Professional Documents
Culture Documents
Building Building Construction Construct
Building Building Construction Construct
CONSTRUCTION
l
PREPARATION FOR CONSTRUCTION
Preparation for
Construction 1.0
• The height of the batter boards may be level with or a little higher that the top
of the finished foundation.
Preparation for
Construction 1.0
Adjustable
Metal Shores
Braced T-
and L-heads Bracing
Single Post
Wood Shore
Sills
Preparation for
Construction 1.0
COLUMN FORMS
Staking-Out the Building WOOD FORMWORKS
Laying the Batterboards
Reusable forms may have a
Formwork & Shoring 1.3
Construction Tools & square or rectangular cross
Equipment section
Foundation Bed
Site Investigation YOKES are clamping devices
Excavation & Earthworking
Slope Protection and
for keeping column forms and
Retaining Structures tops of wall forms from
spreading under the fluid
pressure of newly placed
concrete
WALL FORMS
SPREADERS usually of wood,
space and keep the wall or
forms apart
FORM TIES
PLYWOOD SHEATHING
HORIZONTAL WALERS
WOOD STUDS
SILL PLATE
BRACING
Preparation for
Construction 1.0
Ledgers
Adjustable
Braces
Fixed Braces
Preparation for
Construction 1.0
4. Position scaffold boards and ladders. 5. Additional ledgers and braces 6. Once all levels are complete,
can now be added, with additional jacks and heads can now be
braces. positioned.
7. Jack head levels finalized and any jack 8. Primary beams can be 9. Secondary beams can be
bracing required is now fitted. positioned, clamped and levels positioned and clamped to primary
checked. beams, plywood decking to follow.
Preparation for
Construction 1.0
b. Powder-actuated
b. Rotary hammer is like an electric
stud driver is a kind
drill that operates with both rotating
of nailer that is
and reciprocating actions and is used
powered by
to drill holes in concrete.
gunpowder and is
used to drive long
Powder-actuated
pins into wood, steel stud driver.
or concrete.
b. Surveyor’s level is
that which is used to
determine an
unidentified elevation
from a known one.
Surveyors level.
Bulldozer.
Front-end loader.
Preparation for
Construction 1.0
Highway construction equipment
Staking-Out the Building are:
Laying the Batterboards
Formwork & Shoring
Construction Tools &
1.4 a. Scraper is a machine that loads,
Equipment
Foundation Bed hauls and dumps soil over medium
Site Investigation to long distances.
Excavation & Earthworking Scraper.
Slope Protection and
Retaining Structures b. Grader is an earthworking
machine that grades or levels the
ground.
2. Decayed rock (rotten rock). Sand, clays and other materials resulting from the
disintegration of rock masses, lacking the coherent qualities but occupying the
space formerly occupied by the original rock.
3. Loose rock. Rock masses detached from the ledge of which they originally
formed a part.
5. Boulders. Detached rock masses larger than gravel, generally rounded and
worn as a result of having been transported by water a considerable distance
from the ledges of which they originally formed a part.
Preparation for
Construction 1.0
6. Sand. Non-coherent rock particles smaller than ¼” in maximum dimension.
Staking-Out the Building
Laying the Batterboards
Formwork & Shoring 7. Clay. A plastic material resulting from the decomposition and hydration of
Construction Tools & feldspathic rocks, being hydrated silicate of alumina, generally mixed with
Equipment
Foundation Bed 1.5 powdered feldspar, quartz and other materials.
Site Investigation
Excavation & Earthworking
Slope Protection and 8. Hard-pan. Any strong coherent mixture of clay or other cementing material
Retaining Structures with sand, gravel and boulders.
10. Mud. Finely divided earthy material generally containing vegetable matter
and deposited from still or slowly moving water.
14. Filled Ground. All artificial fills and some natural fills are liable to a more or
less uniform but continuous settlement or shrinkage due to the gradual
consolidation of the material of which the fill is composed
Preparation for
Construction 1.0
1.5.2 ALLOWABLE LOADS ON FOUNDATION BEDS
Staking-Out the Building
Laying the Batterboards
Formwork & Shoring Because there are variations in the materials and conditions affecting
Construction Tools &
Equipment such materials, thorough investigation is required before one can
Foundation Bed 1.5
Site Investigation
determine the allowable unit load on the foundation bed. In cases
Excavation & Earthworking wherein the material and conditions are uniform over the entire site of
Slope Protection and
Retaining Structures the building, a uniform unit load may be used. In cases wherein entirely
different conditions exist under different portions of the same building,
the unit load on the foundation bed must be reduced as much as
possible so as to reduce the differences in settlements between the two
sections of the building to a minimum.
Preparation for
Construction 1.0
DEWATERING
EXISTING
WATER TABLE
WATER TABLE
AFTER PUMPING
Preparation for
Construction 1.0
0.5 H
C2
Preparation for
Construction 1.0
b) T-type Cantilevered Retaining Wall – limited to a height of 20’
Staking-Out the Building
Laying the Batterboards (6 M); beyond this height a counterfort wall is employed.
Formwork & Shoring
Construction Tools &
8” (205)
Equipment Batter refers to backward
Foundation Bed sloping face of a wall as it
Site Investigation
Excavation & Earthworking
rises to offset illusion of face
Slope Protection and leaning forward
Retaining Structures 1.8
Temperature steel for walls
more than 10” (255) thick
Drainage mat w/ filter fabric
0.6H or porous gravel backfill
(0.9H w/ surcharge)
2” (51 mm) o weepholes @
4’-6’ (1220-1830mm) o.c. or
perforated drainpipe sloped
to outlet away from wall
2” (51) min
3” (75) min
Structural Steel
reinforcement
0.7H
(1.25 w/ surcharge)
0.6H
(1.0 w/ surcharge)
END