MinutesofMeeting SEPCO SL 08-11-23 #28
MinutesofMeeting SEPCO SL 08-11-23 #28
ATTENDEES
Organization Name Email Address
SAMT Fouad Maksoud
Wang Guodong
Xia Mingwen
SEPCO Zhang Mingfei
Guan Shousuo
Zhang Shuhao
Rakesh Raghav
Sargent &
Rahul Mandal
Lundy
Imran Mushtaq
Other
ACTION ITEMS
10/05: S&L has shared RFI with not only ESF, but including other
technical aspects, SEPCO will review and provide feedback on the
same.
17/05: SEPCO has provided partial response to the RFI list, S&L will
review and revert on the same.
24/05 : Total will provide feedback for the editable files related to
ESF part.
31/05- Awaiting Total’s feedback.
07/06- Awaiting Total’s feedback.
14/06- Awaiting feedback.
21/06- Awaiting feedback.
28/06- Awaiting feedback.
05/07 - Awaiting feedback.
12/07 – S&L has received some input regarding ESF from SEC. S&L
1. will check and feedback. S&L 19/05/23
19/07- S&L has sent the updated input requirement list to SEPCO.
02/08 - S&L has shared the updated input requirement list for ESF.
SEPCO will check with TTE/ SEC.
09/08 - SEPCO to further check with SEC.
23/08 – ESF input requirements are marked on the new DCS (from
Al- Babtain). Same is shared with SEPCO.
TTE to collect the inputs.
30/08: Awaiting TTE’s reply.
06/09 - Awaiting TTE’s reply.
13/09 – As discussed with TTE in the E&P meeting, S&L will give a list
of documents required only for the preparation of S&L’s deliverables
as per MDL.
20/09 – S&L has submitted the list. SEPCO has forwarded to TTE.
Awaiting TTE’s feedback.
27/09- No action. TTE‘s response awaited.
04/10 – SEPCO will forward a download link.
11/10 – S&L will send the updated input list to SEPCO by 11/10/23
01/11 – Al Dar is involved.
ACTION ITEMS
10/05: S&L has shared RFI with not only ESF, but including other
technical aspects, SEPCO will review and provide feedback on the
same.
17/05: SEPCO has provided partial response to the RFI list, S&L will
review and revert on the same.
24/05 : Total will provide feedback for the editable files related to
ESF part.
31/05- Awaiting Total’s feedback.
07/06- Awaiting Total’s feedback.
14/06- Awaiting feedback.
21/06- Awaiting feedback.
28/06- Awaiting feedback.
05/07 - Awaiting feedback.
12/07 – S&L has received some input regarding ESF from SEC. S&L
1. will check and feedback. S&L 19/05/23
19/07- S&L has sent the updated input requirement list to SEPCO.
02/08 - S&L has shared the updated input requirement list for ESF.
SEPCO will check with TTE/ SEC.
09/08 - SEPCO to further check with SEC.
23/08 – ESF input requirements are marked on the new DCS (from
Al- Babtain). Same is shared with SEPCO.
TTE to collect the inputs.
30/08: Awaiting TTE’s reply.
06/09 - Awaiting TTE’s reply.
13/09 – As discussed with TTE in the E&P meeting, S&L will give a list
of documents required only for the preparation of S&L’s deliverables
as per MDL.
20/09 – S&L has submitted the list. SEPCO has forwarded to TTE.
Awaiting TTE’s feedback.
27/09- No action. TTE‘s response awaited.
04/10 – SEPCO will forward a download link.
11/10 – S&L will send the updated input list to SEPCO by 11/10/23
01/11 – Al Dar is involved.
ACTION ITEMS
10/05: S&L has shared RFI with not only ESF, but including other
technical aspects, SEPCO will review and provide feedback on the
same.
17/05: SEPCO has provided partial response to the RFI list, S&L will
review and revert on the same.
24/05 : Total will provide feedback for the editable files related to
ESF part.
31/05- Awaiting Total’s feedback.
07/06- Awaiting Total’s feedback.
14/06- Awaiting feedback.
21/06- Awaiting feedback.
28/06- Awaiting feedback.
05/07 - Awaiting feedback.
12/07 – S&L has received some input regarding ESF from SEC. S&L
1. will check and feedback. S&L 19/05/23
19/07- S&L has sent the updated input requirement list to SEPCO.
02/08 - S&L has shared the updated input requirement list for ESF.
SEPCO will check with TTE/ SEC.
09/08 - SEPCO to further check with SEC.
23/08 – ESF input requirements are marked on the new DCS (from
Al- Babtain). Same is shared with SEPCO.
TTE to collect the inputs.
30/08: Awaiting TTE’s reply.
06/09 - Awaiting TTE’s reply.
13/09 – As discussed with TTE in the E&P meeting, S&L will give a list
of documents required only for the preparation of S&L’s deliverables
as per MDL.
20/09 – S&L has submitted the list. SEPCO has forwarded to TTE.
Awaiting TTE’s feedback.
