 Total
1944 TOTAL
1955 TOTAL 5538.62
1957 TOTAL 6316.79
1959 Total 7264.31
1979 TOTAL
1981 TOTAL
1983 TOTAL
1985 Total
2016 TOTAL
2018 TOTAL
2020 TOTAL
2022 Total
2042 TOTAL
2054 TOTAL 20269.09
2056 TOTAL 23116.89
2058 Total 26584.43
2078 TOTAL
2080 TOTAL
2082 TOTAL
2084 Total
2120 TOTAL
2122 TOTAL
2124 TOTAL
2126 Total
2146 TOTAL
2148 TOTAL
2160 TOTAL 2395.07
2162 Total 2754.33
2183 TOTAL
2185 TOTAL
2187 TOTAL
2189 Total
2218 TOTAL
2220 TOTAL
2222 TOTAL
2224 Total
2245 TOTAL
2247 TOTAL
2249 TOTAL
2251 Total
2282 TOTAL
2284 TOTAL
2286 TOTAL
2288 Total
2323 TOTAL
2325 TOTAL
2327 TOTAL
2329 Total
2367 TOTAL
2369 TOTAL
2371 TOTAL
2373 Total
2398 TOTAL
2400 TOTAL
2402 TOTAL
2414 Total 1924.71
2435 TOTAL
2437 TOTAL
2439 TOTAL
2441 Total
2472 TOTAL
2474 TOTAL
2476 TOTAL
2478 Total
2500 TOTAL
2502 TOTAL
2504 TOTAL
2506 Total
2535 TOTAL
2537 TOTAL
2539 TOTAL
2541 Total
2571 TOTAL
2573 TOTAL
2575 TOTAL
2577 Total
2599 TOTAL
2601 TOTAL
2603 TOTAL
2605 Total
2636 TOTAL
2638 TOTAL
2640 TOTAL
2642 Total
2661 TOTAL
2672 TOTAL 342
2674 TOTAL 390.05
2676 Total 448.56
2692 TOTAL
2694 TOTAL
2696 TOTAL
2698 Total
2721 TOTAL
2723 TOTAL
2725 TOTAL
2727 Total
2740 TOTAL
2742 TOTAL
2744 TOTAL
2746 Total
2757 TOTAL
2759 TOTAL
2771 TOTAL 281.04
2773 Total 323.2
2786 TOTAL
2788 TOTAL
2790 TOTAL
2792 Total
2803 TOTAL
2805 TOTAL
2807 TOTAL
2809 Total
2833 TOTAL
2835 TOTAL
2837 TOTAL
2839 Total
2848 TOTAL
2850 TOTAL
2852 TOTAL
2854 Total
2866 TOTAL
2879 TOTAL 438.78
2881 TOTAL 500.43
2883 Total 575.5
2895 TOTAL
2897 TOTAL
2899 TOTAL
2901 Total
2913 TOTAL
2915 TOTAL
2917 TOTAL
2919 Total
2941 TOTAL
2943 TOTAL
2945 TOTAL
2947 Total
2959 TOTAL
2961 TOTAL
2963 TOTAL
2965 Total
2989 TOTAL 253.16
2991 TOTAL 255.69
2993 TOTAL 291.62
2995 Total 335.36
3007 TOTAL
3009 TOTAL
3011 TOTAL
3013 Total
3025 TOTAL
3027 TOTAL
3029 TOTAL
3031 Total
3055 TOTAL
3057 TOTAL
3059 TOTAL
3061 Total
3071 TOTAL
3073 TOTAL
3075 TOTAL
3077 Total
3099 TOTAL
3101 TOTAL
3103 TOTAL
3105 Total
3115 TOTAL
3117 TOTAL
3119 TOTAL
3121 Total
3143 TOTAL
3145 TOTAL
3147 TOTAL
3149 Total
3159 TOTAL
3161 TOTAL
3163 TOTAL
3165 Total
3185 TOTAL
3187 TOTAL
3189 TOTAL
3191 Total
3201 TOTAL
3203 TOTAL
3205 TOTAL
3207 Total
3218 TOTAL
3220 TOTAL
3231 TOTAL
3233 Total
3243 TOTAL
3245 TOTAL
3247 TOTAL
3249 Total
3263 TOTAL
3265 TOTAL
3267 TOTAL
3278 Total
3288 TOTAL
3290 TOTAL
3292 TOTAL
3294 Total
3307 TOTAL
3309 TOTAL
3311 TOTAL
3313 Total
3333 TOTAL
3335 TOTAL
3337 TOTAL
3339 Total
3350 TOTAL
3352 TOTAL
3354 TOTAL
3356 Total
3380 TOTAL
3382 TOTAL
3384 TOTAL
3386 Total
3396 TOTAL
3398 TOTAL
3400 TOTAL
3402 Total
3426 TOTAL
3428 TOTAL
3430 TOTAL
3432 Total
3442 TOTAL
3444 TOTAL
3446 TOTAL
3448 Total
3472 TOTAL 113.52
3474 TOTAL 114.66
3476 TOTAL 130.76
3478 Total 150.38
3490 TOTAL
3492 TOTAL
3494 TOTAL
3496 Total
3521 TOTAL
3523 TOTAL
3525 TOTAL
3527 Total
3542 TOTAL
3544 TOTAL
3546 TOTAL
3548 Total
3576 TOTAL
3578 TOTAL
3580 TOTAL
3582 Total
3597 TOTAL
3599 TOTAL
3601 TOTAL
3603 Total
3632 TOTAL
3634 TOTAL
3636 TOTAL
3638 Total
3653 TOTAL
3655 TOTAL
3657 TOTAL
3659 Total
3689 TOTAL
3691 TOTAL
3693 TOTAL
3695 Total
3714 TOTAL
3726 TOTAL 11213.31
3728 TOTAL 12731.83
3730 Total 14580.81
3749 TOTAL
3751 TOTAL
3753 TOTAL
3755 Total
3785 TOTAL
3787 TOTAL
3789 TOTAL
3791 Total
3810 TOTAL
3812 TOTAL
3814 TOTAL
3826 Total
3846 TOTAL
3848 TOTAL
3850 TOTAL
3852 Total
3882 TOTAL
3884 TOTAL
3886 TOTAL
3888 Total
3908 TOTAL
3910 TOTAL
3912 TOTAL
3914 Total
3946 TOTAL
3948 TOTAL
3950 TOTAL
3952 Total
3972 TOTAL
3984 TOTAL 89609.67
3986 TOTAL 101808.93
3988 Total 116662.93
4009 TOTAL
4011 TOTAL
4013 TOTAL
4015 Total
4045 TOTAL
4047 TOTAL
4049 TOTAL
4051 Total
4071 TOTAL
4073 TOTAL
4075 TOTAL
4086 Total
4106 TOTAL
4108 TOTAL
4110 TOTAL
4112 Total
4141 TOTAL
4143 TOTAL
4145 TOTAL
4147 Total
4167 TOTAL
4169 TOTAL
4171 TOTAL
4183 Total 5805.59
4203 TOTAL
4205 TOTAL
4207 TOTAL
4209 Total
4240 TOTAL
4242 TOTAL
4244 TOTAL
4246 Total
4266 TOTAL
4268 TOTAL
4270 TOTAL
4272 Total
4301 TOTAL
4303 TOTAL
4305 TOTAL
4307 Total
4336 TOTAL
4338 TOTAL
4340 TOTAL
4342 Total
4362 TOTAL
4364 TOTAL
4366 TOTAL
4368 Total
4389 TOTAL
4391 TOTAL
4393 TOTAL
4395 Total
4413 TOTAL
4415 TOTAL
4417 TOTAL
4419 Total
4445 TOTAL
4447 TOTAL
4449 TOTAL
4451 Total
4468 TOTAL
4470 TOTAL
4472 TOTAL
4474 Total
4501 TOTAL
4503 TOTAL
4505 TOTAL
4507 Total
4524 TOTAL
4526 TOTAL
4528 TOTAL
4540 Total
4557 TOTAL
4559 TOTAL
4561 TOTAL
4563 Total
4580 TOTAL
4593 TOTAL 3169.32
4595 TOTAL 3614.61
4597 Total 4156.8
4614 TOTAL
4616 TOTAL
4618 TOTAL
4620 Total
4647 TOTAL
4649 TOTAL
4651 TOTAL
4653 Total
4670 TOTAL
4672 TOTAL
4674 TOTAL
4676 Total
4703 TOTAL
4705 TOTAL
4707 TOTAL
4709 Total
4726 TOTAL
4728 TOTAL
4730 TOTAL
4732 Total
4767 TOTAL
4769 TOTAL
4771 TOTAL
4773 Total
4803 TOTAL
4805 TOTAL
4807 TOTAL
4809 Total
4829 TOTAL
4831 TOTAL
4833 TOTAL
4835 Total
4864 TOTAL
4866 TOTAL
4868 TOTAL
4870 Total
4902 TOTAL
4904 TOTAL
4906 TOTAL
4908 Total
4927 TOTAL
4929 TOTAL
4931 TOTAL
4933 Total
4965 TOTAL
4967 TOTAL
4969 TOTAL
4971 Total
5000 TOTAL
5002 TOTAL
5004 TOTAL
5006 Total
5027 TOTAL
5029 TOTAL
5031 TOTAL
5033 Total
5062 TOTAL
5064 TOTAL
5066 TOTAL
5068 Total
5099 TOTAL
5101 TOTAL
5103 TOTAL
5105 Total
5124 TOTAL
5126 TOTAL
5128 TOTAL
5130 Total
5198 TOTAL
5200 TOTAL
5202 TOTAL
5204 Total
5270 TOTAL
5272 TOTAL
5274 TOTAL
5276 Total
5340 TOTAL
5342 TOTAL
5344 TOTAL
5356 Total 13211.42
5423 TOTAL
5425 TOTAL
5427 TOTAL
5429 Total
5493 TOTAL
5495 TOTAL
5497 TOTAL
5499 Total
5575 TOTAL
5577 TOTAL
5579 TOTAL
5581 Total
5597 TOTAL
5599 TOTAL
5601 TOTAL
5603 Total
5629 TOTAL
5631 TOTAL
5633 TOTAL
5635 Total
5651 TOTAL
5653 TOTAL
5655 TOTAL
5657 Total
5683 TOTAL
5685 TOTAL
5687 TOTAL
5689 Total
5703 TOTAL
5705 TOTAL
5707 TOTAL
5709 Total
5733 TOTAL
5735 TOTAL
5737 TOTAL
5739 Total
5754 TOTAL
5756 TOTAL
5758 TOTAL
5760 Total
5782 TOTAL
5784 TOTAL
5786 TOTAL
5788 Total
5801 TOTAL
5803 TOTAL
5805 TOTAL
5807 Total
5820 TOTAL
5832 TOTAL 93.89
5834 TOTAL 96.99
5836 Total 100.76
5849 TOTAL
5851 TOTAL
5853 TOTAL
5855 Total
5868 TOTAL
5870 TOTAL
5872 TOTAL
5884 Total
5898 TOTAL
5900 TOTAL
5902 TOTAL
5904 Total
5916 TOTAL
5918 TOTAL
5920 TOTAL
5922 Total
5944 TOTAL
5946 TOTAL
5948 TOTAL
5950 Total
5962 TOTAL
5964 TOTAL
5966 TOTAL
5968 Total
5989 TOTAL 126.13
5991 TOTAL 126.38
5993 TOTAL 129.84
5995 Total 134.07
6007 TOTAL
6009 TOTAL
6011 TOTAL
6013 Total
6025 TOTAL
6027 TOTAL
6029 TOTAL
6042 Total
6054 TOTAL
6056 TOTAL
6058 TOTAL
6060 Total
6082 TOTAL
6103 TOTAL
6105 TOTAL
6107 TOTAL
6109 Total
6260 TOTAL
6280 TOTAL
6298 TOTAL
6345 TOTAL
6347 TOTAL
6349 TOTAL
6351 Total
6377 TOTAL
6379 TOTAL
6381 TOTAL
6383 Total
6402 TOTAL
6404 TOTAL
6406 TOTAL
6417 Total 3007.13
6433 TOTAL
6435 TOTAL
6437 TOTAL
6439 Total
6469 TOTAL
6471 TOTAL
6473 TOTAL
6475 Total
6491 TOTAL
6493 TOTAL
6495 TOTAL
6497 Total
6523 TOTAL
6525 TOTAL
6527 TOTAL
6529 Total
6543 TOTAL
6545 TOTAL
6547 TOTAL
6549 Total
6572 TOTAL
6574 TOTAL
6576 TOTAL
6578 Total
6592 TOTAL
6594 TOTAL
6596 TOTAL
6598 Total
6621 TOTAL
6623 TOTAL
6625 TOTAL
6627 Total
6641 TOTAL
6643 TOTAL
6645 TOTAL
6647 Total
6670 TOTAL 627.16
6672 TOTAL 633.44
6674 TOTAL 722.43
6676 Total 830.8
6690 TOTAL
6692 TOTAL
6694 TOTAL
6696 Total
6722 TOTAL
6724 TOTAL
6726 TOTAL
6728 Total
6742 TOTAL
6744 TOTAL
6746 TOTAL
6748 Total
6771 TOTAL
6773 TOTAL
6775 TOTAL
6777 Total
6791 TOTAL
6793 TOTAL
6795 TOTAL
6797 Total
6820 TOTAL
6822 TOTAL
6824 TOTAL
6826 Total
6840 TOTAL
6842 TOTAL
6844 TOTAL
6846 Total
6870 TOTAL
6872 TOTAL
6874 TOTAL
6876 Total
6890 TOTAL
6892 TOTAL
6894 TOTAL
6896 Total
6923 TOTAL
6925 TOTAL
6927 TOTAL
6929 Total
6945 TOTAL
6947 TOTAL
6949 TOTAL
6951 Total
6977 TOTAL
6979 TOTAL
6981 TOTAL
6983 Total
6996 TOTAL
6998 TOTAL
7000 TOTAL
7002 Total
7025 TOTAL
7027 TOTAL
7029 TOTAL
7031 Total
7044 TOTAL
7046 TOTAL
7048 TOTAL
7050 Total
7071 TOTAL
7073 TOTAL
7075 TOTAL
7077 Total
7087 TOTAL
7089 TOTAL
7091 TOTAL
7093 Total
7264 Total 175.02
7275 TOTAL
7277 TOTAL
7279 TOTAL
7281 Total
7294 TOTAL
7296 TOTAL
7298 TOTAL
7300 Total
7321 TOTAL
7323 TOTAL
7325 TOTAL
7327 Total
7341 TOTAL
7343 TOTAL
7345 TOTAL
7347 Total
7370 TOTAL
7372 TOTAL
7374 TOTAL
7376 Total
7387 TOTAL
7389 TOTAL
7391 TOTAL
7393 Total
7407 TOTAL
7409 TOTAL
7420 TOTAL 89.99
7422 Total 103.48
7433 TOTAL
7435 TOTAL
7437 TOTAL
7439 Total
7452 TOTAL
7454 TOTAL
7456 TOTAL
7468 Total
7477 TOTAL
7479 TOTAL
7481 TOTAL
7483 Total
7499 TOTAL
7501 TOTAL
7503 TOTAL
7505 Total
7532 TOTAL
7534 TOTAL
7536 TOTAL
7538 Total
7555 TOTAL
7557 TOTAL
7569 TOTAL
7571 Total
7588 TOTAL
7590 TOTAL
7592 TOTAL
7594 Total
7624 TOTAL
7626 TOTAL
7628 TOTAL
7630 Total
7647 TOTAL
7649 TOTAL
7651 TOTAL
7653 Total
7680 TOTAL
7682 TOTAL
7684 TOTAL
7686 Total
7703 TOTAL
7705 TOTAL
7707 TOTAL
7718 Total 8237.93
7735 TOTAL
7737 TOTAL
7739 TOTAL
7741 Total
7756 TOTAL
7758 TOTAL
7769 TOTAL 5642.12
7771 Total 6424.15
7786 TOTAL
7788 TOTAL
7790 TOTAL
7792 Total
7807 TOTAL
7809 TOTAL
7820 TOTAL 10009.16
7822 Total 11421.17
7836 TOTAL
7838 TOTAL
7840 TOTAL
7842 Total
7854 TOTAL
7856 TOTAL
7858 TOTAL
7871 Total
7883 TOTAL
7885 TOTAL
7887 TOTAL
7889 Total
7901 TOTAL
7903 TOTAL
7905 TOTAL
7918 Total
7930 TOTAL
7932 TOTAL
7934 TOTAL
7936 Total
7950 TOTAL
7952 TOTAL
7954 TOTAL
7966 Total 153.82
7977 TOTAL
7979 TOTAL
7981 TOTAL
7983 Total
7994 TOTAL
7996 TOTAL
7998 TOTAL
8000 Total
8024 TOTAL
8026 TOTAL
8028 TOTAL
8030 Total
8044 TOTAL
8046 TOTAL
8048 TOTAL
8050 Total
8076 TOTAL
8078 TOTAL
8080 TOTAL
8082 Total
8096 TOTAL
8098 TOTAL
8100 TOTAL
8102 Total
8126 TOTAL
8128 TOTAL
8130 TOTAL
8132 Total
8143 TOTAL
8145 TOTAL
8147 TOTAL
8149 Total
8174 TOTAL
8176 TOTAL
8178 TOTAL
8180 Total
8191 TOTAL
8193 TOTAL
8195 TOTAL
8197 Total
8223 TOTAL
8225 TOTAL
8227 TOTAL
8229 Total
8245 TOTAL
8247 TOTAL
8249 TOTAL
8251 Total
8277 TOTAL
8279 TOTAL
8281 TOTAL
8283 Total
8299 TOTAL
8301 TOTAL
8303 TOTAL
8305 Total
8331 TOTAL
8333 TOTAL
8335 TOTAL
8337 Total
8353 TOTAL
8355 TOTAL
8357 TOTAL
8359 Total
8385 TOTAL
8387 TOTAL
8389 TOTAL
8391 Total
8407 TOTAL
8409 TOTAL
8411 TOTAL
8423 Total
8439 TOTAL
8441 TOTAL
8443 TOTAL
8445 Total
8461 TOTAL
8463 TOTAL
8465 TOTAL
8477 Total 37023.83
8493 TOTAL
8495 TOTAL
8497 TOTAL
8499 Total
8515 TOTAL
8517 TOTAL
8519 TOTAL
8521 Total
8546 TOTAL
8548 TOTAL
8550 TOTAL
8552 Total
8568 TOTAL
8570 TOTAL
8572 TOTAL
8574 Total
8600 TOTAL
8602 TOTAL
8604 TOTAL
8606 Total
8628 TOTAL
8630 TOTAL
8642 TOTAL
8644 Total
8663 TOTAL
8665 TOTAL
8667 TOTAL
8669 Total
8698 TOTAL
8700 TOTAL
8702 TOTAL
8704 Total
8725 TOTAL
8727 TOTAL
8729 TOTAL
8731 Total
8761 TOTAL
8763 TOTAL
8765 TOTAL
8767 Total
8796 TOTAL
8798 TOTAL
8800 TOTAL
8802 Total
8821 TOTAL
8823 TOTAL
8825 TOTAL
8827 Total
8858 TOTAL
8860 TOTAL
8862 TOTAL
8864 Total
8883 TOTAL
8894 TOTAL
8896 TOTAL
8898 Total
8917 TOTAL
8919 TOTAL
8921 TOTAL
8923 Total
8954 TOTAL
8956 TOTAL
8958 TOTAL
8960 Total
8978 TOTAL
8980 TOTAL
8982 TOTAL
8984 Total
9012 TOTAL
9014 TOTAL
9016 TOTAL
9018 Total
9036 TOTAL
9038 TOTAL
9040 TOTAL
9053 Total
9071 TOTAL
9073 TOTAL
9075 TOTAL
9077 Total
9106 TOTAL 27691.5
9108 TOTAL 27958.05
9110 TOTAL 31740.47
9112 Total 36346.02
9130 TOTAL
9132 TOTAL
9134 TOTAL
9136 Total
9166 TOTAL
9168 TOTAL
9170 TOTAL
9172 Total
9191 TOTAL
9193 TOTAL
9195 TOTAL
9197 Total
9226 TOTAL
9228 TOTAL
9230 TOTAL
9232 Total
9251 TOTAL
9253 TOTAL
9266 TOTAL
9268 Total
9287 TOTAL
9289 TOTAL
9291 TOTAL
9293 Total
9312 TOTAL
9323 TOTAL 124206.91
9325 TOTAL 141033.99
9327 Total 161522.92
9346 TOTAL
9348 TOTAL
9350 TOTAL
9352 Total
9379 TOTAL
9381 TOTAL
9383 TOTAL
9385 Total
9405 TOTAL
9407 TOTAL
9409 TOTAL
9411 Total
9440 TOTAL
9442 TOTAL
9444 TOTAL
9446 Total
9466 TOTAL
9477 TOTAL 23064.34
9479 TOTAL 26198.93
9481 Total 30015.66
9501 TOTAL
9503 TOTAL
9505 TOTAL
9507 Total
9537 TOTAL
9539 TOTAL
9541 TOTAL
9543 Total
9563 TOTAL
9565 TOTAL
9567 TOTAL
9569 Total
9599 TOTAL
9601 TOTAL
9603 TOTAL
9605 Total
9636 TOTAL 64991.86
9638 TOTAL 65621.44
9640 TOTAL 74555.46
9642 Total 85433.66
9663 TOTAL
9665 TOTAL
9667 TOTAL
9669 Total
9698 TOTAL
9700 TOTAL
9702 TOTAL
9704 Total
9723 TOTAL
9725 TOTAL
9727 TOTAL
9729 Total
9758 TOTAL
9760 TOTAL
9762 TOTAL
9764 Total
9793 TOTAL 144820.66
9795 TOTAL 146218.4
9797 TOTAL 166052.92
9799 Total 190203.75
9818 TOTAL
9820 TOTAL
9822 TOTAL
9824 Total
9856 TOTAL
9858 TOTAL
9860 TOTAL
9862 Total
9882 TOTAL
9884 TOTAL
9896 TOTAL 9781.55
9898 Total 11210.38
9918 TOTAL
9920 TOTAL
9922 TOTAL
9924 Total
9953 TOTAL
9955 TOTAL
9957 TOTAL
9959 Total
9979 TOTAL
9981 TOTAL
9983 TOTAL
9985 Total
10015 TOTAL
10017 TOTAL
10019 TOTAL
10021 Total
10041 TOTAL
10053 TOTAL
10055 TOTAL
10057 Total
10075 TOTAL
10077 TOTAL
10079 TOTAL
10081 Total
10111 TOTAL
10113 TOTAL
10115 TOTAL
10117 Total
10137 TOTAL
10139 TOTAL
10151 TOTAL 71764.04
10153 Total 82294.17
10171 TOTAL
10173 TOTAL
10175 TOTAL
10177 Total
10204 TOTAL
10206 TOTAL
10208 TOTAL
10210 Total
10222 TOTAL
10224 TOTAL
10226 TOTAL
10228 Total
10241 TOTAL
10243 TOTAL
10254 TOTAL 42.34
10256 Total 48.7
10267 TOTAL
10269 TOTAL
10271 TOTAL
10273 Total
10284 TOTAL
10286 TOTAL
10288 TOTAL
10290 Total
10330 TOTAL
10332 TOTAL
10334 TOTAL
10336 Total
10376 TOTAL
10378 TOTAL
10380 TOTAL
10382 Total
10412 TOTAL
10414 TOTAL
10416 TOTAL
10418 Total
10434 TOTAL
10436 TOTAL
10438 TOTAL
10440 Total
10473 TOTAL
10475 TOTAL
10477 TOTAL
10479 Total
10507 TOTAL 808.04
10509 TOTAL 816.12
10511 TOTAL 930.79
10513 Total 1070.4
10530 TOTAL
10532 TOTAL
10534 TOTAL
10536 Total
10560 TOTAL
10562 TOTAL
10564 TOTAL
10566 Total
10583 TOTAL
10585 TOTAL
10587 TOTAL
10598 Total 2174.31
10615 TOTAL
10617 TOTAL
10619 TOTAL
10621 Total
10648 TOTAL
10650 TOTAL
10652 TOTAL
10654 Total
10671 TOTAL
10673 TOTAL
10675 TOTAL
10677 Total
10708 TOTAL
10710 TOTAL
10712 TOTAL
10714 Total
10731 TOTAL
10733 TOTAL
10735 TOTAL
10737 Total
10763 TOTAL
10765 TOTAL
10767 TOTAL
10769 Total
10786 TOTAL
10797 TOTAL 4089.66
10799 TOTAL 4664.25
10801 Total 5363.89
10817 TOTAL
10819 TOTAL
10821 TOTAL
10823 Total
10851 TOTAL
10853 TOTAL
10855 TOTAL
10857 Total
10871 TOTAL
10873 TOTAL
10875 TOTAL
10877 Total
10904 TOTAL
10906 TOTAL
10908 TOTAL
10910 Total
10924 TOTAL
10926 TOTAL
10928 TOTAL
10930 Total
10957 TOTAL
10959 TOTAL
10961 TOTAL
10963 Total
10977 TOTAL
10979 TOTAL
10981 TOTAL
10983 Total
11010 TOTAL
11012 TOTAL
11014 TOTAL
11016 Total
11030 TOTAL
11032 TOTAL
11034 TOTAL
11036 Total
11063 TOTAL
11065 TOTAL
11067 TOTAL
11069 Total
11083 TOTAL
11085 TOTAL
11087 TOTAL
11089 Total
11116 TOTAL
11118 TOTAL
11120 TOTAL
11122 Total
11148 TOTAL
11150 TOTAL
11152 TOTAL
11164 Total 7189.04
11189 TOTAL
11191 TOTAL
11193 TOTAL
11195 Total
11229 TOTAL
11231 TOTAL
11233 TOTAL
11235 Total
11260 TOTAL
11262 TOTAL
11264 TOTAL
11277 Total 8068
11302 TOTAL
11304 TOTAL
11306 TOTAL
11308 Total
11342 TOTAL
11344 TOTAL
11346 TOTAL
11348 Total
11371 TOTAL
11373 TOTAL
11375 TOTAL
11388 Total
11413 TOTAL
11415 TOTAL
11417 TOTAL
11419 Total
11454 TOTAL
11456 TOTAL
11458 TOTAL
11460 Total
11495 TOTAL
11497 TOTAL
11499 TOTAL
11501 Total
11526 TOTAL
11528 TOTAL
11530 TOTAL
11532 Total
11567 TOTAL
11569 TOTAL
11571 TOTAL
11573 Total
11589 TOTAL
11591 TOTAL
11593 TOTAL
11605 Total 68.16
11617 TOTAL
11619 TOTAL
11621 TOTAL
11623 Total
11635 TOTAL
11637 TOTAL
11639 TOTAL
11641 Total
11660 TOTAL
11662 TOTAL
11664 TOTAL
11666 Total
11678 TOTAL
11680 TOTAL
11682 TOTAL
11684 Total
11696 TOTAL
11698 TOTAL
11710 TOTAL 248.04
11712 Total 285.24
11724 TOTAL
11726 TOTAL
11728 TOTAL
11730 Total
11742 TOTAL
11744 TOTAL
11746 TOTAL
11748 Total
11770 TOTAL
11772 TOTAL
11774 TOTAL
11776 Total
11788 TOTAL
11790 TOTAL
11792 TOTAL
11794 Total
11813 TOTAL 428.84
11815 TOTAL 433.12
11817 TOTAL 493.98
11819 Total 568.07
11831 TOTAL
11833 TOTAL
11835 TOTAL
11837 Total
11850 TOTAL
11852 TOTAL
11864 TOTAL 6699.62
11866 Total 7704.56
11890 TOTAL
11892 TOTAL
11894 TOTAL
11896 Total
11929 TOTAL
11931 TOTAL
11933 TOTAL
11935 Total
11965 TOTAL
11967 TOTAL
11969 TOTAL
11971 Total
11994 TOTAL
11996 TOTAL
11998 TOTAL
12000 Total
12033 TOTAL
12035 TOTAL
12037 TOTAL
12039 Total
12072 TOTAL
12074 TOTAL
12076 TOTAL
12078 Total
12116 TOTAL
12118 TOTAL
12120 TOTAL
12122 Total
12146 TOTAL
12148 TOTAL
12160 TOTAL
12162 Total
12176 TOTAL
12178 TOTAL
12180 TOTAL
12182 Total
12193 TOTAL
12195 TOTAL
12197 TOTAL
12208 Total 83.46
12219 TOTAL
12221 TOTAL
12223 TOTAL
12225 Total
12236 TOTAL
12238 TOTAL
12240 TOTAL
12242 Total
12265 TOTAL
12267 TOTAL
12269 TOTAL
12271 Total
12281 TOTAL 180
12283 TOTAL 181.8
12285 TOTAL 207.34
12287 Total 238.44
12311 TOTAL
12313 TOTAL
12315 TOTAL
12317 Total
12328 TOTAL
12330 TOTAL
12332 TOTAL
12334 Total
12345 TOTAL
12347 TOTAL
12358 TOTAL 167.03
12360 Total 192.08
12371 TOTAL
12373 TOTAL
12375 TOTAL
12377 Total
12388 TOTAL
12390 TOTAL
12392 TOTAL
12394 Total
12415 TOTAL
12417 TOTAL
12419 TOTAL
12421 Total
12432 TOTAL
12434 TOTAL
12436 TOTAL
12438 Total
12449 TOTAL
12461 TOTAL 365.62
12463 TOTAL 416.99
12465 Total 479.54
12476 TOTAL
12478 TOTAL
12480 TOTAL
12482 Total
12493 TOTAL
12495 TOTAL
12497 TOTAL
12509 Total 512.66
12520 TOTAL
12522 TOTAL
12524 TOTAL
12526 Total
12537 TOTAL
12539 TOTAL
12541 TOTAL
12543 Total
12565 TOTAL
12567 TOTAL
12569 TOTAL
12571 Total
12580 TOTAL
12582 TOTAL
12584 TOTAL
12586 Total
12606 TOTAL 410
12608 TOTAL 414.1
12610 TOTAL 472.28
12612 Total 543.12
12626 TOTAL
12628 TOTAL
12630 TOTAL
12632 Total
12650 TOTAL
12652 TOTAL
12654 TOTAL
12656 Total
12666 TOTAL
12668 TOTAL
12670 TOTAL
12672 Total
12682 TOTAL
12684 TOTAL
12696 TOTAL 150.9
12698 Total 173.53
12708 TOTAL
12710 TOTAL
12712 TOTAL
12714 Total
12724 TOTAL
12726 TOTAL
12728 TOTAL
12730 Total
12757 TOTAL
12759 TOTAL
12761 TOTAL
12763 Total
12773 TOTAL
12775 TOTAL
12777 TOTAL
12779 Total
12797 TOTAL
12799 TOTAL
12801 TOTAL
12803 Total
12813 TOTAL
12815 TOTAL
12817 TOTAL
12819 Total
12829 TOTAL
12831 TOTAL
12843 TOTAL 133.62
12845 Total 153.66
12855 TOTAL
12857 TOTAL
12859 TOTAL
12861 Total
12878 TOTAL 148
12880 TOTAL 149.48
12891 TOTAL 170.48
12893 Total 196.05
12904 TOTAL
12906 TOTAL
12908 TOTAL
12910 Total
12919 TOTAL
12921 TOTAL
12923 TOTAL
12925 Total
12946 TOTAL 287
12948 TOTAL 289.87
12950 TOTAL 330.6
12952 Total 380.19
12963 TOTAL 345
12965 TOTAL 348.45
12967 TOTAL 397.41
12969 Total 457.02
12980 TOTAL 179
12992 TOTAL 180.79
12994 TOTAL 206.19
12996 Total 237.12
13010 TOTAL
13012 TOTAL
13014 TOTAL
13016 Total
13026 TOTAL
13028 TOTAL
13040 TOTAL 266.09
13042 Total 306
13052 TOTAL
13054 TOTAL
13056 TOTAL
13058 Total
13068 TOTAL
13070 TOTAL
13072 TOTAL
13074 Total
13094 TOTAL
13096 TOTAL
13098 TOTAL
13100 Total
13110 TOTAL
13112 TOTAL
13114 TOTAL
13116 Total
13140 TOTAL 179
13142 TOTAL 180.79
13144 TOTAL 206.19
13146 Total 237.12
13157 TOTAL
13159 TOTAL
13161 TOTAL
13163 Total
13174 TOTAL
13176 TOTAL
13178 TOTAL
13180 Total
13200 TOTAL
13202 TOTAL
13204 TOTAL
13206 Total
13217 TOTAL
13219 TOTAL
13221 TOTAL
13223 Total
13245 TOTAL
13247 TOTAL
13249 TOTAL
13251 Total
13262 TOTAL
13264 TOTAL
13266 TOTAL
13268 Total
13279 TOTAL
13292 TOTAL 689.83
13294 TOTAL 786.75
13296 Total 904.76
13307 TOTAL
13309 TOTAL
13311 TOTAL
13313 Total
13324 TOTAL
13326 TOTAL
13328 TOTAL
13340 Total 904.76
13351 TOTAL
13353 TOTAL
13355 TOTAL
13357 Total
13368 TOTAL
13370 TOTAL
13372 TOTAL
13374 Total
13395 TOTAL
13397 TOTAL
13399 TOTAL
13401 Total
13412 TOTAL 887
13414 TOTAL 895.87
13416 TOTAL 1021.74
13418 Total 1175
13429 TOTAL 887
13431 TOTAL 895.87
13433 TOTAL 1021.74
13435 Total 1175
13461 TOTAL
13463 TOTAL
13465 TOTAL
13467 Total
13478 TOTAL
13480 TOTAL
13482 TOTAL
13484 Total
13505 TOTAL
13507 TOTAL
13509 TOTAL
13511 Total
13522 TOTAL
13524 TOTAL
13526 TOTAL
13528 Total
13539 TOTAL
13550 TOTAL 275.73
13552 TOTAL 314.47
13554 Total 361.64
13565 TOTAL
13567 TOTAL
13569 TOTAL
13571 Total
13582 TOTAL
13584 TOTAL
13586 TOTAL
13588 Total
13609 TOTAL
13611 TOTAL
13613 TOTAL
13615 Total
13626 TOTAL
13628 TOTAL
13630 TOTAL
13632 Total
13655 TOTAL
13657 TOTAL
13659 TOTAL
13661 Total
13672 TOTAL
13674 TOTAL
13676 TOTAL
13678 Total
13689 TOTAL
13691 TOTAL
13704 TOTAL 786.75
13706 Total 904.76
13717 TOTAL
13719 TOTAL
13721 TOTAL
13723 Total
13734 TOTAL
13736 TOTAL
13738 TOTAL
13740 Total
13761 TOTAL
13763 TOTAL
13765 TOTAL
13767 Total
13778 TOTAL
13780 TOTAL
13782 TOTAL
13784 Total
13795 TOTAL
13807 TOTAL 895.87
13809 TOTAL 1021.74
13811 Total 1175
13822 TOTAL
13824 TOTAL
13826 TOTAL
13828 Total
13839 TOTAL
13841 TOTAL
13843 TOTAL
13845 Total
13867 TOTAL
13869 TOTAL
13871 TOTAL
13873 Total
13884 TOTAL
13886 TOTAL
13888 TOTAL
13890 Total
13916 TOTAL
13918 TOTAL
13920 TOTAL
13922 Total
13933 TOTAL
13935 TOTAL
13937 TOTAL
13939 Total
13950 TOTAL
13961 TOTAL 202
13963 TOTAL 230.38
13965 Total 264.94
13976 TOTAL
13978 TOTAL
13980 TOTAL
13982 Total
13993 TOTAL
13995 TOTAL
13997 TOTAL
13999 Total
14018 TOTAL
14020 TOTAL
14022 TOTAL
14024 Total
14035 TOTAL
14037 TOTAL
14039 TOTAL
14041 Total
14052 TOTAL
14054 TOTAL
14066 TOTAL 503.38
14068 Total 578.89
14079 TOTAL
14081 TOTAL
14083 TOTAL
14085 Total
14096 TOTAL
14098 TOTAL
14100 TOTAL
14102 Total
14123 TOTAL
14125 TOTAL
14127 TOTAL
14129 Total
14140 TOTAL
14142 TOTAL
14144 TOTAL
14146 Total
14157 TOTAL
14169 TOTAL 689.83
14171 TOTAL 786.75
14173 Total 904.76
14184 TOTAL
14186 TOTAL
14188 TOTAL
14190 Total
14201 TOTAL
14203 TOTAL
14205 TOTAL
14207 Total
14229 TOTAL
14231 TOTAL
14233 TOTAL
14235 Total
14248 TOTAL
14250 TOTAL
14252 TOTAL
14254 Total
14275 TOTAL
14277 TOTAL
14279 TOTAL
14281 Total
14292 TOTAL
14294 TOTAL
14296 TOTAL
14298 Total
14309 TOTAL
14321 TOTAL 895.87
14323 TOTAL 1021.74
14325 Total 1175
14336 TOTAL
14338 TOTAL
14340 TOTAL
14342 Total
14358 TOTAL
14360 TOTAL
14371 TOTAL 218.86
14373 Total 251.69
14385 TOTAL
14387 TOTAL
14389 TOTAL
14391 Total
14404 TOTAL
14406 TOTAL
14408 TOTAL
14410 Total
14431 TOTAL
14433 TOTAL
14435 TOTAL
14437 Total
14450 TOTAL
14452 TOTAL
14454 TOTAL
14456 Total
14468 TOTAL
14480 TOTAL 340.37
14482 TOTAL 388.19
14484 Total 446.42
14496 TOTAL 409
14498 TOTAL 413.09
14500 TOTAL 471.13
14502 Total 541.8
14514 TOTAL
14516 TOTAL
14518 TOTAL
14531 Total 712.68
14543 TOTAL 576
14545 TOTAL 581.76
14547 TOTAL 663.5
14549 Total 763.02
14561 TOTAL 681
14563 TOTAL 687.81
14565 TOTAL 784.45
14567 Total 902.11
14590 TOTAL 838
14592 TOTAL 846.38
14594 TOTAL 965.3
14596 Total 1110.09
14608 TOTAL
14610 TOTAL
14612 TOTAL
14614 Total
14638 TOTAL 193
14640 TOTAL 194.93
14642 TOTAL 222.32
14644 Total 255.67
14656 TOTAL
14658 TOTAL
14660 TOTAL
14662 Total
14682 TOTAL 248
14684 TOTAL 250.48
14686 TOTAL 285.67
14688 Total 328.52
14700 TOTAL
14702 TOTAL
14704 TOTAL
14706 Total
14718 TOTAL
14720 TOTAL
14722 TOTAL
14735 Total 423.9
14746 TOTAL 461
14748 TOTAL 465.61
14750 TOTAL 531.03
14752 Total 610.68
14763 TOTAL 565
14765 TOTAL 570.65
14767 TOTAL 650.83
14769 Total 748.45
14789 TOTAL
14791 TOTAL
14793 TOTAL
14795 Total
14806 TOTAL 726
14808 TOTAL 733.26
14810 TOTAL 836.28
14812 Total 961.73
14833 TOTAL 840
14835 TOTAL 848.4
14837 TOTAL 967.6
14839 Total 1112.74
14850 TOTAL 1138
14852 TOTAL 1149.38
14854 TOTAL 1310.87
14856 Total 1507.5
14871 TOTAL
14883 TOTAL 236.34
14885 TOTAL 269.55
14887 Total 309.98
14898 TOTAL
14900 TOTAL
14902 TOTAL
14904 Total
14915 TOTAL
14917 TOTAL
14919 TOTAL
14921 Total
14943 TOTAL
14945 TOTAL
14947 TOTAL
14949 Total
14960 TOTAL
14962 TOTAL
14964 TOTAL
14966 Total
14987 TOTAL 875
14989 TOTAL 883.75
14991 TOTAL 1007.92
14993 Total 1159.1
15004 TOTAL
15006 TOTAL
15008 TOTAL
15010 Total
15034 TOTAL 150
15036 TOTAL 151.5
15038 TOTAL 172.79
15040 Total 198.7
15051 TOTAL
15053 TOTAL
15055 TOTAL
15057 Total
15066 TOTAL
15068 TOTAL
15070 TOTAL
15081 Total 253.02
15092 TOTAL 205
15094 TOTAL 207.05
15096 TOTAL 236.14
15098 Total 271.56
15109 TOTAL 287
15111 TOTAL 289.87
15113 TOTAL 330.6
15115 Total 380.19
15137 TOTAL
15139 TOTAL
15141 TOTAL
15143 Total
15154 TOTAL 478
15156 TOTAL 482.78
15158 TOTAL 550.61
15160 Total 633.2
15171 TOTAL 683
15173 TOTAL 689.83
15186 TOTAL 786.75
15188 Total 904.76
15199 TOTAL 683
15201 TOTAL 689.83
15203 TOTAL 786.75
15205 Total 904.76
15246 Total 253.02
15442 TOTAL 287
15444 TOTAL 289.87
15446 TOTAL 330.6
15448 Total 380.19
15510 TOTAL 550.61
15512 Total 633.2
15590 TOTAL
15592 TOTAL
15594 TOTAL
15596 Total
15604 TOTAL
15606 TOTAL
15608 TOTAL
15610 Total
15629 TOTAL
15631 TOTAL
15633 TOTAL
15635 Total
15643 TOTAL
15645 TOTAL
15647 TOTAL
15649 Total
15657 TOTAL
15659 TOTAL
15661 TOTAL
15673 Total
15681 TOTAL
15683 TOTAL
15685 TOTAL
15687 Total
15701 TOTAL
15703 TOTAL
15705 TOTAL
15707 Total
15729 TOTAL
15731 TOTAL
15733 TOTAL
15735 Total
15744 TOTAL
15746 TOTAL
15748 TOTAL
15750 Total
15806 TOTAL
15808 TOTAL
15810 TOTAL
15812 Total
15850 TOTAL
15852 TOTAL
15854 TOTAL
15856 Total
15892 TOTAL
15894 TOTAL
15896 TOTAL
15898 Total
15937 TOTAL
15939 TOTAL
15941 TOTAL
15943 Total
15972 TOTAL
15974 TOTAL
15985 TOTAL 37737.3 Y
15987 Total 43397.9 Z
16364 TOTAL
16366 TOTAL
16368 TOTAL
16371 Total
16407 TOTAL
16418 TOTAL 1895.76 X
16420 TOTAL 1984.63 Y
16423 Total 2092.83 Z
16466 TOTAL
16468 TOTAL
16479 TOTAL 1969.69 Y
16482 Total 2085.53 Z
16520 TOTAL
16522 TOTAL
16534 TOTAL 1993.99 Y
16537 Total 2109.83 Z
16577 TOTAL
16579 TOTAL
16590 TOTAL 2058.34 Y
16593 Total 2192.42 Z
16631 TOTAL
16633 TOTAL
16643 TOTAL 2082.64 Y
16646 Total 2216.72 Z
16661 TOTAL
16663 TOTAL
16665 TOTAL
16667 Total
16679 TOTAL
16681 TOTAL
16683 TOTAL
16694 Total 399.5
16707 TOTAL
16709 TOTAL
16711 TOTAL
16713 Total
16725 TOTAL
16727 TOTAL
16729 TOTAL
16731 Total
16752 TOTAL
16754 TOTAL
16756 TOTAL
16758 Total
16770 TOTAL
16772 TOTAL
16774 TOTAL
16776 Total
16796 TOTAL
16798 TOTAL
16800 TOTAL
16802 Total
16814 TOTAL
16816 TOTAL
16818 TOTAL
16820 Total
16860 TOTAL
16862 TOTAL
16864 TOTAL
16866 Total
16904 TOTAL
16906 TOTAL
16908 TOTAL
16910 Total
16991 TOTAL
16993 TOTAL
17078 TOTAL
17080 TOTAL
17082 TOTAL
17084 Total
17121 TOTAL
17123 TOTAL
17125 TOTAL
17127 Total
17165 TOTAL
17167 TOTAL
17169 TOTAL
17171 Total
17210 TOTAL
17212 TOTAL
17214 TOTAL
17216 Total
17253 TOTAL
17255 TOTAL
17257 TOTAL
17259 Total
17288 TOTAL
17290 TOTAL
17292 TOTAL
17303 Total
17329 TOTAL
17331 TOTAL
17333 TOTAL
17335 Total
17375 TOTAL
17377 TOTAL
17379 TOTAL
17381 Total
17419 TOTAL
17421 TOTAL
17423 TOTAL
17425 Total
17525 TOTAL
17527 TOTAL
17529 TOTAL
17532 Total
17673 TOTAL 9185.98
17675 TOTAL 9199.72 X
17677 TOTAL 9394.64 Y
17680 Total 9631.97 Z
17755 TOTAL
17757 TOTAL
17759 TOTAL
17762 Total
17914 TOTAL
17916 TOTAL
17918 TOTAL
17921 Total
18005 TOTAL
18007 TOTAL
18018 TOTAL 24481.24 Y
18021 Total 26027.71 Z
18105 TOTAL
18116 TOTAL 23360.71 X
18118 TOTAL 24630.8 Y
18121 Total 26177.27 Z
18143 TOTAL
18160 TOTAL
18189 TOTAL
18207 TOTAL
18301 TOTAL
18303 TOTAL
18305 TOTAL
18308 Total
18399 TOTAL
18401 TOTAL
18403 TOTAL
18406 Total
18541 TOTAL
18543 TOTAL
18554 TOTAL 17976.2 Y
18557 Total 18151.17 Z
18643 TOTAL
18645 TOTAL
18647 TOTAL
18650 Total
18780 TOTAL
18782 TOTAL
18784 TOTAL
18787 Total
18865 TOTAL 1012.63
18867 TOTAL
18869 TOTAL
18872 Total
18938 TOTAL
18950 TOTAL 242.68 X
18952 TOTAL 273.08 Y
18955 Total 310.09 Z
18980 TOTAL
18982 TOTAL
18984 TOTAL
18987 Total
19018 TOTAL
19020 TOTAL
19022 TOTAL
19025 Total
19063 TOTAL
19065 TOTAL
19067 TOTAL
19070 Total
19106 TOTAL
19108 TOTAL
19110 TOTAL
19113 Total
19132 TOTAL
19134 TOTAL
19136 TOTAL
19138 Total
19164 TOTAL
19166 TOTAL
19168 TOTAL
19170 Total
19186 TOTAL
19188 TOTAL
19190 TOTAL
19192 Total
19225 TOTAL
19227 TOTAL
19229 TOTAL
19232 Total
19261 TOTAL
19263 TOTAL
19265 TOTAL
19268 Total
19287 TOTAL
19289 TOTAL
19291 TOTAL
19294 Total
19328 TOTAL
19330 TOTAL
19332 TOTAL
19334 Total
19353 TOTAL
19355 TOTAL
19357 TOTAL
19369 Total 1002.32 Z
19392 TOTAL
19394 TOTAL
19396 TOTAL
19399 Total
19431 TOTAL
19433 TOTAL
19435 TOTAL
19438 Total
19453 TOTAL
19455 TOTAL
19457 TOTAL
19459 Total
19502 TOTAL
19504 TOTAL
19506 TOTAL
19509 Total
19549 TOTAL
19551 TOTAL
19553 TOTAL
19556 Total
19593 TOTAL
19595 TOTAL
19597 TOTAL
19600 Total
19671 TOTAL
19673 TOTAL
19675 TOTAL
19678 Total
19756 TOTAL
19758 TOTAL
19760 TOTAL
19763 Total
19807 TOTAL
19809 TOTAL
19811 TOTAL
19814 Total
19856 TOTAL
19858 TOTAL
19860 TOTAL
19863 Total
19918 TOTAL
19920 TOTAL
19922 TOTAL
19925 Total
19973 TOTAL
19975 TOTAL
19977 TOTAL
19980 Total
20040 TOTAL
20042 TOTAL
20044 TOTAL
20047 Total
20107 TOTAL
20109 TOTAL
20111 TOTAL
20114 Total
20142 TOTAL
20144 TOTAL
20146 TOTAL
20149 Total
20163 TOTAL
20165 TOTAL
20167 TOTAL
20170 Total
20309 TOTAL
20311 TOTAL
20314 Total
20362 TOTAL 1833.26 W
20364 TOTAL 1833.68 X
20366 TOTAL 1839.54 Y
20369 Total 1846.69 Z
20402 TOTAL
20404 TOTAL
20406 TOTAL
20409 Total
20451 TOTAL
20453 TOTAL
20455 TOTAL
20458 Total
20498 TOTAL
20500 TOTAL
20502 TOTAL
20505 Total
20551 TOTAL
20553 TOTAL
20555 TOTAL
20558 Total
20625 TOTAL
20627 TOTAL
20629 TOTAL
20632 Total
20720 TOTAL
20722 TOTAL
20724 TOTAL
20727 Total
20802 TOTAL
20804 TOTAL
20806 TOTAL
20809 Total
20873 TOTAL
20875 TOTAL
20877 TOTAL
20880 Total
20946 TOTAL
20948 TOTAL
20950 TOTAL
20953 Total
20985 TOTAL
21004 TOTAL
21034 TOTAL
21096 TOTAL
21098 TOTAL
21100 TOTAL
21103 Total
21141 TOTAL
21143 TOTAL
21145 TOTAL
21148 Total
21172 TOTAL
21174 TOTAL
21186 TOTAL 278.54 Y
21188 Total 320.32 Z
21210 TOTAL
21212 TOTAL
21214 TOTAL
21216 Total
21248 TOTAL
21250 TOTAL
21252 TOTAL
21254 Total
21287 TOTAL
21289 TOTAL
21291 TOTAL
21293 Total
21315 TOTAL
21317 TOTAL
21319 TOTAL
21329 Total 44898.37
21351 TOTAL
21353 TOTAL
21355 TOTAL
21357 Total
21387 TOTAL
21389 TOTAL
21391 TOTAL
21393 Total
21416 TOTAL
21428 TOTAL 102055.43 X
21430 TOTAL 116394.21 Y
21432 Total 133853.34 Z
21456 TOTAL
21458 TOTAL
21460 TOTAL
21462 Total
21602 TOTAL
21604 TOTAL
21606 TOTAL
21608 Total
21630 TOTAL
21632 TOTAL
21634 TOTAL
21636 Total
21668 TOTAL
21670 TOTAL
21672 TOTAL
21674 Total
21705 TOTAL
21707 TOTAL
21709 TOTAL
21711 Total
21788 TOTAL
21790 TOTAL
21792 TOTAL
21794 Total
21826 TOTAL
21828 TOTAL
21830 TOTAL
21832 Total
21866 TOTAL
21868 TOTAL
21870 TOTAL
21872 Total
21905 TOTAL
21907 TOTAL
21909 TOTAL
21911 Total
21936 TOTAL
21938 TOTAL
21940 TOTAL
21974 TOTAL
21976 TOTAL
21978 TOTAL
21980 Total
22012 TOTAL
22014 TOTAL
22016 TOTAL
22018 Total
22050 TOTAL
22052 TOTAL
22054 TOTAL
22056 Total
22096 TOTAL
22098 TOTAL
22100 TOTAL
22102 Total
22137 TOTAL
22139 TOTAL
22141 TOTAL
22143 Total
22209 TOTAL
22211 TOTAL
22213 TOTAL
22321 TOTAL
22323 TOTAL
22325 TOTAL
22327 Total
22360 TOTAL
22362 TOTAL
22364 TOTAL
22366 Total
22397 TOTAL
22399 TOTAL
22401 TOTAL
22403 Total
22438 TOTAL
22440 TOTAL
22442 TOTAL
22444 Total
22468 TOTAL
22555 TOTAL
22557 TOTAL
22559 TOTAL
22596 TOTAL
22598 TOTAL
22600 TOTAL
22602 Total
22636 TOTAL
22638 TOTAL
22640 TOTAL
22642 Total
22678 Total
22680 TOTAL
22682 TOTAL
22684 Total
22713 Total
22715 TOTAL
22717 TOTAL
22719 Total
22739 Total
22741 TOTAL
22743 TOTAL
22745 Total
22774 Total
22776 TOTAL
22778 TOTAL
22780 Total
22822 TOTAL
22824 TOTAL
22826 TOTAL
22828 Total
22865 TOTAL
22867 TOTAL
22869 TOTAL
22871 Total
22906 TOTAL
22908 TOTAL
22910 TOTAL
22912 Total
22945 TOTAL
22947 TOTAL
22949 TOTAL
22951 Total
22979 TOTAL
23021 TOTAL
23023 TOTAL
23025 TOTAL
23054 TOTAL
23056 TOTAL
23058 TOTAL
23060 Total
23071 TOTAL 15000
23073 TOTAL 15150
23075 TOTAL 17278.58
23099 TOTAL
23101 TOTAL
23103 TOTAL
23105 Total
23115 TOTAL
23117 TOTAL
23119 TOTAL
23121 Total
23145 TOTAL
23147 TOTAL
23149 TOTAL
23151 Total
23162 TOTAL 29500
23164 TOTAL 29795
23166 TOTAL 33981.2
23168 Total 39078.38
23192 TOTAL
23194 TOTAL
23196 TOTAL
23198 Total
23208 TOTAL
23210 TOTAL
23212 TOTAL
23214 Total
23227 TOTAL 29500
23256 TOTAL 15000
23258 TOTAL 15150
23260 TOTAL 17278.58
23262 Total 19870.36
23273 TOTAL 23600
23275 TOTAL 23836
23277 TOTAL 27184.96
23279 Total 31262.7
23309 TOTAL
23311 TOTAL
23313 TOTAL
23315 Total
19832 Total
Total == 0.029
0.086 cum
cum Say
18282 0.09 cum
Total = 0.086 cum Say
18370 0.09 cum
18261 Total
Total == 0.135
0.26 +cum
0.09 = 0.35
20101 cum
Total = 0.26 + 0.09 = 0.35
20290 cum
Total = 0.345 cum Say
20207 0.35
Totalcum
= 0.891 + 1.069 =
20265 1.96 cum
Total = 1.294+0.02 =
20084 1.1.314 cum
20198 Total = 2.561 cum
18724 Total = 3.735 cum
20213 Total
Total ==0.69sqm.
4.184 cum Say
5170 0.70sqm.
5489 5.9.3 Total
Total =0.86 sqm.= 0.026
deduction
20269 cum
Total deduction= = (-)
20202 0.026deduction==
Total cum (-)
20217 0.181 cum
Total for 2.25 m depth =
20223 4.0+ 0.38 =4.38 cum
6129 Total:
6159 Total:
6179 Total:
6211 Total:
6231 Total:
19786 Total= 0.018 cum
16560 Total= 0.026 cum
16615 Total= 0.026 cum
18245 Total= 0.026 cum
18344 Total= 0.026 cum
18728 Total=
Total= 0.052
0.086 cum
cum Say 0.09
18523 cum
Total= 0.086 cum Say 0.09
18624 cum
Total= 0.086 cum Say 0.09
18752 cum
Total= 0.119 cum Say 0.12
18361 cum
18358 Total= 0.135 cum
19643 Total= 0.229 cum
17710 Total=
Total= 0.249
0.2554cumcumsaySay0.25
18513 0.26 cum
Total= 0.2554 cum Say
18616 0.26 cum
18510 Total= 0.277 cum
17982 Total=
Total= 0.369
0.4099cumcum. Say
5398 0.41 cum.
Total= 0.419 cum Say 0.42
18744 cum
18742 Total= 0.446 cum
Total= 0.547 sqm Say 0.55
20617 sqm
20663 Total= 0.553 cum
18241 Total= 0.557
18041 Total= 0.811 cum
20776 Total=
Total= 0.917
0.934 sqm
cum Say 0.93
17702 cum
20538 Total= 1.080 sqm
20933 Total= 1.186 sqm
20915 Total= 1.38 sqm
5336 5.9.3 Total= 1.49 sqm.
20596 Total= 1.592 sqm
18291 Total=
Total= 1.75
144.96sqmSay 145
21053 numbers
11249 Total= 15.70 cum
11209 Total= 15.96 cum
11178 Total= 16.17 cum
11137 Total= 16.31 cum
11291 Total= 16.56 cum
11322 Total= 17.26 cum
11556 Total= 17.44 cum
11360 Total= 17.79 cum
11402 Total= 18.14 cum
11443 Total= 18.23 cum
11515 Total= 18.24 cum
11474 Total= 18.38 cum
20673 Total= 2.44 sqm
18071 Total= 2.652 sqm
18806 Total=
Total= 3.735
4.483 cum
sqm Say 4.48
18531 sqm
Total= 4.483 sqm Say 4.48
18632 sqm
18761 Total= 7.61 sqm
18855 Total= 7.61 sqm
5469 13.9.1 Total=2.16sqm.
5316 Total=4.41sqm.
Totol for 4.45 m depth
20208 2.54 + 0.35
Transportation and
23308 9977 consumables etc.
Trenching and refilling L.S. 33.56 2
357 etc.
Trenching and refilling
391 etc.
Trenching and refilling
416 etc.
Trenching and refilling
451 etc.
Trenching and refilling
476 etc.
Trenching and refilling
511 etc.
Trenching and refilling
803 etc.
Trenching and refilling
841 etc.
Trenching and refilling
869 etc.
Trenching and refilling
908 etc.
Trenching and refilling
946 etc.
Trenching and refilling
974 etc.
Trenching and refilling
1007 etc.
Trenching and refilling
1036 etc.
Trenching and refilling
1075 etc.
Trenching and refilling
1781 etc.
Trenching and refilling
1818 etc.
Trenching and refilling
1852 etc.
Trenching and refilling
1878 etc.
Trenching and refilling
1915 etc.
Trenching and refilling
1941 etc.
Trenching and refilling
1976 etc.
Trenching and refilling
2013 etc.
Trenching and refilling
2039 etc.
Trenching and refilling
2075 etc.
Trenching and refilling
2395 etc.
Trenching and refilling
2432 etc.
Trenching and refilling
2469 etc.
Trenching and refilling
2497 etc.
Trenching and refilling
2532 etc.
Trenching and refilling
2558 etc.
Trenching and refilling
2596 etc.
Trenching and refilling
2633 etc.
boring machine shall not
22299 Note: be used.
2315 18.40.1 two or more coats
2346 18.40.2 two or more coats
6073 Under the pipe = 75mm+
6118 Under the pipe = 75mm+
6148 Under the pipe = 75mm+
6168 Under the pipe = 75mm+
6200 Under the pipe = 75mm+
6220 Under the pipe = 75mm+
6269 Under the pipe = 75mm+
6289 Under thecm
union 30 pipe = 75mm+
long 15 mm
3378 9988 bore
union 30 cm long 20 mm
3394 9988 bore
union 45 cm long 15 mm
3424 9988 bore
union 45 cm long 20 mm
3440 Code 9988 bore
21947 Description
Code Unit Quantity Rate Amount
22221 Description
Code Unit Quantity Rate Amount
22566 Description
Code Unit Quantity Rate Amount
23034 Description Unit Quantity Rate Amount
1158 Description Unit Quantity Rate Amount
1275 Description Unit Quantity Rate Amount
Code
22176 Description
Code Unit Quantity Rate Amount
22476 Description
Code Unit Quantity Rate Amount
22520 Description
Code Unit Quantity Rate Amount
22988 Description
Code Unit Quantity Rate Amount
23084 Description
Code Unit Quantity Rate Amount
23130 Description
Code Unit Quantity Rate Amount
23235 Description Unit Quantity pipe
P.V.C.connection Rate Amount
3377 1687 with brass
P.V.C.connection pipe each 1 30
3393 1688 with brass
P.V.C.connection pipe each 1 35
3423 1689 with brass
P.V.C.connection pipe each 1 35
3439 1690 with brass each 1 48
3556 18.25.1 Up to 300 mm dia
3622 18.26.1 Up to 300 mm dia
8016 18.66.1 Up to 300 mm dia
8067 18.67.1 Up to 300 mm dia
6333 18.42.1 Up to 6 metres depth
8119 18.68.1 Up to 600 mm dia
8166 18.69.1 Up
Upto to50
600tonne
mm diacapacity
23249 20.8.1 pile
Upto 50 tonne Safe
23187 20.7.1.1 capacity pile
23144 upto 50MT. good the
and making
2317 same
3065 18.19.1.2 Vertical
3109 18.19.2.2 Vertical
3153 18.19.3.2 Vertical
3195 18.19.4.2 Vertical
3237 18.19.5.2 Vertical
3282 18.19.6.2 Vertical
20623 9999 vertical
(initial) ofgrating
piles in
23093 7247 direction
accordance of with
Engineer per test 1 45000
23041 20.6 incharge.
(INITIAL) of piles in
23048 7246 accordance
(INITIAL) of piles in per test 1 40000
23139 7248 accordance per test 1 50000
16006 W = 12.4 + 30 = 42.4
16106 W = 124 + 300 = 424 mm
16026 W = 18.2 + 30 = 48.2
16057 W = 23.4 + 30 = 53.4
16077 W = 29 + 30 = 59
16249 W
W == 290
D + X+ ;300
X = =300
590mm,
mmD
16104 =W100= D++12X ;+X = 300 mm, D
16247 =Wall
250: +1.40x0.45 m = 0.63
20671 sqm
Wall : 1.80x0.70 m = 1.26
20592 sqm
Wall : 1.80x0.70 m = 1.26
20670 sqm
Wall : 1.90x0.45 m =
20536 0.855 sqm
Wall : 2.13x0.30 m =
20774 0.639
Wall : sqm
2.40x0.30 m = 0.72
20833 sqm
21052 Wastage 10%on
wastage etc. = 13.718
P,
543 9999 30xP/100
wastage etc. on P,
566 9999 30xP/100
wastage etc. on P,
599 9999 30xP/100
wastage etc. on P,
623 9999 30xP/100
wastage etc. on P,
658 9999 30xP/100
wastage etc. on X 3 * X /
11881 100
wastage etc. on X 3 * X /
11920 100
wastage etc. on X 3 * X /
11947 100
wastage etc. on X 3 * X /
11985 100
wastage etc. on X 3 * X /
12024 100
wastage etc. on X 3 * X /
12053 100
wastage etc. on X 3 * X /
12094 100
wastage etc. on X 3 * X /
12133 100
Water meter (including
7616 7418 testing charges)
Water meter (including each 1 2030
7639 testingmeter
7419 Water charges) (including each 1 3143
7672 7420 testing charges)
Water meter (including each 1 4765
7695 7421 testing
Q) Wherecharges)
Sin Q = each 1 5145
16140 #ERROR! [R/(W/2)]
WD1 + R²(Cot= 2R/W
Q) -
16136 #ERROR! R²(3.14/2
Weight - Q)
= (2x257) = 514kg
3505 = 5.14 quintal
3536 Weight
Weight =for70x10 = 700kg.
carriage = pipe
2625 weight
Weight for carriage = pipe
2173 weight +for carriage = pipe
Weight
2198 weight
Weight +for carriage = pipe
2235 weight
Weight +for carriage = pipe
2272 weight
Weight +for carriage = pipe
2340 weight +for carriage = pipe
Weight
2489 weight
Weight +for carriage = pipe
2524 weight
Weight +for carriage = pipe
2550 weight
Weight +for carriage = pipe
2588 weight
Weight +for carriage = pipe
2111 weight
Weight +for
15% for fiitings
carriage = pipe=
2137 weight
Weight +for
15% for fiitings
carriage = pipe=
2301 weight
Weight +for
15% for fiitings
carriage = pipe=
2388 weight + 2% for fiitings
Weight for carriage = pipe =
2425 weight
Weight +for
2%carriage
for fiitings =
= pipe
2452 weight
Weight +of2% 1m forpipes
fiitings
= =
3863 103.10
Weight Kgof 1 m pipes =
9183 106.640ofKg1 m pipes =
Weight
10032 108.100
Weight ofKg1 m pipes =
8751 110.00
Weight Kgof 1 m pipes =
9589 110.970 Kg
Weight of 1 m pipes =
3899 125.45
Weight Kg
of 1 m pipes =
10066 127.800
Weight ofKg1 m pipes =
9616 129.480
Weight ofKg1 m pipes =
8776 135.70
Weight Kg
of 1 m pipes =
9218 138.61 Kg
Weight of 1 m pipes =
10102 147.900
Weight ofKg1 m pipes =
8947 15.39
WeightKgof 1 m pipes =
3936 151.270
Weight ofKg1 m pipes =
8811 166.80
Weight Kg
of 1 m pipes =
9653 168.680
Weight ofKg1 m pipes =
9370 17.76
WeightKgof 1 m pipes =
3963 177.090
Weight ofKg1 m pipes =
9243 188.92
Weight Kg
of 1 m pipes =
3680 19.820 Kg
Weight of 1 m pipes =
10128 198.900
Weight ofKg1 m pipes =
8848 201.60
Weight Kg
of 1 m pipes =
9847 21.700 Kg
Weight of 1 m pipes =
9690 217.540ofKg1 m pipes =
Weight
8971 22.750
Weight Kg
of 1 m pipes =
8873 234.80 Kg
Weight of 1 m pipes =
3999 236.000
Weight ofKg1 m pipes =
9715 242.600ofKg1 m pipes =
Weight
9279 243.51
Weight Kg
of 1 m pipes =
3706 25.820 Kg
Weight of 1 m pipes =
10164 254.900
Weight ofKg1 m pipes =
9396 26.27 Kgof 1 m pipes =
Weight
9750 267.100
Weight ofKg1 m pipes =
8619 27.00
WeightKgof 1 m pipes =
9005 30.090
Weight Kg
of 1 m pipes =
8907 315.30 Kg
Weight of 1 m pipes =
3741 32.180 Kg
Weight of 1 m pipes =
9873 32.600
Weight Kg
of 1 m pipes =
9775 321.290
Weight ofKg1 m pipes =
9338 348.23
Weight Kg
of 1 m pipes =
9431 36.15 Kg
Weight of 1 m pipes =
9810 380.190
Weight ofKg1 m pipes =
9029 39.310
Weight Kg
of 1 m pipes =
8655 44.10
WeightKgof 1 m pipes =
9909 44.200
Weight Kg
of 1 m pipes =
3776 47.090 Kg
Weight of 1 m pipes =
9064 48.400
Weight Kg
of 1 m pipes =
9935 59.400 Kg
Weight of 1 m pipes =
9492 60.490 Kg
Weight of 1 m pipes =
3802 63.450
Weight Kg
of 1 m pipes =
8680 63.50 Kg
Weight of 1 m pipes =
9088 66.020
Weight Kg
of 1 m pipes =
9970 76.400 Kg
Weight of 1 m pipes =
9123 78.280
Weight Kg
of 1 m pipes =
3837 81.820 Kg
Weight of 1 m pipes =
10006 91.400
Weight Kg
of 1 m pipes =
9554 94.800 Kg
Weight of 10m pipes
3864 103.10x10 = pipes
Weight of 10m
9184 106.640x10
Weight of 10m pipes
9590 110.970x10
Weight of 10m pipes
3900 125.45x10 = 1254.50
Weight of 10m pipes Kg
9617 129.480x10
Weight of 10m pipes
9219 138.61x10
Weight of 10m pipes
8948 15.39x10
Weight of=10m
153.90 Kg
pipes
3937 151.270x10
Weight = pipes
of 10m
9654 168.680x10
Weight of 10m pipes
9371 17.76x10
Weight of=10m
177.60 Kg
pipes
3964 177.090x10
Weight of 10m pipes
9244 188.92x10
Weight of 10m pipes
3681 19.820x10 = 198.20
Weight of 10m pipesKg
9691 217.540x10
Weight of 10m pipes
8972 22.750x10 = 227.50
Weight of 10m pipesKg
4000 236.000x10
Weight of 10m pipes
9716 242.600x10
Weight of 10m pipes
9280 243.51x10
Weight of 10m pipes
3707 25.820x10 = 258.20
Weight of 10m pipesKg
9397 26.27x10
Weight of=10m
262.70 Kg
pipes
9751 267.100x10
Weight of 10m pipes
9305 282.74x10 = 2827.40
Weight of 10m pipes Kg
9006 30.090x10 = 300.90
Weight of 10m pipesKg
3742 32.180x10
Weight = 321.80
of 10m pipesKg
9776 321.290x10
Weight of 10m pipes
9339 348.23x10
Weight of 10m pipes
9432 36.15x10
Weight of=10m
361.50 Kg
pipes
9811 380.190x10
Weight of 10m pipes
9030 39.310x10 = 393.10
Weight of 10m pipesKg
3777 47.090x10 = 470.90
Weight of 10m pipesKg
9458 48.00x10
Weight of=10m
480.00 Kg
pipes
9065 48.400x10
Weight of 10m pipesKg
= 484.00
9493 60.490x10 = 604.90
Weight of 10m pipesKg
3803 63.450x10 = 634.50
Weight of 10m pipesKg
9089 66.020x10 = 660.20
Weight of 10m pipesKg
9124 78.280x10
Weight = 782.80
of 10m pipesKg
9529 79.730x10
Weight of 10m pipesKg
= 797.30
3838 81.820x10 = 818.20
Weight of 10m pipesKg
9160 91.410x10 = 914.10 Kg
Weight of 10m pipes
9555 94.800x10
Weight of 5=m 948.00
pipes Kg
10033 108.100x5
Weight of 5=m 540.50
pipes Kg
8752 110.00x5
Weight of 5 m pipesKg
= 550.00
10067 127.800x5
Weight of 5=m 639.00
pipes Kg
8777 135.70x5
Weight of=5678.50
m pipesKg
10103 147.900x5
Weight of 5=m 739.50
pipes Kg
8812 166.80x5
Weight of 5 m pipesKg
= 834.00
10129 198.900x5
Weight of 5=m 994.50
pipes Kg
8849 201.60x5
Weight of=51008.00
m pipes Kg
9848 21.700x5
Weight of=5108.50
m pipesKg
8874 234.80x5
Weight of 5 m pipes Kg
= 1174.00
10165 254.900x5
Weight of 5=m 1274.50
pipes Kg
8620 27.00x5
Weight of= 135.00
5 m pipes Kg
8908 315.30x5
Weight of=51576.50
m pipes Kg
9874 32.600x5
Weight of 5 m pipesKg
= 163.00
8656 44.10x5
Weight of= 220.50
5 m pipes Kg
9910 44.200x5
Weight of=5221.00
m pipesKg
9936 59.400x5
Weight of=5297.00
m pipesKg
8681 63.50x5 = 317.50
Weight of 5 m pipes Kg
9971 76.400x5
Weight of=5382.00
m pipesKg
8716 85.30x5
Weight of= 426.50
5 m pipes Kg
10007 91.400x5
Where Sin=Q457.00 Kg
= [R/(W/2)] =
16103 2R/W
Where Sin Q = [R/(W/2)] =
16246 2R/W
16002 Where W = D + X
16053 Where W = D + X
16073 Where W=D
White lead, + X and oil
hamp
6454 9999 etc. L.S. 6.76 2
2114 9999 White lead, hemp, oil etc. L.S. 8.06 2
2140 9999 White lead, hemp, oil etc. L.S. 8.06 2
2177 9999 White lead, hemp, oil etc. L.S. 9.49 2
2202 9999 White lead, hemp, oil etc. L.S. 9.49 2
2239 9999 White lead, hemp, oil etc. L.S. 13.52 2
2276 9999 White lead, hemp, oil etc. L.S. 13.52 2
2313 9999 White lead, hemp, oil etc. L.S. 8.06 2
2344 9999 White lead, hemp, oil etc. L.S. 8.06 2
2391 9999 White lead, hemp, oil etc. L.S. 5.33 2
2428 9999 White lead, hemp, oil etc. L.S. 5.33 2
2455 9999 White lead, hemp, oil etc. L.S. 6.76 2
2493 9999 White lead, hemp, oil etc. L.S. 6.76 2
2528 9999 White lead, hemp, oil etc. L.S. 9.49 2
2554 9999 White lead, hemp, oil etc. L.S. 9.49 2
2592 9999 White lead, hemp, oil etc. L.S. 13.52 2
2629 9999 White
Width lead,
of sand hemp,
fillingoil= etc. L.S. 13.52 2
6071 300mm
Width of sand filling =
6116 300mm
Width of sand filling =
6146 300mm
Width of sand filling =
6166 300mm
Width of sand filling =
6218 300mm
Width of sand filling =
6267 300mm
Width of sand filling =
6287 300mm
300mmDepth of sand
6199 filling
With 20 mm diameter
18960 19.15.2 round
With 20 barmm diameter
19075 19.17.2 round bar
With 20x20 mm square
18918 19.15.1 bar
With 20x20 mm square
19032 19.17.1 bar
with bolts, nuts and
7622 rubber insertions
with bolts, etc.
nuts and
7645 rubber insertions
with bolts, etc.
nuts and
7678 rubber
with insertions
bolts, etc.
nuts and
7701 rubber insertions
with bolts, nuts and etc.
7733 rubber insertions
with bolts, etc.
nuts and
7754 rubber insertions
with bolts, etc.
nuts and
7784 rubber
with insertions
bolts, etc.
nuts and
7805 rubber insertions
F.P.S. (non modular) etc.
10307 18.76.1 bricks
bricks of class designation
18414 19.10.1 7.5
bricks of class designation
18657 19.12.1 7.5
bricks of class designation
18879 19.14.1 7.5
bricks of class designation
20512 19.27.1 7.5
bricks of class designation
20565 19.28.1 7.5
bricks of class designation
20652 19.29.1 7.5
bricks of class designation
20758 19.30.1.1 7.5
bricks of class designation
21040 19.32.1 7.5
bricks of class designation
16324 19.4.1.1 7.5
bricks of class designation
16430 19.4.2.1 7.5
bricks of class designation
16544 19.4.3.1 7.5
bricks of class designation
17459 19.7.1.1 7.5
bricks of class designation
17688 19.7.2.2 7.5
bricks of class designation
17928 19.7.3.1 7.5
bricks of class designation
18130 19.8.1.1 7.5
bricks of class designation
18176 19.8.2.1 7.5
bricks of class designation
18226 19.9.1.1 7.5
F.P.S.(non modular) bricks
5147 18.32.1 of class designation
F.P.S.(non modular) 7.5
bricks
5211 18.33.1 of class designation 7.5
F.P.S.(non modular) bricks
5285 18.34.1 of class designation
F.P.S.(non modular) 7.5
bricks
5366 18.35.1 of class designation 7.5
F.P.S.(non modular) bricks
5436 18.36.1 of class designation
F.P.S.(non modular) 7.5
bricks
5519 18.37.1 of class designation
opaque white or as 7.5
6935 approved by
including installation of
23049 loading
including installation of
23140 loading
With Sewer bricks
18431 19.10.2 conforming
With Sewer IS : 4885
bricks
18681 19.12.2 conforming IS : 4885
With Sewer bricks
18901 19.14.2 conforming
With Sewer IS : 4885
bricks
16375 19.4.1.2 conforming to IS : 4885
With sewer bricks
16487 19.4.2.2 conforming
With Sewer to IS : 4885
bricks
16599 19.4.3.2 conforming to
With Sewer bricksIS : 4885
17536 19.7.1.2 conforming
With Sewer to IS : 4885
bricks
17766 19.7.2.2 conforming
With Sewer to IS : 4885
bricks
18026 19.7.3.2 conforming
With Sewer to IS : 4885
bricks
18147 19.8.1.2 conforming to
With Sewer bricksIS : 4885
18193 19.8.2.2 conforming
With Sewer to IS : 4885
bricks
18313 19.9.1.2 conforming
Wooden block to IS
@:14885
block
22853 per two piles
9999 Wooden block @ 1 block L.S. 442 2
22887 9999 per two piles
Wooden block @ 1 block L.S. 442 2
22927 9999 per two piles
Wooden block @ 1 block L.S. 442 2
22967 9999 per two piles
Wooden block @ 1 block L.S. 442 2
23009 9999 per two piles L.S. 442 2
19852 23 work
10371 Work
16220 Work
16271 Work
18515 Work
19222 Work
19249 Work
19285 Work
19326 Work
19351 Work
19390 Work
19429 Work
20496 Work
work in excavation for
11173 dismantling
work in excavation for
11204 dismantling
work in excavation for
11244 dismantling
work in excavation for
11286 dismantling
work in excavation for
11317 dismantling
work in excavation for
11355 dismantling
work in excavation for
11397 dismantling
work in excavation for
11469 dismantling
work in excavation for
11510 dismantling
work in excavation for
11551 dismantling
21785 Work supervisor
21823 Work supervisor
21863 Work supervisor
21902 Work supervisor
21933 Work supervisor
21971 Work supervisor
22009 Work supervisor
22047 Work supervisor
22093 Work supervisor
22134 Work supervisor
22166 Work supervisor
22206 Work supervisor
22318 Work supervisor
22357 Work supervisor
22394 Work supervisor
22435 Work supervisor
22465 Work supervisor
22509 Work supervisor
22552 Work supervisor
22593 Work supervisor
22633 Work supervisor
22675 Work supervisor
22703 Work supervisor
22736 Work supervisor
22771 Work supervisor
22819 Work supervisor
22862 Work supervisor
22903 Work supervisor
22935 Work supervisor
22976 Work supervisor
23018 Work supervisor
wt. = 121.5x10=1215kg =
4956 1.215t. say 1.22t
wt. = 150.5x10=1505 kg =
4982 1.5
wt. t. say 1.5 t
= 179.9x10=1799kg =
5018 1.799t.
wt. say 1.80t
= 229.9x10=2299kg =
5054 2299t. say 2.30t
wt. = 242.4x10=2424kg =
5080 2.424t. say 2.42t
wt. = 56.3x10=563kg =
4821 0.563t. say 0.56t
wt. = 68.3x10=683kg =
4856 0.68t say 0.68t
wt. = 72.5x10=725kg =
4882 0.725t. say 0.72t
wt. = 86.5x10=865kg =
4919 0.865t. say 0.865t
wt.= 44.3x10=443kg=
4759 0.443t.
X = 300 say
mm0.44t
as trench
16004 depth is
X = 300 mm less as
than
trench
16024 depth is less than
X = 300 mm as trench
16075 depth is less than
16261 x 3.14/180)] sqmm
19047 1006 #ERROR!
16843 1714 #ERROR!
16877 1715 #ERROR!
16122 4.1.10 #ERROR!
2626 #ERROR!
3965 #ERROR!
4001 #ERROR!
5178 #ERROR!
5181 #ERROR!
5257 #ERROR!
5326 #ERROR!
5443 #ERROR!
5479 #ERROR!
5552 #ERROR!
6076 #ERROR!
6079 #ERROR!
6121 #ERROR!
6126 #ERROR!
6151 #ERROR!
6156 #ERROR!
6171 #ERROR!
6176 #ERROR!
6203 #ERROR!
6208 #ERROR!
6223 #ERROR!
6228 #ERROR!
6257 #ERROR!
6272 #ERROR!
6277 #ERROR!
6292 #ERROR!
6295 #ERROR!
9185 #ERROR!
9220 #ERROR!
9245 #ERROR!
9281 #ERROR!
9340 #ERROR!
9591 #ERROR!
9618 #ERROR!
9655 #ERROR!
9692 #ERROR!
9717 #ERROR!
9752 #ERROR!
9777 #ERROR!
9812 #ERROR!
10319 #ERROR!
10325 #ERROR!
10369 #ERROR!
10410 #ERROR!
10431 #ERROR!
10467 #ERROR!
10490 #ERROR!
10524 #ERROR!
10554 #ERROR!
10577 #ERROR!
10609 #ERROR!
10632 #ERROR!
10665 #ERROR!
10702 #ERROR!
10725 #ERROR!
10757 #ERROR!
10780 #ERROR!
11136 #ERROR!
11177 #ERROR!
11208 #ERROR!
11248 #ERROR!
11290 #ERROR!
11321 #ERROR!
11359 #ERROR!
11401 #ERROR!
11442 #ERROR!
11473 #ERROR!
11514 #ERROR!
11555 #ERROR!
15800 #ERROR!
15886 #ERROR!
15966 #ERROR!
16001 #ERROR!
16008 #ERROR!
16021 #ERROR!
16028 #ERROR!
16029 #ERROR!
16052 #ERROR!
16059 #ERROR!
16072 #ERROR!
16079 #ERROR!
16080 #ERROR!
16100 #ERROR!
16102 #ERROR!
16110 #ERROR!
16113 #REF!
16115 #REF!
16117 #ERROR!
16118 #ERROR!
16119 #ERROR!
16208 #REF!
16210 #REF!
16212 Err:509
16213 Err:509
16214 #ERROR!
16215 #ERROR!
16218 #ERROR!
16245 #ERROR!
16251 #ERROR!
16258 #ERROR!
16260 #ERROR!
16262 #REF!
16264 Err:509
16265 #ERROR!
16266 #ERROR!
16308 Err:509
16309 Err:509
16310 #ERROR!
16311 #ERROR!
16338 #ERROR!
16341 #ERROR!
16388 #ERROR!
16392 #ERROR!
16451 #ERROR!
16501 #ERROR!
16505 #ERROR!
16558 #ERROR!
16562 #ERROR!
16613 #ERROR!
16617 #ERROR!
16851 #ERROR!
16891 #ERROR!
16895 #ERROR!
16925 #ERROR!
16978 #ERROR!
17108 #ERROR!
17112 #ERROR!
17142 #ERROR!
17146 #ERROR!
17188 #ERROR!
17192 #ERROR!
17231 #ERROR!
17235 #ERROR!
17275 #ERROR!
17279 #ERROR!
17316 #ERROR!
17320 #ERROR!
17362 #ERROR!
17366 #ERROR!
17406 #ERROR!
17410 #ERROR!
17503 #ERROR!
17504 #ERROR!
17513 #ERROR!
17709 #ERROR!
17735 #ERROR!
17736 #ERROR!
17745 #ERROR!
17972 #ERROR!
17974 #ERROR!
17984 #ERROR!
17985 #ERROR!
17995 #ERROR!
18043 #ERROR!
18044 #ERROR!
18051 #ERROR!
18052 #ERROR!
18073 #ERROR!
18081 #ERROR!
18083 #ERROR!
18084 #ERROR!
18094 #ERROR!
18251 #ERROR!
18260 #ERROR!
18263 #ERROR!
18264 #ERROR!
18281 #ERROR!
18351 #ERROR!
18360 #ERROR!
18369 #ERROR!
18502 #ERROR!
18509 #ERROR!
18512 #ERROR!
18530 #ERROR!
18615 #ERROR!
18623 #ERROR!
18631 #ERROR!
18735 #ERROR!
18751 #ERROR!
18818 #ERROR!
18837 #ERROR!
18845 #ERROR!
19012 #ERROR!
19220 #ERROR!
19247 #ERROR!
19283 #ERROR!
19324 #ERROR!
19349 #ERROR!
19388 #ERROR!
19427 #ERROR!
19486 #ERROR!
19488 #ERROR!
19489 #ERROR!
19533 #ERROR!
19535 #ERROR!
19536 #ERROR!
19567 #ERROR!
19569 #ERROR!
19570 #ERROR!
19636 #ERROR!
19648 #ERROR!
19699 #ERROR!
19701 #ERROR!
19711 #ERROR!
19718 #ERROR!
19723 #ERROR!
19913 #ERROR!
19942 #ERROR!
19960 #ERROR!
19961 #ERROR!
19968 #ERROR!
20019 #ERROR!
20034 #ERROR!
20035 #ERROR!
20078 #ERROR!
20083 #ERROR!
20099 #ERROR!
20100 #ERROR!
20209 #ERROR!
20244 #ERROR!
20274 #ERROR!
20282 #ERROR!
20283 #ERROR!
20340 #ERROR!
20394 #ERROR!
20443 #ERROR!
20482 #ERROR!
20484 #ERROR!
20493 #ERROR!
20708 #ERROR!
20712 #ERROR!
20835 #ERROR!
20848 #ERROR!
20858 #ERROR!
20860 #ERROR!
20931 #ERROR!
20939 #ERROR!
21047 #ERROR!
21061 #ERROR!
21064 #ERROR!
22498 #ERROR!
22541 #ERROR!
22582 #ERROR!
22622 #ERROR!
20425 -20
20376 -10
7188 0.87
7200 1.15
7217 1.21
7246 1.32
7229 1.6
7192 12.36
7196 15.05
7213 16.12
7242 16.12
1116 17
1119 17
1154 17
1222 17
1249 17
1356 17
7221 17.19
1121 18
8976 18.23 metre
9696 18.23 metre
10169 18.23 metre
7250 18.75
1114 19
1152 19
1220 19
1247 19
1354 19
7225 20.93
7254 22.83
17778 23
17779 24
20465 35
7211 105
7240 116
7204 116.55
7202 116.56
7231 162.05
7233 162.05
21237 367 metre
21657 367 metre
17017 657.05
17015 657.07
45 1424
95 1425
143 1426
191 1427
234 1428
284 1429
338 1430
385 1431
432 1432
483 1433
532 1434
581 1435
632 1436
680 1437
731 1438
779 1439
834 1440
885 1441
941 1442
994 1443
1046 1444
1102 1445
1206 1446
1326 1447
1396 1448
1444 1449
1489 1450
1542 1451
1589 1452
1639 1453
1690 1454
1744 1455
1794 1456
1846 1457
1898 1458
1950 1459
2002 1460
2050 1461
2107 1462
2156 1463
2210 1464
2260 1465
2309 1466
2362 1467
2410 1468
2462 1469
2512 1470
2566 1471
2619 1472
2668 1473
2716 1474
2767 1475
2819 1476
2875 1477
2928 1478
2985 1479
3038 1480
3084 1481
3130 1482
3178 1483
3226 1484
3274 1485
3319 1486
3368 1487
3418 1488
3468 1489
3515 1490
3570 1491
3615 1492
3667 1493
3721 1494
3769 1495
3821 1496
3875 1497
3926 1498
3980 1499
4029 1500
4081 1501
4132 1502
4179 1503
4231 1504
4280 1505
4331 1506
4381 1507
4429 1508
4482 1509
4535 1510
4588 1511
4640 1512
4693 1513
4745 1514
4793 1515
4843 1516
4894 1517
4941 1518
4991 1519
5042 1520
5091 1521
5140 1522
5192 1523
5241 1524
5294 1525
5352 1526
5406 1527
5455 1528
5512 1529
5563 1530
5614 1531
5667 1532
5721 1533
5774 1534
5827 1535
5879 1536
5931 1537
5985 1538
6037 1539
6089 1540
6136 1541
6193 1542
6250 1543
6307 1544
6363 1545
6413 1546
6462 1547
6513 1548
6564 1549
6615 1550
6666 1551
6716 1552
6764 1553
6812 1554
6861 1555
6909 1556
6960 1557
7012 1558
7063 1559
7112 1560
7260 1561
7309 1562
7363 1563
7415 1564
7464 1565
7513 1566
7564 1567
7612 1568
7663 1569
7714 1570
7765 1571
7816 1572
7866 1573
7913 1574
7962 1575
8006 1576
8057 1577
8108 1578
8159 1579
8208 1580
8261 1581
8314 1582
8367 1583
8418 1584
8473 1585
8528 1586
8583 1587
8637 1588
8689 1589
8741 1590
8792 1591
8838 1592
8890 1593
8942 1594
8994 1595
9048 1596
9102 1597
9156 1598
9206 1599
9261 1600
9318 1601
9366 1602
9418 1603
9472 1604
9525 1605
9576 1606
9632 1607
9684 1608
9736 1609
9789 1610
9837 1611
9892 1612
9944 1613
9996 1614
10049 1615
10096 1616
10147 1617
10199 1618
10249 1619
10298 1620
10348 1621
10401 1622
10454 1623
10503 1624
10548 1625
10594 1626
10643 1627
10698 1628
10744 1629
10792 1630
10844 1631
10897 1632
10950 1633
11003 1634
11056 1635
11109 1636
11160 1637
11218 1638
11273 1639
11332 1640
11383 1641
11436 1642
11490 1643
11542 1644
11601 1645
11652 1646
11705 1647
11758 1648
11809 1649
11860 1650
11905 1651
11959 1652
12010 1653
12061 1654
12106 1655
12155 1656
12204 1657
12259 1658
12303 1659
12353 1660
12403 1661
12457 1662
12505 1663
12551 1664
12596 1665
12643 1666
12692 1667
12743 1668
12790 1669
12838 1670
12886 1671
12934 1672
12988 1673
13036 1674
13088 1675
13136 1676
13186 1677
13238 1678
13288 1679
13336 1680
13389 1681
13443 1682
13493 1683
13546 1684
13595 1685
13649 1686
13700 1687
13750 1688
13803 1689
13853 1690
13903 1691
13956 1692
14008 1693
14062 1694
14112 1695
14165 1696
14215 1697
14263 1698
14317 1699
14367 1700
14422 1701
14475 1702
14527 1703
14577 1704
14625 1705
14678 1706
14730 1707
14781 1708
14829 1709
14878 1710
14930 1711
14983 1712
15030 1713
15077 1714
15131 1715
15182 1716
15241 1717
15325 1718
15438 1719
15506 1720
15575 1721
15620 1722
15669 1723
15719 1724
15771 1725
15826 1726
15876 1727
15929 1728
15981 1729
16040 1730
16096 1731
16163 1732
16241 1733
16304 1734
16360 1735
16414 1736
16474 1737
16529 1738
16585 1739
16639 1740
16689 1741
16738 1742
16788 1743
16837 1744
16887 1745
16940 1746
17047 1747
17101 1748
17153 1749
17201 1750
17247 1751
17298 1752
17344 1753
17395 1754
17450 1755
17499 1756
17551 1757
17669 1758
17725 1759
17775 1760
17906 1761
17959 1762
18013 1763
18064 1764
18111 1765
18167 1766
18219 1767
18272 1768
18329 1769
18389 1770
18441 1771
18494 1772
18549 1773
18611 1774
18667 1775
18715 1776
18774 1777
18833 1778
18892 1779
18945 1780
18997 1781
19042 1782
19095 1783
19147 1784
19205 1785
19257 1786
19311 1787
19365 1788
19421 1789
19472 1790
19526 1791
19583 1792
19630 1793
19685 1794
19742 1795
19795 1796
19847 1797
19901 1798
19955 1799
20014 1800
20070 1801
20123 1802
20178 1803
20238 1804
20298 1805
20358 1806
20415 1807
20475 1808
20530 1809
20585 1810
20640 1811
20699 1812
20750 1813
20797 1814
20854 1815
20910 1816
20962 1817
21025 1818
21082 1819
21134 1820
21182 1821
21229 1822
21276 1823
21324 1824
21375 1825
21424 1826
21470 1827
21595 1828
21643 1829
21693 1830
21755 1831
21805 1832
21851 1833
21897 1834
21944 1835
21991 1836
22037 1837
22080 1838
22128 1839
22173 1840
22218 1841
22286 1842
22338 1843
22382 1844
22430 1845
22473 1846
22517 1847
22563 1848
22612 1849
22662 1850
22709 1851
22756 1852
22801 1853
22848 1854
22894 1855
22940 1856
22985 1857
23031 1858
23081 1859
23127 1860
23176 1861
23232 1862
23292 1863
23351 1864
21542 2523.79
21544 2523.8
21573 3301.15
21571 3301.17
1147 8306
1215 8307
1243 8308
1270 8309
1349 8310
1107 8635
15220 8926
15258 8927
15285 8928
15337 8929
15363 8930
15389 8931
15459 8932
15486 8933
15523 8934
15550 8935
1149 9999
1217 9999
1245 9999
1272 9999
1351 9999
5283 :
5364 :
6969 :
18461 :
18697 (-)
: 0.02 cum =
17479 0.16 cum
17951 (1
(-) cement
0.021 cum
:4
19624 coarse sand)
17613 steel
(inside)
@
5558 80kg/cum.
17611 allowable
(low duty)lateral
23247 load on pile :
(0.76)³ =0.083
18823 cum
[R²/2(3.14/2-Q)]
16232 -4x(0.15)²(-)
(3.14/2)R² =
20092 0.0216 cum =
48.06 kg/cum
17591 10.57 kg cum
m = 0.061
16444 Total
80.09=0.107
kg/cumcum=
17826 24.83 kg
3)1/2] = 0.017
16447 cum
qm. Total =
5235 2.16sqm.
1.06mx1.06mx0.
20571 15
m =m= 0.17cum
0.426 cum
19879 Say
m = 0.43
0.547cum
cum
17934 Say
m = 1.178cum
0.55 cum
18574 Say 1.18 cum
m = 1.178 cum
20059 Say 1.18 cum
0.68x0.68x0.10
16440 m = 0.046 cum
6240 10 metre long.
7194 100.35 Y
7334 sqm
108 gms
For 10 m
16172 length
7198 floating
115.41 Zcoat of
20902 neat cement
plaster 1:3 (1
17570 cement
floating :coat
3 of
17482 neat
floating coat of
17807 neat
7215 121.12 W
7219 122.33 X
7244 132.12 W
7248 133.44 X
7223 Width
139.52of Y sand
6316 filling = 300mm
7252 160
152.19
mmY Outer
1161 dia
7227 160.45 Z
15215 18.100.1
15544 18.100.10
15252 18.100.2
15280 18.100.3
15332 18.100.4
15358 18.100.5
15384 18.100.6
15454 18.100.7
15480 18.100.8
15518 mm
18.100.9
nominal
3409 bore
inner hinged
7490 round grating
1141 18.6A
1143 18.6A.1
1211 18.6A.2
1239 18.6A.3
1266 18.6A.4
1345 of
18.6A.5
class
18463 designation
conforming IS 7.5:
18562 4885
of class
18699 designation
conforming IS 7.5:
18792 4885
internal
19301 dimension
560 mm internal
19376 diameter
560 mm internal
19406 dia
of class
20818 designation
of class 7.5
designation
20888 of class 7.5
20974 designation
of class 7.5
20992 designation
of class 7.5
21010 designation
0.20m = 0.727.5
19994 cum
1.20x3.14/4x(0.1
17950 5m)² = 600 mm
20.2A.1
22301 dia piles 750 mm
20.2A.2
22333 dia piles 1000
20.2A.3
22371 20.2A.4
mm dia piles
1200
22409 mm dia piles
20.2A.5 1500
22449 mm dia 450
20.4.3 pilesmm
22723 dia
2.5 piles
times the
23045 1.5
Safetimes
capacity)
the
23065 Safe capacity)
2.5 times the
23136 Safe capacity)
1.5 times the
23156 Safe capacity)
400 tonne Safe
23221 capacity of group
1163 1x0.90x3.14/4x(0
20xP/100
17563 .15m)²
1x0.90x3.14/4x(0
17477 .15m)² =
1.20x3.14/4x(0.1
5m)²
17799 0.018 cum Say
18596 0.02
gradedcumstone
18321 aggregate
graded stone
18570 aggregate
3.14/4x(1.05)²x0.
19416 15 = 0.1299 cum
(4/3)x3.14x(0.61)
18602 ³³ =0.043 cum
Total =0.043
20090 cum
1.069 Total =
18584 1.320
1.069 Total=
18481 1.320
= 0.08 sqm
17485 Total= 0.25 sqm
= 0.08 sqm
17575 Total=
x1.00 m0.25 sqm
= 0.88
21016 cum
15m = 1.037 cum
20002 =pipes
2.561 cum
= 79.730
9519 Kg
0)²x(100x100)/
10690 1000x0.5 gms
19894 44 graded
graded stone
stone
17949 aggregate
0/2) x
19948 (0.30+0.20)/2
mm nominal
17474 size) for
2x0.56x0.15 m=
18058 0.17 sqm
2.10 sqm
17718 2x½x0.90x0.10m
20187 4.32x0.23x0.35
4.25 m depth)
17545 m = 0.348 cum
4.32x0.23x0.35
19885 m40=mm0.348 cum
nominal
18572 size)
1.67x1.67x0.225
m = 0.63
18323 40mm cum
nominal
5449 size)
iron pipes (in 5.5
9148 m5 =lengths)
0.027 cum =
17939 0.811 cumcum
m = 1.178
Say 1.18 cum
18471 2.74x2.74x0.30
18707 m = 2.25 cum
4.32x0.23x0.35
17467 m = 0.348 cum
7186 87.12 W
7190 tar
87.99 X
9999
17617 Sundries
Add 1 % Water
1171 charges
Add 1 % on "W"
Water 322.28
1191 charges
Add 1 % on "W"
Water 1.39
1289 Add
charges
1 % on "W"
Water 1.88
1307 charges on
Add 1 % Water"W" 2.28
1371 charges
Add 1 % on "W"
Water 4.44
7119 charges
Add 1 % on "W"
Water
7146 Add
charges
1 % on "W"
Water
7173 charges on
Add 1 % Water"W"
15231 charges
Add 1 % on "W"
Water 1.91
15295 charges
Add 1 % on "W"
Water 2.05
charges on
15312 Add 1 % Water "W" 2.05
15399 charges
Add 1 % on "W"
Water 2.05
15416 charges
Add 1 % on "W"
Water 2.87
15469 charges
Add 1 % on "W"
Water 4.78
charges on
15496 Add 1 % Water "W" 4.78
15533 charges
Add 1 % on "W"
Water 6.83
16949 charges
Add 1 % on "W"
Water
21511 charges
profit andon "W"
1175 profit
overheads
and on "Y" 5568.5
1195 overheads
profit and on "Y" 24.07
1293 overheads
profit and on "Y" 32.53
1311 overheads on "Y" 39.48
profit and
1375 overheads
profit and on "Y" 76.73
7127 overheads
profit and on "Y"
7154 overheads
profit and on "Y"
7181 overheads
profit and on "Y"
15299 overheads
profit and on "Y" 35.42
15316 overheads
profit and on "Y" 35.42
15403 overheads
profit and on "Y" 35.42
15420 overheads
profit and on "Y" 49.59
15473 overheads
profit and on "Y" 82.59
15537 overheads
profit and on "Y" 118.01
16957 overheads
profit and on "Y"
23239 overheads
overheads onon "Y"
"Y" 5097.18
16999 Total
overheads on "Y"
21519 Total
and wastage etc.
1162 on
AddP,Cess @ 1% 5114.6
1177 on
Add"Z"
Cess @ 1% 426.92
1197 on "Z"
Add Cess @ 1% 1.85
on "Z"
1295 Add Cess @ 1% 2.49
1313 on "Z"
Add Cess @ 1% 3.03
1377 on
Add"Z"
Cess @ 1% 5.88
7131 on "Z"
Add Cess @ 1%
7158 Add
on "Z"
Cess @ 1%
15301 on "Z"
Add Cess @ 1% 2.72
15318 on
Add"Z"
Cess @ 1% 2.72
15405 on "Z"
Add Cess @ 1% 2.72
15422 Add
on "Z"
Cess @ 1% 3.8
15475 on "Z"
Add Cess @ 1% 6.33
15539 on
Add"Z"
Cess @ 1% 9.05
16961 on "Z"
Add Cess @ 1%
23086 Add
on "Z"
Cess @ 1% 198.7
23241 on "Z"
cost for 10 metre 390.78
21521 Rate
factorper metreon
0.1405)
1173 "X"
factor 0.1405) on 4573.28
1193 "X"
factor 0.1405) on 19.77
1291 "X"
factor 0.1405) on 26.72
1309 "X"
factor 0.1405) on 32.42
1373 "X"
factor 0.1405) on 63.02
7123 "X"
factor 0.1405) on
7150 "X"
factor 0.1405) on
7177 "X"
factor 0.1405) on
15233 "X"
factor 0.1405) on 27.1
15297 "X"
factor 0.1405) on 29.09
15314 "X"
factor 0.1405) on 29.09
15401 "X"
factor 0.1405) on 29.09
15418 "X" 40.73
factor 0.1405) on
15471 "X"
factor 0.1405) on 67.83
15498 "X"
factor 0.1405) on 67.83
15535 "X"
factor 0.1405) on 96.92
16953 "X"
factor 0.1405) on
16995 "X"
factor 0.1405) on
21515 "X"
factor 0.1405) on
23237 "X"
x (0.30+0.20)/2 = 4186.2
19895 0.18 cum cum
m = 0.426
17463 Say 0.43 cum
7184 +Amount
(91)² (Cot Q -
16150 3.14 + Q)(Cot Q -
+ (117)²
16206 3.14 + Q)+ 30625
[211250
16294 (1/0.6387
Area = WxD1 - 180°
+
2x½xR= Cot
16132 Area WxD1 QxR+
16230 2x½xR
2x½xR Cot QxR --
Cot QxR
16185 [R²/ 2(3.14/2-
[R²/2(3.14/2-Q)]
16278 -cement
(3.14/2)R²
: 3 fine
18594 sand )
17476 benching
17562 benching
17798 Bleaching
benching
10688 powder
Total deduction
20578 =bottom
0.011 cum
of pile
22065 cap).
0x0.23m = 0.327
20009 cum
extruded brunt
18592 fly
cement: 4 coarse
21014 sand)
5.52mx0.23mx1.
20000 20m = 1.524
cement: cum
4 coarse
18883 sand)
bricks of class
18475 cement
designation
: 4 75 in
17938 coarse sand)
extruded brunt
18578 fly ash clay
extruted brunt
17787 fly ash clay
22656 Bulb - 0.033 cum
17483 cement
17574 cement
17716 2x½x0.90x0.10m
cement
=
17808 mm 0.09sqm
nominal size
19414 )mm nominal
17561 size) for
mm nominal size
18820 )Cement concrete
18319 Cement
1:3:6 (1 cement
concrete:
18568 1:3:6
1:3:6 (1 cement ::
(1 cement
18469 3 coarse
1:3:6 sand : :
(1 cement
18705 3 coarse sand :
mm nominal
18032 size)
m = 0.547 cum
17783 Say
mm 0.55 cum
nominal
20569 size)
1:4 (1 cement : 4
18477 coarse sand)
aggregate 20
17489 mm
40 mm nominal
19992 size)
floating coat of
17572 neat
floating coat of
17714 neat
floating coat of
18056 neat cement
1105 Code
1209 complete
Code as per
19004 design.
making good the
202 wall
makingetc.good the
walls etc.
1625 3.14/4x(0.40)²x2
22794 0 = 2.51 cum
Concrete around
16442 trap
1198 Cost of 1 each 186.36
1296 Cost of 1 each 251.92
1314 Cost of 1 each 305.71
1378 Cost of 1 each 594.17
1179 Cost of 1 metre 4311.87
16965 Cost
Cost of
of 1
1 metre
metre
21952 pile
Cost of 1 metre 5634.95
22186 pile
Cost of 1 metre 2561.27
22226 pile
Cost of 1 metre 3936.12
22484 pile
Cost of 1 metre 17607.44
22530 pile
Cost of 1 metre 2238.5
22571 pile 2727.82
7133 Cost of 1 no.
7160 Cost of 1 no.
15302 Cost of 1 no. 274.28
15319 Cost of 1 no. 274.28
15406 Cost of 1 no. 274.28
15423 Cost of 1 no. 383.99
15476 Cost of 1 no. 639.53
15540 Cost of 1 no. 913.81
1178 Cost of 10 metre 43118.72
6327 Cost
Cost of
of 10
10 metre
metre 3976.28
22529 pile
Cost of 10 metre 22384.99
22570 pile
Cost of 10 27278.22
16963 metres
Cost of 15 metre
21951 pile
Cost of 15 metre 84524.18
22225 pile
Cost of 20 metre 59041.85
22185 pile
Cost of 9 metre 51225.33
22483 pile 158466.96
Cost of one
6328 metre 397.63
23087 Cost per test 20069.06
23131 Cost per test 30772.57
23242 3.14x1.45x0.24x
Cost per test 39469.16
18479 0.23 = 0.251
3.14x1.45x0.24x
18582 0.23 = 0.251
3.14x1.45x0.24x
20065 0.23
+ (½ x= 182)
0.251= 241
16146 mm
+ (½ Rx 234)
= 91 mm
= 267
16197 mm
+ (½ x 350) = 325
16290 mm
0.23m R ==175 mm
0.008
20004 cum
16446 Deduct:
19989 Above
deep the pipe =
6318 150mm+
21111 Detail
design.for 10
21481 metre
Detail of cost for
11583 one
one cut.
pit test (Ten
pits inmone
23299 0.61 day)
extra
18659 depth
cement : 4
18683 coarse
cementsand):4
18433 coarse sand)
1.88 m extra
18881 depth
Details of cost
20255 for 0.61ofmetre
Details cost
22652 for 1 bulb.
Details of cost
22752 for 1 bulb.
Details of cost
17930 Details
for 1 manhole
of cost
18028 for 1 manhole
Details of cost
18315 for 1 manhole
Details of cost
18465 for 1 manhole
Details of cost
18564 Details
for 1 manhole
of cost
18701 for 1 manhole
4 coarse sand : 8
17461 graded
Details ofstone
cost
7336 for 1 no.
Details of cost
7356 for 1 no.of cost
Details
7402 for 1 no.of cost
Details
12249 for 1 no.of cost
Details
13081 for 1 no.of cost
Details
for 1 no.of cost
13230 Details
13381 for 1 no.of cost
Details
13639 for 1 no.of cost
Details
14398 for 1 no.of cost
Details
15122 Details
for 1 no.of cost
15225 for 1 no.of cost
Details
15290 for 1 no.of cost
Details
15307 for 1 no.
Details of cost
15394 for 1 no.of cost
Details
15411 for 1 no.of cost
Details
15428 for 1 no.of cost
Details
15464 for 1 no.of cost
Details
15491 for 1 no.of cost
Details
15528 for 1 no.of cost
Details
15555 for 1 no.of cost
Details
23251 for 1 test
Details of cost
10357 for 10 holes
Details of cost
38 for 10 metre
Details of cost
131 for 10 metre
Details of cost
690 for 10 metre
Details of cost
792 for 10 metre
Details of cost
for 10 metre
820 Details of cost
858 for 10 metre
Details of cost
897 for 10 metre
Details of cost
925 for 10 metre
Details of cost
for 10 metre
963 Details of cost
1024 for 10 metre
Details of cost
1063 for 10 metre
Details of cost
1092 for 10 metre
Details of cost
1469 Details
for 10 metre
of cost
1771 for 10 metre
Details of cost
1993 for 10 metre
Details of cost
2096 for 10 metre
Details of cost
2613 Details
for 10 metre
of cost
5768 for 10 metre
Details of cost
8933 for 10 metre
Details of cost
9144 for 10 metre
Details of cost
9515 Details
for 10 metre
of cost
9677 for 10 metre
Details of cost
15997 for 10 metre
Details of cost
16830 for 10 metre
Details of cost
17389 for
for 10
10 metre
metre
16130 length pipe
for 10 metre
16228 length pipe
[R²/2(3.14/2-Q)]
16091 -Details
(3.14/2)R²
of cost
for 100 of
10684 Details metres
cost
10830 for 100 metres
Details of cost
10884 for 100 of
Details metres
cost
10937 for 100 metres
Details of cost
10990 Details
for 100 of
metres
cost
11043 for 100 metres
Details of cost
11096 for 100 of
Details metres
cost
1183 for 1No.
Details of cost
1279 for 1No.of cost
Details
1299 for 1No.of cost
Details
1317 for 1No.of cost
Details
1361 for
for 1No.
20 m length
22790 of pile
Details of cost
15820 for
for 30 metre
40.26 m or 11
11427 nos. joints.
excavation forEarth
11131 dismantling
Details of cost
10089 for 5 metre
Details of cost
6916 for 500 litresof 10
for a depth
6447 metre
Details of cost
5287 for one of
Details chamber
cost
20567 for one
for one chamber
19516 connection
Details of cost
19124 for one of
Details cover
cost
19156 for one cover
Details of cost
19179 for
for one
one cover
M.S foot
19034 rests
Details of cost
20324 for one of
Details manhole
cost
20467 for one manhole
for one manhole
20378 Dismantling
for one manhole of
20427 Details
Dismantling
of costof
21012 for one metre
Details of cost
3411 for one of
Details no.cost
6506 for one of
Details no.cost
6853 Details
for one of
no.cost
7945 for one no.cost
Details of
10187 for one of
Details no.cost
19006 for one of
Details no.cost
19303 for
for one
one no.
no.
7604 water meter
Details of cost
21113 for one soak
a manhole pit
1.22
20054 m internal
140x90 cm and
2.45
19987 cm andm 45 cm
19875 deep
dismantling one
20189 manhole
sand filling
6314 alround
alround 65mm
6238 dia. pipe
21489 diameter
dia 1.68 m
20056 deep
Engineer in-
19871 charge
graded :stone
20228 1.178
aggregate
cum.40mm
Say
20257 1.18 cum.
aggregate stone
20057 40 mm
1:4:8 (1nominal
cement :
19990 4
aggregate stone
19877 40
1:4mm nominal
(1 cement :4
20063 coarse sand 8
1:4 (1 cement : 4 )
19998 coarse sand)
15776 2x½x3.14x0.25m
DRAINAGE
18586 x0.230x0.10
x0.230 = 0.008 m
18483 cum
12750 Elbow 90°
13003 Equal Tee
1431 Exposed on wall
2092 Exposed on wall
345 External work
1767 External work
2381 Extra
External workfor
labour
making
17603 Extra channel
labour for :
17837 making
Connector/ channel :
14349 Adapter
Female Thread
13908 Tee
Threaded Elbow
15017 90°
mm nominal dia
15223 threaded
mm nominal dia
15288 threaded
mm nominal dia
15305 threaded
mm nominal dia
15392 threaded
mm nominal dia
15409 threaded
mm nominal dia
15426 threaded
mm nominal dia
15462 threaded
mm nominal dia
15489 threaded
mm nominal dia
15526 threaded
mm nominal dia
15553 threaded
3.14/4x(1.52)²x0.
18822 20 = 0.363 cum
1.36x1.26x0.15m
17491 0.61x0.455x0.15
= 0.257 cum
17579 m0.7854x(0.50)²x0
17819 .15m
sqm = 0.442 sqm
17595 Say 0.44 sqm
1.20x0.90 = 1.08
sqm
17830 mm nominal size
18600 )1x0.96x0.20x0.2
For benching :
20692 0 m Tan Q =
Hence
16204 0.4877
020x0.15 m
20095 =0.123 cum
20816 -inlets :
EXPOSED ON
10 WALL
10836 LABOUR
10890 LABOUR
10943 LABOUR
10996 LABOUR
11049 LABOUR
11102 LABOUR
15923 LABOUR
17601 LABOUR
17835 LABOUR
21499 LABOUR
1164 LABOUR:
1187 LABOUR:
1285 LABOUR:
1303 LABOUR:
1367 0.61x0.455m
LABOUR: =
17597 (-) 0.278
0.884 sqmsqm Say
17832 0.88 sqm
3.14/4x(0.28)² x
20097 0.15 m : (-)
0.61x0.455x0.15
17493 m
1x0.90x3.14/4x(0
19896 .15m)²
x0.23m==(-)(-)
19887 0.008 cum
2x3.14x(0.15m)²
17556 x0.23m
2x3.14x(0.15m)²
17791 x0.23m
2x3.14x(0.15m)²
17941 x0.23m
x0.23m = (-)
17469 0.008 cum
pipe :1.22x3.14/
18605 4x(0.15)²(-)
4x(0.15)²(-) =
18827 0.027 cum
19177 less than 108 kg
19154 Connector/
less than 58 kg
14630 Adapter
13453 Male
Male Threaded
Thread Tee
15212 Elbow
Mason90O(brick
17839 layer) 1st
Mason (brickclass
17841 layer) 2nd class
133 MATERIAL
1471 MATERIAL
1995 MATERIAL
2098 MATERIAL
6855 MATERIAL
7606 MATERIAL
8935 MATERIAL
9146 MATERIAL
9517 MATERIAL
10189 MATERIAL
10686 MATERIAL
10832 MATERIAL
10886 MATERIAL
10939 MATERIAL
10992 MATERIAL
11045 MATERIAL
11098 MATERIAL
12251 MATERIAL
13383 MATERIAL
13641 MATERIAL
15124 MATERIAL
15227 MATERIAL
15291 MATERIAL
15308 MATERIAL
15395 MATERIAL
15412 MATERIAL
15429 MATERIAL
15465 MATERIAL
15492 MATERIAL
15529 MATERIAL
15556 MATERIAL
17932 MATERIAL
18030 MATERIAL
18317 MATERIAL
18467 MATERIAL
18566 MATERIAL
18703 MATERIAL
19036 MATERIAL
19305 MATERIAL
19518 MATERIAL
22654 MATERIAL
22792 MATERIAL
23301 MATERIAL
692 MATERIAL:
794 MATERIAL:
822 MATERIAL:
860 MATERIAL:
899 MATERIAL:
927 MATERIAL:
965 MATERIAL:
1026 MATERIAL:
1065 MATERIAL:
1094 MATERIAL:
1184 MATERIAL:
1281 MATERIAL:
1300 MATERIAL:
1318 MATERIAL:
1363 MATERIAL:
21483 391.50mm
MATERIALSSay
:
6320 0.392m
76.6mm = 301.6
6244 Say 302mm
17027 metre
21552 reinforcement
metre
17589 for slab :
reinforcement
17824 for slab nominal
15 mm :
15229 dia
15 mmthreaded
nominal
15293 dia threaded
20 mm nominal
15310 dia
25 mmthreaded
nominal
15397 dia threaded
25 mm nominal
15414 dia
32 mmthreaded
nominal
15431 dia threaded
32 mm nominal
15467 dia
40 mmthreaded
nominal
15531 dia threaded
50 mm nominal
15558 dia
X40threaded
mm nominal
dia threaded
15494 0.45x0.23x0.10
20575 m
cum Say 2.54
20007 cum
0.008 = 0.340
19889 cum
- 0.0216 = 0.26
20093 cum
cum Say 0.43
20580 cum
1.294 Say 1.29
18487 cum
1.294 Say 1.29
18589 cum
17490 nominal size)
17578 nominal size)
17815 nominal size)
20229 not
nominal size) 23
less than
19122 kg
machine shall
22067 not be used15.00
= 0.30x50= .
15921 kg
21498 per
partsstandard
Sand)
20650 design :
21763 refilling
PILE WORK of
11430 excavated earth
1160 PPR
PN-10 (SDR 11) -
Union
20mm
1182 PPR Union
1277 25mm
PPR Union
1298 32mm
PPR Union
1316 40mm
PPR Union
1359 50mm
Providing and
1181 fixing PPR Unions
pipe with
10193 P.T.M.T.
WD1 + R²(Cot Nuts Q -
16189 3.14
WD1++Q) R²(Cot Q)
16187 - R²(3.14/2 -
16203 Qty
Q= 26°0'
for 2.45m
20232 depth
0.486 cum Say
20230 0.49 cum
qty. of concrete
16174 reqd.
10 = (-)0.22cum.
6322 = 2.13 cum.
16199 cement:
R = 117 mm 1.5
20690 coarse
no 13.9.1 of :SH
sand 3:
17812 Finishing
21475 Rate per metre
12294 Reducing
Reducer Elbow
12870 90°
13123 Engineer-in-
Reducing Tee
12868 charge.
2.40x0.75=1.80s
5233 qm.
coat of neat
18886 cement
1180 Say
1199 Say
1297 Say
1315 Say
1379 Say
6329 Say
7135 Say
7162 Say
15303 Say
15407 Say
15424 Say
15477 Say
15541 Say
16967 Say
21477 Say
21523 Say
21953 Say
22187 Say
22227 Say
22485 Say
22531 Say
22572 Say
22997 Say
23039 Say
23088 Say
23132 Say
23243 5.12x0.23x0.80
Say
17789 m
1:4=(1
0.942
cementcum: 4
18580 coarse
cementsand)
:4
19883 size)
coarseForsand)
20088 benching
cement : 2:
19893 coarse sand :=
(2x117)/534
16201 0.4382 therefor
Q = 32°34' Hence
16292 Tan Q = 0.6387
Q = 22°12' Hence
16148 Tan Q = 0.4081
19878 size)
20058 Slip
size)Coupling/
12619 Socket
2 SUB HEAD : 18.0
15774 SUB HEAD : 19.0
21760 SUB HEAD : 20.0
6325 supply
4887 Supply)
7943 than 85 gms
1170 TOTAL 32227.75
1172 TOTAL 32550.03
1174 TOTAL 37123.31
1176 Total 42691.8
1190 TOTAL 139.29
1192 TOTAL 140.68
1194 TOTAL 160.45
1196 Total 184.52
1288 TOTAL 188.29
1290 TOTAL 190.17
1292 TOTAL 216.89
1294 Total 249.43
1306 TOTAL 228.49
1308 TOTAL 230.78
1310 TOTAL 263.2
1312 Total 302.68
1370 TOTAL 444.09
1372 TOTAL 448.53
1374 TOTAL 511.55
1376 Total 588.28
6326 TOTAL 3976.28
7117 TOTAL
7121 TOTAL
7125 TOTAL
7129 Total
7144 TOTAL
7148 TOTAL
7152 TOTAL
7156 Total
7171 TOTAL
7175 TOTAL
7179 TOTAL
15230 TOTAL 191
15232 TOTAL 192.91
15234 TOTAL 220.01
15294 TOTAL 205
15296 TOTAL 207.05
15298 TOTAL 236.14
15300 Total 271.56
15311 TOTAL 205
15313 TOTAL 207.05
15315 TOTAL 236.14
15317 Total 271.56
15398 TOTAL 205
15400 TOTAL 207.05
15402 TOTAL 236.14
15404 Total 271.56
15415 TOTAL 287
15417 TOTAL 289.87
15419 TOTAL 330.6
15421 Total 380.19
15468 TOTAL 478
15470 TOTAL 482.78
15472 TOTAL 550.61
15474 Total 633.2
15495 TOTAL 478
15497 TOTAL 482.78
15532 TOTAL 683
15534 TOTAL 689.83
15536 TOTAL 786.75
15538 Total 904.76
16947 TOTAL
16951 TOTAL
16955 TOTAL
16959 Total
16997 TOTAL
21509 TOTAL
21513 TOTAL
21517 TOTAL
21949 Total 84141.85
22177 TOTAL 48183.46 W
22179 TOTAL 48273.47 X
22181 TOTAL 49550.8 Y
22183 Total 51106.09 Z
22223 Total 58911.82
22477 TOTAL 146652.31 X
22479 TOTAL 151764.74 Y
22481 Total 157989.71 Z
22521 TOTAL 18093.73 W
22523 TOTAL 18220.72 X
22525 TOTAL 20022.68 Y
22527 Total 22216.78 Z
22568 Total 27109.63
22989 TOTAL 140583.83
22991 TOTAL 143308.04
22993 Total 146625.07
23035 Total
23085 Total 19870.36 Z
23236 TOTAL 29795 X
23238 TOTAL 33981.2 Y
23240 Total
Total = 0.026 39078.38 Z
18485 cum
Total = 0.340
17470 cum
17566 Total= 0.16 cum
18603 Total= 0.277 cum
18825 Trenching
Total= 0.446 andcum
refilling
1167 the pipeetc.
=
6243 150mm+
14863 W
Valve Connector
= 182 + 300 =
16144 482 mm
W = 234 + 300 =
16195 W
534= mm350 + 300 =
16288 650 mm
+ 16 + 16 = 182
16142 mm
200+ 17 + 17 =
16193 234
+ 25mm + 25 = 350
16286 mm
Wall : 2.90x0.30
20904 m = 0.87 sqm
4 pipes
WATER SUPPLY
= 91.410
9150 Kg
[R/(W/2)] =
16191 2R/W
[R/(W/2)] =
16284 2R/W
Depth of sand
6241 filling
excavation for
11429 dismantling
16175 #ERROR!
16234 #ERROR!
16280 #ERROR!
16282 #ERROR!
16296 #ERROR!
16298 Err:509
17720 #ERROR!
17821 #ERROR!
17953 #ERROR!
18587 #ERROR!
19950 #ERROR!
20005 #ERROR!
20576 #ERROR!
20694 #ERROR!
1
5187
9731
12882
16145
17002
17005 4911.06 W
17006 49.11
17007 4960.17 X
17008 696.9
17009 5657.08 Y
17010 848.56
17011 6505.64 Z
17012 65.06
17013 6570.69
17014
17016
17018
17019
17020
17021
17022
17023
17036 5789.06 W
17037 57.89
17038 5846.95 X
17039 821.5
17040 6668.45 Y
17041 1000.27
17042 7668.71 Z
17043
17360 metre
17386
20190
21549
21561 24673.54 W
21562 246.74
21563 24920.27 X
21564 3501.3
21565 28421.57 Y
21566 4263.24
21567 32684.81 Z
21568 326.85
21569 33011.65
21570
21572
218.58 A
36.24 A
45.5 A
57.13 A
71.83 A
81.84 A
101.98 A
1323.96 A
1323.96 A
264.79 A
264.79 A
595.79 A
595.79 A
1668.75 A
2148.93 A
3601.3 A
4460.87 A
5332.24 A
1313.07 A
1668.75 A
2024.44 A
2563.89 A
6814.32 A
7184.82 A
8992.89 A

