Transformer Data

You might also like

Download as docx, pdf, or txt
Download as docx, pdf, or txt
You are on page 1of 14

(7.

1) Details of Equipment with Observations


Sr.No. Name of Asset Regulator (max dB) Tertiary Rectifier (max dB)
HT Side LT side (max dB) AC side DC side
Unit-01 Rϕ 8.0 Rϕ 8.3 Rϕ 17.3
Transformer Yϕ 8.3 Yϕ 8.2 9.1 Yϕ 17.5 -
1 Bϕ 8.2 Bϕ 8.1 Bϕ 14.9
Observation Nil
Recommendation Details of the report are mentioned in the Detailed Ultrasound Report 1 (A)and (B)
Unit-02 Rϕ 7.9 Rϕ 8.2 Rϕ 21.2
Transformer Yϕ 8.9 Yϕ 8.2 8.3 Yϕ 16.9 -
2 Bϕ 8.1 Bϕ 8.2 Bϕ 17.9
Observation Nil
Recommendation Details of the report are mentioned in the Detailed Ultrasound Report 2 (A)and (B)
Unit-03 Rϕ 8.1 Rϕ 8.4 Rϕ 17.6
Transformer Yϕ 8.5 Yϕ 8.2 8.4 Yϕ 16.3 -
3 Bϕ 7.9 Bϕ 8.2 Bϕ 14.8
Observation Nil
Recommendation Details of the report are mentioned in the Detailed Ultrasound Report 3 (A)and (B)
Unit-04 Rϕ 8.1 Rϕ 8.1 Rϕ 17.5
Transformer Yϕ 8.2 Yϕ 8.1 10.4 Yϕ 15.0 -
4 Bϕ 8.5 Bϕ 8.2 Bϕ 20.0
Observation Nil
Recommendation Details of the report are mentioned in the Detailed Ultrasound Report 4 (A)and (B)
Unit-05 Rϕ 8.1 Rϕ 8.2 Rϕ 17.6
Transformer Yϕ 8.1 Yϕ 8.3 8.4 Yϕ 19.0 -
5 Bϕ 8.4 Bϕ 8.2 Bϕ 17.5
Observation Nil
Recommendation Details of the report are mentioned in the Detailed Ultrasound Report 5 (A)and (B)

Sr.No. Name of Asset HT side LT side Observation Recommendations


(max dB) (max dB)
Auxiliary Rϕ 8.1 Rϕ 8.1 Details of the report are mentioned in
1 Transformer-01 Yϕ 8.2 Yϕ 8.2 Nil the Detailed Ultrasound Report 6.
Bϕ 8.2 Bϕ 8.3
Auxiliary Rϕ 8.1 Rϕ 8.1 Details of the report are mentioned in
2 Transformer-02 Yϕ 7.8 Yϕ 8.1 Nil the Detailed Ultrasound Report 7.
Bϕ 8.2 Bϕ 8.3
Report Reference: Report No.01(A)
Date of Inspection 19 Dec 2023 Inspection done by: Vinod V. V
Unit-01
Equipment Name: Location Regulator
Transformer
Partial Discharge
Application: dB Value 7.5/8.3 dB (Min/Max)
Detection

HT side LT side

R Phase R Phase

Y Phase Y Phase

B Phase B Phase

Observation: Ultrasound intensity of all phases less than 30 dB.


FFT Analysis of the Ultrasonic signature did not show problem related
Conclusion:
to Partial Discharge.

Repair Priority: No repairs required.

1. On half yearly basis undertake physical inspection and Insulation


Resistance Test between Phase to Phase and Phase to Ground. Undertake
Recommendation/
necessary steps to improve Insulation Resistance if found week.
Suggested Corrective
2. Carryout tests suggested in Para 8(f) above if sound level increases.
action:
3. Regularly monitor using Ultrasound Technology to assess the asset
condition and undertake necessary repairs as required.
Date of Analysis and Report prepared
01th Jan 2024 Vinod V. V
Report preparation by:-
Report Reference: Report No.01(B)
Inspection done
Date of Inspection 19 Dec 2023 Vinod V. V
by:
Unit-01
Equipment Name: Location Rectifier
Transformer
Partial Discharge 15.4/17.5 dB
Application: dB Value
Detection (Min/Max)
AC side

R Phase

Y Phase

B Phase

Observation: Ultrasound intensity of all phases less than 30 dB.