27/09- No action. TTE‘s response awaited.
04/10 – SEPCO will forward a download link.
11/10 – S&L will send the updated input list to SEPCO by 11/10/23
01/11 – Al Dar is involved.
ACTION ITEMS
10/05: S&L has shared RFI with not only ESF, but including other
technical aspects, SEPCO will review and provide feedback on the
same.
17/05: SEPCO has provided partial response to the RFI list, S&L will
review and revert on the same.
24/05 : Total will provide feedback for the editable files related to
ESF part.
31/05- Awaiting Total’s feedback.
07/06- Awaiting Total’s feedback.
14/06- Awaiting feedback.
21/06- Awaiting feedback.
28/06- Awaiting feedback.
05/07 - Awaiting feedback.
12/07 – S&L has received some input regarding ESF from SEC. S&L
1. will check and feedback. S&L 19/05/23
19/07- S&L has sent the updated input requirement list to SEPCO.
02/08 - S&L has shared the updated input requirement list for ESF.
SEPCO will check with TTE/ SEC.
09/08 - SEPCO to further check with SEC.
23/08 – ESF input requirements are marked on the new DCS (from
Al- Babtain). Same is shared with SEPCO.
TTE to collect the inputs.
30/08: Awaiting TTE’s reply.
06/09 - Awaiting TTE’s reply.
13/09 – As discussed with TTE in the E&P meeting, S&L will give a list
of documents required only for the preparation of S&L’s deliverables
as per MDL.
20/09 – S&L has submitted the list. SEPCO has forwarded to TTE.
Awaiting TTE’s feedback.
27/09- No action. TTE‘s response awaited.
04/10 – SEPCO will forward a download link.
11/10 – S&L will send the updated input list to SEPCO by 11/10/23
01/11 – Al Dar is involved.
ACTION ITEMS
10/05: S&L has shared RFI with not only ESF, but including other
technical aspects, SEPCO will review and provide feedback on the
same.
17/05: SEPCO has provided partial response to the RFI list, S&L will
review and revert on the same.
24/05 : Total will provide feedback for the editable files related to
ESF part.
31/05- Awaiting Total’s feedback.
07/06- Awaiting Total’s feedback.
14/06- Awaiting feedback.
21/06- Awaiting feedback.
28/06- Awaiting feedback.
05/07 - Awaiting feedback.
12/07 – S&L has received some input regarding ESF from SEC. S&L
1. will check and feedback. S&L 19/05/23
19/07- S&L has sent the updated input requirement list to SEPCO.
02/08 - S&L has shared the updated input requirement list for ESF.
SEPCO will check with TTE/ SEC.
09/08 - SEPCO to further check with SEC.
23/08 – ESF input requirements are marked on the new DCS (from
Al- Babtain). Same is shared with SEPCO.
TTE to collect the inputs.
30/08: Awaiting TTE’s reply.
06/09 - Awaiting TTE’s reply.
13/09 – As discussed with TTE in the E&P meeting, S&L will give a list
of documents required only for the preparation of S&L’s deliverables
as per MDL.
20/09 – S&L has submitted the list. SEPCO has forwarded to TTE.
Awaiting TTE’s feedback.
27/09- No action. TTE‘s response awaited.
04/10 – SEPCO will forward a download link.
11/10 – S&L will send the updated input list to SEPCO by 11/10/23
01/11 – Al Dar is involved.
ACTION ITEMS
10/05: S&L has shared RFI with not only ESF, but including other
technical aspects, SEPCO will review and provide feedback on the
same.
17/05: SEPCO has provided partial response to the RFI list, S&L will
review and revert on the same.
24/05 : Total will provide feedback for the editable files related to
ESF part.
31/05- Awaiting Total’s feedback.
07/06- Awaiting Total’s feedback.
14/06- Awaiting feedback.
21/06- Awaiting feedback.
28/06- Awaiting feedback.
05/07 - Awaiting feedback.
12/07 – S&L has received some input regarding ESF from SEC. S&L
1. will check and feedback. S&L 19/05/23
19/07- S&L has sent the updated input requirement list to SEPCO.
02/08 - S&L has shared the updated input requirement list for ESF.
SEPCO will check with TTE/ SEC.
09/08 - SEPCO to further check with SEC.
23/08 – ESF input requirements are marked on the new DCS (from
Al- Babtain). Same is shared with SEPCO.
TTE to collect the inputs.
30/08: Awaiting TTE’s reply.
06/09 - Awaiting TTE’s reply.
13/09 – As discussed with TTE in the E&P meeting, S&L will give a list
of documents required only for the preparation of S&L’s deliverables
as per MDL.
20/09 – S&L has submitted the list. SEPCO has forwarded to TTE.
Awaiting TTE’s feedback.
27/09- No action. TTE‘s response awaited.
04/10 – SEPCO will forward a download link.
11/10 – S&L will send the updated input list to SEPCO by 11/10/23
01/11 – Al Dar is involved.
