Professional Documents
Culture Documents
PAP212
PAP212
ABSTRACT: Tunnel final lining is often designed to fully undertake all loads during tunnel service
life, such as loads from the surrounding ground, water pressure, live, accidental and seismic loads,
while neglecting any contribution of the temporary support. The role of the temporary support
measures in the final lining loading and design, even if they are finally deactivated or removed, is
significant, since they affect the stress history in the vicinity of the tunnel. This paper describes the
long-term performance of temporary support measures based on data from literature and investigates
via numerical analyses the load transfer from temporary support to final lining as well as the role of
face treatment measures to the final lining loading.
interface. Indirect loads are initially undertaken Thus, a significant percentage of the
by temporary support (only in conventional construction cost corresponds to measures with
tunnelling) and eventually are transferred to the limited technical life. Therefore, a reasonable
final lining, when temporary support becomes consideration is that a different design approach,
ineffective during tunnel service life. Therefore, which takes into account the temporary support
the role of the temporary support measures is during the project service life, could lead to a
significant, even if they are finally removed or decrease of the total cost. More specifically, an
deactivated, since they affect the stress history improvement of the quality control e.g. of the
and determine the equilibrium state after the shotcrete construction, so as to meet quality
completion of the excavation. requirements of a permanent structure, could
The assumption of temporary support lead to smaller final lining sections and decrease
degradation although very conservative, is the total cost without any change in the
common in final lining design, due to the performance of the tunnel.
uncertainties and the limited data concerning the This paper addresses the role of the
long-term behaviour of the temporary support, temporary support in the final lining design.
the poor quality control in its construction and Data from the literature and relevant codes are
code requirements. Data from 35 tunnels along presented regarding the long-term behaviour of
the Greek Egnatia Motorway (Marinos et al., the temporary support measures. Additionally,
2012) show that deactivation of temporary using numerical analyses the influence of the
support was a fundamental assumption in all temporary support measures on the final lining
final lining designs. However, specifications loading is described and the load transfer
and design methodologies can be found in mechanism - in case of deactivation of
literature (e.g. Thomas, 2009) and codes for the temporary support - is illustrated.
analysis and construction of shotcrete primary
lining as a permanent structure.
Figure 1 illustrates that the cost of final 2 SUPPORT SHELL: SHOTCRETE - STEEL
lining (assuming deactivation of the temporary SETS
support) varies from 10% to 60% of the
temporary support cost (the prices include the Shotcrete has been used more often as a
excavation cost). The high ratios, over 60%, permanent structure compared to rock bolts and
mainly correspond to light temporary support steel sets and therefore there is more available
sections, where the final lining design was data. In the “Report Nο 005. Shotcrete for rock
defined by the minimum acceptable values of support. A summary report on state-of-the-art”
the codes and not by the structural analysis. (ITA, 2010) it is described that some countries
such as Brazil, Czech Republic, Norway, Russia
100% 60% 40% 20% and Sweden have adopted shotcrete as
Final lining cost in 2013 prices (€/m)
9000
permanent structure in specific projects,
8000
whereas a complete record of shotcrete use in
7000 permanent structures is presented by Franzen et
6000 al. (2001).
5000 10% Bakogiannis (2004) suggests that the
4000 shotcrete shell can be taken into account during
3000 the tunnel service life if (a) its main scope is the
protection against small structural failures and
2000
not the restraint of potential convergence, (b)
1000 Data from 307 temporary support the reliability control requirements are satisfied,
and final lining sections
0 (c) the total deformations are less than a critical
0 10000 20000 30000 40000 50000 value of 0.8% and (d) the induced stresses do
Temporary support cost in 2013 prices (€/m) not exceed 70% of the design strength.
According to Yiouta-Mitra et al. (2010) the
Figure 1. Construction cost of temporary support and final
lining sections (Data from: TIAS Database, Marinos et main reasons for the long-term deactivation of
al., 2012). The 2013 values have been calculated from the shotcrete are the reduced strength, the
2004 values using the inflation rate of HICP for the Euro construction methodology, the stress and
Area (http://appsso.eurostat.ec.europa.eu/, update deformation field and the shotcrete creep
15/11/2013). behaviour, which depends on shotcrete
2
Proceedings of the World Tunnel Congress 2014 – Tunnels for a better Life. Foz do Iguaçu, Brazil.
composition, structure dimensions, loads and shear transfer may lead to a significant
shotcrete strength at the “first” loading. difference in the final lining internal forces.
