Professional Documents
Culture Documents
Plant Design Day 6-7 Lab - Resource and Space Determination
Plant Design Day 6-7 Lab - Resource and Space Determination
Day 6/7
Technical Documentation,
Resource Determination, Space Determination
Isometric
drawing
Half-
sectioned
isometric
Exploded
assembly
drawing
Variant I Variant II
10. Cutting 10. Cutting
20. Turning I 20. Turning I
30. Turning II 30. Turning II
40. Milling 40. Drilling
50. Handwork 50. Drilling
60. Drilling 60. Milling
70. Drilling 70. Handwork
10. CUTTING
40. TURNING
⬧⬧
⬧⧫⧫
◼
◆
⬧⬧ ◼
◼◼◆
◆⧫⧫
◼
◼◼
⬧
◆
◼◼
◆
◼◼
⧫⧫
⧫◼⧫
◆◼
⚫⚫
◼
◼◼
◼
◼
⧫⚫
◼
⧫
◼⬧
⧫⚫
◼
𝒐𝒖𝒕 𝒔𝒄𝒓𝒂𝒑
𝒀= =𝟏−
𝒊𝒏 𝒊𝒏
Example: During the transformation of 352 semi finished parts, 347 finished parts
were produced and 5 parts were scrapped because defective. Calculate the yield
of the process Y.
𝟑𝟒𝟕
𝒀= = 𝟎, 𝟗𝟖𝟓𝟖
𝟑𝟓𝟐
𝑫𝒆𝒇𝒆𝒄𝒕𝒔
𝑫𝑷𝑼 =
𝑼𝒏𝒊𝒕𝒔 𝒊𝒏
Example: During the transformation of 352 semi finished parts, 347 finished parts
were produced and 5 parts were scrapped because defective. Calculate the yield
of the process Y.
𝟓
𝑫𝑷𝑼 = = 𝟎, 𝟎𝟏𝟒𝟐𝟎
𝟑𝟓𝟐
𝑷𝒊 (𝟏−𝒔𝒊 )
→ 𝒀𝒊 = = 𝟏 − 𝒔𝒊
𝑷𝒊
A Vocational Degree programme developed by MCAST 33
Example 1 WP1 WP2
The operation process chart is shown
on picture.
P1s1 P2s2
The percentage of rejected parts at (4)
processes 1, 2, 3 and 4 are 7%, 4%, O
6% and 5%, respectively. WP3 WP4
(1)
P3s3 P4s4
The annual operating time is 2800 hours, and the annual demand forecast
for the product is 580000 units. Due to possible forecasting errors, 8000
additional units per year are required.
Find the production rate at each station.
Note. For assembly of one finished product, 4 parts have to be machined
on processes 1 and 2, and 1 has to be machined in process 3.
580000 + 8000
O= = 210 pcs/hr. P1s1 P2s2
2800 (4)
O 210
O
P4 = = = 221,06 pcs/hr. WP3 WP4
(1 − s4 ) 0,95 (1)
P3s3 P4s4
For assembly of one finished product,
4 parts have to be machined on process 2
1 has to be machined in process 3
P4 221,06
P4 = O3 P3 = = = 235,16 pcs/hr.
(1 − s3 ) 0,94
O2 = 4O3 4P4 4 221,06
P2 = = = 921,08 pcs/hr.
(1 − s2 ) 0,96
P2 = O1 P2 921,08
P1 = = = 990,41 pcs/hr.
(1 − s1) 0,93
A Vocational Degree programme developed by MCAST 35
Example 2 - Processes in line
Consider a product that requires 6 processes, in line.
After the operation is performed, each unit is inspected. If the demand for
this product is 5000 units per month.
Calculate production input P1.
𝑂 𝑝𝑐𝑠
𝑃1 = = 6068
(1 − 𝑠1 )(1 − 𝑠2 )(1 − 𝑠3 )(1 − 𝑠4 )(1 − 𝑠5 )(1 − 𝑠6 ) 𝑚𝑜𝑛𝑡ℎ
A Vocational Degree programme developed by MCAST 37
Production Rate Requirements – Processes in line
P1 1 2 ….. n-1 n On
𝑂𝑛 𝑂𝑛
𝑃1 = =
1 − 𝑠1 1 − 𝑠2 ⋯ (1 − 𝑠𝑛−1 )(1 − 𝑠𝑛 ) ς𝑖 𝑌𝑖
→ In a process in line the total yield is the product of the yield of each
machine/process
𝒀 = ෑ 𝒀𝒊
𝒊
A Vocational Degree programme developed by MCAST 38
Production Rate Requirements with Rework
𝑝𝑐𝑠 𝑝𝑐𝑠
𝑃1 = 𝑀1 1 − 𝑟1 → 𝑃1 = 17.66 ൗℎ𝑟 ∙ 0.93 = 16.43 ൗℎ𝑟
𝑝𝑐𝑠 𝑝𝑐𝑠
𝑂𝑖−1 = 𝑃𝑖 = 𝑀𝑖 1 − 𝑟𝑖 → 𝑃𝑖 = 32.14 ൗℎ𝑟 ∙ 0,51 = 16.39 ൗℎ𝑟 Demand @WPi-1
It provides more information than the classic Yield metric, which considers the
number of defective units rather than the total number of defects occurring on
those units.