ACTION ITEMS
10/05: S&L has shared RFI with not only ESF, but including other
technical aspects, SEPCO will review and provide feedback on the
same.
17/05: SEPCO has provided partial response to the RFI list, S&L will
review and revert on the same.
24/05 : Total will provide feedback for the editable files related to
ESF part.
31/05- Awaiting Total’s feedback.
07/06- Awaiting Total’s feedback.
14/06- Awaiting feedback.
21/06- Awaiting feedback.
28/06- Awaiting feedback.
05/07 - Awaiting feedback.
12/07 – S&L has received some input regarding ESF from SEC. S&L
1. will check and feedback. S&L 19/05/23
19/07- S&L has sent the updated input requirement list to SEPCO.
02/08 - S&L has shared the updated input requirement list for ESF.
SEPCO will check with TTE/ SEC.
09/08 - SEPCO to further check with SEC.
23/08 – ESF input requirements are marked on the new DCS (from
Al- Babtain). Same is shared with SEPCO.
TTE to collect the inputs.
30/08: Awaiting TTE’s reply.
06/09 - Awaiting TTE’s reply.
13/09 – As discussed with TTE in the E&P meeting, S&L will give a list
of documents required only for the preparation of S&L’s deliverables
as per MDL.
20/09 – S&L has submitted the list. SEPCO has forwarded to TTE.
Awaiting TTE’s feedback.
27/09- No action. TTE‘s response awaited.
04/10 – SEPCO will forward a download link.
11/10 – S&L will send the updated input list to SEPCO by 11/10/23
01/11 – Al Dar is involved.
ACTION ITEMS
10/05: S&L has shared RFI with not only ESF, but including other
technical aspects, SEPCO will review and provide feedback on the
same.
17/05: SEPCO has provided partial response to the RFI list, S&L will
review and revert on the same.
24/05 : Total will provide feedback for the editable files related to
ESF part.
31/05- Awaiting Total’s feedback.
07/06- Awaiting Total’s feedback.
14/06- Awaiting feedback.
21/06- Awaiting feedback.
28/06- Awaiting feedback.
05/07 - Awaiting feedback.
12/07 – S&L has received some input regarding ESF from SEC. S&L
1. will check and feedback. S&L 19/05/23
19/07- S&L has sent the updated input requirement list to SEPCO.
02/08 - S&L has shared the updated input requirement list for ESF.
SEPCO will check with TTE/ SEC.
09/08 - SEPCO to further check with SEC.
23/08 – ESF input requirements are marked on the new DCS (from
Al- Babtain). Same is shared with SEPCO.
TTE to collect the inputs.
30/08: Awaiting TTE’s reply.
06/09 - Awaiting TTE’s reply.
13/09 – As discussed with TTE in the E&P meeting, S&L will give a list
of documents required only for the preparation of S&L’s deliverables
as per MDL.
20/09 – S&L has submitted the list. SEPCO has forwarded to TTE.
Awaiting TTE’s feedback.
27/09- No action. TTE‘s response awaited.
04/10 – SEPCO will forward a download link.
11/10 – S&L will send the updated input list to SEPCO by 11/10/23
01/11 – Al Dar is involved.
ACTION ITEMS
10/05: S&L has shared RFI with not only ESF, but including other
technical aspects, SEPCO will review and provide feedback on the
same.
17/05: SEPCO has provided partial response to the RFI list, S&L will
review and revert on the same.
24/05 : Total will provide feedback for the editable files related to
ESF part.
31/05- Awaiting Total’s feedback.
07/06- Awaiting Total’s feedback.
14/06- Awaiting feedback.
21/06- Awaiting feedback.
28/06- Awaiting feedback.
05/07 - Awaiting feedback.
12/07 – S&L has received some input regarding ESF from SEC. S&L
1. will check and feedback. S&L 19/05/23
19/07- S&L has sent the updated input requirement list to SEPCO.
02/08 - S&L has shared the updated input requirement list for ESF.
SEPCO will check with TTE/ SEC.
09/08 - SEPCO to further check with SEC.
23/08 – ESF input requirements are marked on the new DCS (from
Al- Babtain). Same is shared with SEPCO.
TTE to collect the inputs.
30/08: Awaiting TTE’s reply.
06/09 - Awaiting TTE’s reply.
13/09 – As discussed with TTE in the E&P meeting, S&L will give a list
of documents required only for the preparation of S&L’s deliverables
as per MDL.
20/09 – S&L has submitted the list. SEPCO has forwarded to TTE.
Awaiting TTE’s feedback.
27/09- No action. TTE‘s response awaited.
04/10 – SEPCO will forward a download link.
11/10 – S&L will send the updated input list to SEPCO by 11/10/23
01/11 – Al Dar is involved.
ACTION ITEMS
10/05: S&L has shared RFI with not only ESF, but including other
technical aspects, SEPCO will review and provide feedback on the
same.
17/05: SEPCO has provided partial response to the RFI list, S&L will
review and revert on the same.
24/05 : Total will provide feedback for the editable files related to
ESF part.
