0904-2 - Exercise of Airport Terminal Planning (Question
0904-2 - Exercise of Airport Terminal Planning (Question
Exercise Challenge
Question
17 September 2019
1. Exercise challenge
2. Precondition
3. Prediction of civil aviation demand
4. Calculation of the necessary size of facilities and required land area
4-1. Apron Plan(Spot, GSE yard)
4-2. Passenger Terminal Area Plan
(Passenger Terminal Building, Parking Area)
4-3. Cargo Terminal Area Plan
4-4. Fueling Facility Area Plan
4-5. Administration Facility Area Plan
(Administration office and control tower, Power supply facilities ,
Fire-fighting and rescue facilities)
4-6. Small Aircraft Facility Area Plan
5. Creating of Airport Terminal Area Plan
2
1. Exercise challenge
Exercise challenge : To make the New Kitakyushu Airport Terminal Area Plan
Planning point in time of this exercise : 2002 (You are in 2002, now.)
Target year : Facilities Size : 2012
Land Area : 2017
1.Summary of New Kitakyushu Airport
・ Installer : Minister of Land, infrastructure and Transport
・ Administrator : Minister of Land, infrastructure and Transport
・ Location : Kitakyushu-City
・ Area : 159ha
・ Runway : (length x width) : 2,500 m x 60 m, (Direction) : 18/36
・ Operation time : 24 hours
Kitakyushu Airport
Terminal Area
3
1. Exercise challenge
2.Background
・ The existing Kitakyushu Airport has a short runway of 1,600 m, and it is difficult to extend the
runway because there are mountains and urban areas around it.
・ So, it has been decided to construct the New Kitakyushu Airport with a runway of 2,500m on
the offshore sea of the old airport.
・ The artificial island for the new airport is under construction now.
・ You must to make the Terminal Are Plan for the airport.
existing Airport
Old Kitakyushu airport
Kitakyushu
4
2. Precondition
(1) Precondition
5
2. Precondition
2,870
Apron
990m
6
3. Prediction of civil aviation demand
Annual number of
2,832,656 3,284,749 3,493,948
passengers (person) Osaka
Annual cargo handling Tokyo
18,830 21,840 23,230 Kitakyushu
volume (ton) Chubu
Kansai
(2) Annual number of passengers by route, Aircraft take-offs / landings Miyazaki
by type, Annual cargo handling volume Naha
Kagoshima
(※ JJ : B747 etc.,LJ : B777 etc.,MJ : B767 etc.,SJ : MD90,B737 etc., PR : DHC8 etc. )
2007 2012 2017
Aircraft JJ LJ MJ SJ PR JJ LJ MJ SJ PR JJ LJ MJ SJ PR
Aircraft JJ LJ MJ SJ PR JJ LJ MJ SJ PR JJ LJ MJ SJ PR
(Example)
Apron
72 445 GSE yard for the passenger terminal
40.5 59.5 72.5 72.5 59.5 59.5 40.5 40.5 and cargo terminal
190
JJ / LJ JJ / LJ
Apron shoulder
25
GSE lane
Passenger terminal
building
Cargo terminal
9
4.Calculation of the necessary size of facilities and required land area
4-2-1. Calculation of the size of the domestic passenger terminal building and required land area
2007 2012 2017
A:Annual number of passengers
(person)
b:Peak day concentration ratio
C:Number of peak day passengers
(person)
d:Peak hour concentration ratio
E:Number of peak hour passengers (person)
f:Floor area of passenger terminal building per
peak hour passenger (㎡/person)
G:Required floor area of passenger
terminal building (㎡)
h:Terminal building level factor
I: Building area of terminal building (㎡) Terminal building land
Terminal
building site
m:Land area ratio for terminal building
N:Land area of terminal building (㎡)
10
4.Calculation of the necessary size of facilities and required land area
4-3-1. Calculation of the floor area of the cargo terminal building and required land area
2007 2012 2017
Cargo Terminal A:Annual cargo handling volume (ton)
(Building plan )
Layout scheme for cargo facilities Separate (Separate arrangement of airline shed and agent’s building )
b:Cargo handling volume per unit
(ton/㎡)
C:Area of airline shed (㎡)
d:Composition ratio of area of airline
shad and agents’ building
E:Area of agent’s building (㎡)
The total floor area of cargo terminal
building (㎡) (C+E)
Cargo Terminal f1:Depth of Airline shed (m) 20 20 20
(Land plan) Case2:Separate
G:Frontage of land area for cargo
terminal (m)
f2:Depth of agent’s building (m) 10 10 10
GSE zone
h1:Landside area ①depth (m) Embedded piping zone
Airside area
h2:Landside area ②depth (m) ※ 10 10 10
i
f1
J : Landside area (㎡) Airline shed
i :Airside depth (m)
K : Airside area (㎡) 5m
h1
5m Landside area ①
Depth of land area for cargo terminal
(m) (f1+f2+h1+h2+i)
f2
Agent’s building
L:Land area for cargo terminal (㎡)
Landside area ②
h2
( G (f1+f2+h1+h2+i))
G
※ Although the standard depth of the landside area ② is 15 m, it shall be 10 m here.
