Professional Documents
Culture Documents
Road Rate Analysis - 3
Road Rate Analysis - 3
Road Rate Analysis - 3
8 Sand -
a Local m3 1,800.000 322.99 2,122.99
9 River bed/Quarry site Gravel m3 1,318.400 Rukum East (collection) 322.99 1,641.39
11 Stone m3 1,200.00 Rukum East (collection) 322.99 1,522.99
19 Wood for formwork (Saal) m 3
162,322.74 162,322.74
20 Wood for formwork (Sisau) m3 105,862.66 0 105,862.66
64 HDPE Pipe (NS-40) 2" dia. (2.5 kg/cm 2) R.m. 205.97 Pyuthan 205.97
B Manpower -
1 Labour skilled md 1,000.00 Bhume RM 1,000.00
2 Labour unskilled md 640.00 Bhume RM 640.00
Department
C Tools & Equipments Equipment Fuel Total al Fuel
(L/hr)
2 Dozer Wheel (CAT 814; 181-230 HP) hr 4,702.00 DoR 1,441.21 6,143.21 14.14
10 Excavator Track; 111-150HP hr 2,803.00 DoR 929.55 3,732.55 9.12
11 Excavator+Breaker; 111-150HP hr DoR - -
12 Generator 125 kVA hr 1,191.00 DoR 1,320.94 2,511.94 12.96
17 Loader Wheel hr 2,262.00 DoR 842.91 3,104.91 8.27
21 Back Hoe Loader; JCB 3CX-4 hr 1,335.00 DoR 814.38 2,149.38 7.99
28 Crane (3T) hr 2,047.00 DoR 550.39 2,597.39 5.4
29 Truck Flatbed 5.5 cum hr 1,218.00 DoR 964.21 2,182.21 9.46
30 Tipper 5 cum hr 874.00 DoR 703.28 1,577.28 6.9
34 Tractor hr 930.00 Bhume RM 458.66 1,388.66 Bhume RM 4.5
44 Concrete Mixer 0.4 cum hr 319.00 DoR 51.98 370.98 0.51
Decription of Works Roadway excavation in ordinary rock as per Drawing and technical specifications including removal of stumps and other deleterious matter, all lifts and lead as per 120.00
Unit
SP. Cl. No. 905 Drawing and instruction of the Engineer. (Mechanical Means) cum
Labour (A) Material (B) Equipment (C)
Norms No.
Type Unit Qty. Rate Amount Type Unit Qty. Rate Amount Type Unit Qty. Rate Amount
Skilled day 1.00 1,000.00 1,000.00 Hydraulic Excavator hour 6 3,732.55 22,395.30
9.1 B (II)
Unskilled day 3.00 640.00 1,920.00 -
Sub total of A 2,920.00 Sub total of B 0.00 Sub total of C 22,395.30
Sub total of A +B + C 25,315.30 Contractor's overhead expenses 15% 3,797.29 Unit Rate 242.60
Decription of Works Roadway Excavation in hard rock with rock breakers, including breaking rock, lifts and lead for disposal as per Drawing and Technical Specifications (Mechanical 16.00
Unit
SP. Cl. No. 905 Methods, Blasting Prohibited) cum
Labour (A) Material (B) Equipment (C)
Norms No.
Type Unit Qty. Rate Amount Type Unit Qty. Rate Amount Type Unit Qty. Rate Amount
Hydraulic Excavator with rock
Skilled day 1.00 1,000.00 1,000.00 hour 6.00 3,732.55 22,395.30
breaker attachment
9.1 B (II) Credit for excavated rock for use
Unskilled day 10.00 640.00 6,400.00 @ 50% of excavated (if avilable cum (8.00) 1,522.99 (12,183.92)
rock is used)
Sub total of A 7,400.00 Sub total of B 0.00 Sub total of C 10,211.38
Sub total of A +B + C 17,611.38 Contractor's overhead expenses 15% 2,641.71 Unit Rate 1,265.81
Decription of Works Earthwork in excavation of foundation of structures, including construction of shoring and bracing, removal of stumps and other deleterious matter and backfilling with 240.00
Unit
SP. Cl. No. 907 approved Material as per drawing and Technical Specifications. (Mechanical Means) (Depth upto 3m) cum
Labour (A) Material (B) Equipment (C)
Norms No.
