Professional Documents
Culture Documents
CH 052
CH 052
CH 052
ABSTRACT: In the execution of the lot E52 of the Brenner Base Tunnel, environmen-
tal challenges were mastered for reduceing the environmental impact and sparing
resources. According to the geological preliminary investigations, the Bündner Schist
which formerly should be deposited was released for recycling on the basis of intensive
geological and engineering investigations. After beginning the construction phase, the
project partners planned cooperatively to implement the recycling of tunnel spoil not
previously used in Austria. Within a few months, the necessary steps of sampling, trial
production, laboratory tests for decisions and technical development were carried out.
The complexity of this topic is presented and the measures for quality control and adap-
tion of process cycles are displayed. With the implementation of tunnel spoil recycling at
“Erkundungslos Padastertal + Wolf II”, BBT-SE mastered important steps for planning
and concrete execution of further construction lots as well as an innovative path for the
construction industry.
1 INTRODUCTION
The Brenner Base Tunnel is the key structure of the trans-European North-South link
between Helsinki and Valletta (Malta). The construction of the North-South corridor is
part of the TEN Strategic Plan to cope with the increasing movement of goods and
people. The strategic plan gives priority to the development of the rail infrastructure, the
Brenner Base Tunnel is subject to the highest funding from the European Union due to
its importance.
Lot Wolf II is part of the Brenner Base Tunnel and essentially comprises the following con-
struction measures:
• 4 000 m access tunnel, excavation area 120 m², via which the central construction site logis-
tics for the subsequent main construction lot must be ensured
• Connecting cavern, branch cavern, fan cavern, excavation areas 230–350 m²
• 950 m spoil removal tunnel, excavation area approx. 60 m²
• 180 m cross-connection tunnel from access tunnel to exploration tunnel
• 1 140 m diversion tunnel for Padasterbach, excavation area 26 m²
• 360 m diversion tunnel for Padasterbach in open construction method
• 145 m transverse drainage tunnel, excavation area 10 m²
• 700 m inner lining Padastertunnel
• 1 000 m inner lining Saxenertunnel, connection tunnel to motorway A13
• Hydraulic structures (bed load barriers, intake structures, fish ponds etc.) in the Padastertal
• Landfill construction of the landfill Padastertal
All tunnels of this lot were excavated by blasting. The contract value of the construction lot
was approx. 104 million euros, construction began on December 4th 2013.
495
Figure 1. Lot Wolf II, E52 (picture: BBT SE).
On the basis of the Waste Management Law (Abfallwirtschaftsgesetz - AWG), with the target of
“recycling of waste” (see AWG §1 and §8 (3)), the Brenner Base Tunnel BBT SE commissioned
studies involving the University BOKU Vienna and external experts to examine the main litholo-
gies of the Austrian project area (Innsbruck Quartzphyllite and Bündner Schist) for the possibil-
ity of processing aggregates for concrete and filter material. Since no mining operator in
Austria used Bündner Schist for concrete at that time, its suitability as aggregate was unclear.
Investigations for Bündner Schist (see e.g. (Voit, K 2013)) have shown that Schist prepared by
crushing, screening and washing is suitable for the aggregate production for shotcrete as well as
for structural concretes. In contrast, the suitability of the Innsbruck Quartzphyllite, which is to
be found in the northern project area, as aggregate for structural concretes could not be proven.
In the course of the construction of the lot Wolf II, innovative steps were taken to optimise
material logistics and valuable experience was gained in the use of prepared tunnel spoil as aggre-
gate for concrete production. Mainly shotcrete (almost 100 000 m³) was produced out of tunnel
spoil.
Processing and recycling of tunnel spoil brought the following positive aspects for the project:
• Use of processed tunnel spoil and thus cost reduction for inert materials to be purchased
externally
• Reduction of landfill volume
• Avoid any transport of inert materials outside of the site
• Compliance with AWG requirement that tunnel spoil is recycled
• Improvement of the life cycle assessment (e.g. CO2, SO2, non-renewable energy and min-
eral resources according to (BBT-intern, 2015)
3 RECYCLING CONCEPT
With regard to processing and production of the fractions, an optimal concept suitable for
construction site had to be found.
