Professional Documents
Culture Documents
APLNG Enviro Social Report July To Dec 2015 FINAL
APLNG Enviro Social Report July To Dec 2015 FINAL
Environmental
and Social Report
he Australia
July to December 2015
Pacific LNG
brand.
Environmental and Social was first produced from Train 1 of the approximately 67 percent of all areas
Performance Downstream facility on 9 December disturbed to date.
2015, and the first shipment of LNG
The shareholders of Australia Pacific An additional direct offset on the
departed the Australia Pacific LNG
LNG aim to develop the Business in Colamba property was included in the
facility on Curtis Island on 9 January
a sustainable manner by identifying portifolio, located north-east of Miles.
2016. A total of three produced cargoes
and assessing potential impacts, and The Colamba offset will compensate
were shipped in January to customers
introducing sustainable practices for Project impacts on Brigalow, fauna
including Sinopec, pursuant to the
and solutions to manage them. This habitat and wetland values not yet
Sinopec SPA.
approach, detailed in the Project’s acquitted by existing offsets.
Environmental Impact Statement,
Safety, Health, and The Dukes Plain Offset and
reflects the existing practices of the
Environmental Management Rehabilitation Management Plan, was
Project’s joint venture partners, Origin
The Business health and safety goal approved by the Australian Government
Energy, ConocoPhillips and Sinopec,
remains at zero injuries across all Department of the Environment
and is integral to developing the
activities. During this period, Australia in October 2015. On the ground
Business in a transparent, accountable
Pacific LNG reported 24 recordable management activities continued to be
and sustainable manner.
injuries, representing a solid downward implemented. Implementation of the
This, the eighth Environmental and Social trend in the Total Recordable Injury Inverness offset site also continued with
Report for the Project, covers the period Frequency Rate (TRIFR), which Cycad seedlings planted.
between July and December 2015, improved by 19 percent from 3.1 in Work continued in the Monte Christo
and provides updates on the Project’s June to 2.5 at 31 December 2015. offset site over the past six months
progress, safety and environmental
The responsibility of managing on the transfer of the remaining
management, and benefits to local and
environmental impact is taken seriously. freehold allotments to the Queensland
regional communities.
Strict government environmental Government for inclusion in the
Construction Overview regulations result in the thorough and Queensland Conservation Estate.
As at 31 December 2015 the Business transparent management of water
employed 5,793 full-time equivalent (produced, storm and waste), emissions
(FTE). Upstream employed 2,766 FTEs (waste, greenhouse gases and dust),
including Operations and Project delivery land, and biodiversity.
while 2,987 FTEs were engaged in Our environmental incident frequency
Downstream Operations and Project rate continues to decrease and as
delivery. The Australia Pacific LNG at 31 December it stood at 1.35, an
Corporate Office employed 40 FTEs. improvement of 10 percent compared
The Upstream Project was 99 percent with the previous reporting period.
complete at 31 December 2015. 1,272 There were 11 environmental incidents
development wells had been drilled reported to the Regulatory Authorities,
and 1,090 wells commissioned. All key 10 classified as minor and one incident
facilities are now commissioned and classified as moderate.
the Upstream Project is complete with Biodiversity Conservation
the only activities remaining relating to
contract ‘close out’. The rehabilitation effort continued with
901 ha being reinstated in the reporting
The Downstream Project was 96 percent period, bringing the total to 6,258
complete at 31 December 2015. LNG ha of reinstated land, representing
Size Two trains, each with a nameplate production capacity of 4.5 Mtpa
Timing LNG was first produced from Train 1 of the Downstream facility in
December 2015. The first shipment of LNG departed the Australia
Pacific LNG facility on Curtis Island in January 2016.
Upstream 99%
Downstream 96%
Origin manages the construction and operation of The LNG facilities comprise two gas processing
the Upstream Project, including the development trains, two LNG storage tanks, and standard
of CSG resources and delivery of gas to feed the infrastructure services, including power, water,
LNG plant. The Upstream Project involves drilling telecommunications, and sewage disposal.
and completing CSG wells, construction of field gas
Mainland support and temporary construction
and water gathering networks, gas processing and
facilities are located in the Gladstone area. The LNG
water treatment facilities, electricity infrastructure,
plant is situated on Curtis Island, 11 kilometres
and gas transmission pipeline infrastructure.
northwest of the city of Gladstone, Queensland.
The CSG fields comprise wells and associated
surface facilities, gas gathering and water gathering
pipeline systems, seven gas processing facilities,
two associated water treatment facilities, water
storage ponds, and treated water and brine
disposal facilities.
ConocoPhillips manages the construction and
operation of the LNG facilities on Curtis Island.
Bechtel is the engineering, procurement and
construction contractor for the LNG plant and much
of the related infrastructure.
Upstream
The Upstream Project was 99 percent CSG production increased steadily
complete as at 31 December 2015. during the reporting period with the
1,272 development wells had been arrival of gas at the LNG plant and first
drilled and 1,090 wells commissioned. LNG production in December. Total
All key facilities are now commissioned production increased from 474 TJ/day
and the Upstream Project is complete in July to over 1,000 TJ/day at the end
with the only activities remaining of December.
relating to contract ‘close out’.
2.2.1 Sustain Phase
2.1.1 Upstream Phase 1 Project December marked a major milestone
The Phase 1 Project is largely complete with commissioning of the first
and the demobilisation organisation horizontal well in Spring Gully. Sustain
concluded through December. Going phase drilling was 25 wells ahead of
forward Phase 1 will be closed target at the end of CY15 and 21 wells
out through a centralised delivery were commissioned in December.
organisation. The contracts closeout
exercise is well underway with 400
of the 700 contracts now closed
and on target to complete in March
2016. Pipelines remediation work is
scheduled to start early in CY16.
2.1.2 Facilities
During December, Australia Pacific
LNG exceeded operated asset target
production and is now producing at
a rate which, combined with volumes
provided from non-operated assets, is
more than sufficient to supply domestic
contracts and feed gas for one
LNG Train.
2.1.3 Pipelines
All Australia Pacific LNG pipeline and
pipeline compression assets are now
commissioned, with 98 percent of all
new pipelines easements registered.
Prior to full LNG Train 1 operation, the
Woleebee and Condabri laterals were
run at higher pressure than the mainline
to supply domestic and LNG markets.
Downstream
The Downstream Project was 96 LNG was first produced from Train 1
percent complete at 31 December on 9 December 2015, and the first
2015. Overall construction and shipment of LNG departed the LNG
commissioning on Curtis Island facility on 9 January 2016. A total of
was 93.1 percent complete. Train three produced cargoes were shipped
1 and outside battery limits (OSBL) to customers in January.
construction was 99.4 percent
complete. Pre-commissioning and
commissioning was 68 percent
complete. Out of the total 225
systems in Train 1 and OSBL, 220
of these systems have reached
Mechanical Completion.
Train 2 construction was 73.1
percent complete. Train 2 electrical
and instrumentation works were
constrained by resources but ramped
up slowly during December.
