Project : DMM052 D2 - STC DATA CENTER

Contractor : BMS
Subcontractor : Enjaz Al-Arabiya Contracting Company
Subject : Extra work done by Enjaz Al-Arabiya Till 10-01-2024
SI ITEM Location UNIT QTY
1 Automatic Air Vent 1/2" and valve for cooling skid supply and return D2 PCS 32.00

2 Automatic Air Vent 2" for Storage Tanke D2 PCS 6.00

3 Pressure Relief Valve 2" for Storage Tanke D2 PCS 6.00

4 Rent of Submersible Pump + drain truck D2 PCS 1.00

5 Decoment Controller ( start from 01-09-2023 ) D2 Month 6.00

6 House keeping , man Power ( start from 01-09-2023 ) D2 Month 6.00

7 Support relocation near to TEST on Day1 D1 LOT 1.00

8 POD CRAH flexible pipe rectification D2 PCS 72.00

9 CRAH flexible pipe rectification D2 PCS 72.00

10 CRAH Stanless Steel Hose both MNPT fixed 1.5" X 70 cm D2 PCS 24.00

11 Remove and install new insulation and cladding on SCWP 7 & 8 to avail plate D2 LOT 1.00
Thermal storage tank Leakage maintenaince ,,, Romove cladding and insulation and reinstall
12 D2 PCS 6.00
new material
13 Thermal storage tank : Alumium Clading Box for Cover Tank LEG D1/D2/D3 Tank 16.00
14 Modify of Chilled Water Pipe in D-1 for FCU`s in the corridor with new insulation and cladding D1 Lot 1.00
15 Circulation pump and generator expenses after flushing (As Mail) D2 Day 13.00

16 Bag filter housing D2 PCS 1.00

17 Supply and install 6 inch valves instead of motorized BFV to procees with flushing D2 PCS 4.00
18 Supply and install 1/2 inch valve for DPT D2 PCS 8.00

19 Size 12 inch valves for future flushing D2 PCS 2.00

20 Ultrasonic Water Balance Test (Flowmeter) D2 Lot 1.00


Installation of submersible pumps (Include supply and installation of guiderail, pump, gate
21 D2 Set 2.00
valves, check valves and piping connection)
22 Supply and install 2000L make up tank D2 PCS 1.00

23 Supply and install DRV for PM CRAH D2 PCS 12.00

24 Supply and install DRV for BM FCU and POD 4 FCU D2 PCS 16.00

25 Engineering support during TCCF L3/L4 and operation of plant with technical team D2 LOT 1.00
Preprartion of the As-built and shop drawing for the Fuel system, water supply and
26 D2 LOT 1.00
condensation drawings
27 Supply and install ball valves for cooling skid CRAH connection POD 6 D2 PCs 12.00

28 Installation of ball valves for cooling skid CRAH connection POD 4,5 D2 PCs 24.00

29 CRAH DUCT Clothes with foster over insulation D2 m2 147.00

30 Vibration and Noise test for Chiller Area D1/D2 LOT 1.00

31 Jet diffuser 8" D2 PCs 24.00

32 DPS and DPSL installation for SCWPs D2 PCs 10

33 Sight glass 1 inch for generator filling line D2 PCs 10

TOTAL
Enjaz Al- arabiya Engineer
Eng/ Mohamed A Elmorsy

SBM PROJECT Engneer SBM PROJ


Eng/ Mahmoud Hany Eng/ Ahmad
UNIT PRICE TOTAL REMARKS
600.00 19,200.00

3,300.00 19,800.00

3,900.00 23,400.00

2,500.00 2,500.00 for rain water (4 trucks)

7,000.00 42,000.00

9,000.00 54,000.00

0.00 0.00

80.00 5,760.00

110.00 7,920.00

500.00 12,000.00

1,000.00 1,000.00

1,500.00 9,000.00

1,200.00 19,200.00
‫‪0.00‬‬
‫‪5,600.00‬‬ ‫‪72,800.00‬‬ ‫الزم تكون في ورق مستقل‬

‫‪28,000.00‬‬ ‫‪28,000.00‬‬

‫‪2,887.00‬‬ ‫‪11,548.00‬‬
250.00 2,000.00

3,000.00 6,000.00

3,400.00 3,400.00

3,500.00 7,000.00

5,000.00 5,000.00

680.00 8,160.00

600.00 9,600.00

20,000.00 20,000.00

15,000.00 15,000.00

408.00 4,896.00

250.00 6,000.00

75.00 11,025.00 each duct duct is 4 m2

0.00

0.00

0.00

0.00

407,009.00
SBM PROJECT MANGER
Eng/ Ahmad Al-Zou'bi
Project : DMM052 D2 - STC DATA CENTER
Contractor : BMS
Subcontractor : Enjaz Al-Arabiya Contracting Company
Subject : Extra work done by Enjaz Al-Arabiya Till 16-05-2023

