Technical Specifications
June 2019
Town of Davie
7351 SW 30th Street
Davie, Florida 33314
Technical Specifications
Division 15 - Equipment
15060 Modifications to Reverse Osmosis Membrane Units and Cleaning System
Drawings
General
G-0 Cover Sheet
G-1 Location Map, General Notes, and Drawing Index
G-2 Legend and Abbreviations
G-3 Specifications
Mechanical
M-1 RO Process Bay – Overall Plan
M-2 RO Unit Modifications – Isometric
M-3 RO Unit Modifications – Plan
M-4 RO Unit Modifications – Elevations and Details
M-5 RO Unit Modifications – Elevations
M-6 Cleaning System Piping Modifications - Details
M-7 Mechanical Details
The following Technical Data is bound into this document following the Bidding
Documents for the Bidders’ convenience. In addition to the documents listed below, the
Operating and Maintenance Manual, Reverse Osmosis & Clean In Place System,
prepared by Aerex Industries, Inc., is available for Bidders’ review upon request to the
Owner.
Technical Data
1. Selected Record Drawings from the Town of Davie, Florida, Water Treatment and
Water Reclamation Facility, AECOM, November 2010.
2. Selected shop drawings for reverse osmosis process equipment and related
systems, Aerex Industries, Inc., 2010-2011.
3. Excerpt from Dow Water & Process Solutions FILMTEC™ Reverse Osmosis
Membranes Technical Manual, Section 6: Cleaning and Sanitation.
Accompanying Documentation:
CONTRACTOR'S Certification:
The undersigned CONTRACTOR certifies that (1) all previous progress payments received from OWNER on
account of Work done under the Contract referred to above have been applied on account to discharge
CONTRACTOR’s legitimate obligations incurred in connection with Work covered by prior Applications for
Payment numbered 1 through _____ inclusive; (2) title of all Work, materials and equipment incorporated in said
Work or otherwise listed in or covered by this Application for Payment will pass to OWNER at time of payment
free and clear of all Liens, security interests and encumbrances (except such as are covered by a Bond acceptable to
OWNER indemnifying OWNER against any such Lien, security interest or encumbrance); and (3) all Work covered
by this Application for Payment is in accordance with the Contract Documents and not defective.
Dated ____________________________
CONTRACTOR
By:
State of ______________________________
County of ____________________________
Subscribed and sworn to before me this ____
day of __________________, ________
____________________________________
Notary Public
My Commission expires: _____________________
Dated ___________________________
ENGINEER
By:
EJCDC No. 1910-8-E (1996 Edition)
Prepared by the Engineers Joint Contract Documents Committee and endorsed by The Associated General Contractors of America and the Construction Specification
Institute.
Application No._____ Date:_____________________
ITEM UNIT ESTIMATED SCHEDULE QUANTITY AMOUNT MATERIAL AMOUNT
PRICE QUANTITY OF VALUES COMPLETED % STORED COMPLETED
AMOUNT AND STORED
1. $ $ $ $ $
2.
3.
4.
5.
6.
7.
8.
9.
10.
11.
12.
13.
14.
15.
16.
17.
18.
19.
20.
21.
22.
23.
24.
25.
26.
27.
28.
29.
30.
TOTAL $ $ $ $
Note: Total Schedule of Values Amount should equal the current Contract Price.
WORK CHANGE DIRECTIVE
No. __________________
OWNER
CONTRACTOR
Contract:
Project:
OWNER's Contract No. ___________________ ENGINEER's Project No. _________________
If OWNER or CONTRACTOR believe that the above change has affected Contract Price any Claim for a
Change Order based thereon will involve one or more of the following methods as defined in the Contract
Documents.
Unit Prices
Lump Sum
Cost of the Work______________________
Estimated increase (decrease) in Contract Price: Estimated increase (decrease) in Contract Times:
$_____________________________________. Substantial Completion: ______ days;
If the change involves an increase, the estimated Ready for final payment: ______ days.
amount is not to be exceeded without further
authorization.
____________________________________________________________________________________
RECOMMENDED: AUTHORIZED:
_______________________________________ _______________________________________
ENGINEER OWNER
By: ___________________________________ By: ___________________________________
EJCDC No. 1910-8-F (1996 Edition)
Prepared by the Engineers Joint Contract Documents Committee and endorsed by The Associated General Contractors of America and the Construction
Specifications Institute.
CHANGE ORDER
No. ______________
OWNER
CONTRACTOR
Contract:_________________________________________________________
Project: _________________________________________________________
OWNER's Contract No. ________________________ ENGINEER's Contract No. _______________________
ENGINEER
You are directed to make the following changes in the Contract Documents:
Description:
OWNER
CONTRACTOR
Contract:
Project:
This Certificate of Substantial Completion applies to all Work under the Contract Documents or to the following
specified parts thereof:
To_____________________________________________________________________________
OWNER
And To _________________________________________________________________________
CONTRACTOR
The Work to which this Certificate applies has been inspected by authorized representatives of OWNER,
CONTRACTOR and ENGINEER, and that Work is hereby declared to be substantially complete in accordance
with the Contract Documents on
______________________________
DATE OF SUBSTANTIAL COMPLETION
A tentative list of items to be completed or corrected is attached hereto. This list may not be all-inclusive, and the
failure to include an item in it does not alter the responsibility of CONTRACTOR to complete all the Work in
accordance with the Contract Documents. The items in the tentative list shall be completed or corrected by
CONTRACTOR within _______ days of the above date of Substantial Completion.