Curtis Island
Australia site LNG
Pacific – December
liquefied 2013 gas facility on Curtis Island commenced commercial operation in December 2015.
natural
KEY STAKEHOLDERS
HSE AND SD
MS STANDARD
APLNG Environment and Social Management Plan (ESMP) ELEMENTS
Policy
STANDARDS AND ESMP SUB-PLANS HSE Obligations
GUIDELINES
Planning, Objectives and Targets
Parent Company Labour and Working Pollution Prevention
Policies and Systems Conditions and Abatement Hazard and Risk Management
Regulatory Requirements Community Health Land Acquisition and Training and Competency
Safety and Security Involuntary Resettlement Communication
IFC Environmental and
Social Standards Biodiversity Sustainable Resource HSE Programs and Procedures
Conservation Management
Contractor and Supplier
Equator Principles and
Indigenous Peoples Cultural Heritage Management
US Ex-Im Policies
Emergency Preparedness
and Response
Incident Management, Corrective
and Preventative Action
Actions
Monitoring and Measurement
Operator Management Plans Assurance
Contractor Management Plans Management Review
Figure 3.1 Australia Pacific LNG Environmental and Social Management Plan
The Australia Pacific LNG HSE & During this reporting period,
Australia Pacific LNG initiated an
3.4.1
SD Assurance Plan describes the
activities that the Australia Pacific audit of implementation of corrective Independent
LNG Corporate Office undertakes actions by the Upstream and Environmental and
to fulfil its assurance, oversight, and Downstream Operators.
Social Consultant
communication roles. This is done on
behalf of Shareholders for Operator
The Upstream and Downstream Review
Operators have developed and
activities and performance in the areas implemented HSE assurance plans, The Independent Environmental and
associated with HSE & SD. These procedures and programs to verify Social Consultant (IESC), Lummus
include targeted Operator Health, that controls are developed to mitigate Consultants International, conducted
Safety and Environmental Management health, safety, environmental and a review of various components of
Systems (HSEMS) implementation and social impacts. Assurance activities the Business in September 2015. The
compliance audits, pre-construction are planned in consideration of reviewing team travelled to the LNG
and operational readiness reviews, construction and operational activities Facility construction site on Curtis
environmental and social condition with the greatest HSE and SD risk Island, and inspected key aspects of
compliance audits, and data along with other factors including construction of the two LNG trains,
verification of the compliance system outcomes of previous audits, results of the LNG tanks, and the administration
(Atlas). Australia Pacific LNG leverages incident investigation and independent and plant control buildings. With
the Operator’s own assurance activities third-party audits and regulator- respect to the Upstream Operator,
as much as possible through: initiated audits. the review included an inspection of
• participating in an observer capacity reinstatement of one of the Campsites
in identified Operator HSE and SD (Camp 4) and the Narrows section of
audits, workshops and reviews the pipeline corridor to verify the state of
reinstatement and close out that item.
• performing a quality assurance Lummus Consultants noted, “As always,
review of identified Operator-initiated the dedication and professionalism is
HSE and SD audits, workshops clear and for environmental and social
and reviews. aspects the teams continue to deliver
All Australia Pacific LNG-initiated best practice with performance excellent
HSE and SD audits are undertaken across the Project”.
using a methodology consistent Overall, Lummus Consultants confirmed
with the requirements of ISO that principal environmental approvals
19011:2003 Guidelines for Quality and planning permits remain valid,
and/or Environmental Management specific to the Australia Pacific LNG
Systems Auditing. Project, and that conditions of approval
are being appropriately tracked,
implemented and measured.
Lummus Consultant Jeff Bleathman and Australia Pacific LNG staff Michael Stahl, Candice Shelley and Marianne
Gibbons at the Narrows.
3.5.1
Non-Conformances Upstream
Protection of the environment The Upstream Operator received no
Environmental and social milestones
continues to be a priority for Australia warning notices or fines. No Penalty
are part of the Project Execution
Pacific LNG, which has a corporate Infringement Notices (PINs) or fines
Plans for development and operation
goal of maintaining zero regulatory were imposed between 1 July and
of the Upstream and Downstream
shutdowns and finable incidents. 31 December 2015. The Upstream
components. All environmental and
Operator had two instances of non-
social milestones related to the
A non-conformance is a situation compliance with waste disposal
Project as outlined in the ESMP have
inconsistent with conditions of certificates. A further 16 instances
been completed.
approval or formal commitments of non-conformance related to late
made by Australia Pacific LNG. Non- submissions of reports, updates
conformances are recorded during to management plans or failure to
audits or inspections conducted by conduct monitoring in accordance with
Regulators, Shareholders, Australia the Environmental Authority (EA), were
Pacific LNG, Operators or Contractors. reported and all have been closed out.
Downstream
The Downstream Operator received no
warning notices from EHP.
Upstream Downstream
Individual tasks are managed through Environmental risks have been Safety management tools such
the use of procedures, Job Hazard identified through a series of as Safety Task Analysis and Risk
Analysis and/or Permit to Work. workshops that align with the LNG Risk Reduction Talk (STARRT) cards,
Management Framework. Job Hazard Analysis (JHA), Job
Regular monthly reporting records Safety Analysis (JSA), Job Safety
hazard management activities across Level 1 Environmental Risk Registers and Environmental Analysis (JSEA),
the Upstream Operator sites and exist for the Upstream Operator at a manager walk-throughs, and tool
facilities, listed in Table 4.1. Business Unit level. box talks are used on the LNG facility
construction site to build a strong
safety culture and positive work habits.
Hazard management type Totals Additionally, leading and lagging
safety indicators are tracked and
Manager site visits 823 used to promote an ongoing
Injuries (no treatment cases and higher) 104 safety focus, and celebrated when
milestones are achieved. Table 4.2
Near Misses 151
lists activities conducted by Bechtel
Life Saving Rule breaches 29 and its subcontractors to help improve
awareness and manage hazards
Emergency Response Drills 947
during the reporting period.