The classic yield estimate also often only considers defects that are passed onto
the customer, ignoring defects that are corrected (reworked), a source of internal
waste.
A Vocational Degree programme developed by MCAST 42
6σ metric
EXAMPLE: How to calculate FPY
During the transformation of 352 semi finished parts,98 parts were
reworked, 347 finished parts were produced and 5 parts were scrapped
because defective. Calculate the Throughput Yield of the process FPY.
𝟑𝟓𝟐 − 𝟗𝟖 − 𝟓
𝑭𝑷𝒀 = = 𝟎, 𝟕𝟎𝟕𝟒
𝟑𝟓𝟐
Here and there throughout organizations, rework and fix practices arise and
become engrained as “that’s just the way we do it” parts of the standard practices.
But if you measure yield by using the first-time yield method you naturally
objectively review and acknowledge process effectiveness.
A Vocational Degree programme developed by MCAST 44
6σ metric
Complex processes are frequently a sequence of simpler
processes.
Rolled throughput yield (RTY) is a way Six Sigma quantifies the
complexity of a system is to count the number of processes
involved.
𝑹𝑷𝒀 = ෑ 𝑭𝑷𝑰𝒊
𝒊
That means that the chance of a purchase order going through the process
the first time with no rework or scrap is only 51.8 percent! (The last
“confirmation” step in the process acts as a final test. This last step has a
90-percent yield, so you know a lot of hidden factory stuff must be going on
to drop the RTY to 51.8 percent.)
A Vocational Degree programme developed by MCAST 46
6σ metric
Even if the first time yields of the individual process steps are high, if the
overall process becomes more and more complex, the system rolled
throughput yield will continue to erode.
𝒐𝒖𝒕 𝒔𝒄𝒓𝒂𝒑
𝒀= =𝟏−
𝒊𝒏 𝒊𝒏
46 46
𝟒𝟔
𝒀𝟏 = = 𝟎. 𝟗𝟐𝟎
𝟓𝟎
𝟒𝟔
𝒀𝟐 = = 𝟏. 𝟎𝟎𝟎
𝒐𝒖𝒕 𝒔𝒄𝒓𝒂𝒑 𝟒𝟔
𝒀= =𝟏− 𝟑𝟕
𝒊𝒏 𝒊𝒏 𝒀𝟑 = = 𝟎. 𝟖𝟎𝟒
𝟒𝟔 Please note that:
𝟑𝟕 𝟒𝟔 𝟒𝟔 𝟑𝟕 𝟑𝟕
𝒀𝒐𝒗𝒆𝒓𝒂𝒍𝒍 = = 𝟎. 𝟕𝟒𝟎 ς𝒊 𝒀𝒊 = = = 𝟎. 𝟕𝟒𝟎
𝟓𝟎 𝟓𝟎 𝟒𝟔 𝟒𝟔 𝟓𝟎
A Vocational Degree programme developed by MCAST 49
6σ metric
EXAMPLE: How to calculate Yield, TPY and RTY
Starting from right to left
→ In3=Out3 + Scrap3→ In3= 37+9=46.
→ In2=Out3 + Scrap3, being In3=Out2 → In2= 46+0=46.
46 46
𝟓𝟎 − 𝟒 − 𝟔
𝑭𝑷𝒀𝟏 = = 𝟎. 𝟖𝟎𝟎
𝟓𝟎
𝟒𝟔 − 𝟎 − 𝟏𝟐
𝒊𝒏 − 𝒔𝒄𝒓𝒂𝒑 − 𝒓𝒆𝒘𝒐𝒓𝒌 𝑭𝑷𝒀𝟐 = = 𝟎. 𝟕𝟑𝟗
𝑭𝑷𝒀 =
𝒊𝒏
𝟒𝟔
𝟒𝟔 − 𝟗 − 𝟎
𝑭𝑷𝒀𝟑 = = 𝟎. 𝟖𝟎𝟒
𝟒𝟔
𝑹𝑻𝒀 = ς𝒊 𝑭𝑷𝒀𝒊 = 𝟎. 𝟖𝟎𝟎 ∙ 𝟎. 𝟕𝟑𝟗 ∙ 𝟎. 𝟖𝟎𝟒 = 𝟎. 𝟒𝟕𝟓
A Vocational Degree programme developed by MCAST 50
Example 5
Consider the assembly line in figure.
WPi si ri
M1r1 1 2% 6%
2 5% 14%
M1 3 2% 0
PA WP1 Ins1 M3r3
O1
M1s1 M3 O3
M2r2 WP3 Ins3
M2 O2 M3s3
PB WP2 Ins2
M2s2
The demand for this product is 750,000 units per year and the annual
operating time is 1,950 hours.