OWNER:
CONTRACTOR:
The following documents are attached to and made a part of this Certificate:
[For items to be attached see definition of Substantial Completion as supplemented and other specifically
noted conditions precedent to achieving Substantial Completion as required by Contract Documents.]
This certificate does not constitute an acceptance of Work not in accordance with the Contract Documents
nor is it a release of CONTRACTOR's obligation to complete the Work in accordance with the Contract
Documents.
___________________________________________
ENGINEER
By: __________________________________________
(Authorized Signature)
By: __________________________________________
(Authorized Signature)
By: _______________________________________
(Authorized Signature)
SECTION 01010
SUMMARY OF WORK
PART 1 GENERAL
A. All work of this Contract is located at the Town of Davie Reverse Osmosis Water
Treatment Plant.
A. The CONTRACTOR shall furnish all labor, materials, equipment, tools, services and
incidentals to complete all work required by these Specifications and as shown on the
Drawings.
B. The CONTRACTOR shall perform the work complete, in place, disinfect where
applicable and make ready for continuous service, and shall include repairs,
replacements and restoration required as a result of work performed and damages
caused during the Work.
C. Furnish and install all materials, equipment and labor which is reasonably and properly
inferable and necessary for the proper completion of the work.
A. The Work in general consists of furnishing and installing piping and valving
modifications to the membrane cleaning system and the cleaning piping on the four
reverse osmosis membrane units, as shown on the Drawings and specified herein.
Following construction of the system modifications, the CONTRACTOR shall clean the
membrane elements in each of the four membrane units. Following cleaning of each
membrane unit, the CONTRACTOR shall prepare the unit for placing back on line and
assist the Owner’s operating staff with startup of the unit before cleaning the next
membrane unit.
B. The Work includes, but is not necessarily limited to, the following:
A. The work shall be completed to meet the requirements of the Substantial Completion
and Final Completion milestones, as specified herein. The work associated with each of
these milestones is defined below:
1. To satisfy the conditions of the Substantial Completion milestone the Work shall
be satisfactorily completed and the membrane units shall be ready for use by the
OWNER for their intended use, with the piping modifications installed,
membrane elements cleaned, membrane units prepared for startup, and leak
tested.
2. To satisfy the conditions of Final Completion, all work under this Contract shall
be complete and ready for final payment, including all punchlist work, OWNER
training and demonstration, submittal and approval of O&M data, and transfer of
up-to-date normalized membrane performance data spreadsheets for each
membrane unit to the OWNER.
A. Coordinate use of premises with the ENGINEER. All conflicts over use of the premises
shall be resolved without additional cost to the OWNER.
B. CONTRACTOR shall assume full responsibility for security of all their and their
subcontractor’s materials and equipment stored on the site.
D. If directed by the OWNER or ENGINEER, move any stored items which interfere with
operations of OWNER at no additional cost to the OWNER.
E. Obtain and pay for use of additional storage or work areas if needed to perform the
Work.
F. Obtain and pay for off-site staging/storage areas as required if on-site areas are
insufficient for construction activities.
A. Coordinate all activities with OWNER and ENGINEER to minimize conflict and to
facilitate OWNER usage.
END OF SECTION
CONSTRUCTION SEQUENCING
PART 1 GENERAL
A. Several areas of Work under this contract must be coordinated with the Plant
Superintendent or Plant Supervisor at the water treatment plant and accomplished in
a logical order to maintain the process flow through the plant and to allow work to be
completed within the Contract Times. CONTRACTOR shall also coordinate his
activities with other contractors working on the site, if any, to allow orderly and timely
completion of the Work.
D. Various interconnections within the plant will depend on the closure of various valves.
Many of these valves are old, may be difficult to operate, or may not seal properly.
CONTRACTOR shall coordinate with the Plant Superintendent or Plant Supervisor
prior to requesting any such closure and shall provide any corrective measures or
temporary facilities necessary to attain the shut-off needed to perform the work at no
additional cost to the OWNER and without interrupting the plant operation. Only
OWNER’s personnel shall operate plant valves.
E. Various interconnections within the plant may require temporary partial power
shutdown. CONTRACTOR will make every effort necessary to minimize the
shutdown time and will coordinate with the ENGINEER, plant operating personnel,
and/or utility authorities at least five (5) working days prior to attempting any such
power shutdown. Furthermore, CONTRACTOR will provide any corrective measure or
temporary facilities necessary to perform the work at no additional cost to the
OWNER and without interrupting the plant operation. The CONTRACTOR shall
submit a plan for each anticipated partial power shutdown.
F. Within the Schedule developed in accordance with Section 01310 of the Contract
Documents, the CONTRACTOR shall identify all periods of time during which existing
facilities shall be taken out of service, either temporarily or permanently.
G. During leak testing, the CONTRACTOR shall make available the staffing, labor,
equipment, and manufacturer’s representatives required to make any necessary
adjustments and training.
H. Scheduled shutdowns will be made in those instances when it is necessary to shut off
power in order to perform the necessary work. Prior to any shutdown, all materials
and facilities shall be on hand, and any preparatory work necessary shall have been
accomplished before any shutdowns will be allowed. The CONTRACTOR shall submit
a plan for each anticipated partial power shutdown.
