Precast Manhole Installation
Precast Manhole Installation
PROJECT: SUPPLY AND LAY THE PROPOSED BY PASS TREATED EFFLUENT LINE
Contract No.: BOI/BEPZ/ES/2022/07/03.031
REF: MS/BIYAGAMA/MH INSTALLATION
1.0 Scope
The method statement for precast manhole installation is to explain the systematic procedures,
arrangements and safety measures, which ought to be followed during installation of precast manhole.
Contractor shall be accountable to comply with all work and safety stipulations/measures as stated in this
method statement.
2.0 Surveying
The coordinates and elevations of the survey monuments shall be given to the Contractor by the Client.
The Contractor shall verify the survey reference points. The Contractor shall furnish these reference points
on the Site and using these reference points, shall perform all surveying and staking required to complete
the Work. Existing Survey Monuments in the Work area shall be preserved and protected from damage or
disturbance and shall not be removed unless necessary.
1200mm
Flow Direction
1200mm
Flow Direction
4.0 Excavations
4.1 General
Excavation shall be done after clearing and grubbing has been completed. Excavations shall preferably be
performed in dry conditions. Proper drainage for excavated areas shall be maintained to prevent ponding
of water. Excavated areas shall be kept dry by pumping or other suitable methods. Prior to completion of
drainage facilities, sufficient temporary ditches and culverts to prevent ponding shall be installed.
All the general excavation methodology will be applied and the excavation pit size will be 4050mm x
4050mm in order to facilitate working space for manhole placing and in situ concrete jacket work for
manholes.
If necessary, dewatering will be done and for the pond side shoring will be arranged if any concerns arise
after the inspection. Necessary slope preparation work will be done in order to prevent the collapse of
banks at the other side.
METHOD STATEMENT FOR PRECAST MANHOLE INSTALLATION WORKS
PROJECT: SUPPLY AND LAY THE PROPOSED BY PASS TREATED EFFLUENT LINE
Contract No.: BOI/BEPZ/ES/2022/07/03.031
REF: MS/BIYAGAMA/MH INSTALLATION
All the general excavation methodology will be applied and the excavation will be done according to below
figure 04.
900mm
900mm
1650mm 900mm
1000mm
650mm
Necessary collapse prevention method will be used for the existing drainage line bank side based on the
condition of the site. All the excavations will be carried out in a dry weather condition.
METHOD STATEMENT FOR PRECAST MANHOLE INSTALLATION WORKS
PROJECT: SUPPLY AND LAY THE PROPOSED BY PASS TREATED EFFLUENT LINE
Contract No.: BOI/BEPZ/ES/2022/07/03.031
REF: MS/BIYAGAMA/MH INSTALLATION
All the general excavation methodology will be applied and the excavation will be done according to below
figure 05.
900mm
2700mm
900mm
900mm
1000mm
650mm
1500mm
Necessary collapse prevention method will be used for the existing drainage line bank side based on the
condition of the site. All the excavations will be carried out in a dry weather condition. Excavation for
900mm Hume pipe also done in parallel with the excavation of the manhole 02. Coffer Dam will be
constructed and the existing drainage line will be diverted as in Figure 06.
METHOD STATEMENT FOR PRECAST MANHOLE INSTALLATION WORKS
PROJECT: SUPPLY AND LAY THE PROPOSED BY PASS TREATED EFFLUENT LINE
Contract No.: BOI/BEPZ/ES/2022/07/03.031
REF: MS/BIYAGAMA/MH INSTALLATION
DI or Flexible Pipe
Clay/DI Pipe
DI or Flexible Pipe
Clay/DI Pipe
A A
A A
1500mm
Coffer Dam Coffer Dam
Manhole 02
Hume pipe
All the general excavation methodology will be applied and the excavation will be done according to below
figure 08.
Embankment
4050mm
3532mm
Earthwork Protection
Necessary collapse prevention method will be used for the embankment side using shoring plates based
on the condition of the site. All the excavations will be carried out in a dry weather condition.
METHOD STATEMENT FOR PRECAST MANHOLE INSTALLATION WORKS
PROJECT: SUPPLY AND LAY THE PROPOSED BY PASS TREATED EFFLUENT LINE
Contract No.: BOI/BEPZ/ES/2022/07/03.031
REF: MS/BIYAGAMA/MH INSTALLATION
5.1 Bedding
After excavation complete base of the excavation pit compacted in order to lay the chip bedding. After
that 100mm thick 5-10mm chip bedding lay on the compacted soil layer and compacted to 50mm.
Another layer also laid and follow the same procedure.
After the bedding compaction completed, level measurements were taken to ensure the proper levels was
maintained. After that bottom part of the manhole was places as in Figure 09 by using boom truck. After
placing bottom part again necessary level measurements were taken and then form work for concrete
benching was fixed and C35A Sulphate resistant concrete was used to pour the concrete benching. After
that 20mm thick sulphate resistant cement concrete topping will be applied on top of the concrete
benching. After that inlet and outlet Hume pipes were connected to the bottom part of the manhole. Then
intermediate parts and top covers were placed and cement sand mortar was used to seal the connecting
groove.
METHOD STATEMENT FOR PRECAST MANHOLE INSTALLATION WORKS
PROJECT: SUPPLY AND LAY THE PROPOSED BY PASS TREATED EFFLUENT LINE
Contract No.: BOI/BEPZ/ES/2022/07/03.031
REF: MS/BIYAGAMA/MH INSTALLATION
After placing manhole up to top cover, circular form work was made around the manhole as in figure 10
and 11.
A A
600mm
900mm 900mm
Manhole
Circular Formwork
Excavated Trench
Manhole
6mm Plywood formwork
5mm thk flat iron circles 200mm C to C
Maximum formwork height will be 1200mm and concrete bonding agent will be used for the concrete
connection for the manholes which are taller than 1200mm.
After finishing concrete cover around the manhole, brick covering will be build using engineering bricks
and 1:3 CT: SAND Mortar and height of the brick covering will be decided according to the manhole top
finish level and road formation level. Finally, 600mm dia Manhole and cover frame will be installed and
cover the frame using 1:3 Cement sand Mortar.