Safety Inspections 10,719
Drug and alcohol tests conducted 99,756
Training conducted 1,214
9
Consolidated APLNG
8
7 Downstream Operator
6 Upstream Operator
5
4
3
2
1
0
TRIFR (No. of injuries per million hours worked)
9
S1 S2 S1 S2 S1 S2 S1 S2 Consolidated APLNG
8 2012 2012 2013 2013 2014 2014 2015 2015
7 Consolidated APLNG Downstream Operator
6 Consolidated APLNG Downstream Operator Upstream Operator
5
Downstream Operator Upstream Operator
4 Figure 4.2: Australia Pacific LNG Consolidated Safety Performance by Reporting Period
3 Upstream Operator
2
1
0
S1 S2 S1 S2 S1 S2 S1 S2
2012 2012 2013 2013 2014 2014 2015 2015
S2 S1 S2 S1 S2
2013 2014 2014 2015 2015
S2
2015
Injuries
60 4
Injuries
and 4.4. 4 RWC
50 RWC
50
Recordable
Hands continue to be the most 3
Recordable
40 3 MTC
commonly injured body part (50 40 MTC
percent of all injuries). However, the 30 2
30 2 TRIFR (rolling 12 m
percentage of hand injuries reduced 7 20 TRIFR (rolling 12 mo
through the first half of 2015 (by Injury
20 Category
1
7 10 1
approximately 33 percent), but rose 6 Injury
10 Category
again in the second half of the year. 6 0 Fatality 0
100 0 7 0
Both Operators have taken measures Fatality
S1
S1
S2
Injury S1
S2 Category
S1
S2
S2
S1
S1
S2
S2
S1
S1
S2
S2
5 2012 2012 2013 2013 2014 2014 2015 2015
90 over the past year to address 2012
LTC 2012 2013 2013 2014 2014 2015 2015
100 hand injuries and protecting hands 5 6
LTC 7
80 Fatality Injury Category
Figure 4.3 Recordable Injuries by Reporting Period
90 continues to be a daily topic at pre- 4
70 100
start meetings. 4
7 5RWC 6 7
RWC LTC Fatality Injury Category
80 Injury Category
60 90 3
3 4MTC 5 6
70 6 MTC RWC LTC Fatality
50 80 Fatality
60 22
Recordable Injuries
70 3 4 months) 5
40 5 TRIFR (rolling 12
TRIFR LTC
LTC (rolling 12 months)
MTC RWC
50
30 60 11
Recordable Injuries
4 2 3 4
40 RWC TRIFR (rolling 12 months)
MTC RWC
20 50
30 003 1 2 3
10 40
S2 S1 S1 S2 S2 S1 S1 S2S2 S1
S1 S2
S2 MTC TRIFR (rolling 12MTC
months)
20
2012201320132013
2013 2014
201430 2014
2014 2015
2015 2015
2015
0 0 0 1 Fatalities2
2
10 TRIFR (rolling 12 months) TRIFR (rolling 12 months)
S1 S2 S1 20 S2 S1 S2 S1 S2
2012 2012 2013 2013 2014 2014 2015 2015 4
0 1 0 1
LTC Injuries
10
S1 S2 S1 S2 S1 S2 S1 S2
2012 2012
0 2013 2013 2014 2014 2015 20154 0 Injuries
0 RWC
S2 S1 S2 S1 S1
S2 S2
S1 S1
S2 S2 S1 S2 S1 S2
2012 2013 2013 2014 2012
2014 2012
2015 2013
2015 2013 2014 2014 2015
16 2015
MTC Injuries
280
FAC Injuries
300
Downstream
250
Upstream
No. of Indigenous Employees
200
150
100
50
0
S1 S2 S1 S2 S1 S2 S1 S2
2012 2012 2013 2013 2014 2014 2015 2015
Downstream Upstream
300,000
Upstream Operations Scope 2
200,000
800,000 Upstream Operations Scope 1
Downstream Operations Scope 2
100,000
700,000
0 Downstream Operations Scope 1
600,000
S1 S2 S1 S2 S1 S2 S1 S2
2012 2012 2013 2013 2014 2014 2015 2015
Downstream Operations Scope 2 Downstream Construction
Tonnes of C02 -eq
500,000
300,000
Downstream Operations Scope 2 Downstream Construction Upstream Operations Scope 2
200,000
Downstream Operations Scope 1 Upstream Construction Upstream Operations Scope 1
100,000
S2 S1 S2 S1 S2 S1 S2
012 2013 2013 2014 2014
Upstream 2015Scope
Operations 2015
1 Australia Pacific LNG Environmental and Social Report 31
Upstream Downstream 5.1.2 Fugitive Emissions
The GHG emission profile has made The use of diesel fuel related to plant CSG fugitive emissions come from
an expected but notable shift from construction, power generation, infrastructure, and minor venting of
emissions related to construction and and vehicle and vessel movements methane where it is not practicable
commissioning of facilities, to emissions remained a contributor to greenhouse to flare.
related to an increase in production. gas emissions generated on site.
The operation and maintenance However, with the commencement of
regime of the commissioned plant will commissioning, coal seam gas used for
be continually optimised to minimise power generation and flaring activities
the possibility of any long term also contributed to total emissions
deterioration in the emissions intensity on site.
performance. In the immediate term,
we also expect to see reductions in
flaring as unplanned interruptions are
reduced, as the operations teams
gain experience with the new plant.
Additional opportunities to reduce
emissions and introduce improvements
in energy efficiency will also continue to
be considered.
5.3.1 Unregulated
Wastes
Waste
Wastecategories
categoriesinintonnes and
tonnes disposal
and methods
disposal methods
minium Cans,
um Cans, Plastic
Plastic
s and Cardboard -3 General
General
General Comingled
Co-mingled
ComingledWaste
waste →- Landfill
Waste Landfill
- Landfill
nd Cardboard -3
Metals and Scrap Metals - Recycle
61 58 Metals
Metals andand Scrap
Scrap Metals
Metals - Recycle
→ Recycle
70 61 58
70
Construction Waste - Landfill
668 Construction
Construction Waste
Waste
S2 - Landfill
→ Landfill
2015
668
Paper, Wood and Textiles - Recycle
Paper, Wood
Paper, andand
Wood Textiles → Recycle
Textiles - Recycle
Comingled Waste - Recycle
Co-mingled
Comingled waste
Waste→ Recycle
- Recycle
1,179 Poly Pipe - Recycle
245
1,179 Poly
Poly Pipe
Pipe - Recycle
→ Recycle
245
Aluminium Cans, Plastic Bottles and Carboard - Recycle
Aluminium
Aluminium Cans,
Cans, Plastic
Plastic Bottles
Bottles and Carboard
and Cardboard - Recycle
→ Recycle
Figure 5.4 Upstream Operator Regulated Liquid Figure 5.5 Upstream Operator Regulated Solid
5.4 Upstream Operator Regulated Liquid Wastes Volumes S2 2015 Separator Solids
Wastes Volume and Disposal Methods Wastes Tonnage and Disposal Methods
and Disposal Methods
Residual Chemicals - Recyc
0.010.01 Waste categories
Waste categories inintonnes
tonnesand
and
micalsResidual
– 7 Chemicals – 7 Waste Categories (in kilolitres) anddisposal
disposal method disposal method
ng Oil – 2 Cooking Oil – 2 11 Waste Categories (in kilolitres) and method disposal method
Cooking Oil - Recycle
Cooking Oil – 2 11 15
ng Oil – 2 15
Drilling Muds Treated Wood -→Landfill
Treated Wood Landfill
Drilling
2 Muds- →
Recycle
Recycle Treated Paint Related Wastes - Lan
Wood - Landfill
78 35
Drilling
2 Muds - Recycle
Interceptor Pond 0.5
78 35 Interceptor PondWater- Recyle
Water0.5
→ Recycle Oily Rags/Oily Filters-
Oily Rags/Oily Filters → Landfill
Landfill
Interceptor Pond Water- Recyle Oily Rags/Oily Filters- Landfill
66 Septic Waste
77 Septic WasteUntreated
Untreated- Recycling
→ Recycle
Batteries (Palletised)
(Palletised)-→ Recycle
Recycle
66 69
SepticWashdown
Waste Untreated Batteries (Palletised) - Recycle
415
77 Washdown Sludge →- Recycle
Recycling
Sludge- Recyle
786 69 15 Washdown 20
Printer
Printer Cartridges Recycle
Cartridges -→Recycle
Sludge
Completion