31/05- Awaiting Total’s feedback.
07/06- Awaiting Total’s feedback.
14/06- Awaiting feedback.
21/06- Awaiting feedback.
28/06- Awaiting feedback.
05/07 - Awaiting feedback.
12/07 – S&L has received some input regarding ESF from SEC. S&L
1. will check and feedback. S&L 19/05/23
19/07- S&L has sent the updated input requirement list to SEPCO.
02/08 - S&L has shared the updated input requirement list for ESF.
SEPCO will check with TTE/ SEC.
09/08 - SEPCO to further check with SEC.
23/08 – ESF input requirements are marked on the new DCS (from
Al- Babtain). Same is shared with SEPCO.
TTE to collect the inputs.
30/08: Awaiting TTE’s reply.
06/09 - Awaiting TTE’s reply.
13/09 – As discussed with TTE in the E&P meeting, S&L will give a list
of documents required only for the preparation of S&L’s deliverables
as per MDL.
20/09 – S&L has submitted the list. SEPCO has forwarded to TTE.
Awaiting TTE’s feedback.
27/09- No action. TTE‘s response awaited.
04/10 – SEPCO will forward a download link.
11/10 – S&L will send the updated input list to SEPCO by 11/10/23
01/11 – Al Dar is involved.
ACTION ITEMS
10/05: S&L has shared RFI with not only ESF, but including other
technical aspects, SEPCO will review and provide feedback on the
same.
17/05: SEPCO has provided partial response to the RFI list, S&L will
review and revert on the same.
24/05 : Total will provide feedback for the editable files related to
ESF part.
31/05- Awaiting Total’s feedback.
07/06- Awaiting Total’s feedback.
14/06- Awaiting feedback.
21/06- Awaiting feedback.
28/06- Awaiting feedback.
05/07 - Awaiting feedback.
12/07 – S&L has received some input regarding ESF from SEC. S&L
1. will check and feedback. S&L 19/05/23
19/07- S&L has sent the updated input requirement list to SEPCO.
02/08 - S&L has shared the updated input requirement list for ESF.
SEPCO will check with TTE/ SEC.
09/08 - SEPCO to further check with SEC.
23/08 – ESF input requirements are marked on the new DCS (from
Al- Babtain). Same is shared with SEPCO.
TTE to collect the inputs.
30/08: Awaiting TTE’s reply.
06/09 - Awaiting TTE’s reply.
13/09 – As discussed with TTE in the E&P meeting, S&L will give a list
of documents required only for the preparation of S&L’s deliverables
as per MDL.
20/09 – S&L has submitted the list. SEPCO has forwarded to TTE.
Awaiting TTE’s feedback.
27/09- No action. TTE‘s response awaited.
04/10 – SEPCO will forward a download link.
11/10 – S&L will send the updated input list to SEPCO by 11/10/23
01/11 – Al Dar is involved.
ACTION ITEMS
10/05: S&L has shared RFI with not only ESF, but including other
technical aspects, SEPCO will review and provide feedback on the
same.
17/05: SEPCO has provided partial response to the RFI list, S&L will
review and revert on the same.
24/05 : Total will provide feedback for the editable files related to
ESF part.
31/05- Awaiting Total’s feedback.
07/06- Awaiting Total’s feedback.
14/06- Awaiting feedback.
21/06- Awaiting feedback.
28/06- Awaiting feedback.
05/07 - Awaiting feedback.
12/07 – S&L has received some input regarding ESF from SEC. S&L
1. will check and feedback. S&L 19/05/23
19/07- S&L has sent the updated input requirement list to SEPCO.
02/08 - S&L has shared the updated input requirement list for ESF.
SEPCO will check with TTE/ SEC.
09/08 - SEPCO to further check with SEC.
23/08 – ESF input requirements are marked on the new DCS (from
Al- Babtain). Same is shared with SEPCO.
TTE to collect the inputs.
30/08: Awaiting TTE’s reply.
06/09 - Awaiting TTE’s reply.
13/09 – As discussed with TTE in the E&P meeting, S&L will give a list
of documents required only for the preparation of S&L’s deliverables
as per MDL.
20/09 – S&L has submitted the list. SEPCO has forwarded to TTE.
Awaiting TTE’s feedback.
27/09- No action. TTE‘s response awaited.
04/10 – SEPCO will forward a download link.
11/10 – S&L will send the updated input list to SEPCO by 11/10/23
01/11 – Al Dar is involved.
ACTION ITEMS
10/05: S&L has shared RFI with not only ESF, but including other
technical aspects, SEPCO will review and provide feedback on the
same.
17/05: SEPCO has provided partial response to the RFI list, S&L will
review and revert on the same.
24/05 : Total will provide feedback for the editable files related to
ESF part.
31/05- Awaiting Total’s feedback.
07/06- Awaiting Total’s feedback.
14/06- Awaiting feedback.
21/06- Awaiting feedback.
28/06- Awaiting feedback.
05/07 - Awaiting feedback.