A. CONTRACTOR shall not interfere with the operation of the water treatment plant or
adjacent facilities during construction or testing of the improvements. Available
treatment capacity and storage at the plant cannot be assumed to be sufficient to
satisfy system demand in a single plant operation scenario for other than brief (less
than four hour) periods. This section lists constraints which CONTRACTOR must
consider in developing the overall plan for construction and testing. This list of
constraints is not intended to release CONTRACTOR from responsibility to coordinate
the Work in a manner which will ensure project completion within the time allowed. A
summary of construction sequencing constraints within each major area of Work,
where necessary, is included in Paragraph 1.04 of this section.
B. The CONTRACTOR shall be responsible for coordinating the work in a manner which
will ensure project completion within the Contract Times.
C. The OWNER may require CONTRACTOR to perform facility shutdown work during
non-regular working days and hours at no additional cost to the OWNER.
D. Within sixty (60) days after the Notice to Proceed and prior to the submittal of shop or
layout drawings for pipe connecting to existing pipe, the CONTRACTOR shall gather
necessary information so as to avoid subsequent delays in project completion or
additional cost to the OWNER.
A. Only one (1) membrane unit may be taken out of service at a time due to the
CONTRACTOR’s work. The remaining units must remain operational.
B. No membrane unit shall be out of service for greater than 14 calendar days.
C. The following construction tasks must be completed, tested, and operational prior to
the first membrane unit being taken out of service:
A. Within fourteen days after the award of the Contract, submit to the ENGINEER, a
Construction Sequence Schedule. This schedule shall provide a listing of major
construction and testing items and the sequencing of these items of work so as to
impact the operation of the water treatment plant and adjacent facilities to the
minimum extent possible.
B. Work shall be sequenced so as to achieve the contract milestones set forth in the
Conditions of the Contract within the Contract Times specified in the Agreement.
B. In order to provide adequate treatment of raw water, the existing treatment facilities
shall be kept in continuous operation during construction. Partial shutdowns as
approved in the sequence of construction may be allowed. The timing and duration of
such shutdown, however, shall be as approved by the OWNER and will be predicated
upon plant operating requirements at that time. When the CONTRACTOR desires a
partial shutdown, he shall notify the OWNER/ENGINEER a minimum of five (5)
working days in advance.
C. Night work and/or work on Saturday, Sunday or holidays may be required when
making connections to existing pipes or structures. It will be the decision of the
OWNER if connections or modifications must be made other than during normal
working hours, and this will be accomplished at no additional cost to the OWNER.
A. It is assumed that portions of the work will be completed prior to completion of the
entire work. Upon completion of construction in each individual facility, including
testing, if the OWNER, at its sole discretion, desires to accept the individual facility,
the CONTRACTOR will be issued a dated certificate of completion and acceptance
for each individual facility. The OWNER will assume ownership and begin operation
of the individual facility on that date and the one-year guaranty period shall
commence on that date. The OWNER has the option of not accepting any individual
completed facility, but accepting the entire work as a whole when it is completed and
tested.
END OF SECTION
PART 1 GENERAL
A. Submit Applications for Payment to the ENGINEER in accordance with the schedule
established by Conditions of the Contract and the Agreement between OWNER and
CONTRACTOR.
B. The accepted Schedule of Values, Section 01370, shall be used as the basis for
CONTRACTOR’s Application for Payment.
A. Contract Agreement
1. Format, schedules, line items and values: Those of the Section 01370 Schedule of
Values accepted by the ENGINEER.
A. Application Form:
1. Fill in required information, including that for Change Orders executed prior to date
of submittal of applications.
2. Fill in summary of dollar values to agree with respective totals indicated on
continuation sheets.
3. Execute certification with signature of a responsible officer of CONTRACTOR.
B. Continuation Sheets:
1. Fill in total list of all scheduled component items of work, with item number and
schedule dollar value for each item.
Town of Davie 01152-1 Application for Payment
2. Fill in dollar value in each column for each scheduled line item when wok has been
performed or products stored.
3. List each Change Order executed prior to date of submission, at the end of the
continuation sheets.
1. Project.
2. Application number and date.
3. Detailed list of enclosures.
4. For stored products:
B. Submit one copy of data and cover letter for each copy of application.
B. Use continuation sheet for presenting the final statement of accounting as specified in
Section 01700 – Contract Closeout.
A. Submit Applications for Payment to the ENGINEER at the times stipulated in the
Agreement.
C. When the ENGINEER finds Application properly completed and correct, he will
transmit certificate for payment to the OWNER, with copy to CONTRACTOR.
END OF SECTION
PART 1 GENERAL
1.01 REQUIREMENTS INCLUDED
1.02 DEFINITIONS
A. Change Order: A written order from the OWNER to the CONTRACTOR executed
in accordance with the City’s Procurement Code, as amended, authorizing an
addition, deletion, or revision to the work, or an adjustment in the Contract Price or
the Contract Time after the date of the Contract.
D. Field Order: A written order to the CONTRACTOR signed by the ENGINEER and
the CONTRACTOR, which is issued to interpret/clarify the Contract Documents,
order minor changes in the work and/or memorialize trade-off agreements. The
work described by the Field Order is to be accomplished without change to the
Contract Sum, Contract Time, and/or claims for other costs.
3. The project time span for making the change and a specific statement as to
whether overtime work is, or is not, authorized.
