Plastering Work
Plastering Work
Plastering Work
PROJECT: SUPPLY AND LAY THE PROPOSED BY PASS TREATED EFFLUENT LINE
Contract No.: BOI/BEPZ/ES/2022/07/03.031
REF: MS/BIYAGAMA/Plastering
1.0 PURPOSE:
The purpose of this method statement is to define the procedure for internal and external plaster work in
accordance with the requirement specified in the relevant specification procedures and drawing
throughout the progress of the work
2.0 SCOPE:
This method statement applies to the application of plaster works complying with the project General
specifications for civil & architectural works
3.0 REFERENCES
General specifications for civil & architectural works
Approved Drawings
Material Approval Request
4.0 RESPONSIBILITIES:
Project Manager is overall responsible for the project execution, quality, and safety and technical officer
to check the positioning of the walls. Technical officer/Site Engineer is responsible for overall execution of
the job and is directly responsible for the quality of the job being produced. Technical officer/Site Engineer
shall ensure that all works are carried out according to design. Technical Officer to ensure that the work
crew is familiar with the safety requirements
5.1 Equipment
Plaster checking Equipment (Straight edge)- different sizes of aluminum tubes.
Measuring Tapes
5.2 Materials
Plaster Accessories
Rush coat for concrete surfaces
Render for concrete surface & block work)
Clean potable water
6.0 PROCEDURE
6.1 INSTRUCTIONS
All the necessary PPEs will be provided (safety shoes, helmet, hand gloves), safety belts and scaffolding.
Company waste management guidelines shall be adhered in disposing all the waste. All survey instruments
shall be calibrated by the approved agency as per Company guidelines.
METHOD STATEMENT FOR PLASTERING WORKS
PROJECT: SUPPLY AND LAY THE PROPOSED BY PASS TREATED EFFLUENT LINE
Contract No.: BOI/BEPZ/ES/2022/07/03.031
REF: MS/BIYAGAMA/Plastering