@WP3 2 parts from WP1 are assembled with 1 part from WP2.
Determine
➢ the production rate at each processing station.
➢ the number of units of A and B that need to be supplied.
A Vocational Degree programme developed by MCAST 51
M3r3
Example 5 - Rework
M3 Ins3
P3 WP3 O3
Consider WP3.
𝑘𝑝𝑐𝑠ൗ M3s3
750 𝑦𝑒𝑎𝑟 𝑝𝑐𝑠
𝑂3 = = 384.62 ൗℎ𝑟
ℎ𝑟
1950 ൗ𝑦𝑒𝑎𝑟
𝑝𝑐𝑠
𝑂3 384. 6 ൗℎ𝑟 𝑝𝑐𝑠 Production rate @WP3 to
𝑀3 = → 𝑀𝑖 = = 392. 45 ൗℎ𝑟 fulfill the demand O3
(1 − 𝑟𝑖 − 𝑠𝑖 ) (1 − 0 − 0,02)
𝑝𝑐𝑠
𝑃3 = 𝑀3 1 − 𝑟3 → 𝑠𝑖𝑛𝑐𝑒 𝑟3 = 0 → 𝑃3 = 𝑀3 = 392. 45 ൗℎ𝑟
@WP3 2 parts from WP1 are assembled with 1 part from WP2.
→ O1=2P3 and O2=P3
𝑝𝑐𝑠
𝑂1 784. 90 ൗℎ𝑟 𝑝𝑐𝑠 Production rate @WP1 to
𝑀1 = → 𝑀1 = = 853. 15 ൗℎ𝑟 fulfill the demand O1
(1 − 𝑟1 − 𝑠1 ) (1 − 0.06 − 0,02)
𝑝𝑐𝑠
𝑂2 392. 45 ൗℎ𝑟 𝑝𝑐𝑠 Production rate @WP2 to
𝑀2 = → 𝑀2 = = 484. 51 ൗℎ𝑟 fulfill the demand O2
(1 − 𝑟2 − 𝑠2 ) (1 − 0.14 − 0,05)
For example:
A manufacturing process is operating 8 hr/day producing a part every 2
seconds.
Knowing that under optimal conditions the process was able to increase
the production rate to 0.75 pcs/s, calculate the OEE of the process.
ℎ𝑟 𝑠 𝑠
➢ Actually the process is working 8 ∙ 3600 = 28,800 to
𝑑𝑎𝑦 ℎ𝑟 𝑑𝑎𝑦
manufacture
𝑠 1 𝑝𝑐𝑠 𝑝𝑐𝑠
→ 𝑃𝑎𝑐𝑡𝑢𝑎𝑙 = 28,800 ∙ = 14,400
𝑑𝑎𝑦 2𝑠 𝑑𝑎𝑦
➢ Under optimal conditions the time required to manufacture the same
number of parts is
14,400 𝑝𝑐𝑠
→ 𝑡𝑜𝑝𝑡𝑖𝑚𝑢𝑚 = 𝑝𝑐𝑠 = 19,200 𝑠
0.75 𝑠
19,200 𝒔
→𝑶𝑬𝑬 =
28,800 s = 𝟎. 𝟔𝟔𝟕
Availability
𝒐𝒑𝒆𝒓𝒂𝒕𝒊𝒏𝒈_𝒕𝒊𝒎𝒆 𝒖𝒑𝒕𝒊𝒎𝒆
𝑨𝒗𝒂𝒊𝒍𝒂𝒃𝒊𝒍𝒊𝒕𝒚 = =
𝒔𝒄𝒉𝒆𝒅𝒖𝒍𝒆𝒅_𝒕𝒊𝒎𝒆 𝒖𝒑𝒕𝒊𝒎𝒆 + 𝒅𝒐𝒘𝒏𝒕𝒊𝒎𝒆
Availability
Considering the operating time in the figure, we know that the process will
be up between failures and down during repair.
The losses due to wasted performance are also often called speed losses.
In practice it is often difficult to determine speed losses, and a common
approach is to merely assign the remaining unknown losses as speed
losses.
It can be calculated as
𝑃𝑎𝑟𝑡𝑠_𝑤𝑜𝑟𝑘𝑒𝑑 ∙ 𝑆𝑡𝑎𝑛𝑑𝑎𝑟𝑑_𝑡𝑖𝑚𝑒
𝜂=
𝑜𝑝𝑒𝑟𝑎𝑡𝑖𝑛𝑔_𝑡𝑖𝑚𝑒
Example - Performance and productivity
1 1 𝑚𝑖𝑛
𝑡𝑠𝑡𝑎𝑛𝑑𝑎𝑟𝑑 = → 𝑡𝑠𝑡𝑎𝑛𝑑𝑎𝑟𝑑 = 𝑝𝑐𝑠 = 1.5 𝑝𝑐𝑠
𝑃𝑅𝑠𝑡𝑎𝑛𝑑𝑎𝑟𝑑 40
𝑚𝑖𝑛
𝑚𝑖𝑛 𝑚𝑖𝑛
𝑡𝑜𝑝𝑒𝑟𝑎𝑡𝑖𝑛𝑔 = 480 − 30 ∙ 5 − 300 = 1950
𝑤𝑒𝑒𝑘 𝑤𝑒𝑒𝑘
𝑝𝑐𝑠 𝑚𝑖𝑛
1228 ∙ 1.5
𝑤𝑒𝑒𝑘 𝑝𝑐𝑠
𝜂= = 0.945
𝑚𝑖𝑛
1950
𝑤𝑒𝑒𝑘
Quality
The Quality portion of the OEE Metric represents the yield of the process
→ Good Units produced as a percentage of the Total Units Started.
