This document provides a checklist for preventative maintenance of a jockey pump. The checklist includes 7 items to inspect the pump-motor operation, clean external surfaces and air inlets, check for water leaks, clean the foundation, lubricate bearings, check operating parameters, and ensure the control panel is functioning properly. The checklist also includes sections to record any spare parts, materials, or tools used during maintenance.
This document provides a checklist for preventative maintenance of a jockey pump. The checklist includes 7 items to inspect the pump-motor operation, clean external surfaces and air inlets, check for water leaks, clean the foundation, lubricate bearings, check operating parameters, and ensure the control panel is functioning properly. The checklist also includes sections to record any spare parts, materials, or tools used during maintenance.
This document provides a checklist for preventative maintenance of a jockey pump. The checklist includes 7 items to inspect the pump-motor operation, clean external surfaces and air inlets, check for water leaks, clean the foundation, lubricate bearings, check operating parameters, and ensure the control panel is functioning properly. The checklist also includes sections to record any spare parts, materials, or tools used during maintenance.
This document provides a checklist for preventative maintenance of a jockey pump. The checklist includes 7 items to inspect the pump-motor operation, clean external surfaces and air inlets, check for water leaks, clean the foundation, lubricate bearings, check operating parameters, and ensure the control panel is functioning properly. The checklist also includes sections to record any spare parts, materials, or tools used during maintenance.
1. Check Pump-motor operation for noise and vibration. Ok
2. Cleaning of pump-motor set, wipe off dirt, dust, oil, or other liquid from external Ok surfaces. Remove dirt on the ventilating air inlets. This can be carried into the motor windings and may cause overheating or insulation breakdown. 3. Check for water leaks from the mechanical seal/packing glands. Add and adjust Ok packing when the water drops exceeds by 6 but a maximum of 10 drops. 4. Clean the concrete foundation of the pump set. Ok 5. Check/lubricate Pump-motor bearings. Ok 6. Check parameters of operation stage: voltage, current, frequency, RPM, Ok discharge and suction pressure, pressure vessel pressure, and cut-in/cut-off of pressure switch setting.
Pressure cut-in: 80 psi
Pressure cut-off: 85 psi 7. Check panels, indicator/pilot lights and ensure O-H-A switch in normal (AUTO) In Auto operation position before leaving the work area. Retighten terminal connections as necessary.
Pump Materials/Spare parts/ Tools used Consumable used