Download as pdf or txt
Download as pdf or txt
You are on page 1of 88

Welcome to

Environmental
and Social Report
he Australia
July to December 2015

Pacific LNG
brand.

Australia Pacific LNG


Brand Guidelines Edition 2.5
May 2011

Australia Pacific LNG Environmental and Social Report 1


Contents
Executive Summary 02 7. Sustainable Resource Management 52
1. Introduction 04 7.1 Agricultural Land 53
2. Construction Overview 06 7.2 Water Management 53
2.1 
Upstream Construction 07 7.3 Raw Materials 57
2.2 Upstream Production Operations 07 7.4 Gas Industry Social Environmental
Research Alliance (GISERA) 58
2.3 Downstream Construction, Commissioning and Start-up 08
7.5 Key Performance Indicators 58
First LNG Cargo Milestone Achieved 09
CSG: Boom Time Benefits 59
3. Safety, Health, Environment and Social Management 10
8. Community, Stakeholders and Social Management 60
3.1 Approach 11
8.1 Stakeholder Communication and Consultation 61
3.2 Federal and State Impact Assessment Approvals 12
8.2 Local Content 62
3.3 Management of Change 13
Local Supplier of Ethylene Sourced for Australia Pacific LNG 63
3.4 Verification and Assurance 14
8.3 Community Grievance and Dispute Resolution 64
3.5 Conformance 16
8.4 Collaborative Industry Initiatives 64
3.6 Environment and Social Milestones 16
8.5 Community Investment 65
4. Labour and Working Conditions 17
8.6 Land Access 76
4.1 Hazard Management 19
8.7 Indigenous People 77
4.2 Safety Performance 20
Funding Boost for Thornhill Training Centre 79
4.3 Shift Work and FIFO Regimes 23
8.8 Cultural Heritage 80
4.4 Diversity 24
8.9 Key Performance Indicators 81
4.5 Training 25
Appendix – Abbreviations and Glossary of Terms 82
4.6 Wellbeing and Accommodation 27
Permanent Medical Centre Now Open at the Australia
Pacific LNG Facility 28
4.7 Transition to Operations 29
4.8 Key Performance Indicators 29
5. Pollution Prevention and Abatement 30
5.1 Air Emissions 31
5.2 Noise and Vibration 33
5.3 Waste Management 34
5.4 Environmental Incidents, Notifications and Investigations 39
5.5 Spill Prevention and Response 41
5.6 Key Performance Indicators 41
6. Biodiversity Conservation 42
6.1 Ecological Management 43
Quoin Island Turtle Rehabilitation Centre 44
6.2 Quarantine 45
6.3 Weed, Plant Pathogen and Pest Management 46
6.4 Reinstatement 47
6.5 Offset Strategy 48
Fish Ladder Installed at Condamine Weir 50
6.6 Key Performance Indicators 51

Australia Pacific LNG Environmental and Social Report 1


Executive summary

Environmental and Social was first produced from Train 1 of the approximately 67 percent of all areas
Performance Downstream facility on 9 December disturbed to date.
2015, and the first shipment of LNG
The shareholders of Australia Pacific An additional direct offset on the
departed the Australia Pacific LNG
LNG aim to develop the Business in Colamba property was included in the
facility on Curtis Island on 9 January
a sustainable manner by identifying portifolio, located north-east of Miles.
2016. A total of three produced cargoes
and assessing potential impacts, and The Colamba offset will compensate
were shipped in January to customers
introducing sustainable practices for Project impacts on Brigalow, fauna
including Sinopec, pursuant to the
and solutions to manage them. This habitat and wetland values not yet
Sinopec SPA.
approach, detailed in the Project’s acquitted by existing offsets.
Environmental Impact Statement,
Safety, Health, and The Dukes Plain Offset and
reflects the existing practices of the
Environmental Management Rehabilitation Management Plan, was
Project’s joint venture partners, Origin
The Business health and safety goal approved by the Australian Government
Energy, ConocoPhillips and Sinopec,
remains at zero injuries across all Department of the Environment
and is integral to developing the
activities. During this period, Australia in October 2015. On the ground
Business in a transparent, accountable
Pacific LNG reported 24 recordable management activities continued to be
and sustainable manner.
injuries, representing a solid downward implemented. Implementation of the
This, the eighth Environmental and Social trend in the Total Recordable Injury Inverness offset site also continued with
Report for the Project, covers the period Frequency Rate (TRIFR), which Cycad seedlings planted.
between July and December 2015, improved by 19 percent from 3.1 in Work continued in the Monte Christo
and provides updates on the Project’s June to 2.5 at 31 December 2015. offset site over the past six months
progress, safety and environmental
The responsibility of managing on the transfer of the remaining
management, and benefits to local and
environmental impact is taken seriously. freehold allotments to the Queensland
regional communities.
Strict government environmental Government for inclusion in the
Construction Overview regulations result in the thorough and Queensland Conservation Estate.
As at 31 December 2015 the Business transparent management of water
employed 5,793 full-time equivalent (produced, storm and waste), emissions
(FTE). Upstream employed 2,766 FTEs (waste, greenhouse gases and dust),
including Operations and Project delivery land, and biodiversity.
while 2,987 FTEs were engaged in Our environmental incident frequency
Downstream Operations and Project rate continues to decrease and as
delivery. The Australia Pacific LNG at 31 December it stood at 1.35, an
Corporate Office employed 40 FTEs. improvement of 10 percent compared
The Upstream Project was 99 percent with the previous reporting period.
complete at 31 December 2015. 1,272 There were 11 environmental incidents
development wells had been drilled reported to the Regulatory Authorities,
and 1,090 wells commissioned. All key 10 classified as minor and one incident
facilities are now commissioned and classified as moderate.
the Upstream Project is complete with Biodiversity Conservation
the only activities remaining relating to
contract ‘close out’. The rehabilitation effort continued with
901 ha being reinstated in the reporting
The Downstream Project was 96 percent period, bringing the total to 6,258
complete at 31 December 2015. LNG ha of reinstated land, representing

2 Australia Pacific LNG Environmental and Social Report


Sustainable Resource long beyond the life of the Project.
Management The framework for these partnerships
is detailed in our Social Impact
During the reporting period, 11,920
Management plans. Australia Pacific
megalitres (Ml) of CSG water was
LNG continues to support a range
produced, a 15 percent increase
of community initiatives including a
over the previous period, reflecting
vocational education training program
the increase in the number of wells
to deliver civil construction qualifications
brought online. The Business’ effort to
for indigenous participants, a
apply treated CSG water to beneficial
program to increase the capacity of
use continues to expand with the
new and existing businesses in the
provision of water for irrigation to local
South West including Aboriginal and
landholders and the ramp up of aquifer
Torres Strait Islander businesses,
re-injection. These factors allowed a
affordable community housing, and
total of 9,511 Ml or 80 percent of all
two partnerships with local councils to
CSG water produced to be applied to
advance the region’s tourism potential
beneficial use.
and diversify the regional economy.
Community, Stakeholders, During the last six months, Australia
and Social Management Pacific LNG has invested AUD$1.93
million in community projects, bringing
Australia Pacific LNG maintained the total committed investment in this
its commitment to stakeholder area to approximately AUD$41 million.
engagement activities that included
65 formal engagement sessions and
1,622 informal engagement events
including informal presentations, Page Maxson
emails, telephone calls, walk-ins
to regional offices, and sponsored Chief Executive Officer
community events. Activities also Australia Pacific LNG
included employment and information
displays, sponsorship events, specific
Indigenous events, and individual
meetings with local government and
community members.
Approximately 78 percent of the total
Project expenditure to date occurred
in Australia, and 57 percent within
the State of Queensland, bringing
substantial benefits to the national and
local economies.
To contribute positively to local
communities, the Business develops
partnerships to encourage sustainable
development, aiming to deliver benefits

Australia Pacific LNG Environmental and Social Report 3


1. Introduction
Australia Pacific LNG is a Coal Seam Gas (CSG) to
Liquefied Natural Gas (LNG) Business delivering a clean
and sustainable energy source. Australia Pacific LNG is
the largest producer of natural gas in eastern Australia,
supplying gas to power stations to produce lower
emissions electricity, and to major industrial customers,
homes and businesses in South East Queensland.

Australia Pacific LNG is an incorporated Australia Pacific LNG executed a sale-and-


joint venture consisting of Origin (37.5%), purchase agreement—Australia’s largest LNG
ConocoPhillips (37.5%) and Sinopec (25%). sales agreement by annual volume—with Sinopec
Origin is responsible for construction and for 7.6 Mtpa of LNG for 20 years. An agreement
operation of the gas fields and pipeline. for the sale and purchase of approximately 1.0
ConocoPhillips is responsible for construction Mtpa for 20 years has also been signed with
and operation of the LNG facility and Kansai Electric.
associated infrastructure.
Rigorous management systems are applied to
At 31 December 2015 the Business employed control environmental and social impacts of the
5,793 full-time equivalents (FTE) in Australia. Once Business. The Environmental and Social Report,
fully operational, the Business will employ over released every six months, provides updates
2,000 people, boosting regional and national on the construction activity and the sustainable
economies. Importantly, Queensland will have approach to developing the Business. This,
a new, long-term gas processing and export the eighth report for the Business, covers the
industry generating significant benefits at regional, period between July and December 2015 (S2
state and national levels. 2015). It details the construction progress, the
commencement of operations, workforce safety
The Australia Pacific LNG Business consists of:
and health, environmental and social impact
• further development of Australia Pacific LNG’s management activities, and benefits to local and
existing gas fields in the Surat and Bowen regional communities.
basins in southwestern and central Queensland
• construction of a 530 km high pressure gas
pipeline from the gas fields to an LNG Facility
near Gladstone in Queensland
• an LNG Facility on Curtis Island near Gladstone,
the first two trains having a combined
nameplate processing capacity of approximately
9.0 million tonnes per annum (Mtpa).

4 Australia Pacific LNG Environmental and Social Report


Project Summary
Description Project based on Australia’s largest 2P CSG reserves

Size Two trains, each with a nameplate production capacity of 4.5 Mtpa

JV Interests Origin Energy 37.5%; ConocoPhillips 37.5%; Sinopec 25%

Reserves 2P 13,778 PJ, 3P 16,174 PJ – Additional 2,760 PJ (2C)


(as at 30 June 2015) of contingent resources

Off-take 7.6 Mtpa LNG supply for 20 years to JV partner, Sinopec


Agreement 1.0 Mtpa LNG supply for 20 years to Kansai Electric

Timing LNG was first produced from Train 1 of the Downstream facility in
December 2015. The first shipment of LNG departed the Australia
Pacific LNG facility on Curtis Island in January 2016.

Figure 1.1 Project location

Australia Pacific LNG Environmental and Social Report 5


2. Construction
Overview
Project Component Percent complete on 31 December 2015

Upstream 99%

Downstream 96%

Origin manages the construction and operation of The LNG facilities comprise two gas processing
the Upstream Project, including the development trains, two LNG storage tanks, and standard
of CSG resources and delivery of gas to feed the infrastructure services, including power, water,
LNG plant. The Upstream Project involves drilling telecommunications, and sewage disposal.
and completing CSG wells, construction of field gas
Mainland support and temporary construction
and water gathering networks, gas processing and
facilities are located in the Gladstone area. The LNG
water treatment facilities, electricity infrastructure,
plant is situated on Curtis Island, 11 kilometres
and gas transmission pipeline infrastructure.
northwest of the city of Gladstone, Queensland.
The CSG fields comprise wells and associated
surface facilities, gas gathering and water gathering
pipeline systems, seven gas processing facilities,
two associated water treatment facilities, water
storage ponds, and treated water and brine
disposal facilities.
ConocoPhillips manages the construction and
operation of the LNG facilities on Curtis Island.
Bechtel is the engineering, procurement and
construction contractor for the LNG plant and much
of the related infrastructure.

6 Australia Pacific LNG Environmental and Social Report


2.1 Upstream 2.2 Upstream Production
Construction Operations

Upstream
The Upstream Project was 99 percent CSG production increased steadily
complete as at 31 December 2015. during the reporting period with the
1,272 development wells had been arrival of gas at the LNG plant and first
drilled and 1,090 wells commissioned. LNG production in December. Total
All key facilities are now commissioned production increased from 474 TJ/day
and the Upstream Project is complete in July to over 1,000 TJ/day at the end
with the only activities remaining of December.
relating to contract ‘close out’.
2.2.1 Sustain Phase
2.1.1 Upstream Phase 1 Project December marked a major milestone
The Phase 1 Project is largely complete with commissioning of the first
and the demobilisation organisation horizontal well in Spring Gully. Sustain
concluded through December. Going phase drilling was 25 wells ahead of
forward Phase 1 will be closed target at the end of CY15 and 21 wells
out through a centralised delivery were commissioned in December.
organisation. The contracts closeout
exercise is well underway with 400
of the 700 contracts now closed
and on target to complete in March
2016. Pipelines remediation work is
scheduled to start early in CY16.

2.1.2 Facilities
During December, Australia Pacific
LNG exceeded operated asset target
production and is now producing at
a rate which, combined with volumes
provided from non-operated assets, is
more than sufficient to supply domestic
contracts and feed gas for one
LNG Train.

2.1.3 Pipelines
All Australia Pacific LNG pipeline and
pipeline compression assets are now
commissioned, with 98 percent of all
new pipelines easements registered.
Prior to full LNG Train 1 operation, the
Woleebee and Condabri laterals were
run at higher pressure than the mainline
to supply domestic and LNG markets.

Australia Pacific LNG Environmental and Social Report 7


2.3 Downstream 2.3 Downstream
Construction, Operations
Commissioning and
Start-up

Downstream
The Downstream Project was 96 LNG was first produced from Train 1
percent complete at 31 December on 9 December 2015, and the first
2015. Overall construction and shipment of LNG departed the LNG
commissioning on Curtis Island facility on 9 January 2016. A total of
was 93.1 percent complete. Train three produced cargoes were shipped
1 and outside battery limits (OSBL) to customers in January.
construction was 99.4 percent
complete. Pre-commissioning and
commissioning was 68 percent
complete. Out of the total 225
systems in Train 1 and OSBL, 220
of these systems have reached
Mechanical Completion.
Train 2 construction was 73.1
percent complete. Train 2 electrical
and instrumentation works were
constrained by resources but ramped
up slowly during December.

Curtis Island
Australia site LNG
Pacific – December
liquefied 2013 gas facility on Curtis Island commenced commercial operation in December 2015.
natural

8 Australia Pacific LNG Environmental and Social Report


First shipment to customer and shareholder Sinopec on the Pavilion Vanda.

First LNG Cargo Milestone Achieved


Australia Pacific LNG continues to make strong
progress in the transition from the construction
phase to sustainable ‘steady-state’ operations.
On Curtis Island, final commissioning of Train 1 was December, combined production from all new and existing
completed and production of LNG commenced in Australia Pacific LNG gas wells exceeded 1,000 Terajoules
December 2015, with progressive cool-down of LNG per day (T/day).
pipework and storage facilities successfully completed
As a result Australia Pacific LNG is able to meet all
prior to loading the first LNG cargo for export.
customer obligations, including export cargoes from
The LNG tanker Methane Spirit was loaded with LNG and Train 1 on Curtis Island and domestic customers.
departed the LNG Facility on Saturday 9 January. By early
Upstream operator Origin is now focused on sustain
February Australia Pacific LNG had successfully produced
operations with progress on sustain wells proceeding
and loaded four more export cargoes, including the
to plan.
Sinopec LNG tanker MW Pavilion Vanda (above).
Origin has also established a new Condabri distribution
ConocoPhillips’ works on Curtis Island now focus on
facility. This holds the bulk of the capital spares required
completion of tasks associated with preparations for the
to support the gas field and pipeline operations and
start of Train 2. Successful completion of works on Train 1
maintenance activities and the development inventory to
has allowed re-deployment of additional resources and
deliver our well campaigns and gathering networks into
support towards train two completion activities.
the future.
Upstream gas field facilities associated with Phase One
The Condabri facility has 6,000 m2 under roof storage and
activities are complete, with all seven new Gas Processing
120,000 m2 in associated laydown yards centrally located
Facilities (GPF) online.
in the Surat Basin to support inventory requirements for
The 977th and final Phase 1 well, COM462, was Australia Pacific LNG gas field and pipeline operations.
successfully commissioned at Combabula in November,
In addition, the Brisbane Central Control Room
and commissioning of the Compression Facility and
demonstrated remote facility management capability with
Interconnect was completed.
a successful remote restart of the Reedy Creek Water
As at 31 December 2015, 1,272 development wells Treatment Facility.
had been drilled and 1,090 wells commissioned. In late

Australia Pacific LNG Environmental and Social Report 9


3. Safety, Health,
Environment and
Social Management
Australia Pacific LNG recognises that environmental
management, workplace health and safety and
community engagement are integral to the success
of the Business, and integrates these priorities into
day-to-day operations.
3.1 Approach
The Australia Pacific LNG Environmental and Social
Management Plan (ESMP) articulates the Business’
approach to the management of environmental and
social issues. The ESMP is supported by the Health,
Safety, Environment and Sustainable Development
(HSE and SD) Management System (MS) Standard
and topic-related sub-plans.

KEY STAKEHOLDERS

Lenders Shareholders Regulators Public/Community NGOs Workforce

APLNG HSE and SD Management System Standard

HSE AND SD
MS STANDARD
APLNG Environment and Social Management Plan (ESMP) ELEMENTS
Policy
STANDARDS AND ESMP SUB-PLANS HSE Obligations
GUIDELINES
Planning, Objectives and Targets
Parent Company Labour and Working Pollution Prevention
Policies and Systems Conditions and Abatement Hazard and Risk Management

Regulatory Requirements Community Health Land Acquisition and Training and Competency
Safety and Security Involuntary Resettlement Communication
IFC Environmental and
Social Standards Biodiversity Sustainable Resource HSE Programs and Procedures
Conservation Management
Contractor and Supplier
Equator Principles and
Indigenous Peoples Cultural Heritage Management
US Ex-Im Policies
Emergency Preparedness
and Response
Incident Management, Corrective
and Preventative Action
Actions
Monitoring and Measurement
Operator Management Plans Assurance
Contractor Management Plans Management Review

Figure 3.1 Australia Pacific LNG Environmental and Social Management Plan

Australia Pacific LNG Environmental and Social Report 11


3.2 Federal and State
Impact Assessment
Approvals

3.1.1 Policies, Conditions compliance continues to


be met under the guidance of the
The State of Queensland and the
Australian Federal Government
Principles and SIMP. However SIMPs are no longer a subjected Australia Pacific LNG
Systems requirement of Coordinated Projects in to a full environmental and social
Queensland, and have been replaced assessment process. This resulted in a
Australia Pacific LNG’s commitment to by a new policy framework – The Social comprehensive set of conditions related
managing its activities for the protection Impact Assessment (SIA) Guideline. to environmental and social issues in
of the health and safety of people, November 2010.
the environment, and the community Australia Pacific LNG submitted a
is formalised and communicated in Change Request to move from the The Environmental Impact Statement
its Health, Safety, Environment and SIMP framework to the SIA guideline (EIS) executive summary provides
Sustainable Development Policy. under transitional arrangements offered an overview of the Project impact
by the Coordinator General (CG). assessment process and stakeholder
The sustainable development aspects The new policy continues to confer consultation for non-technical readers.
of the policy are achieved by integrating responsibility on proponents to mitigate
Australia Pacific LNG’s Sustainability Approximately 1,600 conditions were
impacts and also to report on social
Principles when planning activities. imposed on the sanction of the Project
impact management (SIM reporting)
The Upstream and Downstream under State and Commonwealth laws,
until 2017 – two years into operations.
Operators have integrated these in addition to a large number of voluntary
The Change Request was approved by
Sustainability Principles into their commitments made by the Project in the
the CG on 29 September 2015.
management systems and activities EIS process.
during the Project’s construction and In anticipation of the changing
operation phases. nature of social impacts during the
operational phase, the Upstream
3.1.2 Compliance Operator undertook an internal Social
Register Impact Assessment (SIA) in 2014.
Commencing 2016, the Upstream
Australia Pacific LNG and the Upstream Operator will seek to address impacts
and Downstream Operators utilise identified in this internal SIA, as well
a common data register to record as community related risks and
reporting of compliance with the compliance obligations through annual
Environmental Impact Statement (EIS) community plans.
commitments and approval conditions.
A working group, comprising staff from
3.1.4 Incident
Australia Pacific LNG and Upstream Notification and
and Downstream Operators, monitors Reporting
updates to the compliance register,
meeting monthly to review its status Incident notification and reporting
and issues arising from its usage. are handled as part of the respective
incident management processes
3.1.3 Environmental managed for Australia Pacific LNG
by Operators. Incidents are reported
and Social according to the Australia Pacific LNG
Management Plans Incident Notification Procedure.
The Upstream and Downstream Australia Pacific LNG’s Health, Safety
Operators have developed and and Environment (HSE) team reviews,
implemented environmental analyses and reports incidents as well
management plans (EMPs) and social as HSE and Sustainable Development
impact management plans (SIMPs). performance on a monthly basis
These plans have been designed to to management, shareholders and
mitigate environmental and social lenders. Reporting occurs in the event
impacts during construction and of significant incidents or breaches of
operation, and reflect conditions conditions or regulations.
imposed throughout the approvals Major incidents are subject to
process. These plans define immediate notification to shareholders
contractors’ and subcontractors’ and the Independent Environment and
requirements, and are tailored to Social Consultant as per the schedule
specific scopes of work. specified in Section 10.8.3 of the ESMP.