The Quality Metric is a pure measurement of Process Yield that is designed
to exclude the effects of Availability and Performance.
The losses due to defects and rework are called quality losses and quality
stops.
𝒐𝒖𝒕 𝒔𝒄𝒓𝒂𝒑
𝒀= =𝟏−
𝒊𝒏 𝒊𝒏
Example 6 - OEE
Mi Ins.
Pi WPi i Oi
𝑜𝑢𝑡 𝑂𝑖
𝑌= =
𝑖𝑛 𝑃𝑖
By considering the red node →𝑂𝑖 = 𝑀𝑖 (1 − 𝑠𝑖 − 𝑟𝑖 )
𝟏−𝒓𝒊 −𝒔𝒊
By considering the green node →𝑃𝑖 = 𝑀𝑖 1 − 𝑟𝑖 → 𝒀 =
𝟏−𝒓𝒊
𝟏−𝟎.𝟏𝟎−𝟎.𝟎𝟐
𝑶𝑬𝑬 = 𝑨 ∙ 𝜼 ∙ 𝒀 → 𝑶𝑬𝑬 = 𝟎. 𝟗𝟔𝟕𝟕 𝟏 − 𝟎. 𝟏𝟎 = 𝟎. 𝟗𝟎𝟗𝟒
𝟏−𝟎.𝟏𝟎
Example 6 - OEE
OEE metric formula value
𝑀𝑇𝐵𝐹
Availability 𝐴= 0.9677
𝑀𝑇𝑇𝑅 + 𝑀𝑇𝐵𝐹
Performance 𝜂 = 1−𝑟 0.90
1−𝑟−𝑠
Quality 𝑌= 0.9778
1−𝑠
OEE 𝑂𝐸𝐸 = 𝐴 ∙ 𝜂 ∙ 𝑌 0.9094
Solution
Takt time is the rate at which you need to complete a product to meet
customer demand. It can be calculated as
𝑡𝑛𝑒𝑡_𝑎𝑣𝑎𝑖𝑙𝑎𝑏𝑙𝑒
𝑡𝑡𝑎𝑘𝑡 =
𝐷𝑒𝑚𝑎𝑛𝑑
Where the net available time is defined as the amount of time available for
work excluding break times and any expected scheduled activity
(meetings, scheduled maintenance, drills, team briefings, etc.).
1 𝑠ℎ𝑖𝑓𝑡 𝑚𝑖𝑛 𝑚𝑖𝑛 𝑚𝑖𝑛
𝑡𝑛𝑒𝑡_𝑎𝑣𝑎𝑖𝑙𝑎𝑏𝑙𝑒 = 480 − 30 − 2 ∙ 15 − 10 − 10 → 𝑡𝑛𝑒𝑡𝑎𝑣𝑎𝑖𝑙𝑎𝑏𝑙𝑒 = 400
𝑑𝑎𝑦 𝑠ℎ𝑖𝑓𝑡 𝑠ℎ𝑖𝑓𝑡 𝑑𝑎𝑦
𝑚𝑖𝑛
𝑡𝑛𝑒𝑡_𝑎𝑣𝑎𝑖𝑙𝑎𝑏𝑙𝑒 400𝑑𝑎𝑦 𝑚𝑖𝑛
→ 𝑡𝑡𝑎𝑘𝑡 = → 𝑡𝑡𝑎𝑘𝑡 = 𝑝𝑐𝑠 = 2.0
𝐷𝑒𝑚𝑎𝑛𝑑 200𝑑𝑎𝑦 𝑝𝑐𝑠
Example 8 – Takt Time
The demand to a manufacturing plant is 1000 units per day.
The production is scheduled on one shift having a duration f 8 hours,
during which there is a 30 minutes lunch break, a 10 minutes personal
allowances and, on average, 8 minutes scheduled activities.
Calculate the takt time and the throughput rate the plant should produce.