2795.6 A
2771.61 A
2735.61 A
2691.05 A
2838.46 A
2958.44 A
3049.28 A
3109.27 A
3124.7 A
3150.41 A
3126.41 A
2989.29 A
51.42 A
45.03 A
56.53 A
70.98 A
89.25 A
101.69 A
126.71 A
159.7 A
187.06 A
1185.25 A
5957.92
2142.98 A

4285.95
428.6 A
428.6 A
4553.94
4553.94
5395.99
5396
539.6 A
539.6 A
5957.92
8263

8396.93
8396.93
2030.64 A
2013.21 A
1987.06 A
1954.69 A
2061.76 A
2148.92 A
2214.9 A
2258.48 A
2269.68 A
2288.36 A
2270.93 A
2171.33 A

16.12
16.12
107.64
27.04
2985.26 A
A
10028.52
8434.344 A
23.2
620 X
620 X
620 X

30

5800

71
46.5
57

71

116
105
780 X
780 X
780 X
200570.31
325

97
1100 X
1100 X
1100 X
1570 X
1570 X
1570 X

A
2350.00 X
2350 X
3300 X
3300 X
W
4400
4400
2300
9000
9000
5000
194.92
574.66
17.01
19.81

33.63
13.73
17.85
22.28
14.66
19.77
26.04
34.8
16.8
20.14
36.09
37.09
55.09
55.09
85.93

128.99
219.63
286.59
386.8
463.45
611.61
740.68
859.68
1203.37
241.42
270.53
260.53
320.64
360.68
400.82
751.15
891.42

1.24
1.4
0.79
-0.05
2.57
1.62
0.27
0.27
0.41
0.41
0.54
0.54
0.16
0.16
0.22

0.27
0.27
0.16
0.16
0.22
0.22

0.24
0.27
0.3
372.8
453.8
592.56
24.2
35.59
52.85
57.69
28.1
45.26
57.48
81.72
51.99
62.09
85.8
90.57
124.09
172.09
130.59
187.59
65.62
102.59
162.21
195.7
250.05
315.07
408.2
520.34
646.99
897.18
80.23
114.39
140.63
180.89
226.1

319.61
387.78
437.58
563.87
733.87
913.87

1237.73
76.73
115.39
158.13

276.1
336.55
432.11
502.58

759.87

1140.8
1152.73

1562.73
55.12
82.69
104.06
147.95
190.05
239.77
308.55
323.94
460.29
609.43
719.79
5.85
16.08
5.33
0.27
17.84
20.39
23.01
25.83
30.9
36.24
41.13
46.01
51.07
56.15
61.21
71.36
19.81
31.68
6.26
6.26
6.7
6.7
7.76
7.76
13.74

43.42
43.42
89.5

9.79
9.79
10.13
10.13
10.13
10.13

1.85
2.14
2.56
2.27
7.16
6.16
6.16
7.17
6.22
9.48
12.38
2.23
2.24
2.96
28.79
40.5
7.18
10.74
0.14
0.14
0.3
0.3
0.04
0.04
0.3

0.48
0.55
0.57
6.45
2.4
9.01
14.56
13.79
13.53

13.27
180.47
213.9
252.65
249.49
288.62
290.8
286.21
326.71
73.67
76.64
98.16
286.51
281.56
289.32
295.06
360.27
127.27
126.82
127.38
10.04
10.13
10.19
10.6
191.97
221.5
191.97
191.97
191.97
191.97
14.27
16.95
21.71
28.88
41.34
53.69
13.19
15.27
19.43
25.54
36.61
48.96
12.44
16.1
20.34
29.31
39.79
10.32
13.62
18.5
25.38
36.32
41.35
57.72

116.31
2.76
5.75
10.24
13.13
17.53
22.18
29.74
40.52
59.57
11.44
15.24
20.38
26.88
35.79

110.67
141.58
200.68
424.27
16.85
20.79
27.32
33.42
39.85
49.06
14.53
17.49
23.21
27.7
31.78
37.91
48.17
59.41
3.39
8.46
2.89
2.26
2.44
2.26
2.44
3.72
3.44
4.34
5.07
6.5
11.12
16.58

2.89
2.94
3.57
3.77
4.8
5.3
5.92
7.32
8.55
9.35
15.28
15.38
21.61
25.41
2.21
2.54
3.28
0.54
0.59
0.62
0.75

1.41
6.04
15.51
17.6
25.99
26.44
35.06
43.83
52.79
54.33
70.91
79.53
84.16
113.52
176.09
9.9
16.02
17.02
20.16
22.26
30.88

42.97
61.33
75.92
86.46
101.49
13.95
16.43
19.5
22.7
7.77
29.79
7.86
1.21
1.4
1.99
2.32
2.83
3.72

6.86
2.97
3.16
3.75
4.08
4.59
6.11
8.66
9.25
32.88
32.88
3.13
4.63
4.13
4.53
3.98
0.46
1.71
0.87
1.13
1.5
1.44
1.57
0.78
0.73
0.28
0.38
1.26
1.43
1.89
3.54
5.44
9.34
1.16
0.84
0.98
26.21
40.38
61.34
74.3
99.76
107.76
174.69
202.15
215.88
279.49
389.9
444.9
489.33
629.22
736.64
0.71
0.84
0.37
0.61
0.85
6.12

10.14
12.23
16.41
20.76
23.24
25.83
28.58
31.39
34.38

2.24
2.75
3.38
3.96
6.13
7.05
7.93
9.33
10.75
12.23
13.73
16.79
0.51
0.69
0.96
1.3
1.74
2.15
2.59
3
3.44
3.86

5.1
58.16
19.87
31.73
37.43
50.67
52.58
70.33
0.59
0.63
0.89
1.31
1.58

1.03
1.41
1.45
1.84
1.87
1.9
3.59
3.62
3.62
3.87
4.1
4.1
4.1
4.1

0.47
0.63
0.89
1.31
1.58
1.7
0.58
0.63
0.96
1.09
1.16
1.5
1.91
2.21

1.59
2.31
2.73
4.37
6.83
8.87

2.73
2.73
4.37
4.37
4.37
6.83
6.83
6.83
6.83
8.87
8.87
8.87

1.79
2
2.05
2.73
2.73
2.73
4.37
4.37
4.37
4.37
6.83
6.83
6.83
6.83
6.83
8.87
8.87
8.87
8.87
8.87
8.87
1.79
2

2.73
2.73
2.73
4.37
4.37
4.37
4.37
6.83
6.83
6.83
6.83
6.83
8.87
8.87
8.87
8.87
8.87
8.87
1.9
2.3
2.37
2.77
2.86

5.38

9.65

2.27

3.13
3.2

6.49
2.76
2.95
4.24
6.29

11.76

1.91
1.91

4.78

0.45
0.64
0.84
1.63
2.36
2.99
2.14
2.71
4.07
55.36
91.24
153.84
233
327.61
2.73
3.02
3.21
3.4
3.59
4.14
4.52
4.72
27.3
30.05

95.37
114.49
136.26
177.45
212.91
290.19
339.51
378.27
420.57
9.63
23.65
50.71
4.92
2.42
3.25
164.93
215.24
338.93
419.29
550.63
1010.45
188.63
473.33
587.29
697.63
1426.14
400

450
230
500

150
230

6.38
108.2

237.33

750.28
750.28

169.09
169.09

174.97
174.97
174.97

32.04
36.99
44.2
39.22
123.64
106.36
106.36
123.85
107.44
163.73
213.84
38.46
38.64
51.11
497.41
699.72
124.15
185.53
2.47
2.47
5.26
5.26
0.63
0.63
5.27

8.22
9.48
9.79
111.44
41.48
155.71
251.51
238.21
233.77
229.32
293.91
342.29

581.16
237.27
308.42
384.97
253.24
341.68
449.93
601.27
290.27
347.96
623.66
640.94
951.95
951.95
1484.78

2228.71
3794.87
4951.93
6683.43
8007.7
10567.73
12797.85

20792.45
4171.31
4674.34
4501.56
5540.23
6232.02
6925.53
12978.82

21.42
24.12
13.58
-0.83
44.36
27.93
4.67
4.67
7.01
7.01
9.3
9.3
2.79
2.79
3.73

4.67
4.67
2.79
2.79
3.73
3.73

4.22
4.67
5.12
6441.45
7841.02
10238.59
418.14
614.94
913.17
996.8
485.53

993.17

1072.9
1482.58
1565
2144.17
2973.54
2256.48
3241.36
1133.75
1772.67
2802.83
3381.36
4320.55
5444.02
7053.19
8990.71
11179.04

1386.29
1976.44
2429.87
3125.59
3906.77

5522.39
6700.24
7560.72
9742.81
12680.16
15790.31

21386.26
1325.82
1993.72
2732.24

4770.7
5815.04
7466.23
8683.82

13129.41

19711.39
19917.58

27001.79
952.33

1798.09
2556.31
3283.83
4142.94
5331.38
5597.2
7953.13
12436.92
101.16
277.8
92.17
4.67
308.19
352.36
397.5
446.38
533.85
626.24
710.63
794.95
882.5
970.18
1057.64
1232.95
342.34
547.38
3118.25
3695.91
4365.39
4310.75
5024.65
4945.33
5645.14
1272.84
1324.21
4950.53
4864.9
4999.08
5098.15
2191.23
2200.95
173.52
175.05
176.07
183.14
3317.03
3827.27
3317.03
3317.03
3317.03
246.64
292.94
375.17
498.97
714.23
927.62
227.89
263.83
335.71
441.28
632.49
845.88
214.93
278.13
351.41
506.42
687.54
178.34
235.41
319.73
438.59
627.59
714.47
997.39

2009.6
47.7
99.33
176.98
226.79

383.26
513.91
700.08
1029.26

263.38
352.07
464.5
618.34

1912.24
2446.28

7330.8
291.22
472.1
577.41
688.49
847.64
251.05
302.22
401.02
478.68
549.12
655.11
832.25
1026.45

146.22
49.87
39.07

39.07
42.16
64.2
59.43

87.61
112.25
192.18
286.43

49.9
50.88
61.69
65.15
82.87
91.51
102.33
126.52
147.75
161.57
263.96
265.69
373.31
438.97
38.12
43.95
56.61
9.41
10.27
10.72
12.97

24.38
104.28
267.97
304.16
449.1
456.91
605.86
757.25
912.07
938.78
1225.27
1374.08
1454.15
1961.51
3042.66
171.01
276.76
294.04
348.4
384.69
533.55

742.49
1059.63
1311.76
1493.98
1753.52
241.09
283.84
336.98
392.23
134.22
514.77
135.73
20.96
24.24
34.43
40.14
48.95
64.3
118.56
51.25
54.53
64.72
70.43
79.24
105.61
149.67
159.86
568.15
568.15
54.11
79.91
71.33
78.3
68.7
7.91
29.48
15.05
19.55
25.85
24.88
27.12

12.63
4.89
6.62
21.83
24.74
32.63
61.25
94.08
161.46
20.06
14.43
16.85
898.39
452.93
697.75
1059.92
1283.87
1723.79
1862.02
3018.33
3492.82
3730.06
4829.2
6736.85
7687.17
8454.99
10871.96
12728.05
12.26
14.52

10.5
14.65
105.66

175.29
211.25
283.61
358.79
401.63
446.25
493.85
542.38
593.96

38.67
47.53
58.43
68.5
105.98
121.83
136.97
161.22
185.83
211.37
237.18
290.12
8.89
11.96
16.67
22.49
30.01

44.72
51.92
59.39
66.63

88.18

343.28
548.33
646.82
875.46
908.56
1215.2
10.19
10.89
15.38
22.63
27.3

17.8
24.36

31.79
32.31
32.83
62.03

62.55
66.87
70.84
70.84
70.84
70.84

8.12
10.89
15.38

27.3
29.37
10.02
10.89
16.59
18.83

25.92

33
38.19

27.47

47.17
75.51
118.01
153.26

47.17
47.17
75.51
75.51
75.51
118.01

118.01
118.01
153.26
153.26
153.26

30.93
34.56
35.42
47.17

47.17
75.51
75.51
75.51
75.51
118.01

118.01
118.01
118.01
153.26

153.26
153.26
153.26
153.26
30.93
34.56

47.17
47.17
47.17
75.51

75.51
75.51
118.01
118.01

118.01
118.01
153.26
153.26
153.26
153.26

153.26

39.74
40.95
47.86
49.42

92.96

166.74

39.22

54.08

112.14
47.69
50.97
73.26
108.68

203.2

33
33

82.59

7.78
11.06
14.51
28.16
40.78
51.66
36.98
46.82
70.32
956.58
1576.44
2658.1
4025.88

47.12

55.43
58.76
62.09
71.51
78.16
81.49
471.71
519.25
1647.82
1978.29
2354.46
3066.06
3678.82
5014.08
5866.23
6535.94
7266.85
166.36
408.71
876.15
85.01

56.15
2849.8
3718.96

7244.8
9514.17

3259.31
8178.55
10147.6
12054.12
24641.72
6911.43

7775.36
3974.07
8639.29

2591.79
3974.07

110.24
241.61
378.33
26
48.6
59.4
84.6
88.2
122
26
48.6
214.94
86.54

214.94
322.14
504.44
563.46
836.36
1195.26
1771.66
39
72.9
89.1
126.9
132.3
183
39
72.9
186
234
330
471
990
145.65
233.4
340.8
490.95
686.1
1125.75
2379.9
3093.15
4400.25
9435.45
186
234
330
471
705
990
705
145.65
233.4
340.8
490.95
686.1
1125.75
129.81
200.4
537.35
465
585
825
1177.5
364.13
583.5
852
1227.38
324.53
501
22.53
26.24

44.56
18.19
23.65
29.51
19.41
26.2
34.49
46.1
22.25
26.68
47.81
49.14
72.98
72.98
113.83

170.87
290.94
379.65
512.4
613.92
810.19
981.17

1594.09
319.8
358.37
345.12
424.75
477.79
530.96
995.04

1.64
1.85

-0.06
3.4
2.14
0.36
0.36
0.54
0.54
0.71
0.71
0.21
0.21
0.29

0.36
0.36
0.21
0.21
0.29
0.29

0.32
0.36
0.39
493.84
601.14
784.96
32.06
47.15
70.01

37.22

76.14
113.66

164.39
227.97
173
248.5
86.92
135.9
214.88
259.24
331.24
417.37
540.74
689.29
857.06

106.28
151.53
186.29
239.63
299.52

423.38
513.69
579.65
746.95
972.15
1210.59

1639.61
101.65
152.85
209.47

365.75
445.82
572.41
665.76

1006.59

1527.01
2070.14
73.01

137.85
195.98
251.76
317.63
408.74
429.12
609.74

953.5
7.76
21.3
7.07
0.36

27.01
30.48

40.93
48.01
54.48
60.95
67.66
74.38
81.09
94.53
26.25
41.97
8.3

18.2

57.52
57.52

12.96
12.96
13.41
13.41
13.41

2.46
2.84
3.39
3.01
9.48
8.15
8.15
9.5

12.55
16.39
2.95
2.96
3.92
38.13
53.65
9.52
14.22
0.19
0.19
0.4
0.4
0.05
0.05
0.4

0.73
0.75
8.54
3.18
11.94
19.28
18.26
17.92

17.58
239.07
283.35
334.68
330.49
385.22
379.14
432.79
97.58
101.52
379.54
372.98
383.26
390.86
167.99
168.74
13.3
13.42
13.5
14.04
254.31
293.42
254.31
254.31
18.91
22.46

38.25
54.76

17.47
20.23

33.83
48.49
64.85
16.48
21.32
26.94
38.83
52.71
13.67
18.05

33.63
48.12
54.78
76.47
154.07
3.66
7.62
13.57
17.39

29.38
39.4

78.91

20.19
26.99
35.61
47.41

146.61
187.55

562.03
22.33

36.19
44.27
52.78
64.99

23.17
30.74
36.7
42.1
50.23
63.81
78.69

11.21
3.82
3

3
3.23
4.92
4.56

6.72
8.61
14.73
21.96

3.83

4.73
4.99
6.35
7.02
7.85
9.7
11.33
12.39
20.24
20.37
28.62
33.65

3.37
4.34
0.72
0.79
0.82
0.99

1.87
7.99
20.54
23.32
34.43
35.03
46.45

69.93
71.97
93.94
105.35
111.49
150.38
233.27
13.11
21.22
22.54
26.71
29.49
40.91

56.92
81.24
100.57
114.54
134.44
18.48
21.76
25.83

10.29
39.47
10.41
1.61
1.86
2.64
3.08
3.75
4.93

9.09
3.93
4.18
4.96
5.4
6.07
8.1
11.47
12.26
43.56
43.56
4.15
6.13
5.47
6
5.27
0.61

2.26
1.15
1.5
1.98
1.91
2.08

0.97
0.38
0.51
1.67
1.9
2.5
4.7
7.21
12.38

1.11

68.88
34.72
53.49
81.26
98.43
132.16
142.76
231.41
267.78
285.97

516.49
589.35
648.22
833.52
975.82
0.94
1.11

0.8
1.12
8.1

13.44
16.2

27.51
30.79
34.21
37.86
41.58
45.54

2.96
3.64
4.48
5.25
8.13
9.34
10.5
12.36
14.25
16.21
18.18
22.24

0.92
1.28
1.72
2.3

3.43
3.98
4.55
5.11

6.76

26.32
42.04
49.59
67.12
69.66
93.17
0.78

1.18
1.74
2.09

1.36
1.87

2.44
2.48
2.52
4.76

4.8

5.43

5.43
5.43

0.62
0.83
1.18

2.09
2.25
0.77
0.83
1.27
1.44

1.99

2.53
2.93

2.11

3.62
5.79
9.05
11.75

3.62

5.79
5.79
5.79
9.05

9.05

11.75
11.75
11.75

2.37
2.65
2.72
3.62

3.62

5.79
5.79
5.79
9.05

9.05
9.05
9.05
11.75

11.75

11.75
11.75
2.37
2.65

3.62
3.62
3.62
5.79

5.79
5.79
9.05
9.05

9.05

11.75
11.75
11.75
11.75

11.75
3.05
3.14
3.67
3.79

12.78

3.01

4.15

8.6

3.66
3.91
5.62
8.33

15.58

2.53

6.33

0.6
0.85
1.11
2.16
3.13
3.96
2.83
3.59
5.39
73.34
120.86
203.79
308.65

3.61

4.25
4.51
4.76
5.48
5.99
6.25
36.16
39.81

126.33
151.67
180.51
235.06
282.04
384.41
449.74
501.09
557.13
12.75
31.33
67.17
6.52

4.3
218.48
285.12

555.43
729.42

249.88
627.02
777.98
924.15
1889.2
529.88
596.11
304.68
662.35

198.7
304.68

8.45

27.04
27.04
40.56
40.56
53.82
53.82
16.12
16.12
21.58
21.58
24.44
24.44
27.04
29.64
32.24
16.12
16.12
21.58
21.84
27.04
27.04
80.6
40.3
41.34
53.82
241.38
281.11

477.3
194.87
253.3
316.17
207.98
280.62
369.52
493.81
238.39
285.77
512.2
526.39
781.82
781.82
1219.42

1830.38
3116.64
4066.91
5488.95
6576.54
8679.04
10510.58

17076.37
3425.8
3838.93
3697.03
4550.06
5118.22
5687.78
10659.21
12649.63

17.59
19.81
11.16
-0.68
36.44
22.93
3.84
3.84
5.76
5.76
7.64
7.64
2.29
2.29
3.06

3.84
3.84
2.29
2.29
3.06
3.06

3.47
3.84
4.21
5290.22
6439.65
8408.72
343.41
505.04
749.97
818.65
398.75
642.26
815.67
1159.65
881.15
1217.61
1285.3
1760.96
2442.1
1853.2
2662.06
931.12
1455.85
2301.9
2777.04
3548.37
4471.05
5792.63
7383.87
9181.09
12731.48
1138.53
1623.2
1995.59
2566.97
3208.54

4535.41
5502.76
6209.44
8001.54
10413.93
12968.22

17564.04
1088.87
1637.39
2243.93

3918.06
4775.76
6131.84
7131.83

10782.88

16188.51
16357.85

22175.96
782.12
1173.46
1476.73
2099.44
2696.94
3402.5
4378.54
4596.85
6531.73
8648.16
10214.16
83.08
228.15
75.7
3.84
253.11
289.38
326.46
366.6
438.44
514.31
583.63
652.88
724.78
796.79
868.62
1012.6
281.15
449.55
88.86

110.12

616.19
616.19

138.87
138.87

143.7
143.7
143.7

26.31
30.38
36.3
32.21
101.54
87.35
87.35
101.72
88.24
134.47
175.62
31.58
31.73
41.97
408.51
101.96
152.37
2.03
2.03
4.32
4.32
0.52
0.52
4.33

6.75
7.78
8.04
91.52
34.07
127.88
206.56
195.64
191.99

188.34
2560.95
3035.37
3585.19
3540.32
4095.62
4126.63
4061.49
4636.22
1045.35
1087.55
1392.9
4065.76
3995.44
4105.63
4186.99
1806.08
1799.61
1807.59
142.51
143.77
144.61
150.41
2724.2
3143.25
2724.2
2724.2
2724.2
202.56
240.58
308.12
409.8
586.58
761.83
187.16
216.68
275.71
362.41
519.45
694.7
176.51
228.42
288.61
415.91
564.66
146.47
193.33
262.59
360.21
515.42
586.78
819.13

1650.44
39.18
81.58
145.35
186.25

314.76
422.06
574.96
845.31

216.31
289.15
381.48
507.83

1570.48
2009.08

6020.62
239.17
295.05
387.73
474.21
565.44
696.15
206.18
248.21
329.35
393.13
450.98
538.03
683.51
843

120.08
40.96
32.09
34.62
32.09
34.62
52.73
48.81

71.95
92.19
157.83
235.24

40.99
41.79
50.67
53.5
68.06
75.16
84.04
103.91
121.34
132.7
216.79
218.21
306.59
360.52
31.3
36.1
46.49
7.73
8.43
8.8
10.65

20.03
85.64
220.08
249.8
368.84
375.25
497.58
621.91
749.06
771
1006.29
1128.5
1194.26
1610.94
2498.87
140.44
227.3
241.49
286.13
315.93
438.19

609.79
870.25
1077.32
1226.97
1440.13
198
233.11
276.75
322.13
110.23
422.77
111.48
17.21
19.91
28.28
32.96
40.2
52.81

97.37
42.09
44.78
53.16
57.84
65.08
86.73
122.92
131.29
466.61
466.61
44.44
65.63
58.58
64.3
56.42
6.5
24.21
12.36
16.05
21.23
20.43
22.28

10.38
4.02
5.44
17.93
20.32
26.79
50.3
77.26
132.61
16.48
11.85
13.84
737.83
371.98
573.05
870.49
1054.41
1415.71
1529.24
2478.89
2868.57
3063.41
3966.11
5532.82
6313.3
6943.89
8928.89
10453.26
10.07
11.93

8.62
12.03
86.78

143.96
173.49
232.92
294.66
329.85
366.49
405.59
445.45
487.81

31.76
39.03
47.99
56.26
87.04
100.06
112.49
132.41
152.62
173.59
194.79
238.27
7.3
9.82
13.69
18.47
24.64

36.73
42.64
48.77
54.72

72.42
825.34
281.93
450.33
531.22
719
746.18
998.02
8.37
8.94
12.63
18.59
22.42

14.62
20.01

26.11
26.54
26.96
50.94

51.37
54.92
58.18
58.18
58.18
58.18

6.67
8.94
12.63
18.59
22.42
24.12
8.23
8.94
13.62
15.47

21.29

27.1
31.36

22.56
32.78
38.74
62.01
96.92
125.87

38.74
38.74
62.01
62.01
62.01
96.92

96.92
96.92
125.87
125.87
125.87

25.4
28.38
29.09
38.74

38.74
62.01
62.01
62.01
62.01
96.92
96.92
96.92
96.92
96.92
125.87

125.87
125.87
125.87
125.87
25.4
28.38

38.74
38.74
38.74
62.01
62.01
62.01
62.01
96.92
96.92

96.92
96.92
125.87
125.87
125.87
125.87

125.87
26.96
32.64
33.63
39.31
40.58

76.34

136.94

32.21

44.42
45.41
92.1

39.17
41.86
60.17
89.26

166.88

27.1
27.1

67.83

6.39
9.08
11.92
23.13
33.49
42.43
30.37
38.46
57.76
785.62
1294.69
2183.04
3306.36
4648.92
38.7
42.8
45.53
48.26
50.99
58.73
64.19
66.93
387.4
426.45
1353.32
1624.73
1933.66
2518.09
3021.33
4117.95
4817.8
5367.81
5968.1
136.63
335.67
719.56
69.82
34.31
46.11
2340.48
3054.3
4809.65
5949.99
7813.77

2676.79
6716.86
8334
9899.78
20237.68
5676.2

6385.73
3263.82
7095.25

2128.58
3263.82

90.53
33194.11 A
40970.72 A
49582.4 A
113569.79 A
163882.88 A
247.17
307.09
367.01
367.01
490.6
490.6
247.17
247.17
247.17
247.17
307.09
367.01
367.01
490.6
490.6
247.17
247.17
247.17
307.09
367.01
367.01
367.01
490.6
490.6
247.17
247.17
247.17
247.17
247.17
307.09
367.01
367.01
490.6
614.18
247.17
247.17
63.67
232.19
374.5
561.75
561.75
749
936.25
1123.5
1123.5
1498
1685.25
1778.88
2434.25
56.18
93.63
93.63
112.35
112.35
149.8
149.8
187.25
187.25
224.7
243.43
280.88
374.5
561.75
749
936.25
1123.5
1123.5
1498
1685.25
1778.88
2434.25
2883.65
2883.65
3183.25
3745
4119.5
187.25
235.94
280.88
329.56
411.95
486.85
561.75
655.38
749
842.63
936.25
1123.5
247.17
247.17
247.17
247.17
247.17
247.17
247.17
247.17

211.7478
211.75
211.75
314.41
420.29
420.29
211.75
211.75
211.75
211.75
51.33
211.75
51.33
211.75
51.33
211.75
51.33
211.75
105.87
211.75
105.87
211.75
211.75
211.75
211.75
420.29
420.29
211.75
211.75
211.75
51.33
211.75
80.21
211.75
80.21
211.75
105.87
211.75
105.87
211.75
211.75
211.75
211.75
211.75
311.21
256.66
311.21
256.66
35.29
35.29
35.29
211.75
211.75
211.75
314.41
420.29
420.29
211.75
211.75
211.75
211.75
51.33
211.75
51.33
211.75
80.21
211.75
80.21
211.75
105.87
211.75
105.87
211.75
211.75
211.75
211.75
211.75
311.21
256.66
494.08
385
211.75
211.75
211.75
314.41
420.29
526.16
211.75
211.75
51.33
211.75
51.33
211.75
80.21
211.75
80.21
211.75
105.87
211.75
105.87
211.75
211.75
211.75
211.75
211.75
105.87
144.37
105.87
426.7
795.66
641.66
962.49
962.49
1283.32
1604.15
1924.98
1924.98
2566.64
2887.47
3047.89
4170.79
256.66
320.83
320.83
352.91
352.91
417.08
417.08
481.25
481.25
545.41
577.49
641.66
28.87
962.49
1122.91
1283.32
54.54
240.62
32.08
35.29
35.29
35.29
35.29
35.29
48.12
48.12
48.12
105.87
105.87
105.87
105.87
105.87
144.37
144.37
144.37
320.83
962.49
1283.32
1604.15
1924.98
1924.98
2566.64
2887.47
3047.89
4170.79
4940.78
4940.78
5454.11
6416.6
7058.26
401.04
535.79
320.83
420.29
526.16
632.04
737.91
946.45
1158.2
1264.07
1369.94
1472.61
1578.48
1684.36
1896.11
157.21
182.87
211.75
237.41
288.75
352.91
417.08
481.25
545.41
609.58
673.74
802.08
1283.32
1443.74
1604.15
1764.57
2085.4
2406.23
2727.06
3047.89
3368.72
3689.55
4010.38
4652.04
19.25
25.67
35.29
48.12
64.17
80.21
96.25
112.29
128.33
144.37
160.42
192.5
211.75
211.75
211.75
211.75
211.75
211.75
211.75
211.75
962.49
1283.32
1443.74
1764.57
1924.98
157.21
157.21
157.21
157.21
157.21
192.5
211.75
211.75
202.12
250.25
481.25

481.25
519.74
587.12
660.91
731.49
962.49
1389.19
2021.23
2781.6
32.08
16.04
32.08
16.04
16.04
32.08
32.08
32.08
32.08
38.5
38.5
38.5
9.62
80.21
80.21
105.87
866.24
1122.91
12.83
16.04
962.49
160.42
19.25
25.67
773.2
587.12
962.49
1389.19
2781.6
4170.79
773.2

962.49
1389.19
2781.6
4170.79
641.66
641.66
641.66
641.66
1122.91
1283.32
1443.74
1604.15
802.08
802.08
962.49
1122.91
962.49
1122.91
1283.32
1443.74
1604.15
641.66
641.66
641.66
641.66
320.83
320.83
320.83
320.83
962.49
3458.55
962.49
962.49
962.49
962.49

740
828.8
976.8
888
976.8
888
1036
1139.6
1332
236.8
444
562.4
592
8.88
17.76
23.68
29.6

320.83
320.83
401.04
481.25
481.25
51.33
51.33

105.87
105.87
105.87
134.75
134.75
160.42
160.42
192.5
214.96
6.42
9.62
105.87
105.87
160.42
160.42
214.96
320.83
105.87

160.42
160.42
214.96
320.83
37.45
37.45
37.45
37.45
14.4
21.6
32.4
48.6
84.6
133.2
190.8
259.2
340.2
430.2
531
763.2
5.4
7.2
10.8
16.2
28.8
45
63
86.4
113.4
144
176.4
253.8

440
880
960
1200
1360
1920
1920
2880
4480
5600
6400
7600
210
225
350
410
480
620
1080
1620
210
225

4491.5
2684.5

1233
778.5

A
477
477
477
477
477
477
40.22
40.22
54.42
54.42
65
65
3840
3840
3840
3840
3840
3840
3840
3840
3840
3840
3840
3840
3840
3840
477
140
160
220
24100
26000
36000
75000
109800
155000
27000
32000
40000
89000
145000
182000
375
290
40
385
430
430

27.04
13.78
13.78
13.78
13.78
13.78
13.78
22.62
3.64
5.4

52
52
52
1589.64
199.57

41.04
26.94
32.24
13.52

13.52
13.52
27.04
27.04
14.3
14.3
14.3
257.75
128.88
2.86
16.12
14.3
41.51
52.83
52.83
64.15
67.92
81.6
115.09
141.51
169.81
216.98
228.3
9.43
9.43
9.43
9.43
285.84
9.43
9.43
9.43
9.43
9.43
9.43
9.43
9.43
773.26
38.66
62.89
89.37
110.47
154.65
210.89
257.75
257.75
386.63
386.63
386.63
579.95
1.79
3.4
5
8.87
11.79
0.47
0.57
0.85

2.26
2.45
3.02
3.49
3.96
4.62
5.19
5.75
6.41
0.12
0.18
1.13
1.51
2.36
2.64
3.21
4.62
1.13

2.64
3.21
4.62
52
52
78
104

0.64

7
9.76
1.8
2.33
3.5
4.88
1.8

4.88
1.06
2.02
2.97
5.31
7.96
0.85
3.5
3.82
4.56
7.85
8.7
0.11
0.15
3.93
5.84

3.93
5.84
1.27
5.31
6.05
1.33
1.72
2.67
3.44
3.96
5.61
1.33
1.72
1.18
1.53
2.37
3.05
3.51
4.97
6.38
8.31
3.51
13.52
13.52
13.52
13.52
27.04
27.04
26.78
26.78
10.66
18.98
21.58
27.04
35.1
40.56
48.36
53.82
62.14
67.34
80.6
5.46
8.32
8.32
8.32
8.32
10.66
10.66
10.66
16.12
16.12
16.12
18.98
9
9
9
9
9
9
16.12
18.98
16.12
18.98
21.58
37.7
40.56
80.6
94.38
107.64
13.52
16.12

16.12
16.12
16.12
16.12
18.98
18.98
16.12
16.12
8.32
8.32
8.32
43.16
53.82
64.48
64.48
64.48
16.12
13.52
13.52
24.44
27.04
6.76
6.76
6.76
16.12
24.44
27.04
29.64
32.24
37.7
43.16
53.82
64.48
27.04
27.04
29.64
29.64
32.24
32.24
35.1
35.1
37.7
40.56
24.44
24.44
27.04
27.04
16.12
10.66
10.66
10.66
3.64
3.64
3.64
3.64
3.64
3.64
3.64
3.64
3.64
3.64
3.64
3.64
3.64
3.64
3.64
3.64
3.64
3.64
18.98
9.43
2.86
3.64
13.52
14.3
14.3
23.2
773.26
773.26
773.26
773.26
773.26
773.26
773.26
773.26
773.26
773.26
38.66
89.37

257.75
257.75
257.75
257.75
386.63
386.63
386.63

386.63
579.95
579.95
579.95
773.26
46.7
93.39
155.66
266.84
333.55
106.13

23.2
11.6
30.99
62.89
31.45
44.69
44.69
110.47
55.23
154.65
77.33
210.89
105.44
257.75
128.88
257.75
128.88
386.63
193.32
23.2
38.66
62.89
89.37
110.47
154.65
210.89
257.75
257.75
386.63
11.6
19.33
31.45
55.23
77.33
105.44
128.88
128.88
193.32
38.66
19.33
89.37
0.28
0.5
1.34
0.28
0.5
0.65
0.92
1.17
2.08
4.16
52
52
78
104
27.04
358.8
358.8
3.64
3.64
3.64
3.64
23.14
32.5
27.82
23.14
40.2
40.2
40.2
56.86 A
128.77
128.77
128.77
5.46
5.46
8.32
8.32
10.66
10.66
5.46
5.46
5.46
8.32
10.66
10.66
5.46
5.46
8.32
10.66
10.66
8.32
5.46
5.46
8.32
8.32
10.66
10.66
5.46
5.46
5.46
10.66
10.66

14667.5 X
485.50 X
485.50 X
485.5 X
31451.5 X
778 X
778 X
778 X
1136 X
1136 X
1136 X
1636.5 X
1636.5 X
1636.5 X
2287 X
2287 X
3752.5 X
3752.5 X
7933 X
10310.5 X

575

575

880
880
880
880
880
1170
44
50

652.5
211.75
211.75
211.75
211.75
211.75
211.75
211.75
211.75
211.75
211.75
211.75
211.75
211.75
256.66
256.66
211.75
211.75
211.75
211.75
211.75
211.75
211.75
211.75
256.66
385
211.75
211.75
211.75
211.75
211.75
211.75
211.75
211.75
35.29
115.5
144.37
163.62
182.87
202.12
221.37
240.62
259.87
-131.54

-186.08

-198.91
-198.91
962.49
-12.19
-102.67
-163.62
-247.04
-77
-131.54
-36.25
-36.25
-77
-102.67
4251.52
4374.91
4091.05
4208.83
416.2
493.62
715.66
1288.17
658.3
8230.06
813.52

544.54

274.4
345.65
368.53
330
3164.81
6784.33
1195.55
1002.21
1002.21
1197.21

1446.46
1834.46
1834.46
5382.96
5537.93
6969.7
7171.99
16593.46
17116.53
1464.34
31195.71
32179.08

1324.16
2143.08

2697.79
2978.76
4131.47

5749.33
8205.06
10157.4
11568.4
13578.08
1400.1
1437.44
1474.77
1493.44
1549.44
3986.03
4399.41
4399.41
1051.03
132.42
214.31

269.78
297.88
413.15

574.93
820.51
1015.74
1156.84
1357.81
140.01
143.74
147.48
149.34
154.94
6273.66
6458.74
7512.43
7733.03
844.34

162.28
187.7
266.64
310.79
379.03
497.93

918.05
396.82
422.24
501.18
545.34
613.57
817.77
1158.94
1237.88

53644.28
2682.21
65058.5
3252.92
69406.25
3470.31
78596.09
3929.8
5120.23
6203.96
8142.38
1572.45
1792.38
1925.13
2125.51

369.39
769.17
1370.44
234.23
227.02
70.14
108.06
164.15

266.96

467.44
540.92
577.66

1043.31

1309.4

1971.15
190.98
226.83

386.37
553.05

325.29
362.75

547.72
176.46
204.29

341.7
489.76
654.99
166.42
215.37
272.11
392.14
532.39
281.43
336.52

138.1
182.28

339.62
485.96
553.24
772.31

1556.1
175.61

296.77
397.94

796.99
293.79
362.28
446.1
563.29

203.94
272.62
359.67
478.8
1480.71
1894.24

5676.48
225.5

365.57
447.1

656.36
329.12
374.94

234.02
310.52
370.66
425.2
507.28
644.44
794.81
97.68
148.32

424.59
500.85
677.9
703.53
940.97
362.79
521.56
246.9
406.9
686.09
1039.12

36.49

42.93

48.08
55.37
60.52
63.1
365.26
402.08
1275.96
1531.86
1823.13
2374.15
2848.63
3882.57

5060.99
5626.97
2077.61
2533.58
3051.11
3316.02
9334.65
12091.25
17108.57
1595.45
1873.67
3875.79
5571.97
9314.85
12222.73
3018.53
3368.65
418.96
618.8
552.33
606.27
531.99
61.25

228.28
116.56
151.35
200.18
192.64
210.03

97.83
37.89
51.27
169.01
78.94
119.08
175.27
211.39

137.81
188.65

246.18
250.19
254.21
480.32

484.33

548.55

548.55
548.55

62.88
84.29
119.08

211.39
227.45
77.6
84.29
128.44
145.84

200.69

255.55
295.68

212.73

365.26
584.68
913.81
1186.75

365.26
584.68
584.68
584.68
913.81

913.81

1186.75
1186.75
1186.75

239.49
267.59
274.28
365.26

365.26

584.68
584.68
584.68
913.81

913.81
913.81
913.81
1186.75

1186.75

1186.75
1186.75
239.49
267.59

365.26
365.26
365.26
584.68

584.68
584.68
913.81
913.81

913.81

1186.75
1186.75
1186.75
1186.75

1186.75

307.73
317.09
370.61
382.65

1291.11

303.71

418.77

868.32

369.27

567.29
841.56

1573.41

255.55

639.53
913.81
60.21
85.63
112.39
218.08
315.75
400.04
286.32
362.58
7252.92

11776.49

16899.45
23321.55
17769.11
25395.36
3789.89
4214.97
4107.98
4947.82
5580.15
6158.66
11005.85
12968.46
16072.8
20936.85
22326.75
26127.69
3502.6
5190.32
7610.6

4024.4
1039.31
51202.27
62039.57
81423.81
2342.32
2270.2
2355.23
3477.57
3538.04
4691.34

7062.44
7269.28
9487.69
10639.95
11260
15188.59
1909.85
2268.31

3863.73
5530.53

3252.86
3627.48

5477.18
1764.62
2042.91

3416.97
4897.56
6549.91
1664.24
2153.68
2721.09
3921.4
5323.86
2814.29
3365.22

1380.95
1822.84

3396.18
4859.62
5532.38
7723.12

15561.04
1756.08
2967.68
3979.39

7969.92
2937.94
3622.8
4461.02
5632.88

2039.43
2726.21
3596.74
4787.98

14807.15
18942.38

56764.82
2254.98

3655.66
4471.04
5331.18
6563.56
3291.2
3749.43

2340.18
3105.23
3706.61
4251.99
5072.77
6444.39
7948.15
11808.22

17763.46
30124.91
39342.03
53037.11
63625.94
83801.04
101474.93
164710.47
114.04
133.94
177.02
208.61
247.87
291.14
57.81
67.07
86

118.02
138.16
66.59
78.1
99.86
118.12

159.41
195.87
226.72
1381.43
2445.51
2520.18
2669.52
10976.47
15662.4
19288.14
24819.85
31011.75

43991.76
53318.09
60219.81
77619.18
101154.32
126094.95

171071.06
10545.27

21724.57

37891.37
46280.37
68985.06

104315.3
144245.82

158424.53

215056.59
976.83
1483.24
2658.14
4245.89
5008.52
6778.99
7035.31
9409.71
3627.86
5215.58
93346.55
93148.53
30185.33
33686.47
6934.9
8481.2
9886.93

3295.95
5341.75
6278.9
7309.76
8434.34
364.86

429.25

480.76
553.73
605.24
631
3652.6
4020.76

12759.61
15318.57
18231.33
23741.54
28486.34
38825.7

50609.93
56269.65
37898.85
42149.7
41079.75
49478.21
55801.55
61586.58
110058.54
129684.58
160727.98
209368.52
223267.54
261276.91
818.19

1357.3
1635.75

2778.2
3109.94
3455.44
3824.05

4599.24

299.44
368.03
452.47
530.4
820.67
943.37
1060.61
1248.41
1438.94
1636.72
1836.56
2246.5
83579.62
41552.23
50671.66
61022.13
66320.32
31909
37473.3
77515.8
7407.13
12206.87
20582.56
31173.69

7513.22
7800.69

9033.97
9956.52
10766.85
11523.32
12227.87
12951.18
13587
14707.79
8991.09
14073.53
22202.86
26853.83
34319.48
43221.53
55925.41
71201.63
88407.39
122514.95
7545.41

14270.36
20260.95
26027.93
32798.11
42130.99
44344.84
62746.29

98306.25
807.48
3507.18
5402.91
8207.34
9941.41
13347.91

23371.95
27046.04
28883.08

52165.7

65469.79
84185.18
98557.52
2197.87
2609.33

2074.97
108821.27
153977.1
110004.59
2076.82

9586.56

20394.03
20567.89

92.59
129.1
174.18
232.35

346.27
402.01
459.84
515.93
682.8
559.75
1798.22
2814.71
4440.57
693.49

988.69

4439.38

8369.49
5290.73
6039.35
7026.94

1132.21
1866.82

9769.31
2198.3
2910.91
235.52
347.76
353.8
469.13

706.24
726.93

1063.99
1126
1518.86
8.8

1304.67
7667.22

18227.74
7305.5
6906.72
9530.51
9620.3
18396.46
38920.29
39589.69
386.15
1180.82

1776.35
3012.49
3934.2
5303.71
6362.59
8380.1
10147.49

16471.05
11.4
13.39
17.7
20.86
24.79
29.11
5.78
6.71
8.6

11.8
13.82
6.66

9.99
11.81

15.94
19.59
22.67
138.14
244.55
252.02
266.95
366.31
434.89

692.87
398.6
186.62
193.76

224.39
247.31
267.43
286.22
303.72
321.69
337.48
365.32

1056.71
1853.57
3506.7
2688.32

2694.35
247.28
302.53

302.53
326.43
497.15
460.22

678.39
869.18
1488.11
2217.9

386.42

477.7

641.73
708.63
792.38
979.69
1144.07
1251.11
2043.97
2057.35
2890.69
3399.11
340.34
438.36
72.84
79.53
83.01
100.4

188.81
191.54
252.63
474.27
728.48
1250.28

111.74
94.91
112.44

81.29

434.75
157.1
296.42
5125.6
5259.39
7667.68
7667.68
23560.32
21479.79
2284.93
5370.77
6863.9
8644.31
11185.08
14240.33
17681.48
24502.99
1097.65
1566.24
1928.81
2481.98
3101.17
4399.18
5331.81

7761.92
10115.43
12609.5

17107.11
1054.53

2172.46

3789.14
4628.04

6898.51

10431.53
14424.58

15842.45

21505.66
1509.08

2854.07
4052.19
5205.59
6559.62
8426.2
8868.97
12549.26

19661.25
329.6
534.18
627.89
730.98
843.43
4371.39
4766.67
5547.8
917.62
53517.51
60207.19
66896.88

20069.06
30772.57

853.59

59
63
89
131
158
180

1400.1
1437.44
1474.77
3976.28217 A

15000
23000
23000
494.08
385
35.29
35.29
35.29
35.29
385
276.08
52.36
52.36
52.36
52.36

-15647.60 A 6234.1
-19824.44 A 6234.1
-24468.85 A 6234.1
-29611.99 A 6234.1
-67827.03 A 6234.1
-97875.4 A 6234.1
22066.98
28797.15

56098.92
73671.41

25237.89
63329.24

93339.09
190809.04
W
W
W
W
W
W
W
W
W
W
W
W
234.00 W
W

W
W
W
W
W
W
W
W
W
W
W

W
W
W
W
W

W
W

4370
5540
7860
2680

27.04

59100
37150
45250
7650
11500
15750
22000
27500
33500
43000
50000
62700
75600
105000
113500
114500
139000
155500
8000
11400
14000
18000
22500
26500
31750
38520
43500
56000
73000
91000
118000
123000
12400
17200
5500
10375
14750
18950
23900
30750
32265
45900
60750
71850
8250
18750
13050
58
63
96
109
116
150

159
231
273
437
683
887
9
17.1
25.2
45
67.5
5.4
7.2
10.8
29.7
32.4
38.7
45
51.3
59.4
66.6
73.8
82.8
0.9
1.26
15.3
19.8
29.7
33.3
41.4
49.5
15.3

33.3
41.4
49.5
0

242.32
157.08
157.08
157.08
157.08
157.08
157.08
157.08
157.08
157.08
157.08
38.08
38.08
38.08
38.08
76.16
76.16
157.08
157.08
157.08
157.08
157.08
157.08
157.08
157.08
38.08
57.12
57.12
76.16
76.16
119
119
176.12
176.12
52.36
52.36
52.36
157.08
157.08
157.08
157.08
157.08
157.08
157.08
157.08
157.08
157.08
38.08
38.08
57.12
57.12
76.16
76.16
119
119
176.12
276.08
157.08
157.08
157.08
157.08
157.08
157.08
157.08
157.08
38.08
38.08
57.12
57.12
76.16
76.16
119
119
157.08
214.2
157.08
80.92
442.68
476
714
714
952
1190
1428
1428
1904
2142
2261
3094
71.4
119
119
142.8
142.8
190.4
190.4
238
238
285.6
309.4
357
238
295.12
357
80.92
157.08
47.6
52.36
52.36
52.36
52.36
52.36
71.4
71.4
71.4
157.08
157.08
157.08
157.08
157.08
214.2
214.2
214.2
476
714
952
1190
1428
1428
1904
2142
2261
3094
3665.2
3665.2
4046
4760
5236
157.08
233.24
314.16
390.32
547.4
704.48
780.64
856.8
937.72
1013.88
1094.8
1247.12
52.36
76.16
104.72
128.52
276.08
285.6
285.6
333.2
380.8
428.4
476
571.2
28.56
38.08
52.36
71.4
95.2
119
142.8
166.6
190.4
214.2
238
285.6
157.08
157.08
157.08
157.08
157.08
157.08
157.08
157.08

41.34
10.66

5500
5500
A

140
185
210
280
325
375
465
560
605
655
840
186.5
233
279.5
326.5
420
513
560
606.5
653
700
746
840
15
15
25
1046.5
1046.5
928.2
1380
1380
1224
1966.5
1744.2
2472.5
2193
2875
2550
2550
3565
3162
4029
5151
50
452
30
30
49
49
108
108
141
141
192
192
249
249
504
504
563
563
977.03 A

W
W
330
450
560
820
1490
2120
350
500
700
900
1500
2500

210
235
230

32.08

1330
1330
1330
2625
1330
2625
2625
2625
3360
70
70
70
70
35
35
35
70
420
420
420
420
420
420
10800
14400
18000
18000
21000
20400
20100
23100
22500
21000
20700
20100
23100
10800
10800
10800
10800
600
600
600
600
180
180
180
180
180
180
180
300
180
180
180
180
180
180
180
180
300
90
180
180
180
30
30
30
30
1500
1500
1500
1500
1500
1500
2000
3750
2500
510
510
510
510
510
510
680
850
1275
1786
2280
2850
2660
11400
11400
11400
11400
11400
11400
375
465
562.5
19
38
38
38
57
76
85
85
113.5
113.5
142
18.95
18.95
28.4
28.4
37.88
56.83
75.75
75.75
94.7
113.65
132.6
170.5

3.64
3.64
3.64
3.64
3.64

0
68.12
78
104
130
208
78
78
104
78
104
130
208

A
A
A
A
A
A
A
A
A
A
A
A
A

1505
1505
1505
1505
1505
1505
1505
1505
1505
1505
1505
1505
1505
1505
977.03 A
977.03 A
977.03 A
A
977.00 A
977.00 A
A

76.16
395.08
476
714
833
1071
1190
152.32
185.64
257.04

357
385.56
437.92
490.28
542.64
595
647.36
699.72
756.84
28.56

38.08
38.08
38.08
28.56
28.56
47.6
47.6
47.6
47.6
9.52
9.52
9.52
23.8
76.16
238
9.52
14.28
178.5
218.96
297.5
323.68
378.42
547.4
178.5

323.68
378.42
547.4
119
23.8
57.12
57.12
333.2
404.6
19.04
23.8
59.92
310.84
93.63
374.5
561.75
655.38
842.63
936.25
119.84
146.06
202.23

280.88
303.35
344.54
385.74
426.93
468.13
509.32
550.52
595.46
22.47

29.96
29.96
29.96
37.45
37.45
37.45
7.49
7.49
74.9
18.73
18.73
44.94
44.94
59.92
262.15
318.33
14.98
18.73
187.25
7.49
11.24
140.44
172.27
234.06
254.66
297.73
430.68
140.44

234.06
254.66
297.73
22.47
22.47
37.45
79.2
79.2
108
108
38.08
38.08
38.08
38.08
66.64
76.16
85.68
95.2
57.12
57.12
57.12
66.64
57.12
66.64
76.16
85.68
119
38.08
38.08
38.08
38.08
9.52
9.52
9.52
9.52
57.12
514.08
57.12
57.12
57.12
57.12
W
W
W

W
W
W
W

1332.08 A

210.74 A
1437.35 A

4285.95 A
A
A
A
A
A
A
A
A
8262.94 A
A
A

W
W
W
W
W
W
200.00 W
W
W
W
W
W
W
W
W
W
W
W
W
W
W

154.5
30
54
78
133.5
A
A
A
A
A
A

13.52
13.52
13.52
13.52
13.52
14.3
14.3
14.3

17600

300
W

W
W
W
W
103.00 w
W
W
W

W
W
W
W
W
W
W
W
W
W
W
W
W
W

A
A

179.4
179.4
110
432.70 P
432.70 P
668.00 P
1074.70 P
1074.7 P
1074.70 P
1610.70 P
1610.70 P
2522.20 P
2522.2 P
2817.30 P
4181.80 P
5976.30 P
8858.30 P

432.70 P
668.00 P
2750
2750
93.86
261.82
464.36
617.5
29.64
44.46

128.44
158.08
182.78
207.48
242.06
271.7
301.34
335.92
6.42
9.39
123.5
138.32
167.96
242.06
59.28

138.32
177.84
24.7
118.56
59.28
79.04
167.96
242.06
483.6

933

620
235
235
620
53.82
79.82

100
100
135
290
480
870
20
125

138
57
62
84
70

A
150
1120
1200
1400
175
250

400
460
560
600
800
940

2000
29000
32000
35100
2120
3500

7500
9250
11000
14850
18000
25000

22.41 A
28.14 A
35.33 A
44.42 A
50.62 A
63.07 A
55.45
69.62
87.42
109.92
125.24
156.07
164.85 A
508.68 A
310.86 A
68.29 A
68.29 A
70.65 A
70.65 A
37.68 A
37.68 A
515.74 A
567.55 A
567.55 A
989.09
412.12 A
412.12 A
548.71
1055.03 A
1055.03 A
602.87
602.88
1792.13 A
1792.13 A
2117.12
2117.12
75.36 A
141.30 A
14.13
14.13 A
254.34 A
365.02 A
555.77 A
211.95 A
800.69
800.69
989.09
548.71
58.87
501.61
565.19
682.94
1038.56 A
1511.91 A
508.67
247.27 A
315.57 A

351.56 A
200.89 A
351.56 A
1185.25 A
322.38 A
454.26 A
278.42 A
351.68 A
1670.46 A
277.81 A
522.6 A
6278.9 A
7309.76 A
8481.20 A
9886.93 A
5341.75 A
6934.9

878.12 A
1229.37 A
175.62 A
658.59 A
1009.84 A
1448.9 A
658.59 A
570.78 A
395.15 A
395.15 A
351.25 A
351.25 A
351.25 A
922.03 A
702.50 A
790.31 A
1273.27 A
878.12 A
965.93 A
1141.56 A
351.25 A

59.54
59.54
3333.93 A
3333.93 A
6244.50 A
6244.50 A
11906.89 A
11906.89 A
2130.74 A
2725.36 A

2725.36 A
2725.36 A

639.64 A
639.64 A
142.14 A
710.71 A
639.64 A
7.11 A
56.86 A
56.86 A
56.86 A
56.86 A
56.86 A
639.64 A
639.64 A
639.64 A
497.50 A

263.1 A
1447.06 A
26.31 A
26.31 A
59.2 A
26.31 A
26.31 A
149.95 A
26200.38 A
861.93 A
2037.29 A
1880.58 A
1723.86 A
2429.08 A
2585.8 A
2585.8 A

17406.6 A
22052.99 A
27219.49 A
32940.78 A
45909.05 A
54438.97 A
70527.95 A
110264.93 A
22052.99 A
27219.49 A
39182.19 A
45909.05 A
39182.19 A
45909.05 A
54438.97 A
70527.95 A
110264.93 A
5395.35 A
10249.78 A
13217.92 A
16643.76 A
228.85 A
436.90 A
561.73 A
707.36 A
17406.60 A
22052.99 A
27219.49 A
32940.78 A
75451.73 A
108877.95 A
559.17 A
686.63 A
534.5 A
596.17 A
217.91 A
226.13 A
374.15 A
230.25 A
275.47 A
374.15 A
468.3
206.05 A

412.11 A

388.69 A
388.69 A
412.11 A
388.69 A
552.83 A
7297.29 A
718.67 A
718.67 A
718.67 A
5141.28 A
2929.97 A
3482.8
7131.45 A
3648.65
20343.96 A
38.7 A
27.64 A
1603.19 A
2377.15 A
1160.93 A
1216.22 A
3869.78
4201.47
4864.86

3151.1 A
5749.38 A
3151.1 A
1934.89 A

742.98 A
742.98 A
742.98 A

4572.16 A
5658.05
6743.94
3029.06 A
3600.58
7372.61 A
3772.03
21031.94 A
30061.96

181.71 A
363.42 A

1340.41 A
191.00 A
191.00 A
382.01 A
1350.41
1870.78
160.71 A
251.11 A
291.29 A
266.19 A
340.48 A

1465.35 249.11 A
380.99 A
29.31 A
288.30 A
788.59 A
2450.58 A
1110.82 A
839.47 A
1000.58 A
1263.45 A
212.68 A
334.15
296.4 A
296.4 A
296.4 A
296.4 A

977.03 A
977.03 A

977.03
977.03 A
977.03 A
977.03 A
379.56 A
250.24 A
488.49 A
702.74 A
250.25 A
186.83 A

119.09 A
1548.13 A
2500.83 A
238.17 A
178.63 A
178.63 A
238.17 A
178.63 A
178.63 A
178.63 A
59.54 A
2500.83 A
952.70 A

1488.59 A

1488.59 A
1488.59 A
714.52 A
714.52 A
1548.13 A
119.09 A
178.63 A
404.45 A
1652.77 A
2473.12 A
790.19 A
1345.21 A
796.98 A

1872.18 A

1992.82 A
373.98 A
603.23 A
471.28 A
616.05 A
120.64 A
1992.82
995.28 A
7835.75
470.14 A
470.14 A
1018.65 A
1332.08 A
5472.97
6523.34
977 (A)
977.03 (A)
-2688.3
37.35 A
181.77 A
354.83 A
510.45 A
181.77 A
135.71 A
1332.08 A
2115.65 A
3212.66 A
1018.65 A
1723.86 A
156.71 A
402.74 A
1077.1 A
482.35 A
697.77
402.74
4441.16 A
5470.15 A
279.01 A
412.7 A
567.91 A
754.07 A
950.29 A
1252.54 A
1489.29 A
1743.32 A
2034.11 A
2649.93 A
4196.09 A
5047.4 A
171.24 A
256.07 A
347.19 A
466.58 A
600.11 A
717.94 A
848.33 A
1003.86 A
1162.53 A
1563.13 A
2967.58
3825.34
3417.51
3811.2
5972.71
2003
296.4 A
296.4 A
296.4 A
296.4 A
296.4 A
296.4 A
296.4 A
296.4 A
1381.43
1493.44
1549.44
2445.51 A
2520.18 A
2669.52277 A
977
128.77
128.77
128.77

2206.7
2879.72

5609.89
7367.14

6332.92

9333.91
19080.9
311.05 A
405.31 A
505.86 A
739.93 A
997.57 A
1285.06 A
1619.68 A
1971.58 A
2376.89 A
2782.24 A
3707.56 A
212.08 A
347.19 A
499.57 A
670.81 A
864.04 A
1066.7 A
1310.2 A
1583.55 A
1844.33 A
2477.44 A
241.93
358.18
472.87
617.4
760.35
1036.85
1230.08
1435.88
1674.67
2177.38
38850
55650
50400
65100
94500
136500
14960
17330
19950

31500

773.26

1400

1400
1400
1400
910

670

675

118
103
141
145
184
187
190
359
362
362
387
410
410
410
410

191
221

179
273
273
437
437
437
683
683
683
683
887
887
887

14.3
14.3
14.3
16.12
16.12
16.18
14.3
14.3
16.12
14.3

14.3
14.3
3.64
3.64

201.34

180
200
200
250
400
450
500
730
920
1100
1250
160
1450
1800
3150
3700
5500
6300
11500
13500
14500
18250
27500
33000
36250
48000
57250
3700
3600
670
258
460
360
630.56
630.56
972.23
972.23
570
880

880
100
100
130
130
225
225
185
240
8570
10670
12860
21900
28570
38570
46190
60950
73810
85710
119950
6200
8571
9048
5190

1225
191
226.85
290.5
386.35
553.05
718.3
325.3
362.75
437.65
547.7
176.45
204.3
259.95
341.7
489.75
655
166.4
215.35
272.1
392.15
532.4
281.45
336.5
395.8
138.1
182.3
247.6
339.6
485.95
553.25
772.3
1093.4
1556.1
369.4
769.15
1370.45
175.6
234.5
296.75
397.95
542.1
797
293.8
362.3
446.1
563.3
153.05
203.95
272.6
359.65
478.8
733.7
1480.7
1894.25
2685.05
5676.5
225.5
278.2
365.55
447.1
533.1
656.35
329.1
374.95
194.4
234
310.5
370.65
425.2
507.3
644.45
794.8
453.05
1132.2
386.15
302.55
326.45
302.55
326.45
497.15
460.2
581.25
678.4
869.2
1488.1
2217.9
338.7
386.4
394
477.7
504.45
641.75
708.65
792.4
979.7
1144.05
1251.1
2043.95
2057.35
2890.7
3399.1
295.15
340.35
438.35
72.85
79.55
83
100.4
151.9
188.8
157.1
296.4
5125.6
5259.4
7667.7
7667.7
1180.8
1472.25
1776.35
3012.5
3934.2
5303.7
6362.6
8380.1
10147.5
11780.15
16471.05
235.5
347.75
353.8
469.15
586.35
706.25
726.95
948.75
1064
1126
1518.85
23560.3
132.4
214.3
227.7
269.8
297.9
413.15
419.85
574.95
820.5
1015.75
1156.85
1357.8
3789.9
4214.95
4108
4947.8
5580.15
6158.65
11005.85
12968.45
16072.8
20936.85
22326.75
26127.7
1304.65
7667.2
13212.45
18227.75
7305.5
6906.7
11.4
13.4
17.7
20.85
24.8
29.1
5.8
6.7
8.6
10.1
11.8
13.8
6.65
7.8
10
11.8
13.45
15.95
19.6
22.65
138.15
1866.8
140
143.75
147.5
149.35
154.95
244.55
252
266.95
366.3
434.9
506.2
692.85
398.6
1051.05
162.3
187.7
266.65
310.8
379.05
497.95
839.1
918.05
396.8
422.25
501.2
545.35
613.55
817.75
1158.95
1237.9
8.8
8.8
418.95
618.8
552.35
606.25
532
61.25
176.75
228.3
116.55
151.35
200.2
192.65
210.05
104.5
97.85
37.9
51.25
169
5120.25
6203.95
8142.4
3502.6
5190.3
7610.6
8314.35
4024.4
6484.1
8230.05
11529.4
191.55
252.65
474.25
728.5
1250.3
155.35
111.75
130.5
7252.9
8604.25
11776.5
12414.7
16899.45
23321.55
17769.1
25395.35
70.15
108.05
164.15
198.85
266.95
288.35
467.45
540.9
577.65
747.9
1043.3
1190.5
1309.4
1683.7
1971.15
1798.2
2814.7
4440.55
5370.75
6863.9
8644.3
11185.1
14240.35
17681.5
24503
1097.65
1566.25
1928.8
2482
3101.15
3669.9
4399.2
5331.8
6022
7761.9
10115.45
12609.5
16309.35
17107.1
1054.55
1585.05
2172.45
3030.85
3789.15
4628.05
5930.3
6898.5
8626.75
10431.55
14424.6
15644.3
15842.45
19205.55
21505.65
1509.1
2264
2854.05
4052.2
5205.6
6559.6
8426.2
8868.95
12549.25
16620.3
19661.25
94.9
112.45
49.2
81.3
113.4
234.25
227
97.7
148.3
818.2
1081.1
1357.3
1635.75
2196.05
2778.2
3109.95
3455.45
3824.05
4199.85
4599.25
5417.55
299.45
368.05
452.45
530.4
820.65
943.35
1060.6
1248.4
1438.95
1636.7
1836.55
2246.5
179.15
186.6
193.75
201.25
224.4
247.3
267.45
286.2
303.7
321.7
337.5
365.3
68.85
92.6
129.1
174.2
232.35
288.1
346.25
402
459.85
515.95
573.75
682.8
7781.6
265.8
424.6
500.85
677.9
703.55
940.95
362.8
521.55
78.95
84.3
119.1
175.25
211.4
240.85
137.8
188.65
194
246.2
250.2
254.2
480.3
484.35
484.35
517.8
548.55
548.55
548.55
548.55
548.55
62.9
84.3
119.1
175.25
211.4
227.45
77.6
84.3
128.45
145.85
155.2
200.7
198
255.55
295.7
384
461.6
239.5
212.75
309.05
365.25
584.7
913.8
1186.75
239.5
365.25
365.25
584.7
584.7
584.7
913.8
913.8
913.8
913.8
1186.75
1186.75
1186.75
1186.75
1186.75
239.5
267.6
274.3
365.25
365.25
365.25
584.7
584.7
584.7
584.7
913.8
913.8
913.8
913.8
913.8
1186.75
1186.75
1186.75
1186.75
1186.75
1186.75
239.5
267.6
267.6
365.25
365.25
365.25
584.7
584.7
584.7
584.7
913.8
913.8
913.8
913.8
913.8
1186.75
1186.75
1186.75
1186.75
1186.75
1186.75
254.2
307.75
317.1
370.6
382.65
450.9
547.2
719.8
770.65
911.15
1121.2
1291.1
258.2
303.7
331.8
418.75
428.15
616.8
755.95
868.3
971.35
1123.85
1522.55
313.1
369.25
394.7
567.3
841.55
1170.7
1573.4
200.7
255.55
255.55
274.3
384
639.55
639.55
913.8
913.8
255.55
274.3
384
639.55
913.8
60.2
85.65
112.4
218.1
315.75
400.05
286.3
362.6
544.55
246.9
406.9
686.1
1039.1
1461.05
693.5
848.1
988.7
1143.3
329.6
534.2
627.9
731
843.45
2076.8
2101.1
2094.4
2118.7
2202.7
2227
36.5
40.35
42.95
45.5
48.1
55.35
60.5
63.1
365.25
402.1
774.55
1275.95
1531.85
1823.15
2374.15
2848.65
3882.55
4542.4
5061
5626.95
9586.55
9650.15
20394.05
20567.9
26146.3
26295.85
6273.65
7512.45
7733.05
9530.5
9620.3
5382.95
5537.95
18164.6
18396.45
6969.7
7172
38920.3
39589.7
16593.45
17116.55
312.95
274.4
345.65
368.55
330
1288.15
3164.8
6784.35
1195.55
1002.2
1002.2
1197.2
1010.55
1446.45
1834.45
658.3
416.2
493.6
715.65
6999.75
9769.3
2198.3
2910.9
1056.7
1853.55
3506.7
844.35
1005.45
813.5
917.6
1847.25
2894.05
2694.35
247.3
4439.4
4887.15
8369.5
5290.75
6039.35
4371.4
4766.65
5547.8
21479.8
2284.95
323.5
434.75
2206.7
2879.7
4534.75
5609.9
7367.15
13519.2
6332.9
7857.65
9333.9
19080.9
2077.6
2533.6
3051.1
3316
9334.65
12091.25
17108.55
1595.45
1873.65
3875.8
5571.95
9314.85
12222.75
3018.55
3368.65
1572.45
1792.4
1925.15
2125.5
2682.2
3252.9
3470.3
3929.8
53517.5
60207.2
66896.9
20069.05
30772.55
20069.05
31575.35
853.6
6550
10240
16190
19525
24950
31430
40715
51905
64570
89525
549.45 W

100
125

224.28
W
W

47
63
89
131
158
170
85
100
115
150
200
270
310
370
395
425
510
225
600
750
4.5
9
450
900
575

150
W
W
W
W
W
W

W
W
W
W
W
6100 (X)
1300.00 (X)
1300 (X)
2430.00 (X)
2430 (X)
2970.00 (X)
4230.00 (X)
4410 (X)
45
64
84
163
236
299
179
200
200
273
273
273
437
437
437
437
683
683
683
683
683
887
887
887
887
887
887
190
230
237
277
286
337
538
965

191
191

478

179
200
205
273
273
273
437
437
437
437
683
683
683
683
683
887
887
887
887
887
887
227
313
320
649

214
271
407
234
276
295
424
629
875
1176

3025
165
5500
11000
26290
110
17600
600
14.3
32.24
80.34
13.52
18.98
21.58
27.04
35.1
40.56
48.36
53.82
62.14
67.34
80.6
8.32
16.12
16.12
16.12
16.12
16.12
27.04
27.04
27.04
14.5
8.84
5.78
16.12
43.16
3.64
5.46
8.84
10.66
14.3
16.12
19.76
21.58
24.96
27.04
30.42
32.24
27.04
33.28
33.28
40.56
40.56
33.8
33.8
33.8
33.8
33.8
33.8
27.04
27.04
27.04
33.28
33.28
40.56
40.56
14.3
16.18
33.28
40.56
40.56
27.04
27.04
27.04
51.68
27.04
1042.16
785.4
1060
743.76
1147.14
1795.78
1466.74
2226.96
461.38
175.9
634.86
263.16
634.86
263.16
351.78
581.58
1186.96
821.84
553.64
389.62
416.3
884
2 27.04
107.64
107.64
107.64
134.42
134.42
161.46
188.24
215.28
242.06
269.1
295.88
349.7
68.12
53.82
19.76
27.04
35.88
45.76
62.92
80.6
88.92
96.72
107.64
116.48
127.4
142.74
8.84
8.84
10.92
14.3
19.76
21.58
27.04
32.24
35.88
41.34
46.54
52
210
210
210
210
125
250

296.53 A
2524.72 A

37.45
260
260
312
312

W
W
W
W
W
337.00 W
W
W
W
W
W
W
W
W
W
W
W

1427.46 W
1441.73 X
1644.3 Y
1890.94 Z
1695.38 W
1712.33 X
1952.91 Y
2245.85 Z
2171.3 W
2193.01 X
2501.13 Y
Z
2887.82 W
2916.7 X
3326.5 Y
3825.47 Z
4133.622 W
4174.96 X
4761.54 Y
5475.77 Z
5368.622 W
5422.31 X
6184.14 Y
7111.76 Z
2678.03 W
2695.04 X
2936.42 Y
3230.33 Z
2958.03 W
2977.84 X
3258.95 Y
3601.24 Z
3518.03 W
X
Y
Z
4340.53 W
4374.16 X
4851.46 Y
5432.63 Z
1318.91 W
1332.1 X
1519.26 Y
1747.15 Z
1526.91 W
1542.18 X
1758.85 Y
2022.68 Z
1942.91 W
1962.34 X
2238.05 Y
2573.75 Z
2553.91 W
2579.45 X
2941.86 Y
3383.14 Z
3660.53 W
3697.13 X
4216.58 Y
4849.07 Z
4895.53 W
4944.48 X
5639.18 Y
6485.06 Z
1243.89
1256.33 X
1432.84 Y
1647.77 Z
1609.7
1625.79 X
1854.22 Y
2132.35 Z
2033.8
2054.14 X
2342.74 Y
2694.15 Z
2930.93
2960.24 X
3376.15 Y
3882.57 Z
3979.15
4018.94 X
4583.61 Y
5271.15 Z
2350.22 W
2363.96 X
2558.82 Y
2796.1 Z
2762 W
2779.85 X
3033.15 Y
3341.57 Z
3205.05 W
3227.33 X
3543.5 Y
3928.47 Z
1032.15 W
1042.47 X
1188.94 Y
1367.28 Z
1362.42 W
1376.05 X
1569.38 Y
1804.79 Z
1850.46 W
1868.97 X
2131.56 Y
Z
2538.37 W
2563.75 X
2923.96 Y
3362.55 Z
3632.17 W
3668.49 X
4183.91 Y
4811.5 Z
4135 W
4176.35 X
4763.13 Y
5477.6 Z
5772.4 W
5830.13 X
6649.26 Y
7646.65 Z
8172.21 W
X
Y
Z
11630.61 W
11746.92 X
13397.36 Y
15406.97 Z
276.09 W
278.85 X
318.03 Y
365.74 Z
574.89 W
580.64 X
662.22 Y
761.55 Z
1024.29 W
1034.53 X
1179.89 Y
1356.87 Z
1312.53 W
1325.65 X
1511.91 Y
1738.69 Z
1752.7 W
X
Y
Z
2218.1 W
2240.28 X
2555.04 Y
2938.29 Z
2974.27 W
3004.02 X
3426.08 Y
3939.99 Z
4051.72 W
4092.24 X
4667.2 Y
5367.28 Z
5956.87 W
6016.44 X
6861.75 Y
7891.01 Z
2442.65 W
2457.31 X
2665.29 Y
2918.53 Z
2954.53 W
2974.3 X
3254.92 Y
3596.6 Z
3581.03 W
3607.07 X
3976.59 Y
4426.52 Z
4456.9 W
4491.7 X
4985.51 Y
5586.79 Z
1144.06 W
1155.5 X
Y
Z
1524.31 W
1539.55 X
1755.86 Y
2019.24 Z
2037.62 W
2058 X
2347.15 Y
2699.22 Z
2688.27 W
2715.16 X
3096.64 Y
3561.13 Z
3578.63 W
3614.42 X
4122.24 Y
4740.58 Z
5483.78 W
X
Y
Z
11067.14 W
11177.81 X
12748.3 Y
14660.54 Z
14157.89 W
14299.47 X
16308.55 Y
18754.83 Z
20068.4 W
X
Y
Z
42427.1 W
42851.37 X
48871.99 Y
56202.79 Z
1685.41 W
1702.27 X
1941.43 Y
2232.65 Z
2079.22 W
2100.01 X
Y
Z
2732.31 W
2759.63 X
3147.36 Y
3619.46 Z
3341.74 W
3375.16 X
3849.37 Y
4426.78 Z
3984.62 W
4024.47 X
4589.91 Y
5278.39 Z
4905.73 W
4954.79 X
5650.93 Y
6498.58 Z
2723.48 W
2740.28 X
2978.67 Y
3268.94 Z
3068.87 W
3089.01 X
3374.79 Y
3722.75 Z
1452.95 W
1467.48 X
1673.66 Y
Z
1749.1 W
1766.59 X
2014.8 Y
2317.01 Z
2320.91 W
2344.12 X
2673.47 Y
3074.49 Z
2770.39 W
2798.1 X
3191.23 Y
3669.91 Z
3178.02 W
3209.8 X
3660.78 Y
4209.9 Z
3791.48 W
3829.4 X
4367.43 Y
5022.54 Z
4816.66 W
4864.83 X
5548.34 Y
6380.59 Z
5940.6 W
6000 X
6843 Y
7869.45 Z
338.61 W
X
Y
Z
846.23 W
854.7 X
974.78 Y
1121 Z
288.61 W
291.5 X
332.46 Y
382.32 Z
226.12 W
228.38 X
260.47 Y
299.54 Z
243.98 W
246.42 X
Y
Z
226.12 W
228.38 X
260.47 Y
299.54 Z
243.98 W
246.42 X
281.04 Y
323.2 Z
371.58 W
375.3 X
428.02 Y
492.23 Z
343.98 W
347.42 X
396.23 Y
455.67 Z
434.44 W
X
Y
Z
507.04 W
512.11 X
584.06 Y
671.67 Z
649.64 W
656.14 X
748.32 Y
860.57 Z
1112.24 W
1123.36 X
1281.19 Y
1473.37 Z
1657.7 W
1674.28 X
1909.51 Y
2195.94 Z
W
X
Y
Z
288.82 W
291.71 X
332.69 Y
382.6 Z
294.48 W
297.42 X
339.21 Y
390.09 Z
357.04 W
360.61 X
411.28 Y
472.97 Z
377.04 W
380.81 X
434.31 Y
499.46 Z
479.64 W
484.44 X
552.5 Y
635.37 Z
529.64 W
534.94 X
610.09 Y
701.61 Z
592.24 W
598.16 X
682.2 Y
784.53 Z
732.24 W
739.56 X
843.47 Y
969.99 Z
855.1 W
863.65 X
984.99 Y
1132.74 Z
935.1 W
944.45 X
1077.15 Y
1238.72 Z
1527.7 W
1542.98 X
1759.77 Y
2023.73 Z
1537.7 W
1553.08 X
1771.28 Y
2036.98 Z
2160.56 W
2182.17 X
2488.76 Y
2862.07 Z
2540.56 W
2565.97 X
2926.48 Y
3365.46 Z
220.6 W
222.81 X
254.11 Y
292.23 Z
254.38 W
256.92 X
293.02 Y
336.97 Z
327.64 W
330.92 X
377.41 Y
434.02 Z
54.44 W
54.98 X
62.71 Y
72.12 Z
59.44 W
60.03 X
68.47 Y
78.74 Z
62.04 W
62.66 X
71.46 Y
82.18 Z
75.04 W
75.79 X
86.44 Y
99.4 Z
W
X
Y
Z
141.12 W
142.53 X
162.56 Y
186.94 Z
603.53 W
609.56 X
695.21 Y
799.49 Z
1550.87 W
1566.38 X
1786.45 Y
2054.42 Z
3905.84
3941.93 X
4454.13 Y
5077.79 Z
4005.84 W
4042.93 X
4569.32 Y
5210.26 Z
5805.84 W
5860.93 X
6642.75 Y
7594.7 Z
5805.84 W
5860.93 X
6642.75 Y
7594.7 Z
8904.25 W
8990.18 X
10209.6 Y
11694.38 Z
11106.30 W
X
Y
Z
13404.52 W
13533.51 X
15363.89 Y
17592.6 Z
22702.82 W
22922.45 X
26039.1 Y
29833.97 Z
29656.95 W
29943.54 X
34010.45 Y
38962.38 Z
39965.53 W
40352.33 X
45841.28 Y
52524.72 Z
47964.33 W
48427.78 X
55004.32 Y
63012.01 Z
63132.47 W
63744.08 X
72423.11 Y
82990.85 Z
76444.65 W
77185.32 X
87695.91 Y
100493.76 Z
88749.99 W
X
Y
Z
124044.19 W
125247.56 X
142323.93 Y
163116.38 Z
1760.34 W
1777.94 X
2027.74 Y
2331.91 Z
2599.2 W
2625.19 X
2994.03 Y
3443.14 Z
2644.4 W
2670.84 X
3046.1 Y
3503.01 Z
3506.4 W
3541.46 X
4039.04 Y
4644.9 Z
4382.6 W
4426.43 X
5048.34 Y
Z
5278.6 W
5331.39 X
6080.45 Y
6992.51 Z
5433.2 W
5487.53 X
6258.53 Y
7197.31 Z
7091.28 W
7162.19 X
8168.48 Y
9393.75 Z
7952.5 W
8032.03 X
9160.52 Y
10534.6 Z
8415.94 W
8500.1 X
9694.36 Y
11148.52 Z
11352.24 W
11465.76 X
13076.7 Y
15038.21 Z
17609.43 W
17785.53 X
20284.39 Y
23327.05 Z
989.7 W
999.6 X
1140.04 Y
1311.05 Z
1601.78 W
1617.79 X
1845.09 Y
2121.86 Z
1701.78 W
1718.79 X
1960.28 Y
2254.33 Z
2016.38 W
2036.55 X
2322.68 Y
2671.08 Z
2226.38 W
2248.65 X
2564.58 Y
2949.27 Z
3087.94 W
3118.82 X
3557.01 Y
4090.56 Z
3137.94 W
X
Y
Z
4297.16 W
4340.13 X
4949.91 Y
5692.4 Z
6132.62 W
6193.94 X
7064.19 Y
8123.82 Z
7591.83 W
7667.75 X
8745.07 Y
10056.83 Z
8646.44 W
8732.9 X
9959.88 Y
11453.86 Z
10148.52 W
10250 X
11690.13 Y
13443.64 Z
29740.53 W
29981.94 X
33407.74 Y
37579.05 Z
33007.53 W
33278.06 X
37116.99 Y
41791.34 Z
32275.52 W
32536.05 X
36233.07 Y
40734.63 Z
38642.52 W
38963.17 X
43513.23 Y
49053.46 Z
43612.84 W
43973.52 X
49091.74 Y
55323.76 Z
48041.49
48442.31 X
54130.09 Y
61055.62 Z
84674.32 W
85425.47 X
96084.68 Y
109063.49 Z
99560.3 W
100451.72 X
113101.34 Y
128503.73 Z
123565.04 W
124664.74 X
140270.01 Y
159271.22 Z
160294.24 W
161746.41 X
182353.42 Y
207444.84 Z
170810.05 W
172362.34 X
194390.01 Y
221211.25 Z
199675.66 W
201498.52 X
227365.79 Y
258862.19 Z
1262.77 W
1264.01 X
1281.61 Y
1303.03 Z
7620.06 W
7621.45 X
7641.26 Y
7665.37 Z
13185.89
13186.68 X
13197.83 Y
Z
18229.36 W
18229.32 X
18228.63 Y
18227.81 Z
7218.73 W
7221.3 X
7257.74 Y
7302.1 Z
6852.11
6853.72 X
6876.66 Y
6904.58 Z
104.9 W
105.17 X
109.01 Y
113.68 Z
124.8 W
125.07 X
128.91 Y
133.58 Z
163.31 W
163.72 X
169.48 Y
176.48 Z
194.9 W
195.3 X
201.06 Y
208.07 Z
229.68
230.22 X
237.85 Y
247.15 Z
272.96 W
273.49 X
281.13 Y
290.43 Z
52.36 W
52.52 X
54.81 Y
57.59 Z
61.62
61.78 X
64.07 Y
66.85 Z
78.71 W
78.93 X
81.99 Y
85.72 Z
93.67 W
X
Y
Z
108.88 W
109.16 X
112.99 Y
117.66 Z
129.02 W
129.29 X
133.13 Y
137.8 Z
61.15
61.31 X
63.59 Y
66.38 Z
72.65
72.81 X
75.1 Y
77.89 Z
92.56
92.78 X
95.84 Y
99.57 Z
110.83
111.04 X
114.11 Y
117.84 Z