12 Australia Pacific LNG Environmental and Social Report


3.3 Management
of Change

Australia Pacific LNG and their


operators, contractors, and
subcontractors are required to apply
appropriate change management
procedures for all changes or
deviations to agreed Business scope Upstream Downstream
and objectives. The overall scope and
objectives are governed by cost and Two Project Change Notices (PCNs) No significant change related
schedule baselines and design and related to environmental and social to environmental and social
philosophy documents. issues were approved and are aspects occurred.
being implemented.
The Australia Pacific LNG Project
Change Management Procedure 1. Commencement of an accelerated
defines how changes to the Business development program in Combabula,
outside of Operator delegations are specifically the development
managed across the Upstream and activities on Usher Pastoral and the
Downstream projects on behalf of Dinoun State Forest. Planning with
Australia Pacific LNG. This includes Council has commenced to manage
changes to the technical design, expected additional traffic and
compliance or license application transport impacts.
requirements not envisaged in the
2. Environmental Authority amendments
initial Business scope, and compliance
at Spring Gully and the Walloons
with required environmental and
have been authorised to facilitate
social standards committed under the
landspraying whilst drilling.
Syndicated Facility Agreement with
the lenders.

Australia Pacific LNG Environmental and Social Report 13


3.4 Verification and Assurance

The Australia Pacific LNG HSE & During this reporting period,
Australia Pacific LNG initiated an
3.4.1
SD Assurance Plan describes the
activities that the Australia Pacific audit of implementation of corrective Independent
LNG Corporate Office undertakes actions by the Upstream and Environmental and
to fulfil its assurance, oversight, and Downstream Operators.
Social Consultant
communication roles. This is done on
behalf of Shareholders for Operator
The Upstream and Downstream Review
Operators have developed and
activities and performance in the areas implemented HSE assurance plans, The Independent Environmental and
associated with HSE & SD. These procedures and programs to verify Social Consultant (IESC), Lummus
include targeted Operator Health, that controls are developed to mitigate Consultants International, conducted
Safety and Environmental Management health, safety, environmental and a review of various components of
Systems (HSEMS) implementation and social impacts. Assurance activities the Business in September 2015. The
compliance audits, pre-construction are planned in consideration of reviewing team travelled to the LNG
and operational readiness reviews, construction and operational activities Facility construction site on Curtis
environmental and social condition with the greatest HSE and SD risk Island, and inspected key aspects of
compliance audits, and data along with other factors including construction of the two LNG trains,
verification of the compliance system outcomes of previous audits, results of the LNG tanks, and the administration
(Atlas). Australia Pacific LNG leverages incident investigation and independent and plant control buildings. With
the Operator’s own assurance activities third-party audits and regulator- respect to the Upstream Operator,
as much as possible through: initiated audits. the review included an inspection of
• participating in an observer capacity reinstatement of one of the Campsites
in identified Operator HSE and SD (Camp 4) and the Narrows section of
audits, workshops and reviews the pipeline corridor to verify the state of
reinstatement and close out that item.
• performing a quality assurance Lummus Consultants noted, “As always,
review of identified Operator-initiated the dedication and professionalism is
HSE and SD audits, workshops clear and for environmental and social
and reviews. aspects the teams continue to deliver
All Australia Pacific LNG-initiated best practice with performance excellent
HSE and SD audits are undertaken across the Project”.
using a methodology consistent Overall, Lummus Consultants confirmed
with the requirements of ISO that principal environmental approvals
19011:2003 Guidelines for Quality and planning permits remain valid,
and/or Environmental Management specific to the Australia Pacific LNG
Systems Auditing. Project, and that conditions of approval
are being appropriately tracked,
implemented and measured.

Lummus Consultant Jeff Bleathman and Australia Pacific LNG staff Michael Stahl, Candice Shelley and Marianne
Gibbons at the Narrows.

14 Australia Pacific LNG Environmental and Social Report


3.4.2 Regulators’ The Upstream Operator HSE
Corrective Actions Audit identified
Audits four audit findings (non-compliances
During the six months from 30 against documented internal
June 2015, seven third party requirements) and two opportunities
environmental audits were completed for improvement. The Downstream
Operator HSE Corrective Actions
Downstream
and submitted to the respective
Regulatory Departments in relation to Audit identified two audit findings The Downstream Operator conducted
the Upstream Project. These audits (non-compliances against documented a single Level 2 audit during the
did not identify any significant issues, internal requirements) and three reporting period; an audit of the
with most findings raised against opportunities for improvement. Principal Contractor’s implementation
administrative and retrospective issues. of the Construction Environmental
These audits covered the following Management Plan.
Environmental Approvals, Coordinator
Nineteen non-conformances were
General Conditions and Material
identified, all risk ranked as medium
Change of Use:
or low. All non-conformances were
• Environmental Protection and administrative in nature and did not
Biodiversity Conservation Act Upstream result in environmental harm. As at
the end of the reporting period, the
• Coordinator General Conditions During the six months from 1 July majority of corrective actions had
• Condabri Facility 2015, Origin initiated two shareholder been completed.
audits on the Upstream Operator
• Mainline (Export) Pipeline covering the Cost Reduction Program
• Narrows Crossing Pipeline and Anti-Bribery and Corruption.
These audits did not identify any
• Gladstone Infrastructure Corridor issues relating to environmental,
State Development Areas, Material health and safety and social
Change of Use (Coordinator responsibility processes.
General Condition)
Level 3 audits: The Origin Internal
• Callide Infrastructure Corridor Audit group initiated three audits
State Development Areas, Material during the second half of CY 2015.
Change of Use (Coordinator These audits covered Drilling and
General Condition). Completions, Operational Technology
There were no third party or regulator and Field Delivery. The results of these
audits relating to the Downstream audits are still being finalised.
Project during the reporting period. Level 2 audits: For the six months
ending 30 December 2015 the
Upstream Operator conducted
3.4.3 Operator and eight reviews and internal control
Shareholder Audits assessments requested by selected
Business Units. These audits did
Two Level 3 Australia Pacific LNG not identify any issues relating to
Corporate Office HSE audits were environmental, health and safety and
completed in December 2015 to review social responsibility processes.
the implementation and compliance
with both Operators’ processes Level 1 audits: Level 1 Assurance
and procedures pertaining to the activities continue with oversight from
development, approval, tracking to Business Unit Assurance functions.
completion, and monitoring and review These include, but are not limited
of corrective and preventative actions. to, a range of activities including
The scope of the audit included structured audits, inspections and
Level 2 and Level 3, including third monitoring programs.
party audits and reviews, significant
incidents, regulatory reportable
environmental incidents, and regulatory
non-compliances for the period of the
calendar years 2014 and 2015.

Australia Pacific LNG Environmental and Social Report 15


3.5 Conformance 3.6 Environment and
Social Milestones

3.5.1
Non-Conformances Upstream
Protection of the environment The Upstream Operator received no
Environmental and social milestones
continues to be a priority for Australia warning notices or fines. No Penalty
are part of the Project Execution
Pacific LNG, which has a corporate Infringement Notices (PINs) or fines
Plans for development and operation
goal of maintaining zero regulatory were imposed between 1 July and
of the Upstream and Downstream
shutdowns and finable incidents. 31 December 2015. The Upstream
components. All environmental and
Operator had two instances of non-
social milestones related to the
A non-conformance is a situation compliance with waste disposal
Project as outlined in the ESMP have
inconsistent with conditions of certificates. A further 16 instances
been completed.
approval or formal commitments of non-conformance related to late
made by Australia Pacific LNG. Non- submissions of reports, updates
conformances are recorded during to management plans or failure to
audits or inspections conducted by conduct monitoring in accordance with
Regulators, Shareholders, Australia the Environmental Authority (EA), were
Pacific LNG, Operators or Contractors. reported and all have been closed out.

Downstream
The Downstream Operator received no
warning notices from EHP.

16 Australia Pacific LNG Environmental and Social Report


4. Labour
and Working
Conditions
Attracting and retaining a qualified workforce
is crucial to the success of Australia Pacific LNG.
Achieving a safe and healthy workplace is a priority.

At 31 December, the Business 25


Consolida
engaged 5,793 full-time equivalent
(FTE) employees and contractors, 20
representing an approximate 46 percent
decrease on the previous reporting
15
period. This reflects the current state of
Million hours

construction, with the demobilisation


of a number of the completed 10
components of the Project.
5
The Upstream Operator engaged
2,766 FTEs, comprised of 762 FTEs
in operations, 1,926 FTEs working 0
specifically on the Upstream Project S1 S2 S1 S2 S1 S2 S1 S2
2012 2012 2013 2013 2014 2014 2015 2015
development and 78 FTEs in Phase
1 Project delivery. The Upstream Figure 4.1 Total Australia Pacific LNG Consolidated Exposure Hours by
workforce was down 47 percent from Reporting Period
the previous reporting period and
includes 661 FTE direct employees and
2,105 FTE contractors.
The Downstream Operator engaged
2,987 FTEs including 329 employees
and 2,658 contractors, the majority
working for Bechtel.
The Australia Pacific LNG Corporate
Office engaged 40 FTEs, primarily
shareholder secondees.
Exposure hours decreased from
13,096,770 hours in the previous period
to 9,728,085 hours. The decrease
in exposure hours of approximately
26 percent reflects current Business
activity with a number of key
construction components having been
completed (Figure 4.1).

18 Australia Pacific LNG Environmental and Social Report


4.1 Hazard Management
Downstream and Upstream Operators manage hazards through
a positive behaviour-based safety management strategy.

Upstream Downstream
Individual tasks are managed through Environmental risks have been Safety management tools such
the use of procedures, Job Hazard identified through a series of as Safety Task Analysis and Risk
Analysis and/or Permit to Work. workshops that align with the LNG Risk Reduction Talk (STARRT) cards,
Management Framework. Job Hazard Analysis (JHA), Job
Regular monthly reporting records Safety Analysis (JSA), Job Safety
hazard management activities across Level 1 Environmental Risk Registers and Environmental Analysis (JSEA),
the Upstream Operator sites and exist for the Upstream Operator at a manager walk-throughs, and tool
facilities, listed in Table 4.1. Business Unit level. box talks are used on the LNG facility
construction site to build a strong
safety culture and positive work habits.
Hazard management type Totals Additionally, leading and lagging
safety indicators are tracked and
Manager site visits 823 used to promote an ongoing
Injuries (no treatment cases and higher) 104 safety focus, and celebrated when
milestones are achieved. Table 4.2
Near Misses 151
lists activities conducted by Bechtel
Life Saving Rule breaches 29 and its subcontractors to help improve
awareness and manage hazards
Emergency Response Drills 947
during the reporting period.
Safety Inspections 10,719
Drug and alcohol tests conducted 99,756
Training conducted 1,214

Table 4.1 Upstream Hazard Management*


* Not all hazard management activities conducted were recorded. Table 4.1 represents recorded hazard
management activities.

Hazard Management Type Total

Tool Box meetings 1,814


JSAs/JHAs/JSEAs 5,227
Safety Inspections 10,543
Emergency Response Drills 115
Orientations 413
Manager site visits/walk throughs 2,575
Personal Tasks hazard ID or STARRTs 7,434

Table 4.2 Downstream Hazard Management

Australia Pacific LNG Environmental and Social Report 19


4.2 Safety Performance

Australia Pacific LNG’s safety achieved a 9 percent reduction over


performance continued to improve in the past six months. The Downstream
this reporting period. The key safety Operator has led our improvement with
indicator—the rolling 12-month Total a 32 percent reduction.
Recordable Injury Frequency Rate During this period, Australia Pacific
(TRIFR)—continued to improve in the LNG incurred 24 recordable injuries,
second half of 2015, standing at 2.5 compared to 33 injuries recorded in
at the end of December. This measure the previous period, representing a
shows approximately 19 percent solid downward trend in the 12-month
improvement over the previous six rolling recordable injury rate (refer to
months. The Upstream Operator has Figure 4.2).
TRIFR (No. of injuries per million hours worked)

9
Consolidated APLNG
8
7 Downstream Operator
6 Upstream Operator
5
4
3
2
1
0
TRIFR (No. of injuries per million hours worked)

9
S1 S2 S1 S2 S1 S2 S1 S2 Consolidated APLNG
8 2012 2012 2013 2013 2014 2014 2015 2015
7 Consolidated APLNG Downstream Operator
6 Consolidated APLNG Downstream Operator Upstream Operator
5
Downstream Operator Upstream Operator
4 Figure 4.2: Australia Pacific LNG Consolidated Safety Performance by Reporting Period
3 Upstream Operator

2
1
0
S1 S2 S1 S2 S1 S2 S1 S2
2012 2012 2013 2013 2014 2014 2015 2015
S2 S1 S2 S1 S2
2013 2014 2014 2015 2015
S2
2015

20 Australia Pacific LNG Environmental and Social Report


100 7
The 24 recordable injury cases 100 7 Injury Category
Injury Category
involved four lost time cases (LTC), four 90
90 6
restricted work cases (RWC), and 16 80
6 Fatality
80 Fatality
medical treatment cases (MTC). For
70 5
the same period there were 280 first 70 5 LTC
LTC
aid cases (FAC). Refer to Figures 4.3 60

Injuries
60 4

Injuries
and 4.4. 4 RWC
50 RWC
50

Recordable
Hands continue to be the most 3

Recordable
40 3 MTC
commonly injured body part (50 40 MTC
percent of all injuries). However, the 30 2
30 2 TRIFR (rolling 12 m
percentage of hand injuries reduced 7 20 TRIFR (rolling 12 mo
through the first half of 2015 (by Injury
20 Category
1
7 10 1
approximately 33 percent), but rose 6 Injury
10 Category
again in the second half of the year. 6 0 Fatality 0
100 0 7 0
Both Operators have taken measures Fatality
S1
S1
S2
Injury S1
S2 Category
S1
S2
S2
S1
S1
S2
S2
S1
S1
S2
S2
5 2012 2012 2013 2013 2014 2014 2015 2015
90 over the past year to address 2012
LTC 2012 2013 2013 2014 2014 2015 2015
100 hand injuries and protecting hands 5 6
LTC 7
80 Fatality Injury Category
Figure 4.3 Recordable Injuries by Reporting Period
90 continues to be a daily topic at pre- 4
70 100
start meetings. 4
7 5RWC 6 7
RWC LTC Fatality Injury Category
80 Injury Category
60 90 3
3 4MTC 5 6
70 6 MTC RWC LTC Fatality
50 80 Fatality
60 22
Recordable Injuries

70 3 4 months) 5
40 5 TRIFR (rolling 12
TRIFR LTC
LTC (rolling 12 months)
MTC RWC
50
30 60 11
Recordable Injuries

4 2 3 4
40 RWC TRIFR (rolling 12 months)
MTC RWC
20 50
30 003 1 2 3
10 40
S2 S1 S1 S2 S2 S1 S1 S2S2 S1
S1 S2
S2 MTC TRIFR (rolling 12MTC
months)
20
2012201320132013
2013 2014
201430 2014
2014 2015
2015 2015
2015
0 0 0 1 Fatalities2
2
10 TRIFR (rolling 12 months) TRIFR (rolling 12 months)
S1 S2 S1 20 S2 S1 S2 S1 S2
2012 2012 2013 2013 2014 2014 2015 2015 4
0 1 0 1
LTC Injuries
10
S1 S2 S1 S2 S1 S2 S1 S2
2012 2012
0 2013 2013 2014 2014 2015 20154 0 Injuries
0 RWC
S2 S1 S2 S1 S1
S2 S2
S1 S1
S2 S2 S1 S2 S1 S2
2012 2013 2013 2014 2012
2014 2012
2015 2013
2015 2013 2014 2014 2015
16 2015
MTC Injuries

280
FAC Injuries

Figure 4.4 Safety Performance Pyramid - Jul to Dec 2015

Australia Pacific LNG Environmental and Social Report 21


High Potential
Incidents Upstream Downstream
There were three High Potential The Upstream Operator’s TRIFR Seven recordable safety incidents
Incidents (HPIs) during the reporting improved by approximately 8.5 percent occurred at the Curtis Island
period. The Upstream Operator from 3.5 in the previous reporting construction site.
recorded one HPI involving a pressure period to 3.2.
The TRIFR for the Downstream
build up in the well, causing an eight Over the reporting period, a number Operator fluctuated slightly each
metre section of polished rod to eject of sub-projects completed their month, and stood at 1.7 at the end
from the well, landing immediately construction phases and demobilised of December (compared to 2.5 in the
beside the wellhead. It resulted in no from site, resulting in a large decrease previous reporting period).
harm to work crew members. of hours worked (4.46 million hours
The Downstream Operator recorded worked in the reporting period
two HPIs, involving a boom striking compared to 7.31 million hours worked
the safety cage on a permanent in the previous reporting period).
ladder and a crane making contact There was continued focus on
with scaffolding. contractor management, including
The recurrence of HPIs are prevented the management of HSE-related
by post-incident measures including demobilisation risk and simplification
better communication of safety alerts of safety management plans to
throughout Australia Pacific LNG, new ensure consistent standards across
or enhanced training programs, as well the business.
as amended procedures. Preventative
measures include active engagement
of site leadership with craft,
implementation of Life Saving Rules,
robust Operator Tier 2 audit programs
and lessons learnt (and shared) from
other Operators.

22 Australia Pacific LNG Environmental and Social Report


4.3 Shift Work and FIFO Regimes

Australia Pacific LNG requires a large and diverse


workforce. The routine operations include sites
requiring extended work hours, including those
operating at 24-hours a day, seven days a week.

The ‘hours of work’ and ‘rest breaks’ of


Australia Pacific LNG and its Operator
and contractor personnel are governed
by a number of directives, procedures
and agreements.
Australia Pacific LNG recognises Upstream Downstream
fatigue as an occupational health and
safety risk affecting health, increasing Upstream operations and drilling and Downstream construction employees
workplace injury risk, and reducing completions predominantly work a and contractors currently work a 58–
performance and productivity. It 14-days on and 14-days off eventime hour week, comprising five 10-hour
impacts on workplace safety and roster. Across construction activities for shifts Monday through Friday and an
operational capabilities. the Upstream Project, the predominant additional eight-hour shift on Saturday.
roster is 21-days on and seven-days FIFO workers operate on shifts
off. People working under these shift consisting of 28-days on and seven-
roster arrangements generally work a days off, working six days per week.
12-hour period followed by a 12-hour The FIFO regime covers 71 percent
rest period. Across the Upstream (2,011 workers) of the construction
Project, site-based rostered employees workforce. The percentage has
are offered a charter flight between increased over this reporting period
Brisbane and Roma or Miles at the due to the peak construction phase.
start of their FIFO work cycle. The
employees are transported via bus or
pool vehicle to site accommodation.
At the end of December, approximately
40 percent of the workforce (1,102
workers), including employees and
contractors, were working under the
FIFO/DIDO regime.