Solution
𝑡𝑛𝑒𝑡_𝑎𝑣𝑎𝑖𝑙𝑎𝑏𝑙𝑒
𝑡𝑡𝑎𝑘𝑡 =
𝐷𝑒𝑚𝑎𝑛𝑑
1 𝑠ℎ𝑖𝑓𝑡 ℎ𝑟 𝑚𝑖𝑛 𝑚𝑖𝑛 𝑚𝑖𝑛
𝑡𝑛𝑒𝑡_𝑎𝑣𝑎𝑖𝑙𝑎𝑏𝑙𝑒 = 8 60 − 30 − 10 − 8 → 𝑡𝑛𝑒𝑡𝑎𝑣𝑎𝑖𝑙𝑎𝑏𝑙𝑒 = 432
𝑑𝑎𝑦 𝑠ℎ𝑖𝑓𝑡 ℎ𝑟 𝑠ℎ𝑖𝑓𝑡 𝑑𝑎𝑦
𝑚𝑖𝑛
𝑡𝑛𝑒𝑡_𝑎𝑣𝑎𝑖𝑙𝑎𝑏𝑙𝑒 432𝑑𝑎𝑦 𝑚𝑖𝑛
→ 𝑡𝑡𝑎𝑘𝑡 = → 𝑡𝑡𝑎𝑘𝑡 = 𝑝𝑐𝑠 = 0.432
𝐷𝑒𝑚𝑎𝑛𝑑 1000𝑑𝑎𝑦 𝑝𝑐𝑠
1 1 𝑝𝑐𝑠
→ 𝑅𝑡ℎ𝑟𝑜𝑢𝑔ℎ𝑝𝑢𝑡 = → 𝑅𝑡ℎ𝑟𝑜𝑢𝑔ℎ𝑝𝑢𝑡 = 𝑚𝑖𝑛 = 2.31
𝑡𝑡𝑎𝑘𝑡 0.432 𝑝𝑐𝑠 𝑚𝑖𝑛
Example 9 – How many people should we hire?
The standard production time of an assembly line is 0.13898 man-hours
per part produced.
The marketing department is forecasting a sale of 2500 pcs/day.
How many people should I hire if I estimate an OEE of 75%?
Solution
The standard time is the time required by an average skilled operator, working at
a normal pace, to perform a specified task using a prescribed method. It includes
appropriate allowances to allow the person to recover from fatigue and, where
necessary, an additional allowance to cover contingent elements which may occur
but have not been observed. → this does not take into account the ineffectiveness
of the process (unavailability of the machine, reworks and defects)
The processing lead time is the time required to complete the order (this time
considering also the ineffectiveness of the process). It can be calculated as:
𝒕𝒔𝒕𝒂𝒏𝒅𝒂𝒓𝒅
𝒕𝒍𝒆𝒂𝒅 = ∙ 𝑫𝒆𝒎𝒂𝒏𝒅
𝑶𝑬𝑬
ℎ𝑟
0.13898 𝑝𝑐𝑠 𝑝𝑐𝑠 ℎ𝑟
→ 𝑡𝑙𝑒𝑎𝑑 = ∙ 2500 = 463.27
0.75 𝑑𝑎𝑦 𝑑𝑎𝑦
to complete the daily order 463.27 hours must be worked, so if we employ workers
@ 8hr/day
𝑡𝑙𝑒𝑎𝑑
→ #𝑤𝑜𝑟𝑘𝑒𝑠 = ℎ𝑟 → #𝑤𝑜𝑟𝑘𝑒𝑠 = 57.9 𝑤𝑜𝑟𝑘𝑒𝑟𝑠
8 𝑑𝑎𝑦
Personal Requirements
n t i Oi
N =
i =1 H
where:
Oi - aggregate number of operation type i required on all products
manufactured per day.
ti - standard time required for an average operation Oi.
H - total production time available per day.
η - assumed production efficiency of the plant.
n - number of types of operations.
n t i Oi
N =
i =1 H
ℎ 𝑝𝑐𝑠
0.13898 𝑝𝑐𝑠∙2500𝑑𝑎𝑦
→ #𝑤𝑜𝑟𝑘𝑒𝑠 = ℎ𝑟 → #𝑤𝑜𝑟𝑘𝑒𝑠 = 57.9 𝑤𝑜𝑟𝑘𝑒𝑟𝑠
0.75∙8
𝑑𝑎𝑦
Example 1X – Conveyor belt
SuperBBQ is a company that manufactures grills.
The production is organized in 1 daily shift of 8 hours, during which there is
a programmed (paid) break of 25 minutes. Additionally, a 10-minute
personal allowance (paid) is given to each worker. During the year an
average of 3.75 hours are used for training programs, team meetings, fire
drills and other activities that require the stopping of the production. The
production is running 240 days per year.
One of their new products will be assembled on a line that will be served by
a conveyor belt on which the WIP, which has a footprint of 30x30 cm,
travels from one working-station to the other.
The daily demand forecasted for the product is 240 pcs/day.
Knowing that the MTTR is 90 min and the MTBF is 6 hrs,
A. Calculate the takt time and the throughput rate.
B. The standard production rate.
C. Set the speed of the conveyor belt (consider 10 cm distance between
WIPs).
