METHOD STATEMENT FOR PRECAST MANHOLE INSTALLATION WORKS

PROJECT: SUPPLY AND LAY THE PROPOSED BY PASS TREATED EFFLUENT LINE
Contract No.: BOI/BEPZ/ES/2022/07/03.031
REF: MS/BIYAGAMA/MH INSTALLATION

1.0 Scope
The method statement for precast manhole installation is to explain the systematic procedures,
arrangements and safety measures, which ought to be followed during installation of precast manhole.
Contractor shall be accountable to comply with all work and safety stipulations/measures as stated in this
method statement.

2.0 Surveying
The coordinates and elevations of the survey monuments shall be given to the Contractor by the Client.
The Contractor shall verify the survey reference points. The Contractor shall furnish these reference points
on the Site and using these reference points, shall perform all surveying and staking required to complete
the Work. Existing Survey Monuments in the Work area shall be preserved and protected from damage or
disturbance and shall not be removed unless necessary.

2.1 Special setting outs for MH01 and MH03


Since there is existing Hume pipe line and DI line along the setting out area, setting out will be carried out
in order to avoid any interaction between existing line and the manhole. After finishing the sewer system
existing line will be diverted in to Manhole 01 and Manhole 03 as shown in Figure 01 and Figure 02.

Proposed Line Diversion

Existing Sewer line

1200mm

Flow Direction

Figure 01: Diversion of the line near MH01


METHOD STATEMENT FOR PRECAST MANHOLE INSTALLATION WORKS
PROJECT: SUPPLY AND LAY THE PROPOSED BY PASS TREATED EFFLUENT LINE
Contract No.: BOI/BEPZ/ES/2022/07/03.031
REF: MS/BIYAGAMA/MH INSTALLATION

Proposed Line Diversion

Existing Sewer line

1200mm

Flow Direction

Figure 02: Diversion of the line near MH03

3.0 Clearing and Grubbing


Areas to be excavated, filled, or graded shall be cleared and grubbed (cleaning the grass and roots).
Clearing and grubbing shall consist of the removal and disposal of trees, stumps, brush, roots, vegetation,
logs, rubbish, and other objectionable materials. Stumps, roots, and other similar refuse shall be removed
to a depth of not less than 150mm below the existing ground surface and to a distance of at least 600mm
beyond the excavation limits. Holes remaining after removal of stumps, roots, and other similar refuse
shall be backfilled with suitable material and compacted to at least the density of the adjacent undisturbed
material. Material cleared from the site shall be either burned or removed from the site. Disposal or
burying of cleared materials shall comply with local laws, codes, regulations.
METHOD STATEMENT FOR PRECAST MANHOLE INSTALLATION WORKS
PROJECT: SUPPLY AND LAY THE PROPOSED BY PASS TREATED EFFLUENT LINE
Contract No.: BOI/BEPZ/ES/2022/07/03.031
REF: MS/BIYAGAMA/MH INSTALLATION

4.0 Excavations

4.1 General
Excavation shall be done after clearing and grubbing has been completed. Excavations shall preferably be
performed in dry conditions. Proper drainage for excavated areas shall be maintained to prevent ponding
of water. Excavated areas shall be kept dry by pumping or other suitable methods. Prior to completion of
drainage facilities, sufficient temporary ditches and culverts to prevent ponding shall be installed.

4.2 Excavations for Manholes MH04-MH09

All the general excavation methodology will be applied and the excavation pit size will be 4050mm x
4050mm in order to facilitate working space for manhole placing and in situ concrete jacket work for
manholes.

Figure 03: Excavation for MH04 to MH08

If necessary, dewatering will be done and for the pond side shoring will be arranged if any concerns arise
after the inspection. Necessary slope preparation work will be done in order to prevent the collapse of
banks at the other side.
METHOD STATEMENT FOR PRECAST MANHOLE INSTALLATION WORKS
PROJECT: SUPPLY AND LAY THE PROPOSED BY PASS TREATED EFFLUENT LINE
Contract No.: BOI/BEPZ/ES/2022/07/03.031
REF: MS/BIYAGAMA/MH INSTALLATION

4.3 Excavations for Manholes MH01 and MH03

All the general excavation methodology will be applied and the excavation will be done according to below
figure 04.

900mm

900mm
1650mm 900mm

1000mm
650mm

Existing drainage line

Figure 04: Excavation for MH01 and MH03

Necessary collapse prevention method will be used for the existing drainage line bank side based on the
condition of the site. All the excavations will be carried out in a dry weather condition.
METHOD STATEMENT FOR PRECAST MANHOLE INSTALLATION WORKS
PROJECT: SUPPLY AND LAY THE PROPOSED BY PASS TREATED EFFLUENT LINE
Contract No.: BOI/BEPZ/ES/2022/07/03.031
REF: MS/BIYAGAMA/MH INSTALLATION

4.3 Excavations for Manholes MH02

All the general excavation methodology will be applied and the excavation will be done according to below
figure 05.