Completion - Recyle
Fluids
Fluids → Recycle
- Recycle Printer Cartridges - Recycle
852 15 20
Septic Waste
Septic WasteTreated
Treated- Recycle
→ Recycle Fluro
Fluro Lamps
Lamps → Recycle
- Recycle
Completion Fluids - Recycle Fluro Lamps - Recycle
1,183
Oily
Oily Water (Bunds)- Recycle
Water (Bunds) → Recycle
Septic Waste Treated - Recycle
2,520 Oily
Oily Filters
Filters -→ Landfill
Landfill
14,414
Oily Water (Bunds)
Wet Oil - Recycle
→ Recycle
Wet Oil - Recycle
Grease
Oily Filters
GreaseS2- 2015
Trap-→
Landfill
Trap Recycle
Recycle
S2 2015
6,433 Oil
Oil (Dry) Recycle
(Dry) -→Recycle
14,414 Wet Oil - Recycle
Waste Oils-→
Waste Oils Recycle
Recycle
Grease Trap - Recycle
Coolants -→Recycle
Coolants Recycle
Oil (Dry) - Recycle
4 Upstream Operator Regulated Liquid Wastes Volumes
Separator Solids → Recycle
Separator Solids
d Disposal Methods WasteResidual
Oils - Recycle
Residual Chemicals- Recycle
Chemicals → Recycle
Coolants - Recycle
Cooking
Cooking Oil-→
Oil Recycle
Recycle
Paint
Paint Related Wastes- Landfill
Related Wastes → Landfill
Separator Solids
or Regulated Liquid Wastes Volumes
s
Residual Chemicals - Recycle
Australia Pacific LNG Environmental and Social Report 37
Cooking Oil - Recycle
Waste categ
Waste categories in kilolitres and disposal methods
Environmental Incidents
Summary
Our environmental incident frequency The level of risk associated with each
rate continues to decrease and currently incident was rated using a matrix that
stands at 1.35, an improvement of included safety, health, environmental,
10 percent over the previous regulatory, and legal and public
reporting period. considerations. Ten incidents were
classified as Severity 1 or minor, the
Our most common environmental
lowest category (causing minor local
reportable incident is an uncontrolled
impacts and no lasting effects). One
release to the environment including
incident was classified as Severity
hydrocarbon spills and sediment
2 or moderate (short term impacts
releases. Hydrocarbon spills are typically
to habitat, species or ecosystems).
very small in nature and sediment
This occurred when the unauthorised
releases are usually the result of a
clearing of 317 m2 occurred outside the
significant rain event that is above
approved disturbance limits adjacent to
the design criteria for erosion control
the lease pad.
devices installed.
A pre-clearance ecology survey of the
There were 11 reportable environmental
site confirms that the cleared area did
incidents incurred in the period involving
not comprise of remnant vegetation and
the following categories:
contained no regrowth of Endangered
• Hydrocarbon spills Regional Ecosystems. Refer to Figure
5.8 and Figure 5.9.
• Water quality exceedances
All incidents were recorded and
• Produced CSG water discharge
investigated to determine and
• Unauthorised clearing. communicate causes and potential
prevention measures and solutions.
60
50
40
No. of Incidents
0 Severity 5
30
0
Severity 4
20
0
Severity 3
10
1
Severity 2
10 0
Severity 1
S1 S2 S1 S2 S1 S2 S1 S2
60 2012 2012 2013 2013 2014 2014 2015 2015
Figure 5.8 Environmental Incidents by Severity Level Upstream
Figure 5.9 Environmental Incidents by Project Component
50
Upstream Downstream
30
Upstream Impacts on Fauna
There were nine reportable incidents 2 (moderate). These include eight spill In addition to the reportable
recorded by the Upstream Operator. events which are listed in Table 5.1 and environmental incidents, Australia
Eight incidents had a consequence one instance of unauthorised clearing Pacific LNG is required to notify the
ranked as Severity 1 (minor). One of vegetation. The list of reportable spill Regulatory Authorities of instances of
incident had a consequence of severity incidents is described in Table 5.1. fauna injury and deaths associated with
Business activities or occurring within
Australia Pacific LNG’s sites.
Reportable Spills Inventory
The Upstream Operator notified the
Incident Contaminant State (solid, Quantity Receiving Regulatory Authorities of six reportable
fauna deaths involving species in
(substance) liquid or (Kg, Litres environment
accordance with the relevant, approved
gas) or m3) (land, water
Species Management Plan. Species
or air) reported included: one Short-beaked
1 CSG produced water Liquid 100,000 L Land Echidna, four Grey snakes, and one
2 Drilling fluid Liquid 10,000 L Land Golden tailed gecko.
3 Turbid water Liquid 4.2 Ml Water At Curtis Island, two reportable fauna
4 CSG produced water Liquid < 20,000 L Land deaths occurred onsite, a Hardhead
Duck and an Australian Magpie were
5 CSG produced water Liquid 10.1 ML Water found deceased onsite. In addition,
6 CSG produced water Liquid 40,000 L Water six Torresian Crow eggs were found
CSG produced water Liquid 66,000 L Land abandoned in a nest that could not
7
be salvaged.
8 Hydrocarbon Solid 80 m (of soil)
3
Land
Downstream
There were two reportable incidents Fire ant inspections are ongoing and no
recorded by the Downstream Operator. further infestations have been found.
The first involved turbid water The Department of Agriculture and
overflowing spillways following a heavy Fisheries did not undertake any fire
rain event. The second was a reportable ant inspections during the reporting
spill where 50 ml of Panolin spilled into period as Australia Pacific LNG has
the Gladstone Harbour. demonstrated compliance with the Fire
All incidents were recorded, notified to Ant Management plan.
regulators and investigated. All incidents
were actual consequence Severity
1 (minor).
Water (Gladstone
1 Panolin (hydraulic fluid) Liquid 50 ml
Harbour)
Downstream
Number of reportable
2
environmental incidents
Incidents of non-compliance
0
waste conditions
Incidences of non-compliance
0
with noise limits
Upstream Downstream
Prior to conducting activities involving No additional vegetation clearing works
significant land disturbance, an were conducted during the period.
assessment of the condition, type and
During the reporting period, seven
ecological value of vegetation in the
snakes (pythons, an Eastern Brown
area is undertaken. This is referred to
Snake and a Lesser Black Whipsnake)
as the field ecological assessment.
were successfully caught and relocated
Following this, a pre-construction field
to adjacent bushland.
environmental scout is undertaken.
Migratory shorebird monitoring was
A field environmental scout
conducted in December 2015. During
also confirms the suitability of
the survey no disturbances to roosting
infrastructure layout in accordance
or foraging behaviour associated with
with the Environment Protection and
construction or operation activities
Biodiversity Conservation (EPBC) Act
were observed.