Solution
𝑡𝑛𝑒𝑡_𝑎𝑣𝑎𝑖𝑙𝑎𝑏𝑙𝑒
𝑡𝑡𝑎𝑘𝑡 =
𝐷𝑒𝑚𝑎𝑛𝑑
𝑚𝑖𝑛
𝑚𝑖𝑛 𝑚𝑖𝑛 ℎ𝑟 60 𝑚𝑖𝑛
𝑡𝑛𝑜𝑡_𝑎𝑣𝑎𝑖𝑙𝑎𝑏𝑙𝑒 = 25 − 10 − 3,75 ℎ𝑟 = 50
𝑠ℎ𝑖𝑓𝑡 𝑠ℎ𝑖𝑓𝑡 𝑦𝑒𝑎𝑟 𝑠ℎ𝑖𝑓𝑡 𝑑𝑎𝑦 𝑑𝑎𝑦
1 240
𝑑𝑎𝑦 𝑦𝑒𝑎𝑟
𝑚𝑖𝑛
𝑡𝑛𝑒𝑡_𝑎𝑣𝑎𝑖𝑙𝑎𝑏𝑙𝑒 = 𝑡𝑡𝑜𝑡 − 𝑡𝑛𝑜𝑡_𝑎𝑣𝑎𝑖𝑙𝑎𝑏𝑙𝑒 → 𝑡𝑛𝑒𝑡𝑎𝑣𝑎𝑖𝑙𝑎𝑏𝑙𝑒 = 430
𝑑𝑎𝑦
𝑚𝑖𝑛
𝑡𝑛𝑒𝑡_𝑎𝑣𝑎𝑖𝑙𝑎𝑏𝑙𝑒 430 𝑚𝑖𝑛
𝑑𝑎𝑦
→ 𝑡𝑡𝑎𝑘𝑡 = → 𝑡𝑡𝑎𝑘𝑡 = 𝑝𝑐𝑠 = 1.79
𝐷𝑒𝑚𝑎𝑛𝑑 240𝑑𝑎𝑦 𝑝𝑐𝑠
1 1 𝑝𝑐𝑠
→ 𝑅𝑡ℎ𝑟𝑜𝑢𝑔ℎ𝑝𝑢𝑡 = → 𝑅𝑡ℎ𝑟𝑜𝑢𝑔ℎ𝑝𝑢𝑡 = 𝑚𝑖𝑛 = 0.558
𝑡𝑡𝑎𝑘𝑡 1.79 𝑚𝑖𝑛
𝑝𝑐𝑠
𝐿 = 𝑣 ∙ 𝑑𝑢𝑟𝑎𝑡𝑖𝑜𝑛
→ Parts have to be cured for 10 minutes @ 200° → 𝐿𝑜𝑣𝑒𝑛 = 21.8 𝑚
→Parts have to be cooled for 15 minutes @ RT → 𝐿𝑐𝑜𝑜𝑙𝑖𝑛𝑔 = 32. 7𝑚
The company does not have all this space. Any suggestions?
A Vocational Degree programme developed by MCAST 80
Example 10 – Number of machines
The standard production time of a machine is 0.400 min/pcs.
The production engineer receives an order of 2000 pcs/day.
Knowing that:
➢ The working day is made by an 8 shift; during the shift a 30 minutes
lunch break and 2 personal allowances breaks of 10 minutes each.
➢ The MTBF is 1000 min, the MTTR is 120 min; the efficiency index is
0,90 and the yield is 0,99.
A. Calculate
1. the standard production rate
2. the takt time
3. the throughput rate
4. the number of machines required to run the order
B. Consider the number of machines is A and, per shift, calculate
1. Design Capacity
2. Effective Capacity
3. Actual Capacity
4. Design utilization
5. Effective utilization
A Vocational Degree programme developed by MCAST 91
Example 10 – Number of machines
The standard production rate is the inverse of the standard time
1 1 𝑝𝑐𝑠
→ 𝑅𝑠𝑡𝑎𝑛𝑑𝑎𝑟𝑑 = → 𝑅𝑠𝑡𝑎𝑛𝑑𝑎𝑟𝑑 = 𝑚𝑖𝑛 = 2,5
𝑡∗ 0,400 𝑝𝑐𝑠 𝑚𝑖𝑛
The Takt time is the rate at which you need to complete a product to meet
customer demand. It can be calculated as
𝑡𝑛𝑒𝑡𝑎𝑣𝑎𝑖𝑙𝑎𝑏𝑙𝑒
𝑡𝑡𝑎𝑘𝑡 =
𝐷𝑒𝑚𝑎𝑛𝑑
Where the net available time is defined as the amount of time available for
work excluding break times and any expected scheduled activity.
