DAILY RIG MOVE SAFETY MEETING

LTA PERSONAL LEADING THE MEETING DATE. LOCATION


300 days Khaled Ahmed Rig Manager NC-115 R33 Old Location
Esam Zubaydah HSE Supervisor NC112 –M20 New Location
Rig move Safely 27.6.2023 Items Discussed:

Rigging up safely – connecting drilling line


1. Ensure using of tag lines
2. Supervisor should inspect the lifting chain
3. All hand tools should be clean to avoid any slip hazard
4. Avoid pinch point
5. Wear proper PPE
6. Ensure that the tension applied same on all legs otherwise slake again and adjust the chain length to
have same tension on all legs
7. Close supervision in place Qualified banks man to give signal to crane operator
8. Ensure safe position of all involved persons
9. No working allowed under working area
10. Do not rush into a job stop, plan and consider alternative safe work methods to remove and reduce the
hazard
11. Timesheet review,

Attendants
Signature Position Name No
Nightpusher 1
Driller Fares Abudayaf 2
Asst Driller Zayad Mohamed Elhashmi 4
Asst Driller Abdulmajeed salem 5
Derrickman Abdulmajeed abdulah aljjadoor 7
Floorman Idres Ali Barkah 8
Floorman Eihab Almabrouk 9
Floorman Almoayed Mohamed Kshedan 10
Floorman Abdalhakem Saleh Emam 11
Floorman Nasar salah almahdi 12
Floorman Nader Naji Alabayed 13
Rousabout Ali Saeed Ali 14
Floorman Ayoub Mohamed Ayad 15
Rousabout Saleh Mohamed Shakoo
Sr Electrician Abdalhamed Beddiaf 16
Sr Mechanic Huassni Noori abdulwafi 17
Asst Electrician Abdulateef Abdusalam Matoug 18
Asst Electrician Murad Hsain Mohamed 19
Asst Mechanic Suhail elmabrouk Ali 20
Asst Mechanic Mouad naser abdullah 21
Welder Abdulkareem Ali abdusalam 22
Forklift Opt’er Seraj Madi 23
Kenworth Driver Suliman Mohamed 24
Forklift opt Mohamed Ali Khair 25
26
27
28
29
30

Signature HSE Supervisor


Signature Rig Manager

Safety Supervisor
Esam Zubaydah