X
Y
Z
151.15
151.4 X
154.87 Y
159.09 Z
186.74
187.01 X
190.84 Y
195.52 Z
216.7
217 X
221.2 Y
226.32 Z
1381.43
1395.3
1409.25 X
1607.25 Y
1848.34 Z
2445.51
2520.18
2669.52
1642.73 W
1659.16 X
1892.27 Y
2176.11 Z
1950.27 W
1969.77 X
2246.52 Y
2583.5 Z
2270.06 W
2292.76 X
2614.89 Y
Z
776.8 W
784.57 X
894.8 Y
1029.02 Z
2979.23 W
3009.03 X
3431.8 Y
3946.56 Z
785.56 W
793.42 X
904.89 Y
1040.63 Z
121.29 W
122.5 X
139.72 Y
160.67 Z
140.29 W
141.69 X
161.6 Y
185.84 Z
199.29 W
201.28 X
229.56 Y
264 Z
232.29 W
234.61 X
267.58 Y
307.71 Z
283.29 W
286.12 X
326.32 Y
375.27 Z
372.16 W
375.89 X
428.7 Y
493 Z
W
X
Y
Z
686.16 W
693.03 X
790.4 Y
908.96 Z
296.59 W
299.56 X
341.65 Y
392.9 Z
315.59 W
318.75 X
363.53 Y
418.06 Z
374.59 W
378.34 X
431.5 Y
496.22 Z
407.59 W
411.67 X
469.51 Y
539.94 Z
458.59 W
463.18 X
528.26 Y
607.5 Z
611.21 W
617.33 X
704.06 Y
809.67 Z
866.21 W
874.88 X
997.8 Y
1147.47 Z
925.21 W
934.47 X
1065.76 Y
1225.62 Z
3288.2 W
3321.08 X
3787.69 Y
4355.85 Z
3288.2 W
3321.08 X
3787.69 Y
4355.85 Z
313.14 W
316.27 X
360.71 Y
414.81 Z
462.5 W
467.13 X
532.76 Y
612.67 Z
412.82 W
416.95 X
475.53 Y
546.86 Z
453.14 W
457.67 X
521.97 Y
600.27 Z
397.62 W
401.6 X
458.02 Y
526.72 Z
45.78 W
46.24 X
52.73 Y
60.64 Z
Z
170.62 W
172.33 X
196.54 Y
226.02 Z
87.12 W
87.99 X
100.35 Y
115.41 Z
113.12 W
114.25 X
130.3 Y
149.85 Z
149.62 W
151.12 X
172.35 Y
198.2 Z
143.98 W
145.42 X
165.85 Y
190.73 Z
156.98 W
158.55 X
180.83 Y
207.95 Z
78.12 W
78.9 X
Y
Z
73.12 W
73.85 X
84.23 Y
96.86 Z
28.32 W
28.6 X
32.62 Y
37.52 Z
38.32 W
38.7 X
44.14 Y
50.76 Z
126.32 W
127.58 X
145.51 Y
167.33 Z
38603.96 W
38976.76 X
44266.97 Y
50708.43 Z
46703.96 W
47157.76 X
53597.4 Y
61438.42 Z
61398.98 W
61991.54 X
70400.26 Y
80638.85 Z
2684.79 W
2708.99 X
3052.4 Y
3470.54 Z
3987.6 W
4023.19 X
4528.22 Y
5143.17 Z
5824.6 W
5877.45 X
6627.42 Y
7540.59 Z
6364.79 W
6422.48 X
7241.13 Y
Z
3074.79 W
3102.89 X
3501.64 Y
3987.17 Z
4954.6 W
4999.86 X
Y
Z
6287.6 W
6345.08 X
7160.75 Y
8153.92 Z
8767.79
8849.51 X
Y
Z
143.16 W
144.59 X
164.91 Y
189.64 Z
188.82 W
190.71 X
217.5 Y
250.13 Z
354.48 W
358.02 X
408.33 Y
469.58 Z
544.48 W
549.92 X
627.19 Y
721.27 Z
934.48 W
943.82 X
1076.43 Y
1237.9 Z
116.12 W
117.28 X
133.76 Y
Z
83.52 W
84.36 X
96.21 Y
110.64 Z
97.52 W
98.5 X
112.33 Y
129.18 Z
5495.84 W
5547.83 X
6285.66 Y
7184.05 Z
6505.84 W
6567.93 X
7449.08 Y
8521.98 Z
8876.84 W
8962.64 X
10180.25 Y
11662.82 Z
9353.84 W
9444.41 X
10729.71 Y
12294.7 Z
12705.84 W
12829.93 X
14590.89 Y
16735.07 Z
17505.84
17677.93 X
20120.04 Y
23093.58 Z
13355.84
13486.43 X
15339.63 Y
17596.11 Z
19055.84 W
19243.43 X
21905.49 Y
25146.85 Z
2621.33 W
2647.54 X
3019.52 Y
3472.45 Z
4038.24 W
4078.62 X
4651.67 Y
5349.42 Z
6134.32 W
6195.66 X
7066.15 Y
8126.08 Z
7430.4 W
7504.7 X
8559.11 Y
9842.98 Z
9976.48 W
10076.24 X
11491.96 Y
13215.75 Z
10776.48 W
10884.24 X
12413.48 Y
14275.5 Z
17468.64 W
17643.33 X
20122.21 Y
23140.55 Z
20214.72 W
20416.87 X
23285.44 Y
26778.25 Z
21587.76 W
21803.64 X
24867.05 Y
28597.11 Z
27949.04 W
28228.53 X
32194.64 Y
Z
38989.63 W
39379.53 X
44912.35 Y
51649.2 Z
44489.63 W
44934.53 X
51247.83 Y
58935 Z
48933.36 W
49422.69 X
56366.58 Y
64821.57 Z
62921.6 W
63550.82 X
72479.71 Y
83351.66 Z
73663.76 W
74400.4 X
84853.65 Y
97581.7 Z
6773.68 W
6839.3 X
7770.42 Y
8904.17 Z
10606.52 W
10709.11 X
12164.96 Y
13937.63 Z
16721.02 W
16883.23 X
19185.14 Y
21987.97 Z
20240.5 W
20436.19 X
23213.23 Y
26594.59 Z
25869.27 W
26119.32 X
29667.69 Y
33988.24 Z
32574.02 W
32889.1 X
37360.14 Y
42804.16 Z
42130.64 W
42538.85 X
48331.47 Y
55384.66 Z
53617.43 W
54137.76 X
61521.63 Y
70512.34 Z
66543.21 W
67190.2 X
76371.29 Y
87550.33 Z
92195.75 W
93092.93 X
105824.41 Y
121326.46 Z
8265.13 W
8345.36 X
9483.89 Y
10870.19 Z
11796.85 W
11911.23 X
13534.44 Y
15510.87 Z
14535.76 W
14676.39 X
16671.98 Y
19101.85 Z
18706.77 W
18887.66 X
21454.63 Y
24580.22 Z
23370.82 W
23596.93 X
26805.46 Y
30712.23 Z
W
X
Y
Z
33190.97 W
33510.58 X
38045.99 Y
43568.37 Z
40213.63 W
40601.41 X
46104.16 Y
52804.41 Z
45432.42 W
45870 X
52079.44 Y
59640.16 Z
58564.01 W
59127.88 X
67129.42 Y
76872.23 Z
76354.21 W
77088.08 X
87502.01 Y
100182.17 Z
95211.97
96125.83 X
109094.05 Y
124884.36 Z
123021.11 W
X
Y
Z
129243.42 W
130481.15 X
148045.19 Y
169431.45 Z
7952.2 W
8028.94 X
9117.8 Y
10443.62 Z
11951.36 W
12066.75 X
13704.14 Y
15697.86 Z
16380.8 W
16538.93 X
18782.86 Y
21515.1 Z
22843.44 W
X
Y
Z
28560.75 W
28836.86 X
32754.92 Y
37525.61 Z
34907.2 W
35243.74 X
40019.5 Y
45834.55 Z
44700.18 W
45132.29 X
51264.13 Y
58730.36 Z
52001.07
52503.65 X
59635.47 Y
68319.3 Z
W
X
Y
Z
78636.56 W
79396.43 X
90179.31 Y
103308.72 Z
108675.26 W
109727.84 X
124664.44 Y
142851.48 Z
117891.14 W
119031.94 X
135220.46 Y
154931.85 Z
119469.35 W
120622.08 X
136979.93 Y
156897.51 Z
W
X
Y
Z
162245.97 W
163808.7 X
185984.66 Y
212986.45 Z
5682.84 W
5737.95 X
6520.08 Y
7472.4 Z
8525.4 W
8608.09 X
Y
Z
10753.63 W
10857.7 X
12334.42 Y
14132.51 Z
15261.27 W
15409.21 X
17508.65 Y
20064.97 Z
19605.35 W
19795.4 X
22492.34 Y
25776.17 Z
24695.26 W
24935.04 X
28337.54 Y
32480.48 Z
31703.77 W
32012.33 X
36390.87 Y
41722.25 Z
33397.73 W
33721.67 X
38318.53 Y
43915.73 Z
47191.4 W
47651.69 X
54183.42 Y
62136.55 Z
62506.44 W
63115.87 X
Y
Z
73981.88 W
74701.67 X
84915.83 Y
97352.75 Z
70.94 W
71.65 X
81.72 Y
93.97 Z
84.04 W
84.88 X
96.81 Y
111.33 Z
36.76 W
37.13 X
Y
Z
60.76 W
61.37 X
69.99 Y
80.49 Z
84.76 W
85.61 X
97.64 Y
112.28 Z
2144.47
2150.32 X
2233.41 Y
2334.57 Z
1726.87 W
1742.95 X
1971.1 Y
2248.9 Z
796.56 W
801.89 X
877.59 Y
969.77 Z
1474.1 W
1474.37 X
1478.21 Y
1482.88 Z
611.53 W
617.64 X
704.42 Y
810.08 Z
W
X
Y
Z
1014.48 W
1024.62 X
1168.58 Y
1343.87 Z
1222.59 W
1234.81 X
1408.31 Y
1619.55 Z
1641.37 W
1657.78 X
1890.7 Y
Z
2076.48 W
2097.24 X
2391.9 Y
2750.69 Z
2324.43 W
2347.67 X
2677.52 Y
3079.15 Z
2582.66 W
2608.49 X
2974.98 Y
3421.23 Z
2858.17 W
2886.75 X
3292.34 Y
3786.19 Z
3139.04 W
3170.43 X
3615.88 Y
4158.26 Z
3437.56 W
3471.93 X
3959.74 Y
4553.7 Z
4049.17 W
X
Y
Z
223.81 W
226.04 X
257.8 Y
296.47 Z
275.07 W
277.82 X
316.86 Y
364.39 Z
338.19 W
341.57 X
389.56 Y
447.99 Z
396.43 W
400.4 X
456.65 Y
525.15 Z
613.39 W
619.52 X
706.56 Y
812.55 Z
705.09 W
712.14 X
812.2 Y
934.03 Z
792.72 W
800.65 X
913.14 Y
1050.11 Z
933.09 W
942.42 X
1074.83 Y
1236.05 Z
1075.49 W
1086.25 X
1238.86 Y
1424.69 Z
1223.32 W
1235.55 X
1409.14 Y
1620.52 Z
1372.68 W
1386.41 X
1581.2 Y
1818.38 Z
1679.08 W
1695.87 X
1934.13 Y
2224.26 Z
6609.9 W
6627.74 X
6880.85 Y
Z
6824.08
6844.47 X
7133.85 Y
7486.2 Z
7023.24 W
7046.25 X
7372.71 Y
7770.21 Z
7229.18 W
7255.02 X
7621.62 Y
Z
7989.86 W
8020.76 X
8459.2 Y
8993.04 Z
8731.71 W
8767.96 X
9282.27 Y
9908.51 Z
9376.98 W
9418.11 X
10001.73 Y
10712.37 Z
9968.54 W
10014.55 X
10667.43 Y
11462.38 Z
10501.86 W
10552.93 X
11277.71 Y
12160.21 Z
11053.69 W
11109.84 X
11906.62 Y
12876.8 Z
11518.45 W
11579.66 X
12448.27 Y
13505.91 Z
12296.35 W
12367.71 X
13380.31 Y
14613.26 Z
51.45 W
51.96 X
59.27 Y
Z
69.21 W
69.9 X
79.72 Y
91.68 Z
96.49 W
97.46 X
111.15 Y
127.82 Z
130.18 W
131.49 X
149.96 Y
172.45 Z
173.67 W
175.4 X
200.05 Y
230.05 Z
215.33 W
217.48 X
Y
Z
258.81 W
261.4 X
298.12 Y
342.84 Z
300.47 W
303.48 X
346.11 Y
398.03 Z
343.69 W
347.13 X
395.9 Y
455.29 Z
385.61 W
389.47 X
444.19 Y
510.82 Z
W
X
Y
Z
510.34 W
515.44 X
587.86 Y
676.04 Z
5816.12 W
5874.28 X
Y
Z
1986.74 W
2006.61 X
2288.54 Y
2631.82 Z
3173.46 W
3205.19 X
3655.52 Y
4203.85 Z
3743.47 W
3780.9 X
4312.12 Y
4958.93 Z
5066.74 W
5117.41 X
5836.41 Y
6711.87 Z
5258.33 W
5310.91 X
6057.09 Y
6965.66 Z
7033 W
7103.33 X
8101.34 Y
9316.55 Z
2958.31 W
2978.13 X
3259.28 Y
3601.62 Z
4145 W
4176.68 X
4626.23 Y
5173.62 Z
59 W
59.59 X
67.96 Y
78.16 Z
63
63.63 X
72.57 Y
Z
89
89.89 X
102.52 Y
117.9 Z
131
132.31 X
150.9 Y
173.53 Z
158
159.58 X
182 Y
209.3 Z
W
X
Y
Z

104.03 X
118.65 Y
136.44 Z
141
142.41 X
162.42 Y
186.78 Z
145
146.45 X
Y
Z
184
185.84 X
211.95 Y
243.74 Z
187 W
188.87 X
215.41 Y
247.72 Z
190
191.9 X
218.86 Y
251.69 Z
359
362.59 X
413.53 Y
475.56 Z
362
X
Y
Z
362
365.62 X
416.99 Y
479.54 Z
387
390.87 X
445.79 Y
Z
410
414.1 X
472.28 Y
543.12 Z
410
414.1 X
472.28 Y
543.12 Z
410
414.1 X
472.28 Y
543.12 Z
410
414.1 X
472.28 Y
543.12 Z
W
X
Y
Z
47 W
47.47 X
54.14 Y
62.26 Z
63 W
63.63 X
72.57 Y
83.46 Z
89 W
89.89 X
102.52 Y
117.9 Z
131 W
132.31 X
Y
Z
158 W
159.58 X
182 Y
209.3 Z
170 W
171.7 X
195.82 Y
225.2 Z
58 W
58.58 X
66.81 Y
76.83 Z
63 W
63.63 X
72.57 Y
83.46 Z
96 W
96.96 X
110.58 Y
127.17 Z
109 W
110.09 X
125.56 Y
144.39 Z
116 W
117.16 X
Y
Z
150 W
151.5 X
172.79 Y
198.7 Z

X
Y
Z
191
192.91 X
220.01 Y
253.02 Z
221
223.21 X
254.57 Y
292.76 Z

X
Y
Z

X
Y
Z

X
Y
Z
159 W
160.59 X
183.15 Y
210.63 Z
231 W
233.31 X
Y
Z
273 W
275.73 X
314.47 Y
361.64 Z
437 W
441.37 X
503.38 Y
578.89 Z
683 W
689.83 X
786.75 Y
904.76 Z
887 W
895.87 X
1021.74 Y
1175 Z
W
X
Y
Z
273
275.73 X
314.47 Y
361.64 Z
273
275.73 X
314.47 Y
361.64 Z
437
441.37 X
503.38 Y
578.89 Z
437
441.37 X
503.38 Y
578.89 Z
437
441.37 X
503.38 Y
578.89 Z
683
689.83 X
786.75 Y
904.76 Z
683 W
X
Y
Z
683
689.83 X
786.75 Y
904.76 Z
683
689.83 X
786.75 Y
Z
887
895.87 X
1021.74 Y
1175 Z
887
895.87 X
1021.74 Y
1175 Z
887
895.87 X
1021.74 Y
1175 Z

X
Y
Z

X
Y
Z
179
180.79 X
206.19 Y
237.12 Z
200
202 X
230.38 Y
264.94 Z
205
207.05 X
236.14 Y
271.56 Z
273
275.73 X
314.47 Y
361.64 Z
273
X
Y
Z
273
275.73 X
314.47 Y
361.64 Z
437
441.37 X
503.38 Y
578.89 Z
437
441.37 X
503.38 Y
578.89 Z
437
441.37 X
503.38 Y
578.89 Z
437 W
441.37 X
503.38 Y
578.89 Z
683
689.83 X
786.75 Y
904.76 Z
683
689.83 X
Y
Z
683
689.83 X
786.75 Y
904.76 Z
683
689.83 X
786.75 Y
904.76 Z
683
689.83 X
786.75 Y
904.76 Z
887
895.87 X
1021.74 Y
1175 Z
887
X
Y
Z
887
895.87 X
1021.74 Y
1175 Z
887
895.87 X
1021.74 Y
1175 Z
887
895.87 X
1021.74 Y
1175 Z
887
895.87 X
1021.74 Y
1175 Z
179
180.79 X
206.19 Y
237.12 Z
200
202 X
230.38 Y
264.94 Z

X
Y
Z
273
275.73 X
314.47 Y
361.64 Z
273
275.73 X
314.47 Y
361.64 Z
273
275.73 X
314.47 Y
361.64 Z
437
441.37 X
503.38 Y
578.89 Z
437
441.37 X
Y
Z
437
441.37 X
503.38 Y
578.89 Z
437
441.37 X
503.38 Y
578.89 Z
683
689.83 X
786.75 Y
904.76 Z
683
689.83 X
786.75 Y
904.76 Z
683
X
Y
Z
683
689.83 X
786.75 Y
904.76 Z
683
689.83 X
786.75 Y
904.76 Z
887
895.87 X
1021.74 Y
1175 Z
887
895.87 X
1021.74 Y
1175 Z
887
895.87 X
1021.74 Y
1175 Z
887
895.87 X
1021.74 Y
1175 Z
887
X
Y
Z
887
895.87 X
1021.74 Y
1175 Z
190
191.9 X
Y
Z
230
232.3 X
264.94 Y
304.68 Z
237
239.37 X
273 Y
313.95 Z
277
279.77 X
319.08 Y
366.94 Z
286
288.86 X
329.44 Y
378.86 Z

X
Y
Z

X
Y
Z
538
543.38 X
619.72 Y
Z

X
Y
Z

X
Y
Z

X
Y
Z
965
974.65 X
1111.59 Y
1278.33 Z
W
X
Y
Z
227
229.27 X
261.48 Y
300.7 Z
W
X
Y
Z
313
316.13 X
360.55 Y
414.63 Z
320
323.2 X
368.61 Y
Z
W
X
Y
Z
W
X
Y
Z
649 W
655.49 X
747.59 Y
859.72 Z
W
X
Y
Z
W
X
Y
Z

X
Y
Z

X
Y
Z
276
278.76 X
317.93 Y
365.61 Z
295
297.95 X
339.81 Y
390.78 Z
424
428.24 X
488.41 Y
561.67 Z
629
635.29 X
724.55 Y
833.23 Z
W
X
Y
Z
1176
1187.76 X
1354.64 Y
1557.84 Z
W
X
Y
Z
191
192.91 X
220.01 Y
253.02 Z
191
192.91 X
220.01 Y
Z

X
Y
Z
W
X
Y
Z
478
482.78 X
550.61 Y
633.2 Z

X
Y
Z

X
Y
Z

X
Y
Z
Z
W
X
Y
Z
Y
Z
45 W
45.45 X
51.84 Y
59.61 Z
64 W
64.64 X
73.72 Y
84.78 Z
84 W
84.84 X
96.76 Y
111.27 Z
163 W
164.63 X
187.76 Y
215.92 Z
236 W
238.36 X
271.85 Y
312.63 Z
299 W
301.99 X
344.42 Y
396.08 Z
214
216.14 X
246.51 Y
283.48 Z
271
273.71 X
312.17 Y
358.99 Z
407
411.07 X
468.83 Y
539.15 Z
5536.23 W
5591.59 X
6377.21 Y
7333.79 Z
9123.65 W
9214.88 X
10509.57 Y
12086.01 Z
15383.8 W
15537.63 X
17720.67 Y
20378.77 Z
23299.81 W
23532.81 X
26839.17 Y
30865.04 Z
32760.78 W
33088.39 X

1865.2 W
1871.46 X
1960.32 Y
2068.53 Z
1889.5 W

1867.85
1874.55 X

1892.15 W
1898.85 X

1940.46 W
1948.22 X

1964.76 W
1972.52 X

272.71 W
275.43 X
314.13 Y
361.25 Z
301.58 W
304.6 X
347.39 Y
Z
320.83 W
324.04 X
369.57 Y
425 Z
340.08 W
343.48 X
391.74 Y
450.5 Z
359.33 W
362.92 X
413.91 Y
476 Z
413.87 W
418.01 X
476.74 Y
548.25 Z
452.37 W
456.89 X
521.09 Y
599.25 Z
471.62 W
476.34 X
543.26 Y
624.75 Z
2730.02 W
2757.32 X
3144.73 Y
3616.43 Z
3005.19 W
3035.25 X
3461.7 Y
3980.95 Z

9536.77 W
9632.14 X
10985.46 Y
12633.28 Z
11449.39 W
11563.88 X
13188.61 Y
15166.9 Z
13626.45 W
13762.71 X
15696.37 Y
18050.83 Z
17744.88 W
17922.33 X
20440.42 Y
23506.48 Z
21291.23 W
21504.15 X
24525.48 Y
28204.3 Z
29019.06 W
29309.25 X
33427.2 Y
38441.28 Z
33950.89 W
34290.4 X
39108.2 Y
44974.43 Z
37826.82 W
38205.09 X
43572.9 Y
50108.84 Z
42057.01 W
42477.58 X
48445.68 Y
55712.53 Z
9122.38 W
9136.11 X
9331.03 Y
9568.36 Z

18926.61 W
18970.03 X
19586.22 Y
20336.51 Z
19100.47 W
19143.89 X
19760.09 Y
20510.37 Z
23121.65 W
23211.16 X

23271.21

6273.66
6458.74
7512.43
7733.03
9199.8 W
9209.58 X
9348.45 Y
9517.54 Z
9289.59 W
9299.37 X
9438.24 Y
9607.33 Z
17822.38
17832.51 X

18054.25 W
18064.38 X
18208.07 Y
18383.04 Z
38578.08 W
38588.21 X
38731.91 Y
38906.87 Z
39247.48 W
39257.61 X
39401.31 Y
39576.27 Z
240.53 W

211.73 W
213.59 X
239.9 Y
271.94 Z
273.3 W
275.44 X
305.82 Y
342.82 Z
282.09 W
284.65 X
320.95 Y
365.14 Z
253.29 W
255.56 X
287.77 Y
326.99 Z
962.8 W
972.43 X
1109.05 Y
1275.41 Z
2365.44 W
2389.09 X
2724.76 Y
3133.48 Z
5070.74 W
5121.45 X
5841.01 Y
6717.16 Z
953.73
960.89 X
1062.43 Y
1186.07 Z
794.19 W
800.35 X
887.7 Y
994.06 Z
794.19 W
800.35 X
887.7 Y
994.06 Z
954.97 W
962.14 X
1063.86 Y
1187.71 Z
800.43 W
806.65 X
894.88 Y

1126.23 W
1135.71 X
1270.18 Y
1433.91 Z
1416.23 W
1428.61 X
1604.23 Y
1818.07 Z
492.02 W
496.95 X
566.77 Y
651.78 Z
340.99
343.21 X
374.79 Y
413.25 Z
418.05 W
420.29 X
452.02 Y
490.66 Z
615.7 W
618.66 X
660.63 Y
711.74 Z
6026.89 W
6055.68 X
6464.19 Y
6961.6 Z
8400.78 W
8441.28 X
9015.94 Y
9715.66 Z
1955.49 W
1962.67 X
2064.63 Y
2188.78 Z
2548.05 W
2558.79 X
2711.16 Y
2896.69 Z
1051.88 W
1052.02 X
1054.05 Y
1056.52 Z
1848.74 W
1848.88 X
1850.91 Y
1853.38 Z
3496.42 W
3496.72 X
3501.04 Y
3506.3 Z
2678.04 W
2678.35 X
2682.66 Y
2687.92 Z
843.11 W
843.15 X
843.66 Y
844.29 Z
1004.22
1004.26 X
1004.77 Y
1005.4 Z
549.75 X
554.08 Y
559.35 Z

2877.97 W
2878.45 X
2885.2 Y
2893.42 Z
2675.81 W
2676.36 X
2684.15 Y
2693.63 Z
228.13 W
228.7 X
236.74 Y
246.53 Z
4221.42 W
4227.87 X
4319.39 Y
4430.83 Z
4806.03 W
4808.43 X
4842.5 Y
4883.98 Z
8064.95 W
8073.96 X
8201.84 Y
8357.55 Z
4798.82 W
4813.37 X
5019.94 Y
5271.45 Z
5573.46 W
5587.24 X
5782.88 Y
6021.09 Z
6569.72 W
6583.25 X
6775.24 Y
7009.02 Z
4371.39
4766.67
5547.8
16940.72 W
17075.03 X
18981.06 Y
21301.86 Z
1836.42 W
1849.69 X
2038.02 Y
2267.35 Z
241.81 W
244.23 X

324.94 W
328.19 X
374.3 Y
430.45 Z
16493.28 W
16658.21 X
18998.69 Y
21848.5 Z
21523.54 W
21738.77 X
24793.07 Y
28512.03 Z
33893.47 W
34232.41 X
39042.06 Y
Z
41929.4 W
42348.69 X
48298.68 Y
55543.49 Z
55063.41 W
55614.04 X
63427.82 Y
72941.99 Z
101044.98 W

18863.28 W
19051.91 X
21728.71 Y
24988.01 Z
47333.47 W
47806.81 X
54523.67 Y
62702.22 Z
58729.4 W
59316.69 X
67650.69 Y
77798.29 Z
69763.41 W
70461.04 X
80360.82 Y
92414.94 Z
142614.3 W
144040.44 X
164278.13 Y
188919.84 Z
35453.5 W
35633.97 X
38194.92 Y
41313.16 Z
43443.13 W
43657.03 X
46692.4 Y
50388.31 Z
52484.23 W
52736.87 X
56322.07 Y
60687.45 Z
57889.28 W
58138.77 X
61679.08 Y
65989.83 Z
74770.73 W
75059.35 X
79154.97 Y
83519.23 W
83810.04 X
87936.67 Y
92961.33 Z
99149.1 W
99435.31 X
103496.8 Y
108442.12 Z
142936.24 W
143262.95 X
147899.17 Y
153544.31 Z
29419.56 W
29493.23 X
30538.58 Y
31811.42 Z
34883.38 W
34960.02 X
36047.57 Y
37371.78 Z
55724.75 W
55822.91 X
57215.81 Y
67833.46 W
68119.97 X
72185.73 Y
77136.26 Z
74064.75 W
74346.31 X
78341.74 Y
83206.65 Z
83371.23 W
83660.56 X
87766.19 Y
92765.27 Z
100033.54 W
100328.6 X
104515.59 Y
109613.73 Z
146292.04
22977.16 W
23104.44 X
24910.52 Y
25899.68 W
26026.5 X
27826.1 Y
30017.33 Z
29381.8 W
29509.18 X
31316.77 Y
33517.73 Z
1233.08 W
1243.12 X
1385.63 Y
1559.15 Z
1450.01 W
1460.14 X
1603.91 Y
1778.96 Z
1580.76 W
1590.95 X
1735.55 Y
1911.63 Z
1767.31 W
1777.91 X
1928.32 Y
2111.47 Z
47156.76 W
47348.74 X
50072.94 Y
53389.97 Z
57573.04 W
57794.55 X
60937.8 Y
64765.07 Z
62918.73 W
63110.7 X
65834.91 Y
69151.94 Z
72108.57 W
72300.54 X
75024.75 Y
78341.78 Z
140391.86 W
194082.8 W
194274.77 X
196998.97 Y
40000
40400 X
46076.2 Y
52987.63 Z

X
Y
45000
45450 X
51835.73 Y
59611.08 Z
23000
23230 X
26493.82 Y
30467.89 Z
50000 W
50500 X
57595.25 Y
66234.54 Z

X
Y
Z
15000
15150 X
17278.58 Y
19870.36 Z
23000 W
23230 X
26493.82 Y
30467.89 Z

W
X
Y
Z
W
X
Y
Z
637.99 W
644.37 X
734.91 Y
845.14 Z

1400.1
1437.44
1474.77
1493.44
1549.44
A

67.12

0
66.49 A
78.00 A
30
35
35
48

45000

40000
50000
2030
3143
4765
5145
13.52
16.12
16.12
18.98
18.98
27.04
27.04
16.12
16.12
10.66
10.66
13.52
13.52
18.98
18.98
27.04
27.04
884
884
884
884
884
3295.95 A
A
A
A
W
W
W
W
W

W
W
4311.85
186.35
251.9
305.7
594.15
397.65

274.3
274.3
384
639.55
913.8

5634.95
2561.25
3936.1
17607.45
2238.5
2727.8
7343.95
10028.5
20069.05
30772.55
39469.15
W
X
Y
Z
W
X
Y
Z
W
X
Y
Z
W
X
Y
Z
W
X
Y
Z

X
Y

X
Y
Z

X
Y
Z

X
Y
Z

X
Y
Z

X
Y
Z
W
X

X
Y
Z

Z
Z
X
Y
Z
200316.01 Z
Description Unit Quantity Rate Amount

Providing and fixing tiled false ceiling of specified materials


of size 595x595 mm in true horizontal level, suspended on
inter locking metal grid of hot dipped galvanized steel
sections ( galvanized @ 120 grams/ sqm, both side
inclusive) consisting of main "T" runner with suitably spaced
joints to get required length and of size 24x38 mm made
from 0.30 mm thick (minimum) sheet, spaced at 1200 mm
center to center and cross "T" of size 24x25 mm made of
0.30 mm thick (minimum) sheet, 1200 mm long spaced
between main "T" at 600 mm center to center to form a
grid of 1200x600 mm and secondary cross "T" of length 600
mm and size 24x25 mm made of 0.30 mm thick (minimum)
sheet to be interlocked at middle of the 1200x600 mm
panel to form grids of 600x600 mm and wall angle of size
24x24x0.3 mm and laying false ceiling tiles of approved
texture in the grid including, required cutting/making,
opening for services like diffusers, grills, light fittings,
fixtures, smoke detectors etc. Main "T" runners to be
suspended from ceiling using GI slotted cleats of size 27 x
37 x 25 x1.6 mm fixed to ceiling with 12.5 mm dia and 50
mm long dash fasteners, 4 mm GI adjustable rods with
galvanised butterfly level clips of size 85 x 30 x 0.8 mm
spaced at 1200 mm center to center along main T, bottom
exposed width of 24 mm of all T-sections shall be
prepainted with polyester paint, all complete for all heights
as per specifications, drawings and as directed by Engineer-
in-charge.
6 mm thick square edge Everest fibre cement board ceiling
Tile of size 595x595 mm,
Details of cost for 100 sqm.
MATERIAL
Celling Area =100 sqm
Add wastage @ 5% = 0.05 sqm.
Total=100.05 sqm
6 mm thick square edge Everest fibre cement board ceiling
Tile of size 595x595 mm, Sqm 105 400
8611 Main T ceiling sections 24x38x0.3 mm each 29.5 115.00
(3 metre long) 0.00
Including Wastage @ 10% 0.00
8612 Perimeter wall angle 24x24x0.3mm each 13.5 80.00
(3 metre long) 0.00
Including Wastage @ 10% 0.00
8613 Intermediate cross T-section 24x25x each 147 35.00
0.3mm (1.2 mtrs long) 0.00
Including Wastage @ 10% on Grid for cut outs 0.00
8614 Intermediate cross T-section 24x25x each 147 17.00
0.3mm (0.6 mtrs long) 0.00
Including Wastage @ 10% on Grid for cut outs 0.00
8615 Hanger rod 4 mm thick each 72 8.00
8616 Adjustment clip 85x30x0.8mm each 72 5.00
8617 Soffit cleat (Size 27x37x25x1.60mm) each 72 4.00
7388 Dash hold fastener 12.5 mm dia, 40 mm long each 72 11.00
with 6 mm dia bolt 0.00
9999 Sundries i.e. scaffolding etc. L.S. 187.95 2.00
9977 Carriage of materials etc. L.S. 89.28 2.00
LABOUR 0.00
14 Carpenter 1st class day 28 505.17
17 Beldar day 23 350.00
TOTAL
Add 1 % Water charges on "W"
TOTAL
Add GST (multiplying factor 0.1405) on "X"
TOTAL
Add 15 % Contractor's profit and overheads on "Y"
Total
Add Cess @ 1% on "Z"
Cost of 100 sqm.
Cost of 1 sqm.
Say

Providing and fixing M.S. BP Sheet 1.66mm to


20mm thick in eaves board/facia/soffits/ceiling
including cutting, fixing and welding to steel roof
members and applying a coat of red lead primer
complete as per the instruction of Engineer-in-
charge (Base members of steel work shall be
measured & paid separtely)

Detail of cost for 6.50 sqm


Materials
B.P. sheet 1.66 mm to 2mm thick
Front facia = 1x10x0.20 =2.00 sqm.
soffit =1x10x0.45 =4.50 sqm
Total =6.50 sqm
Weight 6.50x15.69 kg/sqm =102 kg.
Add. 5% wastage =5.10 kg.
Total =107.10 kg Kg. 107.1 65
1215
Welding charges cms 590 2
Front side 25% of total length
1x10x25 % =2.50 or 250 cms.
Base member @ 30cm c/c
10/0.30+1 =34x5x2 =340 cms
Total =590 cms
Priming coat
2x6.50 =13.00 sqm
13.50.3 as per 13.50.3= marked A sqm 13 26.29
2205 CARRIAGE Tonne 0.107 94.34
LABOUR :
Black Smith 1st class each 0.5 505.17
Beldar each 0.5 350.00
Bhandhani each 0.2 350.00
Sundries L.S. 1 2
TOTAL :
Add 1 % Water charges on "W"
TOTAL
Add GST (multiplying factor 0.1405) on "X"
TOTAL
Add 15 % Contractor's profit and overheads on "Y"
TOTAL
Add Cess @ 1% on "Z"
Cost of 6.50 sqm.
Cost of 1 sqm.
(ii) Providing and fixing double shutters (glazed and wire
guage) NCL seccolor window / ventilators ( double
rebate) Eco 4000 series or equivalent fabricated from
roll framed section made of glavanised steel colour
coated/powder quoted ( base steel as per IS 513 of D
quality galvanised as per IS 277 with zink of 120
gram/square metre) with total coated thickness of
0.60mm (zero point sixty millimetre). Quoted section
should be with primer coat of epoxy primer of 5-7
microns thick, finish painted with polyseter paint of 12-
16 microns thick or powder coated with pure polyster
upto 50-60 microns thick. Section for frames should be of
72mm X 55mm (seventy two into fifty five millimetre)
section of mullion should be of 72mm x 50mm (seventy
two into fifty millimetre). Section for shutter frame
should be of 47mm X 20mm (fourty seven into twenty
millimetre) section for fixed glass bead should be of
12mm X 12mm (twelve into twelve millimetre) and
section for flymess should be 40mm X 20mm (forty into
twenty millimetre) section for frame glazed shutters and
mesh shutters should be cut to length and miter jointed
with polypropylene corner bracket mullion section
should be jointed with frame/mullion using mullion cap
ethyl propylene damien monomer(EPDM) gasket should
be used all around glass in shutter in fixed glass, rubber
gasket should be used around flymesh to fix mesh in
mesh shutters. Each glazed shutter and mesh shutters
should be provided with SS Pivot Hinges-1 set, seccolor
handle and seccolor stay window frame should be fixed
to brick/concrete mansonary by using nylon self
Detail of cost for 1.00 sqm

Materials
Eco 4000 series(Double Sqm 1 4900
Rebate) window & Single Rebate and Double Rebate
Door Frames including double shutter frame .

CARRIAGE
1 KM by Mech. Trpt. L.S
100 Mtrs by head Load L.S
TOTAL :
Add 1 % Water charges on "W"
TOTAL
Add GST (multiplying factor 0.1405) on "X"
TOTAL
Add 15 % Contractor's profit and overheads on "Y"
TOTAL
Add Cess @ 1% on "Z"
Cost of 1 sqm.
Cost of 1 sqm.
(ii) Providing and fixing 4 MM Plain Float Glass to NCL
seccolor window / ventilators ( double rebate) Eco 4000
series as per entire satification of Engineer in charge.
including carriage of materials with in all leads lifts and
other incidentals as per direction of Engineer-in-Charge.
The rate includes, octroi, Malkhana , Toll tax , Goods and
Service Tax, building and other constrction worker,
welfare cess royalty or any other tax, levy or cess in
respect of input for or output by this contract shall be
payable by the contractor and Government shall not
entertain any claim whatsoever in this respect of the
same.

Detail of cost for 1.00 sqm

Materials
2406 Glass of 4 MM Plain Float Glass. Sqm 1 300
CARRIAGE
1 KM by Mech. Trpt. L.S 1 10.8
100 Mtrs by head Load L.S 1 2.16
TOTAL :
Add 1 % Water charges on "W"
TOTAL
Add GST (multiplying factor 0.1405) on "X"
TOTAL
Add 15 % Contractor's profit and overheads on "Y"
TOTAL
Add Cess @ 1% on "Z"
Cost of 1 sqm.
Cost of 1 sqm.

(ii) Providing and fixing Stainless Steel 32 gauge Fly mesh of


304 grades with 144 holes per square Inch to NCL seccolor
window / ventilators ( double rebate) Eco 4000 series as per
entire satification of Engineer in charge. including carriage of
materials with in all leads lifts and other incidentals as per
direction of Engineer-in-Charge. The rate includes, octroi,
Malkhana , Toll tax , Goods and Service Tax, building and other
constrction worker, welfare cess royalty or any other tax, levy
or cess in respect of input for or output by this contract shall
be payable by the contractor and Government shall not
entertain any claim whatsoever in this respect of the same.

Detail of cost for 1.00 sqm


Materials
Sqm 1 350
Stainless Steel 32 gauge Fly
10004 mesh of 304 grades with 144 holes per square Inch.
CARRIAGE
L.S 1 20
TOTAL :
Add 1 % Water charges on "W"
TOTAL
Add GST (multiplying factor 0.1405) on "X"
TOTAL
Add 15 % Contractor's profit and overheads on "Y"
TOTAL
Add Cess @ 1% on "Z"
Cost of 1 sqm.
Cost of 1 sqm.

(ii) Providing and fixing provided with Grill made of 10mm sq.
MS Bars welded to at 150mm center-to-center, 6mm x 12mm
MS flat. Total grill unit should be powder coated and fixed to
window frame with screws. to NCL seccolor window /
ventilators ( double rebate) Eco 4000 series as per entire
satification of Engineer in charge. including carriage of
materials with in all leads lifts and other incidentals as per
direction of Engineer-in-Charge. The rate includes, octroi,
Malkhana , Toll tax , Goods and Service Tax, building and other
constrction worker, welfare cess royalty or any other tax, levy
or cess in respect of input for or output by this contract shall
be payable by the contractor and Government shall not
entertain any claim whatsoever in this respect of the same.

Detail of cost for 1.00 sqm =10.00kg


Materials
Sqm 1 870
Grill made of 10mm sq. MS Bars welded to at 150mm
center-to-center, 6mm x 12mm MS flat. Total grill unit
should be powder coated and fixed to window frame
10005 with screws.
CARRIAGE
1 KM by Mech. Trpt. L.S
100 Mtrs by head Load L.S
TOTAL :
Add 1 % Water charges on "W"
TOTAL
Add GST (multiplying factor 0.1405) on "X"
TOTAL
Add 15 % Contractor's profit and overheads on "Y"
TOTAL
Add Cess @ 1% on "Z"
Cost of 1 sqm.
Cost of 1 sqm.
Providing and fixing door (SINGLE REBATE) frame fabricated
from sections roll formed out of 1.2mm thick galvanized
steel (Base steel as per IS 513) with zinc of 120 gms/sq.mtr.
The overall size of the section should be 105x60mm with
rebate of 37mm for shutter. The frame section should be
cut to length and metre joined with corner brackets made
of CRCA electroplated. The frame should be provided with
(a) 3 Nos. of M.S. powder coated 4” Butt hinges of 2mm
thickness welded to the frame. (b) 6 Nos. of 1.2mm thick
CRCA electroplated stiffeners should be welded to frame.(c)
6 Nos. of 8” M.S. hold fasts with split end tail welded to
stiffener plates.(d) one no. aldrop receiver.(e) Each frame
should be provided with 25x50mm tie rod at bottom. All
welded places should be treated with protective coat of
zinc rich primer. The entire frame should be provided with
a coat of etched primer.

Detail of cost for 5.00 Rmt


Materials
Rmt 5 720
Door frame fabricated from sections roll formed out of
1.2mm thick galvanized steel (Base steel as per IS
513) with zinc of 120
10006 gms/sq.mtr.
CARRIAGE LS 1 50
TOTAL :
Add 1 % Water charges on "W"
TOTAL
Add GST (multiplying factor 0.1405) on "X"
TOTAL
Add 15 % Contractor's profit and overheads on "Y"
TOTAL
Add Cess @ 1% on "Z"
Cost of 5 Rmt.
Cost of 1 Rmt.
Providing and fixing double rebate door frame fabricated
from sections roll formed out of 1.2mm thick galvanized
steel (Base steel as per IS 513) with zinc of 120 gms/sq.mtr.
The overall size of the section should be 125x60mm. The
frame section should be cut to length and meter joined
with corner brackets made of CRCA electroplated. The
frame should be provided with ..... (a) 3 Nos. of M.S.
powder coated 4” Butt hinges of 2mm thickness welded to
the main frame. (b) 6 Nos. of 1.2mm thick CRCA
electroplated stiffeners should be welded to frame. (c) 6
Nos. of 8” M.S. hold fasts with split end tail welded to
stiffener plates (d) One no. aldrop receiver. (e) Each frame
should be provided with 25x50mm tie rod at bottom. All
welded places should be treated with protective coat of
zinc rich primer. The entire frame should be provided with a
coat of etch primer.

Detail of cost for 5.00 Rmt


Materials
10007 double rebate door frame Rmt 5 795
CARRIAGE LS 1 90
TOTAL :
Add 1 % Water charges on "W"
TOTAL
Add GST (multiplying factor 0.1405) on "X"
TOTAL
Add 15 % Contractor's profit and overheads on "Y"
TOTAL
Add Cess @ 1% on "Z"
Cost of 5 Rmt.
Cost of 1 Rmt.
Providing and fixing uni stone cladding 12mm (twelve
millimetre) thick specified size of approved shade and
sample cladding both surface as on faces of arch
masonary wall etc. on 12mm (twelve millimetre) thick
cement plaster 1:3 (one cement : three sand) jointed
with cement slurry including scaffolding etc.including
carriage of materials with in all leads lifts and other
incidentals as per direction of Engineer-in-Charge. The
rate includes, octroi, Malkhana , Toll tax , Goods and
Service Tax, building and other constrction worker,
welfare cess royalty or any other tax, levy or cess in
respect of input for or output by this contract shall be
payable by the contractor and Government shall not
entertain any claim whatsoever in this respect of the
same
Detail of cost for 1.00 sqm
Materials
10008 uni stone cladding Sqm 1
Add 5% for wastage 0.05
1.05 500

3.8 Cement mortar 1:4 Mix Cum 0.014 4129.00


9999 Mortar for pointing LS 25.38 2
367 Portland Cement tonne 0.0033 4375
0023 Mason (brick layer) 1st class day 1 505.17
0017 Beldar day 1 350.00
9999 Sundries etc. LS 16.9 2
CARRIAGE LS 3.95 2
TOTAL :
Add 1 % Water charges on "W"
TOTAL
Add GST (multiplying factor 0.1405) on "X"
TOTAL
Add 15 % Contractor's profit and overheads on "Y"
TOTAL
Add Cess @ 1% on "Z"
Cost of 1 sqm.
Cost of 1 sqm.

3.116 Providing and fixing ISI marked high pressure PVC spigot
and socket, waste and ventilating pipes including fixing with
approved adhesive etc. complete.
i) 150 mm dia.
Detail of cost for 10 pipes of 3.00 mtr long = 30.00 metres

MATERIALS:
150 mm dia PVC pipe ISI marked. mtr 30 330
5 % allowance for westage.
Rubber gaskit / Adhasive L.S.
CARRIAGE:
Carriage of 150 mm dia PVC pipe. L.S.
LABOUR:
19 Fitter Each 0.34 505.17
1 Bandhani Each 0.17 350.00
Beldar Each 0.67 350.00
Scaffolding L.S.
TOTAL :
Add 1 % Water charges on "W"
TOTAL
Add GST (multiplying factor 0.1405) on "X"
TOTAL
Add 15 % Contractor's profit and overheads on "Y"
TOTAL
Add Cess @ 1% on "Z"
Cost of 30 Rmt.
Cost of 1 Rmt.

ii) 110 mm dia.


Detail of cost for 10 pipes of 3.00 mtr long = 30.00 metres

MATERIALS:
7189 110 mm dia PVC pipe ISI marked. (3.00 metre long) mtr 30 250
5 % allowance for westage.
Rubber gaskit / Adhasive L.S.
CARRIAGE:
Carriage of 110 mm dia PVC pipe. L.S.
LABOUR:
Fitter Each 0.34 505.17
Bandhani Each 0.17 350.00
Beldar Each 0.67 350.00
Scaffolding L.S.
TOTAL :
Add 1 % Water charges on "W"
TOTAL
Add GST (multiplying factor 0.1405) on "X"
TOTAL
Add 15 % Contractor's profit and overheads on "Y"
TOTAL
Add Cess @ 1% on "Z"
Cost of 30 Rmt.
Cost of 1 Rmt.

iv) 75 mm dia.
Detail of cost for 10 pipes of 3.00 mtr long = 30.00 metres

MATERIALS:
7188 75 mm dia PVC pipe ISI marked. (3.00 metre long) mtr 30 220
5 % allowance for westage.
Rubber gaskit / Adhasive L.S.
CARRIAGE:
Carriage of 75mm dia PVC pipe. L.S.
LABOUR:
Fitter Each 0.34 505.17
Bandhani Each 0.17 350.00
Beldar Each 0.67 350.00
Scaffolding L.S.
TOTAL :
Add 1 % Water charges on "W"
TOTAL
Add GST (multiplying factor 0.1405) on "X"
TOTAL
Add 15 % Contractor's profit and overheads on "Y"
TOTAL
Add Cess @ 1% on "Z"
Cost of 30 Rmt.
Cost of 1 Rmt.

3.117 Providing and fixing PVC single equal branch with oval
access door, insertion rubber washer 3 mm thick bolts and
nuts complete including fixing with approved adhesive etc.
complete.

i) 150 mm dia.
Detail of cost for one branch.
MATERIALS:
10010 150 mm dia PVC single equal branch with oval access door, Each
bolts and nuts etc.
1.00 350.00
Rubber gaskit / Adhasive L.S.
CARRIAGE:
Carriage of material L.S.
LABOUR:
Fixing charges L.S.
TOTAL :
Add 1 % Water charges on "W"
TOTAL
Add GST (multiplying factor 0.1405) on "X"
TOTAL
Add 15 % Contractor's profit and overheads on "Y"
TOTAL
Add Cess @ 1% on "Z"
Cost of 1 No.
Cost of 1 No.

ii) 110 mm dia.


Detail of cost for one branch.
MATERIALS:
10011 110 mm dia PVC single equal branch with oval access door, Each
bolts and nuts etc.
1.00 275.00
Rubber gaskit / Adhasive L.S.
CARRIAGE:
Carriage of material L.S.
LABOUR:
Fixing charges L.S.
TOTAL :
Add 1 % Water charges on "W"
TOTAL
Add GST (multiplying factor 0.1405) on "X"
TOTAL
Add 15 % Contractor's profit and overheads on "Y"
TOTAL
Add Cess @ 1% on "Z"
Cost of 1 No.
Cost of 1 No.

iv) 75 mm dia.
Detail of cost for one branch.
MATERIALS:
10012 75 mm dia PVC single equal branch with oval access door, Each
bolts and nuts etc.
1.00 225.00
Rubber gaskit / Adhasive L.S.
CARRIAGE:
Carriage of material L.S.
LABOUR:
Fixing charges L.S.
TOTAL :
Add 1 % Water charges on "W"
TOTAL
Add GST (multiplying factor 0.1405) on "X"
TOTAL
Add 15 % Contractor's profit and overheads on "Y"
TOTAL
Add Cess @ 1% on "Z"
Cost of 1 No.
Cost of 1 No.

3.118 Providing and fixing PVC door bend with oval access door,
insertion rubber washer 3 mm thick bolts and nuts
complete including fixing with approved adhesive etc.
complete.

i) 150 mm dia.
Detail of cost for one bend.
MATERIALS:
10013 150 mm dia PVC door bend with oval access door, bolts and Each 1 350
nuts etc.
Rubber gaskit / Adhasive L.S.
CARRIAGE:
Carriage of material L.S.
LABOUR:
Fixing charges L.S.
TOTAL :
Add 1 % Water charges on "W"
TOTAL
Add GST (multiplying factor 0.1405) on "X"
TOTAL
Add 15 % Contractor's profit and overheads on "Y"
TOTAL
Add Cess @ 1% on "Z"
Cost of 1 No.
Cost of 1 No.

ii) 110 mm dia.


Detail of cost for one bend.
MATERIALS:
10014 110 mm dia PVC door bend with oval access door, bolts and Each 1 275
nuts etc.
Rubber gaskit / Adhasive L.S.
CARRIAGE:
Carriage of material L.S.
LABOUR:
Fixing charges L.S.
TOTAL :
Add 1 % Water charges on "W"
TOTAL
Add GST (multiplying factor 0.1405) on "X"
TOTAL
Add 15 % Contractor's profit and overheads on "Y"
TOTAL
Add Cess @ 1% on "Z"
Cost of 1 No.
Cost of 1 No.

iv) 75 mm dia.
Detail of cost for one bend.
MATERIALS:
10015 75 mm dia PVC door bend with oval access door, bolts and Each 1 225
nuts etc.
Rubber gaskit / Adhasive L.S.
CARRIAGE:
Carriage of material L.S.
LABOUR:
Fixing charges L.S.
TOTAL :
Add 1 % Water charges on "W"
TOTAL
Add GST (multiplying factor 0.1405) on "X"
TOTAL
Add 15 % Contractor's profit and overheads on "Y"
TOTAL
Add Cess @ 1% on "Z"
Cost of 1 No.
Cost of 1 No.

3.119 Providing and fixing PVC single equal branch plain including
fixing with approved adhesive etc. complete.

i) 150 mm dia.
Detail of cost for one branch.
MATERIALS:
10016 150 mm dia PVC single equal branch plain door, bolts and 1 330
nuts etc.
Each
Rubber gaskit / Adhasive L.S.
CARRIAGE:
Carriage of material L.S.
LABOUR:
Fixing charges L.S.
TOTAL :
Add 1 % Water charges on "W"
TOTAL
Add GST (multiplying factor 0.1405) on "X"
TOTAL
Add 15 % Contractor's profit and overheads on "Y"
TOTAL
Add Cess @ 1% on "Z"
Cost of 1 No.
Cost of 1 No.

ii) 110 mm dia.


Detail of cost for one bend.
MATERIALS:
10017 110 mm dia PVC door bend bolts and nuts etc. Each 1 200
Rubber gaskit / Adhasive L.S.
CARRIAGE:
Carriage of material L.S.
LABOUR:
Fixing charges L.S.
TOTAL :
Add 1 % Water charges on "W"
TOTAL
Add GST (multiplying factor 0.1405) on "X"
TOTAL
Add 15 % Contractor's profit and overheads on "Y"
TOTAL
Add Cess @ 1% on "Z"
Cost of 1 No.
Cost of 1 No.

iv) 75 mm dia.
Detail of cost for one bend.
MATERIALS:
10018 75 mm dia PVC door bend , bolts and nuts etc. Each 1 180
Rubber gaskit / Adhasive L.S.
CARRIAGE:
Carriage of material L.S.
LABOUR:
Fixing charges L.S.
TOTAL :
Add 1 % Water charges on "W"
TOTAL
Add GST (multiplying factor 0.1405) on "X"
TOTAL
Add 15 % Contractor's profit and overheads on "Y"
TOTAL
Add Cess @ 1% on "Z"
Cost of 1 No.
Cost of 1 No.

3.123 Providing and fixing PVC double equal branch with oval
access door, insertion rubber washer 3 mm thick bolts and
nuts complete including fixing with approved adhesive etc.
complete.

i) 150 mm dia.
Detail of cost for one branch.
MATERIALS:
10019 150 mm dia PVC double equal branch with oval access 1 350
door, bolts and nuts etc.
Each
Rubber gaskit / Adhasive L.S.
CARRIAGE:
Carriage of material L.S.
LABOUR:
Fixing charges L.S.
TOTAL :
Add 1 % Water charges on "W"
TOTAL
Add GST (multiplying factor 0.1405) on "X"
TOTAL
Add 15 % Contractor's profit and overheads on "Y"
TOTAL
Add Cess @ 1% on "Z"
Cost of 1 No.
Cost of 1 No.

ii) 110 mm dia.


Detail of cost for one bend.
MATERIALS:
10020 110 mm dia PVC double equal branch bolts and nuts etc. Each 1 250

Rubber gaskit / Adhasive L.S.


CARRIAGE:
Carriage of material L.S.
LABOUR:
Fixing charges L.S.
TOTAL :
Add 1 % Water charges on "W"
TOTAL
Add GST (multiplying factor 0.1405) on "X"
TOTAL
Add 15 % Contractor's profit and overheads on "Y"
TOTAL
Add Cess @ 1% on "Z"
Cost of 1 No.
Cost of 1 No.

iv) 75 mm dia.
Detail of cost for one bend.
MATERIALS:
10021 75 mm dia PVC double equal branch , bolts and nuts etc. Each 1 180

Rubber gaskit / Adhasive L.S.


CARRIAGE:
Carriage of material L.S.
LABOUR:
Fixing charges L.S.
TOTAL :
Add 1 % Water charges on "W"
TOTAL
Add GST (multiplying factor 0.1405) on "X"
TOTAL
Add 15 % Contractor's profit and overheads on "Y"
TOTAL
Add Cess @ 1% on "Z"
Cost of 1 No.
Cost of 1 No.

3.12 Providing and fixing PVC collers including fixing with


approved adhesive etc. complete.
i) 150 mm dia.
Detail of cost for. one PVC collers
MATERIALS:
10022 150 mm dia PVC collers, bolts and nuts etc. Each 1 200
Rubber gaskit / Adhasive L.S.
CARRIAGE:
Carriage of material L.S.
LABOUR:
Fixing charges L.S.
TOTAL :
Add 1 % Water charges on "W"
TOTAL
Add GST (multiplying factor 0.1405) on "X"
TOTAL
Add 15 % Contractor's profit and overheads on "Y"
TOTAL
Add Cess @ 1% on "Z"
Cost of 1 No.
Cost of 1 No.

ii) 110 mm dia.


Detail of cost for one PVC collers
MATERIALS:
10023 110 mm dia PVC collers bolts and nuts etc. Each 1 170
Rubber gaskit / Adhasive L.S.
CARRIAGE:
Carriage of material L.S.
LABOUR:
Fixing charges L.S.
TOTAL :
Add 1 % Water charges on "W"
TOTAL
Add GST (multiplying factor 0.1405) on "X"
TOTAL
Add 15 % Contractor's profit and overheads on "Y"
TOTAL
Add Cess @ 1% on "Z"
Cost of 1 No.
Cost of 1 No.

iv) 75 mm dia.
Detail of cost for one PVC collers
MATERIALS:
10024 75 mm dia PVC collers , bolts and nuts etc. Each 1 140
Rubber gaskit / Adhasive L.S.
CARRIAGE:
Carriage of material L.S.
LABOUR:
Fixing charges L.S.
TOTAL :
Add 1 % Water charges on "W"
TOTAL
Add GST (multiplying factor 0.1405) on "X"
TOTAL
Add 15 % Contractor's profit and overheads on "Y"
TOTAL
Add Cess @ 1% on "Z"
Cost of 1 No.
Cost of 1 No.

3.115 Providing and fixing PVC floor trap of self cleaning design
including fixing with approved adhesive, cost of cutting and
making good the wall and floors etc. complete.

i) 110 mm X 75 mm.
Detail of cost for one floor trap
MATERIALS:
10025 110 mm X 75 mm PVC floor trap of self cleaning design Each 1 250

Rubber gaskit / Adhasive L.S.


CARRIAGE:
Carriage of PVC trap. L.S.
LABOUR:
Mason Ist Class Each 0.6 505.17
Beldar Each 0.6 350
TOTAL :
Add 1 % Water charges on "W"
TOTAL
Add GST (multiplying factor 0.1405) on "X"
TOTAL
Add 15 % Contractor's profit and overheads on "Y"
TOTAL
Add Cess @ 1% on "Z"
Cost of 1 No.
Cost of 1 No.
42000.00

3392.50
0.00
0.00
1080.00
0.00
0.00
5145.00
0.00
0.00
2499.00
0.00
0.00
576.00
360.00
288.00
792.00
0.00
375.90
178.56
0.00
14144.76
8050.00
78881.72 W
788.8172
79670.54 X
11193.71
90864.25 Y
13629.64
104493.89 Z
1044.94
105538.83
1055.39
1055.40

6961.50
1180.00
341.77
10.09
0.00
252.59
175.00
70.00
2.00
8992.95 W
89.9295
9082.88 X
1276.14
10359.02 Y
1553.85
11912.87 Z
119.13
12032.00
1851.08
1851.10
4900.00

98
19.6
5017.60 W
50.176
5067.78 X
712.02
5779.80 Y
866.97
6646.77 Z
66.47
6713.24
6713.24
6713.20
300.00

10.80
2.16
312.96 W
3.1296
316.09 X
44.41
360.50 Y
54.07
414.57 Z
4.15
418.72
418.72
418.70

350
0
20
370 W
3.70
373.7 x
52.5
426.2 y
63.93
490.13
4.9
495.03
495.00 only

870

17.4
3.48
890.88 W
8.91
899.79 x
126.42
1026.21 y
153.93
1180.14
11.8
1191.94
1191.90 only
3600

50
3650 W
36.50
3686.5 x
517.95
4204.45 y
630.67
4835.12
48.35
4883.47
976.70 only
3975
90
4065 W
40.65
4105.65 x
576.84
4682.49 y
702.37
5384.86
53.85
5438.71
1087.70 only
525

57.8
50.8

14.4
505.2
350
33.8
7.9
1544.9 W
15.45
1560.35 x
219.23
1779.58 y
266.94
2046.52
20.47
2066.99
2067.00 only
9900
495
15

20

171.8
59.5
234.5
60
10955.8 W
109.56
11065.36 x
1554.68
12620.04 y
1893.01
14513.05
145.13
14658.18
488.60 only

7500
375
15

20

171.8
59.5
234.5
60
8435.8 W
84.36
8520.16 x
1197.08
9717.24 y
1457.59
11174.83
111.75
11286.58
376.20 only

6600
330
10

15

171.8
59.5
234.5
50
7470.8 W
74.71
7545.51 x
1060.14
8605.65 y
1290.85
9896.5
98.97
9995.47
333.20 only

350.00
10.00

5.00
20.00
385 W
3.85
388.85 x
54.63
443.48 y
66.52
510
5.1
515.1
515.10 only

275.00
7.00

4.00

15.00
301 W
3.01
304.01 x
42.71
346.72 y
52.01
398.73
3.99
402.72
402.70 only

225.00
6.00

4.00

12.00
247 W
2.47
249.47 x
35.05
284.52 y
42.68
327.2
3.27
330.47
330.50 only

350.00
10.00

5.00

20.00
385 W
3.85
388.85 x
54.63
443.48 y
66.52
510
5.1
515.1
515.10 only

275.00
7.00

4.00
15.00
301 W
3.01
304.01 x
42.71
346.72 y
52.01
398.73
3.99
402.72
402.70 only

225.00
6.00

4.00

12.00
247 W
2.47
249.47 x
35.05
284.52 y
42.68
327.2
3.27
330.47
330.50 only

330.00
10.00
5.00

20.00
365 W
3.65
368.65 x
51.8
420.45 y
63.07
483.52
4.84
488.36
488.40 only

200.00
7.00

4.00

15.00
226 W
2.26
228.26 x
32.07
260.33 y
39.05
299.38
2.99
302.37
302.40 only

180.00
6.00

4.00

12.00
202 W
2.02
204.02 x
28.66
232.68 y
34.9
267.58
2.68
270.26
270.30 only

350.00
10.00

5.00

20.00
385 W
3.85
388.85 x
54.63
443.48 y
66.52
510
5.1
515.1
515.10 only

250.00
7.00

4.00

15.00
276 W
2.76
278.76 x
39.17
317.93 y
47.69
365.62
3.66
369.28
369.30 only

180.00
6.00

4.00

12.00
202 W
2.02
204.02 x
28.66
232.68 y
34.9
267.58
2.68
270.26
270.30 only

200.00
10.00

5.00

20.00
235 W
2.35
237.35 x
33.35
270.7 y
40.61
311.31
3.11
314.42
314.40 only

170.00
7.00

4.00

15.00
196 W
1.96
197.96 x
27.81
225.77 y
33.87
259.64
2.6
262.24
262.20 only

140.00
6.00

4.00

12.00
162 W
1.62
163.62 x
22.99
186.61 y
27.99
214.6
2.15
216.75
216.80 only

250.00
6.00

4.00

303.10
210.00
773.102 W
7.73
780.832 x
109.71
890.542 y
133.58
1024.122
10.24
1034.362
1034.40 only
-3
SUB HEAD : 16.0
-2
-1
ROAD WORK
0
1 Code Description Unit Quantity Rate
2 16.1 Preparation and consolidation of sub
4 grade of
Details with
costpower road
for 100sqm. roller of 8 to 12
5 (A) preparation of subgrade.
6 Earth work in excavation including dressing
7 etc. 100sqm.x22.5cm (average depth) =
8 22.5cum.
9 LABOUR
10 28 Mate day 1.8 350.00
11 18 Coolie day 18 350.00
12 17 Beldar day 0.27 350.00
13 3 Hire charges of Diesel Road Roller - 8 to 10 day 0.054 3000
14 16 Chowkidar day 0.054 350.00
15 9999 Sundries L.S. 6.76 2
16 (B) Conslidation of subgrade
17 Roller charges (one roller does 1860 sqm. of
18 conosolidation of sub - grade with road roller of
19 8 to 12 tonne capacity including making good
20 the undulations etc. with earth or quarry spoils
21 3 etc. and rerolling the subgrade 3000

22 Hire charges of Diesel Road Roller - 8 to 10 day 0.054 3000


23 16 tonne
24 Chowkidar day 0.054 350.00
25 9999 Sundries L.S. 6.76 2
26 TOTAL
27 Add 1 % Water charges on "W"
28 TOTAL
29 Add GST (multiplying factor 0.1405) on "X"
30 TOTAL
31 Add 15 % Contractor's profit and overheads on "Y"
32 Total
33 Add Cess @ 1% on "Z"
34 Cost for 100 sqm.
35 Cost per sqm.
36 Say
37
38
39
40 16.2 Extra for compaction of earth work in
47 embankment
LABOUR under optimum moisture
48 (Extra to item No.2.3 in Earth work)
49 11 Bhisti day 0.17 350.00
50 Roller charges (one roller does 1860sqm. of
51 consolidation per day of 8 hours and uses 18
52 3 litres diesel) 3000
53 Hire charges of Diesel Road Roller - 8 to 10 day 0.008 3000
54 16 tonne
55 Chowkidar day 0.008 350.00
56 9999 Sundries L.S. 1.43 2
57 TOTAL
58 Add 1 % Water charges on "W"
59 TOTAL
60 Add GST (multiplying factor 0.1405) on "X"
61 TOTAL
62 Add 15 % Contractor's profit and overheads on "Y"
63 Total
64 Add Cess @ 1% on "Z"
65 Cost of 10 cum.
66 Cost per cum.
67 Say
68
69
70 16.3 Supplying and stacking at site.
71 16.3.1 90 mm to 45 mm size stone aggregate
72 Details of cost for 1 cum.
73 MATERIAL
74 2901 Stone Aggregate (Single size) : 100 mm cum 0.1 1350
75 2902 nominal size cum 0.65 1350
76 Stone Aggregate (Single size) : 80 mm nominal
77 291 size cum 0.25 700
78 Stone Aggregate (Single size) : 63 mm nominal
79 2206 size
80 Carriage of Stone aggregate 40 mm nominal cum 1 115.36
81 size and above
82 Total
83 Add 1 % Water charges on "W"
84 TOTAL
85 Add GST (multiplying factor 0.1405) on "X"
86 TOTAL
87 Add 15 % Contractor's profit and overheads on "Y"
88 Total
89 Add Cess @ 1% on "Z"
90 Cost for 1 cum
91 Say
92
93
99
100 16.3.2 63 mm to 45 mm size stone aggregate
101 Details of cost for 1 cum.
102 MATERIAL
103 2902 Stone Aggregate (Single size) : 80 mm nominal cum 0.1 1350
104 291 size cum 0.65 700
105 Stone Aggregate (Single size) : 63 mm nominal
106 292 size cum 0.25 730
107 Stone Aggregate (Single size) : 50 mm nominal
108 2206 size
109 Carriage of Stone aggregate 40 mm nominal cum 1 115.36
110 size and above
111 Total
112 Add 1 % Water charges on "W"
113 TOTAL
114 Add GST (multiplying factor 0.1405) on "X"
115 TOTAL
116 Add 15 % Contractor's profit and overheads on "Y"
117 Total
118 Add Cess @ 1% on "Z"
119 Cost for 1 cum
120 Say

121 16.3.3 53 mm to 22.4 mm size stone aggregate


122 Details of cost for 1 cum.
123 MATERIAL
124 291 Stone Aggregate (Single size) : 63 mm nominal cum 0.05 700
125 292 size cum 0.3 730
126 Stone Aggregate (Single size) : 50 mm nominal
127 293 size cum 0.65 730
128 Stone Aggregate (Single size) : 40 mm nominal
129 2206 size
130 Carriage of Stone aggregate 40 mm nominal cum 1 115.36
131 size and above
132 Total
133 Add 1 % Water charges on "W"
134 TOTAL
135 Add GST (multiplying factor 0.1405) on "X"
136 TOTAL
137 Add 15 % Contractor's profit and overheads on "Y"
138 Total
139 Add Cess @ 1% on "Z"
140 Cost for 1 cum
141 Say
142
143
151
152 16.3.4 Over burnt (Jhama) brick aggregate 120
153 mm toof40cost
Details mm for 1 cum.
154 MATERIAL
155 2908 Over burnt (Jhama) Brick Aggregate: 120 mm cum 1 500
156 2260 to 40 mm size
157 Carriage of Brick aggregate cum 1 115.36
158 Total
159 Add 1 % Water charges on "W"
160 TOTAL
161 Add GST (multiplying factor 0.1405) on "X"
162 TOTAL
163 Add 15 % Contractor's profit and overheads on "Y"
164 Total
165 Add Cess @ 1% on "Z"
166 Cost for 1 cum
167 Say

168 16.3.5 Over burnt (Jhama) brick aggregate 90 mm


169 to 45 mm
Details of cost for 1 cum.
170 MATERIAL
171 2909 Over burnt (Jhama) Brick Aggregate: 90 mm to cum 1 480
172 2260 40 mm size
173 Carriage of Brick aggregate cum 1 115.36
174 Total
175 Add 1 % Water charges on "W"
176 TOTAL
177 Add GST (multiplying factor 0.1405) on "X"
178 TOTAL
179 Add 15 % Contractor's profit and overheads on "Y"
180 Total
181 Add Cess @ 1% on "Z"
182 Cost for 1 cum
183 Say
184
185
192
193 16.3.6 Stone screening 13.2 mm nominal size
194 (Type of
Details A)cost for 1 cum.
195 MATERIAL
196 2910 Stone chippings/ screenings 12.5/ 13.2 mm cum 0.05 1150
197 2911 nominal size 1150
198 Stone chippings/ screenings 10/ 11.2 mm cum 0.8 1150
199 2903 nominal size
200 Stone chippings/ screenings 4.75 mm nominal cum 0.15 1400
201 2202 size
202 Carriage of Stone aggregate below 40 mm cum 1 106.13
203 nominal size
204 TOTAL
205 Add 1 % Water charges on "W"
206 TOTAL
207 Add GST (multiplying factor 0.1405) on "X"
208 TOTAL
209 Add 15 % Contractor's profit and overheads on "Y"
210 Total
211 Add Cess @ 1% on "Z"
212 Cost for 1 cum
213 Say

214 16.3.7 Stone screening 11.2 mm nominal size


215 (Type of
Details B)cost for 1 cum.
216 MATERIAL
217 2911 Stone chippings/ screenings 10/ 11.2 mm cum 0.1 1150
218 2903 nominal size
219 Stone chippings/ screenings 4.75 mm nominal cum 0.75 1400
220 2904 size 1400
221 Stone chippings/ screenings 150 micron cum 0.15 1400
222 2202 nominal size
223 Carriage of Stone aggregate below 40 mm cum 0.85 106.13
224 2267 nominal size 106.13
225 Carriage of Stone dust cum 0.15 106.13
226 TOTAL
227 Add 1 % Water charges on "W"
228 TOTAL
229 Add GST (multiplying factor 0.1405) on "X"
230 TOTAL
231 Add 15 % Contractor's profit and overheads on "Y"
232 Total
233 Add Cess @ 1% on "Z"
234 Cost for 1 cum
235 Say
236
237
244
245 16.3.8 bajri
246 Details of cost for 1 cum.
247 MATERIAL
248 304 Bajri cum 1 1000
249 2311 Carriage of bajri cum 1 106.13
250 TOTAL
251 Add 1 % Water charges on "W"
252 TOTAL
253 Add GST (multiplying factor 0.1405) on "X"
254 TOTAL
255 Add 15 % Contractor's profit and overheads on "Y"
256 Total
257 Add Cess @ 1% on "Z"
258 Cost for 1 cum
259 Say

260 16.3.9 Good earth


261 Details of cost for 1 cum.
262 Excavation :
263 LABOUR
264 17 Beldar day 0.177 350.00
265 18 Coolie day 0.167 350.00
266 979 Royalty for good earth cum 1 40
267 2241 Carriage of Good earth by mechanical cum 1 132.66
268 transport upto 5 km lead
269 TOTAL
270 Add 1 % Water charges on "W"
271 TOTAL
272 Add GST (multiplying factor 0.1405) on "X"
273 TOTAL
274 Add 15 % Contractor's profit and overheads on "Y"
275 Total
276 Add Cess @ 1% on "Z"
277 Cost for 1 cum
278 Say
279

287
288 16.3.10 Moorum
289 Details of cost for 1 cum.
290 MATERIAL
291 810 Moorum cum 1 500
292 2265 Carriage of Moorum cum 1 106.13
293 TOTAL
294 Add 1 % Water charges on "W"
295 TOTAL
296 Add GST (multiplying factor 0.1405) on "X"
297 TOTAL
298 Add 15 % Contractor's profit and overheads on "Y"
299 Total
300 Add Cess @ 1% on "Z"
301 Cost for 1 cum
302 Say
303

304 16.4 Laying, spreading and compacting stone


305 aggregate of specified sizes to WBM
306 LABOUR
307 17 Beldar day 0.26 350.00
308 18 Coolie day 0.26 350.00
309 11 Bhisti day 0.26 350.00
310 Roller charges (one roller does 30 cum
311 consolidation per day of 8 hours and uses 18
312 3 litres of diesel oil). 3000
313 Hire charges of Diesel Road Roller - 8 to 10 day 0.033 3000
314 16 tonne
315 Chowkidar day 0.033 350.00
316 9999 Sundries L.S. 2.73 2
317 TOTAL
318 Add 1 % Water charges on "W"
319 TOTAL
320 Add GST (multiplying factor 0.1405) on "X"
321 TOTAL
322 Add 15 % Contractor's profit and overheads on "Y"
323 Total
324 Add Cess @ 1% on "Z"
326 Cost for 1 cum
327 Say
328
335
336 16.5 Laying water bound macadam sub-
337 base with brick aggregate and binding
338 16.5.1 Over burnt (Jhama) brick aggregate 120
339 mm toof40cost
Details mm for 1 cum.
340 LABOUR
341 17 Beldar day 0.35 350.00
342 18 Coolie day 0.26 350.00
343 11 Bhisti Day 0.18 350.00
344 Roller charges (one roller does 230cum.
345 consolidation per day of 8 hours and uses 18
346 3 litres of diesel oil) 3000
347 Hire charges of Diesel Road Roller - 8 to 10 day 0.004 3000
348 16 tonne
349 Chowkidar day 0.004 350.00
350 9999 Sundries L.S. 2.73 2
351 TOTAL
352 Add 1 % Water charges on "W"
353 TOTAL
354 Add GST (multiplying factor 0.1405) on "X"
355 TOTAL
356 Add 15 % Contractor's profit and overheads on "Y"
357 Total
358 Add Cess @ 1% on "Z"
359 Cost for 1 cum
360 Say
361
362
368
369 16.5.2 Over burnt (Jhama) brick aggregate 90 mm
370 to 45 mm
Details of cost for 1 cum.
372 LABOUR
373 17 Beldar day 0.35 350.00
374 18 Coolie day 0.26 350.00
375 11 Bhisti day 0.18 350.00
376 Roller charges (one roller does 230cum.
377 consolidation per day of 8 hours and uses 18
378 3 litres of diesel oil) 3000
379 Hire charges of Diesel Road Roller - 8 to 10 day 0.004 3000
380 16 tonne
381 Chowkidar day 0.004 350.00
382 9999 Sundries L.S. 2.73 2
383 TOTAL
384 Add 1 % Water charges on "W"
385 TOTAL
386 Add GST (multiplying factor 0.1405) on "X"
387 TOTAL
388 Add 15 % Contractor's profit and overheads on "Y"
389 Total
390 Add Cess @ 1% on "Z"
391 Cost for 1 cum
392 Say
393
394
395 16.6 Supplying, stacking and Spreading 6 mm
396 16.6.1 thick road
With bajri,roller/
watering and
hand rolling complete
roller
397 Details of cost for 6 mm thick and 100 sqm
398 area = 0.60 cum.
399 (A) Supplying and stacking of bajri at site.
400 MATERIAL
401 304 Bajri cum 0.6 1000
402 2311 Carriage of bajri cum 0.6 106.13
403 (B) Spreading of bajri
404 LABOUR
405 17 Beldar day 0.54 350.00
406 11 Bhisti day 0.54 350.00
407 Roller charges (one roller does 1860sqm.
408 consolidation per day of 8 hours and uses 18
409 3 litres of diesel oil) 3000
410 Hire charges of Diesel Road Roller - 8 to 10 day 0.054 3000
411 16 tonne
412 Chowkidar day 0.054 350.00
413 TOTAL
414 Add 1 % Water charges on "W"
415 TOTAL
416 Add GST (multiplying factor 0.1405) on "X"
417 TOTAL
418 Add 15 % Contractor's profit and overheads on "Y"
419 Total
420 Add Cess @ 1% on "Z"
421 Cost for 100 sqm.
422 Cost per sqm.
423 Say

431
432 16.7 Brick edging in full brick width and
433 half brick depth including excavation,
434 16.7.1 With common burnt clay F.P.S. (non
435 modular)
Details bricks
of cost of class
designation 7.5
for 10m.
436 MATERIAL
437 2602 Common burnt clay F.P.S. (non modular) 1000 0.16 5000
438 bricks class designation 7.5 including 12% Nos
439
440 2201 wastage
441 Carriage of Bricks 1000 0.16 283.01
442 LABOUR Nos
443
444 23 Mason (brick layer) 1st class day 0.17 505.17
445 24 Mason (brick layer) 2nd class day 0.17 403.67
446 18 Coolie day 0.35 350.00
447 9999 Removal of rubbish L.S. 17.94 2
448 9999 Sundries L.S. 8.97 2
449 TOTAL
450 Add 1 % Water charges on "W"
451 TOTAL
452 Add GST (multiplying factor 0.1405) on "X"
453 TOTAL
454 Add 15 % Contractor's profit and overheads on "Y"
455 Total
456 Add Cess @ 1% on "Z"
457 Cost for 10m.
458 Cost per m.
459 Say
460
461 16.8 Brick edging laid lengthwise with half
462 brick depth including excavation, refilling
463
464
465
466
467 1147
468
469
471 16.8.1 With common burnt clay F.P.S. (non
472 modular)
Details bricks
of cost of class
designation 7.5
for 10m.
473 MATERIAL
474 2602 Common burnt clay F.P.S. (non modular) 1000 0.049 5000
475 bricks class designation 7.5 including 12% Nos
476
477 2201 wastage
478 Carriage of Bricks 1000 0.049 283.01
479 LABOUR Nos
480
481 23 Mason (brick layer) 1st class day 0.04 505.17
482 24 Mason (brick layer) 2nd class day 0.04 403.67
483 18 Coolie day 0.09 350.00
484 9999 Removal of rubbish L.S. 4.16 2
485 TOTAL
486 Add 1 % Water charges on "W"
487 TOTAL
488 Add GST (multiplying factor 0.1405) on "X"
489 TOTAL
490 Add 15 % Contractor's profit and overheads on "Y"
491 Total
492 Add Cess @ 1% on "Z"
493 Cost for 10m.
494 Cost per m.
495 Say
496
497 16.9 Scarifying metalled (water-bound)
498 road surface including disposal of rubbish,
499 with power road roller of 8 to 10 tonne
500 capacity.
501 Details of cost for 100sqm.
502
503 LABOUR
504 17 Beldar day 1.35 350.00
505 18 Coolie day 1.08 350.00
506 Consolidation of scarified material
507 100sqm.x50mm = 5cum + Less 20% wastage
508 = 1 cum.
509 = 4 cum.
510 003 Hire charges of Diesel Road Roller - 8 to 10 day 0.132 3000
511 16 tonne
512 Chowkidar day 0.132 350.00
513 9999 Sundries L.S. 5.46 2
514
515
516
517
518 1148
519
520
522 TOTAL
523 Add 1 % Water charges on "W" 12.29
524 TOTAL
525 Add GST (multiplying factor 0.1405) on "X" 174.39
526 TOTAL
527 Add 15 % Contractor's profit and overheads on "Y" 212.33
528 Total
529 Add Cess @ 1% on "Z" 16.28
530 Cost for 100 sqm. 1644.17
531 Cost per sqm. 16.44
532 Say 16.45
533
534
535 16.10 Making bajri path including
536 preparation of subgrade, supplying and
537 Details of cost for 100sqm.
538 Earth work in excavation including dressing
539 etc.
540 100x0.075=7.5cum.
541 2.6.1 (Rate as per item no.2.6.1 of S.H. Earth work) cum 7.5 131.05
542 Collection and stacking of brick aggregate
543 286 53mm nominal size 100x0.075 =7.50cum.
544 Brick Aggregate (Single size) : 50 mm nominal cum 7.5 650
545 2260 size
546 Carriage of Brick aggregate cum 7.5 115.35876
547 Supply staking bajri
548 100x0.012= 1.2 cum
549 16.3.8 Rate as per Item Number 16.3.8 of cum 1.2 1479.95
550 SH: Road Work
551 Collection and stacking of moorum at site
552 16.3.10 100x0.012 = 1.20cum.
553 Rate as per Item Number 16.3.10 of cum 1.2 810.95
554 SH: Road Work
555 Spreading and consolidation of brick aggregate
556 and blinding material etc.
557 LABOUR
558 17 Beldar day 1.95 350.00
559 18 Coolie day 2.63 350.00
560 11 Bhisti day 1.35 350.00
561 3 Hire charges of Diesel Road Roller - 8 to 10 day 0.135 3000
562 16 tonne
563 Chowkidar day 0.135 350.00
564 9999 Sundries L.S. 20.15 2
565
566
567
568 1149
569
570
572 Spreading of bajri, watering and rolling
573 3 Hire charges of Diesel Road Roller - 8 to 10 day 0.054 3000
574 16 tonne
575 Chowkidar day 0.054 350.00
576 TOTAL
577 Add 1 % Water charges on "W-A" 8310.65
578 TOTAL
579 Add GST (multiplying factor 0.1405) on "X-A" 8393.76
580 TOTAL
581 Add 15 % Contractor's profit and overheads on 9573.08
582 "Y-A"
583 Total
584 Add Cess @ 1% on "Z-A" 11009.04
585 Cost for 100 sqm.
586 Cost per sqm.
587 Say
588
589
590 16.11 Dry stone pitching 22.5 cm thick
591 including supply of stones and preparing
592 Details of cost for 10 sqm.
593 MATERIAL
594 1158 Stone for pitching 15 cm x 22.5 cm cum 2.25 600
595 2216 Carriage of Stone blocks white & red sand tonne 5.05 94.34
596 stone & kota stone slab 2.25x2245/1000 = 5.05
597 t
598 LABOUR
599 23 Mason (brick layer) 1st class day 1.08 505.17
600 24 Mason (brick layer) 2nd class day 1.08 403.67
601 17 Beldar day 2.15 350.00
602 18 Coolie day 1.61 350.00
603 9999 Sundries L.S. 6.76 2
604 TOTAL
605 Add 1 % Water charges on "W"
606 TOTAL
607 Add GST (multiplying factor 0.1405) on "X"
608 TOTAL
609 Add 15 % Contractor's profit and overheads on "Y"
610 Total
611 Add Cess @ 1% on "Z"
612
613
614
615
616
617 1150
618
619
621 Cost for 10 sqm.
622 Cost per sqm.
623 Say
624
625 16.12 Dry brick pitching half brick thick in
626 drains including supply of bricks and
627 16.12.1 With common burnt clay F.P.S. (non
628 modular) bricks of class designation 7.5
629 Details of cost for 10 sqm.
630 MATERIAL
631 2602 Common burnt clay F.P.S. (non modular) 1000 0.645 5000
632 bricks class designation 7.5 Nos
633 2201 Carriage of Bricks 1000 0.645 283.01
634 LABOUR Nos
635
636 23 Mason (brick layer) 1st class day 0.4 505.17
637 24 Mason (brick layer) 2nd class day 0.4 403.67
638 17 Beldar day 1.08 350.00
639 TOTAL
640 Add 1 % Water charges on "W"
641 TOTAL
642 Add GST (multiplying factor 0.1405) on "X"
643 TOTAL
644 Add 15 % Contractor's profit and overheads on "Y"
645 Total
646 Add Cess @ 1% on "Z"
647 Cost for 10 sqm.
648 Cost per sqm.
649 Say
650
651 16.13 Cutting road and making good the
652 same including supply of extra quantities
653 16.13.1 bituminous portion
654 Details of cost for 1.08cum. (road 6 metres
655 wide, 0.6 metre length wise and 0.30m
656 (average depth) volume = 1.08 cum).
657 MATERIAL
658 Supplying and stacking stone aggregate 53mm
659 16.3.3 to 24 mm nominal size at site.
660 Rate as per Item Number 16.3.3 of cum 0.09 1753.2
661 SH: Road Work
662 Supplying and stacking bajri at site
663 16.3.8 Rate as per Item Number 16.3.8 of cum 0.023 1479.95
664 SH: Road Work
665
666
667
668 1151
669
670
672 Supplying and stacking moorum at site
673 16.3.10 Rate as per Item Number 16.3.10 of SH: Road cum 0.022 810.95
674 2911 Work 1150
675 Stone chippings/ screenings 10/ 11.2 mm cum 0.092 1150
676 2202 nominal size
677 Carriage of Stone aggregate below 40 mm cum 0.092 106.13
678 309 nominal size 48000
679 Paving bitumen VG-10 of approved quality tonne 0.011 25614
680 2211 Carriage of Tar bitumen tonne 0.011 106.13
681 LABOUR
682 For cutting road and taking out soling and
683 17 metalling including sorting and screening.
684 Beldar day 0.96 350.00
685 18 Coolie day 0.48 350.00
686 Relaying soling stone 3.6x0.15=0.54cum.
687 17 Beldar day 0.24 350.00
688 18 Coolie day 0.24 350.00
689 Relaying road metal with extra quantity and
690 consolidation to 0.10m, thickness
691 17 3.6x0.10=0.36cum.
692 Beldar day 0.71 350.00
693 18 Coolie day 0.48 350.00
694 11 Bhisti day 0.1 350.00
695 Painting two coats, 3.6sqm. including labour
696 17 for spreading grit
697 Beldar day 0.48 350.00
698 18 Coolie day 0.48 350.00
699 9999 Barrier, chowkidar, sprayman, mate, etc. L.S. 40.43 2
700 TOTAL
701 Add 1 % Water charges on "W-A" 1817.21
702 TOTAL
703 Add GST (multiplying factor 0.1405) on "X-A" 1835.38
704 TOTAL
705 Add 15 % Contractor's profit and overheads on 2093.25
706 "Y-A"
707 Total
708 Add Cess @ 1% on "Z-A" 2407.24
709 Cost for 1.08 cum.
710 Cost per cum.
711 Say
712 16.13.2 Water bound macadam
713 Details of cost for 0.90cum.
714
715 Consider a road 6 metres wide and 0.6m. lengthwise
and 0.25m cm average depth =0.90cum.
716
717
718
719
720 1152
721
722
724 MATERIAL
725 Supplying and stacking stone aggregate 53mm
726 16.3.3 to 24mm nominal size at site.
727 Rate as per Item Number 16.3.3 of cum 0.09 1753.2
728 SH: Road Work
729 Supplying and stacking bajri at site
730 16.3.8 Rate as per Item Number 16.3.8 of cum 0.023 1479.95
731 SH: Road Work
732 Supplying and stacking moorum at site.
733 16.3.10 Rate as per Item Number 16.3.10 of cum 0.022 810.95
734 SH: Road Work LABOUR
735 For cutting road and taking out soling and
736 17 metalling including sorting and screening.
737 Beldar day 0.48 350.00
738 18 Coolie day 0.24 350.00
739 For relaying soling stone 3.6x0.15=0.54cum.
740 17 Beldar day 0.24 350.00
741 18 Coolie day 0.24 350.00
742 For relaying road metal with extra quantity and
743 consolidation to 0.10m thickness -
744 17 3.6x0.10=0.36cum.
745 Beldar day 0.48 350.00
746 18 Coolie day 0.48 350.00
747 11 Bhisti day 0.1 350.00
748 9999 Barrier and chowkidar etc. L.S. 53.82 2
749 TOTAL
750 Add 1 % Water charges on "W-A" 832.72
751 TOTAL
752 Add GST (multiplying factor 0.1405) on "X-A" 841.04
753 TOTAL
754 Add 15 % Contractor's profit and overheads on 959.21
755 "Y-A"
756 Total
757 Add Cess @ 1% on "Z-A" 1103.09
758 Cost for 0.90 cum.
759 Cost per cum.
760 Say
761
762 16.14 Cutting bajri paths and making good
763 the same including supply of extra
764 quantities of brick aggregate, moorum and
765 bajri required.
766 Details of cost for 10 sqm.
767
768 10x0.075=0.75cum.
769
770 MATERIAL
771
772
773
774
775
776 1153
777
778
780 Supplying and stacking 50mm brick aggregate
781 286 at site(extra quantity)
782 Brick Aggregate (Single size) : 50 mm nominal cum 0.19 650
783 2260 size
784 Carriage of Brick aggregate cum 0.19 115.36
785 Supplying and stacking bajri at site
786 16.3.8 Rate as per Item Number 16.3.8 of cum 0.06 1479.95
787 SH: Road
788 Supplying and stacking moorum at site
789 16.3.10 Rate as per Item Number 16.3.10 of cum 0.06 810.95
790 SH: Road
791 LABOUR
792 For cutting, sorting out, spreading and
793 17 consolidation of aggregate
794 Beldar day 1.6 350.00
795 18 Coolie day 0.8 350.00
796 TOTAL
797 Add 1 % Water charges on "W-A" 915.41
798 TOTAL
799 Add GST (multiplying factor 0.1405) on "X-A" 924.56
800 TOTAL
801 Add 15 % Contractor's profit and overheads on 1054.47
802 "Y-A"
803 Total
804 Add Cess @ 1% on "Z-A" 1212.64
805 Cost for 10 sqm.
806 Cost per sqm.
807 Say
808
809 16.15 Supplying at site :
810
811 16.15.1 R.C.C. Standards post/ struts/rails/
812 pales of mix 1:1.5:3 (1 cement : 1.5 coarse
813 separately).
814
815 Details of cost for 10 posts = 0.336cum Cubical contents of
one post
816
817 Area bottom A1 = (15+12.5)/2 x8.75+½x 3.14 x(6.25)²
=120.31+61.38=181.69sqcm.
818
819 Area bottom A2 = (10+7.5)/2 x6.25+½x 3.14 x(3.75)²
sqm
820 = 54.68+22.08 = 76.76 sqcm. (A1A2)^½ = 118.10sqcm
821
822
823
824 1154
825
826
828 A1+A2+(A1A2))^½ = 0.03766 sqm
829 Volume = (1.05)/3x0.03766 = 0.01316 cum
830 =0.0132cum.
831 Volume of lower and square portion
832 (16.5x16.5x75) / 100³ = 0.0204cum. Total
833 volume = 0.0132+0.0204 cum = 0.0336 cum.
834 Qty. for 10 post
835 = 0.0336x10 = 0.336cum.
836 Cement concrete 1:1.5:3 (1 Cement : 1.5
837 Coarse sand : 3 graded stone aggregate
838 12.5mm nominal size)
839 4.1.2 Rate as per item no 4.1.2 of S.H. Concrete cum 0.336 6376.3
840 Work.
841 Extra labour for laying cement concrete in RCC
842 17 work
843 Beldar day 0.034 350.00
844 11 Bhisti day 0.067 350.00
845 23 Mason (brick layer) 1st class day 0.013 505.17
846 24 Mason (brick layer) 2nd class day 0.013 403.67
847 28 Mate day 0.013 350.00
848 M.S. Reinforcement 6mm dia. bars
849 10x4x1.88m = 75.20m+
850 10x9x0.50m =45.00m =
851 120.20m
852 120.20m@0.22kg/m =26.44kg.
853 5.22.2 Rate as per Item No.5.22.2 of kg 26.44 78.95
854 SH: Reinforced cement concrete work
855 Centering and shuttering
856 5.9.1 Rate as per item No.5.9.1 of SH : Reinforced sqm 6.99 216.45
857 cement concrete work
858 6mm C.Plaster 1:2 (1 Cement : 2 fine sand)
859 Details of cost for 9.88 sqm. (0.072)/10x9.88 =
860 367 0.071
861 Portland Cement (OPC-43 grade) tonne 0.05 4940
862 2209 Carriage of Cement tonne 0.05 94.34
863 983 Fine sand cum 0.07 850
864 2261 Carriage of Fine sand (1 part badarpur sand : 2 cum 0.07 106.13
865 parts Sand)
866 LABOUR
867 17 Beldar day 0.05 350.00
868 11 Bhisti day 0.02 350.00
869 40 Mason (average) day 0.64 403.67
870 18 Coolie day 0.8 350.00
871 11 Bhisti day 0.27 350.00
872 9999 Hire and running charges of mixer L.S. 1.95 2
873
874
875
876
877 1155
878
879
881 9999 Extra for removing burr, cleaning with wire L.S. 13.26 2
882 brushes, pock making with pointed tool etc.
883 complete
884 9999 Scaffolding and sundries L.S. 11.57 2
885 9977 Carriage of RCC posts L.S. 53.82 2
886 9999 Wooden plugs or 6mm bar nibs L.S. 12.22 2
887 9999 Sundries L.S. 13.52 2
888
889 TOTAL
890 Add 1 % Water charges on "W-A" 1187.88 11.88
891 TOTAL
892 Add GST (multiplying factor 0.1405) on "X-A" 1199.76 168.57
893 TOTAL
894 Add 15 % Contractor's profit and overheads on 1368.33 205.25
895 "Y-A"
896 Total
897 Add Cess @ 1% on "Z-A" 1573.58
898 Cost for 0.336 cum
899 Cost for one cum
900 Say
901
902 16.15.2 Welded steel wire fabric of required
903 width having rectangular mesh painted
904 Details of cost for 27 sqm (209.25 kg).
905
906 MATERIAL
907
908 Steel wire fabric 0.9m wide rectangular mesh
909 75x25mm size weight not less than
910 7.75kg/sqm. 30x0.9 = 27sqm
911 1021 Hard drawn steel wire fabric sqm 27 430
912 2314 Carriage of Barbed wire tonne 0.209 94.34
913 7.75x27=209.25kg=0.209tonne
914 TOTAL
915 Add 1 % Water charges on "W"
916 TOTAL
917 Add GST (multiplying factor 0.1405) on "X"
918 TOTAL
919 Add 15 % Contractor's profit and overheads on "Y"
920 Total
921 Add Cess @ 1% on "Z"
922 Cost for 209.25 kg
923
924
925
926
927 1156
928
929
931 Cost per kg.
932 Say
933
934 16.16 Supplying and fixing turn buckles
935 and straining bolts for barbed wire fencing.
936 Details of cost for one set
937 MATERIAL
938 1030 Galvanised steel turn buckles each 1 25
939 1028 Straining bolts each 1 80
940 9977 Carriage of turn buckles and straining bolts L.S. 2.73 2
941 Labour for fixing straining bolts and turn
942 13 buckles
943 Blacksmith 2nd class day 0.1 403.67
944 TOTAL
945 Add 1 % Water charges on "W"
946 TOTAL
947 Add GST (multiplying factor 0.1405) on "X"
948 TOTAL
949 Add 15 % Contractor's profit and overheads on "Y"
950 Total
951 Add Cess @ 1% on "Z"
952 Cost per set
953 Say
954
955 16.17 Fencing with R.C.C. post placed at
956 required distance, embedded in cement
957 16.17.1 With G.I. barbed wire
958
959 Details of cost for 30m
960
961 MATERIAL
962
963 G.I. barbed wire 30x9 = 270m +
964
965
966
967
968 1157
969
970
972 10x6.32 = 63m
973 Total = 333m
974 333m @9.38kg/100m =31.24kg = 0.31q
975 1029 Galvanised steel barbed wire quintal 0.31 5500
976 2314 Carriage of Barbed wire tonne 0.03 94.34
977 9999 G.I. staples or binding wire L.S. 49.4 2
978 LABOUR
979 Labour for fixing costs in line, fixing and
980 23 stretching wire
981 Mason (brick layer) 1st class day 0.12 505.17
982 24 Mason (brick layer) 2nd class day 0.12 403.67
983 17 Beldar day 0.5 350.00
984 12 Blacksmith 1st class day 0.5 505.17
985 13 Blacksmith 2nd class day 0.5 403.67
986 9999 Sundries L.S. 13.52 2
987 TOTAL
988 Add 1 % Water charges on "W"
989 TOTAL
990 Add GST (multiplying factor 0.1405) on "X"
991 TOTAL
992 Add 15 % Contractor's profit and overheads on "Y"
993 Total
994 Add Cess @ 1% on "Z"
995 Cost for 333m
996 Cost per m
997 Say
998
999 16.18 Fencing with angle iron post placed
### at required distance embedded in cement
### 16.18.1 With G.I. barbed wire
###
### Details of cost for 30m
###
### MATERIAL
###
### G.I. barbed wire 30x9 = 270.00m
###
### 2x10x(12+32)1/2 = 63.24 = 333.24m
###
### 333.24m @ 9.38kg/100m
###
###
###
### 1158
###
###
### =31.26 kg say 0.31 q
### 1029 Galvanised steel barbed wire quintal 0.31 5500
### 2314 Carriage of Barbed wire tonne 0.031 94.34
### Supplying and fixing Turn buckle & staple
### 16.16 Rate as per Item Number 16.16 of SH: Road each 10 197.9
### 9999 Work set 2
### G.I. staples L.S. 49.4 2
### Labour for fixing posts in line and fixing and
### 23 stretching wire:
### Mason (brick layer) 1st class day 0.12 505.17
### 24 Mason (brick layer) 2nd class day 0.12 403.67
### 17 Beldar day 0.5 350.00
### 12 Blacksmith 1st class day 0.5 505.17
### 13 Blacksmith 2nd class day 0.5 403.67
### TOTAL
### Add 1 % Water charges on "W-A" 2494.45
### TOTAL
### Add GST (multiplying factor 0.1405) on "X-A" 2519.39
### TOTAL
### Add 15 % Contractor's profit and overheads on 2873.37
### "Y-A"
### Total
### Add Cess @ 1% on "Z-A" 3304.37
### Cost for 333.24m
### Cost per m
### Say
###
###
### 16.19 Supplying at site Angle iron post &
### strut of required size including bottom to
### drilling holes upto 10 mm dia. etc.
### complete.
### Details of cost for 1 qunital
###
### MATERIAL
### M.S. angle = 1.00 qtl.
### Add 5% wastage = 0.05 qtl. Total = =1.05 qtl
### 1007 Structurals such as tees,angles channels and quintal 1.05 5300
### 2205 R.S. joists
### Carriage of Steel tonne 0.105 94.34
### LABOUR
### 13 Blacksmith 2nd class day 0.75 403.67
### 17 Beldar day 0.5 350.00
###
###
###
###
### 1159 1100
###
###
### For spotting, bending of angle and drilling
### 13 holes etc. :
### Blacksmith 2nd class day 1 403.67
### 17 Beldar day 1 350.00
### 9999 Sundries such as drilling bit etc. L.S. 19.76 2
### TOTAL
### Add 1 % Water charges on "W"
### TOTAL
### Add GST (multiplying factor 0.1405) on "X"
### TOTAL
### Add 15 % Contractor's profit and overheads on "Y"
### Total
### Add Cess @ 1% on "Z"
### Cost for 1 qunital
### Cost of one kg
### Say
###
###
### 16.20 Welded steel wire fabric fencing with
### posts of specified material and of standard
### Details of cost for 30 metres i.e.30x1.20
### =36.00sqm
### Labour for fixing posts in line fixing and
### 23 stretching - welded wire fabric :
### Mason (brick layer) 1st class day 0.12 505.17
### 24 Mason (brick layer) 2nd class day 0.12 403.67
### 17 Beldar day 0.5 350.00
### 12 Blacksmith 1st class day 0.5 505.17
### 13 Blacksmith 2nd class day 0.5 403.67
### 9999 G.I. staple or binding wire L.S. 53.82 2
### 9999 Sundries L.S. 53.82 2
###
###
###
###
###
### 1160
###
###
### TOTAL
### Add 1 % Water charges on "W"
### TOTAL
### Add GST (multiplying factor 0.1405) on "X"
### TOTAL
### Add 15 % Contractor's profit and overheads on "Y"
### Total
### Add Cess @ 1% on "Z"
### Cost for 36 sqm
### Cost per sqm
### Say
### 16.21 Engraving letters in hard stone
### Details of cost for 6 letters 8 cm height
### LABOUR
### For Engraving stone-
### 26 Mason (for ornamental stone work) 1st class day 0.38 505.17
### 9999 Sundries L.S. 6.76 2
### TOTAL
### Add 1 % Water charges on "W"
### TOTAL
### Add GST (multiplying factor 0.1405) on "X"
### TOTAL
### Add 15 % Contractor's profit and overheads on "Y"
### Total
### Add Cess @ 1% on "Z"
### Cost of 6 letters of 8cm heights
### Cost per cm. height per letter
### Say
###
###
### 16.22 Providing and fixing 15x15x90 cm
### boundary stone of hard stone with top 30
### Details of cost for one stone
###
### 1151 Boundry stone top chisel dressed each 1 80
### 15x15x90 cm
### Labour for fixing
### 17 Beldar day 0.12 350.00
### 9977 Carriage to site L.S. 4.16 2
###
###
###
###
### 1161
###
###
### Code Description Unit Quantity Rate Amount
### TOTAL
### Add 1 % Water charges on "W" 1.27
### TOTAL
### Add GST (multiplying factor 0.1405) on "X" 18
### TOTAL
### Add 15 % Contractor's profit and overheads on "Y" 21.91
### Total
### Add Cess @ 1% on "Z" 1.68
### Cost of each. 169.68
### Say 169.7
###
### 16.23 Providing and fixing 15 cm dia at
### top, 20 cm at bottom and 90 cm high
### Details of cost for one stone
### (i) Cement concrete 1:1½:3 (1 cement : 1½
### Coarse sand : 3 graded stone aggregate
### 20mm nominal size) Volume of frustum of
### cone:
### L/3 x [A1+A2+sqrt(A1A2)] = 0.825/3 x
### [0.095²+
### 0.075² + sqrt(0.095 x 0.075²)]x3.142
### 0.01882
### (A) Volume of hemi sphere:
### ½ x 4 /3 x PI x r³ =
### ½x(4/ 3)x(22/7)x0.075³=0.00100 (B)
### Total volume = A+B = 0.01982 Say 0.02cum
### 4.1.2 Rate as per item no 4.1.2 of S.H. Concrete cum 0.02 6376.3
### Work.
### (ii) Extra for laying cement concerte in
### RCC work
### LABOUR
### 17 Beldar day 0.002 350.00
### 11 Bhisti day 0.004 350.00
### 23 Mason (brick layer) 1st class day 0.0008 505.17
### 24 Mason (brick layer) 2nd class day 0.0008 403.67
### 28 Mate day 0.0008 350.00
### (iii) M.S. reinforcement-
###
### 6mm dia. bar
###
### 5.99 metre =5.99x0.22 =1.32kg.
###
###
###
### 1162
###
###
### 5.22.1 Rate as per item no. 5.22.1 of SH : RCC work kg 1.32 75.4
### (iv) Centering and shuttering-
### 1/2x3.142 (0.19+0.15)x0.825 =0.441 +
### 3.142/4(0.19)² =0.028 +
### 1/2x4x3.142(0.075)² = 0.035 = 0.504
### Say 0.50sqm.
### 5.9.1 Rate as per item No.5.9.1 of SH : Reinforced sqm 0.5 216.45
### cement concrete work
### (v) 6mm cement plaster 1:3 (1 Cement :
### 3 fine sand)-
### 1/2x3.142 (0.19+0.15)x0.825 =0.44 +
### 3.142/4(0.19)² =0.028 +
### 1/2x4x3.142(0.075)² = 0.035 = 0.504 Say
### 0.50sqm.
### MATERIAL
### 367 Portland Cement (OPC-43 grade) tonne 0.0018 4375
### 2209 Carriage of Cement tonne 0.0018 94.34
### 983 Fine sand cum 0.0385 850
### 2261 Carriage of Fine sand (1 part badarpur sand : cum 0.0385 106.13
### 2 parts Sand)
### Labour for mortar
### 17 Beldar day 0.0027 350.00
### 11 Bhisti day 0.0002 350.00
### 9999 Hire and running charges of mixer L.S. 0.1 2
### 9999 Sundries L.S. 0.05 2
### Labour for plaster
### 40 Mason (average) day 0.026 403.67
### 18 Coolie day 0.038 350.00
### 11 Bhisti day 0.046 350.00
### 9999 Extra for removing burr L.S. 0.68 2
### 9999 Scaffolding, sundries etc. (vi) Labour for fixing L.S. 0.6 2
### 17 Beldar day 0.12 350.00
### 9977 Carriage to site L.S. 4.16 2
### TOTAL
### Add 1 % Water charges on "W-A" 137.96
### TOTAL
### Add GST (multiplying factor 0.1405) on "X-A" 139.34
### TOTAL
### Add 15 % Contractor's profit and overheads on 158.91
### "Y-A"
### Total
### Add Cess @ 1% on "Z-A" 182.75
### Cost of each.
###
###
###
###
###
### 1163
###
###
### 5.9.1
###
###
### Say
###
### 16.24 Providing and fixing precast
### reinforced cement concrete 1:1.5:3 (1
### 16.24.1 35x111x25 cm size
### Details of cost for one stone
### (i) Cement concrete 1:1.5:3 (1 cement :1.5
### Coarse sand :3 graded stone aggregate
### 20mm nominal size) in Kilometre stone
### 0.35x0.25x0.835m = 0.073
### 0.37x0.27x0.10m = 0.010
### 1/2x22/7x(0.175)²x0.25m = 0.012 = 0.095cum
### Say 0.10cum.
### 4.1.2 Rate as per item no 4.1.2 of S.H. Concrete cum 0.1 6376.3
### Work.
### (ii) Extra for laying cement concrete in RCC
### 17 work
### Beldar day 0.01 350.00
### 11 Bhisti day 0.02 350.00
### 23 Mason (brick layer) 1st class day 0.004 505.17
### 24 Mason (brick layer) 2nd class day 0.004 403.67
### 28 Mate day 0.004 350.00
### (iii) M.S. reinforcement-
### 0.10cum @48.06kg/cum. =4.806kg.
### Say 4.81kg.
### 5.22.1 Rate as per item no. 5.22.1 of kg 4.81 75.4
###
### SH : Reinforced cement concrete work (iv) Centering
and shuttering-(0.35+2x0.25)x0.835 = 0.710 sqm
###
### 2x2x0.25x0.1 = 0.010sqm 1/2x3.142/4x(0.35)²
###
### = 0.048sqm 1/2x0.35x0.25x3.142 = 0.138sqm.
###
### = 1.092sqm. Say 1.09 sqm
###
### Rate as per item No.5.9.1 of sqm 1.09 216.45
###
### SH : Reinforced cement concrete work (v) 6mm
cement plaster 1:3 (1 Cement :
###
### 3 fine sand)-
###
### Qty. as per centering and shuttering = 1.092sqm
###
###
###
### 1164
###
###
### 0.35x0.835 = 0.292sqm
### 0.37x0.10 = 0.037sqm
### 1/2x3.142/4x(0.35)²= 0.048sqm
### 2x0.37x0.01 = 0.007 sqm
### = 1.476 sqm Say 1.48 sqm
### 367 Portland Cement (OPC-43 grade) tonne 0.054 4940
### 2209 Carriage of Cement tonne 0.054 94.34
### 983 Fine sand cum 0.011 850
### 2261 Carriage of Fine sand (1 part badarpur sand cum 0.011 106.13
### : 2 parts Sand)
### Labour for mortar
### 17 Beldar day 0.008 350.00
### 11 Bhisti day 0.0007 350.00
### 9999 Hire and running charges of mixer L.S. 0.03 2
### 9999 Sundries L.S. 0.13 2
### Labour for plaster
### 40 Mason (average) day 0.075 403.67
### 18 Coolie day 0.111 350.00
### 11 Bhisti day 0.136 350.00
### 9999 Extra for removing burr L.S. 1.95 2
### 9999 Scaffolding, sundries etc. (vi) Labour for fixing L.S. 1.82 2
### 17 Beldar day 0.2 350.00
### 9977 Carriage to site L.S. 13.52 2
### TOTAL
### Add 1 % Water charges on "W-A" 506.42
### TOTAL
### Add GST (multiplying factor 0.1405) on "X-A" 511.49
### TOTAL
### Add 15 % Contractor's profit and overheads on 583.35
### "Y-A"

