This document provides a quantity check and clarification for the Pacific Bike project with amounts in three main categories:
A) Architecture quantity check of over 5.5 billion for the main building and over 86 million for the support building, with a deduction of over 4.4 billion for certain interior items.
B) Structure quantity check of over 9.1 billion for the main building and deductions of nearly 2 billion for infrastructure, with additions of over 368 million for the support building.
C) The total summary amount for the project is over 10.2 billion.
This document provides a quantity check and clarification for the Pacific Bike project with amounts in three main categories:
A) Architecture quantity check of over 5.5 billion for the main building and over 86 million for the support building, with a deduction of over 4.4 billion for certain interior items.
B) Structure quantity check of over 9.1 billion for the main building and deductions of nearly 2 billion for infrastructure, with additions of over 368 million for the support building.
C) The total summary amount for the project is over 10.2 billion.
This document provides a quantity check and clarification for the Pacific Bike project with amounts in three main categories:
A) Architecture quantity check of over 5.5 billion for the main building and over 86 million for the support building, with a deduction of over 4.4 billion for certain interior items.
B) Structure quantity check of over 9.1 billion for the main building and deductions of nearly 2 billion for infrastructure, with additions of over 368 million for the support building.
C) The total summary amount for the project is over 10.2 billion.
QUANTITY CHECK - CLARIFICATION MEETING, DATED 31 Jan - 12 Feb 2024
No. Description Amount
A Architecture qty. check 5.533.619.504 1 Main Building 5.447.255.000 - Block Wall + Cement Plaster 595.398.092 - Door and Window 3.604.320.900 - Façade ACP 711.719.700 - Canopy 456.829.092 - Painting 78.987.216 2 Support Building 86.364.504 - Block Wall + Cement Plaster 75.008.788 - Painting (supportB) 11.355.716 B Item Take Out -4.429.558.993 - Internal Partition -1.738.818.192 - HT/Ceramic (Floor Finishing) -1.441.517.780 - Ceiling -277.463.286 - Internal paint -267.367.121 - Furniture -475.968.840 - Backdrop -228.423.774
C Structure qty check 9.147.468.516
1 Main building 10.694.290.309 Pekerjaan Pile Cap 60.020.214 Pekerjaan Tie Beam -999.153.579 Pekerjaan Kolom Pedestal K1 1.559.772.995 Pekerjaan Kolom K2 141.427.672 Pekerjaan Kolom Pedestal K3 -2.295.168.227 Pekerjaan Kolom K4 224.470.899 Block wall Gedung A -26.811.459 Block wall Gedung B 257.391.045 DINDING GESER LIFT -103.853.373 Dinding geser -18.738.677 PLAT LANTAI G-A (+0,00 M) 15.991.716 PLAT LANTAI G-A (+8,00 M) 1.608.256.806 PLAT LANTAI G-A (+16,00 M) 1.608.244.125 PLAT LANTAI G-B (+0,00 M) 15.991.716 PLAT LANTAI G-B (+8,00 M) 2.703.268.248 PLAT LANTAI G-B (+16,00 M) 1.496.574.741 PLAT LANTAI kantor (+4,00 M) -19.008.524 PLAT LANTAI kantor (+8,00 M) 59.786.543 PLAT LANTAI KANTOR (+12,00 M) 59.786.543 PLAT LANTAI KANTOR (+16,00 M) 45.039.863 PLAT LANTAI KANTOR (+19,00 M) 260.985.593 PLAT LANTAI KANTOR (+22,00 M) -50.994.637 PLAT LANTAI KANTOR (+24,00 M) 4.411.902 LANTAI BETON 2.788.033.307 PAGAR KELILING (FENCING) 766,65 meter 1.298.564.856 Project : PACIFIC BIKE QUANTITY CHECK - CLARIFICATION MEETING, DATED 31 Jan - 12 Feb 2024
No. Description Amount
2 Infrastructure qty check -1.914.907.727
DRAINAGE U-dith 65.261.893 BOX CULVERT -4.579.676.313 JALAN AKSES DALAM 1.294.375.804 PAGAR KELILING (FENCING) 766,65 meter 1.305.130.890
3 Support Building 368.085.934
Ruang Thiner 14.912.099 Ruang TPS LB3 4.295.041 Ruang TPS Domestik 10.902.836 Ruang Tunggu supir 5.965.094 Ground Tank 329.169.476 Ruang Pos Jaga 2.841.388