Document Information Page

Document Classification and Version Document Status and Release Date


Classification Status
Document Version: Released Date

Document Name:
Document ID:
Version:
Location
Owner
Author
Reviewed by
Reviewed by
Approved by

Amendment History
Document Version Date Modified By Section, Pages, Description

Restricted
Purpose
The purpose of Daily Operations Meeting serve as a tracking platform for both STT and site specific Facilities Management
(FM) Team to ensure all daily and follow up action activities are recorded and conduct accurately.

Objective
The main objective of daily operations meeting is to keep track for upcoming weekly schedule, rack power up, provisioning
and Incidents activites that require follow up and to ensure all planned activities are executed in accordance to the schedule.

Process
1) The daily operations meeting template are sorted into individual tabs. There are Weekly Schedule, Rack Power Up,
Provisioning and Incidents.

2) Both STT and FM Team are to schedule daily recurrence meeting to discuss on the progress of the Daily Operations
Meeting presented by the Day shift personel.

3) Night shift personel will check and update if there are any amendments that need to be done.

4) All daily operation meeting activities for the day itself will be highlighted in the meeting and all necessary information are to
be filled in the remarks column on the latest information provided.

5) Upon completion of activity in Weely Schedule and Incident tabs, STT Team will ensure all service reports are submitted.

Restricted
DAILY OPERATIONS MEETING
Site Name:

Date:

WEEKLY SCHEDULE

MAINTENANCE

Ticket Number

ELECTRICAL
C-009385
C-009387
C-009400
C-008488
C-009297
C-010307
C-010290
C-010300
C-009406
C-009597

ACMV
C-007572
C-008895
C-009407
C-008512

ECMS/CMS/BMS systems

SECURITY SYSTEMS
C-009776
C-009777

BUILDING
C-009415

Client / STT
Projects

DLP ADHOC PM

ADHOC
OPERATIONS MEETING
STT MAKATI

3 March, 2024

Description

Monthly KVA Reading for March 2024 at MK2


Monthly PM of Panelboards
Quarterly Thermal Scanning
Generator System 1-9 Monthly No Load Test for the month of March 2024
INSTALLATION OF EQUALIZATION LINE AND REDUNDANT LINE TO GENSET 7, 8 AND 9
PM and Changeoil of Genset 1-4 at MK2
PM and Changeoil of Genset 5-9 at MK2
PM of Synchronizing Panel Serving Genset 1-4
Non-Intrusive PM of 10 x UPS Symmetra
Power Tapping and Energization of 4 units panelboards.

MONTHLY PREVENTIVE MAINTENANCE OF FAN COIL UNITS


Installation of Air Deflector for PACU 4D
MK2-QUARTERLY-PM of AHU Serving Zone B
PM at Telco 1,3,5&6

MS/BMS systems

Quarterly PM of CCTV
Quarterly PM of Access Control System

Monthly General Pest Control


Night Shift Team:

Day Shift Team:


Customer Access
Ticket Status Customer Affected
Approval

Approved NA NA
Approved NA NA
Approved NA NA
Approved NA NA
Approved NA NA
Approved NA NA
Approved NA NA
Approved NA NA
Approved NA NA
Approved NA NA

Approved NA NA
Approved NA NA
Approved NA NA
Approved NA NA

Approved NA NA
Approved NA NA

Approved NA NA
Darledi Domino

Lyka Nazareno / Paul Cansino


Start date End date Door Isolation Fire System Isolation

11-Mar-24 31-Mar-24 NA NA
1-Mar-24 31-Mar-24 NA NA
1-Mar-24 31-Mar-24 NA NA
16-Mar-24 31-Mar-24 NA NA
1-Mar-24 10-Apr-24 NA NA
8-Mar-24 9-Mar-24 NA NA
10-Mar-24 12-Mar-24 NA NA
13-Mar-24 13-Mar-24 NA NA
20-Mar-24 21-Mar-24 NA NA
8-Mar-24 12-Mar-24 NA NA

1-Mar-24 31-Mar-24 NA NA
7-Mar-24 14-Mar-24 NA NA
7-Mar-24 9-Mar-24 NA NA
21-Mar-24 23-Mar-24 NA NA

25-Mar-24 31-Mar-24 NA NA
25-Mar-24 31-Mar-24 NA NA

24-Mar-24 24-Mar-24 NA NA
Remarks/Update

Ongoing
Ongoing

Ongoing

Ongoing
DAILY OPERATIONS MEETING
Site Name: STT MAKATI
Date: 3 March, 2024
PROVIS
Client Provisioning number
DICT R-010414

Night Shift Team:

Day Shift Team:


PROVISIONING / CROSS CONNECT
Racks/Cross Connect
Rack 11 and Rack 12

Darledi Domino

Lyka Nazareno / Paul Cansino


VISIONING / CROSS CONNECT
Date/Time
March 01, 2024 / 1930H
Remarks
Power Up Validation
DAILY OPERATIONS MEETING
Site Name: STT MAKATI

Date: 3 March, 2024

Client User Request Number

Night Shift Team:

Day Shift Team:


RACK ENERGIZATION

Number of Racks

Darledi Domino

Lyka Nazareno / Paul Cansino


RACK ENERGIZATION

Date/Time
Remarks
DAILY OPERATIONS MEETING
Site Name: STT MAKATI

Date: 3 March, 2024

Date Created Ticket Number Type/Category

I-003869
26-Aug-23

I-009849
15-Feb-24
I-007242
28-Nov-23

Night Shift Team:

Day Shift Team:


INCIDENTS

Description

UPS System

Electrical

ATS 2 failure to transfer emergency power to normal


power automatically

ACMV

Zone A PACU 7A Oil Leak on Compressor System 2

Fire Protection System


Fire Alarm at Zone E (FL VOID SD 5)

LIFT

ECMS/CMS/BMS systems

SECURITY

Others

Darledi Domino

Lyka Nazareno / Paul Cansino


INCIDENTS

Remarks/Update Status

UPS System

Electrical

TAC Action Taken:


Action 1: Transfer LVSG 2 to LVSG 1
To avoid manual transfer incase of power interruption
Action 2: Call the vendor hotline. Pending for Rectification

Vendor ETA: ongoing coordination

Next Update: Aug 26 2023 / 1700H


ACMV

Subject: Zone A PACU 7A Oil Leak on Compressor System 2


Incident Occurrence Date: 15 February 2024
Incident Occurrence Time: 1622H
Customer Impact: No
Severity: Low
Level of Redundancy: N+1

Elaboration: Vendor found oil leak on Compressor during Pending for Rectification
Preventive Maintenance.

Vendor Actio Taken:


Action 1: Check sight glass level - Low Oil Level
Action 2: Change Temp Setpoint from 18 to 20deg
Action 3: Request for replacement of compressor or System
reprocess.

TAC Action Taken:


Action 1: Coordinate with Vendor - waiting for quotation

Note: PACU 7A System 1 is in Normal Operation

Fire Protection System


Vendor Actions Taken:
Action 1: PACU 2E still under monitoring (24hrs)
Action 4: As for the NN100 Refill, 2 vendors done in site survey on
NN100 - awaiting for feedback on the availability of equipment to
refill the NN100. Pending for Rectification

Note: Continues monitoring of the area and other data halls by the
firewatchers / responders.
Data Halls, UPS Rooms and Power Centers are in normal
operations

LIFT

ECMS/CMS/BMS systems

SECURITY

Others
Date of next update RCA Status