TÜV Rheinland Arabia LLC

Pakistan Branche
Industrial Services

INSPECTION REPORT
REPORT NUMBER: I01-PE-23-10-0461 Rev: 00 SHEET: Page 1 of 12
Contract No.: PROC-SERVICES/CB/CORR-5243/2021

Mechanical Integrity Assessment of REFERENCE PAK-TR-IS-22-


PROJECT NAME:
Regenerator Gas Scrubber PT-I NUMBER: 10-0315

Oil And Gas Development Company CLIENT ORDER


CLIENT: JT-PP-QP-47
Limited Pakistan NO.:

DATE OF INSPECTION: Mr. Umair - Plant Representative


CLIENT
REPRESENTATIVE: Muhammad Naeem Uddin (J.E Mechanical)
16th Sep to 5th Oct 2023
® TÜV, TUEV und TUV are registered trademarks. Any use or application requires prior approval.

PLACE OF INSPECTION:
Mr. Muhammad Anas Bajwa - API Inspector
ATTENDEES:
OGDCL Qadir Pur Gas Field Mr. Nasir – BV NDT Lead

ITEM/TAG NUMBER & DESCRIPTION: Regenerator Gas Scrubber V-9209

INSPECTED BY: CHECKED BY:


Name: Mr. Muhammad Anas Name: Mr. Fiaz Ahmad
Bajwa (API 510, 570) (API 510, 570,653,580)

Date: 23-OCT-2023

TÜV Rheinland Arabia LLC Pakistan Branch – 108, Block J-1, Johar Town, Lahore TUVR-PAK-IS-003-PV-Rev-00
www.tuv.com UAN: +92 42 111 TUV (888) 877 / Fax: +92 42 3595 7560
Email: Pakistan@sa.tuv.com Page 1 of 12
TÜV Rheinland Arabia LLC
Pakistan Branche
Industrial Services

INSPECTION REPORT
REPORT NUMBER: I01-PE-23-10-0461 Rev: 00 SHEET: Page 2 of 12
Contract No.: PROC-SERVICES/CB/CORR-5243/2021
Disclaimer: This report is truly based on the actual findings observed at the place and time of inspection. This report does not apply any type
of warranty against the above listed inspected item/s, neither it is eligible for court or legal purpose and the owner of the inspected item/s is strictly
bound to practice its contractual and regulatory responsibilities concerned with the integrity and safety of the operation of equipment/s and
surroundings. TÜV Rheinland Arabia LLC and its staff shall not be accountable in any case for any damage, loss or incident caused by the
inspected item/s.

Contents
1 INSPECTION SUMMARY: ................................................................................................................. 4
® TÜV, TUEV und TUV are registered trademarks. Any use or application requires prior approval.

1.1 DESIGN DATA: ......................................................................................................................... 4


2 ANTICIPATED DAMAGE MECHANISM: ............................................................................................ 4
3 REFERENCE DOCUMENTS: .............................................................................................................. 5
4 EXTENAL INSPECTION FINDINGS: .................................................................................................... 5
5 INTERNAL INSPECTION:................................................................................................................... 6
6 RECOMMENDATION/REPAIR: ......................................................................................................... 6
7 CONCLUSIONS: ................................................................................................................................ 6
8 ANNEXES: ........................................................................................................................................ 6
8.1 Annexure A – VISUAL INSPECTION FINDINGS ......................................................................... 8
8.2 ANNEXURE B-INSPECTION DATA EVALUATION .................................................................... 11

TÜV Rheinland Arabia LLC Pakistan Branch – 108, Block J-1, Johar Town, Lahore TUVR-PAK-IS-003-PV-Rev-00
www.tuv.com UAN: +92 42 111 TUV (888) 877 / Fax: +92 42 3595 7560
Email: Pakistan@sa.tuv.com Page 2 of 12
TÜV Rheinland Arabia LLC
Pakistan Branche
Industrial Services

INSPECTION REPORT
REPORT NUMBER: I01-PE-23-10-0461 Rev: 00 SHEET: Page 3 of 12
Contract No.: PROC-SERVICES/CB/CORR-5243/2021
® TÜV, TUEV und TUV are registered trademarks. Any use or application requires prior approval.