Franzen et al. (2001) present the main In case that both structures are modeled as
conclusions of the “Working Group on beam or shell elements, the actual geometry
Shotcrete Use” of ΙΤΑ. The authors highlight (distance of the structural members’ center line
the lack of data from experimental tests and from the excavation surface) should be modeled
tunnel projects for shotcrete long-term to optimize the calculation of the internal forces.
performance. It is also mentioned that one of the If a structural analysis is carried out only for the
main difficulties in studying shotcrete durability final lining, simulating the geomaterial with
is the variation of many factors among different imposed loads and radial springs, the stiffness
cases (e.g. exposure of shotcrete into different of the springs should be increased due to the
types of quality and strength reducing processes, temporary support shell on the extrados of the
shotcrete exposure resistance capacity in final lining. This increase can be estimated from
relation to the exposure processes). In order to the Figure 2 as a function of the tunnel section
facilitate the assessment of long-term behaviour as well as the rock mass and the support shell
of shotcrete a matrix for the storage of properties (Fortsakis, 2012). These curves are
durability data is proposed. based on the convergence - confinement
Thomas (2009) presents a comprehensive method, assuming hydrostatic initial stress field,
design approach and design requirements for the two materials around the tunnel section (a) a
dimensioning and construction of permanent ring of elastic material that corresponds to the
shotcrete linings. Specific values are proposed support and (b) an infinite surrounding
for the shotcrete properties such as water/binder geomaterial and no slip at the interfaces. El
ratio<0.45 and compressive strength>30- Naggar et al. (2008) have proposed a general
40MPa. Additionally, different methodologies solution for the calculation of displacements and
are proposed for the simulation of shotcrete, if it internal forces in composite liners assuming
is assumed partially or fully deactivated. non-hydrostatic stress field and both slip and no
The compressive strength of high slip at the interfaces.
performance shotcrete in respect with the
d/R = 0.20 d/R = 0.18
additives and the accelerators that were used is 100.0
Et: Deformation modulus of d/R = 0.16
studied by Lee et al. (2005), aiming to satisfy 90.0 temporary support shell
d/R = 0.14
Eg: Deformation modulus of the
the specification of C50. Furthermore Lee et al. 80.0 surrounding geomaterial
d: Thickness of temporary d/R = 0.12
(2006) present results from accelerated 70.0 support shell
R: Excavation section radius d/R = 0.10
durability tests consisting of freeze-thaw tests, 60.0
Keq / Kref
The numerical analyses have been carried out subscript “m” indicates the average value
using the Finite Element code ABAQUS. The around the section.
tunnel section was assumed to be circular with In the case of full face excavation the steps of
diameter D=10m and the overburden height the numerical analyses were: (a) geostatic stress
H=10D=100m. The surrounding rock mass was (b) simulation of the preconvergence (c)
simulated as an isotropic linearly elastic - excavation and activation of the temporary
perfectly plastic material following the Mohr- support (d) activation of the final lining and (e)
Coulomb failure criterion with quadrilateral, 4- deactivation of the temporary support. It is
noded solid elements. Yet, the rock mass noted that the deactivation of the whole
properties were initially quantified using the shotcrete shell in one step, may not be realistic
parameters of Hoek-Brown failure criterion or conservative assumption, since different
(GSI, σci, mi), since it describes better the sections of it may be deteriorated with random
behaviour of rock materials and the equivalent sequence resulting to locally imposed loads.
parameters were calculated according to Hoek et
al. (2002). 7D = 70m
The shotcrete shell was modeled as an
isotropic linearly elastic material with 2-noded
beam elements and the rock bolts were modeled
7D = 70m
summarized in Table 1.