### Total
### Add Cess @ 1% on "Z-A" 670.85
### Cost per stone
### Say
###
### 16.24.2 50x152.5x25 cm size
###
### Details of cost for one stone
###
### (i) Cement concrete 1:1.5:3 (1 cement :1.5 Coarse
sand :3 graded stone aggregate
###
###
###
### 1165
###
###
### 20mm nominal size)
### 0.50x0.25x1.145m = 0.143cum. +
### 0.52x0.27x0.13m = 0.018cum. +
### 1/2x22/7x(0.25)²x0.25m = 0.025cum.
### = 0.186 cum. Say 0.19cum.
### 4.1.2 Rate as per item no 4.1.2 of S.H. Concrete cum 0.19 6376.3
### Work.
### (ii) Extra for laying cement concrete in RCC
### 17 work
### Beldar day 0.019 350.00
### 11 Bhisti day 0.038 350.00
### 23 Mason (brick layer) 1st class day 0.008 505.17
### 24 Mason (brick layer) 2nd class day 0.008 403.67
### 28 Mate day 0.008 350.00
### (iii) M.S. reinforcement-
### 0.19cum @48.06kg/cum. =9.131kg.
### Say 9.13 kg.
### 5.22.1 Rate as per item no. 5.22.1 of kg 9.13 75.4
### SH : Reinforced cement concrete work
### (iv) Centering and shuttering-
### (0.50+2x0.25)x1.145 = 1.145 sqm
### 1/2x(0.25)²x3.142 = 0.098
### 3.142(0.25)x(0.25) =0.196
### (0.52+2x0.27)x0.13 =0.138
### 2x0.52x0.01 =0.10
### 2x2x0.25x0.01 =0.010
### 1x0.50x0.25 =0.125
### =1.722sqm. Say 1.72 sqm
### 5.9.1 Rate as per item No.5.9.1 of SH : Reinforced sqm 1.72 216.45
### cement concrete work
### (v) 6mm cement plaster 1:3 (1 Cement :
### 3 fine sand)-
### Qty. as per centering and shuttering
### = 1.722sqm. +
### 0.50x1.145 = 0.572 +
### 0.52x0.13 = 0.068sqm. +
### 1/2x(0.25)²x3.142 = 0.098 +
### 2x0.52x001 = 0.010
### = 2.470sqm Sq. 2.47 sqm.
### MATERIAL
### 367 Portland Cement (OPC-43 grade) tonne 0.09 4375
### 2209 Carriage of Cement tonne 0.09 94.34
### 983 Fine sand cum 0.2 850
### 2261 Carriage of Fine sand (1 part badarpur sand cum 0.2 106.13
### : 2 parts Sand) Labour for mortar
###
###
###
###
### 1166
###
###
### 17 Beldar day 0.013 350.00
### 11 Bhisti day 0.001 350.00
### 9999 Hire and running charges of mixer L.S. 0.52 2
### 9999 Sundries L.S. 0.26 2
### Labour for plaster
### 40 Mason (average) day 0.126 403.67
### 18 Coolie day 0.185 350.00
### 11 Bhisti day 0.227 350.00
### 9999 Extra for removing burr L.S. 3.38 2
### 9999 Scaffolding, sundries etc. (vi) Labour for fixing L.S. 2.86 2
### 17 Beldar day 0.2 350.00
### 9977 Carriage to site L.S. 13.52 2
### TOTAL
### Add 1 % Water charges on "W-A" 971.08
### TOTAL
### Add GST (multiplying factor 0.1405) on "X-A" 980.79
### TOTAL
### Add 15 % Contractor's profit and overheads on 1118.59
### "Y-A"
### Total
### Add Cess @ 1% on "Z-A" 1286.38
### Cost per stone
### Say
### 16.24.3 35x93.5x18 cm size
### Details of cost for one stone
### (i) Cement concrete 1:1.5:3 (1 cement :1.5
### Coarse sand :3 graded stone aggregate
### 20mm nominal size)
### 0.35x0.18x0.835m = 0.0526 cum. + 0.37x0.20x0.10m =
0.0074 cum.
### = 0.060 cum.
### 4.1.2 Rate as per item no 4.1.2 of S.H. Concrete cum 0.06 6376.3
### Work.
### (ii) Extra for laying cement concrete in RCC
### 17 work
### Beldar day 0.006 350.00
### 11 Bhisti day 0.012 350.00
### 23 Mason (brick layer) 1st class day 0.0024 505.17
### 24 Mason (brick layer) 2nd class day 0.0024 403.67
### 28 Mate day 0.0024 350.00
###
###
###
###
###
### 1167
###
###
### (iii) M.S. reinforcement-
### 0.06cum @48.06kg/cum. =2.8836 kg.
### Say 2.88 kg.
### 5.22.1 Rate as per item no. 5.22.1 of kg 2.88 75.4
### SH : Reinforced cement concrete work
### (iv) Centering and shuttering-
### (0.35+2x0.18)x0.835 = 0.593 sqm
### (0.37+2x0.20)x0.10 = 0.077 sqm
### 2x0.35x0.18 = 0.126 sqm
### 2x0.37x0.01 = 0.007sqm
### 2x2x0.18x0.01 = 0.007sqm
### = 0.810 sqm
### 5.9.1 Rate as per item No.5.9.1 of sqm 0.81 216.45
### SH : Reinforced cement concrete work (v)
### 6mm cement plaster 1:3 (1 Cement :
### 3 fine sand)-
### Qty. as per centering and shuttering
### = 0.810sqm
### 0.35x0.835 = 0.292sqm 0.37x0.10 =0.037sqm
### 2x0.37x0.01 =0.007sqm
### = 1.146 sqm Say 1.15sqm
### MATERIAL
### 367 Portland Cement (OPC-43 grade) tonne 0.042 4375
### 2209 Carriage of Cement tonne 0.042 94.34
### 983 Fine sand cum 0.009 850
### 2261 Carriage of Fine sand (1 part badarpur sand cum 0.009 106.13
### : 2 parts Sand)
### Labour for mortar
### 17 Beldar day 0.006 350.00
### 11 Bhisti day 0.0006 350.00
### 9999 Hire and running charges of mixer L.S. 0.26 2
### 9999 Sundries L.S. 0.13 2
### Labour for plaster
### 40 Mason (average) day 0.058 403.67
### 18 Coolie day 0.086 350.00
### 11 Bhisti day 0.105 350.00
### 9999 Extra for removing burr L.S. 1.56 2
### 9999 Scaffolding, sundries etc. (vi) Labour for fixing L.S. 1.3 2
### 17 Beldar day 0.1 350.00
###
###
###
###
### 1168
###
###
### 9977 Carriage to site L.S. 13.52 2
### TOTAL
### Add 1 % Water charges on "W-A" 379.82
### TOTAL
### Add GST (multiplying factor 0.1405) on "X-A" 383.62
### TOTAL
### Add 15 % Contractor's profit and overheads on 437.52
### "Y-A"
### Total
### Add Cess @ 1% on "Z-A" 503.15
### Cost of each
### Say
###
###
### 16.25 Surface dressing on new surface
### with paving bitumen of grade VG - 10 of
### Details of cost for 100 sqm.
### MATERIAL
### Bitumen S-90@2.25kg per sqm. =225 kg =
### 309 0.225 tonne. 48000
### Paving bitumen VG-10 of approved quality tonne 0.225 25614
### 2211 Carriage of Tar bitumen tonne 0.225 106.13
### Stone aggregate 13.2mm nominal size @
### 2910 1.65cum. per 100sqm. 1150
### Stone chippings/ screenings 12.5/ 13.2 mm cum 1.65 1150
### 2202 nominal size
### Carriage of Stone aggregate below 40 mm cum 1.65 106.13
### nominal size
### Steam coal for heating bitumen @2 quintal per
### tonne of bitumen = 2x0.225=0.450q
### 370 Coal (steam) quintal 0.45 440
### 2200 Carriage of steam coal tonne 0.045 121.29
### Labour for cleaning the road surface, heating
### and spraying bitumen and aggregate (a) For
### 28 cleaning :
### Mate day 0.11 350.00
### 17 Beldar day 1.4 350.00
### 18 Coolie day 1.4 350.00
### (b) For heating and spraying bitumen :
### 30 Mistry day 0.08 505.17
### 36 Sprayer (for bitumen, tar etc.) day 0.11 350.00
###
###
###
###
###
### 1169
###
###
### 17 Beldar day 0.93 350.00
### (c) For screening and spreading aggregate :
### 28 Mate day 0.11 350.00
### 17 Beldar day 0.93 350.00
### 18 Coolie day 1.55 350.00
### (d) Consolidation Charges
### 16 Chowkidar day 0.27 350.00
### 11 Bhisti day 0.11 350.00
### 3 Hire charges of Diesel Road Roller - 8 to 10 day 0.11 3000
### 1 tonne 800
### Hire charges of Coaltar Boiler 900 to 1400 day 0.12 800
### 7 litres
### Hire charges of Coaltar Sprayer (e) Misc: day 0.11 300
### 364 Wire brush each 0.11 20
### 365 Soft brush each 0.32 20
### 9999 Brooms and gunny bags L.S. 6.76 2
### 9999 Sundries L.S. 6.76 2
### TOTAL
### Add 1 % Water charges on "W"
### TOTAL
### Add GST (multiplying factor 0.1405) on "X"
### TOTAL
### Add 15 % Contractor's profit and overheads on "Y"
### Total
### Add Cess @ 1% on "Z"
### Cost for 100 Sqm.
### Cost per Sqm.
### Say
###
###
### 16.26 Surface dressing on new surface in
### two coats with bitumen of grade VG -10 of
### Details of cost for 100 sqm.
### MATERIAL
### Bitumen S-90/A-90 @
### 1.8kg/sqm.=180kg.=0.18 tonne
### 309 Paving bitumen VG-10 of approved quality tonne 0.18 48000
### 2211 Carriage of Tar bitumen tonne 0.18 106.13
###
###
###
### 1170
###
###
### 2910 Stone chippings/ screenings 12.5/ 13.2 mm cum 1.5 1150
### 2202 nominal size
### Carriage of Stone aggregate below 40 mm cum 1.5 106.13
### nominal size
### Steam coal for heating bitumen @2 qunital per
### 370 tonne
### Coal (steam) quintal 0.36 440
### 2200 Carriage of steam coal tonne 0.036 121.29
### Labour for cleaning the road surface, heating
### and spraying bitumen and aggregate (a) For
### 28 cleaning :
### Mate day 0.11 350.00
### 17 Beldar day 1.4 350.00
### 18 Coolie day 1.4 350.00
### (b) For heating and spraying bitumen :
### 30 Mistry day 0.08 505.17
### 36 Sprayer (for bitumen, tar etc.) day 0.11 350.00
### 17 Beldar day 1.38 350.00
### (c) For screening and spreading aggregate :
### 28 Mate day 0.27 350.00
### 17 Beldar day 0.85 350.00
### 18 Coolie day 0.85 350.00
### (d) Consolidation Charges
### 16 Chowkidar day 0.11 350.00
### 11 Bhisti day 0.11 350.00
### 3 Hire charges of Diesel Road Roller - 8 to 10 day 0.11 3000
### 1 tonne 800
### Hire charges of Coaltar Boiler 900 to 1400 day 0.12 800
### 7 litres
### Hire charges of Coaltar Sprayer (e) Misc: day 0.11 300
### 364 Wire brush each 0.11 20
### 365 Soft brush each 0.32 20
### 9999 Brooms and gunny bags L.S. 6.76 2
### 9999 Sundries L.S. 16.38 2
### Second Coat
### MATERIAL
### Bitumen S-90/A-90 @ 1.10kg per sqm =
### 110kg.=0.11 tonne
### 309 Paving bitumen VG-10 of approved quality tonne 0.11 48000
### 2911 Stone chippings/ screenings 10/ 11.2 mm cum 1 1150
### 2211 nominal size
### Carriage of Tar bitumen tonne 0.11 106.13
### 2202 Carriage of Stone aggregate below 40 mm cum 1 584.88
### nominal size
###
###
###
###
### 1171
###
###
### Steam coal for heating bitumen @2 qunital per
### 370 tonne of bitumen
### Coal (steam) quintal 0.22 440
### 2200 Carriage of steam coal tonne 0.022 121.29
### Labour for cleaning the road surface, heating
### and spraying bitumen and aggregate
### (a) For cleaning and brushing loose chips:
### 28 Mate day 0.06 350.00
### 18 Coolie day 0.97 350.00
### (b) For heating and spraying bitumen :
### 30 Mistry day 0.05 505.17
### 36 Sprayer (for bitumen, tar etc.) day 0.07 350.00
### 17 Beldar day 0.75 350.00
### (c) For screening and spreading aggregate :
### 28 Mate day 0.07 350.00
### 17 Beldar day 0.62 350.00
### 18 Coolie day 0.62 350.00
### (d) Consolidation Charges
### 16 Chowkidar day 0.15 350.00
### 11 Bhisti day 0.06 350.00
### 3 Hire charges of Diesel Road Roller - 8 to 10 day 0.06 3000
### 7 tonne
### Hire charges of Coaltar Sprayer day 0.07 300
### 1 Hire charges of Coaltar Boiler 900 to 1400 litres day 0.06 800
### 364 Wire brush each 0.03 20
### (with thick wire)
### 365 Soft brush each 0.09 20
### 9999 Sundries L.S. 9.49 2
### TOTAL
### Add 1 % Water charges on "W"
### TOTAL
### Add GST (multiplying factor 0.1405) on "X"
### TOTAL
### Add 15 % Contractor's profit and overheads on "Y"
### Total
### Add Cess @ 1% on "Z"
### Cost for two coats per 100sqm.
### Cost per Sqm.
### Say
###
###
###
###
###
###
###
###
### 1172
###
###
###
### 16.27 Surface dressing on old surface with
### hot bitumen of grade VG - 10 of approved
### Details of cost for 100 sqm.
### MATERIAL
### Bitumen 1.95kg./sqm.= 195kg. or 0.195t
### 309 Paving bitumen VG-10 of approved quality tonne 0.195 48000
### 2911 Stone chippings/ screenings 10/ 11.2 mm cum 1.5 1150
### nominal size
### @ 1.50cum. per 100 sqm.
### 2211 Carriage of Tar bitumen tonne 0.195 106.13
### 2202 Carriage of Stone aggregate below 40 mm cum 1.5 584.88
### nominal size
### Steam coal for heating bitumen @2 quintal per
### 370 tonne of bitumen
### Coal (steam) quintal 0.39 440
### 2200 Carriage of steam coal tonne 0.039 121.29
### Labour for cleaning the road surface, heating
### and spraying bitumen and aggregate etc.
### (a) For cleaning :
### 28 Mate day 0.06 350.00
### 17 Beldar day 0.49 350.00
### 18 Coolie day 0.97 350.00
### (b) For heating and spraying bitumen :
### 30 Mistry day 0.05 505.17
### 36 Sprayer (for bitumen, tar etc.) day 0.06 350.00
### 17 Beldar day 0.69 350.00
### (c) For screening and spreading aggregate :
### 28 Mate day 0.66 350.00
### 17 Beldar day 0.51 350.00
### 18 Coolie day 0.51 350.00
### (d) Consolidation Charges
### 16 Chowkidar day 0.15 350.00
### 11 Bhisti day 0.06 350.00
### 3 Hire charges of Diesel Road Roller - 8 to 10 day 0.06 3000
### 7 tonne
### Hire charges of Coaltar Sprayer day 0.06 300
### 1 Hire charges of Coaltar Boiler 900 to day 0.06 800
### 1400 litres (e) Misc:
### Brushes etc. for cleaning
###
###
###
### 1173
###
###
### 364 Wire brush each 0.05 20
### (with thick wire)
### 365 Soft brush each 0.12 20
### 9999 Brooms and gunny bags L.S. 2.73 2
### 9999 Sundries L.S. 5.33 2
### TOTAL
### Add 1 % Water charges on "W"
### TOTAL
### Add GST (multiplying factor 0.1405) on "X"
### TOTAL
### Add 15 % Contractor's profit and overheads on "Y"
### Total
### Add Cess @ 1% on "Z"
### Cost for 100 sqm.
### Cost per Sqm.
### Say
###
### 16.28 Surface dressing one coat on new
### surface with bitumen of specified grade at
### 16.28.1 Using bitumen emulsion (minimum
### 50% bitumen content- RS grade conforming
### Details of cost for 100 sqm.
###
### MATERIAL
### 310 Bitumen emulsion tonne 0.195 50000
### 2211 Carriage of Tar bitumen tonne 0.195 106.13
### 2910 Stone chippings/ screenings 12.5/ 13.2 mm cum 1.5 1150
### nominal size
### @1.50 cum. per 100 sqm. = 1.50cum
### 2202 Carriage of Stone aggregate below 40 mm cum 1.5 584.88
### nominal size
### Labour for cleaning the road surface, heating
### and spraying bitumen and aggregate :
### (a) For cleaning :
### 28 Mate day 0.11 350.00
### 17 Beldar day 1.4 350.00
### 18 Coolie day 1.4 350.00
### (b) For Spraying bitumen emulsion :
### 30 Mistry day 0.07 505.17
### 36 Sprayer (for bitumen, tar etc.) day 0.1 350.00
###
###
###
###
###
### 1174
###
###
### 17 Beldar day 1 350.00
### (c) For screening and spreading aggregate :
### 28 Mate day 0.11 350.00
### 17 Beldar day 0.85 350.00
### 18 Coolie day 0.85 350.00
### (d) Consolidation Charges
### 16 Chowkidar day 0.27 350.00
### 11 Bhisti day 0.27 350.00
### 3 Hire charges of Diesel Road Roller - 8 to 10 day 0.11 3000
### 7 tonne
### Hire charges of Coaltar Sprayer (e) Misc: day 0.1 300
### Brushes etc. for cleaning
### 364 Wire brush each 0.11 20
### (with thick wire)
### 365 Soft brush each 0.32 20
### 9999 Brooms and gunny bags L.S. 6.76 2
### 9999 Sundries L.S. 9.49 2
### TOTAL
### Add 1 % Water charges on "W"
### TOTAL
### Add GST (multiplying factor 0.1405) on "X"
### TOTAL
### Add 15 % Contractor's profit and overheads on "Y"
### Total
### Add Cess @ 1% on "Z"
### Cost for 100 sqm.
### Cost per Sqm.
### Say
###
###
### 16.29 Surface dressing one coat on old
### surface with bitumen of specified grade at
### 16.29.1 Using bitumen emulsion (minimum
### 50% bitumen content- RS grade conforming
### Details of cost for 100 sqm.
###
### MATERIAL
###
###
###
###
### 1175
###
###
### Bitumen emulsion @1.22 kg per Sqm. =122
### 310 kg. or 0.122 tonne 50000
### Bitumen emulsion tonne 0.122 30099
### 2211 Carriage of Tar bitumen tonne 0.122 106.13
### Stone chippings 11.2mm nominal size @
### 1.10cum. per 100 sqm
### 2911 Stone chippings/ screenings 10/ 11.2 mm cum 1.1 1150
### 2202 nominal size
### Carriage of Stone aggregate below 40 mm cum 1.1 106.13
### nominal size
### Labour for cleaning the road surface, heating
### and spraying bitumen and aggregate :
### (a) For cleaning :
### 28 Mate day 0.06 350.00
### 17 Beldar day 0.49 350.00
### 18 Coolie day 0.97 350.00
### (b) For Spraying bitumen emulsion :
### 30 Mistry day 0.05 505.17
### 36 Sprayer (for bitumen, tar etc.) day 0.06 350.00
### 17 Beldar day 0.63 350.00
### (c) For screening and spreading aggregate :
### 28 Mate day 0.07 350.00
### 17 Beldar day 0.62 350.00
### 18 Coolie day 0.62 350.00
### (d) Consolidation Charges
### 16 Chowkidar day 0.15 350.00
### 11 Bhisti day 0.15 350.00
### 3 Hire charges of Diesel Road Roller - 8 to 10 day 0.06 3000
### 7 tonne
### Hire charges of Coaltar Sprayer (e) Misc: day 0.06 300
### Brushes etc. for cleaning
### 364 Wire brush each 0.11 20
### (with thick wire)
### 365 Soft brush each 0.32 20
### 9999 Brooms and gunny bags L.S. 2.73 2
### 9999 Sundries L.S. 5.33 2
### TOTAL
### Add 1 % Water charges on "W"
### TOTAL
### Add GST (multiplying factor 0.1405) on "X"
### TOTAL
### Add 15 % Contractor's profit and overheads on "Y"
###
###
###
###
###
###
### 1176
###
###
### Code Description Unit Quantity Rate Amount
### Total
### Add Cess @ 1% on "Z" 86.62
### Cost for 100 sqm. 8748.59
### Cost per Sqm. 87.49
### Say 87.5
###
###
### 16.30 16.30 Providing and applying tack
### coat using hot straight run bitumen of
### 16.30.1 On W.B.M. @ 0.75 Kg / sqm
###
### Details of cost for 100 sqm.
### MATERIAL
### 2916 Paving Asphalt VG -10 of approved quality tonne 0.075 24000
### 2211 Carriage of Tar bitumen tonne 0.075 106.13
### 370 Coal (steam) quintal 0.15 440
### 2200 Carriage of steam coal tonne 0.015 121.29
### MATERIAL
### 364 Wire brush each 0.05 20
### (with thick wire)
### 365 Soft brush each 0.12 20
### 9999 Gunny bags L.S. 7.8 2
### 7 Hire charges of Coaltar Sprayer day 0.03 300
### 9999 Sundries L.S. 9.1 2
### LABOUR
### (a) For cleaning :
### 28 Mate day 0.06 350.00
### 17 Beldar day 1.46 350.00
### (b) For heating bitumen:
### 17 Beldar day 0.19 350.00
### (c) For applying tack coat:
### 17 Beldar day 0.47 350.00
### TOTAL
### Add 1 % Water charges on "W"
### TOTAL
### Add GST (multiplying factor 0.1405) on "X"
### TOTAL
### Add 15 % Contractor's profit and overheads on "Y"
### Total
###
###
###
### 1177
###
###
### Add Cess @ 1% on "Z"
### Cost for 100 sqm.
### Cost per Sqm.
### Say
### 16.30.2 On bituminous surface @ 0.50 Kg / sqm
### Details of cost for 100 sqm.
### MATERIAL
### 2916 Paving Asphalt VG -10 of approved quality tonne 0.05 24000
### 2211 Carriage of Tar bitumen tonne 0.05 106.13
### 370 Coal (steam) quintal 0.1 440
### 2200 Carriage of steam coal tonne 0.01 121.29
### MATERIAL
### 364 Wire brush each 0.05 20
### (with thick wire)
### 365 Soft brush each 0.12 20
### 9999 Gunny bags L.S. 7.8 2
### 7 Hire charges of Coaltar Sprayer day 0.03 300
### 9999 Sundries L.S. 7.8 2
### LABOUR
### (a) For cleaning :
### 28 Mate day 0.06 350.00
### 17 Beldar day 1.46 350.00
### (b) For heating bitumen:
### 17 Beldar day 0.19 350.00
### (c) For applying tack coat:
### 17 Beldar day 0.47 350.00
### TOTAL
### Add 1 % Water charges on "W"
### TOTAL
### Add GST (multiplying factor 0.1405) on "X"
### TOTAL
### Add 15 % Contractor's profit and overheads on "Y"
### Total
### Add Cess @ 1% on "Z"
### Cost for 100 sqm.
### Cost per Sqm.
###
###
###
###
###
###
### 1178
###
###
###
### Say
###
### 16.31 Providing and applying tack coat
### using bitumen emulsion conforming to IS:
### 16.31.1 With rapid setting bitumen emulsion
### 16.31.1.1
Details On W.B.M
of cost for 3500 /sqm.
W.M.M. @ 0.4kg/sqm
### MATERIAL
### 7382 Bitumen emulsion rapid setting (R.S.) tonne 1.4 19000
### 2211 confirming to IS : 8887-1995
### Carriage of Tar bitumen tonne 1.4 106.13
### MACHINERY
### 73 Road sweeper (Mechamical Broom) @ 1250 hour 2.8 350
### 58 sqm. Per hour.
### Air compressor hour 2.8 200
### 61 Emulsion Pressure Distributor @ hour 2 800
### 1750 sqm per hour
### LABOUR
### 28 Mate day 0.08 350.00
### 17 Beldar day 2 350.00
### TOTAL
### Add 1 % Water charges on "W"
### TOTAL
### Add GST (multiplying factor 0.1405) on "X"
### TOTAL
### Add 15 % Contractor's profit and overheads on "Y"
### Total
### Add Cess @ 1% on "Z"
### Cost for 3500 sqm.
### Cost per Sqm.
### Say
###
### 16.31.1.2 On bituminous surface @
### 0.25kg/sqm
### Details of cost for 3500 sqm.
### MATERIAL
### 7382 Bitumen emulsion rapid setting (R.S.) tonne 0.875 19000
### 2211 confirming to IS : 8887-1995
### Carriage of Tar bitumen tonne 0.875 106.13
### MACHINERY
### 73 Road sweeper (Mechamical Broom) @ 1250 hour 2.8 350
### sqm. Per hour.
###
###
###
### 1179
###
###
### 58 Air compressor hour 2.8 200
### 61 Emulsion Pressure Distributor @ hour 2 800
### 1750 sqm per hour
### LABOUR
### 28 Mate day 0.08 350.00
### 17 Beldar day 2 350.00
### TOTAL
### Add 1 % Water charges on "W"
### TOTAL
### Add GST (multiplying factor 0.1405) on "X"
### TOTAL
### Add 15 % Contractor's profit and overheads on "Y"
### Total
### Add Cess @ 1% on "Z"
### Cost for 3500 sqm.
### Cost per Sqm.
### Say
###
### 16.31.2 With medium setting bitumen
### emulsion
Details for 3500On
16.31.2.1
of cost W.B.M
sqm. / W.M.M. @
### MATERIAL
### 7742 Bitumen emulsion medium setting (M.S.) tonne 1.4 27909
### 2211 confirming to IS : 8887-1995
### Carriage of Tar bitumen tonne 1.4 106.13
### MACHINERY
### 73 Road sweeper (Mechamical Broom) @ 1250 hour 2.8 350
### 58 sqm. Per hour.
### Air compressor hour 2.8 200
### 61 Emulsion Pressure Distributor @ 1750 sqm per hour 2 800
### hour
### LABOUR
### 28 Mate day 0.08 350.00
### 17 Beldar day 2 350.00
### TOTAL
### Add 1 % Water charges on "W"
### TOTAL
### Add GST (multiplying factor 0.1405) on "X"
###
###
###
###
### 1180
###
###
### TOTAL
### Add 15 % Contractor's profit and overheads on "Y"
### Total
### Add Cess @ 1% on "Z"
### Cost for 3500 sqm.
### Cost per Sqm.
### Say
### 16.31.2.2 On bituminous surface @
### 0.25kg/sqm
Details of cost for 3500 sqm.
### MATERIAL
### 7742 Bitumen emulsion medium setting (M.S.) tonne 0.875 27909
### 2211 confirming to IS : 8887-1995
### Carriage of Tar bitumen tonne 0.875 106.13
### MACHINERY
### 73 Road sweeper (Mechamical Broom) @ 1250 hour 2.8 350
### 58 sqm. Per hour.
### Air compressor hour 2.8 200
### 61 Emulsion Pressure Distributor @ hour 2 800
### 1750 sqm per hour
### LABOUR
### 28 Mate day 0.08 350.00
### 17 Beldar day 2 350.00
### TOTAL
### Add 1 % Water charges on "W"
### TOTAL
### Add GST (multiplying factor 0.1405) on "X"
### TOTAL
### Add 15 % Contractor's profit and overheads on "Y"
### Total
### Add Cess @ 1% on "Z"
### Cost for 3500 sqm.
### Cost per Sqm.
### Say
###
### 16.32 2 cm premix carpet surfacing with
### 1.8 cum and 0.90 cum of stone chippings of
###
###
###
### 1181
###
###
###
### 16.32.1 With paving Asphalt grade VG - 10
### heated and then mixed with solvent at the
### Details of cost for 100 sqm.
###
### Asphalt 80/100
###
### (i) Hot bitumen @52kg.per cum. of stone chippings 1.8cum.
of 13.2mm nominal size
### chippings.
### (ii) Hot bitumen @56kg. per cum. of stone chippings
0.90cum. of 11.2mm nominal size
### chippings.
### Bitumen :52xl.8+56x0.9=144kg. or 0.144 tonne
###
### MATERIAL
### 2916 Paving Asphalt VG 10 of approved quality tonne 0.144 24000
### 2211 Carriage of Tar bitumen tonne 0.144 106.13
### Solvent 70gms/kg. for 0.144 t = 10.08kg.
### 2914 Solvent kilogra 10.08 25
### 2342 m
### Carriage of solvent/ Diesel. quintal 0.1 10.61
### 2910 Stone chippings/ screenings 12.5/ 13.2 mm cum 1.8 1150
### nominal size
### @1.80cum. per 100 sqm
### 2911 Stone chippings/ screenings 10/ 11.2 mm cum 0.9 1150
### nominal size
### @0.90cum. per 100 sqm
### 2202 Carriage of Stone aggregate below 40 mm cum 2.7 584.88
### nominal size
### Steam coal for heating bitumen @ 2 qunitals
### per tonne of bitumen =
### 2x0.144=0.288q
### 370 Coal (steam) quintal 0.288 440
### 2200 Carriage of steam coal tonne 0.0288 121.29
### Labour for cleaning the road surface, heating
### and spraying bitumen and aggregate :
### (a) For cleaning :
### 28 Mate day 0.08 350.00
### 17 Beldar day 1.4 350.00
### 18 Coolie day 1.4 350.00
### (b) For heating bitumen:
### 17 Beldar day 0.57 350.00
### (c) For screening and spreading premixed
### 30 aggregate :
### Mistry day 0.19 505.17
### 17 Beldar day 5 350.00
### (d) Consolidation Charges
### 16 Chowkidar day 0.27 350.00
###
###
###
###
###
### 1182
###
###
### (at barrier for night watch and for road roller)
### 11 Bhisti day 0.11 350.00
### 3 Hire charges of Diesel Road Roller - 8 to 10 day 0.11 3000
### 1 tonne 800
### Hire charges of Coaltar Boiler 900 to 1400 day 0.13 800
### 23 litres
### Hot Bitumen mixer 0.5 cum i/c hand cart (e) day 0.04 3500
### 364 Misc:
### Wire brush each 0.11 20
### (with thick wire)
### 365 Soft brush each 0.32 20
### 9999 Brooms and gunny bags L.S. 6.76 2
### 9999 Sundries L.S. 9.49 2
### TOTAL
### Add 1 % Water charges on "W"
### TOTAL
### Add GST (multiplying factor 0.1405) on "X"
### TOTAL
### Add 15 % Contractor's profit and overheads on "Y"
### Total
### Add Cess @ 1% on "Z"
### Cost for 100 sqm.
### Cost per Sqm.
### Say
###
### 16.32.2 With paving Asphalt grade VG - 30
### with no solvent
### Details of cost for 100 sqm. Asphalt 60/70
###
### (i) Hot bitumen
@52kg.per
### stonechippings 1.8cum. of 13.2mm nominal
### size chippings.
### (ii) Hot bitumen
@56kg. per
### stonechippings 0.90cum. of 11.2mm nominal
### size chippings.
### Bitumen :52xl.8+56x0.9=144kg. or 0.144 tonne
### MATERIAL
### 7309 Paving Asphalt VG-30 of approved quality tonne 0.144 39570
### 2211 Carriage of Tar bitumen tonne 0.144 106.13
### 2910 Stone chippings/ screenings 12.5/ 13.2 mm cum 1.8 1150
### nominal size
### @1.80cum. per 100sqm.
###
###
###
###
###
### 1183
###
###
### 2911 Stone chippings/ screenings 10/ 11.2 mm cum 0.9 1150
### nominal size
### @0.90cum. per 100sqm
### 2202 Carriage of Stone aggregate below 40 mm cum 2.7 584.88
### nominal size
### Steam coal for heating of bitumen @2 quintals
### per tonne of bitumen
### =2x0.144=0.288q
### 370 Coal (steam) quintal 0.288 440
### 2200 Carriage of steam coal tonne 0.0288 121.29
### Labour for cleaning the road surface, heating
### and spraying bitumen and aggregate :
### (a) For cleaning :
### 28 Mate day 0.08 350.00
### 17 Beldar day 1.4 350.00
### 18 Coolie day 1.4 350.00
### (b) For heating bitumen:
### 17 Beldar day 0.57 350.00
### (c) For screening and spreading premixed
### 30 aggregate :
### Mistry day 0.19 505.17
### 17 Beldar day 5 350.00
### (d) Consolidation Charges
### 16 Chowkidar day 0.27 350.00
### 11 Bhisti day 0.11 350.00
### 3 Hire charges of Diesel Road Roller - 8 to 10 day 0.11 3000
### 1 tonne 800
### Hire charges of Coaltar Boiler 900 to 1400 day 0.13 800
### 23 litres
### Hot Bitumen mixer 0.5 cum i/c hand cart (e) day 0.04 3500
### 364 Misc:
### Wire brush each 0.11 20
### (with thick wire)
### 365 Soft brush each 0.32 20
### 9999 Brooms and gunny bags L.S. 6.76 2
### 9999 Sundries L.S. 9.49 2
### TOTAL
### Add 1 % Water charges on "W"
### TOTAL
### Add GST (multiplying factor 0.1405) on "X"
### TOTAL
### Add 15 % Contractor's profit and overheads on "Y"
### Total
### Add Cess @ 1% on "Z"
###
###
###
###
### 1184
###
###
### Cost for 100 sqm.
### Cost per Sqm.
### Say
###
### 16.32.3 With Refinery Modified Bitumen
### CRMB 55 conforming to IRC: SP: 53
### Details of cost for 100 sqm. Asphalt 80/100
###
### (i) Hot bitumen @52kg.per cum. of stonechippings 1.8cum.
of 13.2mm nominal
### size chippings.
### (ii) Hot bitumen
@56kg. per
### stonechippings 0.90cum. of 11.2mm nominal
### size chippings.
### Modified Bitumen CRMB - 55 (Refinary
### produced) :52xl.8+56x0.9=144kg. or 0.144
### tonne
### MATERIAL
### 7739 Modified Bitumen Refinary produced CRMB - tonne 0.144 29995
### 2211 55
### Carriage of Tar bitumen tonne 0.144 106.13
### Solvent 70gms/kg. for 0.144 t = 10.08kg
### 2914 Solvent kilogra 10.08 25
### 2342 m
### Carriage of solvent/ Diesel. quintal 0.1 10.61
### Stone chippings 13.2mm nominal size @
### 2910 1.80cum. per 100sqm. 1150
### Stone chippings/ screenings 12.5/ 13.2 mm cum 1.8 1150
### nominal size
### @1.80cum. per 100sqm.
### 2911 Stone chippings/ screenings 10/ 11.2 mm cum 0.9 1150
### nominal size
### @0.90cum. per 100sqm
### 2202 Carriage of Stone aggregate below 40 mm cum 2.7 584.88
### nominal size
### Steam coal for heating bitumen @ 2 quintals
### per tonne of bitumen =
### 2x0.144=0.288q
### 370 Coal (steam) quintal 0.288 440
### 2200 Carriage of steam coal tonne 0.0288 121.29
### Labour for cleaning the road surface, heating
### and spraying bitumen and aggregate :
### (a) For cleaning :
### 28 Mate day 0.08 350.00
### 17 Beldar day 1.4 350.00
### 18 Coolie day 1.4 350.00
### (b) For heating bitumen:
### 17 Beldar day 0.57 350.00
###
###
###
###
###
### 1185
###
###
### (c) For screening and spreading premixed
### 30 aggregate :
### Mistry day 0.19 505.17
### 17 Beldar day 5 350.00
### (d) Consolidation Charges
### 16 Chowkidar day 0.27 350.00
### 11 Bhisti day 0.11 350.00
### 3 Hire charges of Diesel Road Roller - 8 to 10 day 0.11 3000
### 1 tonne 800
### Hire charges of Coaltar Boiler 900 to 1400 day 0.13 800
### 23 litres
### Hot Bitumen mixer 0.5 cum i/c hand cart (e) day 0.04 3500
### 364 Misc:
### Wire brush each 0.11 20
### (with thick wire)
### 365 Soft brush each 0.32 20
### 9999 Brooms and gunny bags L.S. 6.76 2
### 9999 Sundries L.S. 9.49 2
### TOTAL
### Add 1 % Water charges on "W"
### TOTAL
### Add GST (multiplying factor 0.1405) on "X"
### TOTAL
### Add 15 % Contractor's profit and overheads on "Y"
### Total
### Add Cess @ 1% on "Z"
### Cost for 100 sqm.
### Cost per Sqm.
### Say
###
### 16.33 2.5 cm premix carpet surfacing with
2.25 cum and 1.12 cum of stone chippings
###
### 16.33.1 With paving Asphalt grade VG - 10
### heated and then mixed with solvent at the
### Details of cost for 100 sqm. Paving Asphalt
###
### 80/100
### (i) Hot bitumen @52kg.per cum. of stone chippings
@2.25cum. of 13.2mm nominal size chippings.
###
###
###
###
###
### 1186
###
###
### (ii) Hot bitumen @56kg. per cum. of aggregate
### @1.12cum. of 11.2mm nominal size.
### Bitumen :52x2.25+56x1.12= 180kg
### MATERIAL
### 2916 Paving Asphalt VG -10 of approved quality tonne 0.18 24000
### 2914 Solvent 0.07x180=12.60kg. 25
### Solvent kilo 12.6 25
### 2211 gram
### Carriage of Tar bitumen tonne 0.18 106.13
### 2342 Carriage of solvent/ Diesel. quintal 0.126 10.61
### 2910 Stone chippings/ screenings 12.5/ 13.2 mm cum 2.25 1150
### nominal size
### @1.80cum. per 100 sqm.
### 2911 Stone chippings/ screenings 10/ 11.2 mm cum 1.12 1150
### nominal size
### @0.90cum. per 100 sqm
### 2202 Carriage of Stone aggregate below 40 mm cum 3.37 584.88
### nominal size 2.25+1.12=3.37 cum
### Steam coal for heating of bitumen @2 quintals
### per tonne of bitumen
### =2x0.18=0.36q
### 370 Coal (steam) quintal 0.36 440
### 2200 Carriage of steam coal tonne 0.036 121.29
### Labour for cleaning the road surface, heating
### and spraying bitumen and aggregate :
### (a) For cleaning :
### 28 Mate day 0.08 350.00
### 17 Beldar day 1.4 350.00
### 18 Coolie day 1.4 350.00
### (b) For heating bitumen:
### 17 Beldar day 0.71 350.00
### (c) For screening and spreading premixed
### 30 aggregate :
### Mistry day 0.19 505.17
### 17 Beldar day 6.25 350.00
### (d) Consolidation Charges
### 16 Chowkidar day 0.27 350.00
### 11 Bhisti day 0.11 350.00
### 3 Hire charges of Diesel Road Roller - 8 to 10 day 0.11 3000
### 1 tonne 800
### Hire charges of Coaltar Boiler 900 to 1400 day 0.15 800
### 23 litres
### Hot Bitumen mixer 0.5 cum i/c hand cart (e) day 0.04 3500
### 364 Misc:
### Wire brush each 0.11 20
###
###
###
###
###
### 1187
###
###
### (with thick wire)
### 365 Soft brush each 0.32 20
### 9999 Brooms and gunny bags L.S. 6.76 2
### 9999 Sundries L.S. 9.49 2
### TOTAL
### Add 1 % Water charges on "W"
### TOTAL
### Add GST (multiplying factor 0.1405) on "X"
### TOTAL
### Add 15 % Contractor's profit and overheads on "Y"
### Total
### Add Cess @ 1% on "Z"
### Cost for 100 sqm.
### Cost per Sqm.
### Say
###
###
### 16.33.2 With paving Asphalt grade VG - 30
### with no solvent
### Details of cost for 100 sqm. Paving Asphalt
###
### 60/70
### (i) Hot bitumen @52kg.per cum. of stonechippings
@2.25cum. of 13.2mm nominal
### size
### (ii) Hot bitumen @56kg. per cum. of
stoneaggregate@1.12cum. of 11.2mm nominal size size
### 0.180 tonne
### MATERIAL
###
### 7309 Paving Asphalt VG-30 of approved quality tonne 0.18 39570
### 2211 Carriage of Tar bitumen tonne 0.18 106.13
### 2910 Stone chippings / screenings 12.5/ 13.2 mm cum 2.25 1150
### nominal size
### @2.25cum. per 100sqm
### 2911 Stone chippings / screenings 10/ 11.2 mm cum 1.12 1150
### nominal size
### @1.12cum. per 100sqm
### 2202 Carriage of Stone aggregate below 40 mm cum 3.37 584.88
### nominal size
### 2.25+1.12=3.37 cum.
### 370 Coal (steam) quintal 0.36 440
### 2200 Carriage of steam coal tonne 0.036 121.29
### Labour for cleaning the road surface, heating
### and spraying bitumen and aggregate :
### (a) For cleaning :
### 28 Mate day 0.08 350.00
###
###
###
###
### 1188
###
###
### 17 Beldar day 1.4 350.00
### 18 Coolie day 1.4 350.00
### (b) For heating bitumen:
### 17 Beldar day 0.71 350.00
### (c) For cleaning, mixing and spreading pre-mix
### 30 aggregate :
### Mistry day 0.19 505.17
### 17 Beldar day 6.25 350.00
### 1.05x0.18)/0.267 = 0.71 Nos.
### (d) Consolidation Charges
### 16 Chowkidar day 0.27 350.00
### 11 Bhisti day 0.11 350.00
### 3 Hire charges of Diesel Road Roller - 8 to 10 day 0.11 3000
### 1 tonne 800
### Hire charges of Coaltar Boiler 900 to 1400 day 0.15 800
### 23 litres
### Hot Bitumen mixer 0.5 cum i/c hand cart (e) day 0.04 3500
### 364 Misc:
### Wire brush each 0.11 20
### (with thick wire)
### 365 Soft brush each 0.32 20
### 9999 Brooms and gunny bags L.S. 6.76 2
### 9999 Sundries L.S. 9.49 2
### TOTAL
### Add 1 % Water charges on "W"
### TOTAL
### Add GST (multiplying factor 0.1405) on "X"
### TOTAL
### Add 15 % Contractor's profit and overheads on "Y"
### Total
### Add Cess @ 1% on "Z"
### Cost for 100 sqm.
### Cost per Sqm.
### Say
###
### 16.33.3 With Refinery Modified Bitumen
### CRMB 55 conforming to IRC: SP: 53
### Details of cost for 100 sqm.
###
### MATERIAL
###
### Paving Asphalt 80/100
###
### (i) Hot bitumen @52kg.per cum. of stonechippings
@2.25cum. of 13.2mm nominal size chippings.
###
###
###
###
### 1189
###
###
### (ii) Hot bitumen @56kg. per cum.
### ofaggregate @1.12cum. of 11.2mm nominal
### size.
### 52x2.25+56x1.12=180kg
### 7739 Modified Bitumen Refinary produced tonne 0.18 29995
### CRMB - 55
### Solvent 0.07x180=12.60kg
### 2914 Solvent kilogra 12.6 25
### 2211 Carriage of Tar bitumen tonne 0.18 106.13
### 2342 quintal 0.126
### 2910 Stone chippings/ screenings 12.5/ 13.2 mm cum 2.25 1150
### nominal size
### @2.25 cum. per 100sqm
### 2911 Stone chippings/ screenings 10/ 11.2 mm cum 1.12 1150
### nominal size
### @1.12 cum. per 100sqm
### 2202 Carriage of Stone aggregate below 40 mm cum 3.37 584.88
### nominal size
### 2.25+1.12=3.37 cum.+
### Steam coal for heating of bitumen @2 quintals
### per tonne of bitumen
### =2x0.18=0.36q
### 370 Coal (steam) quintal 0.36 440
### 2200 Carriage of steam coal tonne 0.036 121.29
### Labour for cleaning the road surface, heating
### and spraying bitumen and aggregate :
### (a) For cleaning :
### 28 Mate day 0.08 350.00
### 17 Beldar day 1.4 350.00
### 18 Coolie day 1.4 350.00
### (b) For heating bitumen:
### 17 Beldar day 0.71 350.00
### (c) For screening and spreading premixed
### 30 aggregate :
### Mistry day 0.19 505.17
### 17 Beldar day 6.25 350.00
### (d) Consolidation Charges
### 16 Chowkidar day 0.27 350.00
### 11 Bhisti day 0.11 350.00
### 3 Hire charges of Diesel Road Roller - 8 to 10 day 0.11 3000
### 1 tonne 800
### Hire charges of Coaltar Boiler 900 to 1400 day 0.15 800
### 23 litres
### Hot Bitumen mixer 0.5 cum i/c hand cart (e) day 0.04 3500
### 364 Misc:
### Wire brush each 0.11 20
###
### (with thick wire)
###
###
###
###
### 1190
###
###
### 365 Soft brush each 0.32 20
### 9999 Brooms and gunny bags L.S. 6.76 2
### 9999 Sundries L.S. 9.49 2
### TOTAL
### Add 1 % Water charges on "W"
### TOTAL
### Add GST (multiplying factor 0.1405) on "X"
### TOTAL
### Add 15 % Contractor's profit and overheads on "Y"
### Total
### Add Cess @ 1% on "Z"
### Cost for 100 sqm.
### Cost per Sqm.
### Say
###
### 16.34 2 cm premix carpet surfacing with
### 2.4 cum of stone chippings 11.2 mm
### Details of cost for 100 sqm.
###
### MATERIAL
### Bitumen emulsion M.S. @ 96kg per cum. of
### aggregate
### 96x2.4=230kg =0.230t
### 7742 Bitumen emulsion medium setting (M.S.) tonne 0.23 27909
### 2211 confirming to IS : 8887-1995
### Carriage of Tar bitumen tonne 0.23 106.13
### 2910 Stone chippings/ screenings 10/ 11.2 mm cum 2.4 1150
### nominal size
### @ 2.4cum. per 100 sqm
### 2202 Carriage of Stone aggregate below 40 mm cum 2.4 584.88
### nominal size
### LABOUR
### (a) For mixing and spreading premix aggregate
### 30 :
### Mistry day 0.19 505.17
### 17 Beldar day 3.54 350.00
### (b) Consolidation Charges
### 16 Chowkidar day 0.27 350.00
### 11 Bhisti day 0.11 350.00
### 3 Hire charges of Diesel Road Roller - 8 to 10 day 0.11 3000
### 23 tonne
### Hot Bitumen mixer 0.5 cum i/c hand cart day 0.04 3500
### 9999 Sundries L.S. 9.49 2
###
###
###
###
### 1191
###
###
### Code Description Unit Quantity Rate Amount
### TOTAL
### Add 1 % Water charges on "W" 112.95
### TOTAL
### Add GST (multiplying factor 0.1405) on "X" 1602.85
### TOTAL
### Add 15 % Contractor's profit and overheads on "Y" 1951.66
### Total
### Add Cess @ 1% on "Z" 149.63
### Cost for 100 sqm. 15112.36
### Cost per Sqm. 151.12
### Say 151.1
###
### 16.35 2.5 cm premix carpet surfacing with
### 3 cum of stone chippings 10 mm nominal
### Details of cost for 100 sqm.
### MATERIAL
### Bitumen emulsion M.S. @ 96kg per cum. of
### aggregate
### 96x3 = 288 kg = 0.288 t
### 7742 Bitumen emulsion medium setting (M.S.) tonne 0.288 27909
### 2211 confirming to IS : 8887-1995
### Carriage of Tar bitumen tonne 0.288 106.13
### 2910 Stone chippings/ screenings 10/ 11.2 mm cum 3 1150
### nominal size
### @ 3.00 cum. per 100 sqm
### 2202 Carriage of Stone aggregate below 40 mm cum 3 584.88
### nominal size
### LABOUR
### (a) For mixing and spreading premix aggregate
### 30 :
### Mistry day 0.19 505.17
### 17 Beldar day 4.1 350.00
### (b) Consolidation Charges
### 16 Chowkidar day 0.27 350.00
### 11 Bhisti day 0.11 350.00
### 3 Hire charges of Diesel Road Roller - 8 to 10 day 0.11 3000
### 9999 tonne
### Sundries L.S. 9.49 2
### TOTAL
### Add 1 % Water charges on "W"
### TOTAL
###
###
###
###
### 1192
###
###
### Code Description Unit Quantity Rate Amount
### Add GST (multiplying factor 0.1405) on "X" 1946.01
### TOTAL
### Add 15 % Contractor's profit and overheads on "Y" 2369.49
### Total
### Add Cess @ 1% on "Z" 181.66
### Cost for 100 sqm. 18347.79
### Cost per Sqm. 183.48
### Say 183.5
###
### 16.36 Providing and laying Bitumen
### Penetration Macadam with hard stone
### 16.36.1 For 50mm compacted thickness
### using coarse aggregate of size 50-20 mm
### Details of cost for 370 sqm.
### MATERIAL
### Taking stone aggregate 40mm = 45%
### 20mm = 44%
### 11.2mm = 8%
### Stone dust = 3%
### 293 Stone Aggregate (Single size) : 40 mm nominal cum 9.99 730
### 295 size cum 9.77 790
### Stone Aggregate (Single size) : 20 mm nominal
### 297 size cum 1.78 810
### Stone Aggregate (Single size) : 10 mm nominal
### 1159 size
### Stone dust cum 0.6 1100
### 295 Stone Aggregate (Single size) : 20 mm nominal cum 2.33 790
### 296 size 800
### Stone Aggregate (Single size) : 12.5 mm cum 2.66 1350
### 1159 nominal size
### Stone dust cum 0.56 1100
### 2206 Carriage of Stone aggregate 40 mm nominal cum 9.99 115.36
### size and above
### 2202 Carriage of Stone aggregate below 40 mm cum 12.1 584.88
### 2202 nominal size i.e. 20mm
### Carriage of Stone aggregate below 40 mm cum 4.44 106.13
### 2267 nominal size 106.13
### Carriage of Stone dust cum 1.16 106.13
###
###
###
### 1193
###
###
### 2916 Paving Asphalt VG -10 of approved quality @ tonne 1.85 24000
### 2211 50kg/10 sqm.
### Carriage of Tar bitumen (B) Labour: tonne 1.85 106.13
### 17 Beldar day 16.67 350.00
### for spreading stone metal
### 17 Beldar for hand packing day 5.33 350.00
### 17 Beldar dry rolling day 2.67 350.00
### 17 Beldar day 1.33 350.00
### Bajri spreader
### 36 Sprayer (for bitumen, tar etc.) day 0.67 350.00
### 17 Beldar day 1.33 350.00
### for spreading key aggregate
### 17 Beldar day 6.67 350.00
### for spraying bitumen
### 17 Beldar of power roller day 0.67 350.00
### 28 Mate day 1.77 350.00
### (C) Machinery :
### 1 Hire charges of Coaltar Boiler 900 to 1400 day 0.45 800
### 3 litres 3000
### Hire charges of Diesel Road Roller - 8 to 10 day 0.61 3000
### 9999 tonne
### Misc. items as spray nozzle, joint paper, L.S. 351 2
### coconut oil, country soap etc.
### TOTAL
### Add 1 % Water charges on "W"
### TOTAL
### Add GST (multiplying factor 0.1405) on "X"
### TOTAL
### Add 15 % Contractor's profit and overheads on "Y"
### Total
### Add Cess @ 1% on "Z"
### Cost for 370 Sqm.
### Cost per sqm.
### Say
###
### 16.36.2 For 75 mm compacted thickness in
### two layers using stone aggregate of size
### sqm.
###
### Details of cost for 300 sqm.
###
### MATERIAL
###
### Taking output as 300 sqm. for single layer.
###
### Coarse agg. = 300/10x0.90 = 27 cum.
###
###
###
###
### 1194
###
###
### Key agg = 300/10x0.18 = 5.4 cum.
### Bitumen = 300/10x68 = 2.04 t.
### 2206 Carriage of Stone aggregate 40 mm nominal cum 8.1 115.36
### size and above
### 292 Stone Aggregate (Single size) : 50 mm nominal cum 8.1 730
### 295 size cum 14.58 790
### Stone Aggregate (Single size) : 20 mm nominal
### 297 size cum 4.32 810
### Stone Aggregate (Single size) : 10 mm nominal
### 294 size cum 2.05 760
### Stone Aggregate (Single size) : 25 mm nominal
### 296 size 800
### Stone Aggregate (Single size) : 12.5 mm cum 2.57 1350
### 297 nominal size cum 0.81 810
### Stone Aggregate (Single size) : 10 mm nominal
### 2916 size 24000
### Paving Asphalt VG -10 of approved quality tonne 2.04 24000
### 2202 Carriage of Stone aggregate below 40 mm cum 24.33 584.88
### 2211 nominal size
### Carriage of Tar bitumen tonne 2.04 106.13
### LABOUR
### 17 Beldar day 25 350.00
### for spreading stone metal
### 17 Beldar for hand packing day 8 350.00
### 17 Beldar dry rolling day 4 350.00
### 17 Beldar day 2 350.00
### /Bajri spreader
### 36 Sprayer (for bitumen, tar etc.) day 1 350.00
### 17 Beldar day 2 350.00
### for spreading key aggregate
### 17 Beldar day 10 350.00
### for spraying bitumen
### 17 Beldar road roller day 1 350.00
### 28 Mate day 2.65 350.00
### MACHINERY
### 1 Hire charges of Coaltar Boiler 900 to day 0.5 800
### 1400 litres
### 3 Hire charges of Diesel Road Roller - 8 to day 0.75 3000
### 10 tonne
### 9999 Misc. items as spray nozzle, joint paper, L.S. 429 2
### coconut oil, country soap etc.
### TOTAL
### Add 1 % Water charges on "W"
### TOTAL
### Add GST (multiplying factor 0.1405) on "X"
### TOTAL
###
###
###
###
###
### 1195
###
###
### Code Description Unit Quantity Rate Amount
### Add 15 % Contractor's profit and overheads on "Y" 19870.49
### Total
### Add Cess @ 1% on "Z" 1523.4
### Cost for 300 Sqm. 153863.83
### Cost per sqm. 512.88
### Say 512.9
###
### 16.37 Providing and laying bitumen mastic
### wearing course (as per specifications) with
### 16.37.1 25 mm thick
### Details of cost for surface area of 17.40 sqm
### for single layer of 25 mm finished thickness.
### MATERIAL
### Taking wearing coat as 1 tonne and density as
### 2.3 gm/c.c Volume of bitumen mastic =
### 1000/2300= 0.435 cum surface area =
### 0.435/0.025 = 17.4 sqm.
### (i) Bitumen of penetration 85/25 @ 10.2% by
### 313 weight of mix 53000
### Blown type petroleum bitumen of penetration tonne 0.102 34000
### 85/25 of approved quality
### 2211 Carriage of Tar bitumen tonne 0.102 106.13
### (ii) Weight of coarse aggregate @ 40% (1000 -
### 150) x 40/100 = 340 kg. Stone aggregate :
### 340/43.38x0.0283 = 0.222 cum.
### 295 Stone Aggregate (Single size) : 20 mm nominal cum 0.02 790
### 296 size 800
### Stone Aggregate (Single size) : 12.5 mm cum 0.202 1350
### nominal size
### (iii) Weight of fine aggregate @ 15% 850
### x15/100 = 127.5 kg., volume of fine aggregate:
### 127.5/43.103x0.0283 =0.083 cum
### 1159 Stone dust cum 0.083 1100
### (iv) Weight of lime stone dust @ 45% (850340-
### 127.5) = 382.50 kg., Volume of lime stone dust
### 784 382.50/2200 =0.174 cum.
### Marble dust/ powder cum 0.174 1130
###
### (v) Precoated stone chipping for surface finish:
Volume of chips @ 0.005 cum/10
###
### sqm=17.4x0.005/10 = 0.0087 cum say 0.009 cum
###
###
###
###
### 1196
###
###
### 297 Stone Aggregate (Single size) : 10 mm nominal cum 0.009 810
### size
### Bitumen for precoated stone chipping @
### 2% =0.009x1600x2/100= 0.288 say 0.30 kg.
### 313 Blown type petroleum bitumen of penetration tonne 0.0003 53000
### 2211 85/25 of approved quality
### Carriage of Tar bitumen tonne 0.0003 106.13
### 2202 Carriage of Stone aggregate below 40 mm cum 0.231 584.88
### nominal size
### (0.222 + 0.009) =0.231 cum.
### 2267 Carriage of Stone dust cum 0.083 106.13
### 2208 Carriage of Lime cum 0.174 106.13
### LABOUR
### 37 Skilled Beldar (for floor rubbing etc.) day 1.5 350.00
### 30 Mistry day 0.5 505.17
### 36 Sprayer (for bitumen, tar etc.) day 3.5 350.00
### 37 Skilled Beldar (for floor rubbing etc.) day 0.25 350.00
### 28 Mate day 0.5 350.00
### 16 Mastic Cooker day 0.5 750
### 9999 sundries (Sealing of joints, placing angles, L.S. 153.27 2
### wastage materials)
### Total
### Add 1 % Water charges on "W"
### TOTAL
### Add GST (multiplying factor 0.1405) on "X"
### TOTAL
### Add 15 % Contractor's profit and overheads on "Y"
### Total
### Add Cess @ 1% on "Z"
### Cost for 17.40 sqm
### Cost per sqm
### Say
### 16.37.2 40 mm thick
### Details of cost for surface area of 10.875sqm
### for single layer of 25 mm finished thickness.
### MATERIAL
### Taking wearing coat as 1 tonne and density as
### 2.3 gm/c.c Volume of bitumen mastic =
### 1000/2300= 0.435 cum surface area =
### 313 0.435/0.040 = 10.875 sqm. 53000
### Blown type petroleum bitumen of penetration tonne 0.102 34000
### 2211 85/25 of approved quality
### Carriage of Tar bitumen tonne 0.102 106.13
###
###
###
###
###
###
###
### 1197
###
###
### (ii) Weight of coarse aggregate @ 40% (1000 -
### 150) x 40/100 = 340 kg. Stone aggregate :
### 340/43.38x0.0283 = 0.222 cum.
### 295 Stone Aggregate (Single size) : 20 mm nominal cum 0.02 790
### 296 size 800
### Stone Aggregate (Single size) : 12.5 mm cum 0.202 1350
### nominal size
### (iii) Weight of fine aggregate @ 15% 850
### x15/100 = 127.5 kg., volume of fine
### aggregate: 127.5/43.103x0.0283 =0.083 cum
### 1159 Stone dust cum 0.083 1100
### (iv) Weight of lime stone dust @ 45% (850-340-
### 127.5) = 382.50 kg., Volume of lime stone dust
### 382.50/2200 =0.174 cum.
### 784 Marble dust/ powder cum 0.174 1130
### (v) Precoated stone chipping for surface finish:
### Volume of chips @ 0.005 cum/10
### sqm=17.4x0.005/10 = 0.0087 cum say
### 0.009 cum
### 297 Stone Aggregate (Single size) : 10 mm nominal cum 0.009 810
### size
### Bitumen for precoated stone chipping @ 2%
### =0.009x1600x2/100= 0.288 say 0.30 kg.
### 313 Blown type petroleum bitumen of penetration tonne 0.0003 53000
### 2211 85/25 of approved quality
### Carriage of Tar bitumen tonne 0.0003 106.13
### 2202 Carriage of Stone aggregate below 40 mm cum 0.231 584.88
### nominal size
### (0.222 + 0.009) =0.231 cum
### 2267 Carriage of Stone dust cum 0.083 106.13
### 2208 Carriage of Lime for mastic cooker (Taking cum 0.174 106.13
### capacity of
### cooker as one tonne)
### LABOUR
### 37 Skilled Beldar (for floor rubbing etc.) day 1.5 350.00
### 30 Mistry day 0.5 505.17
### 36 Sprayer (for bitumen, tar etc.) day 3.5 350.00
### 37 Skilled Beldar (for floor rubbing etc.) day 0.25 350.00
### 28 Mate day 0.5 350.00
### 16 Mastic Cooker day 0.5 750
### 9999 sundries (Sealing of joints, placing angles, L.S. 153.27 2
### wastage materials)
###
### Add 1 % Water charges on "W"
### TOTAL
### Add GST (multiplying factor 0.1405) on "X"
### TOTAL
###
###
###
###
###
### 1198
###
###
### Add 15 % Contractor's profit and overheads on "Y"
### Total
### Add Cess @ 1% on "Z"
### Cost for 10.875 sqm
### Cost per sqm
### Say
###
### 16.38 2.5 cm thick bitumastic sheet with
### hot bitumen of approved quality, using
### 16.38.1 With paving Asphalt grade VG - 10 heated
### and then mixed with solvent at the rate of
### Details of cost for 100sqm.
###
### 80/100 bitumen @56kg. per cum. of aggregate
###
### and 128kg. per cum. of sand: 56x1.65=92.4kg. = 0.092t +

