Maydous Housing Colony Phase-II

Samundri Road, Faisalabad


Contract Agreement
Subject: QUOTATION FOR INSTALLATION OF GAS PIPE LINE (MDPE PIPE), DISTRIBUTION
NETWORK AT Maydous Housing Colony Phase-II, Samundri Road, FAISALABAD.

Sr. # Description Quantity Rate (Rs) Remarks


Installation of Gas Pipe Line Per Meter 3,585 Actual Qty
(MDPE) with Digging, Re-filling with Measure as
Dismantled loose earth excluding per actual
Re-in statement, joining, Laying work done
testing including complete with all at site
labor, tools, accessories, and
consumable as per SNGPL,s
standards and specification. (All
pipe Lines (MDPE) should be
provided)
As above installation of Gas Pipe
1 Line (MDPE) 4” Dia
Third Party Inspection SNGPL
1. GD
2. Packing List
3. Authority letter of
Manufacturers
4. Material Test Report of SNGPL
As above installation of Gas Pipe
Per Meter 1885 “
Line (MDPE) 2” Dia
As above installation of Gas Pipe
Per meter 1310 “
Line (MDPE) 1.25” Dia
Proving and installation of Gas Pipe 1 (piece) 8,50,000 “
Line’s valve 150 Clause with all 1. GD
accessories , construction of 2. Packing List
chamber complete in all respect as 3. Authority letter
per SNGPL’s standard’s and of Manufacturers
specification. 4. Material Test
As above installation of Gas Valve Report of SNGPL
4” Dia
2 Proving and installation of Gas Pipe 1 (piece) 4,10,000 “
Line’s valve 150 Clause with all 1. GD
accessories , construction of 2. Packing List
chamber complete in all respect as 3. Authority letter
per SNGPL’s standard’s and of Manufacturers
specification. 4. Material Test
As above installation of Gas Valve Report of SNGPL
2” Dia

TERMS & CONDITIONS:

1. All the MDPE pipe will be provided by the Contractor.


2. Staff & labor of the contractor, accommodation will be provided.
3. All the utilities, electricity, water and etc. will be provided at the site by the client.
4. Reinstatement of the damages due to construction, road cut, horticulture, cables, water
supply, sewerage, telecom and etc. will be executed by the client.
5. All MDPE pipe line accessories will be provide by the contractors.
6. Labor, tools needed for installation of MDPE pipe line will be provided by the contractor.
7. The execution of contract and the quality of work will be as per standards of SNGPL.
8. Material inspection is responsibility of contractor.Material Testing Lab Report (SNGPL)
9. Testing by contractor.
10. Handover to SNGPL by contractor.
11. (Tiein job)
12. Complete Gas Pipe Line work, and all work for SNGPL Department Dealing by Contractor
PAYMENTS:

1. Total work charges 60% advance, 20% during work and 15% on work completion and 5%
after testing
2. All work completion than final payment cleared by the company.
3. After completion the work 100 pounds pressure testing.
4. This rate included income tax.

Regards,

Abid Javed