4. A specific period of time during which the requested price will be considered
valid.
3. Statement of the effect on the Contract Sum and the Contract Time.
A. Work Change Directives will describe changes in the work, both additions and
deletions, with attachments of revised Contract Documents to define details of the
change and will designate the method of determining any change in the Contract
Sum and any change in Contract Time.
B. OWNER and ENGINEER will sign and date the Work Directive Change as
authorization for the CONTRACTOR to proceed with the changes.
A. Support each quotation for a lump-sum proposal and for each unit price which has
not previously been established, with sufficient substantiating data to allow
ENGINEER to evaluate the quotation.
B. On request, provide additional data or support time and cost computations for:
1. Labor required.
2. Equipment required.
C. Support each claim for additional costs and for work done on a time-and-
material/force account basis, with documentation as required for a lump-sum
proposal, plus additional information.
1. Name of the OWNER’s authorized agent who ordered the work and date of the
order.
2. Dates and times work was performed, and by whom.
3. Time record, summary of hours worked, and hourly rates paid.
4. Receipts and invoices for:
B. Change Order will describe changes in the work, both additions and deletions, with
attachments of revised Contract Documents to define details of the change.
C. Change Order will provide an accounting of the adjustment in the Contract Sum
and in the Contract Time.
E. Field Order work will be accomplished without change in the Contract Sum,
Contract Time, and/or claims for other costs.
A. ENGINEER initiates the form, including a description of the changes involved and
attachments based upon documents and proposals submitted by CONTRACTOR,
or requests from OWNER, or both.
B. Once ENGINEER has completed and signed the form, all copies should be sent to
CONTRACTOR for approval. After approval by CONTRACTOR, all copies should
be sent to OWNER for approval. ENGINEER should make distribution of executed
copies.
C. When quantities of each of the items affected by the Change Order can be
determined prior to start of the work:
1. OWNER and ENGINEER will sign and date the Work Directive Change as
authorization for CONTRACTOR to proceed with the changes.
C. ENGINEER will determine the allowable cost of such work, as provided in General
Conditions and Supplementary Conditions.
D. ENGINEER will sign and date the Change Order to establish the change in
Contract Sum and in Contract Time.
E. CONTRACTOR will sign and date the Change Order to indicate agreement
therewith.
A. Not greater than monthly revised Schedule of Values and Request for Payment
forms to record each change as a separate item of work, and to record the
adjusted Contract Sum.
B. Not greater than monthly revise the Construction Schedule to reflect each change
in Contract Time. Revise sub-schedules to show changes for other items of work
affected by the changes.
END OF SECTION
SUBMITTALS
PART 1 GENERAL
C. The CONTRACTOR is to maintain an accurate updated submittal log and will bring
this log to each scheduled progress meeting with the OWNER and the ENGINEER.
This log should include the following items:
A. Shop Drawings
B. Product Data
1. Product data as specified in individual Sections, include, but are not necessarily
limited to, standard prepared data for manufactured products (sometimes
referred to as catalog data), such as the manufacturer’s product specification and
installation instructions, availability of colors and patterns, manufacturer’s printed
statements of compliances and applicability, roughing-in diagrams and templates,
catalog cuts, product photographs, standard wiring diagrams, printed
performance curves and operational-range diagrams, production or quality
control inspection and test reports and certifications, mill reports, product
operating and maintenance instructions and recommended spare-parts listing,
and printed product warranties, as applicable to the work.
C. Samples
1. The CONTRACTOR shall furnish, for the approval of the ENGINEER, samples
required by the Contract Documents or requested by the ENGINEER. Samples
shall be delivered to the ENGINEER as specified or directed and in quantities
and sizes as specified. A minimum of two samples of each item shall be
submitted unless otherwise specified. The CONTRACTOR shall prepay all
shipping charges on samples. Materials or equipment for which samples are
required shall not be used in work until approved by the ENGINEER.
2. Samples specified in individual sections, include, but are not necessarily limited
to, physical examples of the work such as sections of manufactured or fabricated
work, small cuts or containers of materials, complete units of repetitively-used
products, color/texture/pattern swatches and range sets, specimens for
coordination of visual effect, graphic symbols, and units of work to be used by the
ENGINEER or OWNER for independent inspection and testing, as applicable to
the work.
3. The CONTRACTOR shall prepare a transmittal letter in triplicate for each
shipment of samples. He shall enclose a copy of this letter with the shipment and
send a copy of this letter to the ENGINEER. Approval of a sample shall be only
for the characteristics or use named in such approval and shall not be construed
to change or modify any Contract Requirements.
4. Approved samples not destroyed in testing shall be sent to the ENGINEER or
stored at the site of the work. Approved samples of the hardware in good
condition will be marked for identification and may be used in the work. Materials
and equipment incorporated in work shall match the approved samples.
Samples which fail testing or are not approved will be returned to the
CONTRACTOR at his expense, if so requested at time of submission.