INSPECTION SUMMARY

TÜV Rheinland Arabia LLC Pakistan Branch – 108, Block J-1, Johar Town, Lahore TUVR-PAK-IS-003-PV-Rev-00
www.tuv.com UAN: +92 42 111 TUV (888) 877 / Fax: +92 42 3595 7560
Email: Pakistan@sa.tuv.com Page 3 of 12
TÜV Rheinland Arabia LLC
Pakistan Branche
Industrial Services

INSPECTION REPORT
REPORT NUMBER: I01-PE-23-10-0461 Rev: 00 SHEET: Page 4 of 12
Contract No.: PROC-SERVICES/CB/CORR-5243/2021

1 INSPECTION SUMMARY:
Only visual External and internal inspections, were conducted on the Regenerator Gas Scrubber
V-9209, situated at OGDCL Qadir Pur Field. During inspection time no major abnormalities
observed.

1.1 DESIGN DATA:


® TÜV, TUEV und TUV are registered trademarks. Any use or application requires prior approval.

Owner & User OGDCL Qadir Pur Location Qadir Pur


DESCON
Manufacturer ENGINEERING Construction Code ASME Sec Viii Div. 1
WORKS
Year of Built 2019 Name of Process Natural Gas

Design Pressure 950 PSIG Design Temperature 600 F/ 315C0

Material SA516 Gr. 70N Diameter ID 694 mm

PWHT No Radiography Full

Previous Inspected by: N/A Previous Inspection N/A


Date:
Prior Repair: N0 Repair Results: N0

1. SCOPE OF INSPECTION:

Inspection of Particle Filter was performed by carrying out the following;

Visual External inspection as per API-510

Visual Internal Inspection as per API-510

2 ANTICIPATED DAMAGE MECHANISM:


The provided data including operating parameters, design specifications and material of
composition were reviewed and evaluated in accordance with API 571 Recommended Practice.
The Equipment is susceptible to the following damage mechanism;

Atmospheric Corrosion

Erosion / Erosion Corrosion

CO2

TÜV Rheinland Arabia LLC Pakistan Branch – 108, Block J-1, Johar Town, Lahore TUVR-PAK-IS-003-PV-Rev-00
www.tuv.com UAN: +92 42 111 TUV (888) 877 / Fax: +92 42 3595 7560
Email: Pakistan@sa.tuv.com Page 4 of 12
TÜV Rheinland Arabia LLC
Pakistan Branche
Industrial Services

INSPECTION REPORT
REPORT NUMBER: I01-PE-23-10-0461 Rev: 00 SHEET: Page 5 of 12
Contract No.: PROC-SERVICES/CB/CORR-5243/2021
Wet H2S

Amin Corrosion

3 REFERENCE DOCUMENTS:

API-510 Pressure Vessel Inspection Code: In-service Inspection, Rating, Repair, and

Alteration
® TÜV, TUEV und TUV are registered trademarks. Any use or application requires prior approval.

API-572 Inspection Practices for Pressure Vessels

API-571 Damage Mechanism

ASME Sec V Non-destructive Examination

ASME Sec VIII Div. I

4 EXTENAL INSPECTION FINDINGS:


During external visual inspection following observations were made;

The external welding condition found satisfactory.

External protective coatings was found satisfactory.

External protective coatings were found to be damaged on the flange nozzle and at

random locations on the shell.

Saddle supports were found to be in satisfactory condition, and no major anomalies were

observed.

The visual condition of all nozzle weld joints was found to be satisfactory.

The visual condition of all nozzle flanges was found to be satisfactory.

Vessel shells, dish ends, and welds were inspected for evidence of dents and bulges, and

none were observed.

The vessel was found to be free of any major cuts and gouges during the visual

inspection.

No major signs of corrosion and pitting were observed externally.

The overall condition of the shells and both dishes was found to be satisfactory.

TÜV Rheinland Arabia LLC Pakistan Branch – 108, Block J-1, Johar Town, Lahore TUVR-PAK-IS-003-PV-Rev-00
www.tuv.com UAN: +92 42 111 TUV (888) 877 / Fax: +92 42 3595 7560
Email: Pakistan@sa.tuv.com Page 5 of 12
TÜV Rheinland Arabia LLC
Pakistan Branche
Industrial Services

INSPECTION REPORT
REPORT NUMBER: I01-PE-23-10-0461 Rev: 00 SHEET: Page 6 of 12
Contract No.: PROC-SERVICES/CB/CORR-5243/2021

5 INTERNAL INSPECTION:
Internal condition of shell and bottom was found satisfactory.

No corrosion and rusting were observed on the inside surface of the shell.