The Bündner Schist is characterised above all by its good fissile strength along the shearing sur-
faces and its flat appearance. In order to produce suitable aggregates for concrete production, the
individual crushing stages were therefore selected primarily to achieve the required grain shape.
For this purpose and to obtain fractions for working out mix designs two processing trials
were carried out in December 2013 and March 2014 with the following plant constellation (see
(Voit, K 2013)):
496
• Test series 1: Jaw crusher - impact mill
• Test series 2: Jaw crusher - Impact mill - Vertical mill
Test series 1 showed that the production of aggregates from Bündner Schist is basically pos-
sible, but that it is difficult to achieve the required grain shape. It was therefore decided to
additionally use a third crushing stage in the form of a vertical mill. Vertical mills are mainly
used to achieve as cubic a grain shape as possible and subsequently as low an LA value as
possible.
Based on findings from the tests, the planning of the plant in Wolf was started in March
2014 and should meet the following requirements (see also (Bergmeister, K., Kogler, H.,
Murr, R., Cordes, T. & Arnold R., 2016)):
• low space requirement
• rapid availability
• flexible system constellation
• low treatment losses
• acceptable investment costs
497
changeover of the crushing stages in order to be able to react to changes in demand with a
short-term back-crushing of surplus granulations.
498
4.1 Binderpaste- and Mortar Tests
In order to optimise the choice of setting accelerator and to improve the coordination between
setting accelerator and binder combination, tests were carried out in the laboratory to deter-
mine the setting times, compressive strength development at a young age (3h to 24h) and the
loss of strength at the age of 7 days compared to the unaccelerated mortar. The tests were
carried out in accordance with the guideline on shotcrete (Austrian Society for Construction
Technology öbv, 2009), the results of which are shown in Figures 3 to 5.
When determining the setting acceleration, it was found that the required setting acceleration
was achieved with significantly different dosing heights for the various products. During the test,
the mixing in of some combinations of accelerator and binder very quickly led to clumping and
inhomogeneities in the accelerated binder paste due to the high reactivity. It was also shown that
accelerator products which allowed high early strengths within the young age (tested up to 24h)
showed a higher loss of strength compared to the non-accelerated zero mortar.
Based on this, a binder combination of a CEM I 52.5 N and a CEM II/A-M 42.5 N in a
ratio of 50% to 50% and the addition of a hydraulically reactive additive type II (AHWZ) was
selected in the application, which significantly reduced lump formation and the occurrence of
Figure 3. Determination of the setting acceleration of binder paste with different setting accelerators
Products.
Figure 4. Determination of the compressive strength development of accelerated binder paste in cylin-
drical test specimens with different setting accelerators Products.
Figure 5. Determination of the loss of strength of accelerated mortar prisms with different accelerated
setting products at the age of 7 days.
499
inhomogeneities. The drop in strength determined on the mortar prism at the age of 7 days
was between 8% and 22%, depending on the product, compared with the unaccelerated zero
mortar, see Figure 5.
The shotcrete SpC25/30(120)/II/J2/XC4/GK8 was used in the period from December 2014 to
April 2016 with a compacted monitoring to ensure the uniformity of the paving quality. The
formulation of the sprayed concrete is listed in Table 1 (see also (BBT, 2016)). The evaluation
of the installed shotcrete quality was carried out using the available test documents:
• Recipe check from 18th December 2014
• Conformity tests in the period between December 2014 and April 2016
• Identity tests between December 2014 and April 2016
• Component testing (drill core removal)
• Additional tests (Youngs-modulus test, frost resistance test XF3)
500
curve J2 showed a slight underrun in individual samples at an age of approx. 3–9 hours. A
higher EB dosage leads to a reduction of the strength development at an age of >28 d.
The evaluation of the shotcrete test according to ÖVBB guideline shotcrete (öbv, 2009) and
ÖNORM EN 13791 according to Table 2 led to a confirmation of the required compressive
strength:
Table 2. Evaluation of the tests according to (öbv, 2009) and ÖNORM EN 13791 (BBT, 2016)).
