(a) 1:3
(b) 1:4
(c) 1:6
(d) 1:8
5. The essential requirement to prepare a good estimate is :
(a) Lift
(b) lead
(c) Pushta
(d) None of these
9. The normal lift allowed for earth work in excavation is:
(a) 5m
(b) 1.5m
(c) 2m
(d) 4m
10. The water charge for rate analysis of P.C.C, R.C.C, plastering,
brickwork etc is
(a) 112 %
(b) 123 %
1
(c) %
3
1
(d) %
5
11. The contracts profit is taken at the rate of ______ of the
cost of material and Labour.
(a) 5%
(b) 15%
(c) 10%
(d) 20%
12. The total overhead costs can be broadly grouped in
(a) PCU
(b) D.S.R
(c) S.S.R
(d) PWD
14. The weight of one bag of cement is
(a) 50 kg
(b) 100 kg
(c) 150 kg
(d) 200kg
15. 1 m³ is equal to_______ quintal of steel.
(a)74.5
(b) 75.5
(c) 79.5
(d) 78.5
16. The number of bag of cement in one cubic meter is
(a) 50 bags
(b) 40 bags
(c) 30 bags
(d) None
17. The weight of cement in 1 m³ volume is
(a) 28.8bags
(b) 30bags
(c) 30.8bags
(d) None
18. The proportion of concrete mix for M-15 grade is
(a) 1:1:2
(b) 1:2:4
(c) 1:1.5:3
(d) None
19. The proportion of concrete mix for M-25 grade is
(a) 1:1:2
(b) 1:2:4
(c) 1:1.5:3
(d) None
20. The material required for brickwork is
(a) brick
(b) sand
(c) cement
(d) All of the
(21) The essential requirement to prepare a good estimates:
(a) 20 cm x 10 cm x 10 cm
(b) 19 cm x 9 cm x 9 cm
(c) Both (a) and (b)
(d) None of these
(23) Brick flat soling is measured in:
(a) M
(b) m²
(c) m³
(d) All of the above
(24) In long wall and short wall method of building estimate short
wall is measured?
(a) 2%
(b) 3%
(c) 4%
(d) 5% or more
(27) The quantity of wood work for chaukhat of doors and
windows is calculated in:
(a) m
(b) m²
(c) m³
(d) All of the above
(28) Which of the following is not included in plinth area?
(a)1.5 to 2%
(b) 5 to 7%
(c) 10 to 12%
(d) None of these
(30) In which work thickness is specified?
(a) Plaster
(b) Painting
(c) White washing
(d) All of the above
(31) The volume of cement required to prepare 10m cement
concrete (1:2:4) is:
(a) 1.5 m³
(b) 2.0 m³
(c) 2.2 m³
(d) 2.8 m
(32) In building estimate, the area is measured correct to the nearest of:
(a)0.01 m
(b) 0.05 m
(c) 0.10 m
(d) None of these
(33) Unit weight of steel in KN/m³ is:
(a)60
(b) 70
(c) 75
(d) 78.5
(34)The additional length of one hook in the steel reinforcement rod is:
(Where d dia. of rod)
(a)3d
(b) 6d
(c) 9d
(d) 12d
(35)The expenses of items which do not come under any regular
head of items and the cost of unforeseen items are called:
(a) Extra expenses
(b) Contingencies
(c) Both (a) and (b)
(d) (d) None of these
(36) If d be the height of banking B be the formation width and 1:S be
side slope then total cross sectional area will be:
a. Bd+S𝑑2
b. Bd x Sd
c. Bd Sd
d. None of these
(37)Damp proof course (D.P.C.) is provided at:
(a) Ground level
(b) Sill level
(c) Plinth level
(d) All of the above
(38)The rate of an item of work depends on its: (b)
a. Specification
b. Quality
c. Both (a) and (b)
d. None of these