The condition of the demister pad was found to be in good condition.

Internally, bottom dish end surface cannot inspect due to limited access.
® TÜV, TUEV und TUV are registered trademarks. Any use or application requires prior approval.

6 RECOMMENDATION/REPAIR:
Deteriorated paint spots and deliberately removed paint areas need to be repainted.

Apply the protective coating to all shell surfaces as well as the flange to nozzle.

External corrosion on the bottom dish end and its support needs to be removed, and the
proper paint coating should be applied after the corrosion is removed.

All nozzle flanges need to be inspected in the next turnaround interval.

The inside surface of the bottom dish end needs to be inspected in the next turnaround
interval.

7 CONCLUSIONS:

Based on the results of visual inspection, overall assessment of the pressure vessel, it is
concluded that Regeneration Gas Scrubber V-9209 is safe to operate at the current operating
parameters until the next recommended inspection interval.

8 ANNEXES:

Annexure A – Visual Inspection Findings

Annexure B – Inspection Data Evaluation

TÜV Rheinland Arabia LLC Pakistan Branch – 108, Block J-1, Johar Town, Lahore TUVR-PAK-IS-003-PV-Rev-00
www.tuv.com UAN: +92 42 111 TUV (888) 877 / Fax: +92 42 3595 7560
Email: Pakistan@sa.tuv.com Page 6 of 12
TÜV Rheinland Arabia LLC
Pakistan Branche
Industrial Services

INSPECTION REPORT
REPORT NUMBER: I01-PE-23-10-0461 Rev: 00 SHEET: Page 7 of 12
Contract No.: PROC-SERVICES/CB/CORR-5243/2021
® TÜV, TUEV und TUV are registered trademarks. Any use or application requires prior approval.

Annexure A

VISUAL INSPECTION FINDINGS

TÜV Rheinland Arabia LLC Pakistan Branch – 108, Block J-1, Johar Town, Lahore TUVR-PAK-IS-003-PV-Rev-00
www.tuv.com UAN: +92 42 111 TUV (888) 877 / Fax: +92 42 3595 7560
Email: Pakistan@sa.tuv.com Page 7 of 12
TÜV Rheinland Arabia LLC
Pakistan Branche
Industrial Services

INSPECTION REPORT
REPORT NUMBER: I01-PE-23-10-0461 Rev: 00 SHEET: Page 8 of 12
Contract No.: PROC-SERVICES/CB/CORR-5243/2021
8.1 Annexure A – VISUAL INSPECTION FINDINGS
SR.NO. REFERENCE PHOTOGRAPHS OBSERVATIONS AND RECOMMENDATIONS

Observation:

The overall condition of the vessel is


® TÜV, TUEV und TUV are registered trademarks. Any use or application requires prior approval.

satisfactory.
1
Recommendation:

N/A

Observation:

The nameplate was installed during inspection


2 time.
Recommendation:

N/A

Observation:

The observed bottom dish end and its support


3 structure were in good condition.

Recommendation:

N/A

TÜV Rheinland Arabia LLC Pakistan Branch – 108, Block J-1, Johar Town, Lahore TUVR-PAK-IS-003-PV-Rev-00
www.tuv.com UAN: +92 42 111 TUV (888) 877 / Fax: +92 42 3595 7560
Email: Pakistan@sa.tuv.com Page 8 of 12
TÜV Rheinland Arabia LLC
Pakistan Branche
Industrial Services

INSPECTION REPORT
REPORT NUMBER: I01-PE-23-10-0461 Rev: 00 SHEET: Page 9 of 12
Contract No.: PROC-SERVICES/CB/CORR-5243/2021

Observation:
The internal condition of vessel found
4
satisfactory.
® TÜV, TUEV und TUV are registered trademarks. Any use or application requires prior approval.

Recommendation:
N/A

Observation:
The condition of demister paid was found
satisfactory.

5 Recommendation:
N/A

Observation:
The condition of foundation was found
satisfactory.

Recommendation:
N/A

TÜV Rheinland Arabia LLC Pakistan Branch – 108, Block J-1, Johar Town, Lahore TUVR-PAK-IS-003-PV-Rev-00
www.tuv.com UAN: +92 42 111 TUV (888) 877 / Fax: +92 42 3595 7560
Email: Pakistan@sa.tuv.com Page 9 of 12
TÜV Rheinland Arabia LLC
Pakistan Branche
Industrial Services

INSPECTION REPORT
REPORT NUMBER: I01-PE-23-10-0461 Rev: 00 SHEET: Page 10 of 12
Contract No.: PROC-SERVICES/CB/CORR-5243/2021
® TÜV, TUEV und TUV are registered trademarks. Any use or application requires prior approval.