The rock mass deconfinement due to face
advance was estimated via the methodology Excavation section
proposed by Chern et al. (1998). The numerical
6D = 60m
Figure 4 illustrates the distribution of the initial and the final equilibrium points.
ratio pFL,m/psh,m as a function of the geotechnical Moreover, decrease of the preconvergence,
conditions ratio σc/po,m. In all cases, final lining results to smaller percentage of load transfer,
load is smaller than shotcrete load, since the since it moves the shotcrete and final lining
deactivation of shotcrete abolishes the existing curves to the left of the diagram where the slope
equilibrium, and additional displacements are of the rock mass characteristic curve is higher. It
developed until the new equilibrium between has also been proved using simple geometrical
the geomaterial and the final lining is reached. principles that in the case of elastic response of
In the range of unfavourable geotechnical the surrounding rock mass the ratio between the
conditions (low values of the geotechnical final lining and the shotcrete load is independent
conditions ratio σc/po,m) final lining load is equal of the preconvergence values.
to shotcrete load and as the geotechnical It is evident that in the case of temporary
conditions are improved the pFL,m/psh,m ratio support long-term deactivation, the increase of
decreases until a minimum value shotcrete thickness leads to a “double” cost
pFL,m/psh,m~0.40. It is also evident that increase increase, since it will lead to higher loads on the
of the final lining stiffness leads to larger final lining.
percentage of load transfer.
1.20
1.10
1.00
0.90
0.80
pFL,m / psh,m
0.70
0.60
0.50
0.40
0.30
0.20 dsh = 20cm, dFL = 60cm
0.10 dsh = 40cm, dFL = 40cm
0.00
0.10 0.20 0.30 0.40 0.50 0.60 0.70 0.80 0.90 1.00
σc / p o,m
The geostatic stress ratio (K) strongly affects The only change in the numerical analyses
the total displacements distribution and the steps in the case of sequential excavation is that
plastic zone around the tunnel section and the excavation and activation of temporary
consequently the values of the support load and support for the upper and lower part of the
bolt axial forces. Yet, its role to the load transfer section are simulated in two different steps. This
has been proved insignificant, since all the procedure alters the distribution and decreases
parameters which were adopted are normalized the values of the average load (up to 40%) and
and both the numerator and the denominator are increases the eccentricity of the internal forces
“equally” influenced by the initial stress field. in the concrete section (e=M/N), as it is shown
The mechanism of the load transfer is in Figures 6 and 7. Increased eccentricity values
illustrated in Figure 5 using the convergence - may lead to a significant decrease of the design
confinement curves. In the case of favourable reliability especially in unreinforced final lining
geotechnical conditions the rock mass sections (Fortsakis et al., 2013b).
characteristic curve is steeper, which means that The mechanism of load transfer (Figure 8) is
the load decrease until the new equilibrium qualitatively the same with the one described for
point is relatively large. On the other hand in the the full face excavation since the range of the
case of unfavourable geotechnical conditions, pFL,m/psh,m ratio values remains almost the same
the curvature of the characteristic curve (0.45 - 1.04).
decreases the relative distance between the
5
Proceedings of the World Tunnel Congress 2014 – Tunnels for a better Life. Foz do Iguaçu, Brazil.
1.20
3 LONG-TERM EFFECT OF ROCK BOLTS
pFL,m (Sequential) / psh,m (Full face)
1.10
1.00
0.90
Rock bolts are often assumed to eventually
0.80 become ineffective by corrosion due to ground
0.70 water and poor protection by grout. An
0.60 additional factor that could lead to rock-bolt
0.50 unloading is creep of the surrounding ground,
0.40
which can be important in the case of weak
0.30
0.20
geomaterials under high overburden. Since
dsh = 20cm, dFL = 60cm
0.10
inward displacement of the face plate is fully
dsh = 40cm, dFL = 40cm
0.00 restrained by the final lining, any creep in the
0.10 0.20 0.30 0.40 0.50 0.60 0.70 0.80 0.90 1.00
surrounding ground reduces the frictional force
σc / p o,m
along the grout-ground interface thus reducing
Figure 6. Comparison of average final lining load for the the axial force of the rock-bolt.