FFT Analysis of the Ultrasonic signature did not show problem related
Conclusion:
to Partial Discharge.

Repair Priority: No repairs required.

1. On half yearly basis undertake physical inspection and Insulation


Resistance Test between Phase to Phase and Phase to Ground. Undertake
Recommendation/
necessary steps to improve Insulation Resistance if found week.
Suggested Corrective
2. Carryout tests suggested in Para 8(f) above if sound level increases.
action:
3. Regularly monitor using Ultrasound Technology to assess the asset
condition and undertake necessary repairs as required.
Date of Analysis and Report prepared
01th Jan 2024 Vinod V. V
Report preparation by:-

Report Reference: Report No.02(A)


Date of Inspection 19 Dec 2023 Inspection done by: Vinod V. V
Unit-02
Equipment Name: Location Regulator
Transformer
Partial Discharge
Application: dB Value 7.8/8.2 dB (Min/Max)
Detection

HT side LT side

R Phase R Phase

Y Phase Y Phase

B Phase B Phase

Observation: Ultrasound intensity of all phases less than 30 dB.


FFT Analysis of the Ultrasonic signature did not show problem related
Conclusion:
to Partial Discharge.

Repair Priority: No repairs required.

1. On half yearly basis undertake physical inspection and Insulation


Resistance Test between Phase to Phase and Phase to Ground. Undertake
Recommendation/
necessary steps to improve Insulation Resistance if found week.
Suggested Corrective
2. Carryout tests suggested in Para 8(f) above if sound level increases.
action:
3. Regularly monitor using Ultrasound Technology to assess the asset
condition and undertake necessary repairs as required
Date of Analysis and Report prepared
01th Jan 2024 Vinod V. V
Report preparation by:-

Report Reference: Report No.02(B)


Date of Inspection 19 Dec 2023 Inspection done Vinod V. V
by:
Unit-02
Equipment Name: Location Rectifier
Transformer
Partial Discharge 17.2/21.7 dB
Application: dB Value
Detection (Min/Max)
AC side

R Phase

Y Phase

B Phase

Observation: Ultrasound intensity of all phases less than 30 dB.


FFT Analysis of the Ultrasonic signature did not show problem related
Conclusion:
to Partial Discharge.

Repair Priority: No repairs required.

1. On half yearly basis undertake physical inspection and Insulation


Resistance Test between Phase to Phase and Phase to Ground.
Recommendation/ Undertake necessary steps to improve Insulation Resistance if found
Suggested Corrective week.
action: 2. Carryout tests suggested in Para 8(f) above if sound level increases.
3. Regularly monitor using Ultrasound Technology to assess the
asset condition and undertake necessary repairs as required.
Date of Analysis and Report prepared
01th Jan 2024 Vinod V. V
Report preparation by:-

Report Reference: Report No.03(A)


Date of Inspection 19 Dec 2023 Inspection done by: Vinod V. V
Equipment Name: Unit-03 Location Regulator
Transformer
Partial Discharge
Application: dB Value 7.7/8.2 dB (Min/Max)
Detection

HT side LT side

R Phase R Phase

Y Phase Y Phase

B Phase B Phase

Observation: Ultrasound intensity of all phases less than 30 dB.


FFT Analysis of the Ultrasonic signature did not show problem related
Conclusion:
to Partial Discharge.

Repair Priority: No repairs required.