ANNEXURE B

INSPECTION DATA EVALUATION

TÜV Rheinland Arabia LLC Pakistan Branch – 108, Block J-1, Johar Town, Lahore TUVR-PAK-IS-003-PV-Rev-00
www.tuv.com UAN: +92 42 111 TUV (888) 877 / Fax: +92 42 3595 7560
Email: Pakistan@sa.tuv.com Page 10 of 12
TÜV Rheinland Arabia LLC
Pakistan Branche
Industrial Services

INSPECTION REPORT
REPORT NUMBER: I01-PE-23-10-0461 Rev: 00 SHEET: Page 11 of 12
Contract No.: PROC-SERVICES/CB/CORR-5243/2021

8.2 ANNEXURE B-INSPECTION DATA EVALUATION


Equipment ID: Regeneration Gas Scrubber V-9809

Operating Pressure (P) 750 Psig

Operating Temperature 84 F0
® TÜV, TUEV und TUV are registered trademarks. Any use or application requires prior approval.

Service Period N/A Year

Material SA 516 Gr 70

Vessel Height 2488 mm In Vertical Orientation

Nominal Thickness (Shell) 20 mm

Nominal Thickness (Head) 22 Mm

Inside Diameter (ID) 694 (mm)

Radius (IR) 482 (mm)

Allowable Stress Value (S) 18800 Psi ASME Sec II Part D

Longitudinal Joint Factor (E ) 1 ASME Sec VIII Div 1

Previous Thickness (Shell) 2014 N/A


(mm)
Average minimum
Previous Thickness (Bottom Head) N/A
(mm)
Average minimum
Previous Minimum Thickness (Top N/A (mm)
Head) Average minimum
Current Minimum Thickness (Shell) N/A (mm)
2023 Average minimum
Current Minimum Thickness (Bottom N/A (mm)
Head) Average minimum
Current Minimum Thickness (Top N/A
(mm)
Head) Average minimum
Calculated Thickness (Internal N/A
(mm) ASME Sec VIII Div UG-27
Pressure) Shell
Calculated Thickness (Internal N/A
(mm) ASME Sec VIII Div UG-32
Pressure) Bottom Head
Calculated Thickness (Internal
N/A (mm) ASME Sec VIII Div UG-32
Pressure) Top Head
N/A
Time between previous and current Year

TÜV Rheinland Arabia LLC Pakistan Branch – 108, Block J-1, Johar Town, Lahore TUVR-PAK-IS-003-PV-Rev-00
www.tuv.com UAN: +92 42 111 TUV (888) 877 / Fax: +92 42 3595 7560
Email: Pakistan@sa.tuv.com Page 11 of 12
TÜV Rheinland Arabia LLC
Pakistan Branche
Industrial Services

INSPECTION REPORT
REPORT NUMBER: I01-PE-23-10-0461 Rev: 00 SHEET: Page 12 of 12
Contract No.: PROC-SERVICES/CB/CORR-5243/2021
N/A API 510 Section 7.1 Corrosion Rate
Corrosion Rate (LT) mm/year
Determination
N/A API 510 Section 7.1 Corrosion Rate
Corrosion Rate (ST) inch/year
Determination
N/A
MAWP (Shell) till the next inspection1 Psig

MAWP (Dish end) till the next N/A


Psig
inspection1
N/A API 510 Section 7.2 Remaining Life
Remaining Life Year
® TÜV, TUEV und TUV are registered trademarks. Any use or application requires prior approval.

Calculations
Next Recommended External N/A
Year
Inspection Interval
Next Recommended Internal N/A
Year
Inspection Interval

1. Calculated for assessment purpose only. This allowable working pressure shall not exceed the original
design condition, until/unless rerating to be carried out by engineering.

TÜV Rheinland Arabia LLC Pakistan Branch – 108, Block J-1, Johar Town, Lahore TUVR-PAK-IS-003-PV-Rev-00
www.tuv.com UAN: +92 42 111 TUV (888) 877 / Fax: +92 42 3595 7560
Email: Pakistan@sa.tuv.com Page 12 of 12