900mm

2700mm
900mm
900mm

1000mm
650mm

Existing drainage line

1500mm

Figure 05: Excavation for MH02

Necessary collapse prevention method will be used for the existing drainage line bank side based on the
condition of the site. All the excavations will be carried out in a dry weather condition. Excavation for
900mm Hume pipe also done in parallel with the excavation of the manhole 02. Coffer Dam will be
constructed and the existing drainage line will be diverted as in Figure 06.
METHOD STATEMENT FOR PRECAST MANHOLE INSTALLATION WORKS
PROJECT: SUPPLY AND LAY THE PROPOSED BY PASS TREATED EFFLUENT LINE
Contract No.: BOI/BEPZ/ES/2022/07/03.031
REF: MS/BIYAGAMA/MH INSTALLATION

DI or Flexible Pipe
Clay/DI Pipe
DI or Flexible Pipe
Clay/DI Pipe

A A

A A

Coffer Dam Coffer Dam


1500mm
Coffer Dam Coffer Dam
1500mm

Figure 06: Existing line diversion for MH02

1500mm
Coffer Dam Coffer Dam

Manhole 02
Hume pipe

Figure 07: Section A-A


METHOD STATEMENT FOR PRECAST MANHOLE INSTALLATION WORKS
PROJECT: SUPPLY AND LAY THE PROPOSED BY PASS TREATED EFFLUENT LINE
Contract No.: BOI/BEPZ/ES/2022/07/03.031
REF: MS/BIYAGAMA/MH INSTALLATION

4.4 Excavations for Manholes MH10

All the general excavation methodology will be applied and the excavation will be done according to below
figure 08.

Embankment

4050mm

3532mm
Earthwork Protection

Figure 08: Excavation of Manhole 10

Necessary collapse prevention method will be used for the embankment side using shoring plates based
on the condition of the site. All the excavations will be carried out in a dry weather condition.
METHOD STATEMENT FOR PRECAST MANHOLE INSTALLATION WORKS
PROJECT: SUPPLY AND LAY THE PROPOSED BY PASS TREATED EFFLUENT LINE
Contract No.: BOI/BEPZ/ES/2022/07/03.031
REF: MS/BIYAGAMA/MH INSTALLATION

5.0 Manhole installation

5.1 Bedding

After excavation complete base of the excavation pit compacted in order to lay the chip bedding. After
that 100mm thick 5-10mm chip bedding lay on the compacted soil layer and compacted to 50mm.
Another layer also laid and follow the same procedure.

5.2 Placing of Precast Manhole

Figure 09: Lifting of Manhole Bottom Part

After the bedding compaction completed, level measurements were taken to ensure the proper levels was
maintained. After that bottom part of the manhole was places as in Figure 09 by using boom truck. After
placing bottom part again necessary level measurements were taken and then form work for concrete
benching was fixed and C35A Sulphate resistant concrete was used to pour the concrete benching. After
that 20mm thick sulphate resistant cement concrete topping will be applied on top of the concrete
benching. After that inlet and outlet Hume pipes were connected to the bottom part of the manhole. Then
intermediate parts and top covers were placed and cement sand mortar was used to seal the connecting
groove.
METHOD STATEMENT FOR PRECAST MANHOLE INSTALLATION WORKS
PROJECT: SUPPLY AND LAY THE PROPOSED BY PASS TREATED EFFLUENT LINE
Contract No.: BOI/BEPZ/ES/2022/07/03.031
REF: MS/BIYAGAMA/MH INSTALLATION

5.3 Concrete cover around precast Manholes

After placing manhole up to top cover, circular form work was made around the manhole as in figure 10
and 11.

A A
600mm
900mm 900mm

Manhole
Circular Formwork
Excavated Trench

Figure 10: Circular Formwork


METHOD STATEMENT FOR PRECAST MANHOLE INSTALLATION WORKS
PROJECT: SUPPLY AND LAY THE PROPOSED BY PASS TREATED EFFLUENT LINE
Contract No.: BOI/BEPZ/ES/2022/07/03.031
REF: MS/BIYAGAMA/MH INSTALLATION

Manhole
6mm Plywood formwork
5mm thk flat iron circles 200mm C to C

Figure 11: Section A-A

Maximum formwork height will be 1200mm and concrete bonding agent will be used for the concrete
connection for the manholes which are taller than 1200mm.

5.4 Brick work and Manhole cover

After finishing concrete cover around the manhole, brick covering will be build using engineering bricks
and 1:3 CT: SAND Mortar and height of the brick covering will be decided according to the manhole top
finish level and road formation level. Finally, 600mm dia Manhole and cover frame will be installed and
cover the frame using 1:3 Cement sand Mortar.