Type Unit Qty. Rate Amount Type Unit Qty. Rate Amount Type Unit Qty. Rate Amount
Skilled day 1.00 1,000.00 1,000.00 Hydraulic Excavator hour 6.00 3,732.55 22,395.30
9.1 B (I)
Unskilled day 3.00 640.00 1,920.00 -
Sub total of A 2,920.00 Sub total of B 0.00 Sub total of C 22,395.30
Sub total of A +B + C 25,315.30 Contractor's overhead expenses 15% 3,797.29 Unit Rate 121.30
Decription of Works Earthwork in excavation of foundation of structures, including construction of shoring and bracing, removal of stumps and other deleterious matter and backfilling with 10.00
Unit
SP. Cl. No. 907 approved Material as per drawing and Technical Specifications. (Manual Means) (Depth upto 3m) Ordinary Soil cum
Labour (A) Material (B) Equipment (C)
Norms No.
Type Unit Qty. Rate Amount Type Unit Qty. Rate Amount Type Unit Qty. Rate Amount
Skilled day 1.00 1,000.00 1,000.00 -
9.1 A(I)
Unskilled day 3.00 640.00 1,920.00 -
Sub total of A 2,920.00 Sub total of B 0.00 Sub total of C -
Sub total of A +B + C 2,920.00 Contractor's overhead expenses 15% Unit Rate 292.00
Decription of Works Assembling mechanical woven Gabion boxes / mattresses placing in position including stretching, forming compartments, tying the sides and diaphragms with binding wire in each mesh, 160.00
Unit
SP. Cl. No. 2402 tying with bracing wires and tie wires; and tying down the lid complete as per specification (stone filling not included) sqm
Labour (A) Material (B) Equipment (C)
Norms No.
Type Unit Qty. Rate Amount Type Unit Qty. Rate Amount Type Unit Qty. Rate Amount
Skilled day 2.00 1,000.00 2,000.00
24.3
Unskilled day 10.00 640.00 6,400.00 -
Sub total of A 8,400.00 Sub total of C -
Sub total of A +B + C 8,400.00 Contractor's overhead expenses 15% 1,260.00 Unit Rate 60.37
Providing, assembling and filling stone/boulders in gabion boxes/mattress etc. including dressing, Gabion Size Area (sqm)
bedding, bonding, all complete as per Drawing and Technical Specifications ( Heavy zinc coated 1.5*1*1 8
Hexagonal mesh type 100 × 120 mm, mesh wire 3 mm, selvage wire 3.9 mm, lacing wire 2.4 mm 2*1*1 11
) 3*1*1 16
Decription of Works Provinding and Laying Reinforced Cement Concrete NP3 Flush Jointed pipe for culverts including fixing with cement mortar 1:2 as per Drawing and Technical Specifications. (450 mm 12.50
Unit
SP. Cl. No. 701 internal dia) Rm
Labour (A) Material (B) Equipment (C)
Norms No.
Type Unit Qty. Rate Amount Type Unit Qty. Rate Amount Type Unit Qty. Rate Amount
Add 3% of Labour cost for bellies,
Skilled day 1.00 1,000.00 1,000.00 Sand cum 0.09 2,122.99 191.07 crow bars, chain puley and other T 145.20
7.2 (B)
& P.
Unskilled day 6.00 640.00 3,840.00 Cement mt 0.07 19,675.54 1,377.29 -
RCC Pipes m 12.50 7,297.95 91,224.38
Sub total of A 4,840.00 Sub total of B 92,792.73 Sub total of C 145.20
Sub total of A +B + C 97,777.93 Contractor's overhead expenses 15% 14,666.69 Unit Rate 8,995.56
Decription of Works Provinding and Laying Reinforced Cement Concrete NP3 Flush Jointed pipe for culverts including fixing with cement mortar 1:2 as per Drawing and Technical Specifications. (600 mm 12.50
Unit
SP. Cl. No. 701 internal dia) Rm
Labour (A) Material (B) Equipment (C)
Norms No.
Type Unit Qty. Rate Amount Type Unit Qty. Rate Amount Type Unit Qty. Rate Amount
Add 3% of Labour cost for bellies,
Skilled day 1.00 1,000.00 1,000.00 Sand cum 0.10 2,122.99 212.30 crow bars, chain puley and other T 164.40
7.2 ('C)
& P.