B. The CONTRACTOR shall review shop drawings, product data and samples, including
those by subcontractors, prior to submission to determine and verify the following:
1. Field measurements
2. Field construction criteria
3. Catalog numbers and similar data
4. Conformance with the Specifications
C. Each shop drawing, sample and product data submitted by the CONTRACTOR shall
have affixed to it the following Certification Statement including the CONTRACTOR's
Company name and signed by the CONTRACTOR: "Certification Statement: by this
submittal, I hereby represent that I have determined and verified all field
measurements, field construction criteria, materials, dimensions, catalog numbers
and similar data and I have checked and coordinated each item with other applicable
approved shop drawings and all Contract requirements." Shop drawings and product
data sheets 11-in x 17-in and smaller shall be bound together in an orderly fashion
and bear the above Certification Statement on the cover sheet. The cover sheet shall
fully describe the packaged data and include a listing of all items within the package.
Provide to the Resident Project Representative a copy of each submittal transmittal
sheet for shop drawings, product data and samples at the time of submittal of said
drawings, product data and samples to the ENGINEER.
D-03300-008-B
D = Shop Drawing
03300 = Specification Section for Concrete
008 = The eighth initial submittal under this specification section
B = The second submission (first resubmission) of that particular shop
drawing
F. The review and approval of shop drawings, samples or product data by the
ENGINEER shall not relieve the CONTRACTOR from his responsibility with regard to
the fulfillment of the terms of the Contract. All risks of error and omission are
assumed by the CONTRACTOR and the ENGINEER will have no responsibility
therefor.
G. No portion of the work requiring a shop drawing, sample, or product data shall be
started nor shall any materials be fabricated or installed prior to the approval or
qualified approval of such item. Fabrication performed, materials purchased or
on-site construction accomplished which does not conform to approved shop
drawings and data shall be at the CONTRACTOR's risk. The OWNER will not be
liable for any expense or delay due to corrections or remedies required to accomplish
conformity.
H. Project work, materials, fabrication, and installation shall conform with approved shop
drawings, applicable samples, and product data.
A. The review of shop drawings, data, and samples will be for general conformance with
the design concept and Contract Documents. They shall not be construed:
B. The CONTRACTOR remains responsible for details and accuracy, for coordinating
the work with all other associated work and trades, for selecting fabrication
processes, for techniques of assembly, and for performing work in a safe manner.
C. If the shop drawings, data or samples as submitted describe variations and show a
departure from the Contract requirements which ENGINEER finds to be in the interest
of the OWNER and to be so minor as not to involve a change in Contract Price or time
for performance, the ENGINEER may return the reviewed drawings without noting an
exception.
D. Submittals will be returned to the CONTRACTOR under one of the following codes.
Code 5 - "NOT APPROVED" is assigned when the submittal does not meet
the intent of the Contract Documents. The CONTRACTOR must
resubmit the entire package revised to bring the submittal into
conformance. It may be necessary to resubmit using a different
manufacturer/vendor to meet the Contract Documents.
Codes 1 through 5 designate the status of the reviewed submittal with Code 6
showing there has been an attachment of additional data.
F. Partial submittals may not be reviewed. The ENGINEER will be the only judge as to
the completeness of a submittal. Submittals not complete will be returned to the
CONTRACTOR, and will be considered "Not Approved" until resubmitted. The
ENGINEER may at his option provide a list or mark the submittal directing the
CONTRACTOR to the areas that are incomplete.
G. Repetitive Review - Shop drawings and other submittals will be reviewed no more
than two times at the OWNER's expense. All subsequent reviews will be performed
at times convenient to the ENGINEER and at the CONTRACTOR's expense, based
on the ENGINEER's then prevailing rates. The CONTRACTOR shall reimburse the
OWNER for all such fees invoiced to the OWNER by the ENGINEER. Submittals are
required until approved.
J. Only the ENGINEER will utilize the color "red" in marking submittals.
K. Before final payment is made, the CONTRACTOR shall furnish to ENGINEER two (2)
sets of record shop drawings.
1.06 DISTRIBUTION
A. Mock Up units as specified in individual sections, include but are not necessarily
limited to, complete units of the standard of acceptance for that type of work to be
used on the Project. Remove at the completion of the work or when directed.
END OF SECTION
SECTION 01310
CONSTRUCTION SCHEDULES
PART 1 GENERAL
1.01 SUBMITTALS
A. Information Submittals:
1. Preliminary Progress Schedule: Submit within two weeks after award of the
Contract.
2. Detailed Progress Schedule:
A. Submit a detailed schedule, beginning with Notice to Proceed, for minimum duration
of 90 days, and a summary of balance of Project through Final Completion.
1. Notice to Proceed.
2. Permits.
3. Submittals, with review time. CONTRACTOR may use schedule of Shop
Drawings and Sample specified in Section 01300, Submittals.
4. Early procurement activities for long lead equipment and materials.
5. Specified work sequences and performance constraints including anticipated
shutdowns
6. Contract Milestone and Completion Dates.
7. Systems startup summary.
8. Project closeout summary.
9. Demobilization summary.
A. Submit Detailed Progress Schedule beginning with Notice to Proceed and continuing
through Final Completion.
B. Show the duration and sequences of activities required for complete performance of
the work reflecting means and methods chosen by CONTRACTOR.
C. Detailed Progress Schedule will be cost loaded to facilitate progress payments. Cost
loading will reflect cash flows and the Schedule of Values with the sum of all tasks
equal to the Contract total.
F. Update monthly to reflect actual progress and occurrences to date, including weather
delays.
B. Contents:
1. Schedule shall begin with the date of Notice to Proceed and conclude with the
date of Final Completion.
2. Identify work calendar basis using days as a unit of measure.
3. Show complete interdependence and sequence of Project-related activities
reasonably required to complete the work.
