Professional Documents
Culture Documents
11-Directing A Project
11-Directing A Project
Directing a Project
Dr. Ahmed Taha, PhD, PMP, PMI-RMP, ITIL, PMOC, CBAP, PRINCE2, CBA
www.pmhouse.org
Directing a Project
The purpose of the Directing a Project Process is to enable the Project Board to be
accountable for the project by making key decisions, and to have overall control
Page ▪ 2 www.pmhouse.org
The Objectivs
The objectives of Directing a Project Process are to:
➢ Provide authority to deliver the project’s products. The products are the reason to do the project.
Page ▪ 3 www.pmhouse.org
Process Overview
Page ▪ 4 www.pmhouse.org
Process Overview
➢ The Project Board provides guidance to the Project Manager throughout the project and the Project
Manager can seek advice at any time
➢ The Project Board is responsible for ensuring that there is continued business justification and can
decide to shut down the project if the Business Case becomes no longer viable
Page ▪ 5 www.pmhouse.org
Authorize initiation
Page ▪ 6 www.pmhouse.org
Authorize the project
Page ▪ 7 www.pmhouse.org
Authorize a Stage or Exception Plan
Page ▪ 8 www.pmhouse.org
Give ad hoc Direction
Page ▪ 9 www.pmhouse.org
Give ad hoc Direction
Response to an Issue Report (that exceeds the Project Manager’s tolerances):
➢ If the issue is a big problem or concern, the Project Board can ask for an Exception Plan.
➢ If the issue is a change request or an off-specification, they can decide to accept it or not.
This is the regular report delivered to the Board by the Project Manager during the Controlling a Stage process.
The Board will review it and may decide to make comment.
Page ▪ 10 www.pmhouse.org
Give ad hoc Direction
Response to an Exception Report (used by the Project Manager when he/she believes the stage
will go out of one or more of its tolerances) :
➢ Increase the tolerances for the Project Manager so that the stage can be completed.
➢ Ask to Produce an Exception Plan so that the existing stage can be completed.
Page ▪ 11 www.pmhouse.org
Authorize Project Closure
Page ▪ 12 www.pmhouse.org
Page ▪ 14 www.pmhouse.org
Q1
A
Page ▪ 15 www.pmhouse.org
Q2
C
Page ▪ 16 www.pmhouse.org
Q3
D
Page ▪ 17 www.pmhouse.org
Q4
D
Page ▪ 18 www.pmhouse.org
Q5
A
Page ▪ 19 www.pmhouse.org
THANKS
Page ▪ 20 www.pmhouse.org