cases of full face and sequential excavation. The contribution of the rock bolts as a
temporary support measure has been described
0.125
Full face excavation
in the literature using analytical and numerical
Average ecentricity of internal
0.70
0.60
0.50
0.40
0.30
0.20 dsh = 20cm, dFL = 60cm
0.10 dsh = 40cm, dFL = 40cm
Dense grid, La=8m Sparse grid, La=8m
0.00
0.10 0.20 0.30 0.40 0.50 0.60 0.70 0.80 0.90 1.00
σc / p o,m Figure 9. The two different rock bolt grids simulated in
the numerical analyses. The out of plane distance between
Figure 8. Distribution of the ratio pFL,m/psh,m as a function rock bolts is considered to be equal to the excavation step
of the geotechnical conditions ratio σc/po,m for two (x=1.0m).
different combinations of shotcrete and final lining
thickness (sequential excavation). The shotcrete and final lining parameters
have been presented in Table 1. The bolts length
was Lb=8.0 m, the bolts diameter db=25mm, the
ultimate tensile capacity fs=500MPa and the
deformation modulus Es=200GPa.
6
Proceedings of the World Tunnel Congress 2014 – Tunnels for a better Life. Foz do Iguaçu, Brazil.
In the case of deactivation of the rock bolts the shear force increases rapidly and in many
the rigid final lining shell can offer the cases it is significantly higher than the
confinement that was applied by them. corresponding value in the last step. It is noted
However, the main issue regarding the the values are indicative, since they depend on
additional load from the rock bolts is that they the parameters of the specific analyses and the
are not installed continuously, but in a specific pattern of bolts deactivation.
grid and the primary load parameter which is
calculated and developed in the construction is
the axial stress. Assuming that the bolts are
deactivated during the tunnel service life, the
concentrated forces are transformed into
additional pressure on final lining until the new
equilibrium point. However, there is not a direct
and simplified way to transform these forces to
pressure since this depends on the geotechnical
conditions and the section stiffness (Fortsakis,
2012).
Figure 10 shows that the installation of the
bolts leads, due to the increase of the temporary
support stiffness, to an additional load in the
final lining up to 40% for the sparse and up to
70% for the dense grid. The role of the bolts is
more significant for low values of σc/po,m.
1.80
pFL,m (Anchors) / pFL,m (No anchors)
Desne grid 2m x 1m Figure 11. Comparison of the shear forces in the final
1.70 Sparse grid 2m x 1m lining for the case of gradual and full bolts deactivation.
1.60 The ratios of shear forces are plotted as absolute values
(GSI=20, σci=20MPa, mi=6). The curves correspond to
1.50 different intermediate steps.
1.40
1.30
4 FACE TREATMENT MEASURES
1.20
The support shell was modeled with 4-sided, 4- advancement cores. This leads to a decrease of
noded linearly elastic shell elements, the the preconvergence and finally to maximum
forepole umbrella with elastic 2-noded beam additional pressure of 11%. However, the
elements (this simulation corresponds to influence of the forepole umbrella is
independent pipes and not a fully grouted arch, significantly smaller than the one of the
see also the Oke et al., 2013) and the bolts and fibreglass nails. In the case that both measures
the fibreglass nails with elastoplastic 2-noded are applied the maximum load increase is 19%.
truss elements. The 3D numerical model is The results depend on the density and the axial
illustrated in Figure 12 and the analyses stiffness of the fibreglass nails and the spacing
parameters in Table 2. and bending stiffness of the forepole umbrella.
60m 250.0
150.0
60m
100.0
Fibreglass nails & Forepole Umbrella
No face treatment measures
50.0 Forepole umbrella
Fibreglass nails
Forepole umbrella (no presupport)
0.0
1.0 2.0 3.0 4.0 5.0 6.0 7.0
Position around the tunnel section (m)
Vertical distance from the Bench floor
the beam elements of the pipes were added at lead to a very large number of design scenaria
the same step with the shotcrete shell. The and a complicated design procedure. Therefore,
calculated displacements around the tunnel and based on the particularities of each project, the
the applied pressure (Figure 13) are practically critical situations should be chosen to create an
the same with the case where no pre-support envelope for the final lining design.