4. Identify the work of separate stages and other logically grouped activities, and
clearly identify critical path activities.
5. Reflect sequences of the work, restraints, delivery windows, review times,
Contract Times and Project Milestones set forth in the Agreement and Section
01014, Construction Sequencing.
6. Include applicable, at a minimum:
1. Plot or print on paper not greater than 30 inches by 42 inches or smaller than 22
inches by 34 inches, unless otherwise approved.
2. Title Block: Show name of Project, OWNER, date submitted, revision or update
number, and the name of the scheduler. Update schedules shall indicate the
current data date.
3. Identify horizontally across top of schedule the time frame by year, month, and
day.
4. Identify each activity with a unique number and a brief description of the Work
associated with that activity.
5. Indicate the critical path.
6. Show, at a minimum, the controlling relationships between activities.
7. Plot activities on a time-scale basis, with the length of each activity proportional to
the current estimate of the duration.
8. Plot activities on an early start basis unless otherwise requested by ENGINEER.
9. Plot to include current Early Bars as well as Target/Baseline bars.
10. Provide a legend to describe standard and special symbols used.
D. Schedule Report:
Sort reports, in ascending order: Activity number sequence with predecessor and successor
activity.
A. Format:
B. Contents:
1. Number of days worked over the period, work force on hand, major equipment on
hand
2. General progress of work, including a listing of activities started and completed
Town of Davie 01310-4 Construction Schedules
over the reporting period, mobilization/demobilization of subcontractors, and
major milestones achieved.
3. CONTRACTOR’s plan for management of site (e.g. lay down and staging areas,
construction traffic), utilization of construction equipment, buildup of trade labor,
and identification of potential Contract changes.
4. Identification of new activities and sequences as a result of executed Contract
changes.
5. Documentation of weather conditions over the reporting period, and any resulting
impacts to the work.
6. Description of actual or potential delays, including related causes, and the steps
taken or anticipated to mitigate their impact.
7. In the case that actual or potential delays have been identified, the Narrative
Progress report should be accompanied by a proposed work around schedule to
mitigate potential and or actual delays.
8. Changes to activity logic.
9. Changes to the critical path.
10. Identification of, and accompanying reason for, any activities added or deleted
since the last report.
11. Steps taken to recover the schedule from CONTRACTOR-caused delays.
D. Narrative Report: All changes to activity duration and sequences, including addition or
deletion of activities subsequent to ENGINEER’s acceptance of Baseline Progress
Schedule, shall be delineated in Narrative Report current with proposed Updated
Progress Schedule.
C. Float:
END OF SECTION
Town of Davie 01310-6 Construction Schedules
SECTION 01370
SCHEDULE OF VALUES
PART 1 GENERAL
B. Upon request of the ENGINEER, support the values with data which will substantiate
their correctness.
C. The accepted Schedule of Values shall be used only as the basis for the
CONTRACTOR’s Applications for Payment.
A. General Conditions.
B. Schedule shall list the installed value of the component parts of the work in sufficient
detail to serve as a basis for computing values for progress payments during
construction.
C. Identify each line item with the number and title of the respective major section of the
specification.
D. For each major line item list sub-values of major products or operations under the
item.
1. The cost of the materials, delivered and unloaded, with taxes paid. Paid invoices
are required for materials upon request by the ENGINEER.
2. The total installed value.
F. The sum of all values listed in the schedule shall equal the total Contract Sum.
Town of Davie 01370-1 Schedule of Values
1.04 SUBSCHEDULE OF UNIT MATERIAL VALUES
B. The form of submittal shall parallel that of the Schedule of Values, with each item
identified the same as the line item in the Schedule of Values.
C. The Unit quantity for bulk materials shall include an allowance for normal waste.
D. The unit values for the materials shall be broken down into:
1. Cost of the material, delivered and unloaded at the site, with taxes paid.
2. Copies of invoices for component material shall be included with the payment
request in which the material first appears.
3. Paid invoiced shall be provided with the second payment request in which the
material appears or no payment shall be allowed and/or may be deleted from the
request.
E. The installed unit value multiplied by the quantity listed shall equal the cost of that
item in the Schedule of Values.
END OF SECTION
CONTROL OF WORK
PART 1 GENERAL
1.01 PLANT
A. The CONTRACTOR shall furnish personnel and equipment which will be efficient,
appropriate and sized to secure a satisfactory quality of work and a rate of progress
which will ensure the completion of the work within the Contract Times. If at any time
such personnel appear to the ENGINEER to be inefficient, inappropriate or insufficient
for securing the quality of work required for producing the rate of progress aforesaid, he
may order the CONTRACTOR to increase the efficiency, change the character or
increase the personnel and equipment, and the CONTRACTOR shall conform to such
order. Failure of the ENGINEER to give such order shall in no way relieve the
CONTRACTOR of his obligations to secure the quality of the work and rate of progress
required.
PART 3 EXECUTION
A. All firms or persons authorized to perform any work under this Contract shall cooperate
with the CONTRACTOR and his subcontractors or trades, and shall assist in
incorporating the work of other trades where necessary or required.
B. Cutting and patching, drilling and fitting shall be carried out where required by the trade
or subcontractor having jurisdiction, unless otherwise indicated herein or directed by the
ENGINEER.