12/07 – S&L has received some input regarding ESF from SEC. S&L
1. will check and feedback. S&L 19/05/23
19/07- S&L has sent the updated input requirement list to SEPCO.
02/08 - S&L has shared the updated input requirement list for ESF.
SEPCO will check with TTE/ SEC.
09/08 - SEPCO to further check with SEC.
23/08 – ESF input requirements are marked on the new DCS (from
Al- Babtain). Same is shared with SEPCO.
TTE to collect the inputs.
30/08: Awaiting TTE’s reply.
06/09 - Awaiting TTE’s reply.
13/09 – As discussed with TTE in the E&P meeting, S&L will give a list
of documents required only for the preparation of S&L’s deliverables
as per MDL.
20/09 – S&L has submitted the list. SEPCO has forwarded to TTE.
Awaiting TTE’s feedback.
27/09- No action. TTE‘s response awaited.
04/10 – SEPCO will forward a download link.
11/10 – S&L will send the updated input list to SEPCO by 11/10/23
01/11 – Al Dar is involved.
07/06: RAM Study: S&L will check internally and revert back on it.
14/06- S&L will send e-mail to SEPCO by 14.06.2023
21/06- S&L has sent a mail on 14.06.2023. SEPCO to respond.
05/07 – S&L has submitted Technical Specification for RAM study.
Separate meeting shall be held for the issue.
12/07 – Separate discussion is required with Total. S&L sent mail to
SEPCO on 14.06.2023. SEPCO to send feedback on the mail.
19/07 - S&L is finalizing it internally and shall respond ASAP.
02/08 – S&L has submitted a TQ for RAM study. SEPCO to check with
TTE.
2. 09/08 – Awaiting TTE’s response for the TQ raised earlier. S&L 14/06/23
23/08 - Awaiting TTE’s response for the TQ raised earlier.
30/08 – SEPCO to share the TQ reply from TTE.
06/09- No action as of now.
13/09- SEPCO advised S&L to share RAM specification with 3rd party.
20/09 – S&L is checking internally.
27/09- No action this week.
04/10 - No action this week.
11/10 - No action this week. SEPCO has discussed with Elia to
prepare the TQ.
01/11 - No action this week.
07/06: RAM Study: S&L will check internally and revert back on it.
14/06- S&L will send e-mail to SEPCO by 14.06.2023
21/06- S&L has sent a mail on 14.06.2023. SEPCO to respond.
05/07 – S&L has submitted Technical Specification for RAM study.
Separate meeting shall be held for the issue.
12/07 – Separate discussion is required with Total. S&L sent mail to
SEPCO on 14.06.2023. SEPCO to send feedback on the mail.
19/07 - S&L is finalizing it internally and shall respond ASAP.
02/08 – S&L has submitted a TQ for RAM study. SEPCO to check with
TTE.
2. 09/08 – Awaiting TTE’s response for the TQ raised earlier. S&L 14/06/23
23/08 - Awaiting TTE’s response for the TQ raised earlier.
30/08 – SEPCO to share the TQ reply from TTE.
06/09- No action as of now.
13/09- SEPCO advised S&L to share RAM specification with 3rd party.
20/09 – S&L is checking internally.
27/09- No action this week.
04/10 - No action this week.
11/10 - No action this week. SEPCO has discussed with Elia to
prepare the TQ.
01/11 - No action this week.
07/06: RAM Study: S&L will check internally and revert back on it.
14/06- S&L will send e-mail to SEPCO by 14.06.2023
21/06- S&L has sent a mail on 14.06.2023. SEPCO to respond.
05/07 – S&L has submitted Technical Specification for RAM study.
Separate meeting shall be held for the issue.
12/07 – Separate discussion is required with Total. S&L sent mail to
SEPCO on 14.06.2023. SEPCO to send feedback on the mail.
19/07 - S&L is finalizing it internally and shall respond ASAP.
02/08 – S&L has submitted a TQ for RAM study. SEPCO to check with
TTE.
2. 09/08 – Awaiting TTE’s response for the TQ raised earlier. S&L 14/06/23
23/08 - Awaiting TTE’s response for the TQ raised earlier.
30/08 – SEPCO to share the TQ reply from TTE.
06/09- No action as of now.
13/09- SEPCO advised S&L to share RAM specification with 3rd party.
20/09 – S&L is checking internally.
27/09- No action this week.
04/10 - No action this week.
11/10 - No action this week. SEPCO has discussed with Elia to
prepare the TQ.
01/11 - No action this week.
07/06: RAM Study: S&L will check internally and revert back on it.
14/06- S&L will send e-mail to SEPCO by 14.06.2023
21/06- S&L has sent a mail on 14.06.2023. SEPCO to respond.
05/07 – S&L has submitted Technical Specification for RAM study.
Separate meeting shall be held for the issue.
12/07 – Separate discussion is required with Total. S&L sent mail to
SEPCO on 14.06.2023. SEPCO to send feedback on the mail.
19/07 - S&L is finalizing it internally and shall respond ASAP.