1. On half yearly basis undertake physical inspection and Insulation


Resistance Test between Phase to Phase and Phase to Ground. Undertake
Recommendation/
necessary steps to improve Insulation Resistance if found week.
Suggested Corrective
2. Carryout tests suggested in Para 8(f) above if sound level increases.
action:
3. Regularly monitor using Ultrasound Technology to assess the asset
condition and undertake necessary repairs as required.
Date of Analysis and Report prepared
01th Jan 2024 Vinod V. V
Report preparation by:-

Report Reference: Report No.03(B)


Inspection done
Date of Inspection 19 Dec 2023 Vinod V. V
by:
Unit-03
Equipment Name: Location Rectifier
Transformer
Partial Discharge 17.2/21.7 dB
Application: dB Value
Detection (Min/Max)
AC side

R Phase

Y Phase

B Phase

Observation: Ultrasound intensity of all phases less than 30 dB.


FFT Analysis of the Ultrasonic signature did not show problem related
Conclusion:
to Partial Discharge.

Repair Priority: No repairs required.

1. On half yearly basis undertake physical inspection and Insulation


Resistance Test between Phase to Phase and Phase to Ground.
Recommendation/ Undertake necessary steps to improve Insulation Resistance if found
Suggested Corrective week.
action: 2. Carryout tests suggested in Para 8(f) above if sound level increases.
3. Regularly monitor using Ultrasound Technology to assess the
asset condition and undertake necessary repairs as required.
Date of Analysis and Report prepared
01th Jan 2024 Vinod V. V
Report preparation by:-

Report Reference: Report No.04(A)


Date of Inspection 19 Dec 2023 Inspection done by: Vinod V. V
Unit-04
Equipment Name: Location Regulator
Transformer
Partial Discharge
Application: dB Value 7.2/8.5 dB (Min/Max)
Detection
HT side LT side

Observation: Ultrasound intensity of all phases less than 30 dB.


FFT Analysis of the Ultrasonic signature did not show problem related
Conclusion:
to Partial Discharge.

Repair Priority: No repairs required.

1. On half yearly basis undertake physical inspection and Insulation


Resistance Test between Phase to Phase and Phase to Ground. Undertake
Recommendation/
necessary steps to improve Insulation Resistance if found week.
Suggested Corrective
2. Carryout tests suggested in Para 8(f) above if sound level increases.
action:
3. Regularly monitor using Ultrasound Technology to assess the asset
condition and undertake necessary repairs as required.
Date of Analysis and Report prepared
01th Jan 2024 Vinod V. V
Report preparation by:-

Report Reference: Report No.04(B)


Inspection done
Date of Inspection 19 Dec 2023 Vinod V. V
by:
Unit-04
Equipment Name: Location Rectifier
Transformer
Partial Discharge 14.5 / 17.5 dB
Application: dB Value
Detection (Min/Max)
AC side

R Phase

Observation: Ultrasound intensity of all phases less than 30 dB.


FFT Analysis of the Ultrasonic signature did not show problem related
Conclusion:
to Partial Discharge.

Repair Priority: No repairs required.

1. On half yearly basis undertake physical inspection and Insulation


Resistance Test between Phase to Phase and Phase to Ground.
Recommendation/ Undertake necessary steps to improve Insulation Resistance if found
Suggested Corrective week.
action: 2. Carryout tests suggested in Para 8(f) above if sound level increases.
3. Regularly monitor using Ultrasound Technology to assess the
asset condition and undertake necessary repairs as required.
Date of Analysis and Report prepared
01th Jan 2024 Vinod V. V
Report preparation by:-

Report Reference: Report No.05(A)


Date of Inspection 19 Dec 2023 Inspection done by: Vinod V. V
Unit-05
Equipment Name: Location Regulator
Transformer
Partial Discharge
Application: dB Value 7.1/8.3 dB (Min/Max)
Detection
HT side LT side

R Phase R Phase

Observation: Ultrasound intensity of all phases less than 30 dB.


FFT Analysis of the Ultrasonic signature did not show problem related
Conclusion:
to Partial Discharge.

Repair Priority: No repairs required.