A. All newly constructed work shall be carefully protected from injury in any way. All
portions injured shall be reconstructed by the CONTRACTOR at his own expense.
B. All structures and facilities shall be protected in a manner approved by the ENGINEER.
All damaged portions of the work shall be completely repaired and made good by the
CONTRACTOR at his own expense and to the satisfaction of the ENGINEER. If, in the
final inspection of the work, any defects, faults or omissions are found, the
CONTRACTOR shall cause the same to be repaired or removed and replaced by proper
materials and workmanship without extra compensation for the materials and labor
required. Further, the CONTRACTOR shall be fully responsible for the satisfactory
maintenance and repair of the construction and other work undertaken herein, for at
least the guarantee period described in the Contract.
END OF SECTION
PLANT START-UP
PART 1 GENERAL
1.01 GENERAL
A. Following completion of the specified modifications, the CONTRACTOR shall test the
system for leaks and for proper operation. The CONTRACTOR shall be responsible
for disinfecting the systems following satisfactory testing, membrane element
cleaning, and then assisting the OWNER with start-up of the membrane unit. Each
unit will be tested for leaks and proper operation of the equipment and materials
installed by the CONTRACTOR.
C. All equipment shall be tested, as specified in Divisions 13 and 15, and approved by
the OWNER prior to placing the facilities into operation.
D. All lubricants, fuel and power necessary for initial operation and tests shall be
furnished by the CONTRACTOR.
F. Comply with Federal, State, and Local Codes and regulations and utility company
requirements.
PART 3 EXECUTION
A. General Requirements:
B. Submit Start-up plans to the ENGINEER indicating start-up preparation for valves and
equipment components, and the initial mode of operation for each system.
A. Field tests shall be made to confirm compliance with the contract and to establish
compliance with the technical provision. The test shall be performed by the
CONTRACTOR as herein specified. All water lines, piping, and equipment shall be
tested in the field in the presence of the ENGINEER, in the manner prescribed in the
Sections of these Specifications pertaining to such installation.
3. The point of application of the chlorinating agent shall be at the beginning of the
system and through a nozzle or other convenient location in the newly installed
pipe. The water injector for delivering the chlorine-bearing water into the pipe
may be supplied from a tap on the pressure side of the gate valve controlling the
flow into the pipeline.
4. Water from the existing system or other source of supply shall be controlled so as
to flow slowly into the newly installed pipes during the application of chlorine.
The CONTRACTOR shall not allow the chlorine solution in the line being treated
to flow back into the line supplying the water.
5. Treated water shall be retained in the line at least 24 hours. After the chlorine
treated water has been retained for the required time, the chlorine residual in the
line shall be at least 50 mg/l. Should the initial procedure fail to result in the
conditions specified, the chlorination procedure shall be repeated until results are
obtained, at the CONTRACTOR's expense.
6. The CONTRACTOR shall tap the lines at points designated by the ENGINEER
and provide necessary piping to discharge water from the line.
7. Following chlorination, all treated water shall be thoroughly flushed from the line.
8. Water for first flushing will be provided by the OWNER; subsequent flushing will
be at the expense of the CONTRACTOR. The CONTRACTOR should
coordinate the development of the supply with the pipeline work in order that
A. After all component pieces of equipment have been successfully checked and started,
a functional start-up test will be required for all process equipment.
1. Provide 14 days written notice indicating the date and time during which the
functional test is proposed. Submit with this notice the following for the
ENGINEER’s review and approval:
a. Description of the tests specifically outlining how the test will conform to the
requirements of the technical specifications.
b. Testing devices that will be used in the tests: Description must state what
portion of the tests that the device will perform or measure and device
accuracy.
d. Provide material and equipment required for the test. Water and power will
be supplied by the OWNER for functional testing purposes only.
f. Provide 10 days written notice to the ENGINEER prior to the actual start of
any testing. This will include a statement by the CONTRACTOR that the
equipment and facilities to be tested have been thoroughly inspected and
cleaned of construction debris and other extraneous materials and all
lubrication, materials and preparations are complete.
2. The ENGINEER and OWNER may witness these tests, at their option.
3. A written summary of testing, reporting on the results and summarizing the entire
procedure, shall be submitted to ENGINEER upon completion of the test. A
schedule for retesting, if necessary, including changes to procedures, testing
4. Submit within one week after completion of the tests, the following to the
ENGINEER for approval:
a. Completed test forms for each device or system tested on forms approved
prior to the test.
b. Completed certification, the content of which was approved prior to the tests.
A. CONTRACTOR shall correct any items of work failing to meet the specified
requirements at no to the OWNER. Correct the nonconforming items by rework,
modification or replacement as directed by the ENGINEER. All corrected items shall
be retested at no additional cost.
Client:
Project:
I (we) the undersigned, authorized representatives of the and/or Plant Operating Personnel
have received classroom and hands on instruction on the operation, lubrication, and
maintenance of the subject equipment and prepared to assume normal operational
responsibility for the equipment:
__________________________________________DATE: ________________________
__________________________________________DATE: _________________________
__________________________________________DATE: _________________________
____________________________________________ DATE:
(Signature of OWNER’s Authorized Representative)
END OF SECTION
CONTRACT CLOSEOUT
PART 1 GENERAL
A. Comply with requirements stated in the General Conditions of the Contract and in
Specifications for administrative procedures in closing out the work.