SI ITEM Location UNIT


1 Maintainance of DPT-B connection for copper pipe D1 LOT

2 CRAH DUCT Clothes with foster over insulation D1 m2

3 for two chillers in 1 Loop D1 LOT

4 for two Pumps in 1 Loop D1 LOT

5 Guard room split unit maintenance- Gas filling and cladding rectification on the roof D1 LOT

6 Staging Room D1 m2

7 DC room D1 m2

8 MMR room D1 m2

9 Straight Duct with insulation size 15x10 D1 m.l

10 Duct Elbow 90 Deg with insulation size 15x10 D1 PCS


11 VD supply and installation 15x10 D1 PCS

12 MFSD 15X15 D1 PCS

13 PODs VD relocation (POD1+POD2) D1 PCS

14 supply and install - Return Diffuser D1 PCS

15 Plenum adjust and installation - supply Diffuser D1 PCS

16 Bridge - Steel sheet 16 mm Thick. D2+D3 LOT

17 Air vent for cooling skid and AHU D2 PCS

18 Cutting in Chiller Sprinrg Plate D2 PCS

19 Make up pump shade and support D1 LOT

Romove cladding and insulation from day 1 makeup line and install two pressure guages
20 D1 LOT
and re install insulation and cladding after finish

21 Supply GRB tank for water supply lift station 3000 litre D1 PCS

22 Installation of flexible connection 6" Between cooling skid and main loop with bolts D2 PCS

23 Flanges 6" for the flexible connection D2 PCS

24 chilled water network chemicals ajdustment D1 LOT

25 fitting class 3000 D2 LOT


26 Water supply , Hose Support in Roof D1 PCS

27 Hookup of FCUs in corridor and pipe connection relocation D1 PCS

28 Remove and install new insulation and cladding of piping for last previous item D1 LOT

29 ROOF FILLING HOSE SHADE and Hanger D1 PCS

30 Cleaning and final paint for DAY 1 Gen pipe connection D1 LOT

31 Pipe connection and installation of Fuel Spill Container D1 Pcs

32 Rectify broken pipe connection in D1 tanks and remove diesel leaked from tank area D1 LOT

33 Rectify diesel leak in 2 " pipe supply line connection D1 LOT

34 for FUEL / 3" Ball valve and reducer with hose FOR ROOF D1 LOT

35

TOTAL

Enjaz Al- arabiya Engineer


Eng/ Mohamed A Elmorsy

SBM PROJECT Engneer


Eng/ Mahmoud Hany
QTY UNIT PRICE TOTAL REMARKS
1.00 600.00 600.00 with hose and nippl

147.00 75.00 11,025.00 each duct duct is 4 m2

1.00 9,500.00 9,500.00

1.00 9,500.00 9,500.00

1.00 800.00 800.00

21.00 140.00 2,940.00

2.10 140.00 294.00

2.10 140.00 294.00

3.00 180.00 540.00

3.00 180.00 540.00


2.00 334.00 668.00

2.00 2,265.00 4,530.00

6.00 300.00 1,800.00

2.00 220.00 440.00

2.00 150.00 300.00

1.00 70,000.00 70,000.00

40.00 550.00 22,000.00

16.00 180.00 2,880.00

1.00 5,000.00 5,000.00

1.00 1,500.00 1,500.00

1.00 2,000.00 2,000.00

24.00 920.00 22,080.00

24.00 210.00 5,040.00

1.00 48,000 48,000.00

1.00 18,000.00 18,000.00


1.00 700.00 700.00

2.00 2,000.00 4,000.00

1.00 3,000.00 3,000.00

1.00 3,500.00 3,500.00

1.00 600.00 600.00

2.00 750.00 1,500.00

1.00 5,000.00 5,000.00

1.00 1,000.00 1,000.00

1.00 5,000.00 5,000.00

264,571.00

SBM PROJECT MANGER


Eng/ Ahmad Al-Zou'bi