02/08 – S&L has submitted a TQ for RAM study. SEPCO to check with
TTE.
2. 09/08 – Awaiting TTE’s response for the TQ raised earlier. S&L 14/06/23
23/08 - Awaiting TTE’s response for the TQ raised earlier.
30/08 – SEPCO to share the TQ reply from TTE.
06/09- No action as of now.
13/09- SEPCO advised S&L to share RAM specification with 3rd party.
20/09 – S&L is checking internally.
27/09- No action this week.
04/10 - No action this week.
11/10 - No action this week. SEPCO has discussed with Elia to
prepare the TQ.
01/11 - No action this week.
07/06: RAM Study: S&L will check internally and revert back on it.
14/06- S&L will send e-mail to SEPCO by 14.06.2023
21/06- S&L has sent a mail on 14.06.2023. SEPCO to respond.
05/07 – S&L has submitted Technical Specification for RAM study.
Separate meeting shall be held for the issue.
12/07 – Separate discussion is required with Total. S&L sent mail to
SEPCO on 14.06.2023. SEPCO to send feedback on the mail.
19/07 - S&L is finalizing it internally and shall respond ASAP.
02/08 – S&L has submitted a TQ for RAM study. SEPCO to check with
TTE.
2. 09/08 – Awaiting TTE’s response for the TQ raised earlier. S&L 14/06/23
23/08 - Awaiting TTE’s response for the TQ raised earlier.
30/08 – SEPCO to share the TQ reply from TTE.
06/09- No action as of now.
13/09- SEPCO advised S&L to share RAM specification with 3rd party.
20/09 – S&L is checking internally.
27/09- No action this week.
04/10 - No action this week.
11/10 - No action this week. SEPCO has discussed with Elia to
prepare the TQ.
01/11 - No action this week.
07/06: RAM Study: S&L will check internally and revert back on it.
14/06- S&L will send e-mail to SEPCO by 14.06.2023
21/06- S&L has sent a mail on 14.06.2023. SEPCO to respond.
05/07 – S&L has submitted Technical Specification for RAM study.
Separate meeting shall be held for the issue.
12/07 – Separate discussion is required with Total. S&L sent mail to
SEPCO on 14.06.2023. SEPCO to send feedback on the mail.
19/07 - S&L is finalizing it internally and shall respond ASAP.
02/08 – S&L has submitted a TQ for RAM study. SEPCO to check with
TTE.
2. 09/08 – Awaiting TTE’s response for the TQ raised earlier. S&L 14/06/23
23/08 - Awaiting TTE’s response for the TQ raised earlier.
30/08 – SEPCO to share the TQ reply from TTE.
06/09- No action as of now.
13/09- SEPCO advised S&L to share RAM specification with 3rd party.
20/09 – S&L is checking internally.
27/09- No action this week.
04/10 - No action this week.
11/10 - No action this week. SEPCO has discussed with Elia to
prepare the TQ.
01/11 - No action this week.
07/06: RAM Study: S&L will check internally and revert back on it.
14/06- S&L will send e-mail to SEPCO by 14.06.2023
21/06- S&L has sent a mail on 14.06.2023. SEPCO to respond.
05/07 – S&L has submitted Technical Specification for RAM study.
Separate meeting shall be held for the issue.
12/07 – Separate discussion is required with Total. S&L sent mail to
SEPCO on 14.06.2023. SEPCO to send feedback on the mail.
19/07 - S&L is finalizing it internally and shall respond ASAP.
02/08 – S&L has submitted a TQ for RAM study. SEPCO to check with
TTE.
2. 09/08 – Awaiting TTE’s response for the TQ raised earlier. S&L 14/06/23
23/08 - Awaiting TTE’s response for the TQ raised earlier.
30/08 – SEPCO to share the TQ reply from TTE.
06/09- No action as of now.
13/09- SEPCO advised S&L to share RAM specification with 3rd party.
20/09 – S&L is checking internally.
27/09- No action this week.
04/10 - No action this week.
11/10 - No action this week. SEPCO has discussed with Elia to
prepare the TQ.
01/11 - No action this week.
07/06: RAM Study: S&L will check internally and revert back on it.
14/06- S&L will send e-mail to SEPCO by 14.06.2023
21/06- S&L has sent a mail on 14.06.2023. SEPCO to respond.
05/07 – S&L has submitted Technical Specification for RAM study.
Separate meeting shall be held for the issue.
12/07 – Separate discussion is required with Total. S&L sent mail to
SEPCO on 14.06.2023. SEPCO to send feedback on the mail.
19/07 - S&L is finalizing it internally and shall respond ASAP.
02/08 – S&L has submitted a TQ for RAM study. SEPCO to check with
TTE.
2. 09/08 – Awaiting TTE’s response for the TQ raised earlier. S&L 14/06/23
23/08 - Awaiting TTE’s response for the TQ raised earlier.
30/08 – SEPCO to share the TQ reply from TTE.
06/09- No action as of now.
13/09- SEPCO advised S&L to share RAM specification with 3rd party.