1999 and other applicable regulatory
requirements as well as relevant Quarterly mangrove monitoring
plans for threatened and endangered continued in accordance with
species. These requirements are the Receiving Environment
specified in the Australia Pacific LNG Monitoring Program.
Environmental Constraints Planning and
A Water Mouse survey was conducted
Field Development Protocol.
onsite 14 to 18 November 2015. No
There was one reportable incident evidence of the presence of Water
regarding ecological management in the Mouse was detected in the study area
reported period. The incident involved during the survey, despite extensive
the clearing of 317 m2 of vegetation daytime searches for Water Mouse
adjacent to a lease pad in the Dinoun signs and 400 nights of trapping effort
State Forest. A pre-clearing ecology within habitats suitable for Water
survey confirms that the cleared area Mouse. Despite the lack of detection,
did not comprise of remnant vegetation remaining mangrove habitats within the
and contained no regrowth of study area provide potentially suitable
Endangered Regional Ecosystems. habitat for the species.
Upstream Downstream
Biosecurity packages have been The LNG facility has an overarching
developed and are supported by biosecurity plan for the Downstream
ongoing education and training, activities. This plan serves as a guideline
including an e-learning module and for the biosecurity management
improved weed identification guides. plans used by subcontractors during
Project construction.
There have been no quarantine
incidents reported during July and One important aspect of this plan is
December 2015. the Australia Pacific LNG Sail Away
Clearance Checklist. This checklist
requires a thorough review of customs
clearance documentation, cleanliness
of the modules, final wash down
and re-checks for contamination,
pre-departure inspection by DAF, and
other criteria. The checklist is designed
to prevent biosecurity risk material
entering Australia via the module
transport barge.
Upstream Downstream
Australia Pacific LNG continued The Principal Contractor undertook
to implement pest management a weed survey of the Australia
programs and actions for existing Pacific LNG site on Curtis Island in
weed and pest issues. No pest or September 2015. Three declared
pathogen incidents were recorded pest species were recorded on Curtis
during the reporting period. Island during the September 2015
survey, comprising of parthenium
A weed identification guide specific weed, rubber vine and lantana.
to the Surat and Bowen basins has
been prepared and finalised. The The weeds were removed via a
weed identification guide has been combination of chemical treatment
developed to increase the awareness and manual removal.
of the highest risk weeds to the
Business and enable personnel
to recognise regionally significant
species, including Chilean Needle
Grass, Rats-tail Grasses and prickly
shrub species such as Prickly Acacia.
The guide will be rolled out in 2016
as part of a broader biosecurity
education program.
10,000
10,000 Disturbance
Disturbance vs vs Reinstatement
Reinstatement in ha
in ha
9,000
9,000 Cumulative
Cumulative Reinstatement
Reinstatement in hain ha
8,000
8,000
Cumulative
Cumulative Disturbance
Disturbance in hain ha
7,000
7,000
6,000
6,000
Hectares
Hectares
5,000
5,000
4,000
4,000
3,000
3,000
2,000
2,000
1,000
1,000
0
0
S1 S2 S1 S2 S1 S2 S1 S2
S1
2012 S2
2012 S1
2013 S2
2013 S1
2014 S2
2014 S1
2015 S2
2015
2012 2012 2013 2013 2014 2014 2015 2015
Lummus Consultant Jeff Bleathman and Australia Pacific LNG personnel, Michael
Stahl, Candice Shelley and Marianne Gibbons, reviewing reinstatement of Camp
Four near Biloela in September 2015.
Downstream
The Monte Christo offsets property Work undertaken over the past six Hectares of net disturbance*
purchase, jointly made with two other months has continued to progress
LNG proponents, was developed transfer of the remaining freehold Upstream 9,107 ha
to protect and remove threatening allotments to the Queensland Downstream 193 ha
processes from land containing Great Government for inclusion in the
Barrier Reef World Heritage values, Queensland Conservation Estate.
remnant vegetation and significant Disturbance of remnant
The Long Term Marine Turtle vegetation
marine habitat. The property was
Management Plan was approved
secured with an official announcement Upstream 214 ha
by the Australian Department of the
made in August 2014.
Environment in July 2014. This plan
Downstream 0
This offset property purchase was used builds on existing programs funded by
as a case study in a World Wide Fund Australia Pacific LNG including GISERA Disturbance of high value
for Nature Australia publication, Building and the Western Basin Dredging regrowth in hectares
Nature’s Safety Net 2014: A decade Environmental Review and Monitoring
of protected area achievements in Program. Australia Pacific LNG has Upstream 22 ha
Australia, where the benefit of the offset continued to progress this plan with
Downstream 0
in protecting the critically endangered the other proponents with a program of
Capricorn Yellow Chat was recognised. studies to commence implementation in
Hectares of successfully
This is one of several species with the next reporting period.
improved protection arising from the completed reinstatement*
offset even though it is not directly
Upstream 6,258 ha
impacted by the Business.
Downstream 0
Areas of offset established
and protected
Upstream 1#
Downstream 0
Number of complaints
received related to weed
management
Upstream 0
Downstream 0
Australia Pacific LNG aims to avoid Water is extracted from the target coal 7.2.2 Supply of
or reduce loss of access to Good formations to allow the production of
Quality Agricultural Land (GQAL) by coal seam gas. Low permeability rock Treated CSG Water
locating surface infrastructure away strata that overlay and underlay the for Beneficial Use
from such land where practicable. CSG formations, known as aquitards,
During this reporting period, 586 ha of protect the adjacent aquifers used The quantity of treated CSG water
land disturbed was classed as GQAL, by others from the effects of the supplied for beneficial use also
representing 73 percent of the total resultant coal depressurisation. The increased compared to the previous
area disturbed in the period. Upstream Operator has implemented its reporting period, reflecting the
groundwater monitoring plan to detect increased volume of CSG water
pressure changes in these aquifers. produced. The operation of the
Fairymeadow Road Irrigation Scheme
7.2.1 CSG Water has meant that no releases to the
Condamine River have occurred during
Production the reporting period.
The vast majority of CSG water The volume of treated CSG water
production during the reporting period supplied for beneficial use was 9,511
was generated from the Australia Pacific ML, which represents an approximate
LNG CSG fields of Talinga and Orana, 27 percent increase on the previous
Spring Gully, Condabri, Combabula and reporting period and 80 percent of the
Reedy Creek. Minor volumes of CSG total volume of produced CSG water
water were also produced from the Peat (Figure 7.1).
field and appraisal wells developed as
part of the exploration program.
The total volume of CSG water
production for the reporting period was
11,920 megalitres (Ml), representing
an approximate 15 percent increase
on the previous period, reflecting the
increase in the number of CSG wells
brought online.
CSG water is temporarily stored in
ponds, prior to desalination treatment
and supply for beneficial use, including
irrigation, aquifer injection, project, and
construction uses. Any treated water
unable to be beneficially used is released
under licence to natural streams.