###
### 128x1.65 = 211.2kg = 0.211t
### MATERIAL
### 2916 Paving Asphalt VG -10 of approved quality tonne 0.303 24000
### 2914 Solvent 0.070 kg. x 303 kg. = 21.21kg 25
### Solvent kilogra 21.21 25
### 2211 m
### Carriage of Tar bitumen tonne 0.303 106.13
### 2342 Carriage of solvent/ Diesel. quintal 0.212 10.61
### 2910 Stone chippings/ screenings 12.5/ 13.2 mm cum 0.99 1150
### 2911 nominal size 1150
### Stone chippings/ screenings 10/ 11.2 mm cum 0.66 1150
### 2202 nominal size 584.88
### Carriage of Stone aggregate below 40 mm cum 1.65 106.13
### 370 nominal size
### Coal (steam) quintal 0.606 440
### 2200 Carriage of steam coal tonne 0.0606 121.29
### 982 Coarse sand cum 1.65 800
### 2203 Carriage of Coarse sand cum 1.65 584.88
### Labour for cleaning road surface, heating
### bitumen mixing and spreading aggregate :
### (a) For cleaning :
### 28 Mate day 0.16 350.00
### 17 Beldar day 1.4 350.00
### 18 Coolie day 1.4 350.00
### (b) For heating bitumen :
### 17 Beldar day 1.19 350.00
###
###
###
###
### 1199
###
###
### (c) For cleaning, mixing and spreading pre-mix
### 30 aggregate :
### Mistry day 0.24 505.17
### 17 Beldar day 6.12 350.00
### (d) Consolidation charges :
### 16 Chowkidar day 0.34 350.00
### (at barriers for night watch and for road roller)
### 11 Bhisti day 0.13 350.00
### 3 Hire charges of Diesel Road Roller - 8 to 10 day 0.13 3000
### 1 tonne 800
### Hire charges of Coaltar Boiler 900 to 1400 day 0.21 800
### 23 litres
### Hot Bitumen mixer 0.5 cum i/c hand cart (e) day 0.05 3500
### Misc :
### Wire brush (with thick wire)
### 364 Wire brush each 0.13 20
### 365 Soft brush each 0.4 20
### 9999 Brooms and gunny bags L.S. 7.15 2
### 9999 Sundries L.S. 8.97 2
### TOTAL
### Add 1 % Water charges on "W"
### TOTAL
### Add GST (multiplying factor 0.1405) on "X"
### TOTAL
### Add 15 % Contractor's profit and overheads on "Y"
### Total
### Add Cess @ 1% on "Z"
### Cost for 100 sqm.
### Cost per sqm.
### Say
###
### 16.38.2 With paving Asphalt grade VG - 30
###
### Details of cost for 100sqm. 60/70 bitumen
### @56kg. per cum. of aggregate and 128kg. per
### cum. of sand:
### 56x1.65=92.4kg. = 0.092t +
### 128x1.65 = 211.2kg = 0.211t
### Total= 0.303t
### MATERIAL
### 7309 Paving Asphalt VG-30 of approved quality tonne 0.303 39570
### 2211 Carriage of Tar bitumen tonne 0.303 106.13
### 2910 Stone chippings/ screenings 12.5/ 13.2 mm cum 0.99 1150
### nominal size
###
###
###
###
### 1200
###
###
### 2911 Stone chippings/ screenings 10/ 11.2 mm cum 0.66 1150
### 2202 nominal size 584.88
### Carriage of Stone aggregate below 40 mm cum 1.65 106.13
### nominal size
### Steam coal for heating bitumen @ 2 quintals
### per tonne of bitumen =
### 2x0.303=0.606q
### 370 Coal (steam) quintal 0.606 440
### 2200 Carriage of steam coal tonne 0.0606 121.29
### 982 Coarse sand cum 1.65 800
### 2203 Carriage of Coarse sand cum 1.65 584.88
### Labour for cleaning road surface, heating
### bitumen mixing and spreading aggregate :
### (a) For cleaning :
### 28 Mate day 0.16 350.00
### 17 Beldar day 1.4 350.00
### 18 Coolie day 1.4 350.00
### (b) For heating bitumen :
### 17 Beldar day 1.19 350.00
### (c) For cleaning, mixing and spreading pre-mix
### 30 aggregate :
### Mistry day 0.24 505.17
### 17 Beldar day 6.12 350.00
### (d) Consolidation charges :
### 16 Chowkidar day 0.34 350.00
### (at barriers for night watch and for road roller)
### 11 Bhisti day 0.13 350.00
### 3 Hire charges of Diesel Road Roller - 8 to 10 day 0.13 3000
### 1 tonne 800
### Hire charges of Coaltar Boiler 900 to 1400 day 0.21 800
### 23 litres
### Hot Bitumen mixer 0.5 cum i/c hand cart (e) day 0.05 3500
### 364 Misc :
### Wire brush each 0.13 20
### (with thick wire)
### 365 Soft brush each 0.4 20
### 9999 Brooms and gunny bags L.S. 7.15 2
### 9999 Sundries L.S. 8.97 2
### TOTAL
### Add 1 % Water charges on "W"
### TOTAL
### Add GST (multiplying factor 0.1405) on "X"
### TOTAL
### Add 15 % Contractor's profit and overheads on "Y"
### Total
###
###
###
###
###
### 1201
###
###
### Add Cess @ 1% on "Z" 279.6
###
### Cost for 100 sqm. 28239.69
### Cost per sqm. 282.4
### Say
###
### 16.38.3 With Refinery Modified Bitumen
### CRMB 55 conforming to IRC: SP : 53
### Details of cost for 100sqm.
### MATERIAL
### 7739 Modified Bitumen Refinary produced tonne 0.303 29995
### CRMB - 55
### @56kg. per cum. of aggregate and 128kg. per
### cum. of sand:
### 56x1.65=92.4kg. = 0.092t +
### 128x1.65 = 211.2kg = 0.211t
### Total = 0.303 t
### 2914 Solvent kilogra 21.21 25
### 0.070 kg. x 303 kg. = 21.21kg m
###
### 2211 Carriage of Tar bitumen tonne 0.303 106.13
### 2342 Carriage of solvent/ Diesel. quintal 0.212 10.61
### 2910 Stone chippings/ screenings 12.5/ 13.2 mm cum 0.99 1150
### 2911 nominal size 1150
### Stone chippings/ screenings 10/ 11.2 mm cum 0.66 1150
### 2202 nominal size 584.88
### Carriage of Stone aggregate below 40 mm cum 1.65 106.13
### 370 nominal size
### Coal (steam) quintal 0.606 440
### 2200 Carriage of steam coal tonne 0.0606 121.29
### 982 Coarse sand cum 1.65 800
### 2203 Carriage of Coarse sand cum 1.65 584.88
### Labour for cleaning road surface, heating
### bitumen mixing and spreading aggregate :
### (a) For cleaning :
### 28 Mate day 0.16 350.00
### 17 Beldar day 1.4 350.00
### 18 Coolie day 1.4 350.00
### (b) For heating bitumen :
### 17 Beldar day 1.19 350.00
### (c) For cleaning, mixing and spreading pre-mix
### 30 aggregate :
### Mistry day 0.24 505.17
### 17 Beldar day 6.12 350.00
### (d) Consolidation charges :
### 16 Chowkidar day 0.34 350.00
### 11 Bhisti day 0.13 350.00
###
###
###
### 1202
###
###
### 3 Hire charges of Diesel Road Roller - 8 to 10 day 0.13 3000
### 1 tonne 800
### Hire charges of Coaltar Boiler 900 to 1400 day 0.21 800
### 23 litres
### Hot Bitumen mixer 0.5 cum i/c hand cart (e) day 0.05 3500
### 364 Misc :
### Wire brush each 0.13 20
### (with thick wire)
### 365 Soft brush each 0.4 20
### 9999 Brooms and gunny bags L.S. 7.15 2
### 9999 Sundries L.S. 8.97 2
### TOTAL
### Add 1 % Water charges on "W"
### TOTAL
### Add GST (multiplying factor 0.1405) on "X"
### TOTAL
### Add 15 % Contractor's profit and overheads on "Y"
### Total
### Add Cess @ 1% on "Z"
### Cost for 100 sqm.
### Cost per sqm.
### Say
###
### 16.39 4 cm thick bitumastic sheet with hot
### bitumen of approved quality, using stone
### 16.39.1 With paving Asphalt grade VG - 10
### heated and then mixed with solvent at the
### Details of cost for 100sqm.
###
### MATERIAL
### 2916 Paving Asphalt VG -10 of approved quality tonne 0.479 24000
### @56kg. per cum. of aggregate and 128kg. per
### cum. of sand:
### 56x2.60=145.6kg. = 0.146t +
### 128x2.60 = 332.8kg = 0.333t
### Total = 0.479 t
### 2914 Solvent kilo 33.53 25
### 0.70kg.x479=33.53kg gram
###
###
###
###
### 1203
###
###
### 2342 Carriage of solvent/ Diesel. quintal 0.335 10.61
### 2211 Carriage of Tar bitumen tonne 0.479 106.13
### 2910 Stone chippings/ screenings 12.5/ 13.2 mm cum 1.56 1150
### 2911 nominal size 1150
### Stone chippings/ screenings 10/ 11.2 mm cum 1.04 1150
### 2202 nominal size 584.88
### Carriage of Stone aggregate below 40 mm cum 2.6 106.13
### 982 nominal size
### Coarse sand cum 2.6 1350
### 2203 Carriage of Coarse sand cum 2.6 584.88
### Steam coal for heating bitumen @ 2 qunitals
### 370 per tonne of bitumen = 2x0.479=0.958q
### Coal (steam) quintal 0.958 440
### 2200 Carriage of steam coal tonne 0.0958 121.29
### Labour for cleaning road surface, heating
### bitumen mixing and spreading aggregate :
### (a) For cleaning :
### 28 Mate day 0.16 350.00
### 17 Beldar day 1.4 350.00
### 18 Coolie day 1.4 350.00
### (b) For heating bitumen :
### 17 Beldar day 1.88 350.00
### (c) For cleaning, mixing and spreading pre-mix
### 30 aggregate :
### Mistry day 0.31 505.17
### 17 Beldar day 9.46 350.00
### (d) Consolidation charges :
### 16 Chowkidar day 0.45 350.00
### 11 Bhisti day 0.18 350.00
### 3 Hire charges of Diesel Road Roller - 8 to 10 day 0.18 3000
### 1 tonne 800
### Hire charges of Coaltar Boiler 900 to 1400 day 0.3 800
### 23 litres
### Hot Bitumen mixer 0.5 cum i/c hand cart (e) day 0.03 3500
### 364 Misc :
### Wire brush each 0.09 20
### (with thick wire)
### 365 Soft brush each 0.27 20
### 9999 Brooms and gunny bags L.S. 5.33 2
### 9999 Sundries L.S. 16.12 2
###
###
###
###
### 1204
###
###
### Code Description Unit Quantity Rate Amount
### TOTAL
### Add 1 % Water charges on "W" 257.46
### TOTAL
### Add GST (multiplying factor 0.1405) on "X" 3653.53
### TOTAL
### Add 15 % Contractor's profit and overheads on "Y" 4448.6
### Total
### Add Cess @ 1% on "Z" 341.06
### Cost for 100 sqm. 34446.96
### Cost per sqm. 344.47
### Say 344.45
###
### 16.39.2 With paving asphalt grade VG - 30
### with no solvent
### Details of cost for 100sqm.
### MATERIAL
### 7309 Paving Asphalt VG-30 of approved quality tonne 0.479 39570
### @56kg. per cum. of aggregate and 128kg. per
### cum. of sand:
### 56x2.60=145.6kg. = 0.146t +
### 128x2.60 = 332.8kg = 0.333t
### Total = 0.479 t
### 2211 Carriage of Tar bitumen tonne 0.479 106.13
### 2910 Stone chippings/ screenings 12.5/ 13.2 mm cum 1.56 1150
### 2911 nominal size 1150
### Stone chippings/ screenings 10/ 11.2 mm cum 1.04 1150
### 2202 nominal size 584.88
### Carriage of Stone aggregate below 40 mm cum 2.6 106.13
### 982 nominal size
### Coarse sand cum 2.6 1350
### 2203 Carriage of Coarse sand cum 2.6 584.88
### Steam coal for heating bitumen @ 2 qunitals
### 370 per tonne of bitumen =2x0.479=0.958 qtl
### Coal (steam) quintal 0.958 440
### 2200 Carriage of steam coal tonne 0.0958 121.29
### Labour for cleaning road surface, heating
### bitumen mixing and spreading aggregate :
### (a) For cleaning :
### 28 Mate day 0.16 350.00
### 17 Beldar day 1.4 350.00
### 18 Coolie day 1.4 350.00
### (b) For heating bitumen :
### 17 Beldar day 1.88 350.00
###
###
###
###
### 1205
###
###
### (c) For cleaning, mixing and spreading pre-mix
### 30 aggregate :
### Mistry day 0.31 505.17
### 17 Beldar day 9.46 350.00
### (d) Consolidation charges :
### 16 Chowkidar day 0.45 350.00
### 11 Bhisti day 0.18 350.00
### 3 Hire charges of Diesel Road Roller - 8 to 10 day 0.18 3000
### 1 tonne 800
### Hire charges of Coaltar Boiler 900 to 1400 day 0.3 800
### 23 litres
### Hot Bitumen mixer 0.5 cum i/c hand cart (e) day 0.03 3500
### 364 Brushes etc. for cleaning :-
### Wire brush each 0.09 20
### (with thick wire)
### 365 Soft brush each 0.27 20
### 9999 Brooms and gunny bags L.S. 5.33 2
### 9999 Sundries L.S. 16.12 2
### TOTAL
### Add 1 % Water charges on "W"
### TOTAL
### Add GST (multiplying factor 0.1405) on "X"
### TOTAL
### Add 15 % Contractor's profit and overheads on "Y"
### Total
### Add Cess @ 1% on "Z"
### Cost for 100 sqm.
### Cost per sqm.
### Say
###
### 16.39.3 With Refinery Modified Bitumen
### CRMB 55 conforming to IRC: SP : 53
### Details of cost for 100sqm.
###
### MATERIAL
###
### 7739 Modified Bitumen Refinary produced CRMB - 55 tonne 0.479 29995
###
### @56kg. per cum. of aggregate and 128kg. per cum. of
sand:
###
### 56x2.60=145.6kg. = 0.146t + 128x2.60 = 332.8kg =
0.333t Total = 0.479 tonne
### 2914 Solvent kilogra 33.53 25
### 0.70kg.x479=33.53kg. m
###
### 2342 Carriage of solvent/ Diesel. quintal 0.335 10.61
### 2211 Carriage of Tar bitumen tonne 0.479 106.13
### 2910 Stone chippings/ screenings 12.5/ 13.2 mm cum 1.56 1150
### 2911 nominal size 1150
### Stone chippings/ screenings 10/ 11.2 mm cum 1.04 1150
### 2202 nominal size 584.88
### Carriage of Stone aggregate below 40 mm cum 2.6 106.13
### 982 nominal size
### Coarse sand cum 2.6 1350
### 2203 Carriage of Coarse sand cum 2.6 584.88
### Steam coal for heating bitumen @ 2 qunitals
### 370 per tonne of bitumen = 2x0.479=0.958q
### Coal (steam) quintal 0.958 440
### 2200 Carriage of steam coal tonne 0.0958 121.29
### Labour for cleaning road surface, heating
### bitumen mixing and spreading aggregate :
### (a) For cleaning :
### 28 Mate day 0.16 350.00
### 17 Beldar day 1.4 350.00
### 18 Coolie day 1.4 350.00
### (b) For heating bitumen :
### 17 Beldar day 1.88 350.00
### (c) For cleaning, mixing and spreading pre-mix
### 30 aggregate :
### Mistry day 0.31 505.17
### 17 Beldar day 9.46 350.00
### (d) Consolidation charges :
### 16 Chowkidar day 0.45 350.00
### 11 Bhisti day 0.18 350.00
### 3 Hire charges of Diesel Road Roller - 8 to 10 day 0.18 3000
### 1 tonne 800
### Hire charges of Coaltar Boiler 900 to 1400 day 0.3 800
### 23 litres
### Hot Bitumen mixer 0.5 cum i/c hand cart (e) day 0.03 3500
### 364 Misc :
### Wire brush each 0.09 20
### (with thick wire)
### 365 Soft brush each 0.27 20
### 9999 Brooms and gunny bags L.S. 5.33 2
### 9999 Sundries L.S. 16.12 2
### TOTAL
### Add 1 % Water charges on "W"
### TOTAL
### Add GST (multiplying factor 0.1405) on "X" 4061.03
### TOTAL
### Add 15 % Contractor's profit and overheads on "Y" 4944.77
### Total
### Add Cess @ 1% on "Z" 379.1
### Cost for 100 sqm. 38288.99
### Cost per sqm. 382.89
### Say 382.9
###
### 16.40 Providing and laying seal coat of
### premixed fine aggregate ( passing 2.36 mm
### road roller all complete.
###
### Details of cost for 100sqm.
###
### MATERIAL
### 2916 Paving Asphalt VG -10 of approved quality tonne 0.0768 24000
### @ 128kg/cum. of sand 128x0.60 =
### 76.80kg. = 0.0768 m.t
### 2211 Carriage of Tar bitumen tonne 0.0768 106.13
### 982 Coarse sand cum 0.6 800
### 2203 Carriage of Coarse sand cum 0.6 584.88
### Steam coal for heating bitumen @ 2 qunitals
### 370 per tonne of bitumen =2x0.768=0.1.536 qtl
### Coal (steam) quintal 1.536 440
### 2200 Carriage of steam coal tonne 0.1536 121.29
### Labour for cleaning road surface, heating
### bitumen mixing and spreading aggregate :
### (a) For cleaning :
### 28 Mate day 0.06 350.00
### 17 Beldar day 0.49 350.00
### 18 Coolie day 0.97 350.00
### (b) For heating bitumen :
### 17 Beldar day 0.3 350.00
### 0.38/96x76.8
### (c) For cleaning, mixing and spreading pre-mix
### 17 aggregate :
### Beldar day 1.11 350.00
### 11.39/0.75x0.60
### 30 Mistry day 0.05 505.17
### 0.06/0.75x0.60
### (d) Miscellaneous :
### 16 Chowkidar day 0.15 350.00
### 11 Bhisti day 0.06 350.00
### 3 Hire charges of Diesel Road Roller - 8 to 10 day 0.06 3000
### 1 tonne 800
### Hire charges of Coaltar Boiler 900 to 1400 day 0.05 800
### 23 litres
### Hot Bitumen mixer 0.5 cum i/c hand cart (e) day 0.01 3500
### 364 Misc :
### Wire brush each 0.05 20
### (with thick wire)
### 365 Soft brush each 0.12 20
### 9999 Sundries L.S. 18.2 2
### TOTAL
### Add 1 % Water charges on "W"
### TOTAL
### Add GST (multiplying factor 0.1405) on "X"
### TOTAL
### Add 15 % Contractor's profit and overheads on "Y"
### Total
### Add Cess @ 1% on "Z"
### Cost for 100 sqm.
### Cost per sqm.
### Say
###
### 16.41 16.41 Providing and laying seal coat
### over prepared surface of road with bitumen
### Details of cost for 100sqm.
### MATERIAL
### 2916 Paving Asphalt VG -10 of approved quality tonne 0.098 24000
### 2211 Carriage of Tar bitumen tonne 0.098 106.13
### 298 Stone Aggregate (Single size) : 06 mm nominal cum 0.9 810
### 2202 size 584.88
### Carriage of Stone aggregate below 40 mm cum 0.9 106.13
### nominal size
### Steam coal for heating bitumen @ 2 qunitals
### per tonne of bitumen
### =2x0.0.98=1.96 qtl
### 370 Coal (steam) quintal 1.96 440
### 2200 Carriage of steam coal tonne 0.196 121.29
### Labour for cleaning road surface, heating
### bitumen mixing and spreading aggregate :
### (a) For heating and spraying bitumen :
### 30 Mistry day 0.04 505.17
### 36 Sprayer (for bitumen, tar etc.) day 0.06 350.00
### 17 Beldar day 0.69 350.00
### (b) For cleaning :
### 28 Mate day 0.11 350.00
### 17 Beldar day 1.4 350.00
### 18 Coolie day 1.4 350.00
### (c) For screening and spraying aggregate :
### 28 Mate day 0.05 350.00
### 17 Beldar day 0.51 350.00
### (d) Misc :
### 16 Chowkidar day 0.15 350.00
### 11 Bhisti day 0.06 350.00
### 3 Hire charges of Diesel Road Roller - 8 to 10 day 0.06 3000
### 7 tonne
### Hire charges of Coaltar Sprayer day 0.06 300
### 1 Hire charges of Coaltar Boiler 900 to 1400 day 0.06 800
### 364 litres (e) Misc : 20
### Wire brush each 0.05 20
### (with thick wire)
### 365 Soft brush each 0.12 20
### 9999 Sundries L.S. 18.2 2
### 9999 Brooms and gunny bags L.S. 2.73 2
### TOTAL
### Add 1 % Water charges on "W"
### TOTAL
### Add GST (multiplying factor 0.1405) on "X"
### TOTAL
### Add 15 % Contractor's profit and overheads on "Y"
### Total
### Add Cess @ 1% on "Z"
### Cost for 100 sqm.
### Cost per sqm.
### Say
###
### 16.42 Cement concrete 1:2:4 (1 cement : 2
### coarse sand : 4 graded stone aggregate 40
### Details of cost for 1.00 cum.
### MATERIAL
### 293 Stone Aggregate (Single size) : 40 mm nominal cum 0.52 730
### 295 size cum 0.22 790
### Stone Aggregate (Single size) : 20 mm nominal
### 297 size cum 0.11 810
### Stone Aggregate (Single size) : 10 mm nominal
### 2206 size
### Carriage of Stone aggregate 40 mm nominal cum 0.52 115.36
### size and above
### 2202 Carriage of Stone aggregate below 40 mm cum 0.33 584.88
### 982 nominal size
### Coarse sand cum 0.445 1350
### 2203 Carriage of Coarse sand cum 0.445 584.88
### 367 Portland Cement (OPC-43 grade) tonne 0.32 4375
### 2209 Carriage of Cement tonne 0.32 94.34
### LABOUR
### 40 Mason (average) day 0.1 403.67
### 17 Beldar day 1.63 350.00
### 11 Bhisti day 0.7 350.00
### MACHINERY
### 2 Hire charges of Concrete Mixer 0.25 to day 0.077 800
### 0.40 cum with hooper
### 12 Vibrator (Needle type 40 mm) day 0.07 370
### 9999 Sundries L.S. 26 2
### Side shuttering
### Taking the slab to be 5cm thick and width to be
### 6 metre, length of road 27 metre =
### 9.90/24.30 = 0.407 sqm
### 5.9.1 Rate as per item no 5.9.1 of sqm 0.407 216.45
### SH : Reinforced cement concrete work
### 9999 Sundries L.S. 1.43 2
###
### TOTAL
### Add 1 % Water charges on "W-A" 4402.82 44.03
### TOTAL
### Add GST (multiplying factor 0.1405) on "X-A" 4446.85 624.78
### TOTAL
### Add 15 % Contractor's profit and overheads on 5071.63 760.74
### "Y-A"
### Total
### Add Cess @ 1% on "Z-A" 5832.37 58.32
### Cost for 1 cum. 5978.79
### Say 5978.8
###
### 16.43 Providing and laying design mix
### cement concrete of M-30 grade, in roads/
###
###
### Cement content considered in M-30 is @
### 340 kg/cum. Excess/ less cement used as
### 16.43.1 Cement concrete prepared with
### batch mixing machine
### Details of cost for 1 cum.
### MATERIAL
### 367 Portland Cement (OPC-43 grade) tonne 0.34 4375
### 2209 Carriage of Cement tonne 0.34 94.34
### 293 Stone Aggregate (Single size) : 40 mm nominal cum 0.52 730
### 295 size cum 0.22 790
### Stone Aggregate (Single size) : 20 mm nominal
### 297 size cum 0.11 810
### Stone Aggregate (Single size) : 10 mm nominal
### 982 size
### Coarse sand cum 0.445 1350
### 2206 Carriage of Stone aggregate 40 mm nominal cum 0.52 115.36
### size and above
### 2202 Carriage of Stone aggregate below 40 mm cum 0.33 584.88
### 2203 nominal size 584.88
### Carriage of Coarse sand cum 0.445 106.13
### LABOUR :- FOR MIXING AND LAYING
### 17 Beldar day 2 350.00
### 11 Bhisti day 0.27 350.00
### 23 Mason (brick layer) 1st class day 0.05 505.17
### 24 Mason (brick layer) 2nd class day 0.05 403.67
### 28 Mate day 0.04 350.00
### For compaction by vibrator
### 40 Mason (average) day 0.07 403.67
### 17 Beldar day 0.07 350.00
### MACHINERY
### 4 Production cost of concrete by batch mix plant. cum 1 350
### (Assuming 25 cum. per day)
### 9 Pumping charges of concrete including Hire cum 1 210
### charges of pump, piping work & accessories
### 21 etc.
### Pin vibrator day 0.025 325
### (SHP) with 50 cum. output per day
### 22 Surface Vibrator with 25 cum. output per day day 0.05 400
### 16.43B Add for steel form work
### Rate as per Item Number 16.43B of SH: Road cum 1 472.3
### 9999 work
### Cutting and making joints L.S. 50 2
### TOTAL
### Add 1 % Water charges on "W"
### TOTAL
### Add GST (multiplying factor 0.1405) on "X"
### TOTAL
### Add 15 % Contractor's profit and overheads on "Y"
### Total
### Add Cess @ 1% on "Z"
### Cost per cum.
### Say
###
### 16.43.2 Cement concrete manufactured in
### automatic
Details batching
of cost for 1 cum.plant
(RMC plant) i/c
###
### MATERIAL
### 367 Portland Cement (OPC-43 grade) tonne 0.34 4375
### 2209 Carriage of Cement tonne 0.34 94.34
### 293 Stone Aggregate (Single size) : 40 mm nominal cum 0.52 730
### 295 size cum 0.22 790
### Stone Aggregate (Single size) : 20 mm nominal
### size
### 297 Stone Aggregate (Single size) : 10 mm nominal cum 0.11 810
### 982 size
### Coarse sand cum 0.445 1350
### 2206 Carriage of Stone aggregate 40 mm nominal cum 0.52 115.36
### size and above
### 2202 Carriage of Stone aggregate below 40 mm cum 0.33 584.88
### 2203 nominal size 584.88
### Carriage of Coarse sand cum 0.445 106.13
### LABOUR :- FOR MIXING AND LAYING
### 17 Beldar day 2 350.00
### 11 Bhisti day 0.27 350.00
### 23 Mason (brick layer) 1st class day 0.05 505.17
### 24 Mason (brick layer) 2nd class day 0.05 403.67
### 28 Mate day 0.04 350.00
### For compaction by vibrator
### 40 Mason (average) day 0.07 403.67
### 17 Beldar day 0.07 350.00
### MACHINERY
### 4 Production cost of concrete by batch mix plant. cum 1 350
### (Assuming 25 cum. per day)
### 29 Carriage of concrete by transit mixer. km/ 10 30
### 9 cum 210
### Pumping charges of concrete including Hire cum 1 210
### charges of pump, piping work & accessories
### 21 etc.
### Pin vibrator day 0.03 325
### (SHP) with 50 cum. output per day
### 22 Surface Vibrator with 25 cum. output per day day 0.05 400
### 16.43B Add for steel form work
### Rate as per Item Number 16.43B of SH: Road cum 1 472.3
### 9999 work
### Cutting and making joints L.S. 50 2
### TOTAL
### Add 1 % Water charges on "W"
### TOTAL
### Add GST (multiplying factor 0.1405) on "X"
### TOTAL
### Add 15 % Contractor's profit and overheads on "Y"
### Total
### Add Cess @ 1% on "Z"
### Cost per cum.
### Say
### 16.43A Annexure ‘A’ to Item number 16.43
###
### Details of cost for 8.5 cum.
###
### MATERIAL:
###
### (i) Painting with primer
###
### (i) Construction joint 6.15m. long 30cm deep
6.15x(0.30+0.01)= 1.91sqm.+
###
### (ii) Dummy joints
###
### 4.61m long and 10cm deep 10mm wide
### 4.6 lx(0.10+0.10+0.01) = 0.97 sqm. = 2.88
### sqm.
### 2.88sqm. @0.26 lit./sqm. = 0.75 lit. +
### Add 5% wastage = 0.03
### Total =0.78 lit
### 316 Bitumen solution primer of approved quality litre 0.78 45
### 9977 Carriage L.S. 0.91 2
### (ii) Joint sealing compound (GradeA) for
### construction joint 6.15m long 10mm wide
### 25mm deep.
### 6.15x2x2.5cm = 3075cucm
### For dummy joints
### 461xl.0xl0cm. = 4610cucm.
### = 7685 cum
### Add 5% wastage = 384 cucm
### Total = 8069 cucm
### Say 8.07 cudm. @1.2kg/cudm = 9.68 kg
### 314 Bitumen hot sealing compound : grade A kilogra 9.68 28
### 9977 m
### Carriage L.S. 0.91 2
### 370 Coal (steam) quintal 0.015 440
### 9977 Carriage L.S. 0.91 2
### LABOUR:
### (ii) For applying primer qty. = 2.88 sqm
### 23 Mason (brick layer) 1st class day 3 505.17
### 31 Painter day 0.1 403.67
### (iii) Labour for heating and filling sealing
### 24 compound.
### Mason (brick layer) 2nd class day 0.25 403.67
### (iv) Beldar for heating = 0.06 +
### 17 Beldar day 0.68 350.00
###
### TOTAL
### Cost for 8.5 cum
### Cost per cum.
### Say
###
### 16.43B Annexure ‘B’ to Item number 16.43
### ANALYSIS OF ANNEXTURE 'B' 16.43B
### (Required in 16.43)
### STEEL FORM WORK :
### Part-I Cost of materials :
### Assuming that pavement 30m long 22.5m wide
### and 0.30m deep having panel size
### 6.15x4.61x0.30m or 8.50cu. laid in a day of 8
### hrs. Hence form work to be provided for 2
### days.
### MATERIAL
### 22x30.75 = 676.50 2x46.10 = 92.20
### Total = 768.70m.
### 768.70 @ 83.10 kg/ m = 25.44 M.T.
### Assuming that channel will become
### unserviceable after use for 5000 slab (100
### times) and salvage value of steel shall fetch
### 20% of its basic cost.
### 1007 Structurals such as tees,angles channels and quintal 0.0407104 5300
### 2205 R.S. joists
### Carriage of Steel tonne 0.004071 94.34
### Part-II Labour for assembling, errection,
### dismeritelling and cleaning the shuttering.
### Assuming that 255 labour for steel shuttering
### shall be required as compared to timber
### shuttering. Contact area of 50 slabs of steel
### shuttering.
### Long channel = 11x20x0.30 = 66.00
### = 2x45.10x0.30 = 27.06
### Total= 93.06
### LABOUR
### 13 Blacksmith 2nd class day 2.86 403.67
### 17 Beldar day 2.86 350.00
### Carriage of steel for extra lead of runway
### 17 Beldar day 5.73 350.00
###
### TOTAL
### Cost for 50 slabs / 8.5 cum
### Cost per cum.
### Say
###
### 16.44 Extra for providing and mixing
### hardening compound of approved quality
### Details of cost for 1 litre
###
### MATERIAL
### (including cartage)
### TOTAL
### Add 1 % Water charges on "W"
### TOTAL
### Add GST (multiplying factor 0.1405) on "X"
### TOTAL
### Add 15 % Contractor's profit and overheads on "Y"
### Total
### Add Cess @ 1% on "Z"
### Cost per litre
### Say
###
### 16.45 Providing and fixing in position pre-
### moulded joint filler in expansion joints.
### Details of cost for 18mm thick 15cm deep and
###
### 300m in length
### MATERIAL
###
### 317 Premoulded joint filler 12 mm thick = 300x0.15 sqm 45 360
### 2211 = 45 sqm.
### Carriage of Tar bitumen 45x0.018 =0.81cum. tonne 0.21 106.13
### Weight 256.3kg. per cum. = 256.3x0.81
### = 207.6kg. say 0.21 tonne
### Labour for fixing etc. :
### 24 Mason (brick layer) 2nd class day 1 403.67
### 17 Beldar day 3 350.00
### 9999 Sundries L.S. 26.91 2
### TOTAL
### Add 1 % Water charges on "W"
### TOTAL
### Add GST (multiplying factor 0.1405) on "X"
### TOTAL
### Add 15 % Contractor's profit and overheads on "Y"
### Total
### Add Cess @ 1% on "Z"
### Cost for 300m length, 18mm width and 15cm
### depth
### Cost for one cm. depth one cm. width per
### metre length.
### Say
###
### 16.46 Providing and laying in position
bitumen hot sealing compound for
###
### 16.46.1 Using grade 'A' sealing compound.
###
### Details of cost for 20mm wide 20mm deep and
###
### 300 metres in length.
### Sealing compound300x0.02x0.02 = 0.12cum.
### Weight 256.3kg. per cum. = 256.3x0.12 =
### 30.76 kg
### MATERIAL
### 314 Bitumen hot sealing compound : grade A kilogra 30.76 28
### 2211 m
### Carriage of Tar bitumen tonne 0.03 106.13
### 30.76 = 0.3076 Say
### 0.03 tonne
### Labour for filling :
### 24 Mason (brick layer) 2nd class day 1 403.67
### 17 Beldar day 2.5 350.00
### 9999 Sundries L.S. 20.67 2
### TOTAL
### Add 1 % Water charges on "W"
### TOTAL
### Add GST (multiplying factor 0.1405) on "X"
### TOTAL
### Add 15 % Contractor's profit and overheads on "Y"
### Total
### Add Cess @ 1% on "Z"
### Cost for 20mm depth, 20mm width and 300m length
### Cost for one cm. depth one cm. width per metre
length.
### Say
###
### 16.47 Painting runway/taxi track/apron
### marking with adequate nos of coats to give
### 16.47.1 New work (Two or more coats)
###
### Details of cost for 10sqm.
### MATERIAL
### 1st Coat - 1.66 +
### 2nd Coat -1.13
### Total = 2.79
### 7256 Superior quality road marking paint (water litre 2.79 135
### 9977 based)
### Carriage of paint L.S. 5.07 2
### LABOUR
### 31 Painter day 0.54 403.67
### 17 Beldar day 0.54 350.00
### 9999 Sundries L.S. 36.4 2
### (including painting brush, wire brush, labour for
### controlling traffic and other T&P etc.)
### TOTAL
### Add 1 % Water charges on "W"
### TOTAL
### Add GST (multiplying factor 0.1405) on "X"
### TOTAL
### Add 15 % Contractor's profit and overheads on "Y"
### Total
### Add Cess @ 1% on "Z"
### Cost for 10 sqm.
### Cost per sqm.
### Say
###
### 16.47.2 Old work (One or more coats)
###
### Details of cost for 10sqm.
### MATERIAL
### 7256 Superior quality road marking paint (water litre 1.66 135
### 9977 based)
### Carriage of paint L.S. 1.12 2
### LABOUR
### 31 Painter day 0.36 403.67
### 17 Beldar day 0.36 350.00
### 9999 Sundries L.S. 24.44 2
### (including painting brush, wire brush, labour for
### controlling traffic and other T&P etc.)
### TOTAL
### Add 1 % Water charges on "W"
### TOTAL
### Add GST (multiplying factor 0.1405) on "X"
### TOTAL
### Add 15 % Contractor's profit and overheads on "Y"
### Total
### Add Cess @ 1% on "Z"
### Cost for 10 sqm.
### Cost per sqm.
### Say
###
### 16.48 Painting road surface marking with
### adequate nos of coats to give uniform
### 16.48.1 New work (Two or more coats)
###
### Details of cost for 10sqm.
### MATERIAL
### 7255 Road marking paint (spirit based) litre 1.48 115
### (confirming to IS 164 spirit base)
### 9977 Carriage of paint (1.48/0.8x0.08x6.9) L.S. 2.65 2
### LABOUR
### 28 Mate day 0.1 350.00
### 31 Painter day 0.54 403.67
### 17 Beldar day 1.68 350.00
### for stretching of rope & errecting of barricading
### 9999 Sundries L.S. 36.4 2
### (including painting brush, wire brush, labour for
### controlling traffic and other T&P etc.)
### TOTAL
### Add 1 % Water charges on "W"
### TOTAL
### Add GST (multiplying factor 0.1405) on "X"
### TOTAL
### Add 15 % Contractor's profit and overheads on "Y"
### Total
### Add Cess @ 1% on "Z"
### Cost for 10 sqm.
### Cost per sqm.
### Say
###
### 16.48.2 Old work (One or more coats)
###
### Details of cost for 10sqm.
### MATERIAL
### 7255 Road marking paint (spirit based) (confirming litre 0.89 115
### 9977 to IS 164 spirit base)
### Carriage of paint. L.S. 0.65 2
### LABOUR
### 28 Mate day 0.06 350.00
### 31 Painter day 0.36 403.67
### 17 Beldar day 1.12 350.00
### (stretching of rope & errecting of barricading
### 9999 etc.)
### Sundries L.S. 24.44 2
### (including painting brush, wire brush, labour for
### controlling traffic and other T&P etc.)
### TOTAL
### Add 1 % Water charges on "W"
### TOTAL
### Add GST (multiplying factor 0.1405) on "X"
### TOTAL
### Add 15 % Contractor's profit and overheads on "Y"
### Total
### Add Cess @ 1% on "Z"
### Cost for 10 sqm.
### Cost per sqm.
### Say
###
### 16.49 Making bell mouth opening/ entrance
### of sizeof100x50x50
Details cm
cost for 10 Nos. for drainage pipe
### (i) Earth work in excavation
### Channel :- 10x1x1.00x0.20x0.15 = 0.30+
### Bell mouth :-10x1x1.00x0.50x
### (0.18+0.075)/2 = 0.64
### Total = 0.94
### MATERIAL
### 2.8.1 (Rate as per item no. 2.8.1 of SH: Earth work) cum 0.94 171.4
### (ii) Cement concrete 1:4:8
### Channel :-10x1x1.00x0.20x0.075 = 0.15 cum.
### 4.1.8 Rate as per item no 4.1.8 of cum 0.15 4955.2
### SH : Concrete Work
### (iii) Cement concrete 1:3:6
### Channel
###
### 10x1x1.00x0.20x0.75 = 0.15 + Bed of bell mouth :
###
###
###
### 1221
###
###
### 10x1x1.00x0.50x(0.18+0.075)/2 = 0.64 +
### Haunches portion
### 10x2x(0.35+0.075)/2x0.25x0.375 = 0.40 +
### Rect part :-
### 10x2x0.35x0.25x0.375 = 0.65 +
### Quadrant portion :-
### 10x1[(0.30x0.30)-3.142/4(0.30)²]x0.30 =0.06+
### Central middle part :-
### 10x1x0.30x0.25x0.075 = 0.05 Total = 1.95
### 4.1.5 cum.
### (Rate as per item no.4.1.5 S.H. : Cement cum 1.95 5424.85
### Concrete)
### (iv) RCC in shelves
### 10x1x1.00x0.50x0.05 = 0.25cum.
### 5.3 Rate as per item no. 5.3 SH : Reinforced cum 0.25 7640.80
### cement concrete work
### (v) Reinforcement for RCC @100kg/cum.
### 0.25x100=25kg.
### 5.22.1 Rate as per item no. 5.22.1 SH : Reinforced kg 25 75.4
### cement concrete work
### (vi) Centering and shuttering
### For shelves (sides)
### 10x2(1.00+0.50)x0.05 = 1.50+ Front side of
### bell mouth : 10x2(0.446)x0.375 = 3.34 + Pipe
### portion:
### 10x[0.30x0.375-3.142/4(0.30)²] = 0.04 +
### Out side of bell mouth
### Total= 10x(1.00 =0.50)x0.45 = 9.00+
### Deduct pipe opening
### Total =10x0.785x0.30x0.30 = (-)0.71
### Total = 13.17
### 5.9.1 Rate as per item No.5.9.1 of SH : RCC sqm 13.17 216.45
### (vii) cement plaster on RCC slab
### 10x1.00x0.50 = 5.00 + 10x2(1.00+0.50)x0.05 =
### 5.23 1.50+ Total = 6.50 sqm. 142.35
### Rate as per item no.13.16.1 (viii) Neat cement sqm 6.5 142.35
### punning:
### Qty. same as marked (x) at (9vi) = Total
### =3.34+0.04 = 3.38 sqm.
### Channel portion:
### 10x1x(0.85+0.30)/2x0.25 = 1.43
### Total = 4.81
### 13.18 Rate as per item no.13.18 S.H. Finishing sqm 4.81 42.1
### 367 Portland Cement (OPC-43 grade) tonne 0.024 4375
### 2209 Carriage of Cement tonne 0.024 94.34
### 983 Fine sand cum 0.05 850
### 2261 Carriage of Fine sand (1 part badarpur sand : 2 cum 0.05 106.13
### parts Sand)
### LABOUR
### 17 Beldar day 0.035 350.00
### 11 Bhisti day 0.003 350.00
### 9999 Hire charges of mixer L.S. 1.27 2
### 9999 Sundries L.S. 1.27 2
### Labour for plaster
### 40 Mason (average) day 0.33 403.67
### 18 Coolie day 0.488 350.00
### 11 Bhisti day 0.6 350.00
### 9999 Extra for removing burr L.S. 8.71 2
### 9999 Scaffolding L.S. 7.62 2
### TOTAL
### Add 1 % Water charges on "W-A" 693.71
### TOTAL
### Add GST (multiplying factor 0.1405) on "X" 700.65
### TOTAL
### Add 15 % Contractor's profit and overheads on 799.09
### "Y"
### Total
### Add Cess @ 1% on "Z" 918.95
### Cost for 10 nos.
### Cost for one bell mouth
### Say
###
### 16.50 Providing and fixing Glow studs of
### size 100x20 mm made of heavy duty body
### Details of cost for 15 Nos.
###
### MATERIAL
###
### 7426 Cat's eye each 15 100
###
###
###
###
### 1223
###
###
### 9977 Carriage of cats eyes L.S. 2.6 2
### LABOUR
### 24 Mason (brick layer) 2nd class day 0.5 403.67
### 17 Beldar day 0.5 350.00
### 9999 Sundries L.S. 39 2
### (including material required for fixing cats eyes
### and providing barricading to divert traffic)
### TOTAL
### Add 1 % Water charges on "W"
### TOTAL
### Add GST (multiplying factor 0.1405) on "X"
### TOTAL
### Add 15 % Contractor's profit and overheads on "Y"
### Total
### Add Cess @ 1% on "Z"
### Cost for 15 Nos.
### Cost for one cat's eye.
### Say
###
### 16.51 Preparation of sub-base road
### pavement with commercial dry lime
### 16.51.1 Minimum thickness 15 cm
### Details of cost for 6.67 sqm. or 1 cum.
### MATERIAL
### 777 Dry hydrated lime (factory made) quintal 0.41 290
### 2208 Carriage of Lime cum 0.068 106.13
### 1980 Flyash cum 0.277 10
### 2267 Carriage of Stone dust cum 0.277 106.13
### LABOUR
### (i)For earth work :
### 17 Beldar day 0.116 350.00
### 18 Coolie day 0.116 350.00
### 979 Royalty for good earth cum 0.655 40
### 2241 Carriage of Good earth (ii) For mixing : cum 0.655 132.66
### 17 Beldar day 0.025 350.00
### 18 Coolie day 0.025 350.00
### (iii) For rolling layers :
### 16 Chowkidar day 0.0008 350.00
### 3 Hire charges of Diesel Road Roller - 8 to 10 day 0.0008 3000
### 9999 tonne
### Sundries L.S. 0.18 2
### (iv) Labour for spreading and watering :
### 17 Beldar day 0.26 350.00
### 18 Coolie day 0.26 350.00
### 11 Bhisti day 0.18 350.00
### TOTAL
### Add 1 % Water charges on "W"
### TOTAL
### Add GST (multiplying factor 0.1405) on "X"
### TOTAL
### Add 15 % Contractor's profit and overheads on "Y"
### Total
### Add Cess @ 1% on "Z"
### Cost for 1 cum.
### Say
###
### 16.52 Providing and fixing precast lime fly
### ash concrete blocks 1:2:3:6 (1 lime: 2 fly
### Details of cost for a path of area 10sqm. no. of
###
### blocks required for 10sqm. = 108 nos.
### (a) Concrete in blocks (108x0.30x0.30x0.09 = 0.875
cum.)
### 16.52Y Rate as per sub analysis Item Number cum 0.875 2809.05
### 16.52Y of SH:Road Work
### (b) Labour for surface excavation :
### 17 Beldar day 0.72 350.00
### 18 Coolie day 0.6 350.00
### (c) For levelling course of fine sand
### 6501 Sand zone V (Jamuna) cum 0.1 800
### 2335 Carriage of Sand cum 0.1 106.13
### LABOUR
### 17 Beldar day 0.0089 350.00
### 18 Coolie day 0.0107 350.00
### 11 Bhisti day 0.0035 350.00
### (d) For finishing with 10mm thick cement
### plaster
### cement plaster with cement mortar 1:3(1
### Cement: 3 Coarse sand) qty. for 9.72sqm. =
### 3.8 0.0972 cum
### Rate as per Item Number 3.8 of SH: Mortars cum 0.0972 4469.5
### 40 Mason (average) day 0.787 403.67
### 18 Coolie day 0.787 350.00
### 11 Bhisti day 0.262 350.00
### 9999 Scaffolding and sundries L.S. 12.22 2
### (e) For laying blocks and filling joints with Sand
### 6501 for filling joints 5mm (av.) thick
### Sand zone V (Jamuna) cum 0.005 1225
### 2335 Carriage of Sand cum 0.005 106.13
### 23 Mason (brick layer) 1st class day 0.9 505.17
### 18 Coolie day 1.98 350.00
### 11 Bhisti day 0.05 350.00
### TOTAL
### Add 1 % Water charges on "W"
### TOTAL
### Add GST (multiplying factor 0.1405) on "X"
### TOTAL
### Add 15 % Contractor's profit and overheads on "Y"
### Total
### Add Cess @ 1% on "Z"
### Cost for 10sqm. or 0.9cum.
### Rate per cum.
### Say
###
### 16.52X Sub Analysis X for sub analysis
### item Number 16.52Y
### Sub Analysis 16.52X for use in sub analysis of 16.52Y
### Details of cost for 1cum of lime Flyash mortar
### 1:2:3 (lime:2 flyash:3 coarse sand).
### MATERIAL
### 773 Unslaked lime quintal 1.52 300
### 1980 Flyash cum 0.48 10
### 982 Coarse sand cum 0.72 800
### 2208 Carriage of Lime cum 0.24 106.13
### 2266 Carriage of Surkhi cum 0.48 106.13
### 2203 Carriage of Coarse sand cum 0.72 584.88
### LABOUR
### Labour for slaking the lime making, lime putty,
### grinding, measuring, carrying, depositing and
### 17 mixing.
### Beldar day 0.9 350.00
### 11 Bhisti day 0.45 350.00
### 9999 Running and upkeep of mortar mill L.S. 26.91 2
### 9999 Sundries L.S. 13.52 2
###
### TOTAL
### Cost of 1.00 cum
### Say
### 16.52Y Sub Analysis Y for Item Number 16.52
### Sub Analysis 'Y' (16.52Y) for use in Item
### No. 16.52
### Details of cost for 1 cum. of cement concrete
### MATERIAL
### Lime Flyash mortar
### 16.52X Rate as per sub analysis of Item No 16.52X cum 0.4 2099.6
### 295 Stone Aggregate (Single size) : 20 mm nominal cum 0.64 790
### 297 size cum 0.21 810
### Stone Aggregate (Single size) : 10 mm nominal
### 2202 size 584.88
### Carriage of Stone aggregate below 40 mm cum 0.85 106.13
### nominal size
### LABOUR
### 17 Beldar day 0.65 350.00
### 18 Coolie day 0.6 350.00
### 11 Bhisti day 0.27 350.00
### 23 Mason (brick layer) 1st class day 0.05 505.17
### 24 Mason (brick layer) 2nd class day 0.05 403.67
### 28 Mate day 0.04 350.00
### 9999 Hire and running charges of mixer L.S. 26.91 2
### 9999 Sundries L.S. 13.52 2
### 9999 Hire charges of steel moulds, table vibrators, L.S. 53.82 2
### rammers, bolts, nuts and washers etc.
### TOTAL
### Cost of 1.00 cum
### Say
###
### 16.53 Providing and fixing concertina coil
### fencing with punched tape concertina coil
### (cost of M.S. angle, C.C. blocks shall be
### paid separately)
### Details of cost for 30.00 m length
### MATERIAL
### 8691 Punched tape concertina coil 600 mm dia bundle 5 600
### 10 m openable length (Total length 90 m)
### (Having 50 Nos. of rounds per 6 meter = 1
### bundles)
### Therefore, Nos. of bundles 30/10=3bundles)
### 8692 RBT reinforced barbed wire 9 rounds = 9x30 = metre 270 6.5
### 8693 270m 40
### Turn buckle and strengthening bolt each 10 40
### set
### 9999 G.I. staples clips etc. L.S. 49.4 2
### LABOUR
### Labour for fixing straightening cutting of tape/
### 17 coils & wire
### Beldar day 1 350.00
### 0.50x2 = 1.00 Nos (Taken double due to
### 12 height)
### Blacksmith 1st class day 0.5 505.17
### 13 Blacksmith 2nd class day 0.5 403.67
### Total
### Add 1 % Water charges on "W"
### TOTAL
### Add GST (multiplying factor 0.1405) on "X"
### TOTAL
### Add 15 % Contractor's profit and overheads on "Y"
### Total
### Add Cess @ 1% on "Z"
###
### cost for 30.00 metre
### cost per metre
### Say
###
### 16.54 Providing and laying Dense Graded
### Bituminous Macadam using crushed stone
### 16.54.1 50 to 100 mm average compacted
### thickness with bitumen of grade VG-30 @
### Details of cost for 195 cum (or 450 M.T. )
###
### MATERIAL
### 7309 Paving Asphalt VG-30 of approved quality tonne 22.5 39570
### 2211 (percentage by weight of total mix)
### Carriage of Tar bitumen tonne 22.5 106.13
### Aggregate
### Total weight of mix = 450 tonnes
### Weight of bitumen = 22.50 tonnes
### Weight of aggregate = 450 -22.50 = 427.50
### tonnes
### Taking density of aggregate = 1.5 tonne/cum
### Volume of aggregate =427.50/1.5 =285cum
### Grading - II/19 mm (Nominal Size)
### 25 - 10mm size = 30% of 285 = 85.5 cum
### 10 - 5mm size = 28% of 285 = 79.8 cum
### 5mm and below = 40% of 285 = 114 cum
### 294 Stone Aggregate (Single size) : 25 mm nominal cum 42.75 760
### size
### Qty = 85.5 * 50 /100
### 297 Stone Aggregate (Single size) : 10 mm nominal cum 42.75 810
### size
### Qty = 85.5 * 50 /100
### 297 Stone Aggregate (Single size) : 10 mm nominal cum 39.9 810
### size
### Qty = 79.8 * 50 /100
### 298 Stone Aggregate (Single size) : 06 mm nominal cum 39.9 810
### size
### Qty = 79.8 * 50 /100
### 2903 Stone chippings/ screenings 4.75 mm nominal cum 279.3 1400
### size Qty = 285 * 40 /100 85.5 290
### 2202 Carriage of Stone aggregate below 40 mm cum 6.63 584.88
### nominal size 3 15000
### Lime Filler @ 2% ( percentage by weight of 3 13000
### 777 aggregate) 6 1500
### Dry hydrated lime (factory made) quintal 6 350
### 2208 Carriage of Lime cum 6 900
### (consitering density of lime as 1.29 T per cum) 4500 3
### V =8.55/1.29 = 6.63 cum
### MACHINERY/ HIRE CHARGES: 3.9 300
### 62 Hot mix Plant -120 TPH capacity hour 3.9 360
### 63 Hot mix Plant 100 TPH Capacity hour 3.9 1200
### 64 Paver finisher Hydrostatic with sensor control hour 0.84 350.00
### 69 100 TPH 14 350.00
### Generator 250 KVA hour
### 52 Front end loader 1 cum bucket capacity (incl hour
### POL) Tipper 10 tonne capacity (Taken 10Km
### average lead) 450x10=4500 tonne km.
### 53 Tipper -5 Cum tonne
### Add 10 per cent of cost of carriage to cove r km
###
### 55 cost of loading and unloading
### Smooth Wheeled Roller 8 to 10 tonne for initial hour
### break down rolling.(6*0.65)
### 54 Vibratory roller 8 to 10 tonne for intermediate hour
### 56 rolling.(6*0.65)
### Tandem Road Roller hour
### Finish rolling with 6-8 tonnes smooth
### wheeled tandem roller.(6*0.65)
### LABOUR
### 28 Mate day
### 17 Beldar working with HMP, mechanical broom, day
### paver, roller, asphalt cutter and assistance for
### setting out lines, levels and layout of
### construction
### 37 Skilled Beldar (for floor rubbing etc.) day
###
### for checking line & levels Total Add 1 % Water charges on
"W"
### TOTAL
###
### Add GST (multiplying factor 0.1405) on "X"
###
### TOTAL
###
### Add 15 % Contractor's profit and overheads on "Y"
###
###
### Quantity Rate Amount
###
### 114.0 1400.00159600.00
###
### Total
### Add Cess @ 1% on "Z" 19373.72
###
### Cost for 195 cum(450 M.T.) 1956745.81
### Cost per cum. 10034.59
### Say 10034.6
###
### 16.54.2 50 to 100 mm average compacted
### thickness with bitumen of grade VG-30 @
### capacity.
###
### Details of cost for 195 cum (or 450 M.T. )
###
### MATERIAL
### 7309 Paving Asphalt VG-30 of approved quality tonne 22.5 39570
### 2211 (percentage by weight of total mix)
### Carriage of Tar bitumen tonne 22.5 106.13
### Aggregate
### Total weight of mix = 450 tonnes
### Weight of bitumen = 22.50 tonnes
### Weight of aggregate = 450 -22.50
### = 427.50 tonnes
### Taking density of aggregate = 1.5 tonne/cum
### Volume of aggregate =427.50/1.5 =285cum
### Grading - II/19 mm (Nominal Size)
### 25 - 10mm size = 30% of 285 = 85.5 cum
### 10 - 5mm size = 28% of 285 = 79.8 cum
### 5mm and below = 40% of 285 = 114 cum
### 294 Stone Aggregate (Single size) : 25 mm nominal cum 42.75 760
### size
### Qty = 85.5 * 50 /100
### 297 Stone Aggregate (Single size) : 10 mm nominal cum 42.75 810
### size
### Qty = 85.5 * 50 /100
### 297 Stone Aggregate (Single size) : 10 mm nominal cum 39.9 810
### size
### Qty = 79.8 * 50 /100
### 298 Stone Aggregate (Single size) : 06 mm nominal cum 39.9 810
### size
### Qty = 79.8 * 50 /100
### 2903 Stone chippings/ screenings 4.75 mm nominal cum 114 1400
### size Qty = 285 * 40 /100
### 2202 Carriage of Stone aggregate below 40 mm cum 279.3 584.88
### nominal size
### Lime Filler @ 2% ( percentage by weight of
### 777 aggregate)
### Dry hydrated lime (factory made) quintal 85.5 290
### 2208 Carriage of Lime cum 6.63 106.13
### (consitering density of lime as 1.29 T per cum)
### V =8.55/1.29 = 6.63 cum
### MACHINERY/ HIRE CHARGES:
### 74 Drum Type HMP of 60-90 TPH capacity @ 75 hour 6 12000
### 64 tonne per hour actual output
### Paver finisher Hydrostatic with sensor control hour 6 1500
### 69 100 TPH
### Generator 250 KVA hour 6 350
### 52 Front end loader 1 cum bucket capacity (incl hour 6 900
### POL) Tipper 10 tonne capacity (Taken 10Km
### average lead) 450x10=4500 tonne km.
### 53 Tipper -5 Cum tonne 4500 3
### Add 10 per cent of cost of carriage to cover km
###
### 55 cost of loading and unloading
### Smooth Wheeled Roller 8 to 10 tonne for initial hour 3.9 300
### break down rolling.(6*0.65)
### 54 Vibratory roller 8 to 10 tonne for intermediate hour 3.9 600
### 56 rolling.(6*0.65)
### Tandem Road Roller hour 3.9 1200
### Finish rolling with 6-8 tonnes smooth
### wheeled tandem roller.(6*0.65)
### LABOUR
### 28 Mate day 0.84 350.00
### 17 Beldar day 14 350.00
### working with HMP, mechanical broom, paver,
### roller, asphalt cutter and assistance for setting
### out lines, levels and layout of construction
### 37 Skilled Beldar (for floor rubbing etc.) day 5 350.00
### for checking line & levels Total
### Add 1 % Water charges on "W"
### TOTAL
### Add GST (multiplying factor 0.1405) on "X"
### TOTAL
### Add 15 % Contractor's profit and overheads on "Y"
### Total
### Add Cess @ 1% on "Z"
### Cost for 195 cum(450 M.T.)
### Cost per cum.
### Say
###
###
###
### 16.55 Providing and laying bituminous
### macadam using crushed stone aggregates
### 16.55.1 50 to 100 mm average compacted
### thickness with bitumen of grade VG-30 @
### Plant of 100120 TPH capacity.
###
### Details of cost for 205 cum (or 450 M.T. )
###
### MATERIAL
### 7309 Paving Asphalt VG-30 of approved quality tonne 15.75 39570
### 3.5% of 450 MT = 15.75 MT
### 2211 Carriage of Tar bitumen tonne 15.75 106.13
### Weight of mix = 205 * 2.5 = 450 tonnes
### Aggregate
### Total weight of mix = 450 tonnes Weight of
### bitumen = 15.75 tonnes Weight of aggregate =
### 450 -15.75 = 434.25 tonnes
### Taking density of aggregate = 1.5 tonne/cum
### Volume of aggregate =434.25/1.5
### =289.50cum
### Grading - II/19 mm (Nominal Size)
### 25 - 10mm size = 40% of 289.50 = 115.8 cum
### 10 - 5mm size = 40% of 289.50 = 115.8 cum
### 5mm and below = 20% of 289.50 = 57.9 cum
### 294 Stone Aggregate (Single size) : 25 mm nominal cum 57.9 760
### size
### Qty = 115.8 * 50 /100
### 297 Stone Aggregate (Single size) : 10 mm nominal cum 57.9 810
### size
### Qty = 115.8 * 50 /100
### 297 Stone Aggregate (Single size) : 10 mm nominal cum 57.9 810
### size
### Qty = 115.8 * 50 /100
### 298 Stone Aggregate (Single size) : 06 mm nominal cum 57.9 810
### size
### Qty = 115.8 * 50 /100
### 2903 Stone chippings/ screenings 4.75 mm nominal cum 57.9 1400
### size
### Qty = 289.50 * 20 /100
### 2202 Carriage of Stone aggregate below 40 mm cum 289.5 584.88
### nominal size
### MACHINERY
### 62 Hot mix Plant -120 TPH capacity @75tonne hour 3 15000
### per hour actual output
### 63 Hot mix Plant 100 TPH Capacity hour 3 13000
### @75tonne per hour actual output
### 64 Paver finisher Hydrostatic with sensor hour 6 1500
### control 100 TPH
### @75tonne per hour actual output
### 69 Generator 250 KVA hour 6 350
### 52 Front end loader 1 cum bucket capacity (incl hour 6 900
### POL) Tipper 10 tonne capacity (Taken 10Km
### 53 average lead) 450x10=4500 tonne km.
### Tipper -5 Cum tonne 4500 3
### Add 10 per cent of cost of carriage to cover km
###
### cost of loading and unloading X * 10 / 100 =
### 55 13500.00 * 10 / 100
### Smooth Wheeled Roller 8 to 10 tonne for initial hour 3.9 300
### break down rolling.(6*0.65)
### 54 Vibratory roller 8 to 10 tonne for intermediate hour 3.9 600
### 56 rolling.(6*0.65)
### Tandem Road Roller hour 3.9 1200
### Finish rolling with 6-8 tonnes smooth
### wheeled tandem roller.(6*0.65)
### LABOUR:
### 28 Mate day 0.84 350.00
### 17 Beldar day 14 350.00
### working with HMP, mechanical broom,
### paver, roller, asphalt cutter and
### assistance for setting out lines, levels
### and layout of construction
### 37 Skilled Beldar (for floor rubbing etc.) for day 5 350.00
### checking line & levels
###
### Add 1 % Water charges on "W"
### TOTAL
### Add GST (multiplying factor 0.1405) on "X"
### TOTAL
### Add 15 % Contractor's profit and overheads on "Y"
### Total
### Add Cess @ 1% on "Z"
### Cost for 205 cum(450 M.T.)
### Cost per cum.
### Say
###
### 16.55.2 50 to 100 mm average compacted
### thickness with bitumen of grade VG-30 @
### Plant of 60- 90 TPH capacity.
###
### Details of cost for 205 cum (or 450 M.T. )
###
### MATERIAL
### 7309 Paving Asphalt VG-30 of approved quality tonne 15.75 39570
### 3.5% of 450 MT = 15.75 MT
### 2211 Carriage of Tar bitumen tonne 15.75 106.13
### Weight of mix = 205 * 2.5 = 450 tonnes
### Aggregate
### Total weight of mix = 450 tonnes
### Weight of bitumen = 15.75 tonnes
### Weight of aggregate = 450 -15.75 =434.25
### tonnes
### Taking density of aggregate = 1.5 tonne/cum
### Volume of aggregate =434.25/1.5 =289.50cum
### Grading - II/19 mm (Nominal Size) 25 - 10mm
### size = 40% of 289.50 = 115.8 cum
### 10 - 5mm size = 40% of 289.50 =115.8 cum
### 294 Stone Aggregate (Single size) : cum 57.9 760
### 25 mm nominal size
### 297 Qty = 115.8 * 50 /100 810
### Stone Aggregate (Single size) : cum 57.9 1350
### 10 mm nominal size
### 297 Qty = 115.8 * 50 /100 810
### Stone Aggregate (Single size) : cum 57.9 1350
### 10 mm nominal size
### 298 Qty = 115.8 * 50 /100 810
### Stone Aggregate (Single size) : cum 57.9 1400
### 06 mm nominal size
### 2903 Qty = 115.8 * 50 /100
### Stone chippings/ screenings cum 57.9 1400
### 4.75 mm nominal size
### 2202 Qty = 289.50 * 20 /100
### Carriage of Stone aggregate below cum 289.5 106.13
### 40 mm nominal size
### MACHINERY
### 74 Drum Type HMP of 60-90 TPH hour 6 12000
### capacity @ 75 tonne per hour actual
### output @75tonne per hour actual output
### 64 Paver finisher Hydrostatic with hour 6 1500
### sensor control 100 TPH
### 69 @75tonne per hour actual output
### Generator 250 KVA hour 6 350
### 52 Front end loader 1 cum bucket capacity (incl hour 6 900
### POL) Tipper 10 tonne capacity (Taken 10Km
### 53 average lead) 450x10=4500 tonne km.
### Tipper -5 Cum tonne/ 4500 3
### km
### Add 10 per cent of cost of carriage to cover
### cost of loading and unloading
### 55 Smooth Wheeled Roller 8 to 10 tonne for hour 3.9 300
### 54 initial break down rolling.(6*0.65)
### Vibratory roller 8 to 10 tonne hour 3.9 600
### 56 for intermediate rolling.(6*0.65)
### Tandem Road Roller Finish rolling with 6-8 hour 3.9 1200
### tonnes smooth wheeled tandem roller.(6*0.65)
### LABOUR
### 28 Mate day 0.84 350.00
### 17 Beldar day 14 350.00
### working with HMP, mechanical broom,
### paver, roller, asphalt cutter and
### assistance for setting out lines, levels
### and layout of construction
### 37 Skilled Beldar (for floor rubbing etc.) for day 5 350.00
### checking line & levels
### Total:
### Add 1 % Water charges on "W"
### TOTAL
### Add GST (multiplying factor 0.1405) on "X"
### TOTAL
### Add 15 % Contractor's profit and overheads on "Y"
### Total
### Add Cess @ 1% on "Z"
### Cost for 205 cum(450 M.T.)
### Cost per cum.
### Say
###
### 16.56 Providing and laying semi- dense
### Bituminous concrete using crushed stone
### 16.56.1 25 mm compacted thickness with
### bitumen of grade VG-30 @ 5% (percentage
### Details of cost for 195 cum (450 tonnes)
### Area covered for 25 mm thickness=7800 sqm
### MATERIAL
### 7309 Paving Asphalt VG-30 of approved quality 5% tonne 22.5 39570
### 2211 of 450 MT = 22.50 MT
### Carriage of Tar bitumen tonne 22.5 106.13
###
### Aggregate
###
### Total weight of mix = 450 tonnes Weight of bitumen =
22.50 tonnes Weight of aggregate = 450 -22.50 =
###
### Taking density of aggregate = 1.5 tonne/cum Volume of
aggregate =427.50/1.5 =285cum
### Grading - II/19 mm (Nominal Size)
### 9.5 - 4.75 mm size = 57% of 285 = 162.45 cum
### 4.75mm and below = 41% of 285
### = 116.85 cum
### 296 Stone Aggregate (Single size) : 12.5 mm cum 81.225 1350
### nominal size
### Qty = 162.45 * 50 /100
### 297 Stone Aggregate (Single size) : 10 mm nominal cum 81.225 810
### size
### Qty = 162.45 * 50 /100
### 2903 Stone chippings/ screenings 4.75 mm nominal cum 116.85 1400
### 2202 size Qty = 285 * 41 /100
### Carriage of Stone aggregate below 40 mm cum 279.3 106.13
### nominal size
### Lime Filler @ 2% ( percentage by weight of
### 777 aggregate)
### Dry hydrated lime (factory made) quintal 85.5 290
### 2208 Carriage of Lime cum 6.63 106.13
### (consitering density of lime as 1.29 T per cum)
### V =8.55/1.29 = 6.63 cum MACHINERY/ HIRE
### 62 CHARGES:
### Hot mix Plant -120 TPH capacity @75tonne hour 3 15000
### 63 per hour actual output
### Hot mix Plant 100 TPH Capacity hour 3 13000
### @75tonne per hour actual output
### 64 Paver finisher Hydrostatic with sensor hour 6 1500
### control 100 TPH
### @75tonne per hour actual output
### 69 Generator 250 KVA hour 6 350
### 52 Front end loader 1 cum bucket capacity (incl hour 6 900
### POL) Tipper 10 tonne capacity (Taken 10Km
### 53 average lead) 450x10=4500 tonne km.
### Tipper -5 Cum tonne 4500 3
### Add 10 per cent of cost of carriage to cover km
###
### 55 cost of loading and unloading
### Smooth Wheeled Roller 8 to 10 tonne for initial hour 3.9 300
### break down rolling.(6*0.65)
### 54 Vibratory roller 8 to 10 tonne for intermediate hour 3.9 600
### 56 rolling.(6*0.65)
### Tandem Road Roller hour 3.9 1200
### Finish rolling with 6-8 tonnes smooth
### wheeled tandem roller.(6*0.65)
### LABOUR
### 28 Mate day 0.84 350.00
### 17 Beldar day 14 350.00
### working with HMP, mechanical broom, paver,
### roller, asphalt cutter and assistance for setting
###
### out lines, levels and layout of construction for
checking line & levels
### Total
### Add 1 % Water charges on "W" 14590.52
### TOTAL
### Add GST (multiplying factor 0.1405) on "X" 207046.82
### TOTAL
### Add 15 % Contractor's profit and overheads on "Y" 252103.45
### Total
### Add Cess @ 1% on "Z" 19327.93
### Cost for 7800 Sqm 1952121.03
### Cost per sqm 250.27
### Say 250.25
###
### 16.56.2 16.56.2 25 mm compacted
### thickness with bitumen of grade VG-30 @
### capacity.
###
### Details of cost for 195 cum (450 tonnes)
###
### Area covered for 25 mm thickness=7800 sqm
### MATERIAL
### 7309 Paving Asphalt VG-30 of approved quality 5% tonne 22.5 39570
### 2211 of 450 MT = 22.50 MT
### Carriage of Tar bitumen tonne 22.5 106.13
### Aggregate
### Total weight of mix = 450 tonnes
### Weight of bitumen = 22.50 tonnes
### Weight of aggregate = 450 -22.50 =
### 427.50 tonnes
### Taking density of aggregate = 1.5 tonne/cum
### Volume of aggregate =427.50/1.5 =285cum
### Grading - II/19 mm (Nominal Size)
### 9.5 - 4.75 mm size = 57% of 285 = 162.45 cum
### 4.75mm and below = 41% of 285 = 116.85
### cum
### 296 Stone Aggregate (Single size) : 12.5 mm cum 81.225 800
### nominal size
### Qty = 162.45 * 50 /100
### 297 Stone Aggregate (Single size) : 10 mm nominal cum 81.225 810
### size
### Qty = 162.45 * 50 /100
### 2903 Stone chippings/ screenings 4.75 mm nominal cum 116.85 1400
### size Qty = 285 * 41 /100
### 2202 Carriage of Stone aggregate below 40 mm cum 279.3 584.88
### nominal size
### Lime Filler @ 2% ( percentage by weight of
### aggregate)
### 777 Dry hydrated lime (factory made) quintal 85.5 290
### 2208 Carriage of Lime cum 6.63 106.13
### (consitering density of lime as 1.29 T per cum)
### V =8.55/1.29 = 6.63 cum
### MACHINERY/ HIRE CHARGES:
### @75tonne per hour actual output
### 74 Drum Type HMP of 60-90 TPH capacity @ hour 6 12000
### 75 tonne per hour actual output
### @75tonne per hour actual output
### 64 Paver finisher Hydrostatic with sensor control hour 6 1500
### 100 TPH
### @75tonne per hour actual output
### 69 Generator 250 KVA hour 6 350
### 52 Front end loader 1 cum bucket capacity (incl hour 6 900
### POL) Tipper 10 tonne capacity (Taken 10Km
### 53 average lead) 450x10=4500 tonne km.
### Tipper -5 Cum tonne 4500 3
### Add 10 per cent of cost of carriage to cover km
###
### 55 cost of loading and unloading
### Smooth Wheeled Roller 8 to 10 tonne for initial hour 3.9 300
### 54 break down rolling.(6*0.65)
### Vibratory roller 8 to 10 tonne for intermediate hour 3.9 600
### 56 rolling.(6*0.65)
### Tandem Road Roller hour 3.9 1200
### Finish rolling with 6-8 tonnes smooth
### wheeled tandem roller.(6*0.65)
### LABOUR
### 28 Mate day 0.84 350.00
### 17 Beldar day 14 350.00
### working with HMP, mechanical broom, paver,
### roller, asphalt cutter and assistance for setting
### out lines, levels and layout of construction
### for checking line & levels
### Total
### Add 1 % Water charges on "W"
### TOTAL
### Add GST (multiplying factor 0.1405) on "X"
### TOTAL
### Add 15 % Contractor's profit and overheads on "Y"
### Total
### Add Cess @ 1% on "Z"
### Cost for 7800 Sqm
### Cost per sqm
### Say
###
### 16.57 Providing and laying Bituminous
concrete using crushed stone aggregates
###
### 16.57.1 40/50 mm compacted thickness
### with bitumen of grade VG-30 @ 5.5%
### capacity.
###
### Details of cost for 191 cum (450 tonnes)
###
### MATERIAL
### 7309 Paving Asphalt VG-30 of approved quality tonne 24.75 39570
### @5.50% (percentage by weight of total mix
### 2211 Carriage of Tar bitumen tonne 24.75 106.13
### Aggregate
### Total weight of mix = 450 tonnes
### Weight of bitumen = 24.75 tonnes
### Weight of aggregate = 450 -24.75 =
### 425.25 tonnes
### Taking density of aggregate = 1.5 tonne/cum
### Volume of aggregate =425.25/1.5 =283.50cum
### Grading - II/19 mm (Nominal Size)
### 13.2 - 10mm size = 30% of 283.50 = 85.05
### cum
### 10 - 5mm size = 25% of 283.50 =
### 70.88 cum
### 5mm and below = 42% of 283.50 =
### 119.07 cum
### 296 Stone Aggregate (Single size) : 12.5 mm cum 42.525 800
### nominal size
### Qty = 85.5 * 50 /100
### 297 Stone Aggregate (Single size) : 10 mm nominal cum 42.525 810
### size
### Qty = 85.5 * 50 /100
### 297 Stone Aggregate (Single size) : 10 mm nominal cum 35.44 810
### size
### Qty = 70.88 * 50 /100
### 298 Stone Aggregate (Single size) : 06 mm nominal cum 35.44 810
### size
### Qty = 70.88 * 50 /100
### 2903 Stone chippings/ screenings 4.75 mm nominal cum 1400
### size 119.07 1400
### Qty = 283.5 * 40 /100 275 106.13
### 2202 Carriage of Stone aggregate below 40 mm cum 127.6 290
### nominal size 9.89 106.13
### Lime Filler @ 2% ( percentage by weight of 3 15000
### 777 aggregate) 3 13000
### Dry hydrated lime (factory made) quintal 6 1500
### 2208 Carriage of Lime cum 6 350
### (consitering density of lime as 1.29 T per cum) 6 900
### V = 12.758/1.29 = 9.89 cum 4500 3
### MACHINERY/ HIRE CHARGES:
### 62 Hot mix Plant -120 TPH capacity hour 3.9 300
### 63 Hot mix Plant 100 TPH Capacity hour 3.9 600
### 64 Paver finisher Hydrostatic with sensor control hour 3.9 1200
### 69 100 TPH
### Generator 250 KVA hour
### 52 Front end loader 1 cum bucket capacity (incl hour 900
### POL) Tipper 10 tonne capacity (Taken 10Km
### 53 average lead) 450x10=4500 tonne km.
### Tipper -5 Cum tonne
### Add 10 per cent of cost of carriage to cover km
###
### 55 cost of loading and unloading
### Smooth Wheeled Roller 8 to 10 tonne for initial hour
### break down rolling.(6*0.65)
### 54 Vibratory roller 8 to 10 tonne for intermediate hour
### 56 rolling.(6*0.65)
### Tandem Road Roller hour
### Finish rolling with 6-8 tonnes smooth
### wheeled tandem roller.(6*0.65)
### LABOUR
### 28 Mate day
### 17 Beldar working with HMP, mechanical broom, day
### paver, roller, asphalt cutter and assistance for
### setting out lines, levels and layout of
### construction
### 37 Skilled Beldar (for floor rubbing etc.) for day
### checking line & levels Total
### Add 1 % Water charges on "W"
### TOTAL
### Add GST (multiplying factor 0.1405) on "X"
### TOTAL
### Add 15 % Contractor's profit and overheads on "Y"
Total
### Add Cess @ 1% on "Z" Cost for 191 cum(450 Tonne)
### Cost per cum. 10914.38
### Say 10914.4
###
### 16.57.2 16.57.2 40/50 mm compacted
### thickness with bitumen of grade VG-30 @
### Details of cost for 191 cum (450 tonnes)
### MATERIAL
### 7309 Paving Asphalt VG-30 of approved quality tonne 24.75 39570
### @5.50% (percentage by weight of total mix
### 2211 Carriage of Tar bitumen tonne 24.75 106.13
### Aggregate
### Total weight of mix = 450 tonnes
### Weight of bitumen = 24.75 tonnes
### Weight of aggregate = 450 -24.75 =
### 425.25 tonnes
### Taking density of aggregate = 1.5 tonne/cum
### Volume of aggregate =425.25/1.5 =283.50cum
### Grading - II/19 mm (Nominal Size)
### 13.2 - 10mm size = 30% of 283.50
### = 85.05 cum
### 10 - 5mm size = 25% of 283.50 = 70.88 cum
### 5mm and below = 42% of 283.50 =
### 119.07 cum
### Waste Plastic @ 8% of the weigh of bitumen
### i.e. 24.75*8%
### 7280 Waste plastic additive tonne 1.98 40000
### 296 Stone Aggregate (Single size) : 12.5 mm cum 42.525 800
### nominal size
### Qty = 85.5 * 50 /100
### 297 Stone Aggregate (Single size) : 10 mm nominal cum 42.525 810
### size
### Qty = 85.5 * 50 /100
### 297 Stone Aggregate (Single size) : 10 mm nominal cum 35.44 810
### size
### Qty = 70.88 * 50 /100
### 298 Stone Aggregate (Single size) : 06 mm nominal cum 35.44 810
### size
### Qty = 70.88 * 50 /100
### 2903 Stone chippings/ screenings 4.75 mm nominal cum 119.07 1400
### size
### Qty = 283.5 * 40 /100
### 2202 Carriage of Stone aggregate below 40 mm cum 275 584.88
### nominal size
### Lime Filler @ 2% ( percentage by weight of
### aggregate)
### 777 Dry hydrated lime (factory made) quintal 127.6 290
### 2208 Carriage of Lime cum 9.89 106.13
### (consitering density of lime as 1.29 T per cum)
### V = 12.758/1.29 = 9.89 cum MACHINERY/
### 62 HIRE CHARGES:
### Hot mix Plant -120 TPH capacity hour 3 15000
### 63 Hot mix Plant 100 TPH Capacity hour 3 13000
### 64 Paver finisher Hydrostatic with sensor control hour 6 1500
### 100 TPH
### 69 Generator 250 KVA hour 6 350
### 52 Front end loader 1 cum bucket capacity (incl hour 6 900
### POL) Tipper 10 tonne capacity (Taken 10Km
### average lead) 450x10=4500 tonne km.
### 53 Tipper -5 Cum tonne 4500 3
### Add 10 per cent of cost of carriage to cover km
###
### cost of loading and unloading
### 55 Smooth Wheeled Roller 8 to 10 tonne for initial hour 3.9 300
### break down rolling.(6*0.65)
### 54 Vibratory roller 8 to 10 tonne for intermediate hour 3.9 600
### rolling.(6*0.65)
### 56 Tandem Road Roller hour 3.9 1200
### Finish rolling with 6-8 tonnes smooth
### wheeled tandem roller.(6*0.65)
### LABOUR
### 28 Mate day 0.84 350.00
### 17 Beldar working with HMP, mechanical broom, day 14 350.00
### paver, roller, asphalt cutter and assistance for
### setting out lines, levels and layout of
### construction
### 37 Skilled Beldar (for floor rubbing etc.) for day 5 350.00
### checking line & levels
### Total
### Add 1 % Water charges on "W"
### TOTAL
### Add GST (multiplying factor 0.1405) on "X"
### TOTAL
### Add 15 % Contractor's profit and overheads on "Y"
### Total
### Add Cess @ 1% on "Z"
### Cost for 191 cum(450 Tonne)
### Cost per cum.
### Say
###
###
### 16.57.3 40/50 mm compacted thickness
### with bitumen of grade PMB-40 @ 5.5%
### capacity.
### Details of cost for 191 cum (450 tonnes)
###
### MATERIAL
### 312 Bitumen grade PMB - 40 M.T. 24.75 52000
### @5.50% (percentage by weight of total mix
### 2211 Carriage of Tar bitumen tonne 24.75 106.13
### Aggregate
### Total weight of mix = 450 tonnes
### Weight of bitumen = 24.75 tonnes
### Weight of aggregate = 450 -24.75 =
### 425.25 tonnes
### Taking density of aggregate = 1.5 tonne/cum
### Volume of aggregate =425.25/1.5 =283.50cum
### Grading - II/19 mm (Nominal Size)
### 13.2 - 10mm size = 30% of 283.50 = 85.05
### cum
### 10 - 5mm size = 25% of 283.50
### = 70.88 cum
### 5mm and below = 42% of 283.50
### = 119.07 cum
### 296 Stone Aggregate (Single size) : 12.5 mm cum 42.525 1350
### nominal size
### Qty = 85.5 * 50 /100
### 297 Stone Aggregate (Single size) : 10 mm nominal cum 42.525 810
### size
### Qty = 85.5 * 50 /100
### 297 Stone Aggregate (Single size) : 10 mm nominal cum 35.44 810
### size
### Qty = 70.88 * 50 /100
### 298 Stone Aggregate (Single size) : 06 mm nominal cum 35.44 810
### size
### Qty = 70.88 * 50 /100
### 2903 Stone chippings/ screenings 4.75 mm nominal cum 119.07 1400
### size
### Qty = 283.5 * 40 /100
### 2202 Carriage of Stone aggregate below 40 mm cum 275 584.88
### nominal size
### Lime Filler @ 2% ( percentage by weight of
### 777 aggregate)
### Dry hydrated lime (factory made) quintal 127.6 290
### 2208 Carriage of Lime cum 9.89 106.13
### (consitering density of lime as 1.29 T per cum)
### V = 12.758/1.29 = 9.89 cum MACHINERY/
### 62 HIRE CHARGES:
### Hot mix Plant -120 TPH capacity hour 3 15000
### 63 Hot mix Plant 100 TPH Capacity hour 3 13000
### 64 Paver finisher Hydrostatic with sensor control hour 6 1500
### 100 TPH
### 69 Generator 250 KVA hour 6 350
### 52 Front end loader 1 cum bucket capacity (incl hour 6 900
### POL) Tipper 10 tonne capacity (Taken 10Km
### average lead) 450x10=4500 tonne km.
### 53 Tipper -5 Cum tonne 4500 3
### Add 10 per cent of cost of carriage to cover km
###
### cost of loading and unloading
### 55 Smooth Wheeled Roller 8 to 10 tonne for initial hour 3.9 300
### break down rolling.(6*0.65)
### 54 Vibratory roller 8 to 10 tonne for intermediate hour 3.9 600
### rolling.(6*0.65)
### 56 Tandem Road Roller hour 3.9 1200
### Finish rolling with 6-8 tonnes smooth
### wheeled tandem roller.(6*0.65)
### LABOUR
### 28 Mate day 0.84 350.00
### 17 Beldar working with HMP, mechanical broom, day 14 350.00
### paver, roller, asphalt cutter and assistance for
### setting out lines, levels and layout of
### construction
### 37 Skilled Beldar (for floor rubbing etc.) for day 5 350.00
### checking line & levels
### Total
### Add 1 % Water charges on "W"
### TOTAL
### Add GST (multiplying factor 0.1405) on "X"
### TOTAL
### Add 15 % Contractor's profit and overheads on "Y"
### Total
### Add Cess @ 1% on "Z"
### Cost for 191 cum(450 Tonne)
### Cost per cum.
### Say
###
### 16.57.4 40/50 mm compacted thickness
### with bitumen of grade CRMB-60 @ 5.5%
### capacity.
###
### Details of cost for 191 cum (450 tonnes)
###
### MATERIAL
###
### 7741 Modified Bitumen Refinary produced tonne 24.75 30536
###
### CRMB - 60
### @5.50% (percentage by weight of total mix
### 2211 Carriage of Tar bitumen tonne 24.75 106.13
### Aggregate
### Total weight of mix = 450 tonnes
### Weight of bitumen = 24.75 tonnes
### Weight of aggregate = 450 -24.75 =
### 425.25 tonnes
### Taking density of aggregate = 1.5 tonne/cum
### Volume of aggregate =425.25/1.5
### =283.50cum
### Grading - II/19 mm (Nominal Size)
### 13.2 - 10mm size = 30% of 283.50
### = 85.05 cum
### 10 - 5mm size = 25% of 283.50 = 70.88 cum
### 5mm and below = 42% of 283.50 =
### 119.07 cum
### 296 Stone Aggregate (Single size) : 12.5 mm cum 42.525 800
### nominal size
### Qty = 85.5 * 50 /100
### 297 Stone Aggregate (Single size) : 10 mm nominal cum 42.525 810
### size
### Qty = 85.5 * 50 /100
### 297 Stone Aggregate (Single size) : 10 mm nominal cum 35.44 810
### size
### Qty = 70.88 * 50 /100
### 298 Stone Aggregate (Single size) : 06 mm nominal cum 35.44 810
### size
### Qty = 70.88 * 50 /100
### 2903 Stone chippings/ screenings 4.75 mm nominal cum 119.07 1400
### size
### Qty = 283.5 * 40 /100
### 2202 Carriage of Stone aggregate below 40 mm cum 275 584.88
### nominal size
### Lime Filler @ 2% ( percentage by weight of
### aggregate)
### 777 Dry hydrated lime (factory made) quintal 127.6 290
### 2208 Carriage of Lime cum 9.89 106.13
### (consitering density of lime as 1.29 T per cum)
### V = 12.758/1.29 = 9.89 cum MACHINERY/
### HIRE CHARGES:
### 62 Hot mix Plant -120 TPH capacity hour 3 15000
### 63 Hot mix Plant 100 TPH Capacity hour 3 13000
### 64 Paver finisher Hydrostatic with sensor control hour 6 1500
### 100 TPH
### 69 Generator 250 KVA hour 6 350
### 52 Front end loader 1 cum bucket capacity (incl hour 6 900
### POL) Tipper 10
###
### tonne capacity (Taken 10Km average lead)
###
### 450x10=4500 tonne km.
### 53 Tipper -5 Cum tonne 4500 3
### Add 10 per cent of cost of carriage to cover km
###
### cost of loading and unloading
### 55 Smooth Wheeled Roller 8 to 10 tonne for initial hour 3.9 300
### break down rolling.(6*0.65)
### 54 Vibratory roller 8 to 10 tonne for intermediate hour 3.9 600
### rolling.(6*0.65)
### 56 Tandem Road Roller hour 3.9 1200
### Finish rolling with 6-8 tonnes smooth
### wheeled tandem roller.(6*0.65)
### LABOUR
### 28 Mate day 0.84 350.00
### 17 Beldar working with HMP, mechanical broom, day 14 350.00
### paver, roller, asphalt cutter and assistance for
### setting out lines, levels and layout of
### construction
### 37 Skilled Beldar (for floor rubbing etc.) for day 5 350.00
### checking line & levels
### Total
### Add 1 % Water charges on "W"
### TOTAL
### Add GST (multiplying factor 0.1405) on "X"
### TOTAL
### Add 15 % Contractor's profit and overheads on "Y"
### Total
### Add Cess @ 1% on "Z"
### Cost for 191 cum(450 Tonne)
### Cost per cum.
### Say
###
### 16.57.5 40/50 mm compacted thickness
### with bitumen of grade VG-30 @ 5.5%
### capacity.
###
### Details of cost for 191 cum (450 tonnes)
###
### MATERIAL
### 7309 Paving Asphalt VG-30 of approved quality tonne 24.75 39570
### @5.50% (percentage by weight of total mix
### 2211 Carriage of Tar bitumen tonne 24.75 106.13
### Aggregate
### Total weight of mix = 450 tonnes
### Weight of bitumen = 24.75 tonnes
### Weight of aggregate = 450 -24.75
### = 425.25 tonnes
### Taking density of aggregate = 1.5 tonne/cum
### Volume of aggregate =425.25/1.5
### =283.50cum
### Grading - II/19 mm (Nominal Size)
### 13.2 - 10mm size = 30% of 283.50
### = 85.05 cum
### 10 - 5mm size = 25% of 283.50 = 70.88 cum
### 5mm and below = 42% of 283.50
### = 119.07 cum
### 296 Stone Aggregate (Single size) : 12.5 mm cum 42.525 1350
### nominal size
### Qty = 85.5 * 50 /100
### 297 Stone Aggregate (Single size) : 10 mm nominal cum 42.525 810
### size
### Qty = 85.5 * 50 /100
### 297 Stone Aggregate (Single size) : 10 mm nominal cum 35.44 810
### size
### Qty = 70.88 * 50 /100
### 298 Stone Aggregate (Single size) : 06 mm nominal cum 35.44 810
### size
### Qty = 70.88 * 50 /100
### 2903 Stone chippings/ screenings 4.75 mm nominal cum 119.07 1400
### size
### Qty = 283.5 * 40 /100
### 2202 Carriage of Stone aggregate below 40 mm cum 275 584.88
### nominal size
### Lime Filler @ 2% ( percentage by weight of
### aggregate)
### 777 Dry hydrated lime (factory made) quintal 127.6 290
### 2208 Carriage of Lime cum 9.89 106.13
### (consitering density of lime as 1.29 T per cum)
### V = 12.758/1.29 = 9.89 cum MACHINERY/
### HIRE CHARGES:
### 74 Drum Type HMP of 60-90 TPH capacity hour 6 12000
### @ 75 tonne per hour actual output
### 64 Paver finisher Hydrostatic with sensor control hour 6 1500
### 100 TPH
### 69 Generator 250 KVA hour 6 350
### 52 Front end loader 1 cum bucket capacity (incl hour 6 900
### POL) Tipper 10
### tonne capacity (Taken 10Km average lead)
### 450x10=4500 tonne km.
### (incl POL)
### 53 Tipper -5 Cum tonne 4500 3
### Add 10 per cent of cost of carriage to cover km
### cost of loading and unloading
### 55 Smooth Wheeled Roller 8 to 10 tonne for initial hour 3.9 300
### break down rolling.(6*0.65)
### 54 Vibratory roller 8 to 10 tonne for intermediate hour 3.9 600
### rolling.(6*0.65)
### 56 Tandem Road Roller hour 3.9 1200
### Finish rolling with 6-8 tonnes smooth wheeled
### tandem roller.(6*0.65)
### LABOUR
### 28 Mate day 0.84 350.00
### 17 Beldar working with HMP, mechanical broom, day 14 350.00
### paver, roller, asphalt cutter and assistance for
### setting out lines, levels and layout of
### construction
### 37 Skilled Beldar (for floor rubbing etc.) day 5 350.00
### for checking line & levels
### Total
### Add 1 % Water charges on "W"
### TOTAL
### Add GST (multiplying factor 0.1405) on "X"
### TOTAL
### Add 15 % Contractor's profit and overheads on "Y"
### Total
### Add Cess @ 1% on "Z"
### Cost for 191 cum(450 Tonne)
### Cost per cum.
### Say
###
### 16.57.6 40/50 mm compacted thickness
### with bitumen of grade VG-30 @ 5.5%
### Details of cost for 191 cum (450 tonnes)
### MATERIAL
### 7309 Paving Asphalt VG-30 of approved quality tonne 24.75 39570
### @5.50% (percentage by weight of total mix
### 2211 Carriage of Tar bitumen tonne 24.75 106.13
### Waste Plastic @ 8% of the weigh of bitumen
### 7280 i.e. 24.75*8%
### Waste plastic additive tonne 1.98 40000
###
### Aggregate
###
### Total weight of mix = 450 tonnes
###
### Weight of bitumen = 24.75 tonnes
### Weight of aggregate = 450 -24.75 =
### 425.25 tonnes
### Taking density of aggregate = 1.5 tonne/cum
### Volume of aggregate =425.25/1.5
### =283.50cum
### Grading - II/19 mm (Nominal Size)
### 13.2 - 10mm size = 30% of 283.50
### = 85.05 cum
### 10 - 5mm size = 25% of 283.50 = 70.88 cum
### 5mm and below = 42% of 283.50
### = 119.07 cum
### 296 Stone Aggregate (Single size) : 12.5 mm cum 42.525 1350
### nominal size
### Qty = 85.5 * 50 /100
### 297 Stone Aggregate (Single size) : 10 mm nominal cum 42.525 810
### size
### Qty = 85.5 * 50 /100
### 297 Stone Aggregate (Single size) : 10 mm nominal cum 35.44 810
### size
### Qty = 70.88 * 50 /100
### 298 Stone Aggregate (Single size) : 06 mm nominal cum 35.44 810
### size
### Qty = 70.88 * 50 /100
### 2903 Stone chippings/ screenings 4.75 mm nominal cum 119.07 1400
### size
### Qty = 283.5 * 40 /100
### 2202 Carriage of Stone aggregate below 40 mm cum 275 584.88
### nominal size
### Lime Filler @ 2% ( percentage by weight of
### 777 aggregate)
### Dry hydrated lime (factory made) quintal 127.6 290
### 2208 Carriage of Lime cum 9.89 106.13
### (consitering density of lime as 1.29 T per cum)
### V = 12.758/1.29 = 9.89 cum MACHINERY/
### HIRE CHARGES:
### 74 Drum Type HMP of 60-90 TPH capacity @ 75 hour 6 12000
### tonne per hour actual output
### 64 Paver finisher Hydrostatic with sensor control hour 6 1500
### 100 TPH
### 69 Generator 250 KVA hour 6 350
### 52 Front end loader 1 cum bucket capacity (incl hour 6 900
### POL) Tipper 10
### tonne capacity (Taken 10Km average lead)
### 450x10=4500 tonne km.
### 53 Tipper -5 Cum tonne 4500 3
### Add 10 per cent of cost of carriage to cover km
###
### cost of loading and unloading
### 55 Smooth Wheeled Roller 8 to 10 tonne for initial hour 3.9 300
### break down rolling.(6*0.65)
### 54 Vibratory roller 8 to 10 tonne for intermediate hour 3.9 600
### 56 rolling.(6*0.65)
### Tandem Road Roller hour 3.9 1200
### Finish rolling with 6-8 tonnes smooth wheeled
### tandem roller.(6*0.65)
### LABOUR
### 28 Mate day 0.84 350.00
### 17 Beldar working with HMP, mechanical broom, day 14 350.00
### paver, roller, asphalt cutter and assistance for
### setting out lines, levels and layout of
### construction
### 37 Skilled Beldar (for floor rubbing etc.) day 5 350.00
### for checking line & levels Total
### Add 1 % Water charges on "W"
### TOTAL
### Add GST (multiplying factor 0.1405) on "X"
### TOTAL
### Add 15 % Contractor's profit and overheads on "Y"
### Total
### Add Cess @ 1% on "Z"
### Cost for 191 cum(450 Tonne)
### Cost per cum.
### Say
###
###
### 16.57.7 40/50 mm compacted thickness
### with bitumen of grade PMB-40 @ 5.5%
### capacity.
###
### Details of cost for 191 cum (450 tonnes)
###
### MATERIAL
### 312 Bitumen grade PMB - 40 M.T. 24.75 52000
### @5.50% (percentage by weight of total mix
### 2211 Carriage of Tar bitumen tonne 24.75 106.13
###
### Aggregate
###
### Total weight of mix = 450 tonnes Weight of bitumen =
24.75 tonnes Weight of aggregate = 450 -24.75 =
###
### Taking density of aggregate = 1.5 tonne/cum Volume
of aggregate =425.25/1.5 =283.50cum
### Grading - II/19 mm (Nominal Size)
### 13.2 - 10mm size = 30% of 283.50 = 85.05
### cum
### 10 - 5mm size = 25% of 283.50 =
### 70.88 cum
### 5mm and below = 42% of 283.50 =
### 119.07 cum
### 296 Stone Aggregate (Single size) : 12.5 mm cum 42.525 800
### nominal size
### Qty = 85.5 * 50 /100
### 297 Stone Aggregate (Single size) : 10 mm nominal cum 42.525 810
### size
### Qty = 85.5 * 50 /100
### 297 Stone Aggregate (Single size) : 10 mm nominal cum 35.44 810
### size
### Qty = 70.88 * 50 /100
### 298 Stone Aggregate (Single size) : 06 mm nominal cum 35.44 810
### size
### Qty = 70.88 * 50 /100
### 2903 Stone chippings/ screenings 4.75 mm nominal cum 119.07 1400
### size
### Qty = 283.5 * 40 /100
### 2202 Carriage of Stone aggregate below 40 mm cum 275 584.88
### nominal size
### Lime Filler @ 2% ( percentage by weight of
### aggregate)
### 777 Dry hydrated lime (factory made) quintal 127.6 290
### 2208 Carriage of Lime cum 9.89 106.13
### (consitering density of lime as 1.29 T per cum)
### V = 12.758/1.29 = 9.89 cum MACHINERY/
### HIRE CHARGES:
### 74 Drum Type HMP of 60-90 TPH capacity @ 75 hour 6 12000
### tonne per hour actual output
### 64 Paver finisher Hydrostatic with sensor control hour 6 1500
### 100 TPH
### 69 Generator 250 KVA hour 6 350
### 52 Front end loader 1 cum bucket capacity (incl hour 6 900
### POL) Tipper 10
### tonne capacity (Taken 10Km average lead)
### 450x10=4500 tonne km.
### 53 Tipper -5 Cum tonne 4500 3
### Add 10 per cent of cost of carriage to cover km
###
### cost of loading and unloading
### 55 Smooth Wheeled Roller 8 to 10 tonne for initial hour 3.9 300
### break down rolling.(6*0.65)
### 54 Vibratory roller 8 to 10 tonne for intermediate hour 3.9 600
### rolling.(6*0.65)
### 56 Tandem Road Roller hour 3.9 1200
### Finish rolling with 6-8 tonnes smooth wheeled
### tandem roller.(6*0.65)
### LABOUR
### 28 Mate day 0.84 350.00
### 17 Beldar working with HMP, mechanical broom, day 14 350.00
### paver, roller, asphalt cutter and assistance for
### setting out lines, levels and layout of
### construction
### 37 Skilled Beldar (for floor rubbing etc.) for day 5 350.00
### checking line & levels
### Total
### Add 1 % Water charges on "W"
### TOTAL
### Add GST (multiplying factor 0.1405) on "X"
### TOTAL
### Add 15 % Contractor's profit and overheads on "Y"
### Total
### Add Cess @ 1% on "Z"
### Cost for 191 cum(450 Tonne)
### Cost per cum.
### Say
###
### 16.57.8 40/50 mm compacted thickness
### with bitumen of grade CRMB-60 @ 5.5%
### capacity.
###
### Details of cost for 191 cum (450 tonnes)
###
### MATERIAL
### 7741 Modified Bitumen Refinary produced tonne 24.75 30536
### CRMB - 60
### @5.50% (percentage by weight of total mix
### 2211 Carriage of Tar bitumen tonne 24.75 106.13
### Aggregate
### Total weight of mix = 450 tonnes
### Weight of bitumen = 24.75 tonnes
### Weight of aggregate = 450 -24.75 =
### 425.25 tonnes
### Taking density of aggregate = 1.5 tonne/cum
### Volume of aggregate =425.25/1.5 =
### 283.50cum
### Grading - II/19 mm (Nominal Size)
### 13.2 - 10mm size = 30% of 283.50 =
### 85.05 cum
### 10 - 5mm size = 25% of 283.50 = 70.88 cum
### 5mm and below = 42% of 283.50 =
### 119.07 cum
### 296 Stone Aggregate (Single size) : 12.5 mm cum 42.525 800
### nominal size
### Qty = 85.5 * 50 /100
### 297 Stone Aggregate (Single size) : 10 mm nominal cum 42.525 810
### size
### Qty = 85.5 * 50 /100
### 297 Stone Aggregate (Single size) : 10 mm nominal cum 35.44 810
### size
### Qty = 70.88 * 50 /100
### 298 Stone Aggregate (Single size) : 06 mm nominal cum 35.44 810
### size
### Qty = 70.88 * 50 /100
### 2903 Stone chippings/ screenings 4.75 mm nominal cum 119.07 1400
### size
### Qty = 283.5 * 40 /100
### 2202 Carriage of Stone aggregate below 40 mm cum 275 584.88
### nominal size
### Lime Filler @ 2% ( percentage by weight of
### aggregate)
### 777 Dry hydrated lime (factory made) quintal 127.6 290
### 2208 Carriage of Lime cum 9.89 106.13
### (consitering density of lime as 1.29 T per cum)
### V = 12.758/1.29 = 9.89 cum MACHINERY/
### HIRE CHARGES:
### 74 Drum Type HMP of 60-90 TPH capacity @ 75 hour 6 12000
### tonne per hour actual output
### 64 Paver finisher Hydrostatic with sensor control hour 6 1500
### 100 TPH
### 69 Generator 250 KVA hour 6 350
### 52 Front end loader 1 cum bucket capacity (incl hour 6 900
### POL) Tipper 10
### tonne capacity (Taken 10Km average lead)
### 450x10=4500 tonne km.
### 53 Tipper -5 Cum tonne 4500 3
### Add 10 per cent of cost of carriage to cover km
###
### cost of loading and unloading
### 55 Smooth Wheeled Roller 8 to 10 tonne for initial hour 3.9 300
### break down rolling.(6*0.65)
### 54 Vibratory roller 8 to 10 tonne for intermediate hour 3.9 600
### rolling.(6*0.65)
### 56 Tandem Road Roller hour 3.9 1200
### Finish rolling with 6-8 tonnes smooth
### wheeled tandem roller.(6*0.65)
### LABOUR
### 28 Mate day 0.84 350.00
### 17 Beldar working with HMP, mechanical broom, day 14 350.00
### paver, roller, asphalt cutter and assistance for
### setting out lines, levels and layout of
### construction
### 37 Skilled Beldar (for floor rubbing etc.) for day 5 350.00
### checking line & levels
### Total
### Add 1 % Water charges on "W"
### TOTAL
### Add GST (multiplying factor 0.1405) on "X"
### TOTAL
### Add 15 % Contractor's profit and overheads on "Y"
### Total
### Add Cess @ 1% on "Z"
### Cost for 191 cum(450 Tonne)
### Cost per cum.
### Say
###
###
### 16.59 Manufacturing, supplying and fixing
### retro reflective sign boards made up of 2
###
###
###
### 16.59.1 Mandatory/ Regulatory sign boards of 900
### mm diametre
Detailswith support
cost for 1 no. oflength of 3750
0.636 sqm
###
### MATERIAL
###
### Aluminium sheet 2 mm thick
###
### 3.14/4x(0.9)x(0.9)=0.636 sqm
###
### add 10% wastage = 0.064 i.e. 0.700sqm @ 5.60kg/
sqm = 3.92kg
### 2704 Aluminium Strip 40 mm wide and 2 mm thick kilogra 3.92 240
### m
### 2302 Carriage of G.I. sheet and accessories tonne 0.00392 94.34
### 3.92kg or 0.00392 MT
### High intensity retro reflective sheet = 0.70 sqm.
### High intensity sheet for lettering / sign and
### border etc.
### Taking 40% Area =0.28sqm,total = 0.70 +
### 0.28 = 0.98 sqm
### 8690 High intensity retro - reflective sheet sqm 0.98 1300
### Steel work
### Supporting frame 25x25x3mm for 900mm dia
### board:-
### 3.14D=3.1416x0.90=2.83 metre
### @ 1.10kg/m =3.11kg
### Angle iron 35x35x.5mm for fixing the support
### frame with vertical Tee-iron support post
### 2x0.05=0.10m @ 2.6 kg/m = 0.26kg
### Vertical post of M.S. tee of section
### ISNT 50x50x6mm = 3.75 metre
### @ 4.50kg/m = 16.88 kg
### Bass plate to be welded at bottom end of tee
### (As hold fast)
### (100x100x5mm)x7850/133)=0.39kg, total =
### 3.11 + 0.26 +16.88 + 0.39 = 20.64kg.
### Add wastage @ 5% = 1.03
### Total = 20.64 + 1.03 = 21.67kg.
### 10.2 Rate as per item no 10.2 of SH : Steel work kg 21.67 96.50
### LABOUR
### 28 Mate day 0.01 350.00
### 17 Beldar day 0.25 350.00
### 9999 Cost of material for drilling holes, nut bolts & L.S. 65 2
### rivets, fabrication etc.
### Painting with synthetic enamel paint on steel
###
### work
### support frame 25x25x3mm =2.83x0.10=0.283
###
### sqm
### Fixing angle 35x35x5mm = 2x0.50x0.14=0.014 sqm
###
### Vertical post Tee 50x50x6mm =3.75x0.20=0.750sqm
### Base plate 100x100x5mm
###
### Surface area = 2x[0.10x0.10] =0.02 4x0.10x0.005 =
0.002
###
### Total = 1.069 sqm
### 13.61.1 Rate as per item no 13.61.1 of SH : Finishing sqm 1.07 82.4
### Painting with epoxy paint on back side of
### aluminium sheet.
### 13.52.1 Rate as per Item no. 13.52.1 of SH: Finishing sqm 0.636 132.5
### 9999 Sundries and hold fast etc. L.S. 78 2
### Total
### Add 1 % Water charges on "W-A" 2584.59
### TOTAL
### Add GST (multiplying factor 0.1405) on "X" 2610.43
### TOTAL
### Add 15 % Contractor's profit and overheads on 2977.2
### "Y"
### Total
### Add Cess @ 1% on "Z" 3423.78
### Cost of 1 no.
### Say
###
###
### 16.59.2 Cautionary /warning sign boards of
### equilateral triangular shape having each
### Details cost for 1 board of 0.35 sqm
### MATERIAL
### Aluminium sheet 2 mm thick Area
### 1/2x(0.9)x(0.78)=0.35 sqm
### add 10% wastage = 0.04 i.e. 0.39sqm @
### 5.60kg/ sqm = 2.18kg
### 2704 Aluminium Strip 40 mm wide and 2 mm thick kilogra 2.18 240
### m
### 2302 Carriage of G.I. sheet and accessories tonne 0.00218 94.34
### 2.18kg or 0.00218 MT
### High intensity retro reflective sheet = 0.39 sqm.
### High intensity sheet for lettering / sign/ symbol/
### border etc.
### Taking 40% Area =0.16sqm, total = 0.39 + 0.16
### = 0.55 sqm
### 8690 High intensity retro - reflective sheet sqm 0.55 1300
###
### Steel work
###
### Angle iron frame 25x25x3mm 3x0.90= 2.70 metre
### @ 1.10kg/m =2.97kg
###
### Angle iron 35x35x.5mm for fixing the support frame
to Tee- iron support post 2x0.05=0.10m @ 2.6 kg/m =
###
### Vertical post of M.S. tee of section
### ISNT 50x50x6mm = 1x3.65=3.65m @
### 4.50kg/m =16.43kg
### Bass plate 100x100x5mm connected to bottom
### end of vertocal tee.
### (0.10x0.10x0.005x7850kg =0.39kg, total = 2.97
### + 0.26 + 16.43 + 0.39 = 20.05kg.
### Add wastage @ 5% = 1.00, total = 20.05 +
### 1.00 = 21.05kg
### 10.2 Rate as per item no 10.2 of SH : Steel work kg 21.05 96.50
### LABOUR
### 28 Mate day 0.01 350.00
### 17 Beldar day 0.25 350.00
### 9999 Cost of material for drilling holes, nut bolts & L.S. 65 2
### rivets, fabrication etc.
### Painting with synthetic enamel paint on Angle
### iron .
### support frame 25x25x3mm =1x2.7x0.10=0.27
### sqm.
### Angle 35x35x5mm
### = 2x0.50x0.14=0.014 sqm
### Tee 50x50x6mm
### =1x3.65x0.20 =0.73sqm
### Base plate to be welded at bottom end of
### Tee 100x100x5mm
### 0.022 sqm
### Total = 1.036 sqm
### 13.61.1 Rate as per item no 13.61.1 of SH : Finishing sqm 1.036 82.4
### Painting with epoxy paint on back side of
### aluminium sheet. 0.35 sqm
### 13.52.1 Rate as per Item no. 13.52.1 of SH: Finishing sqm 0.35 132.5
### 9999 Sundries & hold fast etc. L.S. 65 2
### Total
### Add 1 % Water charges on "W-A" 1581.82
### TOTAL
### Add GST (multiplying factor 0.1405) on "X-A" 1597.64
### TOTAL
### Add 15 % Contractor's profit and overheads on 1822.11
### "Y-A"
### Total
### Add Cess @ 1% on "Z-A" 2095.42
### Cost of 1 board.
### Say
###
###
### 16.60 Manufacturing, supplying and fixing
### retro reflective overhead signage boards
###
###
### Rectangular area of the sheet only shall be
### measured for payment).
### 16.60.1 Overhead informatory road signage
###
### Details of cost for boards area 3.00x1.20
### =3.60 sqm
### MATERIAL
### 2704 Aluminium Strip 40 mm wide and 2 mm thick kilogra 21.17 240
### Add 5% wastage = 1.01 kg m
### Total = 20.16 + 1.01 = 21.17 kg.
### 2302 Carriage of G.I. sheet and accessories high tonne 0.02117 94.34
### itensity sheet for written matter.
### Taking 40% 3.60x40% = 1.44 sqm.
### Total = 3.60 + 1.44 = 5.04 sqm.
### 8690 High intensity retro - reflective sheet sqm 5.04 1300
### 588 Chromium plated Brass screws 25 mm for 100 0.34 180
### peripheries = 2x(300+120)/30=28 nos. Nos
### For vertical Rows = 2x (120/30-2)=4 nos.
### Total= 28 + 4 = 32nos.
### For wastage @ 5% =2 nos.
### Total = 32 +2 = 34 nos.
### Labour charges for drilling holes
### 9999 Hire charges of drill machine and sundries L.S. 52 2
### 9999 Hoisting board L.S. 390 2
### Labour charges for manufacturing of board
### including .
### 9999 fixing retro reflective sheet L.S. 564.2 2
### Painting with epoxy paint on back side of
### Aluminium sheet,
### 13.52.1 Rate as per Item no. 13.52.1 of SH: Finishing sqm 3.6 132.5
### Total
### Add 1 % Water charges on "W-A" 13708.4
### TOTAL
### Add GST (multiplying factor 0.1405) on "X-A" 13845.48
### TOTAL
### Add 15 % Contractor's profit and overheads on 15790.77
### "Y-A"
### Total
### Add Cess @ 1% on "Z-A" 18159.39
### Cost of 3.60 sqm
### Cost of 1 sqm.
### Say
###
### 16.61 Providing Retro-reflective regulatory
### sign board of size 900 mm dia meter made
###
###
### Details cost for one board of 0.635 sqm Aluminium
sheet 2mm thick = 0.635 sqm. Add 10% wastage =
### 0.06 = 0.695 sqm.
### Say 0.70 sqm @ 5.6kg/sqm = 3.98 kg
###
### MATERIAL
###
### 2704 Aluminium Strip 40 mm wide and 2 mm thick kilogra 3.98 240
### High intensity retro reflective sheet = 0.70 sqm m
### high intensity sheet for lettering/ sing and
### border etc.
### Taking 40% Area=0.28 sqm, total = 0.70 + 0.28
### = 0.98 sqm.
### 8690 High intensity retro - reflective sheet sqm 0.98 1300
###
### Angle iron 40x40x4mm = 4x0.60=2.40@
### 2.4kg/ mtr = 5.76 kg
### 50x50x5 mm = 2x4m =8m @ 3kg/ mtr
### =24.00 kg
### Total = 5.76 + 24.00 = 29.76 kg
### 10.2 Rate as per item no 10.2 of SH : Steel work kg 29.76 96.50
### LABOUR
### 28 Mate day 0.01 350.00
### 17 Beldar day 0.25 350.00
### 9999 Cost of material for drilling holes, nut bolts & L.S. 70.23 2
### rivets, facrication etc. @ 2% on ( X + Y + A).
### (e) Painting with synthetic enamel paint
### 1x2.40.12=0.29 sqm
### 1x4.00x0.12=0.80 sqm,
### Total = 0.29 + 0.80 = 1.09 sqm
### 13.61.1 Rate as per item no 13.61.1 of SH : Finishing sqm 1.09 82.4
### 13.52.1 Painting with epoxy paint on back side of sqm 0.635 132.5
### aluminium sheet, Rate as per Item no. 13.52.1
### of SH: Finishing
### 9999 Sundries & hole fast etc, L.S. 31.2 2
### Total
### Add 1 % Water charges on "W-A" 2515.48
### TOTAL
### Add GST (multiplying factor 0.1405) on "X-A" 2540.63
### TOTAL
### Add 15 % Contractor's profit and overheads on 2897.59
### "Y-A"
### Total
### Add Cess @ 1% on "Z-A" 3332.23
### Cost for 1 board
### Say
###
### 16.62 Providing and applying 2.5 mm thick
### road marking strips (retro- reflective) of
### Details of cost for 200 sqm (Area covered on one
day):-
### MATERIAL
### Thermoplastic paint screeded in paint form for
### 2.5 mm thick road making stripe including
### glass beads etc. as pe specifications
### 200 sqm @ 5kg/ sqm = 1000 kg
### Wastage @ 5% = 50kg
### Total = 1050 kg
### 8687 Thermoplastic paint kg 1050 65
### Glass beads (B-class) to be sprayed over the
### paint stripe @ 250 gms. Per sqm =
### 100x0.25=25 kg
### 8688 Glass beads kg 50 70
### MACHINERY
### 33 Paint applicator. day 1 750
### 78 Hire charges of TATA 407 or equivalent for day 1 1200
### local shifting.
### 1241 Commercial LPG in cylinder. kg 142 82
### LABOUR
### 42 Operator (Pile/ Special machine) day 1 421.17
### 37 Skilled Beldar (for floor rubbing etc.) day 4 350.00
### 17 Beldar day 4 350.00
### Total
### Add 1 % Water charges on "W"
### TOTAL
### Add GST (multiplying factor 0.1405) on "X"
### TOTAL
### Add 15 % Contractor's profit and overheads on "Y"
### Total
### Add Cess @ 1% on "Z"
### Cost for 200 sqm
### Cost per sqm
### Say
###
###
###
### 16.63 Providing, laying and making kerb
### channel 30 cm wide and 50 mm thick with
### Details of cost for 10 sqm.
### METERIAL
### 287 Brick Aggregate (Single size) : 40 mm nominal cum 1 650
### size
### 2260 Carriage of Brick aggregate cum 1 115.36
### 6501 Sand zone V (Jamuna) cum 0.08 800
### 2335 Carriage of Sand cum 0.08 106.13
### Labour for spreading, ramming and
### consolidation.
### 17 Beldar day 0.35 350.00
### 18 Coolie day 0.26 350.00
### 11 Bhisti day 0.18 350.00
### Cement concrete-1:3:6
### 4.1.6 Rate as per item no 4.1.6 of SH : Concrete cum 0.5 5291.95
### Work
### Total
### Add 1 % Water charges on "W-A" 1125.3
### TOTAL
### Add GST (multiplying factor 0.1405) on "X-A" 1136.56
### TOTAL
### Add 15 % Contractor's profit and overheads on 1296.24
### "Y-A"
### Total
### Add Cess @ 1% on "Z-A" 1490.68
### Cost for 10 sqm.
### Cost for 1 sqm.
### Say
###
### 16.64 Providing and laying 75 mm thick
### compactedofbed of dry brick aggregate of 40
Engineer-in-charge.
### Details of cost for 10 sqm.
### METERIAL
### 287 Brick Aggregate (Single size) : 40 mm nominal cum 1 650
### size
### 2260 Carriage of Brick aggregate cum 1 115.36
### 6501 Sand zone V (Jamuna) cum 0.08 800
### 2335 Carriage of Sand cum 0.08 106.13
### Labour for spreading, ramming and
### consolidation.
### 17 Beldar day 0.35 350.00
### 18 Coolie day 0.26 350.00
### 11 Bhisti day 0.18 350.00
### Total
### Add 1 % Water charges on "W"
### TOTAL
### Add GST (multiplying factor 0.1405) on "X"
### TOTAL
### Add 15 % Contractor's profit and overheads on "Y"
### Total
### Add Cess @ 1% on "Z"
### Cost for 10 sqm.
### Cost for 1 sqm.
### Say
###
### 16.65 Providing and fixing post delineators
### made of ABS round body fitted with 2 nos
### Details of cost for 1 no.
### MATERIAL
### 8685 Delineator each 1 300
### 9999 Fixing materials. L.S. 78 2
### 9999 Fixing charges. L.S. 39 2
### Total
### Add 1 % Water charges on "W"
### TOTAL
### Add GST (multiplying factor 0.1405) on "X"
### TOTAL
### Add 15 % Contractor's profit and overheads on "Y"
### Total
### Add Cess @ 1% on "Z"
### Cost of 1 no.
### Say
###
###
###
### 16.66 Excavating holes upto 0.10 cum,
### including getting out the excavated soil,
### 16.66.1 All kind of soil
###
### Details of cost for 30 holes-
### Earth work 30x0.10 = 3.0 cum.
### Extra labour for filling and ramming
### 2.8.1 Rate as per item no. 2.8.1 of SH: Earth work cum 3 171.4
### 9999 Sundries L.S. 13.52 2
### TOTAL
### Add 1 % Water charges on "W-A" 27.04
### TOTAL
### Add GST (multiplying factor 0.1405) on "X-A" 27.31
### TOTAL
### Add 15 % Contractor's profit and overheads on 31.15
### "Y-A"
### Total
### Add Cess @ 1% on "Z-A" 35.82
### Cost of 30 holes
### Cost of 1 hole
### Say
###
### 16.67 Providing and fixing at or near
### ground level factory made RCC pavement
### Details of cost for 10 sqm
### MATERIAL
### 8694 Precast pavement slab 450 x 450 x 50 mm (M - each 48 135
### 30)
### 9977 Carriage of slab. L.S. 52 2
### 20mm (bed and joints) CM. 1:5
### (1 cement: 5 coarse sand)
### 3.1 Rate as per Item Number 3.10 of SH: Mortars cum 0.25 5607.8
### LABOUR
### 40 Mason (average) day 1.1 403.67
### 10 Bandhani day 1.1 350.00
### 17 Beldar day 0.55 350.00
### 11 Bhisti day 0.27 350.00
### 9999 Sundries L.S. 10.79 2
### Total
### Add 1 % Water charges on "W"
### TOTAL
### Add GST (multiplying factor 0.1405) on "X"
### TOTAL
### Add 15 % Contractor's profit and overheads on "Y"
### Total
### Add Cess @ 1% on "Z"
### Cost for 10 sqm.
### Cost for 1 sqm
### Say
###
### 16.68 Providing and laying 60mm thick
### faciory made cement concrete interlocking
### Details of cost for 10.00 sqm
###
### MATERIAL
### 8689 Interlocking C.C. paver block ( 60 mm thick, M- sqm 10 400
### 30)
### Bedding layer - 50mm thick
### 982 Coarse sand =10x0.050=0.50 cum cum 0.5 800
### 2203 Carriage of Coarse sand cum 0.5 584.88
### 983 Fine sand cum 0.15 850
### 2203 Carriage of Coarse sand cum 0.15 584.88
### Laying charges (Bassed on actual
### observation)
### LABOUR
### 23 Mason (brick layer) 1st class day 0.5 505.17
### 24 Mason (brick layer) 2nd class day 0.5 403.67
### 17 Beldar day 1 350.00
### 18 Coolie day 0.5 350.00
### Total
### Add 1 % Water charges on "W"
### TOTAL
### Add GST (multiplying factor 0.1405) on "X"
### TOTAL
### Add 15 % Contractor's profit and overheads on "Y"
### Total
### Add Cess @ 1% on "Z"
### Cost for 10 sqm.
### Cost for 1 sqm
### Say
###
### 16.69 Providing and laying at or near
### ground level factory made kerb stone of M-
### Details of cost 100 metre i.e.
### 100x0.375x0.20=7.50 cum.
### No. of kerb stones = 100/0.405=247 Nos
### Precast C.C. Kerb stone M - 25 =
### 247x0.40x0.375x0.20=7.41 cum
### METERIAL
### 8686 Precast C.C. Kerb stone M - 25 cum 7.41 5500
### Mortar 1:3 for fixing joints = 246x1x
### [(0.115+0.20)/2] x 0.375x0.005 = 0.073 cum.
### Cement mortar 1:3 (1 cement : 3 coarse sand)
### 3.8 Rate as per Item Number 3.8 of SH: Mortars cum 0.073 4129.00
### Labour for fixing of kerb stones
### 23 Mason (brick layer) 1st class day 2.5 505.17
### 24 Mason (brick layer) 2nd class day 2.5 403.67
### 17 Beldar day 2.5 350.00
### 18 Coolie day 1.65 350.00
### Total
### Add 1 % Water charges on "W"
### TOTAL
### Add GST (multiplying factor 0.1405) on "X"
### TOTAL
### Add 15 % Contractor's profit and overheads on "Y"
### Total
### Add Cess @ 1% on "Z"
### Cost of 7.50 cum
### cost for 1 cum.
### Say
###
### 16.70 Providing and fixing G.I. chain link
### fabric fencing of required width in mesh
### 16.70.1 Made of G.I. wire of dia 4 mm
###
### Details of cost for 10 sqm.
### MATERIAL
### G.I. chain link 50x50 mm mesh = 10.00 sqm.
### Wastage @ 5% = 0.50 sqm.
### Total = 10.50 sqm.
### 8695 Chain link fabric fencing mesh of size sqm 10.5 280
### 50x50 mm made of G.I. wire of dia 4 mm
### 9977 Carriage. L.S. 156 2
### LABOUR
### 13 Blacksmith 2nd class day 2.14 403.67
### 17 Beldar day 1.62 350.00
### 9999 Sundries including G.I. wire, nuts and bolts and L.S. 174.75 2
### warshers.
### Total
### Add 1 % Water charges on "W"
### TOTAL
### Add GST (multiplying factor 0.1405) on "X"
### TOTAL
### Add 15 % Contractor's profit and overheads on "Y"
### Total
### Add Cess @ 1% on "Z"
### Cost for 10 sqm.
### Cost for 1 sqm.
### Say
###
###
###
### 16.70.2 Made of G.I. wire of dia. 4 mm, PVC
### coated to achieve outer dia not less than 5
### Details of cost for 10 sqm.
###
### MATERIAL
### G.I. chain link 50x50 mm mesh PVC coated =
### 10.00 sqm.
### Wastage @ 5% = 0.50 sqm.
### Total = 10.50 sqm.
### 8696 Chain link fabric fencing mesh of size sqm 10.5 300
### 50x50 mm made of G.I. wire of dia 4 mm, PVC
### coated to outer dia 5 mm
### 9977 Carriage. L.S. 156 2
### LABOUR
### 13 Blacksmith 2nd class day 2.14 403.67
### 17 Beldar day 1.62 350.00
### 9999 Sundries including G.I. wire, nuts and bolts and L.S. 174.75 2
### warshers.
### Total
### Add 1 % Water charges on "W"
### TOTAL
### Add GST (multiplying factor 0.1405) on "X"
### TOTAL
### Add 15 % Contractor's profit and overheads on "Y"
### Total
### Add Cess @ 1% on "Z"
### Cost for 10 sqm.
### Cost for 1 sqm.
### Say
###
### 16.71 Providing and fixing G.I. chain link
### fabric fencing of required width in mesh
### direction of Engineer-incharge.
###
### Details of cost for 10 sqm.
###
### MATERIAL
###
### G.I. chain link 25x25 mm mesh = 10.00 sqm.
### Wastage @ 5% = 0.50 sqm.
### Total = 10.50 sqm.
### 8697 Chain link fabric fencing mesh of size sqm 10.5 360
### 25x25 mm made of G.I. wire of dia 3 mm
### 9977 Carriage. L.S. 156 2
### LABOUR
### 13 Blacksmith 2nd class day 2.14 403.67
### 17 Beldar day 1.62 350.00
### 9999 Sundries including G.I. wire, nuts and bolts and L.S. 174.75 2
### warshers.
### Total
### Add 1 % Water charges on "W"
### TOTAL
### Add GST (multiplying factor 0.1405) on "X"
### TOTAL
### Add 15 % Contractor's profit and overheads on "Y"
### Total
### Add Cess @ 1% on "Z"
### Cost for 10 sqm.
### Cost for 1 sqm.
### Say
###
###
### 16.72 Supplying and stacking of hard
### stone
Detail (for for
of cost stone
2.25 pitching)
cum 22.5 cm thick at
### MATERIAL
### 22.5 cm thick stone (Hard)
### 1158 Stone for pitching 15 cm x 22.5 cm cum 2.25 600
### Carriage by mechanical transport i/c loading
### unloading and stacking
### 2215 Carriage of Soling stone & masonary stone cum 2.25 124.86
### TOTAL
### Add 1 % Water charges on "W"
### TOTAL
### Add GST (multiplying factor 0.1405) on "X"
### TOTAL
### Add 15 % Contractor's profit and overheads on "Y"
### Total
### Add Cess @ 1% on "Z"
### Cost for 2.25 cum
### Cost for one cum
### Say
###
###
### 16.73 Dry stone pitching 22.5 cm thick laid
### Detailinofcourses
cost for 10and
sqmrequired profile with
### LABOUR
### 23 Mason (brick layer) 1st class day 1.08 505.17
### 24 Mason (brick layer) 2nd class day 1.08 403.67
### 17 Beldar day 2.15 350.00
### 18 Coolie day 1.61 350.00
### 9999 Sundries L.S. 6.76 2
### TOTAL
### Add 1 % Water charges on "W"
### TOTAL
### Add GST (multiplying factor 0.1405) on "X"
### TOTAL
### Add 15 % Contractor's profit and overheads on "Y"
### Total
### Add Cess @ 1% on "Z"
### Cost for 10 sqm
### Cost for one sqm
### Say
###
### 16.74 75 mm thick back filling for pitching
### including supplying of required materials
### 16.74.1 Moorum
###
### Details of cost for 100 sqm
### MATERIAL
### 810 Moorum cum 7.5 500
### Carriage by mechanical transport i/c loading
### unloading and stacking
### 2265 Carriage of Moorum cum 7.5 106.13
### LABOUR
### 17 Beldar day 1.64 350.00
### 11 Bhisti day 0.13 350.00
### TOTAL
### Add 1 % Water charges on "W"
### TOTAL
### Add GST (multiplying factor 0.1405) on "X"
### TOTAL
### Add 15 % Contractor's profit and overheads on "Y"
### Total
### Add Cess @ 1% on "Z"
### Cost for 100 sqm
### Cost per sqm
### Say
###
###
### 16.74.2 Stone aggregate 20 mm nominal size
### Detail of cost for 100 sqm
### MATERIAL
### 295 Stone Aggregate (Single size) : 20 mm nominal cum 7.5 790
### size
### 100sqm x7.50cm= 7.50 cum
### 2202 Carriage of Stone aggregate below 40 mm cum 7.5 584.88
### nominal size
### LABOUR
### 17 Beldar day 2.05 350.00
### 11 Bhisti day 0.13 350.00
### TOTAL
### Add 1 % Water charges on "W"
### TOTAL
### Add GST (multiplying factor 0.1405) on "X"
### TOTAL
### Add 15 % Contractor's profit and overheads on "Y"
### Total
### Add Cess @ 1% on "Z"
### Cost for 100 sqm
### Cost per sqm
### Say
###
###
### 16.74.3 Stone aggregate 40 mm nominal size
### Detail of cost for 100 sqm
### MATERIAL
### 293 Stone Aggregate (Single size) : 40 mm nominal cum 7.5 730
### size
### 100sqm x7.50cm= 7.50 cum
### 2206 Carriage of Stone aggregate 40 mm cum 7.5 115.36
### nominal size and above
### LABOUR
### 17 Beldar day 2.05 350.00
### 11 Bhisti day 0.13 350.00
### TOTAL
### Add 1 % Water charges on "W"
### TOTAL
### Add GST (multiplying factor 0.1405) on "X"
### TOTAL
### Add 15 % Contractor's profit and overheads on "Y"
### Total
### Add Cess @ 1% on "Z"
### Cost for 100 sqm
### Cost per sqm
### Say
###
### 16.75 Providing and laying C.C. pavement
### of mix M-25 with ready mixed concrete
### Details of cost for 1.00 cum
###
### MATERIAL
###
### Ready mix concrete M 25 = 1.00 cum. i/c placing of concrete,
vibrating, leveling etc.
### 5.37.1 Rate as per Item No.5.37.1 of SH:RCC cum 1 7336.25
### 9999 Operational charges for vacuum dewatering L.S. 57.2 2
### system i/c screed vibration , placing of filter
### mat , top mat, vacuum process, floating ,
### troweling, Brooming etc.
### 9999 T& P charges i/c consumable power charges, L.S. 41.6 2
### loading , unloading and hire
### charges of equipments
### Total
### Add 1 % Water charges on "W-A" 197.6
### TOTAL
### Add GST (multiplying factor 0.1405) on "X-A" 199.58
### TOTAL
### Add 15 % Contractor's profit and overheads on 227.62
### "Y-A"
### Total
### Add Cess @ 1% on "Z-A" 261.76
### Cost for 1 cum
### Say
###
###
###
### 16.76 Deduct for using of M-20 grade
### concrete
C.C. instead of M-25 grade concrete in
pavement.
### Details of cost for 1 cum.
###
### Cement for M-25 mix = 0.410 t
### Cement for M - 20 mix = 0.383 t
### Difference = 0.027 t
### METERIAL
### 367 Portland Cement (OPC-43 grade) tonne 0.027 4375
### 2209 Carriage of Cement tonne 0.027 94.34
### Plasticizer for M- 25 mix = 2.050kg
### Plasticizer for M- 20 mix = 1.915 kg
### Difference = 0.135 kg
### 7318 Plasticizer / super plasticizer kilogram 0.135 36
### Total
### Add 1 % Water charges on "W"
### TOTAL
### Add GST (multiplying factor 0.1405) on "X"
### TOTAL
### Add 15 % Contractor's profit and overheads on "Y"
### Total
### Add Cess @ 1% on "Z"
### Cost for 1 cum.
### Say
###
###
### 16.77 Scarifying the existing bituminous
### road surface to a depth
mechanical of 50 mm and
means).
###
### Details of cost for 100 sqm
###
### LABOUR
### 28 Mate day 0.01 350.00
### 17 Beldar day 0.25 350.00
### MACHINERY
### 38 Tractor with ripper attachment. day 0.01 1200
### 14 Front end loader capacity 1.00 cum day 0.025 6000
### 17 Hire and running charges of tipper day 0.02875 1700
### TOTAL
### Add 1 % Water charges on "W"
### TOTAL
### Add GST (multiplying factor 0.1405) on "X"
### TOTAL
### Add 15 % Contractor's profit and overheads on "Y"
### Total
### Add Cess @ 1% on "Z"
### Cost for 100 sqm
### Cost for 1 sqm
### Say
###
### 16.78 Construction of granular sub-base
### by providing close graded Material
### 16.78.1 With material conforming to Grade-I
### (size range 75 mm to 0.075 mm) having
###
###
###
### 1275
###
###
### Details of cost for 225 cum (450 tonnes)
### MATERIAL
### Close graded graunlar sub-base material as
### per Grading-I of specifications
### 53mm to 9.5mm @ 50% = 144 cum
### 9.5 mm to 2.36mm @ 20% = 57 cum
### 2.36mm below @ 30% = 86.40 cum
### 292 Stone Aggregate (Single size) : 50 mm nominal cum 72 730
### 297 size cum 72 810
### Stone Aggregate (Single size) : 10 mm nominal
### size
### 2206 Carriage of Stone aggregate 40 mm nominal cum 72 115.36
### size and above
### 2202 Carriage of Stone aggregate below 40 mm cum 72 584.88
### nominal size
### 1179 Crushed stone 2.36 mm to 12.5 mm size cum 57 900
### 2202 Carriage of Stone aggregate below 40 mm cum 57 584.88
### nominal size
### 2903 Stone chippings/ screenings 4.75 mm nominal cum 43.2 1400
### size
### 2904 Stone chippings/ screenings 150 micron cum 43.2 1400
### nominal size
### 2203 Carriage of Coarse sand Machinery/ Hire cum 86.4 584.88
### charges:
### 59 Wet Mix Plant 60 TPH @75 tonne capacity hour 6 800
### 70 Generator 100 KVA/125 KVA hour 6 250
### 57 Water Tanker 5 to 6 KL capacity 5 km lead hour 4.5 150
### with one trip per hour
### 52 Front end loader 1 cum bucket capacity hour 6 900
### (incl POL)
### Tipper 10 tonne capacity( taking lead= 10
### Km) =450x10 =4500 t.Km
### 53 Tipper -5 Cum tonne 4500 3
### Add 10 per cent of cost of carriage to cover km
###
### cost of loading and unloading
### 50 Motor Grader 3.35 metre blade hour 6 2450
### 54 Vibratory roller 8 to 10 tonne hour 6 600
### LABOUR
### 28 Mate day 0.4 350.00
### 37 Skilled Beldar (for floor rubbing etc.) day 2 350.00
### 17 Beldar day 8 350.00
### Total
### Add 1 % Water charges on "W"
### TOTAL
### Add GST (multiplying factor 0.1405) on "X"
###
###
###
###
###
### 1276
###
###
### 1277
###
### Details of cost for 225 cum (450 tonnes)