20/09 – S&L is checking internally.
27/09- No action this week.
04/10 - No action this week.
11/10 - No action this week. SEPCO has discussed with Elia to
prepare the TQ.
01/11 - No action this week.
07/06: RAM Study: S&L will check internally and revert back on it.
14/06- S&L will send e-mail to SEPCO by 14.06.2023
21/06- S&L has sent a mail on 14.06.2023. SEPCO to respond.
05/07 – S&L has submitted Technical Specification for RAM study.
Separate meeting shall be held for the issue.
12/07 – Separate discussion is required with Total. S&L sent mail to
SEPCO on 14.06.2023. SEPCO to send feedback on the mail.
19/07 - S&L is finalizing it internally and shall respond ASAP.
02/08 – S&L has submitted a TQ for RAM study. SEPCO to check with
TTE.
2. 09/08 – Awaiting TTE’s response for the TQ raised earlier. S&L 14/06/23
23/08 - Awaiting TTE’s response for the TQ raised earlier.
30/08 – SEPCO to share the TQ reply from TTE.
06/09- No action as of now.
13/09- SEPCO advised S&L to share RAM specification with 3rd party.
20/09 – S&L is checking internally.
27/09- No action this week.
04/10 - No action this week.
11/10 - No action this week. SEPCO has discussed with Elia to
prepare the TQ.
01/11 - No action this week.
07/06: RAM Study: S&L will check internally and revert back on it.
14/06- S&L will send e-mail to SEPCO by 14.06.2023
21/06- S&L has sent a mail on 14.06.2023. SEPCO to respond.
05/07 – S&L has submitted Technical Specification for RAM study.
Separate meeting shall be held for the issue.
12/07 – Separate discussion is required with Total. S&L sent mail to
SEPCO on 14.06.2023. SEPCO to send feedback on the mail.
19/07 - S&L is finalizing it internally and shall respond ASAP.
02/08 – S&L has submitted a TQ for RAM study. SEPCO to check with
TTE.
2. 09/08 – Awaiting TTE’s response for the TQ raised earlier. S&L 14/06/23
23/08 - Awaiting TTE’s response for the TQ raised earlier.
30/08 – SEPCO to share the TQ reply from TTE.
06/09- No action as of now.
13/09- SEPCO advised S&L to share RAM specification with 3rd party.
20/09 – S&L is checking internally.
27/09- No action this week.
04/10 - No action this week.
11/10 - No action this week. SEPCO has discussed with Elia to
prepare the TQ.
01/11 - No action this week.
07/06: RAM Study: S&L will check internally and revert back on it.
14/06- S&L will send e-mail to SEPCO by 14.06.2023
21/06- S&L has sent a mail on 14.06.2023. SEPCO to respond.
05/07 – S&L has submitted Technical Specification for RAM study.
Separate meeting shall be held for the issue.
12/07 – Separate discussion is required with Total. S&L sent mail to
SEPCO on 14.06.2023. SEPCO to send feedback on the mail.
19/07 - S&L is finalizing it internally and shall respond ASAP.
02/08 – S&L has submitted a TQ for RAM study. SEPCO to check with
TTE.
2. 09/08 – Awaiting TTE’s response for the TQ raised earlier. S&L 14/06/23
23/08 - Awaiting TTE’s response for the TQ raised earlier.
30/08 – SEPCO to share the TQ reply from TTE.
06/09- No action as of now.
13/09- SEPCO advised S&L to share RAM specification with 3rd party.
20/09 – S&L is checking internally.
27/09- No action this week.
04/10 - No action this week.
11/10 - No action this week. SEPCO has discussed with Elia to
prepare the TQ.
01/11 - No action this week.
07/06: RAM Study: S&L will check internally and revert back on it.
14/06- S&L will send e-mail to SEPCO by 14.06.2023
21/06- S&L has sent a mail on 14.06.2023. SEPCO to respond.
05/07 – S&L has submitted Technical Specification for RAM study.
Separate meeting shall be held for the issue.
12/07 – Separate discussion is required with Total. S&L sent mail to
SEPCO on 14.06.2023. SEPCO to send feedback on the mail.
19/07 - S&L is finalizing it internally and shall respond ASAP.
02/08 – S&L has submitted a TQ for RAM study. SEPCO to check with
TTE.
2. 09/08 – Awaiting TTE’s response for the TQ raised earlier. S&L 14/06/23
23/08 - Awaiting TTE’s response for the TQ raised earlier.
30/08 – SEPCO to share the TQ reply from TTE.
06/09- No action as of now.
13/09- SEPCO advised S&L to share RAM specification with 3rd party.
20/09 – S&L is checking internally.
27/09- No action this week.
04/10 - No action this week.
11/10 - No action this week. SEPCO has discussed with Elia to
prepare the TQ.
01/11 - No action this week.
07/06: RAM Study: S&L will check internally and revert back on it.
14/06- S&L will send e-mail to SEPCO by 14.06.2023
21/06- S&L has sent a mail on 14.06.2023. SEPCO to respond.