12000
Produced Water Awaiting Treatment
10000
Total Volume of Brine Produced
4000
20%
2000
10% 80%
0
0% 70%
S1 S2 S1 S2 S1 S2 S1 S2
2012 2012 2013 2013 2014 2014 2015 2015
Produced Water Awaiting Treatment 60%
Figure 7.1 CSG Water Produced and Supplied for Beneficial Use 50%
Total Volume of Brine Produced
40%
Produced Water Awaiting Treatment Permeate Discharge to Creek
30%
Total Volume of Brine Produced Total water supplied for beneficial use
10% 80%
0% 70%
20%
S1 S2 S1 S2 S1 S2
2 2013 2013 2014 2014 2015 2015
10% 60%
80%
50%
0% 70%
S2
2015 40%
54 Australia Pacific LNG Environmental
60%and Social Report
30%
50%
7.2.3 Groundwater
Monitoring System
Upstream Downstream
A network of deep groundwater Groundwater monitoring was
monitoring bores has been established undertaken on the Curtis Island site
to provide a regional groundwater from 2010 to 2014. The purpose of
monitoring system for the Australia the study was to collate and analyse
Pacific LNG Business. The network the groundwater monitoring data taken
includes over 120 monitoring bores prior to and during construction at the
purpose-built to provide data to site, to identify trends, and to review
the Office of Groundwater Impact geotechnical data. This was undertaken
Assessment (OGIA), with a total of 48 in order to develop a hydrogeological
km drilled. These dedicated monitoring conceptual model of the site and any
bores will be augmented by existing ongoing monitoring recommendations.
government bores and landholder This included the collation and analysis
production bores. of historic groundwater data for the 38
monitoring bores installed across the
Of the planned network, only five
site prior to and during construction.
dedicated monitoring bores required
to be drilled by the end of 2015 were The Groundwater Monitoring Summary
not completed. All five are scheduled and Conceptualisation Report was
for completion by early February finalised in 2014. Based on the
2016. The additional monitoring bores conceptual model and review of the
originally required to be drilled prior to location of monitoring bores, a number
31 December 2016 are currently under of opportunities were presented for
review as part of OGIA’s tri-annual consideration for any future installation
revision of impact forecasts in the of groundwater bores and the
second iteration of the Underground undertaking of a monitoring program
Water Impact Report. during operations.
At the end of the reporting period, Since the completion of the
27 Queensland Government and Groundwater Monitoring Summary
landholder bores had been equipped and Conceptualisation Report in
with automatic groundwater level data the last quarter of 2014, further
logger instrumentation. groundwater monitoring will only be
undertaken in response to any issues
In addition to these monitoring bores,
that may arise during the remaining
there is a network of shallow sentinel
construction phase.
monitoring bores designed to ensure
the integrity of produced water and
brine storage ponds.
Most completed monitoring bores are
now equipped with groundwater level
loggers and dedicated sampling pumps
as required.
The latest results of groundwater
monitoring undertaken by Australia
Pacific LNG are reported and made
publically available in the 2014-2015
Groundwater Assessment, which is
available at the following link: http://
www. aplng.com.au/environment/
management-plans
Australia Pacific LNG Environmental and Social Report 55
7.2.4 Make Good 7.2.5 Hydraulic 7.2.6 Ground
Agreements Fracturing Subsidence
The Surat Underground Water Impact Hydraulic fracturing frees up gas to Monitoring System
Report (UWIR) ) initially identified 40 flow, meaning that fewer wells are Ground motion is monitored using
bores for ‘make good’ agreements, required. Most of the current natural direct, on-ground instrumentation
with Australia Pacific LNG as the gas production is in high permeability and remote Interferometric Synthetic
responsible tenure holder, involving 24 (or high flow) areas where hydraulic Aperture Radar (InSAR). The on-ground
landholders. Throughout the course of fracturing is not required. Only one instrumentation includes tiltmeters
ongoing operations and assessments, development well required hydraulic and extensometers. Tiltmeters are
various bores have been added fracturing during the period. designed to measure very small
or removed from the make good changes from the horizontal level,
assessment list with refinements to the either on the ground or in structures.
understanding of geological and bore Extensometers are designed to
details, or changes to the responsible measure displacement and are ideal for
tenure holder and immediately subsidence monitoring.
impacted area. Currently, 50 bores are
confirmed or under assessment for A geodetic monitoring network was
make good amongst 25 landholders. established in 2013. This network
Make Good Agreements have been comprises 47 permanent survey marks
executed with 20 of these landholders across Australia Pacific LNG tenures
for 41 bores. During the period there (one survey mark was destroyed
were nine Make Good Agreements between the last two monitoring rounds
executed for 16 bores. as a result of construction activities).
There is ongoing communication The InSAR data collected and
with the regulatory authorities and processed over 2012 to 2015
negotiations continue with landholders. indicates subsidence and uplift trends
in the Undulla nose region. Latest
assessment and details of ongoing
studies can be found in Section 7 of the
2014-2015 Groundwater Assessment
Report. The motion is below any
trigger for formal notification, however
regulators were consulted.
Upstream Downstream
544
754
The principal raw materials required for Raw materials used in construction
the Upstream construction activities consist predominantly of components
were water and gravel. Gravel is used in for making concrete such as cement, 102,500
1,690
construction of access roads and well aggregate material and water. At the end
pads and ongoing maintenance. of the reporting period, approximately
704 m3 of concrete had been used
The Upstream Operator used on Curtis Island. Other raw materials
approximately 400 Ml of water sourced used were mostly sand and aggregate
from landholder bores and dams, (Figure 7.2).
operational Water Treatment Facilities The Gladstone Area Water Board
(i.e. treated CSG water), dams/tanks (GAWB) pipeline continued to supply
with untreated CSG water and municipal reticulated water services to the
110,000
water supply. Project site on Curtis Island. GAWB
supplied the site with 110 Ml of water,
With regard to gravel, approximately a marginal decrease from the previous
121,000 tonnes was used in reporting period. Figure 7.2: Downstream Project
construction of well pads and road Raw Materials
maintenance for the period.
Raw Materials in Tonnes
544
754
Water
102,500
1,690
Sand
Sand
Concre
Concrete
Agrega
Aggregate
110,000
Australia Pacific LNG and peak science Agricultural Land Management Social and Economic
body, CSIRO, entered into a research
alliance in 2011 for five years, initially as The five research projects underway in The four research projects in social
a bilateral venture, and with a view to this portfolio are designed to maximise and economic research aims to identify
establishing industry and government agricultural productivity during and what communities want and need
support. The initial investment from beyond the life of gas extraction to help inform and support changes
Australia Pacific LNG is AUD$10 million on farms. occurring in CSG development regions.
over five years, with CSIRO committing These projects include: These projects include research
a further AUD$4 million in in-kind on monitoring of regional changes,
support. QGC has also joined GISERA • Preserving Agricultural productivity community function and wellbeing and
in recognition that the challenges being – 85 percent complete community aspirations including:
addressed through GISERA are relevant • Shared space – complete
to the entire CSG to LNG industry • Monitoring regional change
and that there are benefits from such • Farm gas design – 85 percent – complete
collaborative research. complete • Community function and wellbeing
GISERA was established in recognition • Making tracks, treading carefully – 90 – complete
of the impacts of CSG on public assets, percent complete • Community aspirations – complete
and the related need to undertake • Without a trace – complete
publicly-available quality research to • Economic assessment and
address those impacts. The overall progress for the five projects forecasting – 30 percent
is approximately 90 percent. The progress for these projects is
GISERA’s main research areas include
water, agriculture, biodiversity, marine approximately 90 percent.
