Download as pdf or txt
Download as pdf or txt
You are on page 1of 19

PRINCE 2

Directing a Project

Dr. Ahmed Taha, PhD, PMP, PMI-RMP, ITIL, PMOC, CBAP, PRINCE2, CBA

www.pmhouse.org
Directing a Project

The purpose of the Directing a Project Process is to enable the Project Board to be

accountable for the project by making key decisions, and to have overall control

Page ▪ 2 www.pmhouse.org
The Objectivs
The objectives of Directing a Project Process are to:

➢ Provide authority to initiate the project.

➢ Provide authority to deliver the project’s products. The products are the reason to do the project.

➢ Provide direction and control during the project.

➢ Be the interface to Corporate or Program Management.

➢ Provide authority to close the project.

➢ Ensure that post-project benefits will be reviewed

Page ▪ 3 www.pmhouse.org
Process Overview

Page ▪ 4 www.pmhouse.org
Process Overview
➢ The Project Board provides guidance to the Project Manager throughout the project and the Project
Manager can seek advice at any time

➢ The Project Board is responsible for ensuring that there is continued business justification and can
decide to shut down the project if the Business Case becomes no longer viable

Page ▪ 5 www.pmhouse.org
Authorize initiation

Page ▪ 6 www.pmhouse.org
Authorize the project

Page ▪ 7 www.pmhouse.org
Authorize a Stage or Exception Plan

Page ▪ 8 www.pmhouse.org
Give ad hoc Direction

Page ▪ 9 www.pmhouse.org
Give ad hoc Direction
Response to an Issue Report (that exceeds the Project Manager’s tolerances):

➢ If the issue is a big problem or concern, the Project Board can ask for an Exception Plan.

➢ If the issue is a change request or an off-specification, they can decide to accept it or not.

Response to a Highlight Report:

This is the regular report delivered to the Board by the Project Manager during the Controlling a Stage process.
The Board will review it and may decide to make comment.

Page ▪ 10 www.pmhouse.org
Give ad hoc Direction
Response to an Exception Report (used by the Project Manager when he/she believes the stage
will go out of one or more of its tolerances) :

➢ Increase the tolerances for the Project Manager so that the stage can be completed.

➢ Ask to Produce an Exception Plan so that the existing stage can be completed.

➢ Instruct the Project Manager to close the project prematurely.

Page ▪ 11 www.pmhouse.org
Authorize Project Closure

Page ▪ 12 www.pmhouse.org
Page ▪ 14 www.pmhouse.org
Q1

A
Page ▪ 15 www.pmhouse.org
Q2

C
Page ▪ 16 www.pmhouse.org
Q3

D
Page ▪ 17 www.pmhouse.org
Q4

D
Page ▪ 18 www.pmhouse.org
Q5

A
Page ▪ 19 www.pmhouse.org
THANKS

Page ▪ 20 www.pmhouse.org

You might also like