Australia Pacific LNG Environmental and Social Report 23


4.4 Diversity

The majority of the workforce are


Australian permanent residents. There
4.4.1 Indigenous
are 177 expatriates (122 Downstream Employment
and 55 Upstream) working in Australia.
At 31 December 2015 124 positions in
The Upstream Operator employs 523 the Business were filled by Indigenous
women and the Downstream Operator people in roles such as managers,
employs 255 women. cultural heritage monitors (part time
casuals), clerical/administrative, and
For the Downstream Operator,
machine operators.
approximately 33 percent (987
workers) come from the Gladstone Figure 4.5 shows the number of
area. The Upstream Operator sources Indigenous people employed to date.
approximately 170 workers from local
areas, however, the majority of its
workers are from Queensland.

300
Downstream

250
Upstream
No. of Indigenous Employees

200

150

100

50

0
S1 S2 S1 S2 S1 S2 S1 S2
2012 2012 2013 2013 2014 2014 2015 2015

Figure 4.5: Indigenous Employment

Downstream Upstream

24 Australia Pacific LNG Environmental and Social Report


4.5 Training

Training, awareness and competency requirements


for Health, Safety and Environment are set out in the
Australia Pacific LNG Health, Safety and Environment and
Sustainable Development Plan.
These requirements include • Leading HSE Induction (Instructor external delivery of courses, with the
environmental and social aspects, and led): 1,008 most frequent training being Leading
are designed to meet: HSE Induction and the Integrated Safe
• LNG Integrated Safe System of Work
Systems of Work suite of courses.
• Relevant Queensland and Australian (ISSoW) - Work Party: 343
Government requirements Binda-Nalkana also has a Practical
• ISSoW Systems Level 2 Permit
Learning Space which is a 2,500 m2
• Environmental Impact Statement Holder: 315
hands-on learning area with tools,
(EIS) commitments
• Code of Conduct (online): 650 machinery and equipment. Currently
• International Finance Corporation Flange Management and Multiskilling
The Drilling and Completions General
performance standards (Social and training are scheduled weekly and
Induction— an industry-based initiative
Environmental Assessment and Authorised Isolator and Gas Test
in Queensland — was launched in
Management Systems). Atmosphere as required.
February 2015, reducing induction
training time. The process is managed Multiskilling of the operational workforce
by Energy Skills Queensland and to has included several elements:
date 3,775 people from 147 companies
• Skilling operators to perform:
have completed this induction. 154
of those people are Origin Drilling and -- minor/routine maintenance tasks
Completions employees.
Upstream A ‘Foundation Program’ incorporates
-- plant and field, chemical and
water sampling tasks.
the former Field Readiness Program
In September 2015, Origin People and • Skilling maintainers to:
that is designed for new starters to
Culture introduced a new cloud-based
work safely. It comprises statutory -- shutdown and depressurise
Human Capital Management system,
training, Origin IT systems and equipment, and implement
called Success Factors. This is an
corporate inductions and is currently isolations following approved
independent SAP business software
under review. Participation rates at this procedures
that manages learning, core HR
time are low due to the low number of
functions, recruiting, onboarding and -- perform minor/routine
new starters.
performance management. operational tasks.
Through commitments to Origin’s
Induction training remains the key Skills development has been achieved
Reconciliation Action Plan (RAP), an
requirement for all new employees and by creating customised knowledge
Indigenous Cultural Capability Pathways
contractors. All field-based employees training sessions coupled with realistic
program was developed which
and contractors are required to practical activities and assessment
produced a publication ‘Deadly Careers
complete an online Field Induction conducted by Capability Delivery
- Origin Supported Industry Pathways’.
with information common to all sites Specialists. Over 200 Operator/
This initiative supports Aboriginal and
and site specific inductions. 6,615 Maintainers have completed
Torres Strait Islander peoples to gain
Site Inductions have been completed multiskilling training.
education and skills training that will
with some personnel and contractors
transition to employment and add
completing inductions for multiple
value to the communities in which
sites. Other courses registering a high
we operate.
number of completions include:
The Regional Learning Centre (Binda-
• HSE General Awareness Induction
Nalkana) located at Condabri Central, is
(online): 3,617
continually being used to deliver training
• HSE Field Induction (online): 2,038 to site employees and contractors
without having to travel to Brisbane.
• Drilling and Completions Field
The facility is used for both internal and
Induction (online): 1,221

Australia Pacific LNG Environmental and Social Report 25


Downstream
The last six months of 2015 have seen HSE Management System modules,
operational personnel completing Safety Case awareness, Management
competence to operate training, of Change overview, Risk Management
commissioning activities and further overview, and HSE Culture sessions 1
training in preparation for plant and 2. The Competency Management
operations. Marine mooring training has System now has over 10,000 records
been a highlight and included theoretical of completed training. Contractors are
training and most recently practical now starting to carry out work and many
training with the Australian Maritime contractors are registered in ISNetworld
College. There has been vendor and completing required training to meet
training provided to both operations ConocoPhillips’ standards.
and maintenance personnel with a
A key sustainable training initiative
significant volume of training provided
started this year is the development of
for GE plant and equipment. There
the LNG Process Operator Traineeship
has also been a focus on electrical
Program; a collaboration between
training, verification of competence
Australia Pacific LNG, QGC and GLNG
program (high risk equipment), medic
to establish an operator traineeship
assist training, helicopter landing officer
program. Trainees are employed by a
training and permit to work. Refresher
third party organisation and are trained
training has now started and in 2015 all
to national LNG training standards in a
operational crews have completed fire
Gladstone facility. This is a key strategy
team refresher training.
to recruit, train and employ locals for
Mandatory training modules have been the LNG Industry in Gladstone, with the
completed for Downstream operations first group of 18 trainees to start this
personnel. These modules consist of program on 1 February 2016.

26 Australia Pacific LNG Environmental and Social Report


4.6 Wellbeing and Accommodation
The importance of maintaining and improving employee and
contractor health and wellness is recognised by Australia Pacific
LNG. Office-based health and wellness programs consist of
educational topics, work station ergonomics, exercise / fitness
programs, and wellness campaigns.

The majority of field-based workers live


in Temporary Accommodation Facilities
(TAFs) near worksites. These may be
camps, hotel, motel accommodation
and provided housing. In addition to
providing housing and food, TAFs
provide access to gym equipment
Upstream Downstream
including weights and cardiovascular The number of workers living in
The number of workers directly
equipment. TAFs also include sporting the Curtis Island TAF at the end of
employed by the Upstream Operator,
facilities, and TAF staff support December decreased substantially
including workers hired by major
employees and contractors with gym to approximately 1,410, although
contractors living in camps at the end
routines and exercise programs. this fluctuated depending on the
of the reporting period was 1,102.
Healthy food choices are an important shift rotation.
The Upstream Operator delivers
aspect to maintaining a fit workforce.
practical and educational programs
Healthy and ‘heart smart’ eating
designed to encourage people to
options are available.
make informed decisions about
Several locations include a fully staffed health and safety, and to prevent or
medical clinic. The primary purpose minimise illness and injuries. Programs
of the clinics is to attend to worksite- encourage physical activity, nutrition
incurred injuries however the clinics and other healthy habits.
have the ability to manage non work-
Upstream Operator wellness initiatives
related medical conditions as well.
included:
Personal health and wellbeing on the
jobsite is supported at every location. • July to December – TouchBase
The availability of medical facilities on- – Rostered Workforce support
site ensures many workers do not have program
to leave the jobsite to seek medical
attention. The Upstream Operator • July to December – STRONG
recorded 2,209 visits to on-site medical Program – body, mind and spirit
clinics, with 91 percent (2,014) of all program aimed at whole-of-body
visits being non work-related. The health for workers
Downstream Operator recorded 4,437 • July to August –
visits to the Curtis Island medical clinic Fatigue Management
with approximately 95 percent of
admissions being non work-related. • September to December –
Heat Stress
HSE and medical staff support the
Operators’ Health and Wellness • Flu shots were provided from July
Programs by delivering a series 2015 to 26 personnel, including
of wellness topics or programs to employees and contractors.
employees and contractors. This
is done by providing educational
materials, access to medical providers,
access to exercise equipment and
healthy food options, all of which
support high employee morale at the
remote work locations.

Australia Pacific LNG Environmental and Social Report 27


Occupational Health Nurse, Jill Brown is one of the nurses based at the medical centre.

Permanent Medical Centre Now


Open at the Australia Pacific
LNG Facility
In preparation for steady-state-operations the permanent
medical centre is now operational at the Australia Pacific
LNG facility on Curtis Island. Managed by the downstream
operator, ConocoPhillips, the centre will service all employees
and allied contractors working at the facility.
ConocoPhillips Occupational Health Coordinator, Dennis “The shift nurse will provide assistance in areas such as
Murphy, said the facility would be staffed daily by a shift health and wellness, injury management, return to work
nurse and provide employees with assistance with health and stay at work programs and personal protective
related concerns and issues. equipment fittings,” he said.
“The centre has been developed to manage the broader “With the centre now operational it will be able to support
occupational health needs of our Curtis Island employees the ongoing work we are undertaking to integrate health
and medical surveillance requirements of the operational and wellness into the business.”
team,” Mr Murphy said.

28 Australia Pacific LNG Environmental and Social Report


4.7 Transition 4.8 Key Performance
to Operations Indicators

Safety Performance Number of women:


Upstream 523
TRIFR:
Downstream 255
Consolidated 2.5
Upstream Upstream 3.2 Number of Indigenous
employees / contractors
Downstream 1.7
The Upstream operations workforce engaged by the Project:
is complete, comprising of 762 FTEs.
Specific training programs were Number of High Upstream 64^
implemented to skill newly hired Potential Incidents:
operators including the Foundation Downstream 60
Upstream 1
Program, multiskilling operators to
perform minor maintenance tasks, and Downstream 2
Community Participation
skilling maintainers to perform minor
operational tasks. Number of local residents
Diversity participating in skills
development programs
Number of Australia Pacific offered by Australia
LNG and contractor workforce Pacific LNG:
sourced from the local area:
Upstream 0
Upstream 170
Downstream 2,113*
Downstream Downstream 987#
Number of apprenticeships:
In the last half of 2015, the HSE Number of workers in
Transition Plan was finalised and FIFO/DIDO regime: Upstream 9
communicated to introduce the Upstream 1,102 Downstream 0
workforce to the transition from the
Project HSE Management System Downstream 2,011 Number of scholarships
(HSEMS) to the Operations HSEMS. The given by the Australia
Number of expatriates
transition will predominantly occur after Pacific LNG Project:
the Performance Test, scheduled for
(457 visas):
Upstream 59**
the first half of 2016. A plan to support Upstream 55
the implementation of the HSEMS Downstream 0
through 2016 was developed. As part Downstream 122
of the implementation plan, Operations
HSE training has commenced on a # For the Downstream Operator this includes all workers sourced from the Gladstone region
number of HSE programs such as
^ 64 directly sponsored by the Upstream Operator equal to 13 FTE in roles of Managers, Cultural
Job Safety Analysis and Personal Heritage Monitors (part time casuals), Clerical Administrative and Machine Operators)
Safety Involvement (behaviour-based
* EQIP-224, QMEA-1889 for details please refer to Table 8.2 - Downstream Project Community Programs
safety program).
**Currently 59 participants from the original 157 scholarships granted since 2007

Australia Pacific LNG Environmental and Social Report 29


5. Pollution
Prevention and
Abatement
Australia Pacific LNG’s Sustainability
Framework describes the approach to
sustainable development, and specifically
refers to principles designed to minimise
environmental impact and prevent pollution.
. combination with relevant laws and regulations, Australia Pacific LNG sustainability
In
principles have guided the development of the sub-plan for prevention and abatement
of pollution. Mitigation measures are based on the nature of the existing environmental
conditions, and sensitive environmental and human receptors.

30 Australia Pacific LNG Environmental and Social Report


5.1 Air Emissions

Air emissions associated with


CSG operations are combustion
5.1.1 Greenhouse gas commissioning and operations, there
is a higher amount of offsite emissions
gases (oxides of nitrogen, carbon emissions generated at the power plant (Scope 2
monoxides, carbon dioxides and The majority of greenhouse gas (GHG) Emissions)** from increased electricity
trace hydrocarbons) and minor emissions from the CSG gas industry used by our operations. These
fugitive methane emissions. During occur at the end-use of the gas emissions have been incorporated in
the construction stage, emissions are where it is burned as fuel. Australia the greenhouse gas emission profile.
also generated by the use of diesel Pacific LNG’s gas processing facilities Overall, compared to S1 2015 there
fuel for electricity generation, and land are designed to significantly reduce was a reduction in greenhouse gas
and marine transport. Dust is also emissions intensity. Consequently, emissions in this reporting period for
considered in this section. only a minor fraction of emissions upstream, which is consistent with the
originate from the gas production and end of commissioning activities and
processing phases. Construction and transition into production, thus resulting
commissioning activities generate GHG in less flaring (Figure 5.1). Downstream
emissions through the use of diesel for emissions increased in S2 2015 as
land and marine transport, local power the LNG Facility progressed through
generators and flaring of gas. These commissioning activities.
emissions are measured as tonnes of
carbon dioxide equivalent (CO2-eq.) Emissions calculations from the LNG
released to the atmosphere. plant operations are being established
using National Greenhouse and
Historically, only direct emissions Energy Reporting Act (2007) compliant
from site (Scope 1 Emissions)* have methodologies, and will continue to be
been reported because it represented reported to the Regulator.
the majority of emissions and was
* Scope 1 emission: For paragraph 10 (1) (a)
the type of emissions that attracted
of the Act, scope 1 emission of greenhouse
direct carbon liability which wasn’t gas, in relation to a facility, means the release of
inherent in the cost of other purchased greenhouse gas into the atmosphere as a direct
energy. With the commencement of result of an activity or series of activities (including
ancillary activities) that constitute the facility.

** Scope 2 emission: For paragraph 10 (1) (aa)


of the Act, scope 2 emission of greenhouse
800,000 gas, in relation to a facility, means the release of
Downstream
greenhouse Operations
gas into the Scope 2 as a direct
atmosphere
700,000 result of one or more activities that generate
electricity, heating, cooling or steam that is
Downstream
consumed by Operations
the facility Scope
but that1do not form part
600,000
of the facility.
Downstream Construction
Tonnes of C02 -eq

500,000 For more details refer to: https://www.comlaw.gov.


au/Details/F2015C00852.
400,000 Upstream Construction

300,000
Upstream Operations Scope 2
200,000
800,000 Upstream Operations Scope 1
Downstream Operations Scope 2
100,000
700,000
0 Downstream Operations Scope 1
600,000
S1 S2 S1 S2 S1 S2 S1 S2
2012 2012 2013 2013 2014 2014 2015 2015
Downstream Operations Scope 2 Downstream Construction
Tonnes of C02 -eq

500,000

Figure 5.1: Australia Pacific LNG Project-Wide GHG Emissions*


400,000 Downstream Operations Scope 1 Upstream Construction

300,000
Downstream Operations Scope 2 Downstream Construction Upstream Operations Scope 2
200,000
Downstream Operations Scope 1 Upstream Construction Upstream Operations Scope 1
100,000

Downstream Construction Upstream Operations Scope 2


*G0
reenhouse gas emissions data is unaudited at the time of publication. Historical data may change from report to report following audit results.
S1 S2 S1 S2 S1 S2 S1 S2
2012
Upstream2012 2013
Construction 2013 2014 2014 2015
Upstream 2015Scope 1
Operations

Upstream Operations Scope 2

S2 S1 S2 S1 S2 S1 S2
012 2013 2013 2014 2014
Upstream 2015Scope
Operations 2015
1 Australia Pacific LNG Environmental and Social Report 31
Upstream Downstream 5.1.2 Fugitive Emissions
The GHG emission profile has made The use of diesel fuel related to plant CSG fugitive emissions come from
an expected but notable shift from construction, power generation, infrastructure, and minor venting of
emissions related to construction and and vehicle and vessel movements methane where it is not practicable
commissioning of facilities, to emissions remained a contributor to greenhouse to flare.
related to an increase in production. gas emissions generated on site.
The operation and maintenance However, with the commencement of
regime of the commissioned plant will commissioning, coal seam gas used for
be continually optimised to minimise power generation and flaring activities
the possibility of any long term also contributed to total emissions
deterioration in the emissions intensity on site.
performance. In the immediate term,
we also expect to see reductions in
flaring as unplanned interruptions are
reduced, as the operations teams
gain experience with the new plant.
Additional opportunities to reduce
emissions and introduce improvements
in energy efficiency will also continue to
be considered.

32 Australia Pacific LNG Environmental and Social Report


5.2 Noise and Vibration

5.1.3 Dust Airborne noise and vibration have the


potential to impact the surrounding
5.2.1 Noise Monitoring
community and environment if not
properly managed.
Noise and vibration may be generated
during construction and operation
of the gas production wells, gas
Upstream pipelines, the LNG plant and associated Upstream
infrastructure. Increased traffic during
A dust deposition monitoring program construction is another source of The Upstream Operator is
is in place across gas field sites. This noise, but mitigation measures have implementing an ongoing gas field-
includes three ambient air quality been adopted. wide noise monitoring program to
monitoring stations continuously
There were four noise complaints within assess the Project’s noise impact and
recording total dust and particulate
the reporting period, of which all have ensure noise levels are in line with the
matter concentrations. There were
been resolved. requirements of the relevant noise
two landholder and community
management guidelines and legislation.
complaints related to dust within the
reporting period, mostly associated In the reporting period, noise
with dust caused by rig movements monitoring focused specifically on
and vehicles on local roads impacting noise emissions from commissioning
nearby properties. All complaints were activities, including flaring, at the Orana
addressed with dust suppression and Combabula GPFs, as well as
activities undertaken to the satisfaction operational activities at the Condabri
of the complainant. Dust suppression GPF. Monitoring was conducted
activities typically involve water tankers to verify noise model predictions
spraying on unsealed roads. and ensure noise emissions were
below the relevant noise limits. Noise
monitoring was also conducted to
assess noise emissions and impacts to
neighbouring landholders from a range
of construction, drilling and pipeline
blow-down activities.

Downstream To manage potential noise impacts,


Australia Pacific LNG implemented
Dust emissions have been minimised specific noise management measures
through implementation of controls such as day time only flaring at the
outlined in the Project Environmental Combabula GPF. In cases where noise
Management Plan. During dry weather, emissions were higher than expected,
dust suppression is conducted by additional controls were implemented
trucks spraying rainwater gathered to ensure potential nuisance impacts to
in collection ponds (if available) or nearby landholders were minimised.
reticulated mains water. However, at
the current construction stage of the
Project dust nuisance is rarely an issue,
as civil works are mostly complete and
major roadways have been paved. No
dust complaints were received during
the reporting period.
Downstream
Noise monitoring for the Downstream
Operator is complaint-based as set out
in the EIS. As part of the EIS process,
baseline noise levels were determined.
While periodic noise monitoring has
been undertaken by subcontractors,
no noise complaints have been logged
since the Project began.

Australia Pacific LNG Environmental and Social Report 33


5.3 Waste Management
The Project developed waste management plans aiming
to eliminate, reduce, reuse, recycle, treat, and dispose of
waste appropriately.