Terrestrial Biodiversity
environment, socio-economic and
greenhouse gas. There are four projects underway in
this portfolio, including understanding
Upstream
The Stakeholder Engagement Engagement with communities is a Enquiries
Strategy articulates Australia Pacific priority for the Upstream Operator.
LNG’s commitment and approach The Upstream Operator held 45 formal The Upstream Operator enables
to stakeholder engagement, and engagements with Local Governments stakeholder contact by maintaining a
describes how this commitment will be and key community stakeholder range of information channels including
managed across the gas fields, pipeline groups throughout the region. Informal regional office walk-ins, the Origin and
and LNG Facility components for the engagement activity continued through Australia Pacific LNG websites, email
life of the Business. support and participation in various enquiry channels, and an information
events. During the period, the Upstream hotline. The majority of enquiries related
These stakeholders are broadly to information regarding the Business,
Operator participated in:
classified as: employment opportunities and
• The Chinchilla Trail Ride landowner matters.
• Community
• Maranoa Regional Council Audio Figure 8.1 summarises enquiries
• Government
Visual Project for Upstream.
• Traditional / Indigenous
• The Queensland Regional
owner groups
Community & Achievement Awards.
• Landholders 10 2
In addition there were 1,132 informal
• Suppliers and contractors engagements including emails,
18
telephone calls and walk-ins to 41
• Employees of Australia Pacific LNG,
regional offices. Regional Community
and its shareholders ConocoPhillips, 45
Consultative Committee (RCCC)
Sinopec and Origin
meetings for the Western Downs,
• Lenders, including export credit Maranoa and Banana Shire regions
agencies and commercial banks that continued as the key forum for
provide financing for certain elements exchanging community insights, priority
of the Project issues and Project information.
• Non-government organisations and
other special interest groups
• Owners/Investors in the shareholders 557
of Australia Pacific LNG (Origin,
ConocoPhillips and Sinopec).
Figure 8.1: Upstream Project Topics
of Enquiry
10 2
Topics of Enquiry
45 Stakeholder Engagement
S2 2015
Employment
Procurement
Community Investment
Downstream
Community relations activities included Local content includes employment, how opportunities are provided for
20 formal stakeholder engagement procurement, training and local businesses to participate in
events, 490 informal stakeholder development, and contracting of the Business. The strategy includes
engagements (emails, telephone people, goods and services who are training and development initiatives to
calls and walk-ins), one sponsored considered by Australia Pacific LNG build capacity in local businesses, as
community event and two collaborative to be nationals or national companies well as our Regional Buy Program.
engagement activities. Employment operating within Australia, including
During the period, more than 360
continues to be amongst the most the immediate area where the Project suppliers attended Regional Buy
frequent enquiries. Topics of enquiries is located. It includes any service or Program workshops in the Surat
are shown in Figure 8.2. maintenance element forming part of Basin. Regional suppliers are a defined
materials purchase. group within our Local Content
.
SinceTopics
2011,of the
Enquiry
Local Content Team Policy and require additional support
4
has referred over 600 businesses to to ensure inclusion in commercial
the Queensland Department of State
Employment opportunities, and competitiveness in
Development, Infrastructure and providing goods and services.
14 12 Planning forProcurement
business diagnostics and Australia Pacific LNG has adopted
development. The range of services the Queensland Resources and
40
include writing capability statements Energy Sector Code of Practice for
Construction and Operations
(approximately 220 companies), being Local Content.
pre-qualified to supply to the Business
135 Approximately 78 percent of all
(approximately 90 companies),
Community Investmentbuilding
competitiveness through contract expenditure for the Project to date
71 management and theand
tendering was sourced in Australia. The Local
Education Training Content benefits have predominantly
process. In addition, the referrals have
resulted in business matching with remained within Queensland, with
Environmental Concerns
other opportunities within the region. over 57 percent of all Project spend
73
As the Project moves to the operations occurring within the State. The
Queensland spend has provided
and maintenance phase,
Community theand
Health teamSafety
significant benefits within the areas
will continue to build local capability
managed by local Regional Councils
Figure 8.2: Downstream Project Topics through collaboration with State and
of Enquiry in the Surat Basin where the gas
Local governments.
and water facilities are located and in
Topics of Enquiry Australia Pacific LNG’s Local Content Gladstone where the LNG facility is
Policy and associated strategy outlines being constructed.
Employment
Procurement
Environmental Concerns
Complaint Categories
Australia Pacific LNG, the Operators and Regional Community
contractors record and respond to all Consultative Committees
Land Access and Compensation
1
community complaints from landholders 1 1
and community members. Australia 2
Australia Pacific LNG is involved in
Noise Community Consultative
four Regional
Pacific LNG endeavours to respond
to all complaints within 48 hours and Committees in Maranoa (jointly with
2
investigate in a fair and transparent Santos), Western Downs, Banana Shire
Others
manner in an effort to achieve a timely and Gladstone (jointly with Santos
resolution with the complainant. 3 18 and QGC).
Dust
During this reporting period, Australia The purpose of the committees is to
Pacific LNG registered 32 complaints, foster open and transparent dialogue
Property Damage
showing a continued reduction when 4 between Australia Pacific LNG and the
compared with 57 complaints received community, by providing a mechanism
in the previous period. for information exchange and the
Rehabilitation
collaborative development of solutions
Complaints were predominantly related to social impacts.
to community concerns about land Figure 8.3: Community Complaint Categories Safety
access, noise and dust. (Refer to Members represent a broad cross-
Figure 8.3 and Figure 8.4). At the end Complaint Categories section of the
Traffic andcommunity
Transport in each
of the reporting period, 84 percent region, including representatives from
of all complaints Land Access and Compensation local council, government departments,
1 received had been
1 1
closed out. welfare groups, local chambers of
2 commerce and the general public.
All community complaints for this Noise
reporting period were received by the
2 Community Programs
Upstream Operator, due to the vast Others
area covered by the Upstream Project The Upstream Operator continued
3and by the much larger number18 of its support of the ‘CSG Industry
Dust Schools Program’, a joint road safety
directly affected stakeholders. The
Downstream Operator did not receive initiative with Police and Citizens
any 4community complaints. Property Damage Youth Club (PCYC), equipment
upgrades for Queensland Fire and
S2 2015 Emergency Services (QFES) and the
Rehabilitation ‘I Can Indigenous Student Retention
Program’, which are jointly funded
Safety with other proponents. The Thornhill
Indigenous Training Centre upgrade,
jointly funded by Australia Pacific LNG,
Traffic and Transport
QGC and Gidarjil was completed
during the period.
120
Australia Pacific LNG total community complaints
100
Number of Complaints
80
60
40
20
S2 2015
0
S1 S2 S1 S2 S1 S2 S1 S2
2012 2012 2013 2013 2014 2014 2015 2015
Four social impact management themes underpin Australia Pacific LNG’s community
investment: social infrastructure, partnerships, sponsorships and donations, and
employee-giving and volunteering (Figure 8.5).
