PAXcrane Complete Piping Installation Scope of Work Rev0 Instro
PAXcrane Complete Piping Installation Scope of Work Rev0 Instro
RFSD
MSD HVSD HASD [If OFFLINE EUSD ILSD
task, select appropriate GCSD
shutdown] LMSD
ONLINE ✘ OFFLINE
Responsible Work Group: PRJ EL
MM FAB BSC ✘
OPS
CRN PHRE CM ✘ SCA PCE
Equipment ID: 02-80-HT-012 CCM ✘ IN
Non-Stock
Description Manufacturer / Supplier Part No. Quantity
Operational Requirements
1 Ensure to walk through the entire scope with the construction party and operations to understand the works
4 Instrumentation team to prepare tubing fittings and tube supports 10 •Comply with Shop JSEA
•Do LLB
5 Instrumentation team to field install tubing fittings and supports 5 •Do LLB
•Comply with the field JSEA
•No live flames or hotwork in the PAX area
•Wear safety harness when working at heights
•Fumes, wear breathing mask when working near
the mixing tank