IOSH Risk Assessment Format

Name of Assessor: Talha Faisal Abbasi ( Talha Trader) Date & Time: _04-03-2024__5:00PM_

Area of RA: AS Steel Manufacturing Company______

General Description: Activity: Construction of Concrete block wall, Fabrication of structure building structure, Excavation for new Building foundation.
Participant :_Site Manager, Site Supervisor, Workers, visitors(Inspectors Managers) Equipment's : Excavators, Scaffolding, Ladder, Drills, Grinders,
Generator(Power source), Hand Tools ( Spanner, Hammer etc)__________________________________________________________________________

New risk rating (R Action monit Action mo


What is the haz Who might be h How might peopl Risk rating
Existing risk control measures Additional controls /Suggested esidual) ored by who nitored by
ard? armed? e be harmed? Perform External and Internal Research
L/P C/S R L C R m? when?
01) Eliminate Extra/over load
02) Remove / or make proper
distance of generator( any machinery 01) SS 01) Same Day
Work at height Fall from height that make vibration or movement. 02) SS 02) Same Day
01) Maintenance 03) Area Barricade 03) SS 03) Same Day
( Falling Hazard 01) Workers M = Cuts & Bruises 02) Supervision 04) SS 04) 01 Day
04) Fall Arrest
while working (Mason /fabricators 2 3 6 05) Safety Guide Rail 1 2 2 05) SS 05) 01 Day
03) Rest Break
on scaffolding/ M = Fractures 06) UN-even Floor 06) SM 06) 05 Day
/ Scaffolder )
climbing via 07) Training / Experience 07) SM 07) 03 Day
ladder) F = Leading To 08) Reduce work load/ Job Rotation 08) SM 08) 02 Day
Death 08) Inspection 09) SM 09) 02 Day
09) PPE’s 10) SS 10) 01 Day

Get Hurt From any


Falling Object falling object 01) Barricade Area / Exclusion Zone 01) SS 01) Same Day
02) Netting or screens 02) SS 02) 02 Days
M = Bruises 03) Tool lanyard 03) SS 03) 02 Days
( Hit from any 01) Worker 01) Supervision 04) Proper Toe Board 04) SS 04) 01 Day
falling object 02) Over heads M = Head injury, 3 3 9 1 2 2 05) SM 05) 05 Days
05) Debris Chutes
like tools 03) visitors shoulder injury, 06) SM 06) 03 Days
machinery or Fractures 06) Training 07) SS 07) 02 Days
construction 07) PPE’s
material) F = Leading To
Death

Load Handling
01) Worker
Excavation &
Cave-ins 02) Over heads
Failure
IOSH Risk Assessment Format

Risk Ratting Scale 3x3

L = 1, 2, 3

(1 = Max Controls OR Effective Safety Implementation)


(2 = Some Controls are missing, situation is tolerable, the existing controls need to be hardened)
(3 = Less or inadequate controls, situation is dangerous)

C = 1, 2, 3

Minor = 1, Serious = 2, Fatal = 3

Review date: ________________________ Trainer Name: Ahmed Raza