A. When the CONTRACTOR considers the work substantially complete, he shall submit
to the ENGINEER a written notice that the work is substantially complete.
B. Within a reasonable time after receipt of such notice, the ENGINEER will make an
inspection to determine the status of completion.
C. Should the ENGINEER determine that the work is not substantially complete:
1. The ENGINEER will promptly notify the CONTRACTOR in writing, giving the
reasons thereof.
2. CONTRACTOR shall remedy the deficiencies in the Work and send a second
written notice of substantial completion to the ENGINEER.
3. The ENGINEER will re-inspect the work.
D. When the ENGINEER finds that the work is substantially complete, he will:
B. The ENGINEER will make an inspection to verify the status of completion with
reasonable promptness after receipt of such certification.
C. Should the ENGINEER consider that the work is incomplete or defective:
D. When the ENGINEER finds that the work is acceptable under the Contract
Documents, he shall request the CONTRACTOR to complete any remaining closeout
submittals.
A. Should the ENGINEER perform re-inspections due to failure of the Work to comply
with the claims of status of completion made by the CONTRACTOR:
1. OWNER will compensate the ENGINEER for such additional services.
2. OWNER will deduct the amount of such compensation from the final payment to
the CONTRACTOR.
B. All operation, maintenance, and warranty information specified in Section 01741 and
elsewhere in the Contract Documents
C. Consent of Surety.
C. ENGINEER will prepare a final Change Order, reflecting approved adjustments to the
Contract Sum which were not previously made by Change Orders.
A. CONTRACTOR shall submit the final Application for Payment in accordance with
procedures and requirements stated in the Contract for Construction.
END OF SECTION
PART 1 GENERAL
A. The scope of work under this contract includes, but is not limited to, the
following general activities:
1. Development and submittal for approval of a written cleaning protocol for
the four reverse osmosis (RO) membrane units using the Owner’s clean-
in-place system and associated equipment.
2. Procurement and delivery of all cleaning chemicals, materials, and
equipment.
3. Preparation of the clean-in-place system and RO membrane units for
cleaning of the membrane elements.
4. Providing all labor, tools, and equipment to prepare cleaning solutions and
clean each RO membrane unit in accordance with these specifications,
recommendations and instructions of the membrane element
manufacturer, and the clean-in-place system operating and maintenance
manual.
5. Flushing each unit following cleaning, including disposal of spent cleaning
solution(s) during and after each cleaning cycle.
6. Preparing each membrane unit to be placed back on line, including leak
testing of the unit.
7. Assisting the Owner in placing the membrane unit back on line, in normal
operation.
8. Assisting the Owner in evaluating the effectiveness of the cleaning
according to industry-standard practices and the membrane element
manufacturer’s recommendations. In this regard the Contractor shall
collect sufficient plant normalization data from the Owner to establish
baseline performance of each RO unit prior to the start of cleaning
operations. The Contractor shall also review normalization data provided
by the Owner for up to 10 days after completion of the membrane cleaning
services. The Contractor shall evaluate and document the improvement
in normalized specific flux, salt passage, and differential pressure per
stage for each stage of all four RO units to demonstrate the improvement
in RO system performance after cleaning.
9. The Contractor shall provide the resume of the Membrane Cleaning
Supervisor who will be responsible for the membrane cleaning system
1.02 SUBMITTALS
A. After award of contract during shop drawing submittals, submit the following:
PART 1 GENERAL
A. The Work in general consists furnishing and installing piping and valving
modifications to the membrane cleaning system and the cleaning piping on the four
reverse osmosis membrane units, as shown on the Drawings and specified herein
and preparing the membrane units for cleaning of the elements.
B. Furnish all materials, labor, equipment and incidentals required for completing the
pipe, fittings, valves, and accessory modifications, as shown on the Drawings.
C. There are four (4) RO membrane units each containing 58 pressure vessels with 7
membrane elements in each vessel for a total of 406 elements per unit.
D. Work scheduling and coordination with the OWNER and operations staff.
E. Mobilization/demobilization.
F. Receiving, storing, and handling of the pipe, valves, fittings, and accessories for
the proposed modifications.
G. Cleaning and disinfection of the new piping and equipment after installation.
I. Supply and installation of specified parts that require replacement during the Work.
K. Correction of any defects associated with the installation, including all leaks
resulting from work on the existing systems.
L. The Work shall be scheduled and staged so that no more than one membrane unit
will be out of service at any given time.
A. The OWNER intends to modify the cleaning piping on its four existing RO
membrane units.
B. The configuration and major design features of the RO units are depicted on the
Drawings and in the record and shop drawings included in the Technical Data.
C. The existing membrane system is free from bacteriological contamination, and the
proposed modifications must not introduce bacterial contamination into the
membranes or membrane system.
1.04 SUBMITTALS
B. Submittals for the membrane replacement shall include at least the following:
PART 2 PRODUCTS
A. All materials shall conform to the material specifications provided on the Drawings.
PART 3 EXECUTION
C. Disinfection and Flushing: Following installation of new piping, the piping shall
be disinfected with chlorine solution. All spillage shall be cleaned up immediately
to prevent damage and corrosion to adjacent equipment.
A. The CONTRACTOR, prior to requesting final payment, shall obtain and submit the
following items to the ENGINEER for transmittal to the OWNER:
2. Releases from all parties who are entitled to claims against the subject project
pursuant to the provisions of law.
END OF SECTION