1 𝑠ℎ𝑖𝑓𝑡 𝑚𝑖𝑛 𝑚𝑖𝑛 𝑚𝑖𝑛
𝑡𝑛𝑎 = 480 − 30 − 2 ∙ 10 → 𝑡𝑛𝑎 = 430
𝑑𝑎𝑦 𝑠ℎ𝑖𝑓𝑡 𝑠ℎ𝑖𝑓𝑡 𝑑𝑎𝑦
𝑚𝑖𝑛
𝑡𝑛𝑎 430 𝑚𝑖𝑛
𝑑𝑎𝑦
→ 𝑡𝑡𝑎𝑘𝑡 = → 𝑡𝑡𝑎𝑘𝑡 = 𝑝𝑐𝑠 = 0.215
𝐷𝑒𝑚𝑎𝑛𝑑 2000𝑑𝑎𝑦 𝑝𝑐𝑠
The facility operates two shift of 8 hours per day having a total of 900
min/day net available time.
Calculate the number of work-centres required to meet the demand
(suppose OEE=1).
𝟒
𝑷𝒊 ⋅ 𝒕∗ 𝒊 40 ⋅ 9 + 120 ⋅ 11 + 60 ⋅ 12 + 75 ⋅ 15
𝑁= = = 3,92 ≅ 4
𝒕𝑵𝑨𝒊 900
𝒊=𝟏
Please note that in this example we considered that the OEE=1 → there
are no losses due to unavailability, to bad performance (rework) or yield
loss.
In reality, to be able to fulfil the demand in a real case scenario, the
number of machines is greater than what we calculated.
Another observation, in this case the net time available for the work-centre
is the same for all the operations. This might not be always true, but is a
good simplification.
➢ the net available time is the same for all the machines and products
𝑃𝑖𝑗 1 200 𝑝𝑐𝑠/𝑠ℎ𝑖𝑓 𝑝𝑐𝑠
→ = = = 0.463
𝑡𝑁𝐴𝑖𝑗 𝑡𝑡𝑎𝑘𝑡 432 𝑚𝑖𝑛/𝑠ℎ𝑖𝑓𝑡 𝑚𝑖𝑛
Part i → 𝑷𝒊𝒋 ⋅ 𝒕∗ 𝒊𝒋
𝒕∗ 𝟏𝒋 𝒕∗ 𝟐𝒋 𝒕∗ 𝟑𝒋 𝒕∗ 𝟒𝒋 𝒕∗ 𝟓𝒋 𝒕∗ 𝟔𝒋
𝒕𝑵𝑨𝒊𝒋
Machine j ↓
A - 0,87 2.00 2.40 2.40 1.50 4.43
B 0.75 3.00 - 2.40 - 1.03 3,32
C 1.71 1.09 - - 2.14 - 2,29
D 1.43 2.86 0.87 - - 1.82 3.23
ℎ𝑟 € €
→ 𝐶𝐿𝑎𝑏𝑜𝑢𝑟 = 𝑡𝑎𝑐𝑡𝑢𝑎𝑙 ∙ 𝑐𝐿𝑎𝑏𝑜𝑢𝑟 → 𝐶𝐿𝑎𝑏𝑜𝑢𝑟 = 0.16346 ∙ 7.50 = 1.23
𝑝𝑐𝑠 ℎ𝑟 𝑝𝑐𝑠
Try it. Using this information it could be possible to calculate the number of
workers required to satisfy the demand if the net time available is the 90%
of the total working time (included scheduled activities).
5 k€/month Raw
Indirect Labour 2 €/kg 10 kg/pcs 20 €/pcs
materials
General Expenses 2 k€/month
Energy 10 c€/kWh 100 kWh/pcs 10 €/pcs
Fixed costs total 26 k€/month
Variable unitarian costs 40 €/pcs
→ 312000 €/year
Revenue
k€
Total costs
400
312
Fixed costs total 312000 €/year
10 V [kpcs]
A Vocational Degree programme developed by MCAST 110
Example 15 – Cost Analysis
Fixed costs total 312000 €/year
Variable unitarian costs 40 €/pcs
€ 𝑝𝑐𝑠 𝑚𝑜𝑛𝑡ℎ €
312000𝑦𝑒𝑎𝑟+700𝑚𝑜𝑛𝑡ℎ∙12 𝑦𝑒𝑎𝑟 ∙40𝑝𝑐𝑠 €
𝑐𝑢 = 𝑝𝑐𝑠 𝑚𝑜𝑛𝑡ℎ = 77.14
700 ∙12 𝑝𝑐𝑠
𝑚𝑜𝑛𝑡ℎ 𝑦𝑒𝑎𝑟
The BE point is defined as the interception between the revenue line and
the total cost line
€
𝐶𝐹 312000 𝑦𝑒𝑎𝑟 𝑝𝑐𝑠
→ 𝑝𝑋 = 𝐶𝐹 + 𝑐𝑉 𝑋 → 𝑋 = 𝑝−𝑐𝑉
→𝑋= € = 5200
𝑦𝑒𝑎𝑟
100 −40 𝑝𝑐𝑠
100k€
FMS
Transfer Line
10k
A B C D E F V [kpcs]
A Vocational Degree programme developed by MCAST 112
Relevant data for new design and restructuring
Structure area
Transport area
Auxiliary area Sanitary area
Social area
Functional area
Source: Pfeffer, IPA Stuttgart
Area for
Area for production control
interin storage and management
Area for
transport
Machine footprint
Area for
turnings,
chips and
waste
Area for
repairs and
assembly
Staging area for jigs
and fixtures, tools,
Area for Operating area testing equipment
material and
tools
Production area
Ap
Ap = An + At + Ai + A a
“Prvomajska”
Saw 4 1800 2200 4 16
Hack saw
“Prvomajska”
Consol mill 4 1590 2140 3.5 14
Mill
“Wotan”
Horizontal mill 2 5250 4925 26 52
“Prvomajska”
Turn 4 1050 3400 3.5 14
Universal turn
…..