5.3.1 Unregulated
Wastes

Waste categories in tonnes and dis

Upstream Aluminium Cans, Plastic


Bottles and Cardboard -3 General Comingled Waste - L
Total unregulated waste rates have
nearly doubled to 2,283t from Metals and Scrap Metals - R
58
1,133t in the last reporting period. 70 61
This is mainly due to the increase
in construction waste generated by Construction Waste - Landfil
668
an extensive general clean-up for
operational readiness. Paper, Wood and Textiles - R
Figure 5.2 shows the main
waste categories, tonnage and Comingled Waste - Recycle
disposal methods.
1,179 Poly Pipe - Recycle
245

Aluminium Cans, Plastic Bott

Figure 5.2 Upstream Operator Unregulated Wastes and Disposal Methods

Waste
Wastecategories
categoriesinintonnes and
tonnes disposal
and methods
disposal methods
minium Cans,
um Cans, Plastic
Plastic
s and Cardboard -3 General
General
General Comingled
Co-mingled
ComingledWaste
waste →- Landfill
Waste Landfill
- Landfill
nd Cardboard -3
Metals and Scrap Metals - Recycle
61 58 Metals
Metals andand Scrap
Scrap Metals
Metals - Recycle
→ Recycle
70 61 58
70
Construction Waste - Landfill
668 Construction
Construction Waste
Waste
S2 - Landfill
→ Landfill
2015
668
Paper, Wood and Textiles - Recycle
Paper, Wood
Paper, andand
Wood Textiles → Recycle
Textiles - Recycle
Comingled Waste - Recycle
Co-mingled
Comingled waste
Waste→ Recycle
- Recycle
1,179 Poly Pipe - Recycle
245
1,179 Poly
Poly Pipe
Pipe - Recycle
→ Recycle
245
Aluminium Cans, Plastic Bottles and Carboard - Recycle
Aluminium
Aluminium Cans,
Cans, Plastic
Plastic Bottles
Bottles and Carboard
and Cardboard - Recycle
→ Recycle

34 Australia Pacific LNG Environmental and Social Report


Downstream
Waste categories in tonnes and dis
Waste management is an important
component of sustainability on the
LNG Facility construction site. The 222 Metals and Scrap Metals –
site continues to use the Gladstone
Area Water Board (GAWB) pipeline 399
Paper, Wood and Textiles
for wastewater disposal, and has 88
one company handling regulated
and unregulated waste from Curtis Food Waste – Landfill
Island and mainland facilities
during construction.
276 Cardboard - Recycle
Waste generation on the LNG
Facility decreased across the board
as the LNG facility has passed the Construction Waste – Lan
peak construction phase. While 451
the quantities have reduced, the
approximate proportions of waste
remain the same from previous
reporting periods. Domestic waste S22015
Figure 5.3 Downstream Operator Unregulated Wastes and Disposal Methods
continues to be the largest unregulated
waste stream from the Curtis Island
site, with metal and scrap metal Wastecategories
Waste categoriesinin tonnes
tonnes and
and disposal
disposal methods
method
again being significant due to plant
Aluminium Cans, Plastic
construction and welding activities. General Comingled Waste - Landfill
Bottles and Cardboard
222to-3 Metals
Metalsand
andScrap
ScrapMetals
Metals→–Recycle
Recycle
Refer Figure 5.3.
399 Metals and Scrap Metals - Recycle
58 Paper,Wood
Paper, Woodand
andTextiles
Textiles→–Recycle
Recycle
88 70 61
Construction Waste - Landfill
668 Food
FoodWaste
Waste→– Landfill
Landfill
246
Paper, Wood and Textiles - Recycle
Cardboard
Cardboard→-Recycle
Recycle
276
Comingled Waste - Recycle
Construction
ConstructionWaste
Waste→–Landfill
Landfill
451
1,179 Poly Pipe - Recycle
245

Aluminium Cans, Plastic Bottles and Carboard - Recycle


S22015

Australia Pacific LNG Environmental and Social Report 35


5.3.2 Waste Water

Upstream Downstream Upstream


Waste water includes untreated and Australia Pacific LNG has partnered Liquid Regulated Waste
treated sewage considered unsuitable with GAWB and Gladstone Regional
The Liquid Regulated Waste data for
for irrigation. This water was sent for Council to construct two pipelines to
this reporting period includes drilling
offsite processing and reuse. The supply water and dispose of sewage
muds and mud additives. Drilling
volumes of treated and untreated septic from Curtis Island. The Downstream
muds continue to be the principal
waste disposed during the period Operator reported 110,219 Kl of septic
regulated liquid waste components,
were 786 Kl and 2,520 Kl respectively waste for the period.
contributing 88 percent of the total
(refer to Figure 5.4). The treated septic
5.3.3 Regulated
regulated liquid waste. Spent drilling
volumes have remained consistent from muds have historically been processed
the last reporting period.
Wastes (Hazardous to develop compost material for
Interceptor pond water (6,433 Kl) and Materials) reuse. The land spraying (of these
muds) while drilling is an initiative that
completion fluids (852 Kl) were taken
Waste disposal of hazardous materials has demonstrated that spent muds
to onsite water treatment facilities for
is highly regulated and governed by the can be safely applied to land directly,
processing and reuse. The volume
Environmental Protection Regulation thereby eliminating wasted resources
of completions fluids reported has
2008 (Queensland). Details—including in transport and treatment in the future.
reduced from the last reporting period
waste type, quantity, waste transporter This practice has been formalised by
from 9,535 Kl to 852 Kl. This is due to
and disposal location—are recorded state regulators into our environmental
the following:
and provided to the authorities (refer to related Case
• change in well productivity (reservoir administering authority. Study). The amount of drilling muds
variance across the fields) recorded for the July to December
2015 period was 571 Kl less than the
• changes to completion/work over
first half of the year. The last half of the
techniques
year saw 67 additional wells drilled,
• changes in Environmental Protection totalling 180 for that period. Given the
Regulation (Schedule 7 section increase in wells that were drilled and
65(3)), stating produced water is no the practice of the land spray initiative
longer a regulated waste. There is at the time, the decrease in muds is a
still a lag in this EPA change as some correlation of these activities.
contractors continue to record this
The other large contributor to liquid
as a trackable waste.
waste is washdown water/sludge
(seven percent). The volume of
washdown water/sludge reported
for the latter half of the year was
approximately five times that of the
first six months of 2015 (1,181 Kl
vs 221 Kl). The increased volume
resulted from necessary changes to
the operational protocol to optimise
equipment performance and reliability.
Coolant and separator solid volumes
have decreased since the last
reporting period. An increase of onsite
storage for separator solids and the
overall reduction of plant and vehicles
on site resulted in decreased offsite
disposal. Coolant volumes have
reduced in the later part of 2015 with
the reduction in equipment testing in
the operations phase.

36 Australia Pacific LNG Environmental and Social Report


Residual Chemicals – 7
Cooking Oil – 2 11 Waste Categories (in kilolitres) and
Cooking Oil – 2 15
Drilling Muds - Recycle
78 35
Interceptor Pond Water- Re

77 66 Septic Waste Untreated - R


69
Washdown Sludge - Recyle
415
0.01
786
Completion Fluids - Recycle
852
Solid Regulated Waste
Septic Waste Treated - Rec
Treated timber pallets (CCA 2
1,183
treated) and oily rags were 0.5
Oily Water (Bunds) - Recycl
the major contributors to the
total amount of solid regulated 2,520 Oily Filters - Landfill
waste generated by Upstream
Operations, of 40 percent and 14,414 Wet Oil - Recycle
52 percent respectively. The 15 20
total tonnage from the last Grease Trap - Recycle
reporting period has remained
relatively unchanged. 6,433 Oil (Dry) - Recycle

A breakdown of regulated wastes Waste Oils - Recycle


for the Upstream Operator can be
seen in Figure 5.4 and Figure 5.5. Coolants - Recycle

Figure 5.4 Upstream Operator Regulated Liquid Figure 5.5 Upstream Operator Regulated Solid
5.4 Upstream Operator Regulated Liquid Wastes Volumes S2 2015 Separator Solids
Wastes Volume and Disposal Methods Wastes Tonnage and Disposal Methods
and Disposal Methods
Residual Chemicals - Recyc
0.010.01 Waste categories
Waste categories inintonnes
tonnesand
and
micalsResidual
– 7 Chemicals – 7 Waste Categories (in kilolitres) anddisposal
disposal method disposal method
ng Oil – 2 Cooking Oil – 2 11 Waste Categories (in kilolitres) and method disposal method
Cooking Oil - Recycle
Cooking Oil – 2 11 15
ng Oil – 2 15
Drilling Muds Treated Wood -→Landfill
Treated Wood Landfill
Drilling
2 Muds- →
Recycle
Recycle Treated Paint Related Wastes - Lan
Wood - Landfill
78 35
Drilling
2 Muds - Recycle
Interceptor Pond 0.5
78 35 Interceptor PondWater- Recyle
Water0.5
→ Recycle Oily Rags/Oily Filters-
Oily Rags/Oily Filters → Landfill
Landfill
Interceptor Pond Water- Recyle Oily Rags/Oily Filters- Landfill
66 Septic Waste
77 Septic WasteUntreated
Untreated- Recycling
→ Recycle
Batteries (Palletised)
(Palletised)-→ Recycle
Recycle
66 69
SepticWashdown
Waste Untreated Batteries (Palletised) - Recycle
415
77 Washdown Sludge →- Recycle
Recycling
Sludge- Recyle
786 69 15 Washdown 20
Printer
Printer Cartridges Recycle
Cartridges -→Recycle
Sludge
Completion
Completion - Recyle
Fluids
Fluids → Recycle
- Recycle Printer Cartridges - Recycle
852 15 20
Septic Waste
Septic WasteTreated
Treated- Recycle
→ Recycle Fluro
Fluro Lamps
Lamps → Recycle
- Recycle
Completion Fluids - Recycle Fluro Lamps - Recycle
1,183
Oily
Oily Water (Bunds)- Recycle
Water (Bunds) → Recycle
Septic Waste Treated - Recycle
2,520 Oily
Oily Filters
Filters -→ Landfill
Landfill

14,414
Oily Water (Bunds)
Wet Oil - Recycle
→ Recycle
Wet Oil - Recycle

Grease
Oily Filters
GreaseS2- 2015
Trap-→
Landfill
Trap Recycle
Recycle
S2 2015
6,433 Oil
Oil (Dry) Recycle
(Dry) -→Recycle
14,414 Wet Oil - Recycle
Waste Oils-→
Waste Oils Recycle
Recycle
Grease Trap - Recycle
Coolants -→Recycle
Coolants Recycle
Oil (Dry) - Recycle
4 Upstream Operator Regulated Liquid Wastes Volumes
Separator Solids → Recycle
Separator Solids
d Disposal Methods WasteResidual
Oils - Recycle
Residual Chemicals- Recycle
Chemicals → Recycle

Coolants - Recycle
Cooking
Cooking Oil-→
Oil Recycle
Recycle

Paint
Paint Related Wastes- Landfill
Related Wastes → Landfill
Separator Solids
or Regulated Liquid Wastes Volumes
s
Residual Chemicals - Recycle
Australia Pacific LNG Environmental and Social Report 37
Cooking Oil - Recycle
Waste categ
Waste categories in kilolitres and disposal methods

Downstream Oily Water - Recyle


Oily

All regulated wastes, except for 15


sewage disposed of via the sewerage Con
Waste Oils - Recycle
system, are stored and monitored
on-site at Curtis Island, until they Med
can be disposed of by the waste
21 36 10 59
management contractor. Sewage
constitutes the largest component
of regulated liquid waste from the
Curtis Island construction site. It
is transported to Gladstone via
the GAWB pipeline and treated
at a licensed facility prior to re-
use as water supply to a nearby
alumina refinery. Figure 5.6 Downstream Operator Regulated Figure 5.7 Downstream Operator Regulated
S1 2015
Liquid Wastes and Disposal Methods Solid Wastes and Disposal Methods
Oily water, waste oil, oily rags, and
waste drums continue to be a major
Waste categories in kilolitres and Waste categories in tonnes and
regulated waste stream originating disposal methods:
disposal methods:
from Downstream construction
activities (refer to Figure 5.6 and Oily water → Recycle Oily rags/oily filters → Recycle
Figure 5.7).
Waste oils → Recycle Contaminated soil → Waste contractor
These waste streams are all
managed by a licenced waste Medical waste → Waste contractor
contractor and then transferred off-
site to certified waste management
facilities. Minor quantities of batteries
and tyres are also generated and
disposed of appropriately.

38 Australia Pacific LNG Environmental and Social Report


5.4 Environmental Incidents,
Notifications and Investigations
Protection of the environment is a priority for
Australia Pacific LNG. Our corporate goal is to ensure
there are no regulatory shutdowns or fines due to
environmental incidents.

Environmental Incidents
Summary
Our environmental incident frequency The level of risk associated with each
rate continues to decrease and currently incident was rated using a matrix that
stands at 1.35, an improvement of included safety, health, environmental,
10 percent over the previous regulatory, and legal and public
reporting period. considerations. Ten incidents were
classified as Severity 1 or minor, the
Our most common environmental
lowest category (causing minor local
reportable incident is an uncontrolled
impacts and no lasting effects). One
release to the environment including
incident was classified as Severity
hydrocarbon spills and sediment
2 or moderate (short term impacts
releases. Hydrocarbon spills are typically
to habitat, species or ecosystems).
very small in nature and sediment
This occurred when the unauthorised
releases are usually the result of a
clearing of 317 m2 occurred outside the
significant rain event that is above
approved disturbance limits adjacent to
the design criteria for erosion control
the lease pad.
devices installed.
A pre-clearance ecology survey of the
There were 11 reportable environmental
site confirms that the cleared area did
incidents incurred in the period involving
not comprise of remnant vegetation and
the following categories:
contained no regrowth of Endangered
• Hydrocarbon spills Regional Ecosystems. Refer to Figure
5.8 and Figure 5.9.
• Water quality exceedances
All incidents were recorded and
• Produced CSG water discharge
investigated to determine and
• Unauthorised clearing. communicate causes and potential
prevention measures and solutions.

60

50

40
No. of Incidents

0 Severity 5
30

0
Severity 4
20
0
Severity 3
10
1
Severity 2

10 0
Severity 1
S1 S2 S1 S2 S1 S2 S1 S2
60 2012 2012 2013 2013 2014 2014 2015 2015
Figure 5.8 Environmental Incidents by Severity Level Upstream
Figure 5.9 Environmental Incidents by Project Component

50
Upstream Downstream

40 Australia Pacific LNG Environmental and Social Report 39


Downstream
ncidents

30
Upstream Impacts on Fauna
There were nine reportable incidents 2 (moderate). These include eight spill In addition to the reportable
recorded by the Upstream Operator. events which are listed in Table 5.1 and environmental incidents, Australia
Eight incidents had a consequence one instance of unauthorised clearing Pacific LNG is required to notify the
ranked as Severity 1 (minor). One of vegetation. The list of reportable spill Regulatory Authorities of instances of
incident had a consequence of severity incidents is described in Table 5.1. fauna injury and deaths associated with
Business activities or occurring within
Australia Pacific LNG’s sites.
Reportable Spills Inventory
The Upstream Operator notified the
Incident Contaminant State (solid, Quantity Receiving Regulatory Authorities of six reportable
fauna deaths involving species in
(substance) liquid or (Kg, Litres environment
accordance with the relevant, approved
gas) or m3) (land, water
Species Management Plan. Species
or air) reported included: one Short-beaked
1 CSG produced water Liquid 100,000 L Land Echidna, four Grey snakes, and one
2 Drilling fluid Liquid 10,000 L Land Golden tailed gecko.
3 Turbid water Liquid 4.2 Ml Water At Curtis Island, two reportable fauna
4 CSG produced water Liquid < 20,000 L Land deaths occurred onsite, a Hardhead
Duck and an Australian Magpie were
5 CSG produced water Liquid 10.1 ML Water found deceased onsite. In addition,
6 CSG produced water Liquid 40,000 L Water six Torresian Crow eggs were found
CSG produced water Liquid 66,000 L Land abandoned in a nest that could not
7
be salvaged.
8 Hydrocarbon Solid 80 m (of soil)
3
Land

Table 5.1 Upstream Operator Reportable Spills Inventory

Downstream
There were two reportable incidents Fire ant inspections are ongoing and no
recorded by the Downstream Operator. further infestations have been found.
The first involved turbid water The Department of Agriculture and
overflowing spillways following a heavy Fisheries did not undertake any fire
rain event. The second was a reportable ant inspections during the reporting
spill where 50 ml of Panolin spilled into period as Australia Pacific LNG has
the Gladstone Harbour. demonstrated compliance with the Fire
All incidents were recorded, notified to Ant Management plan.
regulators and investigated. All incidents
were actual consequence Severity
1 (minor).

Reportable Spills Inventory


Incident Contaminant State (solid, Quantity Receiving
(substance) liquid or (Kg, Litres environment
gas) or m3) (land, water
or air)

Water (Gladstone
1 Panolin (hydraulic fluid) Liquid 50 ml
Harbour)

Table 5.2 Downstream Operator Reportable Spills Inventory

40 Australia Pacific LNG Environmental and Social Report


5.5 Spill Prevention and Response 5.6 Key Performance
Indicators

Upstream Downstream Upstream


110 emergency response training Spill prevention and response onsite is Number of reportable
9
activities were conducted for Australia currently handled under the provisions environmental incidents
Pacific LNG Operations during the of the Principal Contractor’s Emergency
reporting period. 13 percent of the and Spill Prevention and Response Number of reportable water
0
exercised scenarios were Loss of Plans. These plans have been quality exceedances
Containment, most including spill approved by Regulators, and response
response aspects. Scenarios exercised techniques have been included in the Number of reportable
5
included loss of hydrocarbons and emergency management plans of spills to land
response to hazardous material subcontractors. These plans lay out
spills. Spill Trailers, located at Spring specific procedures for addressing Number of reportable
3
Gully, Reedy Creek, Condabri and spills to land and water, depending on spills to water
Talinga, have been used in site the size and nature of the spillage.
exercises and team familiarisation Number of reportable fauna
6
training. Newly trained HAZMAT On deaths / injury
Scene Commanders and HAZMAT
Responders participated in these Incidents of non-compliance
2
activities. Site Emergency Response waste conditions
vehicles for Spring Gully, Reedy Creek
and Condabri arrived in July, with crews Incidences of non-compliance
0
utilising them as part of site responses with noise limits
during the reporting period.

Downstream
Number of reportable
2
environmental incidents

Number of reportable water


1
quality exceedances

Number of reportable spills


0
to land

Number of reportable spills


1
to water

Number of reportable fauna


3
deaths / injury

Incidents of non-compliance
0
waste conditions

Incidences of non-compliance
0
with noise limits

Australia Pacific LNG Environmental and Social Report 41


6. Biodiversity
Conservation
As part of Australia Pacific LNG’s approval process by
the State and Federal Government, biodiversity impacts
were identified and assessed, and measures to avoid,
minimise and mitigate were determined.
Biodiversity conservation involves analysis of potential impacts to biodiversity. Where
potential impacts are identified, avoidance, minimisation, and mitigation measures are
determined to reduce risks to acceptable levels. Any significant residual impact is then offset.
These offset measures include the protection of high biodiversity values across the diverse
terrestrial, aquatic, coastal and marine ecosystems.

Photo courtesy Ralf Regeer, Ausecology.


6.1 Ecological Management

Upstream Downstream
Prior to conducting activities involving No additional vegetation clearing works
significant land disturbance, an were conducted during the period.
assessment of the condition, type and
During the reporting period, seven
ecological value of vegetation in the
snakes (pythons, an Eastern Brown
area is undertaken. This is referred to
Snake and a Lesser Black Whipsnake)
as the field ecological assessment.
were successfully caught and relocated
Following this, a pre-construction field
to adjacent bushland.
environmental scout is undertaken.
Migratory shorebird monitoring was
A field environmental scout
conducted in December 2015. During
also confirms the suitability of
the survey no disturbances to roosting
infrastructure layout in accordance
or foraging behaviour associated with
with the Environment Protection and
construction or operation activities
Biodiversity Conservation (EPBC) Act
were observed.
1999 and other applicable regulatory
requirements as well as relevant Quarterly mangrove monitoring
plans for threatened and endangered continued in accordance with
species. These requirements are the Receiving Environment
specified in the Australia Pacific LNG Monitoring Program.
Environmental Constraints Planning and
A Water Mouse survey was conducted
Field Development Protocol.
onsite 14 to 18 November 2015. No
There was one reportable incident evidence of the presence of Water
regarding ecological management in the Mouse was detected in the study area
reported period. The incident involved during the survey, despite extensive
the clearing of 317 m2 of vegetation daytime searches for Water Mouse
adjacent to a lease pad in the Dinoun signs and 400 nights of trapping effort
State Forest. A pre-clearing ecology within habitats suitable for Water
survey confirms that the cleared area Mouse. Despite the lack of detection,
did not comprise of remnant vegetation remaining mangrove habitats within the
and contained no regrowth of study area provide potentially suitable
Endangered Regional Ecosystems. habitat for the species.