Unskilled day 7.00 640.00 4,480.00 Cement mt 0.08 19,675.54 1,574.04 -
RCC Pipes m 12.50 10,567.95 132,099.38
Sub total of A 5,480.00 Sub total of B 133,885.72 Sub total of C 164.40
Sub total of A +B + C 139,530.12 Contractor's overhead expenses 15% 20,929.52 Unit Rate 12,836.77
Decription of Works Provinding and Laying Reinforced Cement Concrete NP3 Flush Jointed pipe for culverts including fixing with cement mortar 1:2 as per Drawing and Technical Specifications. (900 mm 12.50
Unit
SP. Cl. No. 701 internal dia) Rm
Labour (A) Material (B) Equipment (C)
Norms No.
Type Unit Qty. Rate Amount Type Unit Qty. Rate Amount Type Unit Qty. Rate Amount
Add 3% of Labour cost for bellies,
Skilled day 1.00 1,000.00 1,000.00 Sand cum 0.12 2,122.99 254.76 crow bars, chain puley and other T 164.40
7.2 (D)
& P.
Unskilled day 7.00 640.00 4,480.00 Cement mt 0.09 19,675.54 1,770.80 -
RCC Pipes m 12.50 15,417.95 192,724.38
Sub total of A 5,480.00 Sub total of B 194,749.93 Sub total of C 164.40
Sub total of A +B + C 200,394.33 Contractor's overhead expenses 15% 30,059.15 Unit Rate 18,436.27
Remarks:
1 Planks 38 mm thick 8 times usage
2 Struts, ballies etc 12 times usage
Collection of Gravel
Decription of Works 1.00
Collection and seiving of Gravel including stacking within 10 m Haulage distance (5-70mm) Unit
800 cum
Labour (A) Material (B) Equipment (C)
Norms No.
Type Unit Qty. Rate Amount Type Unit Qty. Rate Amount Type Unit Qty. Rate Amount
Skilled day - 1,000.00 - Add 3% of labour cost for T & P. 38.40
8.1A
Unskilled day 2.00 640.00 1,280.00 - -
-
Sub total of A 1,280.00 Sub total of B - Sub total of C 38.40
Sub total of A +B + C 1,318.40 Contractor's overhead expenses 15% 197.76 Unit Rate 1,516.16
Loading and
Transportation
Unit Weight of the Unloading Total (transportation +
S.N. Material Type Unit Remarks
material (t/m3) Time Taken for Unit Rate per Unit Rate per Loading / Unloading)
ER GR BT Unit Rate per unit
transportation (hr) ton unit
1 Stone cum 1.6 2.00 - - 0.36 32.75 52.40 270.60 322.99
2 Sand / aggregate cum 1.6 2.00 - - 0.36 32.75 52.40 270.60 322.99
3 Cement tonnes - - 160.00 14.40 5,239.55 5,239.55 436.00 5,675.54
4 Steel tonnes - - 160.00 14.40 5,239.55 5,239.55 436.00 5,675.54
Wt. of a 2.5 m, 900 mm
5 RCC Hume Pipe Rm 2.5 - - 160.00 14.40 5,239.55 3,562.89 355.07 3,917.95
dia hume pipe is 1.7 ton
6 Diesel / Petrol ltr 0.749 - - 160.00 14.40 5,239.55 3.92 - 3.92
7 GI Wire m2 - - 160.00 14.40 5,239.55 10.48 10.47 GI wire = 2kg/m2
8.01.02.a) Unskilled md 1.50 640.00 960.00 querry Add 3 % of Labour cost for Tools and Plants
output more
than 66% 28.80
Total of Labour + Materials + Equipments = 988.80
Description of works: Collection and sieving gravel including stacking within 10 m. Hauling distance (5-70mm) - Section 800 (8.1) - A Unit: 1 m3
Labour (A) Material (B) Equipment (C)
Norms No.
Type Unit Qty. Rate Amount Type Unit Qty. Rate Amount Type Unit Qty. Rate Amount
Unskilled md 2.00 640.00 1280.00 Add 3 % of Labour cost for Tools and Plants 38.40
Description of works: Collection of rubble of required size, hauling distance 10 m. and stacking. Section 800 (8.2) Unit: 1 m3
Labour (A) Material (B) Equipment (C)
Norms No.
Type Unit Qty. Rate Amount Type Unit Qty. Rate Amount Type Unit Qty. Rate Amount
8.01.03 Unskilled md 1.40 640.00 896.00 Add 3 % of Labour cost for Tools and Plants 26.88
Total of Labour + Materials + Equipments = 922.88