###
### TOTAL
### Add 15 % Contractor's profit and overheads on "Y" 72827.1
### Total
### Add Cess @ 1% on "Z" 5583.41
### Cost for 225 cum(450 Tonne) 563924.5
### Cost per cum. 2506.33
### Say
###
### 16.78.2 With material conforming to Grade-
### II (size range 53 mm to 0.075 mm ) having
###
### MATERIAL
### Close graded graunlar sub-base material as
### per Grading-I of specifications
### 26.5mm to 9.5mm @ 35% = 100.80 cum
### 9.5 mm to 2.36mm @ 25% = 72 cum
### 2.36mm below @ 40% = 115.20 cum
### 294 Stone Aggregate (Single size) : 25 mm nominal cum 50.4 760
### 297 size cum 50.4 810
### Stone Aggregate (Single size) : 10 mm nominal
### size
### 2202 Carriage of Stone aggregate below 40 mm cum 100.8 584.88
### nominal size
### 1179 Crushed stone 2.36 mm to 12.5 mm size cum 72 900
### 2202 Carriage of Stone aggregate below 40 mm cum 72 584.88
### nominal size
### 2903 Stone chippings/ screenings 4.75 mm nominal cum 57.6 1400
### size
### 2904 Stone chippings/ screenings 150 micron cum 57.6 1400
### nominal size
### 2203 Carriage of Coarse sand Machinery/ Hire cum 115.2 584.88
### charges:
### 59 Wet Mix Plant 60 TPH @75 tonne capacity hour 6 800
### 70 Generator 100 KVA/125 KVA hour 6 250
### 57 Water Tanker 5 to 6 KL capacity 5 km lead hour 4.5 150
### with one trip per hour
### 52 Front end loader 1 cum bucket capacity hour 6 900
### (incl POL)
### Tipper 10 tonne capacity( taking lead= 10
### Km) =450x10 =4500 t.Km
### 53 Tipper -5 Cum tonne 4500 3
### km
### Add 10 per cent of cost of carriage to cover
### cost of loading and unloading
###
###
### 50 Motor Grader 3.35 metre blade hour 6 2450
### 54 Vibratory roller 8 to 10 tonne hour 6 600
### LABOUR
### 28 Mate day 0.4 350.00
### 37 Skilled Beldar (for floor rubbing etc.) day 2 350.00
### 17 Beldar day 8 350.00
### Total
### Add 1 % Water charges on "W"
### TOTAL
### Add GST (multiplying factor 0.1405) on "X"
### TOTAL
### Add 15 % Contractor's profit and overheads on "Y"
### Total
### Add Cess @ 1% on "Z"
### Cost for 225 cum(450 Tonne)
### Cost per cum.
### Say
###
### 16.78.3 With material conforming to Grade-
### III (size range 26.5 mm to 0.075 mm ) having
### Details of cost for 225 cum (450 tonnes)
###
### MATERIAL
### Close graded graunlar sub-base material as
### per Grading-III of specifications
### 9.5mm to 4.75mm @ 35% = 100.80 cum
### 4.75 mm to 2.36mm @ 12.5% = 36.00 cum
### 2.36mm below @ 52.5% = 151.20 cum
### 1179 Crushed stone 2.36 mm to 12.5 mm size cum 100.8 900
### 2202 Carriage of Stone aggregate below 40 mm cum 100.8 584.88
### nominal size
### 1179 Crushed stone 2.36 mm to 12.5 mm size cum 36 900
### 2202 Carriage of Stone aggregate below 40 mm cum 36 584.88
### nominal size
### 2903 Stone chippings/ screenings 4.75 mm nominal cum 75.6 1400
### size
### 2904 Stone chippings/ screenings 150 micron cum 75.6 1400
### nominal size
### 2203 Carriage of Coarse sand Machinery/ Hire cum 151.2 584.88
### charges:
### 59 Wet Mix Plant 60 TPH @75 tonne capacity hour 6 800
### 70 Generator 100 KVA/125 KVA hour 6 250
### 57 Water Tanker 5 to 6 KL capacity 5 km lead hour 4.5 150
### with one trip per hour
###
###
###
### 1278
###
###
### 52 Front end loader 1 cum bucket capacity hour 6 900
### (incl POL)
### Tipper 10 tonne capacity( taking lead= 10
### Km) =450x10 =4500 t.Km
### 53 Tipper -5 Cum tonne 4500 3
### Add 10 per cent of cost of carriage to cover km
###
### cost of loading and unloading
### 50 Motor Grader 3.35 metre blade hour 6 2450
### 54 Vibratory roller 8 to 10 tonne hour 6 600
### LABOUR
### 28 Mate day 0.4 350.00
### 37 Skilled Beldar (for floor rubbing etc.) day 2 350.00
### 17 Beldar day 8 350.00
### Total
### Add 1 % Water charges on "W"
### TOTAL
### Add GST (multiplying factor 0.1405) on "X"
### TOTAL
### Add 15 % Contractor's profit and overheads on "Y"
### Total
### Add Cess @ 1% on "Z"
### Cost for 225 cum(450 Tonne)
### Cost per cum.
### Say
###
### 16.79 Providing, laying, spreading and
### compacting graded stone aggregate (size
### Details of cost for 225 cum (495 tonne)
###
### MATERIAL
###
### Conforming to table ……
###
### 45mm
to22.4mm
###
### Qty for 0292,0293,0294,0295 codes = 89.10 / 4 =
22.275 cum
###
### Qty for 2206, 2202 codes = 89.10 /2 = 4 4.55 cum
###
###
###
### 1279
###
###
### 22.4 mm to 2.36mm @ 40% = 118.80 cum
### Qty for 0294,0295 codes = 118.80 /4
### = 29.70 cum
### Qty for 1179 code = 118.80 /2 = 59.40 cum
### 2.36 mm to 75 microon @ 30% = 89.10 cum
### Qty for =M!A880, 2904 codes = 89.10 / 2
### = 44.55 cum
### 292 Stone Aggregate (Single size) : 50 mm nominal cum 22.275 1000
### 293 size cum 22.275 730
### Stone Aggregate (Single size) : 40 mm nominal
### 294 size cum 22.275 760
### Stone Aggregate (Single size) : 25 mm nominal
### 295 size cum 22.275 790
### Stone Aggregate (Single size) : 20 mm nominal
### size
### 2206 Carriage of Stone aggregate 40 mm nominal cum 44.55 115.36
### size and above
### 2202 Carriage of Stone aggregate below 40 mm cum 44.55 584.88
### 294 nominal size cum 29.7 760
### Stone Aggregate (Single size) : 25 mm nominal
### 295 size cum 29.7 790
### Stone Aggregate (Single size) : 20 mm nominal
### size
### 1179 Crushed stone 2.36 mm to 12.5 mm size cum 59.4 900
### 2202 Carriage of Stone aggregate below 40 mm cum 118.8 584.88
### nominal size
### 2903 Stone chippings/ screenings 4.75 mm nominal cum 44.55 1400
### size
### 2904 Stone chippings/ screenings 150 micron cum 44.55 1400
### nominal size
### 2203 Carriage of Coarse sand Machinery/ Hire cum 89.1 584.88
### charges:
### 59 Wet Mix Plant 60 TPH @75 tonne capacity hour 6.6 800
### 70 Generator 100 KVA/125 KVA hour 6 250
### 57 Water Tanker 5 to 6 KL capacity 5 km lead hour 3 150
### with one trip per hour
### 52 Front end loader 1 cum bucket capacity hour 6 900
### (incl POL)
### Tipper 10 tonne capacity( taking lead= 10
### Km) =450x10 =4500 t.Km
### 53 Tipper -5 Cum tonne 4950 3
### Add 10 per cent of cost of carriage to cover km
###
### cost of loading and unloading
### 65 Paver finisher Mechanical 100 TPH hour 6 800
### 54 Vibratory roller 8 to 10 tonne hour 3.9 600
### LABOUR
### 28 Mate day 0.48 350.00
### 37 Skilled Beldar (for floor rubbing etc.) day 2 350.00
###
###
###
###
###
### 1280
###
###
### 17 Beldar day 10 350.00
### Total
### Add 1 % Water charges on "W"
### TOTAL
### Add GST (multiplying factor 0.1405) on "X"
### TOTAL
### Add 15 % Contractor's profit and overheads on "Y"
### Total
### Add Cess @ 1% on "Z"
### Cost for 225 cum(450 Tonne)
### Cost per cum.
### Say
###
### 16.80 Construction of dry lean cement
### concrete sub base over a prepared sub-
### Details of cost for 450 cum (990 tonne)
### MATERIAL
### Crushed stone coarse aggregate of 25mm &
### 12.5 mm nominal sizes graded as per
### specifications @ 0.90 cum/cum of concrete
### conforming to specification. = 405 cum Coarse
### Sand @0.45 m3 per cum of concrete = 203
### cum
### Cement @150 Kg. per cum of concrete
### = 67.50 cum
### Qty for 0294,0296 codes = 405 / 2 =
### 202.50 cum
### 294 Stone Aggregate (Single size) : 25 mm nominal cum 202.5 760
### size
### 296 Stone Aggregate (Single size) : 12.5 mm cum 202.5 800
### nominal size
### 982 Coarse sand cum 203 800
### 367 Portland Cement (OPC-43 grade) tonne 67.5 4375
### 2202 Carriage of Stone aggregate below 40 mm cum 405 584.88
### nominal size
### 2203 Carriage of Coarse sand cum 203 584.88
### 2209 Carriage of Cement tonne 67.5 94.34
###
###
###
### 1281
###
###
### Machinery/ Hire charges:
### 52 Front end loader 1 cum bucket capacity hour 6 900
### (incl POL)
### @75 tonne capacity
### 66 Batching and Mixing Plant @ 75 cum per hour hour 6 2400
### 69 Generator 250 KVA hour 6 350
### 5 km lead with one trip per hour
### 65 Paver finisher Mechanical 100 TPH hour 6 800
### 54 Vibratory roller 8 to 10 tonne hour 8 600
### 57 Water Tanker 5 to 6 KL capacity hour 8 150
### 53 Tipper -5 Cum tonne 9900 3
### Add 10 per cent of cost of carriage to km
###
### cover cost of loading and unloading
### LABOUR
### 28 Mate day 1.12 350.00
### 37 Skilled Beldar (for floor rubbing etc.) day 6 350.00
### 17 Beldar day 22 350.00
### Total
### Add 1 % Water charges on "W"
### TOTAL
### Add GST (multiplying factor 0.1405) on "X"
### TOTAL
### Add 15 % Contractor's profit and overheads on "Y"
### Total
### Add Cess @ 1% on "Z"
### Cost for 450 cum(990 Tonne)
### Cost per cum.
### Say
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
### 1282
###
###
###
### 16.81 Providing and erecting 2.00 metre
### high temporary barricading at site as per
###
### Details of cost for 2.5 metre
### MATERIAL
### 16.81X Rate as per Sub Analysis No.16.81X metre 2.5 43.15
### 16.81Y Rate as per Sub Analysis No.16.81Y metre 2.5 806.45
### 13.50.3 Rate as per Item No.13.50.3 of sqm 11 33.3
### SH: FINISHING
### 13.61.1 Rate as per Item No.13.61.1 of sqm 11 82.4
### SH: FINISHING
### TOTAL
### Add 1 % Water charges on "W-A" 2123.99
### TOTAL
### Add GST (multiplying factor 0.1405) on "X" 2145.23
### TOTAL
### Add 15 % Contractor's profit and overheads on 2446.63
### "Y"
### Total
### Add Cess @ 1% on "Z" 2813.63
### Cost of 2.5 metre
### Cost of 1 metre
### Say
###
### 16.81X Sub
### analysis
### Sub analysis item no.16.81X to be used in
###
###
###
###
###
### 1283
###
###
### Item No. 16.81
### Details of cost for 2.5 meter
### MATERIAL
### M.S. Sheet 1.63mm thick = 1x2.50x2.00 = 5.00
### sqm @ 12.80 kg/sqm = 64.00 kg wastage @
### 5%= 3.20 kg
### 1013 Total = 67.20 kg quintal 0.672 4600
### Mild steel sheets for tanks
### MS Angle - 40 x 40 x 6 mm
### Outframe=2x(2.50+2.00)=9.00 m
### Vertical extra = 2x0.300 = 0.60 m
### Horizontal = 1x2.50 =2.50 m
### Bracing = 2x3.20 = 6.40 m
### Bracing at bottom = 2x0.50 = 1.00 m
### Total = 19.50 m @ 3.50 kg/m = 68.25 kg +
### wastage @ 5% = 3.14 kg
### Total = 71.66 kg
### 1007 Structurals such as tees,angles channels and quintal 0.717 5300
### R.S. joists
### M.S. Channel = 2x0.50 =1.00 m @ 5.70 kg/m =
### 5.70 kg+ wastage @ 5% = 0.29 kg
### Total = 5.99 kg
### 1007 Structurals such as tees, angles channels and quintal 0.0599 5300
### R.S. joists
### M.S. Flat 30x5 mm
### Horizontal = 2x2.50 = 5.00 m
### Vertical = 2x2.00 = 4.00 m
### Total = 9.00 m @ 1.20 kg/m =10.80 kg +
### wastage @ 5% = 0.54 kg
### Total = 11.34 kg
### 1008 Flats upto 10 mm in thickness quintal 0.1134 5300
### 2205 Carriage of Steel tonne 0.156 94.34
### TOTAL
### Add for maintenance @ 10% on
### Less for salvage value of material @ 50% on
### TOTAL
### Assuming that material will become
### unserviceable after using 40 times, cost of
### 2.5 metre using once = S/40
### Cost of 2.5 meter
### Cost of 1 meter
### Say
###
### 16.81Y Sub analysis item for fabrication
### charges of Item No. 16.81
###
###
###
###
### 1284
###
###
### Sub analysis item no.16.81Y to be used in
### Item No. 16.81
### Details of cost for 2.5 metre
### MATERIAL
### 1215 Welding by electric plant cm 165 2
### Cutting, assembling and erection charges
### LABOUR
### 12 Blacksmith 1st class day 0.115 505.17
### 13 Blacksmith 2nd class day 0.115 403.67
### 10 Bandhani day 0.11 350.00
### 17 Beldar day 0.83 350.00
### 9999 Sundries L.S. 12.1 2
### Labour for riveting / bolting / cutting etc.
### 19 Fitter (grade 1) day 0.41 505.17
### 13 Blacksmith 2nd class day 0.54 403.67
### 10 Bandhani day 0.7 350.00
### 17 Beldar day 0.54 350.00
### 37 Skilled Beldar (for floor rubbing etc.) day 0.81 350.00
### 9999 Sundries L.S. 12.1 2
### TOTAL
### Shifting including transportation, re-erection etc. @
10%
### TOTAL Cost of 2.5 meter
### Cost of 1 meter
### Say
###
### 16.82 Taking out existing kerb stones of all
### types from footpath/ central verge,
### Charge.
###
### Details of cost for 100 meter
###
### LABOUR
### 17 Beldar day 0.75 350.00
### 18 Coolie day 3 350.00
### 9999 Sundries L.S. 2 2
### TOTAL
### Add 1 % Water charges on "W"
###
###
###
###
###
### 1285
###
###
### TOTAL
### Add GST (multiplying factor 0.1405) on "X" 171.3
### TOTAL
### Add 15 % Contractor's profit and overheads on "Y" 208.57
### Total
### Add Cess @ 1% on "Z" 15.99
### Cost of 100 meter 1615.04
### Cost of 1 meter 16.15
### Say
###
### 16.83 Taking out existing CC interlocking
### paver blocks from footpath/ central verge,
### Details of cost for 10 sqm.
### LABOUR
### 17 Beldar day 0.25 350.00
### 18 Coolie day 1 350.00
### 9999 Sundries L.S. 2.7 2
### TOTAL
### Add 1 % Water charges on "W"
### TOTAL
### Add GST (multiplying
factor 0.1405)
### TOTAL
### Add 15 % Contractor's profit and overheads on "Y"
### Total
### Add Cess @ 1% on "Z"
### Cost of 10 sqm.
### Cost of 1 sqm
### Say
###
### 16.84 Laying old cement cocrete
### interlocking paver blocks of any design/
### Details of cost for 10 sqm.
###
### MATERIAL
###
###
###
###
###
### 1286
###
###
### Bedding layer 50mm thick
### 982 Coarse sand cum 0.5 800
### Qty = 10 x 0.05 = 0.50 cum
### 2203 Carriage of Coarse sand cum 0.5 584.88
### 983 Fine sand cum 0.15 850
### 2261 Carriage of Fine sand (1 part badarpur sand : 2 cum 0.15 106.13
### parts Sand)
### LABOUR
### 23 Mason (brick layer) 1st class day 0.5 505.17
### 24 Mason (brick layer) 2nd class day 0.5 403.67
### 17 Beldar day 1 350.00
### 18 Coolie day 0.5 350.00
### TOTAL
### Add 1 % Water charges on "W"
### TOTAL
### Add GST (multiplying factor 0.1405) on "X"
### TOTAL
### Add 15 % Contractor's profit and overheads on "Y"
### Total
### Add Cess @ 1% on "Z"
### Cost of 10 sqm.
### Cost of 1 sqm
### Say
###
### 16.85 Laying at or near ground level old
### kerb stones of all types in position to the
### Details of cost for 100 meter.
###
### MATERIAL
###
### Number of kerb stones = 100 / 0.405 = 247
###
### Nos.
### Qty. = 247 x 0.40 x 0.375 x 0.20 = 7.41cum No. of
joints = 247 - 1 = 246 Nos.
###
### Cement Mortar 1:3 for fixing joints = 246 x [(0.115 +
0.20)/2 x 0.375 x 0.005]
###
###
###
###
### 1287
###
###
### = 0.073 cum
### 3.8 Rate as per Item No.3.8 of SH:MORTARS cum 0.073 4469.5
### LABOUR
### 23 Mason (brick layer) 1st class day 2.5 505.17
### 24 Mason (brick layer) 2nd class day 2.5 403.67
### 17 Beldar day 2.5 350.00
### 18 Coolie day 1.65 350.00
### TOTAL
### Add 1 % Water charges on "W"
### TOTAL
### Add GST (multiplying factor 0.1405) on "X"
### TOTAL
### Add 15 % Contractor's profit and overheads on "Y"
### Total
### Add Cess @ 1% on "Z"
### Cost of 100 meter.
### Cost of 1 meter.
### Say
###
### 16.86 Providing and laying gang saw cut
### 18 mm thick, mirror polished pre moulded
### 16.86.1 With granite stone of area less than
### 0.50 sqm.
### Detail of cost for 0.5sqm.
### Mirror polished granite 0.5 sqm.
### Waste @5% = 0.025 +0.5 = 0.525 sqm.
### 7295 Granite of any colour, 18 mm thick (slab area sqm 0.525 1600
### upto 0.50 sqm)
### 3.9 Rate as per Item No.3.9 of SH: MORTARS cum 0.012 3548.00
### LABOUR :
### 23 Mason (brick layer) 1st class day 0.56 505.17
### 17 Beldar day 0.05 350.00
###
###
###
###
### 1288
###
###
### 18 Coolie day 0.05 350.00
### 9999 Sundries L.S. 17.6 2
### TOTAL
### Add 1 % Water charges on "W"
### TOTAL
### Add GST (multiplying factor 0.1405) on "X"
### TOTAL
### Add 15 % Contractor's profit and overheads on "Y"
### Total
### Add Cess @ 1% on "Z"
### Rate per 0.50 sqm.
### Rate per sqm.
### Say
###
### 16.87 Providing and laying gang saw cut
### 30 mm thick, mirror polished pre moulded
### 16.87.1 With granite stone of area less than
### 0.50 sqm.
### Detail of cost for 0.50 sqm.
### MATERIAL
### Mirror polished granite 0.50 sqm. Waste @5%
### total = 0.025 +0.50 = 0.525 sqm.
### 7296 Granite stone slab 30mm thick sqm 0.525 1800
### 3.9 Rate as per Item No.3.9 of SH: MORTARS cum 0.012 3548.00
### LABOUR :
### 23 Mason (brick layer) 1st class day 0.56 505.17
### 17 Beldar day 0.05 350.00
### 18 Coolie day 0.05 350.00
### 9999 Sundries L.S. 17.6 2
### TOTAL
### Add 1 % Water charges on "W"
### TOTAL
###
###
###
###
###
### 1289
###
###
### Add GST (multiplying factor 0.1405) on "X" 187.97
### TOTAL
### Add 15 % Contractor's profit and overheads on "Y" 228.88
### Total
### Add Cess @ 1% on "Z" 17.55
### Rate per 0.50 sqm. 1772.26
### Rate per sqm. 3544.53
### Say
###
### 16.88 Providing and laying matt finished
### vitrified tile of size 100x100x16mm having
### Detail of cost for 1 sqm.
### MATERIAL
### Matt finished vitrified tile 100x100 x16mm
### =10sqm.
### 7895 Matt finished vitrified tile 100x100 x16mm sqm 1 1000
### 9977 Sundries L.S. 6.24 2
### 3.9 Rate as per Item No.3.9 of SH: MORTARS cum 0.024 3548.00
### 9999 Sundries L.S. 3.64 2
### 367 Portland Cement (OPC-43 grade) LABOUR : tonne 0.0033 4375
### 23 Mason (brick layer) 1st class day 0.2 505.17
### 18 Coolie day 0.2 350.00
### 9999 Sundries L.S. 26.91 2
### TOTAL
### Add 1 % Water charges on "W"
### TOTAL
### Add GST (multiplying factor 0.1405) on "X"
### TOTAL
### Add 15 % Contractor's profit and overheads on "Y"
### Total
### Add Cess @ 1% on "Z"
###
###
###
###
###
### 1290
###
###
### Cost per sqm. 1793.92
### Say
###
### 16.89 Providing and laying matt finished
### vitrified tile of size 300x300x9.8mm having
### Detail of cost for 1 sqm.
### MATERIAL
### Tile 300x300 x9.8mm = 1.00 sqm.
### 7896 Vitrified tile sqm 1 500
### 9977 Sundries L.S. 6.24 2
### 3.9 Rate as per Item No.3.9 of SH: MORTARS cum 0.024 3548.00
### 9999 Sundries L.S. 3.64 2
### 367 Portland Cement (OPC-43 grade) LABOUR : tonne 0.0033 4375
### 23 Mason (brick layer) 1st class day 0.2 505.17
### 18 Coolie day 0.2 350.00
### 9999 Sundries L.S. 26.91 2
### TOTAL
### Add 1 % Water charges on "W"
### TOTAL
### Add GST (multiplying factor 0.1405) on "X"
### TOTAL
### Add 15 % Contractor's profit and overheads on "Y"
### Total
### Add Cess @ 1% on "Z"
### Cost per sqm.
### Say
###
### 16.90 Providing and laying tactile tile (for
### vision impaired persons as per standards)
### Detail of cost for 1 sqm.
###
###
###
###
### 1291
###
###
### MATERIAL:
### Tile 300x300 x9.8mm = 1.00 sqm.
### 7893 Tactile tile sqm 1 1000
### 9977 Carriage L.S. 6.24 2
### 3.9 Rate as per Item No.3.9 of SH: MORTARS cum 0.024 3548.00
### 9999 Sundries L.S. 3.64 2
### 367 Portland Cement (OPC-43 grade) LABOUR : tonne 0.0033 4375
### 23 Mason (brick layer) 1st class day 0.2 505.17
### 18 Coolie day 0.2 350.00
### 9999 Sundries L.S. 26.91 2
### TOTAL
### Add 1 % Water charges on "W"
### TOTAL
### Add GST (multiplying factor 0.1405) on "X"
### TOTAL
### Add 15 % Contractor's profit and overheads on "Y"
### Total
### Add Cess @ 1% on "Z"
### Cost per sqm.
### Say
###
### 16.91 Providing and laying factory made
### chamfered edge Cement Concrete paver
### 16.91.1 60mm thick cement concrete paver
### block of M-35 grade with approved colour,
### Details of cost for 10 sqm.
###
### MATERIAL :
### 7773 Coloured inter locking C.C. paver Block sqm 10 450
### 983 Fine sand cum 0.5 850
### 2261 Carriage of Fine sand (1 part badarpur cum 0.65 106.13
###
###
###
### 1292
###
###
### sand : 2 parts Sand)
### LABOUR
### 23 Mason (brick layer) 1st class day 0.5 505.17
### 24 Mason (brick layer) 2nd class day 0.5 403.67
### 17 Beldar day 1 350.00
### 18 Coolie day 0.5 350.00
### 9999 Sundries L.S. 25 2
### TOTAL
### Add 1 % Water charges on "W"
### TOTAL
### Add GST (multiplying factor 0.1405) on "X"
### TOTAL
### Add 15 % Contractor's profit and overheads on "Y"
### Total
### Add Cess @ 1% on "Z"
### Cost of 10 Cum.
### Cost of 1 Cum.
### Say
###
### 16.91.2 80 mm thick C.C. paver block of M-30 grade
### with approved color design and pattern.
### Details of cost for 10.00 sqm.
### MATERIALS :
### 8785 Interlocking C.C. paver block (80 mm thick, M- sqm 10 470
### 982 30)
### Coarse sand (zone 111) (10 x 0.050 = cum 0.5 1350
### 0.50 cum )
### 2203 Carriage of Coarse sand cum 0.5 584.88
### 983 Fine sand cum 0.15 850
### 2261 Carriage of Fine sand Labour for Laying cum 0.15 106.13
### 23 Mason (brick layer) 1st class day 0.5 505.17
### 24 Mason (brick layer) 2nd class day 0.5 403.67
### 17 Beldar day 1 350.00
### 18 Coolie day 0.5 350.00
### TOTAL
### Add 1 % Water charges on "W"
### TOTAL
### Add GST (multiplying factor 0.1405) on "X"
### TOTAL
###
###
###
###
### 1293
###
###
### Add 15 % Contractor's profit and overheads on "Y" 1120.6
### Total
### Add Cess @ 1% on "Z" 85.91
### Cost of 10 Cum. 8677.17
### Cost of 1 Cum. 867.72
### Say
###
### 16.92 Providing and fixing 10x10x7.50 cm
### Granite stone block hand cut and chisel
### charge.
###
### Details of cost for 10.00 sqm.
###
### MATERIALS :
### Stone size 10x10x7.50cm =1sqm+5%
### 7774 wastage=sqm 10
### Stone size 10x10x7.50cm each 827 10
### 3.9 Rate as per Item No.3.9 of SH: MORTARS cum 0.434 3548.00
### 367 Portland Cement (OPC-43 grade) LABOUR : tonne 0.02 4375
### 24 Mason (brick layer) 2nd class day 1.08 403.67
### 17 Beldar day 0.25 350.00
### 18 Coolie day 1.62 350.00
### 11 Bhisti day 0.27 350.00
### 13.33.1 Rate as per Item No.13.33.1 of sqm 10 163.3
### SH: FINISHING
### TOTAL
### Add 1 % Water charges on "W-A" 11115.57
### TOTAL
### Add GST (multiplying factor 0.1405) on "X-A" 11226.72
### TOTAL
### Add 15 % Contractor's profit and overheads on 12804.08
### "Y-A"
### Total
### Add Cess @ 1% on "Z-A" 14724.69
### Cost of 10 sqm.
### Cost of 1 sqm.
### Say
###
###
###
###
### 1294
###
###
###
### 16.93 Providing and placing in position 100
### mm thick factory made machine batched &
### Details of cost of 1 No of size 1.50 x
### 0.40 = 0.60 sqm
### MATERIALS :
### Precast RCC M-25
### 5.33.1 Rate as per Item No.5.33.1 of cum 0.06 6934.9
### SH: REINFORCED CEMENT CONCRETE
### Reinforcement TMT
### 5.22.6 Rate as per Item No.5.22.6 of Kg 4.59 76.85
### SH: REINFORCED CEMENT CONCRETE
### Welding by gas plant/ Electric plant
### 10.22 Rate as per Item No.10.22 of cm 82 3.40
### SH: STEEL WORK
### M.S. sheet 1.60 mm thick
### 2x(1.50+0.40)x0.10x0.016x7850=4.77kg
### 1013 Mild steel sheets for tanks quintal 0.0477 4600
### Paint 2x(1.50+0.40)x0.10=0.38sqm
### 13.61.1 Rate as per Item No.13.61.1 of sqm 0.38 82.4
### SH: FINISHING Neat Cement Punning
### 1x1.50x0.40=0.60 sqm
### 13.18 Rate as per Item No.13.18 of SH: FINISHING sqm 0.6 42.1
### TOTAL
### Add 1 % Water charges on "W-A" 219.42
### TOTAL
### Add GST (multiplying factor 0.1405) on "X-A" 221.61
### TOTAL
### Add 15 % Contractor's profit and overheads on 252.75
### "Y-A"
### Total
### Add Cess @ 1% on "Z-A" 290.66
### Cost of 0.60 sqm.
###
###
###
###
###
### 1295
###
###
### Cost of 1 sqm. 2322.8
### Say
###
### 16.94 Providing & making Gabion structure
### with Mechanically Woven Double Twisted
### Details cost of one Gabion box/Crates of
### size 2mx1mx1m = 2 cum
### MATERIAL
### 8576 Crates made of Mesh type 10x12 (D=100 mm) sqm 11 190
### Zn coated. (Mesh wire diameter 3.00 mm).
### Surface area required = 11.00 sqm.
### 7753 Stone boulder with least dimension 200mm cum 2 850
### LABOUR
### 28 Mate day 0.1 350.00
### 25 Mason (for plain stone work) 2nd class day 0.5 403.67
### 17 Beldar day 1.5 350.00
### TOTAL
### Add 1 % Water charges on "W"
### TOTAL
### Add GST (multiplying factor 0.1405) on "X"
### TOTAL
### Add 15 % Contractor's profit and overheads on "Y"
### Total
### Add Cess @ 1% on "Z"
### Cost of 2 cum
### Cost of 1 cum
### Say
###
###
###
###
###
###
###
###
###
###
### 1296
###
###
###
### 16.95 Providing & making Gabion structure
### with Mechanically Woven Double Twisted
### Details cost of one Gabion box/Crates of
### size 2mx1mx1m = 2 cum MATERIAL
### 8577 Crates made of Mesh type 10x12 (D=100 mm) sqm 11 220
### Zn+PVC coated. Mesh wire diameter 2.70/3.70
### mm (ID/OD).
### Surface area required = 11.00 sqm.
### 7753 Stone boulder with least dimension 200mm cum 2 850
### LABOUR
### 28 Mate day 0.1 350.00
### 25 Mason (for plain stone work) 2nd class day 0.5 403.67
### 17 Beldar day 1.5 350.00
### TOTAL
### Add 1 % Water charges on "W"
### TOTAL
### Add GST (multiplying factor 0.1405) on "X"
### TOTAL
### Add 15 % Contractor's profit and overheads on "Y"
### Total
### Add Cess @ 1% on "Z"
### Cost of 2 cum
### Cost of 1 cum
### Say
###
### 16.96 Providing & making Gabion structure
### with Mechanically Woven Double Twisted
###
###
###
###
### 1297
###
###
### Details cost of one Gabion box/Crates of
### size 2mx1mx1m = 2 cum MATERIAL
### 8578 Crates made of Mesh type 10x12 (D=100 mm) sqm 11 290
### Zn+10% Al alloy + PVC coated. Mesh wire
### diameter 2.70/3.70 mm (ID/OD).
### Surface area required = 11.00 sqm.
### 7753 Stone boulder with least dimension 200mm cum 2 850
### LABOUR
### 28 Mate day 0.1 350.00
### 25 Mason (for plain stone work) 2nd class day 0.5 403.67
### 17 Beldar day 1.5 350.00
### TOTAL
### Add 1 % Water charges on "W"
### TOTAL
### Add GST (multiplying factor 0.1405) on "X"
### TOTAL
### Add 15 % Contractor's profit and overheads on "Y"
### Total
### Add Cess @ 1% on "Z"
### Cost of 2 cum
### Cost of 1 cum
### Say
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
### 1298
###
###
###
SUB HEAD : 17.0
###
###
###
SANITARY INSTALLATIONS
###
###
### 17.1 Providing and fixing water closet
### squatting pan (Indian type W.C. pan ) with
### cutting and making good the walls and
### floors wherever required:
### 17.1.1 White Vitreous china Orissa pattern
### W.C. pan of size 580x440 mm with integral
### type foot rests
###
### Details of cost for one pan
###
### MATERIAL
### 1954 Vitreous china orrisa type w.c. pan size each 1 1200
### 580 mm
### 7358 Flushing Cistern P.V.C. 10 lts capacity (low level) each 1 575
### (White) (with fittings, accessories and
### flush pipe)
### 1896 100 mm S.C.I. trap with vent heel each 1 320
### 9999 Cement, sand and grit etc. L.S. 26.91 2
### 9977 Carriage of materials L.S. 26.91 2
### LABOUR
### 19 Fitter (grade 1) day 1.25 505.17
### 23 Mason (brick layer) 1st class day 0.5 505.17
### 17 Beldar day 1 350.00
### TOTAL
### Add 1 % Water charges on "W"
### TOTAL
### Add GST (multiplying factor 0.1405) on "X"
### TOTAL
### Add 15 % Contractor's profit and overheads on "Y"
### Total
### Add Cess @ 1% on "Z"
### Cost of each
### Say
###
### 17.1.2 Stainless Steel AISI-304(18/8)
### Orissa pattern W.C. pan of size 585x480
### flush pipe and integrated type foot rests
### Details of cost for one pan
###
### MATERIAL
### 7805 Salem Stainless steel AISI - 304 (18/8) each 1 4500
### Orrisa pattern W.C. pan 724mm X 578mm
### 7358 Flushing Cistern P.V.C. 10 lts capacity (low level) each 1 575
### (White) (with fittings, accessories and
###
###
###
###
### 1299
###
###
### flush pipe)
### 1896 100 mm S.C.I. trap with vent heel each 1 320
### 9999 Cement, sand and grit etc. L.S. 26.91 2
### 9977 Carriage of materials L.S. 26.91 2
### LABOUR
### 19 Fitter (grade 1) day 1.25 505.17
### 23 Mason (brick layer) 1st class day 0.5 505.17
### 17 Beldar day 1 350.00
### TOTAL
### Add 1 % Water charges on "W"
### TOTAL
### Add GST (multiplying factor 0.1405) on "X"
### TOTAL
### Add 15 % Contractor's profit and overheads on "Y"
### Total
### Add Cess @ 1% on "Z"
### Cost of each
### Say
###
### 17.2 Providing and fixing white vitreous
### china pedestal type water closet (European
### 17.2.1 W.C. pan with ISI marked white
### solid plastic seat and lid
### Details of cost for one pan
### MATERIAL
### 1875 White plastic seat (solid)with lid C.P.brass hinges each 1 400
and
### 1955 rubber buffers
### Vitreous china pedestal type water closet each 1 1000
### 7358 Flushing Cistern P.V.C. 10 lts capacity (low level) each 1 575
### (White) (with fittings, accessories and
### flush pipe)
### 9999 Cement, sand and grit etc. L.S. 26.91 2
### 9977 Carriage of materials L.S. 26.91 2
### LABOUR
### 19 Fitter (grade 1) day 1.25 505.17
### 23 Mason (brick layer) 1st class day 0.5 505.17
### 17 Beldar day 1 350.00
### TOTAL
###
###
###
###
###
### 1300
###
###
### Add 1 % Water charges on "W" 32.36
### TOTAL
### Add GST (multiplying factor 0.1405) on "X" 459.27
### TOTAL
### Add 15 % Contractor's profit and overheads on "Y" 559.22
### Total
### Add Cess @ 1% on "Z" 42.87
### Cost of each 4330.2
### Say
###
### 17.2.2 W.C. pan with ISI marked black
### solid plastic seat and lid
### Details of cost for one pan
### MATERIAL
### 1876 Black plastic seat (solid) with lid C.P.brass hinges each 1 310
### and rubber buffers
### 1955 Vitreous china pedestal type water closet each 1 1000
### 7358 Flushing Cistern P.V.C. 10 lts capacity (low level) each 1 575
### (White) (with fittings, accessories and
### flush pipe)
### 9999 Cement, sand and grit etc. L.S. 26.91 2
### 9977 Carriage of materials L.S. 26.91 2
### LABOUR
### 19 Fitter (grade 1) day 1.25 505.17
### 23 Mason (brick layer) 1st class day 0.5 505.17
### 17 Beldar day 1 350.00
### TOTAL
### Add 1 % Water charges on "W"
### TOTAL
### Add GST (multiplying factor 0.1405) on "X"
### TOTAL
### Add 15 % Contractor's profit and overheads on "Y"
### Total
### Add Cess @ 1% on "Z"
### Cost of each
### Say
###
###
###
###
###
###
###
###
###
###
###
###
###
###
### 1301
###
###
###
### 17.3 Providing and fixing white vitreous
### china pedestal type water closet (European
### 17.3.1 W.C. pan with ISI marked white
### solid plastic seat and lid
### Details of cost for one pan
### MATERIAL
### 1875 White plastic seat (solid)with lid C.P.brass hinges each 1 400
and
### 1955 rubber buffers
### Vitreous china pedestal type water closet each 1 1000
### 7006 Vitreous china 10 litres low level cistern with fittings each 1 1240
### 9999 Overflow arrangement and specials for oveflow pipe L.S. 62.79 2
### 1350 Mosquito proof coupling of approved design each 1 30
### 9999 Plugs ,screws etc. L.S. 13.52 2
### 9999 Red lead, white lead and gaskit L.S. 16.12 2
### 9999 Cement, sand and grit etc. L.S. 26.91 2
### 9977 Carriage of materials L.S. 26.91 2
### LABOUR
### 19 Fitter (grade 1) day 1 505.17
### 23 Mason (brick layer) 1st class day 1 505.17
### 17 Beldar day 1 350.00
### TOTAL
### Add 1 % Water charges on "W"
### TOTAL
### Add GST (multiplying factor 0.1405) on "X"
### TOTAL
### Add 15 % Contractor's profit and overheads on "Y"
### Total
### Add Cess @ 1% on "Z"
### Cost of each
### Say
###
### 17.3.2 W.C. pan with ISI marked black
### solid plastic seat and lid
### Details of cost for one pan
###
###
###
###
###
### 1302
###
###
### MATERIAL
### 1876 Black plastic seat (solid) with lid C.P.brass hinges each 1 310
### and rubber buffers
### 1955 Vitreous china pedestal type water closet each 1 1000
### 7006 Vitreous china 10 litres low level cistern with fittings each 1 1240
### 9999 Overflow arrangement and specials for oveflow pipe L.S. 62.79 2
### 1350 Mosquito proof coupling of approved design each 1 30
### 9999 Plugs, screws etc. L.S. 13.52 2
### 9999 Red lead, white lead and gaskit L.S. 16.12 2
### 9999 Cement, sand and grit etc. L.S. 26.91 2
### 9977 Carriage of materials L.S. 26.91 2
### LABOUR
### 19 Fitter (grade 1) day 1 505.17
### 23 Mason (brick layer) 1st class day 1 505.17
### 17 Beldar day 1 350.00
### TOTAL
### Add 1 % Water charges on "W"
### TOTAL
### Add GST (multiplying factor 0.1405) on "X"
### TOTAL
### Add 15 % Contractor's profit and overheads on "Y"
### Total
### Add Cess @ 1% on "Z"
### Cost of each
### Say
###
### 17.4 Providing and fixing white vitreous
### china flat back or wall corner type lipped
### required :
###
### 17.4.1 One urinal basin with 5 litre white
### P.V.C. automatic flushing cistern
### Details of cost for one no.
### MATERIAL
### 1913 Vitreous china lipped front urinal each 1 460
### 7359 P.V.C. automatic flushing cistern 5 lts capacity each 1 470
### 7375 G.I. flush pipe and C.P. brass spreader including C.P. each 1 445
### connecting pipe Single lipped
### urinal
### 9999 Red lead, white lead and gaskit L.S. 13.52 2
### 9999 Plugs ,screws etc. L.S. 13.52 2
###
###
###
###
###
### 1303
###
###
### 9999 Cement, sand and grit etc. L.S. 13.52 2
### 9999 Painting of fittings etc. L.S. 39 2
### 9977 Carriage of materials L.S. 26.91 2
### LABOUR
### 19 Fitter (grade 1) day 0.88 505.17
### 23 Mason (brick layer) 1st class day 0.88 505.17
### 17 Beldar day 1.5 350.00
### TOTAL
### Add 1 % Water charges on "W"
### TOTAL
### Add GST (multiplying factor 0.1405) on "X"
### TOTAL
### Add 15 % Contractor's profit and overheads on "Y"
### Total
### Add Cess @ 1% on "Z"
### Cost of each
### Say
###
### 17.4.2 Range of two urinal basins with 5
### litre white P.V.C. automatic flushing cistern
### Details of cost for one no.
### MATERIAL
### 1913 Vitreous china lipped front urinal each 2 460
### 7359 P.V.C. automatic flushing cistern 5 lts capacity each 1 470
### 7376 G.I. flush pipe and C.P. brass spreader including C.P. each 1 765
### connecting pipe Range of
### two lipped urinals
### 9999 Red lead, white lead and gaskit L.S. 20.28 2
### 9999 Plugs ,screws etc. L.S. 20.28 2
### 9999 Cement, sand and grit etc. L.S. 20.28 2
### 9999 Painting of fittings etc. L.S. 39 2
### 9977 Carriage of materials L.S. 26.91 2
### LABOUR
### 19 Fitter (grade 1) day 1.5 505.17
### 23 Mason (brick layer) 1st class day 1.5 505.17
### 17 Beldar day 2 350.00
### TOTAL
### Add 1 % Water charges on "W"
### TOTAL
### Add GST (multiplying factor 0.1405) on "X"
### TOTAL
### Add 15 % Contractor's profit and overheads on "Y"
### Total
### Add Cess @ 1% on "Z"
###
###
###
###
###
### 1304
###
###
### Cost of each 5991.5
### Say
###
### 17.4.3 Range of three urinal basins with
### 10litre white P.V.C. automatic flushing
### cistern
### Details of cost for one no.
###
### MATERIAL
### 1913 Vitreous china lipped front urinal each 3 460
### 7361 P.V.C. automatic flushing cistern 10 lts capacity each 1 510
### 7377 G.I. flush pipe and C.P. brass spreader including C.P. each 1 1050
### connecting pipe Range of
### three lipped urinals
### 9999 Red lead, white lead and gaskit L.S. 33.67 2
### 9999 Plugs ,screws etc. L.S. 33.67 2
### 9999 Cement, sand and grit etc. L.S. 33.67 2
### 9999 Painting of fittings etc. L.S. 39 2
### 9977 Carriage of materials L.S. 40.3 2
### LABOUR
### 19 Fitter (grade 1) day 2 505.17
### 23 Mason (brick layer) 1st class day 2 505.17
### 17 Beldar day 3 350.00
### TOTAL
### Add 1 % Water charges on "W"
### TOTAL
### Add GST (multiplying factor 0.1405) on "X"
### TOTAL
### Add 15 % Contractor's profit and overheads on "Y"
### Total
### Add Cess @ 1% on "Z"
### Cost of each
### Say
###
### 17.4.4 Range of four urinal basins with 10
### litre white P.V.C. automatic flushing
### cistern
###
### Details of cost for one no.
###
### MATERIAL
### 1913 Vitreous china lipped front urinal each 4 460
### 7361 P.V.C. automatic flushing cistern 10 lts capacity each 1 510
### 7378 G.I. flush pipe and C.P. brass spreader including C.P. each 1 1430
### connecting pipe Range of
### four lipped urinals
###
###
###
###
### 1305
###
###
### 9999 Red lead, white lead and gaskit L.S. 53.82 2
### 9999 Plugs ,screws etc. L.S. 53.82 2
### 9999 Cement, sand and grit etc. L.S. 53.82 2
### 9999 Painting of fittings etc. L.S. 39 2
### 9977 Carriage of materials L.S. 53.82 2
### LABOUR
### 19 Fitter (grade 1) day 3 505.17
### 23 Mason (brick layer) 1st class day 3 505.17
### 17 Beldar day 4 350.00
### TOTAL
### Add 1 % Water charges on "W"
### TOTAL
### Add GST (multiplying factor 0.1405) on "X"
### TOTAL
### Add 15 % Contractor's profit and overheads on "Y"
### Total
### Add Cess @ 1% on "Z"
### Cost of each
### Say
###
### 17.5 Providing and fixing white vitreous
### china flat back half stall urinal of size
### 17.5.1 Single half stall urinal with 5 litre
P.V.C. automatic flushing cistern
###
### Details of cost for one no.
### MATERIAL
### 7379 White vitreous china clay half stall urinal flat back each 1 865
### 580x380x350 mm or angle back
### 450x375x350 mm with waste fittings as per IS : 2556
### 7359 P.V.C. automatic flushing cistern 5 lts capacity each 1 470
### 1532 Flush pipe with union spreaders and clamps all in each 1 270
### 1891 C.P. brass for single stall
### C.I. trap for standard urinal with vent arm with each 1 170
### operating and other couplings in
### C.P.brass: 50 mm dia
### 9999 Red lead, white lead and gaskit L.S. 17.55 2
### 9999 Cement, sand and grit etc. L.S. 26.91 2
### 9999 Painting of fittings etc. L.S. 26 2
### 9977 Carriage of materials L.S. 40.43 2
###
###
###
###
###
### 1306
###
###
### LABOUR
### 19 Fitter (grade 1) day 1.75 505.17
### 23 Mason (brick layer) 1st class day 2 505.17
### 17 Beldar day 4 350.00
### TOTAL
### Add 1 % Water charges on "W"
### TOTAL
### Add GST (multiplying factor 0.1405) on "X"
### TOTAL
### Add 15 % Contractor's profit and overheads on "Y"
### Total
### Add Cess @ 1% on "Z"
### Cost of each
### Say
###
### 17.5.2 Range of two half stall urinals with
### 5 litre P.V.C. automatic flushing cistern
### Details of cost for one no.
### MATERIAL
### 7379 White vitreous china clay half stall urinal flat back each 2 865
### 580x380x350 mm or angle back
### 450x375x350 mm with waste fittings as per IS : 2556
### 7359 P.V.C. automatic flushing cistern 5 lts capacity each 1 470
### 1533 Flush pipe with union spreaders and clamps all in each 1 400
### C.P. brass for double stall
### 1891 C.I. trap for standard urinal with vent arm with each 1 170
### operating and other couplings in
### C.P.brass: 50 mm dia
### 9999 Red lead, white lead and gaskit L.S. 17.55 2
### 9999 Cement, sand and grit etc. L.S. 53.82 2
### 9999 Painting of fittings etc. L.S. 26 2
### 9977 Carriage of materials L.S. 53.82 2
### LABOUR
### 19 Fitter (grade 1) day 2.5 505.17
### 23 Mason (brick layer) 1st class day 3 505.17
### 17 Beldar day 6 350.00
### TOTAL
### Add 1 % Water charges on "W"
### TOTAL
###
###
###
###
###
### 1307
###
###
### Add GST (multiplying factor 0.1405) on "X" 1080.66
### TOTAL
### Add 15 % Contractor's profit and overheads on "Y" 1315.83
### Total
### Add Cess @ 1% on "Z" 100.88
### Cost of each 10188.88
### Say
###
### 17.5.3 Range of three half stall urinals
### with 10 litre P.V.C. automatic flushing
### Details of cost for one no.
### MATERIAL
### 7379 White vitreous china clay half stall urinal flat back each 3 865
### 580x380x350 mm or angle back
### 450x375x350 mm with waste fittings as per IS : 2556
### 7361 P.V.C. automatic flushing cistern 10 lts capacity each 1 510
### 1534 Flush pipe with union spreaders and clamps all in each 1 520
### C.P. brass for range of three
### stall
### 1893 C.I. trap for standard urinal with vent arm with each 1 225
operatin
### C.P.brass: 80 mm dia
### 9999 Red lead, white lead and gaskit L.S. 17.55 2
### 9999 Cement, sand and grit etc. L.S. 80.73 2
### 9999 Painting of fittings etc. L.S. 26 2
### 9977 Carriage of materials L.S. 67.21 2
### LABOUR
### 19 Fitter (grade 1) day 3 505.17
### 23 Mason (brick layer) 1st class day 3.5 505.17
### 17 Beldar day 7 350.00
### TOTAL
### Add 1 % Water charges on "W"
### TOTAL
### Add GST (multiplying factor 0.1405) on "X"
### TOTAL
### Add 15 % Contractor's profit and overheads on "Y"
### Total
### Add Cess @ 1% on "Z"
### Cost of each
### Say
###
### 17.5.4 Range of four half stall urinals with
### 10 litre P.V.C. automatic flushing cistern
###
###
###
###
### 1308
###
###
### Details of cost for one no.
### MATERIAL
### 7379 White vitreous china clay half stall urinal flat back each 4 865
### 580x380x350 mm or angle back
### 450x375x350 mm with waste fittings as per IS : 2556
### 7361 P.V.C. automatic flushing cistern 10 lts capacity each 1 510
### 1535 Flush pipe with union spreaders and clamps all in each 1 600
### C.P. brass for range of four stall
### 1893 C.I. trap for standard urinal with vent arm with each 1 225
### operating and other couplings in
### C.P.brass: 80 mm dia
### 9999 Red lead, white lead and gaskit L.S. 17.55 2
### 9999 Cement, sand and grit etc. L.S. 107.64 2
### 9999 Painting of fittings etc. L.S. 39 2
### 9977 Carriage of materials L.S. 80.73 2
### LABOUR
### 19 Fitter (grade 1) day 3.5 505.17
### 23 Mason (brick layer) 1st class day 4 505.17
### 17 Beldar day 8 350.00
### TOTAL
### Add 1 % Water charges on "W"
### TOTAL
### Add GST (multiplying factor 0.1405) on "X"
### TOTAL
### Add 15 % Contractor's profit and overheads on "Y"
### Total
### Add Cess @ 1% on "Z"
### Cost of each
### Say
###
### 17.6 Providing and fixing one piece
### construction white vitreous china squatting
### 17.6.1 Single squatting plate with 5 litre
### P.V.C. automatic flushing cistern
### Details of cost for one no.
### MATERIAL
### 1915 Vitreous china squatting plate urinal each 1 1053
### 7359 P.V.C. automatic flushing cistern 5 lts capacity each 1 470
### 1540 Flush pipe and spreaders G.I.for single set of one each 1 175
### squatting plate urinal
### 9999 Red lead, white lead and gaskit L.S. 17.55 2
###
###
###
###
###
### 1309
###
###
### 9999 Cement, sand and grit etc. L.S. 26.91 2
### 9999 Painting of fittings etc. L.S. 26 2
### 9977 Carriage of materials L.S. 26.91 2
### LABOUR
### 19 Fitter (grade 1) day 1.75 505.17
### 23 Mason (brick layer) 1st class day 0.75 505.17
### 17 Beldar day 3 350.00
### TOTAL
### Add 1 % Water charges on "W"
### TOTAL
### Add GST (multiplying factor 0.1405) on "X"
### TOTAL
### Add 15 % Contractor's profit and overheads on "Y"
### Total
### Add Cess @ 1% on "Z"
### Cost of each
### Say
###
### 17.6.2 Range of two squatting plates with
### 5 litre P.V.C. automatic flushing cistern
### Details of cost for one no.
### MATERIAL
### 1915 Vitreous china squatting plate urinal each 2 1053
### 7359 P.V.C. automatic flushing cistern 5 lts capacity each 1 470
### 1541 Flush pipe and spreaders G.I.for range of two each 1 250
### squatting plates urinal
### 9999 Red lead, white lead and gaskit L.S. 17.55 2
### 9999 Cement, sand and grit etc. L.S. 53.82 2
### 9999 Painting of fittings etc. L.S. 26 2
### 9977 Carriage of materials L.S. 33.15 2
### LABOUR
### 19 Fitter (grade 1) day 2.5 505.17
### 23 Mason (brick layer) 1st class day 1 505.17
### 17 Beldar day 4 350.00
### TOTAL
### Add 1 % Water charges on "W"
###
###
###
###
###
### 1310
###
###
### TOTAL
### Add GST (multiplying factor 0.1405) on "X" 856.59
### TOTAL
### Add 15 % Contractor's profit and overheads on "Y" 1043
### Total
### Add Cess @ 1% on "Z" 79.96
### Cost of each 8076.27
### Say
###
### 17.6.3 Range of three squatting plates
### with 10 litre P.V.C. automatic flushing
### Details of cost for one no.
### MATERIAL
### 1915 Vitreous china squatting plate urinal each 3 1053
### 7361 P.V.C. automatic flushing cistern 10 lts capacity each 1 510
### 1542 Flush pipe and spreaders G.I.for range of three each 1 300
### squatting plates urinal
### 9999 Red lead, white lead and gaskit L.S. 17.55 2
### 9999 Cement, sand and grit etc. L.S. 80.73 2
### 9999 Painting of fittings etc. L.S. 26 2
### 9977 Carriage of materials L.S. 42.12 2
### LABOUR
### 19 Fitter (grade 1) day 3 505.17
### 23 Mason (brick layer) 1st class day 1.5 505.17
### 17 Beldar day 5 350.00
### TOTAL
### Add 1 % Water charges on "W"
### TOTAL
### Add GST (multiplying factor 0.1405) on "X"
### TOTAL
### Add 15 % Contractor's profit and overheads on "Y"
### Total
### Add Cess @ 1% on "Z"
### Cost of each
### Say
###
### 17.6.4 Range of four squatting plates with
### 10 litre P.V.C. automatic flushing cistern
###
###
###
###
### 1311
###
###
### Details of cost for one no.
### MATERIAL
### 1915 Vitreous china squatting plate urinal each 4 1053
### 7361 P.V.C. automatic flushing cistern 10 lts capacity each 1 510
### 1543 Flush pipe and spreaders G.I.for range of four each 1 390
### squatting plates urinal
### 9999 Red lead, white lead and gaskit L.S. 17.55 2
### 9999 Cement, sand and grit etc. L.S. 107.64 2
### 9999 Painting of fittings etc. L.S. 26 2
### 9977 Carriage of materials L.S. 69.03 2
### LABOUR
### 19 Fitter (grade 1) day 3.5 505.17
### 23 Mason (brick layer) 1st class day 1.75 505.17
### 17 Beldar day 5.5 350.00
### TOTAL
### Add 1 % Water charges on "W"
### TOTAL
### Add GST (multiplying factor 0.1405) on "X"
### TOTAL
### Add 15 % Contractor's profit and overheads on "Y"
### Total
### Add Cess @ 1% on "Z"
### Cost of each
### Say
###
### 17.7 Providing and fixing wash basin with
### C.I. brackets, 15 mm C.P. brass pillar taps,
### 17.7.1 White Vitreous China Wash basin
### size 630x450 mm with a pair of 15 mm C.P.
### brass pillar taps
###
### Details of cost for one no.
###
### MATERIAL
### 1947 Vitreous china flat back wash basin 630x450 mm each 1 725
### 1885 15 mm C.P.brass tap each 2 207
### 1951 C.P. brass waste 32 mm each 1 80
### 1309 C.I. bracket for wash basin and sinks pair 1 88
### 9999 Red lead, white lead and gaskit L.S. 16.12 2
### 9999 Cement, sand and grit etc. L.S. 13.39 2
###
###
###
###
###
###
### 1312
###
###
### 9999 Painting of brackets, fittings etc. L.S. 26.91 2
### 9977 Carriage of materials L.S. 13.52 2
### LABOUR
### 19 Fitter (grade 1) day 0.33 505.17
### 23 Mason (brick layer) 1st class day 0.33 505.17
### 17 Beldar day 0.67 350.00
### TOTAL
### Add 1 % Water charges on "W"
### TOTAL
### Add GST (multiplying factor 0.1405) on "X"
### TOTAL
### Add 15 % Contractor's profit and overheads on "Y"
### Total
### Add Cess @ 1% on "Z"
### Cost of each
### Say
###
### 17.7.2 White Vitreous China Wash basin
### size 630x450 mm with a single 15 mm C.P.
### brass pillar tap
###
### Details of cost for one no.
###
### MATERIAL
### 1947 Vitreous china flat back wash basin 630x450 mm each 1 725
### 1885 15 mm C.P.brass tap each 1 207
### 1951 C.P. brass waste 32 mm each 1 80
### 1309 C.I. bracket for wash basin and sinks pair 1 88
### 9999 Red lead, white lead and gaskit L.S. 16.12 2
### 9999 Cement, sand and grit etc. L.S. 13.39 2
### 9999 Painting of brackets, fittings etc. L.S. 26.91 2
### 9977 Carriage of materials L.S. 13.52 2
### LABOUR
### 19 Fitter (grade 1) day 0.3 505.17
### 23 Mason (brick layer) 1st class day 0.33 505.17
### 17 Beldar day 0.63 350.00
### TOTAL
### Add 1 % Water charges on "W"
### TOTAL
### Add GST (multiplying factor 0.1405) on "X"
###
###
###
###
###
###
### 1313
###
###
### TOTAL
### Add 15 % Contractor's profit and overheads on "Y" 300.97
### Total
### Add Cess @ 1% on "Z" 23.07
### Cost of each 2330.53
### Say
###
### 17.7.3 White Vitreous China Wash basin
### size 550x400 mm with a pair of 15 mm C.P.
### brass pillar taps
###
### Details of cost for one no.
###
### MATERIAL
### 3229 Vitreous china flat back wash basin 550x400 mm each 1 545
### 1885 15 mm C.P.brass tap each 2 207
### 1951 C.P. brass waste 32 mm each 1 80
### 1309 C.I. bracket for wash basin and sinks pair 1 88
### 9999 Red lead, white lead and gaskit L.S. 16.12 2
### 9999 Cement, sand and grit etc. L.S. 13.39 2
### 9999 Painting of brackets, fittings etc. L.S. 26.91 2
### 9977 Carriage of materials L.S. 13.52 2
### LABOUR
### 19 Fitter (grade 1) day 0.33 505.17
### 23 Mason (brick layer) 1st class day 0.33 505.17
### 17 Beldar day 0.67 350.00
### TOTAL
### Add 1 % Water charges on "W"
### TOTAL
### Add GST (multiplying factor 0.1405) on "X"
### TOTAL
### Add 15 % Contractor's profit and overheads on "Y"
### Total
### Add Cess @ 1% on "Z"
### Cost of each
### Say
###
### 17.7.4White Vitreous China Flat back
### wash basin size 550x 400 mm with single
###
###
###
###
### 1314 40
###
###
### Details of cost for one no.
### MATERIAL
### 3229 Vitreous china flat back wash basin 550x400 mm each 1 545
### 1885 15 mm C.P.brass tap each 1 207
### 1951 C.P. brass waste 32 mm each 1 80
### 1309 C.I. bracket for wash basin and sinks pair 1 88
### 9999 Red lead, white lead and gaskit L.S. 16.12 2
### 9999 Cement, sand and grit etc. L.S. 13.39 2
### 9999 Painting of brackets, fittings etc. L.S. 26.91 2
### 9977 Carriage of materials L.S. 13.52 2
### LABOUR
### 19 Fitter (grade 1) day 0.3 505.17
### 23 Mason (brick layer) 1st class day 0.33 505.17
### 17 Beldar day 0.63 350.00
### TOTAL
### Add 1 % Water charges on "W"
### TOTAL
### Add GST (multiplying factor 0.1405) on "X"
### TOTAL
### Add 15 % Contractor's profit and overheads on "Y"
### Total
### Add Cess @ 1% on "Z"
### Cost of each
### Say
###
### 17.7.5 White Vitreous China Angle back
### wash basin size 600 x 480 mm with single
### mm C.P. brass pillar tap
###
### Details of cost for one no.
###
### MATERIAL
### 1949 Vitreous china angle back wash basin 600x480 mm each 1 725
### 1885 15 mm C.P.brass tap each 1 207
### 1951 C.P. brass waste 32 mm each 1 80
### 1309 C.I. bracket for wash basin and sinks pair 1 88
### 9999 Red lead, white lead and gaskit L.S. 16.12 2
### 9999 Cement, sand and grit etc. L.S. 13.39 2
### 9999 Painting of brackets, fittings etc. L.S. 26.91 2
### 9977 Carriage of materials L.S. 13.52 2
### LABOUR
###
###
###
###
###
###
### 1315 40
###
###
### 19 Fitter (grade 1) day 0.3 505.17
### 23 Mason (brick layer) 1st class day 0.33 505.17
### 17 Beldar day 0.63 350.00
### TOTAL
### Add 1 % Water charges on "W"
### TOTAL
### Add GST (multiplying factor 0.1405) on "X"
### TOTAL
### Add 15 % Contractor's profit and overheads on "Y"
### Total
### Add Cess @ 1% on "Z"
### Cost of each
### Say
###
### 17.7.6 White Vitreous China Angle back
### wash basin size 400 x 400 mm with single
### Details of cost for one no.
### MATERIAL
### 1950 Vitreous china angle back wash basin 400x400 mm each 1 425
### 1885 15 mm C.P.brass tap each 1 207
### 1951 C.P. brass waste 32 mm each 1 80
### 1309 C.I. bracket for wash basin and sinks pair 1 88
### 9999 Red lead, white lead and gaskit L.S. 16.12 2
### 9999 Cement, sand and grit etc. L.S. 13.39 2
### 9999 Painting of brackets, fittings etc. L.S. 26.91 2
### 9977 Carriage of materials L.S. 13.52 2
### LABOUR
### 19 Fitter (grade 1) day 0.3 505.17
### 23 Mason (brick layer) 1st class day 0.33 505.17
### 17 Beldar day 0.63 350.00
### TOTAL
### Add 1 % Water charges on "W"
### TOTAL
### Add GST (multiplying factor 0.1405) on "X"
### TOTAL
### Add 15 % Contractor's profit and overheads on "Y"
###
###
###
###
###
### 1316
###
###
### Total
### Add Cess @ 1% on "Z" 19.1
### Cost of each 1929.15
### Say
###
### 17.7.7 White Vitreous China Flat back
### wash basin size 450x 300 mm with single
### mm C.P. brass pillar tap
### Details of cost for one no.
###
### MATERIAL
### 7004 Vitreous china flat back wash basin 450x300 mm each 1 310
### 1885 15 mm C.P.brass tap each 1 207
### 1951 C.P. brass waste 32 mm each 1 80
### 1309 C.I. bracket for wash basin and sinks pair 1 88
### 9999 Red lead, white lead and gaskit L.S. 16.12 2
### 9999 Cement, sand and grit etc. L.S. 13.39 2
### 9999 Painting of brackets, fittings etc. L.S. 26.91 2
### 9977 Carriage of materials L.S. 13.52 2
### LABOUR
### 19 Fitter (grade 1) day 0.3 505.17
### 23 Mason (brick layer) 1st class day 0.33 505.17
### 17 Beldar day 0.63 350.00
### TOTAL
### Add 1 % Water charges on "W"
### TOTAL
### Add GST (multiplying factor 0.1405) on "X"
### TOTAL
### Add 15 % Contractor's profit and overheads on "Y"
### Total
### Add Cess @ 1% on "Z"
### Cost of each
### Say
###
### 17.7.8 White Vitreous China Surgeon type
### wash basin of size 660x460 mm with a pair
### Details of cost for one no.
###
### MATERIAL
###
###
###
###
###
###
### 1317
###
###
### 3213 Vitreous china Surgeon type wash basin of size each 1 1000
### 660x460 mm
### 7363 15 mm C.P. brass tap with elbow operation lever each 2 430
### 1951 C.P. brass waste 32 mm each 1 80
### 1309 C.I. bracket for wash basin and sinks pair 1 88
### 9999 Red lead, white lead and gaskit L.S. 16.12 2
### 9999 Cement, sand and grit etc. L.S. 13.39 2
### 9999 Painting of brackets, fittings etc. L.S. 26.91 2
### 9977 Carriage of materials L.S. 13.52 2
### LABOUR
### 19 Fitter (grade 1) day 0.33 505.17
### 23 Mason (brick layer) 1st class day 0.33 505.17
### 17 Beldar day 0.67 350.00
### TOTAL
### Add 1 % Water charges on "W"
### TOTAL
### Add GST (multiplying factor 0.1405) on "X"
### TOTAL
### Add 15 % Contractor's profit and overheads on "Y"
### Total
### Add Cess @ 1% on "Z"
### Cost of each
### Say
###
### 17.7.9 White Vitreous China Surgeon type
### wash basin of size 660x460 mm with single
### Details of cost for one no.
### MATERIAL
### 3213 Vitreous china Surgeon type wash basin of size each 1 1000
### 7363 660x460 mm
### 15 mm C.P. brass tap with elbow operation lever each 1 430
### 1951 C.P. brass waste 32 mm each 1 80
### 1309 C.I. bracket for wash basin and sinks pair 1 88
### 9999 Red lead, white lead and gaskit L.S. 16.12 2
### 9999 Cement, sand and grit etc. L.S. 13.39 2
### 9999 Painting of brackets, fittings etc. L.S. 26.91 2
### 9977 Carriage of materials L.S. 13.52 2
### LABOUR
### 19 Fitter (grade 1) day 0.3 505.17
###
###
###
###
###
###
### 1318
###
###
### 23 Mason (brick layer) 1st class day 0.33 505.17
### 17 Beldar day 0.63 350.00
### TOTAL
### Add 1 % Water charges on "W"
### TOTAL
### Add GST (multiplying factor 0.1405) on "X"
### TOTAL
### Add 15 % Contractor's profit and overheads on "Y"
### Total
### Add Cess @ 1% on "Z"
### Cost of each
### Say
###
### 17.7.10 Stainless Steel AISI-304(18/8)
### Round basin 405x355 mm with single 15
### C.P. brass pillar tap
###
### Details of cost for one no.
###
### MATERIAL
### 7806 Salem Stainless steel AISI - 304 (18/8) each 1 1500
### Round basin 405mm X 355mm
### 1885 15 mm C.P.brass tap each 1 207
### 1951 C.P. brass waste 32 mm each 1 80
### 1309 C.I. bracket for wash basin and sinks pair 1 88
### 9999 Red lead, white lead and gaskit L.S. 16.12 2
### 9999 Cement, sand and grit etc. L.S. 13.39 2
### 9999 Painting of brackets, fittings etc. L.S. 26.91 2
### 9977 Carriage of materials L.S. 13.52 2
### LABOUR
### 19 Fitter (grade 1) day 0.3 505.17
### 23 Mason (brick layer) 1st class day 0.33 505.17
### 17 Beldar day 0.63 350.00
### TOTAL
### Add 1 % Water charges on "W"
### TOTAL
### Add GST (multiplying factor 0.1405) on "X"
### TOTAL
### Add 15 % Contractor's profit and overheads on "Y"
### Total
###
###
###
###
### 1319
###
###
### Add Cess @ 1% on "Z" 33.34
### Cost of each 3367.43
### Say
###
### 17.7.11Stainless Steel AISI-304(18/8)
### Wash basin 530x345 mm with single 15 mm
### brass pillar tap
###
### Details of cost for one no.
###
### MATERIAL
### 7807 Salem Stainless steel AISI - 304 (18/8) each 1 2000
### Wash basin 530mm X 345mm
### 1885 15 mm C.P.brass tap each 1 207
### 1951 C.P. brass waste 32 mm each 1 80
### 1309 C.I. bracket for wash basin and sinks pair 1 88
### 9999 Red lead, white lead and gaskit L.S. 16.12 2
### 9999 Cement, sand and grit etc. L.S. 13.39 2
### 9999 Painting of brackets, fittings etc. L.S. 26.91 2
### 9977 Carriage of materials L.S. 13.52 2
### LABOUR
### 19 Fitter (grade 1) day 0.3 505.17
### 23 Mason (brick layer) 1st class day 0.33 505.17
### 17 Beldar day 0.63 350.00
### TOTAL
### Add 1 % Water charges on "W"
### TOTAL
### Add GST (multiplying factor 0.1405) on "X"
### TOTAL
### Add 15 % Contractor's profit and overheads on "Y"
### Total
### Add Cess @ 1% on "Z"
### Cost of each
### Say
### 17.7A Providing and fixing wash basin with C.I.
### brackets,
hole basin15 mm dia
mixer CP Brassquality
of approved single and
make, including painting of fittings
### and brackets, cutting and making good the
### walls wherever required:-
### (a) White Vitreous China Wash basin size
### 550x400 mmDetails
with aof15 mm
cost for CP
1 no.Brass single
###
### MATERIAL
### 3229 Vitreous china flat back wash basin 550x400 mm each 1 545
### 9001 C.P. Brass Centre Hole Basin Mixer With each 1 1600
###
###
###
###
###
###
### 1320
###
###
### Cast Spout ( Kigston/Marc/Prima/ Parko/
### Hindware)
### 1951 C.P. brass waste 32 mm each 1 80
### 1309 C.I. bracket for wash basin and sinks pair 1 88
### 9999 Red lead, white lead and gaskit L.S. 16.12 2
### 9999 Cement, Sand and grit etc. L.S. 13.39 2
### 9999 Painting of brackets, fittings etc. L.S. 26.91 2
### 9977 Carriage of materials L.S. 13.52 2
### LABOUR
### 19 Fitter (grade 1) day 0.33 505.17
### 23 Mason (brick layer) 1st class day 0.33 505.17
### 17 Beldar day 0.63 350.00
### TOTAL
### Add 1 % Water charges on "W"
### TOTAL
### Add GST (multiplying factor 0.1405) on "X"
### TOTAL
### Add 15 % Contractor's profit and overheads on "Y"
### Total
### Add Cess @ 1% on "Z"
### Cost of each
### Say
### 17.7B Providing and fixing wash basin with C.I.
### brackets,
mm PTMT15 mm coupling
waste PTMT pillar
of cock, 32
standard
### pattern,
and including
brackets, painting
cutting of fittings
and making good the
### walls wherever
Vitreous required.
China Flat White basin size
back wash
### 550x400 mm with
PTMT pillar cock. single 15 mm
### Details of cost for 1 No.
### MATERIAL
### 3229 Vitreous china flat back wash basin 550x400 mm each 1 545
### 7406 PTMT pillar cock each 1 125
### 7491 PTMT - Waste Coupling 31/32 mm each 1 34
### 1309 C.I. bracket for wash basin and sinks pair 1 88
### 9999 Red Lead, White Lead and Gasket L.S. 16.12 2
### 9999 Cement, sand and grit etc L.S. 13.39 2
### 9999 Painting of brackets, fittings etc. L.S. 26.91 2
### 9977 Carriage of materials L.S. 13.52 2
### LABOUR
### 19 Fitter (grade 1) day 0.33 505.17
###
###
###
###
###
### 1321
###
###
### 23 Mason (brick layer) 1st class day 0.33 505.17
### 17 Beldar day 0.67 350.00
### TOTAL
### Add 1 % Water charges on "W"
### TOTAL
### Add GST (multiplying factor 0.1405) on "X"
### TOTAL
### Add 15 % Contractor's profit and overheads on "Y"
### Total
### Add Cess @ 1% on "Z"
### Cost of each
### Say
###
### 17.8 Providing and fixing white vitreous
### china pedestal for wash basin completely
### recessed at the back for the reception of
### pipes and fittings.
### Details of cost for one pedestal
### MATERIAL
### 1396 Vitrous china pedestal for wash basin each 1 900
### 9999 White cement mortar L.S. 40.3 2
### 9988 Carriage of materials and fixing charges L.S. 40.43 2
### TOTAL
### Add 1 % Water charges on "W"
### TOTAL
### Add GST (multiplying factor 0.1405) on "X"
### TOTAL
### Add 15 % Contractor's profit and overheads on "Y"
### Total
### Add Cess @ 1% on "Z"
### Cost of each
### Say
###
### 17.9 Providing and fixing kitchen sink
### with C.I. brackets, C.P. brass chain with
### and brackets, cutting and making good the
### walls wherever required:
### 17.9.1 White glazed fire clay kitchen sink
### of size 600x450x 250 mm
### Details of cost for one no.
### MATERIAL
### 1863 Fire clay kitchen sink: 600x450x250 mm each 1 1283
### 1309 C.I. bracket for wash basin and sinks pair 1 88
### 1315 C.P.brass chain with 40 mm dia rubber plug each 1 40
### 1952 C.P. brass waste 40 mm each 1 95
###
###
###
###
###
### 1322
###
###
### 9999 Red lead, white lead and gaskit L.S. 16.12 2
### 9999 Cement, sand and grit etc. L.S. 13.39 2
### 9999 Painting brackets etc. L.S. 26.91 2
### 9977 Carriage of materials L.S. 13.52 2
### LABOUR
### 19 Fitter (grade 1) day 0.22 505.17
### 23 Mason (brick layer) 1st class day 0.33 505.17
### 17 Beldar day 0.56 350.00
### TOTAL
### Add 1 % Water charges on "W"
### TOTAL
### Add GST (multiplying factor 0.1405) on "X"
### TOTAL
### Add 15 % Contractor's profit and overheads on "Y"
### Total
### Add Cess @ 1% on "Z"
### Cost of each
### Say
###
### 17.10 Providing and fixing Stainless Steel
### A ISI 304 (18/8) kitchen sink as per IS:
### fittings and brackets, cutting and making
### good the walls wherever required :
### 17.10.1 Kitchen sink with drain board
###
### 17.10.1.1 510x1040 mm bowl depth 250 mm
### Details of cost for one no.
### MATERIAL
### 7095 Stainless steel kitchen sink - with drain board bowl each 1 2480
### depth 250 mm.
### 1309 C.I. bracket for wash basin and sinks pair 2 88
### 9999 Cement, sand and grit etc. L.S. 27.04 2
### 9999 Painting of brackets etc. L.S. 26.91 2
### 9977 Carriage of materials L.S. 13.52 2
### LABOUR
### 19 Fitter (grade 1) day 0.22 505.17
### 23 Mason (brick layer) 1st class day 0.6 505.17
### 17 Beldar day 0.82 350.00
### TOTAL
### Add 1 % Water charges on "W"
### TOTAL
### Add GST (multiplying factor 0.1405) on "X"
### TOTAL
### Add 15 % Contractor's profit and overheads on "Y"
###
###
###
###
### 1323
###
###
### Total
### Add Cess @ 1% on "Z"
### Cost of each
### Say
### 17.10.1.2 510x1040 mm bowl depth 225 mm
### Details of cost for one no.
### MATERIAL
### 7096 Stainlees steel kitchen sink - with drain board 510 x each 1 3000
### 1040mm bowl depth 225 mm.
### 1309 C.I. bracket for wash basin and sinks pair 2 88
### 9999 Cement, sand and grit etc. L.S. 27.04 2
### 9999 Painting of brackets etc. L.S. 26.91 2
### 9977 Carriage of materials L.S. 13.52 2
### LABOUR
### 19 Fitter (grade 1) day 0.22 505.17
### 23 Mason (brick layer) 1st class day 0.6 505.17
### 17 Beldar day 0.82 350.00
### TOTAL
### Add 1 % Water charges on "W"
### TOTAL
### Add GST (multiplying factor 0.1405) on "X"
### TOTAL
### Add 15 % Contractor's profit and overheads on "Y"
### Total
### Add Cess @ 1% on "Z"
### Cost of each
### Say
### 17.10.1.3 510x1040 mm bowl depth 200 mm
### Details of cost for one no.
### MATERIAL
### 7097 Stainlees steel kitchen sink - with drain board 510 x each 1 2800
### 1040mm bowl depth 200 mm.
### 1309 C.I. bracket for wash basin and sinks pair 2 88
### 9999 Cement, sand and grit etc. L.S. 27.04 2
### 9999 Painting of brackets etc. L.S. 26.91 2
### 9977 Carriage of materials L.S. 13.52 2
### LABOUR
### 19 Fitter (grade 1) day 0.22 505.17
###
###
###
###
###
###
### 1324
###
###
### 23 Mason (brick layer) 1st class day 0.6 505.17
### 17 Beldar day 0.82 350.00
### TOTAL
### Add 1 % Water charges on "W"
### TOTAL
### Add GST (multiplying factor 0.1405) on "X"
### TOTAL
### Add 15 % Contractor's profit and overheads on "Y"
### Total
### Add Cess @ 1% on "Z"
### Cost of each
### Say
### 17.10.1.4 510x1040 mm bowl depth 178 mm
### Details of cost for one no.
### MATERIAL
### 7098 Stainless steel kitchen sink - with drain board each 1 2500
### 510x1040mm bowl depth 178 mm
### 1309 C.I. bracket for wash basin and sinks pair 2 88
### 9999 Cement, sand and grit etc. L.S. 27.04 2
### 9999 Painting brackets L.S. 26.91 2
### 9977 Carriage of materials L.S. 13.52 2
### LABOUR
### 19 Fitter (grade 1) day 0.22 505.17
### 23 Mason (brick layer) 1st class day 0.6 505.17
### 17 Beldar day 0.82 350.00
### TOTAL
### Add 1 % Water charges on "W"
### TOTAL
### Add GST (multiplying factor 0.1405) on "X"
### TOTAL
### Add 15 % Contractor's profit and overheads on "Y"
### Total
### Add Cess @ 1% on "Z"
### Cost of each
### Say
###
### 17.10.2 Kitchen sink without drain board
### 17.10.2.1 610x510 mm bowl depth 200 mm
### Details of cost for one no.
### MATERIAL
### 7101 Stainless steel kitchen sink - without drain board each 1 1800
### 610x510mm bowl depth 200 mm
### 1309 C.I. bracket for wash basin and sinks pair 1 88
###
###
###
###
###
###
### 1325
###
###
### 9999 Cement, sand and grit etc. L.S. 13.52 2
### 9999 Painting brackets L.S. 26.91 2
### 9977 Carriage of materials L.S. 13.52 2
### LABOUR
### 19 Fitter (grade 1) day 0.22 505.17
### 23 Mason (brick layer) 1st class day 0.33 505.17
### 17 Beldar day 0.56 350.00
### TOTAL
### Add 1 % Water charges on "W"
### TOTAL
### Add GST (multiplying factor 0.1405) on "X"
### TOTAL
### Add 15 % Contractor's profit and overheads on "Y"
### Total
### Add Cess @ 1% on "Z"
### Cost of each
### Say
### 17.10.2.2 610x460 mm bowl depth 200 mm
### Details of cost for one no.
### MATERIAL
### 7102 Stainless steel kitchen sink - without drain board each 1 1200
### 610x460mm bowl depth 200 mm.
### 1309 C.I. bracket for wash basin and sinks pair 1 88
### 9999 Cement, sand and grit etc. L.S. 13.52 2
### 9999 Painting brackets L.S. 26.91 2
### 9977 Carriage of materials L.S. 13.52 2
### LABOUR
### 19 Fitter (grade 1) day 0.22 505.17
### 23 Mason (brick layer) 1st class day 0.33 505.17
### 17 Beldar day 0.56 350.00
### TOTAL
### Add 1 % Water charges on "W"
### TOTAL
### Add GST (multiplying factor 0.1405) on "X"
### TOTAL
###
###
###
###
###
###
###
### 1326
###
###
### Add 15 % Contractor's profit and overheads on "Y"
### Total
### Add Cess @ 1% on "Z"
### Cost of each
### Say
### 17.10.2.3 470x420 mm bowl depth 178 mm
### Details of cost for one no.
### MATERIAL
### 7103 Stainless steel kitchen sink - without drain board each 1 1050
### 470x420mm bowl depth 178 mm
### 1309 C.I. bracket for wash basin and sinks pair 1 88
### 9999 Cement, sand and grit etc. L.S. 13.52 2
### 9999 Painting brackets L.S. 26.91 2
### 9977 Carriage of materials L.S. 13.52 2
### LABOUR
### 19 Fitter (grade 1) day 0.22 505.17
### 23 Mason (brick layer) 1st class day 0.33 505.17
### 17 Beldar day 0.56 350.00
### TOTAL
### Add 1 % Water charges on "W"
### TOTAL
### Add GST (multiplying factor 0.1405) on "X"
### TOTAL
### Add 15 % Contractor's profit and overheads on "Y"
### Total
### Add Cess @ 1% on "Z"
### Cost of each
### Say
###
### 17.11 Providing and fixing white vitreous china
### laboratory sink with C.I. brackets, C.P.
### 17.11.1 Size 450x300x150 mm
###
### Details of cost for one no.
### MATERIAL
### 1871 White vitreous china laboratry sink 450x300x150 mm each 1 1500
### 1309 C.I. bracket for wash basin and sinks pair 1 88
### 1315 C.P.brass chain with 40 mm dia rubber plug each 1 40
### 1952 C.P. brass waste 40 mm each 1 95
###
###
###
###
###
###
### 1327
###
###
### 1895 C.P.brass trap40 mm dia each 1 300
### 3617 C.P.brass union 40 mm dia each 1 200
### 9999 Red lead, white lead and gaskit L.S. 16.12 2
### 9999 Cement, sand and grit etc. L.S. 13.39 2
### 9999 Sundries L.S. 26.91 2
### 9977 Carriage of materials L.S. 13.52 2
### LABOUR
### 19 Fitter (grade 1) day 0.22 505.17
### 23 Mason (brick layer) 1st class day 0.33 505.17
### 17 Beldar day 0.56 350.00
### TOTAL
### Add 1 % Water charges on "W"
### TOTAL
### Add GST (multiplying factor 0.1405) on "X"
### TOTAL
### Add 15 % Contractor's profit and overheads on "Y"
### Total
### Add Cess @ 1% on "Z"
### Cost of each
### Say
###
### 17.11.2 Size 600x450x200 mm
###
### Details of cost for one no.
### MATERIAL
### 1872 White vitreous china laboratry sink 600x450x200 mm each 1 2500
### 1309 C.I. bracket for wash basin and sinks pair 1 88
### 1315 C.P.brass chain with 40 mm dia rubber plug each 1 40
### 1952 C.P. brass waste 40 mm each 1 95
### 1895 C.P.brass trap40 mm dia each 1 300
### 3617 C.P.brass union 40 mm dia each 1 200
### 9999 Red lead, white lead and gaskit L.S. 16.12 2
### 9999 Cement, sand and grit etc. L.S. 13.39 2
### 9999 Sundries L.S. 26.91 2
### 9977 Carriage of materials L.S. 13.52 2
### LABOUR
### 19 Fitter (grade 1) day 0.22 505.17
###
###
###
###
###
###
### 1328
###
###
### 23 Mason (brick layer) 1st class day 0.33 505.17
### 17 Beldar day 0.56 350.00
### TOTAL
### Add 1 % Water charges on "W"
### TOTAL
### Add GST (multiplying factor 0.1405) on "X"
### TOTAL
### Add 15 % Contractor's profit and overheads on "Y"
### Total
### Add Cess @ 1% on "Z"
### Cost of each
### Say
###
### 17.12 Providing and fixing draining board with
### C.I. brackets including painting of
### brackets, cutting and making good the
### walls wherever required :
### 17.12.1 White glazed fire clay draining board of
### size 600x450x 25 mm
### Details of cost for one no.
### MATERIAL
### 7364 White glazed fire clay draining board 600x450x25 each 1 525
### mm
### 1309 C.I. bracket for wash basin and sinks pair 1 88
### 9999 Cement, sand and grit etc. L.S. 13.39 2
### 9999 Painting brackets etc. L.S. 26 2
### 9977 Carriage of materials L.S. 7.8 2
### LABOUR
### 19 Fitter (grade 1) day 0.06 505.17
### 23 Mason (brick layer) 1st class day 0.17 505.17
### 17 Beldar day 0.22 350.00
### TOTAL
### Add 1 % Water charges on "W"
### TOTAL
### Add GST (multiplying factor 0.1405) on "X"
### TOTAL
### Add 15 % Contractor's profit and overheads on "Y"
### Total
### Add Cess @ 1% on "Z"
###
###
###
###
###
###
### 1329
###
###
### Cost of each 1187.34
### Say
###
### 17.13 Providing and fixing white vitreous china
### water closet squatting pan (Indian type) :
### 17.13.1 Long pattern W.C. pan of size 580 mm
###
### Details of cost for one no.
### MATERIAL
### 1953 Vitreous china indian type w.c. pan size each 1 450
### 580 mm
### 9999 Cement, sand and grit etc. L.S. 13.39 2
### 9977 Carriage of materials L.S. 13.52 2
### LABOUR
### 23 Mason (brick layer) 1st class day 0.5 505.17
### 17 Beldar day 0.5 350.00
### TOTAL
### Add 1 % Water charges on "W"
### TOTAL
### Add GST (multiplying factor 0.1405) on "X"
### TOTAL
### Add 15 % Contractor's profit and overheads on "Y"
### Total
### Add Cess @ 1% on "Z"
### Cost of each
### Say
###
### 17.13.2 Orissa pattern W.C. pan of size 580x440
### mm
### Details of cost for one no.
### MATERIAL
### 1954 Vitreous china orrisa type w.c. pan size each 1 1200
### 580 mm
### 9999 Cement, sand and grit etc. L.S. 13.39 2
### 9977 Carriage of materials L.S. 13.52 2
### LABOUR
### 23 Mason (brick layer) 1st class day 0.5 505.17
### 17 Beldar day 0.5 350.00
### TOTAL
### Add 1 % Water charges on "W"
### TOTAL
###
###
###
###
### 1330
###
###
### Add GST (multiplying factor 0.1405) on "X" 234.46
### TOTAL
### Add 15 % Contractor's profit and overheads on "Y" 285.48
### Total
### Add Cess @ 1% on "Z" 21.89
### Cost of each 2210.59
### Say
###
### 17.14 Extra for using coloured W.C. pan instead
### of white W.C. pan :
### 17.14.1 Orissa pattern W.C. pan 580x440 mm
###
### Details of cost for one no.
###
### MATERIAL Difference in cost of