11
4.Calculation of the necessary size of facilities and required land area
4-4. Fueling Facility Area Plan
4-4-1. Calculation of size of fueling facilities and required land area
Route 2007 2012 2017
Route distance
(km) total JJ LJ MJ SJ total JJ LJ MJ SJ total JJ LJ MJ SJ
A : Peak day aircraft take
- - -
Shin- -offs by type and route
1,530 b : Fuel consumption(kl) - - -
Chitose
C : Peak day fuel supply (kl)
A : Peak day aircraft take
- - -
-offs by type and route
Tokyo 911 b : Fuel consumption(kl) - - -
C : Peak day fuel supply (kl)
A : Peak day aircraft take
- - -
-offs by type and route
Chubu 663 b : Fuel consumption(kl) - - -
C : Peak day fuel supply (kl)
A : Peak day aircraft take
- - -
-offs by type and route
Osaka 515 b : Fuel consumption(kl) - - -
C : Peak day fuel supply (kl)
A : Peak day aircraft take
- - -
-offs by type and route
Kansai 500 b : Fuel consumption(kl) - - -
C : Peak day fuel supply (kl)
A : Peak day aircraft take
- - -
-offs by type and route
Miyazaki 341 b : Fuel consumption(kl) - - -
C : Peak day fuel supply (kl)
A : Peak day aircraft take
- - -
Kagoshi -offs by type and route
374 b : Fuel consumption(kl) - - -
ma
C : Peak day fuel supply (kl)
A : Peak day aircraft take
- - -
-offs by type and route
Naha 1,050 b : Fuel consumption(kl) - - -
C : Peak day fuel supply (kl)
ΣC:(The total of) Peak day fuel supply (kl)
d:Number of days fuel is held (day)
E:Required fuel storage(kl)
f:Required number of tanks 2 2 3
Frontage(X) 100
Depth(Y) 85
G:Land area for the fueling facility area(㎡) 8,500
11
12
4.Calculation of the necessary size of facilities and required land area
4-5-1. Building size and land area for the administration office and control tower
4-5-2. .Building size and land area for power supply facilities
4-5-3. Building size and land area for fire-fighting and rescue facilities
2007 2012 2017
13
4.Calculation of the necessary size of facilities and required land area
○ Size of small aircraft facilities and land area shall be used as follows.
4-6-1. Apron for small aircrafts 4-6-2. Hangar for small aircrafts
Apron for small aircraft shall be planed as follows. Hanger and land area for small aircraft shall be planed as follows.
a rotor
Clearance
Full length of a fixed
Full width of
Full length of
Clearance
Clearance
Clearance
Clearance
Shoulder
Full width of
a rotor
a rotor
a rotor
14
5. Creating of Airport Terminal Area Layout Plan
You should create “Airport Terminal Layout Plan” in the red broken line frame
Airport
access road
52m
(Sea)
990m
15