A Vocational Degree programme developed by MCAST 136
Project work example
prvomajska
select-o-mat-320-s
…..
A Vocational Degree programme developed by MCAST 140
Project work example
…..
Forklift (elec.) VD-2502 25000 N 3m 4280 kg h = 3m l = 3,1m w = 1,3m
…..
A Vocational Degree programme developed by MCAST 142
Warehouse of finished products
No Part name Part number Zn Zg Dimensions Zk Zk / Zn Quantity Quantity Lenght
pcs/btc pcs/yr pcs/qua ser/qua palets/yr Palets/qua
1 Working shaft 322-725-37/1 30 720 ø100 x 268 180 6 24 6 7,20
2 Jaw 132-19 30 510 100 x 31.2 x 12.2 128 4,25 2 1 1,20
3 Glider 900-200:01 30 510 240 x 72 x 80 128 4,25 4 1 1,20
4 Housing 2 800-100:01 30 720 ø62 x 75,5 180 6 24 6 7,20
5 Bar 1 900-100:02 30 510 40 x 20 x 1755 128 4,25 17 5 6,00
6 Bar 3 900-100:03 30 600 20 x 10 x 455 150 5 40 10 12,00
7 Axle with gear 55-200:09/4 30 510 ø45 x 214 128 4,25 9 3 3,60
8 Base plate 132-08 30 600 146 x 200 x 27,4 150 5 2 1 1,20
9 Lever 3 93-146-03 30 810 66 x 30 x 27 203 6,75 7 2 2,40
10 Movable jaw 132-21 30 510 97 x 91 x 43,2 128 4,25 3 1 1,20
11 Angle body 800-100:02 30 900 160 x 140 x 110 225 7,5 15 4 4,80
12 Paralel guide 900-200:02 30 510 60 x 100 x 835 128 4,25 17 5 6,00
13 Shaft 114-100:03/3 30 510 ø65 x 765 128 4,25 17 5 6,00
14 Gear 348-100:03/4 30 810 ø95 x 36 203 6,75 14 4 4,80
15 Groved axle 55-132:09/4 30 810 ø28 x 226 203 6,75 5 2 2,40
ΣL (total lenght) 67,20
Type of cabinet NP 2600
Lr (usable lenght) 10,40
ΣL / Lr 7,00
n 7
(reqired number of cabinets) ◼◼◼◼◼◼◼
…..
A Vocational Degree programme developed by MCAST 145
Total space requirements
R aw material warehous e area 87.25
Warehous e of finis hed parts 93.10
produc tion area 848.56
R es trooms 25
Offic e 9
T ools area 9
Ins pec tion 9
T O T AL AR E A (m2) 1080.91
Plant layout
R ang e (m) 12 12, 18, 24, 30 or 36 m
S tep (m) 6 6 or 12 m
H eig ht (m) 6.00
R as ter (m2) 72.00
R eqired ras ters 15.01
C hos en number of ras ters 18
L ay out area (m2) 1296.00
POW-
DIMENSIONS WEIGHT Num.
TYPE MANUFACTURER ER
l (mm) w (mm) h (mm) P (kW) m (kg) n
SELECT-O-MAT 320 Prvomajska 2200 1800 1440 3,85 1150 1
3451B Stankoimport Moskva 1500 1000 1750 2,8 6200 1
SB-3 Prvomajska Dalstroj 850 570 840 1,8 780 1
GU-2 Prvomajska 2140 1590 1950 14,5 3680 2
MCV32 Prvomajska Dalstroj 1600 1300 300 11,3 8300 1
BRB-4 Prvomajska 2200 1500 2700 4 2240 1
D-420/1500 Prvomajska 3400 1050 1300 11 2180 2
3A130 Stankoimport Moskva 3060 2000 1550 7,5 3780 1
VR2-1500 Camut Torino 3730 2300 2800 9,7 6100 1
RAPID 1R Wotan 4925 5250 4520 7,7 6300 2
BG01 LŽT 1500 1000 1750 2,8 6200 1
OFA 16 Strojimport Prag 1990 1640 1665 5,5 3550 1
SS-30-X MAAG Zurich 2590 1200 1790 1,4 3450 1
SOK-110 Prvomajska 4800 2000 1800 19,2 4000 1
H-85-A TOS 3200 1400 1800 8 4800 1
Handwork - 3000 3000 2000 - - 1
painting - 3000 3000 2000 - - 1
Heat treatment - 3000 3000 2000 - - 1