SpC25/30
Minimum Characteristic Demanded Attained
Compressive strength fck,is (MPa) Conformity testing
Identity testing including
Drill Core (L/D=1/1) (MPa) (MPa) Structural testing
26
From the mean value criterion
Estimated characteristic
Compressive strength fck,is 26.8 26.2
From the single value criterion
Estimated characteristic
compressive strength fck,is 29.5 30.0
501
6 STUDIES TO OPTIMICE MIX DESIGN
Based on the experience gained, investigations were carried out for further recipe optimisa-
tion. Since it had to be established during the execution that the water demand of the pro-
cessed aggregates was very high despite adjustment of the grading curve and optimised
concrete admixture, the possibility of reducing the water demand by partial to complete
replacement of the processed aggregate fraction 0/4 was investigated. In the investigations, the
percentages of the tunnel excavation sand 0/4 were gradually replaced by a calcitic sand 0/4. If
the sand is replaced, it is increasingly necessary to adjust the additive dosages or products for
the individual mixtures (e.g. also the air-entraining agents). The following mixtures were com-
pared, whereby the binder remained unchanged:
The proportion of aggregates remained uniform in the investigations, but with different
compositions of the individual fractions:
502
compressive strength decreases by 5%. Under this assumption, the following table shows the
compressive strength for the existing air content of the test specimens and the compressive
strength related to the calculated air content of 5.0%.
It can be seen that with the increasing replacement of tunnel spoil 0/4 by calcitic sand 0/4,
the compressive strength of the concrete also increases and that this is mainly expressed in the
possibility of water saving. The following figure illustrates this relationship:
Figure 7. Concrete Strength Curve for NM, M20, M35 and M50 Mixes.
This simple estimation results in a mass ratio of shotcrete to rock in the landfill of approx.
4%. A similar value resulted from a back-calculation of the actual masses for the lot H33
Tulfes-Pfons. The proportion of rebound is relatively low (approx. 1%), the more important
part is the shotcrete used to secure the face of the village.
503
Table 8. Ratio of excavated to recycled rock volume for lot Wolf II.
Year Quantity excavated Quantity recycled Mass percentage
(-) (to) (to) (%)
2013 20.500 0 0
2014 764.000 0 0
2015 600.000 140.000 23
2016 341.250 100.000 29
2017 20.500 0 0
Total 1.746.250 240.000 14
8 CONCLUSION
This article gives an overview of the developed processing concept and a description of the
current shotcrete technology with the experience of the material processing of Bündner Schist
as aggregates for concrete production in the construction of the Brenner Base Tunnel. In the
successful pilot project lot Wolf II, it was shown that the processed Bündner Schist is well
suited as aggregate for shotcrete and structural concrete. The processed tunnel spoil was used
to successfully supply aggregates for 144 000 m³ of concrete. Furthermore, in concrete tests it
was determined that the concrete strength can be increased by replacing tunnel spoil 0/4 with
calcitic sand 0/4. The recylcling of tunnel spoil improve the sustainability of the project by
reducing the environmental impact and sparing resources.
REFERENCES
BBT-internal report, 2015, E52 Life Cycle Assessment (LCA), Ökobilanzstudie Variantenuntersuchung
Spritzbeton.
BBT-internal report, 2016, quality evaluation sprayed concrete, Wolf E52 intern
Bergmeister, K. & Kogler, H. & Murr, R. & Cordes, T. & Arnold R., 2016: Brenner Basistunnel Innova-
tionen zur Aufbereitung des Tunnelausbruchmaterials und Optimierung der Betonzusammensetzung.
Zement+Beton 1, Page 48–57
Bundesministerium Nachhaltigkeit und Tourismus, 2002, Abfallwirtschaftsgesetz AWG
Österreichische Vereinigung für Beton und Bautechnik, 2009, Guideline Shotcrete.
Swiflty Green, 2015, Report “Infrastructure spatial planning and environmental effects” https://www.swif
tlygreen.eu
Voit K. 2013: Einsatz und Optimierung von Tunnelausbruchsmaterial des Brenner Basistunnels, Phd-
Thesis, University of Natural Resources and Life Sciences, Vienna
Wesche, K. 1993: Baustoffe für tragende Bauteile, Band 2, Beton und Mauerwerk, Bauverlag GmbH.
Wiesbaden und Berlin.
Cordes, T. & Hofmann, M. & Murr, R. & Bergmeister, K. 2018: Aktuelle Entwicklungen der Spritzbe-
tontechnologie und Spritzbetonbauweise am Brenner Basistunnel, Spritzbeton – Tagung 2018,
Alpbach.
504