Australia Pacific LNG Environmental and Social Report 43


Australia Pacific LNG External Affairs Manager, Fiona McLeod and ConocoPhillips Manager Communities and Sustainable
Development, Robert Gibb with Roxy, a juvenile Hawksbill turtle before her release.

Quoin Island Turtle Rehabilitation Centre


ConocoPhillips and Australia Pacific LNG have announced they will
continue its partnership with Quoin Island Turtle Rehabilitation
Centre, located in the Gladstone Harbour, celebrating with the
release of Roxy the turtle back into the wild.
Roxy, a juvenile Hawksbill turtle, was tagged and hand-raised in 2013. With four stand-alone tanks, an in-ground heated
Vanuatu and is one of the Centre’s recent success stories. After rehabilitation pool, an air conditioned treatment room and dry
being accidently hooked by a fisherman in July she was brought dock room, water filtration systems and a necropsy facility, the
to the centre, underwent surgery and was fully rehabilitated and Centre has cared for over 165 turtles since opening.
released after three months.
The Centre treats the more common green turtles as well
The Centre, which rescues and rehabilitates sick and injured as other rare breeds including Loggerheads, Hawksbills
turtles, has been supported by Australia Pacific LNG since and Flatbacks.

44 Australia Pacific LNG Environmental and Social Report


6.2 Quarantine

Upstream Downstream
Biosecurity packages have been The LNG facility has an overarching
developed and are supported by biosecurity plan for the Downstream
ongoing education and training, activities. This plan serves as a guideline
including an e-learning module and for the biosecurity management
improved weed identification guides. plans used by subcontractors during
Project construction.
There have been no quarantine
incidents reported during July and One important aspect of this plan is
December 2015. the Australia Pacific LNG Sail Away
Clearance Checklist. This checklist
requires a thorough review of customs
clearance documentation, cleanliness
of the modules, final wash down
and re-checks for contamination,
pre-departure inspection by DAF, and
other criteria. The checklist is designed
to prevent biosecurity risk material
entering Australia via the module
transport barge.

The Principal Contractor has completed


planned procurement and only field
orders remain as required. An estimated
5,000 international shipments have
been imported to Australia since the
Project began. To date, there have
been no significant breaches of the DAF
quarantine procedures.

Australia Pacific LNG Environmental and Social Report 45


6.3 Weed, Plant Pathogen
and Pest Management

The Upstream and Downstream


Operators have developed Biosecurity
Management Plans, which include
weed hygiene procedures. These
plans outline controls to reduce
the introduction and spread of
pest species including weeds.
Australia Pacific LNG’s biosecurity
requirements have been incorporated
into contractor management plans to
ensure the plans are implemented.

Upstream Downstream
Australia Pacific LNG continued The Principal Contractor undertook
to implement pest management a weed survey of the Australia
programs and actions for existing Pacific LNG site on Curtis Island in
weed and pest issues. No pest or September 2015. Three declared
pathogen incidents were recorded pest species were recorded on Curtis
during the reporting period. Island during the September 2015
survey, comprising of parthenium
A weed identification guide specific weed, rubber vine and lantana.
to the Surat and Bowen basins has
been prepared and finalised. The The weeds were removed via a
weed identification guide has been combination of chemical treatment
developed to increase the awareness and manual removal.
of the highest risk weeds to the
Business and enable personnel
to recognise regionally significant
species, including Chilean Needle
Grass, Rats-tail Grasses and prickly
shrub species such as Prickly Acacia.
The guide will be rolled out in 2016
as part of a broader biosecurity
education program.

46 Australia Pacific LNG Environmental and Social Report


6.4 Reinstatement

Reinstatement is the process of The Upstream Operator reinstated


bringing the construction earthen 901 ha of disturbed areas including
landscape back to the original profile of well leases, flow lines, access tracks
the surrounding environment, including and rights of way. Other reinstated
the stabilisation of the disturbance areas included helipads, camps
site. Stabilisation can include seeding and laydowns, bringing the total of
with grasses of a suitable species reinstatement completed to over
in their applicable environment; i.e. 6,258 ha, representing approximately
improved pasture returned where 67 percent of all areas disturbed.
improved pasture was disturbed. The Figure 6.1 shows the progress of
reinstatement task is built into the reinstatement in relation to the total
process of construction. disturbed areas.

10,000
10,000 Disturbance
Disturbance vs vs Reinstatement
Reinstatement in ha
in ha

9,000
9,000 Cumulative
Cumulative Reinstatement
Reinstatement in hain ha
8,000
8,000
Cumulative
Cumulative Disturbance
Disturbance in hain ha
7,000
7,000

6,000
6,000
Hectares
Hectares

5,000
5,000
4,000
4,000
3,000
3,000
2,000
2,000
1,000
1,000
0
0
S1 S2 S1 S2 S1 S2 S1 S2
S1
2012 S2
2012 S1
2013 S2
2013 S1
2014 S2
2014 S1
2015 S2
2015
2012 2012 2013 2013 2014 2014 2015 2015

Figure 6.1 Upstream Operator Disturbance and Reinstatement Progress

Lummus Consultant Jeff Bleathman and Australia Pacific LNG personnel, Michael
Stahl, Candice Shelley and Marianne Gibbons, reviewing reinstatement of Camp
Four near Biloela in September 2015.

Australia Pacific LNG Environmental and Social Report 47


6.5 Offset Strategy

Australia Pacific LNG adopts a


strategic approach to offsets, which
6.5.1 Offset Progress Australia Pacific LNG continues
supporting terrestrial and marine
provides environmental benefits with Australia Pacific LNG recognises the biodiversity research through the Gas
improved biodiversity outcomes and development of its LNG Facility on Industry Social and Environmental
increased confidence of conservation Curtis Island, along with supporting Research Alliance (GISERA).
outcomes. This strategic approach to infrastructure and services, increases Current projects with biodiversity
offsetting has been adopted in line with the management requirements impacts include:
government recommendations. for maintaining terrestrial and
marine biodiversity. • Priority threat identification,
At least three strategic offset sites are management and appraisal
required to compensate for Business Under the EPBC Act 1999, offsets (terrestrial biodiversity)
impacts on: compensate for the impacts
associated with development. • Fire ecology of grassy woodlands
• Brigalow and semi-evergreen vine Offsets include protection of at-risk (terrestrial biodiversity)
thicket and fauna habitat environmental assets, restoration • Habitat selection by two
• Cycas megacarpa (cycads) or extension of habitat for species focal species
threatened by development, or
• World Heritage Area, Shorebirds, improvement of the values of a place • Ensuring biodiversity offset success
Water Mouse and fisheries. with a high degree of heritage value. (optimising seed sourcing for
one plant)
Additional small offsets are expected Environmental offsets for the Project
to be required for significant impacts comprises both land-based sites • An integrated study of the Gladstone
on Brigalow and semi-evergreen vine (direct offsets) and contributions to marine system (marine environment).
thicket flora species. other activities such as removing Australia Pacific LNG is on track to
threatening processes and research provide a substantial portfolio of direct
(indirect offsets). Australia Pacific and indirect offsets to compensate for
LNG’s offsets aim to secure strategic unavoidable impacts on environmental
environmental areas with the following values. These offsets represent a
priorities: Great Barrier Reef World long-term commitment, and will involve
Heritage values, threatened ecological many years of on-ground management
communities, endangered and of as suitable sites are secured.
concern remnant and high value
regrowth vegetation, marine habitat,
wetlands, watercourses, threatened
flora and habitat for threatened fauna.

The Colamba offset area. Photo courtesty of Ralf Regeer, Ausecology.

48 Australia Pacific LNG Environmental and Social Report


Upstream
Direct Offsets establishment/maintenance of fire pedleyi individuals be established
breaks and pest management. within the offset area from propagated
The two key offsets are Dukes Plain stock and protected, maintained and
and Inverness. The Dukes Plain Inverness is Australia Pacific monitored for a minimum of 10 years.
property is located south of Theodore LNG’s offset site to compensate
in central Queensland. This will provide for disturbance to threatened flora
Indirect Offsets
offsets for threatened ecological species Cycas megacarpa and Acacia
communities, endangered and of pedleyi. Last year 261 mature salvaged Australia Pacific LNG has continued
concern vegetation and associated Cycads were planted in the Inverness to support the conservation of the
threatened fauna habitat. The offset area. Mid 2015, a further 309 Fitzroy River turtle. The nest protection
Inverness offset property is located Cycad seedlings (propagated over the program again involved the location
on the ranges west of Gladstone and previous three years) were planted. and protection of nests along a seven
is where translocation and planting of kilometre stretch of the Fitzroy River
Approximately 2,000 propagated
threatened flora species removed or during the spring/summer months.
Cycas megacarpa individuals are
impacted from the pipeline corridor is Surveys have shown that when nests
currently being stored, maintained and
taking place. are protected, predation rates can be
monitored at a nursery in Townsville
halved from the 90 to 100 percent
Included into the portfolio in 2015 prior to planting at the Inverness
rates observed prior to the program.
is a direct offset on the Colamba offset area. The total number of Cycas
property, located north-east of Miles. megacarpa to be propagated and In 2012 a Deed of Agreement was
The Colamba offset will compensate planted will take into account a 30 signed between Australia Pacific LNG
for Project impacts on Brigalow, percent mortality rate over the life of and Fisheries Queensland, committing
fauna habitat and wetland values not the program, to ensure a minimum to providing a one-off contribution
yet acquitted by existing offsets. An of 1,800 Cycas megacarpa are of at least $100,000 for a project on
offset agreement with the Colamba successfully established at the offset restoration of fish movement and
landholder was signed in September area in accordance with the Project’s rehabilitation of freshwater habitats
2015. The Colamba Offset Area approval conditions. in either the Fitzroy or Murray Darling
Management Plan (OAMP) which Catchments. Queensland Murray-
To date, specific management and
details conservation outcomes and Darling Committee (QMDC) were then
monitoring activities have been
management objectives for Brigalow engaged to construct a fishway at the
undertaken for the translocated Cycas
threatened ecological communities, Condamine town weir, a commitment
megacarpa to assess the condition
threatened fauna habitat and wetland of $190,000. The project involves the:
and the success of the translocation
values, has been developed for • Construction of an operational
program and opportunistically across
approval. In recent months ecological fishway at the Condamine town weir,
the whole offset area. In addition, an
assessments have been undertaken to facilitate movement of the Murray
in-situ Cycas megacarpa population
and long term monitoring set up. The River Cod and other native fish to
is also being monitored to assess
establishment of offset area fencing enable passage around the weir
any temporal variation between the
and firebreaks is currently being
reference and translocated populations. • Weed and pest management
worked through.
A total of 6,955 Acacia pedleyi seeds activities within the Condamine town
The Dukes Plain Offset and weir vicinity, in order to improve the
were collected and set in early to mid
Rehabilitation Management Plan, habitat of the Murray cod and other
2015 in preparation for the first stage of
which details conservation outcomes native fish in the Condamine River.
planting at the Inverness offset area in
and management objectives for
March 2016. Planting will occur within
Brigalow and semi-evergreen Construction of the fishway was
approximately 4.5 ha of suitable habitat
vine thicket threatened ecological completed in late 2015. QMDC will
at a planting rate of approximately
communities and threatened fauna continue to monitor the fishway in
2,500 plants per ha. Additional seed
habitat, was approved by the 2016 to assess its functionality. In
will be collected and propagated for
Australian Government Department addition, QMDC will undertake weed
subsequent planting events. Acacia
of Environment in October 2015. On and pest management activities within
pedleyi plantings will be managed
the ground management activities the surrounding Condamine town weir
and monitored in accordance with the
implemented in 2015 include trials vicinity, including carp-trapping both
approved Inverness OAMP, including
to optimise the growth of Brigalow, upstream and downstream of the
weed control and site preparation prior
ecological assessments and Condamine town weir.
to planting. Project approval conditions
monitoring, cultural heritage surveys,
require a minimum of 8,050 Acacia

Australia Pacific LNG Environmental and Social Report 49


The completed fish ladder - already working.

Fish Ladder Installed at Condamine Weir


Australia Pacific LNG has supported construction of a fish ladder
which will enable fish migration and improve native fish habitat and
breeding grounds along a large section of the Condamine River in
southern Queensland.
Origin on behalf of Australia Pacific LNG has contributed to ensure that native fish habitat is enhanced in areas of the
approximately $180,000 in funding through an environmental Queensland Murray-Darling Basin where Australia Pacific LNG
offset arrangement in partnership with the Queensland Murray- operates,” Natasha said.
Darling Committee (QMDC) to construct a fish ladder below the
QMDC CEO Geoff Penton said weirs that are a barrier to fish
Condamine Bridge to help native fish ‘step’ their way over the
migration had been identified as a contributor to the decline of
town weir wall.
native fish species in the Murray-Darling Basin.
The ladder is a series of rising rock pools and will effectively
“This fish ladder is low maintenance and is expected to open up
open the river stretch from Cotswold to the Condabri Weir,
almost 100 kms of the Condamine River to fish passage which
giving native species such as the vulnerable Murray River Cod a
is a significant gain for fish needing to migrate to forage and
better chance of survival.
breed,” Geoff said. “And it’s already working, with sightings of
Natasha Patterson, Origin General Manager Approvals, Land dozens of native fish resting in the pools during a flow in the river
and Community, said the partnership with QMDC was an from recent rain.”
important initiative. “We are proud to be assisting in efforts

50 Australia Pacific LNG Environmental and Social Report


6.6 Key Performance
Indicators

Downstream
The Monte Christo offsets property Work undertaken over the past six Hectares of net disturbance*
purchase, jointly made with two other months has continued to progress
LNG proponents, was developed transfer of the remaining freehold Upstream 9,107 ha
to protect and remove threatening allotments to the Queensland Downstream 193 ha
processes from land containing Great Government for inclusion in the
Barrier Reef World Heritage values, Queensland Conservation Estate.
remnant vegetation and significant Disturbance of remnant
The Long Term Marine Turtle vegetation
marine habitat. The property was
Management Plan was approved
secured with an official announcement Upstream 214 ha
by the Australian Department of the
made in August 2014.
Environment in July 2014. This plan
Downstream 0
This offset property purchase was used builds on existing programs funded by
as a case study in a World Wide Fund Australia Pacific LNG including GISERA Disturbance of high value
for Nature Australia publication, Building and the Western Basin Dredging regrowth in hectares
Nature’s Safety Net 2014: A decade Environmental Review and Monitoring
of protected area achievements in Program. Australia Pacific LNG has Upstream 22 ha
Australia, where the benefit of the offset continued to progress this plan with
Downstream 0
in protecting the critically endangered the other proponents with a program of
Capricorn Yellow Chat was recognised. studies to commence implementation in
Hectares of successfully
This is one of several species with the next reporting period.
improved protection arising from the completed reinstatement*
offset even though it is not directly
Upstream 6,258 ha
impacted by the Business.
Downstream 0
Areas of offset established
and protected
Upstream 1#

Downstream 0

Number of complaints
received related to weed
management
Upstream 0
Downstream 0

*These KPI values represent total value from


Business inception. All other KPIs in this
subsection refer to the reporting period only.

Inverness, as detailed in section 6.5.1.


#

Australia Pacific LNG Environmental and Social Report 51


7. Sustainable Resource
Management
Australia Pacific LNG strives to ensure resources are
used, developed, and protected within the Business
in a way and at a rate that enables people and
communities, including Indigenous peoples, to provide
for their present and future social, economic, and
cultural wellbeing.
7.1 Agricultural 7.2 Water
Land Management

Australia Pacific LNG aims to avoid Water is extracted from the target coal 7.2.2 Supply of
or reduce loss of access to Good formations to allow the production of
Quality Agricultural Land (GQAL) by coal seam gas. Low permeability rock Treated CSG Water
locating surface infrastructure away strata that overlay and underlay the for Beneficial Use
from such land where practicable. CSG formations, known as aquitards,
During this reporting period, 586 ha of protect the adjacent aquifers used The quantity of treated CSG water
land disturbed was classed as GQAL, by others from the effects of the supplied for beneficial use also
representing 73 percent of the total resultant coal depressurisation. The increased compared to the previous
area disturbed in the period. Upstream Operator has implemented its reporting period, reflecting the
groundwater monitoring plan to detect increased volume of CSG water
pressure changes in these aquifers. produced. The operation of the
Fairymeadow Road Irrigation Scheme
7.2.1 CSG Water has meant that no releases to the
Condamine River have occurred during
Production the reporting period.

The vast majority of CSG water The volume of treated CSG water
production during the reporting period supplied for beneficial use was 9,511
was generated from the Australia Pacific ML, which represents an approximate
LNG CSG fields of Talinga and Orana, 27 percent increase on the previous
Spring Gully, Condabri, Combabula and reporting period and 80 percent of the
Reedy Creek. Minor volumes of CSG total volume of produced CSG water
water were also produced from the Peat (Figure 7.1).
field and appraisal wells developed as
part of the exploration program.
The total volume of CSG water
production for the reporting period was
11,920 megalitres (Ml), representing
an approximate 15 percent increase
on the previous period, reflecting the
increase in the number of CSG wells
brought online.
CSG water is temporarily stored in
ponds, prior to desalination treatment
and supply for beneficial use, including
irrigation, aquifer injection, project, and
construction uses. Any treated water
unable to be beneficially used is released
under licence to natural streams.

Australia Pacific LNG Environmental and Social Report 53


Spring Gully Talinga and Condabri Reedy Creek
The primary beneficial use scheme The primary beneficial use scheme The primary beneficial use scheme for
for Spring Gully is aquifer injection. for treated CSG water produced treated CSG water produced from the
This comprises a permeate treatment from the Talinga and Condabri WTF’s Reedy Creek WTF is aquifer injection.
facility (PTF) and three injection bores is the supply for irrigation purposes The scheme has a maximum daily
into the Precipice aquifer, with a total by landholders connected to the capacity of 40 Ml/d which is the largest
daily capacity of 8.1 Ml/d. The Spring Fairymeadow Road Irrigation Pipeline aquifer injection system in Australia.
Gully aquifer injection scheme was the (FRIP) and for Project activities. Treated It commenced operation in January
first approved in Australia for treated water produced from the Talinga 2015 and comprises a permeate
CSG water. The aquifer injection WTF is pumped to Monreagh Dam treatment facility and 12 injection bores
scheme commenced operations and then supplied to landholders which direct treated CSG water into
in December 2014. The scheme is via the Monreagh Pump Station the Precipice aquifer. The scheme
supplemented by a 300 ha Pongamia into the FRIP. When Monreagh Dam is supplemented by approval for
plantation irrigation scheme, Business is full a contingency release to the emergency release to Yuleba Creek for
activities, and a contingency release to Condamine River is authorised. The a limited period.
Eurombah Creek. Condabri plant became operational in
December 2014.