COMMUNITY INVESTMENT
In addition, the following priority areas form the basis of all activity and initiatives
undertaken by Australia Pacific LNG in any of the identified social impact
management themes seen in Figure 8.6.
SKILLS, EDUCATION Supporting community capacity building through local skills development and adding to
AND TRAINING local education opportunities
COMMUNITY SAFETY Supporting safer and healthier communities (including efforts by ambulance, healthcare,
police and emergency services) and public welfare activities
HEALTH AND WELLBEING
SUSTAINABLE Supporting projects that assist to manage population influx in a responsible and
sustainable manner
POPULATION GROWTH
Supporting the protection and enhancement of productivity in our natural resources
NATURAL RESOURCE
including agriculture, land, water and biodiversity
STEWARDSHIP
Figure 8.6 Priority areas for community investment
35 $185,659
Cumulative APLNG Investment
30
25
Million AUD$
20 $379,296
15
10
5
0 $1,338,253
S1 S2 S1 S2 S1 S2 S1 S2
2012 2012 2013 2013 2014 2014 2015 2015
Figure 8.7 Cumulative Australia Pacific LNG Community Investment Figure 8.8 Upstream Community Investment
by Priority Areas
$1,338,253
66 Australia Pacific LNG Environmental and Social Report
Downstream
$2,100
Downstream community investment
expenditure from June to December
2015 was AUD$22,100, with the bulk Skills, Education & Training
of 2015 expenditure occurring at the
start of the calendar year. This takes Community Cohesion
the total funds expended to date to
AUD$18.2 million. The Downstream
Operator committed extra funding to
the Gladstone Chamber of Commerce
‘Boom or Bust’ Gladstone Region
Business Study 2015, which studied
the effects, both actual and anticipated,
of the downturn in the construction $20,000
industry on local Gladstone businesses.
Figure 8.9 shows the Downstream
Operator’s community investment areas
and values for the reporting period. Figure 8.9 Downstream Community Investment
$2,100 by Priority Areas
Table 8.2 displays the complete list
of Community Investment Projects
managed by the Downstream Operator. Skills, Education & Training
Community Cohesion
$20,000
Target Duration of
Region Initiative Description Status Value
Group Investment
Program partner, Horizon Housing,
Lower income
completed the development of nine
Horizon Housing – earners Completed in
Western Downs homes in March 2013, which were Completed $2,050,000
Miles needing 2013
rented and sold at a significant
housing
discount to local residents.
Lower income
Funded a Housing Officer at Murilla
Housing Case earners Two years
Western Downs Community Centre in Miles and Completed $150,000
Management needing 2011- 2012
Chinchilla Family Support Centre.
housing
Total
Committed All Projects $22,714,437
by Upstream
* Shared sponsorship with the Downstream Operator for the total of AUD$1,000,000
Target Duration of
Region Initiative Description Status Value
Group Investment
Seed funding for the development
of affordable housing options, Lower income
One-off
Gladstone and funds to the Urban Land earners
Gladstone investment Complete $6,500,000
Affordable Housing Development Authority (ULDA) to needing
2012
fast-track affordable residential land housing
development.
Gladstone
Chamber of
Support of a study into the effects,
Commerce;
both actual and anticipated, of the Business
Gladstone ‘Boom or Bust’ 2015 Completed $20,000
downturn in the construction industry General
Gladstone
on local Gladstone businesses.
Region Business
Study 2015
Collaborative development of
Port Curtis Coral strategies to maximise the potential Aboriginal
Gladstone Coast Traditional of local Aboriginal and Torres Strait and Torres 2013 Completed $19,700
Owners Islander business involvement in the Strait Islander
Operations phase of the Project.
Queensland
General
Gladstone Symphony Sponsorship of a community event. 2012 Completed $10,000
Community
Orchestra
Total
All partnership and
Committed by All Projects $18,146,786
sponsorship programs.
Downstream
* Shared sponsorship with the Upstream Project for the total of AUD$1,000,000
Downstream
Upstream
Amongst the identified Indigenous Muddy Waters, a wholly-owned The Downstream Operator has
suppliers on the Upstream Operator subsidiary of Mandandanji Pty Ltd, partnered with supply chain
vendor list are: continue to be a preferred supplier partners and contractors to deliver
for weed hygiene wash-down a successful local indigenous
• St George Handy Store (a wholly- services to the Upstream Operator. content strategy as part of our
owned Indigenous business) Muddy Waters also provides these commitment to sustainable
• Roma Security Service (50 services for other CSG proponents operations. Gladstone has very few
percent indigenously owned and and businesses in Chinchilla and the indigenous-owned businesses and
operated, trading for over 20 surrounding areas. there are major capacity-building
years in Roma). constraints in the community. This
The Upstream Operator has is the beginning of a long-term
• RBY Projects (involved in developed a series of training strategic commitment to indigenous
construction and rehabilitation of programs with Corporate Culcha to content and engagement. Results to
leases for Australia Pacific LNG in provide a greater understanding of date include:
the Upstream Project area) Aboriginal and Torres Strait Islander
peoples’ history, cultural behaviours, • 14 contractors have committed to
• CRC Electrical (Electrical indigenous supply, employment
Instrumentation) and practices that may impact
the workplace, customer base and training
• Muddy Waters Weed Hygiene and community. • 16 sub-contracts have been
(weed hygiene wash down awarded in carpentry, cultural
services to the Upstream Ongoing efforts to provide awareness training, cleaning,
Operator and other businesses in opportunities to Traditional gardening, communications,
the Chinchilla area). Owner businesses will continue media, freight transport, art/
with assistance provided to culture
• Corporate Culcha (Indigenous groups to assist with capability
training program providers). and performance. • 22 full time positions have
been awarded for indigenous
Indigenous earthmoving and civil
employment in maintenance,
construction contractor RBY have
operations and maintenance,
continued involvement with the
ropes and non-destructive
Project with 35 percent of their
testing (NDT), security, waste
workforce (45 FTE Indigenous
management, cleaning
employees) involved in construction
and administration
and rehabilitation of leases for
Australia Pacific LNG in the • 11 indigenous traineeships
Upstream area. RBY are pre- have been awarded in
qualified to undertake work for the engineering, ropes and NDT,
Upstream Operator. telecommunications, plant
operations, warehouse and
waste management
• continued to engage a 100
percent indigenous-owned
business, Marion’s Cleaning
Service (MCS). Owned by Byellee
man Michael Eggmolesse, who
is a traditional owner of Curtis
Island, and his partner Marion
Dodd, MCS employs ten local
indigenous people
• ConocoPhillips has indigenous
trainees in warehouse
and operations.
Downstream 0 Upstream 6
Number of legacy
cases resolved in 3
the period
Number of landholder
18
complaints**
Number of ongoing
0
litigation cases
Number of cases
mediated in the 0
reporting period
*Social behaviour incidents refers to workforce behaviour complaints as detailed in Section 8.3.