1. On half yearly basis undertake physical inspection and Insulation


Resistance Test between Phase to Phase and Phase to Ground. Undertake
Recommendation/
necessary steps to improve Insulation Resistance if found week.
Suggested Corrective
2. Carryout tests suggested in Para 8(f) above if sound level increases.
action:
3. Regularly monitor using Ultrasound Technology to assess the asset
condition and undertake necessary repairs as required.
Date of Analysis and Report prepared
01th Jan 2024 Vinod V. V
Report preparation by:-

Report Reference: Report No.05(B)


Inspection done
Date of Inspection 19 Dec 2023 Vinod V. V
by:
Unit-05
Equipment Name: Location Rectifier
Transformer
Partial Discharge
Application: dB Value 14/19 dB (Min/Max)
Detection
AC side

R Phase

Observation: Ultrasound intensity of all phases less than 30 dB.


FFT Analysis of the Ultrasonic signature did not show problem related
Conclusion:
to Partial Discharge.

Repair Priority: No repairs required.

1. On half yearly basis undertake physical inspection and Insulation


Resistance Test between Phase to Phase and Phase to Ground.
Recommendation/ Undertake necessary steps to improve Insulation Resistance if found
Suggested Corrective week.
action: 2. Carryout tests suggested in Para 8(f) above if sound level increases.
3. Regularly monitor using Ultrasound Technology to assess the
asset condition and undertake necessary repairs as required.
Date of Analysis and Report prepared
01th Jan 2024 Vinod V. V
Report preparation by:-

Report Reference: Report No.06


Date of Inspection 19 Dec 2023 Inspection done by: Vinod V. V
Auxiliary
Equipment Name: Transformer-01
Location
Partial Discharge
Application: dB Value 7.1/8.3 dB (Min/Max)
Detection
HT side LT side

R Phase R Phase

Observation: Ultrasound intensity of all phases less than 30 dB.


FFT Analysis of the Ultrasonic signature did not show problem related
Conclusion:
to Partial Discharge.

Repair Priority: No repairs required.

1. On half yearly basis undertake physical inspection and Insulation


Resistance Test between Phase to Phase and Phase to Ground. Undertake
Recommendation/
necessary steps to improve Insulation Resistance if found week.
Suggested Corrective
2. Carryout tests suggested in Para 8(f) above if sound level increases.
action:
3. Regularly monitor using Ultrasound Technology to assess the asset
condition and undertake necessary repairs as required.
Date of Analysis and Report prepared
01th Jan 2024 Vinod V. V
Report preparation by:-

Report Reference: Report No.07


Date of Inspection 19 Dec 2023 Inspection done by: Vinod V. V
Auxiliary
Equipment Name: Transformer-02
Location
Partial Discharge
Application: dB Value 7.2/8.3 dB (Min/Max)
Detection
HT side LT side

R Phase R Phase

Observation: Ultrasound intensity of all phases less than 30 dB.


FFT Analysis of the Ultrasonic signature did not show problem related
Conclusion:
to Partial Discharge.

Repair Priority: No repairs required.

1. On half yearly basis undertake physical inspection and Insulation Resistance


Test between Phase to Phase and Phase to Ground. Undertake necessary steps to
Recommendation/
improve Insulation Resistance if found week.
Suggested Corrective
2. Carryout tests suggested in Para 8(f) above if sound level increases.
action:
3. Regularly monitor using Ultrasound Technology to assess the asset
condition and undertake necessary repairs as required.
Date of Analysis and Report prepared
01th Jan 2024 Vinod V. V
Report preparation by:-

8.(f) If the sound intensity increases further, please undertake following tests: -
i) Transformer Turn Ratio Test - For all taps
ii) Transformer Winding Resistance Test - For all taps.
iii) Magnetic Balance Test
iv) Magnetizing Current
v) Capacitance and Tan Delta Test on windings and Bushings
vi) Insulation Resistance Test and PI (Core, Tank and Frame insulation resistance test)
vii) Dirana Test for Transformers
viii) Surge Arrester - Tan Delta / Leakage Current Test

You might also like