Lay 6”black 94 x 55 ------------------------------------------------------------------- = $ 5,170

Settle concrete in foundation 35 ft run x 140 -------------------------------- = $ 4,900

Make kitchen counter in inside and outside kitchen sum ----------------------- = $ 160,000

black up and dress grease trap 10000 x 3 -------------------------------------------------- = $ 30,000

box and cast and dress big column top # 5 x 6500 --------------------------- = $ 32,500

Supervise leveling yard spray yard install iron to wall sum ----------------------- = $ 60,0

Make farm work 245.32 sq ft x 45 ------------------------------------------------------------- = $ 11,037.6

Erect steel 261 lbs x 28 ----------------------------------------------------------------------- = $ 7,308

Make small stirrup 7.6 dozen x 800 -------------------------------------------------------- = $ 6,080

pin up metal pipe 92.6 ft run x150 ----------------------------------------------------- = $ 13,890

2 mason help cast belt beam ½ day pay for 2 days x 7000 -------------------- = $ 14,000

2 mason make scafoldding to rough cast and render wall ½ day each --------- = $ 7,000

Total --------------- = $ 274,147

Erect back up board 55.6 ft run x 150 ------------------------------------------------- = $ 8,340


Erect bRc and screed floor 866.7 sq ft x 20 --------------------------------------- = $ 17,334

Rod and wood float floor 96.3 sq yd x 600 ------------------------------------------- = $ 57,780

Install 3” drain pipe sum of ----------------------------------------------------------------------- = $ 5000

Pull down back eve and cut zinc tale sum of ----------------------------------------------- = $ 9000

½ day for 2 mason to help cast belt beam 2 x 3500 ------------------------------------ = $ 7,000

total ------------------- = $ 347,196

rough cast and wood float beam and column 91 ft run x 139 ----------------- = $ 12,649

Install hand rale 3 days x 5000 ------------------------------------------------------ = $ 15,000

Erect farm work ,steel up and cast stair case sum of 70,000 --------------------- = $ 70,000

Rough cast and wood float upstan 90 ft run x 139 ---------------------------------- = $ 12,510

Rough cast ceiling 6.6 sq yd x 470 -------------------------------------------------- = $ 3,102

rough cast and render beam and column 32 ft run x 185 ------------------------ = $ 5,920

total --------------- = $ 240,276


`

box and cast and dress small column top # 3 x 4500 ----------------------------- = $ 13,500

dress soap holder small 2000 x 6 -------------------------------------------------------- = $ 12,000

Install and dress hd manhole cover 5000 x 5 ------------------------------------------------- = $ 25,000

install and dress gully basin cover 3000 x 2 --------------------------------------------------- = $ 6,000

cast ,lay and dress crove wall 106.9 ft run x 800 ----------------------------------- = $ 85,520

Dress wall 21 sq yd x 370 ----------------------------------------------------------------------- =$ 7,770

Make bar counter in basement and roof top sum ------------------------------------ = $ 90,000

Make step 6 tred x 4000 ----------------------------------------------------------------------- = $ 24,000

Screed and wood float yard 264.9 sq yd x 600 ------------------------------- = $ 158,940

Mark concrete in yard 264.9 sq yd x 350 ----------------------------------------- = $ 92,715

Total --------------- = $ 535,195


Lay 4” black 92 x 65 --------------------------------------------------------------------- = $ 5,980

Total -------------- $ 640,133

erect and strip farm work to septic 369.8 sq ft x 180 --------------------------------------------- = $ 66,564

Erect 5/8 steel 1120 lbs x 28 ----------------------------------------------------------------- = $ 31,360

Erect farm work ,steel up and cast pit top sum of 50,000 ----------------------------- = $ 50,000

strip farm work to beam 93.3 sq ft x 30 -------------------------------------------------- = 2,799


Total --------------------- = $ 1,089,873

dress and steel float septic and gravel bed 50.7 sq yd x 555 ------------------------------------ = $ 30,913

Less Advance to erect decking ------------------------------------- = $ 200,000

Balance -------------------- = $ 889,873

Spray 2,423 sq ft of floor

Render wall sq yd x 370 --------------------------------------------------------------- =$

Erect and strip farm work to arch way 80 sq ft x 180 ----------------------------- = $ 14,400

Erect back up board to floor 68 ft run x 130 ---------------------------------------- = $ 8,840


40,09829

Erect ¾ “ steel 1120 x 28 ---------------------------------------------------------------------- =$

Erect farm work to decking 1788.2 sq ft x 130 -------------------------------------------------- = $ 232,466

Erect back up board to beam side 259.6 sq ft x 130 -------------------------------------------- = $33,748

Total ------------------------- = $ 798,799

Mark out first floor

Mark out first floor 2652 sq ft x 15 ------------------------------------------------- = $ 39,780

Erect 3/8 steel 2240 lbs x 28 ----------------------------------------------------------------- =$

Rod and wood float decking 50 cy x 800 --------------------------------------------- = $40,000

Total ----------------------------- $ 1,141,894