### 7104 Coloured Orissa pattern W.C. pan 580x440 mm each 1 1830
### 1954 Vitreous china orrisa type w.c. pan size each -1 1200
### 580 mm
### TOTAL
### Add 1 % Water charges on "W"
### TOTAL
### Add GST (multiplying factor 0.1405) on "X"
### TOTAL
### Add 15 % Contractor's profit and overheads on "Y"
### Total
### Add Cess @ 1% on "Z"
### Cost of each
### Say
###
### 17.15 Providing and fixing white vitreous china
### pedestal type (European type/ wash
### down type) water closet pan.
###
### Details of cost for one no.
###
### MATERIAL
### 1955 Vitreous china pedestal type water closet each 1 1000
### 9999 Cement, sand and grit etc. L.S. 13.39 2
### 9977 Carriage of materials L.S. 13.52 2
###
###
###
###
###
###
### 1331 30
###
###
### LABOUR
### 23 Mason (brick layer) 1st class day 0.5 505.17
### 17 Beldar day 0.5 350.00
### TOTAL
### Add 1 % Water charges on "W"
### TOTAL
### Add GST (multiplying factor 0.1405) on "X"
### TOTAL
### Add 15 % Contractor's profit and overheads on "Y"
### Total
### Add Cess @ 1% on "Z"
### Cost of each
### Say
###
### 17.16 Extra for using coloured pedestal type
### W.C pan (European type) with low level
### Details of cost for one no.
### MATERIAL
### 7105 Coloured Pedestal type W.C. pan each 1 860
### 580x440 mm (European type)
### Deduct
### 1955 Vitreous china pedestal type water closet each -1 1000
### 7106 Coloured Vitreous china 10 lit. low level cistern each 1 1050
### Deduct
### 7005 Vitreous china 10 litres low level cistern without each -1 715
### fittings
### TOTAL
### Add 1 % Water charges on "W"
### TOTAL
### Add GST (multiplying factor 0.1405) on "X"
### TOTAL
### Add 15 % Contractor's profit and overheads on "Y"
### Total
### Add Cess @ 1% on "Z"
### Cost of each
### Say
###
###
###
###
###
###
### 1332
###
###
###
### 17.16A Providing and fixing 8 mm dia C.P. / S.S.
### Jet
longwith
withflexible tube upto
S.S. triangular 1 metre
plate to Eureopean
### type W.C. by
approved of quality
Engineerand make
- in as
- charge.
### Details of cost for 1 No.
### 1313 8 mm dia C.P. Brass/ S.S. Jet with flexible tube upto each 1 200
### 1 metre long with S.S. tringular plate for Eureopean
### type W.C.(Hindware/ Kingston/Prima/Parko/Marc)
### 9999 Carriage of material and fixing charges L.S. 11.2 2
### TOTAL
### Add 1 % Water charges on "W"
### TOTAL
### Add GST (multiplying factor 0.1405) on "X"
### TOTAL
### Add 15 % Contractor's profit and overheads on "Y"
### Total
### Add Cess @ 1% on "Z"
### Cost of each
### Say
###
### 17.17 Providing and fixing a pair of white
### vitreous china foot rests of standard
### 17.17.1 pattern for squatting pan water closet :
### 250x130x30 mm
### Details of cost for one pair
### MATERIAL
### 1363 Vitreous china foot rests 250x130x30 mm pair 1 100
### 9988 Cement, sand including carriage of materials L.S. 8.06 2
### LABOUR
### 23 Mason (brick layer) 1st class day 0.06 505.17
### TOTAL
### Add 1 % Water charges on "W"
### TOTAL
### Add GST (multiplying factor 0.1405) on "X"
### TOTAL
### Add 15 % Contractor's profit and overheads on "Y"
### Total
### Add Cess @ 1% on "Z"
### Cost for 1 pair
### Say
###
### 17.17.2 250x125x25 mm
###
### Details of cost for one pair
### MATERIAL
### 1970 Vitreous china foot rests 250x125x25 mm pair 1 100
### 9988 Cement, sand including carriage of materials L.S. 8.06 2
###
###
###
###
### 1333
###
###
### LABOUR
### 23 Mason (brick layer) 1st class day 0.06 505.17
### TOTAL
### Add 1 % Water charges on "W"
### TOTAL
### Add GST (multiplying factor 0.1405) on "X"
### TOTAL
### Add 15 % Contractor's profit and overheads on "Y"
### Total
### Add Cess @ 1% on "Z"
### Cost for 1 pair
### Say
###
### 17.18 Providing and fixing P.V.C. low level
### flushing cistern with manually controlled
### 17.18.1 complete.
### 10 litre capacity - White
### Details of cost for one no.
### MATERIAL
### 7358 Flushing Cistern P.V.C. 10 lts capacity (low level) each 1 575
### (White) (with fittings, accessories and
### flush pipe)
### 9977 Carriage of materials L.S. 5.2 2
### LABOUR
### (Considering 1 fitter and 1 beldar can fix
### 8 cistern in one day)
### 19 Fitter (grade 1) day 0.125 505.17
### 17 Beldar day 0.125 350.00
### TOTAL
### Add 1 % Water charges on "W"
### TOTAL
### Add GST (multiplying factor 0.1405) on "X"
### TOTAL
### Add 15 % Contractor's profit and overheads on "Y"
### Total
### Add Cess @ 1% on "Z"
### Cost of each
### Say
###
### 17.18.2 10 litre capacity - coloured
###
### Details of cost for one no.
###
### MATERIAL
###
###
###
###
###
###
###
### 1334
###
###
### 7123 Coloured High density polythylene/ poly propylene each 1 550
10
### lit. (full flush) capacity controlled low level flushing
### cistern with
### fittings
### 9977 Carriage of materials L.S. 7.02 2
### LABOUR
### (Considering 1 fitter and 1 beldar can fix
### 8 cistern in one day)
### 19 Fitter (grade 1) day 0.125 505.17
### 17 Beldar day 0.125 350.00
### TOTAL
### Add 1 % Water charges on "W"
### TOTAL
### Add GST (multiplying factor 0.1405) on "X"
### TOTAL
### Add 15 % Contractor's profit and overheads on "Y"
### Total
### Add Cess @ 1% on "Z"
### Cost of each
### Say
###
### 17.19 Providing and fixing controlled flush, low
### level cistern made of vitreous china with all
### 17.19.1 10 litre (full flush) capacity-white
###
### Details of cost for one no.
### MATERIAL
### 7126 White Vitreous china 10 lit. (full flush) capacity each 1 700
### controlled low level flushing
### cistern with all fittings
### 9977 Carriage of materials L.S. 13.52 2
### LABOUR
### 19 Fitter (grade 1) day 0.5 505.17
### 17 Beldar day 0.5 350.00
### TOTAL
### Add 1 % Water charges on "W"
### TOTAL
### Add GST (multiplying factor 0.1405) on "X"
### TOTAL
### Add 15 % Contractor's profit and overheads on "Y"
### Total
### Add Cess @ 1% on "Z"
### Cost of each
### Say
###
### 17.19.2 10 litre (full flush) capacity-
### coloured
###
###
###
###
### 1335
###
###
### Details of cost for one no.
### MATERIAL
### 7127 Coloured Vitreous china 10 lit. (full flush) capacity each 1 1150
### controlled low level flushing
### cistern with all fittings
### 9977 Carriage of materials L.S. 13.52 2
### LABOUR
### 19 Fitter (grade 1) day 0.5 505.17
### 17 Beldar day 0.5 350.00
### TOTAL
### Add 1 % Water charges on "W"
### TOTAL
### Add GST (multiplying factor 0.1405) on "X"
### TOTAL
### Add 15 % Contractor's profit and overheads on "Y"
### Total
### Add Cess @ 1% on "Z"
### Cost of each
### Say
###
### 17.20 Providing and fixing solid plastic
### seat with lid for pedestal type W.C. pan
### 17.20.1 complete :
### White solid plastic seat with lid
### Details of cost for one no.
### MATERIAL
### 1875 White plastic seat (solid)with lid C.P.brass hinges each 1 400
and
### 9988 rubber buffers 2
### Carriage of materials and fixing charges L.S. 13.39 2
### TOTAL
### Add 1 % Water charges on "W"
### TOTAL
### Add GST (multiplying factor 0.1405) on "X"
### TOTAL
### Add 15 % Contractor's profit and overheads on "Y"
### Total
### Add Cess @ 1% on "Z"
### Cost of each
### Say
###
### 17.20.2 Black solid plastic seat with lid
###
### Details of cost for one no.
###
### MATERIAL
###
###
###
###
###
###
### 1336
###
###
### 1876 Black plastic seat (solid) with lid C.P.brass hinges each 1 310
### 9988 and rubber buffers 2
### Carriage of materials and fixing charges L.S. 13.39 2
### TOTAL
### Add 1 % Water charges on "W"
### TOTAL
### Add GST (multiplying factor 0.1405) on "X"
### TOTAL
### Add 15 % Contractor's profit and overheads on "Y"
### Total
### Add Cess @ 1% on "Z"
### Cost of each
### Say
###
### 17.20.3 Coloured (other than black &
### white) solid plastic seat with lid
### Details of cost for one no.
### MATERIAL
### Difference in cost of
### 7107 Coloured (other than black) solid P.V.C. each 1 390
### seat in European W.C. pan
### 9988 Carriage of materials and fixing charges L.S. 13.39 2
### TOTAL
### Add 1 % Water charges on "W"
### TOTAL
### Add GST (multiplying factor 0.1405) on "X"
### TOTAL
### Add 15 % Contractor's profit and overheads on "Y"
### Total
### Add Cess @ 1% on "Z"
### Cost of each
### Say
###
### 17.22 Providing and fixing G.I. inlet
### connection for flush pipe connecting with
### pan.
###
### Details of cost for one no.
###
### MATERIAL
### 1614 G.I. inlet connection each 1 60
### 9988 Carriage of materials and fixing charges L.S. 13.39 2
###
###
###
###
###
### 1337
###
###
### TOTAL
### Add 1 % Water charges on "W"
### TOTAL
### Add GST (multiplying factor 0.1405) on "X"
### TOTAL
### Add 15 % Contractor's profit and overheads on "Y"
### Total
### Add Cess @ 1% on "Z"
### Cost of each
### Say
### 17.22A Providing and fixing CP Brass 32mm size
### Bottleand
make Trapasofperapproved qualityof&Engineer-
the direction
### in-charge.
Details of cost for 1 no.
### MATERIAL
### 7121 Bottle Trap (Hindware/ Kingston/ Prima/ Parko / Marc) each 1 620
### 9988 Carriage and sundries L.S. 20 2
### TOTAL
### Add 1 % Water charges on "W"
### TOTAL
### Add GST (multiplying factor 0.1405) on "X"
### TOTAL
### Add 15 % Contractor's profit and overheads on "Y"
### Total
### Add Cess @ 1% on "Z"
### Cost of each
### Say
### 17.22B Providing and fixing CP Brass Single lever
### telephonic
make wall mixer
as approved byof quality &
Engineer in charge.
### (a) 15 mm nominal dia
### Details of cost for 1 no.
### MATERIAL
### 7122 CP Brass Single lever telephonic wall mixer of each 1 4500
### approved make (Hindware/Kingston/ Prima /Parko/
### Mark)
### 9977 Carriage of material and fixing charges L.S. 34.71 2
### TOTAL
### Add 1 % Water charges on "W"
### TOTAL
### Add GST (multiplying factor 0.1405) on "X"
### TOTAL
### Add 15 % Contractor's profit and overheads on "Y"
### Total
###
###
###
###
###
###
### 1338
###
###
### Add Cess @ 1% on "Z" 60.53
### Cost of each 6113.6
### Say
###
### 17.23 Providing and fixing white vitreous
### china flat back or wall corner type lipped
### Details of cost for one no.
### MATERIAL
### 1913 Vitreous china lipped front urinal each 1 460
### 9977 Carriage of materials L.S. 9.49 2
### LABOUR
### 19 Fitter (grade 1) day 0.38 505.17
### 17 Beldar day 0.38 350.00
### TOTAL
### Add 1 % Water charges on "W"
### TOTAL
### Add GST (multiplying factor 0.1405) on "X"
### TOTAL
### Add 15 % Contractor's profit and overheads on "Y"
### Total
### Add Cess @ 1% on "Z"
### Cost of each
### Say
###
### 17.24 Providing and fixing white vitreous
### china squatting plate urinal with integral
### rim longitudinal flush pipe.
### Details of cost for one no.
###
### MATERIAL
### 1915 Vitreous china squatting plate urinal each 1 1053
### 9999 Cement, sand and grit etc. L.S. 10.79 2
### 9977 Carriage of materials L.S. 13.39 2
### LABOUR
### 19 Fitter (grade 1) day 0.5 505.17
### 23 Mason (brick layer) 1st class day 0.5 505.17
### 17 Beldar day 1 350.00
### TOTAL
### Add 1 % Water charges on "W"
### TOTAL
### Add GST (multiplying factor 0.1405) on "X"
###
###
###
###
###
### 1339
###
###
### TOTAL
### Add 15 % Contractor's profit and overheads on "Y" 327.98
### Total
### Add Cess @ 1% on "Z" 25.15
### Cost of each 2539.66
### Say
###
### 17.25 Providing and fixing white vitreous
### china wash basin including making all
### 17.25.1 Flat back wash basin of size
### 630x450 mm
### Details of cost for one no.
### MATERIAL
### 1947 Vitreous china flat back wash basin 630x450 mm each 1 725
### 9999 Fixing charges L.S. 53.82 2
### 9977 Carriage of materials L.S. 9.49 2
### TOTAL
### Add 1 % Water charges on "W"
### TOTAL
### Add GST (multiplying factor 0.1405) on "X"
### TOTAL
### Add 15 % Contractor's profit and overheads on "Y"
### Total
### Add Cess @ 1% on "Z"
### Cost of each
### Say
###
### 17.25.2 Flat back wash basin of size
### 550x400 mm
### Details of cost for one no.
### MATERIAL
### 3229 Vitreous china flat back wash basin 550x400 mm each 1 545
### 9999 Fixing charges L.S. 53.82 2
### 9977 Carriage of materials L.S. 9.49 2
### TOTAL
### Add 1 % Water charges on "W"
### TOTAL
### Add GST (multiplying factor 0.1405) on "X"
### TOTAL
### Add 15 % Contractor's profit and overheads on "Y"
###
###
###
###
### 1340
###
###
### Total
### Add Cess @ 1% on "Z" 8.9
### Cost of each 898.59
### Say
###
### 17.25.3 Angle back wash basin of size
### 600x480 mm
### Details of cost for one no.
### MATERIAL
### 1949 Vitreous china angle back wash basin 600x480 mm each 1 725
### 9999 Fixing charges L.S. 53.82 2
### 9977 Carriage of materials L.S. 9.49 2
### TOTAL
### Add 1 % Water charges on "W"
### TOTAL
### Add GST (multiplying factor 0.1405) on "X"
### TOTAL
### Add 15 % Contractor's profit and overheads on "Y"
### Total
### Add Cess @ 1% on "Z"
### Cost of each
### Say
###
### 17.25.4 Angle back wash basin of size
### 400x400 mm
### Details of cost for one no.
### MATERIAL
### 1950 Vitreous china angle back wash basin 400x400 mm each 1 425
### 9999 Fixing charges L.S. 53.82 2
### 9977 Carriage of materials L.S. 9.49 2
### TOTAL
### Add 1 % Water charges on "W"
### TOTAL
### Add GST (multiplying factor 0.1405) on "X"
### TOTAL
### Add 15 % Contractor's profit and overheads on "Y"
### Total
### Add Cess @ 1% on "Z"
### Cost of each
### Say
###
### 17.25.5 Flat back wash basin of size
### 450x300 mm
### Details of cost for one no.
###
###
###
###
###
### 1341
###
###
### MATERIAL
### 7004 Vitreous china flat back wash basin 450x300 mm each 1 310
### 9999 Fixing charges L.S. 53.82 2
### 9977 Carriage of materials L.S. 9.49 2
### TOTAL
### Add 1 % Water charges on "W"
### TOTAL
### Add GST (multiplying factor 0.1405) on "X"
### TOTAL
### Add 15 % Contractor's profit and overheads on "Y"
### Total
### Add Cess @ 1% on "Z"
### Cost of each
### Say
### 17.25.6 Surgeon type wash basin of size 660x460
### mm of cost for one no.
Details
### MATERIAL
### 3213 Vitreous china Surgeon type wash basin of size each 1 1000
### 9999 660x460 mm
### Fixing charges L.S. 53.82 2
### 9977 Carriage of materials L.S. 9.49 2
### TOTAL
### Add 1 % Water charges on "W"
### TOTAL
### Add GST (multiplying factor 0.1405) on "X"
### TOTAL
### Add 15 % Contractor's profit and overheads on "Y"
### Total
### Add Cess @ 1% on "Z"
### Cost of each
### Say
###
### 17.26 Providing and fixing kitchen sink
### including making all connections excluding
###
###
###
### 1342
###
###
###
### 17.26.1 White glazed fire clay sink of size
### 600x450x250 mm
### Details of cost for one no.
### MATERIAL
### 1863 Fire clay kitchen sink: 600x450x250 mm each 1 1283
### 9999 Fixing charges L.S. 40.43 2
### 9977 Carriage of materials L.S. 10.79 2
### TOTAL
### Add 1 % Water charges on "W"
### TOTAL
### Add GST (multiplying factor 0.1405) on "X"
### TOTAL
### Add 15 % Contractor's profit and overheads on "Y"
### Total
### Add Cess @ 1% on "Z"
### Cost of each
### Say
###
### 17.27 Providing and fixing white vitreous
### china laboratory sink including making all
### connections excluding cost of fittings :
### 17.27.1 Size 450x300x150 mm
### Details of cost for one no.
### MATERIAL
### 1871 White vitreous china laboratry sink 450x300x150 mm each 1 1500
### 9999 Fixing charges L.S. 40.43 2
### 9977 Carriage of materials L.S. 10.79 2
### TOTAL
### Add 1 % Water charges on "W"
### TOTAL
### Add GST (multiplying factor 0.1405) on "X"
### TOTAL
### Add 15 % Contractor's profit and overheads on "Y"
### Total
### Add Cess @ 1% on "Z"
### Cost of each
### Say
###
### 17.27.2 Size 600x450x200 mm
###
### Details of cost for one no.
###
### MATERIAL
###
###
###
###
###
### 1343
###
###
### 1872 White vitreous china laboratry sink 600x450x200 mm each 1 2500
### 9999 Fixing charges L.S. 40.43 2
### 9977 Carriage of materials L.S. 10.79 2
### TOTAL
### Add 1 % Water charges on "W"
### TOTAL
### Add GST (multiplying factor 0.1405) on "X"
### TOTAL
### Add 15 % Contractor's profit and overheads on "Y"
### Total
### Add Cess @ 1% on "Z"
### Cost of each
### Say
###
### 17.28 Providing and fixing P.V.C. waste
### pipe for sink or wash basin including P.V.C.
### waste fittings complete.
### 17.28.1 Semi rigid pipe
### 17.28.1.1 32 mm dia
### Details of cost for one no.
### MATERIAL
### 7117 Semi Rigid PVC waste pipe for sink and wash basin each 1 25
### 32 mm dia with length not less
### than 700 mm i/c PVC waste fittings
### 9988 Carriage of materials and fixing charges L.S. 20.28 2
### TOTAL
### Add 1 % Water charges on "W"
### TOTAL
### Add GST (multiplying factor 0.1405) on "X"
### TOTAL
### Add 15 % Contractor's profit and overheads on "Y"
### Total
### Add Cess @ 1% on "Z"
### Cost of each
### Say
### 17.28.1.2 40 mm dia
### Details of cost for one no.
### MATERIAL
### 7118 Semi Rigid PVC waste pipe for sink and wash basin each 1 33
### 40 mm dia with length not less
###
###
###
###
### 1344
###
###
### than 700 mm i/c PVC waste fittings
### 9988 Carriage of materials and fixing charges L.S. 20.28 2
### TOTAL
### Add 1 % Water charges on "W"
### TOTAL
### Add GST (multiplying factor 0.1405) on "X"
### TOTAL
### Add 15 % Contractor's profit and overheads on "Y"
### Total
### Add Cess @ 1% on "Z"
### Cost of each
### Say
### 17.28.2 Flexible pipe
### 17.28.2.1 32 mm dia
### Details of cost for one no.
### MATERIAL
### 7119 Flexible (coil shaped) PVC waste pipe for sink and each 1 35
### wash basin 32 mm dia with length
### not less than 700 mm i/c PVC waste fittings
### 9988 Carriage of materials and fixing charges L.S. 20.28 2
### TOTAL
### Add 1 % Water charges on "W"
### TOTAL
### Add GST (multiplying factor 0.1405) on "X"
### TOTAL
### Add 15 % Contractor's profit and overheads on "Y"
### Total
### Add Cess @ 1% on "Z"
### Cost of each
### Say
### 17.28.2.2 40 mm dia
### Details of cost for one no.
### MATERIAL
### 7120 Flexible (coil shaped) PVC waste pipe for sink and each 1 35
### wash basin 40 mm dia with length
### not less than 700 mm i/c PVC waste fittings
### 9988 Carriage of materials and fixing charges L.S. 20.28 2
### TOTAL
### Add 1 % Water charges on "W"
### TOTAL
###
###
###
###
###
###
### 1345
###
###
### Add GST (multiplying factor 0.1405) on "X" 10.72
### TOTAL
### Add 15 % Contractor's profit and overheads on "Y" 13.06
### Total
### Add Cess @ 1% on "Z" 1
### Cost of each 101.09
### Say
###
### 17.29 Providing and fixing 100 mm sand
### cast Iron grating for gully trap.
### Details of cost for one no.
### MATERIAL
### 1369 S.C.I. gully or nahani grating 100 mm dia each 1 25
### 9988 Carriage of materials and fixing charges L.S. 4.16 2
### TOTAL
### Add 1 % Water charges on "W"
### TOTAL
### Add GST (multiplying factor 0.1405) on "X"
### TOTAL
### Add 15 % Contractor's profit and overheads on "Y"
### Total
### Add Cess @ 1% on "Z"
### Cost of each
### Say
###
### 17.30 Providing and fixing in position 25
### mm diameter mosquito proof coupling of
### approved municipal design.
### Details of cost for one no.
###
### MATERIAL
### 1350 Mosquito proof coupling of approved design each 1 30
### 9988 Carriage of materials and fixing charges L.S. 1.82 2
### TOTAL
### Add 1 % Water charges on "W"
### TOTAL
### Add GST (multiplying factor 0.1405) on "X"
### TOTAL
### Add 15 % Contractor's profit and overheads on "Y"
###
###
###
###
###
###
### 1346
###
###
### Total
### Add Cess @ 1% on "Z" 0.45
### Cost of each 45.01
### Say
###
### 17.31 Providing and fixing 600x450 mm
### beveledcleats
wooden edge mirror of superior
with C.P. glass and
brass screws (of
### washers
Details of cost for one no. complete.
### MATERIAL
### 1392 Mirror of superior make glass 60x45 cm each 1 400
### 7116 Hard board 6 mm thick sqm 0.27 115
### 600x450 mm
### Wooden cleats
### 8.23 Rate as per item no 9.32 of SH : Wood and each 4 25.4
### PVC work
### 588 Chromium plated Brass screws 25 mm 100 Nos 0.04 180
### 9977 Carriage of materials L.S. 4.16 2
### 9999 Sundries L.S. 1.43 2
### LABOUR
### 15 Carpenter 2nd class day 0.33 403.67
### 17 Beldar day 0.33 350.00
### TOTAL
### Add 1 % Water charges on "W-A" 678.89
### TOTAL
### Add GST (multiplying factor 0.1405) on "X-A" 685.68
### TOTAL
### Add 15 % Contractor's profit and overheads on "Y-A" 782.02
### Total
### Add Cess @ 1% on "Z-A" 899.32
### Cost of each
### Say
###
### 17.32 Providing and fixing mirror of
### superior
shadeglass
with(of approved
6 mm quality)
thick hard boardand of
### backing
17.32.1 Circular shape: 450 mm dia
###
### Details of cost for one no.
###
### MATERIAL
###
###
###
###
### 1347
###
###
### 7112 Circular shape 450 mm dia Mirror with each 1 430
### Plastic moulded frame
### Hard board 0.45x0.45 = 0.2025 sqm
### Add wastage @ 10% = 0.0203 sqm
### = 0.2228 sqm say 0.22sqm
### 7116 Hard board 6 mm thick sqm 0.22 115
### 7048 Rawl plug 50 mm (designation 10 no.) each 2 25
### 588 Chromium plated Brass screws 25 mm 100 Nos 0.02 180
### 9999 Sundries L.S. 1.43 2
### 9977 Carriage of materials L.S. 4.16 2
### LABOUR
### 15 Carpenter 2nd class day 0.33 403.67
### 17 Beldar day 0.33 350.00
### TOTAL
### Add 1 % Water charges on "W"
### TOTAL
### Add GST (multiplying factor 0.1405) on "X"
### TOTAL
### Add 15 % Contractor's profit and overheads on "Y"
### Total
### Add Cess @ 1% on "Z"
### Cost of each
### Say
### 17.32.2 Rectangular shape 453x357 mm
### Details of cost for one no.
### MATERIAL
### 7113 Rectangular shape 453x357 mm Mirror with each 1 290
### Plastic moulded frame
### Hard board 0.453x0.357 = 0.1617 sqm
### Add wastage @ 10% = 0.0162 sqm
### = 0.1779 sqm say 0.18 sqm
### 7116 Hard board 6 mm thick sqm 0.18 115
### 7048 Rawl plug 50 mm (designation 10 no.) each 4 25
### 588 Chromium plated Brass screws 25 mm 100 Nos 0.04 180
### 9999 Sundries L.S. 1.43 2
### 9977 Carriage of materials L.S. 4.16 2
### LABOUR
### 15 Carpenter 2nd class day 0.33 403.67
### 17 Beldar day 0.33 350.00
### TOTAL
### Add 1 % Water charges on "W"
### TOTAL
### Add GST (multiplying factor 0.1405) on "X"
### TOTAL
### Add 15 % Contractor's profit and overheads on "Y"
### Total
###
###
###
###
###
### 1348
###
###
### Add Cess @ 1% on "Z" 8.72
### Cost of each 881.08
### Say
###
### 17.32.3 Oval shape 450x350 mm (outer
### dimensions)
### Details of cost for one no.
### MATERIAL
### 7114 Ovel shape 450x350 mm (outer dimensions) each 1 340
### Mirror with Plastic moulded frame
### Hard board 0.45x0.35=0.1575 sqm
### Add wastage @ 10% = 0.0158 sqm
### = 0.1733 sqm say 0.17 sqm
### 7116 Hard board 6 mm thick sqm 0.17 115
### 7048 Rawl plug 50 mm (designation 10 no.) each 4 25
### 588 Chromium plated Brass screws 25 mm 100 Nos 0.04 180
### 9999 Sundries L.S. 1.43 2
### 9977 Carriage of materials L.S. 4.16 2
### LABOUR
### 15 Carpenter 2nd class day 0.33 403.67
### 17 Beldar day 0.33 350.00
### TOTAL
### Add 1 % Water charges on "W"
### TOTAL
### Add GST (multiplying factor 0.1405) on "X"
### TOTAL
### Add 15 % Contractor's profit and overheads on "Y"
### Total
### Add Cess @ 1% on "Z"
### Cost of each
### Say
###
### 17.32.4 Rectangular shape 1500x450 mm
###
### Details of cost for one no.
### MATERIAL
### 7115 Rectangular shape 1500x450 mm Mirror each 1 670
### with Plastic moulded frame Hard board 1.50x0.45 =
### 0.675 sqm
### Add wastage @ 10% = 0.0675 sqm
### = 0.7425 sqm say 0.74sqm
### 7116 Hard board 6 mm thick sqm 0.74 115
### 7048 Rawl plug 50 mm (designation 10 no.) each 6 25
### 588 Chromium plated Brass screws 25 mm 100 Nos 0.06 180
### 9999 Sundries L.S. 1.43 2
###
###
###
###
###
###
### 1349
###
###
### 9977 Carriage of materials L.S. 4.16 2
### LABOUR
### 15 Carpenter 2nd class day 0.33 403.67
### 17 Beldar day 0.33 350.00
### TOTAL
### Add 1 % Water charges on "W"
### TOTAL
### Add GST (multiplying factor 0.1405) on "X"
### TOTAL
### Add 15 % Contractor's profit and overheads on "Y"
### Total
### Add Cess @ 1% on "Z"
### Cost of each
### Say
###
### 17.33 Providing and fixing 600x120x5 mm
### glass shelf with edges round off, supported
### guard rail complete fixed with 40 mm long
### screws, rawl plugs etc., complete.
### Details of cost for one no.
###
### MATERIAL
### 3228 600x120 mm glass shelf with anodised aluminium each 1 250
### angle frame, C.P. brass
### brackets and guard rail of standard size
### 7048 Rawl plug 50 mm (designation 10 no.) each 2 25
### 586 Chromium plated Brass screws 40 mm 100 Nos 0.04 290
### 9977 Carriage of materials L.S. 4.16 2
### LABOUR
### 15 Carpenter 2nd class day 0.25 403.67
### 17 Beldar day 0.25 350.00
### TOTAL
### Add 1 % Water charges on "W"
### TOTAL
### Add GST (multiplying factor 0.1405) on "X"
### TOTAL
### Add 15 % Contractor's profit and overheads on "Y"
### Total
### Add Cess @ 1% on "Z"
### Cost of each
### Say
###
### 17.34 Providing and fixing toilet paper
### holder :
###
###
###
###
###
### 1350
###
###
###
### 17.34.1 C.P. brass
###
### Details of cost for one no.
### MATERIAL
### 1889 C.P.brass toilet paper holder of standard size each 1 225
### Wooden cleats
### 8.23 Rate as per item no 9.32 of SH : Wood and each 2 25.4
### PVC work
### 588 Chromium plated Brass screws 25 mm 100 Nos 0.02 180
### 9977 Carriage of materials L.S. 4.29 2
### LABOUR
### 15 Carpenter 2nd class day 0.12 403.67
### 17 Beldar day 0.12 350.00
### TOTAL
### Add 1 % Water charges on "W-A" 320.62
### TOTAL
### Add GST (multiplying factor 0.1405) on "X-A" 323.83
### TOTAL
### Add 15 % Contractor's profit and overheads on "Y-A" 369.32
### Total
### Add Cess @ 1% on "Z-A" 424.72
### Cost of each
### Say
###
### 17.34.2 Vitreous china
###
### Details of cost of one no.
### MATERIAL
### 3749 Vitreous china toilet paper holder of each 1 100
### standard size Wooden cleats
### 8.23 Rate as per item no 9.32 of SH : Wood and PVC each 2 25.4
### work
### 588 Chromium plated Brass screws 25 mm 100 Nos 0.06 180
### 9977 Carriage of materials L.S. 4.29 2
### LABOUR
### 15 Carpenter 2nd class day 0.12 403.67
### 17 Beldar day 0.12 350.00
###
###
###
###
###
###
### 1351
###
###
### TOTAL
### Add 1 % Water charges on "W-A" 202.82 2.03
### TOTAL
### Add (multiplying factor 0.1405) on "X-A" 204.85 28.78
### TOTAL
### Add 15 % Contractor's profit and overheads on "Y-A" 233.63 35.04
### Total
### Add Cess @ 1% on "Z-A" 268.67 2.69
### Cost of each 322.16
### Say
###
### 17.35 Providing and fixing soil, waste and
### vent pipes :
### 17.35.1 100 mm dia
###
### 17.35.1.1 Sand cast iron S&S pipe as per IS: 1729
### Details of cost for 17.37 m
### (1.8mx10)-(9x0.07m) = 17.37 m
### MATERIAL
### 1617 S.C.I. soil, waste and vent single socketed pipe 1.80 each 10.5 1135
### metres long: 100mm dia
### 9999 Scaffolding L.S. 80.73 2
### 9977 Carriage of materials L.S. 53.82 2
### LABOUR
### 19 Fitter (grade 1) day 0.42 505.17
### 10 Bandhani day 0.21 350.00
### 17 Beldar day 0.83 350.00
### TOTAL
### Add 1 % Water charges on "W"
### TOTAL
### Add GST (multiplying factor 0.1405) on "X"
### TOTAL
### Add 15 % Contractor's profit and overheads on "Y"
### Total
### Add Cess @ 1% on "Z"
### Cost for 17.37 m pan
### Cost per metre
### Say
### 17.35.1.2 Centrifugally cast (spun) iron socket &
### spigotof(S&S)
Details pipe
cost for asmper IS: 3989
16.87
### (1.75mx10)-(9x0.07m) = 16.87 m
### MATERIAL
### 3620 C.C.I.(spun) socketed soil, waste and vent pipe 1.80 each 10.5 1200
### metres long:100mm dia
###
###
###
###
### 1352
###
###
### 9999 Scaffolding L.S. 80.73 2
### 9977 Carriage of materials L.S. 53.82 2
### LABOUR
### 19 Fitter (grade 1) day 0.42 505.17
### 10 Bandhani day 0.21 350.00
### 17 Beldar day 0.83 350.00
### TOTAL
### Add 1 % Water charges on "W"
### TOTAL
### Add GST (multiplying factor 0.1405) on "X"
### TOTAL
### Add 15 % Contractor's profit and overheads on "Y"
### Total
### Add Cess @ 1% on "Z"
### Cost for 16.87 m pan
### Cost per metre
### Say
###
### 17.35.1.3 Hubless centrifugally cast (spun) iron pipes
### epoxy coated inside & outside IS:15905
### Detail of cost for 18.00 m (6 x 3.00 m)
###
### MATERIAL
### 7621 Hubless centrifugally cast (spun) iron pipes as per IS metre 18.54 700
### 15905 - 100 mm dia (3000 mm
### length pipe) i/c (3% wastage)
### 9999 Scaffolding L.S. 80.73 2
### 9977 Carriage of materials L.S. 53.82 2
### LABOUR
### 19 Fitter (grade 1) day 0.42 505.17
### 10 Bandhani day 0.21 350.00
### 17 Beldar day 0.83 350.00
### TOTAL
### Add 1 % Water charges on "W"
### TOTAL
### Add GST (multiplying factor 0.1405) on "X"
### TOTAL
### Add 15 % Contractor's profit and overheads on "Y"
###
###
###
###
###
### 1353
###
###
### Total
### Add Cess @ 1% on "Z"
### Cost of 18.00 metre
### Cost of 1 metre
### Say
### 17.35.2 75 mm diameter :
### 17.35.2.1 Sand cast iron S&S pipe as per IS: 1729
### Details of cost for 17.42 m
### (1.8mx10)-(9x0.065m) = 17.415 m say
### 17.42 m
### MATERIAL
### 1616 S.C.I. soil, waste and vent single socketed pipe 1.80 each 10.5 1050
### metres long:75mm dia
### 9999 Scaffolding L.S. 80.73 2
### 9977 Carriage of materials L.S. 40.38 2
### LABOUR
### 19 Fitter (grade 1) day 0.35 505.17
### 10 Bandhani day 0.17 350.00
### 17 Beldar day 0.7 350.00
### TOTAL
### Add 1 % Water charges on "W"
### TOTAL
### Add GST (multiplying factor 0.1405) on "X"
### TOTAL
### Add 15 % Contractor's profit and overheads on "Y"
### Total
### Add Cess @ 1% on "Z"
### Cost for 17.42 m pan
### Cost per metre
### Say
### 17.35.2.2 Centrifugally cast (spun) iron socketed pipe
### as perofIS:
Details 3989
cost for 16.92 m
###
###
###
###
###
###
### 1354
###
###
### (1.75mx10)-(9x0.065m) = 16.915 m say 16.92 m
### MATERIAL
### 3621 C.C.I.(spun) socketed soil, waste and vent pipe 1.80 each 10.5 1100
### metres long:75mm dia including 5% allowance for
### wastage
### 9999 Scaffolding L.S. 80.73 2
### 9977 Carriage of materials L.S. 40.38 2
### LABOUR
### 19 Fitter (grade 1) day 0.35 505.17
### 10 Bandhani day 0.17 350.00
### 17 Beldar day 0.7 350.00
### TOTAL
### Add 1 % Water charges on "W"
### TOTAL
### Add GST (multiplying factor 0.1405) on "X"
### TOTAL
### Add 15 % Contractor's profit and overheads on "Y"
### Total
### Add Cess @ 1% on "Z"
### Cost for 16.92 m pan
### Cost per metre
### Say
### 17.35.2.3 Hubless centrifugally cast (spun) iron pipes
epoxy coated inside & outside
### IS:15905
### Detail of cost for 18.00 m (6 x 3.00 m)
### MATERIAL
### 7622 Hubless centrifugally cast (spun) iron pipes as per IS metre 18.54 570
### 15905 - 75 mm dia (3000 mm length pipe) i/c (3%
### wastage)
### 9999 Scaffolding L.S. 80.73 2
### 9977 Carriage of materials L.S. 40.38 2
### LABOUR
### 19 Fitter (grade 1) day 0.35 505.17
### 10 Bandhani day 0.17 350.00
### 17 Beldar day 0.7 350.00
### TOTAL
### Add 1 % Water charges on "W"
### TOTAL
### Add GST (multiplying factor 0.1405) on "X"
###
###
###
###
###
###
### 1355
###
###
### TOTAL
### Add 15 % Contractor's profit and overheads on "Y" 1944.83
### Total
### Add Cess @ 1% on "Z" 149.1
### Cost of 18.00 metre 15059.48
### Cost of 1 metre 836.64
### Say
###
### 17.36 Providing and filling the joints with
### spun yarn, cement slurry and cement
### mortar 1:2 ( 1 cement : 2 fine sand) in S.C.I./
### 17.36.1C.I.75
Pipes : pipe
mm dia
###
### Details of cost for 4 joints
###
### MATERIAL
###
### 9999 Cement mortar, spun yarn etc. L.S. 6.89 2
### LABOUR
### 19 Fitter (grade 1) day 0.28 505.17
### 17 Beldar day 0.28 350.00
### TOTAL
### Add 1 % Water charges on "W"
### TOTAL
### Add GST (multiplying factor 0.1405) on "X"
### TOTAL
### Add 15 % Contractor's profit and overheads on "Y"
### Total
### Add Cess @ 1% on "Z"
### Cost of 4 joints
### Cost of 1 joint
### Say
###
### 17.36.2 100 mm dia pipe
###
### Details of cost for 4 joints
### MATERIAL
### 9999 Cement mortar, spun yarn etc. L.S. 8.06 2
### LABOUR
### 19 Fitter (grade 1) day 0.33 505.17
### 17 Beldar day 0.33 350.00
### TOTAL
### Add 1 % Water charges on "W"
###
###
###
###
###
### 1356
###
###
### TOTAL
### Add GST (multiplying factor 0.1405) on "X" 39.6
### TOTAL
### Add 15 % Contractor's profit and overheads on "Y" 48.22
### Total
### Add Cess @ 1% on "Z" 3.7
### Cost of 4 joints 373.38
### Cost of 1 joint 93.35
### Say
###
### 17.37 Providing and fixing M.S. holder-bat
### 17.37.1 clamps
good the of approved
walls etc. : design to Sand Cast
### For 100 mm dia pipe
### Details of cost for 5 nos.
### MATERIAL
### 1331 M.S.Holder bat clamp of approved design for 100 mm each 5 30
### 9977 S.C.I. pipe
### Carriage of bat clamps L.S. 2.47 2
### LABOUR
### 19 Fitter (grade 1) day 0.125 505.17
### 24 Mason (brick layer) 2nd class day 0.75 403.67
### 17 Beldar day 0.5 350.00
### 9999 Sundries L.S. 7.15 2
### 295 Stone Aggregate (Single size) : 20 mm nominal size cum 0.0033 790
### 297 Stone Aggregate (Single size) : 10 mm nominal size cum 0.0011 810
### 2202 Carriage of Stone aggregate below 40 mm nominal cum 0.0044 584.88
### 982 size
### Coarse sand cum 0.0022 1350
### 2203 Carriage of Coarse sand cum 0.0022 584.88
### 367 Portland Cement (OPC-43 grade) tonne 0.0016 4375
### 2209 Carriage of Cement tonne 0.0016 94.34
### 17 Beldar day 0.0045 350.00
### 18 Coolie day 0.0032 350.00
### 11 Bhisti day 0.0014 350.00
### 23 Mason (brick layer) 1st class day 0.0003 505.17
### 24 Mason (brick layer) 2nd class day 0.0003 403.67
### 28 Mate day 0.0002 350.00
###
###
###
###
### 1357
###
###
### 9999 Hire charges of machine etc. L.S. 0.26 2
### 9999 Sundries L.S. 0.13 2
### 9999 Sundries L.S. 0.13 2
### TOTAL
### Add 1 % Water charges on "W"
### TOTAL
### Add GST (multiplying factor 0.1405) on "X"
### TOTAL
### Add 15 % Contractor's profit and overheads on "Y"
### Total
### Add Cess @ 1% on "Z"
### Cost of 5.00 bat clamps
### Cost of each
### Say
###
### 17.37.2 For 75 mm dia pipe
###
### Details of cost for 5 nos.
### MATERIAL
### 1332 M.S.Holder bat clamp of approved design for75 mm each 5 27
### S.C.I. pipe
### 9977 Carriage of bat clamps L.S. 2.47 2
### LABOUR
### 19 Fitter (grade 1) day 0.125 505.17
### 24 Mason (brick layer) 2nd class day 0.75 403.67
### 17 Beldar day 0.5 350.00
### 9999 Sundries L.S. 7.15 2
### C.C. Black 5x0.1x0.1x0.1 = 0.005 cum
### 295 Stone Aggregate (Single size) : 20 mm nominal size cum 0.0033 790
### 297 Stone Aggregate (Single size) : 10 mm nominal size cum 0.0011 810
### 2202 Carriage of Stone aggregate below 40 mm nominal cum 0.0044 584.88
### 982 size 800
### Coarse sand cum 0.0022 1350
### 2203 Carriage of Coarse sand cum 0.0022 584.88
### 367 Portland Cement (OPC-43 grade) tonne 0.0016 4375
### 2209 Carriage of Cement tonne 0.0016 94.34
### 17 Beldar day 0.0045 350.00
### 18 Coolie day 0.0032 350.00
### 11 Bhisti day 0.0014 350.00
### 23 Mason (brick layer) 1st class day 0.0003 505.17
### 24 Mason (brick layer) 2nd class day 0.0003 403.67
###
###
###
###
###
### 1358
###
###
### 28 Mate day 0.0002 350.00
### 9999 Hire charges of machine etc. L.S. 0.26 2
### 9999 Sundries L.S. 0.13 2
### 9999 Sundries L.S. 0.13 2
### TOTAL
### Add 1 % Water charges on "W"
### TOTAL
### Add GST (multiplying factor 0.1405) on "X"
### TOTAL
### Add 15 % Contractor's profit and overheads on "Y"
### Total
### Add Cess @ 1% on "Z"
### Cost of 5.00 bat clamps
### Cost of each
### Say
###
### 17.38 Providing and fixing bend of
### required degree with access door, insertion
### rubber washer 3 mm thick, bolts and nuts
### complete.
17.38.1 100 mm dia
### 17.38.1.1 Sand cast iron S&S as per IS - 1729
### Details of cost for one no.
### MATERIAL
### 1625 S.C.I. bend with access door 100mm dia each 1 300
### 1374 Rubber insertions for 100 mm dia pipe joints each 1 18
### 9988 Carriage of materials and fixing charges L.S. 13.52 2
### TOTAL
### Add 1 % Water charges on "W"
### TOTAL
### Add GST (multiplying factor 0.1405) on "X"
### TOTAL
### Add 15 % Contractor's profit and overheads on "Y"
### Total
### Add Cess @ 1% on "Z"
### Cost of each
### Say
### 17.38.1.2 Sand cast iron S&S as per IS - 3989
### Details of cost for one no.
### MATERIAL
### 3624 S.C.I. S&S bends with access door 100mm dia each 1 300
### 1374 Rubber insertions for 100 mm dia pipe joints each 1 18
###
###
###
###
###
###
### 1359
###
###
### 9988 Carriage of materials and fixing charges L.S. 13.52 2
### TOTAL
### Add 1 % Water charges on "W"
### TOTAL
### Add GST (multiplying factor 0.1405) on "X"
### TOTAL
### Add 15 % Contractor's profit and overheads on "Y"
### Total
### Add Cess @ 1% on "Z"
### Cost of each
### Say
###
### 17.38.1.3 Hubless centrifugally cast (spun) iron
### epoxy coated inside
Detail & outside
of cost as per
for one no.
###
### MATERIAL
### 7639 Hubless centrifugally cast (spun) iron bend with each 1 365
acces
### 1374 Rubber insertions for 100 mm dia pipe joints each 1 18
### 9977 Carriage of materials and fixing charges L.S. 13.52 2
### TOTAL
### Add 1 % Water charges on "W"
### TOTAL
### Add GST (multiplying factor 0.1405) on "X"
### TOTAL
### Add 15 % Contractor's profit and overheads on "Y"
### Total
### Add Cess @ 1% on "Z"
### Cost of each
### Say
###
### 17.38.2 75 mm dia
###
### 17.38.2.1 Sand cast iron S&S as per IS - 1729
### Details of cost for one no.
### MATERIAL
### 1624 S.C.I. bend with access door 75mm dia each 1 240
### 1373 Rubber insertions for 80 mm dia pipe joints each 1 16
### 9988 Carriage of materials and fixing charges L.S. 10.79 2
### TOTAL
### Add 1 % Water charges on "W"
### TOTAL
### Add GST (multiplying factor 0.1405) on "X"
###
###
###
###
###
### 1360
###
###
### TOTAL
### Add 15 % Contractor's profit and overheads on "Y"
### Total
### Add Cess @ 1% on "Z"
### Cost of each
### Say
### 17.38.2.2 Sand cast iron S&S as per IS- 3989
### Details of cost for one no.
### MATERIAL
### 3625 S.C.I. S&S bends with access door75mm dia each 1 250
### 1373 Rubber insertions for 80 mm dia pipe joints each 1 16
### 9988 Carriage of materials and fixing charges L.S. 10.79 2
### TOTAL
### Add 1 % Water charges on "W"
### TOTAL
### Add GST (multiplying factor 0.1405) on "X"
### TOTAL
### Add 15 % Contractor's profit and overheads on "Y"
### Total
### Add Cess @ 1% on "Z"
### Cost of each
### Say
###
### 17.38.2.3 Hubless centrifugally cast (spun) iron
### epoxy coated inside
Detail & outside
of cost as per
for one no.
###
### MATERIAL
### 7640 Hubless centrifugally cast (spun) iron bend with each 1 290
### access door - 75 mm dia as per IS 15905 including
### 1373 cost of bolts & nuts.
### Rubber insertions for 80 mm dia pipe joints 3mm each 1 16
thick
### 9977 Carriage of materials and fixing charges L.S. 10.79 2
### TOTAL
### Add 1 % Water charges on "W"
### TOTAL
### Add GST (multiplying factor 0.1405) on "X"
### TOTAL
###
###
###
###
###
### 1361
###
###
### Add 15 % Contractor's profit and overheads on "Y" 56.6
### Total
### Add Cess @ 1% on "Z" 4.34
### Cost of each 438.28
### Say
###
### 17.39 Providing and fixing plain bend of
### required degree.
### 17.39.1 100 mm dia
###
### 17.39.1.1 Sand cast iron S&S as per IS - 1729
### Details of cost for one no.
### MATERIAL
### 1621 S.C.I. plain bend 100 mm dia each 1 258
### 9988 Carriage of materials and fixing charges L.S. 13.52 2
### TOTAL
### Add 1 % Water charges on "W"
### TOTAL
### Add GST (multiplying factor 0.1405) on "X"
### TOTAL
### Add 15 % Contractor's profit and overheads on "Y"
### Total
### Add Cess @ 1% on "Z"
### Cost of each
### Say
### 17.39.1.2 Sand cast iron S&S as per IS : 3989
### Details of cost for one no.
### MATERIAL
### 3628 S.C.I. S&S bend100mm dia each 1 265
### 9988 Carriage of materials and fixing charges L.S. 13.52 2
### TOTAL
### Add 1 % Water charges on "W"
### TOTAL
### Add GST (multiplying factor 0.1405) on "X"
### TOTAL
### Add 15 % Contractor's profit and overheads on "Y"
### Total
### Add Cess @ 1% on "Z"
### Cost of each
###
###
###
###
### 1362
###
###
### Say
### 17.39.1.3 Hubless centrifugally cast (spun) iron pipes
### IS:15905 epoxy
### Detail of cost for one no.
### MATERIAL
### 7623 Hubless centrifugally cast (spun) iron plain bend as each 1 230
### per IS 15905- 100 mm dia
### 9977 Carriage of materials and fixing charges L.S. 13.52 2
### TOTAL
### Add 1 % Water charges on "W"
### TOTAL
### Add GST (multiplying factor 0.1405) on "X"
### TOTAL
### Add 15 % Contractor's profit and overheads on "Y"
### Total
### Add Cess @ 1% on "Z"
### Cost of each
### Say
###
### 17.39.2 75 mm dia
###
### 17.39.2.1 Sand cast iron S&S as per IS -1729
### Details of cost for one no.
### MATERIAL
### 1620 S.C.I. plain bend 75 mm dia each 1 210
### 9988 Carriage of materials and fixing charges L.S. 10.79 2
### TOTAL
### Add 1 % Water charges on "W"
### TOTAL
### Add GST (multiplying factor 0.1405) on "X"
### TOTAL
### Add 15 % Contractor's profit and overheads on "Y"
### Total
### Add Cess @ 1% on "Z"
### Cost of each
### Say
### 17.39.2.2 Sand cast iron S&S as per IS - 3989
### Details of cost for one no.
###
###
###
###
### 1363
###
###
### MATERIAL
### 3629 S.C.I. S&S bend75mm dia each 1 195
### 9988 Carriage of materials and fixing charges L.S. 10.79 2
### TOTAL
### Add 1 % Water charges on "W"
### TOTAL
### Add GST (multiplying factor 0.1405) on "X"
### TOTAL
### Add 15 % Contractor's profit and overheads on "Y"
### Total
### Add Cess @ 1% on "Z"
### Cost of each
### Say
### 17.39.2.3 Hubless centrifugally cast (spun) iron pipes
### IS:15905 epoxy
### Detail of cost for one no.
### MATERIAL
### 7624 Hubless centrifugally cast (spun) iron plain bend as each 1 160
### per IS 15905 - 75 mm dia
### 9977 Carriage of materials and fixing charges L.S. 10.79 2
### TOTAL
### Add 1 % Water charges on "W"
### TOTAL
### Add GST (multiplying factor 0.1405) on "X"
### TOTAL
### Add 15 % Contractor's profit and overheads on "Y"
### Total
### Add Cess @ 1% on "Z"
### Cost of each
### Say
###
### 17.40 Providing and fixing heel rest
### sanitary bend
### 17.40.1 100 mm dia
###
### 17.40.1.1 Sand cast iron S&S as per IS - 1729
### Details of cost for one no.
### MATERIAL
### 1667 Sand cast iron heel rest bend 100mm dia each 1 347
### 9988 Carriage of materials and fixing charges L.S. 13.52 2
### TOTAL
###
###
###
###
###
### 1364
###
###
### Add 1 % Water charges on "W"
### TOTAL
### Add GST (multiplying factor 0.1405) on "X"
### TOTAL
### Add 15 % Contractor's profit and overheads on "Y"
### Total
### Add Cess @ 1% on "Z"
### Cost of each
### Say
### 17.40.1.2 Sand cast iron S&S as per IS - 3989
### Details of cost for one no.
### MATERIAL
### 3634 S.C.I. S&S heel rest sanitary bend 100mm dia each 1 296
### 9988 Carriage of materials and fixing charges L.S. 13.52 2
### TOTAL
### Add 1 % Water charges on "W"
### TOTAL
### Add GST (multiplying factor 0.1405) on "X"
### TOTAL
### Add 15 % Contractor's profit and overheads on "Y"
### Total
### Add Cess @ 1% on "Z"
### Cost of each
### Say
###
### 17.40.2 75 mm dia
###
### 17.40.2.1 Sand cast iron S&S as per IS - 1729
### Details of cost for one no.
### MATERIAL
### 1666 Sand cast iron heel rest bend75mm dia each 1 274
### 9988 Carriage of materials and fixing charges L.S. 10.79 2
### TOTAL
### Add 1 % Water charges on "W"
### TOTAL
### Add GST (multiplying factor 0.1405) on "X"
### TOTAL
### Add 15 % Contractor's profit and overheads on "Y"
### Total
### Add Cess @ 1% on "Z"
### Cost of each
###
###
###
###
###
### 1365
###
###
### Say
### 17.40.2.2 Sand cast iron S&S as per IS - 3989
### Details of cost for one no.
### MATERIAL
### 3635 S.C.I. S&S heel rest sanitary bend 75mm dia each 1 250
### 9988 Carriage of materials and fixing charges L.S. 10.79 2
### TOTAL
### Add 1 % Water charges on "W"
### TOTAL
### Add GST (multiplying factor 0.1405) on "X"
### TOTAL
### Add 15 % Contractor's profit and overheads on "Y"
### Total
### Add Cess @ 1% on "Z"
### Cost of each
### Say
###
### 17.41 Providing and fixing double equal
### junction of required degree with access
### door, insertion rubber washer 3 mm thick,
### bolts and nuts complete :
### 17.41.1 100x100x100x100 mm
###
### 17.41.1.1 Sand cast iron S&S as per IS - 1729
### Details of cost for one no.
### MATERIAL
### 1637 S.C.I. double equal junctions 100x100x 100x100 mm each 1 715
### dia with access door.
### 1374 Rubber insertions for 100 mm dia pipe joints each 1 18
### 9988 Carriage of materials and fixing charges L.S. 13.39 2
### TOTAL
### Add 1 % Water charges on "W"
### TOTAL
### Add GST (multiplying factor 0.1405) on "X"
### TOTAL
### Add 15 % Contractor's profit and overheads on "Y"
### Total
### Add Cess @ 1% on "Z"
### Cost of each
### Say
### 17.41.1.2 Sand cast iron S&S as per IS - 3989
###
###
###
###
###
### 1366
###
###
### Details of cost for one no.
### MATERIAL
### 3654 S.C.I. S&S double equal junctions with access door each 1 615
### 100x100x100x100 mm.
### 1374 Rubber insertions for 100 mm dia pipe joints each 1 18
### 9988 Carriage of materials and fixing charges L.S. 13.39 2
### TOTAL
### Add 1 % Water charges on "W"
### TOTAL
### Add GST (multiplying factor 0.1405) on "X"
### TOTAL
### Add 15 % Contractor's profit and overheads on "Y"
### Total
### Add Cess @ 1% on "Z"
### Cost of each
### Say
###
### 17.41.2 75x75x75x75 mm
###
### 17.41.2.1 Sand cast iron S&S as per IS - 1729
### Details of cost for one no.
### MATERIAL
### 1636 S.C.I. double equal junctions75x75x75x 75 mm dia each 1 500
### with access door.
### 1373 Rubber insertions for 80 mm dia pipe joints each 1 16
### 9988 Carriage of materials and fixing charges L.S. 10.79 2
### TOTAL
### Add 1 % Water charges on "W"
### TOTAL
### Add GST (multiplying factor 0.1405) on "X"
### TOTAL
### Add 15 % Contractor's profit and overheads on "Y"
### Total
### Add Cess @ 1% on "Z"
### Cost of each
### Say
### 17.41.2.2 Sand cast iron S&S as per IS - 3989
### Details of cost for one no.
### MATERIAL
### 3655 S.C.I. S&S double equal junctions with access door each 1 480
### 75x75x75x75 mm.
### 1373 Rubber insertions for 80 mm dia pipe joints each 1 16
### 9988 Carriage of materials and fixing charges L.S. 10.79 2
### TOTAL
###
###
###
###
### 1367
###
###
### Add 1 % Water charges on "W" 5.18
### TOTAL
### Add GST (multiplying factor 0.1405) on "X" 73.45
### TOTAL
### Add 15 % Contractor's profit and overheads on "Y" 89.43
### Total
### Add Cess @ 1% on "Z" 6.86
### Cost of each 692.49
### Say
###
### 17.42 Providing and fixing double equal
### plain junction of required degree.
### 17.42.1 100x100x100x100 mm
###
### 17.42.1.1 Sand cast iron S&S as per IS - 1729
### Details of cost for one no.
### MATERIAL
### 1634 S.C.I. plain double equal junctions 100x100x100x100 each 1 590
### mm dia
### 9988 Carriage of materials and fixing charges L.S. 13.52 2
### TOTAL
### Add 1 % Water charges on "W"
### TOTAL
### Add GST (multiplying factor 0.1405) on "X"
### TOTAL
### Add 15 % Contractor's profit and overheads on "Y"
### Total
### Add Cess @ 1% on "Z"
### Cost of each
### Say
### 17.42.1.2 Sand cast iron S&S as per IS - 3989
### Details of cost for one no.
### MATERIAL
### 3650 S.C.I. S&S double equal junctions 100x100x100x100 each 1 620
### mm
### 9988 Carriage of materials and fixing charges L.S. 13.52 2
### TOTAL
### Add 1 % Water charges on "W"
### TOTAL
### Add GST (multiplying factor 0.1405) on "X"
### TOTAL
### Add 15 % Contractor's profit and overheads on "Y"
### Total
###
###
###
###
### 1368
###
###
### Add Cess @ 1% on "Z"
### Cost of each
### Say
### 17.42.1.3 Hubless centrifugally cast (spun) iron pipes
### IS:15905 epoxy
### Detail of cost for one no.
### MATERIAL
### 7625 Hubless centrifugally cast (spun) iron double equal each 1 510
### plain junction as per IS 15905 - 100x100x100x100
### mm dia
### 9977 Carriage of materials and fixing charges L.S. 13.52 2
### TOTAL
### Add 1 % Water charges on "W"
### TOTAL
### Add GST (multiplying factor 0.1405) on "X"
### TOTAL
### Add 15 % Contractor's profit and overheads on "Y"
### Total
### Add Cess @ 1% on "Z"
### Cost of each
### Say
###
### 17.42.2 75x75x75x75 mm
###
### 17.42.2.1 Sand cast iron S&S as per IS - 1729
### Details of cost for one no.
### MATERIAL
### 1633 S.C.I. plain double equal junctions 75x75x75x75 mm each 1 382
### dia
### 9988 Carriage of materials and fixing charges L.S. 10.79 2
### TOTAL
### Add 1 % Water charges on "W"
### TOTAL
### Add GST (multiplying factor 0.1405) on "X"
### TOTAL
### Add 15 % Contractor's profit and overheads on "Y"
### Total
### Add Cess @ 1% on "Z"
### Cost of each
### Say
###
###
###
###
### 1369
###
###
###
### 17.42.2.2 Sand cast iron S&S as per IS - 3989
### Details of cost for one no.
### MATERIAL
### 3651 S.C.I. S&S double equal junctions 75x75x75x75 mm each 1 462
### 9988 Carriage of materials and fixing charges L.S. 10.79 2
### TOTAL
### Add 1 % Water charges on "W"
### TOTAL
### Add GST (multiplying factor 0.1405) on "X"
### TOTAL
### Add 15 % Contractor's profit and overheads on "Y"
### Total
### Add Cess @ 1% on "Z"
### Cost of each
### Say
### 17.42.2.3 Hubless centrifugally cast (spun) iron pipes
### epoxy coated inside & outside
IS:15905
### Detail of cost for one no.
### MATERIAL
### 7626 Hubless centrifugally cast (spun) iron double equal each 1 275
### plain junction as per IS 15905 - 75x75x75x75 mm dia
### 9977 Carriage of materials and fixing charges L.S. 10.79 2
### TOTAL
### Add 1 % Water charges on "W"
### TOTAL
### Add GST (multiplying factor 0.1405) on "X"
### TOTAL
### Add 15 % Contractor's profit and overheads on "Y"
### Total
### Add Cess @ 1% on "Z"
### Cost of each
### Say
###
### 17.43 Providing and fixing single equal
### plain junction of required degree with
### door, insertion rubber washer 3 mm thick,
### bolts and nuts complete.
### 17.43.1 100x100x100 mm
###
### 17.43.1.1 Sand cast iron S&S as per IS - 1729
###
### Details of cost for one no.
###
### MATERIAL
###
###
###
###
###
### 1370
###
###
### 1631 S.C.I. single equal junctions 100x100x 100 mm dia each 1 405
### with access door.
### 1374 Rubber insertions for 100 mm dia pipe joints each 1 18
### 9988 Carriage of materials and fixing charges L.S. 13.52 2
### TOTAL
### Add 1 % Water charges on "W"
### TOTAL
### Add GST (multiplying factor 0.1405) on "X"
### TOTAL
### Add 15 % Contractor's profit and overheads on "Y"
### Total
### Add Cess @ 1% on "Z"
### Cost of each
### Say
### 17.43.1.2 Sand cast iron S&S as per IS - 3989
### Details of cost for one no.
### MATERIAL
### 3644 S.C.I. S&S single equal junctions with access door each 1 495
### 100x100x100 mm
### 1374 Rubber insertions for 100 mm dia pipe joints each 1 18
### 9988 Carriage of materials and fixing charges L.S. 13.52 2
### TOTAL
### Add 1 % Water charges on "W"
### TOTAL
### Add GST (multiplying factor 0.1405) on "X"
### TOTAL
### Add 15 % Contractor's profit and overheads on "Y"
### Total
### Add Cess @ 1% on "Z"
### Cost of each
### Say
###
### 17.43.2 75x75x75 mm
###
### 17.43.2.1 Sand cast iron S&S as per IS - 1729
###
### Details of cost for one no.
###
### MATERIAL
###
###
###
###
###
###
###
### 1371
###
###
### 1630 S.C.I. single equal junctions75x75x75 mm dia with each 1 320
### access door.
### 1373 Rubber insertions for 80 mm dia pipe joints each 1 16
### 9988 Carriage of materials and fixing charges L.S. 10.79 2
### TOTAL
### Add 1 % Water charges on "W"
### TOTAL
### Add GST (multiplying factor 0.1405) on "X"
### TOTAL
### Add 15 % Contractor's profit and overheads on "Y"
### Total
### Add Cess @ 1% on "Z"
### Cost of each
### Say
### 17.43.2.2 Sand cast iron S&S as per IS - 3989
### Details of cost for one no.
### MATERIAL
### 3645 S.C.I. S&S single equal junctions with access door each 1 373
### 75x75x75 mm
### 1373 Rubber insertions for 80 mm dia pipe joints each 1 16
### 9988 Carriage of materials and fixing charges L.S. 10.79 2
### TOTAL
### Add 1 % Water charges on "W"
### TOTAL
### Add GST (multiplying factor 0.1405) on "X"
### TOTAL
### Add 15 % Contractor's profit and overheads on "Y"
### Total
### Add Cess @ 1% on "Z"
### Cost of each
### Say
###
### 17.44 Providing and fixing single equal
### plain junction of required degree :
### 17.44.1 100x100x100 mm
###
### 17.44.1.1 Sand cast iron S&S as per IS - 1729
###
### Details of cost for one no.
###
### MATERIAL
###
###
###
###
###
###
### 1372
###
###
### 1628 S.C.I. plain single equal junctions 100x100x100 mm each 1 360
### dia
### 9988 Carriage of materials and fixing charges L.S. 13.52 2
### TOTAL
### Add 1 % Water charges on "W"
### TOTAL
### Add GST (multiplying
factor 0.1405)
### TOTAL
### Add 15 % Contractor's profit and overheads on "Y"
### Total
### Add Cess @ 1% on "Z"
### Cost of each
### Say
### 17.44.1.2 Sand cast iron S&S as per IS - 3989
### Details of cost for one no.
### MATERIAL
### 3640 S.C.I. S&S single equal junctions 100x100x100 mm each 1 472
### 9988 Carriage of materials and fixing charges L.S. 13.52 2
### TOTAL
### Add 1 % Water charges on "W"
### TOTAL
### Add GST (multiplying
factor 0.1405)
### TOTAL
### Add 15 % Contractor's profit and overheads on "Y"
### Total
### Add Cess @ 1% on "Z"
### Cost of each
### Say
### 17.44.1.3 Hubless centrifugall epoxy
### per IS:15905 y cast coated
### Detail of cost for one no.
### MATERIAL
### 7627 Hubless centrifugally cast (spun) iron single equal each 1 400
### plain junction as per IS 15905 100x100x100 mm dia
### 9977 Carriage of materials and fixing charges L.S. 13.52 2
### TOTAL
### Add 1 % Water charges on "W"
###
###
###
###
###
###
### 1373
###
###
### TOTAL
### Add GST (multiplying factor 0.1405) on "X"
### TOTAL
### Add 15 % Contractor's profit and overheads on "Y"
### Total
### Add Cess @ 1% on "Z"
### Cost of each
### Say
### 17.44.2 75x75x75 mm
### 17.44.2.1 Sand cast iron S&S as per IS - 1729
### Details of cost for one no.
### MATERIAL
### 1627 S.C.I. plain single equal junctions 75x75x75 mm dia each 1 278
### 9988 Carriage of materials and fixing charges L.S. 10.79 2
### TOTAL
### Add 1 % Water charges on "W"
### TOTAL
### Add GST (multiplying factor 0.1405) on "X"
### TOTAL
### Add 15 % Contractor's profit and overheads on "Y"
### Total
### Add Cess @ 1% on "Z"
### Cost of each
### Say
### 17.44.2.2 Sand cast iron S&S as per IS - 3989
### Details of cost for one no.
### MATERIAL
### 3641 S.C.I. S&S single equal junctions 75x75x75 mm each 1 330
### 9988 Carriage of materials and fixing charges L.S. 10.79 2
### TOTAL
### Add 1 % Water charges on "W"
### TOTAL
### Add GST (multiplying factor 0.1405) on "X"
### TOTAL
### Add 15 % Contractor's profit and overheads on "Y"
### Total
### Add Cess @ 1% on "Z"
### Cost of each
###
###
###
###
###
###
###
### 1374
###
###
###
### Say
###
### 17.44.2.3 Hubless centrifugally cast (spun) iron
### epoxy coated inside
Detail & outside
of cost as per
for one no.
###
### MATERIAL
### 7628 Hubless centrifugally cast (spun) iron single equal each 1 215
### plain junction as per IS 15905 75x75x75 mm dia
### 9977 Carriage of materials and fixing charges L.S. 10.79 2
### TOTAL
### Add 1 % Water charges on "W"
### TOTAL
### Add GST (multiplying factor 0.1405) on "X"
### TOTAL
### Add 15 % Contractor's profit and overheads on "Y"
### Total
### Add Cess @ 1% on "Z"
### Cost of each
### Say
###
### 17.45 Providing and fixing double
### unequal junction of required degree with
### door, insertion rubber washer 3 mm thick,
### bolts and nuts complete:
### 17.45.1 100x100x75x75 mm
###
### 17.45.1.1 Sand cast iron S&S as per IS - 1729
### Details of cost for one no.
### MATERIAL
### 1662 Sand cast iron S&S double unequal junctions: each 1 700
### 100x100x75x75 mm dia with access door.
### 1374 Rubber insertions for 100 mm dia pipe joints each 1 18
### 9988 Carriage of materials and fixing charges L.S. 13.52 2
### TOTAL
### Add 1 % Water charges on "W"
### TOTAL
### Add GST (multiplying factor 0.1405) on "X"
### TOTAL
### Add 15 % Contractor's profit and overheads on "Y"
### Total
### Add Cess @ 1% on "Z"
### Cost of each
### Say
###
###
###
###
###
###
###
###
###
### 17.45.1.2 Sand cast iron S&S as per IS - 3989
###
### Details of cost for one no.
###
### MATERIAL
###
### 3674 S.C.I. S&S double unequal junctions with access each 1 850
### door 100x100x75x75 mm
### 1374 Rubber insertions for 100 mm dia pipe joints each 1 18
### 9988 Carriage of materials and fixing charges L.S. 13.52 2
### TOTAL
### Add 1 % Water charges on "W"
### TOTAL
### Add GST (multiplying factor 0.1405) on "X"
### TOTAL
### Add 15 % Contractor's profit and overheads on "Y"
### Total
### Add Cess @ 1% on "Z"
### Cost of each
### Say
###
### 17.46 Providing and fixing double
### unequal plain junction of required degree :
### 17.46.1 100x100x75x75 mm
###
### 17.46.1.1 Sand cast iron S&S as per IS - 1729
### Details of cost for one no.
### MATERIAL
### 1659 Sand cast iron S&S plain double unequal junctions : each 1 615
### 100x100x75x75 mm dia
### 9988 Carriage of materials and fixing charges L.S. 13.52 2
### TOTAL
### Add 1 % Water charges on "W"
### TOTAL
### Add GST (multiplying factor 0.1405) on "X"
### TOTAL
### Add 15 % Contractor's profit and overheads on "Y"
### Total
### Add Cess @ 1% on "Z"
### Cost of each
### Say
### 17.46.1.2 Sand cast iron S&S as per IS - 3989
### Details of cost for one no.
###
###
###
###
###
###
###
### MATERIAL
### 3670 S.C.I. S&S double unequal junctions 100x100x75x75 each 1 800
### mm
### 9988 Carriage of materials and fixing charges L.S. 13.52 2
### TOTAL
### Add 1 % Water charges on "W"
### TOTAL
### Add GST (multiplying factor 0.1405) on "X"
### TOTAL
### Add 15 % Contractor's profit and overheads on "Y"
### Total
### Add Cess @ 1% on "Z"
### Cost of each
### Say
###
### 17.46.1.3 Hubless centrifugally cast (spun) iron
### epoxy coated inside
Detail & outside
of cost as per
for one no.
###
### MATERIAL
### 7629 Hubless centrifugally cast (spun) iron double each 1 400
unequal
### plain junction as per IS 15905 - 100x100x75x75 mm
### dia
### 9977 Carriage of materials and fixing charges L.S. 13.52 2
### TOTAL
### Add 1 % Water charges on "W"
### TOTAL
### Add GST (multiplying factor 0.1405) on "X"
### TOTAL
### Add 15 % Contractor's profit and overheads on "Y"
### Total
### Add Cess @ 1% on "Z"
### Cost of each
### Say
###
###
###
### 17.47 Providing and fixing single unequal
### junction of required degree with access
### 17.47.1 100x100x75 mm
###
### 17.47.1.1 Sand cast iron S&S as per IS - 1729
###
### Details of cost for one no.
###
###
###
###
###
###
###
### MATERIAL
### 1656 Sand cast iron S&S single unequal junctions: each 1 550
### 100x100x75 mm dia with access door.
### 1374 Rubber insertions for 100 mm dia pipe joints each 1 18
### 9988 Carriage of materials and fixing charges L.S. 13.52 2
### TOTAL
### Add 1 % Water charges on "W"
### TOTAL
### Add GST (multiplying factor 0.1405) on "X"
### TOTAL
### Add 15 % Contractor's profit and overheads on "Y"
### Total
### Add Cess @ 1% on "Z"
### Cost of each
### Say
### 17.47.1.2 Sand cast iron S&S as per IS - 3989
### Details of cost for one no.
### MATERIAL
### 3664 S.C.I. S&S single unequal junctions with access door each 1 640
### 100x100x75 mm
### 1374 Rubber insertions for 100 mm dia pipe joints each 1 18
### 9988 Carriage of materials and fixing charges L.S. 13.52 2
### TOTAL
### Add 1 % Water charges on "W"
### TOTAL
### Add GST (multiplying factor 0.1405) on "X"
### TOTAL
### Add 15 % Contractor's profit and overheads on "Y"
### Total
### Add Cess @ 1% on "Z"
### Cost of each
### Say
###
### 17.48 Providing and fixing single unequal
### plain junction of required degree :
### 17.48.1 100x100x75 mm
###
### 17.48.1.1 Sand cast iron S&S as per IS - 1729
### Details of cost for one no.
### MATERIAL
### 1653 Sand cast iron S&S plain single unequal junctions : each 1 494
### 100x100x75 mm dia
###
###
###
###
###
###
###
### 9988 Carriage of materials and fixing charges L.S. 13.52 2
### TOTAL
### Add 1 % Water charges on "W"
### TOTAL
### Add GST (multiplying factor 0.1405) on "X"
### TOTAL
### Add 15 % Contractor's profit and overheads on "Y"
### Total
### Add Cess @ 1% on "Z"
### Cost of each
### Say
### 17.48.1.2 Sand cast iron S&S as per IS - 3989
### Details of cost for one no.
### MATERIAL
### 3660 S.C.I. S&S single unequal junctions 100x100x75 mm each 1 570
### 9988 Carriage of materials and fixing charges L.S. 13.52 2
### TOTAL
### Add 1 % Water charges on "W"
### TOTAL
### Add GST (multiplying factor 0.1405) on "X"
### TOTAL
### Add 15 % Contractor's profit and overheads on "Y"
### Total
### Add Cess @ 1% on "Z"
### Cost of each
### Say
###
### 17.48.1.3 Hubless centrifugally cast (spun)
### iron epoxy coated inside & outside as per
### Detail of cost for one no.
###
### MATERIAL
### 7630 Hubless centrifugally cast (spun) iron single each 1 375
### unequal plain junction as per IS 15905 100x100x75
### mm dia
### 9977 Carriage of materials and fixing charges L.S. 13.52 2
### TOTAL
###
###
###
###
###
###
###
### Add 1 % Water charges on "W" 4.02
### TOTAL
### Add GST (multiplying factor 0.1405) on "X" 57.05
### TOTAL
### Add 15 % Contractor's profit and overheads on "Y" 69.47
### Total
### Add Cess @ 1% on "Z" 5.33
### Cost of each 537.9
### Say
###
### 17.49 Providing and fixing double equal
### plain invert branch of required degree:
### 17.49.1 100x100x100x100 mm
###
### 17.49.1.1 Sand cast iron S&S as per IS - 1729
### Details of cost for one no.
### MATERIAL
### 1673 S.C.I. double equal invert branch of required degree each 1 550
### 100x100x100x100 mm dia
### 9988 Carriage of materials and fixing charges L.S. 13.52 2
### TOTAL
### Add 1 % Water charges on "W"
### TOTAL
### Add GST (multiplying factor 0.1405) on "X"
### TOTAL
### Add 15 % Contractor's profit and overheads on "Y"
### Total
### Add Cess @ 1% on "Z"
### Cost of each
### Say
### 17.49.1.2 Sand cast iron S&S as per IS 3989
### Details of cost for one no.
### MATERIAL
### 3685 S.C.I. S&S double equal invert branch each 1 530
### of required degree100x100x100x
### 100 mm dia
### 9988 Carriage of materials and fixing charges L.S. 13.52 2
### TOTAL
### Add 1 % Water charges on "W"
### TOTAL
###
###
###
###
###
###
###
###
### Add GST (multiplying factor 0.1405) on "X" 79.05
### TOTAL
### Add 15 % Contractor's profit and overheads on "Y" 96.25
### Total
### Add Cess @ 1% on "Z" 7.38
### Cost of each 745.28
### Say
###
### 17.49.1.3 Hubless centrifugally cast (spun) iron
### epoxy coated inside & outside as per
### Details of cost for one no.
###
### MATERIAL
###
### 7631 Hubless centrifugally cast (spun) iron each 1 625
### double equal plain invert branch as per
### IS 15905 - 100x100x100x100 mm dia
### 9977 Carriage of materials and fixing charges L.S. 13.52 2
### TOTAL
### Add 1 % Water charges on "W"
### TOTAL
### Add GST (multiplying factor 0.1405) on "X"
### TOTAL
### Add 15 % Contractor's profit and overheads on "Y"
### Total
### Add Cess @ 1% on "Z"
### Cost of each
### Say
### 17.49.2 75x75x75x75 mm
### 17.49.2.1 Sand cast iron S&S as per IS -
### 1729
Details of cost for one no.
### MATERIAL
### 1672 S.C.I. double equal invert branch of each 1 410
### required degree 75x75x75x75 mm dia
### 9988 Carriage of materials and fixing charges L.S. 10.79 2
### TOTAL
### Add 1 % Water charges on "W"
### TOTAL
###
###
###
###
###
###
###
###
### Add GST (multiplying factor 0.1405) on "X"
### TOTAL
### Add 15 % Contractor's profit and overheads on "Y"
### Total
### Add Cess @ 1% on "Z"
### Cost of each
### Say
### 17.49.2.2 Sand cast iron S&S as per IS -
### 3989
Details of cost for one no.
### MATERIAL
### 3686 S.C.I. S&S double equal invert branch each 1 425
### of required degree 75x75x75x75 mm dia
### 9988 Carriage of materials and fixing charges L.S. 10.79 2
### TOTAL
### Add 1 % Water charges on "W"
### TOTAL
### Add GST (multiplying factor 0.1405) on "X"
### TOTAL
### Add 15 % Contractor's profit and overheads on "Y"
### Total
### Add Cess @ 1% on "Z"
### Cost of each
### Say
###
###
### 17.50 Providing and fixing single equal
### plain invert branch of required degree :
### 17.50.1 100x100x100 mm
###
### 17.50.1.1 Sand cast iron S&S as per IS- 1729
### Details of cost for one no.
### MATERIAL
### 1670 S.C.I. single equal invert branch of required degree each 1 410
### 100x100x100 mm dia
### 9988 Carriage of materials and fixing charges L.S. 13.52 2
### TOTAL
### Add 1 % Water charges on "W"
### TOTAL
### Add GST (multiplying factor 0.1405) on "X"
###
###
###
###
###
###
###
###
### TOTAL
### Add 15 % Contractor's profit and overheads on "Y"
### Total
### Add Cess @ 1% on "Z"
### Cost of each
### Say
### 17.50.1.2 Sand cast iron S&S as per IS - 3989
### Details of cost for one no.
### MATERIAL
### 3681 S.C.I. S&S single equal invert branch of required each 1 425
### degree 100x100x100 mm dia
### 9988 Carriage of materials and fixing charges L.S. 13.52 2
### TOTAL
### Add 1 % Water charges on "W"
### TOTAL
### Add GST (multiplying factor 0.1405) on "X"
### TOTAL
### Add 15 % Contractor's profit and overheads on "Y"
### Total
### Add Cess @ 1% on "Z"
### Cost of each
### Say
###
### 17.50.1.3 Hubless centrifugally cast (spun) iron
### epoxy coated inside
Detail & outside
of cost as per
for one no.
###
### MATERIAL
### 7632 Hubless centrifugally cast (spun) iron single each 1 390
### equal plain invert branch as per IS 15905
### 100x100x100 mm dia
### 9977 Carriage of materials and fixing charges L.S. 13.52 2
### TOTAL
### Add 1 % Water charges on "W"
### TOTAL
### Add GST (multiplying factor 0.1405) on "X"
### TOTAL
###
###
###
###
###
###
###
###
### Add 15 % Contractor's profit and overheads on "Y"
### Total
### Add Cess @ 1% on "Z"
### Cost of each
### Say
### 17.50.2 75x75x75 mm
### 17.50.2.1 Sand cast iron S&S as per IS - 1729
### Details of cost for one no.
### MATERIAL
### 1669 S.C.I. single equal invert branch of required each 1 320
### degree75x75x75 mm dia
### 9988 Carriage of materials and fixing charges L.S. 10.79 2
### TOTAL
### Add 1 % Water charges on "W"
### TOTAL
### Add GST (multiplying factor 0.1405) on "X"
### TOTAL
### Add 15 % Contractor's profit and overheads on "Y"
### Total
### Add Cess @ 1% on "Z"
### Cost of each
### Say
### 17.50.2.2 Sand cast iron S&S as per IS - 3989
### Details of cost for one no.
### MATERIAL
### 3682 S.C.I. S&S single equal invert branch of required each 1 323
### degree 75x75x75 mm dia
### 9988 Carriage of materials and fixing charges L.S. 10.79 2
### TOTAL
### Add 1 % Water charges on "W"
### TOTAL
### Add GST (multiplying factor 0.1405) on "X"
### TOTAL
### Add 15 % Contractor's profit and overheads on "Y"
### Total
### Add Cess @ 1% on "Z"
### Cost of each
###
###
###
###
###
###
###
###
###
### Say
###
### 17.50.2.3 Hubless centrifugally cast (spun) iron
### epoxyofcoated
Detail cost for inside
one no. & outside as per
### MATERIAL
### 7633 Hubless centrifugally cast (spun) iron single each 1 260
### equal plain invert branch as per IS 15905 75x75x75
### mm dia
### 9977 Carriage of materials and fixing charges L.S. 10.79 2
### TOTAL
### Add 1 % Water charges on "W"
### TOTAL
### Add GST (multiplying factor 0.1405) on "X"
### TOTAL
### Add 15 % Contractor's profit and overheads on "Y"
### Total
### Add Cess @ 1% on "Z"
### Cost of each
### Say
###
### 17.51 Providing and fixing double
### unequal invert branch of required degree :
### 17.51.1 100x100x75x75 mm
###
### 17.51.1.1 Sand cast iron S&S as per IS - 1729
### Details of cost for one no.
### MATERIAL
### 1677 S.C.I. double unequal invert branch of required each 1 570
### degree 100x100x75x75 mm dia
### 9988 Carriage of materials and fixing charges L.S. 13.52 2
### TOTAL
### Add 1 % Water charges on "W"
### TOTAL
### Add GST (multiplying factor 0.1405) on "X"
### TOTAL
### Add 15 % Contractor's profit and overheads on "Y"
### Total
### Add Cess @ 1% on "Z"
### Cost of each
### Say
###
### 17.51.1.2 Sand cast iron S&S as per IS - 3989
###
### Details of cost for one no.
###
### MATERIAL
###
###
###
###
###
###
###
### 3695 S.C.I. S&S double unequal invert branch of required each 1 725
### degree100x100x75x75 mm dia
### 9988 Carriage of materials and fixing charges L.S. 13.52 2
### TOTAL
### Add 1 % Water charges on "W"
### TOTAL
### Add GST (multiplying factor 0.1405) on "X"
### TOTAL
### Add 15 % Contractor's profit and overheads on "Y"
### Total
### Add Cess @ 1% on "Z"
### Cost of each
### Say
###
### 17.52 Providing and fixing single unequal
### plain invert branch of required degree :
### 17.52.1 100x100x75 mm
###
### 17.52.1.1 Sand cast iron S&S as per IS - 1729
### Details of cost for one no.
### MATERIAL
### 1674 S.C.I. single unequal invert branch of required each 1 495
### degree100x100x75 mm dia
### 9988 Carriage of materials and fixing charges L.S. 13.52 2
### TOTAL
### Add 1 % Water charges on "W"
### TOTAL
### Add GST (multiplying factor 0.1405) on "X"
### TOTAL
### Add 15 % Contractor's profit and overheads on "Y"
### Total
### Add Cess @ 1% on "Z"
### Cost of each
### Say
### 17.52.1.2 Sand cast iron S&S as per IS - 3989
### Details of cost for one no.
### MATERIAL
### 3690 S.C.I. S&S single unequal invert branch of required each 1 545
### degree100x100x75 mm dia
### 9988 Carriage of materials and fixing charges L.S. 13.52 2
### TOTAL
### Add 1 % Water charges on "W"
### TOTAL
###
###
###
###
###
###
###
### Add GST (multiplying factor 0.1405) on "X" 81.18
### TOTAL
### Add 15 % Contractor's profit and overheads on "Y" 98.84
### Total
### Add Cess @ 1% on "Z" 7.58
### Cost of each 765.35
### Say
###
### 17.52.1.3 Hubless centrifugally cast (spun) iron
### epoxy coated inside & outside as per
### Detail of cost for one no.
###
### MATERIAL
### 7634 Hubless centrifugally cast (spun) iron single unequal each 1 430
### plain invert branch 45 degree as
### per IS 15905 - 100x100x75 mm dia
### 9977 Carriage of materials and fixing charges L.S. 13.52 2
### TOTAL
### Add 1 % Water charges on "W"
### TOTAL
### Add GST (multiplying factor 0.1405) on "X"
### TOTAL
### Add 15 % Contractor's profit and overheads on "Y"
### Total
### Add Cess @ 1% on "Z"
### Cost of each
### Say
###
### 17.53 Providing and fixing sand cast iron
### S&S off sets as per IS: 1729
### 17.53.1 76 mm off sets
###
### 17.53.1.1 With 75 mm dia pipe
### Details of cost for one no.
### MATERIAL
### 3746 S.C.I. S&S, 75 mm offset for 75 mm dia pipe each 1 218
### 9988 Carriage of materials and fixing charges L.S. 10.79 2
### TOTAL
### Add 1 % Water charges on "W"
### TOTAL
### Add GST (multiplying factor 0.1405) on "X"
### TOTAL
###
###
###
###
###
###
###
###
### Add 15 % Contractor's profit and overheads on "Y"
Total
###
### Add Cess @ 1% on "Z" Cost of each
###
### Say
###
### 17.53.1.2 With 100 mm dia pipe
###
### Details of cost for one no.
###
### MATERIAL
###
### 3747 S.C.I. S&S, 75 mm offset for 100 mm dia pipe
###
### 9988 Carriage of materials and fixing charges 2
###
### TOTAL
###
### Add 1 % Water charges on "W"
###
### TOTAL
###
### Add GST (multiplying factor 0.1405) on "X"
###
### TOTAL
###
### Add 15 % Contractor's profit and overheads on "Y"
Total
###
### Add Cess @ 1% on "Z" Cost of each
###
### Say
###
### 17.53.2 114 mm off sets
###
### 17.53.2.1 With 75 mm dia pipe
###
### Details of cost for one no.
###
### MATERIAL
###
### 3712 S.C.I. S&S, 114 mm offset for75 mm dia pipe
###
### 9988 Carriage of materials and fixing charges 2
###
### TOTAL
###
### Add 1 % Water charges on "W"
###
### TOTAL
###
### Add GST (multiplying factor 0.1405) on "X"
###
### TOTAL
###
### Add 15 % Contractor's profit and overheads on "Y"
Total
###
### Add Cess @ 1% on "Z"
###
###
###
### 41.4
###
### 317.37 Z
###
### 3.17
###
### 320.54
###
### 320.55
###
###
###
###
###
###
### each 1 363
### L.S. 10.79 2
### 384.58 W
### 3.85
### 388.43 X
### 54.57
### 443 Y
### 66.45
### 509.45 Z
### 5.09
### 514.54
### 514.55
###
###
###
###
###
###
###
###
### each 1 300
### L.S. 13.52 2
### 327.04 W
### 3.27
### 330.31 X
### 46.41
### 376.72 Y
### 56.51
### 433.23 Z
### 4.33
###
###
###
###
###
###
###
### Cost of each
### Say
### 17.53.2.2 With 100 mm dia pipe
### Details of cost for one no.
### MATERIAL
### 3713 S.C.I. S&S, 114 mm offset for100 mm dia pipe each 1 383
### 9988 Carriage of materials and fixing charges L.S. 13.52 2
### TOTAL
### Add 1 % Water charges on "W"
### TOTAL
### Add GST (multiplying factor 0.1405) on "X"
### TOTAL
### Add 15 % Contractor's profit and overheads on "Y"
### Total
### Add Cess @ 1% on "Z"
### Cost of each
### Say
###
### 17.53.3 152 mm off sets
###
### 17.53.3.1 With 75 mm dia pipe
### Details of cost for one no.
### MATERIAL
### 3716 S.C.I. S&S, 152 mm offset for75 mm dia pipe each 1 358
### 9988 Carriage of materials and fixing charges L.S. 17.94 2
### TOTAL
### Add 1 % Water charges on "W"
### TOTAL
### Add GST (multiplying factor 0.1405) on "X"
### TOTAL
### Add 15 % Contractor's profit and overheads on "Y"
### Total
### Add Cess @ 1% on "Z"
### Cost of each
### Say
###
###
###
###
###
###
###
###
### 17.53.3.2 With 100 mm dia pipe
### Details of cost for one no.
### MATERIAL
### 3717 S.C.I. S&S, 152 mm offset for100 mm dia pipe each 1 455
### 9988 Carriage of materials and fixing charges L.S. 17.94 2
### TOTAL
### Add 1 % Water charges on "W"
### TOTAL
### Add GST (multiplying factor 0.1405) on "X"
### TOTAL
### Add 15 % Contractor's profit and overheads on "Y"
### Total
### Add Cess @ 1% on "Z"
### Cost of each
### Say
### 17.53A Providing and fixing Hubless centrifugally cast iron offsets
### inside & outside as per IS:15905 epoxy
### 17.53A.1 65 mm offsets
### 17.53A.1.1 With 100 mm dia pipe
### Detail of cost for one no.
### MATERIAL
### 7635 Hubless centrifugally cast (spun) iron 65 mm offset each 1 360
### with 100 mm dia pipe as per IS 15905
### 9977 Carriage of materials and fixing charges L.S. 10.79 2
### TOTAL
### Add 1 % Water charges on "W"
### TOTAL
### Add GST (multiplying factor 0.1405) on "X"
### TOTAL
### Add 15 % Contractor's profit and overheads on "Y"
### Total
### Add Cess @ 1% on "Z"
### Cost of each
### Say
### 17.53A.1.2 With 75 mm dia pipe
### Detail of cost for one no.
### MATERIAL
### 7636 Hubless centrifugally cast (spun) iron 65 mm offset each 1 295
### with 75 mm dia pipe as per IS 15905
###
###
###
###
###
###
###
### 9977 Carriage of materials and fixing charges L.S. 10.79 2
### TOTAL
### Add 1 % Water charges on "W"
### TOTAL
### Add GST (multiplying factor 0.1405) on "X"
### TOTAL
### Add 15 % Contractor's profit and overheads on "Y"
### Total
### Add Cess @ 1% on "Z"
### Cost of each
### Say
###
### 17.54 Providing and fixing sand cast iron
### S&S off sets as per IS: 3989 :
### 17.54.1 75 mm off sets
###
### 17.54.1.1 With 75 mm dia pipe
### Details of cost for one no.
### MATERIAL
### 3699 S.C.I. S&S, 75 mm offset for75 mm dia pipe each 1 225
### 9988 Carriage of materials and fixing charges L.S. 10.79 2
### TOTAL
### Add 1 % Water charges on "W"
### TOTAL
### Add GST (multiplying factor 0.1405) on "X"
### TOTAL
### Add 15 % Contractor's profit and overheads on "Y"
### Total
### Add Cess @ 1% on "Z"
### Cost of each
### Say
###
### 17.54.2 150 mm off sets
###
### 17.54.2.1 With 75 mm dia pipe
### Details of cost for one no.
### MATERIAL
### 3707 S.C.I. S&S, 150 mm offset for75 mm dia pipe each 1 285
### 9988 Carriage of materials and fixing charges L.S. 16.12 2
### TOTAL
### Add 1 % Water charges on "W"
###
###
###
###
###
###
###
### TOTAL
### Add GST (multiplying factor 0.1405) on "X"
### TOTAL
### Add 15 % Contractor's profit and overheads on "Y"
### Total
### Add Cess @ 1% on "Z"
### Cost of each
### Say
### 17.54.2.2 With 100 mm dia pipe
### Details of cost for one no.
### MATERIAL
### 3708 S.C.I. S&S, 150 mm offset for 100 mm dia pipe each 1 390
### 9988 Carriage of materials and fixing charges L.S. 16.12 2
### TOTAL
### Add 1 % Water charges on "W"
### TOTAL
### Add GST (multiplying factor 0.1405) on "X"
### TOTAL
### Add 15 % Contractor's profit and overheads on "Y"
### Total
### Add Cess @ 1% on "Z"
### Cost of each
### Say
### 17.54A Providing and fixing Hubless centrifugally cast iron offsets
### inside & outside as per IS:15905 epoxy
### 17.54A.1 130 mm offsets
### 17.54A.1.1 With 100 mm dia
### Detail of cost for one no.
### MATERIAL
### 7637 Hubless centrifugally cast (spun) iron 130 mm offset each 1 440
### with 100 mm dia pipe as per IS 15905
### 9977 Carriage of materials and fixing charges L.S. 13.52 2
### TOTAL
### Add 1 % Water charges on "W"
### TOTAL
### Add GST (multiplying factor 0.1405) on "X"
### TOTAL
### Add 15 % Contractor's profit and overheads on "Y"
### Total
### Add Cess @ 1% on "Z"
### Cost of each
###
###
###
###
###
###
###
###
### Say
### 17.54A.1.2 With 75 mm dia
### Detail of cost for one no.
### MATERIAL
### 7638 Hubless centrifugally cast (spun) iron 130 mm offset each 1 310
### with 75 mm dia pipe as per IS 15905
### 9999 Carriage of materials and fixing charges L.S. 10.79 2
### TOTAL
### Add 1 % Water charges on "W"
### TOTAL
### Add GST (multiplying factor 0.1405) on "X"
### TOTAL
### Add 15 % Contractor's profit and overheads on "Y"
### Total
### Add Cess @ 1% on "Z"
### Cost of each
### Say
###
### 17.55 Providing and fixing door piece,
### insertion rubber washer 3mm thick, bolts &
### 17.55.1 100 mm
###
### 17.55.1.1 Sand cast iron S&S as per IS - 1729
### Details of cost for one no.
### MATERIAL
### 1683 S.C.I. door pieces 100 mm dia each 1 475
### 1374 Rubber insertions for 100 mm dia pipe joints each 1 18
### 9988 Carriage of materials and fixing charges L.S. 13.52 2
### TOTAL
### Add 1 % Water charges on "W"
### TOTAL
### Add GST (multiplying factor 0.1405) on "X"
### TOTAL
### Add 15 % Contractor's profit and overheads on "Y"
### Total
### Add Cess @ 1% on "Z"
### Cost of each
### Say
### 17.55.1.2 Sand cast iron S&S as per IS - 3989
### Details of cost for one no.
### MATERIAL
### 3728 S.C.I. S&S door pieces 100 mm dia each 1 400
###
###
###
###
###
###
###
### 1374 Rubber insertions for 100 mm dia pipe joints each 1 18
### 9988 Carriage of materials and fixing charges L.S. 13.52 2
### TOTAL
### Add 1 % Water charges on "W"
### TOTAL
### Add GST (multiplying factor 0.1405) on "X"
### TOTAL
### Add 15 % Contractor's profit and overheads on "Y"
### Total
### Add Cess @ 1% on "Z"
### Cost of each
### Say
###
### 17.55.2 75 mm
###
### 17.55.2.1 Sand cast iron S&S as per IS - 1729
### Details of cost for one no.
### MATERIAL
### 1682 S.C.I. door pieces 75 mm dia each 1 283
### 1373 Rubber insertions for 80 mm dia pipe joints each 1 16
### 9988 Carriage of materials and fixing charges L.S. 10.79 2
### TOTAL
### Add 1 % Water charges on "W"
### TOTAL
### Add GST (multiplying factor 0.1405) on "X"
### TOTAL
### Add 15 % Contractor's profit and overheads on "Y"
### Total
### Add Cess @ 1% on "Z"
### Cost of each
### Say
### 17.55.2.2 Sand cast iron S&S as per IS - 3989
### Details of cost for one no.
### MATERIAL
### 3729 S.C.I. S&S door pieces 75 mm dia each 1 295
### 1373 Rubber insertions for 80 mm dia pipe joints each 1 16
### 9988 Carriage of materials and fixing charges L.S. 10.79 2
### TOTAL
### Add 1 % Water charges on "W"
### TOTAL
### Add GST (multiplying factor 0.1405) on "X"
### TOTAL
### Add 15 % Contractor's profit and overheads on "Y"
###
###
###
###
###
###
### Total
### Add Cess @ 1% on "Z" 4.41
### Cost of each 444.97
### Say
###
### 17.56 Providing and fixing terminal
### guard :
### 17.56.1 100 mm
###
### 17.56.1.1 Sand cast iron S&S as per IS - 1729
### Details of cost for one no.
### MATERIAL
### 1640 Slotted cowl (terminal guard ) 100 mm dia each 1 239
### 9988 Carriage of materials and fixing charges L.S. 13.52 2
### TOTAL
### Add 1 % Water charges on "W"
### TOTAL
### Add GST (multiplying factor 0.1405) on "X"
### TOTAL
### Add 15 % Contractor's profit and overheads on "Y"
### Total
### Add Cess @ 1% on "Z"
### Cost of each
### Say
### 17.56.1.2 Sand cast iron S&S as per IS - 3989
### Details of cost for one no.
### MATERIAL
### 3733 S.C.I. S&S, Slotted Cowl (Terminal Guard) 100 mm each 1 264
### 9988 Carriage of materials and fixing charges L.S. 13.52 2
### TOTAL
### Add 1 % Water charges on "W"
### TOTAL
### Add GST (multiplying factor 0.1405) on "X"
### TOTAL
### Add 15 % Contractor's profit and overheads on "Y"
### Total
### Add Cess @ 1% on "Z"
### Cost of each
### Say
###
###
### 17.56.1.3 Hubless centrifugally cast (spun) iron
### epoxy coated inside
Detail & outside
of cost as per
for one no.
###
###
###
###
###
###
### MATERIAL
### 7641 Hubless centrifugally cast (spun) iron terminal guard each 1 270
### (slotted cowl) - 100 mm dia
### as per IS 15905
### 9977 Carriage of materials and fixing charges L.S. 13.52 2
### TOTAL
### Add 1 % Water charges on "W"
### TOTAL
### Add GST (multiplying factor 0.1405) on "X"
### TOTAL
### Add 15 % Contractor's profit and overheads on "Y"
### Total
### Add Cess @ 1% on "Z"
### Cost of each
### Say
###
### 17.56.2 75 mm
###
### 17.56.2.1 Sand cast iron S&S as per IS - 1729
### Details of cost for one no.
### MATERIAL
### 1639 Slotted cowl (terminal guard )75 mm dia each 1 191
### 9988 Carriage of materials and fixing charges L.S. 10.79 2
### TOTAL
### Add 1 % Water charges on "W"
### TOTAL
### Add GST (multiplying factor 0.1405) on "X"
### TOTAL
### Add 15 % Contractor's profit and overheads on "Y"
### Total
### Add Cess @ 1% on "Z"
### Cost of each
### Say
### 17.56.2.2 Sand cast iron S&S as per IS - 3989
### Details of cost for one no.
### MATERIAL
### 3734 S.C.I. S&S, Slotted Cowl (Terminal Guard) 75 mm each 1 210
### 9988 Carriage of materials and fixing charges L.S. 10.79 2
### TOTAL
### Add 1 % Water charges on "W"
### TOTAL
### Add GST (multiplying factor 0.1405) on "X"
### TOTAL
###
###
###
###
###
###
###
### Add 15 % Contractor's profit and overheads on "Y"
### Total
### Add Cess @ 1% on "Z"
### Cost of each
### Say
### 17.57 Providing and fixing collar :
###
### 17.57.1
### 100 mm
### 17.57.1.1 Sand cast iron S&S as per IS - 1729
### Details of cost for one no.
### MATERIAL
### 1686 S.C.I. collar 100 mm dia each 1 246
### 9988 Carriage of materials and fixing charges L.S. 13.52 2
### TOTAL
### Add 1 % Water charges on "W"
### TOTAL
### Add GST (multiplying factor 0.1405) on "X"
### TOTAL
### Add 15 % Contractor's profit and overheads on "Y"
### Total
### Add Cess @ 1% on "Z"
### Cost of each
### Say
### 17.57.1.2 Sand cast iron S&S as per IS - 3989
### Details of cost for one no.
### MATERIAL
### 3738 S.C.I. S&S, collars 100 mm each 1 279
### 9988 Carriage of materials and fixing charges L.S. 13.52 2
### TOTAL
### Add 1 % Water charges on "W"
### TOTAL
### Add GST (multiplying factor 0.1405) on "X"
### TOTAL
### Add 15 % Contractor's profit and overheads on "Y"
### Total
### Add Cess @ 1% on "Z"
### Cost of each
### Say
###
###
###
###
###
###
###
### 17.57.2
### 75 mm
### 17.57.2.1 Sand cast iron S&S as per IS - 1729
### Details of cost for one no.
### MATERIAL
### 1685 S.C.I. collar 75 mm dia each 1 177
### 9988 Carriage of materials and fixing charges L.S. 10.79 2
### TOTAL
### Add 1 % Water charges on "W"
### TOTAL
### Add GST (multiplying factor 0.1405) on "X"
### TOTAL
### Add 15 % Contractor's profit and overheads on "Y"
### Total
### Add Cess @ 1% on "Z"
### Cost of each
### Say
### 17.57.2.2 Sand cast iron S&S as per IS - 3989
### Details of cost for one no.
### MATERIAL
### 3739 S.C.I. S&S, collars 75 mm each 1 170
### 9988 Carriage of materials and fixing charges L.S. 10.79 2
### TOTAL
### Add 1 % Water charges on "W"
### TOTAL
### Add GST (multiplying factor 0.1405) on "X"
### TOTAL
### Add 15 % Contractor's profit and overheads on "Y"
### Total
### Add Cess @ 1% on "Z"
### Cost of each
### Say
### 17.57A Providing and fixing shielded coupling for
### 17.57A.1 Hubless
100 centrifugally cast iron pipe
mm dia
###
### 17.57A.1.1 SS 304 grade coupling with EPDM rubber gasket
###
### Detail of cost for one no.
###
###
###
###
###
###
###
### MATERIAL
### 7644 SS 304 grade shielded coupling with EPDM rubber each 1 275
### gasket for 100 mm dia Hubless
### centrifugally cast (spun) iron
### 9977 Carriage of materials and fixing charges L.S. 13.52 2
### TOTAL
### Add 1 % Water charges on "W"
### TOTAL
### Add GST (multiplying factor 0.1405) on "X"
### TOTAL
### Add 15 % Contractor's profit and overheads on "Y"
### Total
### Add Cess @ 1% on "Z"
### Cost of each
### Say
### 17.57A.2 75 mm dia
### 17.57A.2.1 SS 304 grade coupling with EPDM
### rubber
Detail of cost for one no. gasket
### MATERIAL
### 7645 SS 304 grade shielded coupling with EPDM rubber each 1 250
### gasket for 75 mm dia Hubless
### centrifugally cast (spun) iron
### 9977 Carriage of materials and fixing charges L.S. 10.79 2
### TOTAL
### Add 1 % Water charges on "W"
### TOTAL
### Add GST (multiplying factor 0.1405) on "X"
### TOTAL
### Add 15 % Contractor's profit and overheads on "Y"
### Total
### Add Cess @ 1% on "Z"
### Cost of each
### Say
###
### 17.58 Providing lead caulked joints to
### sand cast iron/centrifugally cast (spun) iron
### pipes and fittings of diameter :
###
### 17.58.1 100 mm
###
### Details of cost for one joint
###
### MATERIAL
### 1397 Pig lead kilogram 0.98 176
### 1881 Spun yarn kilogram 0.11 50
### 9999 Kerosene oil, fuel and other sundries L.S. 13.52 2
### 9977 Carriage of materials L.S. 1.43 2
### LABOUR
### 19 Fitter (grade 1) day 0.06 505.17
###
###
###
###
###
###
###
### 20 Assistant Fitter or 2nd class Fitter day 0.06 403.67
### 17 Beldar day 0.12 350.00
### TOTAL
### Add 1 % Water charges on "W"
### TOTAL
### Add GST (multiplying factor 0.1405) on "X"
### TOTAL
### Add 15 % Contractor's profit and overheads on "Y"
### Total
### Add Cess @ 1% on "Z"
### Cost of each joint
### Say
###
### 17.58.2 75 mm
###
### Details of cost for one joint
### MATERIAL
### 1397 Pig lead kilogram 0.88 176
### 1881 Spun yarn kilogram 0.09 50
### 9999 Kerosene oil, fuel and other sundries L.S. 10.79 2
### 9977 Carriage of materials L.S. 1.43 2
### LABOUR
### 19 Fitter (grade 1) day 0.05 505.17
### 20 Assistant Fitter or 2nd class Fitter day 0.05 403.67
### 17 Beldar day 0.09 350.00
### TOTAL
### Add 1 % Water charges on "W"
### TOTAL
### Add GST (multiplying factor 0.1405) on "X"
### TOTAL
### Add 15 % Contractor's profit and overheads on "Y"
### Total
### Add Cess @ 1% on "Z"
### Cost of each
### Say
###
### 17.58.3 50 mm
###
### Details of cost for one joint
### MATERIAL
### 1397 Pig lead kilogram 0.77 176
### 1881 Spun yarn kilogram 0.06 50
### 9999 Kerosene oil, fuel and other sundries L.S. 6.76 2
### 9977 Carriage of materials L.S. 1.43 2
### LABOUR
### 19 Fitter (grade 1) day 0.04 505.17
###
###
###
###
###
###
###
### 20 Assistant Fitter or 2nd class Fitter day 0.05 403.67
### 17 Beldar day 0.05 350.00
### TOTAL
### Add 1 % Water charges on "W"
### TOTAL
### Add GST (multiplying factor 0.1405) on "X"
### TOTAL
### Add 15 % Contractor's profit and overheads on "Y"
### Total
### Add Cess @ 1% on "Z"
### Cost of each
### Say
###
### 17.59 Providing and fixing M.S. stays and
### clamps for sand cast iron/ centrifugally
### cast (spun) iron pipes of diameter :
### 17.59.1 100 mm
### Details of cost for one no.
### MATERIAL
### 1330 Clamps and M.S. stays including bolts and nuts for each 1 67.5
### 100 mm pipe
### 9988 Carriage of materials and fixing charges L.S. 13.52 2
### TOTAL
### Add 1 % Water charges on "W"
### TOTAL
### Add GST (multiplying factor 0.1405) on "X"
### TOTAL
### Add 15 % Contractor's profit and overheads on "Y"
### Total
### Add Cess @ 1% on "Z"
### Cost of each
### Say
###
### 17.59.2 75 mm
###
### Details of cost for one no.
### MATERIAL
### 1335 Clamps and M.S. stays including bolts and nuts for each 1 37
75
### mm pipe
### 9988 Carriage of materials and fixing charges L.S. 10.79 2
### TOTAL
### Add 1 % Water charges on "W"
### TOTAL
### Add GST (multiplying factor 0.1405) on "X"
### TOTAL
### Add 15 % Contractor's profit and overheads on "Y"
###
###
###
###
###
###
### Total
### Add Cess @ 1% on "Z"
### Cost of each
### Say
### 17.59.3 50 mm
### Details of cost for one no.
### MATERIAL
### 1334 Clamps and M.S. stays including bolts and nuts for each 1 35
50
### mm pipe
### 9988 Carriage of materials and fixing charges L.S. 9.49 2
### TOTAL
### Add 1 % Water charges on "W"
### TOTAL
### Add GST (multiplying factor 0.1405) on "X"
### TOTAL
### Add 15 % Contractor's profit and overheads on "Y"
### Total
### Add Cess @ 1% on "Z"
### Cost of each
### Say
###
### 17.60 Providing and fixing trap of self
### cleansing design with screwed down or
### and making good the walls and floors :
### 17.60.1 100 mm inlet and 100 mm outlet
### 17.60.1.1 Sand cast iron S&S as per IS: 3989
### Details of cost for one no.
### MATERIAL
### 7808 Centrifugally cast (spun) iron S&S 100 mm inlet and each 1 450
### 100 mm outlet
### 9999 Cement, sand and grit etc. L.S. 13.52 2
### 9977 Carriage of materials L.S. 2.73 2
### LABOUR
### 23 Mason (brick layer) 1st class day 0.5 505.17
### 17 Beldar day 0.5 350.00
### TOTAL
### Add 1 % Water charges on "W"
### TOTAL
### Add GST (multiplying factor 0.1405) on "X"
### TOTAL
###
###
###
###
###
###
###
###
### Add 15 % Contractor's profit and overheads on "Y"
### Total
### Add Cess @ 1% on "Z"
### Cost of each
### Say
### 17.60.1.2 Sand Cast Iron S&S as per IS: 1729
### Details of cost for one no.
### MATERIAL
### 1897 100 mm S.C.I. trap with 100 mm inlet and each 1 271
### 100 mm outlet
### 9999 Cement, sand and grit etc. L.S. 13.52 2
### 9977 Carriage of materials L.S. 2.73 2
### LABOUR
### 23 Mason (brick layer) 1st class day 0.5 505.17
### 17 Beldar day 0.5 350.00
### TOTAL
### Add 1 % Water charges on "W"
### TOTAL
### Add GST (multiplying factor 0.1405) on "X"
### TOTAL
### Add 15 % Contractor's profit and overheads on "Y"
### Total
### Add Cess @ 1% on "Z"
### Cost of each
### Say
###
### 17.60.1.3 Hubless centrifugally cast (spun) iron
### epoxy coated inside
Detail & outside
of cost as per
for one no.
###
### MATERIAL
### 7642 Hubless centrifugally cast (spun) iron trap with 100 each 1 540
### mm inlet and 100 mm outlet as
### per IS 15905
### 9977 Carriage of materials and fixing charges L.S. 13.52 2
### TOTAL
### Add 1 % Water charges on "W"
### TOTAL
### Add GST (multiplying factor 0.1405) on "X"
### TOTAL
###
###
###
###
###
###
###
### Add 15 % Contractor's profit and overheads on "Y"