12000
Produced Water Awaiting Treatment

10000
Total Volume of Brine Produced

8000 Permeate Discharge to Creek


Megalitres (Ml)

Total water supplied for beneficial use


6000

4000

20%
2000
10% 80%

0
0% 70%
S1 S2 S1 S2 S1 S2 S1 S2
2012 2012 2013 2013 2014 2014 2015 2015
Produced Water Awaiting Treatment 60%

Figure 7.1 CSG Water Produced and Supplied for Beneficial Use 50%
Total Volume of Brine Produced

40%
Produced Water Awaiting Treatment Permeate Discharge to Creek
30%
Total Volume of Brine Produced Total water supplied for beneficial use

Permeate Discharge to Creek

Total water supplied for beneficial use 20%

10% 80%

0% 70%
20%
S1 S2 S1 S2 S1 S2
2 2013 2013 2014 2014 2015 2015
10% 60%
80%

50%
0% 70%
S2
2015 40%
54 Australia Pacific LNG Environmental
60%and Social Report

30%
50%
7.2.3 Groundwater
Monitoring System

Upstream Downstream
A network of deep groundwater Groundwater monitoring was
monitoring bores has been established undertaken on the Curtis Island site
to provide a regional groundwater from 2010 to 2014. The purpose of
monitoring system for the Australia the study was to collate and analyse
Pacific LNG Business. The network the groundwater monitoring data taken
includes over 120 monitoring bores prior to and during construction at the
purpose-built to provide data to site, to identify trends, and to review
the Office of Groundwater Impact geotechnical data. This was undertaken
Assessment (OGIA), with a total of 48 in order to develop a hydrogeological
km drilled. These dedicated monitoring conceptual model of the site and any
bores will be augmented by existing ongoing monitoring recommendations.
government bores and landholder This included the collation and analysis
production bores. of historic groundwater data for the 38
monitoring bores installed across the
Of the planned network, only five
site prior to and during construction.
dedicated monitoring bores required
to be drilled by the end of 2015 were The Groundwater Monitoring Summary
not completed. All five are scheduled and Conceptualisation Report was
for completion by early February finalised in 2014. Based on the
2016. The additional monitoring bores conceptual model and review of the
originally required to be drilled prior to location of monitoring bores, a number
31 December 2016 are currently under of opportunities were presented for
review as part of OGIA’s tri-annual consideration for any future installation
revision of impact forecasts in the of groundwater bores and the
second iteration of the Underground undertaking of a monitoring program
Water Impact Report. during operations.
At the end of the reporting period, Since the completion of the
27 Queensland Government and Groundwater Monitoring Summary
landholder bores had been equipped and Conceptualisation Report in
with automatic groundwater level data the last quarter of 2014, further
logger instrumentation. groundwater monitoring will only be
undertaken in response to any issues
In addition to these monitoring bores,
that may arise during the remaining
there is a network of shallow sentinel
construction phase.
monitoring bores designed to ensure
the integrity of produced water and
brine storage ponds.
Most completed monitoring bores are
now equipped with groundwater level
loggers and dedicated sampling pumps
as required.
The latest results of groundwater
monitoring undertaken by Australia
Pacific LNG are reported and made
publically available in the 2014-2015
Groundwater Assessment, which is
available at the following link: http://
www. aplng.com.au/environment/
management-plans
Australia Pacific LNG Environmental and Social Report 55
7.2.4 Make Good 7.2.5 Hydraulic 7.2.6 Ground
Agreements Fracturing Subsidence
The Surat Underground Water Impact Hydraulic fracturing frees up gas to Monitoring System
Report (UWIR) ) initially identified 40 flow, meaning that fewer wells are Ground motion is monitored using
bores for ‘make good’ agreements, required. Most of the current natural direct, on-ground instrumentation
with Australia Pacific LNG as the gas production is in high permeability and remote Interferometric Synthetic
responsible tenure holder, involving 24 (or high flow) areas where hydraulic Aperture Radar (InSAR). The on-ground
landholders. Throughout the course of fracturing is not required. Only one instrumentation includes tiltmeters
ongoing operations and assessments, development well required hydraulic and extensometers. Tiltmeters are
various bores have been added fracturing during the period. designed to measure very small
or removed from the make good changes from the horizontal level,
assessment list with refinements to the either on the ground or in structures.
understanding of geological and bore Extensometers are designed to
details, or changes to the responsible measure displacement and are ideal for
tenure holder and immediately subsidence monitoring.
impacted area. Currently, 50 bores are
confirmed or under assessment for A geodetic monitoring network was
make good amongst 25 landholders. established in 2013. This network
Make Good Agreements have been comprises 47 permanent survey marks
executed with 20 of these landholders across Australia Pacific LNG tenures
for 41 bores. During the period there (one survey mark was destroyed
were nine Make Good Agreements between the last two monitoring rounds
executed for 16 bores. as a result of construction activities).
There is ongoing communication The InSAR data collected and
with the regulatory authorities and processed over 2012 to 2015
negotiations continue with landholders. indicates subsidence and uplift trends
in the Undulla nose region. Latest
assessment and details of ongoing
studies can be found in Section 7 of the
2014-2015 Groundwater Assessment
Report. The motion is below any
trigger for formal notification, however
regulators were consulted.

56 Australia Pacific LNG Environmental and Social Report


7.3 Raw Materials

Upstream Downstream
544
754
The principal raw materials required for Raw materials used in construction
the Upstream construction activities consist predominantly of components
were water and gravel. Gravel is used in for making concrete such as cement, 102,500
1,690
construction of access roads and well aggregate material and water. At the end
pads and ongoing maintenance. of the reporting period, approximately
704 m3 of concrete had been used
The Upstream Operator used on Curtis Island. Other raw materials
approximately 400 Ml of water sourced used were mostly sand and aggregate
from landholder bores and dams, (Figure 7.2).
operational Water Treatment Facilities The Gladstone Area Water Board
(i.e. treated CSG water), dams/tanks (GAWB) pipeline continued to supply
with untreated CSG water and municipal reticulated water services to the
110,000
water supply. Project site on Curtis Island. GAWB
supplied the site with 110 Ml of water,
With regard to gravel, approximately a marginal decrease from the previous
121,000 tonnes was used in reporting period. Figure 7.2: Downstream Project
construction of well pads and road Raw Materials
maintenance for the period.
Raw Materials in Tonnes
544
754

Water
102,500
1,690
Sand
Sand

Concre
Concrete
Agrega

Aggregate

110,000

Australia Pacific LNG Environmental and Social Report 57


7.4 Gas Industry Social Environmental
Research Alliance (GISERA)

Australia Pacific LNG and peak science Agricultural Land Management Social and Economic
body, CSIRO, entered into a research
alliance in 2011 for five years, initially as The five research projects underway in The four research projects in social
a bilateral venture, and with a view to this portfolio are designed to maximise and economic research aims to identify
establishing industry and government agricultural productivity during and what communities want and need
support. The initial investment from beyond the life of gas extraction to help inform and support changes
Australia Pacific LNG is AUD$10 million on farms. occurring in CSG development regions.
over five years, with CSIRO committing These projects include: These projects include research
a further AUD$4 million in in-kind on monitoring of regional changes,
support. QGC has also joined GISERA • Preserving Agricultural productivity community function and wellbeing and
in recognition that the challenges being – 85 percent complete community aspirations including:
addressed through GISERA are relevant • Shared space – complete
to the entire CSG to LNG industry • Monitoring regional change
and that there are benefits from such • Farm gas design – 85 percent – complete
collaborative research. complete • Community function and wellbeing
GISERA was established in recognition • Making tracks, treading carefully – 90 – complete
of the impacts of CSG on public assets, percent complete • Community aspirations – complete
and the related need to undertake • Without a trace – complete
publicly-available quality research to • Economic assessment and
address those impacts. The overall progress for the five projects forecasting – 30 percent
is approximately 90 percent. The progress for these projects is
GISERA’s main research areas include
water, agriculture, biodiversity, marine approximately 90 percent.
Terrestrial Biodiversity
environment, socio-economic and
greenhouse gas. There are four projects underway in
this portfolio, including understanding

7.4.1 Project Updates


threats to biodiversity, fire study, habitat
selection for two focal species and
7.5 Key Performance
Surface and Groundwater
biodiversity offset success. Indicators
These projects include: (all values refer to this reporting period)
The research projects in this portfolio
look at maximising the reinjected • Priority threat identification and
amount of treated coal seam gas water management – 85 percent complete
into aquifers. Initial results identified Volume of CSG
11,920 MI
clay mobilisation as a significant source • Fire study – 65 percent complete Water produced
of reinjection clogging, a process that • Habitat selection by two focal Volume of water
reduces the volume of water that can species – 25 percent complete 3,267 Ml
injected to aquifers
be reinjected. These projects include:
• Ensuring biodiversity offset success Volume of CSG water
• Geochemical response to reinjection – 50 percent complete 9,511 Ml
applied to beneficial use
– 90 percent complete
The overall progress for these projects Volume of salt recovered for
• Reinjection of CSG water is approximately 60 percent. 0
beneficial/commercial use
– 75 percent complete
• Groundwater modelling - complete Marine Environment Number of Make Good
9
Agreements finalised
• Groundwater baseline study Marine environment research aims
– 65 percent complete to improve the understanding of the
vulnerable components of the marine
• Hydrocarbons in groundwater ecosystem to minimise impacts
– 15 percent complete from LNG developments around
The overall progress for these projects Gladstone Harbour.
is approximately 70 percent. The research project examined
how sediments from dredging and
Greenhouse Gas Footprint discharge affect seagrass and turtle
This project measures methane feeding grounds.
seeping from underground in the
Surat Basin, and identifies sources This project is complete.
of methane.
The progress for this project is
approximately 60 percent complete.

58 Australia Pacific LNG Environmental and Social Report


Jamie and Natalie Dingle - Roma Wire and Steel suppliers.

CSG: Boom Time Benefits


The growth in CSG in southern Queensland has brought
substantial changes to regions where development has occurred
during the construction phase, with positive effects in terms
of income, ongoing jobs, and attracting young people to local
communities, according to a new report.
The report - Overview and synthesis of regional economic This included an influx of younger people, both male and
effects of the CSG industry during the construction phase female in the regions, due to the increased demand for
was produced by GISERA and was based on a review of employment in service and support industries. While the
studies undertaken in the Surat and Bowen basins since the reports focused on the impact of the construction phase,
early years of CSG development. it also found that as the industry moves into long-term
operations, “many labour requirements… can be sourced
The report found that the CSG industry’s extensive
either from local towns or from nearby town centres.”
geographical footprint allowed for “a broader range of
stakeholders to benefit from resource extraction, potentially Further details about GISERA’s activities or a copy of the
affecting more evenly the initial distributions of income report can be found on the GISERA website:
across regions.” www.gisera.org.au

Australia Pacific LNG Environmental and Social Report 59


8. Community,
Stakeholders and
Social Management
Australia Pacific LNG establishes stakeholder
engagement strategies that strive for positive and
practical outcomes that help to address impact, share
the benefits of the Business, and respond to identified
stakeholder needs and issues. Stakeholder engagement
reflects the diversity of stakeholders and uses
innovative, practical partnerships to achieve mutually
beneficial outcomes.

60 Australia Pacific LNG Environmental and Social Report


8.1 Stakeholder Communication
and Consultation

Upstream
The Stakeholder Engagement Engagement with communities is a Enquiries
Strategy articulates Australia Pacific priority for the Upstream Operator.
LNG’s commitment and approach The Upstream Operator held 45 formal The Upstream Operator enables
to stakeholder engagement, and engagements with Local Governments stakeholder contact by maintaining a
describes how this commitment will be and key community stakeholder range of information channels including
managed across the gas fields, pipeline groups throughout the region. Informal regional office walk-ins, the Origin and
and LNG Facility components for the engagement activity continued through Australia Pacific LNG websites, email
life of the Business. support and participation in various enquiry channels, and an information
events. During the period, the Upstream hotline. The majority of enquiries related
These stakeholders are broadly to information regarding the Business,
Operator participated in:
classified as: employment opportunities and
• The Chinchilla Trail Ride landowner matters.
• Community
• Maranoa Regional Council Audio Figure 8.1 summarises enquiries
• Government
Visual Project for Upstream.
• Traditional / Indigenous
• The Queensland Regional
owner groups
Community & Achievement Awards.
• Landholders 10 2
In addition there were 1,132 informal
• Suppliers and contractors engagements including emails,
18
telephone calls and walk-ins to 41
• Employees of Australia Pacific LNG,
regional offices. Regional Community
and its shareholders ConocoPhillips, 45
Consultative Committee (RCCC)
Sinopec and Origin
meetings for the Western Downs,
• Lenders, including export credit Maranoa and Banana Shire regions
agencies and commercial banks that continued as the key forum for
provide financing for certain elements exchanging community insights, priority
of the Project issues and Project information.
• Non-government organisations and
other special interest groups
• Owners/Investors in the shareholders 557
of Australia Pacific LNG (Origin,
ConocoPhillips and Sinopec).
Figure 8.1: Upstream Project Topics
of Enquiry
10 2
Topics of Enquiry

18 General Project Information


41

45 Stakeholder Engagement

S2 2015
Employment

Procurement

Community Investment

557 Education and Training

Australia Pacific LNG Environmental and Social Report 61


8.2 Local Content

Downstream
Community relations activities included Local content includes employment, how opportunities are provided for
20 formal stakeholder engagement procurement, training and local businesses to participate in
events, 490 informal stakeholder development, and contracting of the Business. The strategy includes
engagements (emails, telephone people, goods and services who are training and development initiatives to
calls and walk-ins), one sponsored considered by Australia Pacific LNG build capacity in local businesses, as
community event and two collaborative to be nationals or national companies well as our Regional Buy Program.
engagement activities. Employment operating within Australia, including
During the period, more than 360
continues to be amongst the most the immediate area where the Project suppliers attended Regional Buy
frequent enquiries. Topics of enquiries is located. It includes any service or Program workshops in the Surat
are shown in Figure 8.2. maintenance element forming part of Basin. Regional suppliers are a defined
materials purchase. group within our Local Content
.
SinceTopics
2011,of the
Enquiry
Local Content Team Policy and require additional support
4
has referred over 600 businesses to to ensure inclusion in commercial
the Queensland Department of State
Employment opportunities, and competitiveness in
Development, Infrastructure and providing goods and services.
14 12 Planning forProcurement
business diagnostics and Australia Pacific LNG has adopted
development. The range of services the Queensland Resources and
40
include writing capability statements Energy Sector Code of Practice for
Construction and Operations
(approximately 220 companies), being Local Content.
pre-qualified to supply to the Business
135 Approximately 78 percent of all
(approximately 90 companies),
Community Investmentbuilding
competitiveness through contract expenditure for the Project to date
71 management and theand
tendering was sourced in Australia. The Local
Education Training Content benefits have predominantly
process. In addition, the referrals have
resulted in business matching with remained within Queensland, with
Environmental Concerns
other opportunities within the region. over 57 percent of all Project spend
73
As the Project moves to the operations occurring within the State. The
Queensland spend has provided
and maintenance phase,
Community theand
Health teamSafety
significant benefits within the areas
will continue to build local capability
managed by local Regional Councils
Figure 8.2: Downstream Project Topics through collaboration with State and
of Enquiry in the Surat Basin where the gas
Local governments.
and water facilities are located and in
Topics of Enquiry Australia Pacific LNG’s Local Content Gladstone where the LNG facility is
Policy and associated strategy outlines being constructed.
Employment

Procurement

Construction and Operations


S2 2014
Community Investment

Education and Training

Environmental Concerns

Community Health and Safety

62 Australia Pacific LNG Environmental and Social Report


From left to right, President ConocoPhillips Australia East, Warwick King; BOC South Pacific Managing Director, Colin
Isaac and Qenos Chief Executive Officer and Executive Chairman, Jonathan Clancy at the Qenos facility in Victoria.

Local Supplier of Ethylene Sourced


for Australia Pacific LNG
ConocoPhillips celebrated an innovative achievement for
Australia Pacific LNG operations in 2015, ensuring a reliable
domestic supply of ethylene to the Curtis Island Facility.
Warwick King, President Australia East, said the “We have worked with BOC and Qenos so they have the
collaboration with BOC and Qenos reduced plant reliability ability to supply Australia Pacific LNG with 60% of the
risks by augmenting a traditionally international supply of ethylene we will use at the facility, with the remaining 40%
ethylene with a locally produced refrigerant. purchased from international suppliers in South East Asia.”
“International supply has a 12 week lead time so the ConocoPhillips worked with BOC and Qenos to develop
capability to source ethylene in Australia assists ongoing and install a unique ISO refilling terminal at the Qenos facility
plant reliability,” Mr King said. in Victoria, which will supply required quantities to two
ConocoPhillips-operated LNG facilities - Australia Pacific
“As we use a significant amount of ethylene, a refrigerant
LNG and Darwin LNG.
used in our cooling process, we have historically sourced it
from international markets as local suppliers were unable to
supply it in the quantities we required,” he said.

Australia Pacific LNG Environmental and Social Report 63


8.3 Community Grievance and 8.4 Collaborative
Dispute Resolution Industry Initiatives

Complaint Categories
Australia Pacific LNG, the Operators and Regional Community
contractors record and respond to all Consultative Committees
Land Access and Compensation
1
community complaints from landholders 1 1
and community members. Australia 2
Australia Pacific LNG is involved in
Noise Community Consultative
four Regional
Pacific LNG endeavours to respond
to all complaints within 48 hours and Committees in Maranoa (jointly with
2
investigate in a fair and transparent Santos), Western Downs, Banana Shire
Others
manner in an effort to achieve a timely and Gladstone (jointly with Santos
resolution with the complainant. 3 18 and QGC).
Dust
During this reporting period, Australia The purpose of the committees is to
Pacific LNG registered 32 complaints, foster open and transparent dialogue
Property Damage
showing a continued reduction when 4 between Australia Pacific LNG and the
compared with 57 complaints received community, by providing a mechanism
in the previous period. for information exchange and the
Rehabilitation
collaborative development of solutions
Complaints were predominantly related to social impacts.
to community concerns about land Figure 8.3: Community Complaint Categories Safety
access, noise and dust. (Refer to Members represent a broad cross-
Figure 8.3 and Figure 8.4). At the end Complaint Categories section of the
Traffic andcommunity
Transport in each
of the reporting period, 84 percent region, including representatives from
of all complaints Land Access and Compensation local council, government departments,
1 received had been
1 1
closed out. welfare groups, local chambers of
2 commerce and the general public.
All community complaints for this Noise
reporting period were received by the
2 Community Programs
Upstream Operator, due to the vast Others
area covered by the Upstream Project The Upstream Operator continued
3and by the much larger number18 of its support of the ‘CSG Industry
Dust Schools Program’, a joint road safety
directly affected stakeholders. The
Downstream Operator did not receive initiative with Police and Citizens
any 4community complaints. Property Damage Youth Club (PCYC), equipment
upgrades for Queensland Fire and
S2 2015 Emergency Services (QFES) and the
Rehabilitation ‘I Can Indigenous Student Retention
Program’, which are jointly funded
Safety with other proponents. The Thornhill
Indigenous Training Centre upgrade,
jointly funded by Australia Pacific LNG,
Traffic and Transport
QGC and Gidarjil was completed
during the period.
120
Australia Pacific LNG total community complaints
100
Number of Complaints

80

60

40

20
S2 2015
0
S1 S2 S1 S2 S1 S2 S1 S2
2012 2012 2013 2013 2014 2014 2015 2015

Figure 8.4: Total Number of Complaints by Reporting Period

64 Australia Pacific LNG Environmental and Social Report


8.5 Community Investment

Four social impact management themes underpin Australia Pacific LNG’s community
investment: social infrastructure, partnerships, sponsorships and donations, and
employee-giving and volunteering (Figure 8.5).

COMMUNITY INVESTMENT

SOCIAL PARTNERSHIPS SPONSORSHIPS EMPLOYEE-


INFRASTRUCTURE • Focus on sustainable AND DONATIONS GIVING AND
• Large scale community • Assistance to small VOLUNTEERING
investment in ‘hard’ development scale community • Support for
infrastructure events and projects employees to
• Programs to build volunteer and give
• Informed by capacity and • Support community to local projects/
local and state address social connectedness and organisations
government plans/ impacts build relationships
priorities • Support integration
of workforce into
community

Figure 8.5 Community investment categories

In addition, the following priority areas form the basis of all activity and initiatives
undertaken by Australia Pacific LNG in any of the identified social impact
management themes seen in Figure 8.6.