measures were used, which means that the role In case that long-term deactivation of the
of the steel pipes in a transversal section and a shotcrete shell is assumed, shotcrete load is
2D numerical analysis in terms of stiffness is completely transferred to the final lining in
negligible. However, a full 3D simulation of the unfavourable geotechnical conditions, whereas
forepole umbrella is needed to evaluate also the this percentage continuously decreases as the
microarching that is developed between the geotechnical conditions are improved
pipes. (pFL,m/psh,m=0.40-1.00). The installation of rock
bolts, contributes to the decrease of the
displacements and moments in the shotcrete
5 CONCLUSIONS shell during the excavation, but also leads to the
increase of the final lining load, since it
Tunnel final lining design is a complex increases the equivalent stiffness of the
geotechnical and structural problem, since it temporary support section. Finally, the role of
strongly depends on the interaction of the the face treatment measures should be taken into
system surrounding geomaterial - temporary account in final lining design, even if they are
support - final lining in the case of conventional removed during the construction (e.g. fibreglass
tunnelling. Therefore the role of the temporary nails).
support measures, even if they are finally
deactivated or removed, is significant, since
they affect the stress history in the vicinity of ACKNOWLEDGEMENTS
the tunnel. The present paper describes the long-
term performance of temporary support The authors would like to acknowledge the
measures based on data from literature, studies contribution of M. Demerouti, Civil Engineer,
the load transfer from temporary support to final M.Sc. and I.I. Barbakou, Civil Engineer, M.Sc.
lining and the role of face treatment measures to to the development of the 3D numerical model.
the final lining loading via numerical analyses.
There is little available data in literature
regarding the performance of shotcrete, steel REFERENCES
sets and rock bolts during tunnel service life.
However, a significant number of projects, in Bakogiannis, I. 2004. Actions, methods and analysis
which the temporary measures were adopted as models of tunnel final lining. In: T. Tasios (ed.)
Tunnel final lining analysis and dimensioning.
long-term support, have been reported in recent Athens: Greek Tunnelling Society, p.25-50 (in greek).
publications. Therefore, these projects should be Cantieni L. and Anagnostou G. 2011. On a paradox of
monitored very thoroughly, so as to evaluate if elasto-plastic tunnel analysis. Rock Mechanics and
and how these measures can be taken into Rock Engineering, v.44, No. 2, p.129-147
account as permanent structures. Carranza-Torres, C. 2009. Analytical and numerical study
The incorporation of the initial shotcrete of the mechanics of rockbolt reinforcement around
tunnels in rock masses. Rock Mechanics and Rock
shell in the permanent structural system may Engineering. v.42, p.175-228.
lead to a significant decrease of the total cost. Chern, J.C., Shiao, F.Y. and Yu, C.W. 1998. An empirical
Prerequisites for this approach are guidelines safety criterion for tunnel construction. In:
that will describe the specifications and Proceedings of the Regional Symposium on
construction quality control during the Sedimendary Rock Engineering. Taipei. p.222-227.
El Naggar, H., Hinchberger, S.D. and Lo, K.Y. 2008. A
excavation that corresponds to a permanent closed-form solution for composite tunnel linings in a
structure. homogenous infinite isotropic elastic medium.
The assumption of full deactivation of all the Canadian Geotechnical Journal. v.45, p.266-287.
temporary support measures may not always be Fortsakis, P. 2012. Investigation of the static interaction
realistic or conservative for the dimensioning of of the surrounding soil/rock with the tunnel final
the final lining. The temporary support lining. Thesis (PhD in Civil Engineering) - National
Technical University of Athens (NTUA), School of
measures may be not deactivated, or they can be Civil Engineering, Department of Geotechnical
fully, partially or locally deactivated. This may Engineering, Athens, 466p. (in greek).
9
Proceedings of the World Tunnel Congress 2014 – Tunnels for a better Life. Foz do Iguaçu, Brazil.
Fortsakis, P., Chortis, P., Prountzopoulos, G. and Engineering. v.3, p.891-910. doi: 10.1007/s10706-
Kavvadas, M. 2013a. Investigation of the loads on the 012-9570.
primary lining for tunnels excavated with face support Prountzopoulos, G. 2012. Investigation of the excavation
or improvement. In: Proceedings of the World Tunnel face stability in shallow tunnels. Thesis (PhD in Civil
Congress 2013, Underground -The way to the future Engineering) - National Technical University of
(Anagnostou, G. and Ehrbar, H. (eds)). Geneva, Athens (NTUA), School of Civil Engineering,
Switzerland, p.661-668. Department of Geotechnical Engineering, Athens,
Fortsakis, P., Litsas, D. and Kavvadas, M. 2013b. 452p. (in greek).