###
### Total
###
### Add Cess @ 1% on "Z"
###
### Cost of each
###
### Say
###
### 17.60.2 100 mm inlet and 75 mm outlet
###
### 17.60.2.1 Sand cast iron S&S as per IS - 3989
###
### Details of cost for one no.
###
### MATERIAL
###
### 7809 Centrifugally cast (spun) iron S&S 100 mm inlet and 500
###
### 75 mm
### outlet
9999 Cement, sand and grit etc.
###
### 9977 Carriage of materials 2
###
### LABOUR
###
### 23 Mason (brick layer) 1st class
###
### 17 Beldar
###
### TOTAL
###
### Add 1 % Water charges on "W"
###
### TOTAL
###
### Add GST (multiplying factor 0.1405) on "X"
###
### TOTAL
###
### Add 15 % Contractor's profit and overheads on "Y"
Total
###
### Add Cess @ 1% on "Z" Cost of each
###
### Say
###
### 17.60.2.2 Sand Cast Iron S&S as per IS- 1729
###
### Details of cost for one no.
###
### MATERIAL
###
### 1898 100 mm S.C.I. trap with 100 mm inlet and 75 mm
###
### outlet
### 9999 Cement, sand and grit etc.
###
### 9977 Carriage of materials 2
###
### LABOUR
###
### 23 Mason (brick layer) 1st class
###
### 17 Beldar
###
### TOTAL
###
### Add 1 % Water charges on "W"
###
###
###
### 97.98
###
### 751.15 Z
###
### 7.51
###
### 758.66
###
### 758.65
###
###
###
###
###
###
###
###
### each 1 500
### L.S. 13.52 2
### L.S. 2.73 2
### day 0.5 505.17
### day 0.5 350.00
### 930.92 W
### 9.31
### 940.22 X
### 132.1
### 1072.33 Y
### 160.85
### 1233.17 Z
### 12.33
###
### 1245.51
###
### 1245.5
###
###
###
###
###
### each 1 218
### L.S. 13.52 2
### L.S. 2.73 2
### day 0.5 505.17
### day 0.5 350.00
### 648.92 W
### 6.49
###
###
###
###
###
###
###
###
### TOTAL
### Add GST (multiplying factor 0.1405) on "X" 92.08
### TOTAL
### Add 15 % Contractor's profit and overheads on "Y" 112.12
### Total
### Add Cess @ 1% on "Z" 8.6
### Cost of each 868.21
### Say
###
### 17.60.2.3 Hubless centrifugally cast (spun) iron
### epoxy coated inside & outside as per
### Detail of cost for one no.
###
### MATERIAL
### 7643 Hubless centrifugally cast (spun) iron trap with 100 each 1 385
### mm inlet and 75 mm outlet as per IS 15905
### 9977 Carriage of materials and fixing charges L.S. 13.52 2
### TOTAL
### Add 1 % Water charges on "W"
### TOTAL
### Add GST (multiplying factor 0.1405) on "X"
### TOTAL
### Add 15 % Contractor's profit and overheads on "Y"
### Total
### Add Cess @ 1% on "Z"
### Cost of each
### Say
###
### 17.61 Cutting chases in brick masonry
### walls for following diameter sand cast iron/
### (1 cement : 4 coarse sand) :
### 17.61.1 100 mm dia
### Details of cost for one metre
### MATERIAL
### Cement concrete 1:3:6 (1 cement :
### 3 coarse sand :6 graded stone aggregate )
### 4.2.5 Rate as per item no 4.2.5 of SH : Concrete work cum 0.022 6577.55
###
###
###
###
###
###
###
### 9999 Plastering in cement mortar 1:4 L.S. 10.4 2
### 9977 Carriage of materials L.S. 4.16 2
### LABOUR
### 23 Mason (brick layer) 1st class day 0.14 505.17
### 17 Beldar day 0.27 350.00
### TOTAL
### Add 1 % Water charges on "W-A" 182.38
### TOTAL
### Add GST (multiplying factor 0.1405) on "X-A" 184.21
### TOTAL
### Add 15 % Contractor's profit and overheads on "Y-A" 210.09
### Total
### Add Cess @ 1% on "Z-A" 241.6
### Cost of one metre
### Say
###
### 17.61.2 75 mm dia
###
### Details of cost for one metre
### MATERIAL
### Cement concrete 1:3:6 (1 cement :
### 3 coarse sand :6 graded stone aggregate )
### 4.2.5 Rate as per item no 4.2.5 of SH : Concrete work cum 0.015 6577.55
### 9999 Plastering in cement mortar 1:4 L.S. 7.8 2
### 9977 Carriage of materials L.S. 3.51 2
### LABOUR
### 23 Mason (brick layer) 1st class day 0.1 505.17
### 17 Beldar day 0.2 350.00
### TOTAL
### Add 1 % Water charges on "W-A" 134.39
### TOTAL
### Add GST (multiplying factor 0.1405) on "X-A" 135.73
### TOTAL
### Add 15 % Contractor's profit and overheads on "Y-A" 154.8
### Total
### Add Cess @ 1% on "Z-A" 178.02
### Cost of one metre
### Say
###
###
###
###
###
###
###
###
### 17.61.3 50 mm dia
###
### Details of cost for one metre
### MATERIAL
### Cement concrete 1:3:6 (1 cement :
### 3 coarse sand :6 graded stone aggregate )
### 4.2.5 Rate as per item no 4.2.5 of SH : Concrete work cum 0.008 6577.55
### 9999 Plastering in cement mortar 1:4 L.S. 5.2 2
### 9977 Carriage of materials L.S. 2.73 2
### LABOUR
### 23 Mason (brick layer) 1st class day 0.07 505.17
### 17 Beldar day 0.14 350.00
### TOTAL
### Add 1 % Water charges on "W-A" 94.1
### TOTAL
### Add GST (multiplying factor 0.1405) on "X-A" 95.04
### TOTAL
### Add 15 % Contractor's profit and overheads on "Y-A" 108.39
### Total
### Add Cess @ 1% on "Z-A" 124.65
### Cost of one metre
### Say
###
### 17.62 Painting C.I. cistern with bitumastic
### or any other anti-corrosive
complete for newpaint
work.inside and
### Details of cost for one cistern with fittings
###
### MATERIAL
### 828 Anticorrosive bituminous paint (black) litre 0.23 100
### 4202 Red oxide Zinc chromate primer litre 0.2 110
### 834 Synthetic enamel paint in all shades except black or litre 0.4 160
### chocolate shade
### 9977 Carriage of materials L.S. 1.43 2
### 9999 Sundries L.S. 6.76 2
### LABOUR
### 31 Painter day 0.25 403.67
### 17 Beldar day 0.5 350.00
### TOTAL
###
###
###
###
###
###
###
### Add 1 % Water charges on "W" 3.79
### TOTAL
### Add GST (multiplying factor 0.1405) on "X" 53.84
### TOTAL
### Add 15 % Contractor's profit and overheads on "Y" 65.56
### Total
### Add Cess @ 1% on "Z" 5.03
### Cost of each 507.64
### Say
###
### 17.63 Re-painting C.I. cistern with
### bitumastic or any other anti-corrosive paint
### pan with acid wherever necessary.
### Details of cost for one cistern with fittings
###
### MATERIAL
### 828 Anticorrosive bituminous paint (black) litre 0.23 100
### 834 Synthetic enamel paint in all shades except black or litre 0.2 160
### chocolate shade
### 9999 Polishing of wooden seat and cleaning of W.C. pan L.S. 20.67 2
### with acid
### 9988 Sundries and carriage of materials L.S. 7.15 2
### LABOUR
### 31 Painter day 0.2 403.67
### 17 Beldar day 0.25 350.00
### TOTAL
### Add 1 % Water charges on "W"
### TOTAL
### Add GST (multiplying factor 0.1405) on "X"
### TOTAL
### Add 15 % Contractor's profit and overheads on "Y"
### Total
### Add Cess @ 1% on "Z"
### Cost of each
### Say
###
### 17.64 Repainting C.I. cistern with
### synthetic enamel
etc.paint of approved colour,
complete.
### Details of cost for one cistern with fittings
###
### MATERIAL
### 834 Synthetic enamel paint in all shades except black or litre 0.2 160
### chocolate shade
###
###
###
###
###
###
### 9988 Sundries and carriage of materials L.S. 3.64 2
### LABOUR
### 31 Painter day 0.09 403.67
### 17 Beldar day 0.12 350.00
### TOTAL
### Add 1 % Water charges on "W"
### TOTAL
### Add GST (multiplying factor 0.1405) on "X"
### TOTAL
### Add 15 % Contractor's profit and overheads on "Y"
### Total
### Add Cess @ 1% on "Z"
### Cost of each
### Say
###
### 17.65 Painting sand cast iron/
### centrifugally cast (spun) iron soil, waste
### work :
### 17.65.1 100 mm diameter pipe
### Details of cost for 10 metres
### MATERIAL
### Perimeter = 3.14x110 mm =345.71
### Area 10x0.3457 = 3.46 sqm
### Priming coat
### 13.50.3 Rate as per item no 13.50.3 of SH : Finishing Painting sqm 3.46 33.3
### two coats with paint of any colour such as
### chocolatem grey or buff etc.
### 13.61.1 Rate as per item no 13.61.1 of SH : Finishing sqm 3.46 82.4
### 9999 Add for delay L.S. 17.16 2
### TOTAL
### Add 1 % Water charges on "W-A" 34.32
### TOTAL
### Add GST (multiplying factor 0.1405) on "X-A" 34.66
### TOTAL
### Add 15 % Contractor's profit and overheads on "Y-A" 39.53
### Total
### Add Cess @ 1% on "Z-A" 45.46
### Cost of 10 metres
### Cost of 1 metre
### Say
###
###
###
###
###
###
###
###
### 17.65.2 75 mm diameter pipe
###
### Details of cost for 10 metres
### MATERIAL
### Perimeter = 3.14x82 mm =257.71
### Area 10x0.2577 =2.577 sqm say 2.60 sq. m for outer
### 13.50.3 surface Priming coat sqm 2.6 33.3
### Rate as per item no 13.50.3 of SH : Finishing Painting
### two coats with paint of any colour such as choclate
### grey or buff etc.
### 13.61.1 Rate as per item no 13.61.1 of SH : Finishing sqm 2.6 82.4
### 9999 Add for delay L.S. 15.21 2
### TOTAL
### Add 1 % Water charges on "W-A" 30.42
### TOTAL
### Add GST (multiplying factor 0.1405) on "X-A" 30.72
### TOTAL
### Add 15 % Contractor's profit and overheads on "Y-A" 35.04
### Total
### Add Cess @ 1% on "Z-A" 40.3
### Cost of 10 metres
### Cost of 1 metre
### Say
###
### 17.66 Repainting sand cast iron/
### 17.66.1 as centrifugally castoriron
chocolate, grey buff(spun)
etc : iron, soil,
### 100 mm diameter pipe
### Details of cost for 10 metres
### Painting one coat with paint of any colour such as
### chocolate,grey or buff etc.
### 13.99.1 (Rate as per item no 14.54.1 of S.H. Repair to sqm 3.46 53.85
### Building)
### 9999 Add for delay L.S. 12.22 2
### TOTAL
### Add 1 % Water charges on "W-A" 24.44
### TOTAL
### Add GST (multiplying factor 0.1405) on "X-A" 24.68
### TOTAL
### Add 15 % Contractor's profit and overheads on "Y-A" 28.15
### Total
### Add Cess @ 1% on "Z-A" 32.38
### Cost of 10 metres
### Cost of 1 metre
### Say
### 17.66.2 75 mm diameter pipe
### Details of cost for 10 metres
###
###
###
###
###
###
### Painting one coat with paint of any colour such as
### chocolate,grey or buff etc.
### 13.99.1 (Rate as per item no 14.54.1 of S.H. Repair to sqm 2.58 53.85
### Building)
### 9999 Add for delay L.S. 9.49 2
### TOTAL
### Add 1 % Water charges on "W-A" 18.98
### TOTAL
### Add GST (multiplying factor 0.1405) on "X-A" 19.17
### TOTAL
### Add 15 % Contractor's profit and overheads on "Y-A" 21.86
### Total
### Add Cess @ 1% on "Z-A" 25.14
### Cost of 10 metres
### Cost of 1 metre
### Say
###
### 17.67 Repainting bath tub of size
### 1700x730x430 mm with enamel paint.
### Details of cost for one tub
### MATERIAL
### 830 Enamel paint litre 0.9 165
### 9999 Sundries L.S. 6.76 2
### LABOUR
### 31 Painter day 0.25 403.67
### 18 Coolie day 0.25 350.00
### TOTAL
### Add 1 % Water charges on "W"
### TOTAL
### Add GST (multiplying factor 0.1405) on "X"
### TOTAL
### Add 15 % Contractor's profit and overheads on "Y"
### Total
### Add Cess @ 1% on "Z"
### Cost of each
### Say
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
###
### 17.68 Providing and fixing vitreous china
dual purpose closet suitable for use as
###
### and making good the walls and floors
### wherever required:
### 17.68.1 White vitreous china dual
### purpose WC pan with white solid plastic
### lid with white vitreous china flushing
### cistern and
Details C.P.for
of cost flush bend.
one no.
###
### MATERIAL
### 1875 White plastic seat (solid)with lid C.P.brass hinges each 1 400
and
### rubber buffers
### 1965 White vitreous china dual purpose closet (Anglo each 1 2500
### Indian W.C.) suitable for use as sequatting pan or
### European type water
### closet as per manufacturer's specifications
### 7006 Vitreous china 10 litres low level cistern with fittings each 1 1240
### 9999 20 mm G.I.over flow pipe and specials for over flow L.S. 276.25 2
### pipe
### 1350 Mosquito proof coupling of approved design each 1 30
### 9999 Plugs, screws etc. L.S. 59.15 2
### 9999 Red lead, white lead and gaskin etc. L.S. 71.76 2
### 9999 Cement,sand and grit L.S. 118.43 2
### 9977 Carriage of materials L.S. 118.43 2
### LABOUR
### 19 Fitter (grade 1) day 1 505.17
### 23 Mason (brick layer) 1st class day 1 505.17
### 17 Beldar day 1 350.00
### TOTAL
### Add 1 % Water charges on "W"
### TOTAL
### Add GST (multiplying factor 0.1405) on "X"
### TOTAL
### Add 15 % Contractor's profit and overheads on "Y"
### Total
### Add Cess @ 1% on "Z"
### Cost of each
### Say
###
### 17.69 Providing and fixing PTMT Waste
### Coupling for wash basin and sink, of
### approved quality and colour.
###
### 17.69.1 Waste coupling 31 mm dia of 79
### mm length and 62mm breadth weighing not
### less than 45 gms
###
### Details of cost for one no.
###
### MATERIAL
###
###
###
###
###
###
###
### 7491 PTMT Waste Coupling 31/32MM each 1 34
### 9988 Carriage of materials and fixing charges L.S. 20.28 2
### TOTAL
### Add 1 % Water charges on "W"
### TOTAL
### Add GST (multiplying factor 0.1405) on "X"
### TOTAL
### Add 15 % Contractor's profit and overheads on "Y"
### Total
### Add Cess @ 1% on "Z"
### Cost of each
### Say
###
### 17.69.2 Waste coupling 38 mm dia of 83
### mm length and 77mm breadth, weighing
### less than 60 gms
###
### Details of cost for one no.
###
### MATERIAL
### 7492 PTMT Waste Coupling 38/40MM each 1 48
### 9988 Carriage of materials and fixing charges L.S. 20.28 2
### TOTAL
### Add 1 % Water charges on "W"
### TOTAL
### Add GST (multiplying factor 0.1405) on "X"
### TOTAL
### Add 15 % Contractor's profit and overheads on "Y"
### Total
### Add Cess @ 1% on "Z"
### Cost of each
### Say
###
### 17.70 Providing and fixing PTMT Bottle
Trap for Wash basin and sink.
###
### Bottle trap 31mm single piece
17.70.1
### moulded with height of 270 mm, effective
### Details of cost for one no.
### MATERIAL
### 7493 PTMT Bottle Trap 31/32MM each 1 210
### 9988 Carriage of materials and fixing charges L.S. 20.28 2
### TOTAL
### Add 1 % Water charges on "W"
### TOTAL
###
###
###
###
###
###
###
### Add GST (multiplying factor 0.1405) on "X" 35.56
### TOTAL
### Add 15 % Contractor's profit and overheads on "Y" 43.29
### Total
### Add Cess @ 1% on "Z" 3.32
### Cost of each 335.23
### Say
###
### Bottle trap 38 mm single piece
17.70.2
### moulded with height of 270 mm, effective
### Details of cost for one no.
### MATERIAL
### 7494 PTMT Bottle Trap 38/40MM each 1 220
### 9988 Carriage of materials and fixing charges L.S. 20.28 2
### TOTAL
### Add 1 % Water charges on "W"
### TOTAL
### Add GST (multiplying factor 0.1405) on "X"
### TOTAL
### Add 15 % Contractor's profit and overheads on "Y"
### Total
### Add Cess @ 1% on "Z"
### Cost of each
### Say
###
### 17.71 Providing and fixing PTMT liquid
### soap containerthan
109 105
mm gms.
wide, 125 mm high
### Details of cost for one no.
###
### MATERIAL
### 7503 PTMT Liquid Soap Container of 400ml capacity each 1 105
### 9988 Carriage of materials and fixing charges L.S. 6.76 2
### TOTAL
### Add 1 % Water charges on "W"
### TOTAL
### Add GST (multiplying factor 0.1405) on "X"
### TOTAL
### Add 15 % Contractor's profit and overheads on "Y"
###
###
###
###
###
###
###
###
### Total
### Add Cess @ 1% on "Z" 1.57
### Cost of each 158.57
### Say
###
### 17.72 Providing and fixing PTMT towel
### ring trapezoidal shape 215 mm long, 200
### MATERIAL
### 7504 PTMT - Towel Ring 215x200x37mm each 1 130
### 9988 Carriage of materials and fixing charges L.S. 20.28 2
### TOTAL
### Add 1 % Water charges on "W"
### TOTAL
### Add GST (multiplying factor 0.1405) on "X"
### TOTAL
### Add 15 % Contractor's profit and overheads on "Y"
### Total
### Add Cess @ 1% on "Z"
### Cost of each
### Say
###
### 17.73 Providing and fixing PTMT towel rail
### complete with brackets fixed to wooden
### quality and colour.
###
### 17.73.1 450 mm long towel rail with total
### length of 495 mm, 78 mm wide and
### Details of cost for one no.
### MATERIAL
### 7505 PTMT Towel Rail (450mm) Wooden cleates each 1 135
### 8.23 Rate as per item no 9.32 of SH : Wood and each 2 25.4
### PVC work
### 588 Chromium plated Brass screws 25 mm 100 Nos 0.06 180
### 9977 Carriage of materials L.S. 4.16 2
### LABOUR
### 15 Carpenter 2nd class day 0.17 403.67
### 17 Beldar day 0.17 350.00
### TOTAL
### Add 1 % Water charges on "W-A" 272.33
### TOTAL
###
###
###
###
###
###
###
### Code Description Unit Quantity Rate
### Add GST (multiplying factor 0.1405) on "X" 275.05
### TOTAL
### Add 15 % Contractor's profit and overheads on "Y" 313.69
### Total
### Add Cess @ 1% on "Z" 360.75
### Cost of each
### Say
###
### 17.73.2 600 mm long towel rail with total
### length of 645 mm, width 78 mm and
### height of 88 mm, weighing not less than
### 190 gms.
Details of cost for one no.
###
### MATERIAL
### 7506 PTMT Towel Rail (600mm) Wooden cleates each 1 165
### 8.23 Rate as per item no 9.32 of SH : Wood and each 2 25.4
### PVC work
### 588 Chromium plated Brass screws 25 mm 100 Nos 0.06 180
### 9977 Carriage of materials L.S. 4.16 2
### LABOUR
### 15 Carpenter 2nd class day 0.17 403.67
### 17 Beldar day 0.17 350.00
### TOTAL
### Add 1 % Water charges on "W-A" 302.33
### TOTAL
### Add GST (multiplying factor 0.1405) on "X" 305.35
### TOTAL 348.25
### Add 15 % Contractor's profit and overheads on "Y"
### Total 400.49
### Add Cess @ 1% on "Z"
### Cost of each
### Say
###
### 17.74 Providing and fixing PTMT shelf 440
### mm long, 124 mm width and 36 mm
### height of approved quality and colour,
### weighing not less than 300 gms.
### Details of cost for one no.
### MATERIAL
### 7507 PTMT Shelf 450x124x36mm Wooden cleates each 1 200
### 8.23 Rate as per item no 9.32 of SH : Wood and each 2 25.4
### PVC work
### 588 Chromium plated Brass screws 25 mm 100 Nos 0.06 180
### 9977 Carriage of materials L.S. 4.16 2
### LABOUR
### 15 Carpenter 2nd class day 0.17 403.67
### 17 Beldar day 0.17 350.00
### TOTAL
### Add 1 % Water charges on "W-A" 337.33
### TOTAL
### Add GST (multiplying factor 0.1405) on "X-A" 340.7
### TOTAL
###
###
###
###
###
###
### Add 15 % Contractor's profit and overheads on "Y-A" 388.57
### Total
### Add Cess @ 1% on "Z-A" 446.85
### Cost of each
### Say
###
### 17.75 Providing and fixing PTMT 15 mm
### Urinal spreader size 95x69x100 mm with
### 1/2" BSP thread and shapes, weighing not
### less than 60 gms.
### Details of cost for one no.
### MATERIAL
### 7508 PTMT Urinal Spreader 15mm each 1 76
### 9988 Carriage of materials and fixing charges L.S. 6.76 2
### TOTAL
### Add 1 % Water charges on "W"
### TOTAL
### Add GST (multiplying factor 0.1405) on "X"
### TOTAL
### Add 15 % Contractor's profit and overheads on "Y"
### Total
### Add Cess @ 1% on "Z"
### Cost of each
### Say
###
### 17.76 Providing and fixing PTMT urinal
### cock of approved quality and colour.
### 17.76.1 15 mm nominal bore, 80 mm long,
### 42 mm high and 30mm wide with BSP
### Details of cost for 1 no.
### MATERIAL
### 7858 P.T.M.T. Urinal cock 15mm dia each 1 106.5
### 9988 Carriage of materials and fixing charges L.S. 8.06 2
### TOTAL
### Add 1 % Water charges on "W"
### TOTAL
### Add GST (multiplying factor 0.1405) on "X"
### TOTAL
### Add 15 % Contractor's profit and overheads on "Y"
### Total
### Add Cess @ 1% on "Z"
###
###
###
###
###
###
###
### Code Description Unit Quantity Rate
### Cost of each
### Say
###
### 17.77 Providing and fixing M.S. holder bat
### clamp of approved design to sand cast
### shall be fixed with M.S. nuts, bolts, &
### washers of size 25x6 mm, one bolts on
### 17.77.1 Total bracket length 580 mm of
### approved shape and design (for single 100
### Details of cost for 5 nos.
### MATERIAL
### M.S. flats 50x5mm 5 x 0.58 = 2.90m @ 1.97 kg/
### metre = 5.71 kg.
### M.S. flats 30x1.6mm 5x0.42 = 2.10m.
### 0.38kg/metre = 0.80kg. Total = 6.51kg.
### Add wastage 5% = 0.33kg.
### Total = 6.86 kg.= 0.0686 quintal
### 1007 Structurals such as tees,angles channels and R.S. quintal 0.0686 5300
### joists
### 2205 Carriage of Steel tonne 0.00686 94.34
### LABOUR
### 19 Fitter (grade 1) day 0.033 505.17
### 13 Blacksmith 2nd class day 0.049 403.67
### 17 Beldar priming coat 5x0.58x0.11 = 0.32 Day 0.065 350.00
### 5x0.42x0.063 = 0.13
### Total=0.45sqm
### 13.50.1 Rate as per item no 13.50.1 of SH : Finishing sqm 0.45 38.95
### 9999 Sundries L.S. 1.35 2
### P/F expansion hold fasteners 6mm threaded dia 5x4
### Nos = 20 nos.
### 8.8.1.1 "Rate asper item no. 8.8.1.1 of each 20 27.45
### SH :- Marble work
### Total
### Add 1 % Water charges on "W-A" 373.82
### TOTAL
### Add GST (multiplying factor 0.1405) on "X-A" 377.56
### TOTAL
### Add 15 % Contractor's profit and overheads on "Y-A" 430.6
### Total
### Add Cess @ 1% on "Z-A" 495.2
### Cost of 5 Nos.
###
###
###
###
###
###
###
### Cost of each 213.35
### Say
###
### 17.77.2 Total bracket length 810 mm of
approved shape and design (for two 100
###
### Details of cost for 5 nos.
###
### MATERIAL
### M.S. flats 50x5mm 5 x 0.81 = 4.05m @ 1.97 kg/
### metre = 7.98 kg.
### M.S. flats 30x1.6mm 5x2x0.42 = 4.20m.
### 0.38kg/metre = 1.60kg. Total = 9.58kg.
### Add wastage 5% = 0.48kg.
### Total = 10.06 kg.
### M.S.flats 10.06kg. = 0.1006 quintal
### 1007 Structurals such as tees,angles channels and R.S. quintal 0.1006 5300
### joists
### 2205 Carriage of Steel tonne 0.01006 94.34
### LABOUR
### 19 Fitter (grade 1) day 0.048 505.17
### 13 Blacksmith 2nd class day 0.072 403.67
### 17 Beldar priming coat day 0.096 350.00
### 5x0.81x0.11 = 0.45
### 5x2x0.42x0.063 = 0.26
### Total =0.71sqm
### 13.50.1 Rate as per item no 13.50.1 of SH : Finishing sqm 0.71 38.95
### 9999 Sundries L.S. 1.98 2
### P/F expansion hold fasteners 6mm threaded dia 5x4
### Nos = 20 nos.
### 8.8.1.1 "Rate asper item no. 8.8.1.1 of each 20 27.45
### SH :- Marble work
### Total
### Add 1 % Water charges on "W-A" 548.28
### TOTAL
### Add GST (multiplying factor 0.1405) on "X-A" 553.76
### TOTAL
### Add 15 % Contractor's profit and overheads on "Y-A" 631.57
### Total
### Add Cess @ 1% on "Z-A" 726.3
### Cost of 5 Nos.
### Cost of each
### Say
###
###
###
###
###
###
###
###
###
###
###
### 17.77.3 Total bracket length 1040 mm of
### approved shape and design (for three 100
### dia pipes)
###
### Details of cost for 5 nos.
###
### MATERIAL
### M.S. flats 50x5mm 5 x 1.04= 5.20m @ 1.97 kg/ metre
### = 10.24 kg.
### M.S. flats 30x1.6mm 5x3x0.42 = 6.30m.
### 0.38kg/metre = 2.39kg. Total = 12.63kg.
### Add wastage 5% = 0.63kg.
### Total = 13.26 kg.
### M.S.flats 13.26kg. = 0.1326 quintal
### 1007 Structurals such as tees,angles channels and R.S. quintal 0.1326 5300
### joists
### 2205 Carriage of Steel tonne 0.01326 94.34
### LABOUR
### 19 Fitter (grade 1) day 0.063 505.17
### 13 Blacksmith 2nd class day 0.095 403.67
### 17 Beldar priming coat day 0.126 350.00
### 5x1.04x0.11 = 0.57
### 5x3x0.42x0.063 = 0.40
### Total=0.97sqm
### 13.50.1 Rate as per item no 13.50.1 of SH : Finishing sqm 0.97 38.95
### 9999 Sundries L.S. 2.6 2
### P/F expansion hold fasteners 6mm threaded dia 5x4
### Nos = 20 nos.
### 8.8.1.1 Rate asper item no. 8.8.1.1 of SH :- Marble work each 20 27.45
### Total
### Add 1 % Water charges on "W-A" 722.4
### TOTAL
### Add GST (multiplying factor 0.1405) on "X-A" 729.63
### TOTAL
### Add 15 % Contractor's profit and overheads on "Y-A" 832.14
### Total
### Add Cess @ 1% on "Z-A" 956.96
### Cost of 5 Nos.
### Cost of each
### Say
###
### 17.78 Providing and fixing white vitreous
### china extended wall mounting water closet
### bolts and gasket etc complete.
###
### Details of cost for one pan
###
### MATERIAL
###
###
###
###
###
###
###
###
### 7072 Wall mounted water closet each 1 6000
### 7073 Adjustable Vetrious China Cistern with fittings each 1 1900
### 1875 White plastic seat (solid)with lid C.P.brass hinges each 1 400
and
### rubber buffers
### 9977 Carriage of materials L.S. 9.79 2
### LABOUR
### 19 Fitter (grade 1) day 1 505.17
### 23 Mason (brick layer) 1st class day 1 505.17
### 17 Beldar day 1 350.00
### TOTAL
### Add 1 % Water charges on "W"
### TOTAL
### Add GST (multiplying factor 0.1405) on "X"
### TOTAL
### Add 15 % Contractor's profit and overheads on "Y"
### Total
### Add Cess @ 1% on "Z"
### Cost of each
### Say
###
### 17.79 Providing & fixing white vitreous
### china water less urinal of size 600 x 330 x
### having debris catcher and hygiene seal.
###
### Details of cost for one pan
###
### MATERIAL
### 7074 White Vetrious China Waterless Urinal each 1 9650
### 7075 Cistern with fittings for Waterless Urinal each 1 2290
### 9977 Carriage of materials L.S. 9.79 2
### LABOUR
### 19 Fitter (grade 1) day 0.5 505.17
### 17 Beldar day 0.5 350.00
### TOTAL
### Add 1 % Water charges on "W"
### TOTAL
### Add GST (multiplying factor 0.1405) on "X"
### TOTAL
### Add 15 % Contractor's profit and overheads on "Y"
### Total
### Add Cess @ 1% on "Z"
### Cost of each
###
###
###
###
###
###
### Say
###
### 17.80 Providing and fixing white vitreous
### china battery
specification andbased infrared
direction sensor
of Engineer-in-
### Details of cost for one charge.
pan
### MATERIAL
### 7076 White Vetrious Urinal each 1 4500
### 9977 Carriage of materials L.S. 9.79 2
### LABOUR
### 19 Fitter (grade 1) day 0.5 505.17
### 17 Beldar day 0.5 350.00
### TOTAL
### Add 1 % Water charges on "W"
### TOTAL
### Add GST (multiplying factor 0.1405) on "X"
### TOTAL
### Add 15 % Contractor's profit and overheads on "Y"
### Total
### Add Cess @ 1% on "Z"
### Cost of each
### Say
###
###
### 17.81 Providing and fixing floor mounted,
### white vitreous china single piece, double
### Charge.
###
### Details of cost for 1 no.
###
### MATERIAL
### Floor mounted, white vitreous china single piece,
### double traps syphonic water closet of approved
### brand/make, shape, size and pattern including
### integrated white vitreous china cistern of capacity 10
### litres with dual
### 1966 flushing system including all fittings and fixtures each 1 9500
with
### seat cover, cistern fittings, nuts, bolts and gasket
etc.
###
###
###
###
###
###
###
### 9977 Carriage of material L.S. 9.79 2
### LABOUR
### 19 Fitter (grade 1) day 1 505.17
### 17 Beldar day 1 350.00
### 23 Mason (brick layer) 1st class day 1 505.17
### TOTAL
### Add 1 % Water charges on "W"
### TOTAL
### Add GST (multiplying factor 0.1405) on "X"
### TOTAL
### Add 15 % Contractor's profit and overheads on "Y"
### Total
### Add Cess @ 1% on "Z"
### Cost of each
### Say
###
###
1423
Code Description Unit Quantity Rate

ROAD WORK
SUB HEAD : 16.0
Amount

630.00
6300.00
94.50
162.00
18.90
13.52

162.00
0.00
18.90
13.52
7413.34 W
74.1334
7487.47 X
1051.99
8539.46 Y
1280.92
9820.38 Z
98.20
9918.58
99.19
99.20 91.3
59.50

24.00
0.00
2.80
2.86
89.16 W
0.8916
90.05 X
12.65
102.70 Y
15.41
118.11 Z
1.18
119.29
11.93
11.90

135.00
877.50

175.00

0.00
115.36

1302.86 W
13.0286
1315.89 X
184.88
1500.77 Y
225.12
1725.89 Z
17.26
1743.15
1743.15
1743.20 1843.5
135.00
455.00

182.50

0.00
115.36

887.86 W
8.8786
896.74 X
125.99
1022.73 Y
153.41
1176.14 Z
11.76
1187.90
1187.9
1187.90

35.00
219.00

474.50

0.00
115.36

843.86 W
8.4386
852.30 X
119.75
972.05 Y
145.81
1117.86 Z
11.18
1129.04
1129.04
1129.00 1753.2

500.00
0.00
115.36
615.36 W
6.1536
621.51 X
87.32
708.83 Y
106.33
815.16 Z
8.15
823.31
823.31
823.30

480.00
0.00
115.36
595.36 W
5.9536
601.31 X
84.48
685.79 Y
102.87
788.66 Z
7.89
796.55
796.55
796.60 796.55
57.50
0.00
920.00
0.00
210.00
0.00
106.13

1293.63 W
12.9363
1306.57 X
183.57
1490.14 Y
223.52
1713.66 Z
17.14
1730.80
1730.8
1730.80

115.00
0.00
1050.00
0.00
210.00
0.00
90.21
0.00
15.92
1481.13 W
14.8113
1495.94 X
210.18
1706.12 Y
255.92
1962.04 Z
19.62
1981.66
198.17
198.20 1981.65
1000.00
106.13
1106.13 W
11.0613
1117.19 X
156.97
1274.16 Y
191.12
1465.28 Z
14.65
1479.93
1479.93
1479.90

61.95
58.45
40.00
132.66

293.06 W
2.9306
295.99 X
41.59
337.58 Y
50.64
388.22 Z
3.88
392.10
392.1
392.10 378.65

0.00

500.00
106.13
606.13 W
6.0613
612.19 X
86.01
698.20 Y
104.73
802.93 Z
8.03
810.96
810.96
811.00

91.00
91.00
91.00

99.00
0.00
11.55
5.46
389.01 W
3.8901
392.90 X
55.20
448.10 Y
67.22
515.32 Z
5.15
520.47
520.47
520.50 488.75

0.00

122.50
91.00
63.00

12.00
0.00
1.40
5.46
295.36 W
2.9536
298.31 X
41.91
340.22 Y
51.03
391.25 Z
3.91
395.16
395.16
395.20

122.50
91.00
63.00

12.00
0.00
1.40
5.46
295.36 W
2.9536
298.31 X
41.91
340.22 Y
51.03
391.25 Z
3.91
395.16
395.16
395.20

0.00

600.00
63.68

189.00
189.00

162.00
0.00
18.90
622.58 W
6.2258
628.81 X
88.35
717.16 Y
107.57
824.73 Z
8.25
832.98
83.3
83.30

0.00

800.00

0.00
45.28
85.88
68.62
122.50
35.88
17.94
376.10 W
3.761
379.86 X
53.37
433.23 Y
64.98
498.21 Z
4.98
503.19
50.32
50.30

0.00

245.00

0.00
13.87

20.21
16.15
31.50
8.32
335.05 W
3.3505
338.40 X
47.55
385.95 Y
57.89
443.84 Z
4.44
448.28
44.83
44.80

472.50
378.00

396.00
0.00
46.20
10.92

453.12 W
4.5312
457.65 X
64.30
521.95 Y
78.29
600.24 Z
6.00
606.24
60.62
60.60
982.88

0.00
4875.00
0.00
865.19
0.00
0.00
1775.94 A
0.00
0.00
0.00
973.14
0.00
0.00
0.00
0.00
682.50
920.50
472.50
405.00
0.00
47.25
40.30
0.00
0.00
0.00

0.00
0.00
0.00
162.00
0.00
18.90
12042.63 W
83.11
12125.74 X
1179.32
13305.06 Y
1435.96

14741.02 Z
110.09
14851.11
148.51
148.5

1350.00
476.42

545.58
435.96
752.50
563.50
13.52
4137.48 W
41.3748
4178.85 X
587.13
4765.98 Y
714.90
5480.88 Z
54.81
5535.69
553.57
553.60

5304.64
530.46
530.45
3225.00

182.54

202.07
161.47
378.00
4149.08 W
41.4908
4190.57 X
588.78
4779.35 Y
716.90
5496.25 Z
54.96
5551.21
555.12
555.10

0.00

0.00
157.79

34.04 A
17.84 A
0.00
105.80
0.00
9.76
0.00
281.75
1.17

0.00
336.00
168.00

84.00
84.00

0.00
248.50
168.00
35.00

0.00
168.00
168.00
80.86
2026.87 W
18.17
2045.05 X
257.87
2302.92 Y
313.99

2616.9 Z
24.07
2640.98
2445.35
2445.35
0.00
0.00
157.79 A

34.04 A

17.84 A

0.00
168.00
84.00

84.00
84.00

0.00
168.00
168.00
35.00
107.64
1042.38 W
8.33
1050.71 X
118.17
1168.88 Y
143.88

1312.76 Z
11.03
1323.79
1470.88
1470.9
0.00
123.50
0.00
21.92

88.80 A

48.66 A

0.00
560.00
280.00
1052.86 W
9.15
1062.02 X
129.9
1191.92 Y
158.17

1350.09 Z
12.13
1362.22
136.22
136.2
0.00

2142.44

0.00
11.90
23.45
6.57
5.25
4.55

2087.44
1512.99

0.00
247.00
4.72
59.50
7.43

17.50
7.00
258.35
280.00
94.50
3.90

26.52

23.14
107.64
24.44
27.04

6930.74 W

6942.62 X

7111.19 Y

7316.44 Z
15.74
7332.18
21821.95
21821.95
11610.00
19.72

11629.72 W
116.2972
11746.02 X
1650.32
13396.34 Y
2009.45
15405.79 Z
154.06
15559.85
1555.98
1556.00

74.36
74.35

25.00
80.00
5.46

0.00
40.37
150.83 W
1.5083
152.34 X
21.40
173.74 Y
26.06
199.80 Z
2.00
201.80
20.18
20.20

0.00

1705.00
2.83
98.80

0.00
60.62
48.44
175.00
252.59
201.84
27.04
867.16 W
8.6716
875.83 X
123.05
998.88 Y
149.83
1148.71 Z
11.49
1160.20
116.02
116.00

0.00

1705.00
2.92

1979.00 A
0.00
98.80
0.00
0.00
60.62
48.44
175.00
252.59
201.84
4473.49 W
24.94
4498.44 X
353.97
4852.41 Y
431.01
5283.42 Z
33.04
5316.46
15.95
15.95

5565.00
0.00
9.91

302.75
175.00

0.00

0.00
403.67
350.00
39.52
793.19 W
7.9319
801.12 X
112.56
913.68 Y
137.05
1050.73 Z
10.51
1061.24
106.12
106.10
0.00
57.12
48.44
175.00
252.59
201.84
107.64
107.64

417.12 W
4.1712
421.29 X
59.19
480.48 Y
72.07
552.55 Z
5.53
558.08
55.81
55.80
0.00

191.96
13.52
1433.25 W
14.332524
1447.58 X
203.39
1650.97 Y
247.65
1898.62 Z
18.99
1917.61
191.76
191.80

80.00

42.00
8.32

50.32 W
0.5032
50.82 X
7.14
57.96 Y
8.69
66.65 Z
0.67
67.32
6.73
6.70
127.53 A

0.70
1.40
0.40
0.32
0.28

99.53 A

108.23 A

7.88
0.17
32.73
4.09

0.95
0.07
0.20
0.10

10.50
13.30
16.10
1.36
1.20
42.00
8.32
473.24 W
1.38
474.62 X
19.58
494.2 Y
23.84

518.04 Z
1.83
519.86

0.00

519.85

0.00
637.63

0.00
3.50
7.00
2.02
1.61
1.40

362.67

235.93

266.76
5.09
9.35
1.17

2.80
0.25
0.06
0.26

30.28
38.85
47.60
3.90
3.64
70.00
27.04
1742.68 W
5.06
1747.74 X
71.86
1819.61 Y
87.5

1907.11 Z
6.71
1913.82
1913.8
1211.50

0.00
6.65
13.30
4.04
3.23
2.80

688.40

372.29

393.75
8.49
170.00
21.23
4.55
0.35
1.04
0.52

50.86
64.75
79.45
6.76
5.72
70.00
27.04
3243.32 W
9.71
3253.03 X
137.8
3390.83 Y
167.79

3558.62 Z
12.86
3571.48
3571.5
0.00

382.58 A

0.00
2.10
4.20
1.21
0.97
0.84
217.15

175.32

183.75
3.96
7.65
0.96

2.10
0.21
0.52
0.26

23.41
30.10
36.75
3.12
2.60
35.00
27.04
1154.89 W
3.8
1158.69 X
53.9
1212.59 Y
65.63

1278.22 Z
5.03
1283.25
1283.25

0.00
5763.15
23.88
0.00
0.00
1897.50
0.00
175.11

198.00
5.46

0.00
38.50
490.00
490.00

40.41
38.50

325.50

38.50
325.50
542.50

94.50
38.50
330.00

96.00
0.00
33.00
2.20
6.40
13.52
13.52
627.64 W
6.2764
633.92 X
89.07
722.99 Y
108.45
831.44 Z
8.31
839.75
83.97
84.00
8640.00
19.10

1725.00
0.00
159.20
0.00
0.00
0.00
158.40
4.37
0.00
0.00
0.00
38.50
490.00
490.00
0.00
40.41
38.50
483.00
0.00
94.50
297.50
297.50
0.00
38.50
38.50
330.00

96.00
0.00
33.00
2.20
6.40
13.52
32.76
0.00
0.00
0.00
0.00
5280.00
1150.00
0.00
11.67
584.88

0.00
96.80
2.67

21.00
339.50

25.26
24.50
262.50

24.50
217.00
217.00

52.50
21.00
180.00
0.00
21.00
48.00
0.60

1.80
18.98
343.88 W
3.4388
347.32 X
48.80
396.12 Y
59.42
455.54 Z
4.56
460.10
46.01
46.00

9360.00
1725.00

20.70
877.32

0.00
171.60
4.73

21.00
171.50
339.50

25.26
21.00
241.50

231.00
178.50
178.50

52.50
21.00
180.00
0.00
18.00
48.00

1.00

2.40
5.46
10.66
19.52 W
0.1952
19.72 X
2.77
22.49 Y
3.37
25.86 Z
0.26
26.12
2.61
2.60

9750.00
20.70
1725.00

877.32

38.50
490.00
490.00

35.36
35.00

350.00

38.50
297.50
297.50

94.50
94.50
330.00
0.00
30.00

2.20

6.40
13.52
18.98
590.10 W
5.901
596.00 X
83.74
679.74 Y
101.96
781.70 Z
7.82
789.52
78.95
79.00

0.00
3672.08
12.95
0.00
0.00
1265.00
0.00
116.74
0.00
0.00
0.00
0.00
21.00
171.50
339.50
0.00
25.26
21.00
220.50
0.00
24.50
217.00
217.00
0.00
52.50
52.50
180.00
0.00
18.00

2.20

6.40
5.46
10.66
327.72 W
3.2772
331.00 X
46.51
377.51 Y
56.63
434.14 Z
4.34
438.48
43.85
43.90

8661.97 Z

1800.00
7.96
66.00
1.82

1.00

2.40
15.60
9.00
18.20

21.00
511.00

66.50

164.50
805.80 W
8.058
813.86 X
114.35
928.21 Y
139.23
1067.44 Z
10.67
1078.11
107.81
107.80

34.73
3507.25
35.07
35.05
0.00

1200.00
5.31
44.00
1.21

1.00

2.40
15.60
9.00
15.60

21.00
511.00

66.50

164.50
803.20 W
8.032
811.23 X
113.98
925.21 Y
138.78
1063.99 Z
10.64
1074.63
107.46
107.50

26.65

26600.00
0.00
148.58
0.00
980.00
0.00
560.00
1600.00
28.00
700.00
4016.58 W
40.1658
4056.75 X
569.97
4626.72 Y
694.01
5320.73 Z
53.21
5373.94
537.39
537.40

16625.00
0.00
92.86

980.00

560.00
1600.00

28.00
700.00
2888.00 W
28.88
2916.88 X
409.82
3326.70 Y
499.01
3825.71 Z
38.26
3863.97
386.4
386.40

39072.60
0.00
148.58
0.00
980.00
0.00
560.00
1600.00

28.00
700.00
4016.58 W
40.1658
4056.75 X
569.97
4626.72 Y
694.01
5320.73 Z
53.21
5373.94
537.39
537.40
49564.75 Y
7434.71
56999.47 Z
569.99
57569.46
16.45
16.45

24420.38
0.00
92.86
0.00
980.00
0.00
560.00
1600.00

28.00
700.00
3960.86 W
39.6086
4000.47 X
562.07
4562.54 Y
684.38
5246.92 Z
52.47
5299.39
529.94
529.90

3456.00
15.28
252.00
0.00
1.06
2070.00

1035.00

1579.18

126.72
3.49

28.00
490.00
490.00

199.50

0.00
95.98
1750.00

94.50

38.50
330.00

104.00

140.00
0.00
2.20

6.40
13.52
18.98
615.10 W
6.151
621.25 X
87.29
708.54 Y
106.28
814.82 Z
8.15
822.97
82.3
82.30

5698.08
15.28
2070.00

1035.00
1579.18

126.72
3.49

28.00
490.00
490.00

199.50

0.00
95.98
1750.00
0.00
94.50
38.50
330.00

104.00

140.00
0.00
2.20

6.40
13.52
18.98
615.10 W
6.151
621.25 X
87.29
708.54 Y
106.28
814.82 Z
8.15
822.97
82.3
82.30
17090.28
170.9
170.9

4319.28
0.00
15.28
0.00
252.00
#VALUE!
1.06
0.00
0.00
2070.00

1035.00

1579.18

126.72
3.49
28.00
490.00
490.00

199.50

0.00
95.98
1750.00
0.00
94.50
38.50
330.00

104.00

140.00
0.00
2.20

6.40
13.52
18.98
615.10 W
6.151
621.25 X
87.29
708.54 Y
106.28
814.82 Z
8.15
822.97
82.3
82.30
4320.00
0.00
315.00
0.00
19.10
1.34
2587.50

1288.00

1971.05

158.40
4.37

28.00
490.00
490.00
0
248.50

0.00
95.98
2187.50
0.00
94.50
38.50
330.00

120.00

140.00
0.00
2.20

6.40
13.52
18.98
38.90 W
0.389
39.29 X
5.52
44.81 Y
6.72
51.53 Z
0.52
52.05
5.2
5.20
7122.60
19.10
2587.50

1288.00

1971.05

158.40
4.37

28.00

490.00
490.00

248.50

0.00
95.98
2187.50
0.00
0.00
94.50
38.50
330.00

120.00
140.00
0.00
2.20

6.40
13.52
18.98
631.10 W
6.311
637.41 X
89.56
726.97 Y
109.05
836.02 Z
8.36
844.38
84.44
84.40

5399.10

315.00
19.10
#VALUE! 1.34
2587.50

1288.00

1971.05

158.40
4.37

28.00
490.00
490.00

248.50

0.00
95.98
2187.50
0.00
94.50
38.50
330.00 330

120.00

140.00
0.00
2.20
6.40
13.52
18.98
38.90 W
0.389
39.29 X
5.52
44.81 Y
6.72
51.53 Z
0.52
52.05
5.2
5.20

6419.07
0.00
24.41
2760.00

1403.71

0.00
95.98
1239.00
0.00
94.50
38.50
330.00

140.00
18.98
158.98 W
1.5898
160.57 X
22.56
183.13 Y
27.47
210.60 Z
2.11
212.71
21.27
21.30

8037.79
0.00
30.57
3450.00

1754.64

0.00
95.98
1435.00

94.50
38.50
330.00
0.00
18.98
2012.96 W
20.1296
2033.09 X
285.65
2318.74 Y
347.81
2666.55 Z
26.67
2693.22
269.32
269.30

15796.63 Y

18166.13 Z

7292.70
7718.30

1441.80

0.00
660.00
1840.70
0.00
3591.00
0.00
616.00
1152.45
0.00
7077.05
0.00
471.22
0.00
123.11

44400.00
0.00
196.34
5834.50

1865.50
934.50
465.50

234.50
465.50

2334.50

234.50
619.50

360.00
0.00
1830.00
0.00
702.00

6080.50 W
60.805
6141.31 X
862.85
7004.16 Y
1050.62
8054.78 Z
80.55
8135.33
813.53
813.50
934.42

5913.00
11518.20

3499.20

1558.00

0.00
3469.50
656.10
0.00
0.00
48960.00
14230.13
0.00
216.51

8750.00

2800.00
1400.00
700.00
350.00
700.00

3500.00

350.00
927.50

400.00

2250.00

858.00

8285.50 W
82.855
8368.36 X
1175.75
9544.11 Y
1431.62
10975.72 Z
109.76
11085.48
1108.55
1108.60

152340.42 Z

0.00
0.00
3468.00

10.83

15.80
0.00
272.70

91.30

0.00
196.62

7.29

15.90
0.00
0.03
135.11

8.81
18.47

525.00
252.59
1225.00
87.50
175.00
375.00
306.54

2973.91 W
29.7391
3003.65 X
422.01
3425.66 Y
513.85
3939.51 Z
39.40
3978.91
397.89
397.90
0.00

0.00
3468.00
0.00
10.83

15.80
0.00
272.70
91.30

196.62

7.29

15.90
0.00
0.03
135.11

8.81
18.47

525.00
252.59
1225.00
87.50
175.00
375.00
306.54
6904.93 W

69.05
6973.98 X
979.84
7953.82 Y
1193.07
9146.9 Z
91.47
9238.37
849.51
849.5

0.00

7272.00
0.00
530.25
0.00
32.16
2.25
1138.50
0.00
759.00
0.00
175.11
0.00
266.64
7.35
1320.00
965.05

56.00
490.00
490.00
416.50

0.00
121.24
2142.00
0.00
119.00
0.00
45.50
390.00

168.00

175.00

2.60
8.00
14.30
17.94
16921.67 W
169.22
17090.89 X
2401.27
19492.16 Y
2923.82
22415.98 Z
224.16
22640.14
226.4
226.4
11989.71
32.16
1138.50

759.00
0.00
175.11

266.64
7.35
1320.00
965.05

56.00
490.00
490.00

416.50

0.00
121.24
2142.00

119.00

45.50
390.00

168.00
175.00
0.00
2.60

8.00
14.30
17.94
21106.88 W
211.07
21317.95 X
2995.17
24313.12 Y
3646.97
27960.09 Z

282.4

9088.49

530.25

32.16
2.25
1138.50
0.00
759.00
0.00
175.11
0.00
266.64
7.35
1320.00
965.05

56.00
490.00
490.00

416.50

0.00
121.24
2142.00

119.00
45.50

390.00

168.00

175.00
0.00
2.60

8.00
14.30
17.94
18738.16 W
187.38
18925.54 X
2659.04
21584.58 Y
3237.69
24822.26 Z
248.22
25070.48
250.7
250.7

11496.00

838.25

3.55
50.84
1794.00
0.00
1196.00
0.00
275.94
0.00
3510.00
1520.69

0.00
421.52
11.62
56.00
490.00
490.00

658.00

0.00
156.60
3311.00
0.00
157.50
63.00
540.00

240.00

105.00
0.00
1.80

5.40
10.66
32.24

25746.31 W

26003.77 X

29657.3 Y

34105.9 Z
18954.03

50.84
1794.00
0.00
1196.00
0.00
275.94
0.00
3510.00
1520.69
0.00
0.00
421.52
11.62

56.00
490.00
490.00

658.00

0.00
156.60
3311.00
0.00
157.50
63.00
540.00

240.00

105.00
0.00
1.80

5.40
10.66
32.24
32362.53 W
323.63
32686.16 X
4592.41
37278.56 Y
5591.78
42870.35 Z
428.7
43299.05
432.99
433

14367.61

838.25

3.55
50.84
1794.00
0.00
1196.00
0.00
275.94
0.00
3510.00
1520.69
0.00
0.00
421.52
11.62

56.00
490.00
490.00

658.00

0.00
156.60
3311.00
0.00
157.50
63.00
540.00

240.00

105.00
0.00
1.80

5.40
10.66
32.24
28617.91 W
286.18
28904.09 X

32965.12 Y

37909.89 Z
1843.20

8.15
480.00
350.93

0.00
675.84
18.63

21.00
171.50
339.50

105.00

0.00
388.50

25.26

52.50
21.00
180.00

40.00

35.00
0.00
1.00

2.40
36.40
4745.51 W
47.46
4792.96 X
673.41
5466.37 Y
819.96
6286.33 Z
62.86
6349.19
63.49
63.5

2352.00
10.40
729.00
0.00
95.52

862.40
23.77

20.21
21.00
241.50

38.50
490.00
490.00

17.50
178.50

52.50
21.00
180.00
0.00
18.00
48.00
0.00
1.00

2.40
36.40
5.46
6335.67 W
63.36
6399.02 X
899.06
7298.09 Y
1094.71
8392.8 Z
83.93
8476.73
84.77
84.75

379.60
173.80

89.10

0.00
59.99
0.00
193.01
0.00
600.75
260.27
1400.00
30.19

40.37
570.50
245.00

61.60
25.90
52.00

88.10 A

2.86

4490.92 W

4534.94 X

5159.73 Y

5920.47 Z

1487.50
32.08
379.60
173.80

89.10

0.00
600.75
59.99
0.00
193.01
0.00
47.23
0
700.00
94.50
25.26
20.18
14.00

28.26
24.50

350.00

210.00

0.00
8.13
0.00
20.00
0.00
472.30
0.00
100.00
5568.9 W
55.69
5624.59 X
790.26
6414.85 Y
962.23
7377.08 Z
73.77
7450.85
7450.85

0.00

1487.50
32.08
379.60
173.80

89.10
0.00
600.75
59.99
0.00
193.01
0.00
47.23
0.00
700.00
94.50
25.26
20.18
14.00
0.00
28.26
24.50
0.00
350.00
0.00
300.00
0.00
210.00
0.00
0.00
9.75
0.00
20.00
0.00
472.30
0.00
100.00
5868.9 W
58.69
5927.59 X
832.83
6760.42 Y
1014.06
7774.48 Z
77.74
7852.23
7852.25
0.00
35.10
1.82

271.04
0.00
1.82
6.60
1.82
0.00
0.00
1515.51
40.37
0.00
0.00
100.92

238.00

2095.44
2095.44
246.52
246.5
215.77
0.00
0.38

1154.50
1001.00

2005.50

4014.65
4014.65
472.31
472.3
38.00 W
0.38
38.38 X
5.39
43.77 Y
6.57
50.34 Z
0.5
50.84
50.85

16200.00
0.00
22.29

403.67
1050.00
53.82
17613.1 W
176.13
17789.23 X
2499.39
20288.61 Y
3043.29
23331.91 Z
233.32
23565.23

2.91

2.9
861.28
0.00
3.18

403.67
875.00
41.34
2082.38 W
20.82
2103.2 X
295.5
2398.7 Y
359.81
2758.51 Z
27.59
2786.09
2.32
2.3

376.65
0.00
10.14

217.98
189.00
72.80

835.07 W
8.35
843.42 X
118.5
961.92 Y
144.29
1106.21 Z
11.06
1117.27
111.73
111.75

224.10
0.00
2.24

145.32
126.00
48.88

525.54 W
5.26
530.79 X
74.58
605.37 Y
90.81
696.18 Z
6.96
703.14
70.31
70.3
170.20

5.30

35.00
217.98
588.00

72.80

1021.61 W
10.22
1031.82 X
144.97
1176.79 Y
176.52
1353.31 Z
13.53
1366.85
136.68
136.7

102.35
0.00
1.3

21.00
145.32
392.00

0.00
48.88

665.93 W
6.66
672.59 X
94.5
767.09 Y
115.06
882.15 Z
8.82
890.97
89.1
89.1

161.12

743.28

0.00

0.00
10578.46
1910.20 A

1885.00

2850.65

0.00
925.28

202.50
105.00
2.26
42.50
5.31

12.25
1.05
2.54
2.54

133.21
170.80
210.00
17.42
15.24
19999.09 W
6.94
20006.03 X
98.44
20104.47 Y
119.86

20224.33 Z
9.19
20233.52
2023.35
2023.35

1500.00

0.00

5.20

201.84
175.00
78.00

1930.87 W
19.31
1950.17 X
274
2224.17 Y
333.63
2557.8 Z
25.58
2583.38
172.23
172.25
0.00

118.90
7.22
2.77
29.40

40.60
40.60
26.20
86.89
8.75
8.75

0.28
2.40
0.00
0.36

91.00
91.00
63.00
589.45 W
5.89
595.35 X
83.65
678.99 Y
101.85
780.84 Z
7.81
788.65
788.65

2457.92
252.00
210.00

80.00
10.61

3.12
3.75
1.23

0.00
434.44
317.69
275.45
91.70
24.44

0.00
6.13
0.53
454.65
693.00
17.50
5198.44 W
51.98
5250.42 X
737.68
5988.1 Y
898.22
6886.32 Z
68.86
6955.18
7727.98
7728
456.00
4.80
576.00
25.47
50.94
421.11

0.00
315.00
157.50
53.82
27.04

2099.61
2099.61
2099.6
0.00

839.84
505.60
170.10

0.00
90.21

227.50
210.00
94.50
25.26
20.18
14.00
53.82
27.04
107.64

2809.07
2809.07
2809.05

3000.00

1755.00
0.00
400.00

98.80

0.00
350.00

0.00
252.59
201.84
5999.88 W
60
6059.88 X
851.41
6911.29 Y
1036.69
7947.99 Z
79.48

8027.47
267.58
267.6
890325.00
0.00
2387.93

32490.00

34627.50

32319.00

32319.00

391020.00
24795.00
3877.75
45000.00
39000.00
9000.00
2100.00
5400.00
13500.00
0.00
1170.00
1404.00
4680.00
294.00
4900.00

0.00
0.00

0.00

0.00
0.00

0.00
0.00

0.00

1937372.09 Z
890325.00
0.00
2387.93

32490.00

34627.50

32319.00

32319.00

159600.00

163356.98

0.00
24795.00
703.64

72000.00
0.00
9000.00
0.00
2100.00
5400.00
0.00
0.00
13500.00
0.00
0.00
0.00
1170.00
0.00
2340.00
0.00
4680.00

294.00
4900.00

1750.00
1450508.96 W
14505.09
1465014.05 X
205834.47
1670848.52 Y
250627.28
1921475.8 Z
19214.76
1940690.56
9952.26
9952.25

623227.50
1671.55

44004.00

46899.00

46899.00

46899.00

81060.00

169322.76

45000.00

39000.00

9000.00

2100.00
5400.00

0.00
13500.00
0.00
0.00
0.00
0.00
1170.00
0.00
2340.00
0.00
4680.00

294.00
4900.00

1750.00
1183624.82 W

11836.25
1195461.07 X
167962.28
1363423.35 Y
204513.5
1567936.85 Z
15679.37
1583616.22
7724.96
7724.95

623227.50

1671.55
44004.00

0.00
78165

0.00
78165.00
0.00
0.00
81060.00
0.00
0.00
81060.00
0.00
0.00
30724.64
0.00
0.00
72000.00
0.00
0.00
9000.00
0.00
0.00
2100.00
5400.00
0.00
0.00
13500.00
0.00
0.00
0.00
1170.00
0.00
2340.00
0.00
4680.00
294.00
4900.00

1750.00

1170143.97 W
11701.44
1181845.41 X
166049.28
1347894.69 Y
202184.2
1550078.89 Z
15500.79
1565579.68
7636.97
7636.95

890325.00
0.00
2387.93

109653.75

65792.25
163590.00
0.00
29642.11
0.00
0.00
0.00
24795.00
703.64
0.00
0.00
0.00
45000.00
0.00
39000.00

9000.00

2100.00
5400.00

0.00
13500.00
0.00
0.00
0.00
1170.00
0.00
2340.00
0.00
4680.00

294.00
4900.00

1459052.31 W

1473642.83 X
1680689.65 Y

1932793.1 Z

890325.00
0.00
2387.93

64980.00

65792.25

163590.00

163356.98

24795.00
703.64
72000.00

9000.00

2100.00
5400.00

0.00
13500.00
0.00
0.00
0.00
1170.00
0.00
2340.00
0.00
4680.00
0.00

294.00
4900.00

1447052.31 W
14470.52
1461522.83 X
205343.96
1666866.79 Y
250030.02
1916896.81 Z
19168.97
1936065.78
248.21
248.2
979357.50

2626.72

34020.00

34445.25

28706.40

28706.40

0.00
166698.00
29185.75
37004.00
1049.63
45000.00
39000.00
9000.00
2100.00
5400.00
13500.00
0.00
1170.00
2340.00
4680.00
0.00

0.00

0.00

0.00

0.00
0.00

0.00
0.00

0.00

979357.50
2626.72

79200.00
34020.00

34445.25

28706.40

28706.40

166698.00

160842.00

37004.00
1049.63

0.00
45000.00
39000.00
9000.00
2100.00
5400.00

13500.00
1350

1170.00

2340.00

4680.00

294.00
4900.00

1750.00

1637304.38 W
16373.04
1653677.42 X
232341.68
1886019.1 Y
282902.86
2168921.96 Z
21689.22
2190611.18
11469.17
11469.15

1287000.00
2626.72

57408.75

34445.25

28706.40

28706.40

166698.00

160842.00

0.00
37004.00
1049.63

0.00
45000.00
39000.00
9000.00

2100.00
5400.00
13500.00
1350

1170.00

2340.00

4680.00

294.00
4900.00

1750.00

1375696.88 W
13756.97
1389453.85 X
195218.27
1584672.11 Y
237700.82
1822372.93 Z
18223.73
1840596.66
9636.63
9636.65

755766.00
2626.72

34020.00

34445.25

28706.40

28706.40

166698.00

160842.00

37004.00
1049.63

45000.00
39000.00
9000.00

2100.00
5400.00
13500.00
1350

1170.00

2340.00

4680.00

294.00
4900.00

1750.00

1334512.88 W
13345.13
1347858.01 X
189374.05
1537232.06 Y
230584.81
1767816.87 Z
17678.17
1785495.03
9348.14
9348.15

979357.50
2626.72

57408.75

34445.25

28706.40

28706.40

166698.00

160842.00

37004.00
1049.63

72000.00

9000.00

2100.00
5400.00
13500.00
1350

1170.00

2340.00

4680.00

294.00
4900.00

1750.00

1546104.38 W
15461.04
1561565.42 X
219399.94
1780965.36 Y
267144.8
2048110.17 Z
20481.1
2068591.27
10830.32
10830.3

979357.50

2626.72

0.00
79200.00
57408.75

34445.25

28706.40

28706.40

166698.00

160842.00

0.00
37004.00
1049.63

72000.00

9000.00

2100.00
5400.00

13500.00
1350

1170.00

2340.00
0.00
4680.00

294.00
4900.00

1750.00
1625304.38 W
16253.04
1641557.42 X
230638.82
1872196.24 Y
280829.44
2153025.68 Z
21530.26
2174555.93
11385.11
11385.1

1287000.00

2626.72
34020.00

34445.25

28706.40

28706.40

166698.00

160842.00

37004.00
1049.63

72000.00

9000.00

2100.00
5400.00
13500.00
1350

1170.00

2340.00

4680.00

294.00
4900.00

1750.00

1363696.88 W
13636.97
1377333.85 X
193515.41
1570849.25 Y
235627.39
1806476.64 Z
18064.77
1824541.41
9552.57
9552.55

755766.00

2626.72
34020.00

34445.25

28706.40

28706.40

166698.00

160842.00

37004.00
1049.63

72000.00

9000.00

2100.00
5400.00
13500.00
1350

1170.00

2340.00

4680.00

294.00
4900.00

1750.00

1322512.88 W
13225.13
1335738.01 X
187671.19
1523409.2 Y
228511.38
1751920.58 Z
17519.21
1769439.78
9264.08
9264.1

0.00
940.80

0.37

1274.00

2091.16

3.50
87.50
130.00
88.17

84.27
156.00
4634.73 W
25.85
4660.57 X
366.77
5027.34 Y
446.58

5473.92 Z
34.24
5508.16
5508.15

523.20

0.21

715.00
2031.33 A

3.50
87.50
130.00

85.37 A

46.38 A
130.00
3537.54
15.82
3553.36 X
224.47
3777.83 Y
273.32

4051.14 Z
20.95
4072.1
4072.1

5080.80

2.00

6552.00
61.20

104.00
780.00

1128.40

477.00 A
14185.41 w
137.08
14322.5 X
1945.29
16267.79 Y
2368.62

18636.4 Z
181.59
18818
5227.22
5227.2

955.20

1274.00

2871.84

3.50
87.50
140.46

89.82
84.14

62.40
5268.13 w
25.15
5293.29 X
356.96
5650.24 Y
434.64

6084.88 Z
33.32
6118.21
6118.2

68250.00

3500.00

750.00
1200.00

11644.00

421.17
1400.00
1400.00
88302.64 w
883.03
89185.67 X
12530.59
101716.25 Y
15257.44
116973.69 Z
1169.74
118143.43
590.72
590.7
650.00

115.36
64.00
8.49

122.50
91.00
63.00

2645.98 A

3771.28 w
11.25
3782.53 X
159.69
3942.22 Y
194.44

4136.66 Z
14.91
4151.56
415.16
415.15

650.00

115.36
64.00
8.49

122.50
91.00
63.00
1125.3 w
11.25
1136.56 X
159.69
1296.24 Y
194.44
1490.68 Z
14.91
1505.59
150.56
150.55

300.00
156.00
78.00
534 w
5.34
539.34 X
75.78
615.12 Y
92.27
707.38 Z
7.07
714.46
714.45

514.20
27.04
541.25 w
0.27
541.52 X
3.84
545.36 Y
4.67

550.03 Z
0.36
550.39
18.35
18.35

6480.00

104.00

1401.95

444.04
385.00
192.50
94.50
21.58
8499.19 w
84.99
8584.18 X
1206.08
9790.26 Y
1468.54
11258.79 Z
112.59
11371.38
1137.14
1137.15

4000.00
400.00
292.44
127.50
87.73

252.59
201.84
350.00
175.00
5785.48 w
57.85
5843.33 X
820.99
6664.32 Y
999.65
7663.97 Z
76.64
7740.61
774.06
774.05

40755.00

301.42

1262.93
1009.18
875.00
577.50
44538.97 w
445.39
44984.36 X
6320.3
51304.66 Y
7695.7
59000.36 Z
590
59590.36
7945.38
7945.4

2940.00

312.00

863.85
567.00
349.50

4922.67 w
49.23
4971.9 X
698.55
5670.45 Y
850.57
6521.02 Z
65.21
6586.23
658.62
658.6
3150.00

312.00

863.85
567.00
349.50

5132.67 w
51.33
5184 X
728.35
5912.35 Y
886.85
6799.21 Z
67.99
6867.2
686.72
686.7

3780.00

312.00

863.85
567.00
349.50
5762.67 w
57.63
5820.3 X
817.75
6638.05 Y
995.71
7633.76 Z
76.34
7710.1
771.01
771

1350.00

280.94
1630.93 w
16.31
1647.24 X
231.44
1878.68 Y
281.8
2160.48 Z
21.6
2182.09
969.82
969.8

545.58
435.96
752.50
563.50
13.52
2138.38 w
21.38
2159.76 X
303.45
2463.21 Y
369.48
2832.69 Z
28.33
2861.02
286.1
286.1

3750.00

795.98

574.00
45.50
5113.84 w
51.14
5164.98 X
725.68
5890.66 Y
883.6
6774.26 Z
67.74
6842.01
68.42
68.4

0.00

5925.00

4386.60

717.50
45.50
11620.38 w
116.2
11736.59 X
1648.99
13385.58 Y
2007.84
15393.42 Z
153.93
15547.35
155.47
155.45

0.00

5475.00

865.20

717.50
45.50
11314.60 w
113.15
11427.75 X
1605.6
13033.34 Y
1955
14988.35 Z
149.88
15138.23
151.38
151.4

7336.25
114.40

83.20

7533.85 w
1.98
7535.83 X
28.04
7563.87 Y
34.14

7598.01 Z
2.62
7600.63
7600.65

118.13
2.55

4.86
140.79 w
1.41
142.19 X
19.98
162.17 Y
24.33
186.5 Z
1.86
188.36
188.35
3.50
87.50

12.00
150.00
48.88
294.29 w
2.94
297.23 X
41.76
339 Y
50.85
389.84 Z
3.9
393.74
3.94
3.95

52560.00
58320.00
8305.92

42111.36

51300.00
33338.16

60480.00

60480.00

50533.63

4800.00
1500.00
675.00

5400.00

13500.00
1350

14700.00
3600.00

140.00
700.00
2800.00
421487.88 w
4214.88
425702.76 X
59811.24
485513.99 Y

558341.09 Z

2506.35

38304.00
40824.00

58955.90

64800.00
42111.36

80640.00

80640.00

67378.18

4800.00
1500.00
675.00

5400.00

13500.00
1350

14700.00
3600.00

140.00
700.00
2800.00
441587.09 w
4415.87
446002.96 X
62663.42
508666.38 Y
76299.96
584966.33 Z
5849.66
590815.99
2625.85
2625.85

90720.00
58955.90

32400.00
21055.68

105840.00

105840.00

88433.86
4800.00
1500.00
675.00

5400.00

13500.00
1350

14700.00
3600.00

140.00
700.00
2800.00
414227.09 w
4142.27
418369.36 X
58780.9
477150.25 Y
71572.54
548722.79 Z
5487.23
554210.02
2463.16
2463.15

0.00
22275.00
16260.75

16929.00

17597.25

5139.29

26056.40
22572.00

23463.00

53460.00
69483.74

62370.00

62370.00

52112.81

5280.00
1500.00
450.00
5400.00

14850.00
1485

4800.00
2340.00
0
168.00
700.00

3500.00
441805.72 w
4418.06
446223.78 X
62694.44
508918.22 Y
76337.73
585255.96 Z
5852.56
591108.52
2627.15
2627.15
153900.00

162000.00

162400.00
295312.50
236876.40

118730.64
6367.95

5400.00

14400.00
2100.00

4800.00
4800.00
1200.00
29700.00
2970

392.00
2100.00
7700.00
1299857.45 w
12998.57
1312856.02 X
184456.27
1497312.29 Y
224596.84
1721909.14 Z
17219.09
1739128.23
3864.73
3864.75

107.88
2016.13
366.30

906.40

3396.69 w
21.24
3417.93 X
301.4
3719.33 Y
366.99

4086.33 Z
28.14
4114.46
1645.78
1645.8

0.00

3091.20

3800.10

317.47
601.02
14.72
7189.96
719
-3594.98
4313.97
107.85

107.85
43.14
43.15

330.00

58.09
46.42
38.50
290.50
24.20

207.12
217.98
245.00
189.00
283.50
24.20
1832.88
183.29
2016.17
806.47
806.45

262.50
1050.00
4.00
1207.11 w
12.07

1219.18 X

1390.48 Y

1599.05 Z

16.15

87.50
350.00
5.40
406.44 w
4.06
410.5 X
57.68
468.18 Y
70.23
538.4 Z
5.38
543.79
54.38
54.4

400.00

292.44
127.50
15.92

252.59
201.84
350.00
175.00
1785.48 w
17.85
1803.33 X
253.37
2056.7 Y
308.51
2365.21 Z
23.65
2388.86
238.89
238.9

326.27

1262.93
1009.18
875.00
577.50
3783.97 w
37.84
3821.81 X
536.96
4358.77 Y
653.82
5012.59 Z
50.13
5062.71
50.63
50.65
840.00

42.58

282.90
17.50

17.50
35.20
1219.62 w
12.2
1231.82 X
173.07
1404.89 Y
210.73
1615.62 Z
16.16
1631.78
3263.56
3263.55

945.00
42.58

282.90
17.50
17.50
35.20
1324.62 w
13.25
1337.87 X

1525.84 Y

1754.72 Z

3544.55

1000.00
12.48
85.15
7.28
14.44
101.03
70.00
53.82
1340.81 w
13.41
1354.22 X
190.27
1544.48 Y
231.67
1776.16 Z
17.76
1793.9

500.00
12.48
85.15
7.28
14.44
101.03
70.00
53.82
840.81 W
8.41
849.22 X
119.32
968.53 Y
145.28
1113.81 Z
11.14
1124.95
1124.95

1000.00
12.48
85.15
7.28
14.44
101.03
70.00
53.82
1340.81 W
13.41
1354.22 X
190.27
1544.48 Y
231.67
1776.16 Z
17.76
1793.92
1793.9

4500.00
425.00
68.98

252.59
201.84
350.00
175.00
50.00
5975.48 W
59.75
6035.23 X
847.95
6883.18 Y
1032.48
7915.66 Z
79.16
7994.82
799.48
799.5

4700.00
0.00
675

292.44
127.50
15.92
252.59
201.84
350.00
175.00
6485.48 W
64.85
6550.33 X
920.32
7470.66 Y

8591.25 Z

867.7
0.00
8270
1539.83
87.50
435.96
87.50
567.00
94.50
1633.00 A

12748.61 W
111.16
12859.76 X
1577.35
14437.12 Y
1920.61

16357.73 Z
147.25
16504.97
1650.5
1650.5

416.09

352.74
278.80

219.42

31.31

25.26
1319.53 W
2.19
1321.72 X
31.14
1352.86 Y
37.91

1390.77 Z
2.91
1393.68

2322.8

2090.00

1700.00

35.00
201.84
525.00
4490.58 W
44.91
4535.48 X
637.24
5172.72 Y
775.91
5948.63 Z
59.49
6008.11
3004.06
3004.05

2420.00

1700.00

35.00
201.84
525.00
4820.58 W
48.21
4868.78 X
684.06
5552.85 Y
832.93
6385.78 Z
63.86
6449.63
3224.82
3224.8

3190.00

1700.00

35.00
201.84
525.00
5590.58 W
55.91
5646.48 X
793.33
6439.81 Y
965.97
7405.79 Z
74.06
7479.84
3739.92
3739.9
1200.00

575.00

320.00
53.82
53.82

631.46
252.59
350.00
3356.47 W
33.56
3390.03 X
476.3
3866.33 Y
579.95
4446.28 Z
44.46
4490.75
4490.75

4500.00

575.00

320.00
53.82
53.82
631.46
252.59
350.00
6656.47 W
66.56
6723.03 X
944.59
7667.62 Y
1150.14
8817.76 Z
88.18
8905.94
8905.95

400.00
0.00
1000
575.00

53.82
53.82

631.46
252.59
350.00
3236.47 W

3268.83 X
3728.11 Y

4287.32 Z

4330.2

310.00

1000.00
575.00

53.82
53.82

631.46
252.59
350.00
3146.47 W
31.46
3177.93 X
446.5
3624.43 Y
543.67
4168.1 Z
41.68
4209.78
4209.8
400.00
0.00
1000
1240.00
125.58
30.00
27.04
32.24
53.82
53.82

505.17
505.17
350.00
4235.33 W
42.35
4277.68 X
601.01
4878.7 Y
731.8
5610.5 Z
56.11
5666.61
5666.6
310.00

1000.00
1240.00
125.58
30.00
27.04
32.24
53.82
53.82

505.17
505.17
350.00
4145.33 w
41.45
4186.78 X
588.24
4775.03 Y
716.25
5491.28 Z
54.91
5546.19
5546.2

460.00
470.00
445.00

27.04
27.04
27.04
78.00
53.82

444.55
444.55
525.00
2906.95 W
29.07
2936.01 X
412.51
3348.52 Y
502.28
3850.8 Z
38.51
3889.31
3889.3

920.00
470.00
765.00

40.56
40.56
40.56
78.00
53.82

757.76
757.76
700.00
4478.16 W
44.78
4522.94 X
635.47
5158.41 Y
773.76
5932.18 Z
59.32

5991.5

1380.00
510.00
1050.00

67.34
67.34
67.34
78.00
80.60

1010.34
1010.34
1050.00
6167.11 W
61.67
6228.78 X
875.14
7103.92 Y
1065.59
8169.51 Z
81.7
8251.21
8251.2

1840.00
510.00
1430.00

107.64
107.64
107.64
78.00
107.64

1515.51
1515.51
1400.00
8427.88 W
84.28
8512.16 X
1195.96
9708.12 Y
1456.22
11164.33 Z
111.64
11275.98
11276
865.00

470.00
270.00
0.00
170

35.10
53.82
52.00
80.86

884.05
1010.34
1400.00
5065.1 W
50.65
5115.75 X
718.76
5834.51 Y
875.18
6709.69 Z
67.1
6776.79
6776.8

1730.00
470.00
400.00

170.00

35.10
107.64
52.00
107.64

1262.93
1515.51
2100.00
7615.36 W
76.15
7691.51 X

8772.17 Y

10088 Z

10188.9

2595.00

510.00
520.00
225.00

35.10
161.46
52.00
134.42

1515.51
1768.10
2450.00
9572.79 W
95.73
9668.52 X
1358.43
11026.94 Y
1654.04
12680.99 Z
126.81
12807.8
12807.8

3460.00

510.00
600.00

225.00

35.10
215.28
78.00
161.46
1768.10
2020.68
2800.00
11421.48 W
114.21
11535.69 X
1620.77
13156.46 Y
1973.47
15129.93 Z
151.3
15281.23
15281.25

1053.00
470.00
175.00

35.10

53.82
52.00
53.82

884.05
378.88
1050.00
4045.23 W
40.45
4085.68 X
574.04
4659.72 Y
698.96
5358.68 Z
53.59
5412.27
5412.25

2106.00
470.00
250.00

35.10
107.64
52.00
66.30

1262.93
505.17
1400.00
6036.36 W
60.36

0.00

6096.72 X

6953.31 Y

7996.31 Z

8076.25
3159.00
510.00
300.00

35.10
161.46
52.00
84.24

1515.51
757.76
1750.00
8047.95 W
80.48
8128.43 X
1142.04
9270.47 Y
1390.57
10661.04 Z
106.61
10767.66
10767.65

0.00

4212.00
510.00
390.00

35.10
215.28
52.00
138.06

1768.10
884.05
1925.00
9816.01 W
98.16
9914.17 X
1392.94
11307.11 Y
1696.07
13003.17 Z
130.03
13133.2
13133.2

725.00
414.00
80.00
88.00
32.24
26.78

0.00

53.82
27.04

166.71
166.71
234.50
1976 W
19.76
1995.76 X
280.4
2276.16 Y
341.42
2617.58 Z
26.18
2643.76
2643.75

725.00
207.00
80.00
88.00
32.24
26.78
53.82
27.04

151.55
166.71
220.50
1741.88 W
17.42
1759.3 X
247.18

0.00

2006.48 Y

2307.46 Z
2330.55

545.00
414.00
80.00
88.00
32.24
26.78
53.82
27.04

166.71
166.71
234.50
1796 W
17.96
1813.96 X
254.86
2068.82 Y
310.32
2379.14 Z
23.79
2402.93
2402.95

0.00

545.00
207.00
80.00
88.00
32.24
26.78
53.82
27.04

151.55
166.71
220.50
1561.88 W
15.62
1577.5 X
221.64
1799.14 Y
269.87
2069.01 Z
20.69
2089.7
2089.7

725.00
207.00
80.00
88.00
32.24
26.78
53.82
27.04

0.00
151.55
166.71
220.50
1741.88 W
17.42
1759.3 X
247.18
2006.48 Y
300.97
2307.46 Z
23.07
2330.53
2330.55

425.00
207.00
80.00
88.00
32.24
26.78
53.82
27.04

151.55
166.71
220.50
1441.88 W
14.42
1456.3 X
204.61
1660.91 Y
249.14
1910.05 Z

1929.15

310.00
207.00
80.00
88.00
32.24
26.78
53.82
27.04

151.55
166.71
220.50
1326.88 W
13.27
1340.15 X
188.29
1528.44 Y
229.27
1757.71 Z
17.58
1775.29
1775.3
1000.00

860.00
80.00
88.00
32.24
26.78
53.82
27.04

166.71
166.71
234.50
2697 W
26.97
2723.97 X
382.72
3106.68 Y
466
3572.69 Z
35.73
3608.41
3608.4

1000.00
0.00
430
80.00
88.00
32.24
26.78
53.82
27.04

151.55
166.71
220.50
2239.88 W
22.4
2262.28 X
317.85
2580.13 Y
387.02
2967.15 Z
29.67
2996.82
2996.8

1500.00

207.00
80.00
88.00
32.24
26.78
53.82
27.04

151.55
166.71
220.50
2516.88 W
25.17
2542.05 X
357.16
2899.21 Y
434.88
3334.09 Z

3367.45

2000.00

207.00
80.00
88.00
32.24
26.78
53.82
27.04

151.55
166.71
220.50
3016.88 W
30.17
3047.05 X
428.11
3475.16 Y
521.27
3996.44 Z
39.96
4036.4
4036.4
545.00
1600.00

80.00
88.00
32.24
26.78
53.82
27.04

166.71
166.71
220.50
2969.16 W
29.69
2998.85 X
421.34
3420.19 Y
513.03
3933.22 Z
39.33
3972.55
3972.55
545.00
125.00
34.00
88.00
32.24
26.78
53.82
27.04

166.71

166.71
234.50
1461 W
14.61
1475.61 X
207.32
1682.93 Y
252.44
1935.37 Z
19.35
1954.72
1954.7

900.00
80.60
80.86
1061.46 W
10.61
1072.07 X
150.63
1222.7 Y
183.41
1406.11 Z
14.06
1420.17
1420.15

1283.00
88.00
40.00
95.00

32.24
26.78
53.82
27.04

111.14
166.71
196.00
2087.34 W
20.87
2108.22 X
296.2
2404.42 Y
360.66
2765.09 Z
27.65
2792.74
2792.75
2480.00

176.00
54.08
53.82
27.04

111.14
303.10
287.00
3444.34 W
34.44
3478.78 X
488.77
3967.55 Y
595.13

4562.69 Z
45.63
4608.31
4608.3

3000.00

176.00
54.08
53.82
27.04

111.14
303.10
287.00
3964.34 W
39.64
4003.98 X
562.56
4566.54 Y
684.98
5251.53 Z
52.52
5304.04
5304.05

2800.00

176.00
54.08
53.82
27.04

111.14

303.10
287.00
3764.34 W
37.64
3801.98 X
534.18
4336.16 Y
650.42
4986.59 Z
49.87
5036.45
5036.45

2500.00

176.00
54.08
53.82
27.04

111.14
303.10
287.00
3464.34 W
34.64
3498.98 X
491.61
3990.59 Y
598.59
4589.18 Z
45.89
4635.07
4635.05

1800.00

88.00

27.04
53.82
27.04
111.14
166.71
196.00
2437.36 W
24.37
2461.74 X
345.87
2807.61 Y
421.14
3228.75 Z
32.29
3261.04
3261.05

1200.00

88.00
27.04
53.82
27.04

111.14
166.71
196.00
1837.36 W
18.37
1855.74 X
260.73
2116.47 Y

317.47
2433.94 Z
24.34
2458.28
2458.3

1050.00

88.00
27.04
53.82
27.04

111.14
166.71
196.00
1687.36 W
16.87
1704.24 X
239.45
1943.68 Y
291.55
2235.24 Z
22.35
2257.59
2257.6

1500.00
88.00
40.00
95.00
300.00
200.00
32.24
26.78
53.82
27.04

111.14
166.71
196.00
2804.34 W
28.04
2832.39 X
397.95
3230.34 Y
484.55
3714.89 Z
37.15
3752.04
3752.05

2500.00
88.00
40.00
95.00
300.00
200.00
32.24
26.78
53.82
27.04

111.14
166.71
196.00
3804.34 W
38.04
3842.39 X
539.86
4382.24 Y
657.34
5039.58 Z
50.4
5089.98
5090

525.00

88.00
26.78
52.00
15.60

30.31
85.88
77.00
887.44 W
8.87
896.32 X
125.93
1022.25 Y
153.34
1175.59 Z
11.76
1187.35

450.00

26.78
27.04

252.59
175.00
902.24 W
9.02
911.26 X
128.03
1039.29 Y
155.89
1195.18 Z
11.95
1207.13
1207.15

1200.00

26.78
27.04

252.59
175.00
1652.24 W
16.52
1668.76 X
1903.22 Y

2188.7 Z

2210.6

1830.00
-1200.00

630 W
6.3
636.3 X
89.4
725.7 Y
108.86
834.56 Z
8.35
842.9
842.9

1000.00
26.78
27.04

0.00

252.59
175.00
1452.24 W
14.52
1466.76 X
206.08
1672.84 Y
250.93
1923.76 Z
19.24
1943
1943

860.00

-1000.00
1050.00

-715.00
W
195
1.95
196.95 X
27.67
224.62 Y
33.69
258.31 Z
2.58
260.9
260.9

0.00

200.00

22.40
222.4 W
2.22
224.62 X
31.56
256.18 Y
38.43
294.61 Z
2.95
297.56
297.55

100.00
16.12

30.31
144.68 W
1.45
146.13 X
20.53
166.66 Y
25
191.66 Z
1.92
193.57
193.55

100.00
16.12

0.00

30.31
144.68 W
1.45
146.13 X
20.53
166.66 Y
25
191.66 Z
1.92
193.57
193.55

575.00

10.40
63.15
43.75
685 W
6.85
691.85 X
97.21
789.06 Y
118.36
907.42 Z
9.07
916.49
916.5

0.00

550.00

14.04

63.15
43.75
663.64 W
6.64
670.28 X
94.17
764.45 Y
114.67
879.12 Z
8.79
887.91
887.9

700.00

27.04

252.59
175.00
1125.46 W
11.25
1136.71 X
159.71
1296.42 Y
194.46
1490.88 Z
14.91
1505.79
1505.8

0.00

1150.00

27.04

252.59
175.00
1575.46 W
15.75
1591.21 X
223.56
1814.77 Y
272.22
2086.99 Z
20.87
2107.86
2107.85

400.00
0.00
26.78
426.78 W
4.27
431.05 X
60.56
491.61 Y
73.74
565.35 Z
5.65
571.01
571
310.00
0.00
26.78
336.78 W
3.37
340.15 X
47.79
387.94 Y
58.19
446.13 Z
4.46
450.59
450.6

390.00

26.78
416.78 W
4.17
420.95 X
59.14
480.09 Y
72.01
552.1 Z
5.52
557.63
557.65

60.00
26.78
86.78 W
0.87
87.65 X
12.31
99.96 Y
14.99
114.96 Z
1.15
116.11
116.1

620.00
40.00
660 W
6.6
666.6 X
93.66
760.26 Y
114.04
874.3 Z
8.74
883.04
883.05

4500.00

69.42
4569.42 W
45.69
4615.11 X
648.42
5263.54 Y
789.53
6053.07 Z

6113.6

460.00
18.98

191.96
133.00
781.78 W
7.82
789.59 X
110.94
900.53 Y
135.08
1035.61 Z
10.36
1045.97
1045.95

1053.00
21.58
26.78
252.59
252.59
350.00
1898.19 W
18.98
1917.17 X
269.36

2186.53 Y

2514.51 Z

2539.65

725.00
107.64
18.98
851.62 W
8.52
860.14 X
120.85
980.99 Y
147.15
1128.13 Z
11.28
1139.41
1139.4
545.00
107.64
18.98
671.62 W
6.72
678.34 X
95.31
773.64 Y
116.05

889.69 Z

898.6

725.00
107.64
18.98
851.62 W
8.52
860.14 X
120.85
980.99 Y
147.15
1128.13 Z
11.28
1139.41
1139.4
425.00
107.64
18.98
551.62 W
5.52
557.14 X
78.28
635.41 Y
95.31
730.73 Z
7.31
738.03
738.05

310.00
107.64
18.98
436.62 W
4.37
440.99 X
61.96
502.94 Y
75.44
578.39 Z
5.78
584.17
584.15

1000.00
0.00
107.64
18.98
1126.62 W
11.27
1137.89 X
159.87
1297.76 Y
194.66
1492.42 Z
14.92
1507.35
1507.35

1283.00
80.86
21.58
1385.44 W
13.85
1399.29 X
196.6
1595.9 Y
239.38
1835.28 Z
18.35
1853.63
1853.65
1500.00
80.86
21.58
1602.44 W
16.02
1618.46 X
227.39
1845.86 Y
276.88
2122.74 Z
21.23
2143.96
2143.95

2500.00
80.86
21.58
2602.44 W
26.02
2628.46 X
369.3
2997.76 Y
449.66
3447.43 Z
34.47
3481.9
3481.9
25.00

40.56
65.56 W
0.66
66.22 X
9.3
75.52 Y
11.33
86.85 Z
0.87
87.72
87.7

33.00

40.56
73.56 W
0.74
74.3 X
10.44
84.73 Y
12.71
97.44 Z
0.97
98.42
98.4
35.00

40.56
75.56 W
0.76
76.32 X
10.72
87.04 Y
13.06
100.09 Z
1
101.09
101.1

35.00

40.56
75.56 W
0.76
76.32 X

87.04 Y

100.09 Z

101.1
25.00
8.32
33.32 W
0.33
33.65 X
4.73
38.38 Y
5.76
44.14 Z
0.44
44.58
44.6

30.00
3.64
33.64 W
0.34
33.98 X
4.77
38.75 Y
5.81

44.56 Z

45
400.00
31.05

101.60 A

7.20
8.32
2.86

133.21
115.50
780.49 W
6.79
787.28 X
96.34
883.62 Y
117.3
1000.92 Z
8.99
1009.91
1009.9

430.00

25.30
50.00
3.60
2.86
8.32

133.21
115.50
749.54 W
7.5
757.03 X
106.36
863.4 Y
129.51
992.91 Z
9.93
1002.84
1002.85

290.00

20.70
100.00
7.20
2.86
8.32

133.21
115.50
658.54 W
6.59
665.12 X
93.45
758.57 Y
113.79
872.36 Z
881.1

340.00

19.55
100.00
7.20
2.86
8.32

133.21
115.50
707.39 W
7.07
714.46 X
100.38
814.84 Y
122.23
937.07 Z
9.37
946.44
946.45

670.00

85.10
150.00
10.80
2.86

8.32

133.21
115.50
1156.54 W
11.57
1168.1 X
164.12
1332.22 Y
199.83
1532.06 Z
15.32
1547.38
1547.4

250.00

50.00
11.60
8.32

100.92
87.50
493.75 W
4.94
498.69 X
70.07
568.76 Y
85.31
654.07 Z
6.54
660.61
660.6

0.00

225.00

50.80 A

3.60
8.58

48.44
42.00
371.42 W
3.21
374.63 X
45.5
420.12 Y
55.4
475.52 Z
4.25
479.77
479.75
100.00

50.80 A

10.80
8.58

48.44
42.00

253.62 W

255.65 X

284.43 Y

319.47 Z

322.15

11917.50

161.46
107.64

212.17
73.50
290.50
12720.18 W
127.2
12847.39 X
1805.06
14652.44 Y
2197.87
16850.31 Z
168.5
17018.81
979.78
979.8

12600.00

161.46
107.64

212.17
73.50
290.50
13402.68 W
134.03
13536.71 X
1901.91
15438.62 Y
2315.79
17754.41 Z
177.54
17931.95
1062.95
1062.95
12978.00

161.46
107.64

212.17
73.50
290.50
13780.68 W
137.81
13918.49 X
1955.55
15874.04 Y
2381.11

18255.14 Z
182.55
18437.69
1024.32
1024.3

11025.00

161.46
80.76

176.81
59.50
245.00
11712.94 W
117.13
11830.07 X
1662.13
13492.2 Y
2023.83
15516.03 Z
155.16
15671.19
899.61
899.6

11550.00

161.46
80.76

176.81
59.50
245.00
12237.94 W
122.38
12360.32 X
1736.63
14096.95 Y
2114.54
16211.49 Z
162.11
16373.6
967.71
967.7
10567.80

161.46
80.76

176.81
59.50
245.00
11255.74 W
112.56
11368.3 X
1597.25

12965.55 Y

14910.38 Z

836.65

13.78

141.45
98.00
236.89 W
2.37
239.26 X
33.62
272.88 Y
40.93
313.81 Z
3.14
316.95
79.24
79.25

16.12

166.71
115.50
279.07 W
2.79

281.86 X

321.47 Y

369.69 Z

93.35
150.00
0.00
4.94

63.15
302.75
175.00
14.30
2.61
0.89
2.57
0.00
2.97
1.29
7.00
0.15
1.58
1.12
0.49
0.15
0.12
0.07

0.52
0.26
0.26
691.97 W
6.92
698.89 X
98.19
797.09 Y
119.56
916.65 Z
9.17
925.82
185.16
185.15
135.00

4.94

63.15
302.75
175.00
14.30

2.61
0.89
2.57
0.00
2.97
1.29
7.00
0.15
1.58
1.12
0.49
0.15
0.12

0.07
0.52
0.26
0.26
676.97 W
6.77
683.74 X
96.07
779.81 Y
116.97
896.78 Z
8.97
905.75
181.15
181.15

300.00
18.00
27.04
345.04 W
3.45
348.49 X
48.96
397.45 Y
59.62
457.07 Z
4.57
461.64
461.65

300.00
18.00

27.04
345.04 W
3.45
348.49 X
48.96
397.45 Y
59.62
457.07 Z
4.57
461.64
461.65

365.00
18.00
27.04
410.04 W
4.1
414.14 X
58.19
472.33 Y
70.85
543.18 Z
5.43
548.61
548.6

240.00
16.00
21.58
277.58 W
2.78
280.36 X
39.39

319.75 Y
47.96
367.71 Z
3.68
371.38
371.4

250.00
16.00
21.58
287.58 W
2.88
290.46 X
40.81
331.26 Y
49.69
380.95 Z
3.81
384.76
384.75

290.00

0.00
16
21.58
327.58 W
3.28
330.86 X
46.49
377.34 Y
433.94 Z

438.3

258.00
27.04
285.04 W
2.85
287.89 X
40.45
328.34 Y
49.25
377.59 Z
3.78
381.37
381.35

265.00
27.04
292.04 W
2.92
294.96 X
41.44
336.4 Y
50.46
386.86 Z
3.87
390.73
390.75

230.00

27.04
257.04 W
2.57
259.61 X
36.48
296.09 Y
44.41
340.5 Z
3.4
343.9
343.9

210.00
21.58
231.58 W
2.32
233.9 X
32.86
266.76 Y
40.01
306.77 Z
3.07
309.84
309.85
195.00
21.58
216.58 W
2.17
218.75 X
30.73
249.48 Y
37.42
286.9 Z
2.87
289.77
289.75

160.00

21.58
181.58 W
1.82
183.4 X
25.77
209.16 Y
31.37
240.54 Z
2.41
242.94
242.95

347.00
27.04
374.04 W
3.74
377.78 X
53.08
430.86 Y
64.63
495.49 Z
4.95
500.44
500.45

296.00
27.04
323.04 W
3.23
326.27 X
45.84
372.11 Y
55.82
427.93 Z
4.28
432.21
432.2

274.00
21.58
295.58 W
2.96
298.54 X
41.94
340.48 Y
51.07
391.55 Z
3.92
395.47
395.45

250.00
21.58
271.58 W
2.72
274.3 X
38.54
312.83 Y
46.93
359.76 Z
3.6
363.36
363.35

715.00

18.00
26.78
759.78 W
7.6
767.38 X
107.82
875.19 Y
131.28
1006.47 Z
10.06
1016.54
1016.55

615.00

18.00
26.78
659.78 W
6.6
666.38 X
93.63
760 Y
114
874 Z
8.74
882.74
882.75

500.00

16.00
21.58
537.58 W
5.38
542.96 X
76.29
619.24 Y
92.89
712.13 Z
7.12
719.25
719.25

480.00

16.00
21.58
517.58 W

522.76 X

596.2 Y

685.63 Z

692.5

590.00

27.04
617.04 W
6.17
623.21 X
87.56
710.77 Y
106.62
817.39 Z
8.17
825.56
825.55

620.00

27.04
647.04 W
6.47
653.51 X
91.82
745.33 Y
111.8
857.13 Z

8.57
865.7
865.7

510.00

27.04
537.04 W
5.37
542.41 X
76.21
618.62 Y
92.79
711.41 Z
7.11
718.53
718.55
382.00

21.58
403.58 W
4.04
407.62 X
57.27
464.89 Y
69.73
534.62 Z
5.35
539.96
539.95

462.00
21.58
483.58 W
4.84
488.42 X
68.62
557.04 Y
83.56
640.59 Z
6.41
647
647
275.00

21.58
296.58 W
2.97
299.55 X
42.09
341.63 Y
51.24
392.88 Z
3.93
396.81
396.8

405.00

18.00
27.04
450.04 W
4.5
454.54 X
63.86
518.4 Y
77.76
596.16 Z
5.96
602.13
602.15

495.00

18.00
27.04
540.04 W
5.4
545.44 X
76.63
622.07 Y
93.31
715.39 Z
7.15
722.54
722.55

320.00

16.00
21.58
357.58 W
3.58
361.16 X
50.74
411.9 Y
61.78
473.68 Z
4.74
478.42
478.4

373.00

16.00
21.58
410.58 W
4.11
414.69 X
58.26
472.95 Y
70.94
543.89 Z
5.44
549.33
549.35

360.00

27.04
387.04
3.87
390.91
55
445.83
67
512.71
5.13
518
517.85

472.00
27.04
499.04
4.99
504.03
71
574.85
86
661.07
6.61
668
667.7

400.00

27.04
427.04
4.27

0.00

431.31 X
60.6
491.91 Y
73.79
565.7 Z
5.66
571.35
571.35

278.00
21.58
299.58 W
3
302.58 X
42.51
345.09 Y
51.76
396.85 Z
3.97
400.82
400.8

330.00
21.58
351.58 W
3.52
355.1 X
49.89
404.99 Y
60.75
465.73 Z
4.66
470.39

0.00
470.4

215.00

21.58
236.58 W
2.37
238.95 X
33.57
272.52 Y
40.88
313.4 Z
3.13
316.53
316.55

700.00

18.00
27.04
745.04 W
7.45
752.49 X
105.72
858.22 Y
128.73
986.95 Z
9.87
996.82
996.8
850.00

18.00
27.04
895.04 W
8.95
903.99 X
127.01
1031 Y
154.65
1185.65 Z
11.86
1197.51
1197.5

615.00

27.04
642.04 W
6.42
648.46 X
91.11
739.57 Y
110.94
850.5 Z
8.51
859.01
859

800.00

27.04
827.04 W
8.27
835.31 X
117.36
952.67 Y
142.9
1095.57 Z
10.96
1106.53
1106.55

400.00

27.04
427.04 W
4.27
431.31 X
60.6
491.91 Y
73.79
565.7 Z
5.66
571.35
571.35

550.00

18.00
27.04
595.04 W
5.95
600.99 X
84.44
685.43 Y
102.81
788.24 Z
7.88
796.13
796.15

640.00

18.00
27.04
685.04 W
6.85
691.89 X
97.21
789.1 Y
118.37
907.47 Z
9.07
916.54
916.55

494.00

27.04
521.04 W
5.21
526.25 X
73.94
600.19 Y
90.03
690.22 Z
6.9
697.12
697.1

570.00
27.04
597.04 W
5.97
603.01 X
84.72
687.73 Y
103.16
790.89 Z
7.91
798.8
798.8

375.00

27.04
402.04 W

406.06 X

463.11 Y

532.58 Z

537.9

550.00

27.04
577.04 W
5.77
582.81 X
81.88
664.7 Y
99.7
764.4 Z
7.64
772.04
772.05

530.00

27.04
557.04 W
5.57
562.61 X

641.66 Y

737.91 Z

745.3

625.00

27.04
652.04 W
6.52
658.56 X
92.53
751.09 Y
112.66
863.75 Z
8.64
872.39
872.4

410.00

21.58
431.58 W
4.32
435.9 X

61.24
497.14 Y
74.57
571.71 Z
5.72
577.43
577.45

425.00

21.58
446.58 W
4.47
451.05 X
63.37
514.42 Y
77.16
591.58 Z
5.92
597.5
597.5

410.00

27.04
437.04 W
4.37
441.41 X
62.02

503.43 Y
75.51
578.94 Z
5.79
584.73
584.75

425.00

27.04
452.04 W
4.52
456.56 X
64.15
520.71 Y
78.11
598.81 Z
5.99
604.8
604.8

390.00

27.04
417.04 W
4.17
421.21 X
59.18
480.39 Y

72.06
552.45 Z
5.52
557.97
557.95

320.00

21.58
341.58 W
3.42
345 X
48.47
393.47 Y
59.02
452.49 Z
4.52
457.01
457

323.00

21.58
344.58 W
3.45
348.03 X
48.9
396.92 Y
59.54
456.46 Z
4.56
461.03

461.05

260.00

21.58
281.58 W
2.82
284.4 X
39.96
324.35 Y
48.65
373.01 Z
3.73
376.74
376.75

570.00

27.04
597.04 W
5.97
603.01 X
84.72
687.73 Y
103.16
790.89 Z
7.91
798.8
798.8

725.00

27.04
752.04 W
7.52
759.56 X
106.72
866.28 Y
129.94
996.22 Z
9.96
1006.18
1006.2

495.00

27.04
522.04 W
5.22
527.26 X
74.08
601.34 Y
90.2
691.54 Z
6.92
698.46
698.45

545.00

27.04
572.04 W
5.72
577.76 X

658.94 Y

757.78 Z
765.35

430.00

27.04
457.04 W
4.57
461.61 X
64.86
526.47 Y
78.97
605.44 Z
6.05
611.49
611.5

218.00
21.58
239.58 W
2.4
241.98 X
34
275.97 Y
0.00

0.00

0.00

0.00
0.00

0.00

0.00

0.00

0.00

363
21.58
300
27.04

437.56
437.55

383.00
27.04
410.04 W
4.1
414.14 X
58.19
472.33 Y
70.85
543.18 Z
5.43
548.61
548.6
358.00
35.88
393.88 W
3.94
397.82 X
55.89
453.71 Y
68.06
521.77 Z
5.22
526.99
527

455.00
35.88
490.88 W
4.91
495.79 X
69.66
565.45 Y
84.82
650.26 Z
6.5
656.77
656.75
coated

360.00

21.58
381.58 W
3.82
385.4 X
54.15
439.54 Y
65.93
505.48 Z
5.05
510.53
510.55

295.00

21.58
316.58 W
3.17
319.75 X
44.92
364.67 Y
54.7
419.37 Z
4.19
423.56
423.55

225.00
21.58
246.58 W
2.47
249.05 X
34.99
284.04 Y
42.61
326.64 Z
3.27
329.91
329.9

285.00
32.24
317.24 W
3.17

320.41 X
45.02
365.43 Y
54.81
420.24 Z
4.2
424.45
424.45

390.00
32.24
422.24 W
4.22
426.46 X
59.92
486.38 Y
72.96
559.34 Z
5.59
564.93
564.95
coated

440.00

27.04
467.04 W
4.67
471.71 X
66.28
537.99 Y
80.7
618.68 Z
6.19
624.87

624.85

310.00

21.58
331.58 W
3.32
334.9 X
47.05
381.95 Y
57.29
439.24 Z
4.39
443.63
443.65

475.00
18.00
27.04
520.04 W
5.2
525.24 X
73.8
599.04 Y
89.86
688.89 Z
6.89
695.78
695.8

400.00

18.00
27.04
445.04 W
4.45
449.49 X
63.15
512.64 Y
76.9
589.54 Z
5.9
595.44
595.45
283.00
16.00
21.58
320.58 W
3.21
323.79 X
45.49
369.28 Y
55.39
424.67 Z
4.25
428.92
428.9

295.00
16.00
21.58
332.58 W
3.33
335.91 X
47.19
383.1 Y
57.47

440.57 Z

444.95
239.00
27.04
266.04 W
2.66
268.7 X
37.75
306.45 Y
45.97
352.42 Z
3.52
355.94
355.95

264.00
27.04
291.04 W
2.91
293.95 X
41.3
335.25 Y
50.29
385.54 Z
3.86
389.39
389.4

270.00
27.04
297.04 W
2.97
300.01 X
42.15
342.16 Y
51.32
393.49 Z
3.93
397.42
397.4

191.00
21.58
212.58 W
2.13
214.71 X
30.17
244.87 Y
36.73
281.6 Z
2.82
284.42
284.4

210.00
21.58
231.58 W
2.32
233.9 X
32.86
266.76 Y
40.01
306.77 Z
3.07
309.84
309.85

246.00
27.04
273.04 W
2.73
275.77 X
38.75
314.52 Y
47.18
361.69 Z
3.62
365.31
365.3

279.00
27.04
306.04 W
3.06
309.1 X
43.43
352.53 Y
52.88
405.41 Z
4.05
409.46
409.45
177.00
21.58
198.58 W
1.99
200.57 X
28.18
228.75 Y
34.31
263.06 Z
2.63
265.69
265.7

170.00
21.58
191.58 W
1.92
193.5 X
27.19
220.68 Y
33.1
253.78 Z
2.54
256.32
256.3
275.00

27.04
302.04 W
3.02
305.06 X
42.86
347.92 Y
52.19
400.11 Z
4
404.11
404.1

250.00

21.58
271.58 W
2.72
274.3 X
38.54
312.83 Y
46.93
359.76 Z
3.6
363.36
363.35
172.48
5.50
27.04
2.86

30.31

24.22
42.00
297.41 W
2.97
300.38 X
42.2
342.59 Y
51.39
393.98 Z
3.94
397.92
397.9

154.88
4.50
21.58
2.86

25.26
20.18
31.50
255.22 W
2.55
257.77 X
36.22
293.99 Y
44.1
338.09 Z
3.38
341.47
341.45

135.52
3.00
13.52
2.86

20.21

20.18
17.50
208.71 W
2.09
210.79 X
29.62
240.41 Y
36.06
276.47 Z
2.76
279.24
279.25

67.50

27.04
94.54 W
0.95
95.49 X
13.42
108.9 Y
16.34
125.24 Z
1.25
126.49
126.5

37.00

21.58
58.58 W
0.59
59.17 X
8.31
67.48 Y
10.12

77.6 Z
0.78
78.38
78.4

35.00

18.98
53.98 W
0.54
54.52 X
7.66
62.18 Y
9.33
71.51 Z
0.72
72.22
72.2

450.00

27.04
5.46
0
252.59
175.00
880.92 W
8.81
889.72 X
125.01
1014.73 Y

152.21
1166.94 Z
11.67
1178.61
1178.6

271.00

27.04
5.46

252.59
175.00
701.92 W
7.02
708.93 X
99.61
808.54 Y
121.28
929.82 Z
9.3
939.12
939.1

540.00

27.04
567.04 W
5.67
572.71 X
80.47
653.18 Y
0.00

0.00
0.00

0.00

0.00

0.00

0.00

0.00
0.00

0.00

0.00

0.00

0.00

0.00

0.00

0.00

500
27.04
5.46
252.59
175.00
218
27.04
5.46
252.59
175.00

655.4 X

747.49 Y

859.61 Z

868.2

385.00

27.04
412.04 W
4.12
416.16 X
58.47
474.63 Y
71.19
545.83 Z
5.46
551.28
551.3

144.71

20.80
8.32

70.72
94.50
327.09 W
1.82
328.91 X
25.88
354.8 Y
31.51
386.31 Z
2.42
388.72
388.7

98.66 A
15.60
7.02

50.52
70.00
233.05 W
1.34
234.39 X
19.07
253.46 Y
23.22
276.68 Z
1.78
278.46
278.45

52.62 A
10.40
5.46

35.36
49.00
146.72 W
0.94
147.66 X
13.35
161.01 Y
16.26
177.27 Z
1.25
178.52
178.5
23.00
22.00
64.00

2.86
13.52

100.92
175.00
379.42

383.21 X

437.06 Y

502.61 Z

507.65

23.00
32.00

41.34

14.30
80.73
87.50
265.75
2.66
268.4 X
37.71
306.12 Y
45.92
352.03 Z
3.52
355.55
355.55

32.00

7.28

36.33
42.00
111.48 W
1.11
112.6 X
15.82
128.42 Y
19.26
147.68 Z
1.48
149.16
149.15
115.22

285.10 A
34.32
434.63 W
0.34
434.97 X
4.87
439.84 Y
5.93
445.77 Z
0.45
446.23
44.62
44.6

86.58

214.24 A
30.42
331.23 W
0.3
331.54 X
4.32
335.85 Y
5.26
341.11 Z
0.4
341.51
34.15
34.15

186.32

24.44
210.74 W
0.24
210.99 X
3.47
214.46 Y
4.22
218.68 Z
0.32
219
21.9
21.9

138.93

18.98
157.9 W
0.19
158.09 X
2.69
160.78 Y
3.28
164.06 Z
0.25
164.31
16.43
16.45

148.50
13.52

100.92
87.50
335.85 W
3.36
339.21 X
47.66
386.87 Y
58.03
444.9 Z
4.45
449.35
449.35
400.00

2500.00

1240.00
552.50

30.00
118.30
143.52
236.86
236.86

505.17
505.17
350.00
6730.87 W
67.31
6798.18 X
955.14
7753.32 Y
1163
8916.32 Z
89.16
9005.48
9005.5
34.00
40.56
74.56 W
0.75
75.31 X
10.58
85.89 Y
12.88
98.77 Z
0.99
99.76
99.75

48.00
40.56
88.56 W
0.89
89.45 X
12.57
102.01 Y
15.3
117.31 Z
1.17
118.49
118.5
210.00
40.56
250.56 W
2.51
253.07 X

288.62 Y

331.91 Z

335.25

220.00
40.56
260.56 W
2.61
263.17 X
36.97
300.14 Y
45.02
345.16 Z
3.45
348.61
348.6
105.00
13.52
118.52 W
1.19
119.71 X
16.82
136.52 Y
20.48

157 Z

158.55

130.00
40.56
170.56 W
1.71
172.27 X
24.2
196.47 Y
29.47
225.94 Z
2.26
228.2
228.2
135.00
50.80 A

10.80
8.32

68.62
59.50
323.13 W
2.72
325.85 X

Amount
38.64
364.49 Y
47.05
411.55 Z
3.61
415.16
415.15

165.00
50.80 A

10.80
8.32

68.62
59.50
353.13 W
3.02
356.15 X
42.9
399.05 Y
52.24
451.29 Z
4
455.29
455.3

200.00
50.80 A

10.80
8.32

68.62
59.50
388.13 W
3.37
391.5 X
47.87
439.37 Y

58.29
497.65 Z
4.47
502.12
502.1
76.00
13.52
89.52 W
0.9
90.42 X
12.7
103.12 Y
15.47
118.59 Z
1.19
119.77
119.75

106.50
16.12
122.62 W
1.23
123.85 X
17.4
141.25 Y
21.19
162.43 Z
1.62

Amount
164.06
164.05
363.58

0.65

16.67
19.78
22.75

17.53 A
2.70

549.00 A

940.42 W
3.74
944.16 X
53.05
997.21 Y
64.59
1061.8 Z
4.95
1066.75

213.35
533.18

0.95

24.25
29.06
33.60

27.65 A
3.96

549.00 A

1125.01 W
5.48
1130.49 X
77.8
1208.3 Y
94.74
1303.03 Z
7.26
1310.3
262.06
262.05
702.78

1.25

31.83
38.35
44.10

37.78 A
5.20

549.00 A
1309.26 W
7.22
1316.48 X
102.51
1419 Y
124.82
1543.82 Z
9.57
1553.39
310.68
310.7
6000.00
1900.00
400.00

19.58

505.17
505.17
350.00
9592.41 W
95.92
9688.33 X
1361.21
11049.55 Y
1657.43
12706.98 Z
127.07
12834.05
12834.05

9650.00
2290.00
19.58
252.59
175.00
12358 W
123.58
12481.57 X
1753.66
14235.24 Y
2135.29
16370.52 Z
163.71
16534.23

16534.25

4500.00
19.58

252.59
175.00
4918 W
49.18
4967.17 X
697.89
5665.06 Y
849.76
6514.82 Z
65.15
6579.97
6579.95
9500.00

19.58

505.17
350.00
505.17
10792.41 W
107.92
10900.33 X
1531.5
12431.83 Y
1864.77
14296.61 Z
142.97
14439.57
14439.55

0.00
Amount
-973638

You might also like