SKILLS, EDUCATION Supporting community capacity building through local skills development and adding to
AND TRAINING local education opportunities

COMMUNITY SAFETY Supporting safer and healthier communities (including efforts by ambulance, healthcare,
police and emergency services) and public welfare activities
HEALTH AND WELLBEING

SUSTAINABLE Supporting projects that assist to manage population influx in a responsible and
sustainable manner
POPULATION GROWTH
Supporting the protection and enhancement of productivity in our natural resources
NATURAL RESOURCE
including agriculture, land, water and biodiversity
STEWARDSHIP
Figure 8.6 Priority areas for community investment

Australia Pacific LNG Environmental and Social Report 65


To date, approximately AUD$41 million landscaping and fencing, construction
has been committed by Australia Pacific of a shade structure, events platform
LNG to community investment projects and additional car parks. The upgrade
and over AUD$38 million has actually will enhance the park’s function as
been spent (Figure 8.7). Investments an area for remembrance, but also
are targeted at priority areas identified
through the Social Impact Management
Upstream as a place for tourists to stop, and a
meeting point for local families and
Plan consultation process. The Business continued investing in community members.
measures to mitigate impacts and Upstream also continued to deliver the
create community development projects listed in Table 8.1 in order to
opportunities across a range of help mitigate social impacts, ensure
areas, including housing, training, community capacity to sustain Project
community safety and community operations and to share Project value.
capacity building.
Figure 8.8 shows the Upstream
Upstream community investment Operator community investment
expenditure from June to December areas and actual spend values for the
2015 was approximately AUD$1.9 reporting period.
million, taking the total funds expensed
to date to AUD$19.8 million. During A complete list of community
the period, the Project committed investment programs managed by the
funds to an upgrade of the ANZAC Upstream Operator is in Table 8.1.
Park in Miles, including expansion,

40 Community Investment in Million AUD$

35 $185,659
Cumulative APLNG Investment
30
25
Million AUD$

20 $379,296
15
10
5
0 $1,338,253
S1 S2 S1 S2 S1 S2 S1 S2
2012 2012 2013 2013 2014 2014 2015 2015

Figure 8.7 Cumulative Australia Pacific LNG Community Investment Figure 8.8 Upstream Community Investment
by Priority Areas

Sustainable Population Growth


$185,659

Community Safety, Health & Wellbeing

Skills, Education & Training


$379,296

$1,338,253
66 Australia Pacific LNG Environmental and Social Report
Downstream
$2,100
Downstream community investment
expenditure from June to December
2015 was AUD$22,100, with the bulk Skills, Education & Training
of 2015 expenditure occurring at the
start of the calendar year. This takes Community Cohesion
the total funds expended to date to
AUD$18.2 million. The Downstream
Operator committed extra funding to
the Gladstone Chamber of Commerce
‘Boom or Bust’ Gladstone Region
Business Study 2015, which studied
the effects, both actual and anticipated,
of the downturn in the construction $20,000
industry on local Gladstone businesses.
Figure 8.9 shows the Downstream
Operator’s community investment areas
and values for the reporting period. Figure 8.9 Downstream Community Investment
$2,100 by Priority Areas
Table 8.2 displays the complete list
of Community Investment Projects
managed by the Downstream Operator. Skills, Education & Training

Community Cohesion

$20,000

Australia Pacific LNG Environmental and Social Report 67


Table 8.1 Upstream Community Investment Projects

Target Duration of
Region Initiative Description Status Value
Group Investment
Program partner, Horizon Housing,
Lower income
completed the development of nine
Horizon Housing – earners Completed in
Western Downs homes in March 2013, which were Completed $2,050,000
Miles needing 2013
rented and sold at a significant
housing
discount to local residents.

Program partner, Horizon Housing,


Lower income
will develop in Roma up to 18 Under
Horizon Housing – earners
Maranoa affordable dwellings over two construction In progress $1,875,000
Roma needing
phases, also supported by Maranoa 2014-2015
housing
Regional Council.

Lower income
Funded a Housing Officer at Murilla
Housing Case earners Two years
Western Downs Community Centre in Miles and Completed $150,000
Management needing 2011- 2012
Chinchilla Family Support Centre.
housing

Funded an engineer to work for two


years with Western Downs Regional
WDRC Town Council (WDRC) to assist with town General Two years
Western Downs Completed $260,000
Planning Support planning and timely approval of Community 2013-2014
development applications linked to
population growth.

The Project provided financial support


Maranoa to Regional Development Australia
REMPLAN data Local One-off
Western Downs (RDA) to access REMPLAN data Completed $25,000
access Government investment 2013
Banana Shire access to assist Local Government in
forward planning.

Funding to support the Western


Downs Regional Council to increase
Miles Water and the water and sewerage network General
Western Downs 2014-2015 Completed $1,290,000
Sewerage Upgrade capacity in Miles, as part of the Community
Queensland Government Royalties for
the Regions program.

Funding to support the Maranoa


Regional Council to increase capacity
Roma Sewerage General
Maranoa of the sewerage treatment facility, as 2014 - 2015 In progress $1,500,000
Upgrade Community
part of the Queensland Government
Royalties for the Regions program.

Funding for a Housing Officer at


Rent Connect General
Western Downs Murilla Community Centre in Miles and One year 2012 Completed $65,000
Officer Community
Chinchilla Family Support Centre.

A short term initiative to subsidise Lower income


Rent Subsidy - rent for participating properties while earners Two years
Western Downs Completed $72,000
Miles market rents were impacted by needing 2012-2013
high demand. housing

The Roma airport was upgraded


Roma Airport to cater for increased numbers of General One-off
Maranoa Completed $1,000,000
Upgrade travellers to the region and reduce Community investment 2011
road traffic, contributing to safer travel.

Additional funding to support


Roma Airport General
Maranoa the expansion of airport facilities 2014-2015 Completed $500,000
Extension Community
and amenities.

Centralisation of community services


Roma Community from six locations to one to improve General One-off
Maranoa Completed $500,000
Hub community service delivery and Community investment 2014
support to local community.

68 Australia Pacific LNG Environmental and Social Report


Target Duration of
Region Initiative Description Status Value
Group Investment
Queensland Fire & Emergency
Services (QFES) - A partnership with
QFES QGC to address communication One-off
General
Maranoa Communications black spots that emergency services investment In progress $100,000
Community
Enhancement experience between the towns of 2014-2015
Roma, Injune, Taroom, Wandoan
and Mitchell.

Funding contributed to the relocation


Chinchilla
and expansion of the Chinchilla General One-off
Western Downs Kindergarten Completed $400,000
Community Kindergarten, doubling its Community investment 2013
Expansion
capacity for 2014.

The mobile parenting space provides a


Roma Parenting clean and safe room for parenting for General One-off
Maranoa Completed $95,000
Van use at shows and events throughout Community investment 2011
the Maranoa Region.

The project supports small scale, local


community programs focused on skills
Western Downs
Community and education, community cohesion, General Ongoing since
Banana Shire In progress $562,750
Sponsorships sustainable population growth, natural Community 2012
Maranoa
resource stewardship and health
and safety.

This program provides support to


community centres in Miles and
Community Support General Two years
Western Downs Chinchilla to cater for an increased In progress $225,000
Program Community 2013-2015
demand in services during the
Project’s period of peak impact.

Targeting community centres in


One year 2013-
Chinchilla, Miles, Dalby and Tara,
NGO Capacity General 2014 with a one
Western Downs the program aims to build capacity In progress $188,000
Building Program Community year extension
in the areas of governance and
option
funding sustainability.

To provide support to local businesses


to successfully address changes in the Business Two years
Western Downs Miles Ahead Completed $240,000
business environment associated with Community 2013-2014
the CSG industry.

To provide financial support for


Miles Training the fit out of the Trade Training Youth in the One-off
Western Downs Completed $113,000
Centre Centre as part of its workforce and Community investment 2013
training strategies.

An Indigenous school student


retention program run across the
Maranoa I Can Indigenous Indigenous
gas fields in partnership with the Three years Up to
Western Downs schools retention high school In progress
Gold Coast Titans NRL team's 2012-2014 $600,000
Banana Shire program students
Titans 4 Tomorrow community
development arm.

Partnership with QGC, Santos and


Arrow to build local workforce capacity
Maranoa Three years
Education Qld by enhancing student interest in High school Up to
Western Downs 2013-2015 with In progress
Schools Program science, mathematics, engineering students $300,000
Banana Shire annual review
and technology in 41 schools across
the Surat Basin.

QLD Minerals and Energy Academy


Maranoa (QMEA) to educate high school
CSG School High school Three years
Western Downs students in CSG-related engineering Completed $250,000
Program (QMEA) students 2010-2012
Banana Shire opportunities by promoting relevant
subjects within the curriculum.

Australia Pacific LNG Environmental and Social Report 69


Target Duration of
Region Initiative Description Status Value
Group Investment
CSS provides up to $13,500 to
apprentices within the gas fields
Maranoa Apprentices $2,000,000
Community Skills region to help them complete their Ongoing since
Western Downs in the In progress committed to
Scholarship (CSS) apprenticeships locally. Since 2007 2007
Banana Shire community date
more than 150 scholarships have
been awarded.

Identifying females in the Surat Basin


Maranoa willing to work but currently outside
Count Me In Women in the Two phases
Western Downs of the workforce, identifying barriers Completed $200,000
(YWCA) Community 2012-2014
Banana Shire to employment, and providing
targeted training.

Jointly funded website to provide a


Maranoa
Careers in Gas single portal for advertising jobs in the General Three years
Western Downs Completed $35,000
website gas fields region and the CSG/LNG Community 2012-2014
Banana Shire
industry.

This partnership (jointly funded with


Maranoa Wesley St Andrews Australia Pacific LNG Downstream) will
General Two years
Western Downs Research Institute research regional health issues to help In progress $500,000*
Community 2013-2015
Gladstone Partnership shape private and public investment in
health improvement initiatives.

This research partnership with the


GISERA Research
Maranoa CSIRO aims to measure social
Partnership (Social General Three years
Western Downs and environmental impacts and In progress $1,000,000
& Environmental Community 2012-2015
Banana Shire opportunities associated with the
stream)
CSG industry.

Developed in response to local


concerns and delivered in partnership
Maranoa
CARS (Caring with the Royal Automobile Club High School Ongoing since Intake
Western Downs $210,000
About Road Safety) of Queensland (RACQ), the CARS Students 2007 completed
Banana Shire
program equips new drivers with safe
driving strategies.

Co-funded with Banana Shire Council,


Taroom Weed Wash the upgrade of the Taroom weed General Completed
Banana Shire Completed $400,000
Down Facility wash down facility aims to prevent the Community 2013
spread of weeds from vehicles.

Funding to more than double the


capacity of the existing training
Maranoa, facility, delivering camp facilities and
Thornhill Indigenous
Western Downs hospitality training for Indigenous Indigenous
Training Centre 2014 - 2015 In progress $482,000
and Banana trainees. For the first five years, Trainees
Upgrade
Shires 15% of training participation will be
from Western Downs, Maranoa and
Banana Shire.

Funding of the Police Citizens Youth


Club (PCYC) for four driver training
Maranoa, simulators to support education Youth/
Once-off
Western Downs PCYC Driving programs for at-risk drivers identified Indigenous/
Investment in Completed $207,500
and Banana Simulators by Queensland Police Service, General
2014
Shire including youth, Indigenous drivers Community
and participants in the Under the Limit
program.

70 Australia Pacific LNG Environmental and Social Report


Target Duration of
Region Initiative Description Status Value
Group Investment
Partnership to address equipment
Maranoa, needs across the Surat Basin for
Western Downs QFES Equipment Queensland Fire and Emergency General
2014-2015 Completed $663,700
and Banana Partnership Services incorporating the rural and Community
Shire urban fire services and the State
Emergency Service (SES).

Continued partnership with Horizon


Housing Solutions to mitigate ongoing,
Project-related housing impacts
in the Western Downs Region, by Lower income
Affordable
purchasing properties, already on the earners
Western Downs Accommodation – 2015 Completed $2,000,000
market, to rent affordably in Miles. needing
Miles
This fulfils the Integrated Housing and housing
Accommodation Strategy (Q-LNG01-
15-MP-0126) commitments to the
Coordinator-General and community.

This partnership addresses the


limited support available to increase
the capacity of new and existing
Western businesses in Southwest Queensland
Indigenous
Downs, including Aboriginal and Torres Strait
Many Rivers and General 2015-2017 In progress $430,000
Maranoa, Islander businesses. Many Rivers
Community
Toowoomba is a not-for-profit microenterprise
development organisation that
works with marginalised and
disadvantaged Australians.

Western The program delivers civil construction


Downs, Development qualifications for Indigenous Indigenous
2015 In progress $100,000
Maranoa, Academy participants seeking to build on their Community
Toowoomba current plant operation competencies.

Partnership with Council to advance


Economic General
Banana Shire the region’s tourism potential and 2015-2017 In progress $500,000
Development Community
diversify the regional economy.

Partnership with Council to advance


Economic General
Western Downs the region’s tourism potential and 2015-2017 In progress $750,000
Development Community
diversify the regional economy.

This project assists the Thangool


Thangool Airport Airport to alleviate existing capacity General
Banana Shire 2015 In progress $425,487
Upgrade constraints, cater for future growth, Community
and comply with aviation regulations.

Partnership with Western Downs


Regional Council to upgrade the
ANZAC Park ANZAC Park in Miles, to enhance its General
Western Downs 2015-2016 In progress $450,000
Legacy Project function as a memorial, driver reviver Community
facility and family and community
meeting point.

Total
Committed All Projects $22,714,437
by Upstream

* Shared sponsorship with the Downstream Operator for the total of AUD$1,000,000

Australia Pacific LNG Environmental and Social Report 71


Table 8.2 Downstream Community Investment Projects

Target Duration of
Region Initiative Description Status Value
Group Investment
Seed funding for the development
of affordable housing options, Lower income
One-off
Gladstone and funds to the Urban Land earners
Gladstone investment Complete $6,500,000
Affordable Housing Development Authority (ULDA) to needing
2012
fast-track affordable residential land housing
development.

Perpetual trust fund established with


One-off
Gladstone the Public Trustee of Queensland to General
Gladstone investment Completed $5,000,000
Foundation provide social infrastructure to the Community
2012
Gladstone Region.

To offer business mentoring and


Aboriginal and
Many Rivers microenterprise loans to start-up and Three years,
Gladstone Torres Strait Ongoing $1,950,000
Microfinance eligible businesses aimed at ensuring 2012 - 2015
Islanders
economic stability and enrichment.

Rental subsidies are made available


to eligible applicants from the region’s
Police, Fire,
emergency services, medical,
Ambulance,
Rental Assistance educational and welfare sectors to Two years,
Gladstone Healthcare, Completed $1,000,000
Program assist in ensuring the continuity and 2012 - 2014
Education
stability of these services during the
workers
economically challenging period of
population influx.

A program aimed at cultural


enrichment. Music students are able
Queensland School
to work closely with professional Feb 2012 to
Gladstone Symphony students, Ongoing $630,000
musicians to enhance their skills. Dec 2015
Orchestra general public
The entire orchestra performs a free
concert for the Gladstone community.

This partnership (jointly funded with


Wesley St Andrews Australia Pacific LNG Upstream) will
General Two years
Gladstone Research Institute research regional health issues to help In progress $500,000*
Community 2013-2015
Partnership shape private and public investment in
health improvement initiatives.

Gladstone and Queensland Workforce Under-


Skilling Strategies provide pre- represented,
Energy Skills employment skilling programs in areas unemployed, Three years,
Gladstone Completed $300,000
Queensland of identified skills shortages which Indigenous 2012 - 2015
have direct links to the expansion of and migrant
the CSG-LNG industry. groups

Financial support for the marine turtle Environment


Quoin Island Two years,
Gladstone rehabilitation facility located on Quoin and Ongoing $290,000
Sanctuary 2013 - 2015
Island in the Gladstone Harbour. Community

Secondary schools science


Secondary
Port Curtis program enhancing students’ Three years,
Gladstone School Ongoing $218,284
Harbourwatch understanding and practice in marine 2013 -2016
Students
ecological research.

Gladstone Chamber A suite of campaigns and programs


Business Three years,
Gladstone of Commerce and aimed at local small business capacity Ongoing $210,900
General 2013 - 2016
Industry development.

A schools-based trainee / apprentice


program that assists students to
Year 11/12 Three years,
Gladstone EQIP complete Year 12 while also getting Completed $200,000
students 2012 - 2015
started on a trade skills pathway with
local businesses.

72 Australia Pacific LNG Environmental and Social Report


Target Duration of
Region Initiative Description Status Value
Group Investment
Indigenous pre-employment and
vocational training programs chosen in
consultation with industry and tailored Aboriginal and
Energy Skills
Gladstone to suit the local region’s labour market Torres Strait 2014 Completed $150,000
Queensland
demands for traffic control, trades Islanders
assistant / civil construction and other
local jobs.

Support for a range of programs


Youth Inclusion and events aimed at social
Gladstone Young People 2014-2015 Ongoing $145,900
Program inclusion, cultural learning and
community leadership.

Schools-based program raising


Year 11/12
awareness of career opportunities
QMEA (Queensland students,
within the energy sector. Within the Sep 2011 to
Gladstone Mineral and Energy teacher Ongoing $145,500
education curriculum the program Dec 2015
Academy) Professional
promotes the professional pathways
Development
into the industry.

2011-2014 Aboriginal and


Support for 2014 NAIDOC Week
Gladstone NAIDOC Week Torres Strait 2011-2014 Completed $82,500
celebrations in Gladstone.
Celebrations Islander

Sponsorship of a key annual


General
Gladstone Harbour Festival community event held in Gladstone 2011-2015 Ongoing $80,000
Community
celebrating the Harbour.

Sponsorship of a program aiming to


Exodus Tutorial School
Gladstone improve literacy levels of students in 2013 Completed $60,000
Centre Students
years 5 to 7.

Support for the fit-out of new


Volunteer Marine General
Gladstone headquarters of the Gladstone 2013 Completed $54,000
Rescue Community
Volunteer Marine Rescue Service.

This partnership, in collaboration


with a number of Gladstone based
FutureEye Vision partners, supports a program and General
Gladstone 2014-2015 In progress $50,000
2035 committee to develop a common, Community
structured view on what stakeholders
see as Gladstone’s future.

Joint industry initiative supporting


increased Police presence in the
CBD Community Community
Gladstone Gladstone entertainment precinct on 2013 Completed $40,633
Safety Program General
Friday and Saturday nights aimed at
preventing antisocial behaviour.

Sponsorship of a key annual


Botanic to Bridge
community event held in Gladstone General
Gladstone and Healthy Living 2011-2014 Completed $40,385
promoting healthy active lifestyles Community
Expo
through a fun run.

A program of events held throughout


the region aimed at promotion of
Gladstone Year of Cycling Community 2012 Completed $30,000
cycling to achieve a healthy active
lifestyle to the community.

Sponsorship of an annual event aimed


Cultural Diversity General
Gladstone at improved integration of culturally 2012-2013 Complete $29,000
Forum Community
and linguistically diverse people.

Australia Pacific LNG Environmental and Social Report 73


Target Duration of
Region Initiative Description Status Value
Group Investment
Sponsorship of a key annual
Mount Larcom community event held in the
General
Gladstone and District Gladstone region celebrating 2012 Completed $28,000
Community
Show Society the region’s diversity and
agricultural history.

An educational program aimed at


Gladstone Secondary
Gladstone fostering knowledge and commitment 2013 Completed $26,000
EnviroKids Students
to environmental sustainability.

Seed funding to undertake critical


safety upgrades and allow for further General
Gladstone Road to a Dream 2013 Completed $25,000
expansion of existing sporting facilities Community
in Agnes Waters.

Subsidised rental properties leased to


Queensland
QPS subsidised the Queensland Police Service (QPS)
Gladstone Police 2013 Completed $24,620
housing enabling accommodation of new
Service
officers posted to Gladstone.

Sponsorship of a local community


Gladstone
event aimed at improved integration General
Gladstone Multicultural 2012 Completed $22,000
of culturally and linguistically Community
Festival 2012
diverse people.

Purchase of new grandstand


Mount Larcom seating to allow the expansion of the General
Gladstone 2013 Completed $22,000
Showgrounds showground’s capacity in holdings Community
and functionality.