05/07 – S&L has submitted Technical Specification for RAM study.
Separate meeting shall be held for the issue.
12/07 – Separate discussion is required with Total. S&L sent mail to
SEPCO on 14.06.2023. SEPCO to send feedback on the mail.
19/07 - S&L is finalizing it internally and shall respond ASAP.
02/08 – S&L has submitted a TQ for RAM study. SEPCO to check with
TTE.
2. 09/08 – Awaiting TTE’s response for the TQ raised earlier. S&L 14/06/23
23/08 - Awaiting TTE’s response for the TQ raised earlier.
30/08 – SEPCO to share the TQ reply from TTE.
06/09- No action as of now.
13/09- SEPCO advised S&L to share RAM specification with 3rd party.
20/09 – S&L is checking internally.
27/09- No action this week.
04/10 - No action this week.
11/10 - No action this week. SEPCO has discussed with Elia to
prepare the TQ.
01/11 - No action this week.
07/06: RAM Study: S&L will check internally and revert back on it.
14/06- S&L will send e-mail to SEPCO by 14.06.2023
21/06- S&L has sent a mail on 14.06.2023. SEPCO to respond.
05/07 – S&L has submitted Technical Specification for RAM study.
Separate meeting shall be held for the issue.
12/07 – Separate discussion is required with Total. S&L sent mail to
SEPCO on 14.06.2023. SEPCO to send feedback on the mail.
19/07 - S&L is finalizing it internally and shall respond ASAP.
02/08 – S&L has submitted a TQ for RAM study. SEPCO to check with
TTE.
2. 09/08 – Awaiting TTE’s response for the TQ raised earlier. S&L 14/06/23
23/08 - Awaiting TTE’s response for the TQ raised earlier.
30/08 – SEPCO to share the TQ reply from TTE.
06/09- No action as of now.
13/09- SEPCO advised S&L to share RAM specification with 3rd party.
20/09 – S&L is checking internally.
27/09- No action this week.
04/10 - No action this week.
11/10 - No action this week. SEPCO has discussed with Elia to
prepare the TQ.
01/11 - No action this week.
07/06: RAM Study: S&L will check internally and revert back on it.
14/06- S&L will send e-mail to SEPCO by 14.06.2023
21/06- S&L has sent a mail on 14.06.2023. SEPCO to respond.
05/07 – S&L has submitted Technical Specification for RAM study.
Separate meeting shall be held for the issue.
12/07 – Separate discussion is required with Total. S&L sent mail to
SEPCO on 14.06.2023. SEPCO to send feedback on the mail.
19/07 - S&L is finalizing it internally and shall respond ASAP.
02/08 – S&L has submitted a TQ for RAM study. SEPCO to check with
TTE.
2. 09/08 – Awaiting TTE’s response for the TQ raised earlier. S&L 14/06/23
23/08 - Awaiting TTE’s response for the TQ raised earlier.
30/08 – SEPCO to share the TQ reply from TTE.
06/09- No action as of now.
13/09- SEPCO advised S&L to share RAM specification with 3rd party.
20/09 – S&L is checking internally.
27/09- No action this week.
04/10 - No action this week.
11/10 - No action this week. SEPCO has discussed with Elia to
prepare the TQ.
01/11 - No action this week.
07/06: RAM Study: S&L will check internally and revert back on it.
14/06- S&L will send e-mail to SEPCO by 14.06.2023
21/06- S&L has sent a mail on 14.06.2023. SEPCO to respond.
05/07 – S&L has submitted Technical Specification for RAM study.
Separate meeting shall be held for the issue.
12/07 – Separate discussion is required with Total. S&L sent mail to
SEPCO on 14.06.2023. SEPCO to send feedback on the mail.
19/07 - S&L is finalizing it internally and shall respond ASAP.
02/08 – S&L has submitted a TQ for RAM study. SEPCO to check with
TTE.
2. 09/08 – Awaiting TTE’s response for the TQ raised earlier. S&L 14/06/23
23/08 - Awaiting TTE’s response for the TQ raised earlier.
30/08 – SEPCO to share the TQ reply from TTE.
06/09- No action as of now.
13/09- SEPCO advised S&L to share RAM specification with 3rd party.
20/09 – S&L is checking internally.
27/09- No action this week.
04/10 - No action this week.
11/10 - No action this week. SEPCO has discussed with Elia to
prepare the TQ.
01/11 - No action this week.
07/06: RAM Study: S&L will check internally and revert back on it.
14/06- S&L will send e-mail to SEPCO by 14.06.2023
21/06- S&L has sent a mail on 14.06.2023. SEPCO to respond.
05/07 – S&L has submitted Technical Specification for RAM study.
Separate meeting shall be held for the issue.
12/07 – Separate discussion is required with Total. S&L sent mail to
SEPCO on 14.06.2023. SEPCO to send feedback on the mail.
19/07 - S&L is finalizing it internally and shall respond ASAP.
Minutes of Meeting (date) 22 23