Reliability analysis of unreinforced tunnel final lining. Thomas, A. 2009. Sprayed concrete lined tunnels. New
In: Proceedings of EURO:TUN 2013, 2nd York: Taylor & Francis, 235p.
International Conference on Computational Methods Oke, J., Vlachopoulos, N. and Diederichs, M. 2012.
in Tunnelling (Meschke, M., Eberhardsteiner, J., Improved input parameters and numerical analysis
Schanz, T., Soga, K. and Thewes, M. (eds)). Bochum, techniques for temporary support of underground
Germany, p. 813-820. excavations in weak rock. In: Proceedings of RockEng
Franzen, T., Garshol, K.F. and Tomisawa, N. 2001. - 21st Canadian Rock Mechanics Symposium.
Sprayed concrete for final linings: ITA working group Edmonton, Canada.
report. Tunnelling and Underground Space Oke, J., Vlachopoulos, N. and Marinos, V. 2013.
Technology, v.16, p.295-309. Umbrella arch nomenclature and selection
Hoek, E., Carranza-Torres, C. and Corkum, B. Hoek- methodology for temporary support systems for the
Brown failure criterion. 2002. In: Proceedings of the design and construction of tunnels. Geotechnical and
5th North American Rock Mechanics Symposium and Geological Engineering. Published online 27
17th Tunnelling Association of Canada: NARMS-TAC. September 2013. DOI 10.1007/s10706-013-9697-4.
Toronto, Canada. v.1, p.267-273. Yiouta-Mitra, P. Gkekas, S. and Sofianos, A. 2010.
Hoek, E., Carranza-Torres, C., Diederichs, M. and Parametric analyses of tunnel final lining loads. In:
Corkum, B. 2008. Integration of geotechnical and Proceedings of the 6th Hellenic Conference on
structural design in tunneling. The Kersten Lecture. Geotechnical and Geoenvironmental. Athens:
Hudson, J.A. and Harrison J.P. 2000. Engineering rock Technical Chamber of Greece. Volos, Greece, v.2,
mechanics. An introduction to the principles, 1st edn. p.595-602. (in greek)
Oxford: Elsevier Science Ltd.
International Tunnelling Association (ITA), Working
Group N°12: Sprayed Concrete Use. 2010. ITA Report
Nο 005. Shotcrete for rock support. A summary report
on state-of-the-art.
Kolymbas, D. 2008. Tunnelling and Tunnel Mechanics. A
rational approach to tunnelling. Berlin: Springer.
439p.
Lee, S., Kim, D., Ryu, J., Lee, S., Kim, J., Kim, H. and
Choi, M. 2006. An experimental study on the
durability of high performance shotcrete for
permanent tunnel support. Tunnelling and
Underground Space Technology. v.21, p.431.
Lee, S.P., Kim, D.H., Ryu, J.H., Yu, J.Y., Lee, S.D., Han,
S.H., Choi, M.S. and Park, C. 2005. An experimental
study on the development of high performance
shotcrete for permanent tunnel support. In:
Proceedings of the ITA-AITES 2005 World Tunnel
Congress, Underground Space Use: Analysis of the
Past and Lessons for the Future (Erdem and Solak
(eds)). Istanbul, Turkey, London: Taylor & Francis
Group. v.2, p. 455-461.
Marinos, P. and Hoek, E. 2000. GSI: a geologically
friendly tool for rock mass strength estimation. In:
Proceedings of the GeoEng2000 at the International
Conference on Geotechnical and Geological
Engineering. Melbourne, Australia. Lancaster:
Technomic publishers, p.1422-1446.
Marinos, V., Marinos, P. and Hoek, E. 2005. The
geological strength index: applications and limitations.
Bulletin of Engineering Geology and the Environment.
v.64, p.55-65.
Marinos, V., Prountzopoulos, G., Fortsakis, P.,
Koumoutsakos, D. and Papouli, D. 2013. Tunnel
Information and Analysis System: A geotechnical
database for tunnels. Geotechnical and Geological
10