Gladstone
Chamber of
Support of a study into the effects,
Commerce;
both actual and anticipated, of the Business
Gladstone ‘Boom or Bust’ 2015 Completed $20,000
downturn in the construction industry General
Gladstone
on local Gladstone businesses.
Region Business
Study 2015

Collaborative development of
Port Curtis Coral strategies to maximise the potential Aboriginal
Gladstone Coast Traditional of local Aboriginal and Torres Strait and Torres 2013 Completed $19,700
Owners Islander business involvement in the Strait Islander
Operations phase of the Project.

Science Schools Sponsorship to support students


Foundation; The from Gladstone to travel to Brisbane Secondary
Gladstone ConocoPhillips to participate in the science-focused School 2014 Completed $15,335
Science educational program at the University Students
Experience 2015 of Queensland St Lucia campus.

Sponsorship of community group


Red Frogs Young
Gladstone working to reduce instances of drug 2013 Completed $15,000
Gladstone People
use and alcoholism in young people.

Sponsorship for an Environmental


training centre, with facilities in
Gidarjil
Gladstone and Bundaberg that Aboriginal
Development
will deliver environmental, marine, and Torres
Gladstone Corporation; 2014 Completed $15,000
business and management, Strait
Marine Training
education and training programs and Islanders
Centre
coordinate employment opportunities
for participants.

74 Australia Pacific LNG Environmental and Social Report


Target Duration of
Region Initiative Description Status Value
Group Investment

A program of events and initiatives


Central Region
held throughout the region aimed General
Gladstone Road Safety 2014 Completed $12,500
at promotion of road safety and Community
Week
driver awareness.

A program of events and initiatives


Aged
Gladstone Seniors Week held throughout the region celebrating 2013 Completed $11,000
Community
the aged.

Queensland
General
Gladstone Symphony Sponsorship of a community event. 2012 Completed $10,000
Community
Orchestra

Sponsorship of the Coordinated


Community Response for Domestic
CCRDFV Family General
Gladstone and Family Violence (CCRDFV) for a 2013 Completed $10,000
Fun Day Community
community event to raise awareness
of domestic and family violence.

Sponsorship of a community event


Air Your Dirty General
Gladstone to raise awareness of domestic and 2012 Completed $10,000
Laundry Community
family violence.

Sponsorship of the Gladstone


Menagerie Art Regional Art Gallery hosting a touring General
Gladstone 2013 Completed $10,000
Exhibition contemporary Aboriginal sculpture Community
exhibition.

The project supports small-scale local


community programs focused on skills
Community and education, community cohesion, General Ongoing since
Gladstone In progress $163,529
Sponsorships sustainable population growth, natural Community 2012
resource stewardship and health and
safety.

Total
All partnership and
Committed by All Projects $18,146,786
sponsorship programs.
Downstream

* Shared sponsorship with the Upstream Project for the total of AUD$1,000,000

Australia Pacific LNG Environmental and Social Report 75


8.6 Land Access

Australia Pacific LNG acknowledges construction and


operation affects a range of land tenures, and interaction with
a significant number of landholders is required to access land
for the gas fields infrastructure, transmission pipeline, and
LNG facilities.

Australia Pacific LNG negotiates


compensation agreements, and
8.6.1 Compensation 8.6.2 Legacy Cases
purchases or leases land to secure Agreements Legacy cases are those where
access for infrastructure and facilities. access was denied by the landholder,
Activities conducted on the land
include construction, operation and notwithstanding an agreed process
Moderate development is generally six
maintenance of the gas wells, flowlines, being in place, until resolution of
wells or less per landholder property,
ponds, and camps. outstanding matters. At the end of the
including localised infrastructure
reporting period, three legacy cases
(gathering systems, ponds). Major
Sixty six compensation agreements were resolved.
development reflects the installation
were completed during the reporting
of major infrastructure facilities and or
period. These agreements secured
development of greater than six wells
access cumulatively to:
per landholder property.
• 209 development well sites
The location of major facilities in the
gas fields is the primary reason for land • Five exploration and appraisal well
purchases or leases. sites; and
• Six ground water monitoring bores.
Access to land for the LNG Plant
and the main Pipeline Project has At the end of December 2015,
been concluded. compensation agreements were in
place for 977 Phase 1 wells and 623
Sustain Phase wells (including Walloons
Appraisal Program), consisting of 300
wells associated with properties owned
by Australia Pacific LNG.

76 Australia Pacific LNG Environmental and Social Report


8.7 Indigenous People

Australia Pacific LNG is committed to continued engagement


and negotiations with Aboriginal and Torres Strait Islander
peoples to develop and implement approved Cultural Heritage
Management Plans and various Native Title agreements for
the Business.

Two sets of Native Title compensation


negotiations have been undertaken by
8.7.1 Indigenous
Australia Pacific LNG: Engagement
• Right to Negotiate (RTN) - applicable Meetings were held with various
in the gas fields enterprises including Mandandanji
Limited, Muddy Waters, Bigambul
• Indigenous Land Use agreements
peoples, Maranoa Civil, Yukenbulla
(ILUA) - generally used for the
Pty Ltd, and RBY Projects about
main transmission pipelines and
business and employment
LNG facility.
opportunities on the Project. Other
These negotiations have all smaller and individual meetings were
been completed. held to discuss various Native Title,
Cultural Heritage and business and
ILUA negotiations were required to employment opportunities.
establish transmission pipeline routes
and infrastructure, land tenure for gas Many Rivers consultancy has been
processing plants, and grant of sea- introduced to the region following
bed leases. success in the Gladstone area. Field
officers were introduced to Toowoomba
Australia Pacific LNG has negotiated and Roma to cover surrounding
Cultural Heritage Management locales. Many Rivers is a not-for-profit
Plans (CHMPs) with all Native Title consultancy that provides business and
groups within Project operating finance to small, mainly Indigenous,
areas for both Upstream and businesses across Australia.
Downstream components.
During the reporting period there
were 35 engagement sessions with
Indigenous groups (Upstream 30 and
Downstream 5).

Australia Pacific LNG Environmental and Social Report 77


8.7.2 Indigenous
Business
Participation

Downstream
Upstream
Amongst the identified Indigenous Muddy Waters, a wholly-owned The Downstream Operator has
suppliers on the Upstream Operator subsidiary of Mandandanji Pty Ltd, partnered with supply chain
vendor list are: continue to be a preferred supplier partners and contractors to deliver
for weed hygiene wash-down a successful local indigenous
• St George Handy Store (a wholly- services to the Upstream Operator. content strategy as part of our
owned Indigenous business) Muddy Waters also provides these commitment to sustainable
• Roma Security Service (50 services for other CSG proponents operations. Gladstone has very few
percent indigenously owned and and businesses in Chinchilla and the indigenous-owned businesses and
operated, trading for over 20 surrounding areas. there are major capacity-building
years in Roma). constraints in the community. This
The Upstream Operator has is the beginning of a long-term
• RBY Projects (involved in developed a series of training strategic commitment to indigenous
construction and rehabilitation of programs with Corporate Culcha to content and engagement. Results to
leases for Australia Pacific LNG in provide a greater understanding of date include:
the Upstream Project area) Aboriginal and Torres Strait Islander
peoples’ history, cultural behaviours, • 14 contractors have committed to
• CRC Electrical (Electrical indigenous supply, employment
Instrumentation) and practices that may impact
the workplace, customer base and training
• Muddy Waters Weed Hygiene and community. • 16 sub-contracts have been
(weed hygiene wash down awarded in carpentry, cultural
services to the Upstream Ongoing efforts to provide awareness training, cleaning,
Operator and other businesses in opportunities to Traditional gardening, communications,
the Chinchilla area). Owner businesses will continue media, freight transport, art/
with assistance provided to culture
• Corporate Culcha (Indigenous groups to assist with capability
training program providers). and performance. • 22 full time positions have
been awarded for indigenous
Indigenous earthmoving and civil
employment in maintenance,
construction contractor RBY have
operations and maintenance,
continued involvement with the
ropes and non-destructive
Project with 35 percent of their
testing (NDT), security, waste
workforce (45 FTE Indigenous
management, cleaning
employees) involved in construction
and administration
and rehabilitation of leases for
Australia Pacific LNG in the • 11 indigenous traineeships
Upstream area. RBY are pre- have been awarded in
qualified to undertake work for the engineering, ropes and NDT,
Upstream Operator. telecommunications, plant
operations, warehouse and
waste management
• continued to engage a 100
percent indigenous-owned
business, Marion’s Cleaning
Service (MCS). Owned by Byellee
man Michael Eggmolesse, who
is a traditional owner of Curtis
Island, and his partner Marion
Dodd, MCS employs ten local
indigenous people
• ConocoPhillips has indigenous
trainees in warehouse
and operations.

78 Australia Pacific LNG Environmental and Social Report


Thornhill opening day: Left to Right: Bradley Maher and Kevin Alley from QGC; Gidarjil Managing Director Kerry Blackman, QGC’s Joanne
Pafumi; Matthew Ralph and Melanie Grills from the Origin Indigenous Engagement Team and Gladstone Regional Council Deputy Mayor
Cr Matt Burnett.

Funding Boost for Thornhill


Training Centre
Aboriginal and Torres Strait Islander people in central Queensland
will have access to additional training and employment
opportunities, thanks to funding from Australia Pacific LNG for the
upgrade and expansion of the Thornhill Training Centre.
The $1.4 million upgrades were constructed in a Gidarjil Managing Director Kerry Blackman commended
partnership between Australia Pacific LNG and QGC, Australia Pacific LNG and QGC for their ongoing
together with funding contributed by Thornhill’s owners, commitment to helping provide training and development
Gidarjil Development Corporation. The centre expansion opportunities for local Indigenous people.
has delivered new accommodation to house 24 people,
“Thanks to the support we’ve received from both
an industrial camp kitchen, dining and laundry facilities.
companies we are now better placed than ever before
Located south of Gladstone on a 170 hectare grazing to give our people the best possible employment
property, the new facilities enable Gidarjil trainees to opportunities,” Kerry said.
undertake accredited training courses while gaining
firsthand experience living and working in a semi-
remote location.

Australia Pacific LNG Environmental and Social Report 79


8.8 Cultural Heritage

The Aboriginal Cultural Heritage Act


(2003) requires a proponent to comply
8.8.1 Cultural Heritage 8.8.3 Chance Findings
with the Duty of Care. This can be Management Plans The process for protection, preservation
achieved through agreements with the and management of chance findings
CHMPs set out processes and plans to
Traditional Owner groups. These groups is detailed in each CHMP. A chance
manage and protect cultural heritage
were identified and Australia Pacific finding occurs when a potential cultural
across the Business. These plans
LNG has negotiated Cultural Heritage heritage site or artefact is discovered or
include a communication protocol,
Management Plans (CHMPs) with unearthed during construction activity.
management structure and survey
relevant Traditional Owner groups. Any person who locates an artifact
process to ensure cultural heritage is
protected. Nine CHMPs have been or object must comply with Business
Cultural heritage remains a priority
negotiated with all Traditional Owner policies developed to conform to the
on active worksites and identification
groups. All of these are in place CHMPs and Duty of Care guidelines
awareness training based on
and are being implemented across under the Queensland Aboriginal
information provided by Traditional
the Business. Cultural Heritage Act (2003).
Owner groups within the development
area are a key component of site On one occasion, the scouting team
orientation throughout the Project sites.
8.8.2 Pre-Construction found possible human remains and
Personnel undertaking work Surveys stopped the job until the police were
called and established the authenticity
causing ground disturbance such
Each CHMP states that a full of the bones. Traditional Owners
as excavations, road maintenance,
archaeological survey is required for confirmed the bones were of Aboriginal
or clear and grade activities must
major infrastructure works and scouts origin and traditionally interred.
complete scientific cultural heritage
identification training. This full-day accompanied by Traditional Owners
A site containing rock art has also been
course is provided by the archaeologist, are required for smaller infrastructure
located and shown to the Landholder
and covers practical identification of including flow lines, lease pads, and
Relations Advisor by a landholder. This
artifacts and other possible culturally access tracks.
site is not directly affected by Australia
significant items, including scar trees Pacific LNG activities and has yet to be
During the reporting period, 947 days
and ceremonial places. It also covers inspected by the Traditional Owners.
of scouting and construction monitoring
the legislative and social requirements
were undertaken with 37 Traditional
for protection and management of The Business continued to engage with
Owners present.
cultural heritage. Traditional Owners to survey for cultural
heritage artefacts on all Australia Pacific
LNG sites.

80 Australia Pacific LNG Environmental and Social Report


8.9 Key Performance
Indicators

Number of social Indigenous Peoples


behaviour incidents*
Number of Indigenous groups providing
Upstream 0 goods and services to the Project

Downstream 0 Upstream 6

Number of community Downstream 1


complaints Cultural Heritage
Upstream 32 Number of non-
Downstream 0 compliance incidents
0
with Cultural Heritage
Percent of community Management Plans
complaints closed out within the Number of chance
reporting period findings (cultural
2
heritage objects) in
Upstream 84%
the reporting period
Downstream N/A
Financial contributions
Number of biosecurity incidents supporting the Community
Investment strategy for the
Upstream 0 reporting period
Downstream 0 Upstream AUD$1,903,208

Access to Land Downstream AUD$22,100

Number of legacy
cases resolved in 3
the period
Number of landholder
18
complaints**
Number of ongoing
0
litigation cases
Number of cases
mediated in the 0
reporting period

*Social behaviour incidents refers to workforce behaviour complaints as detailed in Section 8.3.

**Complaints related to land access and compensation as detailed in Section 8.3

Australia Pacific LNG Environmental and Social Report 81


Appendix 1 – Abbreviations and Glossary of Terms
9.1 Abbreviations
APPEA Australian Petroleum Production and HPI High Potential Incident – A near miss safety
Exploration Association incident with a likely potential consequence
of a fatality
ADWG Australian Drinking Water Guideline
IESC Independent Environment and Social
CAS Community Advisory Service (Gladstone) Consultant
IFC International Finance Corporation
CAR Corrective Action Request
ILUA Indigenous Land Use Agreement
CARS Origin ‘Caring About Road Safety’ Program
LNG Liquefied Natural Gas
CHMP Cultural Heritage Management Plan
LTC Lost Time Case
CG Queensland Coordinator General
Ml Megalitres
CO2 Carbon Dioxide
MTC Medical Treatment Case
CSG Coal Seam Gas
Mtpa Million metric tonnes per year
CSIRO Commonwealth Scientific and Industrial
Research Organisation NGO Non-Government Organisation
DAF Queensland Department of Agriculture and
Fisheries NOx Nitrogen Oxides

DIDO Drive-in-drive-out work regime OSBL Outside Battery Limits

EA Environmental Authority OCIS Origin Collective Intelligence System

EHP Queensland Department of Environment Origin Origin Energy Limited


and Heritage Protection
EIS Environmental Impact Statement PIN Penalty Infringement Notice

EMP Environmental Management Plan QCLNG Queensland Curtis LNG Project

EPC Engineering, Procurement and RCCC Regional Community Consultative


Construction Committee

ESMP Environmental and Social Management RFSU Ready for Start-Up


Plan
RTN Right to Negotiate
EVNT Endangered, Vulnerable and Near
Threatened Species RWC Restricted Work Case
FAC First Aid Case
S1 Semester One
FIFO Fly-in-fly-out work regime
S2 Semester Two
FTE Full Time Equivalent
SD Sustainable Development
GAWB Gladstone Area Water Board
SIMP Social Impact Management Plan
GISERA Gas Industry Social and Environmental
Research Alliance STARRT Safety Task Analysis and Risk
Reduction Talk
GLDMG Gladstone Local Disaster Management
Group TRIFR Total Recordable Injury Frequency Rate.
The ratio of recordable injuries or illnesses
GLNG Gladstone LNG Project per million hours worked averaged over a
12-month period
GPC Gladstone Ports Corporation
UWIR Underground Water Impact Report
GQAL Good Quality Agricultural Land
YTD Year to Date
GRC Gladstone Regional Council
WTF Water Treatment Facility
HDD Horizontal Directional Drilling

HSE Health, Safety and Environment

HSSE Health, Safety, Security and Environment

82 Australia Pacific LNG Environmental and Social Report


9.2 Terms
Australia Pacific LNG Australia Pacific LNG Pty Limited ‘Make Good’ If an existing water bore is impacted by
Agreement a CSG operation, the responsible CSG
Australia Pacific LNG Means, at any time, any of the Gas company must undertake reparation
Pty Limited Production System and Pipeline then- measures to restore the bore’s capacity
wholly-owned or operated by an Australia to supply water, or provide the bore
Pacific LNG Entity. owner with an alternative water supply or
ATLAS Customised proprietary compliance monetary compensation.
and tracking database based on an Project The ‘Project’ comprises the development,
ATLAS Borealis system of information construction, operation, maintenance,
management. and ownership of Australia Pacific LNG’s
Bechtel Bechtel Corporation, the EPC Contractor CSG fields, the construction of a gas
of the LNG Plant and the Shared Facilities transmission pipeline(s), together with
(other than the LNG storage tanks). the construction of LNG facilities and
associated port infrastructure to export
COP Australia ConocoPhillips Australia Pty Ltd, a wholly- LNG to international markets.
owned subsidiary of ConocoPhillips, and
the Downstream Operator. QCLNG Queensland Curtis LNG Project

Downstream The operating agreement between Queensland ‘Queensland Environmental Authority’


Operating Agreement Australia Pacific LNG and the Environmental means the level 1 environmental authority
Downstream Operator, pursuant to which Authority (chapter 5A activities) permit granted
the Downstream Operator manages to Australia Pacific LNG under the
the construction of, and operates and Environmental Protection Act 1994 (Qld).
maintains, the LNG Plant and the Shared
Recordable Injuries Injuries or illnesses of work-related nature
Facilities on behalf of the Borrower and
involving medical treatment cases,
the Shared Facilities Provider.
restricted work cases or lost time cases.
Downstream ConocoPhillips Australia Pty Ltd
Shared Facilities The power generation facilities, utilities,
Operator
storage tanks, loading lines and
Downstream Project The design, construction, testing, arms, jetty, docks, buildings, helipads,
commissioning and operation of the LNG communications facilities, land and
Plant and Shared Facilities. water rights, and other facilities and
infrastructure to be developed on Curtis
EPBC Approval ‘EPBC Approval’ means the approval
Island to be used initially by the LNG
granted to Australia Pacific LNG
Plant but in the future may be used
under the Environment Protection and
in connection with LNG processing
Biodiversity Conservation Act 1999 (Cth)
trains developed by one or more other
dated 21 February 2011 and bearing
developers.
the title ‘Australia Pacific LNG Project -
Development of a LNG Plant and Ancillary Sinopec China Petroleum & Chemical Corporation
Onshore and Marine Facilities on Curtis
Island - EPBC 2009/4977’ . Train 1 The first LNG train to be constructed
under the EPC Contract.
Gas Production a. Gas Production System means all
System wells, valves, compressors, vessels, Train 2 The second LNG train to be constructed
meters, equipment, pipelines, facilities, under the EPC Contract.
installations and apparatus which, in TRIFR Total Recordable Injury Frequency Rate.
the judgment of the Seller, are from The ratio of recordable injuries or illnesses
time to time required to: per million hours worked averaged over a
(a) produce and gather Natural Gas; 12-month period.

Upstream Project The design, construction, testing,


(b) separate water and other constituents
commissioning, and operation of CSG
from that Natural Gas for the purpose of
fields, a high pressure gas pipeline
producing Gas; or
network, and transmission pipelines for
(c) compress and deliver Gas to the supply of gas to the LNG Plant.
Delivery Points.
Upstream Operator Origin Energy Limited.
LNG Plant The gas liquefaction facility to be built by
the Downstream Operator and certain
ancillary facilities (but not including the
Shared Facilities).

LNG Facilities The LNG Plant plus Shared Facilities.

Australia Pacific LNG Environmental and Social Report 83


Curtis Island LNG Facility
www.aplng.com.au

You might also like